DOE G 415.1-1, Information Technology Project Execution Model Guide
Functional areas: Information Technology, Project Management
The guide was developed in support of DOE O 415.1 to assist IT Program and Project Managers in effectively managing and applying sound project management to IT. Does not cancel/supersede other directives.
Version history and related documents
Related documents
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
DOE G 415.1-1
7-17-2014
INFORMATION TECHNOLOGY
PROJECT EXECUTION MODEL GUIDE
[This Guide describes acceptable, but not mandatory means for complying with requirements.
Guides are not requirements documents and are not to be construed as requirements in any audit
or appraisal for compliance with associated rule or directives.]
U.S. Department of Energy
Office of the Chief Information Officer
NOT
MEASUREMENT
SENSITIVE
DOE G 415.1-1 i (and ii)
7-17-2014
FOREWORD
This Department of Energy (DOE) Guide is approved for use by all Department of Energy
(DOE), including National Nuclear Security Administration (NNSA), organizations.
This Guide was developed in support of DOE O 415.1, Information Technology Project
Management, dated 12-03-2012. This Guide assists IT Program and Project Managers in
effectively managing and applying sound project management to IT projects subject to that
order. This Guide leverages key project management and information technology concepts from
the Federal Government and industry, focused on guiding the activities of key project
stakeholders throughout a standard project management lifecycle.
DOE Guides are part of the DOE Directives System and are issued to provide supplemental
information regarding the Department’s expectation of its requirements as contained in rules,
Orders, Notices, and regulatory standards. This Guide does not establish or invoke any new
requirements.
Beneficial comments (recommendations, additions, deletions, and any pertinent data) that may
improve this document should be sent to:
Denise Hill
IM-20
U.S. Department of Energy
Washington, D.C. 20585
Phone (202) 586-5848
DOE G 415.1-1 iii
7-17-2014
Contents
FOREWORD ................................................................................................................................... i
1 INTRODUCTION................................................................................................................. 1
1.1 Purpose ............................................................................................................................. 1
1.2 Background ...................................................................................................................... 1
1.3 Applicability and Exclusions ........................................................................................... 2
2 INFORMATION TECHNOLOGY PROJECT EXECUTION MODEL ........................ 3
2.1 Methodology .................................................................................................................... 3
2.1.1 PMBOK® Guide ....................................................................................................... 3
2.1.2 ITIL v3 ...................................................................................................................... 3
2.1.3 System Engineering .................................................................................................. 4
2.1.4 Federal Organizations ............................................................................................... 4
2.1.5 Government wide or Departmental Requirements ................................................... 4
2.2 IT PEM Framework ......................................................................................................... 6
2.3 IT PEM Elements ............................................................................................................. 7
Section 2
2.3.1 Lifecycle Phases & Stages ........................................................................................ 8
2.3.2 Critical Decision (CD) ............................................................................................ 13
2.3.3 Deliverables and CD Packages ............................................................................... 14
2.3.4 Project Stakeholders................................................................................................ 15
2.4 Quality Management ...................................................................................................... 19
2.4.1 Critical Decision (CD) Review ............................................................................... 19
2.4.2 Independent Reviews (IR) ...................................................................................... 20
2.4.3 Quarterly Project Reviews (QPR) ........................................................................... 21
2.5 Risk Management ........................................................................................................... 21
2.6 Change Control Management......................................................................................... 24
3 KEY PROJECT MANAGEMENT PRINCIPLES .......................................................... 26
3.1 Project Complexity Level (PCL).................................................................................... 26
3.2 Tailoring ......................................................................................................................... 28
3.3 Agile or Modular Development ..................................................................................... 29
3.3.1 Agile or Modular Development Using the IT PEM................................................ 30
4 TEMPLATES & ARTIFACTS ......................................................................................... 33
4.1 Project Management Templates and Artifacts ............................................................... 33
5 IT PEM Framework at a Glance ....................................................................................... 35
iv DOE G 415.1-1
7-17-2014
6 INFORMATION TECHNOLOGY PROJECT MODEL BY PHASE .......................... 37
6.1 Pre-Project Phase: .......................................................................................................... 37
6.2 Initiation Phase: .............................................................................................................. 38
6.3 Planning Phase: .............................................................................................................. 38
6.4 Execution Phase: ............................................................................................................ 39
6.5 Production Phase ............................................................................................................ 40
APPENDIX A ................................................................................................................................. 1
APPENDIX B ................................................................................................................................. 1
GLOSSARY ................................................................................................................................... 1
APPENDIX C ................................................................................................................................. 1
Section 3
ACRONYMS .................................................................................................................................. 1
APPENDIX D ................................................................................................................................. 1
REFERENCES ............................................................................................................................... 1
APPENDIX E ................................................................................................................................. 1
DESCRIPTION of PROJECT ARTIFACTS.................................................................................. 1
DOE G 415.1-1 v (and vi)
7-17-2014
Figures
Figure 1: IT PEM Framework Alignment with Other Methodologies ........................................... 5
Figure 2: IT PEM Framework in a Program Management Environment ...................................... 6
Figure 3: IT PEM Elements ............................................................................................................ 7
Figure 4: Deliverables, CD Package, and CD Review ................................................................ 14
Figure 5: Project Stakeholders and their Communication Paths ................................................. 17
Figure 6: IT PEM Monitoring & Controlling............................................................................... 18
Figure 7: Critical Decision Review Process ................................................................................ 20
Figure 8: Probability and Impact Analysis (Sample Only) .......................................................... 22
Figure 9: Change Control Management Process ......................................................................... 25
Figure 10: Decision Tree for Determining PCL & IT PEM Applicability ................................... 27
Figure 11: IT PEM Tailoring ....................................................................................................... 28
Figure 12: IT PEM Agile & Modular Development ..................................................................... 30
Figure 13: CD-2 & CD-3 Combined ............................................................................................ 31
Figure 14: CD-2 and CD-3 applied for each module or iteration ............................................... 32
Figure 15: Pre-Project Phase ....................................................................................................... 37
Figure 16: Initiation Phase Artifact Workflow ............................................................................. 38
Figure 17: Planning Phase Artifact Workflow ............................................................................. 38
Figure 18: Execution Phase Artifact Workflow (CD-2) ............................................................... 39
Figure 19: Execution Phase Artifact Workflow (CD-3) ............................................................... 39
Figure 20: Production Phase Artifact Workflow .......................................................................... 40
Tables
Section 4
Table 1: Lifecycle Phases & Stages ................................................................................................ 8
Table 2: IT PEM Critical Decision (CD) ..................................................................................... 13
Table 3: Roles and Responsibilities .............................................................................................. 15
Table 4: Independent Reviews for Critical Decisions .................................................................. 21
Table 5: Risk Management ........................................................................................................... 22
Table 6: Change Control Management ........................................................................................ 24
Table 7: Determining Project Complexity Level .......................................................................... 26
Table 8: Illustration of the “IT PEM Artifact Matrix” ................................................................. 34
Table 9: IT PEM Framework at a Glance .................................................................................... 36
DOE G 415.1-1 1
7-17-2014
1 INTRODUCTION
1.1 Purpose
The purpose of the Information Technology (IT) Project Execution Model (PEM) Guide is to
provide U.S. Department of Energy (DOE) IT Program and Project Managers (PM) with
guidance that may be useful to them in effectively and efficiently implementing the requirements
of DOE Order (O) 415.1, Information Technology Project Management, dated December 3,
2012. Specifically, this Guide provides a suggested formal, structured, and integrated standard
approach to managing DOE IT projects and programs.
This Guide describes acceptable, non-mandatory guidelines for meeting requirements contained
in DOE regulations and directives. This Guide provides flexible guidance that is intended to help
DOE organizations effectively manage and apply sound project management practices to IT
projects and initiatives.
1.2 Background
DOE O 415.1 was developed to establish common IT project management principles which
would help ensure that IT projects are delivered within the defined performance baseline, cost,
and schedule and fully meet mission performance, safety, safeguards, and security standards in
alignment with Section 5123 of Public Law (P.L.) 104-106, Performance and Results Based
Management. Additionally, DOE O 415.1 requires that all IT projects apply a formal and
structured project management approach that is acceptable to the sponsoring/funding
organization.
This Guide provides a suggested formal and methodical progression of best practices for IT
project management which should:
• Assist in delivering consistent IT projects within defined scope, schedule and cost
baselines;
• Help to establish accountability and reporting among the sponsor, project staff and
various project key stakeholders;
• Assist in facilitating cross-functional and cross-organizational communication,
coordination, and collaboration;
• Assist in providing overarching accountability and oversight of an IT program or project,
ensuring that it meets mission expectations from a program management perspective;
• Assist in integrating systems engineering activities with cybersecurity governance, IT
governance and management practices that are scalable and repeatable from a project
management perspective; and
• Address Digital Government Strategy and Clinger-Cohen Requirements
Section 5
2 DOE G 415.1-1
7-17-2014
Note: The terms [Program] and [Program Management] are utilized throughout this guide
to mean, “A group of related projects managed in a coordinated way to obtain benefits and
control not available from managing them individually.1”
1.3 Applicability and Exclusions
This Guide applies to all DOE organizational elements, including NNSA organizational
elements, with IT projects that are subject to DOE O 415.1. For simplicity, “DOE” as used
throughout this Guide, includes all DOE organizational elements. IT projects covered by DOE O
415.1 include projects:
• With a Total Project Cost (TPC) equal to or more than $25 Million (M);
• With an impact on more than one DOE Element; or
• As determined by the Under Secretary or Head of Element based on mission, priorities,
risk management or national interest.
DOE O 415.1 requires that all IT projects that do not meet the scope of the order are encouraged
to use the project management principles and guidelines, as applicable to the scale of the project
and as required/requested by the sponsoring/funding organization.
The Project Management Institute (PMI) Project Management Body of Knowledge (PMBOK®
Guide) – Fifth Edition, defines a project as, “A temporary endeavor undertaken to create a
unique product, service, or result1”. The temporary nature of projects indicates a definite
beginning and end. The end is reached when the project’s objectives have been achieved or when
the project is terminated because its objectives will not or cannot be met, or when the need for
the project no longer exists. Furthermore, the PMBOK® defines project management as, “the
application of knowledge, skills, tools, and techniques to project activities to meet the project
requirements1”.
This Guide provides a best practice project management approach that allows for flexibility to
accommodate the unique circumstances (e.g., size, cost, duration, complexity, acquisition
strategy, systems engineering methodology, etc.) of any IT program or project. The
sponsoring/funding organization of the IT project has the flexibility to determine the appropriate
rigor of project management application (i.e., application of this Guide) and apply accordingly.
Note: DOE O 415.1 Applicability & Exclusions criteria for projects are different than the criteria
used for CPIC investments. Project teams are advised to reference the latest Capital Planning and
Investment Control (CPIC) documentation (i.e. DOE Guide to IT Capital Planning and Investment
Control) or contact CPIC team at DOE.CPICMailbox@hq.doe.gov for specific updates to the
investment levels, cost thresholds, and specific DOE and Office of Management and Budget
requirements.
1 A Guide to the Project Management Body of Knowledge (PMBOK® Guide)-Fifth Edition
mailto:DOE.CPICMailbox@hq.doe.gov
DOE G 415.1-1 3
7-17-2014
2 INFORMATION TECHNOLOGY PROJECT EXECUTION MODEL
This Guide delivers the guidance to implement the requirements for DOE as defined in DOE O
415.1. It provides a standard approach to manage DOE projects and programs by setting the
foundation for a common project management language, consistency in project execution, and
continuous improvement. Through standardization we can improve project and program
understanding, communication, reporting, measurability, and most important, proper and timely
decision making across the DOE. This guide integrates project management, information
technology, and governance processes into a common framework known as the “IT PEM.”
Section 6
2.1 Methodology
The IT PEM framework leverages methodologies and principles from the following areas:
• PMI and its PMBOK® Guide-Fifth Edition2
• Information Technology Infrastructure Library (ITIL) v3
• DOE Systems Engineering Methodology (SEM)
• Federal Organizations (Internal & External to DOE)
• Government wide or Departmental Directives and Policies
2.1.1 PMBOK® Guide1
The IT PEM framework incorporates project management guidelines in accordance with PMI’s
PMBOK® Guide2. Similar to the PMBOK® Guide’s “Process Groups”, the IT PEM lifecycle
phases are seldom discrete or one-time events. Instead, the IT PEM lifecycle phases are
overlapping activities that occur throughout the project. The output of one activity generally
becomes an input to another or a project deliverable. Section 2.3.1: Lifecycle Phases & Stages in
this guide describes the IT PEM lifecycle phases in greater detail.
To support specific DOE and IT lifecycle requisites, the IT PEM emphasizes a “Pre-Project”
and a “Production” phase which align to portions of the PMBOK® Guide’s Initiating, Executing,
and Closing Process Groups. Figure 1: IT PEM Framework Alignment with Other
Methodologies provides a high-level illustration of the IT PEM lifecycle phases and its
alignment to the PMBOK® process groups.
2.1.2 ITIL v3
The IT PEM references ITIL v3 to align with an IT industry standard that is customer focused,
promotes measurability, and continuous improvement of its processes and procedures. The ITIL
complements the IT PEM by providing an IT focused approach that may not be attained by a
traditional project management methodology alone. "ITIL provides guidance on the provision of
quality services and project management provides guidance on planning, organizing, and
executing projects. Their similarities drive synergy in the delivery of projects and services by IT
2 A Guide to the Project Management Body of Knowledge (PMBOK® Guide)-Fifth Edition
4 DOE G 415.1-1
7-17-2014
to the business -- and the greatest value is not realized by one or the other process, but by the
integration of the whole.3"
2.1.3 System Engineering
The IT PEM framework emphasizes key system engineering principles from the DOE Systems
Engineering Methodology (SEM) Version 3, dated September 2002. The SEM was derived from
the principles and standards advocated by information management industry leaders, such as the
Institute of Electrical and Electronics Engineers (IEEE) and the Carnegie Mellon Software
Engineering Institute (SEI). SEM principles such as guidelines on “Project Size” and the SEM
“Information Systems Lifecycle Stages” are examples of principles leveraged from the SEM
methodology. Figure 1: IT PEM Framework Alignment with Other Methodologies provides a
high-level illustration of the IT PEM lifecycle phases and its alignment with the SEM Lifecycle
Stages.
2.1.4 Federal Organizations
The IT PEM leverages various IT project management methodologies from internal
organizations such as the NNSA, the Office of Environmental Management (EM), and external
organizations such as the Department of Health and Human Services (HHS) and the Executive
Office of the President (EOP).
2.1.5 Government wide or Departmental Requirements
The IT PEM integrates into its methodology Government-wide and/or Department requirements
for information management. In addition to supporting DOE O 415.1, the PEM strives to
capture and support essential deliverables from CPIC, Configuration Management (CM),
Cybersecurity, Enterprise Architecture (EA), Quality Assurance (QA), Records Management
(RM), Safety and Safeguards (S&S), and System Engineering.
Section 7
3 Rivard, E., & Smith, K. (2010, November 18) Integrating ITIL with IT Project Management Improves Both. IT
Business Edge. Retrieved from: http://www.itswatch.com.
DOE G 415.1-1 5
7-17-2014
Figure 1: IT PEM Framework Alignment with Other Methodologies
Note: The term [Essential Artifact] is utilized throughout this guide to mean Project management
artifacts essential to maintain and/or support federal approaches towards strategy, business,
security, and technology.
Note: The term [Deliverable] is utilized throughout this guide to mean both tangible and intangible
activities and artifacts.
Note: The term [Monitoring & Controlling] is utilized throughout this guide to imply the essential
processes and procedures to manage project scope, schedule, cost, and quality.
6 DOE G 415.1-1
7-17-2014
2.2 IT PEM Framework
The IT PEM framework provides for a formal, structured, integrated, and standard approach to
managing DOE IT projects and programs while allowing for flexibility to meet the unique needs,
principles, and environmental factors of each DOE Element. DOE Elements are first-tier
organizations at Headquarters and in the field who may apply the IT PEM framework for their
program and project management endeavors. Figure 2: IT PEM Framework in a Program
Management Environment illustrates the IT PEM framework in a program management
environment. The illustration depicts how a standard framework (such as the IT PEM) can
provide the methodology and structure to more systematically monitor and control the alignment
and synchronization of multiple projects across the DOE.
Figure 2: IT PEM Framework in a Program Management Environment
DOE G 415.1-1 7
7-17-2014
2.3 IT PEM Elements
The IT PEM framework is comprised of four elements which serve as its foundation and
infrastructure. The four IT PEM elements are composed of:
• Lifecycle Phases & Stages
• Critical Decision (CD)
• Deliverables & CD Packages
• Project Stakeholders
These elements work in concert to deliver a standard that promotes uniformity, measurability,
lessons learned, and continuous process improvement. Figure 3: IT PEM Elements provides a
high-level illustration of all four elements within the IT PEM framework.
Figure 3: IT PEM Elements
8 DOE G 415.1-1
7-17-2014
2.3.1 Lifecycle Phases & Stages
Lifecycle phases and stages are distinct periods in a project’s lifespan. Each period is comprised
of tangible and intangible deliverables that upon fulfilling will help advance the project closer
towards completion. Applying these distinct periods helps by providing a standard structure for
DOE projects to follow and improve deliverable compliance, better alignment and
synchronization with other projects, and improved (standardized) project reporting.
The IT PEM utilizes one preliminary “Pre-Project Phase” and four official project management
phases which include Initiation, Planning, Execution, and Production. In addition, the IT PEM
incorporates six project management stages which support an IT project management lifecycle
development. Monitoring and controlling is conducted at all IT PEM lifecycle phases and stages.
Section 3.0: Monitoring and Controlling in this guide describes the Monitoring and Controlling
processes applied in the IT PEM framework. Table 1: Lifecycle Phases & Stages describes the
IT PEM lifecycle phases and their appropriate stages in greater detail.
Table 1: Lifecycle Phases & Stages
Lifecycle Phases Activity
0) Pre-Project Phase
Section 8
An initial Pre-Project Phase is used in the IT PEM framework to
ensure that critical pre-project tasks have been considered and/or
fulfilled prior to advancing to the Initiation Phase and committing
further federal and contractor resources. The Pre-Project Phase is
typically championed by the business organization (or the designated
business owner) who is requesting a business need and/or objectives.
An approved Business Case or appropriate sponsor approval to initiate
a new project becomes the major milestone in the Pre-Project Phase.
The following list outlines some essential tasks which should be
considered and fulfilled during the Pre-Project Phase.
• Obtain sponsorship
• Identify strategic alignment
• Consider shared services
• Perform high level alternatives analysis
• Complete & Submit “Pre-project Architecture Worksheet”
• Perform Rough Order of Magnitude (ROM) analysis
• Perform cost benefit analysis
• Determine Project Complexity Level (PCL)
• Determine program or portfolio management considerations
• Develop the Business Case
• Submit Business Case
• Obtain Business Case approval
• Assign project to appropriate Federal Sponsor
• Federal Sponsor assigns Federal Project Manager
1) Initiation Phase At the Initiation Phase, the approved Business Case becomes an input
and used by the project manager to complete such tasks and
DOE G 415.1-1 9
7-17-2014
Lifecycle Phases Activity
deliverables as identifying initial scope and development of the
Project Charter. An initial risk assessment should be conducted and
included with the Project Charter. Security requirements and risks
should be determined and captured in the requirements and initial risk
assessment sections of the Project Charter (It is recommended that the
Project Manager seek the appropriate documentation and guidance
from the respective security organization).At the end of the Initiation
Phase, a sponsor approved Project Charter will authorize the project
and project manager. The following bullets highlight some of the
major tasks performed during the Initiation Phase:
• Develop the Project Charter
o Business Needs & Objectives
o Initial Scope (Requirements)
o Stakeholder Register
o Milestone Schedule
o Assumptions & Constraints
o Initial Risk Assessment
o Initial Cost Estimate
• Submit Project Charter
• Project Charter Signed/Approved
• Commit initial financial resources
• Facilitate Quarterly Project Review (As Required)
• Independent Review (Optional)
• Conduct CD-0 Review
2) Planning Phase
At the Planning Phase, the project stakeholders identified at the
Initiation Phase are brought together by the project or program
manager to support in defining requirements, developing the project
plan, and to baseline project Scope, Schedule, and Cost. The project’s
Business Owner supports the project manager and team in many facets
of the Planning Phase such as helping to capture business and
functional requirements, facilitating communication with business
stakeholders, and in determining performance metrics and success
criteria. The bullets highlight some of the major tasks performed
during the Planning Phase:
• Collect Business & Functional Requirements
• Develop Project Management Plan (PMP)
o Scope Management Plan
o WBS/Schedule Management Plan
o Cost Management Plan
o Communications Management Plan
o Change Control Management Plan
o Risk Management (Plan)
o Quality Assurance Plan
10 DOE G 415.1-1
7-17-2014
Lifecycle Phases Activity
o (Other as required for specific project)
Section 9
• Develop Cybersecurity Plan
• Develop Alternative Analysis
• Submit Project Management Plan
• Complete Enterprise Architecture Worksheet
• Obtain Chief Architect Approval
• Baseline Project Scope
• Baseline Cost Performance
• Baseline Project Schedule
• Define Performance Metrics
• Project Management Plan Approval
• Perform Change Control Management
• Perform Risk Management
• Facilitate Quarterly Project Review (As Required)
• Independent Review (Optional)
• Conduct CD-1 Review
3) Execution Phase:
The Execution Phase includes processes performed to complete the
activities (tasks, milestones, deliverables, and artifacts) defined in the
Planning Phase. Processes are performed to track, review, report, and
regulate project progress and performance. Changes to the baseline
plan (Scope, Schedule, and Cost) may require a formal change control
process as specified in the Change Control Plan or PMP.
The Design, Development, and Testing Stages are addressed during
the Execution Phase. These stages may be executed within a waterfall
or modular/agile approach. The three Execution Phase stages are
described:
Design Stage: The primary objective is to create a design that satisfies
the requirements gathered and agreed during the Planning Phase.
Questions move from the previous "what" type questions in the
Planning Phase to the "how" type questions. The end result is an
approved design of how the proposed solution is to be developed. The
bullets highlight some of the major tasks performed during the Design
Stage:
• Manage & Communicate Project Progress
(Reviews/Reports/Escalations)
• Define and Document System Requirements
• Perform System Design Review
• Design Approval
• Perform Change Management
• Perform Risk Management
• Update PM Documents (As Required)
DOE G 415.1-1 11
7-17-2014
Lifecycle Phases Activity
• Facilitate Quarterly Project Review (As Required)
• Independent Review (Optional)
• Conduct CD-2 Review
Development Stage: At this stage, procurement is executed and
developers begin to develop a prototype of the system, product, or
feature in a lab or limited production environment. The Project
Manager and project team rely on the Business Owner to help in
completing the (business) User Acceptance Test Plan and Training
Material by confirming user types, access/licensing, data security, and
other test and training logistics. The bullets highlight some of the
major tasks performed during the Design Stage:
• Manage & Communicate Project Progress
(Reviews/Reports/Escalations)
• Procure Hardware/Software/Human Resources
• Install /Develop System
• Complete Training Material
• Test Readiness Review & Acceptance
• Perform Change Management
• Perform Risk Management
• Update PM Documents (As Required)
Testing Stage: Begins after the system, product, or feature has been
developed. The test plans developed during the planning phase are
utilized to verify that the system, product, or feature being tested
meets the business requirements. The Project Manager and project
team rely on the Business Owner to help facilitate the communication
and coordination for the business user acceptance testing. The bullets
highlight some of the major tasks performed during the Testing Stage:
• Manage & Communicate Project Progress
(Reviews/Reports/Escalations)
• Test Prototype or Lab Environment
• Production Readiness Review & Acceptance
• Perform Change Management
• Perform Risk Management
• Update PM Documents (As Required)
• Facilitate Quarterly Project Review (As Required)
• Independent Review (Optional)
• Conduct CD-3 Review
Section 10
4) Production Phase
The Production Phase includes the Implementation, Closure, and
Maintenance Stages of the project. The three Production Phase stages
are described:
12 DOE G 415.1-1
7-17-2014
Lifecycle Phases Activity
Implementation Stage: In this stage, the system, product, or feature
is implemented in the production environment. Training is provided
to all end-users and a post implementation review is conducted with
the Sponsor to evaluate if the implementation fulfilled business
requirements and is ready for formal release. The bullets highlight
some of the major tasks performed during the Implementation Stage:
• Install or Implement in Production Environment
• Deliver User Training (Operation, Business, and End-User)
• Conduct Post Implementation Review
• Obtain Post Implementation Sponsor Acceptance
• Perform Change Management
• Perform Risk Management
• Update PM Documents (As Required)
• Facilitate Quarterly Project Review (As Required)
Closure Stage: In this stage the project is formally handed-off to
operations, business, and/or end-users. All procurement and project
management processes are closed. Project artifacts are archived.
Final project disposition and status is communicated to stakeholders.
The project team is released from the project. The bullets highlight
some of the major tasks performed during the Closure Stage:
• Formal hand-off to Operations, Business, or End-User
• Close PM Processes (Risk, Change Control, etc.)
• Close Procurement
• Archive PM Artifacts
• Communicate Project Closure
• Release Project Team
• Independent Review (Optional)
• Conduct CD-4 Review
Maintenance Stage: After the Closure Stage, an “Annual Operational
Analysis” is conducted to continuously collect system or product data
and monitor and control the system or product’s lifecycle status.
When determined that the system or product has reached the end of its
lifecycle (retirement), proper system disposition is conducted to
ensure that a system's components, data, software and hardware are
disposed of properly and according to organizational regulations.
Vital information is archived and maintained for future business or
system needs. The bullet below highlights the major task performed
during the Maintenance Stage:
• Perform Annual Operational Analysis
DOE G 415.1-1 13
7-17-2014
2.3.2 Critical Decision (CD)
Critical Decisions (CDs) are formal stage gates or transition points during a project’s lifecycle
where a set of required deliverables (CD Package) are evaluated by CD Approvers to ensure they
were properly and fully completed. Approval at a CD Review suggests that the project is both
prepared and adequately funded to enter the next phase or stage in the IT PEM lifecycle. Table
2: IT PEM Critical Decision (CD) describes the five CD Reviews used in the IT PEM
framework, its respective IT PEM phase, and its descriptive milestones.
Table 2: IT PEM Critical Decision (CD)
CD CD Title IT PEM
Phase Descriptive Milestones
CD-0 Approve Project
Charter Initiation • Project Charter Approved
• Initial Scope Identified
CD-1
Approve
Performance
Measurement
Baseline (PMB)
Planning • Project Management Plan Approved
• Project Baselined (Scope, Schedule, Cost)
CD-2 Approve Start of
Development Execution • Architecture or System Design Approved
• Approval to Begin Development Stage
CD-3 Approve Start of
Production Execution • Test Readiness Review Approved
• Operational Readiness Review Approved
Section 11
CD-4
Approve Project
Closure and Start of
Maintenance Stage
Production
• Post Implementation Review Approved by
Sponsor
• Formal Hand-Off to Operations, Business, or
End-User Completed
2.3.2.1 CD Approvers
CD Approvers should be identified and assigned by each individual project team and their
respective governance early in the project (preferably at Initiation Phase). The CD Approvers
should typically be familiar with the project, its deliverables, and its governance. In addition, the
CD Approvers should have a stake or interest in the success of the project and hold the
appropriate authority to influence financial, budget, and project governance decisions. The
ultimate goal of a CD Approver is to advance a project to its successive phase or stage.
A project may have one or more CD Approvers depending on the size, complexity, and/or
project governance decision. There may also be different CD Approvers assigned to each CD
Review (i.e. CD-2 & CD-3 may require more technically inclined reviewers). A unanimous
decision is required from all CD Approvers at each CD review before advancing the project to its
successive phase or stage. It is the PM’s responsibility to resolve any CD Review conflict/s to
achieve unanimous acceptance. Section 3.1.1: Critical Decision (CD) Review in this guide offers
the CD Review process flow as it may be applied in the IT PEM.
14 DOE G 415.1-1
7-17-2014
2.3.3 Deliverables and CD Packages
IT PEM deliverables can be both tangible (i.e. artifacts) and intangible (i.e. activities). When
deliverables required for a particular CD are grouped together (in a package) they are referred to
as a CD Package. Figure 4: Deliverables, CD Package, and CD Review illustrates the
composition of a CD package and its progress towards a CD review. A CD Memorandum is an
artifact utilized at each CD Review to summarize all the required deliverables and to declare
their completed status.
Figure 4: Deliverables, CD Package, and CD Review
Deliverables required for each of the five CD Packages should be defined by CD-1 as part of the
performance measurement baseline milestone. Deliverables introduced beyond CD-1 may
require acceptance via a change control process as they may bring about scope, schedule, and/or
cost implications which may need to be pre-determined.
Note: Where applicable, the term “Deliverable is utilized in this guide to mean both activities and
artifacts.
Note: DOE O 415.1 requires that IT projects implement formal stage gates or transition points
during the project’s lifecycle to validate that the project is proceeding as planned and a go, no-go, or
hold decision is made.
Note: IT projects may choose to tailor (combine, waive, or modify) CDs as appropriate. It is at the
discretion of each project team and their respective governance to determine how to structure the
CDs throughout the project lifecycle.
Note: Deviations from the standard PEM framework should still satisfy the intent of each CD (CD-2
through CD-4) and comply with federal and governmental requirements such as Cybersecurity,
OMB, and Enterprise Architecture.
DOE G 415.1-1 15
7-17-2014
2.3.4 Project Stakeholders
Various project stakeholders are utilized throughout the IT PEM framework. The PM should
establish, assign, and ensure project team understanding of these roles and their respective
responsibilities early in the project lifecycle (i.e. Initiation Phase). Well-defined roles and
responsibilities promote proper and timely management of deliverables, processes, reviews, and
approvals. Table 3: Roles and Responsibilities lists and describes the typical project
stakeholders found in most DOE IT projects.
Section 12
Table 3: Roles and Responsibilities
Roles Responsibilities
Executive Sponsor
(Mission Owner)
Senior Federal Executive who specifies the business need or mission to the Federal Sponsor
or to the organizational level. The Executive Sponsor is also responsible for allocating
and/or designating the funding for the business need.
Business Owner The Business Owner has ultimate responsibility for seeing that the intended benefits are
realized to create the value forecast in the business case. The Business Owner represents
the business users and serves as part of the Integrated Project Team (IPT). The business
owner's job is to help ensure that the end users become satisfied end users and that they
understand and anticipate the development and deployment process, appreciate the product's
benefits, welcome training, accept the new system and eventually adopt it as their own. The
business owner may perform, participate (or lead) the following core activities:
• Business Case Development
• Business Process & Business Requirements identification
• Functional Requirements Development
• Business User Acceptance Testing
• Business User Training
• Quality/Integrity Oversight
• Communication (Business Stakeholders & Sponsor)
• Achieve Return on Investment
Federal Sponsor Federal executive in appropriate level within an organization with the authority to accept
and assign project management responsibility. The Federal Sponsor manages the budget
within their organization.
Enterprise
Architecture (EA)
An EA includes the rules, standards and systems life cycle information to optimize and
maintain the environment which the agency wishes to create and maintain through its IT
portfolio. An EA should provide a strategy that enables the agency to support its current
state and provides a roadmap for transition to its target environment. An EA defines
principles and goals and sets a direction on such issues as the promotion of
interoperability, open systems, public access, end-user satisfaction, and IT security. The
agency should support an EA with a complete inventory of agency information resources
including: stakeholders and customers, equipment, systems, services, and funds devoted
to information resources management and IT, at an appropriate level of detail.
Acquisition
Executive (AE)
The individual designated to integrate and unify the management system for a Program and
implement prescribed policies and practices.
The Acquisition Executive cannot award or modify contracts, nor commit the Government
in any way, without an approved delegation of authority from the Head of the Contracting
Activity (HCA) to serve as a Contracting Officer.
Contract Officer Individual with authority to enter into, administer, and/or terminate contracts and make
16 DOE G 415.1-1
7-17-2014
Roles Responsibilities
(CO) related determinations and findings. The CO (or Contracting Officer representative) is
accountable for preparing solicitation documents with technical support from the Federal
Project Manager (FPM) and acting on behalf of the Head of the Contracting Activity
(HCA).
Contract Officer
Representative
(COR)
CORs are qualified individuals appointed by the (CO) to assist in the technical monitoring
or administration of a contract.
Critical Decision
(CD) Approvers
Section 13
The ultimate goal of a CD Approver is to advance a project to its successive phase or stage.
CD Approvers should be identified and assigned by each individual project team and their
respective governance early in the project (preferably at Initiation Phase). The CD
Approvers should typically be familiar with the project, its deliverables, and its governance.
The CD Approvers should have a stake or interest in the success of the project and hold the
appropriate authority to influence financial, budget, and project governance decisions. A
project may have one or more CD Approvers depending on the size, complexity, and/or
project governance decision. There may also be different CD Approvers assigned to each
CD Review (i.e. CD-2 & CD-3 may require more technically inclined reviewers).
Federal Project
Manager (FPM)
Federal official with formal project management certification and or training. Responsible
for the overall success of the project and for reporting to key project stakeholders.
Responsible for the development, maintenance, and implementation of the PMP. Defines,
monitors, and reports project cost, schedule, performance, and scope baselines. Manages the
CD approval process. Oversees the development of, and provides concurrence with all CD
packages. Recommends independent reviews. Ensures compliance and coordination with
the OMB-required and DOE-required reporting activities.
Contractor Project
Manager (CPM)
Contractor responsible with supporting the FPM with the day-to-day management of the
project. Assists with the development and implementation of the PMP and successor
artifacts. Manages assigned project resources. Reports status and performance issues to the
FPM. Identifies and remediates risks. Delivers all required documentation to the FPM in a
manner conducive to the PMP, Project Schedule, and CD process. Conducts internal
reviews and testing activities that ensure the quality of the developed solution.
Project Team The Project Team is the group responsible for planning and executing the project. The
Project Team members execute their tasks according to the Project Schedule. Their
responsibility includes executing tasks and producing deliverables as outlined in the Project
Plan and directed by the PM, at whatever level of effort or participation has been defined or
assigned to them.
Integrated Project
Team (IPT)
Inter-disciplinary stakeholder group with the specific knowledge, skills, and abilities
necessary to support and complement the decision-making process. IPT members may be
fully or partially part of the Project Team. The IPT may consist of Federal and contractor
staff. Provides advice and recommendations on key project decisions. Facilitates
communication between the project and the affected organizations. Facilitates execution of
the Capital Planning and Investment Control (CPIC) process, cybersecurity, Enterprise
Architecture (EA), and related activities. Assists the FPM in the performance of in-stage
and post-stage assessments of project performance. May serve as Subject Matter Expert
(SME) in their area of responsibility for the full scope of the project. May support the FPM
in other ways, as required and assigned. Prepares and submits reports per the PMP or
project schedule.
Working Group Inter-disciplinary group designated by the IPT to carry out the development of a task,
analysis, or deliverable. The Working Group does not make decisions but reports directly to
DOE G 415.1-1 17
7-17-2014
Section 14
Roles Responsibilities
the IPT or FPM.
Focus Group Technical subgroup designated by the IPT, FPM, or Working Group to carry out the
development of a task, analysis, or deliverable. The Focus Group does not make decisions
and reports directly to the Working Group.
Change Control
Board (CCB)
The CCB is composed of predefined project stakeholders responsible for ensuring proper
management of change throughout the project. Members of the CCB should have sufficient
knowledge of a project’s requirements and expected outcome (end-product) to recommend
the approval or rejection of change requests.
Independent
Reviewer (IR)
Individual or group not directly involved with the project but provides the PM with an
objective assessment of whether the project is ready for a CD review, and ultimately request
approval to proceed to the next phase.
Figure 5: Project Stakeholders and their Communication Paths illustrates the relationship
between key project management stakeholders and their reporting and collaboration paths.
Figure 5: Project Stakeholders and their Communication Paths
Note: The term Project Manager (PM) is utilized throughout this guide to mean both Federal Project
Manager (FPM) and Contractor Project Manager (CPM).
Note: The project stakeholders referenced in this section suggest a typical composition which may be
utilized at the DOE. Some projects may differ and involve less or more stakeholders depending on
project size, complexity, or specific program office protocol.
18 DOE G 415.1-1
7-17-2014
MONITORING AND CONTROLLING PROCESSES
This section of the IT PEM will introduce the processes and reviews utilized throughout the IT
PEM framework to manage project scope, schedule, cost, and quality. This section may be
utilized as a guide or standard when developing such artifacts as the quality management plan,
risk management plan, change control plan, communication plan, and other segments of the
PMP. The processes and procedures covered in this section include:
• Quality Management
• Risk Management
• Change Control Management
Figure 6: IT PEM Monitoring & Controlling provides a view of the IT PEM framework as it
relates to the monitoring and controlling processes and reviews covered in this section. The
illustration suggests the order in which each process and reviews may occur in the IT PEM
lifecycle.
Figure 6: IT PEM Monitoring & Controlling Processes
DOE G 415.1-1 19
7-17-2014
2.4 Quality Management
The IT PEM promotes three types of project reviews which are essential for building structure
and quality into the project. These reviews also set the foundation to facilitate timely and
effective decision-making for the project. The three types of reviews covered in this section
include the:
• Critical Decision (CD) Review
• Independent Reviews
• Quarterly Project Reviews
2.4.1 Critical Decision (CD) Review
As previously defined in Section 2.3.2: Critical Decision (CD), CDs are formal stage gates or
transition points during the project’s lifecycle where predefined activities and artifacts (CD
Packages) are evaluated to confirm its successful completion. Upon confirmation that the CD
package has been successfully completed, the appropriate CD approver/s can agree on advancing
the project to the next phase or stage in the IT PEM project lifecycle. The following bullets
highlight some of the benefits that can be realized with a sound CD review process:
Section 15
• Quality deliverables and artifacts;
• Increased probability of project success;
• Reduced project risk by providing a clear evaluation criteria;
• Building quality directly into the project;
• Reduced development cycle time, getting it done right the first time and;
• Increased focus on a well-designed product or service
The CD Review process should be performed in preparation for all CDs (CD-0 to CD-4). The
process begins when the PM and project team are ready to confirm that all required deliverables
(CD package) for the current phase or stage have been successfully completed. It is at this point
when the PM performs the steps shown in the process diagram (Figure 7: Critical Decision
Review Process).
The PM and project team may also choose to coordinate an “independent review” to determine if
the project is prepared for a CD review. Section 3.1.2: Independent Reviews (IR) in this guide
describes the independent review process as it may be applied in the IT PEM framework.
20 DOE G 415.1-1
7-17-2014
Figure 7: Critical Decision Review Process
Note: There may be circumstances when the PM and project team agree to proceed to the CD Review
with an incomplete CD package (Steps 2a to 2b in diagram). In these circumstances, the PM should
assign a risk to the phase prior to proceeding to the CD review.
2.4.2 Independent Reviews (IR)
To complement the CD review process, the IT PEM also recommends that PMs coordinate an
Independent Review (IR). The reviewer or reviewing party should consist of personnel that have
no association with the project being reviewed and has knowledge of Software Quality or
Mission Assurance Processes.
The IR will provide the PM with an objective assessment of the project status and whether or not
the CD package should be submitted for review. The ultimate goal is to request approval to
proceed to the next phase. The degree of independence and rigor of the review should be
commensurate with the criticality of the project or the CD under review.
DOE G 415.1-1 21
7-17-2014
The results of the IR should be documented in an IR report, which would be submitted as part of
a CD package. Table 4: Independent Reviews for Critical Decisions summarizes the
recommendations for an IR by CD.
Table 4: Independent Reviews for Critical Decisions
Phase Critical Decision Recommendation for
Independent Review*
Pre-Project N/A: Approve Business Case Not Required
Initiating CD-0, Approve Project Charter Optional – Not Recommended
Planning CD-1, Approve Performance
Measurement Baseline (PMB)
Highly Recommended.
Executing CD-2, Approve Start of Development Highly Recommended.
CD-3, Approve Start of Production Highly Recommended.
Production CD-4, Approve Project Closure and Start
of Maintenance Stage
Optional – Not Recommended
2.4.3 Quarterly Project Reviews (QPR)
One of the most important elements for a successful IT project is effective communication
between all key project stakeholders. In conjunction with other reviews specified in the project’s
Communications Plan, projects should conduct a Quarterly Project Reviews (QPR) on a routine
basis after CD-0. These reviews should continue until the IT project’s solution reaches steady
state.
The QPR should cover key topics including, but not limited to:
• Accomplishments (to date and/or during previous quarter);
• Planned activities (until completion and/or planned for next quarter)
• Critical risks and issues
• Topics that require decision by the Acquisition Executive and other key stakeholders
• Measurement of project performance against baseline (metrics)
Section 16
The QPR should be a management briefing (with any supporting documentation) used by the PM
to brief the AE and other key stakeholders on the status of the IT project.
2.5 Risk Management
A risk is an event or condition that if it occurs, could have a positive or negative effect on a
project’s objectives. The PM working with the project team will ensure that risks are actively
identified, analyzed, and managed throughout the life of the project. Risks should be identified
as early as possible in the project so as to minimize their probability and potential impact. Figure
8: Probability and Impact Analysis (Sample Only) illustrates a sample criteria and matrix for
determining the probability and impact of a particular risk.
22 DOE G 415.1-1
7-17-2014
Figure 8: Probability and Impact Analysis (Sample Only)
The probability of risk occurrence can range anywhere from just above 0% to just below 100%.
If a risk is guaranteed to occur (100%) then it is no longer a risk but an issue and should be
managed using an issue management process. Table 5: Risk Management describes the general
process for managing project risk.
Table 5: Risk Management
Steps Responsible Description Key Artifact
1) Develop The
Risk
Management
Plan
Project
Manager
The Risk Management plan documents how, when, and by
who risks are to be identified, addressed and handled. The
document is prepared by the PM with inputs from appropriate
project stakeholders to ensure alignment on process and risk
tolerance levels.
Risk
Management
Plan
2) Identify Risks Risk Creator
A risk can be identified by anyone and at any point during the
project. PMs should facilitate proactive risk identification
sessions with the project team and pertinent stakeholders to
identify risks at the beginning of the project, as well as at
periodic checkpoints during the project. A Risk Register is
utilized to input and track the risks to the project. The
Risk Register attempts to characterize all of the risks
associated with the project. The document is typically set
up in table form (spread sheet). Each risk is characterized
by its probability of occurring, the impact it would have on
the project, and the steps being taken to address it.
Risk Register
3) Risk Analysis
Risk Owner
Once a risk is identified, it is assigned to a Risk Owner who
will assess the probability and impact of the risk if realized.
The result of this analysis is used to prioritize the risk and
assign it a value or rank (or as specified in the Risk
Management Plan). Figure 8: Probability and Impact
Analysis (Sample Only) above provides a suggested sample
for assigning a probability and impact value to a risk.
Risk Register
DOE G 415.1-1 23
7-17-2014
Steps Responsible Description Key Artifact
4) Risk Response
Planning
Risk Owner
Once a risk’s probability and impact has been assessed, the
following approaches may be selected to address it:
• Avoid – Eliminate the threat or condition or to protect the
project objectives from its impact by eliminating the cause;
• Mitigate – Identify ways to reduce the probability or the
impact of the risk;
• Accept – Nothing will be done;
• Contingency –Define actions to be taken in response to
risks; or
• Transfer – Shift the consequence of a risk to a third party
together with ownership of the response by making another
party responsible for the risk (buy insurance, outsourcing,
etc.).
Risk Register
5) Risk Control
Risk Owner
& Project
Manager
Section 17
Open risks should monitored on a regular basis. During
monitoring, the risk content and status should be reevaluated.
The Risk Owner and PM may need to seek management
support and escalate high probability, high impact risks for
visibility, input, and senior management decision making. Risk Register
6) Close Risk Project
Manager
A risk can be closed by the PM when one of the four actions
occurs:
1. The risk was successfully eliminated or averted;
2. The risk occurs and becomes an issue;
3. The end date of the risk has passed; or
4. The project has been completed.
Risk Register
Note: Projects differ in size, complexity, and risk tolerance. As result, the method for assigning
probability and impact values to a risk may differ from that provided above. The chosen risk
management methodology should be well documented in the projects Risk Management Plan.
Note: The probability cannot be 100%; at 100% it becomes a certainty, not a risk. Also it cannot be
0%, or there would be no risk.
24 DOE G 415.1-1
7-17-2014
2.6 Change Control Management
The aim of this section is to provide a basic understanding of the change control management
process and to help promote a standard for managing changes that may impact scope, schedule,
or budget. The Change Control Management Plan is developed during the Planning Phase and
should describe how, when, and who will be involved in the process. This process should be
followed from this point onward to appropriately assess the impact changes will have on the
project’s scope, schedule, and budget.
Following a Change Control Management Process becomes even more important after the
project is baselined (e.g. CD-1) as it can help to appropriately analyze and accept changes and
avoid scope creep. The process outlined below may be utilized as a guide and not a replacement
or in conflict with each project’s Change Control Plan. Table 6: Change Control Management
describes a general process for managing project changes.
Table 6: Change Control Management
Step Responsible Description Key Artifact
1) Change Request
(CR) Requestor
The requestor, generally a direct project
stakeholder will identify a required change and
submit a Change Request Form (CR Form) to the
PM. The CR Form is a document used to submit
a request for change in a project. The Change
Request Form summarizes the reasons and costs
associated with a particular change.
CR Form
2) Receive
& Process
the CR Form
PM &
Project Team
The PM will review the CR Form for quality and
completeness. If accepted, the CRs are added to
the Change Request Log (CR Log). The CR Log
is a document used to log and track change requests
throughout the life of the project. The CR Log
should be updated as new change requests are
submitted or as existing change requests are
approved, rejected, or deferred. Most of the
information on the change log will come directly
from the CR Form.
CR Form
CR Log
3) Approve the
Request PM & CCB
The PM will present the accepted CR Form to the
CCB who will recommend the approval or
rejection of the change request. The CR Log is
updated with the outcome from the CCB review.
CR Form
CR Log
4) Start Impact
Assessment
Impact
Assessment
Team
If approved, the CR Form is provided to the
individual or team responsible for conducting the
impact assessment. The Impact Assessment
Team will analyze the change request and
estimate the level of effort and/or impact to scope,
schedule, and cost. The Impact Assessment Team
documents their assessment in the designated
section within the CR Form.
Section 18
CR Form
5) Assessment
Review PM & CCB
The PM reviews the Impact assessment with the
CCB and may request clarification or further
analysis from the impact assessment team if
CR Form
CR Log
DOE G 415.1-1 25
7-17-2014
Step Responsible Description Key Artifact
required (The CR Log is updated).
6) Approve
Implementation
PM, CCB,
(or as specified
in the CC Plan)
The PM and CCB (or as specified in CC Plan)
approve or reject the CR based on the impact
assessment information. The CR Log and CR
Form are updated with the approval or rejection
information.
Impact
Assessment
CR Form
CR Log
7) Update PM
Documents and
Communicate to
Stakeholders
PM
The PM communicates the approval or rejection
of the CR to the requestor and pertinent
stakeholders. The PM will update other PM
artifacts such as the PMP, Project Schedule, and
Risk Register. The CR Log and CR Form are
updated and closed.
CR Form
CR Log
Other PM
Artifacts
8) Implement
Approved CR PM The PM manages the implementation of the
approved CR.
Other PM
Artifacts
Figure 9: Change Control Management Process provides a high-level view of the IT PEM
change control management process. The process begins once a project has been baselined
which in the IT PEM occurs at CD-1.
Figure 9: Change Control Management Process
26 DOE G 415.1-1
7-17-2014
3 KEY PROJECT MANAGEMENT PRINCIPLES
This section of the IT PEM will introduce key principles that complement the IT PEM by
promoting structure and flexibility. The principles in this section can be utilized as guides to aid
in determining:
• Project Complexity Level (PCL);
• Tailoring Approach; and
• Modular or Agile Approach;
3.1 Project Complexity Level (PCL)
As mentioned in Section 1.3: Applicability and Exclusions of this guide, DOE O 415.1 has set in
place the following criteria to determine those projects that are within the thresholds of the IT
PEM applicability:
• A Total Project Cost (TPC) equal to or more than $25 Million (M);
• With an impact on more than one DOE Element; or
• As determined by the Undersecretary or Head of Element, based on risk management,
mission, priorities, or national interest.
To support the above criteria and to further establish a method for distinguishing projects of
differing costs and complexity levels, the IT PEM framework utilizes the Project Complexity
Level (PCL). The PCL leverages the criteria set forth in DOE O 415.1 to distinguish projects
based on the following complexity levels: 1) High, 2) Medium, or 3) Low. Table 7: Determining
Project Complexity Level displays a matrix view of the PCL and explains the basic criteria for
each of the PCL sizes.
Table 7: Determining Project Complexity Level
Determining the PCL will help in identifying the proper: level of governance oversight; rightful
program or project office; and tailoring approach. It is therefore strongly suggested that the PCL
be determined during the Pre-Project Phase along with or as part of the (high-level) business case
DOE G 415.1-1 27
7-17-2014
development. The decision tree is shown in Figure 10: Decision Tree for Determining PCL &
IT PEM Applicability illustrates at a high-level the suggested approach for determining the PCL
of a project.
Figure 10: Decision Tree for Determining PCL & IT PEM Applicability
Note: DOE O 415.1 requires that all IT projects that do not meet the above criteria be required to
use a standardized project management approach as specified and approved by the
sponsoring/funding organization.
Section 19
Note: DOE O 415.1 Applicability & Exclusions criteria for projects are different than the criteria
used for CPIC investments. Project teams are advised to reference the latest Capital Planning and
Investment Control (CPIC) documentation (i.e. DOE Guide to IT Capital Planning and Investment
Control) or contact CPIC team at DOE.CPICMailbox@hq.doe.gov for specific updates to the
investment levels, cost thresholds, and specific DOE and Office of Management and Budget
requirements.
Note: In addition to the applicability criteria from DOE O 415.1, IT projects also have the option to
assess other project criteria to determine its PCL. Other project criteria may include, but not be
limited to the following:
• Familiarity of requirements;
• Number of system interfaces (internal or external); and
• Familiarity with technology.
mailto:DOE.CPICMailbox@hq.doe.gov
28 DOE G 415.1-1
7-17-2014
3.2 Tailoring
This section introduces the concept of tailoring as it is applied in the IT PEM framework. This
section may be utilized as a guide or standard for developing the Tailoring Plan. Figure 11: IT
PEM Tailoring suggests a path for developing the Tailoring Plan. As the illustration suggests,
the Tailoring Plan can be incorporated into the PMP and submitted for review at CD-1.
Figure 11: IT PEM Tailoring
The IT PEM tailoring process begins with the determination of the PCL. As described in Section
4.1(Project Complexity Level) of this guide, the PCL provides a method for differentiating
projects based on their level of complexity (see Table 7: Determining Project Complexity Level in
previous section). A project of higher complexity may require greater effort with regards to
process, reviews, and the content and quantity of artifacts.
The PM and project team utilize the PCL to determine an appropriate tailoring strategy. The
Tailoring Strategy should include the project’s request to consolidate, modify, or waive any
standard artifacts or phase gate reviews (CDs) from the standard IT PEM framework in
accordance with the risks, costs, complexity, and strategic visibility of the project. The Tailoring
Strategy may also describe phase, artifact, and review alterations due to using a modular or agile
development approach.
The strategy should then be captured in the Tailoring Plan and included with (or as part of) the
PMP for review at CD-1. The project should attempt to adhere to the work pattern established in
the Tailoring Plan throughout the remainder of the lifecycle. Any subsequent deviation from the
approved work pattern should be analyzed and appropriately approved to ensure adequate
deliverables are provided and to assess impact on project scope, schedule, and cost. Section
DOE G 415.1-1 29
7-17-2014
5.1(Project Management Templates and Artifacts) in this guide provides the IT PEM Artifact
Matrix which suggests project artifacts based on IT PEM phase, stage, PCL, and importance to
DOE O 415.1 and other federal directives.
Note: The following principles should be followed when applying tailoring:
• The Cost Baseline and Schedule Baseline should be adjusted to include the elements of the
Tailoring Strategy.
• The Tailoring Strategy should only apply to deviations from the standard PEM framework starting
with the Planning Phase, immediately following CD-0.
• All projects, regardless of PCL or project type, should complete the same processes and develop
the same project artifacts outlined in the Initiation Phase, leading up to CD-1, Approve
Performance Measurement Baseline (PMB).
Section 20
• The proposed deviations from the standard PEM framework should still satisfy the intent of each
CD (CD-2 through CD-4) and comply with federal and governmental requirements such as
Cybersecurity, OMB, and Enterprise Architecture.
• Tailoring should be proposed with the assertion that there is no significant advantage to staged
decision making, in terms of lowering risk and increasing the probability of success.
3.3 Agile or Modular Development
Agile and Modular development is an alternative to traditional waterfall project management and
typically used in software development. This type of development helps project teams respond to
unpredictability through incremental, iterative work patterns, also known as sprints. Every aspect
of design, development, and testing is continually revisited through the iterative process. Project
teams have the opportunity at every sprint planning meeting to re-evaluate the direction of the
project and steer it in another direction if required. The “inspect-and-adapt” approach to
development can help reduce both development costs and product or feature release to customer.
The goal is to deliver a usable product or feature at the end of each successful sprint.
Per the Office of Management and Budget (OMB), Contracting Guidance to Support Modular
Development, agencies can recognize the following benefits through modular development
approaches:
• Delivery of usable capabilities that provide value to customers more rapidly as agency
missions and priorities mature and evolve;
• Increased flexibility to adopt emerging technologies incrementally, reducing the risk of
technological obsolescence;
• Decreased overall project risk as agencies plan for smaller projects and increments versus
“grand design” (each project has a greater overall likelihood of achieving cost, schedule,
and performance goals than a larger, all-inclusive development effort);
• Creation of new opportunities for small businesses to compete for the work;
• Greater visibility into contractor performance. Tying award of contracts for subsequent
Task Orders to the acceptable delivery of prior projects provides agencies better visibility
30 DOE G 415.1-1
7-17-2014
into contractor performance and allows a greater opportunity to implement corrective
actions without sacrificing an entire project;
• A project can be terminated with fewer sunk costs, capping the risk exposure to the agency
when priorities change, a technology decision does not work or the contractor’s
performance does not deliver results.
3.3.1 Agile or Modular Development Using the IT PEM
This section describes how an agile or modular development may be applied within the IT PEM
framework. The intent is not to focus on a specific agile or modular methodology such as
SCRUM, XP, Kanban, etc. Instead, the intent is to provide a general overview of common
deliverables found in both agile and modular development and describe how those deliverables
may be executed using the IT PEM framework. Figure 12: IT PEM Agile & Modular
Development illustrates the general process flow required to execute a modular or agile approach
within the IT PEM framework. The process involves:
• Identifying the project scope and requirements early in the IT PEM lifecycle (Initiation &
Planning Phases);
• Determining whether an agile or modular development should be used for the project;
• Developing and documenting the agile/modular strategy in the Agile/Modular Plan;
• The Agile/Modular Plan should:
Section 21
o Explain the benefits and risks of using a modular or agile approach;
o Describe the agile / modular approach or methodology to be utilized (i.e. SCRUM,
XP, Kanban);
o Describe specific project stakeholder roles and responsibilities;
o Describe iterative process and sprint/module durations;
o Define the artifacts to be utilized during the iterative process to address design,
development, testing, and operational readiness acceptance (i.e. System Design
Review, Test Readiness Review, and Operational Readiness Review);
o Describe how Monitoring & Controlling processes will be addressed during the
iterative process (i.e. Change Control Management, Risk Management, CD
Reviews, and Quarterly Project/Other Reviews)
o Describe product or feature release method.
• Submit the Agile/Modular Plan along with the PMP for approval at CD-1;
• Begin agile/modular development after CD-1 (or Execution Phase);
• Release system, product, or features after CD-3 approval.
Figure 12: IT PEM Agile & Modular Development
DOE G 415.1-1 31
7-17-2014
The following examples provide two methods of how agile or modular development could be
applied in the IT PEM framework:
Example 1: An IT project may combine CD-2 and CD-3 to create an effective agile process
which will provide flexibility during the systems design, development, and testing stages to
accommodate the inherently iterative nature of IT projects.
Figure 13: CD-2 & CD-3 Combined
Example 2: In the spirit of modular development, an IT project may choose to execute three
software releases in order to produce key features of the product, and thereby minimizing risk
with the uncertainty in software development. Therefore, the IT project may choose to complete
the Execution Phase in an iterative manner. This would produce 3 different CD packages for CD-
2 (CD-2a, CD-2b, CD-2c) and CD-3 (CD-3a, CD-3b, CD-3c).
32 DOE G 415.1-1
7-17-2014
Figure 14: CD-2 and CD-3 applied for each module or iteration
Note: Deviations from the standard PEM framework should still satisfy the intent of each CD
(CD-2 through CD-4) and comply with federal and governmental requirements such as
Cybersecurity, OMB, and Enterprise Architecture.
DOE G 415.1-1 33
7-17-2014
4 TEMPLATES & ARTIFACTS
4.1 Project Management Templates and Artifacts
The IT PEM defines project management through the appropriate application and integration of
logically grouped project management processes across its five lifecycle phases (Pre-Project,
Initiation, Planning, Execution, and Production). Each process leads to the development of a
project artifact. In this section, the aim is to provide project teams with a standard artifact table
that helps them define required, beneficial, and optional artifacts based on the PCL described in
Section 4.1 : Project Complexity Level (PCL) of this guide.
Table 8 illustrates the IT PEM Artifact Matrix which lists the project management artifacts by
IT-PEM Phase and PCL. In addition to the PCL, PEM artifacts are further categorized in the
following criteria:
• Required (REQ): Project management artifacts endorsed by DOE O 415.1 and/or OMB
for Exhibit 300.
• Essential (ESS): | Project management artifacts essential to maintain and/or support
federal approaches towards strategy, business, security, and technology.
• Beneficial (BEN): Best practice and other conventional artifacts that may prove
beneficial for successful project management.
Note: The IT PEM Artifact Matrix (Table 8: Illustration of the "IT PEM Artifact Matrix”) is located
Section 22
in the Corporate IT PMO Framework Repository. For a soft copy or access to the repository, please
send your requests to IM-20, Office of IT Policy and Governance at CorporateITPMO@hq.doe.gov.
Note: DOE O 415.1 Applicability & Exclusions criteria for projects are different than the criteria used
for CPIC investments. Project teams are advised to reference the latest Capital Planning and Investment
Control (CPIC) documentation (i.e. DOE Guide to IT Capital Planning and Investment Control) or
contact CPIC team at DOE.CPICMailbox@hq.doe.gov for specific updates to the investment levels, cost
thresholds, and specific DOE and Office of Management and Budget requirements.
Note: It is at the discretion of each project team and their respective governance to determine how to
structure the CDs throughout the project lifecycle.
Note: Deviations from the standard PEM framework should still satisfy the intent of each CD (CD-2
through CD-4) and comply with federal and governmental requirements such as Cybersecurity, OMB,
and Enterprise Architecture.
mailto:CorporateITPMO@hq.doe.gov
mailto:DOE.CPICMailbox@hq.doe.gov
34 DOE G 415.1-1
7-17-2014
Table 8: Illustration of the “IT PEM Artifact Matrix”"
Beneficial (BEN)
OMB for Exhibit
300 Investment
Enterprise
Architecture (EA) Cybersecurity High Medium Low
Validate w ith specific
requesting
organization (CPIC)
before tailoring
(omitting,
consolidating, or
modifying) below
artifacts.
Validate w ith specific
requesting
organization (EA)
before tailoring
(omitting,
consolidating, or
modifying) below
artifacts.
Validate w ith specific
requesting
organization (Cyber)
before tailoring
(omitting,
consolidating, or
modifying) below
artifacts.
Projects:
> $25M
Projects:
$25M -$5M or
Impacts M ore
Than One
DOE Element
Projects:
<$5M and
does not
Impact other
DOE
Elements
Architecture Review Worksheet (Pre-Project Phase)
* Reference "Architecture Review Process" Template for Specific Requirements
X ESS ESS ESS
Business Case X BEN BEN BEN
Project Charter X X X REQ REQ BEN
Architecture Review Artifacts (FEA, DoDAF, PRM, BRM, DRM, ARM, IRM)
* Reference "Architecture Review Process" Template for Specific Requirements
X ESS ESS ESS
Approval of CD-0 (Memorandum) X X REQ REQ ESS
Requirements Document
(Business, Functional, Non-Functional, Data, and Interface)
X X X REQ REQ ESS
Project Management Plan (PMP) X X REQ REQ BEN
Scope Management Plan X ESS ESS ESS
Schedule Management Plan X BEN BEN BEN
Cost Management Plan X BEN BEN BEN
Work Breakdown Structure (WBS) X BEN BEN BEN
Tailoring, Module, and/or Agile Plan X BEN BEN BEN
Deliverables Table (Activities, Artifacts, or Products) X ESS ESS ESS
Requirements Management Plan X ESS ESS ESS
Configuration Management and Change Control Plan X X X REQ REQ ESS
Quality Management Plan X ESS ESS ESS
Performance Management Plan X X REQ REQ ESS
Human Resource Plan X BEN BEN BEN
Communication Management Plan X BEN BEN BEN
Acquisition Plan X BEN BEN BEN
Training Plan X BEN BEN BEN
Risk Management Plan X X X REQ REQ BEN
Cybersecurity Plan X X REQ REQ ESS
Test Plan X BEN BEN BEN
Alternatives Analysis X X REQ REQ BEN
Basis of Estimate X BEN BEN BEN
Architecture Review Artifacts (FEA, DoDAF, PRM, BRM, DRM, ARM, IRM)
* Reference "Architecture Review Process" Template for Specific Requirements
Section 23
X ESS ESS ESS
Project Schedule (Baseline) X X REQ REQ BEN
Performance Measurement Baseline X X REQ REQ BEN
Risk Register X BEN BEN BEN
Quarterly Project Review (QPR) Presentation X BEN BEN BEN
Independent Review (IR) Documentation X ESS ESS ESS
Approval of CD-1 (Memorandum) X X REQ REQ ESS
System Requirements Document X X ESS ESS ESS
System Design Document X X ESS ESS ESS
Detailed Cost Estmate X X ESS ESS ESS
Risk Register X X X X REQ REQ ESS
Change Control Management Artifacts X X X X REQ REQ ESS
Independent Review (IR) Documentation X ESS ESS ESS
Approval of CD-2 (Memorandum) X X REQ REQ ESS
Training Material Completed X BEN BEN BEN
Test Readiness Review (TRR) Documentation X BEN BEN BEN
Risk Register X X X X REQ REQ ESS
Change Control Management Artifacts X X X X REQ REQ ESS
Operational Readiness (ORR) Documentation X BEN BEN BEN
Quarterly Project Review (QPR) Presentation X BEN BEN BEN
Risk Register X X X X REQ REQ ESS
Change Control Management Artifacts X X X X REQ REQ ESS
Independent Review (IR) Documentation X ESS ESS ESS
Lessons Learned Document X ESS ESS ESS
Approval of CD-3 (Memorandum) X X REQ REQ ESS
Training Material X BEN BEN BEN
Post Implementation Report X X X REQ BEN ESS
Risk Register X X X X REQ REQ ESS
Change Control Management Artifacts X X X X REQ REQ ESS
Project Closure Report X BEN BEN BEN
Independent Review (IR) Documentation X ESS ESS ESS
Lessons Learned Document X X ESS ESS ESS
Approval of CD-4 (Memorandum) X ESS ESS ESS
Mai
nt. Annual Operational Analysis (AOA) X X REQ ESS ESS
Pre-Project N/
A
Production
Im
pl
m
nt
Cl
os
ur
e
Initiation N/
A
Planning N/
A
Execution
De
si
gn
Dv
lp
m
nt
.
Te
st
in
g
PEM
Phase
PE
M
S
ta
ge
Project Artifact
Required (REQ) Essential (ESS) Project Complexity Level
Directive
O 415.1
Best Practice
Artifacts
DOE G 415.1-1 35
7-17-2014
5 IT PEM Framework at a Glance
Table 9: IT PEM Framework at a Glance provides a glance at the IT PEM framework as
described in the previous sections. The purpose of this illustration is to provide a summary for
project managers to reference when applying the IT PEM framework.
36 DOE G 415.1-1
7-17-2014
Table 9: IT PEM Framework at a Glance
DOE G 415.1-1 37
7-17-2014
6 INFORMATION TECHNOLOGY PROJECT MODEL BY PHASE
This section attempts to illustrate IT PEM artifact inputs and outputs for each lifecycle phase in
preparation for its corresponding CD review. The intent is to provide project teams with a
suggested workflow to systematically process and complete deliverables as prescribed by each
CD review.
Note: The artifacts and CD packages displayed in this section have not been tailored nor
designed for a particular PCL. Figures 15 to 20 may contain more or less artifacts than that
actually required by a particular project.
Note: Projects may choose to tailor (combine, waive, or modify) CDs as appropriate. It is at the
discretion of each project team and their respective governance to determine how to structure the
CDs throughout the project lifecycle.
Note: Deviations from the standard PEM framework should still satisfy the intent of each CD (CD-2
through CD-4) and comply with federal and governmental requirements such as Cybersecurity,
OMB, and Enterprise Architecture.
6.1 Pre-Project Phase:
Figure 15: Pre-Project Phase
38 DOE G 415.1-1
7-17-2014
6.2 Initiation Phase:
Figure 16: Initiation Phase Artifact Workflow
6.3 Planning Phase:
Figure 17: Planning Phase Artifact Workflow
DOE G 415.1-1 39
7-17-2014
Section 24
6.4 Execution Phase:
Figure 18: Execution Phase Artifact Workflow (CD-2)
Figure 19: Execution Phase Artifact Workflow (CD-3)
40 DOE G 415.1-1
7-17-2014
6.5 Production Phase
Figure 20: Production Phase Artifact Workflow
DOE G 415.1-1 Appendix A
7-17-2014 A-1
APPENDIX A
OCIO Resources and Departmental Requirements
The IT PEM in accordance with DOE O 415.1 aims to support Government-wide and/or
Department requirements essential to maintain and/or support federal approaches towards
strategy, business, security, and technology. Table 10: Government-wide and DOE Requirements
Integrated into the IT PEM provides a list and brief description of some of the OCIO resources
and/or department requirements supported by IT PEM.
Table 10: Government-wide and DOE Requirements Integrated into the IT PEM
Topic Summary OCIO Contact
Capital
Planning and
Investment
Control
(CPIC)
As defined by the Office of Management and
Budget (OMB) Circular A-11, “Capital planning
and investment control means the same as capital
programming and is a decision-making process for
ensuring IT investments integrate strategic
planning, budgeting, procurement, and the
management of IT in support of agency missions
and business needs. The term comes from the
Clinger-Cohen Act of 1996 and generally is used
in relationship to IT management issues.”
IT Capital Planning and
Architecture Division (IM-21)
DOE.CPICMailbox@hq.doe.gov
Configuration
Management
(CM)
Configuration management (CM) is the detailed
recording and updating of information that
describes an enterprise's hardware and software. It
is a process for establishing and maintaining
consistency of a product's performance, functional
and physical attributes with its requirements,
design and operational information throughout its
life.
Configuration Management
(CM) - OCIO
Cybersecurity The definition of Cybersecurity is the protection of
information systems against unauthorized access
to or modification of information, whether in
storage, processing, or transit, against loss of
accountability for information and user actions,
and against the denial of service to authorized
users, including those measures necessary to
protect against, detect, and counter such threats.
Cybersecurity
(IM-30) - OCIO
Enterprise
Architecture
Enterprise Architecture (EA) refers to the
explicit description and documentation of the
current and desired relationships among
business and management processes and IT of
an organization. It describes the “current
architecture” and “target architecture”. An EA
includes the rules and standards and systems
life cycle information to optimize and maintain
the environment which the agency wishes to
create and maintain through its IT portfolio.
Enterprise Architecture
(IM-1) - OCIO
DOEEAMailbox@hq.doe.gov
https://powerpedia.energy.gov/wiki/Office_of_Management_and_Budget
https://powerpedia.energy.gov/wiki/Office_of_Management_and_Budget
mailto:DOE.CPICMailbox@hq.doe.gov
mailto:DOEEAMailbox@hq.doe.gov
Appendix A DOE G 415.1-1
A-2 7-17-2014
Topic Summary OCIO Contact
An EA should provide a strategy that enables
the agency to support its current state and
provides a roadmap for transition to its target
environment. An EA defines principles and
goals and sets a direction on such issues as the
promotion of interoperability, open systems,
public access, end-user satisfaction, and IT
security. The agency should support an EA
with a complete inventory of agency
information resources including: stakeholders
and customers, equipment, systems, services,
and funds devoted to information resources
management and IT, at an appropriate level of
detail.
Section 25
Performance
Management
and Quality
Assurance
Division
Lead organization for implementing the
requirements of DOE O 414.1D within the Office
of the Chief Information Officer and is designated
as the voting member for the DOE Quality
Council. Within IM-60, PMQAD is responsible
for ensuring compliance with applicable Federal
directives and orders; and ensuring compliance
with contractual performance standards and
industry best practices, including alignment with
ISO 9001:2008 and the Software Engineering
Institute (SEI) Capability Maturity Model
Integrated (CMMI).
Director of Performance
Management and Quality
Assurance Division (IM-60) -
OCIO
EITS_PMQAD@hq.doe.gov
Records
Management
Records management, or RM, is the practice of
maintaining the records of an organization from
the time they are created up to their eventual
disposal. This may include classifying, storing,
securing, and destruction (or in some cases,
archival preservation) of records.
The Records Management
Division (IM-23) - OCIO
Safety and
Safeguards
Conduct a preliminary safety and safeguards
assessment by CD-0. At CD-1, the AE ensures
that the quality assurance practice addresses all
safety and security requirements, per the
Integrated Safety and Safeguards directives.
U.S. Department of Energy
(DOE), Office of Health, Safety
and Security (HSS) - OCIO
mailto:EITS_PMQAD@hq.doe.gov
DOE G 415.1-1 Appendix B
7-17-2014 B-1
APPENDIX B
GLOSSARY
Term Definition
Acquisition Executive (AE) The individual designated by the Secretary of Energy to
integrate and unify the management system for a Program
portfolio of projects and implement prescribed policies and
practices.
The Acquisition Executive cannot award nor modify contracts,
or commit the Government in any way, without an approved
delegation of authority from the Head of the Contracting
Activity (HCA) to serve as a Contracting Officer.”
Agile Development Refers to an alternative to traditional project management,
typically used in software development. It helps teams respond
to unpredictability through incremental, iterative work
cadences, known as sprints. Agile methodologies are an
alternative to waterfall, or traditional sequential development.
Alternative Analysis Refers to an analysis of alternatives for addressing the
performance objectives of an investment. The analysis is
performed prior to the initial decision to implement a solution
and updated periodically, as appropriate, to capture changes in
the context for an investment decision. Alternatives analysis
documentation should be submitted along with Exhibit 300 for
all major IT investments. Alternatives Analysis should be
performed for investments with projects in the planning or DME
stages, whereas strictly operational investments should instead
perform operational analyses until such time as a decision is
made to re-evaluate the investment or to resume development,
modernization or enhancement.
Baseline A quantitative definition of cost, schedule, and technical
performance that serves as a base or standard for measurement
and control during the performance of an effort; the established
plan against which the status of resources and the effort of the
overall Program, Field Program(s), project(s), task(s), or
subtask(s) are measured, assessed, and controlled. Once
established, baselines are subject to a change-control discipline.
Beneficial (BEN)
Artifacts
Best practice and other conventional artifacts that may prove
beneficial for successful project management.
Section 26
Benefit Cost Analysis Refers to the recommended technique to use in a formal
economic analysis of government programs or projects.
Guidance for Benefit-Cost Analysis is described in OMB
Circular A-94.
Budget A prediction of the costs associated with a particular project.
These costs include labor, materials, and other related expenses.
http://www.whitehouse.gov/omb/circulars_a094
http://www.whitehouse.gov/omb/circulars_a094
Appendix B DOE G 415.1-1
B-2 7-17-2014
Term Definition
Business Owner The Business Owner has ultimate responsibility for seeing that the
intended benefits are realized to create the value forecast in the
business case. The Business Owner represents the business users and
serves as part of the Integrated Project Team (IPT). The business
owner's job is to help ensure that the end users become satisfied end
users and that they understand and anticipate the development and
deployment process, appreciate the product's benefits, welcome
training, accept the new system and eventually adopt it as their own.
The business owner may perform, participate (or lead) the following
core activities:
• Business Case Development
• Business Process & Business Requirements identification
• Functional Requirements Development
• Business User Acceptance Testing
• Business User Training
• Quality/Integrity Oversight
• Communication (Business Stakeholders & Sponsor)
• Achieve Return on Investment
Capital Planning and
Investment Control
(CPIC)
(Also called capital programming) refers to a decision-
making process that ensures IT investments integrate
strategic planning, budgeting, procurement, and
management of IT in support of agency missions and
business needs. The term was introduced in the Clinger-
Cohen Act of 1996 and generally is used in relation to IT
management issues.
CD Approvers The ultimate goal of a CD Approver is to advance a project to
its successive phase or stage. CD Approvers should be
identified and assigned by each individual project team and
their respective governance early in the project (preferably at
Initiation Phase). The CD Approvers should typically be
familiar with the project, its deliverables, and its governance.
The CD Approvers should have a stake or interest in the
success of the project and hold the appropriate authority to
influence financial, budget, and project governance decisions.
A project may have one or more CD Approvers depending on
the size, complexity, and/or project governance decision. There
may also be different CD Approvers assigned to each CD
Review (i.e. CD-2 & CD-3 may require more technically
inclined reviewers).
CD Package Required deliverables for a particular CD grouped together (in
a package).
Change Control Board
(CCB)
Predefined project stakeholders responsible for ensuring proper
management of change throughout the project. Members of the
CCB should have sufficient knowledge of a project’s
requirements and expected outcome (end-product) to
recommend the approval or rejection of change requests.
DOE G 415.1-1 Appendix B
7-17-2014 B-3
Term Definition
Chief Information Officer
(CIO)
Senior executive responsible for the information technology
and computer systems that support enterprise goals. The CIO
provides leadership, establishes policy, and maintains oversight
of DOE’s annual investment in information technology (IT), to
enable urgent missions that span from open science to nuclear
security.
Section 27
Closure Stage The purpose of the closing phase is to confirm completion of
project deliverables to the satisfaction of the project sponsor. In
addition, all procurement and project management processes are
closed. All project artifacts are collected and archived. Final
project disposition and status is communicated to all
participants and stakeholders.
Contract A contract is a mutually binding agreement that obligates the
seller to provide the specified product and obligates the buyer to
pay for it.
Contract Officer
(CO)
The CO has the authority to enter into, administer, and/or
terminate contracts and make related determinations and
findings. The term includes certain authorized representatives
of the CO acting within limits of his/her authority as delegated
by the CO. The CO and/or his/her representative are
accountable for preparing solicitation documents with technical
support from the IT PM and acting on behalf of the Head of the
Contracting Activity.
Contract Officer
Representative (COR)
CORs are qualified individuals appointed by the (CO) to assist
in the technical monitoring or administration of a contract.
Contractor Project
Manager
Contractor responsible for day-to-day management of the
contractor project team. This role may also represent any PM
for each distinct IT service (e.g., design, build, and
operations/maintenance) reporting to the FPM.
Cost Refers to the expenditure of funds or use of property to acquire,
produce, operate, or maintain an asset. Examples include, but
are not limited to: sunk costs, operational costs, acquisition
costs, and disposition costs (including variable costs such as
labor hours).
Critical Decision (CD) Critical Decisions (CDs) are formal stage gates or transition
points during a project’s lifecycle where a set of required
deliverables are evaluated by “CD approvers” to ensure they
were properly completed and accepted.
Cybersecurity The protection of information systems against unauthorized
access to or modification of information (whether in storage,
processing, or transit), loss of accountability for information
and user actions, and the denial of service to authorized users,
including those measures necessary to protect against, detect,
and counter such threats.
Appendix B DOE G 415.1-1
B-4 7-17-2014
Term Definition
Deliverable Tangible and intangible outputs (artifacts and activities)
generated throughout the project.
Departmental Directives
Program
Used to establish Directives as the primary means to set,
communicate, and institutionalize policies, requirements,
responsibilities, and procedures for Departmental Elements and
contractors. Equivalencies and exemptions to this Order are
processed in accordance with DOE Order 251.1C,
Departmental Directives Program.
Design Stage The primary objective is to create a design that satisfies the
requirements gathered and agreed during the Planning Phase.
Questions move from the previous "what" type questions in the
Planning Phase to the "how" type questions. The end result is
an approved design of how the proposed solution is to be
developed. The “system design document” and the “system
requirements review document” are utilized to formalize and
document final design.
Development,
Modernization, and
Enhancement (DME)
DME means the project cost for new projects, changes, or
modifications to existing systems to improve capability or
performance; changes mandated by Congress or Agency
leadership; personnel costs for investment management; and
direct support.
Section 28
Development Stage Procurement is executed and developers begin to develop the
actual system or product. This involves writing any software
and building the appropriate architecture.
DOE Elements First-tier organizations at Headquarters and in the field that may
apply the IT PEM framework for their program and project
management endeavors.
Enterprise Architecture
(EA)
An EA includes the rules and standards and systems life
cycle information to optimize and maintain the environment
which the agency wishes to create and maintain through its
IT portfolio. An EA should provide a strategy that enables
the agency to support its current state and provides a
roadmap for transition to its target environment. An EA
defines principles and goals and sets a direction on such
issues as the promotion of interoperability, open systems,
public access, end-user satisfaction, and IT security. The
agency should support an EA with a complete inventory of
agency information resources including: stakeholders and
customers, equipment, systems, services, and funds devoted
to information resources management and IT, at an
appropriate level of detail.
Enterprise-wide IT
Projects
A project that spans or impacts multiple DOE Elements.
DOE G 415.1-1 Appendix B
7-17-2014 B-5
Term Definition
Essential (ESS)
Artifacts
Project management artifacts essential to maintain and/or
support federal approaches towards strategy, business, security,
and technology.
Execution Phase This phase includes processes performed to complete the
activities (tasks, milestones, deliverables, and artifacts) defined
in the Planning Phase. Monitoring and Controlling processes
and procedures are also performed to track, review, and
regulate the progress and performance of the project. Any
changes to the baseline plan may require a formal change
control process or as specified in the PMP.
Executive Sponsor
(Mission Owner)
Senior Federal Executive who specifies the business need or
mission to the Federal Sponsor or to the organizational level.
The Executive Sponsor is also responsible for allocating and/or
designating the funding for the business need.
Federal Project Manager
(FPM)
Federal official responsible for the overall success of the project
and for reporting to the AE. The FPM oversees the project until
project closeout.
Federal Sponsor Federal executive at the organizational level with the authority
to accept and assign project management responsibility. The
Federal Sponsor manages the budget within the organization.
Focus Group Technical subgroup designated by the IPT, FPM, or Working
Group to carry out the development of a task, analysis, or
deliverable. The Focus Group does not make decisions and
reports directly to the Working Group.
Impact Assessment Team Team responsible for the analysis and determination of cost,
time, and resource impacts of a change in project scope,
schedule, or cost.
Implementation Stage System or product is implemented and released to all end-users,
system documentation is provided to end-users, training is
provided to each group of users. Post implementation report is
completed to formalize successful completion, sponsor
acceptance and sign off.
Independent Reviewer (IR) Individual or group not directly involved with the project but
provides the PM with an objective assessment of whether the
project is ready for a CD review, and ultimately request
approval to proceed to the next phase.
Section 29
Information Any communication or representation of knowledge such as
facts, data, or opinions in any medium or form, including
textual, numerical, graphic, cartographic, narrative, or
audiovisual forms.
Information System A combination of information, computer, and
telecommunications resources; other information technology
resources; and personnel resources that collect, record, process,
store, communicate, retrieve, and display information.
Appendix B DOE G 415.1-1
B-6 7-17-2014
Term Definition
Information Technology
(IT)
Information technology, as defined by the Clinger-Cohen Act
of 1996, sections 5002, 5141, and 5142, means any equipment
or interconnected system or subsystem of equipment that is
used in the automatic acquisition, storage, manipulation,
management, movement, control, display, switching,
interchange, transmission, or reception of data or
information. For purposes of this definition, equipment is
“used” by an Agency whether the Agency uses the equipment
directly or it is used by a contractor under a contract with the
Agency that (1) requires the use of such equipment or (2)
requires the use, to a significant extent, of such equipment in
the performance of a service or the furnishing of a
product. Information technology includes computers, ancillary
equipment, software, firmware, and similar procedures, services
(including support services), and related resources. It does not
include any equipment that is acquired by a Federal contractor
incidental to a Federal contract. Information technology is any
proposed acquisition of information technology or information
technology-related resources to support a defined business
need.
Information Technology
Project Execution Model
(IT PEM)
The Information Technology Project Execution Model (IT
PEM) is a guide that supports the U.S. Department of Energy
(DOE) IT Program and Project Managers (PM) with guidance
that may be useful to them in effectively and efficiently
implementing the requirements of DOE Order (O) 415.1,
Information Technology Project Management, and dated
December 3, 2012. Specifically, this Guide provides a
suggested formal, structured, and integrated standard approach
to managing DOE IT projects and programs.
Initiation Phase At this initial phase, the approved (high-level) business case
becomes an input and is utilized to develop the Project Charter
and identify initial scope. Internal and external Stakeholders
(who interact and influence the overall outcome of the project)
are identified and documented in the Stakeholder Register.
Project Charter approval is obtained and both the project and
PM are officially authorized. Initial financial resources are
committed.
Initiative An initiative is created by an Organization in response to a
driver or internal Directives and defines the scope of the
Organizational work- efforts performed.
Integrated Project Team
(IPT)
Inter-disciplinary stakeholder group with the specific
knowledge, skills, and abilities necessary to support and
complement the decision-making process. IPT members may
be fully or partially part of the project team. The IPT may
consist of Federal and contractor staff.
DOE G 415.1-1 Appendix B
7-17-2014 B-7
Term Definition
IT Assets These IT assets provide the infrastructure and operational IT
Section 30
services necessary for accomplishing the site Missions and
Programs. Specifically, they are locally managed IT assets or IT
support services. Examples include the following:
• Networks;
• Telecommunications;
• Desktops;
• Internet/Intranet;
• Email;
• Collaboration Tools;
• IT Planning (EA/CPIC/Program Office Support);
• Web Hosting;
• Data Storage; and/or
• Contractor Business/Financial/Administrative Systems.
IT Investment Refers to the expenditure of IT resources to address mission
delivery and management support. An IT investment may
include a project or projects for the development,
modernization, enhancement, or maintenance of a single IT
asset or group of IT assets with related functionality, and the
subsequent operation of those assets in a production
environment. All IT investments should have a defined life
cycle with start and end dates, with the end date representing the
end of the currently estimated useful life of the investment,
consistent with the investment’s most current alternatives
analysis if applicable.
IT PEM Elements The IT PEM framework is comprised of four elements which
serve as its foundation and infrastructure. The four IT PEM
elements are composed of:
• Lifecycle Phases & Stages
• Critical Decision (CD)
• Deliverables & CD Packages
• Project Stakeholders
IT Project A planned endeavor funded by an approved information
technology investment, thus achieving a specific goal and
creating a unique product, service, or result. A project has a
defined start and end point with specific objectives that, when
attained, signify completion.
IT Project Management
Office
(IT PMO)
An Organizational Element or group that defines and maintains
the standards or processes generally related to Project
Management within the Organization. The PMO develops
project guidance, policies, and procedures.
Appendix B DOE G 415.1-1
B-8 7-17-2014
Term Definition
IT Project Manager
(IT PM)
An individual in the Headquarters (HQ) Organizational
Element responsible for managing a project and its assigned
activities. This individual ensures that all the projects are
properly phased, funded over time, and that each PM is meeting
his/her key milestones. These individuals are the project’s
advocates, ensure proper resourcing, and facilitate the execution
process. They predict Programmatic risks and put mitigation
strategies in place so that projects are not affected.
Life Cycle Phases Lifecycle phases are distinct periods in a project’s lifespan.
Each period is comprised of tangible and intangible deliverables
that upon fulfilling will help advance the project closer towards
completion. The PEM Lifecycle Phases include the: Pre-
Project, Initiation, Planning, Execution, and Production phases.
Maintenance An activity necessary to keep an asset functioning as designed
during its operations and maintenance phase of a project.
Maintenance costs include costs needed to sustain an IT asset at
the current capability and performance levels including:
corrective hardware/software, voice and data communications
maintenance, replacement of damaged or obsolete IT
equipment, and associated overhead costs. Examples of
maintenance projects include operating system upgrades,
technology refreshes, and security patch implementations.
Section 31
Maintenance Stage The Maintenance Stage occurs after project closure. An
“Annual Operational Analysis” is conducted to continuously
collect system or product data and monitor and control the
system or product’s lifecycle status. When determined that the
system or product has reached the end of its lifecycle, proper
system disposition is conducted to ensure that a system's
components, data, software and hardware are disposed of
properly and according to organizational regulations. Vital
information is archived and maintained for future business or
system needs.
Milestone Any significant or substantive point, time, or event of the
project. Milestones typically refer to points at which large-
schedule events or series of events have been completed, and a
new phase(s) is set to begin.
Mission Assurance A full life-cycle engineering process to identify and mitigate
design, production, test, and field support deficiencies of
mission success.
Modular Development
(or Modularization)
This involves dividing a project or investment into smaller parts
in order to reduce investment risk, deliver capabilities more
rapidly, and permit easier adoption of newer and emerging
technologies.
Monitoring and
Controlling
Refers to the processes and procedures essential to manage
project scope, schedule, cost, and quality.
DOE G 415.1-1 Appendix B
7-17-2014 B-9
Term Definition
Objective This defines the principal areas of concern within the overall
goal; it may also provide quantitative measures of future
performance and may list several Strategic Targets that provide
additional quantification of Agency objectives.
Office of the Chief
Information Officer
(OCIO)
The Office responsible to ensure that IT is acquired and
information resources are managed consistent with statutory,
regulatory, and Departmental requirements and priorities.
Operation The day-to-day management of an asset in the production
environment and included activities to operate data centers help
desks, operational centers, telecommunication centers, and end-
user support services. Operations costs include the expenses
associated with an IT asset that is in the production
environment to sustain an IT asset at the current capability and
performance levels including Federal and contracted labor costs
and the costs for the disposal of an asset.
Planning Phase This phase includes processes required to establish the total
scope of the project, define key target performance metrics, and
ensure that the proposed scope, schedule, and cost baseline are
achievable. To accomplish these goals, the PM should develop
the project management plan (PMP), collect business –
functional requirements, refine objectives, perform risk
management, and ultimately baseline the project.
Pre-Project Phase An initial Pre-Project Phase is used in the IT PEM framework
to ensure that critical pre-project tasks have been considered
and/or fulfilled. These critical tasks lay the foundation for the
development of the (high-level) business case. An approved
(high-level) business case is expected prior to advancing the
project to the Initiation Phase and committing federal and
contractor resources.
Process A permanent or semi-permanent collection of measurable,
auditable, and repeatable activities that result in an output.
Production Phase This phase includes the actual implementation of the system or
product in the production environment, the product or system
release to production environment, handoff to operations,
project closure, and initiation of the Retirement Stage.
Section 32
Program Refers to a group of related projects.
Program Management A group of related projects managed in a coordinated way to
obtain benefits and control not available from managing them
individually.
Appendix B DOE G 415.1-1
B-10 7-17-2014
Term Definition
Project A project has a defined start and end point with specific
objectives that, when attained, signify completion thus
achieving a specific goal and creating a unique product, service,
or result. Built on interdependent activities planned to meet a
common objective, a project focuses on attaining or completing
a deliverable within a predetermined cost, schedule, and
technical scope.
Project Complexity Level
(PCL)
The PCL leverages the criteria set forth in DOE O 415.1 to
distinguish projects based on the following complexity levels:
1) High, 2) Medium, or 3) Low.
Project Management Project Management is the discipline of planning, organizing,
securing, managing, leading, and controlling resources to
achieve specific goals. A project is a temporary endeavor with a
defined beginning and end (usually time-constrained, and often
constrained by funding or deliverables) undertaken to meet
unique goals and objectives, typically to bring about beneficial
change or added value.
Project Management Plan
(PMP)
The contractor-prepared document that sets forth the plans,
organization, and systems that the contractor will utilize to
manage the project. Its content and the extent of detail of the
PMP will vary in accordance with the size of the type of project
and state of project execution.
Project Performance The overall measurement of whether a project has met
objectives and requirements of scope, cost, and schedule. A
periodic measurement during the monitoring and controlling
phases of a project performed to observe project execution and
identify variances from the Project Management Plan for
proactive mitigation.
Project Team The Project Team is the group that is responsible for planning
and executing the project. The Project Team members execute
their tasks according to the Project Schedule. Their
responsibility includes executing tasks and producing
deliverables as outlined in the Project Plan and directed by the
PM, at whatever level of effort or participation has been defined
or assigned to them.
http://en.wikipedia.org/wiki/Project
DOE G 415.1-1 Appendix B
7-17-2014 B-11
Term Definition
Quarterly Project Reviews
(QPR)
A quarterly management briefing (with supporting
documentation) where the PM updates key stakeholders and
executives on the status of the IT project. The QPR should
cover key topics including, but not limited to:
• Accomplishments (to date and/or during previous quarter);
• Planned activities (until completion and/or planned for next
quarter)
• Critical risks and issues
• Topics that require decision by the Acquisition Executive
• Measurement of project performance against baseline
(metrics)
Required (REQ)
Artifacts
Project management artifacts endorsed by DOE O 415.1 and/or
required by OMB for Exhibit 300.
Requirements A singular documented need of what a particular product or
service should be or perform. It is a statement that identifies a
necessary attribute, capability, characteristic, or quality of a
system in order for it to have value and utility to a user.
Business requirements describe in business terms what should
be delivered or accomplished to provide value. Functional
requirements describe the functionality that the system is to
execute.
Section 33
Risk Factor, element, constraint, or course of action that introduces
an uncertainty of outcome either positively or negatively that
could impact project objectives.
Risk Management The handling of risks through specific methods and techniques.
Effective risk management is an essential element of every
project. The DOE risk management concept is based on the
principles that risk management should be analytical, forward-
looking, structured, informative, and continuous. Risk
assessments should be performed as early as possible in the
project and should identify critical technical, performance,
schedule, and cost risks. Once risks are identified, sound risk
mitigation strategies and actions should be developed and
documented.
Schedule A listing of a project's milestones, activities, and deliverables,
usually with intended start and finish dates. Those items are
often estimated in terms of resource allocation, budget and
duration, linked by dependencies and scheduled events.
Scope The work that needs to be accomplished to deliver a product,
service, or result with the specified features and functions.
Solution A comprehensive architectural response to a business problem.
Solutions address all layers of EA - strategy, business, data,
applications, and technology/security.
Sponsoring/Funding
Organization
The DOE Organization responsible for providing the necessary
funding to support the project and project activities.
http://en.wikipedia.org/wiki/Functional_requirements
http://en.wikipedia.org/wiki/Functional_requirements
http://en.wikipedia.org/wiki/Project
http://en.wikipedia.org/wiki/Milestone_(project_management)
http://en.wikipedia.org/wiki/Task_(project_management)
http://en.wikipedia.org/wiki/Deliverable
http://en.wikipedia.org/wiki/Estimation_(project_management)
http://en.wikipedia.org/wiki/Resource_allocation
http://en.wikipedia.org/wiki/Budget
http://en.wikipedia.org/wiki/Duration_(project_management)
http://en.wikipedia.org/wiki/Dependency_(project_management)
Appendix B DOE G 415.1-1
B-12 7-17-2014
Term Definition
Stages In addition to the lifecycle phases, the IT PEM also
incorporates six project stages which support IT project
lifecycle requirements. The PEM Stages include: Design,
Development, Testing, Implementation, Closure, and
Retirement stages.
Stakeholder Individuals and Organizations that are actively involved in the
project, or whose interests may be positively or negatively
affected as a result of Program execution or completion. They
may also exert influence over the Program and its results.
Steady State (SS) Steady State means maintenance and operation costs at current
capability and performance levels including costs for personnel,
maintenance of existing information systems, corrective
software maintenance, voice and data communications
maintenance, and replacement of broken IT equipment.
System An interconnected set of information resources organized for
the collection, processing, maintenance, transmission, and
dissemination of information, in accordance with defined
procedures, whether automated or manual.
Tailoring Tailoring is used to determine which processes and outputs are
appropriate, and the degree of rigor that should be applied
based on factors such as scope, size, risk, and complexity.
Testing Stage Begins after the product or feature has been developed. The
test plans developed during the planning phase are utilized to
verify that the features or product meets the business
requirements. User Acceptance Testing (UAT) and the
Operational Readiness Document are utilized as acceptance
criteria to ensure the system or product is ready for transition to
the Production Phase.
Section 34
Total Project Cost
(TPC)
All cost planning and implementation specific to a project
incurred through the startup of continual operations (capability
delivered) but prior to the operation of the facility.
Working Group Inter-disciplinary group designated by the IPT to carry out the
development of a task, analysis, or deliverable. The Working
Group does not make decisions but reports directly to the IPT
or FPM.
DOE G 415.1-1 Appendix C
7-17-2014 C-1
APPENDIX C
ACRONYMS
Acronym Definition
AUP Agile Unified Process
BEN Beneficial
BY Budget Year
C&A Certification and Accreditation
CC Change Control
CCB Change Control Board
CD Critical Decision
CIO Chief Information Officer
CO Contracting Officer
COR Contracting Officer’s Representative
CPIC Capital Planning and Investment Control
CPM Contractor Project Manager
CR Change Request
DME Development, Modernization and Enhancement
DOE Department of Energy
EA Enterprise Architecture
EM Environmental Management
EOP Executive Office of the President
ESS Essential
EVM Earned Value Management
EVMS Earned Value Management System
FASA Federal Acquisition Streamlining Act
FISMA Federal Information Security Management Act
FPM Federal Project Manager
GAO Government Accountability Office
HCA Head of the Contracting Activity
HHS Health and Human Services
HQ Headquarters
IEEE Institute of Electrical and Electronics Engineers
IMS Integrated Master Schedule
IPT Integrated Project Team
IR Independent Review
IT Information Technology
M Million ($)
NNSA National Nuclear Security Administration
O Order
OCIO Office of the Chief Information Officer
OMB Office of Management and Budget
PCL Project Complexity Level
PEM Project Execution Model
Appendix C DOE G 415.1-1
C-2 7-17-2014
Acronym Definition
PMB Performance Measurement Baseline
PMBOK Project Management Body of Knowledge
PMI Project Management Institute
PMO Project Management Office
PMP Project Management Plan
QA Quality Assurance
QPR Quarterly Project Review
REQ Required
RM Records Management
RTM Requirements Traceability Matrix
S&S Safety and Safeguards
SEI Software Engineering Institute
SEM Systems Engineering Methodology
SS Steady State
TPC Total Project Cost
UAT User Acceptance Test
WBS Work Breakdown Structure
XP Extreme Programming
DOE G 415.1-1 Appendix D
7-17-2014 D-1
APPENDIX D
REFERENCES
a. DOE, Secretary Delegation Order No. 00-031.00A, dated June 7, 2007.
b. DOE CIO Memorandum, Enterprise Architecture Guidance, dated January 9,
2007.
c. DOE G 413.3-2, Quality Assurance Guide for Project Management, dated June
27, 2008.
d. DOE G 413.18-A, Integrated Project Team Guide for Formation and
Implementation, dated February 3, 2012.
e. DOE O 200.1A, Information Technology Management, dated December 23, 2008.
f. DOE O 205.1B, Department of Energy Cybersecurity Management Program,
dated May 16, 2011.
g. DOE O 243.1A, Records Management Program, dated November 7, 2011.
h. DOE O 413.1B, Internal Control Program, dated October 28, 2008.
i. DOE O 413.3B, Program and Project Management for the Acquisition of Capital
Assets, dated November 29, 2010.
j. DOE O 414.1D, Quality Assurance, dated April 25, 2011.
k. Executive Order 13011, Federal Information Technology, FR 61-140, dated July
19, 1996.
l. Government Accountability Office (GAO) Report – GAO-11-826, OMB Needs to
Improve Its Guidance on IT Investments, dated September 29, 2011.
m. Office of Science, Definition of a User Facility Memorandum, dated January 6,
Section 35
2012.
n. OMB Circular A-11, Preparation, Submission and Execution of the Budget, dated
August 18, 2011.
o. OMB Circular A-123, Management Accountability and Control, dated December
21, 2004.
p. OMB Circular A-127, Financial Management Systems, dated January 9, 2009.
q. OMB Circular A-130, Management of Federal Information Resources, dated
November 28, 2000.
r. OMB Memorandum M-00-07, Incorporating and Funding Security in
Information Systems Investments, dated February 28, 2000.
s. OMB Memorandum M-11-29, Chief Information Officer Authorities, dated
August 8, 2011.
t. OMB Memorandum M-97-02, Funding Information Systems Investments, dated
October 25, 1996.
u. The Clinger-Cohen Act of 1996, (CCA), (Public Law 104-106, Division E), dated
February 10, 1996.
v. The E-Government Act of 2002, (Public Law 107-347), dated December 17, 2002.
w. The Federal Acquisition Streamlining Act of 1994, Title V (FASA V), dated
October 13, 1994.
x. The Federal Information Security Management Act (FISMA) of 2002, dated
October 24, 2002.
https://www.directives.doe.gov/directives/0413.3-EGuide-02
https://www.directives.doe.gov/directives/0413.3-EGuide-02
https://www.directives.doe.gov/directives/0413.3-BOrder-b/view
https://www.directives.doe.gov/directives/0413.3-BOrder-b/view
Appendix D DOE G 415.1-1
D-2 7-17-2014
y. The Government Information Security Reform Act (GISRA - 2000), dated October
30, 2000.
z. The Government Paperwork Elimination Act of 1998, (Public Law 105-277, Title
XVII), dated October 21, 1998.
aa. The Government Performance and Results Act of 1993 (GPRA) (Public Law 103-
62), dated August 3, 1993.
bb. The Paperwork Reduction Act of 1995, (Public Law 104-13), dated May 22, 1995.
cc. The President’s Management Agenda, Office of Management and Budget, Fiscal
Year 2002, dated January 29, 2001.
dd. Federal Acquisition Regulation (FAR), General Services Administration,
Department of Defense, and National Aeronautics and Space Administration,
dated March 2005.
ee. 25 Point Implementation Plan to Reform Federal Information Technology
Management, U.S. Chief Information Officer, dated December 9, 2010.
ff. Contracting Guidance to Support Modular Development, U.S. Chief Information
Officer, dated June 14, 2012.
gg. Project Execution Model (PEM), National Nuclear Security Administration
(NNSA) Office of the Chief Information Officer, dated September 2009.
DOE G 415.1-1 Appendix E
7-17-2014 E-1
APPENDIX E
DESCRIPTION OF PROJECT ARTIFACTS
Acquisition Plan: A document that details all major concerns for acquiring materials or services
in support of a project. Typically, the Acquisition Plan addresses issues related to technological
aspects, competition, funding, business concerns, management issues, and other significant risk
factors that could potentially impact the sponsoring/funding organization. The Acquisition Plan
establishes a timetable and specific milestones for the effective execution of the process to
mitigate risk.
Alternatives Analysis: A document that details the analysis of alternatives, which is a detailed
study and assessment of the various options available for the purpose of selecting one for
implementation. Ideally, all feasible alternatives should be investigated.
Section 36
Annual Operational Analysis (AOA): Combines elements from the Capital Planning and
Investment Control (CPIC) evaluation and results from monitoring the performance of the
Business Product during normal operations against original user requirements and any newly
implemented requirements or changes. This document assists in the analysis of alternatives for
deciding on new functional enhancements and/or modifications to the business product, or the
need to dispose of or replace the business product altogether.
Architecture Review Artifacts: Provides a valuable opportunity to review all the architecture
documents to prevent duplication and redundancies, reduce cost, minimize risk, increase
interoperability, increase security, enhance collaboration and to ensure the project is aligned to
the DOE’s future Enterprise Architecture and enterprise roadmap. In addition, the Architecture
Review ensures that all IT investments provide value to DOE’s strategic goals by engaging the
business owners and the Chief Architect as an interactive event prior to the Critical Decision
(CD)-0, Approve Project Charter and Critical Decision (CD)-1.
Baseline Change Request (BCR) Form: A document that is completed whenever there is a
proposed change that impacts the scope of work, schedule, and/or budget elements of the
Performance Measurement Baseline (PMB), or the baseline is impacted by outside influences
such as funding limitations or directed schedule delays. The BCR Form should consider impacts
to the PMB – scope, schedule, and budget.
Basis of Estimate: A document that details the premise, or basis, from which critical aspects of a
project cost estimate were developed, including cost and labor estimates, material availability,
any assumptions or deviations, any studies or analysis used as a reference and any other details
which impacted the cost estimates.
Business Case: A formal, written argument intended to convince a decision maker to approve a
project, initiative, or action. A well-crafted business case explores all feasible approaches to a
given problem and enables business owners to select the option that best serves the organization.
In addition to the written argument, a Business Case should also include a list of the business
requirements, an alternative cost analysis, forecasted cost if implemented, forecasted cost if not
Appendix E DOE G 415.1-1
E-2 7-17-2014
implemented, return on investment, and other essential data prescribed by internal and external
federal organizations.
Business Requirements Document (BRD): A document that details the business solution for a
project including information pertaining to the customer needs, customer expectations, and
important technical characteristics.
Communication Management Plan: The document that describes: the communications needs
and expectations for the project; how and in what format information will be communicated;
when and where each communication will be made; and who is responsible for providing each
type of communication. The Communication Management Plan is contained in, or is a subsidiary
plan of, the Project Management Plan.
Section 37
Configuration Management and Change Control Plan: A document that describes how
configuration management and change control will be structured and performed on the project. It
is contained in or is a subsidiary plan of the Project Management Plan. Configuration
management refers to the process for establishing and maintaining consistency of a product’s
performance and functional and physical attributes with its requirements, design, and operational
information through its lifecycle. Change Control refers to the process of establishing a defined
identification of, a thorough documentation of, submission of a formal approval or rejection of,
and asserting control of all changes that are going to take place to the project baselines.
Cost Performance Baseline: A specific version of the time-phased budget used to compare
actual expenditures to planned expenditures to determine if preventive or corrective action is
needed to meet the project objectives.
Chief Architect’s Signature: Occurs during the Planning Phase. Chief Architect approval and
signature after EA project artifacts (As described in the DOE Architecture Review Process) have
been reviewed by the DOE Architecture Review Board.
Cybersecurity Plan: A document that describes managerial, technical and operational security
controls (defined by the National Institute of Standards and Technology) that are designed and
implemented within the system (May also be referred to as System Security Plan (SSP).
Detail Cost Estimate: Provides detail cost and level of effort estimate based on system design
document.
Earned Value Management (EVM) Report: Refers to an integrated management system that
coordinates the work scope, schedule, and cost goals of a program or contract, and objectively
measures progress toward these goals. EVM is a tool used by program managers to: (1) quantify
and measure program/contract performance, (2) provide an early warning system for deviation
from a baseline, (3) mitigate risks associated with cost and schedule overruns, and (4) provide a
means to forecast final cost and schedule outcomes. The qualities and operating characteristics of
earned value management systems (EVMS) are described in American National Standards
Institute (ANSI)/Electronic Industries Alliance (EIA) Standard–748–1998, Earned Value
Management Systems. Additional information on EVMS is available at www.acq.osd.mil/evm.
http://www.acq.osd.mil/evm.
DOE G 415.1-1 Appendix E
7-17-2014 E-3
Functional Requirements Document (FRD). Detailed outline of what needs to be delivered for
the purpose of communicating it to technical teams and/or developers. The Functional
Requirements Document is a successor of the BRD and typically completed by a business
analyst.
Human Resource Plan: A document describing how roles and responsibilities, reporting
relationships, and staffing management will be addressed and structured for the project. It is
contained in or is a subsidiary plan of the project management plan.
Independent Review (IR) Documentation: A set of documentation that describes the approach
for conducting an IR and describes the outcomes of the IR. The goal of the IR is to assess
whether the IT project is prepared to submit a CD submission, and ultimately request approval to
proceed to the next phase.
Independent Verification and Validation (IV&V) Plan: (See Independent Review (IR)
Documentation)
Independent Verification and Validation (IV&V) Report: (See Independent Review (IR)
Documentation)
Section 38
Lessons Learned Document. A document that contains the learning gained from the process of
performing the project. Lessons learned may be identified at any point. Lessons learned are also
considered a project record. Lessons Learned may also be tracked in a knowledge base.
Operational Readiness Review (ORR). A review to ensure the product or feature has been
properly tested, approved, ready, and safe for operations, production environment, and / or end-
user.
Performance Measurement Plan: A system or standard of measurement to determine if a set of
inherent characteristics fulfills requirements.
Post Implementation Report. A document used to evaluate the effectiveness of the IT solution
that was implemented in the production environment. The objectives are to determine if the IT
solution: does what it is designed to do; supports the user in an effective and efficient manner as
required; is successful in terms of functionality, performance, and cost versus benefits. The
results of the report can be used to strengthen the IT solution as well as procedures. For IT
systems, post implementation review typically occurs after the system has been in production for
a period of time (normally 6 months).
Project Archives: Preservation of vital information, including both documentation of project
execution and the data from the production system.
Project Management Plan (PMP): The Project Management Plan is a dynamic formal
approved document that defines how the project is executed, monitored and controlled. It may be
summary or detailed and may be composed of one or more subsidiary management plans and
other planning documents. The main objective of the PMP is to document assumptions and
Appendix E DOE G 415.1-1
E-4 7-17-2014
decisions for how the project is to be managed, to help in communication between all of the
concerned parties and to document the scope, costs and time sequencing of the project.
Pre-Project Architecture Review Worksheet: A document that details the results of an
architecture review prior to the initiation of the project. The pre-project architecture review
ensures the proposed IT solution does not duplicate, interfere, or contradict another IT solution
that already exists or is proposed.
Procurement Documentation: Contracts, Statements of Work, Level of Efforts, Bill of
Materials, and other pertinent bonding agreements required to procure project materials and
resources.
Project Charter: A document issued by the project initiator or sponsor that formally authorizes
the existence of a project, and provides the PM with the authority to apply organizational
resources to project activities. This document also embeds the Project Scope Statement which is
the narrative description of the project scope, including major deliverables, project assumptions,
project constraints, and a description of work that provides a documented basis for making future
decisions and for confirming or developing a common understanding of project scope among the
stakeholders.
Project Closure Report: A document which formalizes the closure of a project. The Project
Closure Report provides confirmation that the criteria for customer acceptance have been met
and requests sign-off from the Business Sponsor to close the project.
Project Schedule: The planned dates for performing schedule activities and the planned dates
for meeting schedule milestones. The Project Schedule may also be referred to as the Integrated
Master Schedule (IMS), which is a network of tasks linked from program start through program
finish, reflecting the interdependencies between tasks and milestones.
Section 39
Project Scope Statement: (See Project Charter)
Quality Management Plan: A document that describes how the project management team will
implement the performing organization’s quality policy. The Quality Management Plan is a
component or a subsidiary plan of the Project Management Plan.
Quarterly Project Review (QPR) Presentation: A presentation to the IT project’s management
and stakeholders that provides status. The presentation may include key topics such as
accomplishments, planned activities, critical risks and issues, and items that require decision by
management.
Requirements Management Plan: A document that details the necessary information to
effectively manage project requirements from definition, through traceability, to project delivery.
Risk Management Plan: The document describing how project risk management will be
structured and performed on the project. It is contained in or is a subsidiary plan of the Project
Management Plan. Information in the Risk Management Plan varies by application area and
project size. The Risk Management Plan is different from the Risk Register that contains the list
DOE G 415.1-1 Appendix E
7-17-2014 E-5
of project risks, the results of risk analysis, and the risk responses. The Risk Management Plan
should include a Security Risk Assessment Plan section to describe the analysis and assessment
process for security functional requirements. The Security Risk Assessment Plan should focus
on how to identify and prevent or mitigate threats and vulnerabilities to the information system;
the impact or magnitude of harm that a loss of confidentiality, integrity, or availability would
have on agency assets or operations and the identification and analysis of security controls for
the information system.
Risk Register: The document containing the results of the qualitative risk analysis, quantitative
risk analysis, and risk response planning. The Risk Register details all identified risks, including
description, category, cause, probability of occurring, impact(s) on objectives, proposed
responses, owners, and current status.
Security Risk Assessment: (See Risk Management Plan)
Stakeholder Register & Strategy: A list of the relevant stakeholders and a brief description of
the functional role each will play in support of the project. It is used to ensure that all
stakeholders are included in the project communications.
System Architecture Review (SAR): The System Architecture Review, or SAR, is a process
that brings stakeholders and technologists together to help ensure that technology solutions are
conceived, designed, developed, and deployed in an effective and efficient manner, to maximize
the benefits and functionality of the technology, while minimizing its cost and risk. The SAR
ensures compliance with existing standards and practices, controlled introduction of new
technologies and services, and appropriate reuse of existing technology, to increase returns on
investment and decrease total costs of ownership.
System Design Document: A document that defines the architecture, components, modules,
interfaces, and data for a system to satisfy specified requirements.
System Requirements Review (SRR): A technical review to ensure that the system under
review can proceed into initial systems development, and that all system requirements and
performance requirements are defined, testable, and consistent with cost, schedule, risk,
technology readiness, and other system constraints.
Section 40
Tailoring Plan: Strategy on how project will adapt the IT PEM specifications to the project
based on its unique circumstances. The Tailoring Strategy should be clearly documented within
the Project Management Plan.
Technical Requirements Document (TRD): The TRD translates the FRD requirements into a
systematic and technically executable list. Specifically, the TRD is specifies what system
specific requirements are needed to deliver what was requested (and approved) in the FRD.
Test Plan: A document defines the types of tests (e.g. unit, function, integration, system,
security, performance (load and stress), regression, user acceptance, and/or independent
verification and validation) to be carried out. The document describes the acceptance criteria for
those tests, roles and responsibilities of individuals involved in the testing process, traceability
Appendix E DOE G 415.1-1
E-6 7-17-2014
matrix, resources required (hardware and software environments), and other elements relevant to
test planning and execution. This plan details the manner of testing (test cases, simulation, etc.)
of the integrated software/hardware system. It should include as part of the main document or as
a separate document detailed Test Case Specifications that describe the purpose and manner of
each specific test, the required inputs and expected results for the test, step-by-step procedures
for executing the test, and the pass/fail criteria for determining acceptance.
Test Readiness Review: The TRR is a multi-disciplined technical review to ensure that the
subsystem or system under review is ready to proceed into formal test.
Training Plan: A document that describes the overall goals, learning objectives, and activities
that are to be performed to develop, conduct, control, and evaluate instructions that are to be
provided to users, operators, administrators, and support staff who will use, operate, and/or
otherwise support the solution.
Training Materials: A set of documentation associated with the deployment of the business
product. Documentation may include, but not be limited to: instructor and student guides; audio-
visual aid; and computer-based or other media used to disseminate information about the final
product to the target audience that is in need of the instruction.
User Manual: (See Training Material)
Work Breakdown Structure (WBS): A deliverable-oriented hierarchical decomposition of the
work to be executed by the project team to accomplish the project objectives and create the
required deliverables. It organizes and defines the total scope of the project.
Work Breakdown Structure (WBS) Dictionary: A document that describes each component
in the Work Breakdown Structure (WBS). For each WBS component, the WBS Dictionary
includes a brief definition of the scope or statement of work, defined deliverable(s), a list of
associated activities, and list of milestones. Other information may include: responsible
organization, start and end dates, resources required, an estimate of cost, charge number, contract
information, quality requirements, and technical references to facilitate performance of the work.
Section 41
FOREWORD
1 INTRODUCTION
1.1 Purpose
1.2 Background
1.3 Applicability and Exclusions
2 INFORMATION TECHNOLOGY PROJECT EXECUTION MODEL
2.1 Methodology
2.1.1 PMBOK® Guide1
2.1.2 ITIL v3
2.1.3 System Engineering
2.1.4 Federal Organizations
2.1.5 Government wide or Departmental Requirements
2.2 IT PEM Framework
2.3 IT PEM Elements
2.3.1 Lifecycle Phases & Stages
2.3.2 Critical Decision (CD)
2.3.2.1 CD Approvers
2.3.3 Deliverables and CD Packages
2.3.4 Project Stakeholders
2.4 Quality Management
2.4.1 Critical Decision (CD) Review
2.4.2 Independent Reviews (IR)
2.4.3 Quarterly Project Reviews (QPR)
2.5 Risk Management
2.6 Change Control Management
3 KEY PROJECT MANAGEMENT PRINCIPLES
3.1 Project Complexity Level (PCL)
3.2 Tailoring
3.3 Agile or Modular Development
3.3.1 Agile or Modular Development Using the IT PEM
4 TEMPLATES & ARTIFACTS
4.1 Project Management Templates and Artifacts
5 IT PEM Framework at a Glance
6 INFORMATION TECHNOLOGY PROJECT MODEL BY PHASE
6.1 Pre-Project Phase:
6.2 Initiation Phase:
6.3 Planning Phase:
6.4 Execution Phase:
6.5 Production Phase
APPENDIX A
APPENDIX B
GLOSSARY
APPENDIX C
ACRONYMS
APPENDIX D
REFERENCES
APPENDIX E
DESCRIPTION OF PROJECT ARTIFACTS