DOE O 415.1, Information Technology Project Management
Functional areas: Information Technology
The Order provides program and project management direction for the acquisition and management of IT projects, investments, and initiatives. Cancels DOE G 200.1-1. Admin Chg 1 approved 1-16-2013.
Supersedes:
DOE G 200.1-1 Ch 7, Programming Stage on Dec 03, 2012
DOE G 200.1-1 Ch 6, System Design Stage on Dec 03, 2012
DOE G 200.1-1 Ch 10, Software Maintenance on Dec 03, 2012
DOE G 200.1-1 App E, Appendix E Stage Exit Process Guide on Dec 03, 2012
DOE G 200.1-1 App A, Appendix A Glossary on Dec 03, 2012
DOE G 200.1-1 Ch 4, Requirements Definition Stage on Dec 03, 2012
DOE G 200.1-1 App B, List of Abbreviations on Dec 03, 2012
DOE G 200.1-1 Ch 8, Software Integration and Testing Stage on Dec 03, 2012
DOE G 200.1-1 Ch 1, Introduction on Dec 03, 2012
DOE G 200.1-1 Ch 5, Functional Design Stage on Dec 03, 2012
DOE G 200.1-1 Ch 9, Installation and Acceptance Stage on Dec 03, 2012
DOE G 200.1-1 Ch 2, Lifecycle Model on Dec 03, 2012
DOE G 200.1-1, Software Engineering Methodology TOC on Dec 03, 2012
DOE G 200.1-1 Ch 3, Planning Stage on Dec 03, 2012
Superseded By:
Version history and related documents
Superseded by
A newer version replaces this document.
Supersedes
Earlier documents this one replaced.
- DOE G 200.1-1 Ch 7Programming Stage (Dec 03, 2012)
- DOE G 200.1-1 Ch 6System Design Stage (Dec 03, 2012)
- DOE G 200.1-1 Ch 10Software Maintenance (Dec 03, 2012)
- DOE G 200.1-1 App EAppendix E Stage Exit Process Guide (Dec 03, 2012)
- DOE G 200.1-1 App AAppendix A Glossary (Dec 03, 2012)
- DOE G 200.1-1 Ch 4Requirements Definition Stage (Dec 03, 2012)
- DOE G 200.1-1 App BList of Abbreviations (Dec 03, 2012)
- DOE G 200.1-1 App FAppendix F Computer System Retirement Guidelines (Dec 03, 2012)
- DOE G 200.1-1 App CAppendix C Conducting Structured Walkthroughs (Dec 03, 2012)
- DOE G 200.1-1 Ch 8Software Integration and Testing Stage (Dec 03, 2012)
- DOE G 200.1-1 App DAppendix D In-Stage Assessment Process Guide (Dec 03, 2012)
- DOE G 200.1-1 Ch 1Introduction (Dec 03, 2012)
- DOE G 200.1-1 Ch 5Functional Design Stage (Dec 03, 2012)
- DOE G 200.1-1 Ch 9Installation and Acceptance Stage (Dec 03, 2012)
- DOE G 200.1-1 Ch 2Lifecycle Model (Dec 03, 2012)
- DOE G 200.1-1Software Engineering Methodology TOC (Dec 03, 2012)
- DOE G 200.1-1 Ch 3Planning Stage (Dec 03, 2012)
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
AVAILABLE ONLINE AT: INITIATED BY:
www.directives.doe.gov Office of the Chief Information Officer
U.S. Department of Energy ORDER
Washington, D.C.
Approved: 12-3-2012
SUBJECT: INFORMATION TECHNOLOGY PROJECT MANAGEMENT
1. PURPOSE. To provide the Department of Energy (DOE) Elements, including the
National Nuclear Security Administration (NNSA), with Information Technology (IT)
Project Management guidance for the acquisition and management of IT projects and
initiatives. Common IT Project Management requirements will ensure that IT projects are
delivered within the original performance baseline, cost, and schedule and fully meet
Mission performance, safety, safeguards, and security standards in alignment with section
5123 of Public Law (P.L.) 104-106, Performance and Results Based Management.
a. To responsibly manage IT projects that will improve the efficiency and
effectiveness of DOE operations and, as appropriate, the delivery of services to
the public;
b. To establish communications within the Office of the Chief Information Officer
(OCIO) and across all DOE Elements for DOE Enterprise-wide IT projects;
c. To align decision making within the OCIO and across all DOE Elements for
Department–wide IT projects; and
d. To reduce duplication of effort and the Total Cost of Ownership (TCO) for DOE
IT projects.
2. CANCELLATION. DOE Guide (G) 200.1-1, Software Engineering Methodology Guide,
dated 5-21-97.
3. DEPARTMENTAL APPLICABILITY.
a. Scope. Except for the exclusions in section 3b and equivalencies and exemptions
in section 3d, the scope of IT projects covered by this Order (O) includes projects:
(1) With a Total Project Cost (TPC) equal to or more than $25 Million (M);
(2) With an impact on more than one DOE Element; or
(3) As determined by the Undersecretary or Head of Element, based on risk
management, Mission, priorities, or National interest.
b. Exclusion. IT projects that are covered by or are a component under a Capital
Asset Project covered by DOE O 413.3B, Program and Project Management for
the Acquisition of Capital Assets, are excluded from this O 415.1.
c. IT Project Management. All IT projects require formal IT Project Management.
IT projects that do not meet the scope of this Order are required to be managed
DOE O 415.1
2 DOE O 415.1
12-3-2012
using a standardized approach as specified and approved by the
sponsoring/funding Organization.
d. Equivalencies/Exemptions for DOE O 415.1. Equivalencies and exemptions to
this Order are processed in accordance with DOE O 251.1C, Departmental
Directives Program. The following equivalencies and exemptions are included in
this Order.
(1) Exemption. Consistent with Secretarial Delegation DOE O 00-033.00B,
To the Administrator and Chief Executive Office (CEO) of Bonneville
Power Administration (BPA), this Order does not apply to BPA.
(2) Exemption. This Order does not apply to Financial Assistance Awards
(FAA), grants, and cooperative agreements covered under 10 Code of
Federal Regulations (CFR) Part 600, Financial Assistance Rules.
(3) Exemption. An Office of Science User Facility, which is a Federally
sponsored research facility available for external use to advance scientific
or technical knowledge under the conditions defined in the Office of
Science, Definition of a User Facility, dated, January 6, 2012.
Section 2
(4) Equivalency. In accordance with the responsibilities and authorities
assigned by Executive Order (E.O.) 12344, Naval Nuclear Propulsion
Program, codified at 50 United States Code (USC) sections 2406 and
2511 and to ensure consistency through the joint Navy/DOE Naval
Nuclear Propulsion Program (NNPP), the Deputy Administrator for Naval
Reactors will implement and oversee requirements and practices
pertaining to this Order for activities under the Director's cognizance, as
deemed appropriate.
(5) Equivalency. DOE Elements that meet all of the following criteria may
demonstrate alignment with specific requirements of this Order. The intent
of this equivalency is to delegate authority to the DOE Elements with the
following:
(a) Established IT Project Management Offices (IT PMO) with
documented and approved Project Management requirements,
processes, and procedures.
(b) Established IT governance policies and procedures that are
consistently used throughout the DOE Element with demonstrated
success.
(c) Demonstrated record of completing IT projects where completed
projects:
DOE O 415.1 3
12-3-2012
1 Do not exceed a cost variance of more than +/- 10% of the
stated cost baseline established for the original, approved
scope of work approved as part of the Detailed Design
Review (DDR);
2 Do not exceed a project schedule variance of more than
+/- 10% of the stated schedule baseline established for the
original approved scope of work as part of the DDR; and
3 Meet the functionality requirements documented in the stated
approved scope of work as part of the DDR.
(d) Requirement that DOE Elements having this equivalency are still
responsible for reporting and coordinating projects that impact
multiple DOE Elements.
(6) DOE Elements that are eligible for the equivalency must take affirmative
action and obtain confirmation of the equivalency with an action
memorandum from the OCIO or designated authority.
(7) The Administrator, NNSA, will ensure that NNSA employees and
contractors comply with their respective responsibilities under this Order.
Nothing in this Order will be construed to interfere with the NNSA
Administrator’s authority under section 3212(d) of P.L. 106-65, National
Defense Authorization Act for Fiscal Year 2000, to establish
Administration-specific policies, unless disapproved by the Secretary.
(8) For DOE contractors, except for the equivalencies and exemptions in
section 3d and as stated above, the Contractor Requirements Document
(CRD), see Attachment 1, sets forth requirements of this Order that will
apply to contracts that include the CRD. The CRD must be included in IT
Program/Project Management and services contracts. As the laws,
regulations, and the DOE Directive clause 970.5204-2 of IT Project
Management and services contracts state, regardless of the performer of
the work, Site/Facility management contractors with the CRD in
Attachment 1 incorporated into their contracts are responsible for
compliance with the requirements of the CRD.
4. REQUIREMENTS.
a. Successful management of IT projects requires the application of knowledge,
skills, tools, techniques, and resources to ensure that the IT system or asset meets
or exceeds the stakeholders’ needs and expectations. To deliver IT investments,
assets, and projects on the stated performance baseline (including within budget,
on schedule, and fully capable of meeting Mission performance, safety,
safeguards, and security standards) and to ensure the implementation of this
Section 3
4 DOE O 415.1
12-3-2012
Order, the following project artifacts must be developed and maintained by each
DOE Element responsible for IT projects.
(1) A Project Management Plan (PMP) that includes:
(a) Budget and resources;
(b) Key decision points; and
(c) Description of the Project Management tools and reports that will
be used during the project.
(2) Alternative Analysis.
(3) Requirements Document approved by the Project Manager (PM) and the
customer that outlines functional, operational, and acceptance criteria.
(4) Project Schedule documenting the entire lifecycle of the project.
(5) Configuration Management and Change Control Plan.
(6) Risk Management Plan.
(7) Cyber Security Plan.
b. Implementation of IT Project Management methodologies, tools, and techniques
that:
(1) Establish the project scope, schedule, and budget;
(2) Hold the PM accountable for delivering the project within cost, scope, and
schedule;
(3) Align the IT investment to the Departmental and/or Organizational
Strategic Plan and objectives;
(4) Establish clearly defined metrics and business value based objectives;
(5) Are consistent with the appropriate statutory, regulatory, Office of
Management and Budget (OMB), and Departmental requirements;
(6) Ensure the products or services are produced according to requirements
and specifications, on time, and within budget;
(7) Ensure reporting to the Acquisition Executive (AE), IT Project Manager
(IT PM), and DOE Element’s leadership, as appropriate, on project
performance and status;
DOE O 415.1 5 (and 6)
12-3-2012
(8) Strengthen line management accountability for successful IT Project
Management results;
(9) Implement formal Stage Gates or transition points during the project’s life
cycle to validate that the project is proceeding as planned and a go, no-go,
or hold decision is made;
(10) Establish a DOE Enterprise culture that recognizes the need to manage
risk, control cost and schedules, and invest in DOE Enterprise-wide
projects with the goal of meeting DOE Mission schedules. Invest in DOE
Enterprise-wide IT projects with the goal of meeting DOE Mission
objectives on budget, on schedule, and with the functionality required; and
(11) Tailor projects, as appropriate.
c. Establishment of an IT asset/project inventory.
d. Requirements for Implementation. Implementation of the requirements contained
in this Order must be documented in an Implementation Plan within 6 months of
the issuance of this Order. The Implementation Plan must ensure that this Order is
fully implemented within 1 year. IT projects initiated prior to the issuance of this
Order may continue to adhere to the management and reporting requirements
established for the project, and the IT PMs of these projects must coordinate with
the DOE Corporate IT PMO on reporting and monitoring.
5. RESPONSIBILITIES. See Responsibilities, Appendix A.
6. REFERENCES. See References, Attachment 3.
Additional References:
a. Acronyms, Attachment 2
b. Glossary of Terms, Attachment 4
7. CONTACT. For assistance, contact the Office of the Chief Information Officer,
202-586-0166.
BY ORDER OF THE SECRETARY OF ENERGY:
DANIEL B. PONEMAN
Deputy Secretary
DOE O 415.1 i (and ii)
12-3-2012
TABLE OF CONTENTS
APPENDIX A: RESPONSIBILITIES
1. NATIONAL NUCLEAR SECURITY ADMINISTRATION (NNSA). ................................. 1
2. DOE CHIEF INFORMATION OFFICER (CIO). .................................................................. 1
Section 4
3. DOE CORPORATE IT PROJECT MANAGEMENT OFFICE (PMO)................................. 2
4. DOE UNDER SECRETARIES, NNSA ADMINISTRATOR/HEADS OF FIELD
ELEMENTS. ........................................................................................................................... 2
5. PROGRAM MANAGERS AND HEADS OF FIELD ORGANIZATIONS. ......................... 3
6. CONTRACTING OFFICER (CO). ......................................................................................... 4
7. DOE CHIEF ARCHITECT (SEE DOE O 200.1A). ............................................................... 4
8. CHIEF HEALTH, SAFETY AND SECURITY OFFICER. ................................................... 4
9. ACQUISITION EXECUTIVE (AE). ...................................................................................... 4
DOE ORDER 415.1 - LIST OF ATTACHMENTS:
Attachment 1: CONTRACTOR REQUIREMENTS DOCUMENT
Attachment 2: ACRONYMS
Attachment 3: REFERENCES
Attachment 4: GLOSSARY OF TERMS
DOE O 415.1 Appendix A
12-3-2012 A-1
APPENDIX A
RESPONSIBILITIES
1. NATIONAL NUCLEAR SECURITY ADMINISTRATION (NNSA).
For all actions on NNSA Information Technology (IT) Programs, projects, and
investments, the Administrator, NNSA, maintains responsibility and has the authority to
delegate responsibilities and authority for implementing the relevant requirements and
responsibilities of this Order (O). This includes, but is not limited to, designating Project
Managers (PMs), establishing Nuclear Security Enterprise-wide IT-related metrics,
delegating decision-making authority relating to NNSA IT project execution, providing
oversight on NNSA IT projects, and implementing corrective actions.
2. DOE CHIEF INFORMATION OFFICER (CIO).
a. Serve as the Department of Energy (DOE) Senior Manager responsible and
accountable for implementing the provisions of the DOE Secretary
Delegation O No. 00-031.00A, To the Chief Information Officer, which delegates
to the CIO the responsibility of oversight and reporting on IT projects across the
DOE Enterprise in a collaborative manner that:
(1) Reinforces and enhances guidance on formalized IT Project Management
to meet the DOE expectation that IT projects are effectively managed,
meeting business needs and providing transparency through reporting in a
timely manner; and
(2) Acknowledges the autonomy and authority of DOE Elements and fosters a
core competency for supporting DOE Enterprise-wide IT initiatives.
b. Mature DOE IT project planning, coordination, and cooperation in an effort to
improve the efficiency and effectiveness of IT across all DOE Elements.
c. Oversee the development and implementation of IT project policies, standards,
and guidelines that align with the DOE Mission, as well as legislative and
regulatory policies and procedures.
d. Identify special interest projects and ensure that appropriate Senior Executive
Level reviews are provided for those projects.
e. Establish and maintain a DOE-wide process for certifying IT PMs.
f. Affirm equivalencies as defined in DOE O 415.1.
g. Promote Enterprise Architecture (EA) as defined in DOE O 200.1A, Information
Technology Management.
h. Promote Information Technology Strategic Planning.
Appendix A DOE O 415.1
A-2 12-3-2012
i. Identify critical DOE IT investments and ensure that they are tracked in the
Strategic Plan.
(1) Review the results of internal and external compliance assessments and
provide transparency across the Agency;
Section 5
(2) Ensure that IT assets are acquired and information resources are managed
consistent with statutory, Office of Management and Budget (OMB), and
Departmental requirements and priorities; and
(3) Ensure the development and management of an optimal IT portfolio that
best supports Programmatic needs.
j. Promote Capital Planning and Investment Control (CPIC) as defined in
DOE O 200.1A.
(1) Ensure the integration and alignment of the CPIC process and tools with
IT Project Management, EA, and other management processes; and
(2) Provide a means for Senior Management to monitor IT investments in
terms of cost, schedule, and requirements.
3. DOE CORPORATE IT PROJECT MANAGEMENT OFFICE (PMO).
a. Support the development, implementation, and maintenance of policies,
templates, and procedures necessary to implement this Order.
(1) Collect, analyze, and disseminate lessons learned and best practices;
(2) Provide assistance and guidance to DOE line Project Management
Organizations managing IT projects covered by this Order;
(3) Ensure coordination and collaboration within the Office of the Chief
Information Officer (OCIO) Organization, including Capital Planning,
EA, Cybersecurity, and Energy IT Services; and
(4) Implement processes to consolidate and report on IT project status.
b. Ensure coordination and collaboration with DOE Elements on IT Project
Management.
4. DOE UNDER SECRETARIES, NNSA ADMINISTRATOR/HEADS OF FIELD
ELEMENTS.
a. Maintain stewardship of Federal IT resources and ensure they are used
efficiently and effectively to achieve intended program results.
DOE O 415.1 Appendix A
12-3-2012 A-3
(1) Ensure sound application of IT Project Management practices for
planning, management, budgeting, execution review, and reporting that
demonstrates projects are effectively managed;
(2) Ensure that all IT PMs have the appropriate qualifications required based
on the size and complexity of the project to manage successful completion
of the project; and
(3) Ensure projects have established and monitored performance measures
that align with the DOE and Program Mission.
b. Take systematic and proactive measures to establish cost-effective and
appropriate internal controls.
c. Ensure IT Organizations within their control are properly informed of this
Order and identify and report on IT projects governed by this Order, as
required.
d. Ensure Program Offices establish additional process-specific quality
requirements to be implemented under a Quality Assurance Program (QAP)
for the control of suspect/counterfeit items (S/CIs) and nuclear-safety
software, as defined in DOE O 414.1D, Quality Assurance.
e. Notify Contracting Officers (COs) of contracts affected by the requirements of
this Order.
5. PROGRAM MANAGERS AND HEADS OF FIELD ORGANIZATIONS.
a. Direct initial project planning and execution roles for projects assigned by Senior
Management.
b. Establish the initial Integrated Project Team (IPT) in advance of the designation
of an IT PM, when required.
c. Oversee development of project definition, technical scope, and budget to support
Mission need.
d. Assign an IT PM, as appropriate, and PMs with the training, experience, and
skills necessary to meet the requirements of the project objectives, budget, and
schedule.
e. Oversee the project line management Organization, and ensure the line project
teams have the necessary experience, expertise, and training in IT Life Cycle
Management (LCM), including budget and schedule performance management.
Section 6
f. Develop project performance measures, and monitor and evaluate project
performance throughout the project ensuring compliance with DOE standards,
security requirements, and other mandates.
Appendix A DOE O 415.1
A-4 12-3-2012
g. Report the cost, schedule, and performance on a monthly basis for all IT projects
governed by this Order to the OCIO Corporate IT PMO. Steady State (SS)
performance is reported through the CPIC process.
h. Identify and correct all reportable problems including cost, schedule, and scope in
a timely and effective manner.
i. Ensure Site/Facility management, support services, and systems development
contractors are responsible for flowing down the requirements of the Contractor
Requirements Document (CRD) to subcontractors at any tier, to the extent
necessary, to ensure IT Program/Project Management and services contractors’
compliance with the requirements.
j. Manage the tailoring of IT investments.
6. CONTRACTING OFFICER (CO).
Once notified, COs are responsible for incorporating this Order into the affected contracts
via the laws, regulations, and DOE Directives clause of the contracts. Requirements
identified as solely a Federal function will not be incorporated into contracts.
7. DOE CHIEF ARCHITECT (SEE DOE O 200.1A).
Identify opportunities for improving the integration of EA and CPIC processes to
maturity and enhance IT Project Management.
8. CHIEF HEALTH, SAFETY AND SECURITY OFFICER.
Refer to DOE O 414.1D, Quality Assurance, for applicability, as appropriate.
9. ACQUISITION EXECUTIVE (AE).
Each designated AE is guided by the specific limits of their delegated authority (see
DOE/NNSA Senior Procurement Executive for contract award and modification
execution authority). There can only be one designated AE per project.
a. Monitor the effectiveness of IT PMs and their support staff;
b. Approve project changes in compliance with the appropriately defined change
control levels and funding profile changes;
c. Conduct Quarterly Project Reviews (QPRs); and
d. Explicitly address integration of safety into design and construction for Hazard
Category 1, 2, and 3 nuclear facilities as a key consideration in the QPRs and
approval of project Stage Gates.
DOE O 415.1 Attachment 1
12-3-2012 Page 1 (and Page 2)
CONTRACTOR REQUIREMENTS DOCUMENT
DOE ORDER (O) 415.1, INFORMATION TECHNOLOGY PROJECT MANAGEMENT
1. THE CONTRACTOR REQUIREMENTS DOCUMENT (CRD).
a. This CRD establishes the requirements for the Department of Energy (DOE) Information
Technology (IT) contractors with access to DOE information systems. Contractors must
comply with the requirements listed in this CRD.
b. Regardless of the performer of the work, the contractor is responsible for complying with
and flowing down the appropriate requirements of this CRD to subcontractors at any tier,
to the extent necessary, to ensure the contractors’ compliance with the requirements. That
is, the contractor will ensure that it and its subcontractors cost effectively comply with
the requirements of this CRD and incur only those costs that are reasonable and would be
incurred by a prudent person in the conduct of a competitive business.
c. The contractor, using a formal IT Project Management process with a graded approach
based on best business practices (BBPs), must develop a Project Management approach
for IT investments that:
(1) Foster IT investments that support DOE Program and Mission goals;
(2) Describe the management methods, Organization, control systems, and
documentation for projects; and
Section 7
(3) Monitor and control projects through Project Management practices.
d. For Federally directed IT investments with a Total Project Cost (TPC) of $25 Million (M)
or more, the contractor must follow the appropriate Program direction for IT Project
Management.
DOE O 415.1 Attachment 2
12-3-2012 Page 1
ACRONYMS
1. ACRONYMS. The acronyms listed in the following table are for terms used in the Department
of Energy (DOE) Order (O) 415.1, Information Technology Project Management, including the
appendix and the attachments.
Acronym Definition
AE Acquisition Executive
BBP best business practices
BPA Bonneville Power Administration
CEO Chief Executive Officer
CFR Code of Federal Regulations
CIO Chief Information Officer
CO Contracting Officer
COTS commercial-off-the-shelf
CPIC Capital Planning and Investment Control
CRD Contractor Requirements Document
DDR Detailed Design Review
DO Delegating Official
DOE Department of Energy
EA Enterprise Architecture
FAA Financial Assistance Awards
FASA Federal Acquisition Streamlining Act
FTE Full Time Employee
G Guide
GAO Government Accountability Office
HQ Headquarters
IPT Integrated Project Team
IT Information Technology
IT PM IT Project Manager
IT PMO IT Project Management Office
LMC Life Cycle Management
M Million
NNPP Naval Nuclear Propulsion Program
NNSA National Nuclear Security Administration
Attachment 2 DOE O 415.1
Page 2 12-3-2012
Acronym Definition
O Order
OCIO Office of the Chief Information Officer
OMB Office of Management and Budget
P.L. Public Law
PM Project Manager
PMO Project Management Office
PMP Project Management Plan
QAP Quality Assurance Program
QPR Quarterly Project Review
S/CIs suspect/counterfeit items
SS Steady State
TCO Total Cost of Ownership
TPC Total Project Cost
USC United States Code
DOE O 415.1 Attachment 3
12-3-2012 Page 1
REFERENCES
1. REFERENCES. This attachment provides information and/or requirements associated with the
Department of Energy (DOE) Order (O) 415.1 as well as information and/or requirements
applicable to contracts in which the associated Contractor Requirements Document
(DOE O 415.1, Information Technology Project Management, Attachment 1) is inserted.
a. DOE, Secretary Delegation Order No. 00-031.00A, dated 6-7-07.
b. DOE CIO Memorandum, Enterprise Architecture Guidance, dated 1-9-07.
c. DOE G 413.3-2, Quality Assurance Guide for Project Management, dated 6-27-08.
d. DOE G 413.3-18A, Integrated Project Team Guide for Formation and Implementation,
dated 2-3-12.
e. DOE O 200.1A, Information Technology Management, dated 12-23-08.
f. DOE O 205.1B, Department of Energy Cybersecurity Management Program, dated
5-16-11.
g. DOE O 243.1A, Records Management Program, dated 11-7-11.
h. DOE O 413.1B, Internal Control Program, dated 10-28-08.
i. DOE O 413.3B, Program and Project Management for the Acquisition of Capital Assets,
dated 11-29-10.
j. DOE O 414.1D, Quality Assurance, dated 4-25-11.
k. Executive Order 13011, Federal Information Technology, FR 61-140, dated July 19,
1996.
l. Government Accountability Office (GAO) Report – GAO-11-826, OMB Needs to
Improve Its Guidance on IT Investments, dated September 29, 2011.
m. Office of Science, Definition of a User Facility Memorandum, dated January 6, 2012.
n. OMB Circular A-11, Preparation, Submission and Execution of the Budget, dated August
18, 2011.
o. OMB Circular A-123, Management Accountability and Control, dated December 21,
2004.
Section 8
p. OMB Circular A-127, Financial Management Systems, dated January 9, 2009.
Attachment 3 DOE O 415.1
Page 2 12-3-2012
q. OMB Circular A-130, Management of Federal Information Resources, dated November
28, 2000.
r. OMB Memorandum M-00-07, Incorporating and Funding Security in Information
Systems Investments, dated February 28, 2000.
s. OMB Memorandum M-11-29, Chief Information Officer Authorities, dated August 8,
2011.
t. OMB Memorandum M-97-02, Funding Information Systems Investments, dated October
25, 1996.
u. The Clinger-Cohen Act of 1996, (CCA), (Public Law 104-106, Division E), dated
February 10, 1996.
v. The E-Government Act of 2002, (Public Law 107-347), dated December 17, 2002.
w. The Federal Acquisition Streamlining Act of 1994, Title V (FASA V), dated October 13,
1994.
x. The Federal Information Security Management Act (FISMA) of 2002, dated October 24,
2002.
y. The Government Information Security Reform Act (GISRA - 2000), dated October 30,
2000.
z. The Government Paperwork Elimination Act of 1998, (Public Law 105-277, Title XVII),
dated October 21, 1998.
aa. The Government Performance and Results Act of 1993 (GPRA) (Public Law 103-62),
dated August 3, 1993.
bb. The Paperwork Reduction Act of 1995, (Public Law 104-13), dated May 22, 1995.
cc. The President’s Management Agenda, Office of Management and Budget, Fiscal Year
2002, dated January 29, 2001.
dd. 25 Point Implementation Plan to Reform Federal Information Technology Management,
U.S. Chief Information Officer, dated December 9, 2010.
DOE O 415.1 Attachment 4
12-3-2012 Page 1
GLOSSARY OF TERMS
1. GLOSSARY OF TERMS. The Glossary of Terms listed in the following table provides
definitions to the terms used in The Department of Energy (DOE) Order (O) 415.1,
Information Technology Project Management.
Term Definition
Acquisition Executive (AE) The individual designated by the Secretary of Energy to
integrate and unify the management system for a Program
portfolio of projects and implement prescribed policies and
practices.
Acquisition Strategy A high-level business and technical-management approach
designed to achieve project objectives within specified
resource constraints with recognition of key project risks and
the strategies identified to handle those risks. It is the
framework for planning, organizing, staffing, controlling,
and leading a project. It provides a master schedule for
activities essential for project success and for formulating
functional strategies and plans.
Baseline A quantitative definition of cost, schedule, and technical
performance that serves as a base or standard for
measurement and control during the performance of an
effort; the established plan against which the status of
resources and the effort of the overall Program, Field
Program(s), project(s), task(s), or subtask(s) are measured,
assessed, and controlled. Once established, baselines are
subject to a change-control discipline.
Business Value The most important factor is the alignment between IT and
business processes, organization structure, and strategy. At
the highest levels, this alignment is achieved through proper
integration of EA, business architecture, process design,
organization design, and performance metrics.
Capital Planning and
Investment Control (CPIC)
Section 9
A systematic approach to managing the risk and returns of IT
investments for a given Mission. The CPIC process is an
integrated, structured methodology to managing IT
investments, which ensures that IT investments align with
the overall Strategic Plan and Mission in support of business
needs while minimizing risks and maximizing returns
throughout the investment’s life cycle. CPIC uses a
systematic selection, control, and continual-evaluation
process to ensure that an investment supports the overall
Mission and business needs.
Chief Information Officer
(CIO)
The individual responsible for overseeing the IT investment
portfolio.
Attachment 4 DOE O 415.1
Page 2 12-3-2012
Term Definition
Commercial off-the-Shelf
(COTS)
A product available in the commercial market place. COTS
products are sold to the general public in the course of
normal commercial business operations at a price based on
established catalog or market prices (Federal Acquisition
Regulations). COTS products are delivered with
pre-established functionality, although some degree of
customization is possible.
Contract A contract is a mutually binding agreement that obligates the
seller to provide the specified product and obligates the
buyer to pay for it.
Contracting Officer
(CO)
The CO has the authority to enter into, administer, and/or
terminate contracts and make related determinations and
findings. The term includes certain authorized
representatives of the CO acting within limits of his/her
authority as delegated by the CO. The CO and/or his/her
representative is accountable for preparing solicitation
documents with technical support from the IT Project
Manager and acting on behalf of the Head of the Contracting
Activity.
Contractor Requirements
Document (CRD)
The DOE document that identifies the requirements that the
prime contractor's Project Management system must satisfy.
Cybersecurity The protection of information systems against unauthorized
access to or modification of information (whether in storage,
processing, or transit), loss of accountability for information
and user actions, and the denial of service to authorized
users, including those measures necessary to protect against,
detect, and counter such threats.
Delegating Official
(DO)
The DO has the authority for approval of information
technology projects to ensure that the proposed expenditures
on IT are consistent with established policies, processes,
budgets, and related requirements.
Demonstrated Success Those IT projects that have been developed through a
defined-information-system life cycle with consistent results
of project completion within the original project schedule,
within budget, and meeting the functionality requirements
originally specified.
DOE O 415.1 Attachment 4
12-3-2012 Page 3
Term Definition
Departmental Directives
Program
Used to establish Directives as the primary means to set,
communicate, and institutionalize policies, requirements,
responsibilities, and procedures for Departmental Elements
and contractors. Equivalencies and exemptions to this Order
are processed in accordance with DOE Order 251.1C,
Departmental Directives Program.
Development,
Modernization, and
Enhancement (DME)
DME means the project cost for new projects, changes, or
modifications to existing systems to improve capability or
performance; changes mandated by Congress or Agency
leadership; personnel costs for investment management; and
direct support. For major IT investments, this amount should
equal the sum of amounts reported for planning and
acquisition plus the associated Full Time Employee (FTE)
costs reported in the OMB Exhibit 300B.
Section 10
DOE Elements Headquarters Elements or first-tier Organizations as listed in
the Correspondence Style Guide, Office of the Executive
Secretariat.
Enterprise Architecture
(EA)
A business-driven plan that describes the current state, future
vision, and transitional states of an operation. This is
presented in terms of: strategy and performance, business,
applications and services, technology, data, and security, all
at the end of a 2-to-5 year planning horizon.
Enterprise-wide IT
Projects
A project that spans or impacts multiple DOE Elements.
Equivalencies That which has the same or almost the same characteristics
or effect.
Information Management
Governance Council
(IMGC)
The IMGC serves as the DOE Corporate Risk Executive
(function) and is further defined in the DOE Order 205.1B,
DOE Cyber Security Program. IMGC-related groups
include:
IMGC Representatives (IMGC-R);
IMGC Advisory Group (IMGC-AG); and
IMGC Working Groups (IMGC-WG).
Information Any communication or representation of knowledge such as
facts, data, or opinions in any medium or form, including
textual, numerical, graphic, cartographic, narrative, or
audiovisual forms.
Information System A combination of information, computer, and
telecommunications resources; other information technology
resources; and personnel resources that collect, record,
process, store, communicate, retrieve, and display
information.
Attachment 4 DOE O 415.1
Page 4 12-3-2012
Term Definition
Information Technology
(IT)
Information technology, as defined by the Clinger-Cohen Act
of 1996, sections 5002, 5141, and 5142, means any
equipment or interconnected system or subsystem of
equipment that is used in the automatic acquisition, storage,
manipulation, management, movement, control, display,
switching, interchange, transmission, or reception of data or
information. For purposes of this definition, equipment is
“used” by an Agency whether the Agency uses the
equipment directly or it is used by a contractor under a
contract with the Agency that (1) requires the use of such
equipment or (2) requires the use, to a significant extent, of
such equipment in the performance of a service or the
furnishing of a product. Information technology includes
computers, ancillary equipment, software, firmware, and
similar procedures, services (including support services), and
related resources. It does not include any equipment that is
acquired by a Federal contractor incidental to a Federal
contract. Information technology is any proposed acquisition
of information technology or information technology-related
resources to support a defined business need.
Initiative An initiative is created by an Organization in response to a
driver or internal Directives and defines the scope of the
Organizational work- efforts performed.
Internal Controls A process affected by an Organization's structure, work and
authority flows, and people and management information
systems; it is designed to help the Organization accomplish
specific goals or objectives. It is a means by which an
Organization's resources are directed, monitored, and
measured.
IT Assets These IT assets provide the infrastructure and operational IT
services necessary for accomplishing the site Missions and
Programs. Specifically, they are locally managed IT assets or
IT support services. Examples include the following:
• Networks;
• Telecommunications;
• Desktops;
• Internet/Intranet;
• Email;
• Collaboration Tools;
• IT Planning (EA/CPIC/Program Office Support);
• Web Hosting;
• Data Storage; and/or
• Contractor Business/Financial/Administrative Systems.
Section 11
DOE O 415.1 Attachment 4
12-3-2012 Page 5
Term Definition
IT Investment For the purpose of this Order, an IT investment is used
interchangeably with an IT asset and IT project.
IT Project A planned endeavor funded by an approved information
technology investment, thus achieving a specific goal and
creating a unique product, service, or result. A project has a
defined start and end point with specific objectives that,
when attained, signify completion.
IT Project Management
Office
(IT PMO)
An Organizational Element or group that defines and
maintains the standards or processes generally related to
Project Management within the Organization. The PMO
develops project guidance, policies, and procedures.
IT Project Manager
(IT PM)
An individual in the Headquarters (HQ) Organizational
Element responsible for managing a project and its assigned
activities. This individual ensures that all the projects are
properly phased, funded over time, and that each Project
Manager is meeting his/her key milestones. These
individuals are the project’s advocates, ensure proper
resourcing, and facilitate the execution process. They predict
Programmatic risks and put mitigation strategies in place so
that projects are not affected.
Life Cycle Management
(LCM)
A business approach to manage the total life cycle of
products and services. LCM is used to understand and
analyze life cycle stages of products and services of a
business; identify potential economic, social, or
environmental risks and opportunities at each stage; and
create ways to act upon those opportunities and reduce
potential risks.
Maintenance An activity necessary to keep an asset functioning as
designed during its operations and maintenance phase of a
project. Maintenance costs include costs needed to sustain an
IT asset at the current capability and performance levels
including: corrective hardware/software, voice and data
communications maintenance, replacement of damaged or
obsolete IT equipment, and associated overhead costs.
Examples of maintenance projects include operating system
upgrades, technology refreshes, and security patch
implementations.
Milestone Any significant or substantive point, time, or event of the
project. Milestones typically refer to points at which
large-schedule events or series of events have been
completed, and a new phase(s) is set to begin.
Attachment 4 DOE O 415.1
Page 6 12-3-2012
Term Definition
Objective This defines the principal areas of concern within the overall
goal; it may also provide quantitative measures of future
performance and may list several Strategic Targets that
provide additional quantification of Agency objectives.
Office of the Chief
Information Officer
(OCIO)
The Office responsible to ensure that IT is acquired and
information resources are managed consistent with statutory,
regulatory, and Departmental requirements and priorities.
Operation The day-to-day management of an asset in the production
environment and included activities to operate data centers,
help desks, operational centers, telecommunication centers,
and end user support services. Operational activities are
reported through Section C of the Exhibit 300B. Operations
costs include the expenses associated with an IT asset that is
in the production environment to sustain an IT asset at the
current capability and performance levels including Federal
and contracted labor costs and the costs for the disposal of an
asset.
Section 12
Process A permanent or semi-permanent collection of measurable,
auditable, and repeatable activities that result in an output.
Project A project has a defined start and end point with specific
objectives that, when attained, signify completion thus
achieving a specific goal and creating a unique product,
service, or result. Built on interdependent activities planned
to meet a common objective, a project focuses on attaining or
completing a deliverable within a predetermined cost,
schedule, and technical scope.
Project Management Project Management is the discipline of planning,
organizing, securing, managing, leading, and controlling
resources to achieve specific goals. A project is a temporary
endeavor with a defined beginning and end (usually
time-constrained, and often constrained by funding or
deliverables) undertaken to meet unique goals and objectives,
typically to bring about beneficial change or added value.
Project Management Plan
(PMP)
The contractor-prepared document that sets forth the plans,
organization, and systems that the contractor will utilize to
manage the project. Its content and the extent of detail of the
PMP will vary in accordance with the size of the type of
project and state of project execution.
DOE O 415.1 Attachment 4
12-3-2012 Page 7
Term Definition
Project Performance The overall measurement of whether a project has met
objectives and requirements of scope, cost, and schedule. A
periodic measurement during the monitoring and controlling
phases of a project performed to observe project execution
and identify variances from the Project Management Plan for
proactive mitigation.
Quality Assurance
Program (QAP)
In Project Management, an inspection of the accomplished
work to ensure its alignment with the project scope. In
practice, projects typically have a dedicated quality control
team, which focuses on this area.
Requirements A singular documented need of what a particular product or
service should be or perform. It is a statement that identifies
a necessary attribute, capability, characteristic, or quality of a
system in order for it to have value and utility to a user.
Business requirements describe in business terms what must
be delivered or accomplished to provide value. Functional
requirements describe the functionality that the system is to
execute.
Risk Factor, element, constraint, or course of action that
introduces an uncertainty of outcome either positively or
negatively that could impact project objectives.
Risk Management The handling of risks through specific methods and
techniques. Effective risk management is an essential
element of every project. The DOE risk management concept
is based on the principles that risk management must be
analytical, forward-looking, structured, informative, and
continuous. Risk assessments should be performed as early
as possible in the project and should identify critical
technical, performance, schedule, and cost risks. Once risks
are identified, sound risk mitigation strategies and actions
should be developed and documented.
Solution A comprehensive architectural response to a business
problem. Solutions address all layers of EA - strategy,
business, data, applications, and technology/security.
Sponsoring/Funding
Organization
The DOE Organization responsible for providing the
necessary funding to support the project and project
activities.
Section 13
Stakeholder Individuals and Organizations that are actively involved in
the project, or whose interests may be positively or
negatively affected as a result of Program execution or
completion. They may also exert influence over the Program
and its results.
Attachment 4 DOE O 415.1
Page 8 12-3-2012
Term Definition
Steady State (SS) Steady State means maintenance and operation costs at
current capability and performance levels including costs for
personnel, maintenance of existing information systems,
corrective software maintenance, voice and data
communications maintenance, and replacement of broken IT
equipment. For major IT projects, this amount should equal
the amount reported for maintenance plus the associated FTE
costs reported in the OMB Exhibit 300B.
System An interconnected set of information resources organized for
the collection, processing, maintenance, transmission, and
dissemination of information, in accordance with defined
procedures, whether automated or manual.
Tailoring Tailoring is used to determine which processes and outputs
are appropriate, and the degree of rigor that should be
applied based on factors such as scope, size, risk, and
complexity.
Total Cost of Ownership
(TCO)
An analysis used to gauge the viability of any project. An
Enterprise may use it as a product/process comparison tool.
The TCO directly relates to an Enterprise's assets and/or
related systems total costs across all projects and processes,
thus giving a picture of the profitability over time.
Total Project Cost
(TPC)
All cost planning and implementation specific to a project
incurred through the startup of continual operations
(capability delivered) but prior to the operation of the
facility.