DOE P 226.1A, Department of Energy Oversight Policy
Functional areas: DOE Oversight, Defense Nuclear Facility Safety and Health Requirement, Safety
The Policy establishes a Department-wide oversight process to protect the public, workers, environment, and national security assets effectively through continuous improvement. Cancels DOE P 226.1. Canceled by DOE P 226.1B
Supersedes:
DOE P 226.1, Department of Energy Oversight Policy on May 25, 2007
Superseded By:
DOE P 226.1B, Department of Energy Oversight Policy on Apr 25, 2011
Version history and related documents
Superseded by
A newer version replaces this document.
- DOE P 226.1BDepartment of Energy Oversight Policy (Apr 25, 2011)
Supersedes
Earlier documents this one replaced.
- DOE P 226.1Department of Energy Oversight Policy (May 25, 2007)
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
U.S. Department of Energy POLICY
Washington, D.C. DOE P 226.1A
Approved: 5-25-07
SUBJECT: DEPARTMENT OF ENERGY OVERSIGHT POLICY
PURPOSE AND SCOPE
The purpose of this Policy is to establish a Department-wide oversight process to protect the
public, workers, environment, and national security assets effectively through continuous
improvement. As used in this Policy, any reference to DOE is also meant to include the National
Nuclear Security Administration (NNSA).
The scope of this Policy includes assurance systems implemented through contracts and by DOE
organizations that manage or operate on site; assurance systems implemented by DOE line
management (both Headquarters and field elements);1 and DOE independent oversight2
organizations. This Policy covers such operational aspects as environment, safety, and health;
safeguards and security; cyber security; and emergency management.
This Policy cancels and supersedes DOE P 226.1, Department of Energy Oversight Policy, dated
6-10-05.
TERMINOLOGY
“Assurance systems” encompass all aspects of the processes and activities designed to identify
deficiencies and opportunities for improvement, report deficiencies to the responsible managers,
complete corrective actions, and share in lessons learned effectively across all aspects of
operation.
“DOE Oversight” encompasses activities performed by DOE organizations to determine whether
Federal and contractor programs and management systems, including assurance and oversight
systems are performing effectively and/or complying with DOE requirements. Oversight
programs include operational awareness activities, onsite reviews, assessments, self-assessments,
performance evaluations, and other activities that involve evaluation of contractor organizations
and Federal organizations that manage or operate DOE sites, facilities, or operations.
“Site programs” protect the public, workers, environment, and national security interests or
support essential mission activities. Site programs specifically include environment, safety, and
health; safeguards and security; cyber security; and emergency management programs.
“Site management systems” are required management systems that provide the framework for a
set of related site programs. Site management systems specifically include Integrated Safety
1DOE line management refers to the management chain with responsibility for the site. This chain typically extends from the
responsible site organization (e.g., site office or field office) to the responsible program office or Under Secretary and ultimately
to the Deputy Secretary and Secretary of Energy.
2Independent oversight refers exclusively to oversight by DOE Headquarters organizations that do not have line management
responsibility for the activity.
AVAILABLE ONLINE AT: INITIATED BY:
www.directives.doe.gov Office of Health, Safety and Security
HQ
FIELD
ELEMENTS
CONTRACTORS
2 DOE P 226.1A
5-25-07
Management, Integrated Safeguards and Security Management, and Quality Assurance
Programs.
POLICY
It is DOE policy to protect the public, workers, environment, and national security assets and to
perform its operations effectively. To meet this goal, all DOE organizations must implement an
assurance system that ensures compliance with applicable requirements, pursues excellence
through continuous improvement, provides for timely identification and correction of deficient
conditions, and verifies the effectiveness of completed corrective actions. Additionally, DOE
oversight programs must determine whether programs, management systems, and assurance
systems comply with requirements and are effectively implemented.
Section 2
It is DOE policy to implement assurance systems and oversight programs that include four
essential elements:
• a comprehensive and rigorous assurance system implemented at all sites;
• DOE field element line management oversight processes, such as inspections, reviews,
surveillances, surveys, operational awareness, and walkthroughs, that evaluate programs
and management systems and the validity of the site assurance system;
• DOE Headquarters line management oversight processes that are focused primarily on
the DOE field elements. To the extent necessary, DOE Headquarters line management
also looks at contractor activities to evaluate the implementation and effectiveness of
field element line management oversight; and
• independent oversight processes that are performed by DOE organizations that do not
have line management responsibility for the management of the activity and thus provide
an independent perspective for senior management on the effectiveness of programs and
activities at all organizational levels (Headquarters, field, and contractor).
The four elements are designed to work
DOEDOE as a comprehensive system to provide
Oversight Model Oversight Model assurance that DOE activities are safe
and secure. Oversight of high
consequence activities, such as high
hazard nuclear operations, requires
additional rigor, such as instituting
Central Technical Authorities for core
nuclear safety functions. The assurance
system puts responsibility and
accountability at the appropriate
organizational level (both Federal and
contractor) to implement comprehensive
and rigorous processes that ensure
adequate protection of the public, workers, environment, and national security assets and
INDEPENDENT
OVERSIGHT
HQ
FIELD
ELEMENTS
CONTRACTORS
INDEPENDENT
OVERSIGHT
3 DOE P 226.1A
5-25-07
effective and efficient operations. The DOE Headquarters and field element line management
oversight processes put responsibility and accountability on line management to determine the
effectiveness, on an ongoing and regular basis, of site operations and to ensure timely corrective
actions if performance does not meet expectations. The independent oversight processes
determine whether Headquarters, field, and contractor line management are effectively
implementing their responsibilities and provide an additional basis for credibility throughout the
system. These assurance systems and oversight activities will be tailored to meet the needs and
unique differences of each site or activity. Consistent with quality assurance objectives,
thorough, rigorous assessments and corrective actions are required to ensure performance and
quality improvement.
ATTRIBUTES OF EFFECTIVE OVERSIGHT
An effective oversight process incorporates the following attributes into the four essential
elements of oversight as appropriate.
Program Plan
Documented program plans need to identify the program areas to be reviewed, the periodicity of
reviews, the reviews necessary to maintain the baseline oversight program, the qualifications of
review personnel, and the source of review criteria. Documented program plans need to describe
the various oversight methods used, how they are used, and how the results of the various
methods are integrated and considered as a whole to give an accurate oversight picture.
Continuous Improvement
Section 3
Assurance systems and oversight processes will identify ways to make programs more effective
and efficient through improved performance and report such opportunities to line managers for
their consideration. Line managers at all levels are responsible for using the results of DOE line
and independent oversight processes and assurance systems. These results are to be used to
make informed decisions about corrective actions that will improve the effectiveness and
efficiency of their programs and operations and about the acceptability of residual risks. The use
of external, nationally recognized experts should be considered to carry out independent risk and
vulnerability studies and to validate that contractor management systems meet applicable
standards. DOE sites and DOE line management must have effective processes for
communicating issues up the management chain to senior management using a graded approach
that considers hazards and risks. The processes must provide sufficient technical basis to allow
managers to make informed decisions. Processes for resolving disputes about oversight findings
and other significant issues shall also be implemented and include provisions for independent
technical reviews of significant issues.
Requirements and Performance Objectives
DOE oversight programs and assurance systems will evaluate performance against requirements
and performance objectives, which may include laws, regulations, national standards, DOE
directives, DOE-approved plans and program documents (e.g., security plans, authorization basis
documents, and quality assurance plans), site-specific procedures/manuals, criteria review and
4 DOE P 226.1A
5-25-07
approach documents, other contractually mandated requirements, and contractual performance
objectives. Requirements and performance objectives are established and interpreted through
approved processes so that they are relevant to the site and mission.
Personnel Competence
Personnel responsible for managing and performing assurance and oversight functions will
possess experience, knowledge, skills, and abilities commensurate with their responsibilities.
Line managers are responsible for ensuring that their personnel with oversight responsibilities
meet applicable qualifications standards. Continuing training and professional development
activities are encouraged to supplement individual experience and provide a means to maintain
awareness of changes and advances in the various fields of expertise.
Baseline Oversight Program and Priorities
Line management is responsible and accountable for establishing and implementing a baseline
oversight program that provides for an adequate assessment of programs, management systems,
and assurance systems. Clear and unambiguous lines of authority and responsibility for
performing line management oversight functions will be established and maintained. Line
management will provide its oversight processes with sufficient resources and access to conduct
an effective oversight program. Site assurance systems and DOE oversight processes will be
tailored to be effective and efficient and will take into account hazards and risks (including risks
associated with potentially hazardous activities and risks to DOE missions including schedule,
cost, and scope uncertainties). Oversight priorities are to be based on a systematic analysis of
hazards, risks, and past performance of organizations, programs, and facilities, including
previous assessment results. Higher hazard or risk activities (e.g., facilities with a higher nuclear
material attractiveness level) and less mature programs will be assessed more frequently and/or
in more depth. The scope and results of reviews by external regulators (e.g., the Environmental
Protection Agency) and organizations (e.g., the Defense Nuclear Facilities Safety Board) are
important factors in determining oversight priorities but are not a substitute for effective line
management oversight.
Section 4
DOE Headquarters and field element line management regularly assess site assurance systems to
determine the appropriate level of overlap and redundancy of DOE Headquarters and field
element line management oversight. Accordingly, DOE line management organizations may
increase their frequency and/or depth based on performance deficiencies or events or may
decrease the frequency and/or depth of line management oversight assessments to reflect
sustained effective site performance. Although external organization reviews and the
effectiveness of assurance systems are considered in determining DOE line management
oversight priorities and the scope and frequency of oversight activities, DOE line management
must always maintain an adequate minimum baseline oversight program that enables DOE line
management to understand the hazards and risks of activities.
Performance Indicators and Measures
Performance indicators and measures will be used as one mechanism to help line management
identify adverse trends and promote improvements. This data is considered in a variety of
DOE P 226.1A 5 (and 6)
5-25-07
management decisions, such as allocating resources, establishing goals, identifying performance
trends, identifying potential problems, and applying lessons learned and good practices. Site
performance criteria will focus on results and system-based metrics to drive improvements in site
programs and management systems at DOE sites.
Self-Assessments of Line Management Functions
Line management must perform self-assessments of its activities, including its oversight
activities and activities necessary to support site assurance and mission activities. Headquarters,
field element, and contractor management organizations are responsible for establishing effective
management assessments and line management oversight processes and to address shortcomings,
identified through self-assessments, in their oversight programs.
Federal Responsibility and Accountability for Activities
DOE line management will require that contracts adequately delineate contractor responsibilities
for programs, management systems, and assurance programs. Contractors will be responsible
under their contracts to provide these assurances DOE line management and contractors may
perform some assessments jointly to increase efficiency and promote common understanding of
processes and results. However, DOE line management is responsible and accountable for
understanding and accepting the hazards and risks associated with activities. To accomplish this,
DOE has the right and responsibility to perform oversight at the level necessary to understand
the hazards and risks, to ensure compliance with applicable requirements, to pursue excellence
through continuous improvement, to ensure timely identification and correction of deficient
conditions, and to verify the effectiveness of completed corrective actions.
BY ORDER OF THE SECRETARY OF ENERGY
CLAY SELL
Deputy Secretary