Section 1
GENERAL PLANT PROJECTS
9-16-91
Change 1: 11-16-92
1. PURPOSE. To establish Departmentwide policies, responsibilities, and
guidance for the budgeting, funding, and execution of General Plant
Projects (GPP).
2. SCOPE . The provisions of this Order apply to all Departmental
Elements (except the Power Marketing Administrations and the Naval
Reactors/Naval Nuclear Propulsion program) that provide funding or
have responsibilities for administering GPP funding, or constructing
GPP at sites that are owned or controlled by the Department of Energy
(DOE), except where otherwise provided by statute or separate
authority.
3. REFERENCES.
a.
b.
c.
d.
e.
f.
DOE 1324.2A, RECORDS DISPOSITION, of 9-13-88, which assigns
responsibilities and authorities and prescribes policies,
procedures, standards, and guidelines for the orderly
disposition of records of the DOE and its management. and
operating contractors.
DOE 2200.4, ACCOUNTING OVERVIEW, of 3-31-88, which establishes
accounting policy, principles, and standards, and explains the
administrative control of funds, financial and cost accounting,
and the financial reporting system in accordance with Government
regulations and generally accepted accounting practices.
DOE 2200.6, FINANCIAL ACCOUNTING, of 10-24-88, which sets forth
the general uses and total dollar and other financial
limitations for GPP funding.
DOE 4300.1C, REAL PROPERTY MANAGEMENT, of 6-28-92, which
establishes Departmentwide policies and procedures for the
acquisition, use, inventory, and disposal of real property and
interests therein.
DOE 4300.2B, NON-DEPARTMENT OF ENERGY FUNDED WORK, of 7-16-91,
which establishes DOE work for others policy.
DOE 4320.1B, SITE DEVELOPMENT PLANNING, of 1-7-91, which
establishes policies and assigns responsibilities and
authorities for the planning and development of DOE sites.
Vertical line denotes change.
I All Departmental Elements Office of Organization, Resources
and facilities Management
2
g.
h.
i.
j.
k.
l.
DOE 4700.3 Chg 1
11-16-92
DOE 4700.1, PROJECT MANAGEMENT SYSTEM, of 3-6-87, which
establishes the DOE project management system and provides
implementing instructions, formats and procedures.
DOE 5000.1B, INSTITUTIONAL PLANNING BY MULTIPROGRAM LABORATORIES,
of 4-9-92, which establishes the Institutional Planning Process
for multiprogram laboratories.
DOE 5100.3, FIELD BUDGET PROCESS, of 8-23-84, which provides
guidance and requirements to field offices for preparation of
field GPP budget data.
DOE 5440.1D, NATIONAL ENVIRONMENTAL POLICY ACT COMPLIANCE PROGRAM,
of 2-2-91, which establishes responsibilities and procedures to
implement the National Environmental Policy Act (NEPA) of 1969.
DOE 6430.1A, GENERAL DESIGN CRITERIA, of 4-6-89, which provides
general design criteria for use in the acquisition of DOE
facilities.
Public Law 99-145, Department of Defense Authorization Act, Sec.
1522, Limits on GPPs, which establishes an overall limit on the
total estimated cost for any GPP at $1.2 million.
4. OBJECTIVES.
a.
b.
c.
d.
To ensure continued integrity and accountability throughout DOE in
the application and use of GPP funds, which are a critical part of
DOE’s capability in meeting its requirements for safe and reliable
facilities operation.
To ensure program offices and field organizations have the needed
flexibility to respond to rapidly changing facility conditions,
regulatory requirements, and mission requirements.
Section 2
To establish the framework for estimating future GPP requirements,
and preparing budget requests for funds that are sufficient to
meet mission and regulatory requirements and prevent undue plant
deterioration.
To establish policies and procedures to ensure that GPP funds are
utilized to meet the most important needs, and that needs are
determined and their priorities are established through systematic
procedures and listings and specific project review and approval
mechanisms as required.
Vertical line denotes change.
DOE 4700.3 Chg 1
11-16-92
3
5. DEFINITIONS.
I
a. Capital Equipment. Equipment that meets the capitalization
criteria specified in Chapter VI, DOE 2200.6.
b. Cognizant Secretarial Officer. A line manager Secretarial Officer
of DOE who has responsibility for overall management and oversight
of a site. In the case of multiprogram laboratories, these
responsibilities are discussed in DOE 5000.1B.
c. Facility Management. For purposes of this Order, facility
management consists of all actions that are necessary to plan,
construct, maintain, and dispose of the facilities at a DOE site.
It includes: site development planning, design management, con-
struction/project management, facility utilization planning and
management, utilities management, energy management, maintenance
management, real property management, and workspace management
planning.
d. Field Element. Any first-level organization located outside the
Washington, DC, metropolitan area. For purposes of this Order,
“first level” includes Managers of DOE Field Offices (excluding
Richland and Savannah River) and Administrators of Bonneville and
Western Area Power Administrations.
e. General Plant_Projects. Defined on page VI-20, paragraph 2h, DOE
2200.6, as miscellaneous minor new construction projects of a
general nature, the total estimated costs of which may not exceed
the congressional authorization of $1.2 million per project. GPP
are necessary to adapt facilities to new or improved production
techniques, to effect economies of operations, and to reduce or
eliminate health, fire, and security problems. These projects
provide for design or construction (or both); additions; and
improvements to land, buildings, and utility systems, and they may
include the construction of small new buildings, replacements or
additions to roads, and general area improvements.
f. Landlord Program. The Headquarters program required to support
and maintain the site-specific infrastructure, or multiprogram
capabilities at a DOE site. This support includes budgeting for
and funding of program GPP.
Vertical line denotes change.
4 DOE 4700.3
9-16-91
g. Line Item Construction Projects. Line item projects are those
construction projects that are submitted for funding as separately
identified projects, and are specifically reviewed and approved by
Congress. They are not subject to dollar ceiling limits and may
exceed the GPP limits. Line item projects are used to provide
land and/or facilities for the long-term programmatic, support and
administrative needs of DOE sites. Examples include programmatic
buildings, support and service buildings, utilities, and roads.
h. Maintenance and Repair. Activities that neither materially add to
the value of nor appreciably prolong the life of plant and
equipment, but merely keep it in an ordinary efficient operating
condition.
(1) Maintenance. The recurring day-to-day work that is required
to maintain and preserve property in a condition suitable
for it to be utilized for its designated purpose.
Section 3
(2) Repair. The restoration or replacement of a detoriorated
item of property and capital equipment, such that it may be
utilized for its designated purpose.
6. BACKGROUND.
a. GPP funding plays a critical role in the ability of DOE to manage
its facilities, and to provide for safe and reliable facility
operations. Requirements for GPP are often impossible to predict
during budget formulation as is the identification of the specific
projects that will require the highest priority attention.
Because of the highly flexible nature of the GPP funding mechan-
ism, it is essential that DOE carefully review and account for the
use of these funds. Therefore, a part of the underlying intent of
this Order is to ensure that the expenditure of GPP funds is
carefully budgeted and accounted for so that DOE’s needed
management flexibility in this area will be continued.
b. In order to implement Departmentwide policy regarding the
budgeting and use of GPP funding, uniform definitions and project
documentation are required. This Order provides these as well as
procedures for executing the responsibilities listed herein.
DOE 4700.3 Chg 1
11-16-92
5
7. POLICY. Various program and field organizations have many review and
management control mechanisms in place for GPP funds and projects. The
provisions contained in this Order are meant to constitute only the
minimum requirements for managing GPP funds and executing projects.
Additional measures, wherever warranted, are encouraged. It is policy
that:
a. GPP funds will be used only for the following types of projects.
Cost of all projects will include such items as related site
preparation, excavation, filling and landscaping or other land
improvements; design of the facility; utilities; equipment
installed in and made part of the facility; and initial moveable
equipment (e.g., machine tools, laboratory and office furniture,
and equipment necessary to outfit a facility for operation).
(1) Conversion. A major revision of a facility that changes the
functional purposes for which the facility was originally
designed or used.
(2) New Construction. The erection, installation, or assembly
of a new plant facility as well as the construction of
additions, expansions, improvements, and extensions to
existing facilities.
(3) Replacement. A complete reconstruction of a property record
unit, which has deteriorated or has been damaged beyond the
point where its individual parts can be economically
repaired.
b. All activities shall only be for facilities required in the
performance of DOE missions and functions, including institutional
requirements. Identified projects should be given priority based
upon problem severity and mission importance. Funds intended for
GPPs must meet all criteria defined in Chapter VI, DOE 2200.6.
The GPP funds shall not be used for alterations (the work required
to adjust interior arrangements or other physical charac-
teristics of an existing property record unit so that it may be
more effectively adapted to or utilized for its designated
purpose. It will not result in a betterment to the record unit).
c. GPP funds shall not be used for uneconomical projects, i.e., those
not having a favorable cost benefit; for projects with low mission
or institutional priority; for introducing large new missions to a
site; or for any other kind of project, which could be construed
as diminishing congressional prerogatives.
Vertical line denotes change.
DOE 4700.3
9-16-91
6
d.
e.
f.
g.
h.
Section 4
i.
j.
Operating funds shall be used for normal facility maintenance and
repair activities including replacement of a retirement unit.
However, repairs which involve the replacement of a retirement
unit must be capitalized in accordance with established
procedures.
GPP funds shall not be used in incremental segments to partially
complete larger facilities. Each project shall result in a
complete and usable facility.
Departmentwide elements shall recognize the need for GPP funds to
accommodate regulatory or mission changes, and provide the capa-
bility for minor, new construction as a part of the annual budget
process. In executing the GPP budget, balanced attention shall be
given to ensure that new (obstruction and other capital
expenditure requirements are satisfied.
To ensure that the best use is made of these funds, the field
organizations shall each maintain a backlog listing of GPPs and
shall incorporate these projects into a prioritized, but contin-
ually evolving and changing multiyear plan, which extends beyond
the current year to, at least, the end of the budget year.
For an individual GPP, design can be funded and begun in 1 year,
and follow-on construction funded and started in the same or a
succeeding year. However. the construction of any project must be
completed as early as possible. The cognizant field element must
maintain controls to ensure compliance with the GPP dollar limit,
regardless of funding year. (See page VI-20, paragraph 2h,
DOE 2200.6)
A Project Construction Directive Authorization, DOE-CH Form 314,
attached, iS required for each project. These project authoriza-
tions shall contain signature approval of the DOE or contractor
official authorizing each project.
The approval of the appropriate DOE official shall be obtained
prior to the start of design or the commitment of funds for each
GPP project estimated at over 25 percent of the GPP overall limit
(currently $300 thousand based on the GPP overall limit of $1.2
million). Each such project must be approved specifically by the
manager of the cognizant field element. The program office or
field element may establish limits lower than the maximum of 25
percent of the GPP overall limit. GPP projects estimated at up to
a maximum 25 percent of the GPP overall limit (currently $300
7DOE 4700.3
9-16-91
k.
l.
m.
n.
o.
thousand) may be approved by the DOE area/site office or the
management and operating (M&O) contractor, with notification to the
DOE official designated by the cognizant Headquarters or field
element. If a project includes new construction that exceeds $1
million it must be approved before design begins by the Program
Secretarial Officer that budgeted the funds.
In cases where it appears that the DOE Field Office or area or site
office GPP approval level (25 percent of the GPP overall limit or
lower) will be exceeded, work shall be discontinued pending review and
approval by the cognizant DOE official.
All GPP funds shall be accurately tracked and accounted for by
individual GPPs. Carryover of GPP Funds from 1 year to the next be
kept to a minimum. The site and/or the DOE Field Office shall
maintain adequate project records as required by DOE 1324.2A.
Minimization of carryover is meant to be within the constraints
imposed by timely receipt of GPP funds.
All dollar, funds usage, project approval, and other limits specified
in this Order will be strictly adhered to. The correct accounting,
segregation, project authority, and application of GPP funds shall be
subject to routine periodic verification.
Section 5
Before actual costs exceed the overall dollar GPP limit, work shall
cease and the circumstances shall be reported immediately to the
cognizant program official and the Office of Chief Financial
Officer (CR-1).
When considering a request to waive constraints imposed by this Order,
the Secretary of Energy will consider all the circumstances and
conditions. This review may include the purpose of the project, the
adequacy of the project planning, and the quality of DOE management
over the project. The Secretary’s action on waivers, with supporting
documentation, shall be forwarded to the cognizant DOE element for
p. All Headquarters program offices shall budget:
(1) For the sites and/or
responsibility.
facilities for which they have
(2) Sufficient GPP funds such that GPP backlog can be reduced.
8 DOE 4700.3
9-16-91
(3) Sufficient and timely line item funding such that the most
economical choices concerning project size can be made.
q. Complete financial and other appropriate records shall be
maintained on all GPP projects as required for proper management
and control.
8. RESPONSIBILITIES.
a. The Secretary.
(1) Resolve disputed issues that cannot be settled at lower
levels.
(2) Issue written waivers to this Order as may be required to
accomplish certain unique missions.
b. Cognizant Secretarial Officers.
(1)
(2)
(3)
(4)
(5)
(6)
(7)
Budget GPP funds needed for programmatic facilities and for
the multipurpose sites and facilities for which they have
landlord responsibility.
Review field performance in tracking and monitoring GPPs and
funds. Assure that the use of non-DOE funds (e.g., work for
others projects) for GPPs are managed by field elements in
accordance with DOE 4300.2B.
Budget sufficient and timely line item funding such that the
backlog of GPP is reduced and the most economical choices can
be made concerning project size.
Approve those GPP new construction projects which exceed
$1 million.
Carry out line management responsibilities and, along with
the Director of Administration and Human Resource Management
(AD-1), review field implementation of this Order.
Ensure that appropriate NEPA review is undertaken early in
project planning.
Develop and disseminate detailed procedures as required for
implementation of this Order.
9
DOE 4700.3
9-16-91
c. Heads of Field Elements. The following responsibilities may, at the
option of a responsible DOE Field Office, be delegated to an area
office or site office reporting through the DOE Field Office. For
those field elements (other than DOE Field Offices) that do not report
through a DOE Field Office, the cognizant Headquarters program office
will
(1)
(2)
(3)
(4)
(5)
(6)
(7)
perform these responsibilities.
Determine the amounts of GPP funding required for new
construction and other capital expenditures.
Submit budgets to the appropriate program office for the
necessary GPP funds to accomplish programmatic and support
requirements.
Review and approve those GPPs that exceed the site GPP approval
limit (maximum is 25 percent of the GPP limit).
Forward to the Program Secretarial Officer, who would provide
the funds, new construction category GPPs that exceed $1
million.
Review the plans for GPP expenditures at least quarterly and
assure that priorities are consistent with DOE policies, are
mission essential, and are consistent with site development,
institutional, and program plans.
Section 6
Keep and, at least quarterly, review financial and other
appropriate records to ensure that the GPP limit is not exceeded
for any individual project.
At the direction and under the supervision of the cognizant
Secretarial Officer, if appropriate, conduct NEPA reviews and
prepare NEPA documents.
d. Chief Financial Officer CCR-1).
(1) Maintain Departmental financial records on all GPP funds.
(2) Review annual GPP budget submissions.
(3) In those instances where it appears that the overall GPP limit
of $1.2 million may be exceeded, review individual circumstances
surrounding each instance, evaluate any available funding
options, and advise as to appropriate follow-on actions.
10 DOE 4700.3
9-16-91
e. Director of Administration and Human Resource Management(AD-1).
(1) Evaluate the budgeting and application of GPP funds through
review and analysis of the GPP submissions from each field
location, and the crosscut maintenance budget, as required by
DOE 5100.3, in the Controller’s annual Field Budget Calls.
(2) Provide an annual analysis of proposed GPP levels to CR–1 and
the program offices in time to support the Internal Review
Budget process.
(3) Maintain GPP management policy and, in conjunction with the
cognizant program offices, perform reviews of field
implementation of this Order.
f. Assistant Secretary for Environment, Safety and Health (EH-1).
(1) Conduct independent reviews of the conformance to laws,
regulations, and DOE Orders related to environment, safety,
and health.
(2) Review and approve NEPA documentation.
9. PROCEDURES.
a. Any new GPP construction over $1 million and any request for
waivers requires approval of the Headquarters program office that
provided the funds or, in the case of shared funding, the site
landlord.
b. Any GPP that exceeds the site approval limit (which can be set no
higher than a maximum of 25 percent of the GPP overall limit of
$1.2 million) must be approved by the Head of the Field Element or
his designated representative, or in the case of offices reporting
directly to Headquarters, the Headquarters program office
performing the function. Below this level, field-developed
approval procedures may be used.
c. Headquarters offices will consider current estimates at completion,
priorities, justification for approval, and other relevant
information when reviewing field requests. Headquarters approvals
will normally be processed and returned to the field within 30
days.
DOE 4700.3 Chg 1 11 (and 12)
11-16-92
d. If, during the process of project development, the design phase,
when bids have been opened on a project, or during construction,
the actual or estimated cost exceeds the existing approval
authority, work shall be stopped until such time as the
appropriate approval is obtained.
e. For the purpose of budget planning and project preparation, all
GPP work will be categorized as New Construction (which includes
erection, installation, and assembly of new free standing facili-
ties, as well as construction of additions, expansions, and
replacements of existing facilities) and Other Capital Expendi-
tures (which includes major conversions of existing facilities).
For budget preparation and crosscut/maintenance budget submittals,
the categories specified in DOE 5100.3, should be utilized.
f. For projects that contain work in both of the above categories,
the dollar amount in each category shall be separately listed on
the project directive authorization form.
Section 7
g. In building their annual GPP budget requests, field elements will
consider new construction and other capital expenditure
requirements in arriving at the total amount of their request.
h. Field elements will utilize the Project Construction Directive
Authorization form shown in Attachment V-1, DOE 4700.1, modified
for local use, to request approval. On the back of this form, or
in a one page attachment, in addition to the project description,
a one paragraph justification for the project will be included.
The adequacy of this project justification paragraph is critical
to the project's approval.
i. On occasion, it may be necessary and appropriate to use GPP funds
for minor land acquisition projects (fee and permanent easement
interests) where the land acquisition is not associated with a
line-item project. In those cases, it will be necessary to
identify in the appropriate GPP Construction Project Data Sheets
(see page II-11, paragraph 5c, DOE 5100.3, for detailed prepara-
tion procedures) that a portion of the funds will be used for land
acquisition. Language should be as specific as possible at the
time the Construction Project Data Sheets are prepared, but need
not identify specific parcels nor estimated values of the prop-
erty. If possible, an estimate should be provided of the total
amount expected to be spent for land acquisition out of the GPP
funds requested on the specific Construction Project Data Sheets.
BY ORDER OF THE SECRETARY OF ENERGY:
DOLORES L. ROZZI
Director of Administration
and Management
Vertical line denotes change.
DOE 4700.3
9-16-91
Attachment I
Page 1
PROJECT CONSTUCTION DIRECTIVE AUTHORIZATION FORM
Attachment I
Page 2
DOE 4700.3
9-16-91
PROJECT CONSTRUCTION DIRECTIVE AUTHRIZATION FORM
(continued)