DOE O 4700.1 Chg 1, Project Management System
Functional areas: Project Management
Canceled by DOE O 430.1.
Superseded By:
DOE O 430.1, Life Cycle Asset Management on Jul 09, 1996
Version history and related documents
Superseded by
A newer version replaces this document.
- DOE O 430.1Life Cycle Asset Management (Jul 09, 1996)
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
3-6-87
Change 1: 6-2-92
PROJECT MANAGEMENT SYSTEM
1.
2.
3.
4.
PURPOSE. To establish the Department of Energy (DOE) project management
system and provide implementing instructions, formats, and procedures,
and to set forth the principles and requirements which govern the
development, approval, and execution of DOE’s outlay program
acquisitions as embodied in the Project Management System (PMS).
APPLICATION TO CONTRACTS. The provisions of this Order are to be
applied to covered contractors and they will apply to the extent
implemented under a contract or other agreement. A covered contractor
is a seller of supplies or services involved with Major System
Acquisitions, Major Projects, and Other Projects, as defined at Figure
I-1 on page I-3, and awarded a procurement contract or subcontract. The
term “procurement contract” does not include small purchases. Covered
contractors shall be required to comply with all paragraphs of this
Order except paragraph 10 on page 5.
REFERENCES. See Attachment 1.
POLICY.
a.
b.
c.
It is Department policy to manage all projects in accordance with
this Order. The chapters of this Order provide instructions,
formats, and procedures to implement the project management system.
Where programs/projects of a classified nature are conducted,
procedures will be tailored accordingly.
This Order does not apply to facilities and activities covered under
Executive Order 12344.
Pursuant to the Bonneville Project Act, the Federal Columbia River
Transmission System Act, the Pacific Northwest Electric Power
Planning and Conservation Act, and other statutory authorities, the
Administrator of the Bonneville Power Administration (BPA) is
authorized and directed to provide, construct, operate, maintain,
and improve electric transmission lines and facilities as necessary,
desirable, or appropriate for the purpose of transmitting electric
energy for sale to existing and potential markets. These
authorities are coupled with the Administrator’s responsibility to
ensure the safety, security, and reliability of electric power
Vertical line denotes change
All Departmental Elements Office of Procurement, Assistance
and Program Management
DOE 4700.1 Chg 1
6-2-92
2
5.
marketing and transmission as well as to meet its legal and
contractual obligations. In light of these unique authorities, this
Order shall not apply to BPA.
d. This Order does not alter the procedure outlined in the May 7, 1986
memorandum entitled “Modified Project Management System for the
Western Area Power Administration, Western Area Power
Administration.”
e. Formality and documentation requirements will be significantly
greater for Major System Acquisitions (MSAs) and major projects, but
this fact does not lessen the responsibility for proper planning and
execution of any project. Acquisition Executives, Program
Secretarial Officers and Heads of Field Elements shall ensure that
the project management system is implemented at a proper level in
all projects.
BACKGROUND.
a.
b.
c.
d.
e.
f.
The project management system has evolved as one of the principal
management processes for the Department. The principles, policies,
and procedures for the system were first promulgated in 1978. This
implemented and institutionalized OMB Circular A-109, Major System
Acquisitions, of 4/5/76.
The next step in the evolutionary process of PMS was issuance of a
requirement for decentralization in 1979. This policy brought the
field offices clearly into the process as a full partner in project
management.
Section 2
In 1980, the Acquisition Executive decision process for Major
Projects was delegated to the Program Secretarial Officers.
In 1989 and 1990 the Department emphasized the strengthening of the
project management system.
The project management system, since inception, has been
substantially improved to: (1) simplify the procedures; (2)
streamline the system; and (3) allow for management by exception.
This revision incorporates the following to the extent noted:
(1) SEN-6D-91, Departmental Organizational and Management
Arrangements, added titles to definitions.
(2) SEN-9-89, Federal Manager’s Financial Integrity Act and Audit
Resolution and Followup, of 7-26-89. Added in its entirety to
Chapter IV, Part A.
(3) SEN-1OE-91, Authorities and Responsibilities of the Deputy
Secretary and Under Secretary, of 6-17-91. Updated titles
throughout document.
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
3
(4) SEN-25-90, Strategic Planning Initiative, of 7-24-90. Added to
Chapter II.
(5) SEN-27-90, Strengthening the Department of Energy Project
Management System, of 8-15-90. Incorporated in its entirety
into Chapters I and II.
(6) DOE N 4700.4A, Baseline Change Control Process at the Executive
Level, of 10-31-91. Incorporated in its entirety into Chapter
III.
6. OBJECTIVES.
a. The primary objective of this Order is to assure the application of
sound management principles to provide a disciplined, systematic,
and coordinated approach to project management resulting in
efficient planning, organization, coordination, budgeting,
management, review, and control of DOE projects.
b. The overall objectives of the project management system and this
Order are to facilitate meeting mission needs, aid in achieving and
sustaining excellence in project management, minimize procedural
requirements, and foster the concepts of baseline management,
accountability, and performance assessment.
c. The specific objectives of the project management system are
summarized as follows:
(1)
(2)
(3)
(4)
(5)
(6)
Ensure all projects are based on clearly defined missions and
mission analyses and are developed with clear time-phased goals
and objectives that support program requirements.
Ensure proper coordination by all appropriate line and staff
elements beginning with program or project inception.
Provide a basis for determining priorities among programs and
projects, and, in turn, relate these to various levels of
resource availability.
Promote project execution which achieves tecnnical, schedule
and cost objectives. Technical objectives include safeguards
and security, environment, health, safety, quality assurance
and all programmatic aspects.
Avoid commitment of major resources prior to adequate project
definition.
Provide an overall plan for project execution including
evaluation of project progress in relation to specific
milestones. This plan should also identify the required
Government staffing as well as the responsibility and authority
of project and matrix staff.
Vertical line denotes change
4 DOE 4700.1 Chg 1
6-2-92
(7) Provide visibility on all key decisions and timely feedback for
all levels of management, and maintain accountability and
traceability of management decisions through and across all
levels of the organization with the minimal amount of
procedures and paperwork.
(8) Centralize authority for project approval and for allocation of
resources, and assure line management authority for project
execution and the utilization of resources in that execution.
Section 3
(9) To assure preparation of well planned budgets.
7. DISCUSSION.
a. The magnitude of the Department’s project management task is
formidable. The diverse array of project responsibilities and
activities requires wide familiarity with, and understanding and
working knowledge of scientific, engineering and managerial skills.
These attributes are necessary to assure that projects meet mission
needs, achieve planned technical and management objectives and are
accomplished on schedule, within cost and scope, and that the
projects serve the purposes intended.
b. This Order is the Department of Energy’s primary written reference
for project managers and program managers responsible for project
management.
c. The cost, complexity, and longevity of a multimillion-dollar effort
demands a formal management system, prescribed authorities and
responsibilities, and finite planning and control. These, in turn,
bring to mind project justifications, plans and charters, reporting,
and project review. However, every project effort--regardless of
size and complexity-has certain inherent characteristics.
Every project effort needs several specific ingredients:
(1) Someone in charge and accountable.
(2) An understanding of that person’s responsibility and authority.
(3) A clear definition of the work scope.
(4) An integrated schedule, including milestones (network
schedule).
(5) Supportive budget planning and execution that considers overall
funding availability within the Department as well as program
and project management.
(6) An overall plan for performance.
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
5
(7) Project execution against the plan.
(8) Sufficient reporting to stay aware of progress.
(9) Periodic management review to ascertain project status.
(10) Organizational commitment to successful project completion.
d. The management differences between MSAs, major projects, and other
projects have to do with substance, not intent. In other words, all
projects must be managed; the extent and formality of that
management is the only issue. Attachment 2 summarizes PMS
application.
e. The attached Chapters I through V comprise the Project Management
System.
8. DEFINITIONS. See Attachment 3.
9. RESPONSIBILITIES.
a.
b.
c.
d.
e.
Acquisition Executive and the Director of Procurement, Assistance
and Program Management, jointly determine and approve changes or
additions to the policies and procedures in the project management
system.
The Associate Director for Program/Project Management and Control
through the Director of Program/Project Management, is responsible
for initiating and updating the guidance for the project management
system, for monitoring its implementation, and for review and
concurrence of all reporting requirements.
Heads of Headquarters Elements assure that the provisions of this
Order, which apply to project management functions over which they
have program direction, both in the field and at Headquarters, are
carried out.
Heads of Field Elements carry out all project management functions
delegated or assigned by Program Secretarial Officers as required by
applicable directives.
Heads of Headquarters Elements and Heads of Field Elements (the
senior ranking DOE official at a DOE office location) shall include
in a procurement request package, for each procurement requiring the
application of this directive, the following: (1) identification of
the directive, (2) identification of the specific requirements with
which a contractor or other awardee is to comply, or, if this is not
practicable, identification of the specific paragraphs or other
portions of this directive with which a contractor or other awardee
is to comply, and (3) requirements for the flowdown
this directive to any subcontract or subaward. For
Section 4
of provisions of
application to
Vertical line denotes change
6
DOE 4700.1 Chg 1
6-2-92
awarded management and operating contracts, Heads of Headquarters
Elements and Heads of Field Elements may set forth this information
in a written communication to the contracting officer rather than in
a procurement request package.
BY ORDER OF THE SECRETARY OF ENERGY:
DONALD W. PEARMAN, JR.
Acting Director
Administration and Human
Resource Management
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
Attachment 1
Page 1
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
REFERENCES
DOE 1300.2A, DEPARTMENT OF ENERGY STANDARDS PROGRAM, of 5-19-92, which
establishes general policy guidelines, authorities and responsibilities
for DOE standards programs, use of voluntary consensus standards, and
guidelines for participation in private sector standards organizations.
DOE 1324.2A, RECORDS DISPOSITION, of 9-13-88, which assigns
responsibilities and authorities, and prescribes policies, procedures,
standards, and guidelines for the orderly disposition of Departmental
records.
DOE 1332.1A, UNIFORM REPORTING SYSTEM, of 10-15-85, which establishes and
provides implementing instructions for a uniform system of reporting the
accomplishments under contracts.
DOE 1332.2, UNIFORM REPORTING SYSTEM FOR FEDERAL ASSISTANCE (GRANTS AND
COOPERATIVE AGREEMENTS), of 10-31-83, which establishes and provides
implementing instructions for a uniform system of reporting the
accomplishments under grants and cooperative agreements.
DOE 1360.1A, ACQUISITION AND MANAGEMENT OF COMPUTING RESOURCES, of
5-30-86, which establishes Departmental policies and procedureS for the
acquisition and management of automatic data processing equipment and
resources.
DOE 2200.4, ACCOUNTING OVERVIEW, of 3-31-88, which establishes the
policy, principles, objectives, and responsibilities for Departmental
accounting and reporting in accordance with Government regulations and
generally accepted commercial and industrial accounting principles.
DOE 2200.9A, MISCELLANEOUS ACCOUNTING, of 3-30-89, which provides
Department of Energy (DOE) policy and general procedures for payroll
accounting (does not include payroll processing procedures), travel and
transportation accounting, financial closeout of contract procedures,
grant accounting, and accounting procedures unique to the power marketing
administrations.
DOE 2250.1D, COST AND SCHEDULE CONTROL SYSTEMS CRITERIA, of 6-12-92,
which delineates the requirements, procedures, authorities, and
responsibilities for establishing and documenting uniform standards for
assessing contractor cost and schedule control systems criteria (CSCSC).
DOE 3220.4, CONTRACTOR PERSONNEL AND INDUSTRIAL RELATIONS REPORTS, of
6-4-85, which prescribes policy and procedures, and assigns
responsibilities and authorities for the preparation and submission of
the subject reports.
DOE 4200.1C, COMPETITION IN CONTRACTING, of 1-9-87, which establishes
policies and procedures to assure that competitive procedures are
utilized to the maximum extent practical in the acquisition of personal
property and nonpersonal services.
Vertical line denotes change
Attachment 1 DOE 4700.1 Chg 1
Page 2 6-2-92
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
DOE 4240.1K, DESIGNATION OF MAJOR SYSTEM ACQUISITIONS AND MAJOR PROJECTS,
of 6-23-92, which lists the specific Department of Energy (DOE) projects
which have been designated as major system acquisitions and major
projects in accordance with the references.
Section 5
DOE 4300.16, REAL PROPERTY MANAGEMENT, of 7-1-87, which establishes DOE
policies and procedures for the acquisition, use, and disposal of real
estate or interest therein.
DOE 4320.16, SITE DEVELOPMENT PLANNING, of 1-7-91, which provides the
policy and procedures for site development, facility utilization, and
related planning.
DOE 4330.4A, MAINTENANCE MANAGEMENT PROGRAM, of 10-17-90, which provides
policy and procedures for the establishment of programs for the
maintenance and repair of Departmental property.
DOE 5000.3A, OCCURRENCE REPORTING AND PROCESSING OF OPERATIONS
INFORMATION, of 5-30-90, that sets forth policy, assigns responsibility,
and provides criteria and instructions for a system of reporting
occurrences that have programmatic significance to DOE operations,
analyzing the information reported and disseminating the analysis
results.
DOE 5100.3, FIELD BUDGET PROCESS, of 8-23-84, which provides requirements
and procedures for the preparation and submission of field budget
material for preparation of the Departmental budget.
DOE 5160.1A, REPROGRAMMING, RESTRUCTURING, AND APPROPRIATION TRANSFER
PROCEDURES, of 12-1-86, which establishes the major policies, criteria,
and procedures for initiating reprogramming, restructuring, and
appropriation transfer actions relating to the appropriation accounts of
the Department of Energy.
DOE 5440.1D, NATIONAL ENVIRONMENTAL POLICY ACT COMPLIANCE PROGRAM, of
2-22-91, which establishes procedures to implement regulation 10 Code of
Federal Regulations (CFR) 1021 for use in complying with the National
Environmental Policy Act of 1969 (NEPA), as amended; Executive Order
11514, as amended; as supplemented by the regulations of the Council on
Environmental Quality and DOE guidelines for compliance with NEPA;
including DOE’s “Environmental Compliance Guide,” Volumes I and II.
DOE 5480.1B, ENVIRONMENT, SAFETY, AND HEALTH PROGRAM FOR DOE OPERATIONS,
of 9-23-86, which establishes the environmental protection, safety, and
health programs for the Department of Energy operations.
DOE 5484.1, ENVIRONMENTAL PROTECTION, SAFETY, AND HEALTH PROTECTION
INFORMATION REPORTING REQUIREMENTS, of 2-24-81, which establishes the
requirements and procedures for the reporting of information having
environmental protection, safety, or health protection significant for
DOE operations.
Vertical line denotes change
DOE 4700.1 Chg 1 Attachment 1
6-2-92 Page 3
21.
22.
23.
24.
DOE 5500.2B, EMERGENCY CATEGORIES, CLASSES, AND NOTIFICATION AND
REPORTING REQUIREMENTS, of 4-30-91, which provides for the coordination
and direction of Departmental planning, preparedness, and response to
operational emergencies involving DOE or requiring DOE assistance, in
which there is a potential for personal injury, destruction of property,
theft or release of toxic, radioactive, or other hazardous material which
represent a potential threat, including terrorist threats of acts, to
health, safety, or the environment.
DOE 5500.3A, PLANNING AND PREPAREDNESS FOR OPERATIONAL EMERGENCIES, of
4-30-91, which establishes requirements for the development of DOE site
specific emergency plans and procedures for radiological emergencies
occurring in existing or planned DOE reactors and nonreactor nuclear
facilities.
DOE 5600.1, MANAGEMENT OF THE DEPARTMENT OF ENERGY WEAPONS PROGRAM AND
WEAPON COMPLEX, of 6-27-79, which establishes the policy and procedures
for the management of the Department’s weapons program and weapon complex
and utilization of the weapon complex facilities for nonweapon DOE
activities.
Section 6
DOE 5700.2C, COST ESTIMATING, ANALYSIS, AND STANDARDIZATION, of 11-2-84,
which establishes the policy and responsibilities for developing and
reviewing project cost estimates; preparing independent cost estimates
and analyses; standardizing cost estimating procedures; and improving
overall cost estimating and analytical techniques, cost data bases, cost
and economic models escalation, and cost estimating systems.
DOE 5700.6C, QUALITY ASSURANCE, of 8-21-91, which provides Departmental
policy, sets forth principles, and assigns responsibilities for
establishing, implementing, and maintaining programs of plans and actions
to assure quality of achievement in DOE programs.
DOE 5700.7B, WORK AUTHORIZATION SYSTEM, of 9-24-86, which establishes a
formal process for budget development, authorization, and monitoring of
Departmentally funded work performed at specified contractor facilities.
DOE 6430.1A, GENERAL DESIGN CRITERIA, of 4-6-89, to be implemented in
coordination with the Director of the Office of Administration and Human
Resource Management memorandum of 6-10-81, which establishes policies and
objectives, responsibilities and authorities, procedures, and
requirements for development and maintenance of general design criteria
and their application in the planning and design, or acquisition, of the
Department’s facilities.
DOE/S-00141, “National Energy Policy Plan of October 1983,” which
describes the policies, plans and goals for the Department of Energy.
DOE/MA-0040, “Cost and Schedule Control Systems Criteria for Contract
Performance Measurement, Work Breakdown Structure Guide,” of October
1981.
DOE/MA-0046, “Cost Estimating Manual,” of January 1982, which is a
compilation of DOE cost estimating procedures.
25.
26.
27.
28.
29.
30.
Vertical line denotes change
Attachment 1 DOE 4700.1 Chg 1
Page 4 6-2-92
31.
32.
33.
34.
35.
36.
DOE/MA-0063, Volume 1, “Cost Guide (Economic Analysis),” of January 1982,
which discusses economic analysis in cost estimating.
DOE/MA-0063, Volume 2, “Cost Guide (Standard Procedures for Determining
Revenue Requirements),” of June 1982, which concerns itself with
establishing standards for conducting economic evaluations using revenue
requirements or product cost methodology.
DOE/MA-0063, Volume 3, “Cost Guide (Cost Factors),” of April 1982, which
provides cost, labor, and material information concerning facilities or
systems.
DOE/MA-0063, Volume 4, “Cost Guide (Cost Data and Cost Estimating
Relationships--CER)," of May 1982, which details the methodology for
establishing CER’s on equipment, material, facilities, and modules.
DOE/MA-0063, Volume 5, “Cost Guide (Construction of Economic Escalation
Indices), Of May 1982, which covers the construction and use of price
change indices to be used in estimating and forecasting.
DOE/MA-0154, “Acquisition Regulators Handbook - Source Evaluation,” of
2-86 which provides guidance for carrying out procurement in excess of $5
million.
DOE/PR-0045, “DOE Acquisition/Assistance Guide for Technical Personnel.”
OMB CIRCULAR A-34, “Instructions on Budget Execution,” which applies to
the management of all appropriations, funds, and other authorizations,
except deposit funds.
OMB CIRCULAR A-76, “Performance of Commercial Activities,” of 8-4-83,
which sets forth procedures for determining whether commercial activities
should be performed under contract with commercial sources or using
government facilities and personnel.
Section 7
OMB CIRCULAR A-109, “Major System Acquisitions,” of 4-5-76, which
establishes policies to be followed by executive branch agencies in the
acquisition of major systems.
OMB CIRCULAR A-119, “Use of Voluntary Standards,” of 1-17-80, which
establishes policies to be followed by executive branch agencies in
working with organizations that plan, develop, produce, and coordinate
voluntary standards.
Federal Acquisition Regulations (FAR) of 4-1-84, which establishes
uniform acquisition regulations for use by Federal Agencies.
37.
38.
39.
40.
41.
42.
Vertical line denotes change
DOE 4700.1 Chg 1 Attachment 1
Page 5 (and 6)6-2-92
43. Department of Energy Acquisition Relations (DEAR) of 4-1-84, which
implements the provisions of the FAR.
44. P.L. 95-224, “Federal Grant and Cooperative Agreement Act of 1977,” which
describes the appropriate circumstances for using government contracts
grants or cooperative agreements.
45. P.L. 95-507, “Small Business Investment Act of 1977,” which provides
guidelines for the utilization of small and disadvantaged businesses in
government contracting.
Vertical line denotes change
DOE 4700.1
3-6-87
Attachment 2
Page 1
APPLICATION OF THE PROJECT MANAGEMENT SYSTEM
ELEMENT TO DOE PROJECTS
CHAPTER AND PART OF
ORDER
APPLICATION
MAJOR
SYSTEM MAJOR OTHER
ACQUISITION PROJECTS PROJECTS
(MSA) (MP) (OTHER)
ELEMENT
Acquisition Executive X X
Acquisition Strategy X X O
Advanced Acquisition or
Assistance Plan Projects X X O
I-C
II-E/Attachment II-6
II-E/Attachment II-7
IV-B/Attachment IV-7Annual Report for
General Plant Projects
Architect/Engineer (A/E)
Services
X
X
X
O
X
X
X X V-A
III-ABaseline
Business
X XManagement
Strategy Group II-E/Attachment II-6X X
X V-B/Attachments V-9
& V-10XConceptual Design Report
Configuration Management III-C/Attachments
III-5 & III-6X X
X
X
X
X
O
V-C/Attachment V-C-12Construction Completion Report X X
XX V-AConstruction Manager
X XContingency Management II-D
II-D X XCost Estimating
Cost and Schedule Control
Systems Criteria (CSCSC)
III-F/Attachment
III-F-7X X
O = Optional
X = Required
Attachment 2 DOE 4700.1 Chg 1
Page 2 6-2-92
ELEMENT
APPLICATION
CHAPTER AND PART OF ORDER
MSA MP OTHER
Design Criteria Package X X X V-A/Attachment V-3
Energy System Acquisition
Advisory Board (ESAAB) X O I-C/Attachments I-I & I-2
II-F
II-F
II-F
Environmental Assessment (EA) X X X
X
X
Environmental Compliance Plan X X
Environmental Impact
Statement (EIS) X X
Finding of No Significant
Impact (FONSI )
Independent Cost Estimate
(ICE)
X
X
X
X
X
X X II-F
X II-D
Internal Review Budget X X II-C
Justification of Mission X II-A/Attachment II-1 Need
Mission
Mission
Network
XAnalysis
Requirements
Scheduling
Diagram)
X I-B
X X X I-B
X X
X
X
X
X
X
II-A/Attachment H4(Logic
OMB Budget
Organizational Financial
Plan
X II-C
X II-C
Vertical line denotes change
DOE 4700.1 Attachment 2
3-6-87 Page 3
APPLICATION
ELEMENT CHAPTER AND PART
MSA MP OTHER OF ORDER
Performance Measurement
Program Manager’s Quarterly
Report to the Acquisition
Executive
Project Authorization System
Project Data Sheet
Project Management Plan (PMP)
Project Manager’s Progress
Report
Project Manager’s Quarterly
Supplemental Report, Cost and
Cost-Plus Commitment Chart
Project Manager’s Quarterly
Summary Report, Management
and Construction Manpower
Project Manager’s Quarterly
Summary Report, Progress
Photographs
Section 8
Project Manager’s Quarterly
Summary Report, Project
Activity
Project Plan (PP)
Project Plan Changes
(Baseline Changes)
x
x
x
x
x
x
O
O
o
x
x
x
x
x
x
x
x
x
o
0
o
x
x
x
III-F
IV-B/Attachment IV-8
V-A
II-A/Attachment II-5
II-A/Attachment II-4
IV-B/Attachment IV-1
IV-B/Attachment IV-4
IV-B/Attachment IV-5
IV-B/Attachment IV-6
IV-B/Attachment IV-3
II-A/Attachment II-2
II-A/Attachment II-3
Generic
Attachment 2
Page 4 DOE 4700.1
3-6-87
APPLICATION
ELEMENT CHAPTER AND PART
MSA MP OTHER OF ORDER
Project Reporting
Project Status Review
Project Transition Plan
Project Validation
Quality Assurance
Responsibility Matrix
Safety Analysis Review
(Report-SAR)
Semiannual Status Report
Status of DOE Energy
Management Projects
Summary Project
Performance Report to
Senior Management
Systems Engineering
Test and Evaluation (T&E)
Uniform Reporting System (URS)
Work Breakdown Structure (WBS)
Work Package Authorization
System (WPAS)
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
IV-B
IV-A
II-H
II-C
III-D
II-A/Attachment II-4
II-F
IV-B/Attachment IV-2
IV-B/Attachment IV-2
IV-B/Attachment IV-9
III-6/Attachments III-1 &
III-2
III-B/Attachments III-3 &
III-4
III-F
II-B
II-C
DOE 4700.1 Chg 1
6-2-92
DEFINITIONS
Attachment 3
Page 1
1.
2.
3.
4.
5.
6.
7.
ACCEPTANCE TESTING. The performance of all necessary testing to
demonstrate that installed equipment will operate satisfactorily and
safely in accordance with the plans and specifications. It includes
required hydrostatic, pneumatic, electrical, ventilation, mechanical
functioning and run-in tests of portions of systems, and finally of
completed systems.
ACQUISITION EXECUTIVE. The individual designated by the Secretary to
integrate and unify the project management system and to monitor
implementation of prescribed policies and practices. Approves the
initiation of a major system acquisition (or a selected major project)
and its transition through phases of the acquisition process and other
sub-phases involving major commitments; selects, from among competing
systems, those that are to be advanced to development, demonstration and
production/operations; and authorizes development of a noncompetitive
(single concept) system.
ACQUISITION PROPONENT. The DOE component having the primary
responsibility for research, development, demonstration, production or
operation of a major system acquisition project (to include, when
applicable, the system for its logistic support) which meets
Departmental objectives in carrying out DOE missions.
ACQUISITION STRATEGY. A description contained in the “Justification of
Mission Need” and subsequent Project Plan of the proposed overall DOE
business approach which will be utilized to ensure that the system being
acquired or supported satisfies the approved mission need. Specific
details of individual procurement actions should be made part of the
Advance Acquisition/Assistance Plan in the Project Management Plan.
ADVANCED DEVELOPMENT. The effort guided by the principle that the work
should lead ultimately to a particular application or product. Advanced
development can cut across several scientific disciplines and is
intended to explore focused innovation in a particular area of one or
more energy technologies.
Section 9
AGENCY COMPETITION ADVOCATE. The individual appointed pursuant to the
Competition in Contracting Act of 1984 to promote full and open
competition in the Department’s acquisitions and to challenge barriers
to competition. In DOE, this is the Competition Advocate located in the
Office of Procurement, Assistance and Program Management.
APPLIED RESEARCH. Systematic study directed towards fuller scientific
knowledge or understanding for direct use in fulfilling specific energy
requirements.
Vertical line denotes change
Attachment 3
Page 2
8.
9.
10.
11.
12.
DOE 4700.1 Chg 1
6-2-92
APPORTIONMENT. A distribution by the Office of Management and Budget of
amounts available for obligation in appropriation of fund accounts of
the executive branch. The distribution makes amounts available on the
basis of time periods (usually quarterly), programs, activities,
projects, objects, or combinations thereof. The apportionment system is
intended to achieve an effective and orderly allocation of funds.
APPROVED FUNDING PROGRAM (AFP). The AFP is an internal DOE document
issued by the Office of Budget to program managers and operating
activities, setting forth the funds available for the program release
activity in each appropriation and fund account. The AFP specifies
pertinent legal limitations and funding ceilings applicable to programs,
sub-programs, activities, and elements of expense. The AFP delegates
the authority to program managers to initiate program release documents
for their respective programs. Each allottee will use the AFP in
conjunction with the associated allotment to establish funding ceilings
on the obligational authority available to program managers and
organization elements (formerly referred to as Financial Plans).
ASSESSMENT. A determination of project or system acquisition conditions
based on a review of project cost, schedule, technical status, and
performance in relation to program objectives, approved requirements,
and baseline project plans. Assessments are made by the responsible
managing or advocate program organization or independently by the Office
of Program/Project Management. In all cases, assessments must be based
on knowledge of the actual project status, performance, problems, and
significant development in both the actual execution activities as well
as required institutional approval, licensing, review, and environmental
processes. They may take the form of:
a. Monthly report status ratings of project performance and outlook
prescribed rating categories; or
b. The Acquisition Executive; the Director of the Office of Procurement
Assistance and Program Management; or acquisition proponent review
ratings of project performance and outlook in similar rating
categories; or
c. Detailed evaluations of all project and system parameters prior to
phase change or key resource commitment decisions.
BASELINE. A quantitative expression of projected costs, schedule, and
technical requirements. Baseline establishment should include criteria
to serve as a base or standard for measurement during the performance of
an effort. It is the data plan against which the status of resources
and the progress of a project can be measured.
BASELINE CHANGE CONTROL BOARD. A multi-discipline functional body of
representatives designated and chartered by the appropriate management
level to ensure the proper definition, coordination, evaluation, and
disposition of all changes to project baselines within their chartered
jurisdiction.
Section 10
Vertical line denotes change
3DOE 4700.1 Chg 1 Attachment
6-2-92 Page 3
13.
14.
15.
16.
17.
18.
BASELINE CHANGE PROPOSAL (BCP). The instrument/document prepared to
provide a complete description of a proposed change and its resulting
impacts on project baselines.
BASIC RESEARCH. Systematic, fundamental study directed toward a more
comprehensive scientific knowledge or understanding of subjects bearing
on national energy needs.
BENEFICIAL USE OR OCCUPANCY DATE. The date on which a facility,
portions thereof, or the last piece of principal equipment, is released
for use by others, prior to final acceptance. Nonintegral or subsidiary
items and correction of design inadequacies subsequently brought to
light may be completed after this date. On multiple-facility projects,
beneficial use of the overall project will be the beneficial use date of
the last major building or facility.
CHANGE IN SCOPE. A change in objectives, work plan, or schedule that
results in a material difference from the terms of an approval to
proceed previously granted by higher authority. Under certain
conditions, stated in the approval instrument, change in resources
application may constitute a change in scope. Under contractual
agreement, contracting officers are the only Government personnel
authorized to issue a change order of contract modification to a
contractor/performer, in order to implement a change of scope. A change
in scope may also affect the availability of current year funds until
the proper congressional notification procedures have been executed.
(See Federal Acquisition Regulation (FAR) 43.101 for additional
information.)
COMPONENT. A major organizational subdivision of DOE, usually at the
program or sub-program level.
CONCEPTUAL DESIGN. Conceptual design encompasses those efforts to:
a. Develop a project scope that will satisfy program needs;
b. Assure project feasibility and attainable performance levels;
c. Develop reliable cost estimates and realistic schedules in order to
provide a complete description of the project for congressional
consideration; and
d. Develop project criteria and design parameters for all engineering
disciplines, identification of applicable codes and standards,
quality assurance requirements, environmental studies, materials of
construction, space allowances, energy conservation features, health
safety, safeguards, and security requirements and any other features
or requirements necessary to describe the project.
Vertical line denotes change
Attachment 3 DOE 4700.1 Chg 1
Page
19.
20.
21.
22.
23.
24.
4 6-2-92
CONDITIONAL OR PROVISIONAL ACCEPTANCE. The acceptance of a unit or
facility with a documented listing of the specific testing to be
accomplished or work remaining including the furnishing of any
outstanding submittal of technical and record data, to be completed by
the construction contractor, and on or by what date the actions are
scheduled to be complete.
CONFIGURATION. The functional and/or physical characteristics of
hardware and/or software, as set forth in technical documentation and
achieved in a product.
CONFIGURATION MANAGEMENT. The systematic evaluation, coordination,
approval (or disapproval), documentation, implementation, and audit of
all approved changes in the configuration of a product after formal
establishment of its configuration identification.
Section 11
CONSTRUCTION. Any combination of engineering, procurement, erection,
installation, assembly, or fabrication activities involved in creating a
new facility or altering, adding to, or rehabilitating an existing
facility. It also includes the alteration and repair (including
dredging, excavating and painting) of buildings, structures, or other
real property. This does not involve the manufacture, production,
finishing, construction, alteration, repair, processing or assembling of
items categorized as personal property. (See FAR 36.102 for additional
information.)
CONSTRUCTION COMPLETION DATE. The date on which work normally performed
by construction forces (including installation of equipment by operating
contractors or others) is accepted by the Government. This includes the
completion of all building items, the erection and/or installation of
mechanical units and/or processing equipment and the installation of all
furnishings as required to make a full functioning building, facility,
or process. Correction of minor deficiencies and exceptions may be
accomplished after the recorded date.
CONSTRUCTION MANAGEMENT. Services that encompass a-wide range of
professional services relating to the management of a project during the
pre-design, design, and/or construction phases. (These services are
deemed to be “professional” in accordance with FAR 15.204, Personal or
Professional Services.) The types of services include development of
project strategy, design review relating to cost and time consequences,
value engineering, budgeting, cost estimating, scheduling, monitoring of
cost and schedule trends, procurement, observation to assure that
workmanship and materials comply with plans and specifications, contract
administration, labor relations, construction methodology and
coordination, and other management efforts related to the acquisition of
construction.
Vertical line denotes change
DOE 4700.1 Chg 1 Attachment 3
6-2-92 Page 5
25.
26.
27.
28.
29.
30.
31.
32.
CONTINGENCY. An amount budgeted to cover costs that may result from
incomplete design, unforeseen and unpredictable conditions, or
uncertainties. The amount of the contingency will depend on the status
of design, procurement, and construction and the complexity and
uncertainties of the component parts of the project. Contingency is not
to be used to avoid making an accurate assessment of expected cost.
CONTRACT. A binding legal relationship basically obligating the seller
to furnish personal property or nonpersonal services (including
construction) for which the buyer compensates. It includes all types of
commitments which obligate the Government to an expenditure of funds and
which, except as otherwise authorized, are in writing. In addition to a
two-signature document, it includes all transactions resulting from
acceptance of offers by awards or notices of awards; agreements and job
orders or task orders issued thereunder; letter contracts; letters of
intent; and orders, such as purchase orders, under which the contract
becomes effective by written acceptance or performance. It also
includes contract modifications.
CONTRACT ADVANCE FUNDING. Obligations to a contract or project, to
cover future work or materials not yet ordered. The value of advanced
funding is the difference between uncosted obligation and unfilled
orders outstanding.
CONTRACTING OFFICER. A person designated to enter into and/or review,
modify, or terminate any contracts, financial assistance awards, and
sales contracts and make related determinations and findings.
Section 12
CONTRACTING OFFICER’S TECHNICAL REPRESENTATIVE. The individual in DOE
who is assigned responsibility for overall technical monitoring of a
contract and identified as such in the contract. The contracting
officer’s technical representative monitors the technical work performed
under the contract, evaluates the contractor’s performance, provides the
contractor and the contracting officer with technical guidance, reports
on contract status to DOE program and project management, and recommends
corrective action when necessary.
CONTRACTOR. The term “contractor” is intended to mean and include all
persons, organizations, departments, divisions, and companies having
contracts, agreements, or a memorandum of understanding with DOE.
COST ESTIMATE. A documented statement of costs estimated to be incurred
to complete the project. Cost estimates provide baselines against which
cost comparisons are made during the life of a project.
COST-SHARING CONTRACT. A cost-reimbursable type contract under which
the contractor receives no fee but is reimbursed only for an agreed
portion of its allowable costs. This type of contract is suitable for
those procurements that cover production or research projects which are
jointly sponsored by the Government and the contractor with benefit to
the contractor in lieu of full monetary reimbursement of costs. In
consideration of this benefit, the contractor agrees to absorb a portion
Vertical line denotes change
Attachment 3 D0E 4700.1 Chg 1
Page 6 6-2-92
33.
34.
35.
36.
38.
of the costs of performance. The following illustrate situations in
which this type of contract is generally desirable:
a. Jointly sponsored research and development work with nonprofit
educational institutions or other nonprofit organizations; or
b. Other research and development work where the results of the
contract may have commercial benefit to the contractor.
COSTS TO DATE. Costs incurred to date by the contractor and reported to
DOE. These are recorded as accrued costs. They represent all charges
incurred for goods and services received and other assets required,
regardless of whether payment for the charges has been made. This
includes all completed work and work in process, chargeable to the
contract. Accrued costs include invoices for: (1) completed work to
which the prime contractor has acquired title; (2) materials delivered
to which the prime contractor has acquired title; (3) services rendered;
(4) costs billed under cost reimbursement or time and material
subcontracts for work to which the prime contractor has acquired title;
(5) progress payments to subcontractors that have been paid or approved
for current payment in the ordinary course of business (as specified in
the prime contract); and (6) fee profit allocable to the contract.
DEFINITIVE WORK. The effort on which a contractual agreement for the
dollar value of the effort has been reached.
DELIVERABLE. A report or product of one or more tasks which satisfies
one or more objectives and must be delivered to satisfy contractual
requirements.
DEMONSTRATE. To verify the soundness of the chosen design concept(s) in
an environmentally acceptable manner, the technical and economic
feasibility of new or advanced equipment, and facilities or processes by
designing, constructing, testing, operating and evaluating near-full
scale modules.
DEMONSTRATION. The verification of scale-up, economic and environmental
viability for commercial application, through design, construction,
test, and evaluation of large-scale energy systems in operational
circumstances.
Section 13
37.
DEVELOPMENT. The development and test of systems and pilot plants
judged to be technically and economically desirable as a means of
achieving principal Departmental goals. Engineering development
concerns itself with processes, preproduction components, equipment,
subsystems, and systems. Initiation of work in this category is
dependent upon successful demonstration of technical feasibility and
economic, potential during the technology phase.
Vertical line denotes change
DOE 4700.1 Chg 1 Attachment 3
6-2-92 Page 7
39. DEVIATION. A specific, before-the-fact, written authorization to depart
from a particular performance or design requirement of a contract,
specification, or referenced document. A deviation differs from an
engineering change, in that, an approved engineering change requires
corresponding revision of the documentation defining the affected
product, whereas a deviation does not contemplate revision of the
applicable specification or drawing.
40.
41.
42.
43.
44.
DIRECT COST. Any cost that can be specifically identified with a
particular project or activity, including salaries, travel, equipment,
and supplies directly benefiting the project or activity.
DIRECTED CHANGE. A change imposed on a project(s), with direction to
implement, which affects one or more of the project’s (projects’)
baselines. Examples of directed changes include, but are not limited
to:
a.
b.
Changes to approved budgets, or funding; and
Changes resulting from DOE policy directives and regulatory or
statutory requirements.
ENGINEERING CHANGE. An approved change to controlled identification
documentation. An Engineering Change Proposal (ECP) is a recommended
Engineering Change (EC). There are typically two classes of EC’s:
a. Class 1. Changes of configuration which affect the Departmental
interest and require approval from the appropriate approval
authority or designated representative. Class 1 engineering changes
are those which affect: (1) technical baseline requirements and/or
(2) nontechnical contractual provisions such as fee, incentives,
cost, schedule, guarantees, or deliveries.
b. Class 2. Changes to a product which do not affect any of the Class
1 engineering change requirements. The Department’s approval prior
to implementation is not required, although such changes are subject
to post-facto classification review by the project office. Other
distinctions may be made at the discretion of the project manager.
ENGINEERING DEVELOPMENT. Systematic use of the knowledge and
understanding gained from research and technology development to achieve
the detailed design, construction and test for performance,
producibility and reliability of energy system prototypes, pilot plants,
and research facilities.
ENVIRONMENT(AL). Air and water quality, land disturbances, ecology,
climate, public and occupational health and safety, and socioeconomic
(including nonavailability of critical resources and institutional,
cultural, and aesthetic) considerations. For conciseness, these are
normally referred to as environment, safety and health considerations.
Vertical line denotes change
Attachment 3 DOE 4700.1 Chg 1
Page
45.
46.
47.
48.
49.
50.
51.
8 6-2-92
FACILITIES. Buildings and other structures; their functional systems
and equipment, including site development features such as landscaping,
roads, walks, and parking areas; outside lighting and communications
systems; central utility plants; utilities supply and distribution
systems; and other physical plant features.
Section 14
FIELD OFFICE (FO). The new designation for the nine major Departmental
offices responsible for day-to-day management of designated functional
activities.
FINAL ACCEPTANCE. A written statement by the contracting officer or
designee that the work performed by the construction contractor has been
accepted as being in accordance with approved plans and specifications.
The operating contractor should also be included in the final
acceptance, if applicable, indicating acceptance of the facilities as
constructed and the date the facilities are to be occupied or available
for the use of operating contractor.
FIXED PRICE CONTRACTS. Fixed price contracts provide for a firm price
or, under appropriate circumstances, may provide for an adjustable price
for the supplies or services that are being procured. In providing for
an adjustable price, the contract may fix a ceiling price, target price
(including target cost), or minimum price. Unless otherwise provided in
the contract, any such ceiling, target, or minimum price is subject to
adjustment only if required by the operation of any contract clause
which provides for equitable adjustment, escalation, or other revision
of the contract price upon the occurrence of an event or a contingency.
FORECAST. The DOE project management office’s most current performance
projection for cost, schedule, and scope.
GENERAL PLANT PROJECTS (GPP). Congress has recognized DOE’s need to
provide for miscellaneous construction items which are required during
the fiscal year and which cannot be specifically identified beforehand.
Congress provides, annually, an amount for these purposes under the
title of General Plant Projects.
GENERAL PURPOSE FACILITIES PROJECTS. Line item construction projects
estimated to cost greater than $1.2 million and which are required to
support the long-term administrative and technical needs of DOE-operated
laboratories and facilities. Examples of general purpose facilities
projects are light or heavy laboratories, administrative offices,
machine shops, steam plants, electrical utilities, roads, railroads, and
warehouses. Multiprogram general purpose facilities are restricted to
general purpose facilities projects at the multiprogram
laboratories/site where no one program will use more than approximately
60 percent of the planned facility.
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
Attachment 3
Page 9
52. GOVERNMENT ESTIMATES. Estimates are used to determine the
reasonableness of competitive bids received in connection with formally
advertised construction contracts, and serve as a control in evaluating
cost and pricing data in negotiated contracts. Normally, the Title II
design estimate, after being reviewed and approved by the Government, is
the basis for the Government estimate. However, the services of an
operating contractor, architect-engineer, cost-plus-fixed-fee
construction contractor (with respect to subcontracts), or construction
manager may be used appropriately to prepare, review, or revise the
Government estimate prior to Government approval (refer to FAR 36.203).
Cost-type contractors shall be required to follow cost estimate
procedures when subcontracting for construction services. Government
review and approval of the Government estimate is not required when the
estimate is within the limits established by the Government’s approval
of the cost-type contractors procurement system. The specifics of a
Government estimate vary with the size and type of contract.
Section 15
53. INCURRED COSTS. Costs are applied to the performance of the project.
All costs incurred for a project are reported whether they arise from
payments, cost accruals, or transfers of costs from other DOE locations
or Federal agencies. Any time costs are incurred by cost-type
contractors, the amount will be included in that period. Incurred costs
also comprise payments made or due to date, including any retained
percent-ages, and lump-sum and unit price contracts based on payment
estimates approved by the contracting officer and designated
representative for the purpose of making the progress or final payments
on work performed to date. Costs shall not be accrued on the basis of a
percentage of physical completion, unless the amounts of such costs are
approved by the contracting officer or his or her designated
representative as progress or partial payments.
54. INDEPENDENT ASSESSMENT. An assessment, made outside the normal advocacy
chain, of a project’s status or condition. In the project management
system, it is made by the Office of Program/Project Management in its
role of independent monitoring. It will consist of independent
evaluation of all pertinent factors in order to provide a condition
rating or detailed analysis of the project or system situation.
Independent assessments will typically be provided in conjunction with
Headquarters reporting to senior DOE management; advisory board decision
reviews; or other purposes associated with the program planning and
budgeting system, acquisition or other DOE management control and
direction processes. These independent evaluations must be based on
knowledge of the actual project and related institutional matters. The
Office of Program/Project Management will obtain this knowledge through
reports from the project management and program organizations; conduct
of field and Headquarters reviews with the program organization, the
Departmental managing office and principal contractors; and direct
communication and discussion of project matters with the DOE managing
and program offices.
Vertical line denotes change
Attachment 3 DOE 4700.1 Chg 1
Page
55.
56.
58.
60.
61.
62.
10 6-2-92
INDEPENDENT COST ESTIMATE. A documented cost estimate that has the
express purpose of serving as an analytical tool to validate, cross-
check, or analyze estimates developed by proponents for a project. An
independent cost estimate also serves as a basis for verifying risk
assessments. It is usually performed by an independent contractor.
57.
INDIRECT COST. A cost incurred by an organization for common or joint
objectives and which cannot be identified specifically with a particular
project or activity. See 10 CFR 600.
INSPECTION. The survey of a unit, facility or area to determine overall
compliance with contract drawings and specifications. It may vary from
inspection of detailed items to extensive testing of operating equipment
(which must be provided for in the contract). It may also serve in
making a determination of the adequacy of the design effort. It
includes a preliminary inspection to fix the number of work items
remaining to be completed (list of exceptions or “punch list”), and a
final inspection to accept the completed construction. (See Title III
Services)
LEAD PROGRAM SECRETARIAL OFFICER (LPSO). The individual assigned line
management responsibility and accountability for Headquarters and field
operations and to which one or more multiprogram field offices report
directly.
Section 16
LIFE CYCLE COST (LCC). The sum total of the direct, indirect,
recurring, nonrecurring and other related costs incurred or estimated to
be incurred in the design, development, production, operation,
maintenance, support and final disposition of a major system over its
anticipated useful life span. Where system or project planning
anticipates use of existing sites or facilities, restoration, and
refurbishment costs should be included.
LINE ITEM PROJECTS. Projects which are specifically reviewed and
approved by Congress. Projects with a total project cost greater than
$1.2 million are categorized as line item projects.
LONG LEADTIME PROCUREMENT ITEMS. Those items of equipment and/or
construction materials that require an order date prior to the estimated
physical construction start to assure availability at the time needed so
as not to delay the construction performance.
59.
MILESTONE. An important or critical event and/or activity that must
occur in the project cycle in order to achieve the project objective(s).
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
Attachment 3
Page 11
63. MISSIONS.
64.
66.
a. Responsibilities assigned to the Department of Energy for meeting
national needs. Agency missions are defined by the Comptroller
General of the United States in Budgeting Definition s, November
1975, as:
“Those responsibilities for meeting national needs assigned to
a specific agency. Agency missions are expressed In terms of
the purpose to be served by the programs authorized to carry
out functions or subfunctions which, by law, are the
responsibility of that agency and its component organizations.
(See Section 201 of the Budget and Accounting Act, 1921, as
amended.)”
b. Additionally, Section 601(i) of the Congressional Budget Act of 1974
(Public Law 93-344) requires that:
“The Budget. ..” shall contain a presentation of budget
authority, proposed outlays, and descriptive information in
terms of:
(1) a detailed structure of national needs which shall be
used to reference all agency missions and programs;
(2) agency missions; and
(3) basic programs.
“To the extent practicable, each agency shall furnish
information in support of its budget requests in accordance
with its assigned missions in terms of Federal functions and
subfunctions, including mission responsibilities of component
organizations, and shall relate its programs to agency
missions.”
MISSION ANALYSIS. Continuing analysis of assigned mission areas,
reconciled with overall program capabilities technological
opportunities, priorities, and resources that are involved.
65. MISSION AREA ASSIGNMENT. Assignment to a Program Secretarial Officer,
by the Secretary, of the responsibility for the formulation and conduct
of programs to carry out functions or subfunctions which by law and
Administration policy are within the mission responsibilities of the
Department.
MISSION NEED. A required capability within DOE’s overall purpose,
including cost and schedule considerations. When the mission analyses,
or studies directed by appropriate executive or legislative authority,
identify a deficiency in existing capabilities or an opportunity, this
will be set forth as justification for purposes of system acquisition
approvals, planning, programming, and budget formulation.
Vertical line denotes change
Attachment 3 DOE 4700.1 Chg 1
Page
67.
68.
69.
70.
12 6-2-92
OPERATIONAL DATE.
Section 17
a. Production Plant. The date when operations personnel introduce feed
materials into the process equipment with the intent to produce the
design plant product (excludes functional testing). For gaseous
diffusion plants, term “on-stream date” is synonymous with operation
date.
(1) Initial Operational Date. If the facility is a multiple unit
type, the date on which feed materials are introduced into the
first of a number of process or production units.
(2) Complete Operational Date. If the facility is a multiple unit
type, the date on which feed materials are introduced into the
last of the process of production units.
b. Reactor.
(1) Initial Operational Date. The date on which initial
criticality is achieved.
(2) Complete Operational Date. The date on which tests have been
completed and permission granted by the designated authority to
go to full power for purposes of normal operation.
c. Accelerators. The date on which operations personnel inject a
subatomic particle into the accelerator and achieve an initial
accelerated beam.
d. Other. Normally, the date on which a building or facility is first
occupied and functions in accordance with its intended purpose.
However, on development projects it refers to completion of the
first major milestone in output.
ORIGINAL ESTIMATE. The first total estimated and total project cost
that are shown: (1) in a project data sheet submitted to the Congress
for line item projects; or (2) in a project data sheet submitted to OMB
for contingency type projects; or (3) in the initial authorization for
general plant, operating funded, equipment funded, or other contingency-
type projects.
ORIGINAL SCHEDULE DATES. The start and finish dates of design,
construction, procurement, and operation submitted in conjunction with
the original estimate or in the first approved schedule.
PHYSICAL CONSTRUCTION START. For purposes of reporting construction
progress, the date on which work at the site physically starts,
including work on site preparation, temporary construction and any earth
moving. The start date of construction of permanent facilities should
also be indicated.
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
Attachment 3
Page 13
71.
72.
73.
PLANNING ESTIMATES. Developed for each project at the time of project
identification. Since these are developed prior to conceptual design,
they are order of magnitude only and have the least amount of accuracy
and lowest confidence level. Care should be exercised in these
estimates to assure that the order of magnitude is correct, since a
tendency exists to avoid changing this estimate, particularly upward,
once established.
PLANT ENGINEERING AND DESIGN FUNDS. Appropriated by Congress at the
request of the Department for the performance of Title I and Title II
design prior to authorization and appropriation of construction funds
for a project. Plant engineering and design funds are limited to
requests for projects which will receive high priority in future year
budget submittal. Completed conceptual design is a prerequisite for
allocation of plant engineering and design funds.
Section 18
PRELIMINARY DESIGN (TITLE I). Continues the design effort utilizing the
conceptual design and the project design criteria as a basis for project
development. Title I design develops topographical and subsurface data
and determines the requirements and criteria which will govern the
definitive design. Tasks include preparation of preliminary planning
and engineering studies, preliminary drawings and outline
specifications, life-cycle cost analysis, preliminary cost estimates,
and scheduling for project completion. Preliminary design provides
identification of long lead procurement items and analysis of risks
associated with continued project development. For a detailed
description of the services provided during preliminary design, see
Department of Energy Acquisition Regulation (DEAR) 936.605c and
952.236.70.
74.
75.
PRODUCT DATA REQUIREMENT. A contract requirement which directs
contractors to collect, organize, prepare, maintain, transmit, deliver,
or retain information incident to the design, development, production,
operation, preservation, maintenance, or repair of contract end items.
Product data includes engineering drawings, product specifications and
standards, part breakdown lists, catalog item physical qualities and
characteristics, preprocurement data, test plans and reports, and other
such data.
PROGRAM. An organized set of activities directed toward a common
purpose, or goal undertaken or proposed in support of an assigned
mission area. It is characterized by a strategy for accomplishing a
definite objective(s), which identifies the means of accomplishment,
particularly in quantitative terms, with respect to manpower, materials
and facilities requirements. Programs are typically made up of
technology base activities, projects, and supporting operations.
Vertical line denotes change
Attachment 3 DOE 4700.1 Chg 1
Page 14 6-2-92
76.
77.
78.
80.
81.
PROGRAM ASSESSMENT. A determination of program condition based on a
review of cost, schedule, technical status and performance in relation
to mission area assignments, program objectives, approved strategy and
milestones. Assessments are made by the responsible line program
organization and outside the advocacy chain by the Office of Program/
Project Management. In all cases, program assessments must be based on
knowledge of the actual program status, performance, problems, and
significant development in approval; review; and environment, safety,
health, and quality assurance processes.
PROGRAM MANAGEMENT. Management responsibility and authority for
specific programs will normally be delegated by the cognizant Program
Secretarial Officer. The Headquarters functions of program management
includes planning and developing the overall program; establishing broad
priorities; providing policy and broad program direction; preparing and
defending the budget; establishing the technical performance, scope,
cost, and schedule requirements for projects; controlling DOE
Headquarters-level milestones; integrating all components of the
program, providing public and private sector policy liaison; expediting
Headquarters interface activities and followup actions; and retaining
overall accountability for program success. The field function includes
implementing these program activities, controlling field-level
milestones, and providing major support to the Headquarters programming
budgeting and processes.
Section 19
PROGRAM MANAGER. An individual in an organization or activity who is
responsible for the management of a specific function or functions, who
is responsible for budget formulation, and for execution of the approved
budget. The Program Manager receives an approved funding program from
the Chief Financial Officer identifying program dollars available to
accomplish the assigned function.
PROGRAM OBJECTIVES. A statement or set of statements defining the
purposes and goals to be achieved during performance of a program to
fulfill a DOE mission including the technical capabilities, cost, and
schedule goals.
PROGRAM OFFICE. The Headquarters organizational element responsible for
managing a program.
PROGRAM SECRETARIAL OFFICER (PSO). A senior outlay program official
which includes the Assistant Secretaries for Conservation and Renewable
Energy (CE), Defense Programs (DP), Fossil Energy (FE), Nuclear Energy
(NE), Environmental Restoration and Waste Management (EM) and the
Directors of Energy Research (ER), Civilian Radioactive Waste Management
(RW), and New Production Reactors (NP).
79.
Vertical line denotes change
DOE 4700.1 Chg 1 Attachment 3
6-2-92 Page 15
82.
83.
84.
85.
86.
PROJECT. A project is a unique major effort within a program which has
firmly scheduled beginning, intermediate, and ending date milestones;
prescribed performance requirements, prescribed costs; and close
management, planning, and control. A project is a basic building block
in relation to a program which is individually planned, approved and
managed. A project is not constrained to any specific element of the
budget structure (e.g., operating expense or plant and capital
equipment). Construction, if required, is part of the total project.
Authorized, and at least partially appropriated, projects will be
divided into three categories: major system acquisitions, major
projects, and other projects.
PROJECT DATA SHEET. A generic term defining the document containing
summary project data and justification required to include the entire
project effort as a part of the Departmental budget. Specific
instructions on the format and content of the project data sheet are
contained in the annual budget call, and DOE 5100.3.
PROJECT DESIGN CRITERIA. Those technical data and other project
information developed during the project identification, conceptual
design, and/or preliminary design phases. They define the project
scope, construction features and requirements, and design parameters;
applicable design codes, standards, and regulations; applicable health,
safety, fire protection, safeguards, security, energy conservation, and
quality assurance requirements; and other requirements. The project
design criteria are normally consolidated into a document which provides
the technical base for any further design performed after the criteria
are developed.
PROJECT MANAGEMENT. A management approach in which authority and
responsibility for execution are vested in a single individual, at a
level below the general manager, to provide focus on the planning,
organizing, directing, and controlling of all activities within the
project. In general terms, project management functions include
assisting the program manager in preparing Headquarters documents and
establishing key milestones and overall schedules. Other activities
include developing and maintaining the project management plan; managing
project resources; establishing and implementing management systems,
including performance measurement systems; and approving and
implementing changes to project baselines.
Section 20
PROJECT MANAGER. An official who has been assigned responsibility for
accomplishing a specifically designated unit of work effort or group of
closely related efforts established to achieve stated or designated
objectives, defined tasks, or other units of related effort on a
schedule for performing the stated work funded as part of the project.
The project manager is responsible for the planning, controlling, and
reporting of the project.
PROJECT OFFICE. The organization responsible for administration of the87.
project management system, maintenance of project files and documents,
and staff support for officials throughout the project life cycle.
Vertical line denotes change
Attachment 3 DOE 4700.1 Chg 1
Page
88.
89.
90.
93.
94.
16 6-2-92
PROJECT SUMMARY WORK BREAKDOWN STRUCTURE. A summary work breakdown
structure tailored by project management to the specific project with
the addition of the elements unique to the project. Generally, the
project summary work breakdown structure will identify project elements
through the third level.
PROJECTIONS. Estimates of budget authority, outlays, receipts, or other
budget amounts that extend a minimum of 5 years beyond the current year.
Projections generally are intended to indicate the budget implications
of continuing current or currently proposed programs and legislation for
an indefinite period of time. These include alternative program and
policy strategies and ranges of possible budget amounts. Projects
should be regarded neither as firm estimates of what actually will occur
in future years nor as recommendations regarding future budget
decisions.
QUALITY ASSURANCE. All of the planned and systematic actions necessary
to provide adequate confidence that a facility, structure, system or
component will perform satisfactorily in service. Quality assurance
includes quality control, which comprises all those actions necessary to
control and verify the features and characteristics of a material,
process, product, or service to specified requirements.
91. REAL PROPERTY. Land and/or improvements including interests
except public domain land.
SCOPE . In baseline management terminology, the term “scope”
therein,
refers to92.
those performance and design requirements, criteria, and characteristics
derived from mission needs that provide the basis for project direction
and execution. In budget terminology, the term “scope” refers to the
congressionally approved project parameter/tasks as defined in the
Congressional Project Data Sheet.
SITE. A geographic entity comprising land, buildings, and other
facilities required to perform program objectives. Generally a site
has, organizationally, all of the required facilities management
functions. That is, it is not a satellite of some other site.
SITE DEVELOPMENT AND FACILITY UTILIZATION PLAN (SITE DEVELOPMENT PLAN).
A formal written document summarizing all of the various data necessary
to plan for the most effective utilization, orderly future development;
and disposal of facilities at an individual site. Such planning shall
be in accordance with site related program objectives and requirements
and shall represent the consolidated views of site management, the field
organization and the resource sponsor.
95. SITE OFFICE. Term used to describe small organizations established near
work sites for the accomplishment of specific projects or work
assignments receiving administrative support from another field
organization.
Vertical line denotes change
Section 21
DOE 4700.1 Chg 1 Attachment 3
6-2-92 Page 17
96.
97.
98.
STATE-OF-THE-ART TECHNOLOGY ASSESSMENTS. An integral part of the
technology base element of a program. The objective of these
assessments is to ensure that technology base and project activities can
benefit from relevant state-of-the-art technology where appropriate.
Furthermore, these assessments can assist in the identification of
mission needs and ensure that DOE officials have a clear understanding
of where a specific energy-related technology stands before making
significant program or project decisions.
SUBCONTRACT. Any agreement or arrangement between a contractor and any
person (in which the parties do not stand in the relationship of an
employer and an employee):
a. For the furnishing of supplies or services or for the use of real or
personal property, including lease arrangements, which, in total or
in part, is necessary to the performance of any one or more
contracts; or
b. Under which any portion of the contractor’s obligation under any one
or more contracts is performed, undertaken, or assumed.
SUBSYSTEM. An aggregation of component items (hardware and software)
performing some distinguishable portion of the function of the total
system of which it is a part. Normally, a subsystem could be considered
a system in itself, if it were not an integral part of the larger
system.
99. SUPPORTING OPERATIONS. All work in an outlay program that is not in the
science and technology base activity and not in projects. It includes
program overhead, personnel, and standing studies, and is generally
characterized by level of effort.
100. SYSTEM. A collection of interdependent equipment and procedures
assembled and integrated to perform a well-defined purpose. It is an
assembly of procedures, processes, methods, routines, or techniques
united by some form of regulated interaction to form an organized whole.
101. TECHNICAL BASELINE. A configuration identification document or a set of
such documents formally designated and approved at a specific time.
(The time need not be the same for each document in the set. ) Technical
baselines, plus approved changes to those baselines, constitute the
current configuration identification.
102. TECHNICAL DIRECTION. The monitoring or surveillance of the scientific,
engineering, and other technical aspects of a work program, as
distinguished from the administrative and business management aspects.
Vertical line denotes change
Attachment 3 DOE 4700.1 Chg 1
Page
103.
104.
105.
106.
107.
108.
109.
18 6-2-92
TECHNOLOGY. A demonstration by experiment of the technical feasibility
of alternative inventive concepts. This category may concern itself
with processes, components, equipment, subsystems, or initial system
prototype, and may encompass: experimental exploitation and refinement
of a known phenomenon; demonstration of the acceptability of the
technical and operational characteristics of one or more specific
concepts; and preliminary system studies responsive to a particular
problem including system analysis, tradeoff, preliminary cost/benefit
studies, and planning and programming studies.
TECHNOLOGY BASE. The equipment and facilities produced for, and the
accumulated results and skills produced by, the conduct of basic
research, applied research and technology development.
TECHNOLOGY OR EXPLORATORY DEVELOPMENT. The systematic application of
knowledge from research toward proof of technology, including
development of nonspecific application prototypes and processes.
Section 22
TITLE I DESIGN ESTIMATES. Estimates prepared upon completion of Title I
design. Through use of plant engineering and design funds, Title I may
be completed prior to inclusion of the project in the budget. If this
should occur, the Title I design estimate becomes synonymous with the
budget estimate.
TITLE I DESIGN SUMMARY. An overview and record document of preliminary
engineering and project management planning, reflecting completed Title
I design and usually prepared under architect-engineer services or by
the operating contractor. Title II design estimates are developed for
each project by the designer as part of the Title I design summary. The
estimates, since they are based on the definitive design, are the most
accurate and have the highest confidence level of any estimate.
TITLE II DESIGN. This continues the development of the project based on
approved preliminary design (Title I). Definitive design includes any
revisions required of the Title I effort; preparation of final working
drawings, specifications, bidding documents, cost estimates, and
coordination with all parties which might affect the project;
development of firm construction and procurement schedules; and
assistance in analyzing proposals or bids. For a detailed description
of the services provided during definitive design, see DEAR
936.605(c)(3) and (4) and DEAR 952.236.70.
TITLE III SERVICES. Those activities required to assure that the
project is constructed in accordance with the plans and specifications
(e.g., construction inspection), and that the quality of materials and
workmanship is consistent with the requirements of the project (e.g.,
materials testing). (See DEAR 936.605(c)(3) and (4) and DEAR 952.236.70
for additional details.)
Vertical line denotes change
DOE 4700.1 Chg 1 Attachment 3
6-2-92 Page 19
110. TOTAL ESTIMATED COSTS (TEC) AND TOTAL PROJECT COSTS (TPC). Definitions
for TEC and TPC are provided in DOE 5100.3, FIELD BUDGET PROCESS, and
5700.2C, COST ESTIMATING, ANALYSIS, AND STANDARDIZATION. The below
listed definitions, extracted from these documents form the basis for
development of standardized cost estimates.
On occasion, there may be projects which cannot comply with these
definitions and guidance. For these projects, variances must be
requested by the project and approved by the Office of Program/Project
Management prior to Key Decision No. 1 when establishing project
baselines and requesting line item funding.
a. TEC. TEC includes the following estimated costs:
Land, land rights, depletable resources, and improvements to land.
Engineering, design, and inspection (Titles I, II, and III).
Construction Management of main plant, balance of plant, other
facilities, other structures and significant alterations,
additions, and improvements to structures (excluding normal
maintenance).
Utilities - including water and sewage systems, heating
ventilation and air conditioning, power systems, communication
systems, and fire prevention systems.
Quality Assurance.
Pre-operational construction changes shown to be required during
integrated systems testing and hot start testing.
Safeguards and security systems.
project and construction management.
Direct and indirect construction costs.
Standard and special facilities.
All equipment, furniture, and systems contained in main, balance
of plant facilities and administrative areas to render the
facility useable.
Computer systems, if dedicated to the project.
Section 23
Contingency and economic escalation.
Decontamination and/or disposal cost of equipment and construction
rubble when the purpose of the project is to replace existing
facilities.
Vertical line denotes change
Attachment 3 DOE 4700.1 Chg 1
Page 20 6-2-92
b. TPC. TPC includes all research and development (R&D), operating,
plant and capital equipment costs, specifically associated with
project construction up to the point of routine operations, which
will include but not be limited to:
Total Estimated Costs.
Pre-Title I activities, such as:
- Conceptual Design Reports (CDR).
- Preliminary Safety Analysis Report, if initiated prior to KD-1.
- Preparation of Project Data Sheets, design criteria, National
Environmental Policy Act (NEPA) documentation, and formulations
of Quality Assurance Criteria.
R&D necessary for fabrication, testing, and rework of prototype
equipment.
R&D (scale-up or demonstration plants of high-risk technology)
required prior to start of construction.
One-time costs related to testing, startup, operator training, and
commissioning.
Initial inventories and spare parts.
Site suitability testing and evaluation.
Quality Assurance related to site suitability and testing.
Regulation compliance.
Grant to state and local governments.
Payments equal to taxes.
Systems studies and selected systems engineering services.
Institutional activities related to facility siting and external
interactions.
Decontamination and decommissioning costs.
Economic escalation.
Contingency (applicable to TPC).
Vertical line denotes change
DOE 4700.1 Chg 1 Attachment 3
6-2-92 Page 21 (and 22)
111.
112.
USER. The entity which ultimately will operate or otherwise use the
system being developed. When the project objective is to demonstrate to
the private sector the utility or feasibility of a given system for
commercial application, the identity of the ultimate user may not be
known. In such case, only the most likely type of user (utility,
constructor, energy supplier) may be identifiable.
VALIDATION. The process of evaluating project planning, development,
baselines and funding prior to inclusion of funds for a project or
system acquisition in the DOE budget. It requires a review of project
planning and conceptual development documentation, as well as discussion
with the program or field element and principle contributing contractors
to determine the source basis, procedures, and validity of proposed
requirements, scope, cost, schedule, funding, and so forth. Findings
and recommendations resulting from the validation process will be
provided for use in the annual budget formultion.
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
i
TABLE OF CONTENTS
CHAPTER I - DOE PROJECT MANAGEMENT SYSTEM
PART A - OVERVIEW OF THE PROJECT MANAGEMENT SYSTEM
1. Introduction
2. Categories of Work Effort
a. Operational Categories
Figure I-1 - Categories of DOE Projects
Figure I-2 - Categories of Work Effort and Research and
Development of Acquisition Phases
b. Statutory Categories
c. Research and Development Phases
PART B - PROGRAM/PROJECT RELATIONSHIPS
1. Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2. Program Policy . . . . . . . . . . . . . . . . . . . . . . . . . . .
3. Project Evolution. . . . . . . . . . . . . . . . . . . . . . . . . .
Figure I-3 - Program Hierarchy . . . . . . . . . . . . . . . . .
4. State-of-the-Art Assessments . . . . . . . . . . . . . . . . . . . .
Section 24
PART C - MANAGEMENT ROLES, RESPONSIBILITIES, AND AUTHORITY . . . . . . .
1.
2.
3.
4.
5.
6.
7.
a.
8.
Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Organization . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Role of the Acquisition Executive . . . . . . . . . . . . . . . . . .
Figure I-4 - Project Management System Relationships . . . . . .
Energy System Acquisition Advisory Board . . . . . . . . . . . . . .
Program Secretarial Officers . . . . . . . . . . . . . . . . . . . .
Heads of Field Organizations . . . . . . . . . . . . . . . . . . . .
Project Manager. . . . . . . . . . . . . . . . . . . . . . . . . . .
Specific Responsibilities . . . . . . . . . . . . . . . . . . . .
b. Project Execution. . . . . . . . . . . . . . . . . . . . . . . .
Departmental Support Organizations . . . . . . . . . . . . . . . . . .
a. Director of Procurement, Assistance and Program Management . . .
(1) The Associate Director for Program/Project Management and
Control
(2) Director of Procurement, Assistance and Program Management .
(3) The Chief Financial Officer . . . . . . . . . . . . . . . .
(4) General Counsel
(5) Assistant Secretary for Environment, Safety, and Health .
(6) Director of Organization, Resources and Facilities
Management . . . . . . . . . . . . . . . . . . . . . . . .
I-1
I-1
I-2
I-2
I-3
I-4
I-5
I-5
I-7
I-7
I-7
I-7
I-8
I-9
I-11
I-11
I-11
I-11
I-12
I-13
I-13
I-14
I-16
I-16
I-16
I-17
I-17
I-17
I-19
I-20
I-20
I-20
I-21
Vertical line denotes change
ii DOE 4700.1 Chg 1
6-2-92
9.
10.
a.
Support to the Project Manager . . . .
Organizational Options
b. Other Than Departmental Support . .
Key Government Functions . . . . .
Management Assignments . . . . . . . .
c.
I-21
I-21
I-21
I-22
I-22
I-22
I-22
a.
a.
Project Management Assignment . . . . . . . .
b. Establishment of Special Project Office . . .
PART D - MAJOR SYSTEM ACQUISITIONS AND MAJOR PROJECTS I-25
1.
2.
3.
4.
5.
Introduction . . . . . . , . . . . . . . . . . .
Key Decisions. . . . . . . . . . . . . . . . . .
I-25
I-26
Figure I-5 - Major System Acquisition and Major Project
Decisions . . . . . . . . . . . . . . . . I-27
I-29
I-30
c.
Designation of Major System Acquisitions and Major Projects
DOE Acquisition Process.. . . . . . . . . . . . . . . . .
Figure I-6 - Major System Acquisition--Phase Transition
Decision Points . . . . . . .
Project Planning for Major System Acquisitions or
I-30a
I-31
I-31
I-31
I-31
I-31
I-32
I-32
I-32
Major Projects
Management Information . . . . . . . . . .
b. Use of Government or Non-Profit Organizations
Affordability . . . . . . . . . .
d. Timeliness . . . . . . . . . . .
e. Competitive Concept Development .
f. Cost Estimates . . . . . . . . .
g. Cost Participation . . . . . . .
Figure I-7 - Key Decisions in the Acquisition
Construction or Development Projects
Process
I-34
PART E -OTHER PROJECTS . . . . . . . . . . . . . . . . . . I-35
1. Introduction . . . . . . . . . . . . . . . . . . . . .
2. Other Project Decisions . . . . . . . . . . . . . . . .
3. Other Project Management Process . . . . . . . . . . .
Attachment I-1 - Energy System Acquisition Advisory
Procedures. . . . . . . . . . . . . . . . . .
I-35
I-35
I-35
Board
I-37
I-47
I-59
Attachment I-2 - Guidelines for Preparation for ESAAB Meetings
Attachment I-3 - Major System Acquisition Procedures. .
CHAPTER II - STRATEGIC PLANNING, PROJECT PLANNING AND BUDGETING
PART A - PROJECT INITIATION AND PLANNING DOCUMENTATION . . . . II-1
Section 25
1. Introduction . . . . . . . . . . . . . . . . . . . . . . .
2. Strategic Planning . . . . . . . . . . . . . . . . . . . .
II-1
II-1
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
iii
PART B - WORK BREAKDOWN STRUCTURE . . . . . . . . . . . . . . . . . . . . . II-9
PART C - PROJECT BUDGET PROCESS . . . . . . . . . . . . . . . . . . . . II-15
PART D - COST ESTIMATING AND CONTINGENCY ESTIMATING
PART E - PROJECT ACQUISITION FOR MAJOR SYSTEM ACQUISITIONS AND MAJOR
Vertical line denotes change
iv DOE 4700.1 Chg 1
6-2-92
PART F - ENVIRONMENTAL PLANNING AND REVIEW . . . . . . . . . . . . . . II-31
PART G - CONSTRUCTION PLANNING . . . . . . . . . . . . . . . . . . . . . II-39
PART H - PROJECT TRANSITION . . . . . . . . . . . . . . . . . . . . . . II-43
CHAPTER III - PROJECT CONTROL
PART A - CHANGE CONTROL AT THE EXECUTIVE LEVEL
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
v
PART B - SYSTEMS ENGINEERING, TEST, AND EVALUATION . . . . . . . III-5
PART C - CONFIGURATION MANAGEMENT . . . . . . . . . . . . . . . . III-11
PART D - QUALITY ASSURANCE . . . . . . . . . . . . . . . . . . . . III-17
PART E - CONSTRUCTION MANAGEMENT . . . . . . . . . . . . . . . . . . . III-23
PART F - PROJECT CONTROL . . . . . . . . . . . . . . . . . . . . . . III-25
Vertical line denotes change
vi DOE 4700.1 Chg 1
6-2-92
PART G -PROJECT TERMINATION . . . . . . . . . . . . . . . . . . . . . . III-41
CHAPTER IV - PROJECT REVIEW, REPORTING, AN ASSESSMENT
PART A - PROJECT STATUS REVIEW . . . . . . . . . . . . . . . . . . . . . IV-1
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
vii
PART B - PROJECT REPORTING AND ASSESSMENT . . . . . . . . . . . . . . . . IV-3
Attachment IV-1 - Project Manager’s Progress Report
Instructions and Example . . . . . . . . . . . . . . . . . IV-11
Attachment IV-2 - Semiannual Status Report for Non-General Plant
Projects Below $5 Million in Total Estimated Cost,
Instructions and Example . . . . . . . . . . . . . . . . . . . IV-23
Attachment IV-3 - Project Activity Report, Instructions
and Example . . . . . . . . . . . . . . . . . . . . . .
Attachment IV-4 - Cost and Cost Plus Commitment Chart,
Instructions and Example . . . . . . . . . . . . . . . . . IV-29
Attachment IV-5 - Engineering, Management, and Construction
Manpower for Cost Type projects Report, Instructions and
Attachment IV-6 - Progress Photographs Instructions . . . . . . IV-35
Attachment IV-7 - Annual Report for General Plant Projects,
Instructions and Example.. . . . . . . . . . . . . . . . . . . . IV-37
Attachment IV-8 - Instructions for the Program Manager’s Summary
Report to the Acquisition Executive . . . . . . . . . . . . IV-39
Attachment IV-9 - Summary Project Performance Report to Senior
Management, Instructions and Example . . . . . . . . . . . . . . . IV-41
Attachment IV-10 - Example of a Quarterly Status
Report - Construction Projects . . . . . . . . . . . . . . . . . . IV-43
Vertical line denotes change
viii DOE 4700.1 Chg 1
6-2-92
CHAPTER V - PROCEDURES FOR CONSTRUCTION MANAGEMENT
PART A - PROCEDURES FOR MANAGING CONSTRUCTION EFFORTS
Vertical line denotes change
DOE 4700.1 Chg 1 ix (and x)
6-2-92
PART C -EXECUTION . . . . . . . . . . . . . . . . . . . . . . . . . . . .V-33
Attachment V-1 - Example of a Project Authorization . . . . . . . V-65
Attachment V-2 - Construction Management . . . . . . . . . . . . V-67
Attachment V-3 - Design Criteria Package Checklist . . . . . . . V-77
Attachment V-4 - Control Aid Descriptions . . . . . . . . . . . . V-83
Attachment V-5 - Planning Chronology for Fiscal Year 1986
Section 26
Construction Budget Projects . . . . . . . . . . . . . . . . V-85
Attachment V-6 - Short Form Data Sheet Contents . . . . . . . . . V-87
Attachment V-7 - Example of a Short Form Data Sheet . . . . . . . V-89
Attachment V-8 - Conceptual Design . . . . . . . . . . . . . . . V-91
Attachment V-9 - Conceptual Design Reports . . . . . . . . . . . V-95
Attachment V-10 - Conceptual Design Report Title Page Example . . V-97
Attachment V-11 - Contents of a Title I Design Summary . . . . . V-99
Attachment V-12 - Construction Completion Report Content . . . V-103
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
I-1
CHAPTER I
DOE PROJECT MANAGEMENT SYSTEM
PART A - OVERVIEW OF THE PROJECT MANAGEMENT SYSTEM
1. INTRODUCTION. The Department’s project management system is an approach
to management in which authority, responsibility, and accountability are
vested in a single individual to provide the detailed planning,
organizing, directing, and controlling of all activities leading to the
successful execution of the project.
a. The project manager’s planning activities include developing a plan
for management and control of the project. He/she is responsible for
ensuring that the baselines established in that plan are followed.
The project manager’s basic tools for controlling baseline activities
are monitoring and contractor reporting.
b. The contractor’s planning efforts must support those of the
Department. Part of the contractual agreement requires inclusion of
how the contractor will measure project performance so that the DOE
project management plan will reflect that data. These agreed-to plans
then become the project manager’s mechanisms for directing and
controlling the project.
c. Baseline establishment, baseline change control, and current,
complete, and accurate contractor reporting are the keys to proper
project management. The project manager is responsible for ensuring
that the project baselines are realistic, for understanding the need
for and value of adequate reporting to measure baseline performance,
and for establishing the proper control mechanism (Uniform Reporting
System and Cost and Schedule Control Systems Criteria) to measure
project performance. These requirements demand that the project
manager be fully cognizant of the concepts and procedural details of
the tools which are available for use.
d. DOE project management policy requires decentralization of projects
unless an exception is granted by the Acquisition Executive.
Decentralization in this context simply means assignment of project
management responsibility to field elements. Normally, for large
decentralized projects such as Major System Acquisitions (MSAs), Major
Projects (MPs) or major line items; scope, cost, and schedule
baselines are provided and controlled by Headquarters.
Vertical line denotes change
I-2 DOE 4700.1
3-6-87
e. The Department categorizes projects into three separate groups: MSAs,
MPs, and other projects. The definition of these categories are
detailed in Figure I-1. For project reporting purposes, other
projects are further subdivided into those costing $15-$50 million,
those $5-$15 million, those $1.2-$5 million, and those under $1.2
million (general plant projects). Chapter IV explains reporting
requirements for all project categories.
2. CATEGORIES OF WORK EFFORT. The projects covered by the project
management system include not only construction efforts, but also
activities which may be defined in terms of operational/statutorial
categories of work effort and the various phases of research and
development. Figure I-2 shows the relationship of the activities; further
details are provided below:
Section 27
a. Operational Categories. The full spectrum of outlay program efforts
can be divided into three categories which together constitute an
individual program.
(1)
(2)
Science and Technology Base. This normally accounts for 8 to 12
percent of the outlay program’s total estimated cost. This work
effort is referred to as tasks or work units, and is managed or
performed by personnel designated as principal investigators, as
opposed to the more formal procedures in projects and project
management. The work is generally characterized as level of
effort, and the documentation and management techniques are not
as formalized or rigorous as those required for project
management. An exception to this is the construction of large
experimental facilities, in such programs as high energy physics
and fusion, to be used in support of technology base activities.
Projects. Concept and demonstration development projects and
full scale development projects normally account for 20 to 40
percent of the outlay program’s total estimated cost. Projects
proceed through several discrete phases, each phase being
separated by a key decision point as shown in Figure I-2. Key
decisions are defined and explained in Chapter I, Part B,
paragraph 2. These project phases can be contained within only a
single statutorial phase of research and development, or they may
pertain to the project as it moves through the various phases of
research and development. It should be recognized that few
projects come from science and technology base and proceed neatly
through the research and development phases.
(3) Operations and Support. Normally in excess of 50 percent of the
outlay program’s total estimated cost can be attributed to
operations and support work effort, which encompasses all work in
an outlay program that is not in the science and technology base
or projects. It includes production, fabrication, and testing,
as well as program overhead, personnel, and studies, much of
which is generally characterized by level of effort.
Historically, some of this work moves into projects over time.
DOE 4700.1 Chg 1
6-2-92 I-3
Figure I-1. Categories of DOE Projects
Major System Acquisitions
A. National urgency, importance, size or complexity.
B. Dollar value-normally those systems or projects which have a total
project cost in excess of $100 million.
Major Projects
A. Total project cost of the project from $50 to $100 million.
B. Importance of project to program objectives.
C. Size and complexity of the project.
D. Degree of DOE control required.
E. Visibility of the project.
F. Potential severity of environmental impact.
G. Recommendations by Program Secretarial Officers.
Other Projects
A. Total project cost of the project below $50 million, including line
items, and GPP items.
B. Line items.
C. GPP items.
Vertical line denotes change
FIGURE 1-2
CATEGORIES OF WORK EFFORT AND RESEARCH AND
DEVELOPMENT OR ACQUISITION PHASES
DOE 4700.1 I-5
3-6-87
b. Statutory Categories. Within the Department, research, development, and
demonstration efforts consist of three statutory general categories:
(1)
(2)
(3)
Science and Technology Base includes basic research, applied
research, and technology or exploratory effort. Normally for budge-
tary reporting purposes, research and development facilities and
devices completed and capitalized are included in this base. The
goal of this effort is to conceive, scope, and explore technology
options to provide the foundation for the development of specific
projects.
Section 28
Concept and Demonstration Development includes advanced development
and engineering development. Its goal is the systematic application
of knowledge towards the identification of solutions to meet specific
energy requirements, including specific application prototypes and
processes. Normally, there is an intended commitment to large scale
projects.
Full Scale Development includes demonstration and production or
operation and is the systematic application of knowledge towards pro-
duction of useful materials, devices, systems or methods; this in-
cludes design, development and improvement of equipment and processes
to meet specific energy requirements. There is a major commitment of
significant resources at this point.
c. Research and Development Phases. The statutory categories above are
further subdivided into research and development phases. The first three
are level-of-effort type phases; the last four are called the acquisition
phases.
(1)
(2)
(3)
(4)
Basic Research. Systematic, fundamental study directed toward fuller
scientific knowledge or understanding of subjects bearing on national
energy needs.
Applied Research. Systematic study directed toward fuller scientific
knowledge for direct use in fulfilling specific energy requirements.
Technology or Exploratory Development. Systematic application of
knowledge from research towards proof of technology including devel-
opment of nonspecific application prototypes and processes.
Advanced Development. Effort that leads ultimately to a particular
application or product. Advanced development can cut across several
scientific disciplines and is intended to explore innovation in a
particular area of one or more energy technologies.
I-6 DOE 4700.1
3-6-87
(5) Engineering Development. Systematic use of the knowledge and
understanding gained from research and technoloy development to
achieve the detailed design, construction, and test for performance,
producibility, and reliability of energy system prototypes, pilot
plants, and research facilities. This category also includes the
preparation of appropriate National Environmental Policy Act documen-
tation.
(6) Demonstration. Verification of economic and environmental viability
through design and construction, test and evaluation of large energy
systems in operational circumstances. Demonstration projects are
intended to:
(a) Overcome “scale-up” problems;
(b) Contribute to the understanding of the economics of fabrication
and operation; and
(c) Resolve other questions such as public assistance and institu-
tional and environmental issues. Preparation of appropriate
National Environmental Policy Act documentation is included in
this phase.
(7) Production or Operations.
(a) Production. Producing the item in quantity, bulk, or other
parameters which meet specifically stated requirements.
(b) Operations. Bringing the system or project from prototype or
pilot plan operational testing status to full-scale operational
condition to meet stated objectives.
DOE 4700.1 I-7
3-6-87
PART B - PROGRAM/PROJECT RELATIONSHIPS
1. INTRODUCTION.
a. Program Requirements flow from Departmental missions and mission area
assignments made by the Secretary. The goals established by the program
requirements necessitate pursuit of state-of-the-art technology develop-
ment, various project executions, and operation of pilot and fully
integrated facilities.
Section 29
b. Responsibilities. The program manager is responsible for attaining
program goals within a mission area assignment and concentrates on assimi-
lation of all aspects of the program into a single entity. The project
manager is responsible for a single project within the program and con-
centrates on meeting project objectives within established baselines.
2. PROGRAM POLICY. Program policy establishes the base for project policy and
execution.
a. Each program Secretarial Officer is responsible for the planning,
programing, budgeting, and execution of programs under his or her
cognizance.
b. Headquarters and field responsibilities and authorities are set forth for
each program.
c. There is a clear hierarchical relationship between missions, programs,
and projects. This hierarchical relationship is graphically depicted in
Figure I-3.
d. Only programs and their constituent elements that fulfill a mission
need, and are in consonance with assigned mission areas, will be
conducted.
e. Continuing mission analysis and independent monitoring are conducted to
ensure that programs are planned, developed and, upon approval, executed
in accordance with assigned mission areas.
f. Significant program issues and near-term milestones of interest to senior
management are identified and their status periodically reviewed.
3. PROJECT EVOLUTION.
a. The Secretary requests proposed changes to current mission area assign-
ments from the program Secretarial Officers. These changes are based on
the results of continuing mission analysis.
I-8 DOE 4700.1
3-6-87
Planning Flow for Programs
DOE Project
Management System
Figure I-3
Program Hierarchy
DOE 4700.1
3-6-87
I-9 (and I-10)
b. A program summary is developed for each program which includes the mission
area assignment supported by the following data: (1) program objectives
and related issues; (2) the program strategy; (3) summary of program
logic; (4) near- and long-term milestones; (5) significant projects; and
(6) the program project structure. The Secretary approves the program
strategy and near-term milestones, and selects milestones and issues for
periodic review.
c. The approved projects and/or project elements of the program then become
specific budget items in the annual planning, programing, budgeting phase
of program management. The planning and programming activities entail the
translation of strategic Departmental policy objectives at a specific
point in time within constrained resources.
4. STATE-OF-THE-ART ASSESSMENTS.
a. The project management system assumes the technical risks associated with
research and technology development are investigated prior to the
establishment of a project, especially MSA’s or MP’s. This risk can vir-
tually be eliminated by requiring proven technology to be available prior
to project initiation. The impact of this requirement, however, may be
severe in terms of cost and schedule penalties as well as unrealistic for
meeting a mission need. In other words, there must often be a tradeoff
between project schedule and state-of-the-art technology. An assessment
has to be made of the impact of one or the other situations.
b. This state-of-the-art assessment is primarily the responsibility of the
program manager, who has better visibility into the technology related to
his program. The assessment should then become an integral part of the
risk assessment aspect of the justification for new start and be sum-
marized in the alternatives and capability section.
Section 30
c. Although the program manager has primary responsibility, the project
manager must also be alert to technology change. State-of-the-art
assessments may relate to any phase of the project, since various com-
ponents in a system may be in different stages of development throughout
the project’s life. In updating the project plan, the project manager
should describe the status of technology as it relates to the project.
Then, as the project matures, early warning of potential deficiencies in
technology readiness should be highlighted in the project manager’s status
reports.
DOE 4700.1 Chg 1
6-2-92
I-11
PART C. MANAGEMENT ROLES, RESPONSIBILITIES, AND AUTHORITY
1. INTRODUCTION. It is the intent of the Department to place authority and
responsibility at the appropriate management level commensurate with the
project effort. This approach allows decisions to be made and actions to
be taken at the appropriate levels within DOE line management. Below are
the detailed roles played by various management levels within the
Department as they relate to the project management system.
2. ORGANIZATION.
a. Headquarters program organizational elements will be responsible for
overall program policy, planning, program development (including
establishment of Broad priorities), budget preparation and defense
(with major support from field organizations), and broad program
direction. Field organizations will be responsible for implementing
these program activities and for providing major support to the
Headquarters programming and budgeting process.
b. Implementation of the Project Management System (PFK) involves both a
“line” chain of authority and necessary participation of various
“staff” elements. The line organization chain begins with the
Secretary and progresses through the Program Secretarial Officers,
Headquarters program organizations, and finally, to the project
manager, the single individual who has full responsibility for
detailed planning and execution of all project activities. Staff
participation and coordination begin very early in a project’s life
cycle and carry through to project completion. (A chart showing
project management system relationships follows as Figure I-4).
c. Project Line Management. The project line management for MSAs, MPs,
and other projects, as depicted in Figure I-4, is the Office of the
Secretary/Acquisition Executive, the Program Secretarial Officer, the
Program Office, the Head of the Field Element, and the Project
Manager.
3. ROLE OF THE ACQUISITION EXECUTIVE
a. The Secretary has delegated the principal responsibility for project
management activities to the Acquisition Executive. This includes
establishing Department project management policies, approving the
PMS, serving as the chairman of the Energy System Acquisition Advisory
Board (ESAAB) and Level Baseline Change Control Board (BCCB) for the
Department’s MSAs and selected MPs and approving establishment of
special project offices.
b. Key decisions on MSAs and certain decisions on selected MPs are
normally reserved for the Acquisition Executive. In some cases, the
Secretary may elect to act as the Acquisition Executive on critical
projects. These include decisions to enter the acquisition phase or
to make transitions between phases (key decisions) and any decisions
Vertical line denotes change
I-12
DOE
4700.1
3-6-87
DOE 4700.1 Chg 1
6-2-92
which will directly result in commitment of major portions
I-13
Section 31
(e.g.,procurement of large long-lead items) of-the- project funds.
Additionally, the Acquisition Executive
a case-by-case basis.
c. Other decisions on MSAs and similar key
MPs are typically made by the cognizant
may reserve other decisions on
and significant decisions on
Program Secretarial Officers.
4. ENERGY SYSTEM ACQISITION ADVISORY BOARD.
a. The ESAAB supports the Acquisition Executive by providing advice,
assistance, and recommendations at key decision points for each MSA
and designated MPs. Attachment I-1 provides complete ESAAB membership
and procedures. The ESAAB provides a single forum for the discussion
of issues and alternatives and is designed to assure coordinated,
objective senior level management advice to the Acquisition Executive.
Attachment I-2 details ESAAB review meeting highlights.
b. The Acquisition Executive is responsible for convening formal
meetings, as required to facilitate the decision process. Board
members and appropriate advisors will attend all meetings. Other
advisors are not required to attend unless asked to participate by the
Acquisition Executive. In addition to prescribed meetings, any board
member may request a meeting to consider significant issues at any
point in the acquisition process for any MSA.
5. PROGRAM SECRETARIAL OFFICERS.
a. Each Program Secretarial Officer has full responsibility for the
management planning and execution of his/her program activities
including projects, subject to the national energy plan; approved
Departmental policies and program strategies; mission area
assignments; enacted budget legislation; approved resource
allocations; and the Departmental PMS. For MPs, the Program
Secretarial Officer is responsible for each approval or key decision
not specifically reserved for the Acquisition Executive.
Additionally, he/she is responsible for providing current information
on program management decisions, the progress of work, status or
resource utilization, major problems encountered, and planned
corrective actions, to the Acquisition Executive and other
Departmental elements having responsibility for activities which must
interface with project activities.
b. Normally, the type and level of detail for the information provided
will be the minimum required for the recipient office to fulfill its
responsibilities in those areas which interface with project
activities. In general, the information concerning projects that is
provided to the Acquisition Executive will be that associated with
MSAs and MPs although special reviews and reports may be requested for
other projects on a case-by-case basis.
Vertical line denotes change
I-14
c.
d.
e.
f.
DOE 4700.1 Chg 1
6-2-92
The responsibility and authority for decision-making shall be
delegated to the appropriate organizational level. To accomplish
this, only those approvals and key decisions on MPs, associated with
entering or making the transition between acquisition phases, those
directly resulting in large commitment of funds (e.g., procurement of
large long lead items) or those of unusual national or programmatic
importance or sensitivity are required at the Program Secretarial
Officer level.
Assistant Secretary for Defense Programs (DP-1) has special
responsibilities for non-weapon work assigned to the weapon complex.
In coordination with appropriate DOE sponsors, he/she reviews the
nature, scope, and future requirements of non-defense-related work.
Additionally, he/she concurs or nonconcurs in the assignment of non-
weapon work or lead missions to the weapon complex facilities.
Section 32
Program Organizations.
(1) Management responsibility for specific programs is delegated by
the cognizant Program Secretarial Officer to one of his/her DOE
Headquarters program offices. This includes overall
responsibility for any projects included in the program
activities. The program organizations are responsible for
assuring that overall requirements are fulfilled in the areas of
environment, technical performance, scope, safety, quality
assurance, cost, schedule, and operational environmental safety
and health. They also continually evaluate and balance project
needs against other programmatic needs and constraints.
(2) In general, the heads of the program offices are responsible for
all the Headquarters approvals and key decisions which are not
specifically reserved for the Program Secretarial Officer or the
Acquisition Executive.
Program Organization Staff. The program organization staff will
assist the director of the Headquarters program organization in the
execution of assigned responsibilities. Precise delineation between
the line management and the staff role is difficult since the staff
functions are highly dependent upon overall organizational
arrangements.
6. HEADS OF FIELD ORGANIZATIONS.
a. Certain planning and all executing responsibility for MSAs, MPs, and
other projects shall be assigned to field offices unless an exception
is obtained from the Acquisition Executive by the Program Secretarial
Officer. The field element shall be involved in the planning of all
assigned projects and shall develop much of the project documentation,
which includes the “Justification of Mission Need” and the Project
Plan, including the project charter. The Head of the Field Element
shall establish an appropriate project management organization and
will delegate appropriate authority to the project manager for
management and direction of the project(s).
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
I-15
b. Specific Responsibilities. Heads of Field Elements will:
(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
Participate and concur in the determination regarding assignment
of project(s) to the field organizations;
Develop project plans, including charters, and other project
documentation for the cognizant program element;
Establish a project management organization and delegate
appropriate authority to the project manager for the management
and direction of the project(s) within the delegated authority;
Assure the project manager is provided the necessary support to
accomplish the project within the project charter guidelines,
particularly in the area of personnel, in both administrative and
technical areas;
Review and approve project management plans;
On MSAs, select the project manager with the concurrence of the
cognizant Program Secretarial Officer or designated
representative; on MPs, select the project manager or designate
management responsibility, after consultation with the cognizant
Program Secretarial Officer or designated representative; and on
all other projects designate management responsibility;
Assure satisfactory management of the project in accordance with
the project plan, including the project charter and project
management plan;
Provide independent assessment on regular reports on project
status, progress, problems, and variances provided to
Headquarters management by the project manager;
Coordinate and integrate all necessary in-house and outside
administrative and technical support to meet project objectives
and requirements;
Section 33
Develop project managers and project management capability;
Within the authority delegated, conduct such contractor
selections and subcontractor approvals as are required.
Within authority delegated, execute and administer contracts;
Assure that the minimum technical reporting requirements of the
Department are met and that all scientific, technical, and
engineering publications are deposited in a timely fashion with
the Office of Technical and Scientific Information;
Assist, when needed, the contractors or industrial partners in—
efforts to formalize experimental research and development
programs to support the assigned project(s);
Vertical line denotes change
I-16 DOE 4700.1 Chg 1
6-2-92
(15) Assure that adequate policy and procedures consistent with
Departmental policy are established to assist the project manager
in accomplishing the planning and execution of the construction
portion of the project;
(16) Prepare National Environmental Policy Act documentation and
assure the environmental protection, safety, and health
protection aspects of facility operations;
(17) Accept the completed contractor efforts; and
(18) Assure effective implementation of required quality assurance
activities.
7. PROJECT MANAGER.
a. Specific Responsibilities. The project manager will be the point of
contact for the information flow to Headquarters. Day-to-day
activities within the scope and charter thresholds and milestones will
normally flow between the project manager and the program manager.
The project manager shall be dedicated full time to the MSAs; however,
on other projects the same project manager may have authority and
responsibility for more than one project. For all projects, the OMB
Circular A-109 requirement to minimize layering above the project
manager must be satisfied.
b. Project Execution. The project manager has direct primary
responsibility and accountability for execution of the project in
accordance with the approved project plan, including the project
charter and the project management plan. The project manager is
responsible for actions indicated below:
(1) Technical Support. The support may be provided, as appropriate,
by technology centers, laboratories, or contractors. Technical
support services generally will be procured directly by the
project manager, but may alternately be provided by contract from
the program manager.
(2) Environment, Safety, and Health. The project manager is
responsible for assuring that all project activities are carried
out in compliance with Federal, State, and local regulations,
laws, and standards for protection of the environment and the
safety and health of employees and the public. The project
manager may procure support services as necessary to achieve such
compliance. In preparing National Environmental Policy Act
documentation, the project manager shall obtain guidance from the
appropriate field organization unit responsible for environment,
safety, and health, and from the Assistant Secretary for
Environment, Safety, and Health.
(3) Reporting. The reporting will be carried out in accordance with
the project management plan and this Order.
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
I-17
(4) Quality Assurance. Procedures in the management of the project
shall be established.
(5) Administrative Matters. The Head of the Field Element will
provide necessary support to the project manager to fulfill
administrative responsibilities associated with the project.
Section 34
(6) Procurement. The project manager shall initiate all procurement
actions necessary for execution of the project. The Head of the
Field Element will provide necessary support to the project
manager to fulfill these procurement responsibilities.
(7) Construction. The project manager shall oversee design review,
construction review, and construction management activities
related to the project.
(8) Financial. Management of project finances including contingency.
Financial management support will be provided by the Head of the
Field Element.
(9) Test Plan and Program. Preparation and execution of a complete
test plan to assure full technical performance capabilities of
the project. The Head of the Field Element will provide
necessary support to the project manager to fulfill these test
plan and program responsibilities.
(10) Configuration Management. Configuration management should be
included for each project that establishes and documents the
configuration baseline; institutes a configuration control system
to ensure the review, approval, and documentation of changes; and
institutes a program of configuration audits to assure compliance
with the form and intent of the configuration control system.
8. DEPARTMENTAL SUPPORT ORGANIZATIONS.
a. Director of Procurement, Assistance and Program Management (PR-1)
is responsible for procurement, cost estimates, and the
development of management and business related policy.
Specifically, responsibilities with respect to the project
management system are carried out by the following:
(1) The Associate Director for Program/Projec t Management and Control
(PR-20), through the Office of Program/Project Management has the
primary responsibility for Department-wide overview of project
activities for the Acquisition Executive. In this role, the
Office of Program/Project Management and Control shall develop,
implement, and maintain Department-wide program/project
management policies and systems. Specific responsibilities of
PR-20 include:
(a) Project Management System (PMS).
1 Develops and maintains the PMS
Vertical line denotes change
I-18 DOE 4700.1 Chg 1
6-2-92
2 Establishes policies and procedures for DOE-wide program
and project management and provides oversight, guidance
and evaluation of this area of responsibility.
3 Establishes requirements for and overview of
configuration management including the Baseline
Change Control Process at the Executive level.
4 Develops, implements, and maintains the Uniform Reporting
System and Cost and Schedule Control Systems Criteria.
5 Establishes requirements for, and overviews, mission
analysis as it relates to the acquisition process.
6 Provides support to and serves as the Energy System
Acquisition Advisory Board and the Level O Baseline
Change Control Board (BCCB) Secretariat.
(b) Project Documentation.
1
2
3
4
5
(c)
Reviews and concurs on project documentation for MSAs and
selected MPs.
Provides input for preparation of project plans as
requested, and reviews final versions and provides
recommendations.
Reviews and recommends approval of project baselines to
the Acquisition Executive.
Provides support to both the ESAAB and Program BCCBs,
including training and consultation for the Program and
Project BCCBs as required.
Ensures programs keep project documentation, reporting
and information current.
Project Execution
1 Performs independent project assessment at each decision
point and presents findings/recommendations to the
Acquisition Executive.
Section 35
2 Completes staff work and coordination to bring the
decision to the Acquisition Executive for approval.
3 Provides evaluation and recommendations on baseline
changes to the Executive Level Change Control Boards.
4 Acts as focal point for development and dissemination of
cost estimating data bases and methodologies for the
Department.
Vertical line denotes change
DOE 47O0.1 Chg 1 I-196-2-92
1
2
3
4
(2)
5 Conducts independent cost estimates prior to Key Decision
1, at the completion of Title I and II designs and at
critical phases of the project, as deemed necessary.
6 Conducts independent cost estimates, as appropriate, of
change control actions for review and approval by the
Acquisition Executive (Level O BCCB).
(d) Analysis and Evaluation
Tracks execution against project baselines and provides
independent assessment of project performance against
approved baselines. Provides coordinated recommendations
to the Acquisition Executive.
Provides coordinated quarterly summary project
performance reports covering project execution and issues
to senior management.
Provides recommendations to Program Secretarial Officers
and Acquisition Executive for periodic project reviews.
Conducts program/project validations, in conjunction with
the program organizations, and in coordination with the
Chief Financial Officer and the Office of Policy,
Planning and Analysis in support of the annual Internal
Review Budget.
Director of Procurement, Assistance and Program Management (PR-1)
performs the following duties:
(a) Policy Development. Provides expertise in procurement,
financial assistance, and business management to support
development of Departmental project management policies.
(b) Project Development. Assists program offices in development
and subsequent implementation of procurement matters on
projects. These procurement and assistance services are
required for MSAs and designated MPs. Assists program and
project offices in development of the procurement strategy
through provision of direct advice and counsel, as well as
through business strategy groups, and concurs in the project
plan and related documents to assure satisfactory business
arrangements.
(c) Project Execution. Responsible for supporting procurement
aspects of project execution. Field and Headquarters
procurement organizations provide assistance to project
organization in the planning of individual procurement
actions, and carrying out necessary actions to solicit,
award, and administer procurements.
Vertical line denotes change
I-20 DOE 4700.1 Chg 1
6-2-92
(d) Other Responsibilities. The Director has specific
responsibilities in two other areas that impact project
management:
1 Personal property management; and
2 Materials allocation program.
(3) The Chief Financial Officer is responsible for budget formulation
and execution activities including:
(a) Assurance that financial controls are established and
maintained in accordance with legislative authority;
(b) Development and publication of budgeting, accounting, and
other policies necessary for implementation of this Order;
(c) Preparation of financial reports as may be requested or
required by Congress, the Office of Management and Budget,
or the General Accounting Office;
(d) Coordination on financial aspects of reports or other
documents required by this Order; and
Section 36
(e) Determination in conjunction with the component program
support offices whether congressional notification is needed
prior to commitment of funds to any action which will result
in, or as a result of, a change in scope, Total Estimated
Cost (TEC), major thrust, or other significant departure
from the previous congressional budget presentation.
(4) General Counsel (GC-1) provides legal counsel to assure that
activities are planned and conducted in accordance with statutory
and regulatory requirements. Counsel organizations in field
organizations perform the specific legal functions necessary for
project execution.
(5) Assistant Secretary for Environment, Safety, and Health (EH-1)
has three basic roles in the PMS.
(a)
(b)
Coordination of Energy Policy. Has primary staff
responsibility. Draft policy, however, is coordinated with
Program Secretarial Officers before issuance: This role
focuses on the front end of the acquisition process, most
specifically, on the Department-wide budget and program
planning process.
Identification, Coordination, and Integration of Major
Issues Analyses and Decisions. These studies are performed
on selected policy and program issues which require the
Secretary’s priority attention for the formulation of budget
and legislative programs.
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
I-21
1
2
3
(c) Independent Review. Independent review of the conformance
to laws, regulations, and DOE Orders related to environment,
safety, and health.
These responsibilities are accomplished through the
following procedures:
The review and approval of environmental documentation,
by assuring compliance with the National Environmental
Policy Act;
The independent overview of operational environment,
safety, and health (occupational and public), and quality
assurance requirements/activities including the safety
analysis and review systems; and
Independent management appraisals of DOE programs and
9.
projects subject to this project management system in the
areas of environmental safety and health protection and
quality assurance per DOE 5700.6C and DOE 5480.1B.
(6) Director of Organization, Resources and Facilities Management
(AD-1O) is responsible for overall facilities management, cost of
ownership issues, specifically in the areas of general design
criteria, In-House Energy Management, maintenance management,
real estate, site development planning, utilities management, and
value engineering.
SUPPORT TO THE PROJECT MANAGER. The project manager and/or the Head of
the Field Element will develop a proposed project organization. The
project organization will be summarized in the project plan and detailed
in the project management plan.
a. Organizational Options. Because of the diversity of projects and
field organizations, there is not a standard project organization.
The project organization can range from a relatively large dedicated
project office for large, complex projects to a single project manager
(having responsibility and authority for more than one project)
receiving matrix support for all activities. The typical project
organization consists of a small, dedicated project office (or
designated individual) with general matrix support provided by the
field organization. This project office reports to the Head of the
Field Organization, generally through an assistant manager.
Section 37
b. Other Than Departmental Support. In addition to DOE personnel,
support from other Federal agencies and/or contractors may be utilized
to extend and strengthen the capabilities of the Departmental managing
organization. Support from other Government agencies (such as the U.S.
Army Corps of Engineers) is obtained through use of interagency
agreements. Contractor support may come from operating contractors or
specialty-type contractors.
Vertical line denotes change
I-22 DOE 4700.1 Chg 1
6-2-92
c. Key Government Functions. Provisions must be made for Government
performance of those responsibilities that cannot be delegated to
contractors. These responsibilities include:
(1) Determination of project and contract scope;
(2) Establishment of the project management and contracting approach;
(3) Selection of prime contractors as well as the award and
administration of prime contracts for work;
(4) Determination of satisfactory contractor performance and
acceptance of completed work;
(5) Assurance of project execution within agreed upon objectives;
(6) Direction and supervision of Government employees;
(7) Distribution and accountability of Government funds;
(8) Assurance of project cost, schedule, and technical performance;
(9) Development, justification, and approval of input into the
President’s budget; and
(10) Management of project contingency funds.
10. MANAGEMENT ASSIGNMENTS.
a. Project Management Assigmment. Responsibility for project management
will generally be assigned to the field element with the greatest
expertise in the program area under which the project falls. If no
single field organization has major exclusive expertise in the program
or project subject area, the program manager will identify an
appropriate field organization for project management on the basis of
staff experience and availability. The cognizant program manager and
the Head of the Field Element will jointly decide the project
management assignment and will issue a charter to the cognizant
Program Secretarial Officer as part of the project plan.
b. Establishment of Special Project Office. Under extraordinary
conditions, a special project office may be established separate from
the existing field structure. A recommendation for this office shall
originate with the cognizant program manager, program director, or
Program Secretarial Officer. The recommendation will be coordinated
with the Office of Procurement Assistance and Program Management and
the Office of Organization, Resources and Facilities Management, and
will be submitted to the Acquisition Executive for approval.
(1) A special project office imposes the heaviest burden on the
Department in terms of Government personnel, and exceptional
justification is required to support a recommendation to
establish one. The specific level of support by a field
organization and its reporting relationship will be established
Vertical line denotes change
DOE 4700.1 Chg 1 I-23 and (I-24)
6-2-92
on a case-by-case basis in consultation with the field
organization involved.
(2) The office shall report to the program office of the cognizant
Program Secretarial Officer or as directed by the Secretary.
Vertical line denotes change
DOE 4700.1
3-6-87
I-25
PART D - MAJOR SYSTEM ACQUISITIONS AND MAJOR PROJECTS
1. INTRODUCTION.
a. OMB has issued an Executive Department policy statement entitled
“Major System Acquisitions” (OMB Circular A-109). This circular
establishes policy to be followed by executive branch agencies in the
acquisition of major systems and provides basic policy guidance for
the PMS. DOE MSAs and MPs shall conform to these requirements.
Section 38
b. OMB and DOE policy requirements include:
(1) Top level management attention to the determination of agency
mission needs and goals;
(2) An integrated systematic approach for establishing mission needs,
budgeting, contracting, and managing programs;
(3) Early direction of research and development efforts to satisfy
mission needs and goals;
(4) Improved opportunities for innovative private sector
contributions to national needs;
(5) Avoidance of premature commitments to full-scale development and
production/operations; and
(6) Early communication with Congress in the acquisition process by
relating MSAs to agency mission needs and goals.
(7) Early identification of projects requiring major siting
decisions.
c. The nature of DOE projects requires that consistent policy be
established for their management and that all participants understand
the objectives of the project. It is important that all Departmental
participants coordinate their efforts in order to:
(1) Assure proper coordination by all appropriate line and staff
elements beginning with program or project inception;
(2) Relate program or project objectives to national planning
documents, mission area assignments, strategy papers, and
legislation, as appropriate;
(3) Assist in determining priorities among programs and projects and,
in turn, relate these to various levels of resource availability;
(4) Avoid commitment of major resources prior to adequate project
definition; and
I-26 DOE 4700.1 Chg 1
6-2-92
(5) Provide program and project managers with a clear view of related
program and project objectives and plans.
2. KEY DECISIONS.
a.
b.
c.
d.
e.
OMB Circular A-109 also specifies certain key decisions and outlines
the logical sequence of activities in the MSA process. The key
decisions and sequencing provide DOE w
how to meet the requirements of the po
Figure I-5 outlines the key decisions.
Key decisions are approved by the Acqu
and selected MPs. Program Secretarial
on major MPs not reserved for the Acqu
i
l
th flexibility in determining
icy and staff key decisions.
sition Executive on all MSAs
Officers make the key decisions
sition Executive. Key
i
i
decisions on other projects, when required, shall be made by the
Program Secretarial Officer or formally delegated.
Project baselines are related to the key decisions. Key Decision O,
Approval of Mission Need, allows the Conceptual Design Report (CDR) to
be developed which provides the data required to develop initial
technical, cost, and schedule baselines. Initial technical, cost, and
schedule baselines are established at Key Decision 1 based on the CDR
and other support documentation. The initial baselines will be
refined and updated as the project proceeds through preliminary design
(Title I), final/detailed design (Title II), construction/full scale
development, testing, and successful start of operations. For
projects funded from operating funds, appropriate equivalent decisions
points reflecting significant expenditure of funds will be identified
by Secretarial Officers and recommended to the Acquisition Executive.
The baselines will be managed using the change control system at the
executive level as defined in Chapter III and project change control
systems for those changes not requiring Headquarters approval.
Updated baselines reflecting incorporation of approved Baseline Change
Requests will be presented at each key decision to the ESAAB or
Program Secretarial Officer, as appropriate.
Section 39
An Independent Cost Estimate (ICE) will be conducted prior to Key
Decision 1 based on the proposed project baselines established from
the CDR and supporting CDR data. The original baselines ICE will be
refined at the completion of preliminary design (Title I) and
final/detailed design (Title II) to provide independent project cost
assessments prior to Key Decision 2 and Key Decision 3, respectively.
The project manager will notify the Office of Program/Project
Management well in advance of the need to update an ICE.
Key decisions may be expanded to include additional Acquisition
Executive milestones or decision points, as appropriate, between the
standard key decisions. These expanded decision points will ensure
the proper Headquarters visibility and ESAAB action prior to all major
commitments of resources for a project. Key decisions and expanded
decision points shall be integrated into the project summary schedule.
Vertical line denotes change
DOE 4700.1 Chg I-27
KEY DECISION O - Approval of Mission Need
Prerequisite for requesting conceptual design funding in the
internal review budget cycle.
Approval must occur prior to the planning stages of the
annual internal review budget cycle and submission of
initial funding requests to the Office of Management and
Budget and Congress.
Documentation Requirement: Approving Mission Need.
Prerequisite for release of appropriated funding by the CFO.
KEY DECISION 1 - Approval of New Start
Prerequisite for requesting project line item finding in the
internal review budget cycle.
Approve Project Plan including initial project baselines.
Initial technical, cost and schedule baselines for the
project will be based on the CDR and its support
documentation.
Implement a change control system delineating specific
responsibilities, authority and accountability at the
appropriate management levels for changes affecting the
project baselines.
Other input to the decision process includes completion of
the budget validation, and independent cost estimate, and
the project data sheet.
Prerequisite for release of appropriated funding by the CFO.
KEY DECISION 2 - Approval to Commence Title II, or Final/ Detailed
Design
Scheduled prior to start of Title II, or Final/Detailed
Design.
Input to decision process includes update to the project
baselines reflecting completion of preliminary design (Title
I), and an independent cost estimate.
Figure I-5
Major System Acquisition and Major Project Key Decisions
Vertical line denotes change
I-28 DOE 4700.1 Chg 1
6-2-92
● Current project plan reflecting approved baseline changes,
as appropriate.
● Approval to begin long-lead procurement, if applicable.
● Prerequisite for release of appropriated funding by the CFO.
KEY DECISION 3 - Approval to Commence Construction or Enter Full-
Scale Development.
● Scheduled prior to start of construction or full-scale
development.
● Input to the decision process includes the update of project
baselines reflecting completion of final/detailed design
(Title II) and an independent cost estimate.
● Current project plan reflecting approved baseline changes,
as appropriate.
● Other input to the decision process includes evidence of
readiness to process, appropriateness of timing and a firm
baseline.
● Prerequisite for release of appropriated funding by the CFO.
KEY DECISION 4 - Approval to Commence Operation/Production
Section 40
● Scheduled prior to the transition from acquisition to
operation/production; transition is not formally made until
demonstrated capability to meet technical performance goals
specified in the baseline.
● Prerequisite for released of appropriated funding by the
CFO.
Figure I-5 (continued)
Major System Acquisition and Major Project Key Decisions
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
I-29
3.
f. Each key decision point (including expanded decision points) will
require ESAAB approval prior to the releases of appropriated funds by
the Chief Financial Officer to proceed with the next phase of the
project.
g. In the event that there are no key decisions or expanded decision
points in a given year for the project, an Energy System Acquisition
Review (ESAR) will be scheduled to advise the Acquisition Executive on
current project status. Attendance at the ESAR will be the same as an
ESAAB meeting with the Acquisition Executive serving as the chairman.
The ESAR will be conducted similar to an ESAAB meeting in that the
Acquisition Executive will review project performance (cost, schedule,
and technical) against current baselines. The Acquisition Executive
may delegate the responsibility for the ESAR to the cognizant Program
Secretarial Officer.
DESIGNATION OF MAJOR SYSTEM ACQUISITIONS AND MAJOR PROJECTS. Projects
that fulfill the prescribed MSA or MP criteria will be so designated by
the Acquisition Executive using the following procedures:
a. The Office of Program/Project Management and Control, which maintains
DOE 4240.1, will develop a list of MSAs and MPs. The list is
submitted to the program organizations for review and comment.
b. Comments and unresolved designations which cannot be resolved at the
program management levels will be forwarded to the Acquisition
Executive for resolution. Appropriate notification of changes or
additional designations is made to OMB and its Office of Federal
Procurement Policy. Subsequently, a change to DOE 4240.1K,
DESIGNATION OF MAJOR SYSTEM ACQUISITION AND MAJOR PROJECTS (or its
successor) is issued.
c. If the approval of any change by a Level O, 1, or 2 Baseline Change
Control Board (BCCB) action caused the Total Project Cost for a
project to change from either the threshold for a MSA ($100 million),
or for a MP ($50 million), the chairperson of the Level 1 BCCB
approving the change shall be required to immediately notify the
Director, Office of Procurement, Assistance and Program Management
(PR-1) of the situation. Specifically, the Level 1 BCCB chairperson
is required to provide such notification in writing within 5 working
days of the approval of the project action which caused the change.
The notification letter shall provide complete explanation of the new
technical, cost, and schedule baselines and status of the project
relative to key decision points to enable PR-1 to make determination
whether an Energy System Acquisition Advisory Board/Energy System
Acquisition Review should be convened, and whether DOE 4240.1 should
be revised to include the subject project.
Vertical line denotes change
I-30
4.
DOE 4700.1 Chg 1
6-2-92
DOE ACQUISITION PROCESS.
a.
b.
Each MSA or MP is directed through the acquisition process by the
project manager who has a charter which provides sufficient authority
and resources to accomplish the stated project objectives and goals.
Layers of authority between the project manager and the responsible
Program Secretarial Officers are kept to a minimum. Figures I-5 and
I-6 denote the process and phasing of MSAs. Figure I-7 provides the
key events in the acquisition process. See Attachment I-3 for MSA
procedures.
Section 41
In order to effectively carry out DOE’s missions, the acquisition
process requires that DOE management:
(1) Express needs and program objectives in DOE mission terms to
encourage innovation and competition in creating, exploring, and
developing alternative energy system options and design concepts.
(2) Conduct initial activities in the system acquisition process to
allow competitive exploration. of alternative energy system
options in response to mission needs.
(3) Establish clear lines of authority, responsibility, and
accountability for management of MSAs.
(4) Maintain a capability to:
(a) Review, monitor and evaluate total project costs, schedule,
and performance during the acquisition process and provide
assessments for consideration at key decision points or when
significant baseline variances occur.
(b) Estimate life cycle costs during system design, concept
evaluation and selection, full-scale development, facility
conversion, and production to ensure appropriate tradeoffs
among investment costs, operating costs, schedules, and
performance.
(c) Use independent cost estimates of the cost of the project
for the applicable phase of the acquisition process, total
project cost, life cycle cost for comparison purposes.
(5) Report on the accomplishment and status of the acquisition
process. Of particular importance is reporting potential cost,
schedule, or performance threshold breaches before corrective
actions are foreclosed.
Vertical line denotes change
Major System Acquisition--Phase Transition Decision Points
Figure I-6
DOE 4700.1 Chg 1
6-2-92 I-31
PROJECT PLANNING FOR MAJOR SYSTEM ACQUISITIONS OR MAJOR PROJECTS. Three
documents are required during the project approval and execution
processes: the Justification of Mission Need, the Project Plan, and the
project management plan. During the development of these documents,
particular attention must be paid to the following, not necessarily
exclusive, concepts:
5.
a.
b.
Management Information. Management information should be limited in
all areas of activity to information essential for effective control.
Normally, the information required by management for decision-making
is obtained from the same data bases used by the contractor. A
realistic work breakdown structure is developed for each project as a
framework for planning and assignment of responsibilities, contracting
and reporting progress.
Use of Government or Non-Profit Organizations. Government
laboratories, federally funded research and development centers,
educational institutions, and other non-profit organizations that
submit alternative major system design concepts for consideration
shall not participate in the evaluation process on those systems.
Care must be taken not to place DOE management and operating
contractors, Government laboratories, and federally funded research
and development centers in competition with private industry, and
further, to assure that inappropriate assignments of work are not made
to such DOE management and operating contractors, Government
laboratories, and federally funded research and development centers
when such work is more appropriate and better suited for performance
by the private sector. If further exploration of an alternative
system design concept is deemed appropriate, that concept may be made
available to industry to propose on the continued development stages.
(1) Departmental operations offices, energy technology centers, and
laboratories may be assigned development tasks to complement a
major system development.
Section 42
(2) DOE energy technology centers and laboratories may be used as
technical arms of the project management office, especially in
matrix management organizations. Typical assignments may include
actions such as studies, analyses, technology developments, risk
and cost reduction efforts, and development test and evaluation.
Affordability. The Program Secretarial Officer will initially
describe the magnitude of resource commitment required to acquire a
system in the Justification of Mission Need and, subsequently, in the
Project Plan. At Key Decisions 1 and 2, affordability considerations
will be used as a factor in determining the selection of alternative
concepts. At Key Decisions 3 and 4, favorable decisions may not be
made unless the system’s project acquisition and operating costs are
available.
Timeliness. Potential savings in acquisition time should be balanced
c.
d.
against cost and technical risks or national urgency. When technical
and cost risks are low, or when the urgency to develop an alternative
energy system exceeds high technical and costs risks, the cognizant
Vertical line denotes change
I-32
e.
f.
g.
DOE 4700.1 Chg 1
6-2-92
Program Secretarial Officer should recommend, with caution, minimizing
acquisition cycle time. This may be accomplished by omitting a phase
of the acquisition process or by overlapping or combining activities
within a phase.
Competitive Concept Development. Alternative solutions to the mission
need shall be obtained competitively unless the Acquisition Executive
has approved pursuing a single concept. Even when pursuing a single
concept, competition shall be employed in development of the concept.
The widest range of acquisition alternatives to satisfy the mission
need shall be considered. At a minimum, solicitations shall outline
the need in mission terms; identify schedule objectives and
constraints; and present project system cost objectives.
Cost Estimates. The validity of conclusions reached at each decision
point depends upon the quality and consistency of cost, schedule and
technical estimates presented in proposed changes to the updated
project plan. Broad intervals of uncertainty and of risk must be
expected early in the acquisition process, with smaller intervals
developed as the project matures and uncertainty and risk decrease.
(See Chapter IV. )
Cost Participation. Cost participation is a generic term denoting any
situation in which the Government does not fully reimburse the
performer for all allowable costs necessary to accomplish the
project. The term encompasses cost sharing, cost matching, cost
limitation, participation in kind, and similar concepts.
(1) In research, development, and demonstration projects for which
there is a reasonable expectation that the performer will receive
present or future economic benefit as a result of performance, it
is Departmental policy to obtain cost participation.
(2)
(3)
Cost participation should begin at the inception of a project
with the Government and the performer each bearing a percentage
of each dollar of allowable costs, including any overrun costs,
as they are incurred. Net income, if any, should be shared in
proportion to the accumulated investment of the parties at the
time of accrual. Failure to reach agreement on cost participation
from project inception may be sufficient reason for project
cancellation.
Section 43
Specific cost participation arrangements must be determined on a
project-by-project basis. The concept of sharing risks and
benefits equally over the life of the project should be the basis
for such a determination. The actual share may be adjusted for
relevant business, technical, and risk factors, particularly as
the project proceeds through its life cycle. Effective
competition will be the ultimate evaluation tool in determining
whether proposals accurately reflect the risks and benefits
anticipated by the offerors. Management responsibilities and
authorities generally should reflect the relative proportion of
funding from each party during the phase being executed.
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
I-33
(4) Since most cost participation projects span several years,
funding of the Government’s share of construction costs should be
sought to demonstrate the Government’s intent to complete the
project. Budgets and program plans should be based on equal
share concept adjusted for relevant business, technical, and risk
factors.
Vertical line denotes change
Key Decisions in the Acquisition Process
for Construction or Development Projects
Figure I-7
DOE 4700.1
3-6-87
I-35
1.
2.
3.
PART E - OTHER PROJECTS
INTRODUCTION. Other projects are not subject to the policy of OMB Circular
A-109. However, other projects of significant value should adhere to the same
management conditions and practices as larger projects to the extent prac-
ticable. The program Secretarial Officer, program manager, or the Head of the
Field Element is responsible for proper application of PMS, choosing manage-
ment practices commensurate with the size, scope and complexity of the pro-
ject.
OTHER PROJECT DECISIONS.
a. Decisions on other projects should be made by the program Secretarial
Officer, the program manager, the Head of the Field Element, or the pro-
ject manager. The authority should be delineated, typically in a respon-
sibility matrix.
b. In a manner similar to key decisions, there should be an affirmative
determination to:
(1) Begin a project;
(2) Commence Title II, or Final/Detailed Design;
(3) Start construction, or enter full scale development; and
(4) Operate or produce (as necessary.)
c. In addition, major resource commitments also should be made only following
an affirmative decision.
OTHER PROJECT MANAGEMENT PROCESS.
a. The process for managing other projects is similar to that used in
managing large projects:
(1) There must be proper coordination of line, staff, and contractor
organizations;
(2) The project must be related to a mission area assignment, to a
mission need, and to Departmental goals; and
(3) Making major resource commitments without adequate project definition
must be avoided.
I-36
b.
DOE 4700.1
3-6-87
Similarly, the progression of projects is the responsibility of a single
person having clear lines of authority and communications with respect to
the project. This individual will be responsible for planning, acquisi-
tion, environmental impact, execution, and transition as these areas
relate to the project.
DOE 4700.1 Chg 1
6-2-92
Attachment I-1
Page I-37
ENERGY SYSTEM ACQUISITION ADVISORY BOARD PROCEDURES
1. PURPOSE. The purpose of the Energy System Acquisition Advisory Board
(ESAAB) is to assist the Acquisition Executive in the decision-making
process for MSAs and selected MPs. The ESAAB process is also utilized for
site selection determinations. In such circumstances, the ESAAB
membership and procedures are as described in paragraph 4, below.
Section 44
2. MEMBERSHIP AND RESPONSIBILITIES.
a. Members of the ESAAB.
(1) The Deputy Secretary/Under Secretary serve as the Acquisition
Executive for their respective program areas by direction from
the Secretary of Energy. The Acquisition Executive chairs the
ESAAB and has approval authority for MSAs and selected MPs.
(2) The Assistant Secretary for Environment, Safety, and Health
advises the Acquisition Executive on:
(a) Environmental acceptability and readiness of the project to
proceed; and
(b) Environmental needs for ensuring phases.
(3) The General Counsel advises the Acquisition Executive on:
(a) Acquisition and construction issues;
(b) Licensing plan assessment;
(c) Legislative or executive action impact assessment;
(d) Patent issues; and
(e) Environmental requirements.
(4) The Chief Financial Officer advises the Acquisition Executive
on:
(a) Budget formulation and execution status;
(b) OMB and congressional concerns and positions; and
(c) Other financial management issues.
(5) The Director of Administration and Human Resource Management
advises the Acquisition Executive on:
(a) Real estate management policy and procedures;
Vertical line denotes change
Attachment I-1
Page I-38
DOE 4700.1 Chg 1
6-2-92
b.
c.
d.
(b) Facilities and maintenance management;
(c) Site development planning;
(d) Utilities management;
(e) Value engineering; and
(f) Personnel issues.
(6) The Director of Procurement, Assistance and Program Management
advises the Acquisition Executive on:
(a) Adequacy of
portions of
(b) Procurement
(c) Conformance
the acquisition strategy, including the related
the project plan;
and contractual policy assessment;
to and implementation of project management
system policies and procedures; and
(d) Results of independent cost estimates in support of key
decisions or the Executive Change Control Process.
Members to the ESAAB, for selected projects, include the Director of
Energy Research, Assistant Secretary for Nuclear Energy, and the
Director of Nuclear Safety. These members will provide an independent
assessment to the Acquisition Executive of potential concerns/issues
at its current phase and ensuing phases.
The Acquisition Proponent. The acquisition proponent will normally be
the Program Secretarial Officer whose MSA or selected MP is being
presented for decision. The acquisition proponent is responsible for:
(1) Conducting the pre-ESAAB review;
(2) Providing to the ESAAB Secretariat a draft of proposed changes to
the project plan and related documentation for executing the
project; and
(3) Providing the final updated project plan to the board Secretariat
after decisions have been made for review and approval by the
Acquisition Executive.
ESAAB Secretariat. The Associate Director for Program/Project
Management & Control serves as the ESAAB Secretariat, providing:
(1) Staff support to the Acquisition Executive and board members for
ESAAB and ESAR presentations (e.g., schedules, agenda, pre-
briefings and presentation requirements);
Vertical line denotes change
DOE 4700.1 Chg 1 Attachment I-1
6-2-92
3.
e.
f.
Page I-39
(2) Independent cost, schedule and technical assessments and analyses
of project planning, baseline changes, key decisions, expanded
decision points, other significant decisions, and budgetary
commitments; and
(3) Project management policy implementation activity and
assessments.
Section 45
Other Assistant Secretaries and Heads of Headquarters Elements may be
asked to participate as advisors when appropriate. Other officials
such as the cognizant DOE Field Office manager may be invited to serve
as advisors to the acquisition proponent.
The project manager will normally present the issues, except for Key
Decision O, and recommended decision for consideration to the board.
The program manager might present a portion of the briefing focusing
on the broader program considerations and issues, while the project
manager stresses the status of the project and problems/issues at the
project level. Other special reports may be presented by either, as
appropriate, such as the results of an independent cost estimate or
technical review.
ESAAB PROCEDURES. The Acquisition Executive may choose to make a decision
and issue a board memorandum without a formal board meeting. Dispensing
with the formal meeting shall be considered when the preliminary review to
a scheduled meeting indicates that there are not substantial issues which
would require a meeting. In this case, an action memorandum will be
prepared and submitted by the acquisition proponent stating the factors in
support of the decision requested. This action memorandum will be
coordinated with board members, advisors and others indicated by the
Chairman before it is forwarded for decision. Following approval by the
Acquisition Executive, the Secretariat will document the decision and the
actions and/or agreements that may have resulted from the process.
a. Scheduling of Energ y System Acquisition Advisory Board Meetings.
(1) A decision/review schedule will be developed and maintained
current by the ESAAB Secretariat for those projects which require
a board review because of an acquisition phase decision, siting
decision, problems, or other project developments that merit
management attention. The decision/review schedules will be
distributed to program offices monthly.
(2) Upon approval by the Acquisition Executive, formal scheduling of
reviews will be accomplished by the ESAAB Secretariat.
(3) Unscheduled board meetings may also be called at the request of
the Acquisition Executive or a Program Secretarial Officer.
These requests will be made through the ESAAB Secretariat.
Vertical line denotes change
Attachment I-1
Page I-40
DOE 4700.1 Chg 1
6-2-92
(4) The steps outlined below provide normal working
times and responsibilities for the activities prior to and
immediately following an ESAAB:
Board Schedule.
Calendar
Days
Relative
Responsible to
Office Meeting
a.
b.
c.
d.
e.
f.
g.
h.
i.
Draft submission to ESAAB members
of Justification of Mission Need,
Project Plan or other appropriate
baseline documentation
Pre-ESAAB meeting (Dry-run)
Program
Dry-run presentation comments
provided to Program Office
Final draft of Justification of
Mission Need, Project Plan or
other appropriate baseline
documentation
Presentation charts submitted to
OP/PM and ESAAB membership
Board briefing books/materials
prepared
Acquisition Executive pre-brief
ESAAB presentation
Board decision memorandum for
Acquisition Executive’s approval
Project documentation reflecting
board decisions provided for
Acquisition Executive’s approval
and issuance.
Program
Program
OP/PM
Program
Program
OP/PM
OP/PM
Program
OP/PM
OP/PM
60 days
20 days
15 days
10 days
10 days
7 days
5 days
O days
+15 days
+30 days
Section 46
b. ESAAB Preparation. It is essential that the presenters address the
significant issues and problems that are associated with the project;
that these issues and problems be fully coordinated well in advance
with cognizant staff and program officials; and that the Acquisition
Executive and the sponsoring Secretarial Officer receive concise
prebriefings to assure that an informed decision or review will occur.
(1) Project Presentation Review. A draft of the project presentation
shall be provided to the Office of Program/Project Management and
representatives for the board members by the cognizant Program
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
Attachment I-1
Page I-41
Secretarial Officer. The draft presentation will be reviewed for
conformance to DOE orders and policies and to identify any
remaining issues for discussion at the Pre-ESAAB meeting. The
draft presentation shall address, as minimum, the following
administrative actions:
(a)
(b)
(c)
Peer Group Review. The program shall receive a current
written statement of project endorsement for the Acquisition
Executive from their respective peer groups. This action
shall be completed prior to the Pre-ESAAB meeting.
Inspector General/General Accounting Office Check. The
program shall make the necessary contacts to determine the
current audit activity on the project and provide a written
statement on the status to the Acquisition Executive. This
action shall be completed and reviewed at the Pre-ESAAB
meeting.
Congressional Briefings. The program shall notify the
appropriate congressional committee staffs on project status
and determine interest or support. A written statement on
the congressional committee(s) response/position must be
completed following the Pre-ESAAB meeting and provided to
the Acquisition Executive prior to the ESAAB. This action
applies to Key Decisions 2 and 3.
(2) Pre-ESAAB Meeting (Dry-Run). The program and project managers
will schedule and conduct a “dry-run” of the developed
presentation for the sponsoring Secretarial Officer for review
and resolution of issues prior to the ESAAB meeting. The Office
of Program/Project Management and board member representatives
should also be invited to participate in a final exchange of
ideas, assure compliance with Department policy/procedures,
discuss and resolve outstanding issues, determine the status of
any independent cost estimating requirements (where applicable),
cover the status of administrative actions, and set a schedule
for remaining actions. At the conclusion of the “dry-run,” a
recommendation shall be made to the Acquisition Executive by the
Office of Program/Project Management on the readiness of the
project to proceed with the scheduled ESAAB meeting based on the
completeness of material and administrative actions presented at
the “dry-run.”
(3) Acquisition Executive Prebrief. A prebriefing is conducted by
the Office of Program/Project Management for the Acquisition
Executive to assist in his preparation for the board meeting.
The objectives of this prebriefing are to acquaint the
Acquisition Executive with a brief background and description of
the project, provide an independent assessment of remaining
issues/problems to be presented, clarify any technical and
management items and provide a final status on administrative
actions so as not to consume too much time during the formal
meeting. In addition, an independent assessment of the project
and issues will be presented with recommended solutions. Any
Section 47
Vertical line denotes change
Attachment I-1
Page I-42
DOE 4700.1 Chg 1
6-2-92
3.
4.
feedback from the prebrief shall be provided immediately by the
Office of Program/Project Management to the cognizant Program
Secretarial Officer.
ESAAB Memorandum. The board Secretariat shall prepare a memorandum
summarizing the results of the meeting.
a.
b.
The memorandum will specify decision(s) reached, actions assigned,
results of special studies and assessments, limitations associated
with approvals, resource levels which may be used for budgetary and
organizational planning, constraints on systems development and
definition, schedules for accomplishing action items, and the time
frame for the next meeting. A summary of the approved cost, schedule
and technical baselines will be attached to the memorandum.
The Secretariat will coordinate the proposed memorandum with the
members and advisors prior to forwarding it to the Acquisition
Executive. Dissenting views will be included in the package.
Signatures of each board member will be obtained on the final
document.
SPECIAL ESAAB FOR SECRETARIAL SITE SELECTION DECISIONS.
a. Responsibilities.
(1)
(2)
(3)
(4)
(5)
(6)
(7)
The ESAAB will be responsible for approving project site
selection decisions.
Program outlay offices will notify the Office of Program/Project
Management when initiating conceptual design on any project which
involves a site selection determination option.
The Office of Program/Project Management will maintain a list of
such projects and will advise the Acquisition Executive of the
schedule for the upcoming decisions.
The Office of Program/Project Management will include an
evaluation of siting considerations in the checklist used in the
project validation process.
Site selection criteria will be established and approved, and
site characterization studies and evaluations will take place
during the early design phase of the acquisition process.
A site selection decision will occur at the earliest appropriate
time during advanced development or preliminary design, although,
in some cases, site selection may not be feasible until Key
Decision 2, Start of Engineering Development or Detailed Design.
The Office of Program/Project Management will assist program
organizations in preparing for ESAAB site selection meetings.
Paperwork and administrative burdens associated with these
presentations will be minimized. Presentations will focus on
issues and ensure adequate coverage of all viable options.
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
Attachment I-1
Page I-43
5.
b. Procedures. The site selection decision process is as follows:
(1) The ESAAB will be convened to enable the Acquisition Proponent to
present background information related to the project and the
siting considerations.
(2) Detailed discussion of the various siting options, including the
pros and cons of each, will be conducted.
(3) The Acquisition Proponent will present specific recommendations
for a siting decision. Supporting and/or opposing views of
ESAAB members will then be considered, after which the ESAAB
Chairman will make the siting decision(s).
ESAAB INVOLVEMENT FOLLOWING SPECIAL INDEPENDENT SCIENTIFIC OR TECHNICAL
REVIEWS OF PROJECTS AND PROGRAMS.
a.
b.
Purpose. When directed by the Acquisition Executive, a special
independent scientific or technical review will be performed if
circumstances are presented that could potentially influence a project
or program from continuing in an effective manner. If the findings of
such a review will result in significant program or project
redirection, the ESAAB will be included in the decision-making
process.
Section 48
Responsibilities.
(1) The Program Secretarial Officers have the responsibility for
technical reviews of their programs or projects and will advise
the Acquisition Executive of events which could “trigger” an
independent scientific or technical review of any of their
programs or projects.
(2) The scientific advisor, when requested by the Acquisition
Executive, will organize independent panels to conduct scientific
or technical reviews of the project and will work with the Office
of Program/Project Management and Control to fully integrate the
cost, schedule and technical aspects into the review and
subsequent recommendations. Technical reviews will be conducted
in a manner which minimizes disruption and delays in the
accomplishment of ongoing projects.
(3) The Office of Program/Project Management and Control will:
(a) Review each new or proposed MSA and MP in order to assure
that high risk technical issues are identified and ensure
that a meaningful technical baseline is included in the
project plan.
(b) Apprise the scientific advisor whenever a potential
requirement for a review appears to be indicated.
Vertical line denotes change
Attachment I-1 DOE 4700.1 Chg 1
Page I-44 (through I-46) 6-2-92
(c) Independently track programs and projects and advise the
Acquisition Executive, of events that could “trigger” an
independent technical review.
(d) Arrange for a presentation to the ESAAB after appropriate
coordination with the Program Secretarial Officers
concerning review of the cost, schedule and technical
status. The cognizant Program Secretarial Officers will be
provided the opportunity to discuss the independent review
at the ESAAB meeting.
c. Events Which Will “Trigger" Independent Reviews. In addition to the
normal review of the project at the key decision points, certain
events could “trigger” an independent review. Examples of such events
are:
(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
Significant program redirection.
Technical problems such as original technical goals or criteria
not achievable.
Basic assumptions on which the project was based have changed.
Advent of a better technology significantly impacting the
project’s mission.
Changed external conditions, markets, economics, etc.
Significant funding constraints.
Lessons learned from other similar projects.
Recommendations from scientific advisor.
Requested by the Acquisition Executive.
Regulatory redirection when obtaining permits.
Vertical line denotes change
6-2-92
DOE 4700.1 Chg 1 Attachment I-2
Page I-47
GUIDELINES FOR PREPARATION FOR ESAAB MEETINGS
1.
2.
3.
GENERAL. These guidelines have been prepared to aid program and project
managers in their preparation of presentation materials for ESAAB
meetings. Attached is a set of sample charts. They may be augmented by
such additional charts that the managers feel are needed to illustrate
project systems, problems, issues, or other pertinent factors.
Presentation materials should be minimized to the extent practical.
COMPOSITION. Each presentation will be organized as followings:
a. Introduction and purpose of meeting;
b. Description of project;
c. Background;
d. Objectives and baseline;
e. Organization;
f. Readiness to proceed;
g. Problems/issues/items of concern; and
h. Summary of key points and next steps.
CHARTS. The discussion that follows describes the information to be
included on the viewgraph charts. All charts shall use standard DOE
notation, as applicable.
Section 49
a. Chart 1, Title Page. Indicate the official name of the project, the
name of the acquisition proponent, and the name of the presenters.
State the ESAAB decision that will be requested at the meeting.
b. Chart 2, Project Technical Process. Show a recent photograph or
artist’s conception of the project. Use a technical process flow
chart or similar graphic to summarize how the facility or machine is
expected to function. A history of project related events and a
detailed technical description should be avoided due to time
constraints. The ESAAB members and advisors should be briefed by
their respective staffs or may request a briefing by the Office of
Program/Project Management and Control.
c. Chart 3, Program/Project Objectives and Technical Baseline. State the
key program and project objectives. The relationship between the
program and project objectives should be clear. Show the basic
technical baseline requirements for the project.
Vertical line denotes change
Attachment I-2 DOE 4700.1 Chg 1
Page I-48 6-2-92
d.
e.
f.
g.
h.
i.
Chart 4, Baseline Project Summary Schedule - All Years. To provide an
overview of project activity, display the baseline schedule for the
life of the project. Include all Acquisition Executive decision
points, other critical decisions and events, major milestones
including ES&H milestones that may impact the project’s critical path,
and critical path for project implementation.
Chart 5, Baseline Resource Plan.
(1) This chart shall show the funding authority available and
anticipated. Show both cumulative obligations and costs planned
by fiscal year over the life of the project. Actual costs and
obligations shall be shown against these plans. All costs and
obligations shall be denoted in current-year dollars for the year
of expenditure.
(2) This chart shall address the total project cost and identify the
industry share, if appropriate. It shall also target the total
estimated cost for design and construction.
Chart 6, Project Organization. Show the participating organizations
and their responsibilities in the form of an organization chart. This
is the opportunity to depict the manner in which the project is being
managed. Laboratory/contractor/partner responsibilities should be
included. Also show, in a separate box, a summary of the DOE
staffing, both on-board and planned.
Chart 7, Readiness to Proceed. In a very brief, bullet style manner,
summarize progress, accomplishments and performance to date. Include
the most significant rationale for readiness to proceed and separately
list the subjects of any substantive problems, issues, and/or items
of concern that will be shown on the subsequent charts.
Chart 8, Problems/Issues/Items of Concern. Succinctly state the
problem, issue, or item of concern, list the corrective actions taken
to date, the additional corrective actions required (with dates), and
an assessment of the impact on the project. Prepare a separate chart
for each topic to be discussed in this section. Supplement each of
these charts, as necessary, with whatever illustrative material is
apprormiate to present the problem, issue, or item of concern in a
fully informative manner.
Chart 9, Summary of Key Points and Next Steps. This chart highlights
the key points from the presentation, restates the decision requested,
and identifies the next actions planned following the requested
decision by the Acquisition Executive.
Vertical line denotes change
Chart 1
Section 50
U.S. Department of Energy
Energy System Acquisition Advisory Board
Project ABC
ESAAB Decision Requested:
● Authority to Initiate Construction
Presented by:
Donald D. Doe
Project Manager
Richland Operations Office
May 12, 1984
Fuels and Materials Examination Facility
Attachment
I-2
Page 1-51
Doe
4700.1
3-6-87
DOE 4700.1
3-6-87
Attachment
I-2
Page I-52
Fiscal years
Attachment
I-2
P
a
g
e
I
-
5
4
chart 7
● Project Status:
Problem: Schedule Delay – Weather
Chart 9
¢ Summary of Key Points:
Project ABC
e ESAAB Decision Requested:
e Next Steps Following Decision Requested:
a-¢
-
L8-
T° 002% 300
(@S-I Pue) LS-] abeg
2-1 puawyseriy
DOE 4700.1
3-6-87
MAJOR SYSTEM ACQUISITION PROCEDURES .
1. PURPOSE. TO describe how the Department carries out a major system acquisi-
tion. The acquisition process is accomplished by the following steps (see
Figure I-8, page I-61).
a. Evaluation of Mission Needs.
(1)
(2)
(3)
Program Secretarial Officers conduct mission analysis to identify
mission needs and any alternative energy system options and design
concepts which are based on national planning documents, strategy
papers, or other energy policy and program-related data. A mission
need may result from a deficiency in existing capabilities or the
decision to establish new capabilities in response to a feasible
technological opportunity. Mission needs are independent of any
particular system or technological solution.
Where more than one Departmental Element is involved, roles and
responsibilities of each component will be assigned by the
Acquisition Executive. Two or more organizational elements may be
permitted to sponsor alternative energy system options and design
concepts in order to foster innovation and competition.
When required to satisfy mission responsibilities, contributions will
be made to the technology base by the conduct, support, or spon-
sorship of research; system design concept studies; proof of concept
work; exploratory subsystem development; and tests and evaluations.
b. Exploration of Alternative Systems.
( 1 ) Intended benefits to be derived from major system acquisitions shall
be optimized by competitive exploration of alternative system design
concepts and tradeoffs of capability, schedule, and cost. Care
should be exercised during the initial steps of the acquisition
process not to conform mission needs or project goals to any known
systems or products that might foreclose consideration of
alternatives.
(2) Alternative system design concepts will be solicited from a broad
base of qualified firms through the competitive procurement process.
In order to achieve the most preferred system solution, emphasis will
be placed on innovation and competition. To this end, participation
of smaller and newer businesses should be encouraged. Concepts will
be solicited primarily from private industry, and, when beneficial to
the Government, foreign technology and equipment may be considered.8
I
Attachment I-3 DOE 4700.1
Page 1-60
(3)
(4)
(5)
(6)
(7)
(8)
3-6-87
Requests for alternative system design concept proposals will explain .
the mission need, schedule, cost, capability goals, and operating
constraints. Each offeror will be free to propose his or her own
technical approach, cost and capability goals. In the conceptual and
early development stages, contractors shall not be restricted speci-
fically by detailed Government specifications and standards.
Section 51
Federal laboratories, federally funded research and development cen-
ters, educational institutions, and other not-for-profit organiza-
tions shall also be considered as potential sources for competitive
system design concepts. Ideas, concepts, or technology developed by
Government laboratories or at Government expense may be made available
to private industry through the procurement process or through other
established procedures. Industry proposals may be submitted on the
basis of these ideas, concepts, and technology, or on the basis of
feasible alternatives which the proposer considers superior.
Research and development efforts shall emphasize early competitive
exploration of alternatives as relatively inexpensive insurance
against the premature or preordained choice of a system that may
prove to be either more costly or less effective.
During the period of identifying and exploring alternative system
design concepts, contracts covering relatively short time periods at
planned dollar levels will be used. Parallel short-term contracts
are awarded for those concepts selected for further exploration to
expand on the concepts and reduce technical uncertainties in each
system. Timely technical reviews of alternative system design con-
cepts will be made to effect the orderly elimination of the least
attractive concepts.
When the system is being developed for Departmental use, contractors
shall be provided with operational test conditions, mission perfor-
mance criteria, and life cycle cost factors that will be used in the
evaluation and selection of the system(s) for full-scale development
and production. In addition, relevant operational and support
experience will be provided to assist participating contractors in
developing performance and other requirements for each alternative
system design concept as test and tradeoffs are made.
Development of subsystems that are intended to be included in a major
system acquisition shall be restricted to less than fully designed
hardware (full-scale development) until the subsystem is identified
as part of a system candidate for full-scale development. Exceptions
may be authorized by the Acquisition Executive if the subsystems are
long lead time items that fill a recognized generic need, or if they
have a high potential for common use among several existing or future
systems.
DOE 4700.1
3-6-87
Attachment I-3
Page I-61
(9) Selections from competing system design concept proposal shall be
based on a review by a team of experts, preferably from both inside
and outside the responsible development organization.
c. Title II or Detailed Design.
(1) Advancement to a competitive test/demonstration phase may be approved
by the Acquisition Executive when DOE’s mission needs, program objec-
tives, and project goals are reaffirmed, and when alternative system
design concepts are selected.
(2) Development of a single system design concept that has not been com-
petitively selected should be considered only if justified by urgency
of need or by the physical and financial impracticability of
demonstrating alternatives. Proceeding with the development of a
noncompetitive (single concept) system may be authorized by the
Acquisition Executive. Strong DOE project management and technical
direction should be used for these systems.
(3) Major system acquisitions will be structured and resources planned to
demonstrate and evaluate competing alternative system design
concepts that have been selected. Exceptions may be authorized by
the Acquisition Executive if demonstration is not feasible.
Section 52
d. Full-Scale Demonstration, Development or Construction.
(1)
(2)
Full-scale demonstration or development, including limited produc-
tion, may be approved by the Acquisition Executive when DOE’s mission
need, program objectives, and project goals are reaffirmed, and com-
petitive demonstration results verify that the chosen system design
concept(s) is sound.
Selection of a system(s) and contractor(s) for full-scale
demonstration/development and production/operation shall be made on
the basis of:
(a) System performance measured against current DOE mission need,
program objectives, and project goals;
(b) An evaluation of estimated acquisition and ownership costs; and
(c) The factors as contractors is demonstrated management, fi-
nancial, and technical capabilities to meet project objectives.
Attachment I-3 DOE 4700.1
Page I-62 3-6-87
(3) The project manager will monitor system tests and contractor progress .
in fulfilling system performance, cost, and schedule commitments.
Significant actual or forecast variances shall be brought to the
attention of the contractor for corrective action.
e. Production or Operation. Full production/operation may be approved when
the Department’s mission need, program objective, and project goals are
reaffirmed, and when system performance has been satisfactorily tested,
independent of user organizations, and evaluated in an environment that
assures achievement of objectives under expected operational conditions.
DOE 4700.1 Chg 1
6-2-92
CHAPTER II
STRATEGIC PLANNING, PROJECT PLANNING AND BUDGETING
1.
2.
3.
.
II-1
PART A - PROJECT INITIATION AND PLANNING DOCUMENTATION
INTRODUCTION. This chapter discusses both strategic planning and project
planning and budgeting. The terms “strategic planning” and “project
planning” may be most easily differentiated by discussing who has
responsibility and accountability for each and at what point in time a
departure is made from one to the other for a specific program or project.
STRATEGIC PLANNING. The Department is committed to the preparation of
strategic plans and annual updating of these plans to maintain them
current. This strategic planning will assure that energy, health, safety,
environment, technology, and economics are molded into a mutually
supportive framework. The plans will provide the capability for
integrating horizontally across the entire range of DOE programs to bring
plans and programs into line with near (1 to 5 years), mid (5 to 10
years), and long-term (15 to 20 years or longer) objectives of the
Department.
a. Responsibilities. Program Secretarial Officers shall be responsible
and accountable to the Secretary for the preparation and annual
updating of Department strategic plans, Multi-Year Program Plans, and
Crosscut Plans for which they have been assigned responsibility.
b. Annual Cycle. Each annual strategic planning cycle is focused on the
fiscal year, 3 years beyond the start of the planning cycle (the
budget cycle is 1 year forward from issuance of OMB guidance). The
strategic planning annual cycle is depicted in Figure II-1.
c. Guidance. Guidance on strategic planning is available from the Office
of Domestic and International Energy Policy.
Section 53
PROJECT PLANNING DOCUMENTATION. Project planning documentation is
necessary to establish approved project scope and technical performance
requirements, schedules, resource plans, levels of responsibility and
authority, organizational interfaces, implementation plans, and
accountability. The documentation is needed to assure the execution of
the project within the approved technical, cost, and schedule baselines.
The key documents required by the Project Management System (PMS) are
shown below and in Figure II-2. Detailed outlines and approvals for
project planning documentation for Major System Acquisitions (MSA) and
major projects are included in Attachments II-1 through II-6. Planning
documentation of other projects should be similar in coverage and quality,
although reduced in quantity to reflect the magnitude of the project and
field organization Procedures.
Vertical line denotes change
II-2 DOE 4700.1 Chg 1
6-2-92
ACTIVITY TIMING
1. Secretarial Policies and On Going
Strategies
2. Secretarial Planning Guidance Annually in August
Issued
3. Strategic Plans by Program Completed Annually by
Secretarial Officers mid-September
4. Review and Approval of Annually in September/October
Strategic Plans by the
Secretary
5. Multi-Year Program Plans Completed Annually by
mid-December
6. Program Guidance to Field Annually in late December
7. Identification of Planning Annually in January/February
Issues
8. Secretarial Decisions and IRB Annually in March/April
Guidance
9. Crosscut Plans Completed Annually by mid-July
Figure II-1
Chronology of Events in the Annual Strategic Planning Cycle
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
II-3
JUSTIFICATION OF PROJECT PLAN PROJECT
MISSION NEED (INCLUDING MANAGEMENT
CHARTER) PLAN
MAJOR SYSTEM REWIRED PER REWIRED PER REQUIRED PER
ACQUISITION ATTACHMENT II-1 ATTACHMENT II-2 ATTACHMENT II-4
MAJOR PROJECT REQUIRED PER REQUIRED PER REQUIRED PER
ATTACHMENT II-1 ATTACHMENT II-2 ATTACHMENT II-4
OTHER PROJECTS
$15-50 MILLION
APPROVED DATA RECOMMENDED PER REQUIRED PER
SHEET OR WPAS1/ ATTACHMENT II-2 ATTACHMENT II-5
TOTAL PROJECT
COST (TPC)
OTHER PROJECTS APPROVED DATA RECOMMENDED PER REQUIRED PER
$5-15 MILLION TPC SHEET OR WPAS ATTACHMENT II-2 ATTACHMENT II-5
OTHER PROJECTS APPROVED DATA APPROVED DATA REQUIRED PER
UNDER $5 MILLION SHEET OR WPAS SHEET OR WPAS ATTACHMENT II-5
GENERAL PLANT GROUPED ON GROUPED ON OPTIONAL GENERIC
PROJECTS SINGLE DATA SHEET SINGLE DATA SHEET ONLY
Figure II-2
Project Management System Documentation
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
II-4
a.
b.
Justification of Mission Need. A Justification of Mission Need must
be submitted for Acquisition Executive approval at Key Decision O, for
projects anticipated to be designated as MSAs, and to the cognizant
Program Secretarial officer for approval on major projects. The
Justification of Mission Need and the Short Form Project-Data Sheet
must be approved prior to starting conceptual design. Other projects
are justified and approved on the basis of a project data sheet. The
cognizant Program Secretarial Officer may require a Justification of
Mission Need for significant other projects (e.g., $15-$50 million).
For projects currently well beyond Key Decision O, a Justification of
Mission Need is not required.
Attachment II-1 details the contents and procedures for developing the
Justification of Mission Need. A copy of the approved Justification
of Mission Need shall be attached to the Key Decision O Decision
Memorandum of Record and shall be reviewed at each ESAAB meeting.
Section 54
Project Plan. The project plan, which includes the project charter,
is a summary of the dimensions of the project to be executed,
including objective, schedule, resources, priority, controlled
milestones, and environmental requirements. For MSAs, the project
plan is a contract between Headquarters and the project office for
execution. For major projects, the project plan is an agreement
between the program office and project office for execution with the
project office reporting directly to the cognizant program office.
The project plan documents the initial cost, schedule and technical
project baselines defined in the CDR, and is updated, as required,
throughout the life of the project to ensure current project
baselines. It is prepared as required documentation to obtain
approval to include the project in the congressional. budget and for
Key Decision 1, Approval of New Start. The project plan is an
evolving document which covers the project from its initiation through
its completion. Guidelines for preparing project plans are contained
in Attachment II-2.
(1)
(2)
Major System Acquisitions and Major Project Approval. Project
plans require approval by the Acquisition Executive for MSAs and
major projects. (The cognizant Program Secretarial Officer serves
as the Acquisition Executive for major projects.) The plan
identifies Acquisition Executive and Program Level decision
points and other milestones, as appropriate. Changes to this
document are permitted only in accordance with formal change
control procedures.
Other Project Approval. There is no requirement for a
Headquarters approved project plan for other projects. However,
the Program Secretarial Officer may require such a plan where
significant resources are involved. Where there is not a
requirement, the circumstances do not obviate the need for such a
plan. For other projects, the project data sheet has many of the
Vertical line denotes change
6-2-92
D0E 4700.1 Chg 1 II-5 (through II-8)
ingredients of a project plan and may serve that purpose with
minor additional information. Field organizations should
establish their own procedures for project plan content and
approval.
(3) Standard Baselines Formats. Attachment II-2 provides
requirements and guidance for preparation of technical, schedule
and cost baselines in project plans.
(4) Changes to the Project Plan. Because the project plan reflects
Acquisition Executive approval, it is essential that the plan be
maintained current. Attachment II-3 provides project plan change
control requirements and guidelines.
c. Project Management Plan. The Project Management Plan (PMP) is the
document which sets forth the plans, organization, and systems that
shall be utilized by those responsible for managing the project. The
PMP is developed by the project manager and concurred with by the
Program Secretarial Officer and approved by the Head of the Field
Element. Guidance for preparation of a PMP is provided in Attachment
II-4.
Vertical line denotes change
DOE 4700.1
3-6-87
II-9
PART B - WORK BREAKDOWN STRUCTURE
1. INTRODUCTION.
Section 55
a. Much of the planning, execution, and control of DOE projects revolves
around the work breakdown structure (WBS). DOE/MA-0040, of October 1981,
provides detailed guidance on WBS implementation. The WBS is a graphic
representation that completely defines the project by relating elements of
work to each other and to the end product. It is the prime tool which DOE
uses in performance of its project responsibilities. A complete guide to
the development and use of the WBS is contained in DOE/MA-0040. Figure
II-3 illustrates a typical WBS. The individual products specified in the
WBS are termed “elements.” Each element is a discrete portion of the WBS,
comprising either an item of hardware, service, or data. Descending
levels provide increasingly detailed definition of the end objective. The
number of levels depends on the scope and complexity of the individual
project and the degree of control it warrants. The top three levels of
the WBS for a project are typically subdivided as below. These three
levels are frequently called a summary WBS, or a Project Summary WBS
(PSMBs).
(1) Level one contains only the project end objective. The product at
this level shall be identifiable directly to elements of the DOE
Budget and Reporting Classification Structure.
(2) Level two contains the major product segments or subsections of the
end objective. Major segments are often defined by location or by
purpose served.
(3) Level three contains definable components, or subsets, of the level-
two major segments.
b. WBS Dictionary. The WBS Dictionary lists and defines the WBS elements.
It is prepared initially by the DOE project manager and then expanded by
supporting contractors. It consists of two parts: Part I is an index
which lists WBS elements extended in accordance with the guidance
contained herein, and Part II contains individual entries to describe each
WBS element and the effort associated with it. The WBS Dictionary shall
be revised to reflect changes and shall be maintained in a current status
throughout the life of the project.
2. PREPARATION OF A WORK BREAKDOWN STRUCTURE. The project manager is responsible
for preparation of the project WBS. This WBS in summary form is then included
in the solicitation documents for contractor information. Contractors, in
turn develop a contract WBS to conform to their support of the project. This
flow of activity is illustrated in Figure II-4.
Figure II-3
Work Breakdown StructureTypical
DOE
Project
Management
Responsibility
Contractors
Responsibility
(1 or More)
Figure II-4
Evolution of the Project Work Breakdown Structure
II-12 DOE 4700.1
3-6-87
3. USES OF THE WORK BREAKDOWN STRUCTURE. A WBS shows the relationship of all
elements supporting the project and provides a sound basis for technical cost
and schedule control. Each level of the structure is closely related to a
management sphere within the project, providing the framework for relating
time and cost summaries to appropriate levels of contractor and DOE managers.
A WBS provides both a basis and an integrating mechanism, for managing key
functions of the project. Use of the WBS to support management control is
described below:
a.
b.
c.
d.
e.
f.
Planning and Budgeting. The WBS technique provides a formal structure
which identifies all the products and relates all the work effort required
to meet the project objective. By breaking the total product and effort
into successively smaller entities, DOE can ensure that all required prod-
ucts are identified to the WBS (and hence, charged to the effort) and
actually contribute to the work objective. Figure II-5 illustrates the
relationships among work, schedule, and budget integration.
Section 56
Funding. The information derived from WBS performance reporting and pro-
jections can assist in establishing, justifying, and allocating project
funds for the next and future fiscal years. Since the work and cost con-
tent, management priority, and status of each WBS element are defined, a
baseline exists for planning, controlling, and accounting for project
funds.
Cost Estimating. The WBS technique provides a systematic approach to cost
estimating that ensures relevant costs are not omitted. An estimate
derived by WBS elements helps the Departmental project manager to monitor,
coordinate, and control the various project activities that DOE and the
contractors are conducting.
Scheduling. The WBS provides a framework for collecting schedule infor-
mation by WBS elements to establish overall and detailed schedules. The
impact of schedule changes may be readily assessed when a WBS is used
because each element’s start and completion date is integrated with the
other elements’ schedules. This allows expedited review and approval by
the Department of contractor proposed schedule changes.
Performance Measurement. The WBS technique accomplishes the objective of
work definition and provides the basis for performance measurement with a
product orientation. It also facilitates work measurement at levels which
meet specific management needs.
Configuration Management. Configuration management is the task of
managing, controll ing, and reporting the planned and actual design of the
physical characteristics of items throughout their intended life. The WBS
may be extended sufficiently to identify elements selected for this pur-
pose. It is not necessary that the WBS level identified for project
control purposes (e.g., contract reporting) be the same as that used for
configuration management.
DOE 4700.1
3-6-87
II-13
DOE 4700.1
3-6-87
II-14
g. Integrated Logistic Support. Integrated logistic support is a composite
of all support elements necessary to assure the effective and economical
support of a system for its life cycle. These elements include logistical
support activities such as the maintenance plan, facilities, support and
test equipment, spares and repair parts, transportation and handling,
technical data, and training. The WBS logistic elements should provide
the capabilities to support the prime system and its components. The ele-
ments shall reflect the lead time planning needs of the site or test
facility.
h. Test and Evaluation. A WBS may provide specifically for testing systems,
subsystems, and components. A test and evaluation element shall be used
to obtain or validate test performance data. This element shall cover the
detailed planning, conduct, support, data reduction, and reports from the
testing. Since testing requires the participation of organizational ele-
ments responsible for accomplishing development, reliability, and qualifi-
cation tests, appropriate supporting elements need to be included.
i. Systems Engineering. The WBS may be used initially to lay out system
functions in the systems engineering discipline. Following design and the
development of a specification tree, the WBS shall be revised to reflect
the end product. Throughout systems engineering, the WBS shall be updated
to reflect current status of the end product.
DOE 4700.1 Chg 1
6-2-92
II-15
1.
2.
PART C - PROJECT BUDGET PROCESS
Section 57
INTRODUCTION. Providing adequate resources to develop, acquire, and
operate a project is first a design constraint and secondly a
determination of the Department’s planning and budgeting process. The
budget decisions shall be consistent with project baselines decisions
derived requirements contained in the project management system. Figure
II-6 displays the chronology of events leading to appropriation of funds.
PROCEDURES. Integration of decisions concerning project resource
availability in the planning and budgeting process involves the following
procedures:
a. Field Budget Call. A field budget call shall be issued by the Chief
Financial Officer in mid-to-late January incorporating any budget
planning decisions that have been made by the Secretariat. Prior to
including a project in the budget, a conceptual design shall be
completed in accordance with Attachment V-8. Also, any planned
conceptual designs which are expected to exceed $1 million shall be
completed and submitted to Headquarters in accordance with Attachments
V-9 and V-10. Project Data Sheets shall be developed and submitted
for new project efforts and ongoing project efforts which require
additional funding. This documentation, and the conceptual design
report shall be used to validate the project and to defend the project
in the internal review budget.
b. Project Validation. Shortly after the field call is issued, the
Office of Program/Project Management shall issue procedures and a
checklist to be used with the information received in the field budget
submission to conduct project validations. In April and May, the
Office of Program/Project Management, in coordination with the program
offices, shall assess new projects over $5 million and ongoing
projects requesting additional funding. The validation process
evaluates the projects for readiness to proceed into the Department’s
budget process and examines the planning, development, and baseline of
a project to ensure that the funds requested are commensurate with the
project’s anticipated scope and schedule. Normally, the project must
be validated prior to inclusion in the internal review budget.
c. Internal Review, Office of Management and Budget, and Congressional
Budgets. These reviews and budgets are described in detail in DOE
Project documentation shall be updated according to decisions
made in each review. The Conceptual Design Report, Justification for
Mission Need, and Project Data Sheet are the mainline documents used
to defend the project within the Department. Outside DOE (i.e., OMB
and Congress) only the Project Data Sheet is used. Therefore, it is
vital that the document be accurate and up-to-date for each review.
Detailed instructions for preparing the data sheets are contained in
DOE 5100.3.
5100.3.
Vertical line denotes change
II-16 DOE 4700.1
3-6-87
3. FIELD WORK PACKAGE PROPOSAL AND AUTHORIZATION SYSTEM.
a. Specific DOE contractors, primarily management and operations
contractors, process their budget submissions through the use of the
Field Work Package Proposal and Authorization System (WPAS). This
system establishes a formal procedure for budget development,
authorization, and monitoring for those contractor so specified.
b. The major emphasis of WPAS is to group associated R&D tasks and
activities into work packages for the purpose of DOE approval and
control. A work package might include several project related efforts
grouped by objectives and technical discipline. Each work package
shall be measurable in terms of performance and include sufficient
specifications of verifiable events or deliverables to mark project
achievement. Complete coverage of WPAS will be found in DOE 5700.7A.
Section 58
D0E 4700.1 Chg 1
6-2-92
II-17 (and II-18)
April - May
TARGET DATE EVENT
October 1. DOE closes out PY
2. Congress appropriates funds for CY
November-December 1. OMB approves President’s Budget for
BY and provides guidance for BY +1,
2, 3, 4.
January 1. President’s Budget for BY is sent to
Congress
2. Chief Financial Officer issues field
budget call for BY +1
February - May 1. Congress conducts hearings on BY
February - April 1. Field offices complete call and
return to program offices, Chief
Financial Officer, and Office of
Program/Project Management
1. Chief Financial Officer issues
internal review budget call for BY +1
2. Program offices and the Office of
Program/Project Management conduct
project validations for BY +1
July - August 1. Secretary conducts-internal review
for BY +1
August - September 1. Department prepares OMB Budget for BY
+1
LEGEND
PY = Prior Year
CY = Current Year
BY = Budget Year
BY=1,2,3,4 = Outyears
BY+l = Planning
Figure II-6
Chronology of Events to Appropriation of Funds
Vertical line denotes change
DOE 4700.1
3-6-87
II-19
PART D - COST ESTIMATING AND CONTINGENCY ESTIMATING
1. INTRODUCTION.
a. Cost estimating is the process of projecting financial requirements to
accomplish a specified objective. Although the primary tasks involved can
best be described and understood if they are discussed separately and
sequentially, in actual practice they are closely related and often
carried out concurrently. The primary cost estimating tasks are:
(1) Defining and planning the estimating task.
(2) Selecting the estimating structure for preparing cost data.
(3) Collecting, evaluating, and applying the necessary cost and cost
related data.
(4) Applying the proper estimating methods.
(5) Documenting the estimate in enough detail, so that it can be
reviewed, evaluated, and used in the decision making process.
b. When the estimate is completed, uncertainties, limiting assumptions, and
constraints identified by the estimator must be understandable. Changes
in ground rules, schedules, quantities, system description, and opera-
tional concepts can significantly affect cost. Using an estimate without
regard to such system changes would be a misapplication of the estimate.
2. METHODS OF ESTIMATING. There are various methods of preparing cost estimates.
The six most frequently used methods are listed below:
a.
b.
Bottom-Up Technique. Generally, a work statement and set of drawings or
specifications are used to “take off” material quantities required to per-
form each discrete task performed in accomplishing a given operation of
producing an equipment component. From these quantities, direct labor,
equipment, and overhead costs are derived and added thereto.
Specific Analogy Technique. Specific analogies depend upon the known cost
of an item used in prior systems as the basis for the cost of a similar
item in a new system. Adjustments are made to known costs to account for
differences in relative complexities of performance, design, and opera-
tional characteristics.
II-20 DOE 4700.1
3-6-87
c. Parametric Technique. Parametric estimating requires historical data
d.
e.
f.
bases on similar systems or subsystems. Statistical analysis is performed
on the data to find correlations between cost drivers and other system
parameters, such as design or performance parameters. The analysis pro-
duces cost equations or cost estimating relationships which can be used
individually or grouped into more complex models.
Section 59
Cost Review and Update Technique. An estimate is constructed by examining
previous estimates of the same project for internal logic, completeness of
scope assumptions and estimating methodology. The estimates are then
updated to reflect the cost impact of new conditions or estimating
approaches.
Trend Analysis Technique. A contractor efficiency index is derived by
comparing originally projected contract costs against actual costs on work
performed to date. The index is used to adjust the cost estimate of work
not yet completed.
Expert Opinion Technique. May be used when other techniques or data are
not available. Several specialists can be consulted reiteratively until a
consensus cost estimate is established.
3. TYPES OF COST ESTIMATES.
a. There are seven types of cost estimates recognized by DOE in the project
management system. They include:
(1) Planning/feasibility study cost estimate;
(2) Budget/conceptual cost estimate;
(3) Title I design cost estimate;
(4) Title II design cost estimate;
(5) Government cost estimate;
(6) Current working cost estimate; and
(7) Independent cost estimate.
b. Identification of a cost estimate by type connotes a certain level of
accuracy and confidence in it. Further information can be found in DOE
Cost Guide DOE/MA-0063 Vol. 6.
c. Estimates for Small Project Efforts. The preparation of Government esti-
mates in connection with work estimated to cost less than $10,000 is
optional with the field office manager. Where the field office manager
DOE 4700.1
3-6-87
II-21
elects to use a contractor’s estimate, bid, or proposal instead of a
Government estimate, the contractor’s estimate shall be carefully eval-
uated to verify that it is fair and reasonable.
4. BASIS FOR THE COST ESTIMATES.
a. When a cost estimate is prepared for a project, a description of the basis
for the cost estimate shall be made and included in the estimate documen-
tation. The general requirements for each type of cost estimate are as
follows:
(1) Planning/Feasibility Study Estimate. The basis for the cost estimate
shall comprise a description of the project’s purpose, general design
criteria, significant features and components, proposed methods of
accomplishment, proposed construction schedule, research and develop-
ment requirements, and any other pertinent cost experiences.
(2) Budget or Conceptual Design Estimate. These cost estimates shall be
based on all the detailed requirements in the conceptual design
report (CDR) such as the design parameters, applicable codes, speci-
fications and standards. Quality assurance requirements, space
requirements, research and development requirements, methods of per-
formance, operations interfaces, safety requirements, and so forth,
should be considered.
(3) Title I Design Estimates. The basis for these cost estimates shall
include the CDR estimate basis, plus all the refinements developed
during the course of producing the Title I engineering package. This
includes all drawings, outline specifications, data sheets, bills of
material, schedule refinements, definitions of scope, methods of
performance, and changes in codes, standards, and specifications.
(4) Title II Design Estimates. The basis for these cost estimates shall
include all the approved engineering data, methods of performance,
final project definition and parameters, project schedule, and final
exact detailed requirements. The statement of “basis” shall include
a complete list of all engineering data used; (i.e., drawing data
sheets, specifications, bills of material, job instructions,
proposed schedules, and so forth).
Section 60
(5) Government or Engineer’s Estimate. Since this estimate is simply a
refinement of a Title II design estimate, the basis used to make
adjustments or refinements shall be listed and made a part of the
file.
DOE 4700.1
3-6-87
II-22
(6) Current Working Estimates. The basis for these cost estimates shall
carefully define the purpose and scope of the estimate along with a
complete list of all the considerations used to develop the estimate
for actual costs to date and for data used to complete the
projections.
5. CONTINGENCY.
a. Contingency is defined as the sum of funds included within an estimate to
cover materials, labor, conditions and risk situations which are an
intrinsic part of the presently intended scope of work, but are not
specifically allowed for elsewhere in the estimate, due to uncertainty
either as to their existence, nature, likelihood of occurrence, or
magnitude of effect. Such items and situations are likely to occur in
the course of every project, but in uncertain combinations and magnitudes.
Guidance on contingency is issued by the Headquarters Independent Cost
Estimating staff.
b. Several important concepts inherent in this definition should be
emphasized:
(1) Contingency funds are included within the project’s total estimated
cost and shall be considered part of that cost and not “extra.”
(2) There is a statistical probability that such funds will be spent to
complete the work, and methods of determining the magnitude of
contingency shall consider such probability.
(3) Contingency is meant to cover only the scope of work as it is pres-
ently conceived and is not intended to provide for additions to scope
or to require reduction of scope.
c. Contingency is derived from a risk analysis of various aspects of the
project. This analysis concerns cost, schedule, and technical risks as
they apply to the project effort, underscoring the uncertainties that
exist in each of the project elements. The amount of contingency is then
reflected both as a total and on an individual element basis at whatever
level is essential to produce an understandable cost estimate.
d. A contingency analysis shall be performed on all project cost estimates.
In most cases, a short, documented statement accompanying the estimate is
appropriate. The statement should simply indicate what rationale or
thought process the estimator used to reach the conclusions. On simple or
preconceptual design projects, an overall bottom line percentage will suf-
fice. For more complex, better detailed, or more expensive projects,
individual cost elements or work breakdown structure elements should be
evaluated and documented individually.
or physical characteristics and focus on
DOE 4700.1
3-6-87
II-23 (and II-24)
e. The estimate types below are an indication of how well the estimator will
be able to understand the scope of equipment, materials, and labor that
make up the project being estimated.
(1) Planning Estimate. Planning estimates are developed soon after
potential projects are identified and described, and they record and
describe quantitatively the scope of the project and the-assumptions
made for the estimate. These assumptions often force improvements in
the project scope definition and provide a basis for assessing the
magnitude of contingency.
Section 61
(2) Budget or Conceptual Estimates. These estimates are based on concep-
tual designs which define maj
elements of the project that have significant impacts on cost. Such
an estimate shall include all items of the project that the concep-
tual design implies, whether detailed in the conceptual design report
or not, and shall be reviewed in detail by the designer for scope of
work included.
(3) Title I Design Estimate. Title I design is performed in order to fix
or freeze the project scope, to investigate alternative design direc-
tions within the overall project scope, and to establish project
design criteria for final construction design. The resulting design
information defines the project structures and equipment, and out-
lines their basic specifications.
(4) Title II Design Estimate. Title II design produces the detailed
drawings and specifications by which procurement and construction are
accomplished. As such, it provides the basis for a detailed estimate
of the cost of the project.
f. To ensure that contingency is properly managed during execution of the
project, the project manager shall develop a contingency plan, which
shall be an integral part of the project management plan.
DOE 4700.1
3-6-87
II-25
PART E - PROJECT ACQUISITION FOR MAJOR SYSTEM ACQUISITIONS AND MAJOR PROJECTS
1. INTRODUCTION.
a. The acquisition process is of such importance to the project evolution of
a major system acquisition or major project that it is necessary to
generate a basic acquisition strategy, then continuously plan to ensure
that the strategy is properly implemented. Similar planning shall be done
for other projects, except at a less formal level.
b. Although most of the acquisition process is the responsibility of the
cognizant contracting officer and the contract specialist, the project
manager is responsible for two aspects of the acquisition process. The
first is acquisition strategy, which shall be developed in harmony with
the program office and the local acquisition and assistance office. The
second is acquisition planning, which is conversion of the acquisition
strategy to a viable, detailed plan for implementation. In both cases,
the project manager can receive advice, assistance, and recommendations
from a business strategy group.
2. ACQUISITION STRATEGY.
a. Acquisition strategy is a brief description of the contractual basis of
the project contained in the project plan. It reflects the management
concepts that shall be used in directing and controlling the project to
ensure that the system being acquired satisfies the approved mission need.
Although the acquisition strategy encompasses the entire acquisition pro-
cess, the strategy can be less detailed at the time of issuing the solici-
tation to explore competitively, alternative system design concepts.
However, sufficient planning shall be accomplished for succeeding project
phases for those considerations which may have a direct influence on com-
petition and design efforts by contractors. The acquisition strategy
shall evolve through an iterative process and become increasingly defini-
tive in describing the interrelationship of the management, technical,
business, resource, and other aspects of the project.
b. Development of the initial project acquisition strategy shall be completed
as soon as feasible after key decision 1. The project acquisition stra-
tegy is unique for each project and shall be tailored by the project
manager to the circumstances surrounding the project.
Section 62
c. Advice and assistance should be sought from business and technical advi-
sors and experienced managers of other major system acquisitions. The
business strategy group is the formal mechanism for obtaining this advice
and shall be used to develop the acquisition strategy for a project.
II-26 DOE 4700.1
3-6-87
d. The project manager is required to keep all management levels informed of
the strategy and is required to summarize certain aspects of it at the key
decision points. At the earliest feasible date and no later than key
decision 3, the project manager is required to have a comprehensive
strategy for full-scale demonstration.
3. ACQUISITION PLANNING.
a.
b.
c.
d.
The purpose of an advance acquisition or assistance plan (AAAP) is to pro-
vide a description of the contractual means by which the project’s
acquisition strategy shall be carried out. Use of a plan reduces acquisi-
tion lead time and ensures consistency in the preparation of project
contractual execution documents by providing contracting officers and
others involved in project management with specific information about
project business objectives. In addition, the plan and the documentation
which normally accompanies it provide these personnel with an
understanding of overall project goals.
The project plan provides a summary description of a project’s acquisi-
tion strategy, emphasizing overall goals and objectives. The advance
acquisition or assistance plan is that component of the project management
plan which describes how that strategy is to be contractually carried out.
Thus, it serves as a transition and link between the general acquisition
strategy statement included in the project plan and the detailed, transac-
tional level business planning which is performed for each project
contractual action in the project life cycle.
The elements commonly included in an advance acquisition or assistance
plan provide a useful checklist of factors which shall be considered and
addressed in the contractual planning of any large project. These factors
include those which OMB Circular A-109, “Major System Acquisitions,”
states shall be considered when tailoring an acquisition strategy to fit
the circumstances of any large project. The details of an AAAP are
included in Attachment II-7. One of the most important of these items in
project planning is consideration of the acquisition process, including
employment of proper lead times for contract actions.
Figure II-7 illustrates the chronological sequence of contractual planning
activities in relation to the preparation of project documents (project
plan and project management plan) containing advance acquisition or
assistance planning information is contained. A description of these
contractual planning activities follows:
(1) Advance acquisition planning is the activity in which program offices
develop an aggregate, summary level plan of the contractual actions
that they expect to initiate during a specified time in the future in
relation to their budget authority.
DOE 4700.1
3-6-87
II-27
e.
f.
g.
h.
i.
(2) The acquisition or assistance planning accomplished by program offi-
ces in the preparation of the acquisition or financial assistance
request package provides the contracting officer with the essential
items of information, statement of work and delivery schedule needed
for inclusion in the solicitation and resulting award documents.
Section 63
(3) The acquisition planning and scheduling called for in DOE/MA-0154,
“Acquisition Regulations Handbook - Source Evaluation Board,” is a
master blueprint of the source evaluation board’s understanding of
the requirement, how the source evaluation board intends to conduct
proposal solicitation and evaluation, and when each major event in
the source evaluation board process is scheduled to take place.
An advance acquisition or assistance plan is appended to the project mana-
gement plan for each major system acquisition and major project. The use
of an AAAP is encouraged for other projects.
Acquisition or financial assistance planning shall be initiated at the
earliest practicable time in the project life cycle. This is normally at
the time the initial project plan is written.
The contractual execution planning for a project which results in an AAAP
is a shared responsibility of the project manager and the contracting
officer. Although the project manager has the overall responsibility for
project implementation, the contracting officer is responsible for deter-
mining the appropriate contractual means for accomplishing project
objectives.
The AAAP is normally completed and forwarded in time for it to be received
by the cognizant contracting office and other organizations involved in
project execution at least 6 months prior to the time that the first
acquisition request form for a contractual action is scheduled for
release.
Changes in the AAAP. Changes my occur in a project which have a signifi-
cant effect on the previously developed AAAP. For Instance, a large
budget adjustment can require revisions; additional information just
developed may need to be included; or problems may be encountered in
implementing the plan. In such cases, any changes which need to be made
to the AAAP are developed, approved, and distributed in the manner
described in Attachment II-7.
4. BUSINESS STRATEGY GROUP.
a. The business strategy group (BSG) is intended to assist the project
manager by providing advice and recommendations relating to sound contrac-
tual and business practices. The BSG is convened by the field manager of
Typical Chronological Sequence
Figure II-7
of Project Acquisition or Assistance Planning
DOE 4700.1 II-29 (and II-30)
3-6-87
b.
the acquisition and assistance office at the request of the program or
project manager. Each BSG shall be staffed by different personnel,
depending upon the nature, complexity, and cost of the project.
In preparing its advice and recommendations, the BSG considers the project
management plan, various business approaches, special contractual aspects
of the project, the state of technology development, and similar
questions. BSG advisory positions are presented to the program or project
manager for consideration in acquisition strategy and plan development.
BSG responsibilities are detailed in Attachment II-7.
DOE 4700.1 II-31
3-6-87
PART F - ENVIRONMENTAL PLANNING AND REVIEW
1. INTRODUCTION. Environmental planning and review form an integral part of the
project management system. The Environmental and Safety Plan and the Environ-
mental Research Plan are used by the project manager in preparing the overall
environmental and safety component of project plans and project management
plans. Assistance in compliance with environmental and safety requirements is
provided by the Assistant Secretary for Environment, Safety, and Health and
the General Counsel.
2. ENVIRONMENTAL STRATEGY.
Section 64
a. The Assistant Secretary for Environment, Safety, and Health, in consulta-
tion with the General Counsel provides assistance and judgments concerning
environmental factors that should be considered in program planning and in
the acquisition of projects.
b. General environmental compliance planning principles are discussed in the
Department of Energy Environmental Compliance Guide. These principles
address the problem of complying with a large number of different environ-
mental review requirements through a comprehensive, integrated environmen-
tal compliance planning strategy, termed “phased compliance.” This
strategy is characterized by:
(1) A comprehensive review of all applicable Federal , State, and local
policies, programs, and regulations and identification of all
requirements;
(2) Integration of requirements into an efficient time schedule,
including identification of critical path(s);
(3) Coordination of various environmental reviews including, in par-
ticular, early reviews under the National Environmental Policy Act,
with the appropriate phases of project development;
(4) Utilization of common environmental data bases; and
(5) Analysis of any environmental constraints and development of suitable
mitigation measures to alleviate these constraints.
c. Within the acquisition process phases, the scope of environmental concerns
broadens to include not only research and status reports but also environ-
mental, health, and safety including socioeconomic assessments of specific
projects and operations which are proposed.
II-32 DOE 4700.1
3-6-87
3. ENVIRONMENTAL ASSESSMENT, ENVIRONMENTAL IMPACT STATEMENTS, AND SAFETY,
ANALYSIS REVIEW.
a.
b.
Environmental Planning. Environmental planning and review mechanisms are
of two types: those that are generic to an energy technology, and those
that are specific to each project. Program Environmental Impact State-
ments (EIS’s), or Environmental Assessments (EA’s), are of the first type.
The second type consists of the Site or Process Specific EIS’s or EA’s,
and the Safety Analysis Review System (SARS). These represent vertical
cuts throughout each acquisition phase in the process (see Figure II-8).
which are discussed in DOE 5440.1C,
Environmental Documents. The principle environmental documents and their
general interaction with the project management system for technology
development are illustrated in Figure II-8. The figure provides a repre-
sentation of how environmental activities and their documentation work to
support the removal of barriers and the identification of uncertainties
that must be considered within the technology before proceeding to produc-
tion or operation. The EA and EIS, if required, are generally prepared
first for a technology development program, and then on a site- or process-
specific basis, early enough to allow major procurements and construction
activities to begin with reduced uncertainties and minimum time delay. In
a similar fashion, the safety analysis examines the health and occupa-
tional hazards of proposed major operations under the cognizance of DOE to
assure that barriers and impacts are resolved without undue time delays.
Subsequent updates assure continued reviews of operational safety.
(1) Environmental Assessment and Environmental Impact Statement, both of
IMPLE MENTATION OF THE NATIONAL
ENVIRONMENTAL POLICY ACT, of 4-9-85, and Department of Energy Compli-
ance with the National Environmental Policy Act (NEPA) (45 FR 20694),
of 3-28-80, and as amended by 47 FR 7976, of 2-23-82.
Section 65
(a) The National Environmental Policy Act of 1969 requires that
agencies prepare environmental impact statements “on proposals
for legislation and other major Federal actions significantly
affecting the quality of the human environment.” For proposals
where it is unclear whether an EIS is required, an EA is to be
prepared. An EA is a statement which provides the information
upon which to base a determination of the necessity for an EIS
or a finding of no significant impact.
(b) Assessments and impact statements are prepared by program offi-
ces according to Departmental procedures and are reviewed and
approved by the Assistant Secretary for Environment, Safety, and
Health, after consultation with General Counsel. Generally
EIS’s and EA’s should be completed prior to initiation of de-
tailed design work. EIS’s required for DOE policy and legis-
lative initiatives should be prepared as required.
Project Specific Safety Analysis
Figure II-8
Principal Environmental Requirements in the Project Management System
II-34 DOE 4700.1
3-6-87
(2) Safety Analysis. This document is prepared by project managers
according to DOE 5481.1A, SAFETY ANALYSIS AND REVIEW SYSTEM, of
8-13-81, for operations early in the design phase of a proposed fa-
cility that DOE intends to use for production activities or to place
in operation for other purposes.
(a) DOE 5481.1A defines operations as “those activities funded by DOE
for which the Department has assumed responsibility for environ-
mental protection, safety, and health protection (ES&H). It is
a general term intended to encompass individual operations or
effort in the aggregate rather than separately.” Safety anal-
yses identify hazards, assess risks and means for their elimina-
tion or control, and document the approval for various stages of
facility design, construction, and operation. DOE 5481.1A
applies to all DOE operations except nuclear weapons production
and activities having only hazards of a type and magnitude
routinely encountered and accepted by the public. The safety
analysis should facilitate early identification of hazards and
their control or elimination. For complex or expensive opera-
tions a preliminary safety analysis shall be prepared and
approved before construction begins. A final safety analysis
shall be prepared and approved before facility or process opera-
tions commence.
(b) The line program organization is responsible for preparing
safety analyses, obtaining an independent review of each safety
analysis, and authorizing the construction operation and sub-
sequent significant modification, including decommissioning, of
each DOE operation. This includes developing safety analysis
and review system implementation plans unique to their specific
needs. The independent review includes a document evaluation of
the adequacy of the preventive or mitigative design features and
the administrative controls provided to limit the probability of
an adverse occurrence or the severity of a hazard.
(c) The Assistant Secretary for Environment, Safety, and Health is
responsible for providing independent assurance that line
program organization responsibilities are fulfilled and as a
part of this responsibility, conducts independent appraisals of
line program safety analysis and review system activities.
4. ENVIRONMENTAL PLANNING.
a. Proper environmental planning is critical to project management. For a
given project effort, a number of environmental requirements may be appli-
cable, and compliance planning may involve complex tradeoffs of time,
Section 66
DOE 4700.1
3-6-87
II-35
risk, costs, and quality. Failure to properly comply with environmental
regulations and statutes invites lawsuits, delays, and loss of resources.
Environmental issues can create severe breaches of baselines.
b. The environmental, safety, and health plan defined as Annex III to the
project management plan contains the information on critical environmental
and safety statutory, regulatory, and directive requirements necessary to
develop the environmental and safety milestones and schedules required in
project plans and project management plans. This information can be
derived by applying the phasing principles outlined in Part I of the DOE
Environmental Compliance Guide (DOE/EV-0132) and using appropriate infor-
mation from ES&H implementation plans prepared in accordance with
DOE 5480.1A, EIS implementation plans prepared in accordance with
DOE 5440.1C, safety analysis reports prepared in accordance with
DOE 5481.1A, plus other ES&H planning efforts as necessary. Requirements
for environmental planning and review pertain primarily to the prepara-
tion, review, and decisions on program plans and project management plans.
c. The following general principles are involved in developing efficient
environmental compliance planning that does not sacrifice the quality of
review of major issues.
(1) Integrate the requirements of National Environmental Policy Act and
other environmental review procedures with the appropriate phase of
project development. The development of environmental analyses,
whether as part of an EIS or part of a permit application, depends on
the availability of an appropriate level of engineering detail.
Therefore, the timing of such analyses is primarily dictated by the
project development schedule. EIS reviews can generally be commenced
with preliminary design information and performed in coordination
with that phase. Permit applications generally require a greater
level of detailed design information; therefore, “permitting” reviews
are generally performed later, in coordination with the detailed
design phase.
(2) An EIS serves as a vehicle for presentation and review of the
environmental issues associated with the project. Compliance with
the NEPA process identifies major issues, allows public participa-
tion, and requires consideration of alternatives and mitigating
measures. Initiation of substantial detailed design work prior to
completion of the EIS process incurs a program risk in: (a) preju-
dicing the NEPA review with attendant litigation risk and criticism;
and (b) prematurely committing financial and other resources to the
project.
(3) Generally, construction cannot commence before successful completion
of preconstruction permitting environmental reviews.
II-36 DOE 4700.1
3-6-87
(4) In light of the opportunities for phasing environmental reviews in
coordination with project schedules discussed above, the proposal
that limits overall environmental review time should be carefully
scrutinized since: (a) it may not actually accelerate the project
schedule; and (b) it may force scheduling that incurs substantial
project risk. On the other hand, initiatives to consolidate or coor-
dinate environmental reviews may be quite useful and productive.
d. These planning principles lead to the development of a proposed environ-
mental plan termed “Phased Compliance” (see Figure II-9). Phased
Compliance generally is characterized by:
(1) Coordination of the EIS and consultative environmental reviews with
the preliminary design phase;
Section 67
(2) Completion of the EIS process prior to commencement of detailed
design;
(3) Submission of permit applications following publication of the EIS
and Record of Decision; and
(4) Submission of permit applications and coordination of permitting
reviews with the detailed design phase.
e. Delayed compliance will normally result when inadequate attention is given
to environmental requirements early in the planning process. A ripple
effect is generated when preparation of the EIS is delayed. In many
instances the permitting authority will not commence review of permit
applications until a draft EIS, as a minimum, has been circulated. As a
result, the permitting process is no longer controlled by the availability
of design information, but instead by the availability of the draft EIS.
This delays the start of construction and makes the EIS and other environ-
mental review processes critical path items. Any delays in these pro-
cesses will further delay the project.
f. The phased environmental compliance plan has a number of major benefits;
in view of these benefits the phased compliance plan is strongly recom-
mended as the approach for planning environmental compliance.
(1) It avoids or minimizes environmentally related delays to the start of
construction;
(2) It avoids or minimizes premature commitment of project resources and
allows for progressive decisionmaking;
(3) It avoids prejudicing the NEPA review thereby reducing litigation
risk and criticism; and
Figure II-9
Project Environmental Phased Compliance
II-38 DOE 4700.1 Chg 1
6-2-92
(4) It facilitates subsequent permitting processes through its early
EIS preparation effort.
g. Cost and Schedule Baselines Considerations for Environmental Planning.
Chapter III, Part A, Baseline Management and Control, provides
requirements and guidance for the establishment of project baselines
and change control of the baselines. During the planning process, the
project cost and schedule baselines should ensure the provision of the
necessary analysis and preparation of documentation required for
Federal, state, and local environmental compliance.
The following National Environmental Policy Act (NEPA) control
milestones shall be included, as a minimum, as Level 1 Control
Milestones in the project schedule baseline unless specifically
excluded at KD No. l:
Issue Categorical Exclusion (CX);
Submit Environmental Assessment (EA);
Issue Finding of No Significant Impact (FONSI);
Submit Draft Environmental Impact Statement (EIS);
Submit Final EIS; and,
Issue Record of Decision (ROD).
The nature and scope of the proposed program or project will determine
the appropriate level of NEPA review.
An alternative to prescribing these milestones is to state the
criteria for assignment of milestones in the project plan for a given
project.
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92 II-39
PART G - CONSTRUCTION PLANNING
1. INTRODUCTION.
a. Construction planning is important to the critical decisions that
affect the design and cost of a project. It is during this phase that
the size, function, technical performance requirements, and location
of the proposed facility are determined and the budget is set. Once
the preliminary decisions are made on these matters, the nature and
cost of the facility are virtually predetermined. (Figure II-10
reflects construction planning).
Section 68
b. The planning phase commences at the initial identification of a
construction project and continues until receipt of the detailed
design and/or construction funds at the level responsible for project
management. Planning for construction effort within DOE occurs
concurrently with the budget process. Since the budget process is
relatively rigid with regard to time, the planning phase must be
structured to provide the necessary project information for budgeting
purposes at the required time.
c. Chapter V prescribes the minimum planning elements and procedures that
field organizations must accomplish to assure construction objectives
are met. The field office manager is responsible for establishing,
where necessary, internal procedures to implement the minimum
requirements contained here.
2. CATEGORIES OF CONSTRUCTION EFFORTS. The following summarizes information
on the determination and selection of construction effort categories which
require certain management control and reporting procedures:
a. Plant and Capital Equipment Budgeted Projects. These are construction
efforts that consist of the acquisition, modification, or retirement
of land, land rights, buildings, structures, major process equipment,
utilities, roads, and other facilities, or any combination thereof,
when a scope of work is involved which may be capitalized. Plant and
capital equipment projects may be line item or contingency projects.
(1)
(2)
Line Item Projects are projects which are specifically reviewed
and approved by Congress. They may either be plant and capital
equipment or operating expenses budgeted. Generally, projects
with a total project cost greater than $1.2 million are
categorized as line item projects.
Contingency Projects are plant and capital equipment-budgeted
line item projects for which different procedures are applied
during the planning and budgeting process. Management of the
design and construction phases is the same as for line item
projects; however, the consequence of planning actions varies
from line item projects.
Vertical line denotes change
Figure II-10
Construction Planning
DOE 4700.1 Chg 1 II-41 (and II-42)
6-2-92
b.
(a) A collection of sub-projects in support of a certain program
at various locations is a contingency project. This type
differs from line item projects in that, as submitted to
Congress, it is a collection of projects, each of which
could be a line item. It is formulated in this manner
because the work required cannot be deferred or sufficiently
defined and estimated at the time the budget request is
submitted. Estimates for the work are generally based on
past experience rather than on specific requirements for the
fiscal year involved.
(b)
(c)
A project providing for a variety of additions,
modifications, improvements, and auxiliary experimental
facilities at specific major programmatic facilities is a
contingency project. The construction project data sheets
submitted in the budget to Congress for such projects set
forth the tentative plans for construction work to be
performed during the fiscal year, although it is recognized
that details of plans are not firm and that circumstances
may necessitate revisions to the plans. Prior to
accomplishment of the work, detailed scope and costs must be
prepared.
Section 69
General plant projects are miscellaneous projects that cost
$1.2 million or less each. A general plant project line
item is submitted to Congress for each outlay program or
specific element of a program requiring one or more of the
job requirements. The individual jobs are not specifically
approved by Congress; however, the jobs anticipated to be
accomplished during the fiscal year are required to be
listed in the construction project data street for the
general plant project line item. Managing field offices may
approve additions and deletions for general plant projects.
Field office manager shall inform program offices of changes
made.
Operating Expense Budgeted Project are projects funded by an
operating expense appropriation, and meet the requirements set forth
in DOE 2200.4, ACCOUNTING OVERVIEW.
c. Capital Equipment Budqeted Projects consist of the acquisition and
installation of capital equipment funded from the plant and capital
equipment not related to construction position of the budget, when the
installation costs exceed $250,000.
Vertical line denotes change
DOE 4700.1 II-43
3-6-87
PART H - PROJECT TRANSITION
1. INTRODUCTION. Projects are planned and executed with an eye to their being
completed. Part of the planning process is to develop cost, schedule, and
technical parameters which define project completion. This phase of the work
must be as carefully planned and executed as any other. The project manager is
responsible for a clear and viable plan to accomplish project transition.
2. SCOPE OF PROJECT TRANSITION.
a. Transitioning a facility from project status to operating status requires
that technical and procedural matters involved be considered during the
planning state. The project plan and project management plan both must
reflect the point at which the project is complete. The project charter
shall indicate at what point the project manager’s responsibility ceases
and an operating contractor takes over. Specifications must clearly
delineate the end product involved, not only for purposes of project exe-
cution, but to indicate the specific parameters of project completion.
b. Besides the dimensions of the project as defined by the project plans,
charter, and specifications, to be a transition plan must be formulated
during project execution. This plan should be developed in conjunction
with the contractor who will operate the facility, in order that there be
complete understanding by both DOE and the contractor as to specific
details of the transition and individual responsibilities. The plan
should contain specifics on the following areas:
(1) DOE and contractor transition responsibilities;
(2) The measurements by which transition is considered appropriate;
(3) A schedule of the activities involved in transition;
(4) DOE procedures for turning over operation of the facility to the
contractor;
(5) Operating contractor procedures for accepting the facility for opera-
tion;
(6) An indication of any permit or licensing obligations involved in
operation which must be satisfied;
(7) Operational testing and certification of technical performance capa-
bility; and
(8) Any other details essential to the transition process.
II-44 DOE 4700.1
3-6-87
3. PROJECT OFFICE TRANSITION.
a. The end of the project means the end of the freed for the staff. The proj-
ect manager needs to be sensitive to this situation and deal with it
before the staff turns its attention fully to post-project speculation.
Section 70
b. The project manager should develop a project office transition plan
whereby project staff members are relieved of the concern for future
assignments. There should be a concerted effort made to assuage these
concerns through discussions with the individuals about their desires;
getting the field organization management involved in the problem; and
assigning new job assignments as early as possible.
c. Another important element of project office transition is that of
completing all the necessary steps for closeout. This procedure includes
completing all contractual relationships, closing contracts for file,
closing out financial records and documents, obtaining necessary
approvals, licenses, and permits, completing the safety analysis report,
establishing operating procedures, plus any other activities peculiar to
the project. A project closeout checklist might be prepared by the
project manager to ensure that all closeout activities are completed.
DOE 4700.1 Chg 1 Attachment II-1
6-2-92 Page II-45
GUIDANCE FOR PREPARING A JUSTIFICATION OF MISSION NEED
1.
2.
3.
The Justification of Mission Need is the document required to obtain
Department approval for expenditure of Department funds for projects
anticipated for designation as major system acquisitions or major
projects, which reflect the determination and identification of DOE
mission need(s), based on the reconciliation of continuing analyses of
current and forecasted capabilities, technological opportunities, overall
priorities, and initial resource expenditure involved with achieving DOE’s
mission. The Program Manager is responsible for Preparation of the
Justification of Mission Need. The Justification of Mission Need should
be a brief (three to six page) document expressing the project need in
terms of the following elements:
a. Program mission/goal;
b. Project objectives;
c. Organization; and
d. Approvals.
Since the mission need is independent of any particular system or
technological solution, the Justification for Mission Need shall not
express the need in terms of equipment or specifications, although
feasibility at this time via availability is relevant.
The Justification of Mission Need shall emphasize the reasons why project
conceptual design funding should be approved by addressing the mission
needs, the purpose and priority of the project in supporting the needs,
the significance of meeting the needs, and shall include the following
information:
a. Program Mission/Goal.
(1)
(2)
(3)
(4)
(5)
Provide the mission of the program, a description of program
goals to be accomplished and relationship to the Secretary’s
mission area assignments.
State how the project will support program goals and explicitly
state why it is needed.
How is the project related to program strategy; how does
relate to other program elements and projects?
Why is it the appropriate action and what would be the
programmatic impact of not doing it at all?
What are the most appropriate alternatives, if any?
it
Vertical line denotes change
Attachment II-1
DOE 4700.1 Chg 1Page II-46 6-2-92
(6) Why are these options being considered?
(7) Why is this the best option?
(8) Describe the appropriateness of the project at this time in view
of the state of current technology.
b. Projec t Objectives.
(1) Technical Objectives:
(a) As specifically as possible, describe the technical
objectives.
(b) Cite the basis for the feasibility of achieving the
technical objectives (e.g., studies, research and
development, state of related technologies).
Section 71
(c) Discuss technical objectives in relation to similar ongoing
or planned activities, both international and domestic.
(d) Describe the impact on the program of not meeting the
technical objectives.
(2) Cost Objectives:
(a) Provide estimate of costs related to developing the
Conceptual Design Report (CDR) and related documentation
required for Key Decision 1.
(b) Provide discussion and justification of how the conceptual
design funds will be distributed (profile) along with the
major cost items.
(c) State when cost estimates resulting from conceptual design
will be available.
(3) Schedule Objectives:
(a) Provide a statement of preliminary project schedule to
include at least: (1) start conceptual design; (2) complete
CDR; and (3) Key Decision 1, Approval of New Start.
(b) Describe the impact, if any, on the program of not meeting
the schedule dates.
Vertical line denotes change
DOE 4700.1 Chg 1 Attachment II-1
6-2-92 Page II-47
4.
5.
c. Organization. Provide a preliminary plan for organizational
involvement and relationships, including, as appropriate, field
organizations, laboratories, universities, industrial concerns, DOE
Headquarters, or other agencies, foreign or domestic for the period
between Key Decision O to Key Decision 1.
d. Risk Asse ssment.
(1) What is the probability of success?
(2) Describe the basis for risk assessment.
e. Approvals. The Justification of Mission Need shall be approved by the
Acquisition Executive for MSA’s and the cognizant Program Secretarial
Officer for major projects. Concurrences of other program and staff
officials, as appropriate, are required prior to these signatures.
Include a specific statement of what the Acquisition Executive or the
Program Secretarial Officer are supposed to approve (e.g., “This
project as described in this Justification for Mission Need is
recommended for inclusion in the FY94 budget submission to OMB”).
As mentioned, the Justification of Mission Need is required only for major
system acquisitions and major projects. For projects other than MSA’s and
major projects, the project data sheet should be sufficient to serve as a
justification if it contains the basic information required above,
tailored by project size and complexity. There may be instances,
particularly for projects approaching $50 million, when the Assistant
Secretary may require a justification as part of the project
documentation.
APPROVAL. The signature page for a Justification of Mission Need shall
include only the following:
a. SUBMITTED BY: Program Manager
b. A paragraph that approves initiation of the major system acquisition
project and directs development of a project plan for signature
approval of the Program Secretarial Officer and the Acquisition
Executive (Deputy or Under Secretary); and
c. For major projects, the Program Secretarial Officer shall be the final
approving official, except in cases where the Deputy or Under
Secretary reserves approval authority.
6. REVIEW AND CONCURRENCE OF JUSTIFICATION OF MISSION NEED.
a. Major System Acquisition. The Justification of Mission Need as
approved by the acquisition proponent shall be transmitted to the
Acquisition Executive via Action Memorandum. The concurrence chain on
the Action Memorandum shall include concurrences of:
Vertical line denotes change
Attachment II-1 DOE 4700.1 Chg 1
Page II-48 6-2-92
(1) Assistant Secretary for Domestic and International Energy Policy;
(2) Director of Program/Project Management and Control; and
Section 72
(3) Director of Procurement, Assistance and Program Management.
b. Major Projects. DOE major project Justification of Mission Need are
to be approved by the Program Secretarial Officer and transmitted to
the Deputy or Under Secretary, as appropriate via Information
Memorandum, with a copy to the Director of Program/Project Management
and Control. The acquisition proponent shall assure that the
Assistant Secretary for Environment, Safety, and Health and the
Associate Director of Program/Project Management and Control and
Director of Procurement, Assistance and Program Management have
concurred.
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
Attachment II-2
Page II-49
GUIDANCE FOR PREPARING A PROJECT PLAN
1.
2.
The project plan describes the project and establishes project baselines
against which overall progress of the project and the effectiveness of its
management shall be measured. The plan guides project execution and
clearly sets forth the essential elements of the project. At key decision
points for MSA’s and major projects, current project plans become a key
part of the Acquisition Executive decision-making, the project’s mission
need is reexamined, and alternatives for executing the next phase are
presented to the Acquisition Executive. The project plan shall be
maintained current to incorporate the Acquisition Executive and other
management decisions to accurately serve as the project baseline document.
The preparation of the project plan shall be the responsibility of the
Program Manager working in cooperation with the Project Manager.
The project plan will be a definitive document, no more than 25 pages in
length (excluding attachments). Specific subject allocations of these
pages cannot be made since the project plan is a document that becomes
more definitive as the project moves through advanced and engineering
development. In the early state of a project, the project plan is focused
more on objectives, technical plan, management approach, acquisition
strategy, and documenting initial costs schedule, and scope baselines.
Once the project is well underway, adjustments are made, as appropriate,
to the technical plan, management approach, and acquisition strategy;
normally these will not change during the remainder of the project. The
project manager shall define the cost and schedule and shall focus on
technical objectives, performance, and the test planning for the project.
The project plan shall be tailored to the needs of the particular project
considering the phase of its acquisition strategy, size, complexity,
sensitivity, and particular project characteristics. Redundant
specification or expression of data shall be avoided or minimized to the
extent practical. The project plan format and the information it shall
contain are described below:
a.
b.
Mission Need and Objectives. This section provides a summary of the
approved mission need with regard to the required capability to be
achieved and outlines technical, resource, and schedule objectives and
projections.
The data and information included must provide reaffirmation of the
Justification of Mission Need that was initially approved at Key
Decision O.
Technical Plan. This section should describe what is going to be done
and how it shall be accomplished.
(1) Document the technical objectives in quantitative terms, briefly
describing what is to be developed or constructed. This
description shall refer to the location (when construction is
involved) and the major systems or elements of the project or
facility.
Section 73
Vertical line denotes change
Attachment II-2 DOE 4700.1 Chg 1
Page II-50 6-2-92
(2) Describe the status of technology or the “technology readiness”
for implementing the project. Include in this discussion a
description of any ongoing or planned supporting development work
on which the project is dependent and which, therefore, is part
of the project.
(3) Either integrate or follow the above discussion with a
description of the specific scientific, technological, or
engineering approaches or processes to be used in meeting the
performance objectives. For projects early in design and
development, emphasis shall be placed on alternative concepts,
design, or technical approaches being considered or pursued. For
more mature projects, the development paths, critical subsystems,
and test and verification procedures shall be described.
(4) For projects pursuing alternative design or technical approaches,
briefly describe each alternative and the basis for selection of
an alternative.
(5) Describe each phase of the project including the work to be
accomplished and projects developed. In this discussion,
indicate the major project events, technical activities, and
decision points and authority that occur during each phase of the
acquisition process. This is considered a key element of the
technical plan.
(6) A project work breakdown structure chart is mandatory and shall
be summarized in this section and included as an attachment. The
work breakdown structure shall be product oriented and present
the products or work elements of the project down to level three.
This breakdown of the project shall conform to the manner in
which the work shall be performed (including environmental work)
and in which project cost and schedule are controlled and
reported.
(7) For complex projects comprised of several major elements, include
a flow of logic diagram that illustrates project element
sequencing and interdependencies. The intent is to show
significant interrelationships among major elements of the
project.
c. Risk Assessment. This section is an assessment of project risks that
identifies critical systems, subsystems, and other factors which
require focused work and resolution. Types of risks that shall be
addressed are technical, schedule, cost, others such as safeguards and
security at all phases, loan guarantee, environmental, health, safety,
regulator, utility, and institutional impediments that are not covered
in other sections. In addressing each risk, the following information
is required:
Vertical line denotes change
6-2-92
D0E 4700.1 Chg 1 Attachment II-2
Page II-51
(1) The assessed level of risk (high, moderate, low);
(2) The basis for this assessment (reliability, availability, and
maintainability analyses; study results; proven or unproven
technology; well established or unproven construction
procedures);
(3) The critical project elements contributing to the risk;
(4) Implications of the risk;
(5) Activities or alternatives planned to minimize the risk; and
(6) The stage of the project in which the risk exists (design,
procurement and construction, or operations). For projects early
in the advanced development phase of the acquisition process, a
full assessment of these risks may not as yet exist. In this
case, the discussion shall identify any risks that are evident
and indicate when (e.g., during Title I design) the risk
assessment for the project shall be developed.
Section 74
d. Management Approach. This section addresses the organization
responsibilities, decision delegations, other management arrangements,
and management control systems under which the project shall be
carried out. Emphasis shall be placed on the extent of the project
manager’s responsibility for total project funds and work effort.
Accordingly, when field office matrix support is used by the project
manager to review or monitor some aspects of project funded work, that
management relationship shall be explained.
Vertical line denotes change
Attachment II-2
Page II-52
DOE 4700.1 Chg 1
6-2-92
(1) Identify the Headquarters program office and division to which
the project is assigned and the field organization responsible
for project management.
(2) Identify the project manager by name in the text.
(3) Depict all participating organizations, (DOE, major contractors,
and others) and their responsibilities on a project organization
chart which shall be included as an attachment. Include names of
the Headquarters program manager and the designated project
manager on the chart.
(4) Where there are industry or utility partners, identify the
partners and describe the management relationships with them and
their role in management and implementation of the project. Also
refer to existing agreements (cost sharing and other) with them
or the status of agreements still to be negotiated.
(5) In discussing the items above, clearly identify decision
delegations and the responsibility of each of the key individuals
and support organizations.
(6) Identity and discuss project transition responsibilities and
areas.
(7) For demonstration projects, indicate how disposition of the plant
shall be determined at the conclusion of the demonstration phase
of the acquisition process or termination at the convenience of
the Government.
(8) If there will be site cleanup problems after conclusion of
project operations, indicate how these needs shall be met.
(9) Describe the integrated program management control system that
will be used to control this project including references to
specific program management documents and systems. Describe the
processes by which the project manager will control costs,
schedules, and technical performance including a Responsibility
Assignment Matrix (RAM) that illustrates responsibilities
(organization breakdown structure).
e. Acquisition Strategy. The acquisition strategy is the underlying
conceptual basis for management of a project and reflects the
interrelationship of its mission, technical, business, and management
objectives. A business strategy group should be used as an advisor to
develop the acquisition strategy. This section shall include a
description of the means by which the management objectives,
prescribed for major system acquisitions and major projects, and the
planning considerations shall be implemented
Vertical line denotes change
DOE 4700.1
3-6-87
Attachment II-2
Page II-53
while assuring consistency with program and project objectives. Key
elements involved in an acquisition strategy are: the use of multi-
phase contracts; sustaining competition; degree of delegation by the
Government of coordination, integration, and management responsibility
to a contractor; and reliance on private industry. These elements and
the others discussed in this paragraph shall be fully understood and
appropriately utilized in the development of an acquisition strategy.
This section shall briefly summarize the acquisition strategy
developed for the project and describe the approach that shall be used
for acquiring the major items of hardware, software, and management
support described in the technical plan section.
Section 75
(1) Begin with a brief summary of the acquisition strategy thus far
developed for the project. This summary shall describe the
management concepts that shall be used in directing and
controlling the project to assure that the systems being acquired
will satisfy the approved mission needs.
(2) Include in this summary a description of how the management
concepts relate to technical, business, resource, and other
aspects of the project.
(3) Indicate whether or not a project manager, construction manager,
or other integrating contractor, including Government management
and operating contractors, will be used in the project and the
extent to which such contractor will be responsible for
implementing the project acquisition strategy.
(4) For projects to be funded jointly by industry or utility
partners, describe the cost sharing or cooperative agreement that
exists. Where the agreement is yet to be negotiated, describe
nonproprietary and/or nonsensitive aspects of the cost sharing
plan and indicate when the agreement is scheduled to be
negotiated. Describe the treatment of future changes in project
scope of an early termination.
(5) In cases where major contracts have already been awarded,
identify each contractor, work being performed, award date,
current contract amount, contract number, and contract type. In
cases where major contracts are yet to be awarded, indicate the
work to be performed, planned award date, estimated cost,
contract type, and approving official to the extent known. When
there are several prime contractors, this information shall be
summarized in a table appended to the plan rather than described
in narrative form.
(6) Indicate the basis and applicable controls for award of
subcontract work and summarize the approach to be employed for
subcontract management.
Attachment II-2 DOE 4700.1 Chg 1
Page II-54 6-2-92
f. Project Sc hedule. This section should be a one-paragraph statement that
refers to the project schedule as an attachment. It should also include
any qualifying statements. The schedule attachment must be consistent
with the project work breakdown structure (WBS) and contain, as a minimum,
the schedule for project WBS elements down to and including level 2,
including the following:
(1)
(2)
(3)
(4)
(5)
Key project activities, by applicable acquisition phase, for the
life of the project;
Key phases of the project described in the technical plan
section;
Identification of all Acquisition Executive key decisions and
appropriate Level O milestones, Program Secretarial Officer’s
decisions and appropriate Level l milestones, and other approval
points as appropriate;
Identification of major environmental and/or safety
documentation, reporting or permit requirements and milestones
which may impact the projects critical path; and
The initial schedule can be in bar chart format. The schedule
for Key Decision 2 and subsequent decisions shall include a C&M
critical path method diagram(s) that will depict the project’s
critical path.
g. Resources Plan. This section refers to the resources plan as an
attachment, includes any qualifying statements, and states the total
project cost. This section also indicates the projected total
manpower level of the project office management staff (DOE, contractor
and other personnel). Life cycle cost considerations for all
resources impacting total project cost, such as energy efficient new
building design features, selection of materials and systems for
maintainability, and selection of the most cost effective utility
services to meet program requirements, etc., shall be included in this
section. These cost considerations shall address all costs for
construction and operation of the project, including the utilities
requirements (e.g., electric, water, steam, gas) and maintenance
requirements, as appropriate. The resource chart shall be consistent
with the WBS and include:
Section 76
(1) Actual funding (budget authority and budget outlay) for prior
years, as recorded in the Financial Information System, and the
current year and estimated funding for budget year and annually
over the life of the project for each WBS level 2 project element
and the total project.
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
Attachment II-2
Page II-55
(2) Separate identification of operating expense and plant and
capital equipment budgeting. Operating expenses for utilities,
maintenance, and janitorial services shall each be separately
identified.
(3) The above cost data must correlate with the costs stated in the
cost baselines of the controlled items section of the plan.
h. Controlled Items/Baselines. The controlled baselines shall be cost,
schedule, and scope (technical).
The baselines shall be presented in a format similar to that depicted
in Figure III-15 which defines both the baselines and the approval
authority for the baselines.
Thresholds for change control authority of the baselines shall be
presented in a format similar to that depicted in Figure III-16 which
defines the thresholds and approval authority for changes to the
baselines identified in Figure III-15.
These items may be included as an attachment.
i. Project Charter. The project charter can be prepared and approved
prior to the preparation of the project plan but should be included as
part of the plan. The project charter clearly delineates management
responsibility, authority, and accountability for the project. It
establishes the operational management relationships between
Headquarters and field project management organizations. The project
charter should contain the information outlined below:
(1) The responsible managing organization (e. g., special project
office, DOE Field Office, energy technology center).
(2) The name of the designated project manager and the effective date
of assignment.
(3) The location of the project management office.
(4) The support (including interface coordination) to be furnished to
the project manager by other participating organizations such as
other Departmental components.
(5) The authorities of the project manager including appropriate
references to DOE Orders, acquisition regulations, and other
guidelines.
(6) The reporting channel of the project manager, established to
account for the size, complexity, and importance of the project
and to eliminate unnecessary layers of authority above the
project manager.
Vertical line denotes change
Attachment II-2 DOE 4700.1 Chg 1
Page II-56 6-2-92
(7) Special instructions, or delegations of authority, to the project
manager for the execution of the approved project.
(8) Special requirements for a transition or termination plan to
outline tentatively the conditions under which the project
management organizational shall phase out or responsibility shall
be transferred.
(9) The staffing positions, including matrix staff, to be provided
for project execution.
3. REVIEW, CONCURRENCE, AND APPROVAL.
a. Major system acquisitions and major projects require Acquisition
Executive approval of the project plan prior to or concurrent with Key
Decision 1. The Headquarters concurrence chain for the plan includes
the Chief Financial Officer, Director of Administration and Human
Resource Management, General Counsel, Director of Procurement,
Assistance and Program Management, and the Assistant Secretary for
Environment, Safety and Health.
Section 77
(1) Concurrence and approval can be facilitated if these offices are
provided with copies of the plan for concurrent review before
forwarding for Acquisition Executive approval. The reviewing
organizations shall take no longer than 2 weeks to complete their
action.
(2) The concurrences of the Director of Procurement, Assistance and
Program Management and the Chief Financial Officer mean that the
business management, procurement, and financial information
presented in the plan are consistent with Departmental
business/financial practices, project requirements and budget
requests. The Director of Procurement, Assistance and Program
Management concurrence further confirms that the acquisition
strategy reflected in the plan is consistent with applicable
Federal and Departmental procurement or financial assistance
policies and regulations. The Associate Director for
Program/Project Management and Control concurrence confirms that
the plan is consistent with applicable OMB and DOE major system
acquisition policy, circulars, and directives. Assistant
Secretary of Environment, Safety and Health concurrence, in turn,
independently confirms that the plan adequately addresses project
conformance with applicable environmental, health, safety, and
quality assurance requirements.
Vertical line denotes change
DOE 4700.1 Chg 1 Attachment II-2
6-2-92 Page II-57 (through 11-60)
b. Timely review and approval of major system acquisitions and major
project plans are essential. In order to ensure timely review and
approval:
(1) The off ice of the responsible Program Secretarial Officer is the
focal point for managing the Headquarters staff review and
approval process.
(2) The Associate Director of Program/Project Management and Control
is responsible for assuring the adequacy of project plans
relative to Departmental policy and implementation guidance.
Furthermore, the Office of Program/Project Management and Control
maintains the DOE repository for project plans and provides
oversight of the change control process.
(3) Acquisition Executive approval will be provided in the Key
Decision 1 ESAAB Decision Memorandum. Project plan approval will
be reaffirmed at Key Decision 2, 3, and 4.
Vertical line denotes change
DOE 4700.1 Chg 1 Attachment II-3
6-2-92 Page II-61 (and II-62)
PROJECT PLAN CHANGES
1. INTRODUCTION. The following requirements will be met for all project plan
changes on major system acquisitions and major projects. Field office
managers are responsible for change requirements for Other Projects. Such
requirements should be consistent with those indicated here.
a. Changes to approved Project Plans shall be in accordance with Chapter
III, Part A;
b. Only changes approved at the appropriate management level will be
incorporated into Project Plans.
c. The responsible project office will incorporate the approved changes.
Each revised page or attachment to a Project Plan will include the
revision number and the date revised.
d. Each Project Plan will include a Project Plan Change Log which will
contain:
(1) The revision number;
(2) A list of the pages that were revised and the revision date; and
(3) The authorizing Baselines Change Proposal number.
f. Whenever changes in a project would, under existing legislation,
require notification to the Congress, such notification shall be
provided with the Baseline Change Proposal. An example is a
congressionally imposed limit on total project cost. This is approved
by the PSO and submitted to Congress by the CFO.
Section 78
g. The cognizant project office will be responsible for preparing all
requested changes. The cognizant program office will prepare all
directed changes.
Vertical line denotes change
DOE 4700.1 Chg 1 Attachment II-4
6-2-92 Page II-63
GUIDANCE FOR PREPARING A PROJECT MANAGEMENT PLAN
1. OVERVIEW. The project management plan (PMP) is the document which sets
forth the plans, organization, and systems that those responsible for
managing the project shall utilize. The content and extent of detail of
the PMP will vary in accordance with the size and type of project and
state of project execution. The plan is developed by the managing
organization and approved by the Head of the Field Element following
review by the cognizant program office and other offices as deemed
appropriate. The plan should be kept current as the project progresses
and an annual review of the plan, with appropriate updating of sections,
should be made by the managing organization to assure that it is current.
The document may be of the magnitude described here, if the effort is a
major system acquisition or a major project: or it may be as simple as a
memorandum of understanding between the project manager and other
interested parties, if the project is small. See Attachment II-5. The
content should include the data described below.
2. THE PROJECT MANAGEMENT PLAN.
a. Introduction. This section should provide an overview of the sections
which follow and describe in general the project’s purpose, scope,
primary participants, and contracts. It should reference other
project documentation including the justification of mission need, the
project plan, which includes the project charter and indicate
subsequent plans which are to be developed (e.g., environmental,
quality assurance, safety, and configuration management).
b. Objectives. This section should expand the specific measurable
objectives of the project delineated in the project plan. The
following types of objectives shall be stated:
(1) Measurable technical and economic objectives in terms of design
criteria or performance capability;
(2) Schedule objectives for major items on the project critical parts
showing their relationship to the project summary work breakdown
structure elements; and
(3) Cost objectives for work breakdown structure level one, two, and
three elements and their relationship to the total project cost
provided in the project plan.
c. Management Organization and Responsibilities. This section consists
of descriptive text accompanied by appropriate organization charts.
The charts should be comprehensive in scope and at a level of detail
consistent with the current project phase of the acquisition cycle,
and
Vertical line denotes change
Attachment II-4 DOE 4700.1
Page II-64 3-6-87
should show significant project interfaces as well as lines of
authority, responsibility, accountability, and communication.
Definitions should be provided for all significant interfaces in the
project such as between project geographic locations, functional
units, and contractors. Any interface management control techniques
that will be utilized should be explained. Where there are industry
or utility partners, the partners should be identified and the
management relationships, their role in management, and implementation
of the project should be described; also, existing agreements (cost
sharing and other) with them or the status of agreements still to be
negotiated should be referenced. The staffing plans for the project
organization should be described in detail; this will include both the
present staff organization and future staffing plans, the mix of
dedicated project staff, grade levels, and the manpower plan by fiscal
year.
Section 79
d. Work Plan. This section should describe in detail what is going to be
done and how it should be accomplished in accordance with the project
summary work breakdown structure. The major subsystems or elements
being developed or constructed, relating to the level two and
associated level three elements, should be described in detail.
Summary system design descriptions relating project performance
requirements and design parameters should be provided. Each phase of
project activity should be described, including what is to be
accomplished in the current and subsequent phases of the acquisition
cycle and the products to be developed. The technical criteria for
project design and construction should be defined including
environment, safety and health requirements; codes, standards, and
specifications of Federal, State, and local Governments and their
agencies; industry and trade organizations; and intermediate technical
goals and milestones to measure accomplishment. A discussion of
quality assurance as it relates to the project, containing the status
of development of the quality assurance plan for the project, should
be included. A description of the structure and links between all
quality control and/or quality assurance elements, identification of
responsible individuals, and a description of the interaction and
coordination among various quality control and quality assurance
functions should be provided.
e. Work Breakdown Structure. This section should briefly discuss the
role of the work breakdown structure in the management of the project.
Provide the project summary work breakdown structure, dictionary, and
element definition to Level 3.
f. Schedule. This section should expand upon the project schedule
attachment to the project plan, show at level 3 of the project summary
work breakdown structure the integrated schedules of all project
effort including related research and operations, and disposition.
These schedules should use standard DOE symbols and contain the
following:
DOE 4700.1 Attachment II-4
Logic Diagrams.
3-6-87
g.
h.
i.
j.
Page II-65
(1) Key project activities, by applicable phases of the acquisition
cycle;
(2) Key aspects of the project described in the work plan section;
(3) Identification of all required Acquisition Executive key decisions
and equivalent program Secretarial Officer decision points;
(4) Significant milestones (particularly those on the critical path) by
which progress of the project can be measured, including required
environmental documentation; and
(5) Milestones for major approval/concurrence/coordination requirements
from other Federal or State agencies or officials.
Depict the proper sequencing of all project elements,
reflecting the work plan and schedule for the project. The logic diagram
shall portray the critical path of activities/events for the project. It
shall set forth all major activities, milestones and activity interface
relationships and cover related research and development, remaining
planning elements, criteria development, land acquisition, utility
acquisition and appropriate National Environmental Policy Act documen-
tation. It should also cover directly related elements charged to
operating or capital equipment not related to construction accounts.
Performance Criteria. Expand upon the technical objectives found in the
project plan, and state in measurable, quantitative terms, the performance
criteria for major subsystems (at a minimum for each level two element of
the project).
Section 80
Cost and Manpower Estimates. Provide cost and manpower estimates for each
project summary work breakdown structure level two and three element for
the duration of the effort by fiscal year to the degree feasible, using
the cost objectives stated in the project plan,
Project Functional Support Requirements. Referencing the project charter,
describe in brief summary the relationship between the project office,
field organization, and Headquarters with respect to the project/
functional organization structure. Describe lines of authority, operating
interrelationships, areas of responsibility, and procedures for resolution
of conflict between responsible organizations.
Attachment II-4
Page II-66
DOE 4700.1
3-6-87
k. Project Management, Measurement, and Planning and Control Systems. This
section describes the integrated systems that shall be used to manage the
cost, schedule, and technical performance of the project. This section
shall also address funds management and control. Items which should be
addressed include the project management philosophy toward project control
goals, and objectives and integration of the systems. Each system shall
be discussed with respect to required documentation, level of control,
relationship to other systems documentation and change control procedures
to be utilized.
1. Information and Reporting.
(1) This section briefly summarizes all pertinent project documentation,
including the document number and dates of original issuance and
latest revision.
(2) Describes contractor reporting requirements as required by the uni-
form reporting system and reflected in the various contracts and/or
agreements concerning the project.
(3) Provides a description and an indication of the frequency of project
reviews that shall be used to keep Departmental management apprised
of project progress and problems from contractor reviews to project
management through reviews for DOE Headquarters management.
m. Systems Engineering Management.
Where systems engineering is an integral
, this section should describe the extent to part of project execution
which systems engineering shall be used, how the process should be
managed, and who should be responsible for various aspects of management.
Chapter III, Part B, contains a discussion of systems engineering and a
sample systems engineering management plan.
n. Configuration Management. This section describes the details of technical
interface management and control during project execution. The con-
figuration management plan should highlight the establishment and opera-
tion of a Configuration Control Board (CCB), and the identification,
recording, and reporting of product interface data. Chapter III, Part C,
discusses the content of a typical configuration management plan and the
workings of a CCB.
o. Contingency. This section shall outline the conditions for use and the
responsibility for approval of contingency funds during execution of the
project.
DOE 4700.l
3-6-87
Attachment II-4
Page II-67
p. Quality Assurance. A section which contains the quality assurance program
elements for an activity, group of activities, or a project and describes
how conformance with such requirements is to be assured for such struc-
tures, systems, components and their operation commensurate with: (1) the
system complexity, duration and importance to satisfactory performance;
(2) the potential impact on environment, safety and health; (3) require-
ments for reliability and a continuity of operations; and (4) reporting of
unusual occurrences and remedial actions.
Section 81
g. Utility Services. This section defines specific actions being taken on
the project to assure availability of reliable utility service for both
project activities and operation.
r. Responsibility Matrix. A responsibility matrix is a two-dimensional
delineation of project actions/decisions and those responsible for
carrying them out. Figure II-11 below is a sample of a typical respon-
sibility matrix. This tool is intended to allow all personnel and organi-
zations involved in the project to ascertain quickly the roles played by
everyone in project planning and execution.
s. Annexes. The project management plan shall contain three annexes: Annex
I - Advance Acquisition or Assistance Plan, Annex II - Test and Evaluation
Plan, Annex III - Environmental, Safety, and Health Protection
Implementation Plan. When comparable documents exist, these documents may
be referenced instead of included as part of the project management plan.
(1) Annex I - Advance Acquisition or Assistance Plan. (See Chapter II,
Part E.) This plan describes the objectives and functions of
acquisition or assistance. Attachment II-7 describes its content.
(2) Annex II - Test and Evaluation Plan. (See Chapter III, Part B.) The
scope of the test and evaluation plan is dictated by the size,
complexity, and technical risk associated with the project. This
annex is detailed to the extent necessary to show the rationale for
the kind, amount, and schedule of the testing planned for the proj-
ect. Attachment, III-3 illustrates a typical test and evaluation plan
approach. Attachment III-4 is a comprehensive test program example.
Attachment II-4
Page II-68
DOE 4700.1
3-6-87
Responsibility Matrix
Change in
Budget
Allocate
Manpower
Change in Design
Specification
Change in
Schedule
(
R = Responsible A = Approve C = Consult I = Inform
Figure II-11
Responsibility Matrix
DOE 4700.1
3-6-87
Attachment II-4
Page II-69
(3) Annex III - Environmental, Safety, and Health Protection Implemen-
tation Plan. (See Chapter II, Part F) This annex defines specific
actions being taken on the project to comply with existing directives
on environment, safety, and health issues. These actions include
environment, safety and health policy; organization; training; prep-
aration of safety analyses, National Environmental Policy Act docu-
mentation, and environmental permits; reviews and audits; reporting
of unusual occurrences and remedial actions; and related management
implementing procedures to protect the health and safety of employees
and the public, and to minimize risks from hazards to life and prop-
erty. DOE/EV-1032 Environmental Compliance Guide and DOE 5480.1A
provide complete details on environmental planning for the project.
t. Submission and Approval. This section shall begin on a separate page.
The signature page for the project management plan shall include the
following:
(1) Submitted by: Project Manager
(2) A paragraph that contains a brief statement of the work that is
approved (e.g., Approved: Head of the Field Element).
u. Review and Concurrence. Timely review and concurrence of project manage-
ment plans are essential. The specific sequential steps in the review and
approval of project management plans are as follows:
(1) Step 1.
f
The project manager notifies the program manager and the
ield office that preparation is beginning on the draft plan or
update.
(2) Step 2. The project manager submits for review and comment one copy
each to the program manager, the Head of the Field Element, and
other offices deemed appropriate.
Section 82
(3) Step 3. The field element, program manager and other reviewing offi-
ces submit comments to project manager (within 14 workdays).
(4) Step 4. The project manager prepares the approval version in
accordance with comments on the draft plan.
(5) Step 5. The project manager sends one copy of the approval version
to the program manager for concurrence.
(6) Step 6. The program office sends concurrence or a list of deficien-
cies to the project manager (within 7 working days).
Attachment II-4
Page II-70
DOE 4700.1
3-6-87
(7) Step 7. If critical deficiencies exist, the project manager ensures
that the project management plan is corrected to eliminate deficien-
cies and obtains program manager concurrence.
(8) Step 8. After obtaining program manager concurrence, the project
manager forwards the project management plan to the Head of the
Field Element for approval.
(9) Step 9. The Head of the Field Element approves the project manage-
ment plan and returns the plan to the project office.
Attachment II-5DOE 4700.1
3-6-87
1.
2.
Page II-71
PLANNING GUIDANCE FOR OTHER PROJECTS
Projects other than major system acquisitions or major projects need careful
planning. The principal responsibility for initiation of other projects lies
with the Head of Field Element. He or she shall develop and implement proced-
ures for project managers to follow.
a. Project Manager Appointment. As the size of projects diminishes, there is
less likelihood of a formal appointment of a project manager and
establishment of a project charter. This does not mean that there will
not be responsible people, but simply, that the responsibility shall be
understood rather than officially delegated in writing. This expedient
can create problems, but its reality must be recognized.
b. Project Management Tools. Local procedures will differ in terms of
managing other projects, reflecting the management concepts of the field
element. There are certain requirements that project managers shall meet
in order to effectively manage the project. These requirements include:
(1) Effective planning;
(2) Realistic scheduling;
(3) Realistic budgeting;
(4) Identification of key personnel; and
(5) Proper change control.
c. Planning Checklist. Before starting any complex planning sequence, it is
valuable to have a checklist of what shall be done. The process can save
the project from aborted planning efforts, redundant actions, and forgot-
ten details.
OTHER PROJECT MANAGEMENT PLAN. A project management plan is necessary, but it
does not have to be elaborate. In some instances, a generic PMP may be suf-
ficient. Even if the project is part of a larger one that has its own overall
PMP, it is still necessary for managers to have a plan from which to work.
The essentials of a PMP are as follows:
a. A summary of the project that can be read by anyone in a few minutes and
that will provide an understanding of the essentials of the project. It
states briefly what is to be done and may mention the methods and tech-
niques to be used. It lists the deliverable end products in such a way
that when they are produced they can be easily identified and compared
with the plan.
Attachment II-5
Page II-72
DOE 4700.1
3-6-87
b. A list of tangible and discrete milestones, identified in such a way that
there can be no ambiguity about whether a milestone has been achieved. In
general, the number of milestones shall correspond to reasonable dollar
portions of the project budget in order to provide adequate monitoring.
Section 83
c. A Work Breakdown Structure that is detailed enough to provide meaningful
identification of all tasks, plus all higher-level work groupings.
d. From the milestone list and the WBS, an activity network that shows the
sequence of the elements of the project and how they are related (which
ones can be done concurrently, which can start only when another is
finished, and so forth). This is more useful than just marking end points
on bar charts.
e. Separate budgets and schedules for all the elements of the project that
some individual is responsible for.
f. An interface plan that shows how the project communicates with the rest of
the world, most particularly with the contractor, but also with Depart-
mental line or staff organizations that are involved.
g. An indication of the reporting and review process--what reports are
needed, who reviews the project, when, and for what purpose.
h. A list of key project personnel and their assignments in relation to the
WBS. Key personnel are those responsible for the various phases of the
project.
3. PROJECT MANAGEMENT PLAN CONSIDERATIONS.
a. Work Breakdown Structure. Each project, no matter how small, shall have a
two- or three-level WBS. It is easy and efficient to review a plan on
paper and see how things are organized and where each piece fits. The WBS
also becomes a handy tool for estimating, scheduling, and reporting, as
well as a checklist for what is going on. Chapter II, Part B, and the WBS
guide DOE/MA-0040 describes the WBS as a project tool.
b. Master Milestone Schedule. Each element of the project has its own set of
milestones. The PMP, therefore, needs a master milestone schedule. The
schedule has two functions:
(1) It shows the time phasing and relationships of the different jobs to
be done, indicating which can be done in parallel and which must be
done in series, or where overlaps are possible; and
(2) It serves as a basic management tool for monitoring progress.
DOE 4700.1
3-6-87
Attachment II-5
Page II-73
c. Project Budget. When a project is initiated, funds are allocated for its
execution and are expended over some period of time. As time progresses,
however, the project manager will find that managing the project to the
total budget amount rather than by a rate of expenditure will be
inadequate. The project manager should be able to estimate the rate of
expenditure as a function of time and plot it on a graph.
(1)
(2)
Other Direct Charge (ODC) items can present a problem throughout the
life of the project since they often do not appear in the cost
reporting system until long after they were incurred. To make the
planned budget look more like the actual reported costs, it might be
wise to build in a time delay for the ODC items that can be foreseen.
The project budget shall consist of a set of plots of expenditures
versus time, one for each project element and one for the total proj-
ect. As the work is being done, one can plot reported actual expen-
ditures on the same graphs, note the variances and then determine
from the plan, the reasons for any large deviations. By tying
budgets and costs to specific pieces of work, it is possible to
determine the true cost variance using the “earned value” technique.
Key personnel are the people who cause things to happen,
Section 84
and are differentiated from others in that they exercise judgment and
discretion in deciding how a thing is to be done, who is to do it, and
when it is to be done. A key employee controls the day-to-day expenditure
of the part of the project budget for which he or she is responsible. The
number one key person is the project manager; other key persons are those
that have been delegated some responsibilities. For purposes of the PMP,
a list of the names and titles (or responsibilities) of the key people on
the project is necessary. The list may be needed in preparing periodic
project reports. Moreover, it is a form of insurance in case the project
manager is removed from the project by sickness, accident, emergency, or
sudden draft for another job need. Anyone who has to take over will find
his or her job easier if it can be seen at a glance who the key persons
are and what their functions have been.
d. Key Personnel.
e. Project Reporting and Review. The PMP shall include a reporting and
review plan. In planning for reviews of projects, two kinds of reviews
shall be considered.
(1) Project Manager Review. The project manager shall be sufficiently
close to the project so that the status is known all the time. This
is normally assured by the reporting system output. Most projects,
however, have certain points where it is appropriate to assess the
status of all the parts. These points are usually easy to identify--
for example, the end of requirements analysis and the beginning of
Attachment II-5 DOE 4700.1
Page II-74
(2)
(3)
3-6-87
the design phase; or the end of the design phase, before implementa-
tion is started. Care shall be taken in scheduling periodic reviews
in the form of project review meetings unless there is something
positive to be expected.
Management Reviews. The field organization may have a policy of
periodic review of all projects. Find out when these reviews are
scheduled and show them in the PMP. If none are scheduled, there
shall be an agreement with management as to when the project shall be
reviewed, and this too shall be shown in the PMP.
There must be some plan for an orderly review process. DO not assume
that it is possible to keep track of everything informally, even if
the project is small. Management will want to know the status of the
project, and the project manager must have good information to give
them. Be sure to allow time in the schedule for preparation of such
reviews, as well as money for travel or other expenses of preparing a
presentation.
4. PROJECT CHANGES. Changes are normal and to be expected, but unless they are
made in an orderly way they can lead to chaos. The PMP contains all the
essential data on the project. When significant changes occur, the PMP should
be revised and all concerned parties shall be notified. Changes should not be
made without previous evaluation of all repercussions. There are several
types of changes:
a.
b.
c.
d.
e.
Technical Changes. Consider the consequences on cost and schedule.
Evaluate the elements of the project that interface with the one changed.
Schedule Changes. Evaluate the effect of schedule change on the other
parts of the project that may be dependent on it for inputs. Does it
affect the delivery dates of the deliverables? Has the contracting
officer been notified? Will it result in increased costs?
Cost Changes. Are the unexpected costs within budget constraints
(contingency reserve) , or will they cause an overrun? Can an overrun be
justified? If so, have the contracting officer and appropriate levels of
management been notified? An explanation should be provided.
Section 85
Personnel Changes. If key personnel have changes, will deliverable dates
be affected? Does the new person have all the information necessary. Are
any contractual requirements affected? Is the former person available for
consultation, if needed?
When any change is made, the project manager shall do the following:
(1) Revise the project management plan, making sure that all concerned
parties are notified;
DOE 4700.1
3-6-87
Attachment II-5
Page II-75 (and II-76)
(2) Evaluate all the consequences of the change and make sure that all
affected parts of the project (including budget and schedule) reflect
the change; and
(3) Ensure that program manager is requested to change the project plan
if there is a revision to the project baseline.
DOE 4700.1
3-6-87
Attachment II-6
Page II-77
BUSINESS STRATEGY GROUP AND ACQUISITION STRATEGY
1. INTRODUCTION. The following procedure describes the role of the business
strategy group in developing acquisition strategy for a DOE project. The
procedure is related predominantly to major system acquisitions and major
projects, but may be used in an abbreviated form for other significant
projects.
2. DEFINITION. A business strategy group is an ad hoc group of experienced
functional specialists established to furnish recommendations to program
or project managers relative to the business aspects of large projects.
Membership of the group may vary depending on the nature of the project
and its relation to other projects, the stage of development of the
project life cycle, and whether or not the group is responding to a
significant change or problem with an ongoing project requiring current
reassessment of strategy as previously planned.
3. RESPONSIBILITIES AND AUTHORITIES.
a. The Director of Procurement, Assistance and Program Management, in
consultation with the cognizant Program Secretarial Officer (or their
respective representatives), establishes business strategy groups for
the purpose of furnishing recommendations on major system acquisitions
and major projects to program or project managers developing
acquisition strategies, project management plans, which include
advance acquisition or assistance plans, and other purposes.
b. Director of Field/Headquarters Liaison or Field Procuring Activities
or their designees shall:
(1) Establish business strategy groups at the request of program or
project managers, or their representatives, for projects other
than those designated major system acquisitions and major
projects, to furnish the program or project managers with
recommendations for the development of acquisition strategies,
advance acquisition or assistance plans, and for other purposes.
(2) Serve as chairperson unless the cognizant Assistant Secretary or
his representative requests that a senior program management
official serve as chairperson in connection with Headquarters
initiated business strategy groups. In this later case, the
Director of Field/Headquarters Liaison or heads of field
procuring activities (or their designees) shall serve as a
member.
PROCEDURAL AND OPERATING GUIDANCE.
Attachment II-6 DOE 4700.1 Chg 1
Page II-78 6-2-92
c. Heads of Departmental Elements, when called upon, shall furnish
knowledgeable representative(s) to participate in the business
strategy groups. These representatives shall be of sufficient
professional stature to provide meaningful and authoritative input to
the business strategy groups in their respective areas of expertise.
Section 86
d. The Business Strategy Group Chairperson:
(1) Determines the functional disciplines that shall be represented
at a business strategy group and requests participation from the
appropriate organizations;
(2) Convenes and leads the discussion of the business strategy group
in order to formulate the recommendations; and
(3) Designates, from the chairperson’s organization, a secretary to
the business strategy group, who prepares the recommendations
report for the chairperson’s signature and distributes the
completed report.
e. Program or Project Managers furnish appropriate background information
on the project to the chairperson for review by the members of the
group prior to the meeting and attend meetings of the business
strategy group.
4.
a. Business Strategy Group Participants. Participants normally include
the following individuals: The chairperson, a secretary, the program
or project manager (depending upon the purpose for which the group is
established), the cognizant contracting officer (if known), and
representatives from the following Headquarters (or equivalent field)
organizations: General Counsel, Chief Financial Officer, the Office of
Procurement, Assistance and Program Management and, the Office of
Environment, Safety, and Health. Depending upon the circumstances,
representation from other functional or staff organizations, such as
personnel and labor relations, may also be required. In the case of a
business strategy group established to provide recommendations
relating to the development of a project acquisition strategy, if the
field organization that will have management responsibility for the
project has been determined, representatives from that organization
shall also be invited to the meeting.
b. Topics Considered by a Business Strategy Group. The Chairperson, in
coordination with the members, develops a list of topics to be
considered and furnishes this list to members prior to the first
meeting of the group. This list is tailored to the particular
circumstances and requirements of the project and situation involved.
A list of topics which would typically be considered by a business
strategy group held to advise program or project managers on the
development of a project acquisition strategy is
Vertical line denotes change
DOE 4700.1 Chg 1 Attachment II-6
6-2-92 Page II-79
contained in paragraph 5, below. Attachment II-7 contains a
description of topics which would typically be considered by a
business strategy group held to advise project mangers on the
development of an advance acquisition or assistance plan. Because the
interrelationships between topics are often as important as the topics
themselves, the business strategy group considers these
interrelationships in its deliberations, as well as the topics
themselves.
Section 87
c. Organization and Direction of a Business Strategy Group. The official
requiring the establishment of a business strategy group does so in a
memorandum to the Director of Field/Headquarters Liaison (PR-132), or
if initiated in the field to the cognizant procuring organization,
with a copy to the program and project managers. This memorandum
requests the designation of the chairperson and the convening of the
business strategy group. The designated chairperson, along with the
program/project manager (if different), determines the appropriate
functional specialties to be represented on the business strategy
group. After this determination has been made, the chairperson asks
each of the organizations that will be represented to designate a
member. The program or project manager provides the chairperson a
draft of the acquisition strategy statement, advance acquisition or
assistance plan, or other documents on which the group will be
providing recommendations, together with any other available
background information that would help the group understand the
project and its objectives. Once the membership has been determined,
the chairperson sends a memorandum to each member stating the purpose
of the business strategy group and outlining the issues that will be
considered by the group, together with the project background
information, the agenda, and time, date, and place of the meeting.
d. Distribution. The recommendation is prepared and furnished by the
chairperson to the cognizant program official. No particular format
is specified for the recommendation, but it should include a summary
of the purpose for establishing the business strategy group, a listing
of the members, a summary of the topics discussed, and the conclusion
and recommendations of the group. Copies of the recommendation are
furnished to each member of the business strategy group. A copy for
all business strategy groups established at Headquarters or in the
field shall be furnished to the Director of Field/Headquarters
Liaison. The recommendation shall generally be distributed within 10
working days of the meeting.
e. Termination of a Business Strategy Group. A business strategy group
is terminated after submittal of its recommendation. A copy shall be
retained in the project file. If a subsequent meeting is considered
necessary to provide advice regarding the same project, to the extent
possible the same members as those participating in the first business
strategy group(s) shall be designated for participation in the
subsequent group.
Vertical line denotes change
Attachment II-6
Page II-80
DOE 4700.1
3-6-87
5. ITEMS FOR CONSIDERATION - ACQUISITION/STRATEGY BUSINESS STRATEGY GROUP.
The following list of topics includes matters which would typically be
considered by a business strategy group held to provide recommendations to
the cognizant program official on the development of an acquisition or
assistance strategy and an advance acquisition or assistance plan for a
project. The list is not all inclusive nor will all business strategy
groups held for this purpose necessarily consider all of these topics.
The exact list of items to be considered by a business strategy group
shall be tailored to the state and the particular characteristics of the
project.
a. OMB Circular A-76 concerns - role of public versus private sector and
determination of appropriate technical, cost, and management risk
balance among the parties involved.
Section 88
b. Role of other governmental bodies, laboratories, operating and
management contractors, and non-profit organizations.
c. Methods of obtaining and sustaining competition, including use of
multi-phase contracts and parallel development.
d. Lessons learned from past similar projects.
e. Project and construction management responsibility, including
responsibility for and method of site acquisition.
f. Plan for cost sharing and/or contractor incentives in light of project
risk balance and potential benefits for contractor. This topic
includes consideration of the structure and capabilities of the
industry involved and the interest of firms and/or the users of the
project results.
g. Project-to-project and project-to-program relationships.
h. Susceptibility of the schedule to change and the impact on contractual
strategy.
i. Preliminary contracting plan, including use of procurement or
financial assistance; general method of contracting and types of
contracts, any perceived requirements and scheduling for establishment
of source evaluation boards and/or architect-engineer devaluation
boards; procedure and justification for any noncompetitive
procurement, general solicitation/invitation content and timing; and
tentative qualification (if any) and evaluation criteria.
DOE 4700.1
3-6-87
Attachment II-6
Page II-81 (and II-82)
j. Demonstration and test criteria - adequacy of criteria and testing time
allowed.
k. Licensing, royalties, and receipts.
l. Preliminary plan for disposition of patents and data rights.
m. Independent cost estimates.
n. Funding plan and risks of reduced funding.
o. Organizational conflict of interest concerns.
p. Participant responsibilities for obtaining necessary permits and environ-
mental approvals.
q. Environmental, safety, and health and quality assurance considerations.
r. Plan for site, facility, and equipment disposition at the end of the proj-
ect. Includes site restoration and transfer of title.
s. Use of options and/or follow-on considerations.
t. Long-lead time items impact.
u. Government furnished property.
v. Public release of information - press releases.
w. Security.
x. Preliminary work breakdown structure.
y. Lease versus buy.
z. Incentives.
aa. Liquidated damages.
bb. Breakout of requirements for small or minority business.
cc. Real estate aspects.
dd. Multiple awards.
ee. Project organization/staffing.
ff. Pre-award survey requirement.
DOE 4700.1
3-6-87
Attachment II-7
Page II-83
ADVANCE ACQUISITION OR ASSISTANCE PLAN
Section 89
1. PURPOSE. Annex I to the project management plan is an Advance Acquisition or
Assistance Plan (AAAP). The document is to be detailed to the extent
necessary to provide a clear understanding of how DOE is to accomplish its
acquisition or assistance process for the project. An AAAP is to provide a
description of the contractual means by which the project’s acquisition
strategy will be carried out. Use of an AAAP aids in reducing procurement
lead time and ensures consistency in the preparation of project contractual
execution documents by providing contracting officers and others involved in
project management with specific information about project business objec-
tives. In addition, the AAAP or the documentation which normally accompanies
it provides these personnel with an understanding of overall project goals.
The AAAP also serves as a lessons learned checklist to help bring to the
attention of the project manager and the business advisor(s) to the project
manager items that have been found to be of significant importance in the
contractual execution of past projects. It is a means for considering all of
the diverse, interacting factors which affect the contractual implementation
of a project and developing a coordinated plan for dealing with those factors.
An AAAP is prepared as an annex to the project management plan (PMP) for each
major system acquisition (MSA) or major project. The use of an AAAP is
encouraged for other projects. Acquisition or financial assistance planning
is initiated at the earliest practicable time in the project life cycle. This
is normally just after project approval for those projects which do not have a
mission need statement prepared. Thus, the initial acquisition or assistance
planning commences concurrent with project budget planning. This initial
advance acquisition and assistance planning is summarized (for major system
acquisitions and major projects) in the acquisition strategy section of the
project plan and for all construction projects in construction planning and
budget exhibit documents.
2. CONTENT OF AN ADVANCE ACQUISITION OR ASSISTANCE PLAN.
a. An AAAP is entitled: “ADVANCE ACQUISITION OR ASSISTANCE PLAN FOR (Name of
Project).” If a project management plan is not prepared for a project, or
if the AAAP is submitted separately from the project management plan, then
the following additional information is also required at the beginning of
an AAAP: (1) the cognizant Headquarters program manager, (2) the cogni-
zant field project management organization, and (3) the Project
Information Control System (PICS) project number of MSA's and major proj-
ects. The AAAP is signed by the project manager, concurred in by the
contracting officer, and approved by the operations office manager.
Attachment II-7
Page II-84
DOE 4700.1
3-6-87
b. Paragraph 3 below lists the elements of an AAAP. The items of information
included in the subparagraphs under paragraph 3 are commonly included in
an AAAP. This listing is not intended to be all-inclusive, nor will all
such plans include all of this information. However, each of the elements
should be considered for inclusion where appropriate in an AAAP. If a
particular item of information described in that paragraph is provided in
an attached project management plan or in another attached document (such
as a project plan) which accompanies the AAAP, then the only entry needed
for that item of information in the AAAP is a reference to where that in-
formation is located in the other attached document. In this case, the
information contained in the other document is incorporated by reference
into the AAAP, and if a change is made to the referenced information, this
constitutes a change to the AAAP.
Section 90
c. If an element listed in paragraph 3, below (other than those described in
subparagraphs a through g) is not applicable to a particular project, the
AAAP for that project includes only the title of the element followed by
"N/A."
d. The amount of discussion in a particular element of an AAAP will vary de-
pending upon the overall size and complexity of the project as well as the
significance of that particular item in the project. If an item of infor-
mation which the project manager deems appropriate for inclusion is not
available at the time that the AAAP is prepared, that fact is stated as an
entry for that item together with a statement indicating when the infor-
mation will be available. When the information subsequently becomes
available, it is distributed as a change to the original AAAP.
3. ADVANCE ACQUISITION OR ASSISTANCE PLAN ELEMENTS.
a. Description of the Project Work. This element includes discussion of the
followlng items:
(1) The overall project objectives in terms of the established technical,
cost, and schedule baseline objectives to be attained as well as a
description of the major phases and decision points of the project,
which will be reflected in the manner in which major contracts are
structured.
(2) The applicable “principal purpose” of the project in terms of either
procurement (acquisition) or financial assistance. This would in-
clude a reference to the applicable “Principal Program Determination”
(PPD) made pursuant to public Law 95-224, “The Federal Grant and
Cooperative Agreement Act of 1977,” if such a determination has been
made.
DOE 4700.1 Attachment II-7
3-6-87 Page II-85
(3) Identification of the technical and contracting organizations that
will have primary responsibility for the project. This includes a
statement about the capability of the cognizant contracting organiza-
tion to carry out this responsibility in terms of available, experi-
enced staff. The identification should also include a description of
the manner (dedicated staff, matrix, or other) in which administra-
tive support will be provided to the project.
b. Funding Plan. This element consists of a description of the present
authorization and appropriations for the project and planned requests for
budget authority. It also includes a statement about the risk of possible
funding changes and the impact that these changes would have on planned
contracts and contractual provisions. For example, if a reduction in the
overall project funds is a significant threat, this element would address
how funding would be made available for contract termination costs.
c. Award Schedule. To the extent to which it can be determined at the time
the AAAP is prepared, this schedule describes the projected items for
which a separate award is to be made, the type of award, the estimated
amount, the dates that procurement/assistance requests are planned to be
delivered to the contracting offices, and target-dates for award and
contract completion for all planned procurement contracts or financial
assistance awards of $1 million or more. This information can be depicted
in graphic form. An important consideration in developing the schedule is
to plan for phased awards and reselections (if parallel development is
employed) to eliminate gaps in project effort and unnecessary contract
extensions. Another consideration is to fit contractual actions together
so that, if appropriate, data resulting from one award is available for
use in Departmental decisionmaking or under other project awards. The
schedule must incorporate appropriate contractual action lead times for
the type and magnitude of contract involved, including those for support
services and Source Evaluation Board activities. The schedule of contrac-
tual actions should be organized according to the work breakdown struc-
ture. If a significant number of award actions will be sent to the
cognizant contracting office for accomplishment in the same time period,
some indication of the relative priority of these actions should be
included in the schedule or in an accompanying narrative.
Section 91
d. Discussion of Project Risks. This element contains a description of the
desired balance of project risks (i.e., cost, technical, schedule,) be-
tween the Government and potential contractors. The element should also
describe how this desired balance is to be contractually implemented.
This includes discussion of anticipated tradeoffs regarding project man-
agement responsibility, the anticipated degree of interest which potential
contractors have in the project, and the cost participation negotiating
Attachment II-7
Page II-86
DOE 4700.1
3-6-87
plan, if applicable. Another topic that would be included is the extent
to which contractual award fee provisions and/or cost, technical, and
schedule incentives will be used to alleviate potential project risks for
the Government.
e. Source Selection. Source selection of architect-engineer contractors is
guided by Interim Procurement Regulations Handbook No. 2, “Architect
Engineer Selection Procedures.” Source selection of other major contrac-
tors is guided by DOE/MA-0154, Acquisition Regulations Handbook Source
Evaluation Board (SEB). The SEB Handbook treats this subject in more
detail. This element consists of discussion of the following items:
(1)
(2)
(3)
(4)
The means by which sources of expertise in the private sector will be
selected to assist in or carry out the project activities. T h i s
includes a description of the means by which competition will be
obtained and sustained in the performance of these activities, such
as through use of parallel development contracts containing options
for extension from one phase of the project to another. If such
contracts will be used, the basis for deciding whether to exercise
the options should be discussed.
The types of solicitation documents that will be used to obtain pro-
posals for performing the project work, including qualification cri-
teria (if any) and evaluation criteria to be used in judging those
proposals.
The extent to which functional as opposed to detailed specification
statements of work will be employed in concept development and other
project research and development and design contracts. If appropri-
ate, a statement is also included discussing the degree to which com-
mercially available products and services will be acquired when
possible in preference to acquiring a Government-unique item. Any
opportunities for grouping requirements within this project and with
other projects to obtain quantity discounts should be addressed. If
the project involves repeated procurements of the same item over a
period of years, the possibility of using multiyear procurement pro-
cedures should also be discussed.
Requirements for any special contractual provisions not discussed in
other parts of the AAAP. This would include, for example, provisions
in long leadtime acquisition contracts which cover non-site-specific
as well as site-specific items to alleviate the impact of delays that
might occur because of problems in obtaining approval to perform the
project at a particular site. It would also include award fee provi-
sions incorporated in accordance with an Award Fee Determination Plan
(see DOE/MA/06007-1, “Types of Contracts and Agreements Guide
(Plan 1)”).
DOE 4700.1
3-6-87
Attachment II-7
Page II-87
Section 92
f. Anticipated Contractors and Participants. This element describes the
types of project contractors or participants. Because their presence may
create special contractual needs if other Government agencies, consortia,
advisory committees, nonprofit organizations, laboratories, other opera-
ting and onsite service contractors, or integrating contractors will be
involved in a project, their roles and any special contractual arrange-
ment(s) governing their roles should be described in this element. If a
justified noncompetitive award is planned to be made to an organization
that has not previously received a DOE award, this fact should also be
noted.
g. Socioeconomic Programs. This element describes the contribution which the
project is expected to make to DOE’s socioeconomic programs (e.g., antici-
pated utilization of small and small disadvantaged businesses, labor
surplus areas, and women-owned businesses), as described in the Annual
Call for Goals required by Public Law 95-507 as implemented annually by
the Office of Management and Budget guidance. This contribution can occur
through either prime awards or subcontracts. A contribution could be
achieved, for example, through use of the small business set-aside for
construction procurement actions.
h. Equipment and Supplies. The information in this element forms the basis
for planning the provision of project equipment and supplies. Included in
the element are the following items:
(1) A description of any equipment or supplies to be furnished by the
Government or a third party, as well as a generic description of
contractor-furnished equipment and supplies.
(2) This element also discusses which party will ultimately receive title
to Government-furnished equipment as well as the Government’s rights
to restore or abandon this equipment. Questions of equipment dispo-
sition should be considered early in the project life cycle, when the
positions developed as a result of this consideration can influence
the Government’s negotiation strategy where appropriate. If title to
such equipment is to be vested in the contractor, this element also
includes a reference to the statutory authority for vestment and, if
appropriate, any congressional notification required for vestment.
(3) If computer equipment must be purchased by the Department for the
project, the element should discuss plans for coordination with the
Headquarters Office of ADP Management (MA-24), preparation of an
Automated Data Processing Implementation Plan and the submittal of a
request to the General Services Administration for a Delegation of
Procurement Authority to DOE, in accordance with DOE 1360.1.
Attachment II-7 DOE 4700.1
Page II-88 3-6-87
i.
j.
k.
l. Receipts.
m.
n.
o.
Anticipated Organizational Conflict of Interest Concerns. This element
includes an explanation of any such concerns together with a statement
about whether legal counsel has been consulted and, if so, the results of
such consultations.
Patents and Data. Any special provision requirements for patents
generated in the course of an award are discussed in this element, as well
as any other anticipated issue involving patent and data rights or
licensing, such as possible problems with obtaining Government rights
because of background patents.
Reporting Requirements. General types of reporting that will be required
for administration of each contract under the Uniform Reporting System are
listed in this element.
Section 93
ducts,
Any anticipated receipts, such as from royalties, sale of pro-
fees, and other charges for services and special benefits, and sale
of Government property including scrap, should be described in this ele-
ment. All such receipts are described and estimated by fiscal year over
the life of the project.
Non-Government Participation. This element should describe the means by
which potential contractors or participants and ultimate users have been
and should be involved in the development and implementation of the
project acquisition strategy and the work description for major projects
awards. This would include any plans for having these parties comment on
draft solicitations for major contracts and for holding presolicitation
conferences.
Site Selection and Acquisition of Real Property. Acquisition of title,
and, in some cases, lesser interests in real property requires a formal
site selection. Site selection and acquisition of real property must
follow DOE policy as stated in DOE 4300.1A, REAL ESTATE (REAL PROPERTY)
MANAGEMENT, of 7-7-83. This element describes any plans for site selec-
tion and real property acquisition and ultimate disposal, including the
party responsible for it, with particular emphasis on any implications of
these actions on project contract provisions. Also included are plans to
contract for utility services for the sites, including a statement about
whether the provision of such services will necessitate an increase in
capacity for the local utility.
Use of Other Procedures. If other procedures, such as design to cost,
life cycle costing use of surveys, questionnaires, or warranties which
will require special contractual provisions, will be used in the project,
they are discussed in this element.
DOE 4700.1 Chg 1
6-2-92
Attachment II-7
Page II-89
4.
p. Other Information. Other information included in an AAAP would
include a discussion of any aspect of the project not previously
discussed which would have a serious impact on contractual actions or
scheduling, such as the following:
(1)
(2)
(3)
(4)
Any special congressional notifications or approvals required:
Approvals or permits required from other organizations, such as
from the Nuclear Regulatory Commission;
Special Headquarters reviews and approvals such as those required
prior to some sole source acquisitions (see DOE 4200.1C) or
before the acquisition of such items as consulting services,
periodicals, and audiovisual products; and
Any anticipated protests of a planned contract award (such as
might occur in a noncompetitive acquisition).
.
AAAP DEVELOPMENT AND APPROVAL PROCEDURES. Regardless of the size and
complexity of the project, there should be an AAAP developed to cover the
contractual aspects of the project. In developing and obtaining approval
of an AAAP, the following procedures should be utilized:
a. For Headquarters-initiated projects, the project manager, with the
advice and assistance of the Office of Procurement Support business
advisor and a business strategy group, normally starts the development
of the overall business strategy for a project after the approval of
the Justification of Mission Need. This overall business strategy is
summarized in the acquisition strategy section of the project plan.
Initial advance acquisition or financial assistance planning is a
natural product of this business strategy development process and is
also reflected in the statement of that strategy contained in the
project plan. Thus, initial advance acquisition or assistance
planning starts after approval of the Justification of Mission Need.
For field-initiated projects, the cognizant management organizations
within the field element perform the functions above to develop the
project business strategy and perform their initial advance
acquisition or assistance planning.
Section 94
b. The initial general advance acquisition and assistance planning,
summarized in the acquisition strategy section of the project plan,
forms the basis for development of the comprehensive AAAP. After
project manager assignment, a draft AAAP is prepared with the
assistance of the cognizant field office contracting officer (or
representative). This draft AAAP includes elements appropriate for
the particular project involved.
Vertical line denotes change
Attachment II-6 DOE 4700.1
Page II-90 3-6-87
c. The draft AAAP is then submitted to a business strategy group for its
consideration, if such a group is used to advise the project manager
in developing the AAAP. The BSG reviews the draft AAAP in light of
the project objectives and characteristics and includes any
recommended changes to the AAAP in a report to the project manager.
If a business strategy group is not used, the project manager obtains
the necessary advice to complete the AAAP from different functional
areas within the manager’s own organization, from other Headquarters
and field elements, and as appropriate, from supporting contractors.
d. The project manager, with the assistance of the cognizant contracting
officer or representative(s), prepares the final AAAP, taking into
account the advice received and the contents of the business strategy
group report (if any). The plan is signed by the project manager and
concurred in by the cognizant contracting officer prior to its
approval by the operations office manager.
e. If a project management plan is prepared for a project, the AAAP
normally becomes an annex to the project management plan and is
reviewed and approved as a part of the project management plan. If a
project management plan is not prepared for a project, or if the AAAP
is submitted separately from the project management plan, the AAAP is
then reviewed and approved in the same manner as is a project
management plan. After approval, the AAAP is distributed to the
cognizant contracting officer, the members of the business strategy
group (if any) that provided advice on preparation of the plan, the
program manager, and all other organizations involved in project
execution. A copy of the AMP, together with the project management
plan, if one exists, is also sent to Headquarters. The AAAP should
normally be completed and distributed in time for it to be received in
the cognizant contracting office and other offices involved in project
execution at least 6 months prior to the time that the first
procurement (or financial assistance) request for a project
contractual action (other than for conceptual design activities) is
scheduled for release.
DOE 4700.1 Chg 1
6-2-92
CHAPTER III
PROJ ECT CONTROL
PART A CHANGE CONTROL AT THE EXECUTIVE LEVEL
III-1
1. INTRODUCTION. This chapter discusses the management of cost, schedule,
and technical baselines of MSAs and MPs. Establishment and maintenance of
baselines are the most important aspects of project control. Change to
baselines must be carefully controlled to avoid loss of control and
distortions in performance reporting.
2. OBJECTIVES. The objectives of this chapter are to:
a. Assure cost, schedule, and scope baselines are clearly defined,
documented and approved at Key Decision 1, approve New Start;
b. Assure baseline changes are defined, documented, and approved, and
authority and responsibilities for such approval are delineated;
c. Provide assurance that decisions are made at the appropriate
management level; and
Section 95
d. Enhance accountability and traceability in the DOE decision-making
process.
3. REQUIREMENTS.
a. Establishment of Baselines. Initial scope, cost, and schedule
baselines for D0E executive level and field level control will be
derived from the Conceptual Design Report (CDR) and related support
documentation. These baselines will be reviewed and approved by the
AE at KD 1.
b. Baseline Change Decision-making Authority. BCCBs will be established
at the D0E executive level (ESAAB and Program BCCBs, identified as
Level O and Level 1 Boards, respectively) and DOE field level (Project
BCCB identified as the Level 2 Board). Membership of the Level O
Board will be the same as the ESAAB. Membership of the Level 1 and 2
Boards will be at the discretion of the respective board chairperson.
Authority and responsibilities of each board are to be defined in its
respective board charter. The BCCB Chairperson shall have full
decision-making authority; a BCCB is an advisory, not a voting board.
A BCCB Chairperson, at his/her discretion, may provide disposition of
a requested change without conducting a board meeting.
c. Baseline Change Authority Thresholds. The thresholds that shall be
used to determine the appropriate management approval level for
requested changes to project baselines follow.
Vertical line denotes change
III-2 DOE 4700.1 Chg 1
6-2-92
(1) The Level O Baseline Change Control Board shall provide
disposition for changes within the following thresholds:
Cost: + $50,000,000 and greater
Schedule: + 6 months and greater
(2) The Level O BCCB shall provide disposition for changes within the
following thresholds:
Cost: less than $50,000,000
Schedule: less than 6 months to Level O Milestones
Authority thresholds for Level 2 Milestones will be established
at KD 1.
(3) The thresholds for lower level boards will be established for
each project at KD 1.
(4) Any change to scope baselines identified at KD 1 must be
submitted to the appropriate level board.
(5) Any change which exceeds + $50,000,000 but does not impact Level
O scope may be approved by the Director of Procurement,
Assistance and Program Management (PR-1). PR-1 may convene a
Level O BCCB meeting for these changes if he/she deems it
necessary. Any change that exceeds + $50,000,000 and impacts
Level O scope and/or TPC requires Level O BCCB approval.
(6) The cost threshold values identified above are the estimated
costs of a change, (design, construction, and testing costs)
regardless of source of budget and funding (increases or
decreases to Total Estimated Costs (TEC), Total Project Cost
(TPC), or available contingency as defined in Attachment 3 of
this order).
d. Baseline Change Decision-making Process Time. Initiators of requested
changes will designate each change as either “priority” or “routine.”
The allowable change processing timeframe for the Level O and 1 Boards
for these designations shall be:
Priority: Maximum 10 working days each
Routine: Maximum 20 working days each
Lower level boards will define their respective processing
designations and timeframes in their charters.
e. Baseline Change Accountability, Traceability, and Overview. Each
board will provide auditable and traceable documentation for (1) board
members’ evaluation and comments and (2) BCCB decisions. Information
copies of BCCB meeting minutes and approved Baseline Change Proposals
will be provided to the next higher level BCCB Secretariat.
Vertical line denotes change
6-2-92
D0E 4700.1 Chg 1 III-3
Section 96
f. Submittal of Requested Changes to Level O, 1, and 2 BCCBs.
(1) Only changes endorsed by the next lower level BCCB Chairperson
will be presented to Executive Level BCCBs for action.
(2) Existing contractor change forms currently utilized by projects
may be utilized for documenting contractor requested baseline
changes, providing that the forms address the following minimum
requirements:
(a) Change justification;
(b) Change description;
(c) A unique identification number and title;
(d) Change request processing time designation (priority or
routine);
(e) Cost impact including impacts on TEC and TPC;
(f) Schedule impact on controlled milestones identified at KD 1;
(g) Designation of a Point-of-contact for coordination;
(h) Impacts on funding profile;
(i) Impacts on scope;
(j) Programmatic impacts;
(k) Mitigating or corrective action if appropriate; and
(l) Other impacts as appropriate.
(3) For directed changes, the directive will be the authorization for
implementing the change (directed changes do not require BCCB
approval). The project office will determine and document
resulting impacts to other baselines, when appropriate, and
provide information copies of the change impacts to appropriate
management levels.
(4) If changes (either approved or directed) exceed Congressionally
mandated thresholds, Congressional notification is required prior
to approval and authorization to proceed. All Congressional
notifications must be coordinated through the Chief Financial
Officer prior to submission in accordance with DOE 5160.1A,
REPROGRAMMING, RESTRUCTURING, AND APPROPRIATION TRANSFER
PROCEDURES.
Vertical line denotes Change
III-4 DOE 4700.1 Chg 1
6-2-92
4. Guidance.
a. Figure III-13 depicts the DOE change control authority hierarchy of
BCCBs. Figure III-14 presents the flow diagram for the DOE Baseline
Change Control Process.
b. Figure III-15 is a sample format that should be utilized for
documenting the initial cost, schedule, and scope (technical)
baselines for approval at KD 1. Subsequent to approval, these
documented baselines will be maintained current by the appropriate
project offices and will be included as a part of documentation
requirements for all ESAAB and Program Reviews.
c. Figure III-16 is a sample format that should be used for documenting
change control thresholds to the baselines for approval at KD 1.
These thresholds define delegation of change control authority within
the DOE. Upon approval of these thresholds, changes to them must be
approved by the appropriate level of authority (AE, Program Manager,
Project Manager).
d. Figure III-17 is a sample format that meets the requirements stated in
Section 3 above for a Baseline Change Proposal (BCP).
e. Contractor level Change Control Boards and change processes will meet
the provisions of Part C of this chapter.
f. Figure III-18 is a sample format for the Baseline Change Control Board
Change Disposition Record.
g. Instructions for completing Figures III-15, III-16, III-17, and III-18
are presented in Attachment III-8.
h. Change Activity Reporting. Baseline Change Control is one of the
Department’s key initiatives to strengthen the current project
management system and has received the full endorsement of the
Acquisition Executives. An effective change control process is
critical to the management of project cost, schedule, and scope
baselines and assuring that the Department is utilizing its limited
resources in the most effective manner possible. To increase
visibility into change control activity, MSA quarterly progress
reports shall be required to include a change activity status. All
level O, 1, and 2 changes are to be reported.
Section 97
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
III-4a
Vertical line denotes change
DOE BASELINE CHANGE
DECISION-MAKING PROCESS
Figure III-14
.
SUMMARY OF BASELINE INFORMATION FORMAT
Figure III-15
REVISION:
DATE:
SUMMARY OF THRESHOLDS FORMAT
Figure III-16
0-0D0-7365/24
DOE 4700.1 Chg 1
6-2-92
III-4e
Vertical line denotes change
III-4f
SAMPLE FORMAT
DOE 4700.1 Chg 1
6-2-92
Vertical line denotes change
III-5 DOE 4700.1
3-6-87
PART B - SYSTEMS ENGINEERING, TEST, AND EVALUATION.
1. INTRODUCTION. The system engineering process is a sequence of activities and
decisions that transforms an identified mission need into a description of
system performance parameters and a preferred system configuration. The
Department’s objective is to ensure that products satisfy their functional
requirements, operate effectively in their intended environment, and
demonstrate a level of performance and reliability that justifies the invest-
ment. The approach outlined below is illustrative of one method of applying
systems engineering principles. The system engineering process is detailed
further in Attachment III-1.
2. SYSTEM ENGINEERING APPROACH.
a.
b.
c.
The system engineering process considers all aspects of system require-
ments from the earliest stages of design through development, test and
operation. The process supports project management by ensuring that tech-
nical control is on a level and integrated with funds, cost, schedule, and
performance controls.
For MSA’s and major projects, the system engineering management process is
normally controlled by adherence to a System Engineering Management Plan
(SEMP) (see Attachment III-2), prepared and maintained at the project
level and by non-DOE organizations contributing to the engineering
efforts. The project level SEMP may be an integration of the plans of
other contributing organizations.
For any project requiring an integrated engineering procedure, the project
office should consider a SEMP as a component of the project management
plan. Similarly, any non-DOE organization contributing to the engineering
effort should prepare and maintain a SEMP that integrates with the project
level plan. The plan should include a discussion of how the various
system engineering management elements will be utilized and controlled on
the project. System engineering management elements include the
following:
(1) Planning.
(a) Technical Objectives.
should
Technical objectives for each project
be established so that relationships among project needs,
urgency, risks, and value can be established.
(b) Engineering Integration. Coordination should be provided for
among the engineering disciplines and specialties, and their
integration into the design process should be provided for as
early as possible.
III-6 DOE 4700.1
3-6-87
(2) Design Concepts.
(a) Completeness. The design should be complete from a total system
viewpoint to include facilities, utilities, hardware, software,
personnel, and procedures.
(b) Interface Compatibility. Requirements regarding design com-
patibility of engineering interfaces should be defined in
appropriate specifications. Interface requirements related to
major system elements, facilities, utilities, hardware, soft-
ware, and procedures should be established, coordinated, and
maintained. Clear lines of communication and timely dissemina-
tion of changes to these interface documents should be
maintained.
Section 98
(c) Simplicity. The concept of design simplicity and maximum stand-
ardization should be promoted (e.g., existing technology and
standard off-the-shelf hardware items should be used whenever
requirements and analyses permit).
(3) Technical Requirement Definition.
(a) Technical Baseline. The technical baseline should initially be
developed with top level requirements based on mission needs and
an assessment of existing available technology, and should
become more detailed as the project progresses. Specifications
should be prepared in accordance with specified standards.
Attainable performance and other required technical parameters
should be established prior to commencement of development,
construction, or fabrication.
(b) Engineering Data. Engineering data (e.g., design drawings,
specifications) should be the primary source of performance
requirements used in the design and production/construction of
the system. Where possible, plans, reports, and other existing
data items should be used to record the system engineering proc-
ess. Government technical information may be made available to
project participants.
(c) Traceability. It should be possible to track system require-
ments from a function to all of its elements; from an element to
its functions; and, from a specific requirement to its source
analysis or contractual constraint. Traceability includes
tracking requirements through the work breakdown structure be-
tween the system level and the lowest level of assembly
requiring logistic or maintenance consideration.
DOE 4700.1
3-6-87
(4) Controls.
III- 7
(a)
(b)
(c)
(d)
(e)
Work Breakdown Structure Compatibility. The technical tasks to
be performed are identified as work breakdown structure ele-
ments. System and technical requirements also should be con-
sistent and traceable throughout the work breakdown structure
so that the impact of cost, schedule, and technical problems can
be promptly determined and accurately evaluated.
Technology Risk Assessment. Specification development, cost
estimates, engineering decisions, and assessments of alternative
development schemes should be aided by estimation and evaluation
of risk in the various project elements, activities, and
technologies.
Technical Performance Measurement. Technical performance
measurement is the comparison of actual achievement against the
technical baseline. It includes an analysis of the differences
between the achievement to date, the current estimate, and the
technical baseline, with any new problems and risk areas
identified.
Compatibility with Related Activities. The system engineering
management activities should be compatible with related project
management activities. For example, changes to system require-
ments in response to identified problem solutions should be
evaluated for total project impact with respect to performance,
cost, and schedules.
Review of Data. System engineering includes design documenta-
tion and review to ensure that all system requirements have been
met. “In process” reviews should be utilized to the fullest
extent possible. The project manager should ensure that all
system engineering procedures, requirements, and data are
available for review and that the contractor’s ability to
satisfy them is documented in the SEMP.
(5) Analysis.
Section 99
(a) Engineering Decision Studies. Engineering decisions regarding
design options should reflect analysis of system cost effective-
ness based on performance and other technical parameters, proj-
ect schedule, resource constraints, risk assessments, and life
cycle cost factors. Significant engineering decisions should be
traceable to the system engineering analysis on which they were
based.
(b) Life Cycle Cost Estimates. These cost estimates include
acquisition and ownership costs including operation, maintenance
and disposition costs.
III-8
3. TEST AND EVALUATION.
a.
b.
c.
DOE 4700.1
3-6-87
It is difficult to develop and utilize a standard project test and eval-
uation plan for DOE projects. The test and evaluation plan should con-
sider both component and systems testing to help ensure technical perfor-
mance. The plan should relate the test and evaluation effort to the proj-
ect’s technical risks, operability, performance criteria, reliability,
availability and maintainability. The test program should measure tech-
nical performance, to assure the project manager that the technical base-
line can be met. Attachment III-3 provides a suggested outline of a test
and evaluation plan for MSA/MP’s and Attachment III-4 gives an illustra-
tion of a comprehensive test program for the measurement of technical per-
formance for an integrated, complex project.
Technical performance measurement involves the assessment of current and
expected performance and identification of technical problems. These
assessments coincide with the completion of significant design and devel-
opment tasks. This provides visibility into actual versus planned tech-
nical performance, and facilitates verification of results achieved. If
performance is different than planned, change options are proposed.
Revised work plans to complete major design and development milestones may
be developed. The revised work plans provide the basis for forecasting
cost and schedule impacts.
A technical performance measurement effort which includes the following
items and is tailored to meet specific project needs should be planned and
executed:
(1) Parameters. The technical performance parameters selected for
tracking and testing should be the key indicators of project success.
Each parameter should be related to a specific work breakdown struc-
ture element and identified in the SEMP. The relationship of tech-
nical performance parameters can be depicted through a specification
tree.
(2) Planning. During test and evaluation planning, the following data,
as appropriate, should be established for each parameter:
(a)
(b)
(c)
Specification;
A time-phased planned value profile that plots the expected
growth over time of the parameter being tested, along with a
tolerance band, the boundaries of which indicate the range
within which the value is expected to be achieved within current
budget and schedule, including usual forecast error;
Other events significantly related to the achievement of the
planned value; and
DOE 4700.1
3-6-87
III-9 (and III-10)
(d) Test conditions.
Section 100
(3) AS design and development progresses, achievement is evaluated for
each technical performance parameter. If actual achievement falls
outside the tolerance band, a new current estimate should be devel-
oped. The current estimate should be determined from the actual
achievement and the remaining schedule and budget. Variation should
be determined by comparing actual achievement against the technical
baseline. An analysis should be accomplished on the variation to
determine the causes and to assess the impact on higher level parame-
ters, on interface requirements, and on system cost effectiveness.
For technical performance deficiencies, alternate recovery plans
should be developed with cost, schedule, and technical performance
implications fully explored. For performance in excess of require-
ments, opportunities for reallocation of requirements and resources
should be assessed.
d. The technical test planning function defines the detailed work require-
ments and forms the basis for scheduling of task elements, allocation and
costing of resources, assignments of authority and responsibility, and the
integration of all technical aspects of the project. On contracts subject
to the cost and schedule control systems criteria, the test and evaluation
planning function is carried out to prescribed work breakdown structure
levels as part of compliance.
e. Cost and schedule performance measurement employs earned value to identify
cost and schedule variances and performance trends. Unexpected technical
problems are often the source of cost and schedule variances. Technical
performance, evaluation may facilitate early identification and definition
of these problems and estimation of their cost and schedule impact.
DOE 4700.1 Chg 1
6-2-92
III-11
PART C - CONFIGURATION MANAGEMENT
1. INTRODUCTION.
a. Configuration management is a project management tool that is designed
to: (1) determine and control baselines; and (2) ensure and document
that all components of a project interface both physically and
functionally. The purpose of configuration management is to ensure
that the product acquired satisfies the project’s technical and
operational requirements, and that the technical requirements are
clearly defined and controlled throughout the development and
acquisition process.
b. The objectives of configuration management are to:
(1) Assist in achieving, at the lowest cost, the required system
performance and operational efficiency.
(2) Promote the maximum degree of design and development latitude,
yet provide the appropriate degree and depth of configuration
control.
(3) Attain maximum efficiency in the management of configuration
changes with respect to their necessity, benefit, cost, timing,
and implementation.
(4) Provide a systematic review of all changes to assure that all
primary and secondary effects of proposed changes are identified
and their costs/benefits are weighed in making a decision to
incorporate a change.
2. CONFIGURATION MANAGEMENT.
a. The configuration management plan establishes technical interface
requirements and procedures, establishes a configuration control
board, and indicates approval levels for changes. Attachment III-5
outlines the configuration management process, and Attachment III-6
outlines a configuration management plan.
b. As a project progresses, the technical requirements become better
defined. At appropriate decision points these requirements are
approved and become part of the project’s technical baseline. The
configuration management requirements are:
Section 101
(1) Configuration Identification. Configuration identification is
established in the form of technical documentation. With DOE
review and approval, the technical baseline initially identified
in the project plan is controlled, detailed, and updated through
conceptual design, preliminary design (e.g., Title I), definitive
design (e.g., Title II), and as-built drawings (e.g., Title III).
Operations and maintenance manuals and specification may be
controlled separately or as part of the definitive design.
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
III-12
(2)
(3)
(4)
Configuration Control. Documentation may be changed as agreed to
by DOE and as described in the contractor’s configuration
management plan. Contractor proposed changes should be screened
by the contractor to determine whether DOE approval is required
prior to implementation. If prior approval is required, the
change shall be formally proposed to the project office prior to
implementation. The project office will approve or disapprove
the change or endorse and forward to the next higher board if the
change exceeds the project office approval authority. If prior
DOE approval is not required, the contractor may implement the
change. The contractor’s control system should:
(a) Permit identification of the status of a proposed change;
(b) Permit identification of status of change implementation;
and
(c) Provide an audit trail of change history.
Configuration Recording and Reporting. As a project progresses,
the status of proposed changes to configuration and the progress
on implementation of approved changes need to be identified and
reported. The project office is responsible for selecting
specific data elements, choosing record and reports formats, and
keeping the actual records. As appropriate, contractor’s records
and report formats will be accepted when they provide the
necessary information. (Attachment III-5 identified typical
configuration identification and reporting data elements.)
Waivers and Deviations. The change process includes a procedure
for converting change proposals to an approved waiver or
deviation where conditions and potential cost benefits warrant.
A deviation constitutes contractual relief prior to producing a
product; a waiver constitutes contractual relief after producing
the product.
3. CONFIGURATION MANAGEMENT PLAN. The configuration management process is
controlled at the project level by a configuration management plan. For
major MSAs and MPs the project office should include a configuration
management plan as a component of the project management plan. For other
projects, which may not require a project management plan, a configuration
management plans should still be utilized. Each non-DOE organization
participating in the engineering effort should similarly be required for
their portion of the work to prepare and maintain a configuration
management plan that integrates with the project level plan. The project
level configuration management plan may be an integrated cohesive assembly
of the plans of participating organizations. The plan should include
discussion of how configuration management will be conducted on the
project and what items will be so managed.
Vertical line denotes change
DOE 4700.1
3-6-87
III-13
4. CONFIGURATION MANAGEMENT PROCESS.
a. Application.
(1)
(2)
(3)
(4)
(5)
Section 102
Configuration management should be consistent with the quantity,
size, scope, and complexity of the project involved. Complex proj-
ects may require a highly organized configuration management system,
while less complex projects may require nothing more than the control
of the applicable technical specification.
The configuration management process should be tailored to the speci-
fic project and to particular products. The selection of a facility,
equipment, or other item for formal configuration management is
determined by the need to control its inherent characteristics or to
control its interface with other items.
Initially, performance oriented functional requirements should be
used for configuration identification. Where appropriate, these
requirements may be allocated to selected items that are part of a
higher level item. Finally, a detailed design should prescribe
“build to” requirements and associated quality assurance provisions.
This identification should be the basis for the preparation of tech-
nical, administrative, and management documents, (e.g., technical
reports and spare parts) that concern or depend upon configuration.
A permanent copy of the controlled identification documents should be
maintained throughout the life cycle, beginning with the initial
baseline documentation and including proposed and approved changes
from those baselines.
Configuration control must be exercised on a basis appropriate to the
management level concerned and to the stage in the life cycle. All
affected project activities, such as engineering, logistic support,
quality assurance, maintenance, and procurement need to be involved
in evaluating proposed changes in the configuration of an item
throughout its life cycle. This would normally be accomplished
through a Configuration Control Board.
b. Change Control.
(1) Changes affecting the configuration of an item are to be limited to
those which are necessary or offer significant benefits to the
Department. Changes are required to:
(a) Correct deficiencies;
(b) Incorporate approved changes in operational or logistic support
characteristics;
(c) Effect substantial life cycle cost savings; or
III-14 DOE 4700.1
3-6-87
(d) Correct safety deficiencies.
(2) The project office ensures that all data required for effective eval-
uation of changes are made available to those individuals responsible
for change decisions. For example, an analysis of the effect caused
by the change in the item’s performance as prescribed in the con-
figuration identification should be provided. Insofar as prac-
ticable, test data needed to validate claimed technical and economic
advantages will also be included in this analysis. Every proposed
configuration change affecting Departmental interests should be eval-
uated on the basis of the change criteria, including not making the
proposed change. The evaluation should take into consideration all
aspects of the change on the products or systems with which it inter-
faces and other contractors affected, Such aspects may include
design, performance, cost, schedule, operational effectiveness,
logistics support, transportability, and training.
(3) The project office establishes priorities and time requirements for
change proposal processing based on its nature and its relative
urgency.
(4) When a configuration change is approved by DOE, the necessary
instructions need to be issued to ensure timely and economical imple-
mentation.
Section 103
c. Duration. Planning for configuration management should start with prep-
aration of the project plan and continue as part of the project planning
process. Configuration management continues throughout the product’s life
cycle until it is removed from inventory.
d. Recordkeeping and Reporting.
(1) Configuration records and reports include identification of:
(a) Technical documentation comprising the approved configuration
identification;
(b) Essential data (e.g., engineering test data);
(c) Contractual information required for each item subject to con-
figuration management, and contractor identification;
(d) Proposed changes to configuration, the status of such changes
and the individual responsible for change decisions; and
(e) Approved changes to configuration, including the specific number
or kind of items to which these changes apply, and the activity
responsible for implementation.
DOE 4700.1
3-6-87
III-15 (and III-16)
(2) The project manager tailors the recording and reporting requirements
in order to ensure that only the minimum information necessary to
manage configuration effectively and economically will be recorded
and reported. The special instruction section of DOE F 1332.1,
“Reporting Requirements Checklist”, should be used to list the
reporting requirements which should be a part of the Request for
Proposal and contract.
5. TECHNICAL BASELINES.
a.
b.
c.
d.
e.
f.
Baselines can be revised several times during the life of a project.
Insofar as performance measurement is concerned, the current configuration
of the end product represents the current technical baseline.
Functional Requirements Baseline is the initial technical baseline and is
based on the functional requirements of the end product that are derived
from the mission needs.
Technical Requirements Baseline is the basis for preliminary (Title I)
design and is established at the completion of conceptual design. It con-
sists of the documentation which describes the selected design approach
and specifies its design and performance requirements.
Design Requirements Baseline is the collection of documentation which
defines the preliminary (Title I) design. It is established at the
completion of preliminary (Title I) design and is the basis for the defi-
nitive (Title II) design.
The final baseline is established when definitive (Title II) design is
complete. It describes all the details of the design necessary for fabri-
cation, assembly, construction, installation, and checkout of the facili-
ties and equipment. It is composed of the specifications and drawings,
quality assurance provisions, test procedures, and operations and main-
tenance manuals.
Project baseline management is completed with the execution of the proj-
ect, but there is a continuing need to update the technical baseline
during its operation. When a completed project goes into operation, there
should be a set of “as-built” drawings which reflect the final con-
figuration of the project. During operation, many changes will take place
which will modify these drawings. It is the responsibility of the project
manager to ensure that the operating contractor makes changes to the spec-
ifications and drawings, so that all “as-builts” remain current for the
life of the facility.
DOE 4700.1
3-6-87
PART D - QUALITY ASSURANCE.
III-17
1. INTRODUCTION.
Section 104
a. Quality assurance (QA) begins at project conception and runs through
design, development, construction, fabrication, and operation. QA affects
cost, availability, effectiveness, safety and impact on the environment;
therefore, quality assurance aspects should be given careful consideration
during the preparation of system acquisition documentation.
b. DOE determines the requirements for assuring quality where there is a
recognized need to obtain the level of product and performance quality
necessary to accomplish Departmental program objectives; for reliability
and continuity of operations, commensurate with Departmental respon-
sibility for health and safety; and for the protection of the environment
and Government property.
c. Responsibility for quality assurance activities is a multifaceted
situation as reflected in Departmental QA policy.
(1) The program independent Office of Quality Assurance and Standards at
Headquarters is responsible for quality assurance overview and man-
agement appraisals of Departmental QA programs.
(2) The program Secretarial Officer is responsible for implementing the
Departmental QA policy.
(3) The project manager is responsible for defining and assuring effec-
tive implementation of required QA activities to be established and
implemented by the contractor.
(4) Contractors shall be responsible for installing and implementing QA
in accordance with their contractual requirements.
(5) DOE 57OO.6A provides the policy obligations required.
2. ELEMENTS OF QUALITY ASSURANCE MANAGEMENT. The quality requirements and the QA
activities considered necessary to accomplish the project objectives shall be
prescribed. Consideration shall be given to the following elements for their
appropriate inclusion in a QA program.
a. Quality Assurance Organization. Organizational responsibility for the
establishment and execution of QA is required. The authority and duties
of persons and organizations performing quality implementation and
assurance functions shall be clearly established and delineated. QA
requires management measures which provide for checking, auditing or
otherwise verifying that procedural controls are defined and implemented,
independent of the individual or group directly responsible for performing
the specific activity.
III-18 DOE 4700.1
3-6-87
b. Quality Assurance Plan. The QA plan documents policies, procedures, and
instructions which should be used throughout the life of any specific
activity. Test procedures shall be incorporated into the QA plan by
reference and shall take into account the need for surveillance, special
controls, processes, test equipment, tools, and skills to attain the
required quality, as well as performance and the attendant need for verif-
ication. The plan shall provide for indoctrination and training of per-
sonnel performing activities effecting quality to ensure that suitable
proficiency is achieved and maintained.
c. Design Control. Design controls should be established to enable designs
to be correctly translated into specifications, drawings, procedures, and
instructions. The measures for accomplishing these translations and the
attendant design reviews and provisions for independent assessment inputs
should be addressed. Design change control, including field changes,
should be subject to design control measures commensurate with those
applied to the original design, and should be approved by the organization
that performed the original design.
Section 105
d. Procurement Control. Measures should be established to assure that design
bases and applicable regulatory requirements, which are necessary to
assure adequate quality, are suitably included or referenced in the docu-
ments for procurements of material, equipment, and services. To the
extent necessary, procurement documents should require contractors and
subcontractors to provide a QA program and implementation plan.
e. Instructions, Procedures, and Drawings. Activities affecting quality
should be prescribed by documented instructions, procedures, or drawings
which include quantitative or qualitative acceptance criteria that can be
used to determine whether activities have been satisfactorily
accomplished.
f. Document Control. Document control is a means by which all program docu-
mentation can be controlled, tracked, and updated in a timely manner to
ensure that applicability and correctness shall be established. The
control measures, which should be initiated and followed, should assure
that such documents are reviewed for adequacy, approved for release by
authorized personnel, and are distributed to and used at the location of
the prescribed activity.
g. Control of Purchased Material, Equipment, and Services. Measures should
be established to assure that purchased material, equipment, and services,
whether purchased directly or through contractors and subcontractors, con-
form to the procurement documents. These measures should include provi-
sions, as appropriate, for source evaluation and selection, objective
evidence of quality furnished by the contractor or subcontractor, inspec-
tion at the contractor or subcontractor source, and examination of prod-
ucts upon delivery. Documentary evidence that material and equipment
conform to the procurement requirements should be available at the—
III-19DOE 4700.1
3-6-87
facility site prior to installation or use of such material and equipment.
This documentary evidence should be retained, be available for inspection
(as required), and should be sufficient to identify Conformance of
material or equipment to the specific requirements, such as codes, stan-
dards, or specifications.
h. Identification, Control, and Traceability of Materials, Parts, and
Components. This step addresses a configuration control system which
should enable identification, control, and traceability of all materials,
parts, and components in the system throughout all phases of construction
and use. Supportive procedures are necessary for activities such as
management approved control, coding, provisions for updating and changes,
and the presentation format for systematized configuration control.
i. Control of Special Processes. Measures should be established to assure
that special processes are controlled in accordance with applicable codes,
standards, and specifications, and are performed by qualified personnel.
Where processes are to be controlled, the appropriate control measures and
procedures should be defined and the applicable codes, standards, specifi-
cations, and personnel qualifications criteria should be identified.
Section 106
j. Inspection. Inspection methods of activities affecting quality should be
established and executed by or for the organization performing the acti-
vity. The inspection should validate conformance with the prescribed
documented instructions, procedures, and drawings. Examinations, measure-
ments, or tests of material or products processed should be performed for
each work operation, where necessary, to assure quality. If inspection of
processed material or products is impossible or not advantageous, indirect
control by monitoring processing methods, equipment, and personnel should
be provided. Both inspection and process monitoring should be provided
when control is inadequate without both. If mandatory inspection points
which require witnessing or inspection by the contractor’s designated
representative, and if work cannot not proceed beyond these points without
the consent of its designated representative, the specific points should
be indicated in appropriate documents.
k. Test Control. A test program should be established to assure that all
testing required to demonstrate that structures, systems, and components
will perform satisfactorily in service, is identified and performed in
accordance with written test procedures which incorporate the requirements
and acceptance limits contained in applicable design documents. The test
program should include, as appropriate, proof tests prior to installation,
preoperational tests, and operational tests during facility operation of
structures, systems, and components. Test procedures should include pro-
visions for assuring that all prerequisites for the given test have been
met, that adequate test instrumentation is available and used, and that
each test is performed under suitable environmental conditions. Test
results should be documented and evaluated to assure that test require-
ments have been satisfied.
III-20 DOE 4700.1
3-6-87
l. Calibration and Control of Test and Measurement Equipment. Standards
should be established to assure that tools, gauges, instruments and other
testing and measuring devices used in activities affecting quality are
properly controlled, calibrated, and adjusted at specified periods to
maintain accuracy within necessary limits. Records of calibration, main-
tenance, and other control activities must be maintained.
m. Handling, Storage, Shipping, and Preservation. The inherent quality of
the design shall not be degraded by lack of attention to these activities.
When necessary, special protective environments such as inert gas atmos-
phere, specific moisture content levels, and temperature levels shall be
specified and provided.
n. Inspection, Test, and Operating Status. Measures should be established to
indicate, by the use of markings such as stamps, tags, labels, routing
cards, or other suitable means, the status of inspection and tests per-
formed upon individual items of the facility. These measures should pro-
vide for the identification of items which have satisfactorily passed
required inspections and tests where necessary, to preclude inadvertent
bypassing of such inspections and tests. Measures also should be
established for indicating the operating status of structures, systems,
and components of the facility, (e.g., by tagging valves and switches) to
prevent inadvertent operation.
Section 107
o. Nonconforming Material, Parts, or Components. Controls should be imple-
mented for materials, parts, or components which do not conform to
requirements in order to prevent their inadvertent use or installation.
These measures should include, as appropriate, procedures for iden-
tification, documentation, and notification to affected organizations.
Nonconforming items should be reviewed and accepted, rejected, repaired,
or reworked in accordance with documented procedures.
p. Corrective Action. Measures should be established to assure that con-
ditions adverse to quality, such as failures, malfunctions, deficiencies,
deviations, defective material or equipment, and nonconformances are
promptly identified and corrected. In the case of significant conditions
adverse to quality, the measures should assure that the cause of the con-
dition is determined and corrective action taken to preclude repetition.
The identification of the significant condition adverse to quality, the
cause of the condition, and the corrective action taken should be docu-
mented and reported to appropriate levels of management.
q. Quality Assurance Records. Sufficient records should be maintained to
furnish evidence of activities affecting quality. The records should
include at least the following: operating logs and the results of
reviews, inspections, tests, audits, monitoring of work performance, and
materials analyses. The records shall also include closely related data
such as qualifications of personnel, procedures, and equipment. Inspec-
tion and test records should, as a minimum, identify the inspector or data
recorder, the type of observation, the results, the acceptability, and the
DOE 4700.1 III-21 (and III-22)
3-6-87
action taken in connection with any deficiencies noted. Records should be
identifiable and retrievable. Requirements for record retention, such as
duration, location, and assigned responsibility shall be established.
r. Audits. A comprehensive system of planned and periodic audits should be
carried out to verify compliance with all aspects of the QA program and to
determine the effectiveness of the QA plan. The audits should be per-
formed in accordance with the written procedures or checklists by
appropriate trained personnel not having direct responsibilities in the
areas being audited. Audit results should be documented and reviewed by
management having responsibility in the area audited. Appropriate follow-
up action, including reaudit of deficient areas, should be taken.
DOE 4700.1 Chg 1
6-2-92
III-23
PART E - CONSTRUCTION MANAGEMENT
1. INTRODUCTION.
a. Most projects accomplished by the Department require the construction
of facilities as a part of the project. The activities normally
associated with construction execution are depicted in Figure III-1.
A detailed construction management plan may be required by the Program
Secretarial Officer prior to the start of the construction. This may
be included as an attachment to the project management plan.
Coordination with the managing field organization should be
established to determine the specifics of each construction activity.
b. Construction management includes implementing procedures and providing
guidance for project activities that occur during the execution phase
of a project. The execution phase begins upon completion of detailed
design and receipt of construction funds at the level responsible for
project management, and continues until the completion and closeout of
the construction effort.
Section 108
c. Since project management is the responsibility of the Head of the
Field Element, considerable latitude in the establishment of
procedures for execution of a project are left to the discretion of
the Head of the Field Element. Managers of the Field Elements
establish and update, as required, written procedures that their
organizations follow in fulfilling their construction project
responsibilities.
d. The specific activities and the sequence in which they occur vary
according to the project characteristics and category. The managing
field organization shall establish logic diagrams for each project and
include these logic diagrams in its project management plans.
2. CONSTRUCTION EXECUTION. Construction efforts execution procedures are in
Chapter V.
Vertical line denotes change
Figure Ill-1
Construction Project Execution
DOE 4700.1
3-6-87
III-25
PART F - PROJECT CONTROL
1. INTRODUCTION.
a. Reporting and performance measurement systems in project management are
used to effectively control project execution. Contractor compliance with
work breakdown structure, cost and schedule control, and performance
reporting provides the necessary assurance that the Department has the
basic data required for timely and meaningful management decisions.
b. These systems must produce standardized, timely, consistent, and accurate
data. The use of these data requires that the cited characteristics be
present. Specifically, these reporting and performance measurement data
are
(1)
(2)
(3)
(4)
(5)
used to:
Provide essential management information;
Meet the information needs of several organizations with minimum
reporting requirements;
Collect and integrate the minimum data required to manage and monitor
contractual agreements;
Support approvals which may be required for periodic disbursement of
funds pursuant to provisions of contractual agreements; and
Enable the detection of possible delays or excess costs early enough
to resolve the difficulties.
2. GENERAL DESCRIPTION OF THE UNIFORM REPORTING SYSTEM.
a. The Uniform Reporting System (URS) addresses the reporting requirements
for contracts, Federal assistance (grants and cooperative agreements), and
financial incentives (loans and loan agreements). In general, it is a
basic process by which reporting requirements are identified, requirements
are specified, and reports are provided. Although URS is built around a
common process, and some components are common to all contractual
agreement types, some remain unique to a specific type. Because of the
similarities, integration of the reporting systems into a single system
provides features of significant advantage both to DOE and to reporting
participants. Figure III-2 illustrates the major steps in the URS.
Figure III-3 illustrates the URS components.
b. Just as the Head of the Field Element, the program manager, and the
Assistant Secretary use project reporting (see Chapter IV) to assess proj-
ect progress during execution, the project manager uses the URS reports to
assess the participant’s progress. The cost, schedule, and technical
report data are measured against original baselines to determine variance
and assess percent completion.
III-26 DOE 4700.1
3-6-87
Uniform
Figure III-3
Reporting System Process
DOE 4700.1 III-27
3-6-87
3. SELECTION OF PLANS AND REPORTS.
Section 109
a. It is important to select the plans and reports for each project which
will provide proper visibility of project status during execution. This
selection requires a knowledge of the project objectives, baselines to be
tracked, total estimated cost of the project, and the type of contract or
Federal assistance involved. With this information in hand, a reasonable
selection of plans and reports can be made. A further determination of
how plan and report data is to be displayed shall also be made. Figure
III-4 lists the forms available in URS.
b. Once a decision is made as to which plans and reports are required for the
project, this information should be transferred to a Reporting Require-
ments Checklist (Figure III-5). The checklist which becomes part of the
solicitation document, and, ultimately, the contract or agreement,
provides these specifics:
(1) Selection of reports;
(2) Frequency of reports;
(3) Distribution of reports (name/title and address);
(4) Number of copies to be submitted; and
(5) Identification of attachments.
c. The project manager should be aware of the information needs of Other
Departmental Elements and shall make arrangements for them to receive the
necessary reports in the required quantity. Organizations designated to
receive reports shall be so advised. DOE 1332.1 includes complete
details on the specific distribution of reports.
4. SPECIAL REQUIREMENTS.
a. Multi-Participant Projects. On occasion, it will be necessary to sum-
marize information from several contractual agreements into a single
report for an overview of the project. A project involving construction
is an example of such an occasion. In this instance, the system shall
feed report information to the project manager or the integrating contrac-
tor to meet DOE reporting requirements. Pagination and title page
requirements shall be adjusted to reflect the single document nature of
this type of submittal.
b. Second Tier Participants. In some instances, DOE may require reporting on
work that is subcontracted, in which case the prime contractor may
require detailed reporting by the subcontractor.
III-28 DOE 4700.1
3-6-87
TYPE OF CONTRACTUAL AGREEMENT
REPORT
CATEGORY/Name
CONTRACT INTER
AGENCY
AGREE-
MENT
FI
Loan
Guarantee
Loan
Firm
Fixed
Price
Form
Number
Cost
Type
A. GENERAL MANAGEMENT
Management Plan N/A
1332.1
N/A
1332.3
1332.4
1332.5
1332.6
1332.7
1332.3
1332.8
1332.9
x x
x
x
x
x
x
x
x
x
x
x
x
Summary Report
Status Report
B. SCHEDULE/LABOR/COST
x
xMilestone
Schedule/Plan
x x x x
Labor Plan x
xCost of Money
Factors
Excluded by
DefinitionContract Cost
of Money
x
x
x
x
x
x
Cost Plan x
x
x
x
C.
x
x
x
x
x
x
x
x
Milestone
Schedule/Report
x
Labor Management
Report
x
xCost Management
Report
x
EXCEPTION REPORTS
Conference Reports
Hot Line Record
N/A
N/A
N/A
1332.10
1332.11
x
x
x
x
x
x
D. PERFORMANCE MEASUREMENT
Management Control
System Description
x Excluded
by
Definition
x
x
x
WBS Dictionary
Index
Elem. Def.
x
x
Figure III-4
Forms Included in Uniform Reporting System
DOE 4700.1
3-6-87
III-29
TYPE OF CONTRACTUAL AGREEMENT
REPORT
CATEGORY/Name
CONTRACT INTER
AGENCY
AGREE-
MENT
FI
Firm
Fixed
Price
Form
Number
Cost
Type
Loan Loan
Guarantee
Cost Performance
Report
Form 1-WBS
Form 2-Function
Form 3-Baseline
1332.12
1332.13
1332.14
x
x
x
x
x
x
x
x
x
E. FINANCIAL INCENTIVES
Statements of
Income and Expense
Balance Sheet
Cash Flow Statement
Section 110
Statement of Changes
in Financial
Position
Loan Drawdown Report
Operating Budget
Supplementary
Information
N/A
N/A
N/A
N/A
N/A
N/A
N/A
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
Excluded by
Definition
x
x
x
F. TECHNICAL
Notice of Energy
RD&D Project
Technical Progress
Report
Draft for Review
Final App. Report
Topical Report
Final Technical
Report
Draft for Review
Final App. Report
DOE 538
N/A
N/A
N/A
N/A
N/A
x x x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
Figure III-4
III-30 DOE 4700.1
3-6-87
Figure III-5
Example of DOE F l332.l, Reporting Requirements Checklist
DOE 4700.1
3-6-87
III-31
c. Integrated Contractors. Integrated contractors who use the work package
authorization system (WPAS) are required also to use URS reports. It
shall be explained clearly to these contractors that individual efforts
must be identified and baselined for reporting purposes.
5. THE MANAGEMENT PLAN.
a.
b.
c.
The management plan is the key contractor input to URS. The management
plan describes how to produce the products identified in the contractual
agreement, and names the management control systems to be used to manage
that performance. It is required as part of the proposal and after nego-
tiations become a binding part of the contractual agreement. Figure III-6
is an outline of a typical management plan.
The management plan should reflect how the contractor(s) plans to execute
the project. The DOE project management plan should also reflect the same
basic data. These two documents should contain the contract baselines
against which future reports will be measured.
Separate from the management plan, but included with it, are the milestone
schedule plan and the cost plan. These two plans detail the schedule and
cost aspects
an extension
generated by
6. STATUS REPORTS.
completed by the
of the project as viewed by the participant. The plans are
of the summary WBS, the schedule, and the cost estimate
DOE.
The project status reports which periodically might be
participant include:
a.
b.
c.
d.
e.
f.
g.
Participant status report;
Milestone schedule status report;
Labor management report;
Cost management report;
Conference record;
Hotline report; and
Technical reports.
7. PERFORMANCE MEASUREMENT.
a. The importance, complexity, and cost of many DOE projects require the use
of performance measurement techniques that promote highly effective
planning, managing, and control. The Department uses the cost and sched-
ule control systems criteria for this purpose. It has the following
characteristics:
III-32 DOE 4700.1
3-6-87
Figure III-6
Management Plan Outline
MANAGEMENT PLAN
EXECUTIVE SUMMARY
I. INTRODUCTION/BACKGROUND
II. EXPECTED RESULT OF EFFORT
A. Technical
B. Schedule
C. Cost
D. Financial
III. MANAGEMENT CONTROL SYSTEMS DESCRIPTION
(Cost and Schedule Performance Measurement)
A. General
B. Organization
C. Planning and Budgeting
D. Accounting
E. Analysis
F. Revisions and Data Access
IV. TECHNICAL SYSTEMS AND CONTROLS DESCRIPTION
A. Systems Engineering
B. Configuration Management
C. Quality Engineering
D. Safety Engineering
E. Environmental Engineering
F. Data Processing
G. Other
V. ADMINISTRATIVE SYSTEMS AND CONTROL DESCRIPTION
A. Security E. Procurement
B. Health and Safety F. Data Processing
C. Personnel G. Property Management
D. Legal H. Other
VI. FINANCIAL SYSTEMS AND CONTROL DESCRIPTION
A. Income G. Payables
B. Expense H. Other Current Liabilities
C. Cash I. Long Term Liabilities
D. Inventory J. Equity
E. Receivables K. Other
F. Fixed Assets
Section 111
ANNEXES
DOE 4700.1 III-33
3-6-87
(1) Sets forth the capabilities required of a contractor’s cost and
schedule control system;
(2) Requires the integration of work organization, planning and
budgeting, accounting, analysis, and change incorporation; and
(3) Requires that baselines be established and maintained for purposes of
performance measurement and that such measurement be on the basis of
earned value.
b. DOE does not impose any specific systems on the contractor, as these ele-
ments are normally inherent in the contractor’s management control
systems. The contractor is allowed maximum flexibility in determining how
internal operations are to be conducted as long as the internal management
control systems satisfy the needs of both the contractor and the Depart-
ment for contract performance information.
c. As can be seen in Figure III-7, compliance with the Cost and Schedule
Control Systems Criteria (CSCSC) is integral to proper contractor direc-
tion and performance measurement. These criteria are delineated in
Attachment III-7. They do not prescribe specific methods or procedures;
rather, contractors can define work, organize, and use procedures best
suited to their needs, environment, and management philosophy, subject
only to meeting the criteria. They are intended to ensure that contrac-
tors submit valid and uniform performance reports which permit data analy-
sis to be performed by both the contractor and DOE using a common data
base and common analytical methods.
d. Complete discussions of CSCSC application can be found in DOE/CR-2250.1B,
DOE/CR-0015, DOE/CR-0017, and DOE/CR-0047.
8. APPLICATION OF REQUIREMENTS.
a. Departmental policy requires that the CSCSC approach (full or modified) be
implemented contractually on all new major system acquisitions, major
projects and other projects as program Secretarial Officers may elect.
The approach is sufficiently general in nature to permit its use by
research, development, demonstration, construction, or production
projects.
b. Each contract is individually evaluated, taking into consideration the
following guidelines:
(1) Estimated cost of the contract (over $50 million--full implemen-
tation; $2 to $50 million--modified criteria implementation).
Figure III-7
DOE Management Functions/Contract Performance Measurement Interface
DOE 4700.1
3-6-87
III-35
(2) Contract duration (contracts with a duration of less than 1 year are
normally not considered for application).
(3) National urgency of the project.
(4) Special problem areas or high risk known or expected to exist during
the contract period.
(5) Recommendations by appropriate DOE management (program Office
Director, program Secretarial Officers).
(6) Type of contract (firm-fixed price or fixed price with escalation
contracts normally are not considered for criteria implementation).
c. Full Implementation. After the contractor demonstrates compliance with
the contractual requirements, a formal review report shall be prepared to
document in detail how the contractor’s management control systems comply.
Based on this report, DOE issues a certificate of validation and the
cognizant contracting officer officially notifies the contractor of the
validation. The contractor shall then be required to update systems docu-
mentation, as necessary, to maintain an accurate description of the
systems. Any changes are forwarded for review and approval by the DOE
project manager prior to incorporation. Upon contractor request, a
Memorandum of Understanding, referencing the validated systems, may be
issued relative to application of the systems to other DOE contracts. The
contractor may then respond to solicitations for potential contracts with
similar requirements by citing the Memorandum of Understanding in his
proposal.
Section 112
d. Modified Implementation. Unlike the full implementation, an acceptance in
a modified implementation is only for the specific contract and the
Memorandum of Understanding is not applicable. The contractor shall be
notified by letter through the routine contract administration process.
Any system operational changes require notification to the DOE project
manager.
9. COST AND SCHEDULE CONTROL SYSTEMS CRITERIA.
a. These criteria (Attachment III-7) serve as DOE standards in evaluating the
adequacy of a contractor’s management control systems. The criteria by
themselves do not represent a management system nor do they prescribe spe-
cific methods of organization or operation. Contractors may organize in
the manner best suited to their individual environments and management
philosophies and use the internal methods and procedures of their choice.
The criteria are grouped into the following five major categories:
III-36
(1)
(2)
(3)
(4)
(5)
DOE 4700.1
3-6-87
Organization. The organization criteria require that the contractor
provide for clear definition and subdivision of the overall contrac-
tual effort, including major subcontractors, within the contractor
work breakdown structure (CWBS). Integration of the CWBS with the
organizational structure is required in order to provide for assign-
ment of responsibility of identified work tasks and to facilitate
performance measurement. Additionally, integration of the planning,
scheduling, budgeting, estimating, work authorizing, and data accumu-
lating systems is required to ensure an effective operational system.
Planning and Budgeting. All the contractually authorized work shall
be planned, scheduled, budgeted, and authorized by the contractor.
Although no specific scheduling techniques are required by the cri-
teria, all authorized work shall be formally scheduled in a manner
which shall permit the evaluation of actual progress against contract
milestones, and the contract master schedule shall be clearly sup-
ported by lower-level schedules. Establishment of the contract per-
formance measurement baseline is based on scheduled cost accounts and
provides the key in properly planning and budgeting the contract
effort. Cost accounts, because of their importance, are further
discussed in paragraph 9b, below.
Accounting. The accounting criteria require that contract costs and
performance measurement data elements be accumulated and summarized
from the bottom up as directly as possible, without allocations. The
contractor’s system must be able to provide material price and usage
variances, cost accumulation for materials on a basis consistent
with the budgets, and full accountability for all contract materials
ordered, received and used. Indirect costs shall be controlled and
procedures are required for identifying management control of
overhead costs.
Analysis. Comparisons of actual versus planned performance are
required by the analysis criteria. Thresholds for variance analyses
are established to avoid excessive contractor effort in analyzing
every variance. Variances are examined in terms of increments or
aggregations of work which are large enough to produce significant
information. Estimates of contract costs, based on performance to
date and on estimates of future conditions shall be developed.
Section 113
Revisions and Access to Data. Contract changes authorized by DOE and
those due to contractor internal replanning and formal reprogramming
shall be incorporated in a timely manner. Particular emphasis shall
be placed on the need to retain a meaningful performance measurement
baseline. Requirements include reconciling original budgets to
current budgets and prohibiting retroactive changes to records. DOE
shall be allowed access to contractor data for systems evaluations
and surveillance.
DOE 4700.1
3-6-87
III-37
b. The Cost Account. The cost account is an inherent and essential feature
of the CSCSC approach. It is the main action point for assignment of
internal management responsibility and planning and control of contractual
effort. In full CSCSC implementations, the cost account is composed of
work packages (i.e., detailed short-span jobs).
10. CONTRACTOR REPORTING.
a.
b.
c.
DOE Information Requirements. A group of related reports are used in con-
junction with contract performance measurement to satisfy Departmental
information requirements. The contents of the reports are obtained from
the same data base that supports day-to-day contractor management and that
provides the means of reporting summary level cost, schedule, and funding
data to DOE. These reports also serve as a basis for project status
reporting to upper DOE management.
Performance Measurement Data Elements. For performance measurement pur-
poses, a unique set of data elements is generated for the contractor’s
internal use in managing and reporting to DOE. Figure III-8 lists the
data elements for earned value reporting. Figure III-9 provides a graphic
representation of their relationship. Actual cost of work performed
(ACWP) consists of the direct and indirect costs applicable to the work
which has been performed. The budgeted cost for work scheduled (BCWS) is
the time-phased budget plan (baseline) which represents the contract work
plan. The budgeted cost for work performed (BCWP), the “earned value” or
the “planned value of work accomplished,” represents the value of work
completed. A comparison of BCWS and BCWP indicates whether more or less
work was done than was scheduled to be done. The difference represents
the schedule variance in terms of dollars. Comparing BCWP with ACWP
results in a cost variance that indicates whether the work that was
actually performed cost more or less than it was planned to cost. Anal-
yses of cost and schedule variances enable the contractors to identify
problems, to determine reasons for deviations from plans, to take correc-
tive actions, and to report the results. Based on performance to date and
estimates of future conditions, an estimated cost at completion (EAC) is
computed and compared to the total BCWS or budget at completion (BAC). At
the contract level, total budget is usually equal to the contract value;
therefore, the difference between BAC and the EAC forecasts a contract
overrun or underrun.
Technical Achievement. A key to effective cost and schedule control is
correlation of technical achievement with accomplishment of the work
effort. If the project is properly defined, correlation of cost, sched-
ule, and technical performance is greatly simplified. Since unfavorable
cost or schedule variances are usually caused by technical difficulties,
the quantitative information in the contractor’s cost and schedule reports
shall be supplemented by narrative to explain the technical problem and
its impact.
III-38 DOE 4700.1
2-6-87
Section 114
ELEMENT DESCRIPTION CRITERIA TERM ACRONYM
WORK PLANNED BUDGETED COST FOR WORK SCHEDULED BCWS
WORK ACCOMPLISHED BUDGETED COST FOR WORK PERFORMED BCWP
(EARNED VALUE)
COST OF WORK ACCOMPLISHED ACTUAL COST OF WORK PERFORMED ACWP
WORK AUTHORIZED BUDGETED COST AT COMPLETION BAC
ESTIMATE OF FINAL CONTRACT ESTIMATED COST AT COMPLETION EAC
COST (LATEST REVISED ESTIMATE)
COST DIFFERENCE COST VARIANCE (BCWP MINUS ACWP) CV
SCHEDULE DIFFERENCE SCHEDULE VARIANCE (BCWP MINUS BCWS) SV
COST AT COMPLETION AT COMPLETION VARIANCE (BAC MINUS EAC) ACV
DIFFERENCE
Figure III-8
Earned Value Data Elements
Figure III-9
Earned Value Data Elements Relationships
DOE 4700.1
3-6-87
III-39 (and III-40)
d. Data Analysis. Performance measurement data analysis is a dual responsi-
bility of the contractor and DOE. The contractor performs this function
for internal management needs and for preparation of the external reports
to DOE. Contract data analysis is initiated at the cost account level by
the appropriate manager. Cost, schedule, and at-completion variances that
exceed established thresholds require review and analysis to determine the
cause, to evaluate options to resolve the situation, and to report actions
to higher-level management. The contractor-furnished performance reports
fulfill this need. They present systematically summarized information in
a manner designed to assist overall assessment of contract status. These
reports may require additional processing by DOE project personnel to
facilitate their use and understanding and to extract their full benefit.
The use of various analytical techniques will assist both the contractor
and DOE in:
(1) Determining the current contract cost and schedule performance sta-
tus;
(2) Highlighting areas requiring more detailed data;
(3) Identifying deviations and trends; and
(4) Forecasting, verifying, or questioning future work status.
The proper collection, analysis, and use of contract performance data are
major ingredients in successful performance measurement. The importance
of making effective use of the data by the contractor and DOE cannot be.
overemphasized.
.
DOE 4700.1
3-6-87
III-41 (and III-42)
PART G - PROJECT TERMINATION
1. INTRODUCTION. Project termination is similar to project transition with the
exception that termination may happen relatively quickly with little planning
having been done. While significant effort goes into properly planning and
effectively executing a project, it sometimes happens that a project must be
stopped abruptly.
2. PROJECT TERMINATION.
a. The issue of project personnel is forced upon the project manager, and
must be dealt with in as enlightened and expeditious a manner as is
possible. There is no plan that can be prepared beforehand, but
reasonable actions on management’s part can alleviate the difficulties.
b. Of major significance to a project termination is disposition of the
unfinished facility or hardware. While there is no set policy for dealing
with disposition, it is almost always better for the Department if the
project products can be disposed of to the contractor(s) involved. Even
if sold at a loss, the situation may be better than future storage, main-
tenance, or non-usage costs. The project manager and the program manager
shall determine disposition as early as possible, once termination is
imminent.
Section 115
c. Equally significant is the cost of termination to DOE. These costs can b
impressive. All contracts and subcontracts shall be settled, and dispo-
sition--either mothballing, dismantling, or disposal--shall be paid for
before the project is closed. The project manager shall plan and budget
carefully to properly effect project termination.
3-6-87
DOE 4700.1 Attachment III-1
Page III-43
SYSTEMS ENGINEERING PROCESS (TYPICAL)
1. SYSTEMS ENGINEERING.
a.
b.
c.
Overview. Systems engineering encompasses management of the engineering
and technical effort required to transform the project objectives into an
operational system. It includes the engineering required to define the
system performance parameters and the configuration to best satisfy the
project objectives. It also includes the planning and control of tech-
nical tasks, integration of the engineering specialties, and the manage-
ment of a totally integrated design effort to meet cost, schedule, and
technical objectives of the system engineering process.
Iteration. The systems engineering process is an iterative one encom-
passing changes at any point in the process. Possible impacts of change
to the system should be analyzed during the conduct of the project. These
impacts should be examined for validity, consistency, desirability, and
attainability with respect to current technology, physical resources,
human performance capabilities, life cycle costs, and other constraints.
The output of this analysis should either verify the existing requirements
or lead to the development of new requirements which are more appropriate
for the mission.
Process Flow. There are seven steps in the systems engineering process as
advocated by DOE (see Figure III-10):
(1) Mission Need, Project Objections, and Constraints. Prepared by DOE,
these broad requirements provide the basis for the systems engi-
neering process. All subsequent design and development is traceable
to, and is conducted for, the purpose of satisfying these top level
requirements.
(2) Function Analysis consists of the three interrelated activities
described below:
(a) Functional Identification. Analysis of system objectives to
identify functions and subfunctions that should be performed to
satisfy the system performance and design parameters.
(b) Functional Performance Requirements Analysis. Development of
technical performance requirements for each function identified.
These requirements define the input and output functions in suf-
ficient detail for direct use as criteria for equipment design
and operation, personnel skill development, computer program-
ming, environmental, safety and health considerations, logistics
support, and so forth.
�
Systems Engineering Process
Figure III-10
DOE 4700.1
3-6-87
Attachment III-1
Page III-45
(c) Time Requirements Analysis. An analysis to determine an appro-
priate “time line” of functions of functional sequences in which
time is critical to mission success, safety, utilization of
resources, minimization of downtime and/or increasing
availability.
(3)
(4)
(5)
(6)
Functional Allocation. Each function and subfunction is allocated a
set of performance and design requirements. Derived requirements
should be stated in sufficient detail for allocation to facilities,
hardware, software, personnel, and procedures. When necessary, spe-
cial skills or peculiar requirements are identified. Allocated
requirements should be traceable through the analysis by which they
were derived to the system requirement they are designed to fulfill.
Section 116
Design Synthesis and Integration. Design synthesis is the point in
the systems engineering process at which a design concept is created
to satisfy the stated requirements. All system elements should be
considered in arriving at a design concept. Requirements that have
been allocated analytically are satisfied through design synthesis.
The resulting component and subassembly level details are then
integrated into a consolidated overall design. Sufficient prelimi-
nary design is then accomplished to confirm and ensure completeness
of the performance and design requirements allocated for detail
design. Reallocation of requirements may be required.
System Definition. The performance, configuration, and arrangement
of a chosen system and its elements are portrayed in suitable forms
which may include schematic diagrams, physical and mathematical
models, computer simulations, layouts, detailed drawings, and similar
engineering graphics. These portrayals illustrate system and item
interfaces, permit traceability between the elements at various
levels of system detail, and provide means for complete and compre-
hensive change control. The specifications for test, support, and
operation are similarly documented in plans and manuals as appro-
priate. The system engineering process generates system and item
configuration specifications for project-peculiar items in accordance
with DOE configuration management guidance.
Evaluation and Optimization.
(a) Desirable and practical tradeoffs among stated operational
needs, engineering design, project schedule and budget, produc-
ibility, constructability, supportability, affordability, and
life cycle costs, as appropriate, should be continually iden-
tified and evaluated. Tradeoff studies should be accomplished
at the various levels of functional or system detail or as spe-
cifically designated and approved by the project manager to sup-
port the decision needs.
Attachment III-1
Page III-46
DOE 4700.1
3-6-87
(b) The following evaluation and optimization techniques should be
performed:
1 Tradeoff Studies. Appropriate tradeoff studies should be
conducted to postulate design alternatives to satisfy the
functional performance requirements allocated. Tradeoff stu-
ies should consider all factors bearing significantly on
operational and logistical support functions of the system.
2 Cost/Effectiveness Analysis. A continuing system cost effec-
tiveness analysis should be conducted to ensure that engi-
neering decisions resulting from the review of alternatives
are made only after considering their impact on system effec-
tiveness and cost of acquisition and ownership, including
operations, maintenance, and disposition. Alternatives which
would provide system effectiveness or costs significantly
different from those based upon contract requirements should
be identified. System effectiveness models should be
approved by the project manager for development and use if
they contribute to the decision process. The models facili-
tate sensitivity analysis by allowing the input parameters to
be varied individually so that their relative effect on total
system performance and life cycle cost can be determined.
Parameters in the effectiveness models relate to parameters
expressed in the performance characteristics allocated to
system functions. The modeling and analysis of life cycle
costs should be updated periodically to identify the cost of
acquisition and ownership.
Section 117
3 Support Analysis. Analyses should be conducted to define
logistics support needs (e.g., maintenance, transportation
and handling equipment, spares, repair parts, personnel,
technical orders, manuals). These analyses address all
levels of operations and maintenance and result in iden-
tification of system support requirements for full operation
following key decision 4, production/operations.
4 Risk Analysis. A continuing analysis should be conducted of
the risks associated with the related cost, schedule, and
technical baseline as design progresses. This analysis
should identify critical areas and investigate methods for
minimizing risk, including prototypes, testing, and backup
development. The analysis should also identify test require-
ments, technical performance measurement parameters, and
critical milestones.
DOE 4700.1
3-6-87
(7)
Attachment III-1
Page III-47
Buildin g, Testing, and Demonstration of System. The system should be
fabricated, assembled, and constructed in accordance with the
detailed design. The objectives, scope, and type of system testing
should be products of the engineering effort wherein all engineering
specialties are integrated to define an effective and economical
total system test effort. Whenever practicable, tests for different
objectives should be combined. Test data that are used for technical
performance measurement analysis should be identified and integrated
with system test planning for maximum utility in updating and veri-
fying the technical parameters being tracked. Verification of the
acceptability and compatibility of human performance requirements,
personnel selection, training, and man-machine interfaces are also
integrated into the system test effort. Following system test, the
system should be demonstrated in accordance with the approved
demonstration plan.
2. TECHNICAL REVIEWS.
a. A series of technical reviews are conducted jointly by the Department and
other project participants to assess the degree of completion of technical
efforts related to technical baseline development. The number and type of
reviews are determined by the DOE project office. The following technical
reviews are normally utilized:
(1) System Requirements Review. This review is conducted to ascertain
progress in defining system functional requirements; and implementing
other engineering management activity.
(2) System (Conceptual) Design Review. This review is conducted to: (a)
evaluate the optimization, correlation, completeness, and risks asso-
ciated with the allocated technical requirements; (b) ensure a tech-
nical understanding among all participants on the updated or
completed system (or system segment) specifications, and other
systems definition effort, products and plans; and (c) summarily
assess the system engineering process which produced the allocated
technical requirements as well as the engineering planning for the
next phases of the effort.
(3) Preliminary Design (Title I) Review. This review is conducted in
order to: (a) evaluate the progress, technical adequacy, and risk
resolution (on a technical, cost, and schedule basis) of the selected
design approach; (b) determine its compatibility with performance and
engineering specialty
and (c) establish the
functional interfaces
nel, and procedures,
requirements of the development specification;
existence and compatibility of the physical and
among facilities, hardware, software, person-
Attachment III-1 DOE 4700.1
Page III-48 3-6-87
Section 118
(4) Definitive Design (Title II) Review. This review is conducted in
order to: (a) determine that the retail design satisfies the per-
formance and engineering specialty requirements of the development
specifications; (b) establish the detail design compatibility among
the items of equipment, facilities, computer programs, and personnel;
(c) assess productivity and risk areas (on a technical, cost, and
schedule basis); and (d) review the preliminary product
specifications.
b. Subcontractor/Vendor Reviews. The project manager is responsible for
ensuring that contracts require that technical efforts by any system sub-
contractor are reviewed. These reviews may be organized by the contractor
or the subcontractor, as mutually agreed. Government participation in
subcontractor/vendor reviews shall be as specified by the DOE project
office.
DOE 4700.1 Attachment III-2
3-6-87 Page III-49 (and III-50)
SYSTEMS ENGINEERING MANAGEMENT PLAN GUIDELINES
1. PROJECT LEVEL PLAN. As appropriate, the project office should prepare a
Systems Engineering Management Plan that describes how systems engineering
will be conducted and managed on the project. The Systems Engineering
Management Plan should include the following sections:
a. Technical Planning and Control section identifies organizational respon-
sibilities and authority for managing the systems engineering process,
including control of subcontracted engineering; levels of control estab-
lished for performance and design requirements and the control method to
be used; technical assurance methods; plans and schedules for design and
technical reviews; and control of documentation.
b. Systems Engineering Process section contains a detailed description of the
process to be used, including the specific tailoring of the process to the
requirements of the project and its contracts; the procedures to be used
to implement the process; in-house documentation; tradeoff study methodol-
ogy; the types of mathematical and/or simulated models to be used for
system and cost effectiveness evaluations, if applicable; and the genera-
tion of specifications.
c. Engineering Integration section describes the coordination of the engi-
neering specialties to achieve a best mix of the technical performance in
the contract, with the detailed specialty plans being summarized or
referenced, as appropriate. This portion of the plan depicts the integra-
tion of the specialty efforts and parameters into the system engineering
process and shows their consideration during each iteration of the proc-
ess. Where engineering specialties overlap, the responsibilities and
authorities of each are defined in this part.
2. CONTRACTOR/RECIPIENT/BENEFICIARY LEVEL PLAN. The project manager should
ensure that potential contractors, recipients of Federal assistance, or bene-
ficiaries of financial incentives submit Systems Engineering Management Plans,
in accordance with the above outline, in support of the project level System
Engineering Management Plan, and following DOE Uniform Reporting System
guidance. This contractor/recipient/beneficiary level Systems Engineering
Management Plan may be a component of, or subsidiary to, the contractor/
recipient/beneficiary project management plan.
DOE 4700.1
3-6-87
Attachment III-3
Page III-51
SUGGESTED OUTLINE FOR A TEST AND EVALUATION PLAN AND PROCEDURE
Section 119
1. TEST AND EVALUATION PLAN. Annex II to the project management plan is the test
and evaluation plan. This document should be detailed to the extent necessary
to show the rationale for the kind, amount, and schedules of the testing
planned for the project. It should relate the test and evaluation effort
clearly to the project’s technical risks, operational issues and concepts,
performance criteria, reliability, availability, maintainability, and acquisi-
tion phase key decisions. It explains the relationship of component, sub-
system, integrated system development tests, and initial operational tests
which when analyzed together provide confidence that the project is ready to
proceed to the next phase of the acquisition process.
a. The plan addresses the testing and evaluation to be performed in each
acquisition phase with the upcoming phase discussed in more detail. In
general, the plan should address critical tests and evaluations, and near-
term and long-term plans, by acquisition phase.
b. The plan should outline the test and evaluation management responsibili-
ties of participating organizations including independent testing and eval-
uation to be performed by another agency or Departmental elements. If
independent testing is not going to be performed, Justification shall be
provided. Highlight arrangements between participants for sharing test
data and responsibilities for test management decisions, and discuss the
adequacy of the planned test periods and schedule to provide confidence in
test results.
c. An integrated test and evaluation plan shall consider the following
phases:
(1) Summary Total Project Developmental Test Planning. On a summary
level milestone chart, display the integrated time sequencing of
developmental tests (sometimes known as research and development
tests) and evaluations for the project and the acquisition cycle key
decision points. Discuss developmental test and evaluation objec-
tives for the project in relation to the acquisition cycle key deci-
sion points. Relate the planned testing to the critical technical
issues appropriate to each phase. The near-term portion of the plan
contains the most detail; the long-term portions are as specific as
possible. Provide, as an attachment, a listing of the issued and
planned test procedures, indicating the level two, level three, and
selected high risk, lower level project summary,work breakdown struc-
ture elements to which they are applicable.
(2) Developmental Testing Conducted. Provide, by phase of the acquisi-
tion cycle, a summary of the developmental tests and evaluations
already conducted based on the best available information. Briefly
describe test articles. Emphasize events and results related to
Attachment III-3
Page III-52
DOE 4700.1
3-6-87
(3)
(4)
(5)
required performance characteristics, critical issues, and require-
ments from earlier management decisions. Highlight technical charac-
teristics or specification requirements that are to be demonstrated
or, from related projects or test programs, systems, subsystems, or
components which have failed to be demonstrated.
Section 120
Developmental Testing Remaining. Discuss remaining tests and eval-
uations planned for the life of the project beginning with the
current phase of the acquisition cycle. Address separately each
remaining phase, including the specific objectives to be addressed
during the phase. The objectives identified shall be the discrete
major goals of the effort, which, when achieved, shall provide solu-
tions to critical technical issues and demonstrate that the engi-
neering is progressing satisfactorily and the project is prepared to
proceed to the next acquisition phase. Summarize the key events
planned to address the objectives, so that the amount and thorough-
ness of testing are clearly apparent. Highlight those items, the
availability of which are critical to conducting adequate tests and
evaluations. If appropriate, display these items on the integrated
schedule.
Operational Test Planning. Discuss the operational tests and eval-
uations to be performed in the demonstration, and the production or
operation phases of the acquisition cycle intended to address opera-
tional effectiveness and identify deficiencies in the system. Relate
the test conditions and expected results to the operational effec-
tiveness and suitability of the systems being acquired.
Developmental and Operational Testing Resource Requirements.
Summarize the resources required that are unique to the project.
Identify, the actual number of articles and support elements of the
system required for testing in each phase. If subsystems are to be
tested individually, identify each subsystem and the quantity
required. Identify planned testing facilities and whether they are
Government or non-Government facilities.
2. AN INTEGRATED TEST AND EVALUATION PLAN shall consider the following:
a.
b.
c.
d.
Total Project Development Test Plan.
Operational Test Plan.
Test Resource Requirements.
Test Procedures:
(1) Identification of tests.
DOE 4700.1 Attachment III-3
3-6-87 Page III-53
(2) Preparation, approval, and issance of test procedures.
(3) Detailed scheduling.
(4) Review and analysis of test results.
e. Project Tests.
(1) Acceptance tests.
(a) Installation check.
(b) Strength and tightness.
(c) Operation.
(2) Alteration and repair tests.
(3) Special tests.
f. Test Documents.
(1) Test specifications.
(2) Test procedures.
(a) Preparation and approval.
(b) Distribution.
(c) Review.
(d) Changes.
g. Test Index.
h. Test Sequence.
i. Prerequisite Lists.
j. Test Instructions.
(1) Organization.
(2) Document control.
(3) Status reporting.
Attachment III-3
Page III-54
(4) Verification of testing.
(5) Signoff.
(6) Interruptions and incidents.
(7) Testing events.
(8) Monitoring records.
DOE 4700.1
3-6-87
3. PERFORMANCE OF TEST PROCEDURES. All operation of the plant and equipment is
to be performed in accordance with Departmental procedures in applicable com-
ponent technical manuals, and approved test documents. Test operating proce-
dures supplied by the plant contractor, which are approved by DOE, may specify
procedures which differ from those in applicable component technical manuals
for purposes of the test program.
DOE 4700.1
3-6-87
Attachment III-4
Page III-55
EXAMPLE OF A COMPREHENSIVE TEST PROGRAM
1. GENERAL.
a. Accomplishment of a project test program requires the following actions:
(1) Identification of necessary testing;
(2) Preparation, approval, and issuance of appropriate test procedures
and associated testing documents;
Section 121
(3) Detailed scheduling and performance of approved test procedures; and
(4) Review and analysis of results to verify acceptability.
b. The documents required to accomplish a project test program and the admin-
istrative processes associated with such documents are described in the
following paragraphs. Test specifications and procedures are required for
components, systems, and subsystems which are contract end items; will be
contractually identified; and will be referenced in the quality assurance
plan.
2. GENERAL DESCRIPTION OF PROJECT TEST PROGRAMS. Project test programs are nor-
mally of three types:
a. New Project Acceptance Tests. An extensive series of individual equip-
ment, plant, and integrated project tests required to establish that the
project is properly built and will perform as designed.
b. Alteration and Repair Acceptance Tests. Tests performed to establish the
acceptability of project equipment or systems which have been altered or
repaired.
Tests for purposes other than those listed above, such as
periodic maintenance tests or troubleshooting tests.
c. Special Tests.
3. TEST PROGRAM SEQUENCES. The paragraph defines the sequence of testing to be
used for the three basic types of project test programs described in paragraph
2 above.
a. New Project Acceptance Test Program. This test program is accomplished in
five phases. The sequence for accomplishing the new project acceptance
test program is keyed to five phases, each of which is discussed below:
Attachment III-4 DOE 4700.1
Page III-56 3-6-87
(1)
(2)
(3)
(4)
(5)
Installation Checks. This phase will include a visual inspection by
system of all components and equipment to assure that installation is
in accordance with design plans. Fluid systems will be checked for
proper arrangement, including locating and mounting of components,
hanging and anchoring of piping, alignment and bolting of machinery
locking devices, space envelopes required for maintenance, and the
accessibility of operating parts of the system. Instrumentation and
control systems will be checked for proper installation, including
grounding, connections, mechanical operability of components, and
proper wiring, including wrapping, servicing, sleeving, and marking.
Circuit continuity, wiring, insulation, and proper ventilation will
be checked, including heat dissipation features.
Flushing and Strength and Tightness Tests. Upon completion of the
point of construction at which filling can proceed, the fluid systems
are filled and flushed. The strength and tightness of fluid systems
are proven by hydrostatic testing. Appropriate piping systems are
fitted with filters that simulate the pressure drop and a test head
prior to filling, and instrumentation and control systems are cali-
brated. The calibration tests are conducted prior to, and concur-
rently with, strength and tightness tests sequenced to meet test
procedure requirements.
System Operation Testing with Minimum Parameters. Fluid systems are
operated at minimum parameters for operation of appropriate equipment
in order to assure, at the earliest possible date, that all com-
ponents are operable and ready for further testing. Instrumentation
and control testing proceed concurrently, sequenced to meet test pro-
cedure requirements.
Section 122
System Operation with Normal Parameters. When fluid systems have
been tested adequately to indicate that operating parameters can be
reached, the systems are tested at designated higher parameters.
Safety and protection devices are tested as parameters are increased.
When all testing designated for this period has been satisfactorily
completed, the designed parameters are reduced, the filters are
removed, and the entrapped contents are examined.
Operational Testing. Upon completion of all tests in the preceding
phases, the project is prepared for the initial operations with
designed fluids/solids. After operations testing is achieved, and as
the equipment is taken to operating conditions, the equipment is
tested through various operating levels up to 100 percent. Then the
project is tested over various expected specified transients. The
intent of this phase is to assure readiness for full operations.
DOE 4700.1
3-6-87
b.
c.
Attachment III-4
Page III-57
Alteration and Repair Acceptance Test Program. This test program consists
of only those tests required to establish the acceptability of project
equipment or systems which have been altered, repaired, opened, inspected,
disassembled, and so forth, during any upgrade period. The test program
is under the cognizance of a testing review board or equivalent group.
Special Test Programs. These consist of tests performed on a project for
purposes other than above, such as varying the output stream, shifting the
feedstock, or varying operating parameters for integration purposes.
4. TEST DOCUMENTS.
a. Test Specifications. Specifications will establish test requirements and
parameters for all levels of tests performed on major components, sub-
systems, or systems as applicable to ensure that essential design, inter-
face, and performance requirements are met. The specifications will be
developed as the system design evolves.
b. Test Procedures. Test procedures are the basic documents of the project
test program. They specify prerequisites, special equipment, precautions,
and the steps to be followed during conduct of the test. Approved written
test procedures are required for the performance of all project tests.
Test requirements specify the testing to be performed and are used to pre-
pare the detailed procedures for accomplishing testing.
(1) Preparation and Approval.
(a) New Project Acceptance Tests. Test requirements are provided to
the contractor as approved operating and acceptance test proce-
dures. These procedures are prepared by the contractor and
approved by DOE.
(b) Repair Tests. The contractor develops test procedures using
procedures or requirements contained in approved documents which
are applicable to the equipment being tested, such as component
technical manuals. Other test procedures and the project’s book
of completed test procedures may also be used if it can be
determined that these procedures fulfill the postrepair test
requirements specified in the component technical manuals. If
approved documents do not contain the procedures required or if
the contractor is uncertain as to which procedures in approved
documents to use, then the contractor submits recommended test
procedures or test requirements to DOE. In some cases a repair
test will consist merely of an operational check which does not
require a test procedure (e.g., an instrument alignment check or
an inspection of a mechanical joint for leakage at normal
operating pressure).
Attachment III-4
Page III-58
Section 123
DOE 4700.1
3-6-87
(c) Use of Manual Procedures in Conducting Evaluations. Where test
procedures to be issued by the contractor provide for perform-
ance of operations in accordance with the component technical
manual, the sections of the manual involved should be reproduced
verbatim by the contractor and attached to or integrated into
the test procedures, procedure changes, or procedures where the
signoff of steps is necessary to provide a record of completion
of testing. Although the contractor has the option of retyping
test procedures in order to integrate applicable steps from com-
ponent technical manuals into the portions of the basic test
procedure where they are to be performed, reproduction of these
manual sections where possible is the preferred method. If test
procedures are retyped, each addition to component technical
manual steps should be clearly marked as such and its source
identified. All reproductions or retyping of test procedures
should be accomplished prior to presentation to the members of
the testing review board.
1 If any caution statements in the plant or component technical
manual procedures to be reproduced require a specific action
to be performed, these cautions should be integrated into the
test procedures as a procedural step.
2 One copy of the test procedures, including reproduced pages
from the manual, should be designated the official record
copy for concurrence by the testing review board.
3 It is not intended to require that routine procedures in the
manuals concerned be reproduced and attached to, or integra-
ted into, each test procedure, provided that these manual
procedures can be followed in a step-by-step manner by a test
monitor without change. Where circumstances are such that
reproduction of sections of the manual involved is not prac-
ticable or desirable and applicable manual sections are
merely referenced, the contractor shall determine an alter-
nate method of maintaining an official status of accomplish-
ment of the procedure, such as through use of the test
monitor log. In any event, the contractor shall assure that
the sections of the manual involved are complete and compat-
ible for use by the test monitor in performing the procedure.
(d) Test Procedure Addenda. Test procedures may be supplemented by
test procedure addenda to specify such information as valve sta-
tus and details for flushing or hydrostatic testing. Local
addenda may also be issued by the contractor to incorporate
supplementary information from other approved documents. These
addenda become part of the applicable basic test procedures in a
DOE 4700.1
3-6-87
Attachment III-4
Page III-59
manner that does not require retyping the basic procedures.
Test procedure addenda are approved by the testing review board.
(2) Distribution.
(a) New Project Acceptance Test Procedures. New project acceptance
test procedures are endorsed and confirmed for performance on a
specific project by means of an endorsing and confirming record
which is prepared and approved as follows:
1 Prepared by the project contractor;
2 Endorsed by the field organization;
3 Confirmed by the Departmental representative at the facility;
and
4 Distributed by the project contractor to the project manager
and field organization.
Section 124
(b) New project reporting and acceptance test procedures, test pro-
cedure changes, and engineering change record sheets are distri-
buted by the plant contractor to all applicable activities.
Each contractor engaged in the construction plants receives a
reproducible master and a limited number of copies of each test
procedure; these are retained in a master file. When a contrac-
tor receives an engineering change record authorizing perform-
ance of a test on specific equipment being tested, the
contractor produces sufficient copies of the test procedure from
the appropriate master for testing review board review and sub-
sequent testing. The contractor is responsible for incor-
porating into the master test procedure all approved changes
which apply to the equipment being tested, including such local
changes as are approved by the testing review board.
(3) Review of Test Procedure Prior to Performance. Test procedures are
reviewed approximately 3 months, and again approximately 3 weeks,
prior to scheduling performance.
(a) Three-Month Review. A comprehensive technical review of all
operating and acceptance test procedures is conducted 3 months
prior to the scheduled performance date. This review by the
board serves the following functions:
1 Assures a mutual understanding of the document content;
2 Provides lead time for procurement of special test equipment
and instrumentation;
Attachment III-4
Page III-60
DOE 4700.1
3-6-87
3 Provides information necessary for detailed planning; and
4 Provides time for contractor/DOE resolution of comments
resulting from this review.
(b) The contractor may, on a case-by-case basis, delete the 3-month
review of operating and acceptance test procedures provided all
of the following conditions are met:
1
2
The procedure has been used successfully by the contractor in
prior test programs of the same equipment type;
The procedure will be extended to all equipment without
change in scope, intent, or method of performing the test;
Twelve months or less has elapsed between the previous per-3
4
formance of the procedure and the date the 3-month review
would be required;
The board must concur with deletion of the 3-month review
each specific procedure; and
The procedure for which a 3-month review will not be per-
formed should be identified in the project test index.
for
5
(c) Three-Week Review. A comprehensive technical review of all
operating and acceptance test procedures is conducted 3 weeks
prior to the scheduled performance date. This review by the
board serves the following functions:
1 Assures that planning for both personnel and equipment is
adequate for proper performance;
2 Assures that all sections of the procedure are applicable and
current;
3 Assures a formal status review of prerequisite lists;
4 Assures adequate resolution of comments from the board on the
procedure at the 3-month review;
5 Assures that special test equipment is available; and
6 Assures that all applicable documents are available.
(4) Distribution of Test Procedures. After the test procedure has been
reviewed and approved by the board, the contractor should formally
DOE 4700.1
3-6-87
Attachment III-4
Page III-61
(5)
distribute the procedure by memorandum. The distribution memorandum
should request written acknowledgement on one of its copies that the
procedure has been received by the project manager. In the case of
approved changes to procedures, this acknowledgement further signi-
fies that the approved changes will be incorporated into the proce-
dure prior to performance of the affected portions of the procedure.
An example of distribution and acknowledgment memorandums are includ-
ed in Figure III-11.
Section 125
Test Procedure Changes. Changes which unnecessarily increase the
scope of existing procedures, and which are not required for safe
operation or to correct errors, should not be submitted. Procedure
change requests must be submitted to the plant contractor, must
include the reason why the change is required, and must give a
technical evaluation showing why the change is satisfactory. The
contractor should obtain concurrence of the board in the need for a
change prior to submitting the change request for approval.
(a) Requests for Test Procedure Changes. Changes to test procedures
should be minimized. Changes should be requested only in cases
where:
1 The equipment cannot be operated safely using an existing
approved procedure;
2 A planned operation cannot be conducted because of an error
in the existing approved procedures; or
3 A change is required to be consistent with an approved system
or component change.
(b) Approval of Test Procedure Changes. Locally identified changes
required to test procedures which were provided or initially
approved by the DOE representative must be approved as follows:
1 Correction of obvious typographical and editorial errors,
addition of items to equipment lists, addition of local
quality control instructions, addition of local work codes,
practices, and safety precautions, addition of caution state-
ments as specific procedural steps when required, and dele-
tion of sections of procedures not applicable to a specific
project may be approved by the members of the board. These
local changes must be clearly marked as such.
Attachment III-4
Page III-62
XYZ CONTRACTOR COMPANY
From: XYZ Contractor Co. Chief Plant Test Engineer
DOE 4700.1
3-6-87
for ANR Project
To: Project Manager, ANR Project
Subj: ANR Project- Plant Test Procedure 782-3, Test Change Notice No. 2
1. The subject test procedure change has been approved by all members of the
testing review board for the ANR Project.
2. You are requested to acknowledge below on a copy of this memorandum that you
have received the subject test procedure change. This change will be incor-
porated into the contractor’s copy of the procedure prior to performance of
the affected portions of the procedure.
/s/ A. B. Jones
Enclose: (1) Test Change Notice No. 2 to Test Procedure 782-3
Copy to: DOE Program Office (w/encl)
DOE Operations Office (w/encl)
From: Project Manager, ANR Project
To: XYZ Contractor Co. Chief Plant Test Engineer for ANR Project
Subj: ANR Project - Test Procedure 782-3; Test Change Notice No. 2
Receipt of the subject test procedure change is hereby acknowledged. The
acknowledgment signifies that the change will be incorporated into the ANR
Project’s copy of the procedure prior to performance of the affected portions of
the procedure.
/s/ H. E. Smith
This example is for distribution of a procedure change. The same format
should be used for initial distribution of a procedure.
Figure III-11.
Example of Test Procedure Distribution Memorandums
DOE 4700.1
3-6-87 Attachment III-4
Page III-63
2 All other procedure changes must be submitted to the project
contractor for concurrence and to the DOE representative for
approval. In the case of the acceptance test program for a
new design project, DOE may designate other categories of
changes which may be approved locally by the board.
(c) Contractor Distribution of Test Procedure Changes. After a test
additional approved test procedure changes shall be issued
locally as follows:
Section 126
procedure has been approved for plant testing by the board,
1 After receipt, the contractor shall review the revision for
use in the specific test program. The contractor shall pre-
pare a change to a test procedure and obtain concurrence of
the members of the board in the proposed change.
2 Procedures need not be retyped when they are changed unless
it is essential to make them readable. However, changes to
procedures shall be issued as whole page changes.
3 A modification of test procedures shall be used to document
board concurrence with procedure changes. The modification
shall be issued by the contractor after being approved by the
board. The modification must be signed by the applicable
members of the board unless all of the following conditions
are met:
a It is identified and approved during the course of
testing;
b
c
Waiting for a board member signature will delay the
testing;
The change and any documents or procedures invoked in the
change by reference are presented to the board member ver-
batim; and
d The change is presented to the Departmental members of the
board by the contractor head engineer.
4 If all of the above conditions exist, the board member, after
concurring in the change orally, may authorize an individual
actually onsite to sign for him. Such onsite individuals
have no board authority on their own. There is no intent to
authorize delegation of group board responsibilities to such
individuals.
Attachment III-4
Page III-64
(6)
(7)
DOE 4700.1
3-6-87
5 Distribution of the procedure changes shall be effected in
accordance with Paragraph 4B(4) of this attachment.
Review of Completed Test Procedure. Following performance of test-
ing, the members of the board review and concur with the data for the
completed test and sign to the effect that the test has been satis-
factorily completed.
Book of Completed Test Procedures. The completed test procedures are
compiled into a book as specified for the project. Completed test
procedures and their supplements are distributed in accordance with
Departmental instructions for the project.
c. DOE Project Test Index. The text index is a summary of all project
testing to be performed during the construction period. For existing
projects, in addition to specifically identifying each test to be per-
formed, the index also identifies the reason for the test (acceptance
test, repair, and so forth) and the document used for the source of the
test requirement and/or procedure. For new construction projects, the
test index is prepared and approved as follows:
(1) Prepared by the contractor;
(2) Approved by the Department;
(3) Issued by the contractor in sufficient time to allow planning; and
(4) Changes to the test index approved by DOE and issued by the
contractor.
d. Project Test Sequence. The project test sequence consists of tests, or
parts of tests, and significant events for each plant arranged in order of
performance so that all prerequisites for testing are met and so that the
results will provide the data required to satisfactorily complete the test
program and the sequence required for project safety. The test sequence
is prepared and approved as follows. For all projects the test sequence
is prepared, reviewed, approved, and issued in the same manner as speci-
fied in subparagraph 4c above, for the test index, and
or subsequent to the test index.
e. Prerequisite Lists.
is submitted with
Section 127
(1) Key Events which Require Prerequisite Lists. For key events in a
test program, prerequisite lists are prepared which specify the
requirements to be satisfied in order to assure readiness and safety
to perform the event. Accomplishment of the items indicated in these
lists is considered to be the minimum required prior to the
DOE 4700.1
3-6-87
Attachment III-4
Page III-65
performance of the specified event. Additional requirements may be
incorporated into these lists. The following key events require
prerequisite lists:
(a) Initial individual component testing;
(b) System operations - minimum parameters;
(c) System operations - normal parameters;
(d) Initial operations testing; and
(e) Full operation.
(2) Administration of Prerequisite Lists. The procedures for admin-
istering prerequisite lists are as follows:
(a) Initial project individual component and initial operations
testing prerequisite lists.
1
2
3
4
Prepared by the contractor.
Approved by DOE.
Issued by the contractor.
Reviewed and approved for local use by the testing review
board; items added as considered necessary by testing review
board members.
Issued by the contractor.
Prior to individual component testing during installation of
the component, the contractor identifies, submits justifica-
tion for, obtains approval of the testing review board for,
and informs DOE of any Departmentally approved prerequisite
list items not to be completed prior to the event. Approval
of the testing review board constitutes approval to proceed
with individual component testing.
5
6
7 Prior to initial operations testing during project construc-
tion, the contractor identifies, submits justification for,
and obtains concurrence of the testing review board for, con-
currence of the project contractor, and approval of DOE for
all Departmentally approved prerequisite list items not to be
completed prior to the event. In addition, specific Depart-
mental approval is required prior to presenting to initial
operations offices.
Attachment III-4
Page III-66
DOE 4700.1
3-6-87
(b) All other prerequisite lists shall be:
1 Prepared by the contractor;
2 Approved by the testing review board; and
3 Issued by the contractor.
(c) Changes to DOE approved prerequisites are concurred in by the
project contractor and approved by DOE. Although not a man-
datory requirement, experience has shown that test time is kept
to a minimum and more management and supervisory attention is
directed to test operations if all test documents required for a
complete test sequence are issued and ready for use before the
sequence is allowed to commence.
f. Test Instructions. A set of test Instructions shall be prepared by the
contractor to establish the detailed procedures for administration, con-
trol, and performance of project equipment testing by the contractor. The
test instructions shall implement those requirements and additional local
requirements for the administration, control, and performance of project
testing, as required. The following is a minimum list of test instruc-
tions and the minimum requirements to be specified in each test instruc-
tion. Each contractor should have additional test instructions as
necessary to administer test programs in accordance with these
requirements.
(1) Responsibilities of the Test Organization and Other Contractor
Elements for Project Testing and Operations. This test instruction
shall cover the following:
Section 128
(a) Definition of the responsibilities of various contractor ele-
ments involved in a project test program and how their efforts
are coordinated. For example:
1 Functions, assignments, responsibilities, and qualifications
of personnel within the test organization. This should in-
clude the responsibilities of personnel designated to prepare
procedures in support of project testing and operations.
2 Responsibilities of production personnel such as managers,
supervisors, technicians or support personnel. It should be
made clear that functions and responsibilities such as
correction of system and component deficiencies, and test
equipment and contractor support system preparation, check-
out, hookup, and maintenance, should be carried out by pro-
duction personnel rather than test organization personnel.
DOE 4700.1
3-6-87
Attachment III-4
Page III-67
3
In this manner; test organization personnel
attention to the safe and proper conduct of
can devote full
plant testing and
operations rather than to production functions.
Responsibilities of support personnel such as quality engi-
neers, inspectors, and control monitors in conjunction with
plant test and operations.
(b) Designation of the boundaries between each project and other
systems and how such boundaries are maintained.
(c) Division of responsibilities between the testing organization
and procedures for transfer of control of project systems and
conditions for operational testing.
(d) Procedures for coordination of efforts between the test organi-
zation and contractor elements responsible for project safety.
(2) Test Document Administration and Control. Each contractor shall have
a test instructIon which implements these requirements for test docu-
ment administration and control.
(3) Performance of Plant Test and Operations. This test instruction
shall establish the following:
(a)
(b)
(c)
(d)
Control Locations for Testing. The test monitor shall be where
he can exert the proper control over testing being performed.
Communications. Requirements shall be established to assure
that formal, consistent, communication procedures are used in
accordance with standard practice for conduct of testing or
changing equipment conditions or system status.
Briefings and Dry Runs. Contractor shall designate tests or
test operations which require briefings and dry runs and
establish procedures for their conduct.
Location Assignment. Contractor test instructions shall iden-
tify testing and evolutions which require specific assignment of
locations for individuals in a test. These assignments provide
for the test monitor, operating personnel, data takers, and
observers for all locations to be present on each shift during
certain tests. The assignment specifies both contractor and DOE
project manager personnel by name. Location assignments are
required for the performance of major tests such as initial
individual component testing, initial operational testing, and
fuel operational testing.
Attachment III-4 DOE 4700.1
Page III-68 3-6-87
1 Location assignments are prepared by the contractor and
reviewed and approved by the members of the testing review
board. Approval of the location assignment by the members of
the testing review board does not constitute approval of the
qualifications of the personnel or of the specific individ-
uals listed in the location assignments.
2 The DOE project manager participates in the preparation of
location assignments for tests in which Departmental person-
Section 129
nel are involved.
3 The DOE project manager will supply the contractor with the
names and locations of Departmental personnel for inclusion
in the location assignments.
4 Approved location assignments shall be posted.
5 Deviations from approved location assignments are allowed
only with the approval of the members of the testing review
board.
(e) Operation of Components and Systems. This test instruction
shall establish how operational control systems or parts of
systems are transferred from the contractor to the operating
personnel and vice versa. This test instruction shall require
formal transfer of systems and shall designate contractor per-
sons authorized to operate systems or components where the
contractor has control of these systems or components. Minimum
qualification requirements for such contractor persons and a
list of qualified persons shall be established and maintained.
(4) Control of Project Conditions and System Status and Project Work.
This test instruction shall include:
(a) Procedures for formal control of:
1 Project conditions and systems status; as defined;
2 Initiation of project work, including repairs and modifica-
tions, in the project and project systems or structure which
could directly affect the project or the conduct of project
testing;
3 Connection of contractor support systems or test equipment
to, and disconnection from, the project; and
DOE 4700.1 Attachment III-4
3-6-87 Page III-69
(b) Definition of the role of test personnel in approval and signoff
of work permits and establishment of system status.
(5) Out-of-Service Procedures. Each contractor shall have a test
instruction governing out-of-service procedures which complies with
prudent safety requirements.
(6) Valve Lineup Procedures. Each contractor shall have a test instruc-
tion governing valve or switch status procedures.
(7) Verification and Signoff of Testing Steps. This test instruction
shall cover the following:
(a) When test or operating procedures require that an individual
sign for an action after verifying the action based on personal
observation, and certify by his signature that the action has
actually been performed in accordance with the specified
requirements, it is the responsibility of the contractor to sign
for the action unless the procedure specifies otherwise. This
responsibility cannot be assigned to another organization
without the approval of the DOE representative.
(b) Responsibilities for and manner of verification and signoff of
prerequisites, plant conditions, special precautions, test
preparations, procedural steps, and data sheets, including:
1 Initial performance of a procedure;
2 Periodic review of prerequisites, plant conditions, and spe-
cial precautions during an extended procedure;
3 Reverification and signoff required after interruption of a
test, including reverification of valve or switch status
affected by the test interruption;
4 Review of status at shift turnover;
5 Reverification and signoff when steps in a procedure must be
reperformed;
6 Verification and signoff for restoration of the plant; and
7 Manner in which inspections shall be performed and data
sheets shall be filled out.
Attachment III-4 DOE 4700.1
Page III-70 3-6-87
(8) Test Interruptions, Unusual Occurrences, and Incidents. Contractors
shall have a test instruction which establishes formal requirements
for handling interruptions, unusual occurrences, and incidents which
occur during plant testing. This test instruction shall include the
following details:
Section 130
(a)
(b)
(c)
(d)
(e)
(f)
What interruptions, unusual occurrences, and incidents require
reporting to higher authority, and to whom they should be
reported;
The procedure for a critique, including what occurrences require
critiques;
Requirements for casualty bills;
Written reports required to document occurrences;
Requirements to be satisfied before resuming testing, including
reverification of valve or switch status affected by the test
interruption; and
Method of voiding signed-off prerequisites, plant conditions,
procedural steps, and data sheets affected by the interruption
and manner of reverification and signoff of these items before
resuming testing.
(9) Testing Events Schedule.
(a) This schedule is a document issued daily by the contractor (or
less frequently as required), listing the following types of
items which are to be started or accomplished during the period
covered by the testing events schedule:
1 Authorized plant tests (including reference to the specific
procedure and revision thereof to be used).
2 Test briefings.
3 Installation of test equipment.
4 Project conditions in effect (may be by reference to appli-
cable project procedures in effect) and any changes in proj-
ect conditions to be accomplished (including reference to the
specific procedure and revision thereof to be used).
5 Training to be conducted, if any.
3-6-87
DOE 4700.1 Attachment III-4
Page III-71
6 Other test documents and functions, as necessary.
7 Project work including preventive maintenance, to be started
or accomplished during the period covered by the schedule
which requires changing project conditions or affects project
testing. Project work, including preventive maintenance,
which does not affect project conditions or project test per-
formance, need not be listed on the schedule and may be
accomplished at the discretion of the test monitor.
8 Nonproject work or testing which could affect project testing
during the period covered by the testing events schedule.
9 Other requirements which must be satisfied for testing or
changes in project conditions to proceed.
(b) The members of the testing review board should concur in the
testing events schedule. Work or testing not listed on the
testing events schedule plan should not be performed until a
formal change to the schedule has been issued. Changes should
be concurred in by the parties who signed the original testing
events schedule.
(c) It is not intended that the members of the testing review board
concur with the detailed scheduling of contractor production
work except to concur that work planned is compatible with proj-
ect testing or changes in project conditions to be performed.
The important function of the testing events schedule is to
assure that all work and testing or project operations planned
are formally identified ahead of time and determined to be com-
patible. In order to facilitate review and resolution of com-
ments or questions, the proposed schedule is normally provided
to members of the testing review board in advance of the testing
events schedule meeting.
(10) Test Monitor Record. This is the official record of the conduct of
testing and operation under the direction of a test monitor for the
project. All information pertinent to the testing and operation must
be entered into the record. This does not include data required to
be recorded in test procedures. The contractor shall issue a test
instruction describing the administrative requirements and controls
for the preparation and maintenance of the record. The instruction
should require that copies of the test monitor record be provided
daily to the DOE project manager. The test monitor record will note
the date of the start and completion of events, vital information
pertaining to performance, and any other pertinent information. The
Section 131
Attachment III-4
Page III-72
test monitor records will be
recordkeeping practice. The
formal and
test monitor
DOE 4700.1
3-6-87
will conform to standard
responsible for allis
entries and must sign and date the test monitor record at the end of
each shift. The record should identify holdups and delays in testing
and operations, plus giving the reason for such delays. Problems
identified during testing should be documented.
(11) Test Monitor Shift Turnover. This test instruction shall specify the
shift turnover requirements to be observed by test monitors during
the performance of project testing and other applicable operations.
The minimum requirements described below shall be included. Shift
turnover is an important evolution which must be performed in a
thorough, formal manner and must assure that necessary information is
transferred between shifts. The relieved test monitor must assure
that all pertinent information is given to the oncoming test monitor,
who must be satisfied that he or she fully understands the condition
of the project and the status of the test procedure in progress.
They may desire to utilize checklists for shift turnover. In addi-
tion, the contractor may develop a test procedure briefing book for
use by the test monitor prior to shift turnover. This book contains
information, such as expected results or test duration, which has
been gathered from the contractor’s past experience, and the
experience of other contractors in performing the test. Debriefings
after test performance should be used to keep the briefing book
current.
(a) Prior to shift turnover, a brief meeting of key oncoming test
personnel should be held to review the provisions of the test
events schedule, discuss the status of test progress, coordinate
planning for testing to be conducted during the next shift, and
review potential problems which could occur during the testing
planned and the corrective action which would be necessary. The
oncoming test monitor should direct the meeting after having ob-
tained necessary status information from the test monitor in
charge of the previous shift. The time and place for the
meeting and for shift turnover should be noted in the test
events schedule.
(b) Before commencing the shift turnover process, the oncoming and
offgoing test monitors must agree on a safe point in the test in
progress when shift turnover should take place and on the place
and manner for shift turnover. The offgoing test monitor should
assure that the project is in a safe, static condition before
the turnover commences. The oncoming test monitor should review
the test monitor record entries since his last shift before com-
mencing the turnover.
Attachment III-4
Page III-73
1
DOE 4700.1
3-6-87
(c) The following should be discussed between the oncoming and
offgoing test monitors prior to shift turnover:
2
3
4
(12)
(13)
(14)
(d)
(e)
Past shift progress and the status of completed and
uncompleted steps in the test procedure, including the speci-
fic point in the procedure from which the next shift should
proceed;
Project conditions and system status including replacement
inventories available;
The status of test equipment and contractor support systems
connected to the project; and
The status of out-of-service equipment and any switches in
cutout or abnormal position or electrical jumpers installed
and the reason for same.
Section 132
The oncoming test monitor shall make an inspection of the spaces
to observe the condition of vital systems, test equipment,
number of personnel in each area, availability of protective
gear, and so forth. During this tour, the test locations will be
observed to verify that each location is manned by a person ade-
quately briefed in the action expected of him or her. A com-
munications check should also be performed.
Relief of contractor personnel directly associated with project
testing may proceed when agreed to by the test monitors. When
turnover of information is complete, the oncoming test monitor
will formally accept responsibility from the offgoing test moni-
tor.
Performance of Installation Checks (Mechanical and Electrical). This
test instruction shall contain requirements for performing installa-
tion checks to verify that systems comply with applicable plans and
requirements.
Performance of Strength and Tightness Tests. This test instruction
shall contain the detailed requirements to perform hydrostatic
testing in accordance with applicable requirements. This test
instruction should include or refer to the procedure or means to
assure that all joints to be inspected during the hydrostatic test
are identified and can be located for ready viewing once the
hydrostatic test commences.
Operational Checks. This test instruction shall contain requirements
governing operational checks which do not require a test procedure.
As a minimum it shall:
Attachment III-4 DOE 4700.1
Page III-74 3-6-87
(a) Define the scope of such checks. Operational checks not
requiring a test procedure are limited to those which meet all
of the following conditions:
1 The check is simple and can be performed verbatim directly
2
3
(15)
(16)
from the applicable component technical manual without
changes or additional operating instructions.
The check does not require operation of the equipment outside
of normal operating limits.
The check does not involve any deviations from specification
requirements.
(b) Establish responsibilities and procedures for identifying each
operational check required, for assuring it is performed when
required and for reviewing and accepting the results.
(c) Establish responsibilities for performing the operational checks
and for documenting their performance.
Preventive Maintenance During a New Project Test Program. This test
instructIon shall cover the following:
(a) Description of how preventive maintenance is to be scheduled and
accomplished during the test program prior to system turnover to
the operating personnel;
(b) Definition of responsibilities for scheduling and accomplishment
of preventive maintenance and recordkeeping subsequent to system
operational control transfer to the operating personnel and type
of agreement to be executed at system turnover;
(c) Designation of responsibilities for contractor review of preven-
tive maintenance results including alignment and calibration
data sheets;
(d) Actions to be taken by the contractor when
maintenance results are noted; and
(e) Preventive maintenance documentation to be
operating personnel.
improper preventive
turned over to
Responsibilities for Contractor Support Systems and Test Equipment.
Each contractor shall have a test instruction governing the respon-
sibilities for contractor support system and test equipment. As a
minimum this test instruction shall:
DOE 4700.1 Attachment III-4
3-6-87 Page III-75
Section 133
(a) Provide for control of contractor support systems and test
equipment.
(b) Establish procedures for assuring that contractor support
systems are properly identified and maintained in a state of
cleanliness.
(c) Establish procedures for assuring that required test equipment
is properly identified, stored, and maintained in a state of
cleanliness and readiness to support testing and identify
responsibilities for such equipment.
(d) Require that contractor support systems and test equipment
comply with all applicable requirements and define the respon-
sibilities for inspection prior to use. Require that periodic
audits be conducted to verify compliance with requirements and
identify responsibilities for assuring compliance.
(e) Require that responsibilities for operational control of con-
tractor support systems and test equipment be agreed to between
the contractor and the operations personnel for each
application.
(f) Identify who in the contractor’s organization is authorized to
operate contractor support systems and test equipment.
(g) Establish procedures for control of work on and maintenance of
contractor support systems and test equipment.
(h) Require that operating procedures be prepared for contractor
support systems where necessary.
(i) Require numbering of contractor support system valves and
switches in a consistent manner and require the use of these
valve and switch numbers where appropriate in test and project
conditions documents.
(j) Require specifying in appropriate test and project conditions
procedures those valves, switches, and breakers in contractor
support systems and test equipment which shall be the respon-
sibility of the operating personnel to operate and require those
valves, switches, and breakers to be so identified.
Attachment III-4
Page III-76
DOE 4700.1
3-6-87
(17) Administration of Test Instructions. Each contractor shall have a
test instruction which establishes a formal method of maintaining,
revising and disseminating test instructions. The application of the
test instructions to each specific plant shall be approved by the
testing review board. In addition, the board has the option to
request that they approve application of other test instructions,
which may be prepared to supplement the test instructions listed
above, prior to contractor application to specific equipment. Unless
a specific compelling reason overrides, this shall be carried out by
approval of a cover sheet implementing the identical words in effect
for previous similar equipment. A copy of all test instructions (or
equivalent documents) prepared, and changes thereto, should be pro-
vided to DOE for information. Test instructions shall not be used in
lieu of or to circumvent requirements of approved operating proce-
dures or technical manuals. Departmental approval must be obtained
for any deviations from applicable technical manuals, approved test
or operating procedures, or Departmental directives.
5. PERFORMANCE OF TEST PROCEDURES. All operation of the plant and equipment is
to be performed in accordance with Departmentally approved procedures in
applicable component technical manuals, and approved test documents. Test
operating procedures which are supplied by the plant contractor and approved
by DOE may specify procedures which differ from those in applicable component
technical manuals for purposes of the test program.
DOE 4700.1 Attachment III-5
3-6-87 Page III-77
SUGGESTED CONFIGURATION MANAGEMENT PLAN
Section 134
1. Each contractor should submit a Configuration Management Plan, describing how
it will manage and conduct the configuration management effort in response to
the requirements of a solicitation.
a. The offeror identifies in the plan, items proposed for inclusion in the
contract. Only those items which are basic to the satisfaction of project
objectives need to be placed on contract. The plan must be updated as
required pursuant to contract award.
b. Contractor procedures and other planning baselines need to be prepared in
sufficient detail to support Departmental requirements for visibility,
validation, and verification of the contractual items.
2. The contractor’s plan should conform to the outline below. Paragraphs listed
may be further subdivided.
Cover Sheet
Section 1 - Introduction
Table of Contents1.1
1.2 Special Material Features
1.3 Special Organizational Features
Section 2 - Organization
2.3 Policy Directives
2.1 Responsibilites
2.2 Structure
Section 3 - Technical Baseline Identification
3.1 Functional Requirements Baseline
3.2 Technical Requirements Baseline
3.3 Design Requirements Baseline
3.4 Product Configuration Baseline
Section 4 - Configuration Change Control
4.1 Procedures
4.2 Interface Control
Section 5 - Status Recording and Reporting
5.2 Data Bank Content
5.3 Reporting
5.4 Audits
5.1 Data Bank Establishment
Section 6 - Special Considerations
Attachment III-5
Page III-78
DOE 4700.1
3-6-87
3. The information described in the following paragraphs is required to be
included in each plan:
a.
b.
c.
d.
e.
f.
g.
Cover Sheet. The cover sheet shall provide the nomenclature of the system
or product, contractor, contract number, and date of issue.
Section 1 - Introduction. The special features of the contractor’s facil-
ities, which have a determining effect on the nature of the configuration
management program, shall be briefly described. Characteristics such as
manufacturing capabilities, design and drafting personnel, and organiza-
tional relationships shall be defined.
Section 2 - Organization. This section shall outline the contractor’s
organization and the organizational relationships of the individuals and
activities involved in the configuration management program. Individuals
in the contractor’s organizational structure, in related contractor’s
organizations, and in Government activities shall be depicted. The
responsibilities of each shall be defined. Their relationships shall be
outlined in chart form, and the policy directives that govern the program
shall be listed. Procedures shall not be included in this section.
Section 3 - Baseline Identification. Requirements covering preparation,
approval, and subsequent release of the Departmentallysubmission for DOE
approved documentation which defines each of the required baselines shall
be established in this section. The contractor’s method under which the
documentation shall be prepared, approved by DOE, and released, shall be
described and the time periods in which these steps shall be accomplished
shall be indicated.
Section 4 - Configuration Change Control. Procedures for processing engi-
neering change proposals and requests for deviations or waivers shall be
outlined in this section.
Section 5 - Status Recording and Reporting. This section shall outline
plans for collecting, storing, handling, verifying, and reporting of con-
figuration status information. It shall indicate the techniques to be
applied to provide a dynamic information system, responsive to the needs
of the entire management team.
Section 135
Section 6 - Special Considerations. Peculiarities of the configuration
management program that result from participation by a large number of
organizations, use of many commercial items, use of existing drawings and
specifications or other departures from the normal, and innovations for
more effective configuration management shall be described here.
DOE 4700.1
3-6-87
Attachment III-6
Page III-79
CONFIGURATION MANAGEMENT PROCESS FLOW (TYPICAL)
1. INTRODUCTION. The configuration management process flow will vary from proj-
ect to project depending upon the product, complexity, estimated cost, and
technical interface details. There is, however, a general flow in configura-
tion management which will be relatively consistent. This flow is illustrated
in Figure III-12.
2. HEADQUARTERS PROGRAM OFFICES should:
a. Approve baseline identification documents.
b. Approve an engineering change proposal (ECP) if cost, schedule, or tech-
nical impact exceeds parameter thresholds prescribed by the project
charter, or project management plan. Program office approval is normally
limited to changes to documents which require such approval for the origi-
nal document.
3. FIELD ORGANIZATION/PROJECT OFFICE should:
a. Establish project procedures, define engineering change classes, and
establish the Configuration Control Board (CCB).
b. Develop the functional requirements baseline in support of the objectives
delineated in the justification for new start.
c. Furnish contractor with copies of the technical requirements baseline
documents.
d. Review contractor ECPs:
(1) An ECP form should provide a means for suggesting or recommending
changes to configuration identification. At a minimum, it should
include the basic data elements identified below. An ECP is normally
accompanied by an ECP checklist, which identifies documents and func-
tional organizational elements affected by the change as well as
organizational elements responsible for implementation of the change.
(Other documents required, therefore, may also be attached.)
(a) Baseline Impact. Indicate whether the cost, schedule or tech-
nical baseline shall be impacted. If more than one baseline
will be impacted, so indicate.
(b) Priority. Indicate whether the change priority is Emergency,
Urgent or Routine.
A. Program Office
Figure III-12
Typical Configuration Management Process
.
DOE 4700.1
3-6-87
Attachment III-6
Page III-81
(c) Approval Need Date. Enter the date by which Departmental CCB
approval is required in order to allow work to continue without
additional cost or schedule Impact.
(d) Class. Enter the number indicating whether the ECP is Class 1
or Class 2 (or other, as agreed to with the DOE project office).
(e) CIN/Date. Enter the contractor identification number, which
uniquely identifies the ECP, and the date on which it was
assigned.
(f) Category of Change. Indicate the reason for the change.
(g) Project/End Functions Affected. Briefly describe the top level
functions that will be affected by the CCB decision.
(h) Prepared By. Enter the name and phone number of the responsible
engineer, and the date the ECP was completed. Also enter the
name of the organizational element of the preparer.
(i) Change Title. Enter a brief, descriptive phrase which describes
the proposed change. To the extent practicable the title shall
be unique.
(j) Description/Justification of Change. Describe the proposed
change and the reasons in suff icient detail to fully inform the
CCB members of what is being proposed and why. Continuation
sheets and other documents may be used as required.
Section 136
(k) Cost Impact.
E
Identify the type of funds affected by the change.
nter the estimated impact on cost and the fiscal years in which
the impact shall occur. Also enter the total cost estimate at
completion resulting from execution of the proposed change.
(l) Schedule Impact. Enter a brief statement of the effect that the
implementation of the change will have on the contract end date
(e.g., slip 2 weeks; none; gain 3 months). A more detailed
impact statement may be provided on a continuation sheet.
(m) Impact of Change If Not Made. Explain briefly what the effect
of not making the proposed change shall have on cost, schedule,
and technical performance.
(n) Approvals. The contractor CCB Chairman, the Departmental CCB
Chairman, and DOE project manager shall indicate their approval.
Attachment III-6
Page III-82
DOE 4700.1
3-6-87
(2) Each contractor-proposed change must be forwarded to the contractor
CCB for approval. On approval, it is forwarded by the contractor to
the DOE CCB.
e. Notify the contractor of approval of the baseline, authorizing the con-
tractor to issue the baseline identification documents.
f. Receive and evaluate Class 1 engineering change proposals and engineering
changes which require contract modification (i.e., change order). The
project manager approves or disapproves recommendations. Disapproved
ECPs are returned to the originating office with an explanation of the
reasons for disapproval.
(1) Engineering Change Evaluation.
(a) A change evaluation form provides a means for CCB members to
record their evaluation of each ECP considered by the board.
The form illustrated may be modified as required by the project
office. However, at a minimum, it must include the data ele-
ments identified on the sample form and in the related instruc-
tions below.
(b) The following should be included in the change evaluation:
1 ECP number, revision, correction and title;
2 Recommended modification to ECP as submitted and reasons;
3 Recommended actions and remarks: and
4 CCB
g. Authorize change
(1) The purpose
documenting
It provides
.
member signature and date.
implementation through the appropriate authority.
of a change concurrence form is to provide a means for
the deliberations of the DOE Configuration Control Board.
identification of each ECP and the CCB meeting at which
it was considered, a summary cost and schedule impact of the proposed
change, directed modifications to the ECP, and the position of each
board member with respect to the ECP. It also provides a vehicle for
transmitting, through the work authorization and contract administra-
tion processes, directions to the contractor with respect to each
ECP. The change concurrence should be structured so that it may also
be used by the contractors for documenting the deliberations of their
own CCBs. The concurrence should include the data elements iden-
tified below:
DOE 4700.1
3-6-87
Attachment III-6
Page III-83
h.
i.
(a) ECP number and date, revision number and date, correction number
and date, and ECP title;
(b) Configuration control board meeting date;
(c) ModificatIons to submitted ECP;
(d) Cost impact summary;
(e) Schedule impact summary;
(f) Board members position on ECP as modified above;
(g) Recommended action on ECP; and
(h) Signature of chairman and date.
(2) A change concurrence should be prepared for each ECP considered by
the CCB. It can then be submitted to the contracting officer as an
attachment to work authorization documents for his use in transmit-
ting to
Section 137
Initiate any
document and
Review Class
the contractors the directions resulting from CCB actions.
required revision to an earlier or higher level baseline
provide to all affected parties.
2 changes. If the project office does not concur in the
Class 2 classification, notify the contractor to resubmit the change as
Class 1.
4. CONTRACTORS shall:
a. Upon contract award, implement the contractually required configuration
management plan.
b. Develop configuration identification in support of the current baseline
requirements.
c. Using the ECP format, submit the proposal to issue baseline identification
documents.
d. Issue the baseline identification documents and maintain the document
masters.
e. Develop changes to configuration identification documents that may result
from the contractor’s normal engineering process, from other contractor
initiated ECPs, or from changes in project requirements directed by the
project office.
Attachment III-6
Page III-84
DOE 4700.1
3-6-87
f. Prepare and process ECPs in accordance with the configuration management
plan.
g. Segregate Class 1 and Class 2 ECPs and forward them to the DOE project
o f f i c e .
h. Issue the revised configuration identification.
i. Incorporate the authorized change into the hardware/software in accordance
with the revised documentation and track the incorporation of these
changes.
j. Monitor the inspection, acceptance, and checkout to verify that the “as
built” configuration of hardware/software is consistent with its current
configuration identification. Identify deficiencies.
k. If a change is required, proceed to develop configuration identification,
ECP, and supporting documentation.
l. Establish and maintain the administrative records and files necessary for
support of the configuration management process.
m. Prepare and distribute periodic configuration status reports in accordance
with contract reporting instructions.
DOE 4700.1 Attachment III-7
3-6-87 Page III-85
1.
2.
COST AND SCHEDULE CONTROL SYSTEMS CRITERIA
GENERAL. The prospective contractor’s cost and schedule control system
proposal shall be evaluated to determine whether it meets the criteria
described in paragraph 2 below. An element in the evaluation of proposals
will be the proposer’s systems for planning and controlling contract perform-
ance. The prospective contractor shall agree to operate systems that are in
compliance with the cost and schedule control systems criteria throughout the
period of contract performance if awarded the contract. DOE shall rely on the
contractor’s systems and, therefore, shall not impose separate management
control systems.
CRITERIA. The contractor’s management control systems shall include policies,
procedures, and methods which are designed to ensure that they will accomplish
the following:
a. Organization.
(1) Define all authorized work and related resources to meet the require-
ments of the contract, using the framework of the contract work
breakdown structure.
(2) Identify the internal organizational elements and the major sub-
contractors responsible for accomplishing the authorized work.
(3) Provide for integration of the contractor’s planning, scheduling,
budgeting, estimating, work authorization, and cost accumulation
systems with each other, the contract work breakdown structure, and
the organizational structure.
(4) Identify the managerial positions responsible for controlling over-
head (indirect costs).
Section 138
(5) Provide for integration of the contract work breakdown structure with
the contractor’s functional organizational structure in a manner that
permits cost and schedule performance measurement for contractor work
breakdown structure and organizational elements.
b. Planning and Budgeting.
(1) Schedule the authorized work in a manner which describes the sequence
of work and identifies the significant task interdependencies
required to meet the development, production, construction, installa-
tion, and delivery requirements of the contract.
(2) Identify physical products, milestones, technical performance goals,
and other indicators that will be used to measure output.
Attachment III-7 DOE 4700.1
Page III-86 3-6-87
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
Establish and maintain a time-phased budget baseline cat the cost
account level against which contract performance can be measured.
Initial budgets established for this purpose shall be based on the
negotiated target cost. Any other amount used for performance meas-
urement purposes shall be formally recognized by both the contractor
and the Government.
Establish budgets for all authorized work with separate identifi-
cation of cost elements (labor, material, and so forth).
To the extent the authorized work can be identified in discrete,
short-span work packages, establish budgets for this work in terms of
dollars, hours, or other measurable units. Where the entire cost
account cannot be subdivided into detailed work packages, identify
the long-term effort in larger planning packages for budget and
scheduling purposes.
Provide that the sum of all work package budgets, plus planning
package budgets within a cost account equals the cost account budget.
Identify relationships of budgets or standards in underlying work
authorization systems to budgets for work packages.
Identify and control level of effort activity by time-phased budgets
established for this purpose. Only that effort which cannot be iden-
tified as discrete, short-span work packages or as apportioned effort
shall be classed as level of effort.
Establish overhead budgets for the total costs of each significant
organizational component whose expenses will become indirect costs.
Reflect in the contract budgets at the appropriate level the amounts
in overhead pools that will be allocated to the contract as indirect
costs.
Identify management reserve and undistributed budget.
Provide that the contract target cost plus estimated cost of author-
ized but unpriced work is reconciled with the sum of all internal
contract budgets and management reserve.
c. Accounting.
(1) Record direct costs on an applied or other acceptable basis in a for-
mal system that is controlled by the general books of account.
(2) Summarize direct costs from cost accounts into the work breakdown
structure without allocation of a single cost account to two or more
work breakdown structure elements.
DOE 4700.1
3-6-87
Attachment III-7
Page III-87
(3)
(4)
Summarize direct costs from he cost accounts into the contractor’s
functional organizational elements without allocation of a single
cost account to two or more organizational elements.
Record all indirect costs which will be allocated to the contract.
(5) Identify the bases for allocating the cost of apportioned effort.
(6) Identify unit costs, equivalent unit costs, or lot costs as appli-
cable.
(7) The contractor’s material accounting system shall provide for:
(a)
Section 139
(b)
(c)
(d)
(e)
(f)
d. Analysis.
Accurate cost accumulation and assignment of costs to cost
accounts in a manner consistent with the budgets, using
recognized, acceptable costing techniques;
Determination of price variances by comparing planned versus
actual commitments;
Cost performance measurement at the point in time most suitable
for the category of material involved, but no earlier than the
time of actual receipt of material;
Determination of cost variances attributable to the excess usage
of material;
Determination of unit or lot costs when applicable; and
Full accountability for all material purchased for the contract,
including the residual inventory.
(1) Identify the following items at the cost account level on a monthly
basis using data from, or reconcilable with, the accounting and
budgeting systems:
(a) Budgeted cost for work scheduled and budgeted cost for work per-
formed;
(b) Budgeted cost for work performed and applied (actual where
appropriate) direct costs for the same work;
(c) Estimates at completion and budgets at completion; and
(d) Variances resulting from the above comparisons classified in
terms of labor, material, or other appropriate elements together
Attachment III-7 DOE 4700.1
Page III-88
(2)
(3)
(4)
(5)
(6)
3-6-87
with the reasons for significant variances, including technical
problems.
Identify on a monthly basis in the detail needed by management for
effective control, budgeted indirect costs, actual indirect costs,
and variances along with the reasons.
Summarize the data elements and associated variances listed in sub-
paragraph 2d(1) and (2), above, through the contractor organization
and contract work breakdown structure to the reporting level
specified in the contract.
Identify significant differences on a monthly basis between planned
and actual schedule accomplishment, together with the reasons.
Identify managerial actions taken as a result of subparagraphs 2d(1)
through (4) above.
Based on performance to date and on estimates of future conditions,
develop revised estimates of cost at completion for work breakdown
structure elements identified in the contract, and compare these with
the contract budget base and the latest statement of funds require-
ments reported to the Government.
e. Revisions and Access to Data.
(1) Incorporate contractual changes in a timely manner recording the
effects of such changes in budgets and schedules. In the directed
effort before negotiation of a change, base such revisions on the
amount estimated and budgeted to the functional organizations.
(2) Reconcile original budgets for those elements of the work breakdown
structure identified as priced line items in the contract, and for
those elements at the lowest level of the project summary work break-
down structure, with current performance measurement budgets in terms
of changes to the authorized work and internal replanning in the
detail needed by management for effective control.
(3) Prohibit retroactive changes to records pertaining to work performed
that will change previously reported amounts for direct costs,
indirect costs, or budgets, except for correction of errors and
routine accounting adjustments.
(4) Prevent revisions to the contract budget base except for Government-
directed changes to contractual effort.
(5) Document, internally, changes to the performance measurement baseline
and, on a timely basis, notify the Government project management
through prescribed procedures.
Section 140
DOE 4700.1 Attachment III-7
3-6-87 Page III-89 (and III-90)
(6) Provide the contracting officer and his or her duly authorized repre-
sentatives access to all of the preceding information and supporting
documents.
DOE 4700.1 Chg 1
6-2-92
Attachment III-8
Page III-91
1.
2.
GUIDELINES FOR PREPARING REWIRED SUMMARY OF BASELINE INFORMATION,
BASELINE CHANGE CONTROL THRESHOLDS,
BASELINE CHANGE PROPOSAL FORMATS, AND CHANGE DISPOSITION RECORD
Introduction. This attachment provides guidance for preparation of the
required formats provided by:
Figure III-15,
Figure III-16,
Figure III-17,
Figure III-18,
Summary of Baseline Information Format;
Summary of Thresholds Format;
Baseline Change Proposal Format; and
Change Disposition Record Format
Figures III-15 and III-16 are required for inclusion in the controlled
items section of all MSAs and MPs project plans.
Figure III-17 is the format that will be used to request Level O BCCB
approval of changes to project cost, schedule, and technical baselines.
Figure III-18 is the format for the change disposition record following
Level O BCCB actions.
Summary of Baseline Information Format.
Figure III-15, Summary of Baseline Information Format, is the format that
shall be utilized to establish initial cost, schedule, and technical
(scope) baselines. The responsible Program Secretarial Officer provides
his/her recommendations for the project baselines for each of the four
levels of authority that will be approving baseline documents and changes
to those approved baseline documents on this format for ESAAB approval at
KD-1. ESAAB approval is required prior to start of preliminary design.
Where necessary, attachments may be provided when space in the format
prohibits clear and complete definitions of baselines. References to
other documents should be minimized, as this format is to be included in
each project plan which is the highest level program document in a
project. In these cases where clear definition is not possible (i.e., the
period prior to Key Decision 3 for the Level 2 and 3 baselines) recognized
generic document titles may be used. The following
guidelines/instructions for completing each block of the format is
preceded by the column and row titles of the block.
a. Level O Technical (Scope) Baseline. Enter the primary project
parameters which, if changed, would have significant impacts on all
three baselines. These parameters should be selected from the
Conceptual Design Report (CDR) and be expressed quantitatively.
Example of those entries are:
Vertical line denotes change
Attachment III-8
Page III-92 DOE 4700.1 Chg 1
6-2-92
(1) Total Plant Capacity
(a) reprocess 100 kg Pu per/yr.
(b) generate 2,000 MW (thermal).
(c) receive and store 3,000 gallons of low level waste/yr.
(2) Plant size
(a) 250,000 sq. ft.
(b) 60 acre secure zone
(c) 25 sq. mile exclusion zone
(3) Release limits
(4) Quantity of reactor coolant loops
b. Level O Schedule Baselines. Enter the titles and schedule dates
(month/year) if key milestones to be controlled by the Acquisition
Executive. The listing shall include Key Decisions 1, 2, 3, and 4 and
an annual ESAAB review for those years, through Key Decision 4, for
which no Key Decisions are scheduled.
will be identified. A sample listing follows:
At least one milestone per year
Milestone Schedule Date
Key Decision 1
ESAR
9/91
9/92
Key Decision 2
ESAR
6/93
6/94
Authorize Long-Lead 4/95
Procurement
Authorize Site 2/96
Preparation
Section 141
Key Decision 3
ESAR
10/96
10/97
Complete Construction
ESAR
7/98
7/99
Key Decision 4 12/99
c. Level O Cost Baseline. Enter TEC and TPC values.
d. Level 1 Technical (Scope) Baseline. Enter the remaining primary
project parameters, not previously identified as Level O, selected
from the CDR which, if changed, would have significant impacts on all
three baselines. Examples of these entries would be:
(1) Design approach for HVAC heating and cooling
(2) Design approach for total electrical power
(3) Selected system performance parameters
Vertical line denotes change
Milestone
DOE 4700.1 Chg 1 Attachment III-8
6-2-92 Page III-93
e. Level 1 Schedule Baseline. Enter the titles and schedule dates
(month/year) of key milestone to be controlled by the project Program
Secretarial Officer. The listing shall include those milestones
identified in section 4 g of Part F, Environmental Planning and
Review, of Chapter II, Project Planning and Budgeting. Additional
suggested control milestones are:
Schedule Date
Complete Conceptual Design
Start Title I Design
Complete Title I Design
Start Title II Design
Complete Title II Design
Start Site Preparation
Start Construction
Start Testing
Complete Testing
7/91
11/91
4/93
8/93
8/96
9/96
12/96
9/98
10/99
f. Level 1 Cost Baseline. Enter control points (established from Level 2
WBS) for TEC and/or TPC, as appropriate.
g. Level 2 Technical (Scope) Baseline. List project performance
parameters selected from the CDR and not identified as Level O or 1,
which if changed, would have major impacts on all baselines. As the
project proceeds through its acquisition phases, this baseline will
expand to meet the needs of each phase. At the completion of
Preliminary Design, DOE approved design requirements will be added.
At the completion of detail design, DOE approved design/construction
requirements will be added. At the completion of construction, DOE
approved testing/operations documents will be added. This baseline
evolves as the project evolves.
h. Level 2 Schedule Baseline. Enter the title and schedule dates (month/
year) of major milestones to be controlled by the Project Manager.
The listing should include:
(1) Start and completion dates for preparation of critical project
documentation required for submission to and approval by the
Program Office and Acquisition Executive.
(2) Start and completion dates of critical contractor documentation
requiring Project Manager approval.
(3) Start and completion dates of critical system contractor
developed engineering documentation requiring Project Manager
approval. These milestones shall be supportive of Level O and 1
control milestones.
i. Level 2 Cost Baseline. Enter value of approved project contingency.
Vertical line denotes change
Attachment III-8
Page III-94
DOE 4700.1 Chg 1
6-2-92
3. Summary of Thresholds Format. This format is used for baselining change
control thresholds. Each threshold defines the limit(s) of authority of
each of the four management levels for approving proposed changes to
approved cost, schedule, and technical baselines agreed to at Key Decision
1 and documented in the Summary of Baseline Information format. Where
necessary, attachments may be provided when space in the format prohibits
clear and complete definitions of thresholds. The following guidelines/
instructions for completing each block of the format is preceded by the
column and row titles of the block.
Section 142
a. Level O BCCB Technical (Scope), Schedule, and Cost Thresholds.
Currently defined in Figure III-16. Variations to these currently
defined thresholds must be justified and receive ESAAB approval at Key
Decision 1 or subsequent ESAAB meetings or Level O BCCB meetings.
b. Level 1 BCCB Technical (Scope) Threshold. Same guidelines/
instructions as provided by 3.a. above.
c. Level 1 BCCB Schedule Thresholds. This block will define the
thresholds for both Level O and Level 1 control milestones for which
the Level 1 BCCB will have approval authority. An example of these
thresholds is:
(1) < + 6 and > + 3 months to Level O milestones
(2) > + 3 months to Level 1 milestones
d. Level 1 BCCB Cost Thresholds. All proposed cost changes that impact
TEC or TPC with an estimated cost >0 but less than $50M.
e. Level 2 BCCB Technical (Scope) Thresholds. Same guidelines/
instructions as provided by 3.a. above.
f. Level 2 Schedule Thresholds. This block will define the thresholds
for Level O, 1, and 2 control milestones for which the Level 2 BCCB
will have approval authority. An example of these thresholds is:
(1) < + 3 months to Level O milestones
(2) < + 3 months to Level 1 milestones
(3) all changes to Level 2 milestones
g. Level 2 Cost Thresholds. All proposed changes for which use of
project contingency is required.
4. Baseline Change Proposal (BCP) Format. Figure III-17, Sample Baseline
Change Proposal Format, is the format that should be utilized by all DOE
Program and Project Offices and contractor personnel for proposing changes
to DOE approved cost, schedule, and technical baselines. The format
provided in Figure III-17 may be altered to meet the specific needs of a
program; however, the BCP format must address, as a minimum, all of the
subjects identified in the format. The BCP format will only be used for
Vertical line denotes change
DOE 4700.1 Chg 1 Attachment III-8
6-2-92 Page III-95
presenting the problem, the proposed solution, and the impacts on affected
Department of Energy (DOE) approved project baselines. Accountability and
traceability of all DOE BCCB reviews and dispositions of proposed changes
shall be documented on DOE BCCB Disposition Record formats.
The following guidelines/instructions for completing each block of the
format is proceeded by the title of the block. Additional pages that may
be required for completely defining a proposed change shall be identified
by BCP number and page number and referenced in the appropriate block(s)
of page 1 of the BCP.
a.
b.
c.
d.
e.
Project No. This block is required for tracking/traceability
purposes. Project numbers are assigned and included on the cover
sheet of approved project plans. The initiator of the BCP may obtain
this number from his respective BCCB Secretariat for insertion in the
block. An example of a project number is 85-D-105. This number
sometimes referred to as the budget line item project number.
Project Title. This block is required for tracking/traceability
purposes. The initiator will enter the complete project title or
recognize acronym/abbreviation for the project. An example is
Plutonium Recovery Modification Project.” Its recognized acronym/
abbreviation is PRMP.
Section 143
BCP No. This block is required for tracking/traceability purposes.
As the Level 2 BCCB will have more change activity than the higher
level BCCBs, responsibility for designing and maintaining a numbering
system that meets project needs is delegated to it. The initiator of
the BCP will obtain the BCP number from his respective BCCB
Secretariat for insertion in this block. Once a BCP number has been
assigned, it will not be reassigned; it will be retained and used with
an appropriate suffix for all subsequent revisions or iterations of
the basic BCP. The BCP numbering system for a project will be
standardized within a project to aid in efficient maintenance of a
Project Change Log.
For multi-partite or Multi-site projects, it may be necessary to
design intelligence into the BCP number; the alternative is assignment
of blocks of numbers to affected sites. If intelligence is designed
into the numbering system, a field of the number will be numeric and
assigned only once so that a straight numeric sort of the Project
Change Log is possible.
BCP Title. This block is required for tracking/traceability purposes.
The initiator will enter a brief (60 characters or less) descriptive
title of the proposed change. Examples of titles are “Increase
Chilled Water System Slow Rated,” “Extend Deluge System 8 Main
Header,” "Extend Schedule (FY-91 Funding Reduction).”
BCP Level. This block is required to indicate the BCCB which has
final approval authority for the changes being proposed. The DOE
Project BCCB Secretariat will check the appropriate box subsequent to
determination of approval authority by the Project BCCB.
Vertical line denotes change
Attachment III-8
Page III-96
DOE 4700.1 Chg 1
6-2-92
f.
g.
h.
i.
j.
k.
Point-of-Contact. This block is required for coordination purposes.
In most cases, the name, phone number, and location of the person
taking responsibility for initiation and implementation of the change,
if approved, will be inserted.
Processing Designation. This block is required to identify the
allowable timeframe for Level O, 1, and 2 BCCB processing of the
proposed change. The Level O and 1 timeframes are specified in this
document, and the Level 2 timeframe is specified in the appropriate
BCCB charter. The Project BCCB Secretariat shall check the
appropriate block as soon as possible (within 1 workday) after
receiving the BCP. The definition of “priority” and “routine” is
delegated to the Level 1 and 2 boards and will be defined in the
change control board implementation procedures for each board.
Change Description. This block is required to define the scope of the
change. A complete description of the change will be entered by the
initiator and shall be stated in “from/to” terms in order to avoid
confusion concerning the exact intent of the proposed change, and
should be written in sufficiently clear language to be used as the
“Scope of Work” statement or “scope of work” revision for contractual
implementation. Reproducible attachments shall be included as
necessary to support the change description.
Documentation affected shall be identified along with the affected WBS
elements. The assistance of the A/E contractor and M&O contractor in
identifying the affected documentation should be obtained as
necessary.
Section 144
Change Justification. This block is required to justify the need of
the proposed baseline change. The initiator will provide a
description of the problem the change proposes to correct or the new
capability the change proposes to provide. When the proposed change
is to provide a new capability, the potential improvements and
benefits will be specifically identified. If alternative methods for
resolving the problem have been considered and rejected, the rationale
for selecting the method proposed should be included.
Inadequate justification is the most common reason for disapproval of
a change.
Impact of Non-Approval. This block is required to provide project/
program impacts if change is rejected and not implemented or approval
is delayed. Impact on the project schedule, resources, technical
requirements, safety, environment, etc. will be addressed.
Impacts on Cost Baseline. This block is required to define Department
baseline cost, budgetary and funding impacts and implications if the
change is approved for implementation.
Vertical line denotes change
6-2-92
DOE 4700.1 Chg 1 Attachment III-8
Page III-97
(1) Total Cost. The value inserted here is the total estimated cost
for design, construction, and testing (implementation of change)
if the change is approved regardless of sources of funds and
regardless of whether the change is in-scope or out-of-scope
(contractual). The value in this entry need not necessarily be
equal to the summation of the remaining entries in the block but
will be equal to the sum in many cases.
(2) TEC. If additional funding, or decrease, from TEC is being
requested to implement the change, the value will be inserted
here.
(3) TPC. If additional funding, or decrease, from TPC is being
requested to implement the change, the value will be inserted
here.
(4) Contingency. If the total cost of the change is going to be
funded from contingency, providing change control thresholds are
not exceeded, the value will be entered and the change may be
approved at Level 2. If only part of the funding is from
contingency, enter the value.
(5) Other. If part of the total cost will be budgeted from
contractor management reserve or by a cost-sharing partner
company, enter the value here.
(6) Change to Funding Profile Included. If the magnitude of cost
impact significantly impacts the current funding profile, include
the requested profile change in additional pages of the BCP and
check the “yes” block. If profile changes are not being
requested as part of the BCP, check the “no” block.
l. Impacts on Schedule.
(1) Level O. If implementation of the change will cause a delay or
decrease in the duration of an approved Level O milestone greater
than change control thresholds, check this block and enter the
name of the milestone and its current and proposed schedule
dates.
(2) Level 1. Same guideline/instructions as presented for Level O
milestones.
m. Impacts on Scope.
(1) Technical Documents. If any technical documents require changing
if change is approved and implemented, check the box and provide
a listing of the documents requiring change to the extent
possible. Include as technical documents approved Level O, 1,
and 2 baseline design drawings and specifications, installation
procedures, test procedures, operations procedures, environmental
documents and permits, safety related documents, and contract
Vertical line denotes change
Attachment III-8 DOE 4700.1 Chg 1
Page III-98 6-2-92
Section 145
documents. The listing should include number, title, and
revision identifier of the document requiring change, as
appropriate.
(2) Program Documents. Same guidelines as presented for technical
documents. Include as program documents approved Level O, 1, and
2 baseline strategic plans, project plans, project management
plans, and quality assurance plans or procedures.
n. Other Impacts. When uncertainties exist as to whether or not an
impact not affecting cost, schedule, or scope baselines could assist
in the decision making process for the proposed change, it should be
entered in this block. An example is the proposed change would have a
significant impact on facility operating costs for the life of the
plant or programmatic operating expenses directly related to the
facility.
o. Mitigating or Corrective Actions. When mitigating work-arounds or
corrective actions will be taken to minimize potential impacts,
particularly in environmental and safety aspects, they should be
included in this box.
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
IV-1
CHAPTER IV
1.
2.
PROJECT REVIEW, REPORTING, AND ASSESSMENT
PART A - PROJECT STATUS REVIEW
INTRODUCTION. This chapter discusses the policy and procedures for
project status review and reporting to upper levels of Departmental
management. It examines form and substance of status reviews as well as
report formats for project reporting.
PROJECT STATUS REVIEW. The objectives of project status review are to
inform senior management of project status; problems which require their
attention; imminent completion of a phase in a Major System Acquisition;
an evaluation of concept and definition effort prior to major resource
commitment; controlled goals and thresholds either threatened or exceeded;
and other relevant issues and changes such as mission need,
budget/financial redirection, scope, costs, timing, management structure,
or changes having significant environmental quality assurance and safety
impacts. Although presenting status of basic performance parameters is an
important part of these reviews, sufficient time should also be allotted
for the presentation of issues and problems which need to be brought to
the attention of the management.
a.
b.
Headquarters Reviews. Project reviews shall be presented to the
respective Program Secretarial Officer(s) on all Major System
Acquisition and Major Projects. A project review shall be held on a
regular basis and/or as project progress dictates. Representatives
from the office of Assistant Secretary for Environment, Safety, and
Health; the Directors of Energy Research, Procurement, Assistance and
Program Management; and Administration and Human Resource Management;
the General Counsel;
the subject material
documented through a
presentations and an
shall be sent to the
and other interested offices shall be invited as
dictates. These reviews shall be clearly
memorandum for the record. Copies of
Action Memorandum or memorandum for the record
Office of Program/Project Management.
Project Review. Responsibility for day-to-day review of project
status and application of corrective actions within his or her
authority resides with the project manager. The Head of the
Departmental Element shall maintain cognizance of the project status,
giving special attention to problem areas, and shall direct that
corrective actions be taken as appropriate. The responsible program
manager shall maintain cognizance of project status through review of
monthly and quarterly project manager status reports supplemented by
special briefings as required. He or she shall take corrective
actions within his or her authority as necessary to maintain project
cost, schedule, and technical performance within baselines.
Section 146
Vertical line denotes change
IV-2 DOE 4700.1 Chg 1
6-2-92
c. Field Reviews. Field reviews for field-managed projects shall be
3.
4.
coordinated with the Program Secretarial Officers and conducted prior
to decision points by the head of the field element responsible for
the project. Field office support organization, (e.g., environment,
procurement), the program manager, the Office of Program/Project
Management, and other staff as appropriate, may participate in the
reviews. Normally, field project reviews shall be conducted for
validation prior to insertion in the budget; at the end of conceptual,
preliminary and detailed design, prior to construction release; and at
appropriate points as determined by the field element manager to
update scope, cost, schedule, and funding baselines.
PROJECT STATUS REVIEW FOR MAJOR SYSTEM ACQUISITIONS.
a.
b.
c.
The Acquisition Executive is the reviewing authority for Major System
Acquisitions and shall call for these reviews on an exception basis to
accomplish certain objectives. These occasional reviews shall provide
a greater awareness of the progress of individual large projects that
have a high level of visibility, program importance, technical
complexity, and significant multi-year financial mortgages.
The project reviews for the Acquisition Executive shall be issue-
oriented presentations and discussions. They shall provide clear and
objective reports of project status, current and impending problems,
and identification of areas where senior level management assistance
would be beneficial.
A schedule for the project status reviews for the Acquisition
Executive shall be maintained by the Office of Program/Project
Management in close coordination with the Acquisition Executive and
cognizant program managers.
Federal Managers’ Financial Integrity Act and Audit Resolution and
Followup. The Department is fully committed to the implementation of
effective systems of internal controls and a rigorous program for audit
resolution and followup. The Federal Managers’ Financial Integrity Act
requires the Department to evaluate the adequacy of its internal controls
and to report the results annually to the President and the Congress.
a. Candid Reporting. In compliance with the Federal Managers’ Financial
Integrity Act, DOE has implemented an internal control program which
is highly reliant on management self-assessments and candid reporting
of problems or potential problems to permit expeditious, resolution.
This must be done on a continuing basis to assure effectiveness.
b. Followup of Audits. The Inspector General Act Amendments of 1988
placed added responsibility on the Department for reporting to
Congress on the effectiveness of the DOE audit resolution and follow-
up activities. All recommendations made by the Inspector General or
the General Accounting Office shall be responded to quickly and
candidly and corrective actions undertaken and reported immediately
without delaying until audit completion. Responsive and candid
reporting will increase the effectiveness and efficiency of reporting
systems and provide the high degree of credibility the Department
wishes to achieve.
Vertical line denotes change
DOE 4700.1
3-6-87
IV-3
PART B - PROJECT REPORTING AND ASSESSMENT
1. INTRODUCTION.
a. It is Departmental policy to have a single reporting system, which pro-
vides the status of projects relative to established baselines. The re-
porting by the project manager to higher management and by the Department
Section 147
to Congress shall present the recipient with a clear picture of project
status and resource utilization.
b. The system is flexible, but the degree of flexibility is limited in order
to maintain a standardized structure of formats sufficient to provide
adequate comparisons between projects and to facilitate preparation of
consolidated reports for all Departmental projects. Standardization is
also provided to minimize the workload involved at the organizational
levels preparing the reports. In an effort to further minimize reporting
burdens placed on field organizations, program-unique reports are
discouraged except for essential management information. Reports to
Headquarters shall be comprised of basic information already required by
project managers to manage their projects.
c. The data requested in this reporting system are not intended to limit
field organizations and project managers from requesting either additional
detailed reports or more frequent reporting from their subordinate
organizational elements or contractors. It is left to the discretion of
each field organization to require additional reporting for use at its
organizational level as long as such reporting is consistent with
information provided to Headquarters in the reports specified below and
with the guidelines of DOE 1332.1A.
d. The remainder of this chapter has been organized into two basic sections.
The first section describes the reports to be submitted by project
managers and includes report formats, reporting frequencies, and duration
of reporting requirements. Report preparation instructions are provided
for each format. The second section provides similar guidance for
reports prepared at the Headquarters level and an explanation of the use
made of project manager reports in their preparation.
2. REPORTS PREPARED BY PROJECT MANAGERS (EXCEPT FOR GENERAL PLANT PROJECTS).
a. Major System Acquisitions and Major Projects. Project managers of Major
System Acquisitions (MSAs) and Major Projects (MPs) shall submit quar-
terly, supplemental, and annual reports unless directed otherwise by the
program Secretarial Officer.
IV-4 DOE 4700.1
3-6-87
(1) Project Manager’s Progress Report. The project manager shall provide
to Headquarters quarterly reports through the Head of the Field
Element, using the formats illustrated in Attachment IV-1, unless
directed otherwise by the program Secretarial Officer. The Head of
the Field Element shall transmit the project manager's reports by
cover sheet memorandum. Indicated in the memorandum shall be com-
ments on an exception basis of the project manager’s assessment.
b.
c.
d.
(2) Project Manager's Quarterly Supplemental Reports. Additional details
On MSA’S and major projects shall be provided through submission of
supplemental reports. There are four supplemental reports, three of
which are optional:
(a)
(b)
(c)
(d)
Supplement 1 - Project Activity Report. (See Attachment IV-3.) ,
This is a required supplement.
Supplement 2 - Cost and Cost Plus Commitment Chart. (See
Attachment IV-4.) This is an optional report prepared as
negotiated between program and managing offices.
Supplement 3 - Engineering, Management, and Construction
Manpower for Cost-Type Projects. (See Attachment IV-5.) This is
an optional report prepared as negotiated between program and
managing offices.
Supplement 4 - Progress Photographs. (See Attachment IV-6.)
This is an optional reporting requirement dependent on physical
progress of the project.
Section 148
Other Projects with a Total Estimated Cost of $15 Million or Greater:
Project Manager’s Progress Report. (See Attachment IV-1.) Project mana-
gers of other projects with a Total Estimated Cost (TEC) of $15 million or
more shall submit quarterly reports using the same formats used for MSAs
and major projects reports. Reports shall be submitted quarterly as of
December 31, March 31, June 30, and September 30 of each year.
Other Projects with a TEC of $5 Million to $15 Million: Project Manager’s
Progress Report. (See Attachment IV-1. ) These projects shall be reported
quarterly using an abbreviated format of the Project Manager's Progress
Report. This abbreviated format consists of reporting on part I only of
the two-part content of Attachment IV-1. Should the TEC increase on these
projects to a level of $15 million or more, subsequent reports shall be
governed by paragraph 2b, above.
Other Projects with a TEC Under $5 Million: Semiannual Status Report.
(See Attachment IV-2.) All non-general plant projects, including in-house
energy management with a TEC under $5 million shall be reported to Head-
quarters on a semiannual basis as of March 31 and September 30. These
DOE 4700.1 Chg 1
6-2-92
IV-5
e.
f.
g.
3.
4.
5.
reporting dates have been selected to assist in preparation of the
annual budget. The data elements for these project reports consist of
summary level data. Should the TEC on these reports increase to
$5 million, the appropriate reports form the above grouping of
projects shall be used.
Annual Report for General Plan Projects. (See Attachment IV-7. )
Operations offices shall submit an annual report as of September
all GPPs.
Field Organization Reports. The Head of the Field Element may
prescribe supplementary formats for internal reporting purposes.
such requirements shall be included in the field organization
implementation of the DOE Project Management System.
Cost Underrun Reporting: Each field office must notify the
over
30 on
Any
appropriate Program Secretarial Office of all potential cost underruns
when construction is 80 percent complete. Information copies are to
be provided to the Headquarters Office of Budget, Budget Execution
Branch (CR-131), and to the Associate Director for Program/Project
Management and Control, Office of Program/Project Management (PR-20).
Headquarters DOE written approval is required prior to reapplication
of these funds.
SUBMITTAL REQUIREMENTS. Four copies of each report prepared by a project
manager shall be submitted through the field element manager to the
responsible Headquarters program office and four copies directly to the
Office of Program/Project Management. Reports shall be submitted in time
to reach these offices by the 25th working day following the “as of” date
of the reports. If meeting the 25th working day requires an earlier
cutoff date for financial and cost performance report data, the prior
month data will be acceptable, provided that other portions of the Project
Manager’s Progress Report address the project status through the current
“as of” date.
DURATION OF REPORTING. Reporting shall commence once preliminary design
is initiated and continue until full normal operations involving the
project have commenced and the project is closed, and it is jointly
determined by the Project Manager and the Program Secretarial Officer that
further reporting is not required. Reporting on projects that have a
definite operational or test period for demonstrating their visibility
shall be required during such confirmatory testing periods.
Section 149
SUMMARY OF PROJECT MANAGER REPORTING REQUIREMENTS. Project Manager re-
porting requirements to Headquarters are summarized below in Figure IV-1.
Vertical line denotes change
IV-6 DOE 4700.1 Chg 1
6-2-92
6. REPORT PREPARED BY HEADQUARTERS.
a. Project reports initiated in Headquarters shall be consistent with and
incorporate the contents of the Project Manager reports identified
above. Headquarters’ summary reports on field projects shall be
prepared by both the program office and the Office of Program/Project
Management. Program offices shall be responsible for transmitting
Project Manager’s reports through their Program Secretarial Officers
to the Acquisition Executive with Headquarters line management
comments added as appropriate on an exception basis. The Office of
Program/Project Management is responsible for preparing consolidated
reports on projects for the Department.
(1) Program Manager’s Report to the Acquisition Executive (Cover
Sheet Transmittal). (See Attachment IV-8. ) This report shall be
provided to the Acquisition Executive quarterly by Program
Managers of all MSAs and Major Projects. Submitted through
appropriate program Secretarial Officers, this report shall
consist of a cover sheet to the project manager’s quarterly
reports. It serves as the only mechanism for providing the
project manager’s report to the Acquisition Executive. The cover
sheet shall provide program manager assessments if they differ
from the project manager’s assessments. It shall also address
items raised as Headquarters’ action items by the project manager
and other topics considered to require top management attention.
The Program Secretarial Officer is encouraged to add comments to
the report as deemed appropriate. The cover sheet shall be
submitted to the Acquisition Executive and the Office of
Program/Project Management by the 25th working day following the
“as of” date of the project manager’s report.
(2) Summary Project Performance Report to Senior Management. (See
Attachment IV-9.) This report on MSAs and Major Projects shall
be provided quarterly by the Director of Administration and Human
Resource Management to the Acquisition Executive and Program
Secretarial Officers. The report shall consist of the Project
Manager’s assessment extracted from their reports plus the
comments of the Associate Director, Office of Program/Project
Management. The contents of the report shall be coordinated with
appropriate program managers prior to its submission. The
Summary Project Performance Report to Senior Management shall be
submitted by the 35th working day following the “as of” date of
the report.
(3) Quarterly Status of Department of Enerqy Project. (See
Attachment IV-10.) The quarterly status report is a summary of
baseline data for projects, indicating original and current cost
baselines along with the schedule information. This report shall
be prepared quarterly, as of March 31, June 30, September 30, and
December 31, by the Office of Program/Project Management. The
report shall be distributed Department-wide by the Office of
Program/Project Management upon its completion.
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
b. Figure IV-2 provides a
related to information
mangers.
IV-6a (and IV-6b)
summary of reports prepared in Headquarters
obtained form reports submitted by project
Section 150
7. CRITERIA FOR EVALUATING PROJECT STATUS. To allow for a meaningful
comparison of the status of all projects, a standard set of criteria has
been established. There are three levels of status: satisfactory, minor
concern, and major concern. The technical, cost, and schedule performance
of a project shall be separately evaluated against these three status
levels. In addition, an overall assessment category shall be included.
The overall status shall be determined by the project manager’s composite
evaluations of the impact of the individual ratings for technical, cost,
and schedule. Figure IV-3 is a matrix of the criteria used for evaluating
project status.
Vertical line denotes change
Type and Dollar Reports to Be Submitted Report formats
Level of Project by Title “As-Of” Date by Figure Number#
Major System Acquisitions (MSA) Project Manager’s Progress Report Quarterly or as Attachment IV-1
and Major Projects (MP) Required by Program Parts I & II
Secretarial Officer
Project Manager’s Quarterly End of Each Calendar Attachment IV-3 thru
Supplemental Report Quarter. 6. (1 mandatory, 3
optional)
Other Projects with a Total Project Manager’s Progress Report. End of Each Calendar Attachment IV-1,
Estimated Cost of $15 Million or Quarter. Parts I & II
More
Other Projects with a Total Project Manager’s Progress Report. End of Each Calendar Attachment IV-1,
Estimated Cost of $5 Million to (excludes genaral plant project) Quarter. Part I only
$15 Million
Other Projects with a Total Semi Annual Status Report March 31 and Attachment IV-2
Estimated Cost under $5 Million (excludes general plant projects). September 30.
General Plant Projects (GPP). Annual Report for General Plant End of Each Fiscal Attachment IV-7
Projects. Year.
Note: All reports are due 25 working days after report “as of” date.
Figure IV-1
Summary of Project Managers Reporting Requirements
Project Manager Reports
Type and Dollar Format for Report Included or Used in
Level of Projects Title of Report by Exhibit Number Preparation of Report
Major System Project Manager’s Quarterly Report to Attachment IV-8 Project Manager’s Progam Report
Acquisitions or Major Acquisition Executive Attached to Cover Sheet
Projects Memorandum
Major System Quarterly Project Performance Report Attachment IV-9 Extract of Project Manager’s
Acquisitions or Major to Senior Management. Narrative Highlights from Project
Projects Manager’s Progress Report
All DOE Projects Quarterly Status of Department of Attachment IV-10 Project Manager’s Progress -
Energy Projects. Quarterly, Semi-Annual, and Annual
-Reports.
Figure IV-2
Summary of Headquarters Reporting Requirements
Minor Concern M a j o r C o n c e r n Satisfactory
Essentially meetlng performance/
scope objectives.
Technical/E ngineering problems may
result in inability to meet established
performance/scope objectives
Technical/Engineering Problems will
result in inability to meet established
performance/scope objectives.
Technical
No known Congressional, Administration
or external constraints influencing
achievement of technicdal scope.
Potential Congressional, Administration,
or external constraints jeopardizing
achievement of technical scope.
Probable or confirmed actions by Congress,
Administration or external constralnts
preclude achievement of technical scope.
Obligation and/or cost variance from
Plan greater than 10 percent but less
than 25 percent.
Obligation and/or cost variance from Plan
greater than 25 percent.*
Section 151
Obligations and costs within 10 percent
of Plan.
Total estimated cost may or will increase
by more than 10 percent but less
than 25 percent
Total estimated cost may or will increase
by more than 25 percent.
Total estimated cost is within 10 percent
of baseline.
Cost
Available contingency as a percentage
of uncosted balance is ralatively low.
Contingency is exhausted or is not
commensurate with technical risk.
Available contingency as percentage
of uncosted balance is adequate.
Potential Congresslonal, Administration
or external constralnts influenclng
costs.
Probable or confirmed actions by Congress,
the Administration, or external influences
will affect costs.
No known Congressional, Administration
or external constraints influence cost.
Essentially on baseline schedule and
within 3 months of established project
completion date.
Baseline interim milestones or completion
dates projected to slip at least 3 months
but not more than 6 months.
Baseline interim milestone or completion
dates projected or conflrmed to slip by
6 months or more.
Schedule
Probable or confirmed actlons by Congress.
the Administration, or external
constraints will affect schedule.
No known Congressional, Administration,
or external constraints influencing
schedule.
Potential Congressional, Administration,
or external constraints influencing
schedule
*If the TEC for an actlve line item project increases by 25 percent or more, Congress must be notified before further obligations can occur.
Figure IV-3
Criteria for Evaluating Project Status
DOE 4700.1 Attachment IV-1
3-6-87 Page IV-11
PROJECT MANAGER’S PROGRESS REPORT INSTRUCTIONS AND EXAMPLE
1. GENERAL.
a. This report is formatted in two-parts. Only non-general plan projects
with a total estimated cost of $15 million or more require completion
of both parts I and II. Projects with total estimated costs of $5
million to $15 million, that are not Major System Acquisitions or
Major Projects, complete only part I of this report and report
quarterly.
b. General plant projects and all other projects below $5 million in
total estimated cost report in accordance with the instructions in
Attachments IV-2 and IV-7, respectively.
2. INSTRUCTIONS. The following detailed data is to be provided.
a. Part I. Complete for all projects with a total estimated cost of $5
million or more.
(1)
(2)
(3)
(4)
(5)
(6)
(7)
Item 1a, Project Title/Number. Show the full title of the
project as it appears in its budget data sheet. Include
geographic location of project, if determined. If project
location has not been determined, indicate: “project location to
be determined.”
Item 1b, Reporting Period. Show period of time reported
(example: 1-1-81 to 3-31-81).
Item 1c, Managing DOE Field Locations. Enter name of managing
field organization. If project is not managed by a field
organization, indicate appropriate program management
organization.
Item 1d, Project Sponsor/Program Office Contact. Indicate the
Headquarters program organization with name and telephone number
of the program manager.
Item 1e, Project Manager. Enter project manger’s full name,
telephone number, and mailing address.
Item 1f, Performing Organizations. Provide the names of
laboratories and prime contractors involved in the project and
their responsibilities.
Item 2, Project Manager’s Personnel Assessment.
(a) Item 2a, Summary Status. Complete this item using the
definitions of satisfactory, minor, or major concern
provided in Figure IV-3, “Criteria for Evaluating Project
Status.”
Section 152
Attachment IV-1 DOE 4700.1 Chg 1
Page IV-12 6-2-92
(b) Item 2b, Project Manager’s Narrative Highlights. Using the
space provided, summarize major accomplishments and problems
involving the project. This narrative for Major System
Acquisitions and Major Projects will be extracted to be
included in the Summary Project Performance Report to senior
management. Detailed discussion of problems and variances
between baselines and current estimates of cost, schedule,
or technical performance should be provided in item 5,
“Significant Problems/Variance.”
(8) Item 3, Summary Funding/Cost Status.
(9)
(a) Item 3a, Total Project. Baselines information should be
taken from the latest approved project plan or subsequent
Action Memorandum signed by the appropriate decision
authority (Acquisition Executive for Major Projects, DOE
Field Office manager for other projects). Congressional
project data sheets will be used for baselines purposes only
in the absence of project plans or Action Memorandums.
Funding information requested should reflect the total
project funding as shown in the last project data sheet
formally submitted to Congress.
(b) Item 3b, Cumulative to Date. Reflect the balance of unused
or unallocated contingency. Provide the actual amounts of
funds appropriated to date for the project, the funds made
available to the project manger to date, and the funds
authorized to the contractor to date. Enter the cumulative
actual costs accrued and the Departmental commitments to
contractors to date.
(c) Item 3c, Baselines Documentation. All baseline information
must be supported by appropriate documentation to include
the title of the baseline document, identification of the
approving DOE official, and the date of approval; e.g.,
“Project Plan, Acquisition Executive, 6-30-81.”
Item 4, Summary Schedule Status. Projects that cannot measure
progress in terms of design, procurement, and construction may
provide a composite percent complete estimate for the total
project. Operations completion information pertains only to
demonstration-type projects which have an operational test period
included to provide the technology. Reporting status of
operation is not required for those projects which have an
indefinite operating period following completion of the
acquisition process. Problems and significant variances depicted
in this reporting section should be discussed in item 5,
“Significant Problems/Variance Analysis.”
Vertical line denotes change
DOE 4700.1
3-6-87
Attachment IV-1
Page IV-13
(10) Item 5, Significant Problems/Variance Analysis. Problems and vari-
ances should be discussed here in terms of their impact on the project
wherever possible. Problems satisfactorily resolved during the
reporting period should be discussed in item 5a, particularly those
problems reported as open in previous reports. Item 5b should
reflect those actions which require Headquarters action to be taken
(e.g., scheduling of major milestone decisions, allocation of funds,
and major commitments of resources).
b. Part II. This part is applicable only to major system acquisitions, major
projects, and other projects with a total estimated cost of $15 million or
more.
(1) Item 6, Cost Status Report. This format is organized to accommodate
projects which are managed in accordance with the traditional con-
struction breakdown (design, construction, and so forth). Projects
which are organized along work breakdown structure lines and use
DOE 1332.1A reports, should use the Alternate Cost Status Report.
Baseline costs and estimates for total estimated cost and total proj-
ect cost must reconcile with amounts shown on the Summary Funding/
Cost Status Report (Item 3 of Part I).
Section 153
(2) Item 7, Alternate Cost Status Report.
(a) Projects receiving the Cost Performance Report, or its equiva-
lent, should use the Alternate Cost Status Report. For projects
involving two or more large contracts, data reported should be
taken directly from the total line of format 1 of the contractor
submitted Cost Performance Reports. For projects with multiple
contractors with some reporting on the Cost Performance Report
and others not, the Alternate Cost Status Report should be
employed. For contractors not submitting the Cost Performance
Report, budgeted cost for work performed will equal budgeted
cost for work scheduled in the columns provided, and budgeted
cost for work scheduled can be assumed to be the Cumulative Cost
Plan data. If the project is contained essentially in one major
contract, reporting should be for the level 2 elements of the
project summary work breakdown structure. In all cases, copies
of the Cost Performance Reports may be substituted for this for-
mat, provided that the project manager’s estimate of costs at
completion, the estimated completion dates, and the reconcilia-
tions to total estimated cost and total project cost are
included. See DOE 1332.1A for further detail.
(b) Project contingency is entered in the budget at completion
column on the contingency line. Management reserve is the
contractor's management reserve and is entered in the column
Attachment IV-1
Page IV-14
(3)
(4)
DOE 4700.1
3-6-87
Item 9, Technical Performance Parameters. Provide a brief listing of
the key project technical performance criteria or objectives, the
quantitative values for each reflected in the current projected tech-
nical baseline, and the current forecast of quantitative values which
will actually be attained based on current knowledge and planning.
provided for each total contract entry. (Management reserve for
individual work breakdown stricture elements is not required. )
Item 8, Milestone Log. In addition to the milestone information
requested, milestones which require prior decisions by the Acqui-
sition Executive or other senior level officials should be
identified.
PROJECT MANAGER’S PROGRESS REPORT
PART I
Materials Beam Accelerator AK-78-12B September 30, 1982
Richland Operations Office A. C. Martin Company (Conventional facilities Design)
Safeguard Construction (Conventional Facilities
FTS-252-7894 Construction Management)
Office of Fusion Research/William Woods. . ● Springfield National Laboratory (Special Facilities)
Gary Strauss
FTS 444-3624
2. PROJECT MANAGER’S PERSONAL ASSESSMENT:
COST
LEGEND
SCHEDULE
TECHNICAL
OVERALL PROJECT
The project manager’s assessment remains a minor concern since the accelerator in under study for possible
configuration changes. Alternate accelerator concepts are being studied in the event funding considerations
preclude construction of the accelerator in its present form. These include a neutron-proton configuration
and a light-ion concept. Studies also continue on the proton-proton configuration for cost reduction
possibilities which includes a 4 to 1 concept. Performance by A. C. Martin Company and Safeguard
Construction continued satisfactory through the report period. Procurement packages have been released for
the target assembly and experimental systems.
PROJECT MANAGER'S PROGRESS REPORT
PART J
PROJECT VIE Materials Beam Accelerator
3. SUMMARY FUNDING/COST STATUS (See Item 5 for variance analysis):
Ja. TOTAL PROJECT
3b. CUMULATIVE TO DATE
Section 154
sen BASEL int FuNotNG ° CURRENT ESTIMATE m8 Aout
TOIM, PROJECT COST (TAC) 192.0 141.5 180:1 REMAINING CONTINGENCY 4 W03
oo 192.0 141.5 180.1 FUnDS APPROPRIATED 141.5
twon-008 FUNDS AVAILASLE 141.5
TOM ESTHMICD COST (TEC) 176.7 129.6 162.1 Fans, MuMOMuTED vo contaneren 141.5
oot 176.7 129.6 162.1 COSTS ACCRULO 104.8
woo commacron comuiverns 114.9
3c. BASELINE DOCUMENTATION
DOCUMENT TITLE
Project Plan
APPROVING OFFICIAL
James Murry
DATE
4. SUMMARY SCHEDULE STATUS (See Item 5 for variance analysis):
START DATE COMPLETION DATE PERCENT COMPLETE
me BASELINE FORECAST /ACTUAL BASELINE FORECAST /ACTUAL BASEL IRE actu
pesicn 1-31-78 1-31-78 4-30-85 4-30-85 70.6 72.5
PROCUREMENT 6-30-79 6-30-79 4-30-85 4-30-85 57.7 54.1
CONSTRUCTION 5-30-79 5-30-79 4-30-85 4-30-85 54.5 56.5
OPERATIONS
QT-AI abed
T-AIT uawyrezyy
9-9-0
i
T00Z¢ 300
PROJECT MANAGER’S PROGRESS REPORT
PART 1 PROJECT TlTLE Materials Beam Accelerator
5. SIGNIFICANT PROBLEMS/VARIANCE ANALYSIS
5a. PROBLEMS, IMAPCT ON PROJECT, CORRECTIVE ACTIONS
The lack of a definitive design for the dipole fabricator continues to be a major problem, reflected in
the cumulative cost variance of $ Extensive research and development work is underway to
achieve a reference design. Technical progress is good. The current schedule calls for a first
cell test to be completed by March 1983 consisting of 4 dipoles and 1 quadropole. Also, an additional
10 sets of coils in their own iron are to be tested. Two of the 6 in the first cell and 8 of the 12
additional coil sets are to be accelerator quality.
The major milestone for testing of the 4 MeV accelerator has slipped from April 1983 to August 1983
due to the late selection of the AFQ fabrication. Significant November 1983 tasks were completed on
schedule.
5b. ITEMS REQUIRING HEADQUARTERS ACTION
Provide funding guidance for FY 1984 and outyears.
PROJECT MANA6ER’S PROGRESS REPORT
PART II PROJECT TITLE Houston Test Reactor
6. COST STATUS REPORT
COST ELEMENTS
82,234 562 82,690 56275,690
86,670
109,950
75,970
84,286
110,299
0
5,298
17,868
28,796
5,475
14,281
26,851
5,981
19,347
36,564
0
61,892
6,158
19,347
36,564
1,834
1,268
4,804
4,218 107,852 107,852
147,783918 147,783
0 0 0 0 4,348 4,804 4,348
272,310 270,555 51,962 46,607 62,069D0E TEC 8,468 10,046 342,673 342,673
274,75134,853148,097 149,576 50,846 41,643 56,316 56,002 274,75133,688
TOTAL D0E PROJECT COST 420,407 420,131 102,808 118,07188,250 18,209 43,321 43,734 617,424 617,424
TOTAL PROJECT COST 43,321 617,424 617,424420,407 420,131 102,808 88,250 118,208 43,734118,071
PROJECT MANAGER’S PROGRESS REPORT
PART II PROJECT TITLE Materials Beam Accelerator
7. ALTERNATE COST STATUS REPORT
Special
Facilities
10
20
30
40
50
60
Conventional
Facilities
70
80
57.3
3.6
7.1
5.1
11.0
20.6
9.9
35.2
25.4
9.8
92.5
8.9
59.0
3.6
7.1
5.2
10.8
21.0
10.5
34.7
25.0
9.7
59.4
3.6
7.1
5.3
10.9
21.9
10.6
35.4
25.6
9.8
125.8
10.5
9.4
18.4
20.6
44.0
22.9
35.2
25.4
9.8
126.3
10.5
9.4
18.5
20.7
44.1
23.1
35.8
25.9
9.9
126.3
10.5
9.4
18.5
20.8
44.1
23.1
35.8
25.9
9.9
4-30-85
4-30-85
4-30-85
4-30-85
4-30-85
4-30-85
4-30-85
1-30-82
6-30-82
7-31-82
9-30-84
Program Manage-
ment
Mechanical
Systems
Target Systems
Power
Optics
A/C/D
Laboratory
Office Building
CONTINGENCY 15.7
162.193.7 94.8
10.0
176.7
15.3
162.1TEC
OTHER COSTS
R&D to complete 18.0 9-30-84
9-30-84
18.08.5
102.2
construction
101.4 104.8 92.0 60.1TOTAL PROJECT COST 180.1
Section 155
Attachment
IV-1
Page IV-20
DOE 4700.1
3-6-87
PROJECT MANAGER’ S PROGRESS REPORT
PART II PROJECT TITLE Materials Beam Accelerator
9. TECHNICAL PERFORMANCE PARAMETERS
Office Building
Laboratory Building
Top Energy
Operating Energy Range
Equivalent Fixed Target
Injection Energy
Circumference
Dipole Field at 400 GeV
Vacuum System
Refrigeration Capacity
74,000 square feet
163,000 square feet
450 x 450 GeV
30 x 30 GeV to
340,000 GeV
30 GeV
4,348 meters
70 KG (5 Tesla)
4 x 10-12 Torr
24,750 Watts @
450 x 450 GeV
3.8
F O R E C A S T
Complete
Complete
Same
Same
Same
Same
Same
Same
Same
Same
DOE 4700.1
3-6-87 Attachment IV-2
Page IV-23
1.
2.
SEMIANNUAL STATUS REPORT FOR NON-GENERAL PLANT
PROJECTS BELOW $5 MILLION IN TOTAL ESTIMATED COST, INSTRUCTIONS AND EXAMPLE
GENERAL.
a. All nongeneral plant projects with a total estimated cost under $5
million are to be reported semiannually as of March 31 and September 30.
b. All other projects are reported using a different format. Nongeneral
plant projects with a total estimated cost of $5 million or more are
reported in accordance with Attachment IV-1; general plant projects are
reported per Attachment IV-7.
INSTRUCTIONS. The format of this report provides summary level information on
projects under $5 million. Two lines of information are required per project
allowing several projects to be reported on the same page. The following
detailed data are to be provided using definitions provided in Attachment III.
a. Identification.
(1) Managing DOE Field Office. Enter the name of managing field office.
If project is not managed by field office, indicate appropriate
program management organization.
(2) Reporting Period. Show the period of time reported (e.g., 9-30-80 to
3-31-81).
(3) Report Date. Indicate the date the report was submitted.
(4) Project Title/Project Number. Indicate the full project title with
the project number (from, the project data sheet) below it.
b. Status Information.
(1) Type of Estimate. There are two lines of information for each proj-
ect. The first represents the baseline and the second the current
estimate of the project manager.
(2) Cost Status. Provide both the baseline and current estimate for the
total estimated cost of the project, cumulative actual costs accrued
for prior years against the baseline estimate for that period, and
the actual cost accrued for the current fiscal year to date against
the baseline estimate.
(3) Schedule Status. Provide the dates (month and year) for the start
and completion of design, procurement, and construction, and for the
Attachment IV-2 D0E 4700.1
Page IV-24 3-6-87
start of operations. Provide percent complete for in-process activi-
ties. Dates for activities completed prior to the as-of-date of the
report should be actual dates instead of estimates.
c. Remarks. If the overall status of a project is other than satisfactory,
provide appropriate remarks in footnotes.
SEMI-ANNUAL STATUS REPORT FOR NON-GENERAL PLANT
PROJECTS BELOW $5 MILLION IN TOTAL ESTIMATED COST
wnacing oot fitio orpice: Oak Ridge Operations Office
September 30, 1981 to
PAPORTING PERLOU: March 31, 1982
vroat mt:April 30, 1982
Section 156
COST STATUS SCHLOULE STATUS a
prcct umase crm pesin Procune nat constauctigh | abeantions
te paton CURRENT - ,
. YEARS TEAR Stant COMPLETE 3 START COMPLETE 5 START COMPLETE a staat
Fire Safety and
Fire Protection mse 1165001125 -1 (12-78 {12-79 |---| --- | --- | ---] 3-80 | 4-83 |---|] 3-83
Improvements
80-1-e cme 11.5 11.4 .2 | 4-78 | 1-80 |100] --- | --- |---| 2-80 | 3-82 1100] 3-82
a soe msm [1.3 [1.3 o | 2-80 {12-80 }100| 1-81 | 6-81 | 100] 4-81 }11-81 |---| ---
BO-ES-5 :
comment | 1.3 5 3 | 2-80 | 3-81 /100} 3-81} 4-83] 20] 4-81 | 3-82 | 100] ---
FY 1980 Reactor | wsam | -8 5 .3 [11-81 | 1-82 [100] 3-81 | 12-81 | 100] 6-81 [12-82 | 100] 12-82
Modi fications
Un Eo“ cunscat | 8 4 .2 {11-81 | 7-82 | 95] 3-81] 9-82] 90] 6-81 |11-83 | 80] 11-83
retignation wseiime (2.3 12.3 O | 1-80 11-80 |---| 3-81] 9-82] ---| 9-80 | 9-81 |---| 9-81
B0-ES-7 >> Ia? ze to an Ia3.an linn! co cn "
cmt [2.2 1.7 i) ¢€-6U {11-80 ;100 | 9-80] 9-81] 100] 3-81 | 3-82 [100/ 3-82
potners and Roof | wsam {1.9 [1.9 | 0 [11-79 | 2-81 |---| 2-81 | 11-81] ---] 6-80 | 1-82 }---] 1-R2
B0-ES-2 cen [1-9 [1.9 o | 4-81 | 8-81 [100] 2-81] 11-81] ---| 6-80 | 1-82 | 100] 1-82
* Provide remarks in footnotes a3 eppropriate.
L8-9-€
00Lb 30d
°
iy
“Al abeg
“AI Quawysezqy
(92-AI pue) gz
2
DOE 4700.1
3-6-87 Attachment IV-3
Page IV-27
PROJECT ACTIVITY REPORT INSTRUCTIONS AND EXAMPLE
1. Prepare a complete project milestone plan to show scheduled activity and
actual milestone status using the charting information shown below.
2. In the first column, list the key project milestones, including decision
points.
3. Across the top, list the timeframe (i.e., months, years, and so forth) to
show total project time duration.
4. Each quarter, update the report by placing a vertical dash line to show the
current reporting period cutoff and by darkening in the horizontal bar and
milestones to show actual completion in relation to planned completion.
SYMBOLS EXAMPLES
Key milestone A. Key milestone with an
activity bar
Proposed schedule Schedule deviation
deviation (not yet approved)
Activity bar C. First change approved
(slippage)
Time now D. Time now showing actual
completion
Charting Information
5. If available, the “Milestone Schedule and Status Report” (Form DOE 535) or
equivalent may be substituted for this report.
Attachment
Page IV-28
IV-3 DOE 4700.1
3-6-87
DOE 4700.1
3-6-87
Attachment IV-4
Page IV-29
COST AND COST PLUS COMMITMENT CHART, INSTRUCTIONS AND EXAMPLE
(OPTIONAL)
1. Enter an appropriate scale in dollars for the horizontal lines of the grid and
indicate unit of measure (such as thousands and millions). On the grid formed
by the dollar scale and the months and years, plot the cumulative planned
costs and planned cost plus commitments. Plot the cumulative actual cost and
the actual cost plus commitments for each month up to and including the month
being reported. Extend the cumulative actual cost and cost plus commitment
line to indicate a revised estimate. Provide a total obligation ceiling line
at the top of the graphical representation; i.e., the total available funds to
be obligated by the Government. When applicable, reflect changes in the
obligation ceiling without changing prior the month’s ceiling.
2. Enter the total planned dollar cost and cost plus commitment for each month
and year shown.
3. Enter the total actual dollar cost and cost plus commitment for each month up
to and including the month being reported.
Section 157
4. Enter the cumulative variance by month. Show unfavorable variances in paren-
theses.
5. Enter the total planned and actual costs for all prior fiscal years.
6. Enter the current estimate of total costs required for the project. This
includes prior year actuals, current fiscal year actuals to date, plus the
project manager’s estimate of funds required to complete the remaining work on
the project.
PROJECT MANAGER'S QUARTERLY SUPPLEMENTAL REPORT
COST AND COST PLUS COMMITMENT CHART
patoa Cunngut FUSCA yeaa " P@RACAST
pUSCAL TOTAL
wes 7 ect | wv | ccc | se | cco | me | we | we | om | oe | me see | pve sree tes
200
175 _
Cost plus cofmitnients +7?
(planned [" \ or
150 Pe
VI
” /_
§ 125 | Va
z -17 TUK J_ Jue.
--| 100 —___f = on aciokdd I en ~ 1.4
=| 4 -7 To rk eee eo - 1
= Hp ae fee fe ‘ age \
a 75 * - - — a] +
- -—{Costs (planned)
_. wT
50 +
\L[CostB (adtualp
25
—{CostB plus cotmitments |(acthal )
nuete 82__| 86 | 90] 95 1100175 | 78 | 85] 87 | 91193 | 94 | 97/1 130 | 162 | 172
cases Act 59 61 64] 66 | 69175 | 79 | 82187 | 91194 | 97 1100
amar | 23 | 25] 26/29] 31] 0 [1] 3f of okt) IQ) (3)
nueke 106 107 7112 [113 [114 | 98 [102 $103 [104 |107 fo7 {109 1111] 147 168 172
costs = r
Gams. | Mem | 77 | 78 | 84) 86 | 89] 9B | 99/102 fio4 fio7 flog fi11 prof
oaays —
CU WAR LAME 29 29 28] 27 25 0 3 1 0 OKI) ](2) ]
O€-AI abeg
‘AT Quewyseqiy
c
~
L8-9-
‘002% 300
>
s
DOE 4700.1
3-6-87
Attachment IV-5
Page IV-31
ENGINEERING, MANAGEMENT, AND CONSTRUCTION
MANPOWER FOR COST TYPE PROJECTS REPORT, INSTRUCTIONS AND EXAMPLE
1. CURRENT FISCAL YEAR.
a. Using the grid formed by an appropriate manpower scale and the months,
plot separate planned manpower graphs for engineering, non-DOE management
and construction. On each graph, plot actual manpower for each month up
to and including the quarter being reported. Also, provide a projection
through the end of the fiscal year to indicate an estimate of manpower to
be expended for the remainder of the time period shown. If applicable,
enter a total manpower ceiling line at the top of the graphical represen-
tation. The total manpower ceiling is the total manpower funded by the
Government plus the contractor’s shares. Reflect changes in the manpower
ceiling line without changing the prior month’s information.
b. Enter the total planned manpower for engineering, management, and
construction for each month.
c. Enter the total actual manpower for each month up to and including the
quarter being reported.
d. Enter the manpower variance for each month up to and including the quarter
being reported. Show negative amounts in parentheses.
2. TOTAL PROJECT MANPOWER.
a. Indicate the appropriate unit of measure (man-hours or man-months) and
enter an appropriate scale. On the grid formed by the manpower scale and
the quarters, plot separate average per quarter planned manpower graphs
for engineering, non-DOE management and construction. Plot actual average
per quarter manpower for each quarter up to and including the quarter
being reported. Also, provide manpower projections to indicate an esti-
mate of manpower to be expended for the remainder of the time period
shown. If applicable, enter a total manpower ceiling line at the top of
the graphical representation. The total manpower ceiling is the total
manpower funded by the Government plus the contractor’s shares. Reflect
changes in the manpower ceiling line without changing the prior month’s
data. In
necessary
b. Enter the
c. Enter the
struction
Section 158
subsequent fiscal year reports, adjust
to accommodate cumulative reporting of
fiscal years being reported.
total planned manpower for engineering,
the graphic scale as
total project data.
management, and con-
for each quarter through the completion of construction.
Attachment IV-5
Page IV-32
DOE 4700.1
3-6-87
d. Enter the total actual manpower for each quarter up to and including the
quarter being reported.
e. Subtract the actual manpower from the planned manpower and indicate the
cumulative variance to date. Show minus amounts (when actual is greater
than planned) in parentheses.
DOE 4700.1
3-6-87 Attachment IV-5
Page IV-33 (and IV-34)
DOE 4700.1 Chg 1
6-2-92
PROGRESS PHOTOGRAPHS INSTRUCTIONS
Attachment IV-6
Page IV-35 (and IV-36)
1. GENERAL. This is an optional report based on the physical process of a
project. Progress photographs on all projects estimated to cost $15
million or more, or on other projects that program offices or the Office
of Program/Project Management may request, shall be submitted with the
Quarterly Supplemental Progress Reports from time to time to show
important stages in the fabrication or construction process and unusual
features. Except for the larger projects (over $50 million in cost), or
those of unusual interest, one photograph of the site at beginning of
construction and 15 and 20 during the fabrication or construction period
should suffice to meet these requirements for submission to Headquarters.
Usually, only a couple of views need be submitted for each significant
change in experimental device fabrication or construction progress. In
most cases, it will be helpful if those submitted are taken alternately
from different viewpoints. A few views of device components or
significant elements of interior construction shall also be included
during the project execution period. An aerial photograph that shows the
relative position of major elements of a dispersed project is desirable.
2. INSTRUCTIONS.
a. Three prints
submitted to
Management.
(8” x 10” including margins) of each view shall be
the program division and the Office of Program/Project
Reproduced copies of good quality may be provided in lieu
of glossy prints, with program office concurrence.
b. On the lower right corner of each photograph, the following
information shall be furnished:
(1) Description (DOE Field Office and location, name and number of
project, building, or facility, and any special feature of
interest);
(2) Name of principal contractors; and
(3) Date photograph was taken and percent of device fabrication or
construction completion as of that date.
c. DOE Field Office managers or project managers may require additional
photographic coverage of construction progress for their records.
Vertical line denotes change
DOE 4700.1 Attachment IV-7
3-6-87 Page IV-37
ANNUAL REPORT FOR
GENERAL PLANT PROJECTS, INSTRUCTIONS AND EXAMPLE
1. GENERAL. General plant projects reports shall be limited to a single yearend
annualreport which confirms the work accomplished (or started) with the past
year's general plant project funds. No Headquarters status or progress
reporting shall be required, unless specifically required by a program
manager. This annual report shall cover all general plant projects being
accomplished in the Department. It shall cover general plant project work at
both single and multiprogram installations.
2. INSTRUCTIONS. An annual report shall be provided which includes the
following:
Section 159
a. End of the Year Summary.
(1) List all general plant projects costing more than $85,000 that are
being accomplished with the past years’ general plant project
funding. Identify program(s) supported, title, description, and
total estimated cost.
(2) Consolidate small general plant projects (those costing less than
$85,000) and list them under miscellaneous.
(3) Asterisk (*) new projects not included in the original plan.
b. Upcoming Year - Planned.
(1) List all general plant projects to be accomplished in the upcoming
year that have costs greater than $85,000. Identify program(s)
supported, title, description, and total estimated cost.
(2) Consolidate small general plant projects (those costing less than
$85,000) and list under “miscellaneous.”
.
(3) The list is tentative. It is recognized there may be some substitu-
tions during the year. Confirmation of work actually performed and
projects worked on shall be described in the end-of-year summary.
ANNUAL REPORT FOR GENERAL PLANT PROJECTS
END OF YEAR SUIMMARY - FlSCAL YEAR 1977
Liquid Metal Fast
Breeder Reactor
Liquid Metal Fast
Breeder Reactor
Building 221 Addition, Applied
Mathematics
Renovation of Seven Wash and Locker
Rooms, Biological and Medical
Research, Building 202
Installation of Traffic Signals -
Lemont Road, ANL-East
This project calls for construction of a
6,400 square foot addition, which will
provide storage area and space for air
handling equipment.
Renovation will include the Installation of
new concrete block walls, door, toilet parti-
tions, ceramic and floor tile, rockers and
benches.
This project calls for installation of traf-
fic signals, a left turn lane for Lemont
Road southbound traffic, and improvement
of eastbound lanes.
Total $
UPCOMING YEAR - PLANNED
Criticality Monitoring System, Site,
ANL-East
Modifications to Kennels, Bldg. 202
General Offices, Building 212
Replacement of existing criticality alarm
system with a state-of-the-cost system in
13 buildings to provide maximum protection
to laboratory personnel.
Renovation of wings M, N, O and P dog
kennels and runs.
Conversion of existing unused north
balcony space into general office area.
Total $
412,500
145,200
81,400
639,100
231,900
303,800
127,400
663,100
DOE 4700.1
3-6-87
1.
2.
3.
Attachment IV-8
Page IV-39 (and IV-40)
INSTRUCTIONS FOR THE PROGRAM MANAGER’S
SUMMARY REPORT TO THE ACQUISITION EXECUTIVE
GENERAL. The purpose of this report is to provide the Acquisition Executive
with highlights on the status and activities of major system acquisitions and
major projects. This information keeps the Acquisition Executive apprised of
existing or potential problems and allows such timely followup action as may
be required.
DUE DATE. This summary report, covering activities on major system acquisi-
tions and major projects since the previous report, shall be submitted by the
program manager through the cognizant program Secretarial Officer so as to
reach the office of the Acquisition Executive not later than the 25th working
day following the end of the calendar quarter.
INSTRUCTIONS. The program manager receives the project manager’s monthly
report which may have an operations office manager’s assessment included. The
program manager attaches a cover sheet to the project reports within that
program and provides the program assessment if different from that of the
project manager. The program manager, at his or her
address the following specific areas as concisely as
Section 160
discretion, may desire to
possible:
a. Status;
b. Significant problems, issues, or accomplishments;
c. Other items worthy of top management attention;
d. Key events anticipated during the next 3 months;
e. Cost;
f. Schedule;
g. Technical performance;
h. Project manager’s assessment; and/or
i. Actions taken or planned on items identified by the project manager as
items requiring Headquarters actions.
DOE 4700.1 Chg 1
6-2-92
1.
2.
GENERAL.
Attachment IV-9
Page IV-41
SUMMARY PROJECT PERFORMANCE
REPORT TO SENIOR MANAGEMENT, INSTRUCTIONS AND EXAMPLE
This summary report is prepared by the Office of Program/Project
Management, and is intended to provide the Acquisition Executive with an
independent assessment of project status for comparison with the project
manager’s assessment. This independent assessment is based on information
obtained from field reviews, budget validations, and other formal and
informal sources. The project manager’s assessment is provided to the
Office of Program/Project Management on Part 1 of the Project Manager’s
Progress Report. The Office of Program/Project Management’s comments
shall be coordinated with program offices prior to official submittal to
senior management.
INSTRUCTIONS.
a.
b.
c.
d.
e.
f.
g.
Project Title. Enter the title of the project as shown on the Project
Manager’s Progress Report.
Type. Enter the designation of the project as either a Major System
Acquisition or Major Project.
Project Status - Last 6 Months. Enter the overall project status for
each of the last 2 quarters as reported in the Project Manager’s
Progress Report.
Project Manager’s Comments. Summarize the project manager’s current
comments using key words or phrases to explain less than satisfactory
performance status.
Office of Program/Project Management Assessment. Enter the
independent assessment of project status as determined by the office’s
engineers and analysts.
Office of Program/Project Management Current Month Comments.
Summarize the reasons for the Office of Program/Project Management
assessment using key words or phrases.
Reference Tab. Reference the tab number of the backup sheet which
provides narrative explanations of project status by both the project
manager and the Office of Program/Project Management.
Vertical line denotes change
Attachment
Page IV-42
IV-9
DOE 4700.1
3-6
-87
DOE 4700.1
3-6-87
Attachment IV-10
Page IV-43 and IV-44)
DOE 4700.1
3-6-87
CHAPTER V
V-1
PROCEDURES FOR CONSTRUCTION MANAGEMENT
PART A - PROCEDURES FOR MANAGING CONSTRUCTION EFFORTS
1. INTRODUCTION.
a. Each construction effort is unique due to the different and varying con-
ditions, requirements, and problems associated with each project. In
addition to the uniqueness of each effort, an individual project must
comply with rather rigid procedures in relation to funding, safety, and
other requirements. Construction industry and DOE experience have shown
that efficiency and timeliness results when a construction program is con-
ducted in conformance with a well-defined overall policy and detailed pro-
cedures for the construction effort undertaken. This chapter provides an
overview of the Departmental construction policy and necessary procedures
to assure a coordinated construction management effort within the Depart-
ment. This chapter also provides guidelines to assist the managing field
offices in developing their detailed management procedures.
2. MANAGEMENT ELEMENTS AND GENERAL PROCEDURES.
Section 161
a. Parameters and Requirements for Management of the Construction Effort.
(1) Effective management of construction necessitates establishing the
following parameters and requirements:
(a) Clearly defined scope;
(b) Adequate division of work into packages for management control;
(c) Reliable cost estimates;
(d) Realistic schedules;
(e) Applicable standards and criteria;
(f) Competent personnel;
(g) Efficient organization;
(h) Designated authorities and responsibilities;
(i) Monitoring and reporting status of work;
(j) Comparing progress and costs with schedules and estimates;
(k) Identification of potential or actual problems; and
V-2 DOE 4700.1
3-6-87
(1) Prompt action to eliminate or resolve problems,
(2) The importance of planning in developing parameters and requirements
cannot be overemphasized.
b. Planning for Budget. Planning procedures directed toward the preparation
of construction project data for formal budget submittal are contained in
Chapter II. This separation is for editorial convenience. The entire
process of planning and execution should not be rigidly segmented chrono-
logically or substantively. Each phase of the process can overlap chrono-
logically and can support the development of, or act as a reference point
for performance measurement of other phases.
c. Planning for Execution. The primary objective of the execution phase is
to complete successfully the facility design and construction while
satisfying the programmatic needs within authorized funding limitations
and schedule. To satisfy this objective, it is necessary that each field
organization establish and utilize an effective project management plan
for each project.
(1)
(2)
(3)
(4)
Specific project management plans shall be prepared for each major
system acquisition and major project per Chapter II. Any other proj-
ect that cannot be managed by use of the locally established general
management plan described in subparagraph (2), below, shall also have
a specific management plan.
(a) The responsibility for development of this project management
plan rests with the project manager. The field element shall
provide assistance and guidance to the project manager for the
development of the plan.
(b) Specific management plans will require amplification and revi-
sion as the design and construction progress.
(c) Detailed guidance on the content, form, and approval process is
contained in Chapter II, Part A.
General project management plans shall be prepared for categories or
types of projects which are to be managed similarly, encompassing the
same areas that the specific management plans address.
Projects managed by general management plans shall have a specific
document containing scope, estimate, schedule, and designated indi-
viduals assigned authorities and responsibilities. The project
authorization document satisfies this specific document requirement.
Specific project management plans may be established for projects
normally managed by general management plans at the discretion of the
managing field element.
DOE 4700.1
3-6-87
V-3
d. Key Elements in Managing Construction.
(1) Delivery of a facility by construction requires a team effort on the
part of the managing organization, operating contractors, architect-
engineers, construction contractors, construction managers (if used),
and the appropriate Headquarters program divisions and other Head-
Section 162
quarters organizations. The field office which has the prime respon-
sibility for management shall assure timely and accurate status and
forecast reporting against established management plans, both to the
field element and to Headquarters, and a capability for timely
recognition of problems, and implementation of any necessary correc-
tive actions.
(2) The Head of the Field Element shall appoint an individual responsible
for each construction project. This individual may be designated as
project manager, project engineer, or any other appropriate title.
The responsibilities of the designated individual shall be well
defined and the appropriate authority is vested in the individual to
allow accomplishment of his/her responsibilities. However, for major
system acquisitions, the project manager must be approved by the
cognizant Headquarters program organization. Consultation with
Headquarters program organization is required prior to selection of
the project manager for major construction efforts.
(3) To ensure the completion of all line item projects, the Head of the
Field Element shall establish procedures that contain as a mini-
mum the following requirements:
(a)
(b)
(c)
(d)
Routine management meeting during all phases of the project to
review performance, schedules, and costs; identification of
potential and real problems, and action for solutions and
corrective measures.
Written records of those management meetings which result in
assignment of responsibilities for accomplishment and/or
significant management actions.
During the performance of major activities, periodic (normally
monthly) management meetings involving representatives of all
project participants.
For projects requiring a specific management plan, management
meeting attendance by at least one level of supervision above
those responsible for the day-to-clay execution of the project.
When Headquarters program organizations are providing technical
direction, a representative of the Headquarters organization
shall be invited to participate in the management meetings.
V-4
DOE 4700.1
3-6-87
(e) Briefing of the Head of the Field Element or designee on signif-
icant results of the management meetings.
(f) Permit project managers to:
1 Determine what progress is being achieved;
2 Relate that progress to schedules;
3 Compare commitments to related estimates;
4 Compare budgeted and actual costs of work accomplished; and
5 Forecast estimates at completion based on current costs
experience.
(g) Reporting systems which are established by project managers and
are:
1 Based on the uniform reporting system for contractors for
reports from contractors; and
2 Compatible with the reporting required for reports to DOE
management.
(h) Photographs taken periodically to show construction progress,
special features, and incident scenes and details. Photographs
taken shall be properly labeled, dated, and included in the
project record.
(4) Procedures established by field office managers for non-line item
projects should incorporate as many of the requirements listed in
subparagraph (2), above, as possible, depending upon the field orga-
nizations’ contractor relationship, workload, and ability to perform
the function.
Section 163
Architect-Engineer Selection. Selection procedures for architect-
engineers (A-Es) shall be in accordance with subpart 936.6, "Architect-
Engineer Services,” of the Department of Energy Acquisition Regulations.
It is emphasized that, prior to the selection procedures, the professional
experience and qualifications required for each project are accurately
identified, and the evaluation criteria and prerequisites that are devel-
oped for each A-E services procurement adequately reflect these require-
ments. Prior to A-E selection, field office managers must ensure that the
project design criteria package is complete and complies with DOE 6430.1.
e.
DOE 4700.1
3-6-87
V-5
f. Cost Estimates are important tools in the successful management of a proj-
ect and quite often are compared to the actual cost of the project to
judge the success of the management effort. Cost estimates should always
be fully documented and contain the type of estimate, reference year for
the dollar figures utilized and date of the estimate. Heads of Field
Elements shall assure that contingency allowances included in estimates
are developed utilizing an appropriate contingency analysis procedure
for the project being estimated. The estimate documentation shall
include the details on the contingency allowance development.
(1) Seven general types of cost estimates are developed and used by DOE
throughout the life of a construction project. Identification of an
estimate by type denotes a certain level of accuracy and confidence
in the estimate.
(a)
(b)
(c)
(d)
Planning estimates are developed for each project at the time of
project identification. Since these are developed prior to con-
ceptual design, they are ballpark-type estimates and have the
least confidence level. Care should be exercised in these esti-
mates to assure that the order of magnitude is correct since a
tendency exists to avoid changing, particularly upward, this
estimate once established.
Budget estimates are required in order to obtain authorizing
legislation and appropriations. These estimates should be based
on a completed conceptual design and should also be well docu-
mented since they must be justified. Since these estimates are
used to request authorizations and appropriations, they often
must be used as baselines for justifications of cost overruns
and underruns to the Congress. Accuracy and confidences are
often assumed to be much better than they are. Contingency
allowances can be substantial due to the lack of definitive
design information, particularly for large complex projects.
Title I design estimates are prepared upon completion of Title I
design. Through use of plant engineering and design funds,
Title I may be completed prior to inclusion of the project in
the budget. If this should occur, the Title I design estimate
becomes synonymous with the budget estimate. A guideline for
contingency allowance during this stage could be from 5 to 25
percent of the construction costs.
Title II design estimates are developed for each project by the
designer as part of the Title II design requirements. The esti-
mates, since they are based on the definitive design, are the
most accurate and have the highest confidence level of any esti-
mate. Contingencies generally should range from 5 to 15 percent
of the construction cost dependent upon the extent of uncertain-
ties (unknowns, risk) remaining.
V-6 DOE 4700.1
3-6-87
Section 164
(e) Government estimates are used to determine the reasonableness of
competitive bids received in connection with sealed bids con-
struction contracts; and serve as a control in evaluating cost
and pricing data in negotiated contracts. Normally, the Title
II design estimate prepared by the designer, after being
reviewed and approved by the Government, is the basis for the
Government estimate. However, the services of an operating
contractor, architect-engineer, cost plus fixed-fee construction
contractor (with respect to subcontracts) or construction man-
ager may be used as appropriate to prepare, review, or revise
the Government estimate prior to Government approval. Cost-type
contractors shall be required to follow cost estimate procedures
set forth in this paragraph when subcontracting for construction
services. Government review and approval of the Government
estimate are not required when the estimate is within the limits
established by the Governments approval of the cost-type con-
tractors procurement system. The specifics of a Government
estimate vary with the size and type of contracts as delineated
below:
1
Fixe
Architect-Enqineer, Design-Build Fixed-Price, and Cost Plus
d-Fee Construction Contracts. Government estimates shall
be prerepared for all construction and architect-engineer
contracts estimated at $25,000 and above. Such estimates may
be revised when inaccuracies or inconsistencies are revealed
during technical evaluation and/or negotiations.
2 Fixed-Price Construction Contracts.
a Government estimates for fixed-price construction
contracts and modifications thereto shall be based on
approved Title II working drawings and specifications.
These estimates shall be prepared in accordance with the
practices of the construction industry and in the same
careful manner as if the Government were bidding in com-
petition with private contractors.
b Government estimates shall be summarized to conform with
bid items but shall include the following items, as
backup, listed separately:
(1) Separate estimates for alternates set forth in the
bidding documents;
(2) A breakdown indicating quantities and unit costs
for labor, materials, and equipment entering
into the work;
DOE 4700.1 V-7
3-6-87
(3) Estimates for mobilization and demobilization; and
(4) Allowance for contractor’s overhead and profit,
including the cost of such items as sales tax,
insurance, and bonds.
c Government estimates shall be prepared independently in
advance of any bid or solicited proposal submitted by a
prospective contractor or subcontractor.
d Prior to opening of bids, access to or disclosure of in-
formation concerning Government estimates shall be limited
to personnel requiring such information in performance of
their duties.
e Government estimates for formally advertised or competi-
tive proposal fixed price construction contracts shall not
be changed after the opening of bids or proposals unless
careful reexamination indicates a definite error. In the
event an estimate is changed under such circumstances,
detailed reasons for the revision shall be documented.
3 Estimates for Work Under $25,000. The preparation of
Government estimates in connection with work estimated to
cost less than $25,000 is optional with the field element
manager. Where the Head of the Field Element elects to use
a contractor’s estimate, bid, or proposal instead of a
Government estimate under this limitation, the contractor’s
estimate shall be carefully evaluated to verify that it is
fair and reasonable.
Section 165
(f) Current working estimates are developed periodically during the
life of a project for the primary purpose of determining that
the project can be completed within the funds authorized.
Working estimates are developed by updating previous estimates
to ensure that the latest available cost and design data are
reflected in the cost of the incomplete work. Working estimates
should be designed to facilitate separation of the data required
for accountability, cost control, and information for manage-
ment. Special attention is needed in developing good, updated
forecasts of all incomplete work. Standards should be adopted
which will provide adequate internal control without requiring
extensive examinations or duplication of effort. Careful review
of working estimates for cost plus fixed-fee projects is impor-
tant for early determination of adequacy of funds and control of
construction costs. When the working estimate indicates a
significant change in total estimated cost of the project,
changes to the project documentation and/or financial plan must
V-8 DOE 4700.1
3-6-87
(2)
be made. When working estimates exceed the allowable construc-
tion cost, additional authority must be obtained prior to con-
tinuing the project. The appropriate program organization and
the Controller shall be notified of the situation immediately.
(g) An independent cost estimate is a documented cost estimate that
has the express purpose of serving as an analytical tool to
validate, cross-check, or analyze estimates developed by propo-
nents of a project. An independent cost estimate also serves as
a basis for verifying risk assessments.
Contingency Funds. Included in all cost estimates should be a con-
tingency fund comprised of costs which may result from incomplete
design, changes due to unforeseen, uncertain, and/or unpredictable
conditions (e.g., construction work disturbances due to operations),
and expected costs/savings associated with projected market con-
ditions. The amount of the contingency funds will depend on the
status of design, procurement, and construction as well as the com-
plexity and uncertainties of the project’s component parts. The
market condition reserve requirements will depend upon an analysis of
the anticipated availability of resources to complete the job.
Market condition analysis may result in either a positive or negative
requirement for reserves since, for example, an anticipated shortage
of available construction work would indicate possible receipt of
lower bids. Care must be exercised during the market condition anal-
ysis to consider only those items that are separate from the items
utilized for computation of inflation rate. Market condition con-
siderations are an addition to or subtraction from the project cost
without regard to inflation.
g. Project Authorization System.
(1) Purpose. The project authorization system (formerly the project
directive system) provides the Head of the Field Element with
administrative control over significant construction project activi-
ties so as to assure himself or herself that adequate management
control exists for successful execution of the work covered. The
system also provides for control over the scope of activities, sched-
ules, expenditure of funds, and administration of the activities to
be performed.
(2) Activities Requiring Authorization. Authorization for the effort
will be obtained from the field office manager or his designee prior
to initiation of work or contracting for the activities listed below:
Section 166
(a) Any conceptual design activity estimated to cost more than
$200,000 and any plant engineering and design activity.
(b) Preliminary engineering (Title I work) when the cost is esti-
mated to exceed $25,000.
DOE 4700.1
3-6-87
V-9
(c) Any of the following activities when the total estimated cost of
the project exceeds $150,000 when financed from the operating
expenses or plant and capital equipment portions of the budget:
1 Preparation of working drawings and specifications (Title II
design);
2 Construction of a new facility;
3 Additions, alterations, or improvements to an existing facil-
ity; or
4 Removal, demolition, replacement, or restoration of a
facility.
(d) Design, procurement, fabrication, and installation of equipment
or experimental facilities in connection with:
1 Any equipment of $1 million or more in estimated cost that is
funded from the capital-equipment-not-related-to-construction
portion of the plant and capital equipment budget and
involving installation costs of $250,000 or more; or
2 Any experimental project or reactor test loop of $1 million
or more in estimated cost that is funded from the operating
expense budget.
(e) Procurement and stockpiling of material and equipment prior to
authorization for construction by the field organization.
(f) Heads of Field Organizations may authorize funds to an operating
contractor for non-line item projects utilizing an annual finan-
cial plan. However, if this authorization process is utilized,
the operating contractor shall be required to implement an
internal authorization system equivalent to the system described
here. Field organizations shall assure that the operating
contractor authorization are adequately monitored to ensure
proper control over the scope of activities, schedules, expen-
diture of funds and administration for the activities.
(3) Activities Not Requiring Authorization. While use of the authoriza-
tion system is encouraged for all activities, field office managers
shall establish procedures for those activities not requiring
authorization, to assure that the activities are managed and the
funds expended are recorded.
(4) Documentation Requirements.
(a) As a minimum, the following information shall be included in a
project authorization. Field office managers may include other
V-10 D0E 4700.1
3-6-87
information required to satisfy their locally established
project authorization procedures.
1 Project title and project number shall be shown as they
appear in the authorization act and in the financial plan
(.e.g., 73-3-b, Laser Fusion Laboratory, Los Alamos, New
Mexico). For other projects, suitable identification numbers
shall be used for control purposes.
2 Description of the work to be performed.
3 Justificatfion for the work. If justified by prior project
authorization, appropriate reference shall be made.
4 Method(s) of performance, including participants, contrac-
tors, consultants, types of contracts, and participant
responsibilities.
5 Relationship of work to other work necessary to complete the
project and any important interfaces.
6 Estimated cost of the work to be performed and cost author-
ized, by cost breakdown and participants, and including costs
of directly related elements to be operating expense funded.
7 Source(s) of funds.
8 Source(s) of available excess materials or equipment to be
used and authorization for transfer.
9 Required start and completion dates and appropriate
milestones.
Section 167
10 Any special conditions or requirements such as approval re-
quirements for special features of the work, requirements for
accelerated work performance, and any other special con-
ditions or requirements.
11 References to applicable conceptual design reports, project
design criteria, safety analysis reports, environmental as-
sessments, management plan, preliminary proposals, and system
design descriptions, or use of these applicable documents as
part of the authorization documentation.
12 Requesting organizations (with signature and date, when
applicable).
13 Field office authorizations (with signature and date).
DOE 4700.1 V-11
3-6-87
(b) Attachment V-1 is an example of a recommended project authoriza-
tion format that contains all of the above requirements and is
recommended for use.
(5) Activities Approved by an Authorization. The various types of activ-
ities approved at one time by an authorization will depend upon such
factors as the method of handling the work (operating and so forth),
availability of funds, and the nature and urgency of the project.
(6) Modification of Authorizations. A significant change in the scope of
work, appreciable delay in completion, anticipated expenditure or
commitment of funds in excess of the amount covered by the authoriza-
tion, or any other major change in the conditions set forth in the
authorization shall be adjusted by a modification. The particular
conditions requiring a modification shall be established by the Head
of the Field Element in his or her local management procedures.
Modification to project authorizations providing for continuation or
abandonment of the work under the changed circumstances shall be
issued promptly in the same manner as the basic authorization and
shall be justified by the same type of supporting data. Modifica-
tions shall carry the same serial project number as the basic
authorization and, in addition, shall be given a modification number.
Modifications shall be consecutively numbered and filed with the
basic authorization.
(7) Submittal of Authorizations. Submittal of authorizations to
Headquarters shall be at the request of the appropriate Headquarters
organization. A complete set of project authorizations shall be
maintained in each project file and shall be subject to review by
Headquarters personnel during field visits.
h. Construction Management. Heads of Field Elements shall assure that use
of the construction management concept is considered early in the planning
phase of a project. A discussion of the construction management concept
is contained in Attachment V-2.
i. Design Criteria. Development of design criteria for a facility begins at
the time the need for a project is identified. The base of the criteria
is the statement of the functional parameters that the facility must meet.
These functional criteria are further developed, validated, and expanded
during the conceptual design phase. The development of criteria which are
complete and specifically related to the facility requirements allows for
orderly development of the design. Completeness of the design criteria is
emphasized. However, care shall be taken to avoid citing superfluous
codes and standards; the primary purpose of design criteria is to narrow
the criteria to only those applicable to a specific design effort. Prior
to the selection of an A-E, the design criteria should be consolidated
into a document that will provide guidance to the A-E. The design
criteria document should:
Section 168
V-12 DOE 4700.1
3-6-87
(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
Briefly define the purpose of the project.
Provide a general description of the project.
Give the designer room to exercise expertise in the engineering
design disciplines and to use up-to-date design and construction
applications. The A-E shall use his or her knowledge and expertise
to assure that maximum efficiency and cost effective concepts are
included in the design, in accordance with Departmental guidelines.
Provide all design requirements to be applied by the designer to meet
the needs of a specific facility. Usually a narrative format is used
(limits, capacities, quantities, and space allocations).
Incorporate or reference specific Departmental requirements, such as
DOE 6430.1 and other applicable Orders.
Include plans developed to mitigate environmental impacts in accord-
ance with the National Environmental Policy Act documentation and
environmental permit and license requirements.
Refer to specific operating contractor requirements such as design
standards, plant operating policies, and quality assurance manuals.
Identify applicable national and area codes, standards, and guides
not specifically identified in DOE 6430.1. If certain sections or
parts of a specific code or standard are not applicable or are
exceeded by a more stringent code or standard, this fact should be
stated in the criteria document.
j. Design Criteria Package. The availability and use of a well-prepared
design criteria package allows the designer to proceed with the design
with a minimum of delays, allows for better management of the design, and
prevents problems from arising during design work due to lack of project
definition at the beginning. This package shall be provided to the
designer prior to start of design and should contain as a minimum:
(1) The following information related to performance of engineering
design:
(a) The design criteria document(s).
(b) Studies, reports, and conceptual designs related to the project.
(c) Copies of DOE 6430.1, applicable documents referenced therein,
and any additional energy conservation, environmental, safety,
and health standards, including National Environmental Policy
Act documentation.
DOE 4700.1 V-13
3-6-87
(d) Copies of applicable operating contractor standards, guides, and
manuals such as design standards, plant policy and operating
standards, quality assurance program manual, and cost estimating
guides.
(e) Sketches or drawings developed during conceptual design which
contain necessary information related to the specific facility,
such as:
1 Site and location plan;
2 Typical floor plan;
3 Typical elevations;
4 Existing utilities plan and information;
5 Equipment layout plan and listing (operations or production);
6 Special systems layout plan and listing;
7 One-line piping and instrumentation diagrams (process or pro-
duction flows); and
8 Other pertinent information.
(f) Information available on standard and special equipment items
(this does not include building systems) such as:
1 Government furnished and operating contractor installed
equipment (only if pertinent to design needs);
2 Government furnished and construction contractor installed
equipment; and
3 Construction contractor procured and installed equipment.
(2) Other information related to criteria and performance of design
(usually separate attachments to the criteria package):
Section 169
(a) Listing of Departmental and contractor computer programs
available for use by the designer and how they can be obtained.
(b) Listing of related submittals such as reports, calculations,
conceptual design, and costs.
(c) Required drawing size and list of suggested drawings and titles
(Separate attachments with the criteria package).
(d) Estimated cost of construction breakdown thereof.
V-14 DOE 4700.1
3-6-87
(e) Copies of information pertaining to the management of the proj-
ect (project management plan).
(f) Information pertaining to procurement of construction, such as
bid package structure, required contract clauses, and types of
specifications.
(3) A checklist which may be used as a guide in preparing or reviewing
criteria packages is provided in Attachment V-3.
k. Site Selections. Personnel involved in project planning must be aware of
the detailed and sometimes complex nature of the site selection and acqui-
sition processes. The requirements and procedures for the accomplishment
of these processes are detailed in DOE 4300.1A and DOE 4320.1A. Sequenc-
ing of these tasks, particularly in light of their interrelationships with
environmental tasks, has a profound impact on the method of accomplishment
of the project. Site selection and acquisition methods and the timing can
affect the detailed planning of all aspects of the actual construction.
In light of the above, it is imperative that considerable effort be
expended to properly plan the site selection activities very early in the
planning process. Project management plans should contain the detailed
plan of action for the completion of the required site selection tasks.
l. Construction Health and Safety. A comprehensive health and safety program
must be established and utilized for all Departmental construction proj-
ects. The goals of this program are to protect DOE employees, contractor
employees, and the general public from hazards; to protect property from
damage, and to prevent delay or interruption in the Department’s programs
caused by accidents and fires in connection with construction activities.
The authorities, responsibilities, and standards for construction safety
are contained in DOE 5480.1A, DOE 5481.1A, and DOE 6430.1, Chapter 10.
Consideration of safety requirements must begin early in the planning
phase of a project to ensure that they are included in all plans, studies,
schedules, and cost estimates. An example of a safety requirement which
must be considered early is the case in which additional real estate may
be required to achieve fire separations necessary to meet the “improved
risk” criteria of DOE 5480.1A.
m. Environmental Protection. In the planning of a project, it is important
that planners are aware of environmental protection requirements and
include them in all plans and studies prior to preparation of cost and
schedule estimates. The Project Environmental Plan should describe the
actions required to properly protect the environment. Particular atten-
tion must be given to satisfying the requirements of DOE 5440.1C. Early
attention to environmental requirements may avoid costly and time-con-
suming delays in project implementation.
DOE 4700.1 V-15
3-6-87
n. Control Aids.
(1) Successful completion of a construction effort usually depends upon
management’s ability to control the planning, design, and construc-
tion activities. The project manager must select, based upon the
Section 170
project particulars, aids to provide him the control he desires.
Descriptions of the most common control aids are contained in
Attachment V-4.
(2) Control aids utilized by the project manager must be compatible with
the system utilized by the contractor performing the work. The
contractor normally is permitted to utilize his or her established
control system for the contracted work. The most important benefit
from this approach is that the contractor operates in his normal
fashion without extensive new requirements for a particular contract,
which results in greater efficiency and lower costs due to avoidance
of the learning process. The responsibility of the learning process
is placed upon the project manager. It is imperative that the proj-
ect manager and his staff fully understand the contractor’s system.
On large projects, it may be necessary for the project manager and
his staff to receive orientation by the contractor on the operation
of the contractor’s system. Knowledge of the contractor’s system
will allow the project manager to utilize the system to enhance per-
formance of the work. The major benefit from this knowledge will be
the early recognition of problems and the opportunity to apply
corrective action when it will provide the greatest effect.
o. Quality Assurance. The goals of quality assurance are to assure that
research, development, demonstration, and production activities as well as
strategic facility complexes are designed in a controlled manner; that
components, system, and processes are designed, developed, constructed,
tested, operated, and maintained according to sound engineering standards,
quality practices, and technical specifications; and that resulting tech-
nical data are valid and retrievable. Quality assurance begins with the
formative style of design and continues through Titles I, II, and III
services. It comprises both quality engineering and quality control (in-
spection). Quality assurance elements that shall be considered during the
design and construction effort are listed below.
(1) Design.
(a)
(b)
Quality assurance during design shall include review of
materials of construction and installed equipment for economics,
compatibility with other components and maintainability.
Continuous review of the design is required to ensure that the
facility can be constructed as designed using the most efficient
techniques available. In addition, the cost of construction can
be greatly increased by the type of design. Constructability
includes consideration of interferences between disciplines,
V-16 DOE 4700.1
3-6-87
compatibility of specifications with respect to seasonality of
construction, and integration of different contractors on the
job when applicable:
(c) Quality assurance during design shall include provisions to
assess the operability of the facility after completion.
(d) The most important aspect of quality assurance during design is
continuous surveillance of the design. Except in very small
projects, accomplishment of periodic design reviews is seldom
adequate to assure the proper level of quality assurance.
Continuous surveillance assists in reducing the comments
required during the design reviews (e.g., assuring that proper
quality assurance requirements during construction are included
in the specifications), and reducing the total design effort by
reducing time spent on engineering change proposals and for
correction of review comments. It is important to assure that
the bid packages contain the proper clauses for accomplishment
of quality assurance during construction.
Section 171
(2) Construction.
(a) A submittal control system shall be established and operated.
The project manager shall assure the contractor establishes and
follows a plan for shop drawings, test results, and certifi-
cation submittals. The project manager shall also assure that
the architect-engineer, construction manager, or Government per-
sonnel act in a timely manner on approval of shop drawings, test
results, and certifications.
(b) A reporting system shall be established and operated. The
system shall include quality assurance reports from contractors
and quality inspectors together with procedures for reviewing
the reports and taking prompt effective action on quality
assurance.
(c) Adequate staffing of quality assurance inspectors and assurance
that they are qualified to perform the job shall be provided.
(d) Continual checks shall be made to assure that all of the quality
assurance functions specified in the quality assurance plan are
being performed and prompt corrective actions are being taken
when necessary.
(e) All quality assurance reports, x-rays, and other quality
assurance documents shall be filed and stored in Department-
controlled storage facilities.
DOE 4700.1 V-17
3-6-87
p.
q.
r.
Decontamination and Decommissioning. Field office managers shall ensure
that facilities are constructed and operated so that they may be decon-
taminated and decommissioned of in a cost-effective manner.
Decontamination and decommissioning (D&D) considerations shall include:
(1) Limiting contamination of the facility, equipment and site to the
minimum extent consistent with accomplishing the purposes of the
facility.
(2) Providing design features that ease decontamination (see DOE 6430.1).
(3) Incorporate design features that promote reuse of the contaminated
facilities.
(4) Consideration of D&D costs as part of the life cycle cost.
(5) Selection of a tentative D&D method during facility design.
Maintainability. Field office managers shall assure that facilities are
designed and constructed so that they are easily and economically main-
tained (see DOE 4330.4). Maintainability considerations shall include:
(1) Incorporation into the facility of easily maintained features and
durable materials;
(2) Ease of replacement of installed equipment (i.e., without structure
modification);
(3) Accessibility of installed equipment and building systems for
performance of maintenance;
(4) Life cycle costs in selection of features, systems, and finishes; and
(5) Provisions of maintenance instructions and as-built drawings, espe-
cially the location of underground and otherwise concealed utility
lines, process chemical and coolant piping.
Compatibility with Master Plan. Facilities shall be constructed in
accordance with the approved site development and facility utilization
plan (see DOE 4320.1A). In relation to this plan, the following proce-
dures shall be accomplished during the planning, design, and construction
of facilities:
(1) Early in the planning stage the site development plan shall be uti-
lized to determine:
(a) Building siting (location);
V-18
DOE 4700.1
3-6-87
(b) Orientation;
(c) Exterior materials, if specified;
(d) Height and general configuration and footprint;
(e) Size; and
(f) Landscaping features.
Section 172
(2) During the planning process, compatibility of the proposed design
with the site development plan shall be assured.
arise in which the site development plan cannot be followed or pru-
dence dictates that it should not, then action must be taken either
to effect a change to the site development plan so that it and the
design are brought in consonance, or to obtain a waiver of the site
development plan criteria must be obtained. This waiver shall be
approved by the cognizant field office, or for sites administered by
Headquarters, by the outlay program manager. Any waiver that has an
effect on an outlay program shall have the concurrence of the outlay
program manager.
Should conditions
(3) During the process of design and construction, coordination with the
organization responsible for site planning shall be effected to
assure that:
(a) The design and construction remain in consonance with the site
development plan; and
(b) The site development organization is aware of current develop-
ments.
(4) Upon completion of construction, the organization responsible for
site planning shall be provided as-built drawings of the new
facilities, if desired by the organization.
s. Construction Project Records.
(1) A project record shall be maintained for all construction projects.
These records should be maintained by the field element for all line
item projects. The project record may be maintained by operating
contractors at the discretion of field office managers.
(2) The project record normally should be maintained by the project
manager. The following documents shall, as appropriate, be
contained in the project record:
(a) Short form data sheets;
(b) Conceptual design plans;
DOE 4700.1
3-6-87
(c) Conceptual designs;
(d) Conceptual design reports;
(e) Copies of each submitted construction project data sheet;
(f) Project design criteria package;
(h)
(g) Management plan and changes thereto;
(i)
(j)
(k)
(l)
(m)
(n)
(o)
(p)
(q)
(r)
(s)
(t)
(u)
(v)
V-19
Architect-Engineer selection plan, if utilized;
Title I design summary;
A-E design contract;
Project authorization and all modifications thereto;
Title II design;
All cost estimates;
All project reports;
Construction contract and changes;
Construction manager contract;
Construction photographs;
Minutes of project review meetings;
Cost closing statements;
Construction completion reports;
As-built drawings; and
Other documentation of a special nature such as audit reports or
other items directly relating to the project.
(3) Disposition of project records will be governed by DOE 1324.2.
Operations office managers shall maintain such records in the current
records area for a minimum of 1 year after cost closing statement is
issued.
V-20 DOE 4700.1
3-6-87
3. ROLES OF PARTICIPANTS IN MANAGING CONSTRUCTION. Headquarters and field
element roles in project performance tire well defined in Chapter I. However,
it iS necessary to define the roles of other organizations and individuals
that may participate in the planning, design, and construction of a facility,
a. Contracting Officer. A contracting officer is a Departmental represen-
tative designated to enter into and/or administer contracts and make
related determinations and findings. Of particular importance is the
requirement that he or she advise the contractors of the names and
authorities of those acting for him or her and providing technical sur-
veillance of the work.
Section 173
b. Project Manager. The project manager has direct primary responsibility
and accountability for the management of the construction effort. He or
she normally will be designated as the contract administrator or con-
tracting officer’s technical representative for the construction effort by
the contracting office. Among the usual functions of the project manager
are the following:
(1) Assures that cost, schedule, and scope requirements are met;
(2) Acts as the principal contact and serves as the liaison for the
exchange of information between the contractor and DOE;
(3) Assures that instructions to the contractor are within the terms of
the contract;
(4) Assures compliance by the contractor with the technical, safety, and
administrative requirements of the contract;
(5) Participates in the formulating of, and approving, plans and
schedules;
(6) Arranges for contacts between the construction contractor, other par-
ticipants, and appropriate staff, as required;
(7) Assures continuity in performance and information exchange among the
project team participants; and
(8) Initiates to the contracting officer procurement request packages for
contract modifications.
c. Project Engineer or Construction Engineer. This engineer is the individ-
ual responsible for construction projects for which a project manager is
not assigned. He or she performs within well defined responsibilities
established by the Head of the Field Element. Specific responsibilities
vary depending upon the field office management method. He or she may be
assigned as the contracting officer’s technical representative.
DOE 4700.1
3-6-87
V-21
d. Architect-Engineer. The architect-engineer usually furnishes Titles I
and II engineering services, with optional Title III services; consults
with the contract administrator on questions concerning services; and
coordinates the work with the operating and construction contractors and
public utilities, as required by contract. The architect-engineer may
also develop conceptual designs, assist in the preparation of design
criteria, and perform special studies.
e. Construction Contractor. The construction contractor usually furnishes
all materials of construction; performs all construction work in
accordance with the construction drawings and specifications, except for
equipment to be furnished by others; and coordinates his or her efforts
with those of the construction manager, contracting office, and
operating contractor as required by the construction contract.
f. Construction Manager. A construction manager provides professional
services to and functions in support of the project manager. He becomes
part of the project team consisting of the project manager, the
architect-engineer, the construction manager, and operating and
construction contractors. It is seldom beneficial for the construction
manager to be the same firm (or a subsidiary of) as the architect-
engineer or construction contractor because of the possibility of
organizational conflict of interest. In cases where the construction
manager is contemplated as being the same firm (or a subsidiary of) as
any of the other project participants, specific approval shall be
obtained from the responsible outlay program manager and the
Department’s senior procurement official. Tasks that the construction
manager can perform encompass the full spectrum of management activities
of a project. The decision to use a construction manager on a project
is not as difficult as determining the tasks he must undertake and the
method of payment for these services. Considerable thought must be
given to the tasks assigned to the construction manager in order to
affect the best management of the project at the minimum cost. Factors
that help determine construction manager tasks are size and complexity
of the job, capabilities of project management staff, and contemplated
scope of the architect-engineer and the construction contracts.
Section 174
g. Operating Contractor.
(1) The operating contractor may serve as the construction manager or
perform jointly with the construction manager. Operating
contractor’s capabilities to perform these functions should be
carefully evaluated. Operating contractors may not have the
necessary expertise to perform all of the listed functions.
Depending upon expertise, the operating contractor may be assigned
the following functions associated with design and construction
activities:
(a) Preparation of master plans for site and facilities
development as directed by the field element;
V-22 DOE 4700.1 Chg 1
6-2-92
4.
(2)
(b) Planning for facilities, including conceptual design,
preparation of construction project data sheets or other
project proposals, and preparation of environmental
assessments and environmental impact statements;
(c) Preparation of project and process design criteria for
facilities;
(d) Preparation of safety analysis reports;
(e) Procurement of process, specialized, and long leadtime
equipment;
(f) Participation in the review and concurrence in Titles I and II
design work by the architect-engineer and in-house efforts.
(g) Performance of Titles I, II, and III engineering services,
particularly for specialized areas;
(h) Participation in project management;
(i) Participation in final inspection and testing of facilities
when construction is completed;
(j) Participation in the acceptance of facilities for operation;
and
(k) Procurement of design and construction.
If the operating contractor participates in the design, its
coordination with the architect-engineer in the application of the
basic design criteria and concurrence in functional design
criteria, drawings, and specifications is of primary importance.
The operating contractor should consult with the architect-
engineer, the project manager, and any technical representatives
concerning equipment requirements. The operating contractor should
review the detailed design for compliance with the design criteria
and suitability for operation.
LESSONS LEARNED. DOE has extensive experience in construction management.
It is evident from this experience that it should be beneficial to focus
management attention on lessons learned and problems that have plagued past
projects. Some of these problem areas with some recommended solutions are
discussed below. Field office managers should assure that their management
procedures provide for the proper attention to these areas and that lessons
learned are submitted to the Office of Program/Project Management and
Control for incorporation into the Design Information Exchange System.
Vertical line denotes change
DOE 4700.1
3-6-87
V-23
a. Failure to Design to Requirements. A tendency exists during design of a
project to improve the design by consideration of only the benefits of
different design options. Past experience has shown that this can result
in a design with a project scope and costs substantially in excess of the
initial baseline. This problem can be mitigated by utilizing a principle
of the “design to cost” philosophy, where, if any option in a set of
options, with increased costs over baseline is selected, it must be offset
by equal decreased costs under baseline in other areas. Value engineering
can help reduce the cost in some areas.
b. Failure to Establish Realistic Baselines. Baselines should be established
for cost, schedule, and technical requirements when there are sufficient
data to define a realistic cost and schedule. Since baselines are
generally the basis for budgeting and tracking, they must be realistic.
Section 175
(1) On occasion, baselines have been established when sufficient data for
their establishment were not available. In addition, there may have
been a tendency to scope projects and establish schedule in such a
manner that initial costs are favorable. These problems may be miti-
gated if management procedures require a careful review of all proj-
ect data, preferably by an independent organization or staff, prior
to the baseline establishment. This review, to be effective, should
consider the sensitivity of costs related to risks and possible scope
and schedule changes.
(2) Generally, baselines are established after completion of conceptual
design. A careful review of the conceptual design data should assist
in determining the accuracy of the baselines.
(3) It is recognized that certain projects cannot be accurately scoped or
scheduled prior to submission of data for a budget request. For
these projects a contingency cost should be included in the cost
baseline submitted for budget purposes. Scope and schedule uncer-
tainties considered in determining contingency cost should be
recorded in the project documentation.
c. Inadequate Change Control Procedures. Inadequate change control proce-
dures can lead to large scope and schedule changes and result in large
cost increases. Inadequate change control procedures can also preclude
the inability to trace the reasons for cost growth from the original base-
line. These problems can be greatly reduced by development and strict use
of a detailed change control procedure. The procedures are most effective
when they include cost as a consideration for approval, an independent
review of the proposed change, and strict rules that a proposed change
must meet to be considered.
V-24 DOE 4700.1
3-6-87
d. Inadequate and Inaccurate Project Status Reports. TO perform properly,
project managers must continuously assess and analyze the project status.
This has been impossible on some past projects due to the lack of, or
improper reports, from the contractors. In addition, some reports have
been found to contain inaccurate data, thereby resulting in incorrect
analysis and assessment. Identifying early in the planning process what
information is needed to assess and analyze the project properly, and
requiring that information to be furnished by contract, will assist in
minimizing this problem. The problem of inaccurate data may be mitigated
by periodically verifying the submitted data against the data source and
making corrections to the data recording procedure when necessary.
e. Lack of Sufficient Experienced Project Management Staff. Personnel
assigned or hired to manage a project must have sufficient knowledge and
experience to adequately perform the requirements of the position, and the
number of positions on the project management team must be sufficient to
perform the work. This problem can be addressed by conducting a resource
requirements analysis which determines the manpower requirements for the
project staff, the management philosophy, and the requirement for support
contractors. If understaffing occurs, the problems discussed in this
paragraph are more likely to occur. Use of the construction manager con-
cept discussed above may solve some understaffing problems.
f. Insufficient Use of Incentives. Incentives have been shown to be effec-
tive to the construction industry. DOE has utilized incentives sparingly
in the past. The establishment of an incentive policy by the managing
field office for both Departmental personnel and contractors could provide
benefits to the Government.
Section 176
g. Insufficient Project Reviews. Both the frequency and the content of proj-
ect reviews have been inadequate on some past projects. This problem can
be minimized by assuring that project management personnel give the proper
emphasis to the review process. Consideration should be given to estab-
lishing a control or interdisciplinary review group for certain projects.
DOE 4700.1 Chg 1
6-2-92
V-25
PART B - CONSTRUCTION PROJECT PLANNING
1.
2.
PURPOSE. Part B defines the necessary budget process requirements for DOE
construction projects. In addition, it prescribes the minimum planning
elements and procedures that field element must accomplish to assure that
policy and objectives with respect to construction projects are met. As in
all areas of this Order, the Head of the Field Element is allowed
considerable latitude in procedures. He/she is responsible for establishing
internal procedures, where necessary, in order to implement the minimum
requirements contained in this Part.
THE PROJECT PLANNING CYCLE, REQUIREMENTS, AND PROCEDURES.
a. General.
(1) The interconnected planning and budget cycles encompass an
approximate 4-year period. During this time, project
identification, project selections, project scope and construction
requirements, reliable cost estimates, and advance project planning
needed to assure timely project initiation are developed and
accomplished. This time must be well utilized to assure that each
of the required projects is clearly identified and adequately
scoped and that sufficient conceptual design work is completed.
(2) The planning chronology is contained in Attachment V-5. Program
and Field Element should supplement this chronology with internal
required actions and include the supplemental chronology in their
organizational document and procedures that implement this Order.
b. Requirements and Procedures.
(1) Receipt of List of Candidate Projects at Headquarters.
(a) Departmental Elements originating projects shall submit lists
of candidate projects accompanied by short form data sheets to
the appropriate program division and the Office of
Program/Project Management, prior to February 15 each year for
Current Fiscal Year (CFY) +3 candidate projects. For example,
identification of candidate projects for the 1990 budget shall
be accomplished by February 15, 1987. Heads of Headquarters
Elements who will receive appropriate lists will be the
following:
1 Assistant Secretary for Conservation and Renewable Energy;
2 Assistant Secretary for Fossil Energy;
3 Assistant Secretary for Nuclear Energy;
Vertical line denotes change
V-26 DOE 4700.1
6-2-92
Chg 1
4 Assistant Secretary for Environment, Safety, and Health;
5 Assistant Secretary for Defense Programs;
6 Director of Administration and Human Resource Management;
7 Director of Energy Research; and
8 Director of Program/Project Management.
(b) The information to be included on the short form data sheet is
described in Attachment V-6. An example short form data sheet
is provided as Attachment V-7. A currently updated
construction project data sheet shall be utilized for
continuing projects (i.e., projects previously partially
authorized or submitted for consideration in a previous
budget). Continuing project data sheets submitted at this
time shall have the following information in the upper right
corner of the first page:
“Short Form” Continuing Project
FY 19XX Budgeting Cycle
Submitted 2-1-XX
(2) Headquarters Review and Decision on List of Candidate Projects.
Section 177
(a) Upon receipt of the candidate project lists, Headquarters
program organizations shall review the projects and provide
the Field Elements, not later than April 1 each year,
notification of the tentative project to be considered for
inclusion in the CFY+3 budget. This program organization
review is conducted utilizing the short-form data sheets and
the current 5-year energy program plan.
(b) Field Elements shall proceed with project planning on all
projects submitted on the candidate lists after April 1 each
year unless informed in writing to defer specific projects
contained on the candidate list. It is imperative that
program offices provide guidance to the field on projects that
will not be included in the CFY+3 budget. Strict adherence to
the above procedure will assure the maximum utilization of
planning resources, both personnel and funds. Past experience
indicates that lack of timely guidance has resulted in loss of
planning effort. Program offices shall provide to the Office
of Program/Project Management and Control a copy of their
guidance furnished to the field.
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
V-27
(3) Use of Tentative Project Data for Planning, Programming, and
Budgeting Process by Headquarters Elements.
(a) During April and May, program offices prepare program
documents reflecting the initial approvals of candidate
projects and perform other requirements of the planning,
programming, and budgeting process.
(b) Actions taken are in accordance with the approved planning,
programming, and budgeting system and the annual program
review guidance. Information contained in short form data
sheets is utilized for these actions.
(4) Inclusion of Current Fiscal Year +3 Plant Engineering and Design
Requirements into Current Fiscal Year +2 Budget.
(a) In August of each year, program organizations revise the CFY+2
plant engineering and design line item request to include
CFY+3 requirements as determined through the planning,
programming, and budgeting process. Upon completion of this
action, the program offices shall notify the affected field
element to enable adjustments to be made to the affected
project schedules.
(b) Data provided by the short form data sheets and supplemental
data obtained from the field elements are utilized for this
action. Decisions as to projects for which plant,
engineering, and design funds will be requested evolve from
the planning, programming, and budgeting system.
(5) Headquarters Review of Current Program Status.
(a) During November and December each year, the program
organizations review the tentative construction program for
CFY+2 in light of the approved CFY program and the CFY+1
program as submitted to and adjusted by the Office of
Management and Budget. Upon completion of this review, and no
later than January 1 each year, program organizations shall
notify the field offices and the Office of Program/Project
Management, in writing, of the CFY+2 budget projects for which
planning should continue and actions to be taken on those
projects that will be deferred to later budgets. Field
elements shall adjust their planning activities accordingly.
(b) Information provided by the short form data sheets, the CFY+1
OMB budget, and the current appropriation act shall be
utilized to complete this action. Program organizations shall
assure that field elements are aware of all current plans to
assure that the field can implement the plans if approved.
Vertical line denotes change
Section 178
V-28 DOE 4700.1 Chg 1
6-2-92
(6) Submission of Project Data Sheets.
(a) Prior to March 1 of each year, the field elements shall submit
project data sheets to the appropriate program organization
and the Office of Program/Project Management and Control.
These submissions shall be accompanied by the conceptual
design reports. Projects for which conceptual design was
approved shall have conceptual designs completed and the
report prepared at this time. Such projects for which the
conceptual design report is not completed are subject to being
dropped from consideration by the program organization.
Failure to provide complete project data sheets and/or
completed conceptual design reports on schedule will
jeopardize programmatic support and the validation process.
Support for any late submittal will be at the option of the
outlay program in coordination with the Office of
Program/Project Management and Control.
(b) Project data sheets shall contain all information required by
current Chief Financial Officer instructions. Data that is
not final and will be updated prior to August 1 each year
shall be footnoted. Minimum contents of the conceptual design
report are contained in Attachment V-10. Project data sheets
shall contain the following information in the upper right
corner of the first page:
FY 19XX Budget
Submitted 3-1-XX
(7) Headquarters Validation of Project Data Sheets and Planning,
Programming, and Budgeting Actions.
(a) During the period from March through July, the Office of
Program/Project Management and Control, in coordination with
the program and field offices, shall validate the project data
sheets planned for inclusion in the CFY+2 Internal Review
Budget submittal. Headquarters Elements shall also complete
all the actions required by the planning, programming, and
budgeting system during this period.
(b) Validation shall be accomplished utilizing the project data
sheets, conceptual design reports, and additional project
details provided by the field elements during field meetings
scheduled for validation presentation. Any changes made to
the project data sheets by a Headquarters action shall be
coordinated with the field by the program organization before
the project is included in the budget submittal. Project data
sheets and conceptual design reports shall be utilized in
completing the required planning, programming and budgeting
actions. Validation results shall be
Vertical line denotes change
DOE 4700.1 Chg 1 V-29
6-2-92
reported to the respective program organizations sufficiently
in advance of internal review dates for use in budget
determinations.
(8) Field Element Submission of Additional and Updated Data for Project
Data Sheets.
(a) Field elements shall promptly provide mission and/or updated
information for the tentative CFY+2 budget projects. A
project for which mission or updated information, including
conceptual design reports, has not been received at
Headquarters prior to August 1 of each year will be subject to
withdrawal from the proposed budget.
(b) Information to be submitted is identified as a result of the
validation and other planning, programming, and budgeting
actions. It is obtained as a result of conceptual design
progress, additional studies, and other actions determined and
managed by the field organizations.
(9) Submission of Budget to OMB.
(a) Headquarters takes necessary actions during August and
September to incorporate the latest updated project data
sheets for the approved CFY +2 projects into the budget
document for forwarding to OMB.
Section 179
(b) This action is completed in accordance with the planning,
programming, and budgeting system, and yearly guidance.
(10) Allotment of Current Fiscal Year Plant Engineering and Desire Funds
for Approved Current Fiscal Year +1 Projects.
(a)
(b)
In October of each year, or as soon thereafter as possible,
the plant engineering and design funds contained in the CFY
appropriation for the approved CFY +1 projects shall be made
available to the appropriate field organizations. Field
elements shall accomplish the plant engineering and design in
an efficient and timely manner.
This action is completed by Headquarters in accordance with
the procedures established for disbursement of funds to the
field organizations, which accomplish their required actions
in accordance with their locally established procedures.
(11) Administration and Legislative Actions. During the period from
June through October, several actions take place with respect to
the CFY +1 budget that do not require specific action on
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
V-30
the part of field elements. These actions are included in the
chronology contained in Attachment V-5. The target dates may, in
some cases, occur later than shown for other projects in order to
increase the time available at the project level to produce better
cost estimates. Where different target dates are to be used, new
target dates shall be approved and published by the program office.
(12) Design and/or Construction on Current Fiscal Year Projects.
(a) From October to December, field elements take contractual
actions to start the design and/or construction of the CFY
projects for which funds have been appropriated and received.
(b) These actions are in conformance with Chapter V, Part C,
Execution.
c. Variations for General Plant Projects.
(1)
(2)
(3)
(4)
Project data sheets for General Plant Projects (GPP) contain only a
tentative list of sub-projects to be accomplished with the line
item funds since latitude is allowed in the actual use of these
funds by Congress. However, field elements shall indicate their
current priorities for this line item in each submission of the GPP
project data sheets. While a considerable portion of these funds
will be utilized for unanticipated projects, attention shall be
directed to the planned use of GPP funds in regard to the
institutional plans. Further information on site development and
maintenance is contained in DOE 4320.1B and DOE 4330.4A,
respectively.
Conceptual designs for GPP are not required for inclusion into a
budget. Field elements shall establish their requirements and
procedures for management of the GPP program to include the project
documentation and timing of these actions. It is the intent of
Congress that GPP project funds be utilized during the fiscal year
for which the funds were authorized and appropriated. Large
amounts of funds uncosted for prior years in the GPP account can
seriously affect the GPP funding for future years. Field
procedures shall require that GPP funds are committed, obligated,
and costed promptly.
Field element procedures shall ensure that the GPP program for the
CFY+l is established and plans for accomplishment have been
completed prior to October 1 of each year. Minimal changes to the
GPP program should occur after the beginning of the fiscal year for
which the funds were authorized and appropriated.
GPP funds are limited to projects $1.2 million and under in total
project cost. Field elements, when the current estimate
Section 180
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
V-31
for a GPP exceeds $1.2 million, shall submit a complete report to
the Chief Financial Officer and appropriate program division. The
report shall completely explain the reasons that the estimated cost
now exceeds $1.2 million. The Chief Financial Officer shall comply
with the congressional reporting requirement. The field element
shall not allow the costs of the project to exceed $1.2 million
unless approval is received from the Chief Financial Officer.
d. Variations for Multiprogram General Purpose Facilities.
(1) Because the Multiprogram General Purpose Facilities (MGPF) program
is of extreme importance to the accomplishment of the DOE mission
and the limitation on available funds, it must place different
requirements upon the field organizations. While the project data
sheets are utilized, other documents are utilized in the MGPF
program which may require more detailed information than required
by this Order for other projects.
(2) Specific instructions are provided each year on the information and
documents required for candidate MGPF projects. These instructions
are provided by the Office of Field Operations Management under the
Director of Energy Research.
3. OTHER ESSENTIAL PLANNING REQUIREMENTS. This paragraph discusses planning
requirements that are considered essential and are not contained in the
chronology presented above. While these elements are essential, the timing
of the performance and extent of their execution is dependent upon the
management philosophy and desires of the executing organization. Therefore,
Heads of Field Elements shall be responsible for incorporating the
management elements discussed in this paragraph into their planning policies
and procedures. Field Elements are solely responsible for the documentation
and execution procedures of these elements, except as specified by this
Order.
a.
b.
c.
Preparation of Candidate Project Lists. Field elements shall establish
policy and procedures that define how their candidate project lists will
be determined.
Conceptual Design Plans. The importance of conceptual design cannot be
overemphasized. Guidance on conceptual design, its contents and
reports, is contained in Attachments V-8, V-9, and V-10. Because
completion of conceptual design must be timely, field offices shall
prepare conceptual design plans. Content and procedures are the
responsibility of the Head of the Field Element.
Architect-Engineer Selection Plans. Past experience has shown that
project schedules have been delayed due to lost time in completing the
architect-engineer selections and awarding the contract. Planning for
this effort will mitigate this problem.
Vertical line denotes change
V-32 DOE 4700.1
3-6-87
d. Design Criteria Plans and Reviews. Delays in projects occur due to
incomplete design criteria. Field elements shall prepare and implement
plans and procedures to ensure that design criteria are properly
utilized.
e. Management Plan Preparation and Change Procedures. Construction
projects cannot be effectively managed without a management plan. Field
elements shall have specific procedures for the preparation, change, and
use of these plans. These procedures shall provide for timely
initiation of plan preparation, completion, and implementation.
DOE 4700.1 Chg 1
6-2-92
V-33
PART C - EXECUTION
1. PURPOSE.
Section 181
a. The execution phase begins upon receipt of the detailed design and/or
construction funds at the level responsible for project management and
continues until the completion and closeout of the construction effort.
b. Since project management is the responsibility of the Head of the Field
Element, considerable latitude in the establishment of procedures for
the execution phase has been left to the discretion of the Head of the
Field Element. Field managers shall establish and update, as required,
written procedures which their offices will follow in fulfilling their
construction project execution responsibilities. Copies shall be
furnished to the Office of Program/Project Management and Control.
Field office adherence to their established procedure shall be an area
of concern during routine Headquarters review and assessment visits to
the field organizations.
c. The specific activities and the sequence in which they occur vary
depending upon the project characteristics and category. The field
elements should consider establishing logic diagrams for each project
category and including these logic diagrams in their project management
directives.
2. DESIGN.
a. Design Objectives. Design objectives shall be:
(1) Achieving minimum construction costs consistent with programmatic,
environmental, security, and safety requirements;
(2) Achieving technical adequacy;
(3) Achieving optimum economy in operation and maintenance; and
(4) Assuring that appropriate consideration is given to the expected
period of use; quality construction practices; energy conservation,
decontamination, decommissioning, and quality assurance
requirements; and the appearance of completed facilities.
b. Design Methods. Considerable improvements in the method of design
accomplishment are emerging with the use of computer-aided design.
Field organizations shall utilize the advantages of computer-aided
design when appropriate.
c. Tradeoff Studies. Tradeoff studies are an essential element of the
design effort required to achieve the design objectives. Construction
project
Vertical line denotes change
V-34 DOE 4700.1
3-6-87
managers shall assure that appropriate use of tradeoff studies is made
during the design of facilities.
d. Importance of Criteria, Codes, and Standards. In the past, projects
that have had the most problems during the construction phase have been
those for which a project design criteria package did not exist, was
incomplete, or was prepared after the design had started. Lack of an
adequate criteria package prior to the start of design causes delays in
the design and construction phases of the project. It is most important
that the project design criteria provide a clear, concise, and
professional description of the design requirements without the need to
provide an extensive list of other documents as part of the criteria or
numerous cross-references to other documents. Project-specific design
criteria should, whenever possible, be included entirely within the
package, thereby reducing references to other documents to a minimum.
This requires that considerable effort be expended on the preparation of
the criteria document. Expenditure of this effort during the planning
phase, prior to the authorization and appropriation of the funds, can
shorten the design and construction time for the project. Architect-
Engineer evaluation boards should be assigned, as a task, to review the
criteria package. This procedure provides three advantages:
Section 182
(1) Better assurance that the criteria package is complete and that
there is time to improve it, if necessary;
(2) Shortening the time required for the award of the architect-
engineer (A-E) contract after receipt of funds; and
(3) Better matching of the required architect-engineering
qualifications to the requirements of the project,
e. Preliminary Design (Title I).
(1) Scope. The preliminary stage of project design utilizes the
conceptual design and/or design criteria that have been prepared
for the project as a design basis. Sufficient design needs to be
performed during Title I work to firmly fix (freeze) the project
scope and features and further develop costs and schedules. Title
I design generally includes:
(a) Conduct of preliminary (tradeoff) studies, including
evaluation of alternative design approaches;
(b) Definition of the project design criteria and establishment of
quality levels for systems and components in greater detail or
revision to reflect data and information developed (during
title I design), to be applied in the follow-on Title II
design;
detail and
of new
Development of outline specifications for construction; and
specifications for equipment procurement;
DOE 4700.1
3-6-87
(c)
(d)
Expansion of conceptual design drawings in greater
development of additional drawings, or development
drawings based on new design concepts;
V-35
(e) Additional analyses of health, safety, environmental
and other program aspects;
protection,
(f) Development of preliminary estimates of construction labor,
equipment, and material quantities and identification of long-
lead procurement or other potential labor or material supply
problems;
(g) Development of more accurate project cost estimates, time sched-
ules for project performance, and methods of construction
performance;
(h) Further evaluation and selection of energy conservation measures
and energy sources of supply;
(i) “Preliminary Safety Analysis Report,” if not in conceptual
design report;
(j) Preparation of a Title I design summary; and
(k) Other work as required.
(2) Performance.
(a) In Title I, the design criteria are defined in greater detail
and drawings for the approved project concept are expanded with
more detailed information, together with additional required
drawings. Also, further refined descriptive information and
more detailed outline specifications are developed that will
serve as the firm basis to proceed with definitive design (Title
II).
(b) From the more detailed drawings and information developed, more
accurate cost estimates and project schedules are developed.
This may reveal the need at this stage of design for revisions
in scope or project features to keep the project within
authorized funds.
(c) The outline specifications should be sufficiently detailed to
permit determinations of compliance with DOE 6430.1.
V-36 DOE 4700.1
3-6-87
(d) The preliminary estimate of project costs should be sufficiently
detailed by components, and in units and unit costs, to facili-
tate review and evaluation.
(e) An important concern during the preliminary design is to assure
that proper considerations are being given to protection of the
environment. Project managers shall assure that the project
actions concerning the environment (i.e., environmental assess-
ment and/or impact statement) are properly coordinated with the
Section 183
Title I design. Proper integration of the environmental con-
cerns into the Title I design will prevent project delays and
design and construction changes later in the project. The above
also applies to safety considerations. A preliminary safety
analysis report should be a product of the Title I design, if
required, and not completed during conceptual design.
(f) Design coordination is needed between the field organization,
the operating contractor, and the design contractor, and with
Headquarters participation, where appropriate, to assure that
the design contractor fully understands the project require-
ments, cost and schedule constraints, and the operational needs
of the project, and to adequately direct and monitor the design
contractor’s efforts and performance. Periodic progress and
manpower reporting by the design contractor is required for
management purposes.
(3) Title I Design Summary.
(a) Definition and Purpose. The Title I report (summary) or updated
conceptual design report, as appropriate, is an overview and
record document of preliminary engineering and project manage-
ment planning, reflecting completed Title I design and usually
prepared under architect-engineer services or by the operating
contractor. This document serves two purposes. The first and
primary one is to provide the field office manager with summary
design information for approval prior to authorizing start of
definitive design (Title II). The second is to provide the
Headquarters program office and other interested offices with
the necessary project information to assist in program planning,
improving policy, and criteria guidance for future projects.
This summary will allow the field office manager to determine
that:
1 The project, as scoped, is consistent with the project as
authorized by the Congress or as previously authorized by the
field organization.
2 Programmatic or other requirements are being adequately
satisfied.
DOE 4700.1
3-6-87
V-37
3 Applicable design criteria, incorporating simplicity and
economy, are being followed in design.
4 Reasonably uniform standards of size, design, and materials
of construction are being applied, and new construction
will be compatible with existing structures and facilities
where required.
5 Project cost estimates and schedules for performance are
reasonable.
6 Safety and environmental impact assessments have been made,
hazard and impact prevention measures are being applied,
and compliance with environmental health and safety
standards and guidelines will be achieved.
7 Applicable energy conservation and provisions for the
handicapped regulations and guidelines are being followed.
(b) Projects Requiring Title I Design Summaries. Title I design
summaries are required for:
1 Any construction project for which the total estimated cost
exceeds $250,000 when financed from the construction
projects portion of the budget.
2 Any project involving the design, procurement, fabrication,
and installation of equipment of experimental facilities in
connection with:
a Any equipment project of $1 million or more in estimated
cost that is funded from the “capital equipment not
related to construction” portion of the budget involving
budget installation costs of $250,000 or more.
b Any experimental project or reactor test loop of $1
million or more in estimated cost.
Section 184
3 Field office managers may, on some projects, elect to
utilize a one-step design process without a separate
distinction between Title I and Title II design. If this
method is utilized, formal periodic review shall be made
and properly documented to assure that the project
objectives are being met. One of these formal reviews may
be substituted for the Title I design summary, provided the
project manager or field office manager approves the
selected design review documents. The review selected as
being the substitute for the Title I design summary shall
be performed prior to the design reaching the 50 percent
completion milestone. The guidance
V-38 DOE 4700.1 Chg 1
6-2-92
provided herein pertaining to Title I design summaries
should be considered in determining the format and content
of the design review to be substituted for the Title I
design summary.
(c) Contents of a Title I Design Summary.
1 For projects above $1.2 million in Total Project Cost
(TPC), the Title I design summary should contain the
applicable information listed in Attachment V-11, arranged
as convenient to the field organization.
2 For all projects requiring summaries, the Title design
summary may consist of the completed “Title I Design
Report” or “preliminary proposal” submitted by the
operating contractor, or any other document or documents
utilized by the field organization to make the decision to
proceed to Title II, provided it contains the applicable
information listed in Attachment V-11, and a procedure is
followed that requires the project manager of field office
manager’s approval.
3 Since the primary purpose of the Title I design summary is
to provide a decision basis for the Head of the Field
Organization, the contents of the summary must be
determined by the individual. Attachment V-11 is provided
only as a guideline to assist the field managers in
selecting the contents of the summary. Field managers
shall establish procedures that allow for determination of
the summary contents for each project. It is suggested
that the project management plan specify the form, source,
and contents of the design summary.
(d) Dividing or Grouping Project for Title I Design Summaries. If
desired, preparation and review of Title I design summaries
for large or urgent projects may be handled in stages with the
initial proposal covering the concept and general layout of
the overall project and proposals on the components being
submitted as soon as preliminary design is completed on each.
1 The scheduling of summaries for components of a major
project may be arranged to fit the proposed construction
schedule. The information furnished at each stage should
include the data needed for authorizing the start of
preparation of working drawings and specifications for the
components and should show how the component fits into the
overall project.
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92 V-39
2 Related portions of several projects may be grouped into a
single summary if this provides a logical distribution of
the work and simplifies preparation and review of the
summaries.
(e) Design Summary Procedures.
1 Field office managers should establish procedures for
review and approval of all design summaries. Design
summaries should be approved prior to authorization of
detailed (Title II) design. A copy of the approved design
summary shall be contained in the project files.
Section 185
2 Copies of each design summary for major projects and major
system acquisitions shall be submitted to each of the
following Headquarters organizations immediately upon
approval of the summary by the field organization.
a Appropriate program division;
b Director of Program/Project Management; and
c Deputy Assistant Secretary for Environment, Safety, and
Health.
3 Headquarters submission of design summary for line item
projects (over $1.2 million) other than major system
acquisitions and major projects shall be on an as-requested
basis by the Headquarters Elements. Design summaries for
GPP shall not be submitted to Headquarters.
4 Design summaries provide the Headquarters offices with a
source of information that will assist them in improving
policy and criteria and should enable more enlightened
program decisions. Summaries shall be submitted by cover
letter providing information considered by the field office
manager to be of importance to the Headquarters Elements in
programming and policy actions. The letter serves as a
“lessons learned” report during the project’s execution and
allows early application of the “lessons learned” to other
projects and timely changes to be made to policy criteria
and methods.
5 If modifications in a project involve significant changes
in scope, TEC, schedules, or type of construction, a
revised design summary shall be prepared and approved by
the field office manager. Procedures for revised summaries
shall be the same as for the basic summary.
Vertical line denotes change
V-40 DOE 4700.1
3-6-87
f. Definitive Design (Title II).
(1) Scope. Title II definitive design (sometimes referred to as
“final” or “detailed” design) is performed by an architect-engineer
firm or, in limited circumstances, by the operating contractor who
utilizes the approved Title I design and the revised project design
criteria as the design base. Completion of the definitive design
ends the design phase of a project and normally allows the
beginning of the construction phase. Definitive design normally
includes:
(a)
(b)
(c)
(d)
(e)
(f)
(g)
Restudy and redesign work resulting from changes as may be
required from the preliminary design;
Development of final (working) drawings and specifications for
procurement and construction;
Estimate development of construction, labor, equipment, and
material quantities;
Development of detailed estimates of the cost of construction,
procurement and construction schedules, methods of
performance, and identification of work packages;
Preparation of analyses of health, safety, environmental, and
other project aspects;
Identification of test plan and permit requirements,
preparation of procurement plan, and determination of utility
service requirements in coordination with the operating
contractor and/or the supply utility companies; and
Other work as required.
(2) Performance.
(a) The scheduling of definitive design shall be based upon a
detailed analysis of a project and its component parts.
Engineering work involved in defining equipment and materials
having long-lead procurement time shall be scheduled for early
completion, in order that procurement can be initiated prior
to the construction contracting when timing would make
inclusion of the procurement as part of the contract
infeasible. When construction is to be performed under a
number of fixed-price contracts or under a cost-plus-fixed-fee
contract, construction drawings and related documents should
be scheduled in the sequence required for construction
operations.
Section 186
DOE 4700.1
3-6-87
V-41
(b) Of major assistance in scheduling the performance of definitive
design is the early establishment of detailed schedules of the
need for drawings and specifications to support construction and
procurement. Such detailed schedules assist in determining
engineering manpower requirements and assure that completion of
individual documents meet procurement and construction
schedules.
g. Periodic and Final Design Reviews. As a vital part of the overall manage-
ment of the project, periodic design reviews need to be performed during
the preliminary (Title I) and definitive (Title II) design to assure that
project development and design are proceeding in an orderly manner; assure
that the project will satisfy program and operating objectives; review
performance, schedules, and costs; identify potential and real problem
areas; and initiate action for timely solutions and corrective measures.
Procedures for conducting, monitoring, and controlling these necessary
design reviews must be developed by the Heads of the Field Elements.
In addition to procedures for design review, Heads of the Field Element
shall develop procedures for the distribution and approval of design
documents.
h. Design and Construction Scheduling and Methods of Performance.
(1) Scheduling.
(a) Considerations Pertaining to Performance Time of Contractors and
Effects on Cost. To the extent possible, schedules for engi-
neering, procurement, and construction services shall be estab-
lished concurrently to assure assignment of adequate time for
performance and to properly coordinate the accomplishment of the
services. Construction completion of project elements shall
satisfy operating requirements, including time for tests and
adjustments prior to operation. If required completion dates do
not permit normal performance periods, the available time must
be allocated to achieve maximum overall economy, based on a
careful determination of the feasibility and cost of performance
of each service in less than normal time (i.e., with premium
time). Sometimes the total time available may not, by any
reasonable allocation, allow completion of all design prior to
starting construction. Under such conditions, the design shall
be scheduled so that logically separable portions of the work,
such as sitework, foundations, superstructure, mechanical, and
equipment installation can be awarded as separate contracts,
bearing in mind that for maximum effectiveness a contractor
should have, subject to security limitations, full control of
the area in which he is working. However, it may be necessary
to perform both engineering and construction on a cost-plus-
fixed-fee basis so that both can proceed concurrently. Where
plans involve use of more than one fixed-price contract for
V-42 DOE 4700.1
3-6-87
(b)
construction, special care should be taken to assure that the
plans and specifications clearly and completely define the scope
of work to be accomplished under each contract. Sequential
fixed-price contracts should be scheduled to permit orderly
progress and timely completion.
Section 187
Considerations Pertaining to Performance Times Required to
Accomplish Administrative Actions. Past experience indicates
that schedule delays have occurred on many projects due to the
insufficient allowance for the time required to accomplish the
administrative functions on the project. In scheduling the
work, proper consideration shall be given to the time required
for such activities as the selection of the architect-engineer
selection of a cost-plus-fixed-fee construction contractor,
administrative approval requirements, and bidding and award of
fixed-price construction or procurement contract(s). The field
office manager shall determine the type and number of
architect-engineer contracts to be used and the most appropriate
type of contractual arrangements required. During the course of
preliminary and definitive design, the field office manager
reviews and firms up the preliminary determination as to the
type and number of construction contracts to be used. Field
office managers should ensure that realistic times are scheduled
for selection of architect-engineer and construction managers,
appropriate administrative approvals, and award of procurement
and construction contracts. Appropriate procedures and controls
shall be established and utilized for the accomplishment of
these administrative functions that will ensure on-time
completion of these actions.
(c) Use of Logic Diagrams. During the entire process of scheduling,
the use of logic diagrams can be extremely helpful to the
planner or scheduler to recognize the relationships between the
various actions required on a particular project. It must be
recognized that perhaps the largest benefit from the use of the
performance evaluation review technique (PERT) or critical path
method (CPM) can be gained during the early phases of project
design. Design decisions and regulatory requirements during the
design phase may create considerable changes to the project
logic. In some cases, a design or other decisions may have such
an effect on the project cost and schedule to require a modifi-
cation or reversal of the decision. For this reason, the proj-
ect manager must continually revise and utilize the logic
diagram.
(2) Methods of Performance.
(a) General. In determining the manner and method of performance,
consideration should be given to constantly evolving innovations
which may result in improvements in the traditional methods of
DOE 4700.1
3-6-87
V-43
design and construction of buildings and facilities required for
accomplishment of programs. New techniques and new ways of
doing things may provide solutions to new challenges and prob-
lems which may arise. New practices should be adopted which
will reduce design and construction time; use of other cost
saving techniques should be maximized; and new methods of
contracting should be considered which will produce economies in
construction costs. Use of performance-type specifications may
permit the application of new technology and produce improved
designs to meet requirements. In adopting any new techniques or
methods, care should be exercised to assure that the design cri-
teria are satisfied, and that the results will be achieved
without any decrease in desired quality and without any sacri-
fice in essential requirements. Methods of performance and
scheduling must be considered together, comparing the advantages
of a method with the effect it has on the schedule and cost.
During the design phase of a project, this interaction between
these two important actions must be continually considered.
Construction contracting and erection methods can greatly affect
the design method and sequence and should be determined early in
the design phase. Field office managers must ensure that provi-
sions for the above considerations are included in the project
management plan.
Section 188
(b) Cost Estimates. The importance of continual development of the
project cost cannot be overemphasized particularly under the
current market conditions of rapidly rising costs. Inclusion of
“nice to have” features in the design, and failure to consider
improved construction methods will contribute to excessive
project cost growth. Consideration of cost during design eval-
uations can limit this growth, as well as facilitate the prep-
aration of the formal cost estimates required during the life
of a project. Further information and guidance on cost esti-
mates is contained in Chapter II of this Order and DOE 5700.2C.
(c) Bidding and Award Activities. Projects may be delayed by the
failure of bidding and award activities to be timely. The
reasons for this delay can be a result of unrealistic allowance
of time in the schedule for these activities or lack of atten-
tion to the accomplishment of these functions. Both of these
reasons can be negated by the establishment of advance planning
procedures within the field organizations for accomplishment of
these tasks. The procedures established must contain controls
or milestones to inform the project manager of delays so that
immediate corrective action may be taken. Since these activi-
ties are of short duration in relation to the total schedule,
many of the possible problem areas must be anticipated prior to
V-44
the start of the actual bid
nique is the utilization of
DOE 4700.1
3-6-87
and award functions. A useful tech-
a checklist by the project manager
items as availability of funds, bids containing proper infor-
mation to allow preaward actions, availability of personnel for
preaward audit, and possibility of bidding time being extended.
In many cases, extension of the bidding and award activities are
just accepted as fact without corrective actions attempted.
Proper procedures and prior planning can allow the bidding and
award activities to be accomplished in the least possible time.
prior to the start of the bidding and award containing such
(d) Change Control Procedures.
1 Change control procedures for both design and construction
must be established early in the execution process. Delays
in processing design changes can seriously affect the project
progress. The planned or desired procedures should be
included or referenced in the project management plan prior
to the start of the execution phase. If consideration for
contractor’s method of change control is given and his method
accepted, the modifications must be included in an update of
the project management plan. The adopted procedures for
changes should include rigid provisions for reporting the
progress of changes timewise by the project manager’s organi-
zation, in addition to the normal change control reporting
provisions. Standard change controls procedures shall be
established for projects not having specific project managem-
ent plans. These procedures shall include authorities and
responsibilities for changes during both design and construc-
tion.
2 Particular attention must be paid to the time when certain
changes should be prohibited to allow completion of the work.
Failure to establish design change procedures will almost
guarantee delay of the project. During construction, the
project manager should have the authority to prevent changes.
During this period, changes should not be allowed unless they
are operationally required, to meet safety requirements,
and/or result in cost savings.
Section 189
i. Traditional Engineering Services. These services which encompass Titles I
and II as defined above, are normally performed by architect-engineer
firms under DOE prime or subcontract arrangements. To obtain the highest
qualified professional services available, Departmental Elements shall
comply with the policy and procedure set forth by the Brooks Bill, (40
U.S.C. 471, et seq.); DOE implementing regulations; and OMB Circular A-76.
Operating contractors may perform Titles I and II work when it is
determined by the field office manager to be in the best interest of the
Government and is not a violation of the policy and procedures set forth
by the references cited above.
DOE 4700.1 V-45
3-6-87
(1)
Projects for which the operating contractor might perform design services
include those for which the design involves a high degree of interfacing
with existing equipment, operations and/or facilities; work is closely
tied to ongoing research and development; and/or special expertise and
knowledge is required which is generally only available to the operating
contractor.
3. CONSTRUCTION.
a. Fixed-Price Construction Contracts. As previously mentioned, allowance
shall be made for the time required for bidding, bid evaluation, award,
and subsequent mobilization by the contractor. The contractor must be
assured adequate work space and free access to his work area within
security limitations. In situations where several independent contractors
will be performing work in the same area at the same time, detailed
planning must be performed prior to the award of the contract to develop
procedures to handle the unavoidable conflicts. These procedures should
be included within the contract. The construction planning effort should
attempt to minimize these situations. Government efforts should be
devoted to ensuring that the contractor is free to manage his effort.
Government functions should be done on time with no unnecessary disruption
to the contractor’s plan.
(2)
Equipment Furnished by Others. When equipment or materials are to be
installed by a fixed-price construction contractor but are procured
by other participants, the field organization shall take necessary
actions to assure that deliveries comply with schedule set forth in
the construction contract, to minimize requests for time extensions
and cost increases.
Indoctrination of Contractor. After the contract has been awarded,
the contractor should be advised as to:
(a) The extent of authority and responsibility of the contract
administrator, the operating contractor and the
architect-engineer, and any other project participant;
(b) The administrative procedures for review and approval of shop
drawings;
(c) The administrative procedures for progress payments;
(d) The administrative procedures for changes to the contract;
(e) Contract provisions for special safety, environmental protec-
tion, security, quality assurance, and other requirements for
performance;
(f) The conditions specified by the contract under which work shall
be performed and accepted; and
V-46
b.
DOE 4700.1
3-6-87
(g) The reporting procedures required by the contract, and
coordination and understanding of the contractor’s cost and
schedule control system by all appropriate project management
personnel.
Section 190
(3) Cost and Schedule Breakdown. After the award of the contract, the
contractor shall be required to submit proposed schedules for the
major features of the work and for the overall project, as well as a
cost breakdown covering each element or subdivision of the schedule.
The schedules and the breakdown estimates shall be reviewed by the
project manager and/or the architect-engineer and approved by the
contracting officer. Upon approval, the breakdown estimates and the
weight factors incorporated in the schedules shall be used as a basis
for progress payments. Fixed-price incentive fee contracts normally
will be governed by cost and schedule control requirements.
Cost Reimbursement Construction Contracts (Fixed or Incentive Fee).
(1)
(2)
(3)
Equipment Furnished by Others. As with the fixed-price contract, it
is necessary to assure that equipment or materials furnished by
others is supplied in accordance with delivery schedules. The cost
reimbursement contract is more flexible in this respect; however, the
flexibility has a cost associated with it. Rescheduling work,
shifting personnel, and disrupting plans as a result of missed deliv-
eries all cause an increase in the total project cost and possibly
extend the project completion date. It must be recognized that the
responsibility for assuring that availability of equipment and
supplies not furnished by the contractor remains with the Government
project personnel or the construction manager and not on the
contractor.
Advisory Services to the Architect-Engineer. Early selection of a
cost-reimbursement contractor is desired because he can contribute
practical and economical suggestions for inclusion in the plans and
specifications, and can aid in establishing a coordinated design and
construction schedule. If a construction manager is employed for the
above purposes, then early selection of the cost-reimbursement
construction contractor may not be necessary or appropriate.
Separation of Work. If it is determined that cost-plus-fixed-fee
construction contract should be utilized, buildings or elements
should be separated whenever practicable from the main contract and
handled on a fixed-price basis, either as prime contracts with DOE or
a subcontract under the cost-reimbursement contractor. As many ele-
ments of the contract as practicable, such as subassemblies, rein-
forcing steel and ductwork, should be obtained on a fixed-price basis
utilizing established industry sources. These elements should be
fabricated off site whenever operationally and economically
advantageous.
DOE 4700.1
3-6-87
V-47
(4) Experience Gained on Similar Project. In cost-reimbursement
contracts, Government experience or “lessons learned” on similar
projects should be freely provided to the cost-reimbursement
contractor. This is desired since any problems avoided by use of
this experience by the contractor results in a direct benefit to
the Government.
(5) Indoctrination of Contractors.
(a) Initial discussion, after the contract is awarded, with the
construction contractor should cover the following topics:
1 Indoctrination of the contractor’s key personnel with
policies, procedures and discussion of Government
management interface with contractor’s management plan;
2 Clarification and understanding of the responsibilities and
authorities of the various participants.
3 The architect-engineer,
are authorized to issue
limitations thereon;
4 Procedures for progress
Section 191
DOE representatives or others who
field instructions and the
payments;
5 Procedures for changes to the contract;
6 Procedures for review and approval of shop drawings,
equipment, and material;
7 Conditions specified by the contract under which the work
shall be performed and accepted, to include environmental,
health, safety, security, quality assurance, special
safety, and other requirements for performance; and
8 Administrative requirements including personnel, supply,
fiscal and progress reports, and records.
(b) During these discussions, items such as organizational
pattern, key personnel to be assigned initially, schedule of
assignments for additional personnel, and recruitment program
are resolved. The contractor shall be furnished with
applicable Departmental regulations and procedures.
(c) Emphasis should be placed on the contractor’s management plan.
Specific requirements such as functional organization and
personnel requirements, reporting and records procedures,
subcontract procurement, construction plan, quality assurance
plan, manpower scheduling, cost control, and estimates should
be discussed. Discussion and resolution of problems early in
the contract help assure that the contractor establishes a
sound
V-48 DOE 4700.1 Chg 1
6-2-92
plan at an early date. A sound plan understood by both the
Government and the contractor helps assure orderly and
economical construction.
(d) Contractor personnel and industrial relations reporting must
be discussed for those projects to which this reporting system
is applicable. Generally, these reports are applicable only
to projects being accomplished by onsite contractors. Project
applicability and contracts requiring reports are defined in
DOE 1332.2.
(6) Contractor’s Procedures.
(a) The contractor should be required to develop subcontracts and
purchase orders and related document forms as soon as possible
after award of the contract. He/she may be requested to
prepare other procedures covering the work to be accomplished
within organization units, and indicate the distribution of
documents such as construction drawings and specifications,
subcontracts, requisitions, purchase orders, shop drawings,
cost estimates, cost reports, progress reports, and results of
safety inspections and meetings. The procedures may be
especially tailored for the project or may be the contractor’s
standard procedures, provided that they meet the needs of the
project manager.
(b) The contractor must assure that his/her accounting and
reporting systems provide current cost data to management in
accordance with the contract. The contractor’s accounting
system must be capable of providing the necessary costs to
allow the field office to report completion costs and
recording of capital investment for both facilities and
installed equipment in accordance with applicable procedures.
(c) The contractor shall develop and furnish his/her plans and
procedures on quality assurance as directed by the field
element.
(d) The field organization, with assistance from Headquarters as
required, shall review all of the procedures for adequacy and
compliance with Departmental policies and procedures and, if
satisfactory, approve the procedures. Revisions shall be made
by the contractor as appropriate and shall also be reviewed
and approved by the field element.
(7) Subcontract Planning and Scheduling. As design develops, the
construction contractor or construction manager, depending upon the
project team structure, analyzes the elements of the project to
determine the most feasible method of construction. Based on
design
Section 192
Vertical line denotes change
DOE 4700.1
3-6-87
schedule, necessary construction period, established completion
dates, and nature of the work, the contractor usually recommends
V-49
to
the field element the type (fixed-price or cost), scope, and sched-
uled starting and completion dates of each proposed subcontract.
The field element shall review these recommendations for compliance
with the Federal and DOE procurement regulations, coordinate the
subcontract requirements with design schedule, and approve the
types and numbers of subcontracts to be utilized.
(a) Fixed-Price Construction Subcontracts are to be utilized to the
maximum extent feasible. Such subcontracts may cover a complete
building, group of buildings, or such work as excavating, steel
erection, elevator installation, roofing, and so forth. In sub-
contracting to fixed-price contractors, consideration should be
given to the factors covered in paragraph 3a, above.
(b) Cost-Reimbursement Construction Subcontractors should be util-
ized for specialty work when fixed-price subcontracts are not
feasible. If cost-reimbursement subcontractors are to be used,
their early selection is desirable to assist the prime contrac-
tor in planning, to initiate material takeoffs, and to initiate
requisitions and purchase orders.
(8) Procurement Planning and Scheduling.
(a) The orderly delivery of equipment and materials at the site of
the construction work, in a sequence that meshes with the
installation schedule, is of major importance in meeting the
required project completion dates at minimum cost. Receipt of
equipment and materials subsequent to the time scheduled for
installation tends to decrease the drive and effort of construc-
tion forces and thereby becomes a major contributing factor to
decreases in labor productivity.
(b) The contractor determines equipment and material delivery sched-
ules necessary to meet the required completion dates, taking
into consideration times required for such activities as prep-
aration of bid invitations and requisitions, bidding, shop
drawing preparation, reviews and approval, fabrication, and
transportation. The contractor provides the field elements
with a schedule of milestones in his plan for completing the
construction.
If scheduled deliveries of items procured by other participants
do not meet scheduled installation requirements, the contractor
advises the field element as to the required delivery dates.
The field element then takes action to expedite delivery to
meet the installation requirements.
(c)
V-50 DOE 4700.1
3-6-87
(d) To coordinate deliveries to the project, the administration of
purchase orders placed by other participants for long lead-time
items may be assigned to a contractor or subcontractor. This
administration may include expediting, receiving, inspection and
acceptance, and recommendations for partial and final payments.
(e) Prompt receipt and approval of shop drawings are essential to
orderly fabrication of equipment and timely detailing of foun-
dations and connections.
(f) For projects involving a considerable number of items procured
by other participants, the procurement management function could
most likely be best accomplished by a construction manager.
(g) For projects in which excess Government equipment and materials
could be utilized, the project manager should require the
contractor to establish procedures for reviewing “excess” tabu-
lations and obtaining excess items.
Section 193
(h) Priority and allocation authority shall be exercised in accord-
ance with the defense materials and priorities system regula-
tions. Assistance in exercising this system can be obtained
from the Director of Procurement and Assistance Management.
Special assistance should be requested from the Director of
Procurement and Assistance Management when the defense materials
and priorities system procedures have proven ineffective.
(9) Construction Equipment Requirements. Delivery and installation sched-
ules for building equipment and materials assist in determining
construction equipment requirements. The contractor establishes the
construction equipment required by his own forces and by any cost-
reimbursement subcontractor. If the field organization approves
these requirements, equipment may be made available from excess
stocks of the Department and other Government agencies, by rental
from the contractor, or by rental or purchase by the contractor. The
appropriateness of rental versus purchase requires detailed analysis
of requirements. (See Federal Property Management Regulation,
Chapter 101-25.5.)
(10) Construction Plant.
(a) The contractor recommends for field element approval locations
for shops, warehouses, and other temporary construction facili-
ties. These facilities should be located to minimize congestion
within the construction area and to permit efficient flow of
materials. The field element will consider the requirements
of other participants and activities in the area when reviewing
the recommendations.
DOE 4700.1
3-6-87
V-51
(b) Project facilities such as roads, railroads, water supply,
sewage collection and disposal, electrical, telecommunications,
alarm systems, shops, and warehouses that can be utilized by the
construction forces should be completed early to permit con-
struction force utilization.
(11) Manpower Planning and Scheduling.
(a) As a guide to establishing and scheduling manpower requirements,
the field element should assure that the contractor analyzes
existing labor conditions, anticipated productivity, avail-
ability of housing, and other factors. Considering required
completion dates, the contractor recommends the length of
the basic workweek and the number of shifts. Every effort
should be made to avoid extended workweeks. The field element
shall approve the basic workweek and the number of shifts
to be used on the project. This effort should be reflected in
the contractor’s manpower plan.
(b) The contractor develops overall manpower schedules by trades
covering his own work and the work to be performed under the
cost-reimbursement and fixed-price subcontracts. To the extent
possible, manpower peaks of short duration should be leveled.
The manpower schedules by trades will dictate the supervisory
personnel required.
(c) The field element shall assure that the contractor establishes
procedures for, and complies with, all mandated labor laws
and regulations such as equal opportunity in employment and
minority employee goals. All labor relation aspects shall be
given consideration.
(12) Cost and Schedule Control.
(a) Since the contractor may utilize his own cost and schedule
control system, which may have been established prior to award
of the contract as meeting the DOE criteria, the field element
should ensure that project personnel understand the contractor’s
system. On some large projects, assuring this understanding
may require that the contractor provide some training to the
Government, architect-engineer, construction manager, and
operating contractor personnel as the case may be. Initial
understanding of the system by all personnel involved can
help minimize problems during the completion of the project.
Section 194
(b) The contractor prepares his subcontract, procurement, construc-
tion, and manpower schedules, and when directed by the field
element, consolidates these schedules with those of other
participants to develop overall project schedules, including
V-52 DOE 4700.1
3-6-87
networks such as CPM and PERT. Work of the contractor’s own
forces is integrated with the work of subcontractors and offsite
fabricators, and with the scheduled deliveries of equipment and
materials.
(c) The contractor estimates direct labor costs, direct equipment
and materials costs, and indirect costs, including administra-
tion,to determine the estimated total costs he will incur.
This process is applied,to each physical unit (work package) of
the project as established by the project management plan.
(d) The field element shall review the contractor’s cost esti-
mates for adequacy, and after approval, consolidate the esti-
mated costs of the work of all participants to arrive at the
overall project estimate. In establishing this estimate, the
field element shall reconcile any difference between estimates
prepared by the architect-engineer, construction, and operating
contractors.
(e) Depending on the complexity of the project and the field ele-
ments management plan, the greater portion of the above work
may be assigned to a construction manager.
c. Inspection (Title III).
(1) The organization or project manager may elect to have inspection
services performed by the architect-engineer construction manager, or
with in-house personnel. Inspection services shall not be performed
by the construction contractor, and special conditions apply to the
performance of inspection services by the architect-engineer.
(2) Inspection Services. Under Title III contract services, the contrac-
tor generally will:
(a) Furnish and maintain governing lines and benchmarks to provide
horizontal and vertical controls to which construction may be
referred;
(b) Verify all vendors’ shop drawings to assure conformity with the
approved design and working drawings and specifications;
(c) Inspect construction workmanship, materials, and equipment, and
report on their conformity or nonconformity to the approved
drawings and specifications;
(d) Make or procure such field or laboratory tests of construction
workmanship, materials, and equipment as may be required.
DOE 4700.1
3-6-87
V-53
(e) Prepare estimates of reasonable amounts of increase or decrease
in contract price and/or contract completion time for contract
modifications, evaluate proposals submitted by the construction
contractor for such contract adjustments, and make recommen-
dations for use in negotiating;
(f) Prepare reports and make recommendations on status of deliveries
of materials and equivalent as may be required;
(g) Prepare monthly and other reports of the progress of construc-
tion, as may be required, and partial, interim, and final esti-
mates and reports of quantities and values of construction work
performed for payment or other purposes; and
(h) Furnish reproducible “as built” record drawings and marked-up
specifications showing construction as actually accomplished.
(3) Performance of Inspection.
(a)
(b)
Scheduling. Inspection schedules shall be based on the con-
struction schedules and the quality assurance requirements of
the project as set forth in the project quality assurance plan.
General Procedures.
Section 195
1 Inspection of construction work, including procurement and
installation of associated equipment, shall be conducted in
all cases prior to acceptance, and shall be consistent with
the practices and procedures set forth in this section.
2 Inspection should be made at such times and places as may be
necessary to provide the degree of assurance required to
determine that the materials of services comply with contract
and specification requirements, including quality level
requirements.
3 The type and extent of inspection needed will depend on the
nature, value, and functional importance of the project and
its component parts. In determining whether inspection of
manufactured articles should be made at the source (vendor’s
plants) or destination (construction site), the criteria con-
tained in FAR 46.402 and 46.403 shall be followed.
4 Inspection requirements and testing required to be performed
by the contractor or vendor shall be clearly established in
the contract documents. Specific instructions shall be
issued to define the scope of authority delegated to inspec-
tors and the specific duties and responsibilities assigned to
V-54 DOE 4700.1
3-6-87
them, and concerned contractors and vendors shall be fur-
nished copies of such instructions to avoid disputes con-
cerning inspection or acceptance of services or supplies.
(c) Types of Inspection. Because of the variety of types of
contracts and subcontracts and the degree of responsibility
assigned to the operating contractors, the architect-engineer,
the construction contractors, and individual vendors, specific
rules covering all phases of inspection cannot be prescribed.
In general, inspection activities are divided into three
types--functional, general, and detailed--as described below:
1 Functional Inspection is performed to determine overall
compliance with contract drawings and specifications. It may
vary from inspection of minor items to extensive testing of
operating equipment (which must be provided for in the
contract). It may also serve in making initial determination
of the adequacy of the design effort. The field element
and the operating contractor participate in functional
inspections from the viewpoints of owner and user.
2 General Inspection is the fundamental and comprehensive
inspection to ascertain that workmanship and kind and quality
of materials conform to the contract specifications.
3 Detailed Inspection includes, but is not limited to, verifi-
cation of details, such as checking location and size of
reinforcing bars, maintaining records of concrete batching
plant operations, verifying the use of proper welding rods,
checking riveting and welding, and performing other inspec-
tion for quality assurance purposes. It starts with initial
construction operations and extends through all construction
stages.
(d) Assignment of Inspection Functions. Field offices shall:
1 Assure adequate and properly coordinated inspection of
construction; and
2 Determine who will perform required inspection services. In
addition to means at their immediate disposal, field offices
may utilize the inspection services of other, Government
agencies.
DOE 4700.1
3-6-87 V-55
a Inspection by Contractors.
(1) Normally, the architect-engineer should have
responsibility for inspection to assure conformance
with the contract drawings and specifications.
(2) The operating contractor may have responsibility for
inspection of any construction when advantageous to
the Government.
Section 196
(3) In unusual cases, the best interest of the Government
may be served by having a single contractor perform
design, construction, and inspection. In these
cases, it is usually advantageous to the Government
to obtain a construction manager as part of the proj-
ect team and the construction manager perform the
inspection services. If, in these cases, the
“design-construct” contractor is to perform the
inspection services, his organization and procedures
for inspection must be carefully reviewed to assure
that a department of the contractor, separate and
distinct from the department furnishing construction
services, performs the inspection services. The
inspection performed under these conditions shall not
constitute final inspection and acceptance by the
Government.
b Departmental Inspection. General and detailed inspection
by DOE personnel should be held to a minimum and should
not duplicate competent inspection by contractors. Self-
inspection of construction should be avoided whenever
practicable. Inspection performed by DOE should, however,
be sufficient to ascertain that the party or parties
responsible for inspection are adequately qualified and
are doing their jobs properly, and that proper coordina-
tion is attained. Participation in functional inspection
by DOE personnel is of primary importance.
(e) General Practices. In carrying out the procedures set forth
above, field organizations shall observe the following addi-
tional general practices:
1 At a minimum, inspection shall conform to accepted
practices/methods used in private industry, and shall be
supplemented, as necessary, commensurate with the quality
assurance standards and objectives applicable to the par-
ticular construction project.
V-56 DOE 4700.1
3-6-87
2 Inspection services shall not be procured from construction
contractors with respect to their own work, since this would
represent self-inspection.
3 A level of supervision partially equivalent to detailed
inspection shall be furnished by cost-type contractors, as
appropriate to reduce the requirements and costs of other
detailed inspection services.
4 Sufficient inspection shall be provided for all work to
assure minimum compliance with safety standards contained in
DOE 5480.1A.
(f) Inspection Criteria and Recommended Practices.
1 Field inspection, in its general and detailed phases, fre-
quently paces construction progress. It shall be scheduled
so that inspection will not hinder the construction effort.
2 When one contractor is to inspect the work of another, writ-
ten instructions should be furnished to the inspecting
contractor defining responsibilities and stating that he is
not authorized to modify the terms and conditions of the
contract, nor to direct additional work, nor to waive any
requirements of the contract, nor to settle any claim or
dispute. Copies of these instructions should be furnished to
the contractor whose work is to be inspected, with a request
that he acknowledge receipt on a copy to be returned to the
contracting officer. In this manner, both contractors are on
express notice of the authority, and limitations on the
authority, of the inspecting contractor.
3 For fixed-price construction contracts, inspection provisions
are set forth in SF-23A, "General Provisions” of the
contract. For both cost-reimbursement and fixed-price
contracts, the extent of inspection is largely subject to
determination by the project manager. He or she shall
require thorough inspection with adequate documentation for
all important phases and details of a construction job.
Inspection is one of the prerequisites upon which final
payment of the contractor is based.
Section 197
4 Fundamentally, the construction contractor is responsible for
the quality of his work. He must furnish detailed super-
vision of construction and be able to show that material,
equipment, and workmanship conform to the contract. This
requires coordination with design and inspection forces, the
DOE 4700.1
3-6-87
V-57
scope and details of which shall be reviewed and approved by
the field element. For complex quality level facilities,
it may be necessary for construction contractors to provide
their own inspection services to assure the quality of their
work.
5 Continuous inspection and testing should be provided for all
work for which the quality of workmanship cannot be deter-
mined by subsequent inspection or testing without detriment
to the work as a whole. Classes of work in this category
include pile driving, concrete work, testing of pipe and
welding in enclosed or radiation-hazard areas, and verifica-
tion of vital measured distances.
6 Frequently, special items must be inspected at the mill or
fabrication shop to determine, in advance, that materials and
workmanship are in accord with specifications. A requirement
placed on the vendor for mill certification and certificates
of vendor inspection, when properly identifiable with the
special items, will often expedite matters. The contracting
officer shall require that personnel assigned to offsite
inspections be qualified both to interpret and obtain
adherence to the specifications.
7 Field elements should assure that inspection procedures,
instructions, and/or checklists, as a minimum, provide for
the following:
a Statement of quality characteristics to be inspected;
b Organization or individual responsible for performing the
inspection;
c Acceptance and rejection criteria;
d Method of inspection description;
e Evidence that inspection has been completed; and
f Records of the inspection.
8 An effective management practice for inspection is the use of
a list of items that must be completed or corrected, normally
referred to as a punch list. Punch lists are normally ini-
tiated shortly after the start of the physical construction
and maintained throughout the work effort. The punch list
may include major items that require completion before other
work can proceed and both major and minor items on which
V-58 DOE 4700.1
3-6-87
d.
additional and/or corrective work must be performed prior to
acceptance. The punch list is updated as inspections are
performed and items added or deleted as appropriate.
Normally, deletion of all items from the punch list results
in the project being ready for final acceptance.
Acceptance of Completed Facilities. The following procedures for the
acceptance of completed facilities, and the orderly transfer of these
facilities from construction to operating responsibility, are intended to
be a guide for the field element to use in the establishment of detailed
procedures and responsibilities for accomplishment of these functions:
(1) Definitions.
(a)
(b)
(c)
(d)
Acceptance Testing is the performance of all necessary testing
to demonstrate that installed equipment will operate satis-
factorily and safely in accordance with the plans and specifica-
tions. It includes required hydrostatic, pneumatic, electrical,
ventilation, mechanical functioning, and run-in tests of port-
ions of systems, and finally of completed systems.
Section 198
Inspection as used herein means the survey of a unit, facility,
or area to determine status of acceptability. It includes a
preliminary inspection to fix the number of work items remaining
to be completed (list of exceptions or punch list), and a final
inspection to accept the completed construction.
Conditional or Provisional Acceptance is the acceptance of a
unit or facility with a documented listing of the specific
testing to be accomplished or work remaining, including fur-
nishing of any outstanding submittals of technical and record
data, to be completed by the construction contractor, and on or
by what date the actions are scheduled to be complete.
Final Acceptance is a written statement by the field element
or its designee that the work performed by the construction
contractor has been accepted as being in accordance with
approved plans and specifications. The final acceptance also
should be signed by the operating contractor, if applicable,
indicating his acceptance of the facilities as constructed and
the date the facilities are to be occupied or available for the
use of the operating contractor.
(2) Assignment of Test and Acceptance Functions. Field elements shall
assure that adequate test and acceptance procedures, defining the
respective roles of the field organizations and its contractor
participants to the fullest extent possible, are established and
followed, and the requirements are included in the contractual
arrangements.
DOE 4700.1
3-6-87
V-59
(3) Roles of Contractors. The roles of the contractors normally are as
follows:
(a) The architect-engineer, as part of Title II services, usually
prepares the performance specifications for equipment and
systems. Title III services include test scheduling and
arrangements for preliminary and final inspection. The field
office manager or designee should approve these procedures and
schedules prior to distribution to all parties involved.
(b) The construction contractor usually participates in inspections
and schedules and conducts acceptance tests. Allowing bene-
ficial occupancy by the operating contractor after the accept-
ance test relieves the construction contractor from liability
for damage caused by persons or operations not under his
control. The construction contractor’s conditional responsi-
bility continues until all exceptions are cleared and final
acceptance is signed by the field element or its designee.
The contractor’s responsibilities continue for any guarantees or
warranties required by the terms of the contract.
(c) The operating contractor, rather than the architect-engineers
may be assigned the responsibility for preparation of acceptance
test procedures, schedule, and testing of process equipment.
The field element should approve these procedures and schedules.
Representatives of the operating contractor generally will
participate in final inspections, observe tests, and sign
acceptance papers when the facilities are to be occupied by, or
for the use of, the operating contractor.
(d) Test and acceptance functions may also be assigned to a con-
struction manager when one is utilized for the project. The
functions are normally assigned to a construction manager when
the “design-construct” approach is utilized.
(4) Procedures.
(a) Establishment of Procedures.
1 In preparing a procedure for the acceptance and transfer of
constructions, field elements shall carefully evaluate the
role of each organization. Each party involved in the
acceptance procedures must have a clear understanding before-
hand of the responsibilities and functions of the other par-
ticipants.
Section 199
2 Procedures will vary according to the complexity of facili-
ties, and responsibilities will vary according to the methods
of construction management. Buildings or facilities not
involving operating equipment may require only preliminary
V-60 DOE 4700.1
3-6-87
and final inspections, completion of punch list items, and
signing of acceptance documents. Facilities involving
operating equipment also will require acceptance testing.
This may be complicated and extensive, requiring written
detailed procedures, planning, and scheduling.
(b) Beneficial Occupancy.
Acceptance of a completed facility as a unit may be
desirable. Construction forces are then completely removed,
and interferences involved in having construction and
operating labor in a common area are avoided.
It may be necessary, or more practicable, to turn over for
beneficial occupancy, by operators, portions of a facility as
they are substantially completed prior to final acceptance.
A list of items remaining to be completed or corrected by the
construction contractor shall be prepared to define fully the
items that remain as the construction contractor’s respon-
sibility. The operating contractor can train personnel in
these portions, proceed with dry runs, or, in some types of
facilities, start operating in initially completed units.
Under beneficial occupancy, the field element may assign to
the operating contractor prime responsibility for the facil-
ity and may limit access of construction forces to those
engaged in cleanup of exceptions. Responsibility for main-
tenance of permanent facilities generally transfers to the
operating contractor upon occupancy.
(c) Acceptance Testing of Equipment.
1 If procedures for acceptance testing of equipment are not
covered by the specifications and detailed written procedures
are required, they shall be prepared as early as practicable
in the construction period so that portions of a system may
be tested as construction progresses. The construction
contractor usually will arrange the acceptance tests, and the
field element will assure that tests are conducted promptly.
2 Acceptance tests may be made both on portions of systems and
on completed systems. Such tests usually will be witnessed
by the architect-engineer, the construction contractor, the
operating contractor, and the construction manager, if
applicable. The field element may, as appropriate, assign
personnel to witness acceptance tests. All responsible
witnesses shall sign the final test report.
1
2
3
DOE 4700.1
3-6-87
V-61
(d) Final Inspection and Acceptance.
1 Upon substantial completion of construction and acceptance
testing, a preliminary inspection usually should be made.
This will establish the number of work items remaining to be
completed and permit preparation of a list of exceptions.
The A-E, construction manager, construction, and operating
contractors should participate in the inspection. The field
element may, as appropriate, assign Departmental personnel
to participate in the inspection. A date should be set
for the performance of the final inspection, allowing time
for completion of exceptions.
Final inspection should be made by all parties who partici-2
pated in the preliminary inspections. They shall indicate in
writing that such inspection was made and note any further
exceptions. Upon cleanup of such exceptions, the work is
finally accepted through the signing of documents by the
field element, construction manager, A-E, and construction
and operating contractors, as appropriate.
Section 200
(e) Testin g, Inspection, and Acceptance Documents. Appropriate
forms shall be developed and used for acceptance testing and
final inspection. Forms shall be signed by all responsible
individuals involved in tests and inspections. Documents for
final inspection and acceptance may be combined in a single
form.
4. MANAGEMENT TECHNIQUES FOR CONSTRUCTION ECONOMICS.
a. General. Construction by its very nature presents a very difficult
problem in controlling costs and preventing waste and error. A principal
problem is that the project can always be analyzed after completion and
better ways theorized as to how it should have been done. Every well-run
project, regardless of size, utilizes a program or method to control
construction costs and reduce waste and error. Again, the methods and
programs that will be effective vary with each individual project. Some
of the major cost reduction and efficiency measurement methods used on
past projects are summarized herein. Utilization of one or more of the
techniques outlined will assist in reducing costs, preventing waste and
error, and keeping management currently informed as to those features of
the project which need corrective action.
b. Cost Reduction Methods for Cost-Plus-Fixed-Fee Construction Contracts.
(1) Force Account Construction Productivity Assessment. When major por-
tions of the construction of a project are to be accomplished by
V-62 DOE 4700.1
3-6-87
force account cost-plus-fixed-fee labor, provision should be made for
monitoring and assessing labor productivity. A system should be
employed which compiles data on actual productivity experience and
enables comparison with estimated or budgeted unit labor costs for
the activity. The forecasting of labor productivity on the balance
of the work should flow from this system and the current working
estimate should be maintained accordingly. Specifically, data should
be provided on unit and total labor experience for such work elements
as concrete forming, placement, reinforcing, piping, and electrical
installation units. Summaries of productivity experiences versus
budget estimates for civil/structural, piping, and electrical costs
also should be available to enable overall assessment of trade per-
formance. This productivity assessment system should accomplish the
following:
(a) It should identify specific and general productivity problems in
order to allow measurement of improvement.
(b) It should enable maintenance of a current project estimate
reflecting force account labor experience.
(c) It should provide updated experience data weekly or biweekly.
(2) Foreman Training Program is designed to transmit policy and infor-
mation through to the working level, train foremen to handle their
assignments, increase overall job efficiency and safety, effect econ-
omies, and minimize labor difficulties.
(3) On-The-Job Worker Surveillance Program is the so-called “head count”
which determines the number of employees gainfully occupied at a
given time. It provides a valuable tool to relative productivity of
workers and to locate areas where improvement is necessary. Its
regular use is recommended for all cost-reimbursable, construction
work. In comparing data for separate projects, allowance must be
made for differences in jobs and job conditions, and in judgment of
those making the counts.
Section 201
(4) Other Methods. On moderate- and large-size jobs, periodic meetings
should be held of supervisory and key staffs of the A-E, the con-
struction contractor, DOE and, if desired, the operating contractor.
At these meetings, the participants should discuss problems with
which they are confronted. If solutions are not immediately avail-
able, efforts should be made to provide answers as soon as possible.
Informal or round table meetings of craft and area superintendents
also may be held. This permits the dissemination of new methods and
information more rapidly than by formal programs. There also is a
possibility that an accomplishment in one area that provided an
outstanding competitive record for its originators can be passed on
and utilized in all areas.
DOE 4700.1 V-63
3-6-87
(5) Productivity Comparisons with Prior Work. The in-place value of work
per person-month of labor for projects which have been completed can
be used to check overall efficiency of the job. These figures are
particularly useful for checking overall estimates in those limited
instances where duplicate or similar projects are being constructed.
Direct cost comparisons of cost-plus jobs are impractical unless
similar facilities are being constructed, since numerous adjustments
must be made for local situations before the relative efficiency of
the work can be determined. Despite local variations, it is possible
to compare features of projects on a unit basis and against estimates
prepared by the A-E prior to start of work. Current cost data and
records compared with the amount of work accomplished also will indi-
cate areas where corrections or adjustments are needed for economical
construction.
c. Cost Reduction Methods for Fixed-Price Construction Projects.
(1) Prevention of numerous change orders to the contract is the most
important aspect of cost reduction on fixed-price contracts. This
prevention is best accomplished during the design phase by having
personnel with extensive construction experience review the plans and
specifications in order to eliminate the possibility for changes once
the contract is executed.
(2) Rapid action on problems that arise during construction will also
reduce the total cost of the changes. Delay in providing the design
modifications and providing instructions to the fixed-price contrac-
tor always increases the total project cost and, in most instances,
the completion date. Project managers/field elements should assure
that the proper procedures are established to rapidly satisfy
Government responsibilities when changes or problems occur during
construction.
(3) Value engineering incentive programs are being used widely in Federal
construction to effect cost reductions in fixed-price construction
jobs. The technique invites construction contractors to submit
suggested changes in contract requirements which will result in
reducing costs without sacrificing required quality or function, and
to share in such savings. Such a program may not be very practical
on complex and unique projects which are specifically tailored to
meet special and unusual requirements. However, it may produce
savings on more conventional construction projects to be accomplished
under fixed-price contracts, and DOE field organizations should,
whenever possible, use the technique.
Section 202
d. Construction Performance Evaluation Based on Installation Rates. From the
project schedule and work packages, the weekly bulk quantity installation
rates for concrete piping and electrical work can be determined. Weekly
installation experience can be observed and recorded. Continued analysis
of installation performance will provide a check on the reasonableness of
V-64 DOE 4700.1
5.
3-6-87
the schedule and a good method for assessing work progress and forecasts.
This method can also assist in isolating areas in which problems are
occurring and further analysis of that specific area can determine speci-
fic cause, whether it be productivity supervision or lack of supplies.
The continued monitoring of installation rates will also assist in deter-
mining the effectiveness of corrective actions applied to the perceived
problem.This method can be applied to cost reimbursement contracts and,
to a limited extent, to fixed-price contracts.
CONSTRUCTION COMPLETION REPORTS.
a. General.
(1)
(2)
(3)
Construction completion reports are required to ensure that the
necessary information on the completed construction is entered into
the Real Property Inventory System upon occupancy or acceptance of
the new facilities.
These reports are also helpful for purposes of project history, as
references for future project planning and execution, use in training
project personnel, and for recording benefits attained from innova-
tive approaches to the project.
The form, content and procedures for preparation of the report are
the responsibility of the Head of the Field Element. Heads of Field
Elements shall ensure that their use of this management tool is
appropriate to ensure that the proper information is entered into the
Real Property Inventory System.
b. Preparation and Disposition of Reports.
(1)
(2)
(3)
The Head of the Field Element, in determining the form, content,
procedures and timing of the construction completion report, shall
comply with the Real Property Inventory System requirements that
facility data be entered into this system upon occupancy or accept-
ance by DOE of the facility. Normally, this requirement will not
allow combining the construction completion report with the cost
completion report.
The Real Property Inventory System timeliness of data entry require-
ment will require subproject completion reports for large projects
where the construction is occupied or accepted in stages. The Heads
of the Field Elements shall provide for this situation in their
procedures regarding construction completion reports.
Suggested contents of the construction completion report are con-
tained in Attachment V-12. Use of these suggested contents would
maximize the usefulness of the construction completion report.
DOE 4700.1
3-6-87 Attachment
Page V-65
V-1
EXAMPLE OF A PROJECT AUTHORIZATION
Attachment V-1
Page V-66 DOE 4700.1
3-6-87
DOE 4700.1
3-6-87
Attachment V-2
Page V-67
a.
b.
CONSTRUCTION MANAGEMENT
1. GENERAL.
The term construction management has been used in many different contexts,
from something that covers all facets of the construction industry to
something as limited as critical path method scheduling.
The construction manager is an additional participant in the project
delivery team. The construction manager usually will be from private
industry but may be selected from another Federal or local Government
agency. The addition of this participant results in some modification of
the responsibilities and authorities of the normal participants involved
in the conventional delivery system of design-bid-build and design
construct (or turn-key).
Section 203
c. The construction management process is utilized on projects where the
expertise of the construction manager can significantly benefit the
Government in the performance of the variety of functions or services it
is responsible for under the conventional delivery systems. The construc-
tion manager, through his or her expertise, assists and advises the
Government to obtain the desired facilities at the lowest possible cost
and delivery in the shortest possible time. The construction management
process greatly enhances the opportunity to benefit from the advantages of
phased construction. Normally, the construction management process oper-
ates most effectively when the construction management firm is employed at
the start of the planning and predesign phase, and continues through to
project completion. In this capacity, the construction manager can assist
the Department in functions such as project planning and budget admin-
istration. Likewise, the construction manager could assist the A-E in
such activities as providing information on materials selection, labor
impact, construction techniques. With respect to quality, the construc-
tion manager is interested in maintaining the quality desired rather than
assuring the quality is a part of the design, which is the responsibility
of the designer.
2. ADVANTAGES.
a. The use of the construction management concept can result and has resulted
in several advantages to the project owner, both in the civilian sector
and the Government. Some of the advantages that can be gained from the
proper use of the construction management approach are as follows:
(1) An additional professional input which, if provided during the
planning and design stages, permits establishment of more accurate
and reliable time, cost, and quality schedules and controls.
Attachment V-2
Page V-68
DOE 4700.1
3-6-87
b.
(2) Reliable
on costs
information on market,and labor conditions and their effects
and schedules.
(3) The efficient use of phased construction (fast-track) procedures and
thus, the reduction of project time and cost.
(4) Increased flexibility throughout the entire project, both in design
and construction; adjustments to budgets and contracts may be made
more readily as they arise.
(5) Competitive bidding for subcontracts; construction management im-
proves competitive bidding under public laws, and reduces the
possibility of bid shopping, auctioning, and similar unfair practices
with respect to subcontractors.
(6) Provision to DOE of professional expertise in the particular con-
struction services required for a specific project.
(7) Incorporation of the latest technology and current market conditions
into the descisionmaking process.
(8) A reduction in the layering of bonding required. The financial
structure is compartmentalized, and the effects of financial failure
are minimized.
It is recognized that all the advantages above cannot be realized for all
projects. As with most new concepts, use of construction managers has, in
some cases, failed to realize any of the anticipated advantages. The
results, as always, depend upon the management skill utilized in applying
the concept. Tailoring the construction management contract to the par-
ticular project is extremely important.
DETERMINING WHETHER A CONSTRUCTION MANAGER SHOULD BE USED. Several factors
should be evaluated when considering a project for use of the construction
manager concept. These factors should be evaluated with respect to the bene-
fits and costs expected to occur if the construction management method is uti-
lized instead of a conventional delivery system approach.
Section 204
a. Complexity of a project;
b. Size of project;
c. Required delivery schedule;
d. Procurement strategy;
e. Availability of qualified Government personnel to perform necessary
functions;
3.
DOE 4700.1
3-6-87
f. In cost share contracts; capabilities of partners; and
g. Unique project characteristics,
4. CONSTRUCTION MANAGEMENT FUNCTIONS.
Attachment V-2
Page V-69
a. General.
(1) Construction management services are performed by firms with the
knowledge and expertise required to provide the services listed in
(2)
this section. Based on the unique requirements of each construction
project, the Department project manager, as an integral part of the
planning process, must determine which functions would be best
performed by a construction management firm to accomplish the
project in the most economic, efficient, and effective manner. Each
project requires a separate combination of management functions and
techniques to obtain the desired result of a complete and usable
facility utilizing minimum time and money.
Considerable care shall be exercised in selection and description, in
the contract, of the services to be performed. Whenever possible,
emphasis should be placed upon the construction manager as an expe-
diter and advisor to all of the construction team members. The
assignment of the construction manager as the director of any portion
of the design and/or construction shall be avoided to prevent the
introduction of unnecessary conflict into the construction team con-
cept. The construction management service to be provided should be
determined by the Government expertise available, project require-
ments, project specifics, and procurement strategy.
b. Planning and Design Services. Should construction management services be
required during the predesign phase, the construction manager would be
required to perform some of the following functions:
(1) Participate with the Department in the revision of preparation of
project scope and design criteria with respect to construction
process functions;
(2) Review scope and design criteria for effective compatibility with
construction methods, materials, and techniques;
(3) Develop, in coordination with the Department, a comprehensive project
management plan, including an overall project schedule to assure
timely completion;
(4) Prepare preliminary construction cost estimates, and develop prelimi-
nary schedule for accomplishment of the project;
DOE 4700.1Attachment V-2
Page V-70
c.
(5)
(6)
(7)
3-6-87
Participate with the Department in completing other project elements
such as environmental assessments and acquisition, quality control,
and safety plans;
Assist in the determination of applicable local, State, and Federal
laws which the project must meet and develop procedures to ensure
that the project complies with these laws;
Perform market survey of available labor and materials;
(8) Monitor schedules for all project activities by the participating
organizations; and
(9) Participate with the Department in contracting for field services
such as collection of environmental data.
Design Phase. Should construction management services be required during
this phase, the construction manager may be required to perform the
following functions:
(1)
(2)
(3)
(4)
(5)
(6)
Establish the project controls to be utilized, so that it will pro-
vide the agency with the data it requires and assure that prospective
contractors understand the controls by including appropriate infor-
mation in the bid packages;
Section 205
Participate in value engineering conferences and participate with the
A-E in developing a design that will permit the use of the most eco-
nomical and efficient construction techniques and methods;
Provide the A-E with current market information on the availability
of construction materials and labor conditions, with recommendations
as to how design alternatives can reduce overall costs;
Provide the construction cost estimate, and develop lead time
requirements for acquisition, contracting, and the project accom-
plishment within the desired time frame;
Utilize the advantages of phased construction to the extent possible
and determine the contents of the separate bid packages for contract
bid and award purposes, base the contract groupings on the work
sequence, labor and material availability, trade union agreements,
and other pertinent factors;
Provide periodic updating of the estimated construction schedules and
the development of a project budget as the design details evolve; and
assist the Departmental project manager in solving problems related
to costs and schedules;
DOE 4700.1
3-6-87
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
Attachment V-2
Page V-71
Review plans and specifications with the A-E to provide responsive
specification terminology, to avoid overlapping trade jurisdictions,
and to prevent overlapping or voids in the separate bid package
specifications;
Participate with the Department in conducting public hearings;
Publish notices of work, prepare bidders lists, assemble and issue
the invitation for bid or the request for proposal packages, answer
inquiries, arrange prebid or prenegotiation conferences, issue adden-
dums, and schedule bid openings or negotiation meetings;
Conduct bid openings, evaluate bids, and recommend appropriate action
to the Department, or award contracts;
For projects utilizing the guaranteed maximum price, prepare the
guaranteed maximum price, agree with Government on guaranteed
maximum price, and perform functions required by the guaranteed
maximum price concept, such as award of construction contracts;
Implement the acquisition plan for the purchase of long leadtime
items; and expedite these purchases to assure on-time delivery of
supplies;
Participate with the Department in contracting for field services
such as collection of environmental data;
Assist the project participants in securing necessary permits, licen-
ses, and approvals, to satisfy the requirements of local, State, and
Federal laws; and
Accomplish or arrange for accomplishing any special studies required
for the project such as transportation; social, economic, or
archeological.
d. Construction and Postconstruction Phases. Should construction management
services be required during this phase, the construction manager may be
required to perform the following functions:
(1) Perform all management and administrative aspects of the project as
required by the Department;
(2) Implement the project management plan by establishing and maintaining
coordination procedures among all project participants;
(3) Furnish the various general condition items such as security, tem-
porary field construction facilities, debris removal, general safety
requirements, and any other similar project requirements not provided
for in the bid packages, normally by contract;
Attachment V-2
Page V-72
DOE 4700.1
3-6-87
(4) Provide onsite personnel to facilitate and coordinate the activities
of the various contractors to assure that the workmanship and mater-
Section 206
ials being used are in compliance with plans and specifications, and
that interference among the trades is minimized;
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
Perform functions necessary to obtain, verify, record, and con-
solidate required data, and prepare progress status reports required
by the Department;
Secure information from the contractors regarding necessary field and
lab tests, and review results for compliance with specifications;
Assist in the review and coordinate the submittal of samples and shop
drawings;
Adjust the project schedule for changed conditions and unexpected
interferences;
Maintain financial and cost accounting records and perform financial
analysis;
Recomnend, for approval by the Department, a procedure for processing
requests for changes, and maintain records for change and notice to
proceed orders in accordance with the terms and conditions of the
contract;
For projects utilizing the guaranteed maximum price, perform the
functions required by the guaranteed maximum price concept, such as
approval of change order and contract payments;
Process contractor claims in accordance with the terms and conditions
of the contract;
Review and process vouchers and invoices from contractors and vendors
in accordance with the contract requirements;
Provide early identification of problems and take necessary actions
to resolve them to minimize additional cost and schedule slippage;
Maintain a record of changes made during the construction and pre-
pare, or have prepared, as-built drawings that reflect the
constructed work;
Prepare and assist the agency in accomp
acceptance procedures and tests; and
ishing project completion andl
DOE 4700.1
3-6-87
Attachment V-2
Page V-73
(17) Complete the postconstruction functions, including assembling
operating manuals and warranties, maintenance manual preparation,
warranty problem resolutions, startup assistance, training develop-
ment and implementation, and preliminary operations assistance.
5. CONSTRUCTION MANAGER CONTRACT PROCUREMENT METHODS. Construction manager
contracts are procured either by formal advertising or by negotiation.
Contracts procured by formal advertising generally should utilize the two-step
formal advertising method since the procurement is for professional services
where technical and management approach is of considerable importance, and it
is not normally desirable to specify the technical and management approach to
be utilized.
6. TYPES OF CONTRACTS.
a. A construction manager contract may be of any type or combination of types
listed below, which will promote the best interests of the Government sub-
ject to the restrictions placed upon the types of contracts by procurement
regulations. The contract, if desired, may be structured to provide addi-
tional incentives.
(1) Fixed price contract.
(2) Cost-plus-fixed-fee contract.
(3) Cost-plus-award-fee contract.
(4) Cost-plus-incentive-fee contract.
b. Since the construction manager is procured to protect the best interests
of the Government, the fixed-price contract is the preferred type of
contract for construction manager contracts. However, the unique require-
ments of each construction project often require that other contract types
be used.
7. THE CONSTRUCTION MANAGER CONTRACT WITH GUARANTEED MAXIMUM PRICE.
Section 207
a. Guaranteed maximum price construction manager contracts require the
contractor to stipulate, at a specified time during the design phase, a
guaranteed maximum price. This guaranteed maximum price is the maximum
amount the Government will be required to pay for completion of the work
included in the guaranteed maximum price as prescribed by the contract.
If the actual cost of the work exceeds the agreed-upon guaranteed maximum
price, the construction manager is required to complete the work at no
additional cost to the Government. The guaranteed maximum price is the
sum of the following:
Attachment V-2
Page V-74
DOE 4700.1
3-6-87
b.
c.
(1) The agreed-upon cost of all work to be performed by contractors
awarded contracts by the-construction manager;
(2) The estimate of all reimbursable costs to be incurred by the con-
struction manager;
(3) The fixed-fee for construction management services of the construc-
tion management contract; and
(4) The agreed-upon contingency to cover the cost of known and unknown
items not included in the agreed-upon cost in subparagraph 7a(1),
above.
The construction manager contract with guaranteed maximum price is uti-
lized when it is beneficial to the Government to have the assurance that
the project costs will be established prior to the beginning of construc-
tion. The guaranteed maximum price requires the contractor to offer a
guaranteed maximum price for delivery of the entire project. If the
guaranteed maximum price is agreed upon by the Government, the offered
guaranteed maximum price is made a part of the contract. Using this type
of contract, the construction manager assumes the financial risk of
completing the project within the guaranteed maximum price. As with other
construction manager contracts, it is not normally intended that the
construction manager will do any of the actual construction work. The
construction manager will solicit competitive bids and award subcontracts
to construction contractors. If force account labor must be included in
construction manager contract, it must be set forth in detail and shall
require approval, in advance, by the contracting officer.
The construction management contract with guaranteed maximum price is pro-
cured in the same manner as other construction manager contracts. The
construction manager guaranteed maximum price contract shall be so
executed to provide conversion to a construction manager contract without
guaranteed maximum price, should the guaranteed maximum price not be
agreed upon, or provide the termination without costs. The guaranteed
maximum price is formulated as the summation of the agreed-upon cost of
the items of work unnecessary to the delivery of the project. These work
items shall be set forth as separate line items in the guaranteed maximum
price provision. Inclusion of specific construction management services
are required in the guaranteed maximum price contract to allow the
construction manager to comply with the guaranteed maximum price
provisions. Some of these service functions, but not necessarily all,
include action to:
(1) Award construction and service contracts;
(2) Process and approve change orders;
(3) Approve and issue notice to proceed;
DOE 4700.1
3-6-87
Attachment V-2
Page V-75
(5) Formulate, coordinate, update, and change project schedule.
d.
e.
f.
g.
(4) Approve and issue progress payments; or
Section 208
A guaranteed maximum price one-part contract requires the construction
manager and the Government to execute a contract with agreed-upon cost for
services provided by the construction manager throughout the project. The
contract includes a guaranteed maximum price clause, as an option, pro-
viding for an agreement to a guaranteed maximum price. If a guaranteed
maximum price is agreed to, all of the remaining services to be performed
will be governed by the guaranteed maximum price clause.
The guaranteed maximum price two-part (A&B) contract requires the
construction manager and the Government to execute a contract with agreed-
upon cost for services provided by the construction manager during the
predesign and/or design phase (part A) and construction phase (optional).
Upon stipulation of the guaranteed maximum price by the construction
manager, and agreed upon by the Government; part B of the contract is exe-
cuted, whereby the provisions of a guaranteed maximum price clause are in
effect. If a guaranteed maximum price is not agreed upon, part B is not
executed and the construction manager performs the services during the
construction phase at the cost agreed to under Part A (if provided for) or
is terminated. In the latter case, the contract should provide for ter-
mination without cost.
The final cost to the Government for work under an executed guaranteed
maximum price provision will be either the sum of the actual costs of
subparagraphs 7a(1), (2), and (4) above plus the fixed-fee of 7a(3), or
the guaranteed maximum price, whichever is less. Reimbursable costs
should be kept to a minimum.
Adjustments should be made to the guaranteed maximum price utilizing the
following guidelines:
(1) A change in the construction management fee may be negotiated when
the Governments action changes the scope of services utilized to
determine the construction manager fee.
(2) A change to the guaranteed maximum price may be negotiated when the
Government's action increases the cost of any of the following
elements:
(a) The agreed-upon cost of all work to be performed by contractors
awarded contracts by the construction manager;
(b) The estimates of all reimbursable costs to be incurred by the
construction manager;
Attachment V-2
Page V-76
DOE 4700.1
3-6-87
(c) The agreed-upon contingency to cover the cost of known and
unknown items not included in the agreed upon costs in
subparagraph 7a(2)(a), above.
(3) The construction manager fee will not decrease when actions of the
construction manager result in a reduction in the cost and/or time of
performance of the project.
h. If, as a result of the award of a construction contract, any excess funds
are generated because the award price is less than the guaranteed maximum
price line item, these funds shall be placed in a separate line item iden-
tified as the reserve fund. This fund may be used by the construction
manager to cover bids exceeding the line item amount set forth in the
guaranteed maximum price for any of the line items, but shall not be used
to cover change orders or claims arising after award of contracts. Any
funds remaining in the reserve fund after all line items have been bid
shall be released by the construction manager to the contracting officer.
Section 209
8. CONSTRUCTION MANAGEMENT FEES. Normally, a construction management contract
would be broken into two sections, one for the design services and one for the
construction services. Fees should be likewise broken down. Normally, fees
are stated in fixed, lump sum-amounts and are modified only when a change in
project scope or time is directed by the Government. If the construction
manager is solely responsible for the establishment of the schedule, then time
extensions due to schedule slipping are the responsibility of the construction
manager, and the fee is not subject to change as a result. Fees are not
affected by changes in cost unless the cost changes are due to change in proj-
ect scope. Fees shall include compensation to officers, salaries of home
office personnel (including accounting, purchasing, estimating and cost
control, related taxes, all insurance and pensions), profit, overhead, cost of
home office facilities expenses, job-site personnel costs, professional fees
for consultation, legal, labor relations, accounting, and bookkeeping expen-
ses. Reimbursable costs must be itemized in definitive terms in the construc-
tion management contract, preferably set forth as a separate item in the
contract. In order to keep administration of the construction management
contract to a minimum, reimbursables should be limited to travel and per diem
of construction management personnel, and general condition services provided
by the construction manager.
DOE 4700.1
3-6-87
Attachment V-3
Page V-77
DESIGN CRITERIA PACKAGE CHECKLIST
This checklist is intended as a guide to ensure the development of a complete cri-
teria package. Field Elements may add to this checklist as necessary to meet
their particular requirements. The checklist items are considered necessary to be
included within the criteria package to ensure that adequate information is pro-
vided for the designer of the facility. The criteria package should:
1. Describe the functions or operations to be performed in the facility or proj-
ect.
2. Provide a general description of the planned or proposed facility as conceived
in the conceptual design, including:
a. Proposed occupancy, type of buildings, parameters, work spaces, and spe-
cial needs;
b. Site location;
c. Site preparations, conditions, removals, temporary roads, fencing, work
areas, disposal, areas, borrow area, grading, drainage, and excavations;
d. Site improvements, parking, roads, walks, fencing, and lighting;
e. Utilities, existing and proposed; and
f. Special security, environmental, safety, and health needs.
3. Refer to and include copies of applicable publications or information, such
as:
a. Departmental directives, studies, and references; and
b. Operating contractor manuals, standards, and references.
4. Refer to applicable codes, standards, or guides.
5. Provide a general description of building requirements, including:
a. General proposed layout and configuration;
b. General operational or functional needs and special functional or system
needs;
c. Building fenestration and orientation;
d. Dead and live loads, special loads, and wind loads;
Attachment V-3
Page V-78
DOE 4700.1
3-6-87
e. General building structure or frame;
f. Foundation and soil conditions;
g. Walls, exterior and interior, and finishes, including insulation, moisture
protection, doors, windows, and vestibules;
h. Roofing, moisture proofing, insulation, walkways, hatches, ceilings, and
finishes;
i. Floors and finishes;
Section 210
j. Energy usage targets and/or limits; and
k. Fixed fire protection features such as fire rated walls, doors, windows,
and interior flame spread ratings.
6. Provide general description of the building mechanical systems requirements,
including:
a. General heating, ventilation and air conditioning needs and requirements,
heat recycling and/or recovery, monitoring, and control.
b. General heating, ventilation and air conditioning parameters, including:
(1) Occupancy loads and operations uses;
(2) U values for the building envelope;
(3) Design temperatures and humidity control;
(4) Controls systems; and
(5) Instrumentation.
c. Codes, standards, and guides.
d. Energy conservation parameters.
e. Special conditions or parameters, including:
(1) Special systems or equipment loads; and
(2) Special ventilating and filtering information.
f. Piping and plumbing needs, including:
(1) Codes and standards;
DOE 4700.1
3-6-87
Attachment V-3
Page V-79
(2) Process water or cooling water-needs; and
(3) Cooling water chemistry control needs.
g. Fire protection.
h. Systems performance and operating tests.
7. Provide general description of building electrical systems requirements,
including:
a. Lighting needs.
b. Power needs.
c. Electrical systems parameters including:
(1) Occupancy and operations use;
(2) Illumination guides and proposed methods; and
(3) Control measures.
d. Codes, standards, and guides.
e. Energy conservation measures.
f. Special conditions or parameters, including:
(1) Equipment loads and information; and
(2) Special system information.
g. Emergency or backup power, including:
(1) Onsite power from diesel generators; and
(2) Backup power from independent power transmission lines.
h. Lightning protection and grounding.
i. Controls and instrumentation.
j. Fire detection and alarm systems.
8. Provide general description of alarm, detection monitoring, and control
systems, including:
a. General definition of systems:
Attachment V-3
Page V-80
DOE 4700.1
3-6-87
(1) Safety;
(2) Security;
(3) Controls; and
(4) Fire Protection.
b. One-line diagrams and information.
c. Codes, standards, and guides.
d. Systems checkout and test requirements.
9. Provide general description of special facilities, equipment, or systems,
including:
a. General definition of facilities, equipment, or systems;
b. Participants and roles for design, procurement, and installations;
c. Layout configuration and identification;
d. Piping and instrumentation diagrams; and
e. Equipment service needs, loads and information, including:
(1) Electrical and mechanical; and
(2) Ventilation and filtration.
10. Provide general description of standard equipment, including:
a. Definition of standard equipment;
b. Participants and roles for procurement and installation;
c. Layout and identification; and
d. Service needs and loads.
11. Provide general description of quality assurance measures, including:
a. General quality assurance levels, including:
(1) Project;
(2) Architectural and civil;
DOE 4700.1
3-6-87
(3) Mechanical;
Attachment V-3
Page V-81 (and V-82)
(4) Electrical; and
(5) Special facilities and standard equipment.
b. Quality assurance manual and/or guides (examples or copies).
12. Provide general information relating to:
a. Required procurement clauses;
b. Type of specifications;
c. Contents of bid packages;
d. Available computer programs; and
e. Available reports and calculations related to the project.
Section 211
13. Provide a listing of suggested drawings and titles.
14. Provide required drawings size, type, and number of copies.
15. Provide estimated cost of construction and breakdown by cost elements.
DOE 4700.1
3-6-87 Attachment V-4
Page V-83
CONTROL AID DESCRIPTIONS
1. GANTT CHARTS (BAR CHART). The GANTT or bar chart is the most common of
control aids used in the construction industry. In many cases, it is the only
aid used. Perhaps the reason is its simplicity, almost universal understand-
ing, and ability to be used at all levels of supervision. The following
shortcomings of the bar chart should be kept in mind:
a. Failure to require a detailed analysis and breakdown of activities (freely
overlapped timewise);
b. Omissions of many time-consuming activities;
c. Failure to communicate complete details of the project plan (sequential
relationships not shown);
d. Failure to adequately indicate the consequences of scheduling deviations;
and
e. Failure to provide a suitable project model for updating purposes.
2. NETWORKING TECHNIQUES such as the critical path method and program evaluation
and review technique, were developed to overcome the disadvantages of the
GANTT chart. Networking is extremely valuable in executing a job; a hierarchy
of networks should exist in order to meet the needs of different levels of
management. A network is a dynamic document and requires continuous update
from the lowest detail in order to be of use to any level of management, a
requirement which must be considered in conjunction with the cost of manpower
and equipment to maintain the network system. Complicated and expensive pro-
cedures for updating and ineffectiveness as a management control at the low
level will cause the entire system to be useless at any level and a cost bur-
den to the project.
3. PERCENTAGE COMPLETION CURVE (S CURVE) illustrates forecasted and actual cumu-
lative percent completion plotted on a time scale and is used primarily as a
control tool. During the design effort productivity may be monitored, pro-
vided the system can measure actual work completed, by plotting in labor hours,
forecasted effort, actual work completed, and actual effort expended.
4. LABOR SCHEDULES may be developed for separate classifications of labor,
showing the number of persons required each time period.
5. MATERIAL SCHEDULES for important items of material or equipment indicating
deadlines for such events as vendor quotes, procurement, preparation of shop
drawings, beginning of fabrication, date of shipment, and date needed at job
site.
Attachment V-4
Page V-84
6. EQUIPMENT SCHEDULES may be developed for separate types and sizes of equipment
and showing the number of units required each time period.
7. FINANCE SCHEDULES indicate on a time scale the forecasted expenditures, the
actual expenditures, and the difference between the two.
DOE 4700.1
3-6-87
DOE 4700.1
3-6-87
Attachment V-5
Page V-85
YEAR
FY 1983
FY 1983
FY 1983
FY 1983
FY 1984
FY 1984
FY 1984
FY 1984
FY 1984
FY 1985
PLANNING CHRONOLOGY FOR FISCAL YEAR 1986
CONSTRUCTION BUDGET PROJECTS
ACTIVITY ELEMENTS FOR FY 1986 PROJECTS
1. Receipt of list of candidate projects
for FY 1986 accompanied by short-form
data sheets.
2. Headquarters program--division review
and decision on tentative 1986
projects. Notification to field of
selected projects.
3. Headquarters elements utilize selected
1986 tentative projects in planning,
programing, and budgeting process.
Section 212
4. Inclusion of FY 1986 plant engineering
and design requirement in FY 1985 budget.
5. Headquarters review of programmatic
requirements and supporting construction
program. Notification to field elements
of changes to tentative candidate projects.
6. Field elements submit updated construc-
tion project data sheets to Headquarters with
conceptual design report, if available.
7. Headquarters validation of construction
projects and utilization of construction
project data sheets for implementation
of planning, programming, and budgeting
process.
8. Field submission of additional data for
construction project data sheets.
9. Submission of budget to OMB.
10. Allotment of FY 1985 plant engineering
and design funds for FY 1986 projects.
TARGET DATES
2-1-83
Feb-March
NLT 4-1-83
Apr-May
8-83
11-83
12-83
NLT 1-1-84
NLT 3-1-84
3-84
7-84
NLT 8-1-84
9-84
10-84
Attachment V-5
Page V-86
FY 1985
FY 1985
FY 1985
FY 1985
FY 1986
FY 1986
11. Design started on FY 1986 projects with
FY 1985 plant engineering and design funds.
12. President's budget submitted to Congress.
13. Authorization and appropriate acts passed.
14. Design completed with FY 1985 plan
engineering and design funds.
15. OMB apportionment and DOE allotment to
field elements.
16. Design and/or construction started.
DOE 4700.1
3-6-87
12-84
1-85
6-85
9-85
9-85
10-85
10-85
12-85
DOE 4700.1 Attachment V-6
3-6-87 Page V-87 (and V-88)
SHORT FORM DATA SHEET CONTENTS
Short-form data sheets should be limited in size and content to not more than two
pages and shall contain, as a minimum, the following information:
1.
2.
3.
4.
5.
6.
7.
8.
HEADINGS. The first part of the data sheet shall contain:
a. Project title and location;
b. Program supported;
c. Submitting field office;
d. Total estimated cost and date of estimate;
e. Design start date; and
f. Construction complete date.
BACKGROUND AND JUSTIFICATION. This paragraph includes the requirements the
project will meet and the urgency; historical data supporting the need, or
reference thereto; and other indirect data which will support the necessity
for the project.
DESCRIPTION OF EXISTING CONDITIONS. This section shall include specific
standards, program milestones, regulations, orders, and guidance which are not
currently being met. If a new mission, reasons existing facilities cannot be
utilized should be indicated.
CONSEQUENCES OF FACILITY NOT BEING SUPPORTED. This section shall include
effects of nonsupport on program, employees, maintenance, and other elements
such as safety, environment, and operational costs.
TOTAL ESTIMATED COST (TEC). This section requires the best (planning) esti-
mate of project costs available. Costs shall be indicated separately for
engineering (Titles I through III), construction, and contingencies.
OTHER PROJECT COSTS. This section includes estimated direct costs not
included in total estimated costs such as conceptual design and R&D necessary
to complete construction.
PROPOSED SCHEDULE. Proposed start and end dates for conceptual design, defin-
itive design (both Titles I and II), construction, operation, and other major
milestones, if any, shall be indicated.
PLANT ENGINEERING AND DESIGN (PE&D) REQUIREMENTS. If PE&D funds are
requested, reasons for the requirements, date funds are required, extent of
design to be accomplished with these funds, and consequences of not providing
these funds shall be indicated.
EXAMPLE OF A SHORT FORM DATA SHEET
Section 213
Submission Date 2-1-83
SHORT FORM DATA SHEET
Operations Office Fiscal Year 1986 P r o g r a m
Oak Ridge Enthalpy Research
Laboratory and Production Facility
for Prototype Devices
Design Start: TEC: $30,000.000
11-15-84 Oak Ridge National Laboratory Estimate date 1-15-83
Construction Complete: Oak Ridge, Tennessee
10-1-87
1. Mission Requirements: Project supports new mission involving research on and production
of prototype devices for the enhancement of that recovery from various bodies. Project
is required to meet the national urgency needs as described in the Enthalpy Research
program plan. Need exists from documented research and validated need for increased
energy recovery. Complete justification for project and historical data are contained
in Enthalpy Research program plan.
2. This represents a new mission for the Oak Ridge Laboratories. Current and future
programmatic needs occupy 100 percent of available lab space and requirements exist for
2 million square feet of additional space for existing programs during the next 10
3.
years. Details are provided in FY 83-88 Institutional Plan of 11-1-82 and current Oak
Ridge Lab Site Development Plan with 5-year plan of 6-1-82.
If this facility is not operational on 10-1-87 the Enthalpy Research program needs will
be met with temporary facilities such as trailers and program milestones will slip a
minimum of 12 months. In addition, the program plan will require modification with
certain research and production postponed until completion of adequate facilities for
these programs.
Date 2-1-83 FY 1986
Page 2
SHORT FORM DATA SHEET
Laboratory and Production Facility
for Prototype Devices
4. Total Estimated Cost (TEC) $30,000,000
a. Engineering (Titles I through III) $ 4,000,000
b. Construction 22,000,000
c. Contingency 4,000,000
a.
5. Other Costs
Conceptual Design
b. R&D necessary to complete const.
6. Tentative Schedule Start
Conceptual Design 4-1-83
Title I 11-1-84
Title II 4-1-85
Construction 11-1-86
Operation 11-1-87
2,240,1O0
240,000
2,000,000
End
2-1-84
3-1-85
3-1-86
1O-1-87
- - -
7. Due to urgency of meeting operational date, request FY 85 PE&D Funds of 1,200,000 for
accomplishment of Title I and 40 percent of Title II design. These design funds will
allow sufficient design to be completed during FY 85 so that construction can begin
during the 1st quarter of FY 86. Failure to provide these funds will delay construc-
tion start one year from date contained in proposed schedule. This requirement is
currently included in item 4a. If approved, CPDS submission will indicate reduction of
TEC for PE&D Funds. If project is not considered in FY 86 budget, PE&D request for
FY 85 should still be supported since project is urgent and validated requirement.
Manager, Oak Ridge
Operations Office
DOE 4700.1 Chg 1
6-2-92
Attachment V-8
Page V-91
CONCEPTUAL DESIGN
1. As a key element of project planning, conceptual designs shall be
performed for construction projects for which congressional authorization
is planned to be requested prior to requesting Departmental approval.
Excepted from this requirement are general plant projects, line item
projects, and contingency line items which are specifically excepted by
the appropriate program organization. Conceptual designs for all projects
shall be authorized by DOE prior to initiation.
2. The fundamental objectives of conceptual design are to:
a. Develop a project scope that satisfies program needs, operating needs,
and statutory requirements;
Section 214
b. Assure and/or validate project feasibility and attainable technical
performance levels;
c. Identify and quantify any project risks; and
d. Develop a reliable cost estimate and a realistic performance schedule.
3. The guidelines developed as part of a conceptual design include the
following:
a. General project criteria and design parameters including applicable
codes and standards;
b. Quality assurance requirements to satisfy program and project
objectives;
c. Safeguards against potential environmental damage and methods for
mitigating environmental hazards;
d. Types and material of construction, basic facility drawings, and
outline construction specifications;
e. Space allowances for various functions;
f. Significant features and components;
g. Facility siting and utility services requirements;
h. Site development requirements;
i. Energy consumption and type(s) of energy supply;
j. Energy conservation initiatives and associated design/construction
features;
Vertical line denotes change
Attachment V-8
Page V-92
k. Health, safety, safeguards, and security requirements;
DOE 4700.1 Chg 1
6-2-92
l. Barrier-free design/construction features for facility accessibility
by the handicapped;
m. Total estimated cost, performance schedules for design, procurement
and construction, and methods of performance;
n. Requirements, cost estimates, and performance schedules for
prerequisite research and development related to the project;
o. Any other statutory or special requirements for the project;
p. Identification and elimination of uncertainties;
q. Acquisition strategy for the project;
r. Contingency requirements and analysis; and
s. Decontamination and disposal requirements.
4. Conceptual designs may be performed by operating contractors, onsite
services contractors, or by A-E firms. When choosing a conceptual
designer, the Head of the Field Element should, as a minimum, consider the
following factors:
a. Availability and expertise of operating or onsite services contractor
personnel;
b. Existing and projected workloads of these contractors;
c. Size, complexity, and urgency of the project;
d. Possibility of utilizing an economically disadvantaged A-E; and
e. The need to develop and enhance A-E capability within a geographical
area of operations.
5. For general plant and contingency projects (under $1.2 million), the Heads
of the Field Elements need to assure that the objectives of conceptual
design are met. Due to the size of these projects, this assurance may be
obtained by use of preliminary authorization requests or other locally
defined documents. These documents generally are developed by the
operating contractors in accordance with field element procedures. The
information developed shall generally cover the same basic elements as
conceptual designs, but in less detail.
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92 Attachment V-8
Page V-93 (and V-94)
6. It is important that sufficient conceptual design work be accomplished to
adequately scope each project and develop supportable project cost
estimates prior to project submittal to the Office of Management and
Budget. Field office managers shall sufficiently manage the conceptual
design effort to assure that the best possible scope and costs are
established in the time available. Conceptual designs will include a
preliminary work breakdown structure to delineate major project elements.
Section 215
a. Project urgency may require, in some cases, that a project be included
in the budget although conceptual design is not developed sufficiently
to establish reliable cost and schedule information. In these cases,
order of magnitude, cost estimates, and tentative scope determinations
shall be made. Reasons for this incompleteness shall be explained
within the construction project data sheets. In many of these cases,
the budget requests should be for design funds only.
b. For some projects, establishing, the scope and determining reliable
cost and schedule information may be beyond the reasonable limits of
conceptual design. In such cases, the budget request should also be
for design funds only.
Vertical line denotes change
DOE 4700.1 Attachment V-9
3-6-87 Page V-95
CONCEPTUAL DESIGN REPORTS
1. GENERAL. The conceptual design report is a summary of the conceptual design
results. The report contains the conclusions and recommendations reached as a
result of the conceptual design. Heads of Field Elements shall determine the
organization responsible for the preparation of the report. Normally, it
will be the organization performing the conceptual design. Reports shall be
approved and signed by the Head of the Field Element or his designee.
2. COVERAGE. A conceptual design report shall be prepared for all construction
projects for which conceptual designs are performed prior to inclusion of the
project in the DOE budget reports. Reports shall be submitted to
Headquarters.
3. CONTENTS. Arrangements, format, and content of the conceptual design report
shall be determined by Heads of Field Elements. The following items
shall be included as applicable:
a. Official project number and title.
b. Project justification.
c. Detailed description of the project scope.
d. Performance requirements for the project system or process.
e. Total estimated cost including individual estimates for each title of
design (I, II, and III), construction, standard equipments uncertainties,
and contingencies. Cost estimate methodology and backup details shall be
included.
f. Project design, procurement, construction, and environmental compliance
schedules (critical path method schedule is recommended).
g. Methods of performance for design, procurement, and construction with
backup details.
h. Work breakdown structure.
i. Requirements and assessments for:
(1) Safeguards and security;
(2) Energy conservation;
(3) Health and safety;
Attachment V-9 DOE 4700.1
Page V-96 3-6-87
(4) Environmental protection (detailed schedule for compliance with
National Environmental Protection Act and other environmental review
requirements as appropriate);
(5) Decontamination and decommissioning;
(6) Quality assurance;
(7) Maintenance and operation;
(8) Telecommunications;
(9) Computer equipment; and
(10) Provision for handicapped and fallout shelters.
j. Analysis of uncertainties, contingencies, and effort required to resolve
uncertainties.
k. Conceptual drawings and outline specifications.
l. Applicable codes, standards, and quality levels.
4. PROTECTION OF INFORMATION. Significant portions of conceptual design reports
have been held by the courts to be exempt from mandatory disclosure under the
Freedom of Information Act (FOIA) (5 U.S.C. 552), because the information is
recommendatory in nature and includes information which will be instrumental
in Government negotiations and which, if disclosed, would expose and jeop-
ardize the selection process for A-E contractors.
Section 216
a. The Head of the Field Element responsible for a conceptual design shall
assure protection of the conceptual design information. Only sufficient
copies of the conceptual design reports as are necessary to meet its
official purpose shall be generated. Distribution shall be limited to
those individuals or organizations which are necessary to fulfill
Department requirements.
b. The following legend shall be included in each conceptual design report:
"This Conceptual Design Report contains confidential commercial
information that shall be used or duplicated only for official
Governmental purposes, and this notice shall be affixed to any
reproduction or abstract thereof. Disclosure of the confidential
commercial information contained in this report outside the
Government shall not be made without the advice of counsel. The
restrictions contained in this notice do not apply to any data or
information in this report which is not commercial information or
to information generally available to the public on an
unrestricted basis.”
DOE 4700.1
3-6-87
CONCEPTUAL DESIGN REPORT
TITLE PAGE EXAMPLE
Conceptual Design Report
LABORATORY AND PRODUCTION FACILITY
FOR PROTOTYPE DEVICES AT
OAK RIDGE NATIONAL LABORATORY
Project 86-13-am
Attachment V-10
Page V-97 (and V-98)
For the
U.S. Department of Energy
Oak Ridge Operations Office
Oak Ridge, Tennessee
Prepared by Design Tech, Inc.
Architects & Engineers
Manager
Oak Ridge Operations Office
U.S. Department of Energy
3-18-84
2-28-84
DOE 4700.1 Attachment V-11
3-6-87 Page V-99
CONTENTS OF A TITLE I DESIGN SUMMARY
1. A Title I design summary should contain the applicable information listed
below, summarizing preliminary engineering and project management planning and
reflecting completed Title I design.
2. Project titles and project numbers shall be shown as they appear in the
authorization act or the financial plan, and for other projects, suitable
identification numbers shall be shown.
3. General description of work, consisting of a comprehensive statement outlining
the purpose of the facility, its location, the overall concept and layout, and
the types of facilities involved shall be included. If a fallout shelter is
to be provided, its location and significant features should be described.
4. An analysis of safety and pollution aspects, reflecting the latest project
planning and design information available prior to the start of any signifi-
cant Title II effort, should include, such as:
a. Discussion and analysis of the principal hazards and risks which may be
encountered in the operation of the proposed facility.
(1) Potential injury and property damage accidents due to fire, explo-
sion, radiation, structural failure, seismic activity, and operating
error;
(2) Predicted consequences of such accidents; and
(3) A thorough evaluation of the measures proposed for preventing such
accidents or reducing risks to acceptable levels, including
pertinent features of design and operation of the facility which
would provide primarily for protection of life and property (e.g.,
monitoring of, and protection from, radiation and fire).
b. Essential environmental considerations associated with the project. These
should be described in concise narrative form and include the following
kinds of information:
(1) Nature of potential environmental (air, water, land) impact including
types of pollutants, quantities, sources, release points, and prob-
able impacts;
Section 217
(2) Measures proposed to avoid adverse environmental effects and meet
applicable standards and guidelines (type and effectiveness of
proposed control and treatment methods, quality of effluents to be
discharged, and prevention of accidental releases); and
Attachment V-11
Page V-1OO
5.
6.
7.
8.
9.
DOE 4700.1
3-6-87
(3) Applicable environmental standards and guidelines currently in effect
and anticipated (e.g., Federal, State, and local effluent regula-
tions, EPA guidelines, DOE design criteria):
Justification and explanation of the factors used in establishing the size,
capacity, and type of equipment and structures required, or otherwise having a
bearing on the design and operation of the facility. The factors include:
a. Initial and ultimate planned capacity;
b. Type of feed, process flow diagrams, material balance flow sheet, and
product specifications;
c. Number of operating personnel, occupants, persons served, or extent of
services provided;
d. Type and extent of telecommunications and signal systems;
e. Material accountability; and
f. Security.
If a technical facility is involved, diagrams showing the processing or opera-
tions to be carried out should be furnished, including the reasons why the
selected process or type of facility is considered best.
Consideration given to existing structures and commercial-industrial sources
shall be outlined where not covered by prior project justification to Head-
quarters. This should include the reasons why existing structures cannot be
utilized, and an explanation of why the goods to be produced or the services
to be provided by proposed facility should not or cannot be obtained from pri-
vate enterprise through ordinary business channels. Specific steps taken to
determine availability from such sources and the basis upon which it has been
determined that it is not reasonable to obtain the goods or services from such
source, also should be provided.
Preliminary plans should consist of a plot plan, and building plans showing
the principal dimensions, equipment layout, partitioning, elevations typical
cross sections, space utilization, outside utility and site work, and so
forth. If a fallout shelter is included, its layout should be indicated on
the floor plan involved.
Outline specifications for buildings should consist of a statement showing the
principal materials to be used, the structural framing system, and exterior
and interior materials. The extent of features such as air-conditioning,
ventilation, air and water pollution control facilities, acoustical treatment,
hung ceilings, sprinklers, crane runways, and special construction because of
radioactivity, should be described. As a minimum, an order of magnitude
DOE 4700.1
3-6-87
Attachment V-11
Page V-101
statement is required instead of such statements as “to the extent required,”
and “as needed.” Where alternate materials may be specified for fire protec-
tion or safety reasons, note the reason (e.g., "to provide a 4-hour rated fire
wall, “ “to achieve a flamespread rating under 25”).
10. Major operating equipment needed should be indicated, including the estimated
electrical load for building services and operating equipment for major items
of mechanical equipment (air conditioning, ventilating, heating, and so forth)
type, functional requirements, and
telecommunications equipment, give
capacity.
11. Preliminary estimate of cost shall
the information at hand. General,
Section 218
estimated capacity shall be given. For
type and estimated size, number, power, or
be prepared as accurately as possible from
administrative, and other indirect costs
shall be prorated among the various elements of the project estimate. The
preliminary estimate shall be broken down as follows, generally conforming to
the procedure utilized on the construction project data sheets as contained in
the budget.
a. Engineering, Design, and Inspection Costs. (Also indicate this item as a
percentage of the construction costs shown in paragraph 11c, below);
b. Land and Land Rights, when applicable;
c. Construction Costs, including;
(1)
(2)
(3)
(4)
(5)
Improvements to Land, such as landscaping, roads, bridges, walks,
paved areas, drains, and fences;
Buildings (Building Construction or Remodeling), Including site
preparation directly related to the erection of the building and all
facilities required in the operation of buildings;
Other Structures, such as retention basins, pits, special use towers
and platforms, and stacks (when not an integral part of the
building);
Special Facilities. Including major items of special equipment and
systems specifically designed for the project, such as reactor
vessels, high vacuum systems, accelerator components special
environments, and movable shielding; and
Utilities, such as water, gas, electrical and sewer beyond a point 5
feet outside buildings (and utility extensions for building
additions).
d. Standard Equipment. Include all items, such as office, cafeteria, and
laboratory furniture and equipment, hoists, and machine tools, that can be
Attachment V-11
Page V-102
DOE 4700.1
3-6-87
e.
f.
g.
h.
procured with only a nominal engineering effort for selection; specifica-
tion, and inspection (as from a catalog or “off the shelf”). Exclude
items properly included in subparagraph 11c, above.
Removal Cost Less Salvage. Include removal costs less savings incidental
to the replacement of plant and equipment applicable to the project.
Contingency Allowance. Indicate the percentage this is of all other proj-
ect costs.
Energy Conservation. Specifically identify those items included to reduce
facility energy use. Provide the percent of the construction cost that
these items constitute.
Total Project Estimate. Sum of items a through f, above.
12. The above breakdown shall include quantities and unit costs showing how totals
were reached. For example, for buildings, give dimensions, the gross area,
and the estimated cost on a square-foot basis; for utilities, roads, and so
forth, give length, type, and size, with price per unit listed. Identify
originating organization, basis of estimate, date made, status of plans, and
any allowances made for isolation of construction area or speed up if other
than normal working hours are planned. Explain any unusually high or low unit
costs.
13. The cost or estimated value of any Government-owned materials or equipment
transferred to the project shall be stated separately in the project estimate.
Cost in this case refers to the current depreciated value (net book value),
not the cost of original acquisition. However, when an activity is moved from
one building to another, and the equipment that has been used by that activity
is moved with it, and such equipment remains in custody of the same contrac-
tor, only the moving and reinstallation costs are included in the project.
Section 219
14. Generally, the preliminary estimate includes only capital improvements.
However, in projects for which operating expense costs may be incurred with
the principal project activity, a cost description of work, and justification
for these costs, shall be included in the preliminary proposal. (Do not
include the cost of conceptual design. ) Where a project requires directly
related elements to be operating-expense funded, include a brief description
of each item, its estimated cost, and a schedule for accomplishing the item,
showing the estimated start and completion dates, and the relevant project
interface dates.
15. Proposed or actual starting and completion dates shall be indicated for
Title I and Title II engineering, procurement, and construction. Furnish the
same information for each of the participants in paragraph 16 below.
16. Proposed method of accomplishment shall include scope and estimate cost by
participants and types of contracts.
DOE 4700.1
3-6-87
Attachment V-12
Page V-103
CONSTRUCTION COMPLETION REPORT CONTENT
1. GENERAL. The following applies to all construction completion reports.
a. Additional date may be included as deemed necessary by the field office
manager.
b. The arrangement of information need not be as indicated in paragraph 2.
c. If a contractor is to prepare the report, the requirement should be
included in the contract.
d. The report should be adequately titled. Elaborate formats and binding
shall be avoided.
2. CONTENT.
a. Reports for all line item projects having a total estimated cost greater
than $5 million should contain the following information:
(1) General Information.
(a) Identification of project (name, location, field element, and
budget project number).
(b) Brief description of project, including its function, scope,
and relationship to other DOE facilities.
(c) Statement of major criteria which dictate type of design.
(d) Starting and completion dates for both overall design and
construction.
(e) Beneficial use dates for major components and initial operating
dates of production units.
(f) Layout plan and limited number of significant photographs of
the completed facilities.
(2) Contract Data. Contract data shall be furnished as outlined below.
If a single contract covers more than one project, give details.
(a) Architect-Engineer Contracts. For prime contracts, and sub-
contracts under operating contractors, furnish the following:
1 Name and home office of address of contractor, contract
number, and scope of work.
Attachment V-12 DOE 4700.1
Page V-104 3-6-87
2 Dates work was started and completed.
3 Final cost of work under the contract. Give breakdown of
costs by Titles I, II, and III, and other services. For
lump-sum contracts, list reimbursable costs separately.
4 Number of drawings and cost per drawing (based on Titles I
and II costs only) if available.
(b) Prime Construction Contracts and Cost-Plus-Fixed-Fee
Construction Subcontracts. Furnish all applicable information
set forth in subparagraph 2a(2)(a), above, for all prime
construction contracts (fixed-price and cost-plus-fixed-fee) and
cost-plus-fixed-fee construction contracts.
(c) Fixed-Price Construction Subcontracts Under Cost-Plus-Fixed-Fee
Contracts.
1 For principal fixed-price subcontracts under cost-plus-fixed-
fee prime contracts or subcontracts, give name of subcontrac-
tor, contract number, type of work, and final amount of each
subcontract.
Section 220
2 Give total dollar amount of all fixed-price construction sub-
contracts.
(d) Operating Contractor Participation. Where operating contractors
perform A-E and construction services, furnish all applicable
information set forth in subparagraph 2a(2)(a), above.
(e) Construction Manager Contracts. Furnish the following where
construction managers have been employed on the project;
1 Name and home office address of contractor and contract num-
ber;
2 Description of services provided during predesign, design,
and construction stages, as applicable; and
3 Final cost of work under the contract. For fixed-price
contracts, list reimbursable costs separately.
(f) Other Contractors. Give names of principal contractors,
contract number, amount of contract, and brief description of
work for special manufacturing, research and development,
testing, and other items, charged to project funds.
DOE 4700.1
3-6-87
Attachment V-12
Page V-105
(9) Major Equipment Suppliers. List the major suppliers of
process and other equipment items. Furnish contract number,
brief description of items, and final amount of contract.
(3) Descriptive Data.
(a) Buildings. Provide a description of major buildings,
including brief information on the following items;
1 General description of building (number of stories,
number of wings, overall dimensions, whether basement is
provided, significant materials or construction, and
finishes).
2 Each function or process carried on in the building.
Care shall be taken to avoid higher classification of the
complete report than necessary. Data of higher
classification may be submitted as an appendix if
desired.
3 Gross area and gross volume.
4 Building facilities, including:
a Ventilating and air conditioning (type and extent);
b Type of heating system;
c Major equipment;
d Type of fire protection (e.g., sprinklers, automatic
alarm); and
e Number of elevators (passenger and freight).
5 Special features (e.g., describe any radiation shielding,
protective construction, and so forth).
(b) Cafeteria. Give the overall size of kitchen and dining
area, number of serving lines, and number of seats.
(c) Laboratories. Indicate the extent (if any) and the activity
levels (high or low) of radioactive materials used.
(d) Utilities. Give a general description (materials, length
size of lines) of outside utilities.
Attachment V-12
Page V-106
DOE 4700.1 Chg 1
6-2-92
(4) Cost Data.
(a) Project Cost Summary.
1 Provide a cost summary broken down into the same major
categories as given in original project data sheet.
2 If a project includes several buildings or units, the
breakdown should give costs for major units separately.
3 The total cost of Government-owned materials or equipment
transferred to the project should be included above and
should be stated separately. Cost in this case refers to
transferred cost, not the cost of original acquisition.
4 Give original budget estimate and any revisions thereof.
(b) Unit Costs.
1 For each major building give:
a Cost per square foot of gross area; and
b Cost per cubic foot of gross volume.
2 Other Significant Costs. Give any unit costs available
for site and utility work of important building and
equipment components.
(5) Performance Data.
(a) Schedules.
1 Progress schedules for design and construction of overall
project as originally scheduled and as actually
accomplished.
2 Labor hours schedule for A-E and for construction
services as originally estimated and as actually
employed.
Section 221
(b) Factors Affecting Progress and Costs.
1 Discuss job progress and costs as affected by changes in
scope and delays by DOE; operating, A-E, and construction
contractors; vendors; weather; foundation conditions; and
others, as applicable.
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
Attachment V-12
Page V-107 (and V-108)
2 Actions which resulted in improvements in schedule or
cost reduction should also be covered. These are
extremely important since they can be utilized as case
histories in training or project manager personnel, and
can be disseminated Department-wide to assist others in
providing successful solution to construction related
problems. It is important that these items be recorded
as they occur during the execution of the project then
consolidated for inclusion in the construction completion
report. This is desired since a great portion of the
important data may be lost during the period of time
between the action and the preparation of the completion
report.
(c) Reports for all projects not covered by subparagraph 2a
above, including sub-projects of line items when submitted
individually, should contain the following information:
1 Project identification;
2 Start and completion dates for design and construction
(both baseline scheduled and actual);
3 Cost summary baseline and actual costs in the same major
categories included on the original project data sheet;
4 Factors that affected the cost and schedule, either
positively or negatively, that may be of benefit to
others, if any; and
5 All information required by the Real Property Inventory
System.
Vertical line denotes change