U.S. Department of Energy ADMIN CHANGE
Washington, D.C.
Chg 1: 10-22-2015
SUBJECT: ADMINISTRATIVE CHANGE TO DOE G 413.3-10A, EARNED VALUE
MANAGEMENT SYSTEM (EVMS)
1. EXPLANATION OF CHANGES. These Administrative Changes are limited to changing
the Office of Primary Interest (OPI) to the Office of Project Management Oversight and
Assessments.
2. LOCATIONS OF CHANGES:
Page Paragraph Changed To
Title INITIATED BY:
Office of Management
INITATED BY:
Office of Project Management
Oversight & Assessments
1 2 Those topics are beyond the scope
of this guide; however, FPDs and
other DOE elements are
encouraged to contact the Office of
Engineering and Construction
Management (OECM) for
consultation.
Those topics are beyond the
scope of this guide; however,
FPDs and other DOE elements
are encouraged to contact the
Office of Project Management
Oversight & Assessments
(PMOA) for consultation.