DOE O 5480.21, Unreviewed Safety Questions
Functional areas: Environmental Quality & Impact
Canceled by DOE N 251.42.
Superseded By:
DOE N 251.42, Cancellation of Directives on Feb 09, 2002
Version history and related documents
Superseded by
A newer version replaces this document.
- DOE N 251.42Cancellation of Directives (Feb 09, 2002)
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
12-24-91
UNREVIEWED SAFETY QUESTIONS
1. PURPOSE. To set forth the definition and basis for determining the
existence of an Unreviewed Safety Question (USQ).
2. CANCELLATION. DOE 5480.5, SAFETY OF NUCLEAR FACILITIES, of 9-23-86,
paragraphs 5s and DOE 5480.6, SAFETY OF DOE-OWNED NUCLEAR REACTORS, of
9-23-86, paragraphs 5x and DOE 5480.1B, ENVIRONMENT, SAFETY, AND HEALTH
PROGRAM FOR DEPARTMENT OF ENERGY OPERATIONS, of 9-23-86, paragraph 5o.
3. SCOPE. The provisions of this Order apply to all Departmental Elements
and to covered contractors to the extent implemented under a contract or
other agreement. A covered contractor is a seller of supplies or
services, involving a DOE-owned or -leased nuclear facility, under a
contract or subcontract containing one of four contract clauses as
follows: (1) Safety and Health (Government-owned or -leased facility)
[DEAR 970.5204-2], (2) Nuclear Facility Safety [DEAR 970.5204-26], (3)
Radiation Protection and Nuclear Criticality [DEAR 952.223-72], or (4)
another clause whereby DOE elects to require compliance with DOE nuclear
safety requirements. The provisions of this Order will be applied to
DOE-owned nuclear facilities and operations exempt from Nuclear Regulatory
Commission (NRC) licensing. This Order does not apply to those facilities
and activities conducted under Executive Order 12344 and Public Law
98-525, paragraph 1634, 98 stat 2649 (paragraph 9f).
4. EXCLUSIONS.
a. This Order does not apply to the Naval Nuclear Propulsion Program
(paragraph 9f).
b. This Order does not apply to sites that consist entirely of space
controlled and maintained by the General Services Administration (GSA)
or property leased by DOE or DOE contractor(s) for which maintenance
is contractually the responsibility of the lessor.
c. This Order does not apply to activities with nuclear explosives,
nuclear explosives components, or nuclear explosive-like assemblies
which are covered under DOE 5610.1, PACKAGING AND TRANSPORTING OF
NUCLEAR EXPLOSIVES, NUCLEAR COMPONENTS, AND SPECIAL ASSEMBLIES, of
911-79, or DOE 5610.3, PROGRAM TO PREVENT ACCIDENTAL OR UNAUTHORIZED
NUCLEAR EXPLOSIVE DETONATIONS, of 12-18-80.
All Departmental Elements Office of Nuclear Energy
2 DOE 5480.21
12-24-91
d. In accordance with Section 302 of the Department of Energy
Organization Act (PL 95-91), the Secretary operates and maintains the
Power Marketing Administration (PMA) electric power transmission
systems by and through the PMA Administrators. The PMA has management
programs in place that are geared to the special needs of utility
operations, that respond to coordinated multi-utility system
requirements, and that conform with prudent utility practice. In view
of the unique nature of the Administrators’ obligations to meet their
statutory and public utility responsibilities for the safety,
security, and reliability of electric power transmission and of their
legal and contractual obligation, the Administrators shall determine
the appropriate Unreviewed Safety Question procedures for their
facilities, which will include consideration of appropriate parts of
the criteria set forth by this Order.
5. REFERENCES.
a. DOE 5480.5,
establishes
b. DOE 5480.6,
c.
d.
e.
f.
SAFETY OF NUCLEAR FACILITIES, of 9-23-86, which
DOE’s nonreactor nuclear facilities safety programs.
SAFETY OF DEPARTMENT OF ENERGY-OWNED NUCLEAR REACTORS, of
9-23-86, which establishes DOE’S nuclear reactor safety program.
Section 2
DOE 5480.1B, ENVIRONMENT, SAFETY, AND HEALTH PROGRAM FOR DEPARTMENT OF
ENERGY OPERATIONS, of 9-23-86, which establishes the Environment,
Safety, and Health program for DOE operations.
Title 10 CFR 50.59, which establishes the basis for Unreviewed Safety
Questions within the commercial nuclear industry.
Title 10 CFR 50.71(e), which establishes requirements for Safety
Analysis Report Updates within the commercial nuclear industry.
NSAC-125, Guidelines for 10 CFR 50.59 Safety Evaluations, of June
1989, which establishes guidance for the implementation of Title 10
CFR 50.59.
Regulatory Guide 1.70, Revision 3, which establishes the standard
format and content for Safety Analysis Reports (SARs) for power
reactors within the commercial nuclear industry.
6. DEFINITIONS.
a. Accident Analyses. For the purposes of properly implementing the USQ
Order, the term accident analyses refers to those bounding analyses
selected for inclusion in the SAR. These analyses refer to design
basis accidents only.
b. Authorization Basis. Those aspects of the facility design basis and
operational requirements relied upon by DOE to authorize operation.
These aspects are considered to be important to the safety of facility
DOE 5480.21 3
12-24-91
operations. The authorization basis is described in documents such as
the facility Safety Analysis Report and other safety analyses; Hazard
Classification Documents, the Technical Safety Requirements, DOE-
issued safety evaluation reports, and facility-specific commitments
made in order to comply with DOE Orders or policies.
c.
d.
e.
f.
g.
h.
i.
Design Basis. The set of requirements that bound the design of
systems, structures, and components within the facility. These design
requirements include consideration of safety, plant availability,
efficiency, reliability, and maintainability. Some aspects of the
design basis are important to safety, although others are not.
Design Basis Accidents. Those accidents that are considered credible
enough to be postulated for the purpose of establishing design and
performance requirements for systems, structures, and components
important to safety.
Contractor. Any person under contract with the Department of Energy
with responsibility to perform activities in connection with a nuclear
facility.
Important to Safety. For the purposes of this Order, equipment
important to safety is intended to include any equipment whose
function can impact safety either directly or indirectly. This
includes safety-related equipment, equipment relied upon for safe
shutdown, and in some instances, balance-of-plant equipment.
Line Organization. See DOE 5480.1B, ENVIRONMENT, SAFETY, AND HEALTH
PROGRAM FOR DEPARTMENT OF ENERGY OPERATIONS.
Margin of Safety. That margin built into the safety analyses of the
facility as set forth in the authorization basis acceptance limits.
Nonreactor Nuclear Facility. Those activities or operations that
involve radioactive and/or fissionable materials in such form and
quantity that a nuclear hazard potentially exists to the employees or
the general public. Included are activities or operations that: (1)
produce, process, or store radioactive liquid or solid waste,
fissionable materials, or tritium; (2) conduct separations operations;
(3) conduct irradiated materials inspection, fuel fabrication,
decontamination, or recovery operations; (4) conduct fuel enrichment
operations; or (5) perform environmental remediation or waste
management activities involving radioactive materials. Incidental use
and generation of radioactive materials in a facility operation (e.g.,
check and calibration sources, use of radioactive sources in research
and experimental and analytical laboratory activities, electron
microscopes, and X-ray machines) would not ordinarily require the
facility to be included in this definition. Accelerators and reactors
and their operations are not included. The application of any
rule/Order to a nonreactor nuclear facility shall be applied using a
graded approach.
Section 3
4 5480.21
12-24-91
j.
k.
l.
m.
n.
o.
p.
q.
Nuclear Facility. All reactor and nonreactor nuclear facilities.
Program Manager. See DOE 5000.3A, OCCURRENCE REPORTING AND PROCESSING
OF OPERATIONS INFORMATION, of 5-30-90.
Program Secretarial Officer (PSO). A senior outlay program manager,
including the Assistant Secretaries for Conservation and Renewable
Energy (CE), Defense Programs (DP), Fossil Energy (FE), Nuclear Energy
(NE), and Environmental Restoration and Waste Management and the
Directors of Energy Research (ER), Civilian Radioactive Waste
Management (RW), and New Production Reactors (NP).
Reactor means, unless it is modified by words such as containment,
vessel, or core, the entire nuclear reactor facility, including the
housing, equipment, and associated areas devoted to the operation and
maintenance of one or more reactor cores. Any apparatus that is
designed or used to sustain nuclear chain reactions in a controlled
manner, including critical and pulsed assemblies and research, test,
and power reactors, is defined as a reactor. All assemblies designed
to perform subcritical experiments that could potentially reach
criticality are also to be considered reactors. Critical assemblies
are special nuclear devices designed and used to sustain nuclear
reactions. Critical assemblies may be subject to frequent core and
lattice configuration change and may be used frequently as mockups of
reactor configurations.
Safety Analysis. See DOE 5480.5, SAFETY OF NUCLEAR FACILITIES.
Safety Analysis Report (SAR). See DOE 5480.6, SAFETY OF DEPARTMENT OF
ENERGY-OWNED NUCLEAR REACTORS.
Safety Evaluation. A safety evaluation is that record required by
this Order to document the review of a “change.” This document records
the scope of the evaluation and the logic for determining whether or
not an Unreviewed Safety Question exists.
Technical Safety Requirements (TSR). Those requirements that define
the bounding conditions for safe operation, and bases thereof, and the
management or administrative controls required to ensure the safe
operation of a nuclear facility. (Formerly known as Operational
Safety Requirements for nonreactor nuclear facilities and Technical
Specifications for nuclear reactor facilities.)
7. BACKGROUND.
a. The concept of the Unreviewed Safety Question was established to allow
contractors to make physical and procedural changes and to conduct
test and experiments without prior DOE approval, as long as these
changes do not explicitly or implicitly affect the authorization basis
of the facility or result in a Technical Safety Requirement change.
The intent of this Order is to provide contractors with the
DOE 5480.21
12-24-91
5
flexibility needed to conduct day-to-day operations and to require
that those issues with a potential impact on the authorization basis,
and therefore the safety of the facility, be brought to the attention
of DOE--thus maintaining the proper safety focus. The authorization
basis is described in documents such as the facility Safety Analysis
Report, other safety analyses, Hazard Classification Documents, the
Technical Safety Requirements, D0E-issued safety evaluation reports,
and facility-specific commitments made in compliance with DOE Orders
or policies.
Section 4
b. This Order has been developed according to some of the same principles
present in the commercial industry and enumerated in 10 CFR 50.59.
The purpose of this Order is similar to that of 10 CFR 50.59. DOE has
not simply copied what is contained in 10 CFR 50.59 and its guidance
document, NSAC-125, “Guidelines for 10 CFR 50.59 Safety Evaluations,”
but has adapted this Order to DOE facilities and to previous DOE
operational experiences. One significant addition to this Order is
its application in instances where a potential inadequacy of the
currently accepted analysis, as documented in a facility’s Safety
Analysis Report, or a possible reduction in the margin of safety, as
defined by the Technical Safety Requirements, is discovered. When a
potential inadequacy of any part of the authorization basis is
discovered, the impact of this inadequacy may pose serious
implications. For this case, it may be necessary to perform a safety
analysis to determine conclusively whether a safety problem exists;
however, DOE requires that a USQ determination be completed
immediately, thus providing a benchmark of the relative safety
significance, and that the facility be put in a safe condition. In
these instances, the contractor is responsible for making an initial
assessment of the potential impact of the analytic inadequacy and for
determining what operational restrictions, if any, may be warranted.
c. Requirements, beyond those employed in the design of a nuclear
component or nuclear facility, have been established by DOE to protect
the public health and safety from the risks of hazardous and
radioactive materials. These requirements affect the design,
operation, and maintenance of any DOE nuclear facility. These safety
requirements, and how they are met, are reflected in the authorization
basis. In order to perform an evaluation of a USQ, an understanding
of the authorization basis of the facility, and of the specific
requirements of the DOE Orders and policies, is necessary.
d. The USQ review process should be integrated into all technical aspects
of the contractor organization responsible for design, engineering,
maintenance, inspection, operations, and assessment of the nuclear
facility or activity. As such, all individuals involved in these
aspects of the organization should be familiar with the requirements
of this Order and should be able to identify potential USQs during the
course of carrying out their normal responsibilities.
8. POLICY. It is the Department’s policy that:
6 5480.21
12-24-91
a. Each facility develop procedures to implement the Unreviewed Safety
Question review process consistent with the provisions described in
this Order.
b. Any changes made to a facility that directly or indirectly affect the
facility authorization basis, and therefore its safety, be reviewed in
accordance with the provisions of this Order.
c. Primary responsibility, authority, and accountability for the
direction and management of the USQ process reside with the line
management of the facility organization responsible for the design and
safety analyses.
9. RESPONSIBILITIES AND AUTHORITIES.
a. Program Secretarial Officers (PSO), shall perform the following
functions for all nuclear facilities under their program
responsibility:
(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
Ensure the preparation, review, and approval of contractor
documentation implementing the requirements of this Order;
Section 5
Actively monitor the USQ identification, review, and
decisionmaking process of DOE Field Offices and contractors under
their cognizance to determine whether an incident, analysis, or a
proposed change/modification to systems, components, processes,
operations, tests, or experiments involves a USQ;
Provide direction to field organizations for implementation of
the requirements of this Order;
Declare the existence of a USQ, when discovered, and direct the
Field Office Manager to curtail or suspend operations, tests,
experiments, or actions to implement the proposed
changes/modifications pending resolution of the USQ concerns, or
take other actions as appropriate to reduce the risk;
Assist the contractor or Field Office Manager, when requested, in
determining whether an incident, analysis, or proposed
change/modification to systems, components, processes,
operations, tests, or experiments involves a USQ;
Approve changes determined to involve a USQ prior to
implementation, and approve operations when a USQ has been
determined to exist;
Ensure that Program Managers oversee the implementation of
changes within the purview of this Order; and
Establish the authorization level for each facility under their
program responsibility.
DOE 5480.21 7
12-24-91
(9) Designate an individual(s) to be responsible for bringing to the
attention of the contracting officer each procurement falling
within the scope of this Order. Unless another individual is
designated, the responsibility is that of the procurement request
originator (the individual responsible for initiating a
requirement on DOE F 4200.33, “Procurement Request
Authorization”).
(a)
(b)
Procurement request originators (the individuals responsible
for initiating a requirement on DOE F 4200.33) or such other
individual(s) as designated by the cognizant PSO shall bring
to the attention of the cognizant contracting officer the
following: (1) each procurement requiring the application of
this Order, (2) requirements for flowdown of provisions of
this Order to any sub-contract or sub-award, and (3)
identification of the paragraphs or other portions of this
Directive with which the awardee, or, if different, a sub
awardee, is to comply.
Contracting officers, based on advice received from the
procurement request originator or other designated
individual, shall apply applicable provisions of this Order
to awards falling within its scope. For awards, other than
management and operating contracts, this shall be by
incorporation or reference using explicit language in a
contractual action, usually bilateral. All paragraphs of
this Order shall be applied to contractors, excluding
paragraph 9.
b. Assistant Secretary for Nuclear Energy (NE-1) , in addition to the
requirements of paragraph 9a shall perform the following functions:
(1) Develop, promulgate, and maintain guidance documents necessary to
implement relevant training, policies, and procedures;
(2) Assist line management in developing, implementing, and
evaluating criteria, standards, and requirements associated with
changes to nuclear facilities;
(3) Provide guidance and technical assistance to the cognizant PSO
and the field organization; and
(4) Monitor reports relative to changes at DOE nuclear facilities to
assess implementation of these requirements and modify or provide
additional guidance as necessary.
c. Director, Office of Nuclear Safety (NS-1), acting as the independent
element for nuclear safety oversight of line management performance
for the Department, shall perform the following functions:
Section 6
8 5480.21
12-24-91
(1) Assess the level of safety and degree of compliante by
Departmental Elements with the DOE requirements of this Order;
(2) Monitor and audit activities of the cognizant PSO and the
affected field organization to assure the requirements of this
Order are consistently applied;
(3) Monitor the USQ identification, review, and decision-making
process of the line organization to assure compliance with the
requirements of this Order;
(4) Review USQ governing and implementing procedures to assure their
consistency in application of the requirements of this Order; and
(5) Declare the existence of a USQ, that has not been identified,
analyzed, or adequately resolved by the line organization and
ensure that the USQ is adequately addressed by the line
organization.
d. Assistant Secretary for Environment, Safety, and Health (EH-1), acting
as the independent element responsible for environment, occupational
safety, and health oversight of line management for the Department,
shall perform the following functions:
(1)
(2)
(3)
(4)
(5)
Assess the level of safety and degree of compliance by
Departmental Elements with the DOE requirements of this Order;
Monitor and audit activities of the cognizant PSO and the
affected field organization to assure that the requirements of
this Order are consistently applied;
Monitor the USQ identification, review, and decision-making
process of the line organization to assure compliance with the
requirements of this Order;
Review USQ governing and implementing procedures to assure their
consistency in application of the requirements of this Order; and
Declare the existence of a USQ, that has not been identified,
analyzed, or adequately resolved by the line organization and
ensure that the USQ is adequately addressed by the line
organization.
e. Heads of Field Organizations, for facilities and operations under
their jurisdiction shall perform the following functions:
(1) Ensure that adequate contractor procedures are in place and
assess the effectiveness of their implementation, consistent with
the provisions of this Order;
DOE 5480.21
12-24-91
9
(2) Approve documentation prepared by the contractor demonstrating
compliance with this Order;
(3) Actively monitor the USQ identification, review, and
decisionmaking process of contractors under their cognizance to
determine whether an incident, analysis, or proposed
change/modification to systems, components, processes,
operations, tests, or experiments involves a USQ; and
(4) Declare the existence of a USQ, when discovered, and direct the
contractor to curtail or suspend operations, tests, experiments,
or actions to implement the proposed changes/modifications
pending resolution of the USQ concern, or take other actions as
appropriate to reduce the risk.
(5) Assure that DOE contractors to whom this Order is made applicable
implement the requirements of paragraph 10 of this Order.
(6) Designate an individual(s) to be responsible for bringing to the
attention of the contracting officer each procurement falling
within the scope of this Order. Unless another individual is
designated, the responsibility is that of the procurement request
originator (the individual responsible for initiating a
requirement on DOE F 4200.33 “Procurement Request
Authorization”).
Section 7
(a) Procurement request originators (the individuals responsible
for initiating a requirement on DOE F 4200.33) or such other
individual(s) as designated by the cognizant heads of field
organizations shall bring to the attention of the cognizant
contracting officer the following: (1) each procurement
requiring the application of this Order, (2) requirements
for flowdown of provisions of this Order to any subcontract
or sub-award, and (3) identification of the paragraphs or
other portions of this Order with which the awardee, or, if
different, a sub-awardee, is to comply.
(b) Contracting officers, based on advice received from the
procurement request originator or other designated
individual, shall apply applicable provisions of this Order
to awards falling within its scope. For awards, other than
management and operating contracts, this shall be by
incorporation or reference using explicit language in a
contractual action, usually bilateral. All paragraphs of
this Order shall be applied to contractors excluding
paragraph 9.
f. Director, Naval Nuclear Propulsion Program. Executive Order 12344,
statutorily prescribed by PL 98-525 (42 USC 7158 note) establishes the
10 5480.21
12-24-91
responsibilities and authority of the Director, Naval Nuclear
Propulsion Program (who is also the Deputy Assistant Secretary for
Naval Reactors within the Department) over all facilities and
activities which comprise the Program, a joint Navy-DOE organization.
These executive and legislative actions establish the responsibilities
of the Director as including the safety of reactors and associated
naval nuclear propulsion plants, the control of radiation and
radioactivity associated with naval nuclear propulsion plants, and the
operating practices and procedures applicable to naval nuclear
propulsion plants. Accordingly, the provisions of this Order do not
apply to the Naval Nuclear Propulsion Program. The Director shall
establish the unreviewed safety question determination requirements
implemented within the program.
10. PROGRAM REQUIREMENTS.
a. A contractor authorized to operate DOE nuclear facilities shall:
(1) Perform all safety evaluations required by paragraph (b) of this
section to determine whether a situation involves USQ;
(2) Prior to implementation of a proposed action, obtain PSO approval
for situations determined to involve a USQ or a Technical Safety
Requirements (TSR) change; and
(3) Develop and implement procedures to govern the need for, and the
performance of, safety evaluations under this section.
b. A safety evaluation shall be performed for:
(1) Temporary or permanent changes in the facility as described in
the existing safety analyses;
(2) Temporary or permanent changes in the procedures as described in
existing safety analyses; or
(3) Test or experiments not described in existing safety analyses.
c. A situation involves a USQ if:
(1) The probability of occurrence or the consequences of an accident
or malfunction of equipment important to safety previously
evaluated in the facility safety analyses could be increased;
(2) The possibility for an accident or malfunction of a different
type than any evaluated previously in the facility safety
analyses could be created; or
DOE 5480.21 11
12-24-91
(3) Any margin of safety, as defined in the bases of the TSRs, could
be reduced.
d. When a contractor identifies information that indicates a potential
inadequacy of previous safety analyses or a possible reduction
margin of safety as defined in the TSRs, the contractor shall:
Section 8
(1) Notify the PSO of the situation upon discovery of the
information;
(2) Make an evaluation in accordance with paragraphs 10a and
(3) Take action to place the facility in a safe condition until
safety evaluation is completed; and
in the
10c;
the
(4) Submit the completed safety evaluation prior to removing any
operational restrictions initiated pursuant to paragraph 10d(2).
e. For all safety evaluations required under this section, a contractor
shall:
(1) Document the basis for the USQ determination, utilizing the
procedures provided for in paragraph l0a(3) of this section and
the criteria of paragraph l0c;
(2) Maintain documentation required by paragraph lOe(1) for the
authorized operating period of the nuclear facility and ensure
the complete transfer of all documentation to any subsequent
contractor prior to termination of its contract;
(3) Incorporate in the existing SAR, any changes that are needed as a
result of the safety evaluation or any action taken; and
12 5480.21
12-24-91
(4) Submit to the PSO, on a schedule corresponding to the periodic
updates of the SAR, a report summarizing all situations for which
a safety evaluation was required by this section and indicating
all “changes” considered in a safety evaluation and implemented 6
months or more before the submittal date of the report.
BY ORDER OF THE SECRETARY OF ENERGY:
JOHN J. NETTLES, JR.
Director of Administration and
Human Resource Management
DOE 5480.21
12-24-91
i
TABLE OF CONTENTS
CHAPTER I: GENERAL INTRODUCTION I-1
1. Background . . . . . . . . . . . . . . . . . . .
2. Purpose. . . . . . . . . . . . . . . . . . . . .
CHAPTER II: APPLICABILITY . . . . . . . . . . . . .
1.
2.
3.
4.
5.
Background
Changes in the Nuclear Facility as Described in
Safety Analyses. . . . . . . . . . . . . . . . .
Changes in the Procedures as Described in Safety
Analyses
Conduct of Tests of Experiments Not Described
Safety Analyses . . . . . . . . . . . .
Discovery of Analytic Errors, Omission,
Inadequacies . . . . . . . . . . . . .
CHAPTER III: IMPLEMENTATION GUIDANCE
1.
2.
3.
4.
5.
6.
7.
8.
9.
Introduction . . . . . . . . . . . . .
Governing Process . . . . . . . . . . .
Understanding the Authorization Process
Screening Criteria and Procedures . . .
Implementing Procedures . . . . . . . .
Safety Evaluations (USQ Determination)
Periodic Reports . . . . . . . . . . .
Training . . . . . . . . . . . . . . .
Implementation Schedule . . . . . . . .
CHAPTER IV: INTERPRETATIONS
1. Purpose. . . . . . . . . . . . . . . .
2. Unreviewed Safety Question . . . . . .
or
3. Increase in the Probability of Occurrence
Acciedent--Question (1)
of
4. Increase in Probability of Occurrence of a
Malfunction of Equipment Important to
Safety--Question (3) . . . . . . . . . .
5. Increase in Consequences of Accidents or
Malfunctions of Equipment Important to
Safety--Questions (2) and (4) . . . . .
in
I-1
I-1
II-1
II-1
II-1
II-3
II-5
II-6
III-1
III-1
III-3
III-3
III-4
III-5
III-6
III-6
III-6
IV-1
IV-1
IV-2
IV-3
IV-4
6. Possible Malfunction or Accident of a Different
ii DOE 5480.21
12-24-91
Type--Questions (5) and (6) . . . . . . . . . . . . . . . . . . IV-5
7. Margin of Safety as Defined in the Bases of any Technical Safety
Requirement--Question (7) . . . . . . . . . . . . . . . . . IV-5
FIGURES
FIGURE II-1 What Constitutes a Change? . . . . . . . . . . . . . II-4
FIGURE III-1 USQ Flow Process Input/Output . . . . . . . . . . . III-2
Section 9
FIGURE IV-1 Example of Margin of Safety . . . . . . . . . . . . . IV-8
ATTACHMENTS
Attachment IV-I. . . . . . . . . . . . . . . . . . . . . . . .Page IV-9
DOE 5480.21
12-24-91
1-1 (and I-
CHAPTER I
GENERAL INTRODUCTION
1. Background.
The Unreviewed Safety Question Order has a primary role of preserving the
DOE authorization basis for each nuclear facility while allowing for
“operational” flexibility. The concept of the Unreviewed Safety Question
was established to allow contractors to make physical and procedural
changes and to conduct tests and experiments without prior DOE approval,
as long as these changes do not explicitly or implicitly affect the
authorization basis of the facility or result in a Technical Safety
Requirement change.
2. Purpose.
The purpose of the following Chapters and Attachment IV-I is to assist
facilities in the proper implementation of the Order and to present a
method by which contractors can achieve compliance. The guidelines
presented in Chapters I-IV set forth minimum standards for contractor
compliance. While it is expected that methods of compliance may vary, the
level of compliance should not. Attachment I to this Order is not
considered to be a requirement of this Order but has been provided as an
example for the implementation of the Unreviewed Safety Question review
process.
DOE 5480.21
12-24-91
II-1
1.
2.
CHAPTER II
APPLICABILITY
Background.
a. This Order is applicable to all aspects of safety relied upon for
facility authorization. This includes both hazardous material and
radiological consequences at the applicable nuclear facilities.
b. All changes to a nuclear facility require analysis, but those that may
affect the authorization basis require completion of a safety
evaluation in accordance with this Order. Despite this qualification,
the applicability of this Order is broad. It covers most nuclear and
nonnuclear equipment and supporting systems (e.g., a change to a cable
tray that may affect the redundancy or separation of systems assumed
redundant in the safety analyses falls under this Order). Nonsafety-
related systems are not excluded from the scope of this Order if they
could affect the proper operation of safety systems, structures, or
components relied upon for facility authorization (e.g., losses of
certain nonsafety-related systems may represent critical operational
occurrences identified as initiators in the accident analysis).
Therefore, changes to nonsafety-related systems must be evaluated and
may be determined to involve a USQ. Physical interactions may also
fall under the purview of this Order. For example, the installation
of a nonseismically supported piece of equipment above a seismically
qualified component designed to perform a safety function explicitly
or implicitly assumed in the safety analyses may constitute a USQ.
Changes invalidating the environmental qualification of components
assumed to function in safety analyses may also be considered a USQ.
That is, any change that has the potential to alter the ability of a
structure, system, or component to meet its expected performance based
on the accident analyses may involve a USQ. Changes include
previously undiscovered conditions, operational incidents, or results
of new analyses or reanalyses that deviate from those described in the
safety analyses or that could reduce existing margins of safety. The
following sections discuss the types of changes, tests, and
experiments as well as discoveries and inadequacies that are within
the purview of this Order.
Section 10
Changes in the Nuclear Facility as Described in Safety Analyses.
a. This Order only requires safety evaluations for changes to a nuclear
facility that alter the design, function, or method of performing the
function of a structure, system, or component (SSC) described in the
safety analyses either by text, drawing, or other information relied
upon as the authorization basis. The safety analyses include
descriptions of many SSCs, but a nuclear facility also contains many
II-2 DOE 5480.21
12-24-91
SSCs not explicitly described in the safety analyses. These can be
components, subcomponents of larger components, or even entire
systems. A common question is whether written safety evaluations
should be performed only for changes to SSCs explicitly described in
the safety analyses. The answer is “no” because changes to SSCs that
are not explicitly described in the safety analyses can have the
potential for altering the function of SSCs explicitly described in
the safety analyses. An example would be the replacement of a relay
in the overspeed trip circuit of an emergency diesel generator (EDG)
with a nonequivalent relay. The relay is not described in the safety
analyses, but the overspeed trip circuit and the EDG should be. The
replacement of the relay might change the performance or design of the
overspeed trip circuit as described in the safety analyses. If so, a
safety evaluation would be required. In such cases, the recommended
approach for deciding whether a modification involves a change to the
nuclear facility as described in the safety analyses is to consider
the larger SSCs of which the SSC being modified may be a part. If the
SSC is part of a larger SSC described in the safety analyses, and if
the change alters the design, function, or method of performing the
function of the larger SSC as described in the safety analyses, then a
safety evaluation is required.
b. The necessity to distinguish between changes and routine maintenance
activities is an important consideration. Routine maintenance
activities do not require review under this Order, except for those
activities that are not enveloped by current analyses or might violate
a Technical Safety Requirement (TSR). Examples of routine maintenance
activities include calibration, refurbishment, replacement with an
equivalent component, and housekeeping. (An equivalent component may
be identical, meet all design and seismic specifications and quality
class, or have been demonstrated and documented to be equivalent. )
However, there are some plant activities that may not clearly be
maintenance. Plant heat exchanger tube plugging where limits are not
specified provides an example. It may be necessary to do a safety
evaluation to assure that normal and accident heat removal capability
is preserved and pumps continue to deliver adequate flow with some
tubes plugged. Systems or components removed from service for
maintenance should be covered by the TSRs for allowable outage times,
permissible mode conditions, and permitted reduction in redundancy. A
safety evaluation therefore need not be performed for these
activities. However, for systems or components that are included in
safety analyses for the nuclear facility, and for which allowed outage
times are not included in the TSRs, a safety evaluation should be
completed.
Section 11
c. Understanding the term “change” as it applies to modes of operation or
facility processes is also important. For example, when a facility is
designed to accommodate several nuclear processes but must modify
equipment line-up to accommodate another process, this change in the
equipment line-up does not constitute a change under this Order if the
DOE 5480.21 II-3
12-24-91
change is performed in accordance with approved procedures and was
considered within the authorization basis of the facility.
d. Temporary changes to the nuclear facility should be evaluated to
determine whether an Unreviewed Safety Question exists. Examples of
temporary modifications include jumpers and lifted leads, temporary
lead shielding on pipes and equipment, temporary blocks and bypasses,
temporary supports, and equipment used on a temporary basis. The fact
that a change to nonsafety-related equipment not described in the
safety analyses can indirectly affect whether equipment important to
safety can perform its intended function makes evaluation of temporary
modifications an important consideration. For example, if nonsafety-
related equipment is mounted above a safety-related component in such
a manner that it could fall and damage the safety-related component
during an earthquake, the seismic evaluation of the safety-related
component is changed. This would be a change to the nuclear facility
as described in the safety analyses and would require a written safety
evaluation. Seismic qualification, missile protection, flooding
protection, fire protection, environmental qualification, high-energy
line breaks, and masonry block walls are some of the areas where
changes to nonsafety-related equipment can result in changes to
safety-related equipment through indirect or secondary effects. The
conservative approach is to provide a written safety evaluation for
any change to the nuclear facility, whether discussed in safety
analyses or not. However, it is possible that some changes can be
justified as not requiring evaluations under this Order, provided
screening criteria are developed that will ensure that there are no
indirect or secondary effects of the change. In this case, the
screening criteria are relied upon to ensure that the change does not
introduce an Unreviewed Safety Question.
e. The actual modification implementation process (e.g., work
authorization system) used in the field should be reviewed for
possible development of Unreviewed Safety Questions. Changing plant
configurations while work is in progress may involve an Unreviewed
Safety Question even though the modification, when completed, may not.
f. To determine whether the proposed change alters the design, function,
or method of performing the function of the SSC, an engineering
evaluation and a thorough understanding of the design basis of the
system involved are essential. Examples of questions that could be
considered are shown in Figure II-l.
g. For any nuclear facility in which the design basis had to be changed
to make it agree with the as-built condition, the change could
constitute a change to the facility as described in the safety
analyses and may therefore require a safety evaluation, even though no
physical change took place in the facility.
II-4 DOE 5480.21
Changes
(a) Does the change add, delete, or convert an automatic or manual feature
of the SSC?
(b) Does the change introduce new system interactions?
(c) Does the change alter the seismic qualification, environmental
qualification, or quality group classification of SSC?
Section 12
(d) Does the change replace a component with equipment equivalent to that
of the old component? For example, are the instrument response times,
ranges, and design pressures and temperatures equivalent to those of
the old instrument? Are the pump flow/head characteristics, design
temperature and pressure, motor size, and controls equivalent to those
of the old pump? Are the valve operating times, failure positions,
sizes, design temperatures and pressures, valve operators, and controls
equivalent to those of the old valves? Are the piping materials,
design temperatures and pressures, supports, insulation, and routing
equivalent to those of the old piping? Are the fuel fission product
barriers and operating characteristics enveloped by previous analyses?
Will the new electrical loads effect the diesel generator loading
sequence or the design capability?
12-24-91
Procedures
(1) If, in the description of waste system in the safety analysis, the
contractor states that the Shift Supervisor will authorize all liquid
releases, a safety evaluation to meet the requirements of 5480.USQ
would be required before assigning this function to another individual.
However, if the safety analysis states that liquid releases will be
authorized as detailed by plant procedures, redesignation of the
authorization function would not require a safety evaluation.
(2) If the nuclear facility startup procedure, as described in the safety
analysis, contains eight fundamental sequences, a decision to eliminate
one of the sequences would require a safety evaluation. However,
consolidation of the eight fundamental sequences, which did not alter
the basic functions performed, would not require a safety evaluation.
Figure II-1
What Constitutes a Change?
DOE 5480.21
12-24-91
II-5
3. Changes in the Procedures as Described in Safety Analyses.
a.
b.
c.
There are three types of procedure changes to be considered. First,
if a procedure is not contained or described in the safety analyses,
it would not require a USQ evaluation to be performed before a change
an be implemented. Second, changes to procedures simply listed, and
not outlined, summarized, or described in the safety analyses, do not
require evaluation in accordance with this Order. Finally, changes to
procedures that are outlined, summarized, or described must be
evaluated in accordance with this Order if the outline, summary, or
description in the safety analyses are impacted.
Procedures are not limited to those items specifically identified as
procedure types (e.g., operating, chemistry, system, test,
surveillance, and emergency plan) but could include anything described
in the safety analyses that defines or describes activities or
controls over the conduct of work. If changes to these activities or
controls are made, such changes qualify as changes to procedures as
described in the safety analyses, and the changes must be evaluated.
In instances when procedural modifications are implementing
operational changes, such as setpoint changes, while the procedure
itself may not meet the requirement for evaluation, in accordance with
this Order, the operational change should be evaluated to assure it
does not impact-authorization basis limits or supporting safety
analyses.
Contrasting examples of safety analyses procedures, as described above,
are shown in Figure II-1.
Section 13
4. Conduct of Tests or Experiments Not Described in Safety Analyses. Written
safety evaluations are required for tests or experiments not described in
safety analyses or other approved documentation that provide the
authorization basis of the nuclear facility. The intent of the criterion
of this Order is to require safety evaluations of tests and experiments
that are not described in the safety analyses that might affect safe
operations. By definition, these are tests and experiments that could
degrade the margins of safety during normal operations or anticipated
transients or degrade the adequacy of structures, systems, or components
to prevent accidents or mitigate accident conditions. Thus, previously
evaluated tests do not require written safety evaluations under this
Order. For example, for preoperational tests, surveillance tests,
functional tests, and startup tests that are performed regularly, safety
evaluations are not required every time a test is performed. However,
one-of-a-kind tests used to measure the effectiveness of new techniques or
a new system configuration that might affect systems important to safety
will require evaluation before they can be conducted. Post-modification
testing should be considered and included in the safety evaluation for the
modification.
II-6 DOE 5480.21
12-24-91
5. Discovery of Analytic Errors, Omission, or Inadequacies.
a. Written safety evaluations are required for instances where discovery
of an analytic error, omission, or inadequacy present the potential
for an Unreviewed Safety Question. These analytic errors, omissions,
or inadequacies must have the potential for impacting the
authorization basis, thereby calling into question information
explicitly or implicitly relied upon in the facility safety analyses
or by reducing the margins of safety as defined in the Technical
Safety Requirements. The intent here is to assure that the operations
are conducted in a safe manner that is consistent with the
authorization basis.
b. Because an analytical error, omission, or inadequacy as specified
above has the potential for calling into question information relied
upon for authorization of operations, DOE requires the following: (1)
the contractor shall immediately notify the PSO; (2) shall take steps
assuring that operation is conducted in a mode or manner within the
authorization basis, despite the analytic discrepancy; and (3) the
contractor shall complete a safety evaluation and submit it to the PSO
prior to removing any operational restrictions implemented to
compensate for the analytical discrepancy.
c. Implementation of this Order in these instances will provide a measure
of the safety significance of discovered analytic discrepancies. If a
USQ is determined to be present, this safety evaluation will require
not only DOE review but DOE approval, prior to removing any
operational restrictions.
DOE 5480.21
12-24-91
III-1
CHAPTER III
1. Introduction.
IMPLEMENTATION GUIDANCE
a. Since it has been established that this order is intended to allow for
facility changes as long as these changes do not impact the
authorization basis of the facility, two basic elements must be
defined in order to properly implement a USQ program.
Section 14
b. First, each facility must identify the methods by which facility
changes can be made (i.e., are changes made under a modification
process, nonconformance processes, maintenance processes, etc.).
After these methods have been identified, each facility must determine
what constitutes an acceptable means to make a change. That is, the
contractor must clearly control the facility change process and must
perform and document changes in accordance with approved procedures.
Performing a modification under the guise of maintenance is not
acceptable because the proper control processes to analyze the
proposed change and document its outcome would probably be absent.
Identification of all means for performing a change is necessary
because each one provides a direct input into the USQ process and must
be integrated accordingly.
c. Second, in order to determine what constitutes a USQ, an understanding
of what constitutes the facility’s authorization basis must be
defined; it is this basis that ultimately provides the acceptable
bounds of operation without requiring prior DOE approval.
2. Governing Process. Once the contractor organization has determined the
various sources of a change, it must then determine the process by which
these sources of changes should be integrated into the USQ review process.
This process should ensure that the need for completion of a safety
evaluation is not overlooked and that this process is integrated into
existing procedures or that new procedures are developed, as necessary.
Figure III-l illustrates a method for integrating the requirements of this
Order within a hypothetical change process. It is recommended that each
facility develop its own change flow process and that this process and its
integration be controlled by a USQ governing procedure. This procedure is
termed a governing procedure because its purpose is to define clear
relationships with the requirements of this Order and other change
procedures, including design procedures and configuration control
programs. Its purpose is to govern the USQ process and not to implement
the specifics of the Order itself.
III-2 DOE 5480.21
12-24-91
Figure III-1
USQ Flow Process
Input/Output
DOE 5480.21 III-3
12-24-91
3.
4.
Understanding the Authorization Basis. Although the term authorization
basis has been defined, it is important to understand how this concept
relates to the language and terms used in the Order.
a. The Order consistently refers to the safety analyses. These safety
analyses are intended to define those aspects of design and operations
that are important to safety and therefore those aspects that DOE
relies upon to allow initial and continued operations. Although
ideally all changes made to a facility would be analyzed, documented,
and incorporated into the Safety Analysis Report, thus providing a
complete authorization basis, such thoroughness has rarely occurred in
the past. In addition, often times when facility operations require
the completion of different processes (campaigns) the safety analysis
supporting individual processes may or may not be incorporated into
the Safety Analysis Report.
Section 15
b. When DOE facilities were first authorized to operate, it was not
anticipated that the need for facility modifications would be
implemented with the frequency that has proven to be necessary. As a
result, the need for elaborate configuration and modification controls
were not clearly understood. Because of this, many changes have taken
place at facilities and the supporting documents and analyses have not
always been integrated into a single facility SAR. Hence, the
authorization basis of the facility may not be reflected in total in
the current facility SAR. For this reason, the language in this Order
referring to safety analyses is intended to mean the facility
authorization basis. This basis, depending upon the facility, may
reside in several different types of documents. These may include not
only the facility SAR, but historical commitments made by contractors
to support modifications and the imposition of new DOE requirements or
administrative changes. These may also include DOE safety evaluation
reports that modify contractor-proposed changes or analyses. The
intent of this Order is to preserve the authorization basis, and, if
this basis is not reflected in total in the SAR, the contractor must
define that population of documents comprising the various elements of
the authorization basis and must use this defined population of
documents as the basis for performing safety evaluations under the
requirements of this Order.
c. It is expected that, as an initial step toward developing a USQ
process, each contractor will define for their facility those aspects
and documents that constitute the authorization basis and identify
these documents within the facility USQ procedures.
Screening Criteria and Procedures.
a. DOE finds that it is acceptable to use screening criteria to limit the
number of proposed actions for which written safety evaluations must
be performed, provided the reasons for exclusion are documented and
well supported. In fact, DOE encourages the use of screening criteria
III-4 DOE 5480.21
12-24-91
because, when properly defined and implemented, the screening criteria
should. assist in reducing the efforts expended for issues of minor
significance and should focus efforts more fully on the aspects of
safety for which this requirement is intended.
b. Screening criteria are intended to be applied to those items that, by
broad definition, enter into the USQ process but for which a detailed
safety evaluation is not necessary. For example, an operational
procedure which is described in the SAR may require a change to
correct a typographical error or include an additional reference to an
equipment list. This change, although by definition within the bounds
of this Order, is not of any safety significance. If the contractor
applied a screening procedure that asks: “Is the change
inconsequential”? (i.e., a spelling or typographical correction,
grammatical change, clarification, or additional note or reference),
the reviewer could document the change and thus avoid the need to
answer the detailed questions of the safety evaluation process.
Section 16
c. A different manner in which screening criteria may be applied is
through categorical exclusions (e.g., different procedure, types). For
the purpose of illustration, maintenance procedures may be considered.
If it is true that no modifications or changes are performed under
maintenance procedures, then a basic premise of performing maintenance
is that the plant will be returned to the exact same “condition” it
was in prior to maintenance. That is, the functional condition will
continue to meet or exceed those performance capabilities set forth in
the authorization basis. A change to a maintenance procedure would
therefore not be governed under this Order. Other requirements, such
as the DOE 4330.4A, may draw some bounds upon the subject and content
of these procedures, but this Order need not be considered. However,
it should be understood that, by applying screening criteria in this
manner, DOE would expect to find a detailed evaluation of why, for
example, a one-time categorical exclusion of maintenance procedures
from the USQ process is acceptable.
d. For physical modifications to the facility, DOE does not believe that
screening criteria would be appropriate. The application of screening
criteria for administrative changes may prove useful, but contractors
must ensure that the use of these criteria do not inappropriately
screen out changes that require safety evaluations.
5. Implementing Procedures.
a. Contractors are required to develop procedures that provide detailed
guidance for the performance and review of USQ determinations. At a
minimum, the procedures shall define the purpose of the procedure; set
forth the procedure’s applicability; provide definitions of
appropriate terms, including those set forth in this Order; include
screening criteria, as appropriate, and the basis for their
application; include detailed guidance on what must be considered and
DOE 5480.21 III-5
12-24-91
evaluated when performing or reviewing a safety evaluation; define the
qualifications needed and responsibilities of personnel performing and
reviewing safety evaluations; and include documentation requirements
for each USQ determination.
b. The purpose of the procedure should reflect the purpose of the Order
and its implementation as defined herein. The applicability of the
procedure should set forth the facility(s) to which it applies and the
types of change processes to which it applies (e.g., use-as-is
nonconformances, corrective actions for violations, procedural
changes, and facility changes). If desired, the contractor may elect
to develop separate implementing procedures for procedural changes
versus facility and administrative changes. If this option is
selected, each procedure should provide enough guidance to permit its
independent use.
c. Contractors are expected to provide detailed guidance and instructions
on how to perform a safety evaluation. This guidance should include,
at a minimum, the information provided in Chapter IV of this guidance
document, refined to include the specifics of the applicable facility.
Instructions and a worksheet similar to that provided in Attachment I
to this Order are recommended. Again, this information should be
adapted to each facility’s specific circumstances and needs.
d. The implementing procedures should address the personnel
qualifications needed in order to perform or review a safety
evaluation. This includes required educational background, years
and/or types of work experience, knowledge of the facility,
understanding of DOE requirements, and familiarity with the facility
authorization basis. Specific responsibilities of those performing or
reviewing safety evaluations should be clearly defined.
Section 17
e. Documentation requirements should also be discussed in the USQ
implementing procedures. They should identify the level of detail
necessary to document performance of the safety evaluation and
conclusions reached; a list of references relied upon to reach this
conclusion as well as guidance for the retention of records should
also be included. Other items cited for inclusion in the implementing
procedures are self-explanatory.
6. Safety Evaluations (USQ Determination). Specific guidance on how to
conduct a safety evaluation is contained in Attachment I to this Order.
The concepts used to develop this process are contained throughout this
document. The intent of this section is not to reiterate these points but
to explain more clearly the scope of a safety evaluation and thereby
clarify its practical uses.
a. A safety evaluation, unlike a safety analysis, is somewhat limited in
scope. When reading this Order, it should be noted that the
definitions of a USQ are based on consequences and probabilities of
III-6 DOE 5480.21
12-24-91
7.
8.
accidents. These accidents, their assumed initiators, and their
consequences focus on the performance capabilities of systems,
structure, and components under presumed conditions. These
performance capabilities are related to facility operations and design
inasmuch as the design and/or specific operations are relied upon to
meet performance requirements set forth in the authorization basis of
the systems, structures, and components in question. When reviewing
or evaluating a change in this manner, those aspects of design that
support the particular performance of systems, structures, and
components relevant to the change will be reviewed, although others
may not be.
b. A contractor may decide to replace an existing gate valve with another
valve type. Under this Order, he/she will evaluate this change to
assure that the new valve meets or exceeds its intended performance
requirements as set forth in the authorization basis. This evaluation
may discuss such issues as closure times, valve leakage, and
suitability of the new valve materials for its particular environment.
This evaluation may conclude that a USQ will not be created. It may
also be true that this new valve contains materials that-have
different corrosive properties than the previous valve, which in turn
requires different maintenance practices. If properly maintained,
this aspect of the design of the new valve may in no way inhibit
performance and would therefore be unlikely to be considered in the
safety evaluation. This aspect of the new valves design should not
and will not be overlooked if a proper safety analysis is conducted.
When making a change, the safety analysis process requires that all
aspects of both design and performance be considered.
c. A safety evaluation is not a substitute for a safety analysis; it
merely serves as a benchmark for whether the authorization basis is
being preserved. Contrary to the above-cited example, a safety
analysis may show that a proposed change is safe, yet the safety
evaluation may determine that this change is an Unreviewed Safety
Question and hence requires DOE approval prior to implementation.
Contractor procedures should clearly establish the differences between
the concepts supporting a safety analysis and those used for a safety
evaluation. The procedures governing the safety analysis process and
the safety evaluation process, although similar in many respects,
should be treated separately.
Section 18
Periodic Reports. At a minimum, all contractors should submit to DOE a
report summarizing all “changes” made under this Order. This requirement
is noted in paragraph 10.
Training. All personnel responsible for performing, reviewing, or
approving USQ determinations should receive initial training on the
application of the Order and of facility-specific procedures. R e t r a i n i n g
is recommended on an interval of every 2 years or as may be proposed by
the contractor.
DOE 5480.21 III-7 (and III-
12-24-91
9. Implementation Schedule. Because the concepts set forth in this Order are
not new to DOE and its contractors, but merely clarify and consolidate
requirements previously implemented within the DOE Order system,
compliance with this Order is expected immediately upon its promulgation.
However, since DOE understands that the manner and rigor with which this
Order is implemented departs somewhat from previous interpretations of
these requirements, implementation of a program in the manner described
herein shall be established based on the schedule set forth below.
a.
b.
c.
Development of USQ Governing Procedures. The manner in which changes
are made at a facility and the formal integration and documentation of
these change processes with the requirements of this Order should be
completed within 9 months of the promulgation of this Order.
Development of Facility-Specific Safety Evaluation Procedures. These
procedures shall be completed within 9 months of the promulgation of
this Order.
Implementation of Initial Training. Initial training should be
completed within 1 year of the promulgation of this Order.
DOE 5480.21
12-24-91
IV-1
CHAPTER IV
EXPLANATION OF TERMS
1. Purpose. This section further defines the terms used in this Order.
a. At the design stage, protection of health and safety is ensured
through the design of the engineered protection of physical barriers
to guard against radioactive and hazardous material releases. These
barriers are designed to fulfill their operational function reliably
by meeting all applicable criteria and standards. The
defense-in-depth philosophy includes reliable design, provisions to
safely terminate accidents, and provisions to mitigate the
consequences of accidents. The health and safety protection functions
are considered in the authorization basis and in the physical design
as documented in safety analyses.
b. This protection philosophy pervades the accident analyses and DOE
safety requirements. To understand and apply the defense-in-depth
philosophy, it is necessary to understand this perspective of
maintaining the integrity of the physical barriers designed to contain
hazardous and radioactive materials. This reflects the fact that
accidents and malfunctions are analyzed in terms of their effect on
physical barriers and that “consequences” are related to acceptance
dose and hazardous-material release limits, depending on the event
frequency. The other terms of the USQ process, such as
“probabilities” and “margin of safety,” have a specific meaning in
this Order and are discussed in detail later.
Section 19
c. The safety analyses for each nuclear facility establish the set of
limiting analyses important to safe operation. The limiting analyses
are utilized to confirm the adequacy of the systems and equipment
design and performance, to identify critical setpoints and operator
actions, and to support the establishment of the Technical Safety
Requirements. The final results of these limiting analyses (accident
analyses) assume that the equipment functions as specified in the
authorization basis under predetermined conditions. The SAR considers
analyses of potential accidents and demonstrates that, under the
assumed accident conditions, the consequences of accidents challenging
the integrity of the barriers will not exceed the criteria established
by DOE in authorizing operation of any particular nuclear facility.
Changes impacting this portion of nuclear facility design and
performance may affect the probability and consequences of accidents,
create new accidents, and reduce margins of safety as defined in the
bases of Technical Safety Requirements.
IV-2 DOE 5480.21
12-24-91
2. Unreviewed Safety Question.
a.
b.
This Order requires that a proposed change, test, or experiment or the
identification of an analytic inadequacy shall be deemed to involve an
Unreviewed Safety Question under any of the following circumstances:
(1) If the probability of occurrence or the consequences of an
accident or malfunction of equipment important to safety
previously evaluated by safety analyses could be increased;
(2) If the possibility for an accident or malfunction of a different
type than any evaluated previously by safety analyses could be
created; or
(3) If any margin of safety, as defined in the basis for any Technical
Safety Requirement, could be reduced.
For the purpose of performing safety evaluations, the three criteria
2a(1) through 2a(3) above can be broken down into seven separate
questions:
(1) Could the proposed activity increase the probability of occurrence
of an accident previously evaluated in the safety analyses?
(2) Could the proposed activity increase the consequences of an
accident previously evaluated in the safety analyses?
(3) Could the proposed activity increase the probability of occurrence
of a malfunction of equipment important to safety previously
evaluated in the safety analyses?
(4) Could the proposed activity increase the consequences of a
malfunction of equipment important to safety previously evaluated
in the safety analyses?
(5) Could the proposed activity create the possibility of an accident
of a different type than any previously evaluated in the safety
analyses?
(6) Could the proposed activity create the possibility of a
malfunction of equipment important to safety of a different type
than any previously evaluated in the safety analyses?
(7) Does the proposed activity reduce the margin of safety as defined
in the basis for any technical safety requirement?
3. Increase in the Probability of Occurrence of Accident--Question (1).
a. To understand how the probability of occurrence of an accident could
be increased, one must first understand how the term “accident” is
DOE 5480.21 IV-3
12-24-91
b.
c.
d.
e.
applied: the term “accidents” refers to the anticipated operational
transients and postulated design basis accidents considered credible
enough to warrant inclusion in the Safety Analysis Report. These
accidents and events define the design features necessary such that
the resultant accident consequences are within the specified DOE
safety limits intended to protect the public health and safety.
Section 20
For each nuclear facility, a group of credible accidents will be
identified. These accidents will then be screened to include in the
safety analyses those accidents that are limiting. For example, for a
particular scenario, several different accidents may be identified,
yet the consequences of one may envelope several others. As a result,
and at a minimum, the limiting (worst-case) accident scenario will be
included in the Safety Analysis Report.
In addition to considering the severity of the consequences of
different accident scenarios, the Safety Analysis Report also
considers the likelihood and frequency of occurrence. This
information provides insight into developing the necessary design
features for mitigation. Although DOE’s facilities categorize and
define frequency groups in different manners, for the purpose of
illustration, we have provided the example below.
For later vintage commercial nuclear power plants, the qualitative
assessment of event frequencies has resulted in the categorization of
four frequency categories:
(1) Normal Operations. Expected frequently or regularly in the course
of operation, modification, maintenance or maneuvering.
(2) Incidents of Moderate Frequency. Any one incident expected per
nuclear facility during a calendar year.
(3) Infrequent Incidents. Any one incident expected per nuclear
facility during the plant lifetime.
(4) Limiting Faults. Not expected to occur but could release
significant amounts of hazardous material, thus requiring
protection by design.
Changes that result in a change from one frequency class to a more
frequent class are examples of changes that increase the probability
of occurrence. However, this is not to say that changes within a
category may not also result in an increase in the probability of
occurrence of an accident if there is a clearly discernible increase
in trend. Such compensating effects as changes in the administrative
controls may be used to offset an increase in trend in the probability
of accidents of moderate frequency. Normally, the determination of a
probability increase is based on a qualitative assessment that uses
engineering evaluations consistent with the original safety analysis
IV-4 DOE 5480.21
12-24-91
assumptions. However, if a nuclear facility-specific probability
calculation can be used to evaluate a change in a quantitative sense,
it should be used. Probabilistic Risk Assessments (PRAs) constitute
just one tool used to evaluate safety, and PRA use iS not necessarily
needed to perform safety evaluations.
4. Increase in Probability of Occurrence of a Malfunction of Equipment
Important to Safety--Question (3).
a. The accident analysis assumes the proper functioning of some portion
of safety systems in demonstrating the adequacy of design. The proper
functioning of other systems, although not specifically identified in
the accident analysis, is credited in an indirect sense. The bounds
of the accident analysis are extended to include these systems. For
example, a change that does either of the following is a change that
increases the probability of occurrence of a malfunction of equipment
important to safety:
(1) Degrades the performance of a safety system assumed to function in
the accident analysis below the authorization and/or design basis.
(2) Increases challenges to safety systems assumed to function in the
accident analysis such that safety system performance is degraded
below the authorization and/or the design basis without
compensating effects.
Section 21
b. Whether there is an increase in the probability of occurrence of a
malfunction is normally determined by using a qualitative engineering
evaluation. As noted in the previous section, a probability
calculation can be used to demonstrate the change in probability in a
quantitative sense, if available and practical.
5. Increase in Consequences of Accidents or Malfunctions of Equipment
Important to Safety--Questions (2) and (4).
a. Safety analyses of a nuclear facility provide acceptance criteria and
frequency relationships for “conditions for design.” By defining what
changes represent an “increase in consequences” pursuant to this
Order, it must be recognized that the objective of this requirement is
the protection of health and safety. Therefore, an increase in
consequences must involve an increase in hazardous material releases
and/or radioactive doses above the worst-case limiting consequences in
the authorization basis that serves as the established acceptance
limit. Changes in barrier performance that do not result in increased
consequences are appropriately addressed in this document under
“Margin of Safety. ” For nuclear facilities, DOE may require by
reference, compliance with the requirements of 10 CFR 20, Standards
for Protection Against Radiation, and 10 CFR 100, Reactor Site
Criteria. On-site consequences that may involve a USQ are those that
restrict access to vital areas or otherwise impede actions to mitigate
DOE 5480.21
12-24-91
IV-5
the consequences of nuclear facility accidents. For example, 10 CFR
20 provides the requirements for determining maximum acceptable levels
of radioactivity (airborne or liquid pathway) in restricted and
unrestricted areas during normal operations. For accidents (e.g.,
radwaste system component failures) that affect a boundary for which a
10 CFR 20 limit has been established, the threshold for an increase in
consequences would be the 10 CFR 20 limit, unless a separate limit in
the authorization basis is more restrictive, in which case it would
serve as the acceptance limit.
b. An increase in the calculated off-site consequences resulting from a
change, test, or experiment does not represent an increase in
consequences as long as the established acceptance limits for the
accident continues to be met. For example, if a change affects the
consequences of a ventilation system failure and the new off-site dose
or hazardous material consequence releases remain within the
criterion, and the authorization limit is still met, there is no
increase in consequences.
6. Possible Malfunction or Accident of a Different Type--Questions (5) and
(6).
a. An accident or malfunction that involves an initiator or failure not
considered in the nuclear facility safety analyses is potentially an
accident or malfunction of a different type. An example would be
turbine missiles from a gas turbine added as an alternate power
source. Certain accidents or malfunctions are not treated in the
nuclear facility safety analyses because their effects are bounded by
other related events that are analyzed. For example, a postulated
pipe break in a small line may not be evaluated within the safety
analyses of the nuclear facility because it has been evaluated to be
less limiting than a pipe break in a larger line within the same area.
Therefore, if a proposed design change would introduce a small,
high-energy line break into an area that already had a pipe break from
a larger high-energy line analyzed for energy release, pipe whip,
etc., postulated breaks in the smaller line should not be considered
an accident or malfunction of a different type.
Section 22
b. The possible malfunctions or accidents of a different type are limited
to those that are considered to be as likely to happen as those
considered in the authorization basis. For example, a seismic-induced
failure of a component that has been designed to the appropriate
seismic criteria will not cause a malfunction of a different type.
However, a change that increases the probability of an analyzed
accident, or a newly discovered accident previously thought incredible
to the point where it becomes as likely as the accidents considered in
the authorization basis, creates a possible accident of a different
type. For example, there are a number of scenarios, such as multiple
tube ruptures in heat exchangers, that may have been analyzed
extensively. However, these scenarios are of such low probability
IV-6 DOE 5480.21
12-24-91
that they may not have been considered as part of the design basis.
If a change is made so that a scenario such as multiple tube rupture
becomes credible in heat exchangers, the change would be considered to
create the possibility of an accident of a different type. A possible
malfunction of a different type could be created by a change that adds
a new single failure. It would have to be analyzed for meeting the
criteria of the safety analyses of the nuclear facility. In some
instances, these potential accidents are already in the design bases
or are presented in the safety analyses of the nuclear facility.
7. Margin of Safety as Defined in the Bases of any Technical Safety
Requirement--Question (7).
a.
b.
c.
Technical Safety Requirements (TSRs) set forth the minimum acceptable
limits for operation under normal and specified failure conditions;
they ensure that the available equipment and initial conditions meet
the assumptions in the accident analysis. TSRs are a distillation of
those aspects of the Safety Analysis Report that are required in order
to assure the performance of systems, structures, components, and
personnel as relied upon and defined in the SAR. The bases for TSRs
define the acceptance limits from which margins of safety may be
determined.
To the maximum extent practicable, the bases for a TSR should
explicitly define or address the margin of safety. If the bases do
not specifically address a margin of safety, then the safety analyses
and other appropriate authorization basis documents should be reviewed
to determine whether the proposed change, test or experiment, or new
information has or would result in a reduction in a margin of safety.
The margin may be implicitly rather than explicitly expressed as a
numerical value. A margin of safety defined in the Bases Section of a
TSR document may depend on a parameter other than one of the process
variables. Therefore, the precise determination of a numerical value
associated with a change is not always required to comply with this
Order. Implicit margins are, for example, conditions for acceptance
for a computer code, method, or industry accepted practice. It may be
sufficient to determine only the direction of the margin change (i.e.,
increasing or decreasing).
For purposes of performing the safety evaluation, the margin of safety
is the range above the acceptance limit reviewed and approved by the
DOE as part of the authorization process. In making the judgment on
whether the margin is reduced, the decision should be based on
physical parameters or conditions that can be observed or calculated.
Where a change in margin is so small or the uncertainties in
determining whether a change in margin has occurred are such that it
cannot be concluded reasonably that the margin actually has changed
(i.e., there is no clear trend toward reducing the margin), the change
need not be considered a reduction in margin.
Section 23
DOE 5480.21 IV-7
12-24-91
d. With regard to the margin of safety, the change, test or experiment,
or new information should be evaluated with respect to safety limits,
limiting safety system settings (LSSS), limiting conditions of
operation (LCO), as well as design parameters for systems and
individual components. Various margins exist between strain or
failure and a TSR safety limit, the TSR safety limit and design value,
and the LSSS and the operating value or limit. These margins are
based on, for example, assumptions of initial conditions, conservatism
in computer modeling and codes, allowance for instrument drift and
system response time, redundancy and independence of components in
safety trains, and plant response during operating transient and
accident conditions. Some modifications may affect these margins in
opposite directions. However, a change in the margin of safety above
the acceptance limit is the focus of this Order.
e. A change in initial conditions, or in a system response time, or in
some other parameters affecting the course of an accident analysis
supporting the bases of TSRs must be evaluated to determine whether
the change causes the acceptance limit to be exceeded for that
analysis. If the limit is exceeded, the change would involve a
reduction in the margin of safety pursuant to this Order.
f. It is recognized that there are “margins” associated with safety
analyses to account for uncertainties in the design, construction, and
operation of a nuclear facility (e.g., conservatism in computer
modeling and codes and allowances for instrument drift and for system
response time). These “margins” may be reduced by contractors,
provided specific acceptance conditions, criteria, and limits (e.g.,
models, tests, uncertainties, and methodology) are not invalidated.
g. The determination of whether a reduction in margin is involved is
based on the results of the analyses and not on the change itself.
For example, an increase in initial conditions (not already limited by
TSRs) in the nonconservative direction can be compensated for by
lowering a setpoint or reallocating analyses conservatism. If the
analyses results continue to be bounded by the acceptance limit, a
reduction of margin is not involved.
h. To develop the definition of “margin of safety,” it is necessary to
define the relationship of operating points, acceptance limits, and
actual failure points (see Figure IV-1). To do this, one must
determine the original authorization basis of the parameter in
question. A margin of safety defined in the Bases Section of the TSR
may depend on a parameter other than one of the process variables.
However, a change in the margin will depend only on an increase in the
result beyond an established acceptance limit.
IV-8 DOE 5480.21
12-24-91
Figure IV-1
Example of Margin of Safety Using
Containment Overpressure Transient
DOE 5480.21
12-24-91
Attachment IV-1
Page IV-9
ATTACHMENT IV-I
1. Safety Evaluation Process.
If it has been determined that a USQ review is required, the safety evaluation
can be approached by providing an answer to each of the seven questions
identified using the interpretations given in Chapter IV. If any of these
questions is answered “yes,” the change is considered to be an Unreviewed
Safety Question. An appropriate justification for each answer should be
recorded. The examples given in the following subsections are provided to
help the reviewer identify potential Unreviewed Safety Questions. They are
not meant to be examples of Unreviewed Safety Questions nor are they intended
to be requirements. They are only intended as examples, Determination of an
Unreviewed Safety Question requires consideration of the safety analyses of
the nuclear facility or other approved documentation that provides the
authorization basis for design or operations, and the specific details of the
issue.
Section 24
1.1 Could the Proposed Activity Increase the Probability of Occurrence of an
Accident Previously Evaluated in the Safety Analyses?
In answering this question, the first step is to determine what accidents,
that have been evaluated in the previously approved safety analyses, may be
affected by the proposed activity. A determination is made as to whether the
likelihood of the accident occurring would be increased. The following
examples may provide a useful approach in making this determination.
(a) Will the proposed activity meet the design, material, and
construction standards applicable to the system or equipment being
modified? If the answer is “yes,” this aspect of the proposed
change is judged not to increase the likelihood of an accident
occurring. If the answer is “no” to any of the items, either a
justification for saying there is no increase in the likelihood of
the accident occurring will need to be developed or it is
concluded that the likelihood of the accident occurring is
increased.
(b) Will the proposed activity affect overall system performance in a
manner that could increase the probability of an accident?
Examples of questions to ask are:
(1) Will the proposed activity use instrumentation with
accuracies or response characteristics that are different
than existing instrumentation such that an accident is more
likely to occur?
Attachment IV-1
Page IV-10
(2)
(3)
(4)
DOE 5480.21
12-24-91
Will the proposed activity cause systems to be operated
outside their design or testing limits? Examples include the
following: imposing additional loads on electrical systems,
operating a piping system at higher than normal pressure,
and operating a motor outside of its rated voltage and
amperage.
Will the proposed activity cause system vibration or water
hammer, fatigue, corrosion,thermal cycling, or degradation
of the environment for equipment important to safety that
would exceed the design limits?
Will the proposed activity cause a change to any system
interface in a way that would increase the likelihood of an
accident?
If the proposed activity affects overall system performance in a manner
that could lead to an accident or cause an accident previously evaluated
to shift to a higher frequency category, then the issue would increase
the probability of an accident previously evaluated in safety analyses.
1.2 Could the Proposed Activity Increase the Consequences of an Accident
Previously Evaluated in Safety Analyses?
In answering this question, the first step is to determine which
accidents evaluated in the safety analyses may have their radiological
and hazardous material consequences altered as a direct result of the
issue. The next step is to determine whether the issue does, in fact,
increase the consequences of any of the accidents evaluated in the
safety analyses. Examples of questions that assist in this
determination are as follows:
(1) Will the proposed activity change, degrade, or prevent actions
described or assumed in the accident analyses?
(2) Will the proposed activity alter any assumptions previously made
in evaluating the radiological and hazardous material consequences
in the accident analyses?
(3) Will the proposed activity play a direct role in mitigating the
radiological or hazardous material consequences assumed in the
accident analyses?
(4) Will the proposed activity affect any fission product or any
radioactive or hazardous material barriers?
Section 25
If it is determined that the issue does have an effect on the
consequences of any accident analysis previously described in safety
analyses, then the contractor should either--
DOE 5480.21 Attachment IV-1
12-24-91 Page IV-11
(1) Demonstrate and document that the safety consequences of the
accident described in the safety analyses are bounding for the
proposed activity (e.g., by showing that the results of the
previous analyses bound those that would be associated with the
issue); or
(2) Revise and document the analysis, taking into account the proposed
activity and compare the consequences to the acceptance limits in
the prior analyses.
1.3 Could the Proposed Activity Increase the Probability of Occurrence of a
Malfunction of Equipment Important to Safety Previously Evaluated in
Safety Analyses?
In answering this question, the first step is to determine what
important to safety (ITS) equipment could be impacted by the proposed
activity. Then evaluate the effects of this activity on ITS equipment.
This evaluation should include both direct and indirect effects. Direct
effects are those where the issue affects the equipment (e.g, a motor
change on a pump). Indirect effects are those in which the issue
impacts one piece of equipment, and this piece of equipment affects the
ITS equipment.
After identifying the impact of the issue on the ITS equipment, a
determination is made if an increase in the probability of a malfunction
of the ITS equipment has occurred. The following are examples of
questions that can be used in making the determination.
(a) Will the proposed activity meet the original design specifications
for materials and construction practices when the following
questions are considered:
(1) Are the seismic specifications met (e.g., use of proper
supports, proper lugging at terminals, and isolation of
lifted leads)?
(2) Are separation criteria met (e.g., minimum distance between
circuits in separate divisions, channels in the same
division, and jumpers run in conduit)?
(3) Are the environmental qualification criteria met (e.g., use
of materials qualified for the radiation or thermal
environment in which they will be used)?
(b) Will the proposed activity degrade structure, system or component
(SSC) reliability by--
(1) Imposing additional loads not analyzed in the original
design?
Attachment IV-1
Page IV-12
(2)
(3)
(4)
(5)
(6)
DOE 5480.21
12-24-91
Deleting or modifying system/equipment protection features?
Downgrading the support system performance necessary for
reliable operation of the ITS equipment?
Reducing system/equipment redundancy or independence?
Increasing the frequency of operation of ITS
system/equipment?
Imposing increased or more severe testing requirements on
ITS system/equipment?
If the issue adversely impacts the ITS equipment, the likelihood of
equipment malfunction may be increased. A “yes” answer to any question
in (b) above does not mean that there is a negative impact on safety.
However, it would indicate the existence of a USQ and the need for
justification that the equipment can provide the intended safety
function.
1.4 Could the Proposed Activity Increase the Consequence of a Malfunction of
Equipment Important to Safety Previously Evaluated in Safety Analyses?
Section 26
This question is asking whether, assuming a malfunction of ITS
equipment, the issue would result in increased hazardous material or
radiological consequences. For example, consider a change such that a
safety-related valve now fails in the closed position where previously
it failed in the open position. If failing the valve in the closed
position results in an increase in consequences of an accident, then
this is a change that increases the consequence of a malfunction of
equipment important to safety.
1.5 Could the Proposed Activity Create the Possibility of an Accident of a
Different Type than any Previously Evaluated in Safety Analyses?
In answering this question, the first step is to determine the types of
accidents that have been evaluated in the prior safety analyses. The
types of credible accidents that the issue could create can then be
identified. Comparing the two lists will determine the answer to the
question.
1.6 Could the Proposed Activity Create the Possibility of a Malfunction of
Equipment Important to Safety of a Different Type than any Previously
Evaluated in Safety Analyses?
This question asks whether the issue could lead to a failure mode of a
different type than the types evaluated in previous safety analyses. In
answering this question, the types of failure modes of ITS equipment
that have previously been evaluated in safety analyses affected by the
issue are identified. Then types of failure modes that the issue could
create are identified. Comparing the two lists can provide an answer to
DOE 5480.21 Attachment IV-1
12-24-91 Page IV-13
the question. An example that might create a malfunction of a different
type could be the relocation of equipment so that it now becomes
susceptible to flooding. Another might be replacement of a mechanical
control system on equipment important to safety with a digital control
system that can potentially fail in a different mode.
1.7 Does the Proposed Activity Reduce the Margin of Safety as Defined in the
Basis for any Technical Safety Requirement?
To answer this question, it is first necessary to determine whether a
margin of safety as defined in the bases for any TSR is involved. To do
this, the Bases Sections of all applicable TSR documents should be
consulted. If a margin of safety is defined there, or if any
authorization basis document defines a margin of safety that TSRs were
derived from, then a margin of safety as defined is involved and the
effects of the issue on the margin should be assessed.
Safety Evaluation Performance
In performing a safety evaluation of an issue, one must provide a
comprehensive justification for the USQ determination. Consistent with
the intent of this Order, these explanations should be complete in the
sense that a qualified independent reviewer could draw the same
conclusion.
The importance of the documentation is emphasized by the fact that
experience and engineering knowledge other than models and experimental
data are frequently relied upon in performing the safety evaluation.
Since an important goal of the safety evaluation is demonstration that
the authorization basis is being maintained, the items considered by the
evaluator must be clearly stated.
By documenting the effects that were considered, the independent
reviewers will be able to assess the adequacy of the review and its
conclusions. To provide an example of appropriate documentation, an
example safety evaluation worksheet follows. The format of the
worksheet is not set forth as a requirement but is intended to assist
the contractor-in development of facility specific procedures.
Section 27
Attachment IV-1
Page IV-14
DOE 5480.21
12-24-91
EXAMPLE SAFETY EVALUATION WORKSHEET
Safety Evaluation Number: Revision No.
Facility Issue Number: Revision No.
Facility Issue Title:
1.
2.
3.
4,
1.
2.
3.
4.
5.
INTRODUCTION
Description of the aspects of the issue being eva
expected effects.
Identification of parameters and systems affected
luated and its
by the issue.
Identification of the credible failure modes associated with the issue.
References to location of information used for the safety evaluation.
PART I: IMPACT ON THE ACCIDENTS EVALUATED AS THE DESIGN BASIS
Identify the design basis accidents reviewed for potential impact by the
issue.
Discuss how the parameters and systems, affected by the issue, impact
the consequences of these accidents.
Identify the design basis accidents, if any, for which failures modes
associated with the issue can be an initiating event.
Discuss the impact of the issue on the probability of occurrence of the
design basis accidents identified in 3 above.
Identify the safety systems and systems important to safety affected by
the issue.
1 For the purposes of this Appendix, “issue” will mean any change, test or
experiment, or new information identified.
DOE 5480.21 Attachment IV-1
12-24-91 Page IV-15
6. Discuss the impact of the issue and/or the failure modes associated with
the issue on the probability of failure of the systems identified.
7. Discuss the impact of the issue on the performance of the safety
systems.
SUMMARY
Yes No
Based on 2 above, does the issue increase the
consequences of a design basis accident?
Based on 4 above, does the issue increase the
probability of a design basis accident?
Based on 6 above, does the issue increase the
probability of a malfunction of a safety system?
Based on 7 above, does the issue degrade the
performance of a safety system below that
assumed in the design basis analysis?
If any of the above is answered “yes,” the issue is an Unreviewed Safety
Question.
Attachment IV-1 DOE 5480.21
Page IV-16 12-24-91
PART II: POTENTIAL FOR CREATION OF A NEW TYPE OF UNANALYZED EVENT
1. Based on Part I, assess the impact of the issue and/or failure modes
associated with the issue to determine whether the impact has modified
the facility response to the point where it can be considered a new type
of accident. Discuss the basis for this determination.
2. Determine whether the failure modes of equipment important to safety
associated with the issue represent a new unanalyzed type of
malfunction. Discuss the basis for this determination.
3. Determine whether the issue, or a failure mode associated with the
issue. increases the probability of an accident to the point where it
should be considered within the authorization/design basis.
SUMMARY
Yes No
Based on 1, 2, and 3 above, does the issue create the potential
for new type of unanalyzed accident or a new type of
malfunction?
If the answer is “yes,” the issue represents an Unreviewed Safety Question.
DOE 5480.21
12-24-91
Attachment IV-1
Page IV-17
PART III: IMPACT ON THE MARGIN OF SAFETY
1. Based on the results identified in Part I, discuss the impact of the
consequences on the protective boundaries.
2. Identify how the protective boundaries, if any, are directly affected by
the issue or a failure mode of the issue.
3. Discuss the impact of the issue on the acceptance limits for the
protective boundaries identified above.
4. Identify the margins of safety related to this issue that are defined in
the bases of Technical Safety Requirements.
SUMMARY
Yes No
1. Based on 1 above, do the consequences of the design
basis accidents exceed the limits for an acceptable
issue?
2. Based on 2, 3, and 4 above, does the issue reduce the
margin of safety provided for the protection
boundaries?
3. Based on 4 above, does the issue reduce other margins
of safety in the bases for the Technical
Safety Requirements that are not related to the
boundaries?
9Attachment IV-I
Page IV-18
PART IV: SAFETY EVALUATION CONCLUSION
Based on the evaluation in Parts I, II, and III, the issue--
Does not constitute an Unreviewed Safety Question.
Does constitute an Unreviewed Safety Question.
Preparer’s Signature
Independent Review Signature
Approval Signature
(Use as many as appropriate)
DOE 5480.21
12-24-91
Date
Date
Date