DOE N 430.1, Energy Systems Acquisitions Advisory Board Procedures
Functional areas: Work Processes
The Notice streamlines the Energy Systems Acquisition Advisory Board (ESAAB) process to ensure informed, objective, and documented Strategic and Major System Critical Decision, Baseline Change Proposal, and site selection final decisions. Does not cancel other directives.
Superseded By:
Version history and related documents
Superseded by
A newer version replaces this document.
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
Distribution: Initiated By:
All Departmental Elements Office of Field Management
DOE N 430.1
Approved: 10-28-97
Expires: 10-28-98
U.S. Department of Energy NOTICE
Washington, D.C.
SUBJECT: ENERGY SYSTEMS ACQUISITION ADVISORY BOARD PROCEDURES
1. OBJECTIVES.
a. To streamline the Energy Systems Acquisition Advisory Board (ESAAB) process and
to ensure informed, objective, and documented Strategic and Major System Critical
Decision, Baseline Change Proposal, and site selection final decisions.
b. To implement Office of Management and Budget (OMB) Circular A-109.
c. To address Departmentwide issues and opportunities before committing resources prior
to proceeding to the next acquisition phase in the life cycle of a Strategic System (SS)
or Major System (MS), and to ensure formal, executive decision making consistent with
the Department’s strategic planning and annual budget processes.
d. To integrate DOE fixed asset management processes, found in DOE O 430.1, LIFE-
CYCLE ASSET MANAGEMENT (LCAM), with the ESAAB executive decision-
making process.
e. To incorporate the substance of this Notice, when appropriate, into DOE O 430.1.
2. CANCELLATION. None.
3. APPLICABILITY. This Notice and the ESAAB and ESAAB-equivalent decision-making
processes apply to every program and project designated as an SS or MS. Similar decision
procedures, to be individually tailored by the designated Acquisition Executive to the size
and complexity of the project, apply to projects below the MS level. Naval Nuclear
Propulsion Program Facilities and activities under Executive Order 12344 and Public Law
98-525 are excluded from the provisions of this Notice.
4. REQUIREMENTS.
a. The ESAAB and its related ESAAB decision-making process shall be used to make
final decisions on SS Critical Decisions, Level 0 Baseline Change Proposals, and site
selections.
2 DOE N 430.1
10-28-97
b. ESAAB-equivalent and related procedures shall be developed and used to ensure a
formal, documented, and auditable management process for making final decisions on
delegated SS and MS Critical Decisions, Level 1 Baseline Change Proposals, and site
selections. Similar procedures for project decisions below the MS level shall be
developed by the responsible Acquisition Executive (Program Secretarial Officer, Field
Office Manager, or other official as delegated) and shall be graded, as appropriate, to
reflect the size and complexity of the project.
c. All SS/MS Critical Decisions and site selections shall be approved by the appropriate
Acquisition Executive before proceeding to the next acquisition phase.
d. Requests for a final action from the ESAAB or ESAAB-equivalent Acquisition
Executive regarding Critical Decisions, Baseline Change Proposals, or site selections
shall be coordinated with the ESAAB or its equivalent either through an
ESAAB/ESAAB-equivalent meeting or an Action Memorandum.
e. Either the Secretary, Deputy Secretary, or Under Secretary shall serve as the ESAAB
Acquisition Executive for an SS; the Cognizant Secretarial Officer (CSO) shall serve as
the ESAAB-equivalent Acquisition Executive for MS or delegated SS decisions. Final
decision authority below either level shall be expressly delegated and documented by
the appropriate Acquisition Executive.
f. ESAAB membership shall include the CSOs and the Offices of General Counsel; Chief
Financial Officer; Human Resources; Environment, Safety and Health; Field
Management; Policy; Environmental Management; and Economic Impact and Diversity;
or as identified by the Acquisition Executive.
Section 2
g. ESAAB-equivalent board members shall represent the same functions as the ESAAB.
These members may be from either (1) Headquarters (HQ) functional offices of the
ESAAB member (e.g., the Chief Financial Officer, General Counsel, etc.) or (2) a
similar functional element in the office of the CSO, provided that the HQ functional
office representative is notified prior to an impending decision and is given an
opportunity to participate in the decision-making process.
h. The ESAAB Secretariat shall reside in the Office of Project and Fixed Asset
Management, Field Management.
i. An SS shall be designated based on a Total Project Cost (TPC) of $400 million or
more, and an MS, based on a TPC of $100-$400 million. In addition to TPC, SS and
MS designations shall consider risk factors, international implications, stakeholder
interest, and/or national security. The final decision authority for SS and MS
designations, and for changes in the criteria for designation, is the Acquisition
Executive.
DOE N 430.1 3
10-28-97
j. The SS/MS Critical Decision (CD) points, for which an ESAAB or ESAAB-equivalent
Acquisition Executive final decision is required, are shown in Table 1.
Table 1. SS/MS Critical Decision (CD) Points.
Pre-conceptual Conceptual Execution Operations
Design Phase Phase Phase
•• •• ••
Approve: CD-1 CD-2 CD-3
Mission
Need
Baseline Start Construction
or Remedial Action
•
CD-4
Start Operations or
Complete Cleanup
k. The starting points of phases delineated in LCAM, which include the conceptual design,
execution, and operations phases, define CD-1, CD-2, and CD-4, respectively. (See
DOE O 430.1, Paragraph 6e(7).) CD-3 relates directly to the approximate mid-point of
the execution phase and is typically made between completion of final design and start
of construction, build, or remedial action. The relationship between the Critical
Decisions (requiring ESAAB or ESAAB-equivalent Acquisition Executive approval
before proceeding to the next phase) and the LCAM life cycle phases is illustrated in
Table 1.
l. Final decision authority for an SS CD-3 shall be delegated to the ESAAB-equivalent
Acquisition Executive on the condition that:
• the Secretary (Deputy or Under Secretary) has been notified, with either a copy
to or through the ESAAB Secretariat, of the impending decision not less than 30
or more than 90 days before the scheduled decision; and
• the Secretary (Deputy or Under Secretary) has decided not to require final
decision authority at the ESAAB level.
m. All delegated SS Critical Decisions require a 30-day notification to the ESAAB
Acquisition Executive of an impending intent to approve a Critical Decision.
n. To ensure that an auditable, formal, documented ESAAB-equivalent process is in place,
the office of the ESAAB-equivalent Acquisition Executive shall:
• inform the ESAAB Acquisition Executive, through the ESAAB Secretariat, of all
Critical Decisions, Level 1 Baseline Change Proposals, and site selections and
• provide the appropriate documentation to the ESAAB Secretariat.
4 DOE N 430.1
10-28-97
Section 3
o. An SS Baseline Change Proposal that exceeds Level 0 thresholds requires (1) formal
notification to the ESAAB Secretariat and (2) ESAAB Acquisition Executive approval.
The Acquisition Executive shall determine if a request for ESAAB concurrence is
appropriate based on a recommendation from the ESAAB Secretariat with input from
the program office.
p. SS Level 0 thresholds are defined as: (1) any change of $50 million or more and/or
(2) any change in TPC and/or (3) a 6-month-or-more change in schedule and/or
(4) changes in scope that affect mission need.
q. An Energy Systems Acquisition Review (ESAR) meeting shall be conducted with the
appropriate Acquisition Executive, in lieu of an ESAAB meeting, for any project or
program that does not have all the Critical Decision points illustrated in Table 1.
5. RESPONSIBILITIES. Roles and responsibilities shall be determined using a graded
approach and are generally defined at the discretion of the ESAAB and ESAAB-equivalent
Acquisition Executive and Board member.
a. ESAAB Acquisition Executive.
(1) Chairs the ESAAB/ESAR meeting.
(2) Makes all final decisions for SS Critical Decisions 1, 2, and 4, unless delegated;
selected Critical Decisions CD-3, as noted; Level 0 Baseline Change Proposals;
and SS site selections. All Critical Decisions shall be documented either through
an Action Memorandum or an ESAAB meeting.
(3) Makes the final decision regarding project/program SS/MS designation.
(4) Delegates final decision-making authority.
b. ESAAB Secretariat.
(1) Serves as staff to the ESAAB Acquisition Executive.
(2) Performs duties necessary to implement ESAAB-related responsibilities, including
recommendations regarding SS/MS designation, together with program/field
offices.
(3) Ensures that ESAAB-equivalent procedures for program and field offices, based
on ESAAB Acquisition Executive guidance, are documented and implemented.
(4) Formulates and periodically updates ESAAB guidelines to reflect current senior
management practices.
DOE N 430.1 5
10-28-97
(5) Issues SS/MS list annually.
c. ESAAB Members.
(1) Serve as advisors to the ESAAB Acquisition Executive.
(2) Based on their areas of primary responsibility, provide recommendations or
concurrence/nonconcurrence on final decisions for SS Critical Decisions, Level 0
Baseline Change Proposals, and SS site selections. Because the ESAAB is an
advisory body, nonconcurrence by a member shall not require resolution prior to
forwarding the request to the Acquisition Executive for a decision.
d. Acquisition Proponent. The CSO who seeks Acquisition Executive approval for final
decisions for Critical Decisions, Baseline Change Proposals, and site selections.
e. Cognizant Secretarial Officer (CSO).
(1) Chairs the ESAAB/ESAR-equivalent meeting and makes the final decision for
delegated SS/MS Critical Decisions, Level 1 Baseline Change Proposals, and
delegated site selections.
(2) Develops and documents procedures for the ESAAB-equivalent process, which
should include the following:
(a) a requirement that an ESAAB-equivalent board is appointed for each MS;
(b) a requirement that the ESAAB-equivalent board is appointed for delegated
SS CD-3 in accordance with the conditions stated in 4g;
(c) provisions to ensure that ESAAB members are notified and their concerns
considered prior to the ESAAB-equivalent meeting/Action Memorandum;
and
Section 4
(d) provisions to ensure that documentation is provided to the ESAAB
Secretariat for all delegated SS and all MS Critical Decisions, Level 0 and
Level 1 Baseline Change Proposals, and delegated site selection decisions.
(3) Provides ESAAB Secretariat with annually updated list of all planned and/or
actual Critical Decision, Baseline Change Proposal, and site selection final
decisions.
(4) Provides ESAAB-equivalent procedures to the ESAAB Secretariat for review
and comment.
6 DOE N 430.1
10-28-97
(5) Formally notifies the ESAAB Secretariat when initiating Conceptual Design for
an SS that involves a site selection.
(6) Identifies the Critical Decision approval authority for an SS/MS delegated to a
lower level.
(7) Delegates final decision-making authority.
(8) Ensures that appropriate procedures for project decisions for projects other than
SSs or MSs, graded to reflect the size and reduced risk of such projects, are
addressed for projects for which the CSO holds or delegates decision authority.
6. CONTACTS. Office of Field Management, Office of Project and Fixed Asset Management
(FM-20), Ute Debus, 202-586-9265.
BY ORDER OF THE SECRETARY OF ENERGY:
ARCHER L. DURHAM
Assistant Secretary for
Human Resources and Administration