DOE O 430.1 Chg 1, Life Cycle Asset Management
Functional areas: Work Processes
The order addresses stewardship of physical assets as valuable national resources in a cost-effective manner to meet the DOE mission using industry standards, a graded approach, and performance objective.
Supersedes:
DOE O 430.1, Life Cycle Asset Management on Oct 26, 1995
Superseded By:
DOE O 430.1A, Life Cycle Asset Management on Oct 14, 1998
Version history and related documents
Superseded by
A newer version replaces this document.
- DOE O 430.1ALife Cycle Asset Management (Oct 14, 1998)
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
U.S. Department of Energy
Washington, D.C.
DOE O 430.1
SUBJECT: LIFE CYCLE ASSET MANAGEMENT
ORDER
Approved: 08-24-95
Review Date: 08-24-97
Chg 1: 10-26-95
1. OBJECTIVES . The Department of Energy (DOE), in partnership with its
contractors, shall plan, acquire, operate, maintain, and dispose of
physical assets as valuable national resources. Stewardship of these
physical assets shall be accomplished in a cost-effective manner to meet
the DOE mission. This shall incorporate industry standards, a graded
approach, and performance objective.
2. IMPLEMENTATION. This Order shall be implemented on a site-by-site basis
through the establishment, by contract or financial assistance
agreements, of site-specific performance criteria and a performance
measurement system. The existing Orders listed below and already
implemented in current contracts remain in effect until such
incorporation takes place. Additionally, for specific facilities under
the purview of the Defense Nuclear Facilities Safety Board, DOE 4330.46,
MAINTENANCE MANAGEMENT PROGRAM, and DOE 6430.1A, GENERAL DESIGN CRITERIA,
remain in effect until 10 CFR 830.340, MAINTENANCE MANAGEMENT, and D0E O
420, FACILITY SAFETY, for defense nuclear facilities are issued as finals
by the Assistant Secretary for Environment, Safety, and Health. For
sites not managed by a contractor, implementation shall occur when the
responsible DOE organization has completed the development of appropriate
performance measures.
3. CANCELLATION. The following directives are deleted or consolidated into
this Order and shall be phased out as noted in paragraph 2:
DOE 1332.1A UNIFORM REPORTING SYSTEM
DOE 401O.1A VALUE ENGINEERING
DOE 4300.1C REAL PROPERTY MANAGEMENT
DOE 4320.16 SITE DEVELOPMENT PLANNING
DOE 4320.2A CAPITAL ASSET MANAGEMENT PROCESS
DOE 4330.4B MAINTENANCE MANAGEMENT PROGRAM
DOE 4330.5 SURPLUS FACILITY TRANSFER
DOE 4540.1C UTILITY ACQUISITION AND MANAGEMENT
DOE 4700.1 PROJECT MANAGEMENT SYSTEM
DOE 4700.3 GENERAL PLANT PROJECTS
DOE 4700.4 PROJECT MANAGER CERTIFICATION
DOE 5700.2D COST ESTIMATING , ANALYSIS, AND STANDARDIZATION
DOE 6430.1A GENERAL DESIGN CRITERIA
Vertical line denotes change.
DISTRIBUTION,
All Departmental Elements
INITIATED BY:
Office of Field Management.
CANCELE
D
DOE O 430.1
8-24-95
2
4.
5.
6.
APPLICABILITY. This Order applies to all DOE elements except the Naval
Reactors/Naval Nuclear Propulsion Program. This Order does not preclude
issuance of program directions unrelated to asset management systems.
While this Order applies to al 1 the physical assets in DOE, there are
additional requirements for special and nuclear facilities that are the
responsibility of the Assistant Secretary for Environment, Safety, and
Health to develop and maintain.
DEFINITIONS. See Attachment 1.
REQUIREMENTS .
a. DOE elements shall use a value-added, quality driven, graded
approach to life-cycle asset management.
b. Every site shall be supported by a Headquarters program office that
functions as the landlord. Landlords shall coordinate their
facilities management activities to provide a consistent corporate
approach to facilities management, especially at multi-program
sites. At single program sites, the responsible program office
shall perform the landlord responsibilities.
c. Assets management performance measures shall be based upon best
industry practice and shall be commensurate with the value and
importance of the asset using a graded approach.
Section 2
d. Asset management performance measures shall ensure formal,
comprehensive, integrated, documented planning, and control methods
for the acquisition, use, maintenance, and disposal of physical
assets, including real estate and energy and utilities. This shall
address, but shall not be limited to, the following:
(1) A comprehensive land-use planning process with stakeholder
involvement.
(2) The efficient and effective acquisition, management, and use of
energy and utilities.
(3) The management of backlogs associated with maintenance, repair,
and capital improvements.
(4) A method for the prioritization of infrastructure requirements.
(5) A method to declare assets surplus
e. The process for physical asset acquisition shall be an integrated,
systematic approach that shall ensure, but shall not be limited to,
the following:
CANCELE
D
DOE O 430.1 3
08-24-95
(1) Use of a comprehensive land-use process with
stakeholder involvement.
(2) Use of a process tool, such as value engineering, to
improve efficiency and cost-effectiveness when
analyzing physical asset acquisition.
(3) Specification of the appropriate state, regional, or
national building codes to which physical assets shall be designed and
constructed.
(4) Consideration of maintainability, operability, life-
cycle costs, and configuration integrity in designs and
acquisitions.
(5) Consideration of current mission needs and an
appropriate scope.
(6) Use of a DOE-certified real estate specialist for the
execution of real estate acquisitions.
(7) A project management system based on effective
management practices that is sufficiently flexible to
allow for the size and complexity of the project. For
line item projects, the following requirements are
considered minimal:
(a) Prior to the commencement of conceptual design,
include the following in project planning for
approval:
1 mission need,
2 minimum technical functional requirements,
3 proposed cost and schedule ranges,
4 preliminary environmental strategy,
5 identification of project technical and
organizational interfaces, and 6 integration
with other projects and activities.
(b) Prior to the commencement of execution, include
the following in project planning for approval:
1 project objectives,
2 scope, schedule, and cost baselines, including
contingencies,
3 life-cycle cost analysis,
4 preliminary safety assessment,
5 project controls, including baseline change
control, change control thresholds, and
statusing,
6 completion of National Environmental Protection Act
documentation prior to final commitment to an
alternative,
CANCELE
D
4 DOE O 430.1
7 verification of performance criteria through test and
evaluation, and
8 design alternatives.
(c) Prior to operation, a plan for turnover of a facility
shall be prepared; verification of performance criteria
through test and evaluation shall be accomplished; and
operational readiness shall be verified.
f. The process for the operation and maintenance of physical assets
shall ensure, as a minimum, the following:
(1) The identification, inventory, and periodic assessment of the
condition of physical assets in the maintenance program.
(2) The establishment of requirements, budgets, and a work
management system to maintain physical assets in a condition
suitable for their intended use.
(3) The preventive, predictive, and corrective maintenance to
ensure physical asset availability for planned use and/or
proper disposition.
Section 3
(4) A configuration management process to ensure the integrity of
physical assets and system.
(5) The efficient and effective management and use of energy and
utilities.
(6) A method for the prioritization of infrastructure requirements.
(7) The management of backlogs associated with maintenance, repair,
and capital improvements.
g. The process for the disposition of physical assets shall ensure, as
a minimum, the following:
(1) The use of a signed agreement to document items and conditions
when transferring assets between DOE program offices.
(2) The use of a DOE-certified real estate specialist to execute
the disposal of real estate, including the disposal of DOE
improvements without the underlying land.
(3) A method of timely identification and reporting of surplus
assets.
(4) In addition, for nuclear facilities, as a minimum the following
apply:
(a) The development of a decommissioning turnover plan.
(b) The development of a decontamination plan if appropriate
for the facility.
(c) The completion of a deactivation readiness review.
h. Utility services shall be acquired and disposed of through a DOE
prime contract.
i. The DOE corporate physical assets database shall be maintained as a
complete, current inventory of the DOE physical assets. The
CANCELE
D
DOE O 430.1 5
corporate database is Facilities Information Management System
(FIMS).
j. In the acquisition, operation, maintenance, and disposition of
physical assets, DOE elements shall ensure that all applicable
Federal, state, and local laws and regulations are followed.
7. RESPONSIBILITIES.
a. Secretary.
(1) Authorizes actions to acquire title to or interest in real
property by condemnation.
(2) Accepts donations of physical assets from outside DOE.
(3) Approves critical decisions on strategic systems.
b. Associate Deputy Secretary of Field Management.
(1) With General Counsel and participation of field elements,
jointly represents DOE consumer interests by intervening, or
otherwise participating in, hearings or proceedings before
utility regulating bodies, when these proceedings affect DOE
operations.
(2) With General Counsel and the Office of Clearance and Support,
jointly reviews and approves documents for the acquisition and
sale of utility services.
(3) With DOE elements, coordinates the possible reuse of facilities
that field elements report as excess.
(4) In coordination with program offices and program offices with
landlord responsibilities, takes the lead in verifying that
field elements have the asset management performance criteria
and measures in place to effectively oversee the contractors.
(5) Provides technical assistance to the program offices,
landlords, and field elements.
(6) Coordinates among program offices and field elements to support
an efficient, economic approach to physical asset management.
(7) Manages the certification program for DOE real estate
specialists.
(8) Supports the planning and budgeting process for physical
assets.
(9) Sponsors and coordinates the Life-Cycle Asset Management
Planning and Analysis Group.
(10) Acts as the DOE point-of-contact for external activities and
issues relating to life-cycle asset management.
(11) Supports the Secretary in the strategic systems critical
decision process.
(12) Supports the development of Departmental performance
CANCELE
D
6 DOE O 430.1
objectives.
(13) Facilitates the assignment of the landlord program office
responsibility.
Section 4
(14) Conducts independent cost assessments on strategic systems (or
on other projects, as requested) to verify a sound basis for
critical decision making that commits large expenditures of DOE
resources.
c. Program Office.
(1) Leads in defining, planning, and budgeting for program needs,
including operations, facilities, and projects.
(2) Leads in verifying that program objectives are met and is
accountable to the Secretary for program direction and
execution through the field element.
(3) Notifies field elements of plans to close program facilities.
(4) Coordinates with the Office of Field Management and field
elements to support an efficient, economic approach to physical
asset management.
(5) Develops, documents, and maintains a system to prioritize the
acquisition of programmatic physical assets, including
upgrades.
(6) Participates in the Life-Cycle Asset Management Planning and
Analysis Group.
(7) Supports or, if delegated, leads the critical decision process
for strategic systems funded by the program.
(8) Conducts reviews of field element performance, including
design, scope, and cost peer reviews for program elements under
their programmatic authority.
(9) Issues policy relative to its programmatic planning, budgeting,
and execution activities.
(10) Leads in establishing and clearly stating expected program
performance objectives and program performance criteria and
supports the contracting officer in implementation of
performance criteria for stated objectives.
(11) Supports the Office of Field Management to verify that field
elements have the asset management performance criteria and
measures in place to effectively oversee programmatic
facilities.
(12) Supports, including funding, the field elements in the
management of inactive and surplus program facilities that have
not been transferred to the Office of Environmental Management.
(13) For single program sites, performs responsibilities of the
landlord.
(14) For multi-program sites, provides support, including resources,
CANCELE
D
DOE O 430.1 7
to the program performing the responsibilities of the landlord.
(15) Leads oversight of field elements to ensure that performance
criteria and measures are in place to effectively achieve
program and project objectives related to the program office's
programmatic authority.
(16) Assumes the responsibilities of the field element for project
management and physical asset management not delegated to the
field element.
d. Program Office Designated as Landlord.
(1) Supports DOE field element's management of site infrastructure
by prioritizing and budgeting for real property needs in a
manner consistent with current and planned site mission
activities. For multi-program sites these responsibilities
include coordination of funding requirements with other program
offices.
(2) Issues policy relative to its infrastructure planning and
budgeting activities.
(3) Leads in establishing infrastructure performance objectives and
supports the contracting officer in developing performance
criteria for the site.
(4) Supports the Office of Field Management in verifying that field
elements have asset management performance criteria and
measures in place to effectively oversee nonprogrammatic
facilities.
(5) Leads reviews of field elements infrastructure activities, in
coordination with the program offices and the Office of Field
Management.
(6) Develops, documents, and maintains a system to prioritize the
acquisition of nonprogrammatic physical assets.
Section 5
(7) Supports, including funding, field elements in the management
of inactive and surplus landlord facilities that have not been
transferred to the Office of Environmental Management.
(8) Supports or, if delegated, leads the critical decision process
for strategic systems funded by the landlord.
(9) Leads issue resolution between program offices regarding
possible conflicts in planned infrastructure uses at multi-
program sites.
(10) Supports field elements in site-wide and external facilities
management and infrastructure issues requiring Headquarters
involvement.
(11) Coordinates landlord facilities management activities with
other DOE landlord programs to provide a consistent approach to
landlord facilities management.
e. Field Elements.
CANCELE
D
8 DOE O 430.1
(1) Serve as contracting officers for site contracts and all other
contracts and financial assistance agreements executed by field
elements.
(2) Prepare initial budget requests and planning for physical
assets.
(3) Obtain necessary approvals for projects from the sponsoring
program offices including mission need and project baselines,
as appropriate.
(4) Oversee projects delegated to them and oversee those projects
executed by contractors to verify requirements are met.
(5) Notify the Office of Field Management of excess real property
that has a significant remaining useful life.
(6) Verify adequate management of inactive and surplus facilities
until a reuse is found or the real property is disposed of.
(7) Lead the verification of an efficient, economic approach to
physical asset management in coordination with program offices
and the Office of Field Management.
(8) Participate in the DOE certification program for real estate
specialists.
(9) Participate in the Life-Cycle Asset Management Planning and
Analysis Group.
(10) Support the strategic systems critical decision process.
(11) Support the program offices in development of performance
criteria for program performance objectives and lead in
implementing program criteria.
(12) Lead in negotiating the performance criteria and measures with
the contractor to meet the defined performance objectives.
(13) Lead in evaluating the performance of the contractor against
the performance measures in the contract.
(14) Are accountable to the program offices and the landlord program
office for contractor performance.
(15) Coordinate all review and external oversight activities of the
contractors.
(16) With General Counsel and the Office of Field Management,
participate in the DOE's utility intervention process.
(17) When project size and complexity warrants, conduct independent
design, scope, and cost reviews.
8. ASSISTANCE. For answers to questions, contact the Office of Field
Management at (202) 586-2850.
CANCELE
D
DOE O 430.1 Attachment 1
Page 1
DEFINITIONS
1. Assets. See Physical Assets.
2. Asset Management Systems. Processes and/or procedures that are employed
for non-programmatic management of a facility or physical asset.
3. Baseline. A quantitative expression of projected costs, schedule, and
technical requirements; the established plan against which the status of
resources and the progress of a project can be measured.
4. Certified Realty Specialist. A DOE employee that is certified in one or
more of the four specialty realty areas: acquisition, non-GSA leasing,
GSA leasing, and land management and disposal. Employees so certified
may authorize or contract for real estate actions within certified
specialty area(s).
Section 6
5. Commencement of Execution. The beginning of the project phase that
accomplishes development and remedial action/construction. This project
phase advances the project from conceptual design to turnover to
operations, through the execution of the design, construction/building-
/remediation and acceptance of the project. During this project phase,
preliminary design, detailed design and construction/remedial design and
remedial actions take place.
6. Conceptual Design. The activities required to evaluate project design
alternatives and to develop sufficient detail to baseline the scope, cost
and schedule for project authorization.
7. Corporate Facilities. See DOE Facilities.
8. Corrective Maintenance. See Repair.
9. Critical Decision. A formal determination at a specific point in a
project that allows the project to proceed. Critical decisions occur in
the course of a project, for example: prior to commencement of
conceptual design, commencement of execution and prior to turnover.
10. Disposal. Permanent or temporary transfer of DOE control and custody of
real property to a third party who thereby acquires rights to control,
use, or relinquish the property.
11. Disposition. Those activities that follow completion of program mission,
including, but not limited to, stabilization, deactivation,
decontamination, decommissioning, dismantlement, and/or reuse of physical
assets.
12. DOE Elements. First tier organizations at Headquarters and in the field.
Field elements include all operations offices, field offices, energy
technology centers, and power marketing administrations.
13. DOE Facilities. Any of the DOE-owned, -leased, or -controlled
facilities.
14. Excess. Physical assets that are not required for DOE needs and the
discharge of its responsibilities.
15. Facilities. Land, buildings, and other structures, their functional
CANCELE
D
Attachment 1 DOE O 430.1
Page 2
systems and equipment, and other fixed systems and equipment installed
therein, including site development features outside the plant, such as
landscaping, roads, walks, and parking areas; outside lighting and
communication systems; central utility plants; utilities supply and
distribution systems; and other physical plant features.
16. Facilities Management. A documented process by which facilities are
operated and maintained.
17. Facility. The buildings, utilities, structures, and other land
improvements associated with an operation or service and dedicated to a
common function.
18. Graded Approach. The depth of detail required and the magnitude of
resources expended for a particular management element to be tailored to
be commensurate with the element's relative importance to safety,
environmental compliance, safeguards and security, programmatic
importance, magnitude of the hazard, financial impact, and/or other
facility-specific requirements.
19. Infrastructure. All real property and installed equipment and personal
property that is not solely supporting a single program mission.
20. Landlord Program Office. (Landlord) The Headquarters program office
responsible for the support, planning, acquisition, operation,
maintenance, and disposition of physical assets related to
infrastructure.
21. Life-Cycle. The life of an asset from planning through acquisition,
maintenance, operation, and disposition.
22. Line Item Project. Those separately identified project activities that
are submitted for funding and are specifically reviewed and approved by
Congress.
Section 7
23. Maintenance. Day-to-day work, including preventive and predictive
maintenance, that is required to maintain and preserve plant and capital
equipment in a condition suitable for it to be used for its designated
purpose.
24. Maintenance Backlog. The amount of maintenance and repair work not
accomplished at the end of the fiscal year that is needed or planned to
sustain the assigned mission.
25. Partnership. A process in which individual stakeholders create a team
approach to achieve mutual goals and objectives or to resolve problems.
26. Performance Criteria. A condition or set of conditions that, when
satisfied, indicate successful completion of the performance objective.
27. Performance Measures. Any evaluation, comparison, or judgement toward
meeting the performance objective.
28. Performance Objective. A statement of wants, needs, and expectations of
customers that sets the direction for all contract effort.
29. Personal Property. See Physical Assets.
30. Physical Assets. All DOE-owned or DOE-used and -controlled land, land
CANCELE
D
DOE O 430.1 Attachment 1
Page 3
improvements, structures, utilities, motor vehicles, equipment, and
components are included.
a. Real Property or Real Estate. Real property includes land,
improvements on the land, or both, including interests therein. All
equipment or fixtures (such as plumbing, electrical, heating,
built-in cabinets, and elevators) that are installed in a building
in a more or less permanent manner or that are essential to its
primary purpose are usually held to be part of real property.
b. Related Personal Property. Related personal property means any
personal property that, once installed, becomes an integral part of
the real property in which it is installed or is related to,
designed for, or specially adapted to the functional or productive
capacity of the real property. The removal of related personal
property will significantly diminish the economic value of the real
property or the related personal property. Examples of related
personal property are communications and telephone systems.
c. Personal Property. Generally, capitalizable property that can be
moved, or that is not permanently affixed to and part of real
estate. Generally, items remain personal property if they can be
removed without seriously damaging or diminishing the functional
value of either the capitalizable property or the real estate.
Examples of personal property are shop equipment and automated data
processing and peripheral equipment.
31. Programmatic Management. Functions that include planning and developing
the overall program; establishing broad priorities; providing program
technical direction; preparing and defending the program budget;
controlling milestones; integrating all components of the program;
providing public and private sector policy liaison; expediting interface
activities and follow-up actions; and retaining overall accountability
for program success.
32. Project. In general, a unique effort that supports a program mission
with defined start and end points, undertaken to create a product,
facility, or system with interdependent activities planned to meet a
common objective/mission. Projects include planning and execution of
construction/renovation/modification/environmental restoration or
decontamination and decommissioning efforts, and large capital equipment
or technology development activities. Tasks that do not include the
above elements, such as basic research, grants, and operations and
maintenance of facilities, are not considered projects.
Section 8
33. Property. See Physical Assets.
34. Related Personal Property. See Physical Assets.
35. Repair. The restoration of failed or malfunctioning equipment, system,
or facility to its intended function or design condition. Repair does
not result in a significant extension of the expected useful life.
36. Site. A geographic entity comprising leased or owned land, buildings,
and other structures required to perform program activities.
37. Strategic System. (formerly Major Systems Acquisition) A special type
of line item project(s) that is a single, stand-alone effort within a
program mission area that is a primary means to advance the Department's
CANCELE
D
Attachment 1 DOE O 430.1
Page 4
strategic goals. Designation of a strategic system is determined by the
Secretary based on cost, risk factors, international implications,
stakeholder interest, and/or national security.
38. Strategic System Critical Decision Process. See Critical Decision.
39. Surplus. Any facility that the responsible program office declares
available for other use.
40. Utility. A system, or any of its components, that generates and/or
distributes (via pipelines, wires, buses, or electromagnetic waves) a
commodity or service to itself and/or to other facilities.
41. Utility Service. A service, such as the furnishing of electricity,
natural gas, steam, water, and sewer service and the furnishing of
appurtenant facilities and systems. Telecommunication services or the
removal and disposal of garbage, rubbish, and trash are not included.
CANCELE
D
DOE O 430.1 Attachment 1
Page 5 (and 6)
42. Value-added. A decision-making process that leads to an improvement in
an operation or process, based on effectiveness, efficiency, cost-
effectiveness, safety, etc.
43. Value Engineering. An organized effort, directed by a person trained in
value engineering (VE) techniques, to analyze the functions of systems,
equipment, facilities, services, and supplies to achieve the essential
functions at the lowest life-cycle cost that is consistent with required
performance, reliability, availability, quality, and safety. (Terms such
as value analysis, value control, value improvement, value management,
and functional analysis are synonymous).
CANCELE
D