DOE O 5100.5, Office of Management and Budget - Budget Process
Functional areas: Planning, Programming, and Budgeting
Canceled by DOE N 251.3 and DOE O 130.1.
Superseded By:
DOE O 130.1, Budget Formulation on Sep 29, 1995
DOE N 251.3, Cancellation of Directives on Sep 29, 1995
Version history and related documents
Superseded by
A newer version replaces this document.
- DOE O 130.1Budget Formulation (Sep 29, 1995)
- DOE N 251.3Cancellation of Directives (Sep 29, 1995)
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
DOE-5100.5/TOC
TABLE OF CONTENTS
ISSUE DATE: 07-21-83
LAST CHANGE:
CHANGE DATE:
DOE-5100.5 OFFICE OF MANAGEMENT AND BUDGET - BUDGET PROCESS
TABLE OF CONTENTS
CHAPTER I - GENERAL Page
1. Introduction ................................................... I-1
2. General Policies and Guidelines ................................ I-2
Figure I-1 - Cross Reference of OMB Directives ........ I-2
3. Restrictions on Disclosure of Budget Information ............... I-4
4. Freedom of Information Act (FOIA) .............................. I-5
5. Public Request for Budgetary Information ....................... I-5
CHAPTER II - OFFICE OF MANAGEMENT AND BUDGET - PHASE I
1. OMB Submission ................................................. II-1
a. Overview ................................................... II-1
b. Initial Submission.......................................... II-1
c. Justification - General Guidance............................ II-2
(1) Overview of Budget Justification Material.............. II-2
(2) Funding Levels......................................... II-2
(3) Ranking................................................ II-2
(4) Staffing Control Levels................................ II-3
Figure II-1 - Ranking Sheets........................... II-4
d. Justification - Detailed Guidance........................... II-5
(1) Lead Table............................................. II-5
(2) Summary of Changes..................................... II-5
Figure II-2 - Lead Table............................... II-6
Figure II-3 - Summary of Changes....................... II-7
(3) Narrative.............................................. II-8
(4) Construction Project Data Sheets....................... II-8
Figure II-4 - Financial Schedule - Construction
Projects ................................ II-14
Figure II-5 - Financial Schedule - General Plant
Projects................................. II-14
Figure II-6 - Construction Project Data Sheets - Plant
and Capital Equipment Funded............. II-31
Figure II-7 - Construction Project Data Sheets
Operating Expenses Funded................ II-38
(5) Federal Manpower Justification......................... II-45
(6) Manpower Figures....................................... II-45
Figure II-8 - Summary of Full-Time Equivalents -
Program Organizations.................... II-46
Figure II-9 - Summary of Full-Time - Headquarters Staff
Organizations............................ II-47
Figure II-10 - Summary of Full-Time Equivalents
Operations Offices ...................... II-48
Section 2
e. Computer Materials (Fall Overview).......................... II-49
(1) Checklist for Supplementary Source Document............ II-49
(2) Checklist for Current Services Estimates (SSD-S)....... II-50
2. Other OMB Materials............................................. II-51
a. Telecommunications.......................................... II-51
b. Mayor Computer Requirements................................. II-51
(1) Major Item Identification.............................. II-51
(2) Major Computer Requirements Crosscut Summary........... II-52
(3) Data on ADP Systems.................................... II-52
(4) Initial Submission (OMB Estimates)..................... II-52
(5) Revised Submission (Congressional Estimates)........... II-52
3. Data on Research and Development................................ II-52
Figure II-11 - Report on Obligations for
Telecommunications Systems.............. II-54
4. Data on Environmental Programs.................................. II-55
CHAPTER III - OFFICE OF MANAGEMENT AND BUDGET SUBMISSION - PHASE II
1. Print Materials Submission (Budget Appendix Material)........... III-1
a. Appropriation Language...................................... III-1
b. Program and Financing Schedule.............................. III-1
c. Object Classification....................................... III-2
d. Personnel Summary........................................... III-2
Figure III-1 - End of Year Positions, Fiscal Year FTE
Summary................................. III-4
Figure III-2 - Permanent Positions by Appropriation.... III-5
Figure III-3 - Personnel Summary by Appropriation...... III-6
Figure III-4 - Personnel Summary by Appropriation
by Year................................. III-7
e. Checklist for the Budget Appendix Materials................. III-8
2. Pay Cost Supplementals.......................................... III-9
3. Special Information Submission.................................. III-10
4. Departmental Administration..................................... III-10
Figure III-5 - Organizations Included in Departmental
Administration.......................... III-11
Figure III-6 - Federal Personnel Support Services
Schedule................................ III-12
Figure III-7 - Federal Travel and Transportation of
Persons Schedule........................ III-13
Figure III-8 - Federal Personnel Expenses Summary
Schedule................................ III-14
Figure III-9 - Object Class Funding Summary............ III-15
5. Outlays......................................................... III-16
Figure III-10 - Analysis of Budget Authority,
Obligations and Outlays................ III-17
6. Supplemental Requests........................................... III-18
Figure III-11 - Example Supplemental Budget Request
Memorandum............................. III-21
7. OMB Appeal Process.............................................. III-24
Figure III-12 - FY 19BY Appeal Format.................. III-25
Figure III-13 - Summary of FY 19BY Appeal Item......... III-26
Figure III-14 - FY 19CY Supplemental Agenda............ III-27
Figure III-15 - Summary of FY 19CY Supplemental Appeal
Items.................................. III-28
Section 3
DOE-5100.5/CI
CHAPTER I - GENERAL
ISSUE DATE: 07-21-83
LAST CHANGE:
CHANGE DATE:
DOE-5100.5 OFFICE OF MANAGEMENT AND BUDGET - BUDGET PROCESS
CHAPTER I
GENERAL
1. INTRODUCTION.
a. The OMB Budget submission provides a mechanism for the annual OMB
review of the Department's resource requirements. The OMB budget
represents an update of the Internal Review Budget (IRB) to reflect
the Secretary's decisions on the Department's budget. The
submission should be based on the guidance contained in the
Secretary's budget allowance. The process is initiated in early
August with the issuance of the OMB call letter to the Heads of
Headquarters Elements and selected field elements. Included in the
call letter will be due dates; an approved program structure; a list
of required figures; and any pertinent fiscal and policy information
necessary to prepare the budget request.
b. A statistical table reflecting the final Secretary's allowance will
be issued shortly after the Secretary makes the final budget
decisions and will serve as the control table for the OMB
submission. Following reviews at the Assistant Secretary level the
budget submissions undergo a second review, by the budget analysts
in the Office of Budget, to determine that they accurately represent
Secretarial decisions and are suitably supported by the
justification. When the estimates are received in OMB they are
referred to the examiners assigned to the program involved. They
identify budgetary and programmatic issues of major importance to be
raised for discussion with the Department's representatives at
hearings conducted by OMB. Following the hearings, OMB examiners
prepare their summary of the issues and their recommendations for
the OMB Director's review. The Director's review results in the
initial OMB allowance and provides an opportunity for the principal
officials of OMB to obtain an understanding of the Department's
program operations and budget requests. Analyses are prepared
reflecting significant issues involving the relationship of the
Department requests to the planning ceiling set for the Department
as a result of the spring planning review.
c. In anticipation of receipt of the OMB allowance, the Office of the
Secretary and the Assistant Secretary, Management and
Administration, will inform Departmental Elements of the OMB plans
for passback of the allowances, together with a DOE schedule of
events that will lead to the submission of an appeal document to
OMB. The schedule of events includes dates for submission of formal
appeals and timing of internal DOE reviews.
d. OMB transmits the allowances to DOE in late November. OMB prepares
an allowance fact sheet for each major program receiving an
allowance different than the original DOE request. The fact sheet
includes dollar allowances for current year supplementals, budget
year requests, and 2 out years. Prior to actual receipt of the
allowance, the Office of Budget personnel meet with OMB budget
examiners to obtain additional clarifying information. Based on the
analysis of the OMB allowance the Department undertakes an appeal
process which results in additional supporting justification being
sent to OMB. After analysis of the DOE appeals, OMB informs the
Secretary of their final budget actions. On occasion the OMB may
request hearings or additional information concerning the DOE appeal
data.
Section 4
2. GENERAL POLICIES AND GUIDELINES. General information and policies on
the preparation and submission of budget estimates are contained in OMB
Circular A-11, "Preparation and Submission of Budget Estimates." The
budget request to OMB must conform to the policies and other
requirements of Circular A-11. Circular A-11 sections, cross referenced
against OMB directives and other regulations, provide the additional
guidance necessary for the preparation of estimates (see Figure I-1).
__________________________________________________________________________
| Circular A-11 Circular or |
| Reference Other Regulations Title or Subject |
| ------------- ----------------- ---------------- |
| 13.2 Circular A-19 Procedures for the |
| coordination and |
| clearance of agency |
| recommendations on |
| proposed, pending, and |
| enrolled legislation. |
| |
| 13.5 Circular A-45 (revised), Policies governing |
| A-25 and A-121 charges for rental |
| quarters and related |
| facilities. |
| |
| 13.7 Circular A-10 Responsibilities for |
| disclosure with |
| respect to the budget. |
| |
| 13.2 Executive Order 12291 Reduction of onerous |
| paperwork. |
| |
| 13.3 Circular A-64 Position management |
| system and employment |
| ceiling. |
| |
| 13.3 Circular A-76 Policies for acquiring |
| 13.5(o) commercial or |
| industrial products |
| for Government use. |
| |
| 13.3(12) Circular A-30 Federal Employee |
| Executive Order 11609 Uniform Allowance Act. |
| |
| 13.4(c) Executive Order 12348 Comparative cost |
| Circular A-63 analysis to lease or |
| (Revised) purchase general |
| purpose real property. |
Section 5
| |
| 13.4(d) Executive Order 11490 Design and |
| construction of |
| Federal building |
| including fallout |
| protection. |
| |
| 13.4(e) Circular A-106 Reporting requirements |
| Executive Order 11752 in connection with the |
| Executive Order 12088 prevention, control, |
| and abatement of |
| environmental |
| pollution at existing |
| Federal facilities. |
| |
| 13.4(g) Executive Order 11988 Use of flood plains |
| Executive Order 11990 for construction. |
| |
| 13.4(m) Circular A-18 Policies on |
| construction of family |
| housing. |
| |
| 13.4(n) GSA FPMR Policies on |
| 101-35.2 acquisition of |
| automated data |
| processing equipment. |
| |
| 13.4(p) Circular A-95 Evaluation, review, |
| and coordination of |
| Federal and federally |
| assisted programs and |
| projects. |
| |
| 13.4(r) Circular A-63 Advisory committee |
| management. |
| |
| 13.5 Circular A-112 Methods for estimating |
| outlays. |
|________________________________________________________________________|
Figure I-1
Cross-reference of OMB Directives
3. RESTRICTIONS ON DISCLOSURE OF BUDGET INFORMATION. OMB Circular
A-10,
Revised, "Responsibilities for Disclosure With Respect to the Budget,"
imposes upon Federal officials and employees certain responsibilities
with respect to the executive budget. Attention is specifically
directed to the provisions of this Circular which restrict budgetary
disclosures, as set forth below:
Section 6
"Requirements for confidentiality prior to official transmittal.
The confidential nature of agency submissions, requests,
recommendations, supporting materials, and similar communications
should be maintained, since these documents are an integral part of
the decision making process by which the President resolves budget
issues and develops recommendations to the Congress. Presidential
budget decisions are not final until the budget itself is
transmitted to Congress. Amendments to the budget and supplemental
appropriation requests may also follow the transmittal of the
budget. Budgetary information should not be disclosed in any form
prior to transmittal by the President of the material to which it
pertains. The head of each agency is responsible for preventing
premature disclosures of this budgetary information.
"Agency testimony before and communications with Congress on
budgetary matters. In furnishing information on appropriations and
budgetary matters, representatives of agencies should be aware of
the limitations on such communications, including the limitation
that:
"No estimate or request for an appropriation and no request
for an increase in an item of any such estimate or request...
shall be submitted to Congress or any committee thereof by any
officer or employee of any department or establishment, unless
at the request of either House of Congress." (31 U.S.C. 15)
"Furthermore, agency representatives should be aware of
restrictions upon communications to influence legislation that are
not conducted through proper official channels (18 U.S.C. 1913).
"Clearance of changes in the President's budget. The prohibition
against submissions by agencies to Congress of estimates or
requests for appropriations without the approval of the President
or request of either House of Congress applies to changes in
appropriation language and to changes in the limitations
recommended in the budget. When an agency desires to propose such
changes, written requests will be presented to the Office of
Management and Budget (in accordance with the provisions of OMB
Circular No. A-11). All such requests must be transmitted through
the Office of Budget and must include complete justification as to
the need for the change."
4. FREEDOM OF INFORMATION ACT (FOIA). This Act requires that, with
certain exceptions, identifiable records of the agency must be made
available to the public. Nevertheless, OMB Circular A-10, revised,
states that an agency should not release budgetary documents subject to
the FOIA before the end of the fiscal year to which those records
pertain. Specifically, it reads as follows: "Information available to
the public. An agency may disclose budgetary records of that agency, if
otherwise appropriate, upon a request for such records pursuant to the
FOIA following the end of the fiscal year to which such information
pertains. Although it is not possible to determine merely by the
generic category of records whether an agency would be authorized to
withhold records requested under the FOIA in every instance, most
budgetary documents of an agency that are subject to the FOIA should be
exempt from mandatory release pursuant to the provisions of 5 U.S.C.
552(b)(5), and an agency should not release such records prior to the
expiration of the fiscal year to which such records pertain. Depending
upon the nature of the records requested, other exemptions to the FOIA
may apply or the release of records within 5 U.S.C. 552(b)(5) may be
inappropriate even after the end of the fiscal year to which the records
pertain. Agency heads will be held responsible for determining the
propriety of releases of records under the FOIA pertaining to budgetary
matters."
Section 7
5. PUBLIC REQUESTS FOR BUDGETARY INFORMATION. Information from the
Department's field budget requests, the Internal Review Budget (IRB)
request, or the OMB request may not be released to the public.
Information from these documents falls within the purview of OMB
Circular A-10. Citizen inquiries may be referred to the Budget
Formulation Branch (MA-301.3).
DOE-5100.5/CII
CHAPTER II - OFFICE OF MANAGEMENT AND BUDGET SUBMISSION - PHASE I
ISSUE DATE: 07-21-83
LAST CHANGE:
CHANGE DATE:
DOE-5100.5 OFFICE OF MANAGEMENT AND BUDGET - BUDGET PROCESS
CHAPTER II
OFFICE OF MANAGEMENT AND BUDGET SUBMISSION - PHASE I
1. OMB SUBMISSION.
a. Overview. The DOE budget is transmitted to OMB in several distinct
phases. The initial submission due 9-15, includes the
justifications, legislative proposals, and projected program
supplementals as well as certain analytical crosscuts annually
specified by OMB Circular A-11, section 15.1. Also included as part
of the "initial submission" but usually due several days later is
the "computer materials" submission. This is also referred to by
OMB as "fall overview" and includes current services estimates,
multi-year projections, receipts estimates, loan and credit program
data and supplementary source documents. The second phase is the
"print material" submission which is due to OMB upon receipt of the
initial OMB allowance (OMB Circular A-11, section 15.3). The print
material submission encompasses the items that are included in the
Appendix to the President's Budget. In addition, after receipt of
the initial OMB allowance the "computer materials" must be updated
to reflect the allowance. Pay cost supplemental requests are
generally on a separate track with due dates specified by OMB during
the review process.
b. Initial Submission. The OMB submission is divided into four
categories, the regular budget request, legislative proposals,
program supplementals, and certain crosscut materials required by
OMB Circular A-11. Each of these four categories require separate
OMB schedules.
(1) The regular request consists of items for which funds are
requested and which typically have existing substantive
legislation authorizing the program. This represents the
majority of the funds requested.
(2) The legislative program represents a notification to Congress
that a request for funds will be submitted upon enactment of
substantive legislation. These items are typically included in
a separate section of the President's budget.
(3) Program supplementals include amounts needed for the current
year due to unanticipated increases in resource requirements.
(See page III-19, paragraph 6, for detailed guidance.)
(4) OMB Circular A-11, "Crosscut Materials," includes specific
analytical exhibits in specific subject areas. Detailed
guidance for preparation of these materials is contained in OMB
Circular A-11 and on page II-51, paragraph 2, of this
directive.
c. Justification - General Guidance.
Section 8
(1) Overview of Budget Justification Material (OMB Circular A-11,
Section 24.1). The Department's budget justifications will
be prepared on the basis of discrete programs or organizational
entities known as decision units. For each decision unit,
programs will identify and discuss the implications of several
funding levels. The format is similar to that used in the IRB
Process. In addition, all decision unit funding levels must be
ranked in priority order. Organizations, including those
budgeted in the Departmental administration appropriation, are
required to justify their staffing requests in their budget
submissions to OMB. Manpower justifications are to be
expressed in terms of full-time equivalents (FTE) (full-time
permanent (FTP) and total).
(2) Funding Levels (OMB Circular A-11, Section 24.1(a)). For each
decision unit, the implications of the following will be
identified and discussed:
(a) Departmental Request will reflect the Department's
preferred funding level, which is generally above the
anticipated revised OMB target. All budget justifications
are to be written to this level.
(b) Revised OMB Target will reflect the amounts contained in
the mid-session review as modified by OMB. These amounts
are generally issued by OMB in mid-July. They may only be
modified to reflect subsequent congressional action or
approved Presidential initiatives.
(c) Decrement Level is a level that typically falls below both
the Departmental request and the revised OMB target. It
will describe what activities will not be performed as a
result of a 10 percent decrement below the revised OMB
target. A decremental level is not required for each
decision unit. However, organizations must have a
sufficient number of reduced level packages to equal an
overall 10 percent reduction from the revised OMB target
level for their respective organizations. Further, they
may not be used to reopen major issue items already the
subject of Secretarial decisions.
(3) Ranking (OMB Circular A-11, Section 24.1(b)3.).
(a) To facilitate the Departmentwide ranking, organizational
elements should also include a single comprehensive list,
which ranks the various funding levels of all decision
units in decreasing order of priority. A format for the
ranking is illustrated by Figure II-1. For any decision
unit, the decrement level must be ranked before the
revised OMB target or Departmental request levels of the
same decision unit. However, a Departmental request level
for one decision unit may be ranked ahead of the
decremental level of another decision unit. The ranking
format should include:
1 A clear indication of the priority assigned to the
funding level.
Section 9
2 Identification of the decision unit and of each funding
level.
3 Budget authority, budget outlays, and total full-time
equivalent associated with each of the funding levels.
4 Cumulative budget authority, budget outlays, and FTE
amounts.
5 A concise description of the decision unit at each
funding level.
(b) Program offices must submit a statement containing the
rationale for their ranking. It should focus on how the
request furthers the overall DOE goals and objectives.
This rationale will be used in the Department-wide
ranking. Therefore, the priority strategy employed and
the potential impact of the rankings should be carefully
considered.
(4) Staffing Control Levels. Budget Year staffing controls reflect
the budget levels to be requested. The basic justification
will be written for the Departmental request level. Control
tables reflecting the decisions on staffing will be included in
the Secretary's allowance letter. Control levels for manpower,
expressed in terms of FTP and total full-time equivalents given
in the Secretary's allowance letter will be computerized for
all organizations. These computerized tables will be provided
to OMB as the official record of the Departmental staffing
requested by appropriation, decision unit, and organization.
The staffing levels shown in these tables will be those from
which OMB will develop its manpower allowance mark for each
decision unit, organization, and for the Department in total.
Questions regarding these controls should be addressed to the
Manpower Control Branch (MA-211.2). Changes in mix or
deviation from the control levels cannot be made without prior
approval of the Manpower Resource Management Division (MA-211).
Changes will be considered only if the request is specific and
justified.
____________________________________________________________________________
| Department of Energy |
| FY 19BY OMB BUDGET |
| RANKING SHEET |
| Organization |
| (in thousands of dollars) |
| |
| Cost This Activity Cumulative |
| Rank Decision Unit -------------------- ----------------------- |
| BA BO FTE BA BO FTE |
| ------- ------- --- --------- --------- --- |
| 1. Multi-Program Facilities 35,500 40,000 --- 35,500 40,000 --- |
| (decrement) |
| |
| 2. Basic Energy Sciences 228,500 231,700 7 264,000 271,700 7 |
| (decrement) |
| |
| 3. High Energy Physics 356,600 360,000 9 620,600 631,700 16 |
| (decrement) ___|________| |
| | |
| 4. Basic Energy Sciences | 31,000 31,000 3 651,600 662,600 19 |
| (revised OMB target) | |
| | |
| | |
|21. Multi-Program Facilities| 15,000 5,000 --- 1,701,500 1,689,000 327 |
Section 10
| (Departmental request)| |
| | |
| ------------------------- | |
| Narrative explanation of | |
| | |
| _______________________|______________________ |
| | Outlays associated with decrement packages | |
| | often higher than BA because decremental | |
| | level includes all outlays resulting from | |
| | prior year appropriations. | |
| |____________________________________________| |
| |
| Description |
| Rank Decision Unit ------------------------------------------ |
| |
| 1. Multi-Program Facilities Provides $25 million for continued funding |
| (decrement) of 19PY construction starts, $7 million to |
| begin construction of ESRL at ORNL, $2.5 |
| million for new starts in 19BY Reduced |
| program level. |
| |
| 2. Basic Energy Sciences Defer Social and Economic Sciences and |
| (decrement) High Temperature Materials Lab. Decreases |
| of research of 8% from 19PY level. |
| Several facilities shutdown or severely |
| limited in operation. |
| |
| 3. High Energy Physics Facility utilization 20-30%. Isabelle and |
| (decrement) tevatron 1 pace slowed, Energy Saver |
| Operation deferred until late 19PY+1, |
| Tevatron II deferred, and 20% loss of |
| scientific manpower. |
| |
| 4. Basic Energy Sciences Defer Social and Economic Sciences and |
| (revised OMB target) High Temperature Materials Lab. Decrease |
| of research of 3% from 19PY level. |
| Reduced utilization of existing facilities |
| and less planned use of new facilities. |
| |
| |
| 21. Multi-Program Facilities Provides for a more economic funding |
| (Departmental request) pattern for 19PY projects and permits |
| about $43 Million for new starts in 19BY |
| comprised of 18 project at several |
| different labs. Enables progress on |
| backlog. | |
| | |
| ___________________|____________________ |
| | Cannot be longer than 4 lines, 50 | |
| | characters per line for each funding | |
| | level. | |
| |______________________________________| |
|__________________________________________________________________________|
Figure II-1
Section 11
Ranking Sheet
d. Justification - Detailed Guidance.
(1) Lead Table. Justifications prepared for each Assistant
Secretary by appropriation at the decision unit level of detail
will include a lead table in the format of Figure II-2. The
table should include a breakout of each lower level of detail
addressed in the narrative. Funding data included in the table
must be consistent with control tables and the narrative
justifications. The table will include five columns, as
follows:
(a) Prior Year (PY) Appropriation. Reflects amounts
appropriated to date including enacted supplementals made
comparable to the Fiscal Year 19 Budget Year (FY 19BY)
structure. Comparability transfers should be footnoted.
(b) Calendar Year (CY) Estimate. Should reflect the amounts
contained in the President's budget, as amended, made
comparable to the budget year. However, if there is an
enacted appropriation or a conference report, funding
provided in the appropriate congressional reports would be
reflected. Comparability transfers should be footnoted.
(c) Budget Year (BY) Estimates:
1 Decrement level;
2 Revised OMB target; and
3 Departmental request.
(2) Summary of Changes.
(a) A summary of changes, Figure II-3, will follow each lead
table in the justification material and be consistent.
This table is an itemized list of the dollar changes which
occur among the FY 19CY budget level, the decremental, OMB
target, and program planning FY 19BY levels. The table is
not intended to be a justification, but rather an
identification of proposed changes. The relationship
between the lead table and the summary of changes table is
analogous to the same tables used in the congressional
justification.
(b) The summary of change will be prepared for each decision
unit and must agree with the preceding lead table.
Increases will be identified for each subactivity level
shown in the lead table and discussed in the narrative
justification. The stub should be constructed in such a
way that in one or two lines the increases can be
explained.
Section 12
____________________________________________________________________________
| DEPARTMENT OF ENERGY |
| FY 19BY OMB BUDGET |
| LEAD TABLE |
| NUCLEAR |
| ------- |
| Energy Supply Research and Development - Operating Expenses |
| Energy Supply Research and Development - Plant and Capital Equipment |
| (Tabular dollars in thousands. Narrative material in whole dollars.) |
| |
| FY 19BY Revised |
| ------------------------------- |
| Depart- |
| FY 19PY FY 19CY mental |
| Appropriation Request Decrement OMB Target Request |
| ------------- ------- ----------- ---------- -------- |
| Conventional Reactor |
| Systems (NE) |
| Light Water Reactor |
| Systems |
| Operating Expenses $23,900 $49,500 $51,200 $56,900 $62,600 |
| Capital Equipment 0 500 600 600 600 |
| -------- ------- -------- -------- -------- |
| Subtotal 23,900 50,000 51,800 57,500 63,200 |
| Three Mile Island |
| (TMI) |
| Examination Activities |
| Operating Expenses 0 0 9,000 10,000 10,000 |
| Capital Equipment 0 0 0 0 0 |
| -------- ------- -------- -------- -------- |
| Subtotal 0 0 9,000 10,000 10,000 |
| Advanced Reactor |
| Systems |
| Operating Expenses 4,000 4,700 5,400 5,400 5,400 |
| Capital Equipment 100 300 300 300 300 |
| -------- ------- -------- -------- -------- |
| Subtotal 4,100 5,000 5,700 5,700 5,700 |
| Program Direction |
| Operating Expenses 941 1,298 1,500 1,500 1,600 |
| -------- ------- -------- -------- -------- |
| Subtotal 941 1,298 1,500 1,500 1,600 |
| Total |
| Operating Expenses 68,341 55,498 67,100 73,800 79,600 |
| Capital Equipment 2,600 800 900 800 900 |
Section 13
| -------- ------- -------- -------- -------- |
| Conventional Reaction $ 70,941 $56,298 $ 68,000 $ 74,600 $ 80,500 |
| Systems |
| |
| Staffing Total FTE's 65/67 63/65 62/63 63/65 63/65 |
| ------------------------------------------------------------------------ |
| Authorization: Section 31, P.L. 83-703 |
| ------------------------------------------------------------------------ |
|__________________________________________________________________________|
Figure II-2
Lead Table
____________________________________________________________________________
| DEPARTMENT OF ENERGY |
| FY 19BY OMB BUDGET |
| |
| SUMMARY OF CHANGES |
| ------------------ |
| Decision Unit Title |
| (dollars in thousands) |
| |
| FY 19CY Budget request $ 68,700 |
| |
| High temperature reactor technology |
| - reduce scope of experiment -1,200 |
| by eliminating one test |
| |
| TMI |
| - Increase number of inspections +500 |
| -------- |
| Decremental level $ 68,000 |
| High Temperature reactor technology |
| - Expand number of experiments +5,700 |
| |
| TMI |
| - Expand program to include core |
| removal +1,000 |
| -------- |
| OMB Target level $ 74,700 |
| |
| High temperature reactor technology |
| - Conduct temperature test +5,700 |
| |
| Program direction |
| - Increase FTE by 3 positions +100 |
| in quality control monitoring -------- |
| Departmental request level $ 80,500 |
|__________________________________________________________________________|
Figure II-3
Summary of Changes
Section 14
(3) Narrative (OMB Circular A-11, Section 24.1(b)1).
(a) The narrative justification provides a detailed, logical
explanation of program goals and objectives, the best
means for attaining them, the rationale for a Federal
role, and the estimated resources required to do so. The
justification documents for each Assistant Secretary are
to be organized by appropriation accounts and detailed at
the specific decision unit level of detail. The
justification must explain and justify the FY 19BY amounts
in the lead table in a consistent and organized manner.
It should focus on the Departmental request level.
Further, OMB Circular A-11 provides specific minimum
requirements for the narrative portion of the
justification. This includes the nature of the problem
being addressed, the rationale for a Federal role,
objectives and accomplishments, as well as the
relationship to other programs and constraints.
(b) The narrative should utilize the financial and workload
data which will enhance the understanding of the
characteristics of the organization or appropriation.
Lower level breakdown strengthens the justification, and
its use is encouraged. In a separate section, the
narrative should describe the activities that would be
eliminated and the impact if the decision unit were funded
at the OMB target level. In another separate, but
similar, section the narrative should describe the
additional activities that would be eliminated and the
impact if the decision unit were funded at the decrement
level.
(4) Construction Project Data Sheets.
(a) Key Concepts, Budgeting for Plant Acquisition and
Construction, and Capital Equipment Not Related to
Construction versus Operating Expenses. The budgets for
operating expenses (OE), plant acquisition and
construction (PL), and capital equipment not related to
construction (CE) should be prepared so as to be
consistent with the accounting treatment as prescribed in
DOE 2200.1, ACCOUNTING POLICY AND PRACTICES, paragraph 4b,
chapters II and VI. Below are guidelines to be used in
simplifying the determination as to where the acquisition
of land, facilities, or equipment should be budgeted:
1 Items of capital equipment for which the Department
will retain title, cost in excess of $3,000, have an
expected service life of more than 1 year, and not
required to complete a construction project, shall be
budgeted for as capital equipment not related to
construction. Low value capital equipment, $3,000 or
less, may be budgeted from plant and capital equipment
(P&CE) or operating expenses in accordance with the
policy stated in DOE 5100.1. PROGRAMMING, BUDGETING,
AND ACCOUNTING FOR THE ACQUISITION OF LOW VALUE CAPITAL
EQUIPMENT.
Section 15
2 Items of capital equipment not related to construction
required for experimental projects shall be budgeted
from operating expenses if the equipment will be
destroyed during the experiment or will have no further
value other than scrap upon completion of the
experiment.
3 Budget plant and capital equipment funds for the
following:
a All land acquisition (fee or easement).
b All constructed facilities and capital equipment
necessary to provide a complete and operable
facility.
c Exception, facilities, or equipment which meet the
definition of research and development, and which
normally have an estimated life of less than 3 years
may be budgeted for as operating expenses.
4 The leasing of facilities and equipment is permissible
when it is in the best interest of the Government to do
so. Lease payments are budgeted for as operating
expenses:
a Lease With Option to Purchase. When a lease
contains an option to purchase, the lease payments
are budgeted as operating expenses. However, if the
option is exercised by the Government, the purchase
price under the option will be budgeted for as plant
and capital equipment not related to construction.
b Lease Purchase Agreements. Agreements which provide
for transfer of title at the end of the lease term
or for the transfer of title by exercise of an
option at a nominal sum unrelated to the value of
the property at the time the option is exercised,
are considered installment purchases. Funds for the
annual payments shall be budgeted under operating
expenses. However, because the Department assumes
all risks of ownership, the total amount of the
annual payments shall be recorded as an item of
DOE-owned property and capitalized. In the event
the purchase is accelerated prior to the last year
of the lease-to-ownership arrangement whereby the
full amount of the remaining installments are paid
at one time, then funds required to complete the
purchase shall be budgeted for as plant and capital
equipment not related to construction. Note that
real property may not be acquired in this manner as
the Department has no lease-purchase authority for
real estate.
c ADP Planning Documents. When ADP equipment is going
into a rehabilitated location it should be capital
equipment; in a new location it should be plant.
(b) General.
Section 16
1 Construction project data sheets are used to explain
and justify the need for construction projects. These
documents are to be updated and submitted annually as
part of the field budget submissions for all projects
requesting DOE funding in FY 19BY. The data sheets
shall be prepared as illustrated in Figure II-6, "Plant
and Capital Equipment," and Figure II-7, "Operating
Expenses Funded," using the amount of space required
for the presentation under each section. Continuation
pages shall be used as necessary. The data sheets
examples may not contain all of the elements described
in the instructions.
2 Construction projects and operating expenses funded
projected over $25 million total estimated cost (TEC)
should be validated by the Office of Project and
Facilities Management (MA-22) prior to submission of
the IRB.
3 Construction project data sheets present the
description, justification, and cost data for all
construction projects budgeted and accounted for under
plant and capital equipment and operating expenses
appropriations. Include in the cost of a construction
project, all costs in connection with the addition and
or retirement of plant and equipment (including
transferred equipment and materials), land,
improvements to land, buildings (including permanently
attached equipment), utilities, and initial movable
equipment such as machine tools, laboratory and office
furniture, and equipment necessary to outfit a building
or group of buildings for operation. Exclude initial
stocks of spare parts or other materials and supplies
which are initially chargeable to inventories.
Estimates for general plants projects (GPP) shall
provide only for work to be authorized during the
fiscal year, since funds for this purpose are both
authorized and appropriated annually.
4 General plant projects shall be assigned to outlay
programs. The predominant program at any given site
normally assumes budget responsibility for those GPP's
which provide basic support for all functions at the
site. GPP support for program-specific work at the
weapons activities multiprogram laboratory will be
funded by the program originating the request.
(c) Preparation of Construction Project Data Sheets.
1 DOE is required by law to obtain congressional
authorization for the appropriation of funds. Insofar
as practical, the development and review of the program
to be submitted to the Congress for authorization will
be undertaken as an integral part of the regular budget
process, both internally and through OMB. Construction
project data sheets shall be prepared and submitted for
all projects requiring authorization or appropriation
in the budget year.
Section 17
2 Construction project data sheets shall be prepared as
follows:
a A separate data sheet shall be submitted for each
new plant or facility and for each alteration or
addition involving the construction, modification,
alteration, or improvement of a building which is
estimated to cost more than $1 million. The
construction of a number of similar or related
units, under a specific program, may be submitted as
a single project, i.e., the construction of a group
of facilities for a specific reactor.
b A single data sheet shall be submitted to include
other projects on a consolidated basis, covering
alterations, improvements, additional, or new
construction as well as provision, where necessary,
for construction items of an unpredictable or
unforeseeable nature which is estimated to cost less
than $1 million. These projects shall be titled
"General Plant Projects." The data sheet shall be
prepared to indicate the funds requested in the
program planning estimate, and include a note to
indicate which projects would be deleted to attain
the target estimate and the decremental estimate as
indicated in Figure III-15.
c Data sheets for the multi-program general purpose
facilities program will be submitted for those
projects selected by the multi-program general
purpose facilities review committee.
d A data sheet should be an objective document written
from the standpoint of the Department as a whole
rather than as one segment of the Department.
Personal pronouns, building and area numbers,
identification of staff personnel, and
unsubstantiated value judgements should not be used.
A data sheet should be self-sufficient. The use of
technical terms that have a special connotation in
industry or science should be avoided and should not
depend on the reader having access to other
documents.
e The scope of the project shall be set forth in the
data sheets in detail sufficient to permit a careful
review and evaluation of the project. The data
sheet items should not, however, be stated so
precisely as to preclude the exercise of appropriate
latitude by the manager in the actual design and
construction of the project, as described in the
data sheet, after authorization and appropriation of
the funds.
Section 18
f Information required on page II-25, subparagraphs n
through r for Figure II-6 and page II-30,
subparagraphs o through s for Figure II-7 should be
presented on separate sheets as these data are
removed from the figures for the submission to
Congress.
3 The following detailed instructions govern the
preparation of construction project data sheets, Figure
II-6.
a Item 1, Title and Location of Project.
i Each project title must be unclassified.
ii Project titles shall be sufficiently short and
descriptive to permit ready reference.
iii Project title should not include specific
building or area numbers.
iv In typing project titles, an initial capital
shall be used for the first word in the project
title and for proper names.
v The location of the project shall be given.
b Item 2, Project Number. New project numbers shall
be issued by the Budget Formulation Branch within
each budget year, showing the year, the
organizational code, the appropriation, and the
sequential number of the project.
c Items 3 and 3a, Date A-E Work Initiated and Date
Physical Construction Starts. Insert the quarter
and year in which A-E work began or is to be
initiated and physical construction started or is to
be started, respectively. Do not assume "start" of
a budget year project prior to the start of FY 19BY.
The most realistic dates possible should be shown
based on the status of conceptual work, assuming
availability funds at the beginning of the budget
year.
d Item 4, Date Construction Ends. Insert the quarter
and year in which construction is expected to be
completed.
e Item 5, Previous Cost Estimate.
i Insert the last total estimated cost of project
which has previously been submitted to the
Congress. The date on which that estimate was
determined shall also be shown.
ii If the project has not previously been submitted
to Congress then the word "none" should be shown.
f Item 6, Current Cost Estimate. Insert the current
total estimated cost of the project and the date on
which the estimate was prepared or reviewed and
confirmed. If plant engineering and design (PE&C)
funds are included in the current cost estimate,
indicate as follows:
Current Cost Estimate $27,350
Less amount for PE&D 350
Section 19
Net Cost Estimate $27,000
g Item 7, Financial Schedules. For all construction
projects, indicate by fiscal year, the amounts
required for authorization, appropriation,
obligations, and costs. The total of these columns
shall agree with item 6, "Current Cost Estimate" or
"Net Cost Estimate," if PE&D is included. The
tabulation should be consistent with the project
schedule dates as shown in items 3, 3a, and 4.
Where the totals of these columns are at variance
with item 6, an explanation footnote should be
provided. Financial schedules should reflect all
funding for the project from its beginning. Where
an authorization bill was not enacted, authorization
data should reflect the amounts appropriated to the
extent necessary to bring authorizations to date in
line with appropriations to date. Programs should
seek sufficient authorization to cover budget year
appropriations only. The Department will no longer
request authorization of the total estimated project
cost in advance of the appropriation requirements.
i Figure II-4 is a financial schedule required for
all construction projects:
___________________________________________________________________
| Fiscal Year Authorizations Appropriations Obligations Costs |
| ----------- -------------- -------------- ----------- ------- |
| Prior Years $50,000 $30,000 $30,000 $ 5,000 |
| 19CY --- $20,000 $20,000 $ 7,000 |
| 19BY $15,000 $15,000 $15,000 $13,000 |
| 19BY+1 $15,000 $15,000 $15,000 $20,000 |
| 19BY+2 $20,000 |
| after 19BY+3 $14,400 |
| |
|_________________________________________________________________|
Figure II-4
Financial Schedule - Construction Projects
ii In addition, General Plant Projects shall show,
for purposes of comparison, the obligations and
costs incurred for similar work in the 2
preceding years. This data shall be reported as
outlined in Figure II-5.
Section 20
_______________________________________________________________________
| Costs |
| --------------------------------- |
| Fiscal Year Obligations FY 19PY FY 19CY FY 19BY After |
| ------------------ ----------- ------- ------- --------------- |
| FY 19PY-1 Projects $ 0 1/ $1,000 $ 500 $ 0 $ 0 |
| FY 19PY Projects 5,000 3,000 1,000 1,000 0 |
| FY 19CY Projects 6,000 0 4,000 1,000 1,000 |
| FY 19BY Projects 7,000 0 0 4 000 3,000 |
| ------ ------ ------ ------ |
| $4,000 $5,500 $6,000 $4,000 |
| |
| 1/ FY 19PY-1 or prior projects shall be shown only if costs are |
| incurred in FY 19PY, 19CY, or 19BY. Costs prior to FY 19PY |
| shall not be shown for such projects. |
|_____________________________________________________________________|
Figure II-5
Financial Schedule - General Plant Projects
h Item 8, Brief Physical Description of Project. This
item should state clearly, but concisely, the
essential features of the project, indicating
whether it is a new facility, alteration of existing
facilities, or addition to existing facility. In
describing facilities, code words, if used, should
be identified as such. Any unusual technical terms
should be explained when used in project
descriptions. Describe the following physical
aspects as applicable. The description should read
such that easy correlation can be made with the cost
estimate given in item 10.
i Describe improvements to land and, where this
item constitutes a major portion of the project,
include information such as the approximate
length, width, and type of roadways, approximate
capacities of parking areas, and any proposed
drainage structures and fencing.
ii Describe each building or building addition,
including approximate floor plan dimensions,
gross area, number of stories, story heights,
basement, if provided; types of construction and
reason for using such if not obvious; types of
heating and air-conditioning; capacities of
cranes and any design, fabrication, or
construction features which are unusual or
specialized and have a significant impact on the
cost estimate, such as shielding, protective
construction, hot cells, or special ventilation
systems, environmental protection systems, and
fire protection systems.
iii Describe other structures, such as pits, tunnels,
towers, bunkers, stacks, and other enclosures not
included in subparagraph ii, above.
Section 21
iv Describe any special facilities, such as
accelerator components, movable shielding, vacuum
systems, processing piping, power or controls,
reactor vessels, inert gas, hydrogen or purging
systems, or cryogenic systems.
v Describe types of utilities to be provided, such
as water, sewer, and power, and where this item
constitutes a major portion of the project,
include information such as the length and size
of the utility lines.
vi Describe any standard equipment included in this
project such as office and laboratory furniture
and equipment, hoists, and machine tools.
vii Describe any computer system or component of a
computer system having a total estimated purchase
cost of $400,000 or more including related
capitalizable costs. The types of related
capitalizable costs and an estimate of each cost
shall be provided. A brief justification and
explanation of the rationale for utilizing
construction funds shall be provided.
viii For those projects not receiving full
appropriation in this year's budget, provide a
brief description of that portion of the scope to
be accomplished with this year's appropriation.
ix For those facilities where nuclear contamination
will occur, identify the tentative method of
decommissioning the facility at the end of its
useful life, indicate the expected useful life of
the facility, and include a cost estimate for
decommissioning. The cost estimate should be
developed using constant year dollars. (See page
II-22, subparagraph m). Indicate that the
estimate is in constant year dollars and the
reference year. Identify the approximate year
when the final decommissioning method will be
selected and the final cost estimate for
decommissioning will be developed. This
information will be used as a baseline for an
authorization request for a construction project
where the decommissioning will be a significant
project.
x Projects for GPP may be described in more general
terms by identifying the contractor and other
installations covered by the project and stating
the nature of the various types of alterations,
modifications, improvements, or new construction
to be undertaken.
Section 22
i Item 9, Purpose, Justification of Need, and Scope of
Project. This item should lead off with a sentence
stating clearly and concisely the primary reason for
proposing the project. The narrative justification
shall also include the following elements as
applicable:
i Describe the research, development, or production
program which is underway or planned, including
the relationship of the proposed facility (both
as to need and timing) to the program objectives
and schedules.
ii State the criteria which determined the size or
scope of the project, such as volume of
production, storage capacity, number of persons
to be housed, and/or space requirements for
research.
iii To the maximum extent feasible within security
limitations, data sheets for projects involving
production increases should indicate the present
production rate or capacity and the change
proposed. If the project is deemed to be an
intermediate phase of a long-range program,
indicate its relationship to the foreseeable
planned capacity. If a production facility,
state annual capacity and basis therefore, i.e.,
1-shift, 2-shift operation, 5-day week, 6-day
week. When inclusion of capacity involves "Top
Secret" data, indices shall be used therefore to
the maximum extent practicable, or, if not
practicable, the information shall be submitted
separately to the program organization concerned.
iv If the purpose of the project is for replacement
of existing facilities, explain fully the
circumstances which make replacement necessary
and the disposition to be made of the replaced
facilities.
v Indicate that existing facilities have been
reviewed to determine that the need cannot be met
by modification of existing facilities. This is
of particular importance in the case of
radioactively contaminated facilities where
decontamination and decommissioning costs are
factors.
vi State the reasons for the proposed timing of the
completion of the project and the effect on the
program if the project is deferred or not
authorized.
Section 23
vii To the maximum extent practicable, justifications
should contain data on the economics of the
project including the basis for calculating
savings and payout. In computing savings,
comparative cost estimates shall include the cost
of depreciation of the facility. Justifications
can often be strengthened by reference to
alternatives and to the consequences of
disapproval.
viii If the data sheet shows both a previous cost
estimate and a current cost estimate on line 5
and 6 of Figure II-6, explain the factors
involved in determining the revised estimate.
ix If construction costs include overhead of an
offsite contract laboratory operated by a
university or other institution, the reasons for
including such overhead and the method by which
the amount of such overhead was determined shall
be stated.
x The construction project data sheet shall state
the estimated gross annual cost (excluding
depreciation) for operating the facilities upon
completion, less any offsetting reductions which
are applicable. In case of replacement
facilities, include comparative data for the
facilities being replaced.
aa For production type facilities or power
producing facilities both the first
full-year's operating costs, maintenance
costs, and the annual costs at equilibrium
should be set forth. Gross annual costs,
revenues, or other offsetting reductions, and
new annual costs should be shown.
bb For research or development facilities,
including new research machines, show
separately the operating costs, maintenance
costs, the total cost of the the research or
development program to be carried out, and
the incremental program cost related to
occupation of the new building.
cc In all cases, the basis for these estimates
of annual cost for operations and maintenance
should be included.
xi For any construction project which requires the
conduct of a research and development (R&D)
program directly pre-requisite to its specific
design and construction features and for which
R&D funds are included in the operating expenses
appropriation request, the total estimated costs
for the budget year and for each future year of
such R&D will be included for such project. (See
page II-23, subparagraph bb).
Section 24
xii The justification for GPP shall set forth major
known subprojects and examples of cost, a brief
physical description, and a concise narrative
justification. Include only those
classifications that are applicable to the
project. All costs should be presented in
current year dollars.
j Item 10, Detail of Cost Estimate.
i This section of the data sheet consists of an
estimate for each of the account classifications
listed in subparagraph iii, below. Under each of
the classifications give a breakdown of the
costs, indicating significant units and costs
wherever possible.
ii General administrative and other indirect costs,
properly charged to the project, shall not be
shown as a line item but shall be prorated among
the various elements of construction costs. Also
the estimated costs of construction management
services by private firms shall be similarly
prorated among the various elements of
construction costs. Only the account
classifications applicable to the project need be
listed. However, if it has been determined that
the project will be administered under an
"offsite" contract with a university or other
institution, and that the institution will be
reimbursed for overhead in connection with such
administration, a memorandum entry shall be
included indicating the estimated amount of such
overhead. The costs for preparing system design
descriptions or any comparable technical
documentation are to be budgeted for and costed
to the operating or plant and capital equipment
appropriations consistent with the treatment of
related expenditures, e.g., documents which are
accomplished for conceptual design are charged to
operating costs while those performed for Title I
and II are charged to plant and capital
equipment. The costs for preparing environmental
documentation shall be budgeted for and costed to
operating expenses.
iii The account classifications to be used, together
with explanatory notes, are provided below:
aa Engineering Design and Inspection Costs at
the Approximate Percent of Construction
Costs. Compute costs and indicate as
approximate percentage of total construction
costs rounding off to the nearest percent.
Include costs for safety analysis reviews
made after selection of the site.
Section 25
bb Land and Land Rights. Provide a breakdown
identifying each site to be acquired, the
acreage or square miles involved, unit cost,
and total cost or the cost of each land right
acquired. See DOE 4300.1, REAL ESTATE
MANAGEMENT, for regulations concerning the
acquisition of real property.
cc Construction Costs.
(i) Improvements to Land. Indicate the
types of improvements to be made and
total cost. Where this subitem
constitutes a major portion of the
project, it should be expressed in terms
of units, unit costs, and total cost,
such as ____ miles of road at $____ per
mile.
(ii) Buildings. List and identify each
Building or building addition to be
constructed or existing building to be
modified, showing gross square feet,
unit cost, and total cost. If the unit
cost is unusually high, provide a
footnote explanation.
(iii) Other Structures. List and provide
costs for each major other structure
described on page II-14, subparagraph h.
(iv) Special Facilities. Identify major
engineered equipment, and special
systems, as described on page II-14
subparagraph h. Where major equipment
components identified under "Special
Facilities" appear to be standard in
nature but are listed as special
because, for example, they actually
require special engineering and/or
fabrication to meet requirements, an
explanation of the special nature of the
equipment should be included.
(v) Utilities. List the types of utilities
described on page II-14, subparagraph h
and the total cost. Where this subitem
constitutes a major portion of the
project, units, unit costs, and total
costs should be shown.
dd Standard Equipment. List and provide costs
for the major items of "off-the-shelf"
equipment and furnishings, requiring a
nominal engineering effort, as described in
item 8. Costs shall include any engineering
effort required.
Section 26
ee Major Computer Items. List and provide costs
for each major computer item as described in
item 8.
ff Removal Cost Less Salvage. Include removal
costs less salvage incident to the
replacement of plant and equipment applicable
to the project. Separate projects shall be
established to budget and account for removal
costs and salvage incident to the retirement
of plant and equipment which is not to be
replaced.
gg Contingency at Approximate Percentage of
Above Costs. Compute and indicate a
contingency amount as a percentage of all
above costs, rounding to the nearest percent.
This contingency is provided to cover
unforeseen and unpredictable situations and
shall not provide for increasing the scope of
the project. The amount of contingency will
depend on the status of design and complexity
of the project.
hh Unit cost per square foot or cubic foot for
buildings or other construction shall be
computed on the basis of gross areas and
shall exclude the amount included in the
estimate for contingencies. Unit costs
should not be more precise than warranted by
the status of design.
ii The items to be shown in this section of the
data sheet should include all pertinent data
on quantities and unit costs, even if this
repeats some data reported in item 8 or 9.
Unusual unit cost, engineering design, and
inspection or contingency rates should be
explained in footnotes. The total estimated
cost shall agree with item 6.
jj A statement should be included as a footnote
at the end of the estimate to show the basis
for the estimate, e.g., "conceptual design is
complete, and Title 1 design is 25 percent
complete."
kk The items to be shown in this section of the
data sheet shall be listed in tabular form,
wherever practicable; so that the cost data
may stand out in the presentation. If
explanatory notes for any of the items listed
are necessary, they will be provided as a
footnote to the section. Explanatory notes
shall be provided to indicate reasons why
certain unit costs may be out of the normal
range; cost allowances made for isolation;
costs related to speedup of construction
showing hours per week which estimate is
based; and factors affecting the contingent
amount. The method to be used in showing
these footnotes is noted in Figure II-6.
Section 27
ll Normally, costs should be rounded off to the
nearest $10,000 for item costs and to the
nearest $100,000 for total costs.
mm Escalation rates should be explicitly stated
and when the rates are significantly
different that the guidance provided in the
budget call, a thorough explanation should be
provided.
k Item 11, Method of Performance. Indicate the type
of contracting arrangements contemplated, using the
following paragraphs or combinations of parts of
these paragraphs as a guide:
i Design and inspection will be performed under a
negotiated architect or engineer contract.
Construction and procurement will be accomplished
by fixed price contracts awarded on the basis of
competitive bidding.
ii Design and inspection will be performed by the
operating contractor. To the extent feasible,
construction and procurement will be accomplished
by fixed price contracts and subcontracts awarded
on the basis of competitive bidding.
l Items 12 and 13. All projects which have a total
estimated cost (TEC) of $5 million or more, and for
projects with a TEC of less than $5 million where
there are significant "other direct project costs"
or when there are exceptionally large "other related
costs," will have an item 12 and an item 13. Item
12 will contain the financial schedule and item 13
will contain the narrative material associated with
the financial schedule. These items are used to
explain and justify construction projects on a total
cost basis. Items 12 and 13 shall be prepared as
illustrated in Figure II-6, using the amount of
space as required for presentation under each
section. If items 12 and 13 are not required,
indicate on the data sheet "items 12 and 13 are not
required."
m The following are more detailed instructions to use
in completing items 12 and 13. The cost estimates
in items 12 are to be developed using the general
guidance provided below. Item 13 will parallel the
costs detailed in item 12 with a narrative
justification and explanation. The narrative shall
include a brief description of each item in 12, its
cost, the basis for operating expense funding and a
schedule for accomplishment of the item. It should
include the estimated start and completion dates and
relevant project interface dates.
Section 28
i Total Project Cost.
aa Total Facility Cost. This section shall
contain all those costs which are directly
related to construction of the facility.
(i) The construction line item costs must
agree with those costs contained in
prior sections of the data sheet.
(ii) Plant Engineering and Design (PE&D)
costs shall be shown in the proper
year to agree with data sheet.
(iii) Operating Expense Funded Equipment. Any
equipment, system, component, or other
item which is funded from the operating
expenses appropriation for the direct
use of the construction project or is
required to make the facility or
experiment complete and operable should
be included. A narrative justification
should be included to explain the
reasons for expenses funded items and
examples of items to be funded in this
manner.
(iv) Inventories. Any inventories which are
necessary to put the facility into use
should be included.
bb Other Project Costs.
(i) R&D Necessary to Complete Construction.
Any construction project which requires
the conduct of a research and
development program directly
prerequisite to its specific design and
construction features and for which R&D
funds are included in the operating
expenses appropriation request, the
total estimated cost by fiscal year for
such R&D will be included. Funds used
for conceptual design should be included.
(ii) Conceptual Design. Indicate the cost of
conceptual design and should be
escalated to the year of expenditure.
(iii) Other Project Related Costs. Any other
costs directly related to the project
that occur on a one time basis, such as
startup costs, training, and
decommissioning cost, should be listed
and provide a narrative explaining and
justifying each cost.
(iv) All costs under (i) and (iii) shall be
escalated to the year of expenditure.
Section 29
ii Other Related Funding Requirements. This section
should include the ongoing costs directly
associated with the operation of the facility and
the programmatic effort to be conducted using the
facility which is not appropriate for inclusion
in total project cost. An estimate of the annual
costs and a narrative explanation should be
included. In this portion of the data sheet, the
narrative explanation will take precedence over
the cost estimates. Any significant variances in
the annual cost estimates should be explained in
the narrative. For example, there may be the
planned purchases of a major item of equipment
which will substantially change the annual
costing rate or make a significant change in the
mode of operation. Indicate the estimated useful
life of the project (years).
aa A facility operating cost estimate should
include the annual costs to operate and
and maintain the facility including cost of
utilities, labor, and materials. Indicate
the man-years of efforts required to operate
facility.
bb Include programmatic effort which relies upon
the direct and primary use of the facility.
Provide a yearly estimate and narrative
justification.
cc An estimate of annual capital equipment
needs not related to construction but related
to the programmatic effort included in
subparagraph ii, above, should be included.
The accompanying narrative should explain any
expected installations of new programmatic
related capital equipment.
dd Include a yearly cost estimate and narrative
justification of GPP or other expected
construction related to programmatic effort
included in subparagraph ii, above. Include
the man-years of effort required to maintain
and repair the facility.
ee Any other expected annual costs should be
listed with an accompanying narrative.
iii Significant Cost Variations. In addition, any
significant variations in the annual costing
rates for the preceding items should be
footnoted. For example, the procurement of a new
nuclear reactor core on a very infrequent basis
would greatly increase the annual capital
equipment cost rate for a facility. These
deviations in costs should be segregated from the
annual cost rates.
Section 30
n Item 14, Incorporation of Fallout Shelters in Future
Federal Buildings. For all suitable buildings the
total estimated costs shall include fallout shelter
space conforming to the design requirements. The
existence of adequate fallout shelter space in the
vicinity or the location of this facility in a
security area should not necessarily prevent the
consideration of providing shelter space in new
facilities. For purposes of this item, one of the
following statements should normally be used:
i Efforts will be made through the use of slanting
techniques in design of this building to provide
additional shelter space at little or no
additional costs.
ii If fallout shelters are not provided, indicate
the reason, i.e., sufficient space available, and
deficiency programmed in another project.
iii The building to be constructed as a part of this
project is not suitable for use as a fallout
shelter because ... (the reason may be type of
construction, such as prefabricated metal
buildings, or type of work to be performed in the
facility, such as the handling of explosives or
radioactive material).
iv This project does not include the construction of
new buildings or building additions. Therefore,
the provision for fallout shelters is not
applicable.
o Item 15, Federal Compliance with Pollution Control
Standards. This section of the data sheet should
contain a statement indicating that the total
estimated cost of the project includes the cost of
those measures which may be necessary to assure that
the facility or building will meet the requirements
of Executive Order 12088, "Federal Compliance with
Pollution Control Standards". A brief statement of
those controls provided which assure compliance with
the foregoing should also be provided for each type
of pollutant. This section should normally contain
one of the following paragraphs:
i The total cost of this project includes the costs
of those measures necessary to assure compliance
with Executive Order 12088. Sanitary waste will
be discharged into existing sewers connected to
adequate sewage treatment facilities. Airborne
contaminants will be collected and filtered
before being released to the atmosphere. (This
paragraph should be modified to reflect the type
of pollutants produced by each particular
project.)
Section 31
ii The performance of this project will inherently
assure compliance with the requirements of
Executive Order 12088. (To be used for projects
specifically for pollution control.)
iii As presently conceived, operation of this project
will not generate any environmental pollutants;
therefore, the requirements of Executive Order
12088 are not applicable.
p Item 16, Evaluation of Flood Hazards. This section
of the data sheet should contain a statement with
regard to the evaluation and consideration of flood
hazards in accordance with the requirements of
Executive Order 11988, "Evaluation of Flood Hazard
in Locating Federally Owned or Financed Buildings,
Roads, and Other Facilities, and in Disposing of
Federal Lands and Properties." Section 4 of the
Executive order requires that, "Any requests for
appropriations for Federal construction of new
buildings, structures, roads or other facilities...
shall be accompanied by a statement by the head of
the agency on the findings of his agency's
evaluation and consideration of flood hazards in the
development of such requests." Reference is made to
the Flood Hazard Evaluation Guidelines for Federal
Executive Agencies, published by the Water Resources
Council, of 5-72. If it is determined that the
project site is not subject to the defined hazards,
it is recommended that the following statement be
used:
"This project will be located in an area not
subject to flooding determined in accordance
with Executive Order 11988."
q Item 17, Compliance with the National Environmental
Policy Act, Floodplains/Wetlands Environmental
Review Requirements, and Other Related Environmental
Statutes. This section of the data sheet should
present information on planning for compliance with
the National Environmental Policy Act, DOE 5440.1B,
IMPLEMENTATION OF THE NATIONAL ENVIRONMENTAL POLICY
ACT, the Council on Environmental Quality Regulation
(40 CFR 1500-1508), DOE's NEPA guidelines (45 FR
20694, as amended), DOE's regulation 10 CFR 1022,
and other related statutes including but not limited
to the Clean Air Act, the Clean Water Act, the
National Historic Preservation Act, and the
Endangered Species Act. Examples of such
information include, if a NEPA document has been
completed for the proposed project, reference to
that document should be made; if a NEPA document is
under preparation for a proposed project, reference
should be made to that document, its status, and its
schedule completion date; and, if a determination on
the level of NEPA documentation has not been made
for a proposed project, indicate when information
will be provided for Headquarters use in determining
the need for further documentation for those actions
still requiring Headquarters determinations. In all
Section 32
cases, state whether or not the proposed project is
located in a floodplain/wetland.
r Item 18, Accessibility for the Handicapped. Provide
a statement indicating that the project will be
accessible to the handicapped in accordance with the
Architectural Barriers Act, Public Law 90-480, and
implementing instructions in the Federal Property
Management Regulations (41 CFR 101-91.6). Section
501 of the Rehabilitation Act of 1973 (Public Law
93-112), as amended, requires the development of an
affirmative action plan for employment of the
handicapped by Federal agencies. Affirmative action
plans are also required by 41 CFR 60-250,
"Affirmative Action Obligations of Contractors and
Subcontractors for Disabled Veterans and Veterans of
the Vietnam Era," 41 CFR 60-741, "Affirmative Action
Obligations of Contractors and Subcontractors for
Handicapped Workers," and DOE 3220.2, EQUAL
OPPORTUNITY IN OPERATING AND ONSITE SERVICE
CONTRACTOR FACILITIES.
4 The following instructions govern the preparation of
Operating Expenses Funded Project Data Sheets, Figure
II-7. This document should be prepared only if the
project is in procurement, fabrication, or construction
phases in the FY 19BY and the total cost is estimated
to be $5 million or more. This includes projects to be
jointly funded by the end of the FY 19BY. The schedule
is not required if the project is still in the
conceptual design stage in the FY 19BY. Figure II-7
contains the following information:
a Project Title. The title should be short and
descriptive.
b Total Estimated Cost (TEC). The TEC should be only
the total cost of construction as if the project
were a line item construction project, i.e., the
cost to build an operable facility or experiment.
c Operating Expenses (OE). For the items listed below
on page II-29, subparagraphs d through g, provide
the cumulative obligations for prior (before FY
19PY) year, the B/A, Obligations and B/O for the FY
19PY, the B/A and B/O for the FY 19CY and FY 19BY,
and an estimate of future year requirements (BA/BO)
through completion of the project.
i Design and Construction. This is the cost of
constructing the facility. These costs should
include engineering, design, inspection, physical
construction costs, standard equipment, and
contingency.
Section 33
ii R&D Related to Construction. Includes conceptual
design and any other R&D related to the
construction of the facility.
iii Facility Operations. Includes all costs
associated with the programmatic use and
operation and maintenance of the facility and the
number of years estimated for operation.
iv Direct Project Related Support Costs. Includes
all other operating expense funds such as
inventories, and training.
v Capital Equipment. Includes equipment to be used
in the construction of the facility or for
facility operations.
vi Total Operating Expenses. Summation of
subparagraph i through v above.
d Other DOE Costs. Includes all other DOE funding
related to the program/project activity (i.e., PE&D
and line item).
e Total DOE Cost. Total of subparagraphs c and d
above.
f Non-DOE Cost. Includes identification of all
non-DOE funding. The basis for the non-DOE funding
should be identified (i.e., signed contract and
contractor proposal).
i Design and construction.
ii Facility operations and maintenance.
iii Other.
iv Total non-DOE funding.
g Total Project Cost. Summation of subparagraphs e
and f, above.
h Description, Objective, and Justification. Provide
a clear and concise description of the project
indicating in general terms the technical features
of the project. State the objectives of the project
and how they relate to the overall mission of the
program and the Department. Also state why this
project will meet the objective stated above.
i Schedule of Planned Activities. Provide a schedule
indicating quarter and fiscal year of the start and
completion of major activities. At a minimum,
include schedule for conceptual design, detailed
design, long-lead procurement, construction and
startup/operations. Include explanatory notes to
highlight and clarify the schedule (i.e., the reason
that long lead procurement must be initiated).
j Management and Contracting Plan. This plan is
required to identify overall program or project
strategy regarding the procurement approach,
anticipated participation by industry or other
Government agencies, program or project management
location, and general approach to management
organization contemplated.
Section 34
k Prior Year Achievements. Provide a narrative
description of achievement relating to the
development of the project in prior years.
l CY Achievements. Refer to subparagraph k above.
m Reasons for Increases or Decreases. Indicate the
reason for an increase or decrease in funding
requirements as related to the last budget request
approved by Congress. Also indicate the fiscal year
of the last approved budget request.
n Construction Cost Estimate. Refer to page II-18,
subparagraph j.
o Incorporation of Fallout Shelters in Future Federal
Buildings. Refer to page II-25, subparagraph n.
Judgment should be exercised in locating fallout
protection in operating expenses funding facilities
which have a useful life of 3 years or less.
p Federal Compliance with Pollution Control Standards.
Refer to page II-26, subparagraph o.
q Evaluation of Flood Hazards. Refer to page II-26,
subparagraph p).
r Compliance with the National Environmental Policy
Act and Related Statutes. Refer to page II-27,
subparagraph q.
s Accessibility for the Handicapped. Refer to page
II-27, subparagraph r.
____________________________________________________________________________
| Department of Energy |
| FY 19BY OMB BUDGET SUBMISSION |
| |
| CONSTRUCTION PROJECT DATA SHEETS |
| Atomic Energy Defense Activities - Plant and Capital Equipment |
| Atomic Energy Defense Activities |
| Decision Unit |
| |
| (Tabular dollars in thousands. Narrative material in whole dollars.) |
| ________________________________________________________________________ |
| 1. Title and location of project: 2. Project No. 80-AE-3 |
| Steam generation facilities, |
| Idaho Fuels Processing Facility, |
| Idaho |
| ________________________________________________________________________ |
| 3. Date A-E work initiated: 4th Qtr. 5. Previous cost |
| FY 1979 (PE&D) Funds) estimate: $24,000 |
| Less amount for 500 |
| 3a. Date physical construction PE&D: ------- |
| starts: 2nd Qtr. FY 1982 Net cost estimate: $23,500 |
| Date: 1/80 |
| 4. Date construction ends: 3rd Qtr. |
| FY 1984 a/ 6. Current cost |
| estimate: $29,000 |
| Less amount for 500 |
| PE&D (FY 79): ------- |
| Net cost estimate: $28,500 a/|
| Date: 12/80 |
Section 35
| ________________________________________________________________________ |
| 7. Financial Schedule: |
| ------------------- |
| Fiscal Year Authorization Appropriations Obligations Costs |
| ----------- ------------- -------------- ----------- ----- |
| 1980 $23,500 $10,000 $ 7,000 b/ $ 0 |
| 1981 -- 8,500 11,500 c/ 10,000 |
| 1982 5,000 10,000 10,000 9,500 |
| 1983 -- -- -- 8,000 |
| 1984 -- -- -- 1,000 |
| _____________________________ |
| a/ The increased TEC reflects the addition of a cogenerator capability, |
| delays caused by studies on alternative energy sources such as |
| geothermal and natural gas, and revisions in the funding schedule in |
| FY 1980 and FY 1981. |
| b/ Reflects Congressional deferrals of $3,000,000 to FY 1981. |
| c/ Reflects Congressional reduction of $5,000,000. |
|__________________________________________________________________________|
Figure II-6
Construction Project Data Sheets
Plant and Capital Equipment Funded
____________________________________________________________________________
| CONSTRUCTION PROJECT DATA SHEETS |
| -------------------------------- |
| ________________________________________________________________________ |
| 1. Title and location of project: Steam 2. Project No. 80-AE-3 |
| generation facilities, Idaho Fuels |
| Processing Facility, Idaho |
| ________________________________________________________________________ |
| 8. Brief Physical Description of Project |
| ------------------------------------- |
| This project provides for the design, procurement, and construction |
| of a coal-fired steam generator facility to meet present and |
| projected steam requirements for projects planned at IFPF through FY |
| 1985. The facility will be designed for a 25-year life, will be |
| steel frame construction with insulated metal panels and be |
| approximately 125' x 132'. The project will include: (a) facilities |
| for coal receiving, handling, and storage; (b) two 67,500 lb/hr |
| coal-fired boilers; (c) a 16,500 s.f. building to house the |
| necessary equipment; (d) water treatment equipment; (e) air |
| pollution control equipment; (f) solid waste disposal equipment; (g) |
| liquid waste treatment equipment; (h) utility tunnel; (i) |
| connections to existing utility systems; (j) railroad spur; (k) |
| connecting roads; (l) parking facilities; (m) all ancillary features |
| required for peak operating efficiency and safety; (n) capability to |
| convert to cogeneration; and (o) a boiler stack. Funds requested |
| will allow for the construction of the boiler house and stack, and |
| will support installation of long lead procurement items such as the |
| boilers and associated auxiliary equipment. |
| |
| 9. Purpose, Justification of Need for, and Scope of Project |
| -------------------------------------------------------- |
| The purpose of this project is to provide a coal-fired steam |
Section 36
| generation facility which will replace, in part, the existing |
| oil-fired equipment and will provide expansion capacity for planned |
| plant requirements and normal reserve capacity, plus capability to |
| convert to cogeneration at some future date. |
| |
| The budget authority level requested in FY 1982 is for the |
| continuance of facility design, equipment procurement and the |
| initiation of construction. |
| |
| The Idaho Fuels Processing Facility (IFPF) was built in 1951 and has |
| undergone a series of expansions and modifications which have |
| increased steam requirements beyond the steam generation |
| capabilities of the original installation. The present steam system |
| will not provide for essential loads should one boiler go off-line. |
| New production facilities are being designed and built which will |
| further exceed the existing available steam generation capabilities. |
| Without additional steam capacity, required production rates would |
| not be achieved. |
| |
| Specific programs and projects are the driving force behind the need |
| for increased steam generation capacity at IFPF. These projects and |
| projected peak steam requirements are: (a) the New Waste Calcining |
| Facility (NWCF), 19,440 lb/hr; (b) Fluorinel and Storage (FAST) |
| Facility, 11,880 lb/hr; (c) Remote Analytical facility Upgrade and |
| Expansion, 1,404 lb/hr; (d) a proposed Plant Process Chemistry |
| Building, 22,097 lb/hr; (e) other GPP projects, 900 lb/hr; and (f) |
| reserve capacity, steam plant load and distribution losses, 13,930 |
| lb/hr for a total additional future requirement of approximately |
|__________________________________________________________________________|
Figure II-6
Construction Project Data Sheets
Plant and Capital Equipment Funded
(Continued)
____________________________________________________________________________
| CONSTRUCTION PROJECT DATA SHEETS |
| -------------------------------- |
| ________________________________________________________________________ |
| 1. Title and location of project: Steam 2. Project No. 80-AE-3 |
| generation facilities, Idaho Fuels |
| Processing Facility, Idaho |
| ________________________________________________________________________ |
| 9. Purpose, Justification of Need for, and Scope of Project (continued) |
| -------------------------------------------------------------------- |
| 69,651 lb/hr of steam. This, combined with the current base load of |
| 65,550 lb/hr, will increase the total plant requirement to |
| approximately 135,200 lb/hr. It will not be possible to accommodate |
| additional loads from these facilities without expanding the |
| existing steam generation system and adding reserve capacity. |
| Without reserve capacity, several facilities could be forced into |
| unplanned shutdown should be boiler malfunction during the winter |
| months. Should this project be disapproved, curtailed operation of |
| the above facilities would be required. |
| |
Section 37
| National policy is to minimize the consumption of, and eventually to |
| eliminate the use of, fuel oil. Implementation of this project will |
| permit the IFPF to provide normal steam requirements from coal-fired |
| sources. |
| |
| The scope of this project is determined by the volume and rate of |
| steam generation, coal unloading rate and storage capacity. This |
| facility will produce steam at a peak rate of 135,000 lb/hr |
| including losses incurred from boiler breakdown, distribution, and |
| feedwater heating. The new boilers will be designed to generate |
| steam of a quality required for cogeneration and for process and |
| plant heating purposes. |
| |
| The coal handling plant is sized for an unloading rate of 100 ton |
| capacity receiving hopper. The dean storage area is sized to |
| contain 6,400 tons of coal, which represents a 30 day supply for |
| each boiler. Coal will be delivered in 70 to 90 ton capacity bottom |
| dumping cars. Ten cars with 700 tons of coal will be sufficient for |
| a three day capacity at a maximum rate of 135,000 lb/hr steam. |
| |
| A bucket elevator will transfer the coal from the receiving hopper |
| to two live coal bunkers in the boiler house at a rate of 100 ton/hr.|
| The live coal bunkers have a capacity of 135 tons of coal each, |
| which represents 30 hours supply at maximum continuous rating. |
| |
| The delay in funding or at authorizing this project will have the |
| following effect: |
| |
| (1) The existing steam-generation equipment for production |
| activities is subject to failure causing loss of production. |
| Many facilities will be operable with rigid administrative |
| control of steam use. After 1983, Fluorinel fuel processing |
| and operations of the New Waste Calcining Facility could not be |
| conducted concurrently which would result in significantly |
| reduced processing capacity for Fluorinel, severely increased |
| cost per ton of fuel processed, and increased backlog of fuel |
| being stored. |
| |
| (2) Progressive growth to meet projected production requirements |
| would be severely limited due to lack of steam. |
| |
| (3) Steam required to meet projected production requirements would |
| be installed in a stepwise manner resulting in small units with |
| a higher installation cost, higher operation cost, and |
| substantially decreased energy efficiency. |
| |
| (4) Significantly increased overall cost to maintain and repair the |
| existing aging system. |
| |
| (5) Annual operations and maintenance costs are approximately $1.3 |
| million per year. |
|__________________________________________________________________________|
Figure II-6
Construction Project Data Sheets
Section 38
Plant and Capital Equipment Funded
(Continued)
____________________________________________________________________________
| CONSTRUCTION PROJECT DATA SHEETS |
| -------------------------------- |
| ________________________________________________________________________ |
| 1. Title and location of project: Steam 2. Project No. 80-AE-3 |
| generation facilities, Idaho Fuels |
| Processing Facility, Idaho |
| ________________________________________________________________________ |
| 9. Purpose, Justification of Need for, and Scope of Project (continued) |
| -------------------------------------------------------------------- |
| Disapproval of new coal-fired steam generation equipment will mean |
| complete dependence on oil as fuel and will incur a serious risk to |
| IFPF operations should the current plant's capacity at be available |
| for reasons of repair or maintenance. In any event the existing |
| steam capacity will be inadequate after 1983. |
| |
| 10. Details of Cost Estimate a/ Item Cost Total Cost |
| ------------------------ - --------- ---------- |
| a. Engineering, design and inspection at 24% |
| of construction costs, item b b/ $ 3,400 b/ |
| b. Construction costs 16,500 - |
| (1) Improvements to land including |
| grading, landscaping, drainage |
| diversion, paving, parking, fencing, |
| lighting, and pedestrian access walks $ 200 |
| (2) Buildings 1,600 |
| (a) Coal boiler house, 16,500 sq. ft. |
| at approximately $97/sq. ft. |
| (3) Other structures includes boiler stack, |
| ash burial pit, and underground tunnel 4,300 |
| (4) Utilities, including electrical power, |
| water, sanitary sewer lines, compressed |
| air, fuel oil, condensate return lines, |
| railroad spurs. etc. 1,600 |
| (5) Special facilities includes coal |
| handling equipment, air pollution |
| control equipment, ash handling |
| equipment, water treatment equipment, |
| and two coal fired boilers capable of |
| cogeneration 8,800 |
| c. Standard equipment includes auxiliary |
| equipment ($2,995), and office furniture ($) 3,000 |
| d. Removal less salvage 0 |
| ------- |
| Subtotal 22,900 |
| e. Contingency at approximately 24% of above 5,600 |
| cost ------- |
| Total estimated Costs $28,500 b/c/|
| |
| ---------------------- |
| a/ The above estimates we based on conceptual design and feasibility |
Section 39
| studies which are 100% complete. |
| b/ Excludes $500,000 of PE&D. |
| c/ All cost have been escalated at the rate of 12% to current year costs |
| based upon the methodology developed for ID. |
|__________________________________________________________________________|
Figure II-6
Construction Project Data Sheets
Plant and Capital Equipment Funded
(Continued)
____________________________________________________________________________
| CONSTRUCTION PROJECT DATA SHEETS |
| -------------------------------- |
| ________________________________________________________________________ |
| 1. Title and location of project: Steam 2. Project No. 80-AE-3 |
| generation facilities, Idaho Fuels |
| Processing Facility, Idaho |
| ________________________________________________________________________ |
| 11. Method of Performance |
| --------------------- |
| Contracting arrangements are as follows: |
| |
| a. Design, Procurement and Construction: Fixed-price contract |
| awarded on the basis of competitive bidding. |
| b. Title III Inspection: By Architect-Engineer contractor under |
| operating contractor surveillance. |
| |
| 12. Funding Schedule of Project Funding and Other Related Funding |
| Requirements |
| ------------------------------------------------------------- |
| Prior |
| Years FY 1980 FY 1981 FY 1982 FY 1983 FY 1984 Total |
| ----- ------- ------- ------- ------- ------- -------|
| a. Total project |
| costs |
| 1. Total facility |
| costs |
| (a) Construction |
| line item $ 0 $ 0 $10,000 $ 9,500 $ 8,000 $ 1,000 $28,500|
| (b) PE&D 500 0 0 0 0 0 500|
| (c) Inventories 0 0 0 0 180 0 180|
| ------ ------ ------- ------- ------- ------- -------|
| Total $ 500 $ 0 $10,000 $ 9,500 $ 8,180 $ 1,000 $29,180|
| direct costs |
| 2. Other project |
| costs |
| (a) R&D necessary |
| to complete |
| construction $ 0 $ 0 $ 0 $ 0 $ 0 $ 0 $ 0|
| (b) Conceptual |
| design costs 450 0 0 0 0 0 450|
| (c) Other project |
| related costs 200 0 440 540 470 300 1,950|
| ------ ------ ------- ------- ------- ------- -------|
Section 40
| Total other $ 650 $ 0 $ 440 $ 540 $ 470 $ 300 $ 2,400|
| project costs ------ ------ ------- ------- ------- ------- -------|
| Total project $1,150 $ 0 $10,440 $10,040 $ 8,650 $ 1,300 $31,580|
| costs Item ====== ====== ======= ======= ======= ======= =======|
| 1 & 2) |
| |
| b. Other related annual costs (estimated life of project: 25 years) |
| 1. Facility operating costs $ 1,300 |
| 2. Programmatic operating expenses directly related |
| to the facility 0 |
| 3. Capital equipment not related to construction but |
| related to the programmatic effort in the facility 130 |
| 4. Maintenance, repair, GPP or other construction |
| related to programmatic effort in the facility 100 |
| ------- |
| Total related annual costs $ 1,530 |
| ======= |
|__________________________________________________________________________|
Figure II-6
Construction Project Data Sheets
Plant and Capital Equipment Funded
(Continued)
____________________________________________________________________________
| CONSTRUCTION PROJECT DATA SHEETS |
| ________________________________ |
| ________________________________________________________________________ |
| 1. Title and location of project: Steam 2. Project No. 80-AE-3 |
| generation facilities, Idaho Fuels |
| Processing Facility, Idaho |
| ________________________________________________________________________ |
| 13. Narrative Explanation of Total Project Funding and Other Related |
| Funding Requirements |
| ---------------------------------------------------------------- |
| a. Total project funding |
| |
| 1. Total Facility |
| (a) Inventories - Inventories necessary to put the facility |
| into use are estimated to cost $180,000. |
| |
| 2. Other project funding |
| (a) R&D necessary to complete construction - Conceptual |
| Design was completed at a cost of $450,000. |
| (b) Other project related funding - Project support and |
| startup are estimated to cost $1,950,000. |
| |
| b. Total related funding requirements - It is estimated the |
| facility will be used 25 years for its programmatic purpose. |
| |
| 1. Facility operating costs - The major elements comprising the |
| annual operating costs are coal costs, labor costs, and |
| operating costs of boiler, fan systems and motors. |
| |
| The total delivery cost of coal to the steam plant will be |
Section 41
| approximately $25.45/ton based on 1977 dollars. This is |
| equivalent to a price of $1.48/10 6 BTU. |
| |
| To operate the facility, three boiler plant operators and |
| one coal yard operator on a three shift rotation basis will |
| be required. Routine plant maintenance will be completed by |
| the boiler plant operators. |
| |
| 2. Programmatic operating expenses directly related to the |
| facility - The steam generated by the coal-fired boilers |
| will be consumed by the following IFPF facilities: |
| |
| New Waste Calcining Facilities....................... 14% |
| Remote Analytical Facility Upgrade and Expansion..... 1% |
| Fluorinel and Storage Facility....................... 9% |
| Remainder of Plant................................... 76% |
| |
| 3. Capital equipment not related to construction but related to |
| the programmatic effort in the facility - Estimated cost is |
| to cover the costs of dump trucks, inloader, bulldozer, etc. |
| necessary to handle the coal over a 25 year period. |
| |
| 4. Maintenance, repair, GPP or Other Construction Related to |
| Programmatic Effort - Estimated cost is based on experience |
| with average cost for the replacement of lines, valves, pump |
| and motor repairs per year. |
|__________________________________________________________________________|
Figure II-6
Construction Project Data Sheets
Plant and Capital Equipment Funded
(Continued)
____________________________________________________________________________
| CONSTRUCTION PROJECT DATA SHEETS |
| ________________________________ |
| ________________________________________________________________________ |
| 1. Title and location of project: Steam 2. Project No. 80-AE-3 |
| generation facilities, Idaho Fuels |
| Processing Facility, Idaho |
| ________________________________________________________________________ |
| 14. Incorporation of Fallout Shelters: Indicate whether shelter space |
| ---------------------------------- |
| is included. If not, give the rationale why it is not included. |
| |
| 15. Federal Compliance with Pollution Control Standards: Indicate |
| ---------------------------------------------------- |
| measures taken if necessary, to control environmental pollutants and |
| indicate that those costs we included in the TEC. |
| |
| 16. Evaluation of Flood Hazards: Indicate whether or not flood hazards |
| ---------------------------- |
| have been considered. If located in a flood plain, indicate |
| mitigating action planned. |
| |
Section 42
| 17. Environmental Impact: Indicate status of compliance with the |
| --------------------- |
| National Environmental Policy Act and if the project is located in |
| a floodplain/wetland. |
| |
| 18. Accessibility for the Handicapped: Provide a statement indicating |
| ---------------------------------- |
| accessibility for the Handicapped in accordance with the |
| Architectural Barriers Act (Public Law 90-480) and the Federal |
| Property Management Regulations (41 CFR 101-19.6). |
|__________________________________________________________________________|
Figure II-6
Construction Project Data Sheets
Plant and Capital Equipment Funded
(Continued)
____________________________________________________________________________
| DEPARTMENT OF ENERGY |
| FY 19BY OMB BUDGET PROCESS |
| |
| OPERATING EXPENSE FUNDED PROJECT DATA SHEET |
| ------------------------------------------- |
| DEFENSE PROGRAMS |
| |
| |
| Atomic Energy Defense Activities Construction |
| Atomic Energy Defense Activities |
| Defense Nuclear Waste |
| |
| (Tabular dollars in thousands. Narrative material in whole dollars.) |
| |
| Reedy Creek Utilities Demonstration Plant |
| Idaho Operations Office |
| |
| Total Estimated Cost (TEC) $14,945,000 |
| (For Design and Construction) |
| |
| |
|__________________________________________________________________________|
Figure II-7
Construction Project Data Sheets
Operating Expenses Funded
____________________________________________________________________________
| Reedy Creek Utilities Demonstration Plant |
| Idaho Operations Office |
| |
| Total Estimated Cost (TEC) $14,945,000 |
| |
| (Tabular dollars in thousands. Narrative material in whole dollars.) |
| ------------------------------------------------------------------------ |
| Cumulative FY 1981 |
| Prior Years FY 1980 Actual Estimate |
| ----------- ---------------------- -------------- |
Section 43
| Obs. B/A Obs. B/O B/A B/O |
| ----------- ------ ------ ------ ------ ------ |
| Operating expenses (DOE): |
| ------------------------- |
| Design and construction $ 85 $3,300 $3,300 $2,437 $8,745 $8,400 |
| R&D related to 100 140 140 140 250 250 |
| construction |
| Facility operations 0 0 0 0 0 0 |
| Direct project related 0 0 0 0 0 0 |
| support costs |
| Capital equipment 0 0 0 0 0 0 |
| ----- ------ ------ ------ ------ ------ |
| Total operating expenses 185 3,440 3,440 2,577 8,995 8,650 |
| |
| Other DOE funding: |
| ------------------ |
| Activity - Conservation 0 575 575 575 400 400 |
| and Solar Energy ----- ------ ------ ------ ------ ------ |
| |
| Total DOE funding: 185 4,015 4,015 3,152 9,395 9,050 |
| ------------------ |
| |
| Non-DOE funding: |
| ---------------- |
| Design and construction 0 0 0 0 500 500 |
| ----- ------ ------ ------ ------ ------ |
| Total Project funding $ 185 $4,015 $4,015 $3,152 $9,895 $9,550 |
| --------------------- |
|__________________________________________________________________________|
Figure II-7
Construction Project Data Sheets
Operating Expenses Funded
(Continued)
____________________________________________________________________________
| Reedy Creek Utilities Demonstration Plant |
| Idaho Operations Office |
| |
| Total Estimated Cost (TEC) $14,945,000 |
| |
| (Tabular dollars in thousands. Narrative material in whole dollars.) |
| ------------------------------------------------------------------------ |
| FY 1982 Estimate Total Cost |
| ---------------- ---------- |
| B/A B/O B/A |
| ---------------- ---------- |
| Operating expenses (DOE): |
| ------------------------- |
| Design and construction $1,340 $2,548 $13,470 |
| R&D related to construction 0 0 490 |
| Facility operations 370 370 370 |
| Direct project related support 0 0 50 |
| costs |
| Capital equipment 30 30 30 |
Section 44
| ------ ------ ------- |
| Total operating expenses $1,740 $2,948 $14,410 |
| |
| Other DOE costs |
| --------------- |
| Activity - Conservation and |
| Solar Energy, design and |
| construction 0 0 975 |
| ------ ------ ------- |
| Total DOE costs $1,740 $2,948 $15,385 |
| --------------- |
| |
| Non-DOE costs |
| ------------- |
| Design and construction 0 0 500 |
| ------ ------ ------- |
| Total Project costs $1,740 $2,948 $15,885* |
| ------------------- |
| |
| *To reconcile with the TEC of $14,945,000 delete $940,000 associated |
| with "Direct project related support costs." |
|__________________________________________________________________________|
Figure II-7
Construction Project Data Sheets
Operating Expenses Funded
(Continued)
____________________________________________________________________________
| Reedy Creek Utilities Demonstration Plant |
| Idaho Operations Office |
| |
| Total Estimated Cost (TEC) $14,945,000 |
| |
| (Tabular dollars in thousands. Narrative material in whole dollars.) |
| ------------------------------------------------------------------------ |
| Description, Objective and Justification |
| ---------------------------------------- |
| Conceptual design is complete for a Transuranic (TRU) Waste Treatment |
| Facility (TWTF) at the Idaho National Engineering Laboratory (INEL). |
| Its objective is to process (chemically and physically treat and |
| immobilize) the retrievable stored INEL TRU waste and have the |
| capability to process buried TRU waste. The Reedy Creek Utilities |
| Demonstration Plant, located at Lake Buena Vista, Florida, is being |
| undertaken as a cold (non-radioactive) pilot demonstration plant. |
| |
| A promising technology for immobilizing the TRU waste it the INEL is the |
| slagging pyrolysis incinerator. Rights to this incinerator are held by |
| Andco, Inc. of Buffalo, New York. While the "slagger" is based on "old" |
| blast furnace technology, it has not been used is a nuclear waste |
| incinerator. There is limited experience with this technology in the |
| United States and none in DOE. Development and testing it the Mol, |
| Belgium slagging incinerator will be useful to characterize the end |
| product, however, this incinerator his a different design and scale. |
| Identical scale tests are necessary to confirm how the slagging |
Section 45
| incinerator will perform with simulated INEL transuranic waste. |
| |
| Reedy Creek Utilities Company Incorporated (RCUC), a wholly-owned |
| subsidiary of Walt Disney Enterprises, submitted an unsolicited proposal |
| for a joint project to build an exact scale demonstration incinerator |
| that will support the Idaho project: (a) a slagging pyrolysis |
| incinerator would be designed, constructed, and tested in time to |
| confirm or impact design before construction starts on the Idaho unit; |
| (b) the capacity will be identical to Idaho's at approximately 100 |
| tons/day gross throughout; (c) DOE will have unlimited use of the |
| facility for the first year of operation and 30 days per year for the |
| next 10 years; (d) additional use can be purchased at the pleasure of |
| the Government; and (e) title will transfer to RCUC after the full year |
| of exclusive use by DOE. If the incinerator meets RCUC performance |
| expectations, the U.S. Government (Treasury) will recapture a |
| substantial part of its investment around 1985. |
| |
| By constructing a cold pilot plant, DOE will gain early design, |
| construction, and operating experience before the commitment to |
| construct a major radioactive waste processing facility at the INEL. |
| The demonstration incinerator will verify the designing of the INEL |
| incinerator at the same scale. By operating the demonstration plant |
| with simulated INEL feed, valuable operating and technical data will be |
| gained. The cold demonstration plant may indicate design changes that |
| may be required in the radioactive waste incinerator. Such changes |
| could then be incorporated before construction rather than by retrofit |
| during construction or after startup. |
| |
| (a) Schedule of Planned Activities |
| ------------------------------ |
| The following table presents the total program broken down by |
| primary tasks. |
| |
| Activity Start Complete |
| --------------------------- ---------- ---------- |
| Procurement and Fabrication 1Q FY 1980 4Q FY 1981 |
| Facility Construction 4Q FY 1980 1Q FY 1982 |
| Facility Startup 1Q FY 1982 2Q FY 1982 |
| Test Program 2Q FY 1982 2Q FY 1983 |
|__________________________________________________________________________|
Figure II-7
Construction Project Data Sheets
Operating Expenses Funded
(Continued)
Section 46
____________________________________________________________________________
| Reedy Creek Utilities Demonstration Plant |
| Idaho Operations Office |
| |
| Total Estimated Cost (TEC) $14,945,000 |
| |
| (Tabular dollars in thousands. Narrative material in whole dollars.) |
| ------------------------------------------------------------------------ |
| (b) Management and Contracting |
| -------------------------- |
| The RCUC will design and construct the total facility with the |
| support of appropriate subcontractors. DOE approval will be |
| required for the preliminary design, the final design, and |
| initiation of procurement of long lead items. Operation of the |
| facility will be the sole responsibility of RCUC. |
| |
| Technical decision on the management of the facility, during DOE's |
| dedicated operating periods, will be made jointly by representatives |
| of RCUC and the Department of Energy. RCUC will monitor daily |
| operation and collect date. |
| |
| The RCUC stresses quality control and quality assurance in all |
| aspects of its operation. Quality assurance programs are designed |
| into every facet of the RCUC's operation and are highly successful |
| in providing utilities for up to 80,000 visitors per day plus a base |
| population of 35,000 people at Walt Disney World. Quality assurance |
| at Walt Disney World results primarily from emphasis on planning and |
| the employment of competent professionals and technicians. These |
| procedures, coupled with strong management and administrative |
| control, will provide the same high level of quality assurance in |
| constructing and operating the cold demonstration facility as in the |
| other utilities operated by the company. |
| |
| (c) Prior Year Achievements |
| ----------------------- |
| Engineering design for the facility and the process were completed |
| and construction started. |
| |
| (d) CY Achievements |
| --------------- |
| Civil/structural (building, site, and utilities) were completed. |
| Installation of process equipment was started. Process equipment |
| checkout was started. |
| |
| (e) Reasons for Increases and Decreases |
| ----------------------------------- |
| The TEC for this project has increased by $5,085,000 from the data |
| sheet which supported the FY 19BY Budget Request because: |
| |
| o The original estimate was parametric, we now have fixed-price |
| bids (1-1/2 years later). |
| o Scope changes have been made including building, adding a second |
| overhead crane, and a redundant induced draft fan. |
| o Escalation. |
| |
| o Project start delayed 5 months due to difficult agreement |
| negotiations. |
| o Design/construction schedule had to be extended by 5 months. |
|__________________________________________________________________________|
Figure II-7
Construction Project Data Sheets
Operating Expenses Funded
(Continued)
Section 47
____________________________________________________________________________
| Reedy Creek Utilities Demonstration Plant |
| Idaho Operations Office |
| |
| Total Estimated Cost (TEC) $14,945,000 |
| |
| (Tabular dollars in thousands. Narrative material in whole dollars.) |
| ------------------------------------------------------------------------ |
| (f) Cost Estimate |
| ------------- |
| The costs shown are based on RCUC's final design, appropriately 20% |
| of construction complete, and fixed-price contracts for the bulk of |
| remaining work. The DOE funding outlined in this schedule is |
| limited to the actual design, construction, and checkout periods. |
| The operation of the facility will be the sole responsibility of |
| RCUC with the first year to be devoted exclusively to DOE testing. |
| DOE funding for the Ready Creek testing program is at included in |
| this schedule. |
| Item Cost Total Cost |
| --------- ---------- |
| 1. Engineering, design, and inspection, and |
| project management at 34% of construction |
| costs, Item 2 $ 3,770 |
| |
| 2. Construction costs 11,020 |
| (a) Improvements to land $ 450 |
| (b) Buildings and structures 3,570 |
| (c) Process equipment 5,950 |
| (d) Utilities 550 |
| (e) Startup 500 _______ |
| Subtotal 14,790 |
| |
| 3. Contingency @ approximately 1% of above costs 155 |
| |
| Total Estimated Cost $14,945 a/|
| ======= - |
| -------------------------------- |
| a/ Facility construction will be accomplished by fixed-price contracts |
| and procurements. Estimate is based on fixed-price bids and quotes |
| now in hand. Escalation is at separately identified in these |
| fixed-price commitments. |
|__________________________________________________________________________|
Figure II-7
Construction Project Data Sheets
Operating Expenses Funded
(Continued)
Section 48
____________________________________________________________________________
| Reedy Creek Utilities Demonstration Plant |
| Idaho Operations Office |
| |
| Total Estimated Cost (TEC) $14,945,000 |
| |
| (Tabular dollars in thousands. Narrative material in whole dollars.) |
| ------------------------------------------------------------------------ |
| Incorporation of Fallout Shelters: Indicate whether shelter space is |
| ---------------------------------- |
| included. If not, give the rationale why it is not included. |
| |
| Federal Compliance with Pollution Control Standards: Indicate measures |
| ---------------------------------------------------- |
| taken, if necessary, to control environmental pollutants and indicate |
| that those costs are included in the TEC. |
| |
| Evaluation of flood Hazards: Indicate whether or not flood hazards have |
| ---------------------------- |
| been considered. If located in a flood plain, indicate mitigating |
| action planned. |
| |
| Environmental Impact: Indicate status of compliance with the National |
| --------------------- |
| Environmental Policy Act and if the project is located in a floodplain/ |
| wetland. |
| |
| Accessibility for the Handicapped: Provide a statement indicating |
| ---------------------------------- |
| accessibility for the Handicapped in accordance with the Architectural |
| Barriers Act (Public Law 90-480) and the Federal Property Management |
| Regulations (41 CFR 101-19.6). |
|__________________________________________________________________________|
Figure II-7
Construction Project Data Sheets -
Operating Expenses Funded
(Continued)
(5) Federal Manpower Justification. Federal manpower requests are
to be justified in narrative form on a decision unit basis for
program organizations. For organizations budgeted for in the
Departmental administration appropriation, these justifications
are to be done on an organizational basis. Staffing levels must
be justified for each request level contained in the budget
submission to OMB. Organizations should be very specific in
formulating this narrative. It should clearly indicate the
differences, if any, from the FY 19CY staffing level and contain
an explanation of the difference whether it is an increase or a
decrease. In cases where increases above the FY 19CY level are
being requested, the justification should be very precise and
provide a level of detail that will enable the OMB staff to
fully evaluate the programmatic and functional impacts of the
request.
Section 49
(6) Manpower Figures.
(a) The first tier organization preparing a budget is required
to submit an overall summary of Federal civilian manpower
requirements by appropriation, decision unit, and
organization using either Figure II-8, II-9, or II-10.
(The stub for Figure II-9 must be exactly the same as the
stub on the manpower controls). Some organizations may be
asked to provide more detail on manpower distributions and
will be contacted separately if additional information is
required.
(b) Organizations included in the Departmental administration
appropriation will distribute their manpower requirements
to the major internal organization level.
(c) Full-time permanent employment generally is for those
positions established for a year or more whose incumbents
are expected to work 40 hours per week. The other than
full-time permanent category includes for budget purposes
full-time temporary, part-time (both temporary and
permanent) and intermittent employment subject to OMB
ceiling controls. Youth opportunity programs
(Stay-in-School and Federal Junior Fellowship) are excluded
from the other than full-time permanent category.
(d) Figures II-8, II-9, and II-10 are not to be included in the
budget materials to go to OMB, but are to be submitted
directly to the Office of Organization and Management
Systems.
____________________________________________________________________________
| DEPARTMENT OF ENERGY |
| FY 19BY OMB BUDGET |
| |
| Summary of Staffing Included in Major Activities |
| |
| SUMMARY OF FULL-TIME EQUIVALENT - PROGRAM ORGANIZATIONS |
| ------------------------------------------------------- |
| FY 19BY REQUEST |
| Organization: _________________________ ______________________________ |
| OMB Program |
| Decremental Target Planning |
| Appropriation/Major FY 19BY FY 19CY Level Level Level |
| Activity/Organization FTP Total FTP Total FTP Total FTP Total FTP Total|
| --------------------- --------- --------- ----------- --------- ---------|
| ABC Appropriation: |
| |
| Decision Unit |
| Decision Unit |
| Headquarters |
Section 50
| Operations Office X |
| Operations Office Y |
| |
| Decision Unit |
| Headquarters |
| Project Office A _________ _________ ___________ _________ _________|
| Subtotal ABC |
| Appropriation |
| |
| DEF Appropriation: |
| |
| Decision Unit |
| Decision Unit |
| Headquarters |
| Operations Office X _______ _________ ___________ _________ _________|
| Subtotal DEF |
| Appropriation |
| ---------------------------------------------------|
| |
| Organizational Recap: |
| |
| Headquarters |
| Operations Office X |
| Operations Office Y |
| Project Office A |
| _________ _________ ___________ _________ _________|
| |
| Total |
|__________________________________________________________________________|
Figure II-8
Summary of Full-Time Equivalent -
Program Organizations
____________________________________________________________________________
| DEPARTMENT OF ENERGY |
| FY 19BY OMB BUDGET |
| |
| Summary of Staffing Included in Major Activities |
| |
| SUMMARY OF FULL-TIME EQUIVALENT - HEADQUARTERS STAFF ORGANIZATION |
| |
| FY 19BY REQUEST |
| Organization: _________________________ ______________________________ |
| OMB Program |
| Decremental Target Planning |
| Appropriation/Major FY 19BY FY 19CY Level Level Level |
| Activity/Organization FTP Total FTP Total FTP Total FTP Total FTP Total|
| --------------------- --------- --------- ----------- --------- ---------|
| APPROPRIATION: |
| -------------- |
| Office of the Assistant |
| Secretary |
| (Director, etc.) |
| |
Section 51
| Office of ... |
| |
| Office of ... |
| |
| Office of ... |
| |
| Office of ... |
| |
| |
| _________ _________ ___________ _________ _________|
| Total ========= ========= =========== ========= =========|
| |
|__________________________________________________________________________|
Figure II-9
Summary of Full-Time Equivalent -
Headquarters Staff Organization
____________________________________________________________________________
| DEPARTMENT OF ENERGY |
| FY 19BY OMB BUDGET |
| |
| Summary of Staffing Included in Major Activities |
| |
| SUMMARY OF FULL-TIME EQUIVALENT - OPERATIONS OFFICES |
| |
| FY 19BY REQUEST |
| Organization: _________________________ ______________________________ |
| OMB* Program* |
| Decremental* Target Planning |
| Appropriation/Major FY 19PY FY 19CY Level Level Level |
| Activity/Organization FTP Total FTP Total FTP Total FTP Total FTP Total|
| --------------------- --------- --------- ----------- --------- ---------|
| ABC APPROPRIATION: |
| |
| Program Support |
| Office of the |
| Manager |
| Office of the |
| General Counsel |
| .... for Administration |
| .... for XXXXX |
| .... for YYYYY |
| Subtotal Program ________ _________ ___________ _________ _________|
| Support |
| |
| Program:** |
| |
| Fossil |
| .... |
| .... |
| Energy Research |
| .... |
| Defense |
| .... |
Section 52
| .... |
| Nuclear |
| .... |
| .... |
| Subtotal Program ________ _________ ___________ _________ _________|
| |
| Total ABC |
| Appropriation __________________________________________________|
| |
| DEF Appropriation: |
| |
| Program Support ________ _________ ___________ _________ _________|
| |
| Total ======== ========= =========== ========= =========|
| |
| * Subject to official designation in the budget call. |
| ** Identify all program with 1 or more FTEs in any year. |
|__________________________________________________________________________|
Figure II-10
Summary of Full-Time Equivalent
Operations Offices
e. Computer Materials (Fall Overview). The computer materials listed in
OMB Circular A-11, section 15.1, will be submitted (prior to 10-1)
according to dates to be supplied by OMB. The computer materials
consist of: receipt estimates; supplementary source data; multi-year
planning estimates projections; and current services estimates. The
information will be revised to reflect reestimates, approved
administration initiatives and policy guidance, and completed
congressional action. FY 19BY and approved FY 19BY + 4 data will not
be included on the listings but must be filled in by the program
organizations. Budget requests not reflecting latest policy guidance
will not be acceptable as the basis for revision. All materials will
be revised subsequent to reflect OMB and Presidential decisions,
reestimates, congressional action, and new assumptions. Unlike the
justifications, the computer materials should reflect actual
appropriation amounts and should not be made comparable with the
budget year. The data in each of the budget schedules must be
complete and internally consistent. Consistency is also required
between the various schedules within each account. The following
checklists will assist in determining completeness, internal
consistency, and the consistency of the same data in different
schedules.
(1) Checklist for Supplementary Source Document.
(a) General.
1 Is the correct identification code entered on each page
of the schedule?
2 In section A, "Analysis of Budget Authority and Outlays":
a Are all the required columns filled in on the budget
authority and outlay lines?
Section 53
b Are the amounts for each coded line and the totals
for budget authority and outlays the same as on the
program and financing schedule?
c Where memorandum entries are required, do they agree
with supporting data? (For example, "Appropriation
to liquidate contract authority" must be same as line
coded 40.49 or 60.49 on the program and financing
schedule.)
3 In section B "Distribution of Outlays":
a Do the totals of the columns add to the total outlays
in section A?
b The amounts on line 311 may not exceed the amounts
for new budget authority for each year as shown on
lines coded 40 through 50 on the program and
financing schedule. Similarly, line 312 may not
exceed lines 60 through 69 on the program and
financing schedule.
c The amount on line 313 for each year may not exceed
the obligated balances on lines coded 72 (or 72 with
two-digit suffix) on the program and financing
schedule.
d The amount on line 314 for each year may not exceed
the unobligated balances on lines coded 21 (or 21
with two-digit suffix) on the program and financing
schedule.
e The memo entry amount on line 315 may not exceed the
amount of the memo entry for "Appropriations to
liquidate contract authority" in section A of the SSD
for each year.
4 In section C, "Character Classification":
a Are the totals of budget authority and outlays the
same as in section A for each year?
b Is each separate function in this section treated as
though it were a separate account?
c Are proper character codes shown in each line entry?
(2) Checklist for Current Services Estimates SSSD-S-L.
(a) Detail Data Processing.
1 Are current services estimates provided for each program
and financing schedule that has a transmittal code of
"O"?
2 Is an "S" written at the top of each page?
3 Is the 11-digit identification code for each account
correct? This code is shown on the program and
financing (P and F) schedules in the OMB budget appendix
for the budget year.
4 Are the line codes indicated the same as those in the
program and financing schedule for the account?
2. OTHER OMB MATERIALS. The other OMB materials comprise the final part of
the initial OMB submission. Refer to the OMB Circular A-11 section
shown parenthetically below for specific guidance. Guidance concerning
additional materials is provided below. Typically, the other OMB
materials include: Information in Rental Payments to GSA, (24.3);
Analysis of National Climate Program Activities, (24.4); Data on
Research and Development, (44.1 - 55.4); and Data on Social Research and
Development Activities, (48.1 - 48.5).
Section 54
a. Telecommunications. Where FY 19BY estimates for telecommunications
requirements exceed $1 million or are more than 10 percent of the
total estimate for a decision unit, additional information should be
provided (Figure II-11). In these cases, the telecommunication
systems and services should be described and justified in a
narrative statement reflecting quantifiable benefits in terms of
increased productivity, reduced costs or decreased levels of
staffing attributable to the effective use of communications
technology. Questions on telecommunications requirements may be
addressed to the Division of Telecommunications, MA-253.
b. Major Computer Requirements. Each organization should identify and
justify all major items of ADP equipment proposed for the budget
year (BY) in the appropriate decision unit of the funding or
landlord program; and submit a consolidated crosscut summary
computer table of all major items of ADP equipment for the past year
(PY), the current year (CY), and BY. Each of these requirements is
discussed below.
(1) Major Item Identification. A major item of ADP equipment is
defined as an component or group of components having a total
estimated purchase cost of $400,000 or more including related
capitalizable costs. The determining factor for a major item
of ADP equipment is the estimated purchase cost of the item
irrespective of the type of funding used or whether the actual
method of acquisition is purchase, lease, or some combination
of the two. Thus, a leased item of ADP equipment is a major
item if the estimated purchase cost of the item is $400,000 or
more even if the annual lease cost is less than $400,000. All
major items of ADP equipment proposed for the BY must be
separately identified and justified in the appropriate
narrative material supplied by the funding or landlord program.
This separate identification and justification pertains to all
major items of ADP equipment regardless of whether they are
proposed for lease or purchase or whether they are to be funded
from operating, capital, or construction funds. In cases where
major items of ADP equipment are funded from operating expenses
by a single program, the total annual cost of the lease, or
lease to ownership, must be shown by the funding program. In
those cases where major items of ADP equipment are funded from
operating expenses by multiple programs, the total annual cost
of the lease, or lease to ownership, must be shown by the
program having budget responsibility for general purpose
equipment at that location. Where appropriate, however, it
should be noted that the actual costs will be shared
programmatically according to a charge-back plan based upon
utilization.
(2) Major Computer Requirements Crosscut Summary. In addition to
the requirement to identify and justify all major items of ADP
equipment in the narrative material as described above, the
Department is required to prepare a crosscut summary computer
table which specifically lists each major item of ADP
Section 55
equipment, except for items funded from construction projects,
utilizing/requiring funds during either the PY, CY, or BY. The
Office of ADP Management (MA-24) is responsible for
coordinating the preparation of this consolidated Department
crosscut computer table and assuring its timely submittal to
OMB. In order to assure that the information contained in the
table accurately reflects the latest budget decisions, MA-24
will require the assistance of Headquarters program divisions
prior to the OMB submittal. Accordingly, based upon the
results of the internal review, MA-24 will prepare an initial
crosscut computer table for cognizant program review and
markup. After this review process is completed, MA-24 will
prepare a final Depa