DOE G 424.1-1, Implementation Guide for Use in Addressing Unreviewed Safety Question Requirements
Functional areas: Safeguards, Security, and Emergency Management, Work Processes
This Guide provides information to assist in the implementation and interpretation of Title 10 Code of Federal Regulations (CFR) Part 830.203, Unreviewed Safety Question Process, of the Nuclear Safety Management Rules for applicable nuclear facilities owned or operated by the Department of Energy (DOE), including the National Nuclear Security Administration (NNSA). Canceled by DOE N 251.93.
Superseded By:
Version history and related documents
Superseded by
A newer version replaces this document.
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
DISTRIBUTION: INITIATED BY:
All Departmental Elements Office of Nuclear and Facility Safety Policy
Approved: 10-24-01
Sunset Review: 10-24-03
IMPLEMENTATION GUIDE
FOR USE IN ADDRESSING
UNREVIEWED SAFETY QUESTION
REQUIREMENTS
[This Guide describes suggested nonmandatory approaches for meeting requirements.
Guides are not requirements documents and are not construed as requirements in any
audit or appraisal for compliance with the parent Rule, 10 CFR 830.]
U.S. DEPARTMENT OF ENERGY
Office of Nuclear and Facility Safety Policy
DOE G 424.1-1
CANCELE
D
DOE G 424.1-1 i
10-24-01
FOREWORD
This Department of Energy (DOE) Implementation Guide is approved by the Office of Nuclear
and Facility Safety Policy and is available for use by all DOE components and contractors.
Beneficial comments (recommendations, additions, deletions, and any pertinent data) that may
improve this document should be sent to—
Richard Stark
EH-53/270/GTN
U.S. Department of Energy
Washington, D.C. 20585
Phone (301) 903-4407
Facsimile (301) 903-6172
DOE Guides are part of the DOE directives system and are issued to provide supplemental
information regarding the Department’s requirements as contained in rules, Orders, Notices, and
regulatory standards. Guides also provide acceptable methods for implementing these
requirements.
This Guide may be used by all contractors for DOE Hazard Category 1, 2, or 3 nuclear facilities,
including contractors for National Nuclear Security Administration (NNSA) Hazard Category 1,
2, or 3 nuclear facilities. Throughout this document, wherever it references a contractor or a
DOE contractor, the statement applies to a contractor for NNSA as well.
This Guide was developed in support of Title 10 Code of Federal Regulations (CFR) Part 830,
“Nuclear Safety Management.” It provides guidance for the requirements defined in 10 CFR
830.203, “Unreviewed Safety Question Process.”
In an effort to further improve the implementation of Subpart B of 10 CFR 830, “Safety Basis
Requirements,” DOE is updating three Standards:
• DOE-STD-1104-96, Review and Approval of Nonreactor Nuclear Facility Safety
Analysis Reports;
• DOE-STD-3009-94, Change Notice No. 1, Preparation Guide for U.S. DOE Nonreactor
Nuclear Facility Safety Analysis Reports; and
• DOE-STD-3011-94, Guidance for Preparation of DOE 5480.22 (TSR) and DOE 5480.23
(SAR) Implementation Plans.
The successors to these documents should be consulted and used as soon as they become
available.
This Guide imposes no requirements.
CANCELE
D
ii DOE G 424.1-1
10-24-01
This page intentionally left blank.
CANCELE
D
DOE G 424.1-1 iii
10-24-01
CONTENTS
Page
FOREWORD . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . i
1. INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
2. APPLICATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
2.1 Temporary or Permanent Changes in the Facility . . . . . . . . . . . . . . . . . . . . . . . . . 2
2.2 Temporary or Permanent Changes in the Procedures . . . . . . . . . . . . . . . . . . . . . . 4
2.3 Tests or Experiments Not Described in the Existing DSAs . . . . . . . . . . . . . . . . . 4
2.4 Discovery of Potential Inadequacies in the Existing Safety Analyses . . . . . . . . . . 5
Section 2
3. IMPLEMENTATION GUIDANCE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
3.1 Integrated USQ Process . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
3.2 Screening . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
3.3 Unreviewed Safety Question Determinations . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
3.4 Documentation and Retention . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
3.5 Training and Qualifications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
APPENDIX A. UNREVIEWED SAFETY QUESTION DETERMINATION . . . . . . . . . A-1
APPENDIX B. UNREVIEWED SAFETY QUESTIONS LESSONS LEARNED . . . . . . B-1
CANCELE
D
iv DOE G 424.1-1
10-24-01
This page intentionally left blank.
CANCELE
D
DOE G 424.1-1 1
10-24-01
1. INTRODUCTION
This Guide provides information to assist in the implementation and interpretation of Title 10
Code of Federal Regulations (CFR) Part 830.203, “Unreviewed Safety Question Process,” of the
Nuclear Safety Management Rules for applicable nuclear facilities owned or operated by the
Department of Energy (DOE), including the National Nuclear Security Administration (NNSA).
Section 830.203, “Unreviewed Safety Question Process,” allows contractors to make physical
and procedural changes and to conduct tests and experiments without prior DOE approval if the
proposed change can be accommodated within the existing safety basis. The contractor must
carefully evaluate any proposed change to ensure that it will not explicitly or implicitly affect the
safety basis of the facility. The unreviewed safety question (USQ) process is primarily applicable
to the documented safety analysis (DSA). Although the rule references only the DSA, the DSA
must include conditions of approval in safety evaluation reports and facility-specific
commitments made in compliance with DOE rules, Orders, or Policies. Because application of
the USQ process depends on facility-specific information, results of a USQ determination in one
facility generally cannot be extrapolated to other facilities. DOE approval of the procedure to
implement the USQ process is required by 10 CFR 830.203.
Section 830.203 is expected to be implemented using contractor procedures that ensure that
proposed changes to physical characteristics or operating procedures are adequately evaluated
relative to the approved safety basis and that those proposed changes determined to involve
USQs are brought to the attention of DOE for review and approval before changes are made. A
proposed change or test involves a USQ if—
• the probability or consequences of an accident or malfunction of equipment important to
safety could be increased,
• the possibility of a different type of accident than previously evaluated in the DSA could
be introduced, or
• margins of safety could be reduced.
Section 3
For the purposes of this Guide, equipment important to safety should be understood to include
any equipment whose function can affect safety either directly or indirectly. This includes safety
class and safety significant structures, systems, and components (SSCs), and other systems that
perform an important defense-in-depth function, equipment relied on for safe shutdown, and in
some cases, process equipment. These considerations apply to both workers and the public. In
the case of workers, these considerations apply to all workers, those in immediate proximity to
the hazard as well as collocated workers. In addition to proposed changes, 10 CFR 830.203(g) of
the USQ rule requires notification of DOE and USQ determinations when a potential inadequacy
in the safety analysis is identified. In this case, situations of concern are those wherein it is found
that the current safety analysis may not be bounding or the current safety basis may be otherwise
CANCELE
D
2 DOE G 424.1-1
10-24-01
inadequate. This could be because of an error in the current safety analysis or because the facility
configuration is not what was analyzed.
The existence of a USQ does not mean that the facility or operation is unsafe. The purpose of the
USQ process is to alert DOE of events, conditions, or actions that affect the DOE-approved
safety basis of the facility or operation and ensure appropriate DOE line management action. If a
change is proposed or a condition is discovered that could increase the risk of operating a facility
beyond that established in the current safety basis, DOE line management, including, where
applicable, the NNSA, must review and determine the acceptability of that risk through the
process of approving a revised safety basis that would be developed and submitted by the
contractor.
2. APPLICATION
Section 830.203 applies to all Category 1, 2 and 3 nuclear facilities. All changes to a nuclear
facility, whether temporary or permanent, require application of the USQ process unless a
decision to request DOE approval already has been made. Some changes may be such that they
can be screened out from a detailed USQ determination.
The applicability of Section 830.203 is broad. Nonsafety-related systems are not excluded by the
scope of Section 830.203 if they could affect the proper operation of equipment important to
safety that is relied on in the safety basis. For example, losses of certain nonsafety-related
systems may represent critical operational occurrences identified as initiators in the accident
analysis. Therefore, changes to nonsafety-related systems must be evaluated and may be
determined to involve a USQ.
Physical interactions may also fall under the purview of Section 830.203. For example, the
installation of a nonseismically supported piece of equipment above a seismically qualified
component designed to perform a safety function explicitly or implicitly assumed in the existing
safety analyses may constitute a USQ and must be evaluated.
The following sections discuss the types of changes, tests, and experiments, as well as potential
inadequacies that the USQ process needs to address to comply with Section 830.203.
2.1 Temporary or Permanent Changes in the Facility
Section 830.203 requires USQ determinations for changes to a nuclear facility that alter an SSC’s
design, function, or method of performance as described in the existing safety analyses by text,
drawing, or other information relied on as the safety basis. The safety analyses include
descriptions of many SSCs, but a nuclear facility also contains many SSCs not explicitly
described in the safety analyses. These can be components, subcomponents of larger
components, or even entire systems.
Section 4
Changes to SSCs that are not explicitly discussed in the safety analyses should not be excluded
from the USQ process, since changes to these SSCs may have the potential for altering the
CANCELE
D
DOE G 424.1-1 3
10-24-01
function of an SSC explicitly described in the safety analysis. The recommended approach for
deciding whether a modification involves a change to the nuclear facility, as described in the
safety analyses, is to consider the effect of the change on the SSC of which the SSC being
modified may be a part or which the SSC being modified may support. If the change alters the
design, function, or method of performing the function of the SSC, as described in the safety
analyses, a USQ determination is required. Also, a change to an SSC that does not involve
equipment important to safety could initiate an accident or affect the course of an accident, so
virtually no change can be ignored.
It is important to distinguish between changes and routine maintenance activities. Routine
maintenance activities—except those that are not enveloped by current analyses or that might
violate a technical safety requirement (TSR)—do not require review under Section 830.203. A
TSR limitation on maintenance activities might require limiting the number of systems or
components that can be taken out of service at one time or allowable outage times. Examples of
routine maintenance activities include calibration, refurbishment, replacement with an equivalent
component, and housekeeping. However, some maintenance activities may constitute changes,
such as plant heat exchanger tube plugging where limits are not specified.
The TSR should specify allowable outage times, permissible mode conditions, and permitted
reduction in redundancy for systems or components removed from service for maintenance. A
USQ determination, therefore, need not be performed for these activities. However, for systems
or components that are included in safety analyses for the nuclear facility, and for which allowed
outage times are not included in the TSRs, a USQ determination should be completed.
Understanding the term “change” as it applies to modes of operation or facility processes is also
important. For example, when a facility is designed to accommodate several nuclear processes
but must modify equipment lineup to accommodate another process, the change does not
constitute a change under Section 830.203 if it is performed in accordance with approved
procedures and was considered within the safety basis of the facility.
Temporary changes to the nuclear facility should be evaluated to determine whether a USQ
exists. Examples of temporary modifications include jumpers and lifted leads, temporary lead
shielding on pipes and equipment, temporary blocks and bypasses, temporary supports, and
equipment used on a temporary basis.
The conservative approach is to provide a written USQ determination for any change to the
nuclear facility, whether discussed in existing safety analyses or not. However, it is possible that
some changes can be justified as not requiring evaluations under Section 830.203, as long as
screening criteria are developed that will ensure that no indirect or secondary effects will result
from the change. In this case, the screening criteria are relied on to ensure that the change does
not introduce a USQ.
The actual modification implementation process (for example, work authorization system) used
in the field should be reviewed for possible development of USQs. Changing plant configurations
Section 5
CANCELE
D
4 DOE G 424.1-1
10-24-01
while work is in progress may involve a USQ relating to facility operations, independent of the
safety of the specific work on a modification. For example, if the work involves interrupting a
water supply that a fire protection system (that is not covered by a TSR requirement) depends on,
that interruption should be examined through the USQ process. The work authorization system
should include a step to consider these types of possibilities.
2.2 Temporary or Permanent Changes in the Procedures
A USQ determination may have to be prepared for changes to procedures that are identified in
the facility DSA. However, as discussed in section 3.2, regarding USQ screening, some
procedure changes may not require a USQ determination.
The identification of procedures may be explicit or implicit in the facility DSA. If the procedure
is implied directly by the nature of a topic in the safety basis (including the operational safety
requirements or TSRs), that change should be considered to be to a procedure described in the
DSA, so that a USQ determination is done when appropriate. Such implicitly described
procedures include (1) the procedures that implement a safety management program described in
the safety basis and (2) operating, testing, surveillance, and maintenance procedures for safety
equipment when that equipment is identified in the DSA. If the characteristics of the safety
management program described in the safety basis remain correct, complete, and valid, the result
of the USQ determination would be expected to be negative, signifying that DOE approval is not
required.
Procedures are not limited to those items specifically identified as procedure types (for example,
operating, chemistry, system, test, surveillance, and emergency plan) but could include anything
described in the documented safety analyses that defines or describes activities or controls over
the conduct of work. Changes to these activities or controls qualify as changes to procedures as
described in the documented safety analyses, and therefore must be evaluated as a potential USQ.
Changes to procedures include both revising an existing procedure and creating a new procedure.
For the case of a new procedure, which could not be described already, the question becomes, if
the DSA were to be prepared (or updated) after the new procedure had been approved, is the new
procedure of a type that would be identified in the DSA. If so, a USQ determination should be
prepared for the new procedure.
2.3 Tests or Experiments Not Described in the Existing DSAs
Written USQ determinations are required for tests or experiments not described in the existing
safety analyses. The intent of Section 830.203 is to require USQ determinations of tests and
experiments that might affect safe operations but are not described in the existing safety analyses.
Tests and experiments should be broadly interpreted to include new activities or operations. By
definition, these are activities that could degrade the margins of safety during normal operations
or anticipated transients or degrade the ability of SSCs to prevent accidents or mitigate accident
conditions. New configurations that require a criticality safety evaluation should be considered
CANCELE
D
DOE G 424.1-1 5
10-24-01
Section 6
as a test or experiment. A USQ determination should be performed to ascertain whether a DOE
review and approval of the new configuration is required. For preoperational tests, surveillance
tests, functional tests, and startup tests that are performed regularly, USQ determinations are not
required every time a test is performed. However, one-of-a-kind tests used to measure the
effectiveness of new techniques or a new system configuration that might affect safety SSCs will
require evaluation before they can be conducted. Postmodification testing should be considered
and included in the USQ determination for the modification.
2.4 Discovery of Potential Inadequacies in the Existing Safety Analyses
Written USQ determinations are required when a contractor identifies a potential inadequacy of
the safety analyses that support the DOE-approved safety basis, which indicates the safety
analysis is not bounding or may be otherwise inadequate. The intent is to ensure that the
operations are conducted in a safe manner that is consistent with the safety basis.
Because an inadequacy in the safety analyses has the potential to call into question information
relied on for authorization of operations, DOE requires the contractor to—
• take appropriate action to place or maintain the facility in a safe condition;
• expeditiously notify DOE when the information is discovered;
• perform a USQ determination and submit the results promptly; and
• complete an evaluation of the safety of the situation and submit it to DOE before
removing any operational restrictions implemented to compensate for the analytical
discrepancy.
Bullet item 3, above, means that the USQ determination should be prepared promptly and the
results submitted promptly. This is also intended to mean that the time frame after initial
notification of DOE until submittal of the USQ determination results should be on the order of
hours or days, not weeks or months. If a USQ is determined to be present, the evaluation of the
safety of the situation will require not only DOE’s review but also its approval of resulting
changes before any operational restrictions are removed.
The facility DSA, as part of the safety basis, is important to safety for a number of reasons.
Among these, the DSA defines the safety risks that DOE has accepted when authorizing
operation of the facility. Because of this feature, that analysis is the baseline reference for the
USQ process. If that reference were to be inadequate, the USQ process would be compromised.
Therefore, the USQ process includes special actions to be taken if it appears that the safety
analyses might be inadequate.
The DSA may be inadequate for any number of reasons. In general, it is possible for a
potentially inadequate analysis to arise from three entry conditions: (1) a discrepant as-found
CANCELE
D
6 DOE G 424.1-1
10-24-01
condition, (2) an operational event or incident, or (3) new information, including discovery or an
error, sometimes from an external source. The main consideration is that the analysis does not
match the current physical configuration of the facility, or the analysis is inappropriate or
contains errors. The analysis might not match the facility configuration because of a discrepant
as-found condition. Analytical errors might involve using incorrect input values, using invalid
assumptions, using an improper model, or calculational errors. The USQ process starts when the
facility management has information that gives reason to believe that there is the potential that
the facility DSA might be inadequate.
Section 7
The USQ process does not apply to the process of upgrading DSAs in response to new
requirements or to the use of new or different analytical tools during the upgrade process.
However, the USQ process does apply when there is reason to believe that the current safety
basis might be in error or otherwise inadequate, as discussed in the preceding paragraph.
3. IMPLEMENTATION GUIDANCE
The USQ review process should be integrated into all technical aspects of the contractor
organization responsible for design, engineering, maintenance, inspection, operations, and
assessment of the nuclear facility or activity. Individuals involved in these aspects of the
organization should be familiar with the requirements of Section 830.203 and should be able to
identify activities that might need to enter the USQ process, while carrying out their normal
responsibilities.
Each facility should identify the methods by which facility changes can be made (for example,
whether changes are made under modification processes, nonconformance processes, or
maintenance processes). After these methods have been identified, each facility must determine
what constitutes an acceptable means to make a change; that is, the contractor must clearly
control the facility change process and must perform and document changes in accordance with
approved procedures. Performing a modification under the guise of maintenance is not
acceptable because the proper control processes to analyze the proposed change and document its
outcome would probably be absent. It is necessary to identify all means for performing a change
because each one provides a direct input into the USQ process and must be integrated
accordingly.
The USQ process is intended to be implemented along with a change control process that
includes generalized steps for (1) identifying and describing the temporary or permanent change,
(2) technical reviews of the change, (3) management review and approval of the change,
(4) implementation of the change, and (5) documenting the change. As part of the technical
reviews of a change, the contractor should perform the appropriate type of safety analysis to
ascertain whether the change is indeed safe. This is accomplished separately from the USQ
process. The USQ process is used subsequently to determine if final approval of the change by
the contractor is sufficient or if DOE approval must be obtained.
CANCELE
D
DOE G 424.1-1 7
10-24-01
Contractors should develop procedures that provide detailed guidance for the performance of the
USQ process, including any screening and the USQ determinations. The procedures should—
• define the purpose of the procedure;
• set forth the procedure’s applicability;
• provide definitions of appropriate terms, include screening criteria, as appropriate, and
the basis for their application;
• include detailed guidance on what must be considered and evaluated when performing or
reviewing a USQ determination;
• define the qualifications needed and responsibilities of personnel performing and
reviewing USQ determinations; and
• include documentation requirements for each USQ determination.
DOE relies on the contractor’s implementation of the USQ process to preserve the integrity of
the safety basis while allowing flexibility in operations. The contractor responsible for a DOE
Hazard Category 1, 2 or 3 nuclear facility must submit the procedure that defines its USQ
process to DOE for approval.
3.1 Integrated USQ Process
Section 8
The USQ process should be integrated into the facility’s change control processes. The change
processes should ensure that the USQ process is integrated into existing procedures or that new
procedures are developed, as necessary and that the need for completion of a USQ determination
is not overlooked.
Each facility should develop its own change flow process for both temporary and permanent
changes to SSCs and documents. This process and its integration should be described by a
governing policy, procedure, flowchart, or other description. The purpose of the governing
document is to define clear relationships between the USQ process and other change control
procedures, including design change procedures, configuration control programs, temporary
change procedures, and procedures governing the preparation, review, and approval of
procedures. Its purpose is to describe how the USQ processes required by Section 830.203 are
integrated into the facility's processes and not to implement the details of the rule itself.
The facility USQ procedures should provide that the USQ documents (that is, any screening and
the USQ determination) are prepared by one individual and then reviewed technically by a
second person. That person should be independent in the sense that he/she has not been involved
in the preparation of the USQ documents. That person does not need to be organizationally
independent.
CANCELE
D
8 DOE G 424.1-1
10-24-01
The facility USQ procedure should provide also that facility line management takes approval
action on the USQ documents. This ensures that line management is informed of the results of
the USQ process and can take whatever followup actions are appropriate, such as submitting the
change to DOE for safety review and approval or canceling the proposed change. The use of a
facility operating review committee to review the USQ documents and provide advice to facility
line management may be beneficial, but review by such a committee should not be used in lieu of
the line management approval action. Care should be used to avoid excessive levels of approval.
Typically, one approval is sufficient, with a second corporate-level approval for positive USQ
determinations.
3.2 Screening
The purpose of USQ screening is to ascertain if it is necessary to expend the valuable time and
resources necessary to perform a USQ determination, or if there is reasonable technical
justification for not performing a USQ determination. DOE encourages the use of screening to
limit the number of matters for which USQ determinations must be performed, provided the
reasons for exclusion are documented and well supported. When properly defined and
implemented, the screening criteria should assist in reducing the efforts expended for matters of
minor significance and should focus efforts more on the more important matters for which
Section 830.203 is intended. When an item is screened out from further consideration, the
rationale for the screening should be documented and retained with records of USQ actions.
Candidate items for screening include situations wherein the USQ process may not be applicable:
• changes to a requirement in the TSRs, or the addition of a new TSR requirement;
• changes that management has already decided will be submitted to DOE for safety review
and approval (including TSR changes, above);
• the installation of an item that is an exact replacement (that is, same manufacturer, same
model number, etc.);
Section 9
• the installation of an item that is on the facility “Approved Equivalent Parts” list, for
which a facility engineer has evaluated and concluded that the replacement item meets all
the requirements pertinent to the specific application at the facility, including the service
conditions;
• changes for which common commercial practices would suffice, and a formal nuclear-
grade change control process is not warranted (for example, changing fixtures for
fluorescent lighting in a control room of the facility); and
• changes to documents that are purely editorial and make no technical change.
CANCELE
D
DOE G 424.1-1 9
10-24-01
In some situations, the screening might determine that the matter does not require any further
USQ consideration. In other situations, the screening may determine that the matter should
proceed directly to a USQ determination. The case of a potentially inadequate safety analysis is
an example of this situation. In other situations, the screening might determine that the matter
must be submitted to DOE and therefore the performance of a USQ determination is not
necessary. A change to a requirement in the facility TSRs is an example of this situation.
Screening criteria are to be applied to those items that, by broad definition, might enter into the
Section 830.203 process but for which a detailed evaluation (USQ determination) is not
necessary. For example, an operational procedure that is described in the DSA may be changed
to correct a typographical error or include an additional reference to an equipment list. Such a
change is not of any safety significance and clearly does not involve a USQ. If the contractor
applied a screening procedure that asks: “Is the change purely editorial and without any technical
change?” (that is, a spelling or typographical correction, grammatical change, clarification, or
additional note or reference), the reviewer could document the change and thus avoid the need to
answer the detailed questions of the USQ determination.
Another manner in which screening criteria may be applied is through categorical exclusions (for
example, different procedure types). For the purpose of illustration, maintenance procedures may
be considered. A basic premise of performing maintenance is that the plant will be restored to
the exact same condition it was in prior to maintenance. That is, the functional capability will
continue to meet or exceed those performance requirements set forth in the safety basis. A
change to a maintenance procedure would therefore not be governed under Section 830.203.
However, whenever screening criteria are applied in this manner, a submittal to DOE should be
made, including an evaluation of why a categorical exclusion (for example, of maintenance
procedures) from the Section 830.203 process is acceptable. Such categorical exclusions are
regarded as part of the contractor’s USQ procedure, requiring DOE approval.
Another screening consideration is the possibility that the matter being considered is fully
covered by a previous USQ determination, even when location differences are considered.
When considering the resolution of a nonconformance situation, it should be recognized that any
disposition that involves a corrective action that does not fully meet all the existing requirements
would constitute a design change. This would include a “use-as-is” disposition; it would not
include an exact “restoration modification” wherein the disposition of the nonconformance is
simply to replace the item with an item that meets all the requirements.
Section 10
3.3 Unreviewed Safety Question Determinations
Contractors are expected to provide detailed guidance and instructions in the form of a procedure
on how to perform a USQ determination. Specific guidance on how to conduct a USQ
determination is contained in Appendix A. Concepts used to develop this process are contained
throughout this Guide. A USQ determination is that record required by Section 830.203 to
document the review of a “change” or a situation where there is reason to believe that the
CANCELE
D
10 DOE G 424.1-1
10-24-01
facility’s existing safety analysis may be in error or otherwise inadequate. It records the scope of
the determination and an explanation of the technical basis for the conclusions reached.
For the purpose of USQ procedures and performing USQ determinations, the three USQ criteria
should be broken down into their constituent seven questions:
(1) Could the proposed change increase the probability of an accident previously evaluated in
the facility’s existing safety analyses?
(2) Could the proposed change increase the consequences (to workers or the public) of an
accident previously evaluated in the facility’s existing safety analyses?
(3) Could the proposed change increase the probability of a malfunction of equipment
important to safety previously described in the facility’s existing safety analyses?
(4) Could the proposed change increase the consequences of a malfunction of equipment
important to safety described in the facility’s existing safety analyses?
(5) Could the proposed change create the possibility of an accident of a different type than
any previously evaluated in the facility’s existing safety analyses?
(6) Could the proposed change create the possibility of a malfunction of equipment important
to safety of a different type than any previously evaluated in the facility’s existing safety
analyses?
(7) Does the proposed change reduce the margin of safety?
The term “safety analyses” in these questions refers to those potential events and their controls
considered in the hazard analysis in the DSA. These include not only the explicit description of
the analyses in the DSA but also any analyses performed to support the summary descriptions of
the analyses in the DSA. When a potential event is discovered that is not treated in the DSA, it
should be considered as a possible new event (see question 5) or as an indicator of a potentially
inadequate safety analysis issue.
For the purposes of this Guide, equipment important to safety should be understood to include
any equipment whose function can affect safety either directly or indirectly. This includes safety
class and safety significant SSCs, and other systems that perform an important defense-in-depth
safety function, equipment relied on for safe shutdown, and, in some cases, process equipment.
In the case of a potentially inadequate safety analysis, the fact that there is reason to believe the
safety analysis may be inadequate makes it a USQ. When the potentially inadequate safety
analysis arises from a discrepant as-found condition, the seven listed questions can be used in a
backward-looking manner. That is, the current physical configuration can be looked at as if it
were a proposed modification. If the USQ determination is found to be negative, the contractor
CANCELE
D
DOE G 424.1-1 11
10-24-01
could have approved the discrepant condition without DOE involvement. This would resolve the
discrepancy and provide justification for the current configuration.
Section 11
The contractor’s USQ procedures should require that a defensible explanation be documented for
the answers to each of the USQ criteria. The explanation should provide a good technical basis,
based on sound engineering judgment, for each of the answers. It is inappropriate to set a
numerical margin for increases in the probability or consequences within which a positive USQ
determination would not be triggered. Such margins lend themselves to excessive efforts in
calculations when accident parameters are highly uncertain, and the possibility that the results
might be a function of the calculation methods used, rather than of safety differences. It is the
direction that the change has on probability or consequences that is important, not the magnitude
that is important. For example, if the wall thickness of a pressure vessel is going to be increased,
or the reaction time of a relay in a safety system is shortened, it is likely the change is in the
direction of increased safety. If the changes are in the opposite direction, safety is likely to be
decreased. However, potential increases should be clearly discernible, at least on a qualitative
basis. In the examples described, one might look at the pressure vessel codes and standards or
the required response times for the relay action relative to the safety function and assess whether
there would still be a comfortable margin of safety. If so, a case could probably be argued that
there would be no discernible increase in probability of an accident. When considering these
issues in the context of bounding accidents, it is important to recognize that the bounding
accidents for workers may be (and probably are, especially for immediately involved workers)
different than bounding accidents for the public.
If, as a result of a proposed change, additional protective measures (either administrative or
hardware-related) are warranted during a postulated accident situation to ensure adequate
protection of the public or to provide worker safety, the USQ determination should conclude that
the USQ determination is positive, on the basis that the change will result in either an increase in
probability or an increase in consequences of an accident. Additional protective measures that
are provided to reduce exposures, such as those related to ALARA (as low as reasonably
achievable) levels, and not related to potential accidents, are not included. DOE wants to be
involved for several reasons. First, to verify that the degree of protection is adequate. Second, to
ensure that the safety basis is properly revised to include the additional protective measures.
Third, to verify that any hardware involved is properly classified (for example, as a safety class
or safety significant SSC) and hence will receive appropriate surveillance and maintenance.
When evaluating for “increases in consequences” of an accident, if the previously bounding case
for that family of accidents remains the bounding case, then generally there is no increase in the
consequences within the USQ process. In this regard, it is important that the family of accidents
be related, in addition to being of the same type (for example, fires), but also utilizes the same set
of preventative and mitigative measures. While this is appropriate for public safety, adequate
protection of workers requires further evaluation. Each change must be evaluated for increases
in the consequences to workers. Further, when considering a new scenario within a family of
accidents, it is important to assess whether the criterion of discernibly increasing the probability
of an accident type may be triggered.
Section 12
CANCELE
D
12 DOE G 424.1-1
10-24-01
The bases of hazard control documents (TSRs or other formats) should identify any relevant
margins of safety. However, all safety basis documents should be reviewed to identify any
relevant margins of safety. See Appendix A.1, subitem 7 for a discussion of margin of safety.
Specific responsibilities of those performing or reviewing USQ determinations should be clearly
defined. Documentation requirements should also be discussed in the implementing procedures.
They should identify the level of detail necessary to document performance of the USQ
determination and conclusions reached and include a list of references relied on to reach this
conclusion as well as guidance for the retention of records.
3.4 Documentation and Retention
The contractor must retain records of USQ actions taken pursuant to Section 830.203 for at least
the full operational lifetime of the facility, until the facility is turned over to the decommissioning
and decontamination phase. If there is a change in the contractor operating the facility, the
outgoing contractor must turn over all USQ records to the incoming contractor. At the end of
this life cycle phase, the contractor should consider retaining the USQ records for the next phase
of the facility life cycle.
The contractor must keep the facility DSA current by updating it annually. All changes at the
facility should be reflected in these updates at an appropriate level of detail, including those that
were authorized through the USQ process. Previously it was specified that updates to safety
analysis reports (DSAs) should include all changes implemented 6 months or more before the
submittal of the annual update. This has been changed to a commensurate schedule, to allow
flexibility. It may be practical to include more current changes than prior to 6 months before
submittal of the update. However, at least those implemented 6 months or more before the
submittal of the annual update should be included.
All contractors responsible for a nuclear facility are required to submit to DOE an annual
summary description of all USQ determinations performed. Items that were screened out and a
USQ determination was not necessary do not need to be included in the annual summary
(although they are still required to be retained in the records of USQ actions). This report should
be submitted on a schedule commensurate with annual update of the DSA.
3.5 Training and Qualifications
Implementing procedures should establish the personnel training and qualifications needed to
perform the USQ process. These include required educational background, years and/or types of
work experience, knowledge of the facility, understanding of DOE requirements related to the
facility safety basis (including the USQ process), and familiarity with the facility-specific safety
basis.
CANCELE
D
DOE G 424.1-1 13
10-24-01
All personnel responsible for preparing, reviewing, or approving USQ documents should receive
training on the application of Section 830.203, including any facility-specific procedures. The
recommended interval for retraining is every 2 years.
The contractor should maintain a list of those personnel who are currently qualified to perform
the USQ process.
CANCELE
D
14 DOE G 424.1-1
10-24-01
This page intentionally left blank.
CANCELE
D
DOE G 424.1-1 Appendix A
10-24-01 Page A-1
Section 13
1 For the purposes of this appendix, “change” will mean any change to procedures or equipment (including prior
undocumented changes), any new tests or experiments, or any new information that has the potential to
invalidate the safety basis.
UNREVIEWED SAFETY QUESTION DETERMINATION
A.1 USQ PROCESS
The unreviewed safety question (USQ) determination is not a substitute for a safety analysis; it
merely serves as a benchmark for whether the safety basis is being preserved. A safety analysis
may show that a proposed change is safe, yet the USQ determination may find that the change
creates a USQ and therefore requires Department of Energy (DOE) approval prior to
implementation. Contractor procedures should clearly establish the differences between the
concepts supporting safety analyses for the documented safety analysis (DSA) and those used for
a USQ determination.
Once it has been determined that a USQ determination is required, it can be approached by
providing an answer to each of the seven questions identified using the USQ determination
process. If any of these questions is answered “yes,” the change is considered a USQ. An
appropriate justification for each answer should be recorded. The examples given in the
following subsections are provided to help the reviewer identify potential USQs. They are not
meant to be examples of USQs. That determination requires consideration of the DSA for the
nuclear facility or other DOE-approved documentation that provides the safety basis for
operations or other activities and the specific details of the activity.
1. Could the proposed change1 increase the probability of an accident previously
evaluated in the facility’s existing safety analyses?
To understand how the probability of an accident occurring could be increased, it is
important to understand how the term “accident” is applied: the term “accident” refers to
the anticipated operational transients and postulated accidents considered in the DSA.
In answering this question, the first step is to determine the accidents, which have been
evaluated in the previously approved safety basis, that may be affected by the proposed
change. By focusing on the initiators of the previously evaluated accidents, a
determination is made as to whether there is an increased likelihood that a given accident
would occur. The following questions may provide a useful approach in making this
determination.
(a) Will the proposed change meet the design, material, and construction standards
applicable to the structures, systems, and components (SSCs) being modified? If
the answer is “yes,” this aspect of the proposed change is judged not to increase
the likelihood of the occurrence of an accident. If the answer is “no” to any of the
items, either a justification for saying there is no increase in the likelihood of the
CANCELE
D
Appendix A DOE G 424.1-1
Page A-2 10-24-01
occurrence of an accident will need to be developed or it is concluded that the
likelihood of the occurrence of an accident is increased.
(b) Could the proposed change affect overall SSC performance in a manner that could
increase the probability of a previously analyzed accident? Possible questions to
ask are—
(1) Could the proposed change use instrumentation with accuracies or
response characteristics that are different from those of existing
instrumentation and could make an accident more likely to occur?
Section 14
(2) Could the proposed change cause SSCs to be operated outside their design
or testing limits? Examples include the following: overloading electrical
systems, overpressurizing a piping system, or operating a motor outside its
rated voltage and amperage.
(3) Could the proposed change cause system vibration, water hammer, fatigue,
corrosion, thermal cycling, or degradation of the environment for SSCs
that would exceed the design limits?
(4) Could the proposed change cause a change to any SSC interface in a way
that could increase the likelihood of an accident?
2. Could the proposed change increase the consequences of an accident previously
evaluated in the facility’s existing safety analyses?
In answering this question, the first step is to determine which accidents evaluated in the
safety analyses may have their radiological and hazardous material consequences altered
as a direct result of the change. The next step is to determine whether the change could,
in fact, increase the consequences of any of the accidents evaluated in the existing safety
analyses. Consequences to workers (in-facility, outside, or collocated) and the public
must be considered. Examples of questions that assist in this determination are as
follows:
(a) Could the proposed change degrade or prevent safety functions described or
assumed in the existing safety analyses?
(b) Could the proposed change alter any assumptions previously made in evaluating
the radiological and hazardous material consequences in the existing safety
analyses?
(c) Could the proposed change play a direct role in mitigating the radiological or
hazardous material consequences assumed in the existing safety analyses?
(d) Could the proposed change affect the integrity or function of any fission product
barrier or any radioactive or hazardous material barriers?
CANCELE
D
DOE G 424.1-1 Appendix A
10-24-01 Page A-3
3. Could the proposed change increase the probability of a malfunction of equipment
important to safety previously evaluated in the facility’s existing safety analyses?
The safety analyses for the facility assume the proper functioning of equipment important
to safety in demonstrating the adequacy of design. The proper functioning of other
systems, including support systems, is generally assumed. The scope of the USQ
determination should include these other systems. For example, a change that does either
of the following is a change that increases the probability of a malfunction of equipment
important to safety:
• degrades the performance of equipment important to safety, assumed to function
in the accident analysis, to below the performance level assumed in the existing
safety analyses; or
• increases the challenge to equipment important to safety assumed to function in
the accident analysis (for example, more rapid pressure rise), degrading
performance to a level below that assumed in the existing safety analyses.
In answering this question, the first step is to determine what SSCs could be affected by
the proposed change. Then the effects of this change on equipment important to safety
are evaluated, including both direct and indirect effects. Direct effects are those in which
the change affects the equipment (for example, a motor change on a pump). Indirect
effects are those in which the change affects one piece of equipment, which in turn can
affect equipment important to safety. An example of indirect effects would be one piece
of equipment falling on safety equipment.
Section 15
After the impact of the change on equipment important to safety is identified, a
determination is made whether an increase in the probability of a malfunction of the SSCs
has occurred. The following are examples of questions that can be used in making this
determination.
a. Will the proposed change meet the original design specifications for materials and
construction practices when the following questions are considered:
(1) Are the seismic specifications met (for example, use of proper supports,
proper lugging at terminals, and isolation of lifted leads)?
(2) Are separation criteria met (for example, minimum distance between
circuits in separate divisions, channels in the same division, and jumpers
run in conduit)?
(3) Are the environmental criteria met (for example, use of materials suitable
for the radiation or thermal environment in which they will be used)?
CANCELE
D
Appendix A DOE G 424.1-1
Page A-4 10-24-01
b. Will the proposed change degrade equipment important to safety reliability by—
(1) imposing additional loads not analyzed in the design?
(2) deleting or reducing system or equipment protection features?
(3) downgrading the support system performance necessary for reliable
operation of the equipment?
(4) reducing system or equipment redundancy or independence?
(5) increasing the frequency of operation of systems/equipment?
(6) imposing increased or more severe testing requirements on systems or
equipment?
If the change adversely affects the equipment important to safety, the likelihood of
equipment malfunction may be increased. A “no” answer to any question in paragraph 3a
or a “yes” answer to any question in paragraph 3b may not mean that there is a negative
impact on safety. It would, however, indicate the existence of a USQ and the need for
further analyses.
4. Could the proposed change increase the consequence of a malfunction of equipment
important to safety previously evaluated in the facility’s existing safety analyses?
This question asks whether, assuming a malfunction of equipment important to safety, the
change would result in increased hazardous-material or radiological consequences. For
example, consider a change that caused a valve in a safety system to fail in the closed
position where previously it was assumed to fail in the open position. If this change
results in an increase in consequences of an accident, it indicates the change involves a
USQ. In some situations, such as a loss of a preferred failure mode, the change might not
lead to an increase in the calculated consequences but should be considered within the
context of a possible reduction in a margin of safety.
5. Could the proposed change create the possibility of an accident of a different type
than any previously evaluated in the facility’s existing safety analyses?
An accident or malfunction that involves an initiator or failure not considered in the
nuclear facility’s existing safety analyses is potentially an accident or malfunction of a
different type. An example would be turbine missiles from a gas turbine added as an
alternate power source. Certain accidents or malfunctions are not treated in the nuclear
facility’s existing safety analyses because their effects are bounded by similar events that
are analyzed.
CANCELE
D
DOE G 424.1-1 Appendix A
10-24-01 Page A-5
Section 16
The possible malfunctions or accidents of a different type are limited to those considered
to be as likely to happen as those considered in the existing safety analyses. For example,
a seismic-induced failure of a component designed to appropriate seismic criteria will not
cause a malfunction of a different type. However, a change that increases the probability
of an accident previously thought to be beyond extremely unlikely, so that it is as likely as
the accidents considered in the existing safety analyses, creates a possible accident of a
different type.
In answering this question, the first step is to determine the types of accidents evaluated
in the existing safety analyses. The types of credible accidents that the change could
create can then be identified and listed. Evaluating the differences between the two lists
will determine the answer to the question. The accidents evaluated in the existing safety
analyses are generally chosen to be bounding for a broad class of credible accidents.
Thus, comparison of a new accident to the existing analyses may require referral to the
underlying hazard analyses.
6. Could the proposed change create the possibility of a malfunction of equipment
important to safety of a different type than any previously evaluated in the facility’s
existing safety analyses?
To answer this question, the types of failure modes of equipment important to safety that
have been previously evaluated in the existing safety analyses and that would be affected
by the change are identified. Then the types of failure modes that the change could create
need to be identified. Comparing the two lists can provide an answer to the question. An
example of a change that might create a malfunction of a different type is the relocation
of equipment so that it becomes susceptible to flooding; another example is the
replacement of a mechanical control system with a digital control system that could fail in
a different mode.
7. Does the proposed change reduce the margin of safety?
This section deals with margins of safety related to DOE-approved hazard control
documents. These controls may be technical safety requirements (TSRs), or they may be
in another form, as permitted in Section 830.205 for certain environmental restoration
activities.
For purposes of performing the USQ determination, a margin of safety is defined by the
range between two conditions. The first is the most adverse condition estimated or
calculated in safety analyses to occur from an operational upset or family of related
upsets. The second condition is the worst-case value known to be safe, from an
engineering perspective. This value would be expected to be related to the condition at
which some accident prevention or mitigation action must be taken in response to the
upset or accident, as required by a DOE-approved TSR, not the actual predicted failure
point of some component.
CANCELE
D
Appendix A DOE G 424.1-1
Page A-6 10-24-01
Hazard control documents set forth the minimum acceptable limits for operation under
normal and specified failure conditions; they ensure that the available safety equipment
and operating conditions meet the assumptions in the existing safety analyses. They
distill those aspects of the safety analyses that are required to ensure the performance of
safety SSCs and personnel as relied on and defined in the safety analyses.
Section 17
The bases for a hazard control should define the margin of safety. If the bases of a hazard
control do not specifically identify a margin of safety, the DSA and other appropriate
safety basis documents should be reviewed to determine whether the proposed change,
test or experiment, or new information has or would result in a reduction in a margin of
safety. The judgment on whether the margin is reduced should be based on physical
parameters or conditions that can be observed or calculated.
The safety margin is sometimes implicitly described. A margin of safety can depend on a
parameter other than one of the process variables. Therefore, the precise determination of
a numerical value associated with a change is not always possible. Implicit margins are,
for example, conditions for acceptance for a computer code, method, or industry-accepted
practice. It may be sufficient to determine only the direction of the margin change (that
is, increasing or decreasing) due to the proposed change.
Safety margins generally include worst-case assumptions of initial conditions,
conservative assumptions in computer modeling and codes, allowance for instrument drift
and system response time, redundancy and independence of components in safety trains,
and plant response during operating transient and accident conditions. A change that
affects initial conditions, a system response time, or some other parameter that can affect
the course of an accident analysis supporting the bases of hazard controls must be
evaluated to determine whether the change would reduce the margin of safety.
A.2 PERFORMING USQ DETERMINATIONS
In performing USQ determinations of a proposed change, documented justification for the USQ
determination should be developed. Consistent with the intent of Section 830.203, this
documentation should be complete in the sense that a qualified independent reviewer could draw
the same conclusion.
The importance of the documentation is emphasized by the fact that experience and engineering
knowledge, rather than models and experimental data, are frequently relied on to make the USQ
determination. Since an important goal of the USQ determination is to demonstrate that the
safety basis is being maintained, the items considered by the evaluator must be clearly stated.
Documentation of the effects considered will enable the independent reviewers to assess the
adequacy of the USQ determination and its conclusions. To provide an example of appropriate
documentation, a USQ determination worksheet is provided below.
CANCELE
D
DOE G 424.1-1 Appendix A
10-24-01 Page A-7
A.3 EXAMPLE USQ DETERMINATION WORKSHEET
USQ Determination Number: Revision No.
Facility Change Number: Revision No.
Facility Change Title:
INTRODUCTION
1. Description of the aspects of the change being evaluated and its expected effects.
2. Identification of parameters and structures, systems, and components (SSCs) affected by
the change.
3. Identification of the SSC failure modes associated with the change.
4. References to the location of information used for the USQ determination.
PART I: IMPACT ON THE ACCIDENTS EVALUATED AS THE SAFETY BASIS
1. Identify the design basis or evaluation basis accidents reviewed for potential impact by
the change.
2. Discuss how the parameters and SSCs affected by the change affect the consequences of
these accidents.
Section 18
3. Identify the design basis or evaluation basis accidents, if any, for which failure modes
associated with the change can be an initiating event.
4. Discuss the impact of the change on the probability of occurrence of the design basis or
evaluation basis accidents identified in item 3 of this part.
5. Identify the equipment important to safety affected by the change.
6. Discuss the impact of the change and/or the failure modes on the probability of failure of
the SSCs identified.
7. Discuss the impact of the change on the performance of the SSCs.
CANCELE
D
Appendix A DOE G 424.1-1
Page A-8 10-24-01
SUMMARY: PART I
Yes No
Based on item 2 above, could the change increase the consequences of a
design basis or evaluation basis accident?
Based on item 4 above, could the change increase the probability of a design
basis or evaluation basis accident?
Based on item 6 above, could the change increase the probability of a failure of
equipment important to safety?
Based on item 7 above, could the change degrade the performance of
equipment important to safety below that assumed in the design basis or
evaluation basis analysis?
If the answer to any of the above questions is “yes,” the change represents a USQ.
PART II: POTENTIAL FOR CREATION OF A NEW TYPE
OF UNANALYZED EVENT
1. Based on Part I, assess the impact of the change or the failure modes or both associated
with the change to determine whether the impact has modified the facility response to the
point where the change can be considered a new type of event. Discuss the basis for this
determination.
2. Determine whether the failure modes of equipment important to safety associated with
the change represent a new unanalyzed type of malfunction. Discuss the basis for this
determination.
SUMMARY: PART II
Yes No
Based on 1 and 2 above, could the change create the potential for a new type of
unanalyzed event or a new type of malfunction?
If the answer is “yes,” the change represents a USQ.
CANCELE
D
DOE G 424.1-1 Appendix A
10-24-01 Page A-9
PART III: IMPACT ON THE MARGIN OF SAFETY
1. Based on the results identified in Part I, discuss the impact of the consequences on the
protective barriers against release.
2. Identify how the protective barriers against release, if any, are directly affected by the
change or a failure mode of the change.
3. Discuss the impact of the change on the design limits for the protective barriers against
release identified above.
4. Identify the margins of safety related to this change.
SUMMARY: PART III
Yes No
Based on 1 above, could the consequences of the design or evaluation basis
accidents increase?
Based on 2, 3, and 4 above, could the change reduce the margin of safety
provided for the protective barriers?
Based on 4 above, could the change reduce other margins of that are not
related to the barriers?
PART IV: USQ DETERMINATION CONCLUSION
Based on the evaluation in Parts I, II, and III, the change—
Does not constitute an unreviewed safety question.
Does constitute an unreviewed safety question.
Preparer’s Signature Date
Independent Reviewer’s Signature Date
Approval Signature Date
CANCELE
D
Appendix A DOE G 424.1-1
Page A-10 10-24-01
This page intentionally left blank.
CANCELE
D
DOE G 424.1-1 Appendix B
10-24-01 Page B-1
UNREVIEWED SAFETY QUESTIONS LESSONS LEARNED
The following list of lessons learned has been developed from experience in applying the
unreviewed safety question (USQ) process.
B.1 TITLE
Section 19
The title of the process, “unreviewed safety questions,” may suggest that the process determines
the safety of changes. However, the USQ process is intended to determine the final approval
authority for a change [that is, the contractor or Department of Energy (DOE)].
The USQ process is not intended to replace or to serve instead of a safety analysis of the change.
The safety implications of a change should be reviewed, analyzed, understood, addressed,
determined to be acceptable, and documented by the contractor separately from the USQ process.
Using the USQ process instead of the safety analysis complicates the USQ process. Further, such
a usage is inappropriate because the seven questions to be answered in the USQ determination
are not geared toward understanding whether the change is safe but rather if any of the
probability or consequence risk factors may have increased beyond what has been accepted
previously by DOE and hence if the existing safety controls remain adequate. The change should
already be known to be safe before it enters the USQ process. The USQ process determines if
final approval by the contractor is sufficient or DOE review and approval are required. DOE
wants to review and approve those changes that involve a USQ (that is, when the USQ
determination is positive) to verify that the safety controls are adequate to provide an acceptable
level of safety to the public and workers. The existence of a positive USQ determination does
not mean that the change is unsafe, but only that DOE must take the final approval action.
B.2 IDENTIFYING POTENTIALLY INADEQUATE SAFETY ANALYSES
When an employee identifies a potentially inadequate safety analyses, the facility management is
allowed a reasonable time prior to notifying DOE to confirm the reasonableness of the potential
for having an inadequate safety analysis. This time should be on the order of hours, up to several
days, but not a matter of weeks, or months.
B.3 REPORTING POTENTIAL INADEQUACIES IN SAFETY ANALYSES
After the potential for having inadequate safety analyses has been confirmed, 10 CFR 830.203
requires four special actions to be taken. One of those actions is to notify DOE of the situation.
The current DOE reporting system (DOE O 232.1A and the associated Manual, DOE M
232.1-1A) require that a potential degradation of the safety basis be categorized and reported as
an “off-normal” condition. The Occurrence Reporting and Processing System (ORPS) may be
used for this notification if the report explicitly states that the situation involves a “potential USQ
involving a potentially inadequate safety analysis.”
CANCELE
D
Appendix B DOE G 424.1-1
Page B-2 10-24-01
Another action required for a potentially inadequate safety analysis is the preparation of a USQ
determination on the situation. In the event that the USQ determination is positive, the current
DOE reporting system requires that this condition be categorized and reported as an “unusual
occurrence.”
B.4 CONTROL OF HAZARDS DURING INSTALLATION
Hazards that may be involved during the installation of a modification should be addressed by
appropriate safety management programs (such as work planning and control, that includes job
hazard analysis or a similar process). As discussed in Section 2.1 of the Guide, the work
authorization system should include a step for consideration of possible USQ situations on the
facility safety basis, beyond the planned work.
Section 20
DOE relies on the contractor’s commitment to various safety management programs to address
the hazards involved in the actual installation of a modification for worker protection, not on the
USQ process. These programs include radiation protection, hazardous material protection, work
planning and control, Occupational Safety and Health Administration, ALARA (as low as
reasonably achievable), and lockout/tagout. One basic tenet of the USQ process is to assess the
potential change in probability and consequences risk factors that might be involved when
facility operations are resumed after the modification is implemented. However, sometimes a
modification might be only partially implemented because it is interrupted by unforeseen
circumstances. In such cases, the USQ documentation would need to be revisited to ensure that
it adequately addresses operation with the partially implemented configuration.
B.5 “DECLARING” A USQ TO EXIST
Section 830.203 assigns the contractor the basic responsibility to evaluate changes and determine
if a USQ exists, or is involved. If the result of the contractor’s USQ determination is positive, a
USQ exists.
DOE can declare that a USQ exists as part of its oversight responsibility of the USQ process. Such
a declaration might result from a disagreement with a contractor’s negative USQ determination or
might result from a condition for which the contractor has not done a USQ determination. When
DOE declares a USQ, it is because DOE believes it should be involved in the review and
approval of the situation to fulfill its responsibilities.
B.6 SUBMITTALS TO DOE
At some sites, the completed USQ determination form is submitted routinely to DOE for
approval. This practice should be reconsidered because it is not required and can shift the focus
of the DOE review from the safety characteristics of the change to how well the USQ
determination was prepared. For a potentially inadequate safety analysis, the rule requires that an
evaluation of the safety of the situation (not the USQ determination) be submitted prior to
removing any restrictions.
CANCELE
D
DOE G 424.1-1 Appendix B
10-24-01 Page B-3
The USQ process does not encompass all situations for which the contractor may need to request an
amendment to the safety basis of a facility. For example, a change to the hazard categorization
level for a facility requires DOE approval, but should not be addressed by the USQ process.
Some contractors have developed a formalized process for requesting amendments to the safety
basis.
At some facilities, the USQ process is being used virtually every time there is need to request an
amendment to the safety basis, regardless of whether or not a change to the facility or procedures
is involved. In some situations, the USQ process is inappropriate. A formalized procedure that
defines the content of the submittal to DOE requesting an amendment to the facility safety basis
could supplement the USQ process (regarding positive USQ determinations). Such a procedure
would also support other situations that do not involve the USQ process. Such a procedure might
outline the expected content as including items such as (1) an introductory summary of the
purpose of the letter and its contents, (2) a description of the situation that generated the need for
action, (3) alternative actions considered, (4) a description of the selected action, (5) engineering
technical considerations, (6) safety implications of the action, including the results of the USQ
process when applicable, (7) programmatic implications, (8) budgetary considerations,
(9) schedule considerations, and (10) basis on which the contractor believes that DOE should
approve the action.
Section 21
B.7 NEED FOR USQ DETERMINATIONS FOR TSR CHANGES
Section 830.205 requires that changes to the technical safety requirements (TSRs) be submitted
to DOE for review and approval. Changes to the TSRs could involve the need either to modify
an existing TSR or to add a new TSR. If it is known that a proposed change only involves a TSR
change, it is not required to go through the USQ determination to determine if DOE approval is
also required by 830.203. Similarly, if a change involves a TSR change, calling the change a
positive USQ determination just because it requires DOE approval would be inappropriate.
However, while performing a USQ determination for TSR changes is not required, it may be
desirable. When the TSR change is submitted to DOE for review and approval, the contractor
should include appropriate information to support the contractor's position that the change should
be approved (that is, the contractor should include the basis for the proposed change). Such
supporting information might include some of the same considerations that would be addressed
in a USQ determination.
B.8 TENANT/LANDLORD RELATIONSHIPS
In some cases a “tenant/landlord” relationship exists, such as for research and development
activities or other operations being performed by one organizational unit at a nuclear facility that
is operated or managed by a different organizational unit. In these cases, the recommended
approach to allow flexibility for the tenant’s activities and still protect the safety basis via the
USQ process is to: (1) ensure that a hazards analysis (or other appropriate safety analysis) exists
for each tenant activity such that the collective hazards analyses for all tenant activities are
encompassed by the facility safety basis, (2) require that the tenant review any changes in the
CANCELE
D
Appendix B DOE G 424.1-1
Page B-4 10-24-01
activities being considered against the corresponding hazards analysis , and then (3) if the current
hazards analysis does not envelope the change, require that the USQ process be entered more
formally.
There is a potential conflict between requiring that all changes within a facility be considered
within a formal change control process and allowing sufficient flexibility that researchers and
other tenants may conduct their activities without undue restrictions that might stifle the desired
creativity. The objective should be to impose the formality necessary to ensure that all activities
are conducted safely within the DOE-approved safety basis for the facility without applying any
unnecessary restrictions on the activities. Having the tenant take an active role in development of
an appropriate envelope for the activities within the hazards analysis can promote ownership.
This participation can also enhance safety responsibility without limiting the activities.
B.9 GRADED APPROACH
The graded approach is applied to the USQ process only indirectly. During the hazards analysis
and safety analysis processes, equipment is classified as safety class, safety significant, “other”
safety, or nonsafety. Once these classifications are established, they are used to indicate how
much effort should be applied. However, no steps of the USQ process can be eliminated based
on such grading.
Section 22
In some situations, attempts to apply the graded approach to the USQ process have resulted in
inadequate USQ determinations. For example, some contractors have applied the graded
approach to the change control processes in a manner that does not require the application of
formal change controls unless the change involves equipment, procedures, or operations
important to safety. Caution needs to be applied in such a situation to ensure that this approach
does not prevent changes from being considered by the USQ process, which is a subset of change
control. The only application of the graded approach to the USQ process is indirect. The graded
approach may give a rough indication of how much justification or basis information should be
provided when explaining the answers to each of the seven USQ determination criteria. More
elaborate and thorough basis information would be expected for changes to safety equipment
than for nonsafety equipment. In any case, the justification for the answers to the USQ
determination criteria needs to be defensible.
B.10 UNIFIED AND CONSOLIDATED PROCEDURES
Contractors should consider the desirability of requiring that each nuclear facility at the site
adhere to a single sitewide USQ procedure and sitewide USQ training/qualification requirements.
Facility-specific considerations, such as identifying the safety basis documents, could be
addressed by appendices to the sitewide procedure. At some sites, each nuclear facility uses a
different USQ procedure, leading to inconsistencies and misapplications. One DOE field office
assessment found that a root cause of USQ problems was the lack of a common procedure and
common USQ training. A single sitewide USQ procedure could improve the quality of the USQ
process by taking advantage of the best aspects of each of the different facility procedures. Using
CANCELE
D
DOE G 424.1-1 Appendix B
10-24-01 Page B-5
the same USQ forms for screens and USQ determinations and using the same training and
qualification requirements can help develop a high-quality USQ process across the site.
B.11 USQ SCREENING
USQ screening is intended to be a simple go/no-go decision-making step, without evaluative
consideration. When appropriately streamlined, this step in the USQ process can often be
completed in a matter of minutes. Screening to determine whether an SSC is described in the
safety analyses (safety basis) should consider only whether the equipment is identified anywhere
in the safety basis. Screening criteria should not be based on whether the SSC is formally
classified as a safety SSC (that is safety class or safety significant), is taken credit for in the
safety analysis (or accident analysis) chapter of the safety basis document, nor whether the
particular characteristic(s) of the SSC to be changed are taken credit for.
The basic intent of screening is to eliminate unnecessary time and effort being spent performing a
USQ determination if there is no possible way that the change could impact the safety basis and
involve a USQ. Conversely, screening criteria must make certain that changes which could
possibly involve a USQ are “screened in” and hence a USQ determination is performed. The
USQ screening criteria center on the question of whether the item to be changed is described in
the safety basis.
Section 23
An example of an inappropriate, highly evaluative, screening criterion is: “Does this change
significantly adversely impact the ability of an SSC described in the safety basis to perform its
safety functions?” Such a criterion encompasses four separate considerations: (1) determining if
the SSC is identified in the safety basis, (2) finding out what the safety functions are for the SSC,
which might not be stated very clearly or completely, (3) evaluating if the impact of this change
could adversely affect the capability to perform a safety function, and (4) evaluating if the impact
could be significant. All but the first consideration are evaluative considerations that depend
strongly on which individual does the USQ screen. These types of evaluative considerations
should be in the domain of the USQ determination, not part of the simple screening step.
If someone were to subdivide the safety basis documents into those parts that are “descriptive”
and those parts that are important to safety, the results would be highly subjective. Limiting the
performance of USQ determinations to only those SSCs taken credit for in the safety analysis
chapter, or even further to only those characteristics of SSCs taken credit for can lead to serious
problems, including bypassing the USQ determination and thereby, unknowingly exceeding the
bounds of the safety basis. Similarly, limiting screening to safety SSCs (that is, those identified
as safety class or safety significant) before a USQ determination is done is inappropriate due to
the potential for unrecognized direct or indirect interactions.
B.12 DOE INVOLVEMENT IN THE USQ DETERMINATION
The contractor should make every effort to complete its USQ determinations without DOE
involvement. DOE has charged the contractor with performing the USQ process to determine if
CANCELE
D
Appendix B DOE G 424.1-1
Page B-6 10-24-01
contractor approval is sufficient. At times, there will be borderline cases or “gray areas” where
engineering judgment will play a large role in the determination. The contractor should complete
the determination with sufficient justification to defend the conclusion, despite whether the final
determination is positive or negative. While DOE and the contractor are “partners” in many
senses, when it comes to its nuclear safety regulatory and oversight responsibilities, DOE must
maintain an appropriate degree of independence from the contractor’s activities.
B.13 USQS AND CRITICALITY SAFETY EVALUATIONS
All proposed new or changed processes involving criticality safety, including those in an
experimental facility, are required to undergo a USQ review by the Nuclear Safety Management
rule. When the USQ determination is positive, indicating the need for DOE review and approval
of the change, the safety analyses and controls associated with the approved action become part
of the safety basis for the facility. Any changes necessary to the DSA and TSR documents as a
result of the change should be incorporated at the next annual update. The results of the USQ
determination define the need for DOE approvals of the supporting criticality safety evaluations
and explicit updates of the DSA and TSRs.
CANCELE
D
DOE G 424.1-1
Foreword
Contents
1. Introduction
2. Application
3. Implementation Guidance
Appendix A, Unreviewed Safety Question Determination
Appendix B, Unreviewed Safety Questions Lessons Learned