DOE P 413.1, Program and Project Management Policy for the Planning, Programming, Budgeting, and Acquisition of Capital Assets
Functional areas: Acquisition, Program Management, Program Planning and Management, Project Management
To establish Department of Energy (DOE) program and project management policy for the planning, programming, budgeting, and acquisition of capital assets consistent with the following Office of Management and Budget (OMB) circulars: OMB Circular A-11, Part 3, Planning, Budgeting, and Acquisition of Capital Assets, and the supplement to Part 3, Capital Programming Guide; OMB Circular A-123; OMB Circular A-127; and OMB Circular A-130. Does not cancel other directives.
Canceled by DOE N 251.99
Superseded By:
DOE N 251.99, Cancellation of DOE P 413.1 on Mar 02, 2011
Version history and related documents
Superseded by
A newer version replaces this document.
- DOE N 251.99Cancellation of DOE P 413.1 (Mar 02, 2011)
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
DOE P 413.1 7-14-04
E R R A T A S H E E T
This Errata Sheet transmits an administrative change to DOE P 413.1, Program and
Project Management Policy for the Planning, Programming, Budgeting, and Acquisition
of Capital Assets, dated 6-10-00. A “Review Date” and an “Expiration Date” were
inadvertently placed on DOE P 413.1. These dates have been deleted since Policies do not
expire.
This Errata Sheet must remain with the Policy.
DISTRIBUTION: INITIATED BY:
All Departmental Elements Office of the Chief Financial Officer
U.S. Department of Energy POLICY
Washington, D.C.
Approved: 6-10-00
SUBJECT: PROGRAM AND PROJECT MANAGEMENT POLICY FOR THE
PLANNING, PROGRAMMING, BUDGETING, AND ACQUISITION OF
CAPITAL ASSETS
PURPOSE
To establish Department of Energy (DOE) program and project management policy for the
planning, programming, budgeting, and acquisition of capital assets consistent with the
following Office of Management and Budget (OMB) circulars:
· OMB Circular A-11, Part 3, Planning, Budgeting, and Acquisition of Capital Assets, and
the supplement to Part 3, Capital Programming Guide;
· OMB Circular A-123;
· OMB Circular A-127; and
· OMB Circular A-130.
Capital assets are land, structures, equipment, and information technology (e.g., hardware,
software, and applications) that are used by the Federal Government and that have an estimated
useful life of 2 years or more. Capital assets include the environmental restoration
(decontamination and decommissioning) of land to make useful, leasehold improvements and
land rights and assets whose ownership is shared by the Federal Government with other entities.
Capital assets do not include grants for acquiring capital assets made to State and local
governments or other entities. Capital assets also do not include intangible assets, such as the
knowledge resulting from research and development and education and training.
POLICY
Federal program and project managers are accountable for the planning, programming,
budgeting, and acquisition of capital assets. The principal DOE goal is to deliver capital assets
on schedule, within budget, and fully capable of meeting mission performance and
environmental, safety, and health standards. DOE Federal program and project managers are
responsible for ensuring that capital asset projects are managed with integrity and in compliance
DOE P 413.1
2 DOE P 413.1
6-10-00
with applicable laws. Major DOE objectives include obtaining quality products, ensuring
timeliness of performance, controlling cost, and mitigating adverse events. To achieve these
goals, Federal program and project managers should assemble an integrated team, which
includes other DOE functional areas such as budget, financial, legal, safety, and contracting, to
assist them with the planning, programming, budgeting, and acquisition of capital assets.
DOE Federal managers will—
· justify budgets needed for acquisition of capital assets,
· ensure line management involvement in and accountability for project performance,
· establish and maintain strong project management organizations and systems,
· use appropriate project management tools and train personnel, and
· develop and implement programs for institutionalizing project management capabilities.
Section 2
The Office of Engineering and Construction Management (OECM), within the Office of the
Chief Financial Officer, will lead implementation of this Policy and will develop and maintain
capital asset program and project management directives, procedures, and guidance documents
for the Department. OECM will support the Secretarial Acquisition Executive in oversight of
the DOE program and project management activities for the effective acquisition of capital assets
which are fully capable of meeting mission performance requirements. The DOE program
offices have line responsibility and DOE functional offices such as budget, chief information
officer, legal, safety, and contracting have staff responsibility for effective implementation of
this policy.
BY ORDER OF THE SECRETARY OF ENERGY:
T.J. GLAUTHIER
DEPUTY SECRETARY