Section 1

DOE 4320.2A 2-10-94 CAPITAL ASSET MANAGEMENT PROCESS 1. PURPOSE. To establish policy and responsibilities for the management of Department of Energy (DOE) assets; for prioritization of asset resource requirements; for implementing the Condition Assessment Survey (CAS); and for preparing the Capital Asset Management Process (CAMP) Report. 2. CANCELLATION. DOE 4320.2, CAPITAL ASSET MANAGEMENT PROGRAM, of 3-13-92. 3. SCOPE. This Order applies to assets DOE owns, leases, or controls for production, operation, research, development, or demonstration; except for the exclusions stated below or as otherwise provided by statute or by separate delegation of authority from the Secretary of Energy. The provisions of this Order apply to all Departmental Elements and to covered contractors to the extent implemented under a contract or other agreement. A covered contractor is a seller of supplies or services under a management and operating contract. All paragraphs of this Order are to be applied to covered contracts except paragraph 8. 4. EXCLUSIONS. a. This Order does not apply to assets entirely controlled and maintained by the General Services Administration (GSA), and the Naval Petroleum Reserves in California. b. Executive Order 12344, (Order), Title 10 Code of Federal Regulations (CFR) 445.1 et seq., reprinted in Title 42 United States Code (U.S.C.) § 7158 note, establishes the responsibilities and authority of the Director, Naval Nuclear Propulsion Program, Office of Nuclear Energy, over all facilities and activities that comprise the joint Navy-DOE program. In view of the unique nature of Naval nuclear propulsion applications, the Director shall determine the appropriate maintenance and repair criteria applicable to this program's property and activities. Such determination shall include consideration of appropriate parts of the criteria set forth in this Order. Public Law (P.L.) 98-525, Title XVI, § 1634, directs that provisions of this Order pertaining to the Naval Nuclear Propulsion Program shall remain in force until changed by law. c. In accordance with Section 302 of the Department of Energy Organization Act of 1977 (P.L. 95-91, 91 Stat. 578), the Secretary operates and maintains the Power Marketing Administrations (PMA) electric power transmission systems by All Departmental Elements Office of the Associate Deputy Secretary for Field Management 2 DOE 4320.2A 2-10-94 and through the PMA Administrator. The PMAs have maintenance management programs in place that are geared to the special needs of utility operations, responsive to coordinated multi-utility system requirements, and in conformance with prudent utility practices. Administrators shall determine the appropriate maintenance management program for their facilities including consideration of appropriate parts of the criteria set forth by this Order. 5. REFERENCES AND DEFINITIONS. See Attachment 1. 6. POLICY. Assets shall be managed in a manner demonstrating good stewardship, sufficient to ensure facility preservation and to ensure safe, secure, environmentally sound, and cost-effective operations. Assets shall be maintained in accordance with policies and practices that reflect Departmental standards and national priorities. In addition, prioritization of asset projects shall be objectively determined on the basis of sound, traceable engineering and industry practices, and management judgment. 7. OBJECTIVES.

Section 2

a. Provide a credible, standardized and auditable process that is objectively and consistently applied DOE-wide to assess asset conditions, identify and prioritize corrective actions, allocate resources, and establish schedules. Implement this process in a cost- effective manner in full consultation with the appropriate Secretarial Officers and related parties. b. Ensure responsibility, authority, and accountability for management of DOE assets are clearly defined and appropriately assigned. c. Identify asset maintenance and technical support requirements. d. Provide asset management tools such as CAS, Life Cycle Plans (LCPs), the Project Prioritization Process, and the Site CAMP Report. These tools serve to effectively and efficiently plan and budget projects consistent with anticipated missions. e. Provide asset managers with a comprehensive look at the condition of their asset inventory and serve as a vehicle to effectively plan and prioritize projects. f. Ensure assets needed to meet future and assigned missions are sustained in appropriate condition. g. Provide a mechanism to develop Site CAMP Reports that document the results of the process described in this Order. The Site CAMP Reports support budget requests and are not budget documents in and of themselves. DOE 4320.2A 3 2-10-94 8. RESPONSIBILITIES AND AUTHORITIES. a. The Secretary has overall responsibility and authority for CAMP and shall take necessary management actions, through the Associate Deputy Secretary for Field Management, to ensure that the Department's assets are effectively managed and maintained. b. The Associate Deputy Secretary for Field Management shall provide management direction and coordination in the development, implementation, and conduct of oversight of the comprehensive Departmental CAMP program, have the primary stewardship responsibility to implement CAMP policies and procedures in an effective manner, and shall: (1) Advise the Office of the Secretary and Heads of Headquarters and Field Elements at least annually on the status of CAMP. In addition, provide recommendations as appropriate. (2) Provide support to Departmental Elements on CAMP as required. (3) Appoint the DOE CAMP Administrator to serve as the focal point for CAMP development and implementation, and direct the activities of the Planning and Analysis Group. (4) Oversee a Planning and Analysis Group consisting of DOE and contractor representatives. The Planning and Analysis Group helps to ensure that the CAMP Order is consistently applied and observed throughout DOE. It also analyzes the results of the CAMP and provides feedback and recommends enhancements to improve CAMP, assists users with specific technical problems, and recommends changes to the CAMP Order. Additionally, the Planning and Analysis Group shall develop and maintain appropriate training and guidance materials (e.g., a CAMP Handbook) to assist users in applying the process and preparing the CAMP Report. (5) Provide management direction and coordination to develop and implement training for the policies and procedures of this Order. (6) Develop, promulgate, and maintain all policies, procedures, and guidance materials necessary to implement and sustain an effective CAMP within the Department. (7) Serve as the Departmental oversight body to ensure that CAMP is effectively implemented by Headquarters line management through the Field Elements and the sites. (8) Issue the annual CAMP Call.

Section 3

(9) Develop and maintain the CAS manuals, a Quality Assurance program for CAS, and Condition Assessment Information System (CAIS). (10) Support CAS teams as appropriate and necessary. (11) Provide liaison with Headquarters Elements. (12) Provide annual program direction and guidance to field elements according to the schedule provided in the annual CAMP Call. This guidance shall include workload and strategic planning assumptions necessary for the preparation of Site CAMP Reports. (13) Ensure that their organizations have the necessary resources and organizational structure to effectively manage assets consistent 4 DOE 4320.2A 2-10-94 with this and other related Orders. (14) Review Site CAMP Reports for consistency and adequacy. Ensure that performance trends are detected and used to develop optimum CAMP strategies. (15) Ensure budget proposals for field elements provide sufficient resources to implement and operate CAMP. (16) In coordination with Heads of Headquarters Elements, assure consistency and integration of CAMP reporting requirements with other facilities related Orders, including, for example, DOE 4330.4B, MAINTENANCE MANAGEMENT PROGRAM, DOE 4320.1B, SITE DEVELOPMENT PLANNING, and DOE 5100.3, FIELD BUDGET PROCESS. (17) Coordinate implementation of CAMP at Multi-Contractor and Multi- Program Sites to ensure consistency and minimize reporting requirements. c. Heads of Headquarters Elements (1) Provide the budget for the assets required to meet mission assignments. In addition, Heads of Headquarters Elements shall take all actions necessary to meet their statutory responsibilities to maintain their program's assets in the most reasonable and economical manner possible. (2) Designate an organizational element specifically responsible for the program element CAMP. (3) Provide annual CAMP data requirements and instructions to the DOE CAMP Administrator to develop and release the consolidated CAMP Call. d. Heads of Field Elements shall: (1) Ensure assets under their purview are managed consistent with this and other related Orders. DOE 4320.2A 5 (and 6) 2-10-94 (2) Provide for the assets required to meet mission assignments. In addition, Heads of Field Elements shall take all actions necessary to meet their responsibilities to maintain assets in the most reasonable and economical manner possible. (3) Provide guidance and direction to site operating contractors consistent with this and other related orders. Assure existing and proposed site management and operating contracts include provisions to implement this Order. Include in a procurement request package, the appropriate Department of Energy Acquisition Regulations (DEAR). (4) Ensure that Site CAMP Reports are prepared and provided to the appropriate Heads of Headquarters Elements in accordance with this Order, Headquarters guidance, and the schedule provided in the annual CAMP Call. (5) Designate an organizational unit specifically responsible for the CAMP. (6) Advise the responsible Headquarters Element of CAMP-related problems that may have significant site or Department level impact. (7) Review Site CAMP Reports for consistency and adequacy. Ensure that performance trends are detected and used to develop optimum CAMP strategies. (8) Ensure budget proposals for assigned functions provide sufficient resources to meet requirements identified in the Site CAMP Report, to implement and operate CAMP, and to address recommendations from the responsible Headquarters Element in the formulation of budget requests.

Section 4

(9) Ensure appropriate maintenance issues for assets are addressed in the Site CAMP Report. (10) Assure consistency and integration of CAMP reporting requirements with other facilities-related Orders, including, for example, DOE 4330.4B, MAINTENANCE MANAGEMENT PROGRAM; DOE 4320.1B, SITE DEVELOPMENT PLANNING; and DOE 5100.3, FIELD BUDGET PROCESS. 9. ASSISTANCE. Questions concerning this Order should be directed to Greg Coleman, FM-22, 202-586-4543. DOE 4320.2A Attachment 1 2-10-94 Page 1 REFERENCES 1. DOE 1300.2A, DEPARTMENT OF ENERGY STANDARDS PROGRAM, of 5-19-92, establishes general policy guidelines, authorities, and responsibilities for DOE standards programs and guidelines for participation in private sector standards organizations. 2. DOE 2200.6A, FINANCIAL ACCOUNTING, of 1-7-93, is the Accounting Handbook for the Department. 3. DOE 4320.1B, SITE DEVELOPMENT PLANNING, of 1-7-91, establishes policies and assigns responsibilities and authorities for the planning and development of DOE sites. 4. DOE 4300.1C, REAL PROPERTY MANAGEMENT, of 6-28-92, establishes Department wide policies and procedures for the acquisition, use, inventory, and disposal of real property or interests therein. 5. DOE 4330.2D IN-HOUSE ENERGY MANAGEMENT, of 5-18-92, prescribes policies and procedures, assigns responsibilities and authorities for the management of energy use in DOE facilities (owned and leased) and vehicles and equipment. 6. DOE 4330.4B, MAINTENANCE MANAGEMENT PROGRAM, of 2-10-94, establishes policy and objectives for the establishment of programs for the management and performance of cost-effective maintenance and repair of DOE property. 7. DOE 4700.1, PROJECT MANAGEMENT SYSTEM, of 3-6-87, Chapter III, "Configuration Management," is a project management tool designed to: (a) determine and control baselines; and (b) ensure and document that all components of a project interface both physically and functionally. 8. DOE 4700.3, GENERAL PLANT PROJECTS, of 9-16-91, establishes policies, responsibilities, and guidance for Headquarters offices and field elements for the budgeting, funding, and execution of general plant projects (GPP). 9. DOE 5000.1B, INSTITUTIONAL PLANNING BY MULTIPROGRAM LABORATORY, of 4-9-92, establishes policies regarding institutional planning, outlines general characteristics of a satisfactory planning process, defines Departmental responsibilities, and describes the relationship of the planning process to the oversight of laboratory exploratory research and development (R&D) and work for others. 10. DOE 5100.3, FIELD BUDGET PROCESS, of 8-23-84, provides requirements and procedures for the preparation and submission of field budget material required for preparation of the DOE budget. 11. DOE 5440.1E, NATIONAL ENVIRONMENTAL POLICY ACT COMPLIANCE PROGRAM, of 11-10-92, establishes internal responsibilities and procedures to implement the National Environmental Policy Act of 1969 (NEPA). Attachment 1 DOE 4320.2A Page 2 2-10-94 12. DOE 5480.1B, ENVIRONMENT, SAFETY, AND HEALTH PROGRAM FOR DEPARTMENT OF ENERGY OPERATIONS, of 9-23-86, establishes the Environment, Safety, and Health (ES&H) Program for DOE operations. 13. DOE 5480.19, CONDUCT OF OPERATIONS REQUIREMENTS FOR DOE FACILITIES, of 7-9-90, provides requirements and guidelines in developing directives, plans, and/or procedures relating to the conduct of operations at DOE facilities.

Section 5

14. DOE 5483.1A, OCCUPATIONAL SAFETY AND HEALTH PROGRAM FOR DOE CONTRACTOR EMPLOYEES AT GOVERNMENT-OWNED CONTRACTOR-OPERATED FACILITIES, of 6-22-83, establishes requirements and procedures to ensure occupational safety and health standards pursuant to the Atomic Energy Act of 1954, as amended, the Energy Reorganization Act of 1974, and DOE Organization Act of 1977, provide occupational safety and health protection for DOE contractor employees in Government-owned contractor-operated facilities. This protection is consistent with the protection afforded private industry employees by the occupational safety and health standards promulgated under the Occupational Safety & Health Act of 1970 (OSHA), P.L. 91-596, 84 Stat. 1590. 15. DOE 5632.6, PHYSICAL PROTECTION OF DOE PROPERTY AND UNCLASSIFIED FACILITIES, of 2-9-88, establishes DOE policies and procedures for the physical protection of DOE property and unclassified facilities, and establishes baseline physical protection requirements and standards for those interests. 16. DOE 5700.6C, QUALITY ASSURANCE, of 8-21-91, provides DOE policy, sets forth requirements, and assigns responsibilities for establishing, implementing, and maintaining plans and actions to assure quality achievement in DOE programs. 17. DOE 6430.1A, GENERAL DESIGN CRITERIA, of 4-6-89, provides general design criteria for use in the acquisition of the Department's facilities and establishes responsibilities and authorities for the development and maintenance of these criteria. DOE 4320.2A Attachment 1 2-10-94 Page 3 ABBREVIATIONS ALARA - As Low As Reasonably Achievable CAMP - Capital Asset Management Process CAIS - Condition Assessment Information System CAS - Condition Assessment Survey CDR - Conceptual Design Report CE - Capital Equipment CFO - Chief Financial Officer CFR - Code of Federal Regulations D&D - Decontamination & Decommissioning DOE - Department of Energy ES&H - Environment, Safety & Health FU - Functional Unit FUBS - Functional Unit Breakdown Structure FUDS - Functional Unit Data Sheet GPP - General Plant Project GSA - General Services Administration IRB - Internal Review Budget LCP - Life Cycle Plan NEPA - National Environmental Policy Act of 1969 OMB - Office of Management & Budget OSHA - Occupational Safety & Health Act of 1970 P.L. - Public Law PMA - Power Marketing Administration R&D - Research & Development S&S - Safeguards & Security SNM - Special Nuclear Material TSA - Technical Safety Appraisal U.S.C. - United States Code Attachment 1 DOE 4320.2A Page 4 2-10-94 DEFINITIONS 1. ASSET. A tangible product of value, generally property or equipment, that has an anticipated service life of 2 years or more and a cost equal to or greater than $5,000. (See DOE 2200.6A, FINANCIAL ACCOUNTING). 2. CAPITAL ASSET MANAGEMENT PROCESS. The standardized, auditable process for determining condition of DOE assets including forecasting life cycle events, and identifying, planning, and prioritizing activities necessary to meet the requirements. 3. CATEGORIES. The four major functional areas of consideration for project prioritization ranking. They are as follows: a. health and safety b. environment/waste management c. safeguards and security d. programmatic 4. CONDITION ASSESSMENT INFORMATION SYSTEM. The Condition Assessment Information System (CAIS) is an electronic database providing descriptive information on the material condition of a site's assets.

Section 6

5. CONDITION ASSESSMENT SURVEY. A periodic systematic inspection process to determine asset conditions using universally accepted methods and standards. A CAS results in a determination of the current condition of assets, their estimated time to failure, and the estimated cost to correct the identified deficiencies. These methods and standards will be found in the CAS Manuals discussed in Chapter II. CAS assesses the condition of all assets including architectural, structural, mechanical, civil, geotechnical and electrical features; communications, safety, and security systems; exterior features and grounds; and equipment. CAS provides a consistent assessment of assets for planning purposes based on actual conditions. 6. CRITERIA. Standard benchmarks for each major category and its respective subcategories on which a decision can be made for rating a specific problem/project. 7. FUNCTIONAL UNIT. A functional unit (FU) is comprised of an assembly of similar assets. The FUs shall be capable of being audited in terms of mission requirements and performance standards. 8. FUNCTIONAL UNIT BREAKDOWN STRUCTURE: The Functional Unit Breakdown Structure (FUBS) provides a method for identifying a site's FUs and establishing a framework for reporting on the Department's assets by FU. The FUBS is a series of FUs that include all assets and provides a logical hierarchical structure for identifying, summarizing, and justifying asset needs. DOE 4320.2A Attachment 1 2-10-94 Page 5 9. FUNCTIONAL UNIT DATA SHEET. The Functional Unit Data Sheet (FUDS) is a summary document containing the relevant data for a significant project in the life of a particular FU. (See Chapter 3, Attachment III-1) 10. HEADS OF HEADQUARTERS ELEMENTS. Senior program managers within a line organizational structure. For purposes of this Order, these positions include appropriate Secretarial Officers and Directors, and the Administrators of the Bonneville and Western Area Power Administrations. 11. LIFE-CYCLE PLAN. A Life-Cycle Plan (LCP) shows forecasted major activities in the life of an asset through final disposition. 12. LINE MANAGEMENT. The organizational chain of command responsible for carrying out Departmental policies and procedures. For purposes of this Order, line management flows from the Secretary through the Associate Deputy Secretary For Field Management to the Heads of Headquarters Elements, then to the Heads of Field Elements. 13. MAINTENANCE. Day-to-day work that is required to sustain property in a condition suitable for it to be used for its designated purpose and includes preventive, predictive, and corrective (repair) maintenance. 14. MAINTENANCE BACKLOG. The maintenance and repair work not accomplished that is still needed to sustain the assigned mission. 15. PROJECT. A project is the selected alternative listed and prioritized in the CAMP report for meeting an asset requirement. A project may involve a single asset or an entire functional unit. CAMP projects include significant maintenance; reduction of the site's existing maintenance backlog; CE; GPP; expense-funded line-item project development activities, such as conceptual design report (CDR) and NEPA activities, and construction activities; or line-item projects. 16. RANKING. Ordering of projects in terms of priority. 17. RATING. Estimate of the severity of a problem or assessment of a condition. 18. REMEDIATION. Elimination of any problems remaining after decommissioning.

Section 7

19. REPAIR. The restoration of failed or malfunctioning equipment, system, or facility to its intended function or design condition. Repair does not result in a significant extension of the expected useful life. 20. SECRETARIAL OFFICER. For purposes of this Order, a Secretarial Officer is a senior outlay program official and includes the following Assistant Secretaries: Defense Programs, Energy Efficiency and Renewable Energy, Environmental Restoration and Waste Management, and Fossil Energy, and the following Directors: Civilian Radioactive Waste Management, Energy Research, and Nuclear Energy. 21. SCORE. The numerical scale for the benchmark criteria in each category and subcategory. 22. SHALL. Denotes a requirement. 23. SHOULD. Denotes a recommendation. 24. SITE. Geographic entity consisting of land, buildings, structures and utilities that are or will be used to support one or more mission objective. Attachment 1 DOE 4320.2A Page 6 2-10-94 25. SITE CAMP REPORT. Combines the functional unit analysis of life-cycle plans (LCP) and supporting functional unit data sheet (FUDS) into a Site CAMP Report, that will be prepared annually and submitted in support of budget submittals to the appropriate Heads of Headquarters Elements and Field Management through the responsible Field Element. The Site CAMP report provides the narrative basis for evaluating and justifying funding requests for asset requirements. 26. SUBCATEGORIES. Functional characteristics/requirements for project prioritization ranking within the four major categories. DOE 4320.2A i 2-10-94 TABLE OF CONTENTS Page CHAPTER I - ELEMENTS OF THE CAPITAL ASSET MANAGEMENT PROCESS 1. INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . I-1 2. PROCESS ELEMENTS . . . . . . . . . . . . . . . . . . . . . . . . . I-1 a. Assign Capital Assets . . . . . . . . . . . . . . . . . . . . I-1 b. Receive Headquarter's Guidance . . . . . . . . . . . . . . . I-1 c. Develop Life-Cycle Plans . . . . . . . . . . . . . . . . . . I-1 d. Identify Deficiencies/Requirements . . . . . . . . . . . . . I-1 e. Evaluate Alternatives . . . . . . . . . . . . . . . . . . . . I-1 f. Identify Projects . . . . . . . . . . . . . . . . . . . . . . I-2 g. Prioritize Projects . . . . . . . . . . . . . . . . . . . . . I-2 h. Prepare Site CAMP Report . . . . . . . . . . . . . . . . . . I-2 Attachment I-1. CAMP ANNUAL CYCLE OF EVENTS . . . . . . . . I-3 CHAPTER II - CONDITION ASSESSMENT SURVEY 1. INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . II-1 2. OBJECTIVE . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-1 3. MAINTENANCE PROJECTIONS . . . . . . . . . . . . . . . . . . . . . II-1 4. IMPLEMENTATION . . . . . . . . . . . . . . . . . . . . . . . . . II-1 a. CAS Manuals . . . . . . . . . . . . . . . . . . . . . . . . II-2 b. Frequency of Inspections . . . . . . . . . . . . . . . . . II-2 c. Use of CAIS. . . . . . . . . . . . . . . . . . . . . . . . II-2 d. Quality Assurance . . . . . . . . . . . . . . . . . . . . . II-2 e. Inspector Training . . . . . . . . . . . . . . . . . . . . II-2 f. Formation of Specialized Inspection Teams . . . . . . . . . II-2 g. Data From Other Inspection Systems . . . . . . . . . . . . II-3 h. Facility Information Centralization. . . . . . . . . . . . II-3 5. RESULTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-3 a. Identification of deficiencies . . . . . . . . . . . . . . II-3 b. Identification of repairs . . . . . . . . . . . . . . . . . II-3 c. Identification of technical or functional deficiencies . . II-3 d. Identification of technical or functional deficiencies . . II-3

Section 8

CHAPTER III - SITE CAMP REPORT 1. INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . III-1 2. KEY ELEMENTS . . . . . . . . . . . . . . . . . . . . . . . . . . III-1 a. Basic Guidance . . . . . . . . . . . . . . . . . . . . . . III-1 b. Functional Units (FUs) . . . . . . . . . . . . . . . . . . III-2 Figure III-1 Summary Functional Unit Coding III-3 Figure III-2 Summary Functional Unit Breakdown Structure . . . . . . . . . . . III-4 c. Life-Cycle Plans . . . . . . . . . . . . . . . . . . . . . III-5 d. Functional Unit Level Analysis. . . . . . . . . . . . . . . III-5 e. Identification of Projects . . . . . . . . . . . . . . . . III-6 f. Maintenance Plan . . . . . . . . . . . . . . . . . . . . . III-7 g. Project Prioritization . . . . . . . . . . . . . . . . . . III-8 h. Functional Unit Data Sheet . . . . . . . . . . . . . . . . III-8 3. RESULTS. . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-8 a. The Site CAMP Report provides a site perspective summary . III-8 b. The Site CAMP Report . . . . . . . . . . . . . . . . . . . III-8 CHAPTER IV - CAPITAL ASSET MANAGEMENT PROCESS PRIORITIZATION 1. INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . IV-1 2. BACKGROUND . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-1 a. Development Basis . . . . . . . . . . . . . . . . . . . . . IV-1 b. Universality . . . . . . . . . . . . . . . . . . . . . . . IV-1 ii DOE 4320.2A 2-10-94 3. APPROACH . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-1 a. Steps . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-2 b. Severity Rating Scale . . . . . . . . . . . . . . . . . . . IV-2 c. Benchmark Criteria . . . . . . . . . . . . . . . . . . . . IV-2 d. Sample . . . . . . . . . . . . . . . . . . . . . . . . . . IV-2 e. Initial Ranking . . . . . . . . . . . . . . . . . . . . . . IV-2 f. Final Ranking . . . . . . . . . . . . . . . . . . . . . . . IV-2 Attachment IV-1 CATEGORY/SUBCATEGORY BENCHMARK CRITERIA . IV-5 Attachment IV-2 PROBABILITY AND FREQUENCY LANGUAGE . . . . IV-11 Attachment IV-3 SAMPLE OF PROBLEM RATING, SCORING, AND RANKING . . . . . . . . . . . . . . . IV-13 INDEX . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . i DOE 4320.2A I-1 2-10-94 CHAPTER I ELEMENTS OF THE CAPITAL ASSET MANAGEMENT PROCESS 1. INTRODUCTION. CAMP is a credible, consistent, auditable, and technically sound process for the Department to forecast, plan, and prioritize requirements for assets. CAMP provides an objective, rational basis for allocating budgeted resources for maintenance, repair, modification, reuse, and eventual replacement of assets required to meet site missions. CAMP is an effective and efficient mechanism that ensures compliance with applicable laws, regulations, and standards. The following paragraphs discuss each of the key elements of CAMP in a general, chronological order. A flow diagram illustrating the annual CAMP cycle is shown on Attachment I-1. 2. PROCESS ELEMENTS. CAMP is an integrated process and requires the performance of each of the following elements: a. Assign Capital Assets. Assign each asset to an appropriate functional unit (FU). No asset may be assigned to more than one FU. The FU is the reporting level used by the Department in CAMP. This allows comparison of assets on a Departmentwide basis. Appropriate Secretarial Officers and sites may manage at levels other than FUs as desired. (See Chapter III.)

Section 9

b. Receive Headquarter's Guidance. Heads of Headquarters Elements send multiyear strategic mission statements and program direction and guidance to the field at least annually. Additional guidance will also be provided in the annual CAMP Call. The CAMP Site Report shall incorporate this guidance. (See Chapter III.) c. Develop Life-Cycle Plans. As appropriate, develop LCPs for assets based on life-cycle requirements to meet missions and prioritize projects to meet those requirements. These LCPs become part of the justification for the new projects. (See Chapter III.) d. Identify Deficiencies/Requirements. The Condition Assessment Survey (CAS) identifies site asset deficiencies. CAS is also used as a tool to help meet the facilities inspection requirements of DOE 4330.4B, MAINTENANCE MANAGEMENT PROGRAM. The data captured from CAS is directly read into the Condition Assessment Information System (CAIS). e. Evaluate Alternatives. Develop and evaluate alternatives for meeting the identified requirements. Alternatives may include, but are not limited to, maintenance, repair, modification, reuse, or replacement of existing assets, or construction of new assets. (See Chapter III.) I-2 DOE 4320.2A 2-10-94 f. Identify Projects. If the preferred alternative is identified as a project, develop rationale, scope, cost, and schedule. g. Prioritize Projects. Prioritize the projects by ranking scores to ensure the most cost-effective application of limited resources to meet the most critical needs. Sites shall validate, compare, and normalize initial project rating scores across the entire site without respect to the source or availability of funding. (See Chapter IV.) h. Prepare Site CAMP Report. Prepare the Site CAMP Report in accordance with the format and schedule provided in the CAMP Call. The Site CAMP Reports support budget requests but are not budget documents in and of themselves. DOE 4320.2A 2-10-94 Attachment I-1 Page I-3 (and I-4) CAMP ANNUAL CYCLE OF EVENTS Jan Feb Mar Apr May Jun Jul Aug Sept Ott Nov Dec IFM t * Field Off —+ — — — — —ti & oMB I I * NOTE:Secretarial Offlcersmayksue internalCAMPcalls onadflerentschedule. DOE 4320.2A II-1 2-10-94 CHAPTER II CONDITION ASSESSMENT SURVEY 1. INTRODUCTION. The Condition Assessment Survey (CAS) is a systematic inspection process to determine asset conditions. This Chapter provides general information on CAS and the basic method for implementing CAS throughout the Department. The relationship to the Site CAMP Report is discussed in detail in Chapter III of this Order. Programmatic objectives of DOE 4330.4B, MAINTENANCE MANAGEMENT PROGRAM, call for facility condition inspections and Condition Assessment Surveys. CAS shall be performed within the context of this Chapter. 2. OBJECTIVE. The primary objective of CAS is to assist all DOE sites in assessing the condition of their assets. CAS is based on a set of consensus standards, methods, and technologies to conduct the surveys and to collect and disseminate the survey and inspection information. The information is assembled in a database (the Condition Assessment Information System (CAIS)) that provides basic information necessary for the maintenance and asset management programs. CAIS data is also used to compile the Site CAMP Report.

Section 10

3. MAINTENANCE PROJECTIONS. Appropriate levels of maintenance can be projected for assets nearing the end of their useful lives. The identification of assets projected for disposal can trigger requests for planning support and design funding for replacement. Managers can use CAIS to project current deficiency data into the future. CAIS can assist in developing annual funding profiles for maintenance, repair, rehabilitation, or replacement of assets. 4. IMPLEMENTATION. The effective implementation of CAS depends on the following: The systematic application of consistent standards for inspection, Proper use of a graded approach agreed to by the specific site Operations Office and the appropriate Management and Operating (M&O) contractors, The formation and training of inspection teams, The application of quality assurance procedures, The use of a flexible database, and The exercise of consistent management oversight. II-2 DOE 4320.2A 2-10-94 The following paragraphs outline DOE's approach to the implementation of CAS through the CAS Manuals: a. CAS Manuals. The CAS Manuals contain detailed information for field implementation of CAS. These Manuals provide a foundation for checklists and other information in CAIS to assist field inspectors in determining the condition of existing assets relative to industry standards. CAS manuals delineate standards and procedures for CAS inspection. They are designed to ensure that one site does not determine an asset as deficient when another site declares a like asset with similar problems as adequate. CAS standards and procedures shall be periodically updated in accordance with DOE 1300.2A, DEPARTMENT OF ENERGY STANDARDS PROGRAM. CAS Manuals may be augmented with such documents as DOE 6430.1A, GENERAL DESIGN CRITERIA, current OSHA and environmental regulations, specialized industry standards such as those defined by the Institute of Nuclear Power Operations, standards published by nationally recognized professional organizations, etc. b. Frequency of Inspections. The CAS Manuals recommend frequency of inspections by type of asset. c. Use of CAIS. The implementation of CAS requires the use of CAIS, database management software designed to store and manipulate basic levels of inspection data. The Associate Deputy Secretary for Field Management supports and maintains CAIS. d. Quality Assurance. CAS incorporates a quality assurance (QA) program to certify the credibility of the CAS process, and to ensure that routine inspections are performed by site personnel that reflect current standards and procedures. The Associate Deputy Secretary for Field Management shall maintain a QA program for CAS. The standards and procedures used shall be periodically evaluated against state-of- the-art engineering practice, procedures, and requirements to determine both the accuracy and applicability of the Department's CAS process. e. Inspector Training. The inspectors shall be trained in the use of DOE standards and procedures for developing consistent and accurate inspection results, and the use of special tools, equipment and software. f. Formation of Specialized Inspection Teams. Certain assets unique to DOE may require highly specialized techniques and equipment to perform periodic inspections. To minimize the cost of these anticipated frequent inspections, DOE may establish teams of specialists to inspect these assets at DOE sites. Variables that may affect the decision to use such teams include, but are not limited to, the following examples:

Section 11

(1) Nuclear facility versus non-nuclear facility. (2) The safety significance of nuclear facility systems. (3) Active facility versus partially active or inactive facility. (4) Short-term versus long-term facility mission. (5) Modernization or Decontamination and Decommissioning plans. (6) Lack of CAS standards. g. Data From Other Inspection Systems. CAIS should be used to incorporate the results of other specialized inspection programs that may contribute to the identification of asset related deficiencies. Some DOE 4320.2A II-3 (and II-4) 2-10-94 examples are: OSHA inspections, preventive maintenance program findings, safety reviews, etc. h. Facility Information Centralization. CAIS is recommended as a central repository for facility information at the sites. 5. RESULTS. A systematically applied CAS assesses the condition of assets and their remaining useful life. CAS facilitates time-phased budgeting of maintenance, repair, rehabilitation, or replacement. CAS produces the following results: a. Identification of deficiencies found during the CAS inspection process that are classified as requiring recurring maintenance and that require the use of annually appropriated operating funds to correct. b. Identification of repairs that require the use of operating or line item funds to correct. c. Identification of technical or functional deficiencies for which maintenance or repair is not an acceptable solution, and therefore requiring modification, expansion, rehabilitation, improvement, etc., normally considered to be capital improvements to correct. d. Identification of technical or functional deficiencies that require the complete replacement of the asset using General Plant Projects (GPP), Capital Equipment (CE), or Line Item (LI) funds, etc. DOE 4320.2A III-1 2-10-94 CHAPTER III SITE CAMP REPORT 1. INTRODUCTION. This chapter provides information and direction for the preparation of Site CAMP Reports. The Site CAMP Report provides consistent asset planning information from a comprehensive assessment of the condition of the site's assets. In addition, the Report provides a comprehensive assessment of the functional unit analysis of life-cycle plans to support asset funding requirements. In general, the Site CAMP Report provides DOE with a contractor's best estimate for projects, functional unit analysis of life-cycle plans, and a summary of the maintenance plans. The Site CAMP Report also summarizes maintenance and maintenance backlog issues at each site and helps to ensure repairs, rehabilitation, and replacement needs are identified, planned, and coordinated with other DOE facility-related initiatives and processes. Finally, the Site CAMP Report summarizes and documents the categories for project prioritization rating, i.e., health and safety, environment/waste management, safeguards and security, and programmatic projects and activities. (See Chapter IV for more details.) The Site CAMP Report supports budget requests but is not a budget document in and of itself. The CAMP Call will contain additional guidance for the Site CAMP Report as necessary. 2. KEY ELEMENTS. Key elements in the preparation of the Site CAMP Report are described below. The specific format of the Site CAMP Report is delivered in the annual CAMP Call and is supported by additional guidance developed by the CAMP Planning and Analysis Group (i.e., the CAMP Handbook).

Section 12

a. Basic Guidance. Program direction derived from Headquarters multiyear and strategic planning guidance will be updated and issued annually by Heads of Headquarters Elements in time for the preparation of the Site CAMP Report. Each site shall submit a single report covering all assets of the site. The following guidance shall be used when preparing a Site CAMP Report: (1) Assume that funding will be provided for maintenance, preservation, and projects essential for worker and public health and safety, satisfy Environment, Safety and Health (ES&H) requirements, satisfy Safeguards & Security (S&S) requirements, and meet mission requirements. Funding for activities that enhance or improve capabilities, but which are not essential for mission performance, may be provided on an available basis. (2) Assume that the expected useful life of assets will be realized through reduction of the maintenance backlog, the application of appropriate elements of the maintenance programs, and the repair, replacement, and rehabilitation of assets as required. An asset's remaining useful life should be evaluated at a time interval that precludes unanticipated failures that necessitate the wholesale replacement of an asset. (3) Assume that all applicable laws, regulations, and Departmental requirements will be met as a precondition of operations. (4) The Site CAMP Report shall be prepared in accordance with a CAMP Call issued annually and updated to reflect the Department's strategic planning guidance. The CAMP Call provides specific instruction and typically contains the following: Report format, III-2 DOE 4320.2A 2-10-94 Schedules for submission, Significant project reporting guidance, Prioritization guidance, FUDS format, Appropriate software, Life-cycle planning guidance, Program specific guidance, and Planning horizon. (5) The Site CAMP Report shall contain sitewide strategies to address common asset needs such as office buildings, training centers, roads, and basic infrastructure requirements. Significant differences between the present submission and the previous submission shall be addressed. (6) The CAMP Administrator provides additional guidance as needed. b. Functional Units (FUs). The assembly of assets into FUs in the CAMP Report is required to provide comparability across all DOE sites. The 30 FU codes listed in Figure III-1 shall be used for the Site CAMP Report. While assembly, analysis, planning, and reporting by FU is required for the Site CAMP Report, other planning units may be used by the sites to manage their facilities. FU assignments shall be capable of being reviewed to assure consistency with DOE guidelines. The FU Breakdown Structure (FUBS) provides a method for identifying the site's FUs and establishing a framework for reporting on the Department's assets by FU. The flexibility of the FUBS allows several levels for reporting, depending on the complexity of the site and the management requirements. A more detailed FUBS (see Figure III-2) provides a method for identifying the site's FUs and establishes a framework for identifying the site's FUs in a hierarchical structure. The third level is the level at which CAMP reporting normally occurs. Site personnel shall define the site's FU levels based on their operational needs and their need to identify and track planning at a particular level of detail. The guidance concerning preparation and format of the FUBS is contained in the additional materials provided by the CAMP Administrator.

Section 13

REPORTING LEVEL (3) LEVEL 3 CODE* BUILDINGS Administrative Code 10 Housing Code 11 Storage Code 12 Production Code 13 Service Code 14 Research & Development Code 15 Reactor and Accelerator Code 16 Other Code 29 STRUCTURES/UTILITIES Transportation Systems Code 30 Other Known Assets Code 31 Research & Development Code 32 DOE 4320.2A III-3 2-10-94 Storage Code 33 Industrial/Production/Process Code 34 Service Structures Code 35 Communication Type Systems Code 36 Distribution Systems Code 37 Reactor and Accelerator Code 38 EQUIPMENT Heavy Mobile Equipment Code 50 Hospital & Medical Equipment Code 51 Laboratory Equipment Code 52 Motor Vehicles and Aircraft Code 53 Office Furniture and Equipment Code 54 Process Equipment Code 55 Railroad Rolling Stock Code 56 Reactors and Accelerators Code 57 Security and Protection Equipment Code 58 Shop Equipment Code 59 Automatic Data Processing Equipment & Software Code 60 Portable Communications Electronic Equipment Code 61 Miscellaneous Equipment Code 79 * FUs may be at reporting level (3) or below. Figure III-1 Summary Functional Unit Coding III-4 DOE 4320.2A 2-10-94 Level 1, Site Site XXXXX (5-digit installation ZIP code) Level 2 Area 1 YYY (Program or Funding Category) (Optional) Area 2 ZZZ Level 3, Functional Unit Buildings Structures & Utilities Equipment Administrative 10 Transportation Systems 30 Heavy Mobile Equipment 50 Housing 11 Misc. 31 Hospital/Med. 51 Storage 12 R&D 32 Laboratory 52 Production 13 Storage 33 Vehicles & Aircraft 53 Service 14 Industrial/ Production/ Process 34 Office Furniture & Equipment 54 R&D 15 Service 35 Process 55 Reactor & Accelerator 16 Communication Type Systems 36 Railroad Rolling Stock 56 Other 29 Distribution Systems 37 Reactors & Accelerators 57 Notes: 1. List all assets in each FU. 2. No asset may be listed in more than 1 FU. Reactor & Accelerator 38 Security 58 Shop 59 ADP 60 Portable Comm. 61 Misc. 79 Level 4 - 6, Subordinate FUs As Needed & Defined by the Site (Optional) Figure III-2 Summary Functional Unit Breakdown Structure DOE 4320.2A III-5 2-10-94 c. Life-Cycle Plans. The Site CAMP Report requires an FU Level Analysis of LCPs. LCPs show forecasted major activities throughout the life of an asset, its maintenance and associated projects (LI, CE, GPP). An alternatives analysis for facilities, major equipment, and infrastructure requirements is performed. The LCP provides an overview of a specific asset and an assessment of the activities and resources needed to sustain it over its mission or asset life. LCPs contain a summary of all relevant costs. d. Functional Unit Level Analysis. An FU level analysis contains the following elements: (1) Planning Basis. The planning basis is a discussion that justifies the need and describes the life-cycle mission for the FU and its importance to the overall DOE operation. The planning basis shall also include any information necessary to explain proposed upgrade and improvement projects, a short analysis of recommended maintenance actions, and an overall assessment of the FU's material condition and its suitability for service or any resulting operational limitations. The planning basis shall be prepared by experts outside the site organization to objectively analyze and understand the proposed maintenance and capital investment requirements for the FU. The planning basis for the FU must contain, as appropriate, a discussion of the following factors: Mission.

Section 14

Relationship to other FUs, organizational, site, legal, regulatory, or other changes. Material condition and expected remaining useful life based on applicable CAIS information. Key activities and upgrades to achieve useful life projections. ES&H and S&S upgrades. Standby, transition surveillance and maintenance, or decontamination and decommissioning (D&D) activities. (2) Description of Activities. The description of activities is a concise, narrative discussion of each of the activities identified in the planning basis (see paragraph 2d(1), above). The narratives of the activities shall be provided in chronological order. Information contained in the narratives shall include explanations of factors listed in the planning basis that influence a given activity. III-6 DOE 4320.2A 2-10-94 (3) Maintenance Issues. This element consists of a summary of the maintenance issues specific to the FU. Pertinent issues to be considered include the following: Significant preventive, corrective, and emergency maintenance activities. Maintenance backlog and any actions planned to reduce the maintenance backlog. Special or unusual funding requirements. Other maintenance program concerns. e. Identification of Projects. Asset managers shall develop and evaluate alternatives for meeting each FU's requirements defined in its respective LCP or Functional Unit Level Analysis (See paragraph 2d, above). When the preferred alternatives are identified as projects, they shall include adequate scope, cost, and schedule information to allow prioritization in accordance with Chapter IV of this Order. Note the broad definition of projects in Attachment 1 of this Order. (1) Cutoff Level for Reporting of Projects. All significant projects that can reasonably be forecast for the life of an FU shall be reported. For CAMP, the following parameters shall be considered in determining whether or not a project is significant: The magnitude of the cost of a project. The cost of the project relative to the replacement plant value of the asset or FU involved. The impact of the project on the function of the asset or FU. For example, a relatively low cost project that is critical to continued operation may need to be reported, particularly if it will require an outage to accomplish. The priority of the project as determined by the method described in Chapter IV of this Order. (2) Project Constraints. Project packaging (i.e., electrical deficiencies in several buildings of the same FU) is a tool that may be used to manage the correction of large numbers of deficiencies. It is also important that project schedules be critically examined and coordinated to avoid large, unmanageable "mortgage" requirements or large year-to-year variances in out- year funding requirements, that projects be executed on the most economical schedule, and that costs be realistic. Projects that are presented as "buy-ins" (low first-year costs with disproportionate out-year costs) or that have artificially extended and, consequently, less than optimum schedules are unacceptable. Judgment of the responsible site personnel is the essential ingredient in assuring compliance with these project constraints. Appropriate Secretarial Officers shall exercise oversight of projects. f. Maintenance Plan. A highlight summary of the maintenance plans produced in compliance with DOE 4330.4B, MAINTENANCE MANAGEMENT PROGRAM.

Section 15

g. Project Prioritization. A prioritized listing as appropriate of the site's projects, derived from the method discussed in Chapter IV of DOE 4320.2A III-7 (and III-8) 2-10-94 this Order. The CAMP prioritization system is the only authorized system for rating and ranking DOE assets. h. Functional Unit Data Sheet. The Functional Unit Data Sheet (FUDS) is a summary document containing the relevant data for a significant project in the life of a particular FU. 3. RESULTS. a. The Site CAMP Report provides a site perspective summary of the condition of existing assets as related to the mission of the site. b. The Site CAMP Report, submitted to the Heads of Field Elements, represents the contractor's notification to DOE of the requirements for assets. DOE 4320.2A IV-1 2-10-94 CHAPTER IV CAPITAL ASSET MANAGEMENT PROCESS PRIORITIZATION 1. INTRODUCTION. Consistency throughout the Department in the prioritization, preparation, and submission of asset management resource requirements is a key element of the Capital Asset Management Process (CAMP). To achieve the desired consistency, all sites shall adopt the CAMP prioritization process discussed in this Chapter. The prioritization process is designed to rate and rank each project. The priority lists shall be updated annually. This process shall be used as a tool to help prioritize projects on a sitewide, Field, and Headquarters (HQ) level. 2. BACKGROUND. The CAMP prioritization process is a systematic, structured, and consistent method for determining the preferred order for allocating limited resources to solve problems. This process prioritizes the problems (events, conditions, situations, requirements, etc.) that projects are intended to address. Other methods and techniques are used to assess the appropriateness or readiness of a project; examples are: value engineering, justification reviews, and project validations. For the purposes of this chapter, problems and projects can be thought of as interchangeable in the prioritization process. a. Development Basis. The CAMP prioritization process was developed on the basis of risk management and reflects the values and culture of the Department. The prioritization criteria consist of the two elements of risk--consequence and probability. They are combined in the criteria statements and are influenced by the terminology and expressions commonly used by the people who work with the various rating criteria categories. The scores represent the risk-consequence and probability of occurrence based on the descriptions under each rating criteria. The rating criteria were developed and positioned based on Departmental intentions and public expectations, appropriate standard industrial practices, and represent the desired level of operational conduct (see Attachment IV-1). b. Universality. The CAMP prioritization process is universal, encompassing four major categories: (1) health and safety; (2) environment/waste management; (3) safeguards and security; and (4) programmatic. The process provides for expansion, change, and improvements. Further, it can easily accommodate ratings derived from other prioritization systems, as long as the ratings reflect the same values and culture. The rating criteria and scoring process are contained in the Attachments to this Chapter and shall be maintained by HQ. Any changes to the prioritization process will be transmitted with the annual CAMP Call.

Section 16

3. APPROACH. The problem-rating criteria within each of the four major categories and their subcategories are aligned along a scoring scale so that they represent the same severity or priority. Therefore, any rating score in one category or subcategory represents the same problem severity as the same numerical rating score in any other category. This alignment of criteria is crucial to achieve an equivalent, integrated ranking between dissimilar problems or projects. a. Steps. The CAMP prioritization process consists of four steps: (1) rating; (2) scoring; (3) initial ranking; and (4) final ranking. It is vital that bias be minimized. To this end, ratings are normalized in each step of the consolidation review process (i.e., from facility, to site, to Operations Office, to HQ Program Office). This ensures consistency, equitable application of ratings, and fair and IV-2 DOE 4320.2A 2-10-94 accurate comparisons and rankings. The process for developing a total score for each problem/project gives greatest emphasis to the most severe rating, but also recognizes that some problems have multiple dimensions. The process therefore should duly reflect their contributions. b. Severity Rating Scale. The problem severity ratings span a scale from 20 to 80. The scale could have been infinite, but the two ends were collapsed for ease of use. c. Benchmark Criteria. To assist in assigning major category ratings, benchmark criteria are given for a number of subcategories under each major category. Subcategory benchmark criteria are shown in Attachment IV-1. The subcategories enable project sponsors to rate problems with reference to specific technical and managerial benchmarks, as a guide to accurate rating. The probability and frequency languages used in the benchmark rating criteria for all four major categories and their respective subcategories are outlined in Attachment IV-2. d. Sample. A sample of an application of the rating and ranking process is presented in Attachment IV-3. e. Initial Ranking. Rank initially in descending order according to total rating score. The highest rating score, therefore, is the highest ranked priority. (Note: As previously stated, the benchmarks are defined so that a numeric rating on any scale denotes problem severity equal to the severity of the same numeric rating on any other scale.) For instance, a problem rating of 52 in the Programmatic Category is as important as a problem rating of 52 on the Health & Safety Category, by design. However, where two or more problems have identical overall problem ratings, their initial rankings shall be determined through a tie breaker by giving priority to each major category in the following order: Health & Safety; Environment/Waste Management; Safeguards and Security; and Programmatic. f. Final Ranking. (1) Projects proposed to address the prioritized problems for out- years are seldom thoroughly defined at the time the 5-year plan is prepared and are best ranked according to the severity ratings of the problems they are to address. Once CDRs are completed, project cost, scope, and results are better defined. Nevertheless, projects should continue to be ranked primarily according to problem severity throughout the planning period. Management review of the initial ranking is important to ensure all considerations are reflected in the final ranking. Techniques such as pair-wise comparisons are useful. Supplemental information to adjust rankings may include cost, problem improvement or severity reduction (rating reduction effected by the project), scope, readiness of a project, etc. Whether and how supplemental information modifies an installation's initial ranking is left to local discretion.

Section 17

(2) Rankings may be done for all the problems/projects in the 5-year planning period and then organized into individual fiscal year rankings or ranked initially by year. Because of budget formulation considerations (e.g., funding limitations, project readiness, consolidation of like projects, etc.), actual project budget submissions could result in modifying the order of the yearly rankings. DOE 4320.2A Attachment IV-1 2-10-94 Page IV-5 CATEGORY/SUBCATEGORY BENCHMARK CRITERIA Major Category Rating Criteria Score I. Health & Safety II. Environment III. Safeguards & Security IV. Programmatic 10 Acceptable risk; minor incidents unlikely In compliance; working towards ALARA Minor problems unlikely Minor problems unlikely 20 Minor incidents slightly likely Consistently in compliance; violations extremely unlikely Routinely secure with acceptable risk Adequate with acceptable risk 30 Minor incidents moderately likely; serious incidents unlikely Routinely in compliance; low-impact violations are the exception; no offsite concern Routinely secure with some minor problems Adequate with some minor problems 40 Minor incidents moderately likely; serious incidents slightly likely Occasional violations of moderate consequence Modest threat to classified information, technology, and parts (moderately likely) Adequacy in question with many minor problems 50 Minor incidents likely; serious incidents moderately likely Frequent problems of moderate consequence; occasional serious problems; moderate offsite concern Serious threat to classified information, technology, property, and parts (moderately likely) Mission accomplishment at moderate risk 60 Serious incidents likely; fatalities unlikely Consistently have problems of moderate consequence; frequent serious problems Serious threat to SNM/tritium or personnel (moderately likely) Mission accomplishment at high risk 70 Serious incidents highly likely; fatalities moderately likely Highly likely large and uncontrolled contamination/release to offsite areas with lasting serious environmental impact Extreme threat to SNM or personnel (moderately likely); extreme threat to classified information, technology, property, and parts (highly likely) Critical/strategic mission accomplishment severely impacted or shut down 80 Highly likely life- threatening situation Extreme threat to SNM or personnel (highly likely) . . . HEALTH~~&”’;SAFETy RATING CRITERIA suBcATEGo~IEs;:.;!,., ‘!, . , , . .;:.::;, Y+x::, : : .:-*;:e No concerns No exposure to Event . f. . 20. In compliance, No:tO~~ti&y {~Ae;rfo;. . ; +’: but upcoming -;<; $,: problems Y --- ..= I - - - ““..”*.M, Propert l o s s Y Oev{atlon - upccqj~ actbl Pr or!ty 4 llmlt ex$sure X!slonal extr~ y -“ ~!Mghtly Iof mission a n d ‘“ I minor change . - poss &Tll* standnrd-minor unllkely or of trlv~al value fran approved cond{t!ons or,.ic{dent$ ! o f ~uccess’and/or ‘ -” procedures high risk (Category 1) -.30 Consistent ly Some min?r in ccxplimce concer- - Meet inn c+nnA9w.4 “oderate Infraction - “ ~-- w i th recaum ,,,””.3., l-l =x sure to thesignlficant. . . . “: ~ca3&A..* .-...-. protection, Pu I!c sli htly change fras. . ‘: ‘- minor __ Jectives~s. o p e r a t i o n s - ! ~{~~ a~~ptable ikely (1. !~.. deviat ion. . exposure “ approved REM/yr);. . . at/belou conditions or prop&rty losses exposure to. -..: standards expected procedures but workers up to 1 no realistic- --- . REII!/yr;

Section 18

.- :- ~“ wa to cause a ~~fately YC:a:c::!t 4(3:; ~;~ue&inor Many minor p,Tiger Teal Y Y!) Pr*vcnt ana{n.t Minor injuries Event, with.1 .-....:~L$”- concerns/ Event with ‘q reccxnnendati on: - teed goals minor injury. ,. > :.s~ - ----- ation of.5 Y;* I probabi l i ty I I f ca abi l i ty and - 1 ikely .- -,--- ? I exposure approximately .:.%% .=+ ef iciencv: *tanrtaed* nRIW 1 0 -8 * Inational-obj&ives; Ilofig-te~orobabilitv ‘- ” - - - ‘--’7--’--II;; P msl -mdat ions Elulla I ● I I IreOevelop neu approaches, techniques, and thoch to improve l!%%%i$~f~~~~ ‘i’’:::’”-’ ‘ IOevelopneumetMs - - - - - - - - rlorityi? 7 to i rovelenhance -=-’’’-’l:; $1 heal%ti safety fre Ucnt 1Vio 1 II IS&2?t:$ I I lntennedi~te --=----- “- “,, ,J 3$?-, ..? throu h probabtlityof ?adnin strative I I--. .-. r.* success andlor 10U controls risk IOevelop neu methods rlorltyt? ~;n :en+ Y n4nn* 4-4,,.4-*1 t o imorove/enhance L ---I “ “50 -?L Frequently h ~~e:~:~lf Icant l~!--- ‘-- “$F ~e:k-’ ccunpllance, ,:$:%=+. but serf~~ ><;p-g~ violations recomn--- ,W,., Vfolationof I I ! ncalcn m salel:” I exposure ..? :~~ Ucasional ly Internal I occasional I l i k e l y ; - g abi l i t ies and standards - no serious Standard \:k:?-f%i~i-,-. .; &,f%J occur stands .- 1 lclencv: snort- ! controls I injuries I industrial . . . ., , . -. . ava{lahla REH/yr): high protection: exoosure t o 1 krtls; I I term protibilit” -of _ _ _ _ _ II ::**;& I I Hs u c c e s s andlor CM I,, . . . . --- . . .— z-. . . Ioccasional” un;k-m ‘- n II “’ I I I 9 ,Sm bP4n41* IM””~”-df~s ‘- - - - “ I I I {ii~;~ \cant ;Xpsure ‘o the - continuation of u lic sli htlyactlvity would pro~rty losses {kely ( 5 - ? 0 0 $ign\ficantly-A., - - “EWyr); worker increase I exposure above pro“A”.,1.b---- --, Se. ___ I-!011U9 b= violatbns and sch frquent, o r due to signifl ;%lnuing problem minor deviat’ suspens ) I ISA PrlOrity 2 Oevelop n e c e s s a r y k I PotentialI thods, processesa suhstanti~l in4118.4A. . . . . . . and techniques in I i ------ . . - . “ , Idanger to site ~&{~~~ I Y sup rt o f - c r i t i c a l hea th 6 safetv R:%%:e’ F I I -. ..--= . . object ives; sh6rt- 1 I IWULIIIC exoastiret n**r- nc Clons t e r m probabilit o f tc - . X Ion T Isuccess and/or w reauirtid ‘“” I I I CyU laLU1 z14.n4** 11 -1.. Grltlc I*---- ~---.-, ----- trm action Ishutckm penamg ac possible risk Ser ious, life- threatenlng TSA P r i o r i t y I iolations Ti er Team 1 !Prority 1 ianger on site 1’ erson P#$’l); ata!j~iei I . I 1 1 lllllLa !!RCIT IULN (5-10 REM/yr~ ,. __-= ubstant~al F a t a l i t i e s F a t a l i t i e s r to Hoderate =.,..,.,.possible possible ex Osure to the~~~,Lt946.. me 1. !ntl l{e Ilk-l” I I Ipass ltI Ie Issured I I ‘ _25:~:YlicalitYor I Q Hi hly l i k e l y lli?e- Hi hly l i k e l y Hi t threatenhg [ li?e- 1 i?e- situation thr *IW 0lllte- 1 tft=- .fi* r 1 p =fiyg ““‘ ., -”. threatening c r i t i c a l i t y situat ion (Categories 4 I — . . . . . I I I J . ..+‘~EMANAGEMENTm: i.:x!:.l.$ :::: Oort Rqulatory lteet’:?tene qllancxl No concerns No concerns No concerns 250.> ~~s Istent ly !io Intervention Ti er Team Develo n e w 7 Y Effective Consistently at present, but Pr ortty 4 techno og tn f transport /. . meets canpltance, upcan!ng *ctlon support o mission $ but upccsning possible storage; requirements and national treatment “-.” problems 1-. object ives; long- discharge . . Posstble

Section 19

I tem probab{ltt o f meets isuccess andlor lgh requirements 3 0 lConslstently Scsm minor Develop new Dccastonal i-in concerns/ approaches, discharge c T 1 lance, recanmdatfons techniques and exceeding ..- Wlt methodologies to materfal -“;::. y;ional hprove operations goals ,“, _devlattons 4 0 - Frrrent Many mtnor Ti er Team Develop new 1 Occasional Occasional concerns/ Pror!ty 3 methodologies to v{olatlon of Inadequac _. vlolattons: . recamnenda- improve/enhance dk~~rge {o f permtt ed. heal th & safety stora el; : ::;;!+1:% capab~llttes and ?~. .= handl ng; . - concernsl efftcienctes; tran:;port/ :“ recanrmdatlons {ntermedtate packdg!ng/ . . probabilltyof dtsposal success andlor caoac!tv medfm rtsk . ~~:equently V i o l a t i o n of Ti er Team Develop new ? Many or system contractor Pr ority 2 methodologies to immediate capacit -. compliance, standards; imrove/enhance vlolat{ons {freauen lY I inadequate~:. but-ser ious contractor .. violat~ons sumension of o concerns Process generates I m{ninxnn waste ustng best englneertng I I p r a c t i c e - onsfstently Process enerates Oecontam\nat{on and eets 7relattve y l~ttle deccmn{ss!on!ng qu{rements waste (D&D) a t sttes wfth no present @eratives ,, ! m~sstons Process enerates Remedfal urrently !more was e than act\ons/O&D needed ~th{n an eff icient to reduce risk, ennitted process prcmote ccfnpl!ance, evels, but or maintain fnisston lard to continuity ytntain I m!ss!ons \ ‘ ccasionally ‘xceed lerm~tted I evels by a mall amount ~im!ss!ons Process generates Remedial out-of- requently excess!ve waste actions/DbD c Y 1 \ance !xceed required by {n- Wft mnitted force agreements levels, bya requirements, but no signed large amount agreement I IProcess generates Actions requtred as bctions ::;Md;hat part of a signed I required as interagency regulatory l{mfts agreement ;art of a Is{gned I interagency agreement ;misstons sxtreme ly ~igh on Xcasion (not l\ fe- threaten{ng) !mtss!ons Process generates excessive waste such that severe environmental impact !s tnevttable Remedial Act{ons needed I actions/O&O w{th{n 1 ● ar I required to protect to preven { from near-term ::::nficant ,r!sks I P $an erously Rhfg (l{fe-. th;eatenln I SAFEGUARDS & SECURITY RATING CRITERIA SUBCATEGORY= .’ .,, 0ss extremely are and of rfvial value me mall osse$ expected tandard ndustr~al Irotect!on occasional ,ign\f\cant IUss ; frequent ]Inor 10ss )ccas{onal major loss 10 chance for ~ !xposure to kmger ;aft and iecure; nom? i :oncerns 1 $2 z m Cannot m reasonably assure z protection, serious Injury Possfble I ilerrorist Iattack or hosts e ?Isitlja fon l~~ke~ w~th 7Ifatal t!es jmss!ble : :,! .::: . . ::..:, !. :::,:. . .: :. ;; ;, : ; .. . . . . . . . . . . . . 6RAMMATIC RATING CRITERI ‘:” ‘:” I Score j;(;:Comf31 iance+. .. . y,j~ltk?derss ..<. .“:.‘< “‘ .:. . ;:::,.. >.>,,::” . . . :.x. .% . ../ .jjlnitlatlves,;. ‘:,?,. . . . . . ,,. .: . . . . . . . . ● . : :.>.,;,. ::.....:.. a@@itict~ves.. . . . . . . . . . . . . . “~”lQfi. Exceeds requiruxsnts.: . . I I 20+ llncompl{ance, but MO lntervent~on -- upcaning problems at pre~ent, but .- :: sl~ghtly Ifkely upcom!ng &ction . . . . . possible; IROR~ - .. 20%- . . n 30 fi-lConsistently fn Some fa!nor “ cqliance, with concerns/recmnefi . :--” -.$+.. occasbnal minor datfons: SROR~ ..” deviations< ‘+4’ 50%.? ~ 2: . . . . .40 lRORZ 75%; Sane . •. slgnif!cant.%.. . ..- --+ concernsl<-...

Section 20

;. : .@&- recomnendat~ons 50 -lFrquently In V\olat\on of . . compliance, but {nternal . -:- serlous vlolatiom standards;- .- .- occasfonally occur.-. . suspension of . owrat~ons da{lY: lROR~ 100% - Serious violations Mandated fixes frequent, or many and schedules du~ ‘continuing minor to slgnif!cant deviations: shutdown problems: l{kely possible suspension of operations Dend!na action %-l-- ret known future requirements E!E?” Ei::: ‘ possible )evelop new technology in Process adequate to viable for Able to meet Good - performs to t \upport of mission and r et prograni m{sslon \ational objective; long- requirements, but tennprobabtltty of improvements )uccess and/or h{gh risk warranted )evelop new approaches, techniques, and nethodolog!es to improve >perattons Ission r Develop new methodologies Can meet m{ss{on with Viable for 1A to impiove/enhance - problems ltkely L I !ssion on r nisston capability and schedule with efficiency; intermediate overthne: s probability of success prob lmns i and/or medtum risk rately r likely - Develop neumethodolog~es Canmeetm{sg!on with On schedule u to Wprovelenhance d!ff!culty with s vlss{on capability and significant r efflc~ency; short-term overt ime probabtltty of success and/or 10U rfsk Oevelop necessary Cannot meet mission; Inadequate L methodologies, processes, or unique capability ca~aclty to n and techniques {n support in jeopardy support r of cr~t!cal programmatic minimum objectives; short-term requirements probability of success of mission and/or 10U rtsk Critical/strategic mfssion capab{llty does not ex\st - requirements; or{glnal specs wfth minor rout!ne preventive improvements maintenance; downtime poss(ble does not affect , operat!onfmlsslon , I Able to meet Adequate - meets requirements; m{sslon, but cannot I some perform to all orlgtnal’ significant specs, cm corrective improvements maintenance necessary I -~red to meet Fair - occasional ranents; substandard operat!on; ~ repet{t{ve corrective , ficant nu(ntenance; can nw& vanents m~sslon with minor red problems e to meet Poor - consistent substandard rements performance; operations/n4ss{on threatened e to meet Severely deteriorated; tnlss!on asstgmnent at rements high risk Crlt!cal/strategic fac!lft{es inoperable , 4 DOE 4320.2A Attachment IV-2 2-10-94 Page IV-11 (and IV-12) PROBABILITY AND FREQUENCY LANGUAGE The probability and frequency languages used in the benchmark rating criteria for all four major categories and their respective subcategories have many different terms. The definitions of these terms are subject to different interpretations among the various potential users. To minimize misinterpretation, the probability and frequency languages, along with the respective algorithms, have been standardized. Those standards and their corresponding ranges are shown in the figures below. Standardized Terms Range (Events/Year) Essentially Impossible (<10 8) Extremely Unlikely (10 8 10 6) Unlikely (10 6 10 3) Slightly Likely (0.001 0.01) Possible (0.01 0.1) Moderately Likely (0.1 0.4) Likely (0.4 0.7) Highly Likely (0.7 1.0) Figure IV-1 Probability Language Standardized Terms & Synonyms Frequency Range (Context Dependent) Consistent(ly), continuous, almost always >98% of the time Routine(ly), generally >90% of the time Frequent(ly), often, common 12 to 120 per year Many, numerous 10 to 100 per year Some, several 5 to 50 per year Occasional(ly), few 1 to 10 per year

Section 21

Figure IV-2 Frequency Language DOE 4320.2A Attachment IV-3 2-10-94 Page IV-13 SAMPLE OF PROBLEM RATING, SCORING, AND RANKING 1. PROBLEM. A nitrate recovery system is badly deteriorated, unreliable, less efficient than new technology, and incapable of meeting expected new liquid waste discharge regulations. 2. PROCEDURE. The highest single category rating score is identified. For each of the remaining three major categories, up to 3 points may be added. How many points are added depends on the nearness of the category rating to the highest category rating. Category ratings at or below 20 on the rating scale, or categories not rated, do not contribute to increasing the overall problem score. Category ratings higher than 20 add more points the closer they are to the highest category rating. The default level of 20 represents a satisfactory or adequate rating. a. Rating. (1) First, assign a problem rating for each subcategory determined to be applicable and defensible in any or all of the major categories. This should be based on the projected condition of the problem at the time of correction. For a single subcategory, do this by finding a benchmark on the scale that most nearly describes the problem, then select its corresponding numerical rating score. Interpolations along the scoring scale between rating criteria benchmarks is appropriate. (2) Second, assign a rating for each major category that is defined as the highest single subcategory rating under that major category. Use a default rating of 20 for each major category for which no subcategory rating was initially assigned. EXAMPLE: MAJOR CATEGORY SUBCATEGORY RATING Environmental/Waste Mgmt. Regulatory Compliance 65 Environmental/Waste Mgmt. Liquid Waste 62 Environmental/Waste Mgmt. Waste Minimization 57 Programmatic Physical Condition 53 Programmatic Best Mgmt. Practice 35 b. Assign category ratings. (1) Health and Safety: 20 (default value for unrated categories); (2) Environmental/Waste Management: 65 (highest subcategory rating); (3) Safeguards and Security: 20 (default value for unrated categories); (4) Programmatic: 53 (highest subcategory rating). Attachment IV-3 DOE 4320.2A Page IV-14 2-10-94 3. SCORING. Compute the overall rating score. EXAMPLE: MAJOR CATEGORY RATING CALCULATION POINTS Environmental/Waste Mgmt. (65) 65 = 65 Programmatic (53) 3 x (53-20)/(65-20)= 2.2 Health and Safety (20) 3 x (20-20)/(65-20)= 0* Safeguards & Security (20) 3 x (20-20)/(65-20)= 0* TOTAL = 67.2 *Shortcut Note: Unrated categories will always yield "0" points. 4. RANKING a. Rank initially according to problem rating. Suppose other proposed projects and their ratings are B (54), C (64), and D (68). The initial ranking is D (first priority), A (second priority), C (third priority), and B (last priority). b. Establish final ranking. The final ranking is derived from the initial ranking following management review that considers all possible factors, including problem improvement, problem scope, project cost, and project readiness. DOE 4320.2A i 2-10-94 INDEX addition . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-5, III-1 asset . . 1-6, i, ii, I-1, II-1, II-2, II-3, III-1, III-2, III-4, III-5, III-6, IV-1 assets . . 1-5, 4, i, I-1, II-1, II-2, II-3, III-1, III-2, III-3, III-4, III-7 backlog . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5, III-1, III-6 budget . . . . . . . . . . . . . . . . . . 2, 4, 5, 1, 3, 6, I-2, III-1, IV-3 CAIS . . . . . . . . . . . . . . . . . . 3, 4, i, I-1, II-1, II-2, II-3, III-5 CAMP . . 1-5, 3, 5, 6, i, ii, I-1, I-2, I-3, II-1, III-1, III-2, III-3, III-5,

Section 22

III-6, III-7, IV-1, IV-2 CAMP call . . . . . . . . . . . . . . . . . . 3-5, I-1, I-2, III-1, III-2, IV-1 capital asset . . . . . . . . . . . . . . . . . . . . 1, 3, 4, i, ii, I-1, IV-1 capital asset management process . . . . . . . . . . 1, 3, 4, i, ii, I-1, IV-1 capital equipment . . . . . . . . . . . . . . . . . . . . . . . . . . . 3, II-3 CAS . . . . . . . . . . . . . . . . . . . . . . . 1-4, i, I-1, II-1, II-2, II-3 CDR . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3, 5 CE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3, 5, II-3, III-5 CFO . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3 CFR . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1, 3 condition assessment information system . . . . . . . . . . . . 3, 4, I-1, II-1 condition assessment survey . . . . . . . . . . . . . . . 1, 3, 4, i, I-1, II-1 construction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5, I-1 contractor . . . . . . . . . . . . . . . . . . . . . 1, 3, 4, 2, III-1, III-7 contractors . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1, 5, II-1 D&D . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3, III-5 database . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4, II-1, II-2 decommissioning . . . . . . . . . . . . . . . . . . . . . . . 3, 5, II-3, III-5 deficiencies . . . . . . . . . . . . . . . . . . . . . 4, i, I-1, II-3, III-6 ES&H . . . . . . . . . . . . . . . . . . . . . . . . . . . 2, 3, III-1, III-5 exclusions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 expansion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-3, IV-1 extension . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5 facility . . . . . . . . . . . . . . . 2, 5, i, II-1, II-2, II-3, III-1, IV-2 Field Management . . . . . . . . . . . . . . . . . . . . . . . . 3, 5, 6, II-2 FU . . . . . . . . . . . . . . . . 3-5, I-1, III-2, III-4, III-5, III-6, III-7 FUBS . . . . . . . . . . . . . . . . . . . . . . . . . . 3, 4, III-2, III-3, 3 FUDS . . . . . . . . . . . . . . . . . . . . . . . . . . 3, 5, 6, III-2, III-7 functional unit . . . . . 3-6, i, I-1, III-1, III-3, III-4, III-5, III-6, III-7 functional unit breakdown structure . . . . . . . . . . . . . . . . 3, 4, III-4 functional unit data sheet . . . . . . . . . . . . . . . . . 3, 5, 6, i, III-7 FUs . . . . . . . . . . . . . . . . . . . 4, i, I-1, III-2, III-3, III-4, III-5 general plant projects . . . . . . . . . . . . . . . . . . . . . . . . 1, II-3 GPP . . . . . . . . . . . . . . . . . . . . . . . . . . . 1, 3, 5, II-3, III-5 improve . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3, III-1 improvement . . . . . . . . . . . . . . . . . . . . . II-3, III-5, IV-3, IV-14 improvements . . . . . . . . . . . . . . . . . . . . . . . . . . . II-3, IV-1 inspection . . . . . . . . . . . . . . . . . . . . 4, i, I-1, II-1, II-2, II-3 inspections . . . . . . . . . . . . . . . . . . . . . . . . i, II-1, II-2, II-3 inspectors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-2 laboratory . . . . . . . . . . . . . . . . . . . . . . . . 1, 5, III-3, III-4 LCP . . . . . . . . . . . . . . . . . . . . . . . . . . . 3, 5, 6, III-5, III-6 LCPs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2, I-1, III-5 LI . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-3, III-5 life cycle plan . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3 life-cycle . . . . . . . . . . . . . . . . . . . . 5, 6, i, I-1, III-1, III-5 line item . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-3 maintenance . . . 1, 2, 4, 5, 1, 2, 5, i, I-1, II-1, II-3, III-1, III-5, III-6,

Section 23

III-7 maintenance management . . . . . . . . . . . . . 2, 4, 5, 1, I-1, II-1, III-7 mission . . . . . . . . . . . . 4, 5, 4-6, I-1, II-3, III-1, III-5, III-7, IV-5 modification . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-1, II-3 National Environmental Policy Act . . . . . . . . . . . . . . . . . . . . 1, 3 NEPA . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1, 3, 5 prioritization . . . 1, 2, 4, 6, i, ii, III-1, III-2, III-6, III-7, IV-1, IV-2 prioritize . . . . . . . . . . . . . . . . . . . . . . . 2, i, I-1, I-2, IV-1 project 2, 1, 3-6, i, I-2, II-1, III-1, III-2, III-6, III-7, IV-1, IV-2, IV-3, ii DOE 4320.2A 2-10-94 IV-14 projects . 2, 1, 5, i, I-1, I-2, II-3, III-1, III-5, III-6, III-7, IV-1, IV-2, IV-3, IV-14 property . . . . . . . . . . . . . . . . . . . . . . . . . . 1, 2, 4, 5, IV-5 QA . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-2 quality assurance . . . . . . . . . . . . . . . . . . . . . 3, 2, i, II-1, II-2 ranking . . . . . . . . . . . . . 4-6, ii, I-2, III-7, IV-2, IV-3, IV-13, IV-14 rating . . 4, 5, ii, I-2, III-1, III-7, IV-1, IV-2, IV-3, IV-5, IV-11, IV-13, IV-14 real property . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 repair . . . . . . . . . . . . . . . . . . . . . 1, 5, I-1, II-1, II-3, III-1 replacement . . . . . . . . . . . . . . . . . . . I-1, II-1, II-3, III-1, III-6 reuse . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-1 S&S . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3, III-1, III-5 safeguards and security . . . . . . . . . . . . . . 4, III-1, IV-1, IV-2, IV-13 schedule . . . . . . . . . . . . . . . . . . . . . . . . . . 4, 5, I-2, III-6 Secretarial Officer . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5 shall . . . 1-5, 4, 6, I-1, I-2, II-1, II-2, III-1, III-2, III-5, III-6, III-7, IV-1, IV-2 should . . . . . . . . . . . . . . . . . 5, 6, II-3, III-1, IV-2, IV-3, IV-13 site 2, 4, 5, 1, 4-6, i, ii, I-1, I-2, II-1, II-2, III-1, III-2, III-4, III-5, III-6, III-7, IV-2 Site CAMP Report . . . . 2, 5, 6, i, ii, I-2, II-1, III-1, III-2, III-5, III-7 Site CAMP Reports . . . . . . . . . . . . . . . . . . . . . 2, 4, 5, I-2, III-1 standards . . . . . . . . . . . . . . 2, 1, 2, 4, I-1, II-1, II-2, II-3, IV-11 training . . . . . . . . . . . . . . . . . . . . . . . 3, i, II-1, II-2, III-2 upgrade . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-5