DOE G 430.1-3, Deactivation Implementation Guide
Functional areas: Environmental Management
As DOE facilities complete mission operations and are declared excess, they pass into a transition phase which ultimately prepares them for disposition. The disposition phase of a facility's life cycle usually includes deactivation, decommissioning, and surveillance and maintenance (S&M) activities.
Related To:
Version history and related documents
Related documents
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
NOT MEASUREMENT
SENSITIVE
DOE G 430.1-3
Approved: 9-29-99
DEACTIVATION
IMPLEMENTATION GUIDE
U.S. Department of Energy
Washington, D.C. 20585
Office of Field Integration
DISTRIBUTION: INITIATED BY:
All Departmental Elements Office of Field Integration
i DOE G 430.1-3
9-29-99
FOREWORD
The Department of Energy (DOE) faces an enormous task in the disposition of the nation’s excess
facilities. Many of these facilities are large and complex and contain potentially hazardous
substances. As DOE facilities complete mission operations and are declared excess, they pass
into a transition phase which ultimately prepares them for disposition. The disposition phase of a
facility’s life cycle usually includes deactivation, decommissioning, and surveillance and
maintenance (S&M) activities.
DOE has developed four Guides to provide implementation guidance for requirements found in
DOE O 430.1A, LIFE-CYCLE ASSET MANAGEMENT, specific to the transition and disposition
of contaminated, excess facilities. The Guides are DOE G 430.1-2, IMPLEMENTATION GUIDE
FOR SURVEILLANCE AND MAINTENANCE DURING FACILITY TRANSITION AND
DISPOSITION; DOE G 430.1-3, DEACTIVATION IMPLEMENTATION GUIDE; DOE G
430.1-4, DECOMMISSIONING IMPLEMENTATION GUIDE; and DOE G 430.1-5,
TRANSITION IMPLEMENTATION GUIDE. The goal of the processes described in the Guides
is a continuum of hazard mitigation and risk reduction throughout the transition and disposition
phases, leading to timely, cost-effective disposition of the facility.
Transition activities occur between the operations and disposition phases in a facility’s life cycle.
Transition begins once a facility has been declared or forecast to be excess to current and future
DOE needs. It includes placing the facility in stable and known conditions, identifying hazards,
eliminating or mitigating hazards, and transferring programmatic and financial responsibilities
from the operating program to the disposition program. Timely completion of transition activities
can take advantage of facility operational capabilities before they are lost, allowing DOE to
eliminate or mitigate hazards in a more efficient, cost-effective manner. In preparation for the
disposition phase, it is important that material, systems, and infrastructure stabilization activities
be initiated prior to the end of facility operations.
Following operational shutdown and transition, the first disposition activity is usually to
deactivate the facility. The purpose of the deactivation mission is to place a facility in a safe
shutdown condition that is economical to monitor and maintain for an extended period, until the
eventual decommissioning of the facility. Deactivation of contaminated, excess facilities should
occur as soon as reasonable and for as many facilities as possible. In this way, DOE can apply its
resources in a manner that accomplishes the greatest net gains to safety and stability in the shortest
time. Deactivation places the facility in a low-risk state with minimum S&M requirements.
The final facility disposition activity is typically decommissioning, during which the facility is
taken to its ultimate end state through decontamination and/or dismantlement. After
decommissioning is complete, the facility or surrounding area may require DOE control for
protection of the public and the environment or for environmental remediation.
Section 2
S&M activities are conducted throughout the facility life cycle, including when a facility is not
operating and is not expected to operate again. During these last periods of a facility life cycle, it
is important to ensure that S&M is adequate to maintain the facility safety envelope during the final
ii DOE G 430.1-3
9-29-99
stages of operations through a seamless transition to the final disposition of the facility. S&M is
adjusted during the facility life cycle as transition, deactivation, and decommissioning activities
are completed. S&M activities include periodic inspections and maintenance of structures,
systems, and equipment to ensure that, at a minimum, any contamination is adequately contained
and that the potential hazards to workers, the public, and the environment are eliminated or
mitigated and controlled.
The technical, managerial, and planning perspectives offered in these Guides can be equally
effective in conducting activities other than transition and disposition, such as refurbishment and
“cleanup” for reuse. As such, this guidance can be adapted for use at facilities that are not being
declared excess.
An important objective throughout transition and disposition is to maintain an integrated and
seamless process linking deactivation, decommissioning, and S&M with the previous life-cycle
phases. Activities of facility transition and disposition must incorporate integrated safety
management at all levels to provide cost-effective protection of workers, the public, and the
environment.
DOE G 430.1-3 iii (and iv)
9-29-99
CONTENTS
1. INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1.1 Purpose . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1.2 Alternative Methods . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1.3 Applicability . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1.4 Crosswalk of DOE O 430.1A Requirements to DOE G 430.1-3 . . . . . . . . . . . . . . 2
2. THE DISPOSITION PROCESS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
3. DEACTIVATION PHASE—GENERAL GUIDANCE . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
3.1 Project Management Principles—Systems Engineering . . . . . . . . . . . . . . . . . . . . . 8
3.2 Integrated Safety Management . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
3.3 Graded Approach . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
4. THE DEACTIVATION PHASE—PROCESS GUIDANCE . . . . . . . . . . . . . . . . . . . . . . . 13
4.1 Early Decisions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
4.1.1 Step 1: Policy and Operational Decisions . . . . . . . . . . . . . . . . . . . . . . . . 13
4.1.2 Step 2: Facility End-State Decision . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
4.2 Deactivation Project Planning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
4.2.1 Step 3: Determine Project Scope . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20
4.2.2 Step 4: Integrate Safety into the Project . . . . . . . . . . . . . . . . . . . . . . . . . . 20
Section 3
4.2.3 Step 5: Develop Detailed End Points . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
4.2.4 Step 6: Identify and Evaluate Alternatives . . . . . . . . . . . . . . . . . . . . . . . . 25
4.2.5 Step 7: Prepare Baselines . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
4.2.6 Step 8: Issue Project Plan Document . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28
4.2.7 Step 9: Detailed Work Packages . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28
4.3 Step 10: Project Execution . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29
4.3.1 Step 11: Feedback . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29
4.4 Project Closeout . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30
4.4.1 Step 12: End-Point Closeout . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30
4.4.2 Step 13: Final Report . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31
4.4.3 Step 14: Deactivation to Decommissioning . . . . . . . . . . . . . . . . . . . . . . . 32
1 DOE G 430.1-3
9-29-99
1. INTRODUCTION
1.1 PURPOSE
This Guide was prepared to aid in the development, planning, and implementation of deactivation
requirements and activities at Department of Energy (DOE) facilities that have been declared
excess to any future mission requirements. It is one of four Guides developed to provide guidance
for facility transition and disposition activities. The other three Guides are—
• DOE G 430.1-2, IMPLEMENTATION GUIDE FOR SURVEILLANCE AND
MAINTENANCE DURING FACILITY TRANSITION AND DISPOSITION;
• DOE G 430.1-4, DECOMMISSIONING IMPLEMENTATION GUIDE; and
• DOE G 430.1-5, TRANSITION IMPLEMENTATION GUIDE.
Requirements for deactivation are stated in DOE O 430.1A, LIFE-CYCLE ASSET
MANAGEMENT (LCAM), which identifies the minimum requirements for disposition of an
excess DOE facility. This Guide defines activities or actions that continue the process of risk
reduction after seamless transition from operations to the selected disposition path. It is part of the
DOE Directives System and is consistent with the principles and core functions of DOE P 450.4,
SAFETY MANAGEMENT SYSTEM POLICY. Other documents that should be consulted to
support the planning and conduct of disposition activities include DOE-STD-1120-98, Integration
of Environment, Safety and Health into Facility Disposition Activities, and the Good Practice
Guides associated with LCAM.
1.2 ALTERNATIVE METHODS
This Guide presents acceptable methods for implementing the deactivation requirements specified
in LCAM to ensure effective and efficient management of DOE excess facilities. It does not
impose additional requirements. The Department has invested substantial time and effort in
developing a deactivation framework that (1) meets DOE’s requirements and expectations, (2)
draws on DOE’s previous experience, and (3) is responsive to oversight entities. Although
alternative methods and approaches to the ones discussed in this Guide may be used, a comparable
amount of time and effort may be needed to evaluate the acceptability of those alternatives.
1.3 APPLICABILITY
Section 4
This Guide may be applied to deactivation activities and processes at contaminated DOE
facilities. “Contaminated” refers to both radioactive contamination and to hazardous-substance
contamination. Both nuclear facilities and nonnuclear contaminated facilities are included in the
scope of this Guide. Project personnel are expected to apply a graded (i.e., tailored) approach in
planning and conducting deactivation activities at different types of facilities and with different
hazard conditions.
2 DOE G 430.1-3
9-29-99
1.4 CROSSWALK OF DOE O 430.1A REQUIREMENTS TO DOE G 430.1-3
The LCAM requirements that apply to deactivation activities are included in Table 1, cross-
referenced to the sections of this Guide where they are addressed. Though the table quotes the
requirements as they appear in LCAM, this Guide addresses only those requirements that apply to
deactivation activities. Parallel tables in the other three LCAM Guides provide crosswalks
between requirements and guidance for surveillance and maintenance (S&M), decommissioning,
and transition.
Table 1. Mapping of Requirements—Deactivation.
Requirement Where Addressed in Guide
DOE O 430.1A, paragraph 6a: DOE elements shall use a
value-added, quality-driven, graded approach to life-
cycle asset management.
Section 3.3, Graded Approach
DOE O 430.1A, paragraph 6g(1): Application, as Section 3, Deactivation Phase
appropriate, of guidelines contained or referenced in —General Guidance; Section
DOE-STD-1120-98, Integration of Environment, Safety 4.2.2, Step 4: Integrate Safety into
and Health into Facility Disposition Activities. the Project
DOE O 430.1A, paragraph 6g(6)(a): A method to ensure
that deactivation, S&M, and decommissioning activities
are appropriately planned, conducted, and documented in
a manner consistent with the guiding principles and core
functions of the Department’s integrated safety
management and facility disposition policies.
Section 3.2, Integrated Safety
Management; Section 4.2,
Deactivation Project Planning; and
Section 4.2.2, Step 4: Integrate
Safety into the Project
DOE O 430.1A, paragraph 6g(6)(a)(i): The collection of
baseline data to support a physical, chemical, and
radiological characterization, updated as necessary to
reflect changes in facility conditions during the
disposition process.
Section 4, Deactivation Phase
—General Guidance, and Section
4.4.2, Step 13: Final Report
DOE O 430.1A, paragraph 6g(6)(a)(iii): A method for
identifying, assessing, and evaluating alternatives for
deactivating and/or decommissioning and for selecting
and documenting a preferred alternative.
Section 4.2.4, Step 6: Identify and
Evaluate Alternatives
DOE G 430.1-3 3 (and 4)
9-29-99
Table 1. Mapping of Requirements—Deactivation (continued).
Requirement Where Addressed in Guide
DOE O 430.1A, paragraph 6g(6)(a)(iv): An end-point
process in deactivation and decommissioning planning
that identifies specific facility end points and activities
needed to achieve those end points.
Section 3.1, Project Management
Principles— Systems Engineering;
Section 4.2, Deactivation Project
Planning; Section 4.2.3, Step 5:
Develop Detailed End Points
DOE O 430.1A, paragraph 6g(6)(a)(v): A method for
detailed engineering planning and for plan documentation
to execute the preferred deactivation and/or
decommissioning alternative.
Section 3.1, Project Management
Principles—Systems Engineering
Section 5
DOE O 430.1A, paragraph 6.g.(6).(c): The development Section 4.4.2, Step 13: Final
of a final report, or equivalent document, for each Report
deactivation and/or decommissioning project. Where
deactivation and decommissioning are conducted as a
single, uninterrupted activity, only one final report, or
equivalent, is required.
DOE O 430.1A, paragraph 6i: DOE corporate physical
assets databases shall be maintained as complete, current
inventories of the DOE physical assets. For real
property, the corporate database is Facilities Information
Management System (FIMS).
Section 4.4, Project Closeout
DOE O 430.1A, paragraph 6j: In the acquisition, Chapter 3, Deactivation General
operation, maintenance, leasing, and disposition of Guidance
physical assets, DOE elements shall ensure that all
applicable Federal, State, and local laws, regulations, and
negotiated agreements are followed and that safeguards
and security as well as integrated safety management
requirements and policies are followed.
5 DOE G 430.1-3
9-29-99
2. THE DISPOSITION PROCESS
The disposition phase of a facility’s life cycle occurs after transition activities have been
completed and the programmatic and financial responsibilities have been transferred from the
operating program to the disposition program. After the transition activities have been completed,
it is expected that hazards have been identified and either eliminated or mitigated and the facility
and its contents are in stable and known conditions, thus reducing risk associated with the facility.
Guidance for these transition activities is given in DOE G 430.1-5.
The LCAM Order requires a Pre-Transfer Review report for contaminated, excess facilities that
are transferred from the operating program to the disposition program. The operating program
completes the report prior to transfer, documenting the condition of the facility at the time of
transfer. The report is intended to verify the actions taken to arrive at the stable and known
condition of the facility, its systems, and contents. The Pre-Transfer Review report not only
documents the existing condition of the facility but provides the receiving organization with a clear
understanding of stabilization and other transition activities completed and the results that were
obtained.
DOE has developed a process to address the various elements of disposition. This process
includes the transition from operations to deactivation and decommissioning as well as the
continuing S&M required throughout the disposition phase. It also includes S&M that may be
conducted as a stand-alone activity after deactivation activities have been completed and prior to
commencing decommissioning.
The flowchart in Figure 1 depicts the elements of the disposition process. It identifies the steps
necessary to eliminate or mitigate any remaining hazards and to safely complete the disposition of
a contaminated excess facility. The flowchart shows the system boundaries that distinguish the
deactivation activities from those required both prior to and after deactivation of the facility. It
also includes activities that will be completed after the closeout of all deactivation activities to
prepare the facility for decommissioning or continued S&M status while awaiting eventual
decommissioning.
Section 6
Guidance for the deactivation activities is addressed in the remaining chapters of this guidance
document. S&M activities are referenced as appropriate to deactivation activities. As previously
stated, more specific guidance on S&M and decommissioning activities may be found in
DOE G 430.1-2 and DOE G 430.1-4. When special nuclear materials are involved in deactivation
activities, work will be performed in accordance with DOE O 470.1, SAFEGUARDS AND
SECURITY PROGRAM, which provides the requirements for handling these materials.
6 DOE G 430.1-3
TRANSITION
•Excess Declaration
Transfer Initiation
•Facility Conditions
•Early Actions
•Adjust Authorization
Basis
•End Points
•Project Planning and
Execution
•Pre-Transfer Review
•Facility Transfer
Deactivation
Boundary
EARLY DECISIONS
Step 1
•Policy and Operations
Step 2
•Facility End State
PROJECT PLAN
Step 3
•Project Scope
Step 4
•Integrate Safety
Step 5
•Detailed End Points
Step 6
•Identify and Evaluate
Alternatives
Step 7
•Prepare Baselines
Step 8
•Issue Project Document
Step 9
•Detailed Work Packages
Complete ?
No
Yes
EXECUTION
Step 10
•Project Execution
ANALYSIS AND
FEEDBACK
Step 11
•Feedback
DEACTIVATION
PROJECT CLOSEOUT
Step 12
•End Point Closeout
Step 13
•Final Report
Develop S&M
DEACTIVATION
TO
DECOMMISSIONING
Step 14
•Identify Receiving
Organization
•Transfer Review
•Signed Agreement
– MOA
– Project Closeout
Documentation
9-29-99
D
E
C
O
M
M
I
S
S
I
O
N
I
N
G
Deactivation
Boundary
Figure 1. Disposition Process
S&M
S&M
S&M
7 DOE G 430.1-3
9-29-99
3. DEACTIVATION PHASE—GENERAL GUIDANCE
Deactivation is the process of placing a contaminated, excess facility in a stable condition to
minimize existing risks and the concomitant life-cycle cost of an S&M program that is protective
of workers, the public, and the environment. Hazard elimination or mitigation must be continued
during the deactivation process because hazards associated with the facility or its systems and/or
contents remain even after transition activities have been completed. Deactivation end points
define the characteristics of the facility when deactivation is completed and are specified to guide
the scope of deactivation activities. In some instances, deactivation may not be necessary because
the hazards and associated risks will be at an acceptable level until the facility’s reuse or disposal
is established.
As deactivation proceeds, unneeded systems within the facility are terminated, the hazards are
reduced, and the S&M burden drops. This results in a stable, low-risk condition that is
economically and technically practical to maintain for extended periods. Activities during this
period include, for example, removal of equipment, rerouting or isolating systems, and draining
and/or de-energizing nonessential systems. Deactivation may also include removing any remaining
hazardous chemicals, spent fuel, and other radioactive materials/wastes; Resource Conservation
and Recovery Act (RCRA) closures; and related actions. The pre-transfer characterization
baseline data should be updated throughout facility deactivation. Updates of safety documentation
that identify the reduction in the facility hazards are valuable to post-deactivation S&M.
Section 7
S&M activities are adjusted and performed to monitor and document the presence, status, or
condition of structures, systems, components, and hazards associated with the facility as
deactivation activities are completed. Continuing S&M throughout deactivation ensures, at a
minimum, that any contamination is adequately contained and that potential hazards to the public,
the workers, and the environment are minimized. DOE G 430.1-2 provides further guidance on
S&M activities throughout facility deactivation.
Since DOE has committed to conducting all work efficiently and in a manner that ensures the
protection of workers, the public, and the environment, as well as to maintaining a safe shutdown
configuration, this Guide references, as appropriate, the various components of DOE P 450.4 and
DOE-STD-1120-98.
Nuclear material stabilization and facility deactivation activities performed during the
deactivation phase are supported by and based on a defensible authorization basis, established in
accordance with DOE-STD-1120-98, and commensurate with the hazards and impacts to workers,
the public, and the environment. This basis includes the definition of work to be performed, any
identified hazards related to the work, the associated analysis, and the administrative and/or
engineering controls identified to prevent and mitigate risks associated with the hazards.
Other actions may be required during deactivation activities that are addressed in other
requirement documents. It is not the intent of this Guide to offer guidance for these. The project
manager and others involved with the development and/or the execution of a DOE deactivation
project should be well versed in other Federal, State, and local laws and regulations, as required
8 DOE G 430.1-3
9-29-99
by LCAM, as well as requirements that address integrated safety management, conduct of
operations, conduct of maintenance, radiological protection, and other requirements that are
integral to the planning, development, and conduct of work.
A systems engineering approach is used throughout deactivation to ensure that essential elements
are integrated at all appropriate levels. These elements primarily include safety management, as
defined in DOE P 450.4 and the application of a tailored approach, as defined in DOE G 450.3-3,
TAILORING FOR INTEGRATED SAFETY MANAGEMENT APPLICATIONS.
3.1 PROJECT MANAGEMENT PRINCIPLES—SYSTEMS ENGINEERING
The LCAM Order requires that a method for detailed engineering planning and plan documentation
be used to execute the preferred deactivation alternative. DOE has defined deactivation end
points methodology as an acceptable method for meeting the requirements for detailed engineering
planning. Further guidance regarding deactivation management and end-point management is
provided in Chapters 2 and 3 of Facility Deactivation— Methods and Practices Handbook,
DOE/EM-0318, (Revision 1, dated 9/10/99). Although DOE/EM-0318 primarily discusses the
end-point methodology relative to deactivation, it is important to recognize that these acceptable
methods are directly applicable to and can be used as the systems engineering method for the
implementation of transition and stabilization activities.
Section 8
Deactivation end-points methodology is a formal project management approach that presents
proven systems engineering concepts and tools to be used in the planning and implementation of
deactivation projects. Specifying end points is the key to planning, implementing, measuring and
knowing when a deactivation project is complete. Specifying and meeting end points is a
systematic, engineering way of proceeding from an existing condition to a stated final set of
conditions in which a facility is safe and can be economically monitored and maintained until final
decommissioning. The end-point method is a way to translate a broad mission statement to
explicit goals that are readily understood by engineering and crafts personnel who implement the
work. More detailed discussion and implementation guidance on end-points methodology is
provided in Section 4.2.3.
Project management envelopes the entire deactivation process, including planning, design,
execution, and end-use activities. A clear understanding of these phases enables greater control of
Departmental resources in achieving the deactivation goals. Using a project management system,
described in the LCAM Good Practice Guides, assists in the successful completion of each phase
of a deactivation project, from facility assessment, through technical engineering, to the execution
of the project tasks. These project phases generally occur in sequence. However, a continuous
feedback system must be implemented to improve the quality of the tasks performed and to ensure
that the safety management mechanisms address the industrial and radiological hazards
experienced at each phase of work.
The purpose of deactivation project management is to establish management intentions and a set of
objectives that results in a largely passive facility that can be maintained and monitored at minimal
risk and cost. A deactivation project plan specifies the deactivation work to be done to achieve
9 DOE G 430.1-3
9-29-99
the project objectives by establishing the project’s requirements and describing how the project
will be accomplished. (See Section 4.2.)
The first step is to define the top-level deactivation objectives. These objectives, which apply to
all deactivation activities, are as follows.
• Protect workers, the public, and the environment by establishing a low-risk facility status.
• Facilitate low-cost surveillance and maintenance after the facility is deactivated.
• Facilitate ultimate decommissioning work.
• Comply with regulations and requirements, including administrative requirements.
• Fulfill commitments to stakeholders.
3.2 INTEGRATED SAFETY MANAGEMENT
The DOE policy covering incorporation of a safety management system into management and work
practices is identified in DOE P 450.4. The policy identifies six components in a safety
management system that facilitate the orderly development and implementation of safety
management throughout the deactivation of an excess facility. These components are as follow.
• The objective is to ensure that the overall management of safety functions and activities
becomes an integral part of mission accomplishment in protecting the worker, the public,
and the environment.
• The guiding principles are the fundamental policies that guide actions, from development
of safety directives to performance of work. These include the delineation of roles and
responsibilities, competence levels, balanced priorities, identification of safety standards
and requirements, hazard controls tailored to the work being performed, and operations
authorization.
Section 9
• The core functions are to define the work, analyze the hazards, develop and implement
hazard controls, perform the work within the controls, and provide feedback and
continuous improvement.
• Integrated safety management mechanisms define how functions are performed. These
mechanisms are based on DOE directives, policies, and procedures to identify and analyze
hazards; perform safety analyses; set safety standards; and document these mechanisms,
such as the Health and Safety Plan, Safety Analysis Reports, Chemical Hygiene Plans, and
Process Hazard Analyses.
• Responsibilities for integrated safety management, appropriate to the mechanisms used,
must be clearly defined to satisfy each safety management principle or function and to
ensure establishment of the associated approval authority.
• Implementation involves specific definition of work and planning, hazards identification
and analysis, definition and implementation of hazard controls, performance of work,
10 DOE G 430.1-3
9-29-99
development and implementation of operating procedures, and monitoring and assessment
of performance for improvement.
The major mechanism for integrating safety and health into deactivation efforts is the work
planning process during which existing safety documentation is reviewed and evaluated,
deactivation activities are identified and evaluated against existing controls, and modifications to
controls are identified as required by the new activities. The safety documentation of an older
facility, including worker safety and health aspects, often falls short of today’s standards and/or
requirements. Worker safety and health considerations, comparable to or exceeding the levels
demanded by the Occupational Safety and Health Act (OSHA), must be incorporated into revisions
of, or supplements to, such safety documentation. Existing safety documentation from the facility’s
operational phase is used as the basis for deactivation project safety documentation. Revisions,
comparisons, crosswalks, and other evaluation techniques can be used to determine which
deactivation actions may be covered in existing documentation and which actions require
supplemental coverage. Such evaluation efforts, especially if performed by those who know the
facility well, are more cost effective and time efficient than preparation of new safety
documentation.
Worker involvement in all levels of safety/hazards analyses required for the planning and
execution of deactivation tasks is key to making all elements of deactivation efficient and
satisfactory. This involvement also helps in providing management with a higher level of
assurance that workers will participate willingly and enthusiastically in the performance of those
activities required for facility deactivation.
3.3 GRADED APPROACH
LCAM requires the “graded approach” to the application of requirements to a particular project,
activity, or facility. The “tailoring approach” defined in DOE G 450.3-3 is an acceptable method
of complying with this requirement. DOE G 450.3-3 demonstrates that tailoring is integral to the
integrated safety management system. Tailoring is appropriate for all steps in facility deactivation.
Tailoring allows project managers to choose from among a variety of engineering and
administrative controls that provide adequate protection for workers, the public, and the
environment during the performance of work. Tailoring of higher-level contractual and project
agreements enables contractors to establish general standards for work. Individual tasks are
tailored so that each task has controls that fit the specific work and hazards associated with it and
that are consistent with higher-level performance expectations.
Section 10
Tailoring permits consideration of differences between facilities and provides a means to
determine the extent to which actions are appropriate for a particular facility (or portions thereof).
The depth of detail required and the magnitude of resources expended for a particular management
element is commensurate with the relative importance of that element to safety, environmental
compliance, safeguards, and security; the magnitude of any hazard identified; programmatic
importance; financial impact; and/or other facility-specific requirements. For projects for which
no logical delineation between deactivation and decommissioning exists, the requirements are
integrated to serve the overall project and completion objectives. In doing so, planning considers
DOE G 430.1-3 11 (and 12)
9-29-99
the possibility of future changes to priorities and identifies the conditions (end points) where a
project may be safely and efficiently slowed or accelerated, if it becomes necessary to do so.
Tailoring is cost effective because it does not demand a high level of analysis and/or planning for
simple jobs already covered in established procedures. Worker involvement, as stated earlier,
has also proven to be cost effective because these employees often have spent many years
performing tasks during operations, and they may have a good understanding of the safety and
performance requirements of the deactivation activities.
Tailoring the integrated safety management system offers a means to grade activities and processes
to different hazards associated with individual facilities. Tailoring is used to scale expectations
and acceptable performance to the needs of the site, activity, facility, or work to be performed.
When applied to the deactivation objectives listed in Section 3.1, tailoring promotes a work
management system that is safe, efficient, and cost effective.
13 DOE G 430.1-3
9-29-99
4. THE DEACTIVATION PHASE—PROCESS GUIDANCE
4.1 EARLY DECISIONS
Some hazards and associated risks remain after transition activities have been completed. As a
result, many strategic choices need to be made early in the deactivation phase. These early
decisions address policy and operational issues at the onset of the deactivation project and lead to
a well-defined end state for the project. These decisions also help facility managers define the
work scope that can be prudently undertaken before the formal deactivation plan is completed.
These early decisions are expected to remain valid throughout the subsequent planning and
execution steps. However, because changes in facility condition and regulatory requirements can
occur, these decisions may need to be reevaluated periodically, either formally or informally, as
deactivation work progresses. These early decisions are shown as Steps 1 and 2 in the
deactivation process and are discussed below.
4.1.1 Step 1: Policy and Operational Decisions
Policy and operational issues that apply to facility deactivation are identified as early as possible
to ensure the deactivation tasks can be planned and executed as effectively as possible. Examples
of policy and operational issues that need to be addressed are listed below:
• Policy issues
- Organizational responsibilities after completion of deactivation.
- Post-deactivation disposition path (e.g., extended S&M or immediate
decommissioning).
- Future uses of the facility.
- Safeguards and security requirements.
- Immediate demolition in place of deactivation.
Section 11
- Disposition path for remaining radiological and hazardous materials.
- Material interim storage needs.
- Goal for the appropriate reduction of hazards and modification of the safety basis,
consistent with existing and end-state conditions.
14 DOE G 430.1-3
9-29-99
• Operational issues
- Identification of personnel with operational expertise.
- Continued elimination or mitigation of hazards.
- Safeguards and security implementation plan.
- Quickest means of reducing S&M resource burdens during deactivation.
- National Environmental Policy Act (NEPA); RCRA; Comprehensive
Environmental Response, Compensation, and Liability Act; OSHA, etc.
requirements.
- Heating, ventilation, lighting, and other service requirements after deactivation.
- Projected structural integrity of the facility during post-deactivation S&M.
Decisions related to these issues that constrain, dictate, or otherwise affect detailed deactivation
planning must be made as soon as possible. Other issues deserving consideration in the early
decision process include—
• Establishment of the overall deactivation end state of the facility.
• Identification of any facility-specific commitments.
• Identification of deactivation tasks that are required regardless of the detailed end points.
• Evaluation of alternatives for deactivation actions (re-engineering).
When possible, early decisions should be initiated before the deactivation process formally
begins. Advance efforts for the major decisions often are needed, based on the characterization
findings in the Pre-Transfer Review report. To meet the top-level objectives, some deactivation
or stabilization (if required) tasks may begin before detailed facility end points are specified.
When deactivation is initiated before detailed end-point criteria have been established, an
assumed, realistic, overall facility deactivation end state should be identified so that prudent
planning can take place.
4.1.2 Step 2: Facility End-State Decision
The deactivation end state represents the agreed-upon facility condition that is to be achieved after
completion of the deactivation effort. This condition is the ultimate goal of deactivation and is
characterized by a safe facility configuration that can be maintained until decommissioning is
feasible. Safety and health considerations are a major concern and drive the end state and the end
point definitions.
An excess facility’s expected condition at the completion of deactivation should be stated as that
facility’s deactivation end state as early as possible in the deactivation phase. This provides a
basis for proceeding with planning for early tasks and completion activities. For example, the
15 DOE G 430.1-3
9-29-99
conditions to be established can vary considerably if a facility is to be decommissioned
immediately after deactivation, contrasted with being placed in a state in which S&M activities
may be required for an extended period prior to the eventual decommissioning. Therefore, the
deactivation end state includes decisions on whether the facility will be—
• used by the current responsible DOE office after deactivation,
• placed in an extended S&M period, or
• decommissioned and/or dismantled immediately after deactivation.
The deactivation end state also identifies which organization is intended to assume management
and financial responsibility upon completion of deactivation.
4.2 DEACTIVATION PROJECT PLANNING
Section 12
As discussed previously, a clear set of facility-specific objectives needs to be defined and agreed
upon early in the project to ensure a cost-effective, technically efficient deactivation process that
is grounded in, and bound by, a defensible safety and technical basis. This definition is required
to translate high-level deactivation goals into identifiable objectives to be achieved. By
proceeding from a common set of top-tier goals, a consistent and systematic approach can be
implemented at facilities undergoing deactivation.
The purposes of the deactivation project planning process are to communicate the objectives,
requirements, and constraints to the project organization and to document how the deactivation
project is to be carried out. The output from the planning process is documented in a deactivation
project plan. The deactivation project plan identifies specific activities that must be done to
achieve the end points and the overall deactivation end state. It also identifies methods for the
conduct of work. The intent of a project plan is to describe how the deactivation project will be
managed and to communicate summary-level scope, cost, and schedule information.
Deactivation will be appropriately planned, conducted, and documented in a manner consistent
with the guiding principles and core functions of DOE’s integrated safety management policies.
To ensure this, the project plan will be developed in accordance with the principles of integrated
safety management identified in DOE-STD-1120-98, Section 3.0, “Integrated Safety Management
System.” Appendix C of the referenced Standard, “ISMS Performance Expectations,” provides
information that may be helpful to verify that the project plan adequately addresses integrated
safety management considerations. Other guidance may be found in Section 3.2 of this Guide and
is discussed further in Section 4.2.2.
The project plan consists of two distinct but interrelated parts: (1) the project plan document and
(2) the supporting appendixes. The project plan document provides the strategies and methods for
managing the project. It includes an overview or summary of project scope, cost, and schedule.
The project plan document is updated as the detailed supporting documentation is developed. A
suggested project plan outline is as follows:
16 DOE G 430.1-3
9-29-99
1. Introduction. Describes the purpose and overview of the plan. It outlines, in summary
form, the strategy of the project plan versus details in the supporting appendixes that
follow.
2. Project Objectives. Describes the purpose of the deactivation project and explains its
driving objectives, which are covered in Section 3.1 of this Guide.
3. Project Scope. Describes the facilities (addressed in Section 4.2.1 of this Guide) that will
be deactivated and the major actions which comprise the project.
4. Project Organization. Describes the project organization and all functional relationships
and discusses the roles and responsibilities with respect to accomplishing the project
objectives.
5. Project Management and Control. Describes the systems and processes to be used to
manage and control all aspects of the project (e.g., cost, schedule, scope). This section of
the project plan document also includes a process for issue resolution and technical
decision making.
6. Project Baseline. Contains a roll-up summary of the work breakdown structure, schedule,
proposed milestones, and cost estimate. These subjects are addressed in more detail in
Section 4.2.5 of this Guide.
Section 13
7. End Points. Describes the process used to develop the end points. Section 4.2.3 of this
Guide addresses the development of end points for a deactivation project.
8. Quality Assurance. Describes the policies and procedures to be used to meet quality
assurance objectives.
9. Regulatory. Provides an overview of the deactivation project regulatory drivers and the
proposed approaches to ensuring compliance.
10. Safety and Health. Provides the safety basis and the strategy and methods to be used for
evaluating the hazards associated with the project activities. The strategy includes
integration of worker safety and health issues as well as protection of the public and
dislocated site workers. Incorporating safety into the deactivation project is addressed in
detail in Section 4.2.2 of this Guide as well as in DOE-STD-1120-98, Section 3.0,
“Integrated Safety Management System.”
11. Communications. Outlines a plan for public and stakeholder outreach and involvement and
provides the proposed communications objectives and methods. Section 4.2.4 of this
Guide discusses the need for open communications during the deactivation project.
12. Project Risk. Provides an outline of the method to be used in performing a project risk
assessment.
17 DOE G 430.1-3
9-29-99
The supporting appendixes to the deactivation project plan provide the detailed documentation for
application and implementation of the project strategies. The supporting appendixes also provide
the detailed cost and schedule data. These appendixes are used to provide guidance to project
staff for day-to-day management of the project and are developed, maintained, and approved by the
deactivation contractor. The following topics and their descriptions are suggested as supporting
appendixes to be included as part of the project plan.
• Work Management. Describes the work management system and procedures to be used in
the performance of project objectives.
• Current Fiscal Year Execution Plan. Establishes the scope, cost, and schedule for the
project integrating the deactivation activities defined by the end-point document. The
current fiscal year execution plan is a site-specific document and therefore may be
identified differently (e.g., multiyear program plan, annual operating plan, project plan).
Its intent is consistent across the DOE complex in specifying the project milestones and
deliverables and forming the project baseline in terms of cost and schedule. It serves as
the vehicle for obtaining DOE approval of the planned work scope.
• Schedules. Provides the top-level one or two project baseline schedules and the network
diagram. The project baseline schedule is included in the site’s current fiscal year
execution plan. Detailed working schedules (from which the baseline is developed) are
maintained and controlled by the project team.
• Work Breakdown Structure Dictionary and Basis of Estimate. Describes the key
assumptions and work scope for each deactivation activity included in the baseline
schedule.
• Cost Estimate Work Sheets. Provides a compendium of the work sheets used to estimate
resources and materials required to implement the schedule. The work sheets constitute the
project estimate and provide the basis for the current fiscal year execution plan.
• Schedule Preparation and Change Control. Describes the schedule preparation
methodology and best management practices. This appendix also identifies the procedures
for schedule maintenance, change control, and status reporting.
Section 14
• Configuration Control. Describes the configuration control practices to be used for the
project. It also identifies the compliance approach with the site configuration control
procedures and how waivers or exemptions will be approved and documented.
• Technical Baseline Development and Control. Describes the relationship of systems
engineering to preparation of the technical baseline. The best management approaches for
development of technical baseline documentation should be described here.
• Project Metrics. Identifies the performance measures to be used to communicate project
performance.
18 DOE G 430.1-3
9-29-99
• End-Point Document. Contains the facility-specific material stabilization and facility
deactivation end-point criteria and the agreed-upon end points. These end points define the
work that will be performed during the deactivation project, which is integrated and
presented in the current fiscal year execution plan.
• End-point Closure Methods and Practices. Provides the acceptable methods and
procedures for end-point closeout (addressed in Section 4.4.1 of this Guide) to ensure that
a consistent and defensible end-point closure is achieved.
• S&M Plan. Outlines the facility-specific S&M activities to be performed in conjunction
with the deactivation project activities to ensure the facility’s safety envelope is
maintained in a safe, efficient, compliant, and cost-effective manner. This plan includes
the key interfaces with project activities, the phase-out of pre-deactivation S&M, and the
phase-in of post-deactivation S&M as required. The post-deactivation S&M is used and
maintained until decommissioning activities begin.
• Health and Safety Documentation. Provides detailed implementation procedures for the
safety and health plan identified in the first part of the deactivation project plan.
• Project Risk Assessment. Provides an evaluation of the project baseline risks that does not
include safety and health risk. The technical, cost, and schedule baselines should be
evaluated with regard to risk factors such as technology, interfaces, stakeholder
involvement, worker issues, etc. This assessment is a combined effort between the
contractor and the customer.
• Radiological Controls. Describes the ALARA (as low as reasonably achievable)
implementation and radiological exposure/dose reduction practices. This appendix
includes projected radiological dose estimates and the actual measured doses. It also
defines the key radiological control management indicators.
• Waste Management. Identifies the projected wastes by type and volume and captures the
waste generation actuals. Waste management, pollution prevention, and waste
minimization practices and methods are also identified. Other regulatory aspects may be
included as appropriate.
• Closure Plan. Provides detailed actions to be completed during deactivation to
accomplish the closure of specific systems in compliance with regulatory requirements.
During development of the deactivation project plan, facility conditions and/or business situations
are identified that necessitate the inclusion of more than the usual plan elements. The deactivation
project plan should include additional appendixes, other than those previously suggested, which
address the following on an as-needed basis and as agreed upon by management:
• Separate identification of costs to operate and maintain the facility, exclusive of direct
deactivation tasks. (The costs of deactivation activities are identified in the deactivation
Section 15
19 DOE G 430.1-3
9-29-99
project plan.) This allows illustration and analysis of the deactivation project’s mortgage-
reduction achievement.
• Resource needs for the deactivation of existing facilities. An important aspect is the
transformation of the existing facility’s organizational structure from what may be primarily
a production (continuous level of effort) organization to a project organization that moves
toward decreasing resource needs.
• Technical integration with other projects and activities. For deactivation of existing
facilities, the primary emphasis is on physically connected facilities and service systems
outside of the project scope.
• Project flow or logic diagram for purposes of identifying important decisions that affect the
project performance, their dependencies, and results of the options to be considered.
• Stakeholder involvement and agreements that affect worker and public health and the
conduct or results of deactivation work.
• Environmental activities and documentation, in particular, where prior facility-specific
agreements are to be incorporated into the deactivation work and/or where deactivation
activities potentially have a substantial environmental impact beyond the current
environmental operating basis.
Together, the project plan document and the supporting appendixes form the “body of knowledge”
for the project and provide a useful working tool throughout the life of the project. The level of
detail in addressing specific issues should be appropriate to the nature of the facility and the scope
and magnitude of the deactivation project (i.e., tailoring). The following sections describe the
steps to be taken during the deactivation planning process. Further guidance regarding
deactivation management and deactivation work planning is provided in Chapters 2 and 7 of
DOE/EM-0318.
4.2.1 Step 3: Determine Project Scope
The facility identification and boundaries of a deactivation project normally include the facility
and its associated supporting facilities, offices, and infrastructure. However, a deactivation
project could also be developed around a particular shutdown process (or operation) that may
occur in several different facilities (or areas). The project management team should consider
combining similar processes (or operations) in the facilities into one project.
4.2.2 Step 4: Integrate Safety into the Project
Protection of the worker, the public, and the environment during deactivation is of paramount
importance. It is the direct responsibility of the project management team to ensure that safety
standards and requirements are in place and are integral parts of planning and implementation.
During deactivation projects, workers, for example, are potentially exposed to hazards and risks,
including occupational/industrial, chemical, and radiological. The risks can be similar to those
20 DOE G 430.1-3
9-29-99
experienced when the facility was in operation but can often be quite different since the tasks
involved in deactivation may be different from those performed during operation. DOE-STD
1120-98 provides further guidance for establishing a set of safety standards applicable to facility
disposition activities.
Integrated Safety Management. In accordance with DOE P 450.4 and DOE-STD-1120-98, the
identification of facility hazards and deactivation tasks will be integrated into the work planning
process to ensure that all existing hazards are identified, hazards associated with deactivation
activities are recognized, and appropriate controls are established. This analysis is iterative
throughout the deactivation process.
Section 16
The overlying objective is to deactivate the facilities in a safe and hazard-free manner—both for
the employees conducting such work and for the public and the environment—by reducing the
likelihood of release and exposure to the numerous hazards that may be present. To accomplish
this objective, the project team weighs the identified hazards and mitigation options against the
safety and health standards that apply to those hazards and the work to be performed. The project
team, and any involved stakeholders, determine the extent of the safety standards applicable under
safety and health requirements from Federal, State, local, and Departmental Orders and Standards
and nationally and internationally recognized consensus standards. A consensus should be reached
on the applicability to the project.
This group also determines the adequacy of these requirements to protect the workers, the public,
and the environment. Once agreement has been reached, the safety and health standards are
incorporated into the work tasks.
Scope of Hazards. The identification of hazards in the facility is a critical element in future
planning for the end state of the facility. Hazards are evaluated against operational system,
materials handling, safety and health, and regulatory requirements. A preliminary hazard analysis
is conducted commensurate with the adequacy of existing safety documentation, the extent of
hazards, and the nature of the work activities to be performed.
Accurate facility characterization information is a critical element in understanding the hazards.
The information obtained from the Pre-Transfer Review report, which was prepared during the
facility’s transition, should be commensurate with the existing hazards at the time of transfer to the
disposition program. This report is a useful source of information; however, more up-to-date
information may need to be obtained to ensure the current hazards at the facility are well
understood.
The establishment of a multidisciplinary team is recommended to evaluate the hazards. This team
provides a more comprehensive hazard analysis with fewer opportunities to overlook critical
items. Team-member disciplines should cover areas such as environmental, electrical, structural,
mechanical, and nuclear engineering; safety and health experts; and operational staff from the
facility. Pending the options considered for deactivation, the teams may include persons from
areas such as safeguards and security, transportation, and regulatory compliance.
21 DOE G 430.1-3
9-29-99
Authorization Basis. Deactivation activities (including any remaining material stabilization) must
be supported by and based on a defensible authorization basis. This basis includes the definition
of work to be performed, any identified hazards related to the work and the associated analysis,
and the administrative and/or engineering controls identified to eliminate or mitigate risks
associated with the hazards.
Worker and public safety and health must be protected from adverse impacts associated with
deactivation activities. Several DOE and external safety and health directives, which describe the
development or updates of documentation, provide guidance for the declaration of how this
protection should be accomplished. DOE-STD-1120-98 provides guidance on the appropriate
integration of such guidance.
Section 17
Safety documentation serves as a key document for authorizing deactivation of a facility. The type
and extent of hazard baseline documents varies depending on the deactivation activity’s work
scope and hazards but typically include a combination of either a Safety Analysis Report, Basis for
Interim Operation, Technical Safety Requirements, or other types of documented analysis and
work packages used to plan and control work tasks. Existing documentation (such as a Safety
Analysis Report written for operations) is evaluated to determine whether it is adequate to meet
the latest operational or deactivation requirements and whether the facility configuration is well
documented for the remainder of the facility’s life cycle. Typically, when an existing DOE facility
Safety Analysis Report does not meet the requirements of DOE 5480.23, NUCLEAR SAFETY
ANALYSIS REPORTS, a Basis for Interim Operation is prepared as an interim hazard baseline
document until the Safety Analysis Report can be upgraded. DOE-STD-3011-94, Guidance for
Preparation of DOE 5480.22 (TSR) and DOE 5480.23 (SAR) Implementation Plans, provides
guidance for preparing a Basis for Interim Operation.
A Safety Analysis Report or Basis for Interim Operation typically serves as the hazard baseline
document for Hazard Category 2 or 3 nuclear facilities, as required by DOE 5480.23, and other
equivalent documents serve as the baseline for hazardous chemically contaminated
(nonradiological) facilities. These documents are the principal safety and health documents that
ensure worker hazards are identified, evaluated, controlled, and communicated. This
documentation is used to prepare work packages for the worker before a given activity begins.
They also provide a baseline or inventory of hazards against which unforseen hazards can be
evaluated.
Process Systems Evaluations. Evaluation of the critical systems needed to maintain the facility at
the deactivation end state must be completed in order to plan work effectively. This evaluation
helps ensure the necessary configurations are maintained in a safe and secure manner. A history of
the operational systems should be reviewed to investigate past occurrences or accidents,
performance constraints of the system, and anticipated life-cycle issues that may require
replacement of system components before deactivation or decommissioning can be accomplished.
Materials Hazards Evaluations. One of the major drivers for deactivating an excess facility is to
place it in a low-risk state with minimum S&M requirements. Some of the first S&M costs that
can be reduced are those related to surveillance of stored hazardous and radioactive materials and
wastes. There may be situations where the facility contains these stored materials and wastes even
22 DOE G 430.1-3
9-29-99
after the completion of transition activities. Disposition paths may not yet be available or
agreements prior to facility transfer may have been made between the operating program and the
disposition program. Removal of these materials and wastes should be one of the first decisions
made prior to conducting any other deactivation activities.
Finding an alternative use for some materials may be better than waste disposal. This option
should be considered regardless of returned monetary value. A key factor in the evaluation is the
impact a waste designation may have on management of the material. Long-term regulatory control
and the costs associated with maintaining facilities for treatment and disposal, including
maintenance of documentation, should be evaluated.
Section 18
Prioritization of Facility Hazards. Prioritizing facility hazards is an important step in developing
the specific work packages. As the level of detail of available information improves during the
planning phase, improvement to the levels of work to be performed can be made. As the improved
work scope develops, the ability to modify the priority for execution of near-term tasks improves.
This may also assist sitewide prioritization during deactivation of multiple facilities.
Identification of Standards and Requirements. Many requirements and standards are applicable
to a deactivation project, ranging from materials accountability to facility integrity. A necessary
and sufficient set of standards is one that meets the performance expectations and goals for the
work and contains only the standards necessary for the given work activities and the associated
work hazards under consideration. This process consists of the following actions:
• initiating the necessary and sufficient closure process for each project;
• compiling or developing a necessary and sufficient set of standards;
• incorporating these standards into the work planning; and
• evaluating work performance against these standards.
As the deactivation work progresses, it is necessary to evaluate the completed actions and
reconsider the standards decided upon during the work planning. Based on the hazard level
remaining in the facility following completion of work, changes may be made to improve the
effectiveness and control of the remaining deactivation activities.
Implementation of Controls. After analyzing the hazards, defining the work scope, and
determining the standards and requirements, sufficient detail exists to complete each work scope
task. Control methods are implemented, such as significant check points in the work planning and
performance process, to ensure that the activities are completed in a safe and timely fashion.
Approach to Meeting Requirements. Prior to the physical start of deactivation, the level of
detail should be sufficiently high to determine detailed end-point specifications, an authorization
basis to perform the work safely, work package specifications, and detailed cost and schedule
estimates. By incorporating this information into the project plan, the project team ensures that
configuration controls have been established for the level of work to be performed.
Before validating and initiating the deactivation project, and after establishing and approving the
baselines, the project team, especially the project manager, should implement the appropriate
23 DOE G 430.1-3
9-29-99
controls on those project areas that were identified as high risk. The project manager or team can
control a project by regulating the degree of detail, frequency of feedback, accuracy of feedback,
timeliness of feedback, and formality of feedback based on the unique project characteristics and
complexity.
4.2.3 Step 5: Develop Detailed End-Points
A fundamental premise of project management for deactivation is to identify when the deactivation
project is complete. Specifying the end-points for the facility’s spaces, systems, and major
equipment is the key to identifying when a facility has been deactivated. End-point specifications
for the entire facility are used during and/or after implementation:
• as input for scheduling and cost estimating;
• to create detailed work plans for each space and system in the facility;
Section 19
• to document bases for performance-based contracting or out-sourcing of work, where
practical to do so;
• to demonstrate conformance to agreements negotiated with third parties who have a
legitimate stake in the condition of the facility after deactivation; and
• to show compliance with both local and Federal regulations.
A consensus on the desired end points helps to reduce scope, cost, and schedule changes and
ensures an improved level of satisfaction by stakeholders.
Since identifying the end points is an integral part of deriving the project work breakdown
structure, schedule, and budget, end-point planning and specification should be initiated as soon as
possible. Specifying end conditions is the first part of the end-point planning process. Facility
end points are derived for plant areas, structures, systems, and equipment. The specifications
should be quantitative, where possible, and in all instances must be explicit.
Specifying and achieving end points is a systematic engineering method for progressing from an
existing condition to a desired final set of conditions in which the facility is safe, shutdown, and
can be economically maintained and monitored. An end-point method is a way to translate broad
mission statements into explicit goals that are readily understood by engineers and the crafts
personnel who perform the work. The method is a systematic process that can result in hundreds,
to a thousand or more, explicitly stated conditions to be achieved.
The detailed specification and the actual end points achieved will undoubtedly vary from facility
to facility across the DOE complex. Variations are expected because of the differences among
facilities with respect to previous mission requirements, equipment and systems, containment,
degree of contamination, ability to isolate the contamination, facility environs, projected ultimate
disposition, and a host of other factors. Regardless of variations in conditions to be achieved, the
methods used to decide and specify end points are fundamentally similar.
24 DOE G 430.1-3
9-29-99
Several guiding principles form the foundation of the end-point process:
• The decision to specify an end point needs to be driven by, and clearly linked to, top-tier
program objectives.
• End-point decisions are integrally linked to decisions (and constraints) on resources and
methods. If a proposed end point is not economically feasible, it will only be specified if
mandated by law, applicable regulation, or formal agreement.
• End-point decisions may consider, but should not be driven by, decommissioning
presumptions.
• Defense-in-depth as a fundamental safety approach is used to determine the end-point
condition of the deactivated facility. As applied here, defense-in-depth involves three
layers of protection: (1) elimination or mitigation of hazards, (2) effective facility
containment, and (3) facility monitoring and control. In this context, the concept of
reducing risk to acceptable levels can be applied.
• Successful end-point development requires “ownership” by all affected organizations,
including the planners, the deactivation work force, and the receiving organization.
• Work teams in the field need clear, quantitative completion criteria. End points must be
established up front, must meet the completion criteria, and be practical and achievable.
• End-point development is an iterative process. Most end-point decisions can be made
during the planning stages early in the project; however, some end points will have to be
revisited as deactivation proceeds.
Section 20
• A deactivation project is intended to be done in the short term; therefore, it must be
possible to achieve the objective with current knowledge. That is, a reasonable schedule
probably would not allow for preliminary research as a prerequisite for activities to
achieve an end point.
These guidelines should be used when selecting the end-point method, setting up criteria, and
specifying detailed end points. The use of a tailoring approach in the development of the facility
end points is appropriate to differentiate between complex facilities with process systems and/or
significant hazards and those with relatively simple buildings that are not substantially
contaminated and do not have complex equipment or systems. DOE considers the hierarchical
end-point or checklist end-point methods described in Chapters 5 and 6 of DOE/EM-0318 to be
acceptable methods for deriving end-point specifications.
4.2.4 Step 6: Identify and Evaluate Alternatives
As previously stated, the overall mission of deactivation is to achieve a safe shutdown of the
contaminated facility, reduce risks, and attain a low-cost S&M until the eventual decommissioning
of the facility. This includes identifying, assessing, and evaluating alternatives and end points for
deactivation activities which support both the deactivation and the decommissioning end states.
25 DOE G 430.1-3
9-29-99
The alternatives and end points, and the methods for developing them, are included during the
deactivation planning process.
An important part of this step in the deactivation process consists of compiling all pertinent
information contained in the Pre-Transfer Review report, end-point determinations, and any other
analyses or reviews. This information provides the basis for identifying deactivation alternatives
and selecting the most appropriate alternative with input from the public, as appropriate.
The identification and evaluation of deactivation alternatives along with the end points determines
the extent of action to be taken to deactivate the facility (or portions thereof). Following
identification of candidate alternatives, data from several interrelated activities and incorporation
of integrated safety management provides the information necessary for the selection of the
preferred alternative, including:
• characterization results and documentation from prior transition activities (augmented as
necessary);
• the need to continue maintaining adequate controls for worker safety while conducting
deactivation;
• risk assessments that support the safety analysis and are proportionate to the potential
threat resulting from actual conditions in the facility; and
• analyses of hazards and identification of mitigating measures associated with each
deactivation alternative.
Information on factors that could influence the selection of deactivation alternatives (e.g., potential
future use, long-range site plans, facility condition and potential health, safety and environmental
hazards) are contained in the Pre-Transfer Review report. A tradeoff analysis to systematically
analyze alternative options is used to compare characteristics such as:
• life-cycle cost,
• schedule,
• worker exposure,
• waste generated, and
• discharge of hazardous material(s) to the environment
Examples of three types of cost-benefit evaluations to choose among deactivation end-points is
provided in Chapter 9, Section 9.1.2, of DOE/EM-0318. These analyses greatly enhance the
process of identifying, assessing, and evaluating alternatives and the selection of the preferred
alternative.
Section 21
Sound engineering must be incorporated in the planning process to ensure the alternative actions
identified meet the project objectives, the environmental issues associated with the deactivation
are recognized and assessed, and there is a support structure for the preparation of any required
environmental documentation.
26 DOE G 430.1-3
9-29-99
Using the information gained in this step of the deactivation process, DOE formulates and evaluate
deactivation alternatives and select the preferred alternative. The analysis of deactivation
alternatives is to be commensurate with the scope and complexity of the deactivation project,
consistent with the application of tailoring.
Communication and involvement with stakeholders should also be actively maintained as needed
throughout the development of the project execution alternatives and the selection of the preferred
deactivation alternative. Constant communication during alternatives development allows for
incorporation of requirements, concerns, and expectations into the project execution alternatives.
Open communication during the development of the project execution alternatives facilitates
consensus on which alternative will be pursued.
The final decision in the selection of the deactivation action is documented. The decision takes
into account all analyses of deactivation alternatives and the comments received on the
alternatives. The documentation on the selection of the preferred alternative includes the rationale
for the selection.
4.2.5 Step 7: Prepare Baselines
The project baseline is a quantitative expression of projected costs, schedule, and physical
progress of a deactivation project. Projects are approved and resources are allocated based on
the expectation that risks and hazards will decrease and overall costs will be reduced. Cost and
schedule baselines are a base or standard for objectively measuring the technical achievements
and expenditure of resources. Baselines increase in the level of detail as the deactivation project
progresses. Only high-level schedule parameters are identified initially, and the total baseline is
provided after the detailed deactivation project plan is developed. Baseline development for each
deactivation project is unique and depends on the specific hazards and risks associated with the
facility. However, the process is iterative in nature and proceeds in the following sequence:
1. Performance Baseline. The performance policies for a deactivation project are the first
project expectations generated and are documented in the performance baseline. This
baseline presents a quantitative expression of the physical transformation the facility will
undergo (i.e., decontamination achieved, remaining hazardous materials removed, etc.) and
provides an objective reference for the measurement of progress toward the project’s end
points and eventual deactivation end state.
The performance baseline is developed after the existing conditions at an excess facility
are identified. This allows the project manager to understand the existing hazards, risks,
liability, and costs, associated with the facility. The desired deactivation end state also
identifies and is a quantitative description of the level of contamination, amount of
hazardous materials, etc., in the facility when the deactivation project is completed.
Section 22
2. Cost and Schedule Baselines. After the performance baseline is determined, the sequence
of actions and the associated costs necessary to achieve the desired end points are
identified. Cost and schedule baselines are evolutionary in nature. During the first phase
of development of the deactivation project plan, an initial total cost estimate can be
27 DOE G 430.1-3
9-29-99
determined using parametric cost-estimating techniques. As the plan is finalized, a
detailed funding profile is developed, a detailed cost estimate is produced, and an activity-
based cost estimate is associated with the detailed design. The budget developed for the
deactivation project plan should refer to the cost estimate.
3. Technical Baseline and Milestones. The technical baseline provides clear definition of the
deactivation project’s scope and the technical approach that was selected for the project.
It is used to capture the results of the engineering effort which converted the functional
objectives and requirements of the project into clear technical specifications. The
technical baseline also contains significant technical milestones such as completion of
scope required to meet regulatory agreements and stakeholder commitments.
Each deactivation activity undertaken to support the project provides information not only in
support of decisions to be made but also for other activities during the decision-making process.
A schedule for accomplishing these activities should be developed with milestones identified.
The project baseline is the integration of the technical scope, the cost, and the schedule baselines.
Each component baseline is measurable and must be established by the end of the full project
definition so that the performance can be monitored and controlled throughout the project’s life
cycle. Tracking performance against the approved baseline allows the use of standard project
management performance measurement tools, such as “earned value” to determine the intermediate
levels of success toward completion.
4.2.6 Step 8: Issue Project Plan Document
Documentation of the outputs from the various deactivation planning steps allows communication
of the objectives, requirements, and constraints to the project organization and documents how the
deactivation project is to be carried out. This information is issued to the project organization
responsible for the planning and performance of the work tasks required to meet the deactivation
end points.
4.2.7 Step 9: Detailed Work Packages
The information contained in the project plan forms the basis for the development of detailed work
packages. These specific work packages provide the safety and health requirements as well as the
step-by-step instructions to the workers responsible for the conduct of the work to be performed.
As the level of detail improves during project development, detailed work tasks can be developed
and scheduled. These tasks should be identified, evaluated, and controlled within the facility’s
existing job-control system. As indicated in Section 3.2 of this Guide, the principles of integrated
safety Management must be an integral part of the work package and job-control system.
To be effective, work packages need to include the following items:
• A description of specific work scope activities.
28 DOE G 430.1-3
9-29-99
• Identification of the type of hazard analysis required for the activity and verification that
the analysis was performed.
Section 23
• A method to ensure that hazards associated with each of the planned activities are
documented and communicated to workers together with the steps to eliminate, minimize,
or reduce the risk of those hazards to an acceptable level.
• Work permits necessary to conduct such work.
• The necessary training requirements to perform each task.
• A listing of specialized equipment and each item’s intended use.
• The personal protective equipment needed to limit exposure to the identified hazards.
• The emergency response procedures applicable to the task and the area of work.
• A description of the management structure, including communication and reporting
channels.
• Engineering studies applicable to the task.
• The expected results upon completion of the task.
The detailed work packages provide the details of the work to be accomplished and the process
for doing such work safely and efficiently. The work packages, also, provide the structure of
project activities needed to sufficiently inform all involved parties of the work to be
accomplished. This documentation ensures that safety and health impacts have been verified and
evaluated and that controls are established prior to commencing work.
As a final step to work package preparation, the planned work activities are evaluated against the
potential impact to the safety authorization of the facility. A safety review is conducted to ensure
that the work activities are authorized to be performed within the facility’s safety envelope. The
formality and rigor of this type of process may vary with the existing hazards or the hazard
classification of the project or facility. However, a determination of the impact on the
authorization basis is essential.
4.3 STEP 10: PROJECT EXECUTION
After the work packages have been developed, the work is performed. Because work execution is
highly variable and execution guidance can be found in many other sources, it is described and
listed as a single general step in this Guide. The execution phase will have to be continuously
revisited both formally and informally, as deactivation work progresses.
This step is performed until the end point criteria are achieved as stated in the deactivation plan.
During the conduct of deactivation activities, provisions of the facility’s safety and health plans
and the technical specification of the deactivation project plan must be followed to ensure that
field activities are protective of workers, the public, and the environment. Wastes generated
29 DOE G 430.1-3
9-29-99
during the performance of deactivation activities must be handled in compliance with applicable
regulatory requirements. In addition, DOE’s Pollution Prevention Program Plan, dated 1996,
and Pollution Prevention/Waste Minimization User’s Guide for Environmental Restoration
Projects: Decommissioning and Remedial Actions, DOE/OHG 1320.2A-1, dated March 1998,
which provide guidance for developing qualitative and quantitative waste reduction goals, should
be considered.
4.3.1 Step 11: Feedback
Project personnel must maintain safety during the deactivation period while conducting the tasks
defined in the work packages and performing the remaining day-to-day S&M activities. Integrating
the normal S&M activities with the deactivation tasks is critical to maintaining safety. One way to
do this is by conducting pre-job briefings, which include the procedures to be used, a review of
the hazards and adopted controls, a review of the emergency procedures, and consideration of all
of the additional activities ongoing in the facility. This also provides an excellent opportunity to
verify that all permits are in place, the emergency response plan is ready for implementation, and
personnel have completed the appropriate training to accomplish the activity.
Section 24
While performing deactivation tasks, project personnel must ensure that hazard controls and work
practices are monitored for adequacy. It is necessary to establish a feedback mechanism to
provide information on unforseen hazards and to develop corrective actions to mitigate any
hazards. The feedback system can also provide an avenue to review completed work activities
and assess the need for additional controls or the removal of controls as a result of lowered risks
in the facility.
The effectiveness of the feedback system can be ensured with management support and
commitment. It is important that project personnel understand their rights and responsibilities
related to maintaining safety and health during the course of the deactivation project.
4.4 PROJECT CLOSEOUT
The completion of the deactivation project is determined by verifying that the end state has been
achieved and the end points have been met. The end-point closeout formally demonstrates
completion and provides the necessary documentation, including the physical and administrative
characteristics and current safety and health information to support post-deactivation reviews.
This documentation also verifies that quality control and quality assurance provisions have been
met.
Facility-specific data contained in DOE’s Facility Information Management System (FIMS) is to
be reviewed and updated to reflect the facility condition as a result of the completion of
deactivation end points.
Closeout of the deactivation project signifies completion of one step in the life cycle of the facility
and the beginning of another. Details pertaining to post-deactivation S&M, ownership of those
activities, as well as the timing for decommissioning are addressed in DOE G 430.1-2 and DOE G
430.1-4.
30 DOE G 430.1-3
9-29-99
4.4.1 Step 12: End-Point Closeout
Facility end points provide the critical link to the success of moving the facility through the
deactivation process. It is necessary to evaluate the end points obtained through the deactivation
operation to determine if the achieved end points meet those originally planned. A variety of
methods may be used to verify the end points, ranging from visual inspections to explicit
measurement procedures. A record of the verification method used is included in the project
closeout documentation, allowing transfer of this essential information during the transition of the
facility into decommissioning.
4.4.2 Step 13: Final Report
Just as the Pre-Transfer Review report documents the condition of the facility at the time of
transfer from the operating program to the disposition program, the final deactivation report
provides a facility condition status after the deactivation end points have been completed. This
report includes S&M recommendations for ensuring the remaining facility hazards are contained
and monitored. The post-deactivation S&M should be consistent with the guidance provided in
DOE G 430.1-2. At this point in the project, sufficient information should be available to prepare
this report with minimal effort.
The intent of the deactivation final report is not only to document the existing condition of the
facility but to provide the receiving organization with a clear understanding of the deactivation
activities and the results that were obtained. The following elements should be addressed in the
final report:
Section 25
• Project Background. This section documents the facility description and physical
boundaries. Descriptions of the deactivation project concept, objectives and scope are
helpful in order to better understand the deactivation activities that were completed. This
is important in that some number of years may have elapsed in a continuing surveillance
and maintenance mode prior to any decommissioning efforts.
• Project Performance. The deactivation project activities are included or referred to in the
deactivation project plan and the project results identified. It is important to also describe
any issues and barriers that were necessary to overcome and any special management
methods required in the performance of the deactivation tasks.
• Project Management. Typical project performance elements such as cost and schedule are
summarized. The work breakdown structure used is also helpful in understanding how the
deactivation activities were managed.
• Project Safety and Health Management. A summary description of all remaining
radiological, industrial, nuclear, and environmental facility hazards must be provided. Any
project results directly related to safety are also included.
• Configuration. A list of all existing operating systems and the surveillance and
maintenance activities required to maintain the current safety envelope of the facility will
DOE G 430.1-3 31 (and 32)
9-29-99
be included. The location of all documentation and records such as those that define the
authorization basis; the permits, licenses, and agreements that remain imposed on the
facility; and the remaining commitments to regulatory authorities, stakeholders and DOE
organizations that require action are identified.
• Lessons Learned Summary. As with all projects, it is important to document the lessons
learned during the planning and performance of deactivation activities. This information,
provided in the final report, assists in planning for the next phase, decommissioning, as
well as other deactivation projects at the same or other sites within the DOE complex.
An updated characterization of the facility and the remaining materials contained therein and a
revised condition assessment of all structures, existing protective barriers and systems installed to
ensure the safety of workers, the public, and the environment, minimizes the effort required to
complete the final deactivation report. This information is invaluable in providing the receiving
organization with an understanding of the facility’s condition; the nature, levels, and probable
extent of remaining hazardous chemical and radiological contamination within and around the
facility; and an inventory or estimate and the locations of the remaining toxic, hazardous, and
radioactive materials.
4.4.3 Step 14: Deactivation to Decommissioning
This step is the boundary between the deactivation phase and the decommissioning phase of the
facility’s life cycle. Once the deactivating program organization verifies that the project
deactivation end state has been achieved and is adequately documented, the receiving organization
(usually the decommissioning organization) is identified. Management and financial responsibility
of the facility may now be transferred.
Section 26
Similar transfer reviews, documentation, and memorandums, as outlined in DOE G 430.1-5, may
be used in the transfer process (e.g., a report including all project documentation and the use of a
signed agreement to document condition, state of readiness, and associated funding for transfer). It
is important to maintain the same objective of an integrated and seamless process linking the new
decommissioning phase with deactivation as the excess facility is transferred to its next life-cycle
phase.
Development of decommissioning activities is discussed further in DOE G 430.1-4.
DEACTIVATION. IMPLEMENTATION GUIDE.
FOREWORD
CONTENTS
1. INTRODUCTION
1.1. PURPOSE
1.2. ALTERNATIVE METHODS
1.3. APPLICABILITY
1.4 CROSSWALK OF DOE O 430.1A REQUIREMENTS TO DOE G 430.1-3
2. THE DISPOSITION PROCESS
TRANSITION
EARLY DECISIONS
PROJECT PLAN
EXECUTION
ANALYSIS AND FEEDBACK
DEACTIVATION.
PROJECT CLOSEOUT
DEACTIVATION. TO. DECOMMISSIONING.
Figure 1. Disposition Process
3. DEACTIVATION PHASE—GENERAL GUIDANCE
3.1 PROJECT MANAGEMENT PRINCIPLES—SYSTEMS ENGINEERING
3.2. INTEGRATED SAFETY MANAGEMENT
3.3 GRADED APPROACH
4. THE DEACTIVATION PHASE—PROCESS GUIDANCE
4.1 EARLY DECISIONS
4.1.1 Step 1: Policy and Operational Decisions
4.1.2 Step 2: Facility End-State Decision
4.2 DEACTIVATION PROJECT PLANNING
4.2.1 Step 3: Determine Project Scope
4.2.2 Step 4: Integrate Safety into the Project
4.2.3. Step 5: Develop Detailed End-Points
4.2.4. Step 6: Identify and Evaluate Alternatives
4.2.5. Step 7: Prepare Baselines
4.2.6. Step 8: Issue Project Plan Document
4.2.7. Step 9: Detailed Work Packages
4.3. STEP 10: PROJECT EXECUTION
4.3.1 Step 11: Feedback
4.4 PROJECT CLOSEOUT
4.4.1 Step 12: End-Point Closeout
4.4.2 Step 13: Final Report
4.4.3. Step 14: Deactivation to Decommissioning