Section 1
U.S. Department of Energy NOTICE
Washington, D.C.
AVAILABLE ONLINE AT: INITIATED BY:
www.directives.doe.gov Office of Management
DOE N 350.2
Approved: 10-19-05
Expires: 10-19-06
SUBJECT: SUPPLEMENTAL REQUIREMENTS FOR THE USE OF MANAGEMENT AND
OPERATING OR OTHER FACILITY MANAGEMENT CONTRACTOR
EMPLOYEES FOR SERVICES TO DOE IN THE WASHINGTON, D.C., AREA
1. OBJECTIVES. To supplement review and approval requirements in Department of
Energy (DOE) O 350.2A, Use of Management and Operating (M&O) or Other Facility
Management Contractor Employees for Services to DOE in the Washington, D.C., Area,
dated 10-29-03.
2. CANCELLATION. None.
3. APPLICABILITY.
a. DOE Elements. Except for the exclusions in paragraph 3c, this Notice applies to
all DOE elements funding M&O or other facility management contractor
assignments to the Washington, D.C., area. See Attachment 1 for a complete list
of DOE elements to which this Notice is applicable. This Notice automatically
applies to DOE elements created after it is issued.
The NNSA Administrator will assure that NNSA employees and contractors
comply with their respective responsibilities under this Notice.
b. DOE Contractors. While DOE O 350.2A contains a Contractor Requirements
Documents (CRD) and is applicable to DOE contractors, this Notice does not
contain any changes to the CRD and is not applicable to contractors.
c. Exclusions.
(1) the Power Marketing Administrations,
(2) the Office of the Deputy Administrator for Naval Reactors,
(3) assignments under Intergovernmental Personnel Act Mobility Program
Agreements,
(4) work for others agreements, or
(5) such others as may be exempted by the Director, Office of Management,
or the Associate Administrator for Management and Administration,
NNSA.
2 DOE N 350.2
10-19-05
4. REQUIREMENTS.
a. The following requirements address findings of a DOE Inspector General’s
audit and supplement DOE O 350.2A, which will be updated to include the
revisions defined in this Notice.
b. Sponsoring organizations will revise internal organizational review and
approval procedures to ensure compliance with the following supplemental
direction.
5. REASSESSMENTS OF CURRENT CONTRACTOR ASSIGNMENTS. (See
Attachment 2 of this Notice, Assignment Information Standards.)
a. Sponsoring organizations are to take appropriate action to reassess current
assignments as follows.
(1) Assignments that will remain active through FY 2006 will be reassessed
immediately.
(2) Assignments that are not expected to be active throughout FY 2006 do
not require reassessment.
(3) An extension proposed for an assignment to remain active through
FY 2006 must meet the assessment requirements of this Notice prior to
approval.
(4) Any extension that proposes to keep an assignment active in FY 2006
must meet the requirements of this Notice prior to approval.
b. To determine whether the current assignments are justified and supported,
sponsoring organizations will review—
(1) documentation that defines the need for the assignment,
(2) basis for approval,
(3) basis for choosing an M&O or facility management contractor rather than
an alternative source such as a support service contractor,
(4) rationale for and accuracy of the estimated duration of the assignment, and
(5) basis for determining that the assignment costs were reasonable.
c. Following reassessment, sponsoring organizations are to—
(1) notify the Office of Procurement and Assistance Management (OPAM)
and submit documentation of significant findings,
Section 2
DOE N 350.2 3
10-19-05
(2) terminate assignments that do not meet the requirements of this Notice,
and
(3) develop internal cost reassessment procedures for assignments that
exceed one year.
6. SUPPLEMENTAL REQUIREMENTS. Unless otherwise noted, these requirements
apply equally to critical skills staffing and contractor administrative/overhead plans.
Sponsoring organizations must incorporate these requirements in standard review and
approval procedures.
a. Assignment Planning.
(1) Annual critical skills staffing plan submissions must be approved by
heads of DOE elements.
(2) Each submission for a new assignment must include a statement
confirming that an assessment has been completed.
(3) A statement will be submitted only after the sponsoring organization
staffing plan has been assessed and updated to meet requirements of this
Notice.
(4) For an existing assignment initially approved for a period exceeding one
year (not to exceed three years), a submission must confirm one of the
following.
(a) Information in the initial assessment has not changed, and the
original assessment is still valid or
(b) Information in the initial assessment has changed, and the
changes have been assessed.
(5) A submission for extension of an existing assignment beyond the
originally approved assignment period must include a statement
confirming that an assessment has been completed.
b. Cost and Duration of Assignment Implementation Schedule and Restrictions.
(1) Ongoing assignments are to be reassessed annually to determine if there
is a basis for continuing the assignment.
(2) Assessment documentation should be maintained by the sponsoring
organization and at a minimum must satisfy the assignment information
standards (Attachment 2).
4 DOE N 350.2
10-19-05
(3) Sponsoring organizations must establish annual assignment cost
containment target levels that impose target limits on total costs for
organization-sponsored assignments.
(4) Annual critical skills staffing and administrative/overhead staffing plans
will include assignment cost containment target levels for the upcoming
fiscal year.
(5) Reimbursement to assignees will not exceed the organization’s
approved cost containment target levels without written authorization
from the head of the organization.
(6) Reassessment and approval by the head of the sponsoring organization
is required for extending an assignment beyond the three–year limit.
Approval authority may not be delegated.
(7) Reimbursement for assignment to a contractor’s Washington, D.C., staff
office will be limited to salary, benefits, business travel, and if
applicable, and only the assignee’s initial relocation. Once an employee
has been relocated, reimbursement is limited to salary, benefits, and
business travel.
(8) All cost reimbursements should be based on actual costs or reduced per
diem rate as determined by the sponsoring organization.
(9) Using the DOE assignment tracking database, sponsoring organizations
will provide to the OPAM monthly notification that database records
under their purview have been updated and are current as of the date of
the notification.
(10) Assignment and cost restrictions will apply as follows.
(a) An assignment of greater than three years in duration will be
considered a relocation, and assignment reimbursements will
cease at the end of the fiscal year in which the three year limit is
reached, at which point the revised policy will be applied or the
assignee must return to his/her former duty station. (NOTE:
Reduced one time relocation costs and salary adjustment will be
permitted with written approval from the head of the sponsoring
organization.)
Section 3
(b) Assignments of less than three years in duration will continue to
receive reimbursements until the end of the fiscal year during
which the three year limit is reached. Actions should be taken to
DOE N 350.2 5
10-19-05
ensure that the revised policy is applied to the assignment by the
end of the fiscal year in which the three year limit is reached.
(c) Assignments approved after issuance of this Notice will be
subject to the revised policy.
7. RESPONSIBILITIES.
a. Director, Office of Management, or NNSA Associate Administrator for
Management and Administration.
(1) Approves exemptions from requirements of this Notice.
(2) Develops policy changes to be implemented in support of this Notice.
b. Sponsoring Organizations.
(1) Prepare thorough justification for contractor assignments to the
Washington, D.C., area.
(2) Ensure that associated costs are reasonable and comply with
requirements of this Notice.
(3) Before submitting assignment requests, document the following
comprehensive information:
(a) bases for making assignments;
(b) defined periods when the critical skills are needed;
(c) alternatives pursued before requesting contractor assignments;
and
(d) research data confirming that costs are reasonable and comply
this Notice.
(4) Ensure that contractor assignment records in the DOE assignment
tracking database are accurate.
c. Heads of DOE Elements.
(1) Confirm completion of reassessment of current contractor assignments
sponsored by their organizations.
(2) Notify OPAM when reassessments are complete and document
significant findings.
6 DOE N 350.2
10-19-05
(3) Develop internal cost assessment procedures.
(4) Establish annual assignment cost containment target levels for
organization-sponsored assignments.
(5) Approve/authorize assignments and associated costs that exceed
established duration and cost limits.
8. CONTACT. For additional information, contact Richard H. Hopf, Office of
Procurement and Assistance Management, at 202-287-1310.
SAMUEL W. BODMAN
Secretary of Energy
DOE N 350.2 Attachment 1
10-19-05 Page 1 (and Page 2)
DOE ELEMENTSTO WHICH DOE N 350.2 IS APPLICABLE
Office of the Secretary
Departmental Representative to the Defense Nuclear Facilities Safety Board
Energy Information Administration
National Nuclear Security Administration
Office of the Chief Financial Officer
Office of the Chief Information Officer
Office of Civilian Radioactive Waste Management
Office of Congressional and Intergovernmental Affairs
Office of Counterintelligence
Office of Economic Impact and Diversity
Office of Electricity Delivery and Energy Reliability
Office of Energy Efficiency and Renewable Energy
Office of Environment, Safety and Health
Office of Environmental Management
Office of Fossil Energy
Office of General Counsel
Office of Hearings and Appeals
Office of Human Capital Management
Office of Independent Oversight and Performance Assurance
Office of Inspector General
Office of Intelligence
Office of Legacy Management
Office of Management
Office of Nuclear Energy, Science and Technology
Office of Policy and International Affairs
Office of Public Affairs
Office of Science
Office of Security and Safety Performance Assurance
Secretary of Energy Advisory Board
DOE N 350.2 Attachment 2
10-19-05 Page 1
ASSIGNMENT INFORMATION STANDARDS
The following information must be included in all submissions for assigning DOE
management and operating (M&O) or facility contractor personnel to service in the
Washington, D.C., area.
Section 4
1. The employee’s full name, contractor for whom he/she works, and proposed job
classification.
2. Starting and ending dates of the assignment.
3. A detailed statement of work the employee is being assigned to perform. (NOTE:
Assignees are not to be allowed to perform functions set forth at DOE O 350.2A,
paragraph 4e.)
4. The relationship of the employee’s proposed work activity to the sponsoring
organization and to the M&O or facility management contract scope of work and
mission.
5. Is this request an extension of a previous assignment? If yes, describe why the
continued assignment is critical and what significant mutual benefit will be gained by
the sponsoring office and the facility.
6. Is the request proposing to extend the assignment beyond the three-year duration
limitation? If yes, please provide a rationale for continuing this assignment that can be
used to obtain the required approval of the head of the sponsoring DOE program
organization.
7. Explain why the described work cannot be performed at the employee’s regular duty
station.
8. Describe any adverse program impacts if the contractor employee were not assigned to
perform the intended work.
9. Describe why, given the sponsoring organization’s requirements, alternative sources
are not practicable or appropriate.
10. Describe the basis used for determining that assignment costs are reasonable.
11. List the program organizational subcomponent to which the employee will provide
services and the physical location where the employee will be assigned (if at a
contractor’s area office, include the address).
12. Provide the name, organizational code, and phone number of the Federal employee
who will be responsible for ensuring that the employee is in attendance and performing
Attachment 2 DOE N 350.2
Page 2 10-19-05
his/her work as required and for ensuring that the employee’s work activities conform
to the requirements and restrictions of DOE O 350.2A and DOE N 350.2.
13. Confirm that the assignment of this employee is not to replace a support service
contractor that provided the same services previously.
14. Confirm that approval of this employee assignment will not result in your organization
exceeding its Deputy Secretary approved annual assignment allocation. If the request
proposes an assignment that results in exceeding the allocation, has a waiver per DOE
350.2A been approved?
15. Is this assignment being requested to support activities at a DOE M&O contractor
Washington D.C., staff office? If yes, are costs limited to salary and benefits and, if
applicable, a one-time charge for relocation?
16. What is the total monthly and/or annualized cost for this assignment (include all costs
associated with the assignment, salary, benefits, per-diem, etc.)?
17. Are the proposed reimbursement costs consistent with requirements defined in
DOE O 350.2A and this Notice?
18. Does the request propose reimbursement of costs beyond the limitations delineated in
this Notice and if so, has the head of the sponsoring organization obtained the required
approval to exceed the limitations?
19. Do annual costs (other than salary and benefits) exceed estimated total cost based on a
daily per-diem rate for the year? If so, explain why the costs are to exceed the annual
per-diem rates. Specifically, what costs elements cause this to happen and what is the
rationale being used to approve exceeding the per-diem rate?
20. What are the detailed costs elements for this assignment? Cost detail must include but
is not limited to the following:
Section 5
a. salary and benefits (fully burdened, indicate the percentage of indirect costs
burden);
b. personal effects shipment;
c. monthly and annual housing costs;
d. work related travel costs (number of trips, estimated cost per trip, and
destination);
e. personal travel costs for returning to permanent duty station (include the
number and frequency of these trips during a one year period and the costs
estimated for each trip);
DOE N 350.2 Attachment 2
10-19-05 Page 3 (and Page 4)
f. other costs (including, but not necessarily limited to per-diem etc.).*
NOTE: An assignment of greater than three years in duration will be considered a
relocation, and assignment reimbursements will cease at the end of the fiscal year in
which the three year limit is reached, at which point the revised policy will be applied or
the assignee must return to his/her former duty station. (NOTE: Reduced one time
relocation costs and salary adjustment will be permitted with written approval from the
head of the sponsoring organization.)
* Costs in excess of $1,000 per year or 10 percent of the monthly costs (which ever is less) should be detailed and
itemized separately.
OBJECTIVES
APPLICABILITY
DOE Elements
DOE Contractors
Exclusions
REQUIREMENTS
REASSESSMENTS OF CURRENT CONTRACTOR ASSIGNMENTS
SUPPLEMENTAL REQUIREMENTS
Assignment Planning
Cost and Duration of Assignment Implementation Schedule and Restrictions
RESPONSIBILITIES
Director, Office of Management, or NNSA Associate Administrator for Management and Administration
Sponsoring Organizations
Heads of DOE Elements
CONTACT
ATTACHMENT 1. DOE ELEMENTSTO WHICH DOE N 350.2 IS APPLICABLE
ATTACHMENT 2. ASSIGNMENT INFORMATION STANDARDS