DOE G 435.1-1, Implementation Guide for Use with DOE M 435.1-1
Functional areas: Environmental Management, Radioactive Waste Management
The objective of the guide is to ensure that responsible individuals understand what is necessary and acceptable for implementing the requirements of DOE M 435.1-1. Separate chapters have been combined to form a single document. Individual chapters have been archived.
Version history and related documents
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
DOE G 435.1-1
Approved: 7-09-99
IMPLEMENTATION
GUIDE
for use with DOE M 435.1-1
U.S. DEPARTMENT OF ENERGY
Distribution: Initiated By:
All Departmental Elements Office of Environmental Management
(This page intentionally left blank.)
i DOE G 435.1-1
7-09-99
IMPLEMENTATION GUIDE FOR USE WITH
DOE M 435.1-1, RADIOACTIVE WASTE MANAGEMENT MANUAL
INTRODUCTION
This guide was developed to aid in implementing the requirements of DOE M 435.1-1,
Radioactive Waste Management Manual. The guide has the same format as the Manual and is
divided into four chapters.
Chapter I, General Requirements and Responsibilities
Chapter II, High-Level Waste Requirements
Chapter III, Transuranic Waste Requirements
Chapter IV, Low-Level Waste Requirements
The material presented in this guide provides suggestions and acceptable ways of implementing
DOE M 435.1-1 and should not be viewed as additional or mandatory requirements. The
objective of the guide is to ensure that responsible individuals understand what is necessary and
acceptable for implementing the requirements of DOE M 435.1-1. For each requirement in DOE
M 435.1-1, the guide provides:
C The objective of the requirement;
C Discussion of the technical, management, and administrative aspects covered by the
requirement;
C Principles, practices, and methods for implementing the requirement, including examples;
C Performance measures for evaluating implementation of the requirement; and
C Supplemental references which may be consulted for more detailed information related to
the requirement.
The guide aids in understanding what is necessary to attain compliance, facilitates effective and
efficient implementation of the requirements, and offers acceptable ways to implement the
requirement. As noted, the guide provides suggestions and acceptable ways of implementing the
requirements, and is not mandatory. Provisions in the guide should not be construed as
requirements. The approaches presented in the guidance are not the only acceptable ways of
complying with any given requirement. Alternate methods that satisfy the requirements of DOE
O 435.1 and DOE M 435.1-1 also are acceptable. A rationale and basis for the approaches
identified in the guide has been provided and no further basis is required to implement the
approaches outlined in the guide. Any implementation method selected must ensure an adequate
level of safety commensurate with the hazards associated with the work. The implementation
method selected must be consistent with the radioactive waste management basis.
Introduction
ii DOE G 435.1-1
7-09-99
Situation-specific attributes and application of the graded approach should always be considered
in applying the information contained in this guide. Activities with greater potential consequences
or hazards may require more rigor or effort to implement the requirements of DOE M 435.1-1,
Radioactive Waste Management Manual.
Wherever possible, existing processes, programs, and documentation should be considered as
possible routes to complying with the requirements of DOE M 435.1-1. Existing processes and
programs generally provide mechanisms for demonstrating compliance and providing auditable
records which will also meet the requirements of DOE M 435.1-1. Therefore, it should not be
necessary to repeat or recreate programs into which the DOE M 435.1-1 requirements can be
integrated.
Section 2
Chapter I, General Requirements and Responsibilities, provides guidance on DOE management
responsibilities and requirements that are applicable to the management of all DOE radioactive
waste types. Chapter II, High-Level Waste Requirements; Chapter III, Transuranic Waste
Requirements; and Chapter IV, Low-Level Waste Requirements, provide guidance on waste-type
specific requirements to be used in conjunction with the guidance on General Requirements and
Responsibilities.
Other requirements and DOE directives are referenced in DOE M 435.1-1, Radioactive Waste
Management Manual, because their applicability to radioactive waste management facilities,
operations, and activities was identified through a hazards analysis as necessary for protection of
workers, the public, or the environment. It is understood and expected that requirements of this
Manual may be satisfied by compliance with other requirements.
Paragraph (4) of the Introduction to the Radioactive Waste Management Manual, DOE M 435.1
1, states that any of the requirements in the Manual may be waived or modified through
application of a DOE-approved requirements tailoring process, such as the “Necessary and
Sufficient Closure Process” in DOE P 450.3 and DOE M 450.3-1 and DOE P 450.4, Safety
Management System Policy, the applicable or relevant and appropriate requirements identification
process for actions taken pursuant to the Department’s CERCLA authorities, or by an exemption
processed in accordance with the requirements of DOE M 251.1-1A, Directives System Manual.
The series of manuals and implementation guides under DOE P 450.4 contain requirements and
guidance for implementing the evaluation processes mentioned above that would allow a waiver
or modification to any of the individual DOE M 435.1-1 requirements. Chapter VII of DOE M
251.1-1A provides the requirements, including roles and responsibilities, for exempting a DOE
site or facility from any of the DOE M 435.1-1 requirements.
When the exemption process of DOE M 251.1-1A is used, the policies of the integrated Safety
Management System must still be followed, and the overall effect of modifications and
exemptions to individual requirements should be evaluated and a determination made that they are
Introduction
iii DOE G 435.1-1
7-09-99
not detrimental to the objectives of DOE O 435.1 and DOE M 435.1-1 for the protection of the
public, workers, and the environment.
Paragraph (4) of the Introduction to the Radioactive Waste Management Manual, DOE M 435.1
1, also states that all DOE entities shall be in compliance with this directive within one year of
issuance. Compliance is defined as implementing the requirements or an approved
implementation or corrective action plan. If compliance cannot be achieved within one year, the
Field Element Manager must request approval from the cognizant Program Secretarial Officer to
extend the compliance date to no later than October 1, 2001. The purpose of this requirement is
to encourage DOE sites and programs to implement the requirements of the Order and Manual as
soon as possible, to ensure that a plan is developed for implementing requirements that will take
longer than one year to implement, and to ensure that the cognizant Program Secretarial Officer is
aware of those requirements for which compliance cannot be achieved in one year. Field
Elements need to evaluate the state of readiness of facilities, operations, and activities under their
authority for compliance with the revised radioactive waste management requirements, and invoke
a systematic process for achieving full implementation as soon as possible.
Section 3
Implementation or corrective action plans establish a commitment and strategy for how sites will
implement the requirements by October 1, 2001, and should include objectives and milestones,
including dates, for implementing the requirements on a site or facility basis.
Example 1: A site implementation plan addresses the requirement for Radioactive Waste
Management Basis (RWMB) in one of two ways. For facilities with an existing
Authorization Basis, the strategy for implementing the RWMB requirement is to review
the Authorization Basis to determine whether it sufficiently covers the requirements
needed for a RWMB, then issue a blanket RWMB for those facilities. For facilities which
do not have an Authorization Basis, implementation of the RWMB will follow
implementation of Waste Acceptance Requirements (for facilities receiving waste) and
Waste Generator Requirements (for facilities generating waste).
Example 2: A site develops an implementation plan for section III.L.(1)(b) “Vents or
other mechanisms....” The site has 1,000 drums of transuranic waste in storage. Two
hundred drums have been prepared to the Waste Acceptance Criteria for the Waste
Isolation Pilot Plant (WIPP WAC) including having filter vents installed. Of the
remaining 800 drums which are not vented, 500 drums are stored in air support storage
buildings awaiting certification, and 300 drums are retrievably stored in earthen-covered
berms. The site prepares an implementation plan for this requirement which summarizes
how the remaining 800 drums will meet the requirement based on existing plans for
management of this waste. The plan states that the 500 drums in the air support storage
buildings are scheduled to be prepared to WIPP WAC during the following two years.
Filter vents will be installed during the certification process. The site has plans to begin
Introduction
iv DOE G 435.1-1
7-09-99
retrieving the bermed waste in five years. Filter vents will be installed on the drums as
they are removed from the berms. The implementation plan shows the schedule and
notes that although the requirement will be implemented outside of the three year
implementation period, the requirement allow for vents to be installed on existing waste
in storage as soon as practical (i.e., the next time the waste is actively managed).
Introduction
v DOE G 435.1-1
7-09-99
TABLE OF CONTENTS
CHAPTER I - GENERAL REQUIREMENTS AND RESPONSIBILITIES . . . . . . . . . . . . . I-1
1. REQUIREMENTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-1
A. Delegation of Authority . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-1
B. Use of Guidance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-3
C. Radioactive Waste Management . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-7
D. Analysis of Environmental Impacts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-13
E. Requirements of Other Regulations and DOE Directives . . . . . . . . . . . . . . . . I-15
(1) Analysis of Operations Information . . . . . . . . . . . . . . . . . . . . . . . . . . I-17
(2) Classified Waste . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-18
(3) Conduct of Operations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-18
(4) Criticality Safety . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-19
Section 4
(5) Emergency Management Program . . . . . . . . . . . . . . . . . . . . . . . . . . . I-19
(6) Environmental and Occurrence Reporting . . . . . . . . . . . . . . . . . . . . . I-19
(7) Environmental Monitoring . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-20
(8) Hazard Analysis Documentation and Authorization Basis . . . . . . . . . I-21
(9) Life-Cycle Asset Management . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-22
(10) Mixed Waste . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-23
(11) Packaging and Transportation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-23
(12) Quality Assurance Program . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-24
(13) Radiation Protection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-24
(14) Records Management . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-25
(15) Release of Waste Containing Residual Radioactive Material . . . . . . . I-26
(16) Safeguards and Security . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-27
(17) Safety Management System . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-27
(18) Site-Evaluation and Facility Design . . . . . . . . . . . . . . . . . . . . . . . . . . I-28
(19) Training and Qualification . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-29
(20) Waste Minimization and Pollution Prevention . . . . . . . . . . . . . . . . . . I-29
(21) Worker Protection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-30
2. RESPONSIBILITIES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-32
A. Program Secretarial Officers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-32
B. Assistant Secretary for Environmental Management . . . . . . . . . . . . . . . . . . . I-35
(1) Complex-Wide Radioactive Waste Management Programs . . . . . . . . I-35
(2) Changes to Regulations and DOE Directives . . . . . . . . . . . . . . . . . . . I-39
C. Assistant Secretary for Environment, Safety, and Health . . . . . . . . . . . . . . . . I-42
D. Deputy Assistant Secretary for Waste Management . . . . . . . . . . . . . . . . . . . I-43
(1) Complex-Wide Radioactive Waste Management Program Plans . . . . I-44
(2) Waste Management Data System . . . . . . . . . . . . . . . . . . . . . . . . . . . I-53
vivi DOE G 435.1-1DOE G 435.1-1
7-09-997-09-99
TABLE OF CONTENTS (cont.)
E. Deputy Assistant Secretaries for Waste Management and Environmental
Restoration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-55
(1) Disposal . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-55
(2) Site Closure Plans . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-65
F. Field Element Managers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-72
(1) Site-Wide Radioactive Waste Management Programs . . . . . . . . . . . . I-72
(2) Radioactive Waste Management Basis . . . . . . . . . . . . . . . . . . . . . . . I-84
(3) Waste Minimization and Pollution Prevention . . . . . . . . . . . . . . . . . I-101
(4) Approval of Exemptions for Use of Non-DOE Facilities . . . . . . . . . I-103
Section 5
(5) Environmental Restoration, Decommissioning, and Other Cleanup Waste
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-111
(6) Radioactive Waste Acceptance Requirements . . . . . . . . . . . . . . . . . I-128
(7) Radioactive Waste Generator Requirements . . . . . . . . . . . . . . . . . . I-134
(8) Closure Plans . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-141
(9) Defense-In-Depth . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-146
(10) Oversight . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-148
(11) Training and Qualification . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-151
(12) As Low As Reasonably Achievable (ALARA) . . . . . . . . . . . . . . . . . I-153
(13) Storage . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-156
(14) Treatment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-159
(15) Disposal . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-161
(16) Monitoring . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-166
(17) Material and Waste Declassification for Waste Management . . . . . . I-170
(18) Waste Incidental to Reprocessing . . . . . . . . . . . . . . . . . . . . . . . . . . I-174
(19) Waste with No Identified Path to Disposal . . . . . . . . . . . . . . . . . . . I-179
(20) Corrective Actions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-188
G. All Personnel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-190
(1) Problem Identification . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-190
(2) Shutdown or Curtailment of Activities . . . . . . . . . . . . . . . . . . . . . . I-191
CHAPTER II - HIGH-LEVEL WASTE REQUIREMENTS . . . . . . . . . . . . . . . . . . . . . . . . . II-1
A. Definition of High-Level Waste . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-1
B. Waste Incidental to Reprocessing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-13
(1) Citation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-13
(2) Evaluation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-13
C. Management of Specific Wastes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-34
(1) Mixed High-Level Waste . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-34
(2) TSCA-Regulated Waste . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-34
D. Complex-Wide High-Level Waste Management Program . . . . . . . . . . . . . . . II-38
vii DOE G 435.1-1
7-09-99
TABLE OF CONTENTS (cont.)
E. Site-Wide High-Level Waste Management Program . . . . . . . . . . . . . . . . . . . II-39
F. Radioactive Waste Management Basis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-43
(1) Generators . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-43
(2) Pretreatment and Treatment Facilities . . . . . . . . . . . . . . . . . . . . . . . . II-43
Section 6
(3) Storage Facilities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-43
G. Quality Assurance Program . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-48
(1) Product Quality . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-48
(2) Audits and Assessments . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-48
H. Contingency Actions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-51
(1) Contingency Storage . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-51
(2) Transfer Equipment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-51
I. Corrective Actions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-56
(1) Order Compliance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-56
(2) Operations Curtailment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-58
J. Waste Acceptance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-61
(1) Technical and Administrative . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-61
(2) Evaluation and Acceptance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-68
K. Waste Generation Planning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-72
(1) Life-Cycle Planning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-72
(2) Waste With No Identified Path to Disposal . . . . . . . . . . . . . . . . . . . . II-72
L. Waste Characterization . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-78
(1) Data Quality Objectives . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-85
(2) Minimum Waste Characterization . . . . . . . . . . . . . . . . . . . . . . . . . . . II-90
(3) Hazardous Characteristics . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-93
M. Waste Certification . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-94
(1) Certification Program . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-99
(2) Certification Before Transfer . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-103
(3) Maintaining Certification . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-104
N. Waste Transfer . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-107
(1) Authorization . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-107
(2) Data . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-109
(3) Records and Transfer Reporting . . . . . . . . . . . . . . . . . . . . . . . . . . . II-112
O. Packaging and Transportation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-116
(1) Canistered Waste Form . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-116
P. Site Evaluation and Facility Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-123
(1) Site Evaluation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-123
(2) Facility Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-128
Section 7
Q. Storage . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-164
(1) Operation of Confinement Systems . . . . . . . . . . . . . . . . . . . . . . . . . II-164
(2) Structural Integrity Program . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-166
viiiviii DOE G 435.1-1DOE G 435.1-1
7-09-997-09-99
TABLE OF CONTENTS (cont.)
(3) Canistered Waste Form Storage . . . . . . . . . . . . . . . . . . . . . . . . . . . II-175
R. Treatment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-178
S. Disposal . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-180
T. Monitoring . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-186
U. Closure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-191
(1) Decommissioning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-191
(2) CERCLA Process . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-191
(3) Closure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-191
V. Specific Operations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-207
(1) Operation of Lifting Devices . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-207
(2) Operation of Facilities for Receipt and Retrieval of High-Level Waste
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II-208
CHAPTER III - TRANSURANIC WASTE REQUIREMENTS . . . . . . . . . . . . . . . . . . . . . III-1
A. Definition of Transuranic Waste . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-1
B. Management of Specific Wastes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-7
(1) Mixed Transuranic Waste . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-7
(2) TSCA-Regulated Waste . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-7
(3) Pre-1970 Transuranic Waste . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-7
C. Complex-Wide Transuranic Waste Management Program . . . . . . . . . . . . . . III-13
D. Radioactive Waste Management Basis . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-14
(1) Generators . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-14
(2) Treatment Facilities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-14
(3) Storage Facilities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-14
(4) Disposal Facilities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-14
E. Contingency Actions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-20
(1) Contingency Storage . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-20
(2) Transfer Equipment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-20
F. Corrective Actions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-24
(1) Order Compliance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-24
Section 8
(2) Operations Curtailment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-26
G. Waste Acceptance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-29
(1) Technical and Administrative . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-29
(2) Evaluation and Acceptance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-39
H. Waste Generation Planning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-43
(1) Life-Cycle Planning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-43
(2) Waste With No Identified Path to Disposal . . . . . . . . . . . . . . . . . . . III-47
I. Waste Characterization . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-54
(1) Data Quality Objectives . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-60
ix DOE G 435.1-1
7-09-99
TABLE OF CONTENTS (cont.)
(2) Minimum Waste Characterization . . . . . . . . . . . . . . . . . . . . . . . . . . III-64
J. Waste Certification . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-69
(1) Certification Program . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-74
(2) Certification Before Transfer . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-77
(3) Maintaining Certification . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-79
K. Waste Transfer . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-84
(1) Authorization . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-87
(2) Data . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-90
L. Packaging and Transportation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-95
(1) Packaging . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-95
(2) Transportation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-105
M. Site Evaluation and Facility Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-109
(1) Site Evaluation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-109
(2) Facility Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-113
N. Storage . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-130
(1) Storage Prohibitions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-130
(2) Storage Integrity . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-131
(3) Container Inspection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-133
(4) Retrievable Earthen-Covered Storage . . . . . . . . . . . . . . . . . . . . . . III-137
O. Treatment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-142
P. Disposal . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-145
Q. Monitoring . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-150
(1) All Waste Facilities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-150
Section 9
(2) Stored Wastes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III-152
(3) Liquid Waste Storage Facilities . . . . . . . . . . . . . . . . . . . . . . . . . . . III-154
CHAPTER IV - LOW-LEVEL WASTE REQUIREMENTS . . . . . . . . . . . . . . . . . . . . . . . . IV-1
A. Definition of Low-Level Waste . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-1
B. Management of Specific Wastes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-7
(1) Mixed Low-Level Waste . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-7
(2) TSCA-Regulated Waste . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-7
(3) Accelerator-Produced Waste . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-7
(4) 11e.(2) and Naturally Occurring Radioactive Material . . . . . . . . . . . . IV-7
C. Complex-Wide Low-Level Waste Management Program . . . . . . . . . . . . . . IV-15
D. Radioactive Waste Management Basis . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-18
(1) Generators . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-18
(2) Treatment Facilities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-18
(3) Storage Facilities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-18
(4) Disposal Facilities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-18
xx DOE G 435.1-1DOE G 435.1-1
7-09-997-09-99
TABLE OF CONTENTS (cont.)
E. Contingency Actions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-23
(1) Contingency Storage . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-23
(2) Transfer Equipment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-23
F. Corrective Actions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-28
(1) Order Compliance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-28
(2) Operations Curtailment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-32
G. Waste Acceptance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-35
(1) Technical and Administrative . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-35
(2) Evaluation and Acceptance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-49
H. Waste Generation Planning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-53
(1) Life-Cycle Planning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-53
(2) Waste With No Identified Path to Disposal . . . . . . . . . . . . . . . . . . . IV-58
I. Waste Characterization . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-70
(1) Data Quality Objectives . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-76
(2) Minimum Waste Characterization . . . . . . . . . . . . . . . . . . . . . . . . . . IV-80
J. Waste Certification . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-84
(1) Certification Program . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-89
(2) Certification Before Transfer . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-92
Section 10
(3) Maintaining Certification . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-93
K. Waste Transfer . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-97
(1) Authorization . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-100
(2) Data . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-103
L. Packaging and Transportation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-108
(1) Packaging . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-108
(2) Transportation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-114
M. Site Evaluation and Facility Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-118
(1) Site Evaluation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-118
(2) Low-Level Waste Treatment and Storage Facility Design . . . . . . . IV-134
(3) Low-Level Waste Disposal Facility Design . . . . . . . . . . . . . . . . . . IV-151
N. Storage and Staging . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-161
(1) Storage Prohibitions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-161
(2) Storage Limit . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-162
(3) Storage Integrity . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-168
(4) Waste Characterization for Storage . . . . . . . . . . . . . . . . . . . . . . . . IV-170
(5) Container Inspection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-173
(6) Storage Management . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-176
(7) Staging . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-178
O. Treatment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-181
P. Disposal . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-185
(1) Performance Objectives . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-185
DOE G 435.1-1 xi (and xii)
7-09-99
TABLE OF CONTENTS (cont.)
(2) Performance Assessment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-188
(3) Composite Analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-199
(4) Performance Assessment and Composite Analysis Maintenance . . . IV-202
(5) Disposal Authorization . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-206
(6) Disposal Facility Operations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-210
(7) Alternate Requirements for Low-Level Waste Disposal Facility Design and
Operation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-219
Q. Closure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-222
(1) Disposal Facility Closure Plans . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-222
(2) Disposal Facility Closure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-232
R. Monitoring . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-238
Section 11
(1) All Waste Facilities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-238
(2) Liquid Waste Storage Facilities . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-241
(3) Disposal Facilities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV-244
APPENDIX A – TECHNICAL BASIS FOR DOE O 435.1 . . . . . . . . . . . . . . . . . . . . . . . . . . A-1
Introduction
(This page intentionally left blank.)
IMPLEMENTATION
GUIDE
for use with DOE M 435.1-1
Chapter I
General Responsibilities and Requirements
(This page intentionally left blank.)
I-1 DOE G 435.1-1
7-09-99
I. 1.A. Delegation of Authority.
Managers charged with responsibilities within this Manual may delegate authority
for these tasks to another manager. All delegations of authority shall be
documented.
Objective:
The objective of this requirement is to provide DOE managers with the needed flexibility in
managing programs while retaining DOE responsibility and ensuring traceability of authority.
Discussion:
Delegation of authority is authorizing another DOE manager to perform the task for the manager
who has been assigned the responsibility in a DOE Directive. The responsibility for ensuring that
the task is performed remains with the DOE manager charged with the responsibility in the DOE
Directive. Requiring that delegation be to another DOE manager retains the elements of DOE
responsibility, accountability, and attention. DOE attention provides a mechanism for assigning
resources necessary for successful execution of the task. Requiring documentation ensures the
traceability of authority.
The delegation of authority can be made to any DOE manager at any level by the DOE manager
charged with the responsibility in DOE M 435.1-1. Any managers who fall in the management
chain between the manager who has been assigned the responsibility in DOE M 435.1-1 and the
manager who is charged the responsibility for the task have no responsibility for the task
themselves but should be notified of the delegation by a copy of the memorandum of record. The
delegation of authority can be revoked at any time and delegated to a different DOE manager by
the DOE manager charged with the responsibility in DOE M 435.1-1. The manager delegated the
authority for a task may further delegate this authority to another manager but must notify the
DOE manager charged with the responsibility of this re-delegation, with a copy to other
managers, as appropriate for their information. The performance of tasks by other DOE staff or
contractors can be assigned by the DOE manager with the authority to perform a task without
affecting the delegation of authority. The manager charged with the responsibility in DOE M
435.1-1 needs to ensure the delegation of authority is successful. This can be achieved by
periodically discussing the task with the manager to whom the authority was delegated, or
requiring a written report from that manager describing how the task is being implemented.
The delegation of authority can be indefinite or for a specific time period, but the selected time
period should be clearly identified in the documentation of the delegation of authority. The
documentation of the delegation of authority can be accomplished by a memorandum of record
which should be maintained as an auditable record. The documentation of the delegation of
Chapter I - General Requirements and Responsibilities
I-2 DOE G 435.1-1
7-09-99
Section 12
authority should clearly describe the authority being delegated; identify any terminating
condition(s) or a termination date of the delegation, as appropriate; identify the DOE manager to
whom authority is being delegated; contain a mechanism for acknowledgment of receipt; and be
managed as an auditable record as long as the delegation is in effect. A delegation of authority
that contains these elements should be considered complete and meets the Manual requirement.
Example: The Field Element Manager is assigned responsibility in DOE M 435.1-1 for
ensuring development of, review, approval, and implementation of closure plans for low-
level waste disposal facilities. The Field Element Manager delegates authority for these
responsibilities to the DOE Radioactive Waste Manager at the site in a memorandum.
The Radioactive Waste Manager does not report directly to the Field Element Manager
but is two levels removed in the management chain. The memorandum states that the
Radioactive Waste Manager is responsible for ensuring development of, review,
approval, and implementation of closure plans for all of the site’s low-level waste
disposal facilities. The memorandum establishes the effective date as the date that the
Radioactive Waste Manager acknowledges receipt of the memorandum and states that
this delegation is in effect until revoked by the Field Element Manager. The manager
who falls in the management chain between the manager charged with the responsibility
and the one who is delegated the authority is copied in the memorandum. The
memorandum is identified as a quality assurance record that must be maintained in
accordance with the Quality Assurance Program’s record keeping requirements.
Delegations of authority should be reviewed whenever a change in DOE management takes place
(e.g., there is a reorganization or a manager leaves). These reviews should evaluate the status of
the delegation of authority to establish its continued validity over time or under the changed
circumstances.
Compliance with this requirement is demonstrated if all DOE managers who have been delegated
authority for DOE M 435.1-1 have documentation that describes the authority being delegated,
identifies the time period for the delegation, and contains an acknowledgment of the receipt of the
delegation of authority. This documentation must be maintained as an auditable record.
Supplemental References:
1. DOE, 1997. Manual of Safety Management Functions, Responsibilities, and Authorities,
DOE M 411.1-1, U.S. Department of Energy, Washington, D.C., October 8, 1997.
Chapter I - General Requirements and Responsibilities
I-3 DOE G 435.1-1
7-09-99
I. 1.B. Use of Guidance.
Additional information supporting the requirements in this Manual is contained in
the Implementation Guide for use with DOE M 435.1-1, Radioactive Waste
Management Manual. This Guide, DOE G 435.1-1, Implementation Guide for DOE
M 435.1-1, shall be reviewed when implementing the requirements of this Manual.
The Guide provides additional information and acceptable methods for meeting the
requirements. Other methods may be used but must ensure an adequate level of
safety commensurate with the hazards associated with the work and be consistent
with the radioactive waste management basis.
Objective:
Section 13
The objective of this requirement is to ensure that individuals responsible for DOE radioactive
waste management operations, facilities, and activities understand what is necessary and
acceptable for implementing the requirements of DOE O 435.1, Radioactive Waste Management,
and DOE M 435.1-1, Radioactive Waste Management Manual. By understanding the objective
of these requirements, individuals responsible for managing radioactive waste should be able to
take the appropriate action even in situations not previously discussed in the requirements.
Discussion:
The Implementation Guide for DOE M 435.1-1, DOE G 435.1-1, serves as a tool to assist
personnel in gaining a comprehensive understanding of how to implement DOE O 435.1 and DOE
M 435.1-1 requirements. Guidance for each requirement discusses the technical, management,
and administrative aspects of the requirement and identifies acceptable principles, practices, and
methods for implementing the requirement. Performance measures for evaluating acceptable
implementation of each requirement are also presented. The guidance also includes examples to
help illustrate concepts being discussed. These examples are based on hypothetical situations and
should not be used as the basis for adapting specific technical standards. Users need to evaluate
real situations to identify the hazards which need to be managed and establish the appropriate
technical standards. The guide, in many cases, also provides a list of supplemental references that
may benefit the individuals responsible for implementing DOE O 435.1 and DOE M 435.1-1. The
referenced documents may, in some instances, be regularly updated. Users are responsible for
ensuring that the most current versions of these documents are available to affected workers and
are referenced as appropriate.
Although the requirements in DOE M 435.1-1 were prepared to be as clear and concise as
possible, they may be interpreted differently among users. The guidance provides contextual
information and explanation to aid users in understanding the purpose and intent of the
requirements. Reviewing the guidance can facilitate use of more consistent approaches to
Chapter I - General Requirements and Responsibilities
I-4 DOE G 435.1-1
7-09-99
implementing the requirements throughout the complex and prevent over or under-interpretation
of the requirements. The information is intended to facilitate understanding of intent, scope of
application, graded application, degree of effort, and, if possible, measurable standards.
The guide also serves as the mechanism for further elaboration and emphasis on concepts which
are important to consider in the implementation of requirements, and describes acceptable ways of
implementing the requirements. The guidance describes situation-specific considerations and
application of the graded approach and necessary and sufficient processes, which can be
considered in applying the requirements. In addition, many requirements of DOE M 435.1-1 can
be met with existing processes, programs, and documentation.
Although DOE M 435.1-1 stipulates that the guidance must be reviewed, this does not mean that
all personnel are responsible for reviewing all guidance. The intent of the requirement is that
personnel responsible for performing particular work processes are accountable for correctly
understanding and interpreting the DOE M 435.1-1 requirements that apply to the work they
perform. For example, those personnel who are responsible for translating specific DOE M
435.1-1 requirements into controlling documents and operating procedures at the sites should
understand how to effectively and efficiently implement them.
Section 14
Example: Site Z has constructed a new facility for storing transuranic waste. Facility
personnel responsible for preparing the waste acceptance criteria read DOE O 435.1
and DOE M 435.1-1 to identify relevant requirements. Based on their review, they
determine that they need to review the General Requirements and Responsibilities
guidance for Radioactive Waste Management Basis, Radioactive Waste Acceptance
Requirements, Radioactive Waste Generator Requirements, Training and Qualification,
Storage, and Waste Declassification. They also read guidance corresponding the
Transuranic Waste Requirement for Definition of Transuranic Waste, Management of
Specific Wastes, Radioactive Waste Management Basis, Contingency Actions, Waste
Acceptance, Waste Certification, Waste Transfer, Packaging and Transportation, and
Storage. The review reminds the storage facility personnel of other sources of
information which need to be considered in developing the waste acceptance criteria,
including the safety analysis, the Waste Acceptance Criteria for the Waste Isolation Pilot
Plant, and the DOE directives addressing safeguards and securities, records
management, and the Safety Management System. Equipped with all of these resources,
waste acceptance criteria that provide for safe receipt and storage of transuranic waste
are developed.
The guide aids in understanding what is necessary to attain compliance, facilitates effective and
efficient implementation of the requirements, and offers acceptable ways to implement the
requirement. Guidance documents, including technical standards, can assist in implementing
requirements. This guide is intending to provide useful information and methodologies on how a
Chapter I - General Requirements and Responsibilities
I-5 DOE G 435.1-1
7-09-99
requirement might be implemented. The guidance includes background information regarding the
intent of the requirement and its technical underpinnings.
Unlike the requirements specifically set forth in a rule or Order, the provisions in guidance
documents are not mandatory. Failure to follow a guidance document does not in itself indicate
noncompliance with a specific requirement – a finding of noncompliance must be based on a
failure to satisfy the requirement. The guidance provided in implementation guides and standards
referenced therein are considered acceptable methods to satisfy requirements. The approaches
presented in the guidance are not the only acceptable ways of complying with any given
requirement. Alternative methods that satisfy the requirements of DOE O 435.1 and DOE M
435.1-1, are also acceptable. Any implementation method selected must ensure that an adequate
level of safety commensurate with the identified hazards associated with work is achieved and be
consistent with the radioactive waste management basis. Generally it is expected that site
documents (e.g., program plans, procedures, waste acceptance criteria) will provide
documentation showing that a requirement is being met consistent with the guidance. However,
personnel can employ alternative methods that may be more appropriate for specific situations.
To the extent that a unique or different approach other than that addressed in the guidance does
not otherwise have a documented rationale or basis, it will be necessary to create one.
Documentation should identify the alternative method and should include a technically defensible
reason for using the alternative approach. The Integrated Safety Management standards
identification processes already have safeguards to address the adequacy of standards and these
should be the processes used for making and documenting any such decisions.
Section 15
Compliance with this requirement is demonstrated by key individuals being familiar with the intent
of DOE M 435.1-1 requirements based on their review of the guidance, and sites meeting DOE M
435.1-1 requirements by establishing processes described in the guidance. Sites meeting DOE M
435.1-1 requirements in a way different than described in the guidance will be able to demonstrate
that an adequate level of safety commensurate with the hazards associated with the work is being
maintained, that the method is consistent with the radioactive waste management basis, and if
necessary, documentation of the rationale for the alternative approach.
Supplemental References:
1. DOE, 1998. Directives System and Directives System Manual, DOE O 251.1A and DOE
M 251.1-1A, U.S. Department of Energy, January 30, 1998.
2. DOE, 1995. Performance Indicators and Analysis of Operations Information, DOE O
210.1, U.S. Department of Energy, Washington, D.C., September 27, 1995.
Chapter I - General Requirements and Responsibilities
I-6 DOE G 435.1-1
7-09-99
3. DOE, 1995. Environment, Safety, and Health Policy for the Department of Energy
Complex, DOE P 450.1, U.S. Department of Energy, Washington, D.C., June 15, 1995.
4. DOE, 1996. Identifying, Implementing and Complying with ES&H Requirements, DOE
P 450.2A, U.S. Department of Energy, Washington, D.C., May 15, 1996.
Chapter I - General Requirements and Responsibilities
I-7 DOE G 435.1-1
7-09-99
I. 1.C. Radioactive Waste Management.
All radioactive waste subject to DOE O 435.1, Radioactive Waste Management, and
the requirements of this Manual shall be managed as high-level waste, transuranic
waste, low-level waste, or mixed low-level waste.
Objective:
The objective of this requirement is to ensure that all DOE radioactive waste is managed as one of
the established waste types, and to eliminate the creation of other waste categories or the
management of radioactive waste outside of the requirements established in DOE M 435.1-1. It
is also the objective of this requirement to ensure that the radioactive waste is managed safely and
effectively within the established programs for high-level waste, transuranic waste, low-level
waste, or mixed low-level waste.
Discussion:
The DOE system for management of radioactive waste has evolved over the last several years into
four complex-wide program areas. The first three correspond to the radioactive waste types
identified in DOE O 435.1: high-level waste, transuranic waste, and low-level waste. The fourth
program, for management of mixed low-level waste, evolved separately from the low-level waste
management program due to the hazardous portion of the waste also being subject to the
Resource Conservation and Recovery Act (RCRA). Mixed low-level waste, being a subset of
low-level waste, must be managed in accordance with the low-level waste requirements of DOE
M 435.1-1 and the applicable requirements of RCRA.
The evolution of the management of high-level waste and transuranic waste, based on the driving
statutes for their management, has not resulted in separate programs for mixed high-level or
mixed transuranic waste. Rather, the programs for those waste types address the combined
programmatic planning aspects of storage, treatment, and disposal of mixed and non-mixed waste
varieties of those waste types.
Section 16
Management of wastes containing radioactivity that do not meet the definitions of the radioactive
waste types in DOE O 435.1 and DOE M 435.1-1 (i.e., 11e.[2] byproduct material, residual
radioactive material as defined in the Uranium Mill Tailings Radiation Control Act [UMTRCA],
or naturally occurring radioactive material [NORM]) should continue to be managed under the
provisions of the UMTRCA, 40 CFR Part 192, or DOE 5400.5, Radiation Protection of the
Public and the Environment, as applicable. However, DOE M 435.1-1 allows for small quantities
of these wastes to be managed in accordance with Chapter IV, Low-Level Waste Requirements
(see the Guidance on DOE M 435.1-1, Section IV.B). Waste in quantities too large for
acceptance at DOE low-level waste disposal sites shall be managed according to the requirements
Chapter I - General Requirements and Responsibilities
I-8 DOE G 435.1-1
7-09-99
of 40 CFR Part 192, and disposed of at specially designated DOE sites or tailing disposal sites
established under the Uranium Mill Tailings Radiation Control Act of 1978.
During the development of the requirements in DOE M 435.1-1, a safety and hazards analysis was
performed to identify operational activities which presented potential hazards that needed to be
mitigated. The analysis was conducted on the waste types that have been established through
federal legislation and regulation, i.e., high-level, transuranic, low-level, and mixed low-level
waste. In order to ensure that the public, workers, and the environment are protected in the
course of radioactive waste management, any waste managed by the Department, pursuant to
DOE M 435.1-1, must be identified as one of these waste types and managed within the
appropriate program. For many years some sites have identified as special case waste that would
otherwise meet the definition of high-level, transuranic, or low-level waste. This term was initially
used for any waste that did not have a disposition path and evolved to encompass waste which
needed special attention. This requirement is intended to preclude the categorization of a
radioactive waste as a special-case waste or something other than high-level, transuranic, low-
level, or mixed low-level waste, and avoid potential problems associated with the waste not being
recognized by and managed within one of the existing waste type programs discussed above.
Table I-1.C provides examples of different waste streams and how they could be categorized by
waste type and by waste management program.
Table I-1.C. Examples of Waste Type and Program Identification
Previous Designation or
Description of Waste
DOE O 435.1 Designation Management Program
DOE Equivalent to GTCC Low-Level Waste LLW or MLLW
Surplus Sealed Sources with
No Potential Reuse
Low-Level Waste or
Transuranic Waste
LLW or TRU
Special Performance
Assessment Required (SPAR)
Low-Level Waste or
Transuranic Waste
LLW, MLLW, or TRU
Waste Samples from Control
Runs of DWPF
High-Level Waste or HLW
Waste Incidental to
Reprocessing if determined to
be so
LLW, MLLW, or TRU
Example: A site with a low-level waste disposal facility has waste that has been
accumulating in storage over the last 20 years. The waste is contaminated with less than
100 nCi/g (3700 Bq/g) of transuranic radionuclides so it does not meet the definition of
Chapter I - General Requirements and Responsibilities
I-9 DOE G 435.1-1
7-09-99
Section 17
transuranic waste. Even though the transuranic radionuclide concentration is less than
100 nCi/g (3700 Bq/g), the low-level waste disposal facility performance assessment does
not project that the waste can be disposed with a reasonable expectation of meeting the
disposal performance measures. Rather than categorize the waste as a special case,
performance assessment-limited waste, the site correctly categorizes the waste as a
low-level waste and includes it as such in the site radioactive waste management
program. Since it is included as a low-level waste and there is not an identified path to
disposal, plans will be developed for resolving conditions which prevent its disposal, and
its existence will be reported to Headquarters for consideration in complex-wide
planning.
This requirement mandating the management of all radioactive wastes as one of the waste types is
not intended to force a presumption about the hazards of managing a waste, nor to automatically
define the management steps to be followed based on the categorization of a radioactive waste.
Instead, it is intended to promote safe management and timely disposal by ensuring that all wastes
subject to DOE O 435.1, including legacy waste and various wastes traditionally called special
case wastes, are managed within one of the four existing waste programs. The hazards associated
with the waste should still be the most important factor in determining the appropriate
management steps for the waste. Therefore, it would be appropriate, for example, to manage all
remote-handled waste in one location, even if some of it has been categorized as transuranic
waste and some as low-level waste, as long as the waste containers are distinctly marked and
segregated, if necessary to deter cross-contamination.
Example 1: The Defense Waste Processing Facility has a piece of failed equipment that
is contaminated as a result of high-level waste operations. Site personnel characterize
the failed equipment to determine the radioactive species and inventories. By applying
the “waste incidental to reprocessing” process described in DOE M 435.1-1, Chapter II,
High-Level Waste Requirements, site personnel determine that the failed equipment is
low-level waste because it meets the evaluation criteria of Section II.B and can be
disposed of in the onsite low-level waste disposal facility.
Example 2: A site has a waste known to be contaminated with transuranic radionuclides
that has been accumulating in storage over the last 20 years. Because a method for
disposing of the waste has not been determined, the waste has been called a special case
waste. Site management determines that the waste meets the definition of transuranic
waste. This categorization does not mean that the waste will necessarily be disposed of
at WIPP. However, it establishes the program in which the waste will be managed and
also the Manual requirements for managing the waste. Site management must ensure
that the waste is appropriately managed as a transuranic waste, considering the hazards
of managing it, and managed to achieve disposal in an appropriate waste disposal
facility.
Chapter I - General Requirements and Responsibilities
I-10 DOE G 435.1-1
7-09-99
If a legacy waste is not characterized and the waste type is not known, then the organization
responsible for the waste should:
C decide the program under which the waste should be managed;
C identify whether there is a path forward for disposition of the waste;
Section 18
C delineate any issues associated with further management steps, including whether it
requires further characterization;
C provide plans for accomplishing the steps needed to achieve disposal; and
C include this information in the documentation of the Site-Wide Radioactive Waste
Management Program.
Example: A piece of equipment remaining from certain processes no longer conducted
at the site is in storage at Building 400. The equipment has been declared waste, but is
not fully characterized. It has lead shielding which is known to be contaminated, and
based on the processes it was used for, is called mixed low-level waste. It is included in
the FY 1999 Site-Wide Radioactive Waste Management Program documentation as
mixed low-level waste without a path forward for disposal, and management steps are
described to fully characterize the equipment to confirm the waste type designation and
to begin an options analysis for treatment and disposal. (Note: Documentation in this
case is the information in the update to the Site’s FFCA Treatment Plan.)
Figure 1 provides a logic diagram to assist in determining the proper waste type and the
appropriate program for managing wastes. Guidance for each waste type chapter should also be
consulted for more detailed information about characterization of specific wastes or waste
streams. As noted above, any waste managed by the Department, pursuant to DOE M 435.1-1,
must be identified as high-level, transuranic, low-level, or mixed low-level waste, and managed
within the appropriate program. For many years some sites have identified as special case waste
that would otherwise meet the definition of high-level, transuranic, or low-level waste. This term
was initially used for any waste that did not have a disposition path and evolved to encompass
waste which needed special attention. Special case waste designations should not be used, nor
should separate systems and/or management programs be established outside the existing
radioactive waste programs.
The Assistant Secretary for Environmental Management is responsible for developing and
maintaining complex-wide programs for managing the three radioactive waste types
(DOE M 435.1-1, Section I.2.B.(1)). Guidance on that requirement discusses the important
elements to be included in a waste type management program. The guidance also explains how
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-11
7-09-99
this responsibility can be met through the existing four waste type specific programs. Specific
guidance for the mixed low-level waste management program, which supplements the guidance
on General Requirements, is provided in the guidance for a complex-wide low-level waste
program, DOE M 435.1-1, Section IV.C.
Compliance with this requirement is met by demonstrating that all radioactive wastes are correctly
categorized as high-level waste, transuranic waste, low-level waste, or mixed low-level waste, and
that all waste and waste streams are managed under one of the four existing waste type specific
management programs. For waste that is not adequately characterized, the Site-Wide Radioactive
Waste Management Program documentation should detail the plans for management of this waste
under one of the four programs and should include a step for confirming the waste type
categorization.
Supplemental References:
1. Resource Conservation and Recovery Act of 1976, as amended, October 21, 1986.
Section 19
2. NRC, 1969. “Proposed Rule Making, 10 CFR Part 50 Licensing of Production and
Utilization Facilities,” Federal Register, Vol. 34, No. 8712, U.S. Nuclear Regulatory
Commission, Washington, D.C., June 3, 1969.
3. Nuclear Waste Policy Act of 1982, as amended, January 7, 1983.
4. Low-Level Radioactive Waste Policy Amendments Act of 1985, as amended, January 15,
1986.
5. Waste Isolation Pilot Plant Land Withdrawal Act of 1992, as amended, October 30, 1992.
6. EPA. Identification and Listing of Hazardous Waste, 40 CFR Part 261, U.S.
Environmental Protection Agency, Washington, D.C.
7. DOE, 1990. Radiation Protection of the Public and the Environment, DOE 5400.5, U.S.
Department of Energy, Washington, D.C., February 8, 1990.
8. Uranium Mill Tailings Radiation Control Act, as amended, 42 U.S.C. 7901 et seq., 1978.
Chapter I - General Requirements and Responsibilities
I-12 DOE G 435.1-1
7-09-99
Figure 1 Logic Diagram for Waste-Type/Program
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-13
7-09-99
I. 1.D. Analysis of Environmental Impacts.
Existing and proposed radioactive waste management facilities, operations, and
activities shall meet the requirements of 10 CFR Part 1021, National Environmental
Policy Act Implementing Procedures; and DOE O 451.1A, National Environmental
Policy Act Compliance Program. All reasonable alternatives shall be considered, as
appropriate. Nothing in this Order is meant to restrict consideration of alternatives
to proposed actions.
Objective:
The objective of this requirement is to ensure the protection of the public, workers, and the
environment in the management of radioactive waste, and in particular, compliance with the
requirements of the National Environmental Policy Act.
Discussion:
The safety and hazards analysis indicated that comprehensive evaluation and documentation of
alternatives to radioactive waste management operations and activities was one way of ensuring
that risks associated with the management of radioactive waste were understood, and avoided if
possible. Additionally, compliance with the requirements of the National Environmental Policy
Act (NEPA) is required for all Departmental actions. The requirements analysis concluded that
the current set of requirements invoked by 10 CFR Part 1021, National Environmental Policy Act
Implementing Procedures, and DOE O 451.1A, National Environmental Policy Act Compliance
Program, adequately addressed the controls which were needed to effect such a program.
Under 10 CFR Part 1021, the Department adopts in full the regulations for implementing the
National Environmental Policy Act published by the Council on Environmental Quality (CEQ) at
40 CFR Parts 1500 through 1508. 10 CFR Part 1021 lays out the procedures DOE decision
making must follow and the general requirements for implementing the CEQ requirements for
Department of Energy projects. In accordance with these requirements, the Department must
review all actions to determine the significance of potential environmental impacts and, as
appropriate, prepare environmental assessments and environmental impact statements; prepare,
analyze, and consider alternatives; and provide for public participation in the Department’s
decision making processes.
Section 20
DOE’s Office of Environment, Safety, and Health (EH) has published extensive guidance on
implementation of CEQ regulations and performing required NEPA analysis for DOE projects in a
two volume set entitled, National Environmental Policy Act Compliance Guide. This guidance
contains all the relevant sections of laws, and all Executive Orders, DOE policies, and policies
from other governmental agencies that need to be considered in complying with NEPA
Chapter I - General Requirements and Responsibilities
I-14 DOE G 435.1-1
7-09-99
requirements for DOE projects, including those involving radioactive waste management facilities,
operations, and activities. No additional guidance on complying with NEPA requirements or to
evaluate radioactive waste management facilities, operations, and activities is needed.
Supplemental References:
1. DOE. National Environmental Policy Act Implementing Procedures, 10 CFR Part 1021,
U.S. Department of Energy, Washington, D.C.
2. CEQ. Regulations for Implementing the Procedural Provisions of the National
Environmental Policy Act, 40 CFR Parts 1500-1508, Council on Environmental Quality,
Executive Office of the President, Washington, D.C.
3. DOE, 1998. National Environmental Policy Act Compliance Guide, Volumes I and II,
U.S. Department of Energy, Washington, D.C., August 1998.
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-15
7-09-99
I. 1.E. Requirements of Other Regulations and DOE Directives.
The following requirements and DOE directives are required for all DOE
radioactive waste management facilities, operations, and activities as applicable.
Any of the requirements for the following Departmental directives may be waived or
modified through application of a DOE-approved requirements tailoring process,
such as the “Necessary and Sufficient Closure Process” in DOE P 450.3 and DOE M
450.3-1 and DOE P 450.4, Safety Management System Policy, or by an exemption
processed in accordance with the requirements of that directive or DOE M 251.1
1A, Directives System Manual.
Objective:
The objective of this requirement is to ensure the protection of the public, workers, and the
environment in the management of radioactive waste through the implementation of controls
required in other regulations and DOE Directives.
Discussion:
The safety and hazards analysis conducted during development of DOE O 435.1 and DOE M
435.1-1 was a comprehensive analysis which evaluated all functions of radioactive waste
management from generation to post-closure of disposal facilities, and which considered potential
impacts on the public, workers, and the environment. The analysis identified numerous
weaknesses and conditions requiring controls that are addressed in other existing DOE directives
or Federal regulations. During the requirements analysis, these directives and regulations were
evaluated to determine if they adequately address the weaknesses and conditions identified in the
safety and hazards analysis. It was determined that many of the directives and regulations include
all of the controls necessary. Rather than repeating or paraphrasing existing requirements within
DOE O 435.1 and DOE M 435.1-1, the current requirement invokes the controls of those
directives and regulations in order to provide full regulation of the activities undertaken in the
management of radioactive waste.
Section 21
In the case of a few of the directives and regulations evaluated, certain controls were considered
too generic to adequately address the specific needs in management of radioactive waste, but
most of the controls were found to be adequate. Also, in the case of a few of the directives and
regulations, emphasis on certain important requirements in them was considered necessary to
ensure adequate protection of the public, workers, and the environment. In both of these cases,
the current requirement invokes the controls of the existing directive or regulation, and additional
requirements are added in DOE M 435.1-1. The need for additional controls is included in the
guidance discussions addressing each of the existing directives or regulations which has been
invoked.
Chapter I - General Requirements and Responsibilities
I-16 DOE G 435.1-1
7-09-99
The safety and hazard analysis conducted in support of the DOE O 435.1 and DOE M 435.1-1
requirements was conducted using generalized assumptions and generic facilities. It is recognized
that this may have resulted in the directives list in this Section containing one or more directives
that do not apply to certain facilities. This list is not meant to force a facility to comply with those
directives, rather, the facility should continue to comply with only the applicable directives.
Example: Facility A is not a nuclear facility or activity. Therefore, the requirements of
DOE O 420.1 and other nuclear safety orders are not being followed at Facility A. No
additional requirements are invoked to replace these requirements, nor is there any
implication that a provision of DOE M 435.1-1 is being violated.
It is expected that the responsibilities which are assigned in these directives and regulations will be
adhered to, as well as the requirements for processing exemptions and other administrative
requirements. It is also expected that any implementation guidance which already exists for the
other directives or regulations will be followed. The guidance discussions that follow include
specific implementation guidance for radioactive waste management facilities which augments
whatever implementation guidance already exists.
Waivers, Modifications, and Exemptions. Because the comprehensive safety and hazards analysis
is the basis for inclusion of the controls of the other existing DOE directives and regulations in
DOE M 435.1-1, the controls should be met to ensure the public, workers, and the environment
are protected. However, since the safety and hazards analysis was conducted using generic
scenarios for radioactive waste management, it is recognized that facility-specific requirements
may be different. There are structured processes through which the requirements of DOE
directives invoked in this section of DOE M 435.1-1 may be determined to be unnecessary or
satisfied through application of some other requirement. See DOE P 450.3 and DOE M 450.3-1
on Necessary and Sufficient Closure Process. Also, an exemption may be requested and granted
for DOE requirements which can be demonstrated to be unnecessary for protection of the public,
workers, or the environment. Consistent with the guidance implementing the Safety Management
System Policy, DOE P 450.4, this requirement does not allow exemptions from regulations or
other requirements which are mandated by law. Regulatory relief from these regulations and
requirements must be obtained by the contractor. See DOE M 450.3-1 and 48 CFR 970.5204
7(8).
Section 22
The process that is used to justify a requirement as unnecessary or adequately addressed (e.g.,
“Necessary and Sufficient Closure Process” in DOE P 450.3 and DOE M 450.3-1 and DOE P
450.4, Safety Management System Policy) should be documented in accordance with the
requirements and guidance of that process. If an exemption is used to demonstrate a requirement
does not need to be met, the exemption should be documented in accordance with the process and
requirements in the directive from which an exemption is being requested. If the subject directive
does not have requirements for exemptions, then the requirements for exemptions in DOE M
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-17
7-09-99
251.1-1A, Directives System Manual, should be followed. Additionally, the documentation
should be managed as an auditable record as long as the requirement is considered unnecessary or
an exemption is in effect. Documentation that identifies a requirement as being unnecessary or
adequately addressed, through the use of an accepted process and which meets the requirements
of that process, should be considered complete and in compliance with the DOE M 435.1-1
requirement.
Each of the regulations and DOE directives invoked by the current requirement is identified
below, and a discussion follows that includes information on why the regulation or directive is
specifically identified in DOE M 435.1-1. Also, where needed, information on implementing the
regulation or directive at DOE radioactive waste management facilities, operations, and activities
is included, as well as references to other guidance sections that discuss the implementation of
requirements in these regulations or directives.
I. 1.E.(1) Analysis of Operations Information. Data that measure the
environment, safety, and health performance of radioactive waste
management facilities, operations, and activities shall be identified,
collected, and analyzed as required by DOE O 210.1, Performance
Indicators and Analysis of Operations Information.
Discussion:
The functional and requirements analyses conducted in development of DOE O 435.1 and DOE
M 435.1-1 concluded that an effective system for identification, monitoring, and analysis of
important data and measurements of environment, safety, and health performance was an effective
measure for identifying potential issues before they begin to propagate throughout the system or
begin to present themselves at other facilities in the complex. The Complex-Wide and Site-Wide
Radioactive Waste Management Programs required by DOE M 435.1-1 should include such a
feedback mechanism as part of the evaluation process.
The requirements analysis indicated that the programs in compliance with DOE O 210.1,
Performance Indicators and Analysis of Operations Information, were sufficient for effecting this
type of program for radioactive waste management. The program should track and analyze
appropriate measures of radioactive waste management performance in order to identify potential
problems requiring technical or management attention before the safety of workers, the public, or
the environment, is threatened. More guidance on an effective feedback mechanism for
radioactive waste management programs can be found in guidance on DOE M 435.1-1, Sections
I.2.B.(1) and I.2.F.(1). The Implementation Plan for Defense Nuclear Facilities Safety Board
Recommendation 98-1, Department of Energy Plan to Address and Resolve Safety Issues
Identified by Internal Independent Oversight, March 10, 1999, contains additional guidance for
feedback and tracking systems.
Section 23
Chapter I - General Requirements and Responsibilities
I-18 DOE G 435.1-1
7-09-99
I. 1.E.(2) Classified Waste. Radioactive waste to which access has been limited
for national security reasons and cannot be declassified shall be
managed in accordance with the requirements of DOE 5632.1C,
Protection and Control of Safeguards and Security Interests, and
DOE 5633.3B, Control and Accountability of Nuclear Materials.
Discussion:
During the safety and hazards analysis, no significant risks were identified concerning the
management of DOE classified waste. However, the requirements analysis did conclude that any
classified radioactive waste should continue to be managed appropriately, and if this meant that its
classified status must be maintained, then the current requirements invoked by the Department for
protecting and controlling classified materials were sufficient.
On the other hand, the requirements analysis also concluded that, if possible, the management of
waste as classified should be continued only if necessary. Therefore, DOE M 435.1-1 contains a
requirement to declassify or render suitable for unclassified radioactive waste management to the
extent practical (DOE M 435.1-1, Section I.2.F.(17)) so it can be managed efficiently with other
like wastes, which would help ensure consistency of controls and probably be less expensive.
Guidance is provided on DOE M 435.1-1, Section I.2.F.(17) for making as much radioactive
waste as practical suitable for unclassified management, thereby minimizing the amount that must
continue to be managed as classified waste.
I. 1.E.(3) Conduct of Operations. Radioactive waste management facilities,
operations, and activities shall be conducted in a manner based on
consideration of the associated hazards. Waste management facilities,
operations, and activities shall meet the requirements of DOE 5480.19,
Conduct of Operations Requirement for DOE Facilities.
Discussion:
The safety and hazard analysis indicated that many weaknesses and conditions which could lead to
potential radiation exposures and environmental contamination could be prevented through
effective analysis of functions being conducted in management of waste and establishment of
procedures to control the activities that would lead to the desired results. These types of required
controls are already implemented by compliance with DOE 5480.19, Conduct of Operations
Requirement for DOE Facilities, and this requirement serves to emphasize the continued
importance of effective conduct of operations as a protective measure, especially in light of some
of the complex activities that are needed in radioactive waste management. No additional
guidance is provided here for implementing these requirements for radioactive waste management
facilities, operations, or activities.
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-19
7-09-99
I. 1.E.(4) Criticality Safety. Radioactive waste management facilities,
operations, and activities shall be covered by a criticality safety
program in accordance with DOE O 420.1, Facility Safety.
Discussion:
The safety and hazard analysis identified that situations which could lead to criticality were a
particularly high-risk aspect of radioactive waste management because the consequences of a rare
event of this type could be catastrophic. The Department already requires a criticality safety
program in compliance with DOE O 420.1, Facility Safety. This DOE M 435.1-1 requirement
serves to emphasize that a criticality program in accordance with DOE O 420.1 must be in place
for radioactive waste management facilities, operations, and activities for which criticality is an
important consideration. No additional guidance is provided here for implementing these
requirements for radioactive waste management facilities, operations, or activities.
Section 24
I. 1.E.(5) Emergency Management Program. Radioactive waste management
facilities, operations, and activities shall maintain an emergency
management program in accordance with DOE O 151.1,
Comprehensive Emergency Management System.
Discussion:
The safety and hazards analysis identified that an emergency management program which
institutes precautions against potential situations which could lead to worker and public radiation
exposures, and which can effectively respond to emergencies is a mitigating measure that should
be in place for all radioactive waste management facilities, operations, and activities. The
requirements analysis indicated that the programs required to be in compliance with DOE O
151.1, Comprehensive Emergency Management System, would be sufficient.
The safety and hazard analysis also revealed a few weaknesses and conditions concerning
radioactive waste management that required special emphasis due to the consequences of
accidents involving liquid radioactive waste. Therefore, additional requirements for contingency
actions for radioactive waste management facilities, operations, and activities are found in each of
the waste type chapters, and implementation guidance on the requirements (DOE M 435.1-1,
Sections II.H, III.E, and IV.E) should be consulted for discussions on meeting those requirements
by incorporating actions into the existing emergency response programs of DOE O 151.1.
I. 1.E.(6) Environmental and Occurrence Reporting. Radioactive waste
management facilities, operations, and activities shall meet the
reporting requirements of DOE O 231.1, Environment, Safety and
Chapter I - General Requirements and Responsibilities
I-20 DOE G 435.1-1
7-09-99
Health Reporting, and DOE O 232.1A, Occurrence Reporting and
Processing of Operations Information.
Discussion:
The functional and requirements analyses conducted in development of DOE O 435.1 and
DOE M 435.1-1 concluded that a system for monitoring and reporting important environmental
data and occurrences of certain actions or off normal events was an effective measure for
mitigating radioactive waste management problems. Reporting is especially important for
identifying potential issues before they propagate through the system or for identifying problems
and issues before they present themselves at other facilities in the complex. The requirements
analysis indicated that the programs already in place in compliance with DOE O 231.1,
Environment, Safety, and Health Reporting, and DOE O 232.1A, Occurrence Reporting and
Processing of Operations Information, were sufficient for effecting this type of program for
radioactive waste management.
The Complex-Wide and Site-Wide Radioactive Waste Management Programs should incorporate
these feedback mechanism as part of the evaluation process. More guidance on effective
feedback mechanisms for radioactive waste management programs can be found in guidance on
DOE M 435.1-1, Sections I.2.B.(1) and I.2.F.(1).
I. 1.E.(7) Environmental Monitoring. Radioactive waste management facilities,
operations, and activities shall meet the environmental monitoring
requirements of DOE 5400.1, General Environmental Protection
Program, and DOE 5400.5, Radiation Protection of the Public and
Environment.
Discussion:
Section 25
The safety and hazard analysis identified that monitoring for releases of radiation and radioactive
material to the environment was an especially important mitigating factor for potential weaknesses
and conditions in radioactive waste management. The requirements analysis concluded that the
environmental monitoring programs and plans, as required by DOE 5400.1, General
Environmental Protection Program; and DOE 5400.5, Radiation Protection of the Public and
Environment, implemented monitoring that would address the kinds of concerns evaluated in the
analysis.
However, monitoring of disposed radioactive waste, because it must remain effective for a long
time period following cessation of operations, presents a unique challenge. Additional monitoring
of low-level waste disposal facilities is addressed in DOE M 435.1-1, Section IV.R.
Implementation guidance for those requirements should be consulted for information on
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-21
7-09-99
incorporating additional low-level waste disposal facility performance monitoring into the
environmental monitoring program and plans already required to be in compliance with the
subject DOE Orders on environmental monitoring.
I. 1.E.(8) Hazard Analysis Documentation and Authorization Basis.
Radioactive waste management facilities, operations, and activities
shall implement DOE Standards, DOE-STD-1027-92, Hazard
Categorization and Accident Analysis Techniques for Compliance with
DOE 5480.23, Nuclear Safety Analysis Reports, and/or DOE-EM-STD
5502-94, DOE Limited Standard: Hazard Baseline Documentation, and
shall, as applicable, prepare and maintain hazard analysis
documentation and an authorization basis as required by DOE O
425.1A, Startup and Restart of Nuclear Facilities, DOE 5480.21,
Unreviewed Safety Questions, DOE 5480.22, Technical Safety
Requirements, and DOE 5480.23, Nuclear Safety Analysis Reports.
Discussion:
The safety and hazard analysis that was conducted in development of DOE O 435.1 and
DOE M 435.1-1 considered a generic or composite facility, operation, or activity in determining
the risks associated with management of radioactive waste. During the analysis, it was recognized
that for an actual facility, operation, or activity, the real risks posed could be different than those
used in development of the set of requirements in the Manual. This requirement was included to
ensure that, where appropriate, hazard analysis and documentation was prepared for actual
facilities in accordance with the established DOE directives covered, so that if any more severe
risks did exist with any radioactive waste management facilities, operations, or activities, then
appropriate controls would be developed to mitigate them. Guidance that discusses the
authorization basis that may be developed in implementing DOE O 425.1A, Startup and Restart
of Nuclear Facilities, DOE 5480.21, Unreviewed Safety Questions, DOE 5480.22, Technical
Safety Requirements, and DOE 5480.23, Nuclear Safety Analysis Reports, appears in discussions
of the radioactive waste management basis requirement, DOE M 435.1-1, Section I.2.F.(2).
Section 26
Supporting the implementation of the DOE Orders are two DOE Standards: DOE-STD-1027-92,
Hazard Categorization and Accident Analysis Techniques for Compliance with DOE Order
5480.23, Nuclear Safety Analysis Reports, and DOE-EM-STD-5502-94, DOE Limited Standard:
Hazard Baseline Documentation. The first Standard establishes guidance for the preparation and
review of hazard categorization and accident analyses techniques as required in DOE 5480.23 and
therefore, applies only to nuclear facilities, i.e., Hazard Category facilities/operations 1, 2, and 3.
The second is a DOE-EM Limited Standard that establishes uniform Office of Environmental
Management guidance on hazard baseline documents that identify and control radiological and
Chapter I - General Requirements and Responsibilities
I-22 DOE G 435.1-1
7-09-99
non-radiological hazards for all Office of Environmental Management facilities including nuclear,
radiological, non-nuclear, and industrial.
Supplemental References:
1. DOE, 1992. Hazard Categorization and Accident Analysis Techniques for Compliance
with DOE Order 5480.23, Nuclear Safety Analysis Reports, DOE-STD-1027-92, U.S.
Department of Energy, Washington, D.C., December 1992.
2. DOE, 1994. DOE Limited Standard: Hazard Baseline Documentation, DOE-EM-STD
5502-94, U.S. Department of Energy, Washington, D.C., August 1994.
I. 1.E.(9) Life-Cycle Asset Management. Planning, acquisition, operation,
maintenance, and disposition of radioactive waste management
facilities shall be in accordance with DOE O 430.1A, Life-Cycle Asset
Management, and DOE 4330.4B, Maintenance Management Program,
including a configuration management process to ensure the integrity
of physical assets and systems. Corporate physical asset databases
shall be maintained as complete, current inventories of physical assets
and systems to allow reliable analysis of existing and potential hazards
to the public and workers.
Discussion:
The hazards analysis and requirements analysis conducted in development of DOE O 435.1 and
DOE M 435.1-1 indicated that effective planning throughout the entire life of a facility or process,
coupled with a maintenance program to maintain facilities and systems in proper working order,
and configuration management to orderly track changes and decisions made in the life of a facility
or operation, were effective ways to avoid problems in management of radioactive waste. DOE O
430.1A, Life-Cycle Asset Management, provides for the kind of planning and configuration
management envisioned by the development process, and is cited in this requirement for emphasis.
Likewise, the maintenance process required by DOE 4330.4B, Maintenance Management
Program, would achieve adequate maintenance for radioactive waste management facilities,
operations, and activities, and is also cited for emphasis. The guidance for the following
requirements should be consulted for incorporation of aspects of implementation of the process
and programs required by these Orders into radioactive waste management facilities, operations,
and activities: DOE M 435.1-1, Section II.P.(2); Section III. M.(2); and Section IV.M.(2).
However, both the safety and hazards and the requirements analyses indicated that some of the
specific weaknesses and conditions which could be experienced with management of radioactive
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-23
7-09-99
Section 27
waste are not covered by the planning required by DOE O 430.1A, Life-Cycle Asset
Management. Specific weaknesses identified that were not adequately addressed by DOE O
430.1A requirements dealt with planning and facility closure when waste streams requiring
additional management or which had no path to disposal were involved. An emphasis on life-
cycle planning for cradle-to-grave management of waste streams from facilities, operations, and
activities was thought to cover these weaknesses and conditions that need controlling in the
management of radioactive waste. Therefore, the concept of life-cycle planning for waste streams
is introduced in DOE O 435.1 and DOE M 435.1-1. The incorporation of life-cycle planning for
radioactive waste is discussed in guidance for the Complex-Wide and Site-Wide Radioactive
Waste Management Programs (DOE M 435.1-1, Sections I.2.B.(1) and I.2.F.(1)), and the
Radioactive Waste Generator Requirements (DOE M 435.1-1, Section I.2.F.(7)).
I. 1.E.(10) Mixed Waste. Radioactive waste that contains both source, special
nuclear, or by-product material subject to the Atomic Energy Act of
1954, as amended, and a hazardous component is also subject to the
Resource Conservation and Recovery Act (RCRA), as amended.
Discussion:
The potential additional risks posed by mixed radioactive waste due to the hazardous constituents
involved, and the complexities of managing mixed radioactive waste, have been recognized for
years. This requirement acknowledges the regulation of the hazardous constituents of mixed
radioactive wastes in accordance with the Resource Conservation and Recovery Act (RCRA), as
amended or in accordance with state hazardous waste regulations promulgated under RCRA
authority. Each of the waste type chapters in DOE M 435.1-1 contains additional requirements
for mixed radioactive wastes. Guidance for those additional requirements (DOE M 435.1-1,
Sections II.C, III.B, and IV.B.(1)) should be consulted to find discussions on management of
radioactive mixed waste under DOE O 435.1. Also, implementation guidance on the
Department’s management of mixed low-level waste is in the guidance on the Complex-Wide
Low-Level Waste Management Program requirement, DOE M 435.1-1, Section IV.C.
I. 1.E.(11) Packaging and Transportation. Radioactive waste shall be packaged
and transported in accordance with DOE O 460.1A, Packaging and
Transportation Safety, and DOE O 460.2, Departmental Materials
Transportation and Packaging Management.
Discussion:
The Department of Transportation maintains regulations covering the transportation of
radioactive materials, and DOE will continue to meet these requirements for all applicable
transportation situations. This requirement emphasizes the need to continue to meet DOE O
Chapter I - General Requirements and Responsibilities
I-24 DOE G 435.1-1
7-09-99
460.1A, Packaging and Transportation Safety, and DOE O 460.2, Departmental Materials
Transportation and Packaging Management, for all transportation of radioactive waste.
However, the safety and hazard analysis revealed weaknesses and conditions concerning
packaging of radioactive waste and waste containers that are not sufficiently covered in the
existing transportation regulations because of the long time frames radioactive waste needs to be
managed compared with the short time radioactive waste is in transport. Therefore, additional
requirements for packaging and transportation of radioactive waste are found in each of the waste
type chapters, and guidance for the requirements (DOE M 435.1-1, Sections II.O, III.L, and
IV.L) should be consulted for discussions on meeting those requirements.
Section 28
I. 1.E.(12) Quality Assurance Program. Radioactive waste management
facilities, operations, and activities shall develop and maintain a
quality assurance program that meets the requirements of 10 CFR
830.120, Quality Assurance Requirements, and DOE O 414.1, Quality
Assurance, as applicable.
Discussion:
The safety and hazards analysis indicated that a strong quality assurance program is appropriate
because of the risks posed by the management of DOE’s radioactive waste. The analysis of
requirements concluded that most of the requirements already imposed for quality assurance
programs in 10 CFR 830.120, Quality Assurance Requirements and Responsibilities, and DOE O
414.1, Quality Assurance, would establish a sufficient program to maintain the quality of products
and processes needed for radioactive waste management. Some specific additional quality
assurance program requirements are invoked for high-level waste management in DOE M 435.1
1, Section II.G, and the guidance for those requirements should be consulted to determine how
they can be implemented within the quality assurance programs already in place as a result of
compliance with 10 CFR 830.120 and DOE O 414.1.
I. 1.E.(13) Radiation Protection. Radioactive waste management facilities,
operations, and activities shall meet the requirements of 10 CFR Part
835, Occupational Radiation Protection, and DOE 5400.5, Radiation
Protection of the Public and the Environment.
Discussion:
The protection of humans and the environment from the dangers of radiation due to radioactive
waste management facilities, operations, and activities is a fundamental requirement of the revised
DOE O 435.1, Radioactive Waste Management, and is invoked in DOE O 435.1, Section 4,
Requirements. This DOE M 435.1-1 requirement emphasizes the need to ensure that the
requirements of 10 CFR Part 835, Occupational Radiation Protection, and DOE 5400.5,
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-25
7-09-99
Radiation Protection of the Public and the Environment, are met for radioactive waste
management facilities, operations, and activities.
An important element of these DOE directives is the As Low As Reasonably Achievable
(ALARA) process. The Manual contains a specific requirement for the Field Element Manager to
ensure that the ALARA principles are incorporated for radioactive waste management facilities,
operations, and activities. The guidance on that Manual requirement (DOE M 435.1-1, Section
I.2.F.(12)) should be consulted for additional information in implementing the ALARA principles
for activities covered by this Manual.
I. 1.E.(14) Records Management. Radioactive waste management facilities,
operations, and activities shall develop and maintain a record-keeping
system, as required by DOE O 200.1, Information Management
Program, and DOE O 414.1, Quality Assurance. Records shall be
established and maintained for radioactive waste generated, treated,
stored, transported, or disposed. To the extent possible, records
prepared in response to other requirements may be used to satisfy the
documentation requirements of this Manual. Additional records may
be required to satisfy the regulations applicable to the hazardous
waste components of mixed waste.
Discussion:
Section 29
The safety and hazards analysis demonstrated that management of information important to
understanding the risks posed by radioactive waste and the needs for establishing controls was an
important control in and of itself. This mitigating factor showed up in many places in the analysis,
and the requirements analysis indicated that DOE O 200.1, Information Management Program,
and DOE O 414.1, Quality Assurance, provided for the necessary programmatic considerations in
establishing effective records and information management.
However, some of the specific controls which were thought necessary for managing the technical
adequacy and accuracy needed for radioactive waste records, especially considering the
magnitude of consequences that could be involved and the long time frames associated with
disposal of waste, are not specific enough in these two orders. Thus, there are specific references
in many places in all three waste type chapters to establishing a particular kind of record, what the
record may be used for, and some indication of the time the record must be kept. These
additional considerations are then discussed in the guidance that explains that requirement in
detail. It is intended that the programmatic recordkeeping requirements of the particular site will
incorporate the necessary changes and accommodations to implement the intent of the DOE M
435.1-1 recordkeeping requirement.
Chapter I - General Requirements and Responsibilities
I-26 DOE G 435.1-1
7-09-99
Records for Waste Generated, Treated, Stored, Transported, and Disposed. The requirement
states that records shall be established for radioactive waste generated, treated, stored,
transported, or disposed. The intention of this part of the requirement is to emphasize that
records should be kept throughout the entire life-cycle of the waste, including after it is disposed.
To that end, there are specific requirements for recordkeeping in waste certification, waste
transfer, high-level waste disposal, low-level waste storage, and radioactive waste management
basis sections of DOE M 435.1-1. Site- or facility-specific recordkeeping requirements for any
radioactive waste management functions that are deemed necessary in addition to the
requirements called out in DOE M 435.1-1 should be established in order to maintain the
information important to protection of the public, workers, and the environment.
Use of Other Documentation Requirements. It is possible that documentation required by other
DOE directives, regulations, or site- or facility-specific requirements may contain all the necessary
information needed and be maintained adequately for radioactive waste management
recordkeeping. To the extent practical, any other recordkeeping requirements that are already
being complied with should be used, or modified if appropriate, to meet the recordkeeping
requirements of DOE M 435.1-1. It is not intended that duplicate or additional recordkeeping be
established to meet DOE M 435.1-1 requirements where sufficient recordkeeping already exists.
Mixed Waste Documentation Requirements. Additional recordkeeping and records management
requirements may be needed for radioactive mixed waste to comply with Federal and/or State
hazardous waste requirements. This part of the requirement stands as a reminder that the
hazardous waste records requirements must still be complied with regardless of the records
management requirements for the radioactive contaminants being addressed in DOE M 435.1-1.
Unless it is agreed to by the appropriate regulators for the hazardous component of mixed waste,
the recordkeeping requirements of DOE M 435.1-1 do not necessarily achieve compliance with
the separate requirements for the hazardous component of the waste.
Section 30
I. 1.E.(15) Release of Waste Containing Residual Radioactive Material. The
process for determining and documenting that waste is suitable to be
released and managed without regard to its radioactive content shall
be in accordance with the criteria and requirements in DOE 5400.5,
Radiation Protection of the Public and the Environment.
Discussion:
The requirements analysis indicated that controls for the management of radioactive waste in
DOE M 435.1-1 may not be necessary for wastes that may have low concentrations of residual
radioactive material. Consistent with DOE 5400.5, Radiation Protection of the Public and the
Environment, this requirement allows the determination of waste streams that may be managed
without regard to their radioactivity. The current requirements in DOE 5400.5, Radiation
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-27
7-09-99
Protection of the Public and the Environment, along with implementation guidance established by
the Office of Environment, Safety, and Health, for making and documenting these determinations
should be consulted for appropriately managing waste streams without regard to their radioactive
content.
I. 1.E.(16) Safeguards and Security. Appropriate features shall be incorporated
into the design and operation of radioactive waste management
facilities, operations, and activities to prevent unauthorized access and
operations, and for purposes of nuclear material control and
accountability, where applicable; and shall be consistent with DOE O
470.1, Safeguards and Security Program.
Discussion:
The requirements analysis concluded that the current requirements delineated in DOE O 470.1,
Safeguards and Security Program, adequately provide for the safeguarding of classified
information and material as well as security for radioactive waste management facilities,
operations, and activities. Therefore, DOE O 470.1 is cited in DOE M 435.1-1 for emphasis. No
additional implementation guidance is considered necessary to address any special needs of the
required programs due to the management of radioactive waste.
I.1.E.(17) Safety Management System. Radioactive waste management
facilities, operations, and activities shall incorporate the principles of
safety management as described in DOE P 450.4, Safety Management
System Policy, and DOE P 450.5, Line Environment, Safety and Health
Oversight, and meet the requirements of the safety management
systems sections of 48 CFR Chapter 9, Department of Energy
Acquisition Regulations and DOE M 411.1-1, Manual of Safety
Management Functions, Responsibilities, and Authorities.
Discussion:
DOE P 450.4, Safety Management System Policy, establishes the Department’s policy that a
formal, organized process shall be used for planning, performing, assessing, and improving the
safe conduct of work. DOE P 450.5, Line Environment, Safety and Health Oversight, establishes
the Department’s policies that line management conduct environment, safety and health line
oversight in a cost-effective, coordinated, integrated, and efficient manner that is seamless to
contractors and that value is placed on the Department's line managers and contractors working
together to identify and ensure resolution of environment, safety and health concerns. In keeping
with this Departmental policy, the principles of integrated safety management were embodied in
the technical analyses and processes used to determine the essential requirements of the DOE
Section 31
Chapter I - General Requirements and Responsibilities
I-28 DOE G 435.1-1
7-09-99
Order and Manual on radioactive waste management. The core functions for implementing these
principles are (1) define the scope of work; (2) analyze the hazards; (3) develop and implement
hazard controls; (4) perform work within the controls; and (5) provide feedback and continuous
improvement.
Requirements for these policies are set forth in Chapter 9 of Title 48, the Department of Energy
Acquisition Regulations, and in DOE M 411.1-1, Manual of Safety Management Functions,
Responsibilities, and Authorities. These requirement sets are invoked in DOE M 435.1-1 not
only because of the flowdown of the Departmental policies, but also because the implementation
of the policies in the Order and Manual were done through evaluating generic situations on a
complex-wide basis. The actual implementation of the policies for radioactive waste management
facilities, operations, and activities is required on an actual site- and facility-specific basis.
Guidance for implementation of a compliant integrated safety management system is found in
DOE G 450.4-1A, Safety Management System Guide. No additional guidance is needed for
implementing a system for radioactive waste management facilities, operations, and activities.
I. 1.E.(18) Site-Evaluation and Facility Design. New radioactive waste
management facilities, operations, and activities shall be sited and
designed in accordance with DOE O 420.1, Facility Safety, and
DOE O 430.1A, Life-Cycle Asset Management.
Discussion:
The safety and hazards analysis demonstrated that the selection and evaluation of a suitable site
plus an appropriate facility design that considered the characteristics of the site chosen were
effective mitigation measures to prevent potential problems with the management of radioactive
waste, especially when the long-time frames required for effective management of disposed waste
are considered. The provisions of DOE O 420.1, Facility Safety, and DOE O 430.1A, Life-Cycle
Asset Management, were evaluated and found to be adequate in providing the necessary controls
in radioactive waste management. In addition to these Orders, refer to the DOE Handbook,
DOE-HDBK-1132-99, Design Considerations. This Handbook includes information and
considerations for the design of systems typical to nuclear facilities, design considerations specific
to various types of special facilities, and information useful to various design disciplines. The
Handbook specifically includes design considerations for confinement systems and radiation
protection and effluent monitoring systems as well as good practices and design principles that
should be considered in specific design disciplines.
The DOE M 435.1-1 waste-type chapters contain specific requirements to supplement DOE O
420.1 and DOE O 430.1A for radioactive waste management facilities. DOE M 435.1-1
(Sections II.P, III.M, and IV.M) contains detailed additional requirements for both site evaluation
and facility design.
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-29
7-09-99
Section 32
The intent of the specific facility design requirements in each waste type chapter is to have them
applied to all radioactive waste management facilities, both existing and new. However, it is
recognized that in some cases it may not be practical, or possible, to apply these requirements to
existing facilities or operations. In such cases a graded application of the requirement, or an
exemption to the requirement, may be warranted. Use of a graded application or exemption to
the requirements may be due to limited programmatic usage, a short service life, or other reasons
that make long-term, capital intensive upgrades unreasonable. The guidance for the DOE M
435.1-1 waste type specific facility design requirements contain discussions for conducting
adequate facility designs for radioactive waste management facilities, operations, and activities
and additional discussions on the application of a graded approach to achieving compliance with
the requirements.
I. 1.E.(19) Training and Qualification. A training and qualification program
shall be implemented for radioactive waste management program
personnel, and shall meet the requirements of DOE O 360.1, Training,
and DOE 5480.20A, Personnel Selection, Qualification, and Training
Requirements for DOE Nuclear Facilities.
Discussion:
The safety and hazards analysis indicated that an effective mitigating measure for a large number
of weaknesses and conditions that could arise in management of radioactive waste was an
effective program for qualification and training of personnel. The requirements analysis indicated
that DOE’s current programs implementing DOE O 360.1, Training, and DOE 5480.20A,
Personnel Selection, Qualification, and Training Requirements for DOE Nuclear Facilities were
adequate in establishing effective radioactive waste management personnel qualification and
training programs.
It is expected that some changes, additions, or improvements to the existing radioactive waste
management personnel qualification and training programs would be needed to train personnel on
the new and revised requirements of DOE O 435.1 and DOE M 435.1-1. The Field Element
Manager is assigned a specific responsibility in DOE M 435.1-1, Section I.2.F.(11) to ensure that
this training and re-qualification is reflective of each individuals specific job responsibilities and
the changes and improvements made to the radioactive waste management Order. Guidance on
DOE M 435.1-1, Section I.2.F.(11) should be consulted for more discussion about the
implementation of a radioactive waste management qualification and training program.
I. 1.E.(20) Waste Minimization and Pollution Prevention. Waste minimization
and pollution prevention shall be implemented for radioactive waste
management facilities, operations, and activities to meet the
requirements of Executive Order 12856, Federal Compliance with
Chapter I - General Requirements and Responsibilities
I-30 DOE G 435.1-1
7-09-99
Right-to-Know Laws and Pollution Prevention Requirements, and
Executive Order 13101, Greening the Government through Waste
Prevention, Recycling, and Federal Acquisition, and DOE 5400.1,
General Environmental Protection Program.
Discussion:
Section 33
The safety and hazards analysis indicated that an effective mitigating measure in management of
radioactive waste was to avoid potential weaknesses and conditions through minimization of
waste. The requirements analysis indicated that DOE’s current programs implementing Executive
Order 12856, Federal Compliance with Right-to-Know Laws and Pollution Prevention
Requirements and Responsibilities, and Executive Order 13101, Greening the Government
through Waste Prevention, Recycling, and Federal Acquisition, and DOE 5400.1, General
Environmental Protection Program, were adequate in establishing effective waste minimization
programs. In addressing this subject, the NRC endorsed EPA’s Guidance to Hazardous Waste
Generators on the Elements of a Waste Minimization Program (59 FR 31114). This guidance
should be reviewed for applicability to site waste minimization issues, and establishing a waste
minimization program. For emphasis, the Field Element Manager is assigned a specific
responsibility in DOE M 435.1-1, Section I.2.F.(3) to ensure that a waste minimization program is
fully implemented.
I. 1.E.(21) Worker Protection. Radioactive waste management facilities,
operations, and activities shall meet the requirements of DOE O
440.1A, Worker Protection Management for DOE Federal and
Contractor Employees.
Discussion:
The safety and hazards analysis indicated that many risks were posed by the management of
radioactive waste that were related to non-radioactive characteristics of the waste, and/or by
activities that would need to be carried out on the waste regardless of its radioactive content. A
few examples of these activities are: conducting activities in tight spaces, handling of heavy,
unstable packages, and operation of forklifts. The requirements analysis concluded that the
requirements of DOE O 440.1A, Worker Protection Management for DOE Federal and
Contractor Employees adequately covered these risks and should be cited in DOE M 435.1-1 for
completeness. DOE O 440.1A invokes external Occupational Safety and Health Administration
requirements (e.g., 29 CFR Part 1910, Occupational Safety and Health Standards) for both DOE
Federal and contractor personnel, along with several industrial and consensus standards for safe
workplaces, such as the American Society of Mechanical Engineers’ Boiler and Pressure Vessel
Safety Code, and the National Fire Protection Association’s Electrical Safety Requirements for
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-31
7-09-99
Employee Workplaces. No additional implementation guidance is needed for implementing DOE
O 440.1A for radioactive waste management facilities, operations, or activities.
Supplemental References:
1. DOE. Nuclear Safety Management, Quality Assurance Requirements, 10 CFR 830.120,
U.S. Department of Energy, Washington, D.C.
2. DOE, 1995. Facility Safety, DOE O 420.1, U.S. Department of Energy, Washington,
D.C., October 13, 1995.
Chapter I - General Requirements and Responsibilities
I-32 DOE G 435.1-1
7-09-99
I. 2.A. Program Secretarial Officers.
Program Secretarial Officers with radioactive waste management facilities,
operations, or activities are responsible within their respective programs for
ensuring that the Field Element Managers meet the requirements of DOE O 435.1,
Radioactive Waste Management, and this Manual.
Objective:
The objective of this requirement is to ensure DOE Headquarters management attention and
oversight of Field Offices’ management of radioactive waste.
Section 34
Discussion:
This requirement applies to any Program Secretarial Officer (PSO) that has responsibility for
facilities, operations, or activities involving the management of radioactive waste. PSOs should
be cognizant of Field radioactive waste management activities under their purview and provide
appropriate oversight of Field Element Manager’s implementation of DOE O 435.1 and DOE M
435.1-1.
A key to successful compliance with any DOE Directive is oversight. This is particularly true of
directives which, like DOE O 435.1 and DOE M 435.1-1, have performance-oriented
requirements that call for review and approval of site- or facility-specific implementation of
procedures and other controls to ensure the requirements are being met. Oversight is defined
(DOE M 435.1-1, Attachment 2) as:
The responsibility and authority assigned to line management to assess the adequacy of
DOE and contractor performance. Independent Oversight refers to the responsibility and
authority assigned to the Assistant Secretary for Environment, Safety, and Health to
independently assess the adequacy of DOE and contractor performance.
The DOE complex has initiated the integrated Safety Management System under Secretarial
policies DOE P 450.4, Safety Management System Policy, DOE P 450.5, Line Environment,
Safety, and Health Oversight, and DOE P 411.1, Safety Management Functions,
Responsibilities, and Authorities Policy. These policies are invoked by DOE M 435.1-1,
I.1.E.(17) for the purposes of emphasis and clarity. DOE P 450.4 provides the overall goals and
objectives of the DOE integrated Safety Management System. Core function No. 5, “Provide
Feedback and Continuous Improvement,” calls for a system of evaluations and reporting in order
to continuously improve in achieving the goals and requirements for safety and protection of the
environment. DOE P 450.5 explains that line management has the responsibility for oversight of
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-33
7-09-99
DOE facilities, operations, and activities, including those involving management of radioactive
waste.
It is expected that the revised requirements of DOE O 435.1 and DOE M 435.1-1 will be
incorporated into contractor self-assessments established under the integrated Safety Management
System, and incorporated into the Field Office oversight of the contractor programs, as
appropriate. Similarly, under the Safety Management System policies, PSOs have the
responsibility to monitor the Field Office oversight and participate in Field Office oversight
functions, as appropriate. Likewise, under the Safety Management Systems policies, the Assistant
Secretary for Environment, Safety, and Health (EH-1) has the responsibility to assess the
adequacy of Field Office and contractor performance, and it is expected that the revised DOE O
435.1 and DOE M 435.1-1 requirements will be assimilated into the Assistant Secretary for
Environment, Safety, and Health’s programs for independent oversight at his/her discretion.
Example: The Assistant Secretary for Defense Programs (DP-1) has been delegated the
responsibility for waste management at the Kansas City Plant. He has delegated the
authority for this responsibility to DP-24, the Office of Site Operations. DP-24 directs
personnel in his organization to conduct an annual evaluation at the Kansas City Plant
during which they assess the site’s implementation of DOE O 435.1 and DOE M 435.1-1.
DP-24 is advised of any non-compliance issues and in turn advises DP-1 of these issues.
Section 35
Compliance with this requirement is demonstrated by appropriate incorporation of DOE O 435.1
and DOE M 435.1-1 requirements within the functions, responsibilities, authorities, and
requirements explained in the set of Safety Management System directives. This results in
thorough and effective oversight of radioactive waste management facilities, operations, and
activities, and assurance that the public, workers, and the environment are protected from the
hazards associated with management of radioactive waste.
Supplemental References:
1. DOE, 1997. Safety Management Functions, Responsibilities, and Authorities Policy,
DOE P 411.1, U.S. Department of Energy, Washington, D.C., January 28, 1997.
2. DOE, 1996. Safety Management System Policy, DOE P 450.4, U.S. Department of
Energy, Washington, D.C., October 15, 1996.
3. DOE, 1997. Line Environment, Safety and Health Oversight, DOE P 450.5, U.S.
Department of Energy, Washington, D.C., June 26, 1997.
4. DOE, 1997. Manual of Safety Management Functions, Responsibilities, and Authorities,
DOE M 411.1-1, U.S. Department of Energy, Washington, D.C., October 8, 1997.
Chapter I - General Requirements and Responsibilities
I-34 DOE G 435.1-1
7-09-99
5. DOE, 1992. Environmental Audit Program Guidance, DOE/EH-0232, U.S. Department
of Energy, Washington, D.C., January 1992.
6. DOE. Performance Objective and Criteria for Conducting DOE Environmental Audits,
DOE/EH-0229, U.S. Department of Energy, Washington, D.C.
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-35
7-09-99
I. 2.B. Assistant Secretary for Environmental Management.
The Assistant Secretary for Environmental Management is responsible for:
(1) Complex-Wide Radioactive Waste Management Programs. Establishing and
maintaining integrated Complex-Wide Radioactive Waste Management
Programs for high-level, transuranic, low-level, and mixed low-level waste.
These programs shall use a systematic approach to planning, execution, and
evaluation to ensure that waste generation, storage, treatment, and disposal
needs are met and coordinated across the DOE complex.
Objective:
The objective of this requirement is to ensure development of complex-wide programs that result
in the safe and efficient management of all DOE high-level, transuranic, low-level, and mixed low-
level waste. The programs are to ensure coordination among DOE sites and among Headquarters
program offices. Such programs provide Headquarters and Field personnel a common basis for
carrying out the radioactive waste management programs’ missions.
Discussion:
The Department is responsible for managing radioactive waste in a manner that is protective of
the public, workers, and the environment. To accomplish this in the most efficient manner, and to
make the best use of resources, programs for managing the various waste types need to be
coordinated among Headquarters Program Offices and among the DOE sites. Radioactive waste
subject to the Radioactive Waste Management Order (DOE O 435.1) and the Manual (DOE M
435.1-1) is to be managed within one of four waste-type programs in accordance with the
Radioactive Waste Management requirement of the Manual (DOE M 435.1-1, Section I.1.C).
The complex-wide programs must respond to current needs affecting the safe, effective, and
efficient management of waste. The complex-wide programs should provide a vision of the final
disposition of each waste type for the complex, yet need to be responsive to the issues that arise
at individual DOE sites.
Section 36
The Assistant Secretary for Environmental Management is assigned responsibility for maintaining
programs for managing each waste type to ensure that there is a focal point for managing the
wastes and ensuring integration across the complex. Integration across the complex involves
coordinating treatment, storage, and disposal to allow the needs of one site to be met by
capabilities at another site, if practical. To that end, activities at individual DOE sites should
support the complex-wide program by providing data needed for complex-wide planning (e.g.,
waste inventories and projections, facility capacities) and by budgeting for and executing site
activities that lead to accomplishing complex-wide program goals. Conversely, the complex-wide
Chapter I - General Requirements and Responsibilities
I-36 DOE G 435.1-1
7-09-99
program should also be supportive of the site programs by establishing realistic goals and
resolving complex-wide issues (e.g., disposal configurations, equity issues, certain issues affecting
waste with no path to disposal), and should be developed with cognizance of individual site
constraints (e.g., agreements with State or local governments, compliance orders).
In addition to ensuring integration across the complex, assigning the Assistant Secretary for
Environmental Management responsibility for program development and maintenance also
provides a focal point for coordination across all Headquarters Program Offices. Thus, regardless
of whether other Headquarters program offices (e.g., Defense Programs, Science) have
responsibility for various waste management activities, the Assistant Secretary for Environmental
Management is responsible for ensuring that activities are coordinated within the waste type
programs.
The requirement calls for a program for each waste type. This is consistent with the way DOE
manages the radioactive waste types and allows the focus of the program to be on the
characteristics and/or legal and regulatory requirements specific to the waste type. For example,
the regulatory constraints on disposal vary among the waste types. DOE plans to dispose of high-
level waste in a geologic repository so the end point objective of the high-level waste program is
to convert the waste into a form that meets the waste acceptance criteria for the repository.
Federal legislation provides for the disposal of defense transuranic waste in a geologic repository,
separate from the spent nuclear fuel/high-level waste repository. Waste characteristics and the
need to coordinate transportation to the repository provides the common basis for having a
transuranic waste management program. The Department’s policy and regulatory authority for
onsite disposal of low-level waste establishes the underlying basis for addressing this waste within
a program; and in part, because of the overlay of external requirements, mixed low-level waste is
addressed within a separate program.
Although individual programs for the waste types are established at the complex-wide level,
separate programs for each waste type are not required at the DOE sites. Rather, the site
programs are to be developed in a manner that the Field Element Manager deems appropriate, as
long as the site programs support the individual complex-wide programs (see guidance for
Site-Wide Waste Management Program).
Section 37
A systematic approach for managing each waste type should provide all of the organizations
involved in the program with a common framework within which they can discharge their
responsibilities. The program framework should identify the overall mission of the program, the
key program participants, participants roles, and expected accomplishments. The top-level
functions of the program are planning or formulation, execution, and evaluation. The planning
function identifies the organizations or sites responsible for implementing the strategies and
activities directed at accomplishing the program mission. Under the execution function of the
program, each organization performs the work for which it is responsible. For example, site
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-37
7-09-99
personnel would perform the activities associated with storing, treating, and disposing of waste
and Headquarters personnel would perform the necessary coordination, data collection and
analysis, and further complex-wide planning. The evaluation function provides the means of
improving the program by learning from the experience gained through execution of the program.
Each of these functions is discussed in more detail below.
Planning. A systematic approach to planning involves identifying and defining those aspects of
the program necessary for the sites to execute their individual responsibilities. The planning
should be consistent with DOE policies, other programs, and controlling or higher level
documents that specify DOE policy or direction.
Example: The waste type programs need to be consistent with the overall plan for clean
up of DOE sites developed under the auspices of the Assistant Secretary for
Environmental Management. The Assistant Secretary’s plan is a higher level document
establishing policy and direction for environmental restoration and waste management
activities in the Department.
The complex-wide program for each waste type should be defined in terms of scope, mission,
goals and objectives, priorities, and interfaces. As used here, the term scope means the
boundaries of the program, such as the waste and the waste management facilities and activities
that are included in the program. The mission, and goals and objectives provide program
participants a common view of what the program is intended to accomplish in the short and long
term. The priorities address the order of importance of the goals, objectives and activities to be
accomplished. A priority may be based on the need to complete a fairly minor activity in order to
support a subsequent activity. The interfaces describe where and how the program interactions
occur, both within the program and with other organizations and facilities outside of the program.
A key interface for each waste type program is the interaction with the other waste type programs
since there are occasions when waste exits one program and enters another programs (e.g., see
guidance on Waste Incidental to Reprocessing).
In order to ensure that waste management needs will be met (e.g., sufficient waste storage
capacity), it is necessary to have data on inventories of waste and estimates of future waste
receipts to compare with current and projected facility capacities. These data provide the basis
for determining the strategy for meeting current and future waste management needs. A strategy
for meeting waste management needs may include constructing new facilities (permanent or
mobile), using commercial facilities or capabilities, coordinating among DOE sites, or
combinations of these and other actions. The Assistant Secretary also needs to ensure that
National Environmental Policy Act (NEPA) analyses are performed to support policy-making and
configuration decisions.
Section 38
Chapter I - General Requirements and Responsibilities
I-38 DOE G 435.1-1
7-09-99
Lastly, the planning function includes developing and submitting a budget request to implement
the planned program activities. Depending on organizational responsibilities assigned at
Headquarters, the Assistant Secretary for Environmental Management may not be responsible for
funding all waste management activities. However, in exercising the responsibility assigned by
this requirement, the Assistant Secretary should be cognizant of the funding for waste
management being requested by other Program Offices to ensure that waste management
activities are integrated. In performing budget planning, it is necessary to plan for events far
enough into the future to allow sufficient lead time for the Federal funding process. Generally, this
requires identifying major expenditures two or three years in advance.
Implementation of the program planning activities may be provided for by existing actions
undertaken by or on behalf of the Assistant Secretary for Environmental Management. To the
extent the planning function is already met by ongoing activities (e.g., the annual budget
submittal, existing waste type program plans), no additional effort is required to fulfill this
responsibility.
Execution. Execution of the waste management programs involves those activities taken to
implement planning. At the complex-wide level, execution will involve performing the studies and
analyses that form the basis for resolving issues and conducting future planning. At the site level,
execution includes the generation, storage, treatment, and disposal of waste. In addition, program
execution includes data collection and documentation associated with waste management
activities, as well as construction and procurement activities necessary to provide future waste
management capabilities.
Evaluation. An important part of a systematic approach to the waste management programs is
evaluating the work accomplished during the execution phase. Progress should be measured
against programmatic goals established during the planning phase. In addition, success should be
measured against parameters established to evaluate protection of the public, workers, and the
environment. The evaluation should include the following elements:
Performance Measures. Metrics should be used in evaluating performance against
program, and environmental, health, and safety goals should be selected and agreed to by
Headquarters and the field;
Performance Data. Performance data should be collected from across the complex to
enable evaluation of performance relative to the measures selected above;
Performance Evaluation and Reporting. Collected data should be reduced into a form that
allows it to be analyzed against the metrics and to allow it to be interpreted and evaluated
for performance and trends; and
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-39
7-09-99
Feedback. Information should be provided for use in the planning process and for use by
the sites in improving performance. Feedback should be in the form of recommendations
for potential changes to program policies, goals, priorities, strategies, or interfaces.
Additionally, feedback may include recommendations on methods to improve protection
of the environment, and human health and safety, either through top-level management
actions (e.g., administration of contractor award fees) or working level management
actions (e.g, changes to site operating practices and/or procedures).
Section 39
The process of planning, execution, and evaluation is iterative. The lessons learned from the
activities undertaken during one fiscal year, or changes in the assumptions on which the program
strategy was based, will require revising the program planning. This in turn will affect the
execution of the program, and therefore the performance measures that will be included in the
evaluation step.
Compliance with this requirement is demonstrated if complex-wide waste type programs exist for
high-level, transuranic, low-level, and mixed low-level waste. These programs should result in
safe and efficient management of all DOE radioactive waste and ensure coordination among DOE
sites and programs.
Supplemental References:
1. DOE, 1997. Safety Management Functions, Responsibilities, and Authorities Policy,
DOE P 411.1, U.S. Department of Energy, Washington, D.C., January 28, 1997.
2. DOE, 1997. Manual of Safety Management Functions, Responsibilities, and Authorities,
DOE M 411.1-1, U.S. Department of Energy, Washington, D.C., October 8, 1997.
3. DOE, 1996. DOE Low-Level Waste System Description Document, U.S. Department of
Energy, Office of Environmental Management, September 1996.
I. 2.B.(2) Changes to Regulations and DOE Directives. Ensuring changes to
regulations and DOE directives are reviewed and, when necessary,
incorporated into revisions of this Manual to ensure the basis for safe
radioactive waste management facilities, operations, and activities is
maintained.
Chapter I - General Requirements and Responsibilities
I-40 DOE G 435.1-1
7-09-99
Objective:
The objective of this requirement is to ensure that changes to pertinent regulations and other DOE
directives are evaluated and incorporated into revisions to radioactive waste management
directives to keep current with new information and practices.
Discussion:
The Assistant Secretary for Environmental Management is responsible for ensuring changes to
regulations and DOE directives are reviewed and evaluated for their impact on safe radioactive
waste management. The results of the review should be used to assess the need to revise DOE O
435.1, Radioactive Waste Management and the associated Manual and Contractor Requirements
Documents. When warranted, these documents are to be revised to ensure protection of workers,
the public, and the environment.
New information leads to changes in regulations and other DOE directives, and practices used in
the management of radioactive waste. This information and the changes should be evaluated and,
when appropriate, incorporated into revisions of DOE O 435.1, Radioactive Waste Management,
or DOE M 435.1-1, Radioactive Waste Management Manual, so that DOE radioactive waste
management requirements and practices are consistent with requirements and practices within
DOE and in commercial radioactive waste management. If the review of a change in a regulation
or directive leads to the potential need for a revision, the determination of the need and rationale
for a revision should be documented. The documentation should be maintained as an auditable
record as long as the directive is in effect.
Section 40
Example: The DOE directive on environmental and occurrence reporting is revised and
a new version issued. The Order and associated documents are reviewed and primarily
administrative requirements (e.g., the way DOE does business) are changed. A review of
the technical basis document does not reveal any reliance on the administrative
requirements of the revised order for protection of workers, the public, or the
environment. Therefore, the results of the review lead to the conclusion that there is no
need to revise DOE O 435.1, Radioactive Waste Management. This conclusion is
documented and maintained as a quality assurance record. Additionally, however, a
change to a technical requirement which was relied upon to address a weakness or
condition associated with radioactive waste management is assessed to determine impact
on the protection of workers, the public, and the environment. A significant impact is
identified that warrants a revision to the requirements of DOE M 435.1-1. The method
of effecting the revision (change page, memorandum, order revision, etc.) should be
documented and managed as a quality assurance record.
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-41
7-09-99
Compliance with this requirement is demonstrated by the existence of a systematic process of
reviewing new and proposed directives and regulations for their impact on the basis for safe
management of DOE radioactive waste. Documented conclusions from the reviews provide
evidence that the process is being implemented.
Supplemental References: None.
Chapter I - General Requirements and Responsibilities
I-42 DOE G 435.1-1
7-09-99
I. 2.C. Assistant Secretary for Environment, Safety, and Health.
The Assistant Secretary for Environment, Safety and Health is responsible for
providing an independent overview of DOE radioactive waste management and
decommissioning programs to determine compliance with DOE environment, safety,
and health requirements and applicable Environmental Protection Agency (EPA)
and state regulations, including:
(1) Advising the Secretary of the status of Departmental compliance with the
requirements of DOE O 435.1, this Manual, and applicable provisions of
other DOE Orders.
(2) Conducting independent appraisals and audits of DOE waste management
programs.
(3) Reviewing site Waste Management Plans with regard to compliance with
DOE environment, safety, and health requirements.
Objective:
The objective of this requirement is to ensure that the existing role of the Office of Environment,
Safety and Health for providing independent oversight is maintained and understood.
Discussion:
The role of the Assistant Secretary for Environment, Safety and Health is to conduct independent
oversight of DOE activities, including radioactive waste management. The purpose of this
oversight is to determine compliance of DOE Headquarters and Field Element programs with
DOE Environment, Safety and Health regulations and applicable EPA and state regulations.
During the development of DOE M 435.1-1, it was recognized that explicit inclusion of this
statement within the General Requirements and Responsibilities Chapter would serve to clarify
this role.
The inclusion of this requirement/responsibility is not expected to change any current reporting,
oversight, or compliance arrangements within the Department, rather it further clarifies existing
roles and responsibilities.
Chapter I - General Requirements and Responsibilities
Section 41
DOE G 435.1-1 I-43
7-09-99
Supplemental References:
1. DOE, 1997. Manual of Safety Management Functions, Responsibilities, and Authorities,
DOE M 411.1-1, U.S. Department of Energy, Washington, D.C., October 8, 1997.
2. DOE, 1988. General Environmental Protection Program, DOE 5400.1, U.S. Department
of Energy, Washington, D.C., November 9, 1988.
3. DOE, 1990. Radiation Protection of the Public and the Environment, DOE 5400.5, U.S.
Department of Energy, Washington, D.C., February 8, 1990.
Chapter I - General Requirements and Responsibilities
I-44 DOE G 435.1-1
7-09-99
I. 2.D. Deputy Assistant Secretary for Waste Management.
The Deputy Assistant Secretary for Waste Management is responsible for:
(1) Complex-Wide Radioactive Waste Management Program Plans. Developing,
implementing, and maintaining integrated Complex-Wide Radioactive Waste
Management Program Plans for high-level, transuranic, low-level, and mixed
low-level waste. Each plan shall, at the DOE complex-wide level, describe the
functional elements, organizations, responsibilities, and activities that
comprise the system needed to store, treat, and dispose of radioactive waste
in a manner that is protective of the public, workers, and the environment.
In addition, the plans shall:
(a) Present a waste management strategy that integrates waste
projections and life-cycle waste management planning into complex-
wide facility configuration decisions; and
(b) Describe the approach to research and technology development being
pursued to improve safety and/or efficiency in managing radioactive
waste.
Objective:
The objective of this requirement is to ensure that complex-wide plans provide an overarching
strategy for making and implementing waste management decisions. The overarching strategy
provides site personnel a framework within which they can formulate and execute plans for
managing wastes at the individual sites.
Discussion:
The Radioactive Waste Management Manual, DOE M 435.1-1, Section I.2.B.(1), assigns the
Assistant Secretary for Environmental Management responsibility for establishing and maintaining
complex-wide management programs for each waste type. This responsibility is fulfilled through
the planning, execution, and evaluation of these programs. The current requirement assigns the
responsibility for a complex-wide program plan for each waste type to the Deputy Assistant
Secretary for Waste Management. These plans are to provide a clear picture of the waste type
program and its direction, and serve as a mechanism for documenting most of the planning
functions of the programs. Although assigned to the Deputy Assistant Secretary, the
development of these plans is a cooperative and iterative effort with the site representatives and
other affected programs. Whereas the Field Element Managers are to develop and implement site
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-45
7-09-99
programs that support the complex-wide plan, the complex-wide plan should be developed based
on the inventory, facility status, constraints, and needs of the individual sites.
Definition of Waste Management Program. The following topics are to be addressed in the waste
type program plans to define the program in a manner that conveys the extent and intent of the
program.
Mission. The program plans should provide a succinct statement of the overall purpose of
the program. The mission statement should reflect the expectation to safely manage each
waste type throughout all stages of waste management and should reflect disposal of
waste as part of the mission.
Section 42
Example: The Low-Level Waste Management Program mission statement states - The
mission of the Department of Energy Low-Level Waste Management Program is to
develop, implement, and coordinate a nationally integrated program for low-level waste
treatment, storage, and disposal that uses a combination of Federal and private facilities
to meet the needs of waste generators while fully protecting workers, the public, and the
environment. Safety of operations and timely disposal of waste are high priorities for the
Department.
Goals, Objectives, and Milestones. A key element of the complex-wide waste type
program plans is the identification of program goals, objectives, and major milestones.
Goals to be defined in the program plans may be general and apply to the complex as a
whole, or they may be site-specific goals, based on input from the field, that are major
events for the program (e.g., opening the Waste Isolation Pilot Plant). One of the
complex-wide goals that should be defined in the plans is the expected end-state for the
waste type. That is, the end of the life-cycle for the particular waste type should be one of
the long-term goals of the program. The complex-wide goals should be specific, long
term measures of the waste type program’s progress, and the goals should be challenging,
yet achievable. To support the periodic assessment of the program’s progress, the goals
should be measurable.
Objectives should be established as interim measures of progress towards meeting the
program goals. The objectives may be established as complex-level objectives, or may
reflect key events at individual sites that are significant to measuring progress in the
program.
Milestones are more specific events, e.g., decision points, completion of specific studies or
analyses, or operation of specific facilities, which have a date of completion associated
with them. Milestones are to be established in support of the goals and/or objectives. As
with the goals and objectives, milestones may be established for activities being addressed
Chapter I - General Requirements and Responsibilities
I-46 DOE G 435.1-1
7-09-99
at the complex-wide level, or may represent major activities that are to be completed at a
specific site consistent with site programs (see DOE M 435.1-1, Section I.2.F.(1)). The
following examples shows program goals, supported by objectives, and specific
milestones.
Example 1:
Goal: Convert Environmental Management high-level waste to a form that can be
accepted by the Office of Civilian Radioactive Waste Management.
Objective: Vitrify all of the high-level liquid waste at the Savannah River Site.
Milestone: Produce 250 canisters of vitrified Savannah River Site high-level
waste in conformance with Environmental Management Waste Acceptance
Product Specification during FY 1999.
Example 2:
Goal: Provide for disposal of all transuranic waste.
Objective: Dispose of defense transuranic waste at the Waste Isolation Pilot Plant.
Milestone: Begin disposal operations at the Waste Isolation Pilot Plant by
September 1998.
Milestone: Remove all packaged transuranic waste from the Rocky Flats
Environmental Technology Site by December 2XXX.
Priorities. The complex-wide program should establish priorities which are then reflected
in the goals and objectives of the program. The priorities for the program may be
influenced by a number of different factors, including legal commitments or agreements,
predecessor-successor relationships of related program activities, timing of the availability
of a technology or facility, and funding considerations.
Section 43
Example 1: A prioritization of activities in the high-level waste management program
has resulted in a decision to construct and start operation of vitrification facilities at the
Savannah River Site and the West Valley Demonstration Project, followed by facilities at
Hanford and the Idaho National Engineering and Environmental Laboratory. These
priorities are based on availability of funding and the stage of technology development
and readiness at these sites.
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-47
7-09-99
Example 2: An example of prioritization for the Transuranic Waste Management
Program would be deciding to open the transportation corridors through New Mexico,
Colorado, Wyoming, Utah, and Idaho prior to opening corridors through eastern states.
This priority is based on the sites that are expected to ship waste to the Waste Isolation
Pilot Plant first.
Boundaries and Interfaces. The program plans should clearly define the boundaries or
scope of the program and describe the internal and external interfaces which must be
managed. The complex-wide plans should define what is within the program boundary,
including a general description of the wastes to be managed. Part of defining the
boundaries or scope in the waste type program plans includes identifying the internal
interfaces. The internal interfaces include the interactions among organizations or
activities that have different funding sources, but are part of the DOE waste management
(e.g., high-level, transuranic, low-level, or mixed low-level waste) programs. Internal
interfaces are defined through the identification of organizations and responsibilities
discussed in a following subsection.
Interfaces external to a waste type program should also be defined in the program plan.
The interfaces exist between waste type programs, with generators, and with external
entities. First, interfaces between waste type programs need to account for transfers of
waste between the programs. Transfer may be necessary to accommodate waste that
changes from one waste type to another (e.g., as a result of assay or a waste incidental to
reprocessing determination), or from generating a waste as a result of managing another
waste type (e.g., high-level waste treatment generates a secondary low-level waste
stream). An important outcome of identifying interfaces with other waste type programs
is ensuring that all waste (subject to DOE O 435.1) under the Department of Energy’s
purview is being managed within one of the waste type programs.
Example: Pretreatment of high-level waste at the Savannah River Site results in a
high-volume stream of salt solution. Through application of the waste incidental to
reprocessing process, a determination is made that the salt solution should be managed
as low-level waste. The high-level and low-level waste programs establish an interface
that ensures that the waste is safely managed according to the appropriate set of
requirements.
Second, each of the programs needs to identify interfaces with the generators of each
waste type. The program plan should document the sources of waste that the program
will manage. Whereas some waste is generated by activities within the program, waste is
also generated by the Environmental Restoration Program, Defense Programs, Science
Programs, and Nuclear Energy Programs.
Chapter I - General Requirements and Responsibilities
I-48 DOE G 435.1-1
7-09-99
Section 44
Third, the program plan should document interfaces with organizations external to the
Department of Energy. This could include external regulatory agencies (Federal or State)
as well as commercial facilities.
Constraints. The program plans should discuss significant constraints on the planning and
execution of each waste type program. As used here, the term constraints has a broad
meaning including program assumptions, Departmental policies which direct or restrict
certain waste management actions, external regulations, etc. Key assumptions that may
impact planning at the complex-wide level include major policies, current and out-year
program funding, expected programmatic or activity decisions, and expected contract
awards.
Example: A key assumption affecting the management of low-level waste is that the six
currently operating low-level waste disposal facilities will continue to operate for the
next two years. Therefore, there would be no significant changes to existing generator-
disposal facility relationships.
Organization and Responsibilities. The organizational and functional responsibilities of the
participants in the complex-wide waste type programs, and their interrelationships, should be
described in the program plans. This description should include the identification of the
organizations within both the Headquarters and Field organizations, and a discussion of their
respective roles in formulating, executing, and evaluating the waste type programs. The plan
should include organization and interface charts that define the roles, responsibilities, and
authorities for each of the major program participants, as well as required lines of communication.
Example: For the Low-Level Waste Management Program, the Program Plan identifies
the entity responsible for supporting the Deputy Assistant Secretaries for Waste
Management and Environmental Restoration in the review and evaluation of disposal
facility performance assessments and composite analyses.
Integrated Program Strategy. The program plan provides a description and basis for the strategy
being pursued to fulfill the program mission and meet the program goals. The strategy addresses
the life-cycle management of waste from generation and generation reduction through the plans
and approaches for effecting disposal of waste. The strategy also needs to recognize that part of
the life-cycle management of the waste may include continued safe storage of legacy waste
pending the ability to dispose of it. The strategy needs to be consistent with the assumptions
described earlier and should be developed considering the following elements:
• Technical and programmatic issues;
• Waste projections;
• Life-cycle waste management planning;
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-49
7-09-99
• Waste minimization and pollution prevention;
• Research and development; and
• Implementation of DOE O 435.1.
Technical and Programmatic Issues. Major issues that impact the safe management of
waste, including regulatory issues; expected changes in Federal, State or local statutes;
and major technical issues should be discussed in the plan. Among the issues included in
the plan should be problems identified by the sites that would best be addressed at a
complex-wide level (e.g., resolving certain issues that result in waste with no path to
disposal). Examples of these types of problems are issues that need to be negotiated at the
Federal level (with Headquarters of another Federal agency or Congress) or issues that
occur at multiple sites that would benefit by a common resolution. In addition to
identifying the issues, the plan should describe proposed solutions or steps towards
resolving them (e.g., obtaining data, completing studies).
Section 45
Example 1: A major issue that should be addressed at the complex-wide level for
transuranic waste management is the disposition of non-defense transuranic waste.
There is currently no path to disposal for non-defense transuranic waste. The plan
should address the development of information and other steps necessary to support
resolution of the issue.
Example 2: In the high-level waste management program, a key technical and
regulatory issue is the high-level waste tank closure process. The plan identifies
technical issues that need to be resolved, such as appropriate methods to solidify and
stabilize residues that remain in the tank, and regulatory issues such as the waste
categorization of the tanks. The activities and schedule for resolving these issues is
identified in the plan.
Waste Projections. The waste projections element of the programs plans should identify
the minimum data requirements that must be included in waste projections, a consistent
projections methodology, data quality objectives, and evaluation of data uncertainties,
maintenance of data quality, and a periodic review and assessment of waste projections
data quality. The collection of waste projections data should be focused on promoting the
safe and efficient life-cycle management of waste. Therefore, data collection is an element
in ensuring that sufficient storage, treatment, and disposal capacity will be available to
handle current and future wastes.
Example: Projections of low-level waste volumes are necessary to ensure that sufficient
disposal capacity will be available, either within DOE and/or at commercially-operated
facilities. Therefore, the types of information that would be needed include the volumes
of waste that would be generated in different time periods, and the inventories and/or
Chapter I - General Requirements and Responsibilities
I-50 DOE G 435.1-1
7-09-99
concentrations of key radionuclides. Through a cooperative effort among personnel
from the complex-wide program, the generating sites, and DOE disposal sites, a
determination is made as to what actions are necessary to ensure adequate waste
disposal capacity.
Life-cycle Waste Management Planning. At the complex-wide level, personnel working
on the program plan should consider the management needs for all of the waste included
in the program when mapping out a strategy. In so doing, personnel developing the
strategy should consider the volumes and characteristics of waste in storage and those
projected to be generated. The availability of waste management facilities to safely and
expeditiously manage the types and amounts of waste should be considered in developing
the program strategy. For much of the waste, management through its entire life cycle
will be possible using existing or planned facilities. The strategy for these types of waste
should then focus on actions to improve efficiency and safety in effecting disposal. If
appropriate, the strategy should consider the use of non-DOE facilities for meeting waste
management needs.
Example 1: In the Transuranic Waste Management Program, a strategy is developed
that calls for the use of mobile equipment for certifying waste at small generator sites.
Use of the equipment results in program cost savings by avoiding the construction of
facilities for waste certification at multiple sites. Program efficiency is also achieved by
being able to coordinate the schedule for the mobile equipment with the schedule for
shipping waste to WIPP.
Section 46
Example 2: Use of non-DOE facilities to help meet waste management needs occurs in
the management of mixed low-level waste for disposal where DOE capabilities do not
currently exist. A commercial facility that has the necessary radioactive materials
license and RCRA permit provides disposal of mixed low-level waste which cannot
currently be transferred to a DOE site for disposal. The use of the commercial facility is
determined to be in the best interest of DOE and an exemption has been approved. The
DOE strategy to allow disposal of small volumes of mixed low-level waste at a
commercial facility promotes compliance with agreements and external regulations at the
individual DOE sites, and reduces the costs and risks associated with storage.
The strategy should also account for managing the wastes that do not have an apparent
path to disposal. The complex-wide plan should provide sufficient information that site
personnel can use to determine whether activities being taken at the complex-wide level
address the issues that prevent disposal or whether the site should take individual actions
to resolve the issues.
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-51
7-09-99
Example: For transuranic waste that currently cannot be disposed at WIPP, a strategy
might be to address the issues preventing disposal of the waste. In this case, personnel
with non-defense wastes that could otherwise meet the WIPP waste acceptance criteria
would rely on the efforts being taken by Headquarters to resolve the issue.
Waste Minimization and Pollution Prevention. The complex-wide plan should
acknowledge the role that waste minimization and pollution prevention play in the
management of radioactive waste. The plan should reference any applicable pollution
prevention program plans which address commitments concerning the particular waste
type.
Example: The program plan for low-level waste or mixed low-level waste references the
Pollution Prevention Program Plan that documents a Secretarial commitment to reduce
the generation rates for the waste types by 50 percent by the end of 1999 (compared to
the 1993 generation rates). This commitment is then translated into a program goal for
the low-level waste and mixed low-level waste programs.
Research and Development (R&D) Activities. The complex-wide plan should address the
research and development being done to address multi-site issues related to disposal and
other waste management issues. This provides a basis for the sites to determine what
issues need to be addressed at the site level.
Example: In the Transuranic Waste Management Program, research is being performed
to re-evaluate the potential for generation of explosive gases in transuranic waste
containers. If the research concludes that gases are not generated in closed transuranic
waste containers, the need for sampling and/or venting prior to placement into the
TRUPACT II could be eliminated for transportation. This research being undertaken by
a central organization may benefit all shippers of transuranic waste.
Implementation of DOE O 435.1. The program plan should consider the time and cost of
implementing the Radioactive Waste Management Order, DOE O 435.1 and the
supporting Manual, DOE M 435.1-1 when establishing program goals and objectives. In
the near term, the complex-wide strategy must include attaining compliance with the
Order as one of its goals. Individual objectives may address significant facilities at
individual sites.
Section 47
Example: Completion of a performance assessment and composite analysis for low-level
waste disposal facilities, and issuance of a Disposal Authorization Statements, are
appropriate key objectives for inclusion in the Low-Level Waste Management Program
Plan. These are required to comply with DOE M 435.1-1 and are significant to the
overall low-level waste management program.
Chapter I - General Requirements and Responsibilities
I-52 DOE G 435.1-1
7-09-99
The program plan also provides a mechanism for documenting means by which the program
progress and compliance can be evaluated. The plan should indicate the types of evaluations that
are going to take place and at what level in the organizational structure they will occur. The
evaluation and oversight responsibilities should include a clear delineation between the roles of
Headquarters, Field, and contractor organizations. Periodic evaluations of program activities will
provide the basis for determining progress toward achieving the program goals and provide the
feedback necessary to improve performance of the waste-type programs.
Examples of evaluation and oversight activities include:
• Contractor self-assessments;
• Field oversight assessments;
• Progress Tracking System reporting; and
• Quarterly Management Reviews.
Compliance with this requirement is demonstrated if a program plan is developed for each of the
waste types specified in DOE M 435.1-1. The program plans should convey the overall purpose
(end-point) of the program, the responsibilities for accomplishing different program activities, and
a strategy that reflects the uncertainties and constraints that affect management of the specific
waste type.
Supplemental References:
1. CAO, 1997. The National TRU Waste Management Plan, Revision 1, DOE/NTP-96
1204, U.S. Department of Energy, Carlsbad Area Office, Carlsbad, NM, December 18,
1997.
2. DOE, 1997. DOE Low-Level Waste Program Management Plan, Revision 0,
DOE/LLW/PMP-001, U.S. Department of Energy, Washington, D.C., March 1997.
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-53
7-09-99
I. 2.D. Deputy Assistant Secretary for Waste Management.
The Deputy Assistant Secretary for Waste Management is responsible for:
(2) Waste Management Data System. Establishing and maintaining a system to
compile waste generation projection data and other information concerning
radioactive waste management facilities, operations, and activities across the
complex.
Objective:
The objective of this requirement is to ensure information and data concerning the management of
radioactive waste is collected and compiled at the DOE complex level. Compilation of waste
management information promotes safe management of radioactive waste by supporting the
integration and optimization activities, and life-cycle waste management planning across the DOE
complex.
Discussion:
To effectively manage radioactive waste, the Department is dependent on information and data
which describe its waste, both previously generated and projected, as well as the facilities and
systems used to manage the waste. In the development of DOE O 435.1 and DOE M 435.1-1,
collecting and managing this information was determined to be an important function for the safe
and effective management of radioactive waste. The information and data are generated and
developed as a result of site-specific compliance with various requirements including DOE M
435.1-1.
Section 48
The "waste management data system" is a general description used to describe systems and
processes needed to collect, compile, and report information in a uniform and consistent manner.
The specific mechanisms for collecting the data and information will vary based on changes in
management approach and implementation methodology. However, the information and data that
are to be managed originate from many diverse sources so consistent reporting is important. The
data must be collected and reported in a manner that makes them useful to the complex-wide
waste-type programs and plans required by DOE M 435.1-1, Sections I.2.B and I.2.D. For
instance, information on waste with no path to disposal needs to be included in the data system to
allow evaluations which could lead to common solutions that would benefit multiple sites. Also,
data need to be collected to support the evaluation phase of waste management by depicting
progress made in the program.
The development and documentation of data requirements are to be completed for all information
to be collected from the field. Use of data requirements ensures consistency and provides a basis
Chapter I - General Requirements and Responsibilities
I-54 DOE G 435.1-1
7-09-99
for accurate reporting. Data requirements describe the information requested, why it's requested,
and how to report it. Information and data will generally be collected for each DOE site in the
complex. Typically, the following information and data for high-level waste, transuranic waste,
low-level waste, and mixed low-level waste are to be included in the waste management data
system:
• Quantities of past, current, and projected waste, by waste type and year;
• Waste characteristics;
• Waste management life-cycle plans, including final disposition and no path to
disposal information;
• Facility and operational information including capacities; and
• Barriers to disposition and technology needs.
Example: Information on DOE field waste management activities is provided to DOE
HQ through the "Accelerating Cleanup: Paths to Closure" reporting process using
various systems and tools. The information is used to generate a DOE report that
includes disposition maps used to help depict the waste management life cycle and any
barriers that may exist for final waste stream disposition.
Compliance with this requirement is demonstrated by the existence of systems and processes for
the collection and management of complex-wide information about DOE radioactive waste. The
data systems should be updated on a routine basis, and support capacity and facility planning,
resource and budget planning, integration and efficiency efforts, and lessons learned.
Supplemental References:
1. DOE, 1998. Accelerating Cleanup: Paths to Closure, DOE/EM-0362, U.S. Department
of Energy, Washington, D.C., June 1998.
2. DOE, 1996. Low-Level Waste Projection Program Guide, U.S. Department of Energy,
Office of Environmental Management, Washington, D.C., December 18, 1996.
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-55
7-09-99
I. 2.E. Deputy Assistant Secretaries for Waste Management and Environmental
Restoration.
The Deputy Assistant Secretary for Waste Management and the Deputy Assistant
Secretary for Environmental Restoration are responsible for:
Section 49
(1) Disposal. Reviewing and approving, along with EH-1, transuranic waste
disposal facility performance assessments and other disposal documents as
required in waste specific chapters for which DOE is responsible for making
compliance determinations. Reviewing and approving performance
assessments and composite analyses, or appropriate CERCLA
documentation, for low-level waste disposal facilities, and issuing disposal
authorization statements.
(a) The Deputy Assistant Secretaries shall establish a review panel
consisting of DOE personnel to review low-level waste disposal facility
performance assessments and composite analyses, review appropriate
CERCLA documentation, recommend low-level waste disposal facility
compliance determinations to the Deputy Assistant Secretaries, and
develop disposal authorization statements.
(b) The Deputy Assistant Secretaries shall issue disposal authorization
statements containing conditions that low-level waste disposal
facilities must meet in order to operate with an approved radioactive
waste management basis.
Objective:
The objective of this requirement is to ensure that the evaluations conducted in the performance
assessment for a transuranic waste disposal facility, and in the performance assessment (or
appropriate CERCLA documentation) and composite analysis (or appropriate CERCLA
documentation) for a low-level waste disposal facility, are found by DOE to be technically
adequate, logical, complete, and defensible for establishing the controls on disposal of waste for
protection of the public and the environment into the future. The evaluations and controls should
result in a reasonable expectation that the standards of 40 CFR Part 191 will be met at the
transuranic waste disposal facility or in a reasonable expectation that the performance objectives
of Chapter IV of DOE M 435.1-1 will be met at the low-level waste disposal facility.
Chapter I - General Requirements and Responsibilities
I-56 DOE G 435.1-1
7-09-99
Discussion:
During the development of the requirements of DOE O 435.1 and DOE M 435.1-1, the safety and
hazard analyses indicated that disposal is a critical activity requiring controls. Disposal is the final
waste management function performed, yet the potential hazards from disposed radioactive waste
will continue far into the future. Thus, there are specific requirements for the protection of the
public, workers, and environment that are critical to maintaining safe and effective disposal of
radioactive waste. Analyses conducted in a performance assessment for a transuranic and a low-
level waste disposal facility (or appropriate CERCLA documentation for a low-level waste
disposal facility), and the composite analysis (or appropriate CERCLA documentation) for a low-
level waste disposal facility, are critical in determining the nature and extent of the controls that
need to be put in place at the facility being evaluated. The review and approval of these
evaluations is extremely important for management of transuranic and low-level waste to ensure it
is being conducted safely and effectively. Therefore, the review and approval of these evaluations
are assigned as the responsibility of senior management within the Office of Environmental
Management.
Section 50
The requirement states that it is the responsibility of the Deputy Assistant Secretaries for Waste
Management and Environmental Restoration, within their respective programs, to review and
approve certain radiological assessments for transuranic and low-level waste disposal facilities
and to issue the disposal authorization statement based on the reviews. The discussions that
follow provide guidance on the requirement for review and approval of the documents and
issuance of the disposal authorization statement. The discussion begins with an explanation for
excluding certain waste disposal from the DOE M 435.1-1, Section I.2.E.
Disposal of Transuranic Waste at WIPP and High-Level Waste. Requirement 4.d of
DOE O 435.1 identifies WIPP and facilities and operations licensed by the Nuclear Regulatory
Commission (NRC) or an Agreement State as having special requirements that supplement, or in
many cases, replace requirements in DOE O 435.1 and DOE M 435.1-1. Requirement 4.d of the
Order effectively ties the protection of the public, workers, and the environment--the major
objective of DOE O 435.1--to key external legal drivers and regulations that achieve these goals
at certain facilities managing DOE radioactive waste. Key among the facilities currently under
external regulation for public, worker, and environmental protection are WIPP (certified by EPA),
the proposed high-level waste repository (regulated by the NRC), and commercial waste
treatment and disposal facilities utilized by DOE (regulated by the NRC or Agreement States) for
treatment and disposal of low-level and mixed low-level waste. A DOE facility for the disposal of
commercial (NRC licensed) Greater-than-class C (GTCC) low-level waste will also be regulated
by the NRC, as specified in 10 CFR Part 61, Section 61.55 (a)(2)(IV) (see additional discussion
on commercial (NRC licensed) GTCC in the guidance on the Complex-Wide Low-Level Waste
Management Program (DOE G 435.1-1, Section IV.C)).
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-57
7-09-99
One effect of this requirement is that the design, construction, operation, closure, analysis of,
licensing, permitting, and regulation of disposal of DOE transuranic waste at WIPP, and
high-level waste at a proposed geologic repository, are evaluated and controlled by regulations
and requirements outside of the DOE directives system. Based on the safety and hazard and
requirements analyses conducted in the development of DOE O 435.1, and the review and
approval of permitting and licensing documentation by other government organizations, it was
concluded that there is no need to repeat any specific requirements from these external regulations
within DOE M 435.1-1, or to define new requirements for disposal.
Example: The NRC requirements for siting, design, facility performance, package
design, quality assurance, and training and certification of operators for a high-level
waste disposal repository are found in 10 CFR Part 60, Disposal of High-Level
Radioactive Wastes in Geologic Repositories. No additional disposal requirements were
determined to be necessary for inclusion in Chapter II of DOE M 435.1-1.
The only requirements for disposal found in DOE M 435.1-1, Chapter II, High-Level Waste
Requirements, and DOE M 435.1-1, Chapter III, Transuranic Waste Requirements, for disposal
at WIPP, reference the regulatory drivers that have created the external requirements for disposal
of these wastes. Guidance for Chapters II and III contains additional discussions concerning
these drivers, and the disposal of high-level waste and transuranic waste.
Section 51
Disposal of Transuranic Waste (not at WIPP). In cases where the Department disposes of
transuranic waste in a facility other than WIPP (e.g., Greater Confinement Disposal at the Nevada
Test Site), the Department is responsible for determining compliance with 40 CFR Part 191 and
issuing a disposal authorization statement. Therefore, the requirement includes the responsibility
for reviewing and approving performance assessments for a transuranic waste disposal facility for
which DOE must make a compliance determination (i.e., other than WIPP). The Deputy
Assistant Secretary for Waste Management and the Deputy Assistant Secretary for Environmental
Restoration, along with EH-1, are responsible for reviewing and approving performance
assessments for transuranic disposal facilities other than WIPP. A process similar to that
described below for reviewing and approving low-level waste disposal facility performance
assessments will be required. In developing the review criteria, DOE staff should evaluate the
following:
• General provisions including purpose, scope, definitions, conditions of approval,
and alternative provisions;
• Compliance certification including completeness and accuracy of submissions and
reference materials;
Chapter I - General Requirements and Responsibilities
I-58 DOE G 435.1-1
7-09-99
• General requirements addressing inspections, quality assurance, models and
computer codes, waste characterization, future state assumptions, expert
judgment, and peer review;
• Containment requirements considering application of release limits, scope of
performance assessments, consideration of drilling events in performance
assessments, and results of performance assessments;
• Assurance requirements including active and passive institutional controls,
monitoring, engineered barriers, and consideration of natural resources; and
• Individual and groundwater protection requirements considering the protected
individual, exposure pathways, underground sources of drinking water, and the
scope and results of the performance assessment.
Example: The Field Element Manager of a site with a small amount of transuranic waste
that cannot be accepted for disposal at the Waste Isolation Pilot Plant confers with
Headquarters and decides to construct a small transuranic waste disposal facility. The
Manager directs the preparation of a performance assessment that provides a reasonable
expectation of meeting the performance measures in 40 CFR Part 191 for the onsite
facility. Since the facility is not WIPP, following approval at the site, the performance
assessment is submitted to Headquarters for approval. The Deputy Assistant Secretary
for Waste Management assigns the task of establishing criteria and conducting a review
to a staff member. The staff member assembles a review team of technically qualified
DOE and contractor staff. The team develops criteria for the review based on the
Department’s criteria for review of low-level waste disposal facility performance
assessments. Upon completing its review, the team provides a recommendation to the
Deputy Assistant Secretary who makes a final determination and documents it in a
memorandum to the Field Element Manager.
Since 40 CFR Part 191 defines performance assessment, the contents of a performance
assessment, and requirements for compliance, the transuranic waste chapter only contains
reference to the 40 CFR Part 191 standards. Guidance on the transuranic waste disposal
requirements in Section III.P of this document should be consulted for additional discussion.
Section 52
Disposal of Low-Level Waste. Although some of DOE’s low-level waste is disposed at
commercial facilities, much of it is still disposed at DOE-owned and operated low-level waste
disposal facilities. The Department meets its responsibilities under the Atomic Energy Act of
1954, as amended, by providing the requirements for protection of the public, workers, and the
environment for its low-level waste disposal facilities in DOE O 435.1 and DOE M 435.1-1.
Meeting the low-level waste disposal requirements remains a responsibility of DOE managers at
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-59
7-09-99
Headquarters and in the Field. DOE M 435.1-1, Chapter IV, Low-Level Waste Requirements,
includes the detailed low-level waste disposal requirements. At the Headquarters level, the
Deputy Assistant Secretaries for Waste Management and Environmental Restoration are
responsible for reviewing and approving the performance assessments and composite analyses (or
reviewing appropriate CERCLA documentation) for low-level waste disposal facilities and for
issuing disposal authorization statements. For purposes of DOE O 435.1 and DOE M 435.1-1,
the term “appropriate CERCLA documentation” means the written materials prepared to
demonstrate compliance with the substantive requirements of DOE M 435.1-1 for low-level waste
disposal facilities managed under CERCLA. Specifically included in such written materials are
crosswalks between CERCLA requirements and DOE M 435.1-1 requirements which are used as
the basis for issuance of a disposal authorization by the Deputy Assistant Secretary for
Environmental Restoration.
Low-Level Waste Performance Assessment and Composite Analysis Reviews. Performance
assessments are conducted to demonstrate that there is a reasonable expectation that low-level
waste disposed of at a DOE facility will not result in exceeding low-level waste disposal facility
performance objectives contained in DOE M 435.1-1, Chapter IV, Low-Level Waste
Requirements, and related performance measures associated with protection of the public from
disposed low-level waste. Composite analyses are conducted as a planning tool to analyze the
interaction of other radioactive source terms at a site along with the low-level waste disposal
facility to minimize the likelihood that current low-level waste disposal activities will result in the
need for future corrective or remedial actions, and to protect the public and environment,
consistent with Departmental limits on total allowable public doses of radiation from all sources.
Performance assessments and composite analyses are reviewed to determine that they are
complete, comprehensive, reflective of site- and facility-specific conditions, are supported by
appropriate rationale, and therefore, are defensible. These reviews are performed to provide the
information to the Deputy Assistant Secretary for Waste Management or the Deputy Assistant
Secretary for Environmental Restoration to conclude there is a reasonable expectation that the
disposal performance objectives of Chapter IV will be met and will continue to be met.
Section 53
Review Panel. The Deputy Assistant Secretaries for Waste Management and Environmental
Restoration must formally establish a panel or group to review performance assessments and
composite analyses. At the time of issuance of DOE O 435.1 and DOE M 435.1-1, the Low-
Level Waste Disposal Facility Federal Review Group was established by the Deputy Assistant
Secretaries for Waste Management and Environmental Restoration to manage the reviews of low-
level waste disposal facilities prepared in accordance with DOE 5820.2A and DNFSB 94-2
commitments and make recommendations regarding performance assessment and composite
analysis approvals and issuance of disposal authorization statements. The Low-Level Waste
Disposal Facility Federal Review Group has been guided by the Department of Energy LLW
Disposal Facility Federal Review Group Performance Assessment and Composite Analysis
Chapter I - General Requirements and Responsibilities
I-60 DOE G 435.1-1
7-09-99
Review Guidance Manual, Revision 0. Following issuance of DOE O 435.1, Revision 0 of the
Low-Level Waste Disposal Facility Federal Review Group Manual will be revised to reflect any
new guidance for reviews and approvals of performance assessments and composite analyses in
accordance with DOE O 435.1 and DOE M 435.1-1 and will be issued as a DOE G 435.1-1
guide. The Low-Level Waste Disposal Facility Federal Review Group reports its findings on
performance assessment and composite analysis reviews directly to the Deputy Assistant
Secretaries.
Example: The Brown Site Low-Level Waste Disposal Facility Composite Analysis is
submitted to Headquarters by the Field Element Manager for review. The Deputy
Assistant Secretaries for Waste Management and Environmental Restoration convene the
Low-Level Waste Disposal Facility Federal Review Group, who in turn selects a Team
Leader to form the Brown Site Review Team to evaluate the Brown Site composite
analysis against the Review Guide. The Low-Level Waste Disposal Facility Federal
Review Group prepares a report based on the Brown Site Team review and submits their
findings to the Deputy Assistant Secretary, Office of Waste Management. Based on the
Low-Level Waste Disposal Facility Federal Review Group’s findings, the Deputy
Assistant Secretary makes a decision on approval of the composite analysis.
Performance Assessments and Composite Analysis Approvals & Issuance of Disposal
Authorization Statement. A review of a performance assessment and/or composite analysis
performed by the Low-Level Waste Disposal Facility Federal Review Group or a similar review
panel produces a report in the form of a compliance evaluation that is transmitted to the
appropriate Deputy Assistant Secretary. The report recommends whether the disposal facility
operations are to be approved, approved with conditions, or disapproved. The Review Guide
contains detailed guidance on the compliance evaluation and approval recommendation.
Section 54
The Deputy Assistant Secretary is responsible for issuing a disposal authorization statement in
accordance with DOE M 435.1-1, Section IV.P.(5). The disposal authorization statement
provides Headquarters approval of the performance assessment and/or composite analysis, and
includes conditions deemed necessary for long-term protection of the public and the environment
from the low-level waste disposal facility. In this fashion, the disposal authorization statement
should be viewed as analogous to a license for a low-level waste disposal facility that would be
issued by the U.S. Nuclear Regulatory Commission or an Agreement State. The disposal
authorization statement will be issued to the Field Element Manager responsible for the disposal
facility. The Field Element Manager must consider any conditions in the disposal authorization
statement that are to be incorporated into the radioactive waste management basis (see DOE M
435.1-1, Section IV.D.(4)) for the facility. Additional detailed guidance on disposal authorization
statements can be found in the guidance on DOE M 435.1-1, Chapter IV, Low-Level Waste
Requirements.
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-61
7-09-99
Example: The Deputy Assistant Secretary for Waste Management and the Deputy
Assistant Secretary for Environmental Restoration jointly issue the Disposal
Authorization Statement Concerning Operation of the Brown Site Low-Level Waste
Disposal Facility to the Field Element Manager. The Statement refers to the compliance
evaluation prepared by the Brown Site Composite Analysis Review Team, which contains
six conditions that must be implemented at the facility in order for operations to continue
safely in accordance with the performance objectives. The compliance evaluation was
reviewed by the Low-Level Waste Disposal Facility Federal Review Group, which
transmitted its recommendation for approval with conditions, those conditions and a
draft disposal authorization statement to the Deputy Assistant Secretaries.
CERCLA Documentation. As discussed in guidance for DOE M 435.1-1, Section I.2.F.(5),
Environmental Restoration, Decommissioning and Other Cleanup Waste, environmental
restoration remedies involving the development and management of radioactive waste disposal
facilities under the CERCLA process are to meet the substantive requirements of DOE O 435.1.
The original guidance on this topic was articulated in: 1) Policy for Demonstrating Compliance
with DOE 5820.2A for Onsite Management and Disposal of Environmental Restoration Low-
Level Waste under the Comprehensive Environmental Response, Compensation, and Liability
Act, May 31, 1996 (DOE, 1996); and 2) Guidance for Complying With DOE 5820.2A,
Radioactive Waste Management, for Onsite Management and Disposal of Low-Level Waste
(LLW) from Environmental Restoration Activities (Alm, 1997). The major concepts of these
policies are:
C The CERCLA requirements and DOE M 435.1-1 requirements include significant
overlap in their substantive requirements given both are designed to ensure safe
management and disposal of waste;
C The CERCLA process is to be used to comply with the requirements of DOE
M 435.1-1 for environmental restoration actions;
C The substantive requirements of DOE M 435.1-1 should be directly incorporated
into the CERCLA process to the extent practical and consistent with site-specific
technical and regulatory issues; and
Section 55
C The Department must demonstrate compliance with the substantive requirements
of DOE M 435.1-1 to fulfill its responsibilities under the Atomic Energy Act of
1954, as amended.
When a proposed environmental restoration response at DOE sites on the National Priorities List
(NPL) involves the development and management of a radioactive waste management facility, the
CERCLA process will be used to assess the performance of the disposal facility. Subject to final
Chapter I - General Requirements and Responsibilities
I-62 DOE G 435.1-1
7-09-99
regulatory approval, the CERCLA process is expected to incorporate the substantive
requirements of DOE M 435.1-1 as described in this section. For sites not on the NPL, DOE may
initiate a response action in accordance with CERCLA under the authority assigned by Executive
Order 12580, Superfund Implementation. In this case, if the remedy under consideration involves
the development and management of a radioactive waste disposal facility, then the requirements
of DOE M 435.1-1 are to be incorporated into the CERCLA documentation as described in this
section, as appropriate, subject to final regulatory approval. There may be situations at non-NPL
sites where DOE chooses to implement a remedy using its authority under the Atomic Energy Act
of 1954, as amended, in which case the procedural requirements of DOE M 435.1-1 would also
apply.
When consideration is being given to a cleanup response that requires development and
management of a radioactive waste disposal facility under CERCLA, in most cases an analysis
satisfying the requirement for a performance assessment will be prepared as part of the project-
specific CERCLA document. The analysis is often contained in the Feasibility Study and is
prepared in accordance with the National Contingency Plan (40 CFR Part 300). In some cases,
an analysis will be performed which includes an evaluation of all interactive sources near the
proposed disposal facility, as suggested in EPA’s Risk Assessment Guidance for Superfund:
Human Health Evaluation Manual, Part A, Interim Final. This analysis would essentially be
equivalent to a composite analysis. If the CERCLA analysis does not include evaluation of all
interactive sources at the proposed radioactive waste disposal facility, then a separate composite
analysis is to be prepared. This separate analysis may be incorporated into the CERCLA process,
including review by the regulatory agencies and stakeholders, or it may be handled as a document
that is reviewed by the Low-Level Waste Disposal Facility Federal Review Group (LFRG)
established under the authority of DOE M 435.1-1.
To fulfill DOE’s responsibilities under the Atomic Energy Act of 1954, as amended, the
Department must demonstrate compliance with the substantive requirements of DOE M 435.1-1
for low-level waste disposal facilities managed under CERCLA. A crosswalk between the
CERCLA and the DOE M 435.1-1 requirements needs to be prepared and reviewed as described
below when the cleanup action involves development and management of a radioactive waste
disposal facility. It is not necessary to prepare a crosswalk to demonstrate compliance with DOE
M 435.1-1 requirements for environmental restoration activities that do not involve development
and management of a radioactive waste disposal facility.
Section 56
The appropriate CERCLA documentation is to be submitted by the Field Element Manager to the
Deputy Assistant Secretary for Environmental Restoration. For purposes of DOE O 435.1 and
DOE M 435.1-1, the term “appropriate CERCLA documentation” means the written materials
prepared to demonstrate compliance with the substantive requirements of DOE M 435.1-1 for
low-level waste disposal facilities managed under CERCLA. Specifically included in such written
materials are crosswalks between CERCLA requirements and DOE M 435.1-1 requirements
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-63
7-09-99
which are used as the basis for issuance of a disposal authorization by the Deputy Assistant
Secretary for Environmental Restoration. Based on the appropriate CERCLA documentation, the
Field Element Manager certifies that compliance with the substantive requirements of DOE M
435.1-1 has been achieved through application of the CERCLA process. Any other analyses that
have not been incorporated into the CERCLA process require a separate review. The Deputy
Assistant Secretary may assign the LFRG the task of reviewing the information submitted by the
Field Element Manager. In this instance, the documents would be reviewed against the criteria set
forth in the guidance entitled Department of Energy LLW Disposal Facility Federal Review
Group Performance Assessment and Composite Analysis Review Guidance Manual (the Review
Guide). Based on the content of the crosswalk, the LFRG will determine whether it needs to
review the detailed analysis. The Low-Level Waste Disposal Facility Federal Review Group will
report its conclusions from this review to the Deputy Assistant Secretary for Environmental
Restoration. The Deputy Assistant Secretary for Environmental Restoration will use this
information as the basis for deciding whether to issue a disposal authorization based on DOE’s
responsibilities under the Atomic Energy Act of 1954, as amended.
The disposal authorization statement does not impact the decision documented in the CERCLA
Record of Decision on whether to build a facility because this decision is made through the
CERCLA process. The disposal authorization statement specifies the limits and conditions on
design, construction, operation, and closure of the radioactive waste disposal facility. The
disposal authorization statement could be included as part of the Record of Decision. If this is the
case, then the guidance on disposal authorization (Chapter IV) should be followed during the
development of the ROD on CERCLA radioactive waste disposal facilities, to the extent practical.
However, it should be understood that compliance with requirements of a law (e.g., CERCLA)
does not release DOE of compliance with another law (e.g., Atomic Energy Act of 1954, as
amended). DOE must determine that whatever actions are taken, Atomic Energy Act
requirements are met.
Example: The remedial action on Operable Unit 34 at Site Q considers construction and
operation of a facility for onsite low-level waste disposal. The CERCLA RI/FS contains
analyses equivalent to the performance assessment and composite analysis required in
DOE M 435.1-1. The site prepares a crosswalk between the CERCLA NCP and DOE M
435.1-1 requirements that demonstrates that the RI/FS documents contain the substantive
requirements of DOE M 435.1-1. The Low-Level Waste Disposal Facility Federal
Review Group evaluates the crosswalk and, if necessary, selected supporting
documentation against the guidance and criteria in the Review Guide, and presents their
conclusions to the Deputy Assistant Secretary for Environmental Restoration. Based on
the evaluation and conclusions, the Deputy Assistant Secretary for Environmental
Restoration decides whether to issue a Disposal Authorization.
Section 57
Chapter I - General Requirements and Responsibilities
I-64 DOE G 435.1-1
7-09-99
Demonstrating Compliance. Compliance with this requirement is demonstrated by:
C Establishment of qualified panels to conduct reviews of performance assessments,
composite analyses, and, as requested, appropriate CERCLA documentation for
environmental restoration activities involving the development and management of
a radioactive waste disposal facility;
C Performance of the reviews by the panels and use of the results that leads to a
decision on operations and long-term protectiveness of a low-level waste disposal
facility, or compliance with 40 CFR Part 191 for a transuranic waste disposal
facility; and
C Documentation of such decisions for low-level waste disposal facilities in a
disposal authorization statement issued by the appropriate Deputy Assistant
Secretary (for Waste Management or for Environmental Restoration) to the
cognizant Field Element Manager. The disposal authorization statement contains
conditions that the disposal facility must meet in order to operate under an
approved radioactive waste management basis. For environmental restoration
activities, if the CERCLA Record of Decision is to serve as the disposal
authorization statement, it must include the same information as stated above, or
the disposal authorization statement can be issued separately.
Supplemental References:
1. DOE, 1999. Format and Content Guide for U.S. Department of Energy Low-Level Waste
Disposal Facility Performance Assessments and Composite Analyses (in preparation),
DOE G 435.1-1, U.S. Department of Energy, Washington, D.C., 1999.
2. DOE, 1999. Review Guide for U.S. Department of Energy Low-Level Waste Disposal
Facility Performance Assessments and Composite Analyses (in preparation), DOE G
435.1-2, U.S. Department of Energy, Washington, D.C., 1999.
3. DOE, 1999. Maintenance Guide for U.S. Department of Energy Low-Level Waste
Disposal Facility Performance Assessments and Composite Analyses. (in preparation),
DOE G 435.1-3, U.S. Department of Energy, Washington, D.C., 1999.
4. EPA, 1985. “Final Rule; Environmental Standards for the Management and Disposal of
Spent Nuclear Fuel, High-Level and Transuranic Radioactive Wastes,” Federal Register,
Vol. 50, No. 182, U.S. Environmental Protection Agency, Washington, D.C., September
19, 1985.
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-65
7-09-99
5. EPA, 1989. Risk Assessment Guidance for Superfund, Vol. 1, Human Health Evaluation
Manual (Part A), Interim Final, EPA/540/1-89/002, U.S. Environmental Protection
Agency, Washington, D.C., December 1989.
6. EPA, 1993. “Final Rule; Environmental Radiation Protection Standards for the
Management and Disposal of Spent Nuclear Fuel, High-Level and Transuranic
Radioactive Wastes,” Federal Register, Vol. 58, No. 242, U.S. Environmental Protection
Agency, Washington, D.C., December 20, 1993.
7. DOE 1996. Interim Format and Content Guide, and Standard Review Plan for U.S.
Department of Energy Low-Level Waste Disposal Facility Performance Assessments,
U.S. Department of Energy, Washington, D.C., October 1996.
8. DOE 1996. Interim Review Process and Criteria for Department of Energy Low-Level
Waste Disposal Facilities Composite Analyses, U.S. Department of Energy, Washington,
D.C., November 1, 1996.
9. DOE, 1996. Interim Guidance for a Composite Analysis of the Impact of Interacting
Source Terms on the Radiological Protection of the Public from Department of Energy
Low-Level Waste Disposal Facilities, U.S. Department of Energy, Washington, D.C.,
October 1996.
Section 58
10. DOE, 1998. Department of Energy LLW Disposal Facility Federal Review Group,
Performance Assessment and Composite Analysis Review Guidance Manual, Revision 0,
U.S. Department of Energy, Washington, D.C., September 1998.
I.2.E.(2) Site Closure Plans. Reviewing and approving closure plans and other
closure documentation for deactivated high-level waste facilities/sites
and issuing authorization for closure activities to proceed.
Objective:
The objective of this requirement is to ensure that closure activities for deactivated high-level
waste facilities/sites do not proceed prior to the review/approval of the site closure plans .
Discussion:
The scope of the requirement, and this guidance, applies only to deactivated high-level waste
closure plans, and other closure documents, e.g., CERCLA documentation, developed in
accordance with the requirements of DOE M 435.1-1, Chapter II.U., Closure. The requirement
Chapter I - General Requirements and Responsibilities
I-66 DOE G 435.1-1
7-09-99
does not apply to the Decommissioning path documentation required by Section II.U. The
documentation and review/approval requirements for this path are defined in DOE O 430.1A and
DOE 5400.5 and are not repeated in this guidance.
This requirement is to be implemented by the Offices of the Deputy Assistant Secretary for Waste
Management and the Deputy Assistant Secretary for Environmental Restoration, and their staff.
However, since the requirement requires prior review and approval by the submitting Field
Element Manager, guidance for Section I.2.F.(8), Closure Plans, should be consulted in
implementing this requirement.
During the development of the requirements for DOE O 435.1 and DOE M 435.1-1, one
high-level waste site was in the process of initiating closure activities for storage tanks.
Additionally, DOE was in the process of responding to DNFSB Recommendation 94-2 related to
the performance of low-level waste disposal facilities. These two activities required consistency
in implementation, and influenced the final requirements. Closure is the final waste management
function performed, yet the potential hazards from residual radioactive material within the facility
or at the site must be assessed to determine their suitability for unrestricted use of the facility/site;
or, if not suitable for unrestricted access, to determine the activities necessary to be incorporated
into the site closure plan to protect members of the public, workers, and the environment. The
development, review and approval, and implementation of high-level waste facility/site closure
plans and other closure documentation are crucial functions in assuring that closure will be, and is
being, conducted safely and effectively, and that the closed facilities/sites will remain safe.
Objectives of the DOE Headquarters Review and Approval. Closure of deactivated high-level
waste facilities can be executed under three paths, as explained in the requirement and guidance
for closure in DOE M 435.1-1, Section II.U. Closure conducted by the first path,
Decommissioning, performed under the provisions of DOE O 430.1A and DOE 5400.5, is not
discussed in this guidance. Refer to these Orders, and guidance, for details on documentation
requirements and review/approval requirements. For the remaining two closure paths, CERCLA
(Section II.U.(2)) and Closure Plans (Section II.U.(3)), the Deputy Assistant Secretary for Waste
Management or the Deputy Assistant Secretary for Environmental Restoration, as appropriate,
must review and approve the appropriate closure documentation and issue an authorization to
proceed with closure activities. This authorization is required prior to the commencement of
remedial actions or activities that cannot be reversed without expending significant resources.
Such activities include, for example, remedial actions such as decontamination activities or the
placing of immobilization materials in a deactivated high-level waste tank. Excluded are such
activities as design and field survey work which are needed to support the development of a
closure plan or other documentation.
Section 59
As discussed in the guidance to Section II.U, closure plans are expected to be two-tier
documents, i.e., their development and review/approval are expected to be conducted in two
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-67
7-09-99
phases. This multi-phase process is considered necessary because much of the data needed may
not be available initially, but becomes available as engineering data and/or other
documents/permits are developed. Headquarters review and approval is primarily focused on the
first tier plans, from which subsequent plans are developed.
The first tier plan, which is to be approved by the Deputy Assistant Secretaries for Waste
Management and/or Environmental Restoration (Section I.2.E.(2)), is intended to define and
bound the parameters of a closure action(s). This level of closure plan should include, at a
minimum the following:
C closure methodology;
C schedules and assumptions
C site or individual closure standards/performance objectives;
C allocation of closure standard/performance objective budgets to individual
facilities/sites;
C assessment (preliminary) of the projected performance of each unit to be closed
relative to the allocated performance objectives;
C assessment (preliminary) of the projected composite performance of all units to be
closed at the site;
C alternatives (if any);
C waste characterization data;
C closure controls plans; and
C stakeholder concerns.
While the availability of some of the above information may be limited and therefore preliminary,
it is necessary to ensure that a credible, bounding review can be conducted by DOE Headquarters.
The Deputy Assistant Secretaries for Waste Management and/or Environmental Restoration are
responsible for issuing an authorization to proceed with closure activities to the responsible Field
Element Manager. This authorization to proceed with closure activities represents DOE
Headquarters approval of the first tier site closure plan, or other closure documentation, as
adequately representing and assessing the closure action planned. In addition, the authorization to
proceed with closure activities contains any conditions on which the approval of the plan or
documentation is based.
As discussed in the guidance to Section II.U., once approved it is expected that closure plans will
be updated periodically, as determined by the Field Element Manager, to reflect revised analysis
and the status of individual facility closure actions that are part of a site closure. However, once
DOE Office of Environmental Management review/approval is gained on the first tier
documentation and an authorization to proceed is issued, additional DOE Office of Environmental
Management approvals are not required provided the bounding conditions defined in the DOE
Chapter I - General Requirements and Responsibilities
I-68 DOE G 435.1-1
7-09-99
Office of Environmental Management-approved first their plan(s) are not exceeded. (See the
guidance for Section II.U for an example.)
Section 60
The assessments of the projected performance of each unit to be closed and the assessment of the
projected composite performance of all units to be closed are critical to deactivated high-level
waste facility closure activities. Therefore, the DOE Headquarters technical review includes the
determination of the adequacy of these analyses to establish the expected performance of the
closed facility/site, the potential hazards, and the activities necessary to protect members of the
public, workers and the environment. The review and approval of the assessment/analysis is
extremely important to ensure that the assumptions regarding source term, leach rates, transport
mechanisms, analytical transport models, hydrologic and other critical aspects of the site,
effectiveness of any barriers to migration of radionuclides on which performance is based, and
other key assumptions are supported by the available data. Furthermore, uncertainties associated
with the key assumptions and are data addressed through identification of compensatory
measures, through combinations of conservatism in the estimates, defense-in-depth, or other
appropriate measures. The review specifically examines and documents the conclusions of the
review with respect to the adequacy of each of these key assumptions.
The reviews of the assessment of performance or composite analysis documentation provide the
basis for approving/disapproving the evaluations contained within them. The Deputy Assistant
Secretary with authority over the facility/site is responsible for issuing an authorization to proceed
with closure activities to the responsible Field Element Manager. The authorization to proceed
with closure activities represents DOE Headquarters approval of the site closure plan, and other
closure documents as adequately representing and assessing the closure action planned. This
includes the acceptance of the assessment of performance and composite analysis, the
identification of long-term hazards, and establishment of the necessary closure activities to ensure
the protection of the public and the environment. In addition, the authorization to proceed with
closure activities contains the conditions on which the approval of the plan or documentation is
based.
Example: The authorization to proceed with closure activities for deactivated high-level
waste Tank XYZ at Site A specifically lists the key assumptions on which the performance
is based (e.g., source term for the specific tank and for other contributors, leach rates,
transport mechanisms, transport models, hydrologic and other critical aspects of the site,
assigned effectiveness of barriers to retard the migration of radionuclides, the
uncertainties in the available data and the measures incorporated in the plan to account
for uncertainties), and the controls (e.g.,the boundary for institutional controls to restrict
access, and the time period for the restriction) necessary for the long term protection of
the public, workers, and the environment both during and after closure.
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-69
7-09-99
Process for Review and Approval of Site Closure Plans and Other Closure Documents. The
Deputy Assistant Secretaries for Waste Management and Environmental Restoration should
establish a cohesive and systematic process to evaluate the technical adequacy of the submitted
closure plans and other closure documents including the assessments of performance or composite
analysis, and to formulate recommendations to the Deputy Assistant Secretaries regarding
approval/disapproval of the plan, and the potential issuance of authorization for the closure
activities to proceed. This process should include the following elements:
Section 61
1. Acceptance Review--Determine that the closure plan is acceptable detailed
technical evaluation by determining that all the essential elements of the plan as
outlined in the requirement in DOE M 435.1-1, Section II.U, and the associated
guidance, are contained in the plan.
2. Review Team--A review team is established whose members include subject matter
experts from Headquarters or the field who do not, by virtue of their current or
past alignments, have a conflict of interest that would prevent an objective and
effective review.
3. Review Team Responsibilities--The responsibilities of the team members are
established as well as the administrative procedures, to include quality assurance,
by which the review will be conducted and documented.
4. Site Visits--The process for conducting site visits is established, whenever it is
determined by the team members to be prudent for such visits in order to acquaint
the team members with the actual circumstances of the facility/site and thus
prepare them to conduct the evaluation of the documentation.
5. Technical Reviews--A overall strategy for evaluating the assessment of
performance and composite analysis and other closure technical documentation is
established, and includes the specific criteria on which the team is to render its
findings. A detailed plan to conduct the review is prepared and assignments made
to team members based on their expertise and experience.
6. Reporting--An outline of the report is established which contains the findings of
the review team with respect to each criterion, a recommendation on the adequacy
of the closure plan and a recommendation relative to issuance of an authorization
to proceed with closure activities. The report contains any other essential elements
that the Deputy Assistant Secretaries may require on which to base their decision.
The Low-Level Waste Disposal Facility Federal Review Group Manual provides a systematic
process that can be tailored to provide a documented process for review of site closure plans, and
Chapter I - General Requirements and Responsibilities
I-70 DOE G 435.1-1
7-09-99
other closure documents, for deactivated high-level waste facilities/sites and the issuance of an
authorization to proceed with closure activities. The process should be interactive, involving the
subject matter experts and the field site personnel to obtain clarifications and additional data as
required to support the review and approval activities.
Analysis conducted during the performance assessment and composite analysis needs to be
integrated into closure planning. Conversely, any information that becomes available during the
closure operations, or any changes made to closure of the facility, that impact the analysis in the
assessment of performance and composite analysis needs to be incorporated into these evaluations
in a reasonable period of time to determine the extent of their impact. When major impacts are
identified or when major changes are required to the closure plan that affect the conditions or the
controls as contained in the authorization to proceed with closure activities, it is the Field Element
Manager’s responsibility to conduct a review and re-approve the revised analysis. In addition, it
is the Field Element Manager’s responsibility to inform the appropriate Deputy Assistant
Secretary of the changes. Upon receipt of such notification, the Deputy Assistant Secretary
reviews the changes and determines what action, if any, is required. At a minimum, the revised
closure plan or analysis is distributed to organizations that have an interest in it.
Section 62
Compliance with this requirement is demonstrated by:
C The authorization to proceed with closure activities at the facilities/sites contains
the conditions for authorization, and the controls necessary to protect the public,
workers, and the environment during and after closure;
C Physical closure activities for high-level waste deactivated facilities/sites do not
proceed prior to the review and approval of closure plans by the appropriate
Deputy Assistant Secretary (based on a formal documented review process) and
the issuance of an authorization(s) to proceed with closure activities at the
facilities/sites;
C Closure operations are actively monitored by the Field Element Manager to
ascertain compliance with the conditions and controls as contained in the
authorization, and to ensure that whenever any information that becomes available
during the closure operations, or any changes made to closure of the facility that
impact the analysis in the assessment of performance and composite analysis are
incorporated into these evaluations to determine the extent of their impact; and
C The appropriate Deputy Assistant Secretary requires site closure plans and other
closure documents to be re-submitted for review and approval when analysis
indicates the bounding conditions within the first tier plans or documents may be
exceeded.
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-71
7-09-99
Supplemental References:
1. DOE, 1998. Low Level Waste Disposal Facility Federal Review Group Manual, Revision
0, U.S. Department of Energy, Washington, D.C., September 1998.
Chapter I - General Requirements and Responsibilities
I-72 DOE G 435.1-1
7-09-99
I. 2.F. Field Element Managers.
Field Element Managers are responsible for:
(1) Site-Wide Radioactive Waste Management Programs. Developing,
documenting, implementing, and maintaining a Site-Wide Radioactive
Waste Management Program. The Program shall use a systematic approach
for planning, executing, and evaluating the site-wide management of
radioactive waste in a manner that supports the Complex-Wide Radioactive
Waste Management Programs and ensures that the requirements of
DOE O 435.1, Radioactive Waste Management, and this Manual are met.
Objective:
The objective of this requirement is to ensure that radioactive waste is managed in a safe,
effective, and efficient manner; radioactive waste management activities are integrated,
coordinated, and support site-wide and complex-wide goals and objectives; and progress towards
goals and objectives are measured and evaluated, and feedback is provided for continued
improvement of the management of radioactive waste. Additionally, the requirement is to ensure
there are mechanisms in place for providing input to and receiving direction from the
complex-wide programs.
Discussion:
Sites with radioactive waste shall develop and document a Site-Wide Radioactive Waste
Management Program. To the extent practical, the site-wide program and documentation
requirement may be met by existing site programs and documents. Multiple programs or
documents can be used or existing programs or documents can be supplemented to meet this
requirement. While the use of existing programs or documents to meet this requirement is
encouraged, what constitutes the site-wide program and its associated documentation is to be
clearly defined and maintained so that ambiguity is avoided. Implementing and maintaining the
Site-Wide Radioactive Waste Management Program should be addressed in site-specific
procedures. These procedures should require periodic review of the Site-Wide Radioactive
Waste Management Program, and review whenever there is a change to complex-wide programs
or plans, site-specific radioactive waste management activities, or DOE policy or directives
regarding the management of radioactive waste. These reviews should evaluate the status of the
Site-Wide Radioactive Waste Management Program and its associated documentation and the
program’s continued validity over time or under the changed circumstances.
Section 63
The site-wide program addresses all of the site’s radioactive waste, including any off-site
radioactive wastes managed by the site. Additionally, all radioactive waste is to be categorized
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-73
7-09-99
and managed as high-level, transuranic, low-level, or mixed low-level waste to facilitate
consistent, efficient, and effective management of radioactive waste among sites. Guidance on the
categorization and management of radioactive waste can be found in Section I.1.C.
The site-wide program provides for the systematic planning, execution, and evaluation of site
radioactive waste management activities in a manner that supports the Complex-Wide Radioactive
Waste Management Programs. The site-wide program incorporates the direction of the complex-
wide programs into site-level planning, execution, and evaluation activities as appropriate. The
site-wide program reflects complex-wide direction and also includes site-specific activities
necessary to accomplish site missions and result in the safe, effective, and efficient management of
radioactive waste in a proactive manner. The site-wide program includes mechanisms for
providing input into the complex-wide programs (such as radioactive waste inventories and
projections and the identification of technical and programmatic issues and other constraints).
The complex-wide and site-wide programs are to be integrated and provide input in both
directions. The Complex-Wide Radioactive Waste Management Programs and program plans
guidance can be found in Sections I.2.B and I.2.D.
The site-wide program provides personnel with an understanding of the site’s radioactive waste
management needs and the strategy for meeting those needs; identifies the organizational
responsibilities and the facilities and methods that will be used by the site to meet those needs; and
establishes evaluation and feedback programs to facilitate continuous improvement of the
site-wide program. The program should implement the requirements of DOE M 435.1-1 and
other directives and regulations such as those listed in DOE M 435.1-1, Section VI.1.D (e.g.,
radiation protection requirements of DOE 5400.5 and 10 CFR Part 835, quality assurance
requirements of DOE O 414.1 and 10 CFR 830.120) for waste management activities.
The Field Element Manager is assigned the responsibility for the Site-Wide Radioactive Waste
Management Program. This establishes a clear management responsibility for radioactive waste
management activities at a site. It is the Field Element Manager’s responsibility to decide how to
meet this requirement. A site may have separate programs for each waste type at the site or one
program that addresses all waste types at the site, however, it is not important that each site have
one single program.
Example: At a site that manages mostly transuranic waste, but also small amounts of
low-level and mixed low-level waste, the Field Element Manager has one program that
addresses all three waste types. At another site where large amounts of high-level and
low-level waste are managed by different organizations, the Field Element Manager has
two separate programs. In this situation, the interface between the programs (with
respect to the generation of low-level waste, including waste incidental to reprocessing,
under the high-level waste program and its transfer to the low-level waste program)
should be addressed.
Chapter I - General Requirements and Responsibilities
Section 64
I-74 DOE G 435.1-1
7-09-99
Additionally, each site may have a Site-Wide Radioactive Waste Management Program or several
sites may be covered under one program.
Example: A Field Element Manager is responsible for the management of DOE
radioactive waste at a DOE site and three off-site locations. Based on the types of waste
being managed and the organizations involved, the Field Element Manager develops and
supports two programs. One program covers the radioactive waste at the primary DOE
site and a separate program covers the radioactive waste at the three off-site locations.
The rationale for this approach is included in the documentation for each program.
In addition to its role defining the radioactive waste program at a site, the documented Site-Wide
Radioactive Waste Management Program may also serve as the site’s end-state description for
radioactive waste at that site, or as a primary reference document for such a plan. A well-
documented Site-Wide Radioactive Waste Management Program could significantly facilitate
development of radioactive waste end-state documents at individual sites.
Systematic Approach. Applying a systematic approach for planning, executing, and evaluating the
site-wide management of radioactive waste facilitates the integration and coordination of
radioactive waste management activities across both the site and the DOE complex. In addition,
it provides a framework within which the site can identify and communicate a logical approach for
effecting waste management activities (planning), manage waste in a manner that is protective of
worker, the public, and the environment (executing), and provide measures of progress towards
completing site and complex-wide goals, as well as generating feedback to support continuous
improvement of the radioactive waste management program (evaluating).
The following sections describe components that are part of a systematic approach to waste
management. Whereas there are various methods of implementing a systematic approach, each
will generally include some common elements. The most basic element is defining the mission or
what the program intends to accomplish. Another common element is the identification of the
functions or what needs to be done to accomplish the mission. At the top level, these functions
are the program planning, execution, and evaluation. Within the execution function are the
functions necessary for management of the waste, generally identified as generation, storage,
treatment, and disposal. Another key element is the identification and implementation of
requirements and constraints. These include regulatory requirements, commitments or
agreements with regulatory or oversight bodies, programmatic requirements, and technical or
process requirements.
Planning. Applying a systematic approach to planning results in a process which can be
used to support decision-making related to radioactive waste management activities and
should involve consideration of the following topics which are discussed below in more
detail:
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-75
7-09-99
C Establishing goals, objectives, and milestones;
C Establishing priorities and prioritizing the goals, objectives, and milestones;
C Describing the radioactive waste management boundaries and interfaces;
C Waste projections;
C Identifying the constraints and assumptions;
C Establishing the integrated site strategy;
C Performing life-cycle radioactive waste management planning;
Section 65
C Defining the schedule; and
C Identifying funding needs.
Goals, Objectives, and Milestones. Long-range goals, interim objectives, and specific
milestones, meaningful to the program are to be established. The site-wide program goals
should reflect complex-wide direction as well as site-specific goals. The site-wide
program should also include site-specific activities necessary to accomplish site missions
and result in the safe, effective, and efficient management of radioactive waste in a
proactive manner and support the complex-wide established goals, objectives, and
milestones as appropriate. Goals, which are long-range in nature, should include
descriptions of end-state conditions for facilities, operations, activities, or waste
categories, and should be challenging yet achievable. Interim objectives and specific
milestones should be established to provide measurements of progress towards goals.
Example 1:
Complex-wide goal: close high-level waste storage tanks.
Supporting site-wide goal: complete closure of all high-level waste storage tanks
at the site.
Objective: complete closure of all high-level waste storage tanks in Area 1 by
December 2010.
Specific milestones:
- Complete negotiations with State regulators on criteria for tank
closures–August 1999.
- Gain acceptance by DOE Headquarters and technical assistance from NRC
on guidelines for determining residual tank waste is incidental to
reprocessing–February 2000.
- Complete partial closure of Tank 1A–September 2002.
- Complete partial closure of Tank 1B–June 2003.
- Complete partial closure of Tank 1C–October 2005.
Chapter I - General Requirements and Responsibilities
I-76 DOE G 435.1-1
7-09-99
Example 2:
Complex-wide goal: dispose of all defense transuranic waste at the Waste
Isolation Pilot Plant.
Supporting site-wide goal: ship all defense transuranic waste stored at the site to
the Waste Isolation Pilot Plant.
Objective: begin shipping transuranic waste to the Waste Isolation Pilot Plant
(WIPP) by May 2008.
Specific milestones:
- Develop and get WIPP approval of waste certification program-June 1999.
- Initiate retrieval of waste from bermed storage-January 2001.
- Complete preparation and authorization of TRUPACT-II loading facility-
March 2003.
- Complete retrieval of waste from bermed storage-September 2005.
- Ship 2000 cubic meters of waste to WIPP-May 2008.
Example 3:
Complex-wide goal: dispose of all low-level waste placed in storage prior to
1998.
Site-wide goal: eliminate waste placed in storage at the site prior to 1998.
Objective: reduce volume of legacy waste in storage by 50 percent by December
2000.
Specific milestones:
- Obtain authorization to ship low-level waste to Nevada Test Site-June 1998.
- Begin monthly shipments of 50 drums from Building 300-August 1998.
Priorities and Prioritizing the Goals, Objectives, and Milestones. Site-wide priorities
should be established and then be used to prioritize the site-wide goals, objectives, and
milestones. The site-wide priorities should reflect complex-wide policy and integration
efforts and should also include priorities which reflect site-specific conditions and needs
that will result in the safe, effective, and efficient management of radioactive waste in a
proactive manner. Establishing priorities should involve consideration of providing
protection to workers, the public, and the environment; meeting regulatory requirements,
legal commitments, or agreements; availability of technologies, facilities, and capacities;
and available funding.
Section 66
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-77
7-09-99
Example:
1) Ensure continued safe storage of site radioactive waste inventories.
2) Reduce radiation exposures to workers.
3) Acquire necessary characterization technology, including assay capabilities.
4) Obtain approval of waste certification programs for all generating facilities
at the site.
5) Reduce storage inventories of radioactive waste at the site.
Boundaries and Interfaces. The site-wide radioactive waste management program is to be
clearly defined and described, including: organization and responsibilities; facility,
operation, and activity descriptions; existing and projected radioactive waste inventories;
and storage, treatment, and disposal capacities.
The organizational and functional responsibilities of participants in the site-wide program
and their interrelationships are to be identified and described. In addition to site
organizations, interfaces with both Headquarters and other Field organizations are also
identified and described, as appropriate, including a discussion of their respective roles and
interactions in planning, executing, and evaluating site-wide radioactive waste
management program activities.
Program documentation should include a brief description of the facilities, operations, and
activities that constitute the site-wide radioactive waste management program and the
interfaces between the site facilities, operations, and activities and other site facilities,
operations, and activities, as well as other programs (e.g., Environmental Restoration or
Defense Programs). A brief discussion of new facilities that have been identified as
necessary to implement the radioactive waste management program, and the plans for
funding, constructing, and obtaining authorization to operate these facilities is included at
appropriate.
An accounting of the current radioactive waste inventories and treatment, storage, and
disposal capacities by facility and expected waste generation and receipt projections
should also be included. Site personnel should be made cognizant of the need for accurate
inventory and projection data to support the planning, execution, and evaluation of site-
wide radioactive waste management activities, as well as, the complex-wide programs.
The purpose is to ensure that all radioactive wastes the site is expected to manage and site
capacities are considered in planning, executing, and evaluating site-wide radioactive
waste management activities.
Example: A site develops a document which is the compilation of the information
provided to Headquarters for the “Accelerating Cleanup: Paths to Closure”
Chapter I - General Requirements and Responsibilities
I-78 DOE G 435.1-1
7-09-99
report. This site specific report represents a summary of the site baseline and
includes disposition maps to aid in visualizing the system.
Waste Projections. A primary element in the Complex-Wide Radioactive Waste
Management Program, waste projections should be implemented by the Site-Wide
Programs, where data collection can be made most efficiently.
The methodology used for projecting waste data is to be documented. The major
assumptions used in developing the estimates, the known activities and operations being
undertaken at the facilities included in the projections, and the steps (treatment, storage,
disposal) required for managing the radioactive waste should be included in the
documentation. The estimation techniques used are to rely on documented information
wherever possible, such as Remedial Investigation studies for cleanup projects and
shipment manifests for operational radioactive waste. The information is to be consistent
in detail and content with that being used to characterize ongoing waste generation.
Section 67
The projections data developed through site-wide program should be collected, formatted,
and reported so that they are easily integrated into the Data Management System that is
established under the DOE M 435.1-1, Section I.2.D.(2), Waste Management Data
System. The projections data should also be consistent and collected so that they can be
easily integrated into life-cycle planning; complex-wide configuration of radioactive waste
management facilities; and evaluations of treatment, storage, and disposal facilities
capacities.
Example: As part of the update to the “Accelerating Cleanup: Paths to Closure”
report, a site revises and updates its waste projection data. The data are input
into a complex-wide standardized system and reports are generated.
Constraints and Assumptions. The site radioactive waste management program should
document the significant constraints which affect planning, execution, and evaluation.
These are generally those pre-existing conditions, commitments, or other factors that
affect activities that can be performed or must be performed, or that otherwise limit the
flexibility of the site-wide program. The constraints and assumptions should include basic
tenets and policies adopted by DOE and the site, assumptions made by the site,
interagency agreements, regulatory requirements or commitments (e.g, compliance
orders), records of decision from National Environmental Policy Act evaluations, physical
capacity constraints (space or through-put limits of facilities), and other resource
constraints (e.g., capacity, resources, funding), and direction in the Complex-Wide
Radioactive Waste Management Programs. Uncertainties should be identified along with
the assumptions which provide a basis for proceeding.
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-79
7-09-99
Example 1: Complex-wide basic tenet: disposal of high-level radioactive waste
shall be in accordance with 40 CFR Part 191.
Example 2: Complex-wide assumption: it is assumed that under current
legislative constraints, non-defense transuranic waste will not be disposed of at
WIPP.
Example 3: Site-wide constraint: funds for shipping stored waste to a disposal
facility are limited and will result in only being able to ship 45 percent of the
waste that is ready for shipment.
Example 4: Site-wide assumption: the Q Area disposal facility for non-mixed
low-level waste will continue to operate for the indefinite future.
Integrated Site Strategy. The program is to document the strategy that will be used and
the associated rationale to accomplish the site-wide program goals, objectives, and
milestones. This strategy should address the allocation of funds and resources, consider
the configuration of existing and the need for new physical assets, be based on current and
projected inventories of radioactive waste (including current waste streams, stored waste
with a path to disposal, and stored waste without a path to disposal), support the site
goals, objectives, and priorities, consider land-use (present and future), and respond to
stakeholder input. Incorporation of waste minimization and pollution prevention
philosophies into site-wide radioactive waste management activities, and research and
development needs and activities also are to be addressed in the strategy.
Section 68
Example 1: A site needs to increase its current high-level waste evaporation
capacity to meet the requirements of an agreement with the State regulator. One
option is to enhance the current capacity by upgrading it, however, this may pose
risks to operating personnel in terms of radiation exposure, as well as reduced
evaporator availability and long-term reliability. Another option is to replace the
existing evaporator(s) with a new one, however, this option will require time (e.g.,
Congressional support, State acceptance) to gain project line-item funding. The
selection of the option to upgrade is documented to be consistent with the site-
wide and complex-wide program goals, objectives, and milestones; stakeholder
input; schedule commitments; and expected funding.
Example 2: A site needs transuranic waste assay capability. One option is to
plan for and indicate the activities and schedule for using a portable assay
facility. A second option is to build a new assay facility at the site. The selection
of the option to build a new facility is documented to be consistent with site-wide
program goals, objectives, and milestones; stakeholder input; and schedule
Chapter I - General Requirements and Responsibilities
I-80 DOE G 435.1-1
7-09-99
commitments. The plans for the funding, constructing, and obtaining
authorization to operate the facilities are also documented. The strategy was also
documented to be consistent with complex-wide goals, objectives, and milestones
for making WIPP shipments from the site.
Life-cycle Radioactive Waste Management Planning. It is the intent of the requirement for
life-cycle planning that disposition for all radioactive waste at a site is addressed. By
evaluating all phases in the life-cycle of the waste, adequate capabilities can be provided
and ensured for handling the radioactive waste and identifying any potential issues that
need to be resolved. Life-cycle waste management planning is to address current waste
streams (also see guidance on Waste Generation Planning in Sections II.K, III.H, and
IV.H), stored waste with a path to disposal, and stored waste without a path to disposal.
The following are elements that are to be included in the life-cycle waste management
planning process for a waste stream:
Waste identification - waste is identified in terms of its source (what facilities and
what activities are the sources of the waste), and its characteristics. The waste
characteristics should include radiological, chemical, and physical characteristics
that need to be considered in determining the disposition of waste.
Waste management steps and locations - the steps necessary for managing the
waste are described along with an identification of the specific means for
accomplishing the steps. This should include:
• Characterization/certification;
• Storage;
• Treatment/pre-treatment/immobilization;
• Transportation; and
• Disposal.
Example 1: Site Z generates low-level waste streams which are collected once
a month from three buildings by central waste management. Central Waste
Management certifies it in accordance with an existing certification program
and ships it to the Nevada Test Site for disposal on an arranged schedule.
The life-cycle waste management planning documentation simply includes
that the waste will be characterized in Laboratory L, collected weekly by the
Waste Management Organization and staged in Storage Building S, certified
in accordance with an existing program, and transferred for disposal at
Nevada Test Site Area 5 when sufficient waste to justify a shipment is
available (every 6-8 months).
Section 69
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-81
7-09-99
Example 2: Scheduling waste shipments to the WIPP facility is highly
complex, requiring the scheduling of TRUPACT-II shipping containers and
their associated tractor-trailer units, and the opening and closing of
transportation corridors from each DOE transuranic waste management site
to the WIPP. A site managing transuranic waste would plan site waste
management activities and transportation preparations so that waste is ready
to ship on the schedules identified in the National Transuranic Waste
Management Plan (CAO, 1996b).
Scheduling. A schedule of activities necessary to implement the site-wide program is to
be developed. The schedule should address developing and maintaining the infrastructure
for managing waste and the management of current waste streams, stored waste with a
path to disposal, stored waste without a path to disposal, and projected wastes.
Funding. The site program documentation is to include cost estimates, as appropriate, for
addressing the site-wide management of radioactive waste. These cost profiles should be
consistent with the integrated site strategy and anticipated funding levels. Cost and
budget information should be provided in sufficient detail, by fiscal year, to identify key
programs, activities, and projects. Proposed privatization efforts, planned productivity
improvements, and other efforts of interest should be identified separately.
Execution. The systematic execution of the site waste management program is the actions
taken to manage the waste and develop the attendant documentation. The documentation
is prepared consistent with the site’s management of radioactive waste, operating
procedures, radioactive waste generator requirements (waste characterization, waste
certification, and waste transfer), radioactive waste acceptance requirements, closure
plans, etc.
Example: Documentation of the execution of the waste management activities for a
storage facility include:
- personnel training records,
- safety documentation governing the facility,
- facility waste acceptance criteria and procedures,
- certification program description,
- receipt records,
- certification records,
- waste transfer records,
- monitoring program/procedures,
Chapter I - General Requirements and Responsibilities
I-82 DOE G 435.1-1
7-09-99
- monitoring records, and
- corrective action records.
Evaluation. An important part of any program is evaluating progress in the program.
Progress should be measured and compared with programmatic goals as well as
environmental, health, and safety parameters. A systematic evaluation should include the
following elements:
• Performance Measures - metrics to be used in evaluating performance against
program, environment, health, and safety goals;
• Performance Data - collection of performance data to support the evaluations;
• Performance Evaluation and Reporting - reduction of data interpretation and
evaluation; and
• Feedback - identifying and recommending potential changes in program policies,
strategies, goals, priorities, or interfaces.
Section 70
Example: A site has the goal of eliminating waste placed in storage at the site prior to
the year 2000. The Site’s objective is to reduce volume of waste in storage by 50 percent
by December 2002. A milestone for this goal and objective is obtaining permission to
ship waste in storage to the Nevada Test Site by June 2000, beginning monthly shipments
of 50 drums from Building 300 by August 2000. Performance measures were identified
which would evaluate performance against both the interim objective and specific
milestones since both provide measurable progress towards meeting the goal. For the
objective, the volume of waste in storage was determined and verified. The reduction in
volume of this waste was used to measure progress towards meeting the objective. For
the milestone to obtain permission to ship waste to the Nevada Test Site, the steps were
identified and a schedule developed which ended with receiving permission in June 2000.
This schedule was then used to measure progress towards meeting this milestone. The
performance measures for the monthly shipments were identified assuming shipments
were able to begin in August 2000 and continue through December 2002. The number of
shipments per month and drums per shipment, and the total number of shipments and
drums shipped to date were used as performance measures. The performance data were
collected monthly and compared to the reference data and performance evaluated and
reported. Evaluation indicated that progress towards meeting the specific milestone was
on track to successful completion.
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-83
7-09-99
The process of planning, execution, and evaluation is an iterative process. The lessons learned
from the activities undertaken during one fiscal year, or changes in the assumptions on which the
program strategy was originally based will require revising the program planning.
Compliance with this requirement is demonstrated if a site-wide program plan(s) is developed for
each of the waste types specified in DOE M 435.1-1. The site-wide plan(s) should support the
complex-wide plans by incorporating the direction of the complex-wide plan into site-level
planning, execution, and evaluation activities.
Supplemental References:
1. CAO, 1996a. Waste Acceptance Criteria for the Waste Isolation Pilot Plant, Revision 5,
DOE/WIPP-069, U.S. Department of Energy, Carlsbad Area Office, Carlsbad, NM, April,
1996.
2. CAO, 1997. The National Transuranic Waste Management Program, Revision 1,
DOE/NTP-96-1204, U.S. Department of Energy, Carlsbad Area Office, Carlsbad, NM,
December 18, 1997.
3. CAO, 1997. Generator Site Certification Guide, Revision 1, DOE/CAO-95-2119, U.S.
Department of Energy, Carlsbad Area Office, Carlsbad, NM, August 1997. (users should
refer to the current version).
4. DOE, 1996. Low-Level Waste Projection Program Guide, U.S. Department of Energy,
Office of Waste Management, December 18, 1996.
5. DOE, 1990. Radiation Protection of the Public and the Environment, DOE 5400.5, U.S.
Department of Energy, Washington, D.C., February 8, 1990.
6. DOE, 1998. Quality Assurance, DOE O 414.1, U.S. Department of Energy, Washington,
D.C., November 24, 1998.
7. DOE. Occupational Radiation Protection, 10 CFR Part 835, U.S. Department of Energy,
Washington, D.C.
8. DOE. Quality Assurance Requirements and Responsibilities, 10 CFR Part 120,
Washington, D.C.
Chapter I - General Requirements and Responsibilities
I-84 DOE G 435.1-1
Section 71
7-09-99
I. 2.F. Field Element Managers.
Field Element Managers are responsible for:
(2) Radioactive Waste Management Basis. Ensuring a radioactive waste
management basis is developed and maintained for each DOE radioactive
waste management facility, operation, and activity; and ensuring review and
approval of the basis before operations begin. The Radioactive Waste
Management Basis shall:
(a) Reference or define the conditions under which the facility may operate
based on the radioactive waste management documentation;
(b) Include the applicable elements identified in the specific waste-type
chapters of this Manual; and
(c) Be developed using the graded approach process.
Objective:
The objective of this requirement is to ensure that the hazards associated with radioactive waste
management facilities, operations, and activities have been identified, their potential impacts
analyzed, and appropriate controls documented, implemented, and maintained for the protection
of workers, the public, and the environment.
Discussion:
DOE M 435.1-1 states that it is the responsibility of the Field Element Manager to ensure
development and approval of a radioactive waste management basis for a radioactive waste
management facility. Guidance on the requirement is provided below under the headings entitled,
Facilities with an Authorization Basis, Review and Approval of the Radioactive Waste
Management Basis, Timing of the Radioactive Waste Management Basis, and Maintaining the
Radioactive Waste Management Basis. Subrequirement (a) is discussed under the heading
Documentation of the Radioactive Waste Management Basis. Subrequirement (b) is discussed
under Elements in the Waste Type Chapters. Subrequirement (c) is discussed under the heading
Graded Approach. Also, at the end of the guidance, Radioactive Waste Management Basis
Statement Examples are presented for some of the hypothetical situations discussed throughout
this guidance.
The requirements in DOE O 435.1 and DOE M 435.1-1 were developed following a systematic
analysis of the hazards associated with management of radioactive waste and the conditions and
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-85
7-09-99
weaknesses that need to be controlled to prevent or minimize the risks due to these hazards. A
principal concept in this analysis is that a significant amount of the waste will present hazards for a
long time. Therefore, in addition to hazards that need to be controlled during operations and
other near-term activities, there are many conditions and weaknesses inherent in managing
radioactive waste that are required to be controlled leading up to disposal and after disposal to
protect future generations from the continuing hazard of the waste.
Example: A liquid waste stream containing high concentrations of long-lived
radionuclides requires stabilization to be disposed at the Site Y disposal facility in order
to provide for site stability and to retard the migration of the long-lived radionuclides for
a long period of time. An incorrectly processed batch of this waste form degrades
prematurely and causes instability in the Site Y disposal facility and leads to significant
migration of radioactivity. As a consequence, the site Y disposal facility must be
remediated.
Section 72
The hazards analysis used to develop the requirements indicated that many weaknesses and
conditions that could result in consequences in the near-term for workers, the public, and the
environment from radioactive waste management are sufficiently addressed through requirements,
processes, procedures, documentation, and evaluations required by existing regulations and
requirements, particularly those for occupational and nuclear safety. DOE M 435.1-1 identifies
many of these in Section I.1.E, Requirements of Other Regulations and DOE Directives. Key
directives that address many of the significant risks from operations and other near-term
management of radioactive waste are DOE 5480.21, Unreviewed Safety Question, and DOE
5480.23, Nuclear Safety Analysis Reports. As a result, the requirements in DOE M 435.1-1
principally address weaknesses and conditions that are not addressed in these other directives or
address weaknesses associated with radioactive waste management activities. Requirements also
address weaknesses associated with particularly vulnerable radioactive waste management steps,
such as waste transfer, or address the weaknesses and conditions associated with the long times
that management of radioactive waste is required.
The requirements in DOE M 435.1-1 are framed primarily as performance-oriented requirements,
and are implemented through documented processes, programs, and procedures on a facility-,
operation-, or activity-specific basis. The oversight of performance-oriented requirements such as
these involves a decision by a DOE authority (e.g., the Field Element Manager) that there is a
basis for a facility to operate. The basis is demonstrated through a review and analysis of the
procedures that concludes that the necessary controls to meet the requirements and operate safely
are in place. DOE 5480.21 contains some performance-oriented requirements, and its
implementation involves development of an Authorization Basis for a facility to safely operate.
During the development of the DOE M 435.1-1 requirements, it was recognized that a basis was
needed similar to the authorization basis that ensured that the potential hazards from management
Chapter I - General Requirements and Responsibilities
I-86 DOE G 435.1-1
7-09-99
of radioactive waste were being sufficiently evaluated and that adequate controls were in place to
provide assurance that the public, workers, and the environment were being protected. As
discussed above, for some aspects of radioactive waste management (e.g., preparation of waste
for disposal), these assurances include consideration of potential future hazards.
Thus, the concept of a radioactive waste management basis was adopted to provide assurances
that controls are developed, documented, in place, and properly implemented for management of
radioactive waste. The term controls used here and elsewhere in the discussion of a radioactive
waste management basis refers to processes, procedures, equipment, instruments, and other items
that are intended to reduce the likelihood of, or the consequences from, a problem that could arise
from managing radioactive waste. Controls include such things as placards, alarms, tools,
shielding, training, checklists, duplication of critical steps, redundant monitoring, analysis,
sampling and testing, etc.
Section 73
The radioactive waste management basis will involve activities such as characterizing and
certifying waste, establishing constraints on the acceptance of waste consistent with a facility or
operation’s characteristics, processing waste, containing waste with or without processing, and
disposing of the waste, including its possible impacts following disposal. Controls will be
implemented on a facility-, operation-, and activity-specific basis consistent with the earlier
discussion about the implementation of performance-oriented requirements.
Facilities with an Authorization Basis. In the case of nuclear facilities with Authorization Basis
documentation, it is likely that most of the controls required for a radioactive waste management
basis are implemented by the Authorization Basis. DOE 5480.21, Unreviewed Safety Question,
defines Authorization Basis as:
"Those aspects of the facility design and operational requirements relied upon by DOE to
authorize operation. These aspects are considered to be important to the safety of facility
operations. The authorization basis is described in documents such as the facility Safety
Analysis Report and other safety analyses; Hazard Classification Documents, the
Technical Safety Requirements, DOE-issued safety evaluation reports, and facility-specific
commitments made in order to comply with DOE Orders or policies."
As prescribed in DOE 5480.23, Nuclear Safety Analysis Reports; DOE STD-3009-94,
Preparation Guide for US DOE Nonreactor Nuclear Safety Analysis Reports; and DOE-EM
5502-94, DOE Limited Standard, Hazard Baseline Documentation, an Authorization Basis is
required for all nuclear facilities that have a hazard categorization of Category 1, 2, and 3. While
there are currently no radioactive waste management Category 1 facilities (reserved for nuclear
reactors), some radioactive waste facilities are Category 2 or 3, as defined by the methodology
outlined in DOE-STD-1027-92, Hazard Categorization and Accident Analysis Techniques for
Compliance with DOE Order 5480.23, Nuclear Safety Analysis Reports. Thus, these radioactive
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-87
7-09-99
waste management facilities have, or are required to have, an approved Authorization Basis. For
these facilities, the radioactive waste management basis requirements are very likely already met
by the implementation of the facility’s Authorization Basis. This should be determined through a
review of the Authorization Basis documentation that leads to a determination that adequate
controls are in place to meet the DOE M 435.1-1 requirements (see additional discussion under
Review and Approval).
Example: A review of the Authorization Basis documentation for the Liquid Radioactive
Waste Handling Facilities at the Savannah River Site (includes F and H Area Tank
Farms, the In-Tank Precipitation Process, the Replacement High-Level Waste
Evaporator, and the Effluent Treatment Facility) found that the Authorization Basis
includes the following documents and associated programs:
C Safety Analysis Reports (SARs);
C Technical Justification for Continued Operation/Basis for Interim
Operation/Design Basis Accident Analysis Report;
C Operational Safety Requirements/Technical Safety Requirements;
C Technical Standards;
C SAR Update Request Packages;
C Other Documents Identified by DOE-SR and WSRC as Authorization Basis
Documents (Safety Evaluations, Exemptions, Unreviewed Safety Questions
Evaluation);
Section 74
C DOE Safety Evaluation Reports; and
C Listing of documents that are to be subject to configuration management but
are not Authorization Basis Documents.
Included within these documents are what DOE-SR considers to be the complete set of
operational requirements relied upon by the site to ensure that the public, workers, and
the environment are protected from the hazards associated with the management of the
radioactive waste handled in the facilities (e.g., the establishment of limits of fissionable
materials and chemical constituents that can be transferred to the waste tanks by the
generators is included in the SARs. These limits are essentially equivalent to the limits
required to be set by the waste acceptance requirements (II.J) of the high-level waste
chapter of DOE M 435.1-1). The existing Authorization Basis documentation contains
all the information demonstrating that DOE O 435.1 and DOE M 435.1-1 are met. This
is documented in a memorandum from DOE-SR to the contractor organization operating
the facilities.
Other radioactive waste management facilities are covered by similar documentation prepared to
meet the requirements of the above Safety Orders and their implementation, such as an Auditable
Safety Analysis, or a DOE- or contractor-established interim safety basis for facility operation
Chapter I - General Requirements and Responsibilities
I-88 DOE G 435.1-1
7-09-99
such as a Basis for Interim Operations (BIO). Facilities operating under one of these may also
have the necessary programs and documentation in place to satisfy the requirements for a
radioactive waste management basis. A review of the existing programs and documentation is to
be conducted for their adequacy in providing the controls needed to meet the DOE M 435.1-1
requirements and determining whether any additional documentation or program is required to
demonstrate that the requirements of DOE O 435.1 and DOE M 435.1-1 will be met.
Radioactive waste management operations and activities that take place in facilities which are
radiological (non-nuclear) facilities are likely to not already have an Authorization Basis or similar
safety-related documentation to consider in evaluating whether the radioactive waste management
basis for the facility already exists. However, programs and controls already implemented at the
facility may wholly or partially fulfill the requirements for a radioactive waste management basis.
For these facilities, a thorough review should be conducted that identifies where additional
programs or controls are needed, and includes the critical step of ensuring that a radioactive waste
management basis exists when these programs and controls are appropriately implemented.
The radioactive waste management basis plays a key role in the self-correcting system employed
by DOE Elements in accordance with DOE P 450.4, Safety Management System Policy. The
radioactive waste management controls forming the basis are evaluated periodically to ensure they
continue to address the hazards of managing the radioactive waste. Adherence to and compliance
with the critical elements of the radioactive waste management basis should become items
measured in accordance with DOE O 210.1, Performance Indicators and Analysis of Operations
Information, and which is reported in accordance with DOE O 232.1A, Occurrence Reporting
and Processing of Operations Information when incidents occur. As such, the critical elements
of the radioactive waste management basis should be considered similar to the Technical Safety
Requirements (TSRs) described in DOE 5480.21. The responsibility should be clear to all
personnel involved in implementing radioactive waste management basis controls that violations
and operations inconsistent with the radioactive waste management basis should be reported, and
steps made to correct the situation consistent with the sections of the Manual entitled Corrective
Actions.
Section 75
Review and Approval of the Radioactive Waste Management Basis. The requirement states that
the Field Element Manager’s responsibility is to ensure review and approval of the radioactive
waste management basis for each radioactive waste management facility under his/her authority.
This review should be done by DOE staff. The DOE staff could be supported by staff of a
contractor who has no conflict of interest. However, the Field Element Manager is responsible
and accountable for the radioactive waste management basis approval.
The approval that is required means the facility, operation, or activity has been determined to have
adequate controls to manage radioactive waste in accordance with the requirements of DOE O
435.1 and DOE M 435.1-1 and is authorized to manage radioactive waste. For new facilities or
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-89
7-09-99
major modifications to existing facilities, this approval should be provided prior to the beginning
of the activities that will create waste. The Field Element Manager must determine how and when
to approve radioactive waste management bases for existing and ongoing waste management
facilities, operations, and activities (see additional discussion under Graded Approach).
In order to approve management of radioactive waste, the requirement calls for review of the
basis. This statement implies review of documents, and in fact, some of the elements identified as
crucial to the radioactive waste management basis for a facility are large documents (e.g., the
composite analysis for a low-level waste disposal facility). While documentation should always be
prepared for all critical activities affecting the management of radioactive waste, it is recognized
that several methods may be employed for meeting requirements in DOE directives and in
documenting compliance with requirements. Thus, the review could include reviewing
documentation, preparation of documentation, the organization assigned the job of document
preparation and its criteria or processes for preparing documentation, or audit results to conclude
the facility, activity, or operation is satisfactorily meeting the DOE O 435.1 and DOE M 435.1-1
requirements. The review called out in this requirement is not supposed to imply the need for
reviewing ALL documentation that is associated with the requirements or implementation of the
requirements. The review should involve appropriate steps to ensure that DOE O 435.1 and DOE
M 435.1-1 requirements are being met.
Example 1: A large DOE facility has several hundred generators, and a system is
established for centralized certification of wastes for treatment and disposal. Generators
submit waste profiles to the central waste management organization for each of their
waste streams as part of certification. Therefore, there are thousands of waste profiles
managed by the central unit. The review by the Field Element Manager at this facility to
ensure the waste certification element of the radioactive waste management basis is being
implemented appropriately includes a review of the procedure used by the central waste
management organization for certification (which includes minimum information that
must be on profiles and criteria for finding them complete), and an annual program
review that assesses all aspects of the central organizations activities.
Section 76
Example 2: A DOE facility consisting of many small operations and activities operates
several storage areas. Its central waste management unit develops a generic waste
acceptance requirements document that each storage area must follow, at a minimum,
plus instructions for adding specific technical criteria to the set of generic requirements
for any specific wastes they are handling. Central waste reviews and approves the
specific criteria developed. The Field Element Manager’s staff has reviewed the generic
waste acceptance requirements with the instructions and finds this adequately addresses
the DOE O 435.1 and DOE M 435.1-1 requirements for this element of the radioactive
waste management basis. The Field staff does not investigate any of the specific waste
acceptance criteria that have been developed and approved.
Chapter I - General Requirements and Responsibilities
I-90 DOE G 435.1-1
7-09-99
Documentation of the Radioactive Waste Management Basis. The radioactive waste management
basis is to be documented for all radioactive waste management facilities, activities, and
operations. The documentation of the radioactive waste management basis consists of results of
reviews and analyses, where appropriate, and a description of radioactive waste management
controls that are in place for protection of the public, workers, and the environment. The results
of the reviews, analyses, and descriptions of the controls that must be in place for the safe and
efficient management of radioactive waste are already prepared, documented, and implemented by
DOE Elements for most radioactive waste management facilities, operations, and activities. The
radioactive waste management basis includes the analysis, programs and their procedures, and
documents that are identified in the waste-type chapters of DOE M 435.1-1, Radioactive Waste
Management Manual.
Example 1: For the Liquid Radioactive Waste Handling Facilities at the Savannah River
Site described in the above section Facilities with an Authorization Basis, of the list of
documents cited in the example, all Safety Analysis Reports, the Safety Evaluation
Report, and the Technical Justification for Continued Operation, plus several Technical
Standards, Technical Safety Requirements, SAR Update Request Packages, several
Exemptions and Unreviewed Safety Question Evaluations, plus many facility procedures,
and several chapters from the Configuration Management list of documents constitute
the radioactive waste management basis documentation.
Example 2: Storage Facility B200 operates under the following procedures and
documents that constitute the radioactive waste management basis: Safety Analysis of
Facility B200; Facility B200 Waste Acceptance Criteria; Procedure B200 - Acceptance
of Waste for Storage, Quality Implementation Procedure (QIP) for Facility B200;
Procedure C200B - Certification of Waste to Disposal, and; Training Module 200W.
Example 3: At Storage Facility B200 in the example above, each of the documents and
procedures listed above is assigned a number [RWMB-xxx], indicating it is a radioactive
waste management basis document, which can easily be found by site personnel who
perform a search for radioactive waste management basis documents in accordance with
the record management system instructions.
Section 77
The documentation of a radioactive waste management basis includes a documented conclusion
that there is adequate protection from the hazards of management of the radioactive waste as a
result of the Field Element Manager, or his/her designee’s review and approval. This
documentation, called a radioactive waste management basis statement in this guidance, is to be
prepared for every radioactive waste management facility, operation, or activity to demonstrate
that a DOE authority has concluded that the hazards associated with management of radioactive
waste have been addressed and that the performance-oriented requirements of DOE O 435.1 and
DOE M 435.1-1 will be met by the implementation of the described controls. The radioactive
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-91
7-09-99
waste management basis statement should include, or reference, the documentation used to
provide the conclusion, (e.g., list of facility procedures), or reference to other reports that contain
the key conclusions (the facility’s DOE Safety Evaluation Report). This key element of a
complete radioactive waste management basis is not already prepared and documented by DOE
Elements for many radioactive waste management facilities, operations, and activities.
For facilities with an Authorization Basis, or other safety-related documentation discussed under
Facilities with an Authorization Basis, the radioactive waste management basis statement should
document that the safety-related documents describe the controls required to ensure that
DOE O 435.1 requirements will be met, describe the critical controls that provide compliance
with DOE O 435.1 and DOE M 435.1-1, and provide information on the location of the controls.
If appropriate, the radioactive waste management basis evaluations and conclusions could be
incorporated into the Authorization Basis or other safety-related authorization if desired by the
Field Element Manager.
Example: A radioactive waste management basis statement is prepared for the Savannah
River Site example described under Facilities with an Authorization Basis. It contains a
full list of facilities that are covered by the statement and it has two attachments. The
first attachment is a complete list of the documents referred to in the previous example in
which all radioactive waste management controls that must be in place to meet DOE M
435.1-1 are found (see Example 1 under Documentation of the Radioactive Waste
Management Basis to see this list). The second attachment is a crosswalk of DOE M
435.1-1 requirements showing which documents and where in the documents analysis and
descriptions of controls can be found to meet that requirement. [An example of this
radioactive waste management basis statement is provided as Example A at the end of this
guidance.]
Elements in the Waste Type Chapters. Each of the waste-type specific chapters in DOE M 435.1
1 contains a list of specific programs, processes, and documents that must be included in the
radioactive waste management basis for facilities that manage these waste types. These
programs, processes, and documents represent implementation of critical radioactive waste
management controls which are based primarily or exclusively on DOE M 435.1-1 requirements.
These should not be considered as a complete list of all of the elements that may need to be
included in a radioactive waste management basis.
Section 78
Many weaknesses and conditions associated with radioactive waste management are controlled by
processes, procedures, and documentation developed and implemented to meet other sets of
requirements, both Federal and State regulations and DOE directives. Many of these are
identified in Section I.1.E, Requirements of Other Regulations and DOE Directives. Controls
based on these other directives and regulations should also be evaluated to ensure that the critical
Chapter I - General Requirements and Responsibilities
I-92 DOE G 435.1-1
7-09-99
aspects to radioactive waste management are adequate, and therefore, contribute to a radioactive
waste management basis finding.
Example 1: A small DOE laboratory includes a storage operation for small amounts of
low-level waste. Waste is accumulated over about a nine-month period of time, after
which it is shipped to the Nevada Test Site for disposal. The radioactive waste
management basis for this facility includes the waste acceptance requirements (DOE M
435.1-1), the waste certification program (DOE M 435.1-1), the radioactive waste
management module of the laboratory training program (DOE O 360.1 and DOE
5480.20A), the facility’s implementation procedure of the site quality assurance program
plan (10 CFR 830.120), and the document control procedure used for maintaining
records of waste that is in storage (DOE O 200.1 and 10 CFR 830.120).
Example 2: Operation at the storage facility discussed in Example 1 above is modified
to store a small amount of classified waste. The radioactive waste management basis
includes the items above, plus Section 14 of the laboratory’s security and safeguard
implementation procedure (DOE O 470.1), which requires appropriate labeling of the
containers of classified waste.
Additional controls are sometimes needed to address situations and conditions that were not
evaluated in the development of requirements and directives, or which are identified through
facility-, process-, or activity-specific hazard analysis. These specific controls also must be
evaluated to ensure the aspects of them that are critical to radioactive waste management are
adequate and contribute to the radioactive waste management basis finding.
Example: The operating procedures for a storage facility containing transuranic waste
includes the items identified in Chapter III; facility-specific procedures implementing two
other DOE directives; and conditions specified in its RCRA storage permit. It also
contains actions from a facility-specific audit conducted by the Carlsbad Area Office in
its radioactive waste management basis to fully cover the hazards associated with the
facility. The radioactive waste management basis statement includes the specific
requirements from the audit report to document the commitments to meet these action
items for safe management of radioactive waste.
The radioactive waste management basis should be limited to only those processes or controls
that are needed based on the hazards that may be present in the facility or operation, the
complexity of activities to manage the waste, and the time that controls are warranted to provide
protection. Controls critical to a radioactive waste management basis at one facility are not
necessarily warranted to be included at all facilities within a site, for example. Thus, a standard
listing of radioactive waste management basis documents cannot be developed.
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-93
Section 79
7-09-99
Graded Approach. The scope of Departmental activities leads to a great deal of diversity in what
constitutes the radioactive waste management basis for a given operation, and the documentation
of the basis should reflect the hazards associated with these diverse activities. In general,
generation and treatment of radioactive waste are more dynamic than storage and disposal, so it
would be expected that the radioactive waste management bases for these types of facilities would
be different, i.e., different topics need to be covered, and different levels of detail are necessary
for proposed controls. Similarly, when identical activities (such as storage and certification to a
disposal facility) are being conducted at many facilities on one site, it is expected that the same
radioactive waste management bases may apply to all of these facilities.
For facilities where little hazard exists or where activities are not dynamic, the radioactive waste
management basis statement may be abbreviated, such as a memorandum which references the
appropriate documents. For facilities where many interrelated activities are occurring and/or
where higher hazards are present, a radioactive waste management basis statement could be
prepared that provides the operational conditions of a radioactive waste management facility ,
similar to a license for a facility regulated by the Nuclear Regulatory Commission.
Example 1: An operating low-level waste disposal facility has approved revisions of all
of the following documents (listed in Chapter IV); the waste acceptance requirements,
the performance assessment, the composite analysis, the disposal authorization
statement, and the monitoring plan. The preliminary closure plan reviewed with the
performance assessment has not been approved, pending an extensive update. Several
disposal site procedures are also approved and implemented. The Field Element
Manager determines that the facility may operate while it updates the closure plan. The
Field Element Manager also identifies the Site Radiation Control Manual and the Site
Health and Safety Plan and an additional document requested by the State mixed waste
regulating authority to include as part of the basis to allow operations for management
of radioactive waste. In this case, the radioactive waste management basis statement
prepared incorporates the aforementioned documents by reference, and contains other
conditions that the facility must adhere to for safe disposal of the low-level waste. One
of these added conditions is that the updated closure plan must be submitted within 15
months of the issuance of the radioactive waste management basis to include
consideration of the comments addressing deficiencies in the preliminary closure plan.
[An example of this radioactive waste management basis statement is provided as Example
B at the end of this guidance.]
Example 2: A laboratory facility stores transuranic and low-level waste in four
temporary storage buildings. Following an approved time period, the waste is collected
by a central waste management operation of the laboratory and consolidated in a
permanent storage facility. The transuranic waste is stored there indefinitely, while the
low-level waste is stored until a sufficient amount is accumulated for shipment to a low-
Chapter I - General Requirements and Responsibilities
I-94 DOE G 435.1-1
7-09-99
Section 80
level waste disposal facility. The low-level waste is certified to a specific disposal
facility’s waste acceptance criteria, while the transuranic waste is certifiable to WIPP
requirements. The radioactive waste management basis statement for all of these
facilities and activities is documented with one radioactive waste management basis
statement. The statement consists of a memorandum that references five laboratory
operating procedures on storage of waste and certification of waste, and the low-level
waste disposal facility and WIPP waste acceptance requirements since the waste is
certified to meet these two disposal facilities’ requirements without any changes being
made to the waste. [An example of this radioactive waste management basis statement is
provided as Example C at the end of this guidance.]
Timing of the Radioactive Waste Management Basis. The requirement states that the radioactive
waste management basis is to be reviewed and approved before operations begin. The
requirement is written from the viewpoint of applying the provisions to a new facility, and thus
emphasizes that the basis must be in place prior to the generating of any radioactive waste. For
existing facilities, the Field Element Manager should establish a schedule for approvals of
radioactive waste management bases to bring existing facilities into compliance with this
requirement. It may be appropriate to consider the hazards associated with each facility and the
radioactive waste managed at it when establishing the implementation schedule for approvals of
radioactive waste management bases. Therefore, a facility with a great deal of hazard or
complexity, such as a multi-waste stream treatment facility, may have a bases approved before
facilities that engage in less complicated or hazardous activities. Implementation is to be
consistent with the requirements of DOE M 435.1-1 as set forth in paragraph (i) 4.
Maintaining the Radioactive Waste Management Basis. The radioactive waste management basis
should be reviewed periodically and whenever there is a change to the subject facility, operation,
or activity, or the requirements of DOE O 435.1 or DOE M 435.1-1. Appropriate changes
should be made to the documentation of the radioactive waste management basis, if warranted.
These reviews should evaluate the status of the radioactive waste management basis and its
continued validity over time. The review should evaluate whether the existing documentation still
adequately identifies the hazards associated with a radioactive waste management facility,
operation, or activity; the analysis of the potential impacts of those hazards is still valid; and the
controls that are in place for protection of workers, the public, and the environment address the
hazards. Existing processes, programs, or documentation that can satisfy this guidance should be
used to the extent possible. Elements of the radioactive waste management basis in the self-
correcting system employed at the site in accordance with the integrated Safety Management
System employed in accordance with DOE P 450.4 should be included as an effective way to
achieve adequate maintenance of the radioactive waste management basis.
The requirement for a radioactive waste management basis is successfully met if all radioactive
waste management facilities, operations, and/or activities at each DOE site has a radioactive
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-95
7-09-99
Section 81
waste management basis, which concludes that appropriate controls are documented and
implemented for the protection of workers, the public, and the environment. The conclusion
should be appropriately documented. The documentation should provide, at a minimum, a
complete list of the controls that implement the requirements of DOE O 435.1 and DOE M
435.1-1 for all waste types being managed at the site, and provide evidence that the radioactive
waste management controls are included in the site’s implementation of the integrated Safety
Management System.
Additional information on the radioactive waste management basis is contained in Chapter II,
High-Level Waste Requirements; Chapter III, Transuranic Waste Requirements; and Chapter IV,
Low-Level Waste Requirements of this guidance.
Supplemental References:
1. DOE, 1991. Unreviewed Safety Question, DOE 5480.21, U.S. Department of Energy,
Washington, D.C., December 24, 1991.
2. DOE, 1992. Nuclear Safety Analysis Reports, DOE 5480.23, U.S. Department of
Energy, Washington, D.C., April 10, 1992.
3. DOE, 1994. Preparation Guide for U.S. DOE Nonreactor Nuclear Facility Safety
Analysis Reports, DOE STD-3009-94, U.S. Department of Energy, Washington, D.C.,
July 1994.
4. DOE, 1994. DOE Limited Standard: Hazard Baseline Documentation, DOE-EM-5502
94, U.S. Department of Energy, Washington, D.C., December 1994.
5. DOE, 1992. Hazard Categorization and Accident Analysis Techniques for Compliance
with DOE Order 5480.23, Nuclear Safety Analysis Reports, DOE-STD-1027-92, U.S.
Department of Energy, Washington, D.C., December 1992.
6. DOE, 1996. Safety Management System Policy, DOE P 450.4, U.S. Department of
Energy, Washington, D.C., October 16, 1996.
7. DOE, 1995. Performance Indicators and Analysis of Operations Information, DOE O
210.1, U.S. Department of Energy, Washington, D.C., September 27, 1995.
8. DOE, 1997. Occurrence Reporting and Processing of Operations Information, DOE O
232.1A, U.S. Department of Energy, Washington, D.C., July 21, 1997.
Chapter I - General Requirements and Responsibilities
I-96 DOE G 435.1-1
7-09-99
9. DOE, 1999. DOE Radiological Control Standard - Radiological Health and Safety
Policy, Draft, U.S. Department of Energy, Washington, D.C., April 1999.
Attachments: Example Radioactive Waste Management Basis Statements
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-97
7-09-99
Example A
Radioactive Waste Management Basis Statement
Savannah River Waste Handling Facilities
(See Example on Pg I-X, Example 1 on Pg I-X, Example on Pg I-X)
MEMORANDUM FOR: Joseph Smith, Field Element Manager, DOE/SR
THRU: Robert Jones, Director, Division of Waste Management, DOE/SR
FROM: Wilburt Littleguy, Operations Manager, SRS Contractor
SUBJECT: RADIOACTIVE WASTE MANAGEMENT BASIS FOR THE
WASTE HANDLING FACILITIES
DATE: June 1, 1999
This memorandum documents the approval of a radioactive waste management basis for the
following facilities, operations, and activities, which are collectively known as the Waste Handling
Facilities at H Area of the Savannah River Plant: F Area Tank Farm, H Area Tank Farm, In-
Tank Precipitation Process, Replacement High-Level Waste Evaporator, and the Effluent
Treatment Facility.
Section 82
The approval of the radioactive waste management basis for the Waste Handling Facilities is
based on a review of the documents on the attached list granting an Authorization Basis to
operate the Waste Handling Facilities under DOE 5480.21. The radioactive waste management
basis review consisted of reviews of targeted chapters and sections of the Authorization Basis
documentation to ensure that the requirements of the revised Order on Radioactive Waste
Management, DOE O 435.1, were being met. The review of the Authorization Basis documents,
and processes and procedures implemented as described, concluded that the requirements of
DOE O 435.1 are being met. A crosswalk is also attached indicating the DOE M 435.1-1
requirements that are being met at the Waste Handling Facilities and the procedure or document
which is the approved implementation of the requirement.
Unless additional review is required due to changes in the facilities or in the DOE 435.1
requirements, the radioactive waste management basis for the Waste Handling Facilities will
remain valid until June 1, 2004.
Original signed by:
W.G. Littleguy
Operations Manager, Waste Handling Facilities
Attachments: As Listed SRS Contractor
Chapter I - General Requirements and Responsibilities
I-98 DOE G 435.1-1
7-09-99
Attachment 1
Radioactive Waste Management Basis
Waste Handling Facilities / Savannah River Plant
1. Safety Analysis Reports (SARs) [Report Nos. WHF-WSRC-003, WHF-WSRC-006,
WHF-WSRC 015]
2.
USQ Package - [USQ-WHF-SER-98]
Technical Justification for Continued Operation/ Basis for Interim Operation/Design Basis
Accident Analysis Report - [Memorandum dated April 1, 1996 with Attachments].
3. Operational Safety Requirements/Technical Safety Requirements [SRC-J-092, SRC-K
063, SRC-U-012]
4. Technical Standards - [WSRC-WMB-013 and OSHA-TYU-003]
5. SAR Update Request Packages - [Memoranda dated April 30, 1996, August 15, 1996,
January 17, 1997]
6. Safety Evaluation Report - [Report No DOE-SRS-SER-003]
7. WSRC Operating Manual and Procedures:
Waste Acceptance Requirements Implementation - [WSRC-OPSMAN-SC3-03]
Waste Characterization Profiling - [WSRC-OPSMAN-SC4-02]
Certification Process and Approval - [WSRC-OPSMAN-WA-W28]
8.
(Example of Attachment 2 not shown)
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-99
7-09-99
Example B
Radioactive Waste Management Basis Statement
Low-Level Waste Disposal Facility
(See Example 1 on Pg I-XX)
MEMORANDUM FOR: Robert Jones, Operations Manager, Site Y Low-Level Waste Disposal Facility
FROM: Joseph Smith, Deputy Field Element Manager, DOE/FO
SUBJECT: DOE M 435.1-1 RADIOACTIVE WASTE MANAGEMENT BASIS FOR SITE Y LOW
LEVEL WASTE DISPOSAL FACILITY.
This memorandum documents the radioactive waste management basis for the Site Y Low-Level Waste Disposal
Facility. The basis is established as a result of reviews and approvals of the Site Y Performance Assessment
(DOC-FO-PA-001) and the Site Y Composite Analysis (DOC-FO-CA-002), and the issuance of the EM-30
Disposal Authorization Statement (HQ-DAS-SITY-1), which is attached. The review and approval of the
Performance Assessment and the Composite Analysis, and the issuance of the Disposal Authorization Statement
included a review of several other documents, including a preliminary closure plan and a preliminary monitoring
plan, which are listed in Appendix F in the April 1998 Low-Level Waste Review Group Team Report on the Site Y
Performance Assessment and Composite Analysis Reviews.
Section 83
The radioactive waste management basis is predicated on the continued adherence to the current revisions of the
Site Y Radiation Control Manual, the Site Y Health and Safety Plan, and on meeting the commitments made in the
April 27, 1997 letter from Smith, DOE/FO to Johnson, State/EPA for finalizing the monitoring well designs for
the RCRA-regulated Site Y storage facilities plume.
The Disposal Authorization Statement contains twelve conditions that must be met in order for the operations at
the Site Y Low-Level Waste Disposal Facility to continue. In addition to these twelve conditions, the following
condition must also be met:
Condition 13: By August 1999, (15 months) the preliminary closure plan submitted with the performance
assessment and composite analysis must be updated to reflect the designs of the monitoring system
incorporated by reference above, letter Smith, DOE/FO to Jones, State/EPA, and the considerations
documented in page 57 of the April 1998 Low-Level Waste Review Group Team Report on the Site Y
Performance Assessment and Composite Analysis Reviews.
Any questions about this memorandum or the radioactive waste management basis for the Site Y Low-Level Waste
Disposal Facility should be directed to me at my office number.
Original Signed By:
Joseph Smith
Field Element Manager,
DOE/Field Office (FO)
Reference:
Site Y Low-Level Waste Disposal Facility Disposal Authorization Statement
Chapter I - General Requirements and Responsibilities
This statement documents the radioactive waste management basis for the operations of the Site
Y Central Waste Management Unit for storage of low-level and transuranic waste at all storage
facilities (see list in Appendix A) at Site Y.
The radioactive waste management basis is founded based on the review and approval of the Site
Y laboratory operating procedures on waste acceptance, certification, and storage which were
found to meet the requirements of DOE O 435.1 and DOE M 435.1-1 (see list in Appendix B).
The Site procedures on waste acceptance commit to meeting the requirements of the WIPP Waste
Acceptance Criteria (WIPP-WAC-007), and the Nevada Test Site Waste Acceptance Criteria
(NTSWAC) since all waste accepted at the storage facilities must be able to be certified for
disposal at one of these two facilities. Therefore, these two documents, as approved by their
respective Field Elements, are incorporated by reference into the radioactive waste management
basis for storage activities at Site Y.
I-100 DOE G 435.1-1
7-09-99
Example C
Radioactive Waste Management Basis Statement
Several Waste Storage Facilities
(See Example 2 on Pg I-XX)
RADIOACTIVE WASTE MANAGEMENT BASIS STATEMENT
SITE Y CENTRAL WASTE STORAGE OPERATIONS.
Appendix A - List of Site Y Storage Facilities
Appendix B - List of Site Y Radioactive Waste Management Basis Procedures
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-101
7-09-99
I. 2.F. Field Element Managers.
Field Element Managers are responsible for:
(3) Waste Minimization and Pollution Prevention. Ensuring implementation of
waste minimization and pollution prevention programs.
Objective:
The objective of this requirement is to ensure that emphasis is placed on the Field Element
Manager’s responsibility for minimizing the generation of radioactive waste and that waste
minimization programs are implemented at radioactive waste management facilities.
Discussion:
Section 84
The safety and hazards analysis indicated that an effective mitigating measure in management of
radioactive waste was to avoid potential weaknesses and conditions through minimization of
waste. The requirements analysis indicated that DOE’s current programs implementing Executive
Order 12856, Federal Compliance with Right-to-Know Laws and Pollution Prevention
Requirements and Responsibilities, and Executive Order 13101, Greening the Government
through Waste Prevention, Recycling, and Federal Acquisition, and DOE 5400.1, General
Environmental Protection Program, were adequate in establishing effective waste minimization
programs, especially for generators of waste. These directives are invoked in the General
Requirement on other directives and regulations (DOE M 435.1-1, Section I.1.E.(20)). This
General Requirement is added to emphasize the Field Element Manager’s responsibilities in
carrying out the requirements of the Executive Orders and DOE 5400.1 for radioactive waste
management facilities, and ensuring that in the cases where radioactive waste is generated during
the course of its management, for example, when ash is created from the incineration of
radioactive waste, that this waste is also minimized. No additional guidance is needed beyond the
documentation already prepared on the Field Element Manager’s responsibilities for waste
minimization and pollution prevention.
Compliance with this requirement is demonstrated if waste minimization and pollution prevention
principles are incorporated into all radioactive waste management activities where appropriate.
Supplemental References:
1. DOE, 1992. Waste Minimization Crosscut Plan Implementation, SEN-37-92, U.S.
Department of Energy, Washington, D.C., May 13, 1992.
Chapter I - General Requirements and Responsibilities
I-102 DOE G 435.1-1
7-09-99
2. O’Leary, 1994. H. O’Leary to Departmental Elements, memorandum, Departmental
Strategy for Compliance With Executive Order 12856, “Federal Compliance With Right-
To-Know Laws and Pollution Prevention Requirements,” U.S. Department of Energy,
Washington, D.C., December 27, 1994.
3. EPA, 1993. Pollution Prevention and Right-to-Know in the Government, E.O. 12856,
EPA 100-K-93-001, U.S. Environmental Protection Agency, Washington, D.C., 1993.
4. EPA. Federal Agency Environmental Management Program Planning Guidance, EPA
300-B-95-001, U.S. Environmental Protection Agency, Washington, D.C.
5. EPA. Federal Facility Pollution Prevention Project Analysis, EPA 300-B-95-008, U.S.
Environmental Protection Agency, Washington, D.C.
6. DOE, 1994. Department of Energy Waste Minimization Reporting Requirements, U.S.
Department of Energy, Washington, D.C., November 1994.
7. DOE, 1996. Pollution Prevention Program Plan, DOE/S-0118, U.S. Department of
Energy, Washington, D.C., 1996.
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-103
7-09-99
I. 2.F. Field Element Managers.
Field Element Managers are responsible for:
(4) Approval of Exemptions for Use of Non-DOE Facilities. DOE radioactive
waste shall be treated, stored, and in the case of low-level waste, disposed of
at the site where the waste is generated, if practical; or at another DOE
facility. If DOE capabilities are not practical or cost effective, exemptions
may be approved to allow use of non-DOE facilities for the storage,
treatment, or disposal of DOE radioactive waste based on the following
requirements:
(a) Such non-DOE facilities shall:
Section 85
1. Comply with applicable Federal, State, and local requirements;
2. Have the necessary permit(s), license(s), and approval(s) for
the specific waste(s); and
3. Be determined by the Field Element Manager to be acceptable
based on a review conducted annually by DOE.
(b) Exemptions for the use of non-DOE facilities shall be documented to be
cost effective and in the best interest of DOE, including consideration of
alternatives for on-site disposal, an alternative DOE site, and available
non-DOE facilities; consideration of life-cycle cost and potential liability;
and protection of public health and the environment.
(c) DOE waste shall be sufficiently characterized and certified to meet the
facility’s waste acceptance criteria.
(d) Appropriate National Environmental Policy Act (NEPA) review must be
completed. For actions taken under the Comprehensive Environmental
Response, Compensation, and Liability Act (CERCLA), it is DOE’s policy
to incorporate NEPA values into the CERCLA documentation.
(e) Headquarters shall be notified of any exemption allowing use of a non-
DOE facility and the Office of the Assistant Secretary for Environment,
Safety and Health (EH-1) shall be consulted prior to the exemption being
executed.
Chapter I - General Requirements and Responsibilities
I-104 DOE G 435.1-1
7-09-99
(f) Host States and State Compacts where non-DOE facilities are located
shall be consulted prior to approval of an exemption to use such facilities
and notified prior to shipments being made.
Objective:
The objective of this requirement is to indicate a clear preference for use of DOE facilities and to
ensure that when it is determined to be necessary to use non-DOE facilities for the treatment,
storage, and disposal of DOE radioactive waste only when such use is in the best interest of the
Department and protective of the public, workers, and the environment.
Discussion:
It has been the Department’s long-standing policy to dispose of low-level waste at the site where
it is generated or at another DOE site if onsite capabilities are not practical. Exemptions to this
policy have been allowed in cases where disposal at a DOE site is not practical and it can be
shown that the action is in compliance with applicable requirements and is protective of the
public, workers, and the environment and that there is a substantial benefit to the Department.
However, use of non-DOE facilities has not been allowed without such justification because of
the potential long-term liabilities and possible negative impacts on DOE-wide or commercial
disposal programs associated with commercial disposal. Additionally, because of the economics
associated with operating onsite disposal facilities, use of non-DOE facilities can result in higher
overall costs for all DOE disposal.
The Department has previously addressed a number of issues related to the use of non-DOE
facilities for the disposal of low-level waste. The Office of Environmental Management, in
consultation with the Office of Environment, Health, and Safety, approved the use of non-DOE
facilities for the disposal of waste originating from remedial activities the Department was
performing at non-DOE sites and for the disposal of small quantities of mixed low-level waste.
Subsequently, Headquarters delegated the authority to make decisions on the use of non-DOE
facilities for disposal of low-level waste to the Heads of Field Elements under certain conditions.
The current requirement and this guidance continue the practice of allowing the Field Element
Managers to grant exemptions for using non-DOE waste management facilities. Exemptions
granted prior to the issuance of DOE O 435.1 remain valid.
Section 86
During the development of DOE M 435.1-1, it was also recognized that the evaluation performed
to justify use of non-DOE facilities for low-level waste disposal, e.g., determining that the action
is protective and in the best interest of the government, was a best management practice that
should be employed for any use of non-DOE waste management facilities. Therefore, the
requirement was broadened to also address storage and treatment.
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-105
7-09-99
This requirement allows the Field Element Manager to approve the use of non-DOE facilities
where use of DOE facilities is not practical after meeting minimum requirements to ensure that the
waste management decision is in the best interest of the government and will not pose an undue
threat to public and worker health and safety, or to the environment.
This requirement does not extend to residues that result from the use of commercial laboratories
to perform analyses on radioactive samples, whether they are waste samples or not. Laboratories
that have the capability to accept radioactive samples for analysis generally have provisions for
disposal of the waste resulting from their activities. This includes excess sample, i.e., sample that
is not used in analyses, as well as sample residue, laboratory equipment, etc. When contracting
for such laboratory services, it is not required that samples be returned to DOE for disposal if the
laboratory has such provisions. The policy for use of non-DOE facilities does not require or
prefer that waste from commercial analysis of samples be returned to the DOE site for waste
management. It is acceptable for the laboratory to dispose of the waste in accordance with the
provisions of their radioactive materials license. However, return of sample waste to the DOE
site is acceptable if it is economically beneficial to DOE.
Use of DOE Capacity. As directed in the current requirement, there is a preference for treatment,
storage, or disposal of DOE radioactive waste to occur at a DOE site. Nevertheless, DOE sites
are explicitly encouraged to seek the most practical disposal option for low-level waste, especially
if there is a lower cost alternative with adequate environment, safety, and health protection. Prior
to using a non-DOE facility, a determination must first be made that the waste management
activity being considered is not practical at the DOE site that generates the waste. Then a second
determination must be made that management of the waste is not practical at another DOE site.
The practicality of performing a waste management function at a particular site depends on the
availability of facilities or capacity, and also the cost associated with performing the activity. As
part of the planning process, a range of waste disposal alternatives must be considered and
documented, including on-site disposal, an alternative DOE disposal site, and available non-DOE
facilities. When evaluating the cost effectiveness of performing a waste management activity at a
DOE versus a non-DOE site, managers should consider the complex-wide implications of this
decision, e.g. if many sites choose non-DOE facilities over a particular DOE facility for a waste
management activity, this facility, losing much of its incoming volume, may become prohibitively
expensive per unit of waste it handles or may not be able to continue operating. This may have a
great impact on waste for which with this facility is the only option. This is particularly true for
low-level waste disposal because the Department must maintain the capability to dispose of low-
level waste since the waste acceptance criteria at currently available commercial facilities do not
accommodate significant amounts of the Department’s waste. Therefore, one should not only
consider the short term impact of a decision that DOE capacity is not practical, but also consider
the implications across the complex and for the long term.
Section 87
Chapter I - General Requirements and Responsibilities
I-106 DOE G 435.1-1
7-09-99
Acceptable Performance. In making a decision to use a non-DOE facility for managing DOE
radioactive waste, the Field Element Manager must ensure that the decision is protective of the
public and the environment. This responsibility is effected by ensuring that the non-DOE facility
is properly licensed and/or permitted, that the facility complies with applicable regulations, and
that the facility has an acceptable history of operational and regulatory performance. Based on
the characteristics of the waste that is being considered for transfer to the non-DOE facility, a
review should be conducted of the licenses and permits held by the facility to determine if they
provide appropriate coverage for management of the waste. This should be accomplished
through a reading of the licenses and permits and through discussions with the issuing authority
(Federal, State, or local licensing/permitting authority). This review should confirm that the
facility is authorized to receive the radionuclides in the waste to be transferred, and if the waste
contains constituents subject to RCRA or TSCA, that the facility has the appropriate
authorization to receive and manage those constituents. Discussions with regulatory authorities
and reviews of inspection reports should also be used to determine whether the facility has a
history of acceptable operational and regulatory performance. Occasional and minor violations
should not be a basis for deciding not to use a non-DOE facility. Significant violations of
regulations and controls which could lead to releases of material or exposure to workers should
be cause for concern and may be a basis for deciding against use of a particular facility.
Example: A DOE site has a mixed low-level waste stream but lacks treatment capability
for meeting the land disposal restriction treatment standards under RCRA. The site
personnel determine that no other DOE site can treat the waste either. Therefore, the
site personnel look for other options and discover there is a non-DOE facility which will
contract with DOE to treat the waste for treatment standards under RCRA. The site
personnel confirm that the non-DOE facility has the necessary radioactive materials
license, hazardous waste permit, and air permit. The site DOE personnel recommend to
the Field Element Manager that the waste be treated at the non-DOE facility. The Field
Element Manager agrees and directs his employees to make arrangements for
contracting with the treatment facility.
Once a determination has been made by a DOE organization that a non-DOE facility has an
acceptable operational and regulatory history, this determination can be used by other DOE
organizations, e.g., a DOE organization can use the results of a review performed by another
DOE organization or DOE contractor in making a decision on the acceptability of the non-DOE
facility’s performance. However, it is the responsibility of a DOE organization using a non-DOE
facility to ensure, on an annual basis, that the facility is maintaining an acceptable performance
record, either through their own review or that conducted by another DOE organization or
contractor. Documentation of the results of the evaluation of regulatory compliance and
acceptable operational history as discussed above is adequate for showing that the use of the
non-DOE facility will be protective of public health and the environment.
Section 88
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-107
7-09-99
Example: Site Z has previously contracted with a non-DOE low-level waste treatment
facility for size reduction, sorting, and compaction services. As part of their effort to
evaluate the regulatory and operational history of the facility, they conducted a thorough
review of the radioactive materials permit of the facility, the waste acceptance criteria,
and the regulatory authority’s inspection reports. The Site Z personnel also contacted
the regulatory authority and followed up on some of the items which had been identified
as concerns in the inspection reports. Site Z personnel documented a description of their
review and presented their conclusions in a report to the Field Element Manager. Six
months later when Site A personnel were considering using the non-DOE treatment
facility, they obtained a copy of the report from Site Z personnel. On the basis of the Site
Z report, and after confirming that the waste acceptance criteria also encompass their
waste, the Site A personnel make a determination that the regulatory and operational
performance of the non-DOE facility is acceptable.
Cost Effectiveness. In addition to ensuring that use of a non-DOE facility is protective of the
public health and the environment, use of such a facility is to be evaluated for cost-effectiveness.
The evaluation of cost-effectiveness is to consider the cost of onsite management, if it is practical,
the cost of management at another DOE site, and the cost of management at a non-DOE facility.
Cost evaluations consider the cost of the specific management action being contemplated (usually
treatment or disposal), and need to consider collateral management costs such as transportation
and storage, and life-cycle costs. It is appropriate to consider the cost-related complex-wide
implications of not using a DOE facility. The evaluation should include qualitative consideration
of the costs associated with safety and liability of the different options considered. Generally
when all costs are considered, the differential between using a DOE facility and using a
commercial or non-DOE facility needs to be significant before a decision to use the non-DOE
facility will be considered cost effective.
Example: A facility has low-level waste which cannot be disposed of on-site due to site
characteristics which prevent safe disposal. The site contacts the other DOE facilities
which could accept and dispose of this waste. The waste characteristics and packaging
do not pose problems and it is determined that several DOE facilities could accept this
waste. In discussing disposal charges with the DOE sites, the generator site determines
that they have insufficient funds to dispose of all of the low-level waste at these DOE
facilities. Discussions with the DOE facilities does not resolve this issue. It is
determined that a non-DOE facility will accept this waste. The non-DOE facility has
lower disposal costs for the specific waste stream, which will allow the generator site to
dispose all of the radioactive waste. (The non-DOE facility has also been determined by
a DOE organization to have an acceptable operational and regulatory history.) A
justification statement supporting the decision to use the non-DOE facility is written and
accompanies the approval request to the Field Element Manager or designee. The Field
Element Manager reviews the request to authorize use of a non-DOE facility for disposal
Section 89
Chapter I - General Requirements and Responsibilities
I-108 DOE G 435.1-1
7-09-99
of the waste. Following discussions with his staff and managers at another DOE site
which could dispose the waste, the Field Element Managers decides to keep as much
waste as current storage capacity allows and dispose of the rest at the non-DOE facility.
The waste placed in storage is sent to another DOE site for disposal following receipt of
the next fiscal year budget in order to keep the unit costs at the DOE site at a
manageable level.
Evaluations of alternatives which lead to a decision that use of a non-DOE facility is cost effective
are to be documented and should be included with the assessment of acceptable performance
discussed above when the request for approval to use the facility is submitted to the Field Element
Manager.
Meeting Waste Acceptance Criteria. Site personnel must characterize waste to meet the minimum
requirements cited in DOE M 435.1-1, and in sufficient detail to evaluate conformance with the
waste acceptance criteria of the non-DOE facility to which waste is being transferred. The site
should ensure that certification and transfer requirements of DOE M 435.1-1 are implemented for
waste to be sent to a non-DOE storage, treatment or disposal facility. Implementing the
certification and transfer requirements provides a structured process for making sure that the
waste acceptance criteria of the non-DOE facility are met, and that the information necessary for
safe handling is transferred along with the waste.
National Environmental Policy Act. Implementing this requirement and using non-DOE facilities
for reasonably small quantities of waste and special circumstances does not represent a change in
DOE policy that requires a Department-wide review under the National Environmental Policy
Act (NEPA). However, as part of approving the use of non-DOE facilities, the Field Element
Manager must ensure that adequate evaluation under NEPA is performed and documented. For
actions taken under the Comprehensive Environmental Response, Compensation, and Liability
Act, NEPA values should be incorporated in the CERCLA documentation. Important
considerations include (1) impacts of the facility receiving the waste, and (2) impacts of
transporting the waste to the facility, and (3) an evaluation of alternative disposal facilities.
Consultation and Notifications. The requirements for granting and implementing an exemption
for use of a non-DOE facility include consultation and notification both within and external to the
Department. Prior to the Field Element Manager granting an exemption, site personnel must
consult the State agency responsible for radioactive materials regulation. If the proposed
exemption is for disposal of low-level or mixed low-level waste, and the state is in a low-level
waste compact, the compact organization also must be consulted. This consultation with the
compact organization is to occur even if the disposal is planned for a non-compact facility. The
consultation is intended to provide information and enable DOE to consider any views that the
state or compact might have regarding the use of the facility for management of DOE radioactive
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-109
7-09-99
waste. Since consultation with the state and compact are prerequisites to granting an exemption,
sites are to include documentation of the consultation in the exemption request.
Section 90
Once the Field Element Manager has signed the exemption request to use a non-DOE facility,
prior to exercising the exemption, notification of Headquarters, specifically to include consultation
with the Headquarters Office of Environment, Safety, and Health, is required. Information
provided to Headquarters, including the Office of Environment, Safety, and Health, is to include:
• A description of the waste stream including characteristics and expected quantities;
• Alternatives evaluated for the management of the waste, including onsite
management, management at another DOE site, and management at a non-DOE
facility, including a description of why a DOE facility is not available or the use of
one is impractical;
• Documentation of the conclusions made regarding the facility’s regulatory and
operational acceptability;
• Documentation of the cost analysis for alternative disposal sites evaluated;
• A description of the environmental review and documentation supporting the
action;
• Documentation of consultation held with the host state and, if applicable, state
compact; and
• Documentation showing the approval of the exemption request by the Field
Element Manager.
The requirement to consult with the Office of Environment, Safety, and Health may be met
without obtaining written confirmation. The process requires that 1) a copy of the complete
exemption request be provided to the Office of Environmental Policy and Assistance (EH-41),
and 2) exemption requests may not be considered approved until after completion of appropriate
environmental review and documentation, adequate demonstration of need for the exemption and
coordination with appropriate officials of the state and state compact where the non-DOE facility
is located.
The Office of Environmental and Policy Assistance will review the exemption and coordinate with
other EH offices as needed. If EH-41 believes that the exemption would raise environmental
concerns, it will respond to the Field Element Manager within 15 working days. If a response is
not received from EH 41 within the 15 working days, Field Element Managers can assume that
Chapter I - General Requirements and Responsibilities
I-110 DOE G 435.1-1
7-09-99
there are no environmental objections and further consultation with EH is not required.
Therefore, Field Elements must send a copy of the exemption to EH-41 for its review and wait 15
working days before considering the exemption request approved. A copy of the exemption
should also be transmitted to the responsible Program Office and the Office of Waste
Management (EM-30).
In exercising the responsibility assigned under this requirement, Field Element Managers and their
staffs should avoid pursuing the use of State Compact disposal facilities. The Department has a
long-standing practice of avoiding actions which have the potential to affect State Compact
disposal facilities. The Department would only consider the use of State Compact disposal
facilities if petitioned by the State Compact for reasons such as economic viability.
Finally, the Field Element Manager must ensure that the state hosting the radioactive waste
management facility is notified prior to actually shipping waste to the facility. Notification can be
on a campaign or waste stream basis; it is not necessary under this requirement that notification be
made for each shipment.
Section 91
Compliance with this requirement is demonstrated by a site having a process for performing and
documenting the actions necessary to get an exemption for use of non-DOE facilities, and by the
site having records which show that the necessary evaluations, consultations, approvals and
notifications have occurred.
Supplemental References:
1. Whitfield, 1991. R.P. Whitfield to L.P. Duffy, memorandum, Commercial Disposal of
Department of Energy Radioactive (By-Product and Low-Level) and Mixed Wastes, U.S.
Department of Energy, Washington, D.C., September 13, 1991.
2. Lytle and Whitfield, 1993. J.E. Lytle and R.P. Whitfield to L.P. Duffy, memorandum,
Commercial Disposal of Department of Energy Radioactive (By-Product and Low-Level)
and Mixed Wastes, U.S. Department of Energy, Washington, D.C., October. 12, 1993.
3. Alm, 1996. A.L. Alm to Department of Energy Operations Office Managers and
Department of Energy Field Office Managers, memorandum, Delegation of Authority to
Grant Exemptions to Department of Energy Order 5820.2A to Allow for the Use of
Commercial Facilities for Department of Energy Low-Level Waste, U.S. Department of
Energy, Washington, D.C., October. 24, 1996.
4. DOE, 1999. Commercial Disposal Policy Analysis for Low-Level and Mixed Low-Level
Wastes, U.S. Department of Energy, Washington, D.C., March 9, 1999.
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-111
7-09-99
I. 2.F. Field Element Managers.
Field Element Managers are responsible for:
(5) Environmental Restoration, Decommissioning, and Other Cleanup Waste.
Ensuring the management and disposal of radioactive waste resulting from
environmental restoration activities, including decommissioning, meet the
substantive requirements of DOE O 435.1, Radioactive Waste Management,
and this Manual. Environmental restoration activities using the CERCLA
process (in accordance with Executive Order 12580) may demonstrate
compliance with the substantive requirements of DOE O 435.1, Radioactive
Waste Management, and this Manual (including the Performance Assessment
and performance objectives, as well as the Composite Analysis) through the
CERCLA process. However, compliance with all substantive requirements
of DOE O 435.1 not met through the CERCLA process must be
demonstrated. Environmental restoration activities which will result in the
off-site management and disposal of radioactive waste must meet the
applicable requirements of DOE O 435.1, Radioactive Waste Management,
and this Manual for the management and disposal of those off-site wastes.
Field Elements performing environmental restoration activities involving
development and management of radioactive waste disposal facilities under
the CERCLA process shall:
(a) Submit certification to the Deputy Assistant Secretary for Environmental
Restoration that compliance with the substantive requirements of DOE O
435.1 have been met through application of the CERCLA process; and
(b) Submit the decision document, such as the Record of Decision, or any
other document that serves as the authorization to dispose, to the Deputy
Assistant Secretary for Environmental Restoration for approval.
Objective:
The objective of this requirement is to ensure that radioactive waste generated as a result of
environmental restoration, decommissioning, or other cleanup is managed in a manner that meets
the requirements of DOE O 435.1, Radioactive Waste Management, and DOE M 435.1-1,
Radioactive Waste Management Manual.
Chapter I - General Requirements and Responsibilities
Section 92
I-112 DOE G 435.1-1
7-09-99
Discussion:
This requirement applies to sites undergoing environmental restoration (including
decommissioning) pursuant to regulatory authorities including, but not necessarily limited to, the
Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), the
Resource Conservation and Recovery Act (RCRA), the Atomic Energy Act of 1954, as amended,
and applicable state requirements. This guidance clarifies how sites developing and managing
facilities for management and disposal of radioactive waste resulting from environmental
restoration activities are to comply with the requirements of DOE O 435.1, Radioactive Waste
Management. The requirements of DOE M 435.1-1 do not apply to other cleanup requirements
addressed by CERCLA or other authorities, such as determinations of protectiveness, cleanup
levels, or cleanup methods associated with remediation of spills and releases. Additionally, these
requirements do not apply to actions performed under environmental restoration which involve
commercial facilities. The original guidance on this topic was articulated in: 1) Policy for
Demonstrating Compliance with DOE 5820.2A for Onsite Management and Disposal of
Environmental Restoration Low-Level Waste under the Comprehensive Environmental Response,
Compensation, and Liability Act, May 31, 1996 (DOE, 1996); and 2) Guidance for Complying
with DOE 5820.2A, Radioactive Waste Management, for Onsite Management and Disposal of
Low-Level Waste (LLW) from Environmental Restoration Activities (Alm, 1997). These policies
were prepared by the Department in response to Defense Nuclear Facilities Safety Board
Recommendation 94-2. In its recommendation, the Board had indicated the need to demonstrate
how disposal and waste management activities performed during environmental restoration
activities ensured compliance with DOE’s radioactive waste management requirements. The
major concepts of these policies are:
C the CERCLA requirements and DOE M 435.1-1 requirements include significant
overlap in their substantive requirements given both are designed to ensure safe
management and disposal of waste;
C the CERCLA process is to be used to comply with the requirements of DOE M
435.1-1 for environmental restoration actions;
C the substantive requirements of DOE M 435.1-1 should be directly incorporated
into the CERCLA process to the extent practical and consistent with site-specific
technical and regulatory issues; and
C the Department must demonstrate compliance with the substantive requirements of
DOE M 435.1-1 to fulfill its Atomic Energy Act responsibilities.
To fulfill DOE’s Atomic Energy Act responsibilities, the Department must demonstrate
compliance with the substantive requirements of DOE M 435.1-1 for low-level waste disposal
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-113
7-09-99
facilities managed under CERCLA. A crosswalk between the CERCLA and the DOE M 435.1-1
requirements needs to be prepared and reviewed as described below when the cleanup action
involves development and management of a radioactive waste disposal facility. It is not necessary
to prepare a crosswalk to demonstrate compliance with DOE M 435.1-1 requirements for
environmental restoration activities that do not involve development and management of a
radioactive waste disposal facility.
Section 93
Regarding the distinction between substantive and administrative requirements, DOE follows the
guidance provided in the rulemakings published for the National Contingency Plan (NCP) (59 FR
47384, September 15, 1994). The preambles to the NCP notices in the Federal Register (53 FR
51394, December 21, 1988; 55 FR 8666, March 8, 1990; and 59 FR 47384, September 15, 1994)
state that substantive requirements are those that set environmental protection requirements,
criteria, or limitations; all other requirements are considered administrative.
Management and Disposal of Environmental Restoration Wastes. The sites to which the
crosswalk requirement applies are those using the CERCLA process to develop and manage
facilities for disposal of radioactive waste resulting from environmental restoration activities. (An
important exception is the disposal of 11e.(2) byproduct material wastes which are subject,
instead, to the requirements of the Uranium Mill Tailings Radiation Control Act). These sites
may be following CERCLA either because they are listed on the National Priorities List (NPL) or
because the regulatory structure established in cleanup strategies (e.g., negotiated agreements) is
based on CERCLA authority and procedures. Under Executive Order 12580, Superfund
Implementation, DOE is the lead agency for responding to a release or threatened release of
hazardous substances, including radionuclides, from any facility or vessel under the jurisdiction,
custody, or control of DOE. As such, DOE has the authority to take appropriate response actions
in accordance with CERCLA at sites not listed on the NPL. Response actions, consisting of
removal actions (40 CFR 300.415) or remedial actions (40 CFR 300.430 and 300.435), may
include onsite disposal, use of access/institutional controls, or other appropriate and feasible
actions which ensure protection of human health and the environment.
A site which is not listed on the NPL may also perform corrective or remedial actions which result
in onsite disposal of environmental restoration wastes. Such activities may be conducted pursuant
to regulatory authorities other than CERCLA including, but not necessarily limited to, RCRA,
applicable state requirements, and the Atomic Energy Act of 1954, as amended. When DOE is
conducting cleanup work at a non-NPL site under its Atomic Energy Act authority or under any
other non-CERCLA authority, the substantive and full procedural requirements of DOE M 435.1
1 apply. When using CERCLA authority to conduct a response action that involves onsite waste
disposal at a non-NPL site, responsible DOE elements need to act consistent with the NCP as
promulgated in 40 CFR Part 300 (including adherence to the requirements for regulatory agency
involvement and public participation) if it is the intent of the Department for the CERCLA
process to satisfy the requirements of DOE M 435.1-1.
Chapter I - General Requirements and Responsibilities
I-114 DOE G 435.1-1
7-09-99
The term onsite under CERCLA is defined as “the areal extent of contamination and all suitable
areas in very close proximity to the contamination and necessary for implementation of the
response action” [40 CFR 300.5]. Additionally, CERCLA Section 104 (d)(4) states “where two
or more noncontiguous facilities are reasonably related on the basis of geography, or on the basis
of the threat, or potential threat to the public health or welfare or the environment, the President
may, in his discretion, treat these related facilities as one.” Therefore, the definition of onsite for
any specific Department installation may include noncontiguous facilities within an installation as
agreed by the parties involved (e.g., DOE, EPA, the State, and stakeholders) and documented in
interagency agreements and/or records of decision.
Section 94
In selecting Applicable or Relevant and Appropriate Requirements (ARARs) for radioactive waste
disposal facilities in accordance with EPA’s guidance CERCLA Compliance with Other Laws
Manual, performance objectives and substantive requirements of DOE M 435.1-1 are included as
information “to be considered” (TBC) rather than specific ARARs because DOE Orders are not
promulgated under the Administrative Procedures Act. However, to meet its Atomic Energy Act
responsibilities, the Department must still demonstrate compliance with the requirements of the
DOE M 435.1-1. To do this, a CERCLA/DOE M 435.1-1 crosswalk may be prepared, showing
how DOE M 435.1-1 was addressed through the CERCLA process. If any substantive Order
requirement was not satisfied through the CERCLA process, it would need to be applied
separately and complied with under the DOE M 435.1-1 process.
An example of a crosswalk between CERCLA requirements and DOE’s waste management
requirements is provided in Attachment 1. This example appeared as an attachment to both the
1996 and 1997 policies referenced above. Although this example was developed to illustrate
compliance with the requirements of DOE 5820.2A and was referred to as a roadmap rather than
a crosswalk, it is nonetheless a valid illustration of the content and level of detail expected in
crosswalks linking the requirements of DOE M 435.1-1 with the requirements of CERCLA. The
example is drawn from the actual comparison performed for the Fernald Environmental
Management Project.
The crosswalk should state if the specific DOE M 435.1-1 performance objective/requirement
was identified as an ARAR/TBC in the CERCLA process, or whether an equivalent requirement
from a promulgated Federal or State law was determined to be an ARAR and was met. The
CERCLA/DOE M 435.1-1 crosswalk should provide specific references to applicable sections of
the site-developed regulatory documentation (e.g., RI/FS) which provide the details that support
the statements made in the crosswalk. The tabular summary shown in Attachment 1 should be
included for completeness. The crosswalk should also provide a brief one or two paragraph
summary of the employed technical review process (e.g., identify reviewing organizations,
regulators, stakeholders, and major comments which resulted in significant changes to the remedy
selection and design).
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-115
7-09-99
In essence, when the CERCLA process is being used to plan for onsite disposal of CERCLA
waste, compliance with the performance objectives of DOE M 435.1-1 is essential and must be
documented. While the format in which compliance is demonstrated is not prescribed,
Attachment 1 offers a suggested means to satisfy this need. As noted above, the crosswalk
presented in Attachment 1 is a real example of a crosswalk prepared in accordance with the
original 1996 CERCLA policy for compliance with the requirements of DOE 5820.2A, and
illustrates the content and level of detail expected. If certain substantive requirements of DOE M
435.1-1 cannot be incorporated into the CERCLA documents, then those requirements must be
met separately and approved using the DOE M 435.1-1 process.
Section 95
Example: Site B is not on the NPL but consistent with DOE policy and Executive Order
12580, is following the CERCLA process in identifying and addressing risks posed by
radioactive wastes previously disposed of at the site. One of the remedial alternatives at
the site calls for building a new onsite disposal facility. The FS includes calculations for
the new facility that are the same as those required for a performance assessment under
DOE M 435.1-1, and reports the results under the detailed evaluation of alternatives
against the CERCLA criteria. In addition, the risk evaluation prepared for the onsite
disposal remedial alternative includes an assessment of all interactive sources and was
submitted as an appendix to the FS. Therefore, the site met the substantive requirements
of DOE M 435.1-1 through their RI/FS and associated process, and documented this
compliance by developing a crosswalk. The CERCLA process is sufficient and there is
no need to conduct any separate analyses.
In some situations, analyses performed under CERCLA will not be identical to those conducted
under DOE M 435.1-1 due to differing assumptions or methodologies (e.g., related to land use,
institutional controls, etc.). In these cases, the brief statement in the crosswalk should identify the
issue and provide an explanation of how the assumption or methodology used under CERCLA
demonstrates compliance with requirements of DOE M 435.1-1.
Example: At Site C, one of DOE’s largest NPL sites, an onsite disposal cell is being
considered as part of an overall remedial strategy under CERCLA. A risk evaluation is
prepared in accordance with EPA’s Risk Assessment Guidance for Superfund: Human
Health Evaluation (Part A). For the remedial alternatives involving the proposed onsite
disposal cell, an inadvertent intruder scenario is not evaluated based on the site’s long
term land use plan. In this case, the CERCLA/DOE M 435.1-1 crosswalk statement
regarding compliance for this specific requirement, identifies the land use assumptions
and explains how the site’s regulatory process ensures compliance. The crosswalk
explains that under CERCLA, the remedy would be evaluated no less than every five
years to ensure it is functioning as intended and remains effective in reducing risks and
complying with ARARs. This crosswalk statement and the accompanying table would
then document compliance with this requirement of DOE M 435.1-1.
Chapter I - General Requirements and Responsibilities
I-116 DOE G 435.1-1
7-09-99
CERCLA requires analysis of risks from all pathways/all sources [see 40 CFR 300.430(d) and 40
CFR 300.430(e)(2)(I)(A)]. However, there is no prescribed methodology for performing such an
evaluation. The Department has established a consistent approach for assessing interactive
sources; the document entitled Guidance for a Composite Analysis of the Impact of Interacting
Source Terms on the Radiological Protection of the Public from LLW Disposal Facilities can be
used to evaluate the impacts potentially resulting from radioactive waste disposal facilities. The
completed composite analysis will be an effective management tool for understanding the site-
wide implications of multiple source-terms.
Example: Fernald, an NPL site, is following CERCLA for cleanup activities and is
disposing of some environmental restoration wastes in an onsite low-level waste disposal
facility. To meet the requirements of DOE M 435.1-1 and CERCLA, the site prepared a
Comprehensive Response Action Risk Evaluation as part of its RI/FS process. This
Evaluation was a key component of the document prepared by the site to demonstrate
compliance with CERCLA and DOE M 435.1-1.
Section 96
Field Element Managers are to submit the appropriate CERCLA documentation to the Deputy
Assistant Secretary for Environmental Restoration. For purposes of DOE O 435.1 and DOE M
435.1-1, the term “appropriate CERCLA documentation” means the written materials prepared to
demonstrate compliance with the substantive requirements of DOE M 435.1-1 for low-level waste
disposal facilities managed under CERCLA. Specifically included in such written materials are
crosswalks between CERCLA requirements and DOE M 435.1-1 requirements which are used as
the basis for issuance of a disposal authorization by the Deputy Assistant Secretary for
Environmental Restoration. Based on the appropriate CERCLA documentation, the Field
Element Manager certifies that compliance with the substantive requirements of DOE M 435.1-1
has been achieved through application of the CERCLA process. Any other analyses that have not
been incorporated into the CERCLA process require a separate review. The Deputy Assistant
Secretary may assign the LFRG the task of reviewing the information submitted by the Field
Element Manager. In this instance, the documents would be reviewed against the criteria set forth
in the guidance entitled, Department of Energy LLW Disposal Facility Federal Review Group
Performance Assessment and Composite Analysis Review Guidance Manual (the Review Guide).
Based on the content of the crosswalk, the LFRG will determine whether it needs to review the
detailed analysis. The LFRG will report its conclusions to the Deputy Assistant Secretary for
Environmental Restoration. The Deputy Assistant Secretary for Environmental Restoration will
use this information as the basis for deciding whether to issue a disposal authorization based on
DOE’s Atomic Energy Act responsibilities.
The disposal authorization statement does not impact the decision documented in the CERCLA
Record of Decision on whether to build a facility because this decision is made through the
CERCLA process. The disposal authorization statement specifies limits and conditions on design,
construction, operations, and closure of the radioactive waste disposal facility. The disposal
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-117
7-09-99
authorization statement could be included as part of the Record of Decision. If this is the case,
then the guidance on disposal authorization (Chapter IV) should be followed during the
development of a ROD on CERCLA radioactive waste disposal facilities, to the extent practical.
However, it should be understood that compliance with requirements of a law (e.g., CERCLA)
does not release DOE of compliance with another law (e.g., Atomic Energy Act of 1954, as
amended). DOE must determine that whatever actions are taken, Atomic Energy Act
requirements are met.
Example: At Site F, DOE and the stakeholders evaluated the disposal of environmental
restoration waste in an onsite disposal cell. The site is using the CERCLA process. The
CERCLA RI/FS team followed the DOE “Guidance for a Composite Analysis of the
Impact of Interacting Source Terms on the Radiological Protection of the Public from
LLW Disposal Facilities” when assessing the sources potentially interacting with the
proposed disposal facility. Therefore a separate composite analysis to comply with the
requirements of DOE M 435.1-1 was not necessary. A crosswalk was developed showing
the linkage between CERCLA requirements and DOE M 435.1-1 requirements. Based
upon the crosswalk, the Field Element Manager certified that the facility would meet all
of the DOE M 435.1-1 requirements and submitted the crosswalk to the Deputy Assistant
Secretary for Environmental Restoration. The Deputy Assistant Secretary turned to the
LFRG to review the crosswalk and the LFRG reported its conclusions to the Deputy
Assistant Secretary. Based on the LFRG report, the Deputy Assistant Secretary issued a
disposal authorization.
Section 97
Environmental restoration activities will generate radioactive waste requiring off-site disposal.
Management of wastes that will be disposed of off-site must meet all the requirements of DOE M
435.1-1. There is no need to prepare a crosswalk documenting how the DOE M 435.1-1
requirements have been addressed in the CERCLA documents and process.
In addition, if DOE plans to use the services of a commercial facility for management of
radioactive waste from environmental restoration activities, the requirements of Section I.2.F.(4)
must be met. These requirements can be included in the appropriate CERCLA documentation or
handled separately.
Demonstrating Compliance. To fulfill DOE’s Atomic Energy Act responsibilities, the Department
must demonstrate compliance with the substantive requirements of DOE M 435.1-1 for low-level
waste disposal facilities managed under CERCLA. Appropriate CERCLA documentation (define
above) may be used to demonstrate compliance with the substantive requirements of DOE M
435.1-1. This may include a crosswalk prepared to demonstrate that the CERCLA process
addresses the requirements of DOE M 435.1-1. In addition, the Field Element Manager must
submit certification to the Deputy Assistant Secretary for Environmental Restoration that the
Chapter I - General Requirements and Responsibilities
I-118 DOE G 435.1-1
7-09-99
substantive requirements have been met for the disposal facility. A disposal authorization must be
issued by the Deputy Assistant Secretary for Environmental Restoration.
Supplemental References:
1. Alm, 1997. Alvin L. Alm (DOE) to John T. Conway (DNFSB), letter, Guidance for
Complying With DOE Order 5820.2A, Radioactive Waste Management for Onsite
Management and Disposal of Low-Level Waste Resulting from Environmental
Restoration Activities, U.S. Department of Energy, Washington, D.C., January 9, 1997.
2. DOE, 1996. Policy for Demonstrating Compliance with DOE Order 5820.2A for Onsite
Management and Disposal of Low-Level Wastes Under the Comprehensive
Environmental Response, Compensation, and Liability Act, U.S. Department of Energy,
Washington, D.C., May 31, 1996.
3. EPA. National Oil and Hazardous Substances Pollution Contingency Plan, 40 CFR Part
300, U.S. Environmental Protection Agency, Washington, D.C.
4. EPA, 1988. “Proposed Rule; National Oil and Hazardous Substances Pollution
Contingency Plan, 40 CFR Part 300,” Federal Register, Vol. 53, No. 245, U.S.
Environmental Protection Agency, Washington, D.C., December 21, 1988.
5. EPA, 1990. “Final Rule, National Oil and Hazardous Substances Pollution Contingency
Plan, 40 CFR Part 300,” Federal Register, Vol. 55, No. 46, U.S. Environmental
Protection Agency, Washington, D.C., March 8, 1990.
6. EPA, 1994. “Final Rule, National Oil and Hazardous Substances Pollution Contingency
Plan, 40 CFR Parts 9 and 300,” Federal Register, Vol. 59, No. 178, U.S. Environmental
Protection Agency, Washington, D.C., September 15, 1994.
7. EPA, 1988. CERCLA Compliance with Other Laws Manual, Draft Guidance,
EPA/540/G-89/006, U.S. Environmental Protection Agency, Washington, D.C., August 8,
1988.
8. EPA, 1989. CERCLA Compliance with Other Laws Manual, Part II - Clean Air Act and
Other Environmental Statutes and State Requirements, Interim Final, EPA/540/G-89
009, U.S. Environmental Protection Agency, Washington, D.C., August, 1989.
9. Superfund Implementation, Executive Order 12580, Washington, D.C., October 26, 1993.
Chapter I - General Requirements and Responsibilities
Section 98
DOE G 435.1-1 I-119
7-09-99
10. EPA, 1989. Risk Assessment Guidance for Superfund, Human Health Evaluation
Manual (Part A), Interim Final, EPA/540/1-89/002, U.S. Environmental Protection
Agency, Washington, D.C., December 1989.
Chapter I - General Requirements and Responsibilities
I-120 DOE G 435.1-1
7-09-99
ATTACHMENT 1
SELECTED PORTIONS FROM A SAMPLE CERCLA/DOE
ORDER 5820.2A [CROSSWALK]
INTRODUCTION
This example of a crosswalk between CERCLA requirements and DOE’s waste management
requirements appeared as an attachment to both the 1996 and 1997 CERCLA policies
referenced above. Although this example was developed to illustrate compliance with the
requirements of DOE 5820.2A and was referred to as a roadmap rather than a crosswalk, it is
nonetheless a valid illustration of the content and level of detail expected in crosswalks linking
the requirements of DOE M 435.1-1 with the requirements of CERCLA. The example is drawn
from the actual comparison performed for the Fernald Environmental Management Project.
This [Crosswalk] provides specific examples of how the Fernald Environmental Management
Project (FEMP) has substantively met the objectives/requirements of DOE 5820.2A. Each
example specifically identifies how each performance objective or requirement was/will be
satisfied at the FEMP via the CERCLA process.
DOE Order 5820.2A is applicable to the FEMP because selected remedies for three of the five
operable units (OUs) include onsite disposal. The FEMP onsite disposal facility (OSDF) will
contain LLW from the remedial activities to be conducted under CERCLA. This [Crosswalk]
demonstrates that the FEMP CERCLA remedial activities of evaluation, design, construction, and
waste placement in the onsite disposal facility has/will substantively satisfy the applicable
requirements and intent of DOE Order 5820.2A, Chapter III, Management of LLW.
The CERCLA process satisfies the requirements and intent of DOE Order 5820.2A through
compliance with ARARs, TBCs, and the information and planning that is derived during the
implementation and completion of the CERCLA process, such as the completion of the CERCLA
mandated remedial investigations, feasibility studies, remedial designs, and remedial planning
documents. This [Crosswalk] will refer to the requirements that mandate these remedial
investigations, feasibility studies, remedial designs, remedial planning documents, and the
guidance used for implementation, as CERCLA Drivers. The ARARs, TBCs, and CERCLA
Drivers serve as the basis for complying with the requirements of DOE 5820.2A and the
[Crosswalk] document demonstrates that compliance has been attained. This [Crosswalk] is
specific to the FEMP alone. The FEMP CERCLA process and associated ARARs, and TBCs
that have been utilized will differ slightly from the ARARs, and TBCs that will be employed at
other CERCLA sites within the DOE complex. Page A2-8 includes a table that summarizes the
requirements of DOE 5820.2A that have been satisfied through the FEMP CERCLA process.
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-121
7-09-99
IDENTIFICATION OF COMPLIANCE WITH THE SUBSTANTIVE REQUIREMENTS
OF DOE ORDER 5820.2A
DOE ORDER 5820.2A CHAPTER III (3) (a) PERFORMANCE OBJECTIVES
Purpose
Section 99
This section of DOE 5820.2A identifies the performance based objectives that a LLW disposal
facility must achieve. The objectives are: (1) protection of public health and safety; (2) releases
to the environment from the LLW disposal facility shall be ALARA, and must not result in an
effective dose equivalent (EDE) that exceeds 25 mrem/year to any member of the public; (3)
prevent the possibility of a 100 mrem/year continuous exposure or 500 mrem acute exposure of
an inadvertent intruder after institutional controls have terminated (100 years); and (4) protect
ground-water resources consistent with Federal, State, and local requirements.
Statement of Compliance for 3(a)(1)
Compliance with this requirement was attained through applying the two CERCLA threshold
criteria as identified in the NCP, which are protecting human health and the environment and
identifying and complying with ARARs. Substantive compliance with this requirement was
further accomplished through the design of the Onsite Disposal Facility (OSDF) and the
establishment of waste acceptance criteria (WAC), which will result in the dose to the public
being lower than the established exposure limits and by providing protection to ground-water
resources.
Identification of ARARs, TBCs, and/or CERCLA Drivers for 3(a)(1)
ARARs: 40 CFR 300.430 (e)(9)(iii)(A), CERCLA Threshold Criteria
Statement of Compliance for 3(a)(2)
Compliance with this requirement was attained through the evaluation of all sources of risk to the
public which was completed in the CERCLA Feasibility Study (FS) risk assessments and the
Comprehensive Response Action Risk Evaluation (CRARE) performed for the FEMP. The
designed containment system (multi-layer cap and liner) of the OSDF eliminates all exposure
pathways except groundwater. Protecting the public through the groundwater pathway was
addressed by meeting applicable Safe Drinking Water Act (SDWA) maximum contaminant level
(MCL) groundwater standards. The established waste acceptance criteria (WAC) for the OSDF
ensure that the MCLs are not exceeded in the groundwater for 1,000 years. By meeting the
proposed SDWA uranium MCL of 20 parts per billion (ppb), the exposure dose from
Chapter I - General Requirements and Responsibilities
I-122 DOE G 435.1-1
7-09-99
groundwater will be below the 25 mrem per year EDE requirement for 1,000 years into the
future.
Identification of ARARs, TBCs, and/or CERCLA Drivers for 3(a)(2)
ARARs: OAC 3745-27-08 (C), Landfill Construction
40 CFR 61.92-93, National Emissions Standards for Hazardous Air Pollutants
(NESHAPS) for emissions of radionuclides other than radon from the Department
facilities
40 CFR 61.192, NESHAPS for emissions of radon from Department facilities
TBCs: DOE 5400.5 Chapter II (1)(a), (b), (3)(a)(5), Chapter IV (4)(c), Radiation Protection
of the Public and the Environment
DOE 5820.2A Chapter III (3)(a)(2), Protection of the General Population from
Releases of Radioactivity
CERCLA Drivers: 40 CFR 300.430, Remedial Investigation/Feasibility Study (RI/FS) and
selection of remedy
40 CFR 300.435, Remedial Design (RD)/Remedial action (RA), operation
and maintenance
US EPA, 1988, Guidance for Conducting Remedial Investigations and
Feasibility Studies Under CERCLA
US EPA, 1988, Superfund Exposure Assessment Manual
US EPA, 1989, Risk Assessment Guidance for Superfund: Human Health
Evaluation manual, Part A, Interim Final
US EPA, Guidance on Preparing Superfund Decision Documents: The
Proposed Plan (PP), The Record of Decision (ROD), Explanation of
Significant Differences, the ROD Amendment
Section 100
Statement of Compliance for 3(a)(3)
Compliance with this requirement was satisfied through the implementation of permanent
institutional controls, and the long-term permanence design of the OSDF. The Operable Unit 2
(OU2) and Operable Unit 5 (OU5) RODs specify that the final land use for the OSDF be
restricted with perpetual federal ownership and maintenance of institutional controls (such as
warning signs and fencing). The NCP and the OU2 and OU5 RODs also specify the design of a
containment system with long-term permanence. The OSDF has a designed nine-foot multi-layer
cap system which includes a three-foot rock barrier layer, and a five-foot multi-layer liner system.
To ensure proper performance of the institutional controls and the containment system, their
overall performance will be reviewed every five years as required by the NCP. The
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-123
7-09-99
implementation of perpetual institutional controls and the designed containment system precludes
the inadvertent intrusion exposure scenario.
Identification of ARARs, TBCs, and/or CERCLA Drivers for 3(a)(3)
ARARs: OAC 3745-27-08 (C), Landfill Construction
OAC 3745-27-11 (H), Landfill Final Closure
OAC 3745-27-14 (A), Landfill Post-Closure Care
TBCs: DOE 5400.5 Chapter II (1)(a)(b), Radiation Protection of the Public and the
Environment
CERCLA Drivers: 40 CFR 300.430, RI/FS and selection of remedy
US EPA, 1988, Guidance for Conducting RI/FS Under CERCLA
US EPA, 1988, Superfund Exposure Assessment Manual
US EPA, 1989, Risk Assessment Guidance for Superfund: Human Health
Evaluation Manual, Part A, Interim Final
US EPA, Guidance on Preparing Superfund Decision Documents: The PP,
the ROD, Explanation of Significant Differences, and the ROD
Amendment
Statement of Compliance for 3(a)(4)
Compliance with this requirement was met through the development of the WAC and design of
the OSDF. These actions resulted in the protection of the groundwater resources in accordance
with all applicable groundwater standards. The groundwater modeling for the OSDF WAC
development demonstrated that the aquifer would be protected to the proposed uranium MCL for
1,000 years into the future. The DOE Fernald Area Office (DOE-FN), DOE Headquarters
(DOE-HQ), the United States Environmental Protection Agency (USEPA), and Ohio
Environmental Protection Agency (EPA) have approved the modeling in the OU2, and OU5 FSs.
Identification of ARARs, TBCs, and/or CERCLA Drivers for 3(a)(4)
CERCLA Drivers: 40 CFR 300.430, RI/FS and selection of remedy
40 CFR 300.435, RD/RA, operation and maintenance
US EPA, 1988, Guidance for Conducting RI/FS Under CERCLA
US EPA, 1988, Superfund Exposure Assessment Manual
US EPA, 1989, Risk Assessment Guidance for Superfund: Human Health
Evaluation Manual, Part A, Interim Final
US EPA, Guidance on Preparing Superfund Decision Documents: The PP,
the ROD, Explanation of Significant Differences, the ROD Amendment
Chapter I - General Requirements and Responsibilities
I-124 DOE G 435.1-1
7-09-99
References for Requirement 3(a)
OU2 Risk Assessment (OU2 FS, Appendix C Risk Evaluation), OU5 Risk Assessment (OU5 FS,
Appendix F Fate and Transport Modeling, Appendix G Short Term Risk Assessment, and
Appendix H CRARE), and OU3 Risk Assessment (OU3 FS, Appendix H Short Term Risk
Assessment, Appendix I CRARE), OU2 ROD, OU5 ROD, and OU3 ROD, Onsite Disposal
Facility (OSDF) Design Criteria Package (OSDF Design Specifications Package, OSDF Design
Calculations Package, OSDF Design Drawings Package), OSDF Support Plans (Appendix A
Impacted Materials Placement Plan)
Section 101
DOE ORDER 5820.2A CHAPTER III (3)(h) LONG-TERM STORAGE
Purpose
This section requires that the long-term storage of LLW be conducted in a manner in which the
performance objectives of Chapter III (3)(a) are maintained.
Statement of Compliance for 3(h)(1), (2), (3), and (4)
The long-term storage requirements specified in DOE 5820.2A are not applicable to the remedial
activities associated with the disposal of waste in the OSDF because there are no plans that
include the long-term storage of waste prior to final disposal in the onsite disposal facility.
DOE ORDER 5820.2A CHAPTER III (3)(k) ENVIRONMENTAL MONITORING
Purpose
This section requires that the LLW disposal facility be monitored by an environmental monitoring
program that can measure (through the monitoring of the applicable environmental media)
operational effluent releases, migration of radionuclides, disposal facility subsidence, and changes
in the disposal facility and site parameters that may effect the long-term performance of the
disposal facility.
Statement of Compliance with 3(k)(1)
Compliance with this requirement will be satisfied by utilization of the Integrated Environmental
Monitoring Plan (IEMP) developed for the FEMP and the OSDF Support Plans. These plans will
include monitoring of OSDF associated ground water, surface water, air, leachate, leak detection
system, and subsidence.
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-125
7-09-99
Identification of ARARs, TBCs, and/or CERCLA Drivers for 3(k)(1)
ARARs: OAC 3745-27-10, Ground-water Monitoring Program
OAC 3745-27-19(E)(26), Sanitary Landfill Operation; maintain integrity of landfill
components
OAC 3745-27-19(J)(1), (4) - Sanitary Landfill Operations; surface water control
structures
TBCs: DOE 5820.2(A) Chapter III(3)(k), Environmental Monitoring
CERCLA Drivers: 40 CFR 300.435, RD/RA, operation and maintenance
Statement of Compliance with 3(k)(2)
See discussion above stating compliance with 3(k)(1).
Identification of ARARs, TBCs, and/or CERCLA Drivers for 3(k)(2)
ARARs: OAC 3745-27-10, Ground-water Monitoring Program
OAC 3745-27-08(C)(1), (2), (3), (4), (5), (6), (7), (9), Leachate collection and
storage; structures must be monitored
OAC 3745-27-19(E)(26), Sanitary Landfill Operation; maintain integrity of landfill
components
OAC 3745-27-19(J)(1), (4) - Sanitary Landfill Operations; surface water control
structures
TBCs: DOE 5820.2(A) Chapter III(3)(k), Environmental Monitoring
CERCLA Drivers: 40 CFR 300.435, RD/RA, operation and maintenance
Statement of Compliance with 3(k)(3)
See discussion above stating compliance with 3(k)(1).
Identification of ARARs, TBCs, and/or CERCLA Drivers for 3(k)(3)
ARARs: OAC 3745-27-10, Ground-water Monitoring Program
OAC 3745-27-19(K)(1), (2), (3) - Sanitary Landfill Operations; leachate detection
TBCs: DOE 5820.2(A) Chapter III(3)(k), Environmental Monitoring
CERCLA Drivers: 40 CFR 300.435, RD/RA, operation and maintenance
Chapter I - General Requirements and Responsibilities
I-126 DOE G 435.1-1
7-09-99
Statement of Compliance with 3(k)(4)
See discussion above stating compliance with 3(k)(1).
Identification of ARARs, TBCs, and/or CERCLA Drivers for 3(k)(4)
ARARs: OAC 3745-27-10, Ground-water Monitoring Program
TBCs: DOE 5820.2(A) Chapter III(3)(k), Environmental Monitoring
CERCLA Drivers: 40 CFR 300.435, RD/RA, operation and maintenance
References for Requirement 3(k)
Section 102
IEMP, Onsite Disposal Facility Support Plans (Appendix C Surface-Water Management and
Erosion Control, and Appendix F Air Monitoring Plan)
FEMP CERCLA REVIEW PROCESS
The CERCLA process at the FEMP involves many resources, organizations, and agencies, which
provides for a thorough review and approval process. Several subject matter expert resources are
utilized during the internal review process at the FEMP by the Department contractor.
Additionally, resources from the major contractor teaming partners are utilized during the internal
review.
The Fernald Area Office reviews and approves all CERCLA documents. The public stakeholders
also have review and comment capabilities throughout the process. Direct involvement in
information exchange meetings and technical review of CERCLA documents by US EPA and
Ohio EPA in the FEMP CERCLA process is required, pursuant to the terms of the 1986 Federal
Facility Compliance Agreement, and a 1990 Consent Agreement between the Department and US
EPA, and a Consent Decree between the Department and Ohio EPA. The US EPA including the
US EPA Radiation and Risk Assessment specialists, the US EPA environmental contractor, the
Ohio EPA, and the Ohio EPA environmental contractor have review and approval authority on all
CERCLA documents.
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-127
7-09-99
REQUIREMENTS IN DOE ORDER 5820.2A, RADIOACTIVE WASTE
MANAGEMENT, CHAPTER III, SECTION 3, MANAGEMENT OF LLW, SATISFIED
THROUGH THE CERCLA PROCESS
The following table identifies requirements a. through m. of DOE 5820.2A, Chapter III, Section 3
that have been satisfied at the FEMP via the CERCLA process. These requirements have been
satisfied through the compliance with ARARs, TBCs, and other drivers of the CERCLA process.
Since these requirements were incorporated as part of the CERCLA process, they do not need to
be applied separately.
For completeness, the table also identifies those requirements that are not incorporated or
satisfied through the CERCLA process. In the case of the FEMP, none were identified for this
category. if any had been identified, they would need to be applied separately and complied with
under the DOE 5820.2A process.
DOE 5820.2A, Radioactive Waste
Management, Chapter III, LLW
Waste Management, Section 3,
Requirements
Requirements satisfied
via the FEMP CERCLA
process
Requirements not
satisfied via the FEMP
CERCLA process
a. Performance Objectives a.1, a.2, a.3, a.4
b. Performance Assessment b.1, b.2, b.3
c. Waste Generation c.1, c.2, c.3, c.4
d. Waste Characterization d.1, d.2, d.3
e. Waste Acceptance Criteria e.1, e.2, e.3, e.4, e.5
f. Waste Treatment f.1, f.2, f.3, f.4
g. Shipment Not Applicable
h. Long-Term Storage Not Applicable
i. Disposal i.1, i.2, i.3, i.4, i.5, i.6, i.7,
i.8
j. Disposal Site Closure/Post Closure j.1, j.2, j.3, j.4, j.5, j.6
k. Environmental Monitoring k.1, k.2, k.3, k.4
l. Quality Assurance all
m. Records and Reports m.1, m.2
Chapter I - General Requirements and Responsibilities
I-128 DOE G 435.1-1
7-09-99
I. 2.F. Field Element Managers.
Field Element Managers are responsible for:
(6) Radioactive Waste Acceptance Requirements. Ensuring development,
review, approval, and implementation of the radioactive waste acceptance
requirements for facilities that receive waste for storage, treatment, or
disposal. Radioactive waste acceptance requirements shall establish the
facility’s requirements for the receipt, evaluation, and acceptance of waste.
Section 103
Objective:
The objective of these requirements is to establish limits and technical criteria which waste and/or
waste containers must meet, based on the hazards of the waste, to ensure that waste is
manageable at receipt and can subsequently be safely stored, treated, or disposed, as applicable.
Discussion:
The discussions that follow provide guidance on the above requirement for radioactive waste
acceptance requirements. Specific guidance for waste acceptance requirements for each of the
waste types is contained in Chapter II, High-Level Waste Requirements; Chapter III, Transuranic
Waste Requirements; and Chapter IV, Low-Level Waste Requirements of this guide.
The analysis of the hazards associated with management of radioactive waste in development of
DOE O 435.1 and DOE M 435.1-1 indicated that a critical point where controls are needed to
prevent or minimize the risks due to the hazards of radioactive waste is when waste is transferred
from one major functional area to another. That is, when waste moves from storage, for example,
to treatment or disposal. There is not only a physical transfer of the waste, but a change in the
management activities that are to be carried out with the waste, possibly a change in potential
risks or hazards, a transfer of the knowledge of the specific content and hazards of the waste, and
also a transfer of the responsibility for management of the waste. This transfer of waste,
knowledge, and responsibility can take place a large distance from where the waste was generated
or treated, or previously stored, or in some cases, after many years in storage. Therefore,
development of and implementation of waste acceptance requirements for storage, treatment, and
disposal facilities is a critically important control that leads to safe and efficient management of
radioactive waste.
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-129
7-09-99
Waste Acceptance Requirements.
The definition of “waste acceptance requirements” (DOE M 435.1-1, Attachment 2) is:
Waste acceptance requirements are waste acceptance criteria, and all other requirements
that a facility receiving waste for storage, treatment, or disposal must meet to receive
waste (e.g., waste acceptance program requirements, receiving facility operations manual).
The waste acceptance requirements include both the program implemented by the facility
receiving the waste, such as waste handling procedures and training, and any technical and
administrative criteria to address the hazards associated with the waste that arise from handling
and managing the waste, and technical and administrative criteria that are provided to waste
generators who transfer waste to the receiving facility that waste must meet in order to be
acceptable, known as “waste acceptance criteria.”
The waste acceptance requirements should include all of the technical limitations and criteria for
radioactive waste to be acceptable for storage, treatment, or disposal at the receiving facility. The
safety analysis report, criticality analysis, and any other appropriate safety, authorization basis, or
performance assessment documents should be used to establish the technical waste acceptance
requirements for the receiving facility, including radioactivity (concentration and inventory) limits,
waste classes or categories, waste form and/or packaging stability requirements, allowable
chemical content, percent liquid, and any other necessary waste container or form requirements to
ensure that the facilities’ design bases, performance, and operating bases are protected.
Section 104
The waste acceptance requirements should include establishment of a process by which the
receiving facility evaluates incoming waste for acceptability and confirms that a waste meets the
acceptance criteria of the facility. The process should include one of, or a combination of,
physical evaluations of waste, such as sampling and testing, or reviews, audits, or observations of
generating facilities’ certification processes and procedures. The process should establish the
procedures and mechanisms for dealing with incoming waste that does not meet the waste
acceptance requirements of the receiving facility. The waste type chapters contain additional
guidance on this element of waste acceptance requirements.
Waste Acceptance Criteria.
The definition of “waste acceptance criteria” (DOE M 435.1-1, Attachment 2) is:
Waste acceptance criteria are the technical and administrative requirements that a waste
must meet in order for it to be accepted at a storage, treatment, or disposal facility.
Chapter I - General Requirements and Responsibilities
I-130 DOE G 435.1-1
7-09-99
The waste acceptance criteria are those technical requirements, such as radionuclide concentration
and package weight limitations, that a waste must meet, and administrative requirements, such as
forms and certification statements, that a generator must prepare, for radioactive waste to be
accepted at a storage, treatment, or disposal facility. Waste acceptance criteria must be
documented, and in fact, for facilities that receive waste from many differing generators, are
commonly known documents, such as the Waste Isolation Pilot Plant Waste Acceptance Criteria
document, or the WIPP WAC.
The waste acceptance criteria should specify the documentation requirements regarding waste
generation, characterization, transport, treatment, storage, disposal, and any other information
that must be prepared by the generator, retained by the generator, sent to the receiving facility,
and accompany the waste in order for waste to be acceptable at the receiving facility. The waste
acceptance criteria should define the key elements to be included in a waste generator's
certification program to confirm that radioactive waste has been properly prepared to meet the
receiving facility's acceptance requirements.
Development of Waste Acceptance Requirements. The facility receiving waste for storage,
treatment, or disposal must document its waste acceptance requirements. The documentation
should be as thorough, clear, concise, and unambiguous as possible to minimize the potential for
unacceptable waste being sent to the facility.
The waste acceptance requirements and documentation should be developed using a graded
approach commensurate with the hazards associated with the management of the waste in the
facility and the complexity of the activities to be conducted in the facility and on the waste. The
complex activities that can involve many hazards that take place at a low-level waste disposal
facility or a high-level waste storage tank would likely involve numerous and/or detailed waste
acceptance requirements. By contrast, a facility which will only pass-through properly packaged
waste directly to a disposal facility may have a minimum set of requirements that refer to the
disposal facility waste acceptance requirements and are often more general in nature. A facility
engaged only in staging of waste for shipment to another facility may not have separate waste
acceptance requirements apart from the facility to which it will eventually be shipped.
Section 105
Example: Facility 200 at Site W contains a high-level waste treatment process. The
treated high-level waste is transferred to Facility 400 for transportation to another DOE
site. Low-level waste and transuranic waste that result from the treatment process are
solidified for disposal at Site W, and transferred to Storage Building A while it waits for
disposal. The waste acceptance and processing documentation for Facility 200 contains
detailed procedures and technical specifications for the acceptance of high-level waste
streams for processing. The documentation contains details that make it clear that, as
long as operations are maintained within appropriate parameters, the solidified low-level
waste and transuranic waste are certifiable to the Site W disposal facility. No additional
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-131
7-09-99
waste acceptance requirements are prepared for Storage Building A where the waste is
stored prior to disposal.
A radioactive waste management facility may have individual, stand-alone requirements, if
warranted by the hazards involved or the complexity of the activities conducted. Or a site may
have general acceptance requirements applicable to all waste management facilities at the site, in
which case separate facilities would add facility-specific acceptance requirements to the site
acceptance requirements, as necessary. This may be the practice at a site with many facilities
which manage small quantities of waste with multiple locations for staging, storage, and/or central
management of waste. At such a facility, most of the process and procedural acceptance
requirements could be in one document applicable to the whole site, which would be
supplemented with specific technical requirements for acceptance at each of the management
locations. If activities at various facilities are the same, they could share the same supplemental
waste acceptance requirements documents. Likewise, if several activities are carried out at
locations that are close to one another, or are managed by the same entity, then it may be
advantageous for one supplemental technical document to be prepared to cover those activities.
Waste acceptance requirements for treatment and storage facilities should consider the waste
acceptance criteria for facilities in subsequent steps of waste management in development of their
waste acceptance criteria. Particular attention should be paid to the requirements for treatment
facilities to prevent generation of waste streams, following treatment, that would have no path
forward to disposal. Waste acceptance requirements should also clearly delineate different
requirements for on-site generators as opposed to off-site generators, if differences exist.
Similarly, if there are any specific requirements for, or accommodations made, at the receiving
facility for small volume generators, these should be specified in the waste acceptance
documentation. Waste acceptance requirements should also address any specific inspections for
leakage, contamination, or presence of hazardous materials required by other DOE Orders or
Department of Transportation regulations.
Section 106
Example: Processes in the Site W Treatment Building include packaging of low-level
and mixed low-level waste, compaction of low-level waste, incineration of mixed low-
level waste, solidification of low-level waste, and storage and staging of waste prior to
disposal. The Site W Treatment Building Waste Acceptance Requirements document
contains provisions that address Department of Transportation requirements, RCRA
Permit requirements, State Hazardous waste law permit requirements, waste acceptance
criteria from the disposal facilities to which waste will be transferred, as well as DOE O
435.1 and DOE M 435.1-1 requirements.
Review and Approval of Waste Acceptance Requirements. The waste acceptance requirements
for DOE facilities that receive waste for storage, treatment, or disposal are a key element of the
radioactive waste management basis, and should be thoroughly reviewed for completeness,
Chapter I - General Requirements and Responsibilities
I-132 DOE G 435.1-1
7-09-99
adequacy, and consistency with the hazards that may be encountered at the facility. The Field
Element Manager, or his/her designee, is responsible for conducting this review. At his/her
discretion, review and approval of facility waste acceptance requirements can be delegated to a
contractor. The waste acceptance requirements document should be finalized and approved prior
to the issuance of a facility’s radioactive waste management basis. The radioactive waste
management basis for the receiving facility should reference the waste acceptance requirements
document, or cite specific acceptance requirements, as critical elements of the radioactive waste
management basis for the facility. Likewise, generating facilities, operations, or activities that
send waste to the receiving facility should also cite or reference the waste acceptance
requirements document for the receiving facility in the radioactive waste management basis
statement applicable to the waste generation.
Implementation. The implementation of the waste acceptance requirements for radioactive waste
management facilities should also follow the graded approach process that is consistent with the
hazards associated with the management of the waste in the facility and the complexity of the
activities to be conducted in the facility and on the waste. Some radioactive waste management
facilities or operations that receive large amounts of waste for storage, treatment, or disposal
from many different generator organizations, should establish a waste acceptance program that
has separate responsibility for receipt, evaluation, and approval of receipt of waste. On the other
hand, waste acceptance at a group of several small facilities at which similar management steps,
like storage, are being undertaken, may require little in the way of an active program for receiving
waste.
Example: The Site D Disposal Facility accepts waste from several generators in the
DOE Complex. Site D establishes a Waste Acceptance Program which runs the receipt
and acceptance of waste, including establishment of the waste acceptance criteria (WAC)
documentation and waste receipt operations (including: container inspection upon
arrival, unloading, transfer to disposal emplacement operators). The Site D Waste
Acceptance Program performs waste certification audits of generators at all other DOE
sites which send waste to the Site D Disposal Facility. By way of contrast, at Site E,
where waste is generated, treated, and stored, and then transferred to Site D for disposal,
the Waste Generator Program handles all waste generation documentation, waste
certification, waste acceptance at Site E treatment and storage facilities, and all transfer
responsibilities to Site D. Site E personnel participate in Site D waste generator
certification audits, but do not conduct separate ones of their own.
Section 107
Compliance with the requirement for radioactive waste acceptance requirements is demonstrated
if all radioactive waste management storage, treatment, and disposal facilities have approved,
documented waste acceptance requirements that include all necessary technical requirements and
limitations for waste to be acceptable upon receipt at the facility, documented waste acceptance
criteria that a generator uses to transfer acceptable waste to the receiving facility, and all
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-133
7-09-99
necessary administrative requirements that include a process for evaluation and acceptance of
incoming waste as meeting the acceptance requirements of the receiving facility.
Supplemental References:
1. DOE, 1997. Nevada Test Site Waste Acceptance Criteria, NTSWAC ( Revision 1), U.S.
Department of Energy, Nevada Operations Office, Las Vegas, NV, August 1997.
2. DOE, 1996. Waste Acceptance Criteria for the Waste Isolation Pilot Plant, DOE/WIPP
069, Revision 5, U.S. Department of Energy, Carlsbad, NM, April 1996.
3. DOE, 1991. Hanford Site Solid Waste Acceptance Criteria, WHC-EP-0063-3, U.S.
Department of Energy, Richland Operations Office, Richland, WA, September 1991.
Chapter I - General Requirements and Responsibilities
I-134 DOE G 435.1-1
7-09-99
I. 2.F. Field Element Managers.
Field Element Managers are responsible for:
(7) Radioactive Waste Generator Requirements. Ensuring development, review,
approval, and implementation of a program for waste generation planning,
characterization, certification, and transfer. This program shall address
characterization of waste, preparation of waste for transfer, certification that
the waste meets the receiving facility's radioactive waste acceptance
requirements, and transfer of waste.
Objective:
The objective of radioactive waste generator requirements is to promote the development of
effective programs for managing the front end of radioactive waste management cycles. Front
end activities consist of those activities performed by waste generators in preparation for turning
over waste for management in systems intended to lead to disposal. The Field Element Manager
is assigned responsibility for ensuring that effective programs are developed and implemented for
managing radioactive wastes in a manner that promotes their eventual disposal.
Discussion:
The requirement for a waste generator program provides for development and implementation of
systematic, integrated capabilities for four key elements: (1) considering waste management needs
prior to and during generation of waste streams (planning), (2) obtaining and maintaining
knowledge about the waste that supports effective decision-making about the waste
(characterization), (3) documenting that waste generated by one facility meets the receiving
facility*s waste acceptance requirements (certification), and (4) and ensuring that waste to be
shipped satisfies certain documentation, authorization, and manifest requirements (transfer).
Hazards associated with the physical aspects of radioactive waste transfer are addressed in
transfer requirements for specific waste types.
The definition of generator (Chapter I, Attachment 2) is;
“Organizations within DOE or managed by DOE whose act or process produces
radioactive waste or, for the purposes of the generator requirements in this Order and
Manual, transfer radioactive waste to a treatment, storage, or disposal facility.”
Section 108
Therefore, a waste generator program is to be implemented by all organizations who produce
waste as a byproduct of a mission or process, and all organizations who transfer waste to a
treatment, storage, or disposal facility, even if they don’t produce waste. Some elements of the
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-135
7-09-99
waste generator program may not be applicable to organizations who only transfer waste, such as
waste characterization or approval to generate waste with no path to disposal. Organizations that
transfer waste are not required to implement any waste generator program elements that are not
necessary to perform a compliant waste transfer. Each generator must determine the elements of
the waste generator program that apply to the specific radioactive waste management facilities,
operations, and activities, and ensure that they are included in the facility’s approved generator
program.
Example: At Site Q, 1400 Area, there are three facilities who generate low-level waste,
and a storage building. The three generator facilities implement all four elements of the
1400 Area waste generator program; planning, characterization, certification, and
transfer. Waste generated at 1400 Area is certified to the Site Q Disposal Facility waste
acceptance criteria, and transferred to the storage building, where it is stored for 9
months prior to transfer for disposal. The storage building implements only two elements
of the 1400 Area waste generator program; waste certification and waste transfer. The
program is very minimal, as the storage building acts only to pass-through waste already
certified to the Site Q Disposal Facility acceptance criteria. Certification involves only a
signature by the storage facility manager on the waste certification statement that the
waste continues to meet Site Q Disposal Facility criteria.
Field Element Managers are required to ensure that their subordinate organizations and personnel
establish and carry out these programs. Field Element Managers are also responsible for ensuring
the adequacy of the programs for achieving the more detailed requirements identified for waste
types and then approving the programs. Finally, Field Element Managers are to ensure that the
programs are implemented as designed and approved.
Specific guidance on the four key elements of waste generator programs (i.e., planning,
characterization, certification, and transfer) and on issues such as reliance on proposed facilities,
conditions under which waste with no path forward can be generated, and demonstration of
acceptable performance is provided in Chapter II, High-Level Waste Requirements; Chapter III,
Transuranic Waste Requirements; and Chapter IV, Low-Level Waste Requirements of this guide.
Some of the conditions and weaknesses that need to be controlled to prevent or minimize the
risks due to the hazards of radioactive waste management are a result of technical and
administrative weaknesses and conditions in generator activities. In some cases, waste has been
generated without due consideration of the benefits of the activity that generated the waste
compared to the work required to manage and dispose of the waste generated. Waste generator
requirements focus on systematic attention to the need for generating a waste and effective
processes for turning over the waste to waste management facilities. The waste generator
program is closely related to other requirements in this Manual, such as waste acceptance
requirements, and the implementation of these related requirements should be integrated.
Section 109
Chapter I - General Requirements and Responsibilities
I-136 DOE G 435.1-1
7-09-99
Development and Implementation of a Waste Generator Program. A facility that generates waste
should have a program in place that provides for integration of four key elements -- planning,
characterization, certification, and transfer. Facilities who transfer waste must also have a waste
generator program that integrates whatever elements of the program are being implemented.
Documentation of the program should be thorough, clear, concise, and unambiguous to promote
integration of these elements and to clearly specify roles and responsibilities. The program does
not need to be managed by a discrete organization with dedicated staff and offices. Rather the
program is intended to describe the processes and procedures needed to integrate and document
the four key elements and to establish roles and responsibilities for carrying out these elements,
even across organizational boundaries.
A separate program need not be developed for each facility or each waste type. The
establishment of a single waste generator program for an entire site may be the most effective and
least expensive option, but depends on the complexity of the facilities and operations and other
practical considerations at the site. Some of the waste generator requirements in DOE M 435.1-1
are identical across the waste types and others are very similar among the waste types.
Ultimately, the structure and organization of the waste generator program are left to the
discretion of Field Element Managers.
The waste generator program and its documentation should be developed using a graded
approach commensurate with the hazards associated with the waste generated, the quantities of
waste generated, and the complexity of the characterization, certification, and transfer activities to
be conducted. Facilities that generate relatively benign radioactive waste with known
management and disposal approaches should not have generator program requirements at the
same level of detail as activities that produce very hazardous (high radiation) wastes whose
management and disposal challenge existing capabilities. For some large, high-hazard facilities, it
may be appropriate to establish a waste generator program that has separate responsibility for
planning, characterization, certification, and transfer of waste. Facilities who are only pass
throughs (i.e., storage) from one management step (e.g., generation of waste certified to a
treatment facility) to another will have minimal waste generator programs.
A radioactive waste generation facility may have individualized requirements if warranted by the
hazards involved or the complexity of the activities conducted. Alternatively, a site may have site-
wide generator requirements applicable to all waste generators at the site with separate generators
supplementing the site requirements with facility-specific requirements as necessary. This would
be a particularly good practice at a site with many facilities that generate small quantities of
similar waste. At such facilities, most of the process and procedural generation requirements
could be articulated in one document applicable to the entire site, which could be supplemented
by specific technical requirements for waste generation at each of the management locations. If
waste generation activities at some of the facilities are the same or very similar, then they could
share the same supplemental waste generator documents. Likewise, if several wastes are
Section 110
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-137
7-09-99
generated at locations that are close to one another, or are managed by the same entity, then it
may be advantageous for one supplemental technical document to be prepared to cover those
activities.
Example: Site X had dozens of operations that each generate approximately one
package of radioactive waste each year and one large facility that generates truckloads
of waste every week. The Field Element Manager decides to require the development of
a site-wide waste generator program that applies to all of the small generators and to
require the large volume generator to develop a separate program that applies only to its
operation.
Waste generator certification and characterization requirements are directly linked to the waste
acceptance requirements for the facility to which a generator will transfer waste. The generator
must certify that waste to be sent to the receiving facility meets its waste acceptance criteria, and
waste characterization determines whether the waste acceptance criteria have been satisfied. The
waste generator program should include a process for reviewing waste acceptance criteria of the
receiving facilities and tailoring certification, characterization, and transfer elements to fully
comply with the applicable waste acceptance criteria. The waste acceptance criteria for the
receiving facility should be thoroughly reviewed to establish the conditions that the waste to be
transferred must meet, as well as the corresponding characterization methods that will be used to
ensure that the wastes meet the criteria. If it is determined that the waste acceptance
requirements of a facility receiving waste for storage, treatment, or disposal have not been met,
the generator bears the financial responsibility for corrective actions necessary to make the waste
acceptable or for return of the waste.
Review and Approval of Waste Generator Requirements. The Field Element Manager is
responsible for ensuring the proposed generator program(s) are reviewed and approved. As
decided by the Field Element Manager, the review and approval may be done by DOE staff or by
the contractor. Waste generator program documentation should confirm that the generators
consider and plan for waste that will be generated; that a process is included for approving
generation of waste that has no path forward to disposal; that waste will be certified to meet
acceptance requirements for a receiving facility prior to transfer; that adequate characterization
capability is in place; and that transfer requirements will be met. The program should document
the roles and responsibilities for carrying out the component elements and should describe
interfaces between the elements that will provide for appropriate integration. Documented
evidence of the waste generation program approval, based on review of the written description of
the program, will serve as the performance measure for this requirement.
Example: Upon completion of the draft written waste generator requirements program,
the Field Element Manager directs his staff to review the process used by the contractor
to review and approve the program against the requirements of DOE M 435.1-1 for
Chapter I - General Requirements and Responsibilities
I-138 DOE G 435.1-1
7-09-99
Section 111
waste generation planning, waste characterization, waste certification, and waste
transfer. The contractor review is performed using procedures developed and
documented for this purpose. Once any deficiencies in the programs are corrected, the
contractor management provides written approval of the program for implementation.
The DOE staff report to the Field Element Manager that they are satisfied with the
process used by the contractor for reviewing and approving the program.
Planning Requirements. The goal of the waste generation planning element of this requirement is
to provide ultimately for the disposal of all radioactive waste that is generated in the future. This
requirement emphasizes analysis of the activities necessary to manage and dispose of waste prior
to generating the waste. The objective of this requirement is to increase assurance that necessary
waste management facilities are available. Planning is required for all new waste streams. All
aspects of waste management up to and including disposal are included. The planning
requirements for specific waste types in this Manual are structured to discourage sites from
generating waste that does not have an identified path for storage, treatment, and disposal; and to
promote the development of plans for resolving issues that prevent disposal of those radioactive
wastes that must be generated, but do not have an identified path to disposal. The general
requirement for waste with no identified path to disposal (see DOE M 435.1-1,
Section I.2.F.(19)) requires approval for generation of such wastes.
Example: A batch of spent fuel stored at Site X is deteriorating, and reprocessing is
necessary to reduce risk. The reprocessing will begin two years after the effective date of
DOE O 435.1 in an existing reprocessing canyon. The spent fuel is different from that
previously reprocessed in the canyon, and necessary process changes will produce a
waste stream unlike those previously produced. The high-level waste produced will be
subjected to pretreatment and treatment. Prior to disposal, the high-level waste will be
solidified. At various stages in this series of operations, temporary or long-term storage
will likely be required. Satisfactory performance of the waste generation planning
requirements will include preparation of a high-level waste stream life cycle description
consisting of identification and explanation of each of these steps and explanation of the
interfaces between the steps. Prior to beginning reprocessing, the generator of the waste
holds discussions with operators of facilities that may be able to manage the waste and
incorporates relevant information on waste management needs and the availability of
facilities to meet those needs in written plans.
Characterization Requirements. The waste characterization element of the waste generator
process is a critical control used by other elements (e.g., waste acceptance requirements,
certification, transfer) to ensure that sufficient knowledge of a waste’s characteristics is available
to support effective decision-making for its management. Waste characterization is a necessary
control to mitigate potential vulnerabilities if a waste stream is not adequately described. The
requirements contained in this section, and in the respective waste type chapters, address the
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-139
7-09-99
Section 112
identified vulnerabilities by specifying the minimum characterization data, and requiring the use of
a data quality objectives, or similar, process.
Example: A waste stream from an actinide processing building is sampled and analyzed
and determined to consist of three primary nuclides: Pu-239, Am-241, and Pu-238.
Multiple samples are found to contain the three radionuclides in essentially the same
ratio, and the process does not vary significantly over time. Therefore, the contents of
future waste packages are routinely characterized based on a gamma energy analysis
which detects gamma radiation from the Am-241 and the Pu-238. The characterization
program requires the collection and full analysis of samples once a month to confirm
that the ratio of the three radionuclides falls within an acceptable range (based on
application of the data quality objectives process).
Certification Requirements. The waste certification element of the waste generator program is
one part of the controls put in place as a result of the hazards analysis performed when developing
DOE O 435.1 and DOE M 435.1-1. Certification requirements address confirmation that the
waste acceptance criteria of a receiving facility have been met.
Example: The Building Five Storage Facility has low-level waste that it has received for
storage over the last year. Facility personnel plan to continue to receive low-level waste
and store it until it can be transferred to the Nevada Test Site disposal facility. The
organization responsible for the storage facility will be considered a generator when the
waste is shipped to the Nevada Test Site disposal facility. The storage facility must
develop and implement a certification program that provides documented confirmation
that the Nevada Test Site Waste Acceptance Criteria have been met.
Transfer Requirements. The waste transfer requirement ensures that waste is transferred to a
receiving facility only with the authorization of the receiving organization. It also ensures that the
waste transfer is accompanied by transfer of relevant information and by appropriate transfer of
responsibility for maintaining, as necessary, the integrity of the waste and its container. Waste
should not arrive at a receiving facility until the sending facility has been authorized to send it by
personnel responsible for the receiving facility. The transferred waste should be accompanied by
relevant documentation about the waste and designation of the individuals in the receiving
organization who will be responsible for maintaining the integrity of the waste and its container.
This requirement is the responsibility of the individual or organization that is transferring
(sending) the waste. While this approach ensures that the receiving organization is aware of and
prepared for arrivals of waste, this requirement is also intended to promote communication
between the sender and the receiver regarding waste acceptance criteria, available capacity of the
receiving facility, and other important coordination information.
Chapter I - General Requirements and Responsibilities
I-140 DOE G 435.1-1
7-09-99
Example: In preparation for transfer of low-level waste to a disposal facility,
characterization and packaging information is documented and, as required,
accompanies the waste to the disposal facility. However, the generator had not received
authorization to transfer the waste to the disposal facility and no disposal capacity was
available when the waste arrived. The waste was shipped back to the generator.
Section 113
Compliance with this requirement for a radioactive waste generator program can be demonstrated
if all radioactive waste generator facilities have a documented waste generator program that
includes, as appropriate, the four key elements -- planning, characterization, certification, and
transfer -- and the Field Element Manager or his designee monitors those activities to verify that
they are being implemented as described in the program.
Supplemental References:
1. EPA, 1994. Guidance for the Data Quality Objectives Process, EPA QA/G-4, U.S.
Environmental Protection Agency, Washington, D.C., September 1994.
2. DOE, 1997. Nevada Test Site Waste Acceptance Criteria (NTSWAC), Revision 1, U.S.
Department of Energy, Nevada Operations Office, Las Vegas, NV, August 1997.
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-141
7-09-99
I. 2.F. Field Element Managers.
Field Element Managers are responsible for:
(8) Closure Plans. Ensuring development, review, approval, and implementation
of closure plans for radioactive waste management facilities in accordance
with the applicable requirements in the waste-type chapters of this Manual.
Objective:
The objective of this requirement is to ensure closure plans for radioactive waste facilities reflect
the engineered and administrative controls established by the facility’s radioactive waste
management basis and that the closure plans and other documentation include sufficient technical
specifications of the final closure of the facility to justify the bases for evaluating the protection of
the public and the environment that are presented in the performance assessment and composite
analysis of the facility, or similar prospective assessments.
Discussion:
The safety and hazard analysis for management of radioactive waste conducted to develop the
essential requirements for DOE O 435.1 and DOE M 435.1-1 indicated that disposal is a critical
activity requiring controls because disposal is the last function conducted on the waste, but yet,
the potential hazards from radioactive waste will continue far into the future. Thus, there are
specific requirements for the disposal of radioactive waste that are critical to protection of the
public, workers, and environment. One of the most important of these controls is the closure plan
for the facility, the elements of which represent the last line of defense against the possible
interaction of buried radioactive materials with the public, workers, and the environment. The
development, review and approval, and implementation of radioactive waste disposal facility
closure plans are necessary to assure disposal is being conducted safely and effectively and that
the disposal facilities will remain safe far into the future. The closure of deactivated high-level
waste facilities and sites also poses potential hazards from radioactivity far into the future, similar
to radioactive waste disposal activities. The development, review and approval, and
implementation of closure plans and other closure documentation for deactivated high-level waste
facilities and sites are also crucial in assuring that the public, workers, and the environment are
protected far into the future.
The DOE M 435.1-1 requirement states that it is the responsibility of the Field Element Manager
to develop, review and approve, and implement radioactive waste facility closure plans. The
discussions that follow provide guidance on these aspects of the requirement for low-level waste
disposal facilities and deactivated high-level waste sites and facilities. As indicated in the
requirement, closure plans required by the Manual must meet the requirements for closure plans in
Section 114
Chapter I - General Requirements and Responsibilities
I-142 DOE G 435.1-1
7-09-99
the waste type chapters of DOE M 435.1-1. Additional guidance on the following subjects, is
found in the guidance on Chapter II, High-Level Waste Requirements and Chapter IV, Low-Level
Waste Requirements.
Low-Level Waste Disposal Facility Preliminary Closure Plan. A preliminary closure plan must be
submitted to Headquarters as part of the review documentation necessary for issuance of a
disposal authorization statement for a low-level waste disposal facility. The preliminary closure
plan documents the closure of the disposal facility that is assumed and evaluated in the
performance assessment and composite analysis submitted for the disposal facility. Detailed
guidance on the contents and submittal of this preliminary closure plan is discussed in guidance,
on DOE M 435.1-1, Section IV.Q.(1).
Development of Low-Level Waste Disposal Facility Closure Plan. The development of a closure
plan is necessary for a planned or operating disposal facility to ensure waste disposal operations
are performed in a manner which is consistent with the assumptions made about closure in the
performance assessment and composite analysis, and so that the actual closure of the facility is
ultimately protective of the public and the environment. The closure plan provides the technical
specifications to be addressed during waste disposal operations and closure of the facility. The
closure plan is developed after consideration and evaluation of such factors as the activities that
will occur at the facility during its use, the expected condition of the facility at the time of closure,
the intended use of the facility following closure, land use plans for the facility, and institutional
control of the disposal facility following closure. The closure plan establishes the conditions to be
met to provide protection to workers, the public and the environment when active disposal
operations have ceased. The specifications and conditions presented in the closure plan provide
the bases for the long-term projection of the performance of the disposal facility and related
facilities that are addressed in the performance assessment and composite analysis for the disposal
facility. Detailed discussions on low-level waste disposal facility closure plans are included in the
guidance on DOE M 435.1-1, Section IV.Q.
Example: The performance assessment and composite analysis for the Site X low-level
waste disposal facility include assumptions regarding waste degradation, infiltration of
water, and leaching of waste that correspond to descriptions of disposal unit closure in
those documents. The closure plan describes the partial closure of the disposal units and
provides technical specifications and conditions for the closure of units and the partial
closure of the facility that are consistent with achieving an infiltration rate of water and
degree of degradation of waste as assumed in the performance assessment and composite
analysis. The closure plan also indicates preliminary plans for the installation of
monitoring wells that will measure infiltration to confirm the assumptions used in the
evaluations, and so appropriate adjustments can be made once closure activities begin.
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-143
7-09-99
Section 115
Review and Approval of Low-Level Waste Disposal Facility Closure Plan. The preliminary
closure plan for a low-level waste disposal facility must be submitted along with the performance
assessment and composite analysis for review prior to issuance of a disposal authorization
statement. Therefore, review and approval of the closure plan for a low-level waste disposal
facility is to be conducted by the Field Element Manager, and the approved closure plan then
becomes part of the radioactive waste management basis for the disposal facility. The preliminary
closure plan for a disposal facility comprises the documentation of the assumed closure
configuration of the facility with some additional detail on how this closure can be achieved. The
closure plan will be a living document that is constantly updated through the operational life of the
facility with specific information about contents, partial closure (e.g., caps on trenches) of
disposal units, and other information necessary (e.g., monitoring locations) to support the final
closed state. It is imperative that the relationship between the closure plan and the analyses
conducted in the performance assessment and composite analysis be considered as the facility is
being operated. Any information that is incorporated into the closure plan or any changes made
to closure of the facility that impact the analysis in the performance assessment or composite
analysis need to be incorporated into these evaluations immediately, to determine their impact.
This allows any changes to waste acceptance, or other aspects of operation, to be made effective
as soon as possible. This relationship between the performance assessment and composite
analysis and the closure plan is discussed in detail in the guidance on DOE M 435.1-1, Section
IV.Q.(1). When major changes are required to the closure plan, based on operational changes or
impacts as evaluated in the long-term assessments, re-approval by the Field Element Manager
should be considered.
Development of Closure Plans and Other Closure Documentation for Deactivated High-Level
Waste Facilities/Sites. The development of closure plans and other closure documentation for
deactivated high-level waste facilities/sites is necessary to ensure that the process of closure
results in a closed facility that is protective of the public and the environment. Closure of
deactivated high-level waste facilities/sites can be accomplished by one of three paths.
Documentation requirements and review/approval requirements for the first path,
decommissioning, are defined in DOE O 430.1A and DOE 5400.5, and refer to these Orders for
information on these topics. Documentation and review/approval requirements for the second
and third paths, CERCLA process and closure, are defined in DOE M 435.1-1, Section II.U,
Section I.2.F.(8), and Section I.2.E.(2). Section II.U defines the documentation requirements
while the two General Requirements sections define the roles and responsibilities of the Field
Element Manager and the Deputy Assistant Secretaries for Waste Management and
Environmental Restoration, respectively.
As discussed in the guidance Section II.U, the development of closure plans and other closure
documentation, e.g., CERCLA plans and analyses, are necessary for a planned closure action to
ensure the closure activities are consistent with the assumptions made about the closure in the
analysis, e.g., assessments of projected performance and projected composite performance, and so
Section 116
Chapter I - General Requirements and Responsibilities
I-144 DOE G 435.1-1
7-09-99
that the actual closure is protective of the public and environment. Refer to Section II.U for the
specific information that is required.
Review and Approval of Site Closure Plans and Other Closure Documentation for Deactivated
High-Level Waste Facilities/Sites. The site closure plans and other closure documents required by
Section II.U must be reviewed and approved by the Deputy Assistant Secretaries for Waste
Management and/or Environmental Restoration, as appropriate, as required by DOE M 435.1-1,
Section I.2.E.(2). Guidance on Section I.2.E.(2) discusses the review and approval process in
detail. The responsible Field Element Manager needs to take the appropriate actions to ensure
that the closure documentation for a facility or site meets the technical and administrative
requirements of Section II.U and that the package of information submitted for the DOE
Headquarters review and approval is adequate. To accomplish these tasks it is expected that the
Field Element Manager will need to develop and implement a formal review and approval process
that is completed prior to submission of the documentation to DOE Headquarters.
The authorization by the Deputy Assistant Secretaries to the Field Element Manager to proceed
with closure activities should be viewed as analogous to a license that would be issued by the U.S.
Nuclear Regulatory Commission or another regulatory agency. As explained in the guidance to
Section I.2.E.(2) and II.U., an authorization to proceed with closure activities is issued by the
Assistant Secretaries to the Field Element Manager responsible for closing the deactivated facility
and contains the conditions of the authorization and controls deemed necessary for the long-term
protection of the public and the environment. Thus the closure documentation is to contain
information on the configuration of the closed facility or site as well as the details on how the
closure will be achieved. It is envisioned that the closure plan, required by Section II.U(3), will
be a living document that is updated as necessary to ensure the assumptions and analysis
contained in the plan are consistent with the conditions at the site. It is imperative that the
relationship between the closure plan and the analysis conducted in the assessment of performance
and composite analysis be kept in mind as the facility or site is being closed. Any information that
becomes available during the closure activity or any changes made to closure of the facility that
impact the analysis in the assessment of performance or composite analysis needs to be
incorporated into these evaluations immediately to determine needs to their impact. Any
information that is incorporated into the closure documentation, or any changes to the closure
activities, that impact the analysis in the performance assessment or composite analysis in the
closure documentation should be incorporated into these evaluations immediately, to determine
the extent of their impact. Once a closure action is authorized by the appropriate Deputy
Assistant Secretary, as provided in Section I.2.E.(2), the Field Element Manager is responsible for
ensuring that the closure plan or other closure documentation, with emphasis on the performance
assessment and composite analyses, remain current with accurate and up-to-date information.
This maintenance function is discussed in the guidance to Section II.U and ensures the data and
analyses are accurate and reflective of current conditions at the closure site. When major changes
or revisions are required to the closure plan or other closure documentation, it is the responsibility
Section 117
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-145
7-09-99
of the Field Element Manager to perform a review and approval of the revised analysis to ensure
the bounding conditions contained in the closure plan, and authorization to proceed with closure
activities, is not exceeded. As explained in the guidance to Section I.2.E.(2), if these bounding
conditions are exceeded, the closure plan needs to be revised and submitted to the appropriate
Deputy Assistant Secretary within the Office of Waste Management for review and/or approval.
Closure Plan Implementation. The closure plan for a radioactive waste facility is a living
document and needs to be implemented during facility operations and continue through final
closure. The aspects of closure that are to be implemented during operations are generally limited
but then increase as the time of final closure of the disposal facility nears. The Field Element
Manager is responsible for ensuring the various aspects of the closure plan are properly
implemented throughout the life cycle of the facility.
Example: The closure plan for a low-level waste disposal facility requires daily cover as
wastes are disposed, and that the wastes and cover material are to be compacted to a
specified density. A Field Element staff member makes periodic site visits to the disposal
facility to ensure these disposal closure criteria are being met as part of facility
operations. In the fifth year of operation, a performance monitoring well is installed at
the north side of the disposal units filled to date. The staff member monitors the
progress of the monitoring well installation, and ensures that the information concerning
the well is incorporated into the closure plan.
Compliance with this requirement is demonstrated if closure plans for radioactive waste facilities
are developed, approved, maintained, and implemented throughout the life cycle of the facility.
Supplemental References:
1. DOE, 1998. Life Cycle Asset Management, DOE O 430.1A, U.S. Department of Energy,
Washington, D.C., October 14, 1998.
Chapter I - General Requirements and Responsibilities
I-146 DOE G 435.1-1
7-09-99
I. 2.F. Field Element Managers.
Field Element Managers are responsible for:
(9) Defense-In-Depth. Ensuring that defense-in-depth principles are
incorporated where potential uncertainties or vulnerabilities warrant their
use when reviewing and approving radioactive waste management activities
and documents. These principles advocate the use of multiple levels of
engineered and administrative controls to provide protection to the public,
workers, and the environment.
Objective:
The objective of this requirement is to ensure that defense-in-depth principles are appropriately
evaluated and applied to the management of radioactive waste where uncertainties or
vulnerabilities warrant multiple levels of controls to provide protection to the public, workers, and
the environment.
Discussion:
Section 118
Defense-in-depth is the use of multiple levels of protection to compensate for potential human and
mechanical failures which could result in the release of radioactive material. Defense-in-depth as
an approach to radioactive waste management safety has precedent in nuclear safety philosophy.
The requirements analysis conducted to develop the requirements in DOE O 435.1 and DOE M
435.1-1 employed the defense-in-depth philosophy as a fundamental approach to hazard control
for radioactive waste management facilities and operations even though they do not pose the
catastrophic accident potential associated with nuclear power plants. In keeping with the
performance-oriented approach to the development of DOE M 435.1-1, there is no requirement
to demonstrate a minimum number of layers of defense-in-depth. However, evaluating and
justifying that defense-in-depth is appropriate at a given facility is necessary for establishing a
safety basis and/or a radioactive waste management basis. Operators of radioactive waste
management facilities should use the rigorous application of defense-in-depth thinking in their
designs and operations. Such an approach is representative of industrial operations with an
effective commitment to public and worker safety and the minimization of environmental releases.
Implementing defense-in-depth can include use of both administrative and design controls.
Administrative controls include plans (e.g., program management, emergency response, and
characterization), training and qualification requirements, written procedures, safety reviews,
quality assurance programs, evaluations, authorization bases, waste acceptance criteria, waste
certification, and other actions. Design controls include secondary confinement, leak detection,
environmental monitoring, backups to critical systems, and other engineered barriers or
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-147
7-09-99
redundancies. The degree to which defense-in-depth is implemented (i.e., graded approach) needs
to be commensurate with the risk that the facility or operation poses to workers, the public, or
environment.
Most radioactive waste management facilities, operations, and activities typically have defense-in
depth. The first layer of defense is a high level of design quality that ensures important systems,
structures, and components will perform their required functions reliably. The next layer of
defense is administrative controls such as training and written procedures. The final measure of
protection is emergency response actions to minimize consequences of a given event for releases
that might occur despite the other layers of defense.
Example: A low-level waste storage facility is authorized to store 100 55-gallon drums of
solid waste. However, the low-level waste acceptance criteria allows up to 5 percent
liquid by volume. Thus the liquid that could be released from a single drum is 2.75
gallons, or 275 gallons for the entire inventory of drums. Historical operational data
indicate that failure of a drum can occur as often as five times per year for a 100 drum
inventory. However, historical data support that the likelihood of failure of all 100
drums is near zero. Using the graded approach facility personnel determine that spill
controls need to be implemented for a spill the size of less than 15 gallons and not the
entire inventory of liquid of 275 gallons. Additional layers of defense-in-depth (other
than the spill controls) include personnel training, container inspections, waste
acceptance criteria, and an emergency response plan.
Section 119
DOE Standard DOE-STD-3009-94 provides further discussion on the use of safety-significant
structures, systems, and components as contributors to defense-in-depth for DOE nonreactor
nuclear facilities.
Compliance with this requirement is demonstrated by documentation in the radioactive waste
management basis that describes and provides a rationale for the layers of controls (defense-in
depth) in place to provide the protection for the public, workers, and the environment.
Supplemental References:
1. DOE, 1994. Preparation Guide for U.S. Department of Energy Nonreactor Nuclear
Facility Safety Analysis Reports, DOE-STD-3009-94, U.S. Department of Energy,
Washington, D.C., July 1994.
Chapter I - General Requirements and Responsibilities
I-148 DOE G 435.1-1
7-09-99
I. 2.F. Field Element Managers.
Field Element Managers are responsible for:
(10) Oversight. Ensuring oversight of radioactive waste management facilities,
operations, and activities is conducted. Oversight shall ensure radioactive
waste management program activities are conducted in accordance with a
radioactive waste management basis and meet the requirements of DOE O
435.1, Radioactive Waste Management, and this Manual.
Objective:
The objective of this requirement is to ensure Field Element oversight of radioactive waste,
management facilities, operations, and activities is carried out.
Discussion:
A key to successful compliance with any DOE Directive is oversight. This is particularly true of
directives which, like DOE O 435.1 and DOE M 435.1-1, have performance-oriented
requirements that call for review and approval of site- or facility-specific implementation of
procedures and other controls to ensure the requirements are being met. Oversight is defined
(DOE M 435.1-1, Attachment 2) as:
The responsibility and authority assigned to line management to assess the adequacy of
DOE and contractor performance. Independent Oversight refers to the responsibility and
authority assigned to the Assistant Secretary for Environment, Safety, and Health to
independently assess the adequacy of DOE and contractor performance.
The DOE Complex has initiated the integrated Safety Management System under Secretarial
policies DOE P 450.4, Safety Management System Policy, DOE P 450.5, Line Environment,
Safety, and Health Oversight, and DOE P 411.1, Safety Management Functions,
Responsibilities, and Authorities Policy. These policies are invoked by DOE M 435.1-1,
I.1.E.(17) for the purposes of emphasis and clarity. DOE P 450.4 provides the overall goals and
objectives of the DOE integrated Safety Management System. Core function No. 5, “Provide
Feedback and Continuous Improvement,” calls for a system of evaluations and reporting in order
to continuously improve in achieving the goals and requirements for safety and protection of the
environment. DOE P 450.5 explains that line management has the responsibility for oversight of
DOE facilities, operations, and activities, including those involving management of radioactive
waste.
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-149
7-09-99
DOE G 450.4-1, Integrated Safety Management System Guide, Revision 0, contains guidance on
Core Function No.5. Included with this guidance is Appendix D, which references other DOE
publications and handbooks for conducting environmental audits and other types of assessments
that can be conducted during self-assessments or which can be used by line management or parties
with independent oversight responsibilities to conduct oversight assessments of contractor work
performance. The guidance in DOE G 450.4-1, Integrated Safety Management System Guide,
Revision 0, is sufficient guidance on oversight of radioactive waste management facilities,
operations, and activities.
Section 120
It is expected that the revised requirements of DOE O 435.1 and DOE M 435.1-1 will be
incorporated into the contractor self-assessments established under the integrated Safety
Management System, and incorporated into the Field Office oversight of the contractor programs,
as appropriate. Similarly, under the Safety Management System policies, Headquarters line
management has the responsibility to monitor the Field Office oversight and participate in Field
Office oversight functions, as appropriate. Likewise, under the Safety Management Systems
policies, the Assistant Secretary for Environment, Safety, and Health (EH-1) has the responsibility
to assess the adequacy of Field Office and contractor performance, and it is expected that the
revised DOE O 435.1 and DOE M 435.1-1 requirements will be assimilated into the Assistant
Secretary’s programs for independent oversight at his/her discretion.
Compliance with this requirement is demonstrated by appropriate incorporation of DOE O 435.1
and DOE M 435.1-1 requirements within the functions, responsibilities, authorities, and
requirements explained in the set of Safety Management System directives. This should result in
thorough and effective oversight of radioactive waste management facilities, operations, and
activities, and assurance that the public, workers, and the environment are protected from the
hazards associated with management of radioactive waste.
Supplemental References:
1. DOE, 1997. Safety Management Functions, Responsibilities, and Authorities Policy,
DOE P 411.1, U.S. Department of Energy, Washington, D.C., January 28, 1997.
2. DOE, 1996. Safety Management System Policy, DOE P 450.4, U.S. Department of
Energy, Washington, DC, October 15, 1996.
3. DOE, 1997. Line Environment, Safety and Health Oversight, DOE P 450.5, U.S.
Department of Energy, Washington, D.C., June 26, 1997.
4. DOE, 1997. Manual of Safety Management Functions, Responsibilities, and Authorities,
DOE M 411.1-1, U.S. Department of Energy, Washington, D.C., October 8, 1997.
Chapter I - General Requirements and Responsibilities
I-150 DOE G 435.1-1
7-09-99
5. DOE, 1992. Environmental Audit Program Guidance, DOE/EH-0232, U.S. Department
of Energy, Washington, D.C., January 1992.
6. DOE. Performance Objective and Criteria for Conducting DOE Environmental Audits,
DOE/EH-0229, U.S. Department of Energy, Washington, D.C.
7. DOE, 1999. Implementation Plan for Defense Nuclear Facilities Safety Board
Recommendation 98-1, Department of Energy Plan to Address and Resolve Safety Issues
Identified by Internal Independent Oversight. U.S. Department of Energy, Washington,
D.C., March 10, 1999.
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-151
7-09-99
I. 2.F. Field Element Managers.
Field Element Managers are responsible for:
(11) Training and Qualification. Ensuring that a training and qualification
program is implemented for designated radioactive waste management
program personnel, and the training is commensurate with job duties and
responsibilities. Only those personnel who have been trained and qualified
shall design or operate safety (safety class and safety significant) structures,
systems, and components.
Objective:
The objective of this requirement is to ensure that Field Element Managers establish the process
and criteria for designating personnel that should be trained on the management of radioactive
waste and establishing the appropriate level of training for those individuals.
Section 121
Discussion:
It is the responsibility of the Field Element Manager to ensure a program is in place that includes a
process for designating those field personnel for which a training and/or qualification program is
required, and a process, for establishing the appropriate training and level of rigor for those
personnel designated to be trained or qualified.
The selection, qualification, and training requirements for personnel involved in the operation,
maintenance, and technical support of DOE-owned nonreactor nuclear facilities is contained in
DOE 5480.20A, Personnel Selection, Qualification, and Training Requirements for DOE
Nuclear Facilities. The requirements for establishing, implementing, documenting, and evaluating
training programs for Federal employees is contained in DOE O 360.1, Training. These two
DOE Orders are invoked by DOE M 435.1-1, Section I.1.E.(19), and are emphasized here only as
an indication of the importance of training to the successful implementation of the requirements in
DOE O 435.1 and DOE M 435.1-1.
The Technical Qualification Program specified in DOE O 360.1 is required of DOE Federal
technical employees whose position requires them to provide management direction or oversight
that could impact the safe operation of a defense nuclear facility. The Technical Qualification
Program is an example of the process used to determine that personnel possess the necessary
knowledge, skills, and abilities to perform their specific duties and responsibilities. This program
(or a similar program) may be specified by the Field Element Manager for a non-defense or
nonnuclear related DOE waste management activity.
Chapter I - General Requirements and Responsibilities
I-152 DOE G 435.1-1
7-09-99
Use of the National Environmental Education and Training Center of Excellence (A. Alm
memorandum, January 30, 1998) ensures DOE takes a corporate approach to optimizing and
standardizing environmental training across the complex. The Center assesses training needs and
develops and provides training courses on crosscutting environmental management topics. The
Field Element Manager can use this resource in fulfilling the training needs of radioactive waste
management personnel.
The second part of this requirement pertains to those personnel designing or operating safety
(safety class and safety significant) structures, systems, and components. The hazards analysis
conducted for preparation of DOE O 435.1 and DOE M 435.1-1 indicated a weakness in the
design process that could lead to moderate or high hazard conditions if design personnel were not
adequately trained and qualified. DOE 5480.20A does not have a requirement for personnel
designing safety significant/safety class components to be qualified. Note that this requirement is
targeted to design authority personnel and does not apply to design agency personnel.
Compliance with this requirement can be demonstrated by documentation that a Technical
Qualification Program or similar personnel training process has been used to ensure that
radioactive waste management personnel are sufficiently trained to perform these duties.
Supplemental References:
1. Alm, A., 1998. A. Alm to Distribution, memorandum, Environmental Management
Training Policy, U.S. Department of Energy, Washington, D.C., January 30, 1998.
2. DOE, 1994. Personnel Selection, Qualification and Training Requirements for DOE
Nuclear Facilities, U.S. Department of Energy, Washington, D.C., November 15, 1994.
Section 122
3. DOE, 1995. Training, U.S. Department of Energy, Washington, D.C., May 31, 1995.
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-153
7-09-99
I. 2.F. Field Element Managers.
Field Element Managers are responsible for:
(12) As Low As Reasonably Achievable (ALARA). Ensuring ALARA principles
for radiation protection are incorporated when reviewing and approving
radioactive waste management activities.
Objective:
The objective of this requirement is to emphasize implementation of the ALARA process in the
management of radioactive waste.
Discussion:
A hazards analysis was conducted as part of the process for developing DOE O 435.1 and DOE
M 435.1-1. In that analysis, there were many functions and activities with the potential for
personnel exposure to radioactivity and radioactive releases to the environment. Application of
the ALARA process was found to be a mitigating factor for these circumstances. ALARA means
“As Low As is Reasonably Achievable,” which is the approach to radiation protection to manage
and control exposures (both individual and collective) to the work force and to the general public
to as low as is reasonable, taking into account social, technical, economic, practical, and public
policy considerations. ALARA is not a dose limit but a process which has the objective of
attaining doses as far below the applicable limits as is reasonably achievable.
An underlying principle of radiation control is that there should be no exposure to workers or the
public, or releases to the environment of ionizing radiation without the expectation of an overall
benefit from the activity causing the exposure or release. This principle advocates the use of
administrative and design controls in work processes to minimize exposures to radiation. These
controls are incorporated into the radioactive waste management system from initial design
through operation. The fundamental outcome the ALARA process seeks to achieve is an absolute
balance between detriment and benefit. Approved ALARA programs which provide the frame
work for making ALARA determinations are probably in place for radioactive waste management
facilities. The purpose of this requirement is to reinforce this concept. The ALARA process must
be incorporated into all radioactive waste management activities. Line management involvement
and accountability at the highest levels must be maintained. The governing directives on
implementing an ALARA process, 10 CFR Part 835 Occupational Radiation Protection and
DOE 5400.5 Radiation Protection of the Public and the Environment, have been previously
noted in DOE M 435.1-1, Section I.1.E. under Applicability of Other Regulations and DOE
Directives.
Chapter I - General Requirements and Responsibilities
I-154 DOE G 435.1-1
7-09-99
DOE waste management operations are to be conducted so that radiation exposures to workers
and members of the public are maintained as far below regulatory limits as possible, and releases
to the environment are minimized, commensurate with sound economics and operating principles.
ALARA requires judgment with respect to what is reasonably achievable. Factors that relate to
societal, technological, economic, and other public policy considerations are evaluated in making
such judgments. Integration of this process into radioactive waste work plans with continuous
feedback for improvement are essential to achieving the goal of ALARA and thus protecting the
worker, public and the environment. Additional guidance may also be found in the
Implementation Guide for Use With Title 10, Code of Federal Regulations, Part 835,
Occupational Radiation Protection.
Section 123
Example: At a DOE site, an analysis of data on doses to maintenance workers at
a radioactive waste treatment facility shows that doses rose rapidly after four
hours in a radiation area. This was attributed to worker fatigue, since work in
radiation areas requires extra caution and concentration, when compared with
work in non-radiation areas. Additionally, this fatigue factor causes tasks
performed after four hours to take disproportionately longer exposing the workers
to the radiological environment longer and is compounded by their being less
efficient than they are in the first four hours. The net result is more exposure with
less productivity during the second four hours. Limiting work in radiation areas
to four hours and alternating maintenance workers between radiation and
nonradiation areas contributes to achieving ALARA where all other factors are
equal.
Compliance with this requirement is demonstrated by documented analyses showing the
application of the site’s approved ALARA process to the planning for the construction
modification, operation, and closure of radioactive waste management facilities, operations, and
activities.
Supplemental References:
1. DOE. Occupational Radiation Protection, 10 CFR Part 835, U.S. Department of Energy,
Washington, D.C., November 1998.
2. DOE, 1994. Implementation Guide for Use with Title 10, Code of Federal Regulations,
Part 835, Occupational Radiation Protection, G-10 CFR Part 835/B1-Rev.1, U.S.
Department of Energy, Washington, D.C., November 1994.
3. DOE, 1990. Radiation Protection of the Public and the Environment, DOE 5400.5, U.S.
Department of Energy, Washington, D.C., February 8, 1990.
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-155
7-09-99
4. DOE, 1990. Department of Energy (DOE) Radiological Control Manual, DOE/EH
0256, U.S. Department of Energy, Washington, D.C., October 30, 1990.
5. DOE, 1997. ALARA Training for Technical Support Personnel, DOE-HDBK-1110-97,
U.S. Department of Energy, Washington, D.C., 1997. (This document is available from
the Radiation Safety Training home page, http://tis-nt.eh.doe.gov/wpphm/rst/rst.html.)
Chapter I - General Requirements and Responsibilities
http://tis-nt.eh.doe.gov/wpphm/rst/rst.html
I-156 DOE G 435.1-1
7-09-99
I. 2.F. Field Element Managers.
Field Element Managers are responsible for:
(13) Storage. Ensuring all radioactive waste is stored in a manner that protects
the public, workers, and the environment in accordance with a radioactive
waste management basis, and that the integrity of waste storage is
maintained for the expected time of storage and does not compromise
meeting the disposal performance objectives for protection of the public and
the environment when the waste is disposed.
Objective:
The objective of this requirement is to properly store radioactive waste by providing for
containment of the waste during storage, protecting the ability of packages to maintain
containment, and ensuring waste is handled in storage in a way that facilitates proper disposal and
contributes to the long-term performance of the disposal facility.
Discussion:
During the development of DOE O 435.1 and DOE M 435.1-1, the storage of radioactive waste
was identified as an activity that presented potential risk to the public, workers, and the
environment. Numerous weaknesses and conditions were identified during the safety and hazards
analysis conducted in support of the Manual documentation. In addition, previous reviews of
radioactive waste storage conditions and management practices (e.g., Complex-Wide Review of
DOE’s Low-Level Waste Management ES&H Vulnerabilities) revealed inadequately or
improperly stored waste, which presents the possibility of human exposure to radiation and the
potential for adverse environmental effects.
Section 124
The evaluations of storage that were conducted during development of the Order and Manual
revealed a variety of current practices, desired end-states, and required lengths of storage among
DOE’s radioactive waste types. For instance, high-level waste has been in storage, and will
remain in storage, for an indefinite period of time in many different forms (liquids in tanks, calcine
in vessels, vitrified forms in canisters). Transuranic waste has been stored in many locations in
dense-pack, until disposal capacity at WIPP was available. Low-level waste is planned for short
term storage, unless unforeseen circumstances require otherwise. Besides these differences, in
storage times, there are differences in the radiological and chemical hazards posed by storage of
the waste types. Because of these differences, there are numerous waste-type specific storage
requirements that must be met to maintain safe storage. The general requirement is performance
based and states that storage must protect public, workers, and the environment. Waste packages
must be maintained during the storage period, and DOE must ensure that nothing occurs to the
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-157
7-09-99
waste or waste packages that is detrimental to the final disposal of the waste or to meeting the
disposal performance objectives of DOE M 435.1-1.
Integrity of Waste Packages. An essential element of proper storage of radioactive waste is the
assurance that the waste is adequately contained in waste packaging and the package is protected
from conditions that could cause it to degrade. Degradation could lead to failure and result in the
spread of contaminated materials, leading to worker, public, or environmental exposure. It could
also result in non-acceptance by a receiving facility.
Radioactive waste storage facilities should establish waste package design, inspection and
corrective action programs to ensure that package integrity is maintained throughout the storage
period. The inspection and corrective action program should evaluate storage conditions and
eliminate conditions that could lead to package failure.
Example: Bulk contaminated soil and debris was packaged in untreated wooden boxes
and stored outside. Inspection of the storage area revealed that the boxes degraded to
the point that they no longer provide proper containment of the waste. The corrective
action included repackaging the waste and storing the waste packages in a protected
area.
Periodic radiation and contamination surveys of storage areas and waste package should be
performed to provide an indication of waste package integrity and ensure worker protection. It is
not advisable to conduct inspections or surveys at a frequency or within a proximity that may lead
to unnecessary exposure. As Low As Reasonably Achievable (ALARA) practices should always
be considered during radioactive waste storage. Detailed guidance on monitoring of radioactive
waste storage is discussed for high-level waste (Section II.T), transuranic waste (Section III.Q),
and low-level waste (Section IV.R).
New radioactive waste storage facilities should be designed, constructed, and operated so that the
minimum amount of residual radioactive material that requires cleanup prior to closure remains in
the facility. Consideration should be given to facility design to meet other potential requirements.
For example, mixed radioactive waste must be stored in facilities that meet RCRA storage
requirements. Therefore, the facility should be designed to accommodate storage of RCRA
wastes. For facilities storing liquid radioactive waste, the facility should be designed to allow
liquid level, waste volume, and significant tank chemistry parameters, to be monitored.
Section 125
Support Meeting Disposal Objectives. Storage of radioactive waste is usually done to facilitate
future disposal of the waste. Disposal options may not be immediately available and long periods
of storage may be required. Storage systems should be designed to last significantly longer than
the anticipated need for capacity to allow for unexpected delays. The optimization of storage
periods and storage conditions, with the waste and the waste packaging should be performed, as
Chapter I - General Requirements and Responsibilities
I-158 DOE G 435.1-1
7-09-99
part of the Site-Wide Radioactive Waste Management Program required in Section I.2.F. of this
guidance.
Example: The need exists to store a certain radioactive waste stream that has no
identified path to disposal. An analysis is performed by the Site-Wide Radioactive Waste
Management Program to determine the probable storage period and all other
requirements for a potential storage facility. An acceptable storage location is identified
that meets all the storage facility requirements and is compatible with the waste package
and the anticipated storage period for the waste.
Particular consideration should be given to the design and operation of storage facilities to meet
the eventual requirements of the disposal facility. Thus, maintaining the certified status of waste
that is already certified for disposal, and protecting the waste from conditions, either man-made or
natural, that would change the certification status and the acceptance of waste at the disposal
facility is essential. (Further guidance on certification of waste and maintaining certification status
of waste is in the guidance for each of the waste type chapters.) For waste that will be in storage
for a short period, this may not require much additional effort. For waste that remains in storage
for longer than anticipated, this could be quite challenging. Storage facilities should have the
capability of differentiating between waste that is already certified to a disposal waste acceptance
criteria and managing it appropriately.
Compliance with this requirement is demonstrated if the public, the workers, and the environment
are protected from radioactive waste in storage while maintaining complete waste package
integrity during the entire storage period plus that period of time necessary to facilitate proper
disposal. As discussed above, each waste type chapter contains numerous specific storage
requirements, and meeting those requirements is essential in achieving the desired safe storage
that is the objective of this requirement. Additional information on the waste-type specific
storage requirements is contained in the guidance on Chapter II, High-Level Wastes; Chapter III,
Transuranic Waste; and Chapter IV, Low-Level Waste.
Supplemental References: None.
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-159
7-09-99
I. 2.F. Field Element Managers.
Field Element Managers are responsible for:
(14) Treatment. Ensuring all radioactive waste requiring treatment is treated in a
manner that protects the public, workers, and the environment and in
accordance with a radioactive waste management basis.
Objective:
The objective of this requirement is to ensure that when radioactive waste treatment technologies
are utilized, they provide the necessary protection to the public, workers and the environment
from treatment operations and from the resulting treated waste.
Discussion:
Section 126
During the development of DOE O 435.1 and DOE M 435.1-1, the treatment of radioactive
waste was identified as an activity that presented potential risk to the public, workers, and the
environment. Numerous weaknesses and conditions were identified that required controls during
the safety and hazards analysis conducted in support of the Manual documentation. As with the
other major functions that were evaluated (i.e. generation, storage, and disposal), most of the
weaknesses and conditions were found to be already covered by controls in numerous DOE
Directives and external regulations, especially those concerning safety during operations. In
addition, the analysis also confirmed that, although treatment is a separate management step taken
with waste and was evaluated as a distinct function, disposal technologies and requirements are
the primary driving force behind the need for treatment and the type of treatment. Except for
some hazardous waste requirements based on RCRA, (e.g., certain constituents must be
destroyed), the desire for an improved waste form behavior after disposal is usually the reason for
treating waste. There may also be a need for reduced volumes to minimize the amount of disposal
capacity utilized, but this is likewise, a disposal requirement driving the need for treatment.
Additionally, the hazards and requirements analysis resulted in identifying characteristics of
radioactive waste that are unsuitable for long-term storage. These wastes require treatment prior
to their acceptance for storage.
Thus, the controls that must be implemented at a treatment facility in addition to those concerning
operations address the waste forms resulting from the treatment process. Several objectives may
be achieved through treatment such as enhancing the waste form, rendering waste suitable for
storage, reducing disposal waste volumes, minimizing the number of transportation shipments,
enhancing the monitorability of waste disposal facilities, or minimizing the long-term risks to the
public and the environment from waste disposal. This requirement basically forms an umbrella
performance-oriented requirement that requires that treatment technologies used must protect the
Chapter I - General Requirements and Responsibilities
I-160 DOE G 435.1-1
7-09-99
public, workers, and the environment. The treatment and waste form requirements in each of the
specific waste-type chapters must also be complied with to treat radioactive waste successfully in
accordance with DOE O 435.1 and DOE M 435.1-1.
Compliance with this requirement is demonstrated by the issuance of a radioactive waste
management basis for a treatment facility that demonstrates that the public, workers, and the
environment will be protected from the hazards inherent in the treatment facility. The radioactive
waste management basis will ensure that waste form requirements for the resultant treated waste
will be met in addition to the safety and environmental protection objectives of this requirement.
Specific requirements for treatment are in Chapter II, High-Level Waste; Chapter III,
Transuranic Waste; and Chapter IV, Low-Level Waste of the Manual. Guidance on those
requirements can be found in the sections of this document corresponding to the treatment
requirements for each waste type.
Supplemental References: None.
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-161
7-09-99
I. 2.F. Field Element Managers.
Field Element Managers are responsible for:
Section 127
(15) Disposal. Ensuring radioactive waste is disposed in a manner that protects
the public, workers, and the environment and in accordance with a
radioactive waste management basis. Reviewing specific transuranic or low-
level waste documentation including the performance assessment and
composite analysis, or appropriate CERCLA documentation, prior to
forwarding them to Headquarters for approval, and obtaining and ensuring
the facility is operated in accordance with the disposal authorization
statement. Conducting performance assessment and composite analysis
maintenance.
Objective:
The objectives of this requirement are to ensure that: (1) transuranic waste is disposed so there is
a reasonable expectation that the disposal standards in 40 CFR Part 191 will be met; (2) and
low-level waste is disposed so that there is a reasonable expectation that the performance
objectives of Chapter IV of DOE M 435.1-1 will be met. The objectives are also to ensure that
the performance assessment for a transuranic waste disposal facility and the performance
assessment and composite analysis for a low-level waste disposal facility are technically adequate,
logical, complete, and defensible for establishing the controls on disposal of waste for protection
of the public, and the environment into the future. Lastly, the objectives are to ensure that data
are collected and studies conducted to verify these analyses and that they are updated whenever
necessary.
Discussion:
The safety and hazard analysis for management of radioactive waste that was conducted to
develop the essential requirements for DOE O 435.1 and DOE M 435.1-1 indicated that disposal
is a critical activity requiring controls because disposal is the last function in managing waste, yet
the potential hazards from radioactive waste continue into the future. There are specific
requirements for disposal of radioactive waste included in the DOE M 435.1-1 to ensure the
protection of the public, workers, and environment. The analyses conducted in the performance
assessment for a transuranic or a low-level waste disposal facility, and the composite analysis for a
low-level waste disposal facility, are critical in determining the nature and extent of the controls
that need to be put in place. The review and approval of these evaluations is important for the
management of radioactive waste to ensure it is being conducted safely and effectively. This
responsibility is placed with senior management in the Office of Environmental Management (see
Section I.2.E.(1)).
Chapter I - General Requirements and Responsibilities
I-162 DOE G 435.1-1
7-09-99
Even more important is the implementation of the controls that are deemed necessary as a result
of these evaluations. The radioactive waste management basis is intended to coordinate
implementation of the necessary controls for disposal of radioactive waste, the performance
assessment and composite analysis, and related documents that are based on the evaluations in
them (e.g., waste acceptance). These analyses and the controls derived from them form the core
of the radioactive waste management basis for a disposal facility. Additional guidance can be
found in the guidance on the requirement for a Radioactive Waste Management Basis (Section
I.2.F.(2)).
Section 128
DOE M 435.1-1 gives the Field Element Manager responsibility for disposing of radioactive
waste safely, reviewing the performance assessment (and composite analysis if applicable) for
radioactive waste disposal facilities under his/her authority, submitting the evaluations to
Headquarters for review and approval, and ensuring that the evaluations in the performance
assessment and composite analysis are maintained. The discussions that follow provide guidance
on the above requirement for review of the documents and submittal to Headquarters. DOE M
435.1-1, Section I.2.E.(1) contains the requirements of Headquarters for review and approval of
the performance assessment and composite analysis. In order to achieve the safe disposal of
waste, the Field Element Manager is responsible for implementing the controls in the radioactive
waste management basis documentation, which includes the performance assessment, composite
analysis, and disposal authorization statement.
Disposal of Transuranic Waste (not at WIPP). In cases where the Department disposes of
transuranic waste in a facility other than WIPP (e.g., Greater Confinement Disposal at the Nevada
Test Site), the Department is currently responsible for determining compliance with 40 CFR Part
191, and ensuring the transuranic waste is disposed of safely. The requirement includes the
responsibility for ensuring safe disposal of transuranic waste disposed at a facility other than
WIPP, and reviewing performance assessments for any transuranic waste disposal facility,
including WIPP, before submittal to Headquarters. Since performance assessment is defined, and
the requirements for compliance and what must be included in a performance assessment for a
transuranic waste disposal facility are fully discussed in 40 CFR Part 191, the transuranic waste
chapter only contains reference to the 40 CFR Part 191 standards, with no additional minimum
requirements for disposal. Guidance on the transuranic waste disposal requirements at Section
III.P should be consulted for additional discussions.
Safe and Environmentally Sound Disposal of Low-Level Waste. DOE M 435.1-1 contains
requirements that must be met for the siting, design, operations, closure, and maintenance of DOE
low-level waste disposal facilities. Achieving the goals of protecting the public, workers, and the
environment from the potential hazards of disposal of low-level waste requires linking the
functions of design, siting, operation, closure, and maintenance to the performance assessment
objectives of DOE M 435.1-1, Section IV.P.(1), taking into consideration the waste and
radionuclides to be disposed. It is the Field Element Manager’s responsibility to link these critical
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-163
7-09-99
functions for control of low-level waste disposal facilities to the performance assessment and
composite analysis evaluations, and to determine the level of controls within each of these
functions that need to be imposed to continue to achieve the low-level waste disposal facility
performance objectives. This responsibility is embodied in the concept of a radioactive waste
management basis for a disposal facility. The linkage between the controls on these operational
functions of the disposal facility and the evaluations in the performance assessment and composite
analysis forms the critical components of the radioactive waste management basis for the facility.
An important aspect of this linkage is the incorporation of changes in disposal facility operations,
closure, monitoring, waste acceptance criteria, or other low-level waste management functions by
the implementation of the conditions spelled out in the disposal authorization statement from
Headquarters.
Section 129
Example: The Field Element Manager for the Site R Low-Level Waste Disposal Facility
approves the radioactive waste management basis for the disposal facility. He has
thoroughly reviewed the performance assessment, disposal authorization statement,
preliminary closure and monitoring plans, quality assurance plan, performance
assessment maintenance procedure, and training manual. He also has a thorough
understanding of the relationship of the controls described in the procedures and
manuals, and of the results of the evaluation explained in the performance assessment
and the conclusions of Headquarters documented in the disposal authorization statement.
Section IV.P. contains the detailed requirements for disposal of low-level waste, and design,
siting, maintenance, closure, and operations of a low-level waste disposal facility. More
discussion on safe disposal of low-level waste, and the link between disposal operational functions
and the performance assessment, composite analysis, and the disposal authorization statement,
appears in the guidance on Chapter IV.
Reviewing and Submitting Low-Level Waste Performance Assessments and Composite Analyses.
It is the responsibility of the Field Element Manager to submit the performance assessment and
composite analysis to Headquarters for review. Chapter IV of the DOE M 435.1-1 contains the
detailed requirements for performance assessments and composite analyses for a low-level waste
disposal facility. More guidance appears on this subject in the guidance on Chapter IV. DOE G
435.1-1, Format and Content Guide for U.S. Department of Energy Low-Level Waste Disposal
Facility Performance Assessments and Composite Analyses (under preparation), will provide
details on the format and content of performance assessments and composite analyses. Preparers
need to follow that guidance document to ensure that complete information is included.
Prior to submitting these documents to Headquarters for review, the Field Element Manager
reviews them to ensure they are complete and consistent with planned disposal facility operations
and use. An independent organization or group may review these documents to assist the Field
Element Manager in ensuring that all manual requirements identified have been properly
Chapter I - General Requirements and Responsibilities
I-164 DOE G 435.1-1
7-09-99
addressed. This review process will ensure that once the document is submitted to DOE
Headquarters it will not be determined to be deficient in content. It also enables the responsible
organization to obtain an independent opinion on the technical adequacy and defensibility of the
information presented.
Example: Prior to submittal to Headquarters for review and approval, the performance
assessment and composite analysis are reviewed against the Standard Format and
Content Guide for U.S. Department of Energy Low-Level Waste Disposal Facility
Performance Assessments and Composite Analyses by two former members of the DOE
Peer Review Panel, funded by the appropriate Field Element Manager. Consideration of
their comments results in a more complete and technically defensible evaluation.
Section 130
The performance assessments and/or composite analyses are submitted to the Deputy Assistant
Secretary for Waste Management, unless the facility being evaluated is an onsite low-level waste
management unit being developed under CERCLA. In the case of a CERCLA onsite low-level
waste management facility, documentation including a crosswalk from CERCLA to DOE O 435.1
(see Section I.2.E) and a separate composite analysis if one is prepared, are submitted to the
Deputy Assistant Secretary for Environmental Restoration. For CERCLA onsite low-level waste
management facilities, the Standard Format and Content Guide, DOE G 435.1-1, should be
consulted and implemented in the development of the CERCLA documentation to ensure that
adequate analysis is included to demonstrate compliance with the DOE O 435.1 and DOE M
435.1-1 (see guidance on DOE M 435.1-1, Section I.2.F.(5)).
Low-Level Waste Performance Assessment and Composite Analysis Maintenance. Once
authorized to operate, a low-level waste disposal facility may be in operation for many years.
Uncertainties may exist in certain aspects of the technical decisions when assumptions were made
during the performance assessment and the composite analysis. Additionally, information about
waste receipts and knowledge concerning the disposal facility environs could change. Therefore,
DOE M 435.1-1 requirements include maintaining the performance assessment and composite
analysis through regular collection of data and studies designed to reduce uncertainties, and a
regular schedule of evaluations to update the analysis. It is the responsibility of the Field Element
Manager to ensure these requirements are carried out. DOE M 435.1-1 Chapter IV contains the
detailed requirements for maintenance of the performance assessment and composite analysis for a
low-level waste disposal facility. Also, DOE G 435.1-3, Maintenance Guide for U.S.
Department of Energy Low-Level Waste Disposal Facility Performance Assessments and
Composite Analyses (under preparation), will provide guidance on performing the critical function
of keeping these important analyses updated.
Example: The Field Element Manager with responsibility over a low-level waste
disposal facility at Site A issues a procedure, in accordance with Site A Manual WM
100-5, mandating performance assessment and composite analysis maintenance that
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-165
7-09-99
follows the guidance in DOE G 435.1-3, Maintenance Guide for U.S. Department of
Energy Low-Level Waste Disposal Facility Performance Assessments and Composite
Analyses.
Compliance with this requirement is demonstrated through the low-level waste disposal facility
documentation, that shows the siting, design, operation, closure, and maintenance of the facility
are linked to the evaluations in the performance assessment and composite analysis, and that these
documents have been properly submitted to Headquarters for review in accordance with guidance
in DOE G 435.1-1, Format and Content Guide for U.S. Department of Energy Low-Level Waste
Disposal Facility Performance Assessments and Composite Analyses. Additionally, the
documentation demonstrates that a program/process has been put in place for conducting
performance assessment and composite analysis maintenance in accordance with DOE 435.1-3,
Maintenance Guide for U.S. Department of Energy Low-Level Waste Disposal Facility
Performance Assessments and Composite Analyses.
Section 131
Supplemental References:
1. DOE, 1999. Format and Content Guide for U.S. Department of Energy Low-Level Waste
Disposal Facility Performance Assessments and Composite Analyses (in preparation),
DOE G 435.1-1, U.S. Department of Energy, Washington, D.C., 1999.
2. DOE, 1999. Maintenance Guide for U.S. Department of Energy Low-Level Waste
Disposal Facility Performance Assessments and Composite Analyses. (in preparation),
DOE G 435.1-3, U.S. Department of Energy, Washington, D.C., 1999.
3. EPA, 1985. “Final rule; 40 CFR Part 191, Environmental Radiation Protection Standards
for Management and Disposal of Spent Nuclear Fuel, High-Level and Transuranic
Radioactive Wastes,” Federal Register, Vol 50, No. 182, U.S. Environmental Protection
Agency, Washington, D.C., September 19, 1985.
4. EPA, 1993. “Final rule; Environmental Radiation Protection Standards for the
Management and Disposal of Spent Nuclear Fuel, High-Level and Transuranic
Radioactive Wastes,” Federal Register, Vol. 58, No. 242, U.S. Environmental Protection
Agency, Washington, D.C., December 20, 1993.
5. DOE, 1996. Interim Format and Content Guide, and Standard Review Plan for U.S.
Department of Energy Low-Level Waste Disposal Facility Performance Assessments,
U.S. Department of Energy, Washington, D.C., October 1996.
6. DOE, 1996. Maintenance of US Department of Energy Low-Level Waste Performance
Assessments, U.S. Department of Energy, Washington, D.C., September 1996.
Chapter I - General Requirements and Responsibilities
I-166 DOE G 435.1-1
7-09-99
I. 2.F. Field Element Managers.
Field Element Managers are responsible for:
(16) Monitoring. Ensuring monitoring is conducted for all radioactive waste
management facilities as required. Ensuring that disposal facilities are
monitored, as appropriate, for compliance with conditions of the disposal
authorization statement.
Objective:
The objective of this requirement is to ensure that all monitoring is conducted as required,
including monitoring of storage, treatment, and disposal facilities with respect to key parameters
and conditions of their authorization statements.
Discussion:
The safety and hazard analysis identified that monitoring for releases of radiation and radioactive
material to the environment was an especially important mitigating factor for potential weaknesses
and conditions in radioactive waste management. The requirements analysis concluded that the
environmental monitoring programs and plans, as required by DOE 5400.1, General
Environmental Protection Program; and DOE 5400.5, Radiation Protection of the Public and
Environment, implemented monitoring that would address the kinds of concerns evaluated in the
analysis.
However, monitoring of disposed radioactive waste, because it must remain effective for a long
time period following cessation of operations, presents a unique challenge. Additional monitoring
of low-level waste disposal facilities is addressed in DOE M 435.1-1, Section IV.R.
Implementation guidance for those requirements should be consulted for information on
incorporating additional low-level waste disposal facility performance monitoring into the
environmental monitoring program and plans already required to be in compliance with the
subject DOE Orders on environmental monitoring.
Section 132
Additionally, while the general environmental monitoring program and the environmental
monitoring plans mandated by these DOE Orders are adequate for most circumstances, they were
judged to not be sufficient in requiring identification of specific warning signs of impending
conditions that would lead to releases, especially for storage of liquid low-level waste. DOE M
435.1-1, Sections IV.R.(1) and IV.R.(2) address these aspects of additional monitoring for low-
level waste facilities. Also, the environmental monitoring requirements did not sufficiently
address monitoring of the performance of a low-level waste disposal facility, for identification of
specific signs that assumptions made in evaluations of the facility (i.e., performance assessment)
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-167
7-09-99
were incorrect or for warning signs of conditions that should be addressed in a timely fashion to
prevent conditions that were not evaluated. DOE M 435.1-1, Section IV.R.(3) addresses
additional monitoring needed for low-level waste disposal facilities.
Additionally, through the conduct of safety analyses, whether they are formal safety analysis
reports or auditable safety analyses, facility personnel identify the quantity and form of radioactive
and/or hazardous material to be handled at the facility and the operations for managing the waste.
The safety analysis establishes a basis for defining the acceptable operations envelope for the
facility, and provides the basis for technical safety requirements (TSRs). The technical safety
requirements may include requirements for monitoring. Review of the safety analysis will
determine if the analyses indicate other monitoring that would be prudent.
The DOE M 435.1-1 requirement states that it is the responsibility of the Field Element Manager
to ensure that monitoring is conducted for all radioactive waste management facilities as required,
including ensuring that disposal facilities are monitored, as appropriate, for compliance with
conditions of the disposal authorization statement.
The requirements for monitoring low-level waste disposal facilities are additional requirements
beyond the Chapter I requirements which are applicable to all facilities. Site-specific performance
assessments and composite analyses are required for all low-level waste disposal facilities by DOE
M 435.1-1, Sections IV.P. (2) and (3). These documents have the purpose of evaluating the
long-term performance of the disposal facility and providing reasonable assurance that the
performance objectives for low-level waste disposal are met. Assessments of the long-term
performance of natural systems often have large uncertainties, and include many assumptions of
the behavior of natural systems over extended periods of time. The performance assessment and
composite analysis of a disposal system identifies these uncertainties and assumptions along with
the results. An effective way to verify assumptions, reduce uncertainties, and build confidence in
the results and conclusions of the performance assessment and composite analysis is to monitor
the performance of the disposal facility.
Thus, the performance assessment and composite analysis are used as primary tools for
establishing the monitoring plan to collect data to develop an understanding of the actual
performance of the disposal facility. The performance assessment and composite analysis should
provide sufficient information to identify the important migration pathways for the transport of
radionuclides, primary mobile radiological and chemical constituents, logical monitoring locations,
monitoring parameters, and sampling frequencies.
Section 133
With respect to long-term performance of the low-level waste disposal facility to ensure the
performance objectives are met, monitoring data are reviewed periodically against the action
levels contained in the monitoring plan (see guidance on DOE M 435.1-1, Section IV.R.(3)(c)).
This review is conducted routinely throughout the operational, closure and post-closure periods
Chapter I - General Requirements and Responsibilities
I-168 DOE G 435.1-1
7-09-99
of the facility to evaluate the performance of the facility as compared to the results contained in
the performance assessment and composite analysis, detect trends in the performance of the
facility sufficiently in advance to allow for necessary corrective actions, and to provide
justification for changes in the monitoring plan for the facility. Additional guidance on this aspect
of monitoring data evaluation is provided with the discussion of Section IV.R.(3)(c).
Compliance with this requirement is demonstrated if monitoring plans are developed, approved,
maintained, and implemented throughout the life cycle of the facilities.
Supplemental References:
1. DOE, 1988. General Environmental Protection Program, DOE 5400.1, U.S. Department
of Energy, Washington, D.C., November 9, 1988.
2. DOE, 1990. Radiation Protection of the Public and the Environmental, DOE 5400.5,
U.S. Department of Energy, Washington, D.C., February 8, 1990.
3. NRC, 1989. Environmental Monitoring of Low-Level Radioactive Waste Disposal
Facility, NUREG-1388, U.S. Nuclear Regulatory Commission, Washington, D.C., 1989.
4. NRC, 1983. Subsurface Monitoring Programs at Sites for Disposal of Low-Level
Radioactive Waste, NUREG/CR-3164, U.S. Nuclear Regulatory Commission (by U.S.
Army Corps of Engineers Waterways Experiment Station), Washington, D.C., 1983.
5. DOE, 1990. Environmental Monitoring for Low-Level Waste Disposal Sites: Low-Level
Management Handbook Series, Revision 2, DOE/LLW-13Tg, U.S. Department of
Energy, National Low-Level Waste Management Program, Idaho Falls, ID, 1990.
6. DOE, 1991. Environmental Regulatory Guide for Radiological Monitoring and
Environmental Surveillance, DOE/EH-0173T, U.S. Department of Energy, 1991.
7. DOE, 1981. A Guide for Environmental Radiological Surveillance at U.S. Department
of Energy Installations, DOE/EP-0023, U.S. Department of Energy, Washington, D.C.,
1981.
8. NRC, 1979. Quality Assurance for Radiological Monitoring Programs (Normal
Operations)--Effluent Streams and the Environment, Regulatory Guide 4.15, U.S.
Nuclear Regulatory Commission, Washington, D.C., February 1979.
9. DOE, 1986. Experience and Improved Techniques in Radiological Environmental
Monitoring at Major DOE Low-Level Waste Disposal Sites, DOE/LLW-54T, U.S.
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-169
7-09-99
Department of Energy, National Low-Level Radioactive Waste Management Program,
Idaho Falls, ID, 1986.
Chapter I - General Requirements and Responsibilities
I-170 DOE G 435.1-1
7-09-99
I. 2.F. Field Element Managers.
Field Element Managers are responsible for:
(17) Material and Waste Declassification for Waste Management. Ensuring, to
the extent practical, radioactive material and waste generated under a
program that is classified for national security reasons is declassified or
rendered suitable for unclassified radioactive waste management.
Objective:
Section 134
The objective of this requirement is to reduce unnecessary management costs and maintain
national security by ensuring that radioactive material and waste is, as practical, declassified and
managed as unclassified waste.
Discussion:
Some radioactive waste is the product of activities that are classified for national security reasons
and therefore the waste may require special handling and protection. The waste may be any
classified substance regardless of its form, e.g., fabricated or processed items, machinery, or
equipment which inherently contains sensitive information. It may be classified for a variety of
reasons such as dimensions, configuration, potential for reverse engineering to determine its
function, or radionuclide content.
The management of classified radioactive waste could be more costly and difficult than
unclassified waste. The Department has an ongoing effort to declassify or sanitize classified
material including waste. Declassification of waste was a requirement in the management of
transuranic waste in the previous order on Radioactive Waste Management. In reviewing
requirements for inclusion in DOE M 435.1-1, it was realized that declassification/sanitization is a
sound management practice that needs to be applied across all waste types. Declassification or
sanitization of radioactive material that will become waste can enhance efficient and cost effective
management of radioactive waste since it allows the Department to avoid the security costs
associated with classified material.
Declassification means a determination by an appropriate authority that information, documents,
or material no longer require protection against unauthorized disclosure for national security
reasons. At one time, many alloys were considered classified, however, as a result of the
Department’s Openness Initiative, the Director of Security Affairs has determined that some of
these alloys no longer require protection as classified information and has declassified them. The
information remains the same, but it no longer requires security protection.
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-171
7-09-99
In contrast, sanitization means the irreversible modification or destruction of a component or part
of a component of a nuclear weapon, device, trainer, or test assembly as necessary to prevent
revealing classified or otherwise controlled information. Figure I.2.F.I provides a description of
the declassification and sanitization process:
Classified by
Classification
Guidance?
Is it
waste?
Does
info. still
warrant
class?
Send proposal to
declassify to NN-52
Classified
Treatment/
Storage/Disposal
Can it be
sanitized?
Classified
Reuse/Recycle
Unclassified
Reuse/Recycle
Yes
NoYes No Yes
Yes
No
No
No
Radioactive
Material
Declassifies
Is it
waste?
Unclassified
Treatment/
Storage/Disposal
Yes
Yes No
Sanitize
Figure I.2.F.1. Flow Diagram for Declassifying or Sanitizing Material for Waste Management
Chapter I - General Requirements and Responsibilities
I-172 DOE G 435.1-1
7-09-99
Section 135
Example 1: As a result of weapons disassembly, components that are made of a
classified alloy have become excess. Some of these components are contaminated by
radioactivity. The custodian of the component believes that the alloy no longer warrants
protection in the interest of national security. The custodian proposes to the Office of
Declassification, that the alloy be declassified. The decision is made that the alloy no
longer needs to be classified and it is declassified. The component is handled as
unclassified excess material and an evaluation made to determine if it has any future
programmatic value. The result of that analysis leads to the conclusion that the
components are radioactive waste so they are treated, stored, and disposed without
classified controls. Since the alloy has been declassified, future decisions concerning
components made of it may be made by a Derivative Declassifier.
Example 2: As a result of weapons disassembly, a component whose shape is classified is
being excessed. It can be sanitized by melting it into another shape or by pulverizing it,
thus destroying the information that needs to be protected. The component can be
handled as unclassified excess material, or if determined to be a radioactive waste, it can
be treated, stored, or disposed without classified controls.
Material that is classified and can be declassified or sanitized should be handled in accordance
with current classification guidance. However, certain classified material, once it is determined to
be of no future programmatic use (i.e., waste), cannot be declassified or sanitized, and thus, is
ultimately disposed of in a classified disposal site.
Example: A radioactive material has been determined to be of no future use due to
advances in technology and is therefore determined to be a radioactive waste. The
characteristics of the radioactive contamination i.e., the level of enrichment, requires
protection to preclude revealing sensitive weapons information. As a waste classified
which cannot be decontaminated, the waste must be afforded security protection and
ultimately disposed of in a classified disposal site.
Classified waste is to be minimized whenever practical to reduce costs and increase efficiency in
waste management programs. Decisions to continue to manage a waste as classified need to be
based on careful consideration of requirements in the areas of environment, safety and health,
safeguards and security, proliferation, and of total cost factors.
If waste can be declassified or economically sanitized, it can be disposed of in conventional
facilities not requiring special protection and it avoids the cost of security during transport.
Declassifying or sanitizing waste also preserves capacity in classified disposal facilities for that
waste that cannot be declassified or sanitized.
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-173
7-09-99
Example: A facility has a classified waste. The facility’s manager analyzes the options
for managing the waste and discovers that it cannot be declassified, but can be sanitized.
However, the treatment required in order to sanitize it would equal or exceed the cost of
the necessary protections during transportation and disposal of the classified waste, with
no increase in the protection of workers, the public, or the environment and no
significant reduction in security or proliferation concerns. Therefore, the manager
decides that the waste need not be sanitized and that use of a classified disposal facility
is appropriate.
Section 136
Compliance with this requirement is demonstrated by documented determinations that waste has
been declassified or sanitized or by documented evaluations that support maintaining the
classification for either national security or economic reasons.
Supplemental References:
1. DOE, 1998. Identifying Classified Information , DOE M 475.1-1, U.S. Department of
Energy, Washington, D.C., May 8, 1998.
2. Classified National Security Information, Executive Order 12958, Washington, D.C.,
April 17, 1995.
Chapter I - General Requirements and Responsibilities
I-174 DOE G 435.1-1
7-09-99
I.2.F. Field Element Managers.
Field Element Managers are responsible for:
(18) Waste Incidental to Reprocessing. Ensuring that waste incidental to
reprocessing determinations are made by either the “citation” or
“evaluation” process as described in Chapter II of this Manual. Ensuring
consultation and coordination with the Office of Environmental
Management for waste determined to be incidental to reprocessing through
the “evaluation” process.
Objective:
The objective of this requirement is to ensure that the processes and responsibilities for making
waste incidental to reprocessing determinations are understood and implemented.
Discussion:
As discussed in Section II.B, Waste Incidental to Reprocessing, there are certain waste streams
that may be generated during the management of high-level waste that may not have to be
managed as high-level waste and therefore can be managed as another type (transuranic or low-
level waste). To make such determinations, DOE M 435.1-1 establishes two processes, the
citation process and the evaluation process. These are described in detail in Section II.B. In
addition, Section II.A, Definition of High-Level Waste, provides assistance in determining
whether a waste stream should be classified as high-level waste.
Determinations. To meet the first part of the requirement, the Field Element Manager, or
designee, needs to establish a process or method that documents waste incidental to reprocessing
decisions. Such a method is required by the evaluation process (see Section II.B.(2)) and is
recommended for the citation process, although not required. While the level of formality of the
process is left to the discretion of site management, the following elements are considered
necessary:
1. Organization and Responsibilities: Identification of the site organizations that are
responsible for formulating and approving the determinations.
2. Procedures: The process is formalized in procedures, including a requirement
confirming the determination process has been followed correctly.
3. Quality Assurance: The determination process is subject to a quality assurance
program that ensures the validity of the information used to make the
determinations.
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-175
7-09-99
4. Document/Record Control: The principal documents that constitute the
documentation of the determination process are controlled and retained.
5. Training: At a minimum, the process requires training of personnel that will
implement the process (e.g., procedures, quality assurance program, document
control).
Section 137
The above elements have been recommended by the Nuclear Regulatory Commission (NRC)
(Bernero, 1993), and adopted by DOE, as good practices for performing and documenting waste
incidental to reprocessing determinations. Invoking existing programs (e.g., quality assurance
program) and processes (e.g., document control) to implement the waste incidental to
reprocessing determination process is appropriate. Additionally, site management may conclude
that instead of making determinations for individual waste streams, it may be cost effective to
establish categories of wastes that meet the citation and the evaluation process requirements and
therefore avoid a determination for each candidate waste.
Example: At Site X, management of the high-level waste tank farm involves periodic
sampling and analysis of tank contents. When taking these samples, operations
personnel generate job wastes, including protective clothing, work tools, and personnel
protective equipment. In implementing the Site’s “Citation Determination Process,” a
determination is made that such job wastes are not high-level waste. The Site’s
procedures for making citation process (waste incidental to reprocessing) determinations
requires that an initial documented determination is necessary for each waste stream.
However, following this determination, and with the appropriate documentation and
approvals, e.g., a basis for concluding the waste stream meets the citation criteria,
similar wastes can be considered to be non-high level waste by inclusion within this
determination. Thus, future generation of similar wastes from similar activities do not
have to be subjected to the citation determination process if it can be shown that they fit
within the existing determination.
Citation Process. The Field Element Manager, using the process described in Section II.B.(1), is
responsible for determining if a waste meets the citation process requirements. While not
required, it is recommended that the process described for the evaluation process be implemented
for the citation process as well. These elements are considered important to making defensible
and consistent citation determinations and would be valuable if such determinations are
questioned or challenged.
Guidance for Section II.B.(1), Citation, provides information and examples of the types of wastes
and waste streams that have been considered to be non-high-level waste by use of the citation
process. However, it is emphasized that these are examples only, and it is the Field Element
Chapter I - General Requirements and Responsibilities
I-176 DOE G 435.1-1
7-09-99
Manager’s responsibility to make, and defend, citation process determinations. While challenges
to these determinations are not expected, prudence suggests that a process similar to that required
for the evaluation process (see below) be considered for the citation process by site management.
In addition, consultation and coordination with the DOE Office of Environmental Management to
support consistent interpretations of citation determinations is encouraged.
Section 138
Evaluation Process. As noted in the guidance to Section II.B.(2), Evaluation, waste incidental to
reprocessing determinations using the evaluation process require the involvement of two
organizations: the program (site) management responsible for the management of the high-level
waste (includes the Field Element Manager, or designee) and the DOE Office of Environmental
Management (DOE EM). In using the evaluation process, the elements described under
Determinations above need to be implemented to ensure that the requirements of Section II.B.(2)
are met. These requirements are met by the use of good record-keeping practices, with an
adequate quality assurance process, and documented to support the determination(s). The
documentation is prepared in a manner that defends and supports the conclusions and provides
adequate information to support outside organizations’ review and approval. During the
preparation of the determination package, the Field Element Manager is responsible for ensuring
it is coordinated with the Office of Environmental Management, to ensure consistency of
evaluation determinations between DOE sites. At the time of the preparation of this guidance the
office within the Office of Environmental Management that is responsible for fulfilling this
consultation role is the Office of Waste Management.
As discussed in the guidance to Section II.B, it is recommended that groups of waste streams or
waste items that have similar characteristics, or will require similar processing/treatment, be
grouped within one evaluation process analysis in lieu of preparing/submitting analysis for
individual waste streams or waste items. Such grouping is expected to be possible and avoid
duplication of preparation and review efforts by Site and the Office of Environmental
Management personnel and expedite management of the wastes. In addition, grouping the waste
streams promotes the best use of resources at both the DOE site level and the Office of
Environmental Management and reduces the number of determinations that need to be processed.
NRC Role in Waste Incidental to Reprocessing Determinations. In September 1998 the DOE
General Counsel (Letter, Mary Anne Sullivan to John T. Greeves, NRDC Petition, September 30,
1998) concluded, in response to a Natural Resources Defense Council Petition, that the NRC has
no licensing authority over the 51 high-level waste tanks at the Savannah River Site. This
conclusion was based on the following summary statement:
“Section 202(4) of the ERA (Energy Reorganization Act) gives the NRC licensing
authority over DOE facilities ‘authorized for the express purpose of subsequent long-term
storage of high level radioactive waste generated by [DOE and its predecessor agencies].’
As explained in greater detail in the discussion below, this statutory language, the
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-177
7-09-99
legislative history and governing case law establish that this licensing authority exists only
with respect to facilities that are (i) authorized by Congress for the express purpose of
long-term storage of HLW and (ii) developed and constructed after the passage of the
ERA. None of the SRS tanks have been authorized for the express purpose of long-term
storage of HLW and only 18 of the newer tanks were constructed after the passage of the
ERA. As a result, NRC has no licensing authority over the SRS tanks.”
Section 139
From this determination DOE has taken the position in DOE O 435.1 and DOE M 435.1-1 that,
unless determined otherwise, NRC does not have licensing authority over DOE’s current high-
level waste tanks and the waste contained in them. While it is acknowledged that similar
determinations have not been made for the high-level waste tanks at Hanford, INEEL, and West
Valley and that Departmental decisions in the future could change this position, it is believed that
the approach defined in the Order and Manual is reasonable for all DOE-managed high-level
waste. It should be noted, however, that the West Valley Demonstration Project Act specifies a
review and consultation responsibility for the NRC which may include oversight of the high-level
waste tanks. If this position changes, i.e., it is determined that the NRC has regulatory authority
over some of the high-level waste tanks within the DOE complex, the requirements in Sections
II.B. and I.2.F.(18) will be revised accordingly.
The Waste Incidental to Reprocessing requirement in Section II.B and the requirement in Section
I.2.F.(18) support the position that formal involvement by NRC in making incidental waste
determinations is not required. However, NRC involvement as a consultant to Field Offices and
Programs on technical issues, is recommended, particularly for those waste streams that are
expected to be controversial or contentious with other regulators or stakeholders. The NRC staff
has conducted several reviews recently on compliance with criteria similar to the evaluation
requirements in Section II.B.(2) and thus possess a level of expertise that is expected to
complement the Field Office and DOE Office of Environmental Management reviews.
Example: Site X anticipates removing and disposing of many contaminated mixers/pumps
and instrument trees from high-level waste tanks in the next few years. Characterization
data and past experience in handling and disposing of this equipment indicate that the
contamination levels, following decontamination activities, will likely allow these pieces
of equipment to be managed and disposed as low-level waste, assuming they can meet the
evaluation requirements under the DOE M 435.1-1, Waste Incidental to Reprocessing,
Section II.B.(2). Plans over the next three years for removal and disposal of this
equipment are reviewed and used to prepare the analysis required by Section II.B.(2).
The decision is to use the most conservative (highest) contamination levels expected for
this grouping of contaminated equipment for the three-year period to avoid continual
preparation/review of separate evaluations. The analysis is prepared and concludes that
the evaluation process requirements at Section II.B.(2)(a) 1., 2., and 3., can be met, and
therefore, these waste items qualify for management as low-level waste. This analysis is
Chapter I - General Requirements and Responsibilities
I-178 DOE G 435.1-1
7-09-99
prepared under Site X’s quality assurance program, is coordinated with the Office of
Waste Management, and is reviewed and approved by Site X waste management
personnel in accordance with Site X procedures. During preparation of the analysis, the
NRC is requested by Site X management to review and provide their position on the
adequacy of the performance assessment prepared to meet the requirement in Section
II.B.(2)(a)2. Following this review and the Site X’s review and acceptance, the Site X
High-Level Waste Program Manager approves the determination allowing these wastes,
as defined in the determination, to be managed and disposed as low-level waste for the
next three years without further review. The analysis and results of the determinations
are incorporated into the facility’s safety documentation and a copy is provided to the
Office of Waste Management.
Section 140
Compliance with this requirement is demonstrated by developing and implementing a process for
documenting waste incidental to reprocessing determinations as specified in Section II.B.
Specific to the evaluation process, the documentation includes analysis that supports the
conclusions reached, as well as DOE Office of Environmental Management concurrence, that the
waste meets the evaluation requirements in Section II.B of DOE M 435.1-1.
Supplemental References:
1. Bernero, 1993. R. Bernero, USNRC, to J. Lytle, DOE-EM, letter, Hanford Waste Tank
Management, U.S. Nuclear Regulatory Commission, Washington, D.C., March 2, 1993.
2. Paperiello, 1997. C. Paperiello, USNRC, to J. Kinzer, DOE-RL, letter, Classification of
Hanford Low-Activity Tank Waste Fraction, U.S. Nuclear Regulatory Commission,
Washington, DC, June 9, 1997.
3. Sullivan, 1998. Mary Anne Sullivan, DOE General Counsel, to John T. Greeves,
Director, Division of Waste Management, USNRC, letter, Natural Resources Defense
Council Petition to Exercise Licensing Authority over Savannah River Site High-Level
Waste Tanks, U.S. Department of Energy, Washington, DC, September 30, 1998.
4. West Valley Demonstration Project Act, as amended, October 1, 1980.
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-179
7-09-99
I. 2.F. Field Element Managers.
Field Element Managers are responsible for:
(19) Waste with No Identified Path to Disposal. Ensuring a process is developed
and implemented for identifying the generation of radioactive waste with no
identified path to disposal, and reviewing and approving conditions under
which radioactive waste with no identified path to disposal may be
generated. Headquarters shall be notified of the decisions to generate a
waste with no path to disposal.
Objective:
The objective of this requirement is to bring issues associated with generating waste with no
identified path to disposal to the attention of appropriate DOE managers before the waste is
generated to resolve the problems that will prevent it from being disposed, to ensure that the
waste has appropriate long-term safe storage until it can be disposed, and to minimize the
generation of waste with no path to disposal.
Discussion:
The Complex-Wide Review of DOE Low-Level Waste ES&H Vulnerabilities conducted in
response to Defense Nuclear Facilities Safety Board Recommendation 94-2 identified storage of
low-level waste with no identified path forward to disposal as a major complex-wide vulnerability.
DOE M 435.1-1 addresses this vulnerability in several ways. The Safety and Hazards Analysis
conducted as part of the preparation of DOE O 435.1 also identified significant weaknesses and
risks associated with wastes being generated with no path to disposal for all radioactive waste
types, particularly weaknesses associated with long-term storage of waste, potential loss of
characterization data from generators, and the problems associated with re-characterization.
This requirement is intended to cover newly generated waste streams. Waste streams generated
in the past with no path to disposal which are now in storage should be addressed in the Site-
Wide Radioactive Waste Management Program required by DOE M 435.1-1, Section I.2.F.(1).
(See discussion entitled, Relationship to Site-Wide Radioactive Waste Management Program.)
Section 141
Waste streams without a path to disposal that currently are being generated are also to be
addressed by the Site-Wide Management Program. A periodic evaluation of whether no path to
disposal waste should continue to be generated should be included in the management plans for
this waste. This evaluation should consider the same conditions for approval for continuing to
generate the waste stream that are described below under Conditions for Review and Approval.
If a facility that currently generates no path forward waste is shutdown, or for any other reasons a
Chapter I - General Requirements and Responsibilities
I-180 DOE G 435.1-1
7-09-99
no path forward waste stream is temporarily not being generated, consideration should be given
to including those wastes in the identification, approval, and notification process described in this
section of the guidance.
Example 1: All transuranic and low-level waste streams to be generated from the New
Mixed Waste Treatment Facility at Site X, scheduled to begin operations three years after
issuance of DOE O 435.1, are all considered new waste streams. A full life-cycle
planning process is applied to all waste from the facility to identify potential disposition
issues and approve its generation.
Example 2: A filter system in Building 440 at Site Y is changed out four months after
issuance of the Order. The resultant filter process waste is mixed low-level waste.
Change out of the filter media has occurred repeatedly in the past, and the mixed low-
level waste is in storage awaiting a disposal path. This is not considered a new waste
stream and is not included in the Site’s procedures for identification of potential no path
forward waste, for approval, and for HQ notification. However, it is described in the
Site’s Waste Management Program documentation, along with the steps being taken to
achieve disposal. The Site’s program documentation also includes an evaluation of the
need to continue to generate this no path forward waste.
Example 3: One year after issuance of the Order, Building 440 is shutdown for major
upgrades, and does not resume operation for 18 months. When operations are resumed,
all waste streams, including the existing filter media waste, will be included in the
identification process and the waste stream generation will be in accordance with the
approval process established by the Field Element Manager.
By requiring Field Element Managers to be involved with the decisions for generating wastes
without a path to disposal prior to waste generation, and notifying Headquarters of the decisions
to generate waste without a path to disposal prior to generation, senior management attention is
directed to the long-term commitment made with the generation of such waste. The long-term
commitment comes from the prolonged storage of the waste and from the work necessary to
resolve issues which prohibit the disposal of the wastes.
The requirement calls for the Field Element Manager to ensure that three items are established in
the programs implemented by waste generators (see DOE M 435.1-1, Section I.2.F.(7)): (1) a
process for identifying the generation of no path forward waste prior to its generation, (2)
approved conditions under which no path forward to disposal waste may be generated, and (3) a
process for notifying appropriate Headquarters management of decisions to generate no path
forward waste. Each of these three items is discussed in the following guidance.
Section 142
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-181
7-09-99
No Path Forward Identification Process. The first part of the requirement is directly related to the
general requirement calling for the Field Element Manager to ensure generation planning is
occurring by all generators (DOE M 435.1-1, Section I.2.F.(7)), and to the subrequirement in
each waste type chapter that requires generator planning to include life-cycle planning for all
wastes prior to their generation (DOE M 435.1-1, Sections II.K.(1), III.H.(1), and IV.H.(1)). As
discussed previously, “prior to their generation” applies to the stage before any of the waste is
produced (e.g.,preceding the activity that will result in the waste). Therefore, this requirement is
not intended to be applied to the generation of an individual waste drum, source, box, etc.
The situations which may lead to the generation of waste without a path to disposal are many.
The life-cycle planning that is required under DOE M 435.1-1, Sections II.K.(1), III.H.(1), and
IV.H.(1) needs to include the necessary elements and components to identify the possible
generation of waste which will have no path to disposal prior to their generation and a process by
which the Field Element Manager is informed of the potential to generate the waste. This element
of the life-cycle planning required under DOE M 435.1-1 is considered very important. No path
forward waste issues and problems may be complicated and should be dealt with early in the life
cycle of the waste to prevent situations that could require expenditure of large amounts of
resources to reverse erroneous steps taken in the managing of the waste.
Example 1: The life-cycle planning process at Facility 300 includes a semi-annual
submittal by individual generators to the waste certification official of known or
suspected new waste streams (i.e, waste streams not already approved for disposal at
Site Q). The waste certification official’s duties include an analysis of these waste
streams to decide if they have a path to disposal. In one such exercise, a suspected waste
stream is determined as not acceptable at disposal Site Q. The waste certification
official submits this information as required in his procedures to the DOE Field Office,
Assistant Manager for Waste Management.
Example 2: Site R has signed a Record of Decision requiring remediation of a seepage
basin by excavation and re-disposal of the contaminated soils. Contaminants include
heavy metals, organics, and radionuclides. Because the waste that will be generated
from this remedial action is a mixed low-level waste, there may be no path forward for
disposal. Therefore, Site R will prepare an analysis for consideration by the Site
Manager, regulators, and other stakeholders identifying the need to generate the waste
(the relevant compliance agreement/Record of Decision), the characteristics of the waste
to be generated (radioactive and hazardous constituents), the plans for storing the waste
after generation (a RCRA-compliant mixed low-level waste storage facility), and the
plans for identifying a disposal option for the waste.
The identification process should occur early enough before the waste is generated so that
alternatives to generating the no path forward waste can be examined as an option. Also,
Chapter I - General Requirements and Responsibilities
I-182 DOE G 435.1-1
7-09-99
Section 143
notification of Headquarters (see guidance below on Notification to Headquarters) prior to waste
generation appropriately involves Headquarters managers into the final decisions for generation
and management of waste with no path to disposal. More detailed guidance for life-cycle
planning for generation of new waste streams is included in guidance for life-cycle planning
requirements in each of the waste type chapters (Sections II.K.(1), III.H.(1), and IV.H.(1)).
The determination of whether a waste stream has an identified path to disposal should be based on
the availability of existing or planned facilities and operations and on the technical acceptability of
the waste at the facility. A planned facility is considered to be available if it has been authorized
(e.g., a line item in a Congressional appropriation or equivalent approval for design and
construction). For purposes of planning for treatment and/or disposal of waste, a facility or
capability that is part of a program or strategic plan, but has not been authorized, should not be
considered available. A facility is also not considered available if it is not authorized to accept or
manage a particular waste type or concentration. If an available planned facility used in life-cycle
planning is canceled, the generator should revise the planning for the life-cycle of the waste and an
alternate path to disposal should be identified and documented. If an alternate path to disposal is
not available, then approval to continue to generate the waste should be obtained in accordance
with this requirement, even though it had not needed approval when the waste was initially
generated.
Example: Several no path forward waste streams generated throughout the Complex are
approved because of a planned new High-Activity Borehole Disposal Facility which has
received initial line item funding. In the FY2003 budget, Congress does not approve
further funding of the facility. The approval to continue to generate these wastes is re
examined by several Field Offices in light of this development.
Whether a path to disposal can be identified should also be based on the acceptability of the waste
at the facilities at which it must be managed. For existing facilities, this involves no more than an
evaluation of the waste stream properties against the waste acceptance requirements of the facility
and determining there are no impediments for its management. For planned facilities, this
determination is more involved. For some waste streams, the acceptability at a planned facility
could be determined based on similar circumstances already known to exist in the Complex. This
may be a common situation for wastes that do not have a full path to disposal because of issues
that are not entirely technical (e.g., non-defense transuranic waste without a disposal option). For
other waste streams, particular those with a technical impediment to disposal, the acceptability
may need to be evaluated and a judgement made that a planned facility will be able to accept the
waste provided some necessary treatment is performed (e.g., waste with explosive properties is
made non-explosive), or some administrative step is successfully accomplished (e.g., a RCRA
permit is obtained so that mixed waste can be accepted).
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-183
7-09-99
Section 144
Example: A new project will generate 2 waste streams for which a path to disposal is
unclear. One waste stream is a typical dry active transuranic waste stream, but it is non-
defense transuranic waste, therefore, planned storage at Storage Facility B followed by
disposal at the new borehole disposal facility under construction is evaluated. The waste
stream is determined to be acceptable at both facilities through a comparison to the
waste acceptance criteria for the two facilities. The second waste stream is a unique
mixed low-level waste stream that can be stored at Facility B, but for which a disposal
facility has not yet been determined. The acceptability of the waste is evaluated by
comparing it to a similar waste stream in the Site Treatment Plan (STP), and determining
that the treatment described in the STP will also work for the new waste stream.
Conditions for Review and Approval. The second part of the requirement calls for the Field
Element Manager to be involved in the decision to generate waste without a path to disposal,
prior to the generation of the waste. This requirement intends to ensure that wastes are generated
with no identified path to disposal only under approved conditions and known circumstances and
are considered to be acceptable by both the Field Managers and Headquarters. The waste type
chapters contain requirements that these conditions for generating a no path to disposal waste
stream must meet.
The review and approval of the generation of waste without a path to disposal is the responsibility
of the Field Element Manager. The approval process and approved waste streams should be
documented. In some cases, the Field Element Manager may approve the conditions under which
an individual waste stream is generated, while in other cases, he/she may approve a process that
confirms the conditions are being met, perhaps through the certification program. The latter
circumstances may be appropriate for the routine generation of waste streams having no path
forward to disposal.
Example 1: A large scale facility dismantlement is about to begin. Life-cycle planning
evaluations indicate that several large components that will be removed from the facility
cannot meet the current acceptance criteria for disposal at WIPP or at any other disposal
facility. The Field Element Manager is directly involved in exploring alternatives to the
generation of this waste, and if appropriate, approving the decision to proceed with the
dismantlement and the plans for long-term storage for the components.
Example 2: A laboratory facility on Site B routinely generates small amounts of several
mixed low-level waste streams. Prior approval to generate two of the waste streams was
necessary in accordance with the guidelines discussed here. DOE Field staff has
approved a process that includes conditions and decision criteria being implemented at
the laboratory as part of its waste certification program. The process allows laboratory
personnel to approve generation of additional mixed low-level waste streams.
Chapter I - General Requirements and Responsibilities
I-184 DOE G 435.1-1
7-09-99
The conditions for generating a waste without an identified path to disposal should include
evaluations and considerations that involve both the waste generating and waste management
organizations. Guidance on Sections II.K.(2), III.H.(2), and IV.H.(2) discusses the evaluations
that must be included in the conditions for generating a no path forward waste.
Section 145
For many newly generated waste streams identified as having no path to disposal, programmatic
or technical problems and issues contributing to the lack of a disposal path may be the same as
ones already experienced by other waste streams at the site, or within the Complex. All or part of
the solution towards disposing of problem waste stream may therefore be actions being taken or
planned as part of the Site-Wide Radioactive Waste Management Programs. Likewise, the issues
or problems may have also been elevated and are being addressed in the Complex-Wide Waste
Management Program for one of the waste types. The relationship of this General Requirement
to the requirements for the Radioactive Waste Management Programs is discussed at the end of
this guidance under Relationship to Site-Wide Radioactive Waste Management Programs.
Example: A new process at a DOE laboratory facility will result in the generation of
some non-defense transuranic waste. This is a programmatic and complex-wide issue
requiring resolution that is being addressed as a high priority item at Headquarters in
accordance with the FY 2000 Transuranic Waste Management Program Plan.
Information is prepared under the four topics (a) - (d) discussed above. The information
on plans in place to take care of the no path forward waste identifies the complex-wide
actions, and the actions being taken specifically at the site.
Notification of Headquarters. The third part of the requirement calls for the Field Element
Manager to inform DOE Headquarters of the decision to generate waste without a path to
disposal. As previously mentioned, only newly generated waste streams are subject to this
requirement. Notifications do not have to be made for wastes already generated at the time DOE
O 435.1 is issued. Documentation of approvals should be provided to the cognizant Program
Secretarial Officer (PSO) for the activity or program generating the waste, with an information
copy to the Assistant Secretary for Environmental Management (EM-1). The notification should
summarize the conditions for approval as described in the previous discussion, and should include
an expiration date for the approval or other conditions that would require a new approval of the
Field Manager. This notification should be accomplished in a timely fashion following the
identification of the potential generation of no path forward waste so that Headquarters
management is fully informed of the situation resulting in no path forward waste, and any
Headquarters management concerns can be appropriately considered and included in the final
Field Element Manager approval to generate the waste.
Example: A new waste generating process is developed that requires a waste treatment
process not currently available for the waste to be acceptable for disposal. The needed
waste treatment process has been approved, but the necessary hardware will not be
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-185
7-09-99
available for five years. The waste generating process is approved by the Field Element
Manager with the conditions that (a) the waste is stored in Storage Building 5, and (b)
satisfactory progress is made toward the installation of the additional waste treatment
process. The approval is documented, and sent to the PSO with an information copy to
EM-1.
Section 146
Relationship to Site-Wide Radioactive Waste Management Program. As previously discussed,
waste streams generated in the past with no path to disposal which are now in storage, and waste
streams without a path to disposal that are currently being generated are intended to be addressed
in the Site-Wide Radioactive Waste Management Programs required by DOE M 435.1-1, Section
I.2.F.(1) (and elevated to the waste type Complex-Wide Waste Management Program, if
appropriate). Waste streams being generated when DOE O 435.1 is issued should also be
evaluated for whether they should continue to be generated. This requirement for an
identification process, approved conditions, and Headquarters notification is intended to cover
newly generated waste streams only.
Since life-cycle planning should be a major element of the Site-Wide Radioactive Waste
Management Program implemented at each site, information on waste streams generated at the
subject site is expected to be documented as part of the program in accordance with the site’s
documentation protocol. It should be understood that the identification, approval, and
notification process called for in this requirement for waste streams not being generated is a
proactive part of the program, and as such, should be included in a site’s operating processes or
procedures.
However, once generation of a waste stream with no path forward is approved, then it should be
included in the site’s life-cycle planning program documentation so that complete waste stream
information is maintained in one place. Revisions of the Site-Wide Management Program
documents should contain appropriate actions to address new issues and problems of no path
forward waste incorporated into them especially from any waste streams not covered in prior
revisions of the documentation. Likewise, information already documented about past waste
streams with no path forward should be updated because of developments concerning new no
path forward wastes.
Example: Three new non-defense transuranic waste streams are approved and generated
at Facility 200 in FY1998. In the FY1999 Site Radioactive Waste Life-Cycle
Management Plan, these three waste streams are added to the list of previously
generated non-defense transuranic wastes that have been managed at the site for years.
The actions already documented in the current Life-Cycle Plan (FY1998) are evaluated
and considered appropriate to pursue for the new as well as previous waste streams.
This is documented, and progress on meeting the actions is updated in the FY1999 Plan.
Chapter I - General Requirements and Responsibilities
I-186 DOE G 435.1-1
7-09-99
Waste without a path to disposal which received approval in accordance with these requirements,
and which have become part of the Site-Wide Program planning information, should continue to
be observed with additional scrutiny. At a minimum, the approval to generate the wastes should
be considered annually, with the primary focus being an evaluation of the progress toward
identifying a path to disposal. Repeated or numerous one-time approvals for the generation of
waste streams without a path to disposal should not be acceptable. The Site-Wide Program
Documentation should be used as the vehicle for the evaluation and continued approval of no path
forward waste streams on an annual basis. The evaluation of waste streams with no path to
disposal should be consolidated with the annual evaluation discussed here.
Section 147
Example: For the example above, the actions referred to in the Life-Cycle Plan are
updated for the FY2000 Life-Cycle Plan for the site. Progress on meeting those actions
is evaluated by a task force established by the Field Element Manager, and it is
determined that progress is adequate. This decision is documented in the FY2000 Plan
as a renewal of the approval of these three non-defense transuranic waste streams.
Major changes to the planned management of waste without a path forward (e.g., changes for
developing the treatment facility or disposal facility to handle the waste) should also result in a re
evaluation and re-confirmation of the acceptability of continuing to generate no path forward
waste. Headquarters should be notified of changes of this magnitude. On the other hand, if the
assumptions for the planned management of approved no path forward waste are only slightly
impacted (e.g., as a result of testing, design, changes in funding, or DOE policy), the information
in the Site-Wide Program documentation should be updated. Slight changes to assumptions and
to the planned management of the waste should not necessarily be a basis for re-evaluating the
generation of the waste.
Example 1: For the three new non-defense transuranic wastes at Facility 200, the
FY2000 Life-Cycle Plan, minor changes in the actions between the FY1999 and FY2000
Life-Cycle Plans are explained in the text of the plan. These minor items include a
decision to add a peer review of one study, and a delay in the scheduled completion dates
for three actions. The text states that the approvals for continuing generation of the non-
defense transuranic wastes were not evaluated because these were deemed minor items.
Example 2: Continuing example 1 above, after the FY2000 Life-Cycle Plan is issued, the
peer review convened on the study finds some of the conclusions in the study to be
invalid. This finding has a significant impact on whether the technology selected for
solidification of the non-defense transuranic waste can still be a cornerstone of the plan
for the site’s no path forward waste. This is considered a major item concerning the
continuing generation of the non-defense transuranic wastes. The continuing approvals
were re-evaluated because of this item, and only two are re-approved. The FY2001
Life-Cycle Plan incorporates these new facts into its updated text.
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-187
7-09-99
Compliance with this requirement is achieved if the life-cycle planning implemented at generator
sites includes a documented process for identifying waste streams which may be generated that
will not have an identified path to disposal; if a documented process is included for review and
approval of the conditions for generation of the waste; if approved conditions are documented for
any new no path forward waste streams being generated; if the approvals of generation of no path
forward waste is appropriately considered in the Site-Wide Radioactive Waste Management
Program documentation; and if Headquarters is being notified of the approval of and conditions
under which new no path forward waste can be generated.
Supplemental References: None.
Chapter I - General Requirements and Responsibilities
I-188 DOE G 435.1-1
7-09-99
I. 2.F. Field Element Managers.
Field Element Managers are responsible for:
Section 148
(20) Corrective Actions. Ensuring a process exists for proposing, reviewing,
approving, and implementing corrective actions when necessary to ensure
that the requirements of DOE O 435.1, Radioactive Waste Management, and
this Manual are met, and to address conditions that are not protective of the
public, workers, or the environment. The process shall allow workers,
through the appropriate level of management, to stop or curtail work when
they discover conditions that pose an imminent danger or other serious
hazard to workers or the public, or are not protective of the environment.
Objective:
The objective of this requirement is to ensure that processes to identify, manage, and resolve
radioactive waste management deficiencies in complying with DOE O 435.1 and address
conditions that are not protective of the public, workers or the environment are established and
implemented.
Discussion:
Corrective actions taken prior to events occurring that pose a threat to the workers, the public, or
the environment can avert serious occurrences. Actions may include improvements to
documentation (e.g., procedures, plans, authorization basis documents), training and qualification
programs or procedures, or physical and process design changes. Corrective actions routinely
occur as part of the implementation of DOE O 232.1A, Occurrence Reporting and Processing of
Operations Information (ORPS). The requirement to implement a corrective actions process in
managing radioactive waste includes those ORPS Corrective actions as well as corrective actions
initiated by circumstances that do not rise to the threshold of reportable incidents.
Potential problems range from minor ones to those which pose an immediate threat to safety and
health. Additional information on problem identification can be found in Section I.2.G.(1),
Problem Identification. For situations where a problem could pose an immediate risk to a worker,
member of the public, or damage to the environment, the immediate corrective action of shutting
an operation down may be appropriate until the threat can be controlled. Guidance on shutting
down or curtailing radioactive waste activities is provided in Section I.2.G.(2), Shutdown or
Curtailment of Activities.
The corrective action process includes problem identification and tracking through resolution;
proposal, review, and implementation of solutions, and a method for approval and assigning
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-189
7-09-99
accountability. Provisions need to be made for interfaces with the lessons learned program when
others could benefit from an action taken. In the corrective actions process, review and approval
by cognizant managers is necessary to assess the effectiveness of the corrective action in
eliminating the problem and preventing recurrence, its practicality, cost effectiveness, and
timeliness. Additional information on corrective action processes may be found in DOE O
232.1A, DOE-HDBK-1089-95 Guidance for Identifying, Reporting and Tracking Nuclear Safety
Noncompliances, and DOE G 452.2A-1A Implementation Guide for DOE Order 452.2A, Safety
of Nuclear Explosive Operations. These guides are specific to the topics for which they are
written, but may have generic applications adaptable for use by radioactive waste management
personnel.
Section 149
Example: At the recommendation of the Defense Nuclear Facilities Safety Board, the
department performed a Complex-Wide Review of DOE’s Low-Level Waste Management
ES&H Vulnerabilities. Site personnel performed a self evaluation followed by an
assessment team visit. Based on the problems identified, Corrective Action Plans (CAPs)
were prepared to address both complex-wide and site specific corrective actions. These
CAPs identify and allow tracking of actions necessary to address the identified problems,
including their time lines, milestones and relative resource impacts. The staff
responsible to ensure that the corrective actions are completed are also identified. The
CAPs were reviewed and approved by senior DOE managers.
Compliance with this requirement is demonstrated by a site corrective actions program that
addresses radioactive waste management-related occurrence reporting and processing of
operations information reports citing corrective actions taken, and by records of changes to
procedures or processes reflecting that changes were made to correct a problem.
Supplemental References:
1. DOE, 1997. Occurrence Reporting and Processing of Operations Information, DOE O
232.1A, U.S. Department of Energy, Washington, D.C., July 21, 1997.
2. DOE, 1995. Guidance for Identifying, Reporting and Tracking Nuclear Safety
Noncompliances, DOE-HDBK-1089-95, U.S. Department of Energy, Washington, D.C.,
December 1995.
3. DOE, 1997. Implementation Guide for DOE Order 452.2A, Safety of Nuclear Explosive
Operations, DOE G 452.2A-1A, U.S. Department of Energy, Washington, D.C.,
January 17, 1997.
Chapter I - General Requirements and Responsibilities
I-190 DOE G 435.1-1
7-09-99
I. 2.G. All Personnel.
All personnel are responsible for:
(1) Problem Identification. Identifying and reporting radioactive waste
management facilities, operations, or activities that do not meet the
requirements of DOE O 435.1, Radioactive Waste Management, and this
Manual, or pose a threat to the safety of the public, workers, or the
environment.
Objective:
The objective of this requirement is to clearly state the responsibility and right of each individual
to identify and report unsafe conditions so that action can be taken to ensure protection of
workers, the public, and the environment.
Discussion:
During the development of DOE M 435.1-1, it was recognized that achievement of safe working
practices and conditions could be realized only if all personnel are involved and constantly critical
of activities and operations. Comprehensive worker protection programs should already exist in
compliance with DOE O 440.1A Worker Protection Management For DOE Federal And
Contractor Employees. Detailed guidance is available in the multiple guides associated with that
Order. This requirement is included in DOE M 435.1-1 to reinforce that accomplishing work
safely is critical.
Safe and environmentally sound operations are not, and cannot be, solely the responsibility of
management or safety professionals. Coordinated and integrated efforts and constant vigilance
are required. Every individual must act in the role of a safety observer. Managers are typically
accountable for the overall worker protection program, including planning and allocating
resources. Supervisors are accountable for ensuring that worker protection plans, programs, and
procedures, including hazard identification and abatement activities, are implemented on a day-to
day basis at the front line. Employee/worker accountability involves following procedures, using
safe work practices, and reporting hazards. Formal roles may vary, but everyone has the role of
identifying and reporting threats to safety.
Section 150
Example 1: A subcontractor at a DOE site is performing roofing repairs in an explosives
processing area which is a non-smoking area. The subcontractor, however, has
permission to have an open flame on the roof because the work involves tar and a
hazards analysis indicated that there was no threat from the flame at that location. The
subcontractor and crew receive the standard safety briefing upon being awarded the
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-191
7-09-99
contract, including an explanation of the rules regulating smoking in the restricted area,
i.e. smoking is authorized only in designated areas. As a DOE employee is walking in
the area, the roofer’s crew is leaving to go to lunch. The employee observes that a
laborer is smoking a cigarette in the bed of the truck. He immediately calls the security
post to have the truck stopped and security personnel inform safety and contract
management personnel to take appropriate action.
Example 2: The approved radioactive waste management basis for a storage facility
requires low level waste to be stored on concrete pads with suitable leak detection and
spill control. The facility manager has allowed two slightly corroded drums of low level
waste to be stored temporarily in a grassy area beside the pad due to a lack of storage
space on the pad. A DOE employee familiar with the radioactive waste management
basis notices the drums on the grass, and notifies his supervisor, who contacts the facility
manager about the situation. The facility manager immediately rectifies the situation by
transferring the waste to an acceptable storage pas at another facility.
Compliance with this requirement is demonstrated by records showing what corrective actions
were taken to remedy situations in the radioactive waste management system.
Supplemental References:
1. DOE, 1998. Worker Protection Management for DOE Federal and Contractor
Employees, DOE O 440.1A, U.S. Department of Energy, Washington, D.C., March 27,
1998.
2. DOE, 1997. Worker Protection Management for DOE Federal and Contractor
Employees Guide for Use with DOE Order 440.1A, DOE G 440.1-1, U.S. Department of
Energy, Washington, D.C., July 10, 1997. (This guide has applicable standards and
guidance documents listed at the end of each chapter.)
I.2.G(2) Shutdown or Curtailment of Activities. Stopping or curtailing work,
through the appropriate level of management, to prohibit
continuation of conditions or activities which pose an imminent
danger or other serious hazard to workers or the public, or are not
protective of the environment.
Chapter I - General Requirements and Responsibilities
I-192 DOE G 435.1-1
7-09-99
Objective:
The objective of this requirement is to ensure that the operation of radioactive waste management
facilities or the performance of radioactive waste management activities is discontinued or
controls put in place if it poses an imminent danger or serious hazard to the public, workers, or
the environment.
Discussion:
Section 151
The shutdown and curtailment of activities requirement complements DOE M 435.1-1,
Section I.2.G.(1), Problem Identification, and requires that the Field Element Manager has a
system in place to ensure that corrective actions are initiated when necessary. The need for
corrective actions has long been recognized in the management of radioactive waste. However,
the responsibility for individual actions was not clearly assigned. Stop work procedures, which
are not specific to radioactive waste management, are anticipated to be already in place and
workers need to be trained to those procedures. DOE O 440.1A requires that DOE elements and
contractors implement procedures to allow workers, through their supervisors, to stop work
when they discover employee exposures to imminent danger or other serious hazards. A worker
has the right to decline to perform an assigned task because of a reasonable belief that, under the
circumstances, the task poses an imminent risk of death or serious bodily harm to that individual,
coupled with a reasonable belief that there is insufficient time to seek effective redress through the
normal hazard reporting and abatement procedures.
Accomplishing work safely is an important DOE goal. When a situation with an imminent danger
is discovered, immediate action must be taken either to correct the dangerous condition or
practice, or to remove all employees from exposure to the dangerous condition until the condition
or practice has been removed. Imminent danger means a situation that could reasonably be
expected to cause death or serious physical harm unless immediate actions are taken. This
requirement to shut down or curtail activities is included in DOE M 435.1-1 to complement
DOE O 440.1A by broadening its application to include threats to the public and environment,
and to emphasize that it applies in radioactive waste management.
Any stop work authority must be exercised in a justifiable and responsible manner. All workers,
supervisors, managers, and safety professionals are responsible for being cognizant of the
conditions in their workplaces and for being prepared to stop work if conditions pose a serious
threat to health or safety, or a detriment to the environment. Hazards analyses and hazard
prevention/abatement processes result in routine hazards being controlled. This requirement is
intended to address extraordinary or unanticipated circumstances and situations where there is a
breakdown in controls. When a reasonable person views the circumstances as having the
potential to cause injury, serious impairment, harmful health effects, or serious damage to the
environment, a stop work order is to be issued. However, the full implications of what will occur
Chapter I - General Requirements and Responsibilities
DOE G 435.1-1 I-193 (and I-194)
7-09-99
must be recognized. Any work stoppage must alleviate the hazard without creating unintended
consequences that are worse than the hazard. Whenever workers see a need to stop work, they
are to advise their supervisors. Before a stop work order is issued, the person issuing it needs to
ensure the work stoppage itself will not negatively impact workers or public health and safety or
the environment.
Section 152
Example: At a site, radioactive waste is stored in an approved storage facility in drums.
These drums are in groups of four on wooden pallets and are strapped together for
stability. In order to remove them for transfer to a treatment facility, the pallets are
lifted by forklifts and placed in trucks. In the course of moving a pallet from the third
tier, an adjacent pallet load becomes unstable. Any further movement would cause it to
fall on support workers who are inventorying and processing the drums for the transfer.
The supervisor recognizes that the pallet load is an imminent threat to those support
workers with the potential to cause serious physical harm. The supervisor immediately
suspends work in the immediate area, clearing all personnel until a second forklift can be
made available to stabilize the threatening pallet load. In accordance with site
procedures, appropriate occurrence reporting and processing system (ORPS) reports are
made.
Compliance with this requirement is demonstrated by having the necessary procedures,
mechanisms, and training in place to effect shutdown or curtailment of activities which pose an
imminent danger or other serious hazard to workers or the public, or are not protective of the
environment.
Supplemental References:
1. DOE, 1998. Worker Protection Management for DOE Federal and Contractor
Employees, DOE O 440.1A, U.S. Department of Energy, Washington, D.C., March 27,
1998.
2. DOE, 1997. Worker Protection Management for DOE Federal and Contractor
Employees Guide for Use with DOE Order 440.1A, DOE G 440.1-1, U.S. Department of
Energy, Washington, D.C., July 10, 1997. (This guide has additional topic specific
standards and guidance documents listed at the end of each chapter.)
Chapter I - General Requirements and Responsibilities
IMPLEMENTATION
GUIDE
for use with DOE M 435.1-1
Chapter II
High-Level Waste Requirements
(This page intentionally left blank.)
II-1 DOE G 435.1-1
7-09-99
II. A. Definition of High-Level Waste.
High-level waste is the highly radioactive waste material resulting from the
reprocessing of spent nuclear fuel, including liquid waste produced directly in
reprocessing and any solid material derived from such liquid waste that contains
fission products in sufficient concentrations; and other highly radioactive material
that is determined, consistent with existing law, to require permanent isolation.
Objective:
The objective of this requirement is to provide the criteria for determining which DOE radioactive
wastes are to be managed as high-level waste, and therefore, in accordance with DOE M 435.1-1,
Chapter II, High-Level Waste Requirements, and Chapter I, General Requirements and
Responsibilities.
Discussion:
As required in DOE M 435.1-1, Section I.1.C., Radioactive Waste Management, all radioactive
wastes subject to DOE O 435.1 shall be managed as either high-level waste, transuranic waste,
low-level waste, or mixed low-level waste. To assist in determining whether a particular waste
stream is high-level waste, another waste type, or not addressed by DOE O 435.1 and DOE M
435.1-1, see the guidance that accompanies the requirement at Section I.1.C. For those waste
streams that meet the definition of high-level waste cited above, the requirements of Chapter II of
DOE M 435.1-1 shall be met.
This definition is consistent with the definition provided in the Nuclear Waste Policy Act of 1982
(NWPA), as amended. It is slightly modified from the Nuclear Waste Policy Act of 1982, as
amended, definition and, as discussed below, allows DOE to make a determination of what is
high-level waste based on existing law.
Section 153
The identification of high-level waste is considered relatively straightforward since it is primarily
linked to the source from which it was derived, i.e., it is the highly radioactive material resulting
from the reprocessing of spent nuclear fuel. However, the definition does imply a concentration
limit by including solid material derived from liquid waste that contains fission products in
sufficient concentrations. Background and knowledge of both the Nuclear Waste Policy Act of
1982, as amended, definition and the Nuclear Regulatory Commission definition, at 10 CFR Part
60, is needed to ensure that waste that is to be managed as high-level waste has been properly
characterized to be high-level waste. High-level waste must be managed in accordance with
Chapter II of DOE M 435.1-1.
Chapter II -High-Level Waste Requirements
II-2 DOE G 435.1-1
7-09-99
Background. The following discussion is provided in terms of the Nuclear Waste Policy Act of
1982, as amended, definition but is fully applicable to the definition at Section II.A of DOE M
435.1-1. The Nuclear Waste Policy Act of 1982, as amended, provides for the disposal of high-
level radioactive waste and establishes a program of research, development, and demonstration
regarding the disposal of high-level radioactive waste. In the Nuclear Waste Policy Act of 1982,
as amended, the term high-level radioactive waste is defined as:
“(a) the highly radioactive material resulting from the reprocessing of spent nuclear fuel,
including liquid waste produced directly in reprocessing and any solid material derived
from such liquid waste that contains fission products in sufficient concentrations; and (b)
other highly radioactive material that the Commission, consistent with existing law,
determines by rule requires permanent isolation.”
Thus the Nuclear Waste Policy Act of 1982, as amended definition for high-level waste provides
for the inclusion of both source-based material and concentration-based material as high-level
waste.
Note that the Nuclear Waste Policy Act of 1982, as amended, does not mandate that materials
regarded as high-level waste pursuant to this definition be disposed of in a geologic repository.
Indeed, the Nuclear Waste Policy Act of 1982, as amended, directs the Secretary of Energy to
continue and accelerate a program of research, development, and investigation of alternative
means and technologies for the permanent disposal of high-level waste. DOE has not been
specifically authorized by Congress to construct or operate facilities for disposal by alternative
means, and it is not clear whether additional authorization might be needed in order to dispose of
high-level waste by means other than emplacement in a deep geologic repository (52 FR 5994).
Also note that the Nuclear Waste Policy Act of 1982, as amended, definition and the definition
for high-level waste in DOE’s predecessor directive for radioactive waste management, DOE
5820.2A, are fundamentally the same. However, there is one exception. The Nuclear Waste
Policy Act of 1982, as amended, provides for an additional mechanism for determining a waste is
high-level waste. This mechanism is to allow the Nuclear Regulatory Commission (NRC) to
determine, by rule, that a waste requires permanent isolation. The wording in Section II.A is
slightly different than the Nuclear Waste Policy Act of 1982, as amended, to allow DOE to make
a determination based upon existing law in Sections 202(3) and 202(4) of the Energy
Reorganization Act of 1974.
Section 154
The NRC has posited that, “radioactive wastes that have historically been referred to as high-level
waste, i.e., reprocessing wastes, are initially both intensely radioactive and long-lived” (52 FR
5994). However, these wastes contain a wide variety of radionuclides with some (e.g., Sr-90, Cs
137) having a relatively short half-life yet representing a large fraction of the radioactivity for the
first few centuries after the wastes are produced. These nuclides produce significant amounts of
Chapter II -High-Level Waste Requirements
II-3 DOE G 435.1-1
7-09-99
heat and radiation, both of which are of concern when managing such wastes. Other
radionuclides, including C-14, Tc-99, I-129 and transuranic nuclides, have very long half-lives and
thus constitute the longer-term hazard of the wastes. Some of these nuclides pose a hazard for
sufficiently long periods of time that the term permanent isolation is used in the Nuclear Waste
Policy Act of 1982, as amended, to describe the type of disposal required to isolate them from the
environment. Permanent isolation does not, however, equate to repository disposal, and can be
conceivably attained by other means which comply with the requirements of 40 CFR Part 191.
The Nuclear Regulatory Commission “considers that these two characteristics, intense
radioactivity for a few centuries followed by a long-term hazard requiring permanent isolation, are
key features which can be used to distinguish high-level wastes from other waste categories” (52
FR 5994).
The Nuclear Waste Policy Act of 1982, as amended, identifies two sources of high-level waste.
First, the Nuclear Waste Policy Act of 1982, as amended, definition of high-level waste refers to
wastes produced by reprocessing spent nuclear fuel, which is essentially identical to the NRC’s
definition at 10 CFR Part 60 [(1) Irradiated reactor fuel, (2) liquid wastes resulting from the
operation of the first cycle solvent extraction system, or equivalent, and the concentrated wastes
from subsequent extraction cycles, or equivalent, in a facility for reprocessing irradiated reactor
fuel, and (3) solids into which such liquid wastes have been converted]. However, there is one
difference. The Nuclear Waste Policy Act of 1982, as amended, wording would classify
solidified reprocessing waste as high-level waste only if such waste “contains fission products in
sufficient concentrations.” This phrase implies that liquid reprocessing waste may be partitioned
or otherwise treated so that some of the solidified products will contain substantially reduced
concentrations of radionuclides and thus not be high-level waste, i.e., incidental waste. Second,
the Nuclear Waste Policy Act of 1982, as amended, authorizes the NRC to classify “other highly
radioactive material” (other than reprocessing wastes) as high-level waste if that material
“requires permanent isolation.” Both of these elements of the Nuclear Waste Policy Act of 1982,
as amended, definition are discussed further below by providing summaries of the Nuclear
Regulatory Commission’s attempt to revise the 10 CFR Part 60 definition of high-level waste.
Section 155
In February 1987, the NRC published an Advanced Notice of Proposed Rulemaking, (52 FR
5992) announcing its intent to revise the definition of the term high-level radioactive waste that
appears in 10 CFR Part 60, “Disposal of High-Level Radioactive Wastes in Geologic
Repositories.” In the Advanced Notice of Proposed Rulemaking, the Commission reviewed the
previous statutory and regulatory uses of the term, the NRC’s current regulations related to waste
classification and disposal, and the pertinent provision of the Nuclear Waste Policy Act of 1982,
as amended, with the purpose of considering a change to its own rules to conform to the Nuclear
Waste Policy Act of 1982, as amended, definition. In particular, the NRC proposed to define
high-level waste in a manner that would apply the term high-level radioactive waste to materials in
amounts and concentrations exceeding numerical values that would be stated explicitly in the form
of a table. Thus, high-level waste would be characterized by the kind of hazard that could only be
Chapter II -High-Level Waste Requirements
II-4 DOE G 435.1-1
7-09-99
guarded against by disposal in a geologic repository or equivalent facility. Those wastes that
could be disposed of safely in a facility less secure than a repository would continue to be
classified as low-level radioactive waste rather than as high-level waste.
At issue was whether the Commission should specify numerically the concentrations of fission
products which it considered sufficient to distinguish high-level waste from non-high-level waste
or, define high-level waste so as to add the Nuclear Waste Policy Act of 1982, as amended,
(clause (a)) wastes with those which have traditionally been regarded as high-level waste (52 FR
5994), i.e. by the waste’s source. In addition, the Commission raised the issue as to whether to
consider a material highly radioactive if it contains concentrations of short-lived radionuclides in
excess of the Class C limits of Table 2 of 10 CFR Part 61. The Commission stated that such
concentrations are sufficient to produce significant radiation levels and to generate substantial
amounts of heat and should be considered highly radioactive. Finally, the phrase permanent
isolation was discussed and was believed to be much less subjective than is the term highly
radioactive. The Commission suggested that the term clearly implies the degree of isolation
afforded by a deep geologic repository, and a waste “requires permanent isolation” if it cannot be
safely disposed of in a facility that is less secure than a repository. Furthermore, the Advanced
Notice of Proposed Rulemaking (52 FR 5995) states that the Commission could determine which
wastes require permanent isolation by evaluating the disposal capabilities of alternative, less
secure, disposal facilities. The Commission noted that such less secure facilities might make use
of intermediate depth burial or various engineering measures, such as intruder barriers, to
accommodate wastes with radionuclide concentrations unsuitable for disposal by shallow land
burial. The Commission suggested that any such wastes which cannot be safely disposed of in
such facilities could be deemed to require permanent isolation and, if also highly radioactive,
could be classified as high-level wastes (52 FR 5995).
Section 156
In May 1988 (53 FR 17709-17711), the NRC published its Proposed Rule at 10 CFR Part 61,
“Licensing Requirements for Land Disposal of Radioactive Waste,” and stated that the proposed
amendments to this Rule obviated “the need for altering existing classifications of radioactive
wastes as high-level or low-level.” In short, the NRC received nearly 100 comments on its
February 1987 Advanced Notice of Proposed Rulemaking and almost all agreed with the
Commission on one point: the use of the term high-level radioactive waste as used in the clause
(b) of the Nuclear Waste Policy Act of 1982, as amended definition, serves to identify those
wastes which require the degree of isolation afforded by a deep geologic repository. However,
comments differed widely regarding the specific wastes perceived to require that degree of
isolation. Some comments advocated classification of all radioactive wastes, other than the most
innocuous, as high-level waste while other comments preferred to reclassify, as low-level waste,
large quantities of defense reprocessing waste long regarded as high-level waste. Conspicuously
absent from the comments was any consensus regarding the means to be used by the Commission
to distinguish high-level waste from non-high-level waste. For example, the concept of a
numerical definition of high-level waste was criticized as an invitation to dilute or fractionate
Chapter II -High-Level Waste Requirements
II-5 DOE G 435.1-1
7-09-99
wastes solely to alter their classification. From this discussion the Commission determined it
would be best to proceed quite differently from its objective suggestion as set forth in the
Advanced Notice of Proposed Rulemaking; i.e., the NRC abandoned their attempt to provide a
risk-based definition for high-level waste. Instead, the Commission continued to embrace the
definition at 10 CFR Part 60. In summary, the Commission stated that the preferable construction
of the statute was to conform to the traditional definition, i.e., to define high-level waste by its
source, not by its concentrations of fission products, and thus equate Nuclear Waste Policy Act of
1982, as amended, wastes with those wastes which have traditionally been regarded as high-level
waste under Appendix F of 10 CFR Part 50 and the Energy Reorganization Act of 1974 (ERA).
The NRC stated that “NWPA (clause (a)) wastes have little significance for purposes of the
NWPA since the Federal Government was already responsible for the disposal of all reprocessing
waste at the time the statute was passed.” Thus “materials that are high-level waste for purposes
of licensing-jurisdiction provisions of the ERA will also be regarded as high-level waste under the
NWPA. This would include the primary reprocessing waste streams at DOE facilities, though not
the incidental wastes produced in reprocessing” (53 FR 17709).
Section 157
Discussion. The above background information is intended to provide some background for the
following discussion on determining what waste streams are, and are not, high-level waste. First,
it is noted that the term reprocessing is not defined statutorily. However, reprocessing is
considered by the Department to be those actions necessary to separate fissile elements (U-235,
Pu-239, U-233, and Pu-241) and/or transuranium elements (e.g., Np, Pu, Am, Cm, Bk) from
other materials (e.g., fission products, activated metals, cladding) contained in spent nuclear fuel
for the purposes of recovering desired materials. Second, as discussed above, the concentration
of fission products is not the primary consideration when making determinations using clause (a)
of the Nuclear Waste Policy Act of 1982, as amended. The source of the waste is the primary
parameter for making high-level waste determinations, not the activity or concentration of fission
products. However, inclusion of solid wastes derived from the waste of spent nuclear fuel
reprocessing activities is also a consideration if the concentration of fission products is sufficient.
Third, it is recognized that the NRC’s definition of high-level waste at 10 CFR 60.2, (which is
consistent with the definition of high-level radioactive waste in 10 CFR Part 50, Appendix F),
limits high-level waste to wastes that are the result of spent nuclear fuel reprocessing, beginning
with the separation/first cycle solvent extraction step, or equivalent. Specifically it states high-
level radioactive waste is:
“(1) irradiated reactor fuel, (2) liquid wastes resulting from the operation of the first cycle
solvent extraction system, or equivalent, and the concentrated wastes from subsequent
extraction cycles, or equivalent, in a facility for reprocessing irradiated reactor fuel, and
(3) solids into which such liquid wastes have been converted.” (10 CFR 60.2)
With regard to part (1) of this definition, it is noted that requirements for DOE-managed spent
nuclear fuel, as of the time of the preparation of this guidance, have not been added to DOE O
Chapter II -High-Level Waste Requirements
II-6 DOE G 435.1-1
7-09-99
435.1. Further, the hazards analysis performed to identify requirements for high-level waste did
not address the functions associated with management of spent nuclear fuel. Thus the
requirements contained in DOE M 435.1-1 do not apply to this DOE-managed spent nuclear fuel.
DOE M 435.1-1 supports the implementation of part (2) of the 10 CFR Part 60 definition to mean
that high-level wastes are wastes that are generated as a product of reprocessing of spent nuclear
fuel downstream of, and including, the first step in a separations process, and the consistent waste
streams from subsequent extraction cycles or steps. Separation processes include aqueous
separation processes, e.g., the Redox and the Purex processes, and nonaqueous processes, e.g.,
pyrometallurgical and pyrochemical processes. Wastes that are produced upstream of these
separations processes, from such processes as chemical or mechanical decladding, fuel
dissolution, cladding separations, conditioning, or accountability measuring, are not high-level
waste. Such wastes are considered processing wastes and should be managed in accordance with
the appropriate Chapters of DOE M 435.1-1, as either transuranic, mixed low-level, or low-level
waste. In addition, these wastes may be commingled with materials-in-process that require
further processing to separate desired materials from wastes. The following example is offered to
clarify this interpretation.
Section 158
Example: The spent nuclear fuel reprocessing operation at Site Z has been shut down for
some time. In the haste of shutting down the operation a number of material streams and
waste streams were left in the facility and are now being reviewed for disposition. The
following table describes some of the streams, designation of the stream as high-level
waste, or non-high-level waste, and the basis for the designation:
Stream Designation Basis
Fuel cladding hulls
(leached, partially leached,
and unleached)
Non-high-level
waste
Hulls are generated upstream of (before) the
first step of a separations process. They
should be characterized to determine proper
classification (e.g., LLW, MLLW, or TRU).
PUREX process first-cycle
raffinate stream, Pu
purification raffinate
stream
High-level waste Both waste streams are generated by the
first step, or subsequent steps, of a
separations/decontamination process.
Chapter II -High-Level Waste Requirements
II-7 DOE G 435.1-1
7-09-99
Stream Designation Basis
Contaminated
equipment/components:
a) Fuel Shear
b) Fuel Dissolver
c) First cycle solvent
extraction column
a) Non-high
level waste
b) Non-high
level waste
c) High-level
waste unless WIR
Evaluation
Process criteria
are met.
a) Waste contained/trapped in a fuel shear
was generated upstream of first step of
separations process. Fuel shear should be
characterized to determine proper
classification (e.g., LLW, MLLW or TRU).
b) Same as a).
c) Waste contained/trapped in column was
generated during first step of separations
process. May be managed as non-high-level
waste if column meets the Waste Incidental
to Reprocessing Evaluation Process criteria.
Electrometallurgical
treatment products:
a) Metal waste form
(includes uranium,
fission products, noble
metals)
b) Ceramic waste form
(includes fission
products, some actinides)
a) High-level
waste
b) High-level
waste
a) & b) Both waste streams are
generated by the first step, or subsequent
step, of a separation/decontamination
process.
As stated above, the Department recognizes that the Nuclear Waste Policy Act of 1982, as
amended, grants the NRC the authority, through the rulemaking process, to designate other highly
radioactive materials as high-level waste under existing law. For DOE, such existing law would
primarily be sections 202(3) and (4) of the Energy Reorganization Act of 1974.
Components and Equipment Contaminated with High-Level Waste. As discussed in detail in the
guidance to Section II.B, Waste Incidental to Reprocessing, components and equipment
contaminated with high-level waste are not considered high-level waste by the application of the
high-level waste definition in Section II.A, or the Nuclear Waste Policy Act of 1982, as amended,
definition, provided they meet the conditions of either the Waste Incidental to Reprocessing
Citation or Evaluation Process. In defining high-level waste both definitions use the term “highly
Chapter II -High-Level Waste Requirements
II-8 DOE G 435.1-1
7-09-99
Section 159
radioactive material” which is interpreted to mean waste material that is a result of reprocessing
spent nuclear fuel and any liquid waste or solid material derived from such liquid. There is no
precedence nor basis for including high-level waste-contaminated components and/or equipment
within the definition. In fact, the identification of items excluded from high-level waste by the
Atomic Energy Commission and subsequently by the Nuclear Regulatory Commission, includes
not only radioactive (fuel) hulls and other irradiated and contaminated fuel structural hardware
but also “ion exchange beds, sludges, and contaminated laboratory items, clothing, tools, and
equipment” (52 FR 5993). Thus, inclusion of these items as candidates for the incidental waste
process supports the DOE M 435.1-1 position that such contaminated items may not be high-level
waste. If they are not, they are subject to management and disposal as another waste type,
provided adequate protection is provided by their disposal as another waste type (e.g., low-level
waste or transuranic waste).
Spent Nuclear Fuel. Spent nuclear fuel is defined in the Nuclear Waste Policy Act of 1982, as
amended, as “fuel that has been withdrawn from a nuclear reactor following irradiation, the
constituent elements of which have not been separated by reprocessing.” Because this definition
was developed with commercially-generated spent nuclear fuel in mind, it fails to differentiate
between defense-related spent nuclear fuel (drivers) and target elements (materials irradiated to
produce defense nuclear materials). For the purposes of managing high-level waste under DOE
M 435.1-1, spent nuclear fuel includes spent driver elements and/or irradiated target elements that
contain transuranium elements. Excluded from spent nuclear fuel are target elements, that after
irradiation, contain no transuranium elements (e.g., those for the production of tritium) since such
spent target elements contain neither fissile material nor long-life transuranic isotopes that require
permanent isolation. Historically, such spent targets (reprocessed and unreprocessed) have been
assayed, treated, and disposed of as low-level waste (Final Environmental Impact Statement,
DOE/EIS-0271, Construction and Operation of a Tritium Extraction Facility at the Savannah
River Site, DOE 1999). DOE M 435.1-1 supports the continuation of this practice.
In April 1992, the Secretary of Energy approved a recommendation to phase out reprocessing of
spent nuclear fuel at DOE’s Savannah River Site and Idaho National Engineering Laboratory for
the purpose of recovering highly enriched uranium for the weapons program (Secretary of Energy
Decision Memo, dated April 28, 1992). In a similar action in December 1994 the Secretary of
Energy approved a recommendation to prohibit the use of plutonium-239 and highly enriched
uranium separated and/or stabilized during facility phaseout, shutdown, and cleanout activities for
nuclear explosive purposes (Memorandum for the Secretary, approved December 20, 1994).
From these actions it is evident that DOE no longer plans to reprocess spent nuclear fuel for the
purposes of recovering fissile materials and significant quantities of additional high-level waste
will not be generated in the future from these operations. However, it is recognized there may be
limited reprocessing at some of the high-level waste sites for spent nuclear fuel that is considered
“at risk materials.” Similarly, for cost effective reasons as well as others, most DOE high-level
waste sites continually add radioactive liquid wastes (e.g., cooling, water, decontamination
Section 160
Chapter II -High-Level Waste Requirements
II-9 DOE G 435.1-1
7-09-99
solutions) that may, or may not be, high-level waste to their high-level waste storage systems.
This practice effectively increases the volume of high-level waste to be managed, however, the net
amount is usually minor due to the evaporation capabilities at the sites. Such co-mingling of high-
level waste with other waste types should be performed considering the waste minimization
objectives of DOE M 435.1-1, Section I.1.E.(20), Waste Minimization and Pollution Prevention.
Disposition of Surplus Weapons-Usable Plutonium. The Department has the authority to emplace
surplus weapons-usable plutonium in immobilized high-level waste canisters and dispose of this
waste form in the geologic repository constructed under the Nuclear Waste Policy Act of 1982, as
amended, (NRC letter, C.J. Paperiello to L.H. Barrett, January 25, 1999). Thus this composite
waste form (plutonium can in a high-level waste canister) is considered high-level waste and
should be managed as such. Although the hazards analysis and requirements analysis prepared to
support the development of the high-level waste chapter of DOE M 435.1-1 did not consider the
inclusion of this waste form, its addition is not expected to change the requirements contained in
the chapter.
Non-Routine High-Level Waste. There is acknowledgment of a sub-category of high-level waste,
"non-routine high-level waste," that includes secondary radioactive solid wastes that meet the
source-based portion of the definition for high-level waste, but may not meet the current
immobilized high-level waste specification for a standard waste form, as defined by the DOE/EM
0093, Waste Acceptance Product Specifications for Vitrified High-Level Waste Forms (EM
WAPS). The current EM-WAPS document was written to allow acceptance of a standard waste
form, borosilicate glass canistered waste, but does recognize the production of “nonconforming
canistered high-level waste forms” from the high-level waste form producers. Examples are
expected to include immobilized waste that is suspected of being contaminated by foreign
materials and glass samples that were generated during production. Such waste forms may be
nonconforming and thus, may require review/acceptance by the DOE Office of Civilian
Radioactive Waste Management. If accepted, they will be a nonstandard waste form. Such
Office of Civilian Radioactive Waste Management acceptance is expected to include satisfying the
requirements in the EM-WAPS and approval of a treatment and disposition plan.
Example: At Site X, non-conforming high-level waste has been generated as a result of
high-level waste storage, pretreatment, and treatment activities. This waste includes:
• glass chipped from high-level waste glass melters,
• glass deposited on equipment
• spilled high-level waste glass that was not captured in a canister,
• glass samples/shards.
The Site is currently managing these wastes as nonconforming high-level wastes since
there are issues regarding contamination by foreign materials and the need to place
Chapter II -High-Level Waste Requirements
II-10 DOE G 435.1-1
7-09-99
these wastes in canisters. However, each canister is expected to meet the EM-WAPS
specifications and be accepted by the Office of Civilian Radioactive Waste Management
as non-standard canistered waste forms. If any do not meet the EM-WAPS
specifications, they will be managed as non-conforming and the Office of Civilian
Radioactive Waste Management acceptance, as nonstandard waste form, will be
necessary by way of an Office of Civilian Radioactive Waste Management-approved
action plan. The requirement for an action plan is included in the EM-WAPS,
specifications 4, Quality Assurance.
Section 161
The high-level waste scraps identified in the above example are considered non-routine high-level
waste forms. Currently both the Defense Waste Processing Facility at Savannah River and West
Valley Demonstration Project vitrification processes have produced small amounts of this material
and are storing it until a path forward can be determined.
Waste Incidental to Reprocessing. Those waste streams that meet the requirements of the waste
incidental to reprocessing processes, either by citation or by evaluation, are also excluded from
the scope of high-level waste. DOE M 435.1-1, Section II.B describes the process for making
such determinations and the accompanying guidance on this section provides further details on
this subject.
Interfaces Between the Office of Environmental Management and Office of Civilian Radioactive
Waste Management. The guidance for high-level waste disposal (DOE G 435.1-1, Section II.S)
provides information on the responsibilities and interfaces between the Offices of Environmental
Management and Civilian Radioactive Waste Management.
Supplemental References:
1. Nuclear Waste Policy Act of 1982, as amended, Public Law 97-425, Section 2.(12),
January 7, 1983.
2. Energy Reorganization Act of 1974, as amended, Public Law 93-438, Section 202 (3) and
(4).
3. AEC, 1969. “Siting of Commercial Fuel Reprocessing Plants and Related Waste
Management Facilities; Statement of Proposed Policy, 10 CFR Part 50, ‘Licensing of
Production and Utilization Facilities’,” Federal Register, Vol. 34, No. 8712, Atomic
Energy Commission, Washington, D.C., June 3, 1969.
4. AEC, 1970. “Siting of Commercial Fuel Reprocessing Plants and Related Waste
Management Facilities, 10 CFR Part 50, ‘Licensing of Production and Utilization
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-11
7-09-99
Facilities’,” Federal Register, Vol. 35, No. 17530-17533, Atomic Energy Commission,
Washington, D.C., November 14, 1970.
5. NRC, 1987. “Advanced Notice of Proposed Rulemaking; 10 CFR Part 60, ‘Definition of
High-Level Radioactive Waste,’” Federal Register, Vol. 52, No. 5992, U.S. Nuclear
Regulatory Commission, Washington, DC, February 27, 1987.
6. NRC, 1988. “Proposed Rule; 10 CFR Part 61, Disposal of Radioactive Wastes, U.S.
Nuclear Regulatory Commission, Washington, D.C., Federal Register, Vol. 53, No.
17709, May 18, 1988.
7. Claytor, 1992. R.A. Claytor, Assistant Secretary for Defense Programs, to The Secretary
of Energy, memorandum, A Decision on Phaseout of Reprocessing at the Savannah River
Site (SRS) and the Idaho National Engineering Laboratory (INEL), U.S. Department of
Energy, April 28, 1992.
8. Reis and Grumbly, 1994. V.H. Reis & T.P. Grumbly, Assistant Secretary for Defense
Programs and Assistance Secretary for Environmental Management, memorandum,
Action: Commitment to Prohibit the Use of Plutonium-239 and Highly Enriched
Uranium Separated and/or Stabilized During Facility Phaseout, Shutdown, and Cleanout
Activities for Nuclear Explosive Purposes, U.S. Department of Energy, December 20,
1994.
9. Atomic Energy Act of 1954, as amended, Public Law 83-703, Title II, Section 11, (dd),
August 30, 1954.
10. NRC. Disposal of High-Level Radioactive Wastes in Geologic Repositories, 10 CFR
Part 60, U.S. Nuclear Regulatory Commission, Washington, D.C.
11. Barrett, 1998. L.H. Barrett to C.J. Paperiello, letter, [no title], U.S. Department of
Energy, Washington, D.C., December 10, 1998.
Section 162
12. Paperiello, 1999. C.J. Paperiello to L.H. Barrett, letter, U.S. Department of Energy Plans
for Disposal of Surplus Weapons Plutonium, U.S. Nuclear Regulatory Commission,
Washington, D.C., January 25, 1999.
13. EPA. Environmental Radiation Protection Standards for Management and Disposal of
Spent Nuclear Fuel, High-Level Waste and Transuranic Radioactive Wastes, 40 CFR
Part 191, U.S. Environmental Protection Agency, Washington, D.C.
Chapter II -High-Level Waste Requirements
II-12 DOE G 435.1-1
7-09-99
14. DOE, 1996. Waste Acceptance Product Specifications for Vitrified High-Level Waste
Forms (EM-WAPS), Revision 2, DOE/EM-0093, U.S. Department of Energy,
Washington, D.C., December 16, 1996.
15. DOE, 1999. Construction and Operation of a Tritium Extraction Facility at the
Savannah River Site, Final Environmental Impact Statement, DOE/EIS-0271, U.S.
Department of Energy, Savannah River Operations Office, March 1999.
16. ERDA, 1977. Waste Management Operations, Savannah River Plant, Aiken, South
Carolina, Final Environmental Impact Statement, ERDA-1537, Energy Research and
Development Administration, Washington, D.C., September 1977.
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-13
7-09-99
II. B. Waste Incidental to Reprocessing.
Waste resulting from reprocessing spent nuclear fuel that is determined to be
incidental to reprocessing is not high-level waste, and shall be managed under
DOE’s regulatory authority in accordance with the requirements for transuranic
waste or low-level waste, as appropriate. When determining whether spent nuclear
fuel reprocessing plant wastes shall be managed as another waste type or as
high-level waste, either the citation or evaluation processes described below shall be
used:
(1) Citation. Waste incidental to reprocessing by citation includes spent nuclear
fuel reprocessing plant wastes that meet the description included in the
Notice of Proposed Rulemaking (34 FR 8712) for proposed Appendix D, 10
CFR Part 50, Paragraphs 6 and 7. These radioactive wastes are the result of
reprocessing plant operations, such as, but not limited to: contaminated job
wastes including laboratory items such as clothing, tools, and equipment.
(2) Evaluation. Determinations that any waste is incidental to reprocessing by
the evaluation process shall be developed under good record-keeping
practices, with an adequate quality assurance process, and shall be
documented to support the determinations. Such wastes may include, but
are not limited to, spent nuclear fuel reprocessing plant wastes that:
(a) Will be managed as low-level waste and meet the following criteria:
1. Have been processed, or will be processed, to remove key
radionuclides to the maximum extent that is technically and
economically practical; and
2. Will be managed to meet safety requirements comparable to
the performance objectives set out in 10 CFR Part 61, Subpart
C, Performance Objectives; and
3. Are to be managed, pursuant to DOE’s authority under the
Atomic Energy Act of 1954, as amended, and in accordance
with the provisions of Chapter IV of this Manual, provided the
waste will be incorporated in a solid physical form at a
concentration that does not exceed the applicable
concentration limits for Class C low-level waste as set out in 10
CFR 61.55, Waste Classification; or will meet alternative
Chapter II -High-Level Waste Requirements
II-14 DOE G 435.1-1
7-09-99
requirements for waste classification and characterization as
DOE may authorize.
Section 163
(b) Will be managed as transuranic waste and meet the following criteria:
1. Have been processed, or will be processed, to remove key
radionuclides to the maximum extent that is technically and
economically practical; and
2. Will be incorporated in a solid physical form and meet
alternative requirements for waste classification and
characteristics, as DOE may authorize; and
3. Are managed pursuant to DOE’s authority under the Atomic
Energy Act of 1954, as amended, in accordance with the
provisions of Chapter III of this Manual, as appropriate.
Objective:
The objective of this requirement is to ensure the implementation of a consistent and defensible
process to make waste incidental to reprocessing determinations across the DOE complex.
Implementation of the process will ensure DOE manages these waste streams within its regulatory
authority for disposal.
Discussion:
Certain waste streams produced during the generation of high-level waste may be determined to
be non-high-level waste through the waste incidental to reprocessing determination process. The
processes for making such determinations are included as requirements in DOE M 435.1-1,
Section II.B, and are described below. In conjunction with Section II.B is a requirement in
Section I.2.F.(18), Waste Incidental to Reprocessing, which delineates the responsibilities of the
Field Element Manager and the DOE Office of Environmental Management for making and
reviewing such waste incidental to reprocessing determinations. The information and analysis
necessary to support these determinations is included.
Background. In the Statement of Proposed Policy (34 FR 8712) for Appendix D, 10 CFR Part
50, “Policy Relating to the Siting of Fuel Reprocessing Plants and Related Waste Management
Facilities,” the Atomic Energy Commission (AEC) noted that the term high-level waste, as used in
the proposed Appendix D, did not include all wastes originating from (spent nuclear fuel)
reprocessing plant operations (Paragraphs 6 and 7). Such wastes, later referred to as incidental
wastes by the Nuclear Regulatory Commission (NRC) (52 FR 5993), included waste streams such
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-15
7-09-99
as ion exchange beds, sludges, and contaminated laboratory items, clothing, tools, and equipment.
Additionally, this category included radioactive hulls and other irradiated and contaminated fuel
structural hardware. Although this language (Paragraphs 6 and 7) concerning incidental waste
was deleted from the final Policy under Appendix F, pending additional study (35 FR 17530
17533), the principle of incidental wastes has been continually supported by both the Department
of Energy and the NRC , as well as their predecessors, even before the Proposed Rulemaking.
In its Advance Notice of Proposed Rulemaking for the Definition of High-Level Radioactive
Waste at 10 CFR Part 60 (52 FR 5992-6001), the NRC introduced the term incidental wastes
and stated that high-level waste does not include such waste streams. Additionally, the
Commission stated (footnote 1, 52 FR 5993) that “incidental wastes generated in further
treatment of HLW (e.g., decontaminated salt with residual activities on the order of 1,500 nCi/g
Cs-137, 30 nCi/g Sr-90, 2 nCi/g Pu, as described in the Department of Energy’s FEIS on long
term management of defense HLW at the Savannah River Plant, DOE/EIS-0023, 1979) would
also, under the same reasoning, be outside the proposed Appendix D definition,” if they met
certain chemical concentrations. Additionally, in the NRC’s Proposed Rule for 10 CFR Part 61,
for shallow-land disposal of radioactive waste, the Commission stated that the preferable
construction of the statute “...is to conform to the traditional definition (for high-level waste).
Under this approach, materials that are HLW for purposes of the licensing-jurisdiction provisions
of the Energy Reorganization Act of 1974 will also be regarded as high-level waste under the
Nuclear Waste Policy Act of 1982, as amended. This would include the primary reprocessing
waste streams at DOE facilities, though not the incidental wastes produced in reprocessing” (53
FR 17709).
Section 164
More recently, in response to a petition regarding disposal of waste at the Hanford site, the NRC
(States of Washington & Oregon: Denial of Petition for Rulemaking, 58 FR 12342-12347)
commented that:
“Assuming implementation of DOE’s plans as described above, the Commission
concludes that any radioactive material from the double shell tanks that is deposited in the
grout facility would not be high-level radioactive waste subject to NRC’s licensing
jurisdiction. The responsibility for safely managing those wastes rest with the Department
of Energy. The basis for the Commission’s conclusion is that the reprocessing wastes
disposed of in the grout facility would be ‘incidental’ wastes because of DOE’s assurance
that they:
(1) have been processed (or will be further processed) to remove key radionuclides to
the maximum extent that is technically and economically practical;
Chapter II -High-Level Waste Requirements
II-16 DOE G 435.1-1
7-09-99
(2) will be incorporated in a solid physical form at a concentration that does not
exceed the applicable concentration limits for Class C LLW as set out in 10 CFR
Part 61; and
(3) are to be managed, pursuant to the Atomic Energy Act of 1954, as amended, so
that safety requirements comparable to the performance objectives set out in 10
CFR Part 61 are satisfied." (58 FR 12345)
A similar characterization was made for the West Valley Demonstration Project in the Technical
Evaluation Report prepared by the NRC Office of Nuclear Material Safety and Safeguards, dated
November 1988, which concluded there is reasonable assurance that the cement solidification of
the decontaminated supernatant (incidental waste) will meet the waste form stability requirements
of 10 CFR Part 61 (NRC Technical Evaluation, 11/88). This is an implicit recognition by the
NRC that the separated low-activity fraction of high-level waste need not be managed and
disposed as high-level waste.
The question of whether the NRC or DOE has the authority to make incidental waste
determinations (using the evaluation process) was raised by NRC Commissioner Curtiss in
December 1992 (SECY-92-391), as a precursor to the Commission’s action on the 1993 Denial
of Petition for Rulemaking. In response, the NRC staff (memo for Commissioner Curtiss from J.
M. Taylor, 1/14/93) stated that DOE has the responsibility to make an initial determination, and if
DOE concludes that the action is not subject to NRC jurisdiction, then DOE can undertake the
activity without involving the NRC in any manner. However, if DOE concludes that NRC
jurisdiction is unclear (i.e., the waste may be high-level waste and therefore potentially subject to
NRC licensing), then DOE has two options: (1) consult with the NRC and then make a decision
based on the results of the consultation; or (2) proceed without communication with the NRC.
The staff response then cites the proposed letter from Bernero (USNRC) to DOE (transmitted
March 2, 1993) that the NRC would call upon DOE to provide relevant technical information that
would enable the NRC to make its own determination, should that be appropriate. (Although this
decision applied to the Hanford case only, DOE’s interpretation, based on discussions with NRC
staff, is that it can be applied more broadly through DOE M 435.1-1.) These two memoranda are
interpreted to mean that the NRC expects the DOE to consult with them for those waste streams
that the DOE has some question of whether the waste stream is high-level waste. In addition, as
discussed in the guidance to Section I.2.F.(18), the NRC has licensing authority over DOE
facilities “authorized for the express purpose of subsequent long-term storage of high-level
radioactive waste generated by DOE and its predecessor agencies” (Sullivan, 1998).
Section 165
Determination Processes. Consistent with these concepts, Section II.B of DOE M 435.1-1 offers
two distinct processes by which DOE can determine whether reprocessing wastes can be managed
as low-level or transuranic waste under DOE’s Atomic Energy Act authorities: (1) by citation, and
(2) by evaluation.
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-17
7-09-99
The citation process refers to those reprocessing waste items of the type that were discussed in
the Statement of Proposed Policy for Appendix D, 10 CFR Part 50, as not being high-level waste.
Although the exclusion of such items from the high-level waste definition was dropped from the
final rule (Appendix F), the concept of incidental waste has been supported by DOE and the NRC.
If a positive determination is made, the waste may require further characterization and/or
acceptable (process) knowledge to determine its final waste classification and disposition, i.e.,
low-level or transuranic waste.
The evaluation process refers to those reprocessing wastes that have met, or will meet, the
evaluation criteria cited above or other consistent protective criteria approved by the Department.
Satisfying these criteria ensures the waste to be regulated and managed for disposal by the DOE
according to the requirement for low-level or transuranic wastes, as appropriate.
Finally, if the requirements of neither of these processes can be met, the reprocessing waste is to
be managed as high-level waste and its disposal must be in accordance with 10 CFR Part 60 and
40 CFR Part 191.
The distinction between the two processes is important because it is clear from background events
that citation process waste streams were so identified because of the ease of determining up front
that they do not pose the long-term hazards associated with high-level waste. Evaluation process
wastes, on the other hand, generally require a case-by-case evaluation and determination.
Consistent with this understanding, the responsibility for citation interpretations rests solely with
the DOE Field Element Manager, although consultation with the Office of Environmental
Management is encouraged. However, the Office of Environmental Management consultation is
required for waste that has been determined to be incidental through the evaluation process. In
addition, it is recommended that consultation with the NRC staff be considered for evaluation
process determinations, although this is not required. Roles and responsibilities are further
explained in the guidance to Section I.2.F.(18) of the General Requirements to DOE M 435.1-1.
Several meetings were held between staff personnel from the NRC and DOE to discuss the
acceptability of this dual determination approach. NRC staff agreed with this approach, but
recommended that sufficient guidance be developed for the implementation of both processes.
This guidance document is provided, in part, to meet the NRC staff recommendation. The NRC
staff also confirmed that it supports the position that DOE has authority to make incidental waste
determinations that involve waste streams that are incidental by use of the citation process. For
waste streams that are considered to be incidental by the evaluation process, and may be subject
to NRC licensing if contained in a facility authorized by Congress for the express purpose of long
term storage, the staff suggested that communications with the NRC be maintained. This
suggestion is consistent with the staff position discussed above and the letter from R. Bernero,
USNRC, to J. Lytle, DOE-EM, dated March 2, 1993 and is provided in DOE M 435.1-1 by
recommending consultation with the NRC staff on evaluation determinations. Such
Section 166
Chapter II -High-Level Waste Requirements
II-18 DOE G 435.1-1
7-09-99
communication needs to: a) document the results of the analyses supporting DOE’s conclusions;
b) be adequate for review; c) be developed with good record-keeping; and d) be conducted under
an adequate quality assurance process. Guidance for DOE M 435.1-1, Section I.2.F.(18),Waste
Incidental to Reprocessing, provides additional information on these elements and the roles and
responsibilities of the Field Element Manager, the DOE Headquarters , and the NRC.
The NRC staff also indicated that if they are requested to consult on such reviews that they would
prefer to review evaluation process waste stream candidates on a macro basis, in lieu of reviewing
individual waste streams or waste items. This is interpreted to mean that the NRC staff would
prefer to review an analysis for a group of high-level waste streams that have similar
characteristics or will require similar processing to meet the evaluation criteria, in lieu of
individual waste streams or waste items. Such grouping of waste streams is expected to make the
most efficient use of the NRC staff’s resources and to avoid its involvement in each evaluation
process determination for each candidate waste stream or item within the DOE complex. The
Office of Environmental Management also prefers to see such grouping be submitted for
consultation and coordination. Further discussion on this subject is provided below under the
evaluation process.
DOE M 435.1-1 is not intended to create, or support the creation, of a new waste type titled
incidental waste. Waste incidental to reprocessing refers to a process for identifying waste
streams that would otherwise be considered high-level waste due to their sources of generation or
concentration, but can be managed in accordance with the DOE requirements for transuranic or
low-level waste, if the requirements for waste incidental to reprocessing are met.
Additionally, it is not the Department’s intent to use the waste incidental to reprocessing process
to circumvent high-level waste disposal standards by not disposing of high-level waste in the
NRC-licensed geologic repository. The goal of the waste incidental to reprocessing determination
process is to safely manage and dispose of a limited number of reprocessing waste streams that do
not warrant geologic repository disposal because of their lack of long-term threats to the
environment and man. Moreover, meeting the evaluation process requirements are difficult and
resource intensive and therefore, the DOE high-level waste sites are encouraged to manage high-
level waste in a manner that will permit treatment and disposal in a geologic repository.
Therefore, non-standard high-level wastes, discussed in the guidance for Section II.A, may be one
of the primary waste streams targeted for application of the waste incidental to reprocessing
determination process.
To assist in making waste incidental to reprocessing determinations, Figure 1, “Decision Tree for
Waste Incidental to Reprocessing Determinations,” has been included in this guidance. This
figure is a simple decision tree that provides some examples of reprocessing wastes and
reprocessing waste streams that are interpreted to be included within each determination process,
however, these examples are not considered all inclusive. It is expected that interpretations and
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-19
7-09-99
Section 167
determinations by the DOE sites, in conjunction with DOE Headquarters, may revise this list.
Updates to this guidance will reflect such determinations and interpretations.
Application of the citation and evaluation processes is for two primary purposes: to support the
determination to manage specific waste streams as non-high-level waste, i.e., as low-level or
transuranic wastes; and to support closure activities of deactivated high-level waste facilities/sites.
Table 1, “Citation and Evaluation Process Results,” is provided to illustrate the six (positive)
possible results that can result from applying the citation and evaluation process requirements to a
waste stream. A negative result to applying both the citation and evaluation processes is possible
with the result being that the waste stream is managed as high-level waste. The check symbols
under the columns Low-Level Waste, Transuranic Waste, and Facility/Site Closure denote the
Section II.B requirements that must be met in order for the waste stream to be managed as
indicated by the column heading.
Table 1. Citation and Evaluation Process Results (NA = not applicable)
Requirement(s)
Section
Low-Level
Waste
Transuranic
Waste
Facility/Site
Closure
II.B.(1)
Citation Process
U U NA
II.B.(2)(a)(1), (2), & (3)
Evaluation Process
U NA U
II.B.(2)(b)(1), (2), & (3)
Evaluation Process
NA U U
Following is a discussion on each of the determination processes, citation and evaluation.
Included, where appropriate, is additional guidance/discussion on the analysis and documentation
necessary for reprocessing waste streams to be managed as low-level waste or transuranic waste.
Additional information on deactivated high-level waste facility/closure process is provided by the
guidance to DOE M 435.1-1, Section II.U, Site Closure.
Citation Process. The citation process refers to those reprocessing waste items of the type that
were discussed in the Statement of Proposed Policy for Appendix D, 10 CFR Part 50, as not
being high-level waste (34 FR 8712). Figure 1 includes examples of wastes that have been
interpreted to be included within the citation process. Included are:
• contaminated job wastes, a general category of wastes that are generated during
high-level waste transfer, pretreatment, treatment, storage and disposal activities.
Chapter II -High-Level Waste Requirements
II-20 DOE G 435.1-1
7-09-99
Included is protective clothing, personal protective equipment (PPEs), work tools,
ventilation filter media, and other job-related materials necessary to complete high-
level waste management activities;
• sample media (e.g., sampling vials, crucibles, other hardware);
• decontamination media and decontamination solutions (e.g., swabs, other decon
work-related materials); and
• laboratory clothing, tools, and equipment.
Interpreted to be excluded from the citation process are the following:
• ion exchange beds;
• sludges;
• fuel cladding hulls and fuel structural hardware;
• process filter media; and
• contaminated components and equipment.
Section 168
This list excludes three items: ion exchange beds, sludges, and fuel cladding hulls that were
included in the Appendix D proposed language. The first two of these have been excluded from
the citation process examples because of the potential long-term hazards their disposal may pose.
However, they may be candidates for the evaluation process. The third example that has been
excluded is fuel cladding hulls and fuel structure hardware. As explained in the guidance for
Section II.A, wastes from processes preceding the first step in a separations process are not
considered high-level waste and therefore are not subject to the waste incidental to reprocessing
process. Fuel structural hardware and fuel cladding hulls are generated prior to the first cycle
solvent extraction process, or equivalent, and are therefore not considered high-level waste. Also
excluded from the examples of citation waste is high-level waste contaminated components and
equipment. As discussed in the guidance to Section II.A, review of available supporting
documentation has concluded that although contaminated components and equipment are not
high-level waste, they can, and often do, retain significant amounts of residual waste even after
extensive decontamination efforts. Therefore, it is considered inappropriate for such components
and equipment to qualify under the citation process. However, they are considered candidates for
the evaluation determination process described below.
The following examples of process filter media and ventilation filter media are provided to clarify
the use of the term in the citation process examples above:
Examples: (1) At Site X, the high-level waste pretreatment process uses a filtration
process to filter precipitated Cs-137 from the tank solution. Disposal of the failed
(process) filter media from this process as transuranic, low-level, or mixed low-level,
using the citation process, is considered inappropriate. However, the filter is a candidate
for disposal as low-level or transuranic waste using the evaluation process. (2) The
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-21
7-09-99
high-level waste storage tanks at this site include a HEPA filtration system. Disposal of
the HEPA filters from this system as low-level or transuranic waste, using the citation
process, is considered appropriate. (3) The same site has an effluent treatment facility
(ETF) that treats overheads (evaporator distillate) from a high-level waste evaporator.
Since these overheads are not considered to be high-level waste (there is no carryover of
high-level waste to the waste stream) disposition of these failed filters does not need to be
subjected to the waste incidental to reprocessing processes. They are managed as low-
level or transuranic waste, as appropriate.
As indicated in Table 1, meeting the requirement in Section II.B.(1) can result in the waste being
managed as low-level waste or transuranic waste. The responsibility of interpreting the Appendix
D proposed language and using the citation process is within the DOE’s authority. As delineated
in DOE M 435.1-1, Section I.2.F.(18), the authority to implement the citation process and make
these interpretations rests with the DOE Program Office responsible for the management of the
waste. In the case of high-level waste this responsibility has been assigned to the Field Element
Manager at the DOE Field Office or Operations Office. Consultation and coordination with the
DOE Office of Environmental Management for the citation process is encouraged to support
consistent interpretations across the DOE complex, but is not required.
Section 169
Evaluation Process. As shown in Figure 1, waste streams resulting from the reprocessing of high-
level waste that not interpreted to be included within the citation process may be assessed for
compliance with the evaluation process requirements. Examples of wastes streams that are
anticipated to be candidates for the application of the evaluation process include:
• residual radioactive tank wastes whose removal is not considered to be technically
and economically practical;
• contaminated storage, pretreatment, and treatment equipment (e.g., tank
mixer/pumps, waste slurry processing tanks);
• thermocouple trees;
• vitrification melter components;
• failed vitrification melters;
• process filter media;
• other process equipment that contains some amounts of waste in the form of
slurry, salt or glass.
The examples provided above are anticipated to meet the three evaluation process criteria;
however, note that the list provided above is not all inclusive. Other reprocessing waste streams
may be candidates for the evaluation process. However, any wastes that are determined to meet
these criteria must be supported by the necessary information and analysis as described in the
guidance for DOE M 435.1-1, Section I.2.F.(18). While the DOE Office of Environmental
Management consultation and coordination is required by the requirement in Section I.2.F.(18),
Chapter II -High-Level Waste Requirements
II-22 DOE G 435.1-1
7-09-99
consultation with the NRC staff related to compliance with the evaluation requirements is also
strongly encouraged. The NRC staff has participated in regulatory compliance reviews using
these criteria in the past and has a level of expertise that is expected to complement the DOE
Office of Environmental Management’s review.
DOE maintains that contaminated equipment, components, etc., whose disposal can be
demonstrated to not jeopardize the health and safety of the public, workers, and the environment
can be managed as non-high-level waste. These waste streams could be managed as low-level
waste, transuranic waste, or residual waste, which is part of a deactivated high-level waste closure
action and meets the performance objectives of a low-level or transuranic waste disposal facility,
provided the waste fits the requirements of the citation or evaluation process as delineated in
Table 1. Guidance for each of the processes follows.
II. B.(2) Evaluation. Determinations that any waste is incidental to
reprocessing by the evaluation process shall be developed under good
record-keeping practices, with an adequate quality assurance process,
and shall be documented to support the determinations. Such wastes
may include, but are not limited to, spent nuclear fuel reprocessing
plant wastes that:
(a) Will be managed as low-level waste and meet the following
criteria:
1. Have been processed, or will be processed, to remove
key radionuclides to the maximum extent that is
technically and economically practical; and
Although key radionuclides are not defined by the NRC in either the Denial of Petition for
Rulemaking or the letter from R. Bernero to J. Lytle, dated March 2, 1993, it is generally
understood that key radionuclides applies to those radionuclides that are controlled by
concentration limits in 10 CFR 61.55. Specifically these are: long-lived radionuclides, C-14, Ni
59, Nb-94, Tc-99, I-129, Pu-241, Cm-242, and alpha emitting transuranic nuclides with half-lives
greater than five years and; short-lived radionuclides, H-3, Co-60, Ni-63, Sr-90, and Cs-137. In
addition, key radionuclides are those that are important to satisfying the performance objectives of
10 CFR Part 61, Subpart C. Analysis to date at DOE sites indicates other isotopes important to
satisfying these performance objectives include Se-79, Sn-126, and Np-237.
Section 170
Processing to remove the key radionuclides to the extent technically practical could be a chemical
treatment process or a physical removal process. The examination of such processes should
include a range of alternatives; from processes that have been demonstrated by plant-scale
experience to be practical to those that have been demonstrated to be impractical due to their
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-23
7-09-99
technological immaturity, uncertainty, or risk. Selection of the chosen “technically practical
process” must be evaluated to a sufficient degree through a formal, documented assessment of
such factors as technical risk, incompatible physical or chemical requirements with the waste, and
potential impacts to the public, the worker and the environment.
The economically practical part of this requirement is determined by the development of total life-
cycle costs for an alternative, or unit costs, e.g., cost per curie removed. Some subjectivity will
be present in determining whether these costs are economically practical; however in general, the
goal should be to determine a relationship between costs and removal of the key radionuclides and
identify the point in this relationship at which removal costs increase significantly and thus become
impractical. An economic assessment may not be considered necessary if a technology option is
not first considered to be technically practical.
Example 1: To satisfy this criterion, Site X identified the available separation
technologies for each of the main radionuclides of interest in the waste stream (Cs-137,
Sr-90, transuranics, Tc-99, Se-79, Sn-126, C-14, I-129, H-3, and uranium), and
individually, as well as collectively, evaluated each to determine the status of the
technology and radionuclide removal efficiencies. A number of technologies were
identified and evaluated, including some for which tests on actual waste had been
conducted. The separation processes that were determined to be technically practical,
due to their technical maturity and full-scale demonstrated applications, were then
examined for economic practicability based on unit removal costs and process life-cycle
costs. An initial evaluation determined that two separation technologies were deemed to
be technically and economically practical and were selected for implementation for the
removal of the key radionuclides identified. A report documenting the assessment of
each of the technologies for technical practicality and economic practicality was issued
by the site program manager. Since this was the first use of the Evaluation Process for
this waste stream, or a similar waste stream, the site employed the consultation services
of the NRC. Following their evaluation, the assessment, confirming that the requirement
at II.B.(2)(a)1. had been met, along with the analysis that supports the position that the
waste meets the other Evaluation requirements at II.B.(2)(a)2. and II.B.(2)(a)3., was
forwarded to the DOE Headquarters for coordination and consultation, as required by
Section I.2.F.(18).
Example 2: The Site X facility and waste are the same as above except the economic
evaluation determined that none of the separation technologies were deemed to be
economically practical for removal of one of the radionuclides from a waste stream, due
to excessively high unit costs ($/Ci removed) and life-cycle costs, when compared to
direct disposal of the radionuclide as low-level waste. A report documenting this and the
assessment of each of the technologies for technical practicality and economic
practicality was issued by the site program manager. The waste stream that contained
Section 171
Chapter II -High-Level Waste Requirements
II-24 DOE G 435.1-1
7-09-99
the radionuclide in question was analyzed for acceptance at a low-level waste disposal
facility and it was concluded that the final waste form, incorporating the radionuclide,
would meet the requirements at both II.B.(2)(a)2. (safety requirements comparable to the
performance objectives in 10 CFR Part 61, Subpart C), and II.B.(2)(a)3. (solid physical
form at a concentration that does not exceed the applicable limits for Class C, 10 CFR
61.55). Therefore, the waste stream was deemed acceptable for disposal as low-level
waste.
II. B.(2)(a) Will be managed as low-level waste and meet the following criteria:
2. Will be managed to meet safety requirements comparable to
the performance objectives set out in 10 CFR Part 61, Subpart
C, Performance Objectives; and
Low-level waste requirements. When the waste stream is to be managed in accordance with low-
level waste requirements, an assessment needs to be prepared that provides reasonable
expectation that low-level waste performance objectives will be met. This assessment is
consistent with the requirements for a performance assessment, as defined in DOE M 435.1-1,
Section IV.P.(2). The Chapter IV performance objectives (Section IV.P.(1)) are considered
comparable to those at 10 CFR Part 61, Subpart C. In some cases the requirement to prepare a
performance assessment may be met in part, or totally, by the waste acceptance and waste
certification programs established by Chapter IV of DOE M 435.1-1. As discussed in the
guidance for Section IV.G, Waste Acceptance, performance assessment data are used to establish
waste acceptance criteria. Additionally, a primary element of a performance assessment is
analysis that demonstrates compliance with the performance objectives in DOE M 435.1-1,
Section IV.P.(1). Therefore, if a waste form is certified as meeting a low-level waste disposal
facility’s waste acceptance criteria the waste form may meet the performance objectives in Section
IV.P.(1) as well, provided performance assessment imposed limits, e.g., quantity of material, are
also met. Documentation providing sufficient data to support this conclusion is submitted for
coordination with the DOE Office of Environmental Management, as required by the requirement
in Section I.2.F.(18).
Example: Site Y has a number of contaminated mixer/pumps that have been removed
from a high-level waste storage tank and are considered waste. Following
decontamination activities, characterization data show that the mixer/pumps can meet the
waste acceptance criteria for an on-site low-level waste disposal facility. Documentation
supporting this conclusion, and consistent with the requirements in Section IV.J, Waste
Certification, is prepared. Additionally, documentation is prepared that concludes that
meeting the disposal site’s waste acceptance criteria meets the disposal facility’s
performance objectives which have been shown previously to be comparable to those in
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-25
7-09-99
the NRC’s 10 CFR Part 61, Subpart C, Performance Objectives. Therefore Site Y
concludes that the requirement at II.B.(2)(a)2. has been met and a stand-alone
performance assessment for this waste stream is not necessary. The set of documentation
supporting this conclusion is submitted to the DOE Office of Environmental Management
for consultation and coordination as required by the requirement in Section I.2.F.(18).
Section 172
Often the location and design of a low-level waste disposal facility are not finalized at the time
such an assessment is needed. In such cases, a preliminary or interim performance assessment
should be prepared, and submitted to the Office of Environmental Management for coordination.
Preparation and approval of a preliminary, or interim, as well as a final performance assessment to
support the meeting of this requirement, need to meet the requirements at DOE M 435.1-1,
Section I.2.E.(1), Disposal.
Example: To meet requirement II.B.(2)(a)2., Site X prepared an interim performance
assessment, in accordance with the requirements of DOE M 435.1-1, Section IV.P.(2), for
a waste stream that meets the other two applicable evaluation process requirements. The
performance assessment was considered interim because it was prepared before the
selection of a disposal facility site and design were finalized and before the final low-
level waste form was selected. The site forwarded a copy of the interim performance
assessment and a draft authorization letter to the DOE Office of Environmental
Management for coordination. The DOE Office of Environmental Management’s review
concluded that although the interim performance assessment was limited in information
it did indicate that the performance objectives would be met. This finding was
conditional on the review of subsequent performance assessments and other stipulations
described in a site authorization letter. Although only an interim performance
assessment, the review and concurrence requirements at DOE M 435.1-1 Section
I.2.E.(1) for a performance assessment were applied.
In the case of facility/site closure with the residual waste characterized as low-level waste, the
requirement to conduct a performance assessment to meet the criterion in Section II.B.(2)(a)2.
should be coordinated with similar requirements in Section II.U, Site Closure, to avoid redundant
analysis.
II. B.(2)(a) Will be managed as low-level waste and meet the following criteria:
3. Are to be managed, pursuant to DOE’s authority under the
Atomic Energy Act of 1954, as amended, and in accordance
with the provisions of Chapter IV of this Manual, provided the
waste will be incorporated in a solid physical form at a
concentration that does not exceed the applicable
concentration limits for Class C low-level waste as set out in 10
Chapter II -High-Level Waste Requirements
II-26 DOE G 435.1-1
7-09-99
CFR 61.55, Waste Classification; or will meet alternative
requirements for waste classification and characterization as
DOE may authorize.
10 CFR 61.55 Concentration Limits. To meet this criterion, DOE needs to demonstrate that the
final waste form will not exceed the limits for Class C waste, as defined in 10 CFR 61.55. These
calculations should compare, by major radionuclide, the expected concentration after the
proposed treatment process with the limits as provided at 10 CFR 61.55. .
Example: To meet this criterion, Site X calculated an estimated total vitrified waste
volume in conjunction with the projected radionuclide activities. From these
calculations, the vitrified waste form is expected to meet the limits for 10 CFR 61.55
Class C, or less. This information was provided to the DOE Office of Environmental
Management for coordination.
Section 173
Dilution of a waste stream to meet the concentration limits established in 10 CFR 61.55 is not
permitted by the Department. While it is recognized that in the course of stabilizing a waste
stream some changes in waste concentration may occur, actions to dilute a waste stream to meet
the above concentration limits are prohibited. The NRC’s Branch Technical Position on
Concentration Averaging, dated January 17, 1995 (NRC, 1995), that supports the regulation at
10 CFR 61.55(a)(8), may be useful in making determinations. The Branch Technical Position
states that, “the concentration of a radionuclide (in waste) may be averaged over the volume of
the waste, or weight of the waste if the units (on the values tabulated in the concentration tables)
are expressed as nanocuries per gram.” This Branch Technical Position provides specific
guidance to waste generators on the interpretation of the requirements in 10 CFR 61.55 as it
applies to a variety of different types and forms of low-level waste.
Consistent with the discussion above for the requirement in Section II.B.(2)(a)2., certification that
a waste form meets a low-level waste disposal facility’s waste acceptance criteria may in part, or
totally, meet this requirement since, in general, waste that meets the definition of low-level waste,
as defined in Section IV.A, meets the concentration limits for Class C low-level waste, as set forth
in 10 CFR 61.55. However, there are exceptions as discussed in the guidance for IV.A. For
example, a waste form with a concentration of Cm-244 exceeding 100 nCi per gram meets the
definition of low-level waste, per Chapter IV of DOE M 435.1-1 (Cm-244 is an alpha-emitting
transuranic nuclide with a half-life of 18.1 years and is therefore not relevant to whether the waste
is transuranic waste) however, it does not meet the concentration limits in Table 1 of 10 CFR
61.55 (Cm-244 has a half-life greater than 5 years and the concentration limit is 100 nCi per
gram). Thus careful attention needs to be paid to ensure that the concentration limits set forth in
10 CFR 61.55 are not exceeded.
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-27
7-09-99
Alternative Requirements. If the limits contained at 10 CFR 61.55 for Class C low-level waste
cannot be met, the DOE Field Element may request that the DOE Office of Environmental
Management review and accept other provisions for the classification of the waste on a specific
basis. This provision is similar to the requirement at 10 CFR 61.58, Alternative Requirements for
Waste Classification and Characteristics. Analysis submitted to the DOE Office of
Environmental Management must provide reasonable expectation that after evaluation of the
specific characteristics of the waste, disposal site, and method of disposal, compliance with the
low-level waste performance objectives can be achieved.
Section 174
Example: Following consultation with the NRC, Site X requested the DOE Office of
Environmental Management to review and accept an alternative to the Class C limits of
10 CFR 61.55 for the closure of a number of former high-level waste storage tanks. The
provided analysis noted that the NRC method for deriving the Class C concentration
limits in 10 CFR Part 61 is based on direct contact with the disposed waste by an
inadvertent intruder scenario and that the overall standard for determining Class C
concentrations limits is an annual dose equivalent to an inadvertent intruder of 500
mrem from all pathways. In the documentation provided to the DOE Office of
Environmental Management the case was made that the intruder scenarios for the Class
C determination are inappropriate because the residual waste in the tank will be
immobilized and located at least 10 meters below the ground surface, and the tank system
will be filled with a stable medium. A site-specific intruder analysis for a hypothetical
closed tank system was provided to the DOE Office of Environmental Management for
their review. The analysis concluded that the postulated site intruder would receive a
dose well below the limit of 500 mrem per year and demonstrated that the tank closures
will comply with the performance objectives of 10 CFR Part 61.
II.B.(2)(b) Will be managed as transuranic waste and meet the following criteria:
1. Have been processed, or will be processed, to remove key
radionuclides to the maximum extent that is technically and
economically practical; and
This is the same requirement as II.B.(2)(a)1., and the process for meeting this requirement is the
same. Therefore, the guidance for Section II.B.(2)(a)1. applies to this requirement.
II.B.(2)(b) Will be managed as transuranic waste and meet the following criteria:
2. Will be incorporated in a solid physical form and meet
alternative requirements for waste classification and
characteristics, as DOE may authorize; and
Chapter II -High-Level Waste Requirements
II-28 DOE G 435.1-1
7-09-99
As discussed in the guidance above for Section II.B.(2)(a)3., Alternative Requirements, if the
limits contained at 10 CFR 61.55 for Class C low-level waste cannot be met, the DOE Field
Element may request that the DOE Office of Environmental Management review and accept other
provisions for classification of the waste, on a specific basis. This provision is similar to the
requirements at 10 CFR 61.58, Alternative Requirements for Waste Classification and
Characteristics, which states:
“The Commission may, upon request or on its own initiative, authorize other provisions
for the classification and characteristics of waste on a specific basis, if, after evaluation, of
the specific characteristics of the waste, disposal site, and method of disposal, it finds
reasonable assurance of compliance with the performance objectives [P.O.] in Subpart C
of this part.”
In those cases where application of the alternative waste classification criteria results in the waste
being characterized as transuranic waste, and disposal will be in a facility other than WIPP (e.g.,
onsite as part of a deactivated high-level waste closure activity or at another DOE transuranic
waste disposal site), characterization/classification provisions may be proposed by a Field
Element. In such cases, DOE Headquarters shall be consulted and an analysis submitted for
review that provides reasonable assurance that after evaluation of the: (1) specific characteristics
of the waste, (2) disposal site characteristics, and (3) method of disposal, compliance with
applicable performance objectives can be achieved.
Section 175
II.B.(2)(b) Will be managed as transuranic waste and meet the following criteria:
3. Are managed pursuant to DOE’s authority under the Atomic
Energy Act of 1954, as amended, in accordance with the
provisions of Chapter III of this Manual, as appropriate.
In those cases where the waste stream will be managed as transuranic waste and disposal will be
in a facility other than the Waste Isolation Pilot Plant (WIPP) (e.g., onsite or at another DOE
transuranic waste disposal site), the Department is currently responsible for determining
compliance with 40 CFR Part 191 and ensuring the transuranic waste is disposed of safely. As
explained in the guidance to Section III.P., Disposal, sites other than WIPP are regulated by the
implementing agency, in this case, DOE. As discussed in the General Requirements Chapter of
this DOE M 435.1-1, Section I.2.F.(15), Disposal, the Field Element Manager is responsible for
reviewing and submitting a performance assessment to DOE Headquarters. The DOE
Headquarters Deputy Assistant Secretary for Waste Management will establish a process similar
to that used for low-level waste disposal facilities for reviewing and approving performance
assessments. Additional details on the criteria for reviewing and approving 40 CFR Part 191
performance assessments is included in the guidance to Section III.P. Since performance
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-29
7-09-99
assessment is defined, and the requirements for compliance and what must be included in a
performance assessment for a transuranic waste disposal facility are discussed in 40 CFR Part
191, this section of the guidance and the transuranic waste chapter only contain reference to the
40 CFR Part 191 standards, with no additional minimum requirements for disposal.
As discussed in the guidance to Chapter III of DOE M 435.1-1, the Department plans to dispose
defense transuranic waste at WIPP. Therefore, evaluations of treatment and disposal options for
those streams must be taken into account.
As discussed above, the high-level waste sites are encouraged to group similar waste streams, that
are to be subjected to the evaluation process, to support the process of coordinating with the
DOE Office of Environmental Management and site review and approval. Such grouping is
expected to expedite the decision process and make the most efficient use of limited resources in
the DOE Office of Environmental Management. Following are two examples of grouping:
Example 1: At Site Y, the high-level waste treatment (vitrification) activities are nearing
completion and plans for dispositioning the equipment contaminated with reprocessing
wastes within the pretreatment and treatment processes are being formulated. Analysis
indicates that decontamination activities can be held to a minimum if a number of
contaminated pretreatment and treatment components (mixer/pumps, slurry transfer
lines, slurry tanks, melter, process filter media) can be disposed as transuranic waste by
way of the evaluation process. In lieu of submitting individual analysis for each of
contaminated components, Site Y consults with the DOE Office of Environmental
Management and the NRC staff on the methodology they propose for meeting the three
appropriate evaluation requirements. Following such consultation, Site Y approves a
methodology for meeting each of the three evaluation criteria for a group of these
components.
Section 176
Example 2: At Site Z, closure analysis activities are underway for a number of high-level
waste tanks. In reviewing the processes for removing the final amounts of high-level
waste from the tanks, it is concluded that the evaluation process requirements can be met
even if some small quantities of residual waste are allowed to remain in the tanks. In lieu
preparing an analysis for each tank, the site submits a methodology for meeting each of
the evaluation requirements for a group of the tanks. The methodology is submitted to
the DOE Office of Environmental Management for coordination and acceptance of this
methodology for the group of tanks is gained from the site program office. The closure
activities proceed for the group of tanks.
Facility Closure. Application of the evaluation process for deactivated high-level waste
facility/site closures is to ensure that any residual waste or residual contaminated components are
disposed appropriately. As indicated in Table 1, the requirements in Section II.B.(2)(a) 1., 2., and
Chapter II -High-Level Waste Requirements
II-30 DOE G 435.1-1
7-09-99
3., or the requirements in Section II.B.(2)(b) 1., 2., and 3., must be met in order to manage the
waste as non-high-level waste and allow the residual waste or residual contaminated components
to be managed as low-level waste, or transuranic waste, as part of a deactivated high-level waste
closure action. Closure actions for deactivated high-level waste facilities are distinguished from
disposal of wastes incidental to reprocessing by the fact that closure actions normally involve
facilities that are not total dismantled and remain in their operational location. However, because
the residual material is part of a closure activity and will remain following closure, the disposal
requirements in Section IV.P. and III.P. for low-level and transuranic wastes, respectively, are the
appropriate requirements to satisfy Sections II.B.(2)(a)2. and II.B.(2)(b)3. The requirements for
closure of these facilities and sites (groups of facilities) are in Section II.U, Site Closure.
The Field Element Manager is responsible for ensuring that the requirements of the evaluation
process are met. DOE M 435.1-1, Section I.2.F.(18), Waste Incidental to Reprocessing, defines
the responsibilities and roles of the Field Element Manager, the Office of Environmental
Management, and the consultation role that NRC staff may take in implementing the evaluation
process. Refer to the guidance for this section for additional information.
Mixed Waste. DOE M 435.1-1, Section II.C., Management of Specific Wastes, imposes the
requirement that all high-level waste is to be considered mixed waste, unless demonstrated
otherwise. This requirement applies to waste incidental to reprocessing determined wastes as
well. Waste that is determined to be incidental to reprocessing by the application of the waste
incidental to reprocessing determination processes should be considered mixed, unless
demonstrated otherwise.
Compliance with this requirement is demonstrated by documented citation and evaluation
processes that are implemented in a defensible manner and ensure that the Department is not
exceeding its regulatory authority.
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-31
7-09-99
Chapter II -High-Level Waste Requirements
II-32 DOE G 435.1-1
7-09-99
Supplemental References:
Section 177
1. AEC, 1969. “Proposed Rule Making Statement of Proposed Policy; Siting of Commercial
Fuel Reprocessing Plants and Related Waste Management Facilities, 10 CFR Part 50,
‘Licensing of Production and Utilization Facilities,’” Federal Register, Vol. 34, No. 8712,
Atomic Energy Commission, Washington, D.C., June 3, 1969.
2. AEC, 1970. “Siting of Commercial Fuel Reprocessing Plants and Related Waste
Management Facilities, 10 CFR Part 50, ‘Licensing of Production and Utilization
Facilities,’” Federal Register, Vol 35, No. 17532, Atomic Energy Commission,
Washington, D.C., November 14, 1970.
3. Energy Reorganization Act of 1974, Public Law 93-438, Section 202 (3) and (4).
4. DOE, 1979. Final Environmental Impact Statement: Long-Term Management of
Defense High-Level Radioactive Wastes, DOE/EIS-0023, Savannah River Plant,
November, 1979.
5. NRC, 1987. “Advanced Notice of Proposed Rulemaking; 10 CFR Part 60, ‘Definition of
High-Level Radioactive Waste,’” Federal Register, Vol. 52, No. 5992, U.S. Nuclear
Regulatory Commission, Washington, D.C., February 27, 1987.
6. Curtiss, 1992. NRC Commissioner J.R. Curtiss to J.M.Taylor, Executive Director for
Operations, memorandum, SECY-92-391: Denial of PRM-60-4-Petition for Rulemaking
Regarding Classification of Radioactive Waste at Hanford, U.S. Nuclear Regulatory
Commission, Washington, D.C., December 29, 1992.
7. Taylor, 1993. J.M. Taylor, Executive Director for Operations to Commissioner Curtiss,
memorandum, Staff Response to Concerns Raised by Commissioner James R. Curtiss on
Denial of PRM-60-4-Petition for Rulemaking Regarding Classification of Radioactive
Waste at Hanford, January 14, 1993.
8. NRC, 1993. “Denial of Petition for Rulemaking, 10 CFR Part 60, ‘States of Washington
and Oregon: Denial of Petition for Rulemaking’,” Federal Register, Vol. 58, No. 12342,
U.S. Nuclear Regulatory Commission, Washington, D.C., March 4, 1993.
9. Bernero, 1993. R. Bernero, USNRC, to J. Lytle, DOE-EM, letter, Hanford Waste Tank
Management, U.S. Nuclear Regulatory Commission, Washington, D.C., March 2, 1993.
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-33
7-09-99
10. Paperiello, 1997. C. Paperiello, USNRC, to J. Kinser, DOE-RL, letter, Classification of
Hanford Low-Activity Tank Waste Fraction, U.S. Nuclear Regulatory Commission,
Washington, D.C., June 9, 1997.
11. DOE, 1998. Life-Cycle Asset Management, DOE O 430.1A, U.S. Department of Energy,
October 14, 1998.
12. DOE, 1997. Deactivation Implementation Guide, Draft DOE G 430.1-3, U.S.
Department of Energy, October 1, 1997.
13. DOE, 1997. Decommissioning Implementation Guide, Draft DOE G 430.1-4, U.S.
Department of Energy, October 1, 1997.
14. NRC, 1988. Cement Solidification of Decontaminated Supernatant Waste for West
Valley Project, Technical Evaluation, Office of Nuclear Material Safety and Safeguards,
November 1988.
15. EPA. Environmental Radiation Protection Standards for Management and Disposal of
Spent Nuclear Fuel, High-Level Waste and Transuranic Radioactive Wastes, 40 CFR
Part 191, U.S. Environmental Protection Agency, Washington, D.C.
16. NRC, 1995. Issuance of Final Branch Technical Position on Concentration Averaging
and Encapsulation, Revision in Part to Waste Classification Technical Position, U.S.
Nuclear Regulatory Commission, Washington, D.C., January 17, 1995.
Section 178
17. Sullivan, 1998. M.A. Sullivan, DOE, to J.T. Greeves, USNRC, letter, Natural Resources
Defense Council Petition to Exercise Licensing Authority over Savannah River Site High-
Level Waste Tanks, U.S. Department of Energy, Washington, D.C., September 30, 1998.
18. NRC, 1993. “Confederated Tribes and Bands of the Yakima Indian Nation: Denial of
Petition to Require License Application,” Federal Register, Vol. 58, No. 64783, U.S.
Nuclear Regulatory Commission, Washington, D.C., December 9, 1993.
19. NRDC Inc. v. Administrator, Energy Research and Development Administration, 606 F.
2d 126, (D.C. Cir. 1979), affirming in part, remanding in part, reversing in part,
vacating in part, 451 F. Supp. 1245 (D.D.C. 1978), denying motion in part, granting
motion in part, 5 NRC 550 (1977) (Commission Decision).
20. NRC, 1994. “F. Robert Cook: Denial of Petition to Require License Application from
DOE with Respect to High-Level Waste,” Federal Register, Vol. 59, No. 10439, U.S.
Nuclear Regulatory Commission, Washington, D.C., March 4, 1994.
Chapter II -High-Level Waste Requirements
II-34 DOE G 435.1-1
7-09-99
II. C. Management of Specific Wastes.
The following provide for management of specific wastes as high-level waste in
accordance with the requirements in this Chapter:
(1) Mixed High-Level Waste. Unless demonstrated otherwise, all high-level
waste shall be considered mixed waste and is subject to the requirements of
both the Atomic Energy Act of 1954, as amended, the Resource Conservation
and Recovery Act, as amended, DOE O 435.1, Radioactive Waste
Management, and this Manual.
(2) TSCA-Regulated Waste. High-level waste containing polychlorinated
biphenyls, asbestos, or other such regulated toxic components shall be
managed in accordance with requirements derived from the Toxic Substances
Control Act, as amended and DOE O 435.1, Radioactive Waste Management,
and this Manual.
Objective:
The objective of this requirement is to ensure that all high-level waste is managed as mixed
waste, unless demonstrated otherwise, and thus meets the requirements of both the Atomic
Energy Act of 1954, as amended and the Resource Conservation and Recovery Act (RCRA), and
that high-level waste that contains TSCA-regulated toxic components be managed in accordance
with the requirements of the Toxic Substances Control Act (TSCA). The RCRA and TSCA (if
applicable) statutes are to be met in addition to the requirements of DOE O 435.1 and DOE M
435.1-1.
Discussion:
DOE M 435.1-1 contains requirements for managing the radioactive character of high-level
waste. Guidance for implementing those requirements is included elsewhere in this document. In
developing DOE M 435.1-1 requirements, a safety and hazards analysis and an evaluation of the
requirements necessary to control the identified hazards were performed. It was concluded that
sufficient external regulations, promulgated pursuant to RCRA and TSCA, exist for controlling
the non-radiological hazard.
RCRA Regulations. The reprocessing of Department of Energy spent nuclear fuel produces high-
level waste that usually exhibits characteristics that render the high-level waste subject to the
requirements of the Resource Conservation and Recovery Act, as well as the Atomic Energy Act
of 1954, as amended.
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-35
7-09-99
Section 179
Considering high-level waste to be a mixed waste is consistent with Department of Energy past
practice. The previous Radioactive Waste Management Order, DOE 5820.2A (see page I - 1),
specified that high-level waste was to be considered mixed waste unless demonstrated to the
contrary.
The DOE Office of Civilian Radioactive Waste Management (OCRWM) has clearly stated that
only spent nuclear fuel and high-level waste that is not regulated as hazardous waste under RCRA
Subtitle C is planned to be disposed in the monitored geologic repository licensed by the Nuclear
Regulatory Commission (NRC) under the Nuclear Waste Policy Act of 1982, as amended. Prior
to acceptance for disposal, generators and custodians must determine and document that the
waste is not regulated as a hazardous waste and is not prohibited from land disposal. Therefore,
DOE must develop appropriate data to ensure State and/or EPA regulators that the applicable
requirements have been addressed.
The processes that produce high-level waste from spent fuel usually involve the use of hazardous
chemicals, so it is reasonable to assume that high-level waste is a mixed waste unless it is
demonstrated to be otherwise. The reprocessing of spent nuclear fuel usually includes dissolution
in acid followed by solvent extraction which is then often neutralized by addition of sodium
hydroxide. The solvent is usually stripped from the component being extracted from the spent
fuel. The solvent is recycled rather than disposed of as high-level waste. Furthermore, the fuel
matrix and cladding are typically a source of hazardous metals. Thus, high-level waste typically
exhibits the characteristics of corrosivity (pH < 2 or pH >12.5 (after neutralization)) and toxicity
(because of the presence of one or more toxic metals).
Wastes exhibiting hazardous characteristics (see 40 CFR Part 261, Subpart C) must be treated for
these characteristics prior to disposal. High-level wastes generated from the reprocessing of spent
nuclear fuel exhibiting the characteristics of corrosivity (D002) and toxicity for metals (D004 –
D011 corresponding to arsenic, barium, cadmium, chromium, lead, mercury, scandium, and silver)
may be treated through vitrification in accordance with the Land Disposal Restriction (LDR)
treatment standards specified in 40 CFR 268.40. The Environmental Protection Agency has
determined that vitrification (HLVIT) is the best demonstrated available technology (BDAT) for
treating high-level wastes that exhibit these characteristics. However, if additional characteristic
waste codes become applicable to the high-level waste, e.g., D018: benzene, the treated high-level
waste may need to meet the Universal Treatment Standards (40 CFR 268.48) for any underlying
hazardous constituents (UHCs). A treatability variance (40 CFR 268.44) and/or determination of
equivalent treatment (40 CFR 268.42(b)) may be necessary to fully comply with the LDR
standards if a DOE site elects to use a technology other than vitrification, the BDAT, of if it is
impractical to comply with all the standards applicable to individual waste codes.
High-level waste treated by vitrification but containing listed hazardous wastes (either from the
reprocessing activities or from subsequent commingling of listed hazardous waste in high-level
Chapter II -High-Level Waste Requirements
II-36 DOE G 435.1-1
7-09-99
Section 180
waste storage tanks) will remain subject to RCRA, unless a delisting request is also approved by
the Environmental Protection Agency. The Office of Environmental Management "Waste
Acceptance Product Specifications for Vitrified High-Level Waste Forms" requires that the
producer of the high-level waste perform the appropriate tests and procedures to determine
whether the waste is a hazardous waste (see Specification 1.5). That specification also requires
that high-level waste producers petition the Environmental Protection Agency to delist the waste
if any RCRA listed components are found in immobilized high-level waste. Currently, high-level
waste at some sites has been determined to contain listed wastes and high-level waste at other
sites has been determined not to contain listed wastes.
Example: In the previous example, the resulting high-level wastes were mixed with
various listed hazardous wastes for which a petition for delisting has not been approved.
Even after the high-level waste is treated by vitrification, it may not be disposed in the
Office of Civilian Radioactive Waste Management-managed monitored, geologic
repository because the high-level waste continues to be considered a mixed waste until
the Environmental Protection Agency approves a petition for delisting of the hazardous
waste components.
The RCRA requirements described above may be imposed by the Environmental Protection
Agency or by states that have been granted these RCRA authorities by the Environmental
Protection Agency. The authorized states are permitted to promulgate hazardous waste
requirements that are more stringent than the federal requirements, as well as specifying the
treatment permitting approach. Any state-level hazardous waste requirements will need to be
reviewed on a state-by-state basis.
In summary, the operations performed in reprocessing spent nuclear fuel often produce high-level
waste that exhibits hazardous characteristics. DOE practice is to assume that high-level waste is a
mixed waste unless demonstrated otherwise. This approach provides a conservative basis for
developing effective plans for high-level waste management including the capabilities for dealing
with hazardous components and characteristics.
PCB, Asbestos, and Other TSCA Wastes. High-level wastes contaminated with PCBs do not
meet the definition of mixed waste, however, the situation is similar to RCRA in that there are
external regulations promulgated under the authority of the Toxic Substances Control Act that
need to be complied with in addition to the requirements of DOE O 435.1 and the Manual. Waste
managers responsible for managing PCB-containing products should consult the EPA
requirements at 40 CFR Part 761. The regulations impose requirements for the destruction,
storage awaiting destruction, and disposal of PCBs. Like mixed wastes, there are currently no
provisions to accommodate PCBs (exceeding 50 ppm) at a geologic repository. Review of the
EPA handbook, “Vitrification Technologies for Treatment of Hazardous and Radioactive Waste,”
(EPA/625/R-92-002) finds that the combination of the vitrification process and off-gas removal
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-37
7-09-99
Section 181
are capable of eliminating 99.99%, or better, of the organic constituents, including
TSCA-regulated organics, in a waste stream. Therefore, vitrification, the BDAT for high-level
waste exhibiting RCRA characteristics of corrosivity and toxicity for metals, is expected to meet
the treatment requirements for PCBs and other TSCA-regulated toxic components, for those
high-level waste streams that are determined to contain these components. At the time of the
preparation of this guidance, no DOE high-level waste site had declared the presence of
TSCA-regulated toxic components in their high-level streams. Planning for management of high-
level wastes that include a component which is regulated under TSCA should be addressed in the
Complex-Wide High-Level Waste Management Program and the appropriate Site-Wide Waste
Management Programs (DOE M 435.1, Sections I.2.B.(1) and I.2.F.(1)).
The DOE M 435.1-1 requirements imposed on the radioactive component of RCRA or TSCA
waste should not create a duplication of management activities that can be satisfied by compliance
with a RCRA or TSCA requirement. Also, documentation required by RCRA or TSCA
regulations which provides the same or similar information as required by DOE M
435.1-1 should be used to satisfy the DOE M 435.1-1 requirement.
Supplemental References:
1. DOE, 1996. Waste Acceptance Product Specifications for Vitrified High-Level Waste
Forms (EM-WAPS), Revision 2, DOE/EM-0093, U.S. Department of Energy,
Washington, D.C., December 16, 1996.
2. EPA. Characteristics of Hazardous Wastes, 40 CFR Part 261, Subpart C, U.S.
Environmental Protection Agency, Washington, D.C.
3. EPA. Lists of Hazardous Wastes, 40 CFR Part 261, Subpart D, U.S. Environmental
Protection Agency, Washington, D.C.
4. EPA. Applicability of Treatment Standards, 40 CFR 268.40, U.S. Environmental
Protection Agency, Washington, D.C.
5. EPA. Treatment Standards Expressed as Specified Technologies, 40 CFR 268.42, U.S.
Environmental Protection Agency, Washington, D.C.
6. EPA. Universal Treatment Standards, 40 CFR 268.48, U.S. Environmental Protection
Agency, Washington, D.C.
7. EPA. Polychlorinated Biphenyls (PCBs) Manufacturing, Processing, Distribution in
Commerce, and Use Prohibitions, 40 CFR Part 761, U.S. Environmental Protection
Agency, Washington, DC.
Chapter II -High-Level Waste Requirements
II-38 DOE G 435.1-1
7-09-99
II. D. Complex-Wide High-Level Waste Management Program.
A complex-wide program and plan shall be developed as described under
Responsibilities, 2.B and 2.D, in Chapter I of this Manual.
Objective:
The objective of this requirement is to ensure that development, documentation, and
implementation of a complex-wide high-level waste management program. The complex-wide
program and plan establishes the framework within which individual site programs operate.
Discussion:
The Department’s management of high-level waste occurs at four sites that generate, store and
treat waste, as well as at a to-be-determined disposal site which is to serve as the nation’s central
repository for high-level waste and spent nuclear fuel. A complex-wide program and plan are
seen as necessary to establish the overall mission for the Department’s management of high-level
waste and to provide a framework within which the individual site programs operate. The
Radioactive Waste Management Manual, DOE M 435.1-1, General Requirements (Section I.2.B)
assigns the Assistant Secretary for Environmental Management’s the responsibility for developing
and maintaining complex-wide, waste-type programs. The Manual General Requirements
(Section I.2.D) also assigns the Deputy Assistant Secretary for Waste Management the
responsibility for developing and implementing complex-wide, waste-type program plans. The
complex-wide high-level waste management program and plan should be developed following the
guidance provided for General Requirements, Sections I.2.B and I.2.D.
Section 182
Compliance with this requirement is demonstrated by the presence of a Complex-Wide High-
Level Waste Management Program which includes the appropriate interfaces, technical
information data inputs, and other elements described in Chapter I of this Manual.
Supplemental References:
1. Toxic Substances Control Act, as amended, October 11, 1976.
2. EPA, 1992. Vitrification Technologies for Treatment of Hazardous and Radioactive
Waste, EPA Handbook, EPA/625/R-92/002, U.S. Environmental Protection Agency,
Washington, D.C., May 1992.
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-39
7-09-99
II. E. Site-Wide High-Level Waste Management Program.
In addition to the items in Chapter I of this Manual, documentation of the Site-
Wide Radioactive Waste Management Program shall include a description of the
High-Level Waste Systems Engineering Management Program to support
decision-making related to nuclear safety, including high-level waste requirements
analysis, functional analysis and allocation, identification of alternatives, and
alternative selection and system control.
Objective:
The objective of this requirement is to establish a structured and documented approach to
evaluating alternatives as the preferred method for reaching informed decisions on any issue
potentially affecting safety of high-level waste management safety systems, structures,
components and processes. Such decisions include selecting the solutions for storage and
treatment of high-level waste, through the design and fabrication of the hardware and the
development of software required (if any) to process the waste.
Discussion:
In addition to the Site-Wide Radioactive Waste Management Program requirements in DOE M
435.1-1, Section I.2.F.(1), this additional requirement applies specifically to the management of
high-level waste. The following guidance addresses that additional requirement only. Guidance
on the implementation of the General Requirements can be found in DOE G 435.1-1, Section
I.2.F.(1).
A systems engineering management program consists of requirements analysis, functional
analysis/allocation, synthesis (developing alternatives), and systems analysis (evaluation of
alternatives) and control. These elements of the process should be used progressively throughout
the life cycle of the program to achieve objectives and to re-define requirements, designs and
solutions for problems that may arise during program execution. A systems engineering
management program should invoke a graded approach consistent with the importance to safety
systems, structures, and components. Each of these elements is explained in detail in the interim
standard for Systems Engineering (EIA/IS 632). This Interim Standard is also referenced in the
Implementation Guide to DOE O 420.1. A brief overview of the systems engineering elements
extracted from the standard is presented below:
(1) Requirements Analysis: An analysis of the needs, objectives, and requirements in the
context of the mission, operations, environment, and the mandatory characteristics of the
system should be performed to determine the functional and performance requirements for
each primary system function.
Chapter II -High-Level Waste Requirements
II-40 DOE G 435.1-1
7-09-99
Section 183
An example of a functional requirement is to separate the high-level waste into a low
activity stream and a high activity stream to minimize the waste required for disposal in
the high-level waste repository. An example of a performance requirement is the percent
of the total radionuclide source term that must be concentrated in the high activity
stream (e.g. 98%) in order to qualify the low activity waste for non-repository disposal.
In other words, the functional requirements tell what must be done and the performance
requirements tell how well the function must be performed.
(1.1) Functional requirements identified in the requirements analysis should be used as
the top-level functions for the functional analysis. Identification of requirements
should include the degree of certainty in their estimate, their degree of criticality to
mission success and their relationship to other requirements.
(1.2) Requirements should be validated to establish traceability, both upwards and
downwards, so that each lower level requirement can be demonstrated to be
derived from a higher level requirement.
(2) Functional Analysis/Allocation: A functional hierarchy should be defined and integrated
down to the lowest level needed to support synthesis of solutions for people, products,
and processes and management of risks. More than one logical set of functional and
performance requirements could be developed to meet the high-level waste mission
objectives.
(2.1) Functional requirements should be analyzed to determine the subsidiary functions
required to accomplish the parent requirement.
For example, if the parent function is to separate the waste streams, subsidiary
functions may be wash the sludge and perform ion exchange.
When time is critical to the performance or sequencing of a function, a time-line analysis
should be performed. Functional requirements need to be logically sequenced with input,
output and interface requirements clearly defined and traceable.
(2.2) Functional allocation should be performed to establish a performance requirement
for each functional requirement. If all lower level functions are performed to meet
their performance requirement, the performance requirement of the highest level
function should also be satisfied.
Continuing the examples above, if sludge washing and ion exchange are the only
two subsidiary functions contained under the parent function “separate the waste
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-41
7-09-99
streams,” then their performance requirements together must produce a high
activity waste stream that contains 98% of the waste.
(2.3) Verification of functional and performance requirements should be accomplished
by traceability.
(3) Synthesis (develop alternative ways to meet the mission/objectives): Solutions for each
logical set of functional and performance requirements should be defined and designed.
This synthesis should be performed interactively with functional analysis/allocation to
define a complete set of potential solutions.
In the examples above, one logical solution may be to allocate the 98% concentration to
only 2 subsidiary functions, while an alternative solution would include three (or more)
subsidiary functions in order to remove additional radionuclide species.
(3.1) The output of the synthesis should describe the complete system, including
interfaces within the system and to external systems.
Section 184
(3.2) Care should be exercised to verify that the process and product design
requirements, and their implementation, satisfies the overall system requirement.
(4) Systems Analysis and Control: Systems analyses, trade-off studies and other analytical
tools should be utilized to select preferred alternatives. Decisions should be documented,
together with supporting material. Implementation of the selected alternative should be
coupled with control mechanisms, such as risk management, configuration management,
data management, and performance-based progress measurements, to assess status,
identify potential problems and to formulate alternative solutions for timely management
consideration.
The systems engineering management program documentation should include an approved
Systems Engineering Management Plan (SEMP), Systems Engineering Master Schedule (SEMS)
and a Systems Engineering Detailed Schedule (SEDS). The content of the SEMP, SEMS, and
the SEDS are explained in EIA/IS-632.
Outputs of the application of the systems engineering process ( inputs to decision making) should
be documented in an integrated decision data base that organizes the data used and generated.
The documentation should provide the audit trail of the systems engineering process outputs,
decisions and results, as well as traceability of the process. Traceability as used here is slightly
different from traceability used in the functional and performance analysis. Here the mission,
objectives, the environment under which the mission must be executed and mandatory overall
system performance is also included. Should any of these parameters change during the course of
Chapter II -High-Level Waste Requirements
II-42 DOE G 435.1-1
7-09-99
the project, this traceability will assist the decision manager to understand how the changes may
impact on the decisions previously made.
Compliance with this requirement is demonstrated by a systems engineering management
program based on EIA/IS-632, Systems Engineering, coupled with the identification of
accountable individuals and their authorities. The implementation guide to DOE O 420.1
references EIA/IS-632 as an acceptable standard for systems engineering.
Supplemental References:
1. EIA, 1994. Electronic Institutes Association, Systems Engineering, EIA/IS-632,
Washington, D.C., December 1994. (Standards Proposal No. 3537-A has been issued
which proposes to upgrade and revise EIA/IS-632. When the proposed upgrade and
revision is approved, the standard will be published as ANSI/EIA-632, and EIA-IS-632
will be CANCELED.)
2. DOE, 1995. Facility Safety, DOE O 420.1, U.S. Department of Energy, Washington,
D.C., October 13, 1995.
3. DOE, 1995. Implementation Guide for Nonreactor Nuclear Safety Design Criteria and
Explosive Safety Criteria, (Implementation guide for DOE 420.1), DOE G 420.1-1, U.S.
Department of Energy, Washington, D.C., September 1995.
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-43
7-09-99
II. F. Radioactive Waste Management Basis.
High-level waste facilities, operations and activities shall have a radioactive waste
management basis consisting of physical and administrative controls to ensure the
protection of workers, the public, and the environment. The following specific waste
management controls shall be part of the radioactive waste management basis:
(1) Generators. The waste certification program.
(2) Pretreatment and Treatment Facilities. The waste acceptance requirements
and the waste certification program.
Section 185
(3) Storage Facilities. The waste acceptance requirements and the waste
certification program.
Objective:
The objective of this requirement is to ensure that the hazards associated with high-level waste
management facilities, operations, and activities have been identified, their potential impacts
analyzed, and appropriate controls documented, implemented and maintained for the protection of
workers, the public, and the environment.
Discussion:
As described in the guidance on Section I.2.F.(2), DOE M 435.1-1 requires the radioactive waste
management basis to provide for development and documentation of measures to ensure the safe
and efficient management of radioactive waste. The measures include processes, procedures,
equipment specifications, instrument specifications, and other items that are intended to reduce
the likelihood of, or the consequences from, a problem that could arise from managing high-level
waste. Requiring an approved radioactive waste management basis for the initiation of new, or
continuation of existing, radioactive waste management activities should prevent the operation of
facilities for which safe design, configuration, and operation have not been demonstrated. The
required elements of the radioactive waste management basis vary with the type of waste
management operation or facility and the types of hazards associated with the operation or
facility. The radioactive waste management basis documentation listed above for each of the
three types of high-level waste management facilities, operations, and activities included in the
scope of DOE O 435.1 are not complete lists of those items which should be included in a
radioactive waste management basis. Several processes, procedures, and documents that are
required by other directives and requirements describe radioactive waste management measures
that should be considered part of the radioactive waste management basis.
Chapter II -High-Level Waste Requirements
II-44 DOE G 435.1-1
7-09-99
The guidance at Section I.2.F.(2) discusses this aspect of the radioactive waste management basis
in detail.
Example: At Site X a facility was designed and built for dry storage of vitrified high-
level waste encapsulated in welded stainless steel canisters. Prior to transferring any
high-level waste to the facility, the Field Element Manager reviewed and approved the
documentation that was prepared and collected for the purpose of establishing the
Radioactive Waste Management Basis. The documentation included two items required
by DOE M 435.1-1— the waste acceptance requirements and the waste certification
program. These two items are designed to ensure that the high-level waste transferred to
the facility is appropriate and that the high-level waste transferred from the facility meets
the waste acceptance requirements for the receiving facility. Additional documentation
that established the Radioactive Waste Management Basis was prepared in response to
requirements other than DOE M 435.1-1 and consisted of the facility-specific procedures
implementing the Site X radiological control program, health and safety plan, training
program, quality assurance program, and record-keeping plan.
Section 186
Also, as discussed in the Section I.2.F.(2) guidance, if a high-level waste management facility
operates under an approved Authorization Basis, it may not need any additional controls to
demonstrate that it has a radioactive waste management basis. In this case, the Authorization
Basis documentation should be reviewed and evaluated to determine whether it sufficiently covers
the requirements needed for a radioactive waste management basis. The Field Element Manager
has the responsibility to ensure the high-level waste management facilities under his or her
authority have a radioactive waste management basis.
Example: The Liquid Radioactive Waste Handling Facilities at Site A (which include the
Tank Farms, the In-Tank Precipitation Process, and the Replacement High-Level Waste
Evaporator) are used for management of highly radioactive and hazardous materials.
They are Category 2 nuclear facilities which renders them subject to a wide range of
DOE nuclear safety requirements. A review of the Authorization Basis documentation
revealed that the Authorization Basis includes the following documents and the
associated programs:
C Safety Analysis Reports (SARs)
C Technical Justification for Continued Operation/Basis for Interim
Operation/Design Basis Accident Analysis Report
C Operational Safety Requirements/Technical Safety Requirements
C Technical Standards
C SAR Update Request Packages
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-45
7-09-99
C Other Documents Identified by DOE-SR and WSRC as Authorization
Basis Documents (Safety Evaluations, Exemptions, Unreviewed Safety
Questions Evaluation)
C DOE Safety Evaluation Reports
C Listing of Documents that are to be Configuration Managed but are not
Authorization Basis Documents
Included within these documents are what the site considers to be the complete set of
operational requirements relied upon by the site to ensure that the public, workers, and
the environment are protected from the hazards associated with the management of the
radioactive waste handled in the facilities. For example, the establishment of limits of
fissionable material and chemical constituents that can be transferred to the waste tanks
by the generators is included in the SARs. These limits are essentially equivalent to the
limits that must be set for the waste acceptance requirements in this chapter (see Section
II. J). A radioactive waste management basis statement is prepared that concludes the
radioactive waste management basis is covered in the Authorization Basis documents.
For a facility that generates high-level waste, the radioactive waste management basis is to include
the program for certifying that waste meets the waste acceptance requirements of the facility(ies)
to which the waste will be sent. The waste certification program should be reviewed against the
applicable requirements of DOE M 435.1-1 and approved in accordance with the manual before
becoming part of the radioactive waste management basis. As discussed in guidance on Section
I.2.F.(2), several other processes and procedures are also part of the complete radioactive waste
management basis at a generating facility.
Example: A spent nuclear fuel reprocessing canyon generates high-level waste. The
radioactive waste management basis includes the waste certification procedures, the
safety and health plan, the training program, and the waste transfer procedure in
addition to the Authorization Basis. These elements are documented in a facility-specific
radioactive waste management basis statement covering the canyon, its operations, and
its activities.
Section 187
Facilities that store or treat high-level waste must have approved waste acceptance requirements
(Section II. J of DOE M 435.1-1) prior to the issuance of a radioactive waste management basis.
The waste acceptance requirements will usually suffice as the documentation of the radiological,
physical, and chemical limitations on waste that can be safely received at the facility, provided
they are developed correctly considering the hazards of the waste to be managed, and are kept up
to date. A facility that stores or treats waste is expected to have a waste certification program.
Waste from these facilities will have to be certified as meeting the waste acceptance requirements
of the facility to which it will be transported, and the facilities have the potential for generating
radioactive waste (e.g., secondary processing streams from treatment, monitoring and sampling,
Chapter II -High-Level Waste Requirements
II-46 DOE G 435.1-1
7-09-99
radioactive release cleanup). Consequently, storage and treatment facilities should also have an
approved waste certification program as part of their radioactive waste management basis.
Example: A storage facility that stores vitrified mixed high-level waste has approved
waste acceptance requirements and a waste certification process to verify that the waste
meets the Office of Environmental Management Waste Acceptance Product
Specifications for Vitrified High-Level Waste Forms (EM-WAPS). The radioactive waste
management basis statement references the waste certification process and the waste
acceptance requirement documentation, which in turn invokes the EM-WAPS. The basis
statement also cites the RCRA permit issued for storage of mixed high-level waste.
Requirements that apply to disposal of high-level waste have been developed by the Nuclear
Regulatory Commission and will be applied to the disposal facilities, operations, and activities of
the DOE Office of Civilian Radioactive Waste Management. Other facilities for high-level waste
management must be covered by an approved radioactive waste management basis. At the end of
the useful life of non-disposal facilities, most or all of the high-level waste will be removed in
preparation for closure. (In this discussion the word “all” is enclosed in quotes to suggest
removal of radioactive material to the extent that the facility can be released for unlimited use.) If
all of the high-level waste is removed, then the facility need no longer be considered a radioactive
waste facility and an approved radioactive waste management basis is no longer needed. In other
cases residual high-level waste will be in the facility being closed, and the facility will be subject to
an approved radioactive waste management basis. However, if the residual waste in the facility is
determined to be incidental to reprocessing, then the waste is managed as low-level waste or
transuranic waste, as appropriate. Under those conditions, either (1) the facility would be subject
to an approved radioactive waste management basis appropriate for the category of the remaining
radioactive waste as long as the waste remains in the facility or (2) the activities and operations
leading to release of the facility for unlimited use would be performed under a radioactive waste
management basis appropriate for the radioactive waste.
Section 188
As part of the radioactive waste management basis, site personnel should implement a system or
process for tracking the waste inventory at a storage, pretreatment or treatment facility. Tracking
the waste inventory is a means of ensuring that radionuclide limits established in accordance with
a safety analysis will not be exceeded. In addition, a system or process for accurately tracking
waste received at a facility can facilitate providing information to the complex-wide waste
management data system (see guidance for Section I.2.D.(2)).
Compliance with these requirements is demonstrated by a documented radioactive waste
management basis statement signed by the Field Element manager or a designee (see I.1.A,
Delegation of Authority) for each high-level waste management facility, operation, or activity.
Using a graded approach, it may be possible to include multiple activities under a single
radioactive waste management basis, but it should be possible to objectively identify which
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-47
7-09-99
activities are covered. Further, the radioactive waste management basis statement should include
or reference the measures that are established on a facility-specific basis to address the unique
waste management requirements and circumstances for each facility, operation, and/or activity.
Supplemental References:
1. DOE, 1996. Waste Acceptance Product Specifications for Vitrified High-Level Waste
Forms (EM-WAPS), Revision 2, DOE/EM-0093, U.S. Department of Energy,
Washington, D.C., December 16, 1996.
2. NRC. Disposal of High-Level Radioactive Wastes in Geologic Repositories, 10 CFR
Part 60, U.S. Nuclear Regulatory Commission, Washington, D.C.
Chapter II -High-Level Waste Requirements
II-48 DOE G 435.1-1
7-09-99
II. G. Quality Assurance Program.
The following requirements are in addition to those in Chapter I of this Manual.
(1) Product Quality. The requirements of DOE/RW-0333P, Quality Assurance
Requirements and Description, shall apply to those high-level waste items and
activities important to waste acceptance/product quality.
(2) Audits and Assessments. The evaluation and assessment requirements of
DOE/RW-0333P, Quality Assurance Requirements and Description, and
associated implementing procedures shall be met for high-level waste
acceptance and product quality activities, in addition to the assessment
requirements of other DOE directives and requirements identified in
Chapter I of this Manual.
Objective:
The objective of this requirement is to ensure that those items and activities important to waste
acceptance/product quality are identified and controlled by a quality assurance program that
implements the requirements of the Office of Civilian Radioactive Waste Management’s Quality
Assurance Program, as defined in DOE/RW-0333P, including the audit and assessment
requirements.
Discussion:
In addition to the quality assurance requirements contained in Section I. 1.E.(12), Quality
Assurance Program, of DOE M 435.1-1, General Requirements, the final high-level waste form
must meet the quality assurance requirements published by the Office of Civilian Radioactive
Waste Management . These quality assurance requirements are imposed on the waste form
Producers by Specification 4., “Quality Assurance Specification,” of the Waste Acceptance
Produce Specifications for Vitrified High-Level Waste Forms, DOE/EM-0093 (EM-WAPS).
The OCRWM requirements are contained in the “Quality Assurance Requirements and
Description for the Civilian Radioactive Waste Management Program (QARD),” (DOE/RW
0333P) which is the principal quality assurance document for the OCRWM Program.
Section 189
The QARD establishes the minimum elements of the quality assurance program and identifies the
program commitments necessary for the development and implementation of such a Quality
assurance program. As stated in the Introduction to the QARD, the QARD applies to the
following high-level waste activities: acceptance; transport and; high-level waste form
development through qualification, production, and acceptance.
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-49
7-09-99
The current revision of the QARD is organized into sections, supplements, appendices, and a
glossary. The 18 Sections contain requirements that are common to all OCRWM Program
activities including high-level waste activities such as high-level waste form development. The
five Supplements contain requirements for specialized activities, e.g, software, sample control,
field survey and the three Appendices contain requirements that are specific to the high-level
waste form production, storage and transportation, and the Mined Geologic Disposal System.
Waste form producers may, but are not required by OCRWM, develop specific quality assurance
procedures that comply with the requirements of the QARD, or they may modify existing
procedures, as necessary, to meet the QARD requirements. If the latter approach is taken, a
crosswalk to demonstrate how the QARD requirements are met by the site quality assurance
procedures should be generated.
Product Quality. Important to the subrequirement (1) is the concept that the QARD requirements
apply only to those high-level waste items and activities that have been designated as important to
waste acceptance/product quality. While a list of these items and activities is not included in
either the EM-WAPS or the QARD, their identification is essential for identifying the bounds of
applicability of the QARD. These items and activities are broadly defined as those which affect
the ability of the waste Producers to produce a canistered waste form that meets the EM-WAPS
requirements. Both of the existing vitrification facilities, DWPF and WVDP, have developed a
methodology for identifying such items and activities for their respective site and have maintained
a list of these items. Refer to these for further details on the approach taken at each site
(references included below).
Audits and Assessments. Subrequirement (2) requires that in addition to the audits and
assessments that are required under Section I.1.E., Requirements of Other Regulations and DOE
Directives, or Section I.2.F.(10), Evaluations, Section 18.0 of the QARD, Audits, establishes
specific requirements for performing internal and external Quality assurance audits to verify
compliance with, and to determine the effectiveness of, the Quality assurance program. Refer to
Section 18 for the specific requirements. In addition, numerous other assessment requirements
are contained throughout the QARD that must be met for those items and activities that are
applicable to the QARD requirements. Included are:
• Section 2.2.6 Surveillances
• Section 2.2.7 Management Assessments
• Section 2.2.8 Readiness Reviews
• Section 2.2.9 Peer Reviews
Responsibilities for conducting audits are identified in several documents. A Memorandum of
Agreement between the Office of Civilian Radioactive Waste Management and the Office of
Waste Management specifies quality assurance responsibilities between these two organizations
Chapter II -High-Level Waste Requirements
II-50 DOE G 435.1-1
Section 190
7-09-99
(see reference) while letters between the high-level waste sites and the Office of Waste
Management assign audit responsibilities between these organizations.
Compliance with this requirement is demonstrated by documented evidence that the requirements
of the QARD have been met for those items and activities that are determined to be waste product
quality affecting; and the QARD audit, readiness reviews, and assessment requirements have been
met.
Supplemental References:
1. DOE, 1997. Office of Civilian Radioactive Waste Management, Quality Assurance
Requirements and Description for the Civilian Radioactive Waste Management Program,
Revision 8, DOE/RW-0333P, U.S. Department of Energy, November 13, 1997.
2. DOE, 1996. Memorandum of Agreement Between the Office of Waste Management and
the Office of Civilian Radioactive Waste Management for Coordination of Quality
Assurance Activities Associated with High-Level Waste and Spent Nuclear Fuel, U.S.
Department of Energy, May 23, 1996.
3. DOE, 1996. Waste Acceptance Product Specification for Vitrified High-Level Waste
Forms, Revision 2, DOE/EM-0093, U.S. Department of Energy, December 1996.
4. DOE, 1997. WVDP Waste Acceptance Manual, Revision 7, WVDP-200, U.S.
Department of Energy, April 22, 1997.
5. DOE, 1996. DWPF Waste Acceptance Reference Manual, Revision 4, WSRC-IM-93-45,
U.S. Department of Energy, February 1996.
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-51
7-09-99
II. H. Contingency Actions.
The following requirements are in addition to those in Chapter I of this Manual.
(1) Contingency Storage. For off-normal or emergency situations involving
high-level waste storage or treatment, spare capacity with adequate
capabilities shall be maintained to receive the largest volume of waste
contained in any one storage vessel, pretreatment facility, or treatment
facility. Tanks or other facilities that are designated for high-level waste
contingency storage shall be maintained in an operational condition when
waste is present and shall meet all the requirements of DOE O 435.1,
Radioactive Waste Management, and this Manual.
(2) Transfer Equipment. Pipelines and auxiliary facilities necessary for the
transfer of waste to contingency storage shall be maintained in an
operational condition when waste is present and shall meet the requirements
of DOE O 435.1, Radioactive Waste Management, and this Manual.
Objective:
The objective of this requirement is to mitigate the impacts on the public, workers, and
environment in the event that a leak develops in a vessel storing high-level waste or in a facility
processing high-level waste. The mitigation is provided by ensuring spare waste storage capacity
is a required part of a site’s emergency management program. To meet this objective, there needs
to be both capacity to handle the largest volume of any single storage vessel or liquid waste in
process, and the capability to transfer the waste.
Discussion:
This requirement shall be implemented through and included in site emergency management
programs that are required by DOE O 151.1, Comprehensive Emergency Management System.
The directive DOE O 151.1 is referenced in DOE M 435.1-1, Chapter I and is considered
necessary for the safe management of radioactive waste. The Comprehensive Emergency
Management System requires the development of a complex-wide system for preparing for and
managing emergencies. At the site level, personnel are to establish an Operational Emergency
Base Program that provides the framework for responding to events involving, among other
impacts, health and safety, and the environment. The program requires a qualitative hazards
survey to identify the emergency conditions, describe the potential impacts, and summarize the
planning and preparedness requirements that apply.
Section 191
Chapter II -High-Level Waste Requirements
II-52 DOE G 435.1-1
7-09-99
During the development of the requirements of DOE M 435.1-1, Radioactive Waste Management
Manual, a waste management hazard and safety analysis identified the loss of confinement of a
storage tank or waste processing facility containing radioactive wastes as a hazard requiring
mitigation. In addition to requiring facility designs to maintain waste confinement (see
DOE M 435.1, Section II.P.(2)(b)), the ability to respond to leaks or other off-normal conditions
if they occur was also considered necessary. Consequently, the requirements to have adequate
spare capacity and the ability to transfer waste to the spare capacity were established. This
requirement is applicable to storage and processing of both liquid high-level waste and solid high-
level waste (e.g., calcine).
Operating procedures are to be developed and utilized for transfer of high-level waste to
contingency storage. The procedures need to address maximum operational capacities and limits
for components of the operational system (e.g., spare storage capacity available in vessels). The
procedures are to define and address all possible emergency transfer scenarios needed to comply
with this requirement.
Contingency Storage. Contingency storage is to be provided for both high-level waste storage
and for high-level waste pretreatment and treatment facilities. In the case of storage vessels,
adequate volumetric capacity must be available to receive the largest volume of waste stored in
any single vessel. In the case of pretreatment or treatment facilities, adequate capacity must be
available to allow in-process wastes in the facility to be moved as necessary to storage or holding
tanks in the event of emergency or off-normal conditions. These storage or holding tanks may be
other process vessels within the facility.
The requirement also requires that tanks, or other facilities, that are designated for high-level
waste contingency storage be maintained in an operational condition when waste is present and
that they meet all the requirements of DOE O 435.1 and DOE M 435.1-1. The operational
requirement is to ensure that all the elements required for safe operation of a functional high-level
waste storage tank that contains waste also are applied to a contingency storage tank. This is
intended to include the implementation of an approved authorization basis, or radioactive waste
management basis, as well as the implementation of operating procedures by trained and qualified
personnel. Development and implementation of these operational elements need to be planned
and completed prior to the designation of a tank or other facility as contingency storage since the
need for contingency storage may be urgent.
The requirement that contingency storage facilities meet all of the Order and Manual requirements
is recognized as demanding, and may be difficult for some DOE sites to meet. However, the
requirement is considered necessary due to the hazardous nature of high-level waste and the
potential consequences of loss of confinement of a tank’s contents. Of particular importance to
contingency storage units is complying with the requirements in Section II.Q, Storage, which
provides for a structural integrity program. As discussed in the guidance to Section II.Q, a
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-53
7-09-99
structural integrity program ensures structural strength and leak-tightness of all tanks designed for
use as high-level waste storage.
Section 192
The requirement in DOE M 435.1-1, Section II.H.(1) does not preclude the designation of
existing single-shell tanks (i.e., do not meet the secondary confinement (design) requirements of
DOE M 435.1 Section II.P.(2)(b)) present at some DOE sites, from being designated contingency
storage facilities. Existing single-shell tanks that can meet all the requirements of DOE M 435.1
1, Chapter II, without having to undergo significant modifications, may be candidates for
designation as contingency storage units. As explained in the guidance to DOE M 435.1-1
Section II.P.(2)(b) the secondary confinement requirements apply to new, and modifications to
existing, tanks. The requirement that must be met for single-shell tanks is the structural integrity
program (DOE M 435.1-1, Section II.Q.(2)) which includes elements such as verifying leak-
tightness and structural strength, identifying corrosion modes, and ultimately identifying the tank’s
safe operating envelope.
Spare capacity may be provided by a single vessel or by the combined available volume in multiple
vessels. In cases where radiation protection considerations allow, spare capacity could be
provided by portable vessels, tankers, e.g., rail-tank cars, or tank trucks if they meet the other
requirements of DOE M 435.1-1. Due to the potential for airborne radioactive material,
impoundments or bermed areas open to the air generally are not be used for spare storage
capacity.
Example: Liquid high-level waste is stored in six underground storage tanks with a
design capacity of 250,000 gallons each. The waste in the tanks has the same chemical
and radiological characteristics. One tank contains 200,000 gallons and each of the
others contain about 100,000 gallons. Capabilities exist to retrieve waste and transfer it
among the six tanks. This system meets the requirement because the largest volume of
200,000 gallons can be distributed between any two of the other tanks.
Spare capacity may be shared by different waste types, however mixing radioactive wastes of
different types needs to be evaluated and is generally not acceptable.
Example 1: A tank farm has tanks containing high-level waste which has been
determined not to be a mixed waste or high-level waste or has other tanks that are
contaminated with listed hazardous wastes. A spare empty tank is maintained and
available for emergency transfers of either waste.
Example 2: A tank farm contains both liquid high-level waste and liquid transuranic
waste in separate tanks. If the spare capacity were provided by excess capacity in tanks
that contain high-level waste, use of the capacity for transuranic waste would be
undesirable. Transferring transuranic waste into a tank containing high-level waste,
Chapter II -High-Level Waste Requirements
II-54 DOE G 435.1-1
7-09-99
would result in a mixture that would no longer be eligible for disposal at the Waste
Isolation Pilot Plant which, by law, cannot dispose of high-level waste. Therefore, waste
managers need to identify different spare capacity to accommodate the two different
waste types.
Section 193
In addition to the spare storage capacity discussed above, other measures may also need to be
implemented. An obvious action is to immediately stop the flow of any materials into the tank
system or tank annulus (if applicable), and inspect the system to determine the cause of the leak.
If the leak site is determined to be above the tank bottom, transferring tank contents until it is at a
level below the leak site would satisfy the requirement. Additionally, some tank systems include a
partial secondary liner in the form of a drain pan or a leak sump. In general the volume capacity
of these structures is limited; however, the viability of recirculating leaked contents from these
structures to the primary tank or vessel as an initial mitigation measure may be assessed. Such re
circulation may preclude the release of a leaking tank’s contents to the soil, while contingency
transfer and storage systems are being prepared to remove the contents from a leaking tank or
vessel.
Transfer Equipment. The ability to perform the transfer is just as important as having the
capacity. Equipment necessary to transfer each vessel or treatment facility volume of high-level
waste in the event of a leak or other off-normal condition is to be identified and documented.
Example: Calcined radioactive waste is stored in six underground bins with a capacity
of 10,000 cubic feet each. The waste in all of the bins is similar, and each bin contains
3,000 cubic feet of calcined high-level waste. Although there are transfer lines to any of
the bins from a central diversion box, the bins were constructed without the capability to
retrieve the waste. This situation does not comply with the requirement at II.H.(2).
Although there is adequate capacity, the ability to transfer the waste does not exist. An
exemption would be required.
In addition, mechanisms must be in place to ensure the equipment identified as necessary to
transfer the contents of each tank can be made available quickly. One approach is to inspect
and/or test the identified equipment and components, as part of a routine waste management
maintenance program (see DOE M 435.1-1, Section I.1.E.(9)).
If the cost of procuring and maintaining such items is economically impractical, an acceptable
alternative would be to have agreements with vendors to procure the necessary equipment and
have it shipped to the site within a specified period of time. Under this approach the use of other
mitigative measures to reduce impacts to the environment from a leaking tank or vessel may be
necessary. Such mitigative measures might include re-circulation of leaked contents from sumps
or pans to the primary tank, as discussed above, or the initiation of emergency remediation actions
in accordance with facility emergency plans.
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-55
7-09-99
The capability to perform an emergency transfer of high-level waste is to be maintained at all
times. Procedures need to be prepared and operations personnel qualified in the operation of
equipment and those procedures necessary for the transfer of high-level waste to contingency
storage facilities.
Example: A large shielding block is in place over a diversion box that needs to be
accessed during an emergency transfer of high-level waste. The block must be moved by
a crane. Therefore, a suitable crane must be on-site or an agreement with a vendor that
such a crane can be delivered within a specified time period, is in place. Additionally,
operators qualified to operate valves within the diversion box must be available when
needed.
Section 194
Many DOE sites have agreements in place with their State and/or EPA regulators that may
overlap, or conflict, with the requirements in this section. Obviously such agreements must be
honored and the intent of these requirements is not to interfere with them. Thus, some
interpretation of these requirements will be necessary to ensure that spare waste storage capacity
is available and that the necessary transfer equipment is available on a real time basis, i.e., at the
earliest practicable time.
Compliance with these requirements is demonstrated if adequate spare capacity and transfer
equipment exist for emergency transfers of all high-level waste. This includes maintaining high-
level waste contingency storage facilities and transfer equipment/facilities in an operational
condition when waste is present.
Supplemental References:
1. DOE, 1995. Comprehensive Emergency Management System, DOE O 151.1, U.S.
Department of Energy, Washington, D.C., September 25, 1995.
Chapter II -High-Level Waste Requirements
II-56 DOE G 435.1-1
7-09-99
II. I. Corrective Actions.
The following requirements are in addition to those in Chapter I of this Manual.
(1) Order Compliance. Corrective actions shall be implemented whenever
necessary to ensure the requirements of DOE O 435.1, Radioactive Waste
Management, and this Manual are met.
Objective:
The objective of this requirement is to ensure that actions will be taken to preclude, minimize, or
mitigate hazards whenever a situation arises at a high-level waste management facility that could
threaten worker or public safety, or the environment.
Discussions:
DOE M 435.1-1, Section I.2.G, states that all personnel have a responsibility to identify
conditions that require corrective actions to achieve compliance with the Order and Manual
requirements or to address health and safety conditions that pose an imminent or possible danger.
The Manual states that this responsibility includes considering shutdown or curtailment of
facilities and activities, if warranted by the seriousness of the circumstances. This requirement
ensures that this responsibility is implemented for all high-level waste management facilities and
activities. DOE M 435.1-1, Section I.2.F.(20), requires the Field Element Manager to ensure that
a process exists for proposing, reviewing, approving, and implementing corrective actions when
necessary to ensure that the requirements of DOE O 435.1 and DOE M 435.1-1 are met, and to
address conditions that are not protective of the public, workers, or the environment.
Corrective actions are activities which, when implemented, will correct a noncompliant or
hazardous condition. These activities can include improvements to documentation (e.g.,
procedures, plans, authorization basis documents), training and qualification programs or
procedures, physical and process design changes, changes to operating conditions, or a
combination of these activities.
Corrective Action System. A corrective action system exists for addressing noncompliant or
hazardous conditions for high-level waste management facilities, operations and activities.
Corrective actions in response to quality assurance program assessments are addressed in the
Implementation Guide for Use with Independent and Management Assessment Requirements of
10 CFR 830.120 and DOE O 414.1, Quality Assurance. The corrective action system provides
for documenting noncompliant or hazardous conditions, identifying the organizations or
individuals responsible for developing and implementing corrective actions, providing corrective
action status, and tracking progress through final implementation of the actions. The corrective
Section 195
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-57
7-09-99
action system is instituted as a fundamental part of the systematic evaluation of radioactive waste
activities that is implemented by the site-wide radioactive waste management program (see
guidance for Section I.2.F.(1)).
A problem requiring corrective action could range from a minor deviation from a procedure, to a
situation that poses an immediate threat to health and safety from an uncontrolled release of large
quantities of radioactive material. For situations where a problem could pose an immediate risk to
a worker, member of the public, or damage to the environment, immediate shutdown of the
process or facility may be appropriate as the first step in addressing the problem. (see guidance for
Section II. I.(2)).
Example: An employee of the Site K high-level waste vitrification facility noticed that
the procedure for taking a high-level waste slurry sample was not being followed
correctly by a waste technician. Such action could allow a release of high-level waste
slurry into the facility’s operating corridor from the sampling station. The employee
alerted the sampling shift manager who in turn alerted the facility operations manager.
The facility corrective action system resulted in a corrective action plan that identified
the sampling station manager as the responsible individual for assuring proper training
of operations personnel on implementing sampling procedures. A reminder memo was
sent to the affected staff and a follow-up review was scheduled for 45 days after the
occurrence.
If a facility or activity can be allowed to operate while a noncompliant or hazardous condition
exists, the allowance and any associated limitations must be defined as part of the facility or
activity’s radioactive waste management basis and/or authorization basis documentation,
identified as a configuration controlled item in a configuration management plan or included in a
revision or modification to an operating procedure or similar controlled documentation. If a
noncompliance impacts safety associated with use of a procedure, system, or facility, the
corrective action system must provide for preventing the use (e.g., locking out) of the affected
procedure, system, or facility.
Example: In the example above, slurry sampling activities were curtailed so that no
slurry sampling was allowed. Due to the potential for a release of high-level waste slurry
into the operating corridor of the facility and significant personnel contamination, waste
sampling activities were curtailed until operator training was completed.
Compliance with this requirement is demonstrated if a corrective action system addresses
noncompliant or hazardous situations involving high-level waste management facilities in a
systematic fashion, and allows identification of problems by all personnel.
Chapter II -High-Level Waste Requirements
II-58 DOE G 435.1-1
7-09-99
Supplemental References:
1. DOE, 1996. Implementation Guide for Use with Independent and Management
Assessment Requirements of 10 CFR 830.120 and DOE O 414.1 Quality Assurance,
DOE G 414.1-1, U.S. Department of Energy, Assistant Secretary for Environment, Safety
and Health, Washington, D.C., August 1996.
II. I.(2) Operations Curtailment. Operations shall be curtailed or facilities
shut down for failure to establish, maintain, or operate consistent with
an approved radioactive waste management basis.
Objective:
Section 196
The objective of this requirement is to limit the operation of waste management activities and
facilities as necessary to avoid creation of near- or long-term safety or environmental hazards.
Discussion:
DOE M 435.1-1 requires that a radioactive waste management basis be established for each
radioactive waste management activity or facility. The radioactive waste management basis is to
include those additional constraints specific to waste management activities (e.g., requirements of
the Manual) that are determined to be necessary for safety and environmental protection. Field
Element Managers are responsible for ensuring a radioactive waste management basis is
developed, reviewed, approved, and maintained for each DOE radioactive waste management
facility, operation, or activity. (DOE M 435.1-1, Section I.2.F.(2)). The guidance for that
requirement should be consulted for additional details on the development, review, and approval
of a radioactive waste management basis. Also, additional discussion concerning the radioactive
waste management basis for high-level waste generator, pretreatment, treatment, and storage
facilities is discussed under guidance for the requirement at Section II. F.
As part of his or her responsibilities for maintaining the radioactive waste management basis for
high-level waste management facilities, operations, and activities under his/her authority, the Field
Element Manager evaluates the compliance of the facilities, operations, and activities with the
constraints and controls documented in the radioactive waste management basis by ensuring that
routine assessments are conducted. If the Field Element Manager determines, either through
routine assessment or by virtue of an occurrence or off-normal event, that a facility, operation, or
activity is not operating in compliance with an approved radioactive waste management basis, the
operation must be curtailed or shut down. The action taken is commensurate with the hazards
associated with the noncompliance and with the continued operation of the facility.
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-59
7-09-99
This requirement is to be implemented in a graded manner. Actions to be taken are based on
assessments of adherence to radioactive waste management bases, and can range from shutdown
of an operation or facility to placing limits or constraints on what activities can be performed or
how the activities are to be performed. Shutdown of a facility involves stopping all operations in
the facility except surveillance or monitoring activities necessary to maintain the facility in a safe
standby condition. Shutdown is considered appropriate when there is either a potential imminent
threat to safety or environmental protection that cannot be mitigated, or a blatant failure to
establish or comply with a radioactive waste management basis.
Alternatively, there may be cases where the facility, operation, or activity assessment determines
that the radioactive waste management basis is not current or has been violated but there is no
imminent threat to public, worker, or environmental protection. In such a case, the Field Element
Manager may decide that shutdown of the facility is not necessary. It may be sufficient to impose
certain limits until the radioactive waste management basis is made current. The limits imposed
may prohibit the generation, receipt, or processing of certain waste streams, or may involve
constraints on the processes that may be performed.
Section 197
Example: Site Z conducts biennial assessments of high-level waste Evaporator Y for
compliance with its radioactive waste management basis. The 1996 biennial assessment
found two non-compliance findings and five observations. The corrective action system
implemented at Site Z requires the non-compliance findings to be entered and formally
responded to with corrective action plans, but not the observations. The non
compliances were in document control and operations training, so evaporator operations
were not curtailed in any way while both the document control and training procedures
were revised. The facility was assessed again in 1997 to determine if the corrections
were in place, which was an accelerated assessment schedule from the normal biennial
assessments.
The action taken in response to the failure to establish a radioactive waste management basis is to
be clearly documented in a formal communication (e.g., letter, memorandum). Such
communication needs to identify the reason for the shutdown or curtailment, and identify what is
necessary to initiate restart. Generally, development of a corrective action that is implemented
through the corrective action system, as discussed in the preceding section, would be appropriate
for responding to a shutdown or curtailment of activities at a high-level waste management
facility.
In concert with Core Requirement #6 of the Integrated Safety Management System, “Feedback
and Improvement,” the Field Element Manager should use the audits and assessments to identify
opportunities for improvement in the implementation of an activity or facility’s radioactive waste
management basis. Identified improvement actions should be shared with like organizations and
tracked by management to determine whether they are yielding the anticipated improvements.
Chapter II -High-Level Waste Requirements
II-60 DOE G 435.1-1
7-09-99
Communicating the results of assessment upward in the DOE and contractor organization will
allow the findings to reach the management level with the authority necessary to effect
improvements.
Compliance with this requirement is demonstrated by a documented system of routine
assessments to determine whether waste management activities and facilities are operating in
accordance with an approved radioactive waste management basis that provides for graded
limitations that can be placed on activities and operations that do not have, or are operating
outside of, an approved radioactive waste management basis, including shutdown of the facility.
Supplemental References:
1. DOE, 1996. Safety Management System Policy, DOE P 450.4, U.S. Department of
Energy, Washington, D.C., October 15, 1996.
2. DOE, 1997. Line Environment, Safety and Health Oversight, DOE P 450.5, U.S.
Department of Energy, Washington, D.C., June 26, 1997.
3. DOE, 1997. Safety Management Functions, Responsibilities, and Authorities Policy,
DOE P 411.1, U.S. Department of Energy, Washington, D.C., 1997.
4. DOE, 1997. Manual of Safety Management Functions, Responsibilities, and Authorities,
DOE M 411.1, U.S. Department of Energy, Washington, D.C., October 8, 1997.
5. DOE, 1999. Implementation Plan for Defense Nuclear Facilities Safety Board
Recommendation 98-1, Department of Energy Plan to Address and Resolve Safety Issues
Identified by Internal Independent Oversight, U.S. Department of Energy, Washington,
D.C., March 10, 1999.
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-61
7-09-99
Section 198
II. J. Waste Acceptance.
The following requirements are in addition to those in Chapter I of this Manual.
(1) Technical and Administrative. Waste acceptance requirements for all high-
level waste storage, pretreatment, or treatment facilities, operations, and
activities shall specify, at a minimum, the following:
(a) Allowable activities and/or concentrations of specific radionuclides;
(b) Acceptable waste form that ensures the chemical and physical
stability of the waste under conditions that might be encountered
during transfer, storage, pretreatment, or treatment;
(c) The basis, procedures, and levels of authority required for granting
exceptions to the waste acceptance requirements shall be contained in
each facility’s waste acceptance documentation. Each exception
request shall be documented, including its disposition as approved or
not approved; and
(d) Pretreatment, treatment, storage, packaging, and other operations
shall be designed and implemented in a manner that will ultimately
comply with DOE/EM-0093, Waste Acceptance Product Specifications
for Vitrified High-Level Waste Forms, or DOE/RW-0351P, Waste
Acceptance System Requirements Document, for non-vitrified
immobilized high-level waste.
Objective:
The objectives of the waste acceptance requirements are to ensure that: high-level waste which is
to be received at a facility contains only the radionuclides that the facility can safely manage, and
only in concentrations and/or total activities which are compatible with the work to be undertaken
in the facility; no high-level waste management activity jeopardizes compliance with waste
disposal specifications, including DOE/EM-0093, Waste Acceptance Product Specifications for
Vitrified High-Level Waste Forms (EM-WAPS), or DOE/RW-0351P, Waste Acceptance System
Requirements Document (WASRD), for non-vitrified immobilized high-level waste; and formal
procedures exist and a decision process is clear concerning the granting of exceptions to waste
acceptance requirements.
Chapter II -High-Level Waste Requirements
II-62 DOE G 435.1-1
7-09-99
Discussion:
As discussed in the guidance to DOE M 435.1-1, Section I.2.F.(6), the waste acceptance
requirements establish the conditions for waste that facilities can safely receive. Therefore, the
acceptance requirements for high-level waste storage, pretreatment, or treatment facilities,
operations and activities include all requirements that high-level waste must meet to be acceptable
for receipt, and for the subsequent storage, pretreatment, or treatment that it will undergo.
In conducting the analyses for development of the DOE M 435.1-1 requirements, minimum
acceptance requirements that must be specified in waste acceptance documentation for storage,
pretreatment, and treatment facilities that must be specified in the waste acceptance
documentation for these types of high-level waste management facilities in order for high-level
waste to be safely handled were identified. Guidance on subrequirement (a) is provided below
under Radionuclide Content or Concentration. Guidance on subrequirement (b) is provided under
Waste Form. Guidance on subrequirement (c) is provided under Exceptions. Guidance on
subrequirement (d) is provided under Waste Acceptance Product Specifications.
Section 199
Development of Waste Acceptance Requirements. A facility receiving high-level waste for
storage, pretreatment, or treatment is required to document the waste acceptance requirements
for the facility. These requirements have their foundation in facility design capabilities such as
volume, handling, weight, allowable contents, and radiological limits (i.e., criticality, radiation,
contamination). Other requirements may include any number of regulations promulgated by the
EPA, NRC, DOT, the host state, and DOE itself. The designer and operator of the facility
receiving waste are likely to be most knowledgeable of the requirements and limitations of the
facility and, therefore, are in the best position to establish the waste acceptance requirements or
criteria that must be met for waste sent to the facility.
DOE is planning to dispose high-level waste in a geologic repository consistent with the Nuclear
Waste Policy Act of 1982, as amended. This plan was outlined in Secretary Hodel’s letter to
President Reagan (DOE, 2/6/85), in which the Secretary recommended that “the Department
proceed with plans and actions to dispose of defense waste in a commercial repository.”
President Reagan’s finding, in accordance with Section 8 of the Nuclear Waste Policy Act of
1982, as amended (Presidential memo, 4/30/85), was that he found no basis to do otherwise and
the Department has since implemented plans to dispose high-level waste in a geologic repository
consistent with the Nuclear Waste Policy Act of 1982, as amended.
The DOE Office of Civilian Radioactive Waste Management has issued the WASRD that
describes the functions to be performed and the technical requirements for a Waste Acceptance
System for accepting spent nuclear fuel and high-level radioactive waste into the Civilian
Radioactive Waste Management System. From this document, the Office of Environmental
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-63
7-09-99
Management has developed and implemented the EM-WAPS. Additional information on this
document is discussed below under Waste Acceptance Product Specifications.
Personnel responsible for high-level waste storage, pretreatment, or treatment facilities are to
consider the EM-WAPS in developing waste acceptance criteria. Criteria to be considered
include limiting the concentrations of species that may inhibit the formation of glass, organic
compounds, and RCRA-listed hazardous wastes.
The waste acceptance requirements and documentation for a facility receiving waste for storage,
pretreatment, or treatment are prepared using a graded approach commensurate with the hazards
associated with the management of the waste in the facility and the complexity of the activities to
be conducted in the facility and upon the waste. The waste acceptance requirements document
for a facility which receives large quantities of high-level waste, or high-level waste with highly
variable contents, or both, may need to address many hazards and consequently may be more
detailed. By contrast, an immobilized high-level waste storage facility that stores only EM-WAPS
compliant waste may only need a minimal set of requirements.
Section 200
The EM-WAPS, legislation, regulations, safety analysis reports, technical safety requirements,
criticality analyses, and other appropriate safety or authorization basis documents are used to
establish the waste acceptance criteria for facilities receiving high-level waste for storage,
pretreatment, or treatment. These documents and analyses provide the basis for radioactivity
(concentration and inventory) limits, allowable chemical content, waste form and/or packaging
stability requirements, and other necessary waste canister or waste form requirements to ensure
that the facilities design bases, performance, and operating bases are not compromised.
Radionuclide Content or Concentration. Radiological limits for storage, pretreatment, and
treatment facilities may be derived from a number of technical as well as administrative sources.
In developing limits for radionuclide concentrations, personnel need to consider storage and
treatment facility limitations, the EM-WAPS, safety analysis reports, and criticality analyses.
At many high-level waste management sites, the storage and treatment facilities require the
control of certain constituents or concentrations of species to ensure safe storage, pretreatment
and treatment of the waste. Such limits, for example, support corrosion protection, prevent the
accumulation of flammable or explosive species, limit the radionuclide content, or meet regulatory
limits. Storage, pretreatment, and treatment facilities need to include appropriate waste
acceptance requirements that protect their authorization or radioactive waste management basis.
The current EM-WAPS for vitrified waste forms contains a number of specifications to be
considered during the development of the waste acceptance requirements for high-level waste
pretreatment and treatment facilities. These include Specification 1.5, “Hazardous Waste,” which
precludes the inclusion of RCRA-listed components in the final high-level waste form, and
Chapter II -High-Level Waste Requirements
II-64 DOE G 435.1-1
7-09-99
Specification 3.5, “Chemical Compatibility,” which requires that the waste producer ensure that
the final waste form is compatible with the canister material.
The safety analysis report or authorization basis for a high-level waste management facility may
identify specific radionuclides that warrant special attention from a worker safety standpoint or an
offsite release standpoint due to an upset or accident condition.
Example: At Site Z the safety analysis for the high-level waste tank farm has established
a limit on the concentration of Cs-137 in Type V Tanks to < 0.6Ci/gal. This limit is set
for these tanks because they do not have secondary confinement. The limit ensures that
the risk of the Cs-137 reaching the environment is comparable to the accepted risk
associated with the waste in a double confinement tank.
Any criticality analyses conducted in accordance with the Criticality Safety Program in
conformance with DOE M 435.1-1, Section I.1.E.(4), may also result in limitations on acceptance
of fissile radionuclides. These limitations should be included in the waste acceptance
requirements, as appropriate.
Section 201
Waste Form. Waste acceptance requirements specify that wastes received at the facility are in a
physically/chemically stable form. Waste acceptance requirements for a high-level waste
pretreatment or treatment facility need to specify the physical and chemical precautions and
conditions under which untreated waste can be received at the facility so that facility safety and
effective operations will not be compromised. Any physical or chemical stabilization of waste
prior to transfer to a facility receiving waste for storage, pretreatment, or treatment needs to be
done according to a systematic process that includes consideration of bench-scale testing and
verification that the process is producing satisfactory results.
The waste acceptance requirements need to specify waste streams, classes, or categories of waste
requiring application of specific physical or chemical stabilization methods, as determined by the
results of safety analyses. Acceptable waste streams or waste forms are specified by the waste
acceptance requirements. The waste acceptance requirements also need to identify any of the
following specific technical requirements that must be included to ensure that waste received at
any storage, pretreatment, or treatment facility is consistent with the operating/authorization basis
of the facility:
C allowable heat generation rates;
C any specific radionuclides or chemical or hazardous materials that are prohibited
from acceptance at the facility. This may include pyrophoric materials, explosives,
or materials that might cause violent reactions during storage, pretreatment, or
treatment; and
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-65
7-09-99
C any specific requirements associated with acceptance of high-level waste needing
out-of-the-ordinary attention for receipt, storage, pretreatment, or treatment.
Exceptions. Waste acceptance requirements are established to ensure that facilities can safely
manage the waste received for storage, treatment, or disposal. Waste acceptance requirements
need to be documented, contain clear and precise criteria specifying the radionuclide limits in the
form of contents or concentrations that can be accepted, the limitations and prohibitions on waste
streams received, and the limits, prohibitions, or instructions concerning any other technical
information to assure that the waste is compatible with the safety basis of the facility, and which
will result in acceptable waste at subsequent steps in managing the high-level waste. Thus,
exceptions or deviations to waste acceptance criteria must not be routine and must be carefully
reviewed and documented. The procedures for granting exceptions need to clearly state the entire
process for requesting an exception, describe acceptable bases for granting exceptions, and
identify any additional information that is needed to supplement the documentation normally
provided for waste transfers. The approval process is clearly stated, including identification of the
officials who have the authority to approve the exception.
Example: At Site Y, the transfer of a high-level waste solution that is non-compliant with
one or more of the receiving facility-specific waste acceptance requirements may be
requested, and allowed, because analysis concludes that blending of the transferred
waste with the existing tank inventory will result in the blended tank waste being
compliant with the receiving tank’s waste acceptance requirements. The Site Y procedure
includes an administrative process that requires a technical basis for the proposed
exception and requires the appropriate reviews, approvals and documentation.
Section 202
Waste Acceptance Product Specifications. This subrequirement is intended to ensure that any
high-level waste management activities such as storage, pretreatment, treatment, packaging, and
any other operations shall be conducted in a manner that will facilitate the acceptance of the final
immobilized high-level waste form by the Office of Civilian Radioactive Waste Management. The
current EM-WAPS include are the technical specifications that waste form producers are required
to meet in order to ensure acceptance of their vitrified high-level waste into the Civilian
Radioactive Waste Management System. The Office of Environmental Management (EM) and
the Office of Civilian Radioactive Waste Management have agreed the Office of Environmental
Management is to provide the final waste form specifications to the waste form producers and the
Office of Environmental Management will ensure that the EM-WAPS is consistent with the
technical baselines as defined in the WASRD. The EM-WAPS governs all elements of the final,
canistered, waste form which includes the borosilicate waste glass, the stainless steel canister, and
the sealed canistered waste form.
Chapter II -High-Level Waste Requirements
II-66 DOE G 435.1-1
7-09-99
As waste form requirements for immobilized high-level waste were developed, the Department
and its operating contractors selected borosilicate glass as a reference waste form. Several high-
level waste sites subsequently identified a vitrified waste form for their sites, and two high-level
waste vitrification facilities are currently operating to produce canisters of borosilicate waste-
glass. The EM-WAPS was written to such borosilicate glass specifications. Recently, however,
several new high-level waste streams have been identified. One such high-level waste stream is
the proposed insertion of small immobilized surplus plutonium containers within a standard high-
level waste canister. Molten vitrified high-level waste is then poured around these plutonium cans
yielding a matrix immobilized waste form. This composite high-level waste stream is considered
high-level waste and can be disposed as such. Another proposed high-level waste stream results
from immobilizing the waste resulting from reprocessing certain spent nuclear fuels using an
electro-metallurgical process. In this case a non-vitrified waste form will result. In both these
cases a product that adheres to all the existing requirements of DOE/EM-0093, Waste Acceptance
Product Specifications for Vitrified High-Level Waste Forms, is not possible. The exact waste
form specifications that these two proposed waste forms must meet are unknown at this time;
however, they will be incorporated in DOE/RW-0351P, Waste Acceptance System Requirements
Document. That document is therefore cited for those unique immobilized high-level waste forms
that cannot meet the requirements of DOE/EM-0093, Waste Acceptance Product Specifications
for Vitrified High-Level Waste Forms (EM-WAPS).
The waste acceptance process requires demonstration of compliance with the EM-WAPS via four
different documents, each prepared by the waste producers, reviewed and accepted by the Office
of Environmental Management, and provided to the Office of Civilian Radioactive Waste
Management. These four documents are: the Waste Form Compliance Plan (WCP); the Waste
Form Qualification Report (WQR); production records and; the storage and shipping records.
The producers included in Revision 2 of the EM-WAPS are Savannah River Site, the West Valley
Demonstration Project, and Hanford. Decisions on a final waste form at the Idaho National
Environmental Engineering Laboratory have not progressed to the point that it has been included
in the current EM-WAPS.
Section 203
The EM-WAPS provides detailed specifications that must be met by the producers in order for
the final waste form to be acceptable to the Civilian Radioactive Waste Management System for
disposal. Amplification on these specifications is considered beyond the scope of this guidance.
Reference is made to existing Waste Compliance Plans for Defense Waste Processing Facility and
the West Valley Demonstration Project, both of which provide a detailed description of the
methods by which they comply with each specifications. Following are the titles of each of the
summaries specification within the EM-WAPS:
• Waste Form Specifications;
• Canister Specifications;
• Canistered Waste Form Specifications;
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-67
7-09-99
• Quality Assurance Specification; and
• Documentation and Other Requirements.
Example: At Site Z, a vitrification operation’s analysis concluded the potential for a
significant savings in plant operating labor costs if the welding of canisters could be
delayed until the vitrification melter operations were shut down for maintenance, which
was normally every 30 days. Thus the proposal was to stage unwelded canisters in the
facility, for as long as 30 days, until melter operations personnel were free to make the
closure welds. However, review of the facility’s Waste Compliance Plan, Waste
Qualification Reports, and the EM-WAPS determined that there was a risk that organic
contaminants may enter the open canisters that would be held for welding. Such
contamination would violate the EM-WAPS, Specification 3.4, Organic Materials
Specification, and the plan was rejected.
Compliance with these requirements is demonstrated by waste acceptance requirements that are
well documented and contain clear and precise criteria specifying: allowable activities and
concentrations; acceptance forms; a clear description of the process for obtaining an exception to
the acceptance criteria; and operations shall be implemented in a manner that does not jeopardize
the final waste form’s ability to meet the EM-WAPS.
Supplemental References:
1. DOE, 1999, Waste Acceptance System Requirements Document, Revision 3, DOE/RW
0351P, U.S. Department of Energy, Washington, D.C., April 1999.
2. DOE, 1996. Waste Acceptance Product Specification for Vitrified High-Level Waste
Forms, Revision 2, DOE/EM-0093, U.S. Department of Energy, December 1996.
3. DOE, 1994. DWPF Waste Form Compliance Plan, Revision 4, WSRC-IM-91-116-0,
U.S. Department of Energy, December 1994.
4. DOE, 1997. Waste Form Compliance Plan for the West Valley Demonstration Project
High-Level Waste Form, Revision 12, WVDP-185, U.S. Department of Energy,
December 1997.
5. DOE, 1985. An Evaluation of Commercial Repository Capacity for the Disposal of
Defense High-Level Waste, DOE/DP/0020/1, U.S. Department of Energy, Washington,
D.C., June 1985.
Chapter II -High-Level Waste Requirements
II-68 DOE G 435.1-1
7-09-99
6. Hodel, 1985. Secretary Hodel to President Reagan, memorandum, Use of Commercial
Repository for Disposal of Defense High-Level Nuclear Waste, U.S. Department of
Energy, Washington, D.C., February 6, 1985.
7. Reagan, 1985. President Reagan to Secretary Herrington, memorandum, Disposal of
Defense Waste in a Commercial Repository, Washington, D.C., April 30, 1985.
II. J.(2) Evaluation and Acceptance. The receiving facility shall evaluate
waste for acceptance, including confirmation that the technical and
administrative requirements have been met. A process for the
disposition of non-conforming wastes shall be established.
Section 204
Objective:
The objective of this requirement is to establish a process by which a facility receiving high-level
waste for storage, pretreatment, or treatment determines that the waste being transferred is
acceptable in accordance with the waste acceptance requirements and for that process to
specifically address the management of waste that does not conform with all of the requirements
when it is received at the facility.
Discussion:
This requirement makes it the responsibility of officials at a facility to which waste is transferred
to confirm that waste is in compliance with the established waste acceptance requirements, and
also to provide a mechanism by which the officials confirm that waste can be accepted and safely
managed at the facility.
Evaluation and Acceptance. The methodology for implementing the evaluation and acceptance of
high-level waste needs to be flexible and defined on a facility-specific basis. The complete process
and procedures, including the responsibilities of the generating facility, need to be clearly
documented so that both the generator and the facility receiving the waste understand the process
that will be used. As with the implementation of other parts of the DOE M 435.1-1, this
requirement is implemented using the graded approach. Facilities receiving high-level waste from
many generators may need to implement more detailed waste evaluation and acceptance processes
than a facility receiving waste from a few generators.
The evaluation and confirmation process consists of one or more of the following approaches that
can contribute to high confidence that the waste presented meets the waste acceptance
requirements of the facility receiving waste for storage, pretreatment, or treatment:
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-69
7-09-99
C Testing, sampling, and analysis of the contents of a representative sample of waste
packages as they are received at the facility;
C Testing and analysis of a number of samples taken by the generator facility;
C Detailed review of sampling and analysis data generated by the sending facility or
an independent laboratory employed by the generating facility;
C Audit, surveillance, or observation of the sender’s waste characterization activities
and processes and waste certification programs.
Testing, sampling, and analysis of the contents of a representative sample of waste is complicated
by the fact that additional risk is posed because of the process required to take and analyze a
liquid sample. Therefore, consideration is given to the additional risk and potential worker dose
when deciding which approach is appropriate. Likewise, analysis of the samples taken by the
generator may involve additional risk, and also may be expensive to implement. If this method is
employed, samples which are representative, either statistically or correlated with generator
profiles, need to be obtained for analysis. This sampling includes samples from the generators
sending the greatest amount of waste to the facility for storage, pretreatment, or treatment; or
samples containing the critical radionuclides as identified in the waste acceptance requirements.
The use of detailed reviews of the sampling and analysis data gathered by others needs to include
an evaluation of the methodologies used for collecting the sample, maintaining the integrity of the
sample and data (e.g., through a chain of custody), and performing chemical analyses and
radioanalyses. As above, the samples collected need to be representative of the waste, either
statistically or with a bias towards large generators or generators of significant radionuclides (i.e.,
those that are most limiting for the storage, pretreatment, or treatment).
Section 205
The use of assessments, audits, or reviews to verify compliance of the waste generators’
certification programs with acceptance requirements are conducted on a regular schedule. The
documentation of the verification process includes review of the organization and authorities;
frequency of assessments; methods to be employed; the information that will be documented as a
result; and the qualifications of personnel.
Example: At Site K, DOE and contractor management teams for the high-level waste
program conduct a quarterly management assessment of waste generators’ waste
certification programs to ensure their programs are compliant with the current tank farm
waste acceptance requirements. This assessment program is in addition to the receiving
facility’s (high-level waste tank farm) monthly audit program that reviews high-level
waste generator sampling, transfer, packaging, and laboratory analysis procedures, and
training requirements.
Chapter II -High-Level Waste Requirements
II-70 DOE G 435.1-1
7-09-99
Non-Conforming High-Level Waste. Facilities receiving waste for storage, pretreatment, or
treatment must have a documented process to be used in the event a non-conforming waste is
received. Facility procedures need to discuss how non-conforming waste will be segregated from
acceptable waste, the process for notifying the sender of the non-conformance, and the acceptable
methods for dispositioning the non-conforming waste. The process includes prior notice to the
waste sender of the actions to be taken by the facility receiving the waste and the sender’s
obligations, particularly regarding the cost of the actions, to support the disposition of the
non-conforming waste.
Example: At Site X, a batch of supernate is transferred from a reprocessing canyon to a
high-level waste storage tank, after which it is determined that the transferred batch is
non-compliant with the receiving tank due to its low concentration of corrosion inhibitors
(nitrites). Upon receipt and discovery of the non-compliance, an analysis indicates that
even after blending of the transferred waste with the nitrite-rich waste in the tank, the
blended waste is non-compliant with the waste acceptance requirements of the receiving
tank. This condition will require the addition of sodium nitrite to the receiving tank to
correct the molar concentration of the supernate. The cost for the addition of sodium
nitrite is charged to the reprocessing canyon management.
Compliance with this requirement is demonstrated by the waste acceptance requirements for a
high-level waste management facility, including a process for evaluation and acceptance of
incoming waste, to ensure that the acceptance criteria of the facility receiving the waste are met.
The process includes one of, or a combination of: (1) testing, sampling, and analysis of
representative samples of incoming waste; (2) testing, sampling, and analysis of samples of waste
taken at the generator facility; (3) evaluation of testing, sampling, and analysis of data provided by
the generator; or (4) audits, reviews, surveillances, or observations of generator waste
certification programs and characterization activities. Additionally, waste acceptance
requirements for storage, pretreatment, or treatment facilities need to have documented
procedures if waste that does not conform to the waste acceptance criteria is received at a facility.
Supplemental References:
Section 206
1. DOE, 1999, Waste Acceptance System Requirements Document, Revision 3, DOE/RW
0351P, U.S. Department of Energy, Washington, D.C., April 1999.
2. DOE, 1996. Waste Acceptance Product Specification for Vitrified High-Level Waste
Forms, Revision 2, DOE/EM-0093, U.S. Department of Energy, December 1996.
3. DOE, 1994. DWPF Waste Form Compliance Plan, Revision 4, WSRC-IM-91-116-0,
U.S. Department of Energy, December 1994.
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-71
7-09-99
4. DOE, 1997. Waste Form Compliance Plan for the West Valley Demonstration Project
High-Level Waste Form, Revision 12, WVDP-185, U.S. Department of Energy,
December 1997.
Chapter II -High-Level Waste Requirements
II-72 DOE G 435.1-1
7-09-99
II. K. Waste Generation Planning.
The following requirements are in addition to those in Chapter I of this Manual.
(1) Life-Cycle Planning. Prior to waste generation, planning shall be performed
to address the entire life cycle for all high-level waste streams.
(2) Waste With No Identified Path to Disposal. High-level waste streams with no
identified path to disposal shall be generated only in accordance with
approved conditions which, at a minimum, shall address:
(a) Programmatic need to generate the waste;
(b) Characteristics and issues preventing the disposal of the waste;
(c) Safe storage of the waste until disposal can be achieved; and
(d) Activities and plans for achieving final disposal of the waste
(compliance with DOE/EM-0093, Waste Acceptance Product
Specifications for Vitrified High-Level Waste Forms).
Objective:
The objective of this requirement is to provide for the disposal of all high-level waste that is
generated by ensuring that: the specific waste management facilities necessary for safe
management of the waste from the time it is generated up to and including its disposal are
identified prior to the generation of a new high-level waste stream; plans are developed for
resolving issues that prevent disposal, and for safe, long-term storage for high-level waste with no
path to disposal; and sites are discouraged from generating high-level waste that does not have an
identified path to disposal.
Discussion:
For purposes of this requirement, the term disposal has essentially the same meaning as
compliance with the DOE/EM-0093, Waste Acceptance Product Specifications for Vitrified
High-Level Waste Forms (EM-WAPS). The EM-WAPS was prepared by the Office of
Environmental Management (EM) to document the applicable specifications for producing a high-
level waste form acceptable to the Office of Civilian Radioactive Waste Management for disposal.
The Nuclear Waste Policy Act of 1982, as amended, charges the Office of Civilian Radioactive
Waste Management with responsibility for management and disposal of high-level waste. The
Office of Civilian Radioactive Waste Management has prepared DOE/RW-0351P, Waste
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-73
7-09-99
Acceptance System Requirements Document (WASRD), which includes the waste acceptance
requirements on which the EM-WAPS is based. The linkages described among these applicable
documents and organizations are consistent with the related requirement of this Manual (Section
II.S., Disposal) that high-level waste be disposed of “…in accordance with the provisions of the
Nuclear Waste Policy Act of 1982, as amended.” In the guidance for this requirement, the term
disposal is, therefore, interchangeable with compliance with the EM-WAPS.
Section 207
Life-cycle planning. Planning, prior to generating high-level waste, is intended to address
high-level waste streams that have not yet been generated. High-level waste streams that are first
generated after issuance of the Order are subjected to this requirement. Waste that has already
been and continues to be generated is addressed in the site-wide program requirements (see
Section I.2.F.(1)). Waste generator planning is closely linked to characterization, certification,
and transfer requirements (see Sections II.L, II.M, and II.N) which comprise the waste generator
requirements program described in DOE M 435.1-1 (see Chapter I, Section I.2.F.(7)).
Example 1: A batch of spent fuel stored at Site X is deteriorating and reprocessing is
necessary to reduce risk. The reprocessing will begin two years after issuance of DOE O
435.1 in an existing reprocessing canyon. The spent fuel is different from that previously
reprocessed in the canyon, and necessary process changes will produce a waste stream
unlike those previously produced. Therefore, the waste generation planning
requirements of DOE O 435.1 must be applied.
Example 2: A reprocessing canyon that was operating when DOE O 435.1 went into
effect continued to operate. Neither the spent fuel input nor the process chemistry or
equipment was changed. In this case, the high-level waste generator planning
requirements would not apply. The continued reprocessing would be addressed by the
site-wide planning requirements (see Sections I.2.F.(1) and II.E).
Planning needs to address the life-cycle of high-level waste from generation through compliance
with the EM-WAPS, including the interim steps of high-level waste management. This can be
accomplished by preparing a high-level waste stream life cycle description and reviewing it with
managers of the facility(ies) that are expected to manage the high-level waste. The high-level
waste stream life cycle description is a sequential description of each step in high-level waste
treatment, storage, and transfer to the Office of Civilian Radioactive Waste Management. It
provides sufficient information to determine what treatment and storage capabilities are needed so
that their availability can be determined. The high-level waste generator needs to confirm with
operators of each management facility to be used that based on the current knowledge of the
high-level waste stream characteristics and planned facility capacity the high-level waste stream
can be managed by the facility.
Chapter II -High-Level Waste Requirements
II-74 DOE G 435.1-1
7-09-99
Example: The new Site X waste stream described in the first example above will be
subjected to chemical dissolution and separations. The high-level waste resulting from
the process will be solidified. At various stages in this series of operations, temporary or
long-term storage will likely be required waste generation planning will include
preparation of a high-level waste stream life cycle description consisting of identification
and explanation of each of these steps and explanation of the interfaces between the
steps. The generator of the waste holds discussions with operators of facilities that may
be able to manage the waste and incorporates relevant information on waste
management needs and the availability of facilities to meet those needs in written plans.
Section 208
A measure to determine whether a high-level waste stream has an identified path to compliance
with the EM-WAPS is the availability of the necessary facilities and operations. A planned facility
is considered to be available if it has been authorized (e.g., a line item in a Congressional
appropriation or equivalent approval for design and construction). For purposes of planning for
compliance with the EM-WAPS by a high-level waste stream, a facility or capabilities that are
part of a program or strategic plan, but have not been authorized, are not considered available. If
a planned or available facility is canceled, the generator site will need to revise the planning for the
life cycle of the high-level waste. An alternate path to compliance with the EM-WAPS needs to
be identified and documented, or approval to generate the high-level waste needs to be obtained
from the cognizant Field Element Manager as required in DOE M 435.1-1, Section I.2.F.(19), and
plans need to be made for ultimate compliance with the EM-WAPS.
The generator is responsible for ensuring that high-level waste is not generated unless there is due
consideration of ultimate compliance with the EM-WAPS. However, it is not the objective of this
requirement to prohibit, under all conditions, the generation of high-level waste that does not have
an identified, achievable path to compliance with the EM-WAPS. In meeting the DOE O 435.1
planning requirement, it is appropriate for high-level waste management organizations to provide
assistance to the generator in determining the high-level waste management path, particularly in
cases where the high-level waste management organization may utilize offsite storage facilities for
post-immobilization storage. Once the waste is determined to comply with the EM-WAPS,
storage conditions are maintained to ensure continued compliance with the EM-WAPS.
Waste streams that do not satisfy the EM-WAPS. There are instances where programmatic needs
may necessitate the generation of high-level waste without an identified path to compliance with
the EM-WAPS. In these instances, the Field Element Manager must ensure development of a
process for identifying generation of high-level waste with no path to compliance with the EM
WAPS and approving the conditions under which such high-level waste can be generated
(DOE M 435.1-1, Section I.2.F.(19)). This process is intended to heighten the awareness of
high-level waste generators that a long-term commitment is made with the generation of such a
high-level waste. The long-term commitment arises from the potential for prolonged storage of
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-75
7-09-99
this high-level waste and from the work necessary to resolve issues that prevent compliance with
the EM-WAPS.
Under the current DOE high-level waste management configuration, there is a process for the
Office of Civilian Radioactive Waste Management acceptance of high-level waste that complies
with the EM-WAPS. As noted above, the EM-WAPS is based on requirements such as those in
the WASRD. In addition, there are facilities for pretreatment, treatment, and storage of some
high-level waste that will be needed prior to compliance with the EM-WAPS.
The conditions for generating a high-level waste without an identified path to compliance with the
EM-WAPS include various evaluations and considerations that involve both the high-level waste
generator and high-level waste management organizations. The decision to proceed with the
activity generating the high-level waste needs to consider the following:
Section 209
(a) The need to generate the high-level waste. There needs to be a clear identification
of the programmatic mission being served that results in the generation of high-
level waste with no identified path to compliance with the EM-WAPS. Alternate
means of accomplishing the mission without generating the high-level waste need
to also be discussed.
(b) High-level waste characteristics which prevent compliance with the EM-WAPS.
The reasons that a high-level waste cannot comply with the EM-WAPS need to be
identified to support development of plans for ultimately achieving compliance
with the EM-WAPS. These may be technical or programmatic reasons. For
example, high-level waste needs to be vitrified in a borosilicate glass matrix
(Specification 1.1) in order to comply with the EM-WAPS. If an appropriate
vitrification facility is not available, the lack of such a facility would be identified as
a reason the high-level waste does not have a path to compliance with the EM
WAPS. Similarly, if a high-level waste is categorized as mixed high-level waste
because of the presence of a listed hazardous waste and approval for delisting has
not been granted by EPA, that would be cited as a reason for no path forward to
compliance with the EM-WAPS (Specification 1.5).
(c) Adequate containment capabilities and facilities for the expected duration of the
storage period. If the high-level waste cannot comply with the EM-WAPS
pending the resolution of programmatic or technical issues, safe storage must be
available. In order to evaluate the ability to provide for the storage of the high-
level waste, there needs to be an estimate of the amount of the high-level waste
that will be generated, as well as an estimate of the time the high-level waste will
be in storage. Identification of acceptable storage facilities should be a prerequisite
to generating the high-level waste.
Chapter II -High-Level Waste Requirements
II-76 DOE G 435.1-1
7-09-99
(d) Plans for resolving the issues that prevent compliance with the EM-WAPS. The
decision to generate high-level waste with no identified path to compliance with
the EM-WAPS also needs to be based on a plan to achieve compliance with the
EM-WAPS eventually. The plan identifies the activities being pursued to resolve
issues preventing compliance with the EM-WAPS and a schedule for their
resolution. The activities described may be detailed if the issue is technical and
involves only a few sites. For example, plans to develop vitrification capabilities
necessary to make a high-level waste that complies with the EM-WAPS could be
detailed. The plans would identify the studies, engineering analyses, environmental
analyses, design and construction activities, and projected dates for performing
them, as appropriate. In other cases that are more programmatic in nature, the
activities and schedules will be less detailed. For example, providing for
compliance with the EM-WAPS for failed vitrification melters may require a
programmatic decision by DOE. The plan for addressing this requirement needs to
identify the data collection and options analyses to be performed by the site and
address how they fit with the actions being taken by the Complex-Wide High-
Level Waste Management Program (see DOE M 435.1-1, Section II.D). Included
in the EM-WAPS are provisions for addressing acceptance of non-standard
wastes. The generator must obtain delivery and procedure confirmation from the
Office of Civilian Radioactive Waste Management prior to transferring such
wastes.
Section 210
If the activities or schedules for conducting the activities are adversely impacted
(e.g., as a result of testing, design, funding profile, DOE policy) then they need to
be updated. Updates to the schedule and minor modifications of the activities
would not be a basis for re-evaluating the generation of the high-level waste.
However, major modifications of the activities (e.g., changes in plans for
developing the treatment facility or changes in the WASRD) would result in a re
evaluation and re-confirmation of the acceptability of continuing to generate the
high-level waste. All changes in plans for resolving issues preventing compliance
with the EM-WAPS are coordinated with the Headquarters Office of Waste
Management so their impact on the complex-wide high-level waste management
program can be reflected in the High-Level Waste Program Plan (see DOE M
435.1-1, Section I.2.D.(l)).
Example: Processing of the new Site X high-level waste stream described in the first
example above requires precipitation and removal of excess chromium to enable
compliance with the product consistency specification in the EM-WAPS (Specification
1.3). Site X management plans to build a facility for chromium removal to supplement
its existing reprocessing facilities, but Congress has not yet appropriated the funds for
design and construction. For purposes of the waste generator planning, the chromium
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-77
7-09-99
removal facility was not available and the generator planning for the life cycle of the
waste elected to seek approval from the cognizant Field Element Manager to generate
the waste in the absence of an available path to compliance with the EM-WAPS. The
generator considered elimination of the need for chromium removal, but that option was
found to be technically infeasible. The Field Element Manager approved the generation
of the waste anyway, based on consideration and documentation of the following four
factors:
(a) the need to generate the high-level waste;
(b) high-level waste characteristics which prevent compliance with the
EM-WAPS;
(c) adequate containment capabilities and facilities for the expected duration
of the storage period; and
(d) plans for resolving the issues that prevent compliance with the EM-WAPS.
Compliance with this requirement is demonstrated by individual sites establishing a process for
evaluating the life cycle of high-level waste prior to its generation, including the identification of
high-level wastes with no path to compliance with the EM-WAPS and appropriate records
justifying the newly generated high-level waste streams. The process would be considered
acceptable if, before generating high-level waste, the Field Element Managers responsible for
operation of the needed treatment and storage facilities approve generation of the high-level
waste. Records substantiating high-level waste generation planning would be of two types. First,
site personnel would have records showing the location(s) where high-level waste will be treated
and stored, the estimated period of storage, and confirmation that the personnel managing the
facilities agree that the high-level waste can be managed at those facilities. Second, the waste
generation organization would have records documenting the decision to generate a high-level
waste that does not have a known path to compliance with the EM-WAPS. This second set of
records is judged to be adequate if they include an explanation of the need for the process that
generates the high-level waste, a discussion of the reason it cannot be disposed of, and an up-to
date schedule of activities being pursued to resolve constraints to the compliance with the EM
WAPS of the subject high-level waste.
Section 211
Supplemental References:
1. DOE, 1996. Waste Acceptance Product Specifications for Vitrified High-Level Waste
Forms (EM-WAPS), Revision 2, DOE/EM-0093, U.S. Department of Energy,
Washington, D.C., December 16, 1996.
2. DOE, 1999. Waste Acceptance System Requirements Document, Revision 3,
DOE/RW-0351P, U.S. Department of Energy, Washington, D.C., April 1999.
Chapter II -High-Level Waste Requirements
II-78 DOE G 435.1-1
7-09-99
II. L. Waste Characterization.
High-level waste shall be characterized using direct or indirect methods, and the
characterization documented in sufficient detail to ensure safe management and
compliance with the waste acceptance requirements of the facility receiving the
waste.
Objective:
The objective of this requirement is to ensure that sufficient knowledge of high-level waste’s
characteristics (e.g., chemical, physical, radiological) is available to support workers during
handling the waste and to support effective decision-making for its management. This
information is to be maintained from generation, through storage, pretreatment and treatment in
sufficient detail to ensure that the requirements of the DOE/EM-0093, Waste Acceptance Product
Specifications for Vitrified High-Level Waste Forms (EM-WAPS) are met. Waste, that is
identified through the waste incidental to reprocessing process to be non-high-level waste, shall be
characterized in a manner that ensures subsequent treatment and disposal requirements for low-
level waste and transuranic waste can be met.
Discussion:
The Radioactive Waste Management Manual, General Requirements, assigns the Field Element
Manager the responsibility of ensuring development and approval of a program that addresses the
responsibilities of waste generators (DOE M 435.1-1, I.2.F.(7)). The generator requirements are
to address hazards associated with a waste management facility receiving unexpected volumes or
types of waste, or receiving waste that may not meet the applicable waste acceptance
requirements. Generator requirements address generation planning, waste characterization, waste
certification, and waste transfer. The characterization requirement addresses the hazards
associated with insufficiently characterizing the waste to ensure safe storage, and to ensure
pretreatment or treatment operations result in a waste form that meets the requirements of the
EM-WAPS. In addition, characterization data that are collected during generation, storage, and
after pretreatment or treatment of high-level waste need to be reliable and in sufficient detail to
ensure subsequent management can be conducted safely and to meet the waste acceptance
requirements of all subsequent receiving facilities. Accurate characterization of high-level waste
is essential to: 1) waste planning by generators, as required by Section II.K; 2) waste transfers by
generators and other senders of waste, as required by Section II.N; and 3) waste certification by
both senders and receivers, as required by Section II.M.
In conducting the analyses for development of the DOE M 435.1-1 requirements, minimum
characterization requirements were identified as necessary to ensure safe management of
high-level waste from generation, storage, pretreatment and treatment processes. Guidance for
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-79
7-09-99
Section 212
requirements for minimum characterization for all high-level waste generation, storage,
pretreatment, and treatment facility activities is provided in subrequirement (2) of Section II.L,
paragraphs (a) through (d). Guidance for the requirements for data quality objectives and
hazardous characteristics is provided in subrequirements (1) and (3), respectively, of Section II.L.
Waste characterization is defined as:
“The identification of waste composition and properties, such as by review of process
knowledge, or by nondestructive examination, nondestructive assay, or sampling and
analysis, to comply with applicable storage, treatment, handling, transportation, and
disposal requirements.”
Thus, waste characterization is a tool for gathering information that will support defensible
decisions regarding safety, process, and environmental matters in the management of high-level
waste. The magnitude of such decisions may vary from whether individual high-level waste
streams are compatible for mixing in a storage tank to whether their mixing may reduce the
likelihood of producing an acceptable final (glass) high-level waste form. The following sections
of guidance address elements of characterization activities that support defensible decision
making: use of indirect methods, characterization documentation, characterization for safe
storage, and characterization for treatment to meet the EM-WAPS.
Use of Indirect Methods. In the safety and hazards analysis performed in support of development
of DOE M 435.1-1, the use of indirect methods of characterizing high-level waste was identified
as a potentially significant factor in maintaining accurate characterization of high-level waste. The
use of indirect methods is particularly applicable when nondestructive evaluation or sampling and
analysis will potentially expose operations personnel to additional radiation. Indirect methods for
characterization of high-level waste are based on the materials or processes used to generate the
waste, as well as the analytical data obtained from the process or waste stream. Indirect methods
for characterization are also considered to include information regarding the process that
generated the waste stream, the physical form and materials composing the waste, the chemical
constituents of the waste, and the nature of the radioactivity present.
Indirect methods may be used to describe high-level waste if the source information is consistent,
defensible, and auditable. The use of indirect methods is justified by its potential to minimize
personnel exposure and to reduce the high costs of intrusive sampling and analysis. In practice,
indirect methods can be effectively used where high-level waste is generated in well known and
tightly controlled processes for which the product is highly predictable.
By using indirect methods, where appropriate, the potential exists for minimizing the exposure of
operating personnel to radiation and complying with the as low as reasonably achievable
(ALARA) principle for keeping exposures to a minimum. Additionally, characterization of
Chapter II -High-Level Waste Requirements
II-80 DOE G 435.1-1
7-09-99
high-level waste by the use of indirect methods reduces the volume of sample materials and
laboratory equipment and expendables that would be contaminated due to the analyzing of the
sample.
Section 213
While the development of a process for identifying and documenting high-level information to
support indirect methods is not required for high-level waste by DOE M 435.1-1, the following
guidance provides an overview of elements of an acceptable process for assembling such
documentation:
C Information to support indirect methods is compiled in an auditable record.
C Correlations within waste streams in terms of time of generation, waste generation
processes, analytical data, and site-specific facilities should be clearly described.
C A reference list of applicable documents, databases, quality control protocols, and
other sources of information that support the indirect methods is prepared.
C Procedures which outline the methodology that is to be used to identify and
assemble auditable, acceptable records to support indirect methods, including the
origin of the documentation, how the assembled information was or will be used,
and any limitations associated with the information.
Characterization data gained by indirect methods must be within the acceptable range of certainty
and precision. Additionally, the effects of time-dependent processes must either be negligible or
predictable. Acceptable information to support indirect methods can be verified by collection and
comparison of statistically valid analytical sampling of processing records. The periodicity of
sampling and analysis should correlate with the nature of any changes in the process creating the
waste or with changes that are being documented in characterization data. Finally, the data must
be consistent with the requirements contained in the EM-WAPS. In particular, data collected and
used for indirect methods that are considered “waste product affecting” must be verifiably correct
and defensible and the strategy for its use must be described and defended by each waste producer
in their waste compliance plan and waste qualification reports.
Indirect methods documentation should follow the process and include the documentation
elements described below with particular emphasis on data quality assurance. As discussed in
DOE M 435.1-1, Section II.N, Waste Transfer, this documentation needs to be organized and
assembled in a manner that allows it to be transferred to the facility or operation that is to receive
the waste.
Example: At the Site Z there is a high level of confidence in the mass balance data
available from the generator (Q-Canyon) for a particular high-level waste stream that is
scheduled to be transferred from a storage tank to the sludge wash (pretreatment)
process. Review of the waste processing information by trained and knowledgeable
personnel concludes that the data are reliable and that, in lieu of sampling and analysis,
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-81
7-09-99
an indirect method will be used to characterize and certify the waste for transfer. This
decision and the quality of the data is documented and included in the documentation
that is transferred with the waste.
Characterization Documentation. The requirement states that characterization data shall be
documented in sufficient detail to enable the waste acceptance requirements of the receiving
facility to be met. The following elements are considered essential to this process for obtaining
and controlling characterization data:
Organization(s) and Responsibilities - Identification of the organizations involved and
responsible for characterization of high-level waste.
Section 214
Quality Assurance - Characterization data need to be subjected to a clearly identified and
well-documented quality assurance program. In the case of characterization data that
applies to high-level waste, items and activities important to waste acceptance/product
quality need to apply the quality assurance requirements of DOE/RW-0333P, Quality
Assurance Requirements and Description for the Civilian Radioactive Waste
Management Program, as specified in DOE M 435.1-1, Section II.G, Quality Assurance
Program.
Procedures - The process for obtaining waste characterization data is formalized in
procedures and need to describe how to follow the steps that are provided and the
administrative process for ensuring the data are of acceptable quality. Procedures need to
be developed for sampling, packaging, transportation, laboratory analysis, and data
control.
Procurement/Purchasing Controls - The procurement and/or purchasing of items or
services that are used in characterizing high-level waste need to be controlled and
documented. Procurement includes the purchase of sampling equipment and sample
transport containers as well as services such as laboratory analyses (onsite or offsite).
Requirements are dictated by the type of procurement, but needs to include, or reference:
the technical specifications for the item/service being procured; identification of quality
assurance requirements including any required inspections; specifications of
documentation requirements (e.g., certification of compliance or conformance, laboratory
analytical results); and a statement ensuring access to the provider’s facilities as necessary
to perform audits and inspections.
Document/Data Change Control - Records that contain characterization data, whether
they have been generated through sampling and analysis, nondestructive assay, or indirect
methods, need to be subject to document and data change control. In addition, the
documentation of waste characterization procedures and the quality assurance program
Chapter II -High-Level Waste Requirements
II-82 DOE G 435.1-1
7-09-99
are subject to control. Document and data change control includes review, approval, and
distribution to designated recipients (users), and a controlled process for making revisions
to documents. Existing document and data control programs at a site may be adequate for
high-level waste characterization data, but will need to be reviewed to ensure the
objectives of DOE M 435.1-1 requirements are met.
Training - Characterization data are generated and managed only by personnel that are
properly trained to recognize the significance of the data.
Records - Waste characterization records include those that are necessary to meet the
waste acceptance requirements of receiving facilities and as specified by the waste
certification program, as specified in Section II.M.
Existing programs at a site may provide the framework within which the elements of waste
characterization can be addressed (e.g., quality assurance, training, document control). The waste
acceptance requirements of a facility to which the waste is to be sent may impose additional
requirements on what is to be included in the waste characterization data.
Section 215
Characterization for Safe Storage. Characterization data for high-level waste streams are
developed to ensure that the transfer and addition of a high-level waste solution, slurry, or sludge
does not present an added risk to the storage systems that receive it, i.e, the transferred material
must be compatible with the tank and its contents. These data are based on an analysis of the
waste stream through either sampling, indirect methods, or a combination of both, and must be in
a form consistent with the receiving facility’s waste acceptance requirements. Consideration also
is given, and documented, to facilities or operations downstream of the receiving facility to ensure
that waste acceptance requirements for these facilities will not be violated.
Example: At Site Z, a high-level waste stream is planned to be transferred by a
generator to the high-level waste tank farms. Characterization of the waste is conducted
by the generator to ensure that not only are the waste acceptance requirements of the
receiving tank satisfied, but also the waste acceptance requirements of the pretreatment
and treatment facilities, downstream of the waste storage tanks. These downstream
facilities require a more extensive chemical analysis to ensure that the waste is
acceptable for making a quality glass waste form.
Various techniques can be employed to characterize high-level waste. Techniques include
sampling and analysis, nondestructive assay techniques, and the use of indirect methods. In
selecting the characterization technique for a particular waste stream, trade-offs are considered to
determine which is most appropriate. Trade-off analyses are part of an ALARA process which
needs to consider:
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-83
7-09-99
• radiation exposure to operations and sampling personnel;
• potential for contamination or other abnormal events;
• costs (personnel, resources and schedule);
• reliability and confidence level of the data;
• availability of data to support indirect methods;
• required management activities (audits, evaluations); and
• re-engineering of sampling operations to reduce worker hazards.
Balancing these competing considerations is considered necessary to meet the requirement. As
discussed in the guidance for the data quality objectives process, Section II.L.(1), the
characterization technique chosen is dependent on the data required, and the quality of such data.
Example: At Site K, additional characterization data for the contents of Tank 300 are
needed promptly to ensure that the addition of 75,000 gallons of a decontamination
solution to the existing 400,000 gallons of high-level waste slurry will not generate a
vapor phase of waste product that is combustible. While the contents of the existing tank
have not been characterized by sampling, its contents are well documented through the
generator documentation (e.g., mass balance calculations). In addition, controls to
ensure additional wastes have not been transferred to the tank are in place and
considered reliable. Furthermore, plans to sample and analyze the tank contents
conclude that a potential exists for significant worker exposure and unacceptable
programmatic schedule delays due to laboratory workload. Thus the decision is made,
through a documented “trade-off” analysis, that the risks of adding the solution to the
tank, using indirect methods about the existing tank waste and knowledge about the
decontamination solution, are lower than the risks of sampling and analyses.
Section 216
Characterization for Treatment to Meet the Office of Environmental Management-Waste
Acceptance Product Specifications (EM-WAPS). For high-level waste, an appropriate level of
characterization data must be available from the time of generation of the waste stream through
storage, pretreatment, treatment, and post-treatment storage to ensure that the final waste form
meets the requirements of the EM-WAPS, applicable revision. The current EM-WAPS outlines
the technical specifications the waste form Producers are required to meet in order to ensure
acceptance of their vitrified high-level waste into the Civilian Radioactive Waste Management
System. The Office of Environmental Management and the Office of Civilian Radioactive Waste
Management have agreed that the Office of Environmental Management is to provide the final
waste form specifications to the waste form producers and that the Office of Environmental
Management will ensure that the EM-WAPS is consistent with the technical baselines as defined
in the Office of Civilian Radioactive Waste Management’s DOE/RW-0351P, Waste Acceptance
System Requirements Document (WASRD). Thus, the EM-WAPS governs all elements of the
final, canistered, waste form which includes the borosilicate waste glass, the stainless steel
canister, and the sealed canistered waste form.
Chapter II -High-Level Waste Requirements
II-84 DOE G 435.1-1
7-09-99
The waste acceptance process requires demonstration of compliance with the EM-WAPS through
four different documents, each prepared by the waste producers, reviewed and accepted by the
Office of Environmental Management, and provided to the Office of Civilian Radioactive Waste
Management. These four documents are: the Waste Form Compliance Plan; the Waste Form
Qualification Reports; the production records; and the storage and shipping records. The waste
producers included in Revision 2 of the EM-WAPS are the Defense Waste Processing Facility at
the Savannah River Site, the West Valley Demonstration Project, and the Hanford Site. Final
waste form developmental work at the Idaho National Environmental Engineering Laboratory has
not progressed to the point that it has been included in the current EM-WAPS.
The EM-WAPS provides detailed specifications that must be met by the waste producers in order
for the final waste form to be acceptable to the Office of Civilian Radioactive Waste Management
for disposal. Amplification on these specifications is considered beyond the scope of this
Implementation Guide; however, Refer to the current Waste Compliance Plans and Waste
Qualification Reports for the Defense Waste Processing Facility and the West Valley
Demonstration Project, both of which provide a detailed description of the methods by which they
comply with each of the specifications. Following are the titles of each of the summary
specifications within the EM-WAPS:
1. Waste Form Specifications
2. Canister Specifications
3. Canistered Waste Form Specifications
4. Quality Assurance Specification
5. Documentation and Other Requirements
The level of characterization needed and the data required for the production of an acceptable
final high-level waste form are described in the EM-WAPS (included in supplement references)
and are not reproduced in this Guide. However, the strategy for complying with these
specifications is left to each waste producer. Each strategy is defined in the waste producer’s
Waste Compliance Plan and demonstrated in their Waste Qualification Reports.
Section 217
Examples: (1) Section 1.1, “Chemical Specification,” of the EM-WAPS, requires that
each waste producer project, in their Waste Qualification Report, the chemical
composition of the final waste form, by oxides present that are in concentrations greater
than 0.5 percent. (2) Section 1.2, “Radionuclide Inventory Specification,” of the
EM-WAPS requires that each waste producer project, in their Waste Qualification
Report, the inventory of radionuclides that have half-lives longer than 10 years and that
are, or will be, present in concentrations greater than 0.05 percent of the total
radioactive inventory, indexed to the years 2015 and 3115. For both specifications each
waste producer is required to provide a strategy on how these projections will be made.
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-85
7-09-99
Waste Incidental to Reprocessing. Waste streams that are subjected to the waste incidental to
reprocessing determination processes (DOE M 435.1-1, Section II.B) need to be adequately
characterized to support the conclusions reached in applying the two processes, i.e., the citation
process and the evaluation process. For those waste streams that are determined to be non-high
level waste by the use of these processes, the applicable characterization requirements are
included in DOE M 435.1-1, Section III.J for transuranic waste, and Section IV.I for low-level
waste.
Compliance with this requirement is demonstrated by the existence of records that document
characterization data for high-level waste that are consistent with the waste acceptance
requirements of high-level waste storage, pretreatment, or treatment facilities. In addition, the
records need to be consistent with the characterization data required by the current version of the
EM-WAPS. For those waste streams that are subjected to the waste incidental to reprocessing
process(es), adequate characterization data records must exist to support the conclusion.
Supplemental References:
1. DOE, 1996. Waste Acceptance Product Specification for Vitrified High-Level Waste
Forms, Revision 2, DOE/EM-0093, U.S. Department of Energy, December 1996.
2. EPA, 1994. Guidance for the Data Quality Objectives Process, EPA QA/G-4, U.S.
Environmental Protection Agency, Washington, D.C., September 1994.
3. DOE, 1994. DWPF Waste Form Compliance Plan, Revision 4, WSRC-IM-91-116-0,
U.S. Department of Energy, December 1994.
4. DOE, 1995. Waste Form Compliance Plan for the West Valley Demonstration Project
High-Level Waste Form, Revision 11, WVDP-185, U.S. Department of Energy, February
1995.
5. DOE, 1999. Waste Acceptance System Requirements Document, Revision 3, DOE/RW
0351P, U.S. Department of Energy, Washington, D.C., April 1999.
II. L.(1) Data Quality Objectives. The data quality objectives process, or a
comparable process, shall be used for identifying characterization
parameters and acceptable uncertainty in characterization data.
Chapter II -High-Level Waste Requirements
II-86 DOE G 435.1-1
7-09-99
Objective:
The objective of this requirement is to invoke a process for determining the type, quantity, and
quality of characterization data needed to support the safe management of high-level waste so as
to ensure that needed data are acquired, the data meet the objectives they are being collected for,
and resources are not wasted on unnecessary, incomplete or unusable data collection efforts.
Discussion:
Section 218
The type, quantity, and quality of characterization data obtained for the safe management of
high-level waste need to be consistent with the purpose for which the characterization information
will be used. As discussed in the guidance to DOE M 435.1-1, Section II.L., the uses of high-
level waste characterization data include: complying with storage, pretreatment, and treatment
facilities’ waste acceptance requirements; meeting the final waste form specifications of the
EM-WAPS; evaluating high-level waste confinement integrity; determining radiation shielding and
other protective measures; evaluating compliance with processing requirements; and meeting
regulatory commitments. This requirement is included in DOE M 435.1-1 to ensure that only the
appropriate characterization data to support the safe management of high-level waste is
generated. The requirement is intended to promote a structured process for the collection, and
use, of high-level waste characterization data and avoid the collection of data that is neither
necessary nor defensible.
The requirement invokes the use of a process to provide the structured approach for determining
the type, quantity, and quality of characterization data needed. Such a process, called data quality
objectives, has been developed by the US Environmental Protection Agency (EPA) and is
documented in EPA’s QA/G-4, Guidance for the Data Quality Objectives Process. However,
use of other comparable processes that employ a structured process to yield similar results are
also supported.
The objectives of applying a structured process such as the data quality objectives process are to:
C Manage and control the risks of making incorrect decisions;
C Determine the data required to support making specific decisions;
C Determine the type and quality of required data;
C Allow decision makers, stakeholders, data users, and relevant technical experts to
participate in planning and assessment;
C Determine the quantity, location, and type of samples required;
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-87
7-09-99
C Quantify the uncertainty in data through development of statistical sampling plans;
and
C Reduce overall costs by identifying resource-efficient sample collection and
analytical methods by optimizing the sample and analysis plans.
The data quality objective process is a strategic planning approach based on the scientific method
that is used to prepare for a data collection activity. The value of using this process to develop
high-level waste characterization parameters is that it: saves resources by making characterization
data collection operations more resource-effective; enables characterization data users and others
to participate in characterization data planning; and provides a structured method for defining
characterization data performance requirements, i.e., quality.
The process for establishing characterization needs via the data quality objectives process requires
input from various waste management organizations and interested groups to establish a clear
understanding of the characterization data needs and the level of data quality that is acceptable for
making high-level waste management decisions.
The Field Element Manager is to ensure that managers of generator facilities assume responsibility
for key activities in the data quality objectives (or similar) process by:
C Designating the author of the data quality objectives document.
Section 219
C Participating in development of the initial data quality objectives strawman.
C Identifying the stakeholders.
C Participating in stakeholder meetings.
C Selecting members of the expert panel.
C Participating in the review of the final data quality objectives process.
C Approving the data quality objectives document prior to submission to the Field
Element Manager.
C Identifying activities that initiate a data quality objectives revision based on the
extent of the revision.
The managers of generator facilities should rely on personnel within the facility organization to
support the elements of the data quality objectives process. Those personnel may be
supplemented by subject matter experts (e.g., facilitators, samplers, laboratory personnel,
statisticians, safety personnel, quality assurance personnel). The facilitator may be part of the
generator organization or a consultant. The facilitator’s role is to keep meetings focused,
maintain the document development schedule, and troubleshoot administrative and logistics
problems.
Chapter II -High-Level Waste Requirements
II-88 DOE G 435.1-1
7-09-99
The data quality objectives process consists of seven steps. The output from each step influences
the choices that will be made later in the process. Even though the data quality objectives process
is depicted as a linear sequence of steps, in practice it is iterative, e.g., the outputs from one step
may lead to a reconsideration of prior steps. This iteration is encouraged since it will ultimately
lead to a more efficient data collection design.
During the first six steps of the process, a team of process-cognizant personnel should develop
decision performance criteria (data quality objectives) that will be used to develop the data
collection design. The final step of the process involves developing the data collection design
based on the data quality objectives developed in the first six steps. The first six steps should be
completed before the team attempts to develop the data collection design because the design is
dependent on a clear understanding of the first six steps taken as a whole.
Following is a listing and brief description of each of the seven steps. This is followed by an
example of how the data quality objectives process can be applied to the generation of high-level
waste characterization data.
1. State the Problem – Concisely describe the problem to be studied. Review prior studies
and existing information to gain a sufficient understanding to define the problem.
2. Identify the Decision – Identify what questions the study will attempt to resolve, and
what actions may result.
3. Identify the Inputs to the Decision – Identify the information that needs to be obtained
and the measurements that need to be taken to resolve the decision statement.
4. Define the Study Boundaries – Specify the time periods and spatial area to which
decisions will apply. Determine when and where data should be collected.
5. Develop a Decision Rule – Define the statistical parameter of interest, specify the
action level, and integrate the previous data quality objective outputs into a single
statement that describes the logical basis for choosing among alternative actions.
6. Specify Tolerable Limits on Decision Errors – Define the decision maker’s tolerable
decision error rates based on a consideration of the consequences of making an incorrect
decision.
Section 220
7. Optimize the Design – Evaluate information from the previous steps and generate
alternative data collection designs. Choose the most resource-effective design that meets
all data quality objectives.
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-89
7-09-99
Example: At Site Z, the operator of a spent nuclear fuel reprocessing facility plans to
restart an existing fuel dissolution process line that will generate a new high-level waste
stream that is significantly different in chemical/radionuclide composition than has been
generated at the site before. Proper management of this new waste stream has been
recognized by the site’s waste management organization as a significant challenge to the
high-level waste management program. It has also been recognized that proper
characterization data, and the quality of this data, are critical to the safe management of
this waste. For this reason, and to ensure unnecessary and unusable data are not
generated, the high-level waste management organization organized a team of cognizant
waste management personnel to implement the data quality objectives process with the
purpose of defining the type, quantity, and quality of characterization data needed. The
site team used the EPA Data Quality Objectives process as follows:
The problem was identified as the introduction of a new high-level waste stream to the
site’s high-level waste management system. The question that needed to be answered
was: What characterization data are needed to support management of this new waste
stream? (Management was defined to include all storage, pretreatment, treatment, and
post treatment storage activities at the site that are needed.) Inputs needed were
identified as: waste acceptance requirements for all affected facilities, authorization
basis/limits for all affected facilities, radiological limits/ controls, RCRA requirements,
state/local regulations, EM-WAPS, characterization data quality/accuracy requirements.
The boundaries were defined as the high-level waste management system and the low-
level/mixed low-level waste management system for secondary waste streams. Other
boundaries identified were that the new waste stream would be generated for only 5
years, beginning in 12 months, and that the total quantity would not exceed 1,000,000
gallons of liquid waste. A major identified constraint/risk to data identification/
collection was the fact that this waste has been produced at bench-scale testing only, and
that the characteristics of the waste at full-scale operations may vary from these results.
Key parameters included: chemical composition, radionuclide composition, pH,
nitrate/nitrite/hydroxide concentrations, volatile/flammable species, organics, RCRA-
listed wastes, fissile material, challenges to receiving facility authorization bases, and
receiving tank waste characteristics.
From the set of parameters identified above, key decision rules were developed. For
example, if the pH of the waste is equal to, or less than, 9.5, the waste is unacceptable for
transfer to the tank farm. For each of identified twenty parameters an acceptable range
of errors was established. These were based on sampling/analysis and operational
experience. For example, the calculation, or measurement, of the pH of the new waste
stream must be within a 95% confidence range; with the most severe consequence being
violation of the tank farm’s authorization basis. Finally, with the individual
characterization parameters identified, a review of the entire collection was conducted to
Section 221
Chapter II -High-Level Waste Requirements
II-90 DOE G 435.1-1
7-09-99
ensure consistency and completeness. This review resulted in the number of the
parameters being deleted and the establishment of a final set of characterization
parameters for the new waste stream. These parameters were incorporated into a waste
characterization plan for the restarted fuel dissolution process.
The above description of the steps using the data quality objectives process, and the example, are
provided as an introduction to the process. A more detailed description of the process can be
found in the referenced EPA Guide. The data quality objectives process is most useful during the
planning stages of identifying high-level waste characterization and uncertainty parameters, i.e.,
before the data are needed and collected. The value of the process is diminished significantly if
the characterization data have already been collected and are being used.
Compliance with this requirement is demonstrated by the documented use of a data quality
objectives, or comparable process, for determining the type, quantity, and quality of
characterization data needed to safely manage high-level waste.
Supplemental References:
1. EPA, 1994. Guidance for the Data Quality Objectives Process, EPA QA/G-4, U.S.
Environmental Agency, Washington, D.C., September 1994.
II. L.(2) Minimum Waste Characterization. Characterization data shall, at a
minimum, include the following information relevant to the
management of the waste:
(a) Physical and chemical characteristics;
(b) Volume, including the waste and any solidification media;
(c) Radionuclides or source information sufficient to describe the
approximate radionuclide content of the waste; and
(d) Any other information which may be needed to demonstrate
compliance with the requirements of the DOE/EM-0093, Waste
Acceptance Product Specifications for Vitrified High-Level
Waste Forms, or DOE/RW-0351P, Waste Acceptance System
Requirements Document, for non-vitrified, immobilized high-
level waste.
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-91
7-09-99
Objective:
The objective of this requirement is to establish minimum high-level waste data that have been
determined to be necessary for safe and effective management during the life cycle of the waste.
Discussion:
In the process of developing DOE O 435.1 and DOE M 435.1-1, characterization of high-level
waste was identified as an activity in the life-cycle management of waste with a significant
potential for loss of adequate waste management controls which could result in exposure or
release of radioactivity. This requirement identifies those critical characterization data points that
must be known at all times to ensure safe handling and proper management. These requirements
are considered the minimum categories of data that the data quality objectives process (DOE M
435.1-1, II.L.(1)) should require and address. The sections below provide guidance on each of
the specific characteristics.
Section 222
Physical and chemical characteristics. The physical and chemical characteristics information
needed should be guided by data needs of the storage, pretreatment, or treatment processes that
the waste is expected to be exposed to and the waste acceptance requirements established for the
facilities and processes that perform these operations. Physical properties should include a
description of the material, its phase (solid or liquid), density, consistency, temperature, and
conductivity. Chemical properties should include pH, reactivity, chemical compounds present,
and hazardous and/or toxic constituents present. However, the complete list of properties that
are needed is guided by the receiving facility’s or operation’s waste acceptance requirements.
Additionally, the high-level waste EM-WAPS, Specification 1.1, “Chemical Specification,” has
specific requirements regarding the identification of the chemical composition of the final
(immobilized) waste form that must be reported in the Waste Qualification Report, for each waste
type, by high-level waste producers. Establishment of the characterization data requirements
must consider these and other EM-WAPS data requirements.
Volume, including the waste and any solidification media. Volume and weight information is
necessary for proper control of immobilized high-level waste storage, transportation, and disposal
as well as control of canistered waste handling systems. The EM-WAPS, Specifications 3.6, “Fill
Height Specification,” and 3.11, “Specifications for Weight and Overall Dimensions,” require that
the filled canister volume, weight, and overall dimensions be reported in the Storage and Shipping
Records that will accompany each canister to the geologic repository disposal site. The method
and basis for meeting these EM-WAPS requirements are described by each waste producer in
their Waste Compliance Plan and the Waste Qualification Reports.
Additionally, the EM-WAPS, in Specification 1.1, “Chemical Specification,” requires waste
producers to include chemical composition projections of the final high-level waste form. These
Chapter II -High-Level Waste Requirements
II-92 DOE G 435.1-1
7-09-99
projections must include all elements, including waste material and solidification media, (e.g.,
glass frit) that are present in concentrations greater than 0.5 percent, by weight, in the final waste
form. As with the volume and weight information, the methods and basis for meeting this
EM-WAPS requirement must be described by each waste producer in their Waste Compliance
Plan and the Waste Qualification Reports.
Radionuclides or source information sufficient to describe the approximate radionuclide content
of the waste. Radionuclide information for liquid (pre-immobilized) high-level waste and the final
waste form is necessary to support proper personnel radiation protection and control for
managing high-level waste. It ensures that all high-level waste management facilities are
inherently safe with respect to criticality. For the final waste form, the EM-WAPS, Specification
1.2, “Radionuclide Inventory Specification,” requires that each waste producer project, in their
Waste Qualification Reports, the total quantities of individual radionculides in each canistered
waste form that are to be shipped to the repository. Additionally, Specification 3.9,
“Specification for Maximum Dose Rates,” of the EM-WAPS, sets limits on the surface (on
contact) gamma dose rates and neutron dose rate at the time of shipment of the final waste form.
Included in the Storage and Shipping Records must be either the calculated or measured values
for both gamma and neutron dose rates at the time of shipment. Finally, Specification 3.7,
“Specification for Removable Radioactive Contamination on External Surfaces,” sets specific
limits on the non-fixed (removable) radioactive contamination that is allowed on the exterior
surface of each canistered waste form. The methods and basis for meeting these specifications
must be described by each waste producer in their Waste Compliance Plan and Waste
Qualification Reports. Following is an example of the type of characterization data that meet this
requirement:
Section 223
Example: Radionuclide characterization data for high-level waste sludge contained in a
tank at Site X include:
Basis: Analysis based on results of 24 samples of dried sludge.
Volume: 37.9 m3 or 10,000 gallons
Density: 2.4 g/cc
Chemical Composition: by element, wt. % and imprecision (% relative standard
deviation)
Radionuclide Composition: by radionuclide, wt %, and imprecision (% relative
standard deviation)
For pre-immobilized high-level waste, the waste acceptance requirements for the storage,
pretreatment, and treatment facilities at which waste will be received dictate the radionuclide
parameters that are needed. Parameters which may be required include:
• total activity of the transferred waste, in curies;
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-93
7-09-99
• identity and activity per unit mass of the major radionuclides. For purposes of this
guidance, major radionuclides are those which are determined to be of importance
to the receiving pretreatment, storage, or treatment facility. These may be dictated
by the facility’s authorization basis and/or radioactive waste management basis.
All of the data requirements described above may not be required for all phases in the life-cycle
management of high-level waste. The specific data needs will be determined by the waste
acceptance requirements of a particular receiving pretreatment, storage, or treatment facility. To
assure the receiving facility’s waste acceptance requirements are met, follow the waste
certification process which is included of Section II.M.
Compliance with this requirement is demonstrated by the existence of records that document
characterization data for high-level waste that are consistent with the minimum characterization
data requirements.
Supplemental References:
1. DOE, 1999. Waste Acceptance System Requirements Document, Revision 3, DOE/RW
0351P, U.S. Department of Energy, Office of Civilian Radioactive Waste Management,
April 1999.
II. L.(3) Hazardous Characteristics. Waste characterization processes shall
yield sufficient chemical and physical data to clearly identify any
hazardous characteristics that may degrade the ability of structures,
systems, and components to perform their radioactive waste
management function.
Objective:
The objective of this requirement is to ensure availability of hazardous characteristics information
about high-level waste that could impact the integrity of confinement and containment systems,
the operation of process equipment, and the effectiveness of waste processes and other related
activities.
Discussion:
In conducting the hazard analyses for the development of the DOE M 435.1-1 requirements, the
identification and control of the hazardous constituents of high-level waste were identified as
being potentially significant factors in maintaining the high-level waste management facilities’
safety envelope for storage, pretreatment, and treatment operations. The term hazardous
Chapter II -High-Level Waste Requirements
II-94 DOE G 435.1-1
7-09-99
characteristics, used in this requirement, is not to be confused with the RCRA use of the same
term. Management of high-level waste streams that exhibit hazardous characteristics, as defined
by RCRA, e.g., corrosivity or toxicity for metals, is discussed in the guidance to DOE M 435.1-1,
Section II.C.
Hazardous characteristics of high-level waste are any qualities of the waste that pose a threat to
the safe management of high-level waste. These can be derived from compounds, chemicals, or
elements contained in the waste.
Section 224
A facility’s waste acceptance requirements and/or authorization basis will normally require
characterization data that are necessary to prevent these characteristics from jeopardizing the safe
confinement or containment of high-level waste. The following examples of parameters are
provided for consideration:
• minimum pH of waste, since the high-level waste tanks at many of the sites are
constructed of carbon steel. Solutions below a pH of 7 cause general corrosion of
the steel;
• volatile species, e.g., benzene and ammonia, that may generate flammable or
detonable concentrations of vapor in tanks and process vessels;
• corrosive species, e.g., chlorides and sulfates, that may cause corrosion of carbon
steel waste storage tanks;
• organic compounds, e.g., tributyl phosphate, that may generate flammable or
detonable concentrations of vapors in tanks and process vessels;
• shock sensitive compounds, e.g., silver nitride, that may breach the confinement
systems of high-level waste system processes.
Compliance with this requirement is demonstrated by the existence of records that document the
chemical and physical data for characteristics of high-level waste that may pose a hazard to high-
level waste structures, systems, and components.
Supplemental References: None.
II. M. Waste Certification.
A waste certification program shall be developed, documented, and implemented to
ensure that the waste acceptance requirements of facilities receiving high-level waste
for storage, pretreatment, treatment, or disposal are met.
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-95
7-09-99
Objective:
The objective of this requirement is to ensure that waste transferred to a facility for storage,
pretreatment, treatment, or disposal meets the receiving facility’s waste acceptance requirements
to reduce the likelihood that transferred wastes contain unacceptable materials or characteristics,
and to avoid hazards that would occur from the transportation and handling of waste packages
which do not meet acceptance requirements. Certification also ensure that the storage,
pretreatment, treatment, or disposal facilities receiving the waste operate within limits of
established safety and/or performance assessments.
Discussion:
As discussed in the guidance for Radioactive Waste Generator Requirements (Chapter I, Section
I.2.F.(7)), the Field Element Manager is to ensure development and approval of a program that
addresses the responsibilities of a waste generator. The generator requirements are to address
hazards associated with a waste management facility receiving unexpected volumes or types of
waste, or receiving waste that may not meet the waste acceptance requirements of the facility to
which it is transferred. The generator requirements address generation planning, waste
characterization, waste certification, and waste transfer. As discussed in this guidance, a
certification program is to be established by generators of radioactive waste to provide a
mechanism for confirming that waste is in compliance with the waste acceptance criteria of the
facility to which the waste is being transferred. The certification program is required by any
organization or facility that transfers waste to another facility.
The certification program is part of the waste generator program that is developed and approved
by the Field Element Manager, or designee. The certification program requires that an authorized
official confirm that waste meets the waste acceptance requirements of the facility to which it is
being transferred. Additional guidance, correlated to the specific requirements in Waste
Acceptance Requirements, Section II.J, is provided below.
Section 225
Program Development and Documentation. The waste certification program needed to meet this
requirement consists of a documented, structured process that works in concert with the DOE M
435.1-1 requirements for waste acceptance (Section II.J) and waste transfer (Section II.N) to
control the transfer of waste to storage, pretreatment, treatment, or disposal facilities.
Development of the waste certification program involves defining and documenting controls for
those items and activities that affect certifying that a waste and its packaging meets the waste
acceptance criteria of the receiving facility. This includes confirmation that the final (vitrified)
waste form meets the requirements of the EM-WAPS, thus ensuring acceptance of the waste into
the Civilian Radioactive Waste Management System. The documentation should include the
following:
Chapter II -High-Level Waste Requirements
II-96 DOE G 435.1-1
7-09-99
(Note: For those “Items and Activities Important to Waste/Product Quality,” as defined by each
high-level waste producer as part of their Waste Compliance Program/Plan, additional
requirements, as specified in RW-0333P (Quality Assurance Requirements and Description) apply
(see DOE G 435.1-1, Section II.G, Quality Assurance Program, for details)).
Organization(s) and Responsibilities. Certification program documentation needs to
identify the organizations involved in the certification process and the responsibilities of
each. Official(s) who are authorized to certify waste are identified in the documentation.
Quality Assurance. The certification program is subject to a quality assurance program.
The quality assurance program that applies to waste certification activities needs to be
identified and documented. The use of an existing quality assurance program under which
the certification activities will be performed is acceptable and appropriate.
Procedures. The process for certifying waste needs to be formalized in procedures. The
procedures describe to the user the steps that are to be followed and the administrative
process for ensuring waste streams are certified. The procedures also require a signed
statement certifying waste meets the appropriate criteria.
Procurement/Purchasing Controls. The procurement and/or purchase of items or services
that are significant to certifying that a waste package meets the waste acceptance criteria
of a receiving facility need to be documented. Such procurements may include the
purchase of materials such as waste containers or laboratory services (onsite or offsite).
As dictated by the type of procurement, the documentation should include or reference the
technical specifications for the item/service being procured, identification of quality
assurance requirements, including any required testing or inspections, specification of
documentation to be provided on delivery (e.g., fabrication inspection and/or test records,
a certificate of compliance or conformance, laboratory analytical results), and a statement
ensuring access to the provider’s facilities as necessary to perform audits and inspections.
The certification program ensures that the procurement documentation is reviewed and
approved by an official with knowledge of the need, intent, and requirements for the
procurement. The program also provides for documented verification commensurate with
the relative importance and complexity of the items or services being procured.
Section 226
Document Control. The principal documents that constitute the certification program
need to be subject to document control. Program documentation will identify which
documents are to be controlled. The waste certification program description, waste
certification procedures, and quality assurance program documentation need to all be
subject to document control. Document control includes review and approval, distribution
to designated recipients (users), and a controlled process for making changes to the
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-97
7-09-99
documents. Existing document control programs at a site may provide the necessary
controls for documents that are part of the waste certification program.
Training. The certification program needs to identify the training requirements for the
various individuals that are involved in the program. At a minimum, the program requires
training of the official who certifies the waste packages to the waste acceptance criteria of
the facility(ies) to which the waste is being transferred. In addition, individuals will need
to be trained to the procedures that control the part of the certification process with which
they are involved.
Records. The certification program documentation needs to describe the management of
certification records (see guidance for Section II. M.(1)).
Example: At Site Z, the Office of Defense Programs generates much of the high-level
waste that is sent to the waste storage tanks which are managed by the high-level waste
management organization. Using the above guidance, Defense Programs should work
with the receiving facility to define the waste certification program. Through a review of
the existing site procedures, site personnel may determine that the waste certification
program can operate under the existing site document control program, procurement
process, records management program, and training program. The certification
program documentation would include identification of these other programs as
applying, identify the facilities from which waste would be transferred, designate the
officials responsible for waste certification at those facilities, and develop procedures
(within the document control program) that ensure compliance with the waste acceptance
criteria. Within the existing programs, site personnel would identify the training
requirements, records to be maintained and retention times, technical specifications and
receipt requirements for obtaining waste packaging materials, and requirement for
analytical data. However, the existing site quality assurance program was found to be
inadequate and required the generation of new quality assurance documentation to
support the Defense Programs Certification Program. Operating within the parameters
defined by the high-level waste program, Defense Programs would be able to certify
waste for transfer to the high-level waste tank farms.
As noted in the preceding example, existing programs at a site may provide the framework within
which elements of the waste certification program can be addressed (e.g., quality assurance,
training, document control). The waste acceptance requirements of the facility to which the waste
is to be sent may impose additional requirements on what is to be included in the waste
certification program. Whether or not the waste acceptance requirements of the facility to which
waste is transferred mandate a waste certification program, the organization transferring the waste
is responsible for developing and implementing a certification program to provide internal
assurance that the waste acceptance requirements will be met.
Section 227
Chapter II -High-Level Waste Requirements
II-98 DOE G 435.1-1
7-09-99
Implementation. The waste certification program is implemented through the use of documented
controls, processes, and procedures. The key document in a waste certification program is the
certification statement, or equivalent. The certification statement is the documentation signed by
a designated official that certifies that the waste meets the appropriate requirements. Following is
a listing of the summary specifications, derived from DOE/EM-0093, Waste Acceptance Product
Specification for Vitrified High-Level Waste Forms, (EM-WAPS) for the final waste form, that
include the elements recommended for consideration in the development of certification
statements. While these specifications are specific to the final (vitrified) waste form they should
be applied during generation, storage, pretreatment, and treatment activities, as appropriate, to
ensure actions are not taken that may jeopardize final waste form compliance with them.
(Amplification on the summary and detailed specifications that are included is considered beyond
the scope of this Guide. Reference is made to the Waste Compliance Plans and Waste
Qualification Reports for the Defense Waste Processing Facility (DWPF) and the West Valley
Demonstration Project, both of which provide a detailed description of the methods by which they
each comply with the specifications.)
1. Waste Form Specifications
2. Canister Specifications
3. Canistered Waste Form Specifications
4. Quality Assurance Specifications
5. Documentation and Other Requirements
Graded Approach. A graded approach is used in implementing the waste certification program.
The above elements are recommended for both intrasite as well as intersite transfers of high-level
waste. While it is recognized that there currently are no intersite transfers of liquid high-level
waste, there may, at a later date, be transfers of the final waste form between sites to
accommodate interim storage. Intersite transfers involve not only certifying that the waste is in
compliance with the requirements for the receiving facility itself, but also with Department of
Transportation requirements. However, even though the above elements should be considered,
the process may be shortened and simplified for on-site transfers where the organizational
relationships and knowledge of the waste and waste generating activities may reduce the
information that needs to be documented and transferred with each transfer. For on-site transfers,
much of the information may already be available to the receiving facility.
Example: For on-site transfers, the receiving facility/organization may already have a
waste stream profile provided by the generator facility/organization. Because of the
existence of the waste stream profile, the certification may be as simple as an individual
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-99
7-09-99
trained to the waste transfer and certification procedures signing a waste transfer request
that provides the radionuclide inventory of the waste transfer being transferred and the
waste stream identification number.
The waste acceptance requirements of the facility receiving the waste (see DOE M 435.1-1,
Section II. J.) may dictate which items must be part of the certification statement. Even if such
information is not dictated by the receiving facility, the waste acceptance criteria should be used
as a resource for identifying key elements to include on the waste certification statement.
Section 228
Compliance relative to the development and documentation portion of the certification
requirement is demonstrated by a waste certification plan that identifies the organizations
involved, assigns responsibilities for implementing the program, and describes or references the
quality assurance, training, procurement controls, records management, and procedures to be
used by the program. Acceptable performance relative to implementing the program is
demonstrated by the appropriate personnel being trained, having and following the procedures
that govern their part of the waste certification process, the waste certification plan and
procedures being current and controlled in accordance with a document controls program, and
records related to certification (e.g., certification statements, training records, procurement
records, characterization records, packaging records) being generated and managed in accordance
with established site program.
Supplemental References:
1. DOE, 1996. Waste Acceptance Product Specifications for Vitrified High-Level Waste
Forms (EM-WAPS), Revision 2, DOE/EM-0093, U.S. Department of Energy,
Washington, D.C., December 16, 1996.
2. WSRC, 1994. DWPF Waste Form Compliance Plan, WSRC-IM-91-116-0, Westinghouse
Savannah River Corporation, Aiken, South Carolina, December 1994.
3. DOE, 1997. Waste Form Compliance Plan for the West Valley Demonstration Project
High-Level Waste Form, Revision 12, WVDP-185, U.S. Department of Energy,
December 1997.
II. M.(1) Certification Program. The waste certification program shall
designate the officials who have the authority to certify and release
waste for shipment; and specify what documentation is required for
waste generation, characterization, shipment, and certification. The
program shall provide requirements for auditability, retrievability,
Chapter II -High-Level Waste Requirements
II-100 DOE G 435.1-1
7-09-99
and storage of required documentation and specify the records
retention period.
Objective:
The objective of this requirement is to ensure the development of waste certification programs
that clearly identify the documentation required for certifying waste, specifying which personnel
have the authority to make the certification, and establishing a traceable and verifiable record of
and basis for certification.
Discussion:
Officials must designate who has the authority to certify that waste meets the waste acceptance
requirements of the receiving facility. To avoid having personnel who are not knowledgeable of
waste acceptance and transfer requirements authorizing the release of waste, the program needs
to identify, by title or name, the officials who are authorized to certify. The officials are qualified
by virtue of their position, responsibilities, and training to make this certification. The official(s)
have sufficient familiarity with the waste being generated and needs to have been trained relative
to the acceptance criteria of the receiving facility (and applicable transportation requirements) to
be able to certify in writing that the waste is acceptable for transfer. The official(s) also need to
have the authorization from the receiving facility to transfer the waste (see DOE M 435.1-1,
Section II. N., Waste Transfer). Implementation of this element should be tailored to specific site
needs and situations.
Section 229
Example: On-site transfers of high-level liquid waste from multiple facilities to the
high-level waste tank farm may involve multiple personnel (e.g., one for each generator
or process) being trained and having the authority to certify waste as meeting the tank
farm’s waste acceptance requirements. However, for the transfer of waste from the tank
farm to an on-site pretreatment or treatment facility, there may be a single designated
official at the site who has been trained relative to the acceptance criteria of the
pretreatment or treatment facility’s waste acceptance criteria that is authorized to certify
the waste as ready for transfer.
The waste certification program needs to specifically identify the documentation that needs to be
produced to support the certification that waste meets the waste acceptance criteria of the
receiving facility. The required documentation may include the following:
Waste Stream Profile (or record relating the waste to a previous profile). The waste
stream profile is a description of the waste stream, generally identifying the source,
physical and chemical description, and upper limits on radionuclides.
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-101
7-09-99
Radionuclide Characterization Data. Radionuclide characterization data include the
concentration and/or inventory of radionuclides as determined by characterization (see
guidance for DOE M 435.1-1, Section II. L., Waste Characterization).
EPA Uniform Hazardous Waste Manifest. The EPA manifest is required by 40 CFR Part
262 for the transfer of a hazardous or mixed waste.
Chain of Custody or Equivalent Documentation, and Packaging Data. (See guidance for
Waste Transfer, DOE M 435.1-1, Section II.N).
Radiological Survey Results (or documentation referencing a survey record). Survey
results include the determination of the surface contamination of the waste package and
the external dose rate (see Section II.L.).
Bill of Lading. A document indicating the contents of a shipment.
Certification Statement. The statement required by DOE M 435.1-1 to document that
waste is in compliance with the acceptance criteria of the facility to which the waste is
being shipped.
Authorization to Transfer. Documentation indicating that an official from the facility to
which the waste is to be shipped has authorized transfer of the waste to the facility.
For the final (vitrified) waste form, most, if not all, of the above recommended elements of the
waste certification program should be met by meeting the requirements of the Waste Acceptance
Product Specifications for Vitrified High-Level Waste Forms EM-WAPS (DOE/EM-0093).
Specifically, compliance with Specification 5.1, “Specification for Waste Acceptance
Documentation,” requires the development of production records (5.1.3) and storage and
shipping records (5.1.4). Development of these documents should provide the necessary program
documentation elements. An example of a production record table of contents for the Defense
Waste Processing Facility is included as an attachment to the EM-WAPS. The information that is
to be provided within the production record is expected to meet recommended elements of the
certification statement.
As noted for other elements of this requirement, the organization developing the certification
program uses a graded approach in determining which of these documents are needed.
Regardless of the extent of the required documentation, the certification statement can serve as a
checklist that all of the waste acceptance criteria have been considered and the waste is in
compliance.
Section 230
Chapter II -High-Level Waste Requirements
II-102 DOE G 435.1-1
7-09-99
In order to ensure that information is available if or when it is needed in the future, the waste
certification program needs to identify which records are to be maintained and how they are to be
maintained. The certification program documentation may include specific records management
requirements or may simply invoke an existing acceptable records management program.
Although no minimum record retention times are established in DOE M 435.1-1, certain records
need to be maintained indefinitely. Whereas hazardous waste regulations require only a three-year
retention period, the DOE geologic repository has specific requirements for disposal of high-level
waste and are specified in the EM-WAPS, Specification 5.1.3 and RW-0333P, U.S. Department
of Energy Office of Civilian Radioactive Waste Management Quality Assurance Requirements
and Description for the Civilian Radioactive Waste Management Program. Generating, storage,
pretreatment, or treatment facility waste management records may not be required beyond the life
of the facility or operation, provided pertinent information has been supplied to the facility where
the waste will be disposed.
Example: Operations personnel at a high-level waste tank farm would maintain records
of when they received waste, what the waste was (characterization data provided by the
generator), and to whom the waste was eventually transferred. Once the final waste form
is produced (via immobilization) and the EM-WAPS- and RW-0333P-required
production records and storage and shipping records are developed, the organization
responsible for the storage records would not need to retain records on these waste
streams. This is because the production records and storage and shipping records are to
be maintained as lifetime quality assurance records that transfer with the waste at the
time of disposal to the Office of Civilian Radioactive Waste Management.
To meet the requirement for auditability and retrievability, the method of records storage and
retention needs to allow a person to trace shipment or waste package information back to the
generator certification data (e.g., characterization data, source data, packaging data). In
accordance with the DOE M 435.1-1, Waste Transfer requirements (Section II. N), information
on the source and characteristics of the waste are to be transferred along with the waste.
However, it is not the intent of this requirement to cause the creation of the certification statement
for existing waste that was received without such information (i.e., waste in storage as of the
issuance of DOE O 435.1). Such documents should be created only for any subsequent transfers
of waste.
Compliance with this requirement is demonstrated by records showing that each waste transfer is
certified as having met the waste acceptance criteria of the facility to which it was transferred, that
the certification statement is supported by additional records regarding the waste source,
characterization, and packaging, and that the waste certification and transfer is in accordance with
a documented program.
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-103
7-09-99
Supplemental References:
1. DOE, 1996. Waste Acceptance Product Specifications for Vitrified High-Level Waste
Forms (EM-WAPS), Revision 2, DOE/EM-0093, U.S. Department of Energy,
Washington, D.C., December 16, 1996.
Section 231
2. DOE, 1995. Quality Assurance Requirements and Description and Description for the
Civilian Radioactive Waste Management Program, Revision 5, DOE/RW-0333P, U.S.
Department of Energy, Washington, D.C., October 2, 1995.
3. WSRC, 1994. DWPF Waste Form Compliance Plan, WSRC-IM-91-116-0, Westinghouse
Savannah River Corporation, Aiken, South Carolina, December 1994.
4. DOE, 1997. Waste Form Compliance Plan for the West Valley Demonstration Project
High-Level Waste Form, Revision 12, WVDP-185, U.S. Department of Energy,
Washington, D.C., December 1997.
II. M.(2) Certification Before Transfer. High-level waste shall be certified as
meeting the waste acceptance requirements before it is transferred to
the facility receiving the waste.
Objective:
The objective of this requirement is certify that waste meets the acceptance requirements of the
storage, pretreatment, treatment, or disposal facility before it is transferred, to prevent transferring
waste that could endanger receiving facility personnel, and to avoid the delay and potential
hazards associated with corrective actions taken to remedy non-compliant conditions.
Discussion:
The waste certification requirements above address development, implementation, and content of
a waste certification program. The requirement that waste be certified before transfer ensures that
the program is effective in preventing the transfer of waste that does not meet the waste
acceptance criteria of the facility receiving the waste for storage, treatment, or disposal. In
accordance with this requirement, waste is released for transfer to another facility only after there
is a certification by an authorized official that the waste acceptance requirements have been met.
Ensuring certification occurs prior to allowing the physical transfer of waste prevents potential
hazards associated with managing waste rejected by the facility to which it is transferred.
Requiring certification before waste is transferred also reduces the likelihood of having to recall a
Chapter II -High-Level Waste Requirements
II-104 DOE G 435.1-1
7-09-99
waste transfer due to a discovery by the certification official, after the waste is transferred, that
the waste does not comply with the waste acceptance requirements.
Certification that the waste is ready for transfer and meets the waste acceptance criteria and the
applicable transportation requirements, is a control point in the transfer process. The procedures
controlling waste transfer do not allow the transfer to occur unless the certification statement has
been signed. Once signed, the certification statement becomes part of the record for the transfer
of the waste (see Waste Transfer, Section II.N).
Compliance with this requirement is demonstrated by the presence of a certification program
approved by the DOE Field Element Manager (or designee), documented approval from the
receiving facility to implement the certification program, if needed, procedures which mandate the
use of a certification statement, and dated records of waste certification.
Supplemental References: None.
II. M.(3) Maintaining Certification. High-level waste that has been certified as
meeting the waste acceptance requirements for transfer to a
pretreatment, treatment, storage, or disposal facility shall be managed
in a manner that maintains its certification status.
Objective:
Section 232
The objective of this requirement is to ensure certified waste is managed so as to maintain the
validity of the certification status to avoid the unnecessary handling of the waste stream or final
waste form packages that would be involved in recertifying waste.
Discussion:
There may be instances where waste must be stored prior to being transferred to the next stage in
the waste management process. If waste is certified as meeting the waste acceptance criteria of
the receiving facility prior to storage, it needs to be stored and controlled so that the certification
remains valid until the waste can be transferred.
Example: As of the issuance of this guidance, the siting of the geologic repository for
high-level waste disposal had not been decided. However, high-level waste treatment
facilities at the Savannah River Site and West Valley Demonstration Project are
producing and certifying final waste forms that must be managed in accordance with the
requirements of the EM-WAPS. These requirements include, for example, Specifications
1.4.2, “Control of Temperature for Phase Stability” and 5.1.4, “Storage and Shipping
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-105
7-09-99
Records.” For the first specification, temperature monitoring of the canister storage
areas maintains certification status. For the second specification, both internal and
external audits ensure the documentation and permanent records support continued
certification status.
Actions necessary to certify a waste that involves the potential of radiation exposure of workers
should be deferred, if possible, until there is a reasonable expectation that the waste can be
transferred to the receiving facility within the time that the certification is valid. Routine
monitoring required for waste in storage may not permit all activities that could result in worker
exposure to be deferred.
This requirement is not to be interpreted in a manner that would interfere with a facility
performing an acceptable waste management function. Therefore, if a waste is certified as
meeting the waste acceptance criteria of a treatment facility, the requirement to maintain the
certification of the waste is not intended to prevent the treatment facility from proceeding with the
treatment even though such action would seemingly violate the certified status of the waste. The
requirement is instead intended to ensure that the waste be stored, transported, and staged at the
treatment facility in a manner that will allow personnel to treat the waste. In spite of the
protection provided for the waste, sampling prior to treatment may still be a necessary process
control step.
Specific requirements for protecting the certification status of a waste are generally negotiated
with the receiving facility. Requirements to be considered include protecting the waste,
preventing unauthorized introduction of material into the waste, and protecting the data on the
waste package. The Waste Transfer requirements (DOE M 435.1-1, Section II. N.) also address
protecting waste packages and data to ensure that characterization and packaging data remain
accurate and useable by waste managers. Final high-level waste form packages (canisters) need to
be protected from the elements in a manner that meets the storage requirements of the EM
WAPS. In addition, it is necessary to be able to relate each waste package to information about
the contents of the package. For the final high-level waste form, the EM-WAPS-required
production record provides the necessary data. Also required by the EM-WAPS are other
container (canister) requirements for identification, labeling, length and diameter (Specifications
2.3 and 2.4).
Section 233
Compliance with this requirement is demonstrated by site personnel showing that the storage of
liquid high-level waste and final waste form packages (canisters) are managed in facilities in a
manner that does not negate their certification status. Further, it is possible to trace each package
to its certification and the information supporting that certification.
Chapter II -High-Level Waste Requirements
II-106 DOE G 435.1-1
7-09-99
Supplemental References:
1. DOE, 1996. Waste Acceptance Product Specifications for Vitrified High-Level Waste
Forms (EM-WAPS), Revision 2, DOE/EM-0093, U.S. Department of Energy,
Washington, D.C., December 16, 1996.
2. DOE, 1995. Quality Assurance Requirements and Description and Description for the
Civilian Radioactive Waste Management Program, Revision 5, DOE/RW-0333P, U.S.
Department of Energy, Washington, D.C., October 2, 1995.
3. WSRC, 1994. DWPF Waste Form Compliance Plan, WSRC-IM-91-116-0, Westinghouse
Savannah River Corporation, Aiken, South Carolina, December 1994.
4. DOE, 1997. Waste Form Compliance Plan for the West Valley Demonstration Project
High-Level Waste Form, Revision 12, WVDP-185, U.S. Department of Energy,
Washington, D.C., December 1997.
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-107
7-09-99
II. N. Waste Transfer.
The following requirements are in addition to those listed in Chapter I of this
Manual.
(1) Authorization. High-level waste shall not be transferred to a storage,
treatment, or disposal facility until personnel responsible for the facility
receiving the waste authorize the transfer.
Objective:
The objective of this requirement is to ensure that transfers of high-level waste are made only with
the cognizance and approval of personnel at the facility receiving waste so the preparation can be
assured for its safe management.
Discussion:
As discussed in the guidance for DOE M 435.1-1, Section I.2.F.(7), General Requirements, the
radioactive waste generator program includes consideration for the generation planning,
characterization, certification, and transfer of high-level waste. During the development of
DOE O 435.1 and DOE M 435.1-1, a review of waste management functions indicated that the
transfer of waste without the knowledge of personnel at the facility to which it was sent presented
a potential hazard. If waste is transferred to a facility without prior authorization, the controls
necessary for the proper and safe management of the waste may not be in place. As a
consequence, the waste may have to be rejected and returned to the sender. This requirement
represents a control to minimize the potential for exposures and releases during the handling and
transfer of high-level waste.
Safe transfer of the waste can only be assured if the facility receiving the waste for storage,
pretreatment, or treatment has considered the acceptability of the waste versus its safety operating
constraints. Personnel at a storage, pretreatment, or treatment facility which authorize the
transfer of waste are indicating that they have the capability to receive the waste and manage it in
a manner that is protective of its workers, the public, and the environment. Therefore, for
purposes of safe life-cycle management it is essential that authorization be received before transfer
of high-level waste to a storage, pretreatment, or treatment facility. Meeting this requirement is
the responsibility of the organization or individual transferring (sending) the waste.
Section 234
The transfer of high-level waste represents moving the waste through a pipeline or to another part
of a facility through a pipeline. The analysis of the hazards associated with the management of
radioactive waste in the development of DOE O 435.1 and DOE M 435.1-1 indicated that the
transportation of liquid high-level waste represents a potential risk of containment and/or
Chapter II -High-Level Waste Requirements
II-108 DOE G 435.1-1
7-09-99
confinement failure. In order to minimize this risk, the transfer of high-level waste should be
minimized. The following are considered transfers:
(1) Waste is physically moved from one location to another, even if ownership does
not change.
(2) Waste is physically moved from one location to another and ownership changes.
(3) Waste is not physically moved, but ownership changes.
The actions and documentation necessary to obtain authorization will depend on the specific
storage, pretreatment, or treatment facility to which waste is to be transferred. In some cases, the
submittal of a waste stream profile which provides a description of the waste and a range of the
waste characteristics, augmented by conversations with the generator, may provide enough
information for the storage, pretreatment, or treatment facility staff to be confident that they can
safely manage the waste. In other cases, the waste acceptance requirements of the storage,
pretreatment, or treatment facility may dictate that an onsite visit and review of the generator’s
waste certification program be performed. In order to expedite the transfer of waste, staff
responsible for sending the waste need to ensure they understand what information and activities
need to be completed in order to receive transfer authorization.
Authorization to transfer waste needs to be received in writing and should state the scope of the
authorization. The authorization may specify a specific group of transfers or specific number of
transfers of a particular waste type. However, it is acceptable for the written authorization to
specify a waste stream(s) which the generator can send on a routine basis. Any additional
conditions or notification requirements can be included in the written authorization. Whereas it is
the responsibility of the storage, pretreatment, or treatment facility receiving the waste to prepare
the written authorization, the organization sending the waste must understand which waste has
been authorized.
Example: At Site Z, a high-level waste stream is periodically generated and transferred
to the high-level waste storage tanks. The waste stream is designated by the number
XX-2233. Consistent with site procedures, the generator prepares a waste stream profile
which describes the characteristics and projected generation rate of the waste stream and
provides it to the waste management organization responsible for operation of the tank
farm. The waste management organization reviews the waste stream profile and calls the
generator facility representative to clarify the information on the waste stream profile.
The waste management organization has previously reviewed the generator’s
certification program. Based on the certification program and the waste stream profile,
the waste management organization prepares a letter authorizing the generator to
transfer any waste that meets the XX-2233 profile until further notice. The authorization
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-109
7-09-99
Section 235
letter also states that the generator must provide the waste management organization
notice of the volume of the waste that is to be transferred 48 hours before a transfer
occurs.
When high-level waste is transferred (moved from one location to another) and the “ownership”
of the waste does not change (i.e., the same individual is responsible for both facilities), a separate
letter authorizing transfer may not be required. Recognizing that the intent of this requirement is
to ensure that the waste is expected and can be safely managed at the facility to which it is being
transferred, other documentation can serve as the written authorization.
Example: The manager of the waste management organization is the official responsible
for authorizing transfer of waste to either of two separate waste tank storage facilities,
Tank Farm C and Tank Farm D. Even though the waste acceptance criteria are the same
for the two tank farms, waste is accepted and logged into each facility separately. The
manager decides to consolidate all of the waste into one tank at Tank Farm C for more
efficient management. The written authorization to transfer is provided by the
certification statement indicating that the waste meets Tank Farm C waste acceptance
requirements, and the documentation of the new storage location on the waste
characterization and packaging data.
Compliance with this requirement is demonstrated by sites having procedures that require a
confirmation of authorization before releasing waste for transfer, and records showing that
transfers are made in accordance with written authorizations.
Supplemental References: None.
II. N.(2) Data. Waste characterization data and generation, storage,
pretreatment, treatment, and transportation information for high-
level waste shall be transferred with or traceable to the waste.
Objective:
The objective of this requirement is to establish and maintain information about the
characteristics of waste and the waste packaging to ensure that sufficient information to support
management of waste in a manner that is protective of workers, the public, and the environment.
Discussion:
The Radioactive Waste Management Manual, General Requirements, assigns the Field Element
Manager the responsibility of ensuring development and approval of a program that addresses the
Chapter II -High-Level Waste Requirements
II-110 DOE G 435.1-1
7-09-99
responsibilities of waste generators (DOE M 435.1-1, Section I.2.F.(7)). The generator
requirements are to address hazards associated with a waste management facility receiving
unexpected volumes or types of waste, or receiving waste that may not meet the applicable waste
acceptance requirements. Generator requirements address generation planning, waste
characterization, waste certification, and waste transfer. The requirement for traceability of data
addresses the hazards associated with transferring waste without providing adequate information
about the packaging and its content. Establishing and maintaining the identity of the waste, as
well as maintaining controls based on the waste’s hazards, are vital to its safe transfer.
Acquisition of information about the waste is addressed in the guidance on Waste
Characterization (DOE M 435.1-1, Section II.L). Certification that waste is ready for transfer
(i.e., meets the waste acceptance requirements and transportation requirements) is discussed in
the guidance on Waste Certification (DOE M 435.1-1, Section II.M). Maintenance of
documentation regarding transfer of waste is discussed later in this section of guidance.
Section 236
Establishing, maintaining, and communicating accurate information on high-level waste is
essential to the safe and proper management of the waste. In the process of developing DOE O
435.1 and DOE M 435.1-1, transfer was identified as the activity in the life-cycle management of
waste with the greatest potential for loss of information about waste packages or waste
characterization data, and the associated loss of adequate waste management controls to avoid
exposure or release of radioactivity. Therefore, when waste is transferred, the waste
characterization and packaging data must be properly transferred to the new “owner” (i.e.,
responsible waste manager) of the waste.
Example: An abnormally high-activity slurry of high-level waste was transferred to a
treatment (vitrification) facility for solidification. The waste was characterized and the
waste characterization information listed on the waste certification statement. Although
the waste met the waste acceptance criteria for the treatment facility and an
authorization to make the transfer was granted, the characterization information was not
transmitted before, or at the time of, the waste transfer. Since recent previous transfers
had been lower activity, i.e., normal, special radiological protection measures, required
for the high-activity waste at the vitrification facility’s sampling station, were not
invoked. During the first transfer of waste to the sampling station, local radiation
monitors alarmed, signaling the operators that the activity of the waste warranted
implementing the special rad protection procedures. Had the characterization
information been documented and transferred with the waste, treatment facility personnel
would have known it was high-activity waste and would have imposed the proper controls
on the waste to protect sampling station personnel.
Sufficient information about the packaging should be provided to the storage, treatment, or
disposal organization to which waste packages are transferred to ensure that the packages are
handled safely. Packaging is defined as a receptacle and any other components or materials
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-111
7-09-99
necessary for the receptacle to perform its required containment function. The waste package is
the packaging plus its contents (i.e., the waste). The information about the packaging that is
transferred with the waste should be supported by and traceable to the more detailed packaging
procurement information (see guidance on Packaging and Transportation, DOE M 435.1-1,
Section II.O)
When waste is initially placed in the packaging, the organization packaging the waste should
document and manage information regarding its characteristics (e.g., radioisotopic inventory, total
activity, radiation dose, waste form). When the waste package is physically transferred or the
“ownership” has changed, the information regarding the waste package must be provided to the
organization that acquires responsibility for the waste.
Section 237
The DOE/EM-0093, Waste Acceptance Product Specification for Vitrified High-Level Waste
Forms (EM-WAPS), requires packaging of the final (vitrified) waste form in a stainless steel
canister to perform the necessary containment function. Proper documentation of packaging
design and procurement records is necessary to ensure safe handling of a waste package.
Specification 5.1.3, “Production Records,” of the EM-WAPS provides the content requirements
for Production Records that must be met to allow disposal at the geologic repository. The
organization that procures the waste packaging is responsible for properly documenting the
essential information regarding the procurement. The purchaser should maintain this information
to answer future questions about subsequent procurements and address questions concerning the
adequacy of the package for its intended purpose. Examples of the content of Production
Records for the Defense Waste Processing Facility and the West Valley Demonstration Project
are included in the EM-WAPS at Appendix E. Included within the Production Records are the
following information on the canisters: canister material specification and compliance information
(2.1), canister fabrication and closure methods (2.2), canister length and diameter (2.4), and final
(filled) canister weight and overall dimensions (3.11).
Compliance with this requirement is demonstrated by procedures requiring that characterization
and packaging data be provided with each transfer and documented records of transfers show that
the information is being provided.
Supplemental References:
1. DOE, 1996. Waste Acceptance Product Specifications for Vitrified High-Level Waste
Forms (EM-WAPS), Revision 2, DOE/EM-0093, U.S. Department of Energy,
Washington, D.C., December 16, 1996.
2. WSRC, 1994. DWPF Waste Form Compliance Plan, WSRC-IM-91-116-0,
Westinghouse Savannah River Corporation, Aiken, South Carolina, December 1994.
Chapter II -High-Level Waste Requirements
II-112 DOE G 435.1-1
7-09-99
3. WVNS, 1995. Waste Form Compliance Plan for the West Valley Demonstration Project
High-Level Waste Form, WVDP-185, Revision 11, West Valley Nuclear Services
Company Incorporated, West Valley, New York, February 1995.
4. DOE, 1995. Hazardous Waste Determination of the DWPF Product, Revision 0, WSRC
IM-91-116-13, U.S. Department of Energy, February 1995.
II. N.(3) Records and Transfer Reporting. The records and transfer
requirements for canistered high-level waste forms shall comply with
DOE/EM-0093, Waste Acceptance Product Specification for Vitrified
High-Level Waste Forms, or DOE/RW-0351P, Waste Acceptance
System Requirements Document, for non-vitrified, immobilized high-
level waste.
Objective:
The objective of this requirement is to ensure that the hazardous waste requirements of DOE/EM
0093, Waste Acceptance Product Specifications for Vitrified High-Level Waste Forms, (EM
WAPS), are met in order to support the determination that the final (canistered) waste form is
acceptable to the high-level waste geologic repository.
Discussion:
Section 238
The current EM-WAPS are the technical specifications the waste form producers are required to
meet in order to ensure acceptance of their vitrified high-level waste into the Civilian Radioactive
Waste Management System. The Office of Environmental Management (EM) and the Office of
Civilian Radioactive Waste Management have agreed that the Office of Environmental
Management is to provide the final waste form specifications to the waste form producers and
that the Office of Environmental Management will ensure that the EM-WAPS is consistent with
the technical baselines as defined in DOE/RW-0351P, Waste Acceptance System Requirements
Document (WASRD). Thus the EM-WAPS governs all elements of the final, canistered, waste
form which includes the borosilicate waste glass, the stainless steel canister, and the sealed
canistered waste form.
The following background is provided to clarify the roles of the EM-WAPS and the WASRD. As
the waste form requirements for immobilized high-level waste developed, the Department and its
operating contractors selected borosilicate glass as a reference waste form. Several high-level
waste sites subsequently identified a vitrified waste form for their sites, and two high-level waste
vitrification facilities are currently operating to produce canisters of borosilicate waste-glass.
Recently, several new high-level waste streams have been identified. One such high-level waste
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-113
7-09-99
stream is the proposed insertion of small immobilized surplus plutonium containers within a
standard high-level waste canister; molten vitrified high-level waste is then poured around these
plutonium cans yielding a matrix immobilized waste form. This composite high-level waste
stream is considered high-level waste and can be disposed as such. Another proposed high-level
waste stream results from immobilizing the waste resulting from reprocessing certain spent
nuclear fuels using an electro-metallurgical process. In this case a non-vitrified waste form will
result.
In both these cases, a product that adheres to all the existing requirements of DOE/EM-0093,
Waste Acceptance Product Specifications for Vitrified High-Level Waste Forms, is not possible.
The exact waste form specifications that these two proposed waste forms must meet are unknown
at this time; however, they will be incorporated in DOE/RW-0351P, Waste Acceptance System
Requirements Document. That document is therefore cited for those unique immobilized high-
level waste forms that cannot meet the requirements of DOE/EM-0093, Waste Acceptance
Product Specifications for Vitrified High-Level Waste Forms (EM-WAPS).
As discussed in the guidance for DOE M 435.1-1, Section I.2.F.(7), General Requirements, the
radioactive waste generator program includes consideration for the generation planning,
characterization, certification, and transfer of high-level waste. In order to ensure the final
high-level (immobilized) waste form meets the specifications of the EM-WAPS, the
characterization and transfer responsibilities should include a determination of whether the waste
stream includes hazardous wastes, as defined by EPA’s or authorized states’ Resource
Conservation Recovery Act (RCRA) requirements.
Section 239
Specification 1.5, “Hazardous Waste Specification,” of the EM-WAPS, requires that each
producer determine and report to the Office of Civilian Radioactive Waste Management the
presence, or absence, of any hazardous waste listed in the RCRA requirements contained in the
Code of Federal Regulations (CFR), Title 40, Sections 261.30 through 261.33, “Lists of
Hazardous Waste,” in the waste or in any feed stream proposed for storage or disposal.
Furthermore, any RCRA-listed component in the waste shall require the producer to petition EPA
and the authorized state(s) to delist the waste as provided under Title 40, Subpart C, “Rulemaking
Petitions,” Part 260.22. Finally, the producer shall perform the appropriate tests and procedures,
as described under Title 40, Subpart C, “Characteristics of Hazardous Waste,” Parts 261.20
through 261.24, to determine if the waste that will be received by the Office of Civilian
Radioactive Waste Management, for transportation and disposal, exhibits any hazardous
characteristics. Any such waste that is shown to have hazardous characteristics shall be treated to
remove such characteristics.
A material is hazardous waste if: a) it contains a listed hazardous waste component, or b) it
exhibits hazardous characteristics (ignitability, corrosivity, toxicity, reactivity). Thus, a final
Chapter II -High-Level Waste Requirements
II-114 DOE G 435.1-1
7-09-99
(vitrified) waste form would be considered hazardous if it contains a listed hazardous waste or is
characteristically hazardous.
To comply with the first part of the EM-WAPS Specification, a review of the practices and
procedures at a site, from waste generation through post-treatment storage, should be performed
to determine if RCRA-listed hazardous wastes are present or introduced into the high-level waste
system. If the conclusion of such a review is negative, i.e., there are no RCRA-listed hazardous
components present in the pre-vitrified waste, then a declaration, with adequate supportive
documentation, is needed in the producer’s Waste Qualification Reports. If, however, the review
finds that listed waste components are present, then the Producer must petition the EPA and the
authorized state(s) to delist the waste for the final waste form to be acceptable to the disposal
repository. Additional information on the delisting process can be found at 40 CFR 260.22,
“Petitions to Amend Part 261 to Exclude a Waste Produced at a Particular Facility.”
The second part of the EM-WAPS Specification requires that the final (vitrified) waste form not
exhibit hazardous characteristics. A review of the final waste form (currently vitrified glass) is
expected to conclude that the glass is a stable waste form and therefore is not corrosive, ignitible,
or reactive. However, to demonstrate that the final waste form is not characteristic hazardous
waste for toxicity, the glass should be subjected to the appropriate tests and procedures as
described in the cited regulations. Currently, the appropriate test is the Toxicity Characteristic
Leaching Procedure (TCLP) found at 40 CFR 261.24, “Toxicity Characteristic,” which is the
EPA mandated test for determining whether a waste form retards the release of specific
contaminants, i.e., hazardous metals (i.e., arsenic, barium, cadmium, chromium, lead, mercury,
selenium, and silver) and organics. If the glass passes this test, i.e., it contains concentrations
lower than the values presented in the requirements for the specific contaminants, then it is not
characteristic hazardous waste.
Section 240
Further amplification on the EM-WAPS Specification is considered beyond the scope of this
Implementation Guide. Refer to the EM-WAPS and the Waste Compliance Plans and Waste
Qualification Reports for the Defense Waste Processing Facility and the West Valley
Demonstration Project for additional information. Both provide detailed descriptions of the
methods by which they each comply with this specification.
Compliance with this requirement is demonstrated by documenting compliance with Specification
1.5 of the EM-WAPS.
Supplemental References:
1. DOE, 1996. Waste Acceptance Product Specifications for Vitrified High-Level Waste
Forms (EM-WAPS), Revision 2, DOE/EM-0093, U.S. Department of Energy,
Washington, D.C., December 16, 1996.
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-115
7-09-99
2. WSRC, 1994. DWPF Waste Form Compliance Plan, WSRC-IM-91-116-0,
Westinghouse Savannah River Corporation, Aiken, South Carolina, December 1994.
3. WVNS, 1995. Waste Form Compliance Plan for the West Valley Demonstration Project
High-Level Waste Form, Revision 11, Draft E, WVDP-185, West Valley Nuclear Services
Company Incorporated, West Valley, New York, February 1995.
4. DOE, 1995. Hazardous Waste Determination of the DWPF Product, Revision 0,
WSRC-IM-91-116-13, February 1995.
5. EPA. Petitions to Amend Part 261 to Exclude a Waste at a Particular Facility ,40 CFR
Part 260 Subpart C, U.S. Environmental Protection Agency, Washington, D.C.
6. EPA. Characteristics of Hazardous Wastes, 40 CFR Part 261, Subpart C, 261.20
through 261.24, U.S. Environmental Protection Agency, Washington, D.C.
7. EPA. Lists of Hazardous Wastes, 40 CFR Part 261, Subpart D, 261.30 through 261.33,
U.S. Environmental Protection Agency, Washington, D.C.
8. DOE, 1999. Waste Acceptance System Requirements Document, Revision 3, DOE/RW
0351P, U.S. Department of Energy, Washington, D.C., April 1999.
Chapter II -High-Level Waste Requirements
II-116 DOE G 435.1-1
7-09-99
II. O. Packaging and Transportation.
The following requirements are in addition to those in Chapter I of this Manual.
(1) Canistered Waste Form. Immobilized high-level waste shall meet the
requirements of the DOE/EM-0093, Waste Acceptance Product Specifications
for Vitrified High-Level Waste Forms, or DOE/RW-0351P, Waste Acceptance
System Requirements Document, for non-vitrified immobilized high-level
waste.
Objective:
The objective of this requirement is to ensure that the final high-level waste form satisfies
packaging and transportation requirements as specified in DOE/EM-0093, Waste Acceptance
Product Specifications for Vitrified High-Level Waste Forms (EM-WAPS), or DOE/RW-0351P,
Waste Acceptance System Requirements Document (WASRD), for non-vitrified immobilized
high-level waste. These documents provide the technical specifications the waste form is required
to satisfy in order to ensure acceptance of the vitrified waste form into the Civilian Radioactive
Waste Management System.
Discussion:
The packaging and transportation requirement of DOE M 435.1-1 is narrowly focused on
producing a canistered waste form for which there is a path forward. To achieve that goal,
consideration must be given to the packaging requirements contained in the EM-WAPS or the
WASRD, prior to the generation of the final high-level waste form. The EM-WAPS is based on
the WASRD, which was developed by the Office of Civilian Radioactive Waste Management
(RW) and establishes the specifications that high-level waste must satisfy to be acceptable to the
Office of Civilian Radioactive Waste Management. For purposes of DOE O 435.1, “acceptable”
is evidenced by documentation that the canistered waste form satisfies the specifications described
in the EM-WAPS. Satisfaction of the EM-WAPS is intended to be essentially the same as
acceptability for disposal.
Section 241
The Office of Civilian Radioactive Waste Management is responsible for developing geologic
disposal capability for high-level waste and for transporting the high-level waste to the repository.
Additional information relevant to the Office of Civilian Radioactive Waste Management’s
responsibilities and the interfaces between the Office of Civilian Radioactive Waste Management
and the Office of Environmental Management are included in the guidance for Section II.S,
Disposal.
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-117
7-09-99
The following background is provided to clarify the roles of the EM-WAPS and the WASRD. As
the waste form requirements for immobilized high-level waste developed, the Department and its
operating contractors selected borosilicate glass as a reference waste form. Several high-level
waste sites subsequently identified a vitrified waste form for their sites, and two high-level waste
vitrification facilities are currently operating to produce canisters of borosilicate waste-glass.
Recently several new high-level waste streams have been identified. One such high-level waste
stream is the proposed insertion of small immobilized surplus plutonium containers within a
standard high-level waste canister; molten vitrified high-level waste is then poured around these
plutonium cans yielding a matrix immobilized waste form. This composite high-level waste
stream is considered high-level waste and can be disposed as such (Draft EIS, DOE/EIS-0283-D,
Surplus Plutonium Disposition Draft Environmental Impact Statement, DOE, 1998). Another
proposed high-level waste stream results from immobilizing the waste resulting from reprocessing
certain spent nuclear fuels using an electro-metallurgical process. In this case a non-vitrified
waste form will result.
In both these cases a product that adheres to all the existing requirements of EM-WAPS is not
possible. The exact waste form specifications that these two proposed waste forms must meet are
unknown at this time; however, they will be incorporated in WASRD. That document is therefore
cited for those unique immobilized high-level waste forms that cannot meet the requirements of
EM-WAPS.
The EM-WAPS requirements apply only to the vitrified waste forms that have been qualified by
the Office of Civilian Radioactive Waste Management and include waste packaging requirements.
Qualification may be sought for additional waste forms at sites that do not currently have high-
level waste processing facilities in operation. Transportation of liquid high-level waste is not
anticipated and is not addressed by the requirements in the EM-WAPS.
Example: Most of the high-level wastes at INEEL are now in the form of a calcine.
Production processes and waste stream input for preparation of a final canistered waste
form are likely to differ significantly from the processes at Savannah River and at West
Valley. Therefore, waste management personnel at INEEL will develop waste acceptance
product specifications tailored to their high-level waste stream and consistent with the
WASRD.
The EM-WAPS specifications are divided into three technically oriented categories -- waste form
specifications, canister specifications, and canistered waste form specifications -- and two
administratively oriented categories -- quality assurance specifications and documentation and
other requirements.
Waste Form Specifications. The EM-WAPS includes specifications for several elements relevant
to packaging and transportation. Waste form specifications in the EM-WAPS include chemical
Section 242
Chapter II -High-Level Waste Requirements
II-118 DOE G 435.1-1
7-09-99
composition, radionuclide inventory, product consistency, phase stability, hazardous waste, and
safeguards reporting. Descriptions of the tests for establishing compliance with the waste form
specifications are to be included in the Waste Form Compliance Plan. The Waste Form
Qualification Report contains the results of all of these tests except for the safeguards
information. The results are reported on a canister-by-canister basis in the production records.
Chemical Composition and Radionuclide Inventory: These specifications require
projection or reporting of specific chemical, crystalline phase, and radionuclide
information and provide that the waste form be a borosilicate glass.
Product Consistency: This requirement provides for consistency (with the benchmark
glass described in the environmental assessment on Waste Form Selection for Savannah
River Plant High-Level Waste) in the glass composition.
Phase Stability: This specification requires information on the glass transition
temperature, a time-temperature-transformation diagram, and temperature control.
Hazardous Waste: This specification requires determination of the presence or absence of
any hazardous waste. The results of the determination are to be reported to the Office of
Civilian Radioactive Waste Management.
Safeguards: The final waste form specification in the EM-WAPS is for safeguards
purposes. Satisfaction of this specification requires reporting of quantities of uranium and
plutonium isotopes on a canister-by-canister basis.
Canister Specifications. Canister specifications in the EM-WAPS include materials, fabrication
and closure, identification and labeling, and canister length and diameter. Descriptions of the tests
for establishing compliance with the canister specifications are to be included in the Waste Form
Compliance Plan. The Waste Form Qualification Report generally contains the test results. Data
on individual canisters (materials, fabrication, closure, length, diameter, wall thickness) are
captured in the production records.
Materials: The material specification requires that the canister be made of austenitic
stainless steel.
Fabrication and Closure: The fabrication and closure specification requires that the closed
canister be leak-tight under well-defined vacuum conditions. The Waste Form
Qualification Report provides evidence that the fabrication and closure methods can
produce a canister that satisfies the leak-tightness criterion.
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-119
7-09-99
Identification and Labeling: The identification and labeling specification imposes
requirements for the alphanumeric identifiers used, where they are located, and other
requirements for readability and durability.
Length and Diameter: The length and diameter specification provides the dimensional
ranges for these parameters.
Canistered Waste Form Specifications. Canister specifications in the EM-WAPS include
requirements on free liquid, gas content, various kinds of reactivity, organic materials, chemical
compatibility, canister fill height, removable contamination, heat generation, maximum dose rates,
subcriticality, weight and overall dimensions, drop tests, handling features, and plutonium
concentration. Descriptions of the tests or methods for establishing compliance with the
canistered waste form specifications are to be included in the Waste Form Compliance Plan. The
Waste Form Qualification Report generally contains the test results. Fill height data on individual
canisters are captured in the production records. Storage and Shipping Records document, by
canister, information on removable contamination tests, heat generation rate, dose rate, and
weight.
Section 243
Free Liquid: The free liquid specification prohibits detectible liquid in the canistered waste
form.
Gas Specification: The gas specification includes requirements on allowable gases and
their partial pressures inside the canister at closure as well as gases that could be generated
after sealing the canisters.
Reactivity: The reactivity of the contents of the canister requires that the generator ensure
that there are not detectable amounts in a canister of materials that are explosive,
pyrophoric, or combustible.
Organic Materials: The organic materials specification prohibits detectable amounts of
organic material in the canistered waste form after closure.
Chemical Compatibility: The chemical compatibility specification addresses interaction
between the canister and its contents.
Fill Height Specification: The fill height specification requires that each canister be filled
to at least 80 percent of the empty volume of the canister.
Removable Contamination: The removable contamination specification provides limits on
allowable radioactive material contamination and guidance on performing wipe tests to
evaluate contamination levels.
Chapter II -High-Level Waste Requirements
II-120 DOE G 435.1-1
7-09-99
Heat Generation: The heat generation specification establishes a maximum rate of 1500
watts per canister, at the year of shipment, and requires reporting of expected heat
generation rates.
Dose Rate: The specification for maximum surface dose rate provides that the gamma
rate not exceed ten thousand rem per hour and that the neutron rate not exceed 10 rem
per hour.
Subcriticality: The subcriticality specification establishes the maximum calculated
effective multiplication factor and states that criticality shall not be possible unless at least
two unlikely, independent changes occur in conditions essential to nuclear criticality
safety.
Weight and Dimensions: The specifications for weight and overall dimensions require that
the canistered waste form not exceed 2,500 kilograms. This specification also establishes
height and diameter limits for the canistered waste form.
Drop Test: The drop test specification requires that the canistered waste form withstand a
seven-meter drop onto an essentially unyielding surface.
Handling Features: The handling features specification establishes the standard canistered
waste form features that allow for grasping and moving the canistered waste form. The
generator describes the grapple in the Waste Form Compliance Plan and provides the
designs in the Waste Form Qualification Report.
Plutonium Concentration: The plutonium concentration specification requires that the
concentration in the canistered waste form be less than 2500 grams per cubic meter.
Quality Assurance Specifications. Generators of high-level waste are required to establish a
quality assurance program to verify that the specifications established in the EM-WAPS are
satisfied. The quality assurance program must be consistent with the Office of Civilian
Radioactive Waste Management Quality Assurance Requirements and Description,
DOE/RW-0333P, and with the Office of Civilian Radioactive Waste Management Waste
Acceptance System Requirements Document. Guidance to Sections I.E.(12) and II.G of
DOE M 435.1-1 provide additional information on these documents.
Documentation and Other Requirements. The four key records that provide documentation for
determining compliance with the EM-WAPS and the results of those determinations are the
Waste Form Compliance Plan, the Waste Form Qualification Report, the Production Records, and
the Storage and Shipping Records.
Section 244
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-121
7-09-99
Waste Form Compliance Plan: The Waste Form Compliance Plan describes tests,
analyses, and process controls for demonstrating compliance with the EM-WAPS as well
as commitments to meet the EM-WAPS.
Waste Form Qualification Report: The Waste Form Qualification Report is the record of
results of the tests and analyses to demonstrate the producers ability to comply with the
EM-WAPS.
Production Records: The Production Records provide descriptions of each canistered
waste form.
Storage and Shipping Records: The Storage and Shipping Records provide physical
description of the individual canistered waste forms and document any abnormal events
that occur during storage.
Compliance with the transportation and packaging requirement of DOE M 435.1-1 can be
demonstrated with a waste certification process that documents that the specifications of the
EM-WAPS have been met.
Supplemental References:
1. DOE, 1999. Waste Acceptance System Requirements Document, Revision 3, DOE/RW
0351P, U.S. Department of Energy, Office of Civilian Radioactive Waste Management,
April 1999.
2. DOE, 1982. Waste Form Selection for the Savannah River High-Level Waste
Environmental Assessment, DOE/EA-0179, U.S. Department of Energy, Washington,
D.C., 1982.
3. DOE, 1995. Quality Assurance Requirements and Description, DOE/RW-0333P, U.S.
Department of Energy, Office of Civilian Radioactive Waste Management, Washington,
D.C., October 2, 1995.
4. DOE, 1996. Waste Acceptance Product Specifications for Vitrified High-Level Waste
Forms (EM-WAPS), Revision 2, DOE/EM-0093, U.S. Department of Energy,
Washington, D.C., December 16, 1996.
5. Paperiello, 1999. C.J. Paperiello to L.H. Barrett, letter, U.S. Department of Energy Plans
for Disposal of Surplus Weapons Plutonium, U.S. Nuclear Regulatory Commission,
Washington, D.C., January 25, 1999.
Chapter II -High-Level Waste Requirements
II-122 DOE G 435.1-1
7-09-99
6. DOE, 1998. Surplus Plutonium Disposition Draft Environmental Impact Statement,
DOE/EIS-0283-D, U.S. Department of Energy, Washington, D.C., July 1998.
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-123
7-09-99
II. P. Site Evaluation and Facility Design.
The following requirements are in addition to those in Chapter I of this Manual:
(1) Site Evaluation. Proposed locations for high-level waste facilities shall be
evaluated to identify relevant features that should be avoided or must be
considered in facility design and analyses.
(a) Each site proposed for a new high-level waste facility or expansion of
an existing high-level waste facility shall be evaluated considering
environmental characteristics, geotechnical characteristics, and
human activities.
(b) Proposed sites with environmental characteristics, geotechnical
characteristics, or human activities for which adequate protection
cannot be provided through facility design shall be deemed unsuitable
for the location of the facility.
Objective:
The objective of this requirement is to ensure that natural environmental factors, human activities,
and geotechnical characteristics of proposed sites are considered in selecting the location and
design features of new high-level waste management facilities or significant modifications of
existing facilities. In addition, that locations are avoided if facility design cannot compensate for
poor site characteristics, environmental conditions, or adverse human activities.
Section 245
Discussion:
The Radioactive Waste Management Manual (DOE M 435.1-1), General Requirements and
Responsibilities, Section I.1.E, invokes the requirements of DOE O 420.1, Facility Safety, and
DOE O 430.1A, Life-Cycle Asset Management, in site evaluation and facility design. In the
development of DOE M 435.1-1, it was determined that specific attention should be given to
selection of a waste management facility location with consideration given to the beneficial and
detrimental aspects of the site.
Site evaluation includes the identification and characterization of potential sites for new high-level
waste management facility or expansion of existing facilities. Selection of sites for DOE facilities
is generally constrained to those federal lands owned and managed by DOE. Within DOE
reservations, the process of selecting sites has the purpose of identifying the best location with
consideration of features which are desirable for a facility. In addition, it is recognized that often
a National Environmental Policy Act (NEPA) analysis will be conducted prior to the initiation of
Chapter II -High-Level Waste Requirements
II-124 DOE G 435.1-1
7-09-99
the site evaluation process. The results of this process should be considered during the site
evaluation process to ensure the bounds of the NEPA analysis are not exceeded. Finally, the site
evaluation process produces a set of data and analysis that is often used to establish a facility’s
authorization basis and Radioactive Waste Management Basis (RWMB). Therefore, data and
analysis quality, as well as records management, are important and must be ensured.
In the context of this requirement the terms environmental factors/characteristics (natural and
human), geotechnical characteristics, and human activities are used to capture specific site
elements that determine its suitability for the proposed facility. These include:
• ecology - the flora and fauna that have evolved and adapted to the other
environmental characteristics of the site;
• topography - the physical features of the ground surface at and around the site;
• meteorology - the normal and extreme weather events of the site;
• hydrology - the surface and ground water at the site;
• geology - the sediment and structural features of the earths crust at the site;
• seismology - the earthquake potential of the area;
• volcanology - the volcano potential of the area;
• soil characteristics - characteristics of the soil that affect its load-bearing, water
infiltration;
• human activities - proximity of the public and human-induced events both internal
and external to the facility;
• emergency services and response - proximity of services and population sheltering;
and
• hazards to other facilities - proximity of existing facilities and proposed facility.
Potential regional impact due to construction, operation or decommissioning of the facility and
the extent of such regional impacts will be determined on the basis of measurable effects on the
population or the environment from the construction, operation, or decommissioning of the
facility.
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-125
7-09-99
Various requirements and guidance documents exist for compliance with National Environmental
Policy Act requirements that are relevant for evaluation of a site. These include DOE O 451.1A,
National Environmental Policy Act Compliance Program, and the “Green Book” (the NEPA
Compliance Guide). The “Green Book” includes guidance for performing habitat evaluations.
This guide should be consulted in evaluating characteristics of potential sites to assess potential
impacts on biological resources including any endangered or threatened species.
Section 246
Characterization of a site should result in collecting the data necessary to support a decision on
acceptability of a site and for use in site-specific design of a facility. The site characterization and
selection process will vary from one DOE site to the next because of substantial differences in the
environmental/geotechnical characteristics or human activities of the sites. Similarly, the interests
of stakeholders which vary from site to site are likely to influence the issues to be addressed in site
characterization and selection. The level of characterization should be established using a data
quality objective-type process where the type and amount of information to be collected is
commensurate with the hazards and the decisions which have to be made based on the data. The
resulting site characterization program should include the investigations and studies needed to
evaluate site and facility performance.
Natural Phenomena Hazards. The characterization of a site for natural phenomena hazards is to
identify the range of normal and extreme natural events that should be taken into account in the
siting and design of the facility. The amount of characterization necessary will be influenced by
the hazard associated with the facility and release of the radionuclide inventory. Guidance on
characterization and consideration of natural phenomena hazard in the design of DOE facilities is
contained in the following standards supporting implementation of Facility Safety (DOE O
420.1):
• Natural Phenomena Hazards Characterization Criteria;
• Natural Phenomena Hazards Assessment Criteria;
• Natural Phenomena Hazards Performance Categorization Guidelines for
Structures, Systems, and Components;
• Natural Phenomena Hazards Design and Evaluation Criteria for Department of
Energy Facilities; and
• Guidelines for Use of Probabilistic Seismic Hazard Curves at Department of
Energy Sites for Department of Energy Facilities.
Example: A new immobilized high-level waste storage facility is being considered at
Site X. Due to the environmental setting, wind effects, seismic activity and volcanic ash
Chapter II -High-Level Waste Requirements
II-126 DOE G 435.1-1
7-09-99
are factors that have to be considered in the design regardless of the location selected at
the site. However, due to the local topography, concerns about flooding can be
addressed by selecting a location on the site’s central plateau. A similar facility is being
considered at Site Y. The Site Y evaluation includes the consideration of flooding and
high winds in the design regardless of location. However, seismic concerns are minimal
because of the region of the country; also flooding impacts can be mitigated by selecting
an appropriate area of the site.
In carrying out characterization activities, field studies should be performed so as to not
compromise the integrity of the land to be dedicated to waste management activities. This is
particularly relevant to disposal facilities where improper design or installation of core sampling or
groundwater sampling wells can lead to a preferential path for the migration of contaminants from
a facility. Also, the characterization should be carried out in accordance with the site’s quality
assurance program, including maintaining records of data collected. Documentation of the results
of the site characterization program is not only needed for use in facility design and establishment
of facility-specific safety design criteria, but may also provide information necessary for
complying with requirements of the NEPA process.
Section 247
Human Activities. The site of a proposed high-level waste management facility should be
evaluated with respect to the effects of the facility on human activities and the effect of human
activities on the facility. Effects of the facility location on human activity should include
consideration of
• transportation routes;
• present and future population distribution;
• present and proposed land and water uses in the region and the hazards they may
pose to the proposed facility; and
• any special characteristics that would influence the consequences of releases of
radioactive material during the life cycle of the facility.
The potential impact of the waste management facility construction, operation, and
decommissioning should be evaluated, considering current and future land use plans and
population distribution. Evaluation and selection of the location for a facility should ensure that
there is and will remain a buffer between the facility and the public. Such considerations in site
selection provide defense-in-depth by ensuring there is space for corrective actions to be taken if
there are unplanned releases and by establishing distance for attenuation of such releases so that
impacts are minimized.
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-127
7-09-99
Example: Site X is going to construct a facility to treat high-level waste to make it
acceptable for off-site disposal. There are no natural environmental characteristics that
make any of the proposed locations superior to others. However, one location is in the
center of the site and the others are either near the current site boundary or in areas
being cleaned up so they can be released from DOE control. Because the criteria for
selecting a site include consideration of the proximity to current and future populations,
the location near the center of Site X is preferred.
Another aspect of human activities is the affect that they may have on the waste management
facility. Locating a facility near other facilities on or near the DOE site may impact the design or
performance of the facility. For instance, a tall building may create a wake on its downwind side
that would cause the exhaust effluent to be dragged down to ground surface in a short distance
with the potential of impacting workers or nearby member of the public. To counter act this
effect, the waste management facility would have to extend its stack higher than the wake effect,
or an alternative location for the facility should be considered.
The term “adequate protection” is intended to support the protection of the worker, public, and
the environment to the extent required by applicable requirements, e.g., 10 CFR Part 835, and
DOE Orders, e.g., DOE 5400.5. Therefore, a site should be selected based on the protection it
affords in meeting the requirements contained in applicable regulations and DOE Orders through
site characteristics and/or facility design features.
Compliance with this requirement is demonstrated by performing an appropriate site evaluation
for new facilities or expansions of existing facilities, and by the ensuring that the environmental
and geotechnical characteristics of the site which are significant to protection of workers, the
public or the environment are accounted for in selection of the site or through facility design.
Supplemental References:
1. DOE, 1997. Design Consideration Manual, Draft, U.S. Department of Energy, 1997.
Section 248
2. DOE, 1992. Guidelines for Use of Probabilistic Seismic Hazard Curves at Department
of Energy Sites for Department of Energy Facilities, DOE-STD-1024-92, Change 1, U.S.
Department of Energy, 1992.
3. DOE, 1993. Natural Phenomena Hazards Performance Categorization Guidelines for
Structures, Systems, and Components, DOE-STD-1021-93, Change 1, U.S. Department
of Energy, 1993.
Chapter II -High-Level Waste Requirements
II-128 DOE G 435.1-1
7-09-99
4. DOE, 1994. Natural Phenomena Hazards Design and Evaluation Criteria for
Department of Energy Facilities, DOE-STD-1020-94, Change 1, U.S. Department of
Energy, 1994
5. DOE, 1994. Natural Phenomena Hazards Characterization Criteria,
DOE-STD-1022-94, Change 1, U.S. Department of Energy, 1994.
6. DOE, 1995. Natural Phenomena Hazards Assessment Criteria, DOE-STD-1023-95
Change 1, U.S. Department of Energy, 1995.
7. DOE, 1995. Implementation Guide for Nonreactor Nuclear Safety Design Criteria and
Explosives Safety Criteria, Revision G, U.S. Department of Energy, September 1995.
8. DOE, 1997. DOE O 451.1A, National Environmental Policy Act Compliance Program,
U.S. Department of Energy, June 1997.
9. DOE, 1998. National Environmental Policy Act Compliance Guide, U.S. Department of
Energy, Office of NEPA Policy and Assistance, August 1998.
10. NRC. Licensing Requirements for the Storage of Spent Fuel in an Independent Spent
Fuel Storage Installation, 10 CFR Part 72, U.S. Nuclear Regulatory Commission,
Washington, D.C.
11. DOE. Occupational Radiation Protection, 10 CFR Part 835, U.S. Department of Energy,
Washington, D.C.
12. DOE, 1993. Radiation Protection of the Public and Environment, DOE 5400.5, Change
2, U.S. Department of Energy, January 1993.
II. P.(2) Facility Design. The following facility design requirements, at a
minimum, apply:
Objective:
The objective of this requirement is to ensure that a minimum set of high-level waste facility
design requirements determined from hazards analyses or policy considerations are applied to
high-level waste management facilities.
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-129
7-09-99
Discussion:
The general design requirements included at DOE M 435.1-1, Sections II.P.(2)(a) through (j), are
included as requirements to ensure adequate protection of the public, workers, and the
environment from nuclear hazards. The requirements contained in these sections apply to all
high-level waste management facilities, except for: II.P.(2)(b), Confinement; II.P.(2)(e);
Consideration of Decontamination and Decommissioning; and II.P.(2)(h), Structural Integrity,
which apply to new or modifications to existing high-level waste facilities. Modification is
generally considered to be an action that significantly increases the probability of a nuclear
accident or requires a change to an operations’ authorization basis (Implementation Guide for
DOE O 420.1, draft Revision G). Discretion is intended to allow upgrading of existing safety
equipment or the installation of minor new improvements without subjecting the process to
onerous procedural requirements and thus discouraging improvements. However, modifications
to facility design and construction during the design and construction phase shall conform to the
design requirements established in this section for new facilities.
Section 249
For additional design assistance, refer to the DOE Handbook, DOE-HDBK-1132-99, Design
Considerations. This Handbook includes information and considerations for the design of
systems typical to nuclear facilities, design considerations specific to various types of special
facilities, and information useful to various design disciplines. The Handbook specifically includes
design considerations for confinement systems and radiation protection and effluent monitoring
systems as well as good practices and design principles that should be considered in specific
design disciplines.
The analysis of the hazards associated with the management of high-level waste in the
development of DOE O 435.1 and DOE M 435.1-1 indicated that appropriate general design
requirements are essential to ensuring the protection of the public, workers, and the environment.
Therefore the intent of these requirements is to have them applied to all high-level waste
management facilities, both existing and new. However, it is recognized that in some cases it may
not be practical, or possible, to apply these requirements to existing high-level waste facilities or
operations. In such cases, an exemption to the requirement may be warranted. These situations
are separate from the exceptions noted above. Exemptions to the requirements may be due to
conditions such as limited programmatic usage, expected short service life of the operation, or
other reasons that make long-term, capital intensive upgrades unreasonable. In this case, non
compliance with the subject requirements requires the use of the exemption process, as provided
at DOE M 435.1-1, Section I.1.E. Section I.1.E. provides for the use of an exemption to a
requirement provided it is processed in accordance with the requirements of DOE M 251.1-1A,
Directives System Manual. The guidance to Section I.1.E. provides additional information on the
DOE M 251.1-1A exemption process.
Chapter II -High-Level Waste Requirements
II-130 DOE G 435.1-1
7-09-99
Example: At Site Q, it is determined that the requirement in DOE M 435.1-1, Section II.
P.2.(d), Ventilation, is not met by an existing high-level waste pretreatment process. The
process has been shutdown for an extended period of time but has been maintained in a
standby mode pending a decision on whether it is needed for future high-level waste
processing/treatment missions. Specifically, the existing process has an air filtration
system that provides adequate decontamination factors for the radionuclides of concern
but lacks proper fire protection to the filter media. In accordance with DOE M 251.1
1A, Chapter VII, “Exemptions,” an Exemption Request is prepared that supports the
position that application of the requirement is not justified by any safety and health
benefit at this time. If the decision is made to restart the process, the decision to upgrade
the fire protection system for the ventilation system will be revisited. The Exemption
Request is processed in accordance with the requirements contained in paragraph 4.,
Exemption Process, in Chapter VII.
The application of these requirements to all existing high-level waste facilities may conflict with
the direction or guidance provided by some other DOE Orders that are invoked by the DOE M
435.1-1, General Requirements, Section I.1.E, Requirements of Other Regulations and DOE
Directives. In such cases the requirements contained in DOE M 435.1-1 have precedence over
requirements contained in other DOE Directives invoked by DOE M 435.1-1.
Section 250
Example: Section I.1.E.(18), Site-Evaluation and Facility Design, invokes DOE O 420.1,
Facility Safety. Guidance to DOE O 420.1 states that the design criteria included in that
Order are “applicable to the design and construction of new nonreactor nuclear facilities
and for modifications to existing nonreactor nuclear facilities when modifications
significantly increase the probability or consequences of a nuclear accident or require a
change in the Technical Safety Requirements (TSRs) of a facility. The definition of the
term ‘significant’ is intentionally left to the judgment of the proposing contractor and the
approving DOE authority to define ‘significant.’ In part, this is intended to allow
upgrading of existing safety equipment or installation of minor new improvements
without subjecting the process to onerous procedural requirements and thus discouraging
improvements.” Thus, under DOE O 420.1, an existing high-level waste management
facility that is to be “in-significantly” modified does not have to meet the design
requirements of DOE O 420.1. However, under DOE M 435.1-1, the same high-level
waste management facility must meet the design requirements of DOE M 435.1-1,
Section II.P.2.(a) through (j), or the requirements that are not to be implemented are
subjected to the DOE M 251.1-1A exemption process. The requirements contained in
DOE M 435.1-1 have precedence, and should be implemented, in lieu of those contained
in DOE O 420.1 (invoked by DOE M 435.1-1, Section I.1.E).
A “backfit” process has been discussed by the Department in the past to address changes that may
be required through the imposition of a new DOE safety requirement. Such changes are
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-131
7-09-99
particularly problematic for many high-level waste facilities and systems that have been in
existence for over 20 years. It is not the purpose of DOE O 435.1 and DOE M 435.1-1 to create
such a process for the Department; however an existing or new field-office or Program Secretarial
Office backfit analysis and review process may be applied to determine whether implementation of
a proposed backfit could be justified on the basis of a substantial safety improvement or on a cost-
benefit basis. One example of a candidate process is contained in expired DOE N 5480.5,
Imposition of Proposed Nuclear Safety Requirements, which expired in 1993 because of an
administrative provision. Another candidate process is described Draft DPOM-FS-300,
“Treatment of Proposed Backfits,” which was developed for the Office of Defense Programs, but
not formally adopted. A third candidate process is documented in Westinghouse Savannah River
Company, High Level Waste Management Engineering Procedure, ENG. 12, “HLWMD Backfit
Analysis Procedure.” For development of new backfit processes Nuclear Regulatory Commission
requirements in 10 CFR 50.109 and 10 CFR 76.76 should be consulted.
Compliance with this requirement is demonstrated by documentation that supports the
implementation of the requirements at Section II.P.2.(a) through (j), or documentation that
supports implementation of the “Necessary and Sufficient Closure Process” or “Integrated Safety
Management System,” or the DOE M 251.1-1A, Exemption Process.
Supplemental References:
1. DOE, 1998. Directives System and Directives System Manual, DOE O 251.1A and DOE
M 251.1-1A, U.S. Department of Energy, January 30, 1998.
Section 251
2. DOE, 1995. Implementation Guide for Nonreactor Nuclear Safety Design Criteria and
Explosives Safety Criteria, Revision G, U.S. Department of Energy, September 1995.
3. DOE, 1993. Defense Programs Operations Manual, “Treatment of Proposed Backfits,”
Draft DPOM-FS-300, Revision 0, U.S. Department of Energy, February 5, 1993.
4. DOE, 1999. Design Considerations, DOE-HDBK-1132-99, U.S. Department of Energy,
Washington, D.C., April 1999.
II. P.(2) Facility Design. The following facility design requirements, at a
minimum, apply:
(a) Safety (Safety Class and Safety-Significant) Structures,
Systems, and Components. Safety structures, systems, and
components for high-level waste storage, pretreatment, and
treatment facilities shall be designated and designed consistent
Chapter II -High-Level Waste Requirements
II-132 DOE G 435.1-1
7-09-99
with the provisions of DOE O 420.1, Facility Safety; DOE
5480.22, Technical Safety Requirements; and DOE 5480.23,
Nuclear Safety Analysis Reports.
Objective:
The objective of this requirement is to ensure the identification and function of safety-class and
safety-significant structures, systems, and components for high-level waste management facilities
are consistent with the provisions of applicable DOE Orders.
Discussion:
DOE M 435.1-1, Section I.1.E.(8), requires that the management of radioactive waste
management facilities, operations, and activities prepare and maintain hazard analysis
documentation and that an authorization basis be prepared, as required by DOE O 425.1A,
Startup and Restart of Nuclear Facilities, DOE 5480.21, Unreviewed Safety Questions, DOE
5480.22, Technical Safety Requirements, and DOE 5480.23, Nuclear Safety Analysis Reports.
For high-level waste management facilities implementation of these Orders require an integrated
approach to the development of a high-level waste operation’s safety analysis, hazard analysis,
and accident analysis, all of which contribute to the operation’s Authorization Basis. An
Authorization Basis defines the aspects of a high-level waste facility’s design basis and operational
requirements that are relied upon by DOE to authorize operations. Details of this integrated
approach are provided in the DOE Standard, DOE-STD-3009-94, as well as the Department’s
recently issued Guide for an Integrated Safety Management System, DOE G 450.4-1. Following
is a summary of this approach; refer to these documents, and the guidance for each, for further
details.
The development of a high-level waste management facility Authorization Basis is necessary to
assure safe operation of a facility, operation, or activity. A critical element of all high-level waste
management facility’s Authorization Basis is a facility-specific, or operation-specific Safety
Analysis Report. DOE 5480.23 requires the development of a Safety Analysis Report for Hazard
Category 1, 2, and 3 operations for the purpose of ensuring a facility can be constructed,
operated, maintained, shut down, and decommissioned safely and in compliance with applicable
laws and regulations. Since most high-level waste management facilities or operations are
designated Hazard Category 2 or 3 operations, through the process prescribed in the DOE-STD
1027-92, they require the preparation of a Safety Analysis Report. (Note: For those high-level
waste management facilities that are designated a hazard category below Hazard Category 3, as
defined by DOE-STD-1027-92 (e.g., Radiological Facilities), refer to the DOE-EM Limited
Standard, DOE-EM-STD-5502-94, for guidance on safety analysis requirements.) The
requirement in Section II.P.(2)(a) does not apply to facilities, operations, or activities that are
below Hazard Category 3.
Section 252
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-133
7-09-99
DOE 5480.23, through DOE-STD-1027-92, also requires the preparation of a hazard analysis for
Hazard Category 1, 2, and 3 operations, with the purpose of systematically identifying facility
hazards and accident potentials through a hazard identification and evaluation process. The
importance of a hazard analysis centers on its thoroughness since it requires evaluation of the
complete spectrum of hazards and accidents that an operation may be subjected to.
From the hazard analysis, a limited subset of accidents (i.e., design-basis accidents) that bound the
envelope of accident conditions and to which the operation could be subjected, are carried
forward to the accident analysis. The accident analysis is used to designate safety-class
structures, systems, and components by comparing the accident consequences to DOE’s (Offsite)
Evaluation Guidelines for the public. Information obtained from specific accidents or
representative accidents are used to specify function requirements for safety-class structures,
systems, and components in the Safety Analysis Report. The safety-class designation of
structures, systems, and components are reserved for those structures, systems, and components
needed for public protection, and as such carries with it the most stringent requirements (e.g.,
enhanced inspection, testing and maintenance, and special instrumentation and control systems).
With the identification of a high-level waste facility’s safety-class structures, systems, and
components, Technical Safety Requirements (TSR) can be derived by using the screening criteria
provided by DOE 5480.22, Technical Safety Requirements. Technical Safety Requirements for
safety-class structures, systems, and components are generally restricted to those that are needed
to meet the DOE Evaluation Guidelines for public protection. See DOE-STD-3009-94, for a
discussion on the DOE Evaluation Guidelines.
Example: At Site X, the high-level waste vitrification plant hazard analysis and accident
analysis concludes that an explosion of the melter will result in the maximally exposed
offsite individual receiving a dose at the site boundary that exceeds the DOE Evaluation
Guidelines. To mitigate such a release, the melter cell offgas monitoring system is
designated a safety-class structure, system, and component. Development of the
Technical Safety Requirements for the facility conclude that a Technical Safety
Requirement “Safety Limit” and an accompanying “Limiting Control Setting” is
required to prevent this accident from occurring.
Likewise, safety-significant structures, systems, and components, which are the major
contributors to the defense-in-depth philosophy and worker safety, are identified by a hazard
analysis. Safety-significant structures, systems, and components are developed by qualitatively
evaluating the credible accidents and designating structures, systems, and components that further
protect the onsite workers or support defense-in-depth.
Example: At Site Y, the high-level waste evaporator hazard analysis and accident
analysis concludes that during the design basis earthquake, a number of evaporator
support systems could fail (e.g., normal power, emergency power, cooling water,
Chapter II -High-Level Waste Requirements
II-134 DOE G 435.1-1
7-09-99
Section 253
instrument air, steam, and ventilation) causing components associated with the
evaporator’s safe shutdown to fail. Analysis indicates that the DOE Evaluation
Guideline for public exposures is not exceeded, however, radiological and chemical
exposures to onsite workers could be significant. Therefore a number of structures,
systems, and components at the evaporator are designated safety-significant: instrument
air, primary ventilation system, and the emergency power system. In addition, a number
of Technical Safety Requirements (Limiting Conditions of Operation) are assigned to
support worker protection and defense-in-depth. Included are hardware and
administrative actions that ensure continued supply of ventilation air to the evaporator,
off-gas filtration, air flow monitoring, seismic detection, and backup power supply.
Compliance with this requirement is demonstrated if safety-class and safety-significant structures,
systems, and components designations are consistent with the cited DOE Orders and Technical
Standards. In addition, the design and maintenance of these designated structures, systems, and
components shall be consistent with the hazard analysis, accident analysis, and Safety Analysis
Report that supports the facility’s Authorization Basis.
Supplemental References:
1. DOE, 1994. Preparation Guide for U.S. Department of Energy Nonreactor Nuclear
Facility Safety Analysis Reports, DOE-STD-3009-94, U.S. Department of Energy,
Washington, D.C., July 1994.
2. DOE, 1997. Integrated Safety Management System Guide, DOE G 450.4-1, U.S.
Department of Energy, Washington, D.C., November 1997.
3. DOE, 1992. Hazard Categorization and Accident Analysis Techniques for Compliance
with DOE Order 5480.23, Nuclear Safety Analysis Reports, DOE-STD-1027-92, U.S.
Department of Energy, Washington, D.C., December 1992.
4. DOE, 1994. DOE Limited Standard, Hazard Baseline Documentation, DOE-EM-STD
5502-94, U.S. Department of Energy, Washington, D.C., August 1994.
II. P.(2) Facility Design. The following facility design requirements, at a
minimum, apply:
(b) Confinement. High-level waste systems and components shall
be designed to maintain waste confinement. The following
requirements apply to new or modifications to existing high-
level waste tank systems, ancillary systems, and components.
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-135
7-09-99
1. Secondary confinement systems shall be designed to
prevent any migration of wastes or accumulated liquid
out of the waste system; shall be capable of detecting,
collecting, and retrieving releases into the secondary
confinement; and shall be constructed of, or lined with,
materials that are compatible with the waste(s) to be
placed in the waste system.
Objective:
The objective of these requirements is to ensure that high-level waste is invoked in the high-level
waste system process vessels, structures, and ancillary systems and components by emphasizing
the importance of secondary confinement and the integrity of system and component connections.
Discussion:
In addition to the facility and general design requirements contained in Chapter I, General
Requirements (Section I.1.E), the above requirements for high-level waste confinement shall be
met. The term “confinement” is defined in Attachment 2, Definitions, to DOE M 435.1-1, as:
“The control or retention of radioactive materials within a designated boundary.
Primary confinements are process enclosures and other spaces normally containing
radioactive material. Secondary confinement surrounds one or more primary
confinement systems.”
Section 254
In broad terms, the purpose of confinement systems is to minimize the spread of radioactive
and/or hazardous materials and the release of these materials in facility effluents during normal
operations, abnormal operations, and potential accidents. These requirements and much of the
following guidance is based on detailed requirements developed by the Environmental Protection
Agency in support of hazardous waste confinement in 40 CFR Parts 264 and 265, Subpart J, Tank
Systems. Most untreated, mobile high-level waste is also a mixed waste that must also meet
certain hazardous waste requirements. The 40 CFR Parts 264 and 265 requirements allow
implementation of one set of requirements for both the radioactive and chemical hazard. A
primary function of process equipment is to provide primary confinement and prevent or mitigate
radioactive and/or hazardous material releases to the environment. Process equipment that
provides primary confinement includes tanks, piping, pressure vessels, pumps, valves, and glove
boxes. Secondary confinement systems are those systems that provide the next level of
confinement and may include a second barrier incorporated in process equipment, e.g., double-
walled tanks, double-walled piping systems, and glove boxes, as well as ventilation and offgas
systems, that further prevent or mitigate uncontrolled releases of radioactive and/or hazardous
materials to the environment. The need for redundancy and the degree of redundancy in these
Chapter II -High-Level Waste Requirements
II-136 DOE G 435.1-1
7-09-99
systems should be determined by the safety analysis process and maintenance concerns for both
active and passive components.
For a specific high-level waste facility or operation, the number and arrangement of confinement
systems or barriers and their required characteristics need to be determined on a case-by-case
basis. Factors that need to be considered in confinement system design include type, quantity,
form and conditions for dispersing the high-level waste material during normal operations and
design basis conditions. Engineering evaluations, trade-offs, and experience should be used to
develop practical designs that achieve confinement system objectives. The adequacy of
confinement systems to perform effectively the needed functions should be documented and
accepted through the facility or operation Safety Analysis Report.
The intent of the requirement at Section II.P.(2)(b)(1) is to impose secondary confinement
requirements on high-level waste systems and ancillary components and to ensure that the
secondary confinement system shall prevent the outflow of high-level waste to the soil,
groundwater, or surface water during the high-level waste system’s design life. Design of the
secondary confinement system needs to be integrated with the hazard analysis and safety analysis
process to ensure that the risks of high-level waste collecting outside the primary confinement are
addressed. Integration of this requirement is best assessed by monitoring the volume of waste in
the tank and monitoring the surrounding soil, groundwater, and surface water for the inflow of
waste.
This requirement also prescribes the provisions for designing and constructing the secondary
confinement of a high-level waste system. Detection requirements of the secondary confinement
systems for failure of the primary confinement is also provided by Section II.P.(2)(b)(2) and
Section II.T, Monitoring Program.
Section 255
Additional guidance, consistent with the performance-based requirements in DOE M 435.1-1, is
recommended to promote effective implementation of the higher level requirements. Additionally,
secondary confinement systems need to be:
• Constructed of or lined with materials that are compatible with the waste(s) to be
placed in the tank system and have sufficient strength and thickness to prevent
failure due to pressure gradients (including static head and external hydrological
forces), physical contact with the waste to which it is exposed, climatic conditions,
and the stress of daily operation (including stresses from nearby vehicular traffic);
• Placed on a foundation or base capable of providing support to the secondary
confinement system, resistance to pressure gradients above and below the system,
and capable of preventing failure due to settlement, compression, or uplift;
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-137
7-09-99
• Provided with a leak-detection system that is designed so that it will detect the
failure of either the primary or secondary confinement structure or the presence of
any release of hazardous waste or accumulated liquid in the secondary confinement
system in accordance with facility requirements determined from safety analyses or
environmental permit restrictions; and
• Sloped or otherwise designed or operated to drain and remove liquids resulting
from leaks, spills, or precipitation. Spilled or leaked waste and accumulated
precipitation should be removed from the secondary confinement system to meet
facility administrative controls or operational requirements determined from safety
analyses or environmental permit restrictions.
Secondary confinement for tanks may include devices such as vaults and double-walled tanks. A
vault is normally either a steel-lined concrete vessel containing the primary confinement vessel or
a concrete vessel properly protected by sealants to protect the concrete from the effects of the
waste. Double-walled tanks are normally steel or concrete tanks with two walls. Leakage from
the primary wall is retained between the two tank walls until it is detected and can be removed.
In general, vault systems need to be:
• Designed or operated to contain 100 percent of the capacity of the largest tank
within its boundary;
• Designed or operated to prevent infiltration of precipitation into the secondary
confinement system unless the collection system has sufficient excess capacity to
contain infiltration. Such additional capacity should be sufficient to contain
precipitation from a 25-year, 24-hour rainfall event;
• Constructed with chemical-resistant water stops in place at all joints (if any);
• Provided with an impermeable interior coating or lining that is compatible with the
stored waste and that will prevent migration of waste into the concrete;
• Provided with a means to protect against the formation of and ignition of vapors
within the vault, if the waste being stored or treated is:
1. ignitable waste; or
2. reactive waste and may form an ignitable or explosive vapor;
Chapter II -High-Level Waste Requirements
II-138 DOE G 435.1-1
7-09-99
• Provided with an exterior moisture barrier or be otherwise designed or operated to
prevent migration of moisture into the vault if the vault is subject to hydraulic
pressure.
Section 256
Example: At Site Z, a high-level waste separations facility was constructed to remove
strontium and cesium from the liquid residue from dissolution of spent fuel. The tanks,
pumps, valves, piping, and additional ancillary equipment is enclosed in a concrete vault
to provide secondary confinement and to protect workers from radiation. The inside
surfaces of the vault were coated with an epoxy resin to prevent absorption of any
releases from the primary confinement into the concrete vault. The expansion joints of
the vaults are sealed with a flexible silicone sealer to help contain any releases from the
primary confinement and to prevent intrusion from the exterior of precipitation, surface
water, and groundwater. The waste to be processed is not ignitable or reactive, so
provision for controlling such vapors need not be included.
The intent of the guidance in paragraphs (iii), (iv), and (vi) above is to protect secondary
confinement systems from the harmful effects of high-level waste and to prevent the migration of
groundwater into the secondary confinement system.
Double-walled tanks are to:
• Designed as an integral structure (i.e., an inner tank completely enveloped within
an outer shell) so that any release from the inner tank is contained by the outer
shell.
• Protected, if constructed of metal, from both corrosion of the primary tank interior
and of the external surface of the outer shell; and
• Provided with a built-in continuous leak detection system capable of detecting any
releases of high-level waste in the outer shell in accordance with facility
requirements determined from safety analyses or environmental permit restrictions.
The intent of this guidance is to design and construct the primary and secondary confinement
systems as one integral system and to provide continuous leak detection system capability within
the secondary confinement system. Detection of leaked wastes in the secondary confinement
system is important to alert operators of a release from the primary vessel and removal is
necessary to reduce the potential for contamination and exposure.
High-level wastes or treatment reagents are not be placed in a tank system if they could cause the
tank, its ancillary equipment, or the containment system to rupture, leak, corrode, or otherwise
fail.
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-139
7-09-99
Due to the hazardous nature of high-level waste and potential airborne and liquid pathway
contamination it poses, the requirements that apply to high-level waste facilities apply also to
ancillary equipment. Ancillary equipment is considered to include piping, valves, jumpers, valve
pits, and other equipment with which the high-level waste can reasonably be expected to be in
contact.
Variances or Exemptions to Secondary Confinement Requirements. Variances or exemptions
from the secondary confinement requirements for new non-immobilized high-level waste handling,
transfer, and storage facilities may not meet exemption criteria because of the potential hazard and
releases/exposures liquid or calcined high-level waste may pose. The high-level waste hazard
analysis conducted in support of preparing DOE M 435.1-1 identified numerous pathways for the
release of high-level waste with the principle one being loss of, or lack of, secondary confinement.
Additionally, the selected scenarios that involved loss of, or lack of, secondary confinement
resulted in high hazard consequences. Therefore, an exemption from the secondary confinement
requirements for new high-level waste facilities that are involved in the handling, transfer, and
storage of non-immobilized high-level waste, i.e., high-level waste that has not yet been
immobilized in its final glass or ceramic form that meets the EM-WAPS specifications, is not
likely to meet exemption criteria.
Section 257
II. P.(2) Facility Design. The following facility design requirements, at a
minimum, apply:
(b) Confinement.
2. Tank and piping systems used for high-level waste
collection, pretreatment, treatment, and storage shall be
welded construction, except where remote
configurations or periodic rerouting of high-level waste
streams require non-welded construction.
Objective:
The objective of this requirement is to ensure that high-level waste tank and piping systems
provide the maximum protection possible to the public and the environment by requiring welded
construction except in those cases where remoteness or rerouting of the component/piping
requires non-welded construction to support operations.
Discussion:
The intent of the requirement for tank and piping systems to be welded construction whenever
feasible is to offer the maximum protection possible to systems containing high-level waste.
Chapter II -High-Level Waste Requirements
II-140 DOE G 435.1-1
7-09-99
However, it is recognized that welded construction is not practical where transferring of
high-level waste streams requires frequent rerouting, e.g., jumpers within tank farm diversion
boxes or when the remoteness, service life, or maintenance requirements of a component/piping
requires the use of jumpers. In such cases non-welded construction of piping systems is
considered adequate when use of non-welded connections is supported by the operations’
authorization basis or radioactive waste management basis.
Example 1: At Site X, a new storage tank is to be added to the existing high-level waste
tank farm. The new tank is to be constructed at a significant distance from the existing
tanks using welded piping. However, to support transfers, the connection to the existing
tank farm is made at a diversion box that utilizes piping jumpers with non-welded
connections.
Example 2: At Site Y, a high-level waste transfer pump is located in a shielded transfer
pit that requires periodic removal for maintenance. Piping and instrumentation
connections to the pump use jumpers, in lieu of welded connections, to facilitate remote
removal.
Supplemental References:
1. EPA. Tank Systems, 40 CFR Parts 264 and 265 Subpart J, U.S. Environmental Protection
Agency, Washington, D.C.
II. P.(2) Facility Design. The following facility design requirements, at a
minimum, apply:
(c) Lifting Devices. The design of hoisting and rigging devices
shall comply with the following specific requirements:
1. Lifting devices that are designated as safety class or
safety significant shall be designed to prevent free fall of
loads.
2. Loading and unloading systems for lifting devices that
are designated as safety class or safety significant shall
be designed with a reliable system of interlocks that will
fail safely upon malfunction.
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-141
7-09-99
Objective:
The objective of this requirement is to ensure that special attention is devoted to the design of
hoisting and rigging devices in order to avoid releases that could result from dropping a container
of high-level waste and to avoid damage to high-level waste containers and systems (e.g., transfer,
pretreatment, treatment) that could occur by dropping equipment, containers, or other objects.
Discussion:
Section 258
The hazards analysis performed to guide development of DOE M 435.1-1 revealed that lifting and
rigging activities pose a high hazard for many high-level waste activities. In particular, physical
and chemical treatment of high-level waste in large storage tanks often involves the use of large,
heavy equipment such as mixers and pumps. Typically, the access to the tanks is through
relatively small risers. Manipulation of loads in restricted spaces with the additional complication
of high radiation and reduced visibility due to use of containment huts requires that precautions be
taken to guard against dropping loads into and onto containers, transfer equipment (e.g.,
pipelines, valves), and other systems containing high-level waste.
Lifting devices that are designated as safety class or safety significant are subject to the
additional requirements for “design to prevent free fall” and “fail safe interlocks on devices for
loading and unloading systems for lifting devices.” These requirements also apply when the lifting
device is not itself a safety class or safety significant device but it could position loads above
safety class or safety significant structures, systems, and components. Safety class structures,
systems, and components means structures, systems, and components (SSCs) that are relied upon
to protect the safety and health of the offsite public as identified by the safety analysis. Safety
significant SSCs means structures which are not designated as safety class SSCs, but whose
preventive or mitigative function is a major contributor to defense-in-depth (i.e., prevention of
uncontrolled material release) and/or worker safety, as determined from hazard analyses. (These
definitions are taken from the guide for DOE O 450.4).
Example: An underground tank containing 500,000 gallons of high-level waste is
determined to have separated into layers, and one of the layers appears to contain
materials that are reacting to form a potentially explosive gaseous product. The
decision has been made to mix the contents of the tank to reduce the potential for abrupt
release of accumulations of explosive gas. The mixer chosen weighs 2 tons and must be
inserted through a three foot diameter riser. Because of the potential for damage to the
tank and release of high-level waste, as well as contamination of workers involved in the
activity, the lifting device is classified as a safety significant SSC and the special
requirements for prevention of free fall of loads and fail safe interlocks for loading and
unloading devices must be applied. In this case, the mechanism used to grasp or hook
the pump must include an interlock to prevent lifting of the pump unless it is securely
Chapter II -High-Level Waste Requirements
II-142 DOE G 435.1-1
7-09-99
grasped or hooked. Also, the lifting device (e.g., crane, hoist, fork lift) must include a
system to prevent free fall of the pump. The lifting activity described in this example is
also subject to the critical lift provisions of DOE-STD-1090-96 as required by the
hoisting and rigging operational requirements in Section II.V.(1).
Compliance with this requirement can be demonstrated by the development and implementation
of procedures that:
C Identify safety class and safety significant lifting devices and safety class and safety
significant structures systems and components that would be adversely impacted by
the failure of the lifting device;
Section 259
C Establish the requirements of II.P.(2)(c) as high-level waste design requirements for
the lifting device and the associated loading and unloading system; and
C Assures the design requirements are incorporated in the construction and modification
of the lifting devices.
Supplemental References:
1. NRC. Disposal of High-Level Radioactive Wastes in Geologic Repositories, 10 CFR
Part 60, Subpart E, Technical Criteria, paragraph 60.131(b)(10), U.S. Nuclear Regulatory
Commission, Washington, D.C.
2. DOE, 1996. Hoisting and Rigging, DOE STD 1090-96, U.S. Department of Energy,
Washington, DC, September 1996. (a U.S. Department of Energy standard).
3. DOE, 1997. Integrated Safety Management System Guide, DOE G 450.4-1, U.S.
Department of Energy, Washington, D.C., November 1997.
II. P.(2) Facility Design. The following facility design requirements, at a
minimum, apply:
(d) Ventilation.
1. Design of high-level waste pretreatment, treatment, and
storage facilities shall include ventilation through an
appropriate filtration system to maintain the release of
radioactive material in airborne effluents within the
applicable requirements.
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-143
7-09-99
Objective:
The objective of this requirement is to ensure that airborne releases of radioactive materials will at
all times be maintained within limits specified in applicable DOE Orders and regulations and
requirements of other relevant Federal and State agencies.
Discussion:
Ventilation, filtration, and off-gas systems need to be designed to ensure that the releases of
airborne radioactive particulate material during normal and off-normal conditions conform to:
C the limits specified in 10 CFR Part 835, Occupational Radiation Protection, for
workers and for members of the public in controlled areas;
C the limits established in other applicable DOE Orders such as DOE 5400.5, Radiation
Protection of the Public and the Environment, and
C generally applicable standards for releases of radioactive material to the environment
that have been promulgated by the Environmental Protection Agency, including those
for the Clean Air Act, 40 CFR Part 61.
The limits for release cited in DOE 5400.5, Radiation Protection of the Public and the
Environment, and in the Clean Air Act requirements, 40 CFR Part 61, are for the DOE site (i.e.,
all the activities of the Department at that site), not for individual facilities. Therefore, the
operational limits for any individual facility should be established based on the potential impacts
from all facilities on the site. Consistent with Departmental practices, and an underlying principle
in development of the Radioactive Waste Management Manual, airborne releases should be kept
as low as reasonably achievable.
Attention to fire protection for filtration on these ventilation systems is important because of the
potential presence of flammable and explosive gases that led to the requirement for ventilation.
Guidance for fire protection of filtration systems in ventilation plenums for nuclear facilities is
provided in Fire Protection Design Criteria, DOE-STD-1066-97. Typical requirements address
materials of construction, location of filters, fire ratings of protective walls, and internal detectors
for fire and high heat.
To preclude the ventilation system itself from becoming a source of ignition for these gases, the
ventilation systems need to employ spark-proof technology.
Section 260
Example: Spark-proof fan motors, spark-proof dampers and actuating mechanisms and
spark-proof fan/fan-grill combinations are used in the ventilation system for Tank 400 at
Chapter II -High-Level Waste Requirements
II-144 DOE G 435.1-1
7-09-99
Site Z because of the presence of flammable gases that could burn if an ignition source
were present.
This requirement specifies that the design of ventilation systems include appropriate filtration so
the emissions from the ventilation system do not exceed established limits. This subrequirement is
to be implemented using the graded approach. This requirement is intended to ensure that high-
level waste management facilities have adequate filtration, not to dictate that each facility must
have a particular type of air filtration. Therefore, the safety analysis or assessment for each
facility should provide the basis for determining the level of filtration required.
Example: A new facility is to be built at Site Z for pretreatment of liquid high-level waste
prior to transferring the waste to an existing vitrification facility. The pretreatment
process equipment will be housed in a new building that protects it from the elements and
provides confinement for any radioactive liquid or air particulates that may leak from the
process equipment. While the portions of the building occupied by workers will be
shielded from the process equipment, ventilation will also be required to mitigate any
release of airborne radioactive material. The design of the facility must provide for
ventilation and appropriate filtration of the exhaust from the system.
Compliance with the ventilation requirements can be demonstrated by:
C incorporating necessary ventilation systems (as indicated by safety analyses or
assessments) in the design of high-level waste management equipment and facilities,
and
C providing filtration capability for each ventilation system, as appropriate, to meet
regulatory requirements for emissions of radioactive materials under normal and off-
normal conditions.
Supplemental References:
1. DOE. Occupational Radiation Protection, 10 CFR Part 835, U.S. Department of Energy,
Washington, D.C.
2. EPA. National Standards for Hazardous Air Pollutants, 40 CFR Part 61, U.S.
Environmental Protection Agency, Washington, D.C.
3. DOE, 1990. Radiation Protection of the Public and the Environment, DOE 5400.5, U.S.
Department of Energy, Washington, D.C., February 8, 1990.
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-145
7-09-99
4. DOE, 1997. Fire Protection Design Criteria, DOE-STD-1066-97, U.S. Department of
Energy, Washington, D.C., March 1997.
II. P.(2) Facility Design. The following facility design requirements, at a
minimum, apply:
(d) Ventilation.
2. When conditions exist for generating gases in flammable
and explosive concentrations, ventilation systems or
other measures shall be provided to keep the gases in a
non-flammable and non-explosive condition. Where
concentrations of explosive or flammable gases are
expected to approach the lower flammability limit,
measures shall be taken to prevent deflagration or
detonation.
Objective:
The objective of this requirement is to keep concentrations of flammable and explosive gases
below the lower flammability limits. However, in those instances where the concentrations of
such gases are expected to approach or exceed the lower flammability limit, the objective is to
prevent detonation or deflagration by an alternate means. These means could include
oxygen/oxidant control or employing designs which prevent ignition (i.e., spark-proof
technologies).
Section 261
Discussion:
Ventilation systems that are required for equipment and facilities that generate and accumulate
quantities of flammable and/or explosive gases in concentrations that would pose a risk of fire
and/or explosion need to be capable of moving a sufficient volume of gases to limit concentrations
of flammable and/or explosive gas to safe levels at all times.
Example: Tank 400 at Site Z generates flammable organic gases. The tank was
constructed and filled with high-level waste in the 1980s. This tank must be equipped
with a ventilation system, and the volume of air circulated through the headspace must
be sufficient to maintain concentrations below the lower flammability limit for the
organics present. The ventilation system must include filtration for removing radioactive
particulates that may be in the ventilation exhaust so release limits are not exceeded.
Chapter II -High-Level Waste Requirements
II-146 DOE G 435.1-1
7-09-99
Attention to fire protection for filtration on these ventilation systems is important because of the
potential presence of flammable and explosive gases that led to the requirement for ventilation.
Guidance for fire protection of filtration systems in ventilation plenums for nuclear facilities is
provided in Fire Protection Design Criteria, DOE-STD-1066-97. Typical requirements address
materials of construction, location of filters, fire ratings of protective walls, and internal detectors
for fire and high heat.
The hazard analysis supporting revision of the DOE requirements for management of high-level
waste identified the potential for generation, accumulation, and ignition of flammable and
explosive gases in high-level waste storage tank headspace as one of the highest risk scenarios.
The analysis indicated that such scenarios could result in uncontrolled releases of radioactive
material to the environment and exposure of workers and the public to radiation from the releases.
When conditions exist for generating gases in flammable and explosive conditions, designs of
high-level waste facilities shall include active ventilation systems with the capability to remove
sufficient quantities of gases to preclude the accumulation of flammable and explosive gases in
concentrations that pose a safety hazard. However, it may not be practical to keep concentrations
below the lower flammability or explosivity limits 100% of the time with ventilation systems.
There may be infrequent period where “puff” releases of gases will result in concentrations that
approach or exceed the lower flammability or explosivity limits for a brief interval of time. In
addition, some processes may routinely result in relatively large releases of such gases. In such
cases, facility designs should include alternate features to preclude deflagration or detonation.
This could be accomplished through the use of spark-proof fan motors, actuating mechanisms,
and fan/grill combinations. Other features, such as the insertion of a sufficient flow of an inert
gases into the headspace, may also provide a practical means to dilute the concentrations of these
gases or the available oxygen/oxidants, and to thereby preclude deflagration and detonation.
Section 262
Example: Tank 400 at Site Z generates flammable organic gases. The tank was
constructed and filled with high-level waste in the 1980s. This tank has been equipped
with a ventilation system, circulated with the capability to circulate through the
headspace a volume of air sufficient to maintain concentrations below the lower
flammability limit for the organics present for 98% of the time. Since the concentrations
of flammable gases are above the lower flammability limit for the remaining 2% of the
time, the ventilation system design also includes spark proof technology. The ventilation
system includes filtration for removing radioactive particulates that may be in the
ventilation exhaust so release limits are not exceeded.
Example: An existing tank at site X is generating flammable gases following the receipt
of waste from another tank. The tank design does not include an active ventilation
system. Without mitigative actions, concentrations of flammable gases will increase to
levels approaching the lower flammability limit. Calculations have demonstrated the
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-147
7-09-99
feasibility of introducing nitrogen into the tank head space in sufficient volume to
displace the oxygen and maintain the concentrations well below the lower flammability
limit. This approach has been selected as the preferred option in view of the cost for
installing an active ventilation system to provide the same level of safety.
Compliance with the ventilation requirements can be demonstrated by:
C identifying new and existing equipment and facilities that require ventilation systems, or
other features to preclude or mitigate the hazards posed by the accumulation of flammable
and explosive gases in concentrations above the lower flammability limit or the lower
explosivity limits of such gases,
C incorporating ventilation systems, or other features, (as indicated by the safety analyses or
assessments) in the design of such high-level waste management equipment and facilities,
and,
C providing filtration capability for each high-level waste facility ventilation system as
appropriate, to meet regulatory requirements for emissions of radioactive materials under
normal and off-normal conditions.
Supplemental References:
1. DOE. Occupational Radiation Protection, 10 CFR Part 835, U.S. Department of Energy,
Washington, DC.
2. EPA. National Standards for Hazardous Air Pollutants, 40 CFR Part 61, U.S.
Environmental Protection Agency, Washington, D.C.
II. P.(2) Facility Design. The following facility design requirements, at a
minimum, apply:
(e) Consideration of Decontamination and Decommissioning.
Areas in new and modifications to existing high-level waste
management facilities that are subject to contamination with
radioactive or other hazardous materials shall be designed to
facilitate decontamination. For such facilities a proposed
decommissioning method or a conversion method leading to
reuse shall be described.
Chapter II -High-Level Waste Requirements
II-148 DOE G 435.1-1
7-09-99
Objective:
The objective of this requirement is to ensure the incorporation of the concept of life-cycle waste
management into the design and construction of radioactive waste management facilities to
minimize the amount of radioactive waste that must be managed in the future, and to reduce the
number of facilities that must be dismantled rather than used for another purpose.
Discussion:
Section 263
During the development of DOE O 435.1 and DOE M 435.1-1, the concept of life-cycle
management of waste was identified as a key theme that would promote safety and provide a
long-term benefit in reducing hazards associated with radioactive waste management. This
requirement was developed to extend the life-cycle management of waste concept to the design of
facilities used for the management of radioactive waste. The goals of applying this concept at the
design stage are to minimize the future generation of waste and to promote the planning for
subsequent beneficial use or decommissioning of a facility at the end of its original mission.
Decontamination and decommissioning activities are becoming a significant part of the life-cycle
costs for high-level waste facilities. This requirement also addresses this situation by promoting
proactive consideration of design features that facilitate decontamination and dismantlement
activities that will lead to a beneficial use or decommissioning.
New high-level waste facilities are defined as those whose design basis is not approved. (The
term design basis is defined in the definitions attachment to the Manual). Thus, if a high-level
waste facility’s design basis is defined, the requirements of this section are applicable. Similarly, if
a significant modification to an existing facility is to be made, this requirement applies.
Application of these requirements to existing facilities should be considered and applied on a case
by-case basis. To support this decision, an analysis should be conducted comparing the expected
benefits of the application of these requirements to the costs of implementing such measures.
These costs should include programmatic impacts current cost and schedule impacts, as well as
potential impacts such as additional worker exposure due to radiation and chemical hazards, and
future costs.
Design to Facilitate Decontamination. Decontamination is defined in Attachment 1 to DOE O
430.1A, Life-Cycle Asset Management, as “the removal or reduction of residual radioactive and
hazardous materials by mechanical, chemical, or other techniques to achieve a stated objective or
end condition.” In conjunction with DOE O 430.1A, DOE M 435.1-1 requires that high-level
waste facilities incorporate measures to reduce areas of contamination, or to simplify
decontamination of areas that may become contaminated with radioactive or hazardous materials
to facilitate either decommissioning or reuse of the facility. Following are design features that
should be considered:
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-149
7-09-99
• Service piping, conduits, and ductwork should be kept to a minimum in areas that could
be potentially contaminated, and their design, if included in such areas, should be arranged
to facilitate decontamination.
• Cracks, crevices, and joints should be filled and finished smooth to prevent accumulation
of contaminated material.
• Walls, ceilings and floors in areas vulnerable to contamination should be finished with
washable or strippable coverings.
• Metal liners, e.g., stainless steel cell lining, should be used in areas that have the potential
to become highly contaminated with high-level waste materials.
• Contaminated or potentially contaminated piping systems should have provisions for
flushing and/or cleaning.
• Accessible, removable covers for inspection and cleanouts should be provided.
Section 264
• Construction materials that reduce the amount of radioactive materials requiring disposal
and that are easily decontaminated should be selected.
Design to Support Decommissioning. Decommissioning, also defined in DOE O 430.1A, is
“actions taken at the end of the life of a facility to retire it from service with adequate regard for
the health and safety of the public and workers and protection of the environment.” Design
features that should be considered to support decommissioning or a reuse of the facility include:
C Use of modular radiation shielding, in lieu of or in addition to, monolithic shielding walls.
C Use of modular, separable confinements to preclude contamination of fixed portions of the
structure.
C Designs that facilitate cut-up, dismantlement, removal, and packaging of contaminated
equipment, such as glove boxes, air filtration equipment, large tanks and vessels, and
ductwork, from the facility.
C Use of localized liquid transfer systems that avoid long runs of buried, contaminated
piping. Special provisions should be included in the design to ensure the integrity of joints
in buried pipelines.
C Piping systems that carry contaminated or potentially contaminated liquid should be free
draining by gravity.
Chapter II -High-Level Waste Requirements
II-150 DOE G 435.1-1
7-09-99
C Location of exhaust filtration components of ventilation systems should be at or near
individual enclosures to minimize long runs of internally contaminated ductwork.
C Equipment, including effluent decontamination equipment, should preclude, to the extent
practical, the accumulation of radioactive or other hazardous materials in relatively
inaccessible areas, including turns in piping and ductwork.
C Provisions for suitable clearances, where practical, to accommodate remote handling and
safety surveillance equipment required for future decontamination and decommissioning.
C Use of lifting devices on large tanks and equipment.
Decommissioning and Reuse Planning. Due to the high life-cycle costs of high-level waste
facilities, the second part of the requirement is intended to promote post-mission planning of high-
level waste facilities by requiring the identification of possible decommissioning methods, or
reuses, of high-level waste facilities, as early as possible. To meet this requirement, high-level
waste facility designs, or significant modification efforts, should include analysis to determine the
best decommissioning methods, using currently available technologies, and factor the results of
this analysis into the facility’s design. Likewise, if a reuse of the facility is envisioned, any features
that can support this reuse mission should be considered in the design effort.
At the time of the preparation of this guidance, the “Decommissioning Implementation Guide,”
Draft G 430.1-4, was in preparation to incorporate deactivation and decommissioning
requirements currently contained in DOE 5820.2A, Chapter V. Refer to this Guide, and DOE O
430.1A, Life-Cycle Asset Management, for further information on deactivation and
decommissioning activities. Also, refer to DOE-STD-1120-98, referenced below, on the
integration of safety and health requirements into facility disposition activities.
Compliance with this requirement can be demonstrated by the existence of design
documentation that indicates decontamination was considered during the design of new high-level
waste facilities or significant modifications to high-level waste facilities. Additionally,
documentation should demonstrate that post-mission planning was considered, as early as possible
in the life of a facility, to assist in the identification of possible decommissioning methods or
facility reuse.
Section 265
Supplemental References:
1. DOE, 1998. Life-Cycle Asset Management, DOE O 430.1A, U.S. Department of Energy,
October 14, 1998.
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-151
7-09-99
2. DOE, 1997. Decommissioning Implementation Guide, Draft G 430.1-4, U.S. Department
of Energy, October 1, 1997.
3. DOE, 1997. Integration of Safety and Health into Facility Disposition Activities, DOE
STD-1120-98, U.S. Department of Energy, Washington, DC, Draft for DOE Complex
Wide Review 9/26/97, September 26, 1997.
II. P.(2) Facility Design. The following facility design requirements, at a
minimum, apply:
(f) Maintenance Exposure Reduction. Remote maintenance
features and other appropriate techniques to maintain as low
as reasonably achievable (ALARA) personnel exposures shall
be incorporated into each high-level waste facility.
Objective:
The objective of this requirement is to incorporate engineered features into the high-level waste
facilities to minimize total personnel radiation exposures at high-level waste facilities in
accordance with ALARA principles.
Discussion:
Those structures, systems, and components for which operation, maintenance, and required
inspections may involve occupational exposure must be designed, fabricated, located, shielded,
controlled, and tested so as to control external and internal radiation exposures to personnel.
Features may be employed individually or in combination to achieve this objective. Some features
include the following:
• preventing the accumulation of radioactive material in those systems requiring access
(e.g., minimizing bends and piping low points);
• decontaminating those systems to which access is required;
• controlling access to areas of potential contamination or high radiation; measuring and
controlling contamination of areas requiring access;
• minimizing the time required to perform work in the vicinity of radioactive
components;
Chapter II -High-Level Waste Requirements
II-152 DOE G 435.1-1
7-09-99
• shielding personnel from radiation exposures; and
• providing remote maintenance features.
Existing DOE Orders address many of the concerns relevant to maintenance exposure reduction.
The policy for DOE 4330.4B, Maintenance Management Program, includes the requirement that
“…DOE property be maintained in a manner which promotes … worker health… while meeting
the programmatic mission.” The guidance for this order includes the development of goals and
objectives such as “…minimize radiological exposure…” consistent with the DOE requirements
for occupational radiation protection.
The principal DOE requirements for occupational radiation protection are found in 10 CFR Part
835, Occupational Radiation Protection, and include requirements for maintaining doses as low
as reasonably achievable (ALARA). Section 835.101 specifically states that DOE activities shall
be conducted in compliance with a radiation protection program that includes formal plans and
measures for applying the ALARA process to occupational exposures. ALARA also includes
consideration of economic as well as technical factors. As noted in DOE M 435.1-1, Section
I.1.E.(13), the requirements of 10 CFR Part 835 apply to radioactive waste management facilities,
operations, and activities which include maintenance activities.
Section 266
Example: In a high-level waste processing facility, a component decontamination cell
and contact-handled maintenance facility are provided. The decontamination cell
incorporates remote decontamination capabilities to reduce contamination levels so that
contact maintenance can be performed in reduced radiation fields. The contact-handled
maintenance facility is located adjacent to the decontamination cell and incorporates
features such as enhanced lighting and temporary shielding to facilitate maintenance.
Example: In a high-level waste vitrification facility, manipulators and remotely operated
work arms are sized to perform certain maintenance functions in addition to limited
operational tasks. Specific maintenance functions such a tool could perform include
change of melter components not accessible by in-cell cranes.
Compliance with this requirement can be demonstrated by having and implementing a
Maintenance Management Program that includes due emphasis on radiation protection. The
radiation protection requirements must not only maintain exposures at or below prescribed limits,
but also must incorporate ALARA principles.
Supplemental References:
1. DOE. Occupational Radiation Protection, 10 CFR Part 835, U.S. Department of Energy,
Washington, D.C.
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-153
7-09-99
2. DOE, 1994. Maintenance Management Program, DOE 4330.4B, U.S. Department of
Energy, Washington, D.C., February 10, 1994.
3. DOE, 1998. Worker Protection Management for DOE Federal and Contractor
Employees, DOE O 440.1A, U.S. Department of Energy, Washington, D.C., March 27,
1998.
4. DOE, 1998. Occupational Exposure Assessment, DOE G 440.1-3, U.S. Department of
Energy, Washington, D.C., March 30, 1998.
II. P.(2) Facility Design. The following facility design requirements, at a
minimum, apply:
(g) Facilities for the Receipt and Retrieval of High-Level Waste.
1. Designs for storage facilities shall incorporate features
to facilitate retrieval capability.
2. High-level waste receipt and retrieval systems shall be
designed to complement the existing storage facilities for
the safe storage and transfer of high-level waste.
Objective:
The objective of this requirement is to ensure that the interfaces for input to and transfer from
high-level waste storage facilities are designed to facilitate subsequent removal of the waste, and
that they are fully compatible with the high-level waste to be stored, including necessary
packaging and transfer operations, and with structural and other limitations of storage facilities.
Discussion:
Facilities for the receipt and retrieval of high-level waste must be designed to allow safe
handling, storage, and retrieval of the wastes. Therefore, before new facilities are constructed
and employed to store high-level waste, strategies for retrieval of that waste need to be identified
and the essential features of those strategies for retrieval of that waste need to be incorporated
into the design of the facilities. Design of existing facilities need to be reviewed to identify
essential additional features that could be engineered into the facility to provide for acceptable
handling and retrieval.
Chapter II -High-Level Waste Requirements
II-154 DOE G 435.1-1
7-09-99
Section 267
Example: At Site Z, a new tank farm is being designed for storage of high-level waste
from reprocessing of deteriorating spent fuel. The reprocessing is intended to remove
isotopes that can be used in power reactors, but the separations process is not highly
efficient, so significant quantities of special nuclear material will remain in the
high-level waste to be vitrified and disposed of with the fission products. Because of the
higher than normal concentrations of special nuclear material, special efforts will be
made to design the tanks so most of the liquid high-level wastes can be removed from
the tanks. Design features include:
• configuration of tank bottoms to slope toward the low point of tanks to promote
removal of most of the waste;
• installation of a residuals pump-out line at the low point of each tank;
• elimination of internal structural members in the tanks that could interfere with
waste removal and clean-out activities for closure; and
• incorporation of adequate risers to accommodate anticipated in-tank activities such
as mining, pumping, and wash-down of the tank walls.
In the interest of identifying the structural needs and other requirements that can be incorporated
in the design of new facilities, t is important to anticipate the types of activities that may be
performed for retrieval of high-level waste. For existing facilities whose structural integrity
limitations would not support the loads for an integral retrieval capability, additional structural
support would be provided to eliminate or minimize imposed loads on the tank structure.
Example: The strategy for retrieval of liquid waste from a storage tank involves the use
of a robotic arm whose weight must be born by the tank structure. The associated loads
need to be included in the structural design requirements for the tank, as well as
provisions for access. The structural integrity program would also use these loads in
assessing the structural integrity of the tank over its life, to assure the tank's integrity
can be maintained during retrieval.
The retrieval of canistered waste for shipment to another storage facility or to a disposal facility
will require transferring the waste into a shipping cask certified by the Nuclear Regulatory
Commission under 10 CFR Part 71. Additional requirements of the Department of
Transportation (49 CFR Part 193, Subpart I) and the DOE Orders, DOE O 460.1A and DOE O
460.2, may also affect the design of the receipt and retrieval features.
Implementation of this requirement must be coordinated with several other related requirements
of this Manual. DOE M 435.1-1, Section II. J. specifies that Waste Acceptance Requirements be
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-155
7-09-99
developed for storage facilities, and the receiving features of storage facilities must be designed
to support any evaluation and acceptance activities necessary to ensure compliance with the
Waste Acceptance Requirements. Finally, the receipt and retrieval features must be designed to
be compatible with the general requirements for waste management including Worker Protection
(Section I.1.E.(21)), Radiation Protection (Section I.1.E.(13)) including maintaining exposures
as low as reasonably achievable, and Safeguards and Security (Section I.1.E.(16)).
Section 268
Compliance with this requirement for new facilities can be demonstrated by the existence of
design documentation of the receipt and retrieval features of high-level waste storage facilities to
provide for necessary evaluation and acceptance activities, and demonstrating that retrieval
operations can be performed under conditions likely to prevail at the time of removal.
Compliance with this requirement for existing facilities can be demonstrated by evaluating the
receipt and retrieval features of storage facilities and the existence of design documentation for
modifications to systems as required to allow retrieval operations to be safely and effectively
performed under conditions likely to prevail at the time of removal of the waste
Supplemental References:
1. NRC. Packaging and Transportation of Radioactive Material, 10 CFR Part 71, U.S.
Nuclear Regulatory Commission, Washington, D.C.
2. USDOT. Shippers-General Requirements for Shipments and Packaging-Radioactive
Materials, 49 CFR Part 173, Subpart I, U.S. Department of Transportation, Washington,
D.C.
3. DOE, 1996. Packaging and Transportation Safety, DOE O 460.1A, U.S. Department of
Energy, Washington, D.C., October 2, 1996.
4. DOE, 1995. Departmental Materials Transportation and Packaging Management,
DOE O 460.2, U.S. Department of Energy, Washington, D.C., September 7, 1995.
II. P.(2) Facility Design. The following facility design requirements, at a
minimum, apply:
(h) Structural Integrity. Designs for new tanks shall contribute to
the confinement requirement at Section II.P.(2)(b) of this
Manual by:
Chapter II -High-Level Waste Requirements
II-156 DOE G 435.1-1
7-09-99
1. Incorporating features to avoid critical degradation
modes at the proposed site where practicable, or
minimize degradation rates for the critical modes; and
2. Incorporating features to facilitate execution of the
Structural Integrity Program required by Section
II.Q.(2) of this Manual.
Objective:
The objective of this requirement is to incorporate engineering features into the design of new
tanks that will allow for longer service life and to facilitate implementing the Structural Integrity
requirement at Section II.Q.(2) after the new tanks are placed in service.
Discussion:
For any new tanks that may be constructed to store high-level waste, the service life is to be
specified. A primary determinant of service life is the structural integrity (leak-tightness and
structural stiffness) of the tank. Confidence that the design service life of new tanks will be
realized can be attained by selection of materials and design features that will avoid critical
degradation modes or minimize their degradation rates. The critical modes and rates of interest
are those that result from the chemistry of the waste to be stored in the tank, the chemistry of its
in-situ environment, and loads that are anticipated to be imposed during its lifetime.
BNL-UC-406, Guidelines for Development of Structural Integrity Programs for DOE High-
Level Waste Storage Tanks identifies guidelines for establishing a structural integrity program for
high-level waste storage tanks. It includes both design and operational features. For tanks
constructed without access for inspection, the uncertainty associated with assessment of
structural integrity is greater because material degradation and remaining thickness must be
inferred from indirect data such as derived corrosion rates. However, new tanks can be designed
to provide access for robotic instruments to travel between the primary and secondary containers
to directly assess the degradation experienced and the material thickness remaining. Access to
conduct other tests (e.g. coupon tests) can also be provided in new tanks to obtain other critical
data so as to minimize personnel exposures.
Section 269
Example: Based on information provided through the structural integrity program at
DOE M 435.1-1, Section II.Q.(2), the remaining service life of five existing tanks at Site
XX cannot meet operational requirements. Therefore, five new tanks are to be designed
and constructed to store high-level waste. The planned service life for the new tanks,
with a range of uncertainty, has been established as a design requirement. Based on
characterization of the existing waste to be transferred to the new tanks, and
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-157
7-09-99
characterization of the site geology, the corrosion modes and rates have been
established for alternative materials, Site XX has developed a strategy for retrieval of
the waste from the tanks using a robotic arm. Loads that will be experienced by the tank
structure from normal soil loads, loads from anticipated ground motion, loads from
retrieval and decommissioning activities, and loads for operational and maintenance
activities have been estimated and established as design requirements. The capability
for access by robotic devices to assess structural degradation and remaining thickness
has also been established as a design requirement as has the capability to monitor
critical structural loads with instrumentation during the service life of the tanks has also
been established as a design requirement.
The actions necessary to comply with this requirement are complementary to those identified in
the guidance for the Structural Integrity requirement at Section II.Q.(2)., except that the actions
are undertaken prior to selection of the materials and the design of the structure. These actions
include:
1. Establishing the design load requirement based on loads anticipated during the service
life of the tank. These loads include: normal soil load; loads from anticipated ground
motion; thermal loads; loads from retrieval and decommissioning activities; and, loads
related to maintenance and operational activities.
2. Establishing design requirements for acceptable corrosion modes and rates based on
the chemistry of the waste that will be stored in the tanks and the in-situ chemistry of
the site and the supporting structure.
3. Establishing design requirements to implement the structural integrity program at
paragraph II.Q.(2), including access for instrumentation to assess degradation and
remaining material thickness
4. Establishing other design requirements which would significantly increase confidence
that the design service life will be achieved (e.g., access for coupon tests; cathodic
protection).
Supplemental References:
1. BNL, 1997. Guidelines for Development of Structural Integrity Programs for DOE
High-Level Waste Storage Tanks, BNL-UC-406, Brookhaven National Laboratory,
Upton, NY, January 1997.
Chapter II -High-Level Waste Requirements
II-158 DOE G 435.1-1
7-09-99
II. P.(2) Facility Design. The following facility design requirements, at a
minimum, apply:
Objective:
(i) Instrumentation and Control Systems. Engineering controls
shall be incorporated in the design and engineering of high-
level waste treatment, storage, pretreatment, and treatment
facilities to provide volume inventory data and to prevent
spills, leaks and overflows from tanks or confinement systems.
Section 270
The objective of this requirement is to include engineering controls in the design of high-level
waste pretreatment, treatment and storage facilities to minimize the likelihood of loss of
confinement during normal and abnormal operations. Additionally, the requirement is to ensure
the incorporation of engineering controls that alert operations personnel of an impending and
actual loss of confinement.
Discussion:
During the development of the DOE O 435.1 and DOE M 435.1-1, a hazards analysis and a
requirements analysis concluded that the loss of confinement due to a spill, leak or overflow at a
high-level waste treatment or storage facility could pose a significant risk to both workers and
the environment. That analysis resulted in the inclusion of this requirement to be applied to all
high-level waste treatment and storage facilities. In the context of this requirement, pretreatment
is a subset of treatment and affected facilities include process vessels, tanks and bins that serve as
a level of confinement for high-level waste in the liquid, slurry, or solid (e.g., calcine) state.
Storage facilities include underground high-level liquid waste storage tanks as well as storage
bins for calcined material.
This requirement is invoked to support prompt detection and prevention of conditions which
could lead to release of radioactive material from high-level waste pretreatment, treatment, and
storage facilities. This is also closely related to the design requirement for monitoring systems.
However, this requirement addresses implementation of controls that prevent the loss of
confinement whereas the monitoring design requirement is intended to address detection of loss
of containment.
For clarification, engineering controls in this requirement are considered to be those systems or
design characteristics that are provided to prevent or mitigate the loss of confinement from
high-level waste storage facilities and which provide volume inventory data. Examples of
engineering controls include flowmeters, level-sensing devices, liquid and solid level alarms, anti-
siphon devices overflow prevention features, and any other instrumentation and controls that
maintain sufficient freeboard within the storage unit.
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-159
7-09-99
Loss of confinement at a high-level waste pretreatment, treatment or storage facility can result
from overflows, spills, leaks and siphoning of waste from the storage unit. Incorporation of
design measures at these facilities to prevent such loss of confinement is necessary, but their
presence alone is not considered sufficient to meet this requirement. Engineering controls must
also be subject to periodic inspection and maintenance to ensure proper operation. In spite of
rigid maintenance and surveillance, such equipment can fail over its expected service life.
Therefore, to fully meet this requirement, mitigative measures to reduce the loss of confinement
are necessary. These mitigative measures should be implemented in conjunction with the
required measures of confinement, as specified by DOE M 435.1-1, Section II.P.(2)(b),
Confinement, of this guidance.
Example 1: At Site X High-Level Waste Tank Farm, an engineering control on a waste
tank includes a waste feed line shut-off valve, which is activated by a tank level-sensing
device, to prevent overflow of waste from the tank. For defense-in-depth, a double-
contained overflow line is attached to the tank to channel any overfill to a spare waste
tank at the tank farm.
Section 271
Example 2: A facility is being designed to separate high-level liquid from precipitated
solids as the mixture is withdrawn from a storage tank. The separations process is a
continuous operation, with the liquid being transferred to a storage tank. To avoid loss
of containment, an interlock is included in the design which prevents feed from entering
the separations process and liquid from being discharged unless the supernatant
receiving tank is below ninety-five percent full.
The graded approach should be used for determining the appropriate level of engineering
controls to incorporate into the design of high-level waste management facilities. As indicated in
the preceding examples, sensing devices, alarms, and spill or overflow prevention features are
most appropriate in facilities storing liquids or with continuous, automatic processes. Other
instances involving bulk or solid high-level waste may need to invoke these controls, as well as a
simple shutoff switch which could prevent overfilling.
It is recognized that incorporation of engineering controls to meet this requirement may be
directed by the facility-specific safety analysis for the storage unit or group of storage units.
Such safety analysis may dictate that some of the engineering controls be designed as safety-class
or safety-significant systems, structures or components (SSC) to ensure they survive the design-
basis accidents. Use of the safety analysis process prescribed by DOE 5480.23, “Nuclear Safety
Analysis Reports,” to identify the necessary engineering controls to meet this requirement for
both new, and upgrades to existing, high-level waste storage facilities is encouraged.
Compliance with this requirement is demonstrated by the incorporation of engineering controls
that provide timely information to facility operations personnel regarding the volumes of high-
Chapter II -High-Level Waste Requirements
II-160 DOE G 435.1-1
7-09-99
level waste being stored, automatic shut-off, anti-siphoning devices, and automatic sensing
devices, and mitigative measures to minimize the spread of high-level waste in the event of loss
of confinement.
Supplemental References:
1. DOE, 1995. Implementation Guide for Nonreactor Nuclear Safety Design Criteria and
Explosives Safety Criteria, DOE O 420.1, Revision G (Draft), Facility Safety, U.S.
Department of Energy, Washington, D.C., September 1995.
II. P.(2) Facility Design. The following facility design requirements, at a
minimum, apply:
(j) Volume Monitoring Systems. Monitoring and/or leak
detection capabilities shall be incorporated in the design and
engineering of high-level waste storage, pretreatment, and
treatment facilities to provide rapid detection of failed
confinement and/or other abnormal conditions.
Objective:
The objective of this requirement is to mandate design and installation of equipment in high-level
waste management facilities that is capable of identifying failures in containing high-level waste
and other conditions that could result in exposure of the public, workers, or releases to the
environment.
Discussion:
This requirement is invoked to address a group of high hazards was identified by the hazards
analysis performed in support of DOE O 435.1 and DOE M 435.1-1 associated with the failure
to promptly detect a release of high-level waste that could impact personnel, the public, or the
environment. This particular requirement addresses the design of monitoring systems so that
unexpected changes in quantity indications can be promptly checked to determine if they are a
reflection of failure in high-level waste confinement facilities/systems and so that high-level waste
transfers can be monitored to avoid overfilling. Monitoring for detecting releases that may be
too small to be detected quickly, via volume changes, is addressed in DOE M 435.1-1 Section
II.T, Monitoring.
Section 272
The hazards analysis performed to guide development of DOE O 435.1 and DOE M 435.1-1
revealed that releases can result from failure of confinement or from failure to stop transfer of
high-level waste when the receiving vessel (e.g., tank or bin) is full. The requirement discussed
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-161
7-09-99
here is generally directed toward prompt detection of acute releases (releases that can be readily
detectable) that become apparent over a time frame of hours or days. In contrast, the
requirements for environmental monitoring (see Section II.T) for compliance with release limits
is directed toward detection of releases that generally evolve slowly and may be detected by low
threshold environmental monitoring devices weeks, months, or longer after the release begins.
Example: A large diameter storage tank for liquid high-level waste includes a
mechanical level indicator that is read and recorded daily. The level indicator
remained stable for six months following the last waste addition to the tank. The level
indicator readings then began to show a downward trend that totaled two inches over a
two week period. There could be causes for the level change other than leakage (see
following additional discussion), but the level indicator change would alert operators of
a potential problem that requires further investigation.
Experience in the management of high-level waste has led to identification of various events for
the release of high-level waste. Some of those factors include the generally corrosive (acidic or
basic) chemical composition of liquid high-level waste, the use of vessel materials such as mild
steel that are not highly resistant to corrosion and other chemical attack, the abrasive physical
form of calcined high-level waste, and the absence of secondary confinement. The consequences
of release of high-level waste, coupled with the factors threatening confinement, led to
development of the requirement for monitoring. Other requirements of this chapter address
Confinement (Section II.P.(2)(b)), Structural Integrity of storage tanks (Section II.P.(2)(h)),
Structural Integrity Program (Section II.Q.(2)), and Instrumentation and Control Systems for
high-level waste volume inventory (Section II.P.(2)(i)). The confinement requirement focuses on
design of waste systems and components to ensure confinement and requires application of a
number of specific design considerations. The Structural Integrity requirement focuses on
assessment of the condition of confinement barriers and processes that promote anticipation of
potential confinement weakness or failure based on known deterioration processes. The
Instrumentation and Control requirement focuses on prevention of releases in contrast to this
requirement, which emphasizes detection of releases.
Storage facility surface level is a relatively straightforward parameter to monitor. In general, the
surface level in a vessel is an appropriate indicator of high-level waste volume. However,
operations and mechanisms that could change the volume in a vessel must be considered to
factor out explainable level changes.
Example 1: An unexpected chemical reaction generates gas that is trapped within the
waste matrix or under a semipermeable layer of waste that retards percolation of the
gas to the surface of the waste. This mechanism maintained the apparent surface level
of high-level waste in a vessel even as liquid was leaking out.
Section 273
Chapter II -High-Level Waste Requirements
II-162 DOE G 435.1-1
7-09-99
Example 2: Operating personnel at a high-level waste storage facility calculate the
evaporation loss expected from a tank based on an assumed radionuclide inventory.
The actual radionuclide inventory is much smaller than that assumed, so the actual heat
generation rate is much smaller than that assumed. Overestimation of the waste volume
change due to evaporation resulted in failure to detect leakage that was incorrectly
assumed to be evaporative loss.
Gas generation and evaporation, as well as intentional additions to and removals from the vessels
must be accurately accounted for if the waste level (or volume) is to be used to monitor for
leakage. The monitoring capability should be coupled with instrumentation and control systems,
such as automatic shutoffs and bypasses with alarms, that will alert operators that action is
needed to prevent or mitigate a release.
For transfer systems, approaches such as continuous flow measurements and comparisons of
total volume input to total volume output can be used to monitor the integrity of the transfer
system. The containment integrity of waste transfer systems can also be monitored for radiation
levels in excess of those expected from residual waste in the transfer system.
Example: A pneumatic transfer system for calcined high-level waste is enclosed in a
concrete tunnel that provides significant shielding for an adjacent work area. Routine
surveys along the outside of the tunnel revealed higher than normal residual activity
when calcine was not being transferred. The surveys also showed progressively higher
activity after each transfer of calcine. Examination inside the tunnel with a remotely
operated camera revealed an accumulation of calcine fines below an elbow where
abrasion from the calcine had apparently eroded a hole in the transfer line.
A highly reliable means of monitoring for releases is the use of secondary confinement, which is
then checked for the presence of high-level waste. This monitoring approach should be applied
to essentially any high-level waste management systems including pretreatment, treatment,
storage, and transfer (see Section II.P.(2)(b)). It also offers the benefit of providing defense-in
depth to avoid the release of high-level waste.
Example: A high-level waste transfer line from a storage tank farm to a vitrification
plant includes a secondary confinement barrier. The transfer line is constructed with
sufficient pitch to cause any leakage into the outer line to flow back to the storage tank.
A conductivity cell, with associated monitor, is included in the outer line to alert
operators of a primary to secondary barrier leak, as a mitigative measure.
What constitutes rapid detection of failed confinement or provides indications of abnormal
conditions needs to be established for each facility, operation, or activity. Monitoring system
design requirements and engineering controls to address catastrophic failures will be established
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-163
7-09-99
through the conduct of safety analyses. The failures and conditions being addressed by this
requirement are not catastrophic, but could result in releases of radioactivity, or doses to
workers or the public, in excess of established limits, if the leak was allowed to continue over a
period of hours or days or individuals were not removed. Similarly if the failure results in
releases of radioactivity to an air or liquid effluent stream, detection needs to occur rapidly
enough to prevent environmental releases from exceeding annual limits.
Section 274
A graded approach should be applied to design and operational implementation of this
requirement for monitoring to detect acute releases promptly. For example, it may not be
necessary to provide continuous monitoring of waste levels in high-level waste storage tanks that
have had the pumpable liquids removed, to the extent possible, or in bins of stored calcined high-
level waste the waste is not especially mobile. Occasional level verification with a non-
permanent detection system for such cases is considered suitable and meets the intent of this
requirement. On the other hand, highly mobile liquid waste in a single-walled, mild steel tank
would probably require continuous monitoring coupled with alarms and transfer equipment.
Compliance with this requirement is demonstrated by the existence of design documents for
high-level waste systems that include the capability to monitor waste volumes and detect volume
changes in a time frame that will allow implementation of corrective measures to limit public and
worker doses and releases to allowable levels.
Supplemental References:
1. EPA. Containment and Detection of Releases, 40 CFR 264.193 for Hazardous Waste
Tank Systems, U.S. Environmental Protection Agency, Washington, D.C.
2. EPA. General Operating Requirements, 40 CFR 264.194 for Hazardous Waste Tank
Systems, U.S. Environmental Protection Agency, Washington, D.C.
Chapter II -High-Level Waste Requirements
II-164 DOE G 435.1-1
7-09-99
II. Q. Storage.
The following requirements are in addition to those in Chapter I of this Manual
and also apply to facilities intended for management of high-level waste awaiting
pretreatment, treatment or disposal, unless stated otherwise.
(1) Operation of Confinement Systems.
(a) Confinement systems shall be operated and maintained so as to
preserve the design basis.
(b) Secondary confinement systems, where provided, shall be operated to
prevent any migration of wastes or accumulated liquid out of the
waste confinement systems.
Objective:
The objective of this requirement is to ensure that containment systems, both primary and
secondary, are: (a) maintained to preserve the design capabilities of the systems to prevent the
release of hazardous materials to the environment; and (b) operated so as to maximize the
effectiveness of the design to contain wastes and accumulated liquids.
Discussion:
The establishment of appropriate operational procedures and diligence in executing the
procedures are essential to maximize the effectiveness of the design capabilities of the waste
containment system. The procedures need to be based on the operational assumptions that
formed the basis for the system design.
Example: At Site Orange, the secondary containment system does not have
instrumentation to detect liquids in the secondary system. Instead, provisions were
included in the design to manually check for liquids. The design of the primary
container does not assume that liquids will be present in the secondary system.
Additionally, the presence of liquids in the secondary containment system will induce an
unanticipated increase in the corrosion rate of the primary system that will reduce its
service life. Operational procedures require daily checks for accumulated liquids in the
secondary containment, and systems are provided and maintained to remove
accumulated liquids promptly.
The stress of daily operational activities can impose degradation modes and increase the rate of
degradation of confinement systems beyond those included in the design basis. It is important to
Section 275
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-165
7-09-99
identify the operational and maintenance assumptions that formed the basis for the system design.
These factors normally include assumptions regarding the frequency and severity of loads
imposed by naturally-induced and human-induced events. Naturally-induced events include
pressure gradients (including static head and external hydrological forces), the physical contact
with the waste, and climatic events. Human-induced events include stresses from nearby
vehicular traffic, and operational events including sampling, installation and removal of pumps,
and other operational activities that impose loads. If the stresses due to these factors exceed the
stresses for which the system was designed, the service life can be substantially reduced which
could result in unanticipated loss of confinement. As discussed in the guidance II.Q.(2),
Structural Integrity Program, many of the single containment systems are already beyond the
service life for which they were designed, and efforts are required to extend the service life of
most tanks even further into the future. For this reason, as well as the consequences of
containment failure, new high-level waste is not be placed into single confinement systems. New
high-level waste imposes a greater heat and corrosive load, which is inimical to efforts to extend
the service life of the oldest tanks.
Example: At Site Red, a mis-routing during transfer of waste has created a safety issue
regarding criticality of the high-level waste in tank XYZ by the introduction of
additional fissile material. A decision has been made to install pumps to re-suspend the
fissile material. Because of the low viscosity of the waste, the pumps required for this
unanticipated operation are much heavier than those assumed in the design of the tanks.
In addition, the crane to install the pumps is much larger and heavier. The integrated
operations and maintenance procedures at the site identify the design basis loads for the
tanks. The maintenance organization has determined that the additional loads of the
pump and crane are greater than the design basis loads for the tank confinement
systems in the tank farm. Therefore, additional structures will be required to support
the loads.
Other operational and maintenance requirements of DOE M 435.1-1, e.g., Section II.Q.(2),
Structural Integrity Program, Section II.J, Waste Acceptance, Section II.L, Waste
Characterization; and Section II.M, Waste Certification, also directly relate to the successful
operation of confinement systems to preclude migration of waste.
Compliance with this requirement is demonstrated by developing, documenting and
implementing a program that integrates the operational and maintenance requirements of DOE M
435.1-1, (the above citations) with the design basis assumptions, implementing operational
procedures that maximize the effectiveness of the system design, and by continually assessing and
modifying the stresses of daily operational and maintenance activities to be as low as practical,
and no greater than the stresses assumed in the design for the containment systems.
Supplemental References: None.
Chapter II -High-Level Waste Requirements
II-166 DOE G 435.1-1
7-09-99
II. Q.(2) Structural Integrity Program.
(a) Leak-Tight Tanks In-Service. A structural integrity program
shall be developed for each high-level waste storage tank site
to verify the structural integrity and service life of each tank
to meet operational requirements for storage capacity. The
program shall be capable of:
Section 276
1. Verifying the current leak-tightness and structural
strength of each tank in service;
2. Identifying corrosion, fatigue and other critical
degradation modes;
3. Adjusting the chemistry of tank waste, calibrating
cathodic protection systems, wherever employed, and
implementing other necessary corrosion protective
measures;
4. Providing credible projections as to when structural
integrity of each tank can no longer be assured; and
5. Identifying the additional controls necessary to maintain
an acceptable operating envelope.
(b) In-Service Tanks that Have Leaked or Are Suspect. For each
high-level waste storage tank in-service that is known to have
leaked, or is suspect, a modified structural integrity program
shall be developed and implemented to identify the safe
operational envelope. The modified program shall be capable
of:
1. Verifying the structural strength of each tank in-service
which has leaked or is suspect;
2. Identifying corrosion, fatigue and other critical
degradation modes;
3. Adjusting the chemistry of tank waste, calibrating
cathodic protection systems, wherever employed, and
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-167
7-09-99
implementing other necessary corrosion protection
measures;
4. Determining which of the tanks that have leaked or are
suspect may remain in service by identifying an
acceptable safe operating envelope;
5. Providing credible projections as to when the acceptable
safe operational envelope can no longer be assured; and
6. Identifying the additional controls necessary to maintain
the acceptable safe operational envelope.
When physical activities, as part of a structural integrity
program, pose additional vulnerabilities, alternative measures
shall be implemented to provide an acceptable storage
operational envelope.
(c) Other Storage Components. The structural integrity of other
storage components shall be verified to assure leak tightness
and structural strength.
Objective:
The objectives of this requirement are to: (1) identify an acceptable safe operational envelope
(where feasible) for tanks that are known, or suspected, to leak and where it is necessary to keep
such tanks in-service for the interim; (2) provide an estimate of the remaining service life for each
tank; (3) identify the frequency for monitoring in-tank waste chemistry; (4) extend the service
life (leak-tightness and structural strength) of individual tanks to meet the operational
requirements for storage capacity where such extensions are feasible; and (5) verify the structural
integrity of transfer piping and other storage components prior to transfer of high-level waste.
Discussion:
In addition to the facility and general design requirements contained in DOE M 435.1-1, Section
I.1.E., Requirements of Other Regulations and DOE Directives, high-level waste storage tanks,
transfer piping and other storage components, shall be subject to a structural integrity program.
During the development of DOE O 435.1 and DOE M 435.1-1, a hazards analysis and a
requirements analysis concluded that there is a need for this requirement to preclude an
uncontrolled release of high-level waste from storage systems due to loss of structural integrity.
Although the analysis that prompted this requirement involved high-level waste “storage
Chapter II -High-Level Waste Requirements
II-168 DOE G 435.1-1
7-09-99
Section 277
systems” that are likely to contain large quantities of liquid high-level waste for extended periods
of time during which corrosion modes and rates could lead to loss of structural integrity, i.e.,
high-level waste underground storage tanks, high-level waste sites are encouraged to apply these
requirements to all storage systems (e.g, process storage vessels, solid (calcined) high-level
waste storage bins).
Meeting operational requirements for storage. Changes in DOE programs now require that
high-level waste storage tanks remain in-service for a significantly longer time than ordinally
planned. The Department has over two hundred and forty high-level waste storage tanks.
These tanks have already exceeded their design service life, and many more tanks will exceed
their original design service life before waste is removed from the tanks. If the structural
integrity program is to meet its requirement to “verify the structural integrity and service life for
each tank to met operational requirements for storage capacity” [Section II.Q.(2)(a)], the service
life of the tanks must be extended beyond that for which they were designed. In the near term,
predictive models will be required to estimate the remaining service life of specific tanks to
determine whether operational requirements for waste storage can be met. The remaining
service life extends to that point in time beyond which structural integrity (leak tightness and
structural strength) cannot be assured. This estimate will be revised periodically with each
reassessment of structural integrity. The purpose of the estimate is to provide management
sufficient time to pursue alternatives for storage of the waste.
Guidelines for establishing a structural integrity program. BNL-UC-406, Guidelines for
Development of Structural Integrity Programs for DOE High-Level Waste Storage Tanks,
(referred to subsequently as “Guidelines”) provides an acceptable process for establishing a
structural integrity program. This set of Guidelines was finalized in January 1997 to promote the
structural integrity of high-level waste storage tanks and transfer lines at facilities of the
Department. In summary, the document lays out the essential elements of a structural integrity
program. The procedures contained in the Guidelines provide an acceptable methodology to
assess the structural integrity of existing tanks and to estimate the end of service life.
The primary elements of a structural integrity program are described in the Guidelines and
include addressing possible aging degradation mechanisms for both steel and concrete
components of tanks. In addition, the Guidelines identify an evaluation process to screen out
non-significant aging mechanisms and contain the details for developing and maintaining such a
program. Guidance Section II.P.(2)(h), Storage Tank Structural Integrity, incorporates
recommendations from BNL-UC-406 on design information for underground high-level waste
storage tanks. The following is a summary of some of the more salient points contained in BNL
UC-406 for operational aspects of a structural integrity program.
A structural integrity program is to be developed for each high-level waste tank farm site
according to its specific needs. Although these programs are expected to be different from site
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-169
7-09-99
Section 278
to site according to the composition and nature of the wastes, intended use of the tanks, and
specific structural features, there are several basic elements and considerations that are included
in the program to ensure a systematic assessment of the tank's structural integrity. The structural
integrity program is to be developed such that the steps required for verification of structural
integrity can be performed. This requires collection of adequate data and their evaluation. The
worst combination of material properties data and loadings during the service life of the tank
system need to be considered in the structural analysis.
An assessment of the current material properties in the high-level waste tanks allows a
verification of their current structural integrity. However, in order to demonstrate that at the end
of the service life of a tank, structural integrity will be maintained, projection of the component
degradation may be required. Alternatively, if the maximum service life of a tank is to be
estimated, a prediction model needs to be developed as part of the structural integrity program.
In either case, a demonstration of structural integrity for future operation requires periodic
inspection and maintenance programs necessary components in an effective structural integrity
program. Ultimately, if the integrity of a tank cannot be demonstrated, the program needs to
provide adequate warning for management actions, such as retrieval of the waste.
The elements of a structural integrity program need to be defined and implemented in a logical
sequence to achieve the above goals. The basic concern for integrity of high-level waste tanks is
the degradation of structural materials. Therefore the first step of a structural integrity program
is to identify any aging mechanisms that could cause material degradation. The next step is to
quantify the degradation and determine its effect on performance of the two desired functions,
leak-tightness and structural adequacy. Program features of the leak detection system and non
destructive examination will verify the leak tightness. A structural analysis program based on
end-of-life material properties data will verify structural adequacy. If both analyses are
successful, no further action is required. If not, additional steps should be considered such as
preventive maintenance, and management options (e.g., retrieval). More specifically the major
program elements are:
C Identification of Aging Mechanisms: the aging mechanisms that may cause degradation of
the materials are identified considering tank-specific conditions, such as thermal loads,
pH level, material types and chemical attack.
C Quantification of the Degree of Degradation: for each aging mechanism identified as part
of the above process, the potential degradation of structural and material properties are
quantified.
C Evaluation of the Effect of Degradation on Tank Integrity: determine the effect of the
degradation on the intended functions of the tanks, i.e., leak tightness and structural
adequacy
Chapter II -High-Level Waste Requirements
II-170 DOE G 435.1-1
7-09-99
C Verification of Leak Tightness: data from a non-destructive examination are studied to
estimate the potential for leakage, including inspections by robotic instruments in the
annular space between the primary and secondary confinement barriers, where
practicable.
Section 279
C Verification of Structural Adequacy: since a reduction of material properties or
significant geometric change can affect the ability of a tank structure to withstand
imposed loads, all loads (hydrostatic, soil pressure, thermal, earthquake and other
accidental loads including appropriate combinations of these) are considered in a
structural analysis. Loads that are generated by the waste contents (e.g., thermal) need
to be routinely monitored. Based on the severity of these loads, a schedule is established
for monitoring (see Section II.T).
C Management Options: in addition to preventive maintenance and repair programs other
options may need to be evaluated, e.g., removal of the supernate or retrieval of the tank’s
entire contents. Such actions will require decisions by the responsible waste management
organization to ensure the decision is consistent with other elements of the program.
A systematic consideration of all the elements delineated in BNL-UC-406 is expected to result in
a successful structural integrity program. The basic elements and considerations of the program
contained in the BNL document is applicable to all high-level waste underground storage tanks.
However, it is recognized that differences in how the data are accumulated, the degradations
modes experienced, the frequency with which the structural integrity program must be repeated,
and whether or not predictions of the end of service life will be required, may differ for certain
tank farms or individual tanks; however, a documented technical basis needs to be available to
support the structural integrity program at each site.
Scope. The scope of this requirement is limited to high-level waste tanks and does not apply to
tank supporting systems that are covered by other requirements within DOE M 435.1-1. For
example, the requirement does not apply to the functional integrity of the high-level waste tank
ventilation system (see requirement at Section II.P.(2)(d). Likewise it does not apply to the
monitoring and leak detection systems/equipment that provide identification of failed
confinement, nor does this requirement apply to monitoring and leak detection
systems/equipment that provide identification of abnormal conditions at high-level waste tanks
and transfer lines (Section II.P.(2)(i)).
Modified structural integrity program for leaking tanks. Although some high-level waste storage
tanks cannot meet the leak-tightness criteria of the structural integrity requirement, i.e., they
have leaked in the past, or are suspected of leaking now, application of a modified structural
integrity program remains important for such tanks that must continue in-service either to store
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-171
7-09-99
high-level waste for the interim, or for contingency use. For tanks that are known to have leaked
in the past, leak now, or are suspected of leaking (single containment or double containment),
the requirement to verify leak tightness and structural strength is to confirm that the tanks do
have sufficient structural strength and that the tanks do, or do not leak. Tanks that are known to
have leaked in the past, and those whose leak-tightness cannot be verified, will be treated as
leaking tanks and are subject to the requirements of the modified structural integrity program.
Where storage requirements, including the requirement for contingency storage, necessitate the
use of leaking tanks for some interim period, the modified structural integrity program for
leaking tanks is required to be capable of determining an acceptable safe operating envelope in
order to continue use of the tank for storage. The acceptable safe operating envelope is that
portion of a structurally adequate tank for which leak-tightness can be verified. An acceptable
operational envelope for continued storage could consider the location of the leak sites and the
viscosity of the waste to be stored.
Section 280
The modified structural integrity program is required to be capable of projecting how long the
acceptable safe operating envelope can be sustained. The Guidelines provide detailed guidance
on how to determine the remaining thickness of the tank wall, identify the degradation modes
and rates and make projections of remaining service life. However, use of tanks that have
leaked, and tanks for which structural integrity cannot be verified, is to be discontinued for
storage, including contingency storage, as soon as capacity in a tank with no known or suspected
leak sites becomes available. Verification of leak-tightness and making credible projections as to
when the acceptable safe operating envelope can no longer be assured (Section II.Q.(2)(b)(5))
for leaking, or suspect leaking, single-shell tanks at some of the sites is not possible due to their
configuration, waste levels, or the risks posed in trying to do so. In such cases, as illustrated in
the examples below, management should identify the options, and, in those cases that waste must
remain for some period of time, add the necessary controls, e.g., periodic pumping to remove as
much of the pumpable liquids as possible, to provide an acceptable storage operational envelope.
Under such conditions the requirements in Section II.Q.(2) are considered met.
The modified structural integrity program is also required to be capable of identifying additional
controls that may be required to maintain an acceptable safe operating envelope. To be effective,
these controls must address the operational and natural threats to safe storage. These threats
include the following:
• Overfilling above the safe operational envelope;
• Permitting waste to be accepted which intensifies the critical corrosion modes;
• Internal Loads
- High temperature and/or temperature cycling
Chapter II -High-Level Waste Requirements
II-172 DOE G 435.1-1
7-09-99
- High pressure and/or pressure cycling
• External loads
- Unequalized soil and hydrologic loads as a result of reducing the volume
of waste in the tank
- Maintenance activities and installation and operation of retrieval
equipment
• Inflow of groundwater through leak sites; and
• High viscosity liquid waste.
Example 1: At Site X, leak sites for two of the high-level waste storage tanks have been
identified at elevations in the top half of each tank. Because of limited retrieval
capability and other storage capacity, waste in only one of the tanks has been
substantially retrieved. This tank has been designated as a contingency storage tank to
accept waste up to an administratively controlled level, well below the elevation of the
leak site. Waste in the other tank has only been partially retrieved to an administratively
controlled level well below the elevation of the leak sites.
Example 2: At Site H, Tank DEF is known to leak, but the number of leak sites, and
their exact locations, cannot be ascertained with a high degree of confidence. Retrieval
capability to remove all of the waste does not exist, nor does capacity exist to store all of
the waste in other tanks. A decision has been made to remove as much of the pumpable
liquid as possible to minimize the consequences of any potential leak. Retrieval
capability and contingency capacity are available to support this option. Periodic
pumping will continue so as to remove any additional liquids that may become available
(interstitial liquids or inflow of groundwater). These actions, together with the very low
viscosity of the remaining waste, will help to minimize any further leakage to the
environment and its consequences. These actions constitute an acceptable safe
operational envelope, with controls, for continued use of the tank for storage where
operational constraints preclude the removal of all of the waste.
Section 281
Corrosion control. BNL-UC-406 also recommends measures to minimize corrosion, including
adjustments to waste chemistry, and verification of corrosion rates following such adjustments.
The following guidance, based on the primary features of the corrosion control program, are
recommended. Refer to the referenced documents for additional details.
1) Ascertain the current in-situ chemical constituents. The chemical constituents of
the waste may vary with depth in the tank as the waste settles out into relatively
homogeneous zones. The levels at which the most critical corrosion mode(s) and
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-173
7-09-99
rate(s) are present are identified, monitored, and controlled. The critical
corrosion zones are established to ensure leak-tightness and tank structural
integrity. Once the critical zone(s) have been established, repeated actions to
identify them should not be required unless the layers in the tank become
disturbed.
A schedule for tank sampling is established that is consistent with the critical
corrosion mode and rate and with the programmatic requirement to maintain tank
integrity, as measured by leak-tightness and structural stability.
Example: At Site Z DOE is currently scheduled to complete treatment
(solidification) of the high-level (tank) waste in the year 2025. This
assumes that no new storage tanks will be built. These programmatic
factors mean that some of the site’s storage tanks must maintain their
structural integrity through the year 2025. These requirements should be
considered in establishing the frequency of tank sampling.
If the projected lifetime of the tanks is very short and the material properties of
the tanks have not degraded, then the sampling schedule can be relaxed.
However, if the operational requirement for the tank to provide safe storage is
relatively long, the corrosion rates are estimated to be high, and the material
properties of the tank have degraded, then an aggressive sampling schedule would
be necessary.
2) Identify the corrosion modes and assess their rates. Based on the current
chemical constituents of the contained high-level waste, expected additional waste
receipts, and the material properties of the tank, the corrosion modes and rates
are assessed to determine the critical mode(s) and rate(s) that threaten tank leak-
tightness and structural stability. Examples of corrosion modes that may be
applicable are general corrosion, pitting, and cracking.
3) Add chemicals to mitigate corrosion. After identifying the critical corrosion
modes for ensuring leak-tightness and structural stability, the chemistry of the
waste are adjusted to mitigate corrosion. Projections for mitigation effectiveness
consider the method by which the chemicals are introduced into the storage tank
system and the time required for the treatment chemicals to reach the critical
zones.
Example: Insertion of liquid corrosion-mitigating chemicals through
tank inlet piping or tank risers and subsequently distributed by
operations of mixing pumps may deliver them directly into the critical
Chapter II -High-Level Waste Requirements
II-174 DOE G 435.1-1
7-09-99
zones immediately. However, dry chemicals applied to the liquid surface
of the wastes stored in the tank, without mixing, may have a long
transport time to reach critical zones, or may not reach the zones without
some agitation. Such an approach would require evaluation.
Section 282
4) Validate the corrosion modes and rates in the tank as a result of the adjusted
chemical constituents of the waste. In step # 3 above, chemicals were added to
the waste to mitigate corrosion rates to a lower target level. In this step, tests are
undertaken to determine if the lower targeted corrosion rate was actually
achieved through the adjustment to waste chemistry. Projections of corrosion
modes and rates based on adjusted tank waste chemistry are validated with tests
involving specimens of the tank material at the critical corrosion zone(s). This
can be accomplished in-situ or in controlled laboratory tests.
Example: Projections of corrosion modes and rates at Site X High-Level
Waste Tank #1001 were validated by subjecting material coupons of the
same material as the tank wall to simulated waste and the added
corrosion-mitigating chemicals. Based on the results of the validation
and the corrosion rates, a frequency for monitoring tank chemistry for
corrosion should be established.
Similarly, active cathodic protection systems, where used, need to be calibrated and the
impressed currents, if applicable, adjusted to minimize corrosion rates as part of the structural
integrity program. The frequency for such calibrations and adjustments is to be established and
justified with a technical basis. In addition, DOE Handbooks, such as DOE-STD-HDBK-1015
and -1017, provide information on both the corrosion theory and corrosion material sciences.
The structural integrity of in-service transfer piping needs to be assessed before each transfer of
high-level waste. This assessment can be accomplished by pressure testing the pipelines with
water or gas.
Compliance with this requirement for leak-tight tanks in service is demonstrated by implementing
a structural integrity program for each tank site that should be consistent with the guidelines
contained in this guidance and BNL-UC-406, as tailored for the conditions at each high-level
waste storage tank site; or as modified by this guidance for leaking tanks.
Supplemental References:
1. BNL, 1997. Guidelines for Development of Structural Integrity Programs for DOE
High-Level Waste Storage Tanks, BNL-UC-406, Brookhaven National Laboratory,
Upton, NY, January 1997.
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-175
7-09-99
2. DOE, 1992. DOE Fundamentals Handbook, Chemistry, DOE-HDBK-1015, Module 2:
“Corrosion,” U.S. Department of Energy, Washington, D.C., June 1992.
3. DOE, 1993. DOE Fundamentals Handbook, Material Science, DOE-HDBK-1017,
Module 2: “Properties of Metals,” U.S. Department of Energy, Washington, D.C.,
January 1993.
II. Q.(3) Canistered Waste Form Storage. Canisters of immobilized high-level
waste awaiting shipment to a repository shall be:
(a) Stored in a suitable facility;
(b) Segregated and clearly identified to avoid commingling with
low-level, mixed low-level, or transuranic wastes; and
(c) Monitored to ensure that storage conditions are consistent
with DOE/EM–0093, Waste Acceptance Product Specifications
for Vitrified High-level Waste Forms, or DOE/RW-0351, Waste
Acceptance System Requirements Document, for non-vitrified
immobilized high-level waste. Facilities and operating
procedures for storage of vitrified high-level waste shall
maintain the integrity of the canistered waste form.
Objective:
Section 283
The objective of this requirement is to ensure that immobilized (vitrified) high-level waste is
stored and monitored in a manner that meets DOE/EM-0093, Waste Acceptance Product
Specifications for Vitrified High-Level Waste Forms (EM-WAPS), or DOE/RW-0351, Waste
Acceptance System Requirements Document (WASRD). Meeting the requirements of the EM
WAPS or the WASRD reflects the best current understanding of the waste acceptance criteria to
support the geologic repository’s safety case. Because the Nuclear Regulatory Commission will
make the final determination of the adequacy of the acceptance criteria in conjunction with
issuing the repository license amendment to emplace, these criteria are not final and changes to
them may occur as the licensing process progresses.
Discussion:
During the development of DOE O 435.1 and DOE M 435.1-1 storage of immobilized (vitrified)
high-level waste was reviewed for the potential risk to the public, workers and the environment.
Because of its stability, storage of the final waste form is considered to pose a low risk.
Chapter II -High-Level Waste Requirements
II-176 DOE G 435.1-1
7-09-99
However, it is critical, for the acceptance of the waste at the geologic repository (disposal site)
that the waste has been stored and monitored in a manner consistent with the EM-WAPS and/or
the WASRD. Meeting the requirements of these documents is essential because they contain the
technical specifications that current waste form producers are required to meet before acceptance
of their vitrified high-level waste, or non-vitrified high-level waste, into the Civilian Radioactive
Waste Management System. A similar requirement for high-level waste treatment operations is
included at DOE M 435.1-1, Section II.R, Treatment.
Since the objective of each of the three subrequirements (a through c) is to ensure to the greatest
extent possible at this time that the waste is acceptable to the repository, each will be discussed
in terms of the critical EM-WAPS or the WASRD specifications. These specifications are
considered critical because they are considered important to storage operations; however, there
may be other requirements that pertain to storage operations. Refer to the EM-WAPS and the
WASRD for full details on each of the specifications and how they may impact storage
operations. Enveloping all three of the subrequirements for vitrified high-level waste forms is the
EM-WAPS Specification 4, Quality Assurance Specification and WASRD, Section 3.9, Quality
Assurance. These specifications require waste producers to establish a quality assurance
program that is consistent with the Quality Assurance Requirements and Description for the
Civilian Radioactive Waste Management Program (DOE/RW-0333P) requirements. These
requirements apply to storage as well as production operations. The following discussion
focuses on the specifications for vitrified high-level waste, as defined in the EM-WAPS.
However, similar specifications are expected to be developed in the WASRD in the near future
and a discussion on these specifications will be added to this guidance at that time.
Section 284
Subrequirement (a) is intended to ensure that immobilized high-level waste is stored in a facility
that meets the requirements of the EM-WAPS. The EM-WAPS specifications that are
considered critical to meeting this subrequirement are Specification 1.4.2, Control of
Temperature for Phase Stability and Specification 3.7, Specification for Removable Radioactive
Contamination on External Surfaces. The first specification is to certify that after initial
cool-down the waste form temperature has not exceeded 400o centigrade. The second
specification prescribes the level of acceptable surface contamination on a canister at the time of
shipment of beta- and gamma-emitting radionuclides and alpha-emitting radionuclides. Both of
these specifications may require storage facility engineering controls (e.g., active ventilation
systems) to ensure that the centerline temperature limit and the surface contamination limits are
not exceeded.
Subrequirement (b) is intended to ensure that the immobilized high-level waste is clearly
identified to avoid commingling it with other waste types and to reduce the potential for
contaminating other wastes with high-level waste potentially requiring such waste to be sent to
the high-level waste repository. The EM-WAPS specification that meets this subrequirement is
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-177
7-09-99
Specification 2.3, Identification and Labeling Specification, which prescribes the identifying label
that is to be attached to each canister and the size and location of the label.
Subrequirement (c) is intended to ensure that all remaining specifications of the EM-WAPS are
met to ensure the waste is acceptable to the waste repository. The EM-WAPS specification that
is considered critical to meeting this subrequirement is Specification 5, Documentation and Other
Requirements. This administrative specification, among other requirements, prescribes the
contents of the Production Records and the Storage and Shipping Records. The Production
Records identify the physical attributes of each canister of final waste form and the Storage and
Shipping Records describe any abnormal events, such as thermal excursions, which have
occurred during the storage of the canister.
Compliance with this requirement is demonstrated by documenting that the immobilized high-
level waste is stored and monitored in compliance with the EM-WAPS or WASRD
specifications, as applicable.
Supplemental References:
1. DOE, 1996. Waste Acceptance Product Specifications for Vitrified High-Level Waste
Forms (EM-WAPS), Revision 2, DOE/EM-0093, U.S. Department of Energy,
Washington, D.C., December 16, 1996.
2. DOE, 1995. Quality Assurance Requirements and Description for the Civilian
Radioactive Waste Management Program, Revision 5, DOE/RW-0333P, U.S.
Department of Energy, Washington D.C., October 1995.
3. DOE, 1999. Waste Acceptance System Requirements Document, Revision 3, DOE/RW
0351P, U.S. Department of Energy, Washington, D.C., April 1999.
Chapter II -High-Level Waste Requirements
II-178 DOE G 435.1-1
7-09-99
II. R. Treatment.
Treatment shall be designed and implemented in a manner that will ultimately
comply with DOE/EM-0093, Waste Acceptance Product Specifications for Vitrified
High-level Waste Forms, or DOE/RW-0351P, Waste Acceptance System
Requirements Document, for non-vitrified, immobilized high-level waste.
Objective:
Section 285
The objective of this requirement is to ensure that high-level waste treatment (and pretreatment)
activities are designed and implemented in a manner that does not jeopardize the final waste
form’s ability to meet DOE/EM-0093, Waste Acceptance Product Specifications for Vitrified
High-Level Waste Forms (EM-WAPS), or DOE/RW-0351P, Waste Acceptance System
Requirements Document (WASRD), for non-vitrified immobilized high-level waste. Meeting the
requirements of the EM-WAPS or the WASRD ensures that the waste will be acceptable for
disposal in a geologic repository managed by the Office of the Civilian Radioactive Waste
Management.
Discussion:
During the development of DOE O 435.1 and DOE M 435.1-1, treatment of waste was
identified as an activity that presented potential risks to the public, workers, and the
environment. It was determined that requirements to address the weaknesses and conditions that
could lead to potential adverse impacts already existed in external requirements (e.g., Clean Air
Act or RCRA) or other DOE requirements and directives (e.g.,10 CFR Part 835, Occupational
Radiation Protection or DOE O 360.1, Training). Consequently, DOE M 435.1-1, General
Requirements and Responsibilities, Section I.2.F.(14), assigns the Field Element Manager an
umbrella, performance-oriented responsibility for ensuring that waste treatment is protective of
the public, workers, and the environment. This requirement focuses instead on the treatment
actions necessary to make waste acceptable for subsequent waste management steps, e.g.,
disposal in a geologic repository.
This requirement was established to ensure that no pretreatment or treatment activities are
undertaken that may jeopardize the final (vitrified and non-vitrified) waste forms ability to meet
the specifications contained in the EM-WAPS or the WASRD. Meeting this requirement is
essential since the EM-WAPS is the technical specifications that current high-level waste form
producers are required to meet to ensure acceptance of their vitrified high-level waste into the
Civilian Radioactive Waste Management System. Likewise, meeting the requirements of the
WASRD is essential for non-vitrified high-level waste. Thus, it is critical that actions taken up to
waste disposal, predominately pretreatment and treatment activities, do not compromise the
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-179
7-09-99
ability of the waste form to meet these specifications. A similar requirement for high-level waste
storage operations is included at DOE M 435.1-1, Section II.Q., Storage.
Refer to the EM-WAPS for vitrified waste forms for full details on each of the specifications and
how they may be impacted by specific pretreatment or treatment operations. The following
examples are offered to display how an action within a pretreatment or treatment facility could
jeopardize the final waste forms ability to meet the EM-WAPS.
Example 1: At Site X, a change to expedite the production of canisters in the
vitrification process is being proposed that may allow organic contaminants to enter the
canister between the time of glass pouring and canister closure. However, Specification
3.4 of the EM-WAPS requires that the producer ensure that the canistered waste form
does not contain detectable amounts of organic materials. Thus, prior to approval of
such a change to the vitrification process, an evaluation needs to be conducted to
determine the likelihood of such organic contamination. If organic contamination is
possible the proposed change should not be allowed because it could violate the
EM-WAPS specification and jeopardize the acceptance of the waste form.
Section 286
Example 2: At Site Y vitrification (treatment) facility, an order of empty canisters is
received that are slightly out of tolerance with the canister diameter specification (63.0
cm versus the specification of 61.0 +1.5 cm, -1.0 cm). Due to vitrification schedule
concerns, it is proposed by the plant operations management that the canisters be
accepted and used. Such acceptance violates EM-WAPS Specification 2.4.2 and should
not be allowed.
Compliance with this requirement is demonstrated by programs and procedures being
documented and used that ensure that high-level waste product specifications for disposal at a
geologic repository are met, and final waste form acceptance documentation (production records
and storage and shipping records) that certify the requirements of the EM-WAPS or the
WASRD have been satisfactorily met.
Supplemental References:
1. DOE, 1996. Waste Acceptance Product Specifications for Vitrified High-Level Waste
Forms (EM-WAPS), Revision 2, DOE/EM-0093, U.S. Department of Energy,
Washington, DC, December 16, 1996.
2. DOE, 1999. Waste Acceptance System Requirements Document, Revision 3, DOE/RW
0351P, U.S. Department of Energy, Office of Civilian Radioactive Waste Management,
April 1999.
Chapter II -High-Level Waste Requirements
II-180 DOE G 435.1-1
7-09-99
II. S. Disposal.
Disposal of high-level waste must be performed in accordance with the provisions
of the Atomic Energy Act of 1954, as amended, the Nuclear Waste Policy Act of
1982, as amended, or any other applicable statutes.
Objective:
The objective of this requirement is to ensure that high-level waste management activities, from
generation through post-treatment storage, do not jeopardize the Department’s ability to meet
the provisions of the Atomic Energy Act of 1954, as amended, the Nuclear Waste Policy Act of
1982, as amended, and other applicable statutes for high-level waste disposal.
Discussion:
The safety and hazard analysis for management of radioactive waste, conducted to develop the
essential requirements for DOE O 435.1 and DOE M 435.1-1, indicated that disposal is the most
critical activity requiring controls because disposal is intended to be the last function conducted
on the waste, yet the potential hazards from radioactive waste will continue far into the future.
Although the disposal of high-level waste at a geologic repository may be regulated by the
Nuclear Regulatory Commission (NRC) and the requirements of DOE O 435.1 and DOE M
435.1-1 do not apply to the repository, except as required by DOE O 435.1, Section 4.d., this
requirement is necessary to ensure that DOE’s high-level waste management activities support
any applicable disposal requirements at a repository.
As discussed in the guidance for Section I.2.F.(15), Disposal, the Field Element Manager is
responsible for ensuring that radioactive waste is disposed in a manner that protects the public,
workers, and the environment. For high-level waste this requirement means that DOE’s actions
taken during generation, pre-treatment, treatment, and post-treatment storage must not
jeopardize the final waste form’s ability to meet the provisions of the Nuclear Waste Policy Act
of 1982, as amended. This is accomplished through compliance with the requirements of the
DOE Office of Environmental Management’s Waste Acceptance Product Specifications (EM
WAPS). The following is a brief description of the programs and documents that ensure the
EM-WAPS meets the provisions of the Nuclear Waste Policy Act of 1982, as amended. Also
included is a brief description of the responsibilities and interfaces between the DOE Office of
Environmental Management and the DOE Office of Civilian Radioactive Waste Management.
Section 287
Nuclear Waste Policy Act of 1982, as amended. From the Energy Reorganization Act of 1974,
the NRC was granted licensing and regulatory authority for the receipt, storage, and disposal of
high-level radioactive wastes at a geologic repository. From this authority and the Nuclear
Waste Policy Act of 1982, as amended, the NRC promulgated 10 CFR Part 60, “Disposal of
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-181
7-09-99
High-Level Radioactive Wastes in Geologic Repositories,” which prescribes the “rules governing
the licensing of DOE to receive and possess source, special nuclear, and byproduct material at a
geologic repository operations area sited, constructed, or operated in accordance with the
Nuclear Waste Policy Act of 1982.”
In addition, the Nuclear Waste Policy Act of 1982, as amended, recognized the Federal
responsibility for managing the disposal of spent nuclear fuel and high-level waste as defined in
the Nuclear Waste Policy Act of 1982, as amended. The Office of Civilian Radioactive Waste
Management, established under the Nuclear Waste Policy Act of 1982, as amended, developed
the DOE/RW-0351P, Waste Acceptance System Requirements Document (WASRD) that
describes the functions to be performed and the technical requirements for a “Waste Acceptance
System” for accepting spent nuclear fuel and high-level radioactive waste into the Civilian
Radioactive Waste Management System. The WASRD, which is subject to the requirements of
the Office of Civilian Radioactive Waste Management DOE/RW-0333P, Quality Assurance
Requirements and Description Document, establishes the requirements for acceptance of high-
level waste into the geologic repository. The waste acceptance requirements contained in the
WASRD are derived from a number of documents including statutes, regulations, and DOE
directives; the primary requirements are contained in 10 CFR Part 60. The EM-WAPS is derived
from the WASRD, and serves as the basis for the high-level waste producer’s Waste Acceptance
programs.
The EM-WAPS outline the technical specifications waste form producers are required to meet in
order to ensure acceptance of their vitrified high-level waste into the Office of Civilian
Radioactive Waste Management system. The Office of Environmental Management has the
responsibility for providing product specifications to the waste form producers. The Office of
Environmental Management also ensures that the EM-WAPS are in concert with the Office of
Civilian Radioactive Waste Management WASRD. Compliance by the vitrified waste form
producers with the current EM-WAPS ensures that the disposal provisions of the Nuclear Waste
Policy Act of 1982, as amended, will be met. The specifications from the current EM-WAPS are
not duplicated here; refer to the current EM-WAPS for additional information on each
specification.
Atomic Energy Act of 1954, as amended. It is recognized that onsite disposal of high-level
waste may be possible under the provisions of the Atomic Energy Act of 1954, as amended.
However, the safety and hazards analysis conducted to support DOE O 435.1 and DOE M
435.1-1 did not evaluate disposal activities for high-level waste at a DOE site. Therefore, DOE
O 435.1 and DOE M 435.1-1 do not include safety and administrative requirements for such
activities. Further, DOE plans that high-level waste be treated to meet specifications for
acceptance for disposal at a repository under the Nuclear Waste Policy Act of 1982, as amended.
Onsite disposal of high-level waste is not consistent with these plans.
Section 288
Chapter II -High-Level Waste Requirements
II-182 DOE G 435.1-1
7-09-99
Interfaces Between the Office of Environmental Management and Office of Civilian Radioactive
Waste Management . Responsibilities of, and interfaces between, the Office of Environmental
Management and Office of Civilian Radioactive Waste Management for the management of high-
level waste are defined in the Memorandum of Agreement between the Office of Environmental
Management and Office of Civilian Radioactive Waste Management (Memorandum of
Agreement for Acceptance of Department of Energy Spent Nuclear Fuel and High-Level
Radioactive Waste), dated January 1999. Guidance on these requirements is provided here to
assist in determining the boundaries of responsibilities for these two organizations.
The Memorandum of Agreement (MOA) responds to the requirements of the Nuclear Waste
Policy Act of 1982, as amended, that Federal agencies requiring disposal services for spent
nuclear fuel and/or high-level waste be accommodated by a suitable interagency agreement
reflecting the terms and conditions set forth in the Standard Contract for Disposal of Spent
Nuclear Fuel and/or High-Level Radioactive Waste as provided in the Nuclear Waste Policy Act
of 1982, as amended. Through the MOA, the Office of Environmental Management and Office
of Civilian Radioactive Waste Management seek to achieve safe and timely disposal of DOE
spent nuclear fuel and high level waste by identifying data needs, interface descriptions, and
acceptance criteria and developing compliance procedures needed to support both the geologic
repository license application to the NRC and the transportation system necessary to transfer
DOE spent nuclear fuel and high-level waste to an Office of Civilian Radioactive Waste
Management facility.
The following are the highlights of the MOA that support the management of high-level waste.
These are provided to support the use of DOE O 435.1 and DOE M 435.1-1. Refer to the MOA
for additional details. The MOA is available on the Internet at
http://www.rw.doe.gov/pages/resource/facts/moafin3r1.pdf.
A. Data Needs
Any changes to the Waste Form Compliance Plan, Waste Form Qualification Report,
Production Records and Storage and Shipping Records, which presently meet the Office
of Civilian Radioactive Waste Management data needs, shall be coordinated between the
Office of Civilian Radioactive Waste Management and Office of Environmental
Management.
B. Design, Certification and Fabrication of Transportation and Storage Systems for DOE
High-level waste
The Office of Environmental Management shall design, fabricate and store high-level
waste pour canisters. The Office of Civilian Radioactive Waste Management shall be
Chapter II -High-Level Waste Requirements
http://www.rw.doe.gov/pages/resource/facts/moafin3r1.pdf
DOE G 435.1-1 II-183
7-09-99
responsible for the design, NRC certification and fabrication of the transportation cask
system.
C. Transportation and Loading Operations
Section 289
The Office of Environmental Management shall be responsible for the Office of
Environmental Management site infrastructure and shall provide all preparation,
assembly, and inspections for loading high-level waste pour canisters into transportation
casks and for the transportation of high-level waste to the Office of Civilian Radioactive
Waste Management. For the loading of high-level waste pour canisters into the
transportation casks, the Office of Civilian Radioactive Waste Management shall provide
written procedures and training for cask handling and loading and information and parts
necessary for cask maintenance. For the handling of high-level waste at an Office of
Civilian Radioactive Waste Management facility, the Office of Environmental
Management shall provide similar records to the Office of Civilian Radioactive Waste
Management. The Office of Civilian Radioactive Waste Management shall be responsible
for routine cask maintenance, while incidental maintenance is the responsibility of
whichever organization possesses the cask.
D. Conformance and Safeguards Verification of High-level waste
The Office of Civilian Radioactive Waste Management shall perform conformance
verification of all high-level waste delivered to the Office of Civilian Radioactive Waste
Management and shall agree to accept the high-level waste that meets the acceptance
criteria for disposal when the Office of Civilian Radioactive Waste Management has
completed safeguards verification and determined that the material is properly loaded,
packaged, marked, labeled and ready for transportation. The Office of Civilian
Radioactive Waste Management reserves the right to refuse to accept improperly
described high-level waste. If the Office of Civilian Radioactive Waste Management has
already accepted improperly described high-level waste, the Office of Environmental
Management must provide the Office of Civilian Radioactive Waste Management with a
proper designation within 30 days. Temporary storage of improperly described high-level
waste will be at the facility where the material resides at the time the improper
designation is discovered.
E. Acceptance of High-level Waste
The Office of Civilian Radioactive Waste Management shall accept high-level waste at
the Office of Environmental Management site after successful conformance and
safeguards verification and shall be solely responsible for control of all material upon
acceptance.
Chapter II -High-Level Waste Requirements
II-184 DOE G 435.1-1
7-09-99
F. NRC Licensing for Storage and Disposal
The Office of Civilian Radioactive Waste Management shall have the lead responsibility
in repository and storage facility (if needed) pre-licensing and licensing interactions with
the NRC. The Office of Environmental Management shall support the Office of Civilian
Radioactive Waste Management in these interactions.
G. Training
The Office of Environmental Management and Office of Civilian Radioactive Waste
Management shall each be responsible for providing or acquiring training specific to their
various responsibilities as described in the MOA.
H. Quality Assurance
Section 290
The Office of Environmental Management and Office of Civilian Radioactive Waste
Management shall abide by requirements of the Office of Civilian Radioactive Waste
Management’s Quality Assurance Requirements and Description (DOE/RW-0333P) and
the Quality Assurance MOAs between the Office of Environmental Management and
Office of Civilian Radioactive Waste Management. For high-level waste, this is the MOA
between the Office of Waste Management and Office of Civilian Radioactive Waste
Management for Coordination of Quality Assurance Activities Associated with High-
Level Waste and Spent Nuclear Fuel (Appendix E to the MOA). Specific activities
subject to Quality Assurance controls are defined in Quality Assurance Requirements
and Description.
Compliance with this requirement is demonstrated by the preparation and acceptance of the
waste acceptance documentation required by the EM-WAPS. This includes the Waste Form
Compliance Plan, the Waste Form Qualification Report, Production Records, and Storage and
Shipping Records. The contents of these documents are specified throughout the EM-WAPS.
Supplemental References:
1. Nuclear Waste Policy Act of 1982, as amended, Public Law 97-425, Section 2.(12),
January 7, 1983.
2. Atomic Energy Act of 1954, as amended, August 30, 1954.
3. DOE, 1999. Waste Acceptance System Requirements Document, Revision 3, DOE/RW
0351P, U.S. Department of Energy, Washington, D.C., April 1999.
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-185
7-09-99
4. DOE, 1995. Quality Assurance Requirements and Description for the Civilian
Radioactive Waste Management Program, DOE/RW-0333P, U.S. Department of
Energy, Washington, D.C., October 2, 1995.
5. DOE, 1996. Waste Acceptance Product Specifications for Vitrified High-Level Waste
Forms (EM-WAPS), Revision 2, DOE/EM-0093, U.S. Department of Energy,
Washington, D.C., December 16, 1996.
6. DOE, 1999. Assistant Secretary for Environmental Management (EM) to the Director
Office of Civilian Radioactive Waste Management (RW), memorandum, Memorandum of
Agreement for Acceptance of Department of Energy Spent Nuclear Fuel and High-Level
Radioactive Waste, Revision 1, U.S. Department of Energy, January, 1999. Available on
the Internet at http://www.rw.doe.gov/pages/resource/facts/moafin3r1.pdf
7. EPA, 1985. “Final Rule; 40 CFR 191, Environmental Radiation Protection Standards for
Management and Disposal of Spent Nuclear Fuel, High-Level and Transuranic
Radioactive Wastes,” Federal Register, Vol 50, No. 182, U.S. Environmental Protection
Agency, Washington, D.C., September 19, 1985.
Chapter II -High-Level Waste Requirements
http://www.rw.doe.gov/pages/resource/facts/moafin3r1.pdf
II-186 DOE G 435.1-1
7-09-99
II. T. Monitoring.
High-level waste pretreatment, treatment, storage, and transportation facilities
shall be monitored for chemical, physical, radiological, structural, and other
changes that could indicate failure of systems confinement, integrity, or safety, and
which could lead to abnormal events or accidents. Parameters that shall be
sampled or monitored, at a minimum, include: temperature, pressure (for closed
systems), radioactivity in ventilation exhaust and liquid effluent streams,
flammable or explosive mixtures of gases, level and/or waste volume, and significant
waste chemistry parameters for non-immobilized high-level waste. Facility
monitoring programs shall also include physical inspections to verify that control
systems have not failed.
Section 291
Objective:
The objectives of this requirement are to: specify minimum parameters for which data will be
routinely collected and analyzed; ensure by physical inspection that instrumentation, controls,
automatic monitoring systems, and automatic shut-off systems have not failed; sample the
chemical characteristics (appropriate parameters and monitoring frequencies) of the waste
necessary to support the requirements of the structural integrity program; and promptly evaluate
the results of the inspections and sample analyses.
Discussion:
This monitoring requirement is intended to alert facility operators to releases and the potential
for releases of radioactivity in effluents and to the generation of explosive and flammable gases
from operations. During the development of DOE O 435.1 and DOE M 435.1-1, monitoring at
radioactive waste management facilities was identified as an effective way to mitigate numerous
weaknesses and conditions associated with all phases of the life-cycle of waste management. An
analysis of existing departmental requirements for environmental monitoring in DOE 5400.1 and
DOE 5400.5 found that they were applicable to all radioactive waste types and all radioactive
waste management facilities. Many of the individual conditions that were evaluated in the safety
and hazards analysis and that warranted monitoring are already monitored due to the
implementation of the requirements in DOE 5400.1 and DOE 5400.5. Consequently, DOE M
435.1-1 Section I.1.E.(7), Environmental Monitoring, requires that these two DOE Orders be
implemented for environmental monitoring of radioactive waste management facilities.
While the environmental monitoring mandated by DOE 5400.1 and DOE 5400.5 is adequate to
detect after-the-fact releases of high-level waste to the environment, additional requirements are
necessary to improve the detection of conditions that could provide warning of impending
releases that could increase worker exposure and/or impact the environment. Some of the
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-187
7-09-99
requirements contained in the Nuclear Safety Analysis Reports Order (DOE 5480.23), related
DOE standards (DOE-STD-3009-93, DOE-STD-1027-92, DOE-EM-STD-5502-04), and the
Facility Safety Order (DOE 420.1), provide information on the hazard categorization of facilities
and the safety analyses to be performed. Through the conduct of safety analyses for high-level
waste management facilities (e.g., storage, pretreatment, treatment, and transportation), facility
personnel identify the quantity and form of radioactive material to be handled at the facility, the
operations for managing the waste, and the associated hazards of this source term under the
proposed operational scenario. The safety analysis establishes a basis for defining the acceptable
operational envelope for the facility and provides the basis for identifying technical safety
requirements if needed. The technical safety requirements may include requirements for
monitoring; however, facility personnel need to also review the safety analysis to determine if it
indicates other monitoring that would be prudent.
An effective monitoring program is dependent on the frequency and the rigor of the monitoring
operations, and the effectiveness of the systems and devices in detecting changes and abnormal
conditions. Therefore, facility managers must take these factors into consideration when
designing the monitoring program to ensure that the high-level waste systems are being operated
according to design.
Section 292
The specified parameters to be monitored are selected based on their significance for anticipating
and identifying undesirable conditions and the availability of a means for monitoring them. In
addition, parameters to be monitored include those to ensure the protection of public health, the
environment, and workers due to releases of radioactivity in ventilation exhausts and liquid
effluent streams, and from unsafe concentrations of flammable and/or explosive gases in the
waste. The accuracy and precision of measurement required is dictated by the expected
variations in the parameters and the level of accuracy and precision needed to identify problems.
The monitoring frequency for specific parameters is likewise determined based on the possible
time variation of the parameter and the response time required to take mitigating action. For
facilities that release radioactive effluents, frequent monitoring or continuous monitoring may
need to be considered.
Example 1: A high-level waste treatment facility includes a holding tank that contains
liquid high-level waste that can be held for months prior to processing. The tank is
equipped with an induced draft ventilation system. The tank must include monitoring
capability for temperature, radioactivity in the ventilation system, waste level and/or
volume, and significant chemical parameters. Where the contents of the waste generate
flammable or explosive mixtures of gases, monitoring capability must also be provided
to detect the concentrations of such gases. The other minimum parameter (pressure)
need not be monitored because the tank is ventilated, not closed.
Chapter II -High-Level Waste Requirements
II-188 DOE G 435.1-1
7-09-99
Example 2: A high-level waste treatment facility has an interim storage tank that
contains liquid high-level waste. The minimum parameters specified in the monitoring
requirement in DOE M 435.1-1 are monitored. The facility manager has identified
additional parameters to be monitored and established a monitoring schedule based on
the hazards identified in the Safety Analysis Report.
High-level waste management facilities are required to apply the monitoring requirement for the
specified parameters using a graded approach. As previously noted, the methods used and the
frequencies of monitoring are commensurate with the significance of changes in the parameters.
The monitoring of waste level and/or volume is required to address a high hazard that was
identified by the hazards analysis performed in support of this Order and Manual -- the failure to
promptly detect a release of high-level waste that could impact workers, the public, or the
environment. The monitoring of these parameters addresses the operation of monitoring systems
to detect vessel or transfer equipment failure that is of sufficient magnitude to cause a detectable
volume change as well as to alert operators that a vessel (e.g., tank or bin) is approaching
capacity so that overfilling can be avoided. This requirement is focused on operations, and is
closely related to the requirement in Section II.P.(2)(j) which requires engineered monitoring
systems.
There are a number of complicating factors that must be considered to meet the level/volume
aspect of the monitoring requirement. Some of these factors could lead to failure to detect leaks
and/or to over-react to changes in surface level indicators. These factors include the following:
Section 293
(1) Irregular shaped crusts can form on the surface of the waste during storage,
which could render automatic surface level detection devices unreliable for
promptly detecting actual changes in the volume of the waste in a storage tank.
The irregular crust could lead to false indications of increase, decrease, or no
change in surface level and tank volume.
(2) High-level waste storage tanks with a very high thermal load will cause
evaporation resulting in a decrease in tank surface level and volume. The
decrease in tank volume must be correlated with the calculated rate of
evaporation before a judgement can be made regarding whether the tank is
leaking.
(3) Chemical conditions in the waste tank can result in gases generated within the
waste becoming trapped within the waste matrix, leading to indications of false
increases in the surface level.
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-189
7-09-99
(4) For underground storage tanks, an increase in the surface level can also result
from an inflow of groundwater through leak-sites above the level of the waste,
indicating a loss of structural integrity.
(5) Intentional additions to and removals from the storage vessels must also be
considered in evaluating the monitoring results.
Example 1: An unexpected chemical reaction generates gas that is trapped within the
waste matrix. The resulting rise in surface level precluded the detection of a leak in the
tank by monitoring surface level only.
Example 2: Operating personnel at a high-level waste storage facility calculated the
evaporative loss expected from a tank based on an assumed radionuclide inventory. The
actual radionuclide inventory was much smaller than that assumed, so the actual heat
generation rate was much smaller than that assumed. Overestimation of the change in
waste volume due to evaporation resulted in failure to detect leakage that was
incorrectly assumed to be evaporative loss.
The monitoring of waste chemistry parameters needs to be able to detect significant changes
important to corrosion, and to the generation of explosive and/or flammable gases. The
frequency of monitoring should satisfy the requirements identified by the structural integrity
program in Section II.Q.(2), but the frequency of monitoring may need to be even greater if
required to monitor the formation of gases.
Monitoring of waste chemistry parameters needs to:
(1) detect changes in the waste chemistry that cause changes in the rates of the
critical corrosion modes previously identified;
(2) determine if new critical corrosion modes have been established;
(3) determine when adjustments to waste chemistry are required to maintain the
predicted corrosion rates established by the structural integrity program
[II.Q.(2)]; and
(4) monitor the formation and accumulation of any gases within the waste.
Other design related requirements of this chapter include Confinement in Section II.P.(2)(b) and
Instrumentation and Control in Section II.P.(2)(i).
Chapter II -High-Level Waste Requirements
II-190 DOE G 435.1-1
7-09-99
A graded approach is applied to operational implementation of this requirement for monitoring
to detect releases promptly. The full suite of parameters to be monitored as well as the methods
for monitoring them are tailored to the specific facility and vessel. For example, it may not be
necessary to provide continuous monitoring of waste levels and waste parameters in bins of
stored calcined high-level waste, since corrosion is not usually a problem.
Section 294
Compliance with this requirement is demonstrated by: the identification of, and justification for,
the parameters to be monitored and the frequency with which they will be monitored including
coordination with the structural integrity program to identify important waste chemistry
parameters and appropriate monitoring frequency; development and implementation of
procedures and training to insure that disciplined and effective monitoring is sustained; and
prompt evaluation of monitoring data by qualified personnel and prompt reporting of findings to
management.
Supplemental References:
1. DOE, 1994. DOE Limited Standard: Hazard Baseline Documentation, DOE-EM-STD
5502-04, U.S. Department of Energy, Washington, D.C., August, 1994.
2. DOE, 1992. Nuclear Safety Analysis Reports, DOE 5480.23, U.S. Department of
Energy, Washington, D.C., April 10, 1992.
3. DOE. DOE Fundamentals Handbook, Material Science, Corrosion, DOE-HDBK-1017.
4. BNL, 1997. Guidelines for Development of Structural Integrity Programs for DOE
High-Level Waste Storage Tanks, Brookhaven National Laboratory, BNL-UC-406,
January 1997.
5. DOE, 1986. Nuclear Safety Analysis and Review System, DOE 5481.1B (canceled),
U.S. Department of Energy, Washington, D.C., September 23, 1986.
6. DOE, 1992. Hazard Categorization and Accident Analysis Techniques for Compliance
with DOE Order 5480.23, Nuclear Safety Analysis Reports, DOE-STD-1027-92, U.S.
Department of Energy, Washington, D.C., December 1992.
7. DOE, 1993. SAR Preparation Guide, DOE-STD-3009-93, U.S. Department of Energy,
Washington, D.C., 1993.
8. DOE, 1995. Facility Safety, DOE O 420.1, U.S. Department of Energy, Washington,
D.C., October 13, 1995.
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-191
7-09-99
II. U. Closure. The following requirements for closure of deactivated high-level waste
facilities and sites are in addition to those in Chapter I of this Manual.
(1) Decommissioning. Deactivated high-level waste facilities/sites shall meet the
decommissioning requirements of DOE O 430.1A, Life-Cycle Asset
Management and the requirements of DOE 5400.5, Radiation Protection of
the Public and the Environment, for release; or
(2) CERCLA Process. Deactivated high-level waste facilities/sites shall be
closed in accordance with the CERCLA process as described in Section
I.2.F.(5); or
(3) Closure. Deactivated high-level waste facilities/sites shall be closed in
accordance with an approved closure plan, as specified below. Residual
radioactive waste present in facilities to be closed shall satisfy the waste
incidental to reprocessing requirements of this Chapter.
(a) Facility/Site Closure Plans. A closure plan shall be developed for
each deactivated high-level waste facility/site being closed that
defines the approach and plans by which closure of each facility
within the site is to be accomplished. This plan shall be completed
and approved prior to the initiation of physical closure activities, and
updated periodically to reflect current analysis and status of
individual facility closure actions. The plan shall include, at a
minimum, the following elements:
1. Identification of the closure standards/performance objectives
to be applied from Chapter III or IV, as appropriate;
2. A strategy for allocating waste disposal facility performance
objectives from the closure standards identified in the closure
plan among the facilities/units to be closed at the site;
Section 295
3. An assessment of the projected performance of each unit to be
closed relative to the performance objectives allocated to each
unit under the closure plan;
4. An assessment of the projected composite performance of all
units to be closed at the site relative to the performance
objectives and closure standards identified in the closure plan;
and
Chapter II -High-Level Waste Requirements
II-192 DOE G 435.1-1
7-09-99
5. Any other relevant closure controls including a monitoring
plan, institutional controls, and land use limitations to be
maintained in the closure activity.
Objective:
The objective of this requirement is to ensure that closure of deactivated high-level waste
facilities follows one of three acceptable closure processes. The first requirement allows
deactivated high-level waste management facilities that can meet the decommissioning
requirements of DOE O 430.1A to be released for restricted or unrestricted use. The second
part allows deactivated high-level waste facilities to be closed using the Comprehensive
Environmental Response, Compensation, and Liability Act of 1980 (CERCLA) process to
demonstrate compliance with DOE Orders and other requirements under the Atomic Energy Act
of 1954, as amended. The final part defines the requirements that shall be met for all other
deactivated high-level waste facilities that are to be closed.
Discussion:
In support of the requirements in Section II.U, there are a number of requirements in Chapter I
of DOE M 435.1-1 that address closure and need to be considered with this section. These
include Section I.2.E.(2), Site Closure Plans, which defines the roles and responsibilities of the
Deputy Assistant Secretaries for Waste Management and/or Environmental Restoration and
Section I.2.F.(8), Closure Plans, which defines the same for the Field Element Manager.
Guidance for each of these sections describes the roles and responsibilities for developing,
reviewing, approving, and implementing the closure documents required by this section.
Additionally, Section I.2.F.(5), Environmental Restoration, Decommissioning, and Other
Cleanup Waste, defines the roles and responsibilities for managing and disposing of radioactive
waste resulting from environmental restoration activities and will likely include decommissioning
activities. These activities may overlap with the closure requirements of this section and
therefore need to be reviewed for applicability.
To understand the scope of the requirements in Section II.U, the following definitions are
provided. Chapter I of DOE M 435.1-1 defines closure as:
“Deactivation and stabilization of a radioactive waste facility intended for long-term
confinement of waste.”
DOE O 430.1A, Life-Cycle Asset Management, defines deactivation as:
“Process of placing a facility in a stable and known condition including the removal of
hazardous and radioactive materials to ensure adequate protection of the worker, public
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-193
7-09-99
health and safety, and the environment thereby limiting the long-term cost of surveillance
and maintenance. Actions include the removal of fuel, draining and/or de-energizing
nonessential systems, removal of stored radioactive and hazardous materials, and related
actions. Deactivation does not include all decontamination necessary for the
dismantlement and demolition phase of decommissioning, e.g., removal of contamination
remaining in the fixed structures and equipment after deactivation.”
Section 296
The scope of the closure requirements in Section II.U includes those activities necessary to
complete the life cycle of former (deactivated) high-level waste facilities, or a group of facilities
(herein named a site), by stabilizing residual hazardous and radioactive materials in a manner that
ensures adequate protection of the worker, public health and safety, and the environment to limit
long-term management of the facility. Activities that may be included are deactivation (as
defined above), as well as post-deactivation activities, such as decontamination and
decommissioning activities, both of which support placing a facility in a final state that requires
the minimal amount of long-term management. The closure of deactivated high-level waste
facilities is considered an activity that may be driven by DOE Orders, external regulations, local
agreements, or both and therefore requires flexibility in meeting the objectives stated above. For
this reason, the requirements in Section II.U provide three alternative paths to accomplishing
closure: (1) meeting the decommissioning requirements of DOE O 430.1A and the release
requirements and guidelines contained in DOE 5400.5; (2) following the CERCLA process to
meet DOE requirements; or (3) meeting the requirements of a DOE-approved facility/site
specific closure plan. Following a brief discussion on the waste incidental to reprocessing
determination process, each of these paths are discussed.
Waste Incidental to Reprocessing. Material remaining in a deactivated high-level waste
management facility that meets the requirements in Section II.B for the Citation or Evaluation
processes can be included in the closure process, as discussed in this guidance, and managed as
either low-level waste or transuranic waste. If it does not meet the criteria for determining that
the waste is incidental to reprocessing, then the residual waste must be managed as high-level
waste.
As discussed in the guidance for Section II.A, Definition of High-Level Waste, DOE plans to
dispose of high-level waste in a geologic repository consistent with the Nuclear Waste Policy Act
of 1982, as amended. This plan was outlined in Secretary Hodel’s letter to President Reagan
(DOE, 2/6/85), in which the Secretary recommended that “the Department proceed with plans
and actions to dispose of defense waste in a commercial repository.” President Reagan’s finding,
in accordance with Section 8 of the Nuclear Waste Policy Act of 1982, as amended (Presidential
memo, 4/30/85), found no basis to do otherwise and the Department has since implemented
plans to dispose high-level waste in a geologic repository consistent with the Nuclear Waste
Policy Act of 1982, as amended. Thus, any residual radioactive material remaining in deactivated
high-level waste management facilities must meet the waste incidental to reprocessing evaluation
Chapter II -High-Level Waste Requirements
II-194 DOE G 435.1-1
7-09-99
process requirements for a high-level waste closure activity to continue under these
requirements.
Section 297
Decommissioning. Section II.U.(1), Decommissioning, provides the opportunity to close
deactivated high-level waste facilities/sites by meeting the Department’s public dose limits for
residual radioactive material which allows restricted or unrestricted release of the property. The
draft guide on decommissioning, Draft G 430.1-4, Decommissioning Implementation Guide, and
Chapter IV of DOE 5400.5, Radiation Protection of the Public and the Environment, discuss
the requirements/guidance on meeting these public dose limits. The draft DOE G 430.1-4
provides the framework and guidance for implementing DOE O 430.1A and DOE P 450.4,
Safety Management System Policy, during decommissioning activities conducted as part of
facility disposition. Draft DOE G 430.1-4 also addresses the implementation of the Policy on
Decommissioning of DOE Facilities Under the Comprehensive Environmental Response,
Compensation, and Liability Act (CERCLA), dated May 22, 1995 (commonly known as the
Decommissioning Policy). Chapter IV, Residual Radioactive Material, of DOE 5400.5, defines
the radiological protection requirements and guidelines for cleanup of residual radioactive
material that are applicable to allow the free release of deactivated high-level waste facilities for
use without radiological restrictions.
While it is believed the number of former high-level waste facilities or sites that can meet this
criteria will be small, the requirement is provided to allow closure through meeting the prescribed
dose limits and surface contamination guidelines, where possible. In order to make such a
determination, release criteria should be developed on the basis of the guidelines found in
Chapter IV of DOE 5400.5. Chapter IV of DOE 5400.5 includes additional information on the
development of site-specific release criteria and guidelines. DOE policy requires residual
radioactivity to be reduced in accordance with ALARA principles before a site is released. The
principles of ALARA are discussed in both DOE 5400.5 and the guidance to DOE M 435.1-1,
Section I.2.F.(12).
The roles and responsibilities of the Field Element Manager, the Program Office, and the Office
of Environment, Safety, and Health that are to be met for this closure path are contained in DOE
5400.5 and DOE O 430.1A.
CERCLA Process. Section II.U.(2), CERCLA Process, allows deactivated high-level waste
facilities/sites to be closed using the CERCLA process to demonstrate compliance with the
Atomic Energy Act requirements in the DOE Orders. Information on use of the CERCLA
process can be found in numerous documents published by the Environmental Protection Agency
(EPA) and DOE. Some of these documents are included in the listing of supplemental references
at the end of this guidance section. Additionally, guidance to DOE M 435.1-1, Section I.2.F.(5),
provides information on the use of the CERCLA process for planning and managing onsite
disposal of low-level waste resulting from environmental activities, which includes
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-195
7-09-99
decommissioning and facility closure. (As noted in the guidance to Section I.2.F.(5), the
requirement in Section I.2.F.(5) replaces the January 1997 guidance for complying with DOE
5820.2A and the May 1996 policy for demonstrating compliance with DOE 5820.2A for
CERCLA or cleanup activities).
Section 298
DOE high-level waste sites may follow the CERCLA process either because they are listed on
the National Priorities List (NPL) or because the regulatory structure established in cleanup
strategies (e.g., negotiated agreements) is based on CERCLA authority and procedures. As
discussed in the guidance to Section I.2.F.(5), the CERCLA process may be used to demonstrate
compliance with the requirements of DOE O 435.1 and DOE M 435.1-1 with regard to the safe
management and onsite disposal of waste generated by environmental restoration activities.
Application of the CERCLA process to the closure of deactivated high-level waste management
facilities involves the following:
• Remedial Investigation (RI) is a process undertaken to determine the nature and
extent of the problem. The RI emphasizes data collection and site
characterization and is generally performed concurrently and in an interactive
manner with the feasibility study.
• Feasibility Study (FS) is undertaken to develop and evaluate options for remedial
action. The FS emphasizes data analysis, using data gathered during the RI, and
defines the objectives of the response action, to develop remedial alternatives and
to undertake an initial screening and detailed analysis of the alternatives.
• Record of Decision documents the final selection of the cleanup option. This
ROD also satisfies relevant NEPA requirements.
• Remedial Design is the technical analysis and procedures which follow the
selection of the remedy and results in detailed plans and specifications for
implementation.
• Remedial Action involves the actual construction or implementation of the
cleanup.
As part of the Remedial Design, the applicable or relevant and appropriate requirements
(ARARs) must be selected. The guidance for Section I.2.F.(5) provides additional information
on the selection of ARARs and the applicability of DOE O 435.1 and DOE M 435.1-1 . This
guidance also provides additional instructions on the applicability and demonstration of
compliance with the performance objectives for a waste disposal facility in Section IV.P.(1) of
DOE M 435.1-1.
Chapter II -High-Level Waste Requirements
II-196 DOE G 435.1-1
7-09-99
The roles and responsibilities of the Field Element Manager and the Deputy Assistant Secretaries
for Waste Management and Environmental Restoration for this closure path can be found in
Sections I.2.F.(8) and I.2.E.(2), respectively.
Closure. Section II.U.(3), Closure, provides the third path for the closure of deactivated
high-level waste facilities. This process includes the preparation of a closure plan that contains
the elements defined in Sections II.U.(3)(a)(1) through (5). Each of these elements, as well as
the expectations for a closure plan, are discussed below. The roles and responsibilities of the
Field Element Manager, defined in Section I.2.F.(8), Closure Plans, and the Deputy Assistant
Secretaries for Waste Management and Environmental Restoration, defined in Section I.2.E.(2),
Site Closure Plans, are critical to the implementation of the closure process and need to be
closely coordinated with the requirements in Section II.U.(3) to ensure the closure process meets
its objectives.
Section 299
Facility/Site Closure Plans. For each deactivated high-level waste facility or site, a closure plan
must be developed. The general purpose of closure plans is to define the approach that will be
taken for ensuring the long-term protection of the public and the environment from the closure of
deactivated high-level waste facilities containing residual low-level or transuranic wastes.
Included as part of this approach are the purpose and objectives of the closure action and general
discussion of how the specific closure action fits within other past, and planned, closure actions.
The closure plan should also address the three phases that a facility closure may experience.
These are: (1) operational or interim closure; (2) final facility closure; and (3) institutional
closure.
Operational, or interim closure, includes those activities that are conducted to stabilize a
deactivated high-level waste facility, but do not include the final actions necessary to support
minimal, long-term maintenance. Final closure activities include those activities that complete
the physical activities necessary for the closure of the facility/site but do not include long-term
institutional control activities. Institutional control closure follows final closure and includes the
actions and measure necessary to ensure long-term stability of the site such as monitoring and
land use limitations.
Example: Closure of a group of deactivated high-level waste tanks at Site K is planned
and defined in a Closure Plan. Included is a schedule and list of activities that defines
the activities planned for each phase of the closure. First is Interim Closure which will
involve all the activities necessary, following bulk waste removal, to stabilize the tanks
and their contents including filling them and the connecting piping with grout, to avoid
subsidence. Stabilization also allows tank surveillance and maintenance activities to be
reduced. The Final Closure phase is planned to be a CERCLA closure action that
includes all the tanks and other facilities within the area of this group of tanks and
includes the application of a cap, ground cover, and the installation of monitoring
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-197
7-09-99
stations and permanent markers. The Institutional Closure phase is planned to last up
to 100 years after the Final Closure phase and will include monitoring, land use
limitations, and any necessary corrective actions, e.g., additional erosion protection, to
ensure protection of the public and the environment.
The closure plan needs to address all activities to be performed during and following
deactivation of a facility, including decommissioning, with emphasis on those activities required
to minimize the need for long-term maintenance and maximize the stability of the closed facility.
As with the closure of low-level waste disposal facilities, a period of active institutional control
of 100 years is normally assumed during which access is controlled, and monitoring, and
custodial maintenance is performed. However, longer periods of institutional control may be
assumed when justification is provided in documented plans which describe long-term site land
use or site remediation.
Section 300
Closure plans need to include the conceptual/preliminary designs and approaches to be taken for
each step in the closure process and should be coordinated with the monitoring plan (see
discussion below) for the closure facility or site. The closure plan provides the details for
accomplishing the closure requirements included in the design. The plan needs to be specific to
the facility or site closure action, the characteristics of the site, and the residual wastes in the
deactivated facility. The plan should provide a discussion of applicable DOE, Federal, State, and
local closure requirements. A discussion of each activity to be performed during each phase of
the closure process, and the relationship between the activities to achieve the desired result of
minimum maintenance and long-term stability are to be provided. The methods for
accomplishing each of the closure activities are to be provided for each phase of the closure,
including those methods to be employed to minimize infiltration of water into the closed site and
the final landscape. As part of this discussion, the plan needs to explain how contaminant
migration will be controlled in the near-term and the long-term. A description of the cover
designs for the closed units and their intended performance is included. Features of the plan
which address the minimization of erosion by wind and water are also described, along with
features to prevent intrusion into the closed unit by plants and animals.
The closure plan includes a summary description of how the activities to be performed will place
the facility into a configuration which will allow the performance objectives identified (see
requirement in Section II.U.(3)(a)(3)) to be met in both the short-term and the long-term. The
schedule for completing facility closure accompanies this presentation. The schedule is to show
each phase of closure and the preparation and approval of related documents and permits, such
as the final assessment of projected performance, projected composite performance of all units to
be closed at the site, safety analysis report, RCRA permit, or State approvals.
Example: The closure plan for Facility X provides a crosswalk summary of the elements
of the facility closure to and the performance objectives for the closure of the facility.
Chapter II -High-Level Waste Requirements
II-198 DOE G 435.1-1
7-09-99
The relationship between each feature included in the closure plan and the
corresponding purpose of the feature with respect to the short-term and long-term
performance of the facility is explained. How the various elements of the closure plan
support minimizing the potential for the transport of contamination is provided. The
closure plan includes the schedule for the facility closure that includes milestones and
the steps for completing each step with dates of completion. The closure plan also lists,
as part of the schedule, all needed permits and documents as part of the closure.
Milestones are established for the completion of all documents and permits. The
schedule includes allowances for review and approval of all documents and permits.
Section 301
The closure plan also addresses corrective actions to be taken at each stage of the closure
process. For example, it includes the elements of an inspection program, the inspection methods
to be used, and the criteria to be used for initiating corrective actions. Specific corrective actions
should be included for the occurrence of subsidence or the indication of contaminant migration.
Other corrective actions to address potential issues such as uncontrolled facility or site access,
natural phenomena, failure of monitoring equipment, ponding of water or excessive infiltration,
erosion, or the presence of undesirable flora or fauna should also be included. The relationship
between corrective actions to ensure compliance with the performance objectives and the
monitoring program need to be clearly identified.
As required by Section II.U.(3)(a), each deactivated high-level waste facility or site, as defined in
this guidance, shall have a plan that is complete and approved, as specified by the requirements in
Sections I.2.F.(8) and I.2.E.(2), prior to physical closure activities. This requirement is intended
to reduce the risk of committing a significant amount of resources to a closure action before the
closure plan has been reviewed and approved by the appropriate levels of management. As
explained in the guidance to these two sections closure plans are expected to be two-tier
documents, i.e., their development and review/approval are expected to be conducted in two
phases. This multi-phase process is considered necessary because it is recognized that much of
the data needed to fulfill all the requirements in Section II.U.(3)(a) are not available initially, but
become available as engineering data and/or other documents/permits are developed. However,
Headquarters’ review and approval is primarily focused on the first tier plans from which
subsequent plans are developed.
The first tier plan, which is to be approved by the Deputy Assistant Secretaries for Waste
Management and/or Environmental Restoration (Section I.2.E.(2)), is intended to define and
bound the parameters of a closure action(s). This level of closure plan should include, at a
minimum, the following topics:
• closure methodology;
• schedules and assumptions;
• site or individual closure standards/performance objectives;
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-199
7-09-99
• allocation of closure standard/performance objective budgets to individual
facilities/sites;
• assessment (preliminary) of the projected performance of each unit to be closed
relative to the allocated performance objectives;
• assessment (preliminary) of the projected composite performance of all units to be
closed at the site;
• alternatives (if any);
• waste characterization data;
• closure controls plans; and
• stakeholder concerns.
While it is recognized that the availability of some of the above information may be limited and
therefore, preliminary, it is necessary to ensure that a credible, bounding review can be
conducted by DOE Headquarters.
Section 302
The second tier of the closure plan, which is to be approved by the Field Element Manager, or
designee, should provide the detailed information related to a specific unit or facility closure
action that is bounded by the analyses contained in the first tier plan. The lower tier closure
documentation should demonstrate that the performance objectives identified in the upper tier
documentation can be met and maintained. As explained in the guidance to Sections I.2.E.(2)
and I.2.F.(8), the first tier closure documentation should be approved by the Deputy Assistant
Secretaries for Waste Management and/or Environmental Restoration before remedial action
activities commence. However, design and field survey work can proceed prior to approval of a
closure plan, particularly in the case where the data are needed to support elements required in
the closure plan. Additionally, once the DOE Headquarters review/approval is gained on the
first tier documentation and an authorization to proceed is issued, additional DOE Headquarters
approvals are not required provided the bounding conditions defined in the approved first tier
plan are not exceeded.
Example: Site ZZ plans to close a cluster of deactivated high-level waste tanks and an
evaporator facility as a single closure unit. While detailed information concerning the
closure actions is not available because of the lack of engineering analysis and RCRA
permit discussions with the State, the Site prepares a first tier Interim Closure Plan that
bounds the expected closure conditions. This plan includes a closure methodology,
schedules and assumptions, identification of the closure site performance objectives (as
required by Section II.U.3.(a)1.), preliminary waste characterization data, a strategy for
apportioning the site performance objectives to each of the facilities within the site,
preliminary closure controls, and current stakeholder concerns. This Interim Closure
Plan for the site is submitted to the DOE Office of Environmental Management for
review and approval. Approval and authorization to proceed is gained and the Site
proceeds with the development of individual closure plans, development of assessments
Chapter II -High-Level Waste Requirements
II-200 DOE G 435.1-1
7-09-99
of the projected performance of each tank, and an assessment of the projected
composite performance of all the units within the closure unit. Further review and
approval by the DOE Office of Environmental Management is not required since the
analysis and assessments prepared as part of the second tier closure plan are bounded
by the DOE Office of Environmental Management-approved plan.
Once approved, closure plans are to be updated periodically, to reflect revised analysis and the
status of individual facility closure actions that are part of a site closure. The closure plan is a
living document that is updated through the operational life of the closure activities with specific
information about the contents and actions of interim closures and other information necessary
(e.g., monitoring locations) to support final closure. As discussed below, it is imperative that the
relationship between the analysis conducted in the assessment of the projected performance of
each unit (Section II.U.(3)(a)(3)) and the assessment of the projected composite performance of
all units (Section II.U.(3)(a)(4)) be kept in mind as the closure activities commence. Any
information that is incorporated into a closure plan or any changes made to the closure activities
of a facility that impacts the analysis in either of these assessments should be incorporated into
them as soon as possible so that the extent of their impact on the closure can be known and any
required changes can be made effective as soon as possible.
Section 303
Following is a brief discussion of each of the closure plan elements identified in Section
II.U.(3)(a)(1) through (5).
1. Identification of closure standards/performance objectives to be applied from Chapter III
or IV, as appropriate;
As discussed in the guidance to Section II.B., Waste Incidental to Reprocessing, residual waste
in deactivated high-level waste facilities that remains as part of the facility’s closure may be
managed as either low-level waste or transuranic waste. Following is a discussion on identifying
the appropriate radiological closure standards/performance objectives for each case.
Low-level waste. For deactivated high-level waste facilities or sites that are closed as low-level
waste sites, the disposal facility performance objectives in DOE M 435.1-1, Section IV.P.(1)
should be met. As discussed in guidance Section IV.P.(1), these performance objectives provide
criteria to be used in a disposal facility performance assessment that define the desired level of
protection of the public and the environment from disposed low-level waste. The analyses in the
performance assessment demonstrates there is a reasonable expectation that, when actually
measured, compliance with actual protection requirements will be easily achieved. A discussion
on the performance objectives can be found in Section IV.P.(1).
Transuranic waste. For deactivated high-level waste facilities or sites that are closed as
transuranic waste sites, the applicable performance objectives/requirements are contained in 40
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-201
7-09-99
CFR Part 191, Environmental Standards for the Management and Disposal of Spent Nuclear
Fuel, High-Level and Transuranic Radioactive Waste, as identified in the guidance to DOE M
435.1-1, Section III.P, Disposal. Within this regulation, Subpart B, Environmental Standards for
Disposal, contains the applicable requirements at 40 CFR 191.13, Containment Requirements;
191.14, Assurance Requirements; 191.15, Individual Protection Requirements; 191.16, Ground
Water Protection Requirements; and 191.17, Alternative Provisions for Disposal. The discussion
contained in guidance to Section III.P provides additional information on the applicability of 40
CFR Part 191 to the disposal of transuranic waste at a non-Waste Isolation Pilot Plant (WIPP)
site. As acknowledged in the guidance to Section III.P, DOE needs to develop 40 CFR Part 191
compliance criteria for the disposal of transuranic waste at sites, other than WIPP.
The term transuranic waste as used in the above discussion is consistent with the definition
provided in DOE M 435.1-1, Section III.A, Definition of Transuranic Waste. Therefore, residual
waste remaining in a deactivated high-level waste facility must meet the definition in Section
III.A in order for it to be closed as a transuranic waste disposal site. If, for example, the waste
meets one of the three exceptions included at Section III.A, it is not considered transuranic waste
under the closure requirements.
In addition to the radiological standards discussed above, there may be nonradiological air,
groundwater and surface-water standards that are applicable to the closure action. Identification
of such standards includes needs to be included during the development of a closure plan, and
included in the plan. These standards may include state and local, as well as other Federal
standards such as inorganic contaminant standards, contained in the Safe Drinking Water Act (40
CFR 141.62). To identify these standards, it is recommended that a performance standards
evaluation process, similar to the CERCLA criteria for the identification of ARARs, be
considered.
Section 304
2. A strategy for allocating waste disposal facility performance objectives from the closure
standards identified in the closure plan among the facilities/units to be closed at the site;
Included in the closure plan is the strategy/method for apportioning the performance
objectives/closure standards identified in Section II.U.(3)(a)(1) to each of the facilities/units to be
closed at the site. This strategy defines how facility or unit-specific performance objectives are,
or will be, established based upon the overall site performance objectives. The strategy or
methodology provides reasonable assurance that the overall performance objectives will not be
exceeded by either the summation of the individual facility closure actions or by future closure
activities. Additionally, the method recognizes that constituents of concern (radionuclides or
chemicals) from various facilities or areas may impact compliance points at different times due to
varying closure scenarios and geological conditions.
Chapter II -High-Level Waste Requirements
II-202 DOE G 435.1-1
7-09-99
The performance standards for the closure of a deactivated high-level waste facility are
concentration or dose limits for specific radiological or chemical constituents released to the
environment. These standards apply to various environmental media, at different points of
compliance, at various periods during or after closure.
Example: Site Z conducted a preliminary evaluation of the environmental pathways and
receptors for a deactivated high-level waste group (site) of tanks and determined that
groundwater was the limiting pathway for radionuclides and chemicals of concern to
impact receptors. Therefore, the strategy of apportioning performance objectives for
the closure of the site, and to be included in the closure plan, was applied to the
groundwater pathway only. This method involved the definition of a groundwater
transport segments (GTS), identification of high-level waste tank systems and other non-
tank sources in the GTS, apportionment of each source based on its contribution to total
impacts, and the development of adjusted and tank-specific performance objectives.
3. An assessment of the projected performance of each unit to be closed relative to the
performance objectives allocated to each unit under the closure plan;
With the allocation of overall performance objectives or closure standards to individual facilities,
an assessment of the projected performance of each facility or unit compared to these objectives
needs to be prepared. As discussed above, the residual material in a deactivated high-level waste
facility may be managed as either low-level waste or transuranic waste. Following is a discussion
on preparing an assessment of projected performance for each of these waste types.
Low-level waste. For deactivated high-level waste facilities or sites that are to be closed as
low-level waste sites, the requirements for a radiological performance assessment for low-level
waste disposal sites, in Section IV.P.(2) of DOE M 435.1-1, are to be met. As discussed in the
guidance to this section, the objectives of a performance assessment are to ensure that all aspects
of low-level waste disposal are evaluated in an assessment to provide reasonable assurance that
the performance objectives will be met. All of the elements of a low-level waste performance
assessment provided in the requirement in Section IV.P.(2) are considered appropriate for this
type of a deactivated high-level waste closure activity. The applicable review and approval
requirements for the closure plan, which includes an assessment of performance, are included in
Section I.2.E.(2). A complete discussion on the preparation of a low-level waste disposal facility
performance assessment can be found in the guidance to Section IV.P.(2).
Section 305
Transuranic waste. Deactivated high-level waste facilities or sites that are to be managed as
transuranic waste disposal sites must demonstrate compliance with 40 CFR Part 191. Details on
the criteria for reviewing and approving 40 CFR Part 191 performance assessments are included
in the guidance to Section III.P.
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-203
7-09-99
4. An assessment of the projected composite performance of all units to be closed at the site
relative to the performance objectives and closure standards identified in the closure plan;
With assessments of the projected performance of each facility or unit completed relative to the
performance objectives allocated to each unit (Section II.U.(3)(a)(3)), an assessment of the
projected composite performance of all the applicable units to be closed needs to be prepared.
The objective of such an assessment is to ensure that the potential dose to hypothetical members
of the public from the cumulative residual radioactive material that is likely to remain on a DOE
site is reasonably expected to not exceed the dose limits for protection of the public.
Low-level waste or transuranic waste disposal is not the only DOE activity that will leave
residual radioactive material on a DOE site when operations have ceased. Environmental
activities will be conducted to mitigate releases from former operations such as disposal of liquid
radioactive waste to soil columns, but will not generally result in the removal of all of the
radioactive material. Also facilities currently operating that involve the use of or handling of
radioactive material or radioactive waste will eventually be closed and their closure may leave
some residual radioactive material.
The assessment of the projected composite performance of all units/facilities to be closed at a
site that are relevant to the performance objectives/closure standards identified in a closure plan,
is considered a reasonably conservative assessment of the cumulative impacts from all the current
and planned closure facilities/units. The composite analysis provides a suggestion of what could
conceivably happen if DOE did not act to protect public health and safety and provides
information that DOE can use for planning. For example, the results of the composite analysis
can assist DOE in identifying those sources that most significantly contribute to the total
projected dose and decide on priorities for remediation, or decide on closure alternatives for
active or inactive closure sites. Hazard implications for some sources may be so low that little
needs to be done beyond land control, minor maintenance, and monitoring.
The requirements and guidance to DOE M 435.1-1, Section IV.P.(3), Composite Analysis,
provide additional information on the development of an assessment of composite performance.
Example: At Site X , deactivated high-level waste tanks and other high-level waste
contaminated facilities will be closed at various time over a period of decades. For
each closure action, in single facilities or groupings of facilities, the site identifies the
potential impacts from all sources that can contribute to the specific closure action by
identifying the limiting exposure pathways for the contamination to move. This is
accomplished by defining a groundwater transport segment (GTS) for the facility to be
closed and identifying and quantifying sources within the GTS. These sources include
the facilities or sites being closed, past contamination sites and closures, and future
closure sites that are known at the time. For this example these sites/sources include
Section 306
Chapter II -High-Level Waste Requirements
II-204 DOE G 435.1-1
7-09-99
closed seepage basins, a closed low-level waste disposal site, and a number of spill sites
that are not expected to be remediated.
In addition, the assessment of the projected performance of all units to be closed relative to the
closure plan needs to be reviewed and updated as appropriate to keep the analysis current. Such
updates should be performed to ensure the assumptions and parameters are appropriate to
maintain the validity and effectiveness of the controls that are applied to the closure site. The
guidance for DOE M 435.1-1, Section IV.P.(4), Performance Assessment and Composite
Analysis Maintenance, provides additional information on maintaining the composite analysis.
5. Any other relevant closure controls including a monitoring plan, institutional controls,
and land use limitations to be maintained in the closure activity.
The final required element of a closure plan is to include those closure controls that are needed
to ensure that the primary health and environmental protection requirements needed are put in
place. These controls are to include, at a minimum, a monitoring plan, institutional controls, and
limits of land use. Each of these is discussed below.
Monitoring Plan. The closure plan addresses the post closure activities to be undertaken to
ensure health and environment protection requirements are met. One of the elements that is
considered key is the development and implementation of a monitoring plan. Such a plan needs
to identify the monitoring activities that are to be conducted after the closure is completed. This
plan includes a location map of the monitoring wells or monitoring points that are considered
necessary, the data that are to be collected, and actions that will be taken in response to the
results of the monitoring activities. Also, the monitoring plan defines the inspection program and
the inspection methods to be used, and describes the criteria to be used for initiating corrective
actions. Specific corrective actions need to be included for the occurrence of subsidence or the
indication of contaminant migration. Other corrective actions to address potential issues, such as
uncontrolled site access, natural phenomena, failure of monitoring equipment, ponding of water
or excessive infiltration, erosion, or the presence of undesirable flora or fauna, need to be
included. The relationship between corrective actions and the monitoring program needs to be
clearly identified.
Example: At Site Z, a closure plan for the closure of a group of deactivated high-level
waste tanks includes: a map of the monitoring wells to be maintained over the
institutional control period after closure; sampling frequencies, sampling methods,
monitoring parameters, and methods of analysis for each monitoring well; the data
management methods, data analysis methods, data reporting and remedial action plan
associated with the monitoring wells for the closed site; and an inspection program that
provides criteria for inspecting and initiating corrective actions for the group of closed
tanks.
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-205
7-09-99
Institutional Controls and Land Use Limitations. The intent of this requirement is to ensure that
institutional control will continue at the closed site until it can be released and that local land use
records appropriately record the use of the land as a closed radioactive waste facility/site. These
actions provide additional protection against misuse of the land in the future and the possibility of
an inadvertent intrusion.
Section 307
Documentation of institutional control and land use assumptions for a closed facility or site that
is to be managed as a low-level waste disposal site should meet the requirements of DOE M
435.1-1, Section IV.Q.(2), paragraphs (c) and (d) and follow the corresponding guidance.
Similarly, closed facilities or sites that are to be managed as a transuranic waste disposal site are
to meet similar requirements. As with a low-level waste disposal site, the closure plan should
identify the necessary activities to be performed to ensure protection of public health and the
environment.
Compliance with these requirements is demonstrated by successful closure and supporting
documentation, e.g., decommissioning documentation, CERCLA documentation, or closure
plan, which provides a reasonable expectation that the proposed closure conditions will achieve
stability of the closed facility/site, reduce the need for active maintenance, and be protective of
worker and public health and the environment.
Supplemental References:
1. DOE, 1998. Life-Cycle Asset Management, DOE O 430.1A, U.S. Department of
Energy, October 14, 1998.
2. DOE, 1997. Decommissioning Implementation Guide, Draft DOE G 430.1-4, U.S.
Department of Energy, October 1, 1997.
3. DOE, 1996. Industrial Wastewater Closure Plan for F- and H-Area High-Level Waste
Tank Systems, Savannah River Site, ESH-CGP-96-0375, Revision 1, U.S. Department of
Energy, July 10, 1996.
4. DOE, 1997. Industrial Wastewater Closure Module for the High-Level Waste Tank 20
System, Savannah River Site, ESH-CGP-97-0003, Revision 1, U.S. Department of
Energy, January 8, 1997.
5. DOE, 1997. Guidance for Complying with DOE Order 5820.2A, “Radioactive Waste
Management,” for Onsite Management and Disposal of Low-Level Waste Resulting
from Environmental Restoration Activities, U.S. Department of Energy, Washington,
D.C., January 9, 1997. (Superseded by Guidance to DOE M 435.1-1, Section I.2.F.(5))
Chapter II -High-Level Waste Requirements
II-206 DOE G 435.1-1
7-09-99
6. DOE, 1996. Policy for Demonstrating Compliance with DOE Order 5820.2A for Onsite
Management and Disposal of Environmental Restoration Low-Level Wastes Under the
Comprehensive Environmental Response, Compensation, and Liability Act, U.S.
Department of Energy, May 31, 1996. (Superseded by Guidance to DOE M 435.1-1,
Section I.2.F.(5))
7. DOE, 1995. Decommissioning Resource Manual, DOE/EM-0246, U.S. Department of
Energy, Office of Environmental Management, August 1995.
8. Sullivan, 1998. M.A. Sullivan, DOE, to J.T. Greeves, USNRC, letter, Natural Resources
Defense Council Petition to Exercise Licensing Authority over Savannah River Site
High-Level Waste Tanks, U.S. Department of Energy, Washington, D.C., September 30,
1998.
9. DOE, 1985. An Evaluation of Commercial Repository Capacity for the Disposal of
Defense High-Level Waste, DOE/DP/0020/1, U.S. Department of Energy, Washington,
D.C., June 1985.
10. DOE, 1985. Secretary Hodel to President Reagan, memorandum, Use of Commercial
Repository for Disposal of Defense High-Level Nuclear Waste, U.S. Department of
Energy, Washington, D.C., February 6, 1985.
11. DOE, 1985. President Reagan to Secretary Herrington, memorandum, Disposal of
Defense Waste in a Commercial Repository, Washington, D.C., April 30, 1985.
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-207
7-09-99
II. V. Specific Operations.
Specific requirements are provided for the operation of lifting devices and facilities
for receipt and retrieval of high-level waste.
Section 308
(1) Operation of Lifting Devices. Hoisting and rigging activities shall be
conducted in accordance with the guidance provided in the DOE Standard
"Hoisting and Rigging” (DOE-STD-1090-96).
Objective:
The objective of this requirement is to ensure avoiding releases of high-level waste that could
result from dropping equipment, containers, or other objects that could damage high-level waste
containers and systems (e. g., transfer, pretreatment, treatment) during hoisting and lifting
operations.
Discussion:
The hazards analysis performed to guide development of DOE M 435.1-1 revealed that lifting
and rigging activities pose a high hazard for many high-level waste activities. In particular,
physical and chemical treatment of high-level waste in large storage tanks often involves the use
of large, heavy equipment such as mixers and dehydrators. Typically the access to the tanks is
through relatively small risers. Manipulation of loads in restricted spaces with the additional
complication of high radiation and reduced visibility due to the potential presence of confinement
huts, requires that precautions be taken to guard against dropping loads into and onto containers,
transfer equipment (e.g., pipelines, valves) and other systems containing high-level waste.
The existing DOE standard for hoisting and rigging, DOE-STD-1090-96, includes a section on
critical lift determinations (Sections 2.1) which is especially applicable to high-level waste
activities. The critical lift designation applies if collision, upset, or dropping could result in:
• Unacceptable risk of personnel injury or significant adverse health impact (onsite or
offsite);
• Significant release of radioactive or other hazardous material or other undesirable
conditions;
• Undetectable damage that would jeopardize future operations or the safety of a
facility; or
Chapter II -High-Level Waste Requirements
II-208 DOE G 435.1-1
7-09-99
• Damage that would result in unacceptable delay to schedule or other significant
program impact such as loss of vital data.
A lift needs to also be designated as critical if the load requires exceptional care in handling
because of size, weight, close-tolerance installation, high susceptibility to damage, or other
unusual factors.
Example: Transfers of liquid high-level waste among tanks is typically performed using
underground piping systems with pumps and valves located in below-grade transfer boxes
over which large shielding blocks are emplaced. Access to the pumps and valves requires
lifting the shielding blocks. The potential for personnel injury, release of radioactive
material, and delay in schedule or other significant program impact [including loss of
transfer capability as required by DOE M 435.1-1, Section II.H.(2)] if a shielding block
were dropped, renders lifts of these blocks subject to the critical lift provisions of DOE
STD-1090-96.
Requirements that apply to critical lifts appear in Section 2.2 of DOE-STD-1090-96. Included
are appointment of a person in charge; preparation of a pre-job plan or procedure; use of
experienced, trained, and qualified lift equipment operators; use of designated, qualified lift
operations signalers; review of the plan or procedure and rigging sketches prior to the lift; and
conduct of a pre-lift meeting to review and ask questions about the plan or procedure. The plan
or procedure is to include identification of the items to be moved and key characteristics, such as
size and weight, identification of the operating equipment to be used, and rigging sketches.
Section 309
Compliance with this requirement for lifting devices can be demonstrated by existence of formal
procedures for prior review of lifting activities to determine when the critical lift provisions of
DOE-STD-1090-96 are to be applied. The procedures should also identify those lifting devices
that are classified as safety-class or safety-significant. Procedures, programs, or other processes
are to be in place to ensure the implementation of these requirements when necessary.
Supplemental References:
1. DOE, 1996. Hoisting and Rigging, DOE STD 1090-96, U.S. Department of Energy,
Washington, D.C., September 1996 (a U.S. Department of Energy standard).
2. DOE, 1997. Safety Management System Guide, DOE G 450.4-1, U.S. Department of
Energy, Washington, DC, November 1997.
II. V.(2) Operation of Facilities for Receipt and Retrieval of High-Level
Waste. High-level waste receipt and retrieval systems shall be
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-209
7-09-99
operated and maintained consistent with high-level waste system
features incorporated in the facilities. Strategies for retrieval of
waste shall be analyzed to ensure that structural and radiological
impacts are consistent with the facility design basis.
Objective:
The objectives of this requirement are to ensure the proper retrieval strategy will be employed
for retrieval of high-level waste and to preserve the operability of design features for the safe
receipt and retrieval of waste.
Discussion:
The threat to losing the design capabilities and safety features of systems for the receipt and
retrieval of waste is very real given the long time period between design and installation of some
of these system components and the time when they will be used. An aggressive program is
necessary to continually ascertain the operability of system components and extend the service-
life of systems and components to meet operational requirements. Operability of the system and
components are threatened by budgetary and operational decisions. The assignment of
insufficient priority to maintain the operability of components and safety features, the use of a
retrieval strategy that is different from the design basis, and operation of systems by personnel
who are inexperienced or untrained are challenges that must be addressed. Therefore, the
essential components of systems for receipt and retrieval of waste, and their performance
requirements, should be identified, maintained and, wherever practicable, used during normal
operations. Similarly, wherever practical, procedures that will be used during receipt and
retrieval should be incorporated into normal operations. Such an approach is necessary to derive
confidence in the receipt and retrieval capabilities by demonstrating the operability of the
equipment and the competence of the operating personnel.
Maintaining the viability of the facilities for receipt and retrieval of waste which were designed
into the systems over the intervening time period between construction of the systems and that
point in time when they will be used requires an understanding of the degradation modes and
retrieval strategies that will be employed in the future and actions that must be employed to
preserve safe operability.
Section 310
This requirement is applicable to storage of high-level waste in the various stages of processing
as well as to the canistered waste form. Liquid high-level waste presents special problems of
retrieval, such as maintaining adequate knowledge of the content of the waste when it may be a
mixture received from many sources, and ensuring that most of the liquid can be removed from
the storage vessel for processing or for closure. Stored vitrified waste in metal canisters must
also be monitored during storage to ensure the canisters can be retrieved and moved.
Chapter II -High-Level Waste Requirements
II-210 DOE G 435.1-1
7-09-99
Implementation of this requirement must be coordinated with several other related requirements
of this Manual. DOE M 435.1-1, Section II.P.(2)(g) requires that the design of the systems be
based on the strategy selected for retrieval. Knowledge of that strategy is required to formulate
and implement an operations and maintenance program. Sections II.P.(2)(h) and II.Q.(1) outline
requirements for structural integrity. Finally, the receipt and retrieval features were designed to
be compatible with the general requirements for waste management including Worker Protection
(Section I.1.E.(21)), Radiation Protection (Section I.1.E.(13)) including maintaining exposures
as low as reasonably achievable, and Safeguards and Security (Section I.1.E.(16)). If strategies
other than the design basis strategy is planned for retrieval, an understanding of the impact of
using a different strategy on structural integrity and on radiation protection is imperative.
Example: Tank farm “C” at site XYZ was designed and constructed based on a retrieval
strategy involving the use of a robotic arm whose weight must be born by the tank
structure. The associated loads were included in the structural design requirements for
the tank as well as provisions for access. An integrated operations and maintenance
plan has been developed and implemented for the receipt and retrieval systems. The
integrated plan is focused on maintaining equipment and personnel operability to
execute the design basis retrieval strategy. The integrated plan documents the structural
and operational features included in the design to support the retrieval strategy. The
plan includes the structural integrity program requirements outlined in DOE M 435.1-1
at II.Q.(1), the waste acceptance requirements of Section II.L, the waste certification
requirements of II.M, and the radiation protection requirements of I.1.E, as they relate
to preserving the design basis operability of the retrieval systems. Procedures for
routine operations and maintenance, including transfer of waste, have been developed
to be consistent with procedures to execute the planned retrieval strategy and are
employed wherever practical
Compliance with this requirement can be demonstrated by developing and implementing an
integrated operations and maintenance program that includes the requirements of other relevant
sections of DOE M 435.1-1.
Supplemental References:
1. NRC. Packaging and Transportation of Radioactive Material, 10 CFR Part 71, U.S.
Nuclear Regulatory Commission, Washington, D.C.
2. USDOT. Shippers-General Requirements for Shipments and Packaging-Radioactive
Materials, 49 CFR Part 173, Subpart I., U.S. Department of Transportation,
Washington, D.C.
Chapter II -High-Level Waste Requirements
DOE G 435.1-1 II-211 (and 212)
7-09-99
Section 311
3. DOE, 1996. Packaging and Transportation Safety, DOE O 460.1A, U.S. Department of
Energy, Washington, D.C., October 2, 1996.
4. DOE, 1995. Departmental Materials Transportation and Packaging Management,
DOE O 460.2, U.S. Department of Energy, Washington, D.C., September 7, 1995.
Chapter II -High-Level Waste Requirements
IMPLEMENTATION
GUIDE
for use with DOE M 435.1-1
Chapter III
Transuranic Waste Requirements
(This page intentionally left blank.)
DOE G 435.1-1 III-1
7-09-99
III. A. Definition of Transuranic Waste.
Transuranic waste is radioactive waste containing more than 100 nanocuries (3700
becquerels) of alpha-emitting transuranic isotopes per gram of waste, with half-lives
greater than 20 years, except for:
(1) High-level radioactive waste;
(2) Waste that the Secretary of Energy has determined, with the concurrence of
the Administrator of the Environmental Protection Agency, does not need
the degree of isolation required by the 40 CFR Part 191 disposal regulations;
or
(3) Waste that the Nuclear Regulatory Commission has approved for disposal on
a case-by-case basis in accordance with 10 CFR Part 61.
Objective:
The objective of this requirement is to provide the criteria for determining if a waste is to be
managed in accordance with DOE M 435.1-1, Chapter III, Transuranic Waste Requirements.
Additionally, it is necessary to determine if a waste meets the definition of transuranic waste to
enable the Department of Energy to comply with provisions in the Waste Isolation Pilot Plant
Land Withdrawal Act of 1992, as amended.
Discussion:
Basis. This definition of transuranic waste is the definition used in the Waste Isolation Pilot
Plant (WIPP) Land Withdrawal Act of 1992, as amended. This definition is functionally
equivalent to that in 40 CFR Part 191, Environmental Radiation Protection Standards for
Management and Disposal of Spent Nuclear Fuel, High-Level and Transuranic Radioactive
Wastes. The WIPP Land Withdrawal Act of 1992, as amended, defines transuranic waste and
limits disposal at WIPP to transuranic waste resulting from atomic energy defense activities which
meets this definition.
Interpretation and Application. In order to ensure consistent application, various terms used in
the definition need to be clarified. First, the limit above which a waste is determined to be
transuranic waste is based on an activity of 100 nanocuries (nCi) (3700 becquerels (Bq)) per gram
of waste. The activity to be counted in making this determination is only that from the isotopes
that would qualify a waste as transuranic waste as described in the following paragraphs. In other
words, one would not include the activity from short-lived fission products (i.e., non-alpha
emitters with half-lives less than 20 years) in calculating the concentration. The mass over which
Chapter III - Transuranic Waste Requirements
III-2 DOE G 435.1-1
7-09-99
the activity is divided in making the waste determination is the waste matrix. This includes the
waste material itself as well as any stabilization media that must be added to meet waste
acceptance criteria for mobility, physical form, structural stability or free liquids. The mass of
added shielding, the container, or any rigid liners is not included in the calculation.
The term transuranic means those elements with an atomic number greater than that of uranium
(i.e., atomic number >92). Therefore, uranium wastes do not qualify as transuranic waste by
virtue of their uranium concentration.
Section 312
The transuranic radionuclides that are to be considered in making a transuranic waste
determination must decay by emission of alpha particles and also must have a half-life greater than
20 years. Consistent with this portion of the definition, there are radionuclides with atomic
numbers greater than 92 that would not cause a waste to be called transuranic waste.
Example: A waste is contaminated with americium-242 which predominantly decays by
emission of a beta particle and has a 16-hour half-life. Even though americium-242 has
an atomic number greater than 92, it cannot be considered in determining the waste type
because it is not an alpha emitter and does not have a 20-year half life.
Given the definition provided in the public law and its application pursuant to DOE M 435.1-1,
the determination of transuranic waste should be made at the time of waste certification, that is,
each time the waste is transferred to another person or facility (see guidance for DOE M 435.1-1,
Section III.J).
Example 1: A waste is contaminated with curium-244 which is an alpha-emitter and has
an atomic number greater than 92. Over a period of about 200 years, a sufficient
inventory of curium-244 will decay to greater than 100 nCi/g of plutonium-240, an alpha
emitter with a 6,750-year half-life. Regardless of the decay product, the curium-244
content of the waste is not relevant to the determination of whether the waste is
transuranic because the curium has an 18.11-year half-life and the determination is
made at the time the waste is certified as meeting a facility’s waste acceptance criteria.
However, even if the waste is determined to be a low-level waste, the method of disposal
must be commensurate with the long-term hazard associated with the plutonium-240
decay product.
Example 2: A waste is generated and placed in bags within 55-gallon drums. The waste
has been characterized and certified as transuranic waste in accordance with the waste
acceptance criteria of the facility receiving the waste. This same waste, if required to
undergo solidification to enable shipment and disposal, could be re-certified after
treatment by the treating facility as low-level waste, in the event that radioassay found
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-3
7-09-99
that the solidification process reduced the concentration of relevant radioisotopes to less
than 100 nCi (3700 Bq) per gram of waste matrix.
In the previous example, the waste form would be altered by the addition of solidifying agents that
would be considered in the radioassay. In either of the two cases in the previous example, the
determination would not consider the waste container or its rigid liner. Even if a waste container
fails and has to be overpacked, the mass of the failed container does not need to be included in the
transuranic waste determination.
Example: A 55-gallon drum is damaged, has leaked, and requires overpacking. The
concentration determination would include the weights of the original waste matrix and
interior bags, but not the weight of the failed drum.
It is also conceivable that a low-level waste could become sufficiently concentrated that it
becomes a transuranic waste.
Example: A waste with a relatively high concentration of transuranic radionuclides (but
less than 100 nCi (3700 Bq) per gram) is transferred to a treatment facility as low-level
waste. The thermal treatment of the waste reduces the mass of the waste matrix enough
that the resulting transuranic concentration exceeds 100 nCi (3700 Bq) per gram. If no
additional treatment (e.g., stabilization) were necessary, the resulting waste would be
categorized as transuranic waste.
Section 313
Determining whether waste exceeds the 100 nCi/g (3700 Bq/g) shall be in accordance with the
requirements and guidance issued by the Carlsbad Area Office in the Transuranic Waste
Characterization Quality Assurance Program Plan, Waste Acceptance Criteria for the Waste
Isolation Pilot Plant, and/or other controlling documents. Waste which does not exceed the 100
nCi/g limit is to be managed in accordance with the low-level waste requirements of DOE M
435.1-1.
Dilution of a transuranic waste stream to reclassify the waste as low-level waste (i.e., reducing the
concentration to less than or equal to 100 nCi (3700 Bq) per gram) is not permitted by the
Department. While it is recognized that in the course of stabilizing a waste stream some changes
in waste concentration may occur, actions to dilute a waste stream below the concentration limits
for transuranic waste are prohibited. It is also recognized that actions taken to process a waste
stream for safety or technological reasons that are justified, may result in the waste being
reclassified after processing as low-level waste.
Example: Due to the moisture content of a transuranic waste sludge, the waste does not
meet the WIPP WAC. The site evaluates several treatment options taking into
consideration factors such as worker exposure, waste minimization, cost and complexity
Chapter III - Transuranic Waste Requirements
III-4 DOE G 435.1-1
7-09-99
of the treatment process and disposal facility waste acceptance requirements. The
treatment process selected involves adding grout to the transuranic waste sludge to
eliminate free liquids resulting in a solidified waste form that contains transuranic
radionuclides in concentrations less than 100 nCi (3700 Bq) per gram and meets the
waste acceptance criteria for a low-level waste disposal facility.
There are three exceptions to the definition of transuranic waste: the high-level waste exception;
the degree of isolation exception; and the NRC-approved disposal exception.
High-Level Waste Exception. The definition of transuranic waste includes exceptions for some
wastes that would otherwise be considered transuranic waste. The first exception to the definition
of transuranic waste is waste that meets the definition of high-level waste (see Definition of High-
Level Waste guidance). Because high-level waste is generated by reprocessing spent nuclear fuel,
much high-level waste contains concentrations of greater than 100 nCi (3700 Bq) per gram alpha-
emitting radionuclides with half-lives greater than 20 years. Separate requirements apply to
management of high-level waste, both within and external to DOE. This exception serves to
distinguish high-level waste, as defined in DOE M 435.1-1, Chapter II, from transuranic waste.
Example: Waste in underground storage tanks at the Hanford Site contains long-lived,
alpha-emitting plutonium and neptunium isotopes in excess of 100 nCi (3700 Bq) per
gram. However, the waste is not categorized as transuranic waste because it is highly
radioactive waste from reprocessing spent nuclear fuel; i.e., it is high-level waste.
Degree of Isolation Exception. The second exception to the definition of transuranic waste is
waste that is determined to not need the degree of isolation that is provided by implementation of
the disposal requirements of 40 CFR Part 191. This allows the Secretary of Energy to make a
determination to remove these wastes from the transuranic waste definition based on an
evaluation of a proposed disposal concept. Such a determination would have to be submitted to
and concurred with by the EPA Administrator.
Section 314
Example: A site is contemplating on-site disposal of a small quantity of a unique waste
contaminated with greater than 100 nCi (3700 Bq) per gram of transuranic
alpha-emitters with greater than 20-year half-lives. Site personnel submit a rationale for
applying standards other than those for transuranic waste disposal, a conceptual
disposal design, and a preliminary radiological impacts analysis to the cognizant
Headquarters Program Office. The Program Office confers with the Offices of
Environmental Management and Environment, Safety, and Health on the proposal. The
Headquarters staff agrees with the site’s approach, so the Office of Environment, Safety,
and Health arranges a meeting with the Environmental Protection Agency. The meeting
results in an agreement on the analyses that need to be conducted and the radiological
performance measures that apply. Site personnel conduct the analyses, which project
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-5
7-09-99
that the performance measures will be met. The analyses are reviewed by Headquarters
staff, then by EPA staff. Following resolution of any concerns, the Secretary of Energy
determines, and the EPA Administrator concurs, that the waste does not need to be
considered transuranic waste, but can be disposed of as low-level waste.
NRC-Approved Disposal Exception. Under the current regulatory regime, this exception does
not affect DOE’s management of defense transuranic waste that is to be disposed of at WIPP.
This exception gives the Nuclear Regulatory Commissioning (NRC) the latitude to not apply the
disposal standards of 40 CFR Part 191 to waste which meets the concentration limits of
transuranic waste if the waste is disposed of in an NRC-licensed facility. Waste generated by
commercial activities could have concentrations of radionuclides that would result in
categorization as transuranic waste. As long as the waste is not high-level waste, it could be
accepted as Greater-than-Class-C low-level waste per the waste classification system in 10 CFR
61.55. In accordance with the Low-Level Radioactive Waste Policy Act, as amended, the
Department is responsible for disposal of Greater-than-Class-C waste; however, disposal of
Greater-than-Class C waste generated by an NRC licensee is to be in a facility licensed by the
NRC.
The NRC issued a final rule requiring the disposal of Greater-than-Class C low-level radioactive
waste in a geologic repository, unless disposal has been approved elsewhere (54 FR 22578,
codified at 10 CFR Part 61). The rulemaking clarified that only the requirements governing
disposal of high-level radioactive waste in geologic repositories (10 CFR Part 60) would be
relevant to disposal of Greater-than-Class C waste in a geologic repository. Although the NRC
has indicated that the disposal of Greater-than-Class C waste in near-surface disposal facilities is
generally not acceptable, the requirements of 10 CFR Part 61 would be applicable to the disposal
of commercially generated (NRC licensed) Greater-than-Class C waste in “intermediate” disposal
facilities. The exception to the definition allows NRC to authorize such waste to be disposed
without necessarily invoking the additional requirements of 40 CFR Part 191.
Supplemental References:
1. Cowan, 1996. Stephen P. Cowan to Distribution, memorandum, Implementation
Guidance Concerning “Atomic Energy Defense Activities” as Used in the Waste
Isolation Pilot Plant Land Withdrawal Act, U.S. Department of Energy, October 17,
1996.
Section 315
2. NRC. Disposal of High-Level Radioactive Wastes in Geologic Repositories, 10 CFR
Part 60, U.S. Nuclear Regulatory Commission, Washington, D.C.
3. NRC. Licensing Requirements for Land Disposal of Radioactive Waste, 10 CFR Part 61.
U.S. Nuclear Regulatory Commission, Washington, D.C.
Chapter III - Transuranic Waste Requirements
III-6 DOE G 435.1-1
7-09-99
4. Waste Isolation Pilot Plant Land Withdrawal Act of 1992, as amended, October 30, 1992.
5. Low-Level Radioactive Waste Policy Amendments Act of 1985, as amended, January 15,
1986.
6. CAO, 1998. U.S. Department of Energy, Transuranic Waste Characterization Quality
Assurance Program Plan, Revision 1, CAO-94-1010, U.S. Department of Energy,
Carlsbad Area Office, Carlsbad, NM, December 18, 1998.
7. CAO, 1996. Waste Acceptance Criteria for the Waste Isolation Pilot Plant, Revision 5,
DOE/WIPP-069, U.S. Department of Energy, Carlsbad Area Office, Carlsbad, NM, April
1996.
8. NRC, 1989. “Final rule, 10 CFR Part 61, Disposal of Radioactive Waste,” Federal
Register, Vol. 54, No. 100, U.S. Nuclear Regulatory Commission, Washington, D.C.,
May 25, 1989.
9. EPA, 1985. “Final rule, 40 CFR Part 191, Environmental Radiation Protection Standards
for Management and Disposal of Spent Nuclear Fuel, High-Level and Transuranic
Radioactive Wastes,” Federal Register, Vol. 50, No. 182, U.S. Environmental Protection
Agency, Washington, D.C., September 19, 1985.
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-7
7-09-99
III. B. Management of Specific Wastes.
The following provide for management of specific wastes as transuranic waste in
accordance with the requirements in this Chapter:
(1) Mixed Transuranic Waste. Transuranic waste determined to contain both a
hazardous component subject to the Resource Conservation and Recovery Act
(RCRA), as amended, and a radioactive component subject to the Atomic
Energy Act of 1954, as amended, shall be managed in accordance with the
requirements of RCRA and DOE O 435.1, Radioactive Waste Management,
and this Manual.
(2) TSCA-Regulated Waste. Transuranic waste containing polychlorinated
biphenyls, asbestos, or other such regulated toxic components shall be
managed in accordance with requirements derived from the Toxic Substances
Control Act, as amended, DOE O 435.1, Radioactive Waste Management, and
this Manual.
(3) Pre-1970 Transuranic Waste. Transuranic waste disposed of prior to
implementation of the 1970 Atomic Energy Commission Immediate Action
Directive regarding retrievable storage of transuranic waste is not subject to
the requirements of DOE O 435.1, Radioactive Waste Management, and this
Manual.
Objective:
The objective of this requirement is to ensure that DOE transuranic waste is managed in
accordance with the applicable requirements of external regulations, specifically those of the
Resource Conservation and Recovery Act and the Toxic Substances Control Act, that address
non-radiological hazards, in addition to being managed in accordance with the requirements of
DOE O 435.1 and the Radioactive Waste Management Manual, DOE M 435.1-1.
Discussion:
The Radioactive Waste Management Manual, DOE M 435.1-1, contains requirements for
managing the radioactive character of transuranic waste. Through the safety and hazards analysis
process used in developing the Manual, non-radiological hazards associated with managing
certain wastes were identified. During development of the requirements necessary to control the
identified hazards, it was concluded that sufficient external regulations, promulgated pursuant to
Resource Conservation and Recovery Act (RCRA) and Toxic Substances Control Act (TSCA),
exist for controlling the non-radiological hazard.
Section 316
Chapter III - Transuranic Waste Requirements
III-8 DOE G 435.1-1
7-09-99
In managing transuranic waste which are subject to RCRA and TSCA requirements, personnel
should be aware of the requirements for storage and disposal of the waste. The ability to dispose
of RCRA and TSCA waste that has a radioactive component is limited. The expectation is that
certain mixed wastes can be disposed of at WIPP without treatment (refer to the Waste
Acceptance Criteria for the Waste Isolation Pilot Plant). Currently, no disposal facilities are
available for TSCA-regulated transuranic wastes. Therefore, to the extent practical, waste
generators should avoid generating mixed or TSCA-regulated transuranic waste, and generators
and waste managers should avoid actions (e.g., commingling wastes with different regulatory
requirements) that result in transuranic waste with no path to disposal (see guidance for DOE M
435.1-1, Section I.2.F.(19)).
Example: According to the Waste Acceptance Criteria for the Waste Isolation Pilot
Plant, PCBs in concentrations greater than 50 ppm cannot be accepted for disposal.
Therefore, in performing work involving PCBs (e.g., activities creating waste or waste
management such as packaging) care should be taken to avoid commingling PCB
contaminated materials with transuranic or mixed transuranic waste. Commingling the
wastes could potentially result in a larger volume of waste with no path to disposal.
Careful control and segregation of the PCB-contaminated material would result in a
relatively small volume of waste that cannot be disposed of and the rest of the waste
being eligible for disposal at WIPP.
RCRA and State Hazardous Waste Regulations. Resource Conservation and Recovery Act
required the Environmental Protection Agency to promulgate regulations for management of
hazardous waste. The Act also provides for states to promulgate and implement hazardous waste
regulatory programs that are at least as protective as the Federal program. The hazardous waste
requirements that personnel must follow in managing (i.e., generating, transporting, treating,
storing or disposing) mixed transuranic waste and in closing affected facilities are primarily in 40
CFR Parts 260 through 270, or authorized state regulations. A variety of guidance manuals and
information relevant to the management of the hazardous component of mixed transuranic waste
has been prepared both by the state regulatory agencies and the Environmental Protection Agency
(see, for example, U.S. Environmental Protection Agency, Catalog of Hazardous and Solid
Waste Publications, EPA530-B-96-007, September, 1996). These guidance documents should
be consulted when developing management programs for mixed transuranic waste.
Hazardous waste regulations promulgated by States with RCRA authority may be more restrictive
than the Federal regulations. The more restrictive requirements may include more waste than the
Federal requirements or may impose another state’s definition of hazardous waste when waste is
received from that state. Waste management personnel therefore need to be aware of the
requirements of the regulations in their own state as well as the implications of the regulations in
states to which they intend to transfer waste.
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-9
7-09-99
Section 317
Example 1: In a state that invokes requirements equivalent to the EPA hazardous waste
regulations, waste oil that meets the radiological criteria for being transuranic waste
would not be managed as mixed waste. However, if the oil was to be shipped to another
state in which the state-passed regulations had expanded the definition of hazardous
waste to include waste oil, the waste would have to be packaged, manifested, transported
and stored as a mixed waste.
Example 2: If the direction of waste transfer in the above example were reversed, a
different situation could arise. The waste would be declared a mixed waste in the state of
origin because the state regulations had a broader definition of hazardous waste. The
state to which it was to be shipped did not specifically regulate waste oil as a hazardous
waste. However, it may be that the state regulations require that waste be considered to
be categorized as it was in the state of origin. Then the waste would still be considered
mixed waste even after it was shipped to the state that did not explicitly regulate waste
oils.
The RCRA requirements prohibit storage of hazardous (including mixed) waste restricted from
land disposal except for purposes of accumulating sufficient quantities to facilitate recovery,
treatment, or disposal. Capabilities and capacities to treat DOE mixed waste to the land disposal
restriction treatment standards do not exist. Congress addressed this issue in 1992 with passage
of the Federal Facility Compliance Act of 1992 (FFCA). The FFCA required the Department to
prepare site-specific treatment plans to address treatment of mixed waste to meet the land
disposal restrictions at each facility at which DOE generates or stores mixed waste. To meet the
requirement, site-specific treatment plans were developed, and through agreements or consent
orders, commitments to schedules to treat or otherwise meet the land disposal restrictions were
made. In accordance with the WIPP Land Withdrawal Act of 1992, as amended, transuranic
mixed waste that is to be disposed at the Waste Isolation Pilot Plant (WIPP) is exempt from
having to comply with the treatment standards and is not subject to the land disposal restrictions
of 40 CFR Part 268. Therefore, management of most of the transuranic waste addressed in the
agreements or consent orders is predicated on the assumption that mixed transuranic waste will be
disposed at WIPP without treatment. Waste that is not eligible for disposal at WIPP, i.e., waste
that cannot meet the Waste Acceptance Criteria for the Waste Isolation Pilot Plant, must comply
with RCRA treatment and disposal requirements, the Federal Facility Compliance Act of 1992,
and consent orders and agreements with the States or EPA. This highlights the importance of
avoiding actions in generating or managing waste that result in a waste not being acceptable for
disposal at WIPP. Personnel should consult the site-specific treatment plans and agreements or
consent orders as part of the life-cycle planning performed in accordance with Waste Generation
Planning (DOE M 435.1-1, Section III.H).
PCB, Asbestos, and Other TSCA Wastes. Transuranic wastes contaminated with PCBs do not
meet the definition of mixed waste, however, the situation is similar to RCRA in that there are
Chapter III - Transuranic Waste Requirements
III-10 DOE G 435.1-1
7-09-99
Section 318
external requirements promulgated under the authority of the Toxic Substances Control Act that
need to be complied with in addition to the requirements of DOE O 435.1 and DOE M 435.1-1.
Waste managers responsible for managing PCB-containing products should consult the EPA
requirements at 40 CFR Part 761. The regulations impose requirements for the destruction,
storage awaiting destruction, and disposal of PCBs. Unlike mixed wastes, there are no provisions
to accommodate PCBs (exceeding 50 ppm) at WIPP. If transuranic waste contaminated with
PCBs cannot be treated to reduce the PCB concentration to less than 50 ppm, then it is one of the
wastes that currently has no path to disposal (see General Requirements, Section I.2.F.(19)).
Waste managers responsible for managing materials containing asbestos should consult the EPA
requirements at 40 CFR Part 61, Subpart M. These regulations impose requirements for the
removal of asbestos during demolition and renovation and disposal of asbestos-containing waste.
This regulation includes cross-references to several other regulations governing management of
asbestos that may also apply. Planning for management of transuranic wastes that include a
component which is regulated under TSCA is addressed in the Complex-Wide Transuranic Waste
Management Program and the appropriate Site-Wide Waste Management Programs (see
DOE M 435.1-1, Sections I.2.B.(1) and I.2.F.(1)).
The DOE M 435.1-1 requirements imposed on the radioactive component of RCRA or TSCA
waste should not create a duplication of management activities that can be satisfied by compliance
with a RCRA or TSCA requirement. Also, documentation required by RCRA or TSCA
requirements which provides the same or similar information as required by DOE M 435.1-1 can
be used to satisfy the DOE M 435.1-1 requirement.
Example: Mixed transuranic waste is being sent from one site to another for storage.
The Uniform Hazardous Waste Manifest is prepared as required by 40 CFR Part 262. It
is determined that the manifest satisfies the need to document the transfer of ownership
of the waste, the transfer date, and physical location of the waste. If the waste
acceptance requirements of the facility receiving the waste allow it, the manifest may also
provide the necessary information on the chemical and physical characteristics of the
waste.
Compliance with these requirements is demonstrated if RCRA, state-hazardous, and TSCA-
regulated radioactive wastes are being managed in compliance with applicable requirements and
agreements or in accordance with a consent order, and consistent with the Transuranic Waste
Requirements of DOE M 435.1-1.
Pre-1970 Transuranic Waste. A definition for transuranic waste was first put into operational use
by the Department’s predecessor in 1970. At that time, the decision was made to store waste
exceeding the transuranic waste limit. Waste disposed of prior to implementation of the 1970
Atomic Energy Commission Immediate Action Directive regarding retrievable storage of
transuranic waste is not subject to the requirements of the Radioactive Waste Management
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-11
7-09-99
Section 319
Manual. This interpretation is consistent with the decision of the Environmental Protection
Agency as documented in the preamble to 40 CFR Part 191 (50 FR 38066). The Agency stated
that the disposal standards do not apply to transuranic waste that already has been disposed of
because the selection of disposal system site, design, and operational techniques are no longer
available options. Therefore, “the Agency believes it appropriate that these disposal standards
only apply to disposal occurring after the standards have been promulgated.” Transuranic waste
consists of waste generated by DOE activities that has been placed in retrievable storage since
1970, and waste that will continue to be generated as a result of plutonium stabilization and
management activities, environmental restoration (including remediation of some sites where
transuranic waste was previously buried), decontamination and decommissioning, waste
management, and testing and research. Transuranic waste that was disposed of prior to 1970,
retrieved as part of environmental restoration activities, may be managed in accordance with the
requirements of the Radioactive Waste Management Manual.
Supplemental References:
1. EPA. 40 CFR Parts 260-270, U.S. Environmental Protection Agency, Washington, D.C.
2. EPA. Polychlorinated Biphenyls (PCBs) Manufacturing, Processing, Distribution in
Commerce, and Use Prohibitions, 40 CFR Part 761, U.S. Environmental Protection
Agency, Washington, DC.
3. CAO, 1996. Waste Acceptance Criteria for the Waste Isolation Pilot Plant, Revision 5,
DOE/WIPP-069, U.S. Department of Energy, Carlsbad Area Office, Carlsbad, NM, April
1996.
4. EPA, 1996. U.S. Environmental Protection Agency Catalog of Hazardous and Solid
Waste Publications, EPA530-B-96-007, U.S. Environmental Protection Agency,
Washington, D.C., September 1996.
5. Federal Facility Compliance Act of 1992, as amended, October 6, 1992.
6. Resource Conservation and Recovery Act of 1976, as amended, October 21, 1986.
7. Toxic Substances Control Act, as amended, October 11, 1976.
8. EPA, 1973. National Emission Standards for Hazardous Air Pollutants – National
Emission Standard for Asbestos, 40 CFR Part 61, Subpart M, U.S. Environmental
Protection Agency, Washington, D.C., April 6, 1973.
Chapter III - Transuranic Waste Requirements
III-12 DOE G 435.1-1
7-09-99
9. AEC, 1970. Policy Statement Regarding Solid Waste Burial, Immediate Action
Directive, IAD No. 0511-21, U.S. Atomic Energy Commission, Washington, D.C., March
20, 1970.
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-13
7-09-99
III. C. Complex-Wide Transuranic Waste Management Program.
A complex-wide program and plan shall be developed as described under
Responsibilities, 2.B and 2.D, in Chapter I of this Manual.
Objective:
The objective of this requirement is to ensure the development, documentation, and
implementation of a complex-wide transuranic waste management program. The complex-wide
program and plan establishes the framework within which individual site programs operate.
Discussion:
Section 320
The Department’s management of transuranic waste occurs at over 15 sites that generate and
store waste, as well as at the Waste Isolation Pilot Plant which is to serve as the central repository
for most of the waste. A complex-wide program and plan establish the overall mission for the
Department’s management of transuranic waste and to provide a framework within which the
individual site programs operate. The Radioactive Waste Management Manual, DOE M 435.1-1,
Section I.2.B assigns the Assistant Secretary for Environmental Management the responsibility for
developing and maintaining complex-wide, waste-type programs. The Manual, DOE M 435.1-1,
Section I.2.D also assigns the Deputy Assistant Secretary for Waste Management the
responsibility for developing and implementing complex-wide, waste-type program plans. The
Complex-Wide Transuranic Waste Management Program and Plan are to be developed following
the guidance provided for DOE M 435.1-1, Sections I.2.B and I.2.D.
Compliance with this requirement is demonstrated by the presence of a Complex-Wide
Transuranic Waste Management Program which includes the appropriate interfaces, technical
information, data inputs, and other elements described in Chapter I of this Manual.
Supplemental References:
1. CAO, 1997. The National TRU Waste Management Plan, Revision 1, DOE/NTP-96
1204, U.S. Department of Energy, Carlsbad Area Office, Carlsbad, NM, December 18,
1997.
Chapter III - Transuranic Waste Requirements
III-14 DOE G 435.1-1
7-09-99
III. D. Radioactive Waste Management Basis.
Transuranic waste facilities, operations, and activities shall have a radioactive waste
management basis consisting of physical and administrative controls to ensure the
protection of workers, the public, and the environment. The following specific waste
management controls shall be part of the radioactive waste management basis:
(1) Generators. The waste certification program.
(2) Treatment Facilities. The waste acceptance requirements and the waste
certification program.
(3) Storage Facilities. The waste acceptance requirements and the waste
certification program.
(4) Disposal Facilities. The performance assessment, disposal authorization
statement, waste acceptance requirements, and monitoring plan.
Objective:
The objective of this requirement is to ensure that the hazards associated with transuranic waste
management facilities, operations, and activities have been identified, their potential impacts
analyzed, and appropriate controls documented, implemented, and maintained for the protection
of workers, the public, and the environment.
Discussion:
As described in the guidance for DOE M 435.1-1, Section I.2.F.(2), the Manual requires the
radioactive waste management basis to provide for development and documentation of controls to
ensure the safe and efficient management of radioactive waste. Requiring an approved radioactive
waste management basis for the initiation of new, or continuation of existing, radioactive waste
management activities should prevent the operation of facilities without the appropriate controls.
The required elements of the radioactive waste management basis vary with the type of waste
management operation or facility and the types of hazards associated with the facility. The term
“controls,” used here and elsewhere in the discussion of a radioactive waste management basis,
refers to processes, procedures, equipment, instruments, and other items intended to curb the
likelihood of, or consequences from, a problem that could arise from managing radioactive waste.
Controls include such things as placards, alarms, tools, shielding, training, checklists, duplication
of critical steps, redundant monitoring, analysis, sampling and testing, etc. The items required for
a radioactive waste management basis listed above for the four types of transuranic waste
management facilities, operations, and activities is not a complete list of those items which should
Section 321
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-15
7-09-99
be included in a radioactive waste management basis. Several processes, procedures, and
documents that are required by other directives and requirements provide for radioactive waste
management controls that should be considered part of the radioactive waste management basis.
The guidance on DOE M 435.1-1, Section I.2.F.(2) discusses this aspect of the radioactive waste
management basis in detail.
Example: Site X has a transuranic waste storage facility in which they store waste to be
shipped to the Waste Isolation Pilot Plant. The Field Element Manager is responsible
for ensuring that it operates in accordance with an approved radioactive waste
management basis. The DOE staff reviews the waste acceptance requirements, the
storage facility’s waste certification program, plus the facility-specific procedures
implementing the site's radiological control program, health and safety plan, training
program, quality assurance program, and record-keeping plan. Based on the staff’s
review, they report to the Field Element Manager that an adequate radioactive waste
management basis has been developed and recommend approval.
Also, as discussed in the Section I.2.F.(2) guidance, if a transuranic waste management facility
already operates under an approved Authorization Basis, it may not need any additional controls
to demonstrate that it has a radioactive waste management basis. In this case, the Authorization
Basis documentation is reviewed and evaluated to determine whether it sufficiently covers the
requirements needed for a radioactive waste management basis. The Field Element Manager has
the responsibility to ensure the transuranic waste management facilities under his or her authority
have a radioactive waste management basis.
Example: Site personnel are developing the radioactive waste management basis for the
Site Q Transuranic Waste Management Facility which provides non-destructive
characterization, selected treatment and repackaging, and storage capabilities for
transuranic waste. The site personnel identify the following documents and programs
which include descriptions of the controls for safely managing waste at the facility:
C Radiological Control Program
C Site Health and Safety Plan
C Safety Analysis Report (SAR)
C Operational Safety Requirements/Technical Safety Requirements
C Basis for Interim Operations
C Technical Standards
C Unreviewed Safety Questions Evaluation
C DOE Safety Evaluation Report
C Listing of documents that are to be Configuration Managed but are not
Authorization Basis Documents (including the waste acceptance criteria
and certification program documents).
Chapter III - Transuranic Waste Requirements
III-16 DOE G 435.1-1
7-09-99
Following an analysis of the information contained in the above documents, the staff
concludes that the complete set of operational requirements relied on by the site to
ensure that the public, workers, and the environment are protected from hazards
associated with management of transuranic waste at the facility are in place. A
statement is prepared that documents that the radioactive waste management basis is
covered by the Authorization Basis for the facility.
Section 322
For a facility that generates transuranic waste, the radioactive waste management basis is to
include the program for certifying that waste meets the waste acceptance requirements of the
facility(ies) to which the waste will be sent. The waste certification program is reviewed against
the applicable requirements of DOE M 435.1-1 and approved in accordance with the Radioactive
Waste Generator Requirements (DOE M 435.1-1, Section I.2.F.(7)) before becoming part of the
radioactive waste management basis. As discussed in guidance on DOE M 435.1-1, Section
I.2.F.(2), several other processes and procedures contribute to a complete radioactive waste
management basis at a generating facility.
Example: A small laboratory facility at Site R generates transuranic waste. The
radioactive waste management basis for the facility is established through review and
approval of the laboratory’s waste certification procedure, and a review confirming the
adequacy of the following: the Radiological Control Program, the Health and Safety
Plan, the Training Program, and the site waste transfer procedure. This is documented
in a radioactive waste management basis statement for the laboratory.
Facilities that store or treat transuranic waste are to have approved waste acceptance
requirements (see DOE M 435.1-1, Section III.G) prior to the issuance of a radioactive waste
management basis. The waste acceptance requirements will usually suffice as documentation of
the radiological, physical, and chemical limitations on waste that can be safely received at the
facility, provided they are developed correctly with consideration of the hazards of the waste to
be managed, and are kept up to date. Controls on the radiological, physical and chemical
limitations need to include considerations of the potential effects of radiolysis.
A facility that stores or treats waste is generally expected to have a waste certification program.
Waste from these facilities will have to be certified as meeting the waste acceptance requirements
of the facility to which it will be transferred and the facilities have the potential for generating
radioactive waste (e.g., secondary processing streams from treatment, monitoring and sampling,
radioactive release cleanup). Consequently, storage and treatment facilities should also have an
approved waste certification program as part of their radioactive waste management basis. An
exception to the need for a waste certification program can be justified based on there being no
known path to disposal for the waste or based on the expectation that a long time will elapse
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-17
7-09-99
(e.g., more than a year) before the certification program has been reviewed and accepted by the
receiving facility.
Example: A transuranic waste storage facility is used for storing defense transuranic
waste that will be shipped to the Waste Isolation Pilot Plant and non-defense transuranic
waste. According to the schedule for receipt of waste at WIPP, shipments from the site
will not occur for six years. The certification program for the defense waste is not
scheduled to be reviewed by WIPP for two years. Because there is no disposal facility to
which the non-defense waste can be sent, it is not possible for the storage facility to
develop a certification program for that waste (i.e., there are no waste acceptance
requirements for a disposal facility to which waste can be certified). The Field Element
Manager should proceed with ensuring the development of and approving a radioactive
waste management basis for the facility even though fully authorized certification
programs do not exist. In this case, an interim certification program for the defense
waste may be included as part of the radioactive waste management basis (interim
because it has not been reviewed by WIPP personnel). The radioactive waste
management basis would be updated after the certification program is reviewed and
accepted by WIPP personnel.
Section 323
The radioactive waste management basis for transuranic waste disposal facilities is to be based on
documented controls similar to those discussed for treatment or storage facilities, but with
additional limitations based on the performance assessment required by 40 CFR Part 191 and any
conditions associated with authorizing operation of the facility (e.g, the conditions of compliance
certification resulting from the Environmental Protection Agency review of DOE’s compliance
certification application per 40 CFR Part 194) and by the disposal authorization statement issued
following approval of the performance assessment. In addition, the radioactive waste
management basis should include the development and implementation of a monitoring program
designed to evaluate performance of the facility (see guidance for DOE M 435.1-1, Section
III.Q).
The results of the 40 CFR Part 191 performance assessment and the safety analyses required by
DOE 5480.23 provide the basis on which the quantities and concentrations of radionuclides that
can be accepted for disposal will be identified and documented in the waste acceptance
requirements. The responsibility for the radioactive waste management basis for transuranic
waste disposal facilities resides with the Field Element Manager. However, a review may be
required by another organization before the issuance and documentation of the radioactive waste
management basis. In the case of the Waste Isolation Pilot Plant, the review was performed by
the Environmental Protection Agency and was documented in a compliance certification. If
another transuranic waste disposal facility is constructed, a performance assessment will need to
be prepared. Review of the performance assessment will be in accordance with either external
Chapter III - Transuranic Waste Requirements
III-18 DOE G 435.1-1
7-09-99
requirements (if regulations similar to those for WIPP certification are promulgated) or a process
imposed by the Department.
Staff responsible for establishing a disposal facility radioactive waste management basis should
combine the results of the review of the performance assessment (and compliance certification
application if applicable) with their own findings on the waste acceptance requirements and
monitoring plans as the basis for documenting the radioactive waste management basis for the
disposal facility. Guidance for DOE M 435.1-1 Sections III.G (waste acceptance requirements)
and III.Q (monitoring) provides details on what information needs to be addressed to meet the
requirements and serve as part of the radioactive waste management basis.
For transuranic waste disposal facilities other than WIPP, a disposal authorization statement is to
be issued by Headquarters following the review and approval of the performance assessment as
required by DOE M 435.1-1, Section I.2.E.(1). The Waste Isolation Pilot Plant met the
requirement for a disposal authorization statement when the Secretary of Energy provided
notification to Congress that the Department of Energy would open WIPP for disposal operations
pursuant to section 7(b)(3) of the Waste Isolation Pilot Plant Land Withdrawal Act of 1992, as
amended. In the notification, the Secretary determined that the Waste Isolation Pilot Plant was in
compliance with all requirements of section 9(a)(1) of the Waste Isolation Pilot Plant Land
Withdrawal Act of 1992, as amended.
Section 324
Contents of a Disposal Authorization Statement. The disposal authorization statement will clearly
indicate the transuranic waste disposal facility and design that is being authorized to operate. The
statement will refer to the performance assessment reviewed as the basis for the authorization and
state the primary features of the disposal facility important for understanding the authorization of
operations of the facility. Conditions and limitations for operations of the facility are clearly
indicated in the disposal authorization statement. These include quantities, limitations, references,
or codification of assumptions contained in the performance assessment. The conditions include
any limitations or allowances required based on independent analysis of the disposal configuration
and conditions being examined in the evaluations. The conditions also include any other
limitations, responsibilities, or commitments that were needed to resolve issues during the review
of the performance assessment or which will serve to answer questions that need to be resolved
during the first years of operation of the disposal facility.
As part of the radioactive waste management basis, site personnel should implement a system or
process for tracking the waste inventory at a storage, treatment, or disposal facility. Tracking the
waste inventory is a means of ensuring that radionuclide limits established in accordance with a
safety analysis or performance assessment will not be exceeded. In addition, a system or process
for accurately tracking waste received at a facility can facilitate providing information to the
complex-wide management data system (see guidance Section I.2.D.(2)).
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-19
7-09-99
Compliance with this requirement is demonstrated if, the radioactive waste management basis is
documented and signed by the Field Element manager or a designee (see DOE M 435.1-1,
Section I.1.A, Delegation of Authority) for each transuranic waste management facility,
operation, or activity. Using a graded approach, it may be possible to include multiple activities
under a single radioactive waste management basis, but it should be possible to objectively
identify which activities are covered. Further, the radioactive waste management basis includes or
references the controls that are established on a facility-specific basis to address the unique waste
management requirements and circumstances for each facility, operation, and/or activity.
Example: A storage facility that stores mixed and non-mixed transuranic waste has
approved waste acceptance requirements and a waste certification program that enables
transuranic waste to be shipped to the Waste Isolation Pilot Plant for disposal. The
mixed transuranic waste is to remain in storage pending WIPP receiving a RCRA Part B
permit. The radioactive waste management basis statement references the waste
certification process and the waste acceptance requirement documentation, which in turn
invoke the waste acceptance requirements of WIPP. In addition to citing site-wide
programs and plans (radiological control, health and safety, training, etc.) the
radioactive waste management basis statement also cites the RCRA permit issued for
storage of mixed transuranic waste and the facility operating procedure for segregating
mixed and non-mixed waste within the facility.
Supplemental References:
Section 325
1. EPA. Environmental Standards for the Management and Disposal of Spent Nuclear
Fuel, High-Level and Transuranic Radioactive Wastes, 40 CFR Part 191, U.S.
Environmental Protection Agency, Washington D.C.
2. EPA. Criteria for the Certification or Re-Certification of the Waste Isolation Pilot
Plant’s Compliance with the 40 CFR Part 191 Disposal Regulations, 40 CFR Part 194,
U.S. Environmental Protection Agency, Washington, D.C.
3. DOE, 1992. Nuclear Safety Analysis Reports, DOE 5480.23, U.S. Department of
Energy, Washington, D.C., April 10, 1992.
Chapter III - Transuranic Waste Requirements
III-20 DOE G 435.1-1
7-09-99
III. E. Contingency Actions.
The following requirements are in addition to those in Chapter I of this Manual.
(1) Contingency Storage. For off-normal or emergency situations involving
liquid transuranic waste storage or treatment, spare capacity with adequate
capabilities shall be maintained to receive the largest volume of liquid
contained in any one storage tank or treatment facility. Tanks or other
facilities that are designated transuranic waste contingency storage shall be
maintained in an operational condition when waste is present and shall meet
the requirements of DOE O 435.1, Radioactive Waste Management, and this
Manual.
(2) Transfer Equipment. Pipelines and auxiliary facilities necessary for the
transfer of liquid waste to contingency storage shall be maintained in an
operational condition when waste is present and shall meet the requirements
of DOE O 435.1, Radioactive Waste Management, and this Manual.
Objective:
The objective of this requirement is to ensure the impacts on the public, workers, or environment
are mitigated in the event that a leak develops in a tank storing transuranic waste or in a facility
processing transuranic waste. The mitigation is provided by ensuring spare waste storage
capacity is a required part of a site’s emergency management program. To meet this objective,
there needs to be both capacity to handle the largest volume of any single storage tank or liquid
waste in process, and the capability to transfer the waste.
Discussion:
This requirement shall be implemented through and included in site emergency management
programs that are required by DOE O 151.1, Comprehensive Emergency Management System.
The directive DOE O 151.1 is referenced in DOE M 435.1-1, Chapter I and considered necessary
for the safe management of radioactive waste. The Comprehensive Emergency Management
System requires the development of a complex-wide system for preparing for and managing
emergencies. At the site level, personnel are to establish an Operational Emergency Base
Program that provides the framework for responding to events involving, among other subjects,
health and safety, and the environment. The program requires a qualitative hazards survey to
identify the emergency conditions, describe the potential impacts, and summarize the planning and
preparedness requirements that apply.
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-21
7-09-99
During the development of the requirements of DOE M 435.1-1, Radioactive Waste Management
Manual, a waste management hazard and safety analysis identified the loss of containment of a
storage tank or waste processing facility containing radioactive liquids as a hazard requiring
mitigation. In addition to requiring facility designs to maintain waste confinement (see
DOE M 435.1, Section III.M.(2)), the ability to respond to leaks or other off-normal conditions if
they occur was also considered necessary. Consequently, the requirements to have adequate
spare capacity and the ability to transfer waste to the spare capacity were established.
Section 326
Operating procedures are developed and utilized for transfer of liquid transuranic waste to
contingency storage. The procedures should address maximum operational capacities and limits
for components of the operational system (e.g., spare storage capacity available in tanks). The
procedures should define and address all possible emergency transfer scenarios needed to comply
with this requirement.
Contingency Storage. Contingency storage is to be provided for both stored liquid transuranic
waste and for liquid transuranic waste treatment facilities. In the case of storage tanks, adequate
volumetric capacity must be available to receive the largest volume of waste stored in any single
tank. In the case of a treatment facility, adequate volumetric capacity must be available to allow
all in-process liquids in the facility to be moved into storage in the event of emergency or off-
normal conditions.
A number of factors are considered in maintaining spare capacity. First, the requirement includes
a provision that the spare capacity has “adequate capabilities.” Therefore, the spare capacity must
have the necessary features and functionality as dictated by the design and safety analysis for the
facility and wastes of concern. Features to be taken into account include appropriate materials of
construction, shielding, ventilation and filtration, heat dissipation, liquid level monitoring, and
mixing. Similarly, if the waste that may need to be transferred is regulated by some external
regulation (e.g., RCRA), the tank(s) that would be used for spare capacity should be properly
permitted.
The requirement specifies that the contingency storage provided is to meet the requirements of
DOE O 435.1 and DOE M 435.1-1. Of prime interest is the ability of contingency storage and
associated facilities to meet the requirements for confinement in Facility Design, DOE M 435.1-1,
Section III.M.(2). Additionally, compliance with the requirements for instrumentation and control
systems, ventilation, and monitoring systems is very important for tanks or facilities that will be
used for contingency storage. Meeting these requirements, in combination, ensures that the use of
existing tanks or other facilities for contingency storage minimizes the potential impacts of off-
normal or emergency situations involving liquid transuranic waste.
Spare capacity may be provided by a single tank or by the combined available volume in multiple
tanks. In cases where radiation fields are sufficiently low, spare capacity could be provided by
Chapter III - Transuranic Waste Requirements
III-22 DOE G 435.1-1
7-09-99
portable tanks, tankers (i.e,. railroad cars), or tank trucks. Due to the potential for airborne
radioactive material, impoundments or bermed areas open to the air should not be used for spare
storage capacity unless a safety analysis shows that the risk to workers and the public is low.
Example: Liquid radioactive waste is stored in six underground storage tanks with a
design capacity of 250,000 gallons each. The waste in the all tanks has the same
chemical and radiological characteristics. One tank contains 200,000 gallons and each
of the others contain about 100,000 gallons. Capabilities exist to retrieve waste and
transfer it among the six tanks. This system meets the requirement because the largest
volume of 200,000 gallons can be distributed between any two of the other tanks.
Section 327
Transfer Equipment. The ability to perform the transfer is just as important as having the
capacity. Equipment necessary to transfer each tank or treatment facility volume of liquid
transuranic waste in the event of a leak or other off-normal condition is to be identified and
documented.
Example: Liquid radioactive waste is stored in six underground tanks with the volumes
and characteristics described in the previous example. Although there are transfer lines
to any of the tanks from a central diversion box, the tanks were constructed without the
capability to retrieve the waste. This situation does not comply with the requirement.
Although there is adequate capacity, the ability to transfer the waste does not exist.
In addition, equipment necessary to transfer the contents of each tank is tested and inspected as
part of a routine maintenance program (see DOE M 435.1-1, I.1.E.(9)). Special attention should
be given to including in the maintenance program equipment and transfer lines that are not
routinely used in managing liquid wastes. Inspection and testing includes the following minimum
items:
• leak testing of pipelines;
• ensuring the availability of any jumpers necessary for completing waste transfer;
• confirming that instrument panels, control panels, valves, pumps and any necessary
ventilation equipment is supplied with the necessary electrical power, air (for
pneumatically-controlled items), steam, and water; and
• performing functional tests of instruments, controls, valves, pumps, and ventilation
equipment.
The capability to perform an emergency transfer of liquid transuranic waste is to be maintained at
all times. Therefore, every shift must include or have immediate access to qualified individuals
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-23
7-09-99
and the equipment necessary to perform transfers in a timely manner, unless analysis of the
hazards associated with the leaking waste demonstrates that immediate transfer is unnecessary.
Example: A large shielding block is in place over a jumper pit that needs to be accessed
during an emergency transfer of liquid waste. The block can only be moved by a crane.
Therefore, implementation of this requirement entails making sure that the crane is
always operationally available (in a matter of hours rather than days) and every shift has
a individual qualified to operate the crane and remove the block.
Spare capacity may be shared by different waste types, however mixing radioactive wastes of
different types should be evaluated and is generally not acceptable.
Example 1: A tank farm contains both high activity liquid low-level waste and liquid
transuranic waste in separate tanks. A spare empty tank is maintained and available for
emergency transfers of either waste.
Example 2: A tank farm contains both high-level waste and liquid transuranic waste in
separate tanks. If the spare capacity were provided by excess capacity in tanks that
contain high-level waste, use of the capacity for transuranic waste would be undesirable.
Transferring transuranic waste into a tank containing high-level waste, would result in a
mixture that would no longer be eligible for disposal at the Waste Isolation Pilot Plant
which, by law, cannot dispose of high-level waste. Therefore, waste managers should
identify different spare capacity to accommodate the two different waste types.
Section 328
Compliance with these requirements is demonstrated by having adequate spare capacity and
transfer equipment exists for emergency transfers of all liquid transuranic waste. In addition, the
capability to perform emergency transfers is demonstrated by having waste transfer routings
identified, operational procedures to direct transfers, staff trained to the procedures, and records
showing that the spare capacity and transfer capability are kept in operating condition.
Supplemental References:
1. DOE, 1995. Comprehensive Emergency Management System, DOE O 151.1, U.S.
Department of Energy, Washington, D.C., September 25, 1995.
Chapter III - Transuranic Waste Requirements
III-24 DOE G 435.1-1
7-09-99
III. F. Corrective Actions.
The following requirements are in addition to those in Chapter I of this Manual.
(1) Order Compliance. Corrective actions shall be implemented whenever
necessary to ensure the requirements of DOE O 435.1, Radioactive Waste
Management, and this Manual are met.
Objective:
The objective of this requirement is to ensure that actions will be taken to preclude, minimize, or
mitigate hazards whenever a situation arises at a transuranic waste management facility that could
threaten worker or public safety, or the environment.
Discussions:
The Radioactive Waste Management Manual, DOE M 435.1-1, Section I.2.G, states that all
personnel have a responsibility to identify conditions that require corrective actions to achieve
compliance with the Order and Manual requirements or to address health and safety conditions
that pose an imminent or possible danger. That responsibility is to ensure that conditions that
pose an imminent or potential danger to the environment, or to the health and safety of workers
or the public are identified and corrected. If necessary, activities are to be curtailed or shutdown
to ensure that the public, workers, and the environment are protected until corrective actions are
implemented to mitigate the identified hazard.
Corrective actions are activities which, when implemented, will address and correct noncompliant
or hazardous conditions. Corrective actions can include improvements to documentation (e.g.,
procedures, plans, authorization basis documents), training and qualification programs or
procedures, physical and process design changes, changes to operating conditions, or a
combination of these activities.
Corrective Action System. A corrective action system exists for addressing noncompliant or
hazardous conditions for transuranic waste management facilities, operations, and activities. The
system for addressing corrective actions may be an integral portion of the site’s quality assurance
program. Corrective actions in response to quality assurance program assessments are addressed
in the Implementation Guide for Use with Independent and Management Assessment
Requirements of 10 CFR 830.120 and DOE O 414.1 Quality Assurance. The corrective action
system provides for documenting noncompliant or hazardous conditions, identifying the
organizations or individuals responsible for developing and implementing corrective action plans,
providing corrective action status, and tracking progress through final implementation of the
actions. The corrective action system is instituted as a fundamental part of the systematic
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-25
7-09-99
Section 329
evaluation of radioactive waste activities that is implemented by the Site-Wide Radioactive Waste
Management Program (see guidance for DOE M 435.1-1, Section I.2.F.(1)).
A problem requiring corrective action could range from a minor deviation from a procedure that
has minimal safety or public health implications, to a situation that poses an immediate threat to
health and safety from an uncontrolled release of large quantities of radioactive material. For
situations where a problem could pose an immediate risk to a worker, member of the public, or
damage to the environment, immediate shutdown of the process or facility may be appropriate as
the first step in addressing the problem (see guidance for DOE M 435.1-1, Section III.F.(2).
Example: An employee performing a routine container inspection in a storage facility
notices that there are drums in an area designated for “WIPP-ready packages” that do
not have a tamper indicating device on the container closure. The worker records his
observation in the inspection log and notifies the building manager. The manager
directs that a corrective action plan be prepared. The plan includes an evaluation of the
conditions that resulted in the package being improperly controlled and recommends
changes in procedures and training to the new procedures to prevent any recurrences. A
notice is sent to staff responsible for receiving and handling waste containers and to
generator organizations reiterating the requirement for tamper indicating devices. In
addition, a follow-up review is schedule for 60 days after the plan is approved.
If a facility or activity can be allowed to operate while a noncompliant or hazardous condition
exists, the allowance and any associated limitations must be defined as part of the facility’s or
activity’s radioactive waste management basis, identified as a configuration controlled item in a
configuration management plan or included in a revision or modification to an operating
procedure or similar controlled documentation. The corrective action system should provide for
preventing the use of systems or facilities (e.g., through lockout), or procedures (through
cancellation) in cases where it is determined that use of the system, facility, or procedure impacts
safety.
Example: In the above example, the facility manager imposes a 2 week moratorium on
receiving additional transuranic waste at the facility or certifying transuranic waste as
meeting the Waste Acceptance Criteria for the Waste Isolation Pilot Plant. The manager
expects that during the two week time period, the underlying problem can be identified
and interim measures implemented to prevent a recurrence until the corrective action
plan is fully implemented.
Compliance with this requirement is demonstrated if a corrective action system exists which
addresses noncompliant or hazardous situations associated with transuranic waste management
and in a systematic fashion, and allows identification of problems by all personnel.
Chapter III - Transuranic Waste Requirements
III-26 DOE G 435.1-1
7-09-99
Supplemental References:
1. DOE, 1996. Implementation Guide for Use with Independent and Management
Assessment Requirements of 10 CFR 830.120 and DOE O 414.1 Quality Assurance,
DOE G 414.1-1, U.S. Department of Energy, Washington D.C., August 1996.
III. F.(2) Operations Curtailment. Operations shall be curtailed or facilities
shut down for failure to establish, maintain, or operate consistent with
an approved radioactive waste management basis.
Section 330
Objective:
The objective of this requirement is to limit the operation of waste management activities and
facilities as necessary to avoid creation of near- or long-term safety or environmental hazards.
Discussion:
The Radioactive Waste Management Manual, DOE M 435.1-1, requires that a radioactive waste
management basis be established for each transuranic waste management facility, operation, or
activity. The radioactive waste management basis documents the conclusion that the potential
hazards from management of radioactive waste have been sufficiently evaluated and that adequate
controls are in place to provide assurance that the public, workers, and the environment are being
protected. Field Element Managers are responsible for ensuring a radioactive waste management
basis is developed, reviewed, approved, and maintained for each DOE radioactive waste
management facility, operation, or activity (DOE M 435.1-1, Section I.2.F.(2)). The guidance for
that requirement should be consulted for additional details on the development, review, and
approval of a radioactive waste management basis. Also, additional discussion concerning the
radioactive waste management basis for transuranic waste generator, treatment, storage, and
disposal facilities is discussed under guidance for DOE M 435.1-1, Section III.D.
As part of his/her responsibilities for maintaining the radioactive waste management basis for
transuranic waste management facilities, operations, and activities under his/her authority, the
Field Element Manager evaluates the compliance of the facilities, operations, and activities with
the constraints and controls documented in the radioactive waste management basis by ensuring
that routine assessments are conducted. If the Field Element Manager determines, either through
routine assessment or by virtue of an occurrence or off normal event, that an operation, activity,
or facility is not operating in compliance with an approved radioactive waste management basis, it
must be curtailed or shut down. The action taken is commensurate with the hazards associated
with the noncompliance and with the continued operation of the facility.
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-27
7-09-99
This requirement is to be implemented in a graded manner. Actions to be taken are based on
assessments of adherence to radioactive waste management bases, and can range from shutdown
of an operation or facility to placing limits or constraints on what activities can be performed or
how the activities are to be performed. Shutdown of a facility involves stopping all operations in
the facility except surveillance or monitoring activities necessary to maintain the facility in a safe
standby condition. Shutdown is considered appropriate when there is either a potential imminent
threat to safety or environmental protection, or a blatant failure to establish or comply with a
radioactive waste management basis.
Alternatively, there may be cases where a facility, operation, or activity assessment determines
that the radioactive waste management basis is no longer current or has been violated, but there is
no imminent threat to public, worker, or environmental protection. In such a case, the Field
Element Manager may decide that shutdown of the facility is not necessary. It may be sufficient
to impose certain limits until the radioactive waste management basis is made current. The limits
imposed may prohibit the generation, receipt, or processing of certain waste streams, or may
involve constraints on the processes that may be performed.
Section 331
The action taken in response to the failure to establish a radioactive waste management basis is to
be clearly documented in a formal communication (e.g., letter, memorandum). Such
communication needs to identify the reason for the shutdown or curtailment, and identify what is
necessary to initiate restart. Generally, development of a corrective action that is implemented
through the corrective action system discussed in the preceding section would be appropriate for
responding to a shutdown or curtailment of activities.
In concert with Core Requirement #6 of the Integrated Safety Management System, “Feedback
and Improvement,” the Field Element Manager should use the audits and assessments to identify
opportunities for improvement in the implementation of an activity or facility’s radioactive waste
management basis. Identified improvement actions should be shared with like organizations and
tracked by management to determine whether they are yielding the anticipated improvements.
Communicating the results of assessment upward in the DOE and contractor organization will
allow the findings to reach the management level with the authority necessary to effect
improvements.
Compliance with this requirement is demonstrated by documented evidence of systematic, routine
reviews to determine whether waste management activities and facilities under are operating in
accordance with an approved radioactive waste management basis. In addition, the
documentation should show that limitations (which may include shutdown) have been placed on
activities and operations that do not have or are operating outside the conditions of an approved
radioactive waste management basis.
Chapter III - Transuranic Waste Requirements
III-28 DOE G 435.1-1
7-09-99
Supplemental References:
1. DOE, 1996. Safety Management System Policy, DOE P 450.4, U.S. Department of
Energy, Washington, D.C. October 15, 1996.
2. DOE, 1997. Line Environment, Safety and Health Oversight, DOE P 450.5, U.S.
Department of Energy, Washington, D.C., June 26, 1997.
3. DOE, 1997. Safety Management Functions, Responsibilities, and Authorities Policy,
DOE P 411.1, U.S. Department of Energy, Washington, D.C., January 1, 1997.
4. DOE, 1997. Manual of Safety Management Functions, Responsibilities, and Authorities,
DOE M 411.1-1, U.S. Department of Energy, Washington, D.C., October 8, 1997.
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-29
7-09-99
III. G. Waste Acceptance.
The following requirements are in addition to those in Chapter I of this Manual.
(1) Technical and Administrative. Waste acceptance requirements for all
transuranic waste storage, treatment, or disposal facilities, operations, and
activities shall specify, at a minimum, the following:
(a) Allowable activities and/or concentrations of specific radionuclides;
(b) Acceptable waste form and/or container requirements that ensure the
chemical and physical stability of waste under conditions that might
be encountered during transportation, storage, treatment, or disposal;
(c) Restrictions or prohibitions on waste, materials, or containers that
may adversely affect waste handlers or compromise facility or waste
container performance;
(d) Requirement to identify transuranic waste as defense or non-defense,
and limitations on acceptance; and
(e) The basis, procedures, and levels of authority required for granting
exceptions to the waste acceptance requirements, which shall be
contained in each facility’s waste acceptance documentation. Each
exception request shall be documented, including its disposition as
approved or not approved.
Section 332
Objective:
The objectives of the waste acceptance requirements are to ensure that transuranic waste which is
received at a facility contains only the radionuclides that the facility can safely manage, and only in
concentrations and/or total activities which are compatible with the work to be undertaken in the
facility; ensure that transuranic waste which is to be received at a facility is in a form or package
that will maintain its integrity and retain acceptable configuration under the conditions that are
expected to be encountered during the management steps the waste will undergo; ensure that no
transuranic waste received at a facility contains materials that will compromise the safety or
integrity of the facility under the expected operating conditions; and ensure that formal
procedures exist and a decision process is clear concerning the granting of exceptions to waste
acceptance requirements.
Chapter III - Transuranic Waste Requirements
III-30 DOE G 435.1-1
7-09-99
Discussion:
As discussed in the guidance for DOE M 435.1-1, Section I.2.F.(6), the waste acceptance
requirements establish the conditions for waste that facilities can safely receive. Therefore, the
acceptance requirements for a transuranic waste storage, treatment, or disposal facility include all
requirements that transuranic waste must meet to be acceptable for receipt, and for the
subsequent storage, treatment, or disposal, as appropriate.
In conducting the analyses for development of the DOE M 435.1-1 requirements, minimum
acceptance requirements that must be specified in the waste acceptance documentation for
storage, treatment, and disposal facilities in order for transuranic waste to be safely handled were
identified. Guidance on subrequirement (a) is provided below under Radionuclide Content or
Concentration. Guidance on subrequirements (b) and (c) is provided under Waste Form and
Package Criteria and Prohibitions. Guidance on subrequirement (d) is provided under
Defense/Non-Defense Waste. Guidance on subrequirement (e) is provided under Exceptions.
Development of Waste Acceptance Requirements. A facility receiving waste for storage,
treatment, or disposal is required to document the waste acceptance requirements for the facility.
These requirements have their foundation in facility design capabilities such as volume, handling
weight, allowable contents, and radiological limits (i.e., criticality, radiation, contamination).
Other requirements may include any number of regulations promulgated by the EPA, NRC, DOT,
the host state, and DOE itself. The designer and operator of the facility receiving waste are likely
to be most knowledgeable and understanding of the requirements and limitations of the facility
and, therefore, are in the best position to establish the waste acceptance requirements or criteria
that must be met for waste sent to the facility.
Although there are exceptions, most transuranic waste in the Department is to be disposed at
WIPP. The exceptions include waste that cannot meet the waste acceptance criteria of WIPP or
are otherwise ineligible (e.g., non-defense waste). Personnel responsible for transuranic waste
storage or treatment facilities which manage waste destined for WIPP need to consider the WIPP
waste acceptance criteria in developing acceptance criteria for their facilities.
Section 333
A transuranic waste management facility at a site may have its own specific stand-alone waste
acceptance requirements. Or a site may have general waste acceptance requirements applicable to
all transuranic waste management facilities at the site, with separate facilities adding facility-
specific acceptance requirements to the site waste acceptance requirements as necessary. This
practice may be particularly effective at sites with many facilities which manage small quantities of
waste with multiple locations for staging, storage, and/or central management of waste. At such
facilities, most of the process and procedural waste acceptance requirements could be in one
document applicable to the whole site, which would be supplemented with specific technical
requirements for acceptance at each of the separate management locations. If activities across
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-31
7-09-99
various facilities are similar, they could share the same supplemental waste acceptance
requirements documents. Likewise, if several activities are carried out at locations that are close
to one another, or are managed by the same entity, then one supplemental technical document
may be prepared to cover those activities.
The waste acceptance requirements and documentation for a facility receiving waste for storage,
treatment, or disposal is prepared using a graded approach commensurate with the hazards
associated with the management of the waste in the facility and the complexity of the activities to
be conducted in the facility. The waste acceptance requirements for a facility which receives large
quantities of transuranic waste from many generators, or with highly variable contents, or both,
may need to address many hazards and consequently be more detailed. By contrast, a storage
facility which will only pass-through properly packaged waste directly to a disposal facility
without any additional processing or packaging may only need a minimal set of requirements.
Perhaps only a few administrative requirements would be necessary for proper receipt of waste at
such a storage facility, along with assurance that waste received at the storage facility meets the
disposal facility technical waste acceptance requirements.
Example 1: The Waste Isolation Pilot Plant is to receive defense transuranic waste
generated by many different processes and from many different sites. In addition, the
transportation of contact-handled transuranic waste to WIPP is to be in TRUPACT II
containers. The requirements for acceptance of waste at WIPP are extensive and require
a high degree of rigor. The waste acceptance requirements are addressed in a number of
interrelated documents. These documents include the Waste Acceptance Criteria for the
Waste Isolation Pilot Plant, the Generator Site Certification Guide, the Quality
Assurance Program Description, and the Transuranic Waste Characterization Quality
Assurance Program Plan.
Example 2: At a DOE site, several facilities are used for storage of transuranic waste.
A single waste acceptance requirements document which contains the necessary
administrative requirements for all of the storage facilities is prepared as an umbrella
document at the site. For each storage facility, a supplemental technical procedure
which contains the technical criteria specific to the facility (e.g., inventory limits based
on safety evaluations) and which invokes the umbrella document for the administrative
processes and forms is prepared. This combination of documents provides the necessary
waste acceptance criteria for waste to be received at the facilities.
Section 334
Legislation, regulations, performance assessments, safety analysis reports, technical safety
requirements, criticality analyses, and other appropriate safety or authorization basis documents
are to be used to establish the waste acceptance criteria for facilities receiving transuranic waste
for storage, treatment, or disposal. These documents and analyses provide the basis for
radioactivity (concentration and inventory) limits, waste categories (e.g., contact-handled or
Chapter III - Transuranic Waste Requirements
III-32 DOE G 435.1-1
7-09-99
remote-handled), waste form and/or packaging stability requirements, allowable chemical content,
allowable free liquid content, and any other necessary waste package or form requirements to
ensure that the facilities’ design, performance, and operating bases are not compromised.
Radionuclide Content or Concentration. Radiological limits for storage, treatment, and disposal
facilities may be derived from a number of technical as well as administrative sources. In
developing radionuclide limits, personnel need to consider legislative and/or regulatory
limitations, the disposal facility performance assessment, safety analysis reports, and criticality
analyses. In addition to establishing general radiological limits (e.g., a contact dose rate), these
sources identify specific radionuclides whose concentration or total activity must be limited in the
waste acceptance criteria in order to remain within the bounds for safe and legal facility operation.
The operating definition of transuranic waste is taken from Federal legislation (see guidance for
DOE M 435.1-1, Section III.A). The definition is significant to transuranic waste management
because the designated disposal facility for defense transuranic waste, WIPP can only accept
waste that meets that definition. Storage and treatment facilities need to include appropriate
waste acceptance requirements that require identification of transuranic waste to facilitate its
eventual transfer for WIPP disposal.
The results of a long-term performance assessment analysis may provide information on critical
radionuclides that are most important to the long-term performance of the disposal facility. The
waste acceptance criteria for the disposal facility are to translate the results of the performance
assessment analyses into limits on the receipt of waste at the facility or on the operation of the
facility.
Example: The performance assessment of WIPP is based on an assumed final inventory
of transuranic and other radionuclides. Although the performance assessment indicated
that facility performance was not sensitive to radionuclide inventory, in the Compliance
Certification Application WIPP committed to tracking the cumulative inventory of
radionuclides of interest. Therefore, the waste acceptance criteria require sites to report
the inventory or concentration of these radionuclides of interest.
Although performance assessments are not required for storage or treatment facilities, personnel
developing waste acceptance criteria for these types of facilities should consider the radiological
limits of WIPP. In most cases, transuranic waste will eventually be transferred to WIPP for
disposal, so WIPP waste acceptance criteria should be factored into the waste acceptance
requirements of the storage or treatment facility to ensure a situation is not created in which the
waste does not have a path to disposal.
Section 335
Example: A transuranic storage facility accepts a high dose rate transuranic waste from
a generator. Due to the dose rate, the waste is managed and stored as remote-handled
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-33
7-09-99
waste. However, when placed into storage, the waste does not meet the WIPP waste
acceptance criteria, thus creating a future management issue. As an alternative, the
waste acceptance criteria could be revised to not allow acceptance of transuranic waste
that does not meet the WIPP waste acceptance criteria. The generator would be
compelled to work with the waste management organizations to determine how to manage
or process the waste at the source in order to meet the disposal criteria of available
facilities (transuranic and/or low-level waste).
The safety analysis report or safety evaluation prepared for a transuranic waste management
facility may identify specific radionuclides that warrant specific attention from a worker safety
standpoint, and may require special handling if received and managed at the facility.
Example: A storage facility that manages mixed transuranic waste is subject to RCRA
Part B permit requirements for routine inspection of the waste. An analysis of worker
radiation exposure associated with inspection of the storage configuration indicates that
several radionuclides need to be controlled below certain concentrations to maintain
doses to workers as low as reasonably achievable. The waste acceptance requirements
for the facility reflect the allowable concentrations from the safety analyses as maxima
for waste that can be accepted for storage in the facility.
Any criticality analyses conducted in accordance with the criticality safety program in
conformance with DOE M 435.1-1, Section I.1.E.(4) may also result in limitations on acceptance
of fissile radionuclides. These limitations need to be included in the waste acceptance
requirements, as appropriate. Similarly, for transuranic waste, the TRUPACT II Safety Analysis
Report for Packaging establishes limits on the amount of fissile material that is allowed to be
transported in the TRUPACT II. These limits need to be considered in the development of waste
acceptance criteria to avoid the need to repackage waste to transfer it to the next step in the waste
management process. These limits are reflected in the Waste Acceptance Criteria for the Waste
Isolation Pilot Plant.
Waste Form and Package Criteria and Prohibitions. Generally, waste acceptance requirements
specify that wastes received at the facility are in a physically/chemically stable form. As used in
this requirement, stability refers to the physical and chemical properties of waste that are
necessary for it to be handled safely at a facility and to undergo the management steps normally
performed at that facility. Such stability is dependent on the waste management steps to be
performed with the waste (e.g., treat, store) and the time to complete the management step (e.g.,
time until treatment or length of expected storage period). Therefore, waste acceptance
requirements must specify the physical and chemical stability that correspond to the specific
operations and activities of a particular facility. Waste acceptance requirements for a transuranic
waste treatment facility need to specify the physical and chemical precautions and conditions
under which untreated waste can be received at the facility so that facility safety and effective
Section 336
Chapter III - Transuranic Waste Requirements
III-34 DOE G 435.1-1
7-09-99
operations will not be compromised. Any physical or chemical stabilization of waste prior to
transfer to a facility receiving waste for storage, treatment, or disposal needs to be done according
to a systematic process that may include consideration of bench-scale testing and verification that
the process is producing satisfactory results.
Example: A facility that is in the process of cleaning out transuranic radionuclide-
contaminated glove boxes determines that operational efficiencies will be realized in the
form of fewer drums, less storage space, and fewer transuranic waste shipments if they
compact the cleanout waste into 55-gallon drums. The organization responsible for
operating the compactor establish a set of waste acceptance criteria for waste that can be
received from the cleanout activities. The criteria, based on expected ability to fit 25
boxes in a drum, specify: waste must be packages in 1 cubic foot cardboard boxes; no
more than 5% of the volume of a box can be incompressible waste; the long axis of
incompressible waste must be oriented in a horizontal plane; boxes must be free of
removable external contamination; the dose rate from any box must be less than
10 mrem/hr; there must be less than 8 plutonium-239 fissile-gram equivalents per box;
there must be less than 3 plutonium-239 equivalent curies per box; waste must be less
than 50 ppm polychlorinated biphenyls, and the waste must be characterized for RCRA
constituents. Based on these criteria, the compactor facility can provide 55-gallon drums
that meet the on-site storage facility’s requirements, and subsequently, the WIPP
requirements.
The waste acceptance requirements are to specify waste streams, classes, or categories of waste
requiring application of specific physical, chemical, or structural stabilization methods, as
determined by the results of safety analyses or long-term performance assessments. Acceptable
waste forms, containers, and packages are specified by the waste acceptance requirements. The
waste acceptance requirements need to list any specific packages and containers pre-approved as
acceptable for the transuranic waste management facilities, as well as acceptable overpacks. The
waste acceptance requirements need to identify any of the following specific technical
requirements that must be included to ensure that waste received at any storage, treatment, or
disposal facility is consistent with the operating basis of the facility:
• the acceptable limits for waste package external surface dose rate for both contact
and remote handled packages;
• the acceptable limits for waste package surface contamination;
• the allowable heat generation rates;
• the acceptable limits for free liquid content, specified on a per package basis;
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-35
7-09-99
• the acceptable limits for maximum void space, specified on a per package basis;
• the necessary labeling and marking, including information about bar coding or
other tracking system used at the facility receiving the waste and the application of
the system by generators;
• any specific radionuclides or chemical or hazardous materials that are prohibited
from acceptance at the facility. This may include pyrophoric materials, explosives,
or materials that might cause violent reactions during storage, treatment, or
disposal;
Section 337
• any specific requirements associated with acceptance of mixed transuranic waste,
including any additional restrictions or limitations on the waste or specifications for
handling mixed waste containers;
• any specific requirements associated with acceptance of special transuranic waste
needing out-of-the ordinary attention for receipt, handling, storage, treatment, or
disposal, (e.g., sealed sources), including any additional restrictions or limitations
on the waste or specifications for handling the waste containers;
• any package protection requirements needed for transport and receipt to provide
needed physical protection of the packages to prevent breaching and so that the
certified status of the waste is preserved; and
• the necessary shipping arrangements for transport to the facility receiving waste,
including any electronic data bases or scheduling system used.
Example 1: Waste acceptance criteria for the Waste Isolation Pilot Plant have been
developed based on applicable requirements, e.g., statutory requirements, other
environmental compliance requirements, operational and safety analysis requirements,
and transportation requirements. Development of waste acceptance requirements based
on these sources ensures that waste received at WIPP complies with applicable
regulations and can be safely managed at the site. The requirements include technical
requirements addressing container properties, physical properties, nuclear properties,
chemical properties, and gas generation; and administrative requirements for data that
need to be provided with waste shipments.
Example 2: A transuranic waste containing spent solvents regulated by RCRA is
transferred from a storage facility to a treatment facility for treatment. The treatment
facility personnel must establish the limits, if any, on the concentration of solvents for
which the treatment process was designed and qualified, and limitations or prohibitions
Chapter III - Transuranic Waste Requirements
III-36 DOE G 435.1-1
7-09-99
on other materials that may adversely affect the processing. The waste treatment process
is to produce a treated waste product that (1) has been reduced in transuranic
contaminant concentrations such that it may be disposed of as mixed low-level waste or
(2) is acceptable for disposal at the WIPP as mixed transuranic waste. In either case, the
final treated waste form must also meet the disposal facility waste acceptance criteria. In
order to ensure that the treatment process product will meet applicable requirements, the
treatment facility must document the limitations in the waste acceptance criteria that the
organization supplying the waste must meet. By doing so, the treatment facility can
safely process the waste, treat it successfully, and produce a product that can be disposed
of.
Defense/Non-Defense Waste. The WIPP Land Withdrawal Act of 1992, as amended, limits the
waste that can be accepted for disposal at WIPP to transuranic waste generated by atomic energy
defense activities. In order to ensure compliance with the statutory constraint, and to facilitate
identification of waste that can be disposed of at WIPP, all transuranic waste acceptance criteria
must include a requirement for waste to be identified as defense or non-defense. At a minimum,
the waste acceptance criteria should require identification of waste as defense or non-defense to
be part of the certification program (see Waste Certification guidance for DOE M 435.1-1,
Section III.J) and be included in the documentation used to transfer responsibility to personnel at
the facility receiving the waste for storage, treatment, or disposal. The requirement applies to all
transuranic waste and to all waste management facilities to ensure that the defense or non-defense
identity of waste is not lost during waste generation and subsequent processing operations.
Section 338
Example: The waste acceptance criteria for a transuranic waste storage facility has a
waste transfer form that is to be used for each transfer of waste to the facility. The form,
which the waste acceptance criteria requires to be used to document the certification that
waste meets the waste acceptance criteria, includes identification of the waste as defense
or non-defense as a mandatory piece of data. In addition, the waste acceptance criteria
require that waste packages be marked to indicate the waste as being defense or non-
defense. The waste acceptance criteria identifies three acceptable means of marking
waste packages, color of the package, labeling, or through bar coding.
The Departmental interpretation is that the term “atomic energy defense activities” used in the
WIPP Land Withdrawal Act of 1992, as amended, has the same meaning as the same term used in
the Nuclear Waste Policy Act of 1982, as amended.
The term “atomic energy defense activities” permits WIPP to dispose of defense
transuranic waste resulting from all of the noncivilian activities and programs of DOE,
including weapons production, naval reactors, defense research and development,
associated defense environmental restoration and waste management and other defense-
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-37
7-09-99
related activities, as defined more specifically in the Nuclear Waste Policy Act, from which
the term was borrowed. (Nordhaus, 1996)
As the Nuclear Waste Policy Act of 1982, as amended, states, the term “atomic energy defense
activity” means any activity of the Secretary [of Energy] performed in whole or in part in carrying
out any of the following functions:
(a) naval reactors development;
(b) weapons activities, including defense inertial confinement fusion;
(c) verification and control technology;
(d) defense nuclear materials production;
(e) defense nuclear waste and materials by-product management;
(f) defense nuclear materials security and safeguards and security investigations; and
(g) defense research and development.
This definition of atomic energy defense activity does not include transuranic waste generated
from DOE’s civilian atomic energy activities.
Exceptions. Waste acceptance requirements are established to ensure that facilities can safely
manage waste received for storage, treatment, or disposal. Thus, exceptions or deviations to
waste acceptance criteria cannot be routine and must be carefully reviewed and documented. The
procedures for granting exceptions need to clearly state the entire process for requesting an
exception, describe acceptable bases for granting exceptions, and identify any additional
information that is needed to supplement the documentation normally provided for waste
transfers. The approval process needs to be clearly spelled out including identification of the
officials who have the authority to approve the exception.
Section 339
Example: The waste acceptance requirements for a transuranic waste storage facility
establishes a per package limit on fissile material. The limit was developed based on
criticality and safety analyses which assumed all of the packages in the facility could
potentially contain the specified amount of fissile material. A generator has a waste
package that slightly exceeds the limit. The waste acceptance requirements specify the
that the generator needs to identify the criterion for which an exception is being
requested and provide relevant information about the waste package or waste stream for
which an exception is being sought. It further identifies to whom the request for an
exception is to be submitted. At the storage facility, there are documented procedures
indicating the process to be followed for evaluating the exception request and identifying
the facility manager as the approval authority. In this case, an analysis is performed
indicating that because of the small inventory of fissile material in the facility, an
exception can be granted. Documentation supporting this decision includes notification
to the generator that the exception is granted, copies of the analyses performed to
Chapter III - Transuranic Waste Requirements
III-38 DOE G 435.1-1
7-09-99
support the decision, and additional controls on waste that can be accepted in the facility
during the time the particular waste remains in storage (i.e., limits may have to be placed
on the per package content of other waste or on the total number of packages that the
facility could accept).
Compliance with these requirements is demonstrated if waste acceptance requirements are
documented, contain clear and precise criteria specifying the radionuclide limits in the form of
contents or concentrations that can be accepted, the limitations and prohibitions on waste forms
and packages that can be received, and the limits, prohibitions, or instructions concerning any
other technical information so that the waste is compatible with the safety basis of the facility, and
which will result in acceptable waste at subsequent steps in managing the transuranic waste.
Waste acceptance requirements are to also contain a clear description of the process and bases for
obtaining an exception or deviation to the acceptance criteria for transuranic waste to be received
at the facility.
Supplemental References:
1. CAO, 1997. Generator Site Certification Guide, Revision 1, DOE/CAO-95-2119, U.S.
Department of Energy, Carlsbad Area Office, Carlsbad, NM, August 1997.
2. CAO, 1996. Waste Acceptance Criteria for the Waste Isolation Pilot Plant, Revision 5,
DOE/WIPP-069, U.S. Department of Energy, Carlsbad Area Office, Carlsbad, NM, April
1996.
3. CAO, 1996. Quality Assurance Program Document, Revision 1, CAO-94-1012, U.S.
Department of Energy, Carlsbad Area Office, Carlsbad NM, 1996.
4. CAO, 1998. U.S. Department of Energy, Transuranic Waste Characterization Quality
Assurance Program Plan, Revision 1, CAO-94-1010, U.S. Department of Energy,
Carlsbad Area Office, Carlsbad NM, December 18, 1998.
5. CAO, 1998. TRUPACT-II Operating and Maintenance Instructions, Revision 1,
DOE/WIPP-93-1001, U.S. Department of Energy, Carlsbad Area Office, Carlsbad NM,
May 1998.
6. Nordhaus, 1996. Robert R. Nordhaus, to Al Alm, memorandum, Interpretation of the
Term “Atomic Defense Activities” as Used in the Waste Isolation Pilot Plant Land
Withdrawal Act, U.S. Department of Energy, Washington, D.C., September 9, 1996.
Section 340
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-39
7-09-99
III. G.(2) Evaluation and Acceptance. The receiving facility shall evaluate
waste for acceptance, including confirmation that technical and
administrative requirements have been met. A process for the
disposition of non-conforming wastes shall be established.
Objective:
The objective of this requirement is to establish a process by which personnel at a facility
receiving transuranic waste for storage, treatment, or disposal determine that the waste being
transferred is acceptable in accordance with the waste acceptance requirements, and for that
process to specifically address management of waste that does not conform with all of the
requirements when it is received at the facility.
Discussion:
This requirement makes it the responsibility of officials at a facility to which waste is transferred
to confirm that waste is in compliance with the established waste acceptance requirements and
also provides a mechanism by which the officials confirm that waste can be accepted and safely
managed at the facility.
Evaluation and Acceptance. The methodology for implementing the evaluation and acceptance of
transuranic waste needs to be flexible and defined on a facility-specific basis. The complete
process and procedures, including the responsibilities of generating facilities, need to be clearly
documented so that both the generator and the facility receiving the waste understand the process
that will be used. As with implementation of other parts of DOE M 435.1-1, this requirement is
implemented using the graded approach. Facilities receiving transuranic from many generators
and/or offsite generators may need to implement more detailed waste evaluation and acceptance
processes than a facility receiving waste from a small number of onsite generators.
The evaluation and confirmation process consists of one or more of the following approaches, and
is designed to demonstrate that the waste presented meets the waste acceptance requirements of
the facility receiving waste for storage, treatment, or disposal:
• Testing, sampling, and analysis of the contents of a representative sample of waste
packages as they are received at the facility;
• Testing and analysis of a number of samples taken at the generator facility;
• Detailed review of sampling and analysis data generated by the sending facility or
an independent laboratory employed by the generating facility;
Chapter III - Transuranic Waste Requirements
III-40 DOE G 435.1-1
7-09-99
• Audit, review, or surveillance of the sender’s waste characterization activities and
processes and waste certification programs.
Testing, sampling, and analysis of the contents of a representative sample of waste packages upon
receipt is complicated by the fact that additional risk is posed if a technique such as opening of
drums and obtaining grab samples is used. Therefore, consideration needs to be given to
implementing non-destructive examination technologies if receipt sampling and analysis is the
preferred approach. Likewise, analysis of samples taken at the generator’s site may involve
additional risk, and also may be expensive to implement. If this method is employed, samples
which are representative, either statistically or correlated with generator profiles, need to be
obtained for analysis to validate this method as accurate. This sampling would include packages
from the generators sending the largest volume of waste to the facility or packages containing the
critical radionuclides as identified in the waste acceptance requirements.
Section 341
Example: The waste acceptance process for a storage facility that receives waste from
multiple generators involves assay to confirm the waste is transuranic, and sample
collection and analysis to confirm its RCRA status. The process calls for assaying and
sampling one waste package of every 100 from established waste streams and one of
every 10 for new waste streams or for waste streams from generators who have a history
of poor compliance with the waste acceptance criteria.
The use of a detailed review of the sampling and analysis data gathered by others would include
an evaluation of the methodologies used for collecting the sample, maintaining the integrity of the
sample and data (e.g., through a chain of custody), and performing the radioanalyses. As above,
the samples collected would need to be representative of the waste, either statistically or with a
bias towards large generators or generators of significant radionuclides (i.e., those that are most
limiting for the storage, treatment, or disposal facility).
The use of assessments (audits, reviews, or surveillances) to verify compliance of the waste
generators’ certification programs with acceptance requirements would need to be conducted on a
regular schedule commensurate with the frequency of waste generation and shipments. The
documentation of the verification process would include organization and authorities; frequency
of assessments; methods to be employed; the information that will be documented as a result; and
the qualifications of personnel.
Example: At the Waste Isolation Pilot Plant, there are no plans for sampling waste
packages upon receipt. Instead, WIPP has instituted a program in which generator site
waste certification programs are reviewed to determine whether they will produce waste
packages meeting the waste acceptance criteria. A Generator Site Certification Guide
describes what is entailed in obtaining an approved site certification program. Once a
site has developed its program, representatives from WIPP evaluate it, and if determined
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-41
7-09-99
to be acceptable, approve it. After a site’s certification program has been approved,
WIPP personnel rely on the combination of site certification that waste packages comply
with the site’s approved program and their own review of transfer documentation and
processes to assure that waste meets the waste acceptance criteria. Site certification
programs are re-evaluated annually to confirm that they are still adequate.
Non-Conforming Waste. Facilities receiving waste for storage, treatment, or disposal must have a
documented process to be used in the event a non-conforming waste is received. A non
conforming waste is a waste container or shipment which is certified by the generator as meeting
the waste acceptance requirements of the receiving facility, but which is found to be in violation
of the acceptance criteria during the facility’s waste receipt and inspection process. Facility
procedures need to address how non-conforming waste will be segregated from acceptable waste,
the process for notifying the sender of the non-conformance, and the acceptable methods for
dispositioning the non-conforming waste. The process includes prior notice to the sender of the
actions to be taken by the facility receiving the waste and the sender’s obligations, particularly
regarding the cost of the actions, to support the disposition of the non-conforming waste.
Section 342
Example: A transuranic waste storage facility’s waste acceptance procedures require
that non-conforming waste be segregated from conforming waste and isolated by a rope
barrier pending resolution of the non-conformance. The procedures further require
notification of the generator of the non-conformance and a resolution to be negotiated
with the generator. The process requires consideration of risk and cost in determining
the proper resolution.
Compliance with these requirements is demonstrated if there is a procedure or process for
evaluating and accepting incoming waste which ensures the acceptance criteria of the facility
receiving the waste are met by one or a combination of: (1) testing, sampling, and analysis of
representative samples of incoming waste upon receipt; (2) testing, sampling, and analysis of
samples of waste taken at the generator facility; (3) evaluation of testing, sampling, and analysis
of data provided by the generator; or (4) audits, reviews, or surveillances of generator waste
certification programs and characterization activities. Additionally, acceptable waste acceptance
requirements for a storage, treatment, or disposal facility will have documented procedures and
actions to be taken if a waste that does not conform to the waste acceptance criteria is received at
the facility.
Supplemental References:
1. CAO, 1997. Generator Site Certification Guide, Revision 1, DOE/CAO-95-2119, U.S.
Department of Energy, Carlsbad Area Office, Carlsbad, NM, August 1997.
Chapter III - Transuranic Waste Requirements
III-42 DOE G 435.1-1
7-09-99
2. CAO, 1996. Waste Acceptance Criteria for the Waste Isolation Pilot Plant, Revision 5,
DOE/WIPP-069, U.S. Department of Energy, Carlsbad Area Office, Carlsbad, NM, April
1996.
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-43
7-09-99
III. H. Waste Generation Planning.
The following requirements are in addition to those in Chapter I of this Manual.
(1) Life-Cycle Planning. Prior to waste generation, planning shall be performed
to address the entire life cycle for all transuranic waste streams.
Objective:
The objective of this requirement is to provide for the disposal of all transuranic waste that is
generated in the future by ensuring that prior to generating a new transuranic waste stream, the
specific waste management facilities necessary for safe management of the waste from the time it
is generated up to and including its disposal are identified; plans are developed for resolving issues
that prevent disposal, and for safe, long-term storage for transuranic waste with no path to
disposal; and sites are discouraged from generating transuranic waste that does not have an
identified path to disposal.
Discussion:
The Department intends on disposing of stored and future defense transuranic waste (the majority
of DOE transuranic waste) that meets waste acceptance requirements at WIPP. The subject
requirement is based on a recognition that protection of the public, workers, and the environment
is best assured if transuranic waste is generated with cognizance of its final disposition and of the
waste management facilities that are needed until the waste is disposed. In developing DOE O
435.1 and DOE M 435.1-1, the safety and hazards analysis identified long-term storage of waste,
and potential loss of characterization data from generators and the subsequent need for
recharacterization as weaknesses to be mitigated. Therefore, as part of the generator planning
requirements in DOE M 435.1-1, Section I.2.F.(7), specific requirements are identified for
planning the management of waste prior to its generation, and for approval to generate
transuranic waste streams with no identified path to disposal.
Section 343
Life cycle planning for all transuranic waste. Planning prior to generating transuranic waste is
primarily intended to address newly-generated waste streams. Life-cycle planning for waste that
has been generated and continues to be generated is documented through the Site-Wide Waste
Management Program required in DOE M 435.1-1, Section I.2.F.(1). The following discussion
describes the types of life cycle planning need. The information needed is influenced by the fact
that, on the implementation date of the Order, the transuranic waste will be in one of three stages
of its life-cycle: (1) waste generated in the past (in storage); (2) waste being generated at present;
and (3) wastes not yet generated (future wastes); and will either have an identified path to
disposal, or will not.
Chapter III - Transuranic Waste Requirements
III-44 DOE G 435.1-1
7-09-99
Therefore, from a waste generation planning perspective, there are six different “states” of
transuranic waste, depending on when the waste was or is generated and whether it has or will
have a path to disposal. The following paragraphs explain the recommended life cycle
information for these different transuranic wastes.
Transuranic Waste With a Path to Disposal
Generated currently - The life-cycle information for currently generated transuranic waste
with an identified path to disposal includes a description of the management steps for the
waste as discussed in guidance for the Site-Wide Radioactive Waste Management
Program.
Generated in the future (from a new process) - The life-cycle information for transuranic
waste with an identified path to disposal that is generated from a new process includes a
description of the management steps for the waste as discussed in guidance for the
Site-Wide Radioactive Waste Management Program.
Generated in the past (in storage) - In addition to the basic information on management
steps, life cycle information for transuranic waste with a path to disposal that is in storage
(due to budget constraints, delays due to regulatory matters or management decisions, or
for other reasons) includes a schedule for achieving disposal. For transuranic waste in
earthen-covered storage, the retrieval plan required by the storage requirements (DOE M
435.1-1, Section III.N) can be used to meet this requirement provided it has a schedule.
Transuranic Waste Without a Path to Disposal
Generated in the past (in storage) - The life-cycle information for transuranic waste in
storage as of the issuance of DOE O 435.1 for which there is not an identified path to
disposal includes the basic information on the management steps for the waste which can
be identified, a discussion of the issues that hinder disposal of the waste, and the plans and
schedule for achieving resolution of the issues.
Generated in the future (from a new process) - The life-cycle information for transuranic
waste without an identified path to disposal which is generated from a new process
includes the basic information on the management steps for the waste which can be
identified, a discussion of the issues that hinder disposal of the waste, and the plans and
schedule for achieving resolution of the issues. This information will be assembled in the
course of getting the generation of the waste approved in accordance with the process
required in DOE M 435.1-1, Section I.2.F.(19), and is also discussed in the next section of
this guidance.
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-45
Section 344
7-09-99
Generated currently - The life-cycle information for transuranic waste without an
identified path to disposal includes the basic information on the management steps for the
waste which can be identified, a discussion of the issues that hinder disposal of the waste,
and the plans and schedule for achieving resolution of the issues. The intent of the
requirement is not to ensure that these waste streams receive approval for generation in
accordance with General Requirement I.2.F.(19). However, the life-cycle planning
information needs to address the continued generation of this waste. The life-cycle
planning information for continuing to generate a no path forward waste needs to include
consideration of the necessity to generate the waste, an understanding of what prevents
disposal of the waste, the needed capacity and capabilities for continued storage of the
waste, and the plans for future disposal of the waste. Discussions would also be included
on any alternatives to the process that generates the no path forward waste that have been
considered.
Providing the life cycle information discussed above for waste streams already being generated is
relatively straightforward. For most transuranic wastes, the information already exists and has
been utilized for other documents such as the Programmatic Environmental Impact Statement and
the Baseline Disposition Maps. To the extent that existing documentation includes the specified
information, they may be used to meet the life cycle planning requirement.
Example: A transuranic waste generating facility operating at Site A continues to
operate with no alterations. The facility generates the same transuranic waste streams it
has been generating for years, and none of them are waste streams without a path to
disposal. The life-cycle information about transuranic waste generated at this facility is
included in the current waste inventories and capacities section of the Site A Radioactive
Waste Management Plan, and no technical or programmatic issues are included in the
Plan concerning these waste streams.
Waste generator planning prior to generation. Planning, prior to generating transuranic waste
(subrequirement H.(1)), is intended to address transuranic waste streams that do not already exist.
Transuranic waste streams that are first generated after issuance of the Order are subject to this
requirement. Waste generator planning is a component of the waste generator program required
in I.2.F.(7) of the General Requirements Chapter of DOE M 435.1-1. Waste generator planning
activities need to be integrated in the generator program with waste characterization, certification,
and transfer activities.
Example: A previously operating high-level waste treatment facility has been shut down
for eighteen months and is to be restarted. Based on past experience, it is known that
contamination control activities in the building will result in the generation of a
transuranic waste stream. As part of the generation planning in support of the restart,
plant personnel must evaluate the life-cycle of all of the waste streams (high-level,
Chapter III - Transuranic Waste Requirements
III-46 DOE G 435.1-1
7-09-99
Section 345
transuranic and low-level) that will come from the facility. For the transuranic waste,
personnel confirm that there is a facility that can accept the waste for storage and that
because the waste is from a defense-related activity, it is eligible for disposal at the
Waste Isolation Pilot Plant. Based on the WIPP waste acceptance criteria and
communications with WIPP personnel, the determination is made that the waste will meet
the waste acceptance criteria and that adequate capacity will be available. From the
perspective of transuranic waste life-cycle planning there are no issues associated with
the restart.
Generator planning addresses the life-cycle of the waste to disposal, including all interim steps of
waste management. This can be accomplished by preparing a waste stream profile and reviewing
it with the facility(ies) that will manage the waste. The waste stream profile format used needs to
be consistent with the needs of the storage, treatment, and/or disposal facilities that will be
involved in managing the waste stream. An example of a waste stream profile form is included as
Figure III.H.1 at the end of this section of guidance. The waste generator confirms with each
storage, treatment, and disposal facility that will be used, that based on the current knowledge of
the waste stream characteristics, and planned facility capacity, the waste stream can be managed
by the facility. It is therefore conceivable that a generator may have to interface with multiple
facilities (e.g., a storage and/or treatment facility in addition to the disposal facility) to ensure that
the waste can be managed.
Example: In the previous example, the treatment facility confirmed with the storage
facility that based on the expected generation rate of the transuranic waste and the
expected commencement of shipments of waste to WIPP that there was sufficient storage
capacity to handle the transuranic waste stream.
The determination of whether a transuranic waste stream has an identified path to disposal is
based on the availability and capacity of existing or planned facilities and operations. A planned
facility is considered to be available if it has been authorized (e.g., a line item in a Congressional
appropriation or equivalent approval for design and construction). A facility is not considered
available if it is not authorized to accept or manage a particular waste type or concentration. If a
planned facility is designated in the planning information, then the planning information also needs
to address the schedule for when the facility will be operational, and the management steps that
will be taken for waste designated for that facility until it becomes operational.
For purposes of planning for disposal of a transuranic waste stream, a facility or capabilities that
are part of a program or strategic plan, but have not been authorized are not considered available.
If a planned or available facility is canceled, the generator site needs to revise the planning for the
life-cycle of the transuranic waste, an alternate path to disposal needs to be identified and
documented, or approval to generate the transuranic waste needs to be obtained from the
cognizant Field Element Manager as required by DOE M 435.1-1, Section I.2.F.(19).
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-47
7-09-99
Section 346
The generator is responsible for ensuring that transuranic waste is not generated unless the
life-cycle management, including disposal of the waste, has been considered. However, as
discussed below, it is not the objective of this requirement to prohibit, under all conditions, the
generation of transuranic waste that does not have an identified path to disposal. In meeting the
DOE O 435.1 planning requirements, it is appropriate for waste management organizations to
provide assistance to the generator in determining the waste management path, particularly in
cases where the waste management organization may utilize offsite treatment, storage, or disposal
facilities.
Compliance with this planning requirement is demonstrated by the individual sites establishing a
process for evaluating the life-cycle of low-level waste prior to its generation, including the
identification of low-level wastes with no path to disposal and appropriate records justifying the
newly generated low-level waste stream(s), and site personnel possessing planning information
showing the location(s) where low-level waste will be stored, treated, and/or disposed along with
a confirmation that the personnel managing the facilities agree that the low-level waste may be
managed at those facilities.
Supplemental References:
1. DOE, 1998. Accelerating Cleanup: Paths to Closure, DOE/EM-0362, U.S. Department
of Energy, Washington, D.C., June 1998.
III. H.(2) Waste With No Identified Path to Disposal. Transuranic waste
streams with no identified path to disposal shall be generated only in
accordance with approved conditions which, at a minimum, shall
address:
(a) Programmatic need to generate the waste;
(b) Characteristics and issues preventing the disposal of the waste;
(c) Safe storage of the waste until disposal can be achieved; and
(d) Activities and plans for achieving final disposal of the waste.
Objective:
The objective of this requirement is to ensure that prior to generation of a new transuranic waste
streams with no path to disposal, the need to generate the waste is carefully considered and plans
Chapter III - Transuranic Waste Requirements
III-48 DOE G 435.1-1
7-09-99
for safe long-term storage and for resolving issues that prevent disposal of the wastes are
developed.
Discussion:
There are instances where programmatic needs may necessitate the generation of transuranic
waste without an identified path to disposal. In these instances, the Field Element Manager must
ensure development of a process for identifying generation of transuranic waste with no path to
disposal and approving the conditions under which such transuranic waste can be generated (DOE
M 435.1-1, Section 1.2.F.(19)). The process of identifying waste with no path to disposal and
establishing conditions for its generation is intended to raise to the attention of DOE management
that a long-term commitment is being made with the generation of such a waste, including
prolonged storage of this waste and resolving those issues that prevent the waste from being
disposed.
Example: Through generation planning it is determined that an Office of Science project
will generate a small volume of non-defense transuranic waste. The generator contacts
the waste management organization and learns that because the waste is non-defense it is
not eligible for WIPP disposal. Working together, generator and waste management
personnel determine there is no way to avoid creating the waste if the project proceeds,
however, the waste management organization does have long-term storage capacity
available. The Field Element Manager determines that due to the importance of the
project, and based on plans that the Department is pursuing to resolve disposal of
non-defense transuranic waste that generating the transuranic waste is acceptable.
Section 347
The minimum conditions for generating a waste without an identified path to disposal are
identified in this requirement. They include various evaluations and considerations that involve
both the waste generating and waste management organizations. The decision to proceed with
the activity generating the wastes is made considering the factors discussed below.
Programmatic need to generate the waste. There must be a clear identification of the
programmatic mission being served that results in the generation of transuranic waste with no
identified path to disposal. Alternate means of accomplishing the mission without generating the
waste should be discussed. These could include use of alternative materials to achieve the
mission, use of different processes, or substitution of chemicals other than the ones originally to
be used.
Characteristics and issues preventing the disposal of the waste. The reasons that the transuranic
waste cannot be disposed of must be identified. These may be technical or programmatic reasons.
For example, if a waste needs to be treated in order to meet a disposal facility waste acceptance
criteria and an appropriate treatment facility is not available, the lack of treatment would be
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-49
7-09-99
identified as the reason the waste does not have a path to disposal. Identifying the characteristics
and issues preventing disposal is necessary to support the development of plans for achieving
disposal.
Safe storage of the waste until disposal can be achieved. Since the waste cannot be disposed of
pending the resolution of programmatic or technical issues, facilities must be available for safe
storage. In order to evaluate the ability to provide for the storage of the waste, there needs to be
an estimate of the amount of the waste that will be generated, as well as an estimate of the time
necessary to keep the waste in storage. Identification of the requirements for safe storage and
acceptable storage facilities is a prerequisite to generating the waste so that unique or risky
aspects that may make long-term storage problematic can be identified. In addition, treatment
necessary to comply with RCRA, if applicable, should be identified.
Activities and plans for achieving final disposal of the waste. The decision to generate waste with
no identified path to disposal must be based on a plan to eventually achieve disposal. The plan to
achieve disposal of the waste needs to identify the activities being pursued to resolve issues
preventing disposal and a schedule for their resolution. The activities described may be fairly
detailed if the problems are technical and involve only one waste stream at a site. In other cases
involving programmatic issues, or which involve several waste streams at several sites, the
activities and schedules to resolve issues may be less certain because they are dependent on other
internal or external organizations. For example, resolution of the issue of disposal of non-defense
transuranic waste may require action external to DOE (e.g., legislation). Sites should defer to the
complex-wide plans for addressing disposal of non-defense transuranic waste in lieu of developing
individual plans and schedules.
Section 348
Example 1: Approval is given to generate transuranic waste with no path to disposal.
The waste is not acceptable for disposal at WIPP because it is reactive (EPA hazardous
waste code D003). The approval to generate the waste is based on the generator
providing plans to develop the treatment capabilities necessary to make the waste
acceptable for WIPP disposal. These plans should be detailed, identifying the schedule
for conducting the studies, tests, and engineering, as well as regulatory activities,
necessary to allow the waste to be treated.
Example 2: A non-defense transuranic waste which is otherwise acceptable for WIPP
disposal may require a programmatic decision by DOE Headquarters and legislative
action to resolve disposal issues. The site plan for addressing this issue should identify
the data collection and options analyses to be performed by the site and address how they
fit with the actions being taken by the Complex-Wide Transuranic Waste Management
Program (see DOE M 435.1-1, Section III.C).
Chapter III - Transuranic Waste Requirements
III-50 DOE G 435.1-1
7-09-99
If the assumptions for the planned management of the waste are adversely impacted (e.g., as a
result of testing, design, funding profile, DOE policy) they should be updated. Minor updates to
the assumptions and changes to the planned management of the waste would not be a basis for re
evaluating the generation of the waste as long as the overall plan remains essentially unchanged.
However, major changes to the plan (e.g., changes in decisions for developing a treatment facility
or disposal facility to handle the waste) must result in a re-evaluation of the acceptability of
continuing to generate the transuranic waste. All changes in plans for resolving issues preventing
disposal should be forwarded to the Headquarters Office of Waste Management so their impact
on the Complex-Wide Transuranic Waste Management Program can reflected in the program plan
(see DOE M 435.1-1, Section I.2.D.(1)).
Compliance with requirement is demonstrated by the waste generation organization having
documentation concerning the decision to generate a transuranic waste stream that does not have
an identified path to disposal. This documentation needs to include the cognizant Field Element
Manager or designee approval to generate the waste, an explanation of the need for the process
that generates the transuranic waste, a discussion of the reason it cannot be disposed of, the
proposed management plan for the waste, and an up-to-date schedule of activities being pursued
to resolve constraints to the disposal of the subject waste. Consistent with the use of a graded
approach for applying DOE M 435.1-1 requirements, the schedule and plans for disposing of non-
defense waste can defer to the complex-wide resolution of the issue.
Supplemental References:
1. CAO, 1996. Waste Acceptance Criteria for the Waste Isolation Pilot Plant,
DOE/WIPP-069, Revision 5, U.S. Department of Energy, Carlsbad Area Office, Carlsbad,
NM, April 1996.
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1
7-09-99
III-51
WASTE STREAM PROFILE FORM Page 1 of 3
Waste Stream Profile Number:
Technical contact:
Technical contact phone number:
Did your facility generate this waste? ~~ Yes
Generator site name:
Generator site EPA ID :
~~ No
If no, provide the name and EPA ID of the original generator:
Waste Stream Information
ID: Summary Category:
Waste Stream Name :
Description from the TWBIR (if available):
Section 349
Defense TRU Waste?: ~~ Yes ~~ No ~~ RH
Concentration of PCBs:
Number of SWBs Number of Drums Number of Canisters
Data package numbers supporting this waste stream characterization:
List applicable EPA Hazardous Waste Numbers:
List the concentrations of VOCs listed in Table 4-2:
List average isotope ratios:
List the weight fraction of CRP:
Acceptable Knowledge Information
For the following, enter supporting documentation used (i.e., references and dates)
C Map of site:
C
C Description of operations that generate waste:
C Waste identification/categorization schemes:
C Types and quantities of waste generated:
C Correlation of waste streams generated from the same building and process, as appropriate:
CH-TRU or RH-TRU?: ~~ CH
Required Program Information
Facility mission description:
Waste certification procedures:
Figure III.H.1. Example Transuranic Waste Stream Profile Form
Chapter III - Transuranic Waste Requirements
C
III-52 DOE G 435.1-1
7-09-99
WASTE STREAM PROFILE FORM Page 2 of 3
Required Waste Stream Information
C Area(s) and building(s) from which the waste stream was generated:
C Waste stream volume and time period of generation:
C Waste generating process description for each building:
C Process flow diagrams:
C Material inputs or other information identifying chemical/radionuclide content and physical waste
form:
C Which Defense Activity generated the waste: (check one)
~~ Weapons activities including defense inertial confinement fusion
~~ Naval Reactors development
~~ Verification and control technology
~~ Defense research and development
~~ Defense nuclear waste and material by products management
~~ Defense nuclear materials production
~~ Defense nuclear waste and materials security and safeguards and security investigations
Supplemental Documentation
C Process design documents:
C Standard operating procedures:
C Safety Analysis Reports:
C Waste packaging logs:
C
C Site data bases:
C
C
C
C Material safety data sheets:
Test plans/research project reports:
Information from site personnel:
Standard industry documents:
Previous analytical data:
C Sampling and analysis data from comparable/surrogate Waste:
C Laboratory notebooks:
Figure III.H.1. Example Transuranic Waste Stream Profile Form (cont.)
Chapter III - Transuranic Waste Requirements
C
DOE G 435.1-1
7-09-99
III-53
WASTE STREAM PROFILE FORM Page 3 of 3
Sampling and Analysis Information (1)
For the following, when applicable, enter procedure title(s), number(s) and date(s).
C Radiography:
C Visual Examination:
I hereby certify that I have reviewed the information in this Waste Stream Profile Form and it is
complete and accurate to the best of my knowledge. I understand that this information will be made
available to regulatory agencies and that there are significant penalties for submitting false information,
including the possibility of fines and imprisonment for knowing violations.
Signature of site project manager Printed name and title Date
Note: (1) If radiography, visual examination, headspace gas analysis, and/or homogeneous
solids/soils/gravel sample analysis were used to determine EPA Hazardous Waste Codes
attach signed summary reports documenting this determination.
Headspace Gas Analysis
VOCs:
Homogeneous Solids/Soils/Gravel Sample Analysis
Metals:
PCBs:
VOCs:
Nonhalogenated VOCs:
Semi-VOCs:
Other (specify):
Waste Stream Profile Form certification:
Section 350
Figure III.H.1. Example Transuranic Waste Stream Profile Form (cont.)
Chapter III - Transuranic Waste Requirements
III-54 DOE G 435.1-1
7-09-99
III. I. Waste Characterization.
Transuranic waste shall be characterized using direct or indirect methods, and the
characterization documented in sufficient detail to ensure safe management and
compliance with the waste acceptance requirements of the facility receiving the
waste.
Objective:
The objective of this requirement is to ensure that sufficient knowledge of transuranic waste’s
characteristics (e.g., chemical, physical, radiological) is available to protect workers handling the
waste and to support effective decision-making for its management. This information is to be
maintained from generation, through storage and treatment in sufficient detail to ensure that the
requirements of subsequent treatment and storage facilities, transportation regulations, and the
disposal requirements for transuranic waste will be met.
Discussion:
The Radioactive Waste Management Manual assigns the Field Element Manager the
responsibility of ensuring development, approval, and implementation of a program that addresses
the responsibilities of waste generators, including waste characterization (DOE M 435.1-1,
Section I.2.F.(7)). The characterization data acquired during generation, storage, and after
treatment of transuranic waste need to be reliable and in sufficient detail to ensure subsequent
management can be conducted safely and to meet the waste acceptance requirements of all
subsequent receiving facilities. Accurate characterization of transuranic waste is essential to:
1) waste planning by generators, as required by DOE M 435.1-1, Section III.H; 2) waste
certification by generators and other senders of waste, as required by DOE M 435.1-1, Section
III.J; 3) waste transfers by generators and other senders of waste, as required by DOE M 435.1
Section III.K; and; 4) waste evaluation and acceptance by receivers of waste, as required by DOE
M 435.1-1, Section III.G.
In conducting the analyses for development of the DOE M 435.1-1, characterization was
identified as necessary to ensuring the safe management of waste from generation through
disposal. Waste characterization is defined (DOE M 435.1-1, Definitions) as:
“The identification of waste composition and properties, such as by review of acceptable
knowledge (which includes process knowledge), or by nondestructive examination,
nondestructive assay, or sampling and analysis, to comply with applicable storage,
treatment, handling, transportation, and disposal requirements.”
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-55
7-09-99
Accurate waste characterization is necessary so that the waste and waste containers are
compatible and worker handling of waste containers can be performed safely. All information
necessary for personnel to safely handle a container of transuranic waste needs to be known at all
times during the life-cycle of the waste.
Waste characterization is a tool for gathering information that supports defensible decisions
regarding safety, process, environmental and compliance matters in the management of
transuranic waste. The significance of the waste management decision will guide the graded
application of this requirement, as well as the more detailed characterization requirements
addressed in subsequent sections of this guidance. These subsequent sections address application
of a data quality objectives process to guide characterization (Section III.I.(1)) and minimum
characterization requirements (Section III.I.(2)).
Section 351
Use of Direct and Indirect Methods. Waste managers are to characterize transuranic waste using
an appropriate combination of direct and indirect methods. The appropriate method for
characterizing waste depends on the parameter being measured, the hazards associated with
acquiring the information, and the amount and quality of the data needed as determined through a
data quality objectives or similar process.
Direct methods of characterizing waste can be used to established certain physical and chemical
attributes as well as radiological characteristics. The most common direct methods for
characterizing the chemical and/or radiological characteristics are sampling and laboratory
analyses and certain nondestructive evaluation techniques (e.g., real-time radiography). Direct
characterization methods are conducted in accordance with the quality assurance program and
plan governing the site and laboratory facilities.
Indirect methods of characterization use non-destructive examination techniques and acceptable
knowledge to replace, supplement, and/or initially provide data that might otherwise be collected
by direct, intrusive characterization of the waste. In the safety and hazard analysis performed in
support of development of DOE M 435.1-1, the use of indirect methods was identified as an
appropriate means of characterizing waste and at the same time complying with the as low as
reasonably achievable (ALARA) principle for keeping radiation exposures to a minimum. An
additional benefit of characterizing transuranic waste by the use of indirect methods is the
avoidance of the generation of waste associated with sample materials, and laboratory equipment
and expendables.
In order for indirect methods of transuranic waste characterization to serve their purpose of
providing information necessary for the safe management of waste, the data need to be sufficiently
accurate. The level of accuracy is determined through application of data quality objectives, or
comparable process. Consistent with the data quality objectives, correlations demonstrating that
data provided by indirect methods are representative of the actual waste may need to be
Chapter III - Transuranic Waste Requirements
III-56 DOE G 435.1-1
7-09-99
supported through the application of direct methods. The methodology could employ a number
of techniques, some of which involve some direct sampling and analysis of the waste stream. The
following guidance paragraphs discuss different indirect methods.
Similar to the EPA and NRC guidance on characterizing mixed waste, DOE endorses the use of
indirect methods such as the use of “acceptable” or “waste knowledge” for characterizing
physical, chemical, RCRA-regulated, and radioactive components of waste. The term “acceptable
knowledge” (or “waste knowledge”) includes process knowledge; records of analyses performed
prior to the effective date of a requirement; or a combination of process knowledge and previous
records, supplemented with chemical analyses (NRC/EPA, 1997). Process knowledge refers to
detailed information on processes that generate waste subject to this requirement or information
on processes similar to those which generated the waste being characterized.
Section 352
Acceptable knowledge characterization of transuranic waste is based on an understanding of the
materials and processes used to generate the waste, or analytical data obtained from the process
or waste stream or both. Acceptable knowledge also includes information regarding the source of
the waste stream, the physical form and materials comprising the waste, the chemical constituents
of the waste, and the nature of the radioactivity present. Acceptable knowledge may be used to
describe transuranic waste if the source information is consistent, defensible, and auditable.
While the development of a process for identifying and documenting transuranic waste acceptable
knowledge is not dictated by this requirement, the following guidance provides an overview of
elements of an acceptable process for assembling acceptable knowledge documentation:
C Acceptable knowledge is compiled in an auditable record.
C Correlations within waste streams in terms of time of generation, waste generating
processes, analytical data, and site-specific facilities are clearly described.
C A reference list of applicable documents, databases, quality control protocols, and
other sources of information that support the acceptable knowledge information is
prepared.
C Procedures which outline the methodology that is to be used to identify and
assemble auditable acceptable knowledge records, including the origin of the
documentation, how the assembled information was or will be used, and any
limitations associated with the information.
Characterization data gained through acceptable knowledge must be within the acceptable range
of certainty and precision identified by the data quality objectives or similar process. Additionally,
the effects of time-dependent processes must either be negligible or predictable. If acceptable
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-57
7-09-99
knowledge is supported by the collection, analysis, and comparison of statistically valid samples
with the acceptable knowledge records, periodicity of sampling and analysis should correlate with
the nature of any changes in the process creating the waste or with changes that are being
documented in characterization data.
Non-destructive examination and assay techniques use methods such as passive-active neutron
assay, high resolution gamma ray spectroscopy, and thermal neutron capture to non-destructively
collect data relating to the radionuclide constituents in the waste. Acceptable performance of
assay techniques is determined through measurement of known standards and comparison to
established quality assurance objectives of the applicable characterization program. A process,
similar to the one discussed above regarding acceptable knowledge, needs to be established and
documented in site procedures that outline the exact nature of the acceptable use of non
destructive examination techniques for providing characterization information on waste.
Another indirect method of providing radionuclide characterization data is through the use of a
known relationship, or scaling factors, between a measured radionuclide or a dose rate and the
radionuclide(s) of interest. As discussed above for acceptable knowledge and non-destructive
examination techniques, use of scaling factors must be correlated with actual data.
Section 353
The use of scaling factors is generally established by an initial characterization that provides a
statistical basis for use of the scaling factors. As with any indirect method, the characterization
program needs to include confirmatory measurements. The frequency of the confirmatory
measurements is to be based on the consistency of the process generating the waste. Additionally,
the history of previous confirmatory measurements may also influence the frequency of future
confirmatory measurements with results that are very consistent providing justification for less
frequent confirmatory measurements.
Example: A waste stream from an actinide processing building is sampled and analyzed
and determined to be composed of three primary nuclides: Pu-239, Am-241, and Pu
238. The samples are found to contain the three radionuclides in essentially the same
ratio. The process is known to be uniform and is therefore expected to generate similar
concentrations in the waste stream as the facility is operated. Therefore, the contents of
future waste containers are routinely characterized based on a gamma energy analysis
which detects gamma radiation from the Am-241 and Pu-238. The characterization
program requires the collection and full analysis of samples once a month to confirm
that the ratio of the three radionuclides falls within an acceptable range (based on
application of the data quality objectives process).
Characterization Documentation. The requirement states that characterization data shall be
documented in sufficient detail to enable the waste acceptance requirements of the receiving
Chapter III - Transuranic Waste Requirements
III-58 DOE G 435.1-1
7-09-99
facility to be met. The following elements are considered essential to this process for acquiring
and controlling characterization data:
Organization(s) and Responsibilities - Identification of the organizations involved and
responsible for characterization of transuranic waste.
Quality Assurance - Characterization data need to be subjected to a quality assurance
program and the program that applies needs to be identified and documented.
Procedures - The process for obtaining waste characterization data is formalized in
procedures which describe to the user the steps that are to be followed and the
administrative process for ensuring the data are of the quality needed. Topics that need to
be proceduralized include the processes for sampling, packaging, transportation,
laboratory analysis, and data control.
Procurement/Purchasing Controls - The procurement and/or purchasing of items or
services that are significant to characterizing transuranic waste are controlled and
documented. Such procurement includes the purchase of sampling equipment and sample
transport containers, as well as services such as laboratory analyses (onsite or offsite). As
dictated by the type of procurement, the documentation needs to include (or reference) the
technical specifications for the item/service being procured, identification of quality
assurance requirements including any required inspections, specifications of
documentation requirements (e.g., certification of compliance or conformance, laboratory
analytical results), and a statement ensuring access to the provider’s facilities as necessary
to perform audits and inspections. The characterization data need to be traceable through
the provider’s process of generating them and verifying their accuracy.
Section 354
Document/Data Change Control - Records that contain characterization data, whether
they have been generated through sampling and analysis, nondestructive assay, or
acceptable knowledge, need to be controlled. In addition, the waste characterization
procedures and quality assurance program documentation are subject to document
control. Document and data control need to include review, approval, and distribution to
designated recipients (users), and a controlled process for making revisions to documents
or data. Existing document and data control programs at a site may be adequate to
provide the necessary controls for documents related to transuranic waste characterization
data, but will need to be reviewed to ensure the objectives of DOE M 435.1-1
requirements are met.
Training - Characterization data are generated and managed only by personnel that are
properly trained to recognize the significance of the data. Generally, training of laboratory
personnel will be adequate to support transuranic waste characterization, but needs to be
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-59
7-09-99
reviewed versus the goals of the characterization. Other staff managing and using
characterization data need to understand what is to be done with the data (i.e., what
decisions are to be made) once data are collected.
Records - Waste characterization records include those that are necessary to meet the
waste acceptance requirements of receiving facilities, and as specified by the waste
certification program DOE M 435.1-1, Section III.J.
As noted above, existing programs at a site may provide the framework within which the elements
of waste characterization can be addressed (e.g., quality assurance, training, document control).
The waste acceptance requirements of a facility to which the waste is sent also may impose
additional requirements on what is to be included in the waste characterization data. The waste
acceptance requirements for the receiving facility include specific quality assurance,
administrative, or documentation requirements so that waste characterization data are acceptable
to the facility.
Example: A site is preparing to transfer waste to WIPP for disposal. The waste
characterization program at the site normally generates data on the physical, chemical,
and radiological characteristics of the waste. However, additional requirements have
been established for the characterization of transuranic waste in order to transfer it to
the WIPP for disposal. In addition to what is normally thought of as characterization
data (chemical and radiological), the waste acceptance criteria require, among other
information, the waste packages to be characterized in terms of their thermal power and
decay heat.
Compliance with this requirement is demonstrated by a program for documenting and the
existence of records that document the process for acquiring and verifying the validity of
transuranic waste characterization data acquired through the use of direct or indirect methods.
Supplemental References:
1. CAO, 1996. Waste Acceptance Criteria for the Waste Isolation Pilot Plant,
DOE/WIPP-069, Revision 5, U.S. Department of Energy, Carlsbad Area Office, Carlsbad,
NM, April 1996.
2. EPA, 1994. Guidance for the Data Quality Objectives Process, EPA QA/G-4,
U.S. Environmental Protection Agency, Washington, D.C., September 1994.
3. NRC/EPA, 1997. “Joint NRC/EPA Guidance on Testing Requirements for Mixed
Radioactive and Hazardous Waste,” Federal Register, Vol. 62, No. 224, U.S.
Section 355
Chapter III - Transuranic Waste Requirements
III-60 DOE G 435.1-1
7-09-99
Environmental Protection Agency and U.S. Nuclear Regulatory Commission, November
20, 1997.
III. I.(1) Data Quality Objectives. The data quality objectives process, or a
comparable process, shall be used for identifying characterization
parameters and acceptable uncertainty in characterization data.
Objective:
The objective of this requirement is to invoke a process for determining the type, quantity, and
quality of characterization data needed to support the safe management of transuranic waste so as
to ensure that needed data are acquired, the data meet the objectives they are being collected for,
and resources are not wasted on unnecessary, incomplete or unusable data collection efforts.
Discussion:
The type, quantity, and quality of characterization data obtained for the safe management of
transuranic waste need to be consistent with the purpose for which the characterization
information will be used. The uses of transuranic waste characterization data include complying
with storage, treatment, and disposal facilities’ waste acceptance requirements; determining
radiation shielding and other protective measures; evaluating compliance with processing
requirements; and meeting legislative or regulatory commitments. This requirement is included in
DOE M 435.1 to ensure that the appropriate characterization data to support the safe
management of transuranic waste are generated. The requirement is intended to promote a
structured process for the collection and use of transuranic waste characterization data and to
avoid the collection of data that is neither necessary nor defensible.
Input from various waste management organizations and interested groups is necessary to
establish a clear understanding of the characterization data needs and the level of data quality that
is acceptable for making transuranic waste management decisions. The current requirement
invokes the use of a structured process for determining the type, quantity, and quality of
characterization data needed. Such a process, called a data quality objectives process, has been
developed by the Environmental Protection Agency and is documented in Guidance for the Data
Quality Objectives Process. Application of the EPA process and use of the guidance for the use
of the data quality objectives process is an acceptable method of meeting this requirement.
However, use of other comparable processes that employ a structured approach to yield similar
results is also acceptable.
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-61
7-09-99
The objectives of applying a structured process such as the data quality objectives process are to:
C manage and control the risks of making incorrect decisions;
C determine the data required to support making specific decisions;
C determine the type and quality of required data;
C allow stakeholders, decision makers, data users, and relevant technical experts to
participate in planning and assessment;
C determine the quantity, location, and type of samples required;
C quantify the uncertainty in data through development of statistical sampling plans;
and
C reduce overall costs by identifying resource-efficient sample collection and
analytical methods by optimizing the sample and analysis plans.
Section 356
The data quality objective process is a strategic planning approach based on the scientific method
that is used to prepare for a data collection activity. The value of using this process to develop
transuranic waste characterization parameters is that it reduces radiation exposure and saves
resources by making characterization data collection operations more resource-effective; enables
characterization data users and others to participate in characterization data planning; and
provides a structured method for defining characterization data performance requirements, i.e.,
quality.
To foster the development and implementation of an effective data quality objectives or similar
process, individuals are assigned responsibility for specific activities for each application of the
process. Key activities of the process include:
• preparing the data quality objectives documentation;
• identifying stakeholders;
• identifying technical experts;
• ensuring opportunities for input and coordinating stakeholder and technical experts
into the data quality objective process;
• reviewing and commenting on the developed data quality objectives; and
Chapter III - Transuranic Waste Requirements
III-62 DOE G 435.1-1
7-09-99
• approving the data quality objectives documents.
A more detailed description of the assignment of specific responsibilities for implementing a data
quality objectives or similar process is presented in the Hanford “Data Quality Objectives
Procedure” (see reference 2).
The data quality objectives process consists of seven steps. The output from each step influences
the choices that will be made later in the process. Even though the data quality objectives process
is depicted as a linear sequence of steps, in practice it is iterative; the outputs from one step may
lead to a reconsideration of prior steps. This iteration is encouraged since it will ultimately lead to
a more efficient data collection design. During the first six steps of the process, a team of
process-cognizant personnel develop decision performance criteria (i.e., data quality objectives)
that will be used to develop the data collection design.
The final step of the process involves developing the data collection design based on the data
quality objectives developed in the first six steps. The first six steps need to be completed before
the team attempts to develop the data collection design because the design is dependent on a clear
understanding of the first six steps taken as a whole.
Following is a listing and brief description of each of the seven steps. This is followed by an
example of how the data quality objectives process can be applied to transuranic waste
characterization.
1. State the Problem – Concisely describe the problem to be studied. Review prior
studies and existing information to gain a sufficient understanding to define the problem.
2. Identify the Decision – Identify what questions the study will attempt to resolve, and
what actions may result.
3. Identify the Inputs to the Decision – Identify the information that needs to be obtained
and the measurements that need to be taken to resolve the decision statement.
4. Define the Study Boundaries – Specify the time periods and spatial area to which
decisions will apply. Determine when and where data should be collected.
5. Develop a Decision Rule – Define the statistical parameter of interest, specify the
action level, and integrate the previous data quality objective outputs into a single
statement that describes the logical basis for choosing among alternative actions.
Section 357
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-63
7-09-99
6. Specify Tolerable Limits on Decision Errors – Define the decision maker’s tolerable
decision error rates based on a consideration of the consequences of making an incorrect
decision.
7. Optimize the Design – Evaluate information from the previous steps and generate
alternative data collection designs. Choose the most resource-effective design that meets
all data quality objectives.
Example: In order to comply with current legislation, the Waste Isolation Pilot Plant has
established a waste acceptance criterion that transuranic waste must exceed 100 nCi
(3700 Bq) of alpha-emitting transuranic nuclides per gram of waste. At the CST Site
waste management personnel worked with the WIPP staff, site laboratory personnel, and
members of the local citizens advisory board to address the transuranic waste
determination issue. The question is formulated as, what are the analytical criteria waste
must meet in order to be categorized as transuranic waste? The answer to this question
makes a significant difference in cost and in the amount of waste that will be shipped to
WIPP, and conversely, the amount of waste that will be designated as low-level waste and
disposed of near surface. From the perspective of worker protection, it was recognized
that a non-intrusive analysis technique was preferred. The CST Site personnel
anticipated that most of the waste would be around 200 nCi/g (7400 Bq/g) so they opted
for a two-tiered characterization approach which employs a fast, inexpensive protocol to
make an initial screening of waste and a slower, more expensive protocol to characterize
waste that fails the initial screening. The data quality objective is:
Waste containers will be categorized as transuranic waste if the results of the
non-destructive analysis exceed the minimum detectable concentration for a
particular assay system and protocol, and the results exceed 100 nCi/g. Waste
containers will be initially analyzed using a system and protocol that has a
minimum detectable concentration of 150 nCi/g. If the result does not exceed
150 nCi/g, the waste container will be analyzed using a system and protocol with
a minimum detectable concentration of no more than 50 nCi/g.
Applying this data quality objective, a waste container is assayed as having 175 nCi/g
using the first system (150 nCi/g minimum detectable concentration) and categorized as
transuranic waste. Another waste container assayed as having 125 nCi/g using the first
system. Even though the assay exceeds 100 nCi/g, the categorization would be
indeterminate because the assayed value is less than the minimum detectable
concentration. An assay of the container using the second system (50 nCi/g minimum
detectable concentration) yields a result of 110 nCi/g. Based on the second measurement
the waste is categorized as transuranic.
Chapter III - Transuranic Waste Requirements
III-64 DOE G 435.1-1
7-09-99
The above description of the use of the data quality objectives process, and the example, are
provided as an introduction to the process. A more detailed description of the process can be
found in the referenced EPA guide. The data quality objectives process is most useful during the
planning stages of identifying transuranic waste characterization and uncertainty parameters, i.e.,
before the data are needed and collected. The value of the process is diminished significantly if
the characterization data have already been collected because there is a tendency to make the
questions that need to be answered fit the available data. The application of the data quality
objectives process is applied in a graded manner, i.e., the depth of detail and the magnitude of the
resources expended in implementing the process should be commensurate with the relative
importance of the characterization data in terms of the decisions to be made and protection of the
public, workers and the environment.
Section 358
The intent of this requirement is not that waste streams with characterization processes already in
place and accepted by storage, treatment, and disposal facilities be recharacterized using the Data
Quality Objectives Process, or a comparable process, or that the characterization processes be
revised using the Data Quality Objectives Process, or a comparable process. The intent is that, as
new waste streams are identified and generated, the Data Quality Objectives Process, or a
comparable process, be used for identifying characterization parameters and acceptable
uncertainty in characterization data. If the characterization parameters of an existing waste
stream characterization process are to be significantly modified, then the Data Quality Objectives
Process, or a comparable process, should be used.
Compliance with this requirement is demonstrated by the documented use of a data quality
objectives or a comparable process for determining the type, quantity, and quality of
characterization data needed to safely manage transuranic waste.
Supplemental References:
1. EPA, 1994. Guidance for the Data Quality Objectives Process, EPA QA/G-4, U.S.
Environmental Protection Agency, Washington, D.C., September 1994.
2. WHC, 1996. Data Quality Objectives Procedure, WHC-IP-1216, Revision 1,
Westinghouse Hanford Company, January 31, 1996, (included as Appendix A in draft
Manual HNF-SD-WM-PROC-021, Revision 0, Lockheed Martin Hanford Corporation,
January 2, 1997).
III. I.(2) Minimum Waste Characterization. Characterization data shall, at a
minimum, include the following information relevant to the
management of the waste:
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-65
7-09-99
(a) Physical and chemical characteristics;
(b) Volume, including the waste and any stabilization or absorbent
media;
(c) Weight of the container and contents;
(d) Identities, activities, and concentrations of major
radionuclides;
(e) Characterization date;
(f) Generating source;
(g) Packaging date; and
(h) Any other information which may be needed to prepare and
maintain the disposal facility performance assessment or
demonstrate compliance with applicable performance
objectives.
Objective:
The objective of this requirement is to establish minimum transuranic waste data that have been
determined to be necessary for safe and effective management during the life cycle of the waste.
Discussion:
In the process of developing DOE O 435.1 and DOE M 435.1-1, the safety and hazard analysis
indicated that certain characterization data were critical because several consequences could be
avoided or minimized if certain basic information was accurately known about transuranic waste.
This requirement identifies those critical characterization data points that must be known for safe
handling and proper management. The sections below provide guidance on each of these specific
characteristics.
Physical and Chemical Characteristics. Physical characteristics support handling and packaging
activities. Parameters include a description of the material, its density, consistency, and
appearance. Chemical characteristics impact handling, storage, containment, and can impact
treatment processes. These characteristics determine the compatibility of the waste with other
waste and the waste container, as well as its compatibility with proposed treatment processes.
Parameters include pH, reactivity, chemical compounds present, and the presence of hazardous
Section 359
Chapter III - Transuranic Waste Requirements
III-66 DOE G 435.1-1
7-09-99
and/or toxic constituents. Physical and chemical characteristics can be determined directly by
visual examination and/or sampling and analysis. Physical characteristics can be determined
directly, indirectly by use of acceptable knowledge and/or by non-destructive examination
techniques such as computer tomography or real-time radiography. Chemical characteristics can
also be determined by use of acceptable knowledge.
Volume and Weight. Volume and weight information is necessary for proper control of storage
and disposal facility capacities as well as proper payload control for transportation and handling
systems. Typical parameters include:
C container volume, measured as the external volume of the waste container which
represents the volume that will be occupied in a storage or disposal facility (e.g.,
55 gallon drum or 120 cu ft (for a 4 x 5 x 6 box));
C actual waste volume, including stabilization media;
C container weight; i.e., the total weight of the container and all of its contents
(waste, shielding, stabilization media) that would have to be handled;
C identification of the stabilization medium, if used; and
C waste container utilization factor, measured as the percentage of the packaging
volume that is filled with waste, including stabilization media. This parameter does
not require an individual calculation be made of stabilization or absorbent media
volume, but that those media be included in the total waste volume calculation.
These characteristics are generally determined by acceptable knowledge (e.g., container size,
stabilization medium) or by measurement (e.g., weight).
Radionuclide Data. Radionuclide information allows for proper control of thermal loads for
storage and disposal facilities, determination of personnel safety procedures, control of total
activity limits for transportation, storage, and disposal, and also determination of the waste type.
Parameters which constitute radionuclide information may include the following:
C total activity in the container, in curies;
C identity and activity per unit mass of the major radionuclides. For purposes of this
guidance, major radionuclides are those which affect the determination that a
waste is transuranic waste and any others determined to be of importance to the
receiving facility (e.g., by safety analysis, performance assessment, etc.);
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-67
7-09-99
C radiation dose levels at the surface of the container; and
C container external surface contamination levels.
These characteristics can be determined directly by smear survey or radiochemical analysis of the
waste, or indirectly by waste package non-destructive assay, radiation survey, and/or by
documentation of nuclear materials accountability information or individual assays performed on
components contained in the container.
Date and Generating Source. Date and generating source information helps to determine the
validity of currently held documentation on the waste, which, in turn, will determine the need for
additional sampling or analysis. Parameters include characterization date, packaging date, DOE
site, building location of the process which generated the waste, and the generating process, if
available.
Section 360
Performance Assessment and Compliance Data. Additional data about waste that are important
to performance or evaluating performance of the disposal facility, or to complying with laws,
applicable regulations, or authorizing conditions (e.g., of a permit) may also need to be collected.
The specific data needed will, by necessity, be identified by the disposal facility operator.
Parameters which need to be included with waste characterization data may be identified by the
analysts developing the disposal facility performance assessment, specified through conditions
imposed on the site through the review and approval of the performance assessment, or derived
from internal regulatory compliance evaluations. Examples of the types of data that may be
needed are the presence and amounts of chelating agents which can enhance the transport of
radionuclides from the disposal facility, or the presence and concentrations of specific chemicals
which are not acceptable above specific limits (e.g., reporting polychlorinated biphenyls
concentrations versus a limit of 50 ppm).
All of these data may not be required for a particular phase in the management of the waste’s life
cycle. The specific data needed will be determined by the waste acceptance criteria of a particular
receiving facility.
Example: Experimental work in a laboratory generates a liquid transuranic waste
stream that is transferred via a pipeline to a central storage tank. Although the minimum
characterization requirements include “weight of the container and contents,” this is not
relevant to this waste stream and the characterization data in the waste acceptance
requirements for the central storage tank do not include packaging weight.
Compliance with this requirement is demonstrated by the existence of a program or procedures
for determining and records that document characterization of transuranic waste consistent with
the minimum characterization data requirements.
Chapter III - Transuranic Waste Requirements
III-68 DOE G 435.1-1
7-09-99
Supplemental References: None.
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-69
7-09-99
III. J. Waste Certification.
A waste certification program shall be developed, documented, and implemented to
ensure that the waste acceptance requirements of facilities receiving transuranic
waste for storage, treatment, or disposal are met.
Objective:
The objective of this requirement is to ensure that waste transferred to a facility for storage,
treatment, or disposal meets the receiving facility’s waste acceptance requirements, to reduce the
likelihood that transferred wastes contain unacceptable materials or characteristics, and to avoid
hazards that would occur from the transportation and handling of waste packages which do not
meet acceptance requirements. Certification also ensures that the storage, treatment, or disposal
facilities receiving the waste operate within limits established through safety analyses and/or
performance assessments.
Discussion:
Section 361
The Radioactive Waste Management Manual, General Requirements, assigns the Field Element
Manager the responsibility of ensuring development and approval of a program that addresses the
responsibilities of waste generators (DOE M 435.1-1, Section I.2.F.(7)). The generator
requirements are to address hazards associated with a waste management facility receiving
unexpected volumes or types of waste, or receiving waste that may not meet the waste acceptance
requirements of the facility to which it is transferred. The generator requirements address
generation planning, waste characterization, waste certification, and waste transfer. As discussed
in this guidance, a certification program is to be established by generators of radioactive waste to
provide a mechanism for confirming that waste is in compliance with the waste acceptance criteria
of the facility to which the waste is being transferred. The certification program is required by any
organization or facility that transfers waste to another facility.
Example: The Transuranic Waste Storage Facility has transuranic waste that it has
received for storage over the last 10 years. Facility personnel plan to continue to receive
transuranic waste and store it until it can be transferred to WIPP. The organization
responsible for the storage facility must have a certification program through which
facility personnel confirm the waste meets the acceptance criteria for WIPP . Since the
storage facility does not change the characteristics of the waste package, the facility
waste acceptance requirement should ensure that the waste they receive is acceptable for
WIPP disposal. In this particular example, the certification program would have to be in
accordance with the Generator Site Certification Guide (CAO, 1997).
Chapter III - Transuranic Waste Requirements
III-70 DOE G 435.1-1
7-09-99
The certification program is part of the waste generator program that is approved by the Field
Element Manager or designee. The certification program requires that an authorized official
confirms compliance with the waste acceptance requirements of the facility to which waste is
being transferred. Additional guidance correlated to the specific waste certification requirements
of the Transuranic Waste Requirements Chapter is provided below.
Program Development and Documentation. The waste certification program should consist of a
documented, structured process that works in concert with the DOE M 435.1 requirements for
waste acceptance (Section III.G) and waste transfer (Section III.K) to control the transfer of
waste to a storage, treatment, or disposal facility. Development of the waste certification
program involves defining and documenting controls for those items and activities that affect
certifying that a waste and its packaging meets the waste acceptance criteria of the receiving
facility. The documentation should include the following:
Organizations and Responsibilities - Certification program documentation needs to
identify the organizations and officials involved in the certification process and the
responsibilities of each. Officials who are authorized to certify waste are identified in the
documentation.
Quality Assurance - The certification program is subject to quality assurance. The quality
assurance controls that apply to waste certification activities needs to be identified and
documented. The use of an existing quality assurance program under which the
certification activities will be performed is acceptable and appropriate.
Section 362
Procedures - The process for certifying waste is formalized in procedures. The
procedures need to describe to the user the steps that are to be followed and the
administrative process for ensuring waste containers are certified. The procedures require
a signed statement certifying waste meets the appropriate criteria. The procedures also
document the steps necessary for complying with the applicable transportation
requirements (e.g., requirements from a safety analysis report for packaging and/or from
Title 49, Code of Federal Regulations).
Procurement/Purchasing Controls - The procurement and/or purchase of items or services
that are significant to certifying that waste meets the waste acceptance criteria of a
receiving facility need to be documented. Such procurement may include the purchase of
materials such as waste containers or laboratory services (onsite or offsite). As dictated
by the type of procurement, the documentation should include (or reference) the technical
specifications for the item/service being procured; identification of quality assurance
requirements including any required testing or inspections; specification of documentation
to be provided on delivery (e.g., fabrication inspection and/or test records; a certificate of
compliance or conformance, laboratory analytical results); and a statement ensuring access
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-71
7-09-99
to the provider’s facilities as necessary to perform audits and inspections. The
certification program ensures that the procurement documentation is reviewed and
approved by an official with knowledge of the need, intent, and requirements for the
procurement. The program also provides for documented verification commensurate with
the relative importance and complexity of the items or services being procured.
Document Control - The principal documents that constitute the certification program
needs to be subject to document control. Program documentation will identify which
documents are to be controlled. The waste certification program description, waste
certification procedures, and quality assurance program documentation need to all be
subject to document control. Document control includes review and approval, distribution
to designated recipients (users), and a controlled process for making changes to the
documents. Existing document control programs at a site may provide the necessary
controls for documents that are part of the waste certification program.
Training - The certification program needs to identify the training requirements for the
various individuals who are involved in the program. At a minimum, the program will
require training of the official who certifies that the waste meets the waste acceptance
criteria of the facility(ies) to which it is being transferred. In addition, individuals will need
to be trained in the procedures that control the part of the certification process with which
they are involved.
Records - The certification program documentation needs to describe the management of
certification records (see guidance for subparagraph (1) of this Waste Certification
requirement).
Section 363
Example: A site generates a small amount of transuranic waste that is sent to a
central facility managed by a waste management organization. The generating
organization works with the receiving facility to define the waste certification
program for the site. Through a review of the existing site procedures, site
personnel determine that the waste certification program can operate under the
existing site quality assurance program, document control program, procurement
process, and records management program. However, they determine that the
site training program does not adequately address the certification process.
Consequently, the waste managers work with the training department to develop a
training module that explains the purpose and process of waste certification. The
certification program documentation would identify these other programs as
applicable, specify the facilities from which waste would be transferred, designate
the officials responsible for waste certification at those facilities and their
training requirements, and develop procedures (within the document control
program) that ensure compliance with the waste acceptance criteria. Within the
Chapter III - Transuranic Waste Requirements
III-72 DOE G 435.1-1
7-09-99
existing programs, site personnel would identify the records to be maintained and
retention times, technical specifications and receipt requirements for obtaining
waste packaging materials, and requirements for analytical data. Operating
within the parameters defined by the program, the waste generators would be able
to certify waste for transfer to the onsite receiving facility.
As noted in the preceding example, existing programs at a site may provide the framework within
which elements of the waste certification program can be addressed (e.g., quality assurance,
training, document control). The waste acceptance requirements of the facility to which the waste
is to be sent may impose additional requirements on what is to be included in the waste
certification program. Whether the waste acceptance requirements of the facility to which waste is
transferred mandate a waste certification program (e.g., a commercial facility), the organization
transferring the waste is responsible for developing and implementing a certification program to
provide internal assurance that the waste acceptance requirements will be met.
Implementation. The waste certification program is implemented through the use of the
documented controls, processes, and procedures. The key document in a waste certification
program is the certification statement or equivalent. The certification statement is the
documentation signed by a designated official that certifies that the waste meets the appropriate
requirements. The list below, derived from the Waste Acceptance Criteria for the Waste
Isolation Pilot Plant, is a generic listing of the topics that are recommended for consideration in
development of certification statements.
1. Container and Physical Properties
- container type or description
- labeling/markings
- weight
- vents
- liquids
2. Nuclear/Radiological Properties
- fissile content
- transuranic activity
- other radioactivity
- dose rate
- surface contamination
- thermal power
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-73
7-09-99
3. Chemical Properties
- mixed waste
- polychlorinated biphenyls
- other hazardous constituents
- pyrophorics
- explosives
- corrosives
- compressed gases
Section 364
- volatile organic compounds
4. Packaging/Shipping Data
- packaging
- shipping information
Graded Approach. A graded approach is used in implementing the waste certification program.
The above list is recommended for the intersite transfer of transuranic waste. Intersite transfers
involve certifying that the waste is in compliance with the requirements for the receiving facility
itself, and also in compliance with Department of Transportation requirements. However, even
though the above list should be considered, it may be shortened and simplified for onsite transfers
where the organizational relationships and knowledge of waste and waste generating activities
may reduce the information that needs to be documented and transferred with each individual
waste container or shipment. For onsite transfers, much of the information may already be
available to the receiving facility. Onsite transportation of waste should be certified as meeting
Department of Transportation requirements or site-specific requirements for transportation.
Example: For onsite transfers the receiving facility/organization may already have a
waste stream profile provided by the generator facility/organization. Because of the
existence of the waste stream profile, the certification may be as simple as an individual
trained to the waste packaging and certification procedures signing a waste pick-up
request that provides the radionuclide inventory of the waste packages being transferred
and the waste stream identification number.
The waste acceptance requirements of the facility receiving the waste (see DOE M 435.1-1,
Section III.G) may dictate additional items which must be part of the certification statement.
Even if such information is not dictated by the receiving facility, the waste acceptance criteria
should be used to identify key elements to include on the waste certification statement.
Compliance with the development and documentation portion of the certification requirement is
demonstrated by a waste certification plan that identifies the organizations involved, assigns
Chapter III - Transuranic Waste Requirements
III-74 DOE G 435.1-1
7-09-99
responsibilities for implementing the program, and describes or references the quality assurance,
training, procurement controls, records management, and procedures to be used by the program.
Acceptable performance for implementing the program is demonstrated when the appropriate
personnel are trained, and have and follow the procedures that govern their part of the waste
certification process. Acceptable performance also requires that the waste certification plan and
procedures are current and controlled in accordance with a document control program, and
records related to certification (e.g., certification statements, training records, procurement
records, characterization records, container records) are generated and managed in accordance
with the established site program.
Supplemental References:
1. CAO, 1997. Generator Site Certification Guide, Revision 1, DOE/CAO-95-2119, U.S.
Department of Energy, Carlsbad Area Office, Carlsbad, NM, April 1997.
2. DOT. Shippers-General Requirements for Shipments and Packagings, 49 CFR Part 173,
U.S. Department of Transportation, Washington, D.C.
3. CAO, 1996. Waste Acceptance Criteria for the Waste Isolation Pilot Plant, Revision 5,
DOE/WIPP-069, U.S. Department of Energy, Carlsbad Area Office, Carlsbad, NM, April
1996.
Section 365
III. J.(1) Certification Program. The waste certification program shall
designate the officials who have the authority to certify and release
waste for shipment; and specify what documentation is required for
waste generation, characterization, shipment, and certification. The
program shall provide requirements for auditability, retrievability,
and storage of required documentation and specify the records
retention period.
Objective:
The objective of this requirement is to ensure waste certification programs are developed that
clearly identify the documentation required for certifying waste, specify personnel with the
authority to make the certification, and provide a traceable and verifiable record of and basis for
certification.
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-75
7-09-99
Discussion:
Officials who have the authority to certify that waste meets the waste acceptance requirements of
the receiving facility must be designated by a cognizant manager. To avoid having personnel who
are not knowledgeable of waste acceptance and transfer requirements authorizing the release of
waste, the program needs to identify, by title or name, the officials who are authorized to certify.
The official(s) are qualified by virtue of position, responsibilities, and training to make this
certification. The official(s) have sufficient familiarity with the waste being generated and have
been trained relative to the acceptance criteria of the facility receiving the waste for storage,
treatment or disposal (and applicable transportation requirements) to be able to certify in writing
that the waste is acceptable for transfer. The official(s) need to also have authorization from the
facility receiving the waste to transfer the waste (see DOE M 435.1-1, Section III.K).
Implementation of this element should be tailored to specific site needs and situations.
Example: Onsite transfers from multiple laboratories or processes to a central waste
management facility may involve training multiple personnel (e.g., one for each
laboratory or process) who have the authority to certify waste as meeting the onsite waste
acceptance requirements. However, for the transfer of waste from the central waste
management facility to an offsite facility, there may be a designated official at the site
who has been trained relative to the acceptance criteria of the offsite storage, treatment,
or disposal facility waste acceptance criteria and transportation requirements that is
authorized to certify the waste as ready for shipment.
The waste certification program needs to specifically identify the documentation to be produced
to support the certification that waste meets the waste acceptance criteria of the receiving facility.
The required documentation may include the following:
Waste Stream Profile (or record relating the waste to a previous profile). The
waste stream profile is a description of the waste stream, generally identifying the
source, physical and chemical description, and upper limits on radionuclides.
Radionuclide Characterization Data. Radionuclide characterization data include
the concentration and/or inventory of radionuclides as determined by
characterization (see guidance for DOE M 435.1-1, Section III.I, Waste
Characterization).
EPA Uniform Hazardous Waste Manifest. The EPA manifest is required by
40 CFR Part 262 for the transfer of a hazardous or mixed waste.
Section 366
Waste Container Data and Integrity Maintenance Documentation. Container data
include information about the container dimensions, other physical attributes, and
Chapter III - Transuranic Waste Requirements
III-76 DOE G 435.1-1
7-09-99
procurement information. Integrity documentation includes the records of
ownership and transfer of waste containers and data. (See guidance for Waste
Transfer, DOE M 435.1-1, Section III.K).
Radiological Survey Results (or documentation referencing a survey record).
Survey results include the determination of the surface contamination of the waste
container and the external dose rate.
Bill of Lading. A document indicating the contents of a shipment.
Real-Time Radiography Results. The results of radiography performed to detect
unallowed material in the waste package (e.g., liquids, compressed gas cylinders).
Certification Statement. The statement required by DOE M 435.1-1 to document
that waste is in compliance with the acceptance criteria of the facility to which the
waste is being transferred.
Authorization to Transfer. Documentation indicating that an official from the
facility to which the waste is to be transferred has authorized transfer of the waste
to the facility.
As noted for other elements of this requirement, the organization developing the certification
program uses a graded approach in determining which of these documents are needed.
Regardless of the extent of the required documentation, the certification statement can serve as a
checklist that all of the waste acceptance criteria have been considered and the waste is in
compliance. An example of a certification statement for waste to be shipped to WIPP is provided
at the end of this section of guidance (Figure III.J.1).
In order to ensure that information is available if or when it is needed in the future, the waste
certification program should identify which records are to be maintained and how they are to be
maintained. The certification program documentation may include specific records management
requirements, or may simply invoke an existing acceptable records management program.
Although no minimum record retention times are established in DOE M 435.1-1, certain records
may need to be maintained indefinitely. Whereas hazardous waste regulations require only a
three-year retention period, DOE disposal facilities should plan on maintaining pertinent records
at least through the operations, closure, and post-closure monitoring periods, and consider
making them part of any local land use records. The pertinent records would be those which
identify physical, chemical, and radiological characteristics of the waste and the certification of
that information. Generating, storage, or treatment facility waste management records may not be
required beyond the life of the facility or operation, provided pertinent information has been
supplied to the facility where the waste will be disposed.
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-77
7-09-99
Example: Personnel at a storage facility maintain records describing when they received
waste, what the waste was (characterization and container data provided by the
generator), and to whom the waste was eventually transferred. Once the waste is
disposed of and the waste characterization and container information is in the possession
of the organization responsible for the disposal facility, the organization responsible for
the storage facility disposes of its records.
Section 367
To meet the requirement for auditability and retrievability, the method of records storage and
retention needs to allow a person to trace shipment or waste container information back to the
generator certification data (e.g., characterization data, source data, container data). In
accordance with the DOE M 435.1-1, Section III.K Transfer Requirements, information on the
source and characteristics of the waste are to be transferred when waste is transferred. It is not
the intent of this requirement that a certification statement be generated for existing waste that
was received without such information (i.e., waste in storage as of the issuance of DOE O 435.1).
However, such documents must be created for any subsequent transfers of waste.
Example: A site should be able to provide the characterization, container, and
certification information for any waste container within a storage, treatment, or disposal
facility if that waste container is transferred after issuance of DOE O 435.1.
Compliance with this requirement is demonstrated by a program or procedure for record keeping
and records showing that each container of waste is certified as having met the waste acceptance
criteria of the facility to which it was transferred and the certification statement is supported by
additional records regarding the waste source, characterization, and container.
Supplemental References:
1. CAO, 1996. Waste Acceptance Criteria for the Waste Isolation Pilot Plant, Revision 5,
DOE/WIPP-069, U.S. Department of Energy, Carlsbad Area Office, Carlsbad, NM, April
1996.
III. J.(2) Certification Before Transfer. Transuranic waste shall be certified as
meeting waste acceptance requirements before it is transferred to the
facility receiving the waste.
Objective:
The objective of this requirement is to ensure that waste meets the acceptance requirements of the
storage, treatment, or disposal facility before it is transferred to prevent transferring waste that
Chapter III - Transuranic Waste Requirements
III-78 DOE G 435.1-1
7-09-99
could endanger receiving facility personnel, and to avoid the delay and potential hazards
associated with corrective actions taken to remedy non-compliant conditions.
Discussion:
The waste certification requirements above address development, implementation, and content of
a waste certification program. The requirement that waste be certified before transfer ensures that
the program is effective in preventing the transfer of waste that does not meet the waste
acceptance criteria of the facility receiving the waste for storage, treatment, or disposal. In
accordance with this requirement, waste should be released for transfer to another facility only
after there is a certification by an authorized official that the waste acceptance requirements have
been met. Ensuring certification occurs prior to allowing the physical transfer of waste prevents
potential hazards associated with managing waste rejected by the facility to which it is transferred.
Requiring certification before waste is transferred also reduces the likelihood of having to recall a
waste shipment due to a discovery by the certification official, after the waste is in transit, that the
waste does not comply with the waste acceptance requirements. Guidance on DOE M 435.1-1,
Section III.K discusses what constitutes a transfer, and can be consulted to determine when this
requirement needs to be met.
Section 368
Certification that the waste is ready for transfer and meets the waste acceptance criteria and the
applicable transportation requirements, is a control point in the transfer process. The procedures
controlling waste transfer should not allow the transfer to occur unless the certification statement
has been signed. Once signed, the certification statement becomes part of the record for the
transfer of the waste (see Waste Transfer, Section III.K). An example of a certification statement
for shipment of contact-handled waste to WIPP is included as Figure III.J.1. As can be seen from
examination of the certification statement in Figure III.J.1, the signature on the certification
statement is confirming that the waste has been characterized for physical, chemical, and
radiological characteristics, properly packaged, and necessary container markings and shipping
data have been prepared.
Example: Central Waste Management Facility personnel are responsible for receiving
waste, providing interim storage, and making transfers to an offsite transuranic waste
storage facility. In order for the workers at the Central Waste Management Facility to
place a waste container on a truck for transfer, the operating procedures for the facility
require that they have a signed certification statement that correlates to the container(s)
(either bar coded or numbered). Once a waste container is loaded, a copy of the
certification statement is included in the waste transfer papers and another is included in
the Central Waste Management Facility files.
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-79
7-09-99
Compliance with this requirement is demonstrated by the presence of a certification program
which includes procedures requiring a signed certification statement prior to the release of waste
for transfer, and by dated records showing that waste was certified before being transferred.
Supplemental References: None.
III. J.(3) Maintaining Certification. Transuranic waste that has been certified
as meeting the waste acceptance requirements for transfer to a
storage, treatment, or disposal facility shall be managed in a manner
that maintains its certification status.
Objective:
The objective of this requirement is to ensure that certified waste is managed to maintain the
certification status and avoid the unnecessary handling of waste containers that would be
necessary for recertifying waste.
Discussion:
There may be instances where waste must be stored before being transferred to the next stage in
the waste management process. If waste is certified as meeting the waste acceptance criteria of
the receiving facility prior to, or during storage, it needs to be stored and controlled so that the
certification remains valid until the waste can be transferred. For instance, many DOE sites will
send transuranic waste to WIPP for disposal. If a facility certifies waste in accordance with a
program authorized by the Carlsbad Area Office, the waste needs to be stored under conditions
and with controls to protect it from physical damage, and to prevent tampering (i.e., placement of
unallowed materials into the container ) so it can be transferred for disposal without re
certification.
Section 369
Example: A facility generates transuranic waste which is sent to an onsite storage
facility. An inventory of everything put into the waste container is maintained while the
container is being filled. Once filled, the container is closed and a numbered
tamper-indicating device is put on the container closing band. The facility’s authorized
waste certification official confirms that the waste has been properly characterized and
meets the storage facility’s waste acceptance criteria. When the authorized waste
certification official fills out the waste certification statement, the number of the
tamper-indicating device is also entered on the form. Facility procedures require closed,
certified waste packages to be staged in an indoor area adjacent to the loading dock.
Thus, at the time of transfer, the generating and receiving facility personnel are assured
that the certification is valid because environmental conditions have not affected the
Chapter III - Transuranic Waste Requirements
III-80 DOE G 435.1-1
7-09-99
package (it has not been exposed to precipitation, freezing, or extreme heat/sunlight) and
because the tamper indicating device indicates that the container has not be opened since
it was certified.
Also, certifying officials need to be aware of any limitations on the amount of time a waste can be
stored without invalidating the certification. Actions necessary to certify a waste that involve
potential radiation exposure of workers are deferred, if possible, until there is a reasonable
expectation that the waste can be transferred to the receiving facility within the time that the
certification is valid. Routine monitoring required for waste in storage may not allow all activities
that could result in worker exposure to be deferred.
This requirement is not to be interpreted in a manner that interferes with a facility performing a
normal acceptable waste management function. Therefore, if a waste is certified as meeting the
waste acceptance criteria of a treatment facility, the requirement to maintain the certification of
the waste is not intended to prevent the treatment facility from treating the waste. Even though,
treating the waste will not “maintain” the certification, the purpose of the certification is to
ensure the waste can be safely accepted for treatment. Maintenance of the certification status is
intended to cause the waste to be stored, transported, and staged at the treatment facility in a
manner that will allow personnel to treat the waste without concern that it no longer meets the
acceptance criteria. In addition, despite the protection provided for the waste, sampling prior to
treatment may still be a necessary process control step.
Specific requirements for protecting the certification status of a container of waste are generally
negotiated with the receiving facility. Requirements to be considered include protecting the waste
container, preventing unauthorized introduction of material into the waste, and protecting the data
about the waste container. The Waste Transfer requirements (DOE M 435.1-1, Section III.K)
also address protecting waste containers and data to ensure that characterization and packaging
data remain accurate and useable by waste managers. Waste containers need to be provided with
sufficient protection from the elements (e.g., precipitation, wind, flooding, excessive heat) such
that the character of the waste and container, and therefore the certification are not altered.
Containers of waste also need to be stored in a manner that prevents modifying their contents
(e.g, under lock and key or with a tamper indicating device) and in a location where the container
will not be damaged (away from equipment high traffic areas where there is the possibility of
damage). In addition, it is necessary to be able to relate each container of waste to information
about the contents of the container. Container markings must be protected from defacement or
removal, and records regarding container identification and contents must be safely stored.
Section 370
Example: Department personnel have learned from experience that below-ground
storage does not provide the type of protection that could be relied on to protect the
certification status of the waste. Although the below-ground environment maintains
waste packages within a reasonable temperature range, it also subjects them to
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-81
7-09-99
environmental conditions that can be detrimental to packaging and marking.
Condensation collecting under plastic has been shown to lead to rust of waste containers
making markings illegible and the container no longer suitable for performing its
containment function.
Compliance with this requirement is demonstrated by the existence of a program or procedure
reflecting this requirement and site personnel able to show that the storage of containers of waste
is in a facility or manner where the containers are not damaged by normal weather events, and
cannot be accessed by unauthorized personnel. Further, each container can be traced to its
certification and the information supporting that certification.
Supplemental References:
1. CAO, 1997. Generator Site Certification Guide, Revision 1, DOE/CAO-95-2119,
U.S. Department of Energy, Carlsbad Area Office, Carlsbad, NM, April 1997.
2. CAO, 1996. Waste Acceptance Criteria for the Waste Isolation Pilot Plant, Revision 5,
DOE/WIPP-069, U.S. Department of Energy, Carlsbad Area Office, Carlsbad, NM, April
1996.
Chapter III - Transuranic Waste Requirements
III-82 DOE G 435.1-1
7-09-99
Container ID Number:
CH-TRU WASTE CERTIFICATION
STATEMENT
Page 1 of 2
CRITERIA LIMITS INITIALS
Container Description C DOT Type A 55-gallon drums or solid waste boxes
(SWBs)
Container/Assembly Weight C # 1000 lbs/55-gallon drum
C # 4000 lbs/SWB
C # TRUPACT-II weight limits
Removable Surface Contamination C # 20 dpm/100 cm2 alpha
C # 200 dpm/100 cm2 beta-gamma (4)
Container Marking C Bar code
C Shipping category (1)
Filter Vents C Payload containers vented
Liquids C No liquid wastes
C < 2 liters total residual liquid per 55-gallon drum
C < 8 liters per SWB
C < 1 in. (2.5 cm) in the bottom of any container
Pu-239 FGE C < 200 g/55-gallon drum
C < 325 g/SWB
C < TRUPACT-II limits
Pu-239 Equivalent Activity Untreated Waste
C # 80 PE-Ci/55-gallon drum
C # 130 PE-Ci/SWB
C # 1800 PE-Ci/55-gallon. Drum overpacked in
SWB or TDOP
Solidified/Vitrified Waste
C # 1800 PE-Ci/55-gallon drum
Contract Dose Rate C # 200 mrem/hr
Thermal Power C Reported if > 0.1 watts/ft3
C < 40 watts per TRUPACT-II
TRU Alpha Activity C > 100 nCi/g of waste matrix
Pyrophoric Materials C < 1% Radionuclide pyrophorics
C No non-radionuclide pyrophorics
Mixed Waste C Characterization per QAPP
C Limited to EPA waste codes listed in WAC
Chemical Compatibility C Chemicals allowed by the CH-TRAMPAC
Figure III.J.1. Example Waste Certification Statement
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-83
7-09-99
Page 2 of 2
CRITERIA LIMITS INITIALS
Hazardous Constituents C Target analytes and TICs reported per QAPP
Explosives, Corrosives and
Compressed Gasses
C None present
PCBs Concentration C < 50 ppm
Decay Heat(1) C # Wattages listed in CH-TRUCON
Flammable VOCs C # 500 ppm in container headspace
VOC Concentration C # Limits shown in WAC Table 3.5.3.3
Aspiration(1) C $ Times shown in CH-TRUCON tables
Shipping Category(1) C Content codes listed in CH-TRUCON
C One category per TRUPACT-II
Section 371
Confinement Layers(1) C Liner punctured/vented
C Number of layers known
C Bags closed by approved methods
C Sealed containers > 4 liters prohibited (except for
waste material Type II.2)
Acceptance Data C Auditable package of data with signed
Certification Statement on file
C WWIS data transmitted
RCRA Data C Waste Stream Profile Form
C Uniform Hazardous Waste Manifest(2)
C Land Disposal Restriction notification(2)
Shipping Data C TRUPACT-II Payload Container Transportation
Certification Documents
C Bill of lading(3)
NOTES: (1) Applies to TRUPACT-II payload control only
(2) Applies to mixed wastes only
(3) A Uniform Hazardous Waste Manifest may be substituted
(4) May be 1000 dpm/100 cm2 for certain isotopes
I hereby certify that I have reviewed the data for this waste container and that it is complete and accurate to the best of my
knowledge. I have determined that it meets the requirements stated in the current revision of the WIPP Waste Acceptance
Criteria. I understand that this information will be made available to regulatory agencies and that there are significant
penalties for submitting false information, including the possibility of fines and imprisonment for knowing violations.
Waste Certification Official Signature Date Initials
Figure III.J.1. Example Waste Certification Statement (cont.)
Chapter III - Transuranic Waste Requirements
III-84 DOE G 435.1-1
7-09-99
III. K. Waste Transfer.
A documented process shall be established and implemented for transferring
responsibility for management of transuranic waste and for ensuring availability of
relevant data. The following requirements are in addition to those in Chapter I of
this Manual.
Objective:
The objective of this requirement is to ensure that the responsibility for transuranic waste
containers is established, maintained, properly transferred, and adequately documented so that
ownership, and therefore responsibility for safe management, of waste is clear. This responsibility
includes maintaining the waste characterization information, the container information, and
information about the treatment, storage, transportation and disposal status of containers of
waste. This responsibility also includes an assurance that the container of waste has not been
altered in a manner that affects its certification status or the ability of the waste to be properly
managed.
Discussion:
As discussed in Section I.2.F.(7) of the guidance for DOE M 435.1-1 Chapter I, the radioactive
waste generator program includes consideration of the generation planning, characterization,
certification, and transfer of transuranic waste. In the generator’s program, initial responsibility is
assigned for containers of transuranic waste and a documented process for transferring the
responsibility is established.
In the development of DOE O 435.1 and DOE M 435.1-1, maintaining the integrity of waste
containers was identified as necessary for the proper control and safe management of transuranic
waste. Similarly, maintaining information about containers of transuranic waste (characterization
and container data) was recognized as vital to making and executing safe management decisions.
In order to ensure that it is clear who has the responsibility for protecting the integrity of each
container of transuranic waste and associated waste and container data, there needs to be one
person who is identified as being responsible for the waste at any time. Confusion over who is
responsible for specific waste containers is avoided by documenting the transfer of responsibility.
Section 372
This requirement is similar to the concept of “chain of custody” used in sample management. As
with samples, transuranic waste containers may be the responsibility of many different
organizations during their management life cycle. At any point during the life cycle management
of the waste, the identity of the individual responsible for each container of waste needs to be
explicit. By clearly identifying the “owner” of each container of waste, there is no question
regarding who is responsible for protecting the waste container and the waste characterization and
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-85
7-09-99
container data, and for moving the waste to the next phase of waste management (i.e., storage,
treatment, or disposal).
Maintaining Waste Container and Data Integrity. The individual responsible for a container of
waste is responsible for maintaining and protecting both the integrity of the container of waste and
the data about the container of waste. Protecting the integrity of the waste container is the same
as protecting the certification status of a waste container as discussed in the Waste Certification
guidance. Essentially it involves managing the container of waste so that it is not damaged or
does not degrade because of the conditions under which it is managed.
Maintaining the data about the container of waste involves ensuring receipt or traceability, or
developing (as discussed below) information necessary to support subsequent waste management
activities, or clearly documenting and ensuring that the information is stored and updated so that
full and accurate information is available to the next individual to whom the waste is transferred.
Transferring Responsibility. The transfer of responsibility for containers of waste and the
associated waste and container data is to be done in accordance with procedures at each of the
facilities involved. The facility from which the waste is transferred, typically establishes (for
newly-generated waste) or possesses (for stored wastes) a record or data package about the
waste and its container. The facility operating procedures should require the development of an
ownership log sheet similar to a “chain-of-custody” log. This log becomes part of the data
package that is transferred with the container of waste. Upon transfer, the facility transferring the
waste is responsible for ensuring personnel at the facility to which the waste is being transferred
have assumed responsibility for the waste. A signed and dated copy of the ownership log sheet
can serve this purpose. All subsequent transfers, e.g., from storage or treatment facilities, are to
be in accordance with procedures requiring the transfer of the data package and documentation of
the transfer of responsibility for the waste.
Procedures at the storage, treatment, or disposal facility should require the receipt of certain
information about any waste which is received. To ensure that they have sufficient information to
safely manage the waste and to transfer the waste to a subsequent waste management facility (if
appropriate), it is important for storage, treatment, and disposal facility personnel to ensure they
are provided information about the containers of waste for which they become responsible. The
receiving facility requires the following documented information be available for all waste they
expect to receive:
Section 373
• Responsible individual. The name, title, affiliation, and phone number of each
person who has held responsibility for the waste, starting with the generator. This
listing can serve as the ownership log with each person signing the log upon
accepting responsibility for the waste.
Chapter III - Transuranic Waste Requirements
III-86 DOE G 435.1-1
7-09-99
• Transfer dates. The date the transfer was accepted by each new “owner” of the
waste.
• Waste container information. Information about the container (see guidance for
III.K.(2) in this section).
• Characterization information. Information about the waste. See guidance on
Waste Characterization.
• Physical location. The site and name (e.g., unique identifier such as a building
number) of each location where the waste was managed.
• Previous transportation. Dates of transportation and names of carriers.
• Certification status. A signed certification statement or equivalent (see guidance
on Waste Certification). Only the certification statement for the facility to which
the waste is being transferred must be part of the waste package data. Previous
certification statements may be included if they serve the purpose of documenting
other data that should be part of the data package (e.g.,container or
characterization data).
• The planned disposition of the waste. Expected storage, treatment, and disposal.
See guidance on Generation Planning and Site-Wide Radioactive Waste
Management Program.
For each transfer of waste, beginning with the generator, the receiver of the waste is responsible
for obtaining the proper information from the sender of the waste. The receiver is responsible for
ensuring receipt or availability of complete and accurate information concerning containers of
waste. The information needs to be reviewed prior to actual transfer and is a condition of
acceptance by the receiver.
Example: A treatment facility receives transuranic waste for processing. Upon signing
for receipt of the waste, the facility manager becomes the individual responsible for the
waste. Facility procedures require that a copy of the data received from the generator be
kept in a file cabinet which is accessible only to one individual on each shift. As the
containers of waste are processed in the facility, information is recorded in a log and the
data package is updated to reflect the change in status of the waste. Upon completion of
the processing, the treated waste is packaged in new waste containers and a certification
statement is generated indicating that the treated waste meets the waste acceptance
criteria for the storage facility to which it will be shipped. Before the waste is
transferred, the treatment facility personnel provide a complete set of data to the storage
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-87
7-09-99
facility personnel. The data package reflects the new container numbers for the treated
waste, but includes the data on the original containers received at the treatment facility.
The treatment facility also keeps a duplicate copy of the data package which includes a
copy of a waste log indicating transfer of ownership to the storage facility.
The responsibility for ownership of the waste can be different than that for waste certification.
The individual responsible for the waste does not necessarily have to be the same individual that
certifies the waste is ready to be transferred (see guidance on Waste Certification). As indicated
above, the certification status is one piece of information that is transferred with the waste.
Section 374
Compliance with this requirement is demonstrated if facilities have procedures for the receipt of
waste and the transfer of waste, as appropriate, which address the acquisition of waste and
container data and the transfer of ownership, respectively. Further evidence of acceptable
performance is facility records showing that data on the waste containers are available and
accurate, and that documented transfer of responsibility occurs.
Supplemental References:
1. EPA 1997. Test Methods for Evaluating Solid Waste, Physical/Chemical Methods,
SW-846, 3rd Edition, U.S. Environmental Protection Agency, Washington D.C., June
1997.
III. K.(1) Authorization. Transuranic waste shall not be transferred to a
storage, treatment, or disposal facility until personnel responsible for
the facility receiving the waste authorize the transfer.
Objective:
The objective of this requirement is to ensure that shipments or transfers of transuranic waste are
made only with the cognizance and approval of personnel at the facility receiving waste so that
preparations can be assured for its safe management.
Discussion:
As discussed in the guidance for DOE M 435.1-1, Section I.2.F.(7), the radioactive waste
generator program includes consideration of the generation planning, characterization,
certification, and transfer of transuranic waste. During the development of DOE O 435.1 and
DOE M 435.1-1, a review of waste management functions indicated that the receipt of waste
without personnel at the facility receiving the waste having knowledge of what was sent presented
a potential hazard. If waste is transferred to a facility without prior authorization, the controls
Chapter III - Transuranic Waste Requirements
III-88 DOE G 435.1-1
7-09-99
necessary for the proper and safe management of the waste may not be in place. As a
consequence, the waste may be rejected and returned to the sender. This requirement represents
a control to minimize the potential for exposures and releases during the handling and transfer of
transuranic waste.
Safe transfer of the waste can only be assured if the facility receiving the waste for storage,
treatment, or disposal has considered the acceptability of the waste versus its safety operating
constraints. Personnel at a storage, treatment, or disposal facility who authorize the transfer of
waste are indicating that they have the capability to receive the waste and manage it in a manner
that is protective of workers, the public, and the environment. Therefore an essential component
to safe life-cycle management is that authorization be received before transfer of transuranic waste
to a storage, treatment, or disposal facility. Meeting this requirement is the responsibility of the
organization or individual transferring (sending) the waste. The following are considered
transfers:
(1) Waste is physically moved from one location to another, even if ownership does
not change.
(2) Waste is physically moved from one location to another and ownership changes.
(3) Waste is not physically moved, but ownership changes.
Section 375
The actions and documentation necessary to obtain authorization will depend on the specific
storage, treatment, or disposal facility to which waste is to be transferred. In some cases, the
submittal of a waste stream profile which provides a description of the waste and a range of the
waste characteristics, augmented by conversations with the generator, may provide enough
information for the storage, treatment, or disposal facility staff to be confident that they can safely
manage the waste. In other cases, the waste acceptance requirements of the storage, treatment,
or disposal facility may dictate that an onsite visit and review of the generator’s waste certification
program be performed. In order to expedite the transfer of waste, staff responsible for sending
the waste need to ensure they understand what information and activities need to be completed in
order to receive transfer authorization.
Authorization to transfer waste is received in writing and states the scope of the authorization.
The authorization may specify a specific group of waste packages or specific number of shipments
of a particular waste type. However, it is acceptable for the written authorization to specify a
waste stream(s) which the generator can send on a routine basis. Any additional conditions or
notification requirements can be included in the written authorization. Whereas it is the
responsibility of the storage, treatment, or disposal facility to prepare the written authorization,
the organization sending the waste must not transfer waste until they have authorization and
understand which waste is included in the authorization.
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-89
7-09-99
Example 1: An activity at Site X results in the routine generation of transuranic waste in
the form of contaminated personnel protective equipment, swipes, plastic sheeting, and
paper waste. The waste stream is designated by the number X-2156. Consistent with site
procedures, the generator prepares a waste stream profile which describes the
characteristics, packaging, and projected generation rate of the waste stream and
provides it to the waste management organization. The waste management organization
reviews the waste stream profile and calls the generator facility representative to clarify
the information on the waste stream profile. The waste management organization has
previously reviewed the generator’s certification program. Based on the certification
program and the waste stream profile, the waste management organization prepares a
letter authorizing the generator to transfer any waste that meets the X-2156 profile until
further notice. The authorization letter also states that the generator must provide the
waste management organization notice of the number of waste containers to be
transferred 48 hours before a transfer occurs.
Example 2: A site plans to ship transuranic waste to WIPP for disposal. A Generator
Site Certification Guide (DOE/CAO-95-2119) has been prepared to aid individual sites
in their preparation to become authorized certifiers of waste destined for WIPP.
Generator sites are authorized by WIPP to certify waste for transfer following an audit
confirming satisfactory implementation of certification requirements. The authorization
is typically good for one year, at which time the transferring facility must be re
authorized through an audit. Once the generator’s certification program has been
audited and found to be acceptable, day-to-day authorization of waste transfers is
accomplished by review and approval of data packages describing planned waste
transfers.
Section 376
When transuranic waste is transferred (moved from one location to another), but the ownership of
the waste does not change (i.e., the same individual is responsible for both facilities), a separate
authorization may not be required. Recognizing that the intent of this requirement is to ensure
that the waste is expected and can be safely managed at the facility to which it is being
transferred, other documentation can serve as the written authorization.
Example: The manager of the waste management organization is the official responsible
for authorizing transfer of waste to either of two separate storage facilities, Building A
and Building B. Even though the waste acceptance criteria are the same for the two
facilities, waste is accepted and logged into each facility separately. The manager
decides to consolidate all of the waste into Building A for more efficient management.
The authorization to transfer is provided by the certification statement indicating that the
waste meets the Building A waste acceptance requirements, and the documentation of the
new storage location on the waste characterization and container data.
Chapter III - Transuranic Waste Requirements
III-90 DOE G 435.1-1
7-09-99
Compliance with this requirement is demonstrated by sites having procedures that require a
confirmation of authorization before releasing waste for transfer, and records showing that
transfers are made in accordance with written authorizations.
Supplemental References:
1. DOE/CAO, 1995. Generator Site Certification Guide, DOE/CAO-95-2119, U.S.
Department of Energy, Carlsbad Area Office, Carlsbad, NM, 1995.
III. K.(2) Data. Waste characterization data, container information, and
generation, storage, treatment, and transportation information for
transuranic waste shall be transferred with or be traceable to the
waste.
Objective:
The objective of this requirement is to ensure establishment and maintenance of information about
the characteristics of waste and the waste containers to ensure that sufficient information to
support management of waste in a manner that is protective of workers, the public, and the
environment is always available.
Discussion:
The Radioactive Waste Management Manual, assigns the Field Element Manager the
responsibility of ensuring development and approval of a program that addresses the
responsibilities of waste generators (DOE M 435.1-1, Section I.2.F.(7)). The generator
requirements are to address hazards associated with a waste management facility receiving
unexpected volumes or types of waste, or receiving waste that may not meet the applicable waste
acceptance requirements. Generator requirements address generation planning, waste
characterization, waste certification, and waste transfer. The requirement for traceability of data
addresses the hazards associated with transferring waste without providing or maintaining
adequate information about the container and its content. Establishing and maintaining the
identity of the waste, as well as maintaining controls based on the waste’s hazards, are necessary
for its safe transfer and subsequent management. Acquisition of information about the waste is
addressed in the guidance on Waste Characterization (DOE M 435.1-1, Section III.I).
Certification that waste is ready for transfer (i.e., meets the waste acceptance requirements and
transportation requirements) is discussed in the guidance on Waste Certification (DOE M 435.1
1, Section III.J). Maintenance of documentation regarding transfer of waste is discussed later in
this section of guidance.
Section 377
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-91
7-09-99
In the process of developing DOE O 435.1 and DOE M 435.1-1, transfer was identified as the
activity in the life-cycle management of waste with the greatest potential for loss of information
about containers of waste, and the associated loss of adequate waste management controls needed
to avoid exposure or release of radioactivity. Therefore, when waste is transferred, the waste
characterization and container data must be transferred or available to the new “owner” (i.e.,
responsible waste manager) of the waste.
Example: A liquid transuranic waste is being transferred to a treatment facility for
solidification. The waste was characterized and the waste characterization information
listed on the waste certification statement. Although the waste met the waste acceptance
criteria for the treatment facility and an authorization to make the transfer was granted,
the characterization information was not transmitted before or in conjunction with the
waste transfer. Due to storage limitations at the treatment facility, the drums of waste
were placed in an unheated staging area. After a three days of below freezing weather, it
was noted that the drums were bulging and split. Had the characterization information
been documented and transferred with the waste, treatment facility personnel would have
known it was an aqueous waste and would have imposed controls on the waste to protect
it from freezing conditions.
Sufficient information about the container in which waste is packaged needs to be provided to the
storage, treatment, or disposal organization to which waste is transferred to ensure that the
containers are handled safely.
The information about the container is supported by and traceable to the more detailed container
procurement information. The organization that procures the container is responsible for properly
documenting the essential information regarding the procurement. The information needs to be
maintained so questions about adequacy of the container for its originally intended or alternate
uses can be assessed and to answer questions about subsequent procurements. Information
documented concerning the procurement of waste containers includes:
C Purpose of the container;
C Container performance requirements;
C Purchase specifications; and
C Manufacturer certifications verifying performance to purchase.
The information concerning the purpose of the container should include the designed service life,
the environments for which the container was designed and is compatible with, and other
information necessary to allow proper use of the container. The procurement information
Chapter III - Transuranic Waste Requirements
III-92 DOE G 435.1-1
7-09-99
includes vendor information, product specifications, lot or serial number information, and other
procurement information necessary to document the container purchased.
The detailed procurement data about containers can be, but does not have to be, transferred at the
time waste is transferred. An acceptable practice for the organization transferring the waste
would be to maintain the records for as long as they are retrievable and can be correlated to the
waste containers.
The type of container information that should be provided upon transfer of containers of waste
will depend on the type of waste and subsequent waste management steps. Typically, the
information includes the following:
Section 378
• container size and type - generally this would be the container that is providing the
primary containment of the waste (e.g., DOT 7A 55-gallon drum, standard waste
box, or DOT 7A 80-gallon overpack);
• container enhancements - additional items that have been added to the primary
container to facilitate container performance (e.g., shielding, liners, plastic bags,
absorbents);
• lifting limitations - allowable and/or unallowable lifting points and methods; and
• load limitations - based on the physical characteristics, the maximum number of
containers or weight that can be placed on top of the waste container.
When waste is initially placed in the container, the organization packaging the waste is to
document and manage the information regarding its characteristics (e.g., radioisotopic inventory,
total activity, radiation dose, waste form). When the container of waste is physically transferred
or the ownership has changed, the information regarding the waste and container must be
provided or made available to the organization that acquires responsibility for the waste. A
transfer is considered to have occurred if the waste is physically moved from one location to
another or if there is a change in responsibility for the waste.
The following waste container characterization data are typically provided with the transfer of
transuranic waste:
• physical and chemical description of waste (use of item description code or waste
stream identifier, if applicable);
• radiological inventory (see guidance on Waste Characterization);
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-93
7-09-99
• gross weight;
• volume percent utilized;
• fissile gram equivalent;
• fixed and removable surface contamination (alpha and beta/gamma);
• surface dose rate;
• seal number;
• TRUCON Code;
• thermal power; and
• shipping category.
Example: Building 2000 is undergoing a facility cleanout that involves the
decontamination of building surfaces and the removal of excess processing equipment.
The organization responsible for the facility identifies two types of waste containers to be
used, 55-gallon drums for small items, personnel-protective clothing, and contamination
control waste, and standard waste boxes for larger pieces of equipment. The job is
managed such that one operator is responsible for logging each piece of waste put into
the containers. Upon filling a waste drum or box, the container is closed, and a
tamper-indicating device is installed. Radiological Services personnel perform
radiological surveys of each container of waste and record the data. The authorized
waste certification official uses the data recorded on the waste log and survey sheets,
supplemented with radiological characterization data, weight data, and other
information to fill out a waste certification checklist. The checklist requires
identification of waste container data as discussed above. In accordance with site
procedures, the checklist is a piece of required paperwork that is to be provided to the
storage, treatment, or storage facility to which the waste is transferred.
This requirement needs to be implemented with consideration given to documentation
requirements imposed by other internal programs or external organizations such as the
Environmental Protection Agency or Department of Transportation. These other documentation
requirements, such as an EPA Uniform Hazardous Waste Manifest or a transportation bill of
lading, may include much of the waste container information that is provided to the storage,
treatment or disposal facility to which waste is transferred. Therefore, to the extent these other
documents have the appropriate information, they may be used to meet the requirement to convey
Section 379
Chapter III - Transuranic Waste Requirements
III-94 DOE G 435.1-1
7-09-99
information about the waste being transferred to a subsequent waste management facility. If
documentation prepared to meet requirements of other programs or organizations is used, it may
need to be supplemented to provide any additional data on waste characterization and packaging
addressed in this guidance.
Example: Transuranic mixed waste is being sent from one site to another for storage.
Since the waste is regulated under RCRA, a Uniform Hazardous Waste Manifest is
prepared as required by 40 CFR Part 262. The manifest includes information about the
physical and chemical characteristics of the waste, the container type, and container
weight. The site has developed a ‘Radiological and Supplemental Characteristics Data
Sheet’ to provide additional information about the containers of mixed waste. The data
sheet provides additional information about the radiological inventory, surface dose rate,
surface contamination, fissile material content, number of the tamper-indicating device
installed on the waste containers, load limitations, and handling limitations. Between the
two documents the storage facility is provided enough information so they can safely
manage the waste.
Compliance with this requirement is demonstrated if there are procedures requiring that
characterization and container data be provided and maintained for each waste transfer and
documented records of transfers show that the information is being provided.
Supplemental References:
1. EPA. Standards Applicable to Generators of Hazardous Waste, 40 CFR Part 262, U.S.
Environmental Protection Agency, Washington, D.C.
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-95
7-09-99
III. L. Packaging and Transportation.
The following requirements are in addition to those in Chapter I of this Manual.
(1) Packaging.
(a) Transuranic waste shall be packaged in a manner that provides
containment and protection for the duration of the anticipated
storage period and until disposal is achieved or until the waste is
removed from the container.
(b) Vents or other mechanisms to prevent pressurization of containers or
generation of flammable or explosive concentrations of gases shall be
installed on containers of newly-generated waste at the time the waste
is packaged. Containers of currently stored waste shall meet this
requirement as soon as practical unless analyses demonstrate that the
waste can otherwise be managed safely.
(c) When transuranic waste is packaged, defense waste shall be packaged
separately from non-defense waste, if feasible.
(d) Containers of transuranic waste shall be marked such that their
contents can be identified.
Objective:
The objective of these requirements is to ensure that when waste is packaged, the container
selected is adequate to contain the waste and limit radiation exposure for the entire time the waste
is in storage, to reduce future exposure by segregating defense and non-defense wastes, and to
ensure that the container can be correlated to necessary information on its contents. The first
subrequirement is to ensure the selection of a container for waste based on the life cycle of the
waste so that there will not be unnecessary repackaging of waste. The second sub-requirement is
to prevent the build-up of pressure or concentrations of gases that could cause a loss of waste
confinement. The third subrequirement is to ensure the segregation of defense waste that can be
accepted for disposal at WIPP from other waste in order to facilitate compliance with the Waste
Isolation Pilot Plant Land Withdrawal Act of 1992, as amended. The last subrequirement is to
ensure that it is possible to identify the contents of the container of waste during storage and
when the waste is removed from storage for treatment or disposal without having to open the
container.
Section 380
Chapter III - Transuranic Waste Requirements
III-96 DOE G 435.1-1
7-09-99
Discussion:
The need for packaging requirements specific to waste management evolved from the
development of DOE O 435.1, and past experience in transuranic waste transportation. The
safety and hazards analysis conducted in support of the Order and Manual development identified
loss of confinement of a waste container as a potential hazard affecting worker safety and releases
to the environment. In addition, the inability to associate a container with data on the contents
was identified as a situation that would result in unnecessary worker exposure due to the need to
re-characterize the waste. Mitigation of each of these concerns can be achieved through proper
packaging and compliance with the requirements of this section. The safety analysis supporting
use of the TRUPACT II for transportation of transuranic waste has identified the build up of
explosive gases as a potential problem.
An analysis of existing requirements affecting the packaging of waste identified the Department of
Transportation (DOT) regulations and the DOE Orders, DOE O 460.1A and DOE O 460.2, as
sources of packaging requirements (see DOE M 435.1-1, Section I.D.(12)). Generally, the DOT
requirements apply to offsite shipments. Packaging and Transportation Safety (DOE O 460.1A)
invokes the DOT requirements, or documented requirements providing equivalent safety, for
onsite shipments. These regulations require the use of DOT Type A or Type B packaging
(depending on radionuclide content) for DOE waste shipments. The DOE O 460.1A also
establishes the means and approval authority for qualifying packaging as Type A or Type B.
Departmental Materials Transportation and Packaging Management (DOE O 460.2) includes
DOE policies and requirements that supplement the DOT regulations. Requirements from
DOE O 460.2 relevant to waste packaging include the inspection of waste shipments upon
receipt, provision of data to the Department’s Packaging Management Plan, and performance of
routine assessments of transportation and packaging operations.
While the DOT regulations and DOE packaging and transportation requirements were considered
adequate for shipping waste, they were not considered sufficient to address the other transuranic
waste management concerns associated with long-term storage or with selecting and packaging
waste based on the entire waste management life cycle.
The life-cycle management of transuranic waste has historically involved the packaging of
transuranic waste followed by a protracted storage period while awaiting disposal. Selection of a
container (i.e., a receptacle and any other components or materials necessary for the receptacle to
perform its required containment function) needs to account for all waste management steps
expected prior to and including disposal. Therefore, the container needs to meet the requirements
for transportation, storage, and eventual disposal (to the extent the disposal requirements are
known). Alternatively, if waste treatment is required, the container needs to be adequate to
contain the waste during storage and allow the waste to be transferred to the treatment facility
where it may be removed from the container prior to treatment. Subsequent to treatment,
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-97
7-09-99
Section 381
packaging of the treated residues is based on meeting all of the requirements of the remaining
waste management steps. Selection of a container that fulfills the needs of all subsequent waste
management actions ensures waste confinement and eliminates the need to repackage the waste,
thus avoiding potential exposure to workers.
Example: The Waste Acceptance Criteria for the Waste Isolation Pilot Plant
(DOE/WIPP-069) identifies the container, packaging, and transportation requirements
that must be met before transuranic waste may be shipped to and disposed in WIPP. The
requirements are derived from several sources which include: the WIPP Safety Analysis
Report, the TRUPACT-II Safety Analysis Report for Packaging, the RH-TRU 72-B Cask
Safety Analysis Report for Packaging, and the WIPP Land Withdrawal Act of 1992, as
amended. Containers that meet the WIPP Waste Acceptance Criteria and the acceptance
criteria for storage would be acceptable since the waste would likely not require
repackaging for any of the expected waste management steps.
Containment and Protection. Transuranic waste must be adequately contained, and the container
protected from conditions that could cause container degradation. Inadequate containers or
container degradation could lead to failure and result in the spread of contaminated materials,
worker exposure, or the non-acceptance by a receiving facility. When selecting transuranic waste
containers, consideration must be given to the conditions to which the container will be subjected.
If waste is to be stored outside for an extended period and subjected to the natural environment,
the container must be made of materials that have been demonstrated to maintain integrity during
these conditions.
Example: Contaminated soil and debris were packaged in wooden boxes or carbon steel
55-gallon drums which were stored in earthen berms for many years. The boxes and
drums degraded to the point that they no longer served as containment and were literally
falling apart. Due to the selection of inadequate containers (for the storage conditions
and duration), the waste had to be repackaged prior to transfer and the used wooden
boxes and drums also managed as transuranic waste.
Transuranic waste must not be incompatible with the container in which it is placed. The
physical, chemical, and radiological attributes of the waste need to be considered when selecting a
container. Container integrity must not be jeopardized due to the size, shape, or weight of objects
contained in the waste. Containers need to be compatible with any unusual chemical
characteristics, water content, and pH of the waste. If absorbent or other materials are used to
bind liquids contained in the waste, the resultant waste matrix must not be capable of spontaneous
combustion, decomposition, explosion, liquid desorption, or otherwise have the ability to affect
the integrity of the containers in any way (see Storage guidance III.N).
Shielding may also be required to provide protection to workers who handle the waste containers
or who are responsible for monitoring waste in storage. The necessity for shielding should be
Chapter III - Transuranic Waste Requirements
III-98 DOE G 435.1-1
7-09-99
Section 382
considered at the time of packaging so that the shielding can be integrated into the waste
container before waste is present if internal shielding is acceptable to the storage, treatment, or
disposal facility. Alternatively, the storage configuration may be designed to provide the
necessary shielding. If shielding is required, consideration needs to be given to the use of
materials that do not have the possibility of becoming a mixed waste if contaminated by the
radiological constituents. Guidance for DOE M 435.1-1, Section III.K discusses the selection and
procurement of waste containers and the necessary information that is documented.
Example: A new facility generates remote-handled transuranic waste sludges with
caustic properties and multiple fission products species. The container selected has been
designed to withstand chemical attack from the sludge, includes sufficient absorbent to
ensure there are no free liquids, and incorporates shielding. The container provides
protection of workers, the public, and the environment during its intended service life.
The anticipated service life needs to be considered when selecting a container for transuranic
waste. A determination of the anticipated storage time, environment, and location (waste
acceptance criteria) is essential to selecting the proper waste container. For waste that does not
have an identified path to disposal, the waste container may need to be designed to remain
effective for an extended and/or indefinite storage period.
Example: A site needs to repackage a small quantity of non-defense transuranic waste
with no identified path to disposal. A policy and plan have not yet been completed for
resolving the disposal issues. The selected container has been designed to last a
minimum of 50 years, if stored indoors.
When selecting containers for transuranic waste, consideration needs to be given to the full life
cycle of the waste, with a goal of packaging the waste only once. The selected waste container
needs to be compatible with transportation requirements and the waste acceptance criteria of the
facilities expected to manage the waste. Sites have generally identified the use of the DOT-
certified 55-gallon drum as the container of choice for all sized, newly-generated waste. An
alternative container is the standard waste box (3.1 x 4.5 x 5.9 ft). Both 55-gallon drums and the
standard waste box will fit in the TRUPACT II used to transport transuranic waste to WIPP for
disposal. Sites should avoid selecting containers which allow quick containment of the waste, but
are not amenable to subsequent waste management steps.
Example 1: A site selected a 4 x 4 x 8-ft box as the container for high volumes of
miscellaneous contact-handled waste because it accommodates large amounts of waste
without the need for any size-reduction. However, because consideration was not given
to the entire life cycle for management of the waste, site personnel did not take into
account that the box was not compatible with any approved transuranic waste disposal
facility or transportation system. Consequently, in order to make the waste acceptable
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-99
7-09-99
for transport and disposal at WIPP, site personnel will have to repackage the waste and
may have to treat the 4 x 4 x 8-ft box as transuranic waste also.
Section 383
Example 2: A requirements analysis was performed on the life-cycle plan for a specific
transuranic waste stream that will generate odd-sized solid debris. The analysis
indicated that a standard waste box could be used to meet all the requirements for
transportation, as well as satisfy the storage and disposal facilities waste acceptance
requirements.
To ensure that the waste container performs as expected, the following need to be considered
when placing waste in the packaging:
• Container free of deformations or imperfections that may cause a loss of container
integrity before the designed lifetime.
• Waste placement in a manner that does not adversely affect the integrity of the
waste container.
• Containers utilized such that void space within the container is minimized,
although care should be taken to avoid exceeding weight or other limitations
identified through consideration of the life-cycle management process.
• Waste container labels and markings permanently applied.
The selection of the container is influenced by the storage conditions, storage duration, and the
monitoring expected for the waste container. Ensuring waste containers provide confinement for
their expected storage life is therefore dependent on ensuring an appropriate storage environment
consistent with the container characteristics. Storage of waste containers is addressed in the
guidance for DOE M 435.1-1, Section III.N.
Vents. Because of the relatively large flux of alpha particles associated with transuranic waste,
there is a potential for radiolysis of hydrogen containing materials and the generation of hydrogen
gases within transuranic waste containers. In addition, depending on the waste contents and/or
the storage conditions, other gases, some of which are potentially flammable or explosive, may be
created. To address this issue, containers of newly generated waste shall be equipped with vents
or other mechanisms to mitigate the hazards associated with the evolution and accumulation of
gases within a waste container. Implementing this requirement includes taking actions to address
the accumulation of gases in inner containers such as bags, paint cans, and drum liners, in addition
to addressing the outer container. Inner containers may be punctured, vented, or provided with
products which have been proven to prevent the accumulation of dangerous quantities of gases.
Outer containers can be provided with filtered vents or products which have been proven to
Chapter III - Transuranic Waste Requirements
III-100 DOE G 435.1-1
7-09-99
prevent the accumulation of gases. The installation of vents or other mechanisms on transuranic
waste containers must not interfere with the container’s ability to maintain waste containment
until the waste is properly dispositioned (treated or disposed).
Waste currently in storage is to be provided with vents or other mitigating mechanisms at the
soonest practical time unless it can be shown that vents are not needed. Implementation of this
requirement does not require waste to be removed from storage solely for the purpose of
installing vents since this would result in exposure which could otherwise be avoided. Instead, the
intent is for site waste managers to install vents the next time the waste containers are accessed
for some other purpose such as assaying, reconfiguring storage, recovering waste from earthen-
covered storage, or preparing for transportation to the Waste Isolation Pilot Plant. The Waste
Acceptance Criteria for the Waste Isolation Pilot Plant requires the installation of vents on
containers so they can be transported in the TRUPACT II.
Section 384
The installation of vents on containers of transuranic waste in storage is not necessary if an
appropriate analysis has been prepared that demonstrates that the unvented containers do not pose
an unacceptable hazard. Application of this allowance within the requirement is dependent on an
approved safety analysis report or equivalent which shows that gas generation is not credible or
that the consequences are acceptable. An acceptable method of demonstrating that venting is not
required is to show that, based on the waste container contents, radiological characteristics,
and/or environmental factors, it is not credible to generate gases which pose a fire or explosion
hazard or create conditions which would otherwise breach the containers, such as over-
pressurization. In this usage, credible has the same meaning as used in safety analysis reports. If
over-pressurization or generation of ignitable or explosive gases is credible or assumed to be
credible, the analysis must show that the consequences of an accident are within established limits
for radiation dose to workers (10 CFR Part 835) and to the public (DOE 5400.5).
The Radioactive Waste Management Manual, Section III.D requires the development of a
radioactive waste management basis for transuranic waste management facilities, operations, and
activities; this includes transuranic waste in storage as of the issuance of DOE O 435.1. In
developing the radioactive waste management basis, site personnel need to consider the hazards
associated with drums of transuranic waste which have not been provided with vents or been
proven to not need vents through an approved safety analysis. For unvented containers in
earthen-covered storage, the facility itself may mitigate the hazards associated with the
accumulation of gases. For above-grade storage of transuranic waste containers, the radioactive
waste management basis needs to include controls which mitigate the hazards associated with the
accumulation of gases by restricting access to the storage area and providing equipment to protect
against fire or explosion. Waste managers should evaluate unvented containers in storage and
determine if it is appropriate to take prompt action to install vents rather than wait until the next
time the waste is actively managed. Immediate action may be warranted if drums show signs of
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-101
7-09-99
gas accumulation (bulging) or if the waste and radiological characteristics are similar to other
containers which contain waste which is known to evolve gases.
Segregating Defense Waste. Consistent with current legislation, the Department plans to dispose
of defense transuranic waste at WIPP. Disposal at WIPP of only defense waste is a constraint in
the WIPP Land Withdrawal Act of 1992, as amended. In contrast to defense waste, there are
currently no planned facilities for the disposal of non-defense waste. The intermixing of defense
and non-defense transuranic waste is therefore a practice that must be avoided, if feasible, so
waste can be accepted for disposal at WIPP. The Radioactive Waste Management Manual, DOE
M 435.1-1, includes a requirement (DOE M 435.1-1, Section III.G) that identification of waste as
defense or non-defense must be included in facility waste acceptance requirements. Additional
discussion of what qualifies as defense waste is included in the guidance for Section III.G of this
document.
Section 385
The language in the Nuclear Waste Policy Act of 1982, as amended, defines “atomic energy
defense activity” to include “any activity...performed in whole or in part in carrying out...defense
nuclear waste and materials by-products management” (Nordhaus). Based on this definition, the
disposal of commingled defense and non-defense transuranic waste at WIPP is permissible in
those cases where it is not feasible to segregate the waste. This is a result of the source of the
waste being “in part” from defense nuclear waste management. The feasibility of segregating and
packaging defense waste separate from non-defense waste needs to be made at the time the waste
is packaged, and needs to be based on consideration of the cost and risk associated with
performing the waste packaging. Waste managers must make a good faith effort to evaluate
whether there is the potential for commingling defense and non-defense waste streams and
whether it is feasible to segregate them prior to generating and packaging the wastes. It is
inappropriate to generate and package waste without regard to the source being a defense or non-
defense activity then claim that it is not feasible to segregate waste once it is commingled in a
container. If the actions necessary to segregate defense waste from non-defense waste would not
normally be performed and performing them would result in undue costs or risk (radiation
exposure), then segregation would not be considered feasible.
Example: Site A has an examination and experimental facility which has a series of
gloveboxes used for performing work on materials containing transuranic isotopes. Both
defense and non-defense experiments are performed in the gloveboxes, however,
generally they are not performed at the same time. A project involving the examination
of materials in support of the Office of Science has been completed. Prior to
commencing the next project, a general clean-out of the gloveboxes is performed in
which material associated with the project, e.g., unused specimens and one-time use
materials (swipes, etc.), are removed from the gloveboxes. These waste materials are
packaged as non-defense waste. Various equipment and tools remain in the gloveboxes
for use in subsequent experiments. Whenever there is a more thorough cleanout of the
Chapter III - Transuranic Waste Requirements
III-102 DOE G 435.1-1
7-09-99
gloveboxes, when maintenance (change-out of gloves or HEPA filters) is performed, or
when failed equipment is removed, it is recognized that there is a commingling of
contamination from defense and non-defense activities. However, because the waste is in
part from defense activities, it is packaged and disposed of as defense transuranic waste.
Similarly, when the gloveboxes are decommissioned and removed, the fact that they were
used for defense program activities makes them eligible for disposal as defense waste.
Waste that is generated after issuance of DOE O 435.1 is to be identified as either defense or non-
defense waste. In this usage, generated means any waste that is packaged after issuance of DOE
O 435.1, including waste from processing plants, treatment plants, cleanup activities, and retrieval
activities. Once identified, if feasible, the waste must be packaged separately and the containers
clearly marked as to whether they contain defense or non-defense transuranic waste.
Identification of waste containers as defense or non-defense can be included in machine-readable
code on the container, but should also be human readable. Different categories can be
distinguished through markings or labeling of waste packages or through color coding. This
provides a ready indication that a waste package is eligible for disposal at WIPP because
personnel involved in the transfer operation can easily see that waste containers are of the correct
category in addition to having the information on records.
Section 386
Example: A site that stores transuranic waste uses color coding to distinguish defense
from non-defense transuranic waste. The site already uses white drums for the storage of
transuranic waste, so opts to have non-defense transuranic waste drums painted with 2
inch red stripes around the drum about 12 inches from each end. In addition to the
characterization documentation indicating the type of waste, the red-striped drums are
easy to distinguish from the plain white drums that contain defense transuranic waste.
The Manual does not require waste containers that were previously (e.g., prior to issuance of
DOE O 435.1) placed in storage in buildings or other accessible above-ground configurations to
be removed from storage so they can be marked or labeled to distinguish those containing defense
waste from those containing non-defense waste. In fact, such an action would be counter to one
of the purposes of these requirements, namely to avoid personnel exposure attributable to
unnecessary handling of waste containers. Also, it is not the intent of this requirement to
segregate defense and non-defense waste that was previously commingled in a waste container.
Such waste is to be considered defense waste. However, when waste containers are removed
from storage for some other reason, such as preparation for transfer to WIPP, waste managers are
to label or mark them as defense or non-defense and/or segregate them to facilitate future waste
handling. Similarly, waste containers in earthen-covered retrievable storage configurations must
be marked or labeled during the time they are recovered, assayed, and transferred to another
waste management activity. If the containers of waste in earthen-covered retrievable storage have
failed and the waste is determined to be transuranic, the new container provided for repackaging
the waste must be marked, labeled, or color coded as discussed above.
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-103
7-09-99
Example: Transuranic waste is stored in drums in a dense-pack array in a storage
facility. Records indicate that most of the waste is defense waste. In the process of
certifying the waste for transfer to WIPP in accordance with the approved certification
program, each waste container is being assayed to determine its transuranic isotope
concentration. As personnel remove and assay each drum, they also apply stickers in
three locations on each drum that indicate whether the waste is defense or non-defense.
This determination is made based on a review of records of the programs that generated
the waste. Those drums identified as containing both defense and non-defense waste are
labeled as defense waste and are eligible for disposal at WIPP. When the waste
containers are returned to storage, personnel segregate the containers of defense waste
from those of non-defense waste.
Section 387
Containers of non-defense transuranic waste are to be segregated from containers of defense
waste in storage facilities in a manner that minimizes and simplifies future waste container
handling. In placing waste into storage, consideration needs to be given to the timing of
transferring waste containers to a subsequent waste management step. Segregation within a
storage facility does not require construction of separate facilities for storing waste or even
providing separate bays within a facility. Segregation can be provided by how and where the
waste is placed in the storage facility and it can be delineated by lines painted on the floor, by rope
barriers, or similar means. The principal concern to consider in storing waste that has been
segregated as defense or non-defense is the ability to access waste for future management without
having to handle other waste. Since WIPP has been identified as the defense transuranic waste
repository, it is likely that waste management steps leading to transfer to WIPP will occur with
defense waste on a schedule separate from actions to be taken with non-defense waste.
Therefore, to the extent practical, waste should be placed in storage to allow access of the WIPP-
bound waste without having to move the non-defense waste.
Marking and Labeling. The marking and labeling of waste containers need to be done in a manner
that allows traceability to the documentation of the waste characteristics and container
information. The marking or labeling needs to be applied such that it will be visible if the waste
package is on the outside of a storage or transportation array. For a 55-gallon drum, this is
generally accomplished by placing the marking or labeling about every 120 degrees around the
outside of the drum. For a waste box, acceptable labeling can be accomplished by placing labels
on each side of the box. Waste package identification should be in medium to low density Code
39 bar code symbology in accordance with ANSI/AIM-BC1-1195. Bar coding is to be a
minimum of 1 inch high and should be accompanied by human-readable alphanumeric characters
at least ½ inch high. Durability and readability of marking and labeling is one of the items
included in the inspection program for waste in storage (see guidance for DOE M 435.1-1,
Sections III.N and III.Q).
Chapter III - Transuranic Waste Requirements
III-104 DOE G 435.1-1
7-09-99
Example: A transuranic waste generator is packaging waste in accordance with the site
certification program that successfully passed a Waste Isolation Pilot Plant Waste
Certification Program audit. In accordance with the site certification procedures, labels
meeting ANSI/AIM-BC1-1995 that contain the site identifier and unique identifier are
placed in three locations equally spaced around each drum. This satisfies the marking
and labeling requirement.
Waste characterization and the container documentation is to be associated with each individual
container of waste. Guidance related to documentation is discussed in guidance for Waste
Transfer (DOE M 435.1-1, Section III.K). The documentation needs to include the aspects
relative to container selection including the designed service life, the environments that the
container was designed for and is compatible with, and other information necessary to allow
proper use of the container.
Section 388
Compliance with the packaging requirement is demonstrated by procedures which document
proper packaging protocols, including documented evidence that, where feasible, non-defense
transuranic waste has been packaged separately from defense transuranic waste and by never
having to repackage transuranic waste that is packaged after issuance of DOE O 435.1 in order to
maintain containment. However, the above protocol may not be satisfied by containers that were
placed in storage prior to issuance of the DOE O 435.1. For those containers, the goal is to only
have to repackage the waste one time after it is retrieved and characterized. Further, acceptable
performance is demonstrated by containers of waste having marking and labeling that allows
correlation with waste characterization data and container information. Successful performance
of this requirement is also demonstrated by a record of container performance in which failure has
not routinely occurred.
Supplemental References:
1. DOE, 1995. Departmental Materials Transportation and Packaging Management,
DOE O 460.2, U.S. Department of Energy, Washington, D.C., September 7, 1995.
2. DOE, 1996. Packaging and Transportation Safety, DOE O 460.1A , U.S. Department of
Energy, Washington, D.C., October 2, 1996.
3. DOT. Shippers-General Requirements for Shipments and Packagings, 49 CFR Part 173,
U.S. Department of Transportation, Washington, DC.
4. ANSI, 1995. Uniform Symbology Specification, ANSI/AIM-BC1-1995, American
National Standards Institute, Automatic Identification Manufacturers, August 16, 1995.
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-105
7-09-99
5. CAO, 1996. Waste Acceptance Criteria for the Waste Isolation Pilot Plant, Revision 5,
DOE/WIPP-069, U.S. Department of Energy, Carlsbad Area Office, Carlsbad, NM, April
1996.
6. Nordhaus, 1996. Robert R. Nordhaus to Al Alm, memorandum, Interpretation of the
Term “Atomic Defense Activities” as Used in the Waste Isolation Pilot Plant Land
Withdrawal Act, U.S. Department of Energy, Washington, D.C., September 9, 1996.
7. Dials, 1997. G.E. Dials to Distribution, memorandum, Carlsbad Area Office Interim
Guidance on Ensuring that Waste Qualifies for Disposal at the Waste Isolation Pilot
Plant, Carlsbad Area Office, U.S. Department of Energy, Carlsbad, NM, February 18,
1997.
8. Waste Isolation Pilot Plant Land Withdrawal Act of 1992, as amended, October 30, 1992.
9. Nuclear Waste Policy Act of 1982, as amended, January 7, 1983.
III. L.(2) Transportation. To the extent practical, the volume of waste and
number of transuranic waste shipments shall be minimized.
Objective:
The objective of this requirement is to reduce the risk associated with transuranic waste
management by reducing the number of miles traveled transporting waste. This is to be done by
the efficient use of waste containers, minimizing the volume of waste which requires shipment,
and optimizing shipping plans and schedules.
Discussion:
The need for transportation requirements specific to waste management concerns was evaluated
in the development of DOE O 435.1, Radioactive Waste Management, and DOE M 435.1-1 the
Radioactive Waste Management Manual. An analysis of existing requirements affecting waste
transportation identified the Department of Transportation (DOT) regulations and the DOE
Orders, DOE O 460.1A and DOE O 460.2 (see DOE M 435.1-1, Section I.1.E.(11)), as sources
of applicable requirements. Generally, the DOT requirements apply to offsite shipments.
Packaging and Transportation Safety (DOE O 460.1A) invokes the DOT requirements, or
documented requirements providing equivalent safety, for onsite shipments. Departmental
Materials Transportation and Packaging Management (DOE O 460.2) includes DOE policies
and requirements specific to DOE that supplement the DOT regulations. Requirements from
DOE O 460.2 relevant to transuranic waste transportation address development of a
Section 389
Chapter III - Transuranic Waste Requirements
III-106 DOE G 435.1-1
7-09-99
Transportation Plan for high-visibility shipment campaigns (e.g., shipments to WIPP), use of the
Department’s Transportation Tracking and Communications System, and administrative
requirements. Additionally, for waste exceeding Type A quantities of radioactive material per
DOT regulations, notification of the expected date of arrival is to be given to the site to which the
waste is being shipped, and if the waste is not received on the expected day, notification of the
shipper is mandated.
The DOT regulations and DOE packaging and transportation requirements were considered
adequate for ensuring safe transportation of the waste. However, recognizing that one of the
higher risks associated with waste management is from the number of miles traveled in
transporting waste, transuranic waste shipments should be minimized to reduce worker exposure,
risk, and cost. This can be achieved, in part, by ensuring that all containers or primary packagings
(e.g., drum or waste box) are used to capacity, and that transportation systems are efficiently
utilized. Reaching the capacity (volume or weight) of the waste container should be a goal of
every waste packaging operation. Containers should be filled so as to minimize headspace
volume and allow closure, without exceeding its weight capacity or compromising its integrity.
Example 1: Miscellaneous defense transuranic waste such as personnel protective
equipment, contaminated tools, and paper and plastic sheeting are being packaged in
55-gallon drums for disposal at WIPP. Site personnel use a compactor to maximize the
amount of waste placed in the drum. Administrative controls ensure that drum weight
limits are not exceeded.
Example 2: Defense transuranic waste is being thermally treated and packaged in
55-gallon drums for disposal at WIPP. Because of the density of thermally treated waste,
site personnel fill each drum to its maximum weight capacity, 1000 pounds, although
excess headspace remains.
There may be circumstances that require the use of dunnage in the form of empty drums when
transporting transuranic waste. Due to TRUPACT II limits on weight, wattage, curies or dose
rate, it may not be possible to include a full complement of containers with waste in a shipment.
Some empty containers may have to be included in the normal 14 drums (or 7 for a half pack)
which constitutes a shipment. In optimizing shipments, the amount of dunnage used is to be
minimized to the extent practical.
The same goal applies to transport systems. Containers of waste should be held and accumulated
until a sufficient number of packages is available to make cost-effective use of the transportation
system.
Example: Defense transuranic waste is being thermally treated and packaged in
55-gallon drums for disposal at the WIPP. Because of the density of thermally treated
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-107
7-09-99
waste, each drum is filled to its maximum weight capacity of 1000 pounds. A sufficient
number of drums (7) is then accumulated at a staging area to enable full and efficient
use of the Halfpack packaging for shipment to the WIPP.
The distance transuranic waste is transported, and the number of times waste is physically handled
is directly related to the risk of release or exposure. As part of the planning and documentation
concerning the life-cycle management of transuranic waste, the Site-Wide Waste Management
Program should seek to reduce the number of times the waste is handled or otherwise
transported. Site transuranic waste management programs need to ensure that both on-site and
off-site transport and handling is minimized.
Section 390
Example 1: A small quantity site performed an optimization study and determined the
nominal volume of transuranic waste that needed to be shipped off-site for the year.
Staging the waste prior to transport reduced the number of shipments and allowed the
transfer of the waste to occur during the summer when road conditions were best.
Example 2: A waste management operation on a large DOE reservation generates
transuranic waste that can only be fully characterized by facilities located elsewhere on
the reservation. Staging the waste and transferring it during off-peak traffic hours
reduced the number of shipments across publicly-traversed roads on the reservation, and
helped minimize the risk to the public.
Transuranic waste transportation needs will be specific to each site. Availability of treatment,
storage, and disposal capabilities, as well as funding profiles, will influence the need to ship
transuranic waste. In this requirement, the term, “to the extent practical” means that site
personnel have latitude in making decisions regarding what is practical for their particular
situation. This requirement is not intended to force decisions that are contrary to safe waste
management, regulatory compliance, or cost-effectiveness. Detailed and documented planning
that provides the rationale for a waste shipment regimen is the best way to balance this
requirement with site-specific realities.
Example: A site-specific evaluation was performed to support a recommendation on
either building transuranic waste storage capacity or maintaining the current number of
small off-site shipments. The evaluation indicated that concerns over building the
storage facility outweighed the benefits of minimizing shipments and the current shipment
regimen was continued. The evaluation was included as part of the Site-Wide Waste
Management Program documentation.
Transportation over the nation's highways and railways results in the most direct contact between
the Department’s radioactive waste and the general public, stakeholders, and representatives of
States, Tribes, and local government organizations. These groups are primarily concerned with
Chapter III - Transuranic Waste Requirements
III-108 DOE G 435.1-1
7-09-99
the shipment of these materials through states, cities, and neighborhoods. Efforts to minimize the
volume and number of transuranic waste shipments will help alleviate their concerns.
Compliance with this requirement can be demonstrated by a combination of site procedures
directing the efficient use of waste container capacity and documentation showing that transuranic
waste shipments are systematically planned and make optimal use of the shipment system (e.g.,
TRUPACT II) to the extent practical.
Supplemental References:
1. DOE, 1995. Departmental Materials Transportation and Packaging Management,
DOE O 460.2, U.S. Department of Energy, Washington, D.C., September 7, 1995.
2. DOE, 1996. Packaging and Transportation Safety, DOE O 460.1A , U.S. Department of
Energy, Washington, D.C., October 2, 1996.
3. DOT. Shippers-General Requirements for Shipments and Packagings, 49 CFR Part 173,
U.S. Department of Transportation, Washington, D.C.
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-109
7-09-99
III. M. Site Evaluation and Facility Design.
The following requirements are in addition to those in Chapter I of this Manual.
Section 391
(1) Site Evaluation. Proposed locations for transuranic waste facilities shall be
evaluated to identify relevant features that should be avoided or must be
considered in facility design and analyses.
(a) Each site proposed for a new transuranic waste facility or expansion
of an existing transuranic waste facility shall be evaluated considering
environmental characteristics, geotechnical characteristics, and
human activities.
(b) Proposed sites with environmental characteristics, geotechnical
characteristics, and human activities for which adequate protection
cannot be provided through facility design shall be deemed unsuitable
for the location of the facility.
Objective:
The objective of this requirement is to ensure that natural and human environmental factors and
geotechnical characteristics of proposed sites are accounted for in selecting the location and
design features of new transuranic waste management facilities or significant modifications of
existing facilities, and that locations are avoided if facility design cannot compensate for negative
site characteristics or environmental conditions.
Discussion:
The Radioactive Waste Management Manual (DOE M 435.1-1, Section I.1.E.(18)) invokes the
requirements of DOE O 420.1, Facility Safety, and DOE O 430.1A, Life Cycle Asset
Management in site evaluation and facility design. In the development of DOE M 435.1-1, it was
determined that specific attention should be given to selection of a waste management facility
location with consideration given to the beneficial and detrimental aspects of the site.
Site evaluation includes the identification and characterization of potential sites (locations within a
DOE reservation) for new transuranic waste management facilities or significant modifications of
existing facilities. Selection of sites for DOE facilities is generally constrained to those federal
lands owned and managed by DOE. Within DOE reservations, the process of selecting sites has
the purpose of identifying the best location with consideration of features which are desirable for a
facility.
Chapter III - Transuranic Waste Requirements
III-110 DOE G 435.1-1
7-09-99
In the context of this requirement, the environmental and geotechnical characteristics include:
• ecology - the flora and fauna that have evolved and adapted to the other
environmental characteristics of the site;
• topography - the physical features of the ground surface at and around the site;
• meteorology - the normal and extreme weather events of the site;
• hydrology - the surface and ground water at the site;
• geology - the sediment and structural features of the earths crust at the site;
• seismology - the earthquake potential of the area;
• soil characteristics - characteristics of the soil that affect its load-bearing, water
infiltration, and percolation;
• human activities - proximity of the public and human-induced events or feature;
• emergency services and response - proximity of services and population sheltering;
and
• hazards to other facilities - proximity of existing facilities and proposed facility.
Section 392
Characterization of a site is to result in collection of the data necessary to support a decision on
acceptability of a site and for use in site-specific design of a facility. The site characterization and
selection process will vary from one DOE site (reservation) to the next because of substantial
differences in their environmental and geotechnical characteristics. Similarly, the interests of
stakeholders which vary from site to site are likely to influence the issues to be addressed in site
characterization and selection. The level of characterization needs to reflect application of a data
quality objective-type process where the type and amount of information to be collected is
commensurate with the hazards and the decisions which have to be made based on the data. The
resulting site characterization program needs to include the investigations and studies needed to
evaluate site and facility performance.
Natural Phenomena Hazards. The characterization of a site for natural phenomena hazards is to
identify the range of normal and extreme natural events that should be taken into account in the
siting and design of the facility. The amount of characterization necessary will be influenced by
the hazard associated with the facility and release of the radionuclide inventory. Guidance on
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-111
7-09-99
characterization and consideration of natural phenomena hazard in the design of DOE facilities is
contained in the following standards supporting implementation of Facility Safety (DOE O
420.1):
• Natural Phenomena Hazards Characterization Criteria;
• Natural Phenomena Hazards Assessment Criteria;
• Natural Phenomena Hazards Performance Categorization Guidelines for
Structures, Systems, and Components;
• Natural Phenomena Hazards Design and Evaluation Criteria for Department of
Energy Facilities; and
• Guidelines for Use of Probabilistic Seismic Hazard Curves at Department of
Energy Sites for Department of Energy Facilities.
Example: A new storage facility is being considered at the Hanford Site. Due to the
environmental setting, wind effects and seismic activity are factors that have to be
considered in the design regardless of the location selected at the Site. However, due to
the local topography, concerns about flooding can be addressed by selecting a location
on the Site’s central plateau. A similar facility is being considered at the Savannah River
Site. The Savannah River Site evaluation includes the consideration of flooding and high
winds in the design regardless of location. However, seismic concerns are minimal
because of the region of the country; also flooding impacts can be mitigated by selecting
an appropriate area of the Site.
In carrying out characterization activities, field studies need to be performed so as to not
compromise the integrity of the land to be dedicated to waste management activities. This is
particularly relevant to disposal facilities where improper design or installation of core sampling or
groundwater sampling wells can lead to a preferential path for the migration of contaminants from
a facility. Also, the characterization is to be carried out in accordance with the site’s quality
assurance program, including maintaining records of data collected. Documentation of the results
of the site characterization program is not only needed for use in design, but may also provide
information necessary for complying with requirements of the NEPA process.
Section 393
Human Activities. The site of a proposed transuranic waste management facility needs to be
evaluated with respect to the effects of the facility on human activities and the effect of human
activities on the facility. Effects of the facility location on human activity includes consideration
of:
Chapter III - Transuranic Waste Requirements
III-112 DOE G 435.1-1
7-09-99
• transportation routes;
• present and future population distribution (future population considerations should
be constrained to reasonable time frames consistent with regional land use
planning, not thousands of years);
• present and proposed land and water uses in the region; and
• any special characteristics that would influence the consequences of releases of
radioactive material during the life cycle of the facility.
The potential impact of the waste management facility construction, operation, and
decommissioning need to be evaluated, considering current and future land use plans and
population distribution. Evaluation and selection of the location for a facility should ensure that
there is and will remain a buffer between the facility and the public. Such considerations in site
selection provide defense in depth by ensuring there is space for corrective actions to be taken if
there are unplanned releases and by establishing distance for attenuation of such releases so that
impacts are minimized.
Example: Site Z is going to construct a facility to treat remote-handled transuranic
waste to make it acceptable for disposal. There are no natural environmental
characteristics that make any of the proposed locations superior to others. However, one
location is in the center of the site and the others are either near the current site
boundary or in areas being cleaned up so they can be released from DOE control.
Because the criteria for selecting a site include consideration of the proximity to current
and future populations, the location near the center of Site Z is preferred.
Another aspect of human activities is the effect that they may have on the waste management
facility. Locating a facility near other facilities on or near the DOE site may impact the design or
performance of the facility. For instance, a tall building may create a wake on its downwind side
that would cause the exhaust effluent from a nearby, downwind facility to be dragged down to
ground surface in a short distance with the potential of impacting workers or nearby members of
the public. To counteract this effect, the waste management facility would have to extend its
stack higher than the wake effect, or an alternative location for the facility should be considered.
Compliance with this requirement is demonstrated by performing an appropriate site evaluation
for new facilities or expansions of existing facilities, and by the ensuring that the environmental
and geotechnical characteristics of the site which are significant to protection of workers, the
public or the environment are accounted for in selection of the site or through facility design.
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-113
7-09-99
Supplemental References:
1. DOE, 1989. General Design Criteria, DOE 6430.1A, U.S. Department of Energy,
Washington, D.C., April 6, 1989 (canceled).
2. DOE 1992. Guidelines for Use of Probabilistic Seismic Hazard Curves at Department of
Energy Sites for Department of Energy Facilities, DOE-STD-1024-92, Change 1, U.S.
Department of Energy, Washington, D.C., 1992.
Section 394
3. DOE, 1993. Natural Phenomena Hazards Performance Categorization Guidelines for
Structures, Systems, and Components, DOE-STD-1021-93, Change 1, U.S. Department
of Energy, Washington, D.C., 1993.
4. DOE, 1994a. Natural Phenomena Hazards Design and Evaluation Criteria for
Department of Energy Facilities, DOE-STD-1020-94, Change 1, U.S. Department of
Energy, Washington, D.C., 1994.
5. DOE, 1994b. Natural Phenomena Hazards Characterization Criteria,
DOE-STD-1022-94, Change 1, U.S. Department of Energy, Washington, D.C., 1994.
6. DOE, 1995. Natural Phenomena Hazards Assessment Criteria, DOE-STD-1023-95
Change 1, U.S. Department of Energy, Washington, D.C., 1995.
III. M.(2) Facility Design. The following facility requirements and general
design criteria, at a minimum, apply:
Objective:
The objective of this requirement is to ensure that a minimum set of facility requirements and
general design requirements determined from hazards analyses or policy considerations are
applied to transuranic waste management facilities.
Discussion:
The facility requirements and general design criteria included in DOE M 435.1-1,
Sections III.M.(2) (a) through (e), are included as requirements to ensure adequate protection of
the public, workers, and the environment from nuclear hazards. The requirements contained in
these sections apply to new and existing transuranic waste management facilities, unless the
requirement specifies otherwise.
Chapter III - Transuranic Waste Requirements
III-114 DOE G 435.1-1
7-09-99
During the development of DOE O 435.1 and DOE M 435.1-1 an analysis of the hazards
associated with the management of waste indicated that appropriate facility safety requirements
and general design requirements are essential to ensuring the protection of the public, workers,
and the environment. Therefore the intent is to apply these requirements to all transuranic waste
management facilities, both existing and new. However, it is recognized that in some cases it may
not be practical, or possible, to apply these requirements to existing transuranic waste facilities or
operations. Such conditions as limited programmatic usage, expected short service life of the
operation, or factors that make long-term, capital-intensive upgrades unreasonable may be bases
for not applying the requirements. In such cases, an exemption to the requirement may be
warranted. The Implementation paragraph of DOE M 435.1-1 provides for an exemption to a
requirement provided it is processed in accordance with the requirements of DOE M 251.1-1A,
Directives System Manual.
Example: At Site Z it is determined that the requirement in DOE M 435.1-1, Section
III. M.(2)(e), Monitoring, for an existing transuranic waste tank is unreasonable due to
the planned short service life of the tank. The existing tank is not routinely being used
and would only be used over the next 18 months for emergency storage of liquid
transuranic waste. A replacement for the tank is under construction. In accordance with
DOE M 251.1-1A, Chapter VII, “Exemptions,” an Exemption Request is prepared that
supports the position that application of the requirement is not justified by any safety and
health benefit. The exemption request also notes that procedures will be implemented to
ensure a once per shift visual check to ensure no waste is inadvertently transferred to the
tank. The Exemption Request is processed in accordance with the requirements
contained in paragraph 4, Exemption Process, in Chapter VII.
Section 395
DOE M 435.1-1 also allows for the use of the “Necessary and Sufficient Closure Process” or the
integrated “Safety Management System.” Use of these processes for deriving facility design
requirements that provide protection comparable to the requirements contained in DOE M 435.1
1, Sections III.M.(2) (a) through (e) is also acceptable at sites where these processes are invoked
by contract.
Application of these requirements to all existing transuranic waste facilities may appear to
contradict the direction or guidance provided by some other DOE Orders that are invoked by
DOE M 435.1-1, Section I.1.E., Requirements of Other Regulations and DOE Directives. In
such cases the requirements contained in DOE M 435.1-1 do apply.
Example: Section I.1.E.(18), Site-Evaluation and Facility Design, invokes DOE O 420.1,
Facility Safety. Guidance to DOE O 420.1 states that the design criteria included in the
Order are “applicable to the design and construction of new nonreactor nuclear facilities
and for modifications to existing nonreactor nuclear facilities when modifications
significantly increase the probability or consequences of a nuclear accident or require a
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-115
7-09-99
change in the Technical Safety Requirements (TSRs) of a facility. The definition of
‘significant’ is intentionally left to the judgment of the proposing contractor and the
approving DOE authority. In part, this is intended to allow upgrading of existing safety
equipment or installation of minor new improvements without subjecting the process to
onerous procedural requirements and thus discouraging improvements.” Thus, under
DOE O 420.1 an existing transuranic waste management facility that is to be
“insignificantly” modified does not have to meet the design requirements of DOE O
420.1. However, under DOE M 435.1-1, the same facility must meet the design
requirements of DOE M 435.1-1, Section III.M.(2) (a) through (e), or follow the DOE M
251.1-1A exemption process. The requirements contained in DOE M 435.1-1 have
precedence, and should be implemented.
A “backfit” process has been discussed by the Department in the past to address changes that may
be required through the imposition of a new DOE safety requirement. Such changes may be
problematic for transuranic waste facilities and systems that have been in existence for over 20
years. It is not the purpose of DOE O 435.1 and DOE M 435.1-1 to create such a process for the
Department; however an existing or new field-office or Program Secretarial Office backfit analysis
and review process may be applied to determine whether implementation of a proposed backfit
could be justified on the basis of a substantial safety improvement or on a cost-benefit basis. One
example of a candidate process is contained in expired DOE N 5480.5, Imposition of Proposed
Nuclear Safety Requirements, which expired in 1993 because of an administrative provision.
Another candidate process is described Draft DPOM-FS-300, “Treatment of Proposed Backfits,”
which was developed for the Office of Defense Programs, but not formally adopted. A third
candidate process is documented in Westinghouse Savannah River Company, High Level Waste
Management Engineering Procedure, ENG. 12, “HLWMD Backfit Analysis Procedure.” For
development of new backfit processes Nuclear Regulatory Commission requirements in 10 CFR
50.109 and 10 CFR 76.76 should be consulted.
Section 396
Compliance with this requirement is demonstrated by documentation that supports the
implementation of the requirements at DOE M 435.1-1, Section III.M.2. (a) through (e), or
documentation that supports the “Necessary and Sufficient Closure Process” or integrated “Safety
Management System,” or the DOE M 251.1-1A exemption process.
Supplemental References:
1. DOE, 1995. Implementation Guide for Nonreactor Nuclear Safety Design Criteria and
Explosives Safety Criteria, Revision G, Draft DOE G 420.1-X, September 1995.
2. DOE, 1993. Defense Programs Operations Manual, “Treatment of Proposed Backfits,”
Revision 0, Draft DPOM-FS-300, U.S. Department of Energy, Washington, D.C.,
February 5, 1993.
Chapter III - Transuranic Waste Requirements
III-116 DOE G 435.1-1
7-09-99
3. DOE, 1998. Directives System, DOE O 251.1A, U.S. Department of Energy,
Washington, D.C., January 30, 1998.
4. DOE, 1998. Directives System Manual, DOE M 251.1-1A, U.S. Department of Energy,
Washington, D.C., January 30, 1998.
III. M.(2) Facility Design. The following facility requirements and general
design criteria, as a minimum, apply:
(a) Confinement. Transuranic waste systems and components
shall be designed to maintain waste confinement.
Objective:
The objective of this requirement is to ensure that the design of transuranic waste management
facilities and equipment include features necessary to prevent the uncontrolled releases of
radioactive materials.
Discussion:
During the development of DOE O 435.1 and DOE M 435.1-1, the unexpected or uncontrolled
release of radioactive materials at different stages of waste management were identified as
potential hazards that could impact workers, the public, or the environment. The DOE M 435.1
1, Section I.1.E.(18) invokes the Facility Safety and Life Cycle Asset Management Orders,
DOE O 420.1 and DOE O 430.1A, respectively, as directives applicable to the design of
radioactive waste management facilities. The current requirement supplements those directives by
specifically requiring that waste management systems and components of those systems be
designed to maintain waste confinement.
The term “confinement” is defined as:
“An area having structures or systems from which releases of hazardous materials are
controlled. Primary confinement systems are process enclosures (gloveboxes, conveyors,
transfer boxes, and other spaces normally containing hazardous materials). Secondary
confinement areas surround one or more primary confinement systems (operating area
compartments).”
In broad terms the purpose of waste confinement is to minimize the spread of radioactive and/or
hazardous materials during normal operations, abnormal operations, and potential accidents. The
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-117
7-09-99
Packaging and Transportation requirements (DOE M 435.1-1, Section III.L) address confinement
of solid transuranic waste in packaging. The Disposal requirements (DOE M 435.1-1, Section
III.P) invoke performance-based requirements for confinement of transuranic waste disposal
facilities. Therefore, the focus of the following guidance is on incorporating confinement features
into the design of treatment or liquid storage systems.
Section 397
The designs of confinement features should be tailored on a case-by-case basis (i.e., graded
approach) based on a consideration of the quantity and form of the transuranic waste and on the
conditions for potentially dispersing the contamination. For liquid waste storage or treatment, the
vessels, piping, pumps, valves, etc. must provide the primary confinement. Similarly, in treatment
systems for solid transuranic waste, hoods, gloveboxes, and process equipment must be designed
to control the spread of contamination. Design of these systems should take into account the
chemical characteristics of the materials to be managed so that appropriate materials of
construction can be selected. Engineering evaluations, trade-offs, and experience should be used
to develop practical designs that achieve the confinement objective. The adequacy of confinement
systems to effectively perform the needed functions needs to be documented and accepted
through the facility or operation safety analysis report or similar documentation.
Example: A treatment system for transuranic waste generates an acidic by-product waste
stream. The facility is designed so that the liquid waste stream is collected in tanks in the
facility, then is batch processed to meet the disposal facility’s waste acceptance criteria.
The design requires the storage vessel, piping, and valves to be constructed of stainless
steel rather than carbon steel because of the pH of the waste stream. In addition, all of
the piping and connections are to be welded construction to prevent the potential for
leaks developing at threaded or flanged fittings.
The need to design secondary confinement into the waste management systems or components
needs to be based on the analysis of the hazards associated with the potential failure of the
primary systems. However, it is generally expected that systems handling liquid wastes will have
secondary confinement to minimize the impacts of leaks, spills, or overflows. The secondary level
of confinement may be provided by use of double-walled equipment, e.g., double-walled vessels
or pipelines, or by using catchments, e.g., diked or bermed areas, or drip pans.
Designs must also account for the flow of air necessary to maintain waste confinement. Air flow
is to be from areas of lesser contamination to areas of greater contamination. To ensure that
proper airflow is maintained, the ventilation system design includes equipment which monitors air
pressure between different levels of confinement and provides alarms if an adequate pressure
differential is not maintained. From the area of highest contamination the air needs to be
exhausted through an appropriate filtration system (see guidance below on ventilation).
Chapter III - Transuranic Waste Requirements
III-118 DOE G 435.1-1
7-09-99
Example: A treatment facility is designed for processing remote-handled transuranic
waste in a process cell. The process cell is in a room which serves as a secondary
confinement. The building ventilation system is designed so that the air flows from the
nonradiological portions of the building, into the process room, and from the process
room into the process cell. The ventilation system is also designed to measure the
relative pressure between adjacent confinement layers. If the pressure within the process
cell is not negative relative to the pressure in the process room, or if the pressure in the
process room is not negative relative to the pressure in the rest of the building an alarm
sounds to indicate that confinement has been compromised.
Section 398
Compliance with this requirement is demonstrated by transuranic waste treatment and storage
facilities providing primary and secondary confinement commensurate with hazards identified in a
safety analysis or similar documentation.
Supplemental References: None.
III. M.(2) Facility Design. The following facility requirements and general
design criteria, as a minimum, apply:
(b) Ventilation.
1. Design of transuranic waste treatment and storage
facilities shall include ventilation, if applicable, through
an appropriate filtration system to maintain the release
of radioactive material in airborne effluents within the
requirements and guidelines specified in applicable
requirements.
2. When conditions exist for generating gases in flammable
or explosive concentrations in treatment or storage
facilities, ventilation or other measures shall be
provided to keep the gases in a non-flammable and non
explosive condition. Where concentrations of explosive
or flammable gases are expected to approach the lower
flammability limit, measures shall be taken to prevent
deflagration or detonation.
Objective:
The objective of this requirement is to ensure that airborne effluents released from transuranic
waste management facilities are in accordance with applicable DOE Orders and external
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-119
7-09-99
regulations, and to preclude or mitigate the accumulation of flammable or explosive gases which
could lead to fire or explosion and the uncontrolled release of radioactive material.
Discussion:
This requirement is based on a similar requirement developed to address a group of hazards that
was identified during the development of the high-level waste chapter of the Radioactive Waste
Management Manual, DOE M 435.1-1. During the development of the Manual, it was
determined that hazardous conditions can result from the unexpected or uncontrolled release of
radioactive material that could result from poorly designed ventilation systems or due to the
accumulation and ignition of flammable or explosive gases. Similar situations could occur at a
transuranic waste management facility and should be addressed to prevent uncontrolled airborne
releases of radioactivity that could endanger workers, the public, or the environment.
Subrequirement III.M.(2)(b)1 is discussed below under Airborne Effluent Filtration Systems and
subrequirement III.M.(2)(b)2 is discussed under Flammable and Explosive Gases.
Airborne Effluent Filtration Systems. The subrequirement to maintain radioactive material in
airborne effluents from transuranic waste management facilities to appropriate levels through the
use of filtration systems is to be implemented using the graded approach. This requirement is
intended to ensure that transuranic waste management facilities have adequate filtration where
necessary, not to dictate that each facility must have a particular type of air filtration or removal
efficiency. Therefore, the safety analysis or assessment for each facility will provide the basis for
determining the level of filtration required.
Section 399
Example 1: A transuranic waste treatment facility is constructed so transuranic waste
packages can be opened, the waste sorted, and the appropriate waste thermally treated.
In order to ensure worker protection, the building ventilation system is constructed to
draw air from radiologically clean areas, to radiologically-controlled areas and finally
to airborne contamination areas such as glove boxes and thermal treatment equipment.
Through the auditable safety assessment, it is determined that the potential exists for
releases of radioactive materials through the exhaust system. The building exhaust
system is therefore equipped with high-efficiency particulate air filters to ensure that
releases are controlled to within limits. Monitoring is used to ensure the necessary
removal efficiency is maintained by the air filter system.
Example 2: A storage building is designed and operated to receive only closed
containers of transuranic waste and to perform nondestructive testing. Through the
preparation of an auditable safety assessment it is determined that the potential for
release of radioactivity in the building is very low. Consequently, the ventilation system
provided for the building is only for climate control and not for contamination control.
The building exhaust system is determined to need no extra filtration to comply with the
Chapter III - Transuranic Waste Requirements
III-120 DOE G 435.1-1
7-09-99
requirements to meet applicable release standards, and the rationale and basis of the
analysis is incorporated into the facility safety documentation.
Standards for DOE compliance with airborne releases are contained in DOE 5400.5, Radiation
Protection of the Public and the Environment, and 40 CFR Part 61. The limits for release cited
in these documents are for the DOE site (i.e., all the activities of the Department), not for
individual facilities. Therefore, the operational limits for any individual facility need to be
established based on the potential impacts from all facilities on the site. Consistent with
Departmental practices and an underlying principle in development of the Radioactive Waste
Management Manual, airborne effluent releases need to be kept as low as reasonably achievable.
The number, size, and design of air filtration equipment need to meet the performance
requirements dictated by the safety analysis or assessment. The location of air filtration units in
the ventilation system is established as close as practical to the source of contamination so as to
minimize spread to the remainder of the ventilation system. The system is designed for ease of
maintenance and periodic inspection and has provisions (test ports) to facilitate insertion of
measuring devices for testing filter performance. Where larger loads are expected or predicted on
the filtration systems (e.g., dusty condition), pre-filters need to be considered to extend the life of
the main filter and reduce maintenance.
Flammable and Explosive Gases. The subrequirement addressing explosive or flammable
concentrations of gases is intended to ensure that the design of facilities and equipment includes
consideration of the potential for generating these types of gases. Generation of flammable or
explosive gases has been a concern in the storage of liquid waste (e.g., high-level waste tanks),
but also needs to be recognized as a potential problem in other situations, such as in treatment
systems.
Section 400
Where sampling data and safety analyses indicate a potential for accumulating gases in
concentrations approaching the lower flammability limit, facilities and equipment shall be provided
to prevent the conditions which could lead to fire or explosion. This is normally accomplished by
the design and installation of ventilation equipment which provides enough air flow to maintain
gases below flammable or explosive concentrations. In situations where gas evolution is episodic
and the concentration of gases approaches the lower flammability limit for short periods of time in
spite of the ventilation system, spark-proof technology needs to be employed in the design of
ventilation equipment so that the equipment itself does not become a source of ignition.
Attention to fire protection for the filtration system also needs to be considered to ensure the
facility can perform under off-normal conditions. Guidance for protection of filtration systems in
ventilation plenums for nuclear facilities is provided in the Fire Protection Design Criteria (DOE
STD-1066-97). This guidance addresses materials of construction, location of filters, fire ratings
of protective walls, and internal detectors for fire and heat.
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-121
7-09-99
Other methods can be employed to prevent conditions which could lead to ignition of flammable
or explosive gases. One such method is the introduction of a sufficient flow of inert gases into the
headspace where flammable or explosive gases would accumulate. The inert gases need to be
supplied at a rate that keeps the concentration of the flammable or explosive gases and of
available oxygen/oxidants below levels that could result in deflagration or detonation. As with
ventilation equipment, the specific conditions of gas generation and of providing an inert
atmosphere in the headspace must be evaluated and a decision made as to whether spark-proof
technology should be included in the design of the system.
Compliance with this requirement is demonstrated by analyses that support the level of filtration
provided on a transuranic waste management facility, and if airborne effluent monitoring data are
available, a demonstration of compliance with the site-established operational guidelines for the
facility. In addition, acceptable implementation is demonstrated by analyses, monitoring data, or
both showing that the potential for generation of explosive or flammable concentrations of gases
has been considered and where the potential exists, the presence of ventilation equipment or other
means that prevent deflagration or detonation. The analysis and rationale for the selected controls
must be documented in the radioactive waste management basis.
Supplemental References:
1. DOE, 1990. Radiation Protection of the Public and the Environment, DOE 5400.5, U.S.
Department of Energy, Washington, D.C., February 8, 1990.
2. DOE, 1997. Fire Protection Design Criteria, DOE-STD-1066-97, U.S. Department of
Energy, Washington, D.C., 1997.
3. EPA. National Emission Standards for Hazardous Air Pollutants, 40 CFR Part 61, U.S.
Environmental Protection Agency, Washington, D.C.
III. M.(2) Facility Design. The following facility requirements and general
design criteria, as a minimum, apply:
Section 401
(c) Consideration of Decontamination and Decommissioning.
Areas in new and modifications to existing transuranic waste
management facilities that are subject to contamination with
radioactive or other hazardous materials shall be designed to
facilitate decontamination. For such facilities a proposed
decommissioning method or a conversion method leading to
reuse shall be described.
Chapter III - Transuranic Waste Requirements
III-122 DOE G 435.1-1
7-09-99
Objective:
The objective of this requirement is to ensure the incorporation of the concept of life-cycle waste
management into the design and construction of radioactive waste management facilities to
minimize the amount of radioactive waste that must be managed in the future from
decontamination and decommissioning activities, and to reduce the number of facilities that must
be dismantled due to contamination rather than re-used for another beneficial purpose.
Discussion:
During the development of DOE O 435.1 and DOE M 435.1-1, the concept of life-cycle
management of waste was identified as a key theme that would promote safety and provide a
long-term benefit in reducing hazards associated with radioactive waste management. This
requirement was developed to extend the life-cycle management concept to the design of facilities
used for the management of radioactive waste. The goals of applying this concept at the design
stage are to minimize the future generation of waste and to promote the planning for subsequent
beneficial use or decommissioning of a facility at the end of its original mission. Decontamination
and decommissioning activities also becoming a significant part of the life-cycle costs for
transuranic waste facilities. This requirement addresses this situation by promoting proactive
consideration of design features that facilitate decontamination and dismantlement activities that
will lead to a beneficial use or decommissioning.
New transuranic waste facilities are defined as those whose design basis was not approved prior
to the implementation date of DOE O 435.1. The term design basis is defined in the Manual
Definitions. If a transuranic waste facility’s design basis is defined after the issuance date of DOE
O 435.1, the requirements of this section are applicable. Similarly, if a significant modification to
an existing facility is made after the implementation date of DOE O 435.1, this requirement to
incorporate features that facilitate decontamination and to consider eventual facility
decommissioning or reuse applies. Application of these requirements to existing facilities should
be considered and applied on a case-by-case basis. To support this decision, an analysis needs to
be conducted comparing the expected benefits by the application of these requirements to the
costs of implementing such measures. These costs include programmatic impacts, resource and
schedule impacts, as well as potential impacts such as additional worker exposures due to
radiation and chemical hazards, and future costs.
Design to Facilitate Decontamination. Decontamination is defined by the Implementation Guide
to DOE O 420.1, Facility Design, as “the act of removing a chemical, biological, or radiological
contaminant from or neutralizing its potential effect on a person, object, or environment by
washing, chemical action, mechanical cleaning, or other techniques.” In conjunction with DOE O
420.1, DOE M 435.1-1 requires that transuranic waste facilities incorporate measures to reduce
areas of contamination or to simplify decontamination of areas that may become contaminated
Section 402
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-123
7-09-99
with radioactive or hazardous materials to facilitate either decommissioning or reuse of the
facility. Following are design features that need to be considered:
• Service piping, conduits, and ductwork kept to a minimum in areas that could be
potentially contaminated and, if included in such areas, their design arranged to
facilitate decontamination.
• Cracks, crevices, and joints filled and finished smooth to prevent accumulation of
contaminated material.
• Walls, ceiling, and floors in areas vulnerable to contamination finished with
washable or strippable coverings.
• Metal liners, e.g., stainless steel cell lining, used in areas that have the potential to
become highly contaminated with radioactive materials.
• Contaminated or potentially contaminated piping systems have provisions for
flushing and/or cleaning.
• Accessible, removable covers for inspection and cleanouts provided.
• Construction materials that reduce the amount of radioactive materials requiring
disposal and that are easily decontaminated.
Example: A transuranic waste thermal treatment facility is being planned. The facility
design is reviewed to determine the ease with which the constructed treatment facility
could be decontaminated following its operational life. The evaluation finds that
transuranic waste transfer lines can be modified by including liners, and certain areas
are found to be amenable to the use of strippable coverings. The design is modified to
incorporate these changes and improve the ability to decontaminate the facility.
Design to Support Decommissioning. Decommissioning, also defined in DOE O 420.1, is “the
process of closing and securing a nuclear facility or nuclear materials storage facility to provide
adequate protection from radiation exposure and to isolate radioactive contamination from the
human environment.” Design features that need to be considered to support decommissioning or
a reuse of the facility include:
• Use of modular radiation shielding, in lieu of or in addition to, monolithic shielding
walls.
Chapter III - Transuranic Waste Requirements
III-124 DOE G 435.1-1
7-09-99
• Use of modular, separable confinements to preclude contamination of fixed
portions of the structure.
• Designs that ease cut-up, dismantlement, removal, and packaging of contaminated
equipment, such as glove boxes, air filtration equipment, large tanks, vessels, and
ductwork, from the facility.
• Use of localized liquid transfer systems that avoid long runs of buried,
contaminated piping; emphasis on localized batch solidification of liquid waste.
Special provisions may also be included in the design to ensure the integrity of
joints in buried pipelines.
• Piping systems that carry contaminated or potentially contaminated liquid that free
drain by gravity.
• Location of exhaust filtration components of ventilation systems at or near
individual enclosures to minimize long runs of internally contaminated ductwork.
• Equipment, including effluent decontamination equipment, that precludes to the
extent practicable, the accumulation of radioactive or other hazardous materials in
relatively inaccessible areas, including turns in piping and ductwork.
• Provisions for suitable clearances, where practical, to accommodate remote
handling and safety surveillance equipment required for future decontamination
and decommissioning.
• Use of lifting lugs on large tanks and equipment.
Section 403
Decommissioning and Reuse Planning. Due to the high life-cycle costs of transuranic waste
facilities, this subrequirement is also intended to promote post-mission planning of transuranic
waste facilities by requiring the identification of possible decommissioning methods or reuses of
transuranic waste facilities as early as possible. To meet this requirement transuranic waste
facility designs, or significant modification efforts, need to include analysis to determine the best
decommissioning methods, using currently available technologies, and factor the results of this
analysis into the facility’s design. Likewise, if a reuse of the facility is envisioned, any features
that can support this reuse mission need to be considered in the design effort.
Life-Cycle Asset Management, DOE O 430.1A, addresses deactivation and decommissioning
requirements of DOE facilities. Refer to DOE O 430.1A and its Guides for further information
on additional information on deactivation and decommissioning activities. Refer also to a new
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-125
7-09-99
DOE Standard, listed below, on the integration of safety and health requirements into facility
disposition activities.
Compliance with this requirement is demonstrated by the existence of design documentation that
indicates decontamination was considered during the design of new transuranic waste facilities or
significant modifications to transuranic waste facilities. Additionally, Site-Wide Radioactive
Waste Management Program documentation demonstrates that post-mission planning was
considered, as early as possible in the life of a facility, to assist in the identification of possible
decommissioning methods or facility reuse.
Supplemental References:
1. DOE, 1995. Implementation Guide for Nonreactor Nuclear Safety Design Criteria and
Explosives Safety Criteria, Revision G, Draft G 420.1-X, U.S. Department of Energy,
Washington, D.C., September 1995.
2. DOE, 1997. Decommissioning Implementation Guide, Draft G 430.1-4, U.S. Department
of Energy, Washington, D.C., October 1, 1997.
3. DOE, 1997. Integration of Safety and Health into Facility Disposition Activities, Draft
for DOE Complex Wide Review 9/26/97, DOE-STD-1120-98, U.S. Department of
Energy, Washington, D.C., September 26, 1997.
4. DOE, 1998. Life-Cycle Asset Management, DOE O 430.1A, U.S. Department of Energy,
Washington, D.C., October 14, 1998.
III. M.(2) Facility Design. The following facility requirements and general
design criteria, as a minimum, apply:
(d) Instrumentation and Control Systems. Engineering controls
shall be incorporated in the design and engineering of
transuranic waste treatment and storage facilities to provide
volume inventory data and to prevent spills, leaks, and
overflows from tanks or confinement systems.
Objective:
The objective of this requirement is to ensure that engineered controls are included in the design
of transuranic waste storage and treatment facilities to minimize the likelihood of release of
radionuclides that could lead to exposures or contamination of the environment.
Chapter III - Transuranic Waste Requirements
III-126 DOE G 435.1-1
7-09-99
Discussion:
Section 404
This requirement for instrumentation and engineering controls is invoked to address a group of
hazards that was identified during the development of DOE O 435.1 and DOE M 435.1-1 -- the
failure to promptly detect and prevent conditions which could lead to a release of radioactive
material from transuranic waste storage or treatment facilities that could impact workers, the
public, or the environment. This requirement is closely related to the previous design requirement
for monitoring systems. However, this requirement focuses on controls to prevent the loss of
containment.
The engineered controls referred to in this requirement are those systems or design features that
are provided to detect and prevent the loss of containment of transuranic wastes volumes in
treatment or storage facilities, and to provide volume inventory data, where appropriate. During
the design of storage or treatment systems, the flow of waste material through the system should
be evaluated to determine where there is a potential for the loss of containment by overfilling or
spilling. Examples of engineering controls include flowmeters and level-sensing devices coupled
with anti-siphon devices or shut-off valves, and any other instrumentation and controls that
maintain sufficient freeboard within a storage vessel or unit. Other instruments and controls
include devices that measure changes in characteristics of liquid waste, e.g., temperature,
pressure, pH, and/or other characteristics providing a measure of a materials stability, that are
combined with shutoff or diversion routing devices. Although this requirement most obviously
applies to management of liquid wastes, it also needs to be considered and applied, as appropriate,
to solid transuranic waste.
Example 1: A tank system has been installed to receive and store transuranic wastes
pending treatment. The wastes are transferred by pipeline to the tanks. The design of
each tank includes a liquid level sensor which is coupled to an alarm and diversion valve.
When the liquid level is at 88% of the tank depth an alarm sounds on the control room
annunciator panel. When the liquid level reaches 92% of the tank depth the diversion
valve is automatically actuated and the liquid level is transferred to a spare tank.
Example 2: A facility is being designed to provide thermal treatment of transuranic
waste. The thermal treatment unit is designed for continuous feed and continuous
discharge of the ash and slag to a disposal container. To avoid the loss of containment,
an interlock is included in the design which prevents feed from entering the combustion
chamber and waste product from leaving the chamber if a disposal container is not in
place at the discharge of the thermal treatment unit.
The graded approach is used in determining the appropriate level of engineering controls to
incorporate into the design of transuranic waste management facilities. As indicated in the
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-127
7-09-99
preceding examples, sensing devices, alarms, and spill or overflow prevention features are most
appropriate in facilities storing liquids or with continuous, automatic processes. Other instances
involving bulk or solid transuranic waste may need to invoke these controls as well, where a
simple shutoff of the equipment could prevent overfilling or other hazardous conditions.
Section 405
The design of engineering controls to meet this requirement will most likely be directed by the
facility-specific safety analysis or safety assessment prepared for the waste management facility.
Such safety analyses or assessments may dictate that certain engineering controls be designed as
safety-class or safety-significant systems, structures, or components (SSC) to ensure they survive
design-basis accidents. Use of the safety analysis process, as prescribed by DOE 5480.23,
Nuclear Safety Analysis Reports, to identify the necessary engineering controls to meet this
requirement for both new and upgrades to existing transuranic waste treatment and storage
facilities, is considered appropriate and encouraged.
Loss of containment at a waste storage or treatment facility can result from overflows, spills,
leaks, or siphoning of waste from a storage vessel. Incorporation of design measures at these
facilities to prevent such loss of containment is necessary, but is not necessarily sufficient to
adequately control the hazards associated with release of radioactive materials. Equipment of this
nature, in spite of rigorous maintenance, can fail over its expected service life. Therefore, as
discussed in the above guidance on confinement, an engineered barrier to fully contain the spilled
waste or a diversion mechanism to channel the waste to a desired location provides defense-in
depth for the circumstances where the engineering controls do not function.
Example: At the Liquid Transuranic Waste Storage Facility, the engineering controls on
the liquid transuranic waste storage tanks include a waste feed line shut-off valve,
activated by a tank liquid level-sensing device, to prevent overflow of waste from the
tank. In addition, the tank is designed with an overflow line so that if the valve
malfunctions and the tank is overfilled, the overflow is routed to another waste tank that
is maintained as a spare at the storage facility.
Compliance with this requirement is demonstrated by the incorporation of engineering controls in
storage facilities or treatment processes that provide detection and automatic shutoff or diversion
of the flow of waste materials that could otherwise spill or overflow the system as documented in
the facility’s safety documentation.
Supplemental References:
1. DOE, 1995. Implementation Guide for Nonreactor Nuclear Safety Design Criteria and
Explosives Safety Criteria, Revision G, Draft DOE G 420.1-X, U.S. Department of
Energy, Washington, D.C., September 1995.
Chapter III - Transuranic Waste Requirements
III-128 DOE G 435.1-1
7-09-99
2. DOE, 1992. Nuclear Safety Analysis Reports, DOE 5480.23, U.S. Department of
Energy, Washington, D.C., April 10, 1992.
III. M.(2) Facility Design. The following facility requirements and general
design criteria, as a minimum, apply:
(e) Monitoring. Monitoring and/or leak detection capabilities
shall be incorporated in the design and engineering of
transuranic waste storage, treatment, and disposal facilities to
provide rapid identification of failed confinement and/or other
abnormal conditions.
Objective:
The objective of this requirement is to ensure the design and installation of equipment capable of
identifying failures in containing transuranic waste and other conditions that could result in
exposure of the public, workers or releases to the environment.
Discussion:
Section 406
During the development of DOE O 435.1 and DOE M 435.1-1, the hazards analysis identified
releases resulting from confinement failure of a component or from failure to stop transfer of
waste when the receiving vessel (e.g., tank or bin) is full as a hazard that needs to be mitigated.
The requirement discussed here is generally directed toward prompt detection of acute releases
(releases that are detectable visually or by some other gross indicator) that become apparent over
a time frame of hours or days. In contrast, the requirements for monitoring (see DOE M 435.1-1,
Section III.Q) for compliance with release limits is directed toward detection of releases that
generally evolve slowly and may be detected by low threshold environmental monitoring devices
weeks, months, or longer after the release begins.
As in implementation of all of the requirements of DOE O 435.1 and DOE M 435.1-1, the graded
approach is used for determining the appropriate level of rigor in applying this control to the
management systems employed at a particular waste management facility. Also, monitoring for
leakage and contamination spread needs to be performed by means appropriate for the type and
character of radioactive waste being managed at the facility. Rigorous application of this
requirement may be most appropriate for circumstances involving storage or treatment of liquid
transuranic waste, for example, highly acidic liquid waste in a single-walled, mild steel tank may
require continuous monitoring coupled with alarms and transfer equipment. A treatment facility
involving solid waste may need to implement monitoring systems such as portable constant air
monitoring systems designed to detect airborne contamination spread from dry processes. A
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-129
7-09-99
facility storing containerized waste may rely on a program of container inspections to meet the
needs for monitoring for leaks and abnormal conditions.
For transfer systems, designers may need to consider the use of continuous flow monitors to
allow comparisons of total volume input to total volume output as an indicator of the integrity of
the transfer system. The containment integrity of waste transfer systems can also be monitored
for radiation levels in excess of those expected from residual waste in the transfer system.
A highly reliable means of monitoring for releases is the use of secondary confinement which is
then checked for waste. It also offers the benefit of providing defense-in-depth in containment of
releases of transuranic waste.
Example: A liquid transuranic waste transfer line from a storage tank to a treatment
facility is enclosed in a larger diameter secondary containment tube. The transfer line
and containment tube were constructed with sufficient pitch to cause any leakage into the
containment tube to flow back to the storage tank area. The transfer line developed a
leak at a coupling which was discovered when waste was found in the secondary
containment at the storage tank area.
Section 407
What constitutes rapid detection of failed confinement or abnormal conditions needs to be
established for each facility, operation, or activity. Monitoring design requirements and
engineering controls to address catastrophic failures will be established through the conduct of
safety analyses. The failures and conditions being addressed by this requirement are those that are
not catastrophic, but could result in releases of radioactivity or doses to workers or the public in
excess of established limits if they were allowed to continue over a period of hours or days.
Detection equipment needs to be designed to detect confinement failures or abnormal conditions
rapidly enough that action can be taken before the situation degrades to the point that response
and recovery would result in doses to workers that approach the dose limits for radiation
protection of workers (10 CFR Part 835). Similarly if the failure releases radioactivity to a air or
liquid effluent stream, detection needs to occur rapidly enough to prevent environmental releases
from exceeding annual limits.
Compliance with this requirement is demonstrated by a documented basis for the design of
monitoring for transuranic waste systems and the capability to monitor waste volume and detect
volume changes in a time frame that will allow implementation of corrective measures to limit
public and worker doses to allowable levels and to limit releases to the environment.
Supplemental References:
1. DOE. Occupational Radiation Protection, 10 CFR Part 835, U.S. Department of Energy,
Washington, D.C.
Chapter III - Transuranic Waste Requirements
III-130 DOE G 435.1-1
7-09-99
III. N. Storage.
The following requirements are in addition to those in Chapter I of this Manual.
(1) Storage Prohibitions. Transuranic waste in storage shall not be readily
capable of detonation, explosive decomposition, reaction at anticipated
pressures and temperatures, or explosive reaction with water. Prior to
storage, pyrophoric materials shall be treated, prepared, and packaged to be
nonflammable.
Objective:
The objective of this requirement is to promote safe storage of transuranic waste by eliminating
from storage materials which could result in fires or explosions due to their reactivity or
ignitability.
Discussion:
The safe storage of transuranic waste can be jeopardized by the presence of materials which may
ignite or explode. To avoid the potential for accidental releases from stored wastes, this
requirement prohibits storage of materials that are known to be readily capable of ignition or
explosion, or which may degrade over time to be ignitable or explosive. In establishing waste
acceptance criteria for storage, waste managers must prohibit the acceptance of materials which
have the potential of igniting or exploding. The following materials are not to be stored:
• Reactive metals - metals that can react violently with water, form potentially explosive
mixtures with water, or ignite when exposed to air; e.g., uranium or plutonium metal
turnings are reactive metals.
• Certain dried ion exchange resins - organic ion exchange resins which have been used for
treating solutions containing nitrates have the potential of igniting or exploding if they are
allowed to dry out.
• Cellulosic materials contaminated with strong oxidizers - cellulosic materials can
spontaneously ignite due to the presence of strong oxidizers, e.g., concentrated nitric acid.
Section 408
• Volatile materials if stored in areas of high temperatures - storage of volatile materials in
closed containers subject to high temperature can result in pressurization of the container
and, depending on the waste materials, evolution of flammable gases.
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-131
7-09-99
• Pyrophoric materials - nonradioactive materials which can ignite spontaneously are not to
be packaged for storage. Radionuclides which may be pyrophoric are to constitute less
than 1% by weight of the container contents unless they are treated to eliminate the
pyrophoric characteristic.
When waste with the characteristics described above have been generated, it is necessary to treat
them prior to placing them into storage. The treatment may consist of causing the reaction to
occur under controlled conditions, e.g., oxidation of pyrophoric metals such as uranium fines, or
may involve the stabilization of waste materials so that they are no longer flammable or explosive.
Example 1: In the process of cleaning out a glovebox, paper absorbent was used to clean
up an acid spill. Prior to placing the absorbent material into a drum for prolonged
storage, it is taken to a RCRA-permitted treatment facility where the acid is neutralized
and the absorbent dried. The treated absorbent materials are then packaged to meet the
waste acceptance requirements of the transuranic waste storage facility.
Example 2: Metal fines from machining operations are routinely generated as a
transuranic waste stream. In order to meet the storage requirements and make the waste
acceptable for future disposal, the fines are treated by solidification in a cement matrix
in 1-gallon cans. Upon curing, the 1-gallon cans are placed in 55-gallon drums along
with filler material that prevents shifting within the drum. The drums are then sent to the
on-site storage facility.
Compliance with this requirement is demonstrated by having waste acceptance requirements
which prohibit waste that is ignitable or explosive from being accepted for storage unless it has
been treated.
Supplemental References: None.
III. N.(2) Storage Integrity. Transuranic waste shall be stored in a location and
manner that protects the integrity of waste for the expected time of
storage and minimizes worker exposure.
Objective:
The objective of this requirement is to ensure that the selection of the location and method for
storing transuranic waste is made so that both workers and the containers of waste are provided
with adequate protection.
Chapter III - Transuranic Waste Requirements
III-132 DOE G 435.1-1
7-09-99
Discussion:
During the development of DOE O 435.1 and DOE M 435.1-1, the storage of radioactive waste
was identified as an activity that presented potential risk to the public, workers, and the
environment. Numerous weaknesses and conditions which could lead to release of waste or
exposure of workers were identified during the safety and hazards analysis and subsequent
reviews conducted in support of the Manual documentation. In addition, previous reviews of
radioactive waste storage conditions and management practices (e.g., Complex-Wide Review of
DOE’s Low-Level Waste Management ES&H Vulnerabilities) revealed inadequately or
improperly stored waste, which presents the possibility of human exposure to radiation and the
potential for adverse environmental effects.
Section 409
The evaluations of storage that were conducted during development of the Order and Manual
revealed a variety of current practices and required lengths of storage for transuranic waste.
Transuranic waste is stored in dense-pack arrays, in earthen-covered configurations, and in
modern, RCRA-compliant storage facilities. In addition, in order to protect the transuranic waste
containers, buildings not originally designed or intended for storage are sometimes used when
other storage capacity is not available.
As discussed in the General Requirements guidance on storage (DOE M 435.1-1, Section
I.2.F.(13)), a principal element of proper storage is ensuring that the container is protected from
degradation so that it can perform its intended function until it is disposed. This requires that
containers be protected from mechanical damage and from environmental conditions that could
impact the waste and container.
Example 1: Due to a large decommissioning project generating unanticipated volumes of
transuranic waste, Site Z decided to store transuranic waste outside until indoor storage
space could be made available. In accordance with the Packaging and Transportation
requirements, filtered vents were installed on the drums used for packaging the waste.
However, in establishing the radioactive waste management basis for the outside storage
pad, personnel failed to recognize the potential for precipitation entering the drums.
Rain accumulated on the tops of the drums, then due to fluctuations in barometric
pressure, the drums “breathed” through the vents. Water was sucked in through the
vents resulting in the need to repackage the waste so that the containers would not
corrode and so they could meet the waste acceptance requirements for disposal.
Subsequently, any waste drums that had to be left outside were provided with covers that
prevented water from accumulating on the tops.
Example 2: Due to a large backlog of transuranic waste, Site Y is required to store
transuranic waste outside until it can be shipped to the Waste Isolation Pilot Plant for
disposal. The waste is stored in containers which prevent the entrance of precipitation
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-133
7-09-99
(lid with lips extending down over the sides) and which resist corrosion (painted carbon
steel). Controls are in place to limit mechanical damage from vehicles and other
operations in the area. The containers are inspected on a monthly basis for deterioration
and repaired as necessary to maintain containment of the waste (e.g., painted,
contained). Personnel are only in the outside storage area during periods of inspections,
container maintenance, and container movement. The outside storage has been analyzed
and documented to provide adequate protection for the expected storage time. This
storage maintains the integrity of the waste and minimizes worker exposure.
Transuranic waste may be stored in facilities designed specifically for waste storage, as well as in
facilities or portions of facilities which originally served another function but have now been
converted for use a storage facility. Any facility to be used for transuranic waste storage must
comply with the applicable requirements of DOE O 420.1, Facility Safety. Special attention is to
be given to DOE O 420.1, Section 4.2, Fire Protection, when a facility is to be used for the
storage of combustible materials. If facilities have the appropriate provisions (e.g., ventilation,
fire suppression) for the type of waste being stored, their use is preferable to storing the waste
containers outside and subjecting them to the elements.
Section 410
In making a decision to use a facility for storage and in developing a radioactive waste
management basis for the activity, particular attention to protection of workers is needed. Waste
is not to be stored in areas where workers are required to spend extended periods of time in
performing other duties (i.e., any duties not related to managing and monitoring the waste). This
limits the facilities or areas of facilities that should be used for waste storage to those that are
excess to current site missions or those that are infrequently accessed as part of normal
operations.
Compliance with this requirement is demonstrated if sites have storage capabilities for transuranic
waste that provide protection of waste containers so that their integrity will not be damaged
through physical or chemical (corrosion) processes and that keep personnel from spending
extended periods of time in the areas where transuranic waste is stored.
Supplemental References: None.
III. N.(3) Container Inspection. A process shall be developed and implemented
for inspecting and maintaining containers of transuranic waste to
ensure container integrity is not compromised.
Chapter III - Transuranic Waste Requirements
III-134 DOE G 435.1-1
7-09-99
Objective:
The objective of this requirement is to prevent or minimize the potential exposure of workers and
release of radioactive contamination to the environment that could result from allowing
transuranic waste containers to degrade. The requirement is intended to ensure that the
confinement abilities of containers is routinely evaluated and action taken to ensure the waste
remains contained.
Discussion:
The containment of transuranic waste in its container is essential for its safe and effective
management. During the development of the Radioactive Waste Management Manual
(DOE M 435.1), inadequate or substandard waste containers and deterioration of containers were
identified as a conditions that could result in the loss of waste containment and potentially impact
workers, the public, or the environment. The General Requirements of the Radioactive Waste
Management Manual (DOE M 435.1-1, Section I.2.F.(13)) assign the Field Element Manager
responsibility to ensure that all waste is stored in a manner that protects the integrity of the waste
container for the expected time of storage. The responsibility for providing adequate storage that
protects the integrity of waste containers is complemented by this requirement to routinely inspect
the packages and correct any conditions of container deterioration. This is particularly important
for transuranic waste that is to be in relatively long-term storage (e.g., waste that will not be
shipped to WIPP for a number of years or non-defense waste for which a disposal facility has not
been identified). This requirement applies to all storage of transuranic waste, not just storage at a
designated storage facility.
Example: An assay facility has two areas where waste is staged, one for containers of
waste awaiting assay and another for those to be placed into storage after they have been
assayed. The assay facility personnel have established operational procedures for the
routine physical examination of all waste containers in either staging area. Existence of
the inspection process mitigates concerns about waste residing in the staging areas for
longer than normal as a result of assay equipment failure or maintenance. The facility
procedures also address actions to be taken if waste container integrity is suspect.
Section 411
Inspection. The waste container inspection and corrective action process is to ensure that
container integrity is maintained throughout the storage or staging period. The process needs to
be tailored to the storage situation. Ideally, the storage configuration would allow visual or
remote visual inspections of the outsides of waste containers. The inspection considers:
• General condition of the container, such as areas of rust, scratches, and minor
dents. The inspection process includes an evaluation of minor surface conditions
to determine their impact on the integrity of the container. Such conditions may
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-135
7-09-99
not require any action, but are to be noted and corrected if there is a trend
indicating eventual deterioration.
• Functioning of the waste container closures. Waste container closures are in place
and securely fastened.
• Evidence of leakage. Leakage can indicate a number of problems including
unacceptable materials in the waste, inadequate internal containers, insufficient
absorbent, or failure of the outer container.
• Evidence of structural problems with the container such as buckling or split seams.
• Bulging of the waste container indicating build up of pressure in the container.
Bulging of the container may indicate inappropriate storage conditions (e.g.,
storing tightly sealed waste containers where they are subject to excessive
heating), a condition inside the container that needs to be remediated, and the need
to replace the container.
• Examination of waste container marking and labeling to ensure that they are
maintained in a legible condition.
Example: Transuranic waste is stored in rows two drums wide and two drums high with
an aisle between the rows. The site procedure calls for an operator to inspect the
condition of the drums every two weeks and record any potentially adverse conditions.
Some older storage configurations (e.g., dense pack storage where there are multiple rows and
layers of waste packages without access space between them) may not allow for direct visual
inspection. In such cases, the inspection may have to be done using remote or indirect techniques.
Remote techniques include the use of video cameras which provide real time or recorded displays
of waste containers which are not accessible for direct inspection. Indirect methods include the
use of radiation detectors to determine when a waste container has failed. To the extent possible,
direct remote visual inspections are to be used in preference to indirect methods since indirect
methods force the inspection and maintenance process into a reactive mode of fixing problems
once they have occurred (as detected by an increase in radioactive contamination) rather than a
proactive mode of preventing breaching of the waste container.
Example: Drums stored in a dense pack array are in a building that has a continuous air
monitor. To ensure adverse waste package conditions are detected as soon as practical,
additional monitoring is performed on a routine basis. The additional monitoring
involves the collection of smear samples by placing swabs on extensions to check for
loose contamination within the array.
Chapter III - Transuranic Waste Requirements
III-136 DOE G 435.1-1
7-09-99
Waste containers should be physically examined about every 30 days to ensure that storage
conditions have not caused the integrity of the container to be compromised. All waste packaging
that exhibits serious deterioration or exhibits a potential for containment of the waste to be
jeopardized need to be replaced or overpacked.
Section 412
Example: During the routine inspection of waste drums at a staging area a drum was
identified as possibly damaged. Upon detailed inspection, it was determined that a seam
of the waste drum had separated. The waste was repackaged and the old drum removed
from service.
Maintenance. The process for waste container maintenance is to include preventive actions as
well as corrective actions. Preventive actions would address minor conditions associated with
ensuring waste containment. Actions might include cleaning and painting small areas on metal to
curb corrosion that could eventually compromise the container. The process also is to provide
capabilities to respond to more serious conditions up to and including breaching of the container
(e.g, from accidental puncture or corrosion).
Maintenance of containers in response to acute conditions (i.e., conditions where there is a release
or imminent threat of a release) provides for prompt containment of the release, assessment of the
situation, and remedying the situation. The immediate response is to ensure that release of
contamination is controlled. Control actions may be as simple as replacing a bolt or closure ring
on a drum, or covering a hole in a container with tape. More serious conditions may require
placing the waste container in a catch tray or immediately placing it in an overpack. The
condition causing the breach or potential breach must be assessed so that, if necessary, the
causative factors can be corrected. If corrosion is affecting the waste container, the reason for the
corrosion needs to be determined so an effective response can be made. If there is a corrosive
material in the waste container, overpacking may only temporarily correct the problem. In such a
situation, it may be more appropriate to treat the waste or to provide a liner that is resistant to
corrosion. If there is buckling of the waste container or split seams, an assessment needs to be
made of whether the contents are too heavy, whether the container is improperly designed, or
whether it was mishandled (e.g., dropped). In cases where an external event is the cause of the
damage (e.g., a waste container is dropped or struck by equipment), repackaging or overpacking
in a similar container is appropriate.
Example: The inspection process in a storage facility identified a waste drum that was
corroding even though the container was stored in acceptable conditions and the paint
on the drum was in good shape. Storage facility personnel recognized that there was a
need to investigate whether the contents of the container were causing the corrosion.
Evaluation of the container contents confirmed that the waste was contaminated with
corrosive material. The waste was treated to neutralize its corrosivity, then repackaged
in a similar container.
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-137
7-09-99
Waste managers are not to interpret the term “maintenance” to imply that refurbishment of
deteriorating waste containers is required. The basic premise of this requirement is that potential
doses to workers are to be avoided. Therefore, overpacking may be the most appropriate action
as opposed to an action requiring handling of the waste and a failed container.
Compliance with this requirement is demonstrated by a documented process for waste container
inspection and maintenance at every facility managing transuranic waste, and documentation for
all waste container inspections and maintenance actions performed.
Section 413
Supplemental References: None.
III. N.(4) Retrievable Earthen-Covered Storage. Plans for the removal of
transuranic waste from retrievable earthen-covered storage facilities
shall be established and maintained. Prior to commencing waste
retrieval activities, each waste storage site shall be evaluated to
determine relevant information on types, quantities, and location of
radioactive and hazardous chemicals as necessary to protect workers
during the retrieval process.
Objective:
The objective of this requirement is to promote the removal of retrievably-stored transuranic
waste from earthen-covered storage and its transfer to subsequent waste management facilities
where there is less potential of release to the environment. Additionally, the purpose of the
requirement is to ensure that, to the extent practical, information about the waste is collected and
analyzed so hazards associated with the waste can be mitigated through selection of equipment,
development of procedures, and implementation of work practices.
Discussion:
The General Requirements chapter of DOE M 435.1-1 assigns the Field Element Manager
responsibility for ensuring that waste is stored in a manner that is protective of the public,
workers, and the environment. Additionally, the Field Element Manager is responsible for
ensuring the integrity of waste containers during the time they are stored (DOE M 435.1-1,
Section I.2.F.(13)). This requirement supplements the General Requirement by encouraging the
removal of waste from storage configurations that may contribute to the degradation of waste
containers.
Following implementation of the 1970 Immediate Action Directive (AEC, 1970) concerning solid
waste management, the Department began storing waste suspected of being transuranic waste
Chapter III - Transuranic Waste Requirements
III-138 DOE G 435.1-1
7-09-99
with the intent of retrieving it for future disposal. Waste disposed of prior to the implementation
of the 1970 Immediate Action Directive is not retrievably stored transuranic waste and therefore,
is not subject to this requirement. Generally, such wastes are managed pursuant to the
Comprehensive Environmental Response, Compensation, and Liability Act.
To implement the Immediate Action Directive, a number of DOE sites designed storage
configurations that involved placement of containers of transuranic waste (or waste suspected of
being transuranic waste) in lined or unlined trenches, or at grade, then covering them with soil.
At the time of emplacement, the configuration was intended for 20-year retrievable storage.
Much of this waste is still in earthen-covered storage, some of it beyond the originally planned 20
years. Experience gained through investigations and retrieval activities has shown that in some
cases the integrity of the containers has been compromised (e.g., moisture condensing on metal
containers has led to significant rusting).
During the development of DOE M 435.1-1, Radioactive Waste Management Manual, a safety
and hazards analysis identified the potential release of radioactivity to the environment from waste
packages in earthen-covered storage and the concomitant hazard to retrieval workers, as
conditions for which radiological controls were needed. Likewise, it was also recognized that the
longer waste containers remain in earthen-covered storage configurations, the greater the
likelihood of a release. Therefore, this requirement was developed to promote the movement of
waste to more acceptable conditions (i.e., better storage conditions, treatment, or disposal). The
hazards to workers are to be mitigated by acquiring as much information as practical about what
will be encountered upon exhumation and implementing controls to address those hazards.
Section 414
Retrieval Plans. Plans for retrieval of waste from earthen-covered storage will vary depending on
the stage of development of the retrieval program, and will need to be updated (maintained) as the
program progresses. In the early stages, the planning will be primarily programmatic with the
focus on identifying and developing the information and infrastructure needed to effect retrieval.
This planning integrates with the documented Site-Wide Program (see DOE M 435.1-1, Section
I.2.F.(1)) because it reflects the same commitments and milestones addressed in the Site-Wide
Program. The plans for retrieval may suffice as the documentation for that portion of the Site-
Wide Program. Recognizing that some of the waste placed in earthen-covered storage may not
meet the current definition of transuranic waste, the planning needs to address determining
whether retrieved containers have transuranic or low-level waste, and the disposition of the
different types of waste. The early planning includes the following:
• The scope of the retrieval activity ( i.e., the facilities (trenches, above-grade pads,
etc.) from which waste will be retrieved);
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-139
7-09-99
• A conceptual description of the approach to be used (e.g., method of removing
overburden, means of removing tarps and/or plywood covering the waste
packages, contamination control during removal operations);
• Data collection (see Pre-Retrieval Evaluation below), analyses, and studies to be
conducted in support of retrieval operations;
• Identification of primary facilities and equipment needed to retrieve waste (weather
enclosures, drum handling equipment, drum venting equipment, earth moving
equipment, transportation vehicles);
• Identification of existing and new support facilities (e.g., needed treatment,
storage, and/or disposal facilities);
• Evaluation of retrieved waste containers (inspection, overpacking, assay);
• Management steps for retrieved packages (e.g., venting, storage, treatment,
disposal);
• Plans for decommissioning the earthen-covered storage facility following removal
of the waste; and
• The cost and schedule for preparing for and accomplishing retrieval of the waste.
Example: A site has waste that was placed into earthen-covered storage under the
assumption that it was transuranic waste. As part of the site-wide waste management
program, a document is prepared that describes the facilities and equipment envisioned
to be needed and the process for retrieving the waste. The document also includes a
schedule for collecting and evaluating data associated with the waste, providing the
needed facilities and equipment, developing control documentation (e.g., permits,
procedures, safety analysis report, health and safety plan), conducting startup activities
(operational readiness reviews), and performing the retrieval. The documentation also
includes a budget estimate for preparing and conducting the retrieval.
As information is acquired and the infrastructure to support retrieval evolves, the plans for
retrieval will need to be updated and become more focused. The planning will become more
project specific and include the development of the time-phased plans for retrieving waste,
characterization plans, radiological control plans, health and safety plans, and emergency response
plans. The planning done at this stage will also be more specific as to the process for exposing
and handling drums, including cover removal; waste management (e.g, contaminated soil, plastic,
plywood); inspections to be performed; handling non-routine drums (e.g., those that are bulging
Section 415
Chapter III - Transuranic Waste Requirements
III-140 DOE G 435.1-1
7-09-99
or deteriorated); venting of drums; assaying; specific plans for disposition of different waste types
(including segregation of defense and non-defense transuranic waste as discussed below); marking
and labeling; and movement of drums. The planning provides the basis for developing the
procedures that will control waste retrieval.
Pre-Retrieval Evaluation. In the early stages of planning, a key activity is the collection and
evaluation of data about the waste that is to be retrieved. Some of these data (e.g., location,
volumes) may be readily available in existing data bases and will be used in the early planning.
However, prior to developing project-specific plans and procedures controlling retrieval activities,
a thorough evaluation of available data needs to be made so that appropriate worker protection
can be planned.
The evaluation of information relevant to waste characteristics will involve collecting information
on the character of the waste, waste containers, and the storage configuration. The evaluation
includes an examination of existing burial records, production records, and design drawings of
waste containers and the storage facility and can be supplemented by interviews with current and
former employees. To the extent the information is available, the evaluation is to identify the
following:
• Type of earthen-covered storage facility (e.g., trenches, above-grade pads, drum
stacks);
• Waste storage facility design and construction (e.g., above-grade, below-grade,
use of tarps and/or plywood);
• Types of containers present (e.g., 55-gallon drums, fiberglass-reinforced plywood,
wooden, or metal boxes) and their approximate sizes and weights;
• Radionuclide species and inventory in the containers;
• Chemical constituents in the waste;
• The presence of waste containers with high dose rates (i.e., above contact-handled
limits per site radiological control practices);
• Any other waste or facility characteristics that may affect health, safety, or the
environment.
Example: To prepare for retrieval of waste from earthen-covered storage, site personnel
undertake a review of available information. They compile copies of as-built blue-prints
for the storage facility, review the shipping and transfer records that accompanied the
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-141
7-09-99
waste when it was received, and based on the records, identify the containers in which the
waste is contained. The shipping and transfer records identify the facilities from which
the waste was received, which leads to interview of staff who worked at the facilities that
generated the waste. Interviews indicate that there may be other radionuclides present
than the few reported on the shipping and transfer records. Expected dose rates from the
waste containers available from the shipping and transfer records are corroborated by
the staff from the generating facilities.
Evaluation of data about the facility and waste is to be used in developing the detailed retrieval
plans and procedures, particularly as they relate to ensuring worker safety. The data can be used
to support decisions on container handling procedures (e.g., remote versus contact handling) and
the type of personnel protective equipment that may be appropriate. Even if data indicate that a
low level of personnel protective equipment is sufficient, initial contact with retrieved waste needs
to be undertaken using a high level of protection (e.g., EPA level A or B). Only after the
expected level of hazard has been confirmed to be low should the level of personnel protection be
lowered.
Section 416
Example: The evaluation of information about an earthen-covered storage facility leads
to the expectation that the waste containers will be in good shape. This means that only
Level C protective equipment (anticontamination clothing, no respiratory equipment) is
required and that the waste can be contact handled. During initial entry into each
storage module, frequent dose rate surveys are conducted and personnel wear respirators
until it is confirmed that dose rates are low and there is no airborne hazard.
Compliance with this requirement is demonstrated if personnel have developed plans and continue
to show progress towards removing waste from earthen-covered storage facilities and the level of
planning is commensurate with the stage of the retrieval program. Early planning describes the
approach to be followed and actions to be taken to initiate waste retrieval. Later planning
includes the specific activity-based plans that are necessary to support actual waste retrieval.
Compliance also is demonstrated by site personnel having collected and compiled information
about the storage facility and waste to be retrieved. In addition, the plans and procedures for
waste retrieval should reflect consideration of the information compiled about the facility,
containers, and waste to be retrieved.
Supplemental References: None.
Chapter III - Transuranic Waste Requirements
III-142 DOE G 435.1-1
7-09-99
III. O. Treatment.
Transuranic waste shall be treated as necessary to meet the waste acceptance
requirements of the facility receiving the waste for storage or disposal.
Objective:
The objective of this requirement is to emphasize that transuranic waste must be treated as
necessary to meet the waste acceptance requirements of the storage, or disposal facility or
facilities to which it will be transferred.
Discussion:
During the development of DOE O 435.1 and DOE M 435.1-1, treatment of waste was identified
as an activity that presented potential risks to the public, workers, and the environment.
Requirements that address the weaknesses and conditions that could lead to potential adverse
impacts were found in external regulations (e.g., Clean Air Act or RCRA ) or other DOE
directives (e.g., 10 CFR Part 835, Occupational Radiation Protection or DOE O 360.1,
Training). The Field Element Manager has a performance-oriented responsibility for ensuring
that waste treatment is protective of the public, workers, and the environment (DOE M 435.1-1,
Section I.2.F.(14)). The current requirement focuses attention on taking the treatment actions
necessary to make waste acceptable for subsequent waste management steps.
The decision to treat waste, i.e., changing the physical or chemical character of the waste, can be
driven by either dictated requirements or programmatic needs. Required treatment includes
treatment necessary to comply with external regulations (e.g., RCRA, FFCA) or to render waste
acceptable for transfer to another facility (i.e., to meet waste acceptance requirements). Waste
acceptance requirements for a facility to which transuranic waste is transferred are required by
DOE M 435.1-1, Section III.G. These requirements are based on safe handling of the waste and
on regulatory compliance. During the development of DOE M 435.1, certain materials which
represented a potential fire or explosion hazard were identified as being unacceptable for storage,
leading to the need to treat waste composed of these materials so it can be accepted for storage.
Waste treatment may range from actions as simple as sorting waste to remove materials which
would make the waste unacceptable (e.g., aerosol cans), to more complex technologies such as
incineration.
Section 417
Storage Prohibitions. Manual requirements for transuranic waste storage include classes of items
which are prohibited from storage because they represent potential fire or explosive hazards. The
materials or classes of items which cannot be stored include dry nitrate-contaminated ion
exchange resins, cellulosic material contaminated with strong oxidizers, reactive metals,
pyrophoric materials, and volatile organics in high temperature areas. Wastes containing the
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-143
7-09-99
above-listed materials must be treated to remove or counteract the potential hazard. Nitrate-
contaminated ion exchange resins can be stored wet or stabilized so they cannot react. Cellulosic
materials can be oxidized under controlled conditions or the oxidizers can be neutralized.
Reactive metals and pyrophoric materials can either be oxidized or stabilized (e.g., in concrete) to
remove their hazards. Similarly, waste contaminated with volatile organics can be oxidized if it
necessary to store the waste in an area of high heat.
Waste with No Path to Disposal. Available treatment options need to be evaluated before a waste
is categorized as having no path to disposal, as discussed in Section I.2.F.(19). Application of
appropriate treatment can potentially resolve waste acceptance issues for waste types such as:
• heterogenous wastes which contain unacceptable items (e.g., pressurized
containers);
• liquid wastes which can be absorbed or solidified;
• wastes classified for security reasons because of shape;
• wastes containing high explosives; and
• wastes containing in excess of 50 ppm polychlorinated biphenyls.
Example: An activity generates an aqueous transuranic waste. In order to make the
waste acceptable for storage and eventual disposal at WIPP, a study is performed to
determine the most appropriate means of treatment. On the basis of the study, the liquid
waste is solidified with an appropriate solidification agent so that the waste meets the
acceptance criteria of both the storage facility and WIPP.
For defense waste, WIPP is the disposal facility, so evaluations of needed treatment generally
need to consider the waste acceptance requirements of WIPP. However, there are some
transuranic wastes for which treatment either is not currently available or will not solve the
problem that makes the waste unacceptable for disposal at WIPP (e.g., non-defense waste). Such
waste needs to be treated to the waste acceptance requirements of the storage facility to which it
will be sent to ensure that it remains safe during the protracted storage period that will be required
before disposal issues can be resolved.
Mixed Transuranic Waste. Treatment necessary to comply with agreements reached pursuant to
the Federal Facility Compliance Act of 1992 must also be considered in making treatment
decisions. Although it was generally assumed that mixed transuranic waste would be sent to
WIPP without treating for the RCRA-regulated component, site personnel need to ensure that
Chapter III - Transuranic Waste Requirements
III-144 DOE G 435.1-1
7-09-99
commitments made in the Site Treatment Plans and consent orders/agreements are met for both
current and newly-generated transuranic wastes.
Section 418
Treatment for Programmatic Reasons. The requirement to treat waste to meet the waste
acceptance criteria of the appropriate storage or disposal facility is not intended to prohibit
treatment for other reasons. Waste managers may elect to treat waste for programmatic reasons,
but in so doing, must ensure that the waste will still meet the waste acceptance criteria of the
facility(ies) to which it will be transferred. Programmatic reasons for treating waste may be to
make more efficient use of the TRUPACT II transportation system and thereby reduce risk and
cost associated with transportation to WIPP (see Section III.L.(2)), or to decrease the storage or
disposal capacity needed.
Example: A site is generating significant amounts of compactable transuranic waste.
Due to the time expected to pass before shipment to WIPP begins, waste projections
indicate that additional onsite storage will be needed to accommodate the as-generated
waste volumes. Results of a study indicate that use of a compactor will allow the site to
store the projected wastes without building a new storage facility, and will also result in
transportation cost savings because fewer TRUPACT II shipments to WIPP will be
needed.
Compliance with this requirement is demonstrated by the custodian of transuranic waste
maintaining documentation which identifies the plans for treating waste, and maintaining the
records that show waste was treated, if necessary, to meet the waste acceptance requirements of
the storage or disposal facility to which it was transferred.
Supplemental References:
1. Resource Conservation and Recovery Act of 1976, as amended, October 21, 1986.
2. Federal Facility Compliance Act of 1992, as amended, October 6, 1992.
3. Toxic Substances Control Act, as amended, , October 11, 1976.
4. DOE, 1996. Waste Acceptance Criteria for the Waste Isolation Pilot Plant, Revision 5,
DOE/WIPP-069, U.S. Department of Energy, Carlsbad Area Office, Carlsbad, NM, April
1996.
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-145
7-09-99
III. P. Disposal.
Transuranic waste shall be disposed in accordance with the requirements of 40 CFR
Part 191, Environmental Radiation Protection Standards for Management and
Disposal of Spent Nuclear Fuel, High-Level and Transuranic Radioactive Wastes.
Objective:
The objective of this requirement is to ensure transuranic waste is disposed of in a facility that
meets the appropriate regulatory requirements and to establish Headquarters as the DOE
authority for making compliance determinations for transuranic waste disposal facilities other than
WIPP.
Discussion:
Responsibility for actions associated with transuranic waste disposal are addressed in the
Radioactive Waste Management Manual. In DOE M 435.1-1, Section I.2.E., the Deputy
Assistant Secretary is assigned responsibility for reviewing and approving certain transuranic
waste disposal facility performance assessments. Paragraphs included in this portion of guidance
explain the cases in which this applies. As discussed in DOE M 435.1-1, Section I.2.F.(15), the
Field Element Manager of a site with a transuranic waste disposal facility is responsible for
ensuring the safe disposal of transuranic waste, for reviewing performance assessments prior to
submitting them to Headquarters, and for maintaining performance assessments.
Section 419
Starting in the 1970s, the Department began storing waste that was suspected of being
contaminated with transuranic isotopes at a concentration greater than 10 nCi per gram of waste.
The concentration of 10 nCi/g (370 Bq/g) was an interim limit used pending completion of a
technical basis for developing a limit. In 1982, the technical analyses for establishing a limit were
discussed at an interagency workshop and the limit was changed to 100 nCi/g (3,700 Bq/g).
Shortly after this workshop, the Environmental Protection Agency (EPA) proposed standards
which included the 100 nCi/g limit for management and disposal of transuranic waste.
The EPA is responsible for developing generally applicable standards for protection of the
environment from radioactive materials pursuant to authority granted by Atomic Energy Act of
1954, as amended, and the Nuclear Waste Policy Act of 1982, as amended. In 1985, the draft
standards EPA proposed in 1982 were promulgated as the Environmental Standards for the
Management and Disposal of Spent Fuel, High-Level and Transuranic Radioactive Wastes, 40
CFR Part 191. In 1987, the U.S. Court of Appeals for the First Circuit remanded Subpart B of
the 1985 standards, “Environmental Standards for Disposal,” for further consideration (Natural
Resources Defense Council, Inc. v. United States Environmental Protection Agency, 824 F.2d
1258). In 1992, Congress reinstated a portion of the remanded disposal standards with the
Chapter III - Transuranic Waste Requirements
III-146 DOE G 435.1-1
7-09-99
passage of the Waste Isolation Pilot Plant Land Withdrawal Act of 1992, as amended. Congress
also directed EPA to resolve the issues that were the basis for the court remand and reissue the
remaining disposal standards. On December 20, 1993, EPA issued the revised sections of the
requirements. They became effective on January 19, 1994 (58 FR 66398).
Requirements Applicable to Disposal. The bulk of DOE’s transuranic waste is related to defense
activities and will ultimately be acceptable for disposal at WIPP. Consistent with this fact, most
of the Department’s focus on transuranic waste disposal has been on the development and
opening of WIPP consistent with the requirements of 40 CFR Part 191. For WIPP, and any
future facilities if they are developed, the requirements of 40 CFR Part 191 apply, including the
revised individual protection and groundwater protection standards.
Example: A site determines that it must construct an enhanced engineered disposal
facility for a small amount of transuranic waste that cannot be made to meet the WIPP
waste acceptance criteria. Since the facility will operate after January 1994, it must
comply with the January 1994 revisions to 40 CFR Part 191.
However, for transuranic waste disposal facilities subject to 40 CFR Part 191 that operated prior
to the January 1994 effective date, the older (1985) standards apply. In the Supplementary
Information published in the 1993 Federal Register promulgating the revisions to the rule, EPA
acknowledges that it previously informed the Department that the 1985 version of 40 CFR Part
191 applied to the Greater Confinement Disposal Facility (Nevada Test Site). The EPA further
states that this determination is not changed by the WIPP Land Withdrawal Act of 1992, as
amended, or the issuance of the revised regulation.
Section 420
Departmental personnel should also note that the 40 CFR Part 191 regulations do not apply to
disposal that occurred prior to promulgation of the regulations. The 1985 version of the
regulations states under the applicability section of Subpart B, “Environmental Standards for
Disposal,” that the standards do not apply to waste disposed prior to the effective date of the rule.
This excludes from the regulations waste that is colloquially known as “pre-1970 TRU waste”,
“suspect buried transuranic waste”, and possibly by other names, if the waste is left in place. If
the waste is exhumed, the waste becomes subject to the currently applicable regulations.
However, as a good management practice, it is recommended that waste meeting the current
definition of transuranic waste that was disposed of after 1970, but before 1994, be evaluated in
accordance with the 1985 regulations.
Example: A site was in the middle of a three-year campaign to dispose of transuranic
waste at the time 40 CFR Part 191 was promulgated in 1985. Consequently, some of the
waste was disposed of before the effective date of the regulation and some was disposed
of after. The site manager decides to include all of the transuranic waste in the
performance assessment prepared under 40 CFR Part 191. Because the operation ended
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-147
7-09-99
prior to 1994, the 1985 version of the regulations are applied as the performance
measures in the assessment.
Approval Authority. Determination of compliance with the requirements of 40 CFR Part 191
depends on the facility being considered. In the WIPP Land Withdrawal Act of 1992, as
amended, Congress assigned EPA the responsibility for issuing the standards discussed above and
for certifying that WIPP meets the standards. In carrying out this responsibility, the EPA issued
criteria by which they would evaluate the DOE certification application and published them as 40
CFR Part 194, Criteria for the Certification and Re-Certification of the Waste Isolation Pilot
Plant’s Compliance with the 40 CFR Part 191 Disposal Regulations; Final Rule. The
Department is responsible for submitting an application for compliance certification to the EPA.
Subsequently, the EPA must determine if the Department complies with the requirements.
Sites other than WIPP are “regulated” by the implementing agency, in this case, DOE. As
discussed in the General Requirements chapter of the Radioactive Waste Management Manual
(DOE M 435.1-1, Section I.2.F.(15)), the Field Element Manager is responsible for reviewing and
submitting a performance assessment to Headquarters. The Headquarters Deputy Assistant
Secretary for Waste Management will establish a process similar to that used for low-level waste
disposal facilities for reviewing and approving performance assessments, and also considers the
following:
• General provisions including purpose, scope, definitions, communications,
conditions of compliance, and alternative provisions;
• Compliance determinations including completeness and accuracy of compliance
submissions and reference materials;
• General requirements that address inspections, quality assurance, models and
computer codes, waste characterization, future state assumptions, expert
judgment, and peer review;
• Containment requirements considering application of release limits, scope of
performance assessments, consideration of drilling events in performance
assessments, and results of performance assessments;
Section 421
• Assurance requirements including active and passive institutional controls,
monitoring, engineered barriers, and consideration of natural resources; and
• Individual and groundwater protection requirements that consider the protected
individual, exposure pathways, underground sources of drinking water, and the
scope and results of the performance assessment.
Chapter III - Transuranic Waste Requirements
III-148 DOE G 435.1-1
7-09-99
Example: The manager of a site that disposed of a small amount of transuranic waste
ensures the development of a performance assessment that provides a reasonable
expectation of meeting the performance measures in 40 CFR Part 191 for the onsite
facility. Since the facility is not WIPP, following his review, the site manager submits the
performance assessment to Headquarters for approval. The Deputy Assistant Secretary
for Waste Management has previously assigned this task to a team that has developed a
review plan that documents the criteria to be used. The team proceeds with the review
and provides a recommendation back to the Deputy Assistant Manager who makes a final
determination and documents it in a memorandum to the site manager.
Compliance with this requirement is demonstrated by timely completion of a technically-
acceptable performance assessment that projects compliance with the standards contained in the
appropriate version of 40 CFR Part 191 as discussed above. Another aspect of acceptable
performance relative to this requirement is development and implementation of a review process
that results in completing the compliance determination within one year of Headquarters’ receipt
of the performance assessment.
Supplemental References:
1. EPA, 1985. “Final Rule, 40 CFR Part 191, Environmental Standards for the Management
and Disposal of Spent Nuclear Fuel, High-Level and Transuranic Radioactive Wastes,”
Federal Register, Vol. 50, No. 182, U.S. Environmental Protection Agency, Washington,
D.C., September 19, 1985.
2. EPA, 1993. “Final Rule, 40 CFR Part 191, Environmental Radiation Protection Standards
for the Management and Disposal of Spent Nuclear Fuel, High-Level and Transuranic
Radioactive Wastes,” Federal Register, Vol. 58, No. 242, U.S. Environmental Protection
Agency, Washington, D.C., December 20, 1993.
3. EPA, 1996. “40 CFR Part 194, Criteria for the Certification and Re-Certification of the
Waste Isolation Pilot Plant’s Compliance with the 40 CFR Part 191 Disposal
Regulations,” Federal Register, Vol. 61, No. 28, U.S. Environmental Protection Agency,
Washington, D.C., February 9, 1996.
4. EPA, 1996. Compliance Application Guidance for 40 CFR Part 194, EPA 402-R-95
014, U.S. Environmental Protection Agency, Washington, D.C., March 29, 1996.
5. Waste Isolation Pilot Plant Land Withdrawal Act of 1992, as amended, October 30, 1992.
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-149
7-09-99
6. Nuclear Waste Policy Act of 1982, as amended, January 7, 1983.
7. Atomic Energy Act of 1954, as amended, 42 U.S.C. 2011 et seq, 1954.
Chapter III - Transuranic Waste Requirements
III-150 DOE G 435.1-1
7-09-99
III. Q. Monitoring.
The following requirements are in addition to those in Chapter I of this Manual:
(1) All Waste Facilities. Parameters that shall be sampled or monitored, at a
minimum, include: temperature, pressure (for closed systems), radioactivity
in ventilation exhaust and liquid effluent streams, and flammable or
explosive mixtures of gases. Facility monitoring programs shall include
verification that passive and active control systems have not failed.
Section 422
Objective:
The objective of this requirement is to specify minimum parameters for which information will be
routinely collected and analyzed for the purpose of anticipating or identifying undesirable
conditions in the management of transuranic waste.
Discussion:
During the development of DOE O 435.1 and DOE M 435.1-1, the hazards and safety analyses
identified timely monitoring of radioactive waste management facilities as an effective means of
mitigating numerous weaknesses and conditions associated with all phases in the life cycle of
waste management. An analysis of existing Departmental requirements for environmental
monitoring in DOE 5400.1 and DOE 5400.5 found that they were applicable to all radioactive
waste types and all radioactive waste management facilities. Many of the individual conditions
evaluated in the safety and hazards analysis which warranted monitoring are already addressed
due to implementation of these Order requirements. These two DOE Orders are invoked by DOE
M 435.1-1, Section I.1.E.(7).
However, while the general environmental monitoring program and the environmental monitoring
plans mandated by DOE 5400.1 and DOE 5400.5 are adequate for most circumstances,
requirements have been included in DOE M 435.1-1 to require identification of specific warning
signs of impending conditions that could lead to releases, especially for storage of liquid
transuranic waste. Requirements III.Q.(1) and III.Q.(2) address these aspects of additional
monitoring for transuranic waste facilities.
Parameters Specified. The minimum parameters specified in the requirement (temperature,
pressure, radioactivity in effluents, flammable/explosive mixtures of gases) were selected based on
their potential significance in predicting and identifying undesirable conditions. Each facility’s
radioactive waste management basis should include an evaluation of the applicability and
significance of the minimum parameters. This evaluation also needs to consider additional
parameters to be sampled or monitored to ensure the protection of the public health, the
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-151
7-09-99
environment, and the workers. If a minimum parameter specified in the requirement is deemed to
be not applicable in any way to the active operation of that facility, then that justification should
be included in the radioactive waste management basis and when approved, constitutes an
exemption to the Manual.
The parameters need to be sampled or monitored with a frequency that is consistent with the need
to detect changes in facility performance. The accuracy and precision of measurement required is
dictated by the expected variations in the parameters and the level of accuracy and precision
needed to identify problems. The monitoring frequency for specific parameters is likewise
determined based on the possible time variation of the parameter and the response time required
to take mitigating action. For facilities that release radioactivity in effluents, frequent monitoring
or continuous monitoring should be considered.
Example: A tank is used to store liquid transuranic waste. In evaluating the potential
for releases from the tank, it is determined that waste temperature, head space pressure,
and radioactivity in the ventilation exhaust must be continuously monitored. An organics
sniffer is used on a weekly basis to check for flammable/explosive mixtures of gases in
the tank. There are no liquid effluents, so no sampling or monitoring is required.
Section 423
The verification that controls and systems are functioning properly is based upon the nature of the
transuranic waste management activity and the potential impact resulting from a failure.
Verification of active control systems for sampling and monitoring critical facility parameters may
require frequent visual inspections or performance testing. Passive controls such as the floor and
curbing in a storage facility may only require physical inspection once every year. Verification
activities are part of the radioactive waste management basis and are to be documented
appropriately.
All transuranic waste management facilities are required to apply the sampling or monitoring
requirement for the specified parameters using a graded approach. As previously noted, the
methods used and the frequency should be commensurate with the significance of a change in the
parameter. This graded approach can extend to determining that it is inappropriate or
unnecessary to monitor or sample for specific parameters, but the basis for such a determination
needs to be documented.
Example: A building is used for the storage of packaged transuranic waste. Based on
the auditable safety analysis, sampling and monitoring for the minimum specified
parameters are applied in a graded manner depending on the parameter. The facility
ventilation system is equipped with a continuous monitor and a sampler. Radioactivity in
liquid effluent and pressure are not monitored or sampled because the parameters do not
apply to the facility. The inspection procedures for the facility specify that personnel
should note whether the temperature in the building is within a range of 55 to 85 degrees
Chapter III - Transuranic Waste Requirements
III-152 DOE G 435.1-1
7-09-99
Fahrenheit. In addition, procedures require personnel to record visual observations of
the drums, including whether there is any bulging that indicates pressurization.
Compliance with this requirement is demonstrated if monitoring or sampling for the stated
parameters is performed for all facilities with an accuracy, precision, and frequency consistent
with timely identification of developing problems and a justification exists in the approved
radioactive waste management basis for those specified parameters which are not monitored or
sampled.
Supplemental References:
1. DOE, 1988. General Environmental Protection Program, DOE 5400.1, U.S. Department
of Energy, Washington, D.C., November 9, 1988.
2. DOE, 1990. Radiation Protection of the Public and the Environmental, DOE 5400.5,
U.S. Department of Energy, Washington, D.C., February 8, 1990.
III. Q.(2) Stored Wastes. All transuranic wastes in storage shall be monitored,
as prescribed by the appropriate facility safety analysis, to ensure the
wastes are maintained in safe condition.
Objective:
The objective of this requirement is to ensure that the results of safety analyses performed as part
of the authorization of transuranic waste facility operations are appropriately translated into
monitoring requirements for waste storage so conditions that could lead to exposure of the public
or workers, or releases to the environment are detected and mitigated.
Discussion:
Section 424
During the development of DOE O 435.1 and DOE M 435.1-1, monitoring at radioactive waste
management facilities was identified as an effective mitigation of numerous weaknesses and
conditions associated with all phases of the life-cycle of waste management. An analysis of
existing Departmental requirements for environmental monitoring in DOE 5400.1 and DOE
5400.5 found that they were applicable to all radioactive waste types and all radioactive waste
management facilities. Many of the individual conditions that warranted monitoring that were
evaluated in the safety and hazards analysis are mitigated due to the implementation of these
Order requirements. Therefore, DOE M 435.1-1, Section I.1.E.(7) requires that these two DOE
Orders be implemented for environmental monitoring of radioactive waste management facilities.
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-153
7-09-99
While the environmental monitoring mandated by DOE 5400.1 and DOE 5400.5 is adequate to
detect environmental releases, it was determined that due to the long storage times that occur
with transuranic waste, monitoring of additional systems or parameters was needed. The DOE
regulation governing radiation exposure of workers (10 CFR Part 835), was also identified as a
source of requirements that would require that a set of controls be put in place to protect workers
from radiation exposure.
Example: Transuranic waste is stored in a building which contains a change room used
by waste management workers. Access to the change room requires workers to pass
through the area where the waste is stored. The health physics staff takes dose rate
readings along the face of the stored transuranic waste, then cordons off a radiological
control area that minimizes exposure to staff that must pass through the building.
Additional systems or parameters that could warn of impending conditions that could lead to
worker exposure or releases to the environment may be indicated in the safety analyses performed
for transuranic waste management facilities. Some of the monitoring that safety analyses indicate
is needed may be also addressed minimum requirements in the other subparagraphs of this
monitoring requirement.
The Nuclear Safety Analysis Reports Order (DOE 5480.23) and related standards
(DOE-STD-3009-93, DOE-STD-1027-92, DOE-EM-STD-5502-04) and the Facility Safety
Order (DOE O 420.1) provide information on the hazard categorization of facilities and the safety
analyses to be performed. Through the conduct of safety analyses, whether they are formal safety
analysis reports or auditable safety analyses, facility personnel identify the quantity and form of
radioactive and/or hazardous material to be handled at the facility and the operations for
managing the waste. The safety analysis establishes a basis for defining the acceptable operations
envelope for the facility, and provides the basis for technical safety requirements (TSRs). The
technical safety requirements may include requirements for monitoring, however, facility
personnel are to also review the safety analysis to determine if the analyses indicate other
monitoring that would be prudent.
Example: An auditable safety analysis is performed as part of the startup of a
transuranic waste storage facility. The safety analysis indicates that a monitoring and
sampling system is required on the building exhaust system to ensure releases do not
endanger workers, the public, or the environment. Site personnel decided that alpha
monitors will be installed in the waste storage bays, in addition to the monitor that is on
the building ventilation system, consistent with the defense-in-depth philosophy.
Section 425
The safety analyses may also indicate the need for routine inspection of waste packages in
storage. Inspections to be performed on waste packages in storage are addressed by
DOE M 435.1-1, Section III.N and are discussed in the guidance for that requirement.
Chapter III - Transuranic Waste Requirements
III-154 DOE G 435.1-1
7-09-99
Compliance with this requirement is demonstrated if the monitoring requirements in the facility
procedures include, at a minimum, monitoring the systems and parameters as indicated by the
safety analysis.
Supplemental References:
1. DOE, 1994. DOE Limited Standard: Hazard Baseline Documentation, DOE-EM-STD
5502-04, U.S. Department of Energy, Washington, D.C., August 1994.
2. DOE, 1992. Nuclear Safety Analysis Reports, DOE 5480.23, U.S. Department of
Energy, Washington, D.C., April 10, 1992.
3. DOE, 1992. Hazard Categorization and Accident Analysis Techniques for Compliance
with DOE Order 5480.23, Nuclear Safety Analysis Reports, DOE-STD-1027-92, U.S.
Department of Energy, Washington, D.C., December 1992.
4. DOE, 1993. SAR Preparation Guide, DOE-STD-3009-93, U.S. Department of Energy,
Washington, D.C., 1993.
III. Q.(3) Liquid Waste Storage Facilities. For facilities storing liquid
transuranic waste, the following shall also be monitored: liquid level
and/or waste volume, and significant waste chemistry parameters.
Objective:
The objective of this requirement is to ensure monitoring of parameters that indicate the quantity
of liquid transuranic waste stored in tanks so that changes can be promptly checked to determine
if they indicate leakage, overfilling, or other problems. The objective of this requirement also
includes tracking of the chemical characteristics of the waste to anticipate and avert undesirable
storage conditions.
Discussion:
This requirement specifies additional parameters to be monitored at facilities storing liquid
transuranic waste. In developing the requirements for DOE O 435.1 and DOE M 435.1-1, a
hazards analyses identified releases resulting from failed containment or from overfilling liquid
waste storage tanks as hazards that can result in exposure of workers or the public and releases to
the environment. The requirement addresses the operation of monitoring systems to detect
storage tank or transfer equipment failure that is of sufficient magnitude to cause a detectable
volume change, as well as volume increases that could lead to overfilling of tanks. The
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-155
7-09-99
monitoring capability should be coupled with operational devices such as automatic shutoffs and
bypasses and alarms that will alert operators that action is needed to prevent or mitigate a release.
Regardless of the radiological hazard of the waste being stored, leak detection equipment and
inspection of catch basins for liquid waste storage facilities should be included in the monitoring
program, consistent with the requirements in DOE 5480.22, to prevent unplanned releases of
liquid waste in storage.
Liquid Level or Waste Volume. Some changes in liquid level or waste volume can occur
normally due to slight changes in temperature or pressure. This requirement addresses measuring
liquid level or waste volume in a storage tank for the purpose of prompt detection of acute
releases (releases that are detectable visually or by some other gross indicator) and more chronic
releases that become apparent over a time frame of hours or days.
Section 426
Example. A large diameter liquid transuranic waste storage tank includes a mechanical
level indicator that is read and recorded daily. The level indicator remains stable for six
months following the last addition of waste to the tank. The level indicator readings then
begin to show a downward trend that totals two inches over a two week period. The level
indicator change alerts operators of a potential problem that requires further
investigation.
Surface level is a relatively straightforward parameter to monitor for detection of leakage from a
liquid waste storage system. In general, the surface level in a storage tank is an appropriate
indicator of waste volume. However, operations and mechanisms that could change the volume
in a tank must be considered to ensure all unexplainable level changes are investigated and to
discount explainable level changes.
Gas generation and evaporation, as well as intentional additions to and removals from the storage
tanks, must be accurately accounted for if the waste liquid level (or volume) is to be used to
monitor for leakage. Also, consideration needs to be given to the separate monitoring of the
liquid fraction and sludge or solid fraction present in the tank, if layering of the waste is present.
Example: In the tank in the example above, an unexpected chemical reaction generates
gas that is trapped within the waste matrix or under a semipermeable layer of waste that
retards percolation of the gas to the surface of the waste. Consequently, there is an
increase in the surface level of the waste. Over time, the gas is released and the waste
volume returns to its normal level. Although the change in liquid level in the tank did not
appear to be a problem once the gas was released, the generation of gas is identified as
an issue that needs further investigation.
Chemical Characteristics. Experience with situations threatening confinement of liquid
radioactive waste in storage tanks led to the part of the requirement focused on monitoring
Chapter III - Transuranic Waste Requirements
III-156 DOE G 435.1-1
7-09-99
chemical characteristics. Chemical characteristics that are not compatible with the material of
construction of waste tanks or transfer equipment often presage containment failure. The
frequency of monitoring and the identification of significant tank chemistry parameters should be
determined on a facility-, waste-, and tank-specific basis. A recommended program for
monitoring and managing waste chemistry as it relates to tank corrosion is described in
Guidelines for Development of Structural Integrity Programs for DOE High-Level Waste
Storage Tanks (BNL-UC-406). Tank waste chemistry also is to be monitored for the potential
generation of flammable or explosive gases. Once waste has been characterized and shown to be
in essentially a steady state relative to gas generation, it is the addition of new waste that needs to
be most closely watched. Selection of parameters is based on the need to protect the public
health, the environment, and workers. Monitoring is performed to provide statistically valid
information of the relevant tank chemistry and any detected changes in the chemistry of the tank.
Example: Some very minor volumes of laboratory spill waste are planned to be added to
liquid storage tank YTR. Tank YTR is made of carbon steel and has been in service since
1978. The pH of the spill waste is measured, then adjusted to a pH of 12 to meet the
waste acceptance requirements for waste transfers to the tank. The pH testing of the
waste is part of the routine monitoring for tank YTR.
Section 427
Graded Approach. A graded approach needs to be applied to implementation of this requirement
for monitoring liquid wastes in storage. The first consideration for a graded approach is that
monitoring parameters and frequencies for liquid waste storage tanks should be specific for each
tank. Also, the frequency of monitoring is selected to detect changes commensurate with the
potential failure mechanisms and resulting risks of the specific waste being stored.
Example: A highly radioactive acidic waste is stored in a stainless steel tank. The tank is
at capacity so no waste additions are planned. Monitoring consists of a permanently
installed liquid level detector and monthly monitoring of tank pH and chlorine
compounds which could cause corrosion. Another tank constructed of carbon steel is
routinely used for receipt of new waste. In addition to monitoring the liquid level in the
tank and tracking additions and removals, the tank chemistry is checked weekly for pH to
ensure that the waste is maintained at a high pH.
Compliance with this requirement is demonstrated by developing operational procedures for
monitoring liquid transuranic waste storage tank liquid level, waste volume, and tank chemistry so
that waste volume or chemistry changes are detected in a time frame that will allow
implementation of corrective measures to limit public and worker doses and to mitigate unplanned
releases of stored liquid waste.
Chapter III - Transuranic Waste Requirements
DOE G 435.1-1 III-157 (and III-158)
7-09-99
Supplemental References:
1. DOE, 1992. DOE Fundamentals Handbook, Chemistry, DOE-HDBK-1015, Module 2:
“Corrosion,” U.S. Department of Energy, Washington, D.C., June 1992.
2. DOE, 1993. DOE Fundamentals Handbook, Material Science, DOE-HDBK-1017,
Module 2: “Properties of Metals,” U.S. Department of Energy, Washington, D.C.,
January 1993.
3. DOE, 1997. Guidelines for Development of Structural Integrity Programs for DOE
High-Level Waste Storage Tanks, BNL-UC-406, Brookhaven National Laboratory,
Upton, NY, January 1997.
4. DOE, 1992. Technical Safety Requirements, DOE 5480.22, U.S. Department of Energy,
Washington, D.C., February 25, 1992.
Chapter III - Transuranic Waste Requirements
IMPLEMENTATION
GUIDE
for use with DOE M 435.1-1
Chapter IV
Low-Level Waste Requirements
(This page intentionally left blank.)
DOE G 435.1-1 IV-1
7-09-99
IV. A. Definition of Low-Level Waste.
Low-level radioactive waste is radioactive waste that is not high-level radioactive
waste, spent nuclear fuel, transuranic waste, byproduct material (as defined in
section 11e.(2) of the Atomic Energy Act of 1954, as amended), or naturally
occurring radioactive material.
Objective:
The objective of this requirement is to provide the criteria for determining which DOE radioactive
wastes are to be managed as low-level waste in accordance with DOE M 435.1-1, Chapter IV,
Low-Level Waste Requirements.
Discussion:
DOE M 435.1-1, Section I.1.C., Radioactive Waste Management, requires that all DOE
radioactive waste shall be managed as either high-level waste, transuranic waste, or low-level
waste within one of the existing Office of Environmental Management radioactive waste
management programs. To assist in determining whether a particular waste stream is low-level
waste, see Figure I.1, Logic Diagram for Determining Radioactive Waste Type, which
accompanies the guidance for the requirement.
Section 428
Management of wastes containing radioactivity that do not meet or are excluded from the
definition of low-level waste above, (i.e., 11e.(2) byproduct material, residual radioactive
material as defined in the Uranium Mill Tailings Radiation Control Act (UMTRCA), or naturally
occurring radioactive material) should continue to be managed under the provisions of the
UMTRCA or DOE 5400.5, Radiation Protection of the Public and the Environment. However,
DOE M 435.1-1 allows for small quantities of these wastes to be managed in accordance with this
chapter. See the guidance on DOE M 435.1-1, Section IV.B.(4).
Basis. The definition of low-level waste is based on, and is essentially equivalent to, the
definition used in the Nuclear Waste Policy Act of 1982, as amended. The requirements analysis
(see methodology discussion of Technical Basis and Considerations, Appendix A) conducted in
development of DOE O 435.1 and DOE M 435.1-1 indicated the Nuclear Waste Policy Act of
1982, as amended, definition should form the basis for the Department’s definition to be
consistent with the full set of legal drivers for radioactive waste management that are now in
public law. This definition also is consistent with the definition in 10 CFR 61.3, NRC’s
requirements for low-level waste disposal.
Section 161 of the Atomic Energy Act of 1954, as amended [Section 161(b)] authorizes the
Department to promulgate rules “to govern the possession and use of special nuclear material,
Chapter IV - Low-Level Waste Requirements
IV-2 DOE G 435.1-1
7-09-99
source material, and byproduct material” and Section 161(i) authorizes the Department to
prescribe such regulations as it deems necessary to govern any activity authorized pursuant to the
Atomic Energy Act of 1954, as amended, specifically including standards for the protection of
health and minimization of danger to life or property. Although most sources of ionizing radiation
are encompassed by the terms “byproduct material,” “source material” and “special nuclear
material,” some sources, such as machine-produced radioactive material, are not. Because all
ionizing radiation has the potential to cause harm, the Department does not limit its radioactive
waste management requirements to situations involving byproduct, source and special nuclear
material.
Low-level radioactive waste is defined by what it is not. The definition provides the framework
for this concept by listing the basic radioactive waste types that are not low-level waste, thereby
limiting the wastes that are to be managed as low-level waste. Thus, an understanding of the
definitions of high-level radioactive waste, spent nuclear fuel, transuranic waste, byproduct
material, and naturally occurring radioactive material is necessary to determine whether a subject
waste is to be managed as low-level waste in accordance with DOE M 435.1-1, Chapter IV. The
definitions of and relevant guidance on high-level waste (see Chapter II.A) and transuranic waste
(see Chapter III.A) are contained in the guidance on Chapters II and III of the Manual,
respectively. The guidance on definitions in Chapters II and III should be consulted first for
making a determination on how to properly manage a suspect waste stream. Specific waste
determination cases discussed in that guidance may provide assistance on deciding which
radioactive wastes are to be managed as low-level waste. Many of these specific waste stream
decisions are referenced and/or discussed again in the following guidance on the definition of low-
level waste.
Section 429
High-Level Waste Exclusion. High-level waste is the first type of radioactive waste excluded
from the definition of low-level waste. Guidance on the definition of High-Level Waste in
Chapter II clarifies the meaning of that term for applicability to certain DOE waste streams. That
guidance should be consulted first for determining if a waste stream should be managed as
high-level waste. Those waste streams that should be managed as low-level waste must meet the
requirements of DOE M 435.1-1, Chapter IV.
Radioactive waste that meets the requirements of waste incidental to reprocessing, either by
citation or evaluation, is excluded from the scope of high-level waste. It is the intent of the
requirements of DOE O 435.1 and DOE M 435.1-1 that wastes which are excluded from the
high-level waste management requirements because they have been determined to be not high-
level waste through the waste incidental to reprocessing determination process and contain
transuranics less than 100 nCi/g are low-level waste to be managed in accordance with Chapter
IV of DOE M 435.1-1. (See guidance on Waste Incidental to Reprocessing, DOE M 435.1-1,
Section II.B).
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-3
7-09-99
Example: At the Hanford Site the high-level waste program used the evaluation process
to gain NRC support for on-site disposal of the low-activity waste stream removed from
the high-level waste tanks as waste incidental to reprocessing. The on-site disposal
facility shall meet the low-level waste requirements for disposal in accordance with DOE
M 435.1-1.
Spent Nuclear Fuel Exclusion. Spent nuclear fuel is excluded from the definition of low-level
waste. Spent nuclear fuel is defined in the Nuclear Waste Policy Act of 1982, as amended, as
“...fuel that has been withdrawn from a nuclear reactor following irradiation, the constituent
elements of which have not been separated by reprocessing.” The term refers to the spent fuel
rods and assemblies as they are managed upon removal from a reactor, especially in terms of the
applicability of provisions for management of spent fuel in the Nuclear Waste Policy Act of 1982,
as amended. Guidance on the definition of high-level waste for Chapter II, DOE M 435.1-1
clarifies the meaning of spent nuclear fuel for applicability to certain Department waste streams
that could fit the description of spent nuclear fuel. That guidance should be consulted first for
determining whether one of these waste streams is to be managed as high-level waste. Those
waste streams that are determined should be managed as low-level waste must meet the
requirements of DOE M 435.1-1, Chapter IV.
Example: Site Q has irradiated target elements in long-term storage that must be
disposed. The targets contain neither fissile material, nor do they meet the definition of
transuranic waste. The targets are managed for disposal as low-level waste.
Transuranic Waste Exclusion. Transuranic waste is excluded from the definition of low-level
waste. As mentioned, the definition of transuranic waste is further explained in the guidance on
Requirement III.A. That guidance clarifies the applicability of the term transuranic waste for
certain DOE radioactive waste streams. The guidance should be consulted first for determining if
a waste stream should be managed as transuranic waste. Those streams that should be managed
as low-level waste must meet the requirements of Chapter IV, DOE M 435.1-1.
Section 430
Three exceptions to the definition of transuranic waste are discussed in the guidance for
transuranic waste requirements (DOE M 435.1-1, Section III.A). The first exception is high-level
waste which, as discussed previously, is also excluded from the definition of low-level waste. The
second exception is waste that DOE, with the concurrence of the EPA Administrator, has
determined does not need the degree of isolation that is provided by implementation of the
disposal requirements of 40 CFR Part 191. This waste is to be managed as low-level waste in
accordance with Chapter IV of DOE M 435.1-1. The third exception applies to waste generated
by commercial activities that have concentrations of radionuclides that would result in
categorization as transuranic waste. As long as the waste is not high-level waste, it could be
accepted (with NRC approval not to invoke 40 CFR Part 191) as Greater-than-Class-C (GTCC)
low-level waste per the classification system in 10 CFR 61.55. This waste is to be managed as
Chapter IV - Low-Level Waste Requirements
IV-4 DOE G 435.1-1
7-09-99
low-level waste in accordance with Chapter IV of DOE M 435.1-1. However, GTCC waste is to
be disposed of in a facility licensed by the U.S. Nuclear Regulatory Commission (See the guidance
on Complex-Wide Low-Level Waste Management Program concerning management of
commercial (NRC licensed) GTCC, DOE M 435.1-1, Section IV.C.).
Also, consistent with the guidance on transuranic waste (DOE M 435.1-1, Section III.A),
radioactive waste that does not meet the definition of transuranic waste in accordance with the
measurement, error, and uncertainty guidance described in Transuranic Waste Characterization
Quality Assurance Program Plan, Waste Acceptance Criteria for the Waste Isolation Pilot Plant,
and/or other controlling documents is also to be managed as low-level waste in accordance with
Chapter IV of DOE M 435.1-1.
Dilution of a transuranic waste stream to reclassify the waste as low-level waste (i.e., reducing the
concentration to less than or equal to 100 nCi (3700 Bq) per gram) is not permitted by the
Department. While it is recognized that in the course of stabilizing a waste stream some changes
in waste concentration may occur, actions to dilute a waste stream below the concentration limits
for transuranic waste are prohibited. It is also recognized that actions taken to process a waste
stream for safety or technological reasons that are justified, may result in the waste being
reclassified after processing as low-level waste.
Example: Due to the moisture content of a transuranic waste sludge, the waste does not
meet the WIPP WAC. The site evaluates several treatment options taking into
consideration factors such as worker exposure, waste minimization, cost and complexity
of the treatment process and disposal facility waste acceptance requirements. The
treatment process selected involves adding grout to the transuranic waste sludge to
eliminate free liquids resulting in a solidified waste form that contains transuranic
radionuclides in concentrations less than 100 nCi (3700 Bq) per gram and meets the
waste acceptance criteria for a low-level waste disposal facility.
Section 431
Byproduct Material Exclusion. Byproduct material as defined in Section 11e.(2) of the Atomic
Energy Act of 1954, as amended, is also excluded from the definition of low-level waste.
Byproduct material is defined as: “. . . (2) The tailings or wastes produced by the extraction or
concentration of uranium or thorium from any ore processed primarily for its source material
content.” Section 11e.(2) byproduct material is included in the waste types not managed as low-
level waste because Congress determined that this waste stream had unique qualities, particularly
the generation of radon gas, and needed to be managed in accordance with its own set of
environmental standards and technical requirements. The Uranium Mill Tailings Radiation
Control Act (UMTRCA) provides the legal framework under which 40 CFR Part 192 and the
Department’s program for remediation of old uranium mill tailings sites was developed and
implemented.
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-5
7-09-99
Naturally Occurring Radioactive Material Exclusion. Waste with naturally occurring radioactive
material is also excluded from the definition of low-level waste. Naturally occurring radioactive
material, or NORM, is material that contains natural radioactivity and is not regulated by NRC
under the Atomic Energy Act of 1954, as amended. In some cases, changes in the composition,
radionuclide concentrations, availability, or proximity to man of such material as a result of human
practices cause a potential for increased exposure to the public. The Atomic Energy Act of 1954,
as amended and the Energy Reorganization Act of 1974 charge DOE with protecting the public
from exposure to radiation caused by its research, development, or production activities.
Therefore, DOE regulates such exposures under its radiation protection directives. For non-DOE
activities, the Congress provided NRC authority for only source, byproduct, and special nuclear
material and not for the generation of consumer products or other products from natural material.
However, DOE does have responsibilities for NORM that has been technologically enhanced by
DOE activity.
The policy of the Department is that small quantities of naturally occurring and/or 11e.(2)
byproduct materials or wastes containing such materials may be disposed in DOE low-level waste
disposal facilities provided that the requirements for disposal of low-level waste are met.
Example: A small amount (100 cubic meters) of 11e.(2) materials that are similar to mill
tailings, but from an apparently different process, are discovered at the remedial action
site near Garden City. These materials are removed from their current location and are
packaged and stored. An evaluation of the performance assessment at Site X indicates
that these materials are acceptable for disposal there. The wastes are certified and
shipped to Site X for disposal.
Chapter IV of DOE 5820.2A addresses this matter and provides the requirements for
management of small quantities of 11e.(2) and naturally occurring radioactive material as low-
level waste. This practice may continue under DOE M 435.1-1, IV.B.(4). Guidance for this
requirement should be consulted for discussions on management of small quantities of 11e.(2)
byproduct and naturally occurring radioactive material as low-level waste.
Supplemental References:
1. Nuclear Waste Policy Act of 1982, as amended, January 7, 1983.
Section 432
2. NRC. Licensing Requirements for Land Disposal of Radioactive Waste, 10 CFR Part 61,
U.S. Nuclear Regulatory Commission, Washington, D.C..
3. CAO, 1998. U.S. Department of Energy, Transuranic Waste Characterization Quality
Assurance Program Plan, Revision 1, CAO-94-1010, U.S. Department of Energy,
Carlsbad Area Office, Carlsbad, NM, December 18, 1998.
Chapter IV - Low-Level Waste Requirements
IV-6 DOE G 435.1-1
7-09-99
4. CAO, 1996. Waste Acceptance Criteria for the Waste Isolation Pilot Plant, Revision 5,
DOE/WIPP-069, U.S. Department of Energy, Carlsbad Area Office, Carlsbad, NM, April
1996.
5. DOE, 1988. Radioactive Waste Management, DOE 5820.2A, U.S. Department of
Energy, Washington, D.C., September 26, 1988.
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-7
7-09-99
IV. B. Management of Specific Wastes.
The following provide for management of specific wastes as low-level waste in
accordance with the requirements in this Chapter:
(1) Mixed Low-Level Waste. Low-level waste determined to contain both
source, special nuclear, or byproduct material subject to the Atomic Energy
Act of 1954, as amended, and a hazardous component subject to the Resource
Conservation and Recovery Act (RCRA), as amended, shall be managed in
accordance with the requirements of RCRA and DOE O 435.1, Radioactive
Waste Management, and this Manual.
(2) TSCA-Regulated Waste. Low-level waste containing polychlorinated
biphenyls, asbestos, or other such regulated toxic components shall be
managed in accordance with requirements derived from the Toxic Substances
Control Act, as amended, DOE O 435.1, Radioactive Waste Management, and
this Manual.
(3) Accelerator-Produced Waste. Radioactive waste produced as a result of
operations of DOE accelerators is low-level waste and shall be managed in
accordance with DOE O 435.1, Radioactive Waste Management, and this
Manual, and all applicable Federal or State requirements.
(4) 11e.(2) and Naturally Occurring Radioactive Material. Small quantities of
11e.(2) byproduct material and naturally occurring radioactive material may
be managed as low-level waste provided they can be managed to meet the
requirements for low-level waste disposal in Section IV.P of this Manual.
Objective:
The purpose of this requirement is to (1) ensure that DOE low-level waste is managed in
accordance with the applicable requirements of external regulations, specifically those of the
Resource Conservation and Recovery Act (RCRA) and Toxic Substances Control Act (TSCA),
that address non-radiological hazards, in addition to being managed in accordance with the
requirements of DOE O 435.1 and the Radioactive Waste Management Manual, DOE M
435.1-1, and (2) allow for the management of certain other radioactive wastes as low-level waste
that are the responsibility of the Department under the Atomic Energy Act of 1954, as amended.
Chapter IV - Low-Level Waste Requirements
IV-8 DOE G 435.1-1
7-09-99
Discussion:
The Radioactive Waste Management Manual, DOE M 435.1-1, contains requirements for
managing the radioactive character of low-level waste. Through the safety and hazards analysis
process used in developing the Manual, non-radiological hazards associated with managing
certain wastes were identified. During the development of the requirements necessary to control
the identified hazards, it was concluded that sufficient external regulations, promulgated pursuant
to RCRA and TSCA, exist for controlling the non-radiological hazards.
Section 433
Section 161 of the Atomic Energy Act of 1954, as amended [Section 161(b)] authorizes the
Department to promulgate rules “to govern the possession and use of special nuclear material,
source material, and byproduct material” and Section 161(i) authorizes the Department to
prescribe such regulations as it deems necessary to govern any activity authorized pursuant to the
Atomic Energy Act of 1954, as amended, specifically including standards for the protection of
health and minimization of danger to life or property. Although most sources of ionizing radiation
are encompassed by the terms “byproduct material,” “source material” and “special nuclear
material,” some sources, such as machine-produced radioactive material, are not. Because all
ionizing radiation has the potential to cause harm, the Department does not limit its radioactive
waste management requirements to situations involving byproduct, source and special nuclear
material.
Through the safety and hazards analysis, it was also recognized that the Department has
management responsibility over some other radioactive waste, namely accelerator-produced,
naturally occurring, and 11e.(2) byproduct material, which is specifically excluded from the
definition of low-level waste, but for which the Department is responsible for protecting the
public, workers, and the environment from the radioactivity from the waste under the Atomic
Energy Act of 1954, as amended, and therefore needed to be considered to cover the full
inventory of radioactive waste that must be managed under DOE O 435.1 and DOE M
435.1-1. The analysis to develop requirements concluded that the Department’s policies,
requirements, and guidance currently in place under DOE 5820.A should be continued and
improved where needed. Guidance below under Accelerator-Produced Waste and 11e.(2) and
Naturally Occurring Radioactive Material discusses the continuation of the 5820.2A policies and
practices and provides discussion for meeting requirements of DOE O 435.1 and DOE M 435.1-1
for these wastes.
Mixed Low-Level Waste. In managing low-level wastes which are subject to RCRA and TSCA
requirements, personnel need to be cognizant of the requirements for storage and disposal of the
waste. The ability to dispose of RCRA or TSCA waste that has a radioactive component is very
limited. Therefore, waste generators should avoid creating a mixed or TSCA-regulated low-level
waste, and generators and waste managers should avoid actions that result in generating low-level
waste with no path to disposal (see guidance for DOE M 435.1-1, Section I.2.F.(19)).
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-9
7-09-99
Example: It is typical for personnel within a radiological control area at Laboratory A
to always declare all waste to be radioactive. It is recognized that all the waste is not
low-level waste; however, by managing it as such, the facility saves time and money in
surveying and performing radioactive/clean determinations. However, RCRA or TSCA
waste is not automatically declared radioactive out of convenience, because such
designation would greatly limit the management and disposal options for the waste and
increase the overall waste management costs at Laboratory A. Instead, personnel
specifically survey any waste that has been identified as RCRA- or TSCA- regulated in
order to make a radioactive/clean determination and thus minimize the amount of waste
that will be designated as mixed or TSCA regulated.
Section 434
RCRA and State Hazardous Waste Regulations. The Resource Conservation and Recovery Act
required the Environmental Protection Agency to promulgate regulations for management of
hazardous waste. The legislation also provides for states to promulgate and implement hazardous
waste regulatory programs that are at least as protective as the Federal program. The hazardous
waste requirements that personnel must follow in managing (i.e., generating, transporting,
treating, storing or disposing) mixed low-level waste and in closing affected facilities are primarily
in 40 CFR Parts 260 through 270, or authorized state regulations. A variety of guidance manuals
and information relevant to the management of the hazardous component of mixed low-level
waste has been prepared both by the state regulatory agencies and the Environmental Protection
Agency (see for example U.S. Environmental Protection Agency, Catalog of Hazardous and
Solid Waste Publications, EPA530-B-96-007, September, 1996). These guidance documents
should be consulted when developing management programs for mixed low-level waste.
Hazardous waste regulations promulgated by states with RCRA authority may be more restrictive
than the Federal regulations. The more restrictive requirements may include a broader definition
of hazardous waste than the Federal requirements or may impose another state’s definition of
hazardous waste when waste is received from that state. Waste management personnel therefore
need to be aware of the requirements of the regulations in their own state as well as the
implications of the regulations in states to which they intend to transfer waste.
Example 1: In a state that invokes regulations equivalent to the EPA hazardous waste
regulations, waste oil that meets the criteria for low-level waste would not be managed as
mixed low-level waste. However, if the oil was to be shipped to another state in which the
state regulations defined hazardous waste to include waste oil, the waste would have to
be packaged, manifested, transported, and stored as a mixed waste.
Example 2: If the direction of waste transfer in the above example were reversed, a
different situation could arise. The waste would be declared a mixed waste in the state of
origin because the state regulations had a broader definition of hazardous waste. The
state to which it was to be shipped does not specifically regulate waste oil as a hazardous
Chapter IV - Low-Level Waste Requirements
IV-10 DOE G 435.1-1
7-09-99
waste. However, the state regulations of the receiving site require that waste be
considered to be as it was categorized in the state of origin. In this case, the waste would
still be considered to be and need to be managed as mixed waste even after it was
shipped to the state that did not explicitly regulate waste oils.
The RCRA requirements prohibit storage of hazardous (including mixed) waste that are restricted
from land disposal except for purposes of accumulating sufficient quantities to facilitate recovery,
treatment, or disposal. The Federal Facility Compliance Act of 1992 required the Department to
prepare site-specific treatment plans to address treatment of mixed waste to meet the land
disposal restrictions at each facility at which DOE generates or stores mixed waste. To meet the
requirement, site-specific treatment plans were developed, and through agreements or consent
orders, commitments to schedules to treat or otherwise meet the land disposal restrictions were
made. These site-specific treatment plans and agreements or consent orders need to be part of the
life-cycle planning performed in accordance with Waste Generation Planning (DOE M 435.1-1,
Section IV.H).
Section 435
PCB, Asbestos, and Other TSCA Wastes. Low-level wastes contaminated with PCBs or asbestos
do not meet the definition of mixed waste. However, the situation is similar because external
regulations promulgated under the authority of the Toxic Substances Control Act (TSCA) must
be complied with in addition to the requirements of DOE O 435.1 and the Manual. Waste
managers responsible for managing PCB-containing products should consult the EPA
requirements at 40 CFR Part 761. The regulations impose requirements for the destruction,
storage awaiting destruction, and disposal of PCBs. Waste managers responsible for managing
materials containing asbestos should consult the EPA requirements at 40 CFR Part 61, subpart M.
These regulations impose requirements for the removal of asbestos during demolition and
renovation and disposal of asbestos-containing waste. This regulation includes cross-references
to several other regulations governing management of asbestos that may also apply. Planning for
management of these wastes and any low-level waste that includes a component which is
regulated under TSCA needs to be addressed in the Complex-Wide Low-Level Waste
Management Program and the Site-Wide Waste Management Programs (DOE M 435.1-1,
Sections I.2.B.(1), I.2.F.(1), and IV.C).
Example: A site has determined that contaminated transformer oil from an on-site
electrical source contains PCBs. The site makes arrangements for treatment at another
facility which is permitted under TSCA for PCB treatment (PCB destruction) and return
of the low-level waste (grouted ash) for disposal at the generating site.
The DOE M 435.1-1 requirements imposed on the radioactive component of RCRA or TSCA
waste should not create a duplication of management activities that can be satisfied by compliance
with either a RCRA or TSCA requirement. Also, documentation required by RCRA or TSCA
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-11
7-09-99
requirements which provide the same or similar documentation as required by DOE M 435.1 can
be used to satisfy the DOE M 435.1-1 requirement.
Example: Mixed low-level waste is being transferred from one site to another for
treatment. The Uniform Hazardous Waste Manifest is prepared as required by 40 CFR
Part 262. The manifest is determined to satisfy the need to document the transfer of
ownership of the waste, the transfer date, the physical location of the waste, and other
information specified in DOE M 435.1-1. If the waste acceptance requirements of the
facility receiving the waste allow it, the manifest may also provide the necessary
information on the chemical and physical characteristics of the waste.
Accelerator-Produced Waste. Commercially generated accelerator-produced waste is not source,
special nuclear, or byproduct material that must be licensed by the NRC under the Atomic Energy
Act of 1954, as amended. However, the Department retains the responsibility under the Atomic
Energy Act of 1954, as amended, for protection of the public, workers, and the environment from
the radioactivity produced from Department of Energy accelerators. Such waste may include
shielding and structures which are activated by operation of an accelerator, or the targets that are
bombarded by the accelerator beam. Radioactive waste produced from Department of Energy
accelerator activities is to be managed as low-level waste. Accelerator-produced wastes have
been managed as low-level waste by the Department in the past, and this provision in DOE M
435.1-1 maintains this practice.
Section 436
Accelerator-produced waste may be mixed with hazardous constituents that are regulated under
RCRA or state-equivalent legislation. In this case, Department Field Elements need to interact
with state authorities concerning the appropriate management of these wastes. These wastes are
not mixed waste to the extent that the accelerator-produced materials are not source, byproduct,
or special nuclear material. However, they should still be managed appropriately for the dangers
posed by both the radioactivity and the hazardous component, as if they were mixed waste. Some
states may have agreed with Department Field Elements already on the appropriate set of
requirements that these wastes should be managed under. The Department is fully responsible for
ensuring that the requirements associated with the hazardous components are complied with, as
well as managing the waste for its radioactivity in accordance with Chapter IV of the Manual.
Example 1: Lead (Pb) bricks are used as shielding in a new tritium production
accelerator in State S. When the shielding is discarded, the resultant waste is a RCRA-
regulated hazardous waste (and is not a “mixed waste” because the radioactive
component is not source, special nuclear, or byproduct material). The lead brick
shielding waste is managed in accordance with State S hazardous waste requirements.
The shielding waste is managed as mixed waste, however, because all DOE Manual
Chapter IV requirements are also met. The tritium production accelerator includes
management requirements for this waste in a RCRA-based agreement with State S.
Chapter IV - Low-Level Waste Requirements
IV-12 DOE G 435.1-1
7-09-99
Example 2: A Department of Energy research accelerator uses a variety of target
materials. None of the targets contain hazardous constituents, however, once a research
activity is completed, the discarded targets have been activated. The discarded targets
are handled to protect against exposure to radiation and are managed as low-level waste
including disposal at a DOE low-level waste disposal facility.
11e.(2) and Naturally Occurring Radioactive Material. This section of DOE M 435.1-1 was
provided to continue the policies, requirements, and guidance in place under DOE 5820.2A
concerning disposal of small quantities of 11e.(2) and naturally occurring radioactive material.
Under the Nuclear Waste Policy Act of 1982, as amended, and the Low-Level Radioactive Waste
Policy Act, low-level waste is defined to exclude 11e.(2) byproduct material. However, DOE O
435.1 continues the Department’s existing policy that small quantities of these materials may be
managed as low-level waste in accordance with the low-level waste requirements of DOE M
435.1-1. This requirement is not intended to allow large volumes of 11e.(2) material from sites
subject to 40 CFR Part 192 would be routinely disposed in a low-level waste disposal facility.
These wastes, waste quantities too large for acceptance at DOE low-level waste disposal sites,
and other 11e.(2) byproduct and naturally occurring radioactive materials that are inappropriate
for management as a low-level waste are to be managed under the provisions of UMTRCA, 40
CFR Part 192, or DOE 5400.5, Radiation Protection of the Public and the Environment, as
applicable. Recognizing DOE’s responsibility for properly managing these materials when
generated or encountered during cleanups, DOE 5400.5 contains requirements that are applicable
for the management of naturally occurring radioactive material waste streams. [Although the
Department is unlikely to manage any of these, examples of such wastes are rare earth processing
facility wastes, mineral extraction byproducts, such as phosphogypsum and copper tailings, coal
ash, and oil and gas extraction byproducts.]
Section 437
The Department manages other radioactive waste streams that contain naturally occurring
radioactive material that are excluded from the definition of low-level waste. These waste
streams are those in which the naturally occurring radioactive material has been technologically-
enhanced and intentionally altered for the purpose of utilizing the radioactive properties of the
material. Examples of these are sealed sources containing radium and compounds of uranium
which no longer are considered source material, but which have not been converted to a form that
could be used productively. These waste streams are appropriately managed as low-level waste
to provide adequate protection of workers, the public, and the environment.
To understand what is meant by the term “small quantities,” the legislative intent of the UMTRCA
as implemented in the policies of the Department provide the needed guidance. In enacting the
UMTRCA, Congress addressed a problem of large volumes of diffuse material in several locations
that required proper controls. These residual radioactive materials regulated under UMTRCA are
managed by the Department according to the requirements of 40 CFR Part 192 and disposed at
specially designated tailings disposal sites established under the UMTRCA.
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-13
7-09-99
It is the policy of the Department that small quantities of naturally occurring and/or 11e.(2)
byproduct materials or wastes containing such materials may be disposed in DOE low-level waste
disposal facilities provided that the requirements for disposal of low-level waste are met.
The requirement, in stating that the disposal requirements in DOE M 435.1-1, Section IV.P must
be met, means the naturally occurring or 11e.(2) byproduct material must be included in the
performance assessment and composite analysis for the facility, that adequate controls are
established for the waste stream based on the evaluations, and the minimum disposal requirements
of Chapter IV are to be met. The inclusion of a significant quantity of naturally occurring or
11e.(2) byproduct material in a low-level waste disposal facility is expected to result in additional
controls for that waste stream due to the risk posed by radon emanation from the waste, where
“significant” in this context is to be determined through the performance assessment and
composite analysis evaluations and other considerations included in the radioactive waste
management basis for the disposal facility.
Example 1: A significant amount (100,000 cubic meters) of new mill tailings are
discovered in a location not previously determined to be contaminated at the UMTRCA
site at Slick Rock, CO. These mill tailings will be removed from their location and either
be disposed of at the Cheney disposal cell or DOE will pay a UMTRCA Title II site to
dispose of the tailings, consistent with UMTRCA, as amended.
Example 2: A small amount (100 cubic meters) of 11e.(2) materials that are similar to
mill tailings, but from an apparently different process, are also discovered at this
contaminated site near Slick Rock. These materials will also be removed from their
current location and managed in the same manner as discussed in Example 1.
Section 438
Example 3: Some uranium bearing waste from processes undertaken at the Fernald
facility is proposed for disposal at the Site Y disposal facility. Sufficient capacity is
available to dispose of the amount of the waste to be generated. The waste is included in
the performance assessment and composite analysis, and controls are established. These
include provisions for stabilizing the waste and placing it in specially designed boxes, for
additional analysis of the cover that will eventually be placed on the disposal unit used,
and for additional information in the records for the disposal facility concerning the
nature of the waste in this specific disposal unit.
Example 4: Small quantities (a few vials) of paints and other items containing radium
are discovered among the radioactive materials that DOE has agreed to take possession
of from a university professor who retired. DOE has no use for the materials, and is not
aware of any needs outside of the Department. The material is considered waste, and is
disposed by the laboratory personnel who took possession of the materials as low-level
Chapter IV - Low-Level Waste Requirements
IV-14 DOE G 435.1-1
7-09-99
waste, after consultation with the disposal facility who will receive the waste that the
amount is not significant and no additional controls for its disposal are needed.
In addition, naturally occurring or 11e.(2) byproduct material determined to be manageable as
low-level waste that is also mixed with constituents covered under RCRA or TSCA must also
meet all of the requirements in those laws and be managed as mixed low-level waste in
accordance with DOE O 435.1 and DOE M 435.1-1.
Supplemental References:
1. Solid Waste Disposal Act, as amended by the Resource Conservation and Recovery Act,
42 U.S.C. 6901 et seq., 1984.
2. Federal Facility Compliance Act of 1992, as amended, October 6, 1992.
3. Toxic Substances Control Act, as amended, October 11, 1976.
4. Uranium Mill Tailings Radiation Control Act, as amended, 42 U.S.C. 7901 et seq., 1978.
5. EPA, 1993. “Final Rule; Environmental Radiation Protection Standards for the
Management and Disposal of Spent Nuclear Fuel, High-Level and Transuranic
Radioactive Wastes,” Federal Register, Vol. 58, No. 242, U.S. Environmental Protection
Agency, Washington, D.C., December 20, 1993.
6. EPA. 40 CFR Parts 260-270, U.S. Environmental Protection Agency, Washington, D.C.
7. EPA. Polychlorinated Biphenyls (PCBs) Manufacturing, Processing, Distribution in
Commerce, and Use Prohibitions, 40 CFR Part 761, U.S. Environmental Protection
Agency, Washington, D.C.
8. EPA, 1996. U.S. Environmental Protection Agency Catalog of Hazardous and Solid
Waste Publications, EPA530-B-96-007, U.S. Environmental Protection Agency,
Washington, D.C., September 1996.
9. EPA, 1973. National Emissions Standards for Hazardous Air Pollutants – National
Emission Standard for Asbestos, 40 CFR Part 61, Subpart M, U.S. Environmental
Protection Agency, Washington, D.C., April 6, 1973.
10. DOE, 1990. Radiation Protection of the Public and Environment, DOE 5400.5, U.S.
Department of Energy, Washington, D.C., February 8, 1990.
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-15
7-09-99
IV. C. Complex-Wide Low-Level Waste Management Program.
A complex-wide program and plan shall be developed as described under
Responsibilities, 2.B and 2.D, in Chapter I of this Manual.
Objective:
Section 439
The objective of this requirement is to ensure the development, documentation, and
implementation of a complex-wide low-level waste management program to provide for
cost-efficient and integrated management of low-level waste throughout the complex and within
individual site radioactive waste management programs. Mixed low-level waste is, as
appropriate, reflected in low-level waste plans and through its own program plan.
Discussion:
The Department’s management of low-level waste occurs at numerous sites that generate, stage,
and store waste, and at several sites that treat and dispose of the waste. A complex-wide program
and plan establish the overall mission for the Department’s management of low-level waste and to
provide a framework within which the individual site programs operate. The Radioactive Waste
Management Manual, DOE M 435.1-1, General Requirements (Section I.2.B) assigns the
Assistant Secretary for Environmental Management the responsibility for developing and
maintaining complex-wide, waste-type programs. The Manual General Requirements (Section
I.2.D) also assigns the Deputy Assistant Secretary for Waste Management the responsibility for
developing and implementing complex-wide, waste-type program plans. The complex-wide low-
level waste management program and plan are developed following the guidance provided for
DOE M 435.1-1, Section I.2.B and I.2.D requirements.
Mixed Low-Level Waste Program. Mixed low-level waste is managed within the Department
through an existing Mixed Low-Level Waste Management Program. Appropriate management
interfaces and exchanges of technical information need to be identified in the low-level waste
management program wherever necessary to affect safe and effective management of both mixed
and non-mixed low-level waste. The systematic planning of mixed low-level waste can either be
integrated with low-level waste planning or as a subset of low-level waste as appropriate. Mixed
low-level waste interfaces, exchanges, inputs, and subsets discussions need to be included in the
documentation of the complex-wide low-level waste management program and in the site
radioactive waste management programs, as appropriate. The low-level and mixed low-level
waste management programs should utilize existing data wherever possible.
Example: A laboratory facility is providing information to be included in the
Complex-Wide Low-Level Waste Management Program Plan. Existing mixed low-level
waste data and plans from the lab’s Site Treatment Plan prepared under the Federal
Chapter IV - Low-Level Waste Requirements
IV-16 DOE G 435.1-1
7-09-99
Facilities Compliance Act are provided and are included in the appropriate sections of
the Complex-Wide Program Plan or in a separate Mixed Low-Level Waste Management
Program Plan, as needed.
Greater-Than-Class C Program. Commercial Greater-than-Class C (GTCC) radioactive waste
(generated by an NRC licensee) is also managed within an existing GTCC Program in the
Department. Appropriate management interfaces and exchanges of technical information also
need to be identified in the low-level waste management program wherever necessary to ensure
safe and effective management of both DOE low-level waste and commercial GTCC low-level
waste. The systematic planning of commercial GTCC waste management can either be integrated
with the low-level waste planning or as a subset of low-level waste, as appropriate. Commercial
GTCC low-level waste interfaces, exchanges, inputs, and subsets discussions need to be included
in the documentation of the complex-wide low-level waste management program and in the site
radioactive waste management programs, as appropriate. The low-level waste management and
the GTCC programs should utilize existing data wherever possible.
Section 440
As specified in the Low-Level Radioactive Waste Policy Act, the facility that will be used to
dispose of commercially generated GTCC from NRC licensees must be licensed by the NRC, in
accordance with 10 CFR Part 61. Therefore, the Complex-Wide Low-Level Waste Management
Program, and the site-wide programs where commercial GTCC will be managed until disposal,
needs to include inventory control, waste tracking, and recordkeeping that will lead to the
successful licensing of the commercial GTCC disposal facility.
Performance Assessment and Composite Analysis Maintenance. Performance assessments of
DOE low-level waste disposal facilities have been developed over a number of years. Composite
analyses for low-level waste disposal facilities have recently been developed. Maintenance of
these analyses is required to ensure that performance assessments and composite analyses
adequately represent the current and expected future state of the low-level waste disposal facilities
for which they are required. Such maintenance is properly the responsibility of the individual
DOE sites conducting performance assessments and composite analyses. However, to promote
efficient use of resources and foster an appropriate degree of consistency among the site
programs, a complex-wide performance assessment and composite analysis maintenance program
should be developed and implemented as part of the Complex-Wide Low-Level Waste
Management Program as described in the Complex-Wide Strategy for Maintenance of
Department of Energy Low-Level Waste Disposal Facility Performance Assessment and
Composite Analysis.
Compliance with this requirement is demonstrated by the presence of the performance assessment
and composite analysis maintenance element in the Complex-Wide Low-Level Waste
Management Program, and the appropriate inclusion of interfaces, technical information, data,
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-17
7-09-99
inputs, and subsets of the DOE mixed low-level waste program and the commercial GTCC
programs into the Complex-Wide Low-Level Waste Management Program.
Supplemental References:
1. DOE, 1998. Complex-Wide Strategy for Maintenance of Department of Energy Low-
Level Waste Disposal Facility Performance Assessments and Composite Analyses, U.S.
Department of Energy, Washington, D.C., October 1998.
Chapter IV - Low-Level Waste Requirements
IV-18 DOE G 435.1-1
7-09-99
IV. D. Radioactive Waste Management Basis.
Low-level waste facilities, operations, and activities shall have a radioactive waste
management basis consisting of physical and administrative controls to ensure the
protection of workers, the public, and the environment. The following specific waste
management controls shall be part of the radioactive waste management basis:
(1) Generators. The waste certification program.
(2) Treatment Facilities. The waste acceptance requirements and the waste
certification program.
(3) Storage Facilities. The waste acceptance requirements and the waste
certification program.
(4) Disposal Facilities. The performance assessment, composite analysis, disposal
authorization statement, closure plan, waste acceptance requirements, and
monitoring plan.
Objective:
The objective of this requirement is to ensure that the hazards associated with low-level waste
management facilities, operations, and activities have been identified, their potential impacts
analyzed, and appropriate controls documented, implemented, and maintained for the protection
of workers, the public, and the environment.
Section 441
Discussion:
As described in the guidance on DOE M 435.1-1, Section I.2.F.(2) requires the radioactive waste
management basis to provide for development and documentation of controls to ensure the safe
and efficient management of radioactive waste. Requiring an approved radioactive waste
management basis for the initiation of new, or continuation of existing, radioactive waste
management activities should prevent the operation of facilities without the appropriate controls.
The term “controls” used here and elsewhere in the discussion of a radioactive waste management
basis refers to processes, procedures, equipment, instruments, and other items that are intended to
curb the likelihood of, or the consequences from, a problem that could arise from managing
radioactive waste. Controls includes such things as placards, alarms, tools, shielding, training
checklists, duplication of critical steps, redundant monitoring, analysis, sampling and testing, etc.
As discussed in Section I.2.F.(2), the radioactive waste management basis for low-level
radioactive waste management facilities, operations, and activities must be documented.
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-19
7-09-99
The required elements of the radioactive waste management basis vary with the type of waste
management operation or facility and the types of hazards associated with the facility. As stated
in the introductory statement of this requirement, the items required for a radioactive waste
management basis listed in the requirement for the four types of low-level waste management
facilities, operations, and activities is not a complete list of those items which should be included
in a radioactive waste management basis. Several processes, procedures, and documents that are
required by other directives and requirements provide for radioactive waste management controls
that should be considered part of the radioactive waste management basis. The guidance on DOE
M 435.1-1, Section I.2.F.(2) discusses this aspect of the radioactive waste management basis in
detail.
Example: Site Q operates a low-level waste storage facility. The Field Element staff is
required to ensure that it operates under a radioactive waste management basis. The
staff reviews the items in the requirement cited above, plus the facility-specific
procedures for implementing the site's radiological control program, health and safety
plan, training program, quality assurance program, and record-keeping plan, and
determines an adequate radioactive waste management basis exists.
Also, as discussed in the DOE M 435.1-1, Section I.2.F.(2) guidance, if a low-level waste
management facility already operates under an approved Authorization Basis, it may not need any
additional controls to demonstrate that it has a radioactive waste management basis. In this case,
the Authorization Basis documentation is reviewed and evaluated to determine whether it
sufficiently covers the requirements needed for a radioactive waste management basis. The Field
Element Manager has the responsibility to ensure the low-level waste management facilities under
his or her authority have a radioactive waste management basis.
Example: The Authorization Basis documentation for a Liquid Radioactive Waste
Handling Facilities at Site T, which includes a Liquid Treatment Facility (a low-level
waste treatment facility), is reviewed. Based on the review, it is determined that the
following Authorization Basis documents and associated programs include significant
descriptions of the controls for the management of low-level waste at the Effluent
Treatment Facility:
Section 442
C Safety Analysis Reports (SARs)
C Technical Justification for Continued Operation/Basis for Interim
Operation/Design Basis Accident Analysis Report
C Operational Safety Requirements/Technical Safety Requirements (includes
waste acceptance requirements of the Effluent Treatment Facility)
C Technical Standards
C SAR Update Request Packages
Chapter IV - Low-Level Waste Requirements
IV-20 DOE G 435.1-1
7-09-99
C
C
C
Other Documents Identified by DOE and the contractor as Authorization
Basis Documents (Safety Evaluations, Exemptions, Unreviewed Safety
Questions Evaluation)
DOE Safety Evaluation Reports
Listing of Documents that are to be Configuration Managed but are not
AB Documents (includes Liquid Treatment Facility Waste Certification
Program Plan for certifying waste to the Solid Waste Disposal Area)
Following analysis of the information, the DOE field office concludes the complete set of
operational requirements relied upon by the site to ensure that the public, workers, and
the environment are protected from the hazards associated with the management of the
radioactive waste at the Liquid Treatment Facility are in place. A radioactive waste
management basis statement is prepared that concludes the basis is covered in the
Authorization Basis documents.
For a facility that generates low-level waste, the radioactive waste management basis is to include
the program for certifying that waste meets the waste acceptance requirements of the facility(ies)
to which the waste will be sent. The waste certification program is reviewed against the
applicable requirements of DOE M 435.1-1 and approved in accordance with the manual before
becoming part of the radioactive waste management basis. As discussed in guidance on DOE M
435.1-1, Section I.2.F.(2), several other processes and procedures will contribute to a complete
radioactive waste management basis at a generating facility.
Example: A small laboratory facility on DOE’s Site R generates low-level waste. The
radioactive waste management basis for the facility is established through the review and
approval of the lab’s waste certification procedure and a review of the following for
adequacy: the site Health and Safety Plan, the site Training Program, and the site Waste
Transfer Procedure. This is documented in a radioactive waste management basis
statement covering the laboratory.
Facilities that store or treat low-level waste are to have approved waste acceptance requirements
(see DOE M 435.1-1, Section IV.G) prior to the issuance of a radioactive waste management
basis. The waste acceptance requirements will usually suffice as the documentation of the
radiological, physical, and chemical limitations on waste that can be safely received at the facility,
provided they are developed correctly considering the hazards of the waste to be managed, and
are kept up-to-date. A facility that stores or treats waste also is generally expected to have a
waste certification program. Waste from these facilities will have to be certified as meeting the
waste acceptance requirements of the facility to which it will be transferred, and the facilities have
the potential for generating radioactive waste (e.g., secondary processing streams from treatment,
monitoring and sampling, radioactive release cleanup). Consequently, storage and treatment
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-21
7-09-99
facilities should also have an approved waste certification program as part of their radioactive
waste management basis.
Section 443
The radioactive waste management basis for low-level waste disposal facilities is to be based on
documented controls similar to those discussed for treatment or storage facilities, but with
additional conditions imposed by the performance assessment and composite analysis required in
DOE M 435.1-1, Section IV.P and by the disposal authorization statement issued following
Headquarters review and approval of the performance assessment and composite analysis. As
described in DOE M 435.1-1, Sections IV.Q and IV.R, the preliminary closure plan and
preliminary monitoring plan are also to be reviewed as part of the evaluation of the performance
assessment and composite analysis leading to the issuance of the disposal authorization statement.
The results of the performance assessment and composite analysis, along with the controls based
on the safety analyses required by DOE 5480.23, provide the basis by which the quantities and
concentrations of radionuclides that can be accepted for disposal will be identified and
documented in the waste acceptance requirements.
The responsibility for the radioactive waste management basis for low-level waste disposal
facilities resides with the Field Element Manager. However, Headquarters review and approval of
the performance assessment and composite analysis and issuance of the disposal authorization
statement is necessary prior to issuance and documentation of the radioactive waste management
basis, in accordance with the requirements in the Manual. Also, the documents required for the
radioactive waste management basis for disposal facilities are related to one another and depend
on information contained in or as a result of information or analysis in one or another of the other
documents.
Example: The radioactive waste management basis for a low-level waste disposal
facility, includes (among many controls, including safety and health plans, training
programs, etc.) limits on tritium that can be accepted in a disposal unit, as calculated by
the performance assessment. This limitation is included in the waste acceptance
requirements of the facility as a limit per package. The disposal authorization statement
also includes a condition that the closure plan is to be updated within 18 months of the
issuance of the disposal authorization statement to include consistent monitoring
locations with the preliminary monitoring plan submitted separately. The radioactive
waste management basis statement references the disposal authorization statement to
include these conditions for continued operations.
The Headquarters review and approval of the performance assessment and composite analysis will
lead to the issuance of the disposal authorization statement to the Field Element Manager, who
should combine this with his/her own findings on the waste acceptance criteria and preliminary
closure and monitoring plans to document the radioactive waste management basis for the
disposal facility. Guidance on DOE M 435.1-1, Sections IV.P.(2) [performance assessment],
Chapter IV - Low-Level Waste Requirements
IV-22 DOE G 435.1-1
7-09-99
IV.P.(3)[composite analysis], IV.P(5)[disposal authorization statement], IV.Q.(1)[preliminary
closure plan], and IV.R.(3)[preliminary monitoring plan] provide details on what information
needs to be addressed in these documents for review and approval for a radioactive waste
management basis to be issued.
Section 444
As part of the radioactive waste management basis, site personnel needs to implement a system or
process for tracking the waste inventory at a storage, treatment, or disposal facility. Tracking the
waste inventory is a means of ensuring that radionuclide limits established in accordance with a
safety analysis or performance assessment will not be exceeded. In addition, a system or process
for accurately tracking waste received at a facility can facilitate providing information to the
complex-wide waste management data system (see guidance Section I.2.D.(2)).
Compliance with this requirement is demonstrated by a demonstrated radioactive waste
management basis that is signed by the Field Element manager or a designee for each low-level
waste management facility, operation, or activity. Using a graded approach, it may be possible to
include multiple activities under a single radioactive waste management basis, but it should be
possible to objectively identify which activities are covered. Further, the documented radioactive
waste management basis includes or references the controls that are established on a facility-
specific basis to address the unique waste management requirements and circumstances for each
facility, operation, and/or activity.
Example: A storage facility that stores mixed and non-mixed low-level waste has
approved waste acceptance requirements and a waste certification process that enables
low-level waste to be stored for 9 months and then shipped to a specific facility for
disposal. The mixed low-level waste is stored indefinitely. The radioactive waste
management basis statement references the waste certification process and the waste
acceptance requirement documentation, which in turn invokes the waste acceptance
requirements of the disposal facility. In addition to other site-wide programs and plans
(e.g., radiological control, health and safety, training), the radioactive waste
management basis statement also cites the RCRA permit issued for storage of mixed
low-level waste, and the facility operating procedure for segregating mixed and
non-mixed waste within the facility.
Supplemental References:
1. DOE, 1992. Nuclear Safety Analysis Reports, DOE 5480.23, U.S. Department of
Energy, Washington, D.C., April 10, 1992.
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-23
7-09-99
IV. E. Contingency Actions.
The following requirements are in addition to those in Chapter I of this Manual.
(1) Contingency Storage. For off-normal or emergency situations involving high
activity or high hazard liquid low-level waste storage or treatment, spare
capacity with adequate capabilities shall be maintained to receive the largest
volume of liquid contained in any one storage tank or treatment facility.
Tanks or other facilities that are designated low-level waste contingency
storage shall be maintained in an operational condition when waste is present
and shall meet the requirements of DOE O 435.1, Radioactive Waste
Management, and this Manual.
(2) Transfer Equipment. Pipelines and auxiliary facilities necessary for the
transfer of high activity or high hazard liquid low-level waste to contingency
storage shall be maintained in an operational condition when waste is present
and shall meet the requirements of DOE O 435.1, Radioactive Waste
Management, and this Manual.
Objective:
Section 445
The objective of this requirement is to mitigate the impacts on the public, workers, or
environment in the event that a leak develops in a tank storing high activity or high hazard liquid
low-level waste or in a facility processing such waste. The mitigation is provided by ensuring
spare waste storage capacity is a required part of a site’s emergency management program. To
meet this objective, there needs to be both capacity to handle the largest volume of any single
storage tank or liquid waste in process, and the capability to transfer the waste.
Discussion:
This requirement shall be implemented through and included in site emergency management
programs that are required by DOE O 151.1, Comprehensive Emergency Management System.
The directive DOE O 151.1 is referenced in DOE M 435.1-1, Chapter I and considered necessary
for the safe management of radioactive waste. The Comprehensive Emergency Management
System requires the development of a complex-wide system for preparing for and managing
emergencies. At the site level, personnel are to establish an Operational Emergency Base
Program that provides the framework for responding to events involving, among other subjects,
health and safety, and the environment. The program requires a qualitative hazards survey to
identify the emergency conditions, describe the potential impacts, and summarize the planning and
preparedness requirements that apply.
Chapter IV - Low-Level Waste Requirements
IV-24 DOE G 435.1-1
7-09-99
During the development of the requirements of DOE M 435.1-1, Radioactive Waste Management
Manual, a waste management hazard and safety analysis identified the loss of containment of a
storage tank or waste processing facility containing radioactive liquids as a hazard requiring
mitigation. In addition to requiring facility designs to maintain waste confinement (see
DOE M 435.1, Section IV.M.(2)), the ability to respond to leaks or other off-normal conditions if
they occur was also considered necessary. Consequently, the requirements to have adequate
spare capacity and the ability to transfer waste to the spare capacity were established.
Liquid low-level waste is considered high activity if procedural or physical controls are required
to protect workers from radiation exposure. Liquid low-level waste is considered a hazard if it
presents a situation that has the potential to adversely impact the health and safety of personnel,
the public, or the environment. High hazards are those with the potential for onsite and offsite
impacts to large numbers of persons or with the potential for major impacts to the environment or
national security.
Operating procedures are developed and utilized for transfer of high activity or high hazard liquid
low-level waste to contingency storage. The procedures should address maximum operational
capacities and limits for components of the operational system (e.g., spare storage capacity
available in tanks). The procedures should define and address all possible emergency transfer
scenarios needed to comply with this requirement.
Contingency Storage. Contingency storage is to be provided for both stored liquid low-level
waste and for liquid low-level waste treatment facilities. In the case of storage tanks, adequate
volumetric capacity must be available to receive the largest volume of waste stored in any single
tank. In the case of a treatment facility, adequate capacity must be available to allow all in-
process liquids in the facility to be moved into storage in the event of emergency or off-normal
conditions.
Section 446
A number of factors are considered in maintaining spare capacity. First, the requirement includes
a provision that the spare capacity has “adequate capabilities.” Therefore, the spare capacity must
have the necessary features and functionality as dictated by the design and safety analysis for the
facility and wastes of concern. Features to be taken into account include appropriate materials of
construction, shielding, ventilation and filtration, heat dissipation, liquid level monitoring, and
mixing. Similarly, if the waste that may need to be transferred is regulated by some external
regulation (e.g., RCRA), the tank(s) that would be used for spare capacity should be properly
permitted. Likewise, the design bases events for the facility must be considered in determining the
design of contingency storage, and whether some events may be severe enough that additional
considerations must be included in the siting design, or operation of contingency storage to ensure
its availability if there were a leak in an existing storage tank.
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-25
7-09-99
The requirement specifies that the contingency storage provided is to meet the requirements of
DOE O 435.1 and DOE M 435.1-1. Of prime interest is the ability of existing contingency tanks
or other facilities to meet the requirements for confinement in Low-Level Waste Treatment and
Storage Facility Design DOE M 435.1-1, Section IV.M.(2). Additionally, compliance with the
requirements for ventilation, instrumentation and control systems, and monitoring systems for
storage facilities is also very important for tanks or facilities that will be used for contingency
storage. Meeting these requirements, in combination, ensures that the use of existing tanks or
other facilities for contingency storage minimize the potential impacts of off-normal or emergency
situations involving high activity or high hazard liquid low-level waste.
Spare capacity may be provided by a single tank or by the combined available volume in multiple
tanks. In cases where radiation fields are sufficiently low, spare short-term capacity may be able
to be provided by portable tanks, tankers (i.e,. railroad cars), or tank trucks, provided that all
applicable requirements can be met. Due to the potential of airborne radioactive material,
impoundments or bermed areas open to the air generally should not be used for spare storage
capacity, unless a safety analysis shows that the risk to workers and the public is low.
Example: Liquid radioactive waste is stored in six underground storage tanks with a
design capacity of 250,000 gallons each. The waste in the all tanks has the same
chemical and radiological characteristics. One tank contains 200,000 gallons and each
of the others contain about 100,000 gallons. Capabilities exist to retrieve waste and
transfer it among the six tanks. This system meets the requirement because the largest
volume of 200,000 gallons can be distributed between any two of the other tanks.
Transfer Equipment. The ability to perform waste transfer is just as important as having the
capacity. Equipment necessary to transfer each tank or treatment facility volume of high activity
or high hazard liquid low-level waste in the event of a leak or other off-normal condition is to be
identified and documented.
Section 447
Example: Liquid radioactive waste is stored in six underground tanks with the volumes
and characteristics described in the previous example. Although there are transfer lines
to any of the tanks from a central diversion box, the tanks were constructed without the
capability to retrieve the waste. This situation does not comply with the requirement.
Although there is adequate capacity, the ability to transfer the waste does not exist.
Equipment necessary to transfer the contents of each tank is tested and inspected as part of a
routine maintenance program (see DOE M 435.1-1, I.1.E.(9)). Special attention should be given
to including in the maintenance program equipment and transfer lines that are not routinely used
in managing liquid wastes. Inspection and testing includes the following items:
Chapter IV - Low-Level Waste Requirements
IV-26 DOE G 435.1-1
7-09-99
• leak testing of transfer pipelines;
• ensuring the availability of any jumpers necessary for completing waste transfer;
• confirming that instrument panels, control panels, valves, pumps and any necessary
ventilation equipment is supplied with the necessary electrical power, air (for
pneumatically-controlled items), steam, and water; and
• performing functional tests of instruments, controls, valves, pumps, and ventilation
equipment.
The capability to perform an emergency transfer of high activity or high hazard liquid low-level
waste is to be maintained at all times. Therefore, every shift must include or have immediate
access to qualified individuals and the equipment necessary to perform transfers in a timely
manner, unless analysis of the hazards associated with the waste concludes that an immediate
transfer is unnecessary.
Example: A large shielding block is in place over a jumper pit that needs to be accessed
during an emergency transfer of liquid waste. The block can only be moved by a crane.
Therefore, implementation of this requirement entails making sure that the crane is
always operationally available (in a matter of hours rather than days) and every shift has
access to an individual qualified to operate the crane and remove the block.
Spare capacity may also be shared by different waste types, however mixing radioactive wastes of
different types should be evaluated and is generally not acceptable.
Example: A tank farm contains both high activity liquid low-level waste and liquid
transuranic waste in separate tanks and a third empty tank for contingency. An empty
mobile tank is maintained and available for emergency transfers of either waste in the
event that the contingency tank must be used by either the low-level transuranic waste.
Mixing waste types is prohibited in this case.
Compliance with these requirements are demonstrated if adequate spare capacity and transfer
equipment exists for emergency transfers of all high activity and high hazard liquid low-level
waste. In addition, the capability to perform emergency transfers is demonstrated by having waste
transfer routings identified, operational procedures to direct transfers, staff trained to the
procedures, and records showing that the spare capacity and transfer capability are kept in
operating condition.
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-27
7-09-99
Supplemental References:
1. DOE, 1995. Comprehensive Emergency Management System, DOE O 151.1, U.S.
Department of Energy, Washington, D.C., September 25, 1995.
Chapter IV - Low-Level Waste Requirements
IV-28 DOE G 435.1-1
Section 448
7-09-99
IV. F. Corrective Actions.
The following requirements are in addition to those in Chapter I of this Manual.
(1) Order Compliance. Corrective actions shall be implemented whenever
necessary to ensure the requirements of DOE O 435.1, Radioactive Waste
Management, and this Manual are met.
Objective:
The objective of this requirement is to ensure that actions will be taken to preclude, minimize, or
mitigate hazards whenever a situation arises at a low-level waste management facility that could
threaten worker or public safety, or the environment.
Discussions:
DOE M 435.1-1, Section I.2.G states that all personnel have a responsibility to identify conditions
that require corrective actions to achieve compliance with the Order and Manual requirements or
to address health and safety conditions that pose an imminent or possible danger. The Manual
states that this responsibility includes considering shutdown or curtailment of facilities and
activities, if warranted by the seriousness of the circumstances. This requirement ensures that this
responsibility is implemented for all low-level waste management facilities and activities.
Corrective actions are activities which, when implemented, will address and correct noncompliant
or hazardous conditions. Corrective actions can include improvements to documentation (e.g.,
procedures, plans, authorization basis documents), training and qualification programs or
procedures, physical and process design changes, changes to operating conditions, or a
combination of these activities.
Corrective Action System. A corrective action system exists for addressing noncompliant or
hazardous conditions for low-level waste management facilities, operations, and activities.
Corrective actions in response to quality assurance program assessments are addressed in the
Implementation Guide for Use with Independent and Management Assessment Requirements of
10 CFR 830.120 and DOE O 414.1 Quality Assurance. The corrective action system provides
for documenting noncompliant or hazardous conditions, identifying the organizations or
individuals responsible for developing and implementing corrective actions, providing corrective
action status, and tracking progress through final implementation of the actions. The corrective
action system is instituted as a fundamental part of the systematic evaluation of radioactive waste
activities that is implemented by the site-wide radioactive waste management program (see
guidance for DOE M 435.1-1, Section I.2.F.(1)).
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-29
7-09-99
A problem requiring corrective action could range from a minor deviation from a procedure, to a
situation that poses an immediate threat to health and safety from an uncontrolled release of large
quantities of radioactive material. For situations where a problem could pose an immediate risk to
a worker, member of the public, or damage to the environment, immediate shutdown of the
process or facility may be appropriate as the first step in addressing the problem (see guidance for
DOE M 435.1-1, Section IV.F.(2)).
Example: An employee of the Site Q laboratory facility noticed that a drum of mixed
low-level waste which was supposed to be closed and ready for shipment did not have a
rim lock and was not correctly labeled. He alerted the lab manager, who alerted central
waste management. The laboratory corrective action system resulted in a corrective
action plan that identified the lab manager as the responsible individual for producing a
revised procedure on locking and labeling waste drums, and providing training to the lab
staff. A reminder memo was sent to affected staff and a follow-up review was scheduled
for 45 days after the occurrence .
Section 449
If a facility or activity can be allowed to operate while a noncompliant or hazardous condition
exists, the allowance and any associated limitations must be defined as part of the facility or
activity’s radioactive waste management basis, identified as a configuration controlled item in a
configuration management plan or included in a revision or modification to an operating
procedure or similar controlled documentation. If a noncompliance impacts safety associated
with use of a procedure, system, or facility, the corrective action system must provide for
preventing the use (e.g., locking out) of the affected procedure, system, or facility.
Example: In the example above, waste generation was temporarily curtailed so that no
new waste drums would be filled until the revised procedure was in place. Waste
generation was allowed to resume as the training took place. No new drums were ready
for locking and labeling until training had been completed.
Corrective Actions for Low-Level Waste Disposal Facilities. Situations could be present at low-
level waste disposal facilities that may require corrective measures even though there is no
immediate or obvious safety or environmental concern. This is because some situations, left
unchecked, could result in performance degradation to an extent that the ability of the disposal
facility to continue to meet performance objectives could be compromised at some time in the
future. Monitoring to detect degrading performance factors must be incorporated in the
performance monitoring plan required by DOE M 435.1-1, Section IV.R (see guidance on DOE
M 435.1-1, Section IV.R.(3)(c)). Some factors that should be considered include:
Chapter IV - Low-Level Waste Requirements
IV-30 DOE G 435.1-1
7-09-99
• Routine and special inspection of site conditions;
• Detection of events or conditions that could degrade performance of the disposal
site;
• Periodic studies and surveys to determine the extent of migration of radionuclides,
projection of potential future public doses, and their significance relative to the
performance objectives;
• Specification of graded levels of response for each pathway; and
• Identification of corrective measures.
Conditions that have resulted in, or may lead to, site performance failure from ponding or
flooding need to be corrected or mitigated as necessary. Ponding and flooding at the site provide
opportunity for increased infiltration of water into the waste disposal units. Corrective measures
to be considered include filling and regrading of the ponded area, construction of adequate surface
water control systems such as dikes or diversion dams, and contouring of surfaces to control
surface runoff.
Conditions at the disposal facility that may lead to site performance failure because of water
accumulation in excavations also need to be corrected. Hydrologic conditions to be considered
include:
• Infiltration through the excavation cover;
• Lateral intrusion; and
• Elevation of the water table.
Other site conditions to be considered include subsidence or cracking of the excavation cover and
inadequate or damaged surface water diversion system. Corrective measures to be considered
include:
• Reduction of the permeability of the excavation cover by compaction;
• Contouring of the cover material for controlled removal of surface water;
• Installation of subsurface drainage;
• Installation of barriers of low-permeability materials;
Chapter IV - Low-Level Waste Requirements
Section 450
DOE G 435.1-1 IV-31
7-09-99
• Modification of nearby topography and surface material to reduce infiltration into
the surrounding soils;
• Excavation of cover subsidence zone (add fill material, compact, contour, and
stabilize, if subsidence is due to voids between packages, grout can be injected into
void space);
• Pothole subsidence (fill, compact, and recontour);
• Cracking (excavate zone around crack, fill, compact, and recontour);
• Design and installation of diversion system to prevent offsite surface water from
entering the site; and
• Repair or installation of onsite drainage system to remove onsite runoff.
Conditions at the site that may lead to exposure of the waste need to be corrected, since such
exposure is a danger to workers and provides the opportunity for radionuclide transport by
surface water and air pathways or by vectors (insects, rodents, etc.). These conditions include
wind and water erosion of the excavation cover, subsidence or cracking of the excavation cover,
burrowing by animals into the waste, and growth of deep-rooted plants. Corrective measures to
be considered include:
• Filling and regrading the surface;
• Establishing erosion resistant cover;
• Filling of burrow holes;
• Installing physical, chemical, and/or biological barriers;
• Removal of deep-rooted plants; and
• Vector control.
Compliance with this requirement is demonstrated if a corrective action system addresses
noncompliant or hazardous situations involving low-level waste management facilities in a
systematic fashion, and allows identification of problems by all personnel.
Chapter IV - Low-Level Waste Requirements
IV-32 DOE G 435.1-1
7-09-99
Supplemental References:
1. DOE, 1996. Implementation Guide for Use with Independent and Management
Assessment Requirements of 10 CFR 830.120 and DOE O 414.1 Quality Assurance,
DOE G 414.1-1, U.S. Department of Energy, Washington, D.C., August 1996.
2. DOE, 1990. Environmental Monitoring for Low-level Waste Disposal Sites: Low-level
Management Handbook Series, Revision 2, DOE/LLW-13Tg, National LLW
Management Program, Idaho Falls, ID, 1990.
3. DOE, 1986. Exposure and Improved Techniques in Radiological Environmental
Monitoring at Major DOE Low-level Waste Disposal Sites, DOE/LLW-54T, National
LLW Management Program, Idaho Falls, ID, 1986.
IV. F.(2) Operations Curtailment. Operations shall be curtailed or facilities
shut down for failure to establish, maintain, or operate consistent with
an approved radioactive waste management basis.
Objective:
The objective of this requirement is to limit the operation of waste management activities and
facilities as necessary to avoid creation of near- or long-term safety or environmental hazards.
Discussion:
DOE M 435.1-1 requires that a radioactive waste management basis be established for each
low-level waste management facility, operation, or activity. The radioactive waste management
basis documents the conclusion that the potential hazards from management of radioactive waste
have been sufficiently evaluated and that adequate controls are in place to provide assurance that
the public, workers, and the environment are being protected. Field Element Managers are
responsible for ensuring a radioactive waste management basis is developed, reviewed, approved,
and maintained for each DOE radioactive waste management facility, operation, or activity (DOE
M 435.1-1, Section I.2.F.(2)). The guidance for that requirement should be consulted for
additional details on the development, review, and approval of a radioactive waste management
basis. Also, additional discussion concerning the radioactive waste management basis for low-
level waste generator, treatment, storage, and disposal facilities is discussed under guidance for
DOE M 435.1-1, Section IV.D.
Section 451
As part of the Field Element Manager’s responsibilities for maintaining the radioactive waste
management basis for low-level waste management facilities, operations, and activities under
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-33
7-09-99
his/her authority, the Field Element Manager evaluates the compliance of the facilities, operations,
and activities with the constraints and controls documented in the radioactive waste management
basis by ensuring that routine assessments are conducted. If the Field Element Manager
determines, either through routine assessment or by virtue of an occurrence or off normal event,
that an operation, activity, or facility is not operating in compliance with an approved radioactive
waste management basis, it must be curtailed or shut down. The action taken is commensurate
with the hazards associated with the noncompliance and with the continued operation of the
facility.
This requirement is to be implemented in a graded manner. Actions to be taken are based on
assessments of adherence to radioactive waste management bases, and can range from shutdown
of an operation or facility to placing limits or constraints on what activities can be performed or
how the activities are to be performed. Shutdown of a facility involves stopping all operations in
the facility except surveillance or monitoring activities necessary to maintain the facility in a safe
standby condition. Shutdown is considered appropriate when there is either a potential imminent
threat to safety or environmental protection that cannot be mitigated, or a blatant failure to
establish or comply with a radioactive waste management basis.
Alternatively, there may be cases where the facility, operation, or activity assessment determines
that the radioactive waste management basis is no longer current or has been violated, but there is
no imminent threat to public, worker, or environmental protection. In such a case, the Field
Element Manager may decide that shutdown of the facility is not necessary. It may be sufficient
to impose certain limits until the radioactive waste management basis is made current. The limits
imposed may prohibit the generation, receipt, or processing of certain waste streams, or may
involve constraints on the processes that may be performed.
Example: Site Q conducts bi-annual assessments of the Building B low-level and mixed
low-level storage facilities for compliance with the radioactive waste management basis.
The 1996 biannual assessment found two non-compliance findings and five observations.
The corrective action system implemented at Site Q requires the non-compliance findings
to be entered and formally responded to with corrective action plans, but not the
observations. The non-compliances were in document control and training, so the
storage activities were not curtailed in any way while the document control and training
procedures were improved. The facility was assessed again in 1997 to determine if the
corrections were in place, which was an accelerated assessment schedule from the
normal bi-annual assessments.
The action taken in response to the failure to establish a radioactive waste management basis is to
be clearly documented in a formal communication (e.g., letter, memorandum). Such
communication needs to identify the reason for the shutdown or curtailment, and identify what is
necessary to initiate restart. Generally, development of a corrective action that is implemented
Section 452
Chapter IV - Low-Level Waste Requirements
IV-34 DOE G 435.1-1
7-09-99
through the corrective action system discussed in the preceding section would be appropriate for
responding to a shutdown or curtailment of activities at a low-level waste management facility.
In concert with Core Requirement #6 of the Integrated Safety Management System, “Feedback
and Improvement,” the Field Element Manager should use the audits and assessments to identify
opportunities for improvement in the implementation of an activity or facility’s radioactive waste
management basis. Identified improvement actions should be shared with like organizations and
tracked by management to determine whether they are yielding the anticipated improvements.
Communicating the results of assessment upward in the DOE and contractor organization will
allow the findings to reach the management level with authority necessary to effect improvements.
Compliance with this requirement is demonstrated with a documented system of routine
assessments to determine whether waste management activities and facilities are operating in
accordance with an approved radioactive waste management basis that provides for graded
limitations that can be placed on activities and operations that do not have, or are operating
outside of, an approved radioactive waste management basis, including shutdown of the facility.
Supplemental References:
1. DOE, 1997. Safety Management Functions, Responsibilities, and Authorities Policy,
DOE P 411.1, U.S. Department of Energy, Washington, D.C., January 28, 1997.
2. DOE, 1996. Safety Management System Policy, DOE P 450.4, U.S. Department of
Energy, Washington, D.C., October 15, 1996.
3. DOE, 1997. Line Environment, Safety and Health Oversight, DOE P 450.5, U.S.
Department of Energy, Washington, D.C., June 26, 1997.
4. DOE, 1997. Manual of Safety Management Functions, Responsibilities, and Authorities
Manual, DOE M 411.1-1, U.S. Department of Energy, Washington, D.C., October 8,
1997.
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-35
7-09-99
IV. G. Waste Acceptance.
The following requirements are in addition to those in Chapter I of this Manual.
(1) Technical and Administrative. Waste acceptance requirements for all low-
level waste storage, treatment, or disposal facilities, operations, and activities
shall specify, at a minimum, the following:
(a) Allowable activities and/or concentrations of specific radionuclides.
(b) Acceptable waste form and/or container requirements that ensure the
chemical and physical stability of waste under conditions that might
be encountered during transportation, storage, treatment, or disposal.
(c) Restrictions or prohibitions on waste, materials, or containers that
may adversely affect waste handlers or compromise facility or waste
container performance.
Objective:
The objectives of the waste acceptance requirements are to ensure that low-level waste which is
received at a facility contains only the radionuclides that the facility can safely manage, and only in
concentrations and/or total activities which are compatible with the work to be undertaken in the
facility; ensure that low-level waste which is to be received at a facility is in a form or container
that will maintain its integrity and retain acceptable configuration under the conditions that are
expected to be encountered during the management steps the waste will undergo; and ensure that
no low-level waste received at a facility contains materials that will compromise the safety or
integrity of the facility under the expected operating conditions.
Section 453
Discussion:
As discussed in Section I.2.F.(6) of the guidance for Chapter I, General Requirements, the waste
acceptance requirements establish the conditions for waste that facilities can safely receive.
Therefore, the acceptance requirements for a low-level waste storage, treatment, or disposal
facility include all requirements that low-level waste must meet to be acceptable for receipt, and
for the subsequent storage, treatment, or disposal, as appropriate.
In conducting the analyses for development of the DOE M 435.1-1 requirements, minimum
acceptance requirements that must be specified in the waste acceptance documentation for
storage, treatment, and disposal facilities in order for low-level waste to be safely handled were
identified. DOE M 435.1-1, Sections IV.G.(1) (a) through (c), and (e) provide minimum
Chapter IV - Low-Level Waste Requirements
IV-36 DOE G 435.1-1
7-09-99
acceptance requirements that must be in all low-level waste storage, treatment, and disposal
facility waste acceptance requirements. DOE M 435.1-1, Section IV.G.(1)(d) provides additional
minimum acceptance criteria that must be in all low-level waste disposal facility requirements.
Guidance on subrequirement (a) is provided below under Radionuclide Content or Concentration.
Guidance on subrequirements (b) and (c) is provided under Waste Form and Package Criteria and
Prohibitions. Guidance on subrequirements (d) and (e) is provided under the citations of those
requirements following the guidance on subrequirements (a) through (c).
Development of Waste Acceptance Requirements. A facility receiving waste for storage,
treatment, or disposal is required to document the waste acceptance requirements for the facility.
These requirements have their foundation in facility design capabilities such as volume, handling
weight, allowable contents, and radiological limits (i.e., criticality, radiation, contamination).
Other requirements may include any number of regulations promulgated by the EPA, NRC, DOT,
the host state, and DOE itself. The designer and operator of the facility receiving waste are likely
to be most knowledgeable and understanding of the requirements and limitations of the facility
and, therefore, are in the best position to establish the waste acceptance requirements or criteria
that must be met for waste sent to the facility.
A low-level waste management facility at a site may have its own specific stand-alone waste
acceptance requirements. Or a site may have general waste acceptance requirements applicable to
all low-level waste management facilities at the site, with separate facilities, adding facility-specific
acceptance requirements to the site waste acceptance requirements as necessary. This practice
may be particularly effective at sites with many facilities which manage small quantities of waste
with multiple locations for staging, storage, and/or central management of waste. At such
facilities, most of the process and procedural waste acceptance requirements could be in one
document applicable to the whole site, which would be supplemented with specific technical
requirements for acceptance at each of the separate management locations. If activities across
various facilities are similar, they could share the same supplemental waste acceptance
requirements documents. Likewise, if several activities are carried out at locations that are close
to one another, or are managed by the same entity, then one supplemental technical document
may be prepared to cover those activities.
Section 454
The waste acceptance requirements and documentation for a facility receiving waste for storage,
treatment, or disposal is prepared using a graded approach commensurate with the hazards
associated with the management of the waste in the facility and the complexity of the activities to
be conducted in the facility and upon the waste. The waste acceptance requirements document
for a facility which receives major transfers of large quantities of low-level waste from many
generators, or with high specific activities or highly variable contents may need to address many
hazards and consequently be more detailed. By contrast, a storage facility which will only pass-
through properly packaged waste directly to a disposal facility without any additional processing
or packaging may only need a minimum set of requirements. Perhaps only a few administrative
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-37
7-09-99
requirements would be necessary for proper receipt of waste at such a storage facility, along with
assurance that waste received at the storage facility meets the disposal facility technical waste
acceptance requirements.
Example 1: A large DOE low-level waste disposal facility accepts waste from many
offsite generators, from a variety of processes, including a variety of types and
concentrations of radionuclides. Waste acceptance requirements for receipt and disposal
of low-level and mixed low-level waste are prepared as a stand-alone set of requirements
due to the complexity and diversity of the wastes received. The processes for acceptance,
and technical and administrative requirements for the waste are unique to this disposal
facility.
Example 2: At a large DOE site, several facilities are used for storage of low-level
waste. One waste acceptance requirements document is prepared containing all of the
necessary administrative requirements for all storage buildings. Each storage facility
has a technical procedure which contains the specific technical criteria for the facility,
and which implements the administrative waste acceptance requirements document for
the processes and forms, etc. that are needed for storage of low-level waste.
The performance assessment, composite analysis, disposal authorization statement, safety analysis
report, criticality analysis, and any other appropriate safety and/or authorization basis documents
are to be used to establish the waste acceptance criteria for receiving facilities low-level waste for
storage, treatment or disposal. These documents and analyses provide the basis for radioactivity
(concentration and inventory) limits, waste classes or categories, waste form and/or packaging
stability requirements, allowable chemical content, allowable free liquid content, and any other
necessary waste package or form requirements to ensure that the facilities’ design bases,
performance, and operating bases are protected.
DOE M 435.1-1, Chapter IV requires the conduct of a performance assessment maintenance
program. Under this program the performance assessment must be revised if changes occur in
radionuclide inventories beyond expected limits, facility design, or the understanding of the site or
any other features that change the conclusions of the existing performance assessment. Thus,
when the performance assessment is changed, the waste acceptance requirements need to be
reviewed to determine if the performance assessment changes affect any acceptance criteria. If
so, then the acceptance requirements are modified as appropriate.
Section 455
Example: Monitoring wells located on the boundary of a low-level waste disposal
facility indicate the presence of migrating radionuclides sooner than estimated by
performance assessment calculations. The data affecting release rates for these
radionuclides in the performance assessment are analyzed following this discovery. The
analysis indicates the presence of a significant chemical catalyst which results in higher
Chapter IV - Low-Level Waste Requirements
IV-38 DOE G 435.1-1
7-09-99
release rates. The calculations in the performance assessment are updated and waste
acceptance requirements and radionuclide inventory limits are revised based on the new
performance assessment modeling results.
Radionuclide Content or Concentration. Radiological limits for storage, treatment, and disposal
facilities may be derived from a number of technical as well as administrative sources. In
developing radionuclide limits, personnel need to consider legislative and/or regulatory
limitations, the disposal facility performance assessment and composite analysis, safety analysis
reports, and criticality analyses. In addition to establishing general radiological limits (e.g., a
contact dose rate), these sources identify specific radionuclides whose concentration or total
activity must be limited in the waste acceptance criteria in order to remain within the bounds for
safe and legal facility operation.
The results of the performance assessment and composite analysis will provide information on
certain critical radionuclides that are most important for assuring that the long-term performance
of the low-level waste disposal facility will be maintained. In some cases, the critical
radionuclides need to be specifically identified in the waste acceptance criteria, and additional
technical or administrative requirements specified for them. A critical radionuclide may require
specific information on the characterization documentation that must be input into the disposal
facility records. The waste acceptance requirement documentation specifies what this information
is and how it is to be provided to the facility receiving waste for storage, treatment or disposal.
Example: The results of the performance assessment for a specific low-level waste
disposal facility indicates that control of several specific radionuclides is important to
the protection of ground water resources. The waste acceptance requirements for the
facility state the limits on each of these radionuclides and that the amount of each of
these nuclides must be specifically reported on the characterization documents for
packages of low-level waste received at the facility. The waste acceptance requirements
indicates that the lower limit of detection of equipment used to characterize waste must
be included in the characterization information where a 0 (zero) is reported for any of
these radionuclides.
The performance assessment analysis may also indicate that some waste streams or forms to be
disposed at the disposal facility being evaluated need to be packaged or otherwise disposed in a
structurally stable form. These wastes may be identified specifically and identified in the waste
acceptance requirements as needing to be structurally stable prior to acceptance at the disposal
facility. Alternatively, the waste acceptance requirements may include a site-specific classification
or categorization system which requires stability, or some other additional management steps, for
wastes containing certain concentrations of specific radionuclides. The waste acceptance
requirements may also allow for acceptance of certain wastes in a bulk, non-containerized fashion.
Section 456
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-39
7-09-99
Example: The results of an intruder analysis in the performance assessment for a
specific low-level waste disposal facility indicate that wastes containing concentrations of
three radionuclides greater than calculated values may not be acceptable for
near-surface disposal unless measures are taken to provide intruder protection from the
wastes. A supplementary intruder analysis is conducted using new assumptions of a more
stable waste form. The supplementary intruder analysis indicates that a higher
concentration of the radionuclides can be accepted using the more stable waste form
assumed in the analysis. Therefore the waste acceptance criteria are developed to allow
for wastes to be received containing the lower concentration of the radionuclide in
untreated waste, and allows for wastes to be received containing the higher concentration
of the radionuclides, if the waste is treated to the more structurally stable waste form.
The safety analysis report prepared for a low-level radioactive waste management facility may
also identify specific radionuclides that warrant specific attention from a worker safety standpoint,
and may require special handling if received and managed at the facility.
Example: A storage facility that manages low-level mixed waste is subject to RCRA Part
B permit requirements for routine inspection of the waste. An analysis of worker
radiation exposure associated with inspection of the storage configuration indicates that
several radionuclides need to be controlled below certain concentrations to maintain
doses to workers as low as reasonably achievable. The waste acceptance requirements
for the facility reflect the allowable concentrations from the safety analyses as maxima
for waste that can be accepted for storage in the facility.
Any criticality analysis that will be conducted to derive the criticality safety program in
conformance with DOE M 435.1-1, Section I.1.E.(4) may also result in some limitations on
acceptance of fissile radionuclides. These limitations need to be included in the waste acceptance
requirements, as appropriate.
Waste Form and Package Criteria and Prohibitions. Waste acceptance requirements should
specify that wastes received at the facility are in a physically/chemically stable form. As used in
this requirement, stability refers to the physical and chemical properties of waste that are
necessary for it to be handled safely at a facility and to undergo the management steps normally
performed at that facility. Such stability is dependent on the waste management steps to be
performed with the waste (e.g., treat, store, or dispose) and the time to complete the management
step (e.g., time until treatment or length of expected storage period). Therefore, waste
acceptance requirements must specify the necessary physical and chemical stability for the specific
operations and activities for a given facility. Waste acceptance requirements for a low-level waste
treatment facility need to specify the physical and chemical precautions and conditions under
which untreated waste can be received at the facility so that facility safety and effective operations
will not be compromised. Any physical or chemical stabilization of waste prior to transfer to a
Chapter IV - Low-Level Waste Requirements
IV-40 DOE G 435.1-1
7-09-99
receiving facility need to be done according to a systematic process that may include
consideration of bench scale testing and verification that the process is producing satisfactory
results.
Section 457
The waste acceptance requirements need to specify waste streams, classes, or categories of waste
requiring application of specific physical, chemical, or structural stabilization methods, as
determined by the results of site-specific analysis of site conditions, the waste that needs physical
or chemical stabilization, and the desired performance of the facility. For treatment and storage
facilities, the results of safety analysis or other safety documentation may indicate certain waste
streams require specific physical or chemical stabilization to be safely handled by workers. The
waste acceptance requirements should specify limitations or technical criteria for these waste
streams, classes, or categories to meet. For disposal facilities, the performance assessment and
composite analysis may conclude that certain waste streams require stabilization in order to
contribute to a reasonable expectation that the disposal performance objectives will be met.
Again the waste acceptance requirements should specify the structural stability limitations or
criteria for these waste streams to meet.
Example: The results of the performance assessment for a specific low-level waste
disposal facility indicate that wastes containing three long-lived radionuclides are
acceptable for near-surface disposal provided some measures are taken to provide
additional protection to water resources. The waste acceptance requirements identify
low-level wastes containing these radionuclides as Category G low-level wastes
(G for groundwater). These category G low-level wastes will only be accepted in high
integrity containers and then be disposed in trenches containing special groundwater
protection barriers.
Acceptable waste forms, containers, and packages providing structural stability or inadvertent
intrusion protection are specified by the waste acceptance requirements. Structural stability refers
to the property of the waste to provide for stability of the disposal site during and after operations
to reduce the amount of subsidence and prevent or minimize radionuclide migration from the
disposal unit. Any structural stabilization that is conducted to meet waste acceptance
requirements needs to also be done according to a systematic process that includes consideration
of bench scale testing and verification that the process is producing satisfactory results, as
appropriate. The waste acceptance requirements indicate the testing and verification processes
that are acceptable. Consideration should be given to incorporating the technical positions and
tests discussed in the US Nuclear Regulatory Commission’s Technical Positions on Waste Form
(Refs. 1 and 2) into the low-level waste disposal site waste acceptance requirements for
acceptable verification tests for structurally stable waste.
The waste acceptance requirements need to list any specific packages and containers
pre-approved as acceptable for the low-level waste management facilities, as well as acceptable
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-41
7-09-99
overpacks. Consideration should be given to the policy on use of standardized low-level waste
disposal containers (Ref. 3) and its attendant guidance on recycling of radioactively contaminated
carbon steel.
The waste acceptance requirements need to identify any of the following specific technical
requirements that must be included to ensure that waste received at any storage, treatment, or
disposal facility is consistent with the operating basis of the facility:
Section 458
C the acceptable limits for waste package external surface dose rate for both contact
and remote handled packages, and heat generation;
C the acceptable limits for free liquid content, specified on a per package basis;
C the acceptable limits for maximum void space, specified on a per package basis;
C the necessary labeling and marking to be applied to low-level waste packages;
C the necessary information about any bar coding or other tracking system used at
the facility receiving the waste and the application of the system by generators;
C any specific requirements associated with acceptance of bulk waste, including any
additional restricted materials or limitations on materials and any specific technical
requirements bulk waste must meet for compatibility with disposal operations and
the conditions or specifications for handling bulk waste containers that will not be
disposed;
C any specific radionuclides or chemical or hazardous materials that are prohibited
from acceptance at the facility;
C any specific requirements associated with acceptance of mixed low-level waste,
including any additional restrictions or limitations on the waste or specifications for
handling mixed waste containers;
C any specific packages or types of packages or containers that are prohibited from
or restricted in acceptance at the facility;
C any specific requirements associated with acceptance of special low-level waste
streams needing out of the ordinary attention for receipt, handling, storage
treatment, or disposal, (e.g., sealed sources), including any additional restrictions
or limitations on the waste or specifications for handling the waste containers;
Chapter IV - Low-Level Waste Requirements
IV-42 DOE G 435.1-1
7-09-99
C any package protection requirements needed for transport and receipt to provide
needed physical protection to the packages to prevent breaching and so that the
certified status of the waste is preserved;
C the necessary shipping arrangements for transport to the facility receiving the
waste, including any electronic traffic data bases or scheduling system used.
Example 1: The Site B mixed waste incinerator waste acceptance criteria contains a list
of acceptable radionuclides and their acceptable concentrations, states the acceptable
limits for waste package external dose rate, contains a list of acceptable RCRA
hazardous constituents that can be destroyed by the incinerator, states that all waste must
be received in specially designed fiberboard boxes (expedites waste feed), prohibits
acceptance of Polychlorinated Biphenyls (PCBs) (it does not have a Toxic Substances
Control Act approval), and prohibits acceptance of gaseous, reactive, and explosive
waste.
Example 2: The Central Waste Management Unit Storage and Transfer Facility at Site B
provides centralized collection, staging, and transfer for all Site B low-level, mixed low-
level, and transuranic wastes. Site B waste is transferred/shipped to a variety of storage,
treatment, and disposal facilities, some on- and some off-site. The waste acceptance
requirements for the Central Waste Management Unit Facility specifies that all waste
must be certified to the waste acceptance criteria of the downstream facility to which it
goes next. The requirements also contain instructions on obtaining specific site-specific
labels containing barcoding from the Central Waste Unit, and instructions for attaching
specifically colored waste drum ring bands corresponding to a code that correlates with
the wastes’ next destination established by Central Waste that facilitates sorting and
segregating of the waste at the Transfer Facility.
Section 459
Compliance with these waste acceptance requirements is demonstrated if they are documented,
contain clear and precise criteria specifying the radionuclide limits in the form of contents or
concentrations that can be accepted, the limitations and prohibitions on waste forms and packages
that can be received, and the limits, prohibitions, or instructions concerning any other technical
information so that the waste is compatible with the safety basis of the facility, and which will
result in acceptable waste at subsequent steps in managing the low-level waste.
Supplemental References:
1. NRC, 1983. Final Waste Classification and Waste Form Technical Position Papers,
U.S. Nuclear Regulatory Commission, Washington, D.C., May 1983.
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-43
7-09-99
2. NRC, 1991. Technical Position on Waste Form, Revision 1, U.S. Nuclear Regulatory
Commission, Washington, D.C., January 1991.
3. Cowan and Owendoff, 1996. Steven Cowan and James Owendoff to Distribution,
memorandum, Use of Standardized Low-Level Waste Disposal Containers, U.S.
Department of Energy, Washington, D.C., April 17, 1996.
IV. G.(1) Technical and Administrative.
(d) The following are additional waste acceptance requirements
that shall be specified in low-level waste disposal facility waste
acceptance requirements:
1. Low-level waste must contribute to and not detract
from achieving long-term stability of the facility,
minimizing the need for long-term active maintenance,
minimizing subsidence, and minimizing contact of water
with waste. Void spaces within the waste and, if
containers are used, between the waste and its container
shall be reduced to the extent practical.
2. Liquid low-level waste or low-level waste containing free
liquid must be converted into a form that contains as
little freestanding liquid as is reasonably achievable, but
in no case shall the liquid exceed 1 percent of the waste
volume when the low-level waste is in a disposal
container, or 0.5 percent of the waste volume after it is
processed to a stable form.
3. Low-level waste must not be readily capable of
detonation or of explosive decomposition or reaction at
anticipated pressures and temperatures, or of explosive
reaction with water. Pyrophoric materials contained in
waste shall be treated, prepared, and packaged to be
nonflammable.
4. Low-level waste must not contain, or be capable of
generating by radiolysis or biodegradation, quantities of
toxic gases, vapors, or fumes harmful to the public or
Chapter IV - Low-Level Waste Requirements
IV-44 DOE G 435.1-1
7-09-99
workers or disposal facility personnel, or harmful to the
long-term structural stability of the disposal site.
5. Low-level waste in a gaseous form must be packaged
such that the pressure does not exceed 1.5 atmospheres
absolute at 20EEC.
Objective:
The objective of the technical and administrative requirements for low-level waste disposal is to
ensure that low-level waste disposed in DOE waste disposal facilities are in a form and/or
packaged so that the waste contributes to the facility meeting the performance objectives for
disposal of low-level waste.
Discussion:
Section 460
The analyses performed in developing the DOE M 435.1-1 requirements indicated that minimum
waste form requirements were needed for disposed low-level wastes to be able to continue to
have reasonable assurance that the long-term hazards from the waste would not adversely impact
the public, workers, or the environment. These minimum waste form requirements are designed
to achieve the performance objectives of the disposal facility over the long term. In order to
effectively contribute to meeting the performance objectives, the waste form and/or packages
should contribute to the goals of minimizing: (1) the need for long-term active maintenance of the
facility following closure; (2) subsidence during and after waste emplacement; and (3) the contact
of water with disposed waste. To assist in achieving these goals, the requirement includes
reducing void spaces within the packages of waste and within the waste itself, minimizing the
amounts of liquid that could be released through leaching or if a waste container were breached,
ensuring that waste packages do not contain any materials which would be potentially harmful to
the public or workers if a container was breached during operations or which would create an
unstable condition in the disposal unit following disposal.
Facility Stability. Subrequirement (DOE M 435.1-1, Section IV.G.(1)(d)1.) is intended to
provide a set of minimum requirements for waste forms and containers to contribute to the
long-term stability of the disposal site and thus contribute to a reasonable expectation that the
performance objectives for the disposal facility will be met for a long time into the future. Waste
acceptance requirements are to specify site-specific limits or criteria for acceptable structural
stability of waste forms and containers based on site conditions, the waste that requires stability,
and the desired performance of the facility. (Long-term stability of a low-level waste disposal
facility is discussed and described further in guidance on Section IV.M.(3), Low-level Waste
Disposal Facility Design.)
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-45
7-09-99
Waste forms and containers should maintain their basic shape and form for a period of time
corresponding to the period of time necessary to achieve performance objectives. For most low-
level waste, standard 55-gallon drums and boxes such as B-25 boxes are adequate. Containers
should be designed to withstand the loads that are likely to be present in the disposal unit,
including waste disposed above and any overburden and closure cover materials. Consideration
needs to also be given as to whether live loads (i.e., vehicles) will be present at the disposal units.
Disposal units disposing of bulk wastes like contaminated dirt and construction rubble need to
compact the disposal units to minimize subsidence. The practice of compaction as a regular part
of disposal unit operations may also be considered for the disposal of waste in cardboard boxes,
which could degrade in an uncontrolled fashion and contribute to subsidence problems unless they
are dynamically compacted at the time of disposal unit covering.
Section 461
The subrequirement also includes the minimization of void spaces to contribute to the stability of
the site. This applies to both the amount of void spaces within the waste, as well as between the
waste and its packaging if containers are used. The control of void spaces is achieved visually for
containers containing job control waste, for example, as well as being an integral parameter for
wastes prepared using a process control. The use of encapsulation methods, such as grout, may
need to be considered for wastes containing highly-activated components that are likely to remain
hazardous well beyond any foreseeable period of time a waste container is likely to last.
Liquid Wastes. The intention of the free liquid subrequirement (DOE M 435.1-1, Section
IV.G.(1)(d)2.) is for liquid wastes or wastes that contain free liquid to be treated or packaged so
that there is as little liquid remaining as is reasonably achievable. The requirement is also intended
to address liquids that could become free liquids during transportation or which could be released
due to thermal cycling or vibration that occurs during shipment. This can be accomplished
through solidification or stabilization methods, by a dewatering process, or by packaging the
waste with absorbent material. (It is, in fact, good practice to add a small quantity of absorbent
(e.g., a quarter inch) in the bottom of most containers of waste. “Dry” waste is often not
completely dry. Condensation also often occurs. The use of absorbent helps to reduce incidence
of surface contamination and needless problems of appearance should small drops of condensation
leak from a container.) For waste placed into a disposal container, the process or design for
removing or reducing the liquid shall result in free liquid that is no more than 1 percent of the
container volume. For wastes that are processed to a stable form, that is, where the waste form
itself acts as a monolithic form and will be placed into the disposal unit without a container, the
process or method shall result in free liquid that is no more than 0.5 percent of the volume of the
waste form. The volume of the waste form in this case is the final volume following treatment to
the stable form. If a waste is treated through a process that results in a processed, stable form,
but it is also inside a container, then the free liquid requirement for the stable form shall be
followed, that is, there should be no more volume of free liquid than 0.5 percent of the volume of
the stabilized waste inside the container of stable waste.
Chapter IV - Low-Level Waste Requirements
IV-46 DOE G 435.1-1
7-09-99
A challenge is presented in determining compliance with the free liquid requirement because of the
need to minimize or prevent exposures to workers. This would be a concern because one way to
determine compliance would be to randomly examine waste forms and containers to determine the
volume of free liquid. This has been done in the past at some older disposal operations by
puncturing a hole in a container as it is received and measuring the amount of liquid that is
obtained from the package. A better approach is to utilize processes, procedures, or methods
whose results can be assumed appropriate as long as written protocol is followed, or which can be
tested without damaging the waste package, for example, through test runs with surrogate
materials. ANS Standard 55.1 (Ref. 1) is recommended for performing measurements of free
liquids in solidified low-level waste forms and containers.
Section 462
When using a container with absorbent materials, the process and procedure for loading the
container with waste needs to call for introduction of more absorbent by volume than is needed
for the amount of free liquid calculated in the waste, both for a safety factor, and because it is
difficult to calculate exactly how much liquid will be freed during transportation and handling.
Another measure in using absorbents to be considered would be redundancy, such as using two
different kinds of absorbents, or using layering, such as double bagging. For processing waste to
a stable form, or for a dewatering process, the use of test runs to produce samples that could
undergo analysis using non-radioactive surrogate materials to determine optimum processing
parameters that will result in meeting the liquid requirement is recommended. Likewise, the
results of test or actual runs could be used to establish parameters for a subsequent treatment
process when the waste material and feed are the same as a previous successful treatment process,
and the correlation can be justified and verified.
Particular attention needs to be placed on the treatment and packaging of low-level waste to
minimize free liquids for waste streams having a high initial moisture content. Additional
measures could be considered for inclusion in waste acceptance criteria that call for specific
calculations of how much of the interstitial liquid could become free liquid during handling and
transportation, specific testing of absorbent to be used for such waste streams, consideration of
the addition of a certain minimum amount or specification of absorbent, or the required
solidification, stabilization, or additional packaging of waste streams that may be of particular
concern (e.g., high-activity liquids present).
Soils present a particular challenge in regards to the free liquid requirement since many soils have
a high initial moisture content, yet, in many cases the soil will not yield a significant amount of
free liquid. Modifications to the measures discussed need to be considered to provide the needed
information without the expenditure of resources that may be necessary for certain operations
waste that may yield free liquids. For example, the evaluation for determining how much of the
interstitial liquid could become free liquid during handling and transportation could be done on a
set of standard soils from the site, with the results being provided on a generic basis rather than on
a container-by-container basis.
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-47
7-09-99
Nuclear power plants employ a “process control program” to consistently produce products
which are acceptable for disposal and which will meet waste acceptance requirements of receiving
facilities. General guidance and requirements for process control programs can be found in
NRC’s standard review plan for nuclear power plants (NUREG-800) (Ref. 2).
Explosive, Reactive, Pyrophoric, and Degrading Low-Level Waste. The intention of the
explosive, reactive, and pyrophoric subrequirement (DOE M 435.1-1, Section IV.G.(1)(d)3.) is
that wastes containing a material that could react with water or spontaneously detonate or ignite
be treated or packaged so that the chance for this to occur is significantly reduced. This is
accomplished through solidification or stabilization or by packaging methods. The requirement is
not intended to prohibit waste from containing potentially explosive or pyrophoric materials, only
that they be appropriately treated, prepared, and packaged so the chance of ignition or explosion
is significantly reduced.
Section 463
Similarly, the intention of the radiolysis, biodegradation, and toxic subrequirement (DOE M
435.1-1, Section IV.G.(1)(d)4.) is that wastes must not be capable of generating toxins that will
be harmful to workers during operations if a container were to be breached, or which could
contribute to a slow degradation of the stability of the disposal site. The requirement in this case
explicitly states that the waste must not contain any of the gases or vapors to begin with, but it
also states that the waste shall not be capable of generating any from the materials present in the
waste. In this case, just like above, a treatment or packaging method is used to render the waste
incapable of generating the gases or vapors.
Gaseous Low-Level Waste. The gaseous low-level waste subrequirement (DOE M 435.1-1,
Section IV.G.(1)(d)5.) is intended to protect workers and the long-term stability of the site by
specifying the maximum pressure at which gaseous radioactive waste is to be packaged. The
requirement is also intended to apply to the situation where gases are generated within the waste
packages following closure of the package. An analysis may need to be conducted on any waste
materials that could potentially generate gases due to conditions of storage or treatment to ensure
that the pressure stated in the requirement will not be exceeded. The analysis needs to also
include the potential for any conditions inherent in the waste and/or waste form that could cause
gas generation. For example, spent ion exchange resins could generate hydrogen gas while in
storage due to radiolysis.
Compliance with the waste acceptance requirements for low-level waste disposal facilities is
demonstrated if they contain these minimum disposal facility requirements, or equivalent.
Chapter IV - Low-Level Waste Requirements
IV-48 DOE G 435.1-1
7-09-99
Supplemental References:
1. ANS, 1979. American National Standard for Solid Radioactive Waste Processing System
for Light Water Cooled Reactor Plants, ANS 55.1, American Nuclear Society, La Grange
Park, IL, 1979.
2. NRC, 1981. Standard Review Plan for Nuclear Power Reactors, NUREG-0800, U.S.
Nuclear Regulatory Commission, Washington D.C., 1981.
IV. G.(1) Technical and Administrative.
(e) The basis, procedures, and levels of authority required for
granting exceptions to the waste acceptance requirements,
which shall be contained in each facility’s waste acceptance
documentation. Each exception request shall be documented,
including its disposition as approved or not approved.
Objective:
The objective of this requirement is to ensure that formal procedures exist and a decision process
is clear concerning the granting of exceptions to waste acceptance requirements.
Discussion:
Waste acceptance requirements are established to ensure that facilities can safely manage waste
received for storage, treatment, or disposal, and is particularly critical for disposal facilities in
assuring the long-term performance will be maintained. Thus, exceptions or deviations to
acceptance criteria cannot be routine and must be carefully reviewed and documented, especially
to provide for the permanent record of waste disposed. The procedures for granting exceptions
needs to clearly state the entire process for requesting an exception, describe acceptable bases for
granting exceptions, and identify any additional information that is needed to supplement the
documentation normally provided for waste transfers. The approval process needs to be clearly
spelled out so the generator can conduct the request appropriately.
Section 464
Example: The waste acceptance requirements for a low-level waste storage facility
specifies three acceptable containers that can be received at the facility. It also includes
a procedure for obtaining an exception to the waste acceptance criteria concerning
containers only. (The requirements specifically state that no other exceptions will be
granted). The procedure for the container exceptions includes minimum information
about any containers other than the three pre-approved that must be submitted, who it is
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-49
7-09-99
to be submitted to, and the criteria that will be used to determine if the container may be
found acceptable as an exception.
Waste acceptance requirements are acceptable if they are documented and contain a clear
description of the procedure and bases obtaining for an exception or deviation to the acceptance
criteria for low-level waste to be received at the facility.
Supplemental References: None.
IV. G.(2) Evaluation and Acceptance. The receiving facility shall evaluate
waste for acceptance, including confirmation that the technical and
administrative requirements have been met. A process for the
disposition of non-conforming wastes shall be established.
Objective:
The objective of this requirement is to establish a process by which personnel at a facility
receiving low-level waste for storage, treatment, or disposal determine that the waste being
transferred is acceptable in accordance with the waste acceptance requirements and for that
process to specifically address the management of waste that does not conform with all of the
requirements when it is received at the facility.
Discussion:
This requirement makes it the responsibility of officials at a facility to which waste is transferred
to confirm that waste is in compliance with the established waste acceptance requirements and
also provides a mechanism by which the officials confirm that waste can be accepted and safely
managed.
Evaluation and Acceptance. The methodology for implementation of this requirement needs to be
flexible and defined on a facility-specific basis. The complete process and procedures, including
the responsibilities of the generating facility, need to be clearly documented so that both the
generator and the facility receiving the waste understand the process that will be used. As with
implementation of other parts of DOE M 435.1-1, this requirement is implemented using the
graded approach process. Facilities receiving low-level wastes from many generators, offsite
generators, or high activity low-level wastes, may need to implement more detailed waste
evaluation and acceptance processes than a facility receiving waste from a small number of onsite
generators.
Chapter IV - Low-Level Waste Requirements
IV-50 DOE G 435.1-1
7-09-99
The evaluation and confirmation process consists of one or more of the following approaches, and
is designed to demonstrate that the waste presented meets the waste acceptance requirements of
the facility receiving waste for storage, treatment, or disposal:
C Testing, sampling, and analysis of the contents of a representative sample of waste
packages as they are received at the facility;
C Testing and analysis of a number of samples taken by the generator facility;
C Detailed review of sampling and analysis data generated by the sending facility or
an independent laboratory employed by the generating facility;
Section 465
C Audit, surveillance, or observation of the sender’s waste characterization activities
and processes and waste certification programs.
Testing, sampling, and analysis of the contents of a representative sample of waste packages upon
receipt is complicated by the fact that additional risk is posed if a technique such as opening of
drums and obtaining grab samples is used. Therefore, consideration needs to be given to
implementing non-destructive examination technologies if receipt sampling and analysis is the
preferred approach. Likewise, analysis of samples taken at the generator’s site may involve
additional risk, and also may be expensive to implement. If this method is employed, samples
which are representative, either statistically or correlated with generator profiles, need to be
obtained for analysis to ensure this method is effective. This sampling would include packages
from the generators sending the largest volumes of waste to the facility or packages containing
the critical radionuclides as identified in the waste acceptance requirements.
The use of a detailed review of the sampling and analysis data gathered by others would include
an evaluation of the methodologies used for collecting the sample, maintaining the integrity of the
sample and data (e.g., through a chain of custody), and performing the radioanalyses. As above,
the samples collected would need to be representative of the waste, either statistically or with a
bias towards large generators or generators of significant radionuclides (i.e., those that are most
limiting for the storage, treatment, or disposal facility).
The use of assessments audits, reviews or surveillances to verify compliance of the waste
generators certification programs with acceptance requirements would need to be conducted on a
schedule commensurate with the frequency of waste generation and shipments. The
documentation of the verification process would include organization and authorities; frequency
of assessments; methods to be employed; the information that will be documented as a result; and
the qualifications of personnel.
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-51
7-09-99
Example: The waste acceptance process for Storage Building B on the Western
Site, which receives waste from multiple generators involves assay to confirm
transuranic waste and to segregate transuranic and low-level waste, and sample
collection and analysis to confirm the RCRA status of waste. The process calls
for assaying and sampling one waste package of every 25 from established waste
streams and one of every 5 for new waste streams of for waste from generators
who have a history of poor compliance with the waste acceptance criteria.
Discussions contained in Methods for Verifying Compliance with Low-Level Radioactive Waste
Acceptance Criteria (Reference 2), provide additional guidance for evaluation and acceptance of
waste at receiving facilities.
Non-Conforming Low-Level Waste. Facilities receiving low-level waste for storage, treatment or
disposal need to have a documented process to be used in the event a non-conforming waste is
received. A non-conforming waste is a waste container or shipment which is certified by the
generator as meeting the waste acceptance requirements of the receiving facility but which is
found to be in violation of the acceptance requirements during the receiving facility’s waste
receipt and acceptance process. Facility procedures need to address how non-conforming waste
will be segregated from acceptable waste, the process for notifying the sender of the
non-conformance, and the acceptable methods for dispositioning the non-conforming waste. The
process includes prior notice to the sender of the actions to be taken by the facility receiving the
waste and the sender’s obligations, particularly regarding the cost of the actions, to support the
disposition of the non-conforming waste.
Section 466
Example: A low-level waste storage facility’s waste acceptance process includes
returning non-conforming waste to the generator under all circumstances, billed to the
generator. The paperwork/certifications for waste return is included in the paperwork
accompanying all packages to facilitate return of packages.
Compliance with the waste acceptance requirements for a low-level waste management facility is
demonstrated if they include a process for evaluation and acceptance of incoming waste to ensure
the acceptance criteria of the facility receiving the waste are met that includes one of or a
combination of: (1) testing, sampling, and analysis of representative samples of waste upon
receipt; (2) testing, sampling, and analysis of split samples of waste taken at the generator site; (3)
evaluation of testing, sampling, and analysis of data provided by the generator, or (4) audits,
reviews, surveillance, or observations of generator waste certification programs and
characterization activities. Additionally, acceptable waste acceptance requirements for a storage,
treatment or disposal facility will have documented procedures and actions to be taken if a waste
that does not conform to the waste acceptance criteria is received at the facility.
Chapter IV - Low-Level Waste Requirements
IV-52 DOE G 435.1-1
7-09-99
Supplemental References:
1. DOE, 1997. Nevada Test Site Waste Acceptance Criteria (NTSWAC), Revision 1, U.S.
Department of Energy, Nevada Operations Office, Las Vegas, NV, August 1997.
2. DOE, 1993. Methods for Verifying Compliance with Low-Level Radioactive Waste
Acceptance Criteria, DOE-LLW-185, U.S. Department of Energy, National Low-level
Waste Management Program, Idaho Falls, ID, September 1993.
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-53
7-09-99
IV. H. Waste Generation Planning.
The following requirements are in addition to those in Chapter I of this Manual.
(1) Life-Cycle Planning. Prior to waste generation, planning shall be performed
to address the entire life cycle for all low-level waste streams.
Objective:
The objective of this requirement is to provide for the disposal of all low-level waste that is
generated in the future by ensuring that prior to generating a new low-level waste stream, the
specific waste management facilities necessary for safe management of the waste from the time it
is generated up to and including its disposal are identified and sites are discouraged from
generating low-level waste that does not have an identified path to disposal.
Discussion:
The Complex-Wide Review of DOE Low-Level Waste ES&H Vulnerabilities conducted in
response to Defense Nuclear Facilities Safety Board Recommendation 94-2 identified storage of
low-level waste with no identified path forward to disposal as a major complex-wide vulnerability.
The safety and hazards analysis conducted as part of the preparation of DOE O 435.1 also
identified significant weaknesses and risks associated with low-level wastes being generated
without a path to disposal, particularly weaknesses associated with long-term storage of waste
and potential loss of characterization data from generators and the subsequent need for
recharacterization. Therefore, as part of the generator planning requirements in General
Requirement I.2.F.(7), specific requirements are identified for planning for management of waste
prior to its generation, and for approval to generate low-level waste streams with no path forward
to disposal.
Life cycle planning for all low-level waste. The Site-Wide Waste Management Program required
in Chapter I of DOE M 435.1-1, Section I.2.F.(1), calls for systematic planning of the
management of all radioactive waste at DOE sites. Guidance on the Site-Wide Waste
Management Program discusses information to be included in life-cycle planning documentation
for all low-level waste streams at the site.
Section 467
However, additional information is required of certain low-level wastes to ensure full life cycle
planning is being done for all waste. The additional information needed for certain waste streams
is influenced by the fact that, on the implementation date of the Order, the low-level waste will be
in one of three stages of its life-cycle: (1) waste generated in the past (in storage), (2) waste being
generated at present; and (3) wastes not yet generated (future wastes); and will either have an
identified path to disposal, or will not.
Chapter IV - Low-Level Waste Requirements
IV-54 DOE G 435.1-1
7-09-99
Therefore, from a waste generation planning perspective, there are six different “states” of low-
level waste, depending on when the waste was or is generated and whether it has or will have a
path to disposal. The following paragraphs explain the recommended life cycle information for
these different low-level wastes.
Low-Level Waste With a Path to Disposal
Generated currently - The life-cycle information for low-level waste that is currently
generated with an identified path to disposal includes a description of the management
steps for the waste as discussed in guidance for the Site-Wide Radioactive Waste
Management Program.
Generated in the future (from a new process) - The life-cycle information for low-level
waste with an identified path to disposal that is generated from a new process includes a
description of the management steps for the waste as discussed in guidance for the Site-
Wide Radioactive Waste Management Program.
Generated in the past (in storage) - In addition to the basic information on management
steps, life cycle information for low-level waste with a path to disposal that is in storage
(due to budget constraints, delays due to regulatory matters or management decisions, or
for other reasons) includes a schedule for achieving disposal.
Low-Level Waste Without a Path to Disposal
Generated in the past (in storage) - The life-cycle information for low-level waste in
storage as of the issuance of DOE O 435.1 for which there is not an identified path to
disposal includes the basic information on the management steps for the waste which can
be identified, a discussion of the issues that hinder disposal of the waste, and the plans and
schedule for achieving resolution of the issues.
Generated in the future (from a new process) - The life-cycle information for low-level
waste without an identified path generated from a new process to disposal includes the
basic information on the management steps for the waste which can be identified, a
discussion of the issues that hinder disposal of the waste, and the plans and schedule for
achieving resolution of the issues. This information will be assembled in the course of
getting the generation of this waste approved in accordance with the process required in
DOE M 435.1-1, Section I.2.F.(19), and which is discussed in the next section of this
guidance.
Generated currently - The life-cycle information for low-level waste without an
identified path to disposal includes the basic information on the management steps for the
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-55
7-09-99
Section 468
waste which can be identified, and a discussion of the issues that hinder disposal of the
waste and the plans and schedule for achieving resolution of the issues. These waste
streams are not expected to receive approval for generation in accordance with General
Requirement I.2.F.(19). However, the life-cycle planning information needs to address the
continued generation of this waste. The life-cycle planning information for continuing to
generate a no path forward waste needs to include consideration of the necessity to
generate the waste, an understanding of what prevents the disposal of the waste, the
needed capacity and capabilities for continued storage of the waste, and the plans for
future disposal of the waste. Discussions would also be included on any alternatives to the
process that generates the no path forward waste that have been considered.
Providing the life cycle information discussed above for waste streams already being generated is
relatively straightforward. Essentially for most low-level waste, the information already exists and
has been utilized for other planning documents such as the Programmatic Environmental Impact
Statement. [Low-Level Waste Baseline Disposition Maps contain much of the information
necessary to satisfy the planning requirements discussed here. An example Disposition Map is
included as Figure IV.H.1 at the back of this section of guidance.]
Example 1: A low-level waste generating facility operating at Site A continues to operate
with no alterations. The facility generates the same low-level waste streams it has been
generating for years, and none of them are waste streams without a path forward to
disposal. The life-cycle information about low-level waste generated at this facility is
included in the current waste inventories and capacities section of the Site A Radioactive
Waste Management Plan, and no technical or programmatic issues are included in the
Plan concerning these waste streams.
Example 2: The same Site A as Example 1 has three waste streams with a path to
disposal that have been in Storage Building 200 for two years. These wastes are also
included in the current waste inventories and capacities section of the documentation of
the Site A Radioactive Waste Management Plan. Also, the issues (one waste contains
PCBs but is not approved for shipment to the TSCA incinerator, the other two wastes
require special shipping casks which have not been approved) that prevent their disposal
are explained in the issues for path forward waste in storage section of the Site A
Radioactive Waste Management Plan, along with discussions of steps toward their
resolution (e.g., the special shipping cask approval is expected January 2000).
Example 3: The disposal facility planned to receive the three wastes discussed in
Example 2 is suddenly closed. The three wastes are now without a path to disposal. The
next time the Site A Plan is updated, they are still included in the current waste
inventories and capacities section, and a determination to move the three wastes from
Building 200 to Building 400 in 2003 is described. A new section of the Plan is written
Chapter IV - Low-Level Waste Requirements
IV-56 DOE G 435.1-1
7-09-99
for issues for no path forward waste in storage, which describes the issues of PCBs and
special casks, but also includes the loss of disposal capacity. Also discussed is the use of
the special cask, once it is approved, to act as a high integrity storage container. Plans
are also described for determining alternate disposal locations, to be completed in July
2002.
Section 469
To provide waste management steps for waste streams that have not been generated yet, it would
likely be inappropriate to assume that the same management steps will be taken as some already
generated waste. Instead, some investigations of appropriate management steps may be necessary
to provide adequate life cycle planning information. The bulk of these generator planning
requirements and the rest of this guidance address planning for new waste streams.
Waste generator planning prior to generation. Planning, prior to generating low-level waste
(subrequirement H.(1)), is intended to address low-level waste streams that do not already exist.
Low-level waste streams that are first generated after issuance of the Order are subject to this
requirement. Waste generator planning is a component of the waste generator program required
in I.2.F.(7) of the General Requirements Chapter of DOE M 435.1-1. Waste generator planning
activities need to be integrated in the generator program with waste characterization, certification,
and transfer activities.
Generator planning prior to generation addresses the life-cycle of the waste to disposal, including
the interim steps of waste management. This can be accomplished by preparing a waste stream
profile and reviewing it with the facility(ies) that will need to manage the waste. The waste
stream profile format used needs to be consistent with the needs of the storage, treatment, and/or
disposal facility that will be involved in managing the waste stream. An example of a waste
stream profile form derived from the Nevada Test Site Waste Acceptance Criteria (NTSWAC) is
included at the back of this guidance as Figure IV.H.2. The waste generator confirms with
potential storage, treatment, and disposal facilities that the waste stream can be managed
appropriately based on the facility’s current waste stream characteristics and the planned facility
capacity. So conceivably, a generator may need to contact multiple facilities (e.g., a storage
and/or treatment facility in addition to the disposal facility) to ensure proper waste management.
Example 1: A previously operating high-level waste treatment facility that generates a
low-level waste stream has been shut down for eighteen months and is scheduled to
restart operations six months after DOE O 435.1 is issued. Low-level waste generation
planning is performed. The planning determines that the previous disposal option for the
low-level waste is not available, but an alternative disposal location is easily arranged.
Therefore, the planning provides early warning of a potential problem which is resolved
prior to the generation of the waste.
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-57
7-09-99
Example 2: Waste stream ARL-111 is a new mixed low-level waste stream to be
generated from a process at Laboratory X. The waste stream is similar to another waste
stream that has been generated for some time, and which receives treatment at the mixed
waste incinerator facility Y, and the residues are disposed at the Low-Level Waste
Disposal Facility. A Laboratory X waste profile is prepared and transmitted to both the
Y incinerator and the disposal facility. After discussions, it is verified that the new waste
stream can be managed at the two facilities.
Section 470
The determination of whether a low-level waste stream has an identified path to disposal is based
on the availability of existing or planned facilities and operations and on the technical capability of
managing the waste at the facility. A planned facility is considered to be available if it has been
authorized (e.g., a line item in a Congressional appropriation or equivalent approval for design
and construction). A facility is not considered available if it is not authorized to accept or manage
a particular waste type or concentration. If a planned facility is designated in the planning
information, then the planning information also needs to address the schedule for when the facility
will be operational, and the appropriate management steps that will be taken for waste designated
for that facility until it becomes operational.
For purposes of planning for disposal of a low-level waste stream, a facility or capabilities that are
part of a program or strategic plan, but have not been authorized are not considered available. If
an available planned facility is canceled, the generator site needs to revise the planning for the life-
cycle of the low-level waste, an alternate path to disposal needs to be identified and documented,
and approval to generate the low-level waste needs to be obtained from the cognizant Field
Element Manager as required in the General Requirements at I.2.F(19).
Example 1: Site X generates a low-level waste with concentrations of uranium that are
too high to be suitable for on-site disposal. A new disposal cell for high-activity long-
lived radionuclides will be developed at another site. The new facility has been
authorized by Congress as a line item and will be operational by 2006. Since this is the
only facility that may be able to dispose of this waste, Site X reflects the assumption to
use the new facility by 2007, subject to operation and certification, since they have no
other path forward for disposal.
Example 2: As in the above example, Site X generates a high-activity long-lived waste
stream that cannot be disposed on site. An existing disposal operation at another site is
technically capable of disposing this waste. The facility, however, has not completed the
necessary analyses under NEPA to be able to accept waste from off site. Until the
necessary NEPA analyses have been completed, the disposal facility is not available to
Site X.
Chapter IV - Low-Level Waste Requirements
IV-58 DOE G 435.1-1
7-09-99
Whether a path to disposal can be identified is also based on the acceptability of the waste at the
facilities at which it must be managed. For existing facilities, this involves no more than an
evaluation of the waste stream properties against the waste acceptance requirements of the facility
and determining there are no impediments for its management. For planned facilities, this
determination is more involved. For some waste streams, the acceptability at a planned facility
could be determined based on similar circumstances already known to exist in the Complex. This
may be a common situation for wastes that do not have a full path to disposal because of issues
that are not entirely technical (e.g., commercially generated [NRC licensed] Greater-than-Class-C
low-level waste). For other waste streams, particularly those with a technical impediment to
disposal, the acceptability may need to be evaluated and a judgement made that a planned facility
will be able to accept the waste provided some necessary treatment is performed (e.g., low-level
waste approved to go to a disposal facility but which is waiting for a final PEIS decision), or some
administrative step is successfully accomplished (e.g., a RCRA permit is obtained so that mixed
waste can be accepted).
Section 471
The generator is responsible for ensuring that low-level waste is not generated unless there is due
consideration for the ultimate disposal of the waste. The objective of this requirement is not to
prohibit, under all conditions, the generation of low-level waste that does not have an identified,
achievable path to disposal. In meeting the DOE O 435.1 planning requirements, it is appropriate
for waste management organizations to provide assistance to the generator in determining the
waste management path, particularly in cases where the waste management organization may
utilize offsite treatment, storage, or disposal facilities.
Compliance with this planning requirement is demonstrated by the individual sites establishing a
process for evaluating the life-cycle of low-level waste prior to its generation, including the
identification of low-level wastes with no path to disposal and appropriate records justifying the
newly generated low-level waste stream(s), and site personnel possessing planning information
showing the location(s) where low-level waste will be stored, treated, and/or disposed along with
a confirmation that the personnel managing the facilities agree that the low-level waste may be
managed at those facilities.
Supplemental References:
1. DOE, 1997. Nevada Test Site Waste Acceptance Criteria (NTSWAC), Revision 1, U.S.
Department of Energy, Nevada Operations Office, Las Vegas, NV, August 1997.
IV. H.(2) Waste With No Identified Path to Disposal. Low-level waste streams
with no identified path to disposal shall be generated only in
accordance with approved conditions which, at a minimum, shall
address:
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-59
7-09-99
(a) Programmatic need to generate the waste;
(b) Characteristics and issues preventing the disposal of the waste;
(c) Safe storage of the waste until disposal can be achieved; and
(d) Activities and plans for achieving final disposal of the waste.
Objective:
The objective of this requirement is to ensure that prior to generation of a new low-level waste
stream with no path to disposal, the need to generate the waste is carefully considered, and plans
for safe long-term storage and for resolving issues that prevent disposal of the wastes are
developed.
Discussion: There are instances where programmatic needs may necessitate the generation of
low-level waste without an identified path to disposal. In these instances, the Field Element
Manager must ensure development of a process for identifying generation of low-level waste with
no path to disposal and approving the conditions under which such low-level waste can be
generated (see Section I.2.F.(19)). The process of identifying waste with no path to disposal and
establishing conditions for its generation is intended to raise to the attention of DOE management
that a commitment is being made with the generation of such a waste, including prolonged storage
of this waste and resolving those issues that prevent the waste from being disposed.
Example: Through generation planning it is discovered that a proposed project to
remediate an old glove box facility would generate some low-level waste streams that
would most likely not have a path to disposal using existing facilities. The Field Element
Manager determines that generating low-level waste streams with no path to disposal is
not worth the benefit of proceeding as planned with the project. Cleanup strategies and
schedules are changed that allow the project to commence and avoids generating the no
path forward waste while determinations are made on disposal options.
Section 472
The minimum conditions for generating a waste without an identified path to disposal are
identified in this requirement. They include evaluations and considerations that involve both the
waste generating and waste management organizations. The decision to proceed with the activity
generating the waste is made considering the total situation based on these minimum
considerations.
Programmatic need to generate the waste. There must be a clear identification of the
programmatic mission being served that results in the generation of low-level waste with no
Chapter IV - Low-Level Waste Requirements
IV-60 DOE G 435.1-1
7-09-99
identified path to disposal. Alternate means of accomplishing the mission without generating the
waste should be discussed. These could include use of alternative materials to achieve the
mission, use of different processes, or substitution of chemicals other than the ones originally to
be used.
Characteristics and issues preventing the disposal of the waste. The reasons that the low-level
waste cannot be disposed of must be identified. These may be technical or programmatic reasons.
For example, if a waste needs to be treated in order to meet a disposal facility waste acceptance
criteria and an appropriate treatment facility is not available, the lack of treatment would be
identified as the reason the waste does not have a path to disposal. Identifying the characteristics
and issues preventing disposal is necessary to support the development of plans for achieving
disposal.
Safe storage of the waste until disposal can be achieved. Since the waste cannot be disposed of
pending the resolution of programmatic or technical issues, facilities must be available for safe
storage. In order to evaluate the ability to provide for the storage of the waste, there needs to be
an estimate of the amount of the waste that will be generated, as well as an estimate of the time
necessary to keep the waste in storage. Identification of the requirements for safe storage and
acceptable storage facilities is a prerequisite to generating the waste so that unique or risky
aspects of storage that may make long-term storage problematic can be identified.
Activities and plans for achieving final disposal of the waste. The decision to generate waste with
no identified path to disposal must be based on a plan to eventually achieve disposal. The plan to
achieve disposal of the waste needs to identify the activities being pursued to resolve issues
preventing disposal and a schedule for their resolution. The activities described may be fairly
detailed if the problems are technical and involve only one waste stream at a site. In other cases
involving more programmatic issues, or which involve several waste streams at several sites, the
activities and schedules to resolve issues may be less certain because they are dependent on other
internal or external organizations (for example, approval of another Field Element Manager to
ship waste).
Consideration might be given to delaying the generation of a waste stream for which there is no
reasonable alternative to generating the no path forward waste if there are difficult problems that
must be overcome to achieve safe storage or final disposal.
For many of the wastes that are currently without an identified path to disposal, programmatic
and/or complex-wide problems and issues contribute to the lack of final disposal. Thus, all or part
of the solution to an individual problem low-level waste stream may be programmatic or complex-
wide steps taken as part of the Site-Wide Radioactive and/or Complex-Wide Low-Level Waste
Management Programs that will address the vulnerabilities associated with no path forward waste
Section 473
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-61
7-09-99
and lead to resolution of issues and disposal of the waste. This process is also discussed in several
places in the General Requirements guidance.
Satisfaction of this planning requirement can be demonstrated by the waste generation
organization having documentation concerning the decision to generate a low-level waste stream
that does not have an identified path to disposal. This documentation needs to include the
cognizant Field Element Manager or designee approval to generate the waste, an explanation of
the need for the process that generates the low-level waste, a discussion of the reason it cannot be
disposed of, the proposed management plan for the waste, and an up-to-date schedule of activities
being pursued to resolve constraints to the disposal of the subject waste.
Supplemental References:
1. DOE, 1997. Nevada Test Site Waste Acceptance Criteria (NTSWAC), Revision 1, U.S.
Department of Energy, Nevada Operations Office, Las Vegas, NV, August 1997.
Chapter IV - Low-Level Waste Requirements
IV-62 DOE G 435.1-1
7-09-99
F
ig
ur
e
IV
.H
.1
.
E
xa
m
pl
e
L
ow
-L
ev
el
W
as
te
D
is
po
si
ti
on
M
ap
Chapter IV - Low-Level Waste Requirements
_______________________________________________________________________________________
_______________________________________________________________________________________
DOE G 435.1-1 IV-63
7-09-99
Figure IV.H.2. EXAMPLE WASTE PROFILE FORM (FOR GENERATION
PLANNING)
A. Generator Information
1. Waste Certification Official _______________ Phone _______________ FAX ____________
2. Technical ____________________________ Phone _______________ FAX ____________
3. DOE Contact _________________________ Phone _______________ FAX ____________
4. Facility Name ________________________________________________________________________
Address__________________________________________________________________________
City ________________________________ ZIP ___________
5. EPA Identification Number __________
B. General Waste Stream Information
1. Waste Stream Identification Number _____________________________________________________
Profile Revisions Number ________________________ Profile Revision Date _________________
2. Waste Description
3. Waste Category Mixed Low-Level
4. Generating Process Description _________________________________________________________
Yes No
Yes No
One Time Only m3
State _______________
Low-Level
Process Description continuation Page Attached
Flow Diagram Attached
5. Estimated Rate of Generation
Ongoing m3/yr
C. Physical Properties
1. Waste Form Description
Solid Solidified
Sealed Absorbed
Sources Liquid
Encapsulated
Other
Sludge Powder/Dust
________________________________
2. List waste stream components Estimated Percent by Volume Weight
Chapter IV - Low-Level Waste Requirements
IV-64 DOE G 435.1-1
7-09-99
Estimated Density (kg/m3)
_______________________________ __________ to __________ ___________________________
_______________________________ __________ to __________ ___________________________
_______________________________ __________ to __________ ___________________________
_______________________________ __________ to __________ ___________________________
_______________________________ __________ to __________
_______________________________ __________ to __________
Component Continuation Page Attached Yes No
Section 474
3. Does the waste contain the following?
Yes No Free Liquids
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
Yes
Yes
Pyrophorics
Yes
Regulated Asbestos-Containing Material
Yes No Radioactive Animal Carcasses
Yes No DOE Equivalent Greater-Than-Class C Packages
Yes No Other
___________________________
___________________________
Particulates
Gases
Etiologic Agents
Chelating Agents
Polychlorinated Biphenyls
No Explosives
No
No
Chapter IV - Low-Level Waste Requirements
_______________________________________________________________
DOE G 435.1-1 IV-65
7-09-99
D. RCRA Characterization
1. RCRA Characterization by Process Knowledge Sampling and Analysis Both
2. Does the waste exhibit any characteristic of hazardous waste as defined in 40 CFR Part 261?
Yes No Ignitability
Yes
No Corrosivity
Yes
No Reactivity
Yes
No Toxicity
3. Yes
Has the waste been treated?
(mg/L)
No (Statistical Mean)
________
________
________
No Is the waste listed as defined in 40 CFR Part 261?
4. Yes No Is the waste hazardous per state-of-generation regulations?
State of generation
5. Yes No
6. If sampling and analysis was used for RCRA characterization, complete applicable portions of summary
table below. If analytical results are available for additional hazardous constituents, attach an equivalent
summary table.
Exceeds
Sample Regulatory
Known or Analysis Detection Limit Level?
Expected? Confidence Interval (mg/L) Yes No
Yes
TCLP Metals:
Arsenic _______ to _______ _________
Barium _______ to _______ _________
Cadmium _______ to _______ _________
Chromium ________ _______ to _______ _________
Lead ________ _______ to _______ _________
Mercury ________ _______ to _______ _________
Selenium ________ _______ to _______ _________
Silver ________ _______ to _______ _________
Chapter IV - Low-Level Waste Requirements
________ _________
________ _________
________
________
________
________
________ _________
________ _________
________ _________
_________
_________
_________
_________
________ _________
________ _________
________ _________
________ _________
________ _________
________ _________
IV-66
_________
_________
_________
_______ to _______ _________
_______ to _______
_______ to _______
_______ to _______
________ _______ to _______
________ _______ to _______
________ _______ to _______
________
TCLP Volatiles:
Benzene
Carbon
Tetrachloride
Chlorobenzene
Chloroform
1,4-Dichloro
benzene
1,2-Dichloro
ethane
1,1-Dichloro
ethylene
Methyl ethyl
ketone
Pyridine
Tetrachloroethylene
Trichloroethylene
Vinyl chloride
TCLP Semivolatiles:
0-Cresol
M-Cresol
p-Cresol
Cresol
2,4-Dinitrotoluene
Hexachlorobenzene
Hexachlorobutadiene
DOE G 435.1-1
7-09-99
Exceeds
Sample Regulatory
Known or Analysis Detection Limit Level?
Expected? (mg/L) Confidence Interval (mg/L) Yes No
Yes No (Statistical Mean)
_______ to _______
_______ to _______
_______ to _______
_______ to _______
_______ to _______
_______ to _______
_______ to _______
_______ to _______
_______ to _______
_______ to _______
_______ to _______
_______ to _______
Chapter IV - Low-Level Waste Requirements
________ _________
________ _________
________
________
________
________
________ _________
________ _________
________ _________
_________
_________
_________
_________
DOE G 435.1-1 IV-67
7-09-99
Sample
Known or Analysis
Expected?
Yes No
Hexachloroethane
Nitrobenzene
Section 475
Pentachlorophenol
2,4,5-Trichloro
phenol
2,4,6-Trichloro
phenol
TCLP Pesticides
and Herbicides:
Chlordante
2,4-D
Endrin
Heptachlor
(And its hydroxide)
Lindane
Methoxychlor
Toxaphene
2,4,5-TP(Silver)
E.
Direct Measurement
Exceeds
Regulatory
Detection Limit Level?
(mg/L) Confidence Interval (mg/L) Yes No
(Statistical Mean)
_________
_________
_________
_______ to _______ _________
_______ to _______
_______ to _______
_______ to _______
________ _______ to _______
________ _______ to _______
________ _______ to _______
________
Radiological Properties
1. Radiological Characterization by (Check all that apply)
Process Knowledge
_______ to _______
_______ to _______
_______ to _______
_______ to _______
_______ to _______
_______ to _______
Sampling & Analysis Materials Control & Accountability
Gross Radiation Measurement Other _______________
2. Were the following used in radiological characterization ? Scaling Factors Ratios
Chapter IV - Low-Level Waste Requirements
_________________________ __________________
_________________________ __________________
_________________________ __________________
_________________________ __________________
_________________________ __________________
_________________________ __________________
_________________________ __________________
_________________________ __________________
_________________________ __________________
_________________________ __________________
_________________________ __________________
________________________ __________________
________________________ __________________
_________________________ __________________
_________________________ __________________
_________________________ __________________
IV-68 DOE G 435.1-1
7-09-99
3. List reportable radionuclides.
Radionuclide
Activity Range
(BQ/m3)
Activity Repre-
sentative of Final
Waste Form
(Bq/m3)
4. Yes No
Transuranic Nuclides
__________________ to __________________
__________________ to __________________
__________________ to __________________
__________________ to __________________
__________________ to __________________
__________________ to __________________
__________________ to __________________
__________________ to __________________
__________________ to __________________
__________________ to __________________
__________________ to __________________
Does the waste contain transuranic waste creating nuclides?
Activity Range
(nCi/g)
__________________ to _________________
__________________ to _________________
__________________ to _________________
__________________ to _________________
__________________ to _________________
Activity Repre-
sentative of Final
Waste Form
(nCi/g)
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1
7-09-99
IV-69
5. Yes No Is enriched uranium present? If yes, provide enrichment of U-253 by weight
percent _________. Provide Maximum mass U-235 per package __________
g/package. Reference controlling documents.
No are other fissionable nuclides present? If yes, list below.
Nuclide Maximum Activity Concentration (Bg/m3)
F. Packaging Description
6. Yes
1. Container type(s)
DOT Specification(s) ______________________________________________________________
Yes No N/A Does container meet 3,375 lb/ft2 strength test?
2. Standard container external dimensions
Packaged bulk external dimensions
3. Weight Range kg to
4. Yes No Waste stream includes unclassified material.
Section 476
5. Yes No Waste stream includes classified material.
6. Yes No Estimated radiation dose rate at disposal package surface.
to mSv/h, at 1 mwrwe to mSv/h.
G. Generator Signature
To the best of my knowledge, the information in this document and attachments is true and accurate.
Preparer's Printed Name Signature Date
Waste Certification Official's Printed Name Signature Date
U.S. Department of Energy Signature Date
Chapter IV - Low-Level Waste Requirements
IV-70 DOE G 435.1-1
7-09-99
IV. I. Waste Characterization.
Low-level waste shall be characterized using direct or indirect methods, and the
characterization documented in sufficient detail to ensure safe management and
compliance with the waste acceptance requirements of the facility receiving the
waste.
Objective:
The objective of this requirement is to ensure that sufficient knowledge of low-level waste’s
characteristics (e.g., chemical, physical, radiological) is available to protect workers handling the
waste and to support effective decision-making for its management. This information is to be
maintained from generation, through storage and treatment in sufficient detail to ensure that the
requirements of subsequent treatment and storage facilities, transportation regulations, and the
disposal requirements for low-level waste will be met.
Discussion:
The Radioactive Waste Management Manual assigns the Field Element Manager the
responsibility of ensuring development, approval, and implementation of a program that addresses
the responsibilities of waste generators, including waste characterization (DOE M 435.1-1,
Section I.2.F.(7)). The characterization data acquired during generation, storage, and after
treatment of low-level waste need to be reliable and in sufficient detail to ensure subsequent
management can be conducted safely and to meet the waste acceptance requirements of all
subsequent receiving facilities. Accurate characterization of low-level waste is essential to: 1)
waste planning by generators, as required by DOE M 435.1-1, Section IV.H; 2) waste
certification by generators and other senders of waste, as required by DOE M 435.1-1, Section
IV.J; 3) waste transfers by generators and other senders of waste, as required by DOE M 435.1
Section IV.K; and; 4) waste evaluation and acceptance by receivers of waste, as required by DOE
M 435.1-1, Section IV.G.
In conducting the analyses for development of the DOE M 435.1-1, characterization was
identified as necessary to ensuring the safe management of waste from generation through
disposal. Waste characterization is defined (DOE M 435.1-1, Attachment 2) as:
“The identification of waste composition and properties, such as by review of acceptable
knowledge (which includes process knowledge), or by nondestructive examination,
nondestructive assay, or sampling and analysis, to comply with applicable storage,
treatment, handling, transportation, and disposal requirements.”
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-71
7-09-99
Accurate waste characterization is necessary so that the waste and waste containers are
compatible and worker handling of waste containers can be performed safely. All information
necessary for personnel to safely handle a container of low-level waste needs to be known at all
times during the life-cycle of the waste.
Section 477
Waste characterization is a tool for gathering information that supports defensible decisions
regarding safety, process, environmental and compliance matters in the management of low-level
waste. The significance of the waste management decision will guide the graded application of
this requirement, as well as the more detailed characterization requirements addressed in
subsequent sections of this guidance. These subsequent sections address application of a data
quality objectives process to guide characterization (Section IV.I.(1)) and minimum
characterization requirements (Section IV.I.(2)).
Use of Direct and Indirect Methods. Waste managers are to characterize low-level waste using
an appropriate combination of direct and indirect methods. The appropriate method for
characterizing waste depends on the parameter being measured, the hazards associated with
acquiring the information, and the amount and quality of the data needed as determined through a
data quality objectives or similar process.
Direct methods of characterizing waste can be used to established certain physical and chemical
attributes as well as radiological characteristics. The most common direct methods for
characterizing the chemical and/or radiological characteristics are sampling and laboratory
analyses and certain nondestructive evaluation techniques (e.g., real-time radiography). Direct
characterization methods are conducted in accordance with the quality assurance program and
plan governing the site and laboratory facilities.
Indirect methods of characterization use non-destructive examination techniques and acceptable
knowledge to replace, supplement, and/or initially provide data that might otherwise be collected
by direct, intrusive characterization of the waste. In the safety and hazard analysis performed in
support of development of DOE M 435.1-1, the use of indirect methods was identified as an
appropriate means of characterizing waste and at the same time complying with the as low as
reasonably achievable (ALARA) principle for keeping radiation exposures to a minimum. An
additional benefit of characterizing low-level waste by the use of indirect methods is the avoidance
of the generation of waste associated with sample materials, and laboratory equipment and
expendables.
In order for indirect methods of low-level waste characterization to serve their purpose of
providing information necessary for the safe management of waste, the data need to be sufficiently
accurate. The level of accuracy is determined through application of data quality objectives, or
comparable process. Consistent with the data quality objectives, correlations demonstrating that
data provided by indirect methods are representative of the actual waste may need to be
Chapter IV - Low-Level Waste Requirements
IV-72 DOE G 435.1-1
7-09-99
supported through the application of direct methods. The methodology could employ a number
of techniques, some of which involve some direct sampling and analysis of the waste stream. The
following guidance paragraphs discuss different indirect methods.
Similar to the EPA and NRC guidance on characterizing mixed waste, DOE endorses the use of
indirect methods such as the use of acceptable or waste knowledge for characterizing physical,
chemical, RCRA-regulated and radioactive components of waste. The term acceptable
knowledge (or waste knowledge) includes process knowledge; records of analyses performed
prior to the effective date of a requirement; or a combination of process knowledge and previous
records, supplemented with chemical analyses (NRC/EPA, 1997). Process knowledge refers to
detailed information on processes that generate waste subject to this requirement or information
on processes similar to that which generated the waste being characterized.
Section 478
Acceptable knowledge characterization of low-level waste is based on an understanding of the
materials and processes used to generate the waste, or analytical data obtained from the process
or waste stream or both. Acceptable knowledge also includes information regarding the source of
the waste stream, the physical form and materials comprising the waste, the chemical constituents
of the waste, and the nature of the radioactivity present. Acceptable knowledge may be used to
describe low-level waste if the source information is consistent, defensible, and auditable. In
practice, acceptable knowledge can be effectively used where low-level waste is generated in well
known and tightly controlled processes for which the product is highly predictable.
While the development of a process for identifying and documenting low-level waste acceptable
knowledge is not dictated by this requirement, the following guidance provides an overview of
elements of an acceptable process for assembling acceptable knowledge documentation:
C Acceptable knowledge is compiled in an auditable record.
C Correlations within waste streams in terms of time of generation, waste generating
processes, analytical data, and site-specific facilities are clearly described.
C A reference list of applicable documents, databases, quality control protocols, and
other sources of information that support the acceptable knowledge information is
prepared.
C Procedures which outline the methodology that is to be used to identify and
assemble auditable acceptable knowledge records, including the origin of the
documentation, how the assembled information was or will be used, and any
limitations associated with the information.
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-73
7-09-99
Characterization data gained through acceptable knowledge must be within the acceptable range
of certainty and precision identified by the data quality objectives or similar process. Additionally,
the effects of time-dependent processes must either be negligible or predictable. If acceptable
knowledge is supported by the collection, analysis, and comparison of statistically valid samples
with the acceptable knowledge records, periodicity of sampling and analysis should correlate with
the nature of any changes in the process creating the waste or with changes that are being
documented in characterization data.
Non-destructive examination and assay techniques use methods such as passive-active neutron
assay, high resolution gamma ray spectroscopy, and thermal neutron capture to non-destructively
collect data relating to the radionuclide constituents in the waste. Acceptable performance of
assay techniques is determined through measurement of known standards and comparison to
established quality assurance objectives of the applicable characterization program. A process,
similar to the one discussed above regarding acceptable knowledge needs to be established and
documented in site procedures that outline the exact nature of the acceptable use of non
destructive examination techniques for providing characterization information on waste.
Another indirect method of providing radionuclide characterization data is through the use of a
known relationship, or scaling factors, between a measured radionuclide or a dose rate and the
radionuclide(s) of interest. As discussed above for acceptable knowledge and non-destructive
examination techniques, use of scaling factors must be correlated with actual data.
Section 479
The use of scaling factors is generally established by an initial characterization that provides a
statistical basis for use of the scaling factors. As with any indirect method, the characterization
program needs to include confirmatory measurements. The frequency of the confirmatory
measurements is based on the consistency of the process generating the waste. Additionally, the
history of previous confirmatory measurements may also influence the frequency of future
confirmatory measurements with results that are very consistent providing justification for less
frequent confirmatory measurements.
Example: A low-level waste stream from an actinide processing building is sampled and
analyzed and determined to be composed of three primary nuclides: Pu-239, Am-241,
and Pu-238. The samples are found to contain the three radionuclides in essentially the
same ratio. The process is known to be uniform and is therefore expected to generate
similar concentrations in the waste stream as the facility is operated. Therefore, the
contents of future waste containers are routinely characterized based on a gamma energy
analysis which detects gamma radiation from the Am-241 and Pu-238. The
characterization program requires the collection and full analysis of samples once a
month to confirm that the ratio of the three radionuclides falls within an acceptable
range (based on application of the data quality objectives process).
Chapter IV - Low-Level Waste Requirements
IV-74 DOE G 435.1-1
7-09-99
Characterization Documentation. The requirement states that characterization data shall be
documented in sufficient detail to enable the waste acceptance requirements of the receiving
facility to be met. The following elements are essential to this process for acquiring and
controlling characterization data:
Organization(s) and Responsibilities - Identification of the organizations involved and
responsible for characterization of low-level waste.
Quality Assurance - Characterization data need to be subjected to a quality assurance
program and the program that applies need to be identified and documented.
Procedures - The process for obtaining waste characterization data is formalized in
procedures which describe to the user the steps that are to be followed and the
administrative process for ensuring the data are of the quality needed. Topics that need to
be proceduralized include the processes for sampling, packaging, transportation,
laboratory analysis, and data control.
Procurement/Purchasing Controls - The procurement and/or purchasing of items or
services that are significant to characterizing low-level waste are controlled and
documented. Such procurement includes the purchase of sampling equipment and sample
transport containers, as well as services such as laboratory analyses (onsite or offsite). As
dictated by the type of procurement, the documentation needs to include (or reference) the
technical specifications for the item/service being procured, identification of quality
assurance requirements including any required inspections, specifications of
documentation requirements (e.g., certification of compliance or conformance, laboratory
analytical results), and a statement ensuring access to the provider’s facilities as necessary
to perform audits and inspections. The characterization data need to be traceable through
the provider’s process of generating it and verifying its accuracy.
Section 480
Document/Data Change Control - Records that contain characterization data, whether it
has been generated through sampling and analysis, nondestructive assay, or acceptable
knowledge, need to be controlled. In addition, the waste characterization procedures and
quality assurance program documentation are subject to document control. Document
and data control need to include review, approval, and distribution to designated recipients
(users), and a controlled process for making revisions to documents or data. Existing
document and data control programs at a site may be adequate to provide the necessary
controls for documents related to low-level waste characterization data, but will need to
be reviewed to ensure the objectives of DOE M 435.1-1 requirements are met.
Training - Characterization data are generated and managed only by personnel that are
properly trained to recognize the significance of the data. Generally, training of laboratory
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-75
7-09-99
personnel will be adequate to support low-level waste characterization, but needs to be
reviewed versus the goals of the characterization. Other staff managing and using
characterization data need to understand what is to be done with the data (i.e., what
decisions are to be made) once data are collected.
Records - Waste characterization records include those that are necessary to meet the
waste acceptance requirements of receiving facilities, and as specified by the waste
certification program DOE M 435.1-1, Section IV.J.
As noted above, existing programs at a site may provide the framework within which the elements
of waste characterization can be addressed (e.g., quality assurance, training, document control).
The waste acceptance requirements of a facility to which the waste is sent also may impose
additional requirements on what is to be included in the waste characterization data. The waste
acceptance requirements for the receiving facility include specific quality assurance,
administrative, or documentation requirements so that waste characterization data are acceptable
to the facility.
Example: Requirements have been established for the characterization of low-level
waste for the disposal facility at the Nevada Test Site. These characterization
requirements are documented in Chapter 4.0 of the Nevada Test Site Waste Acceptance
Criteria (NTSWAC), Revision 1. One of the requirements described there is the
preparation and submittal of waste profile forms containing characterization
information.
Compliance with this requirement is demonstrated by a program for documenting and the
existence of records that document the process for acquiring and verifying the validity of low-
level waste characterization data acquired through the use of direct or indirect methods.
Supplemental References:
1. CAO, 1996. Waste Acceptance Criteria for the Waste Isolation Pilot Plant,
DOE/WIPP-069, Revision 5, U.S. Department of Energy, Carlsbad Area Office, Carlsbad,
NM, April 1996.
2. EPA, 1994. Guidance for the Data Quality Objectives Process, EPA QA/G-4,
U.S. Environmental Protection Agency, Washington, D.C., September 1994.
3. NRC/EPA, 1997. “Joint NRC/EPA Guidance on Testing Requirements for Mixed
Radioactive and Hazardous Waste,” Federal Register, Vol. 62, No. 224, U.S.
Chapter IV - Low-Level Waste Requirements
IV-76 DOE G 435.1-1
7-09-99
Environmental Protection Agency and U.S. Nuclear Regulatory Commission, November
20, 1997.
Section 481
IV. I.(1) Data Quality Objectives. The data quality objectives process, or a
comparable process, shall be used for identifying characterization
parameters and acceptable uncertainty in characterization data.
Objective:
The objective of this requirement is to invoke a process for determining the type, quantity, and
quality of characterization data needed to support the safe management of low-level waste so as
to ensure that needed data are acquired, the data meet the objectives they are being collected for,
and resources are not wasted on unnecessary, incomplete, or unusable data collection efforts.
Discussion:
The type, quantity, and quality of characterization data obtained for the safe management of low-
level waste need to be consistent with the purpose for which the characterization information will
be used. The uses of low-level waste characterization data include: complying with storage,
treatment, and disposal facilities’ waste acceptance requirements; determining radiation shielding
and other protective measures; evaluating compliance with processing requirements; and meeting
legislative or regulatory commitments. This requirement is included in DOE M 435.1 to ensure
that the appropriate characterization data to support the safe management of low-level waste are
generated. The requirement is intended to promote a structured process for the collection and use
of low-level waste characterization data and to avoid the collection of data that is neither
necessary nor defensible.
Input from various waste management organizations and interested groups is necessary to
establish a clear understanding of the characterization data needs and the level of data quality that
is acceptable for making low-level waste management decisions. The current requirement invokes
the use of a structured process for determining the type, quantity, and quality of characterization
data needed. Such a process, called a data quality objectives process, has been developed by the
Environmental Protection Agency and is documented in Guidance for the Data Quality
Objectives Process (Reference 1). Application of the EPA process and use of the EPA guidance
is an acceptable way of meeting this requirement. However, use of other comparable processes
that employ a structured approach to yield similar results is also acceptable.
The objectives of applying a structured process such as the data quality objectives process are to:
C manage and control the risks of making incorrect decisions;
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-77
7-09-99
C determine the data required to support making specific decisions;
C determine the type and quality of required data;
C allow stakeholders, decision makers, data users, and relevant technical experts to
participate in planning and assessment;
C determine the quantity, location, and type of samples required;
C quantify the uncertainty in data through development of statistical sampling plans;
and
C reduce overall costs by identifying resource-efficient sample collection and
analytical methods by optimizing the sample and analysis plans.
The data quality objective process is a strategic planning approach based on the scientific method
that is used to prepare for a data collection activity. The value of using this process to develop
low-level waste characterization parameters is that it: reduces radiation exposure and saves
resources by making characterization data collection operations more resource-effective; enables
characterization data users and others to participate in characterization data planning; and
provides a structured method for defining characterization data performance requirements, i.e.,
quality.
Section 482
To foster the development and implementation of an effective data quality objectives or similar
process, individuals are assigned responsibility for specific activities for each application of the
process. Key activities of the process include:
• preparing the data quality objectives documentation;
• identifying stakeholders;
• identifying technical experts;
• ensuring opportunities for input and coordinating stakeholder and technical experts
into the data quality objective process;
• reviewing and commenting on the developed data quality objectives; and
• approving the data quality objectives documents.
Chapter IV - Low-Level Waste Requirements
IV-78 DOE G 435.1-1
7-09-99
A more detailed description of the assignment of specific responsibilities for implementing a data
quality objectives or similar process is presented in the Hanford “Data Quality Objectives
Procedure” (Reference 2).
The data quality objectives process consists of seven steps. The output from each step influences
the choices that will be made later in the process. Even though the data quality objectives process
is depicted as a linear sequence of steps, in practice it is iterative; the outputs from one step may
lead to a reconsideration of prior steps. This iteration is encouraged since it will ultimately lead to
a more efficient data collection design. During the first six steps of the process, a team of
process-cognizant personnel should develop decision performance criteria (i.e., data quality
objectives) that will be used to develop the data collection design.
The final step of the process involves developing the data collection design based on the data
quality objectives developed in the first six steps. The first six steps need to be completed before
the team attempts to develop the data collection design because the design is dependent on a clear
understanding of the first six steps taken as a whole.
Following is a listing and brief description of each of the seven steps. This is followed by an
example of how the data quality objectives process can be applied to low-level waste
characterization.
1. State the Problem – Concisely describe the problem to be studied. Review prior
studies and existing information to gain a sufficient understanding to define the problem.
2. Identify the Decision – Identify what questions the study will attempt to resolve, and
what actions may result.
3. Identify the Inputs to the Decision – Identify the information that needs to be obtained
and the measurements that need to be taken to resolve the decision statement.
4. Define the Study Boundaries – Specify the time periods and spatial area to which
decisions will apply. Determine when and where data should be collected.
5. Develop a Decision Rule – Define the statistical parameter of interest, specify the
action level, and integrate the previous data quality objective outputs into a single
statement that describes the logical basis for choosing among alternative actions.
6. Specify Tolerable Limits on Decision Errors – Define the decision maker’s tolerable
decision error rates based on a consideration of the consequences of making an incorrect
decision.
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-79
7-09-99
7. Optimize the Design – Evaluate information from the previous steps and generate
alternative data collection designs. Choose the most resource-effective design that meets
all data quality objectives.
Section 483
Example: The Blue Disposal Facility at Site X needed to establish the requirements for
acceptable waste potentially containing free liquids for disposal. Due to their
performance assessment and public concerns, the operating manual for the facility will
specify that no free liquids shall be disposed, so the acceptance documentation must
specify what specifically must be done to waste before it is shipped to ensure there will be
no free liquids upon arrival. They used a data quality objectives-like process to answer
some of the questions or issues related to the waste acceptance criterion. The Site X
personnel worked with technical experts from several waste generators to address the
issues. The question was formulated as, what does a generator have to do with waste that
contains liquids that could potentially become free due to vibration and thermal cycling
during transport? The answer to this question could make a significant difference in the
cost of making waste streams consisting of soils from cleanups acceptable for disposal
depending on how much testing and/or treatment was required by the Blue Facility’s
waste acceptance criteria. The data quality objective that was developed was:
The moisture content of low-level waste with high moisture contents (greater than
35%) must be specified on waste profile data sheets, and shall be packaged with
approved absorbents (see approved absorbents list at Appendix A). The amount
of absorbent added to a waste package shall be equivalent to 2 times the amount
necessary to absorb the amount of free liquid which would result if 80% of the
contained liquid, based on the moisture content, were to become free. [Approved
absorbent must be added in accordance with Recommended Procedure BL-23.]
The above description of the use of the data quality objectives process, and the example, are
provided as an introduction to the process. A more detailed description of the process can be
found in the referenced EPA guide. The data quality objectives process is most useful during the
planning stages of identifying low-level waste characterization and uncertainty parameters, i.e.,
before the data are needed and collected. The value of the process is diminished significantly if
the characterization data have already been collected because there is a tendency to make the
questions that need to be answered fit the available data. The data quality objectives process is
applied in a graded manner, i.e., the depth of detail and the magnitude of the resources expended
in implementing the process should be commensurate with the relative importance of the
characterization data in terms of the decisions to be made and protection of the public, workers
and the environment.
The intent of this requirement is not that waste streams with characterization processes already in
place and accepted by storage, treatment, and disposal facilities be recharacterized using the Data
Chapter IV - Low-Level Waste Requirements
IV-80 DOE G 435.1-1
7-09-99
Quality Objectives Process, or a comparable process, or that the characterization processes be
revised using the Data Quality Objectives Process, or a comparable process. The intent is that, as
new waste streams are identified and generated, the Data Quality Objectives Process, or a
comparable process, be used for identifying characterization parameters and acceptable
uncertainty in characterization data. If the characterization parameters of an existing waste
stream characterization data. If the characterization parameters of an existing waste stream
characterization process are to be significantly modified, then the Data Quality Objective Process,
or a comparable process, should be used.
Section 484
Compliance with this requirement is demonstrated by the documented use of a data quality
objectives or a comparable process for determining the type, quantity, and quality of
characterization data needed to safely manage low-level waste.
Supplemental References:
1. EPA, 1994. Guidance for the Data Quality Objectives Process, EPA QA/G-4, U.S.
Environmental Protection Agency, Washington, D.C., September 1994.
2. WHC, 1996. Data Quality Objectives Procedure, Revision 1, WHC-IP-1216,
Westinghouse Hanford Company, January 31, 1996, (included as Appendix A in draft
Manual HNF-SD-WM-PROC-021, Revision 0, Lockheed Martin Hanford Corporation,
January 2, 1997).
IV. I.(2) Minimum Waste Characterization. Characterization data shall, at a
minimum, include the following information relevant to the
management of the waste:
(a) Physical and chemical characteristics;
(b) Volume, including the waste and any stabilization or absorbent
media;
(c) Weight of the container and contents;
(d) Identities, activities, and concentrations of major
radionuclides;
(e) Characterization date;
(f) Generating source; and
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-81
7-09-99
(g) Any other information which may be needed to prepare and
maintain the disposal facility performance assessment, or
demonstrate compliance with applicable performance
objectives.
Objective:
The objective of this requirement is to establish minimum low-level waste data that have been
determined to be necessary for safe and effective management during the life cycle of the waste.
Discussion:
In the process of developing DOE O 435.1 and DOE M 435.1-1, the safety and hazard analysis
indicated that certain characterization data were critical because several consequences could be
avoided or minimized if certain basic information was accurately known about low-level waste.
This requirement identifies those critical characterization data points that must be known for safe
handling and proper management. The sections below provide guidance on each of these specific
characteristics.
Physical and Chemical Characteristics. Physical characteristics support handling and packaging
activities. Parameters should include a description of the material, its density, consistency, and
appearance. Chemical characteristics impact handling, storage, containment, and can impact
treatment processes. These characteristics determine the compatibility of the waste with other
waste and the waste container, as well as its compatibility with proposed treatment processes.
Parameters should include pH, reactivity, chemical compounds present, and the presence of
hazardous and/or toxic constituents. Physical and chemical characteristics can be determined
directly by visual examination and/or sampling and analysis. Physical characteristics can be
determined directly, indirectly by use of acceptable knowledge and/or by non-destructive
examination techniques such as computed tomography or real-time radiography. Chemical
characteristics can also be determined by use of acceptable knowledge.
Volume and Weight. Volume and weight information is necessary for proper control of storage
and disposal facility capacities as well as proper payload control for transportation and handling
systems. Typical parameters include:
C container volume, measured as the external volume of the waste container which
represents the volume that will be occupied in a storage or disposal facility (e.g.,
55 gallon drum or 120 cu ft (for a 4 x 5 x 6 box));
Section 485
C actual waste volume, including stabilization media;
Chapter IV - Low-Level Waste Requirements
IV-82 DOE G 435.1-1
7-09-99
C container weight; i.e., the total weight of the container and all of its contents
(waste, shielding, stabilization media) that would have to be handled;
C identification of the stabilization medium, if used; and
C waste container utilization factor, measured as the percentage of the packaging
volume that is filled with waste, including stabilization media. This parameter does
not require an individual calculation be made of stabilization or absorbent media
volume, but that those media be included in the total waste volume calculation.
These characteristics are generally determined by acceptable knowledge (e.g., container size,
stabilization medium) or by measurement (e.g., weight).
Radionuclide Data. Radionuclide information allows for proper control of thermal loads for
storage and disposal facilities, determination of personnel safety procedures, control of total
activity limits for transportation, storage, and disposal, and also determination of the waste type.
Parameters which constitute radionuclide information may include the following:
C total activity in the container, in curies;
C identity and activity per unit mass of the major radionuclides. For purposes of this
guidance, major radionuclides are those which affect the determination that a
waste is low-level waste, that the waste is within a site- or facility-specific category
or class of low-level waste (e.g., a category that requires solidification), and any
others determined to be of importance to the receiving facility (e.g., by safety
analysis, performance assessment, etc.);
C radiation dose levels at the surface of the container; and
C container external surface contamination levels.
These characteristics can be determined directly by smear survey or radiochemical analysis of the
waste, or indirectly by waste container non-destructive assay, radiation survey, and/or by
documentation of nuclear materials accountability information or individual assays performed on
components contained in the container.
Characterization Date and Generating Source. The date of characterization and generating source
information help to determine the validity of currently held documentation on the waste, which, in
turn, will determine the need for additional sampling or analysis. Parameters include
characterization date, packaging date, DOE site, building location of the process which generated
the waste and the generating process, if available.
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-83
7-09-99
Performance Assessment and Compliance Data. Additional data about waste that are important
to performance or evaluating performance of the disposal facility, or to complying with laws,
applicable regulations, or authorizing conditions (e.g., of a permit) may also need to be collected.
The specific data needed will, by necessity, be identified by the disposal facility operator.
Parameters which need to be included with waste characterization data may be identified by the
analysts developing the disposal facility performance assessment, specified through conditions
imposed on the site through the review and approval of the performance assessment, or derived
from internal regulatory compliance evaluations. Examples of the types of data that may be
needed are the presence and amounts of chelating agents which can enhance the transport of
radionuclides from the disposal facility, or the presence and concentrations of specific chemicals
which are not acceptable above specific limits (e.g., reporting polychlorinated biphenyls
concentrations versus a limit of 50 ppm).
Section 486
All of these data may not be required for a particular phase in the management of the waste’s life
cycle. The specific data needed will be determined by the waste acceptance criteria of a particular
receiving facility.
Example: Experimental work in a laboratory generates a liquid low-level waste stream
that is transferred via a pipeline to a central storage tank. Although the minimum
characterization requirements include “weight of the container and contents,” this is not
relevant to this waste stream and the characterization data in the waste acceptance
requirements for the central storage tank do not include packaging weight.
Compliance with this requirement is demonstrated by the existence of a program or procedure for
determining and records that document characterization of low-level waste consistent with the
minimum characterization data requirements.
Supplemental References:
1. NRC, 1983. Final Waste Classification and Waste Form Technical Position Papers,
U.S. Nuclear Regulatory Commission, Washington, D.C., May 1983.
Chapter IV - Low-Level Waste Requirements
IV-84 DOE G 435.1-1
7-09-99
IV. J. Waste Certification.
A waste certification program shall be developed, documented, and implemented to
ensure that the waste acceptance requirements of facilities receiving low-level waste
for storage, treatment, and disposal are met.
Objective:
The objective of this requirement is to ensure that low-level waste transferred to a facility for
storage, treatment, or disposal meets the receiving facility’s waste acceptance requirements to
reduce the likelihood that transferred wastes contain unacceptable materials or characteristics, and
to avoid hazards that would occur from the transportation and handling of waste packages which
do not meet acceptance requirements. Certification also ensures that the storage, treatment, or
disposal facilities receiving the low-level waste operate within limits established through safety
analyses and/or performance assessments.
Discussion:
The Radioactive Waste Management Manual, General Requirements, assigns the Field Element
Manager the responsibility of ensuring development and approval of a program that addresses the
responsibilities of waste generators (DOE M 435.1-1, Section I.2.F.(7)). The generator
requirements are to address hazards associated with a waste management facility receiving
unexpected volumes or types of waste, or receiving waste that may not meet the waste acceptance
requirements of the facility to which it is transferred. The generator requirements address
generation planning, waste characterization, waste certification, and waste transfer. As discussed
in this guidance, a certification program is to be established by generators of radioactive waste to
provide a mechanism for confirming that waste is in compliance with the waste acceptance criteria
of the facility to which the waste is being transferred. The certification program is required by any
organization or facility that transfers waste to another facility.
Example: The Building Five Storage Facility has low-level waste that it has received for
storage over the last year. Facility personnel plan to continue to receive low-level waste
and store it until it can be transferred to the Nevada Test Site disposal facility. Building
Five operates under a certification program in accordance with the Nevada Test Site
Waste Acceptance Criteria (NTSWAC) that certifies the waste meets the Nevada Test Site
technical acceptance criteria.
Section 487
The certification program is part of the waste generator program that is approved by the Field
Element Manager or designee. The certification program requires that an authorized official
confirms compliance with the waste acceptance requirements of the facility to which waste is
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-85
7-09-99
being transferred. Additional guidance correlated to the waste certification requirements of
Chapter IV, Low-Level Waste Requirements, is provided below.
Program Development and Documentation. The waste certification program to meet this
requirement consists of a documented, structured process that works in concert with the DOE M
435.1-1 requirements for low-level waste acceptance (Section IV.G) and transfer (Section IV.K)
to control the transfer of waste to a storage, treatment, or disposal facility. Development of the
waste certification program involves defining and documenting controls for those items and
activities that affect certifying that a waste and its packaging meets the waste acceptance criteria
of the receiving facility. The documentation should include the following:
Organizations and Responsibilities - Certification program documentation needs to
identify the organizations and officials involved in the certification process and the
responsibilities of each. Officials who are authorized to certify waste are identified in the
documentation.
Quality Assurance - The certification program is subject to quality assurance controls.
The quality assurance controls that apply to waste certification activities need to identified
and documented. The use of existing quality assurance program under which the
certification activities will be performed is acceptable and appropriate.
Procedures - The process for certifying waste is to be formalized in procedures. The
procedures need to describe to the user the steps that are to be followed and the
administrative process for ensuring waste containers are certified. The procedures require
a signed statement certifying waste meets the appropriate criteria. The procedures also
document the steps necessary for complying with the applicable transportation
requirements (e.g., requirements from a safety analysis report for packaging and/or from
Title 49, Code of Federal Regulations).
Procurement/Purchasing Controls - The procurement and/or purchase of items or services
that are significant to certifying that a waste meets the waste acceptance criteria of a
receiving facility need to be documented. Such procurements may include the purchase of
materials such as waste containers, or laboratory services (onsite or offsite). As dictated
by the type of procurement, the documentation should include (or reference) the technical
specifications for the item/service being procured; identification of quality assurance
requirements including any required testing or inspections; specification of documentation
to be provided on delivery (e.g., fabrication inspection and/or test records; a certificate of
compliance or conformance; laboratory analytical results); and a statement ensuring access
to the provider’s facilities as necessary to perform audits and inspections. The
certification program ensures that the procurement documentation is reviewed and
approved by an official with knowledge of the need, intent, and requirements for the
Chapter IV - Low-Level Waste Requirements
IV-86 DOE G 435.1-1
7-09-99
Section 488
procurement. The program also provides for documented verification commensurate with
the relative importance and complexity of the items or services being procured.
Document Control - The principal documents that constitute the certification program
need to be subject to document control. Program documentation will identify which
documents are to be controlled. The waste certification program description, waste
certification procedures, and quality assurance program documentation need to all be
subject to document control. Document control includes review and approval, distribution
to designated recipients (users), and a controlled process for making changes to the
documents. Existing document control programs at a site may provide the necessary
controls for documents that are part of the waste certification program.
Training - The certification program needs to identify the training requirements for the
various individuals who are involved in the program. At a minimum, the program will
require training of the official who certifies the waste meets the waste acceptance criteria
of the facility(ies) to which the waste is being transferred. In addition, individuals will
need to be trained in the procedures that control the part of the certification process with
which they are involved.
Records - The certification program documentation needs to describe the management of
certification records (see guidance for subparagraph (1) of this Waste Certification
requirement).
Example: A site generates a small amount of low-level waste that is sent to a
central facility managed by a waste management organization. The generating
organizations work with the receiving facility to define the waste certification
program for the site. Through a review of the existing site procedures, site
personnel determine the waste certification program can operate under the
existing site quality assurance program, document control program, procurement
process, and records management program. However, they determine that the
site training program does not adequately address the certification process.
Consequently, the waste managers work with the training department and develop
a training module that explains the purpose and process of waste certification.
The certification program documentation identifies these other programs are
applicable, specifies the facilities from which waste would be transferred,
designates the officials responsible for waste certification at those facilities and
their training requirements, and specifies a procedure (within the document
control program) that ensures compliance with the waste acceptance criteria.
Within the existing programs, site personnel identify the records to be maintained
and retention times, technical specifications and receipt requirements for
obtaining waste packaging materials, and requirements for analytical data.
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-87
7-09-99
Operating within the parameters defined by the program, the waste generators
are able to certify waste for transfer to the onsite receiving facility.
As noted in the preceding example, existing programs at a site may provide the framework within
which elements of the waste certification program can be addressed (e.g., quality assurance,
training, document control). The waste acceptance requirements of the facility to which the waste
is to be sent may impose additional requirements on what is to be included in the waste
certification program. Whether the waste acceptance requirements of the facility to which waste
is transferred mandate a waste certification program (e.g., a commercial facility), the organization
transferring the waste is responsible for developing and implementing a certification program to
provide internal assurance that the waste acceptance requirements will be met.
Section 489
Implementation. The waste certification program is implemented through the use of the
documented controls, processes, and procedures. The key document in a waste certification
program is the certification statement or equivalent. The certification statement is the
documentation signed by a designated official that certifies that the low-level waste meets the
appropriate requirements. The list below is a generic listing of the topics that are recommended
for consideration in development of certification statements for waste shipments that go from one
DOE site to another.
1. Container and Physical Properties
- container type or description
- labeling/markings
- weight
- vents
- liquids
2. Nuclear/Radiological Properties
- fissile content
- transuranic activity
- other radioactivity
- dose rate
- surface contamination
- thermal power
3. Chemical Properties
- mixed waste
- polychlorinated biphenyls
Chapter IV - Low-Level Waste Requirements
IV-88 DOE G 435.1-1
7-09-99
- other hazardous constituents
- pyrophorics
- explosives
- corrosives
- compressed gases
- volatile organic compounds
4. Packaging/Shipping Data
- packaging
- shipping information
Graded Approach. A graded approach is used in implementing the waste certification program.
As mentioned, the above list is recommended for the intersite transfer of low-level waste.
Intersite transfers involve certifying that the waste is in compliance with the requirements for the
receiving facility itself and with Department of Transportation requirements. However, even
though the above list should be considered, it may be shortened and simplified for onsite transfers
where the organizational relationships and knowledge of waste and waste generating activities
may reduce the information that needs to be documented and transferred with each individual
waste container or shipment. For onsite transfers, much of the information may already be
available to the receiving facility. Onsite transportation of waste should be certified as meeting
Department of Transportation or site-specific requirements for transportation.
Example: For an onsite transfer of waste at Site D, the receiving facility/organization
already has a waste stream profile provided by the generator facility/organization.
Because of the existence of the waste stream profile, the certification is performed by an
individual trained in the waste packaging and certification procedures signing a waste
pick-up request that provides the radionuclide inventory of the waste packages being
transferred and the waste stream identification number.
The waste acceptance requirements of the facility receiving the waste (see DOE M 435.1-1,
Section IV.G) may dictate additional items which must be part of the certification statement.
Even if such information is not dictated by the receiving facility, the waste acceptance criteria
should be used to identify key elements to include on the waste certification statement.
Compliance with the development and documentation portion of the certification requirement is
demonstrated by a waste certification plan that identifies the organizations involved, assigns
responsibilities for implementing the program, and describes or references the quality assurance,
training, procurement controls, records management, and procedures to be used by the program.
Acceptable performance for implementing the program is demonstrated when appropriate
personnel are trained and follow the procedures that govern their part of the waste certification
Section 490
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-89
7-09-99
process. Additionally, acceptable performance is demonstrated if the waste certification plan and
procedures are current and controlled in accordance with a document controls program, and
records related to certification (e.g., certification statements, training records, procurement
records, characterization records, container records) are generated and managed in accordance
with the established site program.
Supplemental References:
1. DOE, 1997. Nevada Test Site Waste Acceptance Criteria (NTSWAC), Revision 1, U.S.
Department of Energy, Nevada Operations Office, Las Vegas, NV, August 1997.
IV. J.(1) Certification Program. The waste certification program shall
designate the officials who have the authority to certify and release
waste for shipment; and specify what documentation is required for
waste generation, characterization, shipment, and certification. The
program shall provide requirements for auditability, retrievability,
and storage of required documentation and specify the records
retention period.
Objective:
The objective of this requirement is to ensure waste certification programs are developed that
clearly identify the documentation required for certifying low-level waste, specify personnel with
the authority to make the certification, and provide a traceable and verifiable record of and basis
for certification.
Discussion:
Officials who have the authority to certify low-level waste meets the waste acceptance
requirements of the receiving facility must be designated by a cognizant manager. To avoid
having personnel who are not knowledgeable of waste acceptance and transfer requirements
authorizing the release of waste, the program needs to identify, by title or name, the officials who
are authorized to certify the waste. The official(s) are qualified by virtue of position,
responsibilities, and training to make this certification. The official(s) have sufficient familiarity
with the waste being generated and have been trained relative to the acceptance criteria of the
receiving facility (and applicable transportation requirements) to be able to certify in writing that
the waste is acceptable for transfer. The official(s) need to also have authorization from the
receiving facility to transfer the waste (see DOE M 435.1-1, Section IV.K, Waste Transfer).
Implementation of this element should be tailored to specific site needs and situations.
Chapter IV - Low-Level Waste Requirements
IV-90 DOE G 435.1-1
7-09-99
Example: Onsite transfers of low-level waste at Site E from multiple laboratories or
processes to the central waste management facility involves training multiple personnel
(e.g., one for each laboratory or process) who have the authority to certify waste as
meeting the onsite waste acceptance requirements. However, for the transfer of low-level
waste from the central waste management facility at Site E to an offsite facility, there is
one designated official at the site who is trained on the acceptance criteria of the offsite
storage, treatment, or disposal facility waste acceptance criteria and transportation
requirements, and is authorized to certify the waste.
The waste certification program needs to specifically identify the documentation to be produced
to support the certification that low-level waste meets the waste acceptance criteria of the
receiving facility. The required documentation may include the following:
Section 491
Waste Stream Profile (or record relating the waste to a previous profile). The waste
stream profile is a description of the waste stream, generally identifying the source,
physical and chemical description, and upper limits on radionuclides.
Radionuclide Characterization Data. Radionuclide characterization data include the
concentration and/or inventory of radionuclides as determined by characterization (see
guidance for DOE M 435.1-1, Section IV.I, Waste Characterization).
EPA Uniform Hazardous Waste Manifest. The EPA manifest is required by 40 CFR Part
262 for the transfer of a hazardous or mixed waste.
Waste Container Data and Integrity Maintenance Documentation. Container data includes
information about the containers dimensions and physical attributes and procurement
information. Integrity documentation includes the records of ownership and “transfer” of
waste containers and data. (See guidance for Waste Transfer, DOE M 435.1-1, Section
IV.K.)
Radiological Survey Results (or documentation referencing a survey record). Survey
results include the determination of the surface contamination of the waste container and
the external dose rate.
Bill of Lading. A document indicating the contents of a shipment.
Real-time Radiography Results. The results of radiography performed to detect
unallowed material in the waste package (e.g., liquids, compressed gas cylinders).
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-91
7-09-99
Certification Statement. The statement required by DOE M 435.1-1 to document that
waste is in compliance with the acceptance criteria of the facility to which the waste is
being transferred.
Authorization to Transfer. Documentation indicating that an official from the facility to
which the waste is to be transferred has authorized transfer of the waste to the facility.
As noted for other elements of this requirement, the organization developing the certification
program uses a graded approach in determining which of these documents are needed.
Regardless of the extent of the required documentation, the certification statement can serve as a
checklist that all of the waste acceptance criteria have been considered and the waste is in
compliance.
In order to ensure that information is available if or when it is needed in the future, the low-level
waste certification program needs to identify which records are to be maintained and how they are
to be maintained. The certification program documentation may include specific records
management requirements, or may simply invoke an existing acceptable records management
program. Although no minimum record retention times are established in DOE M 435.1-1,
certain records may need to be maintained indefinitely. Whereas hazardous waste regulations
require only a three-year retention period, DOE low-level waste disposal facilities should plan on
maintaining pertinent records at least through the operations, closure, and post-closure
monitoring periods, and consider making them part of any local land use records. The pertinent
records would be those which identify physical, chemical, and radiological characteristics of the
waste and the certification of that information. Generating, storage, or treatment facility waste
management records may not be required beyond the life of the facility or operation, provided
pertinent information has been supplied to the facility where the waste will be disposed.
Section 492
Example: Personnel at a storage facility maintain records describing when they received
waste, what the waste was (characterization and container data provided by the
generator), and to whom the waste was eventually transferred. Once the waste is
disposed of and the waste characterization and container information is in the possession
of the organization responsible for the disposal facility, the organization responsible for
the storage facility disposes of its records.
To meet the requirement for auditability and retrievability, the method of records storage and
retention needs to allow a person to trace shipment or waste container information back to the
generator certification data (e.g., characterization data, source data, container data). In
accordance with the DOE M 435.1-1 Transfer Requirements (Section IV.K), information on the
source and characteristics of the waste are to be transferred when waste is transferred. However,
it is not the intent of this requirement to mandate that a certification statement be generated for
Chapter IV - Low-Level Waste Requirements
IV-92 DOE G 435.1-1
7-09-99
waste already in storage as of the issuance of DOE O 435.1. Such documents must be created for
any subsequent transfers of waste.
Example: A site should be able to provide the characterization, container, and
certification information for any waste container within a storage, treatment, or disposal
facility if that waste container is transferred after issuance of DOE O 435.1.
Compliance with this requirement is demonstrated by a program or procedure for record keeping
and records showing that low-level waste is certified as having met the waste acceptance criteria
of the facility to which it was transferred and that the certification statement is supported by
additional records regarding the waste source, characterization, and container.
Supplemental References:
1. DOE, 1997. Nevada Test Site Waste Acceptance Criteria (NTSWAC), Revision 1, U.S.
Department of Energy, Nevada Operations Office, Las Vegas, NV, August 1997.
IV. J.(2) Certification Before Transfer. Low-level waste shall be certified as
meeting waste acceptance requirements before it is transferred to the
facility receiving the waste.
Objective:
The objective of this requirement is to certify that low-level waste meets the acceptance
requirements of the storage, treatment, or disposal facility before it is transferred to prevent
transferring waste that could endanger receiving facility personnel, and to avoid the delay and
potential hazards associated with corrective actions taken to remedy non-compliant conditions.
Discussion:
The waste certification requirements above address development, implementation, and content of
a waste certification program. The requirement that waste be certified before transfer ensures that
the program is effective in preventing the transfer of waste that does not meet the waste
acceptance criteria of the facility receiving the waste for storage, treatment, or disposal. In
accordance with this requirement, waste should be released for transfer to another facility only
after there is a certification by an authorized official that the waste acceptance requirements have
been met. Ensuring certification occurs prior to allowing the physical transfer of waste prevents
potential hazards associated with managing waste rejected by the facility to which it is transferred.
Requiring certification before waste is transferred also reduces the likelihood of having to recall a
waste shipment due to a discovery by the certification official, after the waste is in transit, that the
Section 493
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-93
7-09-99
waste does not comply with the waste acceptance requirements. Guidance on DOE M 435.1-1,
Section IV.K discusses when a transfer occurs, and can be consulted to determine when this
requirement needs to be met.
Certification that the waste is ready for transfer and meets the waste acceptance criteria and the
applicable transportation requirements is a control point in the transfer process. The procedures
controlling waste transfer do not allow the transfer to occur unless the certification statement has
been signed. Once signed, the certification statement becomes part of the record for the transfer
of the waste (see Waste Transfer, DOE M 435.1-1, Section IV.K). An example of a certification
statement for shipment of low-level waste to the Nevada Test Site is included as Figure IV.J.1 (in
this case, the certification statement is a label that is affixed to the waste container.) The
signature on the certification statement confirms that the waste has been characterized for
physical, chemical, and radiological characteristics, properly packaged, and necessary container
markings and shipping data have been prepared.
Example: Central Waste Management Facility personnel are responsible for receiving
waste, providing storage for a short time, and making transfers to an offsite low-level
waste storage facility. In order for the workers at the Central Waste Management
Facility to place a waste container on a truck for transfer, the operating procedures for
the facility require that they have a signed certification statement that correlates to the
container(s) (either bar coded or numbered). Once a waste container is loaded, a copy
of the certification statement is included in the waste transfer papers and another is
included in the Central Waste Management Facility files.
Compliance with this requirement is demonstrated by the presence of a certification program
which includes procedures requiring a signed certification statement prior to the release of waste
for transfer, and by dated records showing that waste was certified before being transferred.
Supplemental References:
1. DOE, 1997. Nevada Test Site Waste Acceptance Criteria (NTSWAC), Revision 1, U.S.
Department of Energy, Nevada Operations Office, Las Vegas, NV, August 1997.
IV. J.(3) Maintaining Certification. Low-level waste that has been certified as
meeting the waste acceptance requirements for transfer to a storage,
treatment, or disposal facility shall be managed in a manner that
maintains its certification status.
Chapter IV - Low-Level Waste Requirements
IV-94 DOE G 435.1-1
7-09-99
Objective:
The objective of this requirement is to ensure that certified low-level waste is managed to
maintain the certification status and avoid the unnecessary handling of waste containers that
would be necessary for recertifying waste.
Discussion:
There may be instances where low-level waste that is already certified to a disposal facility's waste
acceptance requirements must be stored before transferred to the next stage in the waste
management process (usually the disposal facility, but it could be another storage facility). If low-
level waste is certified as meeting the waste acceptance criteria of another facility in addition to
the receiving facility, it needs to be stored and controlled so that the certification for the
subsequent management step remains valid until the waste can be transferred.
Section 494
Waste needs to be stored under conditions and with controls to protect it from physical damage,
and to prevent tampering (i.e., placement of unallowed materials into the container) so it can be
transferred for disposal without re-certification. Also, certifying officials need to be aware of any
limitations on the amount of time a waste can be stored without invalidating the certification.
Actions necessary to certify a low-level waste that involve potential radiation exposure to workers
are deferred, if possible, until there is a reasonable expectation that the waste can be transferred to
the receiving facility within the time that the certification is valid. Routine monitoring required for
waste in storage may not allow all activities that could result in worker exposure to be deferred.
This requirement is not to be interpreted in a manner that interferes with a facility performing a
normal, acceptable waste management function. Therefore, if a low-level waste is certified as
meeting the waste acceptance criteria of a treatment facility, the requirement to maintain the
certification is not intended to prevent the treatment facility from treating the waste. Even though
treating the waste will not “maintain” the certification, the purpose of the certification is to ensure
the waste can be safely accepted for treatment. Maintenance of the certification status is
intended to cause the waste to be stored, transported, and staged at the treatment facility in a
manner that will allow personnel to treat the waste without concern that it no longer meets the
acceptance criteria. In addition, despite the protection provided for the waste, sampling prior to
treatment may still be a necessary process control step.
Specific requirements for protecting the certification status of low-level waste are generally
negotiated with the receiving facility. Requirements to be considered include protecting the waste
container, preventing unauthorized introduction of material into the waste, and protecting the data
written or stamped on the waste container. The Waste Transfer requirements (DOE M 435.1,
Section IV.K) also address protecting waste packages and data to ensure that characterization
and container data remain accurate and useable by waste managers. Waste containers need to be
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-95
7-09-99
provided with sufficient protection from the elements (e.g., precipitation, wind, flooding,
excessive heat), such that the character of the waste and container, and therefore the certification
are not altered. Waste containers need to also be stored in a manner that prevents modifying their
contents (e.g, under lock and key or with a tamper indication device) and in a location where the
waste container will not be damaged (away from equipment high traffic areas where there is the
possibility of damage). In addition, it is necessary to be able to relate each waste container to
information about the contents of the container. Container markings must be protected from
defacement or removal, and records regarding container identification and contents must be safely
stored.
Example: Mixed low-level waste is certified to be in compliance with the Site X’s waste
acceptance requirements, and to the waste acceptance requirements of Storage Building
A where it will reside until the disposal can take place. The mixed waste is stored in
accordance with a procedure that ensures the certification status to Site X is unaffected.
The procedure calls for storage of the mixed low-level waste in accordance with a
security plan reviewed and approved by the Site X waste acceptance personnel, storage
in a specially designated area within Storage Building A, and record-keeping in a
separate database from other waste in storage.
Section 495
Compliance with this requirement is demonstrated by a program or procedure reflecting this
requirement is present and site personnel are able to show that the storage of low-level waste
containers is in a facility or manner where the containers would not be damaged by normal
weather events, and cannot be accessed by unauthorized personnel. Further, each container can
be traced to its certification and the information supporting that certification.
Supplemental References:
1. DOE, 1997. Nevada Test Site Waste Acceptance Criteria (NTSWAC), Revision 1, U.S.
Department of Energy, Nevada Operations Office, Las Vegas, NV, August 1997.
2. DOE, 1991. Hanford Site Solid Waste Acceptance Criteria, WHC-EP-0063-3, U.S.
Department of Energy, Office of Environmental Restoration and Waste Management,
September 1991.
Chapter IV - Low-Level Waste Requirements
__________________________________________________ _________________________
__________________________________________________ _________________________
IV-96 DOE G 435.1-1
7-09-99
Figure IV.J.1 - Example Waste Certification Forms
Low-Level Waste Certification
“I certify that containers:
(Container I.D. number[s])
do not contain hazardous waste as defined in Title 40 CFR Part 261 or __________ (state-of-generation)
hazardous waste regulations, and do meet the NTSWAC requirements:
(1) according to the results of tests performed in accordance with the requirements as specified in Subpart C
of Title 40 CFR Part 261; and/or
(2) according to the supporting documentation provided to me about the materials and processes that
produced this waste.
To the best of my knowledge, I believe the information I have submitted is true, accurate, and complete.”
Generator Waste Certification Official (Print Name/Sign) Sign
Mixed Waste Certification for Land Disposal Restrictions:
I certify under penalty of law that I personally have examined and am familiar with the waste through
analysis and testing or through knowledge of the waste to support this certification that the waste in
containers:
(Container I.D. number[s])
complies with the treatment standards specified in Title 40 CFR Part 268, Subpart D, and all applicable
prohibitions set forth in 40 CFR 268.32, RCRA Section 3004(d) or ___________ (state-of-generation)
hazardous waste regulations.
I believe that the information I submitted is true, accurate, and complete, I am aware that there are
significant penalties for submitting a false certification, including the possibility of a fine and imprisonment.
Generator Waste Certification Official (Print Name/Sign) Sign
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-97
7-09-99
IV. K. Waste Transfer.
A documented process shall be established and implemented for transferring
responsibility for management of low-level waste and for ensuring availability of
relevant data. The following requirements are in addition to those in Chapter I of
this Manual.
Objective:
The objective of this requirement is to ensure that the responsibility for low-level waste containers
is established, maintained, properly transferred, and adequately documented so that ownership,
and therefore responsibility for safe management, of waste is clear. This responsibility includes
maintaining the waste characterization information, the container information, and information
about the treatment, storage, transportation and disposal status of containers of waste. This
responsibility also includes an assurance that the container of waste has not been altered in a
manner that affects its certification status or the ability of the waste to be properly managed.
Section 496
Discussion:
As discussed in Section I.2.F.(7) of the guidance for DOE M 435.1-1 Chapter I, the radioactive
waste generator program includes consideration of the generation planning, characterization,
certification, and transfer of low-level waste. In the generator’s program, initial responsibility is
assigned for containers of low-level waste and a documented process for transferring the
responsibility is established.
In the development of DOE O 435.1 and DOE M 435.1-1, maintaining the integrity of waste
containers was identified as necessary for the proper control and safe management of low-level
waste. Similarly, maintaining information about containers of low-level waste (characterization
and container data) was recognized as vital to making and executing safe management decisions.
In order to ensure that it is clear who has the responsibility for protecting the integrity of each
container of low-level waste and associated waste and container data, there needs to be one
person who is identified as being responsible for the waste at any time. Confusion over who is
responsible for specific waste containers is avoided by documenting the transfer of responsibility.
This requirement is similar to the concept of chain of custody used in sample management. As
with samples, low-level waste containers may be the responsibility of many different organizations
during their management life cycle. At any point during the life cycle management of the waste,
the identity of the individual responsible for each container of waste needs to be explicit. By
clearly identifying the owner of each container of waste, there is no question regarding who is
responsible for protecting the waste container and the waste characterization and container data,
Chapter IV - Low-Level Waste Requirements
IV-98 DOE G 435.1-1
7-09-99
and for moving the waste to the next phase of waste management (i.e., storage, treatment, or
disposal).
Maintaining Waste Container and Data Integrity. The individual responsible for a container of
waste is responsible for maintaining and protecting both the integrity of the container of waste and
the data about the container of waste. Protecting the integrity of the waste container is the same
as protecting the certification status of a waste container as discussed in the Waste Certification
guidance. Essentially it involves managing the container of waste so that it is not damaged or
does not degrade because of the conditions under which it is managed.
Maintaining the data about the container of waste involves ensuring receipt or traceability, or
developing (as discussed below) information necessary to support subsequent waste management
activities, or clearly documenting and ensuring that the information is stored and updated so that
full and accurate information is available to the next individual to whom the waste is transferred.
Transferring Responsibility. The transfer of responsibility for containers of low-level waste and
the associated waste and container data is to be done in accordance with procedures at each of the
facilities involved. The facility from which the waste is transferred, typically establishes (for
newly-generated waste) or possesses (for stored wastes) a record or data package about the
waste and its container. The facility operating procedures should require the development of an
ownership log sheet similar to a chain-of-custody log. This log becomes the data package that is
transferred with the container of waste. Upon transfer, the facility transferring the waste is
responsible for ensuring personnel at the facility to which the waste is being transferred have
assumed responsibility for the waste. A signed and dated copy of the ownership log sheet can
serve this purpose. All subsequent transfers, e.g., from storage or treatment facilities, are to be in
accordance with procedures requiring the transfer of the data package and documentation of the
transfer of responsibility for the waste.
Section 497
Procedures at the storage, treatment, or disposal facility should require the receipt of certain
information about any low-level waste which is received. To ensure that they have sufficient
information to safely manage the waste and to transfer the waste to a subsequent waste
management facility (if appropriate), it is important for storage, treatment, and disposal facility
personnel to ensure they are provided information about the containers of waste for which they
become responsible. The receiving facility requires the following documented information be
available for all waste they expect to receive:
• Responsible individual. The name, title, affiliation, and phone number of each
person who has held responsibility for the waste, starting with the generator. This
listing can serve as the ownership log with each person signing the log upon
accepting responsibility for the waste.
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-99
7-09-99
• Transfer dates. The date the transfer was accepted by each new “owner” of the
waste.
• Waste container information. Information about the container (see guidance for
IV.K.(2) in this section).
• Characterization information. Information about the waste (see guidance on
Waste Characterization).
• Physical location. The site and name (e.g., unique identifier such as a building
number) of each location where the waste was managed.
• Previous transportation. Dates of transportation and names of carriers.
• Certification status. A signed certification statement or equivalent (see guidance
on Waste Certification). Only the certification statement for the facility to which
the waste is being transferred must be part of the waste package data. Previous
certification statements may be included if they serve the purpose of documenting
other data that should be part of the data package (e.g.,container or
characterization data).
• The planned disposition of the waste. Expected storage, treatment, and disposal
(see guidance on Generation Planning and Site-Wide Radioactive Waste
Management Program).
For each transfer beginning with the generator, the receiver of the waste is responsible for
obtaining the proper information from the sender of the waste. The receiver’s responsibility is to
ensure receipt or availability of complete and accurate information concerning containers of
waste. The information needs to be reviewed prior to actual transfer and is a condition of
acceptance by the receiver.
Example: A treatment facility receives low-level waste for processing. Upon signing for
receipt of the waste, the facility manager becomes the individual responsible for the
waste. Facility procedures require that a copy of the data received from the generator be
kept in a file cabinet which is accessible only to one individual on each shift. As the
containers of waste are processed in the facility, information is recorded in a log and the
data package is updated to reflect the change in status of the waste. Upon completion of
the processing, the treated waste is packaged in new waste containers and a certification
statement is generated indicating that the treated waste meets the waste acceptance
criteria for the storage facility to which it will be shipped. Before the waste is
transferred, the treatment facility personnel provide a complete set of data to the storage
Chapter IV - Low-Level Waste Requirements
IV-100 DOE G 435.1-1
7-09-99
Section 498
facility personnel. The data package reflects the new container numbers for the treated
waste, but includes the data on the original containers received at the treatment facility.
The treatment facility also keeps a duplicate copy of the data package which includes a
copy of a waste log indicating transfer of ownership to the storage facility.
The responsibility for ownership of the waste can be different than that for waste certification.
The individual responsible for the waste does not necessarily have to be the same individual that
certifies the waste is ready to be transferred (see guidance on Waste Certification). As indicated
above, the certification status is one piece of information that is transferred with the waste.
Compliance with this requirement is demonstrated if facilities have procedures for the receipt of
waste and the transfer of waste, as appropriate, which address the acquisition of waste and
container data and the transfer of ownership, respectively. Further evidence of acceptable
performance is facility records showing that data on the waste containers is available and
accurate, and that documented transfer of responsibility occurs.
Supplemental References:
1. EPA, 1997. Test Methods for Evaluating Solid Waste, Physical/Chemical Methods, SW
846, Third Edition, U.S. Environmental Protection Agency, Washington, D.C., June 1997.
IV. K.(1) Authorization. Low-level waste shall not be transferred to a storage,
treatment, or disposal facility until personnel responsible for the
facility receiving the waste authorize the transfer.
Objective:
The objective of this requirement is to ensure that shipments or transfers of low-level waste are
made only with the cognizance and approval of personnel at the facility receiving low-level waste
so that preparations can be assured for its safe management.
Discussion:
As discussed in the guidance for DOE M 435.1-1, Section I.2.F.(7), the radioactive waste
generator program includes consideration of the generation planning, characterization,
certification, and transfer of low-level waste. During the development of DOE O 435.1 and DOE
M 435.1-1, a review of waste management functions indicated that the receipt of waste without
personnel at the facility receiving the waste having knowledge of what was sent presented a
potential hazard. If waste is transferred to a facility without prior authorization, the controls
necessary for the proper and safe management of the waste may not be in place. As a
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-101
7-09-99
consequence, the waste may be rejected and returned to the sender. This requirement represents
a control to minimize the potential for exposures and releases during the handling and transfer of
low-level waste.
Safe transfer of the waste can only be assured if the facility receiving the waste for storage,
treatment, or disposal has considered the acceptability of the waste versus its safety operating
constraints. Personnel at a storage, treatment, or disposal facility who authorize the transfer of
waste are indicating that they have the capability to receive the waste and manage it in a manner
that is protective of workers, the public, and the environment. Therefore for the purposes of safe
life-cycle management, the receipt of authorization prior to the transfer of low-level waste to a
storage, treatment, or disposal facility is essential. Meeting this requirement is the responsibility
of the organization or individual transferring (sending) the waste. The following are considered
transfers:
Section 499
(1) Waste is physically moved from one location to another, even if ownership does
not change.
(2) Waste is physically moved from one location to another and ownership changes.
(3) Waste is not physically moved, but ownership changes.
The actions and documentation necessary to obtain authorization will depend on the specific
storage, treatment, or disposal facility to which waste is to be transferred. In some cases, the
submittal of a waste stream profile which provides a description of the waste and a range of the
waste characteristics, augmented by conversations with the generator, may provide enough
information for the storage, treatment, or disposal facility staff to be confident that they can safely
manage the waste. In other cases, the waste acceptance requirements of the storage, treatment,
or disposal facility may dictate that an onsite visit and review of the generator’s waste certification
program be performed. In order to expedite the transfer of waste, staff responsible for sending
the waste need to ensure they understand what information and activities need to be completed in
order to receive transfer authorization.
Authorization to transfer waste is received in writing and states the scope of the authorization.
The authorization may specify a specific group of waste packages or specific number of shipments
of a particular waste type. However, it is acceptable for the written authorization to specify a
waste stream(s) which the generator can send on a routine basis. Any additional conditions or
notification requirements can be included in the written authorization. Whereas it is the
responsibility of the storage, treatment, or disposal facility to prepare the written authorization,
the organization sending the waste must not transfer waste until they have authorization and
understand which waste is included in the authorization.
Chapter IV - Low-Level Waste Requirements
IV-102 DOE G 435.1-1
7-09-99
Example: An activity at Site X results in the routine generation of low-level waste in the
form of contaminated personnel protective equipment, swipes, plastic sheeting, and paper
waste. The waste stream is designated by the number X-2156. Consistent with site
procedures, the generator prepares a waste stream profile which describes the
characteristics, packaging, and projected generation rate of the waste stream and
provides it to the waste management organization. The waste management organization
reviews the waste stream profile and calls the generator facility representative to clarify
the information on the waste stream profile. The waste management organization has
previously reviewed the generator’s certification program. Based on the certification
program and the waste stream profile, the waste management organization prepares a
letter authorizing the generator to transfer any waste that meets the X-2156 profile until
further notice. The authorization letter also states that the generator must provide the
waste management organization notice of the number of waste containers to be
transferred 48 hours before a transfer occurs.
When low-level waste is transferred (moved from one location to another), but the ownership of
the waste does not change (i.e., the same individual is responsible for both facilities), a separate
authorization may not be required. Recognizing that the intent of this requirement is to ensure
that the waste is expected and can be safely managed at the facility to which it is being
transferred, other documentation can serve as the written authorization.
Section 500
Example: The manager of the waste management organization is the official responsible
for authorizing transfer of waste to either of two separate storage facilities, Building A
and Building B. Even though the waste acceptance criteria are the same for the two
facilities, waste is accepted and logged into each facility separately. The manager
decides to consolidate all of the waste into Building A for more efficient management.
The authorization to transfer is provided by the certification statement indicating that the
waste meets the Building A waste acceptance requirements, and the documentation of the
new storage location on the waste characterization and container data.
Compliance with this requirement is demonstrated by sites having procedures that require a
confirmation of authorization before releasing waste for transfer, and records showing that
transfers are made in accordance with written authorizations.
Supplemental References:
1. DOE/CAO, 1995. Generator Site Certification Guide, DOE/CAO-95-2119, U.S.
Department of Energy, Carlsbad Area Office, Carlsbad, NM, 1995.
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-103
7-09-99
IV. K.(2) Data. Waste characterization data, container information, and
generation, storage, treatment, and transportation information for
low-level waste shall be transferred with or be traceable to the waste.
Objective:
The objective of this requirement is to establish and maintain information about the characteristics
of low-level waste and the waste containers to ensure that sufficient information to support
management of waste in a manner that is protective of workers, the public, and the environment is
always available.
Discussion:
The Radioactive Waste Management Manual, assigns the Field Element Manager the
responsibility of ensuring development and approval of a program that addresses the
responsibilities of waste generators (DOE M 435.1-1, Section I.2.F.(7)). The generator
requirements are to address hazards associated with a waste management facility receiving
unexpected volumes or types of waste, or receiving waste that may not meet the applicable waste
acceptance requirements. Generator requirements address generation planning, waste
characterization, waste certification, and waste transfer. The requirement for traceability of data
addresses the hazards associated with transferring low-level waste without providing or
maintaining adequate information about the container and its content. Establishing and
maintaining the identity of the waste, as well as maintaining controls based on the waste’s
hazards, are necessary for its safe transfer and subsequent management. Acquisition of
information about the waste is addressed in the guidance on Waste Characterization (DOE M
435.1-1, Section IV.I). Certification that waste is ready for transfer (i.e., meets the waste
acceptance requirements and transportation requirements) is discussed in the guidance on Waste
Certification (DOE M 435.1-1, Section IV.J). Maintenance of documentation regarding transfer
of waste is discussed later in this section of guidance.
In the process of developing DOE O 435.1 and DOE M 435.1-1, transfer was identified as the
activity in the life-cycle management of waste with the greatest potential for loss of information
about containers of waste, and the associated loss of adequate waste management controls needed
to avoid exposure or release of radioactivity. Therefore, when waste is transferred, the waste
characterization and container data must be transferred or available to the new “owner” (i.e.,
responsible waste manager) of the waste.
Section 501
Example: A liquid low-level waste is being transferred to a treatment facility for
solidification. The waste was characterized and the waste characterization information
listed on the waste certification statement. Although the waste met the waste acceptance
criteria for the treatment facility and an authorization to make the transfer was granted,
Chapter IV - Low-Level Waste Requirements
IV-104 DOE G 435.1-1
7-09-99
the characterization information was not transmitted before or in conjunction with the
waste transfer. Due to storage limitations at the treatment facility, the drums of waste
were placed in an unheated staging area. After a three days of below freezing weather, it
was noted that the drums were bulging and split. Had the characterization information
been documented and transferred with the waste, treatment facility personnel would have
known it was an aqueous waste and would have imposed controls on the waste to protect
it from freezing conditions.
Sufficient information about the container in which waste is packaged needs to be provided to the
storage, treatment, or disposal organization to which waste is transferred to ensure that the
containers are handled safely.
The information about the container is supported by and traceable to the more detailed container
procurement information. The organization that procures the container is responsible for properly
documenting the essential information regarding the procurement. The information needs to be
maintained so questions about adequacy of the container for its originally intended or alternate
uses can be assessed and to answer questions about subsequent procurements. Information
documented concerning the procurement of waste containers includes:
C Purpose of the container;
C Container performance requirements;
C Purchase specifications; and
C Manufacturer certifications verifying performance to purchase.
The information concerning the purpose of the container includes the designed service life, the
environments for which the container was designed and is compatible with, and other information
necessary to allow proper use of the container. The procurement information includes vendor
information, product specifications, lot or serial number information, and other procurement
information necessary to document the container purchased.
The detailed procurement data about containers can be, but do not have to be, transferred at the
time waste is transferred. As long as the records are retrievable and can be correlated to the
waste containers, it is acceptable for an organization transferring waste to maintain the records.
The type of container information that should be provided upon transfer of containers of waste
will depend on the type of waste and subsequent waste management steps. Typically, the
information includes the following:
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-105
7-09-99
• container size and type - generally this would be the container that is providing the
primary containment of the waste (e.g., DOT 7A 55-gallon drum, standard waste
box, or DOT 7A 80-gallon overpack);
• container enhancements - additional items that have been added to the primary
container to facilitate container performance (e.g., shielding, liners, plastic bags,
absorbents);
• lifting limitations - allowable and/or unallowable lifting points and methods; and
• load limitations - based on the physical characteristics, the maximum number of
containers or weight that can be placed on top of the waste container.
Section 502
When waste is initially placed in the container, the organization packaging the waste documents
and manages the information regarding its characteristics (e.g., radioisotopic inventory, total
activity, radiation dose, waste form). When the container of waste is physically transferred or the
ownership has changed, the information regarding the waste and container must be provided or
made available to the organization that acquires responsibility for the waste. A transfer is
considered to have occurred if the waste is physically moved from one location to another or if
there is a change in responsibility for the waste.
The following waste container characterization data are typically provided with the transfer of
low-level waste:
• physical and chemical description of waste (use of item description code or waste
stream identifier, if applicable);
• radiological inventory (see guidance on Waste Characterization);
• gross weight;
• volume percent utilized;
• fixed and removable surface contamination (alpha and beta/gamma);
• surface dose rate;
• tamper-indicating device number; and
• thermal power.
Chapter IV - Low-Level Waste Requirements
IV-106 DOE G 435.1-1
7-09-99
Example: Building 2000 is undergoing a facility cleanout that involves the
decontamination of building surfaces and the removal of excess processing equipment.
The organization responsible for the facility identifies two types of waste containers to be
used, 55-gallon drums for small items, personnel-protective clothing, and contamination
control waste, and standard waste boxes for larger pieces of equipment. The job is
managed such that one operator is responsible for logging each piece of waste put into
the containers. Upon filling a waste drum or box, the container is closed, and a
tamper-indicating device is installed. Radiological Services personnel perform
radiological surveys of each container of waste and record the data. The authorized
waste certification official uses the data recorded on the waste log and survey sheets,
supplemented with radiological characterization data, weight data, and other
information to fill out a waste certification checklist. The checklist requires
identification of waste container data as discussed above. In accordance with site
procedures, the checklist is a piece of required paperwork that is to be provided to the
storage, treatment, or storage facility to which the waste is transferred.
This requirement needs to be implemented with consideration given to documentation
requirements imposed by other internal programs or external organizations such as the
Environmental Protection Agency or Department of Transportation. These other documentation
requirements, such as an EPA Uniform Hazardous Waste Manifest or a transportation bill of
lading, may include much of the waste container information that is provided to the storage,
treatment or disposal facility to which waste is transferred. Therefore, to the extent these other
documents have the appropriate information, they may be used to meet the requirement to convey
information about the waste being transferred to a subsequent waste management facility. If
documentation prepared to meet requirements of other programs or organizations is used, it may
need to be supplemented to provide any additional data on waste characterization and packaging
addressed in this guidance.
Section 503
Example: Mixed low-level waste is being sent from one site to another for storage. Since
the waste is regulated under RCRA, a Uniform Hazardous Waste Manifest is prepared as
required by 40 CFR Part 262. The manifest includes information about the physical and
chemical characteristics of the waste, the container type, and container weight. The site
has developed a ‘Radiological and Supplemental Characteristics Data Sheet’ to provide
additional information about the containers of mixed waste. The data sheet provides
additional information about the radiological inventory, surface dose rate, surface
contamination, fissile material content, number of the tamper-indicating device installed
on the waste containers, load limitations, and handling limitations. Between the two
documents the storage facility is provided enough information so they can safely manage
the waste.
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-107
7-09-99
Compliance with this requirement is demonstrated if there are procedures requiring that
characterization and container data be provided and maintained for each low-level waste transfer
and documented records of transfers show that the information is being provided.
Supplemental References:
1. EPA. Standards Applicable to Generators of Hazardous Waste, 40 CFR Part 262, U.S.
Environmental Protection Agency, Washington, D.C.
Chapter IV - Low-Level Waste Requirements
IV-108 DOE G 435.1-1
7-09-99
IV. L. Packaging and Transportation.
The following requirements are in addition to those in Chapter I of this Manual.
(1) Packaging. If containers are used:
(a) Low-level waste shall be packaged in a manner that provides
containment and protection for the duration of the anticipated
storage period and until disposal is achieved or until the waste has
been removed from the container.
(b) When waste is packaged, vents or other measures shall be provided if
the potential exists for pressurizing or generating flammable or
explosive concentrations of gases within the waste container.
(c) Containers of low-level waste shall be marked such that their contents
can be identified.
Objective:
The objective of these requirements is to ensure that when low-level waste is packaged, the
container selected is adequate to contain the waste and limit radiation exposure for the entire time
the waste is in storage, and to ensure that the container can be correlated to necessary information
on its contents. The first subrequirement is to ensure the selection of a container for waste based
on the life-cycle of the waste so that there will not be unnecessary repackaging of waste. The
second subrequirement is to prevent the build up of pressure or concentrations of gases that could
cause a loss of waste confinement. The third subrequirement is to ensure that it is possible to
identify the contents of the container of waste during storage and when the waste is removed from
storage for treatment or disposal without having to open the container.
Discussion:
The need for packaging requirements specific to waste management concerns evolved from the
development of DOE O 435.1, and past experience in low-level waste transportation. The safety
and hazards analysis conducted in support of the Order and Manual development identified loss of
confinement of a waste container as a potential hazard affecting worker safety and releases to the
environment. In addition, the inability to associate a container with data on the contents was
identified as a situation that would result in unnecessary worker exposure due to the need to re-
characterize the waste. Mitigation of each of these concerns can be achieved through proper
packaging and compliance with the requirements of this section.
Section 504
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-109
7-09-99
An analysis of existing requirements affecting the packaging of waste identified the Department of
Transportation (DOT) regulations (49 CFR) and the DOE Orders, DOE O 460.1A and DOE O
460.2 as sources of packaging requirements (see DOE M 435.1-1, Section I.1.E.(11)) .
Generally, the DOT requirements apply to offsite shipments and any other transport on publicly-
accessible roads. Packaging and Transportation Safety (DOE O 460.1A) invokes the DOT
requirements, or documented requirements providing equivalent safety, for onsite shipments.
These regulations require the use of DOT Type A or Type B packaging (depending on
radionuclide content) for DOE waste shipments. DOE 460.1A also establishes the means and
approval authority for qualifying packaging as Type A or Type B. Departmental Materials
Transportation and Packaging Management (DOE O 460.2) includes DOE policies and
requirements that supplement the DOT regulations. Requirements from DOE O 460.2 relevant to
waste packaging include the inspection of waste shipments upon receipt, provision of data to the
Department’s Packaging Management Plan, and performance of routine assessments of
transportation and packaging operations.
While the DOT requirements and DOE packaging and transportation requirements were
considered adequate for shipping waste, they were not considered sufficient to address the other
low-level waste management concerns associated with long-term storage or with selecting and
packaging waste based on the entire waste management life cycle.
The life-cycle management of low-level waste may involve the packaging of waste followed by a
protracted storage period while awaiting disposal. Selection of a container (i.e., a receptacle and
any other components or materials necessary for the receptacle to perform its required
containment function) needs to account for all waste management steps expected prior to and
including disposal. Therefore, the container needs to meet the requirements for transportation,
storage, and eventual disposal (to the extent the disposal requirements are known). Alternatively,
if waste treatment is required, the container needs to be adequate to contain the waste during
storage and allow the waste to be transferred to the treatment facility where it might be removed
from the container prior to treatment. Subsequent to treatment, packaging of the treated residues
is based on meeting all of the requirements of the remaining waste management steps. Selection
of a container that fulfills the needs of all subsequent waste management actions ensures waste
confinement and eliminates the need to repackage the waste, thus avoiding potential exposure to
workers.
Example: The Site X disposal facility will be the recipient of some low-level waste that is
being generated at Site Q. The waste will be stored for 3 months at Site Q, transported to
another facility where it will be consolidated with other low-level waste, stored for
Chapter IV - Low-Level Waste Requirements
IV-110 DOE G 435.1-1
7-09-99
another 3 months, then transported to Site X for disposal. Containers that will be found
acceptable for disposal at Site X were determined to be appropriate for all management
steps; therefore, upon generation, the low-level waste can be immediately placed in a Site
X acceptable container and will not need to be repackaged during any subsequent
management step.
Section 505
Containment and Protection. Low-level waste must be adequately contained and the container
protected from conditions that could cause container degradation. Inadequate containers or
container degradation could lead to failure and result in the spread of contaminated materials,
worker exposure, or the non-acceptance by a receiving facility. When selecting low-level waste
containers, consideration must be given to the conditions to which the container will be subjected.
If waste is to be stored outside for an extended period and subjected to the natural environment,
the container must be made of materials that have been demonstrated to maintain integrity during
these conditions.
Example: Bulk contaminated soil and debris was packaged in wooden boxes and stored
outside for up to four years. The boxes degraded to the point that they no longer served
as containment and were literally falling apart. Due to the selection of inadequate
containers for the time of storage and storage conditions, the waste had to be repackaged
prior to transfer and the used wooden boxes also managed as low-level waste.
Low-level waste must not be incompatible with the container in which it is placed. The physical,
chemical, and radiological attributes of the waste need to be considered when selecting a
container. Container integrity must not be jeopardized due to the size, shape, or weight of objects
contained in the waste. Containers need to be compatible with any unusual chemical
characteristics, water content, and pH of the waste. If absorbent or other materials are used to
bind liquids contained in the waste, the resultant waste matrix must not be capable of spontaneous
combustion, decomposition, explosion, liquid desorption, or otherwise have the ability to affect
the integrity of the containers in any way (see Storage guidance IV.N).
Shielding may also be required to provide protection to workers who handle the waste containers
or who are responsible for monitoring low-level waste in storage. The necessity for shielding is
considered at the time of packaging so that the shielding can be integrated into the waste
container before waste is present if internal shielding is acceptable to the storage, treatment, or
disposal facility. Alternatively, the storage configuration may be designed to provide the
necessary shielding. If shielding is required, consideration needs to be given to the use of
materials that do not have the possibility to become a mixed waste if contaminated by the
radiological constituents. Guidance for DOE M 435.1-1, Section IV.K.(1) discusses the selection
and procurement of low-level waste containers and the necessary information that is documented.
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-111
7-09-99
Example: A new facility generates high-activity low-level waste sludges with caustic
properties and multiple fission products requiring remote-handling. The container
selected has been designed to withstand chemical attack from the sludge, includes
sufficient absorbent to ensure there are no free liquids, and incorporates shielding. The
container provides protection of workers, the public, and the environment during its
intended service life.
The anticipated service life needs to be considered when selecting a container for low-level waste.
A determination of the anticipated storage time, environment, and location (waste acceptance
criteria) is essential to selecting the proper waste container. For low-level waste that does not
have an identified path to disposal, the waste container may need to be designed to remain
effective for an extended and/or indefinite storage period.
Section 506
Example: A site needs to repackage a small quantity of low-level waste with no identified
path to disposal. A plan has not yet been completed for resolving the disposal issues.
The selected container has been designed to withstand the effects of time and last a
minimum of 50 years if stored indoors.
When selecting containers for low-level waste, consideration needs to be given to the full life-
cycle of the waste, with a goal of packaging the waste only once. The selected waste container
needs to be compatible with transportation requirements and the waste acceptance criteria of the
facilities expected to manage the waste. Containers can also be designed and utilized in storage
and treatment facilities that allow for direct disposal. Prior to packaging, the consideration of the
management steps the waste will go through should minimize risks associated with handling and
repackaging the waste. The waste container maintains structural integrity and containment until it
is disposed of or the waste has been removed from it. DOE low-level disposal sites have
generally identified several DOT-certified drums and standard waste boxes in their waste
acceptance criteria documentation as containers that are acceptable for handling and disposal at
their sites. These drums and boxes may be considered for all management steps to facilitate
disposal if they are compatible with the interim management steps the waste will undergo.
Example 1: A site selected a certain 4 x 4 x 8-ft box as the container for high volumes of
miscellaneous low-level waste that was to be stored for a few years prior to disposal.
However, because consideration was not given to the entire life cycle for management of
the waste, site personnel did not take into account that the boxes were not acceptable at
the disposal facility which was to dispose of the waste. Consequently, in order to make
the waste acceptable for disposal, site personnel will have to repackage the waste and
may have to treat the 4 x 4 x 8-ft boxes as low-level waste as well.
Example 2: A requirements analysis was performed on the life-cycle plan for a specific
new low-level waste stream that will generate odd-sized solid debris. The analysis
Chapter IV - Low-Level Waste Requirements
IV-112 DOE G 435.1-1
7-09-99
indicated that a standard waste box could be used to meet all the requirements for
transportation, as well as satisfy the storage and disposal facilities waste acceptance
requirements.
To ensure that the waste container performs as expected, the following need to be considered
when placing waste in the packaging:
• Containers free of deformations or imperfections that may cause a loss of container
integrity before the designed lifetime.
• Waste placement in a manner that does not adversely affect the integrity of the
waste container.
• Containers utilized such that void space within the container is minimized,
although care should be taken to avoid exceeding weight or other limitations
identified through consideration of the life-cycle management process.
• Waste container labels and markings permanently applied.
The selection of the container is influenced by the storage conditions, storage duration, and the
monitoring expected for the waste containers. Ensuring waste containers provide confinement for
their expected storage life is therefore dependent on ensuring an appropriate storage environment
consistent with the container characteristics. Storage of low-level waste containers is addressed
in the guidance for DOE M 435.1-1, Section IV.N.
Section 507
Vents. The use of vents or another mechanism for controlling the accumulation of gases and/or
build up of pressure within the waste container needs to be considered when low-level waste is
packaged or repackaged. Based on the characterization of the waste, a determination is made as
to whether the waste contains materials which could evolve gases (e.g., through decomposition of
organics or radiolysis). The life cycle management of the waste container is also considered from
the standpoint of exposure to environmental conditions that could cause atmospheric pressure in
the waste container to vary enough from the ambient pressure so as to cause a breach of
confinement. Either of these safety-related conditions may result in a decision to use vent clips,
permeable gaskets, or other means for controlling the potential hazards.
Example: Steel boxes are being used to store, transport, and dispose of low-level waste.
The inherent design of the steel box eliminates any possibility for it to become
pressurized or otherwise generate hazardous concentrations of gases.
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-113
7-09-99
If vents are warranted, waste managers need to consider installation of vents or other mitigating
measures at the time the waste is packaged. By installing the vents at the time waste is packaged,
unnecessary waste container handling and the associated radiation exposure can be avoided.
For waste containers currently in storage, a waste manager needs to consider the safety hazards
associated with the containers and install vents as appropriate to mitigate hazards. What action
may be appropriate depends on the immediacy of a hazard associated with the waste containers.
If hazardous concentrations of gases could be generated (e.g., based on similarity of waste
container contents to waste streams known to be a problem, or physical indications such as
bulging drums), action needs to be taken to prevent an accident while the waste is in storage. If
there is no perceived imminent threat, the appropriate time to install vents or apply mitigating
measures may be when the waste containers are being prepared for transfer to the next step in the
waste management cycle.
Example: Low-level waste sludge is currently stored in sealed steel drums which are
scheduled to be disposed shortly. Analysis of the characterization information for the
waste indicates the possibility for the generation of flammable gases. Several
representative drums are sampled for the suspect gas and an analysis is performed.
Based on the low concentrations found it is determined that the drums do not need to be
vented.
Marking and Labeling. The marking and labeling of low-level waste containers need to be done in
a manner that allows traceability to the documentation of the waste characteristics and container
information. The marking or labeling needs to be applied in a manner that will be visible if the
waste package is on the outside of a storage or transportation array. For a 55-gallon drum, this is
generally accomplished by placing the marking or labeling about every 120 degrees around the
outside of the drum. For a waste box, acceptable labeling can be accomplished by placing labels
on each side of the box. Waste package identification should be in medium to low density Code
39 bar code symbology in accordance with ANSI/AIM-BC1-1995. Bar coding is to be a
minimum of 1 inch high and should be accompanied by alphanumeric characters at least ½ inch
high. Durability and readability of marking and labeling is one of the items included in the
inspection program for waste in storage (see guidance for DOE M 435.1-1, Section IV.N.(1)(d)).
Section 508
Example: A waste generator is packaging waste in accordance with its site certification
program that successfully certifies low-level waste for disposal at the Nevada Test Site.
In accordance with the NTS certification procedures, labels meeting ANSI/AIM-BC1
1995 that contain the waste stream identifier, shipment identifier, and unique package
identifier are placed in two locations in accordance with Appendix C of the NTS WAC,
Rev.1. This satisfies the marking and labeling requirement.
Waste characterization and the container documentation is to be associated with each individual
container of waste. Guidance related to documentation is discussed in guidance for Waste
Chapter IV - Low-Level Waste Requirements
IV-114 DOE G 435.1-1
7-09-99
Transfer (DOE M 435.1-1, Section IV.K). The documentation needs to include the aspects
relative to container selection including, the designed service life, the environments that the
container was designed for and is compatible with, and other information necessary to allow
proper use of the container.
Compliance with the packaging requirement is demonstrated by: (1) procedures which document
proper packaging protocols; and (2) no trends of routine repackaging of low-level waste that is
packaged after issuance of DOE O 435.1. Successful performance of this requirement is also
demonstrated by a record of containers for which failure has not routinely occurred under
management conditions. It is recognized that there may be failed containers for waste previously
placed in storage. For those containers, the goal is to only have to repackage the waste one time
after it is retrieved and characterized. Further, acceptable performance is demonstrated by
containers of waste having marking and labeling that allows correlation with waste
characterization data and container information.
Supplemental References:
1. DOE, 1995. Departmental Materials Transportation and Packaging Management,
DOE O 460.2, U.S. Department of Energy, Washington, D.C., September 7, 1995.
2. DOE, 1996. Packaging and Transportation Safety, DOE O 460.1A , U.S. Department of
Energy, Washington, D.C., October 2, 1996.
3. DOT. Shippers-General Requirements for Shipments and Packagings, 49 CFR Part 173,
U.S. Department of Transportation, Washington, D.C.
4. ANSI/AIM, 1995. Uniform Symbology Specification Code 39, ANSI/AIM-BC1-1995,
American National Standards Institute, Automatic Identification Manufacturers,
Pittsburgh, PA, August 16, 1995.
IV. L.(2) Transportation. To the extent practical, the volume of waste and
number of low-level waste shipments shall be minimized.
Objective:
The objective of this requirement is to reduce the risk associated with low-level waste
management by reducing the number of miles traveled in transporting waste. This is to be done
by the efficient use of waste containers, minimizing the volume of waste which requires shipment,
and optimizing shipping plans and schedules.
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-115
7-09-99
Discussion:
Section 509
The need for transportation requirements specific to waste management concerns was evaluated
in the development of DOE O 435.1, Radioactive Waste Management and the Radioactive Waste
Management Manual (DOE M 435.1-1). An analysis of existing requirements affecting waste
transportation identified the Department of Transportation (DOT) regulations (49 CFR) and the
DOE Orders, DOE O 460.1A and DOE O 460.2 (see DOE M 435.1-1, Section I.1.E.(11)), as
sources of applicable requirements. Generally, the DOT requirements apply to offsite shipments.
Packaging and Transportation Safety (DOE O 460.1A) invokes the DOT requirements, or
documented requirements providing equivalent safety, for onsite shipments. Departmental
Materials Transportation and Packaging Management (DOE O 460.2) includes DOE policies
and requirements specific to DOE that supplement the DOT regulations. Requirements from
DOE O 460.2 relevant to low-level waste transportation address development of a Transportation
Plan for high-visibility shipment campaigns, use of the Department’s Transportation Tracking and
Communications System, and administrative requirements. Additionally, for waste exceeding
Type A quantities of radioactive material per DOT requirements, notification of the expected date
of arrival is to be given to the site to which the waste is being shipped, and if the waste is not
received on the expected day, notification of the shipper is mandated.
The DOT requirements and DOE packaging and transportation requirements were considered
adequate for ensuring safe transportation of the waste. However, recognizing that one of the
higher risks associated with waste management is from the number of miles traveled in
transporting waste, low-level waste shipments should be minimized to reduce worker exposure,
risk, and cost. This can be achieved, in part, by ensuring that all containers or primary packagings
(e.g., drum or waste box) are used to capacity, and that transportation systems are efficiently
utilized. Reaching the capacity (volume or weight) of the waste container should be a goal of
every waste packaging operation. Containers should be filled so as to minimize void volume and
allow closure, without exceeding its container weight capacity or compromising its integrity, or
waste acceptance criteria of the storage, treatment, or disposal facility.
Example: Miscellaneous low-level waste such as personnel protective equipment,
contaminated tools, and paper and plastic sheeting are being packaged in 55-gallon
drums for eventual disposal. Site personnel use a compactor to maximize the amount of
waste placed in the drum. Administrative controls ensure that drum weight limits are not
exceeded.
The same goal applies to transport systems, where waste containers should be held and
accumulated until a sufficient number of packages is available to make cost-effective use of the
transportation system. Additional guidance on accumulation of packages for cost-effective
transportation (i.e., staging) is addressed under guidance on storage (DOE M 435.1-1, Section
IV.N).
Chapter IV - Low-Level Waste Requirements
IV-116 DOE G 435.1-1
7-09-99
The distance low-level waste is transported, and the number of times waste is physically handled
is directly related to the risk of release or exposure. As part of the planning and documentation
concerning the life-cycle management of low-level waste, the Site-Wide Radioactive Waste
Management Program should seek to reduce the number of times the waste is handled or
otherwise transported. Site low-level waste management programs need to ensure that both on-
site and off-site transport and handling is minimized.
Section 510
Example 1: A site that generates small quantities of low-level waste performed an
optimization study and determined the nominal volume of waste that needed shipment
off-site for the year. Staging the waste prior to transport reduced the number of
shipments and allowed the transfer of the waste to occur during the summer when road
conditions were best.
Example 2: A waste management operation on a large DOE reservation generates low-
level waste that can only be fully characterized by facilities located elsewhere on the
reservation. Staging the waste and transferring it during off-peak traffic hours reduced
the number of shipments across publicly-traversed roads on the reservation, and helped
minimize the risk to the public.
Low-level waste transportation needs will be specific to each site. Availability of treatment,
storage, and disposal capabilities, as well as funding profiles, will influence the need to ship
low-level waste. In this requirement, the term “to the extent practical” means that site personnel
have latitude in making decisions regarding what is practical for their particular situation. This
requirement is not intended to force decisions that are contrary to safe waste management,
regulatory compliance, or cost-effectiveness. Detailed and documented planning that provides the
rationale for a waste shipment regimen is the best way to balance this requirement with site-
specific realities.
Example: A site-specific evaluation was performed to support a recommendation on
either building low-level waste storage capacity or maintaining the current number of
small off-site shipments. The evaluation indicated that concerns over building the
storage facility outweighed the potential to minimize shipments and the current shipment
regimen was continued. The evaluation was included as part of the Site-Wide Waste
Program documentation.
Transportation over the nation's highways and railways results in the most direct contact between
the Department’s radioactive waste and the general public, stakeholders, and representatives of
States, Tribes, and local government organizations. These groups are primarily concerned with
the shipment of these materials through states, cities, and neighborhoods. Efforts to minimize the
volume and number of low-level waste shipments will help alleviate their concerns.
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-117
7-09-99
Compliance with this requirement can be demonstrated by a combination of site procedures
directing the efficient use of waste container capacity and documentation showing that low-level
waste shipments are systematically planned and optimized to the extent practical.
Supplemental References:
1. DOE, 1995. Departmental Materials Transportation and Packaging Management,
DOE O 460.2, U.S. Department of Energy, Washington, D.C., September 7, 1995.
2. DOE, 1996. Packaging and Transportation Safety, DOE O 460.1A, U.S. Department of
Energy, Washington, D.C., October 2, 1996.
3. DOT. Shippers-General Requirements for Shipments and Packagings, 49 CFR Part 173,
U.S. Department of Transportation, Washington, D.C.
Chapter IV - Low-Level Waste Requirements
IV-118 DOE G 435.1-1
7-09-99
IV. M. Site Evaluation and Facility Design.
The following requirements are in addition to those in Chapter I of this Manual.
(1) Site Evaluation. Proposed locations for low-level waste facilities shall be
evaluated to identify relevant features that should be avoided or must be
considered in facility design and analyses.
Section 511
Objective:
The objective of this requirement is to ensure that a suitable site location is selected and relevant
features of the proposed site that should be included in the design of a low-level waste
management facility are evaluated so the facility can be appropriately designed to provide
protection to the public, workers, and the environment, and to identify features of the site that
would be detrimental to this goal so they can be avoided.
Discussion:
DOE M 435.1-1 includes the requirement in Chapter I, General Requirements and
Responsibilities, to adhere to the requirements contained in DOE O 420.1, Facility Safety, and
DOE O 430.1A, Life Cycle Asset Management, in site evaluation and facility design. In the
development of DOE M 435.1-1, additional requirements for site evaluation were considered to
be necessary to ensure that full consideration of the beneficial or detrimental aspects of a site are
considered to assure that the site location is adequate and to form a sound basis for facility design
that is protective of the workers, the public, and the environment. The importance of site
evaluation was established by the awareness that the characteristics of the site contribute to a
large extent to the ability of the facility to function as planned and in the minimization of the
transport of radionuclides to members of the public and the potential contamination of the
environment.
The subrequirements included in this section are intended to ensure that sites selected for
low-level waste management facilities are properly evaluated, especially sites for low-level waste
disposal, and that sites are not used for which detrimental aspects of the site cannot adequately be
designed against without still compromising the protection of the public, workers, or the
environment. Guidance on subrequirement IV.M.(1)(a) discusses the minimum specific
characteristics of sites for low-level waste management facilities that should be evaluated.
Specific characteristics of a site for a low-level waste disposal facility are identified in the
requirement that must be considered. Guidance on selection of a suitable site for new disposal
facilities is also included.
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-119
7-09-99
Guidance on subrequirement IV.M.(1)(b) provides information on those aspects of a site for
which adequate protection cannot be provided through facility design, and guidance on
subrequirement IV.M.(1)(c) provides detailed guidance on evaluation of sites for low-level waste
disposal facilities that provide for additional contributions to meeting the goals and objectives
contained in this Order and Manual for disposal of low-level waste. Site evaluation includes the
selection and characterization of potential sites, which are necessary steps in the development of a
new low-level waste management facility. Selection of sites for DOE low-level radioactive waste
management facilities is constrained to those federal lands owned and managed by DOE. Within
DOE reservations, the process of selecting sites has the purpose of identifying the best location
with consideration of those natural features which are desirable for the facility. Characterization
of a selected site has the purpose of developing the necessary data to support a site-specific
design of the facility.
Section 512
The site selection process is likely to vary from one DOE site to the next, because of substantial
differences in geology, hydrology, meteorology, ecology, and socioeconomics. Similarly, the
interests of stakeholders, as they are involved in the process, are likely to influence the issues to
be addressed in site selection, and vary from one DOE site to the next. Site characterization is a
program of investigations and tests to determine the properties of the site that are important to the
design of the facility and the analysis of facility and site performance. While generalized program
elements are defined in this guidance, details of the program can only by derived from site-specific
and facility-specific considerations.
Example: New disposal facilities are being considered at the Hanford Reservation and
Savannah River Site. The Savannah River Site evaluation includes the evaluation of
surface water, while the Hanford Reservation site evaluation does not. Likewise, the
Hanford Reservation site evaluation includes the consideration of wind erosion, while the
Savannah River Site evaluation does not.
Compliance with this requirement is demonstrated by proposed site evaluations that are
comprehensive, defensible, and provide sufficient data for facility design, other required analysis,
and for avoiding site characteristics that could compromise objectives for safety and protection of
the environment, and by the inclusion of the evaluations in the radioactive waste management
basis documentation for the facilities.
Supplemental References:
1. DOE, 1995. Facility Safety, DOE O 420.1, U.S. Department of Energy, Washington,
D.C., October 13, 1995.
2. DOE, 1998. Life Cycle Asset Management, DOE O 430.1A, U.S. Department of Energy,
October 14, 1998.
Chapter IV - Low-Level Waste Requirements
IV-120 DOE G 435.1-1
7-09-99
IV. M.(1) Site Evaluation. Proposed locations for low-level waste facilities shall
be evaluated to identify relevant features that should be avoided or
must be considered in facility design and analyses.
(a) Each site proposed for a new low-level waste facility or
expansion of an existing low-level waste facility shall be
evaluated considering environmental characteristics,
geotechnical characteristics, and human activities, including
for a low-level waste disposal facility, the capability of the site
to demonstrate, at a minimum, whether it is:
1. Located to accommodate the projected volume of waste
to be received;
2. Located in a flood plain, a tectonically active area, or in
the zone of water table fluctuation; and
3. Located where radionuclide migration pathways are
predictable and erosion and surface runoff can be
controlled.
Objective:
The objective of this requirement is to ensure that specific evaluations are performed as part of
the evaluation of a site for a low-level waste management facility, and that the evaluations are
appropriately considered in the final site selection and layout, and the design and construction of
the facility. In particular for low-level waste disposal facilities, the objective of this requirement
includes ensuring that particularly important site attributes have been evaluated.
Discussion:
This subrequirement identifies the primary site characteristics that must be evaluated in the
process of establishing a new low-level waste storage, treatment, or disposal facility, or an
expansion of an existing facility, so that the features of the site can be thoroughly understood, that
a determination can be made that the site is suitable to support the facility, and so the relevant
features of the site can be appropriately factored in the facility design. Each of the items is
discussed in the sections that follow.
Section 513
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-121
7-09-99
Some of the site characterization data and evaluations specified in the requirement may already or
are going to be included in documents required for authorization of facility construction and
operation, or documented separately. These documents include analyses prepared in accordance
with the National Environmental Policy Act, the Preliminary Safety Analysis Report, the
Performance Assessment and Composite Analysis (for disposal facilities), and others. If data
already exist or are being prepared for additional documentation or other purposes, then sufficient
references to other documents should be used in establishing the suitability of the site and for
inclusion in the design of the facility.
Some of the site characteristics and how they affect design are more significant if the proposed
facility is a disposal facility. Specific minimum site attributes are listed in the requirement which
must be thoroughly evaluated and included in the disposal facility design. These site attributes are
also critical in determining the suitability of the site for a disposal facility. Guidance on these site
criteria are discussed under Site Selection for a Disposal Facility.
Environmental and Geotechnical Characteristics. The basic environmental and geotechnical
characteristics of a proposed site must be established to determine its suitability for the proposed
use, and so that basic parameters needed for the design of the facility are identified. Basic
elements of this characterization program include meteorology, surface water hydrology,
groundwater hydrology for both saturated and unsaturated media, geology, soils, water quality,
site stability, air quality, ecology, land and cultural resources, and socioeconomics. Field studies
should be performed so as to not compromise the integrity of the land to be dedicated to waste
management activities. The extent of investigation in each of these broad topic areas is dependent
on the site specific characteristics of the proposed site. Data collected during the site
characterization program need to reflect application of the data quality objectives (DQO) process
to ensure meaningful and wise use of resources. The characterization of the site is carried out in
accordance with the site’s quality assurance program, including maintaining records of data
collected. Documentation of the results of the site characterization program is not only needed
for use in design, but it also may serve a valuable purpose in fulfilling the requirements of the
NEPA process.
Design basis events need to be identified and assessed as to their potential impacts on the safe
operation of the facility. Design basis events are certain severe natural events that are estimated
and assumed to occur in order for their impact (or design loadings) to be imposed on the
proposed facility to ensure design of a safe facility. The establishment of the severity of the
events is called the design-basis event. A naturally occurring event that needs to be assumed for a
design basis event may be tectonic (seismic, volcanic, ground rupture), hydrologic or
meteorologic (storms, floods, hurricanes, tsunamis, seiches). Design basis events are typically
assumed to occur for both the operating condition (normal) and for accident conditions
(abnormal) to establish the envelope of potential hazardous situations that must be designed
against.
Chapter IV - Low-Level Waste Requirements
Section 514
IV-122 DOE G 435.1-1
7-09-99
Natural phenomena that may exist or that can occur in the region of a proposed site need to be
identified and assessed according to their potential effects on the safe operation of the facility.
The important natural phenomena that affect the facility design must be identified. These
phenomena are considered different than the design events described above in that these are not
severe events, rather they are normal active processes that are evaluated that may determine
simpler design items such as the material of construction for non-critical items such as ramps,
doorway overhangs, and covers for staged waste. Natural phenomena such as rainfall, snowfall,
wind direction and speed, erosion rates presence of faults, landslide areas, and other natural
events that could influence certain aspects of the design in addition to the design basis events
discussed above are evaluated. Records of events within the region, including their severity, need
to be evaluated for their reliability, accuracy, and completeness. Appropriate methods (including
conservatism) are adopted for evaluating site characteristics of the region and the current state of
knowledge about such events, and to select those external natural events, other than design basis
events, on which the design of the facility would be based.
Example: A new facility for treating low-level and mixed low-level waste is proposed for
a site in the northwest quadrant of the DOE site in Kansas. The particular region has
severe downpours during the summer months, so the design of the facility includes
drainage features to handle a severe rainfall of up to 4 inches per hour.
Human Activities. The region needs to be examined to identify past, present, and proposed man-
made facilities and activities that could affect the safe operation of the facility. Man-made
facilities or influences include such items as upstream dams and other alterations to drainage basin
features, mining, highway construction, housing and industrial development, or establishment of
protected areas or wilderness zones. Information regarding past, present, and potential
occurrences are collected and evaluated for reliability, accuracy, and completeness. Appropriate
methods (including conservatism) need to be adopted for evaluating the man-induced events
within the region and the current state of knowledge about such events to select those events on
which the design of the facility will be based.
Example 1: The projected improvements of a public highway through the Oak Ridge
Reservation could affect the groundwater hydrology associated with the a new disposal
facility, and should be evaluated.
Example 2: A proposed disposal facility is located upstream of a potential hydropower
dam site. The impoundment associated with the potential dam could raise the water table
underlying the site by 100 feet. The significance of this potential development should be
evaluated as part of the site evaluation.
The site of a proposed low-level waste management facility needs to be evaluated with respect to
the effects construction and operation of the facility may have on the populations and
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-123
7-09-99
environmental characteristics of the region, including the transportation of radioactive materials to
or from the facility. The evaluation is based on the population and environmental characteristics
of the region including:
1) the regional extent of external phenomena;
Section 515
2) present and future population distribution;
3) present and proposed land and water uses in the region;
4) any special characteristics that would influence the consequences of releases of
radioactive material during the life cycle of the facility.
The potential impact of the waste management facility construction, operation, and
decommissioning also need to be evaluated, considering both usual and unusual regional
characteristics.
Example: A new disposal facility is proposed to receive waste from other DOE sites.
The new facility will accept wastes delivered by truck with an anticipated receipt of 40
trucks per day. The capability of the existing road system of handling an additional 40
fully loaded trucks per day should be evaluated and include the potential increase in the
population in the nearby community.
Site Selection for a Disposal Facility. The process of site selection for a new DOE low-level
waste disposal facility is initially narrowed to the DOE reservation being considered for facility
development, and the direction of the process is toward identifying the best site within the
reservation. This is different from the way sites are selected for commercial low-level waste
disposal facilities. Sites for commercial facilities are selected from large geographic areas where
ownership of the land may be under private or public control. Site selection processes for
commercial facilities are directed toward identifying sites that meet site suitability requirements, as
defined in 10 CFR Part 61, Subpart D. For DOE site selection, rather than meeting suitability
criteria for a site, the process seeks a site which will contribute to meeting the performance
objectives and other specific technical requirements of DOE M 435.1-1. The requirement,
therefore includes minimum site attributes that must be evaluated to determine their respective
contributions towards meeting the performance objectives. This differing direction can lead to
DOE sites being selected that are located adjacent to or within lands previously contaminated, or
sites where existing characterization information supports the requirements of DOE M 435.1-1,
and the costs of characterization, design, construction, operations, and closure are minimized.
The site selection process is a formalized activity that is documented, reviewed and approved by
the DOE field organization and incorporates stakeholder interest to the extent appropriate. The
Chapter IV - Low-Level Waste Requirements
IV-124 DOE G 435.1-1
7-09-99
documentation of the site selection process needs to describe the method developed for selecting
sites and the criteria used as a basis for including or excluding sites. These criteria must include
the attributes listed in subrequirements (a), (b), and (c), at a minimum, and include additional site-
and facility-specific selection criteria that address specific attributes that are important to site or
facility operations. However, it is not intended that these criteria be used as exclusionary
conditions to eliminate a site from being considered, but instead provide a measure of evaluation
of the site’s contributions to performance of the disposal facility. Use of existing facilities on
DOE reservations should be considered to the extent practical. The minimum site selection
attributes in the subrequirements are the most critical items that must be evaluated in order to
respond to requirement IV.M.(1)(b) and IV.M.(1)(c). That is, these items are the most critical in
terms of attributes of a site that must be avoided or that need to be prevalent in order that there is
a reasonable contribution of the site towards achieving the performance objectives. As such, the
specific attributes are discussed further in the following sections of this guidance.
Section 516
The site selection process can and should be conducted using a reconnaissance level data base
which is comprised of existing studies and available information on the various features of
candidate sites within the DOE reservation. The data used in selecting a site need to be presented
or referenced to provide a reasonable basis for site characterization and design investigations.
The results of the site selection process lead to the identification of one preferred site for site
characterization. The documentation of the site selection process also provides a useful
contribution to the NEPA process, which must be addressed as part of the development of a low-
level waste disposal facility.
The basic steps to be included in a site selection process for a low-level waste disposal facility are
discussed in detail in the Nuclear Regulatory Commissions’s NUREG-0902, Site Suitability,
Selection, and Characterization: Branch Technical Position. For the purpose of site selection at
DOE reservations, these steps are:
C Identification of the region of interest, which is the DOE reservation;
C Screening the region of interest to identify potential sites;
C Screening of potential sites against a common set of criteria to identify a slate of
candidate sites; and
C Review the candidates sites in detail to identify a preferred site.
For DOE reservations, available information will likely be sufficient to complete these basic steps
in the site selection process. Additional information, in the form of feasibility studies, conceptual
designs, preliminary cost estimates, or performance evaluations can be useful in conducting the
last step in the site selection process. The preferred site is usually the only site that is subjected to
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-125
7-09-99
detailed site characterization. If the site characterization program identifies a significant and
unanticipated weakness, another candidate site could be considered for site characterization to the
extent necessary to justify a preferred site.
Example: A new disposal facility is considered at INEEL where the preferred site is
expected to have deep soil deposits and is located in close proximity to existing roads. A
drilling program is initiated to establish the local site characteristics, which reveal
shallow soil deposits. The preferred site is reconsidered and an alternative preferred site
is selected where soil deposits are thicker, but the alternative preferred site is located
further away from existing roads.
Compliance with this requirement is demonstrated for low-level waste storage, treatment, and
disposal facilities if the site evaluation comprehensively considers the environmental and
geotechnical characteristics of the site, the design basis events, external man-induced events, and
the effects of the low-level waste management facility on the region, and includes those features
and events in the design of the facility. Compliance with the requirement is demonstrated for low-
level waste disposal facilities if, in addition, the site evaluation comprehensively considers the
site’s capabilities in demonstrating whether it is located in a flood plain, tectonically active area,
or in the zone of water table fluctuation, and is located where the projected volume of waste can
be accommodated and where radionuclide migration pathways are predictable and erosion and
surface water runoff can be controlled. All analyses and justifications for evaluation and controls
must be part of the radioactive waste management basis for the facilities.
Section 517
Supplemental References:
1. NRC. Licensing Requirements for Land Disposal of Radioactive Waste, 10 CFR Part 61,
U.S. Nuclear Regulatory Commission, Washington, D.C.
2. NRC, 1982. Site Suitability, Selection and Characterization: Branch Technical
Position–Low-Level Waste Licensing Branch, NUREG-0902, U.S. Nuclear Regulatory
Commission, Washington, D.C., April 1982.
IV. M.(1) Site Evaluation. Proposed locations for low-level waste facilities shall
be evaluated to identify relevant features that should be avoided or
must be considered in facility design and analyses.
(b) Proposed sites with environmental characteristics, geotechnical
characteristics, and human activities for which adequate
protection cannot be provided through facility design shall be
deemed unsuitable for the location of the facility.
Chapter IV - Low-Level Waste Requirements
IV-126 DOE G 435.1-1
7-09-99
Objective:
The objective of this requirement is to avoid sites for which postulated severe natural events
cannot be protected from adequately through design and construction and to continue to have
assurance that the public safety and health will be protected and the impacts on the environment
will continue to be minimized.
Discussion:
This subrequirement provides a performance-based requirement on the use of facility design for
meeting the public, worker, and environmental protection requirements of DOE O 435.1 and
DOE M 435.1-1. The site, in most cases, functions as the primary barrier for protection against
the hazards from the low-level waste management facility during the severe events that are
characterized for the site. Engineering alone generally should not be relied upon to overcome
weaknesses that are of a severity such that the site itself cannot be considered a contributor to or
the primary barrier against the impacts of the design basis events. Facility design and engineering
must, together with environmental and geotechnical characteristics, provide adequate protection
of workers, the public, and environment in accordance with the performance objectives stated in
DOE O 435.1.
For a proposed low-level or mixed low-level waste disposal facility, the determination that a
postulated design basis event is so severe or a site is so weak that no amount of engineering or
design can make the proposed site suitable is likely to require consideration of different events and
a longer period of time than other types of waste management facilities. This is because the
disposal facility must perform at a high level of performance for such a long time due to the
hazards present from the disposed waste (especially in comparison to the planned short life of a
storage facility, for example), and the delicate nature of the behavior of ground water and other
geotechnical phenomena known to affect waste disposal sites. Additional detailed guidance on
meeting this DOE M 435.1-1 requirement for low-level waste disposal facilities is discussed
below under guidance for DOE M 435.1-1, Section IV.M.(1)(c).
The selection, characterization, and evaluation of the proposed site for a low-level waste
management facility may identify external events which cannot be adequately addressed by design
to achieve the goals and objectives of the requirements of DOE O 435.1.
Section 518
Example: Area A has been selected for more detailed evaluation for construction of a
new storage facility and low-level waste disposal facility. Flooding within Area A is
determined to be too severe to consider any design adequate for providing reasonable
assurance that the performance objectives will continue to be met for the time of
compliance currently used (1000 years) for a low-level waste disposal facility. However,
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-127
7-09-99
adequate facility design controls are identified which would allow construction and
operation of the proposed storage facility.
For proposed sites that cannot meet the requirements of the Order and Manual Chapter IV, the
requirement states that the preferred site for the facility must be declared unsuitable. The specific
determinations of areas unsuitable for low-level waste management facilities should be thoroughly
documented along with justifications for this conclusion. This documentation is retained as part
of the evaluation of the site which is ultimately selected for full site characterization and
development.
If no areas of a DOE reservation can be found that are suitable for establishment of a new
low-level waste management facility, the Field Element Manager may need to conclude that the
management of low-level waste at the DOE reservation is not appropriate, and shipment of waste
to another DOE site or to a commercial site for treatment, storage, and/or disposal is appropriate.
This information needs to be factored into the life-cycle planning information contained in the
Site-Wide Radioactive Waste Management Program and into the Complex-Wide Radioactive
Waste Management Program as soon as practical.
Compliance with this requirement is demonstrated if design basis external events are evaluated
and a reasonable determination is made that proposed sites for low-level waste management
facilities are either suitable or unsuitable based on the protection afforded by the proposed site
and from facility design to address design basis external events. The analyses and documentation
of the determination must be included as part of the facilities’ radioactive waste management
bases.
Supplemental References:
1. NRC, 1982. Site Suitability, Selection and Characterization: Branch Technical Position
-Low-Level Waste Licensing Branch, NUREG-0902, U. S. Nuclear Regulatory
Commission, Washington, D.C., April 1982.
IV. M.(1) Site Evaluation. Proposed locations for low-level waste facilities shall
be evaluated to identify relevant features that should be avoided or
must be considered in facility design and analyses.
(c) Low-level waste disposal facilities shall be sited to achieve long
term stability and to minimize, to the extent practical, the need
for active maintenance following final closure.
Chapter IV - Low-Level Waste Requirements
IV-128 DOE G 435.1-1
7-09-99
Objective:
The objective of this requirement is to ensure the selection of proposed low-level disposal sites
within DOE reservations that have positive attributes toward meeting the disposal performance
objectives of DOE M 435.1-1, and to the extent practical, ensure that new low-level waste
disposal facilities are not sited in locations which will inherently require long-term active
maintenance to achieve disposal performance objectives.
Discussion:
Section 519
DOE M 435.1-1 includes the general requirements for site evaluation and facility design in
Section I.1.E.(18). This additional requirement, which applies to low-level waste disposal
facilities, emphasizes the need for long-term stability and minimal maintenance. This requirement
recognizes the importance of stability and minimal maintenance to the long-term performance of a
low-level waste disposal facility.
The evaluation of the data collected during site selection and characterization must include the
consideration of long-term stability and active maintenance following closure. Consideration of
the site characteristics to achieve long-term stability in site selection and facility design minimizes
the need for active maintenance following site closure. As part of the documentation for selecting
a preferred site, the evaluation needs to demonstrate how long-term stability of the site was
considered. Furthermore, data developed during site characterization that quantifies the long
term stability characteristics of the site are to be evaluated separately. Aspects of the site stability
which need to be incorporated into the design of the facility to minimize active maintenance
following site closure need to be identified.
Site characteristics, waste and container characteristics, operational practices, and disposal unit
closure all contribute to long-term stability. Disposal site stability is a necessary performance
parameter for meeting the requirements of DOE O 435.1. During site operations and in the
closure and post-closure periods, any indication that stability may be compromised needs to be
addressed immediately.
Example: Two sites are being evaluated as potential sites for a disposal facility. One
site is underlain with limestone formations associated with karst development, and the
other site is underlain by cemented sandstone. All other considerations being equal, the
latter site is selected as a disposal site in favor of the greater potential long-term stability
provided by the cemented sandstone formation.
As part of site maintenance, site inspection to verify the stability of the site is appropriate.
Closure planning also needs to address site specific stability. Specific elements which may need to
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-129
7-09-99
be addressed will likely be revealed through performance assessment maintenance, or from
monitoring activities.
Site Characterization. The site characterization program has the objective of developing a
quantitative database for design and performance assessment through field studies and laboratory
testing. A program plan describing the nature and extent of the site characterization program for
a preferred site is a valuable tool for guiding investigations. The objectives of a site
characterization program are discussed in detail in the Nuclear Regulatory Commission’s
NUREG-0902, Site Suitability, Selection and Characterization: Branch Technical Position. For
the purpose of site characterization at DOE sites, the following specific objectives for developing
technical information are useful in developing a program plan.
C Providing a reasonable expectation that the performance objectives of DOE M
435.1-1 are likely to be met;
C Evaluating the ability of the site to contribute to the containment of low-level
waste;
C Providing adequate information for design of a low-level waste disposal facility;
C Identifying the interaction between the site, waste containers, and low-level waste;
Section 520
C Establishing data collection points, baseline environmental data, and some portion
of the environmental monitoring program; and
C Identifying potential environmental impacts from construction, operation, and
closure of the facility.
The site characterization program needs to be site-specific and flexible to allow for revisions in
the program as data are developed. The program needs to be developed to allow for the
collection of baseline environmental data for a least one year prior to construction, with extended
periods of time preferred for parameters subject to seasonal or annual variations (see guidance on
DOE M 435.1-1, Section IV.R.(3)(b)). For baseline environmental data, the collection points are
selected to continue to serve as collection points throughout the life cycle of the facility, to
facilitate meaningful interpretation of data. Regional data collected over extended periods of time
are useful supplements to the site characterization program.
Example 1: A new low-level waste disposal facility site characterization program
includes the investigation of the subsurface structure with the objective of confirming the
absence of perched water. Specific parameters and measurements were selected through
a recently performed data quality objectives effort for the characterization program.
Chapter IV - Low-Level Waste Requirements
IV-130 DOE G 435.1-1
7-09-99
Drilling data indicate the presence of a perched water deposit on the perimeter of the
proposed site. The subsurface investigation program is expanded to establish the extent
of the perched water deposit and its significance with respect to the performance of the
disposal facility.
Example 2: A new disposal facility characterization program erects a meteorologic
tower to collect wind and precipitation data with the objective of confirming site
conditions are representative of regional conditions. Specific parameters and
measurements were selected through a recently performed data quality objectives effort
for the characterization program. Initial data clearly indicate the site conditions differ
from regional conditions. The frequency of data collection is increased and baseline
monitoring program extended to provide sufficient data for design and performance
assessment activities.
Basic elements of the site characterization program include meteorology, surface water
hydrology, groundwater hydrology for both saturated and unsaturated media, geology, soils,
water quality, site stability, air quality, ecology, land and cultural resources, and socioeconomics.
Field studies are performed in a manner that does not compromise the integrity of the land to be
dedicated to waste disposal. The extent of investigation in each of the topic areas is dependent on
the site-specific characteristics of the preferred site. Data to be collected during the site
characterization program need to be selected in accordance with the data quality objectives
(DQO) process to ensure meaningful and wise use of resources. The quality assurance and record
keeping requirements of DOE M 435.1-1 are followed for all aspects of site characterization to
ensure that data records are maintained and retained throughout the life cycle of the facility.
Documentation of the results of the site characterization program is used in facility design,
performance assessment, waste acceptance criteria development, and in fulfilling the requirements
of NEPA.
Section 521
Site characterization program plans are reviewed and approved prior to initiation of investigations
to ensure that important elements are included and unnecessary activities are not undertaken. The
program is executed by skilled professionals with a multi-disciplinary team of experts representing
environmental and facility monitoring, design, performance assessment, and waste operations.
Routine reviews of collected data are performed to ensure the site characterization program is
accomplishing its specific objectives. The site characterization program also needs to be
integrated with other elements of facility development to ensure characterization information is
correctly utilized in those other elements, principally the performance assessment and facility
design.
Additional general guidance for site evaluation and siting of low-level waste disposal facilities is
available from a variety of sources to be consulted (NRC Reg. Guide 4.19, DOE/LLW 64T,
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-131
7-09-99
DOE/LLW 75T Tab I, DOE/LLW 67T) and incorporated into site-specific investigations where
appropriate.
Site Features Contributing to Stability and Prevention of Maintenance. The requirement to site
facilities for long-term stability and to minimize active maintenance specifically states that these
attributes are to be attained following closure of the low-level waste disposal facility. As
discussed above, these attributes are necessary because the hazard from the disposed low-level
waste will remain for years following closure. Disposal sites that do not require active
maintenance following closure are more likely to be able to demonstrate a reasonable expectation
that the disposal performance objectives will continue to be met. The following discussion
provides additional information on site features that contribute to stability and prevention of
maintenance at a site.
A low-level waste disposal site needs to be located in an area where hydrogeologic conditions
allow reliable prediction of performance. Subsurface migration of radionuclides needs to be
readily and confidently predictable. Such systems may be characterized by thick, partially
saturated zones; low moisture flux through the burial zone; and/or geologic formations with
permeability flow systems that are readily characterized.
A low-level waste disposal site also needs to protect the waste from contact with or intrusion of
water. Materials that can be shaped into a final landscape that diverts offsite surface and
subsurface water, combined with the resistance of the soil material to wind and water erosion and
the ability of the soil material to support certain kinds of vegetation will contribute to the disposal
facility remaining in a stable state.
A low-level waste disposal site needs to include characteristics of earth materials and water
chemistry that favor increased residence times and/or attenuation of radionuclide concentrations in
the subsurface. Attenuation of radionuclide concentrations and slow rates of migration will
increase the retention of radionuclides near the burial trenches. Soil and water chemistry
characteristics that favor retardation provide an additional safety factor in slowing the migration
of many radionuclides.
Section 522
Example: The site for the expansion of the low-level waste disposal facility at Site Y is
considered very advantageous for this purpose. The site is underlain by a simple,
sedimentary layered system consisting of clay and sand horizons which are relatively
easy to conceptualize in mathematical modeling. The clay layer that will form the floor
of the trench has been investigated thoroughly and the flow parameters are well
understood. The layer will act as a retardant for migration of several critical
radionuclides that will be disposed at the facility. Geomorphic investigations of the site
have revealed no evidence of active geologic processes that would lead to erosion or
Chapter IV - Low-Level Waste Requirements
IV-132 DOE G 435.1-1
7-09-99
other facility surface problems that would impact the ability of the site to maintain long
term stability.
Site Features that Should be Avoided. Particular features need to be avoided that contribute to
site instability or transport of radionuclides from a site to potential receptors.
The disposal horizon needs to be outside of the transition zone between saturated and unsaturated
flow, and preferably well above the transition zone or water table. Avoiding the transition zone
requires extensive knowledge of the water table and its fluctuations. Factors to be evaluated
include:
C Water table elevation and range of both seasonal and long-term fluctuations;
C Height of capillary fringe; and
C Thickness of material being excavated above the transition zone.
Complex flow systems, such as flow through cavernous, fractured, or jointed materials, may not
be amenable to reliable predictions, and need to be avoided. A low-level waste disposal site needs
to not be located where erosion caused by wind and water will jeopardize performance. During
the required performance period, wind and water erosion needs to be at levels that would not
cause intrusion on the buffer zone and/or waste cover in such a way as to uncover the waste,
increase surface radiation levels above performance limits, or significantly shorten radionuclide
release pathways.
Surface flooding or inundation needs to be avoided as such events can also accelerate transport of
waste material and/or saturate the waste, increasing leachate formation and accelerating
subsurface water flow.
Geologic hazards that could pose a threat to a low-level waste disposal site performance and
which may need to be considered include:
C Seismic hazards associated with fault zones and earthquakes;
C Mass movement of earthen material, which can range from slow soil creep to
slumping of oversteepened slopes to sudden massive slides of rock or debris;
C Volcanic activity; and
C Subsidence of the land surface, which frequently accompanies subsurface mining,
withdrawal of oil, gas or water, or dissolution of geologic formations.
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-133
7-09-99
Example: The proposed site for the new Brown Facility Low-Level Waste Disposal
Trenches is preferred because of its proximity to three operating treatment facilities at
the Brown Site. However, the proposed disposal unit design will have the trench bottoms
in the transition zone between the saturated zone and unsaturated zone, at least
according to one study conducted several years before. Another more recent study
indicates that the fluctuation has subsided, and that the trench bottoms are no longer in
the transition zone. After further evaluations, the site for the proposed facility is moved
to another location, still near the treatment facilities, but for which there is no dispute
about the depth and extent of the transition zone.
Section 523
Compliance with this requirement is demonstrated if low-level waste disposal facilities are sited so
that natural features are present that contribute to the long-term stability of the disposal facility
and helps minimize any need for maintenance after the facility is closed. Siting avoids any natural
features present at the DOE reservation which would contribute to instability of the site or to
migration of radionuclides from the site. Documentation of analysis of such features must be
included in the radioactive waste management basis.
Supplemental References:
1. NRC, 1988. Guidance for Selecting Sites for Near-Surface Disposal of Low-Level
Radioactive Waste, Regulatory Guide 4.19, U. S. Nuclear Regulatory Commission,
Washington, D.C., August 1988.
2. NRC, 1982. Site Suitability, Selection and Characterization: Branch Technical Position
– Low-Level Waste Licensing Branch, NUREG-0902, U. S. Nuclear Regulatory
Commission, Washington, D.C., April 1982.
3. IAEA, 1994. Siting of Near Surface Disposal Facilities, Safety Series No. 111-G-3.1,
International Atomic Energy Agency, Vienna, Austria, 1994.
4. DOE, 1987. Site Selection: The Critical Path in Developing Low-Level Radioactive
Waste Disposal Facilities, DOE/LLW-64T, U.S. Department of Energy, National Low-
Level Waste Management Program, Idaho Falls, ID, 1987.
5. DOE, 1992. Site Characterization Handbook for Low-Level Radioactive Waste Disposal
Facilities, Revision 1, DOE/LLW-67T, U.S. Department of Energy, National Low-Level
Waste Management Program, Idaho Falls, ID, 1992.
Chapter IV - Low-Level Waste Requirements
IV-134 DOE G 435.1-1
7-09-99
6. DOE, 1983. Low-Level Radioactive Waste Management Handbook Series: Procedures
and Technology for Shallow Land Burial, DOE/LLW-13Td, U.S. Department of Energy,
National Low-Level Waste Management Program, Idaho Falls, ID, 1983.
7. DOE, 1989. Methodology for Compliance with DOE Order 5820.2A Chapter III:
Management of Low-Level Radioactive Waste. DOE/LLW-75T, Tab K, U.S. Department
of Energy, National Low-Level Waste Management Program, Idaho Falls, ID, February
1989.
IV. M.(2) Low-Level Waste Treatment and Storage Facility Design. The
following facility requirements and general design criteria, at a
minimum, apply:
Objective:
The objective of this requirement is to ensure that a minimum set of facility requirements and
general design requirements determined from hazards analyses or policy considerations are
applied to low-level waste treatment and storage facilities.
Discussion:
The facility requirements and general design criteria included in DOE M 435.1-1,
Sections IV.M.(2) (a) through (e), are included as requirements to ensure adequate protection of
the public, workers, and the environment from nuclear hazards. The requirements contained in
these sections apply to new and existing low-level waste management facilities, unless the
requirement specifies otherwise.
Section 524
During the development of DOE O 435.1 and DOE M 435.1-1 an analysis of the hazards
associated with the management of waste indicated that appropriate facility safety requirements
and general design requirements are essential to ensuring the protection of the public, workers,
and the environment. Therefore the intent is to apply these requirements to all low-level waste
treatment and storage facilities, both existing and new. However, it is recognized that in some
cases it may not be practical, or possible, to apply these requirements to existing low-level waste
facilities or operations. Such conditions as limited programmatic usage, expected short service
life of the operation, or factors that make long-term, capital-intensive upgrades unreasonable may
be bases for not applying the requirements. In such cases, an exemption to the requirement may
be warranted. The Implementation paragraph of DOE M 435.1-1 provides for an exemption to a
requirement provided it is processed in accordance with the requirements of DOE M 251.1-1A,
Directives System Manual. Additionally, note that the low-level waste treatment and storage
facility design requirements need to be applied using a graded approach. The considerations and
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-135
7-09-99
controls identified in Sections IV. M.(2)(a) through (e) may not be applicable to some facilities,
such as an outdoor storage yard for packaged low-level waste. These requirements are not
intended to preclude such storage by forcing use of only facilities which possess all the items
listed in requirements (a) through (e). Instead, the requirements are applied, using a graded
approach, where the treatment or storage facility possesses characteristics to which the
requirements are applicable.
Example: At Site Z it is determined that the requirement in DOE M 435.1-1, Section
III. M.(2)(e), Monitoring, for an existing low-level waste tank is unreasonable due to the
planned short service life of the tank. The existing tank is not routinely being used and
would only be used over the next 18 months for emergency storage of liquid low-level
waste. A replacement for the tank is under construction. In accordance with DOE M
251.1-1A, Chapter VII, “Exemptions,” an Exemption Request is prepared that supports
the position that application of the requirement is not justified by any safety and health
benefit. The exemption request also notes that procedures will be implemented to ensure
a once per shift visual check to ensure no waste is inadvertently transferred to the tank.
The Exemption Request is processed in accordance with the requirements contained in
paragraph 4, Exemption Process, in Chapter VII.
DOE M 435.1-1 also allows for the use of the “Necessary and Sufficient Closure Process” or the
integrated “Safety Management System.” Use of these processes for deriving facility design
requirements that provide protection comparable to the requirements contained in DOE M 435.1
1, Sections IV.M.(2) (a) through (e) is also acceptable at sites where these processes are invoked
by contract.
Application of these requirements to all existing low-level waste treatment and storage facilities
may appear to contradict the direction or guidance provided by some other DOE Orders that are
invoked by DOE M 435.1-1, Section I.1.E., Requirements of Other Regulations and DOE
Directives. In such cases the requirements contained in DOE M 435.1-1 do apply.
Section 525
Example: Section I.1.E.(18), Site-Evaluation and Facility Design, invokes DOE O 420.1,
Facility Safety. Guidance to DOE O 420.1 states that the design criteria included in the
Order are “applicable to the design and construction of new nonreactor nuclear facilities
and for modifications to existing nonreactor nuclear facilities when modifications
significantly increase the probability or consequences of a nuclear accident or require a
change in the Technical Safety Requirements (TSRs) of a facility. The definition of
‘significant’ is intentionally left to the judgment of the proposing contractor and the
approving DOE authority. In part, this is intended to allow upgrading of existing safety
equipment or installation of minor new improvements without subjecting the process to
onerous procedural requirements and thus discouraging improvements.” Thus, under
DOE O 420.1 an existing low-level waste management facility that is to be
Chapter IV - Low-Level Waste Requirements
IV-136 DOE G 435.1-1
7-09-99
“insignificantly” modified does not have to meet the design requirements of DOE O
420.1. However, under DOE M 435.1-1, the same facility must meet the design
requirements of DOE M 435.1-1, Section IV.M.(2) (a) through (e), or follow the DOE M
251.1-1A exemption process. The requirements contained in DOE M 435.1-1 have
precedence, and should be implemented.
A “backfit” process has been discussed by the Department in the past to address changes that may
be required through the imposition of a new DOE safety requirement. Such changes may be
problematic for low-level waste facilities and systems that have been in existence for over 20
years. It is not the purpose of this order and manual to create such a process for the Department;
however an existing or new field-office or Program Secretarial Office backfit analysis and review
process may be applied to determine whether implementation of a proposed backfit could be
justified on the basis of a substantial safety improvement or on a cost-benefit basis. One example
of a candidate process is contained in expired DOE N 5480.5, Imposition of Proposed Nuclear
Safety Requirements, which expired in 1993 because of an administrative provision. Another
candidate process is described Draft DPOM-FS-300, “Treatment of Proposed Backfits,” which
was developed for the Office of Defense Programs, but not formally adopted. A third candidate
process is documented in Westinghouse Savannah River Company, High Level Waste
Management Engineering Procedure, ENG. 12, “HLWMD Backfit Analysis Procedure.” For
development of new backfit processes Nuclear Regulatory Commission requirements in 10 CFR
50.109 and 10 CFR 76.76 should be consulted.
Compliance with this requirement is demonstrated by documentation that supports the
implementation of the requirements at DOE M 435.1-1, Section IV.M.2. (a) through (e), or
documentation that supports the “Necessary and Sufficient Closure Process” or integrated “Safety
Management System,” or the DOE M 251.1-1A exemption process.
Supplemental References:
1. DOE, 1995. Implementation Guide for Nonreactor Nuclear Safety Design Criteria and
Explosives Safety Criteria, Revision G, Draft DOE G 420.1-X, September 1995.
2. DOE, 1993. Defense Programs Operations Manual, “Treatment of Proposed Backfits,”
Revision 0, Draft DPOM-FS-300, U.S. Department of Energy, Washington, D.C.,
February 5, 1993.
3. DOE, 1998. Directives System, DOE O 251.1A, U.S. Department of Energy,
Washington, D.C., January 30, 1998.
Section 526
4. DOE, 1998. Directives System Manual, DOE M 251.1-1A, U.S. Department of Energy,
Washington, D.C., January 30, 1998.
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-137
7-09-99
IV. M.(2) Low-Level Waste Treatment and Storage Facility Design. The
following facility requirements and general design criteria, at a
minimum, apply:
(a) Confinement. Low-level waste systems and components shall
be designed to maintain waste confinement.
Objective:
The objective of this requirement is to ensure the design of low-level waste storage and treatment
facilities includes the installation of equipment capable of containing low-level waste so that
releases that could result in exposures to workers or the public or that could contaminate the
environment are minimized.
Discussion:
This requirement is invoked to address hazards identified during the safety and hazards analysis
performed in support of the development of this order and manual associated with the unexpected
or uncontrolled release of radioactive material from low-level waste treatment and storage
facilities that could impact workers, the public, or the environment. In addition to the facility and
general design requirements contained in DOE M 435.1-1, Section I.1.E.(18), the above
requirement for low-level waste confinement must be met.
The term “confinement” is defined in the DOE M 435.1-1 Glossary as:
“The control or retention of radioactive materials within as a designated boundary.
Primary confinement systems are process enclosures and other spaces normally containing
hazardous materials. Secondary confinement areas surround one or more primary
confinement systems.”
In broad terms the purpose of confinement systems is to minimize the spread of radioactive and/or
hazardous materials and the release of these materials in facility effluents during normal
operations, abnormal operations, and potential accidents. One usual function of process
equipment is to provide primary confinement and prevent or mitigate radioactive and/or
hazardous material releases to the environment. Process equipment that would be required to
provide primary confinement includes tanks, piping, pressure vessels, pumps, valves, and glove
boxes. Secondary confinement are those systems that provide the next level of confinement and
can include process equipment, (e.g., double-walled tanks, double-walled piping systems), as well
as curbing and diking of liquid storage tank areas, or secure or closed areas of buildings, that
Chapter IV - Low-Level Waste Requirements
IV-138 DOE G 435.1-1
7-09-99
further prevent or mitigate uncontrolled releases of radioactive and/or hazardous materials to the
environment. The need for redundancy and the degree of redundancy in these systems is
determined by the safety analysis process and maintenance concerns for both active and passive
components.
For a specific low-level waste facility or operation the number and arrangement of confinement
systems or barriers and their required characteristics needs to be determined on a case-by-case
basis. Factors that are considered in confinement system design include type, quantity, form, and
conditions for dispersing low-level waste material during normal operations and design basis
conditions. As in implementation of all of the requirements of DOE O 435.1 and DOE M 435.1
1, the graded approach is used for determining the appropriate level of rigor in applying this
control to the management systems employed at a particular low-level waste management facility.
Section 527
For treatment systems involving liquid low-level waste, it might be appropriate for primary
confinement to be provided by process equipment (i.e, pipes) and facility design to provide for
secondary confinement (i.e, curbing and diking). For storage of dry low-level waste, primary
confinement could be provided by an appropriate container.
Example 1: The low-level waste management facility at laboratory A manages various
types of low-level waste. Primary and secondary confinement for liquid low-level waste
streams is provided by a double-walled piping and tank system maintained in the lab for
management of those waste streams. Analysis indicated that the confinement provided by
the containers for dry process wastes is adequate.
Example 2: Storage of low-level waste at Site B takes place on several outside storage
pads at Area 5 that were designed and built several years ago. In order to implement the
DOE M 435.1-1 storage facility confinement requirement, Site B conducts an analysis of
the current storage conditions at all of these pads. On one pad, some waste containers
are found to be in poor condition, and the confinement requirement is met by installation
of a temporary berm around the pad until repackaging in overpacks can be
accomplished. The containers on the rest of the pads are in good condition, and the
analysis indicates that the confinement requirement is sufficiently met by the container
itself.
Engineering evaluations, trade-offs, and experience are used to develop practical designs that
achieve confinement system objectives. The adequacy of confinement systems to effectively
perform the needed functions needs to be documented and accepted through the facility or
operation Safety Analysis Report or equivalent documentation.
The guidance for DOE M 435.1-1, Chapter II, High-Level Waste Requirements, presents detailed
guidance for complying with the confinement requirement for high-level waste storage tanks.
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-139
7-09-99
That guidance is appropriate to be consulted for any details that may be needed for complying
with the confinement requirement for low-level waste treatment or storage activities that are
hazardous enough that the most rigorous implementation of the confinement requirement must be
applied. The guidance for DOE M 435.1-1, Section II.P.(2)(b) refers to Resource Conservation
and Recovery Act requirements and discusses guidance for confinement that may also be useful in
establishing compliant confinement in accordance with this requirement for mixed low-level or
liquid low-level waste storage facilities or activities that warrant strict confinement conditions.
Compliance with the requirement is demonstrated by designing low-level waste treatment and
storage facilities including systems that provide primary and secondary confinement as appropriate
based on safety analysis or equivalent documentation and documenting the analyses and rationales
for such controls in the facility radioactive waste management basis documentation.
Supplemental References:
1. DOE, 1992. Nuclear Safety Analysis Reports, DOE 5480.23, U.S. Department of
Energy, Washington, D.C., April 10, 1992.
IV. M.(2) Low-Level Waste Treatment and Storage Facility Design. The
following facility requirements and general design criteria, at a
minimum, apply:
(b) Ventilation.
Section 528
1. Design of low-level waste treatment and storage
facilities shall include ventilation, if applicable, through
an appropriate filtration system to maintain the release
of radioactive material in airborne effluents within the
requirements and guidelines specified in applicable
requirements.
2. When conditions exist for generating gases in flammable
or explosive concentrations, ventilation systems or other
measures shall be provided to keep the gases in a non
flammable and non-explosive condition. Where
concentrations of explosive or flammable gases are
expected to approach the lower flammability limit,
measures shall be taken to prevent deflagration or
detonation.
Chapter IV - Low-Level Waste Requirements
IV-140 DOE G 435.1-1
7-09-99
Objective:
The objective of this requirement is to ensure that the design of low-level waste treatment and
storage facilities includes features to remove radioactive materials from airborne effluents that
could endanger worker or public safety and/or the environment to levels allowed in regulations
before they are released, and to preclude or mitigate the accumulation of flammable or explosive
gases in the facilities which could lead to uncontrolled releases of radioactive materials.
Discussion:
This requirement is based on a similar requirement invoked to address a group of hazards that was
identified by the safety and hazards analysis performed in support of the high-level waste chapter
of this Manual. The analysis revealed that very hazardous conditions can result from unexpected
and uncontrolled releases of radioactive material, either because of poorly designed ventilation
systems or due to accumulation and ignition of flammable or explosive gases in high-level waste
storage facilities. Similar circumstances occurring at a low-level waste facility are similarly
problematic, and a similar requirement was believed to be justified to prevent exposures to
workers or the public, radioactive leaks to the environment, and costs for damage mitigation and
cleanup from unanticipated and/or uncontrolled airborne releases of radioactive material.
Subrequirement IV.M.(2)(b)1. is discussed below under Airborne Effluent Filtration Systems and
subrequirement IV.M.(2)(b)2. is discussed under Flammable and Explosive Gases.
Airborne Effluent Filtration Systems. The subrequirement to maintain radioactive material in
airborne effluents from low-level waste management facilities to appropriate levels through the
use of filtration systems is to be implemented using the graded approach. This requirement is
intended to ensure that low-level waste management facilities have adequate filtration where
necessary, not to dictate that each facility must have a particular type of air filtration or removal
efficiency. Therefore, the safety analysis or assessment for each facility will provide the basis for
determining the level of filtration required.
Example 1: A low-level waste treatment facility is constructed so low-level waste
packages can be opened, the waste sorted, and the appropriate waste thermally treated.
In order to ensure worker protection, the building ventilation system is constructed to
draw air from radiologically clean areas, to radiologically-controlled areas and finally
to airborne contamination areas such as glove boxes and thermal treatment equipment.
Through the auditable safety assessment, it is determined that the potential exists for
releases of radioactive materials through the exhaust system. The building exhaust
system is therefore equipped with high-efficiency particulate air filters to ensure that
releases are controlled to within limits. Monitoring is used to ensure the necessary
removal efficiency is maintained by the air filter system.
Section 529
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-141
7-09-99
Example 2: A storage building is designed and operated to receive only closed
containers of low-level waste and to perform nondestructive testing. Through the
preparation of an auditable safety assessment it is determined that the potential for
release of radioactivity in the building is very low. Consequently, the ventilation system
provided for the building is only for climate control and not for contamination control.
The building exhaust system is determined to not need any extra filtration to meet the
requirements of applicable release standard, and the rationale and basis of the analysis
are incorporated into facility safety documentation.
Standards for DOE compliance with airborne releases are contained in DOE 5400.5, Radiation
Protection of the Public and the Environment and 40 CFR Part 61, Clean Air Act regulations.
The limits for release cited in these documents are for the DOE site (i.e., all the activities of the
Department), not for individual facilities. Therefore, the operational limits for any individual
facility need to be established based on the potential impacts from all facilities on the site.
Consistent with Departmental practices and an underlying principle in development of the
Radioactive Waste Management Manual, airborne effluent releases need to be kept as low as
reasonably achievable.
The number, size, and design of air filtration equipment needs to meet the performance
requirements dictated by the safety analysis or assessment. The location of air filtration units in
the ventilation system is established as close as practical to the source of contamination so as to
minimize spread to the remainder of the ventilation system. The system is designed for ease of
maintenance and periodic inspection and has provisions (test ports) to facilitate insertion of
measuring devices for testing filter performance. Where larger loads are expected or predicted on
the filtration systems (e.g., dusty condition), pre-filters need to be considered to extend the life of
the main filter and reduce maintenance.
Flammable and Explosive Gases. The subrequirement addressing explosive or flammable
concentrations of gases is intended to ensure that the design of facilities and equipment includes
consideration of the potential for generating these types of gases. Generation of flammable or
explosive gases has been a concern in the storage of liquid waste (e.g., high-level waste tanks),
but also needs to be recognized as a potential problem in other situations, such as in treatment
systems.
Where sampling data and safety analyses indicate a potential for accumulating gases in
concentrations approaching the lower flammability limit, facilities and equipment shall be provided
to prevent the conditions which could lead to fire or explosion. This is normally accomplished by
the design and installation of ventilation equipment which provides enough air flow to maintain
gases below flammable or explosive concentrations. In situations where gas evolution is episodic
and the concentration of gases approaches the lower flammability limit for short periods of time in
Chapter IV - Low-Level Waste Requirements
IV-142 DOE G 435.1-1
7-09-99
spite of the ventilation system, spark-proof technology needs to be employed in the design of
ventilation equipment so that the equipment itself does not become a source of ignition.
Section 530
Attention to fire protection for the filtration system needs to also be considered to ensure the
facility can perform under off-normal conditions. Guidance for protection of filtration systems in
ventilation plenums for nuclear facilities is provided in the Fire Protection Design Criteria (DOE
STD-1066-97). This guidance addresses materials of construction, location of filters, fire ratings
of protective walls, and internal detectors for fire and heat.
Other methods can be employed to prevent conditions which could lead to ignition of flammable
or explosive gases. One such method is the introduction of a sufficient flow of inert gases into the
headspace where flammable or explosive gases would accumulate. The inert gases need to be
supplied at a rate that keeps the concentration of the flammable or explosive gases and of
available oxygen/oxidants below levels that could result in deflagration or detonation. As with
ventilation equipment, the specific conditions of gas generation and of providing an inert
atmosphere in the headspace must be evaluated and a decision made as to whether spark-proof
technology should be included in the design of the system.
Compliance with this requirement is demonstrated by analyses that support the level of filtration
provided on a low-level waste management facility, and if airborne effluent monitoring data are
available, a demonstration of compliance with the site-established operational guidelines for the
facility. In addition, acceptable implementation is demonstrated by analyses, monitoring data, or
both showing that the potential for generation of explosive or flammable concentrations of gases
has been considered and where the potential exists, the presence of ventilation equipment or other
means that prevent deflagration or detonation. The analyses and rationales for the selected
controls must be documented in the radioactive waste management basis.
Supplemental References:
1. DOE, 1990. Radiation Protection of the Public and the Environment, DOE 5400.5, U.S.
Department of Energy, Washington, D.C., February 8, 1990.
2. DOE, 1997. Fire Protection Design Criteria, DOE-STD-1066-97, U.S. Department of
Energy, Washington, D.C., 1997.
3. EPA. National Emission Standards for Hazardous Air Pollutants, 40 CFR Part 61, U.S.
Environmental Protection Agency, Washington, D.C.
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-143
7-09-99
IV. M.(2) Low-Level Waste Treatment and Storage Facility Design. The
following facility requirements and general design criteria, at a
minimum, apply:
(c) Consideration of Decontamination and Decommissioning.
Areas in new and modifications to existing low-level waste
management facilities that are subject to contamination with
radioactive or other hazardous materials shall be designed to
facilitate decontamination. For such facilities a proposed
decommissioning method or a conversion method leading to
reuse shall be described.
Objective:
The objective of this requirement is to ensure the incorporation of the concept of life-cycle waste
management into the operations of radioactive waste management facilities to result in the
minimization of radioactive waste that must be managed in the future from decontamination and
decommissioning activities, and the reduction of facilities that must be dismantled due to
contamination rather than re-used for another beneficial purpose.
Discussion:
Section 531
During the analysis of requirements conducted in support of DOE O 435.1 and DOE M 435.1,
life-cycle waste management concepts were applied to the generation of waste by waste
management facilities as well as the generators of waste that send waste to waste management
facilities. This requirement was developed to extend the life-cycle management concept to the
design of waste management activities and facilities, with the explicit goal of minimizing the
generation of waste, and also pointing to a beneficial use of the facility following its waste
management use. Decontamination and decommissioning activities are also becoming a
significant part of the life-cycle costs for low-level waste facilities. This requirement addresses
this situation by trying to reduce the costs associated with disposition of waste management
facilities following their use.
New low-level waste facilities are defined as those whose design basis was not approved prior to
the implementation date of DOE O 435.1, with design basis as defined in the Manual Definitions.
If a low-level waste facility’s design basis is defined after the issuance date of DOE O 435.1, the
requirements of this section are applicable. Application of these requirements to existing or low-
level waste facilities that are to undergo significant modifications is left to the discretion of the
Field Office management organization as to whether retrofitting with designed features that
facilitate decontamination is reasonable. To support this decision an analysis needs to be
conducted comparing the expected benefits by the application of these requirements to the costs
Chapter IV - Low-Level Waste Requirements
IV-144 DOE G 435.1-1
7-09-99
of implementing such measures. These costs include programmatic, resource, and schedule
impacts as well as potential impacts such as additional worker exposures due to radiation and
chemical hazards.
Design to Facilitate Decontamination. Decontamination is defined by the Implementation Guide
to DOE O 420.1, Facility Design, as “the act of removing a chemical, biological, or radiological
contaminant from or neutralizing its potential effect on a person, object, or environment by
washing, chemical action, mechanical cleaning, or other techniques.” In conjunction with DOE O
420.1, DOE M 435.1-1 requires that low-level waste facilities incorporate measures to reduce
areas of contamination or to simplify decontamination of areas that may become contaminated
with radioactive or hazardous materials. Examples of design features that need to be considered
include:
• Service piping, conduits, and ductwork kept to a minimum in areas that could be
potentially contaminated and, if included in such areas, their design arranged to
facilitate decontamination.
• Cracks, crevices, and joints filled and finished smooth to prevent accumulation of
contaminated material.
• Walls, ceiling, and floors in areas vulnerable to contamination finished with
washable or strippable coverings.
• Metal liners, e.g., stainless steel cell lining, used in areas that have the potential to
become highly contaminated with radioactive materials.
• Contaminated or potentially contaminated piping systems have provisions for
flushing and/or cleaning.
• Accessible, removable covers for inspection and cleanouts provided.
• Construction materials that reduce the amount of radioactive materials requiring
disposal and that are easily decontaminated.
Section 532
Design to Support Decommissioning. Decommissioning, also defined in DOE O 420.1, is “the
process of closing and securing a nuclear facility or nuclear materials storage facility to provide
adequate protection from radiation exposure and to isolate radioactive contamination from the
human environment.” Design features that need to be considered to support decommissioning (or
beneficial reuse) of the facility include:
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-145
7-09-99
• Use of modular radiation shielding, in lieu of or in addition to, monolithic shielding
walls.
• Use of modular, separable confinements to preclude contamination of fixed
portions of the structure.
• Designs that ease cut-up, dismantlement, removal, and packaging of contaminated
equipment, such as glove boxes, air filtration equipment, large tanks, vessels, and
ductwork, from the facility.
• Use of localized liquid transfer systems that avoid long runs of buried,
contaminated piping; emphasis on localized batch solidification of liquid waste.
Special provisions may also be included in the design to ensure the integrity of
joints in buried pipelines.
• Piping systems that carry contaminated or potentially contaminated liquid that free
drain by gravity.
• Location of exhaust filtration components of ventilation systems at or near
individual enclosures to minimize long runs of internally contaminated ductwork.
• Equipment, including effluent decontamination equipment, that precludes to the
extent practicable, the accumulation of radioactive or other hazardous materials in
relatively inaccessible areas, including turns in piping and ductwork.
• Provisions for suitable clearances, where practical, to accommodate remote
handling and safety surveillance equipment required for future decontamination
and decommissioning.
• Use of lifting lugs on large tanks and equipment.
Decommissioning and Reuse Planning. Due to the high life-cycle costs of low-level waste
facilities this subrequirement is also intended to promote post-mission planning of low-level waste
facilities by requiring the identification of possible decommissioning methods or reuses of low-
level waste facilities as early as possible. To meet this requirement low-level waste facility
designs, or significant modification efforts, need to include analysis to determine the best
decommissioning methods, using currently available technologies, and factor the results of this
analysis into the facility’s design. Likewise, if a reuse of the facility is envisioned, any features
that can support this reuse mission need to be considered in the design effort.
Chapter IV - Low-Level Waste Requirements
IV-146 DOE G 435.1-1
7-09-99
Life-Cycle Asset Management, DOE O 430.1A, addresses deactivation and decommissioning
requirements of DOE facilities. Refer to DOE O 430.1A and its Guides for further information
and guidance on deactivation and decommissioning activities. Also refer to a new DOE Standard
(see Supplemental Reference 3) on the integration of safety and health requirements into facility
disposition activities.
Compliance with this requirement is demonstrated by the existence of design documentation that
indicates decontamination was considered during the design of new low-level waste facilities or
significant modifications to low-level waste facilities. Additionally, Site-Wide Radioactive Waste
Management Program documentation demonstrates that post-mission planning was considered, as
early as possible in the life of a facility, to assist in the identification of possible decommissioning
methods or facility reuse.
Section 533
Supplemental References:
1. DOE, 1995. Implementation Guide for Nonreactor Nuclear Safety Design Criteria and
Explosives Safety Criteria, Revision G, Draft DOE O 420.1-X, U.S. Department of
Energy, Washington, D.C., September 1995.
2. DOE, 1997. Decommissioning Implementation Guide, Draft G 430.1-4, U.S. Department
of Energy, Washington, D.C., October 1, 1997.
3. DOE, 1997. Integration of Safety and Health into Facility Disposition Activities, Draft
for DOE Complex Wide Review 9/26/97, DOE-STD-1120-98, U.S. Department of
Energy, Washington, D.C., September 26, 1997.
4. DOE, 1998. Life-Cycle Asset Management, DOE O 430.1A, U.S. Department of Energy,
Washington, D.C., October 14, 1998.
IV. M.(2) Low-Level Waste Treatment and Storage Facility Design. The
following facility requirements and general design criteria, at a
minimum, apply:
(d) Instrumentation and Control Systems. Engineering controls
shall be incorporated in the design and engineering of low-level
waste treatment and storage facilities to provide volume
inventory and to prevent spills, leaks, and overflows from
tanks or confinement systems.
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-147
7-09-99
Objective:
The objective of this requirement is to ensure that engineering controls are included in the design
of low-level waste management facilities to minimize the likelihood of release of radionuclides
that could lead to exposures or contamination of the environment.
Discussion:
The requirement for instrumentation and engineering controls is invoked to address a group of
hazards that was identified by the hazards analysis performed in support of the development of
this order and manual – the failure to promptly detect a release of radioactive material from low-
level waste that could impact workers, the public, or the environment. This requirement is closely
related to the previous design requirement for monitoring systems, but focuses on controls to
prevent the loss of containment.
Engineering controls in this requirement are considered to be those systems or design
characteristics that are provided to prevent the loss of containment from low-level waste
management facilities, and to provide volume inventory data, where appropriate. Examples of
engineering controls include flowmeters and level-sensing devices coupled with anti-siphon
devices or shut-off valves, and any other instrumentation and controls that maintain sufficient
freeboard within a storage vessel or unit. Other instruments and controls include devices that
measure changes in characteristics of liquid waste, e.g., temperature, pressure, pH, and/or other
characteristics providing a measure of a materials stability, that are combined with shutoff or
diversion routing devices.
The graded approach is used in determining the appropriate level of rigor in incorporating
engineering controls to the management systems employed at a particular low-level waste
management facility. Rigorous application of this requirement may be most appropriate for
circumstances involving treatment of liquid low-level waste, for example, where flowmeters and
devices measuring characteristics of the waste in the feedline of an incinerator, are continuously
operating. However, some handling situations involving bulk or solid low-level waste may need
to invoke these controls as well, where a simple shutoff of the equipment could prevent overfilling
or other hazardous conditions.
Section 534
Loss of containment at a waste storage or treatment facility can result from overflows, spills,
leaks, or siphoning of waste from a storage vessel. Incorporation of design measures at these
facilities to prevent such loss of containment is necessary, but is not considered sufficient to meet
this requirement. Equipment of this nature, in spite of rigid maintenance and surveillance, can fail
over its expected service life. Therefore, to fully meet this requirement mitigative measures to
reduce the loss of containment, are necessary. As discussed in guidance on confinement above,
an engineered barrier to fully contain a leak or a diversion mechanism to channel the waste to a
Chapter IV - Low-Level Waste Requirements
IV-148 DOE G 435.1-1
7-09-99
desired location provides defense-in-depth for the circumstances where the engineering controls
do not suffice. Guidance for Confinement (DOE M 435.1-1, Section IV.M.(2)(a)) provides
additional details on these mitigative measures.
Example: At the Site Q Low-Level Waste Storage Facility, the engineering controls on
the liquid low-level waste storage tank includes a waste feed line shut-off valve, which is
activated by a tank level-sensing device, to prevent overflow of waste from the tank. As a
further mitigative measure in the event the valve malfunctions, a double-contained
overflow line is attached to the tank to channel any overfill to another waste tank that is
maintained as a spare at the storage facility.
The design of engineering controls to meet this requirement will most likely be directed by the
facility-specific safety analysis for waste management facility. Such safety analysis may dictate
that some of these engineering controls be designed as safety-class or safety-significant systems,
structures, or components (SSC) to ensure they survive design-basis accidents. Use of the safety
analysis process, as prescribed by DOE 5480.23, Nuclear Safety Analysis Reports, to identify the
necessary engineering controls to meet this requirement for both new and upgrades to existing
low-level waste treatment and storage facilities, is considered appropriate and encouraged.
Compliance with this requirement is demonstrated by the incorporation of engineering controls
that provide: timely information to facility operations personnel regarding the volumes of waste
being stored; automatic shut-off, anti-siphoning devices, and automatic sensing devices to provide
timely information to operations personnel; and provide mitigative measures to minimize the
spread of low-level waste in the event of loss of containment, which are based on facility safety
analysis and documented in the required safety analysis documentation.
Supplemental References:
1. DOE, 1995. Implementation Guide for Nonreactor Nuclear Safety Design Criteria and
Explosives Safety Criteria, Revision G, Draft DOE G 420.1-X, September 1995.
2. DOE, 1992. Nuclear Safety Analysis Reports, DOE 5480.23, U.S. Department of
Energy, Washington, D.C., April 10, 1992.
IV. M.(2) Low-Level Waste Treatment and Storage Facility Design. The
following facility requirements and general design criteria, at a
minimum, apply:
(e) Monitoring. Monitoring and/or leak detection capabilities
shall be incorporated in the design and engineering of low-level
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-149
7-09-99
waste treatment and storage facilities to provide rapid
identification of failed confinement and/or other abnormal
conditions.
Section 535
Objective:
The objective of this requirement is to ensure the design of low-level waste management facilities
includes the installation of equipment capable of identifying failures in containing low-level waste
and other conditions that could result in exposures of workers or the public to radioactivity or
contamination of the environment.
Discussion:
This requirement is invoked to address a group of hazards that was identified by the hazards
analysis performed in support of the development of this order and manual -- the failure to
promptly detect a release of radioactive material from low-level waste that could impact workers,
the public, or the environment. This particular requirement addresses the design of monitoring
systems directed toward prompt detection of acute releases (releases that are detectable visually
or by some other gross indicator) that become apparent over a time frame of hours or days as well
as to alert operators that a vessel (e.g., tank or bin) is approaching capacity so that overfilling can
be avoided. Monitoring to detect releases that may be too small to be detected in a timely manner
via volume changes is addressed in guidance on Requirements IV.R, Monitoring, later in this
guidance.
As in implementation of all of the requirements of DOE O 435.1 and DOE M 435.1-1, the graded
approach is used for determining the appropriate level of rigor in applying this control to the
management systems employed at a particular low-level waste management facility. Also,
monitoring for leakage and contamination spread needs to be performed by means appropriate for
the type and character of radioactive waste being managed at the facility. Rigorous application of
this requirement may be most appropriate for circumstances involving storage or treatment of
liquid low-level waste, for example, highly acidic liquid waste in a single-walled, mild steel tank
may require continuous monitoring coupled with alarms and transfer equipment. A treatment
facility involving bulk or solid low-level waste may need to implement monitoring systems such as
portable constant air monitoring systems designed to detect and measure airborne contamination
spread from dry processes. A facility storing containerized low-level waste may rely on a
program of container inspections to meet the needs for monitoring for leaks and abnormal
conditions.
Example: Low-Level Waste Storage Building 560 was designed and built several years
ago, and is currently empty. Site plans call for resuming use of the facility for storage of
containerized low-level waste awaiting disposal. In determining how to implement the
Chapter IV - Low-Level Waste Requirements
IV-150 DOE G 435.1-1
7-09-99
DOE M 435.1-1 storage facility monitoring requirement, site management conducts an
analysis of Building 560. The analysis indicates that there are no monitoring systems in
place that would meet the requirement. A Building 560 container inspection program
that involves weekly walk-throughs of the facility will be implemented to meet the storage
facility monitoring requirement.
For transfer systems, designers may need to consider the use of continuous flow monitors to
allow comparisons of total volume input to total volume output as an indicator of the integrity of
the transfer system. The containment integrity of waste transfer systems can also be monitored
for radiation levels in excess of those expected from residual waste in the transfer system.
Section 536
A highly reliable means of monitoring for releases is the use of secondary confinement which is
then checked for waste. It also offers the benefit of providing defense-in-depth in containment of
releases of low-level waste.
Example: A liquid low-level waste transfer line from a storage tank to a treatment
facilities is enclosed in a large diameter secondary containment tube. The transfer line
and containment tube were constructed with sufficient pitch to cause any leakage into the
containment tube to flow back to the storage tank area. The transfer line developed a
leak at a coupling which was discovered when waste was found in the secondary
containment at the storage tank area.
What constitutes rapid detection of failed confinement or abnormal conditions needs to be
established for each facility, operation, or activity. Monitoring design requirements and
engineering controls to address catastrophic failures will be established through the conduct of
safety analyses. The failures and conditions being addressed by this requirement are those that are
not catastrophic, but could result in releases of radioactivity or doses to workers or the public in
excess of established limits if they were allowed to continue over a period of hours or days.
Detection equipment needs to be designed to detect confinement failures or abnormal conditions
rapidly enough that action can be taken before the situation degrades to the point that response
and recovery would result in doses to workers that approach the dose limits for radiation
protection of workers (10 CFR Part 835). Similarly if the failure releases radioactivity to a air or
liquid effluent stream, detection needs to occur rapidly enough to prevent environmental releases
from exceeding annual limits.
Compliance with this requirement is demonstrated by designing low-level waste systems with the
capability to monitor waste volume and detect volume changes in a time frame that will allow
implementation of corrective measures to limit public and worker doses to allowable levels and to
limit releases to allowable levels, which are documented in the radioactive waste management
basis for the facility.
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-151
7-09-99
Supplemental References:
1. DOE. Occupational Radiation Protection, 10 CFR Part 835, U.S. Department of Energy,
Washington, D.C.
IV. M.(3) Low-Level Waste Disposal Facility Design. The following facility
requirements and general design criteria, at a minimum, apply:
(a) Confinement. Low-level waste systems and components shall
be designed to maintain waste confinement.
Objective:
The objective of this requirement is to ensure the design of low-level waste disposal facilities
includes features and/or equipment capable of containing low-level waste so that releases that
could result in exposures to workers or the public or that could contaminate the environment are
minimized.
Discussion:
This requirement is invoked to address hazards identified during the safety and hazards analysis
performed in support of the development of this order and manual associated with the release of
radioactive material from low-level waste disposal facilities that could impact workers, the public,
or the environment. In addition to the facility and general design requirements contained in DOE
M 435.1-1, Section I.1.E(18), the requirement for low-level waste confinement must be met.
Section 537
The purpose of confinement systems is to minimize the spread of radioactive and/or hazardous
materials and the release of these materials in facility effluents during normal operations, abnormal
operations, and potential accidents. For disposal facilities, confinement must also be provided
after the facility is closed, for an extended period of time. Therefore, the design of the
confinement systems or equipment for a disposal facility should include process equipment or
features that will minimize the spread of radioactive material during the placement of waste (the
operational period) and systems or equipment that will minimize the spread of radioactive material
after the disposal unit has been closed and into the future. The consequences of losing
confinement for the operational period of a disposal facility may be greater than the consequences
if confinement were lost after closure, where the loss of confinement is generally characterized as
a slow leak from a disposal unit. These differences in the characteristics of a possible loss of
confinement must be considered in designing the appropriate confinement systems or equipment
for a low-level waste disposal facility. The need for redundancy and the degree of redundancy in
these systems for disposal facilities is determined by the safety analysis process and maintenance
Chapter IV - Low-Level Waste Requirements
IV-152 DOE G 435.1-1
7-09-99
concerns for the operational period and by the performance assessment and composite analysis
and associated closure considerations for the post-closure period.
Example: At the Site S disposal facility, primary confinement during operations is
provided by the trench shape of the disposal unit and depth of emplacement of the waste,
and special offloading equipment being used, while post-closure confinement is being
provided by layering of natural materials that have contrasting water retention
properties on the bottom and sides of the disposal unit that create a capillary break.
The number and arrangement of confinement systems or barriers and their required characteristics
for a low-level waste disposal facility are determined on a case-by-case basis. Factors that need to
be considered in confinement system design include type, quantity, form, and conditions for
dispersing low-level waste material during operations and after closure, especially the design basis
conditions postulated for the post-closure period. As in implementation of all of the requirements
of DOE O 435.1 and DOE M 435.1-1, the graded approach is used for determining the
appropriate level of rigor in applying this control to the management systems employed at a
particular low-level waste disposal facility.
Compliance with this requirement is demonstrated by designing low-level waste disposal facilities
including features and/or equipment that provide confinement for the operational period and
following closure of the facility that are based on evaluations which are contained in the facility
radioactive waste management basis.
Supplemental References:
1. DOE, 1992. Nuclear Safety Analysis Reports, DOE 5480.23, U.S. Department of
Energy, Washington, D.C., April 10, 1992.
IV. M.(3) Low-Level Waste Disposal Facility Design. The following facility
requirements and general design criteria, at a minimum, apply:
(b) Ventilation.
1. Design of low-level waste disposal facilities shall include
ventilation, if applicable, through an appropriate
filtration system to maintain the release of radioactive
material in airborne effluents within the requirements
and guidelines specified in applicable requirements.
Section 538
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-153
7-09-99
2. When conditions exist for generating gases in flammable
or explosive concentrations, ventilation systems or other
measures shall be provided to keep the gases in a
non-flammable and non-explosive condition. Where
concentrations of explosive or flammable gases are
expected to approach the lower flammability limit,
measures shall be taken to prevent deflagration or
detonation.
Objective:
The objective of this requirement is to ensure that the design of low-level waste disposal facilities
includes features to remove radioactive materials from airborne effluents that could endanger
worker or public safety and/or the environment to levels allowed in applicable requirements
before they are released, and to preclude or mitigate the accumulation of explosive and oxidizer
gases in the facilities which could lead to uncontrolled releases of radioactive materials.
Discussion:
This requirement is based on a similar requirement invoked to address a group of hazards that was
identified by the safety and hazards analysis performed in support of the high-level waste chapter
of this Manual and which also has been included for the design of low-level waste treatment and
storage facilities. The analysis revealed that very hazardous conditions can result from
unexpected and uncontrolled releases of radioactive material, either because of poorly designed
ventilation systems or due to accumulation and ignition of flammable or explosive gases in high-
level waste storage facilities. Similar circumstances occurring at a low-level waste disposal
facility are similarly problematic, and a similar requirement was believed to be justified to prevent
exposures to workers or the public, radioactive leaks to the environment, and costs for damage
mitigation and cleanup from unanticipated and/or uncontrolled airborne releases of radioactive
material.
The need for disposal facility ventilation systems to meet these requirements is anticipated for
facilities that might impose operational and/or environmental conditions on waste containers and
forms similar to those of a storage or treatment facility that requires ventilation. Generally, it is
not expected that ventilation would be needed for outdoor disposal in trenches or pits. However,
conditions similar to those in a storage or treatment facility might be present in an above-ground
disposal vault configuration, for example, in which a spill could pose a danger to workers inside if
not properly ventilated. The safety analysis documentation for the facility needs to address the
hazards associated with the design of the specific disposal unit and the waste that is expected to
be disposed, and include proper ventilation, as appropriate.
Chapter IV - Low-Level Waste Requirements
IV-154 DOE G 435.1-1
7-09-99
Guidance for subrequirement IV.M.(3)(b)1. is addressed above under Airborne Effluent Filtration
Systems and subrequirement IV.M.(3)(b)2. guidance is discussed under Flammable and Explosive
Concentrations in the discussion on meeting requirements IV.M.(2)(b)1. and IV.M.(2)(b)2. for
low-level waste storage and treatment facilities.
Compliance with this requirement is demonstrated if ventilation systems are included in the design
of low-level waste disposal facilities when appropriate that can be demonstrated will limit airborne
radioactive effluents to applicable legal and/or regulatory limits and that will prevent the
accumulation of explosive or flammable gases in concentrations that could result in an
uncontrolled release of radioactive material.
Section 539
Supplemental References:
1. DOE, 1990. Radiation Protection of the Public and the Environment, DOE 5400.5, U.S.
Department of Energy, Washington, D.C., February 8, 1990.
IV. M.(3) Low-Level Waste Disposal Facility Design. The following facility
requirements and general design criteria, at a minimum, apply:
(c) Stability. Low-level waste disposal facilities shall be designed
to achieve long-term stability and to minimize to the extent
practical, the need for active maintenance following final
closure.
(d) Control of Water. Low-level waste disposal facilities shall be
designed to minimize to the extent practical, the contact of
waste with water during and after disposal.
Objective:
The objective of these requirements is to ensure that the design features of low-level waste
disposal facilities provide for three basic objectives of safe and environmentally protective
radioactive waste disposal: that the facilities will be stable for a long time; that little or no active
maintenance is needed to maintain this desired stability after the facility is closed; and that contact
of waste and water that could degrade waste forms or transport radionuclides is minimized.
Discussion:
During the safety and hazard analysis conducted in developing the requirements of DOE O 435.1
and DOE M 435.1, providing continued protection into the future from disposed waste was
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-155
7-09-99
identified as a measure to reduce potential exposures to the public, workers, and the environment.
The analysis indicated that some controls are necessary after a low-level waste disposal facility
has been closed and that it is prudent to address long term ramifications of the disposal of waste
in the early stages of facility design. Certain features of design can be utilized to provide an
additional depth of defense against exposure of workers, the public, or the environment to the
hazards posed by the disposed low-level waste. These two design requirements for a low-level
waste disposal facility implement two of the fundamental concepts embodied in 10 CFR Part 61,
stability of the disposal site and control of surface and groundwater at the site.
Several features have been used in the designs of past low-level waste disposal facilities to achieve
stability of the facility during and after disposal, to reduce the need for active maintenance once
the facility is closed, and to control water so that there is little contact of waste with water, both
before and after it is disposed. Engineering barriers/features can include use of rip cap, liners, and
depth of cover. Many design features serve to meet both of these requirements at the same time.
Also, some design features, when combined with operational practices, achieve the most benefit
towards achieving the objectives of these requirements. Subrequirement IV.M.(3)(a) is discussed
in the section below entitled, Stability, and subrequirement IV.M.(3)(b) is discussed in the section
entitled, Control of Water.
Section 540
Stability. The ability of a low-level waste disposal facility to remain stable for the long-term is a
fundamental goal in the meeting the performance objectives for disposal of low-level waste as
defined in Chapter IV, Section P.(1) of DOE M 435.1-1. The discussions on long-term stability
in the Nuclear Regulatory Commission’s rulemaking documentation and guidance for 10 CFR
Part 61 note that site stability should be relied on for the indefinite future, and evaluated for a
period of at least 500 years for purposes of presenting information on design of the facility in a
license application. Long-term stability for DOE low-level waste disposal sites is to be considered
an attribute that needs to be present for the indefinite future, and is determined on a site-specific
basis from analysis of site conditions, any waste that requires structural stability, and the desired
performance of the facility. Site-specific timeframes, therefore, should be used for design bases
events or phenomena, where appropriate, when designing the facility to ensure long-term stability
of the site for the purposes of meeting DOE O 435.1 and DOE M 435.1-1.
There are several principles in establishing the design of the facility that are key to the objective of
long-term stability. First, the design features of the low-level waste disposal facility need to be
directed toward the long-term isolation of the waste, the minimization of migration of
radionuclides, and the avoidance of any need for continuing long-term active maintenance after
closure. Second, the design of the facility needs to lead to closure and the development of a
closure plan that provides assurance that the performance objectives will continue to be met into
the future. Third, the disposal site needs to be designed to complement and augment wherever
possible the ability of the disposal site’s natural characteristics to assure that the performance
objectives will continue to be met.
Chapter IV - Low-Level Waste Requirements
IV-156 DOE G 435.1-1
7-09-99
A low-level waste disposal facility needs to be sited and designed to permit efficient land
utilization and maximum waste volume allocation, while maintaining long-term stability and
isolation. Facility design is based on the projected waste volume and characteristics including the
projected volume of waste to be disposed of over the life of the facility, chemical composition of
the waste, radionuclide content and concentration, and the expected physical form in which the
waste will be received. This information is used to estimate the number of disposal units required
for the facility, and for determining the need for special engineered features. For example, based
on projected receipts of high-activity low-level waste, special excavation designs such as slit
trenches and auger holes may be required in order to provide adequate worker protection.
The spacing between disposal units needs to be considered in establishing the overall dimensions
of units. Sufficient space between adjacent units is needed to assure disposal unit integrity, for
example, the distance between disposal units is such that positioning and use of equipment at a
newly excavated unit will not adversely affect the stability of the unit’s walls and will not disturb
nearby disposal units. Disposal unit spacing needs to also take into account the need for any
buffer zone between disposal units and the boundary of the disposal facility that may be planned.
Section 541
Example: The new disposal facility at the Brown Site has been designed using trench
disposal units sized to dispose of approximately 6 months worth of waste receipts at a
time. The design calls for the trenches to be separated from one another by 50 feet
intervals, as configured after analysis of the expected trench side activities, including
some vehicular traffic. A remedial action is taking place adjacent to the new facility, so
a relatively large (300 feet) buffer zone is established between the two projects to address
a concern of stakeholders regarding future continuing activities that may be necessary at
the remedial action site.
The design of individual disposal units also contributes to the long-term stability of the facility.
The size of disposal units needs to be determined based on the physical size and topography of the
disposal facility, the types and volumes of waste to be disposed, and the dimensions of waste
containers to be buried. Soil characteristics, the need for equipment access and maneuvering
space, and surface water drainage before, during, and after waste emplacement are considered in
deciding on the size and type of disposal units. The depth of disposal units is also a site-specific
design determination which is dependent on the depth of the ground-water table, the need for the
stability of sidewalls, and the depth of disposal of certain categories of waste, if appropriate.
Disposal units generally are oriented parallel to topographic contours of the site. Slopes of the
site should not be so steep as to result in significant elevation differences between sidewalls of a
disposal unit. In addition, the elevation difference of the ground surface between one end of a
disposal unit and the other end needs to be less that the combined thickness of the backfill
overlying the waste and the disposal unit cover.
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-157
7-09-99
The planned sequence of use of disposal units over the facility lifetime needs to reflect the need to
conduct adequate closure and stabilization operations, as each unit is filled. The location of roads
and disposal unit covers, use of heavy equipment, establishment of vegetative cover, and
management of surface water are planned such that operations may be conducted at each disposal
unit without damage to closed disposal units. Location and access to fill and borrow areas are
also planned to assure that they do not compromise the integrity of completed disposal units.
Final slopes of disposal units when shallow land trenches are used are designed to minimize
erosion and failure of slopes. Both potential problems can be minimized by controlling the slope
angle, particle size of the soil, degree of compaction or cementation, and vegetative cover. In arid
regions, where infiltration of water is of less concern and where vegetation may be difficult to
establish, gravel or cobbles may be used in place of vegetation to protect the slope.
Example: The trench sides at the Brown Site low-level waste disposal facility are sloped
at a 80% angle, as configured by soil analysis calculations to remain stable, and are
protected along the entire length of the trench by geofabrics. The trench at the end of the
first row of trenches is designed to be only half as long as its predecessor trenches
because the gradient of the site was beginning to increase, and more chance of instability
would be likely if the same size trench was built.
Section 542
The disposal site is designed to enhance and not degrade the natural physical characteristics of the
area that support long-term stability, and to minimize the consequences of potential abnormal
events. Therefore, based on site characteristics, for example a large rainfall or expected damage
from high winds, and the expected waste characteristics and forms, appropriate engineered
barriers may be required to enhance the natural site characteristics for site stability. Primary
concerns are to reduce the effects of erosion over time and to minimize the impacts to site
stability by an abnormal event.
The use of common engineering materials to augment the long-term stability of a low-level waste
disposal facility is to be carefully planned. A critical examination needs to be made of each
component of a disposal unit and compared to that of the unit as a whole, and a determination
made considering the cost and difficulty of utilizing these materials versus the benefits to
maintaining stability. For example, geotextiles and geomembranes may not have a long design
life, but they may contribute to the stability of the disposal unit as a whole by making placement
of critical materials during closure much easier.
Control of Water. There are also some principles that are key to the objective of minimizing the
contact of waste with water before, during, and after disposal. First, covers of disposal units need
to be designed to minimize water infiltration to the extent practical, and to direct percolating or
surface water away from the waste. Second, surface features need to direct surface water
drainage away from disposal units at velocities and gradients which will not result in erosion that
Chapter IV - Low-Level Waste Requirements
IV-158 DOE G 435.1-1
7-09-99
will require ongoing active maintenance in the future. Third, the disposal unit needs to be
designed to minimize the contact of waste with water during storage, the contact of waste with
standing water during disposal operations, and the contact of wastes with percolating or standing
water following disposal.
Disposal units are designed to minimize infiltration of water into the unit over the long term.
Several factors must be considered in the design of the disposal unit to result in a disposal unit
with sides and a cover which will behave as desired, including: the permeability of the natural
materials the units will be constructed of and within, wind and water erosion, root penetration,
animal burrowing, consolidation, subsidence, desiccation, freeze-thaw cycles, and frost heave.
The design must evaluate whichever of these elements are applicable for a particular site and
design, and ensure the impacts of these are accounted for in minimizing infiltration of water into
the unit.
The cover is to be designed to facilitate drainage and should be several feet in thickness at its
thinnest point, if appropriate. For example, at a humid site using the trench disposal method, clay
barriers are desirable as part of cover systems because of its relatively low permeability. To
assure the integrity of the clay portions of cover systems, it should be insulated from the surface
geologic, atmospheric, and biotic processes by one of more layers of other types of materials.
The cover should extend beyond the site walls of the unit and be directly tied into the surface
drainage system at the original or modified grade to assure surface runoff is not directed along the
sidewalls down into the unit. Cover design needs to include stabilization of some fashion to
assure that it is not significantly affected by wind or water erosion. For example, in humid
climatic regions, such stabilization can be achieved by planting of a shallow rooted vegetative
cover.
Section 543
A surface water management system may be necessary as part of the disposal facility design to
minimize erosion and infiltration into disposal units. An adequate system will usually consist of
three primary parts: collection, transport, and discharge. The collection part of the system is to
collect runoff from disposal unit covers in drainage ditches. These ditches are sloped to allow
transport of all the surface runoff to a drainage collector physically removed from the active
disposal area to allow discharge of the water off-site. This type of system may be considered
desirable for a shallow land trench or other near surface disposal facility within a humid or
moderate climatic regime. Factors to evaluate the necessary requirements for a drainage system
include the capability for managing a 10-year return flood and for diverting a postulated 500-year
flood. Another method instead of this system for smaller sites could incorporate a uniform,
crowned cover designed to remove the runoff by sheetwash.
Example: The spaces between trenches at the new disposal facility at the Brown Site are
designed to steer water towards one of four collection areas in the facility. These
collection areas then drain water to a central collection area away from both the low-
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-159
7-09-99
level waste disposal facility, and the remedial action project which is adjacent to the
facility for discharge.
Disposal units must be designed to drain effectively when water enters the disposal facility.
Bottom drainage can be accomplished by designing the disposal unit floor to be covered with 2
3 feet of pervious material, such as sand, and to be sloped across the width of the unit to a french
drain. The disposal unit floor and the french drain would be sloped along the length of the unit to
sumps. The bottom layer would also serve as a barrier to the capillary rise of water from below.
The base of a completed disposal unit should drain faster than water enters from the top and sides
of the facility. Inclusion of a system like this serves to rapidly drain off water entering the
disposal unit before it is covered and minimizes the time any infiltrating water would be in contact
with the waste.
Example: At the new disposal facility at Site Y, trench bottoms are designed with a
multi-layer system of geofabrics and natural materials that will drain water towards one
side of the trench and then towards one end of the trench to a monitoring well location.
The geofabrics protect the layers of natural material during operations, but are not
relied upon for providing drainage characteristics. The cover design includes a multi-
layered system that is designed to drain water away from the trenches and reduce
infiltration, and includes a deep rooted grass cover on the top. The cover does not use
any geofabric, since no activities are expected on the cover which would disturb its
layering.
Void spaces between waste packages need to be filled with a freely-draining non-cohesive
material, such as clean sand or gravel. These types of materials will promote rapid movement of
water through the disposal unit. In addition, if the backfill has a sufficient contrast in permeability
to the material in the disposal unit cap, capillary forces may promote unsaturated flow of
interstitial water around the disposal unit instead of through it. Instead of a free-draining backfill,
material with extremely low permeability, such as grout or concrete would be used. Clay-soil
mixtures may not be suitable for backfill because of the difficulty in ensuring that void spaces are
filled and the difficulty in achieving sufficient compaction to limit consolidation and permeability
to acceptable levels.
Section 544
Contact of waste with water during disposal operations must be minimized. Closing down site
disposal operations until disposal units are free of visible water is one approach to achieving this.
Active disposal units could be allowed to drain into a sump or into the inactive part of the unit
before waste is emplaced. Keeping the volume of uncovered waste in the disposal units to a
practical minimum is another approach to minimizing contact of waste with water, as is the
practice of placing backfill over the waste as soon as possible after emplacement in the disposal
unit. Acceptable low-level waste disposal facility operations are discussed in the guidance on
DOE M 435.1-1, Section IV.P.(6).
Chapter IV - Low-Level Waste Requirements
IV-160 DOE G 435.1-1
7-09-99
Compliance with this requirement is demonstrated by the design features of the subject low-level
waste disposal facility being focused on achieving and maintaining stability of the disposal site,
minimizing the need for any active maintenance of the disposal facility following its closure, and
preventing the contact of waste with water, both during operations of the facility and following
closure, and these design considerations are justified and documented in the radioactive waste
management basis for the facility .
Supplemental References:
1. NRC, 1982. Technical Position Paper on Near-Surface Disposal Facility Design and
Operation, U.S. Nuclear Regulatory Commission, Washington, D.C., November 1982.
2. DOE, 1989. Methodology for Compliance with DOE Order 5820.2A Chapter III:
Management of Low-Level Radioactive Waste. DOE/LLW-75T, U.S. Department of
Energy, National Low-Level Waste Management Program, Idaho Falls, ID, February
1989.
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-161
7-09-99
IV. N. Storage and Staging.
The following requirements are in addition to those in Chapter I of this Manual.
(1) Storage Prohibitions. Low-level waste in storage shall not be readily capable
of detonation, explosive decomposition, reaction at anticipated pressures and
temperatures, or explosive reaction with water. Prior to storage, pyrophoric
materials shall be treated, prepared, and packaged to be nonflammable.
Objective:
The objective of this requirement is to promote safe storage of low-level waste by eliminating
from storage materials which could result in fires or explosions due to their reactivity or
ignitability.
Discussion:
The safe storage of low-level waste can be jeopardized by the presence of materials which may
ignite or explode. To avoid the potential for accidental releases from stored wastes, this
requirement prohibits storage of materials that are known to be readily capable of ignition or
explosion, or which may degrade over time to be ignitable or explosive. In establishing waste
acceptance criteria for storage, waste managers must prohibit the acceptance of materials which
have the potential of igniting or exploding. The following materials are not to be stored:
• Reactive metals - metals that can react violently with water, form potentially explosive
mixtures with water, or ignite when exposed to air; e.g., non-stabilized uranium or
plutonium metal turnings.
• Certain dried ion exchange resins - organic ion exchange resins which have been used for
treating solutions containing nitrates have the potential of igniting or exploding if they are
allowed to dry out.
Section 545
• Cellulosic materials contaminated with strong oxidizers - cellulosic materials can
spontaneously ignite in the presence of strong oxidizers, e.g., concentrated nitric acid.
• Volatile materials, if stored in areas of high temperatures - storage of volatile materials in
closed containers subject to high temperature can result in pressurization of the container
and, depending on the waste materials, evolution of flammable gases.
• Pyrophoric materials - nonradioactive materials which can ignite spontaneously are not to
be packaged for storage. Radionuclides which may be pyrophoric are to constitute less
Chapter IV - Low-Level Waste Requirements
IV-162 DOE G 435.1-1
7-09-99
than 1% by weight of the container contents unless they are treated to eliminate the
pyrophoric characteristic.
When waste with the characteristics described above have been generated, it is necessary to
ensure that they are properly pre-treated or treated prior to placing them into storage. Treatment
may consist of causing the reaction to occur under controlled conditions, e.g., oxidation of
uranium turnings, or may involve the stabilization of waste materials so that they are no longer
flammable or explosive.
Example 1: Some old glove boxes that contain laboratory equipment such as test tubes,
plastic bottles, wooden utensils, record books, various unidentified materials, and some
laboratory chemicals are being cleaned out at Laboratory A. Some bottles of nitric acid
are included in the chemicals being discarded. The nitric acid is neutralized prior to
placement in the waste container so that there is no interaction with the wooden utensils
and any other cellulosic materials that might be in the lab waste.
Example 2: The fuel fabrication prototype facility at Site Z regularly generates waste
containing uranium turnings from the fabrication of test fuel specimens and prototype
targets. The turnings are solidified in a cement solution formulated specifically for this
use in specially designed cans before being packaged in 55 gallon drums for shipment to
a disposal facility.
Compliance with this requirement is demonstrated by having waste acceptance requirements
which prohibit low-level waste that is ignitable or explosive from being accepted for storage
unless it has been treated, and procedures for properly preparing such materials for safe storage.
IV. N.(2) Storage Limit. Low-level waste that has an identified path to disposal
shall not be stored longer than one year prior to disposal, except for
storage for decay, or as otherwise authorized by the Field Element
Manager.
Objective:
The objective of this requirement is to limit low-level waste in storage, provide for the timely
disposal of low-level waste, and to limit waste from being stored for indefinite periods of time.
Low-level waste is to be actively managed so that final disposition can be achieved with a
minimum of storage time during its life cycle.
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-163
7-09-99
Discussion:
The storage of low-level waste plays an important role in the management of low-level waste, and
provides the opportunity to optimize treatment and disposal activities. The need to store low-
level waste should be balanced with the potential risk that storage of the waste may present.
During the development of the requirements in DOE M 435.1-1, the storage of low-level waste
was identified as an activity that presented potential risk to the public, workers, and the
environment. In addition, The Complex-Wide Review of DOE’s Low-Level Waste Management
ES&H Vulnerabilities (DOE/EM-0280) identified inadequate storage conditions for low-level
waste and storage of low-level waste that has an identified path to disposal as vulnerabilities.
Section 546
The primary requirement for the storage of low-level waste is in DOE M 435.1-1, Section
I.2.F.(13), which charges the responsibility for safe storage with the Field Element Manager.
Storage is defined as the collection and management of waste for the purpose of awaiting
treatment or disposal, in such a manner as to not constitute disposal of the waste. Three scenarios
for the collection and management of low-level waste are provided for in DOE M 435.1-1,
Chapter IV, and discussed in this guidance.
1. The storage of low-level waste with an identified path to disposal.
2. The storage of low-level waste that does not have an identified path to disposal.
3. The accumulation of low-level waste for less than 90 days, referred to as staging.
This requirement is directed at the storage of low-level waste with an identified path to disposal
and is intended to reduce the total amount of low-level waste in storage, provide for the timely
disposal of low-level waste, and minimize the indefinite storage of waste in conditions that are or
could become unsuitable. Life cycle planning for the management of low-level waste is required
as part of the Site-Wide Waste Management Program and includes a documented understanding
of the disposal options for the waste (see Section I.2.E.(1)). An identified path to disposal
determination is based primarily on the ability of the waste to meet the waste acceptance
requirements of a disposal facility and authorization of the disposal facility to accept that waste.
Some waste may not have current disposal options, and thus has no identified path to disposal. A
waste that can meet an existing disposal facility’s waste acceptance requirements is considered to
have an identified path to disposal.
Example: A site is indefinitely storing low-level waste that has a disposal option. The
waste is characterized and could meet the requirements of an off-site disposal facility if
repackaged. As of the issuance of DOE O 435.1 this low-level waste should be
repackaged and received by a disposal facility within one year.
One Year Storage Limit. Determination of the one year time limit is based on the dates recorded
by receiving facilities consistent with the documented process for transferring responsibility of the
Chapter IV - Low-Level Waste Requirements
IV-164 DOE G 435.1-1
7-09-99
waste described in requirement DOE M 435.1-1, Section IV.K.(3). The staging of waste at any
generator or treatment facility prior to acceptance by a storage facility need not be included in the
one-year time limit. In addition, the staging by a disposal facility prior to disposal also need not
be included in the one-year time limit. However, if multiple storage facilities are utilized during
the life cycle management of the waste, the total combined storage time of all storage facilities is
used to determine if the waste has reached the one-year limit for storage.
Example: Low-level waste is staged at a generator facility for two months prior to
transfer to a storage facility. The waste is at the storage facility for five months and
transferred to a treatment facility. The treatment facility holds the waste for two months
and then treats the waste. The waste has been held in storage for a total of seven months
and needs to be transferred to and received by a disposal facility within five months.
Section 547
The intent of this requirement is not that an undue focus be placed on the compliance or non
compliance with the one-year limit. In other words, the requirement is not intended to force
heroic efforts to remove containers of low-level waste from storage for disposal before the one
year is reached, or to cause additional handling of low-level waste so the storage clock can be
restarted. Rather, the intent of this requirement is to focus attention of managers at the site
towards ensuring that waste is being managed to disposal under reasonable time frames. If it
appears that the storage limit will be exceeded, managers should evaluate the conditions of
storage and determine a proper and safe course of action. The evaluation of the existing storage
conditions needs to determine if the waste has undergone any changes that could impact the
characterization data or container information that exists for the waste, such as damage to any
waste containers, and whether continued storage under the same conditions will maintain the
waste in a condition that it can be disposed without further treatment or characterization. The
manager may also need to determine if the reasons for the extended storage period will be
resolved any time soon, and if the answer could be no, then deciding if alternative management
paths need to be identified for the waste.
Storage longer than one year can be justified if the conditions for such storage are approved by
the Field Element Manager as part of the radioactive waste management basis for the facility. The
conditions are to be based on the evaluations of the existing storage conditions and any steps that
are necessary to provide for timely disposal of the waste conducted by the manager when it was
determined that the one-year storage limit was not going to be met. For example, conditions
specifying the additional storage period beyond the one-year which is authorized and some
mandatory maintenance of containers (see guidance for DOE M 435.1-1, Section IV.N.(5)) may
be appropriate when the radioactive waste management basis is amended to allow for additional
storage time. These provisions should also include a date or time period (e.g., 1 year) when
storage conditions will be reevaluated to determine if storage longer than one year can be
continued and provisions for appropriate facility operations (such as container inspections) that
ensure the hazards of the waste are still controlled.
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-165
7-09-99
Storage for Decay. Storage for radioactive decay for a period greater than 1 year for waste that
has an identified path to disposal is allowed. Adequate justification and the supporting
information for storage for decay is to be documented in the radioactive waste management basis
for the facility in which the storage will take place. Adequate justification for storage for decay
includes reduced cost, reduced risk, and the ability to achieve disposal that might not otherwise be
available. When using storage for decay as a management option, waste acceptance requirements
are to be developed for the storage facility that are compatible with the requirements for waste
disposal. These waste acceptance requirements are part of the radioactive waste management
basis for the storage facility approved by the Field Element Manager.
Section 548
Mixed Low-Level Waste. Mixed low-level waste in storage may present a dilemma for
determining compliance with the storage requirements. Some mixed low-level waste generated in
the complex would fall into the category of not having an identified path to disposal, and should
meet only the storage requirements for no path forward waste. However, some mixed low-level
waste has an identified path to disposal, but must remain in storage for some period of time that
exceeds one year, awaiting treatment processes or for other reasons. The Field Element Manager
needs to determine the appropriate way to exempt this waste from the storage limit requirement.
Note that because the hazardous component of mixed low-level waste is subject to the Resource
Conservation and Recovery Act, special requirements apply, including a prohibition on storage.
In accordance with the Resource Conservation and Recovery Act Land Disposal Restrictions,
storage of land disposal-restricted waste is prohibited, other than for the purpose of accumulation
to facilitate treatment. Under the Federal Facility Compliance Act of 1992, DOE sites were
required to develop Site Treatment Plans to bring stored mixed low-level waste into compliance
with these requirements. The Site Treatment Plan needs to be consulted and any mixed low-level
waste stored for the purpose of accumulation to facilitate treatment must meet Resource
Conservation and Recovery Act storage requirements. There could be several ways within
different scenarios that this requirement can be met, as illustrated by the examples below,
however, there are basically four ways to show compliance with the requirement and include
appropriate provisions in the radioactive waste management basis for the facility in which it is
stored. These provisions should include a date or time period (e.g. one year) when the storage
conditions will be re-evaluated to determine if storage longer than one year can be continued and
provisions for appropriate facility operations (such as container inspections) that ensures the
hazard from the radioactive component of the waste is still controlled.
Legacy Waste. Several questions have arisen concerning the ability of some Department facilities
to comply with the one-year storage limit because they store “legacy low-level waste.” Legacy
waste generally refers to large quantities of waste at a few DOE sites that has been in storage for
more than one year already, and may require additional technical studies, characterization,
treatment, or resources dedicated to it, to properly dispose of the waste. The entire volume of
Chapter IV - Low-Level Waste Requirements
IV-166 DOE G 435.1-1
7-09-99
legacy waste at these sites cannot be removed from storage under any reasonable scenario that
implements the one-year storage limit. As discussed above, the intention of the requirement is not
to force malicious compliance or heroic actions which would result in increased risk or safety
concerns. Rather, the intention is that waste in storage longer than one year receives additional
attention to ensure that the public, the workers, and the environment are protected from the
hazards of the waste, and that progress is being made to dispose of the waste. There could be
several ways within different scenarios that this requirement can be met, as illustrated by the
examples below, however, there are basically four ways to show compliance with the
requirement:
1) the radioactive waste management basis allows for storage for no more than one
year.
Section 549
2) the radioactive waste management basis allows for storage for no more than one
year, or for storage for decay only for periods greater than a year, which are
specified on a radionuclide basis.
3) the radioactive waste management basis allows for storage for more than one year,
up to a specified period of time based on a documented technical evaluation that
the waste can be stored in a manner that does not cause changes to the waste or
waste packages that is detrimental to the safe storage of the waste, the final
disposal of the waste or to meeting the disposal performance objectives.
4) the radioactive waste management basis allows for storage for decay (with
specifics) and for storage for more than one year for other low-level waste, up to a
specified period of time based on a documented technical evaluation that the waste
can be stored in a manner that does not cause changes to the waste or waste
packages that is detrimental to the safe storage of the waste, the final disposal of
the waste or to meeting the disposal performance objectives.
The documented technical evaluation the requirement if one is necessary needs to include an
analysis that describes the waste containers, the design of the waste containers, the design life of
the waste containers, and the storage conditions for the container over its service life. The
analysis needs to address the total anticipated storage period and should demonstrates waste
container integrity will be maintained for the extended time period.
Example 1: Storage of low-level waste at Site A occurs in Building 700. The storage
period never exceeds 9 months before it is shipped for disposal at Site X. The radioactive
waste management basis for Building 700 approves this storage with no additional
provisions.
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-167
7-09-99
Example 2: Storage of low-level waste at Site B occurs in Building 400. The storage of
low-level waste occurs over various periods of time, but never greater than 15 months
before it is shipped for disposal. The Field Element Manager determines, based on
container integrity and storage configuration, that the 15 month period of time is
acceptable and approves the radioactive waste management basis for Building 400 with
no additional provisions.
Example 3: Storage of low-level waste at Site 900 includes storage for decay for three
waste streams up to a period of 5 years, and for other low-level waste streams for 14
months. The radioactive waste management basis for the Site 900 storage facility allows
for storage for decay for up to 5 years for the three waste streams only, based on an
analysis of container integrity, with additional provisions ensuring segregation of decay
waste from other waste.
Example 4: Storage of low-level waste at Site G is being done at the generator facilities,
and it can last for up to 16 months prior to disposal. The radioactive waste management
basis for the generator facility does not address storage. Exceedence of the one year
storage limit is a non-compliance. (Also see guidance on Staging, DOE M 435.1-1,
Section IV.N.(7) below)
Section 550
Example 5: Hanford’s Central Waste Complex (CWC) stores Mixed Low-Level Waste
(MLLW), low-level waste, and transuranic waste from inclement weather. The bulk of the
CWC inventory is MLLW received from both on and off site generators to be managed
until treatment technologies become available and disposal is achieved. Because it is
technically impossible to dispose of the CWC’s MLLW inventory within one year and the
waste has an identified path to disposal, a technical evaluation is prepared. The
extended storage of MLLW at CWC is fully justified, determined to be safe, and is the
preferred interim management technique. Documentation supporting this decision is
included in the radioactive waste management basis for the CWC, as well as a
description of the container inspection and reporting program already in place to ensure
continued safe storage.
Compliance with this requirement is demonstrated by the existence of a radioactive waste
management basis for the storage facility approved by the Field Element Manager that includes
the time frames that waste are allowed to be stored, the necessary justifications for storage for
decay, and the necessary technical evaluations if storage is to extend significantly beyond the one-
year time frame.
Chapter IV - Low-Level Waste Requirements
IV-168 DOE G 435.1-1
7-09-99
IV. N.(3) Storage Integrity. Low-level waste shall be stored in a location and
manner that protects the integrity of waste for the expected time of
storage and minimizes worker exposure.
Objective:
The purpose of this requirement is to ensure that the selection of the location and method for
storing low-level waste is made so that both workers and the containers of waste are provided
with adequate protection.
Discussion
During the development of DOE O 435.1 and DOE M 435.1-1, the storage of radioactive waste
was identified as an activity that presented potential risk to the public, workers, and the
environment. Numerous weaknesses and conditions which could lead to release of waste or
exposure of workers were identified during the safety and hazards analysis and subsequent
reviews conducted in support of the Manual documentation. In addition the Complex-Wide
Review of DOE’s Low-Level Waste Management ES&H Vulnerabilities revealed inadequately or
improperly stored low-level waste, which presents the possibility of human exposure to radiation
and the potential for adverse environmental effects.
The Complex-Wide Review and the evaluations of storage that were conducted during
development of the Order and Manual revealed a variety of current practices and lengths of
storage for low-level waste. Low-level waste is stored in dense-pack arrays, in conditions
exposed to the elements, and in modern, RCRA-compliant storage facilities. In addition,
buildings not originally designed or intended for storage are sometimes used when other storage
capacity is not available.
As discussed in the General Requirements guidance on storage (DOE M 435.1-1, Section
I.2.F.(13)), a principal element of proper storage is ensuring that containers are protected from
degradation and perform their intended function until disposal. This requires that containers be
protected from mechanical damage and from environmental conditions that could degrade the
confinement provided by containers.
Section 551
Example 1: Due to a large decommissioning project generating unanticipated volumes of
low-level waste, Site Z decided to store low-level waste outside until indoor storage space
could be made available. In accordance with the Packaging and Transportation
requirements, filtered vents were installed on the drums used for packaging the waste.
However, in establishing the radioactive waste management basis for the outside storage
pad, personnel failed to recognize the potential for precipitation entering the drums.
Rain accumulated on the tops of the drums, then due to fluctuations in barometric
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-169
7-09-99
pressure, the drums “breathed” through the vents. Water was sucked in through the
vents resulting in the need to repackage the waste to meet the waste acceptance
requirements for disposal. Subsequently, any waste drums that had to be left outside
were provided with protective covering from precipitation.
Example 2: Due to a large backlog of low-level waste, Site X is required to store low-
level waste outside until it can be treated and/or disposed. The waste is stored in
containers which prevent the entrance of precipitation (lid with lips extending down over
the sides) and which resist corrosion (painted carbon steel). Controls are in place to
limit mechanical damage from vehicles and other operations in the area. The containers
are inspected on a monthly basis for deterioration and repaired as necessary to maintain
containment of the waste (e.g., painted, contained). Personnel are only in the outside
storage area during periods of inspections, container maintenance, and container
movement. The outside storage has been analyzed and documented to provide adequate
protection for the expected storage time. This storage maintains the integrity of the
waste and minimizes worker exposure.
As noted earlier, low-level waste may be stored in facilities which were not originally designed for
storage. If the facilities have the appropriate provisions (e.g., ventilation, fire suppression) for the
type of waste being stored, their use is preferential to storing the waste containers outside and
subjecting them to the elements. However, in making a decision to use a facility for storage and
in developing a radioactive waste management basis for the activity, particular attention to
protection of workers is needed. Waste is not to be stored in areas where workers are required to
spend extended periods of time in performing other duties (i.e., any duties not related to managing
and monitoring the waste). This limits the facilities or areas of facilities that could be used for
waste storage to those that are excess to current site missions or those that are infrequently
accessed as part of normal operations.
Compliance with this requirement is demonstrated if sites have storage capabilities for low-level
waste that provide protection to waste containers so that their integrity will not be damaged
through physical or chemical (corrosion) processes and that keep personnel from spending
extended periods of time in the areas where low-level waste is stored.
Supplemental References:
1. DOE, 1996. Complex-Wide Review of DOE’s Low-Level Waste Management ES&H
Vulnerabilities, DOE/EM-0280, U.S. Department of Energy, Washington, D.C., May
1996.
Chapter IV - Low-Level Waste Requirements
IV-170 DOE G 435.1-1
7-09-99
IV. N.(4) Waste Characterization for Storage.
Section 552
(a) Low-level waste that does not have an identified path to
disposal shall be characterized as necessary to meet the data
quality objectives and minimum characterization requirements
of this Chapter, to ensure safe storage, and to facilitate
disposal.
Objective:
The objective of this requirement is to establish, document, and maintain minimum
characterization information for low-level waste that does not have an identified path to disposal.
Minimum characterization information will facilitate future disposal because the historical
knowledge of the waste is preserved. Characterizing low-level waste with no identified path to
disposal will enable it to be stored safely and for disposal options to be evaluated. When a
disposal option is ultimately identified the nominal characterization information necessary for it to
be acceptable for disposal will be available.
Discussion:
The establishment and maintenance of characterization information is essential for the safe and
effective management of low-level waste. During the development of the Radioactive Waste
Management Manual (DOE M 435.1-1), the storage of low-level waste without a path to
disposal was identified as an activity that presented potential for waste to exist without being
adequately characterized. The Complex-Wide Review of DOE’s Low-Level Waste Management
ES&H Vulnerabilities (DOE/EM-0280) revealed that inadequacies and inaccuracies in
characterization efforts complicate effective waste management activities and results in an
increased risk of release to the environment and exposure to workers and the public.
Example: High activity low-level waste is stored in a generator facility hot cell. The
waste is generally believed to have no identified path to disposal. However, because the
waste has not been characterized, a path forward cannot be established and the historical
knowledge of the waste is jeopardy of being lost or forgotten.
The requirement to characterize all low-level waste is in DOE M 435.1-1, Section IV.I. In the
interest of accuracy and future economics, characterization is necessary to facilitate future
disposal of low-level waste without a path to disposal. If the characterization necessary for future
disposal is not performed and documented in a timely manner, then the ability to dispose of the
waste may be compromised. The storage of waste represents the opportunity for characterization
information to be inadequately managed and ultimately lost or forgotten. This requirement is
intended to capture characterization information, both direct and indirect (process knowledge,
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-171
7-09-99
materials accountability, etc.) so that when disposal options are available, characterization will not
have to be repeated and possibly not required at all.
Example: A certain low-level waste stream has no identified path to disposal based on
preliminary information. Prior to placement in storage the waste is nominally
characterized as required and pertinent information concerning the process that
generated the waste is documented. Some years later, a treatment facility is identified
that is capable of accepting the waste and producing a waste form that meets the disposal
facility waste acceptance requirements.
Waste with no identified path to disposal needs to be characterized to provide the minimum
information required for safe storage as well as other typical data elements required for disposal.
An example of the typical characterization information that should be documented is that which
would be required by an existing on-site disposal facilities waste acceptance requirements.
Section 553
Example: A generator’s preliminary information indicates that a certain low-level waste
stream has no identified path to disposal. The site has no on-site disposal facility so the
generator decides to characterize the waste as if complying with an existing off-site
disposal facilities requirement. Characterization data are used to develop a safe storage
configuration for the waste awaiting identification of a disposal option.
Compliance with this requirement is demonstrated by documenting the characterization
information for low-level waste with no identified path to disposal. The information includes the
minimum data elements listed in DOE M 435.1-1, Section IV.I.(2) and the data quality objectives
process is used for identifying the characterization parameters. In addition, any other
characterization information that may facilitate future disposal is collected and maintained.
Supplemental References:
1. DOE, 1996. Complex-Wide Review of DOE’s Low-Level Waste Management ES&H
Vulnerabilities, DOE/EM-0280, U.S. Department of Energy, Washington, D.C., May
1996.
2. EPA, 1994. Guidance for the Data Quality Objectives Process, EPA QA/G-4,
U.S. Environmental Protection Agency, Washington, D.C., September 1994.
IV. N.(4) Waste Characterization for Storage.
(b) Characterization information for all low-level waste in storage
shall be maintained as a record in accordance with the
Chapter IV - Low-Level Waste Requirements
IV-172 DOE G 435.1-1
7-09-99
requirements for Records Management in Chapter I of this
Manual.
Objective:
The objective of this requirement is to ensure that characterization information on waste in
storage is maintained as a Federal record, providing a traceable path if future actions require
knowledge of the original characterization information.
Discussion:
The establishment and maintenance of characterization information is essential for the safe and
effective management of low-level waste. During the development of the Radioactive Waste
Management Manual (DOE M 435.1-1), the storage of low-level waste, specifically long-term
storage, was identified as an activity that presented potential for waste characterization
information to be lost, forgotten, or otherwise mismanaged.
Example: Following characterization, it was determined that a specific low-level waste
stream had no identified path to disposal. Many years later, a treatment facility was
identified that might be capable of accepting the waste and producing a waste form that
would meet a disposal facility’s waste acceptance requirements. The complete original
characterization information for the waste has been lost so an evaluation of the ability to
meet the waste acceptance requirements of the treatment facility could not be performed
without re-characterizing the waste.
This requirement is applicable to all low-level waste in storage. Low-level waste with no
identified path to disposal may be stored for extended periods of time pending the development of
a disposal option. The characterization and waste container information must be maintained and
retrievable regardless of the storage period.
The waste characterization and container information on waste in storage needs to be managed as
a Federal record. The guidance on Waste Transfer (DOE M 435.1-1, Section IV.K) discusses the
essential information elements relative to waste containers. Upon disposal of the waste the
records are to be maintained as permanent records. DOE information management experts should
be consulted for execution of this requirement.
Section 554
Example: A low-level waste storage facility uses information management specialists to
maintain a compliant records management system. In addition, training is provided that
defines and addresses the procedures concerning the creation, collection, use,
documentation, dissemination and disposition of records concerning the low-level waste.
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-173
7-09-99
Compliance with this requirement is demonstrated by documented procedures for managing waste
characterization and container information on low-level waste as a Federal record. The records
are managed per the applicable polices and procedures for records management referenced in
DOE O 200.1 and established at the applicable Field Element.
Supplemental References:
1. DOE, 1996. Information Management Program, DOE O 200.1, U.S. Department of
Energy, Washington D.C., September 30, 1996.
IV. N.(5) Container Inspection. A process shall be developed and implemented
for inspecting and maintaining containers of low-level waste to ensure
container integrity is not compromised.
Objective:
The objective of this requirement is to prevent or minimize the potential exposure of workers and
release of radioactive contamination to the environment that could result from allowing low-level
waste containers to degrade. The requirement is intended to ensure that the containment function
of the waste containers is routinely evaluated and action taken to ensure the waste remains
contained.
Discussion:
The containment of low-level waste in containers is essential for its safe and effective
management. During the development of the Radioactive Waste Management Manual
(DOE M 435.1), inadequate or substandard waste containers and deterioration of containers of
waste were identified as conditions that could result in the loss of waste containment and
potentially impact workers, the public, or the environment. The General Requirements of the
Radioactive Waste Management Manual (DOE M 435.1-1) assign the Field Element Manager
responsibility to ensure all waste is stored in a manner that protects the integrity of the waste for
the expected time of storage (Section I.2.F.(13). The responsibility for providing adequate
storage that protects the integrity of waste containers is complemented by this requirement to
routinely inspect the containers and correct any conditions of deterioration. This is particularly
important for low-level waste that is to be in relatively long-term storage (e.g., waste for which a
disposal facility is not identified). This requirement applies to all storage of low-level waste, not
just storage performed at a designated storage facility.
Example: An incineration facility stages waste awaiting treatment. The treatment
facility has established operational procedures for the frequent physical examination of
Chapter IV - Low-Level Waste Requirements
IV-174 DOE G 435.1-1
7-09-99
all waste containers. If containment of the waste is jeopardized their procedures are
available for repackaging the waste, or repair of the waste containers.
Inspection. The inspection and corrective action process is intended to ensure that container
integrity is maintained throughout the storage or staging period. The process needs to be tailored
to the storage situation. Ideally, the storage configuration would allow visual or remote
inspections of the outsides of waste containers. The inspection needs to look for:
Section 555
• general condition of the waste container, such as areas of rust, scratches, and
minor dents. The inspection process includes an evaluation of minor surface
conditions as to their impact on the integrity of the container. Such conditions
may not require action, but should be noted and corrected if there is a trend
indicating eventual deterioration;
• functioning of the waste container closures, in place, and securely fastened;
• evidence of leakage, which may indicate unacceptable materials in the waste,
inadequate internal packaging materials, (insufficient absorbent), or failure of the
container;
• evidence of structural problems with the waste container such as buckling or split
seams;
• bulging of the waste container indicating build up of pressure in the container,
which may indicate inappropriate storage conditions (e.g., storing tightly sealed
waste containers where they are subject to excessive heating), a condition inside
the container that needs to be remediated, and the need to replace the container;
and
• examination of waste container marking and labeling to ensure that they are
maintained in a legible condition.
Example: Low-level waste is stored in rows two drums wide and two drums high with an
aisle between the rows. The site procedure call for an operator to inspect the condition
of the drums every two weeks and record any potentially adverse conditions.
Some older storage configurations (e.g., dense pack storage where there are multiple rows and
layers of waste containers without access space between them) may not allow direct visual
inspection. In such cases, the “inspection” may need to be done using remote or indirect
techniques. Remote techniques include the use of video cameras which provide real time or
recorded displays of waste containers which are not accessible for direct inspection. Indirect
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-175
7-09-99
methods include the use of radiation detectors to determine when a waste container has failed. To
the extent possible, direct remote visual inspections are to be used in preference to indirect
methods since indirect methods force the inspection and maintenance process into a reactive mode
of fixing problems once they have occurred (as detected by an increase in radioactive
contamination) rather than a proactive mode of preventing breaching of the waste containers.
Example: Drums stored in a dense pack array are in a building that has a continuous air
monitor. To ensure adverse waste container conditions are detected as soon as practical,
additional monitoring is performed on a routine basis. The additional monitoring
involves the use of radiation detectors on extension probes to reach inside the array and
a similar use of swabs to check for loose contamination within the array.
Waste containers are to be physically examined on a routine basis to ensure that storage
conditions have not caused the integrity of the container to be compromised. Waste containers
that exhibit serious deterioration and a potential for containment of the waste to be jeopardized
may need to be replaced.
Example: During the routine inspection of waste drums conducted every 30 days at a
staging area a drum was identified as possibly damaged. Upon detailed examination, it
was determined that a forklift had punctured the waste drum. The waste was repackaged
and the old drum removed from service.
Section 556
Maintenance. The process for waste container maintenance should include capabilities for
preventive actions as well as for corrective actions. Preventive actions would address minor
conditions associated with ensuring waste containment. Actions might include cleaning and
painting small areas on metal containers to curb corrosion that could eventually lead to
compromising the container. The maintenance process also provides capabilities to respond to
more serious conditions up to and including breaching of the container (e.g., from accidental
puncture or corrosion).
Maintenance of a container(s) in response to acute conditions (i.e., conditions where there is a
release or imminent threat of a release) needs to provide for prompt containment of the release,
assessment of the situation, and remedying the situation. The immediate response is to ensure
that release of contamination is controlled. Actions may be as simple as replacing a bolt and or
closure ring on a drum, or covering a hole in a container with tape. More serious conditions may
require placing the waste container in a catch tray or in an overpack. An assessment of the
condition causing the breach or potential breach needs to be part of the process so that, if
necessary, the causative factors can be corrected. If corrosion is affecting the waste container, the
reason for the corrosion needs to be determined so an effective response can be made. If there is
a corrosive material in the waste container, overpacking may only temporarily correct the
problem. In such situations, it may be more appropriate to treat the waste or to provide a liner
Chapter IV - Low-Level Waste Requirements
IV-176 DOE G 435.1-1
7-09-99
that is resistant to corrosion. If there is buckling of the waste container or split seams, an
assessment needs to be made of whether the contents are too heavy, whether the container is
improperly designed, or whether the container was mishandled (e.g., dropped). In cases where an
external event is the cause of the damage (e.g., a waste container is dropped or struck by
equipment), repackaging or overpacking in a similar container may be appropriate.
Example: The inspection process in a storage facility identified a waste drum that was
corroding even though the container was stored in acceptable conditions and the paint
on the drum was in good shape. Storage facility personnel recognized that there was a
need to investigate whether the contents of the container caused the corrosion.
Evaluation of the container contents confirmed that the waste included a corrosive
material. The waste was treated to neutralize the corrosion then repackaged in a similar
container.
The term maintenance does not imply that refurbishment of deteriorating waste containers is
required. The premise of this requirement is that potential doses to workers is avoided.
Therefore, overpacking may be the most appropriate action as opposed to a repackaging action
requiring excessive handling of the waste and possible exposure.
Compliance with this requirements is demonstrated by: (1) a documented process for waste
container inspection and maintenance; and (2) documentation for all waste container inspections
and maintenance actions performed.
IV. N.(6) Storage Management. Low-level waste storage shall be managed to
identify and segregate low-level waste from mixed low-level waste.
Objective:
The objective of this requirement is to prevent the commingling of low-level waste with mixed
low-level waste.
Section 557
Discussion:
The management of mixed low-level waste represents challenges not typically encountered with
the management of low-level waste. The additional requirements imposed for the management of
the hazardous constituent can represent additional management effort over that which is required
for the radiological constituent. By identifying and segregating the two waste types, the amount
of mixed low-level waste generated will be minimized and the effort and resources required to
achieve final disposition of the waste will be minimized. Historical problems and current storage
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-177
7-09-99
conditions exist which indicate that a formal requirement to prevent the commingling of waste
types is warranted.
Example: During the decontamination and decommissioning of an old laboratory a
small quantity of mixed low-level waste is placed in a large wooden box with low-level
waste. Segregation of the waste types is not done because it is believed that the waste
will have to be repackaged for treatment in the near future. While in storage, the small
amount of mixed low-level waste commingles with the rest of the waste in the wooden
box. The entire contents of the wooden box must now be managed as mixed low-level
waste.
The management polices and procedures for the storage of all low-level waste need to address the
identification of mixed low-level waste. Identification of mixed low-level waste needs to occur
prior to the waste being placed in storage. The requirements that personnel must follow in
managing (i.e., generating, transporting, treating, storing, or disposing) mixed low-level waste are
primarily in 40 CFR Parts 260 through 270, or similar state regulations (see Section IV.B of this
guidance).
The management polices and procedures for the storage of all low-level waste need to address the
segregation necessary to avoid commingling the waste types. The segregation should be a
combination of physical and procedural requirements.
Example: Low-level waste and mixed low-level waste is stored in the same building.
Procedures have been established to prevent the waste types from coming in contact with
each other. In addition, physical markers such as lines on the floor and rope barriers
are in place to prevent inadvertent contact between the waste types. The entire system is
based on the proper marking and labeling of the waste containers.
Compliance with this requirement is demonstrated by: (1) a documented process for identifying
mixed low-level waste in storage; and (2) documented operating procedures that prevent the
storage of low-level waste in the same immediate area as mixed low-level waste.
Supplemental References:
1. DOE, 1996. Complex-Wide Review of DOE’s Low-Level Waste Management ES&H
Vulnerabilities, DOE/EM-0280, U.S. Department of Energy, Washington, D.C., May
1996.
2. EPA. Standards for Owners and Operators of Hazardous Waste Treatment Storage and
Disposal Facilities, 40 CFR Part 264, U.S. Environmental Protection Agency,
Washington, D.C.
Chapter IV - Low-Level Waste Requirements
IV-178 DOE G 435.1-1
7-09-99
IV. N.(7) Staging. Staging of low-level waste shall be for the purpose of the
accumulation of such quantities of waste as necessary to facilitate
transportation, treatment, and disposal. Staging longer than 90 days
shall meet the requirements for storage above and in Chapter I of this
Manual.
Objective:
Section 558
The objective of this requirement is to allow for the safe temporary accumulation of low-level
waste to facilitate its management without the accumulation being considered storage and thus
bound by the associated requirements for storage.
Discussion:
The storage of low-level waste is an important function required for the effective management of
low-level waste. The storage of low-level waste is defined as the collection and management of
waste for the purpose of awaiting treatment or disposal capacity, in such a manner as to not
constitute disposal of the waste. During the development of the requirements in DOE M 435.1-1,
it was recognized that storage of waste for short periods does not require the same controls that
storage of low-level waste for longer periods would require. A distinction between storage for
less than 90 days and storage for periods greater than 90 days was made when the less-than-90
day storage is for the temporary accumulation of low-level waste to facilitate transportation,
treatment, or disposal. This temporary action is referred to as staging, and is usually associated
with a subsequent management step such as treatment or disposal. The term staging helps
provide a distinction from “storage” in order to know when to apply the needed extra controls
that are necessary when the waste is stored.
The 90-day period was chosen as a result of the requirements analysis conducted in developing
the Manual to be consistent with best management practices as reflected in the management of
hazardous waste in accordance with RCRA requirements. Since this time frame is already being
adhered to for mixed low-level waste, extending this to all low-level waste is prudent and should
not be overly burdensome to facility operations.
The staging of low-level waste should be considered an action that is primarily for the benefit of
achieving the next management step for the waste safely and cost-effectively. For example,
staging could include the accumulation of low-level waste by:
- a generator prior to shipment to a receiving facility;
- a treatment facility prior to treatment;
- a treatment facility following treatment; or
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-179
7-09-99
- a disposal facility prior to emplacement of the waste.
The staging of low-level waste needs to be addressed in the radioactive waste management basis
for the facility that is performing the staging. Generators, treatment facilities, and disposal
facilities that stage waste must ensure that the action of staging is included and authorized as part
of their radioactive waste management basis for the affected facilities, operations, or activities.
Determination of the 90-day time limit shall be based on the date the waste is generated or treated
and the date the waste was received at a treatment or disposal facility. The information regarding
the dates for determination of staging periods needs to be documented consistent with the
requirement for transfer of the waste, DOE M 435.1-1, Section IV.K.
Section 559
As the one-year limit for storage, the intent of this requirement is not that a focus be placed on the
compliance or non-compliance with the 90-day limit. The requirement is not intended to force
shipment of low-level waste when the 90-day period is reached, or to cause additional handling of
low-level waste that would result in increased risk or safety concerns. Rather, the intent of this
requirement is to focus attention of managers at the site towards ensuring that waste is being
managed to disposal under reasonable time frames. The requirement calls for accumulation of
waste longer than 90 days to be subject to the storage requirements in Chapter I and IV of the
Radioactive Waste Management Manual (DOE M 435.1-1). Staging longer than 90 days must
be justified, the conditions for such storage met, and these practices approved by the Field
Element Manager as part of the radioactive waste management basis for the facility.
There needs to be flexibility in the implementation of this requirement due to the complexities of
management of low-level waste and the unpredictability of events as they affect planned
operations. Thus, malicious compliance with the 90-day limit is not necessary, nor is it intended
that no additional “staging” time can be allowed past the 90 days.
Example 1: Drums accumulating in an area awaiting shipment to a disposal facility for
less than 90 days is identified as staging and is included in the radioactive waste
management basis of the facility holding the waste.
Example 2: The drums described above are held for a period of 125 days. The Field
Element Manager has evaluated the conditions at the facility and approves this period of
time for staging in the radioactive waste management basis of the facility because the
requirements for storage are being met.
Example 3: Some of the drums described above do not get loaded in the shipment that
takes place at the end of the 125 days. This is a non-compliance. The radioactive waste
management basis needs to include the rationale for storage of drums not picked up in
Chapter IV - Low-Level Waste Requirements
IV-180 DOE G 435.1-1
7-09-99
the accumulated amount and the conditions for their storage. One of the conditions is
that the one-year storage limitation clock has already had 125 days expire.
Example 4: Low-level waste is accumulated at a treatment facility prior to repackaging
and treatment. Typically, the total time waste is held before and after treatment is less
than 90 days. However, certain treatment campaigns require the staging of waste at the
facility for a longer period of time. The treatment facility has an approved radioactive
waste management basis that includes contingency storage for these circumstances and
includes meeting the applicable requirements for storage.
Compliance with this requirement is demonstrated by a staging program that limits the temporary
storage of waste to only circumstances allowed in the requirement, including justifications for any
staging that exceeds the 90-day period, which is documented in the radioactive waste
management basis for the facility.
Supplemental References: None.
Chapter IV - Low-Level Waste Requirements
DOE G 435.1-1 IV-181
7-09-99
IV. O. Treatment.
Low-level waste treatment to provide more stable waste forms and to improve the
long-term performance of a low-level waste disposal facility shall be implemented as
necessary to meet the performance objectives of the disposal facility.
Objective:
Section 560
The objective of this requirement is to ensure low-level waste is treated to meet disposal facility
waste acceptance criteria, to achieve greater stability of the disposal site, and for a greater level of
assurance that the disposal performance objectives are met.
Discussion:
During the development of DOE O 435.1 and DOE M 435.1-1, treatment of waste was identified
as an activity that presented potential risks to the public, workers, and the environment. The
hazards and requirements analyses identified certain characteristics of radioactive waste that
would be unacceptable for long-term storage, leading to the need for treatment of such waste
prior to its acceptance for storage. Several existing external regulations (e.g., Clean Air Act or
RCRA) or other requirements (e.g., 10 CFR Part 835, Occupational Radiation Protection or
DOE O 360.1, Training) were found to already address requirements pertaining to weaknesses
and conditions that could potentially lead to adverse impacts. Consequently, the Radioactive
Waste Management Manual DOE M 435.1-1, Section I.2.F.(14) assigns the Field Element
Manager an umbrella, performance-oriented responsibility for ensuring that waste treatment is
protective of the public, workers, and the environment. Treatment can also affect low-level waste
disposal technologies and requirements. This requirement focuses attention on the treatment of
low-level waste necessary to make waste acceptable for disposal.
The low-level waste treatment actions necessary to make waste acceptable for storage and
disposal can be driven by dictated external requirements or requirements established by waste
acceptance criteria. Waste acceptance requirements for a storage or disposal facility, established
based on safe handling of the waste and on regulatory compliance, include minimum waste form
characteristics and requirements for stability and other characteristics to enhance their
performance. Treatment may range from actions as simple as sorting waste to remove materials
which would make the waste unacceptable (e.g., aerosol cans) to solidification or vitrification.
Low-level waste may also be treated for programmatic needs. Programmatic needs include
treatment to reduce the use of disposal capacity or to provide an additional protective barrier
during transportation or storage of a controversial waste prior to its disposal.
Chapter IV - Low-Level Waste Requirements
IV-182 DOE G 435.1-1
7-09-99
Improved Waste Forms and Characteristics. The requirements for treatment of low-level waste
are driven by the need for an improved waste from that provides additional protection while it is
in storage or following its disposal. Minimum characteristics of waste that must be specified in
disposal facility waste acceptance requirements are at DOE M 435.1-1, Sections IV.G.(1) (a)
through (c). Characteristics of waste that are prohibited for waste going into storage are at DOE
M 435.1-1, Section IV.N.(1). In order to meet the waste acceptance requirements derived and
specified for these performance oriented requirements at storage and disposal facilities, some
physical or chemical stabilization may need to be performed. Some minimum waste form
requirements specific to low-level waste disposal facilities are at DOE M 435.1-1, Section
IV.G.(1)(d). The disposal facility waste acceptance requirements provide for improved waste
characteristics and waste forms, and low-level waste that cannot meet these minimum waste form
requirements must be treated to meet the requirement prior to disposal. Liquid, pyrophoric,
gaseous, infectious, toxic, and explosive wastes, must be treated prior to disposal to meet the
minimum waste form requirements of a disposal facility. Guidance for the waste acceptance
requirements provides discussions that can assist in the development of processes that will result
in waste forms and packaged waste with the desired characteristics.
Section 561
Example 1: Low-level waste consisting of contaminated metal turnings and fines is
produced from a process at the Site G Fuel Fabrication Plant. An analysis indicates this
waste is pyrophoric. A process is implemented at the Fuel Fab Plant to oxidize the
turning and fines and add grout to packages to stabilize the material prior to shipment
for disposal.
Example 2: Low-level waste containing small amounts of volatile materials must be
stored in Building 500 at the Brown Site. Building 500 is susceptible to high
temperatures in the summer months, and it is unknown how long the waste must remain
in storage. The waste is treated with a neutralizing agent and a solidification media
prior to acceptance at the storage facility.
Besides the prohibited storage characteristics specified in DOE M 435.1-1, Section IV.N.(1) and
the minimum disposal waste form criteria that are specified in DOE M 435.1-1, Section
IV.G.(1)(d), additional technical criteria for physical and chemical stability, waste compressibility,
acceptable waste forms, liquid content, and other parameters may be specified by a specific
facility’s waste acceptance requirements. These criteria are based on safety considerations
derived from the waste management facility safety documentation, or performance considerations
derived from the performance assessment and composite analysis for a low-level waste disposal
facility. The treatment processes and facilities must be developed and designed so that the desired
waste form and characteristics are achieved with the tr