Section 1
U.S. Department of Energy LIMITED CHANGE
Washington, DC
Chg 2 (LtdChg): 11-22-2021
SUBJECT: LIMITED CHANGE TO DOE G 413.3-7A, RISK MANAGEMENT GUIDE
1. EXPLANATION OF CHANGES. To add content related to joint cost and schedule
confidence level (JCL), also known as integrated schedule and cost risk analysis. To add
content related to parametric estimation of contingency. To update references to
superseded DOE directives and standards and external best practices.
2. LOCATIONS OF CHANGES: See chart below.
Page Section Changed To
Throughout Minor formatting updates.
Throughout Minor grammatical edits.
Throughout DOE-STD-1189-2008 DOE-STD-1189-2016
Throughout ANSI/EIA-748B EIA-748D
i Forward “Guides are not requirement
documents and should not be
construed as requirements. DOE
Guides are part of the DOE
Directives Program and provide
suggested ways of implementing
Orders, Manuals, and other
regulatory documents.”
“This Guide does not impose,
but may cite, requirements.
Guides neither substitute for
requirements nor replace
technical standards that
implement requirements.
Program-specific guidance
takes precedence over this
guide. Send citations of errors,
omissions, ambiguities, and
contradictions found in this
guide to
PMpolicy@hq.doe.gov.”
10 2.0 “This guide should not be
intended to replace assessment
processes developed for nuclear
safety and environmental, safety,
health, and quality (ESH&Q). It
should also not be intended to
replace assessment processes
developed for safeguards and
security. This guidance also
recognizes the benefit and
necessity of early consideration
and integration of safety related
project risk into the project risk
management process.”
“This guide should not be
intended to replace assessment
processes developed for nuclear
safety, climate change, and
environmental, safety, health,
and quality (ESH&Q). It should
also not be intended to replace
assessment processes developed
for safeguards and security.
This guidance also recognizes
the benefit and necessity of
early consideration and
integration of climate change,
safety, and security related
DOE G 413.3-7A
Page Section Changed To
project risk into the project risk
management process.”
11 3.2 “In order to implement the risk
management principles and
processes successfully, an
organizational process
perspective should be considered
within which the risk
management.”
“In order to implement the risk
management principles and
processes successfully, an
organizational process
perspective should be
considered within which the
risk management processes
could operate. The processes
and procedures, along with
applicable tools to be used for
performing risk management
functions should be carefully
considered, established, and
well defined when implemented.
The risk management processes
described later in this guide
should be carefully tailored to
involve and meet the needs of
the organization’s internal
planning, assessment, project
controls, risk monitoring,
reporting, and decision-making
processes at the different levels
of risk management.”
12 3.2 “Increase the interaction and
communication between upper
management and functional
contributors, and to better
understand all types of project
risks, such as: political,
economic, social, and
technological, policy, program,
project, financial, resource-based,
health and safety, safeguards and
security, and operational.
Without this interaction,
identification of risks and the
communication and handling of
risks cannot be adequately
accomplished, or be well
understood.”
Section 2
“Increase the interaction and
communication between upper
management and functional
contributors, and to better
understand all types of project
risks, such as: political,
economic, social, and
technological, policy, program,
project, financial, resource-
based, climate change and
extreme weather, health and
safety, safeguards and security,
and operational. Without this
interaction, identification of
risks and the communication
and handling of risks cannot be
adequately accomplished, or be
well understood.”
12 3.3 “A complete responsibility
assignment matrix for risk
“The key roles, roles which
have a significant impact upon
Page Section Changed To
management roles and
responsibilities should be
included in the risk management
plan.”
the risk management of the
project, and responsibilities are
the highest level of project risk
authority and responsibility. A
complete responsibility
assignment matrix for risk
management roles and
responsibilities should be
included in the risk management
plan.”
13 3.3.3 “For non-M&O contracts, the
CPM manages risks under the
Contract Budget Base…”
“The CPM manages risks under
the Contract Budget Base…”
15 4.1 “Instead it is meant to
demonstrate when one should
initiate for the first time certain
process steps.”
“Instead, it is meant to
demonstrate when one should
initiate certain process steps for
the first time.”
19 4.3.1 Added to list. “EM Project Critical Decision
Assessment Tool (CDAT)
analyses.”
19 4.3.1 “Environmental considerations
such as seismic, wind and
flooding”
“Environmental considerations
such as seismic, climate change
and extreme weather (e.g.,
wind and flooding).”
25 Figure 3 Updated the chart format.
26 4.3.6.1.1 “However, there may be little or
no correlation between a risk’s
determinative impact and the
qualitative risk rating, so caution
with the lowest rated risks in the
qualitative analysis.”
“However, a risk’s qualitative
risk rating, does not necessarily
correlate with its determinative
impact. Therefore, one should
exercise caution with the lowest
rated risks in the qualitative
analysis.”
36 4.3.6.2.2 Added section and footnote. Integrating schedule and cost
risk, also known as joint cost
and schedule confidence level
(JCL) analysis, generates a
representation of the likelihood
a project will complete its scope
and achieve its key performance
parameters on time and within
budget. Conduct this analysis
with risks, prioritized by
likelihood of realization and
Page Section Changed To
impact, appearing in the risk
management plan and a fully
burdened resource-loaded
integrated master schedule with
uncertainties associated with
activities. The process uses
software tools that examine the
schedule and cost implications
of the hypothetical realization
of risks or manifestations of
uncertainty to generate an
integrated probability
distribution. The Association
for the Advancement of Cost
Engineering International
(AACE International)[1]
Recommended Practice (RP)
57R-09, Integrated Cost and
Schedule Risk Analysis Using
Risk Drivers and Monte Carlo
Simulation of a CPM Model,
provides a method for
simultaneously considering
schedule and cost risks. The
AACE RP 113R-20, Integrated
Cost and Schedule Risk
Analysis and Contingency
Determination Using Combined
Parametric and Expected Value
provides techniques to deal with
baselines using combined
methods of cost estimating.
Implement JCL on major
systems projects in preparation
for CD-2 and thereafter.
Section 3
[1] Reference
https://web.aacei.org/resources/publica
tions/recommended-practices to see
recommended practices (Cost for these
documents should be factored into
other direct costs).
38 4.3.6.4 Risk attitude, the position that can
be stated or unstated that the
organization holds towards risk,
is one factor that can influence
how risk is handled and how
Risk attitude, the explicitly stated
or unstated position that the
organization holds towards risk,
is one factor that can influence
how risk is handled and how
https://login-rsa.vdi.doe.gov/Citrix/StoreWeb/clients/HTML5Client/src/SessionWindow.html?launchid=1640873711174#_ftn1
https://login-rsa.vdi.doe.gov/Citrix/StoreWeb/clients/HTML5Client/src/SessionWindow.html?launchid=1640873711174#_ftnref1
https://web.aacei.org/resources/publications/recommended-practices
https://web.aacei.org/resources/publications/recommended-practices
Page Section Changed To
values are assigned, and should
be included in the analysis.
values are assigned and should
be included in the analysis.
39 4.3.6.5 Added. A parametric estimating model,
through mathematical cost
relationships, logically and
predictably correlates the
physical or functional
characteristics of a project with
its cost. When used in risk
analyses, some parametric
models relate cost growth to
risk drivers such as the level of
project scope development and
the technology readiness level.
AACE RP 42R-08 , Risk
Analysis and Contingency
Determination Using Parametric
Estimating, offers an approach
to estimating contingency, but
not MR, based on cost data
from similar completed
projects. Another AACE RP,
44R-08, Risk Analysis and
Contingency Determination
Using Expected Value, provides
a basis for generating inputs to
the methodology appearing in
AACE RP 42R-08. Use the
spreadsheet calculator included
in AACE RP 43R-08, Risk
Analysis and Contingency
Determination Using Parametric
Estimating – Example Models
as Applied for the Process
Industries, to make calculations
more efficient and transparent.
The calculator collects cost and
project definition level
information. The contingency
estimates produced following
this methodology best support
cost estimate ranges generated
prior to CD-0 and CD-1.
57 7.3 In establishing the PB when
contracts are in-place, the PB will
comprise the contractor’s price.
In establishing the PB when
contracts are in-place, the PB will
comprise the contractor’s price
(PMB plus MR plus fee) plus
contingency and any
Page Section Changed To
Government other direct costs
(see Figures 4 and 5 above).
7 Attachment 11 Added. An advantage of an integrated
cost and schedule risk model is
the ability to capture schedule
related costs impacts, such as
level-of-effort (LOE) support
activities that increase project
costs as schedule related risk
impacts delay or extend work
efforts. Integrated risk models
increase the flexibility of the
risk analysis and reduce the
amount of manual coordination
needed to model cost and
schedule risk impacts.
Project risks and the associated
cost and schedule impacts are
the primary inputs to the risk
model and are maintained
within the project’s risk register.
Figure A-4 depicts a conceptual
risk model showing typical
inputs and outputs.
8 Attachment 11 Added. When developing risk models,
care should be exercised to
assure the risk models are
developed using appropriate
performance baseline
information and project risk
assumptions.
Section 4
10 Attachment 11 Added. Integrated Schedule and Cost
Risk
Integrated schedule and cost
risk, also known as JCL
analysis, generates a
representation of the likelihood
a project will complete its scope
and achieve its key performance
parameters on time and within
budget. Conduct this analysis
with a prioritized risk
management plan and a fully
burdened resource-loaded
integrated master schedule with
uncertainties associated with
activities. The process uses
Page Section Changed To
software tools that examine the
schedule and cost implications
of the hypothetical realization
of risks or manifestations of
uncertainty to generate an
integrated probability
distribution.
AACE RP 57R-09, Integrated
Cost and Schedule Risk
Analysis Using Risk Drivers
and Monte Carlo Simulation of
a CPM Model, provides a
method for simultaneously
considering schedule and cost
risks. Implement JCL in
preparation for CD-2 and
thereafter on major systems
projects.
11 Attachment 11 Added. Parametric Estimating of
Contingency
AACE RP 42R-08, Risk
Analysis and Contingency
Determination Using Parametric
Estimating, offers an approach
to estimating contingency, but
not MR, based on cost data
from similar completed
projects. Another AACE RP,
44R-08, Risk Analysis and
Contingency Determination
Using Expected Value, provides
a basis for generating inputs to
the methodology appearing in
AACE RP 42R-08. Use the
spreadsheet calculator included
in AACE RP 43R-08, Risk
Analysis and Contingency
Determination Using Parametric
Estimating – Example Models
as Applied for the Process
Industries, to make calculations
more efficient and transparent.
The calculator collects cost and
project definition level
information. The contingency
estimates produced following
this methodology best support
Page Section Changed To
cost estimate ranges generated
prior to CD-0 and CD-1.
2 Attachment 12 project risks be realized that
delay the anticipated project
completion. Note that this differs
from contractor schedule reserve,
which cannot add time or
schedule duration to the
contracted end date.
The FPD may alternately
choose to apply the DOE
schedule contingency to the end
of milestones and/or the project
completion date to determine
the expected completion date
should project risks be realized
that delay the anticipated project
completion. Note that this
differs from contractor schedule
reserve, which cannot add time
or schedule duration to the
contracted end date.
4 - 12 Attachment 12 Added a new section to the
document.
The new section includes the
following headers:
- Quantitative
Contingency Analyses
- Cost and Schedule Risk
Models
- Cost Risk Model
- DOE Schedule Risk
Model
- Integrated Schedule and
Cost Risk
- Parametric Estimating of
Contingency
- Risk Model Outputs
- Updating Contingency
Analyses
1 Attachment 13 Added. Beyond the inputs proposed in
the Risk Management Guide,
the project schedules should
integrate the contractor and
DOE schedules to allow the use
of Monte Carlo simulation
software.
3 Attachment 15 Added. Joint Cost and Schedule
Confidence Level (JCL): “A
process that combines a
project's cost, schedule, and risk
into a complete picture. JCL is
not necessarily a specific
methodology . . . or a product
from a specific tool. The JCL
calculation includes
Page Section Changed To
consideration of the risk
associated with all elements,
regardless of whether or not
they are funded from . . .
appropriations or managed
outside of the project. A JCL
identifies the probability that a
given project or program cost
will be equal to or less than the
targeted cost AND that the
schedule will be equal to or less
than the targeted schedule date.”
Section 5
Appendix A Updated references to most
recent versions and updated
URLs.
Appendix A Added. AACE RP 42R-08, Risk
Analysis and Contingency
Determination Using Parametric
Estimating. AACE RP 43R-08,
Risk Analysis and Contingency
Determination Using Parametric
Estimating – Example Models
as Applied for the Process
Industries.
AACE RP, 44R-08, Risk
Analysis and Contingency
Determination Using Expected
Value.
AACE RP 57R-09, Integrated
Cost and Schedule Risk
Analysis Using Risk Drivers
and Monte Carlo Simulation of
a CPM Model.
DOE, Office of Management,
Sustainability Performance
Division, Vulnerability
Assessment and Resilience
Planning Guidance, September
2021
DOE, 2021 Climate Adaptation
and Resilience Plan, August 25,
2021
Page Section Changed To
EIA-748D, Earned Value
Management Systems, January
2019.
Appendix A Added to the “Checklist
References” list.
http://www.risk-management-
basics.com/risk-management-
checklists.shtml, Risk
Management Basics, March
2006.
http://www.wiredforgrowth.co
m/risk-tools/risk-
checklists/?cprofile=N, Wired
for Growth, 2008.
http://it.toolbox.com/blogs/enter
prise-solutions/risk-
management-checklist-22039,