DOE O 4700.1 Chg 1, Project Management System
Functional areas: Project Management
Canceled by DOE O 430.1.
Superseded By:
DOE O 430.1, Life Cycle Asset Management on Jul 09, 1996
Version history and related documents
Superseded by
A newer version replaces this document.
- DOE O 430.1Life Cycle Asset Management (Jul 09, 1996)
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
3-6-87
Change 1: 6-2-92
PROJECT MANAGEMENT SYSTEM
1.
2.
3.
4.
PURPOSE. To establish the Department of Energy (DOE) project management
system and provide implementing instructions, formats, and procedures,
and to set forth the principles and requirements which govern the
development, approval, and execution of DOE’s outlay program
acquisitions as embodied in the Project Management System (PMS).
APPLICATION TO CONTRACTS. The provisions of this Order are to be
applied to covered contractors and they will apply to the extent
implemented under a contract or other agreement. A covered contractor
is a seller of supplies or services involved with Major System
Acquisitions, Major Projects, and Other Projects, as defined at Figure
I-1 on page I-3, and awarded a procurement contract or subcontract. The
term “procurement contract” does not include small purchases. Covered
contractors shall be required to comply with all paragraphs of this
Order except paragraph 10 on page 5.
REFERENCES. See Attachment 1.
POLICY.
a.
b.
c.
It is Department policy to manage all projects in accordance with
this Order. The chapters of this Order provide instructions,
formats, and procedures to implement the project management system.
Where programs/projects of a classified nature are conducted,
procedures will be tailored accordingly.
This Order does not apply to facilities and activities covered under
Executive Order 12344.
Pursuant to the Bonneville Project Act, the Federal Columbia River
Transmission System Act, the Pacific Northwest Electric Power
Planning and Conservation Act, and other statutory authorities, the
Administrator of the Bonneville Power Administration (BPA) is
authorized and directed to provide, construct, operate, maintain,
and improve electric transmission lines and facilities as necessary,
desirable, or appropriate for the purpose of transmitting electric
energy for sale to existing and potential markets. These
authorities are coupled with the Administrator’s responsibility to
ensure the safety, security, and reliability of electric power
Vertical line denotes change
All Departmental Elements Office of Procurement, Assistance
and Program Management
DOE 4700.1 Chg 1
6-2-92
2
5.
marketing and transmission as well as to meet its legal and
contractual obligations. In light of these unique authorities, this
Order shall not apply to BPA.
d. This Order does not alter the procedure outlined in the May 7, 1986
memorandum entitled “Modified Project Management System for the
Western Area Power Administration, Western Area Power
Administration.”
e. Formality and documentation requirements will be significantly
greater for Major System Acquisitions (MSAs) and major projects, but
this fact does not lessen the responsibility for proper planning and
execution of any project. Acquisition Executives, Program
Secretarial Officers and Heads of Field Elements shall ensure that
the project management system is implemented at a proper level in
all projects.
BACKGROUND.
a.
b.
c.
d.
e.
f.
The project management system has evolved as one of the principal
management processes for the Department. The principles, policies,
and procedures for the system were first promulgated in 1978. This
implemented and institutionalized OMB Circular A-109, Major System
Acquisitions, of 4/5/76.
The next step in the evolutionary process of PMS was issuance of a
requirement for decentralization in 1979. This policy brought the
field offices clearly into the process as a full partner in project
management.
Section 2
In 1980, the Acquisition Executive decision process for Major
Projects was delegated to the Program Secretarial Officers.
In 1989 and 1990 the Department emphasized the strengthening of the
project management system.
The project management system, since inception, has been
substantially improved to: (1) simplify the procedures; (2)
streamline the system; and (3) allow for management by exception.
This revision incorporates the following to the extent noted:
(1) SEN-6D-91, Departmental Organizational and Management
Arrangements, added titles to definitions.
(2) SEN-9-89, Federal Manager’s Financial Integrity Act and Audit
Resolution and Followup, of 7-26-89. Added in its entirety to
Chapter IV, Part A.
(3) SEN-1OE-91, Authorities and Responsibilities of the Deputy
Secretary and Under Secretary, of 6-17-91. Updated titles
throughout document.
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
3
(4) SEN-25-90, Strategic Planning Initiative, of 7-24-90. Added to
Chapter II.
(5) SEN-27-90, Strengthening the Department of Energy Project
Management System, of 8-15-90. Incorporated in its entirety
into Chapters I and II.
(6) DOE N 4700.4A, Baseline Change Control Process at the Executive
Level, of 10-31-91. Incorporated in its entirety into Chapter
III.
6. OBJECTIVES.
a. The primary objective of this Order is to assure the application of
sound management principles to provide a disciplined, systematic,
and coordinated approach to project management resulting in
efficient planning, organization, coordination, budgeting,
management, review, and control of DOE projects.
b. The overall objectives of the project management system and this
Order are to facilitate meeting mission needs, aid in achieving and
sustaining excellence in project management, minimize procedural
requirements, and foster the concepts of baseline management,
accountability, and performance assessment.
c. The specific objectives of the project management system are
summarized as follows:
(1)
(2)
(3)
(4)
(5)
(6)
Ensure all projects are based on clearly defined missions and
mission analyses and are developed with clear time-phased goals
and objectives that support program requirements.
Ensure proper coordination by all appropriate line and staff
elements beginning with program or project inception.
Provide a basis for determining priorities among programs and
projects, and, in turn, relate these to various levels of
resource availability.
Promote project execution which achieves tecnnical, schedule
and cost objectives. Technical objectives include safeguards
and security, environment, health, safety, quality assurance
and all programmatic aspects.
Avoid commitment of major resources prior to adequate project
definition.
Provide an overall plan for project execution including
evaluation of project progress in relation to specific
milestones. This plan should also identify the required
Government staffing as well as the responsibility and authority
of project and matrix staff.
Vertical line denotes change
4 DOE 4700.1 Chg 1
6-2-92
(7) Provide visibility on all key decisions and timely feedback for
all levels of management, and maintain accountability and
traceability of management decisions through and across all
levels of the organization with the minimal amount of
procedures and paperwork.
(8) Centralize authority for project approval and for allocation of
resources, and assure line management authority for project
execution and the utilization of resources in that execution.
Section 3
(9) To assure preparation of well planned budgets.
7. DISCUSSION.
a. The magnitude of the Department’s project management task is
formidable. The diverse array of project responsibilities and
activities requires wide familiarity with, and understanding and
working knowledge of scientific, engineering and managerial skills.
These attributes are necessary to assure that projects meet mission
needs, achieve planned technical and management objectives and are
accomplished on schedule, within cost and scope, and that the
projects serve the purposes intended.
b. This Order is the Department of Energy’s primary written reference
for project managers and program managers responsible for project
management.
c. The cost, complexity, and longevity of a multimillion-dollar effort
demands a formal management system, prescribed authorities and
responsibilities, and finite planning and control. These, in turn,
bring to mind project justifications, plans and charters, reporting,
and project review. However, every project effort--regardless of
size and complexity-has certain inherent characteristics.
Every project effort needs several specific ingredients:
(1) Someone in charge and accountable.
(2) An understanding of that person’s responsibility and authority.
(3) A clear definition of the work scope.
(4) An integrated schedule, including milestones (network
schedule).
(5) Supportive budget planning and execution that considers overall
funding availability within the Department as well as program
and project management.
(6) An overall plan for performance.
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
5
(7) Project execution against the plan.
(8) Sufficient reporting to stay aware of progress.
(9) Periodic management review to ascertain project status.
(10) Organizational commitment to successful project completion.
d. The management differences between MSAs, major projects, and other
projects have to do with substance, not intent. In other words, all
projects must be managed; the extent and formality of that
management is the only issue. Attachment 2 summarizes PMS
application.
e. The attached Chapters I through V comprise the Project Management
System.
8. DEFINITIONS. See Attachment 3.
9. RESPONSIBILITIES.
a.
b.
c.
d.
e.
Acquisition Executive and the Director of Procurement, Assistance
and Program Management, jointly determine and approve changes or
additions to the policies and procedures in the project management
system.
The Associate Director for Program/Project Management and Control
through the Director of Program/Project Management, is responsible
for initiating and updating the guidance for the project management
system, for monitoring its implementation, and for review and
concurrence of all reporting requirements.
Heads of Headquarters Elements assure that the provisions of this
Order, which apply to project management functions over which they
have program direction, both in the field and at Headquarters, are
carried out.
Heads of Field Elements carry out all project management functions
delegated or assigned by Program Secretarial Officers as required by
applicable directives.
Heads of Headquarters Elements and Heads of Field Elements (the
senior ranking DOE official at a DOE office location) shall include
in a procurement request package, for each procurement requiring the
application of this directive, the following: (1) identification of
the directive, (2) identification of the specific requirements with
which a contractor or other awardee is to comply, or, if this is not
practicable, identification of the specific paragraphs or other
portions of this directive with which a contractor or other awardee
is to comply, and (3) requirements for the flowdown
this directive to any subcontract or subaward. For
Section 4
of provisions of
application to
Vertical line denotes change
6
DOE 4700.1 Chg 1
6-2-92
awarded management and operating contracts, Heads of Headquarters
Elements and Heads of Field Elements may set forth this information
in a written communication to the contracting officer rather than in
a procurement request package.
BY ORDER OF THE SECRETARY OF ENERGY:
DONALD W. PEARMAN, JR.
Acting Director
Administration and Human
Resource Management
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
Attachment 1
Page 1
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
REFERENCES
DOE 1300.2A, DEPARTMENT OF ENERGY STANDARDS PROGRAM, of 5-19-92, which
establishes general policy guidelines, authorities and responsibilities
for DOE standards programs, use of voluntary consensus standards, and
guidelines for participation in private sector standards organizations.
DOE 1324.2A, RECORDS DISPOSITION, of 9-13-88, which assigns
responsibilities and authorities, and prescribes policies, procedures,
standards, and guidelines for the orderly disposition of Departmental
records.
DOE 1332.1A, UNIFORM REPORTING SYSTEM, of 10-15-85, which establishes and
provides implementing instructions for a uniform system of reporting the
accomplishments under contracts.
DOE 1332.2, UNIFORM REPORTING SYSTEM FOR FEDERAL ASSISTANCE (GRANTS AND
COOPERATIVE AGREEMENTS), of 10-31-83, which establishes and provides
implementing instructions for a uniform system of reporting the
accomplishments under grants and cooperative agreements.
DOE 1360.1A, ACQUISITION AND MANAGEMENT OF COMPUTING RESOURCES, of
5-30-86, which establishes Departmental policies and procedureS for the
acquisition and management of automatic data processing equipment and
resources.
DOE 2200.4, ACCOUNTING OVERVIEW, of 3-31-88, which establishes the
policy, principles, objectives, and responsibilities for Departmental
accounting and reporting in accordance with Government regulations and
generally accepted commercial and industrial accounting principles.
DOE 2200.9A, MISCELLANEOUS ACCOUNTING, of 3-30-89, which provides
Department of Energy (DOE) policy and general procedures for payroll
accounting (does not include payroll processing procedures), travel and
transportation accounting, financial closeout of contract procedures,
grant accounting, and accounting procedures unique to the power marketing
administrations.
DOE 2250.1D, COST AND SCHEDULE CONTROL SYSTEMS CRITERIA, of 6-12-92,
which delineates the requirements, procedures, authorities, and
responsibilities for establishing and documenting uniform standards for
assessing contractor cost and schedule control systems criteria (CSCSC).
DOE 3220.4, CONTRACTOR PERSONNEL AND INDUSTRIAL RELATIONS REPORTS, of
6-4-85, which prescribes policy and procedures, and assigns
responsibilities and authorities for the preparation and submission of
the subject reports.
DOE 4200.1C, COMPETITION IN CONTRACTING, of 1-9-87, which establishes
policies and procedures to assure that competitive procedures are
utilized to the maximum extent practical in the acquisition of personal
property and nonpersonal services.
Vertical line denotes change
Attachment 1 DOE 4700.1 Chg 1
Page 2 6-2-92
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
DOE 4240.1K, DESIGNATION OF MAJOR SYSTEM ACQUISITIONS AND MAJOR PROJECTS,
of 6-23-92, which lists the specific Department of Energy (DOE) projects
which have been designated as major system acquisitions and major
projects in accordance with the references.
Section 5
DOE 4300.16, REAL PROPERTY MANAGEMENT, of 7-1-87, which establishes DOE
policies and procedures for the acquisition, use, and disposal of real
estate or interest therein.
DOE 4320.16, SITE DEVELOPMENT PLANNING, of 1-7-91, which provides the
policy and procedures for site development, facility utilization, and
related planning.
DOE 4330.4A, MAINTENANCE MANAGEMENT PROGRAM, of 10-17-90, which provides
policy and procedures for the establishment of programs for the
maintenance and repair of Departmental property.
DOE 5000.3A, OCCURRENCE REPORTING AND PROCESSING OF OPERATIONS
INFORMATION, of 5-30-90, that sets forth policy, assigns responsibility,
and provides criteria and instructions for a system of reporting
occurrences that have programmatic significance to DOE operations,
analyzing the information reported and disseminating the analysis
results.
DOE 5100.3, FIELD BUDGET PROCESS, of 8-23-84, which provides requirements
and procedures for the preparation and submission of field budget
material for preparation of the Departmental budget.
DOE 5160.1A, REPROGRAMMING, RESTRUCTURING, AND APPROPRIATION TRANSFER
PROCEDURES, of 12-1-86, which establishes the major policies, criteria,
and procedures for initiating reprogramming, restructuring, and
appropriation transfer actions relating to the appropriation accounts of
the Department of Energy.
DOE 5440.1D, NATIONAL ENVIRONMENTAL POLICY ACT COMPLIANCE PROGRAM, of
2-22-91, which establishes procedures to implement regulation 10 Code of
Federal Regulations (CFR) 1021 for use in complying with the National
Environmental Policy Act of 1969 (NEPA), as amended; Executive Order
11514, as amended; as supplemented by the regulations of the Council on
Environmental Quality and DOE guidelines for compliance with NEPA;
including DOE’s “Environmental Compliance Guide,” Volumes I and II.
DOE 5480.1B, ENVIRONMENT, SAFETY, AND HEALTH PROGRAM FOR DOE OPERATIONS,
of 9-23-86, which establishes the environmental protection, safety, and
health programs for the Department of Energy operations.
DOE 5484.1, ENVIRONMENTAL PROTECTION, SAFETY, AND HEALTH PROTECTION
INFORMATION REPORTING REQUIREMENTS, of 2-24-81, which establishes the
requirements and procedures for the reporting of information having
environmental protection, safety, or health protection significant for
DOE operations.
Vertical line denotes change
DOE 4700.1 Chg 1 Attachment 1
6-2-92 Page 3
21.
22.
23.
24.
DOE 5500.2B, EMERGENCY CATEGORIES, CLASSES, AND NOTIFICATION AND
REPORTING REQUIREMENTS, of 4-30-91, which provides for the coordination
and direction of Departmental planning, preparedness, and response to
operational emergencies involving DOE or requiring DOE assistance, in
which there is a potential for personal injury, destruction of property,
theft or release of toxic, radioactive, or other hazardous material which
represent a potential threat, including terrorist threats of acts, to
health, safety, or the environment.
DOE 5500.3A, PLANNING AND PREPAREDNESS FOR OPERATIONAL EMERGENCIES, of
4-30-91, which establishes requirements for the development of DOE site
specific emergency plans and procedures for radiological emergencies
occurring in existing or planned DOE reactors and nonreactor nuclear
facilities.
DOE 5600.1, MANAGEMENT OF THE DEPARTMENT OF ENERGY WEAPONS PROGRAM AND
WEAPON COMPLEX, of 6-27-79, which establishes the policy and procedures
for the management of the Department’s weapons program and weapon complex
and utilization of the weapon complex facilities for nonweapon DOE
activities.
Section 6
DOE 5700.2C, COST ESTIMATING, ANALYSIS, AND STANDARDIZATION, of 11-2-84,
which establishes the policy and responsibilities for developing and
reviewing project cost estimates; preparing independent cost estimates
and analyses; standardizing cost estimating procedures; and improving
overall cost estimating and analytical techniques, cost data bases, cost
and economic models escalation, and cost estimating systems.
DOE 5700.6C, QUALITY ASSURANCE, of 8-21-91, which provides Departmental
policy, sets forth principles, and assigns responsibilities for
establishing, implementing, and maintaining programs of plans and actions
to assure quality of achievement in DOE programs.
DOE 5700.7B, WORK AUTHORIZATION SYSTEM, of 9-24-86, which establishes a
formal process for budget development, authorization, and monitoring of
Departmentally funded work performed at specified contractor facilities.
DOE 6430.1A, GENERAL DESIGN CRITERIA, of 4-6-89, to be implemented in
coordination with the Director of the Office of Administration and Human
Resource Management memorandum of 6-10-81, which establishes policies and
objectives, responsibilities and authorities, procedures, and
requirements for development and maintenance of general design criteria
and their application in the planning and design, or acquisition, of the
Department’s facilities.
DOE/S-00141, “National Energy Policy Plan of October 1983,” which
describes the policies, plans and goals for the Department of Energy.
DOE/MA-0040, “Cost and Schedule Control Systems Criteria for Contract
Performance Measurement, Work Breakdown Structure Guide,” of October
1981.
DOE/MA-0046, “Cost Estimating Manual,” of January 1982, which is a
compilation of DOE cost estimating procedures.
25.
26.
27.
28.
29.
30.
Vertical line denotes change
Attachment 1 DOE 4700.1 Chg 1
Page 4 6-2-92
31.
32.
33.
34.
35.
36.
DOE/MA-0063, Volume 1, “Cost Guide (Economic Analysis),” of January 1982,
which discusses economic analysis in cost estimating.
DOE/MA-0063, Volume 2, “Cost Guide (Standard Procedures for Determining
Revenue Requirements),” of June 1982, which concerns itself with
establishing standards for conducting economic evaluations using revenue
requirements or product cost methodology.
DOE/MA-0063, Volume 3, “Cost Guide (Cost Factors),” of April 1982, which
provides cost, labor, and material information concerning facilities or
systems.
DOE/MA-0063, Volume 4, “Cost Guide (Cost Data and Cost Estimating
Relationships--CER)," of May 1982, which details the methodology for
establishing CER’s on equipment, material, facilities, and modules.
DOE/MA-0063, Volume 5, “Cost Guide (Construction of Economic Escalation
Indices), Of May 1982, which covers the construction and use of price
change indices to be used in estimating and forecasting.
DOE/MA-0154, “Acquisition Regulators Handbook - Source Evaluation,” of
2-86 which provides guidance for carrying out procurement in excess of $5
million.
DOE/PR-0045, “DOE Acquisition/Assistance Guide for Technical Personnel.”
OMB CIRCULAR A-34, “Instructions on Budget Execution,” which applies to
the management of all appropriations, funds, and other authorizations,
except deposit funds.
OMB CIRCULAR A-76, “Performance of Commercial Activities,” of 8-4-83,
which sets forth procedures for determining whether commercial activities
should be performed under contract with commercial sources or using
government facilities and personnel.
Section 7
OMB CIRCULAR A-109, “Major System Acquisitions,” of 4-5-76, which
establishes policies to be followed by executive branch agencies in the
acquisition of major systems.
OMB CIRCULAR A-119, “Use of Voluntary Standards,” of 1-17-80, which
establishes policies to be followed by executive branch agencies in
working with organizations that plan, develop, produce, and coordinate
voluntary standards.
Federal Acquisition Regulations (FAR) of 4-1-84, which establishes
uniform acquisition regulations for use by Federal Agencies.
37.
38.
39.
40.
41.
42.
Vertical line denotes change
DOE 4700.1 Chg 1 Attachment 1
Page 5 (and 6)6-2-92
43. Department of Energy Acquisition Relations (DEAR) of 4-1-84, which
implements the provisions of the FAR.
44. P.L. 95-224, “Federal Grant and Cooperative Agreement Act of 1977,” which
describes the appropriate circumstances for using government contracts
grants or cooperative agreements.
45. P.L. 95-507, “Small Business Investment Act of 1977,” which provides
guidelines for the utilization of small and disadvantaged businesses in
government contracting.
Vertical line denotes change
DOE 4700.1
3-6-87
Attachment 2
Page 1
APPLICATION OF THE PROJECT MANAGEMENT SYSTEM
ELEMENT TO DOE PROJECTS
CHAPTER AND PART OF
ORDER
APPLICATION
MAJOR
SYSTEM MAJOR OTHER
ACQUISITION PROJECTS PROJECTS
(MSA) (MP) (OTHER)
ELEMENT
Acquisition Executive X X
Acquisition Strategy X X O
Advanced Acquisition or
Assistance Plan Projects X X O
I-C
II-E/Attachment II-6
II-E/Attachment II-7
IV-B/Attachment IV-7Annual Report for
General Plant Projects
Architect/Engineer (A/E)
Services
X
X
X
O
X
X
X X V-A
III-ABaseline
Business
X XManagement
Strategy Group II-E/Attachment II-6X X
X V-B/Attachments V-9
& V-10XConceptual Design Report
Configuration Management III-C/Attachments
III-5 & III-6X X
X
X
X
X
O
V-C/Attachment V-C-12Construction Completion Report X X
XX V-AConstruction Manager
X XContingency Management II-D
II-D X XCost Estimating
Cost and Schedule Control
Systems Criteria (CSCSC)
III-F/Attachment
III-F-7X X
O = Optional
X = Required
Attachment 2 DOE 4700.1 Chg 1
Page 2 6-2-92
ELEMENT
APPLICATION
CHAPTER AND PART OF ORDER
MSA MP OTHER
Design Criteria Package X X X V-A/Attachment V-3
Energy System Acquisition
Advisory Board (ESAAB) X O I-C/Attachments I-I & I-2
II-F
II-F
II-F
Environmental Assessment (EA) X X X
X
X
Environmental Compliance Plan X X
Environmental Impact
Statement (EIS) X X
Finding of No Significant
Impact (FONSI )
Independent Cost Estimate
(ICE)
X
X
X
X
X
X X II-F
X II-D
Internal Review Budget X X II-C
Justification of Mission X II-A/Attachment II-1 Need
Mission
Mission
Network
XAnalysis
Requirements
Scheduling
Diagram)
X I-B
X X X I-B
X X
X
X
X
X
X
II-A/Attachment H4(Logic
OMB Budget
Organizational Financial
Plan
X II-C
X II-C
Vertical line denotes change
DOE 4700.1 Attachment 2
3-6-87 Page 3
APPLICATION
ELEMENT CHAPTER AND PART
MSA MP OTHER OF ORDER
Performance Measurement
Program Manager’s Quarterly
Report to the Acquisition
Executive
Project Authorization System
Project Data Sheet
Project Management Plan (PMP)
Project Manager’s Progress
Report
Project Manager’s Quarterly
Supplemental Report, Cost and
Cost-Plus Commitment Chart
Project Manager’s Quarterly
Summary Report, Management
and Construction Manpower
Project Manager’s Quarterly
Summary Report, Progress
Photographs
Section 8
Project Manager’s Quarterly
Summary Report, Project
Activity
Project Plan (PP)
Project Plan Changes
(Baseline Changes)
x
x
x
x
x
x
O
O
o
x
x
x
x
x
x
x
x
x
o
0
o
x
x
x
III-F
IV-B/Attachment IV-8
V-A
II-A/Attachment II-5
II-A/Attachment II-4
IV-B/Attachment IV-1
IV-B/Attachment IV-4
IV-B/Attachment IV-5
IV-B/Attachment IV-6
IV-B/Attachment IV-3
II-A/Attachment II-2
II-A/Attachment II-3
Generic
Attachment 2
Page 4 DOE 4700.1
3-6-87
APPLICATION
ELEMENT CHAPTER AND PART
MSA MP OTHER OF ORDER
Project Reporting
Project Status Review
Project Transition Plan
Project Validation
Quality Assurance
Responsibility Matrix
Safety Analysis Review
(Report-SAR)
Semiannual Status Report
Status of DOE Energy
Management Projects
Summary Project
Performance Report to
Senior Management
Systems Engineering
Test and Evaluation (T&E)
Uniform Reporting System (URS)
Work Breakdown Structure (WBS)
Work Package Authorization
System (WPAS)
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
IV-B
IV-A
II-H
II-C
III-D
II-A/Attachment II-4
II-F
IV-B/Attachment IV-2
IV-B/Attachment IV-2
IV-B/Attachment IV-9
III-6/Attachments III-1 &
III-2
III-B/Attachments III-3 &
III-4
III-F
II-B
II-C
DOE 4700.1 Chg 1
6-2-92
DEFINITIONS
Attachment 3
Page 1
1.
2.
3.
4.
5.
6.
7.
ACCEPTANCE TESTING. The performance of all necessary testing to
demonstrate that installed equipment will operate satisfactorily and
safely in accordance with the plans and specifications. It includes
required hydrostatic, pneumatic, electrical, ventilation, mechanical
functioning and run-in tests of portions of systems, and finally of
completed systems.
ACQUISITION EXECUTIVE. The individual designated by the Secretary to
integrate and unify the project management system and to monitor
implementation of prescribed policies and practices. Approves the
initiation of a major system acquisition (or a selected major project)
and its transition through phases of the acquisition process and other
sub-phases involving major commitments; selects, from among competing
systems, those that are to be advanced to development, demonstration and
production/operations; and authorizes development of a noncompetitive
(single concept) system.
ACQUISITION PROPONENT. The DOE component having the primary
responsibility for research, development, demonstration, production or
operation of a major system acquisition project (to include, when
applicable, the system for its logistic support) which meets
Departmental objectives in carrying out DOE missions.
ACQUISITION STRATEGY. A description contained in the “Justification of
Mission Need” and subsequent Project Plan of the proposed overall DOE
business approach which will be utilized to ensure that the system being
acquired or supported satisfies the approved mission need. Specific
details of individual procurement actions should be made part of the
Advance Acquisition/Assistance Plan in the Project Management Plan.
ADVANCED DEVELOPMENT. The effort guided by the principle that the work
should lead ultimately to a particular application or product. Advanced
development can cut across several scientific disciplines and is
intended to explore focused innovation in a particular area of one or
more energy technologies.
Section 9
AGENCY COMPETITION ADVOCATE. The individual appointed pursuant to the
Competition in Contracting Act of 1984 to promote full and open
competition in the Department’s acquisitions and to challenge barriers
to competition. In DOE, this is the Competition Advocate located in the
Office of Procurement, Assistance and Program Management.
APPLIED RESEARCH. Systematic study directed towards fuller scientific
knowledge or understanding for direct use in fulfilling specific energy
requirements.
Vertical line denotes change
Attachment 3
Page 2
8.
9.
10.
11.
12.
DOE 4700.1 Chg 1
6-2-92
APPORTIONMENT. A distribution by the Office of Management and Budget of
amounts available for obligation in appropriation of fund accounts of
the executive branch. The distribution makes amounts available on the
basis of time periods (usually quarterly), programs, activities,
projects, objects, or combinations thereof. The apportionment system is
intended to achieve an effective and orderly allocation of funds.
APPROVED FUNDING PROGRAM (AFP). The AFP is an internal DOE document
issued by the Office of Budget to program managers and operating
activities, setting forth the funds available for the program release
activity in each appropriation and fund account. The AFP specifies
pertinent legal limitations and funding ceilings applicable to programs,
sub-programs, activities, and elements of expense. The AFP delegates
the authority to program managers to initiate program release documents
for their respective programs. Each allottee will use the AFP in
conjunction with the associated allotment to establish funding ceilings
on the obligational authority available to program managers and
organization elements (formerly referred to as Financial Plans).
ASSESSMENT. A determination of project or system acquisition conditions
based on a review of project cost, schedule, technical status, and
performance in relation to program objectives, approved requirements,
and baseline project plans. Assessments are made by the responsible
managing or advocate program organization or independently by the Office
of Program/Project Management. In all cases, assessments must be based
on knowledge of the actual project status, performance, problems, and
significant development in both the actual execution activities as well
as required institutional approval, licensing, review, and environmental
processes. They may take the form of:
a. Monthly report status ratings of project performance and outlook
prescribed rating categories; or
b. The Acquisition Executive; the Director of the Office of Procurement
Assistance and Program Management; or acquisition proponent review
ratings of project performance and outlook in similar rating
categories; or
c. Detailed evaluations of all project and system parameters prior to
phase change or key resource commitment decisions.
BASELINE. A quantitative expression of projected costs, schedule, and
technical requirements. Baseline establishment should include criteria
to serve as a base or standard for measurement during the performance of
an effort. It is the data plan against which the status of resources
and the progress of a project can be measured.
BASELINE CHANGE CONTROL BOARD. A multi-discipline functional body of
representatives designated and chartered by the appropriate management
level to ensure the proper definition, coordination, evaluation, and
disposition of all changes to project baselines within their chartered
jurisdiction.
Section 10
Vertical line denotes change
3DOE 4700.1 Chg 1 Attachment
6-2-92 Page 3
13.
14.
15.
16.
17.
18.
BASELINE CHANGE PROPOSAL (BCP). The instrument/document prepared to
provide a complete description of a proposed change and its resulting
impacts on project baselines.
BASIC RESEARCH. Systematic, fundamental study directed toward a more
comprehensive scientific knowledge or understanding of subjects bearing
on national energy needs.
BENEFICIAL USE OR OCCUPANCY DATE. The date on which a facility,
portions thereof, or the last piece of principal equipment, is released
for use by others, prior to final acceptance. Nonintegral or subsidiary
items and correction of design inadequacies subsequently brought to
light may be completed after this date. On multiple-facility projects,
beneficial use of the overall project will be the beneficial use date of
the last major building or facility.
CHANGE IN SCOPE. A change in objectives, work plan, or schedule that
results in a material difference from the terms of an approval to
proceed previously granted by higher authority. Under certain
conditions, stated in the approval instrument, change in resources
application may constitute a change in scope. Under contractual
agreement, contracting officers are the only Government personnel
authorized to issue a change order of contract modification to a
contractor/performer, in order to implement a change of scope. A change
in scope may also affect the availability of current year funds until
the proper congressional notification procedures have been executed.
(See Federal Acquisition Regulation (FAR) 43.101 for additional
information.)
COMPONENT. A major organizational subdivision of DOE, usually at the
program or sub-program level.
CONCEPTUAL DESIGN. Conceptual design encompasses those efforts to:
a. Develop a project scope that will satisfy program needs;
b. Assure project feasibility and attainable performance levels;
c. Develop reliable cost estimates and realistic schedules in order to
provide a complete description of the project for congressional
consideration; and
d. Develop project criteria and design parameters for all engineering
disciplines, identification of applicable codes and standards,
quality assurance requirements, environmental studies, materials of
construction, space allowances, energy conservation features, health
safety, safeguards, and security requirements and any other features
or requirements necessary to describe the project.
Vertical line denotes change
Attachment 3 DOE 4700.1 Chg 1
Page
19.
20.
21.
22.
23.
24.
4 6-2-92
CONDITIONAL OR PROVISIONAL ACCEPTANCE. The acceptance of a unit or
facility with a documented listing of the specific testing to be
accomplished or work remaining including the furnishing of any
outstanding submittal of technical and record data, to be completed by
the construction contractor, and on or by what date the actions are
scheduled to be complete.
CONFIGURATION. The functional and/or physical characteristics of
hardware and/or software, as set forth in technical documentation and
achieved in a product.
CONFIGURATION MANAGEMENT. The systematic evaluation, coordination,
approval (or disapproval), documentation, implementation, and audit of
all approved changes in the configuration of a product after formal
establishment of its configuration identification.
Section 11
CONSTRUCTION. Any combination of engineering, procurement, erection,
installation, assembly, or fabrication activities involved in creating a
new facility or altering, adding to, or rehabilitating an existing
facility. It also includes the alteration and repair (including
dredging, excavating and painting) of buildings, structures, or other
real property. This does not involve the manufacture, production,
finishing, construction, alteration, repair, processing or assembling of
items categorized as personal property. (See FAR 36.102 for additional
information.)
CONSTRUCTION COMPLETION DATE. The date on which work normally performed
by construction forces (including installation of equipment by operating
contractors or others) is accepted by the Government. This includes the
completion of all building items, the erection and/or installation of
mechanical units and/or processing equipment and the installation of all
furnishings as required to make a full functioning building, facility,
or process. Correction of minor deficiencies and exceptions may be
accomplished after the recorded date.
CONSTRUCTION MANAGEMENT. Services that encompass a-wide range of
professional services relating to the management of a project during the
pre-design, design, and/or construction phases. (These services are
deemed to be “professional” in accordance with FAR 15.204, Personal or
Professional Services.) The types of services include development of
project strategy, design review relating to cost and time consequences,
value engineering, budgeting, cost estimating, scheduling, monitoring of
cost and schedule trends, procurement, observation to assure that
workmanship and materials comply with plans and specifications, contract
administration, labor relations, construction methodology and
coordination, and other management efforts related to the acquisition of
construction.
Vertical line denotes change
DOE 4700.1 Chg 1 Attachment 3
6-2-92 Page 5
25.
26.
27.
28.
29.
30.
31.
32.
CONTINGENCY. An amount budgeted to cover costs that may result from
incomplete design, unforeseen and unpredictable conditions, or
uncertainties. The amount of the contingency will depend on the status
of design, procurement, and construction and the complexity and
uncertainties of the component parts of the project. Contingency is not
to be used to avoid making an accurate assessment of expected cost.
CONTRACT. A binding legal relationship basically obligating the seller
to furnish personal property or nonpersonal services (including
construction) for which the buyer compensates. It includes all types of
commitments which obligate the Government to an expenditure of funds and
which, except as otherwise authorized, are in writing. In addition to a
two-signature document, it includes all transactions resulting from
acceptance of offers by awards or notices of awards; agreements and job
orders or task orders issued thereunder; letter contracts; letters of
intent; and orders, such as purchase orders, under which the contract
becomes effective by written acceptance or performance. It also
includes contract modifications.
CONTRACT ADVANCE FUNDING. Obligations to a contract or project, to
cover future work or materials not yet ordered. The value of advanced
funding is the difference between uncosted obligation and unfilled
orders outstanding.
CONTRACTING OFFICER. A person designated to enter into and/or review,
modify, or terminate any contracts, financial assistance awards, and
sales contracts and make related determinations and findings.
Section 12
CONTRACTING OFFICER’S TECHNICAL REPRESENTATIVE. The individual in DOE
who is assigned responsibility for overall technical monitoring of a
contract and identified as such in the contract. The contracting
officer’s technical representative monitors the technical work performed
under the contract, evaluates the contractor’s performance, provides the
contractor and the contracting officer with technical guidance, reports
on contract status to DOE program and project management, and recommends
corrective action when necessary.
CONTRACTOR. The term “contractor” is intended to mean and include all
persons, organizations, departments, divisions, and companies having
contracts, agreements, or a memorandum of understanding with DOE.
COST ESTIMATE. A documented statement of costs estimated to be incurred
to complete the project. Cost estimates provide baselines against which
cost comparisons are made during the life of a project.
COST-SHARING CONTRACT. A cost-reimbursable type contract under which
the contractor receives no fee but is reimbursed only for an agreed
portion of its allowable costs. This type of contract is suitable for
those procurements that cover production or research projects which are
jointly sponsored by the Government and the contractor with benefit to
the contractor in lieu of full monetary reimbursement of costs. In
consideration of this benefit, the contractor agrees to absorb a portion
Vertical line denotes change
Attachment 3 D0E 4700.1 Chg 1
Page 6 6-2-92
33.
34.
35.
36.
38.
of the costs of performance. The following illustrate situations in
which this type of contract is generally desirable:
a. Jointly sponsored research and development work with nonprofit
educational institutions or other nonprofit organizations; or
b. Other research and development work where the results of the
contract may have commercial benefit to the contractor.
COSTS TO DATE. Costs incurred to date by the contractor and reported to
DOE. These are recorded as accrued costs. They represent all charges
incurred for goods and services received and other assets required,
regardless of whether payment for the charges has been made. This
includes all completed work and work in process, chargeable to the
contract. Accrued costs include invoices for: (1) completed work to
which the prime contractor has acquired title; (2) materials delivered
to which the prime contractor has acquired title; (3) services rendered;
(4) costs billed under cost reimbursement or time and material
subcontracts for work to which the prime contractor has acquired title;
(5) progress payments to subcontractors that have been paid or approved
for current payment in the ordinary course of business (as specified in
the prime contract); and (6) fee profit allocable to the contract.
DEFINITIVE WORK. The effort on which a contractual agreement for the
dollar value of the effort has been reached.
DELIVERABLE. A report or product of one or more tasks which satisfies
one or more objectives and must be delivered to satisfy contractual
requirements.
DEMONSTRATE. To verify the soundness of the chosen design concept(s) in
an environmentally acceptable manner, the technical and economic
feasibility of new or advanced equipment, and facilities or processes by
designing, constructing, testing, operating and evaluating near-full
scale modules.
DEMONSTRATION. The verification of scale-up, economic and environmental
viability for commercial application, through design, construction,
test, and evaluation of large-scale energy systems in operational
circumstances.
Section 13
37.
DEVELOPMENT. The development and test of systems and pilot plants
judged to be technically and economically desirable as a means of
achieving principal Departmental goals. Engineering development
concerns itself with processes, preproduction components, equipment,
subsystems, and systems. Initiation of work in this category is
dependent upon successful demonstration of technical feasibility and
economic, potential during the technology phase.
Vertical line denotes change
DOE 4700.1 Chg 1 Attachment 3
6-2-92 Page 7
39. DEVIATION. A specific, before-the-fact, written authorization to depart
from a particular performance or design requirement of a contract,
specification, or referenced document. A deviation differs from an
engineering change, in that, an approved engineering change requires
corresponding revision of the documentation defining the affected
product, whereas a deviation does not contemplate revision of the
applicable specification or drawing.
40.
41.
42.
43.
44.
DIRECT COST. Any cost that can be specifically identified with a
particular project or activity, including salaries, travel, equipment,
and supplies directly benefiting the project or activity.
DIRECTED CHANGE. A change imposed on a project(s), with direction to
implement, which affects one or more of the project’s (projects’)
baselines. Examples of directed changes include, but are not limited
to:
a.
b.
Changes to approved budgets, or funding; and
Changes resulting from DOE policy directives and regulatory or
statutory requirements.
ENGINEERING CHANGE. An approved change to controlled identification
documentation. An Engineering Change Proposal (ECP) is a recommended
Engineering Change (EC). There are typically two classes of EC’s:
a. Class 1. Changes of configuration which affect the Departmental
interest and require approval from the appropriate approval
authority or designated representative. Class 1 engineering changes
are those which affect: (1) technical baseline requirements and/or
(2) nontechnical contractual provisions such as fee, incentives,
cost, schedule, guarantees, or deliveries.
b. Class 2. Changes to a product which do not affect any of the Class
1 engineering change requirements. The Department’s approval prior
to implementation is not required, although such changes are subject
to post-facto classification review by the project office. Other
distinctions may be made at the discretion of the project manager.
ENGINEERING DEVELOPMENT. Systematic use of the knowledge and
understanding gained from research and technology development to achieve
the detailed design, construction and test for performance,
producibility and reliability of energy system prototypes, pilot plants,
and research facilities.
ENVIRONMENT(AL). Air and water quality, land disturbances, ecology,
climate, public and occupational health and safety, and socioeconomic
(including nonavailability of critical resources and institutional,
cultural, and aesthetic) considerations. For conciseness, these are
normally referred to as environment, safety and health considerations.
Vertical line denotes change
Attachment 3 DOE 4700.1 Chg 1
Page
45.
46.
47.
48.
49.
50.
51.
8 6-2-92
FACILITIES. Buildings and other structures; their functional systems
and equipment, including site development features such as landscaping,
roads, walks, and parking areas; outside lighting and communications
systems; central utility plants; utilities supply and distribution
systems; and other physical plant features.
Section 14
FIELD OFFICE (FO). The new designation for the nine major Departmental
offices responsible for day-to-day management of designated functional
activities.
FINAL ACCEPTANCE. A written statement by the contracting officer or
designee that the work performed by the construction contractor has been
accepted as being in accordance with approved plans and specifications.
The operating contractor should also be included in the final
acceptance, if applicable, indicating acceptance of the facilities as
constructed and the date the facilities are to be occupied or available
for the use of operating contractor.
FIXED PRICE CONTRACTS. Fixed price contracts provide for a firm price
or, under appropriate circumstances, may provide for an adjustable price
for the supplies or services that are being procured. In providing for
an adjustable price, the contract may fix a ceiling price, target price
(including target cost), or minimum price. Unless otherwise provided in
the contract, any such ceiling, target, or minimum price is subject to
adjustment only if required by the operation of any contract clause
which provides for equitable adjustment, escalation, or other revision
of the contract price upon the occurrence of an event or a contingency.
FORECAST. The DOE project management office’s most current performance
projection for cost, schedule, and scope.
GENERAL PLANT PROJECTS (GPP). Congress has recognized DOE’s need to
provide for miscellaneous construction items which are required during
the fiscal year and which cannot be specifically identified beforehand.
Congress provides, annually, an amount for these purposes under the
title of General Plant Projects.
GENERAL PURPOSE FACILITIES PROJECTS. Line item construction projects
estimated to cost greater than $1.2 million and which are required to
support the long-term administrative and technical needs of DOE-operated
laboratories and facilities. Examples of general purpose facilities
projects are light or heavy laboratories, administrative offices,
machine shops, steam plants, electrical utilities, roads, railroads, and
warehouses. Multiprogram general purpose facilities are restricted to
general purpose facilities projects at the multiprogram
laboratories/site where no one program will use more than approximately
60 percent of the planned facility.
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
Attachment 3
Page 9
52. GOVERNMENT ESTIMATES. Estimates are used to determine the
reasonableness of competitive bids received in connection with formally
advertised construction contracts, and serve as a control in evaluating
cost and pricing data in negotiated contracts. Normally, the Title II
design estimate, after being reviewed and approved by the Government, is
the basis for the Government estimate. However, the services of an
operating contractor, architect-engineer, cost-plus-fixed-fee
construction contractor (with respect to subcontracts), or construction
manager may be used appropriately to prepare, review, or revise the
Government estimate prior to Government approval (refer to FAR 36.203).
Cost-type contractors shall be required to follow cost estimate
procedures when subcontracting for construction services. Government
review and approval of the Government estimate is not required when the
estimate is within the limits established by the Government’s approval
of the cost-type contractors procurement system. The specifics of a
Government estimate vary with the size and type of contract.
Section 15
53. INCURRED COSTS. Costs are applied to the performance of the project.
All costs incurred for a project are reported whether they arise from
payments, cost accruals, or transfers of costs from other DOE locations
or Federal agencies. Any time costs are incurred by cost-type
contractors, the amount will be included in that period. Incurred costs
also comprise payments made or due to date, including any retained
percent-ages, and lump-sum and unit price contracts based on payment
estimates approved by the contracting officer and designated
representative for the purpose of making the progress or final payments
on work performed to date. Costs shall not be accrued on the basis of a
percentage of physical completion, unless the amounts of such costs are
approved by the contracting officer or his or her designated
representative as progress or partial payments.
54. INDEPENDENT ASSESSMENT. An assessment, made outside the normal advocacy
chain, of a project’s status or condition. In the project management
system, it is made by the Office of Program/Project Management in its
role of independent monitoring. It will consist of independent
evaluation of all pertinent factors in order to provide a condition
rating or detailed analysis of the project or system situation.
Independent assessments will typically be provided in conjunction with
Headquarters reporting to senior DOE management; advisory board decision
reviews; or other purposes associated with the program planning and
budgeting system, acquisition or other DOE management control and
direction processes. These independent evaluations must be based on
knowledge of the actual project and related institutional matters. The
Office of Program/Project Management will obtain this knowledge through
reports from the project management and program organizations; conduct
of field and Headquarters reviews with the program organization, the
Departmental managing office and principal contractors; and direct
communication and discussion of project matters with the DOE managing
and program offices.
Vertical line denotes change
Attachment 3 DOE 4700.1 Chg 1
Page
55.
56.
58.
60.
61.
62.
10 6-2-92
INDEPENDENT COST ESTIMATE. A documented cost estimate that has the
express purpose of serving as an analytical tool to validate, cross-
check, or analyze estimates developed by proponents for a project. An
independent cost estimate also serves as a basis for verifying risk
assessments. It is usually performed by an independent contractor.
57.
INDIRECT COST. A cost incurred by an organization for common or joint
objectives and which cannot be identified specifically with a particular
project or activity. See 10 CFR 600.
INSPECTION. The survey of a unit, facility or area to determine overall
compliance with contract drawings and specifications. It may vary from
inspection of detailed items to extensive testing of operating equipment
(which must be provided for in the contract). It may also serve in
making a determination of the adequacy of the design effort. It
includes a preliminary inspection to fix the number of work items
remaining to be completed (list of exceptions or “punch list”), and a
final inspection to accept the completed construction. (See Title III
Services)
LEAD PROGRAM SECRETARIAL OFFICER (LPSO). The individual assigned line
management responsibility and accountability for Headquarters and field
operations and to which one or more multiprogram field offices report
directly.
Section 16
LIFE CYCLE COST (LCC). The sum total of the direct, indirect,
recurring, nonrecurring and other related costs incurred or estimated to
be incurred in the design, development, production, operation,
maintenance, support and final disposition of a major system over its
anticipated useful life span. Where system or project planning
anticipates use of existing sites or facilities, restoration, and
refurbishment costs should be included.
LINE ITEM PROJECTS. Projects which are specifically reviewed and
approved by Congress. Projects with a total project cost greater than
$1.2 million are categorized as line item projects.
LONG LEADTIME PROCUREMENT ITEMS. Those items of equipment and/or
construction materials that require an order date prior to the estimated
physical construction start to assure availability at the time needed so
as not to delay the construction performance.
59.
MILESTONE. An important or critical event and/or activity that must
occur in the project cycle in order to achieve the project objective(s).
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
Attachment 3
Page 11
63. MISSIONS.
64.
66.
a. Responsibilities assigned to the Department of Energy for meeting
national needs. Agency missions are defined by the Comptroller
General of the United States in Budgeting Definition s, November
1975, as:
“Those responsibilities for meeting national needs assigned to
a specific agency. Agency missions are expressed In terms of
the purpose to be served by the programs authorized to carry
out functions or subfunctions which, by law, are the
responsibility of that agency and its component organizations.
(See Section 201 of the Budget and Accounting Act, 1921, as
amended.)”
b. Additionally, Section 601(i) of the Congressional Budget Act of 1974
(Public Law 93-344) requires that:
“The Budget. ..” shall contain a presentation of budget
authority, proposed outlays, and descriptive information in
terms of:
(1) a detailed structure of national needs which shall be
used to reference all agency missions and programs;
(2) agency missions; and
(3) basic programs.
“To the extent practicable, each agency shall furnish
information in support of its budget requests in accordance
with its assigned missions in terms of Federal functions and
subfunctions, including mission responsibilities of component
organizations, and shall relate its programs to agency
missions.”
MISSION ANALYSIS. Continuing analysis of assigned mission areas,
reconciled with overall program capabilities technological
opportunities, priorities, and resources that are involved.
65. MISSION AREA ASSIGNMENT. Assignment to a Program Secretarial Officer,
by the Secretary, of the responsibility for the formulation and conduct
of programs to carry out functions or subfunctions which by law and
Administration policy are within the mission responsibilities of the
Department.
MISSION NEED. A required capability within DOE’s overall purpose,
including cost and schedule considerations. When the mission analyses,
or studies directed by appropriate executive or legislative authority,
identify a deficiency in existing capabilities or an opportunity, this
will be set forth as justification for purposes of system acquisition
approvals, planning, programming, and budget formulation.
Vertical line denotes change
Attachment 3 DOE 4700.1 Chg 1
Page
67.
68.
69.
70.
12 6-2-92
OPERATIONAL DATE.
Section 17
a. Production Plant. The date when operations personnel introduce feed
materials into the process equipment with the intent to produce the
design plant product (excludes functional testing). For gaseous
diffusion plants, term “on-stream date” is synonymous with operation
date.
(1) Initial Operational Date. If the facility is a multiple unit
type, the date on which feed materials are introduced into the
first of a number of process or production units.
(2) Complete Operational Date. If the facility is a multiple unit
type, the date on which feed materials are introduced into the
last of the process of production units.
b. Reactor.
(1) Initial Operational Date. The date on which initial
criticality is achieved.
(2) Complete Operational Date. The date on which tests have been
completed and permission granted by the designated authority to
go to full power for purposes of normal operation.
c. Accelerators. The date on which operations personnel inject a
subatomic particle into the accelerator and achieve an initial
accelerated beam.
d. Other. Normally, the date on which a building or facility is first
occupied and functions in accordance with its intended purpose.
However, on development projects it refers to completion of the
first major milestone in output.
ORIGINAL ESTIMATE. The first total estimated and total project cost
that are shown: (1) in a project data sheet submitted to the Congress
for line item projects; or (2) in a project data sheet submitted to OMB
for contingency type projects; or (3) in the initial authorization for
general plant, operating funded, equipment funded, or other contingency-
type projects.
ORIGINAL SCHEDULE DATES. The start and finish dates of design,
construction, procurement, and operation submitted in conjunction with
the original estimate or in the first approved schedule.
PHYSICAL CONSTRUCTION START. For purposes of reporting construction
progress, the date on which work at the site physically starts,
including work on site preparation, temporary construction and any earth
moving. The start date of construction of permanent facilities should
also be indicated.
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
Attachment 3
Page 13
71.
72.
73.
PLANNING ESTIMATES. Developed for each project at the time of project
identification. Since these are developed prior to conceptual design,
they are order of magnitude only and have the least amount of accuracy
and lowest confidence level. Care should be exercised in these
estimates to assure that the order of magnitude is correct, since a
tendency exists to avoid changing this estimate, particularly upward,
once established.
PLANT ENGINEERING AND DESIGN FUNDS. Appropriated by Congress at the
request of the Department for the performance of Title I and Title II
design prior to authorization and appropriation of construction funds
for a project. Plant engineering and design funds are limited to
requests for projects which will receive high priority in future year
budget submittal. Completed conceptual design is a prerequisite for
allocation of plant engineering and design funds.
Section 18
PRELIMINARY DESIGN (TITLE I). Continues the design effort utilizing the
conceptual design and the project design criteria as a basis for project
development. Title I design develops topographical and subsurface data
and determines the requirements and criteria which will govern the
definitive design. Tasks include preparation of preliminary planning
and engineering studies, preliminary drawings and outline
specifications, life-cycle cost analysis, preliminary cost estimates,
and scheduling for project completion. Preliminary design provides
identification of long lead procurement items and analysis of risks
associated with continued project development. For a detailed
description of the services provided during preliminary design, see
Department of Energy Acquisition Regulation (DEAR) 936.605c and
952.236.70.
74.
75.
PRODUCT DATA REQUIREMENT. A contract requirement which directs
contractors to collect, organize, prepare, maintain, transmit, deliver,
or retain information incident to the design, development, production,
operation, preservation, maintenance, or repair of contract end items.
Product data includes engineering drawings, product specifications and
standards, part breakdown lists, catalog item physical qualities and
characteristics, preprocurement data, test plans and reports, and other
such data.
PROGRAM. An organized set of activities directed toward a common
purpose, or goal undertaken or proposed in support of an assigned
mission area. It is characterized by a strategy for accomplishing a
definite objective(s), which identifies the means of accomplishment,
particularly in quantitative terms, with respect to manpower, materials
and facilities requirements. Programs are typically made up of
technology base activities, projects, and supporting operations.
Vertical line denotes change
Attachment 3 DOE 4700.1 Chg 1
Page 14 6-2-92
76.
77.
78.
80.
81.
PROGRAM ASSESSMENT. A determination of program condition based on a
review of cost, schedule, technical status and performance in relation
to mission area assignments, program objectives, approved strategy and
milestones. Assessments are made by the responsible line program
organization and outside the advocacy chain by the Office of Program/
Project Management. In all cases, program assessments must be based on
knowledge of the actual program status, performance, problems, and
significant development in approval; review; and environment, safety,
health, and quality assurance processes.
PROGRAM MANAGEMENT. Management responsibility and authority for
specific programs will normally be delegated by the cognizant Program
Secretarial Officer. The Headquarters functions of program management
includes planning and developing the overall program; establishing broad
priorities; providing policy and broad program direction; preparing and
defending the budget; establishing the technical performance, scope,
cost, and schedule requirements for projects; controlling DOE
Headquarters-level milestones; integrating all components of the
program, providing public and private sector policy liaison; expediting
Headquarters interface activities and followup actions; and retaining
overall accountability for program success. The field function includes
implementing these program activities, controlling field-level
milestones, and providing major support to the Headquarters programming
budgeting and processes.
Section 19
PROGRAM MANAGER. An individual in an organization or activity who is
responsible for the management of a specific function or functions, who
is responsible for budget formulation, and for execution of the approved
budget. The Program Manager receives an approved funding program from
the Chief Financial Officer identifying program dollars available to
accomplish the assigned function.
PROGRAM OBJECTIVES. A statement or set of statements defining the
purposes and goals to be achieved during performance of a program to
fulfill a DOE mission including the technical capabilities, cost, and
schedule goals.
PROGRAM OFFICE. The Headquarters organizational element responsible for
managing a program.
PROGRAM SECRETARIAL OFFICER (PSO). A senior outlay program official
which includes the Assistant Secretaries for Conservation and Renewable
Energy (CE), Defense Programs (DP), Fossil Energy (FE), Nuclear Energy
(NE), Environmental Restoration and Waste Management (EM) and the
Directors of Energy Research (ER), Civilian Radioactive Waste Management
(RW), and New Production Reactors (NP).
79.
Vertical line denotes change
DOE 4700.1 Chg 1 Attachment 3
6-2-92 Page 15
82.
83.
84.
85.
86.
PROJECT. A project is a unique major effort within a program which has
firmly scheduled beginning, intermediate, and ending date milestones;
prescribed performance requirements, prescribed costs; and close
management, planning, and control. A project is a basic building block
in relation to a program which is individually planned, approved and
managed. A project is not constrained to any specific element of the
budget structure (e.g., operating expense or plant and capital
equipment). Construction, if required, is part of the total project.
Authorized, and at least partially appropriated, projects will be
divided into three categories: major system acquisitions, major
projects, and other projects.
PROJECT DATA SHEET. A generic term defining the document containing
summary project data and justification required to include the entire
project effort as a part of the Departmental budget. Specific
instructions on the format and content of the project data sheet are
contained in the annual budget call, and DOE 5100.3.
PROJECT DESIGN CRITERIA. Those technical data and other project
information developed during the project identification, conceptual
design, and/or preliminary design phases. They define the project
scope, construction features and requirements, and design parameters;
applicable design codes, standards, and regulations; applicable health,
safety, fire protection, safeguards, security, energy conservation, and
quality assurance requirements; and other requirements. The project
design criteria are normally consolidated into a document which provides
the technical base for any further design performed after the criteria
are developed.
PROJECT MANAGEMENT. A management approach in which authority and
responsibility for execution are vested in a single individual, at a
level below the general manager, to provide focus on the planning,
organizing, directing, and controlling of all activities within the
project. In general terms, project management functions include
assisting the program manager in preparing Headquarters documents and
establishing key milestones and overall schedules. Other activities
include developing and maintaining the project management plan; managing
project resources; establishing and implementing management systems,
including performance measurement systems; and approving and
implementing changes to project baselines.
Section 20
PROJECT MANAGER. An official who has been assigned responsibility for
accomplishing a specifically designated unit of work effort or group of
closely related efforts established to achieve stated or designated
objectives, defined tasks, or other units of related effort on a
schedule for performing the stated work funded as part of the project.
The project manager is responsible for the planning, controlling, and
reporting of the project.
PROJECT OFFICE. The organization responsible for administration of the87.
project management system, maintenance of project files and documents,
and staff support for officials throughout the project life cycle.
Vertical line denotes change
Attachment 3 DOE 4700.1 Chg 1
Page
88.
89.
90.
93.
94.
16 6-2-92
PROJECT SUMMARY WORK BREAKDOWN STRUCTURE. A summary work breakdown
structure tailored by project management to the specific project with
the addition of the elements unique to the project. Generally, the
project summary work breakdown structure will identify project elements
through the third level.
PROJECTIONS. Estimates of budget authority, outlays, receipts, or other
budget amounts that extend a minimum of 5 years beyond the current year.
Projections generally are intended to indicate the budget implications
of continuing current or currently proposed programs and legislation for
an indefinite period of time. These include alternative program and
policy strategies and ranges of possible budget amounts. Projects
should be regarded neither as firm estimates of what actually will occur
in future years nor as recommendations regarding future budget
decisions.
QUALITY ASSURANCE. All of the planned and systematic actions necessary
to provide adequate confidence that a facility, structure, system or
component will perform satisfactorily in service. Quality assurance
includes quality control, which comprises all those actions necessary to
control and verify the features and characteristics of a material,
process, product, or service to specified requirements.
91. REAL PROPERTY. Land and/or improvements including interests
except public domain land.
SCOPE . In baseline management terminology, the term “scope”
therein,
refers to92.
those performance and design requirements, criteria, and characteristics
derived from mission needs that provide the basis for project direction
and execution. In budget terminology, the term “scope” refers to the
congressionally approved project parameter/tasks as defined in the
Congressional Project Data Sheet.
SITE. A geographic entity comprising land, buildings, and other
facilities required to perform program objectives. Generally a site
has, organizationally, all of the required facilities management
functions. That is, it is not a satellite of some other site.
SITE DEVELOPMENT AND FACILITY UTILIZATION PLAN (SITE DEVELOPMENT PLAN).
A formal written document summarizing all of the various data necessary
to plan for the most effective utilization, orderly future development;
and disposal of facilities at an individual site. Such planning shall
be in accordance with site related program objectives and requirements
and shall represent the consolidated views of site management, the field
organization and the resource sponsor.
95. SITE OFFICE. Term used to describe small organizations established near
work sites for the accomplishment of specific projects or work
assignments receiving administrative support from another field
organization.
Vertical line denotes change
Section 21
DOE 4700.1 Chg 1 Attachment 3
6-2-92 Page 17
96.
97.
98.
STATE-OF-THE-ART TECHNOLOGY ASSESSMENTS. An integral part of the
technology base element of a program. The objective of these
assessments is to ensure that technology base and project activities can
benefit from relevant state-of-the-art technology where appropriate.
Furthermore, these assessments can assist in the identification of
mission needs and ensure that DOE officials have a clear understanding
of where a specific energy-related technology stands before making
significant program or project decisions.
SUBCONTRACT. Any agreement or arrangement between a contractor and any
person (in which the parties do not stand in the relationship of an
employer and an employee):
a. For the furnishing of supplies or services or for the use of real or
personal property, including lease arrangements, which, in total or
in part, is necessary to the performance of any one or more
contracts; or
b. Under which any portion of the contractor’s obligation under any one
or more contracts is performed, undertaken, or assumed.
SUBSYSTEM. An aggregation of component items (hardware and software)
performing some distinguishable portion of the function of the total
system of which it is a part. Normally, a subsystem could be considered
a system in itself, if it were not an integral part of the larger
system.
99. SUPPORTING OPERATIONS. All work in an outlay program that is not in the
science and technology base activity and not in projects. It includes
program overhead, personnel, and standing studies, and is generally
characterized by level of effort.
100. SYSTEM. A collection of interdependent equipment and procedures
assembled and integrated to perform a well-defined purpose. It is an
assembly of procedures, processes, methods, routines, or techniques
united by some form of regulated interaction to form an organized whole.
101. TECHNICAL BASELINE. A configuration identification document or a set of
such documents formally designated and approved at a specific time.
(The time need not be the same for each document in the set. ) Technical
baselines, plus approved changes to those baselines, constitute the
current configuration identification.
102. TECHNICAL DIRECTION. The monitoring or surveillance of the scientific,
engineering, and other technical aspects of a work program, as
distinguished from the administrative and business management aspects.
Vertical line denotes change
Attachment 3 DOE 4700.1 Chg 1
Page
103.
104.
105.
106.
107.
108.
109.
18 6-2-92
TECHNOLOGY. A demonstration by experiment of the technical feasibility
of alternative inventive concepts. This category may concern itself
with processes, components, equipment, subsystems, or initial system
prototype, and may encompass: experimental exploitation and refinement
of a known phenomenon; demonstration of the acceptability of the
technical and operational characteristics of one or more specific
concepts; and preliminary system studies responsive to a particular
problem including system analysis, tradeoff, preliminary cost/benefit
studies, and planning and programming studies.
TECHNOLOGY BASE. The equipment and facilities produced for, and the
accumulated results and skills produced by, the conduct of basic
research, applied research and technology development.
TECHNOLOGY OR EXPLORATORY DEVELOPMENT. The systematic application of
knowledge from research toward proof of technology, including
development of nonspecific application prototypes and processes.
Section 22
TITLE I DESIGN ESTIMATES. Estimates prepared upon completion of Title I
design. Through use of plant engineering and design funds, Title I may
be completed prior to inclusion of the project in the budget. If this
should occur, the Title I design estimate becomes synonymous with the
budget estimate.
TITLE I DESIGN SUMMARY. An overview and record document of preliminary
engineering and project management planning, reflecting completed Title
I design and usually prepared under architect-engineer services or by
the operating contractor. Title II design estimates are developed for
each project by the designer as part of the Title I design summary. The
estimates, since they are based on the definitive design, are the most
accurate and have the highest confidence level of any estimate.
TITLE II DESIGN. This continues the development of the project based on
approved preliminary design (Title I). Definitive design includes any
revisions required of the Title I effort; preparation of final working
drawings, specifications, bidding documents, cost estimates, and
coordination with all parties which might affect the project;
development of firm construction and procurement schedules; and
assistance in analyzing proposals or bids. For a detailed description
of the services provided during definitive design, see DEAR
936.605(c)(3) and (4) and DEAR 952.236.70.
TITLE III SERVICES. Those activities required to assure that the
project is constructed in accordance with the plans and specifications
(e.g., construction inspection), and that the quality of materials and
workmanship is consistent with the requirements of the project (e.g.,
materials testing). (See DEAR 936.605(c)(3) and (4) and DEAR 952.236.70
for additional details.)
Vertical line denotes change
DOE 4700.1 Chg 1 Attachment 3
6-2-92 Page 19
110. TOTAL ESTIMATED COSTS (TEC) AND TOTAL PROJECT COSTS (TPC). Definitions
for TEC and TPC are provided in DOE 5100.3, FIELD BUDGET PROCESS, and
5700.2C, COST ESTIMATING, ANALYSIS, AND STANDARDIZATION. The below
listed definitions, extracted from these documents form the basis for
development of standardized cost estimates.
On occasion, there may be projects which cannot comply with these
definitions and guidance. For these projects, variances must be
requested by the project and approved by the Office of Program/Project
Management prior to Key Decision No. 1 when establishing project
baselines and requesting line item funding.
a. TEC. TEC includes the following estimated costs:
Land, land rights, depletable resources, and improvements to land.
Engineering, design, and inspection (Titles I, II, and III).
Construction Management of main plant, balance of plant, other
facilities, other structures and significant alterations,
additions, and improvements to structures (excluding normal
maintenance).
Utilities - including water and sewage systems, heating
ventilation and air conditioning, power systems, communication
systems, and fire prevention systems.
Quality Assurance.
Pre-operational construction changes shown to be required during
integrated systems testing and hot start testing.
Safeguards and security systems.
project and construction management.
Direct and indirect construction costs.
Standard and special facilities.
All equipment, furniture, and systems contained in main, balance
of plant facilities and administrative areas to render the
facility useable.
Computer systems, if dedicated to the project.
Section 23
Contingency and economic escalation.
Decontamination and/or disposal cost of equipment and construction
rubble when the purpose of the project is to replace existing
facilities.
Vertical line denotes change
Attachment 3 DOE 4700.1 Chg 1
Page 20 6-2-92
b. TPC. TPC includes all research and development (R&D), operating,
plant and capital equipment costs, specifically associated with
project construction up to the point of routine operations, which
will include but not be limited to:
Total Estimated Costs.
Pre-Title I activities, such as:
- Conceptual Design Reports (CDR).
- Preliminary Safety Analysis Report, if initiated prior to KD-1.
- Preparation of Project Data Sheets, design criteria, National
Environmental Policy Act (NEPA) documentation, and formulations
of Quality Assurance Criteria.
R&D necessary for fabrication, testing, and rework of prototype
equipment.
R&D (scale-up or demonstration plants of high-risk technology)
required prior to start of construction.
One-time costs related to testing, startup, operator training, and
commissioning.
Initial inventories and spare parts.
Site suitability testing and evaluation.
Quality Assurance related to site suitability and testing.
Regulation compliance.
Grant to state and local governments.
Payments equal to taxes.
Systems studies and selected systems engineering services.
Institutional activities related to facility siting and external
interactions.
Decontamination and decommissioning costs.
Economic escalation.
Contingency (applicable to TPC).
Vertical line denotes change
DOE 4700.1 Chg 1 Attachment 3
6-2-92 Page 21 (and 22)
111.
112.
USER. The entity which ultimately will operate or otherwise use the
system being developed. When the project objective is to demonstrate to
the private sector the utility or feasibility of a given system for
commercial application, the identity of the ultimate user may not be
known. In such case, only the most likely type of user (utility,
constructor, energy supplier) may be identifiable.
VALIDATION. The process of evaluating project planning, development,
baselines and funding prior to inclusion of funds for a project or
system acquisition in the DOE budget. It requires a review of project
planning and conceptual development documentation, as well as discussion
with the program or field element and principle contributing contractors
to determine the source basis, procedures, and validity of proposed
requirements, scope, cost, schedule, funding, and so forth. Findings
and recommendations resulting from the validation process will be
provided for use in the annual budget formultion.
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
i
TABLE OF CONTENTS
CHAPTER I - DOE PROJECT MANAGEMENT SYSTEM
PART A - OVERVIEW OF THE PROJECT MANAGEMENT SYSTEM
1. Introduction
2. Categories of Work Effort
a. Operational Categories
Figure I-1 - Categories of DOE Projects
Figure I-2 - Categories of Work Effort and Research and
Development of Acquisition Phases
b. Statutory Categories
c. Research and Development Phases
PART B - PROGRAM/PROJECT RELATIONSHIPS
1. Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2. Program Policy . . . . . . . . . . . . . . . . . . . . . . . . . . .
3. Project Evolution. . . . . . . . . . . . . . . . . . . . . . . . . .
Figure I-3 - Program Hierarchy . . . . . . . . . . . . . . . . .
4. State-of-the-Art Assessments . . . . . . . . . . . . . . . . . . . .
Section 24
PART C - MANAGEMENT ROLES, RESPONSIBILITIES, AND AUTHORITY . . . . . . .
1.
2.
3.
4.
5.
6.
7.
a.
8.
Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Organization . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Role of the Acquisition Executive . . . . . . . . . . . . . . . . . .
Figure I-4 - Project Management System Relationships . . . . . .
Energy System Acquisition Advisory Board . . . . . . . . . . . . . .
Program Secretarial Officers . . . . . . . . . . . . . . . . . . . .
Heads of Field Organizations . . . . . . . . . . . . . . . . . . . .
Project Manager. . . . . . . . . . . . . . . . . . . . . . . . . . .
Specific Responsibilities . . . . . . . . . . . . . . . . . . . .
b. Project Execution. . . . . . . . . . . . . . . . . . . . . . . .
Departmental Support Organizations . . . . . . . . . . . . . . . . . .
a. Director of Procurement, Assistance and Program Management . . .
(1) The Associate Director for Program/Project Management and
Control
(2) Director of Procurement, Assistance and Program Management .
(3) The Chief Financial Officer . . . . . . . . . . . . . . . .
(4) General Counsel
(5) Assistant Secretary for Environment, Safety, and Health .
(6) Director of Organization, Resources and Facilities
Management . . . . . . . . . . . . . . . . . . . . . . . .
I-1
I-1
I-2
I-2
I-3
I-4
I-5
I-5
I-7
I-7
I-7
I-7
I-8
I-9
I-11
I-11
I-11
I-11
I-12
I-13
I-13
I-14
I-16
I-16
I-16
I-17
I-17
I-17
I-19
I-20
I-20
I-20
I-21
Vertical line denotes change
ii DOE 4700.1 Chg 1
6-2-92
9.
10.
a.
Support to the Project Manager . . . .
Organizational Options
b. Other Than Departmental Support . .
Key Government Functions . . . . .
Management Assignments . . . . . . . .
c.
I-21
I-21
I-21
I-22
I-22
I-22
I-22
a.
a.
Project Management Assignment . . . . . . . .
b. Establishment of Special Project Office . . .
PART D - MAJOR SYSTEM ACQUISITIONS AND MAJOR PROJECTS I-25
1.
2.
3.
4.
5.
Introduction . . . . . . , . . . . . . . . . . .
Key Decisions. . . . . . . . . . . . . . . . . .
I-25
I-26
Figure I-5 - Major System Acquisition and Major Project
Decisions . . . . . . . . . . . . . . . . I-27
I-29
I-30
c.
Designation of Major System Acquisitions and Major Projects
DOE Acquisition Process.. . . . . . . . . . . . . . . . .
Figure I-6 - Major System Acquisition--Phase Transition
Decision Points . . . . . . .
Project Planning for Major System Acquisitions or
I-30a
I-31
I-31
I-31
I-31
I-31
I-32
I-32
I-32
Major Projects
Management Information . . . . . . . . . .
b. Use of Government or Non-Profit Organizations
Affordability . . . . . . . . . .
d. Timeliness . . . . . . . . . . .
e. Competitive Concept Development .
f. Cost Estimates . . . . . . . . .
g. Cost Participation . . . . . . .
Figure I-7 - Key Decisions in the Acquisition
Construction or Development Projects
Process
I-34
PART E -OTHER PROJECTS . . . . . . . . . . . . . . . . . . I-35
1. Introduction . . . . . . . . . . . . . . . . . . . . .
2. Other Project Decisions . . . . . . . . . . . . . . . .
3. Other Project Management Process . . . . . . . . . . .
Attachment I-1 - Energy System Acquisition Advisory
Procedures. . . . . . . . . . . . . . . . . .
I-35
I-35
I-35
Board
I-37
I-47
I-59
Attachment I-2 - Guidelines for Preparation for ESAAB Meetings
Attachment I-3 - Major System Acquisition Procedures. .
CHAPTER II - STRATEGIC PLANNING, PROJECT PLANNING AND BUDGETING
PART A - PROJECT INITIATION AND PLANNING DOCUMENTATION . . . . II-1
Section 25
1. Introduction . . . . . . . . . . . . . . . . . . . . . . .
2. Strategic Planning . . . . . . . . . . . . . . . . . . . .
II-1
II-1
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
iii
PART B - WORK BREAKDOWN STRUCTURE . . . . . . . . . . . . . . . . . . . . . II-9
PART C - PROJECT BUDGET PROCESS . . . . . . . . . . . . . . . . . . . . II-15
PART D - COST ESTIMATING AND CONTINGENCY ESTIMATING
PART E - PROJECT ACQUISITION FOR MAJOR SYSTEM ACQUISITIONS AND MAJOR
Vertical line denotes change
iv DOE 4700.1 Chg 1
6-2-92
PART F - ENVIRONMENTAL PLANNING AND REVIEW . . . . . . . . . . . . . . II-31
PART G - CONSTRUCTION PLANNING . . . . . . . . . . . . . . . . . . . . . II-39
PART H - PROJECT TRANSITION . . . . . . . . . . . . . . . . . . . . . . II-43
CHAPTER III - PROJECT CONTROL
PART A - CHANGE CONTROL AT THE EXECUTIVE LEVEL
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
v
PART B - SYSTEMS ENGINEERING, TEST, AND EVALUATION . . . . . . . III-5
PART C - CONFIGURATION MANAGEMENT . . . . . . . . . . . . . . . . III-11
PART D - QUALITY ASSURANCE . . . . . . . . . . . . . . . . . . . . III-17
PART E - CONSTRUCTION MANAGEMENT . . . . . . . . . . . . . . . . . . . III-23
PART F - PROJECT CONTROL . . . . . . . . . . . . . . . . . . . . . . III-25
Vertical line denotes change
vi DOE 4700.1 Chg 1
6-2-92
PART G -PROJECT TERMINATION . . . . . . . . . . . . . . . . . . . . . . III-41
CHAPTER IV - PROJECT REVIEW, REPORTING, AN ASSESSMENT
PART A - PROJECT STATUS REVIEW . . . . . . . . . . . . . . . . . . . . . IV-1
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
vii
PART B - PROJECT REPORTING AND ASSESSMENT . . . . . . . . . . . . . . . . IV-3
Attachment IV-1 - Project Manager’s Progress Report
Instructions and Example . . . . . . . . . . . . . . . . . IV-11
Attachment IV-2 - Semiannual Status Report for Non-General Plant
Projects Below $5 Million in Total Estimated Cost,
Instructions and Example . . . . . . . . . . . . . . . . . . . IV-23
Attachment IV-3 - Project Activity Report, Instructions
and Example . . . . . . . . . . . . . . . . . . . . . .
Attachment IV-4 - Cost and Cost Plus Commitment Chart,
Instructions and Example . . . . . . . . . . . . . . . . . IV-29
Attachment IV-5 - Engineering, Management, and Construction
Manpower for Cost Type projects Report, Instructions and
Attachment IV-6 - Progress Photographs Instructions . . . . . . IV-35
Attachment IV-7 - Annual Report for General Plant Projects,
Instructions and Example.. . . . . . . . . . . . . . . . . . . . IV-37
Attachment IV-8 - Instructions for the Program Manager’s Summary
Report to the Acquisition Executive . . . . . . . . . . . . IV-39
Attachment IV-9 - Summary Project Performance Report to Senior
Management, Instructions and Example . . . . . . . . . . . . . . . IV-41
Attachment IV-10 - Example of a Quarterly Status
Report - Construction Projects . . . . . . . . . . . . . . . . . . IV-43
Vertical line denotes change
viii DOE 4700.1 Chg 1
6-2-92
CHAPTER V - PROCEDURES FOR CONSTRUCTION MANAGEMENT
PART A - PROCEDURES FOR MANAGING CONSTRUCTION EFFORTS
Vertical line denotes change
DOE 4700.1 Chg 1 ix (and x)
6-2-92
PART C -EXECUTION . . . . . . . . . . . . . . . . . . . . . . . . . . . .V-33
Attachment V-1 - Example of a Project Authorization . . . . . . . V-65
Attachment V-2 - Construction Management . . . . . . . . . . . . V-67
Attachment V-3 - Design Criteria Package Checklist . . . . . . . V-77
Attachment V-4 - Control Aid Descriptions . . . . . . . . . . . . V-83
Attachment V-5 - Planning Chronology for Fiscal Year 1986
Section 26
Construction Budget Projects . . . . . . . . . . . . . . . . V-85
Attachment V-6 - Short Form Data Sheet Contents . . . . . . . . . V-87
Attachment V-7 - Example of a Short Form Data Sheet . . . . . . . V-89
Attachment V-8 - Conceptual Design . . . . . . . . . . . . . . . V-91
Attachment V-9 - Conceptual Design Reports . . . . . . . . . . . V-95
Attachment V-10 - Conceptual Design Report Title Page Example . . V-97
Attachment V-11 - Contents of a Title I Design Summary . . . . . V-99
Attachment V-12 - Construction Completion Report Content . . . V-103
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
I-1
CHAPTER I
DOE PROJECT MANAGEMENT SYSTEM
PART A - OVERVIEW OF THE PROJECT MANAGEMENT SYSTEM
1. INTRODUCTION. The Department’s project management system is an approach
to management in which authority, responsibility, and accountability are
vested in a single individual to provide the detailed planning,
organizing, directing, and controlling of all activities leading to the
successful execution of the project.
a. The project manager’s planning activities include developing a plan
for management and control of the project. He/she is responsible for
ensuring that the baselines established in that plan are followed.
The project manager’s basic tools for controlling baseline activities
are monitoring and contractor reporting.
b. The contractor’s planning efforts must support those of the
Department. Part of the contractual agreement requires inclusion of
how the contractor will measure project performance so that the DOE
project management plan will reflect that data. These agreed-to plans
then become the project manager’s mechanisms for directing and
controlling the project.
c. Baseline establishment, baseline change control, and current,
complete, and accurate contractor reporting are the keys to proper
project management. The project manager is responsible for ensuring
that the project baselines are realistic, for understanding the need
for and value of adequate reporting to measure baseline performance,
and for establishing the proper control mechanism (Uniform Reporting
System and Cost and Schedule Control Systems Criteria) to measure
project performance. These requirements demand that the project
manager be fully cognizant of the concepts and procedural details of
the tools which are available for use.
d. DOE project management policy requires decentralization of projects
unless an exception is granted by the Acquisition Executive.
Decentralization in this context simply means assignment of project
management responsibility to field elements. Normally, for large
decentralized projects such as Major System Acquisitions (MSAs), Major
Projects (MPs) or major line items; scope, cost, and schedule
baselines are provided and controlled by Headquarters.
Vertical line denotes change
I-2 DOE 4700.1
3-6-87
e. The Department categorizes projects into three separate groups: MSAs,
MPs, and other projects. The definition of these categories are
detailed in Figure I-1. For project reporting purposes, other
projects are further subdivided into those costing $15-$50 million,
those $5-$15 million, those $1.2-$5 million, and those under $1.2
million (general plant projects). Chapter IV explains reporting
requirements for all project categories.
2. CATEGORIES OF WORK EFFORT. The projects covered by the project
management system include not only construction efforts, but also
activities which may be defined in terms of operational/statutorial
categories of work effort and the various phases of research and
development. Figure I-2 shows the relationship of the activities; further
details are provided below:
Section 27
a. Operational Categories. The full spectrum of outlay program efforts
can be divided into three categories which together constitute an
individual program.
(1)
(2)
Science and Technology Base. This normally accounts for 8 to 12
percent of the outlay program’s total estimated cost. This work
effort is referred to as tasks or work units, and is managed or
performed by personnel designated as principal investigators, as
opposed to the more formal procedures in projects and project
management. The work is generally characterized as level of
effort, and the documentation and management techniques are not
as formalized or rigorous as those required for project
management. An exception to this is the construction of large
experimental facilities, in such programs as high energy physics
and fusion, to be used in support of technology base activities.
Projects. Concept and demonstration development projects and
full scale development projects normally account for 20 to 40
percent of the outlay program’s total estimated cost. Projects
proceed through several discrete phases, each phase being
separated by a key decision point as shown in Figure I-2. Key
decisions are defined and explained in Chapter I, Part B,
paragraph 2. These project phases can be contained within only a
single statutorial phase of research and development, or they may
pertain to the project as it moves through the various phases of
research and development. It should be recognized that few
projects come from science and technology base and proceed neatly
through the research and development phases.
(3) Operations and Support. Normally in excess of 50 percent of the
outlay program’s total estimated cost can be attributed to
operations and support work effort, which encompasses all work in
an outlay program that is not in the science and technology base
or projects. It includes production, fabrication, and testing,
as well as program overhead, personnel, and studies, much of
which is generally characterized by level of effort.
Historically, some of this work moves into projects over time.
DOE 4700.1 Chg 1
6-2-92 I-3
Figure I-1. Categories of DOE Projects
Major System Acquisitions
A. National urgency, importance, size or complexity.
B. Dollar value-normally those systems or projects which have a total
project cost in excess of $100 million.
Major Projects
A. Total project cost of the project from $50 to $100 million.
B. Importance of project to program objectives.
C. Size and complexity of the project.
D. Degree of DOE control required.
E. Visibility of the project.
F. Potential severity of environmental impact.
G. Recommendations by Program Secretarial Officers.
Other Projects
A. Total project cost of the project below $50 million, including line
items, and GPP items.
B. Line items.
C. GPP items.
Vertical line denotes change
FIGURE 1-2
CATEGORIES OF WORK EFFORT AND RESEARCH AND
DEVELOPMENT OR ACQUISITION PHASES
DOE 4700.1 I-5
3-6-87
b. Statutory Categories. Within the Department, research, development, and
demonstration efforts consist of three statutory general categories:
(1)
(2)
(3)
Science and Technology Base includes basic research, applied
research, and technology or exploratory effort. Normally for budge-
tary reporting purposes, research and development facilities and
devices completed and capitalized are included in this base. The
goal of this effort is to conceive, scope, and explore technology
options to provide the foundation for the development of specific
projects.
Section 28
Concept and Demonstration Development includes advanced development
and engineering development. Its goal is the systematic application
of knowledge towards the identification of solutions to meet specific
energy requirements, including specific application prototypes and
processes. Normally, there is an intended commitment to large scale
projects.
Full Scale Development includes demonstration and production or
operation and is the systematic application of knowledge towards pro-
duction of useful materials, devices, systems or methods; this in-
cludes design, development and improvement of equipment and processes
to meet specific energy requirements. There is a major commitment of
significant resources at this point.
c. Research and Development Phases. The statutory categories above are
further subdivided into research and development phases. The first three
are level-of-effort type phases; the last four are called the acquisition
phases.
(1)
(2)
(3)
(4)
Basic Research. Systematic, fundamental study directed toward fuller
scientific knowledge or understanding of subjects bearing on national
energy needs.
Applied Research. Systematic study directed toward fuller scientific
knowledge for direct use in fulfilling specific energy requirements.
Technology or Exploratory Development. Systematic application of
knowledge from research towards proof of technology including devel-
opment of nonspecific application prototypes and processes.
Advanced Development. Effort that leads ultimately to a particular
application or product. Advanced development can cut across several
scientific disciplines and is intended to explore innovation in a
particular area of one or more energy technologies.
I-6 DOE 4700.1
3-6-87
(5) Engineering Development. Systematic use of the knowledge and
understanding gained from research and technoloy development to
achieve the detailed design, construction, and test for performance,
producibility, and reliability of energy system prototypes, pilot
plants, and research facilities. This category also includes the
preparation of appropriate National Environmental Policy Act documen-
tation.
(6) Demonstration. Verification of economic and environmental viability
through design and construction, test and evaluation of large energy
systems in operational circumstances. Demonstration projects are
intended to:
(a) Overcome “scale-up” problems;
(b) Contribute to the understanding of the economics of fabrication
and operation; and
(c) Resolve other questions such as public assistance and institu-
tional and environmental issues. Preparation of appropriate
National Environmental Policy Act documentation is included in
this phase.
(7) Production or Operations.
(a) Production. Producing the item in quantity, bulk, or other
parameters which meet specifically stated requirements.
(b) Operations. Bringing the system or project from prototype or
pilot plan operational testing status to full-scale operational
condition to meet stated objectives.
DOE 4700.1 I-7
3-6-87
PART B - PROGRAM/PROJECT RELATIONSHIPS
1. INTRODUCTION.
a. Program Requirements flow from Departmental missions and mission area
assignments made by the Secretary. The goals established by the program
requirements necessitate pursuit of state-of-the-art technology develop-
ment, various project executions, and operation of pilot and fully
integrated facilities.
Section 29
b. Responsibilities. The program manager is responsible for attaining
program goals within a mission area assignment and concentrates on assimi-
lation of all aspects of the program into a single entity. The project
manager is responsible for a single project within the program and con-
centrates on meeting project objectives within established baselines.
2. PROGRAM POLICY. Program policy establishes the base for project policy and
execution.
a. Each program Secretarial Officer is responsible for the planning,
programing, budgeting, and execution of programs under his or her
cognizance.
b. Headquarters and field responsibilities and authorities are set forth for
each program.
c. There is a clear hierarchical relationship between missions, programs,
and projects. This hierarchical relationship is graphically depicted in
Figure I-3.
d. Only programs and their constituent elements that fulfill a mission
need, and are in consonance with assigned mission areas, will be
conducted.
e. Continuing mission analysis and independent monitoring are conducted to
ensure that programs are planned, developed and, upon approval, executed
in accordance with assigned mission areas.
f. Significant program issues and near-term milestones of interest to senior
management are identified and their status periodically reviewed.
3. PROJECT EVOLUTION.
a. The Secretary requests proposed changes to current mission area assign-
ments from the program Secretarial Officers. These changes are based on
the results of continuing mission analysis.
I-8 DOE 4700.1
3-6-87
Planning Flow for Programs
DOE Project
Management System
Figure I-3
Program Hierarchy
DOE 4700.1
3-6-87
I-9 (and I-10)
b. A program summary is developed for each program which includes the mission
area assignment supported by the following data: (1) program objectives
and related issues; (2) the program strategy; (3) summary of program
logic; (4) near- and long-term milestones; (5) significant projects; and
(6) the program project structure. The Secretary approves the program
strategy and near-term milestones, and selects milestones and issues for
periodic review.
c. The approved projects and/or project elements of the program then become
specific budget items in the annual planning, programing, budgeting phase
of program management. The planning and programming activities entail the
translation of strategic Departmental policy objectives at a specific
point in time within constrained resources.
4. STATE-OF-THE-ART ASSESSMENTS.
a. The project management system assumes the technical risks associated with
research and technology development are investigated prior to the
establishment of a project, especially MSA’s or MP’s. This risk can vir-
tually be eliminated by requiring proven technology to be available prior
to project initiation. The impact of this requirement, however, may be
severe in terms of cost and schedule penalties as well as unrealistic for
meeting a mission need. In other words, there must often be a tradeoff
between project schedule and state-of-the-art technology. An assessment
has to be made of the impact of one or the other situations.
b. This state-of-the-art assessment is primarily the responsibility of the
program manager, who has better visibility into the technology related to
his program. The assessment should then become an integral part of the
risk assessment aspect of the justification for new start and be sum-
marized in the alternatives and capability section.
Section 30
c. Although the program manager has primary responsibility, the project
manager must also be alert to technology change. State-of-the-art
assessments may relate to any phase of the project, since various com-
ponents in a system may be in different stages of development throughout
the project’s life. In updating the project plan, the project manager
should describe the status of technology as it relates to the project.
Then, as the project matures, early warning of potential deficiencies in
technology readiness should be highlighted in the project manager’s status
reports.
DOE 4700.1 Chg 1
6-2-92
I-11
PART C. MANAGEMENT ROLES, RESPONSIBILITIES, AND AUTHORITY
1. INTRODUCTION. It is the intent of the Department to place authority and
responsibility at the appropriate management level commensurate with the
project effort. This approach allows decisions to be made and actions to
be taken at the appropriate levels within DOE line management. Below are
the detailed roles played by various management levels within the
Department as they relate to the project management system.
2. ORGANIZATION.
a. Headquarters program organizational elements will be responsible for
overall program policy, planning, program development (including
establishment of Broad priorities), budget preparation and defense
(with major support from field organizations), and broad program
direction. Field organizations will be responsible for implementing
these program activities and for providing major support to the
Headquarters programming and budgeting process.
b. Implementation of the Project Management System (PFK) involves both a
“line” chain of authority and necessary participation of various
“staff” elements. The line organization chain begins with the
Secretary and progresses through the Program Secretarial Officers,
Headquarters program organizations, and finally, to the project
manager, the single individual who has full responsibility for
detailed planning and execution of all project activities. Staff
participation and coordination begin very early in a project’s life
cycle and carry through to project completion. (A chart showing
project management system relationships follows as Figure I-4).
c. Project Line Management. The project line management for MSAs, MPs,
and other projects, as depicted in Figure I-4, is the Office of the
Secretary/Acquisition Executive, the Program Secretarial Officer, the
Program Office, the Head of the Field Element, and the Project
Manager.
3. ROLE OF THE ACQUISITION EXECUTIVE
a. The Secretary has delegated the principal responsibility for project
management activities to the Acquisition Executive. This includes
establishing Department project management policies, approving the
PMS, serving as the chairman of the Energy System Acquisition Advisory
Board (ESAAB) and Level Baseline Change Control Board (BCCB) for the
Department’s MSAs and selected MPs and approving establishment of
special project offices.
b. Key decisions on MSAs and certain decisions on selected MPs are
normally reserved for the Acquisition Executive. In some cases, the
Secretary may elect to act as the Acquisition Executive on critical
projects. These include decisions to enter the acquisition phase or
to make transitions between phases (key decisions) and any decisions
Vertical line denotes change
I-12
DOE
4700.1
3-6-87
DOE 4700.1 Chg 1
6-2-92
which will directly result in commitment of major portions
I-13
Section 31
(e.g.,procurement of large long-lead items) of-the- project funds.
Additionally, the Acquisition Executive
a case-by-case basis.
c. Other decisions on MSAs and similar key
MPs are typically made by the cognizant
may reserve other decisions on
and significant decisions on
Program Secretarial Officers.
4. ENERGY SYSTEM ACQISITION ADVISORY BOARD.
a. The ESAAB supports the Acquisition Executive by providing advice,
assistance, and recommendations at key decision points for each MSA
and designated MPs. Attachment I-1 provides complete ESAAB membership
and procedures. The ESAAB provides a single forum for the discussion
of issues and alternatives and is designed to assure coordinated,
objective senior level management advice to the Acquisition Executive.
Attachment I-2 details ESAAB review meeting highlights.
b. The Acquisition Executive is responsible for convening formal
meetings, as required to facilitate the decision process. Board
members and appropriate advisors will attend all meetings. Other
advisors are not required to attend unless asked to participate by the
Acquisition Executive. In addition to prescribed meetings, any board
member may request a meeting to consider significant issues at any
point in the acquisition process for any MSA.
5. PROGRAM SECRETARIAL OFFICERS.
a. Each Program Secretarial Officer has full responsibility for the
management planning and execution of his/her program activities
including projects, subject to the national energy plan; approved
Departmental policies and program strategies; mission area
assignments; enacted budget legislation; approved resource
allocations; and the Departmental PMS. For MPs, the Program
Secretarial Officer is responsible for each approval or key decision
not specifically reserved for the Acquisition Executive.
Additionally, he/she is responsible for providing current information
on program management decisions, the progress of work, status or
resource utilization, major problems encountered, and planned
corrective actions, to the Acquisition Executive and other
Departmental elements having responsibility for activities which must
interface with project activities.
b. Normally, the type and level of detail for the information provided
will be the minimum required for the recipient office to fulfill its
responsibilities in those areas which interface with project
activities. In general, the information concerning projects that is
provided to the Acquisition Executive will be that associated with
MSAs and MPs although special reviews and reports may be requested for
other projects on a case-by-case basis.
Vertical line denotes change
I-14
c.
d.
e.
f.
DOE 4700.1 Chg 1
6-2-92
The responsibility and authority for decision-making shall be
delegated to the appropriate organizational level. To accomplish
this, only those approvals and key decisions on MPs, associated with
entering or making the transition between acquisition phases, those
directly resulting in large commitment of funds (e.g., procurement of
large long lead items) or those of unusual national or programmatic
importance or sensitivity are required at the Program Secretarial
Officer level.
Assistant Secretary for Defense Programs (DP-1) has special
responsibilities for non-weapon work assigned to the weapon complex.
In coordination with appropriate DOE sponsors, he/she reviews the
nature, scope, and future requirements of non-defense-related work.
Additionally, he/she concurs or nonconcurs in the assignment of non-
weapon work or lead missions to the weapon complex facilities.
Section 32
Program Organizations.
(1) Management responsibility for specific programs is delegated by
the cognizant Program Secretarial Officer to one of his/her DOE
Headquarters program offices. This includes overall
responsibility for any projects included in the program
activities. The program organizations are responsible for
assuring that overall requirements are fulfilled in the areas of
environment, technical performance, scope, safety, quality
assurance, cost, schedule, and operational environmental safety
and health. They also continually evaluate and balance project
needs against other programmatic needs and constraints.
(2) In general, the heads of the program offices are responsible for
all the Headquarters approvals and key decisions which are not
specifically reserved for the Program Secretarial Officer or the
Acquisition Executive.
Program Organization Staff. The program organization staff will
assist the director of the Headquarters program organization in the
execution of assigned responsibilities. Precise delineation between
the line management and the staff role is difficult since the staff
functions are highly dependent upon overall organizational
arrangements.
6. HEADS OF FIELD ORGANIZATIONS.
a. Certain planning and all executing responsibility for MSAs, MPs, and
other projects shall be assigned to field offices unless an exception
is obtained from the Acquisition Executive by the Program Secretarial
Officer. The field element shall be involved in the planning of all
assigned projects and shall develop much of the project documentation,
which includes the “Justification of Mission Need” and the Project
Plan, including the project charter. The Head of the Field Element
shall establish an appropriate project management organization and
will delegate appropriate authority to the project manager for
management and direction of the project(s).
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
I-15
b. Specific Responsibilities. Heads of Field Elements will:
(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
Participate and concur in the determination regarding assignment
of project(s) to the field organizations;
Develop project plans, including charters, and other project
documentation for the cognizant program element;
Establish a project management organization and delegate
appropriate authority to the project manager for the management
and direction of the project(s) within the delegated authority;
Assure the project manager is provided the necessary support to
accomplish the project within the project charter guidelines,
particularly in the area of personnel, in both administrative and
technical areas;
Review and approve project management plans;
On MSAs, select the project manager with the concurrence of the
cognizant Program Secretarial Officer or designated
representative; on MPs, select the project manager or designate
management responsibility, after consultation with the cognizant
Program Secretarial Officer or designated representative; and on
all other projects designate management responsibility;
Assure satisfactory management of the project in accordance with
the project plan, including the project charter and project
management plan;
Provide independent assessment on regular reports on project
status, progress, problems, and variances provided to
Headquarters management by the project manager;
Coordinate and integrate all necessary in-house and outside
administrative and technical support to meet project objectives
and requirements;
Section 33
Develop project managers and project management capability;
Within the authority delegated, conduct such contractor
selections and subcontractor approvals as are required.
Within authority delegated, execute and administer contracts;
Assure that the minimum technical reporting requirements of the
Department are met and that all scientific, technical, and
engineering publications are deposited in a timely fashion with
the Office of Technical and Scientific Information;
Assist, when needed, the contractors or industrial partners in—
efforts to formalize experimental research and development
programs to support the assigned project(s);
Vertical line denotes change
I-16 DOE 4700.1 Chg 1
6-2-92
(15) Assure that adequate policy and procedures consistent with
Departmental policy are established to assist the project manager
in accomplishing the planning and execution of the construction
portion of the project;
(16) Prepare National Environmental Policy Act documentation and
assure the environmental protection, safety, and health
protection aspects of facility operations;
(17) Accept the completed contractor efforts; and
(18) Assure effective implementation of required quality assurance
activities.
7. PROJECT MANAGER.
a. Specific Responsibilities. The project manager will be the point of
contact for the information flow to Headquarters. Day-to-day
activities within the scope and charter thresholds and milestones will
normally flow between the project manager and the program manager.
The project manager shall be dedicated full time to the MSAs; however,
on other projects the same project manager may have authority and
responsibility for more than one project. For all projects, the OMB
Circular A-109 requirement to minimize layering above the project
manager must be satisfied.
b. Project Execution. The project manager has direct primary
responsibility and accountability for execution of the project in
accordance with the approved project plan, including the project
charter and the project management plan. The project manager is
responsible for actions indicated below:
(1) Technical Support. The support may be provided, as appropriate,
by technology centers, laboratories, or contractors. Technical
support services generally will be procured directly by the
project manager, but may alternately be provided by contract from
the program manager.
(2) Environment, Safety, and Health. The project manager is
responsible for assuring that all project activities are carried
out in compliance with Federal, State, and local regulations,
laws, and standards for protection of the environment and the
safety and health of employees and the public. The project
manager may procure support services as necessary to achieve such
compliance. In preparing National Environmental Policy Act
documentation, the project manager shall obtain guidance from the
appropriate field organization unit responsible for environment,
safety, and health, and from the Assistant Secretary for
Environment, Safety, and Health.
(3) Reporting. The reporting will be carried out in accordance with
the project management plan and this Order.
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
I-17
(4) Quality Assurance. Procedures in the management of the project
shall be established.
(5) Administrative Matters. The Head of the Field Element will
provide necessary support to the project manager to fulfill
administrative responsibilities associated with the project.
Section 34
(6) Procurement. The project manager shall initiate all procurement
actions necessary for execution of the project. The Head of the
Field Element will provide necessary support to the project
manager to fulfill these procurement responsibilities.
(7) Construction. The project manager shall oversee design review,
construction review, and construction management activities
related to the project.
(8) Financial. Management of project finances including contingency.
Financial management support will be provided by the Head of the
Field Element.
(9) Test Plan and Program. Preparation and execution of a complete
test plan to assure full technical performance capabilities of
the project. The Head of the Field Element will provide
necessary support to the project manager to fulfill these test
plan and program responsibilities.
(10) Configuration Management. Configuration management should be
included for each project that establishes and documents the
configuration baseline; institutes a configuration control system
to ensure the review, approval, and documentation of changes; and
institutes a program of configuration audits to assure compliance
with the form and intent of the configuration control system.
8. DEPARTMENTAL SUPPORT ORGANIZATIONS.
a. Director of Procurement, Assistance and Program Management (PR-1)
is responsible for procurement, cost estimates, and the
development of management and business related policy.
Specifically, responsibilities with respect to the project
management system are carried out by the following:
(1) The Associate Director for Program/Projec t Management and Control
(PR-20), through the Office of Program/Project Management has the
primary responsibility for Department-wide overview of project
activities for the Acquisition Executive. In this role, the
Office of Program/Project Management and Control shall develop,
implement, and maintain Department-wide program/project
management policies and systems. Specific responsibilities of
PR-20 include:
(a) Project Management System (PMS).
1 Develops and maintains the PMS
Vertical line denotes change
I-18 DOE 4700.1 Chg 1
6-2-92
2 Establishes policies and procedures for DOE-wide program
and project management and provides oversight, guidance
and evaluation of this area of responsibility.
3 Establishes requirements for and overview of
configuration management including the Baseline
Change Control Process at the Executive level.
4 Develops, implements, and maintains the Uniform Reporting
System and Cost and Schedule Control Systems Criteria.
5 Establishes requirements for, and overviews, mission
analysis as it relates to the acquisition process.
6 Provides support to and serves as the Energy System
Acquisition Advisory Board and the Level O Baseline
Change Control Board (BCCB) Secretariat.
(b) Project Documentation.
1
2
3
4
5
(c)
Reviews and concurs on project documentation for MSAs and
selected MPs.
Provides input for preparation of project plans as
requested, and reviews final versions and provides
recommendations.
Reviews and recommends approval of project baselines to
the Acquisition Executive.
Provides support to both the ESAAB and Program BCCBs,
including training and consultation for the Program and
Project BCCBs as required.
Ensures programs keep project documentation, reporting
and information current.
Project Execution
1 Performs independent project assessment at each decision
point and presents findings/recommendations to the
Acquisition Executive.
Section 35
2 Completes staff work and coordination to bring the
decision to the Acquisition Executive for approval.
3 Provides evaluation and recommendations on baseline
changes to the Executive Level Change Control Boards.
4 Acts as focal point for development and dissemination of
cost estimating data bases and methodologies for the
Department.
Vertical line denotes change
DOE 47O0.1 Chg 1 I-196-2-92
1
2
3
4
(2)
5 Conducts independent cost estimates prior to Key Decision
1, at the completion of Title I and II designs and at
critical phases of the project, as deemed necessary.
6 Conducts independent cost estimates, as appropriate, of
change control actions for review and approval by the
Acquisition Executive (Level O BCCB).
(d) Analysis and Evaluation
Tracks execution against project baselines and provides
independent assessment of project performance against
approved baselines. Provides coordinated recommendations
to the Acquisition Executive.
Provides coordinated quarterly summary project
performance reports covering project execution and issues
to senior management.
Provides recommendations to Program Secretarial Officers
and Acquisition Executive for periodic project reviews.
Conducts program/project validations, in conjunction with
the program organizations, and in coordination with the
Chief Financial Officer and the Office of Policy,
Planning and Analysis in support of the annual Internal
Review Budget.
Director of Procurement, Assistance and Program Management (PR-1)
performs the following duties:
(a) Policy Development. Provides expertise in procurement,
financial assistance, and business management to support
development of Departmental project management policies.
(b) Project Development. Assists program offices in development
and subsequent implementation of procurement matters on
projects. These procurement and assistance services are
required for MSAs and designated MPs. Assists program and
project offices in development of the procurement strategy
through provision of direct advice and counsel, as well as
through business strategy groups, and concurs in the project
plan and related documents to assure satisfactory business
arrangements.
(c) Project Execution. Responsible for supporting procurement
aspects of project execution. Field and Headquarters
procurement organizations provide assistance to project
organization in the planning of individual procurement
actions, and carrying out necessary actions to solicit,
award, and administer procurements.
Vertical line denotes change
I-20 DOE 4700.1 Chg 1
6-2-92
(d) Other Responsibilities. The Director has specific
responsibilities in two other areas that impact project
management:
1 Personal property management; and
2 Materials allocation program.
(3) The Chief Financial Officer is responsible for budget formulation
and execution activities including:
(a) Assurance that financial controls are established and
maintained in accordance with legislative authority;
(b) Development and publication of budgeting, accounting, and
other policies necessary for implementation of this Order;
(c) Preparation of financial reports as may be requested or
required by Congress, the Office of Management and Budget,
or the General Accounting Office;
(d) Coordination on financial aspects of reports or other
documents required by this Order; and
Section 36
(e) Determination in conjunction with the component program
support offices whether congressional notification is needed
prior to commitment of funds to any action which will result
in, or as a result of, a change in scope, Total Estimated
Cost (TEC), major thrust, or other significant departure
from the previous congressional budget presentation.
(4) General Counsel (GC-1) provides legal counsel to assure that
activities are planned and conducted in accordance with statutory
and regulatory requirements. Counsel organizations in field
organizations perform the specific legal functions necessary for
project execution.
(5) Assistant Secretary for Environment, Safety, and Health (EH-1)
has three basic roles in the PMS.
(a)
(b)
Coordination of Energy Policy. Has primary staff
responsibility. Draft policy, however, is coordinated with
Program Secretarial Officers before issuance: This role
focuses on the front end of the acquisition process, most
specifically, on the Department-wide budget and program
planning process.
Identification, Coordination, and Integration of Major
Issues Analyses and Decisions. These studies are performed
on selected policy and program issues which require the
Secretary’s priority attention for the formulation of budget
and legislative programs.
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
I-21
1
2
3
(c) Independent Review. Independent review of the conformance
to laws, regulations, and DOE Orders related to environment,
safety, and health.
These responsibilities are accomplished through the
following procedures:
The review and approval of environmental documentation,
by assuring compliance with the National Environmental
Policy Act;
The independent overview of operational environment,
safety, and health (occupational and public), and quality
assurance requirements/activities including the safety
analysis and review systems; and
Independent management appraisals of DOE programs and
9.
projects subject to this project management system in the
areas of environmental safety and health protection and
quality assurance per DOE 5700.6C and DOE 5480.1B.
(6) Director of Organization, Resources and Facilities Management
(AD-1O) is responsible for overall facilities management, cost of
ownership issues, specifically in the areas of general design
criteria, In-House Energy Management, maintenance management,
real estate, site development planning, utilities management, and
value engineering.
SUPPORT TO THE PROJECT MANAGER. The project manager and/or the Head of
the Field Element will develop a proposed project organization. The
project organization will be summarized in the project plan and detailed
in the project management plan.
a. Organizational Options. Because of the diversity of projects and
field organizations, there is not a standard project organization.
The project organization can range from a relatively large dedicated
project office for large, complex projects to a single project manager
(having responsibility and authority for more than one project)
receiving matrix support for all activities. The typical project
organization consists of a small, dedicated project office (or
designated individual) with general matrix support provided by the
field organization. This project office reports to the Head of the
Field Organization, generally through an assistant manager.
Section 37
b. Other Than Departmental Support. In addition to DOE personnel,
support from other Federal agencies and/or contractors may be utilized
to extend and strengthen the capabilities of the Departmental managing
organization. Support from other Government agencies (such as the U.S.
Army Corps of Engineers) is obtained through use of interagency
agreements. Contractor support may come from operating contractors or
specialty-type contractors.
Vertical line denotes change
I-22 DOE 4700.1 Chg 1
6-2-92
c. Key Government Functions. Provisions must be made for Government
performance of those responsibilities that cannot be delegated to
contractors. These responsibilities include:
(1) Determination of project and contract scope;
(2) Establishment of the project management and contracting approach;
(3) Selection of prime contractors as well as the award and
administration of prime contracts for work;
(4) Determination of satisfactory contractor performance and
acceptance of completed work;
(5) Assurance of project execution within agreed upon objectives;
(6) Direction and supervision of Government employees;
(7) Distribution and accountability of Government funds;
(8) Assurance of project cost, schedule, and technical performance;
(9) Development, justification, and approval of input into the
President’s budget; and
(10) Management of project contingency funds.
10. MANAGEMENT ASSIGNMENTS.
a. Project Management Assigmment. Responsibility for project management
will generally be assigned to the field element with the greatest
expertise in the program area under which the project falls. If no
single field organization has major exclusive expertise in the program
or project subject area, the program manager will identify an
appropriate field organization for project management on the basis of
staff experience and availability. The cognizant program manager and
the Head of the Field Element will jointly decide the project
management assignment and will issue a charter to the cognizant
Program Secretarial Officer as part of the project plan.
b. Establishment of Special Project Office. Under extraordinary
conditions, a special project office may be established separate from
the existing field structure. A recommendation for this office shall
originate with the cognizant program manager, program director, or
Program Secretarial Officer. The recommendation will be coordinated
with the Office of Procurement Assistance and Program Management and
the Office of Organization, Resources and Facilities Management, and
will be submitted to the Acquisition Executive for approval.
(1) A special project office imposes the heaviest burden on the
Department in terms of Government personnel, and exceptional
justification is required to support a recommendation to
establish one. The specific level of support by a field
organization and its reporting relationship will be established
Vertical line denotes change
DOE 4700.1 Chg 1 I-23 and (I-24)
6-2-92
on a case-by-case basis in consultation with the field
organization involved.
(2) The office shall report to the program office of the cognizant
Program Secretarial Officer or as directed by the Secretary.
Vertical line denotes change
DOE 4700.1
3-6-87
I-25
PART D - MAJOR SYSTEM ACQUISITIONS AND MAJOR PROJECTS
1. INTRODUCTION.
a. OMB has issued an Executive Department policy statement entitled
“Major System Acquisitions” (OMB Circular A-109). This circular
establishes policy to be followed by executive branch agencies in the
acquisition of major systems and provides basic policy guidance for
the PMS. DOE MSAs and MPs shall conform to these requirements.
Section 38
b. OMB and DOE policy requirements include:
(1) Top level management attention to the determination of agency
mission needs and goals;
(2) An integrated systematic approach for establishing mission needs,
budgeting, contracting, and managing programs;
(3) Early direction of research and development efforts to satisfy
mission needs and goals;
(4) Improved opportunities for innovative private sector
contributions to national needs;
(5) Avoidance of premature commitments to full-scale development and
production/operations; and
(6) Early communication with Congress in the acquisition process by
relating MSAs to agency mission needs and goals.
(7) Early identification of projects requiring major siting
decisions.
c. The nature of DOE projects requires that consistent policy be
established for their management and that all participants understand
the objectives of the project. It is important that all Departmental
participants coordinate their efforts in order to:
(1) Assure proper coordination by all appropriate line and staff
elements beginning with program or project inception;
(2) Relate program or project objectives to national planning
documents, mission area assignments, strategy papers, and
legislation, as appropriate;
(3) Assist in determining priorities among programs and projects and,
in turn, relate these to various levels of resource availability;
(4) Avoid commitment of major resources prior to adequate project
definition; and
I-26 DOE 4700.1 Chg 1
6-2-92
(5) Provide program and project managers with a clear view of related
program and project objectives and plans.
2. KEY DECISIONS.
a.
b.
c.
d.
e.
OMB Circular A-109 also specifies certain key decisions and outlines
the logical sequence of activities in the MSA process. The key
decisions and sequencing provide DOE w
how to meet the requirements of the po
Figure I-5 outlines the key decisions.
Key decisions are approved by the Acqu
and selected MPs. Program Secretarial
on major MPs not reserved for the Acqu
i
l
th flexibility in determining
icy and staff key decisions.
sition Executive on all MSAs
Officers make the key decisions
sition Executive. Key
i
i
decisions on other projects, when required, shall be made by the
Program Secretarial Officer or formally delegated.
Project baselines are related to the key decisions. Key Decision O,
Approval of Mission Need, allows the Conceptual Design Report (CDR) to
be developed which provides the data required to develop initial
technical, cost, and schedule baselines. Initial technical, cost, and
schedule baselines are established at Key Decision 1 based on the CDR
and other support documentation. The initial baselines will be
refined and updated as the project proceeds through preliminary design
(Title I), final/detailed design (Title II), construction/full scale
development, testing, and successful start of operations. For
projects funded from operating funds, appropriate equivalent decisions
points reflecting significant expenditure of funds will be identified
by Secretarial Officers and recommended to the Acquisition Executive.
The baselines will be managed using the change control system at the
executive level as defined in Chapter III and project change control
systems for those changes not requiring Headquarters approval.
Updated baselines reflecting incorporation of approved Baseline Change
Requests will be presented at each key decision to the ESAAB or
Program Secretarial Officer, as appropriate.
Section 39
An Independent Cost Estimate (ICE) will be conducted prior to Key
Decision 1 based on the proposed project baselines established from
the CDR and supporting CDR data. The original baselines ICE will be
refined at the completion of preliminary design (Title I) and
final/detailed design (Title II) to provide independent project cost
assessments prior to Key Decision 2 and Key Decision 3, respectively.
The project manager will notify the Office of Program/Project
Management well in advance of the need to update an ICE.
Key decisions may be expanded to include additional Acquisition
Executive milestones or decision points, as appropriate, between the
standard key decisions. These expanded decision points will ensure
the proper Headquarters visibility and ESAAB action prior to all major
commitments of resources for a project. Key decisions and expanded
decision points shall be integrated into the project summary schedule.
Vertical line denotes change
DOE 4700.1 Chg I-27
KEY DECISION O - Approval of Mission Need
Prerequisite for requesting conceptual design funding in the
internal review budget cycle.
Approval must occur prior to the planning stages of the
annual internal review budget cycle and submission of
initial funding requests to the Office of Management and
Budget and Congress.
Documentation Requirement: Approving Mission Need.
Prerequisite for release of appropriated funding by the CFO.
KEY DECISION 1 - Approval of New Start
Prerequisite for requesting project line item finding in the
internal review budget cycle.
Approve Project Plan including initial project baselines.
Initial technical, cost and schedule baselines for the
project will be based on the CDR and its support
documentation.
Implement a change control system delineating specific
responsibilities, authority and accountability at the
appropriate management levels for changes affecting the
project baselines.
Other input to the decision process includes completion of
the budget validation, and independent cost estimate, and
the project data sheet.
Prerequisite for release of appropriated funding by the CFO.
KEY DECISION 2 - Approval to Commence Title II, or Final/ Detailed
Design
Scheduled prior to start of Title II, or Final/Detailed
Design.
Input to decision process includes update to the project
baselines reflecting completion of preliminary design (Title
I), and an independent cost estimate.
Figure I-5
Major System Acquisition and Major Project Key Decisions
Vertical line denotes change
I-28 DOE 4700.1 Chg 1
6-2-92
● Current project plan reflecting approved baseline changes,
as appropriate.
● Approval to begin long-lead procurement, if applicable.
● Prerequisite for release of appropriated funding by the CFO.
KEY DECISION 3 - Approval to Commence Construction or Enter Full-
Scale Development.
● Scheduled prior to start of construction or full-scale
development.
● Input to the decision process includes the update of project
baselines reflecting completion of final/detailed design
(Title II) and an independent cost estimate.
● Current project plan reflecting approved baseline changes,
as appropriate.
● Other input to the decision process includes evidence of
readiness to process, appropriateness of timing and a firm
baseline.
● Prerequisite for release of appropriated funding by the CFO.
KEY DECISION 4 - Approval to Commence Operation/Production
Section 40
● Scheduled prior to the transition from acquisition to
operation/production; transition is not formally made until
demonstrated capability to meet technical performance goals
specified in the baseline.
● Prerequisite for released of appropriated funding by the
CFO.
Figure I-5 (continued)
Major System Acquisition and Major Project Key Decisions
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
I-29
3.
f. Each key decision point (including expanded decision points) will
require ESAAB approval prior to the releases of appropriated funds by
the Chief Financial Officer to proceed with the next phase of the
project.
g. In the event that there are no key decisions or expanded decision
points in a given year for the project, an Energy System Acquisition
Review (ESAR) will be scheduled to advise the Acquisition Executive on
current project status. Attendance at the ESAR will be the same as an
ESAAB meeting with the Acquisition Executive serving as the chairman.
The ESAR will be conducted similar to an ESAAB meeting in that the
Acquisition Executive will review project performance (cost, schedule,
and technical) against current baselines. The Acquisition Executive
may delegate the responsibility for the ESAR to the cognizant Program
Secretarial Officer.
DESIGNATION OF MAJOR SYSTEM ACQUISITIONS AND MAJOR PROJECTS. Projects
that fulfill the prescribed MSA or MP criteria will be so designated by
the Acquisition Executive using the following procedures:
a. The Office of Program/Project Management and Control, which maintains
DOE 4240.1, will develop a list of MSAs and MPs. The list is
submitted to the program organizations for review and comment.
b. Comments and unresolved designations which cannot be resolved at the
program management levels will be forwarded to the Acquisition
Executive for resolution. Appropriate notification of changes or
additional designations is made to OMB and its Office of Federal
Procurement Policy. Subsequently, a change to DOE 4240.1K,
DESIGNATION OF MAJOR SYSTEM ACQUISITION AND MAJOR PROJECTS (or its
successor) is issued.
c. If the approval of any change by a Level O, 1, or 2 Baseline Change
Control Board (BCCB) action caused the Total Project Cost for a
project to change from either the threshold for a MSA ($100 million),
or for a MP ($50 million), the chairperson of the Level 1 BCCB
approving the change shall be required to immediately notify the
Director, Office of Procurement, Assistance and Program Management
(PR-1) of the situation. Specifically, the Level 1 BCCB chairperson
is required to provide such notification in writing within 5 working
days of the approval of the project action which caused the change.
The notification letter shall provide complete explanation of the new
technical, cost, and schedule baselines and status of the project
relative to key decision points to enable PR-1 to make determination
whether an Energy System Acquisition Advisory Board/Energy System
Acquisition Review should be convened, and whether DOE 4240.1 should
be revised to include the subject project.
Vertical line denotes change
I-30
4.
DOE 4700.1 Chg 1
6-2-92
DOE ACQUISITION PROCESS.
a.
b.
Each MSA or MP is directed through the acquisition process by the
project manager who has a charter which provides sufficient authority
and resources to accomplish the stated project objectives and goals.
Layers of authority between the project manager and the responsible
Program Secretarial Officers are kept to a minimum. Figures I-5 and
I-6 denote the process and phasing of MSAs. Figure I-7 provides the
key events in the acquisition process. See Attachment I-3 for MSA
procedures.
Section 41
In order to effectively carry out DOE’s missions, the acquisition
process requires that DOE management:
(1) Express needs and program objectives in DOE mission terms to
encourage innovation and competition in creating, exploring, and
developing alternative energy system options and design concepts.
(2) Conduct initial activities in the system acquisition process to
allow competitive exploration. of alternative energy system
options in response to mission needs.
(3) Establish clear lines of authority, responsibility, and
accountability for management of MSAs.
(4) Maintain a capability to:
(a) Review, monitor and evaluate total project costs, schedule,
and performance during the acquisition process and provide
assessments for consideration at key decision points or when
significant baseline variances occur.
(b) Estimate life cycle costs during system design, concept
evaluation and selection, full-scale development, facility
conversion, and production to ensure appropriate tradeoffs
among investment costs, operating costs, schedules, and
performance.
(c) Use independent cost estimates of the cost of the project
for the applicable phase of the acquisition process, total
project cost, life cycle cost for comparison purposes.
(5) Report on the accomplishment and status of the acquisition
process. Of particular importance is reporting potential cost,
schedule, or performance threshold breaches before corrective
actions are foreclosed.
Vertical line denotes change
Major System Acquisition--Phase Transition Decision Points
Figure I-6
DOE 4700.1 Chg 1
6-2-92 I-31
PROJECT PLANNING FOR MAJOR SYSTEM ACQUISITIONS OR MAJOR PROJECTS. Three
documents are required during the project approval and execution
processes: the Justification of Mission Need, the Project Plan, and the
project management plan. During the development of these documents,
particular attention must be paid to the following, not necessarily
exclusive, concepts:
5.
a.
b.
Management Information. Management information should be limited in
all areas of activity to information essential for effective control.
Normally, the information required by management for decision-making
is obtained from the same data bases used by the contractor. A
realistic work breakdown structure is developed for each project as a
framework for planning and assignment of responsibilities, contracting
and reporting progress.
Use of Government or Non-Profit Organizations. Government
laboratories, federally funded research and development centers,
educational institutions, and other non-profit organizations that
submit alternative major system design concepts for consideration
shall not participate in the evaluation process on those systems.
Care must be taken not to place DOE management and operating
contractors, Government laboratories, and federally funded research
and development centers in competition with private industry, and
further, to assure that inappropriate assignments of work are not made
to such DOE management and operating contractors, Government
laboratories, and federally funded research and development centers
when such work is more appropriate and better suited for performance
by the private sector. If further exploration of an alternative
system design concept is deemed appropriate, that concept may be made
available to industry to propose on the continued development stages.
(1) Departmental operations offices, energy technology centers, and
laboratories may be assigned development tasks to complement a
major system development.
Section 42
(2) DOE energy technology centers and laboratories may be used as
technical arms of the project management office, especially in
matrix management organizations. Typical assignments may include
actions such as studies, analyses, technology developments, risk
and cost reduction efforts, and development test and evaluation.
Affordability. The Program Secretarial Officer will initially
describe the magnitude of resource commitment required to acquire a
system in the Justification of Mission Need and, subsequently, in the
Project Plan. At Key Decisions 1 and 2, affordability considerations
will be used as a factor in determining the selection of alternative
concepts. At Key Decisions 3 and 4, favorable decisions may not be
made unless the system’s project acquisition and operating costs are
available.
Timeliness. Potential savings in acquisition time should be balanced
c.
d.
against cost and technical risks or national urgency. When technical
and cost risks are low, or when the urgency to develop an alternative
energy system exceeds high technical and costs risks, the cognizant
Vertical line denotes change
I-32
e.
f.
g.
DOE 4700.1 Chg 1
6-2-92
Program Secretarial Officer should recommend, with caution, minimizing
acquisition cycle time. This may be accomplished by omitting a phase
of the acquisition process or by overlapping or combining activities
within a phase.
Competitive Concept Development. Alternative solutions to the mission
need shall be obtained competitively unless the Acquisition Executive
has approved pursuing a single concept. Even when pursuing a single
concept, competition shall be employed in development of the concept.
The widest range of acquisition alternatives to satisfy the mission
need shall be considered. At a minimum, solicitations shall outline
the need in mission terms; identify schedule objectives and
constraints; and present project system cost objectives.
Cost Estimates. The validity of conclusions reached at each decision
point depends upon the quality and consistency of cost, schedule and
technical estimates presented in proposed changes to the updated
project plan. Broad intervals of uncertainty and of risk must be
expected early in the acquisition process, with smaller intervals
developed as the project matures and uncertainty and risk decrease.
(See Chapter IV. )
Cost Participation. Cost participation is a generic term denoting any
situation in which the Government does not fully reimburse the
performer for all allowable costs necessary to accomplish the
project. The term encompasses cost sharing, cost matching, cost
limitation, participation in kind, and similar concepts.
(1) In research, development, and demonstration projects for which
there is a reasonable expectation that the performer will receive
present or future economic benefit as a result of performance, it
is Departmental policy to obtain cost participation.
(2)
(3)
Cost participation should begin at the inception of a project
with the Government and the performer each bearing a percentage
of each dollar of allowable costs, including any overrun costs,
as they are incurred. Net income, if any, should be shared in
proportion to the accumulated investment of the parties at the
time of accrual. Failure to reach agreement on cost participation
from project inception may be sufficient reason for project
cancellation.
Section 43
Specific cost participation arrangements must be determined on a
project-by-project basis. The concept of sharing risks and
benefits equally over the life of the project should be the basis
for such a determination. The actual share may be adjusted for
relevant business, technical, and risk factors, particularly as
the project proceeds through its life cycle. Effective
competition will be the ultimate evaluation tool in determining
whether proposals accurately reflect the risks and benefits
anticipated by the offerors. Management responsibilities and
authorities generally should reflect the relative proportion of
funding from each party during the phase being executed.
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
I-33
(4) Since most cost participation projects span several years,
funding of the Government’s share of construction costs should be
sought to demonstrate the Government’s intent to complete the
project. Budgets and program plans should be based on equal
share concept adjusted for relevant business, technical, and risk
factors.
Vertical line denotes change
Key Decisions in the Acquisition Process
for Construction or Development Projects
Figure I-7
DOE 4700.1
3-6-87
I-35
1.
2.
3.
PART E - OTHER PROJECTS
INTRODUCTION. Other projects are not subject to the policy of OMB Circular
A-109. However, other projects of significant value should adhere to the same
management conditions and practices as larger projects to the extent prac-
ticable. The program Secretarial Officer, program manager, or the Head of the
Field Element is responsible for proper application of PMS, choosing manage-
ment practices commensurate with the size, scope and complexity of the pro-
ject.
OTHER PROJECT DECISIONS.
a. Decisions on other projects should be made by the program Secretarial
Officer, the program manager, the Head of the Field Element, or the pro-
ject manager. The authority should be delineated, typically in a respon-
sibility matrix.
b. In a manner similar to key decisions, there should be an affirmative
determination to:
(1) Begin a project;
(2) Commence Title II, or Final/Detailed Design;
(3) Start construction, or enter full scale development; and
(4) Operate or produce (as necessary.)
c. In addition, major resource commitments also should be made only following
an affirmative decision.
OTHER PROJECT MANAGEMENT PROCESS.
a. The process for managing other projects is similar to that used in
managing large projects:
(1) There must be proper coordination of line, staff, and contractor
organizations;
(2) The project must be related to a mission area assignment, to a
mission need, and to Departmental goals; and
(3) Making major resource commitments without adequate project definition
must be avoided.
I-36
b.
DOE 4700.1
3-6-87
Similarly, the progression of projects is the responsibility of a single
person having clear lines of authority and communications with respect to
the project. This individual will be responsible for planning, acquisi-
tion, environmental impact, execution, and transition as these areas
relate to the project.
DOE 4700.1 Chg 1
6-2-92
Attachment I-1
Page I-37
ENERGY SYSTEM ACQUISITION ADVISORY BOARD PROCEDURES
1. PURPOSE. The purpose of the Energy System Acquisition Advisory Board
(ESAAB) is to assist the Acquisition Executive in the decision-making
process for MSAs and selected MPs. The ESAAB process is also utilized for
site selection determinations. In such circumstances, the ESAAB
membership and procedures are as described in paragraph 4, below.
Section 44
2. MEMBERSHIP AND RESPONSIBILITIES.
a. Members of the ESAAB.
(1) The Deputy Secretary/Under Secretary serve as the Acquisition
Executive for their respective program areas by direction from
the Secretary of Energy. The Acquisition Executive chairs the
ESAAB and has approval authority for MSAs and selected MPs.
(2) The Assistant Secretary for Environment, Safety, and Health
advises the Acquisition Executive on:
(a) Environmental acceptability and readiness of the project to
proceed; and
(b) Environmental needs for ensuring phases.
(3) The General Counsel advises the Acquisition Executive on:
(a) Acquisition and construction issues;
(b) Licensing plan assessment;
(c) Legislative or executive action impact assessment;
(d) Patent issues; and
(e) Environmental requirements.
(4) The Chief Financial Officer advises the Acquisition Executive
on:
(a) Budget formulation and execution status;
(b) OMB and congressional concerns and positions; and
(c) Other financial management issues.
(5) The Director of Administration and Human Resource Management
advises the Acquisition Executive on:
(a) Real estate management policy and procedures;
Vertical line denotes change
Attachment I-1
Page I-38
DOE 4700.1 Chg 1
6-2-92
b.
c.
d.
(b) Facilities and maintenance management;
(c) Site development planning;
(d) Utilities management;
(e) Value engineering; and
(f) Personnel issues.
(6) The Director of Procurement, Assistance and Program Management
advises the Acquisition Executive on:
(a) Adequacy of
portions of
(b) Procurement
(c) Conformance
the acquisition strategy, including the related
the project plan;
and contractual policy assessment;
to and implementation of project management
system policies and procedures; and
(d) Results of independent cost estimates in support of key
decisions or the Executive Change Control Process.
Members to the ESAAB, for selected projects, include the Director of
Energy Research, Assistant Secretary for Nuclear Energy, and the
Director of Nuclear Safety. These members will provide an independent
assessment to the Acquisition Executive of potential concerns/issues
at its current phase and ensuing phases.
The Acquisition Proponent. The acquisition proponent will normally be
the Program Secretarial Officer whose MSA or selected MP is being
presented for decision. The acquisition proponent is responsible for:
(1) Conducting the pre-ESAAB review;
(2) Providing to the ESAAB Secretariat a draft of proposed changes to
the project plan and related documentation for executing the
project; and
(3) Providing the final updated project plan to the board Secretariat
after decisions have been made for review and approval by the
Acquisition Executive.
ESAAB Secretariat. The Associate Director for Program/Project
Management & Control serves as the ESAAB Secretariat, providing:
(1) Staff support to the Acquisition Executive and board members for
ESAAB and ESAR presentations (e.g., schedules, agenda, pre-
briefings and presentation requirements);
Vertical line denotes change
DOE 4700.1 Chg 1 Attachment I-1
6-2-92
3.
e.
f.
Page I-39
(2) Independent cost, schedule and technical assessments and analyses
of project planning, baseline changes, key decisions, expanded
decision points, other significant decisions, and budgetary
commitments; and
(3) Project management policy implementation activity and
assessments.
Section 45
Other Assistant Secretaries and Heads of Headquarters Elements may be
asked to participate as advisors when appropriate. Other officials
such as the cognizant DOE Field Office manager may be invited to serve
as advisors to the acquisition proponent.
The project manager will normally present the issues, except for Key
Decision O, and recommended decision for consideration to the board.
The program manager might present a portion of the briefing focusing
on the broader program considerations and issues, while the project
manager stresses the status of the project and problems/issues at the
project level. Other special reports may be presented by either, as
appropriate, such as the results of an independent cost estimate or
technical review.
ESAAB PROCEDURES. The Acquisition Executive may choose to make a decision
and issue a board memorandum without a formal board meeting. Dispensing
with the formal meeting shall be considered when the preliminary review to
a scheduled meeting indicates that there are not substantial issues which
would require a meeting. In this case, an action memorandum will be
prepared and submitted by the acquisition proponent stating the factors in
support of the decision requested. This action memorandum will be
coordinated with board members, advisors and others indicated by the
Chairman before it is forwarded for decision. Following approval by the
Acquisition Executive, the Secretariat will document the decision and the
actions and/or agreements that may have resulted from the process.
a. Scheduling of Energ y System Acquisition Advisory Board Meetings.
(1) A decision/review schedule will be developed and maintained
current by the ESAAB Secretariat for those projects which require
a board review because of an acquisition phase decision, siting
decision, problems, or other project developments that merit
management attention. The decision/review schedules will be
distributed to program offices monthly.
(2) Upon approval by the Acquisition Executive, formal scheduling of
reviews will be accomplished by the ESAAB Secretariat.
(3) Unscheduled board meetings may also be called at the request of
the Acquisition Executive or a Program Secretarial Officer.
These requests will be made through the ESAAB Secretariat.
Vertical line denotes change
Attachment I-1
Page I-40
DOE 4700.1 Chg 1
6-2-92
(4) The steps outlined below provide normal working
times and responsibilities for the activities prior to and
immediately following an ESAAB:
Board Schedule.
Calendar
Days
Relative
Responsible to
Office Meeting
a.
b.
c.
d.
e.
f.
g.
h.
i.
Draft submission to ESAAB members
of Justification of Mission Need,
Project Plan or other appropriate
baseline documentation
Pre-ESAAB meeting (Dry-run)
Program
Dry-run presentation comments
provided to Program Office
Final draft of Justification of
Mission Need, Project Plan or
other appropriate baseline
documentation
Presentation charts submitted to
OP/PM and ESAAB membership
Board briefing books/materials
prepared
Acquisition Executive pre-brief
ESAAB presentation
Board decision memorandum for
Acquisition Executive’s approval
Project documentation reflecting
board decisions provided for
Acquisition Executive’s approval
and issuance.
Program
Program
OP/PM
Program
Program
OP/PM
OP/PM
Program
OP/PM
OP/PM
60 days
20 days
15 days
10 days
10 days
7 days
5 days
O days
+15 days
+30 days
Section 46
b. ESAAB Preparation. It is essential that the presenters address the
significant issues and problems that are associated with the project;
that these issues and problems be fully coordinated well in advance
with cognizant staff and program officials; and that the Acquisition
Executive and the sponsoring Secretarial Officer receive concise
prebriefings to assure that an informed decision or review will occur.
(1) Project Presentation Review. A draft of the project presentation
shall be provided to the Office of Program/Project Management and
representatives for the board members by the cognizant Program
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
Attachment I-1
Page I-41
Secretarial Officer. The draft presentation will be reviewed for
conformance to DOE orders and policies and to identify any
remaining issues for discussion at the Pre-ESAAB meeting. The
draft presentation shall address, as minimum, the following
administrative actions:
(a)
(b)
(c)
Peer Group Review. The program shall receive a current
written statement of project endorsement for the Acquisition
Executive from their respective peer groups. This action
shall be completed prior to the Pre-ESAAB meeting.
Inspector General/General Accounting Office Check. The
program shall make the necessary contacts to determine the
current audit activity on the project and provide a written
statement on the status to the Acquisition Executive. This
action shall be completed and reviewed at the Pre-ESAAB
meeting.
Congressional Briefings. The program shall notify the
appropriate congressional committee staffs on project status
and determine interest or support. A written statement on
the congressional committee(s) response/position must be
completed following the Pre-ESAAB meeting and provided to
the Acquisition Executive prior to the ESAAB. This action
applies to Key Decisions 2 and 3.
(2) Pre-ESAAB Meeting (Dry-Run). The program and project managers
will schedule and conduct a “dry-run” of the developed
presentation for the sponsoring Secretarial Officer for review
and resolution of issues prior to the ESAAB meeting. The Office
of Program/Project Management and board member representatives
should also be invited to participate in a final exchange of
ideas, assure compliance with Department policy/procedures,
discuss and resolve outstanding issues, determine the status of
any independent cost estimating requirements (where applicable),
cover the status of administrative actions, and set a schedule
for remaining actions. At the conclusion of the “dry-run,” a
recommendation shall be made to the Acquisition Executive by the
Office of Program/Project Management on the readiness of the
project to proceed with the scheduled ESAAB meeting based on the
completeness of material and administrative actions presented at
the “dry-run.”
(3) Acquisition Executive Prebrief. A prebriefing is conducted by
the Office of Program/Project Management for the Acquisition
Executive to assist in his preparation for the board meeting.
The objectives of this prebriefing are to acquaint the
Acquisition Executive with a brief background and description of
the project, provide an independent assessment of remaining
issues/problems to be presented, clarify any technical and
management items and provide a final status on administrative
actions so as not to consume too much time during the formal
meeting. In addition, an independent assessment of the project
and issues will be presented with recommended solutions. Any
Section 47
Vertical line denotes change
Attachment I-1
Page I-42
DOE 4700.1 Chg 1
6-2-92
3.
4.
feedback from the prebrief shall be provided immediately by the
Office of Program/Project Management to the cognizant Program
Secretarial Officer.
ESAAB Memorandum. The board Secretariat shall prepare a memorandum
summarizing the results of the meeting.
a.
b.
The memorandum will specify decision(s) reached, actions assigned,
results of special studies and assessments, limitations associated
with approvals, resource levels which may be used for budgetary and
organizational planning, constraints on systems development and
definition, schedules for accomplishing action items, and the time
frame for the next meeting. A summary of the approved cost, schedule
and technical baselines will be attached to the memorandum.
The Secretariat will coordinate the proposed memorandum with the
members and advisors prior to forwarding it to the Acquisition
Executive. Dissenting views will be included in the package.
Signatures of each board member will be obtained on the final
document.
SPECIAL ESAAB FOR SECRETARIAL SITE SELECTION DECISIONS.
a. Responsibilities.
(1)
(2)
(3)
(4)
(5)
(6)
(7)
The ESAAB will be responsible for approving project site
selection decisions.
Program outlay offices will notify the Office of Program/Project
Management when initiating conceptual design on any project which
involves a site selection determination option.
The Office of Program/Project Management will maintain a list of
such projects and will advise the Acquisition Executive of the
schedule for the upcoming decisions.
The Office of Program/Project Management will include an
evaluation of siting considerations in the checklist used in the
project validation process.
Site selection criteria will be established and approved, and
site characterization studies and evaluations will take place
during the early design phase of the acquisition process.
A site selection decision will occur at the earliest appropriate
time during advanced development or preliminary design, although,
in some cases, site selection may not be feasible until Key
Decision 2, Start of Engineering Development or Detailed Design.
The Office of Program/Project Management will assist program
organizations in preparing for ESAAB site selection meetings.
Paperwork and administrative burdens associated with these
presentations will be minimized. Presentations will focus on
issues and ensure adequate coverage of all viable options.
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
Attachment I-1
Page I-43
5.
b. Procedures. The site selection decision process is as follows:
(1) The ESAAB will be convened to enable the Acquisition Proponent to
present background information related to the project and the
siting considerations.
(2) Detailed discussion of the various siting options, including the
pros and cons of each, will be conducted.
(3) The Acquisition Proponent will present specific recommendations
for a siting decision. Supporting and/or opposing views of
ESAAB members will then be considered, after which the ESAAB
Chairman will make the siting decision(s).
ESAAB INVOLVEMENT FOLLOWING SPECIAL INDEPENDENT SCIENTIFIC OR TECHNICAL
REVIEWS OF PROJECTS AND PROGRAMS.
a.
b.
Purpose. When directed by the Acquisition Executive, a special
independent scientific or technical review will be performed if
circumstances are presented that could potentially influence a project
or program from continuing in an effective manner. If the findings of
such a review will result in significant program or project
redirection, the ESAAB will be included in the decision-making
process.
Section 48
Responsibilities.
(1) The Program Secretarial Officers have the responsibility for
technical reviews of their programs or projects and will advise
the Acquisition Executive of events which could “trigger” an
independent scientific or technical review of any of their
programs or projects.
(2) The scientific advisor, when requested by the Acquisition
Executive, will organize independent panels to conduct scientific
or technical reviews of the project and will work with the Office
of Program/Project Management and Control to fully integrate the
cost, schedule and technical aspects into the review and
subsequent recommendations. Technical reviews will be conducted
in a manner which minimizes disruption and delays in the
accomplishment of ongoing projects.
(3) The Office of Program/Project Management and Control will:
(a) Review each new or proposed MSA and MP in order to assure
that high risk technical issues are identified and ensure
that a meaningful technical baseline is included in the
project plan.
(b) Apprise the scientific advisor whenever a potential
requirement for a review appears to be indicated.
Vertical line denotes change
Attachment I-1 DOE 4700.1 Chg 1
Page I-44 (through I-46) 6-2-92
(c) Independently track programs and projects and advise the
Acquisition Executive, of events that could “trigger” an
independent technical review.
(d) Arrange for a presentation to the ESAAB after appropriate
coordination with the Program Secretarial Officers
concerning review of the cost, schedule and technical
status. The cognizant Program Secretarial Officers will be
provided the opportunity to discuss the independent review
at the ESAAB meeting.
c. Events Which Will “Trigger" Independent Reviews. In addition to the
normal review of the project at the key decision points, certain
events could “trigger” an independent review. Examples of such events
are:
(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
Significant program redirection.
Technical problems such as original technical goals or criteria
not achievable.
Basic assumptions on which the project was based have changed.
Advent of a better technology significantly impacting the
project’s mission.
Changed external conditions, markets, economics, etc.
Significant funding constraints.
Lessons learned from other similar projects.
Recommendations from scientific advisor.
Requested by the Acquisition Executive.
Regulatory redirection when obtaining permits.
Vertical line denotes change
6-2-92
DOE 4700.1 Chg 1 Attachment I-2
Page I-47
GUIDELINES FOR PREPARATION FOR ESAAB MEETINGS
1.
2.
3.
GENERAL. These guidelines have been prepared to aid program and project
managers in their preparation of presentation materials for ESAAB
meetings. Attached is a set of sample charts. They may be augmented by
such additional charts that the managers feel are needed to illustrate
project systems, problems, issues, or other pertinent factors.
Presentation materials should be minimized to the extent practical.
COMPOSITION. Each presentation will be organized as followings:
a. Introduction and purpose of meeting;
b. Description of project;
c. Background;
d. Objectives and baseline;
e. Organization;
f. Readiness to proceed;
g. Problems/issues/items of concern; and
h. Summary of key points and next steps.
CHARTS. The discussion that follows describes the information to be
included on the viewgraph charts. All charts shall use standard DOE
notation, as applicable.
Section 49
a. Chart 1, Title Page. Indicate the official name of the project, the
name of the acquisition proponent, and the name of the presenters.
State the ESAAB decision that will be requested at the meeting.
b. Chart 2, Project Technical Process. Show a recent photograph or
artist’s conception of the project. Use a technical process flow
chart or similar graphic to summarize how the facility or machine is
expected to function. A history of project related events and a
detailed technical description should be avoided due to time
constraints. The ESAAB members and advisors should be briefed by
their respective staffs or may request a briefing by the Office of
Program/Project Management and Control.
c. Chart 3, Program/Project Objectives and Technical Baseline. State the
key program and project objectives. The relationship between the
program and project objectives should be clear. Show the basic
technical baseline requirements for the project.
Vertical line denotes change
Attachment I-2 DOE 4700.1 Chg 1
Page I-48 6-2-92
d.
e.
f.
g.
h.
i.
Chart 4, Baseline Project Summary Schedule - All Years. To provide an
overview of project activity, display the baseline schedule for the
life of the project. Include all Acquisition Executive decision
points, other critical decisions and events, major milestones
including ES&H milestones that may impact the project’s critical path,
and critical path for project implementation.
Chart 5, Baseline Resource Plan.
(1) This chart shall show the funding authority available and
anticipated. Show both cumulative obligations and costs planned
by fiscal year over the life of the project. Actual costs and
obligations shall be shown against these plans. All costs and
obligations shall be denoted in current-year dollars for the year
of expenditure.
(2) This chart shall address the total project cost and identify the
industry share, if appropriate. It shall also target the total
estimated cost for design and construction.
Chart 6, Project Organization. Show the participating organizations
and their responsibilities in the form of an organization chart. This
is the opportunity to depict the manner in which the project is being
managed. Laboratory/contractor/partner responsibilities should be
included. Also show, in a separate box, a summary of the DOE
staffing, both on-board and planned.
Chart 7, Readiness to Proceed. In a very brief, bullet style manner,
summarize progress, accomplishments and performance to date. Include
the most significant rationale for readiness to proceed and separately
list the subjects of any substantive problems, issues, and/or items
of concern that will be shown on the subsequent charts.
Chart 8, Problems/Issues/Items of Concern. Succinctly state the
problem, issue, or item of concern, list the corrective actions taken
to date, the additional corrective actions required (with dates), and
an assessment of the impact on the project. Prepare a separate chart
for each topic to be discussed in this section. Supplement each of
these charts, as necessary, with whatever illustrative material is
apprormiate to present the problem, issue, or item of concern in a
fully informative manner.
Chart 9, Summary of Key Points and Next Steps. This chart highlights
the key points from the presentation, restates the decision requested,
and identifies the next actions planned following the requested
decision by the Acquisition Executive.
Vertical line denotes change
Chart 1
Section 50
U.S. Department of Energy
Energy System Acquisition Advisory Board
Project ABC
ESAAB Decision Requested:
● Authority to Initiate Construction
Presented by:
Donald D. Doe
Project Manager
Richland Operations Office
May 12, 1984
Fuels and Materials Examination Facility
Attachment
I-2
Page 1-51
Doe
4700.1
3-6-87
DOE 4700.1
3-6-87
Attachment
I-2
Page I-52
Fiscal years
Attachment
I-2
P
a
g
e
I
-
5
4
chart 7
● Project Status:
Problem: Schedule Delay – Weather
DOE 4700.1
3-6-87
MAJOR SYSTEM ACQUISITION PROCEDURES .
1. PURPOSE. TO describe how the Department carries out a major system acquisi-
tion. The acquisition process is accomplished by the following steps (see
Figure I-8, page I-61).
a. Evaluation of Mission Needs.
(1)
(2)
(3)
Program Secretarial Officers conduct mission analysis to identify
mission needs and any alternative energy system options and design
concepts which are based on national planning documents, strategy
papers, or other energy policy and program-related data. A mission
need may result from a deficiency in existing capabilities or the
decision to establish new capabilities in response to a feasible
technological opportunity. Mission needs are independent of any
particular system or technological solution.
Where more than one Departmental Element is involved, roles and
responsibilities of each component will be assigned by the
Acquisition Executive. Two or more organizational elements may be
permitted to sponsor alternative energy system options and design
concepts in order to foster innovation and competition.
When required to satisfy mission responsibilities, contributions will
be made to the technology base by the conduct, support, or spon-
sorship of research; system design concept studies; proof of concept
work; exploratory subsystem development; and tests and evaluations.
b. Exploration of Alternative Systems.
( 1 ) Intended benefits to be derived from major system acquisitions shall
be optimized by competitive exploration of alternative system design
concepts and tradeoffs of capability, schedule, and cost. Care
should be exercised during the initial steps of the acquisition
process not to conform mission needs or project goals to any known
systems or products that might foreclose consideration of
alternatives.
(2) Alternative system design concepts will be solicited from a broad
base of qualified firms through the competitive procurement process.
In order to achieve the most preferred system solution, emphasis will
be placed on innovation and competition. To this end, participation
of smaller and newer businesses should be encouraged. Concepts will
be solicited primarily from private industry, and, when beneficial to
the Government, foreign technology and equipment may be considered.8
I
Attachment I-3 DOE 4700.1
Page 1-60
(3)
(4)
(5)
(6)
(7)
(8)
3-6-87
Requests for alternative system design concept proposals will explain .
the mission need, schedule, cost, capability goals, and operating
constraints. Each offeror will be free to propose his or her own
technical approach, cost and capability goals. In the conceptual and
early development stages, contractors shall not be restricted speci-
fically by detailed Government specifications and standards.
Section 51
Federal laboratories, federally funded research and development cen-
ters, educational institutions, and other not-for-profit organiza-
tions shall also be considered as potential sources for competitive
system design concepts. Ideas, concepts, or technology developed by
Government laboratories or at Government expense may be made available
to private industry through the procurement process or through other
established procedures. Industry proposals may be submitted on the
basis of these ideas, concepts, and technology, or on the basis of
feasible alternatives which the proposer considers superior.
Research and development efforts shall emphasize early competitive
exploration of alternatives as relatively inexpensive insurance
against the premature or preordained choice of a system that may
prove to be either more costly or less effective.
During the period of identifying and exploring alternative system
design concepts, contracts covering relatively short time periods at
planned dollar levels will be used. Parallel short-term contracts
are awarded for those concepts selected for further exploration to
expand on the concepts and reduce technical uncertainties in each
system. Timely technical reviews of alternative system design con-
cepts will be made to effect the orderly elimination of the least
attractive concepts.
When the system is being developed for Departmental use, contractors
shall be provided with operational test conditions, mission perfor-
mance criteria, and life cycle cost factors that will be used in the
evaluation and selection of the system(s) for full-scale development
and production. In addition, relevant operational and support
experience will be provided to assist participating contractors in
developing performance and other requirements for each alternative
system design concept as test and tradeoffs are made.
Development of subsystems that are intended to be included in a major
system acquisition shall be restricted to less than fully designed
hardware (full-scale development) until the subsystem is identified
as part of a system candidate for full-scale development. Exceptions
may be authorized by the Acquisition Executive if the subsystems are
long lead time items that fill a recognized generic need, or if they
have a high potential for common use among several existing or future
systems.
DOE 4700.1
3-6-87
Attachment I-3
Page I-61
(9) Selections from competing system design concept proposal shall be
based on a review by a team of experts, preferably from both inside
and outside the responsible development organization.
c. Title II or Detailed Design.
(1) Advancement to a competitive test/demonstration phase may be approved
by the Acquisition Executive when DOE’s mission needs, program objec-
tives, and project goals are reaffirmed, and when alternative system
design concepts are selected.
(2) Development of a single system design concept that has not been com-
petitively selected should be considered only if justified by urgency
of need or by the physical and financial impracticability of
demonstrating alternatives. Proceeding with the development of a
noncompetitive (single concept) system may be authorized by the
Acquisition Executive. Strong DOE project management and technical
direction should be used for these systems.
(3) Major system acquisitions will be structured and resources planned to
demonstrate and evaluate competing alternative system design
concepts that have been selected. Exceptions may be authorized by
the Acquisition Executive if demonstration is not feasible.
Section 52
d. Full-Scale Demonstration, Development or Construction.
(1)
(2)
Full-scale demonstration or development, including limited produc-
tion, may be approved by the Acquisition Executive when DOE’s mission
need, program objectives, and project goals are reaffirmed, and com-
petitive demonstration results verify that the chosen system design
concept(s) is sound.
Selection of a system(s) and contractor(s) for full-scale
demonstration/development and production/operation shall be made on
the basis of:
(a) System performance measured against current DOE mission need,
program objectives, and project goals;
(b) An evaluation of estimated acquisition and ownership costs; and
(c) The factors as contractors is demonstrated management, fi-
nancial, and technical capabilities to meet project objectives.
Attachment I-3 DOE 4700.1
Page I-62 3-6-87
(3) The project manager will monitor system tests and contractor progress .
in fulfilling system performance, cost, and schedule commitments.
Significant actual or forecast variances shall be brought to the
attention of the contractor for corrective action.
e. Production or Operation. Full production/operation may be approved when
the Department’s mission need, program objective, and project goals are
reaffirmed, and when system performance has been satisfactorily tested,
independent of user organizations, and evaluated in an environment that
assures achievement of objectives under expected operational conditions.
DOE 4700.1 Chg 1
6-2-92
CHAPTER II
STRATEGIC PLANNING, PROJECT PLANNING AND BUDGETING
1.
2.
3.
.
II-1
PART A - PROJECT INITIATION AND PLANNING DOCUMENTATION
INTRODUCTION. This chapter discusses both strategic planning and project
planning and budgeting. The terms “strategic planning” and “project
planning” may be most easily differentiated by discussing who has
responsibility and accountability for each and at what point in time a
departure is made from one to the other for a specific program or project.
STRATEGIC PLANNING. The Department is committed to the preparation of
strategic plans and annual updating of these plans to maintain them
current. This strategic planning will assure that energy, health, safety,
environment, technology, and economics are molded into a mutually
supportive framework. The plans will provide the capability for
integrating horizontally across the entire range of DOE programs to bring
plans and programs into line with near (1 to 5 years), mid (5 to 10
years), and long-term (15 to 20 years or longer) objectives of the
Department.
a. Responsibilities. Program Secretarial Officers shall be responsible
and accountable to the Secretary for the preparation and annual
updating of Department strategic plans, Multi-Year Program Plans, and
Crosscut Plans for which they have been assigned responsibility.
b. Annual Cycle. Each annual strategic planning cycle is focused on the
fiscal year, 3 years beyond the start of the planning cycle (the
budget cycle is 1 year forward from issuance of OMB guidance). The
strategic planning annual cycle is depicted in Figure II-1.
c. Guidance. Guidance on strategic planning is available from the Office
of Domestic and International Energy Policy.
Section 53
PROJECT PLANNING DOCUMENTATION. Project planning documentation is
necessary to establish approved project scope and technical performance
requirements, schedules, resource plans, levels of responsibility and
authority, organizational interfaces, implementation plans, and
accountability. The documentation is needed to assure the execution of
the project within the approved technical, cost, and schedule baselines.
The key documents required by the Project Management System (PMS) are
shown below and in Figure II-2. Detailed outlines and approvals for
project planning documentation for Major System Acquisitions (MSA) and
major projects are included in Attachments II-1 through II-6. Planning
documentation of other projects should be similar in coverage and quality,
although reduced in quantity to reflect the magnitude of the project and
field organization Procedures.
Vertical line denotes change
II-2 DOE 4700.1 Chg 1
6-2-92
ACTIVITY TIMING
1. Secretarial Policies and On Going
Strategies
2. Secretarial Planning Guidance Annually in August
Issued
3. Strategic Plans by Program Completed Annually by
Secretarial Officers mid-September
4. Review and Approval of Annually in September/October
Strategic Plans by the
Secretary
5. Multi-Year Program Plans Completed Annually by
mid-December
6. Program Guidance to Field Annually in late December
7. Identification of Planning Annually in January/February
Issues
8. Secretarial Decisions and IRB Annually in March/April
Guidance
9. Crosscut Plans Completed Annually by mid-July
Figure II-1
Chronology of Events in the Annual Strategic Planning Cycle
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
II-3
JUSTIFICATION OF PROJECT PLAN PROJECT
MISSION NEED (INCLUDING MANAGEMENT
CHARTER) PLAN
MAJOR SYSTEM REWIRED PER REWIRED PER REQUIRED PER
ACQUISITION ATTACHMENT II-1 ATTACHMENT II-2 ATTACHMENT II-4
MAJOR PROJECT REQUIRED PER REQUIRED PER REQUIRED PER
ATTACHMENT II-1 ATTACHMENT II-2 ATTACHMENT II-4
OTHER PROJECTS
$15-50 MILLION
APPROVED DATA RECOMMENDED PER REQUIRED PER
SHEET OR WPAS1/ ATTACHMENT II-2 ATTACHMENT II-5
TOTAL PROJECT
COST (TPC)
OTHER PROJECTS APPROVED DATA RECOMMENDED PER REQUIRED PER
$5-15 MILLION TPC SHEET OR WPAS ATTACHMENT II-2 ATTACHMENT II-5
OTHER PROJECTS APPROVED DATA APPROVED DATA REQUIRED PER
UNDER $5 MILLION SHEET OR WPAS SHEET OR WPAS ATTACHMENT II-5
GENERAL PLANT GROUPED ON GROUPED ON OPTIONAL GENERIC
PROJECTS SINGLE DATA SHEET SINGLE DATA SHEET ONLY
Figure II-2
Project Management System Documentation
Vertical line denotes change
DOE 4700.1 Chg 1
6-2-92
II-4
a.
b.
Justification of Mission Need. A Justification of Mission Need must
be submitted for Acquisition Executive approval at Key Decision O, for
projects anticipated to be designated as MSAs, and to the cognizant
Program Secretarial officer for approval on major projects. The
Justification of Mission Need and the Short Form Project-Data Sheet
must be approved prior to starting conceptual design. Other projects
are justified and approved on the basis of a project data sheet. The
cognizant Program Secretarial Officer may require a Justification of
Mission Need for significant other projects (e.g., $15-$50 million).
For projects currently well beyond Key Decision O, a Justification of
Mission Need is not required.
Attachment II-1 details the contents and procedures for developing the
Justification of Mission Need. A copy of the approved Justification
of Mission Need shall be attached to the Key Decision O Decision
Memorandum of Record and shall be reviewed at each ESAAB meeting.
Section 54
Project Plan. The project plan, which includes the project charter,
is a summary of the dimensions of the project to be executed,
including objective, schedule, resources, priority, controlled
milestones, and environmental requirements. For MSAs, the project
plan is a contract between Headquarters and the project office for
execution. For major projects, the project plan is an agreement
between the program office and project office for execution with the
project office reporting directly to the cognizant program office.
The project plan documents the initial cost, schedule and technical
project baselines defined in the CDR, and is updated, as required,
throughout the life of the project to ensure current project
baselines. It is prepared as required documentation to obtain
approval to include the project in the congressional. budget and for
Key Decision 1, Approval of New Start. The project plan is an
evolving document which covers the project from its initiation through
its completion. Guidelines for preparing project plans are contained
in Attachment II-2.
(1)
(2)
Major System Acquisitions and Major Project Approval. Project
plans require approval by the Acquisition Executive for MSAs and
major projects. (The cognizant Program Secretarial Officer serves
as the Acquisition Executive for major projects.) The plan
identifies Acquisition Executive and Program Level decision
points and other milestones, as appropriate. Changes to this
document are permitted only in accordance with formal change
control procedures.
Other Project Approval. There is no requirement for a
Headquarters approved project plan for other projects. However,
the Program Secretarial Officer may require such a plan where
significant resources are involved. Where there is not a
requirement, the circumstances do not obviate the need for such a
plan. For other projects, the project data sheet has many of the
Vertical line denotes change
6-2-92
D0E 4700.1 Chg 1 II-5 (through II-8)
ingredients of a project plan and may serve that purpose with
minor additional information. Field organizations should
establish their own procedures for project plan content and
approval.
(3) Standard Baselines Formats. Attachment II-2 provides
requirements and guidance for preparation of technical, schedule
and cost baselines in project plans.
(4) Changes to the Project Plan. Because the project plan reflects
Acquisition Executive approval, it is essential that the plan be
maintained current. Attachment II-3 provides project plan change
control requirements and guidelines.
c. Project Management Plan. The Project Management Plan (PMP) is the
document which sets forth the plans, organization, and systems that
shall be utilized by those responsible for managing the project. The
PMP is developed by the project manager and concurred with by the
Program Secretarial Officer and approved by the Head of the Field
Element. Guidance for preparation of a PMP is provided in Attachment
II-4.
Vertical line denotes change
DOE 4700.1
3-6-87
II-9
PART B - WORK BREAKDOWN STRUCTURE
1. INTRODUCTION.
Section 55
a. Much of the planning, execution, and control of DOE projects revolves
around the work breakdown structure (WBS). DOE/MA-0040, of October 1981,
provides detailed guidance on WBS implementation. The WBS is a graphic
representation that completely defines the project by relating elements of
work to each other and to the end product. It is the prime tool which DOE
uses in performance of its project responsibilities. A complete guide to
the development and use of the WBS is contained in DOE/MA-0040. Figure
II-3 illustrates a typical WBS. The individual products specified in the
WBS are termed “elements.” Each element is a discrete portion of the WBS,
comprising either an item of hardware, service, or data. Descending
levels provide increasingly detailed definition of the end objective. The
number of levels depends on the scope and complexity of the individual
project and the degree of control it warrants. The top three levels of
the WBS for a project are typically subdivided as below. These three
levels are frequently called a summary WBS, or a Project Summary WBS
(PSMBs).
(1) Level one contains only the project end objective. The product at
this level shall be identifiable directly to elements of the DOE
Budget and Reporting Classification Structure.
(2) Level two contains the major product segments or subsections of the
end objective. Major segments are often defined by location or by
purpose served.
(3) Level three contains definable components, or subsets, of the level-
two major segments.
b. WBS Dictionary. The WBS Dictionary lists and defines the WBS elements.
It is prepared initially by the DOE project manager and then expanded by
supporting contractors. It consists of two parts: Part I is an index
which lists WBS elements extended in accordance with the guidance
contained herein, and Part II contains individual entries to describe each
WBS element and the effort associated with it. The WBS Dictionary shall
be revised to reflect changes and shall be maintained in a current status
throughout the life of the project.
2. PREPARATION OF A WORK BREAKDOWN STRUCTURE. The project manager is responsible
for preparation of the project WBS. This WBS in summary form is then included
in the solicitation documents for contractor information. Contractors, in
turn develop a contract WBS to conform to their support of the project. This
flow of activity is illustrated in Figure II-4.
Figure II-3
Work Breakdown StructureTypical
DOE
Project
Management
Responsibility
Contractors
Responsibility
(1 or More)
Figure II-4
Evolution of the Project Work Breakdown Structure
II-12 DOE 4700.1
3-6-87
3. USES OF THE WORK BREAKDOWN STRUCTURE. A WBS shows the relationship of all
elements supporting the project and provides a sound basis for technical cost
and schedule control. Each level of the structure is closely related to a
management sphere within the project, providing the framework for relating
time and cost summaries to appropriate levels of contractor and DOE managers.
A WBS provides both a basis and an integrating mechanism, for managing key
functions of the project. Use of the WBS to support management control is
described below:
a.
b.
c.
d.
e.
f.
Planning and Budgeting. The WBS technique provides a formal structure
which identifies all the products and relates all the work effort required
to meet the project objective. By breaking the total product and effort
into successively smaller entities, DOE can ensure that all required prod-
ucts are identified to the WBS (and hence, charged to the effort) and
actually contribute to the work objective. Figure II-5 illustrates the
relationships among work, schedule, and budget integration.
Section 56
Funding. The information derived from WBS performance reporting and pro-
jections can assist in establishing, justifying, and allocating project
funds for the next and future fiscal years. Since the work and cost con-
tent, management priority, and status of each WBS element are defined, a
baseline exists for planning, controlling, and accounting for project
funds.
Cost Estimating. The WBS technique provides a systematic approach to cost
estimating that ensures relevant costs are not omitted. An estimate
derived by WBS elements helps the Departmental project manager to monitor,
coordinate, and control the various project activities that DOE and the
contractors are conducting.
Scheduling. The WBS provides a framework for collecting schedule infor-
mation by WBS elements to establish overall and detailed schedules. The
impact of schedule changes may be readily assessed when a WBS is used
because each element’s start and completion date is integrated with the
other elements’ schedules. This allows expedited review and approval by
the Department of contractor proposed schedule changes.
Performance Measurement. The WBS technique accomplishes the objective of
work definition and provides the basis for performance measurement with a
product orientation. It also facilitates work measurement at levels which
meet specific management needs.
Configuration Management. Configuration management is the task of
managing, controll ing, and reporting the planned and actual design of the
physical characteristics of items throughout their intended life. The WBS
may be extended sufficiently to identify elements selected for this pur-
pose. It is not necessary that the WBS level identified for project
control purposes (e.g., contract reporting) be the same as that used for
configuration management.
DOE 4700.1
3-6-87
II-13
DOE 4700.1
3-6-87
II-14
g. Integrated Logistic Support. Integrated logistic support is a composite
of all support elements necessary to assure the effective and economical
support of a system for its life cycle. These elements include logistical
support activities such as the maintenance plan, facilities, support and
test equipment, spares and repair parts, transportation and handling,
technical data, and training. The WBS logistic elements should provide
the capabilities to support the prime system and its components. The ele-
ments shall reflect the lead time planning needs of the site or test
facility.
h. Test and Evaluation. A WBS may provide specifically for testing systems,
subsystems, and components. A test and evaluation element shall be used
to obtain or validate test performance data. This element shall cover the
detailed planning, conduct, support, data reduction, and reports from the
testing. Since testing requires the participation of organizational ele-
ments responsible for accomplishing development, reliability, and qualifi-
cation tests, appropriate supporting elements need to be included.
i. Systems Engineering. The WBS may be used initially to lay out system
functions in the systems engineering discipline. Following design and the
development of a specification tree, the WBS shall be revised to reflect
the end product. Throughout systems engineering, the WBS shall be updated
to reflect current status of the end product.
DOE 4700.1 Chg 1
6-2-92
II-15
1.
2.
PART C - PROJECT BUDGET PROCESS
Section 57
INTRODUCTION. Providing adequate resources to develop, acquire, and
operate a project is first a design constraint and secondly a
determination of the Department’s planning and budgeting process. The
budget decisions shall be consistent with project baselines decisions
derived requirements contained in the project management system. Figure
II-6 displays the chronology of events leading to appropriation of funds.
PROCEDURES. Integration of decisions concerning project resource
availability in the planning and budgeting process involves the following
procedures:
a. Field Budget Call. A field budget call shall be issued by the Chief
Financial Officer in mid-to-late January incorporating any budget
planning decisions that have been made by the Secretariat. Prior to
including a project in the budget, a conceptual design shall be
completed in accordance with Attachment V-8. Also, any planned
conceptual designs which are expected to exceed $1 million shall be
completed and submitted to Headquarters in accordance with Attachments
V-9 and V-10. Project Data Sheets shall be developed and submitted
for new project efforts and ongoing project efforts which require
additional funding. This documentation, and the conceptual design
report shall be used to validate the project and to defend the project
in the internal review budget.
b. Project Validation. Shortly after the field call is issued, the
Office of Program/Project Management shall issue procedures and a
checklist to be used with the information received in the field budget
submission to conduct project validations. In April and May, the
Office of Program/Project Management, in coordination with the program
offices, shall assess new projects over $5 million and ongoing
projects requesting additional funding. The validation process
evaluates the projects for readiness to proceed into the Department’s
budget process and examines the planning, development, and baseline of
a project to ensure that the funds requested are commensurate with the
project’s anticipated scope and schedule. Normally, the project must
be validated prior to inclusion in the internal review budget.
c. Internal Review, Office of Management and Budget, and Congressional
Budgets. These reviews and budgets are described in detail in DOE
Project documentation shall be updated according to decisions
made in each review. The Conceptual Design Report, Justification for
Mission Need, and Project Data Sheet are the mainline documents used
to defend the project within the Department. Outside DOE (i.e., OMB
and Congress) only the Project Data Sheet is used. Therefore, it is
vital that the document be accurate and up-to-date for each review.
Detailed instructions for preparing the data sheets are contained in
DOE 5100.3.
5100.3.
Vertical line denotes change
II-16 DOE 4700.1
3-6-87
3. FIELD WORK PACKAGE PROPOSAL AND AUTHORIZATION SYSTEM.
a. Specific DOE contractors, primarily management and operations
contractors, process their budget submissions through the use of the
Field Work Package Proposal and Authorization System (WPAS). This
system establishes a formal procedure for budget development,
authorization, and monitoring for those contractor so specified.
b. The major emphasis of WPAS is to group associated R&D tasks and
activities into work packages for the purpose of DOE approval and
control. A work package might include several proj