To establish the Department of Energy (DOE) requirements for granting facility approvals prior to permitting safeguards and security interests on the premises and the conduct of on-site security and/or nuclear material surveys of facilities with safeguards and security interests. Cancels DOE O 5630.7 and DOE O 5634.1. Canceled by DOE 5634.1B.
Superseded By:
Version history and related documents
Superseded by
A newer version replaces this document.
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
I
1 . 0I u.s. Department of Energy
<)
ORDER
00.
j C Washington, D.C.
I
DOE 5634.1A
I
2-3-88
SUBJECT: FACILITY APPROVALS, SECURITY SURVEYS, AND NUCLEAR MATERIALS SURVEYS
j
1
1. PURPOSE. To establish the Department of Energy (DOE) requirements
for granting facility approvals prior to permitting safeguards and
security interests on the premises and the conduct of on-site
security and/or nuclear material surveys of facilities with
safeguards and security interests.
I ·
2. CANCELLATION. DOE 5630.7, CONTROL AND ACCOUNTABILITY OF NUCLEAR
MATERIALS SURVEYS, of 7-8-81, and DOE 5634.1, SECURITY SURVEY AND
FACILITY APPROVAL, of 5-2-83.
3. SCOPE. The provisions of this Order apply to all Departmental
Elements and contractors performing work for the Department as
provided by law and/or contract and implemented by the appropriate , contracting officer.
~ '·'··· 4. BACKGROUND. DOE shall assure that all facilities eligible to
. ;0·
.,
receive, process, reproduce, store, transmit, or handle classified
matter or special nuclear material (SNM) have been granted facility
approval prior to permitting access to such matter or material.
5. POLICY. DOE special nuclear materials (SNM) and classified
interests shall not be permitted on premises occupied by the DOE
and/or its contractors, subcontractors, consultants, or other
organizations performing work for the DOE until facility approval is
granted. Activities involving the possession, use, and production
of nuclear materials and classified matter shall be afforded
appropriate levels of protection to prevent unacceptable adverse , impact to national security or the health and safety of the public.
6. CONCEPT OF OPERATIONS. DOEl s policy for approving facilities and
conducting surveys to ensure satisfactory safeguards and security of
DOE interests apply equally to all Departmental elements,
contractors, subcontractors and consultants. However, this policy
is implemented at a wide range of facilities, and site- and program
specific characteristics must be considered to assure that
Departmental safeguards and security interests are provided
appropriate and cost-effective protection. In order to allow for
DISTRIBUTION: INITIATED BY:
All Departmental Elements Office of Safeouards and Security
2
o
DOE 5634.1A
2-3-88
J
effective implementation of Departmental policy on a site-specific
or program-specific basis, an exception mechanism is provided that
allow facility approval and survey programs to be tailored to
address these specific requirements. The exception procedures are
outlined in paragraph 6e.
a. Information and requirements regarding cover operations are no
longer provided in this Order. The nature of these sensitive
classified interests require specialized instructions which
shall be provided by DP-34 on an as needed basis.
r
b. Initial facility approval shall be based upon a determination
that satisfactory safeguards and security can be afforded the
DOE interests. Such determination shall be based upon initial
and periodic on-site nuclear materials and/or security surveys
conducted by DOE safeguards and security personnel, and upon
written security and material control and accountability plans
approved by the cognizant field organization or, in the case of
Headquarters, by the Director of Safeguards and Security (DP
34).
Section 2
c. The DOE will determine whether, and to what extent, any
contractors performing or proposing to perform work which will
involve access to classified information or significant
quantities of SNM (as defined in 10 CFR 710), are foreign owned,
controlled, or influenced. In addition, the DOE shall determine
on a case-by-case basis whether any degree of foreign ownership,
control, or influence might constitute a basis for the
compromise of classified information, unauthorized access to or
use of SNM, or other related adverse impact on the national
security. To assist in these determinations DOE will use
information provided by the contractor in accordance with
Department of Energy Acquisition Regulation 952.204-73, "Foreign
Ownership, Control, or Influence Over Contractor
(Representation)." The contractor shall also execute a
certificate which indicates that the information, provided in
accordance with the DEAR clause identified above, is accurate, \
complete, and correct.
d. On-site nuclear materials and/or security surveys shall be
conducted initially and periodically thereafter, at intervals
specified in this Order, to ensure satisfactory safeguards and
security of DOE interests. Surveys of each site for which a
Master Safeguards and Security Agreement has been written shall
be conducted in such a manner as to be consistent with the
Master Safeguards and Security Agreement requirements.
e. Alternate means of providing adequate facility approvals and
security and/or nuclear materials surveys may be proposed to
meet a specific requirement of this Order. Exceptions to the
Order, developed by the Heads of Field Elements, include the
following:
o o
DOE 5634.1A 3 (and 4)
2-3-88
(1) Safeguards and security interests covered by the classified
threat guidance issued by DP-1 and Headquarters program
organizations. These exceptions should be submitted in
writing to DP-34 for review and concurrence prior to
implementation. Written records of such exception should
be included in appropriate field organizations safeguards
and security policy documents and MSSAs.
(2) Safeguards and security interests not covered by the
classified threat guidance issued by DP-1. These
exceptions should be submitted to and approved by the Heads
of Field Elements. Written records of such exceptions
should be included in appropriate field organization
safeguards and security policy documents.
7. REFERENCE. DOE 5630. Safeguards and Security Program for Department
of Energy Operations, and other Facility Approval, Security Surveys
and Nuclear Materials Surveys references cited in Attachment 1 of
this Order.
8. DEFINITIONS. Facility Approval, Security Survey and Nuclear
Materials Survey definitions are appended to this Order at
Attachment 2.
BY ORDER OF THE SECRETARY OF ENERGY:
LAWRENCE F. DAVENPORT
Assistant Secretary
Management and Administration
r.·····.
i \..I
I
~
o 0
J
o o
DOE 5634.1A Attachment 1
2-3-88 Page 1
REFERENC1S
1. DOE 5630.13, MASTER SAFEGUARDS AND SECURITY AGREEMENT, of
2-3-88, which provides guidance on the establishment of
basic safeguards and security requirements.
2. DOE 5632 Series, PHYSICAL PROTECTION OF SECURITY INTERESTS
ORDERS, which prescribe policies, objectives, responsibilities
and authorities, requirements, and standards for the physical
protection of DOE security interests.
3. DOE 5633.3, CONTROL AND ACCOUNTABILITY OF NUCLEAR MATERIALS,
of 2-3-88, which prescribes responsibilities and authorities
for control and accountability of DOE nuclear materials.
Section 3
4. DOE 5670.1, MANAGEMENT AND CONTROL OF FOREIGN INTELLIGENCE, of
8-22-86, which establishes policy for the management of, and
assigns responsibilities and authorities for, foreign
intelligence activities of DOE.
5. ATOMIC ENERGY ACT of 1954, as amended, which describes
requirements for the protection of classified information
relating to atomic energy.
6. TITLE 10 CFR 710, "Criteria and Procedures for Determining
Eligibility for Access to Classified Matter or Significant
Quantities of Special Nuclear Material,tI of 1-1-82, which
establishes criteria and procedures for determining
eligibility for access to classified matter or significant
quantities of SNM.
7. EXECUTIVE ORDER 10450, Security ReqUirements for Government
Employment, of 4-27-53, which establishes criteria for
investigating, and granting authorization for access to
classified National Security Information.
8. EXECUTIVE ORDER 10865, Safeguarding Classified Information
within Industry, of 2-24-60, which established criteria and
procedures for the protection of classified National Security
Information within industry.
9. EXECUTIVE ORDER 12356, National Security Information, of 4-6
82, which establishes government-wide policy for safeguarding
classified National Security Information.
10. Department of Energy Acquisition Regulation (DEAR) 904.70,
FOREIGN OWNERSHIP, CONTROL, OR INFLUENCE OVER CONTRACTORS,
which prescribes DOE policies and procedures regarding foreign
ownership, control, or influence over contractors.
Attachment 1 DOE 5634.1A
Page 2 2-3-8a
11. Department of Energy Acquisition Regulation (DEAR) 952.204-2,
"Security Requirements," of 4-84, which outlines contract
clause requirements for contractors and subcontractors whose
performance involves, or is likely to involve, classified
information.
12. DEAR 952.204-73, "Foreign Ownership, Control, or Influence
over Contractor (Representation)," contract provision.
13. DEAR 952.204-74, of 4-84, "Foreign Ownership, Control, or r
Influence over Contractor," contract clause.
14. DOE Safeguards and Security Standards and Criteria of 4-21-87, •which provide baseline guidance to Heads of Departmental
Elements, Headquarters program managers, field office
managers, and the managers of facilities for planning and
developing protection operations for classified and sensitive
matter and the protection of life and property.
15. DOE Espionage Threat Policy Statement of 3-30-87, which
establishes baseline hostile intelligence threat guidance for
DOE's sophisticated technologies and nuclear weapons research,
production, and testing facilities.
16. DOE GENERIC THREAT GUIDANCE, of 1-31-83, which establishes
baseline threat guidance for DOE nuclear programs and
facilities.
17. DOE PROCEDURAL GUIDE, "Security Standards for Sensitive
Compartmented Information and Facilties," of 1986, which
establishes policy, procedures and responsibilities for
establishing and maintaining the security integrity of
Sensitive Compartmented Information Facilities.
18. Title 10 CFR 50, Domestic Licensing of productli?n an~ Uti lfi zatld·on .
Facilities, of 3-3-75, which provides for the lcenslng 0 pro uct lon
and utilization facilities.
19. Title 10 CFR 1016, Safeguarding of Restricted uate,.ot ~-flU-tltj, .WhtiCdh
establishes criteria and procedures for the protectlon 0 res rlC e
data.
http:uate,.ot
o o
DOE S634.1A Attachment 2
2-3-88 Page 1 c
DEFINITIONS
Section 4
1. Access Permit. A permit, issued by the DOE, authorizing
access by the named permittee to Restricted Data applicable to
the civilian uses of atomic energy.
2. Accountability. That part of the safeguards and security
program which encompasses the measurement and inventory
verification systems and records and reports to account for, nuclear materials.
3. Classified Interest. Classified information or material
possessed by DOE, a DOE contractor, or any other facility• under DOE jurisdiction. This may include SNM owned by DOE.
4. Facility. An educational institution, manufacturing plant,
laboratory, office, building (or complex of buildings
contiguously located on the same site) protected as one unit
and used by the Department or its contractors for the
performance of work under the jurisdiction of the Department.
5. Facility Approval. A determination that a facility is
eligible to receive, produce, use, or store classified matter,
SNM, or other DOE property. This approval determination is
limited to a safeguards and security perspective only.
6. Facility Data and Approval Record. A standard DOE form which
is used to register a security facility on the Master Facility
Register and to record approvals, changes, and deletions of
security facilities and interests, the dates of surveys, and
Headquarters review and analysis of survey reports.
7. Facility Register. An index of security facilities under the
administrative or survey responsibility of a field
organization.
8. Field Organization. DOE Operations Offices, Energy Technology
Centers, Federal Energy Regulatory Commission Regional
Offices, and Power Administrations.
o o
Attachment 2 DOE 5634.1A
Page 2 2- 3-88
9. Finding. A separate and distinct situation in a surveyed
organization that exists in violation of directives.
"Finding" situations shall be either brought into compliance
with DOE Orders, or granted an approval based on an exception,
or accepted program departure. Each "findingll shall be
referenced to a specific directive and assigned a unique
identification number used in conjunction with a specific
corrective action proposed and implemented by the field
organization or contractor.
10. Foreign Ownership, Control, or Influence.
a. Foreign ownership, control, or influence exists when a DOE
contractor performing classified work has an institutional
or personal relationship with any of the following foreign
interests, which are defined as:
(1) Foreign government or foreign government agency;
(2) Any form of business enterprise organized under the
laws of any country other than the United States or
its possession; or
(3) Any form of business enterprise organized or
incorporated under the laws of the U.S., or a State
or other jurisdiction of the U.S., which is owned,
controlled, or influenced by a foreign government,
agency, firm, corporation, or person who is not a
citizen or U.S. national.
b. A contractor is considered to be under foreign ownership,
control, or influence when the degree of interest as
defined above is such that a reasonable basis exists for
concluding that compromise of classified information or
significant quantity of special nuclear material, as
defined in 10 CFR 710, may result.
11. Graded Safeguards. A system designed to provide varying
degrees of physical protection, accountability, and material
control to different types, quantities, physical forms, and
chemical and isotopic compositions of nuclear materials
consistent with the risks associated with malevolent acts and
varying levels of attractiveness and convenience to potential
adversaries.
Section 5
12. Heads of Headquarters Elements. This term refers to the
Office of the Secretary, Secretarial Officers and DOE Staff
Operations.
J
,
..
o o
DOE 5634.1A Attachment 2
~~M Page 3
13. Malevolent Act. An illegal action, or an action that is
committed with the intent of causing wrongful harm.
14. Master Facility Register. Central record index maintained by
DP-34 of all security facilities under the administrative
jurisdiction of Departmental Elements.
15. Nuclear Materials. All materials so designated by the , Secretary. Presently, these materials are: depleted uranium,
enriched uranium, plutonium-242, americium-241, americium-243,
curium, berkelium, californium, plutonium 239-241, lithium-6,
uranium-233, normal uranium, neptunium-237, plutonium-238,
• deuterium, tritium, and thorium.
16. Nuclear Materials Accounting. The part of the safeguards
program applied to nuclear materials and their associated
records to:
(a) Maintain knowledge of the quantities of nuclear
materials;
c
(b) Verify the existence of nuclear materials through
physical inventories;
(c) Promptly detect malevolent acts involving nuclear
material;
(d) Help investigate and resolve apparent losses of
nuclear materials.
17. Nuclear Materials Control. The part of the safeguards program
applied to nuclear material and personnel and equipment
handling nuclear material to:
(a) Govern and maintain vigilance over nuclear material
activities;
(b) promptly verify the existence of nuclear material;
(c) Promptly detect malevolent acts involving nuclear
material;
(d) Help investigate and resolve apparent losses of
nuclear material. Nuclear materials control
interfaces with the nuclear materials accounting and
physical protection parts of the safeguards program.
-
IC
o
Attachment 2 DOE 5634.1A
Page 4 2-3-88
J
18. Nuclear Materials Survey. A comprehensive examination and
evaluation of the effectiveness of the control and
accountability of nuclear materials at DOE facilities to meet
a spectrum of threats.
19. Physical Protection (Physical Security). The application of
methods for preventing malevolent acts against DOE safeguards
and security interests. detecting such acts as they occur. and
responding to such acts. Available methods include, for ,
example. couriers, guards. vaults, and alarm systems. They do
not include such things as seals. in-line instruments, or area
monitors of the recording type, as distinguished from alarms.
20. Property Protection Facility. A facility other than a
security facility.
21. Responsible Organization. The DOE organization responsible
for implementation and oversight of Safeguards and Security
requirements at a DOE facility. including approval of security
plans and resolution of deficiencies other than those which
are specific to another DOE organization's security interests.
If there is more than one DOE organization with security
interests at a facility, the organization which is responsible
for the programs involving the highest level of security
interest is normally the responsible office. However, this
responsibility may, by mutual agreement of the offices
involved, be accepted by an office which does not have the
highest level of security interest but a greater scope
interest, as with a long term or traditional interest.
When more than two offices have interests at the same facility
and when there is no overriding or traditional interest the
Section 6
organization assigned geographic responsibility in Attachment
111-1 of this Order should be assigned as the responsible
organization.
22. Safeguards. A collective term that comprises those measures
designed to guard against malevolent acts involving material
such as source or special nuclear material. Safeguards
includes providing timely or delayed indication of possible
malevolent acts or credible assurance that the malevolent acts
have not occurred. The measures may include, but are not
limited to:
(a) The maintenance and verification of records of
receipt, shipments, and periodic inventories;
(b) Physical protection;
J
j
i
o o
DOE 5634.1A Attachment 2
2-3-88 Page 5c
(c) Personnel security;
(d) Inspection of nuclear facilities to provide
that malevolent acts have not occurred;
assurance
(e) Physical methods to detect or measure
materials; or
loss of
(f) Federal statues.
23. Safeguards and Security Interest. Any of the following that
may require special protection: classified matter, SNM, and
associated facilities; security shipments; critical
facilities; secure communications centers; Sensitive
Compartmented Information Facilities;
processing centers, or other systems that include classified
information or Departmental property.
24. Safeguards and Security Survey. The security survey and/or
nuclear materials survey, as appropriate. The security survey
and nuclear materials survey may be performed independently or
as one integrated survey. Integrated safeguards and security
survey refers to the combined security and nuclear material
survey.
25. Security. Any and all measures taken to guard against theft,
diversion, sabotage, and espionage.
26. Security, Physical. See Physical Protection.
27. Security Facility. Any facility which has been approved by
DOE for generating, receiving, using, proceSSing, storing,
reproducing, transmitting, destroying, or handling classified
matter and/or SNM.
28. Security Interest. Any of the following which requires
special protection: classified matter; special nuclear
material; security shipments; secure communications centers;
Sensitive Compartmented Information Facilities; automatic data
processing centers; or other systems that include classified
information or Departmental property.
29. Security Survey. On-site examination of the devices,
equipment, personnel, and procedures employed at a facility to
safeguard SNM, classified matter, and/or DOE property.
I ·
,
!
I
!j C···"'·
i
I
I
1
I
I
Attachment 2 DOE 5634.1A
Page 6 2-3-88
30. Sensitive Compartmented Information. All classified
information and materials bearing intelligence community
special access controls formally limiting access and
dissemination. This does not include Restricted Data, as
defined in the Atomic Energy Act of 1954, as amended.
31. Sensitive Compartmented Information Facility. An accredited
area, room, group of rooms, or installation where sensitive
compartmented information may be stored, used, and/or
electronically processed.
32. Significant System Alarm. Any facility safeguards and
security capability that provides a communicable indication of
a malevolent act involving radiological or industrial
sabotage, espionage, or the theft or diversion of classified
matter or nuclear materials which could be used to construct
an improvised nuclear device, a nuclear device, or
unauthorized detonation of a weapon or test device.
33. Significant Vulnerability. The loss of, or discovered way to
Section 7
bypass, an essential safeguards and security system component
or set of components for which there is no effective backup.
34. Suggestion. Information a field organization provides as
guidance to a facility's management to identify potential
program enhancements associated with survey observations.
J
35. Surveying Organization. The DOE safeguards and security
organization which has responsibility for conducting a
security and/or nuclear materials survey of a DOE facility.
36. SNM. See Special Nuclear Material.
37. Source Material. Uranium, thorium, or any other material
determined, pursuant to the proviSions of Section 61 of the
Atomic Energy Act of 1954, as amended, to be source material;
or ores containing one or more of the foregoing materials in
such concentration as may be determined by regulation.
38. Special Nuclear Material. Plutonium, uranium enriched in the
isotope 233 or in the isotope 235, and any other material
which, pursuant to the provisions of Section 51 of the Atomic
Energy Act of 1954, as amended, has been determined to be
special nuclear material, but which does not include source
material; or it also includes any material artificially
enriched by any of the foregoing, not including source
material.
39. Special Nuclear Material Facility. Any facility which has
been approved by DOE to possess SNM.
J
o•DOE 5634.1A ;
2-3-88
TABLE OF CONTENTS
CHAPTER I: RESPONSIBILITIES AND AUTHORITIES
G
1. Director of Safeguards and Security •••••••••••••••••••••••• I-l
2. Heads of Headquarters Elements ••••••••••••••••••••••••••••• I-2
Heads of Field Elements ••••••.•••••••••••••.••••••••••••••• I-3
• 4. Director of Computer Services and Telecommunications
3.
Management ••••••••••••••••••••••••••••••.•••••••••••••••• 1-6
5. Director of Procurement and Assistance Management •••••••••• I-6
CHAPTER II: FACILITY IMPORTANCE RATINGS AND APPROVALS
1. Facility Importance Ratings ••••••••••••••••••••••••••••••• ll-l
a. Purpose .......•......................................• I1-1
b. Criteria•••••••••••••••••••••••••••••••••••••••••••••• 11-1
(1) Class "Au •••••••••••••••••••••••••••••••••••••••• II-l
(2) Class "B" ••••••••••••.••••••••••••••••••••••••••• 11-2
(3) Class tlCt' •..••.•.•..••.••..••.•.•.•••••••.••...•• II-2
(4) Class "AP" ••••••••••••••••••••••••••••••••••••••• 11-2
(5) Class "PP" ••••••••••••••••••••••••••••••••••••••• 11-2
c. Facility Register ••••••••••••••••••••••••••••••••••••• 11-3
2. Facility Approval ••••••••••••••••••••••••••••••••••••••••• 11-3
a. Purpose ••••••••••••••••••••••••••••••••••••••••••••••• 11-3
b. Accepting Existing DOE Facility Approval •••••••••••••• II-4
c. Granting New Facility Approval •••••••••••••••••••••••• II-4
d. Verification•••••••••••••••••••••••••••••••••••••••••• 11-7
e. Terminating Facility Approval ••••••••••••••••••••••••• II-7
3. Facility Data and Approval Record ••••••••••••••••••••••••• II-8
a. Purpose ••••••••••••••••••••••••••••••••••••••••••••••• 11-8
b. Submission of the Facility Data and Approval Record ••• II-8
c. Attachment to the Facility Data and Approval Record ••• II-8
d. Nonsubmission of a Facility Data and Approval
Record .............•...••••....•......••..••..•..••• I1-9
e. Distribution•.•••••••••••••••••••••••••••••••••••••••• 11-9
ATTACHMENT II-I
DOE F 5600.2 Facility Data and Approval Record ••••••••••• II-ll
CHAPTER III: GENERAL SURVEY REQUIREMENTS
1. Purpose •.•••..••••.••••••••.•••••.•••••••••••••.••••••••• 111-1
Section 8
2. Types of Surveys ..•••.•.••••••••••••••••••.•••••••••••••• III-l
a. Initial Survey••..••••••••••.•••••••.•••••••••••••••• III-l
b. Periodic Survey•••••••••••••••••••••••••••••••••••••• III-l
c. Special Survey•.•.••••.••••.••••••••••••••••••••••••• III-l
d. Termination Survey••••••••••••••••••••••••••••••••••• Ill-l
e. Shipment Survey •••••••••••••••••••••••••••••••••••••• III-l
3. Coverage••••••••••••••••••••••••••••••••••••••••••••••••• 111-1
a. Initial and Periodic Surveys ••••••••••••••••••••••••• III-l
b. Special Surveys •••••••••••••••••••••••••••••••••••••• III-l
ii
o
DOE 5634.1A
2-3-88 J
c. Termination Surveys •••••••••••.••••.•••••••••.•••.••• III-2
d. Shipment Surveys .••••••.••••.••••••.•••••••••••.••••• III-2
4. Pre-Survey Planning and Scheduling•.••.•••••••••••••••••• III-2
5. Coordination of Nuclear Materials and Security Surveys ••• III-3
6. Survey Documentation and Reports ••••••••••••••••.•••••••• III-3
7. Distribution••••••.••.•.••••.••.•.••.•.•.••••.••••.•••.•. 111-4
ATTACHMENT 111-1
DOE F 5634.2 Safeguards and Security Survey Report •.••••• lII-5
CHAPTER IV: SECURITY SURVEYS
1. Purpose ................................................... IV-l
2. Geographical Responsibilities and Exemptions ••••••••••••• IV-l
3. Frequency ...•....•....•..•.•.......................•...... IV-l
4. Survey Report Content ••••••••••••••••••••••••••••••••••••• IV-2
5. Training and Qualifications •.••••••••••••••••••••••••••••• IV-3
6. Compliance Segment ...........•..•...•.••.....•...•..•..•.• IV-3
7. Performance Segment ............•.........•...........•.•.• IV-3
ATTACHMENT IV-l Geographical Areas for Surveys ••••••.••• IV-5
CHAPTER V: NUCLEAR MATERIALS SURVEYS
1. Purpose .................................................... V-l
2. Frequency ......................•.........•.................V-l
3. Survey Report Content ...•.••..••..••.•..•....•••.•...••••.. V-l
4. Training and Qualifications ••••••••.••••••••••••••••••••••• V-3
5. Camp1i ance Segment ..•......................................V-3
6. Performance Segment ........................................V-3
CHAPTER VI: SURVEY RATINGS AND FOLLOW-UP ACTIONS
1. Rating System.•......•..•......•..•........•..............VI-l
d. Ratings ...............................................VI-l
(1) Satisfactory .....•......•........................VI-l
(2) Marginally Satisfactory ••••••••••••••••••••••••••VI-l
(3) Unsatisfactory .....•.............................VI-1
2. Identified Protection Needs ••••••••••••••••••••••••••••••• VI-l
3. Use of the "Marginally Satisfactory" Rating ...............VI-l
4. Corrective Actions and Survey Ratings ••••••••••.••••••••••VI-2
5. Deficiencies in Documentation••••••••••••••••••••••••••.••VI-2
6. Compliance•••.•••••••••••••••••••.•••••••••••••••••••••••• VI-2
7. Performance...................•.........•.................VI-2
8. Survey Follow-up and Corrective Actions ••••••.•.•••••••••. VI-2
•
J
o o
ODE 5634.1A I-I
2- 3-88
CHAPTER I
RESPONSIBILITIES AND AUTHORITIES
1. THE DIRECTOR OF SAFEGUARDS AND SECURITY (DP-34) shall:
a. Develop for review and approval by the Assistant Secretary
for Defense Programs (DP-l), policies, standards, and
procedures for DOE nuclear materials and security surveys
and facility approvals • •
b. Review and evaluate the degree of adherence by field
elements to DOE policies and procedures relating to the
content and conduct of surveys.
Section 9
c. Review nuclear materials and security survey reports
submitted by each field element.
d. Advise cognizant Headquarters elements, DP-l, and the
Office of Inspector General (IG-l), of any significant
problems identified as a result of reviews of field element
activities and nuclear materials and security survey
reports, and recommend appropriate measures to correct
noted deficiencies.
e. Review and concur on exceptions to this Order, as
appropriate, prior to implementation.
f. Provide policy guidance to all Departmental Elements in the
implementation of the survey and facility approval system.
g. Oversee surveys for Headquarters-administered contracts;
furnish the surveying organization complete information
concerning Headquarters interests when survey coverage is
requested; initiate necessary action to implement
suggestions resulting from surveys of Headquarters
facilities; and notify the surveying organization, when
applicable, of such implementations.
h. Conduct surveys of facilities for which Headquarters is the
surveying organization and transmit copies of survey
reports to responsible Heads of Field Elements and
appropriate Headquarters program organizations.
i. Assure that surveys examine the adequacy and effectiveness
of the protective measures afforded all interests.
j. Assure findings resulting from security and/or nuclear
materials surveys are documented.
k. Maintain the Master Facility Register, including the
recording of: 0"''''',
f
o
1-2 DOE 5634.1A
2-3-88 J
(I) Facility register changes in a timely and accurate
manner; and
(2) At a minimum, the facility's name, location,
importance rating, classified mailing address,
security officer's name, and the identificaton of
responsible and surveying organizations.
1. Maintain a file of facilities either under Headquarters
administered contracts or for which Headquarters is the
surveying organization.
m. Approve physical and technical security criteria for
sensitive compartmented information facilities prior to
initiation of new construction and ensure that appropriate
surveys are performed prior to occupancy.
n. Ensure that, as a prerequisite for the granting of a
facility approval, each contractor has executed a
certificate which includes a statement of the nature and
degree of foreign ownership, control, or influence, or a
statement that there is no foreign involvement.
o. ~:~~~~a~~:~;m~;~~~r~~~~~d~~rb~e~~~~~r~!~~e~~~e~;s~~ and, in . ~
coordination with the Office of General Counsel (GC-l) and ~
Director of Procurement and Assistance Management (MA-4),
determine whether the degree of foreign ownership, control,
or influence may constitute a reasonable basis for
compromise of classified information, unauthorized access
to or use of special nuclear material, or other adverse
impact on the national security.
p. For facilities under Headquarters-administered contracts:
(I) Grant facility approvals;
(2) Approve security plans, when required;
(3) Terminate facility approvals;
(4) Prepare and distribute facility data and approval
records; and
(5) Ensure the conduct of initial and periodic surveys.
2. HEADS OF HEADQUARTERS ELEMENTS shall:
a. For facilities under Headquarters-administered contracts,
request DP-34 to:
(I) Determine the adequacy of safeguards and security, J
grant facility approvals; and
o•DOE 5634.1A 1-3
2-3-88o
Section 10
(2) Terminate the safeguards and security interests, upon
completion of the classified work and removal of
special nuclear material (SNM) or classified matter.
b. For facilities of field elements under their programmatic
or administrative jurisdiction, take action to ensure
acceptable safeguards and security. Such action may
include recommending that the Head of the Field Element
curtail or suspend operations when such operations would
result in an immediate and unacceptable risk to national c security or public health and safety.
c. Recommend to Heads of Field Elements the curtailment or
• suspension of operations when such operations would result
in an immediate and unacceptable risk to national security
or public health and safety.
d. Ensure that contracting officers incorporate contract and
solicitation provisions implementing the requirements of
this Order in new or existing contracts which involve SNM
or classified information.
c
e. Ensure that corrective actions required as a result of
nuclear materials and/or security surveys of facilities
under their administrative jurisdiction are implemented and
that the Director, DP-34 and other responsible Heads of
Field Elements, if appropriate, are promptly notified of
the implementing action.
f. Identify to the contracting officer those procurements
which involve classified information and that require the
security provisions of DEAR 952.204-2.
3. HEADS OF FIELD ELEMENTS shall:
a. Establish written delegations of authorities and
responsibilities for the administration of the facility
approval and nuclear materials and security survey
programs ••
b. Ensure that nuclear materials and/or security surveys are
conducted as specified in this Order and in accordance with
safeguards and security interests under their
administrative jurisdiction. Ensure prompt submission of
survey reports to the Director, DP-34, responsible Heads of
Field Elements, and the appropriate Headquarters elements
and that such survey reports are properly classified.
c. Ensure that procurement request originators (organizations
initiating a requirement on DOE F 4200.33) notify
contracting officers when acquisitions involve safeguards
and security concerns.
1-4 DOE 5634.1A
2-3-88
d. Ensure that prior to the initiation of any action involving
nuclear materials with a license-exempt (as defined in 10
CFR Part 50) contractor, appropriate contractual coverage
is in place to permit the implementation of this Order with
regard to the contractor's classified matter and/or nuclear
materials activities.
e. Develop procedures for the administration and conduct of
nuclear materials and security surveys in accordance with
this Order.
f. Ensure that prior to an initial nuclear materials and/or
security survey, the Manager of the Operations Office or
Head of Headquarters Elements executes a security agreement
that includes a statement of the degree of foreign
ownership, control, or influence or a statement of no
foreign involvement. When foreign ownership, control, or
influence is established, notify DP-34 and forward the
certification statement and all supporting foreign ownership,
control, or influence information, including the review and
rationale for acceptance or non acceptance for final adjudication.
g. In coordination with GC-1 and DP-34, restrict or deny award
of contract in cases where foreign ownership, control, or
influence is such that:
Section 11
(1) A reasonable basis exists for concluding that
compromise of classified information, unauthorized
access to or use of SNM, or other adverse impact on
the national security may result; and
(2) The foreign ownership, control, or influence cannot be
satisfactorily avoided or mitigated.
h. Provide sufficient resources for the survey programs to
support professional, administrative, technical, and
clerical staffing requirements, equipment and materials,
logistics requirements, and training and development.
i. Ensure that corrective action{s) is taken for findings
disclosed during nuclear materials and security surveys and
notify DP-34 and other responsible Heads of Field Elements
of the action(s), as appropriate.
j. Take such action, as may be appropriate, to ensure
acceptable safeguards and security, including curtailment
or suspension of operations when such operation would
result in an immediate and unacceptable risk to national
security or public health and safety.
k. Ensure that contracting officers incorporate contract and
solicitation provisions implementing the requirements of
this Order in new or existing contracts which involve
classified matter and/or nuclear material activities.
o o
DOE 5634.1A
2-3-88
1.
m.
n.
G
o.
p.
q.
r.
s.
t.
G
1-5
Ensure that surveys examine the adequacy and effectiveness
of the protective measures afforded:
(1) Secure communications centers;
(2) Automatic data processing centers and remote
interrogation points; and
(3) Sensitive compartmented information facilities.
Approve each new or updated facility security and nuclear
materials control and accountability plan and submit copies
to DP-34 for incorporation into the Master Facility
Register. Also submit copies to the surveying organization
if different from the responsible organization.
Conduct surveys of selected security shipments for which
they are responsible, take corrective actions resulting
from these surveys, and submit copies of such reports to
DP-34 for incorporation in the Master Facility Register.
Grant facility approval for facilities under their
administrative jurisdiction.
Prepare and submit facility data approval records to DP-34,
as required.
Assign importance ratings to facilities based on criteria
contained in this Order.
Maintain a register of all security and nuclear materials
facilities for which they are either the responsible or
surveying organization including recording:
(1) Facility register changes in a timely and accurate
manner; and
(2) At a minimum, the facility1s name, its importance
rating, location and classified mailing address, and
the security officer1s name.
Wh~n site or program considerations make strict
implementation of this Order not feasible, develop an
alternate approach using the exception procedure cited in
paragraph 6e;
Develop detailed facility approval, suspension, and
termination procedures to accommodate a need to retain
possession of classified matter or nuclear materials at
facilities under their jurisdiction.
o
1-6 DOE 5634.1A
2-3-88
4. THE DIRECTOR OF COMPUTER SERVICES AND TELECOMMUNICATIONS
MANAGEMENT (MA-25) shall conduct COMSEC audits and surveys and
TEMPEST inspections of secure communications centers and crypto
facilities.
Section 12
5. DIRECTOR OF PROCUREMENT AND ASSISTANCE MANAGEMENT (MA-4), shall,
in coordination with GC-l and DP-34, maintain solicitation and
contract articles implementing this Order and procedures to
protect DOE contractual arrangements from foreign ownership,
control, or influence. where these could constitute a
reasonable basis for concluding that the compromise of
classified information, unauthorized access to or use of SNM,
or other related adverse actions could impact on the national
security.
o o
DOE 5634.1A 11-1
c 2- 3-88
CHAPTER II
FACILITY IMPORTANCE RATINGS, APPROVALS, AND RECORDS
1. FACILITY IMPORTANCE RATINGS.
a. Purpose. Importance ratings assigned to security interests
provide a means of identifying the relative importance of
such facilities and interests on facility registers and the
Master Facility Register. The responsible DOE organization
shall assure that all facilities eligible to receive,
process, reproduce, store, transmit, destroy, or use SNM or
classified matter (including SNM owned by DOE) have been
granted facility approval prior to permitting classified
matter or SNM on the premises.
b. Criteria. Facility importance ratings are assigned using
the following criteria:
(1) Class IIA" facility importance ratings are assigned
those facilities which are:
C
(a) Judged by Heads of Field Elements to be engaged
in administrative activities considered to be
essential to the direction and continuity of the
overall DOE nuclear weapons program;
(b) Engaged in research and development, manufacture,
production, assembly, or storage of nuclear
weapons or weapon assemblies;
(c) Engaged in research and development, manufacture,
production, assembly, or operation of military
reactors;
(d) Engaged in major research and development in
uranium enrichment or operation of major uranium
enrichment facilities;
(e) Involved in research and development, manufacture
or production, and assembly of non-nuclear weapon
components, assemblies, and parts essential to
the weapons or military reactors programs;
(f) Receiving, handling, and storing Top Secret
documents (exclusive of keying material for
secure communications) over an extended period;
or
(g) Possessors of Category I quantities of SNM owned
G by DOE.
(2) Class 118" facility importance ratings are assigned to
the following facilities:
II-2 DOE 5634.1A
2-3-88 J
(a) Possessing security interests other than the type
categorized for Class "A" facilities and which
handle and store Secret weapon data documents or
Secret research and development reports;
(b) Other than the type categorized for Class "A"
facilities, in the uranium enrichment program;
(c) Possessing Category II quantities of SNM owned by
DOE;
(d) DOE national laboratories with security interests
other than the type categorized for Class "A"
facilities; or
(e) Emergency operations centers (except those
unmanned, which are Class "CII facil ities).
(3) Class "C" facil ity importance ratings are assigned to
facilities which are:
(a) Engaged in manufacturing, research and
development, administrative or consultant
activities, including machine and specialty
shops, automatic data processing, printing and
photographic work, and design engineering where
the security interests are limited in scope;
(b) Possessors of Categories III and IV quantities of
SNM;
(c) Established for classified bid negotiations or
quotations;
Section 13
(d) Authorized to retain classified matter (except
SNM) other than that noted under paragraphs
Ib(2)(a) and (2)(b) above, after completion or
other aqreement; or
(e) Federal records centers holding DOE security
interests.
(4) Class "AP" (Access Permit) facility importance ratings
are assigned to those facilities at which restricted
data is received, originated, or stored under an
access permit.
(5) Class IIpp ll (Property Protection) facility importance
ratings are assigned to those facilities at which a
special standard of protection must be applied when
significant monetary value, DOE program continuity,
national security considerations, or protection of the
o o
DOE 5634.1A 11-3
~..
2-3-88
~
public health and safety constitutes an important DOE
responsibility. Basic considerations include physical
protection to prevent or deter acts of arson, civil
disorders, riots, sabotage, terrorism, vandalism, and
theft or destruction of DOE property and facilities.
c. Facility Register. The responsible DOE field element and
the surveying office, if not the same, shall maintain a
facility register on those facilities as follows for which
it has responsibility:
(1) The facility register:
(a) Accurately reflects facilities with Class A, B,
C, property protection, and access permit
facility importance ratings.
(b) At a minimum, reflects the facility's name, its
importance rating, location and classified
mailing address, security officer's name, and
identifies the responsible and surveying
organizations.
(c) Is controlled appropriate to its contents.
(2) Changes shall be timely and properly coordinated with
the responsible DOE organization, or surveying
organization if different.
(3) Responsible and surveying organizations shall confirm
the accuracy of Master Facility Register maintained at
Headquarters and that it reflects established
facilities and security interests under their
jurisdiction, via prompt submission of accurate
facility data and approval records (DOE F 5600.2). A
copy of the facility data and approval record is
provided by Attachment II-I.
2. FACILITY APPROVAL.
a. Purpose. To ensure that all facilities eligible to
receive, process, reproduce, store, transmit, use, or
destroy, SNM or classified matter, have been granted
facility approval, based upon a validated satisfactory
safeguards and security system, prior to permitting
classified matter or classified and unclassified SNM on the
premises. The requirements for establishing facility
approvals are outlined below.
o o
11-4 DOE 5634.1A
2-3-88 J
b. Accepting Existing DOE Facility Approval. The organization
seeking to establish a classified interest shall check the
Master Facility Register to determine whether the location
already has DOE facility approval. If already approved,
the responsible organization may accept the existing DOE
facility approval, provided:
(1) The existing safeguards and security program at the
facility accommodates the new DOE interest; and
(2) The responsible organization determines that, on the
basis of the latest survey report, the existing
safeguards and security program is compatible with the
level of the new interest.
Additional requirements shall be established and completed
prior to the initiation of the security interest when the
existing safeguards and security program cannot meet the
requirements of the added DOE interest. These additional
requirements may include the conduct of vulnerability
analyses and validation exercises and shall be documented
Section 14
in approved security and/or Nuclear Material Control and
Accountability plans. As appropriate, the existing MSSA,
and security and material control and accountabiltiy plans
shall be revised to reflect the new or added interest. J
c. Granting New Facility Approval.
(1) Approval of a new facility or interest at a DOE
facility, it's contractors, subcontractors,
consultants, or access permittees. The following
conditions shall be in effect prior to approval:
(a) When SNM is present, all facilities subject to
facility approval shall have DOE approved site
specific security and material control and
accountabilty plans and an established Reporting
Identification Symbol (RIS) for Nuclear Materials
Management and Safeguards System reporting.
(b) For SNM, approval is based upon an initial
security survey and material control and
accountabiltiy survey, both with a satisfactory
composite rating.
(c) For classified information, approval is based on
an initial survey report, conducted by
geographical survey office, with a satisfactory
composite rating.
(d) For those security interests covered under . .~
facility MSSAs which are to be protected in a ,..,
graded fashion, the facility shall have completed
a vulnerability analyses of the proposed security
o o
DOE 5634.1A 11-5
2-3-88 c interest. The facility shall have this analysis
available for review during the survey.
(e) The date of the nuclear materials and security
survey and site-specific security/material
control and accountability plan upon which the
granting of facility approval is based shall not
be more than 12 months prior to the granting of
facility approval.
(f) When the level of classified information is
raised from Confidential to Secret or Top Secret,
or the category of SNM holdings is raised from
Category III to Category II or I, facility
approval at the higher level shall be based upon
a survey with a satisfactory composite rating.
(g) In addition to the above requirements, facility
approval for access permittees is based on a
review of the access permittee's written
statement of its procedures for the safeguarding
of Restricted Data and for the security education
of its employees consistent with the requirements
of 10 CFR Part 1016, Safeguarding of Restricted
Data.
(h) Access authorizations shall be in place at the
responsible DOE organization for persons included
in a new interest.
I
~ (i) Adequate classification guidance pertaining to
the new security interest will be available to
assure protection of the interest.
I (2) Accepting an existing U.S. Government agency facility
approval for work at one of it's contractors when a
I
!
« DOE facility approval does not exist.
I
! (a) Work remains under the programmatic cognizance of
DOE, however, security survey and oversight isi . ceded to the other U.S. Government agency.
Whenever practicable, a DOE security facilityI approval shall be established. However,
accepting another U.S. Government agency facility
approval for work under DOE cognizance may be
considered when:I
1 The interest is short term or of minor
J
t significance to the Department;
J
2 A security facility approval by anotherIO~" agency already exists; ,j
I
o
II-6 DOE 5634.1A
2-3-88
J3 It is not economically prudent for the
responsible or another field organization to
complete the facility approval and survey
requirements; and
4 T,le interest does not involve SNM or access
to restricted data.
Section 15
(b) Facility approval is based upon an existing U.S.
Government agency facility clearance at the
Confidential or Secret classification level and
provided that:
1 The U.S. Government agency facility
clearance encompasses the DOE classified
interest and the last surveyor inspection
report is noted as Satisfactory in those
areas which could affect the DOE interest.
2 The U.S. Government agency cognizant
security office furnishes to the responsible
DOE security office copies of its periodic
inspection reports or periodic memoranda
covering the DOE classified interest, citing
that a satisfactory survey was conducted.
3 The U.S. Government agency cognizant
security office agrees that it will not
cancel the facility clearance without prior
notification to the DOE security office
requesting security support.
4 All employees granted access to DOE
classified information have, as a minimum,
U.S. Government security clearances based on
a National Agency check.
5 Requirements identified in paragraph
2c(2)(a)1 through 2c(2)(a)~ above are
documented in a letter or memorandum of
agreement between the DOE responsible
security office and the U.S. Government
cognizant security office prior to the
establishment of a security interest.
(c) If the foregOing provisions cannot be met or when
SNM or DOE Top Secret, or Secret, or Confidential
Restricted Data is involved, facility approval is
based upon the provisions df paragraph 2c(1), page I1-4.
(d) When an existing U.S. Government agency cleared J
facility also has a DOE facility approval, the .
latter is used, when practicable, instead of the .
other U.S. Government agency facility clearances.
o o
DOE 5634.IA 11-7
2-3-88 c
d. Verification. Verification of capability of other U.S.
Government agencies and their contractors to protect
classified information for reference or use in work not
under DOE cognizance is as follows:
(1) Approval to transmit classified information shall be
based upon a written assurance from the Government
agency that DOE classified matter in its possession or
in the possession of its contractors, subcontractors,
or consultants will be afforded physical protection
and safeguards in accordance with Executive Order
10865, IISafeguarding Classified Information Within
Industry,lI as amended, Executive Order 12356,
"National Security Information," and its implementing
Information Security Oversight Office directive; and
that the mandatory personnel clearance requirements of
the Atomic Energy Act of 1954, as amended, pertaining
to access to restricted data, be met.
(2) When an agreement between DOE and another Government
agency specifically limits the dissemination of
certain categories of DOE classified information
within that agency e.g., restricted data, the
responsible DOE organization shall request the agency,
on execution of the agreement, to furnish a statement
of its procedures to ensure such limitation.
e. Terminating Facility Approval.
(1) When a facility has completed its activities involving
SNM or classified matter, the responsible organization
assures destruction or return of matter or material
returned to DOE custody through a termination survey
or by correspondence that includes the following:
I .,
I (a) Security termination statements;
(b) Written certification of nonpossession of
• classified matter or SNM;
(c) Cancellation of personnel clearances or access
authorizations which are no longer needed;
Section 16
(d) Discontinuance of physical security and material
control and accountabiltiy measures; and
(e) Preparation of a DOE F 5600.2, Attachment II-I,
cancelling facility approval.
c (2) A certificate of possession and periodic surveys are
required if the facility is authorized to retain
classified matter after termination of a contract or
agreement. The responsible DOE organization shall:
11-8 DOE 5634.1A
2-3-88
(a) Maintain appropriate documentation to support
receipts of destruction or certificates of
nonpossess;on.
(b) Establish guidelines for terminating facility
approval and coordinating termination activities
with appropriate contracting, program, security,
and safeguards organizations.
3. FACILITY DATA AND APPROVAL RECORD.
a. Purpose. To register pertinent facility information on the
Master Facility Register which must be in agreement.
Prompt submission of Facility Data and Approval Records and
accuracy of reported information are essential to the
continued integrity of the system.
b. Submission of the Facility Data and Approval Record. A
Facility Data and Approval Record, DOE F 5600.2, is
submitted to DP-34 by the responsible organization when:
(1) Granting initial facility approval;
(2) Accepting existing facility approval for an additional .' .~
interest; ~
(3) There is a Significant change in a registered facility
or interest within a facility (e.g., a change in name,
address, facility importance rating, responsible
organization, classified mailing address, contract or
purchase order number, classification, Restricted Data
authorization, or nature or scope of work);
(4) Facility approval for a registered facility or
interest is terminated;
(5) Interests are surveyed for DOE by DOD or other
Government agencies; or
(6) When SNM is to be placed in the facility.
c. Attachment to the Facility Data and Approval Records. When
sUbmitting facility data and approval records, attach a
copy of the following:
(1) Initial survey reports to the facility data and
approval record granting facility approval;
(2) Report of survey in memorandum form and pertinent
correspondence, when applicable, to the facility data
and approval record granting facility approval; and
• •
DOE 5634.lA 11-9 (and 11-10)
2-3-88
o (3) Termination survey report, if conducted, to the
Facility Data and Approval Record terminating facility
approval.
d. Nonsubm;ssion of a Facility Data and Approval Record.
Nonsubmission of an Facility Data and Approval Record
increases the risk that an interest will not be encompassed
by the normal safeguards and security administration
expected at a cleared facility and may be missed during the
normal oversight provided by a periodic or termination
survey. However, after appropriate consideration, a
Facility Data and Approval Record need not be submitted for
the following:
(1) An organization holding a contract with a facility
executes a purchase order or contract amendment for
additional work or material similar to that registered
under the contract, unless such purchase order or
amendment requires substantial changes in existing
security or nuclear material control and
accountability programs.
(2) An invitation to bid tendered by a field organization
is consonant with the interest(s) previously
registered by that organization.o e. Distribution. The organization preparing the Facility Data
Section 17
and Approval Record shall forward the original and two
copies to DP-34 which will make appropriate distribution to
other Departmental Elements having a safeguards and
security interest.
o o
DOE F 6600:2 DOE 5634.1A Attachment 11-1
(Formerly DP-80) 2-3-88 Page 11-11 (and 11-12)
111-81)
U.S. DEPARTMENT OF ENERGY
fACILITY DATA AND
.APPROVAL RECORD
NO. CM-66-99
1. FACI LlTY NAME AND ADDRESS CITY STATE ZIP CODE
T. A. James and Associates, Inc.
8330 S. Jefferson Rd. Any town Illinois 60699
2. CLASSIFIED MAILING ADDRESS 3. TYPE FACILITY
T. A. James and Associates
4. REASON FOR APPROVAL CHANGEP.O. Box 2278
IKJ Add FacilitY 0 Change Mailing Address Any town , Illinios 60699-2278 o Add Interest 0 Change Shipping Address
o Delete FacilitY 0 Change Facility LocationUSS REGISTERED OR CERTIFIED }ffiIL ONLY o Delete Interest 0 Change FacilitY Interest
o Other (describe): 0 Change Survey Office
o Change Responsible Office
6. IMPORTANCE RATING
Other
OA o B mC OPP o AP 0
5. CLASSIFIED SHIPPING ADDRESS
DNA 7. SECUR ITY OF F I CER (name and telephone number)
Valentino F. Antonio
10. CONTRACT P.O. or A.P. NO(s):
Various Contracts
11. OTHER SECURITY INTERESTS:
o Computer
o Secure Comm. Systems
o Cover
o Other _____________
8. OFFICES INVOLVED
Responsible Field Office
CH
12. HIGHEST CLASSIFICATION OF
Documents Material
SINSI DNA
13. SNM CATEGORY:
DNA 10 110 1110
14. BRIEF DESCRIPTION OF SECURITY INTEREST
T. A. James and Associates TAJA is an engineering firm specializing in the design and
evaluation of high security protection systems. TAJA is performing work for CH
relating to safeguards and security systems at Northeast·- :;ational Laboratory and
Midwest National Laboratory.
ji ' 15. BASIS FOR FACILITY APPROVAL:
!
Periodic security survey conducted by CH.
16. DISTR IBUTION (Item to be filled in by Division of
Security. Haedquarters)
c
17. PREPARED B DATE
John Doe
4,1988Safeg'uard
18. APPROVED By.~rield)
Thomas W. Ha
January 4, 1988Security Branch, SSD
19. RECORDED (Division of Sscurity. H8IIdqusrters) DATE
THIS REPORT AMENDS, SUPERSEDES OR DELETES FDAR NO. CH-88-992/'l5/86
o o
DOE 5634. IA 111-1
2-3-88
CHAPTER III
GENERAL SURVEY REQUIREMENTS
1. PURPOSE. To provide the basis for evaluating the adequacy and
effectiveness of safeguards and security programs and the
protection afforded DOE safeguards and security interests.
2. TYPES OF SURVEYS.
a. Initial Survey. An on-site examination of a facility prior
to granting facility approval.
b. Periodic Survey. An on-site examination of a facility
conducted at scheduled intervals.
c. Special Survey. An on-site examination of a facility
conducted for a specific purpose.
d. Termination Survey. An on-site examination of a facility
conducted when the safeguards and security interests are
removed from a facility or the contractor is changed for a
facility, or to assure proper disposition of nuclear
material and close out of records.
o e. Shipment Survey. An examination of protection afforded
security interests during shipment.
3. COVERAGE.
a. Initial and periodic surveys cover the protection afforded
DOE safeguards and security interests within a facility,
including an evaluation of the adequacy and effectiveness
of material control and accountability (MC&A) and security
programs and a thorough examination of policies and
procedures to ensure compliance/performance with
appropriate safeguards and security directives and
agreements. All facilities are subject to the compliance
and performance segments of surveys, as described in
Chapters IV and V.
Section 18
b. Special surveys evaluate the following:
(1) Existing protection for additional activities;
(2) Need for changes in material control and
accountability and security procedures and measures
due to changing conditions; and
(3) New material control and accountabilty and security
measures taken as a result of findings identified
under a previous survey(s).
• •
I II-2 DOE 5634.1A
2-3-88
c. Termination surveys evaluate actions taken to ensure
termination of safeguards and security interests, execution
of an appropriate security termination statement, and
submission of a certificate of possession or nonpossession,
as appropriate. Termination of facility approvals for
Class "A" facilities, facilities possessing classified
material, and/or SNM, require an on-site termination
survey. For other facilities, termination may be by survey
or correspondence.
d. Shipment surveys provide a basis for evaluating the
adequacy of protection afforded DOE classified matter or
SNM during shipment. Shipments which move between sites by
rail, truck, air, or ship are subject to survey based on an
approved security plan unless the shipment is made via a
commercial carrier(s) licensed by the Nuclear Regulatory
Commission (NRC). Movements of SNM between security areas
at the same site shall be surveyed during the security
survey of the site protection system. Each type of
security shipment shall be surveyed initially and at least
once every 12 months thereafter by the organization having
administrative jurisdiction over the shipment. Shipment
survey reports shall provide sufficient detail to enable a
proper evaluation of the report and its findings.
4. PRE-SURVEY PLANNING AND SCHEDULING. Certain activities should
be accomplished prior to the conduct of a security or nuclear
materials survey. These are normally done by the surveying
organization, the responsible organization (if different from
the surveying), the facility being surveyed, and DP-34. The
following activities are necessary:
a. Determine the extent of, and establish procedures for
reviewing, exceptions and other program departures.
b. Review files for relevant information, issues, and topics
to include in the survey. Such files include those
pertaining to: previous surveys, security and MC&A plans,
exceptions, and correspondence.
c. Define the scope of the survey by identifying the program
areas to be inspected, the methodology, and the resources
to be used. The scope should allow for review of areas of
concern that may arise during the survey process.
d. Coordinate all planned survey activities in advance with
parties involved in advance and establish communications
channels. Such coordination should specifically include
advance planning and agreed participation in a pre-survey
briefing.
e. Schedule the survey to allow prioritization of and changes .'~
to survey coverage of facilities. ~
~
i
I
1;;
~ o o
DOE 5634.1A 111-3j
2- 3-88
Ie 5. COORDINATION OF NUCLEAR MATERIALS AND SECURITY SURVEYS.
a. Security and nuclear materials surveys may be conducted
simultaneously or separately. When performed separately, the I surveying organization shall prepare an agreement outlining the
I
: responsibility of each survey that include the following:
i
I
i
(1) Assessing system performance against applicable threats;
I
(2) Evaluating different components of the safeguards and
security system; andI
Section 19
I (3) Rating items on Headquarters-approved survey report forms.
(See Attachment 111-1.)I .
b. When nuclear materials and security surveys are conducted
separately at Class "A" and "8" facilities, they should be
performed within a 2 month period.
6. SURVEY DOCUMENTATION AND REPORTS.
c
a. The survey report shall describe the state of the safeguards and
security program. The report shall reflect the ratings on
Headquarters-approved survey report forms as well as the
performance ratings based upon exercises, where appropriate. As
locally determined, work papers shall support the contents of the
survey report.
b. The narrative portion of the survey report shall outline
strengths and weaknesses, correlate the results from the
compliance and performance (where required), survey segments, and
discuss both compliance and performance ratings. The report
shall explain in detail the factors responsible for the
assignment of a less than Satisfactory rating.
c. Findings shall be identified and correlated with items on the
survey report forms approved by DP-34. The terms "findings" and
"suggestions" may be used in the survey report. The term
"finding" shall be used to refer to deficiencies, or concerns
reached during the survey. The term "suggestion" may be used to
refer to non-mandatory potential program enhancements for
observations cited in the survey report.
d. Survey results shall be validated by discussion, observations, or
exercises during the survey process to ensure accuracy.
e. As determined locally, survey work papers pertaining to findings
not fully documented in the survey report should be retained, as
a minimum, until the next survey is completed.
o
111-4 DOE 5634.1A
2-3-88
f. Survey observations of conditions in facility operations or
systems which may adversely impact the health and safety of
employees and/or the public shall be reported expeditiously to
the facility's management and the responsible organization's
environmental, safety, and health organization for follow-up
action.
g. Survey reports for Class "PP" facilities and terminations may be
in memoranda form.
h. Findings shall be documented and monitored until resolved.
Quarterly reporting on unresolved findings shall be made by the
responsible organization to DP-34. The first quarterly report
shall be issued not later than 90 days after receiving written
corrective action information from the surveyed facility.
7. DISTRIBUTION.
a. Within 60 working days after the completion of the survey, the
surveying organization(s) shall forward one copy of each survey
report to the responsible organization, two copies to DP-34,
copies to appropriate Headquarters elements, and one copy to the
surveyed organization, as determined locally.
b. Heads of Field Elements or DP-34 (for Headquarters), may make ;~
internal distribution of survey reports, as appropriate. ~
J
3 copies copy
1 copy
1 copy
o •
o
DOE 5634.1A Attachment 111-1
2- 3-88 I II- 5
DOE Form 56342 (148.
(~1.0"'1 U. S. DEPARTMENT OF ENERGY
SAFEGUARDS AND SECURITY SURVEY REPORT
Responsible Field Office: Other Offlce(s) with Interests
SAl'i SNR
Distribution Date:
December 10, 1987
1 copy
1 copy
1 c n
•
Facility Name, Reporting Identihcation Symbol (RIS), and Address
Bates Midtown Division (CES)
909 Prince Avenue
Hidtown, OH 45201
Facility Security Officer: Ronald Limrnins
TelephoneNumber (804) 312-5566
Contract. Pllrchase Order, InQuiry or Access Permil Number
Section 20
Various DOE contracts and Purchase Orders
FaCility Importance Rating (check one):
o Class A [l Class 8 0 Class C 0 Property Protection 0
Other Interests
o Computer o Access Permit
Date of Survey:
November 11-14, 1987 riI Yes 0 No
Date of Previous Su r vel':
November 4-8, 1986
Highest Classification of
Documents S/RD
Materials S/RD
Work: S/RD
DescnptlOn of Interest(s):
For active security interests, see Exhibit tiD" of this report.
Classlhed Mailing Address:
Bates Midtown Division
ATTN: Document Custodian
909 Prince Avenue
Midto'Nn, OH 45201 USE REGISTERED CR CER!I lED
Claaaifted Shipping Address:
Bates Midtown Division
ATTH; Document Custodian
FOR: Ovid Foster
Midtown, OH 45201
Facility MetA Manager: Ovid Foster
Telephone Number: (804) 312-5567
Foreign Ownership, ContrOl or Influence Certificate Submitted I
Ci Yes 0 No
Other
DNAo Other
Composite Facility Rating I
ex Setisfactory
o Marginal
o Unsatisfactory
IPre\l1ous Rallng
"0 SAT I
clear Matenal:
o Category I o Category N
ex Category II DONA
I
!o Category III I r
~
f
I
t
I
!
Surveying Office:
CH
G
I
(See Rever!le Side of Form) I
I
~
o
Attachment 11I-1
II 1-6
PROGRAM PLANNING AND MANAGEMENT
Planning Process
Organization and Management
Safeguards and Security Plans
Reporting and Notification
Resolution of Findings
Rating
PROTEC1l0N PROGRAM OPERAnONS
Physical Security Systems
Property Protection .
Protective Force
System Performance Tests
Rating
MATERIAL CONTROL AND ACCOUNTABIUTY
Program Management
Materials Accounting
Material Control
Administrative Controls
System Performance Tests
Rating
COMPUTER SECURITY
Computer Security Management and Planning
Protection of Information Assets
Physical Protection of Computing Resource Assets
Continuity and Reliability of Critical Operations
TEMPEST Program
Rating
OPSEC
OPSEC Program Structure
Vulnerability Assessment
Rating
PERSONNEL SECURITY
Personnel Clearance Program
Selective Reinvestigation Program
Security Education Program
Visitor Control
Rating
FACILITY SURVEY AND APPROVAL
Facility Register
Facility Approval Process
Security Surveys
MC&A Surveys
Rating
Rate Each Item: S - Satisfactory M - Marginal
DOE 5634.1A
2-3-88
5
-5
-5
-5
-5
~
--L
~
_5_
_5_
_5_
5
-5
-5
U - Unsatisfactory DNA - Does Not Apply
J
c
o o
DOE 5634.1A IV-l
o 2-3-88
CHAPTER IV
SECURITY SURVEYS
1. PURPOSE. To assure that facilities maintain effective safeguards and
security programs by requiring surveys which provide monitoring and
evaluation.
2. EXEMPTIONS. (Attachment IV-l outlines geographic responsibilities
for security surveys). Each field organization and DP-34 shall
conduct surveys of the facilities within its assigned geographic
area, except in cases when a responsible organization may elect to
perform this function itself. In the latter case, the responsible
• organization shall coordinate its decision with the organization
having geographic responsibility.
a. The Pittsburgh Naval Reactors Office, Schnectady Naval Reactors
Office, and the Strategic Petroleum Reserve Project Management
Office are exempt from conducting security surveys for other
field organizations within their immediate geographic areas.
However, this exemption is not all inclusive since travel
restrictions based on budget restraints may dictate that field
organizations request these organizations to conduct the surveys
for them. In such cases, mutually acceptable agreements are
encouraged.
Section 21
b. When the volume of survey work assigned by geographical areas
exceeds the ability of the surveying field organization to absorb
the work, and the problem cannot be resolved between affected
field offices, DP-34 shall be notified. The affected surveying
field organization shall provide DP-34 with a current list of
facilities/interests within its assigned geographical area,
survey delay times, survey schedules, staffing status, and other
pertinent information. If the proposed delays are not
satisfactory, DP-34 will coordinate a resolution with affected
field office and program offices, recommending temporary
reassignment of surveys, personnel or resources to the Heads of
Departmental Elements.
,
3. FREQUENCY. Security surveys are conducted with the following
schedule:
a. Class nAil and "BII facil ities shall be surveyed at least once
every 12 months.
b. Class "C U and Class "AP" facil ities shall be surveyed at least
once every 18 months, except for those facilities containing
security interests listed in paragraph 3c, page IV-2.
c. Secure communication centers, classified automatic data
processing centers, remote interrogation points, sensitive
compartmented information facilities, and selected security
shipments shall be surveyed at least once every 12 months.
IV-2 DOE 5634.1A
2-3-88
d. Property Protection (Class "PP II ) facilities shall be surveyed at
least once every 24 months, except those facilities containing
security interests listed in subparagraph 3c above.
e. Those safeguards and security interests documented in a facility
Master Safeguards and Security Agreement as requiring protection
against industrial or radiological sabotage shall be surveyed at
least once every 12 months.
4. SURVEY REPORT CONTENT. Initial and periodic security survey reports
consist of a narrative section reflecting both the compliance and
performance segments of the survey and a completed survey report form
as supplied by DP-34. A copy of an approved survey report form is
shown as Attachment 111-1. Locally developed survey forms may be
used to supplement the approved survey report form.
a. A report on the results of a survey of a security interest should
include such items as:
(1) A statement of the survey scope and period of coverage.
(2) A statement regarding the facilityls function and scope of
operations related to security interests.
(3) An assessment of management (if appropriate) relative to .'~
security, program planning and review, and security control ~
exercised by the facility.
(4) Corrective actions on findings, including status of prior,
unresolved findings.
(5) Discussion of major points which had, or might have, a
significant effect on security controls at the facility.
b. A periodic survey report need not contain a complete narrative
description of each component and element of the security program
unless significant changes have occurred or 5 years have elapsed
since the last description. The phrases "no change" or lias
previously reported II may be used. However, the new report shall
identify the survey report which provides the latest description
of the unchanged item. When a complete report is warranted,
paragraph 4a above applies.
c. Special and termination survey reports may be written in
memoranda form.
Section 22
d. Within 60 working days after completion of the survey, the
surveying organization shall forward one copy of each survey
report to the responsible organization, one copy to DP-34,
copies to Headquarters elements as directed, and one copy to the
surveyed organization as determined locally. When the special
survey is the basis for granting facility approval for a new or
expanded security interest or for continUing facility approval
for an existing interest, and time is of the essence, the
surveying organization shall:
o
DOE 5634.1A •IV-3 (and I-¥-4)
2-3-88
(1) Advise the responsible organization by telephone or
teletype of the results of the survey;
(2) Confirm this action by memorandum; and/or
(3) Submit a formal survey report, as appropriate.
e. The surveying organization is not required to send a copy of a
survey report to a responsible organization when the only
security interest at the facility involves an individual
interest (e.g., consultant, responsible reviewer, or a person
with a personal service contract). In this case, the surveying
organization should advise the responsible organization by
memorandum that the interest has been included in the survey
report, the date of survey, composite survey rating, and
findings, if applicable.
f. The surveying organization shall forward copies of each
termination survey report, including the certificate of
nonpossession/possession, to the responsible organization, DP
34, and other Headquarters elements, as appropriate.
g. The surveying organization shall forward one copy of the
portions of the survey report regarding secure communications
centers or crypto facilities to the Director of Computer
Services and Telecommunications Management (MA-25).
5. TRAINING AND QUALIFICATIONS. Team personnel for security surveys
shall possess qualifications and training sufficient to accomplish
effective and thorough surveys.
6. COMPLIANCE SEGMENT. The compliance segment of the security survey
shall address how well the facility meets requirements contained in
DOE directives and the applicable facility Security Plan and/or
Master Safegaurds and Security Agreement. The results shall be
entered on an approved security survey report form.
7. PERFORMANCE SEGMENT. Surveys of facilities shall include a
performance evaluation to assess the capability of the
safeguards and security system to meet performance
objectives. The performance evaluation shall determine system
performance against scenarios for applicable threats/targets.
C 0
J
J
J
o o
o
•
c
1
DOE 5634.1A
2-3-88
Field or Headquarters
Organizations
Albuquerque
Chicago
Idaho
Nevada
Oak Ridge
Richland
San Francisco
Savannah River
Office of Safeguards and
Security, Headquarters
Attachment IV-l
IV-5 (and IV-6)
Geographic Responsibilities
for Surveys
Survey Area
Arizona, Colorado, Kansas,
New Mexico, Oklahoma, Texas,
Jackson County in Missouri
Connecticut, IllinOis,
Indiana, Iowa, Maine,
Massachuesetts, Michigan,
Minnesota, Nebraska, New
Hampshire, New Jersey, New
York, North Dakota, Ohio,
Pennsylvania, Rhode Island,
South Dakota, Vermont,
Wisconsin
Idaho, Montana, Utah, Wyoming
Hawaii, Nevada, Johnston Atoll, Aleutian
Islands
Arkansas, Kentucky,
Louisiana, Mississippi,
Puerto Rico, Tennessee, West
Virginia, Missouri (except
Jackson County), Virgin
Islands
Oregon, Washington, Alaska
(except Aleutian Islands)
California
Alabama, Florida, Georgia,
North Carolina, Canal Zone,
South Carolina
Section 23
Delaware, District of Columbia,
Maryland, Virginia, DOE
offices in foreign countries
o
J
o o
DOE 5634.1A
~~M
V-1
CHAPTER V
NUCLEAR MATERIALS SURVEYS
1. PURPOSE. To assure that facilities are maintaining effective
safeguards and security programs. This Order requires and
describes the conduct of surveys which provide such monitoring
and evaluation.
2. FREQUENCY.
a. Nuclear materials surveys of each license-exempt (as
defined in 10 CFR Part 50) contractor and Government
operated facility shall be performed annually for Category
I, II, and III materials, and biennially for Category IV
nuclear materials, unless:
(1) The total value of the nuclear materials inventory at
any time does not exceed $150,000 and the value of
nuclear material receipts for any 12-month period is
less that $500,000;
(2) The total inventory consists entirely of source
material, less than 10 tons of heavy water, less than
350 grams of SNM, or any combination of these; or
(3) Exception approval is obtained from the Operations
Office Manager or Director of Safeguards and Security
(DP-34).
b. Surveys of contractor facilities meeting the criteria in
paragraphs 2a(1) and 2a(2), above, shall be conducted at
the discretion of the Operations Office Manager.
Definitions of Categories I, II, III and IV are contained
in DOE 5633.3.
3. SURVEY REPORT CONTENT. Initial and periodic nuclear materials
survey reports consist of a narrative section reflecting the
results of both the compliance and performance segments of the
survey. For those facilities holding Category II and larger
quantities of SNM, an approved survey report form as provided
by Attachment 111-1.) Locally developed survey forms may be
used to supplement the approved survey report form.
a. A report on the results of a survey of nuclear materials
control and accountability should include such items as:
(1) A statement of the survey scope and period of
coverage.
o (2) A statement regarding the facility·s function and
scope of operations related to nuclear materials.
(3) An assessment of the effectiveness of management (if
appropriate) relative to nuclear material control and
o
V-2 DOE 5634.1A
2-3-88
accountability (MC&A) program planning and review. and
the safeguards control exercised by the facility.
(4) Corrective actions on findings. including status of
prior. unresolved findings.
(5) Discussion of major points which had. or might have. a
significant effect on inventory procedures and
safeguards control at the facility.
b. The nuclear materials survey report shall include results
from:
(1) Assessing the ability of the safeguards system to
detect and respond to theft and/or diversion of
nuclear materials.
(2) Reviewing and evaluating:
(a) Practices and procedures for the inventory of
nuclear materials and the records system
reconciliation;
(b) Measurements and statistical programs. system;
(c) Site's nuclear materials accounting information . .~
system; ~
(d) Nuclear material control practices and
procedures;
(e) Internal control system;and
(f) Program planning and procedures.
(3) Reviewing the training and qualification records of
material balance area custodians. material handlers.
and accountability clerks responsibile for nuclear
material data generation and/or transmission.
(4) Reviewing the facility's vulnerability assessment
program and material control and accountability
internal control system.
Section 24
c. In addition to the requirements in paragraph 3a and 3b.
page V-I above. during periodic nuclear material surveys.
DOE personnel shall, as appropriate for the type and
quantity of nuclear material in the inventory:
(1) Ascertain facility compliance with written procedures
and objectives of DOE directives on control and
accountabilit of nuclear materials and the Material
Control and Accountability plan;
o o
DOE 5634.1A V-3
2-3-88
(2) Review and evaluate the cause, magnitude,
reasonableness, and disposition of accidental losses,
normal operational losses/measured discards, approved
write-offs, inventory differences, and shipper
receiver differences;
(3) Audit the nuclear material records and reports to verify the
accuracy of the facility's material status reports and
subsidiary records; and
{4} Observe inventory procedures and practices and control the
independent tests of the inventory to confirm the facility's
statement of the quantity of material on hand. Operations
offices may develop and use statistically based sampling plans
o
• appropriate for their site-specific needs to establish that
stated nuclear material quantities are accurate. Inventory
testing shall be based on a graded safeguards concept, and
documentation shall be maintained to support the survey
inventory testing criteria, sampling plans, test results, and
conclusions. For those populations that do not conform to
conventional weighing and sampling methods (or Non-Destructive
Assay analyses), confirmation of the contained nuclear
materials shall be consistent with accepted estimation
techniques, whether independently performed or observed by
survey personnel. Inventory exemptions for highly radioactive
materials are contained in DOE 5633.3, CONTROL AND
ACCOUNTABILITY OF NUCLEAR MATERIALS.
d. A periodic survey report need not contain a complete narrative
description of each procedure and element of the Material Control
and Accountability program unless significant changes have occurred
or 5 years have elapsed since the last description. The phrases
"no change" or lias previously reported" may be used. However, the
new report shall identify the survey report which provides the
latest description of the unchanged item.
e. Within 60working-days after completion of the survey, the surveying
organization shall forward one copy of each survey report to DP-34,
copies to Headquarters elements as directed, and one copy to the
surveyed organization as determined locally. When a special
nuclear materials survey is a part of the basis for granting
facility approval for a new or expanded safeguards and security
interest involving SNM, or for continuing facility approval for an
existing interest where SNM is present, and time is of the essence,
the surveying organization shall comply with the requirements of
Chapter IV, paragraphs 4d(1},(2) and (3), page IV-3.
4. TRAINING AND QUALIFICATIONS. Team personnel for nuclear materials
surveys shall possess qualifications and training sufficient to
accomplish effective and thorough surveys.
o 5. COMPLIANCE SEGMENT. The compliance segment of the nuclear materials
survey shall address how well the facility meets requirements contained
in DOE directives and the applicable facility Material Control and
Accountability plan and/or MSSA. Results shall be entered on an
approved nuclear materials survey report form.
o
V-4 DOE 5634.1A
2-3-88
J
6. PERFORMANCE SEGMENT. Surveys of facilities shall include a performance
Section 25
evaluation to assess the capability of the safeguards and security
system to meet performance objectives. The performance evaluation
shall determine system performance against scenarios for applicable
threats/targets.
o Q
DOE 5634.1A VI-1
2-3-88
CHAPTER VI
SURVEY RATINGS AND FOLLOW-UP ACTIONS
1. RATING SYSTEM. Permissible composite nuclear materials or
security survey ratings are SATISFACTORY, MARGINALLY
SATISFACTORY, and UNSATISFACTORY. The following composite
survey rating shall reflect a balance of performance and
compliance results as determined by the surveying organization.
a. Satisfactory. The safeguards and security element being
evaluated meets identified protection needs or provides
plausible assurance that those protection needs will be met
.. should they arise •
b. Marginally Satisfactory. The safeguards and security
element being evaluated only partially meets identified
protection needs or provides questionable assurance that
those protection needs will be met should they arise.
c. Unsatisfactory. The safeguards and security element being
evaluated does not meet identified protection needs or does
not provide adequate assurance that those protection needs
will be met should they arise.
2. IDENTIFIED PROTECTION NEEDS. Identified protection needs are
those defined by DOE Orders as modified by approved MSSAs,
facility safeguards and security plans, approved safeguards and
security upgrades, and documented and approved exceptions to
DOE requirements. These modifiers specify site-specific
considerations and tailor the safeguards and security program
to the local mission and operating environment. They shall be
comprehensive and supportable relative to threat and safegaards
and security interests (i.e., targets).
3. USE OF THE "MARGINALLY SATISFACTORY" RATING. A facility shall
not be assigned a survey rating of Marginally Satisfactory for
consecutive survey periods unless the following conditions
apply:
a. The previous survey which resulted in a composite survey
rating of Marginally Satisfactory identified different
deficiencies and reasons for the rating.
c
b. Thp. deficiencies and reasons which were the basis for the
previous Marginally Satisfactory composite survey rating
were related to the completion of a major line-item
construction project. In that case, acceptable interim
measures must have been implemented and physically verified
pending completion of the construction. These interim
measures shall be documented in the survey report.
4. USE OF UNSATISFACTORY RATING. If either of the conditions
cited in paragraphs 3a or 3b above are not met, an
Unsatisfactory rating shall be assigned.
o
VI-2 DOE 5634.1A
2-3-88
J
5. CORRECTIVE ACTIONS AND SURVEY RATINGS. A composite nuclear
materials and/or security survey rating which must be based on
conditions existing when the rating was assigned. shall be
stated in the survey report, ratings shall not be based upon
future corrective actions. If corrective actions have been
taken in the interval between the performance of the on-site
survey and the aSSignment of the composite survey rating, the
final rating should reflect these actions.
6. DEFICIENCIES IN DOCUMENTATION. A facility·s failure to comply
with procedural documentation requirements, of and by itself,
shall not normally be the basis for a reduction in a composite
rating. Ratings of less than Satisfactory in any area shall be
based on verified weaknesses in the safeguards and security
system or deficiencies in performance in an operational area.
Section 26
7. COMPLIANCE. The compliance segment rating of a facility
reflects the judgments of the surveying organization as to the
assurance with which the facility·s safeguards and security
system protects the DOE interests located at that facility as
measured against related DOE directives, see page V-3,
paragraph 5.
8. PERFORMANCE. The rating for the set of exercises, system
studies, and technical evaluations, constituting the Jperformance segment of the survey, shall be based on an
evaluation of the degree to which the elements of the
safeguards or security system meet protection objectives.
9. SURVEY FOLLOW-UP AND CORRECTIVE ACTIONS.
a. When a nuclear materials and/or security survey report
contains findings, the surveyed organization shall submit a
response identifying corrective action(s) for each finding
to the responsible and surveying organizations not later
than 30 days after receiving the survey report.
b. When a survey report indicates a composite rating of
Satisfactory and contains findings requiring corrective
action, the responsible organization shall provide to DP
34, appropriate Headquarters elements, and the surveying
organization (if appropriate), a quarterly status report of
corrective actions. Notification shall be by memorandum
and shall include the identification of the facility, a
description of the deficiency, and a description of
corrective actions taken to date or planned (with
associated milestone dates).
c. When a survey report has a composite rating of Marginally
Satisfactory, the responsible organization shall notify the J"
Director DP-34, the surveying organization (if
appropriate), and the applicable field and Headquarters
program office(s) within 15 working days after completion
a Q
DOE 5634.1A VI-3
2-3-88
of the survey of interim corrective actions taken, or to be
taken, to correct identified risks or vulnerabilities. If
interim corrective actions are instituted, the surveying
organization shall physically verify them for adequacy. If
the surveying organization differs from the responsible
organization, the surveying organization shall promptly
notify the responsible organization of the rating. The
responsible organization shall then take appropriate
corrective and notification actions outlined above or
authorize the surveying organization to take those
actions. If the surveying organization is unable to
contact the responsible organization and a serious threat
exists or is imminent, the surveying organization shall
take action to protect the safeguards and security
interest(s) until the responsible organization is
notified. Subsequent action shall be taken on the basis of
agreement between the two organizations.
d. When a survey report has a composite rating of
Unsatisfactory, and the rating is indicative of a
significant vulnerability such as unacceptable risk in the
area of SNM theft, radiological or industrial sabotage or
espionage, the Operations Office Manager shall immediately
or as soon as possible, but not later than within 24 hours:
(1) Take action to shut down/suspend operation of the
facility or activity, pending remedial action; or
(2) Provide the rationale for continuing this critical
operation to the Assistant Secretary for Defense
Programs (DP-l), Director, DP-34, Head~ of the
Headquarters Elements; as directed, the Head of the
responsible organization, responsible office, and the
applicable field and Headquarters program office(s)
and identify those immediate interim corrective
actions being undertaken to mitigate identified risks
or vulnerabilities.
Section 27
For all other Unsatisfactory ratings, the Operations Office
Manager of the responsible organization shall notify the
Secretary, DP-l, Director, DP-34, and Heads of Headquarters
Elements, as directed, applicable program and field
office(s), and the responsible office within 15 working
days of interim corrective actions taken, or to be taken,
to correct identified risks or vulnerabilities.
e. When either a Marginally Satisfactory or Unsatisfactory !composite rating is assigned, the responsible office shall
provide to DP-34 and the applicable field and Headquarters
program office(s) quarterly status reports on completed or I
planned corrective actions (with associated milestone
I
fdates) until all have been completed. When the responsible
organization determines that the composite survey rating
should be upgraded to Satisfactory, the surveying
VI-4 DOE 5634.1A
2-3-88
organization shall physically verify the completion and
adequacy of corrective actions for those deficiencies which
contributed to the Marginally Satisfactory or
Unsatisfactory composite rating. The responsible
organization shall then notify the Director DP-34 and the
Head(s) of applicable Headquarters Element(s) that the
rating should be upgraded.
f. A finding associated with a significant vulnerability shall
not be considered closed until associated corrective action
has been completed and the Director DP-34 and Heads of
Headquarters Elements are notified. A commitment by the
facility to institute corrective action does not constitute
completion of that corrective action.