DOE O 151.1E, Comprehensive Emergency Management System
To provide the Department of Energy (DOE), including the National Nuclear Security Administration (NNSA), (herein referred to as DOE or Department) policy for the development, management, and administration of the DOE Emergency Management System. This Order meets the requirements of Executive Orders, Policies, and Directives regarding emergency management, including Presidential Policy Directive 8 (PPD-8) and Homeland Security Presidential Directive 5 (HSPD-5), which mandates that the Department adopts the National Incident Management System, in support of the National Response Framework. This Order assigns responsibilities, authorities, and accountabilities to the appropriate levels of Departmental management and promotes collaboration through consensus based programmatic decision making. It provides policy direction for coordination of planning, preparedness, response, and recovery activities within the Department and with other government and non-government organizations.
Supersedes:
Superseded By:
DOE O 151.1F, Comprehensive Emergency Management System on Aug 05, 2026
Version history and related documents
Superseded by
A newer version replaces this document.
- DOE O 151.1FComprehensive Emergency Management System (Aug 05, 2026)
Supersedes
Earlier documents this one replaced.
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
AVAILABLE ONLINE AT: INITIATED BY:
www.directives.doe.gov Office of National Nuclear Security Administration
U.S. Department of Energy ORDER
Washington, DC
Approved: 10-28-2024
SUBJECT: COMPREHENSIVE EMERGENCY MANAGEMENT SYSTEM
1. PURPOSE. To provide the Department of Energy (DOE), including the National Nuclear
Security Administration (NNSA), (herein referred to as DOE or Department) policy for the
development, management, and administration of the DOE Emergency Management System.
This Order meets the requirements of Executive Orders, Policies, and Directives regarding
emergency management, including Presidential Policy Directive 8 (PPD-8) and Homeland
Security Presidential Directive 5 (HSPD-5), which mandates that the Department adopts the
National Incident Management System, in support of the National Response Framework.
This Order assigns responsibilities, authorities, and accountabilities to the appropriate levels
of Departmental management and promotes collaboration through consensus based
programmatic decision making. It provides policy direction for coordination of planning,
preparedness, response, and recovery activities within the Department and with other
government and non-government organizations.
2. CANCELLATION. DOE O 151.1D, Comprehensive Emergency Management System, dated
10-04-2019. Cancellation of a directive does not, by itself, modify or otherwise affect any
contractual or regulatory obligation to comply with the directive. Contractor Requirements
Documents (CRD) that were incorporated into a contract remain in effect throughout the
term of the contract unless and until the contract or regulatory commitment is modified to
either eliminate requirements that are no longer applicable or substitute a new set of
requirements.
3. APPLICABILITY.
a. Departmental Elements.
(1) Except for the equivalencies and exemptions in Section 3.c., the provisions of this
Order apply to all Departmental elements.
(2) The Administrator of the NNSA must ensure that NNSA employees comply with
their responsibilities under this directive. Nothing in this directive will be
construed to interfere with the NNSA Administrator’s authority under Section
3212(d) of Public Law (P.L.) 106-65, National Defense Authorization Act for
Fiscal Year 2000, to establish Administration specific policies, unless
disapproved by the DOE Secretary.
b. DOE Contractors.
(1) Except for the equivalencies and exemptions in Section 3.c., the CRD
DOE O 151.1E
http://www.directives.doe.gov/
2 DOE O 151.1E
10-28-2024
(2) (Attachment 1) sets forth the requirements of this Order that apply to contracts
that include the CRD. The CRD or its requirements must be inserted in
laboratories, plants, and sites management contracts.
c. Equivalencies and Exemptions. Equivalencies and exemptions to this Order must be
processed in accordance with DOE O 251.1, Departmental Directives Program,
current version. The DOE/NNSA’s Office of Emergency Management is the Office of
Primary Interest (OPI) for equivalencies and exemptions related to this Order.
(1) Equivalency. In accordance with the responsibilities and authorities assigned by
Executive Order 12344, Naval Nuclear Propulsion Program, codified in 50
United States Code (U.S.C.) Section 2406, Deputy Administrator for Naval
Reactors and 50 U.S.C. Section 2511, Naval Nuclear Propulsion Program, and to
ensure consistency throughout the joint Navy and DOE Naval Nuclear Propulsion
Program, the Deputy Administrator for Naval Reactors (Director) will implement
and oversee requirements and practices pertaining to this Directive for activities
under the Director’s cognizance, as deemed appropriate.
Section 2
(2) Exemption. This Order does not apply to activities that are regulated by the U.S.
Nuclear Regulatory Commission (NRC) or a State under an agreement with the
NRC, including activities certified by the NRC under Section 1701, Licensing and
Regulation of Uranium Enrichment Facilities, of P.L. 73-703 Atomic Energy Act
of 1954, as amended. This Order will apply to activities where the NRC does not
exercise regulatory authority or by agreement with the NRC.
(3) Exemption. This Order does not apply to transportation activities that are
regulated by the U.S. Department of Transportation.
(4) Exemption. Power Marketing Administrations (PMAs) are to comply with
Appendix A, “Power Marketing Administration Emergency Management
Program,” and are exempt from all other sections of this Order, unless specified in
Appendix A.
4. REQUIREMENTS.
a. General.
(1) Each DOE laboratory, plant, or site, as defined in this Order, must develop and
participate in an integrated and Comprehensive Emergency Management System
to ensure:
(a) The Department can effectively and efficiently respond to all Operational and
Energy Emergencies and ensure appropriate response measures are taken to
protect workers, the public, the environment, and national security.
DOE O 151.1E 3
4-1-2024
(b) Emergencies are recognized, categorized and, as necessary, classified
promptly; and parameters associated with the emergency are monitored to
detect changed and degraded conditions.
(c) Emergencies are reported to all relevant parties, and notifications are made in
a timely manner.
(d) Reentry activities are properly and safely accomplished in accordance with
approved guidance, and recovery and post-emergency activities commence in
a timely and efficient manner.
(2) Each DOE laboratory, plant, and site must establish and maintain a documented
emergency management program that implements the requirements of this Order
along with applicable federal, state, and local laws, regulations, and ordinances for
fundamental worker safety programs.
(3) The Headquarters Emergency Operations Center (EOC) (which includes the
Headquarters Watch Center) must serve as the point of contact for all incident and
emergency notification and reporting. At the Departmental level, the
Headquarters EOC will be the central coordinator for vertical and horizontal
information exchange with headquarters elements, Program Officers, Program
Officer emergency points of contact, Field Elements, the White House Situation
Room, other federal, state, local and tribal agencies and, as appropriate,
nongovernment organizations.
b. Appendix A, Power Marketing Administration (PMA). This appendix outlines the
PMA’s emergency management program requirements.
c. Attachment 1, Contractor Requirements Document (CRD). The CRD outlines
contractor requirements necessary to execute responsibilities outlined in this Order.
d. Attachment 3, Emergency Management Program. Provides requirements associated
with DOE O 151.1E and requirements applicable to contracts in which the associated
CRD (DOE O 151.1E, Attachment 1) is inserted.
5. RESPONSIBILITIES.
a. DEPUTY SECRETARY, DEPARTMENT OF ENERGY. Serves as the senior
Departmental emergency management official. In consultation with the Secretary,
issues emergency management policy, requirements, and directives; and designates or
delegates responsibility and authority, as appropriate. Administers, activates,
convenes, and chairs the Emergency and Incident Management Council (EIMC).
Appoints the EIMC Secretariat and establishes and maintains charters.
Section 3
b. UNDER SECRETARY FOR INFRASTRUCTURE. Responsible for the line
management and implementation of emergency management programs in accordance
with the requirements of this Order. This includes providing respective laboratories,
plants, and sites with the necessary guidance for meeting requirements in this Order.
4 DOE O 151.1E
4-1-2024
c. UNDER SECRETARY FOR SCIENCE AND INNOVATION. Responsible for the
line management and implementation of emergency management programs for the
DOE Office of Science national laboratories, plants, and sites in accordance with the
requirements of this Order. This includes providing respective laboratories, plants,
and sites with the necessary guidance for meeting requirements in this Order.
d. UNDER SECRETARY FOR NUCLEAR SECURITY AND ADMINISTRATOR,
NATIONAL NUCLEAR SECURITY ADMINISTRATION. Serves as the NNSA
senior emergency management program official, and designates or delegates
programmatic responsibility and authority, as appropriate. Responsible for the line
management and implementation of emergency management programs for NNSA
laboratories, plants, and sites in accordance with the requirements of this Order,
including development of procedures and guidance on how to apply the requirements
of this Order.
e. ASSOCIATE ADMINISTRATOR FOR EMERGENCY MANAGEMENT, NNSA.
(1) Serves as the Department’s OPI for emergency management program activities.
(2) Manages, directs, coordinates, and approves the activities, including
administrative functions, of the various organization units in the DOE/NNSA’s
Office of Emergency Management.
(3) Recommends to the Deputy Secretary, through the NNSA Administrator,
directives, communications, and policy options for the Secretary’s consultation on
matters within delegated authority.
(4) Maintains operational awareness of the Department’s Emergency Management
System to ensure activities are conducted in accordance with this Order. Ensures
the program provides a comprehensive and integrated approach to emergency
management, including planning, preparedness, response, mitigation, and
recovery, and reports the results to the Under Secretaries, Program Secretarial
Officers, and Field Element Managers (FEM) or Field Office Managers (FOM)
for consideration and action, as appropriate. For laboratories, plants, and sites
with Defense Nuclear Facilities, verifies program performance measures at each
organizational level, including specific emergency management oversight
objectives, areas of attention, and defined assessment frequencies.
(5) Coordinates with the Under Secretaries and Program Secretarial Officers to
provide the Deputy Secretary, through the NNSA Administrator, an annual status
report on Departmental readiness assurance.
(6) Oversees coordination, including communication systems and protocols, of all
DOE emergency management related activities, including intra- and inter-
Departmental and international activities.
(7) Prepares, manages, and approves interpretations, instructions, and guidance on
DOE O 151.1E 5
4-1-2024
matters within delegated authority for use by Department elements and
contractors.
(8) Implements, manages, and coordinates a readiness assurance program to ensure
the DOE emergency management program is executed in accordance with
directives, regulations, policies, and applicable laws. This includes issuing format
and content guidelines for the annual Emergency Readiness Assurance Plan
(ERAP) in accordance with Attachment 3, 14.c. of this Order.
Section 4
(9) Collects and disseminates information, as appropriate, to the Secretary, Deputy
Secretary, NNSA Administrator, Under Secretaries, DOE elements, other
government agencies, and contractors.
(10) Ensures the Secretary, Deputy Secretary, NNSA Administrator, Under
Secretaries, Program Secretarial Officers, and field and site managers are kept
informed about emergency management matters that affect their responsibilities.
(11) Subject to appropriate coordination with relevant offices and where
DOE/NNSA’s Office of Emergency Management is a signatory, enters into,
extends, modifies, and terminates agreements with federal, state, tribal, and local
agencies.
(12) In coordination with relevant offices, ensures adequate resources are available to
effectively execute the responsibilities of DOE/NNSA’s Office of Emergency
Management.
(13) Promotes the Department’s emergency management safety culture.
(14) Performs functions as required, and in accordance with, applicable laws, statutes,
and regulations.
(15) Establishes, charters, administers, convenes, and chairs the Emergency
Management Advisory Committee (EMAC).
(16) Integrates DOE response plans and procedures.
(17) Administers and manages the Headquarters EOC, headquarters incident
coordination and support, and related activities.
(18) Develops Critical Information Requirements (CIRs), and issues the CIRs to the
laboratories, plants, and sites. Reviews and revises the CIRs, as appropriate.
(19) Supports and augments NNSA’s Office of Counterterrorism and
Counterproliferation and DOE’s Office of Cybersecurity, Energy Security, and
Emergency Response (CESER) resource needs during responses to
radiological/nuclear incidents and energy emergencies. Supports and augments,
upon request, DOE and NNSA laboratories, plants, sites, and headquarters
organizational elements during other emergency responses.
6 DOE O 151.1E
4-1-2024
(20) Coordinates with relevant offices to develop and maintain a comprehensive
emergency management risk profile for integration into the NNSA and DOE
annual risk profile.
f. ASSOCIATE ADMINISTRATOR FOR COUNTERTERRORISM AND
COUNTERPROLIFERATION, NNSA.
(1) Manages, directs, coordinates, and approves the activities, including
administrative functions, of the various organization units in NNSA’s Office of
Counterterrorism and Counterproliferation.
(2) Administers and manages the Department's radiological/nuclear assets activities
in accordance with DOE O 153.1, Departmental Nuclear Emergency Support
Team Capabilities, current version.
(3) Coordinates radiological/nuclear asset activities with the responsible FEM/FOM
in accordance with DOE 153.1, Departmental Nuclear Emergency Support Team
Capabilities, current version.
(4) Provides strategic direction and oversight for NNSA’s Nuclear Emergency
Support Team (NEST) capabilities in response to countering weapons of mass
destruction, U.S. nuclear weapons accident/incident response, public health and
safety, and nuclear forensics events.
(5) Coordinates NEST emergency response asset planning and support, including the
National Atmospheric Release Advisory Center, provided to Field Elements and
other federal, state, local, or tribal agencies to ensure a cohesive Departmental
response to a nuclear/radiological emergency.
(6) Designates the Senior Response Official for any NEST response, including nuclear
weapon accidents that occur while the nuclear weapon is in DOE or Department
of Defense (DoD) custody.
Section 5
(7) Keeps the Associate Administrator for Emergency Management apprised of
NNSA NEST deployments.
g. ASSISTANT DEPUTY ADMINISTRATOR, OFFICE OF SECURE
TRANSPORTATION (OST), NNSA.
(1) Provides safe and secure transportation of nuclear weapons, nuclear weapon
components, Special Nuclear Material (SNM), and Materials of National Security
Interest in support of U.S. national security.
(2) Coordinates and manages the Transportation Safeguards System for the safe and
secure movement of nuclear weapons and government owned SNM.
(3) Develops and implements appropriate security procedures and protocols for use
DOE O 151.1E 7
4-1-2024
during an Office of Secure Transportation (OST) Operational Emergency (OE) or
OST transportation emergency in the public domain, federal facilities, or military
installations.
(4) Assists recipient and DoD sites by:
(a) Providing recipient and DoD site responders with all necessary
documentation about the specific hazardous materials being transported.
(b) Coordinating and communicating through the recipient site’s Emergency
Response Organization, and the Headquarters EOC during an incident.
(c) Maintaining security and control of the cargo and immediate area
surrounding the OST convoy. Admittance into the OST-controlled area must
be approved by and is at the discretion of the OST Convoy Commander in
Charge or designee.
(d) Recalling the OST Emergency Response Officer Cadre (EROC) when an
OST OE or OST transportation emergency is declared.
(e) Developing and providing procedures to ensure coordination of emergency
public information activities between the recipient site and OST’s General
Attorney.
(f) Providing timely and accurate emergency information to NNSA’s Office of
Communications, to coordinate among DOE, federal, state, local, and tribal
agencies prior to release.
(5) If an emergency occurs in the public domain, OST must:
(a) Provide security for the shipment.
(b) Declare an OST OE and recall the OST EROC.
(c) Retain custody of the cargo.
(d) Assume responsibilities as the initial Incident Commander and participate in
the Unified Command with responding agencies.
(6) OST tenant facilities co-located with a federal or DOE laboratory, plant, or site
will integrate into the laboratory, plant, or site emergency response plan and
Emergency Management System.
(7) OST stand-alone facilities must comply with the requirements outlined in
Attachment 3.
(8) Receives and reviews recipient site emergency response plans to ensure proper
8 DOE O 151.1E
4-1-2024
integrated response during OST-declared OEs or OST transportation emergencies.
(9) Develops and maintains procedures to establish a National Security Area (NSA)
as authorized by the Atomic Energy Act of 1954, as amended, and the
Nuclear/Radiological Incident Annex to the National Response Framework, if
applicable, during an OST OE.
(10) Develop indicators that would require an OST OE categorization of an OST
shipment. Provide OST OE categorization indicators to the recipient sites.
Review the indicators annually and update as appropriate.
(11) Develops an Emergency Planning Hazards Assessment (EPHA) for its shipments
to provide the planning basis for the OST Hazardous Materials Program. An
unclassified version of the EPHA will be provided to the recipient site for the
recipient site’s use in emergency planning.
(12) Develops review criteria for OST vehicle recovery and incident termination.
Reviews annually and updates, as appropriate.
Section 6
(13) Develops and maintains procedures that ensure reports prepared by the OST
EROC are reviewed in accordance with DOE O 471.1, Identification and
Protection of Unclassified Controlled Nuclear Information, current version and
DOE O 475.2, Identifying Classified Information, current version, and reviewed
by an appropriate classification official, Unclassified Controlled Nuclear
Information (UCNI) Reviewing Official, or an appropriate person for Controlled
Unclassified Information (CUI) and the Emergency Manager for classified
information, UCNI, and CUI prior to release.
(14) Implements aviation-specific OST OE criteria that reflects aviation incidents.
(15) Coordinates the establishment of classified video teleconferencing with the
Headquarters EOC as soon as possible after the OST EROC is declared
operational.
(16) Develops procedures, in coordination with recipient sites, to address OST OE and
OST transportation incident termination and recovery.
(17) Vehicle recovery actions for OST equipment must only occur after a
predetermined set of criteria has been met and termination has been coordinated
between the Unified Command at the scene (including the Senior Response
Official), OST Headquarters, DOE Headquarters, and other participating federal
agencies.
(18) Conducts a minimum of one discussion or operations-based exercise per quarter
with the OST EROC.
(19) Plans, develops, and conducts at least one transportation OE functional exercise
DOE O 151.1E 9
4-1-2024
every two years that includes participation of the entire OST EROC.
(20) Conducts a minimum of one discussion or operations-based exercise with a DOE
OST recipient site annually and conducts exercises with all DOE recipient sites
over a rolling five-year period. OST, in coordination with the recipient site and
based on recipient site risk, will determine the type and scope of the exercise.
h. DIRECTOR, OFFICE OF CYBERSECURITY, ENERGY SECURITY, AND
EMERGENCY RESPONSE (CESER).
(1) Manages the Department’s responsibilities as the Sector Risk Management
Agency (SRMA) for the energy sector under PPD-21, Critical Infrastructure
Security and Resilience, PPD-41, United States Cyber Incident Coordination,
Executive Order 13636, Improving Critical Infrastructure Cybersecurity, and P.L.
114-94, Fixing America’s Surface Transportation (FAST) Act.
(2) Serves as the coordinating office for Emergency Support Function 12 (ESF #12)
under the National Response Framework. As the lead for ESF #12, CESER
assesses the impacts of a disaster on the local and regional energy infrastructure;
provides situational awareness updates to federal, state, local, tribal, territorial,
and private sector partners; facilitates legal and regulatory waivers to support
energy delivery; and provides technical subject matter expertise on energy
damage assessment, restoration, and logistical assistance.
(3) Manages and activates the Energy Response Organization to administer ESF #12
and SRMA response activities, including deployment of DOE responders and
sector engagement.
(4) Coordinates an interagency response as the Lead Federal Agency, pursuant to
PPD-44, Implications for Domestic Incident Management, to energy sector
incidents that are outside the scope of the National Response Framework. This
can include major disruptions to energy resources that do not meet criteria under
P.L. 93-288, Robert T. Stafford Disaster Relief and Emergency Assistance Act.
Section 7
(5) Coordinates the Department’s response to cyber incidents impacting or potentially
impacting the energy sector. For an energy sector cyber incident that requires a
coordinated response, CESER activates the Cyber Crisis Action Team. The team
coordinates with other Departmental elements, including the Headquarters EOC
and EIMC (or other supporting structure), and interagency partners, including a
Unified Command Group convened per PPD-41 and the National Cyber Incident
Response Plan.
(6) Coordinates the use of the Department’s emergency response authorities for the
energy sector, such as those authorities under P.L. 81-774, Defense Production
Act of 1950, and Sections 202(c) and 215(a) of the Federal Power Act, as
amended under P.L. 115-325. CESER supports other Departmental and federal
authorities, as needed, and provides subject matter expertise and formal
10 DOE O 151.1E
4-1-2024
concurrence on legal and regulatory waivers issued by other federal agencies.
(7) Manages the operation of the Strategic Petroleum Reserve, including the sales,
releases, and exchanges authorized by the President or Secretary in response to
domestic and international disruptions.
(8) Collects and disseminates information, in coordination with the Headquarters
EOC, to the Secretary; Deputy Secretary; NNSA Administrator; DOE officials;
government agencies; state, local, tribal, and territorial governments; industry;
and the public.
(9) Performs additional activities to fulfill CESER’s responsibilities to include:
(a) Providing technical expertise and assistance to energy industry partners as
applicable.
(b) Providing annual and refresher training to all ESF #12 responders. Refresher
training must be provided when plans, procedures, or systems/equipment
change. Annual refresher training must also be provided to responders who
are likely to be deployed.
(c) Implementing, managing, and coordinating a preparedness program with
other Departmental elements, when appropriate, to ensure the DOE Energy
Emergency Response Program capabilities are maintained in accordance with
directives, regulations, policies, and applicable laws.
(d) Conducting annual response exercises and participating in additional
exercises sponsored by industry or other government entities.
(e) Identifying and resolving issues in accordance with respective processes
associated with DOE O 226.1, Implementation of Department of Energy
Oversight Policy, current version.
(f) Incorporating and tracking lessons learned from training, exercises, and
actual responses.
i. DIRECTOR, OFFICE OF MANAGEMENT. Develops and maintains the
Headquarters Occupant Emergency Program and necessary plans and implementing
procedures.
j. DIRECTOR, OFFICE OF ENVIRONMENT, HEALTH, SAFETY, AND SECURITY
(EHSS). Develops and maintains emergency plans and procedures for Headquarters
facilities and senior executive physical security.
k. PROGRAM SECRETARIAL OFFICERS.
(1) Ensures implementation of emergency management policy and requirements and
DOE O 151.1E 11
4-1-2024
maintains programs and systems consistent with policy and requirements.
(2) Ensures that resources for laboratories, plants, and sites, including transportation
activities, are adequate for the effective implementation and maintenance of
emergency management programs, emergency response assets, and capabilities.
(3) Coordinates with the responsible Under Secretary and the Associate Administrator
for Emergency Management regarding emergency management activities.
Section 8
(4) Designates a round-the-clock single point of contact to provide two-way
notifications and communications between the Program Secretarial Officers and
the Headquarters EOC and to provide internal notifications within their Office.
(5) Coordinates with the DOE Director of Public Affairs and the Associate
Administrator for Emergency Management for the dissemination of emergency
information.
(6) Disseminates delegations of authority from laboratories, plants, and sites to the
DOE/NNSA’s Office of Emergency Management.
(7) Assigns a senior office representative for the EIMC and the EMAC.
(8) Ensures the Secretary, Deputy Secretary, NNSA Administrator, Associate
Administrator for Emergency Management, and laboratory, plant, and site
managers are kept informed about matters that affect their responsibilities.
l. FIELD ELEMENT MANAGER OR FIELD OFFICE MANAGER.
(1) The FEM/FOM may delegate approval responsibilities, after initial approval, for
individual requirements, in accordance with Contractor Assurance Systems with
appropriate oversight. Delegations must be formally documented and sent to the
Program Secretarial Officers and Associate Administrator for Emergency
Management.
(2) Implements emergency management policy and requirements and maintains
programs and systems consistent with the Order.
(3) Reviews and approves laboratory, plant, and site emergency management plans,
including updates.
(4) Reviews and approves laboratory, plant, and site All-Hazards Surveys.
(5) Reviews and approves laboratory, plant, and site EPHAs.
(6) Reviews and approves laboratory, plant, and site-level consolidated and integrated
Emergency Planning Zones.
12 DOE O 151.1E
4-1-2024
(7) Works with contracting officers to ensure laboratory, plant, and site performance
measures for the emergency management program are incorporated into
contractual agreements.
(8) Assesses the Field Element emergency management program annually and
documents the results of the self-assessment in the Field Element portion of the
ERAP.
(9) Reviews laboratory, plant, and site self-assessment reports.
(10) Reviews and approves the annual laboratory, plant, and site exercise plan.
(11) Reviews and approves laboratory, plant, and site corrective action plans for
external issues identified during assessments, exercises, real-world incidents, and
equipment maintenance and testing.
(12) Based on laboratory, plant, and site performance, periodically reviews corrective
action plans, as defined in the laboratory, plant or site emergency management
plan or implementing procedures, to ensure programmatic effectiveness.
(13) Ensure corrective actions are identified, tracked, and implemented.
(14) Reviews and approves the annual ERAP for each laboratory, plant, and site under
the FEM/FOM responsibility. In doing so, prepares the Field Element portion for
submittal to the Associate Administrator for Emergency Management by
November 30 of each year. The FEM/FOM determines if the ERAP will be
submitted individually for each laboratory, plant, and site, or consolidated.
(15) Coordinates with the Program Secretarial Officers to ensure resources are
available to implement this Order on behalf of laboratories, plants, and sites.
(16) Ensures emergency public information planning is integrated with laboratory,
plant, and site emergency management plans.
(17) Ensures effective communication systems, reporting, and protocols are
Section 9
coordinated and maintained with the Headquarters EOC regarding emergencies
involving or affecting laboratories, plants, and sites or materials under DOE
jurisdiction or requiring DOE assistance, to include those defined in the
Headquarters EOC issued CIRs.
(18) Where applicable, pre-designates a DOE employee as the initial on-scene
coordinator for Federal responses under 40 Code of Federal Regulations (CFR)
Part 300, National Oil and Hazardous Substances Pollution Contingency Plan or
its replacement.
(19) Participates in the development and implementation of mutual assistance
agreements, to which the Field Element is a signatory, with state, tribal, and local
DOE O 151.1E 13
4-1-2024
authorities.
(20) Ensures Field Element personnel and laboratory, plant, and site personnel
participate in an emergency preparedness program consisting of the appropriate
level of training and exercises.
(21) During an emergency, conducts appropriate and necessary emergency actions in
accordance with approved plans and implementing procedures.
(22) Implements corrective actions and lessons learned identified from assessment,
exercises, real-world incidents, and equipment maintenance and testing.
(23) Assigns senior Field Element representatives to the EMAC.
(24) Identifies a Senior Official with decision-making authority and responsibilities to
serve as an emergency manager, supported by personnel with communications,
technical, and public affairs expertise.
(25) Where applicable, assigns a Senior Federal Official in the capacity as the
FEM/FOM, with decision-making authority and responsibilities, to the EOC.
(26) Integrates the activities of facilities leased by DOE and NRC licensed facilities
into the DOE site-wide emergency management program. DOE facilities that are
leased to other government agencies must comply with this Order. At a
minimum, the lease arrangements must include a description of how each of the
lessee’s emergency management program elements is integrated into the site-wide
program and must also include a requirement that tenant hazardous material
inventories be reported to the site emergency management organization annually
and before hazardous materials are introduced or inventories exceed existing
analyzed quantities.
(27) Ensures that the responsible Program Secretarial Officers and the Associate
Administrator for Emergency Management are kept informed about matters that
affect their responsibilities. Makes available, upon request, emergency
management documentation to the Program Secretarial Officer and Associate
Administrator for Emergency Management.
m. DIRECTOR, HEADQUARTERS OFFICE OF PUBLIC AFFAIRS. In coordination
with the NNSA Director of Communications, develops and maintains the
Headquarters Emergency Public Information Plan and necessary implementing
procedures. Provides copies of the plan to the Program Secretarial Officers and the
Associate Administrator for Emergency Management.
n. INITIATORS OF PROCURMENT REQUESTS. Specifies, in the procurement
request, whether the requirements in the CRD for this Order are applied to the award
or sub-award resulting from the procurement request.
o. CONTRACTING OFFICER. Ensures that the CRD is incorporated into the
14 DOE O 151.1E
4-1-2024
laboratory, plant, and site management contract in accordance with the laws,
regulations, and DOE directives clause, through negotiation or modification, as
appropriate.
6. INVOKED STANDARDS. There are no invoked standards.
Section 10
7. ACRONYMS AND ABBREVIATIONS. See Attachment 2.
8. REFERENCES. See Attachment 4.
9. DEFINITIONS. See Attachment 5.
10. CONTACT. For assistance regarding this Order, contact the Associate Administrator for
Emergency Management at 202-586-8100.
BY ORDER OF THE SECRETARY OF ENERGY:
DAVID TURK
Deputy Secretary
DOE O 151.1E Appendix A – Federal Employees
4-1-2024 Page A-1
APPENDIX A
POWER MARKETING ADMINISTRATION (PMA)
1. PURPOSE. Establishes emergency management policy and requirements for emergency
planning, preparedness, response, and recovery for the Department of Energy (DOE) PMAs.
Clarifies requirements for specific application to PMAs and is compatible with emergency
preparedness and disaster reporting requirements of the electric utility industry.
2. APPLICABILITY.
a. DOE Elements.
(1) The provisions of this Appendix apply to all PMAs (Bonneville Power
Administration, Southeastern Power Administration, Southwestern Power
Administration, and Western Area Power Administration).
(2) The DOE/National Nuclear Security Administration’s (NNSA) Office of
Emergency Management and the DOE’s Office of Public Affairs have limited
responsibilities in coordinating emergency management with the PMAs.
b. DOE Contractors. This Appendix does not apply to contractors.
c. Exclusions. Except for the DOE elements listed in Appendix A, Section 2.a., of
this Order, all other DOE elements are excluded from this Appendix.
d. Exemptions or Equivalencies.
(1) If a PMA can demonstrate that it is subject to emergency management program
requirements under the authority of other Federal regulatory agencies and those
requirements are at least as stringent as the requirements of this Appendix, an
exemption or equivalency may be requested.
(2) Requests for exemptions or equivalencies are submitted in accordance with
DOE O 251.1, Departmental Directives Program, current version.
(3) Each PMA Administrator defines “facility” for the purpose of implementing
this Appendix. PMAs may group activities and operations for certain
requirements to meet their organizational needs without requesting an
exemption or equivalency.
3. REQUIREMENTS.
a. Each PMA must develop and participate in an integrated and Comprehensive
Emergency Management System, to ensure:
Appendix A – Federal Employees DOE O 151.1E
A-2 4-1-2024
(1) The PMAs respond to Operational Emergencies (OE) and Energy Emergencies.
(2) The PMAs can provide emergency assistance, which includes offers of resources
to support other electric utilities, state or local authorities, or other government
agencies in emergency response.
b. Notify the Headquarters Emergency Operations Center (EOC) and maintain
two-way information exchange for the duration of the incident, including
recovery operations.
4. RESPONSIBILITIES.
a. Deputy Secretary or Designated Chief Operating Officer. Provides the final
decision on requests for exemptions and equivalencies from the requirements of
this Appendix in accordance with DOE O 251.1, Departmental Directives
Program, current version.
b. Associate Administrator for Emergency Management. See DOE O 151.1E,
Comprehensive Emergency Management System, 5.e., Responsibilities.
c. PMA Administrators.
(1) Develop, approve, implement, and manage their individual emergency
management programs.
(2) Designate, by name, title, or position, a person to manage the PMA emergency
Section 11
management program, receive emergency notifications, participate in any
Headquarters response, and represent the PMA at DOE headquarters’ emergency
management meetings or planning activities.
(3) Establish and maintain integrated plans and procedures detailing responsibilities
for emergency response. Ensure that all emergency plans and procedures:
(a) Are consistent with the requirements of this Appendix, electric utility
reliability criteria, and appropriate PMA business objectives and
operations.
(b) Provide support and electrical energy assistance, within resource
constraints, for electrical energy emergencies and emergency assistance.
Emergency assistance may include emergency generation or grid
restoration.
(c) Are coordinated with the appropriate Departmental elements and other
federal, state, local, and tribal agencies, and other utilities as applicable.
(d) Provide a program for emergency management training and exercises.
DOE O 151.1E Appendix A – Federal Employees
4-1-2024 A-3
(e) Provide opportunities for training and exercise participation by appropriate
utilities and local, state, and tribal organizations.
(f) Are reviewed annually and updated, if necessary.
(4) Establish a formal procedure to keep copies of emergency plans, procedures,
and associated documents up to date and accessible at locations where they
may be needed during an emergency.
(5) Identify and maintain emergency operations records as outlined in DOE O 243.1,
Records Management Program, current version.
(6) Ensure that supporting mutual assistance agreements are developed with tribal,
state, and local governments, and other utilities as needed.
(7) Ensure that immediate emergency response is initiated and followed with
appropriate recovery and restoration activities.
(8) Ensure the PMA’s Public Affairs Office is part of emergency planning and
response.
(9) Assess the PMA emergency management program annually and record the results
of the self-assessment in the Emergency Readiness Assurance Plan (ERAP).
(10) Ensure that potential hazards are reviewed and documented for emergency
planning purposes.
(11) Coordinate updates of initial news releases and public statements between PMA
Public Affairs, DOE’s Office of Public Affairs, and the Headquarters EOC for
electrical energy incidents that draw national attention.
5. PROGRAM REQUIREMENTS. Each PMA must establish and maintain an emergency
management program that complies with the emergency management program
requirements.
a. Program Administration.
(1) An individual must be designated to ensure the development and maintenance of
the emergency plan and implementing procedures, development of the annual
ERAP, conduct training and exercises, coordination of self-assessment activities,
maintenance of related facility documentation, and coordination of facility
emergency resources.
(2) Analyze capabilities and resource gaps that would stress the PMA’s capabilities to
plan for, respond to, and recover from the hazards identified in the All-Hazards
Planning Basis; and use the analysis in development of the emergency
Appendix A – Federal Employees DOE O 151.1E
A-4 4-1-2024
management plan.
(3) Emergency plans and procedures must:
(a) Clearly state roles, responsibilities, and requirements associated with
program administration, individual positions, operations, and interfaces.
(b) Be reviewed annually and updated as necessary.
(c) Be integrated with DOE and site security conditions response plans and
Section 12
procedures.
b. All-Hazards Planning Basis. See DOE O 151,1E, Comprehensive Emergency
Management System, Attachment 3, Section 2.
c. Emergency Response Organization. An individual with decision-making
authority must be assigned and trained to manage and control all aspects of the
PMA emergency response, and must:
(1) Activate for any declared OE or other severe incidents.
(2) Maintain the capability to provide a common operating picture.
(3) Maintain two-way information exchange with the Headquarters Emergency
Operations Center for the duration of the incident.
d. Training. Training must cover hazards and protective actions site workers and
visitors may be expected to take based on the All-Hazards Planning Basis.
(1) Training must be conducted and documented upon initial assignment and when
there are changes affecting worker actions or responsibilities.
(2) Refresher training must be provided annually. If a protective action is performed
successfully during an exercise or actual incident, the annual training requirement
is met for that protective action.
(3) Emergency-related information and training on site-specific conditions and
hazards must be offered to off-site response agency personnel and organizations,
including hospitals, that are expected to support on-site response efforts.
e. Emergency Medical Support. See DOE O 151.1E, Comprehensive Emergency
Management System, Attachment 3, Section 5.
f. Off-site Response Agencies. Establish and maintain interfaces with federal,
state, local, and tribal agencies responsible for emergency response or those
DOE O 151.1E Appendix A – Federal Employees
4-1-2024 A-5
who may be used to supplement response capabilities based on the All-Hazards
Planning Basis.
g. Categorization.
(1) Facility-specific indicators to recognize abnormal incidents or conditions as OE
must be developed. Specific indicators must be developed for the spectrum of
emergency conditions identified in the All-Hazards Planning Basis.
(2) Predetermined decision-makers must categorize an incident as an OE within 15
minutes after the availability of laboratory, plant, or site’s defined indicators that
an OE has occurred. Categorization must occur no more than 30 minutes after
discovery.
(3) In addition to an OE, PMAs must categorize electrical energy emergencies as
described in 10 Code of Federal Regulations (CFR) Parts 205.350-353, Report of
Major Electric Utility System Emergencies.
h. Protective Actions.
(1) Plans must be developed for the timely evacuation and/or sheltering of on-site
personnel and must identify protective actions commensurate for the potential
hazards at the PMA.
(2) Maintain procedures for prompt issuance of protective actions to workers.
(3) In the event of a facility emergency evacuation, accountability actions must
continue until all employees are located.
i. Emergency Facilities, Equipment, and Systems.
(1) Facilities and equipment must be adequate to support emergency response and be
able to notify employees of an incident and protective actions, including safe
evacuation from work areas.
(2) For each PMA, the organization responsible for communication with DOE
Headquarters EOC and off-site agencies must test communication systems, at a
minimum, annually or as often as needed to ensure that communication systems
are operational.
j. Notifications and Communications.
(1) Notifications for electrical energy emergencies must be conducted in accordance
Section 13
with 10 CFR Part 205.350-353, Report of Major Electric Utility System
Emergencies and applicable DOE Orders and Manuals.
Appendix A – Federal Employees DOE O 151.1E
A-6 4-1-2024
(2) Provide immediate notification and protective actions to affected employees no
later than 10 minutes after the protective actions have been identified in
accordance with the emergency management plan and related procedures.
(3) Each facility and activity must establish procedures for prompt initial notification
of OE to workers, emergency response personnel, and response organizations,
including, as appropriate, other DOE elements and federal, state, local, and tribal
agencies. Provisions must also be established for continuing effective
communication among response organizations throughout an emergency.
(4) The PMA must notify the Headquarters EOC as promptly as possible, but no
more than 30 minutes after an incident has been categorized as an OE.
(5) As appropriate, notify applicable federal, state, local, and tribal agencies as
promptly as possible. This must occur within 30 minutes, or at an interval
established in mutual agreements, after an incident has been categorized as an OE.
(6) At a minimum, notification of OE to the Headquarters EOC must consist of a
human phone call providing as much information as is known at the time. The
same information must be provided by e-mail either immediately prior to or
following the phone call. Information for initial notification includes, as
available, the following:
(a) Description of the emergency.
(b) Date and time the emergency was discovered.
(c) Damage and casualties.
(d) Whether the emergency has stopped other facility/site operations or
program activities.
(e) Protective actions taken and/or recommended.
(f) Potential impacts.
(g) Agencies involved.
(h) Level of public/media attention.
(i) Contact information of the DOE on-scene point of contact.
(7) Incident status updates and situation reports must be forwarded to the DOE
Headquarters EOC on a continuing basis until incident termination.
DOE O 151.1E Appendix A – Federal Employees
4-1-2024 A-7
(8) Develop and maintain procedures that ensure reports prepared by the PMA are
reviewed in accordance with DOE O 471.7, Controlled Unclassified Information,
current version, and DOE O 471.1, Identification and Protection of Unclassified
Controlled Nuclear Information, current version, and reviewed by an appropriate
classification official, Unclassified Controlled Nuclear Information (UCNI)
Reviewing Official or an appropriate person for Controlled Unclassified
Information (CUI) and the Emergency Manager for UCNI and CUI prior to
release.
k. Emergency Public Information.
(1) The PMA must provide accurate, candid, and timely information consistent with
requirements of the Freedom of Information Act and the Privacy Act to ensure the
health and safety of workers and the public during all incidents. Information must
establish facts, avoid rumors and speculation, and be responsive to public concern
and information needs.
(2) Procedures must be in place to address media inquiries and, as necessary, conduct
briefings or press conferences for other operational emergencies.
(3) Initial news releases or public statements must be approved by the PMA official
responsible for emergency public information review and dissemination.
Following initial news releases and public statements, updates must be
coordinated with the PMA Public Affairs, DOE Public Affairs, and Headquarters
EOC, unless approval is delegated to the PMA.
Section 14
l. Termination and Recovery.
(1) Predetermined criteria for terminating emergencies must be developed and
termination coordinated with off-site agencies.
(2) Reporting requirements must be specified during recovery planning.
(3) Following termination of the incident response and in conjunction with the Final
Occurrence Report DOE O 232.2, Occurrence Reporting and Processing of
Operations Information, current version, each activated ERO must submit a final
report on the emergency response to the site Emergency Manager.
(4) Recovery must include notifications about the termination and establishment of
criteria for resumption of normal operations.
(5) The facility and the accident investigation team must coordinate their activities to
facilitate an orderly transition of responsibilities in accordance with DOE O
225.1, Accident Investigations, current version.
Appendix A – Federal Employees DOE O 151.1E
A-8 4-1-2024
m. Readiness Assurance. The PMA must participate in a formal Readiness
Assurance Program that establishes a framework and associated mechanisms to
validate their emergency plans, procedures, and resources to adequately address
the threats and hazards identified in the All-Hazards Planning Basis and to
ensure timely improvements are made when identified. The Readiness
Assurance Program consists of evaluations, issues management, and the ERAP.
(1) Evaluations include assessments and exercises.
(a) Assessments. Each PMA must assess its emergency management program
annually and record the results of the self-assessment in the ERAP.
(b) Exercises. At a minimum, each site/facility must conduct building
evacuation drills consistent with Federal regulations (to include 41 CFR
Part 102-74.360, What are the Specific Accident and Fire Prevention
Responsibilities of Occupant Agencies?), local ordinances, or appropriate
National Fire Protection Association Standards. Exercises must be
conducted no less than annually to ensure that employees are able to
safely evacuate their work area.
(2) Issues Management includes the identification of issues to create the corrective
action plan and lessons learned.
(a) Corrective action plans for external evaluations must be developed within
45 calendar days of receipt of the final evaluation report.
(b) Corrective actions must be completed as soon as possible. Corrective
actions addressing revision of procedures or training of personnel must be
completed before the next annual emergency management program self-
assessment.
(c) Completion of corrective actions must include a verification and validation
process, independent of those who performed the corrective action, that
verifies that the corrective action has been put in place and validates that
the corrective action has been effective in resolving the original issue.
(d) The readiness assurance program must include a system for incorporating
and tracking lessons learned from training, drills, actual responses, and a
PMA-wide lessons learned program.
(3) Emergency Readiness Assurance Plan. See DOE O 151.1E, Comprehensive
Emergency Management System, Attachment 3, Section 14.c.
DOE O 151.1E Attachment 1 – CRD – Contractors
4-1-2024 Page 1-1
ATTACHMENT 1
CONTRACTOR REQUIREMENTS DOCUMENT (CRD)
DOE O 151.1E, COMPREHENSIVE EMERGENCY MANAGEMENT SYSTEM
Section 15
Regardless of the performer of the work, the contractor is responsible for complying with the
requirements of this CRD. The contractor is responsible for flowing down the requirements
of this CRD to subcontractors at any tier to the extent necessary to ensure the contractor’s
compliance with the requirements. That is, the contractor must (1) ensure that it and its
subcontractors comply with the requirements of this CRD to the extent necessary to ensure
the contractor's compliance and (2) only incur costs that would be incurred by a prudent
person in the conduct of competitive business.
The contractor must establish and maintain a documented emergency management program
that implements the requirements of applicable federal, state, local, and tribal laws,
regulations, and ordinances for fundamental worker safety programs.
In addition to the requirements set forth in this CRD, contractors are responsible for
complying with Attachment 3 to Department of Energy (DOE) O 151.1E, which provides
program requirements applicable to contracts in which this CRD is inserted. References to a
DOE directive in this CRD or in its attachments refer to the CRD associated with the
referenced DOE directive.
Contractors may meet, with prior approval through the formal equivalency and exemption
process, the requirements of this Order by implementing nationally recognized standards or
host institutions applicable standards. See Section 3.c., Equivalencies and Exemptions of
this Order.
DOE O 151.1E Attachment 2 – Federal Employees and Contractors
4-1-2024 Page 2-1
ATTACHMENT 2
ACRONYMS AND ABBREVIATIONS
AAR After-Action Report
AEGLs Acute Exposure Guideline Levels
AEOC Alternate Emergency Operation Center
CESER Office of Cybersecurity, Energy Security, and Emergency Response
CFR Code of Federal Regulations
CIR Critical Information Requirements
COP Common Operating Picture
CRD Contractor Requirements Document
CUI Controlled Unclassified Information
DoD Department of Defense
DOE Department of Energy
EAL Emergency Action Level
EIMC Emergency and Incident Management Council
EMAC Emergency Management Advisory Committee
EOC Emergency Operations Center
EPA Environmental Protection Agency
EPHA Emergency Planning Hazards Assessment
EPZ Emergency Planning Zone
ERAP Emergency Readiness Assurance Plan
ERO Emergency Response Organization
EROC Emergency Response Officer Cadre
ERPG Emergency Response Planning Guidelines
ESF Emergency Support Function
FEM Field Element Manager
FOM Field Office Manager
FSE Full-Scale Exercise
GE General Emergency
GHS Globally Harmonized System
HDBK Handbook
HEPA High Efficiency Particulate Air
HSEEP Homeland Security Exercise and Evaluation Program
HSPD Homeland Security Presidential Directive
ICS Incident Command System
JIC Joint Information Center
Attachment 2 – Federal Employees and Contractors DOE O 151.1E
Page 2-2 4-1-2024
NARAC National Atmospheric Release Advisory Center
NEST Nuclear Emergency Support Team
NFPA National Fire Protection Association
NIMS National Incident Management System
NNSA National Nuclear Security Administration
NRC Nuclear Regulatory Commission
OE Operational Emergency
OPI Office of Primary Interest
OST Office of Secure Transportation
PAC Protective Action Criteria
PAG Protective Action Guide
PAR Protective Action Recommendation
P.L. Public Law
PMA Power Marketing Administration
PPD Presidential Policy Directive
PPE Personal Protective Equipment
SAE Site Area Emergency
SRMA Sector Risk Management Agency
SNM Special Nuclear Material
TED Total Effective Dose
TEEL Temporary Emergency Exposure Limits
UCNI Unclassified Controlled Nuclear Information
Section 16
DOE O 151.1E Attachment 3 – Federal Employees and Contractors
4-1-2024 Page 3-1
ATTACHMENT 3
EMERGENCY MANAGEMENT PROGRAM
This Attachment provides requirements associated with Department of Energy (DOE) O
151.1E, Comprehensive Emergency Management System and is applicable to DOE owned,
leased, and operated laboratories, plants, and sites. This includes contracts in which the
associated Contractor Requirements Document (Attachment 1 of this Order) is inserted.
Each DOE laboratory, plant, and site must establish and maintain an emergency management
program that complies with the Emergency Management Program requirements.
1. PROGRAM ADMINISTRATION AND MANAGEMENT. Program administration and
management must be established to provide effective organizational management and
administrative control of the laboratory, plant, or site emergency management program by
establishing and maintaining authorities and resources necessary to plan, develop,
implement, and maintain a viable, integrated, and coordinated Comprehensive Emergency
Management System. DOE federal and contractor managers responsible for DOE
laboratories, plants, and sites must:
a. Designate an individual to administer the emergency management program.
This individual must:
(1) Be responsible for and have authority for day-to-day operation and maintenance
of the emergency management program.
(2) Have access to management personnel who have authority for laboratory, plant,
and site-level resources and operations.
(3) Brief senior leadership on the emergency management program and their
expected roles and responsibilities during an emergency. This briefing must be
conducted initially and when changes occur that modify their roles and
responsibilities.
(4) Integrate emergency management planning with other applicable programs and
associated documents, as made available, such as the Baseline Needs Assessment,
Site Security Plan, Cybersecurity Plan, Continuity of Operations Plan,
Documented Safety Analysis, and any other programs or documents identified by
the Field Element Manager/Field Office Manager (FEM/FOM).
(5) Oversee implementation of the emergency management plan in accordance with
the requirements of this Order.
(6) Approve or concur on planning documents addressing the program elements listed
in Section 1.b of this Attachment.
b. Ensure the emergency management program addresses the following 14
Attachment 3 – Federal Employees and Contractors DOE O 151.1E
Page 3-2 4-1-2024
program elements, where applicable:
(1) Program Administration and Management
(2) All-Hazards Planning Basis
(3) Emergency Response Organization
(4) Training
(5) Emergency Medical Support
(6) Off-site Response Agencies
(7) Emergency Categorization and Classification
(8) Protective Actions
(9) Consequence Assessment
(10) Emergency Facilities, Equipment, and Systems
(11) Notifications and Communications
(12) Emergency Public Information
(13) Termination and Recovery
(14) Readiness Assurance
c. Analyze capabilities and resource gaps that would stress the laboratory, plant,
or site's capabilities to plan for, respond to, and recover from the hazards
identified in the All-Hazards Planning Basis; and use the analysis in the
development of the emergency management plan.
d. Develop and maintain an all-hazards emergency management plan that is based
on the All-Hazards Planning Basis. The emergency management plan must:
(1) Be reviewed annually and revised, if appropriate.
Section 17
(2) Be submitted to the FEM/FOM for initial approval.
(3) Be submitted to the FEM/FOM for approval of subsequent revisions.
e. Include developed and maintained procedures that describe how the emergency
management plan must be implemented and maintained.
DOE O 151.1E Attachment 3 – Federal Employees and Contractors
4-1-2024 Page 3-3
f. Use a controlled document system for the emergency management plan and
related procedures and documentation.
g. Identify a process for review, approval, and distribution of the emergency
management plan and related procedures and documentation.
h. Address interoperability, integration, and interface with off-site response
agencies for severe incidents with regional impacts.
i. Include developed and maintained procedures that ensure emergency
management documents are reviewed in accordance with DOE O 471.1,
Identification and Protection of Unclassified Controlled Nuclear Information,
current version and DOE O 475.2, Identifying Classified Information, current
version, and reviewed by an appropriate classification official, Unclassified
Controlled Nuclear Information Reviewing Official, or an appropriate person
for Controlled Unclassified Information (CUI) and the Emergency Manager for
classified information, UNCI, and CUI prior to release.
j. Identify and maintain emergency operations records as outlined in DOE O
243.1, Records Management Program, current version.
2. ALL-HAZARDS PLANNING BASIS. The All-Hazards Planning Basis includes an All-
Hazards Survey, an Emergency Planning Hazards Assessment (EPHA), (when applicable),
and the development of Emergency Action Levels (EALs), protective actions, and
Emergency Planning Zones (EPZs). The All-Hazards Survey includes the assessment of all
hazards that are applicable to the operations of the laboratory, plant, or site and the
hazardous material screening process. Based on the All-Hazards Survey results, further
technical analysis of hazardous materials is conducted, if appropriate, through an EPHA.
The results of the EPHA determine if a laboratory, plant, or site is included as a Hazardous
Materials Program and are used to develop the EALs, protective actions, and EPZ. The
All-Hazards Planning Basis must be shared with the laboratory, plant, or site security
program.
a. All-Hazards Survey. An All-Hazards Survey must be performed by DOE federal
and contractor staff responsible for DOE laboratories, plants, and sites. Its purpose
is to identify all threats and hazards that may impact workers or public health and
safety, the environment, or the operation of that laboratory, plant, or site; and
establish the planning basis for the emergency management program. An All-
Hazards Survey may cover a single or multiple facilities at a laboratory, plant, or
site, or an entire laboratory, plant, or site. Other DOE requirements, assessments,
or documentation may be used or referenced, to meet the requirements, in part or in
whole, of the All-Hazards Survey. Each All-Hazards Survey must:
(1) Address the following three types of hazards:
(a) Natural hazards, which result from acts of nature, such as tornadoes,
Attachment 3 – Federal Employees and Contractors DOE O 151.1E
Page 3-4 4-1-2024
hurricanes, earthquakes, wildland fires, droughts, floods or excessive
precipitation, animal disease outbreak, epidemics, or pandemics.
(b) Technological hazards, which result from accidents or the failures of systems
and structures, such as hazardous materials releases or dam failures.
Section 18
(c) Human-caused hazards, which result from an intentional or unintentional
action taken by persons or an adversary.
(2) Describe the applicable health, safety, and environmental impacts of the potential
hazards.
(3) Be approved by the FEM/FOM before implementation.
(4) Be reviewed, at a minimum, every three years from the date of last approval, and,
if appropriate, updated. If the review determines there are no changes from the
last approved All-Hazards Survey, a letter or memorandum to the FEM/FOM
must be submitted to document the review and provide notification that an update
is unnecessary. The date of this letter or memorandum serves as the revised date
of last approval.
(5) Be updated before there are significant changes to laboratory, plant, or site
operations or hazardous materials. At a minimum, significant changes include
new hazardous materials operations, recognition of hazards not previously
identified, and changes that would result in a positive Unreviewed Safety
Question for nuclear facilities, as defined in 10 Code of Federal Regulations
(CFR) Part 830, Nuclear Safety Management. Changes that result in a reduction
of hazards with no adverse effect on safety or emergency preparedness or
response may be included in the next update.
(6) Hazardous Materials Screening Process. All hazardous materials at a DOE
laboratory, plant, or site must be considered in the screening to identify specific
hazardous materials and quantities that, if released, could produce impacts
consistent with the definition of an Operational Emergency (OE). Hazardous
materials must be screened as follows:
(a) Laboratories, plants, and sites may use either the Globally Harmonized
System (GHS), the National Fire Protection Association (NFPA) 704,
Standard System for the Identification of the Hazards of Materials for
Emergency Response, or an alternative method developed by the National
Nuclear Security Administration’s (NNSA’s) Office of Emergency
Management to screen hazardous material. Only one method can be used
and must be identified in the laboratory, plant, or site’s All-Hazards Survey
or emergency management plan. Laboratories, plants, and sites must clearly
state the routes of exposure and the health effect categories in any
documentation for the FEM/FOM to approve the use of GHS.
DOE O 151.1E Attachment 3 – Federal Employees and Contractors
4-1-2024 Page 3-5
(b) Each hazardous material container and associated hazardous process must be
evaluated separately, unless one of the following conditions exists, in which
case the total quantity of the hazardous material must be used.
1 Container is interconnected with other containers, or
2 Multiple containers are located within a facility such that a credible
incident could result in release of the contents of multiple containers.
(c) The capacity of the container must be used when the quantity of the
hazardous material in the container is unknown.
(d) Materials can be excluded from the screening process if they meet one of the
following criteria:
1 Materials used in the same form, quantity, and concentration as a
product packaged for distribution and use by the public (for example,
consumer products for household use).
2 Materials that, because their physical form or other factors, do not
present an airborne exposure hazard. This includes solid materials in
a form with particle size >10 microns and solid materials with no
credible release scenario to reduce the material to particles <10
microns; liquids with a vapor (partial) pressure of <10 mmHg at 25oC;
and aqueous solutions where the hazardous component is a non-
volatile solute.
Section 19
3 Ordinary product of combustion when associated with a scenario
involving a combustion incident.
4 Explosives, regardless of the facility designation, provided the
explosives are also screened through 2.a.(6)(e)4, of this Attachment.
5 Simple asphyxiants and cryogenic materials if the material cannot
impact workers, visitors, or the public.
6 Chemical waste in concentrations below one percent by weight of the
mixture, as defined in 40 CFR 68, Chemical Accident Prevention, and
chemically neutralized chemical waste.
7 Sealed radioactive sources that are engineered to pass the special form
testing specified by Department of Transportation (DOT) or the
American National Standards Institute and radiological materials
stored in DOT Type B shipping containers with overpack if the
Certificates of Compliance are current, the materials stored are
authorized by the Certificate, and the conditions are covered under 10
Attachment 3 – Federal Employees and Contractors DOE O 151.1E
Page 3-6 4-1-2024
CFR Part 71, Packaging and Transportation of Radioactive Material.
8 Materials that have a Health Hazard rating of 0, 1, or 2 based on
NFPA 704. This only applies if NFPA 704 is the screening method
approved for the laboratory, plant, or site.
9 Materials with a GHS Acute Toxicity Hazard Category of 3, 4, or 5.
If multiple GHS Acute Toxicity routes of exposure (inhalation, oral,
or dermal) are available for a material, the Temporary Emergency
Exposure Limits (TEEL) HBK-1046-2016 hierarchy for routes of
exposure (inhalation, oral, dermal, intraperitoneal, intravenous) must
be followed. This only applies if GHS is the approved screening
method for the laboratory, plant, or site.
10 Materials with a GHS Corrosion/Irritation (skin or eye) Category 2 or
3. If a GHS Acute Toxicity Hazard Category 1 or 2 is available, this
exclusion does not apply. This only applies if GHS is the approved
screening method for the laboratory, plant, or site.
(e) Hazardous materials that do not screen out by exclusions in Section
2.a.(6)(d), of this Attachment, require further consideration, including:
1 The release of hazardous materials, other than ordinary products of
combustion, that could result from ignition (fire or explosion) of
excluded materials.
2 Radiological Materials.
a. Radioactive materials associated with a defined Hazard Category 1,
2, or 3 nuclear facility per 10 CFR Part 830, specifically those
materials contributing to the categorization of such a facility when in
quantities greater than the largest Category 3 value (or if the sum of
the ratios) exceeds values in accordance with DOE-STD-1027-2018,
Hazard Categorization of DOE Nuclear Facilities, or revision used
in approved hazard categorization, will require further analysis in the
EPHA.
b. Materials associated with a facility or activity defined as an
accelerator per DOE O 420.2, Safety of Accelerator Facilities,
current version, may be screened out if analysis indicates that all
incidents would be classified as less than an Alert.
3 Hazardous Biological Agents and Toxins. Hazardous biological
agents and toxins exceeding the minimum quantities specified to be
federally regulated identified in lists published in Department of
Health and Human Services regulations (42 CFR Part 73, Select
DOE O 151.1E Attachment 3 – Federal Employees and Contractors
4-1-2024 Page 3-7
Section 20
Agents and Toxins) and Department of Agriculture regulations (7 CFR
Part 331, Possession, Use, and Transfer of Select Agents and Toxins
and 9 CFR Part 121, Possession, Use, and Transfer of Select Agents
and Toxins) will require further analysis in the EPHA.
4 Chemicals.
a. Chemicals not meeting the exclusion criteria in Section 2.a.(6)(d), of
this Attachment, will require further analysis in the EPHA if the
quantity is greater than a quantity that can be “easily and safely
manipulated by one person” in accordance with the provisions of 29
CFR Part 1910.1450, Occupational Exposure to Hazardous
Chemicals in Laboratories. Containers with capacities of no more
than 5 gallons (19 L) for liquids, 40 pounds (18 kg) for solids, or 10
pounds (4.5 kg) for compressed gases are defined as being “easily
and safely manipulated by one person.”
b. Chemical waste, except for satellite accumulation points, in storage
quantities exceeding individual containers with capacities of 5
gallons (19 L) for liquids, 40pounds (18 kg) for solids, or 10 pounds
(4.5 kg) for compressed gases, and concentration comparable to that
which would require such a similar classification will not screen out
and will require further analysis in the EPHA.
c. Substances that may represent an extraordinary toxic hazard beyond
the local incident scene due to high acute toxicity (Acute Exposure
Guideline Level (AEGL)-3. Emergency Response Guideline
(ERPG)-3, or TEEL-3 < 3 ppm) and dispersibility (for example,
chemical warfare nerve agents) exceeding 1-pound (0.45 kg)
threshold value will not screen out and will require further analysis in
the EPHA.
(f) Based on the professional judgment of the person performing or approving
the hazardous materials screening, it is determined that additional analysis
and planning is warranted, even if the material screened out in the All-
Hazards Survey, an EPHA can still be required.
b. Emergency Planning Hazards Assessment. An EPHA must be developed for
hazardous materials that do not screen out based on the criteria in 2.a.(6) of this
Attachment. The EPHA determines, through quantitative analysis, if a laboratory,
plant, or site is included as a Hazardous Materials Program and provides the basis
for establishing a graded approach that will meet the Hazardous Materials Program
requirements outlined in this Attachment.
(1) If the quantitative analysis indicates that all scenarios would not rise to at least the
level of an OE classified as an Alert, an EPHA is not required to be maintained.
The result of quantitative analysis is directly incorporated or referenced in the All-
Attachment 3 – Federal Employees and Contractors DOE O 151.1E
Page 3-8 4-1-2024
Hazards Survey to indicate the laboratory, plant, or site is not considered part of
the Hazardous Materials Program.
(2) Office of Secure Transportation (OST) recipient sites will receive an unclassified
EPHA for their OST shipments and must incorporate the results from the EPHA
into their emergency management program.
(3) An EPHA must be developed for shipments that do not satisfy governing DOT
regulations and specifications for commercial hazardous materials transport based
on DOE O 460.1, Hazardous Materials Packaging and Transportation Safety,
current version. However, if a shipment satisfies DOT regulations and
specifications, then an EPHA is not required.
(4) Hazardous Materials Program laboratories, plants, and sites EPHAs must:
Section 21
(a) Define and describe the laboratory, plant, or site and its operations providing
sufficient detail to support the identification, location, and characterization of
all hazards and their potential consequences.
(b) Characterize the hazardous materials and relevant safety control systems in
the laboratory, plant, or site, including:
1 Maximum quantity of material and its storage or process locations.
2 Conditions under which the material is stored or used.
3 Properties of the material that are needed for determination of source
term and consequence analysis.
4 A description of relevant administrative and engineered controls that
would prevent or mitigate the initiation of a hazardous material release.
(c) Select potential release scenarios associated with the hazardous materials and
relevant safety control systems characterized, to include:
1 Credible natural, technological, and human-caused hazards.
2 Severe incidents, including beyond design-basis scenarios.
3 Consideration of malevolent acts. If information in a security risk
assessment developed in accordance with DOE O 470.3, Design Basis
Threat, current version, or consequence information is sufficient to
determine that malevolent acts are bounded by the scenarios already
evaluated, additional consequence modeling or calculations are not
required, unless an EPHA analyst determines otherwise.
DOE O 151.1E Attachment 3 – Federal Employees and Contractors
4-1-2024 Page 3-9
4 Laboratories, plants, and sites with Defense Nuclear Facilities must
include potential scenarios, ranging from low-consequence, high-
probability scenarios to high-consequence, low-probability scenarios, to
capture a comprehensive picture of the types of incidents and the range of
associated consequences that could occur at an individual laboratory,
plant, or site.
(d) Select the representative cases from the full range of possible release
scenarios identified, analyze each selected scenario, calculate potential
consequences, and identify recognition factors, if available. The following
must be included:
1 Selection of analyzed scenarios using short, descriptive names.
2 Justification for the selection of dispersion and consequence models and
input parameters.
3 Use of at least two sets of dispersion conditions in computing
consequence versus distance for each source term. At minimum, the two
dispersion conditions are:
a. Conservative – DOE site’s 95th percentile worst case, based on the
last five-years of the laboratory, plant, or site’s meteorological data;
or F stability and a wind speed of 1.5 m/s.
b. Average – DOE site specific average, based on the last five-years of
the laboratory, plant, or site’s meteorological data; or D stability and
a wind speed of 3 m/s.
4 Use of 25 miles for accuracy if dispersion model results go beyond 25
miles. Farther distances may be reported for information.
5 Tabulated consequences of the release at key receptor locations identified
for each laboratory, plant, or site containing significant amounts of
hazardous materials must be calculated to include:
a. The region greater than or equal to 30 meters, but less than 100
meters from the point of release.
b. The region greater than or equal to 100 meters, but less than the
nearest site boundary from the point of release.
c. The region at or beyond the nearest site boundary from the point of
release.
d. Nearest emergency response facilities and worker assembly areas.
Section 22
Attachment 3 – Federal Employees and Contractors DOE O 151.1E
Page 3-10 4-1-2024
e. Nearest off-site at-risk populations or applicable fire-zones, or
equivalent, relevant to off-site jurisdiction.
6 Consequence of each radiological, biological, and chemical release must
be calculated, summarized, and documented in the form of a graph or
table. The graph or table must give the dose or concentration versus
distance, extending out to a distance beyond where Thresholds of Early-
Lethality (TELs) are exceeded and out to a distance beyond where
Protective Action Criteria (PACs) are exceeded for the receptors
identified in 2.b.(4)(d)5.
a. For radioactive materials, the current Early-Phase Protective Action
Guides (PAGs) of whole-body dose promulgated by the
Environmental Protection Agency (EPA) must be used [1 rem (10
mSv) adult Total Effective Dose (TED) consistent with the
recommended dose limit for the public]. Use 100 rem for the TEL
criteria.
b. For hazardous biological agents and toxins, PACs are considered
exceeded and protective actions are required for any actual or
potential release of agents or toxins outside of secondary
containment barriers. Long-term PACs are specified by state or
local public health officials.
c. For chemicals, the PAC-2, listed in order of preference, must be used
(use PAC-3 values for the TEL criteria):
i. AEGLs promulgated by the EPA.
ii. ERPGs published by the American Industrial Hygiene
Association.
iii. TEELs maintained by the DOE/NNSA’s Office of Emergency
Management.
7 Some facilities, such as underground facilities, require additional
consideration of how airborne contaminants may be released since an
atmospheric dispersion model would not provide a valid result.
8 Document functioning and non-functioning control measures and
engineered safety systems, to include containment systems, fire
suppression systems, filters, administrative controls, safeguards, and
security systems, if appropriate.
(e) Be documented and submitted to the FEM/FOM for approval. The
documentation must be prepared and documented in a manner that permits
critical review of the analyses and the results and, if necessary,
DOE O 151.1E Attachment 3 – Federal Employees and Contractors
4-1-2024 Page 3-11
reconstruction by independent analysts. Detailed description of assumptions,
methodology, models, and evaluation techniques must be included unless
they are documented elsewhere and referenced.
(f) Be reviewed, at a minimum, every three years from the date of last approval,
and, if appropriate, updated. If the review determines there are no changes
from the last approved EPHA, a letter or memorandum to the FEM/FOM
must be submitted to document the review and provide notification that an
update is unnecessary. The date of this letter or memorandum serves as the
revised date of last approval.
(g) Be updated and submitted for approval before there are significant changes to
laboratory, plant, or site operations or hazardous materials. At a minimum,
significant changes are those that require a new EPHA or new or changed
EALs. Changes that result in a reduction of hazards with no adverse effect
on safety or emergency preparedness or response may be included in the next
EPHA update.
(5) Hazards Materials Program laboratories, plants, and sites must also:
(a) Adjust the emergency management program to be commensurate with
hazards that remain after a decontamination and decommission action is
completed at each laboratory, plant, and site closure.
Section 23
(b) Establish and maintain an accurate and timely method for tracking changes in
operations, processes, or accident analyses that involve hazardous materials.
The method must allow sufficient time for emergency management personnel
to review the EPHA and modify plans and procedures, before introducing
new hazardous materials into the laboratory, plant, or site.
(c) Provide a temporary supplemental analysis report for hazardous materials if
the hazardous materials are coming on site prior to full EPHA approval. The
analysis must include:
1 The possible effects on the adequacy of the facility and site emergency
plans.
2 Temporary compensatory measures that are being considered or
implemented.
3 A schedule for updating the analysis, reporting the results, and proposing
any needed changes to the site’s emergency planning or response
program, if the hazardous material will remain on site for more than six
months.
4 Submission for approval to the FEM/FOM.
Attachment 3 – Federal Employees and Contractors DOE O 151.1E
Page 3-12 4-1-2024
(d) Use the EPHA results to determine the necessary planning, personnel,
resources, and equipment for the Hazardous Materials Program, if the release
or loss of control of the hazardous material analyzed in the EPHA indicates
the potential for an Alert, Site Area Emergency (SAE), or General
Emergency (GE).
1 An Alert occurs when one or more of the following conditions are met:
a. The radiation dose from any release to the environment of radioactive
material or a concentration in air of hazardous chemical material is
expected to exceed the applicable PAG or PAC at or beyond 30
meters but not beyond 100 meters from the point of release or beyond
the laboratory, plant, or site boundary.
b. An actual or potential substantial degradation in the level of safety or
security of nuclear weapon, component, or test device at a fixed
location that would not pose an immediate threat to workers or the
public.
2 An SAE occurs when one or more of the following conditions are met:
a. The radiation dose from any release of radioactive material or
concentration in air from any release of other hazardous material is
expected to exceed the applicable PAG or PAC at or beyond 100
meters from the point of release but not at or beyond the laboratory,
plant, or site boundary.
b. An actual or potential threat to the integrity of a nuclear weapon,
component, or test device that may adversely impact the health and
safety of workers in the immediate area, but not the public.
3 A GE occurs when one or more of the following conditions are met:
a. The radiation dose from any release of radioactive material or a
concentration in air from any release of other hazardous material is
expected to exceed the applicable PAG or PAC at or beyond the
laboratory, plant, or site boundary.
b. Actual or likely catastrophic failures in safety or security systems
threatening the integrity of a nuclear weapon, component, or test
device at a fixed location that may adversely impact the health and
safety of workers and the public.
c. Response Planning Elements. The EPHA provides a quantitative estimate of the
consequences of each release at specific locations. Once the EPHA is complete,
laboratories, plants, and sites recognized as a Hazardous Materials Program must
use the results to develop their EALs, EPZ, and protective actions.
DOE O 151.1E Attachment 3 – Federal Employees and Contractors
4-1-2024 Page 3-13
Section 24
(1) Develop specific EALs for all potential OEs identified in the EPHA and include
protective actions corresponding to each EAL.
(a) EALs are required for malevolent acts and severe incidents, including
beyond design basis accidents, not bounded by scenarios already evaluated.
(b) EALs development must include specific indications to distinguish between
different potential classifications for an analyzed scenario or set of scenarios.
(c) For EALs development, use the conservative dispersion vs. distance
calculations and worst-case source term results from the EPHA analysis.
(d) EALs must be documented according to the incident type or recognition
categories used in the laboratory, plant, or site classification procedures. For
each incident type, it must:
1 Briefly describe the incident, condition, or recognition indicators.
2 Provide recommended classification (Alert, SAE, or GE) of the OE based
on the EPHA analysis.
3 Provide protective actions to be taken by workers and off-site protective
action recommendations (PARs) for the public based on distance to PAG
or PAC calculations from the EPHA.
(2) Determine and document the size of the EPZ.
(a) The EPHA must define an EPZ for the analyzed laboratory, plant, or site as
the area requiring detailed planning. For laboratories, plants, or sites with
multiple EPHAs, a laboratory, plant, or site-level consolidated and integrated
EPZ must be defined incorporating the EPZ from the individual EPHAs.
(b) The integrated EPZ for the laboratory, plant, or site must be of sufficient size
that:
1 Analyzed scenarios do not require predetermined protective actions
beyond the EPZ.
2 The maximum EPZ for any laboratory, plant, or site must not exceed a
nominal radius of 10 miles (16 km) according to report NUREG-
0396/EPA 520/1-78-016, regardless of the DOE or NNSA property
boundary.
3 If the nearest distances to off-site key receptor locations are beyond the
10-mile EPZ, the key receptor locations must still be included in the
laboratory, plant, or site-level emergency management plan to identify
PAR distances to state and local decision makers to protect members of
the public.
Attachment 3 – Federal Employees and Contractors DOE O 151.1E
Page 3-14 4-1-2024
(c) Boundaries may be defined by geopolitical lines or distance and in
coordination with local, State, tribal, and territorial authorities.
(d) The planning process must recognize and provide for the need to refine the
predetermined protective actions and carry out protective actions in limited
portions of the EPZ for specific incidents or conditions.
3. EMERGENCY RESPONSE ORGANIZATION (ERO). An ERO is a structured
organization with overall responsibility for initial and ongoing emergency response. It
includes personnel supporting the incident, to include those in the EOC, and personnel at
the scene managing the incident. It may consist of internal and external organizations.
Each DOE, laboratory, plant, and site must establish and maintain an ERO. A single ERO
may cover one or more location/building at a laboratory, plant, or site. At a minimum, the
ERO must:
a. Have the capability to manage the first operating period of a Type 4 incident as
defined by the National Incident Management System (NIMS).
b. Establish mechanisms, consistent with NIMS, for scaling the activation based
on incident severity and expanding the initial response capability when local
resources are overwhelmed.
c. Consist of personnel with capabilities and resources to respond to incidents
Section 25
based on the All-Hazards Planning Basis.
d. Activate for any declared OE and other severe incidents. Scale the activation based
on the severity of the incident and in accordance with emergency management
plans.
e. Include a position with decision-making authority (the Senior Official) to
implement the laboratory, plant, or site emergency management plan, to include
management and control of all aspects of the response. This person is not the
Incident Commander managing the incident.
f. Designate a primary and at least one alternate for each laboratory, plant, or site
ERO position (this does not include first responders or off-site personnel) to
manage, support, and control the initial and ongoing emergency response and
plan for termination and recovery.
g. Establish an effective first responder capability to mitigate all-hazard
emergencies including emergency medical, fire, hazardous material, and
applicable rescue emergencies as derived through the All-Hazards Planning
Basis and, if applicable, the Baseline Needs Assessment.
h. Establish control at the incident scene in accordance with the Incident
Command System (ICS) and integrate activities with federal, state, local and
tribal agencies that provide on-site emergency response at the incident scene
DOE O 151.1E Attachment 3 – Federal Employees and Contractors
4-1-2024 Page 3-15
using the principles of Unified Command.
i. Establish and maintain communications and coordination between the EOC and
the incident scene.
j. Maintain and use a capability for developing, updating, and disseminating a
common operating picture (COP).
k. Maintain two-way information exchange with the Headquarters Emergency
Operations Center (EOC) for the duration of the incident.
l. Develop incident action plans, consistent with ICS, to support:
(1) Establishment of the operational period.
(2) Establishment of overall priorities.
(3) Establishment of operational objectives.
(4) Establishment of personnel accountability.
m. Provide ERO members with a method of identification for access to the
assigned emergency response location.
4. TRAINING. A comprehensive, coordinated, and documented training program must be an
integral part of the emergency management program to ensure that preparedness activities
for establishing and maintaining program-specific emergency response capabilities are
accomplished. Training programs must include the following:
a. Worker Training.
(1) Training must be conducted and documented upon initial assignment and when
there are changes affecting worker actions or responsibilities.
(2) Refresher training on protective actions must be provided annually. If a
protective action is performed successfully during an exercise or actual incident,
the annual training requirement is met for that protective action.
(3) Training must cover hazards and protective actions workers may be expected to
take in accordance with the All-Hazards Planning Basis. For those workers who
are likely to witness a hazardous material release, the training must include the
procedures for notification of the release to proper authorities.
(4) Determine if additional training must be provided to workers to address response
actions that may be necessary for severe incidents with regional impacts when the
laboratories, plants, and sites may be isolated from off-site response assistance
and infrastructure support.
Attachment 3 – Federal Employees and Contractors DOE O 151.1E
Page 3-16 4-1-2024
Section 26
(5) Determine if additional training must be provided to workers at specific facilities.
This training may consist of facility-specific procedures for safe walk-away
provisions and/or facility-specific response steps to take when there are
disruptions to critical infrastructure.
(6) Worker participation in a building evacuation at least annually, and consistent
with frequency defined in 41 CFR Part 102-74.360, What are the Specific
Accident and Fire Prevention Responsibilities of Occupant Agencies and other
applicable CFRs, standards and federal, state, local, or tribal regulations. Worker
participation in building evacuations must also be conducted after substantial
changes are made to a building, which result in a change to evacuation procedures
or pathways.
b. ERO Training.
(1) Develop a training and qualification program to establish and maintain specific
emergency response capabilities as determined by the All-Hazards Planning
Basis. This training is in addition to other training and certification requirements
required to perform general job functions. Documentation of the training
requirements must include the courses, method of instruction, frequency, and
intended audience.
(2) Assess laboratory, plant, and site ERO member proficiency at least annually.
This may be accomplished by participation in training, exercises, or real-world
incidents. Emergency response personnel (for example, fire, hazardous material,
police, emergency medical services) who perform essentially the same functions
in an ERO as they do on a day-to-day basis demonstrate proficiency doing their
everyday jobs. This annual assessment does not apply to off-site response
agencies. The training for off-site response agencies is addressed in Attachment
3, Section 4.c. of this Order.
(3) ERO training must be provided upon initial assignment and when there are
significant changes to expected emergency response capabilities. Initial training
requirements must include:
(a) Applicable principles of ICS 100, Introduction to ICS, and ICS 700, NIMS,
An Introduction.
(b) Laboratory, plant, and site-specific emergency response concept of
operations, as documented in the emergency management plan, applicable to
each position.
(c) Position-specific roles and responsibilities to include plans, procedures, job
aids, and associated equipment and systems.
(4) Refresher training must be provided no less than annually and include:
DOE O 151.1E Attachment 3 – Federal Employees and Contractors
4-1-2024 Page 3-17
(a) Lessons learned.
(b) Best practices.
(c) Identified gaps or deficiencies in individual training.
(5) Hazardous Materials Program laboratories, plants, and sites must incorporate
additional self-study or classroom training on EPHAs, EALs, emergency
categorization, and emergency classification to those ERO members performing
those functions.
c. Off-Site Response Agencies Training.
(1) Annually offer orientation to emergency responders based on the laboratory,
plant, and site-specific conditions and hazards identified in the All-Hazards
Planning Basis.
(2) Training must be available on unique hazards, as appropriate, to emergency
responders, both primary and pre-defined mutual aid. This may include
equipment, hazardous materials identified in the EPHA, or facility configuration.
d. Visitor Training. The laboratory, plant, or site must provide information on
laboratory, plant, or site protective actions to visitors who have unescorted
access.
Section 27
5. EMERGENCY MEDICAL SUPPORT. DOE laboratories, plants, and sites must
accomplish the following:
a. Conduct planning for medical treatment associated with incidents identified in
the All-Hazards Planning Basis. Pre-planning with off-site responder resources
must address how they integrate emergency medical support in accordance with
applicable laws, regulations, and standards.
b. Establish provisions, where applicable, for sharing patient information between on-
site and off-site health care providers during emergencies. Provisions must be
consistent with the requirements of the 45 CFR Part 160, General Administrative
Requirements, 45 CFR Part 164, Security and Privacy, Subparts A and E, and
Privacy Act of 1974, as amended, 5 United States Code (U.S.C.) Section 552a,
Records Maintained on Individuals.
c. Hazardous Materials Program laboratories, plants, and sites must document the
process to transport, accept and treat contaminated, and injured personnel.
Ensure implementing agreements, as appropriate, are in place with emergency
medical first responder organizations, medical receiving facilities, and
emergency medical transport services (including all reasonable modes of
transportation).
Attachment 3 – Federal Employees and Contractors DOE O 151.1E
Page 3-18 4-1-2024
6. OFF-SITE RESPONSE AGENCIES. DOE laboratories, plants, and sites must establish
and maintain interfaces with federal, state, local, or tribal agencies responsible for
emergency response or those who may be used to supplement response capabilities based
on threats and hazards identified in the All-Hazards Planning Basis, to include planning for
severe incidents. DOE laboratories, plants, and sites must accomplish the following
activities with off-site response agencies:
a. Conduct training and orientation per Attachment 3, Section 4.c., of this Order.
b. Determine access protocols for emergency conditions.
c. Establish a process for communications to use during on-site response.
d. Establish a process to coordinate emergency public information during an
incident involving off-site response agencies that may affect or be of interest to
the media and public as required in Attachment 3, Section 12 of this Order.
e. Hazardous Materials Program laboratories, plants, and sites must coordinate
with federal, state, local, and tribal agencies on the following:
(1) Address off-site protective action recommendations based on the laboratory,
plant, or site’s EPHAs.
(2) Determine a notification process to use during emergencies when protective
actions may be recommended off-site.
(3) Provide information from EPHA analyses to appropriate state, tribal, county, and
local agencies on estimated bounding scenario distance where PAC would be
exceeded at specific off-site receptors for off-site organizations’ incident response
planning. In addition, laboratories, plants, and sites must provide information as
defined in 40 CFR 355, Emergency Planning and Notification.
(4) Provide near real-time information to appropriate state, tribal, county, and local
agencies during a release of hazardous materials when PAC may be exceeded at
specific off-site receptors, including at-risk populations such as emergency
buildings, schools, and hospitals, to facilitate off-site organization decision-
making regarding the appropriate level of response.
(5) Conduct planning for off-site radiological monitoring support with state, tribal,
county, and local governments for GE involving radiological material releases.
Section 28
7. EMERGENCY CATEGORIZATION AND CLASSIFICATION. Categorization is the
DOE process for determining whether an incident or condition is an OE. Categorization
applies to all laboratories, plants, and sites. The classification of an OE is the analysis of
hazardous materials involved in an OE to determine if they fall into one of the three
emergency classes (Alert, SAE, GE). Classification only applies to Hazardous Materials
DOE O 151.1E Attachment 3 – Federal Employees and Contractors
4-1-2024 Page 3-19
Program laboratories, plants, and sites.
a. Categorization.
(1) DOE laboratories, plants, and sites must declare an OE when incidents occur that
represent a significant degradation in the level of safety at a laboratory, plant, or
site resulting in potential health and safety hazards to workers or the public.
Indicators for identifying the conditions of an OE must be developed for the
spectrum of emergency conditions identified in the All-Hazards Planning Basis.
For hazardous materials sites, these indicators are defined in the EALs.
(2) Predetermined decision-makers must categorize an incident as an OE within 15
minutes after the availability of laboratory, plant, or site’s defined indicators that
an OE has occurred. Categorization must occur no more than 30 minutes after
discovery. Such incidents include, but are not limited to:
(a) Incidents or conditions that represent, cause, or have the potential to cause
serious health and safety impacts to workers or members of the public.
1 The discovery of radioactive or other hazardous material contamination
from past DOE operations that may have caused, is causing, or may
reasonably be expected to cause uncontrolled personnel exposures
exceeding the PAG at 1 rem TED or PAC-2 at 30 meters.
2 An occurrence that causes significant structural damage to DOE
facilities, with confirmed or suspected personnel injury or death.
3 Any mass casualty incident, as determined and documented by the
laboratory, plant, or site.
4 A criticality incident.
5 An off-site hazardous material incident not associated with DOE
operations that is observed to have, or is predicted to have, an impact on-
site such that protective actions are required for DOE workers.
(b) Any actual or potential release of a hazardous biological agent or toxin
outside of the secondary barriers of the biocontainment area.
(c) Any actual or potential release of hazardous material or regulated pollutant to
the environment that could result in significant off-site consequences, such as
major wildlife kills, wetland degradation, aquifer contamination, or the need
to secure downstream water supply intakes.
(d) Security incidents subject to reporting in accordance with DOE O 470.4,
Safeguards and Security Program, current version, or other directives as
Attachment 3 – Federal Employees and Contractors DOE O 151.1E
Page 3-20 4-1-2024
applicable. Per this Order, foreign involvement in security incidents must be
reported to the Counterintelligence Directorate within the Office of
Intelligence and Counterintelligence. Safeguards and Security OEs include:
1 Unplanned detonation of an explosive device or a credible threat of
detonation resulting from the location of a confirmed or suspected
explosive device.
2 A terrorist attack, active threat (e.g., armed assault), cyber security
incident with the potential to endanger human life, health, or the
environment, or sabotage incident involving a DOE laboratory, plant, or
site.
Section 29
3 Kidnapping or taking hostages involving a DOE laboratory, plant, or site
worker or visitor.
(3) The following incidents or conditions represent an actual or potential release of
hazardous materials from an OST shipment, or a major security incident without a
hazardous materials release, and must be categorized as an OST OE.
(a) A terrorist attack or other criminal act involving an OST transportation
mission that requires the deployment of OST security assets at the emergency
scene.
(b) Any incident involving an OST transportation mission containing hazardous
materials that causes the initial responders to initiate protective actions at
locations beyond the immediate area.
(c) Failures in safety or security systems that threaten the integrity of a nuclear
weapon, component, or test device.
(d) A transportation emergency resulting in damage, or potential damage, to a
nuclear explosive, nuclear explosive-like assembly, or Category I/II quantity
of special nuclear material.
(4) An OE, once categorized, will remain an OE until the emergency response is
terminated, unless the original categorization was incorrect.
b. Classification.
(1) Hazardous Materials Program laboratories, plants, and sites must:
(a) Use developed EALs from the All-Hazards Planning Basis to classify OEs
involving the actual or potential airborne release of (or loss of control over)
hazardous materials from on-site as an Alert, SAE, or GE.
DOE O 151.1E Attachment 3 – Federal Employees and Contractors
4-1-2024 Page 3-21
(b) Classify an OE as either an Alert, SAE, or GE, in order of increasing
severity. Classification aids in the rapid communication of critical
information and the initiation of appropriate time-urgent emergency response
actions.
(c) Declare a classification when incidents are predicted, are in progress, or have
occurred that result in an actual or credible threat of substantial degradation
in the level of control over hazardous materials. The declaration of:
1 An Alert requires the notification and assembly of the ERO. It may not
require activation of the EOC.
2 An SAE requires activation of the ERO. It may not require activation of
the EOC.
3 A GE requires the activation of the ERO, the EOC, and the
recommendation of public protective actions.
(2) OEs, once classified, must not be downgraded to a lower classification, unless the
original classification was incorrect.
(3) OEs involving federally regulated hazardous biological agents/toxins are not
classified. Protective actions are required for any actual or potential release of
biological agents/toxins outside of secondary containment barriers.
(4) OST OEs are not classified.
8. PROTECTIVE ACTIONS.
a. DOE laboratories, plants, and sites must identify protective actions commensurate
with the All-Hazards Planning Basis and potential hazards at the laboratories, plants,
and sites; and maintain procedures for prompt issuance of protective actions to
workers.
b. Protective actions must be predetermined and serve to minimize emergency related
consequences and maximize life safety and health. DOE laboratories, plants, and sites
must accomplish the following:
(1) Develop a process to issue protective actions.
(2) Develop a procedure to account for workers and visitors and to assist in
identifying workers and visitors who may need rescue or assistance.
Section 30
(3) Consider whether additional protective actions are needed for severe incidents,
such as self-help instructions when the laboratory, plant, or site is isolated from
outside response assistance and evacuation of the laboratory, plant, or site when
Attachment 3 – Federal Employees and Contractors DOE O 151.1E
Page 3-22 4-1-2024
conditions are deteriorating.
c. Hazardous Materials Program laboratories, plants, and sites, must incorporate the
following additional requirements:
(1) Identify predetermined on-site protective actions and off-site PARs consistent
with the hazard and duration of the release based upon the results of EPHAs and
EALs.
(2) Identify and evaluate incidents in which combinations of protective actions for
varying buildings and locations may apply.
(3) Identify authorities for the lifting or adjustment of protective actions once
protective actions have been taken.
(4) Establish methods for controlling, monitoring, and maintaining records of
personnel exposure to hazardous materials.
(5) Establish methods for controlling access to contaminated areas and for
decontaminating personnel or equipment exiting the area.
(6) Identify actions that may be taken to increase the effectiveness of protective
actions, such as shutdown of heating, ventilation, and air conditioning while
sheltering-in-place.
9. CONSEQUENCE ASSESSMENT. Hazardous Materials Program laboratories, plants, and
sites must compute and correctly assess the estimates of on-site and off-site consequences
of actual and potential releases of hazardous materials throughout the emergency response.
The laboratory, plant, or site must accomplish the following:
a. Consider site specific characteristics, which must include topography and
meteorology.
b. Integrate consequence assessment with emergency classification and protective action
decision-making.
c. Integrate facility and field indications and measurements per the emergency
management plan.
d. Coordinate with off-site response agencies.
e. Maintain the capability to use the National Atmospheric Release Advisory Center
(NARAC) as part of near real-time consequence assessment activities for primary,
backup, and/or corroborating consequence assessments.
f. Ensure that laboratory, plant, or site meteorological data and information on source
terms for actual or potential release of hazardous materials to the atmosphere are
DOE O 151.1E Attachment 3 – Federal Employees and Contractors
4-1-2024 Page 3-23
available or can be made available to NARAC to facilitate near real-time
computations.
g. Maintain consequence assessment and atmospheric dispersion modeling resources
with the capability to:
(1) Establish provisions to conduct a timely initial assessment with the worst-case
source term from the EAL using current meteorological conditions or, if
information is available, the actual source term, based on known incident
conditions from observations and indicators using current meteorological
conditions for on-site and off-site consequences.
(2) Indicate the distance at which PAC is exceeded to aid in protective action
decision-making for workers and first responders and to establish the basis for
initial field monitoring activities.
(3) Conduct continuous ongoing assessment for the duration of the emergency as
additional information becomes available.
Section 31
(4) Maintain field monitoring capabilities to perform field monitoring activities to
confirm the plume boundaries. Ensure implementing agreements, as appropriate,
are in place with state, local, and tribal organizations expected to perform off-site
field monitoring in support of the consequence assessment.
10. EMERGENCY FACILITIES, EQUIPMENT, AND SYSTEMS. DOE laboratories, plants,
and sites are responsible for the provision of adequate emergency facilities, equipment, and
systems to support emergency response operations and the ERO commensurate with the
associated threats and hazards identified in the All-Hazards Planning Basis. Equipment
must be maintained and tested, as applicable, to ensure equipment functions as designed for
emergency response and implementation of protective actions based upon the All-Hazards
Planning Basis.
a. Personal Protective Equipment (PPE).
(1) DOE laboratories, plants, and sites must provide appropriate PPE to assigned
emergency responders commensurate to the hazards.
(2) DOE laboratories, plants, and sites must identify, in the emergency management
plan, or other documentation, caches of specialty equipment that may be required
if an incident occurs. These caches must be inventoried, at a minimum, annually.
b. Communications Equipment.
(1) DOE laboratories, plants, and sites must have an emergency notification system
capable of providing immediate notification of protective actions to affected
employees, as required in Attachment 3, Section 11.a.(2) of this Order.
Attachment 3 – Federal Employees and Contractors DOE O 151.1E
Page 3-24 4-1-2024
(2) Communications equipment and the notifications capability must be tested at least
annually.
c. Hazardous Materials Program laboratories, plants, and sites must incorporate the
following additional requirements.
(1) Designate and maintain an EOC capability, which can be physical, virtual, or
hybrid model. The EOC must:
(a) Be accessible on a 24-hour basis to on-site and off-site ERO members.
(b) Be equipped with systems and equipment to support ERO activities. This
includes information management, mapping, and secure and non-secure
communications.
(c) Ensure that the air filtration system removes the types of plausible
contaminates if occupants rely on a filtration system for habitability. High
Efficiency Particulate Air (HEPA) filters used for protection from airborne
contaminants must be certified at an approved HEPA filter test facility.
(2) Maintain an Alternate EOC (AEOC) capability that can perform the required
functions of the primary EOC if the primary EOC is not available.
(a) Any physical AEOC must be located so both it and the primary EOC are not
impacted by the same incident as determined by the results of the EPHAs.
(b) Ensure that the air filtration system removes the types of plausible
contaminates if occupants rely on a filtration system for habitability. HEPA
filters used for protection from airborne contaminants must be certified at an
approved HEPA filter test facility.
(3) Joint Information Center (JIC).
(a) Have provisions in place to establish a JIC to serve as a working location,
where multiple jurisdictions gather, process, and disseminate public
information during an emergency. The JIC can be a physical, virtual, or
hybrid model.
(b) Maintain equipment and systems to support JIC activities to include public
inquiry, media inquiry, media monitoring, media support services, and
management and administrative activities.
Section 32
(c) Identify a location for the JIC outside the EPZ.
(4) Communications Equipment.
DOE O 151.1E Attachment 3 – Federal Employees and Contractors
4-1-2024 Page 3-25
(a) Maintain EOC primary and backup communications capabilities adequate to
support incidents identified in the EPHAs.
(b) Maintain equipment capable of transmitting information in a secured fashion
if classified information or CUI is generated, handled, or stored by the
laboratories, plants, and sites.
(5) Meteorological Monitoring Equipment.
(a) Maintain a meteorological capability to provide real-time on-site/local
meteorological data and maintain access to meteorological expertise for site
consequence assessments.
(b) The on-site data collection, processing, and availability must meet current
guidance and standards and be appropriate for the level of incident possible
per current directives and standards (DOE O 458.1, Radiation Protection of
the Public and the Environment and DOE-HDBK-1216-2015, Environmental
Radiological Effluent Monitoring and Environmental Surveillance, current
versions).
(c) Maintain or have access to a meteorological modeling capability or access to
reliable real-time off-site meteorological data to conduct proper off-site
consequence assessment activities if the lab, plant, or site has EPHA results
that indicate the potential for a GE.
d. Laboratories, plants, and sites with Defense Nuclear Facilities must incorporate the
additional following requirements:
(1) Identify on-site emergency response actions at affected facilities with the
following requirements:
(a) Develop compensatory measures for on-site emergency response facilities
that are not survivable and habitable.
(b) Maintain and test safety functions and features to ensure they function as
designed.
(c) Develop walkaway strategies for equipment and facilities during
emergencies.
(d) Ensure a transition of responsibilities and required actions between normal
work activities, incident activities, and recovery operations.
(2) The following criteria must be in the design, construction, and maintenance of
new EOCs established after the publication date of DOE O 151.1D,
Comprehensive Emergency Management System, dated 8-11-2016:
(a) If the EOC is located within the EPZ, it must be able to remain habitable
Attachment 3 – Federal Employees and Contractors DOE O 151.1E
Page 3-26 4-1-2024
during radiological and hazardous materials releases.
(b) Designate the EOC as an essential facility in accordance with the
International Building Code or state/regional/local equivalent building code
(if approved by the FEM/FOM per DOE O 420.1 Facility Safety, current
version) and meet the design requirements of the applicable building code.
(c) The EOC must be capable of sustaining emergency operations for a
minimum of 72 hours during severe incidents when site or commercial
infrastructure may be disrupted.
(d) Any new EOC design and construction project that has received Critical
Decision 2 (CD-2) (Performance Baseline) approval per DOE O 413.3B
Administrative Change 1, Program and Project Management for the
Acquisition of Capital Assets, as of the date of issuance of DOE Order
151.1D, Comprehensive Emergency Management System, dated 8-11-2016,
is exempt from the requirements of Attachment 3, 11.d.(2), of this Order.
11. NOTIFICATIONS AND COMMUNICATIONS. Initial notifications must be made
Section 33
promptly, accurately, and effectively to all appropriate stakeholders. Follow-up
notifications must be made when conditions change and when the OE is terminated. DOE
laboratories, plants, and sites must accomplish the following:
a. Notifications.
(1) Provide prompt emergency notifications to emergency response personnel and
response organizations.
(2) Provide immediate notification and protective actions to affected employees no
later than 10 minutes after the protective actions have been identified in
accordance with the emergency management plan and related procedures.
(3) Notify the FEM/FOM, Headquarters EOC, and state, local, and tribal
organizations within 30 minutes of categorization of an OE or the activation of
the ERO for an incident not categorized as an OE, to include incidents defined in
the Headquarters EOC issued CIRs.
(4) Hazardous Materials Programs must notify the FEM/FOM, Headquarters EOC,
and state, local, and tribal organizations of the OE classification within 15
minutes of categorization.
(5) Emergency notification to the Headquarters EOC must consist of a human phone
call providing as much information as is known at the time. The same
information must be provided by e-mail either immediately prior to or following
the phone call. Information for initial notification includes, as available, the
following:
DOE O 151.1E Attachment 3 – Federal Employees and Contractors
4-1-2024 Page 3-27
(a) Description of the emergency.
(b) Date and time emergency was discovered or terminated.
(c) Current weather conditions (wind speed, direction, precipitation) at the
incident location.
(d) Other notifications made.
(e) Status of EOC activation (full, partial, standing up, not activated).
(f) Assessment of current incident conditions (improving, stable, degrading,
undetermined).
(g) Damage and casualties.
(h) Protective actions implemented.
(i) Potential and actual impacts.
(j) Agencies involved.
(k) Level of public/media attention.
(l) Contact information for the DOE on-scene point of contact.
(6) Incidents involving an OST OE or OST transportation incident onsite or offsite
must incorporate the following additional notification requirements:
(a) Location of the incident, including coordinates.
(b) Security and condition of the cargo.
(c) Whether or not a national security area has been declared.
(d) Effect on other ongoing OST missions.
b. Communications.
(1) Provide communication methods among on-scene responders, emergency
managers, and response facilities.
(2) Provide updates to the Headquarters EOC based upon the emergency conditions
and/or as directed by Headquarters.
(3) Establish provisions to provide updates to workers during an emergency.
Attachment 3 – Federal Employees and Contractors DOE O 151.1E
Page 3-28 4-1-2024
(4) Initiate, at least annually, communications checks on classified and unclassified
communication systems used for initial notification of the Headquarters EOC.
(5) Ensure communication among response facilities, field response elements, and
off-site command centers by providing a COP of the emergency response and
shared situational awareness among all teams. This must be accomplished by
enabling access to unclassified emergency response information, such as
notification forms, emergency status updates, plume projections, significant
activities data, and field monitoring data.
12. EMERGENCY PUBLIC INFORMATION. DOE laboratories, plants, and sites must
Section 34
provide accurate, candid, and timely information to workers, the media, and the public
during an emergency. DOE laboratories, plants, and sites must:
a. Establish and maintain an emergency public information capability consistent with the
All-Hazards Planning Basis.
b. Document the emergency public information capability in an emergency public
information plan, emergency management plan, or comparable plan. This plan must
include:
(1) Identification of personnel, resources, and facilities necessary to support
emergency public information activities.
(2) Identification of a public information officer who will interact with the media
during emergencies.
(3) Provisions for coordination of information to be released during an emergency.
(4) Identification of public information media to be used and monitored, such as web
sites, social media, news releases, and news briefings.
(5) Identification of a location for the necessary briefings and news conferences
regarding the emergency.
(6) Identification of training and exercises for personnel who will interact with the
media.
(7) Identification of provisions for coordination of public information activities with
off-site response agencies, state, local and tribal governments, and federal
emergency response plans, as appropriate.
(8) Information must be reviewed in accordance with DOE O 471.7, Controlled
Unclassified Information, current version, DOE O 471.1, Identification and
Protection of Unclassified Controlled Nuclear Information, current version and
DOE O 475.2, Identifying Classified Information, current version and reviewed
DOE O 151.1E Attachment 3 – Federal Employees and Contractors
4-1-2024 Page 3-29
by an appropriate classification official, Unclassified Controlled Nuclear
Information (UCNI) Reviewing Official, or an appropriate person for Controlled
Unclassified Information (CUI) and the Emergency Manager for classified
information, UCNI, and CUI prior to release.
(9) Provisions for initial news releases or public statements to be approved by the
Field Element official responsible for emergency public information review and
dissemination.
(10) Provisions to coordinate with the Headquarters EOC and DOE’s Office of Public
Affairs or NNSA’s Office of Communications on information released after the
initial release. This includes information released through news releases and
social media. DOE Office of Public Affairs or NNSA’s Office of
Communications may delegate this to the local level.
c. Hazardous Materials Program laboratories, plants, and sites must also maintain staff
with technical expertise related to the emergency to support the public information
activities.
13. TERMINATION AND RECOVERY. DOE laboratories, plants, and sites must accomplish
the following for termination and recovery:
a. Termination.
(1) Establish a predetermined set of criteria for terminating an OE. Emergency
termination criteria must consider:
(a) Emergency response activities have stopped.
(b) The situation has been stabilized.
(c) Potential threats to workers, the public, the environment, and national
security have been characterized.
(d) Conditions no longer meet established emergency categorization criteria.
(e) It appears unlikely that conditions will deteriorate.
(2) The decision to terminate an OE classified as an Alert, SAE, or GE can only be
made when capabilities and resources of the ERO are no longer needed to manage
the incident.
Section 35
(3) The decision to terminate an OE must be a formal announcement or
acknowledgement that the situation is stabilized, and that the response activity is
ending or has been substantially scaled back.
Attachment 3 – Federal Employees and Contractors DOE O 151.1E
Page 3-30 4-1-2024
(4) Coordinate the decision to terminate the emergency with the responding
organizations and the Field Element or appropriate Federal Manager, as
applicable.
(5) Prior to termination, identify and document in a draft recovery plan the recovery
organization that will activate and address the actions necessary to restore the
laboratory, plant, or site to normal operations.
(6) Notify the Headquarters EOC and other organizations previously notified when
the emergency is terminated.
b. Recovery.
(1) The recovery organization must include an accident investigation, as needed, and
ensure the accident investigation is conducted in accordance with DOE O 225.1,
Accident Investigations, current version.
(2) Hazardous Materials Program laboratories, plants, and sites have the following
additional requirements:
(a) Establish a means for estimating exposure to hazardous materials and for
protecting workers and the public from exposure during reentry and recovery
activities.
(b) Recovery from a terminated OE must include communication and
coordination with federal, state, local, and tribal agencies.
(c) Recovery procedures must include the following:
1 Dissemination of information to federal, state, local, and tribal
agencies regarding the emergency and possible relaxation of public
protective actions.
2 Planning for decontamination actions.
3 Development of reporting requirements.
4 Establishment of criteria for resumption of normal operations.
c. Post Incident Reporting.
(1) Complete an After-Action Report (AAR) evaluating the ERO when activated for
a real-world incident categorized as an OE, to identify lessons learned and
corrective actions.
(2) For an OE, submit the AAR to the FEM/FOM for further dissemination to the
DOE O 151.1E Attachment 3 – Federal Employees and Contractors
4-1-2024 Page 3-31
Associate Administrator for Emergency Management and assigned Program
Secretarial Officer. This report may be done in conjunction with the Final
Occurrence Report in accordance with DOE O 232.2, Occurrence Reporting and
Processing of Operations Information, current version.
14. READINESS ASSURANCE. DOE laboratories, plants, and sites must participate in a
formal Readiness Assurance Program that establishes a framework and associated
mechanisms to validate their emergency plans, procedures, and resources adequately
address the threats and hazards identified in the All-Hazards Planning Basis and ensures
timely improvements are made when identified. The Readiness Assurance Program
consists of evaluations, issues management, and the Emergency Readiness Assurance Plan
(ERAP).
a. Evaluations. Evaluations include assessments, exercises, and performance
indicators. All program elements must be evaluated and validated annually
through assessments, exercises, or reviews of real-world incidents. The scope
of each program element evaluated does not have to include all program
element requirements each year. The determination must be based on the
complexity of the program and ensure all program element requirements are
fully evaluated and validated over a five-year period.
(1) Assessments. DOE laboratories, plants, and sites must:
Section 36
(a) Conduct annual self-assessments to ensure that emergency plans,
procedures, emergency response activities, and resources are adequate and
sufficiently maintained for use in a real-world incident.
(b) Support DOE during the conduct of an external assessment.
(2) Exercises. Laboratories, plants, and sites must have an exercise program that is
consistent with the fundamental principles of the Department of Homeland
Security Exercise and Evaluation Program (HSEEP). The exercise program must
include:
(a) Conduct of an annual exercise (discussion-based or operation-based) to test
and validate emergency plans and procedures. At a minimum, for non-
hazardous material laboratories, plants, and sites, every three years the
annual exercise must be an operations-based exercise. For Hazardous
Materials Program laboratories, plants, and sites, every year the annual
exercise must be an operation-based exercise.
(b) Rotation of the annual exercise scenarios among the threats and hazards
identified in the All-Hazards Planning Basis.
(c) Submission of the exercise schedule annually to the FEM/FOM in
accordance with laboratory, plant, or site procedures.
Attachment 3 – Federal Employees and Contractors DOE O 151.1E
Page 3-32 4-1-2024
(d) Formal invitation to primary off-site response agencies to participate in the
annual exercise.
(e) Formal invitation of laboratory, plant, or site subject matter experts as it
relates to the scenario, and security program personnel to actively participate
in the annual exercise.
(f) Exercise plan preparation in accordance with laboratory, plant, or site
procedures. At a minimum, an exercise plan must be prepared for the annual
exercise.
(g) Submission of the annual exercise plan to the FEM/FOM, no later than 30
calendar days before the annual exercises, for approval in accordance with
laboratory, plant, or site procedures.
(h) Development of AARs that include issues, lessons learned, and overall
evaluation results. Complete AARs within 45 calendar days of the exercise.
AARs for the annual exercise must be submitted to the FEM/FOM in
accordance with laboratory, plant, or site procedures.
(i) Conduct of any exercise with a security-based nexus must be done in
accordance with DOE O 470.3, Design Basis Threat, current version.
(j) Allowance for a real-world incident to replace the annual exercise with the
approval of the FEM/FOM, if an AAR is developed, issued, and documents
the equivalent exercise objectives that were completed during the real-world
incident.
(k) Hazardous Materials Program laboratories, plants, and sites must include the
following additional requirements in their exercise program:
1 Establish and maintain a laboratory, plant, or site-level exercise
program that validates its emergency response capability to the hazards
identified in an EPHA.
2 Develop a rolling five-year exercise schedule. The schedule must
include:
a. A method for determining the appropriate number and types of
exercises and rotation of exercise scenarios among all hazardous
material facilities.
b. Development and conduct a full-scale exercise (FSE), as defined in
HSEEP, for ERO activities involving hazardous materials releases.
The frequency is based on the number of EPHAs as follows:
DOE O 151.1E Attachment 3 – Federal Employees and Contractors
4-1-2024 Page 3-33
i. DOE laboratories, plants, and sites with one or two EPHAs
must conduct an FSE every three years.
Section 37
ii. DOE laboratories, plants, and sites with three or more
EPHAs must conduct an FSE annually.
c. Development and conduct, for ERO activities involving hazardous
material releases based on the EPHAs, operation and discussion-
based exercises that supplement the annual exercise.
d. Demonstration of protective actions during the annual exercise.
e. One severe incident scenario every five years that involves the
release of hazardous materials at more than one facility at a
laboratory, plant, or site and disrupts site infrastructure, such as
power, telecommunications, roadways, or the significant delay of
mutual aid.
f. OST Recipient Sites must conduct an exercise (discussion or
operations-based) with OST once every five years. The exercise
must assess and validate procedures related to the laboratory, plant,
or site’s ability to effectively respond to on-site OST OE or OST
transportation emergency. The exercise scenario will be developed,
in coordination with OST, for a typical shipment to the laboratory,
plant, or site.
g. Facilities with radiological materials must invite one or more of the
Department’s Radiological/Nuclear Assets to participate in an
exercise every three years.
h. Off-site response agencies must be invited to participate in an FSE
at least once every three years.
i. Scenario development that is progressively challenging and based
on identified threats and hazards in the All-Hazards Planning Basis
that involve high consequences, multiple response elements, and as
applicable, off-site impacts.
j. Test of design control and/or mitigation features in multiple
facilities
k. Demonstration of ERO capability.
l. Laboratories, plants, or sites with an ERO that covers a single
location/building must annually evaluate emergency response
capability and proficiency at their location/building by initiating a
Attachment 3 – Federal Employees and Contractors DOE O 151.1E
Page 3-34 4-1-2024
response to simulated, realistic emergency situations/conditions in
a manner that, as nearly as possible, replicates an integrated
emergency response to a real-world incident.
m. Integration with federal, state, local, and tribal agencies.
(l) Laboratories, plants, and sites with Defense Nuclear Facilities must
incorporate the following additional requirements in their five-year exercise
plan:
1 Conduct and evaluate an annual FSE, regardless of the number of
EPHAs.
2 Conduct drills, using a graded approach, involving the Operations staff
and ERO. Consider the following in development of drills:
a. Elements of the ERO staff for OE.
b. Drill scenarios that are representative of the hazards/threats
identified in the All-Hazards Planning Basis.
c. Integration of the ERO with conduct of operations drills as the
initiating activity.
d. Evaluations of drill design and content, to include participants, for
continuous improvement regardless of the scope or mechanism.
e. Rotation of shifts involved in the drill, unannounced drills, and
drills conducted during low staffing levels.
(3) Performance Indicators. DOE laboratories, plants, and sites must participate in a
program of performance indicators.
b. Issues Management. An issues management system is required by laboratories,
plants, and sites per DOE O 226.1, Implementation of Energy Oversight Policy,
current version, and the Contractor Assurance System. Issues identified from
emergency management assessments (to include self-assessments and
independent oversight assessments), exercises, real-world incidents and
equipment maintenance and testing must be included in the issues management
system. The system must include a capability to categorize the significance of
issues based on risk and priority. In addition, the following is required for
corrective actions and lessons learned:
Section 38
(1) Corrective Actions.
(a) Corrective action plans must be developed for issues identified from
DOE O 151.1E Attachment 3 – Federal Employees and Contractors
4-1-2024 Page 3-35
independent oversight assessments and must be submitted to the FEM/FOM
or Program Secretarial Officer for approval.
(b) Corrective action plans must be developed, within 45 calendar days of
reports, evaluations, and AARs, for issues identified during a self-
assessment, exercise, or real-world incident and must be submitted to the
FEM/FOM upon request.
(c) Corrective action plans must be developed for issues of higher significance
identified during maintenance and testing and submitted to the FEM/FOM
upon request.
(d) Use a formal tracking system to track completion of corrective actions. This
tracking system may be part of a laboratory, plant, or site action tracking
system.
(e) Hazardous Materials Program laboratories, plants, and sites must incorporate
the following additional requirements:
1 Identify compensatory measures for issues of higher significance to
reduce risk until causal analysis is performed and corrective actions are
identified and implemented.
2 Conduct a causal analysis to determine root cause and corrective
actions for issues identified as resulting from noncompliance for life
safety.
3 Evaluate, by an independent reviewer, the effectiveness of corrective
actions for issues of higher significance, through verification that the
corrective action has been put in place and validation that the corrective
action has been effective in resolving the original issue.
4 Submit corrective action plans, for issues of higher significance, to the
FEM/FOM for approval.
(2) Lessons Learned
(a) Use a system for incorporating and tracking lessons learned from training,
exercises, actual responses, and the laboratory, plant, or site lessons learned
program.
(b) Review DOE Corporate Lessons Learned Database, under DOE O 210.2,
DOE Corporate Operating Experience Program, current version, and for
emergency management lessons learned, review the Office of Enterprise
Assessments lessons learned report.
Attachment 3 – Federal Employees and Contractors DOE O 151.1E
Page 3-36 4-1-2024
c. Emergency Readiness Assurance Plan (ERAP).
(1) DOE laboratories, plants, and sites must complete and submit an ERAP to the
FEM/FOM for approval by October 15 each year, using the format and content
guidelines provided by the Associate Administrator for Emergency Management,
in coordination with the Program Secretarial Officers. The ERAP must:
(a) Highlight program status, including significant changes in the emergency
management program.
(b) Summarize the hazards/threats and potential impacts identified in the All-
Hazards Planning Basis.
(c) Document assessment, exercise, and real-world incidents and the status of
corrective actions developed to address issues of higher significance.
(d) Identify the goals for the fiscal year that ended and the degree to which those
goals were accomplished.
(e) Identify the goals for the next fiscal year.
(f) Identify emergency management program gaps and needs.
(2) The FEM/FOM must submit an ERAP covering the laboratories, plants, and sites
under the FEM’s/FOM’s supervision to the Program Secretarial Officers and
Associate Administrator for Emergency Management, by November 30 each year.
DOE O 151.1E Attachment 4 – References – Federal Employees and Contractors
4-1-2024 Page 4-1
ATTACHMENT 4
REFERENCES
Section 39
a. Public Law (P.L) 73-703, Atomic Energy Act of 1954, as amended.
b. P.L. 93-288, Robert T. Stafford Disaster Relief and Emergency Assistance Act,
as amended through P.L. 118–44, Enacted March 18, 2024.
c. P.L. 106-65, National Defense Authorization Act for Fiscal Year 2000, dated
10-05-1999.
d. P.L. 114-94, Fixing America’s Surface Transport Act, dated 12-04-2015.
e. P.L. 115-325, Federal Power Act, enacted 12-18-2018.
f. Title 5 United States Code (U.S.C.) § 552a, Records Maintained on Individuals.
g. Title 5 U.S.C. § 552, Freedom of Information Act.
h. Title 42 U.S.C. § 7158, Naval Reactor and Military Application Programs.
i. Title 50 U.S.C. § 2406, Deputy Administrator for Naval Reactors.
j. Title 50 U.S.C. § 2511, Naval Nuclear Propulsion Program.
k. Title 50 U.S.C. § 4501 et seq., Defense Production Act of 1950.
l. Title 7 Code of Federal Regulations (CFR) Part 331, Possession, Use, and
Transfer of Select Agents and Toxins.
m. Title 9 CFR Part 121, Possession, Use, and Transfer of Select Agents and
Toxins.
n. Title 10 CFR Part 71, Packing and Transport of Radioactive Materials.
o. Title 10 CFR Part 205.350-353, Report of Major Electric Utility System
Emergencies.
p. Title 10 CFR Part 830, Nuclear Safety Management.
q. Title 29 CFR Part 1910.1450, Occupational Exposure to Hazardous Chemicals in
Laboratories.
r. Title 40 CFR Part 68, Chemical Accident Prevention.
s. Title 40 CFR Part 300, National Oil and Hazardous Substances Pollution
Attachment 4 – References – Federal Employees and Contractors DOE O 151.1E
Page 4-2 4-1-2024
Contingency Plan.
t. Title 40 CFR Part 355, Emergency Planning and Notification.
u. Title 41 CFR Part 102-74.360, What are the Specific Accident and Fire
Prevention Responsibilities of Occupant Agencies?
v. Title 42 CFR Part 73, Select Agents and Toxins.
w. Title 45 CFR Part 160, General Administrative Requirements.
x. Title 45 CFR Part 164, Subparts A and E, Security and Privacy.
y. Executive Order 12344, Naval Nuclear Propulsion Program.
z. Executive Order 13636, Improving Critical Infrastructure Cybersecurity.
aa. Presidential Policy Directive (PPD) 8, National Preparedness, dated 03-30-
2011.
bb. PPD 21, Critical Infrastructure Security and Resilience, dated 02-12-2013.
cc. PPD 41, United States Cyber Incident Coordination, dated 07-26-2016.
dd. PPD 44, Enhancing Domestic Incident Response, dated 11-07-2016.
ee. Homeland Security Presidential Directive (HSPD) 5, Management of Domestic
Incidents, dated 02-28-2003.
ff. Homeland Security Exercise and Evaluation Program (HSEEP), Department of
Homeland Security, dated 10-2020.
gg. National Cyber Incident Response Plan, Department of Homeland Security,
dated 12-16-2016.
hh. National Incident Management System, Third Edition, Department of Homeland
Security, dated 11-17-2017.
ii. National Response Framework, Fourth Edition, Department of Homeland
Security, dated 10-28-2019.
jj. DOE O 153.1, Departmental Nuclear Emergency Support Team Capabilities,
current version.
kk. DOE O 210.2, DOE Corporate Operating Experience Program, current
DOE O 151.1E Attachment 4 – References – Federal Employees and Contractors
4-1-2024 Page 4-3
version.
ll. DOE O 225.1, Accident Investigations, current version.
mm. DOE O 226.1, Implementation of Department of Energy Oversight Policy,
current version.
nn. DOE O 232.2, Occurrence Reporting and Processing of Operations
Information, current version.
oo. DOE O 243.1, Records Management Program, current version.
Section 40
pp. DOE O 251.1, Department Directives Program, current version.
qq. DOE O 413.3B Program and Project Management for the Acquisition of
Capital Assets, current version.
rr. DOE O 420.1, Facility Safety, current version.
ss. DOE O 420.2, Safety of Accelerator Facilities, current version.
tt. DOE O 458.1, Radiation Protection of the Public and the Environment, current
version.
uu. DOE O 460.1, Hazardous Materials Packaging and Transportation Safety,
current version.
vv. DOE O 470.3, Design Basis Threat (DBT), current version.
ww. DOE O 470.4, Safeguards and Security Program, current version.
xx. DOE O 471.1, Identification and Protection of Unclassified Controlled Nuclear
Information, current version.
yy. DOE O 471.7, Controlled Unclassified Information, current version.
zz. DOE O 475.2, Identifying Classified Information, current version.
aaa. DOE-HDBK-1216-2015, Environmental Radiological Effluent Monitoring and
Environmental Surveillance, current version.
bbb. DOE-STD-1027-2018, Hazard Categorization of DOE Nuclear Facilities,
current version.
Attachment 4 – References – Federal Employees and Contractors DOE O 151.1E
Page 4-4 4-1-2024
ccc. NUREG-0396/EPA 520/1-78-016, Planning Basis for the Development of State
and Local Government Radiological Emergency Response Plans in Support of
Light Water Nuclear Power Plants, dated December-1978.
DOE O 151.1E Attachment 5 – Definitions – Federal Employees and Contractors
4-1-2024 Page 5-1
ATTACHMENT 5
DEFINITIONS
This Attachment provides definitions for terms used in DOE O 151.1E, Comprehensive
Emergency Management System, and is associated where Contractor Requirements Document
(Attachment 1 to DOE O 151.1E) is inserted.
1. Accountability. For the purposes of this document, the process for communicating,
assessing, and confirming the status of life and safety of all on-site personnel affected
by an incident.
2. Active Threat. A dynamic, quickly evolving situation involving an individual (or
individuals) using deadly physical force.
3. After-Action Report (AAR). A document intended to capture observations, issues,
and lessons learned from an exercise or real-world incident.
4. Alternate Emergency Operations Center (AEOC). A physical, virtual, or hybrid
location for use when the primary EOC is unable to support a response effort.
5. Annual (such as “annual exercise”). Occurring or recurring once within a specified,
one year period, as defined by the laboratory, plant, or site.
6. Assessment. An evaluation, performed to determine and document whether items,
processes, systems, or services meet specified requirements and perform effectively.
7. Categorization. The DOE process for determining whether an incident or condition is
an OE.
8. Classification. The process of assessing potential release of hazardous materials in an
Operational Emergencies to determine if they fall into one of the three emergency
classes (Alert, Site Area Emergency (SAE), or General Emergency (GE)).
9. Compliance. Conforming to the requirements of DOE O 151.1E, Comprehensive
Emergency Management System (and referenced federal laws and regulations).
10. Common Operating Picture (COP). A standard overview of an incident, thereby
providing incident information that enables the Incident Commander/Unified Command
and any supporting agencies and organizations to make effective, consistent, and timely
decisions. Compiling data from multiple sources and disseminating the collaborative
information ensures that all responding entities have the same understanding and
awareness of incident status and information when conducting operations.
Section 41
11. Critical Information Requirements (CIR). A comprehensive list of elements of
information that DOE and NNSA leaders have identified as requiring immediate
notification to facilitate timely decision making.
Attachment 5 – Definitions – Federal Employees and Contractors DOE O 151.1E
Page 5-2 4-1-2024
12. Defense Nuclear Facilities.
a. A production facility or utilization facility (as defined in 42 United States Code
(U.S.C.) §2014 [§ 11 of the Atomic Energy Act]) that is under the control or
jurisdiction of the Secretary of Energy and that is operated for national security
purposes, but does not include:
(1) any facility or activity covered by Executive Order No. 12344, dated February 1,
1982 [42 U.S.C. § 7158 note], pertaining to the Naval nuclear propulsion
program;
(2) any facility or activity involved with the transportation of nuclear explosives or
nuclear material;
(3) any facility that does not conduct atomic energy defense activities; or
(4) any facility owned by the United States Enrichment Corporation.
b. A nuclear waste storage facility under the control or jurisdiction of the Secretary of
Energy, but does not include a facility developed pursuant to the Nuclear Waste Policy
Act of 1982 (42 U.S.C. 10101 et seq.) and licensed by the Nuclear Regulatory
Commission
c. A production facility or utilization facility (as defined in section 318 of the Atomic
Energy Act) that is under the control or jurisdiction of the Secretary of Energy and that
is operated for national security purposes; or a nuclear waste storage facility under the
control or jurisdiction of the Secretary of Energy, but does not include a facility
developed pursuant to the Nuclear Waste Policy Act of 1982 (42 U.S.C. 10101 et seq.)
and licensed by the NRC.
13. Discovery. The point at which laboratory, plant, or site workers or visitors identify or
become aware of an incident or condition.
14. Discussion-based Exercise. These types of exercises typically highlight existing plans,
policies, mutual aid agreements, and procedures, and can be used as tools to familiarize
agencies and personnel with current or expected capabilities. Discussion-based
exercises include seminars, workshops, tabletops, and games.
15. Drill. An operations-based exercise often employed to validate a single operation or
function.
16. Emergency. Any incident, whether natural, technological, or human-caused, that
necessitates responsive action to protect life, property, critical infrastructure, or
environment.
17. Emergency Action Level (EAL). A predetermined, laboratory, plant, or site-specific,
DOE O 151.1E Attachment 5 – Definitions – Federal Employees and Contractors
4-1-2024 Page 5-3
observable threshold for an initiating condition that, when met or exceeded, places the
laboratory, plant, or site in a given emergency categorization with the potential for
further classification.
18. Emergency and Incident Management Council (EIMC). The primary DOE
strategic-level leadership coordination, synchronization, and oversight mechanism for
senior Department leadership during an emergency of such significance to warrant
Council activation, to include those incidents that might require the coordinated efforts
of several sites or programs.
19. Emergency Management Advisory Committee. Provides the Department of Energy
(DOE) and National Nuclear Security Administration (NNSA) a forum for federal
headquarters, field, and site office emergency managers to align and prioritize
emergency management program administration and implementation, and to resolve
emergency management issues effectively and timely.
Section 42
20. Emergency Notification System (ENS). A type of Emergency Communication
System that facilitates the real-time, one-way dissemination or broadcast of messages to
one or many groups of people at a laboratory, plant, or site.
21. Emergency Operations Center (EOC). A designated location where the coordination
of information and resources and advanced planning, to support the incident (on-scene
operations) activities, normally takes place. The EOC may be a physical, virtual, or
hybrid model.
22. Emergency Operating Records. Records essential to the continued functioning or
reconstitution of an organization during and after an incident.
23. Emergency Planning Hazards Assessment (EPHA). A quantitative analysis
identifying hazards and the potential consequences from unplanned releases of (or loss
of control over) hazardous materials, using accepted assessment techniques.
24. Emergency Planning Zone (EPZ). A zone identified to facilitate a predetermined
strategy for protective actions during a defined emergency.
25. Emergency Readiness Assurance Plan (ERAP). A documented annual report
detailing the development, implementation, and maintenance status of an Emergency
Management Program. The ERAP is also a planning tool to identify and develop
needed resources and improvements.
26. Emergency Response Organization (ERO). A structured organization with overall
identified responsibilities for initial and ongoing emergency response and mitigation.
27. Emergency Response Officer Cadre (EROC). The Office of Secure Transportation
personnel with specialized skillsets activated to serve in response capacities during OST
Attachment 5 – Definitions – Federal Employees and Contractors DOE O 151.1E
Page 5-4 4-1-2024
emergencies.
28. Energy Emergency. An emergency resulting from an energy supply crisis, economic
impacts, widespread energy distribution interruption, or energy infrastructure damage.
It includes all actions taken to ensure the balance generation and load to ensure
reliability of the electric interconnection.
29. Evacuation. The directed relocation of a population out of a high-risk area prior to or
during an emergency. The evacuation of a laboratory, plant, or site may be necessary
when a hazard, be it natural, technological, or human-caused, threatens the safety of
those within the laboratory, plant, or site.
30. Exercise. An activity delivered through discussion or action to develop, assess, or
validate capabilities to achieve planned objectives. Exercises, under the Homeland
Security Exercise and Evaluation Program (HSEEP) can be discussion-based (examples
include seminars, workshops, tabletop exercise, and games), or operations-based (drills,
functional exercises, or full-scale exercises).
31. Full-scale Exercise (FSE). An operations-based exercise that is typically those most
complex and resource-intensive of the exercise types and often involves multiple
agencies, on-site and off-site jurisdictions/organizations, and real-time movement of
resources.
32. Functional Exercise. An operations-based exercise designed to test and evaluate
capabilities and functions in a realistic, real-time environment; however, movement of
resources is usually simulated.
33. Globally Harmonized System (GHS). A framework that standardizes the
classification and labeling of chemicals worldwide. It is one of two hazardous material
screening methods available to laboratories, plants, and sites.
Section 43
34. Graded Approach. The processes and procedures that incorporates a risk-based
approach to assess and protect against the consequences of hazards (natural,
technological, and man-made) that may have an adverse impact on national security, the
environment, or that may pose significant danger to the health and safety of DOE
Federal and contractor employees or the public.
35. Hazardous Material. Any hazardous biological agents and toxins; any radioactive or
radiological material that emits ionizing radiation; any solid, liquid, or gaseous chemical
that is toxic, explosive, flammable, or corrosive, or could otherwise adversely affect the
health and safety of the public or the workers or harm the environment. Fuel oil and
gases are excluded in the definition of hazardous materials used in this Order.
36. Hazardous Materials Program. An emergency management program with additional
requirements in training, emergency management services, off-site response agencies,
emergency classification, protective actions, emergency facilities and
equipment/systems, emergency public information, termination and recovery and
https://chemicalsafety.com/ghs-labeling-software/
DOE O 151.1E Attachment 5 – Definitions – Federal Employees and Contractors
4-1-2024 Page 5-5
exercises.
37. Homeland Security Exercise and Evaluation Program (HSEEP). A set of guiding
principles for exercise and evaluation programs as well as a common approach to
exercise program management, design and development, conduct, evaluation, and
improvement planning.
38. Incident. An unplanned occurrence (natural, technological, or human-made) that
necessitates a response to protect life, property, critical infrastructure, or environment.
39. Incident Command System (ICS). A management system designed to enable
effective and efficient domestic incident management by integrating a combination of
facilities, equipment, personnel, procedures, and communications operating within a
common organizational structure.
40. Incident Commander. The individual responsible for all incident activities, including
the development of strategies and tactics and the ordering and the release of resources.
The Incident Commander has overall authority and responsibility for conducting
incident operations and is responsible for the management of all incident operations at
the incident site.
41. Issue. Factual statement of identified findings and deficiencies (failure to meet a
documented legal, regulatory, performance, compliance, or other applicable
requirements) in the Emergency Management Program at a laboratory, plant, or site
resulting from an exercise, self-assessment, independent assessment, testing and
maintenance, or real-world event.
42. Joint Information Center (JIC). A facility established to coordinate critical
emergency information, crisis communications, and public affairs functions. It is the
central point of contact for all news media.
43. Key Receptor Location. Public entities that require protective action
recommendations based on at-risk populations. The minimum key receptor locations
for planning purposes include, but not limited to, hospitals, emergency response
agencies, schools, and correctional facilities.
44. Laboratories, Plants, Sites. These include DOE federal owned, leased, and contractor-
operated laboratories, plants, sites, buildings/locations, secure transportation activities,
administrative offices in the field, and headquarters offices.
Section 44
45. Mass Casualty Incident. An incident in which the number of patients and the severity
of their injuries exceed the capacity of area medical systems and facilities, as identified
by the lab, plant, or site. The incident produces more patients than the responding
jurisdiction is routinely capable of handling and necessitates an uncommon level of
resource mobilization.
46. Materials of National Security Interest. A class of strategic materials used in the
Attachment 5 – Definitions – Federal Employees and Contractors DOE O 151.1E
Page 5-6 4-1-2024
development, testing, production, and maintenance of nuclear weapons and other
materials that have been designated as critical to national security.
47. Mitigation. The effort to reduce loss of life and property by lessening the impact of
incidents. Mitigation includes any activities that prevent an emergency, reduce the
chance of an emergency incident occurring, or reduce the damaging effects of
unavoidable incidents.
48. National Incident Management System (NIMS). A set of principles that provides a
systematic, proactive approach guiding government agencies at all levels,
nongovernmental organizations, and the private sector to work seamlessly to prevent,
protect against, respond to, recover from, and mitigate the effects of incidents,
regardless of cause, size, location, or complexity, to reduce the loss of life or property
and harm to the environment.
49. National Security Area (NSA). A DOE-controlled area established for radiological
incidents involving a nuclear weapon, special nuclear material, and/or classified
components that are in DOE custody.
50. Operational Emergency (non-OST). A major unplanned or abnormal incident or
condition that involves or affects DOE facilities and activities by causing or having the
potential to cause serious health, safety, or environmental impacts.
51. Operational Emergency (OST). Incidents or conditions that represent an actual or
potential release of hazardous materials from an OST shipment, or major security
incident without a hazardous materials release. Final confirmation/determination of an
OST OE will be made by the OST Operations Duty Officer in conjunction with the OST
Emergency Response Duty Officer. The declaration of an OST OE by OST has a
significant impact on DOE emergency response and coordination.
(1) An attack or other criminal act involving an OST transportation mission that
requires the deployment of OST security assets at the emergency scene.
(2) Any incident involving an OST transportation shipment containing hazardous
materials that causes the initial responders to initiate protective actions at locations
beyond the immediate area.
(3) Failures in safety or security systems that threaten the integrity of a nuclear
weapon, component, or test device.
(4) A transportation accident resulting in damage to a nuclear explosive, nuclear
explosive-like assembly, or Category I/II quantity of Special Nuclear Material
(SNM).
52. Operations-based Exercises. Operations-based exercises are characterized by actual
response, mobilization of apparatus and resources, and commitment of personnel,
usually held over an extended period. Operations-based exercises can be used to
validate plans, policies, agreements, and procedures and include drills, functional
DOE O 151.1E Attachment 5 – Definitions – Federal Employees and Contractors
4-1-2024 Page 5-7
Section 45
exercises, and full-scale exercises. They can clarify roles and responsibilities, identify
gaps in resources needed to implement plans and procedures, and improve individual
and team performance.
53. Proficiency. Demonstrated skill and competency acquired from training and
experience.
54. Protective Actions. Actions taken to minimize the consequences of emergencies and to
protect the health and safety of workers and the public.
55. Protective Action Criteria (PAC). The level of hazardous material impact that, if
observed or predicted, indicates action is needed to prevent or limit exposure of people
to the hazard. PAC are used for both radiological and non-radiological consequence
criteria in DOE facility emergency planning and response.
56. Protective Action Guides (PAG). Radiation dose guidelines that trigger protective
actions such as evacuation or staying indoors. This Order follows the Environmental
Protection Agency-developed Manual of Protective Action Guides (PAG Manual) to
help federal, state, and local authorities decide how to protect the public during
radiological emergencies.
57. Protective Action Recommendation (PAR). Predetermined actions designed to
protect the health and safety of the public that are consequence-based decisions (known
as protective actions for the lab, plant, or site). DOE laboratories, plants, or sites
recommend protective actions to the public and community for Operational
Emergencies that have the potential to cause off-site consequences.
58. Public Information Officer. A member who serves as the conduit for information to
internal and external stakeholders, including the media or other organizations seeking
information directly from the incident.
59. Radiological/Nuclear Assets (RN). The collective group of capabilities available to
provide technical and operational assistance for any type of nuclear or radiological
accident or incident. These DOE assets can be deployed to assist in an emergency at
any DOE lab, plant, or site, or anywhere domestically or internationally.
60. Readiness Assurance. Activities that ensure emergency plans, procedures, and
resources are sufficiently maintained, exercised, and evaluated, and appropriate and
timely improvements are made when identified. It serves to ensure the readiness and
effectiveness of lab, plant, site, or enterprise Emergency Management on a
programmatic and performance level while promoting a culture of continuous
improvement. It consists of evaluation (self-assessments, exercises, and performance
indicators), issues management (corrective action plan and lessons learned), and the
ERAP.
61. Recipient Site. Any DOE lab, plant, or site, Nuclear Enterprise, Department of
Defense, or Materials of National Security Interest transload location that receives or
Attachment 5 – Definitions – Federal Employees and Contractors DOE O 151.1E
Page 5-8 4-1-2024
ships material through the Office of Secure Transportation (OST).
62. Recovery. The phase of activity that follows termination of an emergency. The
recovery period begins when emergency response is declared terminated, but recovery
planning can proceed before the response is declared terminated. The recovery phase
continues until the objectives of the recovery effort have been met.
63. Reentry. The prioritized actions required to return processes and support functions to
operational stability following an incident.
Section 46
64. Response. Activities that address the short-term, direct effects of an incident and
include immediate actions to save lives, protect property, critical infrastructure, the
environment, achieve incident stabilization, and meet basic human needs.
65. Senior Response Official. Federal employee who provides leadership at the
incident scene for DOE radiological response assets.
66. Senior Federal Official (SFO). A senior management federal personnel, designated by
the Field Element Manager/Field Operations Manager, assigned to the EOC in his/her
capacity with decision-making authority and responsibilities.
67. Senior Official. An individual (senior management level fed or non-fed), designated
by the Field Element Emergency Management Team, who serves on the ERO as an
emergency manager with decision-making authority and responsibilities.
68. Severe Incident. As defined in OE-1:2013-1, Improving Department of Energy
Capabilities for Mitigating Beyond Design Basis Incidents, any incident considered a
Beyond Design Basis expected to cause major disruptions/damage to site-wide and off-
site infrastructure, as well as increased risk to on-site personnel, possibly resulting in
injuries and fatalities. These incidents could potentially isolate a facility or site from
on-site/off-site response assistance and infrastructure support.
69. Special Nuclear Material (SNM). As defined in 10 CFR Part 810, Assistance to
Foreign Atomic Energy Activities, Plutonium, Uranium-233, or Uranium enriched
above 0.711 percent by weight in the isotope Uranium-235.
70. Termination. The declared conclusion of emergency response activities signaling the
onset of the Recovery phase.
71. Total Effective Dose. Sum of the effective dose (for external exposures) and the
committed effective dose.
72. Transportation Emergency (OST). Any accident involving an OST transportation
shipment or convoy, in mission status, that cannot be categorized as an OST OE as
outlined in DOE O 151.1E but may require response beyond normal operations and
local response asset capabilities. No protective action recommendations for nuclear
cargo are issued, but due to the duration, location and support needed, implementation
DOE O 151.1E Attachment 5 – Definitions – Federal Employees and Contractors
4-1-2024 Page 5-9
of NIMS/ICS procedures or other response actions may be required to mitigate or
resolve the emergency.
73. Visitor. An on-site individual who is not an employee, contractor, or subcontractor
of the lab, plant, or site.
74. Walk-Away. A strategy employed during an emergency as an alternative to a
shutdown, whereby a facility is placed in a safe condition requiring no further on-scene
operator action, allowing operations personnel to safely leave the facility until a planned
reentry can be made.
75. Worker. Federal, contractor, or subcontractor employee or visitor performing
activities at a DOE laboratory, plant, or site.
Section 47
1. PURPOSE. To provide the Department of Energy (DOE), including the National Nuclear Security Administration (NNSA), (herein referred to as DOE or Department) policy for the development, management, and administration of the DOE Emergency Management...
2. CANCELLATION. DOE O 151.1D, Comprehensive Emergency Management System, dated 10-04-2019. Cancellation of a directive does not, by itself, modify or otherwise affect any contractual or regulatory obligation to comply with the directive. Contracto...
3. APPLICABILITY.
4. REQUIREMENTS.
5. RESPONSIBILITIES.
6. INVOKED STANDARDS. There are no invoked standards.
7. ACRONYMS AND ABBREVIATIONS. See Attachment 2.
8. REFERENCES. See Attachment 4.
9. DEFINITIONS. See Attachment 5.
10. CONTACT. For assistance regarding this Order, contact the Associate Administrator for Emergency Management at 202-586-8100.
APPENDIX A POWER MARKETING ADMINISTRATION (PMA)
ATTACHMENT 1 CONTRACTOR REQUIREMENTS DOCUMENT (CRD) DOE O 151.1E, COMPREHENSIVE EMERGENCY MANAGEMENT SYSTEM
ATTACHMENT 2 ACRONYMS AND ABBREVIATIONS
ATTACHMENT 3 EMERGENCY MANAGEMENT PROGRAM
ATTACHMENT 4 REFERENCES
ATTACHMENT 5 DEFINITIONS