DOE G 414.1-2B Admin Chg 1, Quality Assurance Program Guide
Functional areas: Administrative Change, Quality Assurance and Oversight, Safety
This Guide provides information on principles, requirements, and practices used to establish and implement an effective Quality Assurance Program. Cancels DOE G 414.1-2A, DOE G 414.1-3 and DOE G 414.1-5. Admin Chg 1, dated 9-27-11. Admin Chg 2, dated 5-8-13.
Supersedes:
DOE G 414.1-2B, Quality Assurance Program Guide on Aug 16, 2011
Superseded By:
Version history and related documents
Superseded by
A newer version replaces this document.
Supersedes
Earlier documents this one replaced.
- DOE G 414.1-2BQuality Assurance Program Guide (Aug 16, 2011)
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
DOE G 414.1‐2B Chg 2
5‐8‐2013
ADMINISTRATIVE CHANGES TO
DOE G 414.1‐2B, QUALITY ASSURANCE GUIDE
Locations of Changes:
Page Paragraph Changed To
Throughout
the Guide
Reference citations. Revised all reference citations
throughout the Guide to reflect
current versions of the
documents.
15, 31,
32
4.3.2.1
Quality
Feedback 2nd
paragraph
Table 3
5.3
DOE M 231.1‐2, Occurrence
Reporting and Processing of
Operations Information, dated 8‐
19‐03.
DOE O 232.2 Occurrence
Reporting and Processing
Operations Information, dated 1‐
1‐12
31 Table 3, Row
3, Column 2
No 2.4 in the IAEA‐TECDOC‐1169
column – remove editing note that
states:
2.4 Communication and
information sharingError!
Bookmark not defined.
Delete: “Error! Bookmark not
defined.”
B‐1 Appendix B DOE M 450.4‐1, Integrated Safety
Management
DOE O 450.2, Integrated Safety
Management, dated 4‐25‐11
B‐2 Appendix B DOE G 450.3‐3, Tailoring for
Integrated Safety Management
Applications, dated 2‐1‐97.
DOE G 450.4‐1C, Integrated
Safety Management System
Guide, dated 9‐29‐11
B‐3 Appendix B DOE M 231.1‐2, Occurrence
Reporting and Processing of
Operations Information, dated 8‐
19‐03.
DOE O 232.2 Occurrence
Reporting and Processing
Operations Information, dated 1‐
1‐12
ADMINISTRATIVE CHANGE TO
Preamble to DOE G 414.1-2B, Quality Assurance Program Guide, dated 8-16-11
Quality Assurance Program (QAP) Guide Enhancements
Department of Energy (DOE) elements and DOE contractors should consult this Guide to
develop and implement an effective Quality Assurance Program (QAP) consistent with the
Department’s quality expectations of the Quality Assurance (QA) Order, DOE Order (O)
414.1D, Quality Assurance, dated 4-25-11, and 10 C.F.R. Part 830 Subpart A, Quality
Assurance Requirements, and that supports DOE Policy (P) 450.4A, Integrated Safety
Management Policy, dated 4-25-11.
This DOE Guide includes enhancements arising from experience with implementing DOE O
414.1D and 10 C.F.R. Part 830 Subpart A. The Guide was evaluated in light of key policy
initiatives, Directive changes, and other changes that have occurred within DOE since the Guide
was last updated.
Evaluation and coordination with user groups have identified specific major improvements to the
Guide as follows:
Clarified the scope of the guidance in accordance with the revisions to DOE O 414.1D.
Revised to incorporate reference to International Atomic Energy Agency (IAEA)
Technical Document, IAEA-TECDOC-1169, Managing Suspect and Counterfeit Items
(S/CIs) in the Nuclear Industry.
Revised to provide additional guidance on S/CIs that is not captured in IAEA-TECDOC-
1169.
Enhanced the guidance on corrective action programs related to DOE QA Criteria 3,
Quality Improvement.
Added information pertaining to the Uniform Federal Policy for Implementing
Environmental Quality Systems (UFP-QS) and Mixed Analyte Performance Evaluation
Program (MAPEP).
Enhanced design criteria to consider safety into design.
Recommended Actions for Implementing DOE G 414.1-2B
The Office of Quality Assurance (HS-33) recommends that DOE elements and contractor
organizations take the following actions to ensure maximum benefit from the approach defined
in this Guide:
Make this Guide available to senior management responsible for establishing and
maintaining the QAP and the Integrated Safety Management System (ISMS).
Section 2
Make this Guide available to employees responsible for developing implementing processes
for these systems.
Consider this Guide when reviewing new and existing DOE and contractor QAPs.
Consider this Guide when planning and implementing Field Office QA assessments.
Provide feedback on the usefulness of this Guide to the Office of Quality Assurance (HS-33),
at 301-903-5452, colette.broussard@hq.doe.gov.
Existing DOE and contractor QAPs should be reviewed to verify that:
Applicable quality criteria are addressed and applied for mission accomplishment;
environment, safety and health; safety system software; and radiation protection programs
developed to meet the requirements of DOE O 414.1D and 10 C.F.R. Part 830 with regards
to safeguards and security work;
Appropriate national/international standards have been identified from the established
requirements set and adopted to implement the QAP; and
A senior management position with responsibility for the QAP is designated in the
organization and the person identified for this position is appropriately qualified (e.g., see
DOE-STD-1150-2002, Quality Assurance Functional Area Qualification Standard, dated
April 2002 (or latest version) for DOE qualification requirements).
AVAILABLE ONLINE AT: INITIATED BY:
https://www.directives.doe.gov Office of Health, Safety and Security
DOE G 414.1-2B
8-16-2011
Chg 1: 9-27-2011
Chg 2: 5-8-2013
QUALITY ASSURANCE
PROGRAM GUIDE
[This Guide describes acceptable, but not mandatory, means for complying with
requirements. Guides are not requirements documents and are not to be construed as
requirements in any audit or appraisal for compliance with associated rule or directives.]
U.S. Department of Energy
Washington, D.C. 20585
NOT
MEASUREMENT
SENSITIVE
DOE G 414.1-2B i (and ii)
8-16-11
FOREWORD
This Department of Energy (DOE) Guide is available for use by all DOE elements and their
contractors for use with DOE Order 414.1D, Quality Assurance, dated 4-25-11 and 10 C.F.R.
Part 830 Subpart A, Quality Assurance Requirements. DOE Guides are part of the DOE
Directives System and are issued to provide supplemental information regarding the
Department’s expectations of its requirements as contained in Rules, Orders, Notices, and
regulatory standards. Guides may also provide acceptable methods for implementing these
requirements. Guides are not substitutes for requirements, nor do they replace technical
standards that are used to describe established practices and procedures for implementing
requirements. This Guide should not be used as requirements in any audits or appraisals for
compliance with associated rules or directives.
Beneficial comments (recommendations, additions, deletions, and any other pertinent data)
or questions regarding this document should be sent to:
Colette A. Broussard
Office of Quality Assurance, HS-33
U.S. Department of Energy
1000 Independence Avenue, SW
Washington, DC 20585-1290
Phone (301) 903-5452
Fax (301) 903-6172
E-mail:colette.broussard@hq.doe.gov
Internet: http://www.hss.doe.gov
This Guide is available electronically on the DOE Directives System at the following address:
http://www.directives.doe.gov
DOE G 414.1-2B iii
8-16-11
Contents
Section 3
1.0 INTRODUCTION ........................................................................................................................ 1
2.0 APPLICATION ............................................................................................................................ 1
3.0 DISCUSSION ............................................................................................................................... 2
4.0 GUIDANCE FOR QUALITY ASSURANCE PROGRAMS ...................................................... 3
4.1 MANAGEMENT/CRITERION 1 – PROGRAM ..................................................................... 3
4.1.1 Introduction ........................................................................................................................ 3
4.1.2 Responsibilities .................................................................................................................. 4
4.1.3 Graded Approach ............................................................................................................... 4
4.1.4 Integrating the Safety Management and Quality Assurance Program ............................... 6
4.1.5 Integration of Quality Assurance Criteria into DOE ORDER 226.1B,
Implementation of DOE Oversight Policy ......................................................................... 7
4.1.6 Use of Technical Standards ............................................................................................. 10
4.2 MANAGEMENT/CRITERION 2 – PERSONNEL TRAINING AND
QUALIFICATION ................................................................................................................. 11
4.2.1 Introduction ...................................................................................................................... 11
4.2.2 Responsibilities ................................................................................................................ 11
4.2.3 Qualification of Personnel ............................................................................................... 12
4.2.4 Training ............................................................................................................................ 12
4.2.5 Training Plans .................................................................................................................. 13
4.3 MANAGEMENT/CRITERION 3 – QUALITY IMPROVEMENT ...................................... 13
4.3.1 Introduction ...................................................................................................................... 13
4.3.2 Quality Improvement Processes ...................................................................................... 14
4.4 MANAGEMENT/CRITERION 4 – DOCUMENTS AND RECORDS................................. 17
4.4.1 Introduction ...................................................................................................................... 17
4.4.2 Document Control System ............................................................................................... 17
4.4.3 Records Management System .......................................................................................... 17
Section 4
4.5 PERFORMANCE/CRITERION 5 – WORK PROCESSES ................................................... 18
4.5.1 Introduction ...................................................................................................................... 18
4.5.2 Work Performance ........................................................................................................... 18
4.5.3 Identification and Control of Items .................................................................................. 19
4.5.4 Item Protection ................................................................................................................. 19
4.6 PERFORMANCE/CRITERION 6 – DESIGN ....................................................................... 19
4.6.1 Introduction ...................................................................................................................... 19
4.6.2 Design Inputs ................................................................................................................... 20
4.6.3 Design Process ................................................................................................................. 20
4.6.4 Design Output .................................................................................................................. 21
4.6.5 Design Verification .......................................................................................................... 21
4.6.6 Design Changes ............................................................................................................... 21
4.7 PERFORMANCE/CRITERION 7 – PROCUREMENT ........................................................ 22
4.7.1 Introduction ...................................................................................................................... 22
iv DOE G 414.1-2B
8-16-11
4.7.2 Procurement Documents .................................................................................................. 23
4.7.3 Supplier Qualification ...................................................................................................... 23
4.7.4 Supplier Performance Monitoring ................................................................................... 24
4.7.5 Inspection of Procured Items ........................................................................................... 24
4.7.6 Supplier Documentation .................................................................................................. 25
4.7.7 Procurement of Safety-Related Items for Nuclear Facilities/Activities .......................... 25
4.7.8 Multi-Site Procurement .................................................................................................... 25
4.8 PERFORMANCE/CRITERION 8 – INSPECTION AND ACCEPTANCE TESTING ........ 26
4.8.1 Introduction ...................................................................................................................... 26
4.8.2 Process ............................................................................................................................. 26
4.8.3 Control of Measuring and Test Equipment ...................................................................... 26
4.8.4 Records ............................................................................................................................ 27
4.9 ASSESSMENT/CRITERION 9 – MANAGEMENT ASSESSMENT .................................. 27
Section 5
4.10 ASSESSMENT/CRITERION 10 – INDEPENDENT ASSESSMENT .................................. 28
5.0 GUIDANCE ON SUSPECT AND COUNTERFEIT ITEMS .................................................... 28
5.1 INTRODUCTION ................................................................................................................... 28
5.2 DOE ORDER 414.1D REQUIREMENTS AND IAEA-TECDOC-1169 MATRIX .............. 28
5.3 RESPONSIBILITY IN REPORTING .................................................................................... 32
5.4 OCCURRENCE REPORTING AND INFORMATION EXCHANGE ................................ 32
5.4.1 Reporting Suspect Counterfeit Items Discovery .............................................................. 32
5.4.2 Government-Industry Data Exchange Program ............................................................... 33
5.4.3 Consultation with Office of General Counsel .................................................................. 33
5.4.4 Suspect Counterfeit Items Review, Analysis, and Notification ....................................... 33
5.5 REPORTING SUSPECT COUNTERFEIT ITEMS TO DOE OIG ....................................... 36
5.5.1 Authority .......................................................................................................................... 36
5.5.2 Reporting Suspect Counterfeit Items to OIG ................................................................... 36
5.5.3 Successfully Prosecuting Suspect Counterfeit Items Cases ............................................. 38
APPENDIX A: QUALITY ASSURANCE PROGRAM REVIEW AND APPROVAL
TEMPLATE
APPENDIX B: REFERENCES
APPENDIX C: DEFINITIONS
APPENDIX D: ACRONYMS
ATTACHMENT 1: QUALITY ASSURANCE ASSESSMENT PLAN TEMPLATE
DOE G 414.1-2B 1
8-16-11
1.0 INTRODUCTION
To accomplish the Department of Energy’s (DOE) missions and objectives, DOE and its
contractors are responsible for the management and oversight functions of a wide range of work
activities, including basic and applied research; product development; design, construction,
operation, modification, decommissioning, and environmental remediation of DOE facilities and
sites. This work should be accomplished safely while minimizing potential hazards to the public,
site or facility workers, and the environment consistent with the quality assurance (QA)
requirements of DOE Order (O) 414.1D, Quality Assurance, dated 4-25-11, and10 C.F.R. Part
830, Subpart A, Quality Assurance Requirements. The quality criteria of DOE O 414.1D and 10
C.F.R. Part 830 Subpart A provide the requirements for a Quality Assurance Program (QAP)
which ensures work is consistent with DOE requirements and expectations.
This Guide (G) revises and supersedes DOE G 414.1-2A, Quality Assurance Management
System Guide for Use with 10 C.F.R. 830 Subpart A, Quality Assurance Requirements, and DOE
O 414.1C, Quality Assurance, dated 6-17-05. This Guide also consolidates relevant guidance
from and cancels DOE G 414.1-3, Suspect/Counterfeit Items Guide for Use with 10 C.F.R. 830,
Subpart A, Quality Assurance Requirements, and DOE O 414.1B, Quality Assurance, dated 11-
3-04, and DOE G 414.1-5, Corrective Action Program Guide, dated 3-2-06.
International Atomic Energy Agency (IAEA) TECDOC-1169, Managing Suspect and Counterfeit
Items in the Nuclear Industry, dated August 2000, has been added as a reference to provide
guidance on suspect and counterfeit item(s) (S/CI(s)). Reporting of S/CIs has been added to
Section 5.0 of this Guide.
Section 6
All software use and development should meet the applicable QA requirements using a graded
approach as described in this Guide. In addition, safety software, as defined in DOE O 414.1D,
should follow DOE G 414.1-4, Safety Software Guide for Use with 10 C.F.R. 830, Subpart A,
Quality Assurance Requirements and DOE O 414.1C, Quality Assurance, dated 6-17-05, to meet
DOE QA requirements described in Attachment 4 of DOE O 414.1D.
For additional guidance on management and independent assessments, see DOE G 414.1-1B,
Management and Independent Assessments Guide for Use with 10 C.F.R. Part 830, Subpart A,
and DOE O 414.1C, Quality Assurance, DOE M 450.4-1, Integrated Safety Management
Systems Manual; and DOE O 226.1A, Implementation of Department of Energy Oversight
Policy, dated 9-27-07. For additional guidance on project QA, see DOE G 413.3-2, Quality
Assurance Guide for Project Management, dated 6-27-08.
2.0 APPLICATION
This Guide provides information on principles, requirements, and practices used to establish and
implement an effective QAP for both non-nuclear and nuclear facilities consistent with the
requirements of DOE O 414.1D and 10 C.F.R. Part 830 Subpart A, hereafter referred to as the
QA Order and the QA Rule, respectively. Additional resources are available at:
http://www.hss.doe.gov/nuclearsafety/qa.
2 DOE G 414.1-2B
8-16-11
This Guide may also be used by a contractor to assist in obtaining QAP approval from its DOE
customer. If this Guide is in conflict with any Regulations, Orders or any contractor
requirements document (CRD), the Regulation, Order, or CRD takes precedence.
The methods and references described in this Guide are not mandatory and do not add,
modify, or delete any requirements identified in the QA Order and QA Rule. Use of this
Guide in conjunction with appropriate standards will facilitate development and approval of a
QAP compliant with the QA Order and QA Rule. An organization may select alternative
methods to document and implement its QAP as long as the QA regulatory requirements in
the QA Rule and the additional QA requirements in the QA Order are satisfied for nuclear
facilities, and all QA requirements in the QA Order are satisfied for non-nuclear facilities.
The content of the QAP should be based on an organization’s unique set of responsibilities,
products and services, hazards, and customer expectations.
NOTE: Throughout this document, when the QA Rule is mentioned, the QA requirements
from the QA Rule pertain to nuclear facilities/work only. The QA Order also contains
requirements that are not found in the QA Rule (i.e., S/CI and safety software quality
assurance (SSQA)). The S/CI requirements are applicable to both nuclear and non-nuclear
work. The SSQA requirements are only applicable to nuclear facilities or nuclear work.
This guidance includes methods for the interrelated functions and responsibilities of
managing, performing, and assessing work. Implementation of a QAP will contribute to
improved safety, quality, management, and reliability of DOE products and services.
3.0 DISCUSS ION
The quality of a product or service is the extent to which that product or service satisfies the
requirements, needs, and expectations of the customer. As used in this Guide, the term
“customer” includes those entities that receive products and services from the organization. The
attainment of quality is the responsibility of each member of an organization. The quality
criteria of the QA Order and QA Rule provide the framework for a results-oriented management
system that focuses on performing work safely and meeting mission and customer expectations
while allowing the organization to become more efficient through process improvement.
Section 7
DOE’s objective is to accomplish its missions while simultaneously satisfying the QA Order,
integrated safety management system (ISMS), policies and regulations, and the QA Rule (if
performing nuclear work). The development and implementation of a QAP, which is
implemented throughout the organization, will improve performance and provide assurance
that the applicable requirements are being satisfied. The implementation of QA requirements
are achieved using a graded approach.
The QA requirements in the QA Order (i.e., the 10 criterion) apply to all software. Calculations
and results derived from software should meet the applicable requirements using a graded
approach as described in Section 4.1.3 of this Guide. Other available guidance is found in the
American Society of Mechanical Engineers (ASME) NQA-1, Quality Assurance Requirements
for Nuclear Facility Applications, Subpart 4.1, Application Appendix: Guide on Quality
DOE G 414.1-2B 3
8-16-11
Assurance Requirements for Computer Software. In addition, SSQA guidance can be found in
DOE G 414.1-4, Safety Software Guide and in ASME NQA-1, Subpart 2.7, Quality Assurance
Requirements for Computer Software for Nuclear Facility Applications. For definitions of
software and safety software, see the QA Order.
4.0 GUIDANCE FOR QUALITY ASSURANCE PROGRAMS
4.1 MANAGEMENT/CRITERION 1 – PROGRAM
4.1.1 Introduction
The QA Order and the QA Rule require that an organization develop, document, implement, and
maintain an effective QAP. The goal of the QAP is delivery of safe, reliable products and
services that meet or exceed the customer’s requirements, needs, and expectations. The QAP is
defined as the overall program or management system established to assign responsibilities and
authorities, define policies and requirements, and provide for the performance and assessment of
work. Defining the proper structure for the organization and the management processes
necessary to conduct work within the organization is critical to assure that work can be
controlled and conducted safely. This allows the organization to efficiently conduct work safely,
as well as meeting or exceeding applicable requirements and expectations.
4.1.1.1 Organization
The first part of developing a management system is to define the organization and its
responsibilities. A well-defined organization allows individuals to understand its structure, how
it operates, and provides for the desired effectiveness within the organization. Organizations
should be defined and documented in sufficient detail. This allows those inside and outside the
organization to adequately identify its structure, roles and responsibilities, and the authorities
assigned to the individuals within the organization. In addition, interfaces within the
organization should be defined in order to avoid “stove piping” and a lack of communication
between organizational elements.
4.1.1.2 Quality Assurance Program/Management System
The criteria of the QA Order and the QA Rule prescribe a comprehensive management system
for DOE work. Work should be properly defined in order to ensure that it is controlled,
conducted safely, on time, and that it meets applicable requirements established by the customer,
government agencies, and those internal to the organization. Organizations should establish and
define documented processes that identify how the organization takes requirements for work. In
addition, the organization should develop the necessary analysis, plans, strategies, and courses of
action. Management should evaluate these processes on a periodic basis to assure that they
remain up to date and that they remain useful and effective in allowing the organization to
efficiently meet its commitments.
Section 8
The focus of the QAP should be to properly and safely accomplish the DOE mission. The QAP
should be integrated with the ISMS as described in DOE P 450.4, Integrated Safety Management
4 DOE G 414.1-2B
8-16-11
Policy, dated 4-25-11, and DOE Acquisition Regulation 48 C.F.R. 970.5204-2 [i.e., the DEAR
ISMS clause].
4.1.2 Responsibilities
The QAP should describe the organizational structure and interfaces, functional responsibilities,
and levels of authority. The role of DOE and contractor senior management is to establish and
cultivate principles that integrate quality requirements into daily work. Management is
responsible for leadership and commitment to quality achievement and improvement in a way
that ensures the safety of the public, workers, and the environment. Management retains the
primary responsibility and accountability for the scope and implementation of the QAP.
However, every individual in the organization is responsible for achieving quality in his or her
activities. Senior management should require and cultivate the achievement and improvement of
quality at all levels of the organization and ensure that the QAP is understood and implemented.
In addition, senior management is responsible for establishing the processes, including planning,
scheduling, and providing resources for the work. DOE and contractor senior management
should ensure flow down of the QA requirements and responsibilities throughout all levels of the
organization. In addition, DOE should ensure proper oversight of the flow down of requirements
by their contractors to subcontractors, vendors and suppliers.
Management should promote effective achievement of performance objectives through
integrated implementation of the QAP and ISMS.
4.1.3 Graded Approach
A graded approach to implementing the QAP complies with requirements, rules, and regulations,
and cannot compromise public, employee, or facility safety or adversely impact the environment.
The graded application of facility/activity requirements is dependent on the hazards and/or level
of risk associated with the activity or structures, systems, and components (SSCs) under
consideration. The scope, depth, and rigor of the QAP’s application of requirements should be
determined by the use of a grading process, before performing the activity. The purpose of
grading is to select the controls and verifications to be applied to various items and activities
consistent with their importance to safety, cost, schedule, and success of the program. Care
should be taken to not double grade. Once the requirements (technical and quality) are specified
in the technical procurement documents, the grading should have been done and this becomes
the set of requirements that should be met.
Consider the use of grading if a single or uniform method of applying a requirement across a
facility or activity does not add value or reduce risk. The grading process provides the
flexibility to design controls that best suit the facility or activity. The grading process is not
used to obtain exemptions from the requirements of the QA Order or the QA Rule.
The grading process is used to determine the appropriate controls to address and mitigate
hazards and/or risks. This process is accomplished by deliberate quality planning and is based
on activity-specific or facility-specific factors such as:
DOE G 414.1-2B 5
8-16-11
Section 9
the relative importance to safety, safeguards, and security;
the magnitude of any hazard or risk involved;
the life-cycle stage of a facility or activity;
impact/consequences on the programmatic mission of a facility;
the particular characteristics of a facility or activity;
the relative importance of radiological and non-radiological hazards; and
any other relevant factors.
The first step in the grading process is to identify the hazards, consequences, and probability of
failures for the work being performed. The second step is to specify the requirements and
controls to be applied. The third step is to determine the depth, extent, and degree of rigor
necessary in the application of the requirements and controls. The final step is to communicate
and implement the appropriate requirements and controls. The necessary degree of rigor should
be applied by means of documented work processes (procedures, instructions, specifications, and
controls). The logic, method of implementation, and basis for grading should be documented in
the QAP, periodically reviewed in light of changes that may have occurred, and, if appropriate,
revised to reflect those changes.
The graded approach cannot be used to “grade quality assurance criterion to zero,” which has
the effect of eliminating all verifications of the requirement (“to get out of work”). Even in
the least stringent application, compliance with applicable portions of stated requirements is
mandatory unless an exemption is approved through an appropriate process.
When considering the use of grading of an item or activity, it is important to consider the
impact of safety on personnel, the public, and the environment. The safety class or safety
significance of the item or activity is critical to the amount of controls imposed which are
necessary to assure the requisite or desired quality.
Risk is a fundamental consideration in determining the extent to which controls should be
applied at the facility level. The varying degrees of the controls applied should be dependent
upon function, complexity, consequence of failure, reliability, repeatability of results, and
economic considerations. These controls are documented and communicated to
facility/activity personnel to ensure appropriate application. This documentation should take
the form of written procedures, practices, requirements documents, policy statements,
standing orders, or other written and controlled means as deemed appropriate by
facility/activity management. The level of approval of this documentation is also based on the
hazards, complexity, and/or relative risk.
Based on an evaluation using these risk factors as applicable, the QAP requirements may be
selected for DOE and NNSA funded facilities, activities or organizations. Depending on the
evaluation, the applicable QAP requirements could be extensive and very prescriptive or few
with only limited prescription requirements or few with a combination of limited and very
prescriptive requirements. As examples, if a contractor is tasked with designing a safety-
related or mission important item or facility, the most important QAP requirement would be
the design control processes, consequently the specified QAP requirements would likely
include ASME NQA-1 Requirement 3, Design Control, requirements as well as less
6 DOE G 414.1-2B
8-16-11
Section 10
prescriptive requirements for organization, training, document control, records and
assessments. If this task was managed by a Headquarter organization, their specified QAP
would emphasize the review and acceptance of deliverables, performance of contractor
assessments (technical and QAP) and less prescriptive requirements for organization, training,
and records.
In contrast with the example of a contractor responsible for a single design would be a
contractor assigned the task of constructing or modifying a safety-related or mission
important facility. Due to the risks associated with these facilities, all applicable requirements
of a national consensus standard, such as ASME NQA-1, would be specified with the possible
exception of Requirement 3 regarding design control. Assuming this work is managed by a
Site Office, their QAP would emphasis training, and the review, inspection and the
assessment of the contractor activities. The Site Office QAP could designate NQA-1, graded
as appropriate, or an International Organization for Standardization (ISO) as the standard to
implement the QA requirements. (Additional examples of grading are provided in ASME
NQA-1, Subpart 4.2, Guidance on Graded Application of Quality Assurance (NQA) Standard
for Research and Development.)
4.1.4 Integrating the Safety Management and Quality Assurance Program
The QAP should be integrated with the ISMS, as described in DOE P 450.4A, Integrated Safety
Management Policy, dated 4-25-11 and DOE Acquisition Regulation 48 C.F.R. § 970.5204-2.
The QAP provides processes and tools for ensuring that ISMS objectives are achieved. DOE P
450.4A expresses a fundamental expectation that work will be performed safely.
The ten criteria of the QA Order and the QA Rule define the generic elements of a management
system applicable to DOE work. They are implemented using a graded approach based on an
evaluation of the risks associated with the work to be performed. The Safety Management
System (SMS) defined in DOE O 450.2, Integrated Safety Management, dated 4-25-11,
selectively applies and amplifies the generic management system requirements defined in by the
ten criteria to ensure that DOE work is performed safely.
This also ensures that workers, the environment, and the public are reasonably protected from
harm. At the organizational or institutional level, the DOE quality and safety requirements share
a management systems approach (see Table 1 below) to achieving their objectives. Therefore,
the required system documentation for each ISMS description and QAP may be integrated into a
single document to describe how the organization intends to implement the requirements. In
some cases, the local DOE office (Site Office or Field Element) and contractor may determine
that maintaining both an ISMS description and a QAP is expedient. In such cases, at a
minimum, the implementing mechanisms that are described in each should be integrated to the
maximum extent practical, and the system description and the QAP should cross-reference these
procedures as applicable. For example, the processes and procedures for conducting
management assessments should be referenced in both the QAP and the ISMS description. The
table shown below is representative of criteria that apply, but is not all inclusive.
DOE G 414.1-2B 7
8-16-11
Table 1: Integration of QA Criteria into the Safety Management System (SMS)
Principles and Functions
QA Criteria
P
ro
gr
am
Section 11
Tr
ai
n
in
g
an
d
Q
u
al
if
ic
at
io
n
Q
u
al
it
y
Im
p
ro
ve
m
en
t
D
o
cu
m
en
ts
a
n
d
R
e
co
rd
s
W
o
rk
P
ro
ce
ss
es
D
es
ig
n
P
ro
cu
re
m
en
t
In
sp
ec
ti
o
n
/A
cc
ep
ta
n
ce
Te
st
in
g
M
an
ag
em
en
t
A
ss
e
ss
m
en
t
In
d
ep
en
d
en
t
A
ss
e
ss
m
en
t
SMS Principles and Functions
Principles
1. Line Management Responsibility for Safety X X X
2. Clear Roles and Responsibilities X X X X X
3. Competence Commensurate with Responsibilities X X
4. Balanced Priorities X X X
5. Identification of Safety Standards and Requirements X X X X X X
6. Hazard Controls Tailored to Work Being Performed X X X
7. Operations Authorization X X
Core Functions
1. Define the Scope of Work X X X X
2. Analyze the Hazards X X
3. Develop and Implement Hazard Controls X X
4. Perform Work Within Controls X X X
5. Provide Feedback and Continuous Improvement X X X X X
Note: X indicates cross reference delineating (a) when the QA criteria and the principle/function have shared intent or (b) when the QA
criterion is applied to the ISMS principle or function.
If the implementation of QA requirements in ISMS overlaps closely, then use the same
implementation process for both. Likewise, a single process (e.g., procedures and plans) that
satisfies quality and safety requirements at the facility level and the activity level should be used.
DOE G 450.4-1C, Integrated Safety Management System Guide, dated 9-29-11, contains
information on safety management principles, supporting attributes, references, and integration
methods.
4.1.5 Integration of QA Criteria into DOE O 226.1B, Implementation of DOE Oversight
Policy
DOE has the responsibility to perform oversight on DOE programs to ensure safe operations at
the department facilities and activities. Table 2 below is an example of how oversight
requirements overlap with QA requirements.
8 DOE G 414.1-2B
8-16-11
Table 2: Integration of QA Criteria into DOE O 226.1B, Implementation of DOE
Oversight Policy
QA Criteria
P
ro
gr
am
Tr
ai
n
in
g
an
d
Q
u
al
if
ic
at
io
n
Q
u
al
it
y
Im
p
ro
ve
m
en
t
D
o
cu
m
en
ts
a
n
d
R
e
co
rd
s
W
o
rk
P
ro
ce
ss
es
D
es
ig
n
P
ro
cu
re
m
en
t
In
sp
ec
ti
o
n
/A
cc
ep
ta
n
ce
Te
st
in
g
M
an
ag
em
en
t
A
ss
e
ss
m
en
t
In
d
ep
en
d
en
t
A
ss
e
ss
m
en
t
DOE O 226.1 REQUIREMENTS
4 REQUIREMENTS
a. All applicable DOE organizations must:
1) Establish and implement an effective oversight program
consistent with DOE O 226.1B and the requirements of this
order
X X X X X X
2) Maintain sufficient technical capability and knowledge of site
and contractor activities to make informed decisions about
hazards, risks and resource allocation; provide direction to
contractors; and evaluate contractor performance
X X
b. Oversight processes implemented by applicable DOE line management
organizations must:
1) Evaluate contractor and DOE programs and management
systems, including site assurance systems, for effectiveness of
performance (including compliance with requirements). Such
evaluations must be based on the results of operational
awareness activities; assessments of facilities, operations, and
programs; and assessments of the contractor’s assurance system.
The level and/or mix (i.e., rigor or frequency in a particular area)
of oversight may be tailored based on considerations of hazards,
the maturity and operational performance of the contractor’s
programs and management systems.
Section 12
X X X
2) Include written plans and schedules for planned assessments,
focus areas for operational oversight, and reviews of the
contractor’s self‐assessment of processes and systems. Address
the role of the Central Technical Authorities and their support
staff for core nuclear safety functions.
X X X X
3) Include DOE Headquarters line organizations’ conduct of
oversight processes that are focused primarily on their DOE Field
Elements, including reviewing contractor activities to the extent
necessary to evaluate the implementation and effectiveness of
the Field Element’s oversight of its contractors.
X X X X
DOE G 414.1-2B 9
8-16-11
QA Criteria
P
ro
gr
am
Tr
ai
n
in
g
an
d
Q
u
al
if
ic
at
io
n
Q
u
al
it
y
Im
p
ro
ve
m
en
t
D
o
cu
m
en
ts
a
n
d
R
e
co
rd
s
W
o
rk
P
ro
ce
ss
es
D
es
ig
n
P
ro
cu
re
m
en
t
In
sp
ec
ti
o
n
/A
cc
ep
ta
n
ce
Te
st
in
g
M
an
ag
em
en
t
A
ss
e
ss
m
en
t
In
d
ep
en
d
en
t
A
ss
e
ss
m
en
t
DOE O 226.1 REQUIREMENTS
4) Include an issues management process that is capable of
categorizing findings based on risk and priority, ensuring relevant
line management findings are effectively communicated to the
contractors, and ensuring that problems are evaluated and
corrected on a timely basis. The issues management process
must ensure for issues categorized as high significance findings:
X X
a) A thorough analysis of the underlying causal factors is
completed
X X
b) Corrective actions that will address the cause(s) of the
findings and prevent recurrence are identified and
implemented;
X X
c) After completion of a corrective action or a set of corrective
actions, the conduct of an effectiveness review using trained
and qualified personnel that can verify the corrective
action/corrective action plan has been effectively
implemented to prevent recurrences;
X X
d) Documentation of the analysis process and results described
in (a) and maintenance tracking to completion of plans and
schedules for the corrective actions and effectiveness
reviews described in (b) and (c) above, in a readily accessible
system; and
X X
e) When findings and/or corrective actions apply to more than
one Secretarial Office, a lead office is appointed by mutual
agreement between the affected Secretarial Officers.
X X
5) Be tailored according to the effectiveness of contractor
assurance systems, the hazards at the site/activity, and the
degree of risk, giving additional emphasis to potentially high
consequence activities.
X
c. DOE line management must establish and communicate performance
expectations to contractors through formal contract mechanisms. Such
expectations (e.g., safety performance measures and commitments)
must be established on an annual basis, or as otherwise required or
determined appropriate by the Field Element.
X X
d. DOE line management must have effective processes for
communicating oversight results and other issues in a timely manner
up the line management chain, and to the contractor as appropriate,
sufficient to allow senior managers to make informed decisions.
X X X X X
10 DOE G 414.1-2B
8-16-11
QA Criteria
P
ro
gr
am
Tr
ai
n
in
g
an
d
Q
u
al
if
ic
at
io
n
Q
u
al
it
y
Im
p
ro
ve
m
en
Section 13
t
D
o
cu
m
en
ts
a
n
d
R
e
co
rd
s
W
o
rk
P
ro
ce
ss
es
D
es
ig
n
P
ro
cu
re
m
en
t
In
sp
ec
ti
o
n
/A
cc
ep
ta
n
ce
Te
st
in
g
M
an
ag
em
en
t
A
ss
e
ss
m
en
t
In
d
ep
en
d
en
t
A
ss
e
ss
m
en
t
DOE O 226.1 REQUIREMENTS
e. For activities and programs at Government‐owned and Government‐
operated facilities and sites that are not under the cognizance of a DOE
Field Element, DOE Headquarters program offices must establish and
implement comparably effective oversight processes consistent with
requirements for the contractor assurance system (see Attachment 1 of
this Guide) and DOE line management oversight processes.
X X
Note: X indicates cross‐reference delineating when the QA criteria are applied to the requirements DOE O 226.1B.
4.1.6 Use of Technical Standards
The Government-wide philosophy of using performance expectations in combination with
national and international consensus standards is consistent with the National Technology
Transfer and Advancement Act of 1995 (P.L. 104-113), Office of Management and Budget
(OMB) Circular A-119, Federal Participation in the Development and Use of Voluntary
Consensus Standards and in Conformity Assessment Activities, and DOE O 252.1A, Technical
Standards Program, dated 2-23-11.
The QA Order requires the QAP to clearly identify which standards, or parts of the standards, are
used to address the requirements. ASME NQA-1, Subpart 4.5, Application Guide on the Use of
NQA-1-2008/1a-2009 for Compliance with Department of Energy Quality Assurance
Requirements 10 CFR 830 Subpart A and DOE O 414.1, provides additional guidance on
identifying gaps between DOE QA requirements and NQA-1 requirements. Additional guidance
can also be found in the Energy Facility Contractors Group (EFCOG) publication titled EFCOG
White Paper on NQA-1 Part II Application at
http://www.efcog.org/wg/ism/docs/EFCOG_White_Paper_on_NQA-1_Subpart_2%20.pdf.
4.1.7 Other Appropriate Quality Program Guidance
4.1.7.1 Uniform Federal Policy for Implementing Environmental Quality Systems
In many cases, the particular standards to be used are specified by the customer. The standards
selected should suit the products and services of the organization and its customers. One
example is the use of the Intergovernmental Data Quality Task Force Uniform Federal Policy for
Implementing Environmental Quality Systems Evaluating, Assessing, and Documenting
Environmental Data Collection/Use and Technology Programs, Version 2, March 2005 (UFP-
QS). The UFP-QS outlines essential elements of a quality system (see definition of Quality
System in Appendix C of this Guide) for management of environmental data collection and use.
DOE G 414.1-2B 11
8-16-11
The UFP-QS provides a framework to ensure that essential elements of a quality system are
addressed. The UFP-QS should be used to develop a new Quality System or to evaluate the
adequacy of an existing quality system. The results of that evaluation should be used to develop
plans for correcting identified deficiencies in the quality system.
The UFP-QS policy was developed as a joint initiative between the U.S. Environmental
Protection Agency (EPA), the Department of Defense (DoD), and the Department of Energy
(DOE) to resolve data quality inconsistencies and/or deficiencies in quality systems. The UFP-
QS represents a voluntary consensus policy.
The benefits of the use of the UFP-QS across Federal agencies include:
Section 14
improved effectiveness of Federal environmental programs by focusing on results, quality of
data and services, and customer satisfaction;
clarification of roles and responsibilities in managing and overseeing environmental data and
environmental technology programs;
sufficient confidence in the systems such that duplication of oversight efforts are minimized;
and
enhanced accountability and public confidence in environmental decisions.
4.1.7.2 The Department of Energy’s Mixed Analyte Performance Evaluation Program
Analytical laboratories providing environmental analyses on behalf of DOE should participate in
an approved proficiency testing program such as DOE’s corporate Mixed Analyte Performance
Evaluation Program (MAPEP). The purpose of MAPEP is to foster reliability and credibility for
the analytical results used in the decision making process, particularly for those decisions
affecting the environment, public health, and safety. Proficiency testing should be conducted on
a semi-annual basis for radiological, inorganic, and organic constituents in various
environmental media. Liquid MAPEP samples are prepared from radiological and stable
inorganic standards traceable to the National Institute of Standards and Technology (NIST).
Final concentrations for these analytes are calculated from the NIST certified standard value and
the standard dilution(s) used. Solid samples are prepared from natural soil matrices spiked with
NIST traceable standards for the various analytes of interest. For more information, see
http://www.hss.doe.gov/CSA/analysis/asp/index.html.
4.2 MANAGEMENT/CRI TERION 2 – PERSONNEL TRAINING AND
QUALIFICATION
4.2.1 Introduction
Qualification and training processes ensure that personnel achieve and maintain the
required capabilities to perform their work.
4.2.2 Responsibilities
Management is responsible for committing resources to facilitate the training and qualification
12 DOE G 414.1-2B
8-16-11
processes for personnel in their organizations and ensuring that personnel hired or transferred
into positions meet the appropriate requirements. Each level of the organization should
adequately describe its training and qualification needs including the need for continued training
to maintain job proficiency. These descriptions should include requirements, interfaces, training
methods, training responsibilities, and duties of line and training organizations.
4.2.3 Qualification of Personnel
Policies and procedures that describe personnel selection, training, and qualification
requirements should be established for each function and follow Federal, State, and local
guidelines, as applicable. These should include the minimum applicable requirements for
education, experience, skill level, and physical condition. For example, DOE personnel
responsible for oversight of QA at defense nuclear facilities are qualified per requirements of
DOE O 426.1, Federal Technical Capability, dated 11-19-09, Chg 1: 9-20-11. Likewise, the
contractor requirements in DOE O 426.2, Personnel Selection, Training, Qualification and
Certification Requirements for DOE Nuclear Facilities, dated 4-21-10, establishes selection,
training, qualification, and certification requirements for contractor personnel who can impact
the safety basis through their involvement in the operation, maintenance, and technical support
of Hazard Category 1, 2, and 3 nuclear facilities. In accordance with the requirements in DOE O
426.1, senior management’s workforce analyses should identify QA and Software Quality
Assurance (SQA) positions as critical technical positions. QA and SQA positions have
responsibilities related to the safe operation of the facility and require specialized skills.
Section 15
Before personnel are allowed to work independently, management should ensure personnel have
the necessary experience, knowledge, skills, and abilities. Personnel should be qualified based
on factors such as:
previous experience, education, and training;
performance demonstrations or tests to verify previously acquired skills;
completion of training or qualification programs; and/or
on-the-job training.
4.2.4 Training
Training assists personnel in acquiring knowledge of the correct and current processes and
methods to accomplish assigned tasks. It enables personnel to understand the fundamentals of
the work, the associated hazards, the context within which the work is performed, and the reasons
for any special work requirements. Training should also include appropriate stop work
responsibility/authority and action/response in abnormal/emergency situations. Initial training
should prepare personnel to perform their job. Continuing training should maintain and promote
improved job performance and proficiency. Training can be grouped into the following
categories:
1. Project-/task-specific training should impart the knowledge required for personnel to
perform their assigned duties safely and successfully. This training may include
project/task goals and schedules, implementing procedures, safety and hazard controls,
DOE G 414.1-2B 13
8-16-11
methods, requirements, process metrics, and skills. Project/task-specific training
requirements should be defined by project managers and the workers.
2. Site-/facility-specific training should convey the safety, emergency plans, security, and
operations information necessary for personnel to prepare for and perform their
assigned duties in the site/facility. Management is responsible for defining training
requirements and ensuring that the training is administered.
3. Institutional training should convey general information about the organization’s
mission, vision, goals, and management system, including a QAP overview. It may also
include general knowledge or skills training.
4. QA personnel training should deliver knowledge of the QA requirements. For Federal
employees performing oversight for nuclear facilities, DOE O 414.1D requires the use of
DOE-STD-1150-2002, Quality Assurance Functional Area Qualification Standard,
dated April 2002. This standard can be used for qualifying other QA personnel as well.
5. Safety software QA personnel training should provide knowledge of safety software
requirements. For Federal employees performing oversight for nuclear facilities, DOE O
414.1D requires the use of DOE-STD-1172-2011, Safety Software Quality Assurance
Functional Area Qualification Standard. This standard can be used for qualifying other
safety software quality personnel.
6. Weapon QA personnel training should provide knowledge of the NNSA requirements.
For Federal employees performing oversight for nuclear facilities, DOE O 414.1D
requires the use of DOE-STD-1025-2008, Weapon Quality Assurance Qualification
Standard.
Contact the National Training Center (NTC) for additional training available at
http://NTC.DOE.gov.
4.2.5 Training Plans
Training plans should:
be prepared for personnel responsible for managing, planning, performing, controlling, and
overseeing work;
be based on the function and responsibilities of the job and any specific qualification
requirements;
be based on current facility, site, or organization procedures; technical and professional
references; and past organization/industry experience;
Section 16
consider changes in hazard conditions, technology, work methods, and job responsibilities;
and
specify the type of training records to be maintained.
4.3 MANAGEMENT/CRI TERION 3 – QUALITY IMPROVEMENT
4.3.1 Introduction
Efforts related to quality improvement are intended to identify, control, and improve items,
services, and processes. Improvement processes also detect and prevent problems while
14 DOE G 414.1-2B
8-16-11
identifying the causes of problems and work needed to prevent recurrence of problems through
corrective actions. The quality improvement process is a disciplined management process based
on the premise that all work can be planned, performed, measured, and improved. Management
should ensure that the focus is on improving the quality of products, processes, and services by
establishing priorities, promulgating policy, promoting cultural aspects, allocating resources,
communicating lessons learned, and resolving significant management issues and problems that
can hinder the organization from achieving its objectives. Management should balance safety
and mission priorities when considering improvement actions, and implement safety and ISMS
for their operations and work practices, based on the ISM guiding Principles provided in DOE P
450.4A.
Management should encourage employees to plan, develop, explore, and implement new ideas
for improving products, processes, and services. Management commitment can be demonstrated
by empowering employees to:
identify and report problems;
identify opportunities for improvement;
identify “best management practices;”
develop alternative approaches for addressing problems and recommend improvements
(e.g., reducing process variability or cycle time);
implement the approved solution;
evaluate the improvement; and
provide lessons learned to other organizations.
Identified problems and other related information (both positive and negative) from internal
and external sources should be reviewed and analyzed to identify improvement opportunities.
Implemented improvements should be monitored and methods established to verify their
effectiveness.
4.3.2 Quality Improvement Processes
An effectively planned and implemented QAP is one that:
uses feedback to improve items, services and the associated processes that produce
them;
prevents or minimizes quality problems;
corrects problems that occur;
measures the effectiveness of corrective actions; and
uses performance measures to identify strengths and weaknesses.
Preventive action minimizes the occurrence of quality problems through appropriate design,
inspection, procurement, and other process controls and assessment activities. DOE and
contractor organizations should prioritize and focus their resources on preventive actions and
on those quality problems that have the greatest potential for:
posing adverse safety risks to the environment and human health;
DOE G 414.1-2B 15
8-16-11
impacting the reliability of operations and products; and
affecting the ability to meet customer requirements.
As used in this Guide, a quality problem is a collective term that may be:
a deficiency in an activity, product, service, item characteristic, or process parameter;
a noncompliance to a requirement;
an indeterminate/substandard condition, or a suspect/counterfeit item (S/CI) as defined in
IAEA-TECDOC-1169; or
conditions adverse to quality and/or significant conditions adverse to quality.
Section 17
4.3.2.1 Quality Feedback
Work activities and management systems can be continuously improved through assessment and
feedback processes. Effective feedback from multiple sources is the foundation for processes
designed to prevent, identify, and correct problems. The least desirable form of feedback results
from accidents or unplanned events that self-disclose the quality problem. The process should
include the use of lessons learned from the local organization and other organizations. Identified
improvement actions should also be shared with other organizations. Management should track
the actions to closure and ensure that the actions are effective in providing the anticipated
improvements. Implementing effective feedback processes can support meeting the
requirements for the ISM core function on providing feedback and continuous improvement.
Additionally, contractors at DOE facilities should develop and maintain implementing
procedures for the occurrence reporting and utilization of the requirements stated in DOE O
232.2, Occurrence Reporting and Processing Operations Information, dated 1-1-12. This
directive requires that all notifications to DOE be timely in accordance with the significance of
the occurrence and that the written notification contain appropriate information describing the
occurrence, significance, causal factors, and corrective actions.
DOE’s Noncompliance Tracking System (NTS), operated and managed by DOE’s Office of
Enforcement, is another source of information for feedback on quality-related events. NTS is
DOE’s centralized, web-based system that allows contractors to voluntarily report non-
compliances of nuclear safety and worker safety, and health regulations, including the QA Rule.
See http://www.hss.doe.gov/enforce/Final_EPO_June_2009_v4.pdf for more information.
4.3.2.2 Identification of Problems Affecting Quality
Problems affecting quality may be identified by internal organization sources (e.g., workers,
customers, suppliers) or external sources (e.g., customers, regulators). Once identified, problems
should be documented and evaluated to determine their significance. The method for
determining the significance of a problem and the process for handling problems should be
documented as part of the QAP.
The causes of problems should be investigated and identified. Causes should be corrected to
prevent recurrence of the problem. For straightforward problems, a simpler apparent cause
16 DOE G 414.1-2B
8-16-11
process may be appropriate. For more serious or complex problems, a disciplined root cause
analysis with a formal extent of condition review should be considered.
Problems that are not significant, but can be readily corrected, should be identified and
documented (e.g., by logging). These types of problems may be handled in an expedient
manner that may not necessarily need to follow the more formal processes for problem
documentation (e.g., nonconformance report) disposition and corrective action.
Safety software problems have specific guidance in DOE G 414.1-4.
4.3.2.3 Corrective Action/Resolution of Problems Affecting Quality
Problems which affect quality may be referred to as conditions adverse to quality and/or
significant conditions adverse to quality, should be identified and corrected as soon as possible.
The identification and reporting process should be documented and include a standard
categorization of problem findings based on significance, criticality, severity, and potential
impact on the safety, security, and mission of the site/organization. A corrective
action/resolution process should consist of the appropriate steps, such as (the list is neither all
inclusive nor limited to):
Section 18
identifying a condition adverse to quality, and/or significant condition adverse to quality;
taking appropriate actions as required to mitigate, stabilize and/or prevent further progression
of unsafe conditions or conditions adverse to quality;
documenting the condition adverse to quality and/or significant condition adverse to quality;
evaluating its significance and extent;
analyzing the problem and determining its causes;
reporting the planned actions to the organization identifying the problem;
assigning responsibility for correcting the problem;
taking prompt corrective (remedial) action and documenting that action;
training or retraining personnel as appropriate;
taking steps to prevent recurrence;
verifying implementation;
documenting closure;
determining effectiveness of the corrective and preventive actions for significant
problems;
tracking and trending conditions adverse to quality as appropriate; and
communicating lessons learned as appropriate.
4.3.2.4 Quality Performance Analysis
Quality problems should be resolved individually and should also be analyzed as part of a
collection to identify systemic quality problems and opportunities for process improvement.
DOE G 414.1-2B 17
8-16-11
4.4 MANAGEMENT/CRI TERION 4 – DOCUMENTS AND RECORDS
4.4.1 Introduction
The document control and records management systems should describe the process to prepare,
review, approve, issue, use, revise, and maintain documents and records. Documents and
records should include applicable requirements to indicate that work (including safety) has been
properly specified and accomplished. Management should identify any documents and records
that should be developed and controlled. Management is responsible for providing the resources
necessary to accomplish the document and record requirements.
4.4.2 Document Control System
A document control system should be in place to control the preparation, review, approval, issue,
control, and revision of documents. Documents should be used by organizations, projects, or
programs to control policy and administrative and/or technical information. A document may
describe work to be done, data to be used at different locations or by different people, or, in
changing situations, data to be controlled for reference purposes. The document control system
should be established to supply the appropriate documents (correct and applicable revision of the
documents) necessary for personnel to safely and correctly perform assigned responsibilities.
Document control systems ensure that the mechanisms developed to implement the safety
management functions of DOE P 450.4A are properly prepared, controlled, and available for use.
Completed documents should be classified as records.
4.4.3 Records Management System
A record contains information that is retained for its expected future value. Records should be
sufficient to support technical and regulatory decisions and provide objective evidence that work
was performed. Records may be in a variety of forms (e.g., electronic, written, or printed;
microfilm; photographs; radiographs; or optical disks). Typical records include procedures;
plans; manuals; training and qualification results; quality improvement results; acceptance test
results; technical/regulatory correspondence; operational records; design basis descriptions;
design review results; design revisions; configuration management data; and quality problem
resolutions or any other required information. Examples of facilities related records are provided
in ASME NQA-1, Requirement 17, Quality Assurance Records, and the non-mandatory
Appendix 17a-1, Guidance on Quality Assurance Records.
Section 19
Records should be compiled in a records management system as described in DOE O 243.1A,
Records Management Program, dated 11-11-11. The system should include provisions for
specifying, preparing, reviewing, approving, disposing, and maintaining records. Procedures for
records retention, protection, preservation, correction, traceability, accountability, and
retrievability should also be specified. The records management system should have schedules
for records retention and disposition consistent with the requirements of DOE O 200.1A,
Information Technology Management, dated 12-23-08.
18 DOE G 414.1-2B
8-16-11
The hardware and software tools used to create and store records should be maintained to ensure
that the records can be retrieved. The records management system should have schedules for
records retention and disposition consistent with the requirements of DOE O 243.1A, Records
Management Program, dated 11-11-11 and DOE O 243.2, Vital Records, dated 2-2-06.
Additional information can be found in DOE G 1324.5B, Implementation Guide, dated 7-19-96,
primarily implements 36 C.F.R. CHAPTER XII,-Subchapter B, Records Management. DOE G
1324.5B provides detailed non-mandatory guidance and an acceptable system for the
organization, maintenance, and disposition of records.
4.5 PERFORM ANCE/CRITERION 5 – WORK PROCESSES
4.5.1 Introduction
Work should be performed consistent with technical standards, administrative controls, and
hazard controls adopted to meet regulatory or contract requirements using approved instructions,
procedures, or other appropriate means. Work processes consist of a series of actions planned
and carried out by qualified personnel using approved procedures, instructions, and equipment
under administrative, technical, and environmental controls to achieve a result.
4.5.2 Work Performance
Managers are responsible for ensuring that personnel under their supervision have the training,
skills (including knowledge and understanding of the capabilities of the processes being used),
equipment, work process documents, and resources needed to accomplish work. Line
management and workers should cooperate to identify processes that can be improved based on
feedback prior to and following implementation of the work process. Before workers begin
work, management should provide adequate information on:
customer requirements;
hazards associated with the work;
safety, administrative, technical, environmental, and quality controls to be used during the
work;
technical standards applicable to the work and final product;
data requirements for the work and final product;
acceptance criteria applicable to the work and final product; and
procedures for verification of the completed work using established criteria.
Procedures, work instructions, or other appropriate means used to define work processes should
be documented and controlled. The scope and detail of documentation should be commensurate
with the complexity and importance of the work; the skills required to perform the work; the
hazards and risks or consequences of quality problems in the product, process, or service; and
the need to meet regulatory and contract requirements. Control of processes, skills, hazards, and
equipment should be clearly specified, understood, and fully documented. This can serve as the
point of integration for the ISMS and QA into an integrated management approach. See DOE P
450.4A and DOE O 422.1, Conduct of Operations, dated 6-29-10 for further details and
additional requirements.
Section 20
DOE G 414.1-2B 19
8-16-11
Workers are responsible for their work quality. Workers should do work correctly the first time
in accordance with established procedures and work instructions. Because workers are the best
resource for contributing ideas for improving work processes, products, and services, workers
should be involved in work process design, process evaluation (pre-job briefing), and provide
feedback necessary for improvement.
4.5.3 Identification and Control of Items
The term “item” is an all-inclusive term and can be used in place of any of the following:
appurtenance, assembly, component, equipment, material, module, part, structure, product,
software, subassembly, subsystem, system, unit, or support system. A process for the
identification and control of items should be established and implemented to:
prevent the use of incorrect or defective items;
identify and control S/CI(s); and
provide for the control and maintenance of items.
The identification and control process should apply from the manufacture and receipt of the
item through delivery, installation, or use. The process should also provide for the
identification and configuration control of installed or replacement items consistent with
specified requirements. Suitable information used for identification can include listing the
unique part, lot, heat, model, version, or serial numbers on the item or in records traceable to
the item, or both. Physical identification of items is preferred.
4.5.4 Item Protection
Work processes should be established and implemented to protect items in accordance with
specified technical standards and administrative controls to prevent damage, loss, or
deterioration. Work processes should specify protective methods for sensitive or perishable
items, such as special handling, shipping, and storage controls for precision instrumentation and
limited shelf life items, and for items requiring special protective environmental controls, such as
temperature and humidity controls.
4.5.5 Equipment Control
Work processes should be established and implemented to ensure that equipment used for
process monitoring and data collection is of the proper type, range, and accuracy. Such
equipment should be calibrated according to technical standards and maintained to ensure
continuing data quality and process capability. (see Section 4.8 of this Guide, Inspection and
Acceptance Testing.)
4.6 PERFORMANCE/CRITERION 6 – DESIGN
4.6.1 Introduction
A design process should be established that provides appropriate control of design inputs,
20 DOE G 414.1-2B
8-16-11
outputs, verification, configuration, and design changes, and technical and administrative
interfaces. Designs should be based on sound engineering judgment and practices, scientific
principles, applicable orders, codes, and standards. Verification/validation of the adequacy of
the design should be performed before equipment is placed into service.
The design of SSCs, software, and processes should be subject to design process controls and
verification requirements appropriate to the level of risk the items present to the public, the
worker, the environment, and project success. For additional guidance, refer to DOE O 420.1B
Facility Safety, dated 4-19-10, which establishes facility safety and programmatic requirements,
DOE-STD-1189-2008, Integration of Safety into the Design Process, dated March 2008 and
ASME NQA-1 non-mandatory Appendix 3A-1, Guidance on Design Control.
Section 21
For example, selection of the applicable design control requirements for a facility should be
guided by safety analyses that establish:
the identification and functions of safety class and safety significant SSCs;
the significance to safety of the functions performed by those SSCs; and
the aspects critical to the performance, reliability, or programmatic requirements of the
designed SSCs.
Designs should provide for appropriate acceptance, inspection, testing, and maintenance
criteria to ensure continuing reliability and safety of the items. The designer should consider
the expected use and life expectancy of the items to allow appropriate disassembly and
disposal requirements to be addressed.
Design records should include documentation such as design inputs; calculations; design
analyses; engineering reports; design outputs; design changes; design verification activities; a list
of approved and controlled computer codes; and other documents that provide evidence that the
design process was completed satisfactorily.
4.6.2 Design Inputs
Design inputs should be based upon contractual requirements and customer expectations and
should be complete and technically correct. Design inputs may include such information as the
design basis, health and safety considerations, expected life cycle, performance parameters,
codes and standards requirements, and reliability requirements.
4.6.3 Design Process
The design process should translate design inputs into design output documents that are
technically correct and compliant with the end user’s requirements. Aspects critical to the
performance, safety, or reliability of the designed items should be identified during the design
phase. Design output documents should be prepared to support other processes such as dose and
risk assessments, procurement, manufacturing, assembly, construction, testing, operation,
inspection, and maintenance. Design processes should also be considered for any
engineering/design requirements during the deactivation and decommissioning of excess
DOE G 414.1-2B 21
8-16-11
facilities. Technical and administrative design interfaces should be identified and methods
established for their control.
4.6.4 Design Output
The completed design should be recorded in design output documents such as drawings,
specifications, test/inspection plans, maintenance requirements, and reports. As-built drawings
and shop drawings should be maintained after production or construction to show actual
configurations. Interfaces should be identified for reporting to the field for items to be installed
in the field. Drawings, specifications, test/inspection plans, and other design documents should
be reviewed for inspection and testing requirements including required Measuring and Test
Equipment (M&TE). The administrative interface process should clearly indicate
responsibilities for design output documents, including the requirements for document control,
configuration management, and records management.
4.6.5 Design Verification
Design verification is a documented process for ensuring that the design and the resulting items
comply with the project requirements. Design verification methods can include design reviews,
alternate calculations, qualification testing, and peer review of experimental design. When
appropriate, the verification process may include consideration of previous verifications of
similar designs or verifications of similar features of other designs.
Section 22
Design verification should be performed by technically knowledgeable persons independent of
those who developed the design. Interim verifications may occur at predetermined stages of
design development. The extent of design verifications should be based on a graded approach
depending on the product’s complexity and importance to safety and project success.
Organizations rely on verified design output to support other work, such as procurement,
manufacture, construction, testing, or experiments. When the verification cannot be achieved
in time for these activities, unverified portions of the design should be identified and
controlled. Design verifications should be completed, including preoperational testing before
relying on the SSC to perform its function.
4.6.6 Design Changes
Design changes should be controlled by measures commensurate with those applied to the
original design. Design changes include field changes and nonconforming items dispositioned
for “use-as-is” or “repair.” Temporary modifications should receive the same levels of control as
the designs of permanent modifications. Design documents should be updated to include all
design changes, including field changes, to maintain configuration control.
22 DOE G 414.1-2B
8-16-11
4.7 PERFORM ANCE/CRITERION 7 – PROCUREMENT
4.7.1 Introduction
The procurement process should ensure that items and/or services provided by suppliers meet the
requirements and expectations of the end user. The procurement process should be planned,
implemented and controlled to ensure that:
identification of supplier QAP requirements using a grading process such as the process
defined in section 4.1.3.
proper flow down takes place and the supplier/vendor clearly understands all procurement
requirements;
the end user’s requirements are accurately, completely, and clearly communicated to the
supplier;
supplier, designer, and end user requirements are met during the production phase;
the product is delivered on time; and
special handling and storage requirements are specified at time of delivery.
The selection of procurement requirements should be commensurate with the importance of the
end use of the purchased item or service. Management controls exist for DOE procurement and
subcontracts through applicable DOE Orders, the Department of Energy Acquisition Regulation
(DEAR) in 48 C.F.R. subchapters A through H, and the Federal Acquisition Regulation (FAR),
in 48 C.F.R. 970 et. seq. The requirements in the QA Order and the QA Rule should not be
interpreted to require the development of redundant procurement management systems, but
rather to ensure that existing procurement management systems adequately respond to end user
requirements.
The procurement process of DOE nuclear facility contractors should include a determination of
the applicability of the QA Rule to the supplier or subcontractor (see 10 C.F.R. § 830.121). If
applicable, procurement documents and contracts for items and services provided to facilities
covered by the QA Rule should include a statement informing the supplier/vendor or
subcontractor of the QA Rule requirements and of the potential for enforcement actions under
10 C.F.R. Part 820. The QA Order requires that contractors be responsible for ensuring proper
flow down of all applicable requirements (including the adopted standards) to suppliers/vendors
and subcontractors. DOE should ensure proper oversight of the flow down of requirements by
their contractors to subcontractors, vendors and suppliers. The DOE contractor is responsible
for determining methods to ensure that procured items and services meet requirements and
perform as expected, including the prevention and control of the introduction of S/CI(s). (Note:
NQA-1 does not address requirements for the prevention and control of S/CI(s) – see Section 5
of this Guide.) The selection of prospective suppliers should be based on specified criteria.
Suppliers/vendors should be evaluated to verify their capability to meet performance and
schedule requirements.
Section 23
Procurement processes should be established and implemented to ensure that approved suppliers
continue to provide acceptable items and services. Suppliers/vendors should be monitored to
ensure that acceptable items or services are produced within the specified schedule.
DOE G 414.1-2B 23
8-16-11
4.7.2 Procurement Documents
Procurement documents should clearly state or reference requirements and acceptance criteria
for purchased items and services. Procurement documents should include any specifications,
standards, QAP requirements, and other applicable documents referenced in the design
documents. Parameters and requirements should be specified, such as document submittals,
product-related documentation, problem reporting, administrative documentation, personnel or
materials qualifications, tests, inspections, performance expectations for services, and reviews.
A graded approach should be applied based on the significance of the item or service procured.
4.7.3 Supplier Qualification
The objective of evaluating suppliers is two-fold: 1) to verify the supplier has implemented a
QAP that conforms to the contractual requirements; and 2) to verify that the supplier is capable
of providing the items or services specified in the contract. An effective evaluation method is to
conduct an assessment at the supplier’s facility. The assessment may include an evaluation of
personnel, technical and equipment capabilities, and processes.
Supplier qualification can include some of the following:
a review of the supplier’s history of providing identical or similar items or services;
a review of shared supplier quality information (e.g., DOE Consolidated Audit Program,
DOE Laboratory Accreditation Program);
an evaluation of certifications or registrations awarded by nationally/internationally
accredited third parties; and
an evaluation of documented qualitative and quantitative performance information
provided by the supplier.
The method or combination of methods chosen should provide adequate confidence that the
supplied item or service will meet requirements.
Potential suppliers should be identified as early as possible in the design and procurement
process to allow time for evaluation and determination of supplier capabilities.
To assist industry and government in the procurement of qualified fasteners, the Fastener Quality
Act (FQA), 15 C.F.R. Part 280, was signed into law (P.L. 106-34) on June 1999. This law
protects against sale of mismarked, misrepresented and counterfeit fasteners. Under this law, all
manufacturers are required that certain fasteners sold in commerce:
conform to the specification to which they are represented to be manufactured;
provide for accreditation of laboratories engaged in fasteners testing; and
require inspection, testing and certification in accordance with standardized methods.
The U.S. Patent and Trademark Office (USPTO) provide a registered trademark list of fasteners.
All DOE programs should procure bolts and fasteners in accordance with the FQA and the
USPTO trademark list. The QAP or lower tier/site specific procedures should address how to
24 DOE G 414.1-2B
8-16-11
procure bolts and fasteners, and the required actions that should be taken if supplier(s) do not
provide fasteners in accordance with the FQA and the USPTO registered trademark list.
Section 24
In 1992, the U.S. Customs Service developed a Suspect/Counterfeit Part Headmark List that
identified known S/CI fasteners. The list is a tool still being utilized throughout the DOE
complex as an aid for identifying legacy items. All DOE programs that discover fasteners
identified on the headmark list should use applicable site procedures to make S/CI
determinations. A copy of the U.S. Custom’s Headmark list can be found on the HSS website at
http://www.hss.doe.gov/sesa/corporatesafety/sci/ref.html.
For reporting criteria, see Section 5.4, Occurrence Reporting and Information Exchange, and
Section 5.5, Reporting SCI to DOE OIG, of this Guide. The USPTO list can be obtained at
http://operatingexperience.doe-hss.wikispaces.net/Suspect-Counterfeit+and+Defective+Items, or
at http://www.uspto.gov/trademarks/ to search the FQA Registry of fastener insignias.
4.7.4 Supplier Performance Monitoring
The qualified supplier’s performance should be evaluated periodically to confirm continuing
capabilities. Qualified supplier’s performance should be reviewed annually and audited every
third year unless events warrant more frequent assessment. Such evaluation should include
monitoring of the supplier’s work processes to ensure conformance to those requirements that
cannot be readily determined by inspection or test of the product. In some cases, due to the
importance of the items being procured or for known quality problems with the supplier, a full-
time resident inspector may be assigned to monitor the supplier’s performance. Monitoring may
include:
surveillance of in-process work activities and review of work package documentation (e.g.,
manufacturing processes and methods);
inspection of facilities and processes;
review of plans and progress reports;
processing and use of change information;
review of internal assessments;
review and disposition of nonconformances; and
selection, qualification, and performance monitoring of sub-tier suppliers.
4.7.5 Inspection of Procured Items
The procurement process should provide for identifying inspections and tests to ensure
conformance with purchase requirements. Design and procurement documents should specify
critical or important acceptance parameters for inspection.
Inspections should include verification that specified documentation has been provided by
the supplier, and that items were not damaged during shipment. Inspection may include the
following methods:
inspections of materials or equipment at the supplier’s facility;
DOE G 414.1-2B 25
8-16-11
receipt inspection of the shipped items using established item critical characteristics;
review of objective evidence such as certifications and reports; and
verification or testing of items before or following shipment.
4.7.6 Supplier Documentation
Supplier-generated documents should be accepted through the procurement system and
controlled and processed by the end user organization. These documents may include
certificates of conformance, drawings, analyses, certified material test reports (CMTR),
maintenance data, nonconformance documentation, corrective actions, approved changes,
waivers, and deviations. Supplier-issued Certificates of Conformance should not be accepted
without an accompanying test report that provides the results of inspection and tests required by
the governing product specification or the manufacturer’s specification.
4.7.7 Procurement of Safety-Related Items for Nuclear Facilities/Activities
Section 25
Items procured that may affect nuclear safety should be:
purchased from a supplier who meets the quality criteria in the QA Rule, and
purchased from a supplier whose QAP has been evaluated and is found to be an acceptable,
documented, and implemented NQA-1 program; or,
if purchased from a supplier who does not have an acceptable NQA-1 program, the items
should be subjected to the Commercial Grade Dedication (CGD) process.
Commercial grade items that affect the safety function of the application in which they are
intended for use should be accepted in accordance with the CGD process. A documented
technical evaluation should be performed by the responsible design organization for acceptance
of the commercial grade items. This evaluation should include: determining the safety
function(s); verifying performance requirements and applicable service conditions; and verifying
critical characteristics including acceptance criteria. Additional guidance for the CGD process
can be found in ASME NQA-1, Subpart 2.14, Quality Assurance Requirements for Commercial
Grade Items and Services, the Electric Power Research Institute (EPRI) Guideline NP-5652,
1988 Revision, Guideline for the Utilization of Commercial Grade Items in Nuclear Safety
Related Applications (NCIG-07), June 1988, and the EPRI Guideline TR-102260, Supplemental
Guidance for the Application of EPRI Report NP-5652 on the Utilization of Commercial Grade
Items. Methods used to verify critical design characteristics and appropriateness of the item for
use include processes such as the following:
special test(s), inspection(s) and/or analysis;
commercial grade survey of the supplier;
source verification; and/or
acceptable supplier item or service performance record.
4.7.8 Multi-Site Procurement
Multi-site procurement is becoming common within the DOE complex and should be addressed
26 DOE G 414.1-2B
8-16-11
in the QAP and the implementing procedures of each site. Interface among DOE and contractor
organizations should be established and documented with a clear definition of the responsibilities
of each organization with regard to quality requirements.
4.8 PERFORM ANCE/CRITERION 8 – INSPECTION AND ACCEPTANCE
TESTING
4.8.1 Introduction
The specified inspections and tests for items, services, and processes should be performed with
calibrated equipment using established acceptance and performance criteria. Inspections and
tests verify that the physical and functional aspects of items, services, and processes meet
requirements and that they are fit for acceptance and use. Performance expectations, inspections,
and tests should be identified or considered early in the design process and/or specified in the
design output and procurement documents. Before performing inspections or tests, workers
should check the materials and equipment used to perform such inspections and tests to ensure
adequate calibration and acceptability.
Safety software should be tested in accordance with DOE G 414.1-4.
4.8.2 Process
Adequate inspection/test planning should be performed. Appropriate sections of approved codes
or standards may be used for establishing acceptance requirements and inspection or test
methods. In planning for inspections/tests, personnel should consider provisions for the
following:
Section 26
identification of characteristics to be examined;
required qualifications of individuals who perform the examinations;
descriptions of examination methods, including equipment and calibration requirements;
acceptance and rejection criteria;
suitable environmental conditions;
shelf life and maintenance;
required safety measures; and
mandatory hold points, when applicable.
Personnel performing inspections and tests should be technically qualified and have the
authority to access appropriate information and facilities to verify acceptance. These qualified
personnel should be independent of the activities being inspected/tested and should have the
freedom to report the results of the inspections/tests. Inspection/test results should be evaluated
and verified by qualified personnel.
4.8.3 Control of Measuring and Test Equipment
Measuring and test equipment (M&TE) used for inspections, tests, monitoring, and data
collection should be calibrated, maintained, and controlled using a documented process. M&TE
DOE G 414.1-2B 27
8-16-11
should be checked before use to ensure that it is of the proper type, range, accuracy, and
precision, and that it is uniquely identified and traceable to its calibration data. Procedures
should be established for testing, retesting, adjusting, and recalibrating M&TE. M&TE should
be calibrated to standards traceable to the NIST or other nationally recognized standards when
appropriate. If no nationally recognized standard exists, the basis for calibration should be
documented. When calibrating and/or checking M&TE for use, computer programs/software
that are part of M&TE should be checked to ensure verification and validation (V&V) have
been performed for the computer programs/software, and that the V&V is current.
The use of M&TE should be traceable to the item inspected because measurements and tests
performed with the M&TE may need to be reevaluated if the M&TE is subsequently found to be
out of its acceptable calibration range. Systems that rely on recording the identity of the M&TE
in work packages are ineffective because review of all work packages to identify each use of a
particular M&TE is almost impossible. A process to provide traceability from the M&TE to the
item inspected should be established. ISO/IEC 17025, General Requirements for the
Competence of Calibration and Testing Laboratories, 2005 and ASME NQA-1, Requirement
12, Control of Measuring and Test Equipment, provide additional information on the control of
M&TE.
4.8.4 Records
Inspection and test records should, at a minimum, identify:
item tested;
date of test;
test method;
tester or data recorder;
observations;
results and acceptability;
action taken concerning problems noted; and
M&TE, including serial number or unique identifier.
Following any inspection or test, the resulting status of items, services, and processes should
be clearly and plainly noted to ensure that only those with acceptable inspection and test
results are used. The process should provide for review and re-inspection/retest of items
whose inspection/test parameters have changed.
4.9 ASSESSMENT/CRITERION 9 – MANAGEMENT ASSESSMENT
The QA Order and the QA Rule require that managers assess their management processes, and
identify and correct problems that hinder the organization from achieving its objectives.
Assessments should promote continuous improvement and ensure that the organization’s
performance is acceptable. Guidance on this topic can be found in DOE G 414.1-1B.
Section 27
28 DOE G 414.1-2B
8-16-11
4.10 ASSESSMENT/CRITERION 10 – INDEPENDENT ASSESSMENT
The QA Order and the QA Rule require that independent assessments are planned and
conducted to measure item and service quality, to measure the adequacy of work performance,
and to promote improvement. Line management should establish sufficient authority and
freedom for the group performing independent assessment. Persons who perform independent
assessments should be technically qualified and knowledgeable in the areas to be assessed, and
should not be involved in the work being evaluated, but may be from the same organization.
Guidance on this topic can be found in DOE G 414.1-1B.
5.0 GUIDANCE ON SUSPECT AND COUNTERFEIT ITEMS
5.1 INTRODUCTION
Approaches and methodologies described in this section were developed to meet the
requirements for S/CIs described in Attachment 3 of the QA Order. Processes established to
implement QA Criteria 3, 6, 7, and 8 contribute to the prevention of the introduction of S/CIs.
Organizations, as part of their QAPs, should establish effective controls and processes that will:
(1) ensure items and services meet specified requirements; (2) prevent entry of S/CI(s) into the
DOE supply chain; and (3) ensure detection, control, reporting, and disposition of S/CI(s). This
section provides guidance for documenting and implementing an effective S/CI process that will
meet the QA Order requirements for S/CI. Programs are free to choose any national or
international consensus standards and industry best practices for S/CIs, as long as the QAP
documents how the S/CI requirements in the QA Order are met.
This section and the IAEA-TECDOC-1169 are intended to assist organizations in establishing
QA procedures and practices to eliminate the hazards created by S/CIs that are present in DOE
facilities and to prevent any further introduction of S/CIs.
5.2 DOE O 414.1D REQUIREMENTS AND IAEA-TECDOC-1169 MATRIX
This section provides a matrix (see Table 3) of where the guidance in the IAEA-TECDOC-1169
meets the S/CI requirements for the control of S/CIs.
D
O
E
G
414.1-2B
29
8-16-11
Table 3: DOE QA Requirements for S/CI and Guidance in IAEA-TECDOC-1169
S/CI Requirements in DOE O 414.1D from Attachment 3 IAEA-TECDOC-1169
2. REQUIREMENTS. The organization's QAP must:
2.a. Include a S/CI oversight and prevention process commensurate with
the facility/activity hazards and mission impact.
2.1 Management Responsibility1
2.b. Identify the position responsible for S/CI activities and for serving
as a point of contact with the Office of Health, Safety, and Security.
2.0 Management
2.1 Management Responsibility
2.3 Training
2.c. Provide for training and informing managers, supervisors, and
workers on S/CI processes and controls (including prevention,
detection, and disposition of S/CIs).
3.0 Performance
3.1 General
3.2 Engineering
3.3 Procurement
3.4 Inspection and testing for acceptance
2.d. Prevent introduction of S/CIs into DOE work by—
(1) engineering involvement:
(a) in the development of procurement specifications;
(b) during inspection and testing; and
(c) when maintaining, replacing, or modifying equipment;
3.3 Procurement
(2) identifying and placing technical and QA requirements in
procurement specifications;
3.4 Inspection and testing for acceptance
(3) accepting only those items that comply with procurement
specifications, consensus standards, and commonly accepted
industry practices; and
Section 28
3.4 Inspection and testing for acceptance
3.5 Disposition of installed S/CIs
(4) Inspecting inventory and storage areas to identify, control, and
disposition for S/CIs.
1 Safety applications are those whose failure could adversely affect the environment, safety, or health of the public or workers. This term includes safety systems
in nuclear facilities (see 10 C.F.R. § 830.3).
*See Section 5.3
**See Section 5.4
***See Section 5.5
30
D
O
E
G
414.1-2B
8-16-11
S/CI Requirements in DOE O 414.1D from Attachment 3 IAEA-TECDOC-1169
2.e. Include processes for inspection, identification, evaluation, and
disposition of S/CIs that have been installed in safety applications2
and other applications that create potential hazards. Also address
use of supporting engineering evaluations for acceptance of installed
S/CI as well as marking to prevent future reuse.
3.2 Engineering
3.5 Disposition of installed S/CIs
4.0 Assessment
2.f. Conduct engineering evaluations to be used in the disposition of
identified S/CIs installed in safety applications/systems or in
applications that create potential hazards. Evaluations must
consider potential risks to the environment, the public and workers
cost/benefit impact, and a schedule for replacement (if required).
3.2 Engineering
3.5 Disposition of installed S/CIs
4.0 Assessment
2.g. Perform the evaluation to determine whether S/CIs installed in non-
safety applications pose potential safety hazards or may remain in
place. Disposition S/CIs identified during routine maintenance
and/or inspections to prevent future use in these applications.
3.5 Disposition of installed S/CIs
4.0 Assessment
2.h. Report to the DOE Inspector General per paragraph 3. below, and
DOE O 221.1A, Reporting Fraud, Waste, and Abuse to the Office of
Inspector General, dated 04-19-08 (or latest version)
2.i. Collect, maintain, disseminate, and use the most accurate, up to date
information on S/CIs and suppliers. Sources are identified on the
DOE S/CI website (http://www.hss.energy.gov/csa/csp/sci/).
2.0 Management
2.4 Communication and information sharing
2.5 Non-conformance identification and
disposition
3.2 Engineering
D
O
E
G
414.1-2B
31
8-16-11
S/CI Requirements in DOE O 414.1D from Attachment 3 IAEA-TECDOC-1169
2.j. Conduct trend analyses for use in improving the S/CI prevention
process.
3.2.3 Engineering input to information management
Note: DOE O 210.2A, DOE Corporate Operating Experience Program,
dated 4-8-11. (or latest version) requires review of existing lessons
learned reports and submittal of new lessons learned reports for
use in improving the S/CI prevention process.
2.4 Communication and information sharing
3. INSPECTOR GENERAL. Contact the DOE Inspector General (IG),
before destroying or disposing of S/CIs and corresponding
documentation, to allow the IG to determine whether the items and
documentation need to be retained for criminal investigation or
litigation.
4. OCCURRENCE REPORTING. S/CIs must be reported in
accordance with DOE O 232.2 Occurrence Reporting and Processing
Operations Information, dated 1-1-12 (or latest version).
32 DOE G 414.1-2B
8-16-11
5.3 RESPONSIBILITY IN REPORTING
The organization’s QAP should include an S/CI oversight and prevention process commensurate
with the facility/activity hazards and mission impact. The QAP should address responsibility for
ensuring that the requirements listed below are met, including the flow down of the requirements
to contractors, subcontractors, suppliers and vendors. S/CI requirements include:
Section 29
identifying the position responsible for S/CI activities, and for serving as a point of
contact with the Office of Health, Safety, and Security (HSS);
reporting to the DOE Inspector General; and
issuing lessons learned reports for use in improving the S/CI prevention process in
accordance with DOE O 210.2A, DOE Corporate Operating Experience Program, dated
4-8-11.
The responsible personnel should contact the DOE Inspector General (IG) before destroying or
disposing of the S/CI(s) and the corresponding documentation. This allows the IG to determine
whether the items and documentation need to be retained for criminal investigation or litigation.
S/CIs are reported in accordance with DOE O 232.2 Occurrence Reporting and Processing
Operations Information, dated 1-1-12
As shown in Table 3, guidance for most DOE S/CI requirements is provided in the IAEA-
TECDOC-1169. The guidance for Occurrence Reporting and Information Exchange for S/CI
requirements not provided by the IAEA document is described in the following Section of this
Guide. The IAEA-TECDOC-1169 is available at www.iaea.org.
5.4 OCCURRENCE REPORTING AND INFORMATION EXCHANGE
5.4.1 Reporting S/CI Discovery
The QA Order states that items, services, and processes that do not meet the specified
requirements be identified, controlled, and corrected. DOE M 231.1-2 requires prompt reporting
of all S/CIs, regardless of their location/application. S/CIs should be reported to the responsible
DOE Operations Office manager and program manager by means of the Occurrence Reporting
Processing System (ORPS), and to the Office of Inspector General (OIG). The use of ORPS and
the S/CI notification process will facilitate the contractor’s reporting obligation. Reporting an
S/CI in ORPS does not substitute for reporting to the OIG.
Prompt reporting of S/CIs in ORPS contributes to improvement of safety, regulatory
compliance, and reliability. The S/CI information reported in ORPS is also used by Program
Offices, other DOE contractors, HSS, OIG, and, where appropriate, by external agencies to
prevent the spread of potentially hazardous items. For this reason, information reported should
be sufficient to alert other organizations of S/CIs, and potential safety or performance problems
associated with the items. Historically, many S/CIs and defective items have been identified
via ORPS. HSS reviews ORPS events on a daily basis for S/CIs and defective items (DIs) with
potential safety impacts on DOE operations.
DOE G 414.1-2B Page 33
6/30/2011
5.4.2 Government-Industry Data Exchange Program
The Office of Management and Budget Policy Letter No. 91-3 requires DOE to participate in
the exchange of failure experience information concerning S/CIs. Accordingly, DOE and their
contractors should participate in the Government-Industry Data Exchange Program (GIDEP).
Information on joining and participating in GIDEP can be found at http://www.gidep.org. HSS
utilizes GIDEP as an S/CI information source to search for S/CIs that may have potential
impacts on DOE operations. A data collection sheet (DCS) is then prepared and the information
posted to the S/CI database on the HSS S/CI Web site. DOE and its contractors should also use
GIDEP information in their procurement, inspection, and maintenance processes to prevent
introduction of S/CIs, assist in the identification of S/CIs that have already entered the facility,
and for reporting S/CI discoveries.
5.4.3 Consultation with Office of General Counsel
Section 30
Federal program managers should consult with DOE’s or NNSA’s Office of General Counsel
regarding legal questions arising from any S/CI occurrence. Typical legal questions involving
an S/CI report include disclosure restrictions; procedures to protect Government rights against
S/CI suppliers; and proper liaison procedures among DOE programs and investigative, law
enforcement, or prosecuting agencies (e.g., the OIG, Defense Criminal Investigative Service
[under Department of Defense], Federal Bureau of Investigation, U.S. Department of Justice,
and U.S. Attorneys). Within the Office of General Counsel, the Office of Assistant General
Counsel for Civilian Nuclear Programs should be consulted for S/CI issues involving nuclear
safety. For S/CI issues involving procurement and contractual-related issues, the Office of
Assistant General Counsel for Procurement and Financial Assistance should be consulted.
Both offices are located at DOE HQ.
5.4.4 S/CI Review, Analysis, and Notification
5.4.4.1 S/CI Review and Analysis
HSS has corporate responsibility for DOE’s S/CI process. This responsibility includes the
collection and review of information from internal and external sources, and the identification
and dissemination of potential S/CI and DI information to the DOE complex. Figure 1 depicts a
flowchart of the S/CI notification process. S/CI information sources include ORPS, GIDEP,
Institute of Nuclear Power Operation (INPO), NTS database, accident investigation reports, and
Nuclear Regulatory Commission (NRC) Generic Communications.
34
D
O
E
G
414.1-2B
`
8-16-11
Figure 1 - Suspect/Counterfeit Item Notification Chart
Source of Information
PSO documents
results of review
and actions. Results
may be that there
are no S/CI-DIs.
Implements corrective action
HSS reviews,
consolidates results
and closes inquiry
HSS initiates S/CI-DI
Operating Experience
Notifications
For high profile or special
case S/CI-DI, HSS
develops & transmits
investigation lines of
inquiry to the PSOs
Initiates Occurrence Report
Field does search for S/CI-DIs
& reports to PSOs
PSOs initiate investigation
with the field offices
HSS reviews
Operating
Experience
S/CI-DI issue
Notifies the IG
When S/CI-DIs are
identified, the field:
OTHER
IG
GIDEP
INPO
ORPS
DOE G 414.1-2B 35
8-16-11
For each potential S/CI identified, HSS prepares a data collection sheet (DCS) and assigns a
tracking number. The DCS is used to facilitate review of the S/CI or DI and to document
actions taken to resolve the issue. After appropriate review, the DCS is published by HSS.
HSS evaluates identified S/CIs and DIs using screening criteria for its applicability to DOE,
and to determine what actions should be taken. HSS may also obtain advice and assistance
from other subject matter experts in DOE to assist in making this determination. Typical
screening criteria include:
Is this a repeat occurrence?
Does the issue affect more than one site or have the potential to affect more than one site?
Has the issue been declared an S/CI or DI, or does it have the potential to be declared an
S/CI or DI?
Is an investigation underway or about to be initiated regarding potential criminal
activities?
Does the issue have any immediate or potential regulatory, environmental, health, or
safety impact?
Could other organizations address the issue more appropriately?
Does the issue have any complex-wide implication?
Is this a legacy item(s) (e.g., high strength bolts found installed (time unknown), no
Section 31
manufacturer insignia, or unknown supplier)?
5.4.4.2 S/CI Notification Process
The purpose of the S/CI notification process is to provide a coordinated mechanism for the
timely dissemination and field review of information concerning potential S/CIs. Based on
the potential significance of the S/CI and its applicability to DOE, the information may be
provided to the DOE complex using one of several methods.
Operating experience notifications, which potentially include:
o HSS Safety Alert – if documentation clearly indicates that an S/CI or DI may be
involved, and a significant regulatory, environmental, health, or safety impact exists.
o POC Notification – if documentation indicates that the S/CI or a DI may be in use at
DOE facilities.
o Operating Experience Summary – if documentation indicates that the S/CI or a DI
may be applicable to DOE facilities.
Complex-wide submittal of ORPS reports.
DCS posted on the DOE HSS S/CI Web site at (http://www.hss.energy.gov/csa/csp/sci/),
and possibly distributed through the e-mail listserver.
Possible notification of S/CI points of contact in the field or at HQ.
Regardless of how the information is disseminated, field and HQ organizations should review
the information for potential applicability to their own facilities and operations. When an
organization identifies an S/CI or DI, it submits an ORPS report and notifies the local OIG.
S/CI information also is shared via other methods. The HSS Operating Experience Committee
36 DOE G 414.1-2B
8-16-11
conducts monthly conference calls and periodically discusses specific information regarding
newly identified S/CIs or offers presentations from internal and external organizations
concerning the status of existing and/or the development of S/CI programs. The Operating
Experience Wiki page (http://operatingexperience.doe-hss.wikispaces.net/) hosts a dedicated web
space for S/CI specific information, including informational publications, presentations, and
videos from internal and external organizations.
5.5 REPORTING S/CIs TO DOE OIG
5.5.1 Authority
DOE O 221.1A requires DOE and contractor personnel to report instances of suspected fraud,
waste, and abuse to the OIG. This all-encompassing requirement includes S/CIs. Reporting
S/CIs pursuant to other DOE directives (e.g., reporting in ORPS) does not substitute for
reporting S/CIs to the OIG.
5.5.2 Reporting S/CIs to OIG
5.5.2.1 General
DOE field elements and contractors report any S/CIs discovered during receipt, maintenance,
testing, inspection, or use, and when there is reason to believe that a fraudulent act occurred
during the manufacturing, shipping, testing, or certification of the S/CI. The following are some,
but not all, indicators that should cause suspicion of fraud:
Although Item X was ordered and billed, evidence exists that the supplier intentionally
provided Item Y.
The S/CI, sold as new, shows evidence of prior use.
Evidence shows that the manufacturer or supplier:
o intentionally provided altered or incomplete testing data, and/or
o did not disclose that some testing data were missing.
Performance is inconsistent with certification or testing data furnished by the manufacturer or
supplier.
Product failure rate exceeds expectations.
The manufacturer’s name, logo, serial number, or manufacture date appear to have been
altered.
Product is certified as meeting specified criteria, but fails independent QA test.
DOE G 414.1-2B 37
8-16-11
Section 32
5.5.2.2 Who Should Report S/CI(s) to OIG
DOE or its contractors at the site (i.e., location) where the S/CI(s) are initially discovered
should report directly to the OIG. Responsibility for reporting S/CI(s) to the OIG, as
described in this Guide, should be defined at each location.
5.5.2.3 Where to Report
Reports to the OIG should be made to the local Office of Investigations within the OIG nearest
the location where the S/CI(s) were initially discovered. Direct coordination with the local
Office of Investigations will ensure communication of the necessary information. Reports may
also be made directly to the OIG Hotline. The following link contains the mailing address and
telephone number for the local OIG offices: http://energy.gov/ig/contact-us/field-offices.
5.5.2.4 What to Report
Report specific characteristics of the potential fraud, including:
Description of the S/CI (e.g., raw material, fasteners, electrical components, valves, fittings,
ratchet straps);
Location of the discovery (e.g., receiving inspection, specific building and room installed);
Name of manufacturer, distributor, and supplier;
Identifying numbers (e.g., serial number, model number, product code);
Point of contact for information on the location of the S/CI and corresponding
documentation;
Date of the S/CI discovery;
Occurrence report number (if available);
Intended end use (e.g., facility construction, component or equipment assembly);
Significance of the S/CI;
Dollar value of the S/CI; and
Other pertinent information, including any action that is underway by the DOE or other
agencies.
5.5.2.5 When to Report
If an S/CI is identified, an Occurrence Report is submitted to ORPS, and the IG is notified in
accordance with the requirements in DOE O 221.1, Reporting Fraud, Waste, and Abuse to the
Office of the Inspector General, dated 4-19-08.
5.5.2.6 How to Report
S/CI may be reported by letter, telephone, fax, or electronic mail to the appropriate OIG
field office (see http://energy.gov/ig/contact-us/field-offices).
38 DOE G 414.1-2B
8-16-11
5.5.2.7 How to Secure the S/CI
S/CIs and corresponding documentation should be held in a secure area per the local non-
conforming item procedures until the OIG has been notified and has responded to the
notification and given disposition directions. S/CI procedures should address appropriate
segregation of S/CI(s), where appropriate, and the use of hold tags.
5.5.2.8 What to Expect from the OIG
Once the OIG has been notified, the OIG will respond, absent compelling circumstances, within
ten (10) calendar days of the notification as to its intent regarding opening an investigation. If
the OIG opens an investigation, DOE and its contractors will retain and secure the S/CI and
corresponding documentation until the investigation is completed or otherwise released by the
OIG. In some instances, the OIG may take custody of the S/CI. The OIG will also require the
corresponding documentation for investigative purposes. At case closing, or when the S/CI is
no longer needed for evidentiary purposes, the OIG will provide notice releasing the S/CI from
the hold status. Once the S/CI is released from the hold status, disposal of the S/CI may proceed
in accordance with approved procedures that clearly identify item(s) as noncompliant and
prevent inadvertent use, installation or return to storage/inventory. If authorized by the OIG,
destruction of the S/CI should be performed in a manner so as to permanently and irrevocably
alter the S/CI so that it cannot be used. If the OIG does not respond as described in this
paragraph, DOE and contractor personnel should feel free to contact the OIG.
Section 33
If the OIG decides not to pursue an investigation or similar review, the OIG will give notice
releasing the S/CI from hold status. This action should not preclude DOE or its contractors
from denying payment, returning substandard or otherwise DIs to the sender, or seeking other
contractual remedies, as appropriate. The OIG’s decision to release an S/CI from a hold status
should not be interpreted as having any bearing on the safety or usability of the product in
question. Release means that the OIG does not need the items for evidentiary purposes.
NOTE: Returning a substandard or otherwise DI(s) to the sender could result in resale of that
item. The purchaser should take action to ensure that either the supplier’s performance is
improved or the supplier is removed from the approved suppliers list.
5.5.3 Successfully Prosecuting S/CI Cases
The best defense against the introduction of S/CIs into the DOE complex is a well-managed and
up-to-date QA program. Prosecution of S/CI offenders is an integral part of the DOE internal
control structure and is used to discourage would-be offenders; however, prosecution without an
effective QA program will not prevent the introduction of S/CIs into the DOE complex.
Implementing the following suggestions will improve the chances for successfully prosecuting
an S/CI offender:
Identify the S/CI during initial receipt at its point of entry into the DOE complex (i.e., where
goods ordered are opened, inspected, tested (when applicable), and compared to the
requisition and shipping paperwork).
DOE G 414.1-2B 39 (and 40)
8-16-11
Limit and document the chain-of-custody of the S/CI and paperwork from receipt
until the OIG releases the S/CI from a hold status.
Ensure that requisitions or purchase orders contain specific product requirements
(where possible, do not purchase products from after-market dealers or grey market
arena).
Require the manufacturer and supplier to certify that the products supplied conform to
contract requirements and specifications.
Conduct an independent test or evaluation to show that the product does not conform
to contract requirements.
DOE G 414.1-2B Appendix A
8-16-11 A-1
APPENDIX A: QUALITY ASSURANCE PROGRAM REVIEW
AND APPROVAL TEMPLATE
This review template is intended for use by the DOE for evaluating a DOE Site Office or
Contractor Quality Assurance Program (QAP) submittal consistent with DOE O 414.1D (the
QA Order) and/or 10 C.F.R. Part 830 (the QA Rule). It may also be used by DOE or
contractors to review other QAPs.
This appendix refers to various DOE Orders, Policies, Standards, and Guides. The user
is advised to use the current revision of the referenced documents.
1.0 REVIEWER QUALIFICATION
Federal personnel assigned to lead review teams at nuclear facilities, and recommend approval
of the contractor QAP should have been qualified, at a minimum, to DOE-STD-1150-2002,
Quality Assurance Functional Area Qualification Standard, dated April 2002 which is
consistent with DOE O 426.1, Federal Technical Capability, dated 11-19-09. Team members
may also be qualified but, at a minimum, should have demonstrated proficiency in quality
assurance (QA) and should be technically qualified and/or knowledgeable in the areas they are
assigned to review.
2.0 QUALITY ASSURANCE PROGRAM REVIEW
The DOE reviewer/approval authority should do the following as part of planning
and performance of the review.
List the requirements, in addition to the QA Order and the QA Rule, applicable to the
QAP, such as:
Section 34
o safety structures, systems, and components identified and discussed in the safety
basis documents;
o appropriate standards selected (e.g., NQA-1, ISO 9001); and
o integration with other management system and quality requirements (e.g.,
integrated safety management system (ISMS), QC-1).
Use the guidance provided in this document. DOE programs may use the applicable
edition of ASME NQA-1 including appropriate Addenda (or a later edition), Quality
Assurance Requirements for Nuclear Facility Application, Part I and applicable
requirements of Part II based on the status of the facility.
Apply the review to all project quality-related activities.
Determine the responsibilities for review and approval of initial submittals and revisions of
the QAP description.
As part of the review, evaluate the implementation of the QAP where possible.
Understand the applicable contract quality requirements and expectations.
Appendix A DOE G 414.1-2B
A-2 8-16-11
3.0 GENERAL PROCESS FOR THE REVIEW
Prepare a review plan in advance.
Base the review plan on this document and the applicable edition of NQA- 1 (or
other appropriate standard(s) for non-nuclear work) and the contract.
Identify the quality criteria that apply to the work.
Prepare checklists for the review.
Use the questions identified below as a starting point and expand them using the contract,
this Guide, and the applicable edition of NQA-1.
Complete the review and document the results.
Notify the contractor of the review results, provide any directed changes to the
contractor’s QAP, and inform the contractor of the status (approved, conditionally
approved, or disapproved).
Notify the contractor of any work restrictions relating to conditional approvals or
disapprovals.
4.0 CH ECKLIST (SEE CORRESPONDING SECTIONS OF THIS GUIDE
AS LISTED BELOW)
This section provides example questions for initial QAP review. Initial review should have the
greatest rigor and subsequent reviews should evaluate programmatic changes and performance
results.
4.1 MANAGEMENT/CRITERION 1 – PROGRAM
Does the quality assurance description describe the established organizational structure,
functional responsibilities, levels of authority, and interfaces for those managing, performing,
and assessing the work?
Has the organization designated the senior management position responsible for development
and maintenance of the QAP?
Does the organization demonstrate senior management leadership for quality and the QAP?
Are senior management expectations for implementation adequately defined and delineated?
Have the requirements for ISMS been adequately addressed and integrated into the QAP?
Are there organizations excluded from the scope of the quality assurance program? If so, is
there sufficient justification for the exclusion?
Are the internal and external interfaces documented?
Have adequate resources been identified for quality program activities, such as planning,
auditing, supplier qualification, technical document review, inspection, calibration, etc.?
Does the QA program description describe management processes, including planning,
scheduling, and providing resources for the work?
Does the QA program description define a process for grading the application of
requirements based on hazards and mission?
DOE G 414.1-2B Appendix A
8-16-11 A-3
Section 35
Does the QA program description address the general requirements for a QAP?
Does the QA program description have a process for the prevention and control of S/CI?
Does the QA program description address the safety software requirements?
Has the QA program description been prepared using the applicable edition of NQA-1-for
organizations responsible for nuclear facilities or nuclear facility oversight applications? If
not related to a nuclear facility, were other consensus standards appropriate for the mission
used (ISO 9001, ASQ Z 1.13, QC-1)?
Does the QA program description include a commitment to the standard?
Does the QAP include any exemptions from portions of the selected standard? Are those
exemptions supported by an adequate basis?
Is the process for determining the quality requirements applicable to
subcontractors/suppliers and passing those requirements down through contracts
clearly defined? Is this process applicable to all contracts?
Has DOE Site Office or contractor senior management endorsed the QAP through a
written quality policy statement?
4.2 MANAGEMENT/CRI TERION 2 – PERSONNEL TRAINING AND
QUALIFICATION
Is the methodology described for establishing requirements to train and qualify personnel so
that they are capable of performing their assigned work?
Does the organization have evidence of an established and documented training plan?
Have adequate resources been identified to support the selection, training, and
qualification of personnel conducting work?
Does the training and qualification program describe the positions and functions to which it
applies?
Are the requirements defined for the qualification and/or certification of personnel in the
various functional areas (e.g., lead auditors, auditors, subject matter experts, nondestructive
examination personnel, welders, etc.)?
Is the methodology described for providing continuing training to personnel to maintain
their job proficiency?
4.3 MANAGEMENT/CRI TERION 3 – QUALITY IMPROVEMENT
Has the organization established, implemented, and documented processes to detect
and prevent quality problems?
Do work processes, procedures, etc., call for identification and reporting of problems?
Does senior management policy encourage problem detection and prevention?
Do processes exist for communicating lessons learned and performance information?
Is a method described for categorizing the significance of problems?
Is the approach to identify, control, and correct items, services, and processes that do not
meet established requirements (nonconforming) adequately described?
Does this approach include the requisite discipline involvement to adequately evaluate
Appendix A DOE G 414.1-2B
A-4 8-16-11
and disposition the nonconforming item, service, or process?
Does this approach address the identification and control of nonconforming items such that
it prevents inadvertent use?
Does the QA program description address documentation and correction of quality
problems associated with services and processes?
Does the QA program description provide for the identification of the causes of
problems and require identification of actions to prevent recurrence as a part of
correcting the problem?
Does the QA program description describe methods for addressing cause, extent, and
remedial and preventative actions for quality problems?
Is a process identified to review item characteristics, process implementation, and other
quality-related information to identify items, services, and processes needing
improvement?
Section 36
Is a quality performance analysis system specified (e.g., six sigma, metrics and
indicators, trending)?
Does the performance analysis system provide a mechanism for feedback to affected and
related entities in the organization?
4.4 MANAGEMENT/CRITERION 4 – DOCUMENTS AND RECORDS
How does the organization prepare, review, approve, issue, use, and revise
documents to prescribe such things as processes, requirements, and design? Does a
document control system exist that provides these functions?
Verify that key functions such as procedures relating to the quality criterion (e.g.,
design, procurement, work control, inspection, testing) are described in approved
document.
Verify that documents prescribe not only internal processes, but also processes to
oversee contractors and suppliers.
Verify that the DOE Site Office key work processes and the activities in their functions,
responsibilities, and authorities (FRA) are supported by documents.
Verify that the DOE Site Office has a documented process for the receipt and distribution of
government furnished information from one contractor to another contractor.
How does the organization specify, prepare, review, approve, and maintain records?
Does a documented records management system exist that provides these functions?
How are the requirements of the National Archives and Records Administration
addressed?
What is the quality records standard applied to the contract?
4.5 PERFORM ANCE/CRITERION 5 – WORK PROCESSES
How does the QA program description provide methods for ensuring that work is
DOE G 414.1-2B Appendix A
8-16-11 A-5
performed consistent with technical standards, administrative controls, and other hazard
controls?
Are the core functions and guiding principles of the DOE Integrated Safety Management
System addressed consistent with DOE O 436.1, Departmental Sustainability, dated 5-2-11;
and with applicable chapters in DOE O 422.1 Conduct of Operations, dated 6-29-10?
Do the approved documents (instructions, procedures, or other appropriate means for
the work processes) meet regulatory or contract requirements?
Does the QA program description provide methods to identify and control items to ensure
their proper use?
Does the QA program description adequately describe the method to maintain items to
prevent their damage, loss, or deterioration? Does this method address the requirements
(e.g., DOE O 433.1B, Maintenance Management Program for DOE Nuclear Facilities,
dated 4-21-10)? Are S/CI(s) addressed in the context of maintenance?
Does the QA program description describe an adequate calibration and maintenance
system for equipment used for process monitoring or data collection?
4.6 PERFORMANCE/CRITERION 6 – DESIGN
Determine whether the Site Office performs design work as the design authority. If not, a
documented process should cover oversight of contractor design activities (see Section 4.4 of
this Guide, Documents and Records). DOE oversight activities may include setting of high-
level requirements for the facility/system, reviewing and commenting on completed systems
design descriptions, or approving critical decision points for moving from preliminary design
to final design.
Do design items and processes use sound engineering/scientific principles and
appropriate Standards and Orders (e.g., DOE O 420.1B)?
Is the use of software in the design and safety analysis process controlled consistent with
DOE G 414.1-4?
Section 37
What method is used to incorporate applicable requirements and design bases in design
work?
Are design changes controlled at the same level as the design?
How are design interfaces identified and controlled, within the design authority and
externally with customers and suppliers, including subcontractors?
Does the QA program description describe a process for design verification and/or
validation for design products? Does the process require the use of individuals or groups
other than those who performed the work?
Is the work verified/validated before approval and implementation of the design?
Is there a system for engineering involvement in the identification, analysis, and control of
suspect/counterfeit items that could affect safety?
How does the design authority control changes to procurement documents that include
design requirements?
Appendix A DOE G 414.1-2B
A-6 8-16-11
4.7 PERFORM ANCE/CRITERION 7 – PROCUREMENT
How are the requirements established for the procurement of items and services? Do the
requirements include performance specifications and acceptance criteria provided by the
design authority and expectations?
Are procurement document changes managed and controlled at the same level as the original
procurement document? Does this process require design authority approval of changes to
design requirements?
Does a system exist to evaluate and select prospective suppliers based on specified criteria?
Does a system exist for identification of potential suspect/counterfeit items and the
prevention of their procurement? Does the organization have standard contract clauses for
this purpose?
Is supplier documentation managed and controlled?
How are processes established and implemented to ensure that approved suppliers continue
to provide acceptable items and services? Is such a process graded to ensure that safety-
related items and mission-critical items are subject to more rigorous methods (e.g., inspection
and testing at the manufacturer and upon receipt)?
4.8 PERFORM ANCE/CRITERION 8 – INSPECTIONS AND ACCEPTANCE
TESTING
How are inspections and tests specified for items, services, and processes? How are
acceptance and performance criteria established and used?
Are inspection and acceptance tests planned and controlled?
Does a system exist for documenting the results of inspections and tests?
Is inspection and test equipment controlled by a process to ensure it is calibrated and
maintained?
4.9 ASSESSMENT/CRITERION 9 – MANAGEMENT ASSESSMENT
Does the QA program description describe how managers, at all levels, assess their
management processes?
Does the QA program description provide for the identification and correction of
problems that hinder the organization from achieving its objectives?
Do managers take responsibility for, and directly participate in, the assessments?
Has third party certification been considered? Used?
Is DOE G 414.1-1B used to develop the management assessment process?
4.10 ASSESSMENT/CRITERION 10 – INDEPENDENT ASSESSMENT
Has the independent assessment process been adequately defined and documented?
Are independent assessments (e.g., audits) planned and conducted to measure item and
DOE G 414.1-2B Appendix B
8-16-11 A-7 (and A-8)
service quality, to measure the adequacy of work performance, and to promote
improvement?
Does the group performing independent assessments have sufficient authority and
freedom from line management (i.e., it is not directly responsible for the work being
assessed)?
Section 38
Are the persons conducting independent assessments technically qualified and/or
knowledgeable in the areas to be assessed?
Does a process exist to obtain technical experts for assessments when none are available in
the organization?
Has third party certification been considered? Used?
Is the independent assessment process applied to internal and external organizations?
Does a system exist for reporting assessment results to responsible management and
for assuring that action is taken to correct identified issues?
Is senior management informed of assessment results and engaged in ensuring
responsible management response to identified issues?
Are DOE G 414.1-1B and appropriate national standards used to develop the independent
assessment process?
DOE G 414.1-2B Appendix B
8-16-11 B-1
APPENDIX B: REFERENCES
The following references provide requirements and acceptable methods for implementing many
of the quality assurance (QA) requirements of DOE O 414.1D, Quality Assurance, dated 04-25-
11 and 10 C.F.R. Part 830 Subpart A. No single reference fully addresses all QA requirements.
The principles, recommended approaches, and applications contained in these references may be
used with the QA requirements to develop an effective quality system.
Most of the documents listed here are accessible online. DOE Orders, Policies, Manuals,
Guides, and Standards are available at www.directives.doe.gov; C.F.R.s, OMB Circulars and
Public Laws may be accessed at www.gpoaccess.gov; and NRC documents are available at
www.nrc.gov.
1.0 RELATED GOVERNMENT POLICIES, RULES, AND ORDERS
10 C.F.R. Part 820, Procedural Rules for DOE Nuclear Activities Facilities.
10 C.F.R. Part 830, Nuclear Safety Management.
36 C.F.R., Chapter XII, Subchapter B, Subpart A, Federal National Archives
and Records Administration.
48 C.F.R. Parts 1–99, Federal Acquisition Regulations System.
48 C.F.R. 970, Department of Energy Acquisition Regulation (DEAR), DOE Management
and Operating Contracts.
DOE O 200.1A, Information Technology Management, dated 12-23-08.
DOE O 210.2A, DOE Corporate Operating Experience Program, dated 4-8-11.
DOE O 221.1A Reporting Fraud, Waste and Abuse to the Office of Inspector General, dated
4-19-08.
DOE O 226.1B, Implementation of Department of Energy Oversight Policy, dated 4-25-11.
DOE O 231.1B, Environment, Safety and Health Reporting, dated 6-27-11.
DOE O 252.1A, Technical Standards Program, dated 2-23-11.
DOE O 360.1C, Federal Employee Training, dated 7-8-11.
DOE O 414.1D, Quality Assurance, dated 4-25-11.
Appendix B DOE G 414.1-2B
B-2 8-16-11
DOE O 420.1B, Facility Safety, Chg 1: 4-19-10.
DOE O 422.1, Conduct of Operations, dated 6-29-10.
DOE O 426.1, Federal Technical Capability, dated 11-19-09, Chg 1: 9-20-11.
DOE O 426.2, Personnel Selection, Training, Qualification, and Certification Requirements for
DOE Nuclear Facilities, dated 4-21-10.
DOE O 436.1, Departmental Sustainability, dated 5-2-11.
DOE P 426.1, Federal Technical Capability, Chg 1: dated 9-20-11.
DOE O 450.2, Integrated Safety Management, dated 4-25-11.
DOE P 450.4A, Integrated Safety Management System Policy, dated 4-25-11.
Public Law 104-113, National Technology Transfer and Advancement Act of 1995.
2.0 RELATED GUIDES, MANUALS AND STANDARDS
DOE-EM-SRP-2001, Standard Review Plan (SRP) Protocol for QAP/QIP Review, Protocol for
EM-HQ Review/Field Self-Assessment of Site-Specific Quality Assurance Programs
(QAPs)/Quality Implementation Plans (QIPs), 2nd Edition, March 2010.
Section 39
DOE G 413.3-2, Quality Assurance Guide for Project Management, dated 6-27-08.
DOE G 414.1-1B, Management and Independent Assessments Guide for Use with 10 C.F.R.,
Part 830, Subpart A, and DOE O 414.1C, Quality Assurance; DOE M 450.4-1, Integrated
Safety Management System Manual; and DOE O 226.1A, Implementation of DOE Oversight
Policy, dated 9-27-07.
DOE G 414.1-4, Safety Software Guide for use with 10 C.F.R 830, Subpart A, Quality
Assurance Requirements, and DOE O 414.1C, Quality Assurance, dated 6-17-05.
DOE G 450.4-1C, Integrated Safety Management System Guide, dated 9-29-11DOE G 450.3-3,
Tailoring for Integrated Safety Management Applications, dated 2-1-97.
DOE G 1324.5B, Implementation Guide for 36 C.F.R. Chapter XII - Subchapter B,
dated 7-19-96.
DOE O 232.2, Occurrence Reporting and Processing Operations Information, dated 1-1-12
DOE-NE-STD-1004-92, Root Cause Analysis Guidance Document, dated February 1992.
DOE G 414.1-2B Appendix B
8-16-11 B-3
DOE/NNSA, Weapon Quality Policy (QC-1), Rev. 10, dated 2-10-04.
DOE/RW-0333P, Office of Civilian Radioactive Waste Management, Quality Assurance
Requirements and Description, Rev. 13.
DOE-STD-1150-2002, Quality Assurance Functional Area Qualification Standard, dated April
2002.
DOE-STD-1172-2011, Safety Software Quality Assurance Functional Area Qualification
Standard, dated March 2011.
DOE-STD-1189-2008, Integration of Safety into the Design Process, dated March 2008.
Office of Management and Budget Circular A-119, Federal Participation in the Development
and Use of Voluntary Consensus Standards and in Conformity Assessment Activities, dated
2-10-98.
American National Standards Institute (ANSI)/American Society for Quality (ASQ), Z
1.13-1999, Quality Guidelines for Research, 1999.
ANSI/National Conference of Standards Laboratories, Z540-1-1994, Calibration
Laboratories and Measuring and Test Equipment: General Requirements, 1999.
ANSI/International Organization for Standardization (ISO)/American Society for Quality
(ASQ) Q9001:2008, Quality Management Systems: Requirements, 2008.
ANSI/ISO/ASQ Q9004:2000, Quality Management Systems: Guidelines for Performance
Improvements, 2001.
ANSI/ISO/ASQ QE19011S-2004, Guidelines for Quality and/or Environmental Management
Systems Auditing, U.S. Version with supplemental guidance added.
ANSI/ASQ E4-2004, Standard: Quality Systems for Environmental Data and Technology
Programs – Requirements with Guidance for Use, 2004.
American Society of Mechanical Engineers (ASME) NQA-1-2008, Quality Assurance
Requirements for Nuclear Facility Applications, Part 1, Subpart 2.7, 2001.
ASME NQA-1, Subpart 4.1, Application Appendix: Guide on Quality Assurance Requirements
for Computer Software
ASME NQA-1a-2009, Addenda A to Quality Assurance Requirements for Nuclear Facility
Applications, dated 8-31-09.
International Atomic Energy Agency IAEA-TECDOC-1169, Managing Suspect and
Counterfeit Items for the Nuclear Industry, 2005.
Appendix B DOE G 414.1-2B
B-4 8-16-11
IAEA-TECDOC-1090, Quality Assurance within Regulatory Bodies, dated June 1999.
IAEA-GS-R-3, Management Systems for Facilities and Activities, 2006.
3.0 RELATED REFERENCES
Intergovernmental Data Quality Task Force, Uniform Federal Policy for Quality Assurance
Project Plan – Evaluating, Assessing, and Documenting Environmental Data Collection and
Use Programs, EPA: EPA-505-B-04-900A; DoD: DTIC ADA 427785; DOE: DOE/EH-
0667, Version 2, dated March 2005.
Section 40
American National Standard ANSI/ASQC E4-1994, Specifications and Guidelines for Quality
Systems for Environmental Data Collection and Environmental Technology Programs, dated
1-3-95.
American Society for Nondestructive Testing (ASNT) ASNT-CP-105-2006, ASNT Standard
Topical Outlines for Qualification of Nondestructive Testing Personnel.
DOE-STD-3009-94, Preparation Guide for U.S. Department of Energy Nonreactor Nuclear
Facility Documented Safety Analyses, dated July 1994.
DOE-STD-1025-2008, Weapon Quality Assurance Qualification Standard
DOE-STD-1027-92, Hazard Categorization and Accident Analysis Techniques for Compliance
with DOE O 5480.23, Nuclear Safety Analysis Reports, dated December 1992.
Electric Power Research Institute (EPRI) Guideline NP-5652, Guideline for the Utilization of
Commercial Grade Items in Nuclear Safety Related Applications (NCIG-07), 1988 Rev.,
dated June 1988.
EPRI Guideline TR-102260, Supplemental Guidance for the Application of EPRI Report NP-
5652 on the Utilization of Commercial-Grade Items.
ISO/IEC 17025, General Requirements for the Competence of Calibration and Testing
Laboratories, 2005.
U.S. Nuclear Regulatory Commission (NRC) NUREG 0856, Final Technical Position on
Documentation of Computer Codes for High-Level Waste Management, 1983.
NRC NUREG/CR-5151, Performance-Based Inspections, dated June 1988.
NRC Regulatory Guide 1.28, Quality Assurance Program Criteria (Design and Construction),
Rev. 4, dated June 2010.
NRC Regulatory Guide 1.33, Quality Assurance Program Requirements (Operation), Rev. 2,
dated February 1978.
DOE G 414.1-2B Appendix C
8-16-11 C-1
APPENDIX C: DEFINITIONS
Certificate of Conformance. A document signed or otherwise authenticated by an authorized
individual certifying the degree to which items or services meet specified requirements.
Certified Material Test Report (CMTR). A written and signed document that is approved by a
qualified party and contains data and information that attests to the actual properties of an item
and the actual results of all required tests.
Commercial Grade Item. An item that is: a) not subject to design or specification requirements
that are unique to nuclear or mission critical facilities or activities; b) used in applications other
than nuclear or mission-critical facilities or activities; and c) to be ordered from the
manufacturer/supplier on the basis of specifications set forth in the manufacturer’s published
product description (e.g., a catalog).
Contractor. For purposes of the directives system, corporate organizations under contract with
DOE to perform services with the clause at DEAR 970.5204-2, laws, regulations, and DOE
directives, in their contract. [Note: This definition of contractor does not include all of the
procurement contracts entered into by DOE.] (Source DOE O 251.1C). A contractor is an all-
inclusive term used for the corporation, company or affiliates, entities, partners, etc., where the
contractor is a LLC or partnership consisting of two or more partner corporations.
Commercial Grade Dedication. An acceptance process undertaken to provide reasonable
assurance that a commercial grade item to be used in a safety system or mission essential facility
meets specified requirements. This assurance is achieved by identifying the critical
characteristics of the item and verifying their acceptability by inspections, tests, or analyses
performed by the purchaser or third party dedicating entity after delivery, supplemented as
necessary by one or more of the following: commercial grade surveys, product inspections or
witness at hold points at the manufacturer’s facility, and analysis of historical records for
acceptable performance.
Section 41
Engineering Evaluation. A technical review conducted by qualified engineering and other
technical personnel using accepted methods to determine the actual or potential cause of a
substantial safety hazard and the effect of an S/CI.
Nonconformance. A deficiency in characteristic, documentation, or procedure that renders the
quality of an item or activity unacceptable or indeterminate.
Quality System: A structured and documented management system describing the policies,
objectives, principles, organizational authority, responsibilities, accountability, and
implementation plan of an organization for ensuring quality in its work processes, products
(items), and services. The Quality System provides the framework for planning, implementing,
and assessing the work performed by an organization and for carrying out required quality
assurance (QA) and quality control (QC) activities (source: ANSI/ASQC E4).
Appendix C DOE G 414.1-2B
C-2 8-16-11
Safety System. A DOE nuclear and nonnuclear facility structure, system, or component of
which the preventive or mitigative function is a major contributor to defense-in-depth (i.e.,
prevention of uncontrolled material release) or worker safety as determined from hazard
analysis. Also, a DOE structure, system, or component, including a primary environmental
monitor or a portion of a process system, the failure of which could adversely affect the
environment, safety, or health of the public or workers.
DOE G 414.1-2B Appendix D
8-16-11 D-1
APPENDIX D: ACRONYMS
ANSI American National Standards Institute
ANST American Society for Nondestructive Testing
ASME American Society of Mechanical Engineers
ASQ American Society for Quality
C.F.R. Code of Federal Regulations
CGD Commercial Grade Dedication
CHRIS Corporate Human Resources Information System
CRD contractor requirements document
DCS Data Collection Sheet
DEAR Department of Energy Acquisition Regulation
DI Defective Items
DoD Department of Defense
DOE Department of Energy
EFCOG Energy Facility Contractors Group
EM Environmental Management
EPA Environmental Protection Agency
FAR Federal Acquisition Regulation
FQA Fastener Quality Act
FRA Functions, Responsibilities, and Authorities
FRAM Functions, Responsibilities, Authorities Manual
GC General Counsel
GIDEP Government-Industry Data Exchange Program
HSS Health, Safety and Security
IAEA International Atomic Energy Agency
IG Inspector General
INPO Institute of Nuclear Power Operations
ISMS Integrated Safety Management System
ISO International Organization for Standardization
MAPEP Mixed Analyte Performance Evaluation Program
M&TE Measuring and Test Equipment
NIST National Institute of Standards and Technology
NNSA National Nuclear Security Administration
NQA Nuclear Quality Assurance
NRC Nuclear Regulatory Commission
NTC National Training Center
OE Operating Experience
OIG Office of Inspector General
OMB Office of Management and Budget
ORPS Occurrence Reporting Processing System
PSO Program Secretarial Office
QA Quality Assurance
QAP Quality Assurance Program
Appendix D DOE G 414.1-2B
D-2 8-16-11
QIP Quality Assurance Implementation Plan
S/CIs Suspect and Counterfeit Items
SMS Safety Management System
SSC Structures, Systems and Components
STD Standard
SQA Software Quality Assurance
UFP-QS Uniform Federal Policy for Implementing Environmental
Quality Systems
USPTO U.S. Patent and Trademark Office
V&V Verification and Validation
DOE G 414.1-2B Attachment 1
8-16-11 Page-1 (and Page 2)
Section 42
[QUALITY ASSESSMENT PLAN TEMPLATE]
Quality Assurance Assessment Plan
For ______________________
Office of
__________________________________
Department of Energy
Office of _______________________
Date:
DOE G 414.1-2B Attachment 1
8-16-11 Page-3
CONTENTS
1
.
SCOPE ............................................................................................................ Page 4
2
.
OBJECTIVE: ................................................................................................. Page 4
3
.
REQUIREMENTS ......................................................................................... Page 4
4
.
ASSESSMENT TEAM .................................................................................. Page 5
5
.
ACTIVITIES TO BE ASSESSED .......................................................................... Page 5
6
.
ORGANIZATIONS TO BE NOTIFIED ................................................................ Page 12
7
.
APPLICABLE RECORDS, INTERVIEWS, OBSERVATIONS ....................... Page 12
8
.
SCHEDULE ................................................................................................... Page 13
9 APPENDIX 1-A. ASSESSMENT TEAM MEMBERS’ BIOGRAPHICAL
INFORMATION ............................................................................................ Page A-1
This assessment plan template is intended for use by the DOE for planning and
assessing DOE Site Office QA implementation. It provides a broad based starting point
for developing an assessment plan and lines of inquiries that should be supplemented
by local requirements. Users are expected to limit the scope and focus the plan on the
specific areas of interest for the given assessment. This template may be easily modified
for use by DOE to plan and conduct assessments of contractor QAP implementation.
Attachment 1 DOE G 414.1-2B
Page 4 8-16-11
1.0 SCO PE
This assessment is considered a preliminary assessment of the implementation of QA
policies and principles in ______________ operations related to ____________ activities.
The areas of interest or activities to be assessed are identified in Section _____.
(1) Program –
(2) Personnel Training and Qualification –
(3) Quality Improvement –
(4) Documents and Records –
(5) Work Processes –
(6) Design –
(7) Procurement –
(8) Inspections and Acceptance Testing –
(9) Management Assessment –
(10) Independent Assessment –
(11) Software Quality Assurance –
(12) Suspect/Counterfeit Items Prevention –
(13) Corrective Action Management Program –
(14) Integrated Safety Management – __________
A follow-up assessment, pending the outcome of this assessment, is anticipated on or about
_________
2.0 OBJECTIVE
To provide feedback for continuous improvement: A process is established and effectively
implemented to continuously improve safety and improve the efficiency and quality of
operations. Procedures and mechanisms are in place to implement integrated safety
management and quality assurance programs through approved program plans.
3.0 REQUIREMENTS
DOE O 414.1D, Quality Assurance
10 C.F.R. 830, Nuclear Safety Management
DOE P 450.4, Safety Management System Policy
Site-specific QA documentation
DOE G 414.1-2B Attachment 1
8-16-11 Page 5
Site-specific ISMS documentation
Organization or Site-specific functions, responsibilities, and authorities manual/functions,
responsibilities, and authorities (FRAM/FRA)
4.0 ASSESSMENT TEAM
Section 43
The Assessment Team will be composed of the following individuals:
___________________________________ Team Leader
___________________________________ (Observer)
___________________________________ (Observer)
Brief biographical information for each team member is provided in Appendix 1-A.
5.0 ACTIVITIES TO BE ASSESSED
The Assessment Team will review the implementation of Quality Assurance (QA) and Integrated
Safety Management Systems (ISMS) by evaluating some of the primary ___________ functions
and high-risk ____________ activities. The Team will focus on __________________
function(s) and a selected set of high-risk (hazard) activities. The Team will choose which
activities to evaluate from a list of activities prioritized by risk provided by ___________ prior to
or at the initial briefing. For a chosen activity, the ____________________________ topics will
be evaluated by “drilling down” into the activity by lines of inquiry. Personnel interviews and
observations may be utilized as determined by the Team while on-location.
As lines of inquiry are being pursued, the Team will also evaluate a number of general QA and
ISMS topics, including ____________________________________________. Spot-checks of
QA and/or ISMS implementation in __________________________ may also be conducted
during the assessment of the major activities.
The initial lines of inquiry listed below will be utilized during evaluation of specific work
processes.
5.1 REVIEW AREA 1 – PROGRAM
1. Review the organization and reporting chain (Criterion 1, DOE O 414.1D) to ensure
that clear lines of authority are established and utilized.
What is the organization structure of this activity?
Has the organization selected and integrated a national or international standard into the
QAP description and implementing procedures?
Are functional responsibilities for QA defined and implemented for this activity?
What is the organization structure of the QA oversight of this activity?
Is the QA organization independent of the line management organizations?
Attachment 1 DOE G 414.1-2B
Page 6 8-16-11
What is the commitment of upper, middle, and lower management to the QA program
and its implementation?
How is Quality policy promulgated and Quality improvement implemented throughout
the organization associated with this activity?
Are QA audits, surveillances, and nonconformance reports part of the QA program?
What are the QA interface points with organizations that support this activity, and how
is QA communicated to and implemented through them?
What is the process for determining the QA requirements for _____ and/or its
contractors for this activity, and what is the review/approval/ implementation status of
this process?
How are quality problems identified, documented, corrected, and prevented in the future
for this activity?
How are Readiness Assessment and Operational Readiness Review results integrated
with quality improvement and operational efficiency?
How are quality and efficiency improvements implemented, and how are lessons learned
applied to this activity?
2. Review the graded approach and any criteria for determining what QA management
requirements are implemented for various types of work.
What are the levels of risk associated with an activity?
What is the process for grading the application of QA requirements for activities? Does
it identify consequences, requirements, and depth/extent/rigor necessary in application
of those requirements?
Section 44
What is the level of commitment of this activity’s senior management to QA?
What are the greatest concerns regarding QA and ISMS implementation?
Are controls and verifications applied to this activity consistent with their importance to
safety, cost, schedule, and success of this mission?
Are controls documented and communicated to personnel involved in this activity to
ensure appropriate application and implementation?
3. Review and approval of contractor QAPs for selected high-risk activities.
What is the QA program description?
Is the QA program description approved? If not, when will it be approved?
What is the review process for the approval of the QA program description for this
activity?
What is the process for determining the QA requirements for _____ and its contractor(s)
for this activity, and what is the review/approval/implementation status of this process?
What is/are the major contractor’s QA program descriptions, and is it/are they
implemented?
DOE G 414.1-2B Attachment 1
8-16-11 Page 7
5.2 REVIEW AREA 2 – PERSONNEL TRAINING AND QUALIFICATION
Evaluate the status of implementation of a training and qualification program that ensures
personnel are capable of performing their assigned work.
What is the organization’s documented training plan? Is it adequate and effective? How
are training requirements established? What is the review and approval process?
Does the organization have adequate resources, processes, and responsible elements to
support the selection, training, and qualification of personnel conducting work?
Does the training and qualification program describe the positions and functions to
which it applies?
How are certifications and special qualifications (e.g., auditors, subject matter experts,
nondestructive examination personnel, welders, etc.) established and maintained
current?
How is proficiency established and maintained for operational positions and/or
functions?
How is on-the-job training established and maintained?
How is the required reading program established and maintained?
5.3 REVIEW AREA 3 – QUALITY IMPROVEMENT
1. Evaluate the status of implementation of a quality improvement process to detect and
prevent quality problems.
Do established work processes and procedures adequately identify and report quality
problems?
Does senior management policy encourage problem detection and prevention?
What are the existing processes for communicating lessons learned and
performance information? Are they adequate? Are they effective?
How is the significance of quality problems categorized and prioritized?
Does this quality improvement process provide for the identification of the causes of
problems? Does it require identification of actions to prevent recurrence? Are both of
these required as part of the problem correction process? Is implementation effective?
How are cause, extent, and remedial and preventative actions for quality problems
addressed?
2. Evaluate the approach to identification, control, and correction of items, services,
and processes that do not meet established requirements (nonconforming).
What procedures determine which disciplines or functions evaluate and disposition the
nonconforming item, service, or process? Are they adequate?
What procedures identify and control nonconforming items to prevent their inadvertent
use? Are these procedures adequate?
How are quality problems associated with services and processes documented and
corrected?
Section 45
Attachment 1 DOE G 414.1-2B
Page 8 8-16-11
3. Evaluate the process to review item characteristics, process implementation, and other
quality-related information to identify items, services, and processes needing improvement.
What quality performance analysis system is in place (e.g., six sigma, metrics and
indicators, trending)? Is it adequate?
How does the performance analysis system provide for feedback to affected and related
organizations or groups?
5.4 REVIEW AREA 4 – DOCUMENTS AND RECORDS
1. Evaluate the process for preparation, review, approval, issue, use, and revision of documents
that prescribe processes, requirements, and design.
What is the approved document control system providing the above functions? Is it
documented? Does it clearly describe responsibilities and functions? Is it adequate?
Are key functions, such as procedures, related to the quality criteria (e.g., design,
procurement, work control, inspection, testing) described in reviewed and approved
documents?
Are key work processes and associated activities and functions in the FRA supported
by documentation?
2. Evaluate the process for specification, preparation, review, approval, and maintenance of
records.
What is the approved and documented records management system providing the above
functions? Is it adequate?
Are the requirements of the National Archives and Records Administration addressed?
What is the quality records standard applied to the applicable contract(s), and is it fully
implemented?
5.5 REVIEW AREA 5 – WORK PROCESSES
Evaluate the implementation of quality management principles in work processes.
Are the methods adequate for ensuring that work is performed consistent with technical
standards, administrative controls, and other hazard controls?
Are the core functions and guiding principles of ISMS addressed in work processes?
Do the approved instructions, procedures, and other appropriate means for the work
processes meet regulatory or contract requirements?
What are the methods that identify and control items to ensure their proper use? What
are the methods that maintain items to prevent their damage, loss, or deterioration? Are
these methods adequate? (see Review Area 3, items 2 and 3 of this Attachment.)
What are the requirements for and methods of ensuring adequate calibration and
maintenance for equipment used for process monitoring or data collection? Are they
adequate?
DOE G 414.1-2B Attachment 1
8-16-11 Page 9
Is there an adequate system in place for use and control of software in accordance with
DOE G 414.1-4?
5.6 REVIEW AREA 6 – DESIGN
Evaluate the implementation of quality management principles in design.
How has this office determined whether it performs actual design work? If not, how is
oversight of contractor design addressed and documented? How is the training and
qualification of personnel carried out for this oversight of design?
Are appropriate standards and sound engineering and scientific principles applied to
design items and processes? How is this documented? Is the graded approach utilized
properly?
Is the use of software in the design and safety analysis process controlled in accordance
with DOE G 414.1-4?
What method is used to incorporate applicable requirements and design bases in design
work?
Section 46
Are design changes controlled at the same level as the design?
How are design interfaces identified and controlled, within the design authority and
externally with customers and suppliers, including subcontractors?
What is the process for design verification and/or validation for design products? Is it
adequate? Are individuals other than those performing the design work utilized?
Is the design work verified/validated before approval and implementation of design?
What is the system for engineering involvement in the identification, analysis, and
control of suspect/counterfeit items that could affect safety? Is it documented? Is it
adequate?
5.7 REVIEW AREA 7 – PROCUREMENT
1. Review contract List A/List B requirements for proper flow down to contractors of DOE O
414.1D and/or 830 Subpart A requirements.
Review the list of contractors.
Review _____________________________ contract (Team will select).
What is the schedule of assessments for this contractor?
For this contractor, how are quality problems identified, documented, reported,
corrected, and prevented in the future?
How are past assessment results implemented?
How are flow down requirements to subcontractors verified? Tracked?
How does __________ ensure that the QA program description and ISMS are
implemented for all contractors?
How does the Field Office assessment program of this contractor continuously
improve quality and efficiency of operations?
Review recent Customer Review Survey for activities of this contractor. How is
feedback relayed to the contractor? What are the follow through activities?
Attachment 1 DOE G 414.1-2B
Page 10 8-16-11
How are contractor commitments tracked? Enforced?
How are new QA and ISMS requirements incorporated into existing contracts?
2. Evaluate the process for review of proposals and selection of contractors, QA and ISMS
requirements flow down, customer requirements flow down
What is the contractor evaluation process used?
What is the process for determining customer requirements/specifications and
how are these requirements captured and incorporated in the contract?
How are QA and ISMS requirements flowed down to the contractor and
subcontractor?
How is the qualification of persons who evaluated the proposals determined?
Compare with training and qualification records in CHRIS.
Review Contractor Records retained. Are the records complete?
How are new QA requirements incorporated into new contracts?
5.8 REVIEW AREA 8 – INSPECTIONS AND ACCEPTANCE TESTING
Evaluate the process for inspections and acceptance testing of items, services, and processes.
What is the method for specifying inspections and tests for items, services, and
processes? Is it adequate?
How are acceptance and performance criteria established and utilized? Is the
graded approach applied satisfactorily?
What is the process for inspecting, testing, and accepting software products? Is it
adequate? What standards and requirements are invoked?
Are inspections and acceptance tests planned and controlled? How?
How are inspections and acceptance tests results documented?
Is inspection and test equipment calibration established and maintained? How?
How is traceability of calibration maintained? Is it adequate?
5.9 REVIEW AREA 9 – MANAGEMENT ASSESSMENT
Section 47
Evaluate the assigned responsibility for _________ implementation of Management Assessment
(Criterion 9 DOE O 414.1D) for selected activities.
What is the schedule of management assessments?
How was the risk model utilized to determine assessment areas, schedule, and rigor?
Does the management assessment program include all levels of management? If so,
how?
Are managers actively involved in the assessment or relying on others for the
assessment?
How are quality problems identified, documented, reported, corrected, and prevented in
the future?
How are past management assessment results implemented?
DOE G 414.1-2B Attachment 1
8-16-11 Page 11
How does the management assessment program continuously improve quality and
efficiency of operations?
How was result of the assessment incorporated in the lessons learned program?
5.10 REVIEW AREA 10 – INDEPENDENT ASSESSMENT
Evaluate the assigned responsibility for ____________ implementation of Independent
Assessment (Criterion 10, DOE O 414.1D for selected activities.
What is the schedule of independent assessments for this activity?
How was the risk model utilized to determine assessment areas, schedule, and rigor?
Is the independent assessment program adequately defined and documented?
By what criteria are assessors chosen for independent assessments?
What is the process for reporting independent assessment results and required
corrective actions to responsible management?
How are past independent assessment results tracked through completion of corrective
actions?
How are past independent assessment results implemented?
What performance parameters does the independent assessment program measure?
How does the independent assessment program continuously improve quality and
efficiency of operations?
How was result of the assessment incorporated in the lessons learned program?
5.11 REVIEW AREA 11 – SOFTWARE QUALITY ASSURANCE
Evaluate the status of implementation of a software QA program.
What safety-related software packages does the contractor use?
What DOE SQA policies and requirements exist for these software packages? Are
these incorporated into a formal QA program by the contractor?
Does the contract include anything specific with regard to DOE SQA policy and
requirements?
What are oversight processes/activities for SQA? Has there been any assessment to
date either independently or as part of other QA or performance assessments?
5.12 REVIEW AREA 12 – SUSPECT/COUNTERFEIT ITEMS PREVENTION
Review the oversight of the S/CI Prevention process implementation.
Does the contractor have an S/CI process in place?
What is the oversight process for this activity?
What are the findings/observations of the most recent two assessment of this program?
What are the corrective actions initiated to address any issues? How are these tracked?
Attachment 1 DOE G 414.1-2B
Page 12 8-16-11
5.13 REVIEW AREA 13 – INTEGRATED SAFETY MANAGEMENT
Review the integration of ISMS into the overall quality assurance program for selected high risk
activities.
What is the management system utilized for implementing ISMS for this activity?
What are the roles and responsibilities for ISMS implementation? Are they clearly
defined/documented? Are they implemented?
What is the process for feedback and continuous improvement in ISMS
Section 48
implementation?
How are ISMS lessons learned applied to this activity?
Are ISMS line management responsibilities defined and implemented?
What work controls are in place to ensure safety?
What is the process for determining and grading the application of ISMS requirements?
What is the commitment of upper, middle, and lower management to the ISMS and its
implementation?
How are Readiness Assessment and Operational Readiness Review results integrated
with ISMS and operational efficiency?
What are the greatest concerns regarding ISMS implementation?
6.0 ORGANIZATIONS TO BE NOTIFIED
List the organizations to be assessed and other appropriate organizations that should be notified
prior to the assessment.
7.0 APPLICABLE RECORDS, INTERVIEWS, AND OBSERVATIONS
The Assessment Team will require support from __________ to do an effective assessment. The
Team has identified preliminary list of records, interviews, and observations of interest. It
should be noted that additional ones may be identified as the assessment progresses.
__________ should be prepared to provide in advance the records and documents identified and
make the required individuals available for the interviews.
Record Review:
FRAM
Quality Assurance Program Description
ISMS Description
Contract List A/List B requirements
Contractor QAP approval
List of current projects and activities
Management Assessment schedule
Independent Assessment schedule
DOE G 414.1-2B Attachment 1
8-16-11 Page 13
For ISMS:
Oversight Assessment Plan for FY____
FY____ Safety Performance Objectives
Current _____ ISMS Description
Contractor ISMS Description
Contract Section I DEAR Clauses 970.5223-1 and 970.5204-2
Interviews:
Senior Management (closeout)
Facility and Operations Team Leader
Quality and Safety Division Director
Quality Assurance and Process Management Team Leader
Quality Assurance Subject Matter Expert
Facility and Materials Disposition Division Acting Director
Waste Disposition Division Acting Director
Lead Facility Representative
Facility Engineers
Others as needed
Observations:
Any Management Assessment in progress
Any Independent Assessment in progress
Oversight or surveillance of contractor’s S/CI process implementation
Corrective action status or planning meeting
Software QA activity
Performance measure status meeting
Effectiveness verification of any ISMS improvement action
8.0 SCHEDULE
Table 1, below, lays out the proposed schedule for the assessment. The Assessment Team will
arrive at the site on _____, _____. The briefing shown in Figure 1 will commence as soon as the
Team arrives on site, which is expected to be ________.
The activities in the following _____ days will include interviews of key personnel and may
include observations of activities. The Assessment Team Leader, in conjunction with
___________ management will identify the individuals that need to be invited for discussions
and the activities to be observed.
Attachment 1 DOE G 414.1-2B
Page 14 8-16-11
Table 1: Proposed Assessment Schedule
Date:
Time: Travel to:
Time: Briefing
Review list of current high-risk activities
Determine schedule for closeout meeting
Collect documents
Review documents
Date:
Time: ISMS Integration into QA
Graded Approach definition, procedures, and
implementation
Time: Contractor Lists A and B
Specific Contracts and Procurement
Contractor Oversight
o QA program description review and approval
S/CI Implementation
Section 49
o CAMP
o Software QA
o Feedback and lessons learned
Date:
Time: Continue oversight elements
Time: New Contract(s) - Review Status
o QA requirements flow down
o Technical requirements flow down
o Bidders questions
Date:
Time: Management
Assessments Independent
Assessment
Additional Assessment Topics As Required
Time: Team meeting
Closeout meeting
Date:
Time: Travel back to DOE HQ
DOE G 414.1-2B Appendix 1-A
8-16-11 Page 1-A-1 (and 1-A-2)
APPENDIX 1-A: ASSESSMENT TEAM MEMBERS’ BIOGRAPHICAL INFORMATION
[Include the following information in the plan for the Team Leader and all members of the
Assessment Team]
Team Leader – Name & Title:
Experience:
Education:
Personal:
Team Leader – Name & Title:
Experience:
Education:
Personal:
Team Leader – Name & Title:
Experience:
Education:
Personal:
DOE G 414.1-2B Chg 1
9-27-11
ADMINISTRATIVE CHANGE TO
DOE G 414.1-2B, Quality Assurance Program Guide
LOCATION OF CHANGES:
Page Paragraph Changed To
Iii List of Appendices changed to reflect
deletion of B and relabeling of C-E
10 4.1.7.1 Appendix D Appendix C
37 5.5.2.3 Appendix B contains the location,
mailing address, telephone number, fax
number, and electronic mail address of
the local OIG offices.
The following link contains the
mailing address and telephone
number for the local OIG offices:
http://energy.gov/ig/contact-
us/field-offices
37 5.5.2.6 S/CI may be reported by letter,
telephone, fax, or electronic mail to
the appropriate OIG field office.
(See Appendix B.)
S/CI may be reported to the
appropriate OIG field office. (See
http://energy.gov/ig/contact-
us/field-offices for contact
information.)
B1-B3 Appendix B Deleted
C-1
through
E-2
Appendices C-E Relabeled to Appendices B-D