DOE O 252.1A Admin Chg 1, Technical Standards Program - Change Chart
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
DOE O 252.1A Chg 1
3-12-2013
ADMINISTRATIVE CHANGES TO
DOE O 252.1A, TECHNICAL STANDARDS PROGRAM
Locations of Changes:
Page Paragraph Changed To
6 5.f(3) In partnership with TSMs, screens
all TSP projects (new draft
standards, revised draft standards,
standard reaffirmations, and standard
cancellations) to ensure that they
meet the intent of a DOE technical
standard and are not duplicative of
existing, adequate VCSs.
In partnership with TSMs,
screens new draft standards,
revised draft standards, standard
reaffirmations, and standard
cancellations to ensure that they
meet TSP requirements.
7 6.d DOE P 450.2A, Identifying,
Implementing and Complying with
Environment, Safety and Health
Requirements, dated 5‐15‐96.
DOE P 450.4A, Integrated
Safety Management Policy,
dated 4-25-2011.
7 6.g DOE P 450.4, Safety Management
System Policy, dated 10-15-96.
Delete
7 6.h now 6.g DOE G 450.4-1B, Integrated Safety
Management System Guide, dated 3-
1-01
DOE G 450.4-1C, Integrated
Safety Management System
Guide, dated 9-29-2011.
7 6.g thru 6.k Renumbered. 6.g thru 6.j
7 6.j now 6.i DOE O 426.1, Federal Technical
Capability, dated 11-19-09.
DOE O 426.1 Chg. 1, Federal
Technical Capability, dated 11-
19-09.
11 1.a The Preparing Activity (PA)
identifies a need for a DOE TS,
prepares a Project Initiation Request
to request to start a project to
develop the DOE TS, and consults
with the organization's Technical
Standards Manager (TSM) about the
project. The Project Initiation
Request must identify related and
potentially applicable VCSs and
provide justification why these are
not adequate for DOE needs. The
Project Initiation Request must be
approved by the PA's Senior Line
Manager (SLM), who is the
Cognizant Secretarial Officer,
designated Senior Program Official,
DOE Federal Technical Capability
Panel (FTCP) Chair, in the case of
FTCP Functional Area Qualification
Standards (FAQS), or Field Office
The Preparing Activity (PA)
identifies a need for a DOE TS,
prepares a Project Justification
Statement (PJS) prior to starting
a project to develop the DOE
TS, and consults with the
organization's Technical
Standards Manager (TSM)
about the request. The PJS
must identify related and
potentially applicable VCSs and
provide justification why these
are not adequate for DOE
needs. The PJS must be
approved by the PA's Senior
Line Manager (SLM), who is
the Cognizant Secretarial
Officer, designated Senior
Program Official, DOE Federal
Technical Capability Panel
(FTCP) Chair, in the case of
DOE O 252.1A Chg 1
3-12-2013
Page Paragraph Changed To
Manager. FTCP Functional Area
Qualification Standards
(FAQS), or Field Office
Manager.
11 1.b The Technical Standards Program
Manager (TSPM) must review the
Project Initiation Request for
completeness and if complete,
send it out for coordination to all
applicable TSMs for 15 days.
The Technical Standards
Program Manager (TSPM) must
review the PJS for completeness
and if complete, send it out for
concurrence review to all
applicable TSMs for 15
business days.
11 1.c The PA must resolve all non-
concurrences received from
commenting TSMs on the Project
Initiation Request before the
project may be approved. Where
non-concurrences cannot be
resolved with TSMs, a dispute
resolution process will be used
where the non-concurrence issues
are elevated to the responsible
SLMs. All applicable
organizations must concur before
a DOE TS project may be
initiated.
Section 2
The PA must resolve all non
concurrences received from
commenting TSMs on the PJS
before the project may be
approved. Where non-
concurrences cannot be
resolved with TSMs, a dispute
resolution process will be used
where the non-concurrence
issues are elevated to the
responsible SLMs. All
applicable organizations must
concur before a DOE TS project
may be initiated.
11 1.d If the Project Initiation Request
receives support from all applicable
TSMs, the TSPM will assign a
project number, and notify the DOE
community that a new project has
been initiated.
If the PJS receives support from
all applicable TSMs, the TSPM
will assign a project number,
and notify the DOE community
that a new project has been
initiated.
11 2. Draft new, revised, and canceled
DOE TSs are coordinated using the
TSP RevCom system. They can
receive either full or limited
coordination, depending on the level
of review required. The process for
coordinating DOE TSs is as follows:
Draft new, revised, reaffirmed,
and canceled DOE TSs are
coordinated using the TSP
RevCom system. They can
receive either full or limited
coordination, depending on the
level of review required. The
process for coordinating DOE
TSs is as follows:
12 4. There are several types of
maintenance activities that may need
to be performed for DOE TSs:
revisions, change notices,
reaffirmations, cancellations,
reinstatements, and in-activations for
There are several types of
maintenance activities that may
need to be performed for DOE
TSs: revisions, change notices,
reaffirmations, and
cancellations. Anyone,
DOE O 252.1A Chg 1
3-12-2013
Page Paragraph Changed To
new design. Anyone, including DOE
TS users, may identify the need for
TS maintenance activities. The
following process applies to all of
the above cases.
including DOE TS users, may
identify the need for TS
maintenance activities. The
following process applies to all
of the above cases.
12 4.d Development, coordination, and
approval of maintenance actions
(revised DOE TSs, reaffirmed DOE
TSs, canceled DOE TSs, reinstated
DOE TSs, or in-activations) must
proceed in accordance with
paragraphs 1, 2, and 3 above, except
that only revisions, cancellations,
and in-activations require new
project numbers. Change Notices
may be used to transmit non-
technical changes that affect less
than 25 percent of the DOE TS.
Development, coordination, and
approval of maintenance actions
(revised DOE TSs, reaffirmed
DOE TSs, or canceled DOE
TSs) must proceed in
accordance with paragraphs 1,
2, and 3 above, except that only
revisions require new project
numbers. Change Notices may
be used to transmit non-
technical changes that affect
less than 25 percent of the DOE
TS.