Delegation of Acquisition Executive Authority for Capital Asset Projects at Small Sites (EM)
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
Department of En~rgy
Washington, DC 20585
February 25, 2011
MEMORANDUM FOR JACK R. CRAIG
DIRECTOR .
CONSOLIDATED BUSINESS CENTER
·'£i:;~ ~ FROM: INES R. TRIA Y ~ cf
ASSISTANT SEC TARY FOR .
SUBJECT:
ENVIRONMENTAL.MANAGEMENT
Delegation of Acquisition Executive Authority for Capital Asset
Projects at Small Sites
In accordance with the guidelines of Department of Energy (DOE) Order (0) 413.3B,
Program and Project·Management of the Acquisition of Capital Assets, I delegate .
Acquisition Executive (AE) Authority for all Environmental Management (EM) Capital
Asset Projects at the following sites with a Total Project Cost of less than $1OOM to you,
as Director, Consolidated Business Center (CBC), with the exception of Critical
Decision-0, "Approve Mission Need."
• West Valley Demonstration Project (WVDP)
• Separation Process Research Until (SPRU)
• Energy Technology Engineering Center {ETEC)
• Moab UMTRA Project
• Argonne National Laboratory (ANL)
• Brookhaven National Laboratory (BNL)
• Stanford Linear Accelerator Center (SLAC)
• Nevada National Security Site (N2S2)
• Los Alamos National Laboratory (LANL)
This. delegation must be specific to each capital asset project: You must demonstrate and
affirm the ability to perform all duties of an AE as identified in the DOE 0 413.3B. As ·
such, each site must have a robust project management system and a functioning project
management organization (including competent and certified Federal Project Directors
(FPD) as well as warranted Contracting Officers (CO)) that deliver acquisition quality,
result in seamless integration with the management of the site's EM portfolio, and
demonstrate due diligence and due process. AE authorities may not be delegated further.
This delegation will remain in force until superseded or rescinded.
As you execute your AE authorities, you must demonstrate within 120 days of the date of
this memorandum:
• A project management organization is in place to oversee contractor
activities and assure compliance with DOE'O 413.3B;
* Printed wllh soy Ink on recycled paper
• At the appropriate certification level, FPD are assigned to, formally
designated on, and fully empowered to direct EM capital. asset projects;
2
• Processes and procedures are in place to implement DOE 0 413.3B,
including a functioning acquisition advisory board that advises and
provides recommendations to you, as the AE, on the disposition of Critical
Decisions (CD), Performance Baseline (PB) deviations, proposed PB
changes, and associated modifications to or other actions taken on
impacted contracts;
• The process of reviewing and dispositioning CDs, PB deviations, and PB
changes is fully integrated with the procedures·of contract administration
su~h that potential contract modifications are coordinated with the CO,
who is solely authorized to execute such changes as specified in the
Federal Acquisition Regulation,. Part 1.602-1 (Authority);
• All affected contacts have been modified to iricorporate DOE 0 413.3B,
including the Contractor Requirements Document; and ,
• You have received a briefing on the changes in DOE 0 413.3B (refer to
briefing by Director, Office of Engineering and Construction
Management) ..
In support of this delegation, it is my expectation that all projects witr adhere to the
requirements of DOE 0 413.3B. The FPD must also assure 'accurate and current
information is reported in the Integrated Planning, AccOuntability, and Budgeting
System, the Project Assessment and Reporting System II, and the Monthly/Quarterly
Progress Reviews. Finally, copies of all AE actions taken at the site should be provided
to Mr. Lowell Ely, Dire~tor, Office of Project Assistance and Assurance. This rescinds
all previous delegation memorandums. ·
If you have any further questions, please contact Dae Y. Chung, Principal Deputy
Assistant Secretary for Envir~nmental Management at (202) 586-~216.