DOE G 226.1-2, Federal Line Management Oversight of Department of Energy Nuclear Facilities
Functional areas: Facility Safety, Nuclear Safety, Oversight
The purpose of this Guide is to provide U.S. Department of Energy (DOE) line management with guidance that may be useful to them in effectively and efficiently implementing the requirements of DOE O 226.1B, Implementation of Department of Energy Oversight Policy, date April 25, 2011, as applied to Federal line management of hazard category 1, 2, and 3 nuclear facilities.
Version history and related documents
Superseded by
A newer version replaces this document.
Related documents
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
AVAILABLE ONLINE AT: INITIATED BY:
www.directives.doe.gov Office of Health, Safety and Security
DOE G 226.1-2
6-21-2012
FEDERAL LINE MANAGEMENT
OVERSIGHT OF DEPARTMENT OF
ENERGY NUCLEAR FACILITIES
[This Guide describes acceptable, non-mandatory means for meeting requirements. Guides are
not requirements documents and are not to be construed as requirements in any audit or
appraisal for compliance with associated rules or directives.]
U. S. DEPARTMENT OF ENERGY
Washington, DC
NOT
MEASUREMENT
SENSITIVE
http://www.directives.doe.gov/
DOE G 226.1-2 i (and ii)
6-21-12
FOREWORD
This Guide is approved for use by all Department of Energy (DOE), including National Nuclear
Security Administration, organizations.
Beneficial comments (recommendations, additions, deletions, and any pertinent data) that may
improve this document should be sent to:
Dr. Patricia Worthington
HS-10
U.S. Department of Energy
Washington, D.C. 20585
Phone (301) 903-5926
DOE guides are part of the DOE Directives System and are issued to provide supplemental
information regarding the Department’s expectations of its requirements as contained in rules,
Orders, Notices, and regulatory standards. This Guide does not establish or invoke any new
requirements.
This Guide was developed in support of DOE Order 226.1B, Implementation of Department of
Energy Oversight Policy. It provides guidance that may be useful to DOE line management
organizations in meeting the provisions of that order when applied to nuclear facilities.
DOE G 226.1-2 iii
6-21-12
Table of Contents
Acronyms .........................................................................................................................................v
1. INTRODUCTION ................................................................................................................... 1
1.1 Purpose ............................................................................................................................ 1
1.2 Scope ............................................................................................................................... 1
1.3 Background ..................................................................................................................... 2
1.4 Applicability and Exclusions .......................................................................................... 2
2. OVERVIEW OF DOE SAFETY OVERSIGHT PROGRAM ................................................ 3
2.1 Contractor Assurance System ......................................................................................... 4
2.2 DOE Line Management Oversight ................................................................................. 5
2.2.1 DOE Field Element Safety Oversight ....................................................................... 6
2.2.2 DOE Program Office Safety Oversight .................................................................... 7
2.2.3 Central Technical Authorities and Chief of Nuclear Safety/Chief of Defense
Nuclear Safety ......................................................................................................................... 7
2.2.4 Federal Training and Qualifications ......................................................................... 8
2.3 Independent Oversight and Other DOE and External Reviews ...................................... 8
Section 2
2.4 Overview of General and Detailed Guidance for Federal Line Management Safety
Oversight of Nuclear Facilities ................................................................................................... 8
3. GUIDANCE FOR FEDERAL LINE MANAGEMENT SAFETY OVERSIGHT OF
NUCLEAR FACILITIES ............................................................................................................. 11
3.1 Scope of DOE Line Management Program for Safety Oversight of Nuclear Facilities 11
3.2 Tailoring to Facilities, Activities, and Hazards ............................................................ 15
3.3 Designing and Implementing DOE Field Element Oversight Programs ...................... 17
3.3.1 Field Element Oversight Objectives for Nuclear Facilities .................................... 17
3.3.2 Field Element Mechanisms for Oversight of Nuclear Facilities ............................. 19
3.3.3 Field Element Nuclear Facility Oversight Plan ...................................................... 20
3.3.4 Integrated Oversight Plan ....................................................................................... 20
3.4 Designing and Implementing DOE Program Office Oversight Programs.................... 22
3.4.1 Program Office Oversight ....................................................................................... 22
3.4.2 CTA Oversight Functions ....................................................................................... 23
3.5 Evaluation Processes ..................................................................................................... 23
iv DOE G 226.1-2
6-21-12
3.5.1 Operational Awareness Activities........................................................................... 24
3.5.2 Assessments of Facilities, Operations, and Programs ............................................ 25
3.5.3 Assessments of the Contractor Assurance System ................................................. 26
3.5.4 Self-Assessment ...................................................................................................... 27
3.6 Issues/Corrective Action Management Program .......................................................... 27
3.6.1 Issue Identification and Resolution ......................................................................... 29
3.6.2 Feedback ................................................................................................................. 31
3.7 Performance Measures and Communications ............................................................... 32
4. DETAILED GUIDANCE FOR FEDERAL LINE MANAGEMENT SAFETY
OVERSIGHT OF NUCLEAR FACILITIES................................................................................ 35
4.1 Detailed Guidance for DOE Line Management Oversight of Core and Cross Cutting
Performance Areas for Nuclear Facilities ................................................................................. 35
4.1.1 Safety System Operability ...................................................................................... 35
4.1.2 Technical Safety Requirements Implementation .................................................... 38
4.1.3 Safety Management Program Implementation ....................................................... 44
4.1.4 Safety Management System Implementation ......................................................... 46
4.1.5 Formality of Operations Programs.......................................................................... 49
Section 3
4.1.6 Safety Culture ......................................................................................................... 51
4.2 Application of Criteria Review and Approach Documents .......................................... 54
4.2.1 Description of a CRAD ........................................................................................... 55
4.2.2 Available Sets of CRADs ....................................................................................... 56
Appendix A1: List of DOE Hazard Category 1, 2 and 3 Nuclear Facilities ............................... A-1
Appendix B1: Rules and Directives Applicable to Nuclear Facilities Line Management
Oversight ............................................................................................................. A-2
Appendix C1: Criteria Review and Approach Documents ......................................................... A-3
LIST OF FIGURES
Figure 1. DOE’s Multi-Tiered Approach to Safety Oversight ........................................................4
Figure 2. Overview of DOE Federal Line Management Oversight .................................................6
Figure 3. Framework for Nuclear Facility Oversight ....................................................................13
1 The appendices are available at http://www.hss.energy.gov/healthsafety/flmo/appendices/index.html
http://www.hss.energy.gov/healthsafety/flmo/appendices/index.html
DOE G 226.1-2 v (and vi)
6-21-12
ACRONYMS
AC Administrative Control
CAP Corrective Action Plan
CAS Contractor Assurance System
CDNS Chief of Defense Nuclear Safety
CFR Code of Federal Regulations
CNS Chief of Nuclear Security
CRAD Criteria Review and Approach Document
CRD Contractor Requirements Document
CTA Central Technical Authority
DNFSB Defense Nuclear Facilities Safety Board
DOE U.S. Department of Energy
DRB Directives Review Board
DSA Documented Safety Analysis
EFCOG Energy Facility Contractors Group
G Guide
HDBK Handbook
HSS Office of Health, Safety and Security
IG Inspector General
IOP Integrated Oversight Plan
ISM Integrated Safety Management
IV Independent Verification
IVR Implementation Verification Review
LOI Line of Inquiry
M Manual
NNSA National Nuclear Security Administration
NQA Nuclear Quality Assurance
NRC Nuclear Regulatory Commission
O Order
P Policy
PSO Program Secretarial Officer
QA Quality Assurance
SAC Specific Administrative Control
SCWE Safety Conscious Work Environment
SMP Safety Management Program
SR Surveillance Requirement
SSC Structures, Systems, and Components
SSO Safety System Oversight
STD Standard
STSM Senior Technical Safety Manager
TSR Technical Safety Requirement
USQ Unreviewed Safety Question
DOE G 226.1-2 1
6-21-12
1. INTRODUCTION
1.1 Purpose
The purpose of this Guide is to provide U.S. Department of Energy (DOE) line management
organizations with guidance that may be useful to them in effectively and efficiently
implementing the requirements of DOE O 226.1B, Implementation of Department of Energy
Oversight Policy, dated April 25, 2011, as applied to Federal line management of hazard
category 1, 2, and 3 nuclear facilities.
This Guide describes acceptable, non-mandatory means for meeting requirements contained in
DOE regulations and directives. This Guide provides flexible guidance that is intended to help
DOE organizations in their efforts to sustain effective line management oversight of nuclear
facilities. Guides are not requirements documents and are not to be construed as requirements in
any audit or appraisal for compliance with associated rules or directives.
Section 4
1.2 Scope
For the purposes of this Guide, “nuclear facilities” refers to facilities and related activities
authorized by the DOE Approval Authority within the scope of an approved safety basis for
nuclear facilities. Nuclear facilities currently include approximately 194 hazard category 1, 2,
and 3 nuclear facilities managed by the National Nuclear Security Administration (NNSA) and
the DOE Offices of Environmental Management, Science, and Nuclear Energy. These facilities
are listed in Appendix A (which is available at
http://www.hss.energy.gov/healthsafety/flmo/appendices/index.html). Designation of facilities as
hazard category 1, 2, or 3 may change as missions within facilities change.
Federal line management safety oversight programs include:
• Maintaining operational awareness and evaluating safety performance of both contractor- and
government-operated nuclear facilities,
• Evaluating the effectiveness of Federal line management safety oversight programs and
functions, such as self-assessments and Facility Representative programs,
• Central Technical Authority (CTA) and Chief of Nuclear Safety (CNS)/Chief of Defense
Nuclear Safety (CDNS) oversight of program offices, field elements, and contractors, and
• Managing issues and corrective action management systems.
This Guide is intended to complement, but not duplicate, other DOE guidance on safety
management, governance, quality assurance (QA), and oversight processes. For instance,
oversight of design and construction of a new, and major modification of an existing, nuclear
facility is covered by DOE-STD-1189-2008, Integration of Safety into the Design Process;
review and approval of nuclear facility safety basis documents is covered by DOE-STD-1104-
2009, Review and Approval of Nuclear Facility Safety Basis and Safety Design Basis
Documents; and activities associated with DOE authorization in the startup or restart process is
covered by DOE O 425.1D, Verification of Readiness to Start Up or Restart Nuclear Facilities.
http://www.hss.energy.gov/healthsafety/flmo/appendices/index.html
2 DOE G 226.1-2
6-21-12
This Guide focuses on the requirements that apply solely to nuclear facilities, such as Title 10
Code of Federal Regulations Part 830, Nuclear Safety Management (10 CFR 830), Subpart A,
Quality Assurance and Subpart B Safety Basis requirements to develop and implement quality
assurance programs, documented safety analyses (DSAs), technical safety requirements (TSRs),
and an unreviewed safety question (USQ) process. This Guide addresses only hazard category 1,
2, and 3 nuclear facilities. It does not address accelerator, radiological, and non-nuclear chemical
or industrial facilities, nor does it include guidance on oversight of security programs or business
elements. This Guide focuses on nuclear safety (i.e., programs and processes designed to prevent
or mitigate a release of radioactive materials or prevent uncontrolled or unmonitored radiation
exposure) and does not address industrial or worker safety within nuclear facilities (except to the
extent that industrial safety programs, such as electrical safety and maintenance, interface with
systems and mechanisms that ensure nuclear safety). However, DOE and contractor management
may find some of the information in this Guide useful in developing other aspects of oversight
programs.
Section 5
Section 2 of this Guide provides an overview of the overall current DOE oversight program to
provide context for the guidance relevant to the scope of this Guide. Sections 3 and 4 provide
general and detailed guidance for DOE line management oversight of nuclear facilities, which, as
stated above, is a subset of the DOE’s overall oversight program.
1.3 Background
DOE policy includes the expectation that safety oversight programs be established and
maintained to ensure that all aspects of nuclear-related work are conducted with the highest
standards of quality and safety. The essential requirements to implement that policy are
contained in DOE O 226.1B. This Guide provides guidance for implementing those
requirements.
The scope and content of this Guide are governed by DOE’s Directives Review Board (DRB). In
the justification memorandum for this Guide, the DRB established that the scope be limited to
Federal line management oversight of nuclear facilities and provide narrowly scoped information
for developing and implementing effective oversight processes.
DOE G 450.4-1C, Integrated Safety Management System Guide, and DOE HDBK 1188-2006,
Glossary of Environment, Safety and Health Terms, provide definitions of terms used in this
Guide. In a few cases, footnotes are used to provide additional information about terms used in
this Guide in the context of nuclear facility safety oversight.
1.4 Applicability and Exclusions
This Guide applies to all DOE organizational elements, including NNSA organizational
elements, that: (1) are covered by DOE O 226.1B and (2) have line management responsibility
for overseeing nuclear facilities. For simplicity, “DOE,” as used throughout this Guide, includes
the NNSA. The lists of DOE nuclear facilities and nuclear safety requirements applicable to
nuclear facilities are maintained in the web sites referenced in Appendices A and B.
DOE G 226.1-2 3
6-21-12
2. OVERVIEW OF DOE SAFETY OVERSIGHT PROGRAM
It is DOE policy to use a graded approach in safety programs. In the graded approach, the level
of rigor and resources needed to effectively provide oversight of a safety program is
commensurate with the magnitude of the hazards associated with the facilities. The graded
approach is established in such DOE regulations and directives as 10 CFR 830.3, Nuclear Safety
Management, Definitions; DOE O 414.1D, Quality Assurance; and DOE O 226.1B,
Implementation of Department of Energy Oversight Policy. These regulations and directives
have more detailed and stringent requirements for high hazard facilities than for low hazard
facilities.
Similarly, DOE uses a graded approach to implement safety oversight. More oversight rigor and
resources are applied to facilities with high hazards than to facilities with low hazards. In
addition, DOE uses a multi-tiered approach to safety oversight in which a high priority is placed
on DOE line management and independent oversight of high hazard facilities such as nuclear
facilities.
Figure 1 illustrates DOE’s multi-tiered approach to safety oversight as established in
DOE O 226.1B (contractor assurance system, DOE field element oversight, and program office
oversight). The DOE Office of Health, Safety and Security (HSS) performs independent
oversight of all three tiers and may perform independent reviews concurrently with DOE line
organizations’ conduct of oversight at all three tiers or may support DOE line management
oversight activities at the request of line management in some circumstances (when such
assistance does not degrade independent oversight’s independence and when the support is in
line with HSS independent oversight priorities and in the best interest of the DOE). The rest of
this section describes the roles and responsibilities of each organizational tier, provides
background about special requirements for safety oversight and related Federal training that
apply to nuclear facilities, and sets the stage for the guidance provided in Sections 3 and 4.
Section 6
4 DOE G 226.1-2
6-21-12
2.1 Contractor Assurance System
The contractor requirements document (CRD) in DOE O 226.1B requires contractors to establish
a contractor assurance system (CAS)2 to monitor site safety performance (Tier 1). The CRD in
DOE O 226.1B requires that the CAS describe assurance processes and address appropriate
processes and mechanisms, including:
• Flowing down the requirements of the CRD to subcontractors to ensure subcontractors’
commitment to compliance with facility safety requirements,
• Monitoring and evaluating safety performance,
• Assigning management responsibilities and accountabilities,
• Compiling and analyzing results of assurance processes,
• Validating the effectiveness of assurance system processes by using third-party audits, peer
reviews, independent assessments, etc.,
• Identifying, performing, and documenting periodic self-assessment and feedback and
improvement activities,
• Ensuring timely communication to the Contracting Officer, including electronic access to
assurance-related information,
• Providing evidence to assure DOE and contractor management that work is being performed
safely, that risks are being identified and managed, and that control systems are effective, and
• Performing trending and analysis to support appropriate, proactive decisions.
2 Most DOE CASs are developed and implemented by DOE contractors. However, DOE has a small number of
nuclear facilities/activities that are operated by DOE personnel. DOE O 226.1B requires DOE Headquarters
program offices to develop and implement oversight processes for these facilities consistent with requirements for
CASs. For simplicity, the term “CAS,” as used in this Guide, includes CASs for nuclear facilities operated by DOE
personnel.
Figure 1. DOE’s Multi-Tiered Approach to Safety Oversight
DOE Program Office
Oversight-
Tier 3
DOE Field Element Oversight-
Tier 2
Contractor Assurance System-Tier 1
Other Site Activities Nuclear Facilities
HSS
Independent
Oversight
DOE G 226.1-2 5
6-21-12
The results of CAS activities are an important source of information for DOE line management’s
oversight activities. DOE line management tailors its oversight program based on the
effectiveness of CASs. However, regardless of the strength of a CAS, DOE directives require
DOE line management to perform various oversight functions to validate the effectiveness of
safety controls at nuclear facilities.
2.2 DOE Line Management Oversight
DOE O 226.1B requires that DOE line management:
• Maintain sufficient technical capability and knowledge of site and contractor activities to
make informed decisions about hazards, risks, and resource allocation; provide direction to
contractors; and evaluate contractor performance;
• Evaluate contractor and DOE programs and management systems, including site assurance
systems, for effectiveness of performance (including compliance with requirements) using
written plans and schedules for planned assessments;
• Conduct Headquarters oversight processes that are focused on the DOE field element
activities to determine the effectiveness of line management oversight of the contractors;
• Establish an issues management process that is capable of categorizing findings based on risk
and priority, ensuring that relevant findings are effectively communicated to the contractors,
and ensuring that problems are evaluated and corrected on a timely basis; and
Section 7
• Establish and communicate performance expectations to contractors through formal contract
mechanisms and establish effective processes for communicating oversight results and other
issues in a timely manner.
Figure 2 shows a generic representation of a DOE line management oversight program. One of
the keys to an effective oversight program is a systematic process for continually evaluating
information from many sources. This information is used to design a comprehensive oversight
program that includes a baseline oversight program (which can be defined as the minimum level
of oversight to be conducted regardless of the contractor’s performance), as well as oversight in
response to the results of processes for determining which areas warrant supplemental oversight
commensurate with the hazards of the nuclear facility, i.e., informed oversight.
DOE line management oversight includes both field element (Tier 2) and program office
oversight (Tier 3) processes that perform complementary functions and are coordinated to
eliminate unnecessary duplication. However, an appropriate degree of overlap is appropriate for
oversight of high hazard nuclear facilities. Key attributes of effective DOE line management
oversight that apply to both DOE field elements and program offices include:
• Requirements Based. The baseline set of oversight activities required by DOE directives are
rigorously conducted, and the results are relatable to the requirements.
• Efficient in Application. To the extent possible, oversight processes appropriately utilize
contractor assurance information to adjust the rigor and frequency of oversight in a particular
area. Similarly, Headquarters (Tier 3) and HSS independent oversight processes
appropriately utilize DOE line management oversight information to adjust the rigor and
frequency of oversight of DOE field elements.
6 DOE G 226.1-2
6-21-12
Figure 2. Overview of DOE Federal Line Management Oversight
2.2.1 DOE Field Element Safety Oversight
The major safety oversight functions performed by DOE field elements (Tier 2) include two
broad categories: (1) DOE field element oversight of DOE contractor activities, and (2) DOE
field element self-assessments of their own activities and functions. Field elements have the most
experience with the activities and hazards at their sites and are in the best position to evaluate
site status and contractor safety performance. Thus, field elements have primary responsibility
for establishing and implementing DOE line management oversight of contractor performance.
Routine DOE field element oversight of DOE contractor activities includes:
• Maintaining safety-related operational awareness,
• Identifying and addressing safety vulnerabilities and issues,
• Confirming contractors’ implementation of safety-related contract provisions that are based
on safety-related regulations and directives,
• Reviewing event reports,
• Observing work,
• Attending meetings (e.g., plan-of-the-day/plan-of-the-week),
• Reviewing Facility Representative and safety system oversight (SSO) assessments, and
• Reviewing subject matter expert reports.
In addition to the above day-to-day oversight activities, field elements perform a wide variety of
safety-related activities, including:
DOE G 226.1-2 7
6-21-12
• Establishing and approving the list of safety requirements in contracts,
• Conducting independent reviews of safety basis documents and providing approval
Section 8
recommendations to the Approval Authority,
• Conducting independent reviews of nuclear safety in new or modified operations,
• Reviewing changes in nuclear safety system designs resulting from a positive unreviewed
safety question (USQ) determination,
• Reviewing the hazard categorization determinations,
• Participating in readiness reviews, and
• Reviewing, and in some cases approving, safety management programs (SMPs).
Field elements may arrange for additional technical assistance or reviews from outside
organizations. Such organizations include their DOE program office’s safety organization; the
applicable DOE CTAs and their technical support organizations, such as the CNS/CDNS office;
HSS; or other field elements.
2.2.2 DOE Program Office Safety Oversight
DOE program offices conduct oversight to ensure that the oversight systems for their nuclear
facilities are working effectively. Program office oversight processes focus on their field
elements, including reviewing contractor activities to the extent necessary to evaluate the
effectiveness of their field element’s oversight of its contractors. DOE program office safety
oversight (Tier 3) functions also include:
• Ensuring that systemic safety issues affecting the DOE complex are identified and addressed,
• Evaluating areas where the field element has not looked or where performance or
vulnerability indicates the need for oversight beyond the scope of that conducted by the field
element, and
• Performing self-assessments of their own activities concerning the safety of their nuclear
facilities.
DOE O 226.1B requires program offices to establish their oversight activities with a planning
process. That process includes scheduled assessments and may also include “for cause” reviews
and reviews requested by the field element.
2.2.3 Central Technical Authorities and Chief of Nuclear Safety/Chief of Defense Nuclear
Safety
DOE CTAs in NNSA and the Under Secretaries for Energy and Science provide centralized
technical expertise and maintain operational awareness to ensure adequate implementation of
nuclear safety policy and requirements. The CTAs are supported by the CNS/CDNS technical
support organizations. The CNS/CDNS perform oversight activities at DOE organizations and
nuclear facilities in support of their respective program offices and CTAs.
8 DOE G 226.1-2
6-21-12
2.2.4 Federal Training and Qualifications
DOE O 226.1B requires DOE organizations to maintain sufficient technical capability and
knowledge of site and contractor activities to make informed decisions about hazards, risks, and
resource allocation; provide direction to contractors; and evaluate contractor performance.
Additional training and qualification requirements apply to defense nuclear facilities. These
include the regulations set out in DOE O 426.1, Chg. 1, Federal Technical Capability, which
applies only to Federal personnel. This directive provides specific requirements for qualification
programs for Facility Representatives, SSO personnel, and senior technical safety managers
(STSMs). DOE O 360.1C, Federal Employee Training, establishes requirements for training
Federal personnel.
2.3 Independent Oversight and Other DOE and External Reviews
Section 9
In accordance with DOE O 227.1, Independent Oversight Program, the DOE independent
oversight program for safety and security (including cyber security; emergency management;
safeguards and security; and environment, safety, and health) programs is implemented by the
HSS Office of Enforcement and Oversight. This program provides DOE and contractor
managers, Congress, and other stakeholders with an independent evaluation of the adequacy of
DOE policy and requirements and the effectiveness of DOE and contractor performance in
safety, security, and other critical functions. As shown in Figure 1, the HSS independent
oversight program is unique in that it examines site programs and the three tiers of line
management oversight to provide management with independent perspectives on the overall
effectiveness of DOE policies, programs, and performance in safety and security.
The HSS independent oversight program is independent of DOE line management. However,
HSS coordinates with DOE line management to make optimum use of resources for conducting
oversight. HSS sometimes conducts independent reviews concurrent with DOE line management
oversight activities and sometimes performs independent reviews at the request of DOE line
management. While HSS coordinates with DOE line management, HSS recognizes that nuclear
facilities contain unique hazards that warrant significant independent oversight.
Other internal and external organizations, including the DOE Inspector General (IG), may
perform reviews or investigations that provide perspectives on DOE’s oversight of nuclear
facility safety. DOE line management should consider the results of those reviews as input to
their line management oversight programs.
2.4 Overview of General and Detailed Guidance for Federal Line Management Safety
Oversight of Nuclear Facilities
This Guide is designed to identify the aspects of DOE O 226.1B for which guidance for safety
oversight of nuclear facilities would be most useful. These aspects are grouped into three
categories: oversight programs, oversight processes, and detailed guidance for evaluations.
Oversight Programs. The oversight policy and order recognize that essential DOE line
management oversight programs must be specific for each nuclear facility. Therefore, the order
DOE G 226.1-2 9 (and 10)
6-21-12
establishes broad performance requirements, rather than detailed procedural requirements, for
oversight programs for facilities. The following topics provide guidance that is useful to DOE
line management in establishing oversight programs for nuclear facilities:
• Scope of DOE Line Oversight Program for Safety Oversight of Nuclear Facilities (Section
3.1)
• Tailoring to Facilities, Activities, and Hazards (Section 3.2)
• Designing and Implementing DOE Field Element Oversight Programs (Section 3.3)
• Designing and Implementing DOE Program Office Oversight Programs (Section 3.4).
Oversight Processes. The oversight order identifies requirements for oversight processes. The
following topics provide guidance for DOE field elements’ oversight processes:
• Evaluation Processes (Section 3.5)
• Issues/Corrective Action Management Program (Section 3.6)
• Performance Measures and Communications (Section 3.7).
Section 10
Detailed Guidance for Evaluations. Two types of detailed guidance for evaluating safety
performance are provided to complement the information on programs and processes. The first
includes detailed guidance for DOE line management assessments of various programs and cross
cutting functions that support safe operation of nuclear facilities. This Guide groups these
functions and programs into four core performance areas (safety system operability, TSR
implementation, SMPs, and safety management systems) and two cross cutting performance
areas (formality of operations and safety culture). The second type of detailed guidance provides
information about criteria review and approach documents (CRADs), which DOE line
management can use to evaluate various elements of a nuclear facility safety program. Guidance
in these two areas is provided as follows:
• Detailed Guidance for DOE Line Management Oversight of Core and Cross Cutting
Performance Areas for Nuclear Facilities (Section 4.1)
• Application of Criteria Review and Approach Documents (Section 4.2).
DOE G 226.1-2 11
6-21-12
3. GUIDANCE FOR FEDERAL LINE MANAGEMENT
SAFETY OVERSIGHT OF NUCLEAR FACILITIES
3.1 Scope of DOE Line Management Program for Safety Oversight of Nuclear Facilities
One of the first and most critical steps in establishing and implementing an effective safety
oversight program for nuclear facilities is for DOE line management to systematically identify
the applicable requirements and elements of nuclear safety programs at each nuclear facility
under its purview. DOE line management should also understand all of the components of
these programs and their interrelationships.
DOE nuclear safety requirements are the collection of the Department’s regulations and
directives that establish requirements for both DOE and its contractors. Title 10 CFR Part 830,
Nuclear Safety Management, is the primary rule for nuclear facilities. Specifically, Subpart B of
10 CFR 830 requires contractors and operators of hazard category 1, 2, and 3 nuclear facilities to
develop and maintain a safety basis and to perform work in accordance with that safety basis,
including the associated TSRs and the USQ process. Similarly, Subpart A provides contractor
requirements for QA activities that affect nuclear safety at DOE nuclear facilities. DOE
directives establish various requirements applicable to nuclear facilities, including requirements
for nuclear facility design, construction, verification of readiness to operate, QA, maintenance,
systems engineering, training, SMPs, and safety management systems. In some cases, DOE
directives invoke industry consensus standards.
A major role of DOE line management oversight is to monitor and ensure compliance with those
safety requirements at nuclear facilities. An important method that DOE line management can
use to monitor compliance with nuclear safety requirements is to evaluate the adequacy of the
following types of activities:
• Designing and constructing compliant facilities,
• Using physical barriers (e.g., containers, gloveboxes, filtered ventilation systems, facility
structures) to safely contain hazardous radioactive materials and prevent uncontrolled and
unmonitored personnel exposure to radiation,
• Preparing and using safety basis documentation that requires multiple layers of defense (e.g.,
engineered and administrative controls) to prevent and mitigate the release of hazardous
radioactive materials,
Section 11
• Operating the facilities according to approved specifications and abiding by strict controls on
changing the design,
• Designing and implementing systems and programs to minimize initiating events that could
lead to an accident,
• Ensuring that safety systems are maintained, operable, and sufficient to perform their
intended safety function as delineated in the safety basis documents, and
• Preparing for emergencies, including developing emergency response programs and plans to
shelter or evacuate people in the event of an accident.
12 DOE G 226.1-2
6-21-12
In addition, the regulations and directives require contractors to establish and maintain various
safety management programs and cross cutting functions that support safe operation of nuclear
facilities. These include:
• An integrated safety management (ISM) program to ensure that safety is an integral part of
each work activity;
• A QA program to ensure reliable performance of systems;
• A USQ process to evaluate proposed changes and as-found discrepant conditions;
• A configuration management program to prevent unauthorized changes to designs,
documentation, and the facility safety program;
• A nuclear maintenance program that maintains the engineered controls that are important to
safety;
• A planning and work control process that supports safe work activities;
• A conduct-of-operations program that fosters formality of operations;
• A radiological control program that maintains exposure to radiation as low as reasonably
achievable;
• A comprehensive fire protection program to minimize the potential for, and consequences of,
a fire or fire-related event;
• A criticality safety program to ensure that activities with the potential for criticality hazards
provide adequate protection to the public, workers, and the environment;
• A sitewide training program to ensure that personnel performing operations and maintenance
affecting nuclear facilities are trained for those duties;
• A program for verifying the readiness for startup and restart of operations; and
• A sitewide emergency management program.
Figure 3 illustrates the framework for nuclear facility oversight, which includes three
components (shown in pink) – regulations and directives, core performance areas, and cross
cutting performance areas – and their interdependence in ensuring nuclear facility safety. The
figure also shows the elements of each component (shown in blue). A more detailed description
of rules and directives applicable to nuclear facilities is provided in Appendix B (which is
available at http://www.hss.energy.gov/healthsafety/flmo/appendices/index.html). Additional
guidance on evaluating the core and cross cutting performance areas is provided in Section 4.1.
http://www.hss.energy.gov/healthsafety/flmo/appendices/index.html
DOE G 226.1-2 13
6-21-12
Figure 3. Framework for Nuclear Facility Oversight
Notes:
* A more detailed description of regulations and directives applicable to nuclear facilities is provided in
Appendix B.
**Emergency preparedness is included in Figure 3 for completeness. However, since comprehensive guidance
for oversight of emergency management programs is provided in DOE O 151.1C, Comprehensive Emergency
Management System, and its guides, the emergency preparedness core performance area is not described
further in this Guide.
Safety Management
Program
Effectiveness
DOE Line Oversight
Directives
Technical Safety
Requirement
Implementation
Safety System
Operability
Section 12
Cross Cutting Performance Areas
Emergency Preparedness**
Safety Management System Effectiveness
10 CFR 830 and Related
Directives
DOE Nuclear Facility
Directives
Regulations and Directives*
Core Performance Areas
Issue Identification
and Resolution
Formality of
Operations Safety Culture
14 DOE G 226.1-2
6-21-12
The following is a list and description of the nuclear facility core and cross cutting
performance areas shown in Figure 3 that are referred to in the remaining sections of this
Guide:
Core Performance Areas
• Safety System Operability. This performance area includes verifying the operability of
safety class and safety significant structures, systems, and components (SSCs) identified
in the DSA, including design features, on a recurring basis.
• TSR Implementation. This performance area includes evaluating the implementation
of TSR controls – surveillance requirements, design features, specific administrative
controls (SACs), and administrative controls (ACs) – on a recurring basis.
• SMP Implementation. This performance area includes evaluating the overall
effectiveness of the SMPs identified in the DSA, over a baseline period of time.
• Safety Management System Implementation. This performance area includes
evaluating the effectiveness of ISM primarily at the activity level, the effectiveness of
the CAS, and the effectiveness of the QA program over a baseline period of time.
• Emergency Preparedness. Comprehensive guidance for oversight of emergency
management programs is provided in DOE O 151.1C, Comprehensive Emergency
Management System, and its guides. Particularly relevant to oversight of emergency
preparedness is DOE G 151.1-3, Programmatic Elements, Section 4. Readiness
Assurance. The emergency preparedness core performance area is not described further
in this Guide.
Cross Cutting Performance Areas
• Formality of Operations Programs. This performance area includes evaluating the
effectiveness of the implementation of conduct of operations (DOE O 422.1), conduct of
maintenance (DOE O 433.1B), conduct of engineering (DOE O 420.1B, Chg. 1), and
conduct of training programs (DOE O 426.1, Chg. 1) over a baseline period of time.
• Safety Culture. This performance area includes developing, monitoring, and
periodically evaluating the nuclear facility safety culture.
• Issue Identification and Resolution. This performance area includes evaluating the
significance determination process and, for those issues with high significance, ensuring
that a rigorous evaluation and resolution process is effectively implemented.
DOE G 226.1-2 15
6-21-12
3.2 Tailoring to Facilities, Activities, and Hazards
DOE O 226.1B, Section 4.b(5), requires DOE line management to tailor oversight programs
according to the effectiveness of CASs, the hazards at the site/activity, and the degree of risk.
The order also requires DOE line management to give additional oversight emphasis to high
consequence activities, such as nuclear facilities.
To meet the tailoring provision for oversight of nuclear facilities, DOE line management
should systematically evaluate each nuclear facility under its purview and the associated
requirements and programs to identify site-specific conditions that warrant increased oversight
attention, as well as factors that could indicate that fewer oversight activities and resources
would be needed, to provide assurance of adequate protection.
Section 13
The information in this subsection identifies the site-specific conditions that DOE line
management should consider in designing oversight processes, establishing oversight
priorities, and allocating oversight resources.
Types of Nuclear Facilities/Activities. DOE has various types of nuclear facilities, including
nuclear reactors, stockpile production/maintenance facilities, storage facilities, research
laboratories, transportation and packaging facilities, and analytical laboratories. DOE nuclear
facilities are also in different stages of their lifecycle (e.g., construction, pre-operational,
operational, inactive, and decommissioning). Furthermore, activities within a specific nuclear
facility change from time to time (e.g., a reactor may be at a high power level at some times
and in a shutdown mode at other times), and certain activities (e.g., moving items in a storage
facility) may involve a unique set of hazards.
DOE organizations should systematically evaluate their nuclear facilities and tailor their
oversight activities to the hazards for each facility. Such evaluations should be reviewed and
updated periodically since facilities and conditions change. DOE organizations should also
systematically identify the activities that are performed at each nuclear facility. The DSA and
TSRs for each nuclear facility provide much of the information needed to help DOE tailor
oversight activities, including detailed analyses of the authorized activities and the associated
safety controls, as well as information about potential accidents and events and their
consequences. DOE organizations should use this information in the design of their oversight
activities, including establishment of a baseline oversight program and identification of
conditions that warrant increased or special oversight emphasis.
Examples of the conditions that might warrant increased or special oversight attention include:
• Research laboratories frequently change experiments and perform activities with new
equipment, materials, or procedures. Oversight activities in the early phases of such
activities could focus on verifying that the activities remain within the provisions of the
safety bases and that any new conditions are properly evaluated.
• During pre-operational, construction, or major modification phases, conditions at a nuclear
facility change rapidly, and certain conditions can be observed best at certain points in the
construction effort. For example, verification of seals, welds, concrete quality, and the
16 DOE G 226.1-2
6-21-12
associated QA provisions might be readily observable at certain phases of construction or
modification. DOE organizations should consider scheduling oversight activities of
contractor processes and QA measures at optimal times to verify conformance with
requirements and identify deficiencies at an early stage for appropriate corrective actions.
In addition to promoting safety, such timely oversight can promote success of the mission
by identifying deficiencies for corrective action before they result in a need for extensive
rework.
• Certain facility activities are particularly important during particular phases of the lifecycle
of the facility or a particular mission within the facility. For example, while always
important, procurement processes are often more extensively used during construction or
major modifications/upgrades. DOE oversight can effectively use its resources by targeting
processes, such as procurement, for increased oversight attention at appropriate times in
the lifecycle of the facility or a mission activity.
Section 14
• DSAs typically identify various accident scenarios that could result in the highest
consequences. Often, such accidents could occur under certain conditions (e.g., during a
fuel move, while a reactor is at high power, or when a vault is open). DOE oversight
processes should consider such information to focus ongoing oversight activities (e.g.,
Facility Representative programs) on these conditions.
• Major safety-related work activities performed by subcontractors may warrant extra
scrutiny. Subcontractors could be subject to organizational, contractual, or financial
incentives or penalties that result in pressure to meet production/mission objectives,
possibly resulting in less priority for safety objectives.
The above list is intended to illustrate the many factors that DOE organizations should
consider in selecting oversight activities. Systematic analysis involving subject matter experts
from various disciplines should be performed to optimize oversight efforts.
Status and Effectiveness of CASs. DOE should evaluate CASs as one factor in setting DOE
oversight priorities. For example, DOE line oversight might focus on problem areas identified
by the contractor. DOE also might analyze the results of CAS efforts, determine that the
contractor is not performing enough reviews of certain areas, and target those areas for
increased attention. DOE organizations are required by regulations (10 CFR 830) and certain
directives (e.g., requirements that apply to Facility Representative and SSO programs) to
perform a minimum set of baseline oversight activities even if the CAS is determined to be
effective. In addition, the continued effectiveness of the CAS should be routinely monitored.
Budget limitations, organizational changes, and shifting priorities are among the many factors
that may impact the continued effectiveness of a CAS. DOE line management should remain
cognizant of such influences and monitor the continued effectiveness of CASs.
Other Factors Considered in Tailoring. DOE line management should be alert to factors in
addition to changes in facility conditions that might affect contractor implementation of safety
requirements. Such factors could include new contractors, contractor reorganizations, changes
in mission scope and workforce levels, significant reassignment of contractor safety
responsibilities, major revisions to safety programs (e.g., rollout of changes to ISM or work
control process), and significant changes in funding levels for safety activities. These changing
conditions could result in changes in how work is performed (e.g., by personnel with less
DOE G 226.1-2 17
6-21-12
experience), in different management attitudes (possibly less attention to safety), and in
different interfaces between contractor organizations (possibly resulting in gaps in recognized
safety responsibilities).
3.3 Designing and Implementing DOE Field Element Oversight Programs
DOE field elements are most familiar with site activities and hazards and perform most of the
DOE oversight activities in all areas, including oversight of nuclear facilities. DOE field
elements use a variety of mechanisms to perform oversight of nuclear facilities, including a
wide range of operational awareness activities (e.g., review of event reports, attendance at
meetings, inspection of field conditions, and observation of work), an SSO program, a Facility
Representative program, a documented oversight plan containing various assessments
(baseline, supplemental, reactive) and assessment techniques (field element assessments or
observing contractor assessments), issues management processes, and investigations of events
and accidents.
Section 15
While most of the guidance in this Guide is relevant to DOE line management, this section
(3.3) applies specifically to the aspects of oversight that relate primarily to DOE field elements
in designing and implementing their oversight program. This subsection includes:
• Field Element Oversight Objectives for Nuclear Facilities (Section 3.3.1),
• Field Element Mechanisms for Oversight of Nuclear Facilities (Section 3.3.2),
• Field Element Nuclear Facility Oversight Plan (Section 3.3.3), and
• Integrated Oversight Plan (Section 3.3.4).
3.3.1 Field Element Oversight Objectives for Nuclear Facilities
Field element line oversight programs for nuclear facilities involve two primary objectives. The
first is to evaluate the adequacy of the contractor’s oversight and assurance activities in each of
the core performance areas and cross cutting performance areas. This objective is accomplished
through assessments of the CAS and operational awareness activities, such as observing
contractor response to issues, inspecting facilities, observing contractor performance of work,
observing contractor oversight activities, and evaluating contractor performance indicator data.
The second objective is to independently evaluate the contractor’s performance in each of the
nuclear facility core performance areas and cross cutting performance areas. This evaluation is
primarily accomplished by performing a set of assessments using approved written plans that
include CRADs. A set of CRADs is available in Appendix C as a starting point for developing
CRADs that are tailored to the particular facility or functional area under consideration.
The set of assessments should include two components: (1) the required field element
assessments (typically referred to as baseline or required assessments) identified in DOE rules
and directives and site- or program-specific assessment requirements; and (2) any supplemental
assessments identified by field element managers to significantly reduce uncertainty about the
likelihood of potential adverse consequences that would have the greatest impact on safe, secure,
and efficient achievement of the DOE mission. The types of information that field element
18 DOE G 226.1-2
6-21-12
managers should evaluate to identify an appropriate set of supplemental assessments include the
magnitude of the potential hazard, the adverse consequence of failures of safety systems or
functions, the current level of contractor performance reflected in performance measures and
indicators, the significance of previous performance issues, the maturity of the contractor’s CAS,
and the maturity of their own field element line oversight processes.
The field element typically develops an annual assessment plan that includes both the required
assessments and any identified supplemental assessments. The annual assessment plan is a key
component of the nuclear facility oversight plan described in Section 3.3.3 below.
Field element managers may use the results of these assessments to: (1) adjust the focus of
operational awareness activities; (2) adjust the frequency, depth, and scope of planned
assessments; and (3) identify the need for any additional assessments, including any “for cause”
assessments. In making such decisions, field element managers should also consider insights
from analysis of hazards, the effectiveness of the CAS, and other factors, as discussed in the
discussion of tailoring in Section 3.2.
Section 16
A more detailed description of the field element oversight activities for each of the two primary
objectives follows.
Field Element Oversight Objective 1. The first objective of field element oversight activities is
to evaluate the adequacy of the contractor’s assurance activities in each of the core and cross
cutting performance areas.
In order to provide specific guidance in this area, it is necessary to briefly describe DOE
expectations for the contractor’s nuclear facility assurance program. For each of the core and
cross cutting performance areas, the contractor develops performance objectives, measures, and
indicators, along with a set of management and independent assessments. The set of assessments
should include two components: (1) the recurring assessments explicitly required by regulations
and DOE directives (typically referred to as baseline or required assessments), and (2) any
supplemental assessments identified by the contractor to significantly reduce uncertainty about
the likelihood of the potential adverse consequences that would have the greatest impact on safe,
secure, and efficient achievement of the DOE mission. The types of information that contractor
managers should evaluate to identify an appropriate set of supplemental assessments include the
magnitude of the potential hazard, adverse consequences of failures of safety systems or
functions, the current level of performance reflected by performance measures and indicators, the
significance of previous performance issues, and the maturity of their CAS. Supplemental
assessments may also be derived from other commitments or internal requirements established
by contractor management and/or from DOE line management expectations identified in the
contract. The contractor then develops an annual assessment plan that includes both the required
assessments and any identified supplemental assessments.
For each of the core and cross cutting performance areas, the responsible field element oversight
lead evaluates the quality and effectiveness of CAS implementing processes and activities
through operational awareness, participation in contractor-led assessments (e.g., joint
assessments), observation of performance of contractor-led assessments (e.g., shadow
DOE G 226.1-2 19
6-21-12
assessments3), and comparison of the results of CAS activities and field element operational
awareness and formal assessments. (See Section 3.5.)
Field Element Oversight Objective 2. The second objective of field element oversight is to
independently evaluate the contractor’s performance in each of the nuclear facility core and cross
cutting performance areas. The field element should consider performance information provided
by the contractor when selecting the operational awareness activities and assessments that will be
used to evaluate contractor safety performance. The number of oversight activities may be
adjusted up or down based on the inherent or base risk of a particular area, the contractor’s
performance in that area, and the field element’s confidence in the CAS. The proportion of
oversight resources committed to assessments, operational awareness activities, and evaluation
of systems and programs using CAS data may also be adjusted, using similar criteria. However,
field element independent assessments of contractor performance should not be adjusted below
the baseline level without adequate justification and formal approval by the appropriate level of
line management. Section 4.1 provides specific guidance for developing an appropriate level of
baseline assessments for each of the core and cross cutting performance areas.
Section 17
3.3.2 Field Element Mechanisms for Oversight of Nuclear Facilities
As shown in Figure 2 (see Section 2.2), DOE field element oversight should incorporate the
following four mechanisms:
• Field element information collection and analysis program (including the sources of
information and analysis of performance),
• Field element oversight planning,
• Conduct of assessments, and
• Corrective action management.
The first two of these mechanisms are discussed here. The other two are discussed in Sections
3.5 and 3.6.
Field Element Information Collection and Analysis Program. DOE field elements should
develop and implement an information program with the following attributes:
• Field element oversight and oversight-related activities should generate performance-related
data and information;
• This data and information should come from many sources, including the CAS, operational
awareness activities, event reporting, worker feedback, issues management, lessons learned,
performance measures/indicators, the DOE operating experience program, accident
investigations, DOE IG findings, Defense Nuclear Facilities Safety Board (DNFSB) reports
and recommendations, and employee concerns investigations;
3 “Shadow assessments” refers to the practice of DOE line management personnel participating in or observing
contractor-led assessments, with the dual purpose of gathering information about the element being assessed and
evaluating the effectiveness of the contractor’s assessment processes and activities.
20 DOE G 226.1-2
6-21-12
• The program should collect, analyze, categorize, and organize historical and current
performance-related information;
• Regular reports should be provided to field element managers summarizing conclusions and
recommendations; and
• Where feasible and cost-effective, multiple information systems, including systems
maintained separately by DOE and contractors, should be consolidated or coordinated.
Field Element Oversight Planning. Field element oversight should be planned and performed
to understand the safety condition of nuclear facilities and to identify and ensure resolution of
identified deficiencies. Field element oversight includes baseline, supplemental, and reactive
evaluation processes, as discussed in Section 3.5.2.
3.3.3 Field Element Nuclear Facility Oversight Plan
A description of the operational awareness focus areas and specific assessments to be performed
by the field element in each of the nuclear facility core and cross cutting performance areas
should be documented in a nuclear facility oversight plan, integrated oversight plan, or master
assessment program. The plan should be updated, at least annually, and approved by the field
element manager. The plan should:
• Identify periodic field element-led assessments required by DOE directives or directed by the
DOE program office;
• Identify other needed assessments based on a documented analysis that includes evaluation
of the level of risk to safety and mission delivery, contractor performance, field element
oversight information, and CAS information; and
• Identify significant operational awareness activities.
Section 4.1, “Detailed Guidance for DOE Line Management Oversight of Core and Cross
Cutting Performance Areas for Nuclear Facilities,” provides specific attributes and guidance for
identifying operational awareness activities and assessment activities for each of the core and
cross cutting performance areas that should be included in a nuclear facility oversight plan.
Section 18
3.3.4 Integrated Oversight Plan
DOE field elements, in concert with program offices, should develop an integrated oversight
plan (IOP) that identifies planned assessments and other significant oversight activities by
various organizations (including program offices and field elements, as well as external
organizations to the extent known). Such a plan enables better coordination of assessments and
oversight activities and minimizes schedule conflicts. A nuclear facility oversight plan (briefly
described in the previous section) that includes specific field element oversight activities for each
nuclear facility at a site should be included or referenced in the IOP. The following are attributes
of an effective IOP:
• DOE IOPs should address:
The required baseline assessments conducted using oversight CRADs;
DOE G 226.1-2 21
6-21-12
Contractual/legal requirements;
Any supplemental assessments or other oversight activities that should be conducted
based on established criteria or conditions, such as:
- Significant changes in a system, program, facility, or activity (for example, change of
site/facility managing contractor, transfer of site/facility ownership from one program
office or field element to another, or permanent cessation of operations);
- Individual and systemic problem areas identified by DOE or contractor oversight
activities and determined by the analysis of information to warrant additional
oversight;
- Inadequate identification or implementation of corrective actions to address
significant or repetitive DOE- or contractor-identified safety issues that warrant
additional follow-up;
- Areas for which little information is documented; and
- Areas of special DOE management interest or priority.
• DOE IOPs should be formally documented, coordinated with the program office and CTAs
and respective technical support organization (e.g., CDNS), and approved for use by the
DOE field element;
• The field element should maintain the IOPs and manage the information;
• The IOP process should include input from craft employees, field safety specialists, Facility
Representatives, safety engineers, program managers, maintenance personnel, and others as
needed;
• The DOE IOP should be coordinated with the contractor’s oversight activities to identify
opportunities for more efficiency through collaboration;
• Changes to scheduled assessments (date change, deferral to next cycle, change in scope,
cancellation, etc.) should be expected in response to changing circumstances, but these
changes should be reviewed and approved by responsible DOE line management in
accordance with a defined change control process; and
• DOE IOPs should be updated and published annually.
The IOP is the opportunity for establishing an effectiveness interface between program offices
and field elements and should ensure that:
• The field element oversight program provides a balance between reviews of documentation
(e.g., plans, procedures, and records) and reviews of the adequacy of implementation through
performance tests and observation of actual work activities at the facilities. Oversight
program activities provide for a similar balance between evaluations of systems (such as the
DOE ISM system), programs (e.g., radiation protection), facility conditions, and
implementation of individual elements of those systems (e.g., specific work activities);
Section 19
• DOE line management oversight coordinates assessment activities with CAS activities to
promote efficient use of resources. DOE line management may conduct some assessments
jointly with contractors, but DOE directives also require DOE line management to maintain
an adequate baseline oversight program that includes sufficient DOE-led assessments of
contractor management systems and site programs;
22 DOE G 226.1-2
6-21-12
• DOE line management (primarily through field organizations) implements a baseline line
management oversight program that focuses resources on selected assessments, operational
awareness activities, performance measure monitoring, and assessment of assurance systems;
• For sites that need improvement in site programs, management systems, or assurance systems
(e.g., insufficient rigor or comprehensiveness in existing systems), DOE line management
should conduct more frequent assessments focusing on areas needing improvement;
• DOE oversight programs and CASs evaluate performance against requirements and
performance objectives from such sources as regulations, national standards, DOE directives,
DOE-approved plans and program documents (e.g., radiation protection program and QA
program, authorization basis documents), site-specific procedures/manuals, CRADs, other
contractually mandated requirements, and contractual performance objectives;
• Requirements and performance objectives are established and interpreted through approved
processes so that they are relevant to the site and mission, and continuous improvement
opportunities are identified and pursued; and
• DOE line management should verify that plans submitted by contractors clearly delineate
actions to be taken and describe programs that meet DOE requirements and expectations.
3.4 Designing and Implementing DOE Program Office Oversight Programs
DOE O 226.1B requires program offices to conduct oversight of nuclear facility safety to ensure
that all of the nuclear facility oversight systems are working effectively. Program office
oversight includes two components: program office oversight and CTA oversight functions.
3.4.1 Program Office Oversight
Program office oversight processes focus primarily on oversight of their subordinate field
elements. However, program offices and their support staff may conduct oversight of contractors
during reviews pursuant to oversight requirements in DOE rules and directives or program office
priorities, or they may provide support to field elements’ oversight activities and when the need
for a “for cause” review is identified.
Program office oversight should incorporate the following mechanisms and attributes:
• Program/field level information collection and analysis: DOE program office personnel
should develop a good understanding of the nuclear facilities within their area of
responsibility by regularly reviewing the results of field element oversight, contractual
expectations, operating experience information, external organization inputs (such as DNFSB
staff observations), and other relevant information. Analysis of this information helps
maintain awareness of conditions and trends in their nuclear facilities and helps determine
the effectiveness of field element oversight processes.
• Planning baseline oversight: Based on the information collected, program offices should
establish appropriate baseline oversight activities and schedules that focus primarily on field
elements but may also include contractor activities.
Section 20
• Conducting/participating in oversight activities: DOE program offices should assess or
participate in assessments led by field elements or contractors to determine independently the
adequacy of the scope and implementation of field element self-assessment activities,
DOE G 226.1-2 23
6-21-12
oversight activities, technical capabilities, and CASs. Program offices should have a formal
process for identifying, planning, and performing assessments that includes expectations for
using CRADs when performing assessments.
• Feedback and improvement: Program offices and CTA support organizations should
establish effective communications with their field elements and provide meaningful
feedback to improve field elements’ nuclear facility safety programs, processes, and
procedures. In addition, program offices should clearly identify the sources of information
used to monitor and analyze performance and should ensure that the information developed
is of appropriate quality and is useful for performing analyses and for decision-making.
Based on an evaluation of the various sources of information available from field element
oversight programs and CASs, program offices may identify the need to perform additional
oversight activities, which may include supplemental assessments of areas of increased
vulnerability and reactive assessments in response to significant events.
3.4.2 CTA Oversight Functions
Oversight of nuclear facility operations warrants additional and focused program office
oversight. Accordingly, DOE has established CTAs and their technical support organizations to
ensure that essential nuclear safety functions are appropriately established and implemented. For
high-consequence nuclear operations, the CTAs should maintain awareness of the content of
applicable DOE line oversight programs, plans, and processes, as well as the maturity and
effectiveness of the CASs, by monitoring and evaluating the oversight programs, performing
trend analyses, monitoring associated assessment reports, and participating in oversight
activities.
The CTAs and their technical support organization staffs also should conduct and participate in
various program office oversight review activities, as defined in the associated oversight
programs. Based on these activities, the CTA should communicate identified issues and trends to
line management, provide advice concerning technical solutions or options, and follow up to
ensure proper closure of issues and/or implementation of corrective actions. Each of the CTAs
and their technical support organizations should define their own approaches and strategies for
selecting, prioritizing, and performing oversight activities.
3.5 Evaluation Processes
DOE O 226.1B, Section 4.b(1), requires DOE organizations to evaluate performance based on
the results of: (1) operational awareness activities; (2) assessments of facilities, operations, and
programs; and (3) assessments of the CAS. This section provides guidance for these three
evaluation methods. DOE O 226.1B and DOE 414.1D also require DOE organizations to
evaluate the performance of their own organizations (i.e., self-assessments), and this section also
provides guidance for self-assessments.
24 DOE G 226.1-2
6-21-12
3.5.1 Operational Awareness Activities
Operational awareness refers to the activities performed by DOE line personnel to maintain
cognizance of overall facility or activity status, major changes planned, and overall safety
posture. Attributes of effective operational awareness include:
Section 21
• DOE line management rigorously reviews and critiques contractor processes and
performance in identifying, evaluating, and reporting events and safety issues that are
required to be reported by rules or directives to determine whether issues are properly
screened, evaluated, and reported;
• DOE line management evaluates and monitors contractor evaluations and corrective actions
for events and issues and assesses whether effective corrective actions have been identified
and implemented to address the issues and prevent recurrence of events;
• Operational awareness activities and results of Facility Representative and SSO activities are
documented either individually or in periodic (e.g., weekly or monthly) summaries; and
• Deficiencies in programs or performance identified during operational awareness activities
are communicated to the contractor for resolution through a structured issues management
process, which can be managed by the field element or the contractor.
Examples of these operational awareness activities include:
• Attending event critiques;
• Reviewing the contractor’s issue response and corrective action follow-up;
• Reviewing contractor performance indicator data;
• Reviewing assessment review plans and reports;
• Reviewing contractor analysis and trending performance reports;
• Attending the contractor’s issues management boards, plan-of-the-day meetings, and other
safety-related management meetings;
• Participating in contractor facility condition inspections and work activity observations;
• Participating in contractor management walk-around program activities; and
• Reviewing parent company and/or peer review reports.
Operational awareness can be enhanced through shadow assessments of contractor-led
assessment activities, which could include:
• Shadowing contractor-led assessments to assess the quality and rigor of assessments and the
area that is being assessed by the contractor;
• Shadowing parent company oversight activities; and
• Shadowing elements of contractor-led assurance system validations.
DOE G 226.1-2 25
6-21-12
3.5.2 Assessments of Facilities, Operations, and Programs
DOE G 414.1-1B provides detailed guidance on how to perform management and independent
assessments. This section provides guidance on how to select the type of assessments to be
performed that complement the guidance in DOE G 414.1-1B.
DOE line management should rely on a robust information collection and analysis program (see
Section 3.3.2) to identify the optimum level and balance of baseline oversight and supplemental
oversight to be performed, and should perform reactive oversight when circumstances warrant.
Baseline Oversight. Baseline oversight is defined as the minimum level of oversight to be
conducted, regardless of the contractor’s performance. Baseline oversight should ensure the
adequacy and effectiveness of contractor and field element performance with respect to safe
operation and adherence to DOE requirements and contract provisions. Baseline oversight should
make use of established CRADs (see Section 4.2) and should consider the following attributes:
• Baseline oversight should be planned, systematic, and scheduled as repetitive cyclic
oversight activities;
• Baseline oversight should be conducted in specified functional areas and at specified
frequencies, even when performance meets requirements;
• The oversight CRADs should be tailored to reflect the appropriate breadth, depth, and scope
with which baseline oversight needs to be conducted for a particular facility or functional
area; and
Section 22
• Baseline oversight should ensure compliance with requirements applicable to the field
element. Field element organizations should establish and implement oversight processes for
monitoring their internal operations and completing required activities, such as review and
approval of important process and procedure documents.
Supplemental Oversight. Supplemental oversight should be conducted in response to declining
performance and should focus on topics of safety significance, as supported by data from the
contractor’s and DOE’s assessment activities. As the need is identified, supplemental oversight
should be added to the integrated schedule during its periodic update. Supplemental oversight
should make use of established CRADs in conjunction with other, more specialized, in-depth
criteria developed on a site-by-site or program-by-program basis.
Reactive Oversight. Reactive oversight should be performed in response to a specific event,
condition, special request, or emerging safety performance issue resulting from analysis of
information. Examples of reactive safety oversight activities include follow-up on significant
employee concerns; response to incidents, accidents, or any unusual event impacting safety;
special follow-up on corrective actions not covered by the baseline or supplemental oversight
program; and technical assistance (in response to a particular event, condition, or request) by a
subject matter expert or group of subject matter experts.
Standardized written guidance (e.g., CRADs) for conducting reactive safety oversight is limited
and may warrant development of one-of-a-kind plans and procedures based on the specific issue
at hand. Consequently, and given the highly focused, technical nature and short response time for
26 DOE G 226.1-2
6-21-12
reactive oversight activities, reactive oversight should rely heavily on the competence and
expertise of the staff that performs the oversight.
3.5.3 Assessments of the Contractor Assurance System
Since the CAS is the baseline tier of oversight and provides the most comprehensive coverage, it
is critically important that the CAS describes comprehensive, detailed, and specific processes
and mechanisms that provide an adequate basis for assuring DOE of safe operations. Therefore,
DOE line management review of the CAS is a critical element of DOE field element oversight.
DOE field elements assess the effectiveness of the CAS and can increase the depth and breadth
of oversight activities relative to the results of the assessments. DOE should devote considerable
rigor and resources to: (1) reviewing the contractor CAS submittals, including updates; (2)
reevaluating the CAS submittal periodically or as needed to ensure that it remains adequate for
evolving site conditions; and (3) evaluating the effectiveness of the contractor CAS and
implementation of the CAS processes and mechanisms.
Attributes of effective oversight of a CAS include:
• DOE line management assesses the implementation and effectiveness of CASs for nuclear
facility safety and supporting sub-elements (e.g., criticality safety, conduct of operations) by
examining:
Assessment methods (e.g., whether sufficient emphasis is placed on observation of work
activities);
Whether the process used for selecting assessment topics is structured and appropriately
implemented (i.e., is the contractor selecting the right assessment subjects based on
appropriate analysis?);
Section 23
The frequency, breadth, and depth of self-assessments;
Line management involvement in self-assessments;
Evaluators’ technical expertise and qualifications;
The number and nature of findings identified;
The degree of rigor applied to self-assessment;
The application of the CAS by subcontractors and prime contractor oversight of
subcontractor safety programs and processes, including self-assessments and issues
management processes;
• DOE line management regularly assesses the adequacy and effectiveness of contractor issues
management and corrective action processes (e.g., categorization, analysis of causes and
extent of condition, and application of controls to prevent recurrence), lessons-learned
processes, and other feedback mechanisms (e.g., worker feedback). DOE line management
also evaluates contractor processes for communicating information, including safety
concerns and dissenting technical opinions, up the management chain. DOE line
management validates that contractor corrective actions have been implemented and are
effective in resolving deficiencies and preventing recurrence;
• DOE line management regularly assesses the contractor’s reporting processes and
performance to determine whether contractors meet reporting requirements for events and
DOE G 226.1-2 27
6-21-12
incidents relevant to nuclear facility safety and takes effective actions to prevent their
recurrence; and
• For sites where contractors report the results of performance measures to DOE (e.g., as part
of a contractual provision), DOE regularly assesses the effectiveness of processes for
collecting, evaluating, and reporting performance data to ascertain the accuracy,
completeness, and validity of the performance measures.
3.5.4 Self-Assessment
Program offices and field elements should have a structured, documented program for self-
assessment of DOE line management nuclear safety functions and oversight to ensure
compliance with applicable requirements and verify effective performance. DOE organizations
should perform self-assessments of programmatic and line management oversight processes and
activities (e.g., Facility Representative programs, SSO, issues management, technical
qualification programs, and training programs) to determine whether requirements and
management expectations are met.
The frequency of assessments of these functions should be commensurate with the hazards and
risks and should comply with applicable directives. Continuous improvement mechanisms (e.g.,
corrective action processes) should be in place to improve the effectiveness and efficiency of
DOE line management self-assessment programs.
3.6 Issues/Corrective Action Management Program
DOE line management should implement documented processes for ensuring that corrective
actions are appropriate, complete, and performed in accordance with requirements before issues4
identified by DOE assessments or reviews are closed. Issues should be analyzed both
individually and collectively to identify causes and prevent recurrences.
To avoid unnecessary duplication of effort, program offices may choose to utilize field element
issues management processes, and field elements may choose to utilize contractor issues
management processes, to track some findings. However, program offices and field elements
may need to use their own issues management systems for certain issues.
Section 24
Criteria should be established to categorize the significance of issues. The highest level of rigor
should be applied to issues categorized as high significance in the implementation of the overall
corrective action management process. Section 3.6.1 includes additional guidance for
determining the significance of issues.
Attributes of effective DOE line management processes for managing and tracking nuclear
safety-related issues and corrective actions at hazard category 1, 2, and 3 nuclear facilities
include:
4 The term “issues” in this discussion of corrective actions management includes deficiencies, findings, or other
types of assessment results that indicate performance that does not fully meet expectations.
28 DOE G 226.1-2
6-21-12
• Categorization of issues in a manner that supports prioritization of corrective actions
(described in Section 3.6.1);
• Processes for ensuring that issues are evaluated and corrected on a timely basis;
• Accurate communication of DOE-identified issues to the contractor;
• Effective processes for communicating line oversight issues within the DOE line
management organizations, and provisions for communicating and documenting
dissenting opinions;
• Accurate communication of expectations for an effective response (e.g., timeliness,
completion of corrective actions, suspension of activities, contractor investigations and/or
assessments) for significant and/or repeated issues;
• Provisions for independent technical reviews of significant issues;
• Corrective action plans (CAPs):
CAPs are a useful tool for implementing an issues management system;
CAPs should describe the analysis (causes and extent of condition); linkages between
issues, causes, and recurrence controls; and actions to be taken to manage the issues,
including timely milestones for corrective actions, verification of closure, and
validation of effectiveness as appropriate;
For external reviews or joint DOE/contractor assessments, DOE-identified oversight
issues and associated corrective actions should be coordinated and may be integrated
with contractor-identified issues and corrective actions to create a sitewide CAP;
As appropriate for each DOE-identified oversight issue, the organization responsible
for correcting the issue should develop a written plan to resolve it. The following
actions should be considered in the written plan:
o Investigate, to the extent necessary, to determine a complete understanding of the
issue, including whether the issue is isolated or represents a systemic program-
related or cross cutting issue;
o Identify apparent causes or root cause and associated causal factors for each issue;
o Develop corrective actions that are clear, concise, and executable; have a measure
of performance to demonstrate the outcome; can be verified and validated as
complete; and address the identified cause(s);
o Identify the organizations and managers responsible for carrying out each
corrective action;
o Ensure that timely completion dates are established for each corrective action;
o Explain how corrective actions will be tracked to closure; and
o Identify mechanisms to verify and validate closure of issues;
• Document the closure of issues:
Closure packages should be generated that specify what measures were completed to
resolve the issue;
The closure package should include objective evidence that the actions taken to
resolve the issue have been completed. The person or persons validating
Section 25
DOE G 226.1-2 29
6-21-12
implementation should consider the need to perform field inspections to validate that
corrective actions were completed as specified;
All documentation should be included with the final documentation package that
closes the issue; and
Closure of issues should not be approved if corrective actions are found to be
inadequate in any way (e.g., the causal analysis was insufficient, the proposed actions
do not address identified causes or after implementation did not prevent recurrence of
the issue), and the issue of inadequate corrective action should be identified as a new
issue;
• Corrective actions review and verification:
Corrective actions for significant issues should be reviewed and approved by the
appropriate line manager, who should be designated based on the significance of the
issue, before they are implemented;
The review and approval process should involve verifying the completeness of the
proposed actions to gauge whether their implementation will likely correct the
identified issues and prevent their recurrence; and
Verification should typically be performed by some combination of individuals
representing the applicable DOE program secretarial officer (PSO), head of the field
organization, and the organization that identified the deficiency; and
• Validation (effectiveness review):
Corrective actions taken to resolve significant issues should be validated. Validation
involves making sure that corrective actions are completed as planned, and that the
actions resolved the issue and will prevent its recurrence;
Validation should be performed by the appropriate organization (which should be
designated in the CAP, considering such factors as the significance of the issue,
knowledge of the corrective action, and appropriate degree of independence) and
should be confirmed by a representative from the applicable field element; and
Depending on the significance of the issue, the person or persons validating CAP
implementation may choose to sample the completed actions. The sample size
depends on the number of corrective actions and the significance of the issue.
3.6.1 Issue Identification and Resolution
The objective of oversight in this area is to evaluate the effectiveness of the contractor’s issues
management program, with emphasis on the issue significance determination process, and, for
issues with high significance, to ensure that a rigorous evaluation and resolution process is
effectively implemented. Methods for evaluation include operational awareness and reviews and
assessments by the field element including the responsible STSM, with input from Facility
Representatives, SSO personnel, and functional area leads.
An essential element of issue identification and resolution is an issues management process that
is capable of accurately categorizing findings in a manner that supports prioritization of
30 DOE G 226.1-2
6-21-12
corrective actions; ensuring that DOE identified findings are effectively communicated to the
contractors; and ensuring that problems are evaluated and corrected on a timely basis.
DOE O 226.1B, Section 4.b(4), requires that the following actions be taken for issues
categorized as high significance findings:
• A thorough analysis of the underlying causal factors is completed;
• Corrective actions that will address the cause(s) of the findings and prevent recurrence are
identified and implemented;
• After completion of a corrective action or a set of corrective actions, an effectiveness review
Section 26
is conducted, using trained and qualified personnel, to verify that the corrective action/CAP
has been effectively implemented to prevent recurrence;
• The causal analysis process and results are documented, and plans and schedules for the
corrective actions and effectiveness reviews are tracked to completion in a readily accessible
system; and
• When findings and/or corrective actions apply to more than one secretarial office, a lead
office is appointed by mutual agreement between the affected secretarial officers.
The field element should identify site-specific criteria for categorizing a finding or issue as a
high significance finding, which is subject to all the elements of a rigorous corrective action
management process. The following definitions and guidance are excerpted from the Nuclear
Quality Assurance Standard, NQA-1, 2008, Quality Assurance Requirements for Nuclear
Facility Operations, to assist with developing issue significance determination criteria.
NQA-1, Part 1, Introduction, Definition section, defines Conditions Adverse to Quality as “An
all inclusive term used in reference to any of the following: Failures, malfunctions, deficiencies,
defective items, and non conformances. Significant Conditions Adverse to Quality is one that, if
uncorrected, could have a serious effect on safety or operability.” In the context of oversight, a
condition adverse the quality is synonymous with a finding or issue, and a significant condition
adverse to quality is synonymous with a high significance finding.
Additionally, NQA-1, Appendix 16A-1, Non Mandatory Guidance on Corrective Action,
includes guidance for classifying conditions adverse to quality. Section 302 of this appendix
states that criteria for classifying conditions adverse to quality (e.g., findings/issues) as to
significance should be established and, as a minimum, should consider the following aspects:
• Impact on health and safety of the public or environment;
• Impact on reliability, availability, or maintainability of the equipment or facility;
• Importance in meeting regulatory requirements;
• Consequence of recurrence; and
• The extent to which the adverse condition (finding/issue) may apply to other items or
activities beyond the specific occurrence where it may have greater impact.
Examples of conditions that may be considered significant under certain conditions include:
• Repeated failure to implement a specific portion of a procedure;
• Adverse trend of near misses;
DOE G 226.1-2 31
6-21-12
• Adverse trend in formality of operations issues or findings;
• Widespread training weakness or operator knowledge gaps; and
• External findings from the DOE IG or HSS.
Additionally, DOE directives require rigorous corrective action management for significant
reportable events defined in the Occurrence Reporting and Processing System (see
DOE O 232.2, Occurrence Reporting and Processing of Operations Information) and for events
meeting criteria for accident investigations.
The field element should also consider developing an action matrix to outline the expected field
element response to identified issues and contractor demonstrated performance through CAS.
The action matrix should provide for a more predictable and consistent field element response to
deficiencies based on the associated safety impact. The action matrix should identify the
attributes that define a performance level of concern, the appropriate response to be taken by the
field element (e.g., level of management interaction, expected contractor action, change in
oversight above baseline), and the required documentation to be generated.
Section 27
3.6.2 Feedback
The feedback and improvement function closes the ISM system loop by connecting the practical
experiences of work to the planning for future work. Following are criteria for assessing
feedback mechanisms:
• Individuals or groups are responsible for identifying feedback information,
• Assessments and other data sources are established to identify feedback issues,
• Feedback requiring evaluation is clearly identified and described,
• Factual accuracy of feedback is assured,
• Line management evaluates feedback to identify safety issues and significance and to
determine causes, and
• The individual or group originally identifying the feedback issues is given an opportunity to
review the improvement plans and CAPs and provide comments for line disposition.
In addition, DOE G 450.4-1C, Integrated Safety Management System Guide, includes
Attachment 2, Section 5, Core Function 5, Provide Feedback and Continuous Improvement,
which assessors can use as background information when planning an assessment that addresses
feedback and improvement mechanisms. This section of DOE G 450.4-1C includes a detailed list
of attributes of effective feedback and continuous improvement mechanisms. DOE G 450.4-1C,
Attachment 9 Continuing Core Expectations, CCE-6, describes the characteristics of an effective
feedback and improvement process, and assessors can use it as background information when
planning an assessment that addresses feedback and improvement mechanisms. In addition, the
Energy Facility Contractors Group (EFCOG) Work Management Subgroup5 has developed
CRADs for performing assessments of activity level work planning and control programs and
CRADs for assessing the effectiveness of the implementation of these programs. Both sets of
5 DOE supports EFCOG activities, but EFCOG-developed guidance is not official DOE guidance.
32 DOE G 226.1-2
6-21-12
these CRADs are included by hyperlink in Appendix C and include a CRAD for assessing
feedback and improvement.
3.7 Performance Measures and Communications
DOE O 226.1B, Section 4.c. requires that DOE line management establish and communicate
performance expectations to contractors through formal contract mechanisms and that these
expectations (e.g., safety performance measures and commitments) must be established on an
annual basis, or as otherwise required or determined appropriate by the field element.
The following attributes should be considered in designing site-specific performance measures
and processes as applied to safety oversight of nuclear facilities:
• Particular attention should be devoted to ensuring that requirements and expectations are
established in contractual documents, including performance indicators, measures,
objectives, and criteria;
• Performance expectations should be established through the development and approval of
program documents that are required by regulations, directives, or contracts;
• DOE line management should verify that plans submitted by contractors clearly delineate
actions to be taken and describe programs that meet DOE requirements and expectations;
• DOE line management should work with contractors to ensure the development and
monitoring of performance indicators and measures that use objective data and evaluation
results that correspond to the requirements, core performance areas, cross cutting
performance areas, and program elements of an effective nuclear safety program, such as
those shown in Figure 3 (see Section 3.1) or a site-specific version that shows a similar set of
nuclear safety program elements;
Section 28
• Indicators and performance measures should be established and periodically reviewed by
DOE line management and communicated to contractors to provide tools for monitoring
performance in meeting expectations;
• DOE line management should devote attention to verifying the accuracy of the data and
information reported via performance measures. Verification could include sampling
performance measures to verify that operating experience was appropriately considered, data
was appropriately entered, reporting thresholds were clearly established and followed, and
action levels/thresholds produced acceptable results;
• Contractor-specific performance objectives and criteria and appropriate incentives should be
identified and specified in contract documents. Objectives and criteria should be challenging,
meaningful, measurable, and focused on improving performance in known areas of
weakness. DOE should encourage the use of both leading and lagging performance
indicators; and
• If the CAS is not adequate for nuclear facilities and nuclear safety programs, DOE line
management should provide direction to the contractor through such measures as contractual
provisions and direction to improve required program documents (e.g., ISM, CAS, QA
program documents).
DOE line management should have effective processes for communicating line oversight
results and other issues up the DOE line management chain, using a graded approach based on
DOE G 226.1-2 33 (and 34)
6-21-12
the hazards and risks. The results of DOE line management oversight activities should be
subject to a process that determines significance. The process should consider various factors
(e.g., the type of hazards, whether a deficiency was isolated or systemic, the extent of
condition, and past process or performance deficiencies in the same area). DOE line
management expectations for a response should be clearly communicated to contractors,
including expectations for a prompt and effective response (e.g., completion of corrective
actions, suspension of activities, contractor investigations/assessments) for significant and/or
repeated deficiencies.
The processes should provide a sufficient technical basis to allow senior DOE managers to
make informed decisions and should include provisions for communicating and documenting
dissenting opinions. Processes for resolving disputes about oversight findings and other
significant issues should also be implemented and should include provisions for independent
technical reviews of significant issues.
DOE G 226.1-2 35
6-21-12
4. DETAILED GUIDANCE FOR FEDERAL LINE MANAGEMENT
SAFETY OVERSIGHT OF NUCLEAR FACILITIES
4.1 Detailed Guidance for DOE Line Management Oversight of Core and Cross Cutting
Performance Areas for Nuclear Facilities
DOE line management oversight of nuclear facilities should include all components of the
nuclear facility oversight framework (see Figure 3 in Section 3.1) with a particular focus on
implementation of the safety basis, which includes the DSA and TSRs. Oversight of the nuclear
facility safety basis can be achieved through a rigorous and continuous evaluation of the core and
cross cutting performance areas discussed below. A field element nuclear safety oversight
program should include a comprehensive set of operational awareness activities and formal
assessments to determine the effectiveness of implementation of the CAS and to independently
evaluate the contractor’s performance in each of the nuclear facility core and cross cutting
performance areas.
Section 29
This section focuses on detailed guidance for establishing an appropriate baseline oversight
program to independently evaluate the contractor’s performance in each of the core and cross
cutting performance areas.
4.1.1 Operability of Safety Systems
Oversight of the operability of safety systems is primarily performed by DOE personnel assigned
to a particular system or multiple systems. The assigned Facility Representative for the nuclear
facility also conducts oversight to support the field element’s independent evaluation of safety
system operability. Depending on the complexity of the individual systems and the range and
number of systems, other field element functional leads (e.g., pressure safety, explosive safety,
electrical safety, nuclear criticality safety, fire protection) may also conduct oversight to support
the overall evaluation of operability. The information gained from the oversight conducted by all
these personnel is periodically analyzed, and the baseline oversight plan is adjusted if necessary.
The responsible field element nuclear facility oversight personnel should identify specific
criteria, such as an adverse trend or a potential vulnerability, that will lead to an increase in
oversight activities from the baseline, as well as action levels for providing technical direction to
the contractor.
Field element oversight of safety SSC operability should include the following attributes:
1. A comprehensive set of routine operational awareness activities is identified and
documented.
The following should be considered when developing the set of operational awareness
activities:
- Review system health reports;
- Participate in contractor system walkdowns;
- Observe system maintenance activities;
36 DOE G 226.1-2
6-21-12
- Observe surveillance activities;
- Observe operability determinations;
- Observe causal analysis and extent-of-condition reviews;
- Review corrective action status; and
- Observe resolution of as-found discrepant conditions.
2. A method for selecting the type, amount, and frequency of routine operational awareness
activities is established and documented.
Expectations for conducting operational awareness activities on a routine basis are
established, and the results of these activities are documented. The expectations should
include identifying activities that are conducted daily, weekly, monthly, quarterly, and
“as needed.” For example, daily activities could include attending plan-of-the-day
meetings and listening to daily operations calls, weekly activities could include reviewing
performance metrics and other sources of contractor data, monthly activities could be
observing system maintenance or surveillance activities, and quarterly activities could be
observing or conducting system walkdowns and shadowing contractor system assessment
activities. “As needed” activities could be observing event causal analysis, observing
operability determinations, observing safety system modifications, reviewing
configuration management activities, reviewing occurrence reports, and evaluating the
adequacy of system compensatory measures resulting from an as-found discrepant
condition.
Operational awareness activities should be broad enough and include a sufficient scope of
safety systems that a periodic analysis of oversight information, including information
from the CAS, can be used to:
- Identify the need for any additional assessments, beyond the baseline set of recurring
Section 30
safety system assessments;
- Identify the need for a “for cause” assessment;
- Adjust the focus of upcoming operational awareness activities;
- Provide feedback on contractor performance based on performance measures;
- Identify new performance targets; and
- Identify the need for any directed contractor actions.
3. The set of safety systems that require baseline recurring SSO assessments is identified
and documented.
Comprehensive assessments, using CRADs, should be conducted for all active and
passive safety systems and design features that are identified in the facility DSA and
TSRs. The set of safety systems requiring periodic assessments may be adjusted based on
the results of field element operational awareness and assessments and contractor
oversight information when there is a reasonable level of confidence in the outputs of the
CAS. However, safety class SSCs should always be included in the set of safety systems
requiring baseline recurring SSO assessments.
DOE G 226.1-2 37
6-21-12
4. A minimum periodicity for conducting SSO assessments for the scope of safety systems
identified as needing periodic reviews is established and documented.
For safety class SSCs, an assessment using a system-specific CRAD using the DSA and
the System Description Document as primary inputs should be conducted at least once
every three years, unless the safety SSC has been significantly modified or changed status
to affect the baseline during this period. For safety significant SSCs identified as needing
baseline recurring SSO assessments, an assessment using system-specific CRADs should
be conducted at least once every five years for SSCs that have not been modified or
changed status significantly. The scope and depth of assessment may be adjusted based
on the types and results of field element operational awareness activities and contractor
assurance activities. However, the scope of the assessments should include, as a
minimum, equipment configuration, material condition, operational reliability, and
maintenance of the safety system. Assessments of a representative sample of a similar
system in another nuclear facility may be used to meet the baseline periodicity if the
systems are of similar age and condition, design, and safety classification and are located
in similar environments that impact the systems in similar ways (e.g., in terms of water
quality and rates of corrosion of piping). For example, if three nuclear facilities each have
a safety class fire suppression system with the same design, operation, and maintenance
requirements, an assessment may be performed on the fire suppression system in only
one of the nuclear facilities every three years. However, if significant findings were
previously identified for a safety system in one such facility, a follow-up assessment may
be warranted on that particular system in addition to the baseline review of the same
system in another nuclear facility. Based on operational awareness activities and
evaluation of contractor assurance information, other systems important to safety may be
included on a one-time or periodic basis. However, such systems do not need assessments
at a recurring frequency.
5. Activities should be documented in oversight plans, with formal change control.
Section 31
The written oversight plan should identify and schedule key operational awareness
activities conducted on a monthly and quarterly basis, such as system walkdowns and
shadow assessments, and the safety system assessments for each annual assessment
cycle. The results of routine and scheduled operational awareness activities, formal
assessments, and the CAS should be comprehensive enough to allow the following to be
periodically conducted, typically on a quarterly and annual basis:
- Identify the need for any additional assessments, beyond the baseline set of recurring
safety system assessments, for the next quarterly or annual cycle;
- Identify the need for a “for cause” assessment;
- Adjust the focus of the upcoming quarter’s operational awareness activities;
- Provide feedback on contractor performance, based on performance measures;
- Identify new performance targets;
- Identify directed contractor actions; and
- Validate the contractor’s evaluation of continued system operability.
38 DOE G 226.1-2
6-21-12
4.1.2 Technical Safety Requirements Implementation
The proper implementation of safety basis controls is important for assuring the protection of
workers and the public. Current requirements promote the use of a graded approach that
emphasizes the controls that are most important for protecting the public and workers. These
controls are identified as TSRs and include safety limits, operating limits, surveillance
requirements, administrative (including specific administrative) and management controls, use
and application provisions, and design features.
DOE requirements for implementing safety basis controls set out in 10 CFR Part 830, Nuclear
Safety Management, and associated DOE directives focus on holding contractors responsible for
proper implementation of controls as part of their QA program. Contractors conduct
implementation verification reviews (IVRs) for new or revised safety basis controls and
periodically conduct IVRs to reconfirm proper implementation of existing safety basis controls in
accordance with DOE G 423.1-1A, Implementation Guide for Use in Developing Technical
Safety Requirements. Such reviews are geared toward meeting the requirements of 10 CFR Part
830 and several DOE orders, including DOE O 414.1D, Quality Assurance; DOE O 226.1B
Implementation of Department of Energy Oversight Policy; DOE O 420.1B, Facility Safety; and
DOE O 426.1, Chg. 1, Federal Technical Capability.
Independent validations of safety basis controls occur at several levels to various degrees. While
contractors perform independent assessments in accordance with 10 CFR 830 and
DOE O 414.1D, field elements provide for reviews by SSO, Facility Representative, and safety
basis personnel during operational readiness reviews, safety basis approvals, and independent
assessments. DOE Headquarters program offices, the CTAs (through their technical support
organizations), and HSS’s Office of Enforcement and Oversight also perform reviews of TSR
implementation. DOE line management may also choose to perform periodic re-verification of
existing safety basis controls similar to a contractor periodic IVR. Guidance for selecting the
scope, sample size, and periodicity for conducting field element IVRs of existing safety basis
controls is provided in this section.
Section 32
For startup of new (or restart of existing) facilities, activities, or operations, the primary means
for DOE's validation of the initial implementation of safety basis controls are readiness reviews.
The readiness review process includes requirements for evaluating whether the contractor’s
processes for ensuring that safety basis controls have been properly implemented are effective.
The readiness review process also includes requirements for DOE to determine whether the
safety basis controls have been appropriately implemented. This determination occurs prior to
the readiness review final report’s conclusion as to whether startup or restart of the nuclear
facility, activity, or operation can proceed safely. A good source of information for identifying
opportunities for DOE oversight of TSR implementation is the startup notification reports
required by DOE Order 425.1D, Verification of Readiness to Start Up or Restart Nuclear
Facilities. The resulting plan of action for the readiness activity, along with supporting
information, provides insight into changes in the safety basis that require implementation of new
safety basis controls, or changes to existing safety basis controls.
DOE G 226.1-2 39
6-21-12
Field element oversight of the ongoing implementation of TSR controls is a shared responsibility
among the Facility Representative, SSO personnel, and other functional oversight leads. The
Facility Representative is typically responsible for oversight of operational controls, such as
daily, weekly, and monthly surveillances that verify system operational parameters and SACs.
SSO personnel are typically responsible for oversight of less-frequent surveillances, such as
quarterly and annual maintenance activities, integrated system testing, and passive design feature
inspections. Depending on the complexity of the individual systems and the range and number of
systems, other field element functional leads may conduct oversight of specific TSR
surveillances or SACs in their area of expertise. Also, the SMPs in the TSRs may have elements
of the program credited as ACs or, in some cases, SACs. For the purposes of this Guide, the ACs
or SACs associated with an SMP are considered part of TSR implementation. Evaluating the
overall adequacy of SMPs is addressed in Section 4.1.3.
DOE line management should ensure that expectations for the scope, breadth, depth, and
periodicity of these SSO and Facility Representative reviews are defined in guidance and site
procedures. The following sections provided attributes that should be considered when
developing and periodically updating such expectations and guidance.
Field element oversight of TSR controls should include the following attributes:
1. A comprehensive set of routine operational awareness activities is identified and
documented.
The following should be considered when developing the set of operational awareness
activities:
- Monitor TSR surveillance completion status board or other tracking tool;
- Review logs and other information to maintain awareness of the results of TSR
surveillances;
- Monitor actions in response to discovered TSR violations and out-of-tolerance
surveillance results;
- Observe contractor implementation of ACs and SACs;
- Observe contractor performance of required surveillance requirements;
- Review contractor performance measures and indicators;
- Observe causal analysis and extent-of-condition reviews; and
- Review corrective action status.
Section 33
2. A method for selecting the type, number, and frequency of routine operational awareness
activities is established and documented.
Expectations for conducting operational awareness activities on a routine basis are
established, and the results of these activities are documented. The expectations should
include identifying routine activities that are conducted daily, weekly, monthly, quarterly,
and “as needed.” For example, daily activities could include reviewing the operations status
board and listening to daily operations calls, weekly activities could include observing ACs
(such as verification of material-at-risk inventories) and reviewing performance metrics and
40 DOE G 226.1-2
6-21-12
other sources of contractor data, monthly activities could be observing system maintenance
or surveillance activities, and quarterly activities could be observing or conducting system
walkdowns and shadowing contractor system assessment activities, including contractor
IVRs of TSR controls. “As needed” activities could be observing responses to TSR non-
compliances, reviewing occurrence reports, and evaluating the adequacy of the
implementation of compensatory measures resulting from an as-found discrepant condition.
Operational awareness activities should include a representative sample of the full set of TSR
controls so that a periodic analysis of oversight information, including information from the
CAS, can be used to:
- Identify areas that warrant an independent assessment of the implementation of a specific
set of controls or new controls;
- Identify the need for a “for cause” assessment;
- Adjust the focus of upcoming operational awareness activities;
- Provide feedback on contractor performance based on performance measures;
- Identify new performance targets; and
- Identify the need for any contractor-directed actions.
3. The method for selecting the scope of safety basis controls credited and included in the TSR
that require an initial and/or a periodic formal assessment (i.e., an IVR) is identified and
documented, along with the periodicity for conducting the IVRs.
Scope and Periodicity of Contractor Safety Basis Control IVRs. Section 3.3 of Appendix D,
Performance of IVRs of Safety Basis Controls, of DOE G 423.1-1A, Implementation Guide
for Use in Developing Technical Safety Requirements, provides guidance for the re-
verification of safety basis controls by nuclear facility contractors. The following is an
excerpt of that guidance to provide context for the additional guidance for conducting DOE
field element IVRs of safety basis controls:
The re-verification of Safety Basis controls is an important tool for contractors to ensure
that they continue to operate the facility in accordance with the Safety Basis. Many of the
hardware controls will have surveillance requirements that periodically ensure they are
operable to perform as documented in the Safety Basis. In general, re-verification of
Safety Basis controls should be performed every 3 to 5 years as part of the contractor’s
ongoing assessment process. Safety controls that are susceptible to the effects of the
degradation of human knowledge (e.g., procedural controls) typically should be re-
verified at least every 3 years, and controls dependent upon hardware functionality
typically should be re-verified at least every 5 years.
The following factors should be considered in determining the specific frequency, scope,
and depth of re-verification of a Safety Basis control.
Section 34
- Safety significance of Safety Basis control
- Type of Safety Basis control and susceptibility to degradation
- Extent of Safety Basis control changes that have accumulated since the last IVR.
DOE G 226.1-2 41
6-21-12
The following guidance is intended to supplement the above general guidance for Federal
oversight of contractor IVRs conducted consistent with DOE G 423.1-1A and to aid in
determining a reasonable basis for assessing the periodicity, breadth, and depth of periodic
contractor IVRs. This additional guidance may be used in the developing site specific
implementing procedures.
The field element should establish, through appropriate contract mechanisms, site-specific
expectations for both initial and periodic contractor IVRs, the frequency of the periodic reviews,
and an approach for establishing the sample size for verifying a single control in facilities with
redundant safety systems and systems with redundant controls and multiple components.
A graded approach for conducting re-verification IVRs should ensure a higher priority, both in
the sample size of the controls to be reviewed and the periodicity of the review, for safety class
controls and controls that are more reliant on human performance, such as SACs. The sample
size for each IVR selected to be performed should be based on the risk significance of the safety
system, past operational performance, and the number of safety systems and their associated
complexity of operation. Greater numbers of safety systems and their associated complexity will
normally result in the need to devote more time to preparing and conducting an assessment. The
following examples illustrate some ways to apply the graded approach to determine the
periodicity, scope, and depth of periodic IVRs. (These examples are for illustrative purposes
only.)
Example 1
A nuclear facility has one safety class system, with one daily surveillance requirement
(SR), two monthly SRs, and one annual SR. The daily SR specifies a check of ten similar
components around the facility, the monthly surveillances specifies a check of two
redundant systems with multiple components, and the annual surveillance specifies a
comprehensive evaluation of the entire system.
Since there is only one safety class system, and it has a relatively small number of
surveillances and components, the scope of the IVR would be expected to include all the
individual surveillances and most of the components within the depth or sample size of
the IVR.
Example 2
A nuclear facility has 5 safety class systems with a total of 20 SRs and 10 safety
significant systems with over 50 SRs and over 200 individual components that are
checked during all the SRs.
Since there is a large number of individual SRs and overall components, the scope and
sample size of the IVRs need to be carefully evaluated and determined. For example, one
approach could be to evaluate one-third of the safety class SRs each year so that all are
covered in three years, with 50% of individual components covered each three-year
cycle. With sustained performance, and based on an analysis of the results of the baseline
42 DOE G 226.1-2
6-21-12
cycle, the sample size for subsequent cycles may be reduced. The overall objective is to
ensure sufficient breadth and depth in the periodic reviews to provide a reasonable level
of confidence that the safety basis controls continue to be effectively implemented over
an established period of time.
Example 3
Section 35
This example illustrates an approach for determining the sample size of individual
components that are tested as part of a single TSR SR.
The safety class Quarterly Fire Alarm System Surveillance requires a physical test of
each of 20 alarm panels the nuclear facility. Since this is a safety class control, an IVR
should be considered every three years, with enough of the individual components
evaluated to reach a conclusion about overall effectiveness. For 20 components, 5 to 10
components may be tested. For a system with only five individual components, the
sample size may be need to initially be all five, and then the sample size may be reduced
for the following three-year cycle based on sustained performance.
Scope and Periodicity of Field Element IVRs. As stated in Section 3.3 of Appendix D of
DOE G 423.1-1A, DOE may also choose to perform periodic re-verification of Safety Basis
controls. This can be performed as part of DOE’s normal oversight efforts (e.g., reviews
conducted by the SSO staff or Facility Representatives, or through DOE shadowing of
contractor IVR activities) and may not be as formal or detailed as the contractor re-
verification. The appropriate reviewers and level of formality should be determined as part of
the DOE’s integrated oversight planning. The following section provides guidance for
selecting the scope, sample size, and periodicity for conducting field element IVRs of
existing safety basis controls.
The field element should document an approach for selecting the scope, sample size, and
periodicity for conducting IVRs. The primary emphasis should be on observing or shadowing
contractor-led IVRs. The type and number of IVRs shadowed by the field element should be
based on the significance of the control, the results of contractor assessments, and the results
of field element operational awareness activities. As previously described in this section, the
routine operational awareness activities of TSR control implementation, such as observing
valve lineup verifications, conducting log reviews, and observing TSR surveillance and
maintenance activities, should be documented so the results can support the selection of
which contractor IVR to shadow.
For facilities that have a relatively small number of safety class SSCs (fewer than 5), with a
relatively small number of total combined surveillances for these systems (fewer than 20 a
year), the field element should only need to shadow contractor IVRs on a small subset of
these controls. For example, with a total of 20 safety class controls, using the guidance in
DOE G 423.1-1A outlined above, the contractor should conduct IVRs on a sample of these
controls each year and should cover a majority of them every three years. The field element
should shadow a subset of the contractor IVRs and, based on the results of the contractor
IVRs and their operational awareness activities, may also decide to lead an IVR on a TSR
DOE G 226.1-2 43
6-21-12
control not included in the scope of a contractor IVR. If performance is good and there is
high confidence in the CAS and the quality of the contractor IVRs, the field element should
not need to lead a separate IVR in a given assessment cycle. However, for safety class SSCs,
the field element should establish a baseline assessment program that includes shadowing at
least one contractor IVR each year and leading an IVR at least once every three years.
Section 36
For facilities that have a greater number of safety class SSCs (e.g., more than 5) and total
combined controls for these systems (e.g., more than 50), the contractor is not expected to
perform IVRs on all the combined controls over a three-year period. To provide confidence
in the overall performance and operability of the greater number of systems, the contractor
should sample enough of the various controls to provide reasonable assurance of continued
system operability and compliance with the TSRs each year. This may mean that only 20-
30% of the individual controls will have an IVR over a three-year period.
Likewise, with a significantly greater number of safety class systems and total controls, the
field element should consider conducting more than one shadow assessment of contractor-led
IVRs and leading at least one IVR each year.
For facilities with only safety significant systems and related surveillances, a similar
approach should be used for selecting the type, number, and scope of shadow assessments of
contractor IVRs and field element-led IVRs. However, the periodicity may be extended so
that at least one shadow assessment is performed every three years and at least one field
element-led IVR is conducted every five years.
The program office for each site should establish specific expectations for the number of
field element IVRs that are expected to be performed on a periodic basis. The periodicity
should be based on the relative number of safety class and safety significant controls,
confidence in the CAS and line oversight, and other relevant factors.
Specific Administrative Controls. Specific expectations for the development and oversight of
SACs are included in DOE-STD-1186-2004, Specific Administrative Controls. Since the
effectiveness of these controls relies more on human performance than on engineered
controls, an appropriate priority should be placed on including the SACs in the scope of
periodic recurring IVRs, both for the contractor and the field element.
Administrative Controls. The DSA may credit elements of SMPs and include them in the
facility TSRs as ACs. These controls should be explicitly evaluated as part of the oversight of
the SMPs. Periodic evaluation of the ACs may be included in the scope of IVRs, both
contractor and field element, if appropriate.
4. A written oversight plan is developed and documented, with formal change control.
The written oversight plan should identify and schedule the significant operational awareness
activities conducted on a monthly and quarterly basis, such as observations of TSR control
performance, selected shadow assessments of contractor assessments and IVRs, and field
element IVRs selected for each annual assessment cycle. The breadth and depth of the
routine and scheduled operational awareness activities and shadow and independent field
44 DOE G 226.1-2
6-21-12
element assessments should be sufficient to allow meaningful conclusions on a recurring
basis, typically quarterly and annually, in the following areas:
- Identify the need for any additional field element assessments and/or IVRs for the next
quarterly or annual cycle;
- Identify the need to conduct a “for cause” assessment;
- Adjust the focus of the upcoming quarter’s operational awareness activities;
- Provide feedback on contractor performance based on performance measures;
- Identify new performance targets;
- Identify directed contractor actions; and
- Independently evaluate the status and overall health of the implementation of TSR
Section 37
controls.
4.1.3 Safety Management Program Implementation
The field element should routinely monitor and formally assess, on a periodic basis, each SMP
defined in the facility DSA. The field element should identify an oversight lead for each credited
SMP. The following are examples of typical SMPs identified in a nuclear facility DSA:
• Fire protection program;
• Criticality safety program;
• Radiation protection program;
• Radioactive waste management program;
• Nuclear material packaging and storage;
• Nuclear explosive safety program;
• Emergency management;
• Safety basis program:
USQ, and
DSA/TSR updates; and
• Other specific safety programs credited in the DSA – for example, the pressure safety
program.
Field element oversight of SMPs should include the following attributes:
1. A comprehensive set of routine operational awareness activities that focuses on SMPs is
identified and documented.
The following should be considered when developing the set of operational awareness
activities to oversee SMPs:
- Review contractor SMP performance metrics;
- Review status of issues and corrective action status;
- Review related occurrence reports;
- Review status and results of contractor assessments;
DOE G 226.1-2 45
6-21-12
- Observe performance of credited SMPs and ACs;
- Review implementing procedure updates; and
- Attend/review related SMP training classes.
2. A method for selecting the type, amount, and frequency of routine operational awareness
activities to oversee SMPs is established and documented.
Expectations for conducting operational awareness activities to oversee SMPs on a routine
basis are established, and the results of these activities are documented. In general, these
activities are performed less often than for safety systems and TSRs. Emphasis should be
placed on monitoring the performance of any credited ACs and monitoring program
performance measures. Some activities should be conducted on a recurring basis, such as
monthly and quarterly.
The overall breadth of operational awareness activities to oversee SMPs should be sufficient
to provide for a periodic analysis of oversight information, including information from the
CAS, that can be used to:
- Identify focus areas for any shadowing of contractor periodic assessments of the SMP;
- Identify focus areas for field element independent periodic assessments of the SMP;
- Provide feedback on contractor performance based on performance measures;
- Identify new performance targets; and
- Identify actions directed by the contractor, such as requiring a special assessment of an
SMP element or the entire SMP.
3. The expectations for periodic assessments of credited SMPs are identified.
A baseline frequency for conducting formal assessments of credited SMPs for nuclear
facilities should be established. Some DOE regulations and directives require field element
reviews of specific contractor programs over a certain period of time. For example, the field
element is required to perform a comprehensive assessment of the conduct-of-operations
program every three years. If the SMP has specific requirements for conducting assessments
on a certain periodicity, those requirements should be followed. If a longer periodicity is
warranted based on sustained good performance and a mature CAS, the field element
manager may request an exemption from the requirement using the process in
DOE O 251.1C, Departmental Directives Program. However, regardless of performance, the
field element should perform an assessment of all credited SMPs at least once every five
years. Where a sitewide SMP covers a number of nuclear facilities, it is appropriate to
sample the implementation in a subset of facilities, if at least one SMP in each nuclear
facility is assessed in a specific five-year period. The breadth and depth of the formal
assessments should be adjusted based on the results of operational awareness activities,
contractor performance, the relative importance of any credited ACs in the SMP, and
confidence in contractor assurance information.
Section 38
46 DOE G 226.1-2
6-21-12
4.1.4 Safety Management System Implementation
The objective of oversight in this area is to evaluate the effectiveness of ISM systems
implementation, primarily at the facility and activity level; the effectiveness of the CAS; and QA
programs.
A field element lead should be identified to evaluate the broad safety management systems listed
below, as they apply to nuclear facilities. These broad safety management systems are normally
applied on a sitewide basis but are relied upon as a safety management program supporting
implementation of the safety basis. Thus, an oversight program focused on nuclear facilities
should assess whether the sitewide program provides effective implementation of the program at
the nuclear facilities.
1. Integrated Safety Management
Effectiveness Reviews. DOE field offices are responsible for performing ISM system
effectiveness reviews and using the results of these reviews to prepare ISM declarations of the
status of both field office and contractor ISM system implementation and submit the declarations
to their respective program office.
Effectiveness reviews should consider both ISM process and outcome measures. Examples of
ISM process measures include how well the organization addresses: (1) implementation of each
ISM core function and principle; (2) integration of ISM with other management systems, such as
QA; and (3) the effectiveness of the identification of weaknesses and the effectiveness of
improvement activities. Additional examples of ISM process measures include: (1) performance
on process-based performance measures, and (2) results of oversight reviews. The ISM outcome
measures can be obtained from the results of the field office’s achievement of their safety goals
and objectives and the results of the contractor meeting DOE’s expectations described in the
contractor’s safety performance objectives, measures, and commitments. DOE O 450.2, Section
5.c. requires “the establishment of the annual Field Element safety goals and objectives and
contractor safety performance objectives, measures, and commitments.” DOE’s acquisition
regulations (DEAR), 48 CFR 970.5223-1, Integration of environment, safety, and health into
work planning and execution, requires “On an annual basis, the Contractor shall review and
update, for DOE approval, its safety performance objectives, performance measures, and
commitments consistent with and in response to DOE's program and budget execution guidance
and direction.”
ISM system effectiveness reviews serve to: (1) determine the effectiveness of the ISM system in
supporting the conduct of work, (2) identify weaknesses to focus attention on corrective and
improvement actions, (3) identify opportunities for improvement in the efficiency or
effectiveness of the ISM system and its implementation, and (4) identify actions for continuous
improvement both at the site and for sharing with other DOE elements to aid in improvements at
other locations.
DOE field offices should identify and provide the criteria that will be used to assess contractor
ISM effectiveness. These criteria should be conveyed to their contractors as early as possible
DOE G 226.1-2 47
6-21-12
Section 39
(preferably one year in advance of planned effectiveness reviews) so that contractors’ efforts and
resources are appropriately applied to meeting DOE's expectations. Similarly, DOE field offices
would benefit from receiving from their program office early identification of effectiveness
criteria in order to plan the field office self-assessments and prepare for program office line
oversight reviews of the field office. The criteria for determining effectiveness should be
included in ISM system descriptions and updated periodically and when changes are made to the
ISM system description.
ISM system re-assessments should be scheduled as part of the site’s IOP once the need, scope,
and frequency of re-assessments are determined. All DOE and contractor organizations are
required to ensure that their ISM system descriptions are complete, accurate, and up to date. The
timing of this process should be coordinated with the DOE budget planning and formulation
cycle so that safety and quality issues and considerations are an integral part of the budget
process. ISM system description updates should be reflected in ISM declarations, if necessary.
Facility and Activity Level Work Planning and Control. DOE G 450.4-1C, Integrated Safety
Management System Guide, includes guidance that is useful for activity level work planning and
control. DOE G 450.4-1C, Attachment 4, Work Planning and Execution, describes a facility and
activity level work planning and control process, and Phase II Core Expectations in Attachment
8, ISM Effectiveness Reviews, Declarations, and Verifications, provides eight core expectations
that sites can use for effectiveness reviews of facility and activity level work planning and
control.
CRADs are useful tools for performing effectiveness reviews. Appendix C of this Guide
(DOE G 226.1-2) provides links to both DOE and EFCOG5 CRADs that can be used to develop
local CRADs for effectiveness reviews of facility and activity level work planning and control.
The DOE CRADs are contained in DOE-HDBK-3027-99, Integrated Safety Management
Systems (ISMS) Verification Team Leader's Handbook, which includes CRADs for verifying
how well the procedures, policies, and manuals of practice for facility and activity level work
planning and control have been implemented. The EFCOG CRADs include CRADs for
performing assessments of activity level work planning and control programs and CRADs for
assessing the effectiveness of the implementation of these programs. Results of effectiveness
reviews of facility and activity level work planning and control, using local CRADs derived from
these published CRADs, should be included in ISM system declarations.
ISM Declarations. The ISM declaration process is essential for promoting continuous
improvement of ISM systems. It provides an opportunity to review, analyze, and evaluate safety
performance.
The need for, and frequency of, declarations must be based on performance history
(DOE O 450.2, Section 4.c.) and should be supported by objective evidence. Performance history
can be determined from multiple indicators of safety performance, including: results of self-
assessments; results of oversight reviews; results of integrated reviews across multiple reporting
elements; performance results for established field office goals and objectives and contractor
performance objectives, measures, and commitments; conclusions of operating experience
programs; and other performance information. Examples of objective evidence include: safety
Section 40
48 DOE G 226.1-2
6-21-12
and quality performance measures data; results of assessments, surveillances, management
walkthroughs, and event and accident investigations; and documented effectiveness of actions
taken to correct safety deficiencies and poor safety and quality performance. The objective
evidence should include results of both DOE and contractor oversight activities.
The recommended process for preparing ISM system declarations consists of the following steps:
(1) perform effectiveness reviews of the contractor's ISM system (this step may be conducted
continuously and the review results summarized when a declaration is prepared); (2) perform
self-assessment of the field office ISM system; (3) update the ISM system goals and objectives,
performance objectives, measures, and commitments; (4) update the ISM system descriptions as
necessary; and (5) prepare the ISM system declaration addressing the specific criteria provided
by the field office and respective program office.
In addition, DOE G 450.4-1C, Integrated Safety Management System Guide, includes
Attachment 8, ISM Effectiveness Reviews, Declarations, and Verifications, which provides
guidelines for ISM declarations that assessors can use as background information when planning
an assessment that addresses ISM declarations.
ISM System Verification. ISM verification reviews typically are performed when DOE
determines a need to perform a comprehensive and in-depth review of ISM system
implementation (e.g., after a new contractor assumes responsibility for a site). Field offices
should consider the scope and periodicity of assessment activities by outside groups in
determining whether a full verification is needed and should tailor the scope of the verification to
focus on areas that have not received recent attention or are known to need verification of
improvement actions. Program offices should plan and conduct full ISMS verifications on a
fixed periodicity, such as once every three to five years, to promote organizational learning and
continuous improvement.
Appendix C of this Guide (DOE G 226.1-2) includes a link to DOE-HDBK-3027-99, Integrated
Safety Management Systems (ISMS) Verification Team Leader's Handbook, which includes two
sets of CRADs for use in verifying the adequacy of ISM programs. One set is for verifying the
adequacy of the documentation of the procedures, policies, and manuals of practice used to
implement safety management and focuses on the management level. The other set is for
verifying the adequacy of how these procedures, policies, and manuals of practice have been
implemented at the facility or activity level.
2. Quality Assurance
DOE Federal organizations should conduct line management oversight and self-assessments to
evaluate whether they are effective in overseeing the contractor’s, as well as their own
organizations’, QA programs.
An effective contractor QA program is essential for effective implementation of the safety basis
(e.g., procurement processes ensure fidelity of components that provide a nuclear safety
function). Adequate oversight of the contractor’s QA program is therefore an essential element
of an effective oversight program for nuclear facilities. DOE Order 414.1D, Quality Assurance,
DOE G 226.1-2 49
6-21-12
requires the use of NQA-1, Quality Assurance Requirements for Nuclear Facility Operations, as
the default QA standard (others can be used if approved by the secretarial officer).
Section 41
Oversight of the approved contractor QA program at nuclear facilities should focus on the
implementation of QA processes for nuclear applications as detailed in the QA program and the
implementing standard (normally NQA-1). Oversight of the contractor QA program should be
integrated with SSO oversight (see Section 4.1.1), since SSO oversight activities necessarily
include a large degree of QA oversight.
Oversight of the contractor QA program at nuclear facilities should have a particular emphasis
on safety systems and should include (but not be limited to) assessments of the effective
implementation of:
• Design control processes;
• Procurement processes, including commercial grade dedication (as described in NQA-1);
• Work control processes;
• Corrective action processes;
• Flowdown of applicable requirements and expectations to subcontractors, vendors, and
suppliers;
• Safety software, as defined by DOE O 414.1D; and
• Suspect/counterfeit items (see DOE O 414.1D, Attachment 3, Suspect/Counterfeit Items
Prevention).
3. Contractor Assurance System
Section 3.5.3 provides information on reviewing a CAS. A published CRAD that can be used for
developing a local CRAD for evaluating the implementation and effectiveness of a CAS is
provided in Appendix C. Corrective action management is described in Section 3.6, and issue
identification is addressed specifically in Section 3.6.1.
4.1.5 Formality of Operations Programs
Formality of operations usually refers the following four programs that are implemented with a
high degree of rigor in a DOE nuclear facility:
• Conduct of Operations (Corresponding Field Element Oversight Lead - Facility
Representative);
• Conduct of Engineering (Corresponding Field Element Oversight Lead - Engineering Lead
with SSO personnel support);
• Conduct of Maintenance (Corresponding Field Element Oversight Lead - Maintenance
Functional Area Lead); and
• Conduct of Training (Corresponding Field Element Oversight Lead - Contractor Training
and Qualification Functional Area Lead).
The responsible field element oversight leads for each of the components of the formality of
operations program should conduct a mix of oversight activities to provide a reasonable level of
50 DOE G 226.1-2
6-21-12
assurance that the formality of operations program supports safe operation of the nuclear facility.
This mix of activities would include operational awareness, shadow assessments, and
independent Federal assessments required by DOE directives. For areas where an independent
Federal assessment is not required by a DOE directive, Federal oversight should focus on
shadowing contractor assessments and conducting operational awareness activities to provide an
adequate level of confidence in the maturity of each of the core components of the formality of
operations program.
Credited elements of the components of the formality of operations program, such as conduct of
operations, are evaluated as part of that SMP. Also, some TSR surveillances require meeting
specific requirements of components of the overall formality of operations program. For
example, a TSR that requires independent verification (IV) should meet the requirements for IV
in the contractor’s conduct of operations program. Another example is maintenance-related
surveillance requirements and tests that would need to meet the applicable requirements of the
nuclear facility maintenance program. The results of these types of TSR implementation
oversight should be reviewed to identify information that also provides insight into the
performance of the individual components of the formality of operations program.
Section 42
Implementation of the components of the formality of operations program is highly interrelated.
For example, the conduct of engineering program may include requirements for identifying
predictive and preventive maintenance requirements. The maintenance program defines
expectations for developing implementing procedures, conducting the preventive and predictive
surveillance requirements, and conducting post-maintenance testing. The conduct of operations
program identifies requirements for maintaining system status during the maintenance activity,
communicating results, and if necessary reporting significant issues. The conduct-of-engineering
program establishes expectations for maintaining the technical baseline and evaluating system
deviations as a result of post-maintenance testing. Finally, the training program identifies
training requirements for operations, maintenance, and engineering activities. As a result, the
field element leads for each component of formality of operations should routinely discuss the
results of their oversight activities in order to identify common issues and weaknesses that may
need to be addressed.
Operational Awareness Activities. Due to the highly interrelated aspects of the each
component of formality of operations, specific observations of an activity should be conducted
from start to finish, including the interfaces with other components of formality of operations.
Each of the oversight leads may conduct these observations of work in process separately, or
collectively as a group. If they are conducted separately, the oversight lead should document any
issues that other leads might factor into their oversight activities. Additionally, field observations
of activity-level work control should include applicable evaluations of elements of formality of
operations.
Formal Assessments. The contractor should periodically assess several key aspects of the
overall formality of operations program over a baseline period. The contractor should establish
the scope and periodicity for these baseline assessments. Some assessments are identified in the
TSRs as ACs with a defined scope and periodicity of review. Another approach is for the
contractor to conduct what are sometimes called “facility centered assessments,” which consist
DOE G 226.1-2 51
6-21-12
of vertical reviews of the interfaces of programs within a facility, system, and activity and
horizontal reviews looking at a single program across a facility, system, and activity. These are
typically conducted on a recurring basis, such as every three or five years.
The field element should encourage contractors to perform integrated facility centered
assessments (or similar approaches) at defined periodicities. The field element should use the
results of operational awareness activities to select focus areas to shadow during these
assessments.
Additionally, the field element needs to identify the set of DOE directive or Headquarters
line/PSO requirements for assessments of the key components of formality of operations on a
recurring basis. Where the formality of operations program covers a number of nuclear facilities,
it is appropriate to sample its implementation in a subset of facilities, if the overall program is
evaluated across all the nuclear facilities within the required timeframe. The breadth and depth of
the formal assessments should be adjusted based on the results of operational awareness
activities, contractor performance, the relative importance of any credited ACs in any of the
components of formality of operations, and confidence in contractor assurance information.
Section 43
Another recommended approach is to conduct an in-depth integrated assessment of a facility
safety system, process, or specific control, or review the results of a detailed vertical slice of a
safety system, process, or control, with an emphasis on aspects of formality of operations.
4.1.6 Safety Culture
Policy and Requirements Related to Safety Culture. The ISM policy and order emphasize that
a healthy safety culture is an inherent element of ISM, and the ISM Guide (DOE G 450.4-1C)
provides guidance related to safety culture. Among other things, the ISM Guide discusses three
key safety culture focus areas (leadership, employee/worker engagement, and organizational
learning) that are consistent with the overarching DOE ISM framework. In addition, DOE and
the EFCOG collaborated to publish information and resource documents related to safety culture.
The EFCOG website (http://efcog.org/wg/ism_pmi/index.htm) identifies a wide range of
resources that can be useful to DOE line managers and site operating contractors in establishing
and sustaining a healthy safety culture. DOE contractors may adopt guidance from
DOE G 450.4-1C or the EFCOG documents, or they may use various other models for
establishing and sustaining a healthy safety culture. As examples, the Nuclear Regulatory
Commission (NRC) has developed policies and guidance related to safety culture including a
safety conscious work environment6 (SCWE).
A December 5, 2011, memorandum on nuclear safety, signed by the Secretary of Energy and
Deputy Secretary of Energy, identifies nuclear safety as a core value of DOE and further
emphasizes DOE’s commitment to a strong and sustained safety culture as an essential element
of nuclear safety (http://www.hss.energy.gov/deprep/2012/TB12J24A.PDF). That memorandum
6 The NRC final guidance for SCWE defines this term as the employee’s willingness to identify safety concerns, an
important, but distinct attribute of a strong safety culture (which includes other attributes, such as safety-over-
production principle, procedural adherence, and conservative decision-making).
http://efcog.org/wg/ism_pmi/index.htm
http://www.hss.energy.gov/deprep/2012/TB12J24A.PDF
52 DOE G 226.1-2
6-21-12
indicates that DOE will be performing a broad assessment of safety culture across DOE that will
identify areas for improvement. In addition, the DOE Implementation Plan for DNFSB
Recommendation 2011-1, Safety Culture at the Waste Treatment and Immobilization Plant,
identifies plans for assessments that will lead to needed improvements in several aspects of
safety culture expectations, including guidance and tools for contractor self-assessment and DOE
oversight of a site’s safety culture. Because DOE’s response to DNFSB Recommendation 2011-
1 is expected to result in revisions to DOE guidance on safety culture, DOE plans to monitor
these efforts and will incorporate the additional guidance and lessons learned into subsequent
revisions to this Guide or through other appropriate mechanisms. In the interim, this version of
this Guide (DOE G 226.1-2) provides information and references that may be useful to DOE
organizations as they prepare to strengthen their capabilities in the oversight of the safety culture
at nuclear facilities.
Section 44
Role of Federal Line Management Oversight. In accordance with the ISM policy, DOE
Federal line managers have a responsibility to ensure a healthy safety culture at all levels of their
organizations. In addition, DOE line management has an important role in overseeing the
effectiveness of the contractor’s nuclear facility safety culture, including determining whether
contractors have established a SCWE in which employees can raise safety questions without fear
of retribution and overseeing the effectiveness of implementing DOE O 442.2, Differing
Professional Opinions for Technical Issues Involving Environment, Safety and Health, for both
DOE and contractor employees.
The DOE responsibilities for oversight of the nuclear safety culture encompass two main areas:
• Assess the adequacy of contractor management and self-assessment of safety culture through
routine monitoring and evaluation; and
• Perform independent and in-depth assessment of the safety culture of DOE and contractor
organizations as circumstances require.
Traditional assessments focus on technical and process issues using established regulations,
codes, standards, and quality assessment tools. In contrast, safety culture assessments are
characterized by a focus on human and organizational issues, using general agreement of the
results of multiple methods to validate those results, and an emphasis on the influence of
perceptions on safety performance.
DOE recognizes that various models may be used to assess safety culture. However, all models
should be determined to be appropriate for the organization under review and used by individuals
who have received training on the use of the model.
Fundamental to the capability to assess safety culture is knowledge of the elements of an
effective safety culture, including SCWE. DOE will conduct safety culture training for multiple
layers of employees as part of the 2011-1 Implementation Plan. DOE and contractor
organizations should ensure that appropriate safety culture training is institutionalized to support
implementation and assessment of safety culture.
DOE G 226.1-2 53
6-21-12
DOE assessment of safety culture should be incorporated into routine monitoring processes
because safety culture influences all aspects of nuclear safety. Issues related to safety culture
often contribute to performance deficiencies. Oversight activities that focus on safety culture
often inform management about the reasons for the deficiencies.
In implementing their oversight role, DOE organizations should be aware of factors that
challenge safety culture (e.g., budget reductions, reductions in force, and schedule pressures) and
issues that may be particularly important to facilities in the design and engineering stages of a
facility’s lifecycle. DOE should also include reviews of DOE programs and processes that are
particularly important to safety culture, such as DOE O 442.1, Department of Energy Employee
Concerns Program, and DOE O 442.2, Differing Professional Opinions for Technical Issues
Involving Environment, Safety and Health.
Routine Monitoring of Safety Culture. For routine monitoring, DOE oversight elements
should use an analytical framework that includes key organizational behaviors in order to
characterize the organization’s safety culture. For example, the NRC oversight framework
(Table 1) includes 13 behaviors grouped into four cross-cutting areas.
Table 1. NRC Oversight Framework
Cross-
Cutting
Areas
Human
Performance
Section 45
Problem
Identification and
Resolution
Safety Conscious
Work
Environment
Other Safety
Culture
Components
Behaviors
Decision
Making
Resources
Work Control
Work Practices
Corrective Action
Program
Operating
Experience
Self/Independent
Assessments
Environment for
Raising
Concerns
Preventing,
Detecting,
Mitigating
Perceptions of
Retaliation
Accountability
Continuous
Learning
Environment
Organizational
Change
Management
Safety Policies
Recurring concerns in two or more of the cross cutting areas may be an indicator that more in-
depth assessment of safety culture by the contractor or DOE is necessary.
In-depth Safety Culture Assessments. DOE in-depth safety culture oversight activities should
use an analytic framework that systematically addresses a defined set of key, observable,
organizational behaviors. DOE organizations could use or adapt information and methods
54 DOE G 226.1-2
6-21-12
developed by the NRC as a starting point for identifying the behaviors that are relevant for their
organization.7
Recommended methods for assessing nuclear safety culture employ multiple tools that provide
quantitative and qualitative data to assess each organizational behavior systematically and
objectively. The safety culture assessment team collectively should have received appropriate
training that ensures it can perform an effective assessment of safety culture.
Sources of Additional Information. DOE organizations may benefit from considering
frameworks, methods, tools, and lessons learned from other organizations and adapting them to
their needs. The following provides information about safety culture assessments that may be
particularly useful to DOE organizations, including links to specific sources.
This EFCOG website includes a document that describes methods for evaluating safety culture
and is particularly pertinent to DOE line management organizations that perform oversight of
SCWE at nuclear facilities The document can be found at:
http://efcog.org/wg/ism_sctt/docs/safety_culture_assessment_012309_final.pdf. NRC has a well
established framework for oversight of safety culture that identifies relevant behaviors. The
approach is defined in the NRC Inspection Manual and associated inspection procedures, which
can be found at: http://www.nrc.gov/reading-rm/doc-collections/insp-manual/.
Within the NRC Inspection Manual, the following chapters and inspection procedures are most
relevant for assessing safety culture:
• NRC Inspection Manual Chapter 0310, Components within the Cross-Cutting Areas;
• NRC Inspection Manual Chapter 1245 Appendix C12, Safety Culture Assessor Training
and Qualification Journal;
• U.S. NRC Inspection Procedure IP 40100, which provides inspector guidance for
evaluating an independent safety culture assessment; and
• U.S. NRC Inspection Procedures IP 95001, 95002, and 95003 and their enclosures
(particular attention to Attachment 95003.02), which provide inspector guidance for
evaluating a third-party safety culture assessment and detailed information on methods
and tools.
4.2 Application of Criteria Review and Approach Documents
DOE oversight encompasses activities performed by DOE organizations to determine whether
Federal and contractor programs and management systems, including assurance and oversight
systems, are performing effectively and complying with DOE requirements. Oversight programs
include operational awareness activities, onsite reviews, assessments, self-assessments,
performance evaluations, and other activities that involve evaluation of contractor organizations
and Federal organizations that manage or operate DOE sites, facilities, or operations.
Section 46
7 More details on these behaviors and assessment methods may be found in the NRC references in the following
paragraphs.
http://efcog.org/wg/ism_sctt/docs/safety_culture_assessment_012309_final.pdf
http://www.nrc.gov/reading-rm/doc-collections/insp-manual/
DOE G 226.1-2 55
6-21-12
CRADs are used to establish the depth and detail of an assessment and to provide clarity and
consistent guidance to the assessment team, as well as to the organization being assessed. The
quality of these documents significantly impacts the overall quality of the assessment. The
criteria delineated within the CRADs should be specific and as objective as possible. The graded
approach is applied to the scope of the assessment through the CRADs. Areas that include
significant hazards, such as nuclear operations, should be assessed to a greater extent than other
areas.
4.2.1 Description of a CRAD
In general, a CRAD consists of the following elements:
• Performance Objective: Identification of the expectation(s) or requirement(s) to be verified,
which reflect the complete scope of the assessment.
• Criteria: The specifics by which the performance objectives are measured, including
regulatory and/or site-specific requirements.
• Review Approach: A statement of the documents, interviews, and observations (e.g., work or
shift evolutions) that are used to obtain objective evidence in order to determine whether a
criterion is met or not.
Creating the Performance Objective. The objective in each CRAD includes all, or portions, of
one or more requirements or performance attributes being assessed. To write the objectives, use
the following as a guide:
• Begin with requirements;
• Use performance goals;
• Use performance expectations; and
• Treat functional areas broadly, allowing criteria to address specifics.
Example:
OBJECTIVE: Line management has established and implemented a fire protection program
to ensure adequate protection of operations and activities.
Criteria. The criteria in the CRAD are developed to reflect the objective and address all
requirements/performance attributes, regardless of the approach used in developing the criteria.
The criteria should follow, and be clearly related to, the requirements. It is important to
remember that the sum of the criteria should provide an adequate basis for determining whether
the objective has been met. Each criterion is a statement of the specific actions or attributes the
team members use to make a judgment that Federal and/or contractor programs and management
systems, including assurance and oversight systems, are performing effectively and complying
with DOE requirements. The criteria should be specific statements that are:
• Measurable (e.g., the “program will have ten working elements”); and
• Assessable (e.g., “there is documented evidence of meeting the working elements”).
56 DOE G 226.1-2
6-21-12
Criterion statements may also be derived from guides, standards, and good practices that are
associated with requirements.
Section 47
Review Approach. The Review Approach section of the CRAD describes the documents to be
reviewed, the personnel to be interviewed, and the field activities, including tours and walk-
downs, to be observed to allow the team to reach a conclusion as to whether the criteria have
been met. Any documents expected to be reviewed (e.g., procedures, drawings, logs, reports,
correspondence, other evaluations) should be cited in the CRAD. It is important to research and
determine how documents that control work (e.g., procedures) are promulgated. There are two
ways to determine whether documents are being followed or understood: interviews, and
observations of work or shift evolutions. The titles of the personnel to be interviewed, along with
the shift evolutions to be observed, should be recorded in the CRAD. The CRAD should also list
any other references (e.g., DOE orders, mandatory standards, or site-specific requirements)
against which the criteria are to be assessed.
For the interview portion of the CRAD, assessors should develop lines of inquiry (LOIs). LOIs
are sets of questions that are directly related to the criteria and are used to determine whether an
objective or criterion is met or not. Questions are tailored for various levels of management and
workers. Each LOI should be designed to ensure the answers from each interview are complete,
unambiguous, and sufficiently comprehensive. Questions that can be answered with a “yes” or
“no” may be used but should be followed with an open-ended question that would provide
insight and details supporting the one-word answer. For example:
• Does the contractor perform periodic assessments of the fire protection program?
• If yes, what mechanisms does line management use to ensure that assessments are performed
and that the contractor’s fire protection program is effective?
• If no, why doesn’t the contractor perform periodic assessments?
The review approach links back to each of the criteria and is tailored to the organization, facility,
staff, and procedures being assessed. If the review approach is conducted correctly, the
documented review becomes a major part of the final writeup.
4.2.2 Available Sets of CRADs
Various DOE organizations have developed CRADs for their evaluations. As examples:
• CRADs have been developed to support Facility Representative Program activities and
reviews. These have been developed by various field elements and groups and are collected
and maintained on the HSS Facility Representative web page.
http://www.hss.energy.gov/nuclearsafety/nfsp/facrep/, which also provides surveillance
guides and other information useful to oversight personnel. These CRADs also are accessible
from Facility Representative Program (HSS) (see Appendix C of this Guide).
• The HSS independent oversight organization has developed a detailed set of CRADs for
performing assessments of various safety topical areas. This organization has also developed
information and CRADs for evaluating emergency management areas, which are relevant to
http://www.hss.energy.gov/nuclearsafety/nfsp/facrep/
DOE G 226.1-2 57 (and 58)
6-21-12
nuclear safety. These CRADs are accessible from Independent Oversight (HSS) (see
Appendix C of this Guide).
• The NNSA CDNS oversight organization has developed a detailed set of CRADs for
performing assessments of various safety topical areas. These CRADs are accessible from
Various (NNSA) (see Appendix C of this Guide).
Section 48
• The EFCOG Work Management Subgroup is developing a work planning and control
program guideline that includes sets of CRADs, one set for assessing the activity-level work
planning and control program and the other for assessing activity level work planning and
control implementation activities. These CRADs are accessible from Appendix C of this
Guide.
• CRADs have been developed to support validation of the adequacy of an ISM program and
the implementation of the program in DOE-HDBK-3027-99, Integrated Safety Management
Systems (ISMS) Verification Team Leader's Handbook. These CRADs are accessible from
ISMS Verification CRADs from DOE Handbook (HSS) (see Appendix C of this Guide).
These existing CRADs provide guidance for reviewing topics; DOE Headquarters and field
elements may adapt them to provide for consistent implementation and effectiveness of periodic
safety oversight assessments. The DOE CRADs can be used for all nuclear facilities, but they are
intended to be tailored as appropriate, based on the specific scope of the review, site-specific
hazards and conditions, the applicability to the site/office, and any specific contractual
requirements.
Appendix C (which is available at
http://www.hss.energy.gov/healthsafety/flmo/appendices/index.html) presents a core set of
CRADs selected from the sources listed above. HSS will maintain this web site of available
CRADs to make them available for use as a starting point to develop facility-specific CRADs.
Although efforts will be taken to keep the CRADs on the website accurate and up to date, the
user of any CRAD should verify that the CRAD is appropriate for use. Under no circumstances
should these CRADs be considered mandatory or unalterable for use. Quite the opposite is true:
DOE line management should tailor CRADs to the DOE organization’s needs and site conditions
when establishing an oversight plan.
The CRADs that relate directly to nuclear safety program elements are expected to be most
useful for oversight of nuclear facilities. However, because nuclear facility safety could be
affected by non-nuclear aspects of operations (e.g., accidents involving chemicals), some
CRADs for other aspects of safety (e.g., chemical safety, electrical safety) and emergency
management are included in the set of CRADs.
http://www.hss.energy.gov/healthsafety/flmo/appendices/index.html
DOE G 226.1-2 A-1 (and A-2)
6-21-12
Appendix A
List of Hazard Category 1, 2, and 3 Nuclear Facilities
Available at http://www.hss.energy.gov/healthsafety/flmo/appendices/index.html
http://www.hss.energy.gov/healthsafety/flmo/appendices/index.html
DOE G 226.1-2 B-1 (and B-2)
6-21-12
Appendix B
Rules and Directives Applicable to Nuclear Facilities Line Management Oversight
Available at http://www.hss.energy.gov/healthsafety/flmo/appendices/index.html
http://www.hss.energy.gov/healthsafety/flmo/appendices/index.html
DOE G 226.1-2 C-1 (and C-2)
6-21-12
Appendix C
Criteria Review and Approach Documents
Available at http://www.hss.energy.gov/healthsafety/flmo/appendices/index.html
http://www.hss.energy.gov/healthsafety/flmo/appendices/index.html