DOE O 420.2D, Safety of Accelerators Implementation Plan
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
1
DOE O 420.2D, Safety of Accelerators
Implementation Plan
What are the major changes in the revised directive?
The applicability and intent have been clarified however, the overall approach to accelerator safety
management has not changed. Additions to the Order include a new set of pre-approved exemptions and
equivalencies, tailored requirements for low powered accelerators that were previously exempt or
undefined, updated approval authorities, updated definitions, and a requirement for the Unreviewed
Safety Issue (USI) process to be approved by DOE. Vague and ambiguous language has been removed
throughout the Order and Contractor Requirements Document (CRD). A clear boundary has been
established for regulation of activities under the Order. Exemptions and equivalencies not listed in the
Order must be processed in accordance with DOE O 251.1D, Departmental Directives Program, Appendix E,
Equivalency and Exemption Process. The CRD was revised to reflect the changes made to the Order, as
applicable. SC-4 will revise the relevant Office of Science Management System (SCMS) procedures to reflect
the changes in the Order.
How was the Implementation Plan developed?
There was continuous stakeholder engagement throughout the revision process. A separate contractor sub-
team was formed to provide feedback to the Integrated Project Team (IPT) on proposed changes. Proposed
changes to the Order were discussed and debated during several sessions at the 2021 Accelerator Safety
Workshop. The revised Order has been thoroughly socialized throughout the accelerator safety community
during the monthly large group videoconference calls.
As part of the Order revision process the IPT drafted a high-level implementation strategy with specific
actions for effectively communicating and implementing the revised requirements. The Office of Primary
Interest (OPI), SC-4, solicited feedback on the plan from affected Site Office Managers through direct
engagement of site office leadership reinforced by participation in DDFO hosted discussions. Feedback was
also included from affected Programs Offices, the Accelerator Safety Community of Practice, and the
National Laboratory Directors Council (NLDC). The 2022 DOE Accelerator Safety Workshop provided a
valuable platform for open discussion with federal and contractor individuals who will be responsible for
implementing the new requirements at their respective sites. The plan includes a set of implementation
FAQs based on stakeholder feedback. The plan and FAQs will be updated as needed based on experience,
observations, results, and additional feedback received.
How does the OPI plan to implement the revised directive?
The Order has been promulgating to Federal staff and applicable contracts via the normal communication
channels in the Departmental Directives Program. The cognizant contracting officer is responsible for
incorporating the CRD into the contracts of affected contractors.
Additional Communication Efforts
The Order and this plan will be shared with the accelerator community via the normal communication
channels. Both documents are available on the Accelerator Safety Community Information Hub SharePoint
Site. Additionally, SC-41 will request the Plan and FAQs be posted on the DOE Directives Website and DOE
OPEXShare database.
2
Section 2
To ensure there is a clear understanding of the revised Order, the OPI will engage with affected Site Offices
and Labs to provide ongoing interactions and discussions via phone calls, email, and site assist visits to
answer questions, and provide guidance. The OPI will work with federal and contractor staff at affected
sites to verify implementation over the next 12 months via a series of accelerator safety program review
assist visits. The DOE Office of Enterprise Assessment (EA) has indicated interest in conducting a series of
independent implementation reviews as early as 12 months following issuance of the revised Order.
Implementation feedback will continue to be collected from the accelerator safety community during the
monthly accelerator safety large group call. Relevant items will be documented for consideration in the
revision of the associated Guide. Post implementation, a high-level document with a list of pre-approved
exemptions and equivalencies will be collected by the Site Offices and maintained by the OPI for SC-1.
Timeline for Implementation
As an SC goal, Requirements for Federal employees should be implemented within 7 months of issuance.
Although sites may vary, contractor activities to meet requirements should target accomplished within 9
months of issuance, if possible. It should be recognized that any operation currently covered under 420.2C
and not covered under 420.2D will need a regulatory basis (or approved transition plan) for continued
operation after 420.2D is implemented at the site.
Suggested key steps for Site Office/Site use and consideration in local implementation plans
Provide a current listing/inventory of accelerators managed under this Order and exemptions or equivalencies
to this Order. (Denote basis for exemption/equivalency)
Review cited use of exemptions or equivalencies to this Order to ensure each is operating under the terms
required to use the exemption/equivalency (i.e., assess compliance with ANSI/HPS N43.3-2008, ANSI/HPS
N43.2-2021, ANSI/HPS N43.5-2005, NCRP Report 72-1983, or ANSI-HPS N43.1-2011)
Establish a periodic onsite validation process to ensure accelerators and devices granted exemptions or
equivalencies provided in section 1. of the CRD continue to be operated under the conditions of the approved
exemption or equivalency.
Establish program elements in section 2.a. of the CRD for all accelerators managed under the CRD.
Establish program elements in section 2.b. of the CRD for all accelerators managed under the CRD that
operate above 10 MeV.
Update the Contractor Assurance System to include processes to review the contractor accelerator safety
program elements listed in this CRD.
Submit accelerator safety documentation requiring DOE approval as established in the CRD.
Approve accelerator safety documentation as established in the Order.
Conduct assist visits and provide implementation guidance.
Create and maintain a high-level document with a list of pre-approved exemptions and equivalencies.
Complete update of accelerator safety documentation as appropriate.
A detailed table of implementation milestones and target completion dates is provided as a reference in
Appendix A.
3
Implementation FAQs
Applicability and Other General Questions
1) How long can a site continue to operate under 420.2C? Each site will develop an implementation
plan in accordance with CO direction and site practice. Generally, up to 1 year is afforded for new
order implementation. It is SC’s goal to implement in less than 1 year.
Section 3
2) What if I have replaced parts of a commercial sourced accelerator over time with parts not from
the manufacturer or fabricated onsite? If unable to demonstrate that each part meets OEM
standards (safety, performance, etc.) then it is considered modified.
3) Is the CRD required to be included in the contract if a site only operates accelerators under an
approved equivalency? Yes, the CRD is still included as the contractual vehicle for the equivalency
and any remaining applicable requirements. The CRD can be appropriately tailored with approval
from the DOE site manager.
4) Is there a de minimis amount of special nuclear material that could be used in an accelerator and
the order still applies? The Order does not define a de minimis level for special nuclear material
(SNM). Any quantity of SNM inside an accelerator will be subject to the same regulations that
would apply outside of an accelerator, in addition to any applicable ASO requirements, unless
superseded by an authorized alternative standard.
Equivalencies and Exemptions
5) Do I have to meet and be able to demonstrate all the requirements in the cited equivalency to
use it? Yes, and expect compliance reviews to address equivalencies
6) Is there a common format to document listed equivalencies? A common format may be
considered by the team developing the new guide, however in the interim use of an equivalency
must denote what equivalency has been invoked.
7) What support is available to review equivalencies? It is recognized that DOE site offices may not
have access to the cited sources that are invoked upon use of the equivalencies. Site offices may
request support directly from SC-41.
8) Can a site use the Lab’s Rad Protection and ISM Programs in place of the equivalencies in the
Order? Yes, provided the Site Office can confirm the existence of an appropriate crosswalk of the
referenced institutional programs with requirements in 2.a through 2.c of the CRD for accelerators
operated below 10 MeV.
9) Which requirements of the CRD will the contractor need to meet for devices that fall under the
1.c Equivalency paragraph of the CRD? The requirements in sections 1, 1.d, 2.a, 2.c, and 2.h of the
CRD apply to all accelerators that meet the definition in attachment 2, regardless of their 1.c
equivalency status. Accelerators that qualify for one of the pre-approved equivalencies in section
1.c should also qualify for relief from the requirements in sections 2.b through 2.g based on the
range of energies in the referenced standards but, this qualification does not by itself relieve the
contractor from meeting the remaining requirements of the CRD (see first sentence).
10) Is the expectation that in order for a < 10 MeV accelerator to be excluded from the requirements
in 4.c, it must also be managed to an equivalency mentioned in 3.c.(3) and/or be operated using
commercially available manufacturer documentation? No, the requirements in 4.c are not
applicable to accelerators that operate < 10 MeV. This is not contingent on meeting an
exemption/equivalency in 3.c.(3). Note that requests for exemptions and equivalencies to the
requirements of the Order which are not addressed in section 3.c. must be processed in accordance
with DOE O 251.1, Departmental Directives Program, current version.
4
Documentation and Processes
Section 4
11) What is required in a USI process to be DOE approved? Each site should work with its site office to
discuss expectations. Beyond the aspects stated in the Order, sites should consider a low enough
bar for review to ensure both individual and cumulative changes are well managed. Per the Order,
DOE must approve a specific version to be in use.
12) Does a site need to list every RGD managed under the ASO individually in the accelerator safety
documentation or can an existing inventory list be referenced? No, an existing inventory may be
referenced provided it is accurate and up to date.
5
Appendix A
Suggested Implementation Milestones
The table below contains suggested milestones and target completion dates.
Task Target Date Status Notes
Final Approval Deputy Sec Sept 9, 2022 Complete
Revised Order posted on
DOE Directives website.
IPT Lead Sept 12, 2022 Complete
Incorporate CRD into
affected contracts.
Cognizant
CO
30 Days after
issuance of
Order per
DEAR
guidance
The contractor can assess the effect
of incorporating the CRD and
propose a timeline for full
compliance. The FEM must concur
on the proposed timeline.
Provide a platform for
additional discussion
about implementation at
the 2022 Accelerator
Safety Workshop.
OPI, IPT lead Oct 18-20,
2022
Complete SC-4 hosted the workshop at DOE
HQ Germantown.
Develop strategy to
prepare Sites for planned
EA implementation
review.
OPI Dec 31, 2022 Ongoing Finalize the implementation plan.
Identify sites to Conduct assist visits
and Accelerator Safety Program
Reviews. Work with EA to gain
insight about assessment criteria.
Develop Lines of Inquiry (LOIs) for
planned program assessments.
Develop site/facility
specific implementation
plan.
Contractor Dec 31, 2022
Conduct assist visits and
provide implementation
guidance.
OPI Starting in Jan
2023
Sites and dates TBD based on OPI
assessment and site office/site
feedback and request. Assist teams
will be comprised of federal and
contractor staff from HQ and the
field. SMEs will be selected from
the Accelerator Safety COP.
Establish a periodic onsite
validation process to
ensure accelerators and
devices granted
exemptions or
equivalencies provided in
section 1. of the CRD
continue to be operated
under the conditions of
Contractor March 1, 2023 The FEM must ensure accelerators
and devices granted exemptions or
equivalencies provided in section
3.c. of this Order continue to be
operated under the conditions of
the approved exemption or
equivalency.
6
the approved exemption
or equivalency.
Provide a current
listing/inventory of
accelerators managed
under this Order and
exemptions or
equivalencies to this
Order.
Contractor March 1, 2023 The FEM must review the
listing/inventory of accelerators
managed under this Order for
appropriateness.
Establish program
elements in section 2.a.
of the CRD for all
accelerators managed
under the CRD.
Contractor March 1, 2023
Establish program
elements in section 2.b.
of the CRD for all
accelerators managed
under the CRD that
operate above 10 MeV.
Contractor April 1, 2023
Update the Contractor
Assurance System to
include processes to
review the contractor
accelerator safety
program elements listed
in this CRD.
Contractor April 1, 2023 The FEM must ensure the
Contractor Assurance System
includes processes for the review of
contractor accelerator safety
program elements as specified in
the CRD.
Complete update of
accelerator safety
documentation as
appropriate.
Section 5
Contractor April 1, 2023 Confirm that 420.2C compliant
safety basis documentation still in
use, meets the requirements of
420.2D.
Submit accelerator safety
documentation requiring
DOE approval as
established in the CRD.
Contractor April 1, 2023
Approve accelerator
safety documentation as
established in the Order.
FEM April 30, 2023
Conduct targeted
Accelerator Safety
Program Reviews to
verify implementation.
OPI/FEM 3rd,4th Qtr.
OPI reviewed
Sites and
Dates TBD.
Reviews can be led by the site office
with assistance from the OPI.
Review teams will be comprised of
federal and contractor staff from
HQ and the field. SMEs will be
selected from the Accelerator
Safety COP.
Create and maintain a
high-level document with
a list of pre-approved
OPI Sept 15, 2023
7
exemptions and
equivalencies.
All sites fully compliant. Contractor,
FEM
Sept 30, 2023 Federal staff at affected sites will be
required to verify implementation
for compliance.