Frequently Asked Questions Regarding DOE G 424.1-1C
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
DOE G 424.1-1C, Implementation Guide for Use in Addressing
Unreviewed Safety Question Requirements
Frequently Asked Questions
Date of issuance: February 6, 2023
Q1: How does the November 2, 2022, DOE response letter from the Secretary to the DNFSB regarding
the unreviewed safety question (USQ) process following a probabilistic seismic hazard analysis (PSHA)
affect expectations established in DOE G 424.1-1C, Implementation Guide for Use in Addressing
Unreviewed Safety Question Requirements?
A1: This FAQ provides further USQ process guidance as it applies to a PSHA based on the DOE response
letter. The DOE response letter states, “… when the contractor determines that the increase in hazard
identified in the PSHA update is potentially not bounded by the safety analysis, the contractor is
required to follow the process in 10 CFR § 830.203(f) because there is a potential inadequacy in the
safety analysis.”
Section 3.4 of the DOE G 424.1-1C, under New Requirements and New Methods, states, “A PISA does not
need to be considered for DSA upgrades in response to new requirements or to the use of new or
different analytical tools during the upgrade process. New requirements typically follow implementation
plans and are incorporated into DSA updates accordingly. For example, if new aircraft accident guidance
was being implemented and resulted in the addition or removal of DSA controls, the possibility of a PISA
does not need to be evaluated. Similarly, if the 10-year Natural Phenomena Hazards review identifies
the need to use new, updated data sets or assessment methods, this would not be a PISA. Following this
review, after a new or revised hazard analysis is completed, the results would be compared against
existing facility design and a determination of whether a PISA exists might be necessary.”
The contractor should note an important PISA distinction between the treatment of the 10-year NPH
review expectations and expectations after a probabilistic seismic hazard analysis (PSHA) is completed.
The Guide explains that the 10-year review is only to determine whether a new hazard assessment is
required for a specific natural phenomenon (e.g., the seismic hazard). If the 10-year review determines
that an updated hazard assessment is warranted, this does not represent a PISA. However, if an
updated PSHA identifies, or it becomes apparent at any point before completion, that a hazard increase
is potentially not bounded by the DSA, then the results of the new assessment should be considered
“new information,” and the PISA process should be followed (guidance is provided in Attachment C of
the Guide).
A USQ determination, under 10 CFR § 830.203(f)(3), for a PISA declared as a result of an increased
hazard resulting from a new PSHA, may require extensive analysis for completion. For facilities with SSCs
classified NDC-3 (SDC-3) and above, an evaluation of such SSCs is required. The Facility Condition
Assessment (FCA) process described in STD-1020-2016 Sections 9.3.2(b) through 9.3.7 may need to
approach completion before the USQ determination can be completed. Therefore, PISAs resulting from
a new PSHA likely will be unable to meet the Guide expectation (in Section C.5) of seven calendar days
to complete the USQD. The Guide acknowledges there may be situations when USQDs necessitate
extended periods of time to resolve them: “The USQ procedure may allow for DOE to approve additional
time to perform USQD evaluations on a case-by-case basis with an appropriate technical basis.”
Section 2
A PISA declaration is often accompanied by compensatory measures or operational restrictions on a
facility under 10 CFR § 830.203(f)(1). The Secretary’s letter recognizes that “Prior to the development of
the information [e.g., prepare a Facility Condition Assessment (FCA)], it is frequently not appropriate or
necessary to implement compensatory controls or operational restrictions to place or maintain the
facility in a safe condition.” Such restrictions may be unnecessary in response to a new PSHA unless the
new FCA indicates certain SSCs could fail under the new hazard load. However, during the USQ
determination and development of the FCA, if it becomes evident that certain SSCs could fail under the
new, higher seismic load, then action should be taken to place or maintain the facility in a safe
condition, and the contractor should implement such compensatory measures.