DOE G 460.1-1 Att, Packaging and Transportation Attachments
Functional areas: Packaging and Transportation, Safety and Security
Attachments to DOE G 460.1-1. The guide and attachments were combined into one document.
Related From:
Version history and related documents
Related documents
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
ATTACHMENT 1
SELECTED CHRONOLOGICAL MILESTONES CONCERNING DEPARTMENT OF
ENERGY ORDERS 1540.2 AND 5480.3
1985. The Department of Energy (DOE) Order 5480.3 provided for a packaging
certification program where each field office was allowed to perform its own
certifications.
Following a congressional inquiry, the program was changed, and a centralized
certification program was established at DOE Headquarters in 1985 under Defense
Programs (DP). This centralized program was proscribed in DOE 1540.2. Management
of transportation operations was also under DP at this time.
However, DOE 5480.3, which addresses packaging and transportation safety, was not
changed. Therefore, one Order allows certification at the field office level, and one does
not. (A memorandum was issued that clearly removed the authority from the field, but
DOE 5480.3 was never changed.)
1987. Defense Programs requested that the Office of Environment, Safety and Health
(EH) update DOE 5480.3 to reflect the current organizational responsibilities
as well as correct 21 areas where the Order conflicted with the Department of
Transportation/Nuclear Regulatory Commission packaging and transportation regulations
used by DOE (essentially Title 10, Code of Federal Regulations, Part 71, and Title 49,
Code of Federal Regulations, Part 173).
EH was also requested to issue a Notice to the Order clarifying the issues until the Order
could be revised. Although Notices were issued, the Notices have expired without any
revisions to the Order: therefore, the current Order continues to reflect the conflicts.
1989–1992 Reorganizations. The Office of Environmental Restoration and Waste
Management (EM) was formed, and the management of transportation operations
function was transferred from DP to EM. Also, during this period, the certification
function was transferred from DP to EH.
These changes left the Orders in a status where they were not only in conflict with one
another and with the federal regulations, but no longer reflected any correct organizational
structure or responsibilities. For example, both Orders showed DP with the major
programmatic responsibilities for packaging and transportation operations and safety.
1992. EH and EM began a concerted effort to update the Orders. Since previous
reorganizations had transferred major responsibilities from DP and split them between EH
and EM, the Order revision effort involved revamping the existing five transportation and
packaging Orders 1540.1, 1540.1A, 1540.3, 1540.4, and 5480.3 into eight Orders
1540.1A, 1540.2A, 1540.3A, 1540.4A, 1540.5A, 1540.6A, 5480.3R, and 5480.X (onsite
safety).
The intent was to cancel DOE 1540.2 and transfer its safety requirements to DOE
5480.3R, the successor to DOE 5480.3 which was being totally rewritten. DOE 1540.2
was to be reissued as a new Order with a different title and different requirements.
1994. Draft Orders 5480.3R, 5480.X, and 5480.3V (Motor Carrier Safety) were
completed.
1995. As part of the Directives Reduction Initiative, DOE O 460.1 was issued which
contained the surviving portions of the three 1994 Safety Orders. At the same time the
revisions to the 1540 series took place in the form of DOE O 460.2.
1996. DOE O 460.1A replaced DOE O 460.1 when the EH packaging and transportation
safety functions were transferred to EM.
1997. DOE G 460.1-1 is issued.
ATTACHMENT 2
LETTER, JUDITH S. KALETA, CHIEF COUNSEL, U. S. DEPARTMENT OF
Section 2
TRANSPORTATION TO SUSAN H. DENNY, DIRECTOR, TRANSPORTATION
MANAGEMENT DIVISION,
U. S. DEPARTMENT OF ENERGY, APRIL 23, 1991
ATTACHMENT 3
LETTER, E. H. BONEKEMPER, ASSISTANT CHIEF COUNSEL, U. S. DEPARTMENT
OF TRANSPORTATION TO JO ANN WILLIAMS, OFFICE OF CHIEF COUNSEL,
U. S. DEPARTMENT OF ENERGY, APRIL 26, 1993.
ATTACHMENT 4
CAPABILITY OF TEST FACILITIES FOR TESTING TYPE A PACKAGINGS
The following sections provide additional description to Section 4.2.2.4.2, “Test Requirements,” presenting
details on the test facility requirements for the Type A packaging tests and the pass/fail criteria for each
test.
a. Chemical Compatibility Test for Plastic Packagings and Receptacles
A chemical compatibility test for plastic packagings and receptacles designed to transport liquid contents is
required by 49 CFR 173.24(e)(3)(ii). To perform this test, a test facility should be capable of filling three
of the plastic packagings or receptacles to rated capacity with the specific hazardous material to be
transported, storing them at one of the specified test temperatures for the test duration required by
Appendix B to 49 CFR 173, inverting the containers for the required times at the beginning and end of the
storage period, and determining the weight loss of hazardous materials contents during the storage period.
After storage, a test facility should be capable of draining, rinsing, and refilling the containers with water to
their rated capacity, then dropping the containers at ambient temperature from the height required by
Appendix B onto a rigid non-resilient, flat and horizontal surface. A test facility should also be capable of
evaluating the containers for visible evidence of permanent deformation due to vapor pressure buildup or
collapse of walls, deterioration, swelling, crazing, cracking, excessive corrosion, oxidization,
embrittlement, leakage, rupture, or other defects likely to cause premature failure or a hazardous condition.
In addition, a test facility should be capable of calculating the rate of permeation over the test period and
comparing it to the permeation limits of Appendix B.
Alternative procedures or rates of permeation are permitted by 49 CFR 173.24(e)(3)(iii) if they yield a level
of safety equivalent to or greater than that provided by 173.24(e)(3)(ii) and are specifically approved by the
Associate Administrator for Hazardous Materials Safety at DOT. Justification and procedures would have
to be developed by the test facility and submitted to EM. If EM approved the request and the supporting
documentation, EM would then submit the application to DOT.
Each test facility should have procedures which describe the equipment to be used for the required storage,
permeation evaluation, and drop test. The test procedure should describe the test equipment, discuss the
method by which the storage temperature would be maintained, state how the various storage
configurations would be achieved and timed, describe how the rate of permeation would be determined,
document the maximum package size (external dimensions and weight) the apparatus is capable of testing,
describe the means by which the proper drop height is assured, provide the pass/fail criteria for the test, and
list the records to be kept of the testing and results. Any package design which exhibited a rate of
permeation in excess of the permeation limits of Appendix B or any visible evidence of permanent
Section 3
deformation of any of the containers due to vapor pressure build-up or collapse of walls, deterioration,
swelling, crazing, cracking, excessive corrosion, oxidization, embrittlement, leakage, rupture, or other
defects likely to cause premature failure or a hazardous condition as a result of this test would fail this test.
b. Vibration Test
A vibration test for non-bulk packaging is required by 49 CFR 173.24a(a)(5). Non-bulk packaging is
defined in 49 CFR 171.8 as a packaging which has (1) an internal volume of 450 liters (119 gallons) or
less as a receptacle for a liquid; (2) a capacity of 400 kg (882 lb) or less or an internal volume of 450 l
(119 gal) or less as a receptacle for a solid; or (3) a water capacity of 454 kg (1,000 lb) or less as a
receptacle for a gas. The ability to withstand vibration is also required of all Type A packagings in 49
CFR 173.410(f).
To perform the vibration test, a test facility should be capable of placing three sample packagings, filled
and closed as for shipment, on a vibrating platform that has a vertical double-amplitude (peak-to-peak
displacement) of 1 in.. The packages should be constrained horizontally to prevent them from falling off
the platform, but should be left free to move vertically, bounce and rotate. The test should be performed
for 1 hour at a frequency that causes the package to be raised from the vibrating platform to such a degree
that a piece of material of approximately 1.6 mm (0.063 in.) thickness (such as steel strapping or
paperboard) can be passed between the bottom of any package and the platform. Immediately following
the period of vibration, each package should be removed from the platform, turned on its side and observed
for any evidence of leakage. Other methods, at least equally effective, may be used, if approved by the
Associate Administrator for Hazardous Materials Safety.
A test facility should provide documentation describing its vibration test apparatus and demonstrating that
it meets the test requirements specified in 49 CFR 178.608. The vibration test procedure should describe
the vibration test equipment, document the maximum package size (external dimensions and weight) the
apparatus is capable of testing, describe the means by which the proper vibration height is assured, provide
the pass/fail criteria for the test, and list the records to be kept of the testing and results. Any package
design showing evidence of rupture or leakage as a result of this test would fail this test.
c. Reduced Ambient Pressure Test
A reduced ambient pressure test should be conducted to verify the Type A package design requirement
found in 49 CFR 173.412(f). To perform this test, a test facility should be capable of subjecting the
containment system to a reduced ambient pressure of 25 kPa (3.5 lb/in. ) or otherwise creating an2
equivalent pressure differential. A test facility should have procedures which describe the equipment to be
used for the test, the range of packaging sizes which can be tested with this equipment, the way in which
the test will be conducted, the test duration, the pass/fail criteria for the test, and records to be kept of the
testing and results. Any package design showing evidence that the containment system would not retain its
radioactive contents under the conditions of this test would fail this test.
d. Water Spray Test
A water spray test is required for Type A packages by 49 CFR 173.465(b). To perform this test, a test
Section 4
facility should be capable of simulating exposure to rainfall of approximately 5 cm (2 in.) per hour for at
least 1 hour. Water spray should either be applied from four different directions simultaneously, in which
case an interval of 2 hours should elapse before the next test is performed on the packaging, or from each
of four directions consecutively in which case no time should elapse before the next test is performed.
Each test facility should have procedures which describe the equipment to be used for the test, any
calibration which is required to ensure a water spray of 5 cm (2 in.) per hour how the test will be conducted
and timed, the pass/fail criteria for the test, and records to be kept of the testing and results. Any evidence
of the following as a result of this test would constitute failure of this test: (1) loss or dispersal of the
radioactive contents, or (2) any significant increase in the radiation levels recorded or calculated at the
external surfaces of the packaging. Because any radiation level increase would be dependent on the
radioactive package contents, this criterion should be evaluated for specific package contents whenever
damage to the packaging occurs as a result of the test. The test facility should document any decrease in
effectiveness of the shielding in a way that will enable a determination of acceptability to be made by any
package user for any contents. This documentation should be incorporated into the Blue Book.
e. Free Drop Test
A free drop test is required for Type A packages by 49 CFR 173.465(c). For liquids and gases, an
additional test is specified in 49 CFR 173.466(a)(1). To perform these tests, a test facility should be
capable of dropping a packaging onto a flat and horizontal surface of such mass and rigidity that any
increase in its resistance to displacement or deformation upon impact by the specimen would not
significantly increase the damage to the specimen. The test apparatus should be capable of handling both
small and large packagings, and should be capable of performing drops ranging from 0.3 m (1 ft) to 9 m
(30 ft).
Each test facility should provide documentation describing its drop test apparatus and demonstrating that
its target surface meets the mass and rigidity requirements of 49 CFR 173.465(c)(5). The drop test
procedure should document the maximum package size (external dimensions and weight) the apparatus is
capable of testing, the means by which packagings of various sizes and types would be lifted and dropped,
the manner in which a maximum-damage drop orientation would be determined for each packaging, the
means by which the appropriate drop orientation and drop height would be ensured during testing, the
pass/fail criteria for the drop tests, and records to be kept (including photographs and/or videotape) of the
testing and results. Any evidence of the following as a result of this test would constitute failure of this
test: (1) loss or dispersal of the radioactive contents, or (2) any significant increase in the radiation levels
recorded or calculated at the external surfaces of the packaging. Because any radiation level increase
would be dependent on the radioactive package contents, this criterion should be evaluated for specific
package contents whenever damage to the packaging occurs as a result of the test. The test facility should
document any decrease in effectiveness of the shielding in a way that will enable a determination of
Section 5
acceptability to be made by any package user for any contents. This documentation will be incorporated
into the Blue Book.
f. Stacking
A compression test is required for Type A packages by 49 CFR 173.465(d). To perform this test, a test
facility should be capable of applying a compressive load uniformly to two opposite sides of a packaging
specimen, one of which should be the base on which the package would normally stand, for a period of at
least 24 hours.
Each test facility should have procedures describing the apparatus used for compression tests, how the
compression test is performed for various packaging sizes and shapes, how the compressive load is
determined for each packaging, the pass/fail criteria for the test, and records to be kept of the testing and
results. Any evidence of the following as a result of this test would constitute failure of this test: (1) loss
or dispersal of the radioactive contents, or (2) any significant increase in the radiation levels recorded or
calculated at the external surfaces of the packaging. Because any radiation level increase would be
dependent on the radioactive package contents, this criterion should be evaluated for specific package
contents whenever damage to the packaging occurs as a result of the test. The test facility should document
any decrease in effectiveness of the shielding in a way that will enable a determination of acceptability to be
made by any package user for any contents. This documentation will be incorporated into Blue Book.
g. Penetration Test
A penetration test is required for Type A packages by 49 CFR 173.465(e). An additional test for Type A
packagings designed for liquids and gases is specified in 49 CFR 173.466(a)(2). To perform these tests, a
test facility should be capable of evaluating a packaging to determine where it is most vulnerable to
puncture, then placing a packaging specimen on a rigid, flat, horizontal surface that will not move while the
test is being performed and dropping a 3.2 cm (1.3 in.) diam, 6 Kg (13.2 lb) bar with a hemispherical end
onto the most vulnerable part of the packaging, from a distance of 1 m (3.3 ft) or greater and with its
longitudinal axis vertical.
Each test facility should have documented procedures describing the means by which the part of the
packaging most vulnerable to penetration is determined, the way in which the test is conducted, the pass/fail
criteria for the test, and records to be kept (including photographs and/or videotape) of the testing and
results. Any evidence of the following as a result of this test would constitute failure of this test: (1) loss
or dispersal of the radioactive contents, or (2) any significant increase in the radiation levels recorded or
calculated at the external surfaces of the packaging. Because any radiation level increase would be
dependent on the radioactive package contents, this criterion should be evaluated for specific package
contents whenever damage to the packaging occurs as a result of the test. The test facility should document
any decrease in effectiveness of the shielding in a way that will enable a determination of acceptability to be
made by any package user for any contents. This documentation will be incorporated into the Blue Book.
ATTACHMENT 5
QUALITY ASSURANCE FOR CONTRACTOR TESTING FACILITIES
The following criteria pertain to establishing quality assurance for contractor testing facilities and provide
Section 6
additional guidance to Section 4.2.2.5, “Quality Assurance.”
a. Management
DOE 5700.6C specifies four management quality assurance criteria.
Criterion 1—Program. Organizations shall develop, implement, and maintain a written quality
assurance program (QAP). The QAP shall describe the organizational structure, functional
responsibilities, levels of authority, and interfaces for those managing, performing, and assessing
adequacy of work. The QAP shall describe the management system, including planning,
scheduling, and cost control considerations.
Each test facility should operate under a documented QAP. This documentation should be provided to EM
for review as part of the approval process for the test facility.
Criterion 2—Personnel Training and Qualification. Personnel shall be trained and qualified to
ensure they are capable of performing their assigned work. Personnel shall be provided continuing
training to ensure that job proficiency is maintained.
The various review and testing tasks which should be performed as part of this program should be defined.
Minimum personnel qualifications should then be established for each of these tasks. Personnel reviewing
the applicant's documentation and evaluating test results should be technically qualified to do so,
particularly in mechanical design areas such as lifting and tie down requirements. Personnel determining
worst-case drop orientations should also be qualified to do so. Personnel performing the tests should be
trained in the test requirements and test procedures. Documentation of the defined tasks and qualification
requirements for each should be provided to EM for review as part of the approval process for each test
facility.
A procedure for qualifying personnel to perform the defined tasks should also be provided to EM. The
procedure should include establishment and maintenance of training records, where appropriate.
Criterion 3—Quality Improvement. The organization shall establish and implement processes to
detect and prevent quality problems and to ensure quality improvement. Items and processes that
do not meet established requirements shall be identified, controlled, and corrected. Correction shall
include identifying the causes of problems and preventing recurrence. Item reliability, process
implementation, and other quality-related information shall be reviewed and the data analyzed to
identify items and processes needing improvement.
Each test facility should provide documentation demonstrating that the test facility organization has
established quality improvement processes and that the test facility operates under these established
processes. This documentation should be provided to EM for review as part of the approval process for the
test facility.
Criterion 4—Documents and Records. Documents shall be prepared, reviewed, approved, issued,
used, and revised to prescribe processes, specify requirements, or establish design. Records shall
be specified, prepared, reviewed, approved, and maintained.
As discussed in Section 4, each test facility is required to have a set of procedures fully documenting the
way in which it processes an application for a Type A package evaluation. The procedures should cover
both the review of the applicant's documentation and the testing which is performed on the packaging
subsequent to the documentation review. These procedures should be provided to EM for review as part of
Section 7
the approval process for the test facility.
The procedures should be prepared, reviewed, approved, issued, used, and revised under a formal document
control system. Documentation of the formal document control system should also be provided to EM for
review as part of the approval process for the test facility.
Each procedure should document the records to be maintained as a result of implementation of that
procedure. The records should provide adequate detail to ensure that the procedure was correctly
implemented and the proper conclusions regarding the packaging were reached. For some tests (e.g., the
drop tests) a visual record (photographs and/or videotape) may be appropriate. Appropriate records
include:
a. applicant's design packet;
b. documentation of review of applicant's design packet, including comment resolution where appropriate;
c. records of the testing and results, including photographs and/or videotape where appropriate;
d. documentation developed by test facility of testing and results, including Blue Book changes where
appropriate; and
e. records of review and approval of the documentation by EM.
Records to be maintained should also include documentation of the test facility program and procedures,
including:
a. documentation of procedures and procedure revisions;
b. documentation of equipment qualification and maintenance, where appropriate;
c. documentation of review and approval of test facility procedures and equipment by EM;
d. task descriptions; and
e. personnel qualifications for individuals performing defined tasks.
Records should be maintained under a formal records maintenance system covering retention, protection,
preservation, traceability, accountability, and retrievableness of records. Documentation of the records
maintenance system for the test facility organization should be provided to EM for review as part of the
approval process for the test facility.
b. Performance
DOE 5700.6C specifies four performance quality assurance criteria.
Criterion 5—Work Processes. Work shall be performed to established technical standards and
administrative controls. Work shall be performed under controlled conditions using approved
instructions, procedures, or other appropriate means. Items shall be identified and controlled to ensure
their proper use. Items shall be maintained to prevent their damage, loss, or deterioration. Equipment
used for process monitoring or data collection shall be calibrated and maintained.
Section 4.2.2.4 of this document discusses the content expected in procedures describing work to be
performed under this program.
Criterion 6—Design. Items and processes shall be designed using sound engineering/scientific
principles and appropriate standards. Design work, including changes, shall incorporate applicable
requirements and design bases. Design interfaces shall be identified and controlled. The adequacy
of design products shall be verified or validated by individuals or groups other than those who
performed the work. Verification and validation work shall be completed before approval and
implementation of the design.
This program performs design verification activities rather than design work. As such, most of the
elements of this criterion do not apply. Careful documentation of the design being reviewed, including
documentation of any design changes resulting from the review, should be assured so that verification of
Section 8
the correct design is established. This program already ensures that verification and validation of the
package design are completed before the packaging is approved for use. Independence of personnel
performing design verification from package design should also be ensured. Documentation should be
provided to EM demonstrating that (1) the test facility will ensure that verification of the correct design is
established and (2) personnel performing the design verification activities are independent of package
design efforts. This documentation should be provided to EM for review as part of the approval process
for the test facility.
Criterion 7—Procurement. The organization shall ensure that procured items and services meet
established requirements and perform as specified. Prospective suppliers shall be evaluated and
selected on the basis of specified criteria. The organization shall ensure that approved suppliers
can continue to provide acceptable items and services.
This criterion should be applied to the procurement of test apparatus and any other items procured in
support of this program. Each test facility organization should have a documented procurement program to
accomplish this. Documentation of the procurement program for the test facility organization should be
provided to EM for review as part of the approval process for the test facility.
Criterion 8—Inspection and Acceptance Testing. Inspection and acceptance testing of specified items
and processes shall be conducted using established acceptance and performance criteria. Equipment
used for inspections and tests shall be calibrated and maintained.
Inspection and acceptance testing of test apparatus should be specifically addressed in the test procedures,
where appropriate.
c. Assessment
DOE 5700.6C specifies two assessment quality assurance criteria.
Criterion 9—Management Assessment. Management at all levels shall periodically assess the
integrated quality assurance program and its performance. Problems that hinder the organization
from achieving its objectives shall be identified and corrected.
Each test facility should provide documentation demonstrating that the test facility organization has an
established management assessment program, and that the test facility operates within this management
assessment program. This documentation should be provided to EM for review as part of the approval
process for the test facility.
Criterion 10—Independent Assessment. Planned and periodic independent assessments shall be
conducted to measure item quality and process effectiveness and to promote improvement. The
organization performing independent assessments shall have sufficient authority and freedom from
the line organization to carry out its responsibilities. Persons conducting independent assessments
shall be technically qualified and knowledgeable in the areas assessed.
Each test facility should provide documentation demonstrating that the test facility organization has an
established independent assessment program, and that the test facility operates within this independent
assessment program. This documentation should be provided to EM for review as part of the approval
process for the test facility.