DOE O 5480.9A, Construction Project Safety and Health Management
Functional areas: Environmental Quality & Impact
Canceled by DOE O 440.1 of 9-30-1995.
Superseded By:
DOE N 251.4, Cancellation of Directives on Sep 29, 1995
Version history and related documents
Superseded by
A newer version replaces this document.
- DOE N 251.4Cancellation of Directives (Sep 29, 1995)
- DOE O 440.1Worker Protection Management for DOE Federal and Contractor Employees (Sep 30, 1995)
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
U.S. Department of Energy ORDER
Washington, DC DOE 5480.9A
4-13-94
SUBJECT: CONSTRUCTION PROJECT SAFETY AND HEALTH MANAGEMENT
1. PURPOSE. To establish specific requirements for the management of
Occupational Safety and Health (OSH) on Department of Energy (DOE)
construction projects.
2. CANCELLATION. DOE 5480.9, CONSTRUCTION SAFETY AND HEALTH PROGRAM, of
12-18-80 and republished 11-18-87.
3. SCOPE. The provisions of this Order apply to all Departmental elements
and, to the extent provided in their contracts/subcontracts, to
contractors and subcontractors performing work on DOE construction
projects which exceed the monetary threshold (currently $2,000) for
application of the wage standards prescribed by the Davis-Bacon Act (40
U.S.C 276a-276a-7).
4. APPLICABILITY. The requirements of this Order shall apply to contracts
at Government-owned or -leased facilities upon which the contract clause
"Safety and health (Government-Owned or -Leased Facility)" (DEAR
970.5204-2) applies.
5. EXCLUSIONS.
a. Director, Naval Nuclear Propulsion Program. Executive Order 12344,
statutorily prescribed by Public Law 98-525 (42 U.S.C. 7158, Note
(1984)) establishes the Director of the Naval Nuclear Propulsion
Program (who is also the Director, Office of Naval Reactors within
the Department) for all facilities and activities that comprise the
Program, a joint Navy-DOE organization. These executive and
legislative actions establish that the Director is responsible for
all matters pertaining to naval nuclear propulsion, including
direction and oversight of environment, safety and health matters
for all program facilities and activities. Accordingly, the Naval
Nuclear Propulsion Program is exempt from the provisions of this
Order.
b. Power Marketing Administration. In accordance with Section 302 of
the Department of Energy Organization Act (PL 95-91), the Secretary
operates and maintains the Power Marketing Administration (PMA)
electric power transmission systems by and through the PMA
Administrators. The PMA has management programs in place that are
geared to the special needs of utility operations, that respond to
coordinated multi-utility system requirements, and that conform
with prudent utility practice. In view of the unique nature of the
Administrators' obligations to meet their statutory and public
utility responsibilities for the safety, security, and reliability
of electric power transmission and of their legal and contractual
obligations, the Administrators' shall determine an appropriate
program for the management of construction project safety and
health with due consideration of applicable program elements
outlined within this Order.
6. REFERENCES AND DEFINITIONS. See Attachment 1.
7. IMPLEMENTATION. The requirements of this Order shall be implemented on
projects for which construction services are ordered or solicited on a
date 6 months or later from the approval date of the Order. There is no
requirement to modify any fixed-price construction contract based upon a
Section 2
solicitation predating this effective date.
8. ASSISTANCE. Questions from DOE Field Organizations concerning this
Order should be directed to EH-313, (301) 903-9876.
Order should be directed to EH-313, (301) 903-9876.
9. RESPONSIBILITIES AND AUTHORITIES.
a. Heads of Field Organizations or their designees shall:
(1) Develop local instructions as needed for implementation of
this Order. Local adoption of the terms used in this Order is
nonmandatory, both within any local implementing instructions
or subsequent contract language.
(2) Ensure that project managers are provided with the training,
resources, and technical support necessary to perform the
duties prescribed by this Order.
(3) Ensure that the construction project acquisition documents for
all construction projects include the program requirements
prescribed by this Order.
(4) Ensure that construction project acquisition documents include
provisions which allow for noncompensable work stoppages for
construction contractor refusal to comply with project safety
and health requirements (refer to DEAR 970.5204-2).
(5) Review safety and health programs developed or implemented by
the host for their maintenance and operational activities and
recommended for application to construction activities (e.g.,
confined space entry, hazard communication, lock out/tag out,
etc.) to determine their utility, applicability and cost
effectiveness for use on construction projects managed by the
host or other site contractors. Ensure that construction
project acquisition documents identify the specific facility
host programs, or parts thereof, which must be incorporated
into the construction contractor's OSH program and project
safety and health plan.
(6) Review and approve construction contractor evaluations
performed by the project manager and use these evaluations to
determine bidder responsibility on solicitations for future
DOE fixed-price construction prime contracts (refer to FAR
36.201).
(7) For projects managed by the Resident Construction Management
Contractor (RCM) or host, ensure that the RCM or host:
(a) Develops and implements a system for evaluating the
effectiveness of contractor safety and health programs on
each construction project.
(b) Applies this system to the determination of bidder
responsibility on future construction projects.
b. Project Manager. The project manager is responsible and
accountable for management of the construction project and for
providing project oversight to ensure compliance by the
construction contractor with the safety and health program
requirements. The project manager may designate a firm or
individual to perform any of the required duties listed below. In
such cases, this firm or individual must be independent of the
construction contractor and construction manager. The designation
Section 3
shall be in writing and shall appropriately describe the assigned
responsibilities of the designee. The project manager or his/her
designee shall:
(1) Avail himself/herself of the skills, training, expertise, and
technical support necessary to perform the duties prescribed
technical support necessary to perform the duties prescribed
below.
(2) Based upon the recommendation of construction manager,
determine the necessity for requiring dedicated construction
contractor OSH personnel on the construction worksite. If it
is determined that dedicated construction contractor OSH
personnel are needed, ensure the requirement (including duties
and necessary qualifications) is specified in the construction
project acquisition documents.
(3) Perform worksite inspections in conformance with paragraph
11.c. below.
(4) Evaluate the effectiveness of the construction contractor's
safety and health program for projects performed through
fixed-price prime contracts with DOE. Refer to the method
prescribed by FAR 36.201 for guidance on contractor
evaluation. Review construction contractor performance
evaluations prepared by either a RCM or host for construction
projects exceeding $500,000.
(5) Ensure the construction manager:
(a) Provides, or has access to, qualified staff and
sufficient resources to fully implement the requirements
of this Order.
(b) Provides within the project acquisition documents
information or reference to the existence of
documentation, along with its location and means of
access, which describe known hazards to which project
employees may be exposed (e.g., site characterization
data, as-built drawings, structural analyses, and
pertinent Safety Analysis Report information).
(c) Reviews the scope of all construction projects and
provides a recommendation to the project manager in cases
where it is felt that the size, complexity, or expected
OSH hazards of a project warrants requiring dedicated
construction contractor OSH personnel on the construction
worksite.
(d) Conducts a prework safety meeting with the construction
contractor to review project safety and health program
requirements with the construction contractor prior to
allowing work to commence on the worksite. This meeting
may be conducted concurrently with other prework meetings
addressing other aspects of project performance.
(e) Reviews and approves project safety and health plan and
preliminary hazard analysis prior to allowing work to
commence on the project worksite.
(f) Reviews and approves the activity hazard analysis for
each project phase prior to allowing work to commence on
that project phase.
Section 4
(g) Evaluates the effectiveness of the construction
contractor's safety and health program throughout the
life of the project, requires revisions of the project
safety and health plan when needed, and approves
revisions to the plan.
(h) Fully documents all formal contract actions (e.g.,
mandated work stoppages, removal of incompetent or
careless personnel, withholding of payment) taken to
careless personnel, withholding of payment) taken to
enforce construction contractor compliance with project
safety and health requirements. This documentation shall
provide a comprehensive summary of the events leading to
the contract action including a description of the
noncomplying work activity or condition, the method,
date, and time of notification to contractor, the
contractor's response, and a description of previous
similar instances of noncompliance with contract safety
and health requirements.
10. PROGRAM REQUIREMENTS. The construction contractor shall establish and
maintain a program to protect the safety and health of all persons on
the construction worksite to include his or her employees, employees of
other contractors or subcontractors, visitors and the public. This
program also shall protect against damage to property, materials,
supplies, and equipment and prevent unnecessary work interruptions. The
program shall ensure compliance by the construction contractor and all
worksite subcontractors with the safety and health standards prescribed
in the construction project acquisition documents. In order to prevent
duplication of requirements and documentation (e.g., Hazard Analyses,
Training, Site-Specific Safety and Health Plan) on construction projects
that fall within the scope of the OSHA Standard for Hazardous Waste
Operations and Emergency Response, Title 29 CFR 1910.120, the project
safety and health program requirements of this Order need not duplicate
those required by the standard (refer to Title 29 CFR 1910.120(b)).
a. Program Implementation.
(1) The construction contractor shall designate in writing the
construction superintendent who is assigned full
responsibility and authority for implementing the construction
contractor's OSH program. A copy of the written designation
shall be provided to the construction manager. This
designation shall also include any individual(s) having
authority to act for the construction contractor during the
absence of the construction superintendent.
(2) The construction superintendent or other duly designated
contractor representative must be present on the worksite
during the performance of any project work activities (refer
to FAR 36.506 for fixed-price construction and FAR 36.519 for
cost reimbursement construction).
(3) In no case shall the requirement for or the presence of
dedicated project OSH personnel relieve the construction
Section 5
superintendent of full and complete responsibility for
compliance with all project OSH requirements.
(4) The construction contractor is responsible for ensuring
compliance by all project subcontractors with project safety
and health requirements. The construction contractor is
further responsible for coordinating with project
subcontractors and other site contractors (i.e., the host or
RCM and their subcontractors) those OSH program elements
addressing worksite hazards to which employees of other
contractors may be exposed.
b. Hazard Analyses. The construction contractor shall evaluate the
work associated with each project phase to identify specific
hazards to which worksite employees and other worksite personnel
may potentially be exposed and to identify appropriate control
measures. The construction contractor shall accomplish this
through the performance of preliminary and activity hazard analyses
as outlined below. For hazards common to multiple phases of the
construction project, these hazards and their control measures may
construction project, these hazards and their control measures may
be identified and addressed in the worksite safety and health
orientation and omitted from the required activity hazard analysis
for each affected project phase. For any project phase where the
preliminary hazard analysis fulfills all requirements for the
activity hazard analysis, additional analysis need not be
performed. A preliminary hazard analysis fulfilling the
requirements given below may be performed by the construction
manager and provided to the construction contractor in the
construction project acquisition documents.
(1) Preliminary Hazard Analysis (PHA). Prior to commencement of
work on a construction project, the construction contractor
shall prepare and have approved by the construction manager a
PHA for the construction project. The PHA shall:
(a) Identify the anticipated construction phases involved in
the construction project.
(b) Identify the types of hazards associated with each
anticipated phase of the project as well as potential
control measures and programs necessary to protect
employees and others at the worksite.
(c) Identify the phases of the project for which
DOE-prescribed OSH standards or the construction project
acquisition documents require that protective measures be
designed, inspected, or approved by a Professional
Engineer or other competent person.
(2) Activity Hazard Analysis (AHA). Prior to commencement of work
on any phase of the project, the construction contractor shall
prepare and have approved by the construction manager a
detailed AHA. For any project phase where the PHA is intended
to fulfill the requirement for an AHA, the construction
contractor shall make note of this intent on the PHA and shall
Section 6
submit the annotated PHA to the construction manager for
approval. The number of phases for which an AHA is required
is not limited to those addressed in the PHA in that the
actual number of phases may differ from the anticipated number
due to variations in subcontractors, construction operations,
or job sequence. The AHA shall expand upon the PHA by:
(a) Identifying the specific hazards, including the use or
presence of any hazardous chemicals, associated with each
activity to be performed in that phase of work as well as
the actual corrective measures planned to control these
hazards.
(b) Including drawings and/or other documentation for all
protective measures for which the construction project
acquisition documents or applicable OSH standards
prescribe preparation by a Professional Engineer or other
competent person.
(c) Designating and identifying the qualifications of the
competent person or Professional Engineer that will
conduct inspections where required by DOE-prescribed OSH
standards or construction project acquisition documents.
c. Training. The construction contractor shall ensure that each
employee entering the worksite has, through experience, training
and, where required, certification, the skills and knowledge
necessary to safely perform his or her assigned tasks. In
addition, the contractor shall ensure that each employee receives
initial worksite safety and health orientation and continued safety
and health training addressing the hazards associated with the work
and health training addressing the hazards associated with the work
and the measures necessary to control or eliminate the hazards.
(1) Worksite Safety and Health Orientation.
(a) Each employee shall receive an initial safety and health
orientation prior to performing any work on the project
worksite. The construction manager shall ensure that
proper local coordination has been performed for issues
that may impact the facility host, the RCM, or any other
contractors. The orientation shall address, at a
minimum, the following points:
(1) Employee rights and responsibilities.
(2) Construction contractor responsibilities.
(3) Use and maintenance of required personnel protective
equipment.
(4) Disciplinary procedures.
(5) Alcohol and drug abuse policy.
(6) First aid and medical facilities.
(7) General project hazards and the applicable policies
and procedures for addressing these hazards.
(8) Hazard recognition and procedures for reporting or
correcting unsafe conditions or practices.
(9) Procedures for reporting accidents and incidents.
(10) Fire prevention and control.
Section 7
(11) Emergency response procedures to include local
warning and evacuation systems.
(12) Hazard communication program (refer to 29 CFR
1926.59).
(13) Access to employee exposure monitoring data and
medical records.
(14) Location of and access to approved project safety
and health plan.
(15) Host OSH programs or procedures applicable to the
project (e.g., confined space, lock out/tag out).
(b) Contractors with a continual onsite presence or with
multiple projects utilizing the same work force may
provide a general orientation on the items above prior to
commencing work on the employee's first onsite project
and at least annually thereafter. Orientation on items
that vary from project to project shall be provided for
each project.
(2) Prephase Training. Prior to commencing any phase of work, the
construction contractor shall review the approved AHA for that
phase with all employees on the affected work crew and provide
training to ensure that all employees understand the potential
hazards and the required protective measures. A copy of each
phase's AHA shall be annotated with the name, signature, and
date of attendance of all workers who have attended the
date of attendance of all workers who have attended the
pre-phase training. The construction contractor shall provide
advance notice to the construction manager for all prephase
training sessions. Further prephase training sessions shall
be conducted for new employees on the work crew, under
changing site conditions, or at the discretion of the
construction manager to reinforce project safety and health
requirements.
(3) "Tool Box" Safety and Health Training. The construction
contractor shall conduct informal "tool box" safety and health
training sessions at least weekly for all employees on the
worksite. Depending on the size and nature of the project,
this may be accomplished in single or multiple sessions and
may address different topics for different work crews.
Outlines of all "tool box" training sessions shall be prepared
by the construction contractor and annotated with the date,
time, and names of all employees in attendance.
(4) Training Records. The construction contractor shall ensure
that records of all required training are maintained and made
available, upon request, to the construction manager, project
manager and other personnel with assigned oversight
responsibilities.
d. Reporting, Recordkeeping, and Accident Investigation. The
construction contractor shall comply with reporting, recordkeeping,
and accident investigation requirements prescribed in the
construction project acquisition documents.
e. Project Safety and Health Plan.
Section 8
(1) The construction contractor shall prepare a written project
safety and health plan which:
(a) Includes the construction contractor's proposal for
implementing this Order's program requirements.
(b) Identifies the proposed construction superintendent and
other construction contractor personnel to be assigned
OSH duties on the worksite, their qualifications, and
their respective duties. The project safety and health
plan shall also identify any other individual(s) the
construction contractor proposes to authorize to act
during periods of construction superintendent absence.
(c) Includes a detailed outline of the proposed employee
worksite safety and health orientation.
(2) The approved project safety and health plan shall be
maintained on the worksite and shall be made available upon
request to the construction manager, project manager, worksite
employees, employee representatives, and other personnel with
assigned oversight responsibilities.
11. INSPECTIONS AND HAZARD ABATEMENT.
a. Construction Contractor. During periods of active construction,
the construction contractor shall conduct daily inspections of the
worksite to identify hazards and instances of noncompliance with
project safety and health requirements. Records shall be kept of
all daily inspections. These records shall note all observed
hazards and the corrective actions taken.
b. Construction Manager. The construction manager shall conduct
worksite safety and health inspections on at least a weekly basis.
The construction manager's attendance, findings, and directed
The construction manager's attendance, findings, and directed
hazard abatement actions shall be documented in both the
construction contractor's and the construction manager's project
inspection records. The construction manager shall immediately
investigate hazards for which correction is outside the project
scope and notify in writing the responsible authority of his
findings, to include a description of interim control measures in
place. The construction manager shall develop and maintain a
system to track the status of all hazards for which corrective
action is not immediate or falls outside of the project scope. On
DOE prime construction contracts for which a DOE official is the
construction manager, a firm or individual independent of the
construction contractor may be designated to perform the weekly
worksite inspections and associated duties.
c. Project Manager. The project manager shall conduct inspections of
all construction projects exceeding $500,000 on at least a monthly
basis during periods of active construction. For projects under
$500,000, the project manager shall develop and implement an
inspection schedule which ensures that a representative sample of
ongoing construction projects is inspected on at least a monthly
basis. The objective of these inspections shall be to assess the
Section 9
effectiveness of the construction manager's supervision of
construction contractor safety and health performance. This shall
be achieved both through a walk-around inspection of the worksite
and through a review of the project safety and health plan and
other safety and health program documentation. Findings of these
inspections shall be documented in the project files.
d. Corrective Action. The construction contractor shall take
immediate corrective action to eliminate or control all identified
hazards. In cases where immediate corrective action is not
possible or responsibility for abatement falls outside the scope of
the project, the construction contractor shall:
(1) Immediately ensure all affected employees are aware of the
hazard and its location.
(2) Immediately post warning signs at the location of the hazard
describing the nature of the hazard.
(3) Implement further interim control measures, as needed, to
protect his/her employees from the identified hazards and
secure construction manager approval for continued use of the
employed measures.
(4) Notify the construction manager of the location and
description of the hazard. Where responsibility for abatement
falls outside the project scope, the construction manager
shall immediately notify the authority responsible for hazard
abatement in the affected facility. Corrective action for
such hazards shall be performed in accordance with the hazard
abatement methodology prescribed in DOE Order 5483.1A.
REFERENCES
1. DOE 5483.1A, OCCUPATIONAL SAFETY AND HEALTH PROGRAM FOR DOE CONTRACTOR
EMPLOYEES AT GOVERNMENT-OWNED CONTRACTOR-OPERATED FACILITIES, 6-22-83,
which establishes requirements and procedures to assure that DOE
contractor employees at Government- owned contractor-operated facilities
are provided occupational safety and health protection consistent with
that provided to private industry employees.
2. 29 CFR 1910.120, which provides the Occupational Safety and Health
Administration (OSHA) standard for hazardous waste operations and
Administration (OSHA) standard for hazardous waste operations and
emergency response.
3. 29 CFR 1926.14, which prescribes that construction safety standards
apply to the construction portions of Federal contracts for mixed
performance (e.g., a contract for both manufacturing and construction
services).
4. 29 CFR 1926.59, HAZARD COMMUNICATION, which provides the OSHA standard
for the evaluation of and the protection from hazardous chemicals.
5. 40 U.S.C. 276a-276a-7, DAVIS-BACON ACT, provides for the payment of
minimum prevailing wage rates on federally funded construction contracts
in excess of $2,000.
6. FEDERAL ACQUISITION REGULATION (FAR), Part 36, Construction and
Architect Engineer Contracts, prescribes policies and procedures
peculiar to contracting for construction and architect engineer
services.
7. FAR, Part 42, prescribes policies and procedures for performing contract
administration functions.
DEFINITIONS
1. CONSTRUCTION is any combination of erection, installation, assembly,
Section 10
demolition, or fabrication activities involved to create a new facility
or to alter, add to, rehabilitate, dismantle, or remove an existing
facility. It also includes the alteration and repair (including
dredging, excavating, and painting) of buildings, structures, or other
real property, as well as any construction, demolition, and excavation
activities conducted as part of environmental restoration or remediation
efforts. This does not involve the manufacture, production, finishing,
construction, alteration, repair, processing or assembling of items
categorized as personal property (refer to FAR 36.102).
2. CONSTRUCTION CONTRACTOR is the contractor or subcontractor who has been
awarded the contract to perform all construction activities described in
the construction project acquisition documents. For the purposes of
this Order, this may be the host contractor, the Resident Construction
Management Contractor (RCM), a subcontractor to either the host or RCM,
or a DOE prime construction contractor.
3. CONSTRUCTION MANAGER is the individual or firm responsible to DOE for
the supervision and administration of a construction project to ensure
the construction contractor's compliance with requirements set forth in
the construction project acquisition documents. For projects performed
under a direct contract with DOE, the construction manager shall be the
Contracting Officer or his duly designated representative. For projects
performed by host or RCM subcontractors, the construction manager is the
host or RCM, respectively. For projects performed by host or RCM
in-house forces, the host or RCM is both the construction contractor and
the construction manager. In such cases, the responsibilities and
duties of the construction manager and construction contractor
prescribed within this Order shall not be duplicated.
4. CONSTRUCTION PROJECT is the full scope of activities required on the
construction worksite to fulfill the requirements of the construction
project acquisition documents. Construction projects also include those
construction activities performed in support of or as part of
maintenance, manufacturing, decontamination and decommissioning (D&D),
or environmental restoration or remediation efforts (refer to Title 29
CFR 1926.14). For application of the $500,000 threshold, construction
project costs are limited to those incurred by the construction
contractor to fulfill the requirements of the construction project
acquisition documents and do not include design, supervision, or
acquisition documents and do not include design, supervision, or
administrative costs incurred by the construction manager or project
manager. In cases where multiple solicitations are used to perform
construction on or of a facility, those services described within each
solicitation shall be deemed a project for the purposes of application
of the construction safety and health program requirements of this
Order.
5. CONSTRUCTION SUPERINTENDENT is the individual designated by the
construction contractor as responsible for the performance of all
aspects of the work described in the project documents including
implementation of the project OSH program. He shall have full authority
to act for the Construction Contractor.
Section 11
6. CONSTRUCTION PROJECT ACQUISITION DOCUMENTS are the documents by which
construction services to be procured are described and solicited. These
include the request for proposal or the invitation for bids, the plans
and specifications and other standards referenced therein, work orders,
or other requisitions for construction services.
7. CONSTRUCTION WORKSITE is the area within the limits necessary to perform
the work described in the construction project acquisition documents.
It includes the facility being constructed or renovated along with all
necessary staging and storage areas as well as adjacent areas subject to
project hazards.
8. HOST is the contractor with the primary landlord responsibility at a DOE
sponsored facility.
9. PROJECT MANAGER is the DOE official responsible for assuring that all
project activities are carried out in compliance with Federal, State,
and local regulations, laws, and standards for protection of the safety
and health of employees and the public. For construction activities
without an assigned project manager, use of the term project manager
within this Order refers to the Head of the responsible DOE Field
Organization or his or her designee.
10. PROJECT PHASE is a separately definable portion of a project involving a
type of work presenting hazards not experienced in previous project
operations or an operation performed by a different subcontractor.
11. RESIDENT CONSTRUCTION MANAGEMENT CONTRACTOR (RCM) is a prime contractor
hired by DOE to perform a variety of construction management services on
a DOE sponsored facility for a long-term basis. These services may
include engineering design, construction management, and construction
with in-house forces. For the purposes of this Order, this definition
shall also apply to a prime contractor hired specifically to perform
environmental restoration activities on DOE facilities (i.e., an
Environmental Restoration Management Contractor (ERMC)).