DOE N 4700.5, Project Control Systems Guidelines
Functional areas: Project Management
Cancels DOE O 2250.1D. Extended by DOE N 4700.6.
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
U.S.DepartmentofEnergy
Washington, D.C.
NOTICE
r -.._..—
DOE, h L700,5
1
L... ~...__._.-.----J
8 21-92
EXPIRE: 8 2193
PROJECT CONTROL SYSTEM GUIDELINES
SUBJECT:
1. PURPOSE. To establish the Department cf Energy (DOE) policy for
applying control systems for overall manigernent of projects, including
Major System Acquisitions (MSAS), Major ‘rejects (MPs), Other Line Item
projects, General Plant Projects (GPP$I. a’.ldoperating funded projects
and contracts within those project$
2. CANCELLATION. DOE 22!501D, COST ANC~$ “DJLE CONTROL SYSTEMS CRITERIA,
of 6-12-92.
3. BACKGROUND. Previously, DOE used t,he~ ::[and Schedule Control Systems
Criteria (CSCSC) to evaluate manageme~~t :::ystemson selected contracts
primarily for MSAS and MPs. Use of t$e CSCSC were normally neither
required nor encouraged for all other p o.jects. Consequently, the
Department has no existing policy for u ;“lication of overall, integrated
project controls to the wide range of OE projects. Replacing the CSCSC
with more comprehe]~sive guidelines an...~~,quiringapplication of these
guidelines to all corlst.ructionano erw~wrlment.alprojects will
significantly expal~clfundamental corItI I Dross the spectrum of DOE
projects.
4. DISCUSSION.
a. A cornerstone of the Department” project management policy is the
concept of accountability at appropriate levels for project
control and management. Project managers, as accountable
managers, must be directly invo’1ed in the application of overall
project controls. “Thispolicy P sures that the accountable
project manager is responsibl~ ‘ r appropriate application of
overall pro jet control:
b. An essential element of account~oi ’lityis overall project control
of technical $cope,, COSt, and so~edule baselines as well as
associated research and develc)r)fi~nt(R&D), transition planning and
baseline chanqe.s This policy ~~f”]ectsDepartmental concern with
all elements of project control ard expands the earlier CSCSC to
encompass ove”all control by pi [;,inggreater emphasis on control
of technical, schedule, and m! baselines and baseline changes.
c. The previous CSCSC Order focu:e principally on MSAS and MPs;
however, the Department is resp n::,itllefor many other types of
projects, This policy direct; co$t effective, graded approach
to application of project cantrd:, providing flexibility in
application t[:all projects arIc lcontr-act.s,MSAS or other, On the
,,,,
DISTRIBUTION: INITIATED BY.
All Departmental Elemenf ]fftie of Procurement, Assistance
ir)jProgram Management
DOE N 4700.5
8-2192
basis of the scale and type and ~nlque needs of each project.
Although the principles of projet control apply equally to a“
projects, project control for a !1 million GPP should be less
complex and less costly than for a $100 million MSA. Project
controls should be applied accor]ing to the needs of the spec
project commensurate with techni a“l,schedule, and cost risks
d. This Notice provides Project Confrol System Guidelines
1
fic
(Guidelines)” (see Attachment 2), which expand upon and replace the
earlier CSCSC The management systems needed to properl,y control
the direction and progress of DOE projects reach beyond control of
costs and extend to control of t(!chnicd and schedule baselines
which significantly impact projef:tcosts. The Guidelines
emphasize management control system re:slultsand de-emphasize the
process to obtain the results. ‘rheGuidelines apply to all
projects; however, full implementation of each guideline is not
required. The DOE Project Manager wil”lassess each contract and
project to determine the appropriate degree of Guidelines
application b~sed on project risl(
Section 2
e. The Guideline$ are assembled int~ three primary categories:
(1) Baseline Develo~ment. Thi:;category includes management
actions necessary to define project scope and
responsikiliiies, est.abli:~~baselines, and plan the project.
(2) Pro,iect,.,PerformanceeThis category includes management
actions after work commenfes that are necessary to monitor
project status, report ano analyze performance, and maintain
visibility of identified {ro.jectrisk.
(3) Chanqe Management. This;fategory includes management
actions necessary to ensure adequate control of changes to
project baselines, irrcludng the performance measurement
baselin~?
f. The Project Control System (PCS retains use of the Uniform
Reporting System’s standardized report formats. However, the PCS
also encourages use of nonstand,:irdreports to depict technical
performance indicators, critics path schedule status and other
project and contract-specific rpc~rts.
9. Through publication of this Not ce, the formal CSCSC contractor
validation process is replaced y a cc~mpliance review process
consisting of a review of the s~st,emdescription followed by a
functional appraisal. The revivw responsibility has been assigned
to each DOE Field Office with P~ogram Secretarial Officer (PSO)
participation. PSOS sponsoring MSAS without direct DOE Field
Office projec:t,management shall be responsible for conducting
compliance r~wiews of their contractors’ systems.
DCJEN 4700.5 3
8-21-.92
h. Assistance in implementation l~fthis new policy is available. A
reference manual is available tclprovide implementation guidance.
The manual addresses application of the Guidelines through a risk-
based, graded approach. The manual clarifies, and provides
examples in application of each guideline element. Additional
sections address roles and re:~pcmsibilities, project status
analysis, reporting, and the (compliance review process. A Project
Control System (PCS) Advisory Team is available through the Office
of Program/Project Management and Control to provide assistance as
required.
5~~ REFERENCES.
a. DOE 1332.1A, IJNIFORMREPORTING SYSTEM, of 10-15-85, which
establishes and provides implementing instructions for a uniform
system of reporting the accomplishments under contracts
b. DOE 4240.lK, DESIGNATION OF MAJOIR SYSTEM ACQUISITIONS AND MAJOR
PROJECTS, of 6-23-92, which lsts specific DOE projects which have
been designated as Major Sy$,t[!mAcquisitions and Major Projects.
c. DOE 4700.1, PROJECT MANAGEMENT SYSTEM, of 3-6-87, which
establishes the DOE project management system and provides imple-
menting instructions, formats,,and procedures, sets forth the
principles and requirements which govern the development,
approval, and execution of [10[‘s outlay program acquisitions.
d. DOE 5700.2D, COST ESTIMATING,,ANALYSIS, AND STANDARDIZA”TION, of
6-12-92, which establishes th~!policy and responsibilities for
developing and reviewing project cost estimates, preparing
independent cost estimates and analysis, standardizing cost
estimating procedures, and improving overall cost estimating and
analytical techniques, cost database, cost and economic. models
escalation, and cost estimat,irq systems,
6. DEFINITIONS. See Attachment 1
7. POLICY.
a. PSOS, field elements, and their contractors are expected to comply
with the Project Control System Guidelines in management of all
projects by applying guideline elements in a graded approach to
reflect the degree of each pr[ject’s and contract’s technical,
schedule, ar~dcost risks
Section 3
b. The Guidelines shall be used to evaluate contractors’ project
control systems to assure that the systems are sound and that
progress reports to DOE management are reliable.
4 DOE N 4700.5
8-2192
c. In accordance with SEN-6E, DEPARTMENTAL ORGANIZATIONAL AND
MANAGEMENT ARRANGEMENTS, of 2-21-92, the DOE Field Office Manager
is accountable to a Lead PSO cln institutional and crosscutting
issues. The Lead PSO is responsible for developing an
Implementation Plan for his/her DOE Field Office. The
Implementation Plan shall be applicable to all projects managed by
the DOE Field Office. The Lead PSO shall be responsible for
coordinating concurrences with all other PSOS sponsoring projects
which are managed through that,DOE Field Office.
d. Each DOE Fidld Office shall formulate an Implementation Plan for
this Notice which outlines the graded approach to projects,
addresses applicability, delinfiates responsibilities, and details
the compliance review process. This Implementation Plan will be
reviewed and approved by the L~+adPSO and other PSOS sponsoring
projects managed through the DOE Field Office, and the Office of
Procurement, Assistance and Pr:,]gramManagement, through the Office
of Program/Project Management lnd Control.
e. PSOS managing MSAS without d~r~ct. DOE Field Office project
management :,upportshall formulate an Implementation Plan which
outlines the graded approach t.(;II contracts, addresses
applicability, delineates responsibilities, and details the
compliance review process. Th~s Implementation Plan shall be
approved by the PSO and the Office of Procurement, Assistance and
Program Management, through t$f Office of Program/Project
Management and Control.
f. PSOS shall ensure implementation of timely and cost-effective
project controll systems in com~lliance with these Guidelines for
all their projects by participating in the compliance review
process and concurrence in com~liance review results.
9- An Advisory i’eamwill be chartered by the Office of
Program/Project, Management and Control to provide expertise and
guidance to rvnsurea practical,,cost-effective interpretation of
the Guidelin~s, This team will provide assistance in determining
compliance fr]runusual circum:it,incesand will recommend resolution
of discrepan~:,,iesthat arise it ~etermining acceptability,,
h. This Notice does not apply to IWwer Marketing Administrations or
facilities and activities cov~r’d under Executive Order 1,2344.
8. OBJECTIVES.
a. Provide a basis for application of project management controls and
when to apply these controls to all DOE projects and project-
related contracts,,
DOE N 4700.5 5
8-21-92
b. Provide project managers the flexibility to tailor requirements,
encourage formulation of customized project control strategies for
each project or group of projects, and emphasize the appropriate
degree of application for each guideline element to effectively
control technical, schedule, ald cost risks.
c. Provide contractor and DOE maniigement with timely, useful
information to manage a projecf, or contract and communicate
information to senior DOE management. The Guidelines establish ii
framework tc]:
(1) Properly define and orqaize project and contract work;
(2) Establish and maintain t’chnical, schedule, and cost
baselines;
(3) Develop practical, meanirlgful performance indicators to
provide early warnings of project problems;
(4) Ensure management visibility for control of technical,
schedule, and cost basel nes;
Section 4
(5) Provide timely, valid, :~d traceable baseline performance
and trend data; and
(6) Ensure accurate, timel;j ~nd properly controlled baseline
changes;
d. Ensure consistent Guidelines (oplication throughout the life of
the contract or project.
e. Promote consistent evaluation of contractors’ systems and provide
assurance that such systems ae sound and cost effective.
f. Compliance reviews for new MP should be completed within 120 days
after KD1 and for MSAS within 180 days after KD1.
9, APPLICABILITY OF_GUIDELINES.
a. The Guidelines shall be used Iy all PSOS for controlling all MSAS,
MPs, other line item projects GPPs and operating funded projects.
The Guidelines are applicable to al-lprojects whether for
production, facility modifications, or research and development
using a risk-based, graded aporoach.
b. The Guidelines shall be appli{:able to DOE contractors performing
DOE project.work. The Guidelnes reflect the needs of sound
project management while provding flexibility. Flowdown of
Guidelines to individual cont~-actors within a project, and the
degree of ~pplication of each guideline element, shall consider
risk, duration, cost, managem{’nt.utility, cost effectiveness, and
6 DOE N 4700.5
8-21-92
contract type. Fixed-price contracts will normally be required to
implement selected guideline elements; schedule status reporting,
problem reporting, and change management are examples of guideline
elements that may be required in fixed-price contracts
c. The Guidelines are not applicable to managing and operating (MAO)
contractors performing normal ,ite operation functions; however,
the Guidelines are applicable ‘o project work performed by M&O
contractors
10. RESPONSIBILITIES A~ AUTHORITY.
a. Director of Procurement, Assis~@lce and Proqram Manaciement,
throuqh the Associate Directo,~~~ Proqram/Pro.iect Management and
Control, shall:
(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
Define and update the Guidelines and other documentation,
and develop the policy f}r guideline use and application.
Provide assistance on application and interpretation of
problems encountered dur:ng compliance reviews.
Review and concur with tne DOE Field Office or PSO Project
Control System Guideline [mpleme~tation Plan.
Participate in compliancy l~eviews for MSAS and concur with
review findings and recwlmendations.
Develop and provide implementing clauses and procurement
reguldt,ions for use in ~ ]1
Monitor compliance with h
Department
Approve technical training
citations and contracts.
s Notice throughout the
courses developed by the Director
of”Professional and Technical Training and Development for
implementation of this I’w}tice.
Establish and chair a f)tiAdvisory Team as the focal point
for interpretation and a~]plication of the Guidelines.
b. Director of Administration and Human Resource Management, throuqh
the Director of Professional ad Technical Traininq and
Development, shall develop and conduct training courses for
implementation of this Notice and the Guidelines, within the
framework of the Departmental training program.
c. Lead Proqram Secretarial Off:~t~ shall:
(1) Ensure development of a ~roject Control System Guidelines
Implementation Plan for ‘he cognizant DOE Field Office.
DOE N 4700.5 7
8-21-92
(2) Coordinate Implementatlor Plan concurrences with other PSOS
responsible for projects managed by the DOE Field Office and
coordinate Implementatior~ F’Ianconcurrences with the Office
of Procurement, Assistance and Program Management..
Section 5
(3) Participate in complianc,l reviews at their respective DOE
Field Offices.
d. Proaram Secretarial Officers W.MI Projects Manaqed Throuqh DOE
Field Office~l shall:
(1) Review and concur with It Field Office Implementation
Plans,
(2) Review and concur with tle M&O contractors’ and other DOE
prime contractors’ pro,]pt control systems.
(3) Participate in reviews o contractor systems.
(4) Concur with project rnanaqer recommendations for extent of
Guidelines application tlal.contractors will be required to
implement for their MSA! aridMPs.
e. Manaqers of DOE Field Off@> hall:
(1)
(2)
(3)
(4)
Designate a primary responsibility organization to prepare
and maintain an overall ‘reject Control System Guidelines
Implementation Plan cove ing all projects managed within the
field element and monito adherence to the plan. The plan
will specify the extent f Guidelines application for all
projects using ~ risk-bii d, graded approach.
Coordinate with the cogn zant PSOS and
Program/Project Managemet and Control
Implementation Plan. a e~essarya
Chair the contractor sys’erncompliance
the Office of
to update the
review and provide
personnel for participant on on the review. Notify the
cognizant PSO and the Of(ice of Program/Project Management
and Control of the compl iancereview.
Incorporate Guidelines ilnp”lementationrequirements into
existing contracts, new ontracts, and solicitations as
appropriate. Provide perspective contractors with informa-
tion on Guidelines’ requ rements. After contract award or
modification of existing contracts, conduct compliance
review~ of contractor pr ,jectcontrol systems in accordance
with d,p“lanand schedull ~~!reedupon between the PSO, the
8
(5)
(6)
(7)
DOE N 4700.5
8-21-92
DOE Field Office, and the Office of Program/Project
Management and Control. Plans and schedules for incorpora-
ting the Guidelines intc existing contracts shall be
included in Implementation Plans.
Obtain PSO and Office 01 Program/Project Management and
Control concurrence for MSA contractors’ project control
systems acceptance follc~wing compliance reviews; and for
other projects, program ~ffice concurrence for other con-
tractor-s’ project contrfl systems following compliance
review!,
Assure that the Project [Management Plan or other
documentation, as appro[ piate, is the basis for Guidelines
implementation.
PSOS managing projects rot managed through a DOE Field. .. ...
Office shall perform thf functions in paragraph 10e(l=)
through (6), above
f. Project Manaclers shall:
(1)
(2)
(3)
(4)
(5)
Identify the degree of applicability of guideline elements
to their particular project and selected contracts therein,
and forward recommendations to the DOE Field Office and PSO,
as required, prior to the compliance review and participate
in the compliance revie~ process, as appropriate.
Prepare a Project Management Plan using the work breakdown
structure and the techni::al, schedule, and cost baselines as
the basis for Guidelin~’! implementation.
Specify the frequency of reporting and establish variance
analyslis)thresholds for ~ffective management.
Develop project-specific procedures for use and allocation
of contingency, as requiwd.
Provide written comments or findings to the contractor for
clearly established management action and resolution
following the review of ‘he system description and
functional appraisal and nDtify the contractor when findings
have been satisfactorily r~solvedm
BY ORDER OF THE SECRETARY OF ENERGY:
Section 6
C\--,<,
@))
DOLORES L. ROZZI
I Director of Administrationi:t #
# and Human Resource Management, ,..,>$7
DOE N 4700.5 Attachment 1
8-21-92 Page 1
1.
2.
3.
4,
5.
6.
7.
8.
9.
10.
DEFINI~,JfiJ
ACCOUNT STRUCTURE. A formal organi~ation of accounting codes used to
collect costs for control account wt~rk.which provides needed
information, segregated as necessar~, for reporting costs.
ACTUAL COST. The Actual Cost of Work Performed (ACWP) is the cost
incurred and recorded in the accounting system for accomplishing the
work performed within a specific tine period.
AUTHORIZED WORK. Work that has bee~ clefinitized and is included in the
contract value as well as work that has been authorized in writing, but
contract value has not been determi~ecl and agreed.
BASELINE. A quantitative expressior~ c~fprojected technical, schedule
and cost base, or standard for measurement during the performance of an
effort: the established plan aqains which the status of resources and
the objectives
BUDGETED COST.
budgets for al
within a given
CHANGE CONTROL
of a project ca~ be measured.
The Budgeted Cost o’ Work Scheduled (BCWS) is the sum of
cont,rol accounts Fo work scheduled to be accomplished
time period.
A ciocumented proce s applying technical and management
review and approval of changes to tchnica’1, schedule, and cost
baselines. ‘“
COMPLIANCE REVIEW. An assessment [~)the contractor’s project management
control system. The assessment norlnally occurs in two steps: a. The
contracto} submits a description of its-management control” system to the
Department of Energy (DOE) for revi:w against specific applicable
Project Control System Guidelines a~d the DOE Field Office or Program
Office Implementation Plan; and b. A review team conducts a functional
analysis of the contractor’s system to determine adherence tcIthe
published description ~nd integrity of contractor data.
COMPLIANCE REVIEW CHAIRMAN. The Ch~irman is normally a DOE Field Office
or PSO representative. The Chairmav\ is responsible for day-to-day
activities, Typica”l activities include planning and scheduling the
review, organizing and leading the review team, resolving identified
system discrepancies with the cont,r~ctor, and preparing the review
report.
COMPLIANCE REVIEW TEAM. A team representing the DOE Field Office
organization or PSO, as appropriate which evaluates a contractor’s
project control :~sltem
CONTINGENCY. An ~mount of budget t cover costs that may result from
incomplete desigr, unforeseen and unpredictable conditions, or
uncertainties. (~lntingency is conto”lled by DOE and not included in the
performance meas~,’ement.baseline
Attachment 1 DOE N 4700.5
Page 2’ 8-21-92
11.
12.
13.
14.
15.
16.
17.
18.
CONTROL ACCOUNT. The management control point at which actual costs are
accumulated and performance determined. It represents the defined work
assigned to one responsible organizational element for the lowest level
work breakdown structure element and must contain the specific scope of
work, definite schedule, assigned budget, unique identification and
method of measuring performance. The control account concept is
applicable to all prc~jects;large projects may have a series of control
accounts which may be divided into wclrkpackages and planning packages,
if desired; small prc~jectsmay have [PIlyone control account consisting
of a single charge number.
Section 7
COST BASELINE. A budget that has been developed from the cost estimate
made at approval of the technical ba:eline, and the majority of the
budget has been time-phased in accordance with the project schedule.
The cost baseline is referred to as a baseline since it is integrated
with the technical and schedule base”ines and subject to formal change
control. The cost baseline normally contains direct and indirect
budget; management reserve budget; undistributed budget and higher level
budgets; contingency amount; and amo[l~tfor fee, as appropriate.
DIRECT COST. Any cost that is specifically identified with a particular
project or activity, including salar es, travel, equipment, and supplies
directly benefiting the project or a~t,ivity.
EARNED VALUE. The value of completed work expressed in terms of the
budget assigned to such work. Also ~:ferred to as the Budgeted Cost of
Work Performed (,BCWP),
ESTIMATE AT COMPLETION (EAC}. The a(:tual cost incurred to date plus the
estimated cost (direct and indirect) of all remaining work, including
authorized work that,has not been de;rlitized.
FUNCTIONAL APPRAISAL. An on-site review of the use and effectiveness of
a contractor’s project control system whereby system deficiencies are
noted and recommendations made for corrective action.
GRADED APPLICATION. A flexible sele~,,,tionprocess that enables the
project manager to include or omit individual guideline elements and,
within elements, choose a less rigorous,application. This flexibility
allows tailoring the project control needs to the specific project or
contract, considering risks and complexities of the project, For
example, the guideline element, “Plalnningand Scheduling,” for a complex
Major Systems Acquisition (MSA) may ecluire multi-level, critical path,
logic based schedules, as compared to a simple Gantt chart with a
completion milestone for a small Gen’ral Plant Project.
INDIRECT COST. The cost incurred by an organization for common or joint
objectives which cannot be identifie! specifically with a particular
project or activity
DOE N.4700.5 Attachment 1
8-21-92 Page 3
19.
20.
21.
22.
23,
24.
25.
26.
27.
INTERFACE POINT. The functional, physical, or system characteristics at
a common boundary between two or mor~ project participants.
LEAD PROGRAM SECRETARIAL OFFICER (Lead PSO). The PSO assigned line
management responsibility and accountability for Headquarters and field
operations and to which one or more nu”lti-prograrnDOE Field Offices
report directly.
LEVEL OF EFFORT (LOE}. Support effort that cannot be measured in terms
of discrete accomplishment. LOE is characterized by a sustained rate of
activity for a specific period of tine.
MANAGEMENT RESERVE (MR). That portiln of the contract or project budget
controlled by the contractor for mand(j(~ment. purposes and not designated
for the accomplishment of specific ttsl~s;when MR is used it is
distributed to specific accounts
ORGANIZATIONAL BREAKDOWN STRUCTURE (0]~. The hierarchical arrangement
for a company’s management organization, graphically depicting the
reporting relationships. Normally, the OBS is limited to showing only
managerial positions, but may depict lower organizational levels. The
structure may also show subcontract ‘relationshipsdepending upon the
purpose of the OBS
PERFORMANCE MEASUREMENT BASELINE (PM~. The total allocated budget less
management reserve. It is the time phased budget plan against which
contract performance is formally mea:,ured. The performance measurement
baseline includes budgets assigned t I:ontrolaccounts and undistributed
budgets.
Section 8
PROJECT. A unique major effort withn a program which has firmly
scheduled beginning, intermediate, a’~dending date milestones;
prescribed performance requirements, prescribed costs; and close manage-
ment, planning, and control. A proj~:ct is a basic building block in
relation to a program which is indivr,dually planned, approved, and
managed. A project is not constrained to any specific element of the
budget structure (e.g. operating exp!n~e or plant and capital equip-
ment) . Construction, f required, i , part of the total project.
Authorized, and at least partially a~)propriated, project will be divided
into three categories: MSAS, Major “)rojects,and Other projects.
PROJECT CONTROL SYSTEM The planninq, scheduling, budgeting,
estimating, work =rization, cost accumulation, performance
measurement, reporting, change contr~l, and other systems used by a
contractor to plan and control the w~rl<,,
PROJECT CONTROL SY~EM GUIDELINES. )01 established characteristics that
contractors’ internal management control systems must possess to assure
effective planning% management, and c]ntrolof projects and contracts.
Attachment 1 DOE N 4700.5
Page 4 8-21-92
28.
29.
30.
31.
32.
33.
34.
35.
36.
37.
PROJECT CONTROL SYSTEM GUIDELINES IMPLEMENTATION PLAN. A DOE Field
Office or PSO plan for implementing the Project Control System
Guidelines. The plan includes implementation policy, describes the
graded application of guideline elements to projects and contracts,
delineates responsibilities, and outlines the compliance review process.
PROJECT RISK. A factor, element, constraint, or course of action on a
project that introduces an uncertainty of outcome and the possibility of
technical deficiencies, inadequate p~rformance, schedule delays, or cost
overruns which could impact a Departmental mission. Evaluation of
project risk must consider the poten+ ial impact and the probability of
occurrence.
SCHEDULE BASELINE. The time phased plan with a logical sequence of
interdependent activities, milestone: and events necessary to complete
the project. The schedule baseline ha,llbe formally changed during the
execution of the pro,jectwhen requ-irld.
TECHNICAL BASELINE. A configuration identification dccument or set of
documents formally designated and apprc~ved by DOE. The Conceptual
Design Report (CDR) will become the nitial project technical baseline.
The initial technical baseline, plus DOE approved changes to that
baseline, constitutes the current tehnical baseline.
TOTAL ALLOCATED BUDGET (TAB). The sl~mof all budgets allocated to the
contract or project, as applicable. TcjtalAllocated Budget consists of
the performance measurement baseline plus management reserve.
TOTAL ESTIMATED COST (TEC). The budfqet.edcosts for land, design,
construction, equipment, escalation ind contingency for a given project.
For further clarification, see DOE 4’00.1.
TOTAL PROJECT COST (TPC). The cost ~f the project including all of the
TEC, the cost of all preliminary desgn, conceptual engineering,
research and development, project sul:]portfor a given project, and the
cost of transition to operations. F r further clarification,, see DOE
4700.1.
UNDISTRIBUTED BUDGET (UB). Budget within the performance measurement
baseline applicable to the work effot that has not yet been identified
to both a responsible organization ~,d a WBS element.
Section 9
VARIANCE. The difference between pl~nned and actual performance.
Variances that exceed established thresholds normally require further
review, analysis or action. Established thresholds should be revised
during the life of a project to en:ue meaningful analysis.
WORK AUTHORIZATION. A contractor’s Internally documented process or
system that ensures work is properl,yauthorized and assigned at the
appropriate organi~ational levels ir o~’to beginning the work.
DOE N 4700.5 Attachment 1
8-21-92 Page 5 (and 6)
38. WORK BREAKDOWN STRUCT~. A multi-tiered framework which organizes and
graphically displays elements representing work to be accomplished in
logical relationships. The WBS may cr may not be product-oriented;
orientation may be towards products, project phases, key decision
points, various budgeting units of measure, e.g. activity data sheets,
or a combination. The WBS should be organized such that each element
can be estimated, ,cheduled, budget~c , and work progress reported.
39. WORK PACKAGE. Subdivisions of the lowest level WBS element accorded
detailed scope, schedule (start and [ompletion points), budget, a
description of SCODP (including acli~ ities) and responsible manager.
DOE N 4700.5
8-21-92
Attachment 2
Pac]e 1
PROJECT CONTROL SY~l:~.GUIDELINES
1. GENERAL.
a. The Project control systems usld by contractors in Plannin9 and
controlling the perfo~mance of their contract work sha-llmeet
Guidelines set forth in this a!t.achment as directed by the
Contracting Officer. The Guidi~l-lnescontained herein are the
basic requirements. The specific Guidelines and Guide”lines
elements applicable to a contr,ict or project will be as determ
by Department of Energy (DOE). Nothing in these Guide”lines is
intended to iiffect the basis o which costs are reimbursed and
he
ned
progress payments are made, an! nothing herein will be construed
as requiring the use of any sig-le system, or specific method of
management control or evaluati n of performance.
b. For contractors responding to -,,solicitation to perform project
work, an element in the evaluation of proposals will be the
offeror’s systems for planning and controlling contract
performance. “Theofferor will fully describe the system to be
used. The ~ystem described in the proposal will be evaluated to
determine whether it meets the necessary project management
control Guidelines promulgated b;ythis notice.
2. PROJECT CONTROL SYSTEM GUIDELINES (G~IllELINES). The Guidelines are
divided into three categories: base’’ine development, project
performance, and change management
a. Baseline Develo~ment. This ca!.egory includes management actions
necessary to define project c ~pe and responsibilities, establish
baselines, iindplan the proj~c ,
(1) Techni~l Baseline and,.,~olkSco~e Definition.
(a) Ob.iective. To stricture the project’s technical work
to ensure defined ~bjectives are achieved. Establish
the framework to ilt,egrate all elements of the
Guidelines.
(b) ~~!ements.
1 Establish and maintain the approved projectL.
technical baseline (work scope typically
established in the Conceptual Design Report) in
a manner that ensures it is subject to formal
change contr]l
2 Define all authorized project work in a Work.
Breakdown !;tlaucture(WBS) that represents the
way the work will be estimated, scheduled,
budgeted, :~c-formed and managed. Maintain the
Attachment 2
Page 2
DOE N 4700.5
8-21-92
(2)
WBS to be cc}nsistent with project needs
throughout the life of the project, ensuring
changes to tne WBS are made within a formal
change cont~~l process.
Section 10
Roles, and ResPonsibil it-M.
(a) Objective. To identify all the project’s
participants, ther responsibilities, and the role
each performs on ‘he project.
(b) ~lements.
1 Clearly identify, utilizing an Organizational—.
Breakdown S+.ructure (OBS) approach, to the
control account level, each manager responsible
for all project work. In addition, identify
their functional and technical scope
responsibil ities, their limits of authority, and
interface p~]intswith other project
participant. ,
2 Identify t.h~+persons with the authority and
responsibil tty for controlling indirect costs.
3 Perform control account management at the level
consistent with management responsibilities,
organizatio~ll:itructure and the contractor’s
commonly ac epted practices.
4 Ensure that each control account is assigned to
a person wh~ has the authority and
responsibil ity to control the resources and work
activities ,~ithinthe written technical,
schedule, dnd cost baselines.
5 Ensure that the control account and the schedule-.
status are Irecordedon a timely basis to
maintain c.ul’rentperiod, cumulative-to-date and
at-completion records.
5 As early as practical throughout the per
of the project, ensure that each control
is assigned to a specific project partic
manager or subcontractor manager who wil-
responsible f[]rthe planning and control
work scope .ompris,ingthat account.
ormance
account
pant
be
of the
DOE N 4700.5
8-21--92
Attachment 2
Page 3
(3)
(4)
Cost Estimating.
(a) Ob.iective. To p“lace emphasis on cost estimating as an
integral and key i~spect of baseline budget
development, emphasize the importance of accurate
estimates-at-completion, and retain the separation of
expense and capiti~l monies.
(b) Elements.
~ Prepare cos! estimates using appropriate
estimating methodologies that are integrated
with the WBS, and the DOE cost structure as
specified b;~the DOE, for all contract work.
Ensure that all estimates are consistent with
DOE 5700.2D and in accordance with FAR 15.804,
“Cost and Price Data Analysis,” as applicable.
Prepare estimates, as applicable, in accordance
with establ shed project phases, maintaining a
distinction between Total Estimated Cost and
Total Proje.t Cost. Maintain an appropriate
cost estimating capability to accommodate
project estrnates-to-complete and est,imates-at-
completion
Planninq and Schedu~ng
(a) Objective. To en,ure that all known requirements
affecting a proje[t are identified and considered in
the development of project baselines; ensure
visibility of critical path activities and DOE
milestones; and ensure that all project work is
scheduled using a disciplined approach, and properly
integrated with other guideline elements.
(b) Elements.
1.- Ensure that a process is established and is in
operation throughout the project life to iden-
tify programmatic, operational, legislative,
institutioniil, and other requirements or con-
straints which may affect technical, cost, or
schedule baselines and ensure that such
baselines properly reflect such potential
impacts,,
~ Develop schedules that integrate with the WBS
and cost estimate, and represent all work scope
regardles, ]f funding source. Use activity
Attachment 2
Page 4 -
DOE N 4700.5
8-21-92
logic to depi[t all work scope, constraints, and
decision points. Estimate and assign durations
to activities representing work accomplishment.
Section 11
3 Establish an approved schedule baseline which
clearly depicts critical path activities and
milestones from which actual performance for all
activities and milestones can be compared, and
from which forecast data can be generated.
Resource-load activities, as required and at the
appropriate level, to develop time-phased
budgets that ~re integrated with the schedule.
Permit only a~thorized changes to the schedule
baseline.
4 Summarize the detail schedule activities to form
master and intermediate level schedules as
required. Maintain identification of milestones
with approprii~t[?schedule levels.
(5) Cost BaseM.
(a) 03ectives.
1 To ensure tha: an account structure is
established t, collect costs against specific
scopes of wor~ , and to measure performance;
~
To ensure tha! budgets for labor, services,
subcontracts, and materials are established at
the proper levels and time phased in accordance
with the proj-ct schedule;
\,,.,. To ensure tha’ the TPC is accounted for within
the system; a c1
4 ‘Toensure thal the project direct costs and
indirect co’;t are identified and managed.
(b) Elements.
J Develop a control account structure that is
integrated with the WBS, and facilitates
collection of expense and capital costs, by
organization dnd cost element as appropriate.
Establish and implement a process for
controlling t’lleopening and closing of control
accounts for ‘he life of the project
DOE N 4700.5
8-21’-92
Attachment 2
Page 5
~ Identify, In each control account, the work
scope for that account. Establish a budget fc}r
the”work, ensuring the budget is time phased
accordance with the schedule baseline and the
availability of resources. Ensure the contro”
account budget basis is reconcilable with the
cost estimate and subsequently approved
revisions
n
~ Ensure th;it all work is represented in contro”l
accounts, and the sum of all control account
budgets, plus contingency, and management
reserve at~dfee, equals the TPC or contract
value, as appropriate. Ensure that budget
values us~!dfor planning purposes, that are not
included In the approved project baseline, are
identifie~las such,
~ Establish a practical and effective method of
measuring performance in the control account
prior to beginning work. Maintain continuity of
the measurement method throughout the life of
the control account. Ensure that values used
for performimce determinations are verifiable
and consistent with schedule performance.
~ Establish and maintain an auditab”le system for
the development, maintenance, analysis and
control o~ indirect budgets and costs.
jj When a management reserve is established, ensure
that procedures are in place to control its
establishment, use, and replenishment.
b. Pro.iect Performance. This category includes management actions
after work commences that are necessary to monitor project status,
report and analyze performance, and manage risk.
(1) Funds Manacrement.
(a) Objective. To provide a process that integrates the
management of funds with other guideline elements, and
ensures that funding impacts are reflected in project
or contract ba:~lines as appropriate.
(b) Elements.
~ Ensure that the commitment and expenditure of
funds wi”’1not exceed the authorized limits.
Provide (arly warnings that funding limits are
about to w exceeded.
Attachment 2
Page 6
DOE N 4700.5
8-21-92
~ Evaluate the impact of changes to planned
funding limits and, in turn, on technical, cost,
and schedule baselines, and ensure that such
impacts are appropriately reflected in changes
to the baselines.
Section 12
3 Maintain the ability to reconcile between
forecasts for funding requirements and estimates
for costs to execute project work.
(2) Accounting._
(a) Objective. To ensure the proper utilization of
accounting data in baseline management.
(b) Elements.
~. Record on a ‘imely basis, at the control account
level, the actual direct costs which have been
incurred for resources applied in the perform-
ance of work Ensure that such cost assignments
are made in ,iccordance with a formal system that
is controlle~~ by the general books of accounts.
~ Ensure that ~ctual costs are applied in the same
accounting ph:riod that performance is measured
and recorded
:3 Consistent w~th Federal Acquisition Regulations,
Department of Energy Acquisition Regulations,
and other applicable regulations, record and
apply all indirect costs that are allocated to
the projec’
4 Where allocations of direct costs must be made.—
from a singlb collection point to multiple
control accoun-ts, substantiate the basis for
such allocat ORS.
~ Correct mi~charges and other accounting errors
in a timel!’ manner.
(3) Work Authorization,
(a) Ob.iective. To ensure that after the work is
sufficiently defined, organized, and planned, the
resulting control ,iccount is authorized by the
appropriate level ]f management before the task is
executed.
DOE N 4700.5
8-21-92
Attachment 2
Page 7
(b) Element. Establi:n and maintain a work authorization
process which authorizes the expenditure of resources
against baselines;, prevents the expenditure of
resources for work or procurement without appropriate
plans and approval at the appropriate level of
management; terminates authority when funding limits
or other limits of authority or constraints would be
exceeded; and prevents the expenditure of funds for
unauthorized work ]r procurement.
(4) Performance Analysis.
(a) Objective. To determine project status by analyzing
technical, schedul?, and cost performance considering
potential problem:,, their impact, and alternative
courses of action
(b) flements.
1 On a periodic basis,.- identify significant
differences between planned and actual cost,
schedule ant!technical accomplishments and
revise pro,j~rt forecasts, as appropriate.
~ Use an accepted and documented performance
measurement process to determine actual
technical, schedule, and cost performance,
identify problems encountered, the reasons for
such problem;, and any impacts and corrective
action requi~ed.
~ Periodically, ensure that the validity of
estimates-at completion (EACS) are evaluated and
revisions generated as required. The EAC must
represent a realistic appraisal of the final
cost of defi’}ed increments of work and undefined
potential fa;tors affecting final cost
summarized t ] the total project level,
(5) ReRortin~
(a) Ob.iective. To communicate timely, accurate periodic
progress reports in the formats and reporting levels
stipulated by DOE to the appropriate management level
which will enable {~nalysis, evaluation, and corrective
action of technics, schedule and cost performance
against the approv+d baselines.
Attachment 2
Page’8
DOE N 4700.5
8-21-92
(b) ~lements.
j Provide narrative status reports, including
problems, technical and physical progress,
performance objectives, schedule status, and
cost performance that includes the contractor
project manager’s summary assessment of progress
commencing it KD1 or project start.
Section 13
Provide schedl~le status reports that include
critical path visibility and progress against
the baseline. The reports must present status
of DOE controlled milestones and provide current
forecast dates. Status, including early or out
of cycle reporting, is to be issued as required
in response to an occurrence that unfavorably
affects th~ project progress.
3 Provide cost status reports, including both-.
direct and indirect costs, that provide current
period, cumulative and estimate-at-completion
costs repor:ed again~t the time phased cost
plan.
4 Provide labor status reports that provide-.
current period, cumulative and estimate-at-
completion floursreported against the time
phased Iab(r plan.
~
J Provide pr{olem reporting that presents the
significant issues or concerns of the project
manager, w-th proposed corrective actions. Any
problem or issue requiring Government action
must be reported. Items reported must be
maintained Ionthe report until satisfactorily
resolved
~ Provide a Iaseline change status report that
presents tie status of changes affecting the
contract I project as appropriate.
7 Develop pr~:deterrninedthresholds that prescribe.-
which varit~nces, issues and problems are
significant and warrant a detailed analysis of
the causes and actions taken to alleviate the
problem,
j~ Provide vi ibility of project technical,
schedule, ~nd cost risks through the narrative
status r~p r-laddressing contract claims,
impa(:t~~~ m new or revised DOE Orders or
DOE N 4700.5
8-21-92
Attachment 2
Page 9 (and 10)
requirement:i, environmental, safety and health
concerns. or ther probable high impact risk
areas.
9 Provide trend charts that graphically display.—
meaningful performance measurement data against
the approved ‘vaselines. The charts must address
technical performance, schedule, labor, and cost
as a minimum
c. Chancie Management. This categoy includes management actions
necessary to ensure adequate coltrol of project baselines
including the performance mea;u ement baseline.
(1) Ob.iective, To establish ~nd maintain a timely, formal
process for managing and ~dministering changes to the
approved technical, cost Ind schedule baselines with
rebaselining occurring on y when necessitated by
signifi~ ant, unrecoverahl project delays, events, or other
impact:
(2) Elemenl.j~.
(a)
(b)
(c)
(d)
(e)
(f)
Assure the technics , schedule, and cost baselines and
established change ontrol thresholds are clearly
defined, documented and approved by DOE;
Pssure that basel~n changes and thresholds are
defined, documented ,indapproved, and authority and
~@sPonsibil ities ‘O )uch approval are documented;
Assure that timel,y :ecisions are made at the
appropriate managem nt level;
Prohibit retroactive changes to cost and schedule
performance data ~+xept to correct errors;
Designate allowable change processing time frames
consistent with the level of change authority
requested and urgen y required; and
Coordinate baseline replanning actions with the DOE
project manager pri r to the occurrence.