Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
Software Engineering Methodology
Chapter 1.0
Introduction
Table of Contents
Chapter Page
1.0 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.0-1
1.1 Implementation of Methodology . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.1-1
1.2 Submitting Change Requests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.2-1
DOE G 200.1-1 Introduction
5-21-97 Chapter 1.0
Date: March 1996 Introduction Page
Rev Date: 1.0-1
Chapter: 1.0
Introduction
Description: The Department of Energy Software Engineering Methodology provides guidance
for software engineering, project management, and quality assurance practices
and procedures. The primary purpose of the methodology is to promote the
development of reliable, cost-effective, computer-based software products while
making efficient use of resources. Use of the methodology will also aid in the
status tracking, management control, and documentation efforts of the project.
This software engineering methodology is consistent with other methodologies
used in the Government and private industry. It complies with Departmental
policy on project management, configuration management, security, and records
management. Significant input for the methodology was obtained from software
management programs at sites and organizations throughout the Department. The
methodology integrates Departmental best practices and focuses on the quality of
both the software engineering process and the work products generated from the
process.
The software engineering methodology is derived from the principles and
standards advocated by software quality industry leaders, such as The Institute of
Electrical and Electronics Engineers and the Carnegie-Mellon Software
Engineering Institute (SEI). This methodology is designed to enable project
teams to fully achieve Level 2 maturity on the SEI Capability Maturity Model.
Some Level 3 key process areas are also incorporated into the methodology.
Software quality assurance is integrated into the software engineering
methodology, making quality the responsibility of all project team manager(s)
and members. To assure the development of quality software products, the
methodology prescribes reviews, inspections, and audits for the lifecycle
processes and technical work products. To protect the integrity of the software,
the methodology also prescribes configuration controls over software, data, and
technical documentation.
The software engineering methodology encompasses all aspects of the software
lifecycle from project planning through production and maintenance, and
integrates the following basic lifecycle management concepts.
Implementation of software engineering preferred practices using a graded
approach based on the level of effort, complexity, and degree of external
impact of the software product.
Description,
DOE G 200.1-1 Introduction
5-21-97 Chapter 1.0
Date: March 1996 Introduction Page
Rev Date: 1.0-2
continued: Implementation of a project management methodology including quality
assurance, configuration management, and a comprehensive testing
approach that is adaptable to the individual site environments.
Application of a complete documentation approach supporting both
lifecycle and project management activities, to assure an effective method
for managing, tracking, and evaluating software engineering activities.
Section 2
The software engineering methodology is intended to be used by individuals,
project teams, and managers who are responsible for developing a new computer-
based software product or make changes to an existing system. The methodology
will be reviewed on a regular basis and modified as needed to keep pace with the
changing needs of the Departmental software engineering environment and the
continuing technical advances in the information systems industry.
The following sections provide additional information about using this software
engineering methodology.
1.1 Implementation of Methodology
1.2 Submitting Change Requests
DOE G 200.1-1 Introduction
5-21-97 1.1 Implementation of Methodology
Date: March 1996 Introduction Page
Rev Date: 1.1-1
Section: 1.1
Implementation of Methodology
Description: This methodology integrates software engineering, project management, and
quality assurance practices and is designed to be flexible. It can be adapted to
accommodate the specific needs of any software project and all computing
platforms used in the Department including standalone and networked
mainframes, minicomputers, and microcomputers.
Projects that were initiated prior to the publication of this document should plan
to implement the methodology at the earliest feasible stage or the next release of
the product. If a Project Plan already exists, make the revisions necessary to
integrate the software engineering, project management, and quality assurance
practices, as appropriate. If a Project Plan does not exist, develop a plan that
summarizes the activities and deliverables of the previous stages and incorporates
the methodology activities and products into the subsequent stages.
The software engineering methodology presented here does not supersede,
replace, or override more stringent requirements that may apply to specific
projects such as scientific and technical practices, and security and safety issues
associated with the Nuclear Weapons Complex.
Since the methodology does not provide specific guidance for every software
engineering situation, suggestions for adapting the methodology to accommodate
projects of varying size, complexity, or criticality are provided in Chapter 2.0,
Lifecycle Model.
Questions: If specific questions are generated concerning the interpretation or applicability of
portions of the methodology, the project team should attempt to resolve them
during the project review activities built into the stages of the lifecycle. The
system owner/user(s) and other project stakeholders must concur with any
adaptations that are made.
When questions about interpretation or applicability of the guidance to a specific
project cannot be resolved by the project team, the issue should be submitted to
the site authority for software engineering, such as the site Information Resources
Management or Information Management organization, for resolution. For
Headquarters projects, the Office of Information Management is the site
authority.
DOE G 200.1-1 Introduction
5-21-97 1.1 Implementation of Methodology
Date: March 1996 Introduction Page
Rev Date: 1.1-2
Questions,
continued: Questions and issues will be analyzed by the site Information Management
Division and a response will be made in one of the following ways.
An immediate solution is determined and will be provided to the project
team.
The issue will be submitted to personnel who are considered experts in the
area in question. Once a solution is reached, it will be provided to the
project team.
Section 3
It is important to also submit questions of interpretation or applicability and the
site-specific resolution to the Headquarters Office of Information Management.
The Office will determine if a modification to the Software Engineering
Methodology is needed to clarify processes or to provide additional adaptation
suggestions. A central clearinghouse for all questions and resolutions will ensure
that needed changes to the methodology can be identified and implemented in a
timely and consistent manner.
DOE G 200.1-1 Introduction
5-21-97 1.2 Submitting Change Requests
Date: March 1996 Introduction Page
Rev Date: 1.2-1
Section: 1.2
Submitting Change Requests
Description: The Departmental software engineering environment is continuously changing as
emerging technologies are integrated into projects, system owner/user
requirements are expanded, and organizational needs evolve. The software
engineering methodology will be expanded and revised, as needed, to reflect
changes in the environment, improvements suggested through user feedback, and
the maturation of software engineering capabilities.
Users of the methodology are encouraged to submit suggestions for improving its
content and to report any practices that are difficult to understand or create an
implementation problem for a project team.
Suggestions and problems should be submitted on the Change Request Form that
is provided at the end of this section. If the form is not available or does not
accommodate the type of request being made, submit a memo that describes the
suggestion or problem.
The Change Request Form or memo should be submitted to the Office of
Information Management at Headquarters in Germantown, Maryland. The
Change Request should be submitted through the site's Information Management
organization. All requests will be evaluated and the originator of the request will
be notified of the action taken.
Some requests will be handled immediately while others may require
investigation by an ad hoc Working Group of knowledgeable personnel. In some
cases, a request may not be appropriate for the current environment, but will be
retained for future consideration.
Software Engineering Methodology
Change Request Form
To be completed by Requestor To be completed by Analyst
Name: Name:
Phone: Phone:
Location: Location:
Date: Date Assigned:
Document Section: Request Number:
Requested Change and Justification: Change Classification Data (check one)
Class I Change ___
Class II Change ___
Class III Change ___
Check if additional pages are attached ___ Check if additional pages are attached ___
Summary of Impact:
Change Impacts Change Impacts
Section Number: ____________________ Section Number: ____________________
Pages: ____________________ Pages: ____________________
Working Group Actions
Approval/Disapproval Reason(s): Date ____________________
Additional Comments:
Software Engineering Methodology
Change Request Instructions
Requestor's Section Instructions
Name: Fill in your name, telephone number, location and date.
Phone:
Location:
Date:
Document Section: List the document section where you want to make a change.
Requested Change and State the change that you want to incorporate and state your reasons for the change.
Justification: Attach additional pages as needed.
Change Impacts: List any section numbers and pages that will be affected by the proposed change.
Section 4
**Send the completed Change Request Form to the Headquarters Office of Information Management, Systems
Engineering Group, Engineering Services Team, HR-433, Germantown, Maryland.
Analyst's Section Instructions
Name: Fill in your name, telephone number, location, and date you received the assignment.
Phone:
Location:
Date Assigned:
Request Number: Obtain the sequential number that will be used to track the request from the
Headquarters Office of Information Management, Systems Engineering Group,
Engineering Services Team, HR-433.
Change Classification Data: Class I Changes in policy, procedures, required actions, or deliverables are defined by
Government units (Congress, Office of Management and Budget), or by DOE policies,
procedures, and administrative requirements. These changes must be reviewed and
approved by HR-433 and incorporated into the methodology with the next update.
Class II Changes in technology or development methodology are descriptions of
innovations in the way software products are developed. These changes require
review and concurrence by a Working Group and must be approved by HR-433.
Changes in required deliverables may be implemented by HR-433 or recommended by
a Working Group. The impact on the remainder of the methodology when such
changes are incorporated require review and concurrence by a Working Group and
approval by HR-433.
Class III Changes in factual information (security requirements), wording, or
corrections of typographical errors will be implemented as soon as possible to keep
the methodology accurate and current. Corrections of typographical errors are
implemented without review. All other changes require review and approval by HR-
433.
Summary of Impact: State what effect the proposed change would have on other sections of the document
or the methodology.
Change Impacts: List any section numbers and pages that will be affected by the proposed change.
Working Group Instructions
Approval/Disapproval State whether the proposed change should be approved or disapproved. Give
Reasons: reasons for the decision. Indicate date of approval/disapproval.