DOE O 425.1B, Startup and Restart of Nuclear Facilities
Functional areas: Requires Crosswalk When Revised, Work Processes
To establish the requirements for the Department of Energy, including the National Nuclear Security Administration (NNSA), for start up of new nuclear facilities and for the restart of existing nuclear facilities
that have been shut down.
Cancels DOE O 425.1A. Canceled by DOE O 425.1C.
Supersedes:
DOE O 425.1A, Startup and Restart of Nuclear Facilities on Dec 21, 2000
Superseded By:
DOE O 425.1C, Startup and Restart of Nuclear Facilities on Mar 13, 2003
Version history and related documents
Superseded by
A newer version replaces this document.
- DOE O 425.1CStartup and Restart of Nuclear Facilities (Mar 13, 2003)
Supersedes
Earlier documents this one replaced.
- DOE O 425.1AStartup and Restart of Nuclear Facilities (Dec 21, 2000)
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
DISTRIBUTION: INITIATED BY:
All Departmental Elements Office of Environment, Safety and Health
DOE O 425.1B
Approved: 12-21-00
U.S. Department of Energy ORDER
Washington, D.C.
SUBJECT: STARTUP AND RESTART OF NUCLEAR FACILITIES
1. OBJECTIVE. To establish the requirements for the Department of Energy, including the
National Nuclear Security Administration (NNSA), for startup of new nuclear facilities and
for the restart of existing nuclear facilities that have been shut down. Nuclear facilities are
activities or operations that involve radioactive and/or fissionable materials in such form or
quantity that a nuclear hazard potentially exists to the employees or the general public. The
requirements specify a readiness review process that must, in all cases, demonstrate that it
is safe to start (or restart) the applicable facility. The facility must be started (or restarted)
only after documented independent reviews of readiness have been conducted and the
approvals specified in this Order have been received. The readiness reviews are not
intended to be tools of line management to achieve readiness. Rather, the readiness reviews
provide an independent confirmation of readiness to start or restart operations.
2. CANCELLATION. DOE O 425.1A, STARTUP AND RESTART OF NUCLEAR
FACILITIES, dated 12-28-98. Cancellation of an Order does not, by itself, modify or
otherwise affect any contractual obligation to comply with such an Order. Canceled Orders
incorporated by reference in a contract remain in effect until the contract is modified to
delete the reference to the requirements in the canceled Orders.
3. APPLICABILITY.
a. DOE Elements, including the NNSA. This Order is applicable to DOE and the NNSA
within the provisions and restrictions of Title 32 of the National Defense
Authorization Act (NDAA) for Fiscal Year 2000, Public Law 106-65 (the “NNSA
Act”). Except for the exclusions in paragraph 3c, below, this Order applies to all
nuclear facilities classified as hazard categories 1, 2, or 3, including National Nuclear
Security Administration (NNSA) facilities.
b. Contractors. The Contractor Requirements Document (CRD), Attachment 1, sets
forth requirements to be applied to contractors awarded contracts for the operation
and management of a DOE-owned or -leased facility, including NNSA facilities.
Contractor compliance with the CRD is required to the extent set forth in a contract.
Contractors must be directed to continue to comply with the requirements of Orders
canceled by this Order until their contracts are modified to delete the reference to the
requirements of the canceled Orders.
2 DOE O 425.1B
12-21-00
c. Exclusions.
(1) Activities regulated through a license by the Nuclear Regulatory Commission
(NRC) or a state under an agreement with NRC, including activities certified by
NRC under section 1701 of the Atomic Energy Act.
(2) Activities conducted under the authority of the Director, Naval Nuclear
Propulsion Program, pursuant to Executive Order 12344, in force under Public
Laws 98-525 and 106-65.
(3) Activities regulated by the Department of Transportation pursuant to 49 CFR
173.7(b).
Section 2
4. REQUIREMENTS. For NNSA facilities, “NNSA line management” is applied wherever
“DOE line management” or similar phrases are invoked in conjunction with a requirement
or action. Direction and control of requirements pertinent to NNSA facilities must fall under
cognizant NNSA management, organizations, and activities, consistent with the NNSA Act.
DOE-STD-3006-00, Planning and Conduct of Operational Readiness Reviews, provides
guidance on approaches and methods approved as acceptable for implementing the
requirements of this Order. Other approaches and methods may be used provided they are
justified, documented, and approved as being in accordance with the requirements of this
Order by the authorization authority for startup or restart.
a. General.
(1) Operational Readiness Review. DOE line management must determine (and
ensure that contractor management determines) if Operational Readiness
Reviews are required for startup or restart of nuclear facilities using the
requirements given below. DOE must conduct (and ensure that contractors
conduct) an Operational Readiness Review in accordance with this Order when
any of the following conditions occur:
(a) Initial startup of a new hazard category 1, 2, or 3 nuclear facility.
(b) Restart after a DOE management official directs the unplanned shutdown
of a nuclear facility for safety or other appropriate reasons.
(c) Restart after an extended shutdown for hazard categories 1 and 2 nuclear
facilities. [Extended shutdown for a hazard category 1 nuclear facility is 6
months. Extended shutdown for a hazard category 2 nuclear facility is 12
months.]
(d) Restart of hazard categories 1 and 2 nuclear facilities after substantial
process, system, or facility modifications. [The restart authority must
determine if the modifications are substantial based on the impact of the
DOE O 425.1B 3
12-21-00
changes on the safety basis and the extent and complexity of changes; this
would not necessarily be determined by the Unreviewed Safety Question
(USQ) process.]
(e) Restart after a nuclear facility shutdown because of operations outside the
safety basis.
(f) When deemed appropriate by DOE management officials, including
restarts of hazard category 3 nuclear facilities.
(2) Readiness Assessment. For restarts of nuclear facilities not requiring an
Operational Readiness Review, as defined in this Order, DOE line management
must evaluate (and ensure that contractor management evaluates) the need for
performing a Readiness Assessment prior to restart. This includes the startup or
restart of program work associated with operating facilities when the new or
restarted program work does not require DOE approval of changes to facility
limits or requirements as stated in Operational Safety Requirements/Technical
Safety Requirements (OSRs/TSRs), Basis for Interim Operations/Safety
Analysis Reports (BIO/SARs), or other equivalent authorization basis
documents. When a Readiness Assessment is required, operations offices must
develop procedures and ensure that the contractors use these procedures to gain
operations office approval of the startup or restart of nuclear facilities. If a
Readiness Assessment is not to be performed, the contractor’s standard
operating procedures for startup or restart will be used. Other requirements for
Readiness Assessments are provided in paragraph 4c, below.
(3) Authorization Authority. For nuclear facility startup or restart actions, the
authorization authority for startup or restart approval must be determined by the
following.
Section 3
(a) For initial startups of new hazard categories 1 and 2 nuclear facilities, the
Secretary of Energy (or designee) must approve startup. For initial
startups of new hazard category 3 nuclear facilities, the cognizant
Secretarial Officer (or designee) must approve startup. If other DOE
Orders require a higher level of startup authorization than this Order, the
official described in this Order will recommend startup to the higher-level
official.
(b) For shutdowns directed by a DOE management official for safety or other
appropriate reasons, approval to restart must be granted by an official of a
level commensurate with the official ordering the shutdown, unless a
higher level is designated by the cognizant Secretarial Officer.
4 DOE O 425.1B
12-21-00
(c) For extended shutdowns of hazard category 1 nuclear facilities, the
cognizant Secretarial Officer must approve restart. For extended
shutdowns of hazard category 2 nuclear facilities, the cognizant Secretarial
Officer (or designee) must approve restart.
(d) For shutdowns because of substantial facility modifications of hazard
category 1 nuclear facilities, the cognizant Secretarial Officer must approve
restart. For such shutdowns of hazard category 2 nuclear facilities, the
cognizant Secretarial Officer (or designee) must approve restart.
(e) For facility shutdowns due to operations outside the safety basis, the
official approving restart must be commensurate with the approval
authority for the safety basis. If the safety basis was approved by a
Headquarters official, the cognizant Secretarial Officer (or designee) must
approve restart. If the safety basis was approved by a field official, the
operations office manager (or designee) must approve restart.
(f) For startups or restarts of nuclear facilities for which Operational
Readiness Reviews were required because a DOE official deemed it
appropriate, the official approving startup or restart must be of a level
commensurate with the official directing the review. If a Headquarters
official directed an Operational Readiness Review to be performed, the
cognizant Secretarial Officer (or designee) must approve the startup or
restart. If a field official directed an Operational Readiness Review, the
operations office manager (or designee) must approve the startup or
restart.
(4) Startup Notification Report. DOE line management procedures must require the
contractor to prepare Startup Notification Reports (SNRs). SNRs must be
submitted at a periodicity specified by DOE (recommended to be quarterly).
Each SNR must project ahead at least 1 year and update information from
previous periods for startups that have not yet occurred and add information for
each startup or restart that has been identified since the last report. The SNR is
to be approved by DOE. The procedures should require the following elements.
(a) Minimum information to be included in the SNR for each startup or restart
should include—
(1) a brief description of the facility or program work;
(2) reason for non-operation (e.g., maintenance or modification outage,
no program work, new facility, shutdown for safety concerns, etc.);
DOE O 425.1B 5
12-21-00
(3) the approximate date operations were last conducted (for restarts)
and the projected date for the startup;
(4) proposed type of readiness review;
(5) basis or justification for proposed type of readiness review;
(6) proposed authorization authority.
Section 4
(b) Each SNR should be reviewed and approved by DOE field office
management. If the startup authority resides with the Program Secretarial
Officer (PSO), the field office management should comment and make a
recommendation regarding approval.
(c) Each SNR, including the field office comments and actions, must be
forwarded to the PSO, the Office of Oversight (EH-2), and the site Lead
Program Secretarial Officer and/or cognizant Secretarial Officer, as
appropriate.
(d) Contractor readiness review action to start or restart operations should not
commence until the DOE authorization authority has approved the
proposed readiness review process.
(e) Every startup or restart of a nuclear operation—other than routine
resumption of operations after a short, planned interruption—should be
included in the SNR. These startups, requiring review, should be started or
restarted using an Operational Readiness Review or properly scoped
Readiness Assessment, as appropriate. Other routine resumptions of
operations can be conducted without a readiness review using normal
contractor operating procedures for the facility or activity. Contractor
routine procedures should not be developed for the purpose of avoiding a
properly scoped Readiness Assessment.
b. Requirements Applicable to Startups or Restarts of Nuclear Facilities Involving
Operational Readiness Reviews. (These requirements are listed sequentially.)
(1) Operational Readiness Review Documentation. For Operational Readiness
Reviews, DOE line management must require contractors to prepare the
following documents: startup/restart notification reports, plans of action,
Operational Readiness Review implementation plans, and final reports. DOE
line management must prepare its plans of action and ensure the Operational
Readiness Review team leaders prepare Operational Readiness Review
implementation plans and final reports. The resolution of all findings from the
Operational Readiness Reviews must be documented and maintained with the
plans of action, implementation plans, and final reports.
6 DOE O 425.1B
12-21-00
(2) Breadth of Operational Readiness Review. DOE line management must develop
(and ensure the contractor develops) the breadth of the Operational Readiness
Review and document it in each plan of action. A minimum set of core
requirements, as defined in paragraph 4d, below, must be addressed when
developing the breadth of the Operational Readiness Review. The plan of action
may reference a timely, independent review that addressed the requirement in a
technically satisfactory manner to justify not performing further evaluation of a
core requirement or portion thereof. During the Operational Readiness Review,
the breadth may be expanded by the Operational Readiness Review team, if
appropriate.
(3) Operational Readiness Review Plan of Action, Approval, and Content. The
contractor and DOE Operational Readiness Review plans of action must be
approved by the authorization authority defined in paragraphs 4a(3)(a) through
4a(3)(f). DOE line management must ensure the contractor’s plan of action
specifies the prerequisites for starting the responsible contractor’s Operational
Readiness Review. The prerequisites must address each minimum core
requirement of paragraph 4d determined to be applicable when developing the
scope of the Operational Readiness Review. The DOE plan of action must
specify additional prerequisites, such as certification of readiness to oversee
facility operations by operations office and Headquarters management. The
DOE and contractor plans of action must be provided to the Deputy Assistant
Secretary for Oversight for review and comment.
Section 5
(4) Operational Readiness Review Teams.
(a) DOE line management must appoint (and ensure that contractor
management appoints) Operational Readiness Review teams in accordance
with the following qualifications and training requirements:
1 technical knowledge of the area assigned for evaluation, including
experience working in the technical area;
2 knowledge of performance-based assessment processes and
methods; and
3 knowledge of facility-specific information.
(b) The Operational Readiness Review teams must not include as senior
members (including team leader) individuals from offices assigned direct
line management responsibility for the work being reviewed; any
exceptions require approval of the authorization authority. Additionally,
no Operational Readiness Review team member should review work for
which he or she is directly responsible.
DOE O 425.1B 7
12-21-00
(c) The Operational Readiness Review team leaders must determine and
document qualifications of Operational Readiness Review team members.
(5) Criteria and Review Approaches. DOE line management requires the DOE
Operational Readiness Review team to determine (and ensures that the
contractor’s Operational Readiness Review team determines) the criteria and
review approaches to be used for their review based on the approved breadth
given in their plan of action. DOE line management must also ensure that the
team (both DOE and contractor) documents the criteria and review approaches
in their Operational Readiness Review Implementation Plan.
(6) Approve and Use Implementation Plans. DOE line management requires that
the DOE Operational Readiness Review team leader approves (and ensures that
the contractor’s Operational Readiness Review team leader approves) their
respective implementation plans and uses the implementation plans to conduct
the Operational Readiness Reviews. DOE line management requires that the
DOE Implementation Plan be provided to the Deputy Assistant Secretary for
Oversight for review and comment. DOE line management must also require
the contractor to provide its Operational Readiness Review Implementation Plan
to the Deputy Assistant Secretary for Oversight for review and comment.
(7) Certification and Verification.
(a) The prerequisites for starting the DOE Operational Readiness Review are
the following.
1 DOE line management has received correspondence from the
responsible contractor certifying that the facility is ready for startup
or restart and this has been verified by the contractor Operational
Readiness Review.
2 DOE line management has verified that the contractor’s preparations
for startup or restart have been completed.
3 DOE line management has certified that it meets the DOE plan of
action that includes, as a minimum, the applicable DOE-specific core
requirements given in paragraph 4d, below.
(b) At the start of the DOE Operational Readiness Review, all actions required
for startup or restart must be complete, with the exception of a manageable
list of open prestart findings. The prestart findings must have a well-
defined schedule for closure to allow the DOE Operational Readiness
Review team to review the results of the closure process. In the
certification and verification process, DOE operations office line
management must document their actions to verify operations office and
8 DOE O 425.1B
12-21-00
Section 6
contractor readiness, including review of closure of contractor Operational
Readiness Review findings, assessments of completion of defined
prerequisites, and other assessments performed to ascertain readiness.
Specific events significant to the startup and restart process that occur prior
to the formal commencement of the DOE Operational Readiness Review
(e.g., site emergency response drills, integrated equipment testing, etc.)
may be reviewed by the DOE Operational Readiness Review team when
they are conducted.
(8) Final Report.
(a) Upon completion of the contractor or DOE Operational Readiness Review,
DOE line management must ensure the Operational Readiness Review
team leader prepares and approves a final report. The final report must
document the results of the Operational Readiness Review and make a
conclusion as to whether startup or restart of the nuclear facility can
proceed safely. Each Operational Readiness Review final report must state
whether the facility has established the following: an agreed-upon set of
requirements to govern safe operations of the facility; that this set of
requirements has been formalized with DOE through the contract or other
enforceable mechanism; that these requirements have been appropriately
implemented in the facility, or appropriate compensatory measures,
formally approved, are in place during the period prior to full
implementation; and that, in the opinion of the Operational Readiness
Review team, adequate protection of the public health and safety, worker
safety, and the environment has been maintained.
This conclusion must be based on—
1 review of the program to document conformance with the agreed-
upon set of requirements, including a process to address new
requirements, and
2 extensive use of references to the established requirements in the
Operational Readiness Review documentation.
(b) Additionally, there must be a “lessons learned” section of the final report
that may relate to design, construction, operation, and decommissioning of
similar facilities and future Operational Readiness Review efforts.
(c) The core requirements, in aggregate, address many of the core functions
and guiding principles of an integrated safety management system. The
final report should include a statement regarding the team leader's
assessment of the adequacy of the implementation of those functions and
principles, already addressed by the Operational Readiness Review, at the
facility undergoing the review.
DOE O 425.1B 9
12-21-00
(9) Submit Final Report. The final report must be submitted to the authorization
authority to be used as a basis to grant approval of the startup or restart of the
nuclear facility. A copy of the final report must be provided to the Deputy
Assistant Secretary for Oversight for review and comment.
(10) Closure of Findings. The mechanism for closure of DOE Operational Readiness
Review findings must include the following:
(a) Development of plans of action approved by DOE to correct the findings.
Action plans must provide evaluation of any overall programmatic
deficiencies and root causes.
(b) Documentation of completion of response actions responding to the
findings in a closure package. Closure packages must include a brief
description of actual corrective actions taken and reasons for concluding
that closure has been achieved.
(c) DOE verification of closure of prestart findings. The organization verifying
the closure will be designated by the authorization authority.
Section 7
(11) Approval. DOE line management must ensure the contractor has satisfactorily
resolved all prestart findings of the DOE Operational Readiness Review prior to
startup or restart of the facility. The authorization authority may approve startup
or restart after prestart findings are resolved.
c. Requirements Applicable to Startups or Restarts of Nuclear Facilities Involving
Readiness Assessments.
(1) Readiness Assessment Procedures. Operations offices must establish
procedures for their offices (and ensure the contractor establishes procedures)
that specify when a Readiness Assessment is required and that provide
requirements for conducting readiness assessments, including procedures by
which contractors will gain operations office approval for the startup or restart of
nuclear facilities. The procedures must require submittal of a startup notification
report to obtain approval to use a Readiness Assessment and preparation of a
formal plan of action that includes, as a minimum, the breadth of the
assessment, team leader designation, and prerequisites for the assessment; the
startup notification report and plan of action must be approved by the
authorization authority. A copy of the plan of action should also be provided to
the Deputy Assistant Secretary for Oversight. For shutdowns directed by
contractor management, these procedures may indicate that, except for serious
safety reasons, the contractor management may be the authorization authority.
10 DOE O 425.1B
12-21-00
1 The italicized numbers in parentheses following each core requirement [e.g., (CR#3)] are the numbers of the core
requirements as they appeared in the previous version of this Order, DOE O 425.1A.
(2) Graded Approach. The operations office’s Readiness Assessment procedures
must specify (and DOE line management must ensure the contractor’s
Readiness Assessment procedures specify) a graded approach to the tenets of
operational readiness requirements specified in this Order. The procedures
should indicate that the Readiness Assessment may be as short and simple as a
restart check procedure, or that it may approach the breadth and depth of an
Operational Readiness Review, depending on the causes and duration of the
shutdown and the modifications accomplished during the shutdown. In view of
the flexibility to fit the rigor of the Readiness Assessment to the circumstances
of the startup situation, it should not be necessary for contractors to develop
readiness review processes similar to Readiness Assessments but called
something different.
(3) Approval. The authorization authority, the operations office manager, or the
manager’s designee may approve startup or restart after prestart findings are
corrected.
d. Minimum Core Requirements. Each of the minimum core requirements listed below
must be addressed when developing an Operational Readiness Review to achieve the
necessary breadth. Justification must be provided in the plan of action, which must
be prepared in accordance with paragraphs 4b(2) and (3), above, if it is determined
that a particular core requirement will not be reviewed. The plan of action may
reference a timely, independent review that addressed the requirements in a
technically sound manner to justify not performing further evaluation of a core
requirement during an Operational Readiness Review. An appropriate set of the core
requirements should be selected when developing the breadth of a Readiness
Assessment. The purpose of these core requirements is to assess the readiness of
facility personnel, programs, and equipment to conduct work safely; hence, these core
requirements are directly related to the seven guiding principles of integrated safety
management. The core requirements apply to both DOE and the contractor as
appropriate, unless otherwise noted.
Section 8
Guiding Principle #1 – Line management is responsible for the protection of
employees, the public, and the environment. Line management includes those
contractor and subcontractor employees managing or supervising employees
performing work.
(1) Line management has established programs to ensure safe accomplishment of
work (the authorization authority should identify in the plan of action those
specific infrastructure programs of interest for the startup or restart). Personnel
exhibit an awareness of public and worker safety, health, and environmental
protection requirements and, through their actions, demonstrate a high-priority
commitment to comply with these requirements. (CR #8) (CR #14)1
DOE O 425.1B 11
12-21-00
Guiding Principle #2 – Clear and unambiguous lines of authority and
responsibility for ensuring ES&H are established and maintained at all
organizational levels.
(2) Functions, assignments, responsibilities, and reporting relationships [including
those between the line operating organization and Environment, Safety and
Health (ES&H) support organizations] are clearly defined, understood, and
effectively implemented with line management responsibility for control of
safety. (CR #11)
Guiding Principle #3 – Personnel possess the experience, knowledge, skills,
and abilities that are necessary to discharge their responsibilities.
(3) The selection, training, and qualification programs for operations and operations
support personnel have been established, documented, and implemented. The
selection process and applicable position-specific training for managers ensure
competence commensurate with responsibilities. (The training and qualification
program encompasses the range of duties and activities required to be
performed.) (CR #2)(CR#19)
(4) Level of knowledge of managers, operations, and operations support personnel
is adequate based on reviews of examinations and examination results and
selected interviews of managers, operating, and operations support personnel.
(CR #3) (CR #19)
(5) Modifications to the facility have been reviewed for potential impacts on training
and qualification. Training has been performed to incorporate all aspects of
these changes. (CR #18b)
Guiding Principle #4 – Resources are effectively allocated to address ES&H,
programmatic, and operational considerations. Protecting employees, the
public, and the environment is a priority whenever activities are planned and
performed.
(6) Sufficient numbers of qualified personnel are available to conduct and support
operations. Adequate facilities and equipment are available to ensure
operational support services are adequate for operations. (Such support services
include operations, training, maintenance, waste management, environmental
protection, industrial safety and hygiene, radiological protection and health
physics, emergency preparedness, fire protection, quality assurance, criticality
safety, and engineering). (CR #8) (CR #13)
12 DOE O 425.1B
12-21-00
Guiding Principle #5 – Before work is performed, the associated hazards are
evaluated and an agreed-upon set of standards and requirements is
established which, if properly implemented, provide adequate assurance that
employees, the public, and the environment are protected from adverse
consequences.
Section 9
(7) Facility safety documentation is in place and has been implemented that
describes the “safety envelope” of the facility. The safety documentation should
characterize the hazards/risks associated with the facility and should identify
preventive and mitigating measures (systems, procedures, administrative
controls, etc.) that protect workers and the public from those hazards/risks.
Safety structures, systems, and components (SSCs) are defined and a system to
maintain control over their design and modification is established. (CR #4)
(8) A program is in place to confirm and periodically reconfirm the condition and
operability of safety SSCs. This includes examinations of records of tests and
calibration of these systems. The material condition of all safety, process, and
utility systems will support the safe conduct of work. (CR #5)
(9) The facility systems and procedures, as affected by facility modifications, are
consistent with the description of the facility, procedures, and accident analysis
included in the safety basis. (CR #15)
Guiding Principle #6 – Administrative and engineering controls to prevent
and mitigate hazards are tailored to the work being performed and associated
hazards. Emphasis should be on designing the work and/or controls to reduce
or eliminate the hazards and to prevent accidents and unplanned releases and
exposures.
(10) Adequate and correct procedures and safety limits are in place for operating the
process systems and utility systems that include revisions for modifications that
have been made to the facility. (CR #1) (CR #18a)
(11) A routine drill program and emergency operations drill program, including
program records, have been established and implemented. (CR #9)
(12) An adequate startup or restart program has been developed that includes plans
for graded operations and testing after startup or resumption to simultaneously
confirm operability of equipment, the viability of procedures, and the
performance and knowledge of the operators. The plans should indicate
validation processes for equipment, procedures, and operators after startup or
resumption of operations including any required restrictions and additional
oversight. (CR #10)
DOE O 425.1B 13
12-21-00
(13) The formality and discipline of operations is adequate to conduct work safely,
and programs are in place to maintain this formality and discipline (e.g.,
DOE 5480.19). (CR #12)
Guiding Principle #7 – The conditions and requirements to be satisfied for
operations to be initiated and conducted are established and agreed-upon by
DOE and the contractor. These agreed-upon conditions and requirements
are requirements of the contract and binding upon the contractor. The extent
of documentation and level of authority for agreement shall be tailored to the
complexity and hazards associated with the work and shall be established in a
Safety Management System.
(14) Formal agreements between the operating contractor and DOE have been
established via the contract or other enforceable mechanism to govern the safe
operations of the facility. A systematic review of the facility’s conformance to
these requirements has been performed. These requirements have been
implemented in the facility, or compensatory measures are in place and formally
agreed to during the period of implementation. The compensatory measures
and the implementation period are approved by DOE. (CR #7)
Section 10
(15) A feedback and improvement process has been established to identify, evaluate,
and resolve deficiencies and recommendations made by oversight groups,
official review teams, audit organizations, and the operating contractor
(e.g., DOE P 450.5). (CR #6)
Additional DOE Oversight Requirements include the following.
(16) The technical and managerial qualifications of those personnel at the DOE field
organization and at DOE Headquarters who have been assigned responsibilities
for providing direction and guidance to the contractor, including the Facility
Representatives, are adequate (DOE Readiness Review only). (CR #16)
(17) The breadth, depth, and results of the responsible contractor Readiness Review
are adequate to verify the readiness of hardware, personnel, and management
programs for operations (DOE Operational Readiness Review only). (CR #17)
(18) DOE operations office oversight programs, such as occurrence reporting,
Facility Representative, corrective action, and quality assurance programs, are
adequate (DOE Readiness Review only). (CR #20)
e. Exemptions. Requirements for exemptions are provided in DOE O 251.1A,
DIRECTIVES SYSTEM.
f. Information Management Program. Requirements for maintenance and disposition of
Federal records, such as those pertaining to Operational Readiness Reviews or
Readiness Assessments, are provided under the general guidance of DOE O 200.1,
14 DOE O 425.1B
12-21-00
INFORMATION MANAGEMENT PROGRAM, dated 9-30-96. The disposition,
including destruction, of Federal records must be in accordance with—
(1) the General Records Schedules, as published by the National Archives and
Records Administration (NARA), or
(2) DOE records disposition schedules (Standard Forms 115) as approved by
NARA.
Consult the cognizant site records officer or cognizant DOE operations office records
officer for guidance.
5. RESPONSIBILITIES.
a. DOE and NNSA Line Management.
(1) Establish procedures (and ensure contractors establish procedures) as necessary
to manage startup and restart actions in accordance with the requirements of this
Order.
(2) Exercise the delegation authority and document all delegations of authority
made under the provisions granted by this Order.
b. Heads of DOE Elements/Deputy Director, NNSA, must ensure that initiators of
procurement requests indicate in procurement requests if the requirements in the
CRD (Attachment 1) are to be applied to the award or subawards resulting from the
procurement request.
c. Assistant Secretary for Environment, Safety and Health. In addition to the general
Departmental responsibilities specified in DOE M 411.1, SAFETY MANAGEMENT
FUNCTIONS, RESPONSIBILITIES, AND AUTHORITIES MANUAL (the FRAM),
the Assistant Secretary for Environment, Safety and Health assigns the Deputy
Assistant Secretary for Oversight to exercise independent oversight of the startup and
restart process for nuclear facilities. This responsibility specifically entails the
following.
(1) In coordination with the PSO, perform independent reviews of startup and
restart activities as appropriate and provide results of these reviews to DOE
Operational Readiness Review team leaders, cognizant operations office
managers, and cognizant Secretarial Officers for resolution.
(2) Assess the PSO, operations office, and contractor procedures for startup or
restart of nuclear facilities and provide periodic reports to the Secretary on their
effectiveness.
DOE O 425.1B 15 (and 16)
12-21-00
Section 11
(3) In coordination with the PSO and the field office, perform independent review
of contractor SNRs and provide results of these reviews to cognizant operations
office managers and cognizant Secretarial Officers for resolution.
(4) Review and comment on contractor and DOE plans of action and
implementation plans for startup or restart of nuclear facilities for both readiness
assessment and Operational Readiness Reviews, including specification of
involvement in startup or restart activities proposed by the Office of Oversight
(EH-2).
(5) Review and comment on the Operational Readiness Review final report
recommendations regarding startup or restart to the DOE authorization
authority.
(6) Provide any dissenting opinion on the readiness of a facility to start up or restart
to DOE line management or the Secretary if a significant safety concern is not
being properly corrected.
(7) If requested by the Secretary, concur in the final decision to start up or restart a
nuclear facility.
6. CONTACT. Questions concerning this Order should be referred to the Director, Office of
Nuclear and Facility Safety Policy, at 301-903-3465.
BY ORDER OF THE SECRETARY OF ENERGY:
T.J. GLAUTHIER
Deputy Secretary
DOE O 425.1B Attachment 1
12-21-00 Page 1-1
CONTRACTOR REQUIREMENTS DOCUMENT
DOE O 425.1B, STARTUP AND RESTART OF NUCLEAR FACILITIES
1. DEPARTMENT OF ENERGY (DOE) and NATIONAL NUCLEAR SECURITY
ADMINISTRATION (NNSA) CONTRACTOR RESPONSIBILITIES. Contractors must
establish procedures as necessary to manage startup and restart actions in accordance with
this Contractor Requirements Document (CRD).
2. CONTRACTOR REQUIREMENTS. DOE-STD-3006-00, Planning and Conduct of
Operational Readiness Reviews, provides guidance on approaches and methods approved
as acceptable for implementing the requirements of this CRD. Other approaches and
methods may be used provided they are justified, documented, and approved as being in
accordance with the requirements of this CRD by the authorization authority for startup or
restart.
a. General.
(1) Operational Readiness Review. Contractor management must determine if
Operational Readiness Reviews are required for startup or restart of nuclear
facilities using the requirements given below. Contractors must conduct an
Operational Readiness Review when any of the following conditions occur.
(a) Initial startup of a new hazard category 1, 2, or 3 nuclear facility.
(b) Restart after a DOE management official directs the unplanned shutdown
of a nuclear facility for safety or other appropriate reasons.
(c) Restart after an extended shutdown for hazard categories 1 and 2 nuclear
facilities. [Extended shutdown for a hazard category 1 nuclear facility is 6
months. Extended shutdown for a hazard category 2 nuclear facility is 12
months.]
(d) Restart of hazard categories 1 and 2 nuclear facilities after substantial
process, system, or facility modifications. [The restart authority must
determine if the modifications are substantial based on the impact of the
changes on the safety basis and the extent and complexity of changes; this
would not necessarily be determined by the Unreviewed Safety Question
(USQ) process].
(e) Restart after a nuclear facility shutdown because of operations outside the
safety basis.
Attachment 1 DOE O 425.1B
Page 1-2 12-21-00
(f) When deemed appropriate by DOE management officials, including
restarts of hazard category 3 nuclear facilities.
Section 12
(2) Readiness Assessment. For restarts of nuclear facilities not requiring an
Operational Readiness Review, contractor management must evaluate the need
for performing a Readiness Assessment prior to restart. This includes the
startup or restart of program work associated with operating facilities when the
new or restarted program work does not require DOE approval of changes to
facility limits or requirements as stated in Operational Safety
Requirements/Technical Safety Requirements (OSRs/TSRs), Basis for Interim
Operations/Safety Analysis Reports (BIO/SARs), or other equivalent
authorization basis documents. When a Readiness Assessment is required, the
contractor must use procedures developed by the operations offices to gain
operations office approval of the startup or restart of nuclear facilities. If a
Readiness Assessment is not to be performed, the contractor’s standard
operating procedures for startup or restart will be used. Other requirements for
Readiness Assessments are provided in paragraph 2c, below.
(3) Authorization Authority. For nuclear facility startup or restart actions, the
contractor must determine the authorization authority for startup or restart
approval by the following.
(a) For initial startups of new hazard categories 1 and 2 nuclear facilities, the
Secretary of Energy (or designee) must approve startup. For initial
startups of new hazard category 3 nuclear facilities, the cognizant
Secretarial Officer (or designee) must approve startup. If other DOE
Orders require a higher level of startup authorization than this CRD, the
official described in this CRD will recommend startup to the higher level
official.
(b) For shutdowns directed by a DOE management official for safety or other
appropriate reasons, approval to restart must be granted by an official of a
level commensurate with the official ordering the shutdown unless a higher
level is designated by the cognizant Secretarial Officer.
(c) For extended shutdowns of hazard category 1 nuclear facilities, the
cognizant Secretarial Officer must approve restart. For extended
shutdowns of hazard category 2 nuclear facilities, the cognizant Secretarial
Officer, or designee, must approve restart.
(d) For shutdowns because of substantial facility modifications of hazard
category 1 nuclear facilities, the cognizant Secretarial Officer must approve
restart. For such shutdowns of hazard category 2 nuclear facilities, the
cognizant Secretarial Officer (or designee) must approve restart.
DOE O 425.1B Attachment 1
12-21-00 Page 1-3
(e) For facility shutdowns due to operations outside the safety basis, the
official approving restart must be commensurate with the approval
authority for the safety basis. If the safety basis was approved by a
Headquarters official, the cognizant Secretarial Officer (or designee) must
approve restart. If the safety basis was approved by a field official, the
operations office manager (or designee) must approve restart.
(f) For startups or restarts of nuclear facilities for which Operational
Readiness Reviews were required because a DOE official deemed it
appropriate, the official approving startup or restart must be of a level
commensurate with the official directing the review. If a Headquarters
official directed an Operational Readiness Review to be performed, the
cognizant Secretarial Officer (or designee) must approve the startup or
restart. If a field official directed an Operational Readiness Review, the
operations office manager (or designee) must approve the startup or
restart.
Section 13
(4) Startup Notification Report. The contractor procedures must provide for Startup
Notification Reports (SNRs). SNRs must be submitted at a periodicity specified
by DOE (recommended to be quarterly). Each SNR must project ahead at least
1 year and update information from previous periods for startups that have not
yet occurred and add information for each startup or restart that has been
identified since the last report. The SNR is to be approved by DOE. The
procedures should require the following elements.
(a) Minimum information to be included in the SNR for each startup or restart
should include—
(1) a brief description of the facility or program work;
(2) reason for non-operation (e.g., maintenance or modification outage,
no program work, new facility, shutdown for safety concerns, etc);
(3) the approximate date operations were last conducted (for restarts)
and the projected date for the startup;
(4) proposed type of readiness review;
(5) basis or justification for proposed type of readiness review;
(6) proposed authorization authority.
Attachment 1 DOE O 425.1B
Page 1-4 12-21-00
(c) Contractor readiness review action to start or restart operations should not
commence until the DOE authorization authority has approved the
proposed readiness review process.
(d) Every startup or restart of a nuclear operation other than routine
resumption of operations after a short, planned interruption should be
included in the SNR. These startups, requiring review, should be started or
restarted using an Operational Readiness Review or properly scoped
Readiness Assessment as appropriate. Other routine resumptions of
operations can be conducted without a readiness review using normal
contractor operating procedures for the facility or activity. Contractor
routine procedures should not be developed for the purpose of avoiding a
properly scoped Readiness Assessment.
b. Requirements Applicable to Startups or Restarts of Nuclear Facilities Involving
Operational Readiness Reviews. (These requirements are listed sequentially.)
(1) Operational Readiness Review Documentation. For Operational Readiness
Reviews, contractors must prepare the following documents: startup/restart
notification reports, plans of action, Operational Readiness Review
Implementation Plans, and final reports. The contractor’s line management must
prepare the plan of action, and the Operational Readiness Review team leader
must prepare the implementation plan and final report. The resolution of all
findings from the Operational Readiness Review must be documented and
maintained with the plan of action, implementation plan, and final report.
(2) Breadth of Operational Readiness Review. The contractor must develop the
breadth of the Operational Readiness Review and document it in the plan of
action. A minimum set of core requirements, as defined in paragraph 2d, below,
must be addressed when developing the breadth of the Operational Readiness
Review. The plan of action may reference a timely, independent review that
addressed the requirement in a technically satisfactory manner to justify not
performing further evaluation of a core requirement, or portion thereof, during
the Operational Readiness Review. The breadth may be expanded at a later time
by the Operational Readiness Review team, if appropriate.
Section 14
(3) Operational Readiness Review Plans of Action, Approval, and Content. The
contractor’s Operational Readiness Review plan of action must be approved by
the appropriate authorization authorities. The contractor’s plan of action must
specify the prerequisites for starting the responsible contractor’s Operational
Readiness Review; the prerequisites must address each core requirement of
paragraph 2d, below, determined to be applicable when developing the scope of
the Operational Readiness Review. The contractor plan of action must be
provided by the contractor to its respective field office for transmittal to the
Deputy Assistant Secretary for Oversight for review and comment.
DOE O 425.1B Attachment 1
12-21-00 Page 1-5
(4) Operational Readiness Review Teams.
(a) Contractor management must appoint Operational Readiness Review
teams in accordance with the following qualifications and training
requirements:
1 technical knowledge of the area assigned for evaluation, including
experience working in the technical area;
2 knowledge of performance-based assessment processes and
methods; and
3 knowledge of facility-specific information.
(b) The Operational Readiness Review team must not include as senior
members (including team leader) individuals from offices assigned direct
line management responsibility for the work being reviewed; any
exceptions require approval of the authorization authority. Additionally,
no Operational Readiness Review team member should review work for
which he or she is directly responsible.
(c) The Operational Readiness Review team leader must determine and
document qualifications of Operational Readiness Review team members.
(5) Criteria and Review Approaches. The contractor’s Operational Readiness
Review team must determine the criteria and review approaches to be used for
the review based on the approved breadth given in the plan of action and
document the criteria and review approaches in the Operational Readiness
Review Implementation Plan.
(6) Approve and Use Implementation Plans. The contractor’s Operational
Readiness Review team leader must approve the implementation plan and use it
to conduct the Operational Readiness Review. The implementation plan must
be provided by the contractor to its respective field office for transmittal to the
Deputy Assistant Secretary for Oversight for review and comment.
(7) Certification of Readiness. The contractor Operational Readiness Review
procedures (also applicable to Readiness Assessments) should include a
provision that prior to starting the independent Readiness Review (Operational
Readiness Review or Readiness Assessment), line management must certify that
all prerequisites specified in the plan of action have been met. (A manageable
list of open items may exist, as discussed in DOE O 425.1B, paragraph 4b(7)(b),
at the time the contractor readiness review starts).
Attachment 1 DOE O 425.1B
Page 1-6 12-21-00
(8) Certification and Verification. The responsible contractor must certify by
correspondence to DOE line management that the facility is ready to start or
restart and that this has been verified by the contractor Operational Readiness
Review.
(9) Final Report.
Section 15
(a) Upon completion of the contractor or DOE Operational Readiness Review,
DOE line management must ensure the Operational Readiness Review
team leader prepares and approves a final report. The final report must
document the results of the Operational Readiness Review and make a
conclusion as to whether startup or restart of the nuclear facility can
proceed safely. Each Operational Readiness Review final report must state
whether the facility has established the following: an agreed-upon set of
requirements to govern safe operations of the facility; that this set of
requirements has been formalized with DOE through the contract or other
enforceable mechanism; that these requirements have been appropriately
implemented in the facility, or appropriate compensatory measures,
formally approved, are in place during the period prior to full
implementation; and that, in the opinion of the Operational Readiness
Review team, adequate protection of the public health and safety, worker
safety, and the environment has been maintained.
This conclusion must be based on—
1 review of the program to document conformance with the agreed-
upon set of requirements, including a process to address new
requirements, and
2 extensive use of references to the established requirements in the
Operational Readiness Review documentation.
(b) Additionally, there must be a “lessons learned” section of the final report
that may relate to design, construction, operation, and decommissioning of
similar facilities and to future Operational Readiness Review efforts.
(c) The core requirements, in aggregate, address many of the core functions
and guiding principles of an integrated safety management system. The
final report should include a statement regarding the team leader’s
assessment of the adequacy of the implementation of those functions and
principles, already addressed by the Operational Readiness Review, at the
facility undergoing the review.
DOE O 425.1B Attachment 1
12-21-00 Page 1-7
(10) Submit Final Report. The final report must be submitted to the authorization
authority to be used as a basis to grant approval of the startup or restart of the
nuclear facility. A copy of the final report must be provided by the contractor to
its respective field office for transmittal to the Deputy Assistant Secretary for
Oversight for review and comment.
(11) Closure of Findings. The contractor’s mechanism for closure of DOE
Operational Readiness Review findings must include the following.
(a) Development of action plans, approved by DOE, to correct the findings.
Action plans must provide evaluation of any overall programmatic
deficiencies and root causes.
(b) Documentation of completion of response actions responding to the
findings in a closure package. Closure packages must include a brief
description of actual corrective actions taken and reasons for concluding
that closure has been achieved.
(12) Approval. The contractor must satisfactorily resolve all prestart findings of the
DOE Operational Readiness Review prior to startup or restart of the facility.
The authorization authority may approve startup or restart after prestart findings
are resolved.
c. Requirements Applicable to Startups or Restarts of Nuclear Facilities Involving
Readiness Assessments.
Section 16
(1) Readiness Assessment Procedures. The contractor must establish procedures
that specify when a Readiness Assessment is required and that provide
requirements for conduct of readiness assessments including procedures by
which contractors will gain operations office approval of the startup or restart of
nuclear facilities. The procedures must require submittal of a startup notification
report to obtain approval to use a Readiness Assessment and preparation of a
formal plan of action that includes, as a minimum, the breadth of the
assessment, team leader designation, and prerequisites for the assessment; the
startup notification report and plan of action must be approved by the
authorization authority. For shutdowns directed by contractor management,
these procedures may indicate that, except for serious safety reasons, the
contractor management may be the authorization authority.
(2) Graded Approach. Contractor Readiness Assessment procedures must specify
a graded approach to the tenets of operational readiness requirements specified
in this CRD. The procedures should indicate that the Readiness Assessment
may be as short and simple as a restart check procedure, or that it may approach
the breadth and depth of an Operational Readiness Review, depending on the
Attachment 1 DOE O 425.1B
Page 1-8 12-21-00
1 The italicized numbers in parentheses following each core requirement [e.g., (CR#3)] are the numbers of the core
requirements as they appeared in the previous version of DOE O 425.1A.
causes and duration of the shutdown and the modifications accomplished
during the shutdown. In view of the flexibility to fit the rigor of the Readiness
Assessment to the circumstances of the startup situation, it should not be
necessary for contractors to develop readiness review processes similar to
Readiness Assessments but called something different.
(3) Approval. The authorization authority, the operations office manager, or the
manager’s designee may approve startup or restart after prestart findings are
corrected.
d. Minimum Core Requirements. Each of the minimum core requirements listed below
must be addressed when developing the breadth of an Operational Readiness Review.
Justification must be provided in the plan of action, which must be prepared in
accordance with this CRD, paragraphs 2b(2) and (3), above, if it is determined that a
particular core requirement will not be reviewed. The plan of action may reference a
timely, independent review that addressed the requirements in a technically sound
manner to justify not performing further evaluation of a core requirement during an
Operational Readiness Review. An appropriate set of the core requirements should
be selected when developing the breadth of a readiness assessment. The purpose of
these core requirements is to assess the readiness of facility personnel, programs, and
equipment to conduct work safely; hence, these core requirements are directly related
to the seven guiding principles of integrated safety management.
Guiding Principle #1 – Line management is responsible for the protection of
employees, the public, and the environment. Line management includes those
contractor and subcontractor employees managing or supervising employees
performing work.
Section 17
(1) Line management has established programs to ensure safe accomplishment of
work (the authorization authority should identify in the plan of action those
specific infrastructure programs of interest for the startup or restart). Personnel
exhibit an awareness of public and worker safety, health, and environmental
protection requirements and, through their actions, demonstrate a high-priority
commitment to comply with these requirements. (CR #14) (CR #8)1
Guiding Principle #2 – Clear and unambiguous lines of authority and
responsibility for ensuring ES&H are established and maintained at all
organizational levels.
DOE O 425.1B Attachment 1
12-21-00 Page 1-9
(2) Functions, assignments, responsibilities, and reporting relationships [including
those between the line operating organization and Environment, Safety and
Health (ES&H) support organizations] are clearly defined, understood, and
effectively implemented with line management responsibility for control of
safety. (CR #11)
Guiding Principle #3 – Personnel possess the experience, knowledge, skills,
and abilities that are necessary to discharge their responsibilities.
(3) The selection, training, and qualification programs for operations and operations
support personnel have been established, documented, and implemented. The
selection process and applicable position-specific training for managers ensure
competence commensurate with responsibilities. (The training and qualification
program encompasses the range of duties and activities required to be
performed.) (CR #2) (CR#19)
(4) Level of knowledge of managers, operations, and operations support personnel
is adequate based on reviews of examinations and examination results and
selected interviews of managers, operating, and operations support personnel.
(CR #3) (CR #19)
(5) Modifications to the facility have been reviewed for potential impacts on training
and qualification. Training has been performed to incorporate all aspects of these
changes. (CR #18b)
Guiding Principle #4 – Resources are effectively allocated to address ES&H,
programmatic, and operational considerations. Protecting employees, the
public, and the environment is a priority whenever activities are planned and
performed.
(6) Sufficient numbers of qualified personnel are available to conduct and support
operations. Adequate facilities and equipment are available to ensure
operational support services are adequate for operations. (Such support services
include operations, training, maintenance, waste management, environmental
protection, industrial safety and hygiene, radiological protection and health
physics, emergency preparedness, fire protection, quality assurance, criticality
safety, and engineering). (CR #8) (CR #13)
Guiding Principle #5 – Before work is performed, the associated hazards are
evaluated and an agreed-upon set of standards and requirements is
established which, if properly implemented, provide adequate assurance that
employees, the public, and the environment are protected from adverse
consequences.
Attachment 1 DOE O 425.1B
Page 1-10 12-21-00
(7) Facility safety documentation is in place and has been implemented that
describes the “safety envelope” of the facility. The safety documentation should
characterize the hazards/risks associated with the facility and should identify
preventive and mitigating measures (e.g., systems, procedures, administrative
controls, etc.) that protect workers and the public from those hazards/risks.
Safety structures, systems, and components (SSCs) are defined and a system to
maintain control over their design and modification is established. (CR #4)
Section 18
(8) A program is in place to confirm and periodically reconfirm the condition and
operability of safety SSCs. This includes examinations of records of tests and
calibration of these systems. The material condition of all safety, process, and
utility systems will support the safe conduct of work. (CR #5)
(9) The facility systems and procedures, as affected by facility modifications, are
consistent with the description of the facility, procedures, and accident analysis
included in the safety basis. (CR #15)
Guiding Principle #6 – Administrative and engineering controls to prevent
and mitigate hazards are tailored to the work being performed and associated
hazards. Emphasis should be on designing the work and/or controls to reduce
or eliminate the hazards and to prevent accidents and unplanned releases and
exposures.
(10) Adequate and correct procedures and safety limits are in place for operating the
process systems and utility systems that include revisions for modifications that
have been made to the facility. (CR #1) (CR #18a)
(11) A routine drill program and emergency operations drill program, including
program records, have been established and implemented. (CR #9)
(12) An adequate startup or restart program has been developed that includes plans
for graded operations and testing after startup or resumption to simultaneously
confirm operability of equipment, the viability of procedures, and the
performance and knowledge of the operators. The plans should indicate
validation processes for equipment, procedures, and operators after startup or
resumption of operations, including any required restrictions and additional
oversight. (CR #10)
(13) The formality and discipline of operations is adequate to conduct work safely,
and programs are in place to maintain this formality and discipline (e.g.,
DOE 5480.19). (CR #12)
Guiding Principle #7 – The conditions and requirements to be satisfied for operations to
be initiated and conducted are established and agreed upon by DOE and the contractor.
DOE O 425.1B Attachment 1
12-21-00 Page 11 (and Page 12)
These agreed-upon conditions and requirements are requirements of the contract and
binding on the contractor. The extent of documentation and level of authority for
agreement shall be tailored to the complexity and hazards associated with the work and
shall be established in a Safety Management System.
(14) Formal agreements between the operating contractor and DOE have been
established via the contract or other enforceable mechanism to govern the safe
operations of the facility. A systematic review of the facility’s conformance to
these requirements has been performed. These requirements have been
implemented in the facility, or compensatory measures are in place and formally
agreed to during the period of implementation. The compensatory measures
and the implementation period are approved by DOE. (CR #7)
(15) A feedback and improvement process has been established to identify, evaluate,
and resolve deficiencies and recommendations made by oversight groups,
official review teams, audit organizations, and the operating contractor (e.g.,
DOE P 450.5). (CR #6)
e. Exemptions. Requirements for exemptions are provided in DOE O 251.1A,
DIRECTIVES SYSTEM.
Section 19
f. Information Management Program. Requirements for maintenance and disposition of
Federal records, such as those pertaining to Operational Readiness Reviews or
Readiness Assessments, are provided under the general guidance of DOE O 200.1,
INFORMATION MANAGEMENT PROGRAM, dated 9-30-96. The disposition,
including destruction, of Federal records must be in accordance with (1) the General
Records Schedules, as published by the National Archives and Records
Administration (NARA), or (2) DOE records disposition schedules (Standard Form
115) as approved by NARA. Consult the cognizant site records officer or cognizant
DOE operations office records officer for guidance.
1. Objective
2. Cancellation
3. Applicability
4. Requirements
5. Responsibilities
6. Contact
Attachment 1, Contractor Requirements Document