Office of Science is Exempt from DOE Order 413.3B, Program and Project Management for the Acquisition of Capital Assets (SC)
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
Department of Energy
Office of Science
Washington, DC 20585
February 2, 2011
MEMORANDUM FO~~~ATE DIRECTORS
FROM: "W~~s~tKMAN
DIRECTOR, OFFICE OF SCIENCE
Office of the Director
SUBJECT: Office of Science is Exempt from DOE Order 413.3B, Program
and Project Management for the Acquisition of Capital Assets
DOE Order 413.3B, Program and Project Management for the Acquisition of Capital
Assets was approved by the Deputy Secretary of Energy on November 29, 2010. The
Order establishes new project management requirements including Critical Decisions
(CD) approval authorities. In addition, DOE Order 413.3B provides criteria that allow a
Program Secretarial Office to be exempt from its requirements.
The Office of Science (SC) currently satisfies all the criteria, and on January 19, 2011, the
Deputy Secretary of Energy approved the SC request for exemption (see attached
approval memorandum). The newly delegated SC Acquisition Executive authority and
SC project management requirements are outlined in the attached matrix. These
requirements are effective immediately and will remain in force until rescinded.
This exemption is a direct result of our past and current project performance. It provides
SC with significant benefits in overseeing our projects. Failure to retain this hard won
exemption would not only tarnish SC's reputation-it would place burdens on future
projects that would take precious time and resources away from delivering on our critical
science missions. Therefore, I want to underscore my expectation that you will continue
to work not just to maintain, but improve upon, the SC track record of project success.
If there are any questions, or further assistance is needed, please contact
Daniel R. Lehman, Director, Office of Project Assessment (SC-28).
Attachments
cc:
P. Dehmer, SC-2
G. Malosh, SC-3
J. Salmon, SC-4
K. Klausing, SC-41
® Printed with soy ink on recycled paper
Department of Energy
Office of Science
Washington, DC 20585
December 22,2010
EXEC-2010-017508
Office of the Director
MEMORANDUM FOR THE DEPUTY SECRETARY
THROUGH:
FROM:
SUBJECT:
)
STEVEN E. KOONIN _tA. t;:_
UNDER SECRETARY FOR SCIENC
~~~~
DIRECTOR, OFFICE OF SCIENCE
ACTION: Request Approval for Office of Science Exemption from
DOE Order 413.38, Program and Project Management for the
Acquisition of Capital Asset
ISSUE: The Office of Science (SC) requests exemption from DOE Order 413.38, based on
SC's satisfactorily meeting all criteria necessary for exemption set forth in the Order,
and the Office of Engineering and Construction Management's (OECM) validation of SC's
project management requirements, processes, and procedures.
BACKGROUND: DOE Order 413.38, Program and Project Management for the
Acquisition of Capital Assets, approved by the Deputy Secretary on November 29, 2010,
allows for Program Secretarial Offices (PSOs) to be excluded from the requ irements of
the Order.
DOE Order 413.38, Paragraph 3.c.(3) states that a PSO may be excluded from specific
requirements of the order if it meets the following criteria:
• Has an established Project Management Support Office (PMSO) with adequate
project management requirements, processes and procedures defined to enable
continued project success;
• Has an on-going active capital asset program, post Critical Decision-2 (CD-2}, of
over ten projects at any time during the current Fiscal Year (FY); and
• Has completed 90% of projects across a three-year rolling average, not
Section 2
exceeding more than 10% of the original scope and cost baseline approved at
CD-2 (for all capital asset projects with a Total Project Cost (TPC) greater than or
equal to $10 million).
® Printed with soy ink on recycled paper
The purpose of the exemption is to transfer Critical Decision approvals normally
reserved for authorities higher than the PSO to the PSO, and to allow activities typically
conducted by OCEM to be performed by the PSO's PMSO.
2
The Deputy Secretary must approve the PSO's exemption. The Deputy Secretary may
specify exceptions (e.g., retain high profile projects) when approving the exemption, and
may rescind any exemption if the PSO is unable to meet the exemption requirements
listed above or at any time at his/her discretion.
Within the DOE organization, SC is a designated PSO. SC currently satisfies all the
eligibility requirements for an exemption .
OECM validated that SC has adequate project management requirements, processes,
and procedures in place to enable continued project success and that are consistent
with the Acquisition Management System as delineated in the Order.
Therefore, having satisfied all requirements necessary, SC through this decision
memorandum, requests approval of the Deputy Secretary to be exempt from the
specific requirements of DOE Order 413.38.
As a condition of the exemption and as required by DOE Order 413.38, SC will continue
to:
• Report all projects into the Project Assessment and Reporting System (PARS II)
monthly;
• Submit all Critical Decision or equivalent documents to the Office of Engineering
and Construction Management (OECM); and
• Submit Performance Baseline Change Proposal approvals to OECM.
Also, OECM will lead Independent Cost Reviews and Independent Cost Estimates as
delineated in Appendix A, Tables 2.0 through 2.3.
A summary chart highlighting new authorities for project decisions enabled by the
exemption is attached.
OPTIONS: There are two distinct options: 1) Approve or 2) Disapprove.
Option #1, Approve Exemption Request. This option places the PSO (Office of Science)
under partial governance of DOE Order 413.38. It recognizes SC's sustained excellent
project performance and effective project management systems. The exemption
requires SC to report project progress; provide documentation necessary to support
Departmental-wide metrics; maintain auditable project records; meet obligations to
external stakeholders; and remain vigilant in its efforts to execute project successfully.
Option #2, Disapprove Exemption Request . This option places the PSO (Office of
Science) under complete governance of DOE Order 413.38.
RECOMMENDATION: Option# 1, approve this exemption request.
APPROVE: ~ DISAPPROVE: DATE: 1/19/2011
Attachment
CONCURRENCES: MA/I.Kolb- 1/12/2011
3
DRAFT--Summary of Major Requirements
1/10/11
TOTAL PROJECT COST (TPC)
$750M or more Less than $750M to
$400M
Less than $400M to
$100M
Less than $100M to
$50M*
Less than $50M* to
$20M
Less than $20M to
$10M**
REQUIREMENTS/APPROVAL Delegation Allowed
SC-1 Approves
SC-28 Reviews
SC-1 Approves
SC-28 Reviews
SC-1 Approves
SC-28 Reviews
SC-1 Approves
SC-28 Reviews
SC-1 Approves
SC-28 Reviews
SC-AD Approves
SC-28 Reviews
SC-1 Approves
SC-28 Reviews
SC-1 Approves
SC-28 Reviews
SC-2 Approves
SC-28 Reviews
SC-AD Approves
SC-28 Reviews
SC-AD Approves
SC-28 Reviews
SC-AD Approves
SC-28 Reviews
CD-0--APPROVE MISSION NEED S-2
(CD-1 to 4 delegated, see below)
SC-1 SC-1 SC-AD SC-AD SC-AD
CD-1--APPROVE ALTERNATIVE SELECTION
AND COST RANGE S-4 SC-1 SC-1 SC-AD SC-AD SC-AD
CD-2 --APPROVE PERFORMANCE BASELINE S-4 SC-1 SC-2 SC-AD SC-AD SC-AD
CD-3--APPROVE START OF CONSTRUCTION SC-1 SC-1 SC-2 SC-AD SC-AD SC-AD
CD-4--APPROVE START OF OPERATIONS OR
PROJECT COMPLETION SC-1 SC-1 SC-2 SC-AD SC-AD SC-AD
B
A
SE
LI
N
E
M
A
N
A
G
E-
M
EN
T
New Performance Baseline Approval S-4 SC-1 SC-2 SC-2 SC-2 SC-2
Prior to CD0, Approve Mission Need Statement
Prior to CD-1, Approve Acquisition Strategy
C
R
IT
IC
A
L
D
EC
IS
IO