DOE O 413.2C, Laboratory Directed Research and Development
Functional areas: Research and Development, Laboratories
To establish Department of Energy (DOE) requirements for laboratory directed research and development (LDRD) while providing the laboratory director broad flexibility for program implementation. Supersedes DOE O 413.2B. Superseded by DOE O 413.2C Chg1 (MinChg)
Supersedes:
Superseded By:
Version history and related documents
Superseded by
A newer version replaces this document.
Supersedes
Earlier documents this one replaced.
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
AVAILABLE ONLINE AT: INITIATED BY:
www.directives.doe.gov Office of Science
U.S. Department of Energy ORDER
Washington, D.C.
Approved: 10-22-2015
SUBJECT: LABORATORY DIRECTED RESEARCH AND DEVELOPMENT
1. OBJECTIVE. To establish Department of Energy (DOE) requirements for laboratory
directed research and development (LDRD) while providing the laboratory director
broad flexibility for program implementation. The objectives of the LDRD program are
to—
maintain the scientific and technical vitality of the laboratories;
enhance the laboratories’ ability to address current and future DOE/NNSA
missions;
foster creativity and stimulate exploration of forefront areas of science and
technology;
serve as a proving ground for new concepts in research and development; and
support high-risk, potentially high-value research and development.
2. CANCELLATION. DOE O 413.2B, Laboratory Directed Research and Development,
dated 4/19/06. Cancellation of an Order does not, by itself, modify or otherwise affect
any contractual obligation to comply with the Order. Canceled Orders that are
incorporated by reference in a contract remain in effect until the contract is modified to
delete the references to the requirements in the canceled Orders.
3. APPLICABILITY.
a. DOE Elements. The provisions of this Order apply to all DOE elements that have
responsibility for laboratories with approved LDRD programs.
The Administrator of the National Nuclear Security Administration (NNSA) must
assure that NNSA employees comply with their responsibilities under this
directive. Nothing in this directive will be construed to interfere with the NNSA
Administrator’s authority under section 3212(d) of Public Law (P.L.) 106-65 to
establish Administration-specific policies, unless disapproved by the Secretary.
b. DOE Contractors. The Contractor Requirements Document (CRD), Attachment 1,
sets forth requirements that are to be applied to contractors operating laboratories
that conduct LDRD programs approved by the appropriate Cognizant Secretarial
Officer (CSO)/Deputy Administrator, NNSA.
c. Exclusions. None.
DOE O 413.2C
http://www.directives.doe.gov/
2 DOE O 413.2C
10-22-2015
4. REQUIREMENTS.
a. LDRD projects must be in the forefront areas of science and technology relevant
to DOE/NNSA missions. Normally LDRD projects will be relatively small and
will also include one or more of the following characteristics—
(1) advanced study of hypotheses, concepts, or innovative approaches to
scientific or technical problems;
(2) experiments and analyses directed towards “proof of principle” or early
determination of the utility of new scientific ideas, technical concepts, or
devices; and
(3) conception and preliminary technical analyses of experimental facilities or
devices.
b. Normally LDRD projects must be limited to a maximum period of performance of
36 months. Exceptions may be granted by the CSO/Deputy Administrator,
NNSA, or his/her authorized designee.
c. DOE must annually concur on each LDRD project before the project is started or
continued.
d. The maximum funding level established for LDRD must not exceed the
congressionally mandated limit
1
of a laboratory’s total operating and capital
equipment budget for the year. For the purposes of this policy, the operating and
capital equipment budget includes non-DOE funded work, but excludes line-item
construction activities and LDRD.
Section 2
e. No individual program, project, or activity at the laboratory may be charged more
than the statutory maximum limit authorized for LDRD. To ensure compliance
with the congressionally mandated limit, DOE laboratories shall allocate LDRD
costs by applying a uniform rate to the same base that is used to calculate the
LDRD budget for the year (see 4.d. above).
f. LDRD expenditures are considered allowable costs in accordance with the terms
and conditions of the laboratory operating contract and must be identified in the
laboratory accounting system. LDRD constitutes a final cost objective and must
be treated in the same manner as non-LDRD final cost objectives in accordance
with the site’s normal cost accounting practices, with the exception that LDRD is
not burdened with LDRD.
g. LDRD costs are separate and distinct from site general and administrative (G&A)
costs. As such, there is no requirement to allocate LDRD costs in the same
manner as G&A.
1
See reference j.
DOE O 413.2C 3
10-22-2015
h. The LDRD cost allocation methodology must be described in the Cost
Accounting Standards disclosure statement and approved by DOE.
i. Costs must be incurred for LDRD projects in the same fiscal year in which the
LDRD funds are collected.
j. LDRD funds must not be used to—
(1) substitute for or increase funding for any tasks for which a specific
limitation has been established by Congress or the Department or for any
specific tasks that are funded by DOE/NNSA or other users of the
laboratory;
(2) fund projects that will require the addition of non-LDRD funds to
accomplish the technical goals of the LDRD project, except as provided
by legislation;
(3) fund construction design beyond the preliminary phase (e.g., conceptual
design, Title I design work, or any similar or more advanced design effort)
or fund line-item construction projects, in whole or in part; or
(4) fund general purpose capital expenditures with the exception of
acquisition of general purpose equipment that is clearly required for the
project and is not otherwise readily available from laboratory inventory.
k. The LDRD program must—
(1) include all discretionary research and development activities other than
those provided for in a DOE/NNSA program or by specific designation in
a DOE contract and
(2) be consistent with all other applicable requirements for similar research
and development activities at the laboratory.
5. RESPONSIBILITIES.
a. Director, Office of Science. In cooperation with cognizant Departmental
elements—
(1) performs periodic reviews of this Order and its implementation and
recommends revisions, as required;
(2) establishes guidelines as required to implement the requirements of this
Order; and
(3) develops a set of LDRD program performance measures that are
consistent among DOE/NNSA laboratories.
4 DOE O 413.2C
10-22-2015
b. Cognizant Secretarial Officers/Deputy Administrators, NNSA.
(1) Exercise general oversight of all activities related to LDRD at the
laboratories for which they have cognizance.
(2) Annually approve each laboratory’s LDRD plan and allowable funding
level and grant exceptions as required under paragraph 4.b.
(3) Annually review each laboratory’s LDRD program with the assistance of
the responsible DOE/NNSA site office manager.
(4) Prepare reports to Congress as required.
c. Site Office Managers.
(1) Assist the CSO/Deputy Administrator, NNSA, in providing oversight and
Section 3
review of the laboratory’s LDRD program.
(2) Provide a recommendation to the CSO/Deputy Administrator, NNSA, on
the laboratory’s proposed annual LDRD plan and funding level.
(3) Formally authorize the annual LDRD program for the laboratory based on
CSO/Deputy Administrator, NNSA, written approval.
(4) Annually concur on each laboratory LDRD project before the project is
started or continued.
(5) Annually review and certify in writing to the CSO/Deputy Administrator,
NNSA, whether the laboratory’s method for accumulating LDRD funds is
consistent with paragraphs 4d and 4e of this Order.
(6) Notify the responsible contracting officer that the CRD must be
incorporated into the contract to manage and operate the laboratory.
d. Contracting Officers. Once notified by site office managers, incorporate the CRD
into affected contracts as directed.
6. REFERENCES.
a. The Atomic Energy Act of 1954, as amended, sections 3, 31, and 33,
42 U.S.C. 2013, 2051, and 2053, which provides broad authority for research and
development activities and their funding.
b. The Energy Reorganization Act of 1974, as amended, Public Law (P.L.) 93-438,
sections 2, 103, and 107, 42 U.S.C. 5801(b), 5813, and 5817(a), which creates the
Energy Research and Development Administration (ERDA) to bring together and
direct Federal activities relating to research and development on the various
sources of energy and to carry out general basic research activities.
DOE O 413.2C 5
10-22-2015
c. The Department of Energy Organization Act, as amended, P.L. 95-91, sections
101 and 102, 42 U.S.C. 7111(4) and 7112(5), which places the research and
development activities formerly performed by the Atomic Energy Commission
and ERDA under the Secretary of Energy, and directs the Department to carry out
the planning, support, and management of a comprehensive energy research and
development program.
d. An Act for Authorizations and Appropriations for the Energy Research and
Development Administration for FY 1977, P.L. 95-39, which provides specific
authority so that the director of a Government-owned, contractor-operated
laboratory may use a reasonable amount of the laboratory’s operating budget to
fund employee-suggested projects up to the pilot stage of development, with the
approval of the Secretary.
e. The National Defense Authorization Act for Fiscal Year 1991, P.L. 101-510,
Section 3132, 50 U.S.C. 2791, which authorizes Government-owned,
contractor-operated laboratories that are funded out of funds available to DOE for
national security programs (i.e., atomic energy defense activities) to carry out
LDRD, not to exceed 6 percent of such funds, for the purpose of maintaining the
vitality of the laboratory in defense-related scientific disciplines.
f. The National Defense Authorization Act for Fiscal Year 1993, P.L. 102-484,
section 3135, which directs that funds authorized to be appropriated to the
Department of Energy for Atomic Energy Defense Activities and made available
for LDRD, shall be made available for cooperative research and development
agreements or other arrangements for technology transfer.
g. The National Nuclear Security Administration Act, Title XXXII of P.L. 106-65,
as amended, which established a separately organized agency within DOE.
h. Homeland Security Act of 2002, P.L. 107-296, 6 U.S.C. 189(6)f, which directs
that funds authorized to be used for LDRD must benefit the homeland security
mission.
Section 4
i. FY 2006 Energy and Water Development Appropriations Act, P.L 109-103,
Section 311, which raises the maximum LDRD funding level to 8 percent and
makes all the DOE laboratories eligible for LDRD funding.
j. The Consolidated Appropriations Act, 2014, P.L. 113-076, which lowers the
maximum LDRD funding level to 6% of the total operating and capital equipment
budget.
k. The Consolidated and Further Continuing Appropriations Act, 2015, P.L. 113-
235, which applies the 6% cap to the program, project, and activity level.
6 DOE O 413.2C
10-22-2015
7. DEFINITIONS.
a. Final Cost Objective. A cost objective which has allocated to it both direct and
indirect costs, and in the organization's accumulation system, is one of the final
accumulation points.
8. CONTACT. Questions covering this Order should be addressed to the Office of
Laboratory Policy, Office of Science, 202-586-5447.
BY ORDER OF THE SECRETARY OF ENERGY:
ELIZABETH SHERWOOD-RANDALL
Deputy Secretary
DOE O 413.2C Attachment 1
10-22-2015 Page 1
CONTRACTOR REQUIREMENTS DOCUMENT
DOE O 413.2C, Laboratory Directed Research and Development
Regardless of the performer of the work, the contractor is responsible for compliance with the
requirements of this Contractor Requirements Document (CRD). The contractor is responsible
for flowing down the requirements of this CRD to subcontractors at any tier to the extent
necessary to ensure the contractor’s compliance with the requirements and the safe performance
of work.
As directed by the contracting officer, the contractor must do the following.
1. Establish and maintain a management system to ensure that the laboratory directed
research and development (LDRD) program meets the following requirements.
a. LDRD projects must be in the forefront areas of science and technology relevant
to Department of Energy (DOE)/National Nuclear Security Administration
(NNSA) missions. Normally LDRD projects will be relatively small and will also
include one or more of the following characteristics—
(1) advanced study of hypotheses, concepts, or innovative approaches to
scientific or technical problems;
(2) experiments and analyses directed towards “proof of principle” or early
determination of the utility of new scientific ideas, technical concepts, or
devices; and
(3) conception and preliminary technical analyses of experimental facilities or
devices.
b. Normally LDRD projects must be limited to a maximum period of performance of
36 months. Exceptions may be granted by the Cognizant Secretarial Officer
(CSO)/Deputy Administrator, NNSA, or his/her authorized designee.
c. DOE must annually concur on each LDRD project before the project is started or
continued.
d. The maximum funding level established for LDRD must not exceed the
congressionally mandated limit
i
of a laboratory’s total operating and capital
equipment budgets for the year. For the purposes of this policy, the operating and
capital equipment budget includes non-DOE funded work, but excludes line-item
construction activities and LDRD.
e. Establish a cost accounting system that ensures that no individual program,
project, or activity is charged more than the statutory maximum limit authorized
for LDRD.
Attachment 1 DOE O 413.2C
Page 2 10-22-2015
(1) DOE laboratories shall allocate LDRD costs by applying a uniform rate to
the same base that is used to calculate the LDRD budget for the year (See
1.d. above).
(2) This methodology shall be described in the Cost Accounting Standards
Section 5
disclosure statement and approved by DOE.
f. LDRD expenditures are considered allowable costs in accordance with the terms
and conditions of the laboratory operating contract and must be identified in the
laboratory accounting system. LDRD constitutes a final cost objective and must
be treated in the same manner as non-LDRD final cost objectives in accordance
with the site’s normal cost accounting practices, with the exception that LDRD is
not burdened with LDRD.
g. Costs must be incurred for LDRD projects in the same fiscal year in which the
LDRD funds are collected.
h. LDRD funds must not be used to—
(1) substitute for or increase funding for any tasks for which a specific
limitation has been established by Congress or the Department or for any
specific tasks that are funded by DOE/NNSA or other users of the
laboratory;
(2) fund projects that will require the addition of non-LDRD funds to
accomplish the technical goals of the LDRD project, except as provided
by legislation;
(3) fund construction design beyond the preliminary phase (e.g., conceptual
design, Title I design work, or any similar or more advanced design effort)
or fund line-item construction projects, in whole or in part; or
(4) fund general purpose capital expenditures with the exception of
acquisition of general purpose equipment that is clearly required for the
project and is not otherwise readily available from the laboratory
inventory.
i. The LDRD program must—
(1) include all discretionary research and development activities other than
those provided for in a DOE/NNSA program or by specific designation in
a DOE contract and
(2) be consistent with all other applicable requirements for similar research
and development activities at the laboratory.
i
The Consolidated Appropriations Act, 2014, P.L. 113-076 sets the maximum LDRD funding level to 6% of the
total operating and capital equipment budget of a laboratory.
DOE O 413.2C Attachment 1
10-22-2015 Page 3 (and Page 4)
2. Establish criteria that emphasize innovative scientific and technological excellence for
selection of projects using internal peer and/or technical management review. A
significant number of the projects selected should be those independently proposed by
individual researchers or small multidisciplinary teams.
3. Submit an annual LDRD program plan for approval to the CSO/Deputy Administrator,
NNSA, and the responsible DOE/NNSA site office manager at least 45 days before the
start of the fiscal year. The plan must provide a requested funding level, general
description, and justification of the LDRD program; the plan must also explain how this
program will meet laboratory needs, support the laboratory’s mission, and benefit
DOE/NNSA and the nation.
4. Submit an annual written report on the laboratory’s LDRD activities to the CSO/Deputy
Administrator, NNSA, and the responsible DOE/NNSA site office manager within
6 months after the end of the fiscal year. The annual report must include an overview of
the program as well as a short summary of each funded project. Additionally, each
laboratory must provide a report on completed projects to the Office of Scientific and
Technical Information.
5. Report annually on the standard LDRD program performance measures, and collect and
provide other data on the LDRD program as negotiated with the CSO/Deputy
Administrator, NNSA.
6. Lead or participate in LDRD program reviews of the business and technical aspects of the
program.
7. Submit to the CSO/NNSA Deputy Administrator or his/her designee requests for
exceptions to the LDRD maximum 36-month performance period.
8. Evaluate the quality of science and technology of the LDRD projects.
9. Annually submit a project data sheet to the responsible DOE/NNSA site office manager
for each LDRD project.
1. OBJECTIVE
2. CANCELLATION
3. APPLICABILITY
a. DOE Elements
b. DOE Contractors
c. Exclusions
4. REQUIREMENTS
5. RESPONSIBILITIES
a. Director, Office of Science
b. Cognizant Secretarial Officers/Deputy Administrators, NNSA
c. Site Office Managers
d. Contracting Officers
6. REFERENCES
7. DEFINITIONS
a. Final Cost Objective
8. CONTACT
ATTACHMENT 1. CONTRACTOR REQUIREMENTS DOCUMENT