DOE M 151.1-1, Power Marketing Administration Emergency Management Program Manual
Functional areas: Emergency Preparedness, Safety and Security
This Manual establishes emergency management policy and requirements for emergency planning, preparedness, readiness assurance, and response for the Department's Power Marketing Administrations. Canceled by DOE O 151.1D.
Supersedes DOE O 5500.11.
Related To:
Version history and related documents
Supersedes
Earlier documents this one replaced.
Related documents
- DOE G 151.1-4Response Elements
- DOE G 151.1-3Programmatic Elements
- DOE G 151.1-5Biosafety Facilities
- DOE O 151.1CComprehensive Emergency Management System
- DOE G 151.1-2Technical Planning Basis
- DOE G 151.1-1AEmergency Management Fundamentals and the Operational Emergency Base Program
- DOE O 151.1CComprehensive Emergency Management System
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
AVAILABLE ONLINE AT: INITIATED BY:
www.directives.doe.gov National Nuclear Security Administration
Office of Emergency Operations
MANUAL
Approved: 9-18-08
POWER MARKETING ADMINISTRATION
EMERGENCY MANAGEMENT
PROGRAM MANUAL
U.S. DEPARTMENT OF ENERGY
Office of Emergency Operations
DOE M 151.1-1
DOE M 151.1-1 1
9-18-08
POWER MARKETING ADMINISTRATION
EMERGENCY MANAGEMENT PROGRAM MANUAL
1. PURPOSE. This Manual establishes emergency management policy and requirements
for emergency planning, preparedness, readiness assurance, and response for the
Department of Energy (DOE) Power Marketing Administrations (PMAs). This Manual
clarifies DOE O 151.1C, Comprehensive Emergency Management System,
requirements for specific application to PMAs and is compatible with emergency
preparedness and disaster reporting requirements of the electric utility industry.
2. CANCELLATIONS. This Manual cancels DOE 5500.11, Power Marketing
Administration Emergency Management Program, dated 5-9-94.
3. APPLICABILITY.
a. DOE Elements.
(1) The provisions of this Manual apply to all PMAs (Bonneville Power
Administration, Southeastern Power Administration, Southwestern
Power Administration, and Western Area Power Administration).
(2) The Office of Emergency Operations within the National Nuclear
Security Administration and the Office of Public Affairs have limited
responsibilities in coordinating emergency management with the PMAs.
b. DOE Contractors. This Manual does not apply to contractors.
c. Exclusions. Except for the DOE elements listed in paragraph 3a, all other DOE
elements are excluded.
4. REQUIREMENTS.
a. Background.
(1) The PMAs operate and maintain electric power transmission systems
and market electric power in 37 states. The Bonneville, Southwestern,
and Western Area Power Administrations operate and maintain
electrical transmission facilities. The Southeastern Power
Administration has only power marketing responsibilities.
(2) PMAs provide wholesale electrical power in coordination with the
North American Electric Reliability Council (NERC) and the
appropriate regional councils within NERC.
(3) PMAs have unique requirements because their primary energy
infrastructure mission is different from other DOE facilities.
2 DOE M 151.1-1
9-18-08
(4) The PMAs respond to operational emergencies and energy emergencies
and provide emergency assistance. Operational emergencies include
natural phenomena (e.g., earthquakes, tornadoes), wild land fires, and
other serious events involving or affecting the facility or having
potential to have serious impacts on health and safety, electric
reliability, the environment, safeguards, and security. Energy
emergencies include all actions taken to ensure the balance generation
and load to ensure reliability of the electric interconnection. This
impacts continuity of PMA business objectives and operations.
Emergency assistance includes PMA offers of resources to support
other electric utilities, a State or local authority or other government
agencies in emergency response.
b. Hazards Survey/Hazards Assessment.
(1) Hazards Survey. See DOE O 151.1C, Chapter III.
(2) Hazards Assessment. See DOE O 151.1C, Chapter IV.
c. Program Administration.
(1) An individual must be designated to ensure the development and
maintenance of the emergency plan and procedures, development of the
emergency readiness assurance plan (ERAP), development and conduct
of training and exercise programs, coordination of self-assessment
activities, development of related facility documentation, and
coordination of facility emergency resources.
Section 2
(2) The emergency plan must document the emergency management
program, including provisions for response to an operational
emergency.
(3) Emergency plan implementing procedures (EPIPs) must describe how
emergency plans will be implemented.
(4) Emergency plans and procedures must—
(a) clearly state roles, responsibilities, and requirements associated
with program administration, individual positions, operations,
and interfaces and
(b) be reviewed annually and updated as necessary.
(5) An Emergency Operating Records Protection Program must be
established to ensure that vital records, regardless of media, essential to
the continued functioning or reconstitution of an organization during
DOE M 151.1-1 3
9-18-08
and after an emergency, are available, per Title 36 Code of Federal
Regulations (CFR) 1236, Management of Vital Records.
d. Training and Drills.
(1) Training must be provided to all onsite workers who may be required to
take protective actions (e.g., assembly, evacuation). This training is
required upon initial employment. Refresher training must be provided
when plans, procedures, systems/equipment, or their expected
protective actions change. Refresher training must also be provided
annually to those workers who are likely to witness a hazardous
material release and who are required to notify proper authorities of the
release.
(2) Emergency-related information and training on facility-activity and
site-specific conditions and hazards must be offered to offsite
emergency response personnel and organizations, including hospitals,
that are expected to support onsite response efforts.
e. Exercises.
(1) At a minimum, each site/facility must conduct building evacuation
exercises consistent with Federal regulations (e.g., 41 CFR 102-74-360,
What are the Specific Accident and Fire Prevention Responsibilities of
Occupant Agencies?), local ordinances, or appropriate National Fire
Protection Association Standards. Exercises must be conducted at least
annually to ensure that employees are able to safely evacuate their work
area.
(2) For each facility or activity, the organization responsible for
communications with DOE Headquarters and/or offsite agencies must
test communications systems annually or as often as needed to ensure
that communications systems are operational.
f. Readiness Assurance.
(1) Self-Assessment. Each PMA must assess their emergency management
program annually and record the results of the self-assessment in the
ERAP.
(2) Corrective Actions. These requirements supplement those in
DOE O 414.1C, Quality Assurance. Continuous improvement in the
emergency management program results from implementation of
corrective actions for findings (e.g., deficiencies, weaknesses) in all
types of evaluations, including both internal and external evaluations.
4 DOE M 151.1-1
9-18-08
(a) Corrective action plans for external evaluations must be
developed within 30-working days of receipt of the final
evaluation report.
(b) Corrective actions must be completed as soon as possible.
(c) Corrective actions addressing revision of procedures or training
of personnel should be completed before the next annual
self-assessment of the program.
(d) Completion of corrective actions must include a verification and
validation process, independent of those who performed the
corrective action, that verifies that the corrective action has been
put in place, and validates that the corrective action has been
effective in resolving the original finding.
Section 3
(3) Lessons Learned. The readiness assurance program must include a
system for incorporating and tracking lessons learned from training,
drills, actual responses, and a PMA-wide lessons learned program.
(4) Emergency Readiness Assurance Plans (ERAPs). Each PMA must
submit an ERAP, summarizing its programs, to the Director, Office of
Emergency Operations, by November 30 of each year. In keeping with
Title 31 United States Code (U.S.C.) 1115 and 1116, Government
Performance Results Act, this report must identify what the goals were
for the fiscal year that just ended (on September 30) and the degree to
which these goals were accomplished. This report must also identify the
goals for the current fiscal year (which started on October 1).
g. Emergency Response Organization. An individual (e.g., building or facility
manager or similar position) must be assigned and trained to manage and
control all aspects of the facility/activity response.
h. Offsite Response Interfaces. If applicable, prior to and during emergencies,
coordination must be maintained with State, Tribal, and local agencies and
organizations responsible for offsite emergency response (e.g., “911”
emergencies) and for protection of public health and safety.
i. Emergency Categorization and Classification.
(1) Facility-specific criteria/means/indicators to recognize abnormal events
or conditions as Operational Emergencies must be developed. The
definitions of Operational Emergencies are as found in DOE O 151.1C,
Chapter V. Specific criteria must be developed for the spectrum of
emergency conditions identified in the Hazards Survey or the
Emergency Planning Hazards Assessment, if necessary.
DOE M 151.1-1 5
9-18-08
(2) An event must be categorized as an Operational Emergency as promptly
as possible, but no later than 15 minutes after event
recognition/identification/discovery.
(3) In addition to Operational Emergencies, PMA must categorize electrical
emergencies as described in 10 CFR 205.350, Report of Major Electric
Utility Emergencies.
j. Notifications and Communications.
(1) PMA notifications for electrical emergencies must be conducted in
accordance with 10 CFR 205.350 and applicable DOE Manuals.
(2) Each facility and activity must establish procedures for prompt initial
notification of other operational emergencies to workers, emergency
response personnel, and response organizations, including, as
appropriate, DOE or NNSA elements and other Federal, tribal, State,
and local organizations. Provisions must also be established for
continuing effective communication among response organizations
throughout an emergency.
(a) The PMA must notify DOE Headquarters operations center as
promptly as possible but no more than 30 minutes after an event
has been categorized as an other operational emergency.
(b) As appropriate, other applicable Federal, tribal, State, and local
organizations are notified as promptly as possible, but no more
than 30 minutes after an event has been categorized as an other
operational emergency or within an interval established in
mutual agreements.
(c) At a minimum, notification of other operational emergencies to
the Headquarters Operations Center must consist of a phone call
providing as much information as is known at the time. The
same information must be provided by e-mail or a fax either
immediately prior to or following the phone call. Information
for initial notification includes as much as possible of the
following:
Section 4
1 that an other operational emergency has been declared,
2 the description of the emergency,
3 the date and time the emergency was discovered,
4 the damage and casualties,
6 DOE M 151.1-1
9-18-08
5 whether the emergency has stopped other facility/site
operations or program activities,
6 the protective actions taken and/or recommended,
7 other notifications made,
8 the weather conditions at the scene of the emergency,
9 the level of any media interest at the scene of the
emergency or at the facility/site, and
10 the contact information of the DOE on-scene point of
contact.
(3) Emergency status updates/situation reports must be forwarded to DOE
Headquarters on a continuing basis until the emergency is terminated.
(4) Following termination of emergency response, and in conjunction with
the Final Occurrence Report (see DOE M 231.1-2), each activated
Emergency Management Team must submit a final report on the
emergency response to the Emergency Manager for submission to the
Director, Office of Emergency Operations.
(5) Reporting requirements must be specified during recovery planning.
(6) All reports and releases must be reviewed for proprietary information
and marked appropriately.
k. Consequence Assessment. Provisions must be in place to determine the impact
of other operational emergencies on workers at PMA facilities.
l. Protective Actions and Reentry.
(1) Plans must be developed for the timely evacuation and/or sheltering of
onsite personnel, along with provisions to account for employees after
emergency evacuation has been completed.
(2) In the event of a facility emergency evacuation, accountability actions
must be continued to support ongoing search and rescue activities.
(3) Provisions must be in place to protect workers involved in response and
cleanup covered by 29 CFR 1910.120, Hazardous Waste Operations
and Emergency Response (HAZWOPER).
(4) Reentry planning must include contingency planning to ensure the safety
of reentry personnel, such as planning for the rescue of reentry teams. All
individuals involved in reentry must receive a hazards/safety briefing
DOE M 151.1-1 7
9-18-08
before emergency response activities consistent with Federal, tribal, State,
and local laws and regulations.
m. Emergency Medical Support. Provisions for response to emergency medical
situations and medical treatment of injured personnel must be implemented, as
required by 29 CFR 1910.151, Medical Services and First Aid. In addition,
planning for mass casualty situations must be conducted in accordance with
DOE O 440.1B and 10 CFR 851, Worker Safety and Health Program. Sharing
patient information between onsite and offsite health care providers during
emergencies must be coordinated in advance and consistent with the requirements
of HIPAA.
n. Emergency Public Information.
(1) The PMA must provide accurate, candid, and timely information
consistent with requirements of the Freedom of Information Act and the
Privacy Act to ensure the health and safety of workers and the public
during all emergencies and must establish facts, avoid rumors and
speculation, and be responsive to public concern and information needs.
(2) Procedures must be in place to address media inquiries and, as necessary,
conduct briefings or press conferences for other operational emergencies.
(3) Initial news releases or public statements must be approved by the PMA
official responsible for emergency public information review and
dissemination. Following initial news releases and public statements,
updates must be coordinated with the DOE Director of Public Affairs and
the Headquarters Emergency Manager.
Section 5
o. Emergency Facilities and Equipment. Facilities and equipment must be adequate
to support emergency response, including the capability to notify employees of an
emergency and to facilitate their safe evacuation from work areas.
p. Termination and Recovery.
(1) Predetermined criteria for terminating emergencies must be
established/developed, and the termination must be coordinated with
offsite agencies.
(2) Recovery must include notifications about the termination and
establishment of criteria for resumption of normal operations.
(3) The facility and the accident investigation team must coordinate or
integrate their activities to facilitate an orderly transition of
responsibilities for the emergency scene. [DOE O 225.1A, Accident
Investigation]
8 DOE M 151.1-1
9-18-08
q. Implementation.
(1) Full compliance with the requirements of this Manual must be
accomplished within 1 year of its issuance.
(2) If compliance is not or cannot be completed within 1 year from issuance
of this Manual, an implementation schedule must be developed by the
PMA and submitted with the Emergency Readiness Assurance Plan due
November 30, 2009.
(3) Non-mandatory implementation guidance for DOE O 151.1C and this
Manual is published separately in the multi-volume DOE G 151.1-1 series
of Emergency Management Guides (or replacements). The
DOE G 151.1-1 series provides non-mandatory, supplemental information
about preferred methods for implementing requirements, including lessons
learned, suggested practices, instructions, and suggested performance
measures.
r. Exemptions.
(1) If a DOE element can demonstrate that it is subject to emergency
management program requirements under the authority of other Federal
regulatory agencies and those requirements are at least as stringent as the
requirements of this Manual, an exemption may be requested.
(2) Requests for exemptions from the requirements of this Manual, including
specific program element requirements, must include the basis for the
request and describe and justify alternatives equivalent to or exceeding
this Manual.
(3) Requests for exemptions are jointly approved by the PMA Administrator
and the Director of Emergency Operations, with conflicts resolved by the
Deputy Secretary or designated Departmental Chief Operating Officer.
(4) Each PMA Administrator defines “facility(ies)” for the purpose of
implementing this Manual. PMAs may group activities and operations for
certain requirements as suits their organizational needs without requesting
an exemption.
5. RESPONSIBILITIES.
a. Deputy Secretary or Designated Departmental Chief Operating Officer.
(1) Resolves conflicts when requests for exemptions from the requirements of
this Manual are not agreed to between the PMA and the Director, Office
of Emergency Operations.
DOE M 151.1-1 9
9-18-08
(2) Other responsibilities are listed in DOE O 151.1C, Chapter I.
b. Director, Office of Emergency Operations.
(1) Serves as the primary point of contact for the overall emergency planning
and operations activities and termination of emergency responses.
(2) In coordination with each PMA Administrator, approves requests for
exemptions from the requirements of this Manual.
(3) Other responsibilities are listed in DOE O 151.1C, Chapter I.
c. PMA Administrators.
(1) Due to each PMA’s unique enabling legislation and scope of their regional
responsibilities, the PMA Administrators are responsible for the
development, approval, implementation and management of their
individual emergency management programs.
Section 6
(2) Designate by name, title, or position a person to manage the PMA
emergency management program, receive PMA emergency notifications,
participate in any Headquarters response, and attend Headquarters
Comprehensive Emergency Management System meetings or planning
activities that involve, or may involve, PMAs.
(3) Establish and maintain integrated plans and procedures detailing
responsibilities for emergency response. Ensure that all emergency plans
and procedures—
(a) are consistent with the requirements of this Manual, electric utility
reliability criteria, and appropriate PMA business objectives and
operations;
(b) provide support, within resource constraints, to energy
emergencies and emergency assistance;
(c) are coordinated with the appropriate Departmental elements and,
where applicable, with other Federal agencies; Tribal, State, and
local governments; and other utilities;
(d) provide for a continuing program of emergency management
training, drills, and exercises, including participation of employees
as required;
(e) provide opportunities for participation by appropriate utilities and
local, State, and Tribal organizations in such drills and exercises;
and
10 DOE M 151.1-1
9-18-08
(f) are reviewed and updated at least annually.
(4) Establish a formal procedure to keep copies of emergency plans,
procedures, and associated documents up to date and accessible at
locations where they may be needed during an emergency.
(5) Establish a program to ensure that vital records, regardless of media,
essential to the continued functioning or reconstitution of an organization
during and after an emergency, are available, per 36 CFR 1236.
(6) Ensure that supporting mutual assistance agreements are developed with
Tribal, State, and local governments and other utilities, where appropriate,
and maintained on record.
(7) Ensure that immediate emergency response is initiated and followed up
with appropriate recovery and restoration activities.
(8) Ensure that their public affairs office is part of emergency planning and
response.
(9) Assess the PMA emergency management program annually and record the
results of the self-assessment in the ERAP.
(10) Ensure that potential hazards are reviewed and documented for emergency
planning purposes.
(11) In coordination with the Director, Office of Emergency Operations
approve requests for exemptions from the requirements of this Manual.
d. DOE Director of Public Affairs and the Headquarters Emergency Manager. In
accordance with this Manual as well as the responsibilities in DOE O 151.1C,
Chapter I, coordinate updates of initial news releases and public statements with
the PMAs.
6. REFERENCES.
a. Title 31 U.S.C. 1115 and 1116, Government Performance Results Act.
b. Title 42 U.S.C 300, Health Insurance Portability and Accountability Act
(HIPAA).
c. Title 10 CFR 205.350, Report of Major Electric Utility Emergencies.
d. Title 10 CFR 851, Worker Safety and Health Program.
e. Title 29 CFR 1910.120, Hazardous Waste Operations and Emergency Response
(HAZWOPER).
DOE M 151.1-1 11 (and 12)
9-18-08
f. Title 29 CFR 151, Medical Services and First Aid.
g. Title 36 CFR 1236, Management of Vital Records.
h. Title 41 CFR 102-74-360, What are the Specific Accident and Fire Prevention
Responsibilities of Occupant Agencies?
i. DOE O 151.1C, Comprehensive Emergency Management System, dated 11-2-05.
j. DOE O 225.1A, Accident Investigation, dated 11-26-97.
k. DOE M 231.1-2, Occurrence Reporting and Processing of Operations
Information, dated 8-19-03.
l. DOE O 414.1C, Quality Assurance, dated 6-17-05.
m. DOE O 440.1B, Worker Protection Management for DOE (Including the
National Nuclear Security Administration) Federal and Contractor Employees,
dated 5-17-07.
7. CONTACT. For assistance regarding this directive, contact the Director of Emergency
Operations at 202-586-9892.
BY ORDER OF THE SECRETARY OF ENERGY:
JEFFREY F. KUPFER
Acting Deputy Secretary