DOE O 425.1F, Verification Of Readiness To Startup Or Restart Nuclear Facilities
This Order of the Department of Energy (DOE) including the National Nuclear Security Administration (NNSA) establishes the requirements for the Department of Energy (DOE) Readiness Reviews (RRs). RRs are used to verify the readiness for startup and rest
Supersedes:
Version history and related documents
Supersedes
Earlier documents this one replaced.
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
AVAILABLE ONLINE AT: INITIATED BY:
www.directives.doe.gov Office of Environment, Health, Safety, and Security
U.S. Department of Energy ORDER
Washington, D.C.
Approved: 08-05-2026
SUBJECT: VERIFICATION OF READINESS TO STARTUP OR RESTART HAZARD
CATEGORY 1 AND 2 NUCLEAR FACILITIES
1. PURPOSE. This Order of the Department of Energy (DOE), including the National
Nuclear Security Administration (NNSA), establishes the requirements for the DOE
readiness reviews (RRs). RRs are used to verify the readiness for startup and restart of
Hazard Category (HC) 1 and 2 nuclear facilities, operations, or activities as described
within this Order. The final report documents the results of the RR and makes a
conclusion as to whether startup or restart of the nuclear facility, activity, or operation
can proceed safely.
2. CANCELS/SUPERSEDES. DOE O 425.1E, Verification of Readiness to Startup or
Restart Nuclear Facilities, dated September 30, 2024.
Cancellation of an Order/directive does not, by itself, modify or otherwise affect any
contractual or regulatory obligation to comply with the Order/Directive. Contractor
Requirements Documents (CRDs) that have been incorporated into a contract remain in
effect throughout the term of the contract unless and until the contract or regulatory
commitment is modified to either eliminate requirements that are no longer applicable or
substitute a new set of requirements.
3. APPLICABILITY.
a. Departmental Applicability. This Order is applicable to DOE within the
provisions and restrictions of the NNSA Act, found at Title XXXII of Public Law
(P.L). 106-65, National Defense Authorization Act for Fiscal Year 2000. This
Order applies to all nuclear facilities, operations or activities as defined in Title 10
of the Code of Federal Regulations (CFR), Part 830, Nuclear Safety Management,
that are classified as HC 1 and 2 nuclear facilities.
(1) Activities regulated by the Department of Transportation; and
transportation of onsite transportation packages authorized by 49 CFR,
Part 173, Shippers—General Requirements for Shipments and Packagings,
Subpart I. Onsite transportation activities may be excluded with Program
Secretarial Officer or Cognizant Secretarial Officer approval, and Central
Technical Authority (CTA) concurrence, provided an alternate process
is identified.
DOE O 425.1F
2 DOE O 425.1F
08-05-2026
(2) The Administrator of the NNSA will assure that NNSA employees comply
with their respective responsibilities under this Order. Nothing in this
Order will be construed to interfere with the NNSA Administrator’s
authority under Section 3212(d) of P.L. 106-65 to establish
Administration-specific policies, unless disapproved by the Secretary.
b. DOE Contractors. The requirements of this Order shall be incorporated into
applicable contracts, including Management and Operating contracts. The
contractor is responsible for flowing down the requirements of this CRD, if
applicable. Contractors shall comply with the requirements of applicable federal,
state, and local laws and regulations in carrying out the requirements of this Order
unless relief has been granted in writing. Omission of any applicable law or
regulation from the Order does not affect the obligation of the contractor to
comply with such law or regulation. Contractors must comply with the
requirements of this Order, except to the extent modified by the equivalencies or
exemptions identified herein or issued to the contractor in writing by DOE
utilizing the process outlined in DOE Order (O) 251.1E, Departmental Directives
Program, including as amended or updated.
Section 2
c. Equivalencies and Exemptions for DOE O 425.1F. Equivalencies and exemptions
to the requirements of this Order are processed in accordance with
DOE O 251.1E. CTA (or designee) concurrence is required for both exemptions
and equivalencies to this Order for nuclear facilities.
(1) Equivalency. In accordance with the responsibilities and authorities
assigned by Executive Order 12344, Naval Nuclear Propulsion Program,
codified at 50 United States Code §§ 2406, Deputy Administrator for
Naval Reactors, and 2511, and to ensure consistency throughout the joint
Navy and DOE organization of the Naval Nuclear Propulsion Program,
the Deputy Administrator for Naval Reactors (Director) will implement
and oversee all requirements and practices pertaining to this DOE Order
for activities under the Director’s cognizance, as deemed appropriate.
(2) Exemptions. This Order does not apply to the following:
(a) Activities regulated through a license by the Nuclear Regulatory
Commission (NRC) or a state under an agreement with NRC,
including activities certified by NRC under Section 1701 of the
Atomic Energy Act.
(b) Activities in the Transportation Safeguards System in NNSA.
(c) Other Equivalencies/Exemptions. Any other equivalency or
exemption to the Order requires the approval of the DOE’s Safety
Basis Approval Authority (SBAA). Requests for
equivalencies/exemption will be adjudicated by DOE’s SBAA
within 14 calendar days of receipt of a substantially
complete request.
DOE O 425.1F 3
08-05-2026
d. Government-Owned, Government-Operated Facilities. Attachment 1, CRD, of
this Order sets forth requirements applicable to DOE government-owned,
government-operated facilities. Government operators must comply with the
requirements in Attachment 1 of this Order.
4. REQUIREMENTS.
a. DOE Head of Field Element or Designee. Ensure that properly scoped RRs are
planned and conducted to verify readiness for the startup or restart of HC 1 and
2 nuclear facilities, activities, or operations.
b. HC 1 and 2 nuclear facilities, activities, or operations may be started (or restarted)
only after RRs have been conducted and the approvals specified in this Order
have been received.
c. RR Process. DOE Head of Field Element or designee will review the procedures
that define the RR processes that will be utilized to implement this Order. The
RR process must, in all cases, demonstrate there is a reasonable assurance for
adequate protection of workers, the public, and the environment from adverse
consequences from the startup (or restart) of an HC 1 and 2 nuclear facility,
activity, or operation. The readiness process is illustrated within Attachment 2,
Readiness Review Process Flow Chart.
(1) Communication. The prime contractor will communicate projected RR
activities to the Startup Approval Authority (SAA) or designee.
(2) Notification of Intent to Startup. The prime contractor will provide formal
correspondence to DOE, which should be at least 90 days prior to the start
of the RR, but no earlier than SBAA approval of the Preliminary
Documented Safety Analysis, if applicable. The SBAA will review the
notification, inform the SAA, and coordinate the RR team. SAA
determination is in accordance with Attachment 3, Startup Approval
Authority and Readiness Review Determination Criteria.
(a) The notification of intent to startup will include the submittal of
the Readiness Review Plan (RP).
(3) RP Content and Approval.
Section 3
(a) Content. The prime contractor will develop an RP, using a graded
approach to define the scope. The RP may take into consideration
the maturity of the prime contractor’s existing safety management
programs that are in place to implement the Core Requirements
(CRs). The level of detail should also be commensurate with the
complexity of the startup or restart.
4 DOE O 425.1F
08-05-2026
It may be appropriate to perform RRs in a segmented approach to
allow flexibility in managing specific activities (e.g., fuel receipt,
storage, and loading before initial startup). All listed
documentation must be included unless it is not applicable to the
specific scope of the activity. Contents or the RP must include:
1 A scope and purpose that addresses all Attachment 4, CRs.
Exclusion of any CRs must be documented and justified
within the RP.
2 Prerequisites, as defined in Attachment 5, must be
completed prior to the start of the RR or have
compensatory measures that have been documented and
approved. This should include documentation ensuring
system operability verification and testing (to the
extent practical).
3 A description of the physical and administrative boundaries
of the RR.
4 A description of the structure, systems, and components
covered by the RR.
5 A description of safety management and security programs
to be reviewed.
6 Proposed activities for the onsite review including
demonstrations, interviews, and drills as applicable.
(b) RP Approval. For a contractor RR, the SAA will review and
approve the RP with SBAA concurrence. For a DOE RR, the RP
must be reviewed and approved by the SBAA. Both approvals are
expected 30 days following the submittal.
(4) DOE RR Team Composition. DOE Head of Field Element or designee
will select the RR team leader. The team leader must then select the RR
team members. The RR team leader must not be assigned to assess
facilities, activities, or operations for which they have direct
responsibilities. Team member should not be assigned to assess facilities,
activities, or operations for which they have direct responsibilities to the
maximum extent possible. Team leader and members’ qualifications must
be documented and shall address the following requirements:
(a) Technical knowledge of the area assigned for evaluation, including
experience working in the technical area.
(b) Knowledge of the performance-based assessment process
and methods.
DOE O 425.1F 5
08-05-2026
(c) Knowledge of the facility, activity, or operations-
specific information.
(5) Prior to starting the DOE RR.
(a) The prime contractor prerequisites will have been met or have
compensatory measures that have been documented and approved.
(b) Specific events significant to the startup and restart process that
occur prior to the formal commencement of the RR (e.g., site
emergency response drills) may be reviewed by the RR team at the
time they are conducted.
(6) Readiness to Proceed. The SBAA must submit to the DOE RR Team
Leader their authorization to commence the RR.
(7) Commencement of RR.
(a) Upon receipt of the authorization to commence the RR, the RR
Team will initiate the RR, in accordance with the approved RP.
(b) The RR will be executed in accordance with the approved RP.
(c) The RR schedule will normally consist of:
1 One week of document review.
2 One week of onsite interviews and performance reviews as
planned in the RP.
3 One week to prepare the final report.
Section 4
4 Deviation from this schedule due to readiness segmentation
may be justified and approved in the RP.
(8) RR Final Report. The final report must be prepared and approved by the
team leader; concurred on by each team member.
(a) The final report documents the results of the DOE RR and makes a
conclusion as to whether startup or restart of the nuclear facility,
activity, or operation can proceed safely. The DOE RR final report
must state whether the contractor has established the following:
1 An agreed set of requirements to govern safe operations of
the facility, activity, or operation has been formalized with
DOE through the contract or other enforceable mechanism.
6 DOE O 425.1F
08-05-2026
That these requirements have been appropriately
implemented in the facility, activity, or operation or that
appropriate compensatory measures, formally approved by
DOE, are in place during the period prior to full
implementation; and
2 That, in the opinion of the RR team, adequate protection of
the public health and safety, of worker safety, and the
environment will be maintained.
(b) If appropriate, the final report will include a Minority Opinion
section that will give a means for team members to convey
diverging opinions to the SBAA.
(c) Any lessons learned during the RR must be documented in a
lessons learned section of the final report.
(9) Final Report Submittal. The final report must be submitted to the SAA to
be used as a basis for approving the startup or restart of the nuclear
facility, activity, or operation. A copy of the final RR report must be
forwarded to the prime contractor and the Assistant Secretary of Energy
for Nuclear Energy (NE-1). A copy must be forwarded to the appropriate
CTA and may be forwarded to DOE Office of Environment, Health,
Safety and Security and Office of Enterprise Assessments for information.
(10) Closure of Findings. The closure of findings must be consistent with the
issues management process.
(11) Restart and Startup Approval. DOE Head of Field Element or designee
must ensure that the prime contractor has satisfactorily resolved all
prestart findings identified during the RRs prior to startup or restart of the
facility, activity, or operation. The SAA, as identified in Attachment 3,
approves startup or restart after compensatory measures (if needed) are in
place and approved corrective action plans are in place to address any
open post-start findings.
(12) Approval to Proceed. The SAA must provide an approval to proceed
memorandum to the responsible prime contractor authorizing startup
or restart.
d. Records Management Program. Requirements for maintenance and disposition of
federal records, such as those pertaining to RRs, are provided under the general
guidance of DOE O 243.1, Records Management Program, current version. The
disposition, including destruction, of federal records must be in accordance with:
(1) The General Records Schedules, as published by the National Archives
and Records Administration (NARA), or
DOE O 425.1F 7
08-05-2026
(2) DOE records disposition authority (Standard Form 115, Request for
Records Disposition Authority), as approved by NARA.
The cognizant Field Element Records Officer can provide guidance.
5. RESPONSIBILITIES.
a. DOE Headquarters Line Management.
(1) Oversee DOE field methods for verifying readiness to startup and restart
nuclear facilities, activities or operations.
(2) Exercise delegation of authority and document all delegations of authority
made under the provisions granted by this Order.
Section 5
b. DOE Head of Field Element or designee.
(1) Ensure that the prime contractor properly implements the requirements of
the CRD in this Order.
(2) Establish procedures as necessary to manage the verification of readiness
to startup or restart nuclear facilities, activities or operations in accordance
with the requirements of this Order.
c. Contracting Officer.
(1) For all applicable contracts and upon notification that a site/facility
management contract is affected by this Order, incorporate the
requirements into the affected contract(s) via the “Laws, Regulations, and
DOE Directives” clause of the contract, or through negotiation and
modification, as appropriate.
6. INVOKED TECHNICAL STANDARDS. This Order does not invoke any DOE
technical standards or industry standards as required methods. Any technical standard or
industry standard that is mentioned in or referenced by this Order is not invoked by this
Order. Note: DOE O 251.1, current version, provides a definition for “invoked
technical standard.”
7. REFERENCES.
a. Title 10 CFR Part 830, Nuclear Safety Management.
b. 10 CFR Part 835, Occupational Radiation Protection
c. 49 CFR, Part 173, Subpart I, Class 7 (Radioactive) Materials
d. DOE O 243.1, Records Management Program, current version.
e. DOE O 420.1, Facility Safety, current version.
8 DOE O 425.1F
08-05-2026
f. DOE O 422.1, Conduct of Operations, current version.
g. DOE O 433.1, Maintenance Management Program for DOE Nuclear Facilities,
current version.
h. DOE-STD-1027-2025, Chg Notice 1, Hazard Categorization of DOE
Nuclear Facilities.
i. DOE-STD-1073-2016, Configuration Management.
j. DOE-STD-1189-2016, Integration of Safety into the Design Process.
k. DOE-STD-3006-2010, Planning and Conducting Readiness Reviews.
l. DOE-STD-3007-2007, Guidelines for Preparing Criticality Safety Evaluations at
Department of Energy Non-Reactor Nuclear Facilities.
8. DEFINITIONS. See Attachment 5.
9. CONTACT. Questions concerning this Order should be referred to the Director, Office
of Nuclear Safety Policy and Assistance, at (301) 903-3331.
JAMES P. DANLY
Deputy Secretary
DOE O 425.1F Attachment 1 - CRD, Contractors Only
08-05-2026 Page 1-1
ATTACHMENT 1
CONTRACTOR REQUIREMENTS DOCUMENT
DOE O 425.1F, VERIFICATION OF READINESS TO STARTUP OR RESTART
HAZARD CATEGORY 1 AND 2 NUCLEAR FACILITIES
In addition to the requirements set forth in this Contractor Requirements Document (CRD),
contractors are responsible for complying with Attachments 3 and 4 of this Order, referenced in
and made a part of this CRD, which provide program requirements and/or information applicable
to contracts in which this CRD is inserted.
1. Department of Energy (DOE), including the National Nuclear Security Administration
(NNSA), Contractor Responsibilities. This CRD applies to all nuclear facilities,
activities, and operations classified as Hazard Categories (HC) 1 and 2 as defined in
10 Code of Federal Regulations (CFR) Part 830. Regardless of the performer of the
work, the contractor is responsible for complying with the requirements of this CRD and
flowing down CRD requirements to subcontractors at any tier to the extent necessary to
ensure contractor compliance.
Contractor Requirements. Contractor line management must develop procedures to
define the processes that will be used to implement the responsibilities of this CRD. The
contractor must not develop RR processes similar to RRs that exempt facilities, activities,
or operations from following the RR process described in this Order.
Section 6
a. RR Process. The RR process must, in all cases, demonstrate there is a reasonable
assurance for adequate protection of workers, the public, and the environment
from adverse consequences from the start (or restart) of a HC 1 and 2 nuclear
facility, activity, or operation. The readiness process is described under
Attachment 2, Readiness Review Process Flow Chart, and Attachment 5,
Definitions. For an RR, the contractor must prepare: an intent to startup
notification, a Readiness Review Plan (RP) and a final report. The contractor will
perform the RR when the Startup Approval Authority (SAA) is the Senior
Contractor Official. Attachment 3, Startup Approval Authority (SAA), and
Readiness Review (RR) Determination Criteria, describes how to determine the
appropriate SAA.
(1) Communication. Contractors must communicate projected RR activities
to the appropriate Safety Basis Approval Authority (SBAA) or designee.
(2) Notification of Intent to Startup. The prime contractor will provide formal
correspondence to DOE, which should be 90 days prior to the start of the
RR, but no earlier than SBAA approval of the Preliminary Documented
Safety Analysis, if applicable. The Senior Contractor Official will
coordinate the RR.
The notification of Intent to Startup will include the submittal of the RP to
the SBAA.
Attachment 1 – CRD, Contractors Only DOE O 425.1F
Page 1-2 08-05-2026
(3) RP Content and Approval.
(a) Content. The prime contractor will develop an RP, using a graded
approach to define the scope. The RP may take into consideration
the maturity of the prime contractor existing safety management
programs that are in place to implement the Core Requirements
(CRs). The level of detail should also be commensurate with the
complexity of the startup or restart. It may be appropriate to
perform RRs in a segmented approach to allow flexibility in
managing specific activities (e.g., fuel receipt, storage, loading
before initial startup). All listed documentation must be included
unless it is not applicable to the specific scope of the activity.
Contents of the RP must include:
1 A scope and purpose that addresses all Attachment 4, Core
Requirements (CRs). Exclusion of any CRs must be
documented and justified within the RP.
2 Prerequisites, as defined in Attachment 5, that must be
completed prior to the start of the RR or have
compensatory measures that have been documented and
approved. This should include documentation ensuring
system operability verification and testing (to the
extent practicable).
3 A description of the physical and administrative boundaries
of the RR.
4 A description of the structures, systems, and components
covered by the RR.
5 A description of safety management and security programs
to be reviewed.
6 Proposed activities for the onsite review, including
demonstrations, interviews, and drills as applicable.
(b) RP Approval. For a contractor RR, the SAA will approve the RP
with SBAA concurrence. For a DOE RR, the RP must be
reviewed and approved by the SBAA. Both approvals are
expected 30 days following the submittal.
(4) Contractor RR Team Composition. The contractor RR team leader must
select the RR team members. RR team leader and team members must not
be assigned to assess facilities, activities or operations for which they have
direct responsibilities. Team leader and members’ qualifications must be
documented and shall address the following requirements:
DOE O 425.1F Attachment 1 - CRD, Contractors Only
08-05-2026 Page 1-3
Section 7
(a) Technical knowledge of the area assigned for evaluation, including
experience working in the technical area.
(b) Knowledge of the performance-based assessment process
and methods.
(c) Knowledge of the facility, activity, or
operations-specific information.
(5) Prior to starting the Contractor RR.
(a) The prime contractor prerequisites have been met or have
compensatory measures that have been documented and approved.
(b) Specific events significant to the startup and restart process that
occur prior to the formal commencement of the RR (e.g., site
emergency response drills) may be reviewed by the RR team at the
time they are conducted.
(6) Readiness to Proceed. The SAA must submit to the contractor RR team
leader their authorization to commence the contractor RR.
(7) Commencement of Contractor RR.
(a) Upon receipt of the authorization to commence the contractor RR,
the contractor RR Team will initiate the contractor RR, in
accordance with the approved RP.
(b) The RR will be executed in accordance with the approved RP.
(8) Contractor RR Final Report. The final report must be prepared and
approved by the team leader and receive concurrence from each team
member, and each team member must approve the section for which the
team member is responsible.
(a) The final report documents the results of the contractor RR and
draws a conclusion as to whether startup or restart of the nuclear
facility, activity, or operation can proceed safely. The contractor
RR final report must state whether the contractor has established
the following:
1 An agreed set of requirements to govern safe operations of
the facility, activity, or operation has been formalized with
DOE through the contract or other enforceable mechanism.
Attachment 1 – CRD, Contractors Only DOE O 425.1F
Page 1-4 08-05-2026
2 That these requirements have been appropriately
implemented in the facility, activity, or operation or
appropriate compensatory measures, formally approved by
DOE, are in place during the period prior to full
implementation; and
3 That, in the opinion of the contractor RR team, adequate
protection of the public health and safety of worker safety,
and the environment will be maintained.
(b) If appropriate, the final report will include a Minority Opinion
section that will give a means for team members to convey
diverging opinions to the SAA.
(c) Any lessons learned during the contractor RR must be documented
in a lessons learned section of the final report.
(9) Final Report Submittal. The final report must be submitted to the SAA.
(10) Closure of Findings. Contractor line management closure of contractor
RR findings must be consistent with the Issues Management Process in
DOE O 226.1, Implementation of Department of Energy Oversight Policy,
current version.
(11) Restart and Startup Approval. Senior Contracting Official must ensure all
pre-start findings identified during the RR are satisfactorily resolved prior
to startup or restart of the facility, activity, or operation. The SAA may
approve startup or restart only after pre-start finding are resolved,
compensatory measures (if needed) are in place; and approved corrective
action plans are in place to address any open post-start findings.
b. Records Management Program. Requirements for maintenance and disposition of
federal records, such as those pertaining to RRs, are provided under the general
guidance of DOE O 243.1, Records Management Program, current version. The
disposition, including destruction, of federal records must be in accordance with:
Section 8
(1) The General Records Schedules, as published by the National Archives
and Records Administration (NARA), or
(2) DOE records disposition authority (Standard Form 115, Request for
Records Disposition Authority), as approved by NARA.
The cognizant Field Element Office Records Officer will provide guidance
as needed.
DOE O 425.1F Attachment 2 – Readiness Review Flowchart
XX-XX-2026 Page 2-1
ATTACHMENT 2
READINESS REVIEW FLOWCHART
This Attachment provides information associated with this Order as well as information
applicable to contracts in which the associated Attachment 1, Contractor Requirements
Document, is inserted. The flow chart describes the Readiness Review (RR) process. Either a
contractor RR or a DOE RR will be performed in accordance with the determination criteria of
Attachment 3, Startup Notification Report, Startup Authorization Authority (SAA), and
Readiness Review (RR) Determination Criteria.
DOE O 425.1F Attachment 3 – Federal and Contractor Employees
08-05-2026 Page 3-1
ATTACHMENT 3
STARTUP APPROVAL AUTHORITY (SAA), AND READINESS REVIEW (RR)
DETERMINATION CRITERIA
This Attachment provides information and/or requirements associated with this Order as well as
information and/or requirements applicable to contracts in which the associated Attachment 1,
Contractor Requirements Document, is inserted.
1. For nuclear facility, activity, or operation startups or restarts, the Approval Authority
must be determined using the criteria in Attachment 3, Table 1, SAA and RR
Determination Criteria. Determining the level of authority, the SAA, must be
commensurate with RR criteria.
2. DOE Head of Field Element or designee must ensure that a properly scoped RR is
planned and conducted to verify readiness for the restart of Hazard Category (HC) 1 and
2 nuclear facilities, activities, or operations, unless both of the following conditions
are met:
a. The restart is a resumption of routine operations after a short interruption (such as
maintenance activities governed by existing maintenance procedures and
processes) as defined in local procedures; and
b. The restart is conducted using contractor approved operating procedures that
provide specific direction for operating systems and equipment during normal
conditions.
3. Justification for the SAA and RR determination must be documented in writing to the
SBAA 90 days prior to the RR, beginning with a copy sent to the Program Secretarial
Officer (PSO) and Central Technical Authority. If an RR is not to be performed, the
contractor’s standard operating procedures for startup or restart will be used.
4. If any of the following conditions occur, a RR must be conducted in accordance with this
Order. Additional criteria are included in Attachment 3, Table 1:
a. Initial reactor startup.
b. Initial startup of a newly constructed HC 1 or 2 non-reactor nuclear facility. For
the purpose of this criterion, a newly constructed HC 1 or 2 non-reactor nuclear
facility refers to a new facility (not operation or activity) with a new safety-basis
documentation—that is, a safety evaluation report (SER), documented safety
analysis (DSA), and technical safety requirements (TSRs).
c. Initial startup after conversion of an existing facility to a new nuclear mission
with a new safety-basis documentation (new SER, DSA and TSRs).
d. Restart of nuclear facility, activity, or operation that has upgraded its hazard
categorization to HC 1 or 2.
Attachment 4 – Federal Employees and Contractors DOE O 425.1F
Page 3-2 08-05-2026
Section 9
e. Restart after a DOE management official directs the shutdown of a nuclear
facility, activity, or operation for safety reasons.
f. Restart after an extended shutdown for an HC 1 or 2 nuclear facility, activity, or
operation. Extended shutdown for an HC 1 or 2 nuclear facility, activity, or
operation is defined as 24 months.
g. Restart of an HC 1 or 2 nuclear facility, activity, or operation after major
modification (determination of “major modifications” is made per DOE-STD-
1189).
h. Initial startup of a new HC 1 or 2 activity or operation after major modification
(determination of “major modifications” is made per DOE-STD-1189 within an
HC 1 or 2 nuclear facility).
i. Startup or restart of facility, activity, or operation as directed by DOE line
management.
j. The SAA level will determine the type of RR, either a DOE RR or contractor RR.
Table 1: SAA and RR Determination Criteria
Activity
Startup Approval Authority
Hazard Category 1 and 2
Off Site
Initial reactor startup Secretary of Energy or designee
Any other activity listed below PSO or designee
On Site
Initial Reactor Startup Secretary of Energy or designee
Initial startup of a newly constructed HC 1 or 2
non-reactor nuclear facility. For the purpose of
this criterion, a newly constructed HC 1 or 2
non-reactor nuclear facility refers to a new
facility (not operation or activity) with a new
safety-basis documentation (new SER, DSA,
and TSRs).
DOE SBAA or designee
Initial startup after conversion of an existing
facility to a new nuclear mission with a new
safety-basis documentation (new SER, DSA
and TSRs).1
DOE SBAA or designee
Restart of nuclear facility, activity, or
operation that has upgraded its hazard
categorization to HC 1 or 2.
DOE SBAA or designee
Restart after a DOE management official
directs the shutdown of a nuclear facility,
activity, or operation for safety reasons.
DOE SBAA or designee
DOE O 425.1F Attachment 3 – Federal and Contractor Employees
08-05-2026 Page 3-3
Activity
Startup Approval Authority
Hazard Category 1 and 2
Restart after extended shutdown for an
HC 1 or 2 nuclear facility, activity, or
operation.2
>24 months
Senior Contractor Official
Restart of an HC 1 or 2 nuclear facility,
activity, or operation after major
modification.3
Senior Contractor Official
Initial startup of a new HC 1 or 2 activity or
operation after major modification within a
HC 1 or 2 facility.3
Senior Contractor Official
Startup or restart of a facility, activity, or
operation as directed by DOE line
management.
DOE SBAA or designee
For all other cases: Senior Contractor Official
Note 1: New includes new construction.
Note 2: Extended shutdown for an HC 1 or 2 nuclear facility, activity, and operation is defined as 24 months.
Note 3: Determination of “major modifications” is made per DOE-STD-1189.
DOE O 425.1F Attachment 4 – Federal Employees and Contractors
08-05-2026 Page 4-1
ATTACHMENT 4
CORE REQUIREMENTS (CRS)
This Attachment provides information and/or requirements applicable to contracts in which
Attachment 1, Contractor Responsibilities Document, is inserted. This Attachment defines the
CRs used in this Order.
1. CRs verify the readiness of personnel, procedures, programs, and equipment within the
scope of the RR to safely startup or restart a nuclear facility, activity, or operation. The
CRs are aligned according to specific functional areas (FAs) or safety management
programs (SMPs) that are developed and implemented across Department of Energy
(DOE) sites to ensure activities are performed in a manner that adequately protects
workers, the public, and the environment. Cross-cutting requirements are applicable to
each of these programs and need to be evaluated to ensure their success.
Section 10
a. Each CR listed as applicable must be evaluated against the following cross-
cutting requirements (cross-cutting requirements may be excluded and
documented in the RP with appropriate justifications):
(1) FA or SMP documents have been approved by DOE, if required by DOE
Order, Codes of Federal Regulations (CFRs), or direction.
(2) FA or SMP implementing procedures have been effectively implemented
in support of the facility and clearly define roles, responsibilities, and
reporting relationships.
(3) A sufficient number of qualified personnel are available to effectively
implement the FA or SMP in support of the facility.
(4) Adequate facilities and equipment are available to ensure that the FA or
SMP can be performed adequately for safe facility operation.
(5) Line management and personnel level of knowledge is adequate based on
examination results, direct observation during performance
demonstrations, and interviews.
(6) Line management and personnel exhibit an awareness of public and
worker safety and health and environmental protection requirements and,
through their actions, demonstrate a high-priority commitment to comply
with these requirements.
(7) Periodic assessments (independent and/or self) of FA or SMPs are
performed to verify continued robust performance. Issues (e.g., findings,
deficiencies, observations, or recommendations) from assessments, both
internal and external, are effectively resolved.
Attachment 4 – Federal Employees and Contractors DOE O 425.1F
Page 4-2 08-05-2026
b. The CRs are as follows:
(1) Conduct of Operations, Procedures, and Work Control. A conduct of
operations program meets the requirements of DOE O 422.1, Conduct of
Operations. The formality and discipline of operations are adequate to
conduct work safely, and programs are in place to maintain this formality
and discipline for site/facility processes in accordance with the approved
Conduct of Operations Implementation Matrix.
Procedures are approved and in place for operating the facility and
systems. The procedures reflect all modifications that have been made to
the facility systems. Only the most current revision of each procedure is
in use.
(2) Contractor Assurance. An effective Contractor Assurance System (CAS)
meets the requirements is necessary. A CAS has been established to
identify, evaluate, and resolve deficiencies and recommendations made by
contractor line management and independent contractor audit and
assessment groups. The process also provides for resolution of issues and
recommendations by external official review teams and audit
organizations.
(3) Criticality Safety. A Criticality Safety Program (CSP) that meets the
requirements of DOE O 420.1, Facility Safety, including DOE approval of
the CSP document, have been developed, implemented, and maintained.
Criticality safety evaluations conducted in accordance with DOE-STD-
3007-2017, Guidelines for Preparing Criticality Safety Evaluations at
Department of Energy Non-Reactor Nuclear Facilities, or by other
documented methods approved by DOE, must show that entire processes
involving fissionable materials will remain subcritical under normal and
credible abnormal conditions, including those initiated by design-basis
events. Implementation of the Criticality Safety Evaluation credited
controls is reviewed annually for all operations.
Facilities that conduct operations using fissionable material in a form that
could inadvertently accumulate in significant quantities must include
procedures for detecting and characterizing accumulations.
Section 11
(4) Emergency Planning and Preparedness, and Operational Drills. A routine
operations drill program and an emergency management drill and exercise
program have been established and implemented. Records for each
program are adequate to demonstrate the effectiveness of completed drills
and exercises as well as planning for future drills and exercises.
DOE O 425.1F Attachment 4 – Federal Employees and Contractors
08-05-2026 Page 4-3
(5) Conduct of Engineering. Structures, systems, and components (SSCs)
required for safe and compliant operations have been identified, and
programs are in place to ensure adequate maintenance, operations, and
modifications. These programs include requirements for demonstrating
compliance with the design requirements, verifying operability of SSCs,
availability of replacement and spare parts, and configuration management
of documents and equipment.
(a) The facility has implemented a maintenance program compliant
with DOE O 433.1, Maintenance Management Program, for DOE
nuclear facilities. A program is in place to confirm and
periodically assess the condition and operability of SSCs. This
includes examinations of records of tests and calibration of these
systems. A documented evaluation of maintenance items open
before the declaration of readiness (if any) has been conducted to
determine if the failure to complete the maintenance item could
adversely influence operations.
(b) Provisions have been established for storage, issuance, and
availability of an adequate and readily available supply of tools
and critical spare parts.
(c) Credited safety equipment being started up or restarted meets the
requirements of DOE O 420.1, Facility Safety, for the safety
functions and process controls credited in the safety
documentation, the design has been analyzed to demonstrate
compliance with the design inputs, and design outputs provide
specific limits, controls, and technical directions for SSCs to the
constructor, operator, or modifier.
(d) A configuration management program in accordance with DOE-
STD-1073, Configuration Management, is defined and
implemented to control facility modifications with emphasis on
SSCs. Authorized modifications within the scope of the RR have
been completed and fully closed or evaluated and determined not
to affect the ability to safely start up or restart nuclear operations.
(6) Fire Protection. A documented fire protection program in accordance with
DOE O 420.1, Facility Safety, that includes the elements and requirements
identified in the Order for design, operations, emergency response, fire
analysis and assessments, wildland fire, and specific Fire Protection
Program criteria has been developed, implemented, and maintained by the
contractor.
Attachment 4 – Federal Employees and Contractors DOE O 425.1F
Page 4-4 08-05-2026
(7) Nuclear Safety. Facility/process safety-basis (SB) documentation
(documented safety analysis [DSA], hazard analysis report [HAR], and
technical safety requirements [TSRs]) characterizes the hazards/risks
associated with the facility/process; identifies preventive and mitigating
measures to adequately protect workers, the public, and the environment
from those hazards/risks; describes the safety envelope of the
facility/process; is approved; and controls are implemented as required by
10 CFR Part 830, Nuclear Safety Management, Subpart B.
A DOE approved Unreviewed Safety Question procedure has been
effectively implemented.
Section 12
Offsite and onsite shipments of hazardous and/or radioactive materials
meet applicable requirements as cited in SB documents.
(8) Personnel and Management Training and Qualifications. The selection,
training, and qualification programs for personnel performing work at or
managing the facility, activity, or operation that is starting or restarting
have been established, documented, and effectively implemented, and they
meet the requirements of DOE O 426.2, Personnel Selection, Training,
Qualification, and Certification Requirements for DOE Nuclear Facilities.
Training and qualification requirements for each position encompass the
range of assigned duties and activities.
Modifications to the facility, process, or system have been reviewed for
potential impacts on training and qualifications. Training has been
performed to incorporate all aspects of these changes.
(9) Quality Assurance. A contractor Quality Assurance Program (QAP)
meeting the requirements of 10 CFR Part 830 is in place and has been
approved by DOE. The Quality Assurance (QA) criteria described in the
QAP have been implemented via the contractor’s QA Program and
integrated with other SMPs. If applicable, the contractor has submitted to
DOE their basis of the graded approach used to implement nuclear
safety requirements.
(10) Radiation Protection. A Radiation Protection Program compliant with
10 CFR Part 835, Occupational Radiation Protection, regulations has been
documented, approved by DOE, and implemented.
DOE O 425.1F Attachment 4 – Federal Employees and Contractors
08-05-2026 Page 4-5
(11) Startup/Restart Startup Plan. An adequate startup plan (if applicable) has
been developed that includes plans for graded operations and testing after
startup or resumption to simultaneously confirm operability of equipment,
the viability of procedures, description of compensatory measures required
during the approach to full operations, and the performance and
knowledge of the operators. The plans should indicate validation
processes for equipment, procedures, and operators after startup or
resumption of operations, including any required restrictions and
additional oversight.
(12) Safety and Health. Other SMPs identified in the SB or FAs deemed
important to the safety and protection of workers, the public, and the
environment are documented, implemented, and maintained. This may
include, but is not limited to, areas such as environmental protection;
safeguards and security; waste management; and transportation
and packaging.
(13) Federal Qualifications (DOE Only). The personnel at the DOE Field
Element assigned responsibilities for providing direction and guidance to
the contractor and those individuals assigned oversight responsibilities
(including facility representatives) within the scope of the RR, possess
appropriate qualification, knowledge and competence to perform
those functions.
(14) DOE Management System (DOE Only). DOE Field Element management
systems for oversight of facility operations, such as oversight and
assessment programs, facility representatives, technical qualification
program, corrective action management system, and quality assurance
programs, are adequate.
DOE O 425.1F Attachment 5 – Federal Employees and Contractors
08-05-2026 Page 5-1
ATTACHMENT 5
DEFINITIONS
This Attachment provides information applicable to contracts in which the Attachment 1,
Contractor Requirements Document, is inserted. This Attachment defines the terms used in and
pertinent to this Order. Additional definitions can be found in DOE-STD-3006-2010, Planning
and Conducting Readiness Reviews.
Section 13
1. Core Requirement (CR). A fundamental area or topic evaluated during a Readiness
Review (RR). CRs verify the readiness of personnel, procedures, programs, and
equipment within the scope of the RR to safely start or restart a nuclear facility, activity
or operations. The CRs are aligned according to specific functional areas/safety
management programs. See Attachment 4 for a detailed description of CRs.
2. Line Management. Refers the unbroken chain of responsibility that extends from the
Secretary of Energy to the Deputy Secretary, to the Secretarial Officers who set program
policy and plans and develop assigned programs, to the program and Field Element
Managers, and to the contractors and subcontractors who are responsible for execution of
these programs.
3. Finding. Nonconformance with a stated requirement that represents either: (1) a
systematic failure to establish or implement an adequate program or control or (2) a
failure that could result in unacceptable impact on the safety of personnel, the facility, the
general public, or the environment during nuclear operations. Findings are categorized as
either pre-start or post-start (DOE-STD-3006-2010, Planning and Conducting Readiness
Reviews, includes pre- and post-start finding screening criteria):
a. Pre-start finding. A finding that reflects a programmatic or implementation
deficiency that requires corrective action to ensure operations are conducted
safely when started.
b. Post-start finding. A finding that requires corrective action to mitigate longer-
term concerns or programmatic deterioration.
4. New Nuclear Facility. This is a reactor or a nonreactor nuclear facility where an activity
is initiated for or on behalf of DOE that includes any related area, structure, facility, or
process to the extent necessary to ensure proper implementation of the requirements
established in 10 CFR 830, Nuclear Safety Management. The term refers to an entire
new facility (or conversion of an existing non-nuclear facility to a nuclear mission)
devoted to the operation and maintenance of a new program activity, which is generally
covered by a unique Documented Safety Analysis.
5. Nuclear Operations. As used in this Order, nuclear operations means nuclear facilities,
operations, and/or activities that fall within the scope of this Order.
Attachment 5 – Federal Employees and Contractors DOE O 425.1F
Page 5-2 08-05-2026
6. Prerequisites. A set of specific, measurable actions or conditions, that the RP has
included as part of the scope of the RR. The prerequisites, when completed, provide
assurance that readiness has been achieved. The prerequisites should include verification
of engineering reviews, safety-basis implementation, procedures, training, system
operability, and integrated testing. The prerequisites are to be completed prior to the start
of the respective RR or have compensatory measures that have been documented
and approved.
7. Program work. Work in a reactor or non-reactor nuclear facility that is accomplished to
further the goals of the facility mission or the program for which the facility is operated.
Program work may include deactivation and decommissioning or environmental
restoration activities when that is the mission of the facility. Program work is not
accomplished when an operational facility is shut down. Program work does not include
work that would be required to maintain the facility in a safe shutdown condition,
minimize radioactive material storage, or accomplish modifications and correct
deficiencies required before program work can resume.
Section 14
8. Restart. The resumption of program work. Restarts requiring an RR can occur in
operating facilities if the activity or operation to be resumed meets RR requirements. A
restart may be required even if the same program work is ongoing in another portion of
the operating facility.
9. Scope. The overall magnitude of the RR. This is defined by the physical breadth and
depth of the facilities, activity, or operation to be started/restarted, the breadth of CRs
selected, and the depth of evaluation of these CRs during the RR.
10. Shutdown. (1) A situation in which a reactor is taken subcritical, either manually or
automatically, to a safe shutdown condition; (2) a condition in which a non-reactor
nuclear facility, activity or operation ceases; or (3) a condition in which a programmatic
nuclear operation or activity ceases, but the structure containing the process may
remain operational (i.e., not shut down). In a shutdown condition, a facility must still
meet all applicable technical safety requirements and environmental, safety, and
health requirements.
A shutdown condition does not exist if all the following apply:
a. Safety Class and Safety Significant SSCs are operable and have been maintained
via an effective maintenance and surveillance program;
b. Operator and support staff knowledge, skills, and qualifications are maintained
through an approved training and proficiency program;
c. Operating, alarm response, and abnormal/emergency procedures are current;
d. Configuration management and safety basis controls (including TSRs) are fully
implemented; and
DOE O 425.1F Attachment 5 – Federal Employees and Contractors
08-05-2026 Page 5-3
e. Existing performance gaps affecting operational readiness are identified and
mitigated through compensatory actions and tracked in an approved corrective
action management process.
11. Startup Approval Authority (SAA). The line manager is designated in accordance with
Attachment 3 of this Order to authorize the start of nuclear operations when all
requirements of the Order have been met. The SAA may range from a Senior Contractor
Official to the Secretary of Energy.