DOE G 413.3-9A, Project Reviews for Capital Asset Projects
Functional areas: Program Management, Project Management
This Guide is a tool for federal project directors (FPDs), integrated project teams and federal program managers in planning and executing project reviews outlined in DOE O 413.3B. It addresses the reviews that are conducted from outside the project team during the lifecycle of a project based on the critical decision (CD) milestones, complexity, and duration of a project. Supersedes DOE G 413.3-9 Chg1 (AdminChg)
Supersedes:
Version history and related documents
Supersedes
Earlier documents this one replaced.
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
AVAILABLE ONLINE AT: INITIATED BY:
www.directives.doe.gov Office of Project Management
DOE G 413.3-9A
9-14-2018
Project Reviews for
Capital Asset Projects
[This Guide describes acceptable, but not mandatory, means for complying with requirements.
Guides are not requirements documents and are not to be construed as requirements in any audit
or appraisal for compliance with associated rule or directives.]
U.S. Department of Energy
Office of Project Management
NOT
MEASUREMENT
SENSITIVE
http://www.directives.doe.gov/
DOE G 413.3-9A i (and ii)
9-14-2018
FOREWORD
This Department of Energy (DOE) guide is for use by all Departmental elements. This guide
assists project teams by outlining reviews and assessments that the Department completes in
executing capital asset projects to meet the requirements of DOE Order 413.3B, Program and
Project Management for the Acquisition of Capital Assets. This guide provides non-mandatory
information for fulfilling requirements contained in rules, regulatory standards, and DOE
directives. Guides are not requirements documents and are not to be construed as requirements in
any audit or appraisal for compliance. Send citations of errors, omissions, ambiguities, and
contradictions found in this guide to PMpolicy@hq.doe.gov.
mailto:PMpolicy@hq.doe.gov
DOE G 413.3-9A iii (and iv)
9-14-2018
TABLE OF CONTENTS
FOREWORD i
TABLE OF CONTENTS iii
1.0 PURPOSE AND SCOPE OF THIS GUIDE 1
2.0 NEED FOR PROJECT REVIEWS 1
3.0 REVIEW TYPES 2
3.1 Design Reviews 2
3.2 Earned Value Management System (EVMS) Review 4
3.3 Energy Systems Acquisition Advisory Board (ESAAB) Review 6
3.4 External Independent Review (EIR) 8
3.5 Independent Cost Review (ICR) and Independent Cost Estimate (ICE) 9
3.6 Independent Project Review (IPR) 11
3.7 Mission Validation Independent Review (MVIR) 12
3.8 National Environmental Policy Act (NEPA) Review 14
3.9 Operational Readiness Review (ORR)/Readiness Assessment (RA) 15
3.10 Project Definition Rating Index (PDRI) Assessment 17
3.11 Project Management Risk Committee (PMRC) Review 18
3.12 Project Peer Review (PPR) 20
3.13 Quarterly Project Review (QPR) 21
3.14 Technical Independent Project Review (TIPR) 22
3.15 Technology Readiness Assessment (TRA) 24
Appendix A: Project Reviews and when they are typically performed A-1
Appendix B: Acronyms B-1
Appendix C: References C-1
DOE G 413.3-9A 1
9-14-2018
1.0 PURPOSE AND SCOPE OF THIS GUIDE
This Guide is a tool for federal project directors (FPDs), integrated project teams and federal
program managers in planning and executing project reviews outlined in DOE O 413.3B. It
addresses the reviews that are conducted from outside the project team during the lifecycle of a
project based on the critical decision (CD) milestones, complexity, and duration of a project.
The guide is organized to summarize each review and provide 5Ws – what, why, when, who, and
where – of each review. The guide describes the content of the review (what), the purpose of the
review (why), when the review is to be conducted during the project lifecycle (when), the office
or entity responsible for executing the review (who), and where the review should take place
(where).
2.0 NEED FOR PROJECT REVIEWS
Section 2
Reviews help assure projects stay on track, within schedule and under budget. They are essential
for the Chief Executive for Project Management (CE), Project Management Executive (PME),
FPD, project manager, project team, and project stakeholders to maintain confidence that project
systems, processes, staffing, and technical efforts are integrated, effectively coordinated and
provide the needed information. Reviews also help to ensure that the project is progressing at an
effective and acceptable rate, particularly regarding established performance baselines (PBs).
Reviews provide peer and subject matter expert opinion and feedback on the project readiness to
proceed to the next stage in the project decision-making process. Although reviews are required
at key junctures by the CD process, FPDs may also recommend additional project reviews at
their discretion at any time if they encounter conditions, such as a project performance deviation,
or a significant risk event impacting the project, which warrant a review.
Reviews and evaluations are performed by several levels of management at various points in the
lifecycle of a project, including the project’s Initiation, Definition, and Execution phases.
Reviews and evaluations should be planned and structured using a tailored, or in the case of
nuclear safety reviews, graded approach. This means that while the applicable order
requirements must be addressed, reviews can be customized in their design depending on
project-specific attributes including review/decision objectives, scope, project size, cost,
technical complexity, findings from previous reviews, and emerging or intervening issues which
may not have been previously presented, defined or evaluated. Where an independent review
identifies a project practice that omits or alters an applicable Order requirement, the project team
in response should document its rationale for doing so.
Reviews and evaluations during the Initiation and Definition phases verify that projects support
the Department’s mission, goals, and strategic plans and that the projects can be successfully
performed within the funding range given applicable conditions such as site and installation
conditions, safety and security requirements, and other applicable regulatory and environmental
requirements. During these phases, the review process should evaluate technology alternatives
and maturation levels prior to granting approval for the project to proceed into design and
execution. This is the time to conduct reviews to verify that the project scope is matured and
well-defined prior to baselining the project.
2 DOE G 413.3-9A
9-14-2018
Reviews and evaluations during the Execution phase support ongoing validation of the project
technical scope, cost and schedule baseline. They ensure that the project is being successfully
executed according to plans and within established cost baselines. These reviews help project
teams increase their understanding of the project risks and improve management strategies. They
provide recommendations for improving the project’s technical scope, schedule, and cost
performance and support the project by developing recommendations and supporting data to
proceed or not proceed with subsequent lifecycle phases. Finally, they ensure agreed-upon
products are being delivered and performance parameters are being achieved.
3.0 REVIEW TYPES
Section 3
The reviews listed here are driven by requirements in DOE O 413.3B and are listed in
alphabetical order. Appendix A provides a table outlining when projects complete each type of
review relative to the CD milestones. This guide does not contain information on reviews of the
project documentation that may be needed to identify classified and controlled unclassified
information. Requirements for these reviews can be found in the applicable directives listed in
Appendix C.
3.1 Design Reviews
What: Design reviews are conducted to ensure design quality and maturity. They include
assessment of whether the design meets operational and functional objectives and whether
interface compatibility is adequately addressed. A design review evaluates design and
construction documents to confirm resolution of past issues and identify new issues before
committing to further work. A design review typically occurs at the end of each stage of design:
(1) conceptual design; (2) preliminary design; and (3) final design.
Each accepted solution or alternative produced during the conceptual design stage meets an
approved need, is deemed technically achievable and affordable, and provides the best value to
the Department. Research, development, testing and other efforts may be required to finalize a
concept. At a minimum, the conceptual design review should evaluate the following:
• Scope and preliminary Key Performance Parameters (KPPs) required to satisfy the
program mission requirements;
• Identification of requirements and features;
• Attainment of specified performance levels;
• Assessment of project risks and identification of appropriate risk handling strategies;
• Reliable cost and schedule range estimates for the alternatives considered;
• Project criteria and design parameters;
• Impact on the site sustainability plan; and
• Project feasibility.
A preliminary design meets all system requirements within acceptable risk levels and cost and
schedule constraints while establishing the basis for detailed design. It will validate the selected
design options, identified interfaces, and described verification methods. KPPs and the project
scope included have sufficient definition to update the cost estimate and cost range.
DOE G 413.3-9A 3
9-14-2018
The final design, completed prior to implementation, produces the final drawings, technical
specifications, and contract documents required to obtain quotes and bids for procurement and
construction. The final design should include clear testing requirements and acceptance criteria
for verifying the safety and functionality of all subsystems.
The results of a design review are documented in a report forwarded to the FPD and project
team for their information and action as the project progresses through the stages of design.
A conceptual design report should clearly and concisely describe the how project’s requirements
are met, especially those related to capabilities and capacities. It should also outline the
applicable design codes and standards.
A preliminary design report should demonstrate how the preliminary design meets all system
requirements within acceptable risk levels and cost and schedule constraints while establishing
the basis for detailed design.
The final design report confirms completion of the design, documents any changes made during
the review, ensures that the final design addresses all project requirements including the KPPs,
and signals readiness for project execution.
Section 4
Why: Design reviews confirm the level of maturity a project’s planning and designs have
attained. Technical Independent Project Reviews (TIPRs) and External Independent Reviews
(EIRs) consider the results of the design reviews.
When: As outlined in DOE O 413.3B, the conceptual design review occurs prior to CD-1. The
preliminary design review precedes CD-2 approval. For Hazard Category 1, 2, and 3 nuclear
facilities, the final design review precedes CD-2 approval. For non-nuclear facilities and less
than Hazard Category 3 nuclear facilities, the final design review precedes CD-3 approval.
Who: Project Team - The design manager leads reviewers external to the project to conduct
design reviews with support from the entire project design team.
Where: Design reviews occur at the project site. However, they could be performed at an offsite
location, if sufficient information and personnel to support the review process are available.
4 DOE G 413.3-9A
9-14-2018
For additional information refer to:
DOE-STD-1189, Integration of Safety into the Design Process,
https://www.standards.doe.gov/standards-documents/1100/1189-astd-2016
3.2 Earned Value Management System (EVMS) Review
What: An EVMS review determines if a contractor executing a capital asset project has an
EIA-748 (current edition) compliant EVMS. An EVMS integrates scope, schedule, and cost
parameters of high‐value, complex projects to manage and assess the overall performance of the
project while providing a basis for forecasting outcomes. The EIA-748 guidelines outline the
characteristics of a credible, reliable, and compliant EVMS. The EVMS review will:
• Assess the status of the contractor’s project management control system to include the
EVMS relative to the requirements of the contract and DOE O 413.3B.
• Determine if control systems generate project performance reports, the Federal IPT
analyzes the reports and contractor management, and that management actions taken
derive from the analysis.
• Determine how the project incorporates formal changes, conducts internal re-planning,
and retains flexibility to accommodate changes. Determine how well the project
documents, justifies, and explains changes, including those accepted retroactively.
Changes may correct errors, adjust accounting, or improve the accuracy of the
performance measurement data.
• Assess if a project contractor with a certified EVMS has an effective self-governance
system in place to maintain compliance with EIA-748 as evidenced by the contractor’s
EVMS or project control description and surveillance program.
• If the project contractor does not have a certified EVMS, assess the likelihood of the
EVMS receiving certification by CD-2 but no later than CD-3.
o Determine if efforts to prepare for an EVMS certification review, including the
review’s scheduling, will likely result in a timely certification.
o Where an EVMS certification review has occurred, determine the likelihood that the
project will resolve open issues sufficiently before establishment of the PB.
The Office of Project Management (PM) engages in four types of EVMS compliance
assessments with each described below:
Certification Review: A formal review to determine that a contractor’s EVMS, on all applicable
projects, fully complies with EIA-748 or as required by the contract, in accordance with either
FAR Subpart 52.234-4, EVMS, or another applicable EVMS clause.
https://www.standards.doe.gov/standards-documents/1100/1189-astd-2016
Section 5
DOE G 413.3-9A 5
9-14-2018
Implementation Review: A special type of surveillance performed in lieu of a certification
review that extends the certification of a contractor's previously certified system to another
facility, from one project to another project after a period of system non-use, from one certified
entity to another, or following significant changes to a certified system.
Review for Cause: A review of specific elements of the contractor’s EVMS that have displayed
a lack of discipline in application or may no longer meet the requirements of the EVMS
guidelines. The review determines if the contractor’s EVMS will retain its certification.
Surveillance Review: The process of reviewing a contractor's EVMS, on all applicable projects,
to assess its continuing compliance with EIA-748, or as required by the contract, in accordance
with either FAR Subpart 52.234-4, EVMS, or another applicable EVMS clause. Surveillance
begins following implementation of a compliant system.
The results of an EVMS review report include the finalized Corrective Action Requests
(CARs), Discrepancy Reports (DRs), and Continuous Improvement Opportunities (CIOs), and
documents the determination of guideline level compliance. The EVMS review director issues
the CARs/DRs to the contractor for the purposes of a factual accuracy review. The contractor
may provide comments relating to the accuracy of the facts and exhibits stated in the CAR/DR
that led to the determination; however, the intent is not to debate the overall conclusion of
non-compliance.
After the completion of the factual accuracy review, the final report is issued from PM-1. The
final report identifies the contractor’s next steps and requested timeframe for submittal of a
corrective action plan. In the case of a Review for Cause, the decision may be to de-certify the
contractor’s EVMS without proceeding through the Corrective Action Plan (CAP).
After the report with the CARs, DRs, and CIOs has been released, the EVMS review team chief
coordinates with the contractor to ensure understanding of the CARs/DRs and the requirements
of the CAP. The preparation of the CAP and progression is an iterative process, led by the
contractor but monitored by the EVMS review team. The steps for corrective actions are: 1)
establish contractor submittal date, 2) receive and review CAP, 3) provide comments, 4) monitor
progress.
The EVMS team plans, schedules, and approves all verification follow up actions and closure of
CARs/DRs. This may be done on site or remotely depending on the nature of the CAR/DR.
The contractor provides the evidence package for CAR/DR closeout. The CAR/DR will identify
the artifacts or other evidential products needed along with the verification methods that will
determine the effectiveness of the corrective actions taken.
The EVMS team reviews the evidence packages and discusses any questions with the contractor.
CARs/DRs are closed upon verification by the review team that the root cause(s) have been
properly identified and corrected.
Why: DOE contracts that address capital asset acquisitions with a TPC greater than $50M
typically invoke EVMS FAR clauses. A compliant EVMS enables the project team to objectively
6 DOE G 413.3-9A
9-14-2018
monitor scope, schedule, and cost during project execution. In addition, an EVMS allows for
forecasting costs based on earned value and actual costs.
Section 6
When: EVMS compliance assessment is conducted on the contractor’s system at various times,
based on contractual requirements, the lifecycle of the project, and implementation concerns.
The type of review conducted depends on the situation causing the review.
Who: Program Office and PM (if TPC is greater than $100M) - For contracts where there are
applicable projects having a TPC of $100M or greater, PM conducts an EVMS review to certify
the contractor’s EVMS complies with EIA-748, or as required by the contract. Contractors
supporting applicable projects with a TPC between $50M and $100M maintain an EVMS
compliant with EIA-748. Although DOE O 413.3B does not require an EVMS review for these
projects, PM conducts EVMS reviews on projects with a TPC between $50M and $100M at the
request of the Project Management Support Office (PMSO).
Where: EVMS reviews are normally conducted at the project site with the contractor providing
the EVM system description and data to support the review. However, they could be performed
at an offsite location, if sufficient information and personnel to support the review process are
available.
For additional information, refer to:
PM’s Earned Value Management System Webpage
https://community.max.gov/display/DOEExternal/PM+EVM+Home
DOE G 413.3-10A, Earned Value Management System (EVMS) Guide
https://www.directives.doe.gov/directives-documents/400-series/0413.3-EGuide-10a-admchg1
3.3 Energy Systems Acquisition Advisory Board (ESAAB) Review
What: The ESAAB advises the Secretary, CE, and PMEs on project management policy and
issues while advising the CE regarding CD milestones for Major System Projects (MSPs). The
Project Management Risk Committee (PMRC) supports the ESAAB.
https://community.max.gov/display/DOEExternal/PM+EVM+Home
https://www.directives.doe.gov/directives-documents/400-series/0413.3-EGuide-10a-admchg1
https://www.directives.doe.gov/directives-documents/400-series/0413.3-EGuide-10a-admchg1
DOE G 413.3-9A 7
9-14-2018
The ESAAB reviews all capital asset projects with a TPC of $100M or more. Based on analysis
provided by the program and other project management organizations, the ESAAB evaluates
project scope, schedule, and cost estimates, management oversight processes, technical
readiness, and other concerns that may affect a project’s successful delivery. The ESAAB
provides recommendations to the CE and PME regarding CDs, Baseline Change Proposals
(BCPs), and other project-related matters. The ESAAB may also identify uncertainties and risks
affecting successful project execution and advise how best to mitigate the uncertainties and risks.
In accordance with requirements outlined in DOE O 413.3B, the ESAAB reviews the following:
• All capital asset projects with a TPC of $100M or greater, focusing on projects at risk of
not meeting their PB;
• CD proposals for MSPs in support of the PME;
• BCPs in support of the PME; and
• Other topics selected by the Secretary or CE.
The results of an ESAAB appear in meeting minutes and memoranda that outline its findings
and recommendations to the CE, PME, and other officials. The ESAAB approves its
recommendations by a majority vote which ESAAB meeting minutes record.
Why: The ESAAB supports the Department of Energy’s strategic objective of achieving and
maintaining excellence in project management with its role and responsibilities detailed in
DOE O 413.3B.
Section 7
When: ESAAB reviews are event-driven as described above. The ESAAB meets at least
quarterly or when convened by the Chair. Projects requiring an ESAAB review will coordinate
scheduling the review through their program office who will make arrangements with the
ESAAB executive secretariat.
Who: ESAAB - The FPD or Program Office will prepare the necessary briefings and
presentations for the ESAAB. The executive secretariat will work with representatives of the CE
and PME to schedule the meeting or presentation.
8 DOE G 413.3-9A
9-14-2018
Where: ESAAB meetings occur at DOE headquarters. The FPD and the project team may
participate by teleconference.
For additional information, refer to:
PM ESAAB Webpage https://community.max.gov/display/DOEExternal/PM+ESAAB+Home
PM SOP Energy System Acquisition Advisory Board (ESAAB) Standard Operating Procedures
(SOP) https://community.max.gov/display/DOEExternal/PM+413.3+SOPs
3.4 External Independent Review (EIR)
What: In fiscal year 2000, Congress directed DOE to formalize and implement a process to
conduct EIRs. PM outlined this requirement in DOE O 413.3B, for all projects with a TPC of
$100M and greater. EIRs review scope, KPPs, schedule, and cost and are required prior to
establishing a performance baseline for projects with a TPC of $100M or greater. They validate
that:
• Schedules and costs are firmly supported with sound underlying planning and technical
assumptions;
• Designs are sufficiently mature to establish a PB with a high level of confidence (which
includes technology readiness, nuclear safety, security and quality assurance);
• The composition, skill set, and effectiveness of the integrated project teams (IPT)
appropriately match the needs of the project; and
• The Acquisition Strategy will position the project for a successful outcome.
PM or the PMSO coordinates all review activities through a collaborative process. During the
planning phase, project background information is assembled for the review committee or team.
A PM analyst, a DOE federal employee, leads an EIR team independent of the project comprised
of federal and contractor Subject Matter Experts (SMEs).
The results of an EIR appear in a report that PM-1 endorses and forwards to the PME for
review and action. The EIR report may include major findings, findings, and observations.
PM tracks all major findings and findings for resolution. The project team and FPD report back
to PM on how they have addressed major findings and findings. EIRs that occur prior to CD-2
will culminate in PM-1 validating the PB and recommending its approval to the PME. PM-1 will
not validate a PB until the project team has satisfactorily addressed all major findings.
Why: PM performs EIRs to provide PMEs, senior leaders within DOE, and Congress an
unbiased assessment of a project’s potential for meeting proposed scope, KPP, schedule and cost
commitments. For MSPs, a second EIR that precedes CD-3 assesses the readiness for
construction or execution while reconfirming the completeness and accuracy of the PB. In
addition to the review elements employed prior to CD-2, this pre-CD-3 EIR for MSPs considers
final drawings, specifications, and construction or execution plans.
https://community.max.gov/display/DOEExternal/PM+ESAAB+Home
https://community.max.gov/display/DOEExternal/PM+413.3+SOPs
DOE G 413.3-9A 9
9-14-2018
Section 8
When: PM performs an EIR prior to CD-2 for all capital asset projects with a TPC greater than
or equal to $100 million. PM performs a construction/execution readiness EIR prior to CD-3 for
MSPs per DOE O 413.3B. Prior to a BCP, PM will perform another EIR to validate the BCP PB.
Who: PM - PM conducts EIRs for projects with a TPC of $100M or greater in coordination with
the FPD and program office representative. The teams consist of senior-level technical personnel
and subject matter experts from the project as well as outside experts, as appropriate.
Where: EIRs normally occur at the project site. However, they could be performed at an offsite
location, if sufficient information and personnel to support the review process are available.
3.5 Independent Cost Review (ICR) and Independent Cost Estimate (ICE)
What: An ICR is a review of the project team’s estimate to examine the reasonableness of the
estimate considering quality, ground rules and assumptions, and risks. An ICE is a new estimate
performed by an organization independent of the project sponsor using the same detailed
technical and procurement information used by the project team.
Prior to CD-0, a DOE PM analyst will lead an ICR for all projects with an anticipated TPC
greater than or equal to $750M and for any other projects selected by the CE or PME. This ICR
evaluates the reasonableness of the project’s initial rough order of magnitude (ROM) cost
estimate based on mission need statement in order to roughly indicate future resource
requirements.
For projects with an anticipated TPC greater than or equal to $100M prior to CD-1, DOE PM
will determine whether to perform an ICR or an ICE based on confidence in the quality of the
project team’s range estimate. Either approach will give the Project Management Executive
(PME), DOE leadership, and Congress confidence that the project cost range, alternative
selected, and processes used in support of CD-1 are reasonable.
An ICE supports the following milestone approvals:
10 DOE G 413.3-9A
9-14-2018
• CD-1 (if factors such as risk and complexity create a significant cost exposure for DOE;
or as required by appropriations acts (e.g., 50 USC §2537(b) requires an ICE before
CD-1 and before CD-2 for each new nuclear facility within the nuclear security enterprise
that is estimated to cost more than $500M))
• CD-2 (required by appropriations acts)
• CD-3 including CD-3A (required by appropriations acts)
• Baseline Change Proposal (BCP)
The results of an ICR for projects with a TPC at or above $100M, appear in a report that the
director of PM (PM-1) endorses and forwards to the PME for review and action. The ICR report
will include findings and recommendations made by the review team regarding the schedule,
cost estimate, and risks developed by the project team. The ICR report will recommend to the
PME schedule and cost ranges for the project germane to that particular critical decision.
The results of an ICE for projects with a TPC at or above $100M, appear in a report that
PM-1 endorses and forwards to the PME for review and action. The ICE report will include
findings and recommendations regarding the project team’s schedule and cost estimate and will
provide an independently generated schedule and cost estimate. If the ICE supports CD-2
approval, the EIR team will base its review of the PB on it.
Section 9
Why: ICRs and ICEs are required at CD-2 and CD-3 by the Consolidated Appropriations Act of
2012 (Public Law 112-74) and subsequent appropriations. Independent estimates provide PMEs
and program managers additional information to help them understand the uncertainty associated
with cost and schedule estimates.
When: DOE O 413.3B requires the development of an ICR prior to CD-0 for projects with a
TPC equal to or greater than $750M and an ICR or an ICE for all projects with a TPC equal to or
greater than $100M prior to CD-1, CD-2 and CD-3. ICEs are also performed prior to approving a
BCP.
Who: Program Office and PM - For all projects greater than $100M, the ICR or ICE required
by DOE O 413.3B will be developed by PM in coordination with the program offices.
DOE G 413.3-9A 11
9-14-2018
Where: ICEs and ICRs normally are performed at the project site. However, they could be
performed at an offsite location, if sufficient information and personnel to support the review
process are available.
For additional information refer to:
GAO-16-89G, GAO Schedule Assessment Guide: Best Practices for Project Schedules,
https://www.gao.gov/products/GAO-16-89G
GAO-09-3SP, GAO Cost Estimating and Assessment Guide: Best Practices for Developing and
Managing Capital Program Costs, https://www.gao.gov/products/GAO-09-3SP
3.6 Independent Project Review (IPR)
What: IPRs are conducted by a non-proponent body to determine whether the scope of
programs, projects, or activities can be accomplished within the established cost and schedule
baselines. IPRs examine the underlying assumptions regarding technology and management;
safety and security; and risks to ensure they are valid and credible. IPRs assist with managing
risk by identifying existing and potential problems and recommended resolutions with minimum
adverse impacts to the project baselines. IPRs may meet a specific objective such as validating a
budget, assessing nuclear safety and security or technology readiness, or fulfilling a CD
precondition. The scope of an IPR varies with the complexity, cost, and status of the project.
One type of IPR is the Technical Independent Project Review (TIPR) which is conducted to
ensure early integration of safety into the design process and discussed separately in this guide.
The results of the IPR appear in a report that the PMSO completes and forwards to the PME for
review and action. The IPR report will include findings and recommendations. The Program
Office tracks findings and recommendations that require follow up actions and then determines
the successfullness of implemented corrective actions at the next project review. Findings from
IPRs conducted in support of a critical decision may require resolution prior to approval of the
critical decision.
Why: An IPR identifies technical and programmatic risks and uncertainties along with activities
that would mitigate the risks.
When: DOE O 413.3B requires IPRs prior to CD-1 (in the form of a TIPR) for Hazard Category
1, 2, and 3 nuclear facilities and prior to CD-2 (to validate the PB) for projects with a TPC less
than $100M when the program has a PMSO. Although not required by the Order, PMSOs
perform IPRs at other points throughout the project lifecycle according to program policy.
https://www.gao.gov/products/GAO-16-89G
https://www.gao.gov/products/GAO-09-3SP
12 DOE G 413.3-9A
9-14-2018
Section 10
Who: Program Office – DOE O 413.3B requires PMSOs to conduct IPRs to validate the PB for
projects with a TPC less than $100M and when otherwise directed by the Program Secretarial
Officer (PSO). Non-proponents of the project, outside of the project and its program, conduct an
IPR. The CE, PSO, PME, site or field office manager, program managers, and federal project
directors may authorize an IPR. The teams consist of senior-level technical personnel and subject
matter experts from the project as well as outside experts, as appropriate.
Where: An IPR normally occurs at the project site. However, they could be performed at an
offsite location, if sufficient information and personnel to support the review process are
available.
For additional information, refer to:
NNSA Business Operating Procedure (BOP)-06.04, Project Reviews
https://nnsaportal.energy.gov/intranet/na-mb/Active%20Policies/BOP-06.04.pdf
DOE Office of Science, Independent Review Process Handbook
https://science.energy.gov/~/media/opa/pdf/processes-and-procedures/1201_Review_Process.pdf
3.7 Mission Validation Independent Review (MVIR)
What: The MVIR is unique to MSPs. It is conducted prior to CD-0 to independently examine
the mission need developed by the program. It evaluates whether the project has clear objectives
strongly linked to mission; identifies major risks; evaluates the acquisition and conceptual
planning relative to those risks; and evaluates the funding request. This review is one of the first
steps in the identification and initiation of a DOE MSP and is used, in part, to properly designate
the appropriate PME. The review includes an examination of the following:
• Mission need statement – to verify that the documented deficiency or capability gap
described in the MNS could hinder or prevent the Department from achieving a strategic
goal.
https://nnsaportal.energy.gov/intranet/na-mb/Active%20Policies/BOP-06.04.pdf
https://science.energy.gov/%7E/media/opa/pdf/processes-and-procedures/1201_Review_Process.pdf
DOE G 413.3-9A 13
9-14-2018
• Program/mission requirements – to assess whether high-level requirements are
sufficiently defined to support identifying potential alternatives.
• Cost range – to review the rough order-of-magnitude (ROM) cost to determine whether
this range reasonably bounds the cost and schedule of alternatives under consideration.
• Schedule range – to assess consistency with strategic requirements for key milestones
including the project’s completion and, when closely linked to other projects, its
integration with the other projects.
The results of the review are documented in a report forwarded to the program secretarial office
(PSO) for consideration in approving the CD-0. If there are any shortfalls, edits, or clarifications
required, the reviewing team will outline those issues for the project team to reconcile and
correct prior to the project receiving CD-0 approval.
Why: The purpose of the MVIR is to provide an independent review of the mission need for
MSPs. It is an extra step to ensure that the mission need outlined is valid and that achievement of
the mission supports DOE’s overarching strategic goals and objectives. Per DOE O 413.3B all
MSPs have this review.
When: The MVIR should be completed prior to CD-0 approval.
Who: Program Office - The MVIR is completed by an independent review team designated by
the PSO. All mission need statements are reviewed by the program office and submitted to the
PSO for approval.
Section 11
Where: The MVIR can be held at the project site or at a location determined by the Program
office.
For additional information regarding Mission Need Statement document refer to:
DOE G 413.3-17, Mission Need Statement Guide.
14 DOE G 413.3-9A
9-14-2018
https://www.directives.doe.gov/directives-documents/400-series/0413.3-EGuide-17-admchg1
NNSA Business Operating Procedure (BOP)-06.04, Project Reviews
https://nnsaportal.energy.gov/intranet/na-mb/Active%20Policies/BOP-06.04.pdf
3.8 National Environmental Policy Act (NEPA) Review
What: The NEPA review provides an early assessment, concurrent with and coordinated with
the Analysis of Alternatives (AoA) process, of the actions required to comply with the National
Environmental Policy Act of 1969 (NEPA). The review leads to a determination of whether an
environmental impact statement (EIS) with a record of decision (ROD), a supplement analysis
(with or without an amended ROD), an environmental assessment (EA) with a finding of no
significant impact (FONSI), a categorical exclusion (CX), or a determination of “no further
NEPA action required,” are necessary to comply with the statute. This review is conducted to
fully inform the program of the range of NEPA impacts for each alternative considered.
Depending on the actions required, NEPA-driven study and analysis can require long timeframes
and incur significant costs. For these reasons, it is important to conduct the review early enough
to both inform decision making and allow for adequate planning to complete the required NEPA
actions.
The results of a NEPA review lead to environmental impact statements (EISs), environmental
assessments (EAs), or categorical exclusions (CXs). NEPA reviews are documented according to
program policy and vary depending on the level of NEPA review required for the proposed
action.
Why: The National Environmental Policy Act of 1969 (NEPA) requires federal agencies to
analyze the potential impacts of major federal actions prior to deciding whether to move forward
with that action. DOE P 451.1 delegates responsibility to Heads of Departmental Elements to
comply with NEPA. DOE O 413.3B requires project teams to complete a NEPA Strategy prior to
CD-1. The strategy documents the project team’s intended approach to comply with the law.
When: The NEPA Review is conducted prior to CD-1 and begins with the development of the
project team’s NEPA Strategy. The team works with the appropriate NEPA Compliance Officer
(NCO) to assess the proposal and realistic alternatives. Depending on the level of NEPA action
required, the required actions may not be completed prior to CD-1. According to the legislation,
all NEPA actions must be completed prior to a federal decision whether to approve the project,
prior to CD-2, and prior to construction start.
https://www.directives.doe.gov/directives-documents/400-series/0413.3-EGuide-17-admchg1
https://nnsaportal.energy.gov/intranet/na-mb/Active%20Policies/BOP-06.04.pdf
DOE G 413.3-9A 15
9-14-2018
Who: Departmental Elements’ NEPA Compliance Officers (NCOs) perform the NEPA review
in conjunction with the program office.
Where: NEPA reviews are conducted at the headquarters, site, or other location as determined
by the Departmental Element.
For additional information refer to:
DOE NEPA Guidance, Revised Recommendations for the Preparation of Environmental
Assessments and Environmental Impact Statements (the Green Book);
https://energy.gov/nepa/downloads/recommendations-preparation-environmental-assessments- a
nd-environmental-impact
Section 12
DOE P 451.1, National Environmental Policy Act Compliance Program
https://www.directives.doe.gov/directives-documents/400-series/451.1-APolicy
DOE Office of NEPA Policy and Compliance website http://energy.gov/nepa
NNSA Policy 451.1, National Environmental Policy Act Compliance Program
https://nnsaportal.energy.gov/collab/na-apm/na-apm-20/Lists/Announcements/DispForm.aspx?I
D=44
3.9 Operational Readiness Review (ORR)/Readiness Assessment (RA)
What: Readiness reviews are grouped into two types: ORRs and RAs. An ORR or RA is
conducted in accordance with DOE O 425.1D and DOE-STD-3006-2010. DOE O 425.1D
provides criteria to determine whether an ORR or an RA is required.
An ORR is an in-depth independent evaluation of the readiness of completed facilities, systems,
equipment, procedures, personnel, and supporting and interfacing systems and organizations to
begin facility operation. In the case of a facility project, the review focuses on the readiness
details associated with turning the facility over to the user, including but not limited to startup,
https://energy.gov/nepa/downloads/recommendations-preparation-environmental-assessments-and-environmental-impact
https://energy.gov/nepa/downloads/recommendations-preparation-environmental-assessments-and-environmental-impact
https://energy.gov/nepa/downloads/recommendations-preparation-environmental-assessments-and-environmental-impact
http://www.directives.doe.gov/directives-documents/400-series/451.1-APolicy
http://www.directives.doe.gov/directives-documents/400-series/451.1-APolicy
http://energy.gov/nepa
https://nnsaportal.energy.gov/collab/na-apm/na-apm-20/Lists/Announcements/DispForm.aspx?ID=44
https://nnsaportal.energy.gov/collab/na-apm/na-apm-20/Lists/Announcements/DispForm.aspx?ID=44
16 DOE G 413.3-9A
9-14-2018
testing and balancing mechanical systems. Because of the importance of this activity, ORR
planning is initiated early in a project’s lifecycle.
An RA is an assessment that uses a graded approach to the tenets of ORR requirements as
specified in DOE O 425.1D to determine a facility’s readiness to startup or restart when an ORR
is not required or when a contractor’s standard procedures for startup are not judged by the
contractor or DOE management to provide an adequate verification of readiness.
The results of an ORR or RA are documented in a report that clearly outlines whether startup
or restart of the nuclear facility, activity, or operation can proceed safely. The final report
contains an adequate level of detail to support its conclusions. A copy of the final ORR report
should be forwarded to the contactor, FPD and program office.
The closure of ORR findings includes:
• Development of corrective action plans to correct the findings. Action plans address
programmatic deficiencies and causes.
• Creation of a finding closure package which includes a brief description of corrective
actions taken, evidence of completion, and reasons for concluding that closure has been
achieved.
• Receipt of a contractor-prepared Readiness to Proceed Memorandum indicating that
readiness to start up or restart nuclear operations has been achieved. The memorandum
may include a manageable list of open prestart issues provided that the issues have a
well-defined schedule for closure.
• Satisfactory contractor resolution of all prestart findings from the DOE and contractor
ORRs prior to startup or restart of the facility, activity, or operation.
Section 13
Why: DOE O 425.1D requires that every startup or restart of a nuclear facility, operation, or
activity be evaluated to determine the required level of readiness review (i.e. ORR or RA). The
Readiness Review process was developed to provide a high degree of confidence that new and
restarted DOE nuclear facility operations will be conducted as intended by the design and safety
basis. A graded independent review approach is used. Independence was deemed necessary to
avoid conflicts of interest that could compromise reviewer ability to objectively determine the
status of the proposed operation. ORRs and RAs are not intended to achieve readiness, but to
provide independent verification of readiness.
When: DOE O 413.3B outlines that an ORR or RA for Hazard Category 1, 2, and 3 nuclear
facilities be conducted in accordance with DOE O 425.1D and DOE-STD-3006-2010 prior to
CD-4.
DOE G 413.3-9A 17
9-14-2018
Who: Program Office - In cases when an ORR or RA is required, the contractor and DOE
program office conduct the review. The DOE ORR may not start until the contractor ORR has
been completed, the identified findings are resolved or addressed by an approved corrective
action plan, and a formal Readiness to Proceed Memorandum has been submitted to DOE. In the
case of an RA, there is more flexibility as to whether it is conducted only by a contractor, jointly
(when approved), or both by a contractor and DOE (in that sequence). DOE field office
management prepares implementing procedures and concurs with contractor implementing
procedures in accordance with the Contractor Requirements Document (CRD) in
DOE O 425.1D. The Startup Authorization Authority may approve startup or restart after prestart
findings are resolved.
Where: ORRs and RAs are conducted at the project site.
For additional information regarding ORRs and RAs, refer to:
DOE O 425.1D Verification of Readiness to Start Up or Restart Nuclear Facilities
https://www.directives.doe.gov/directives-documents/400-series/0425.1-BOrder-d-chg1-admchg
DOE-STD-3006-2010 Planning and Conducting Readiness Reviews
https://www.standards.doe.gov/standards-documents/3000/3006-astd-2010
3.10 Project Definition Rating Index (PDRI) Assessment
What: The PDRI assessment for capital asset projects (both nuclear and non-nuclear) is a project
management tool designed to increase the likelihood of project success by evaluating the
maturity of project documentation. The PDRI assessment tool provides a numerical score to
indicate a capital asset project’s planning and development progress. It serves as a guage by
which project teams and executives can mark the project’s progress and decide on its readiness
to proceed to the next phase. The score has less importance than the learning process that
generates the score. The gap list produced by the assessment helps the team identify, assign,
track and monitor action items that when closed would improve the project’s score, signifying a
greater readiness for the next critical decision milestone.
https://www.directives.doe.gov/directives-documents/400-series/0425.1-BOrder-d-chg1-admchg
https://www.standards.doe.gov/standards-documents/3000/3006-astd-2010
18 DOE G 413.3-9A
9-14-2018
The results of a PDRI assessment are documented by the project team by completing the
applicable PDRI assessment tool for the project.
Section 14
Why: As outlined in DOE O 413.3B, projects with a TPC of $100M or greater conduct a PDRI
analysis. While not mandated for projects with a TPC less than $100M, the assessment is still
recommended to measure planning and design maturity. The Construction Industry Institute has
versions of the PDRI appropriate for lower cost projects.
When: The PDRI assessment benefits projects during front-end planning which encompasses all
activities during conceptual through preliminary design. DOE O 413.3B requires a PDRI
assessment prior to CD-2 for projects with a TPC of $100M or greater. PM will review the PDRI
assessment as part of the EIR.
Who: Project Team - The FPD is responsible for overseeing the PDRI assessment process with
input from the project team.
Where: PDRI assessments could be conducted at the project site or other locations as
determined by the project team.
For additional information refer to:
DOE G 413.3-12, Project Definition Rating Index Guide for Traditional Nuclear and
Non-Nuclear Construction Projects Guide.
https://www.directives.doe.gov/directives-documents/400-series/0413.3-EGuide-12-admchg1
Construction Industry Institute (CII) Front-end Planning;
https://www.construction-institute.org/resources/knowledgebase/best-practices/front-end-plannin
g
3.11 Project Management Risk Committee (PMRC) Review
What: The PMRC provides expert advice to the Secretary, CE, PME, and ESAAB on technical,
schedule, and cost issues experienced by projects with a TPC of $100M or more. Upon request
https://www.directives.doe.gov/directives-documents/400-series/0413.3-EGuide-12-admchg1
https://www.construction-institute.org/resources/knowledgebase/best-practices/front-end-planning
https://www.construction-institute.org/resources/knowledgebase/best-practices/front-end-planning
DOE G 413.3-9A 19
9-14-2018
of the CE, PME, or ESAAB, the PMRC also addresses projects with a TPC less than $100M at
risk of not meeting their PBs.
In accordance with requirements outlined in DOE O 413.3B, the PMRC reviews the following:
• CD proposals and the maturity of the associated project prior to the CE, PME, or ESAAB
considering the CD request for approval;
• BCPs prior to their presentation to the CE, PME, or ESAAB;
• PPR plans, to confirm a focus on pressing issues and an appropriate composition, results,
and corrective actions;
• Under Secretary-level project assessment outcomes to advise the CE, PME, ESAAB and
other program officials on project performance;
• The need for independent assessments to advise the CE, PME or ESAAB accordingly;
• DOE Order 413.3B requirement exemption requests presented by programs; and,
• Other topics selected by the Secretary or CE.
The results of a PMRC review appear as meeting minutes, memoranda, and action items on a
tracking sheet maintained by the PMRC Executive Secretariat with their status briefed at future
PMRC meetings until closure.
Why: The PMRC supports DOE’s strategic objective of excellence in project management by
supporting the CE, PMEs, and ESAAB in their project management decision making. PMRC
reviews also enable routine sharing of best practices and lessons learned.
When: PMRC reviews are event-driven as described above. The PMRC meets biweekly or as
often as the Chair deems necessary. A project requiring a PMRC review will coordinate
scheduling the review through its program office who will make arrangements with the PMRC
executive secretariat.
Section 15
Who: PMRC - The FPD will prepare the necessary briefings and presentations for the PMRC.
The executive secretariat will work with the program office to schedule a presentation or
discussion.
20 DOE G 413.3-9A
9-14-2018
Where: PMRC meetings occur at DOE headquarters. The FPD and the project team may
participate by teleconference.
For additional information, refer to:
PM PMRC Website https://community.max.gov/display/DOEExternal/PM+PMRC+Home
PM’s Project Management Risk Committee (PMRC) Standard Operating Procedures (SOP) for
Planning and Conducting PMRC Meetings.
https://community.max.gov/display/DOEExternal/PM+413.3+SOPs
3.12 Project Peer Review (PPR)
What: PPRs are part assessment and part assistance. They are conducted to determine whether
the following are valid and credible: the scope of programs, projects, or activities; the underlying
assumptions regarding supporting technology; the cost and schedule estimates; the contingency
provisions; and the management approach. They also facilitate cross feed of best practices and
lessons learned between projects, contributing to improvement for the projects being reviewed
and the projects from which the reviewers come.
The objectives of the PPR may include but are not limited to:
• Determining how well the project will meet the mission need;
• Evaluating technical approach and technology readiness level (TRL);
• Evaluating the readiness of the project to proceed to the next CD;
• Determining whether the acquisition strategy represents a technically valid,
cost-effective, realistic means of accomplishing its stated objectives;
• Assessing the potential for meeting schedule and cost baseline targets;
• Evaluating and managing project risks, issues, and challenges;
• Assessing the status of the project;
• Providing constructive recommendations for alternatives or improvements;
• Reviewing corrective action items from previous reviews;
• Assessing the management organization’s staffing, work assignment and management
processes, project management control systems, risk management, quality management,
and environment, safety and health (ES&H) policy compliance; and
• Analyzing compliance with federal labor and employment statutes and regulations,
including the Davis-Bacon Act, the Service Contract Act, and the Fair Labor Standards
Act.
The results of a PPR appear in a report the program office completes and forwards to the PME
for review and action. The PPR report will include findings and recommendations. The project
team will track findings that require corrective action through resolution while reporting progress
made to the Program Office. The next PPR will review the status of all findings and
recommendations.
Why: DOE O 413.3B requires PPRs in order to assist the field in successfully completing the
project, as well as identifying areas where programs need to apply additional resources.
https://community.max.gov/display/DOEExternal/PM+PMRC+Home
https://community.max.gov/display/DOEExternal/PM+413.3+SOPs
DOE G 413.3-9A 21
9-14-2018
The United States Government Accountability Office (GAO) has recognized PPRs as best
business practices that are valuable in assessing the status of projects.
When: For projects $100M and above, a PPR occurs between CD-0 and CD-1, annually between
CD-1 and CD-2, and at least annually between CD-2 and CD-4. Also for the most complex
projects, those experiencing performance challenges, or as directed by the program office, PPRs
occur more frequently.
Section 16
Who: Program Office - The program office or PME requests the review, establishes the review
scope and schedules and selects a team leader as well as the makeup of the review team
members. The teams consist of senior-level technical personnel and subject matter experts from
the project as well as outside experts, as appropriate.
Where: PPRs normally occur at the project site. However, they could be performed at an offsite
location, if sufficient information and personnel to support the review process are available.
For additional information, refer to:
NNSA Business Operating Procedure (BOP)-06.04, Project Reviews
https://nnsaportal.energy.gov/intranet/na-mb/Active%20Policies/BOP-06.04.pdf
DOE Office of Science, Independent Review Process Handbook
https://science.energy.gov/~/media/opa/pdf/processes-and-procedures/1201_Review_Process.pdf
3.13 Quarterly Project Review (QPR)
What: QPRs provide a snapshot of project performance and progress made as compared to the
established PB for the benefit of the PME. They should cover project performance and progress
to include the project’s scope, cost, schedule, risk, environmental, safety and health (ES&H), and
other project issues. If the project has not been baselined, performance should be measured
against the preliminary project execution plan including its milestones. The QPR consolidates or
https://nnsaportal.energy.gov/intranet/na-mb/Active%20Policies/BOP-06.04.pdf
https://science.energy.gov/%7E/media/opa/pdf/processes-and-procedures/1201_Review_Process.pdf
22 DOE G 413.3-9A
9-14-2018
expands upon information in project monthly status reports and is specifically intended to inform
the PME of the details of the project status and issues of concern.
The results of a Quarterly Project Review are documented in meeting minutes and action
tracking sheets along with a suspense for corrective action prepared by the reviewing office. Any
extant action item should be discussed at the next quarterly project review to verify the
corrective actions taken or progress made to resolve the issue.
Why: Quarterly reviews are necessary for the PME to monitor performance and progress. These
reviews provide a forum to communicate status and garner continued support from senior
executives within the Department.
When: These reviews are performed at the discretion of the PME, at least quarterly throughout
the project lifecycle, or more frequently (such as monthly) when the project complexity, cost, or
risks warrant such reviews. After approval of CD-0, begin holding QPRs and continue them
through approval of CD-4 for projects with a TPC of $50M and greater.
Who: Program Office and PMEs conduct QPRs. The FPD is responsible for preparing the
presentation. The Deputy Secretary may delegate quarterly reviews for MSPs to the Under
Secretaries. Under Secretaries may delegate quarterly reviews to the PSO for projects for which
they are the PME. Other PMEs may delegate QPRs as appropriate prior to CD-2, however they
may not delegate QPRs for more than two consecutive quarters after CD-2.
Where: QPRs can be held at the project site or at a location determined by the PME and
program office.
3.14 Technical Independent Project Review (TIPR)
What: TIPRs assess technical risk and uncertainty for projects acquiring or improving Hazard
Category 1, 2, and 3 nuclear facilities. A TIPR is not required for non-nuclear facilities.
Section 17
A TIPR will evaluate safety documentation to assess whether assumptions are reasonably
conservative and appropriately bounded and whether administrative controls can be considered
reliable as the project proceeds. DOE-STD-1189 was developed to provide the Department’s
DOE G 413.3-9A 23
9-14-2018
expectations for incorporating safety early into the design process for new or major
modifications to DOE Hazard Category 1, 2, and 3 nuclear facilities. A TIPR ensures that safety
aspects of the design will be thoroughly investigated. It also evaluates whether or not the IPT
includes personnel appropriately qualified to execute nuclear safety responsibilities and whether
those team members have the necessary availability.
A technical review is also useful when a process technology or unique equipment developed or
adapted for the project is untried, or unproven, and no standards exist against which judgments
regarding viability can be made. In such a case, an in-depth review by appropriately trained and
knowledgeable peers is encouraged. Other areas covered by the TIPR can include:
• Alternative Systems
• Constructability
• Functions and Requirements
• Project Definition (Scope) Assessment
• Design (at all stages of design status)
• Technology Readiness Assessment (TRA)
• System Verification (as part of System Engineering)
• Physical Configuration
• Test Readiness
• Safety and Security
• Functional Configuration
• Operability and Reliability, Availability, and Maintainability
The results of a TIPR are documented in a report that the review team completes and forwards
to the PME. The report summarizes and identifies any technical risks and uncertainty associated
with the technical scope of the project. The findings and recommendations made by the TIPR
team typically address technical, functional, operational, and safety issues in the design. The
findings and recommendations are documented, reviewed and tracked for resolution as the
project progresses towards CD-2.
Why: TIPRs ensure the timely resolution of engineering, system integration, technology
readiness assessments, design, quality assurance, operations, maintenance, and nuclear safety
issues. Technical reviews are necessary when uncertainty exists concerning the outcome of a key
project decision. Reducing technical risks increases the probability of a successful
24 DOE G 413.3-9A
9-14-2018
implementation of the technical scope. DOE O 413.3B requires that a TIPR be conducted for all
Hazard Category 1, 2, and 3 nuclear facilities prior to CD-2.
When: Conduct a TIPR at or near the completion of the preliminary design prior to CD-2 and
prior to the start of any subsequent reviews (e.g. EIR). Identifying the review requirements in a
charge memorandum shortly after CD-1 gives the appropriate SMEs time to plan and conduct the
review. A TIPR completed as soon as possible after preliminary design maximizes time to make
needed corrections.
Who: The program office and FPD jointly request the review, establish the review scope and
schedule, and select a team leader. The team leader appointed by the program office approves the
TIPR review plan and the final review report. Qualified technical personnel external to the
project execute TIPRs.
Where: TIPRs should be conducted at the project site. However, they could be performed at an
offsite location, if sufficient information and personnel to support the review process are
available.
For additional information refer to:
Section 18
NNSA Business Operating Procedure (BOP)-06.04, Project Reviews
https://nnsaportal.energy.gov/intranet/na-mb/Active%20Policies/BOP-06.04.pdf
DOE Office of Science, Independent Review Handbook
https://science.energy.gov/~/media/opa/pdf/processes-and-procedures/1201_Review_Process.pdf
DOE-STD-1189, Integration of Safety into the Design Process
https://www.standards.doe.gov/standards-documents/1100/1189-astd-2016
3.15 Technology Readiness Assessment (TRA)
What: A TRA examines the maturity of technologies and their readiness for insertion into the
project design and execution schedule. This assessment applies to MSPs or first of a kind
projects. Through its use, projects may reduce technical risk and technology-driven schedule
https://nnsaportal.energy.gov/intranet/na-mb/Active%20Policies/BOP-06.04.pdf
https://science.energy.gov/%7E/media/opa/pdf/processes-and-procedures/1201_Review_Process.pdf
https://www.standards.doe.gov/standards-documents/1100/1189-astd-2016
DOE G 413.3-9A 25
9-14-2018
delays and cost increases. Through a methodology adapted from a NASA scale developed in the
1980s, a TRA assigns a technology readiness level (TRL) from 1, basic principles observed,
through 9, total system used successfully in project operations. The project team tracks for
resolution the findings and recommendations from TRAs. The review process should follow the
systems engineering approach to assess proper integration of systems with new technologies into
the project.
The results of a TRA document the process used to conduct the TRA and provide a
comprehensive explanation of the assessed TRL for each Critical Technology Element (CTE). At
a minimum, a TRA should provide:
• A comprehensive review, using an established program or project work breakdown
structure or flow diagram as an outline, of the entire platform or system while identifying
the CTEs;
• An objective scoring of the technology maturity for each CTE by subject matter experts;
• Results that assist the project team in preparing maturation plans for achieving an
acceptable maturity for CTEs prior to critical decisions;
• A final report documenting the findings of the assessment review team; and,
• Lessons learned documented within the TRA report or separately.
Why: DOE O 413.3B requires that CTEs associated with MSPs or first-of-a-kind engineering
endeavors attain TRL-4 prior to CD-1 and TRL-7 prior to CD-2.
When: Conduct TRAs for MSPs or first of a kind projects during conceptual design through
preliminary design, at least 90 days prior to CD milestones. For MSPs where a significant
technology element modification occurs subsequent to CD-2, conduct another TRA as
appropriate prior to CD-3.
Who: Program Office - The program office and FPD jointly request the review, establish the
review scope and schedule and select a team leader. The teams consist of senior-level technical
personnel and subject matter experts from the project as well as outside experts, as appropriate.
26 DOE G 413.3-9A
9-14-2018
Where: Conduct TRAs at the project site. However, they could be performed at an offsite
location, if sufficient information and personnel to support the review process are available.
For additional information refer to:
DOE G 413.3-4A, Technology Readiness Assessment Guide
https://www.directives.doe.gov/directives-documents/400-series/0413.3-EGuide-04-admchg1
GAO-16-410G: GAO Technology Readiness Assessment Guide: Best Practices for Evaluating
the Readiness of Technology for Use in Acquisition Programs and Projects – Exposure Draft,
https://www.gao.gov/products/GAO-16-410G
Section 19
GAO-16-89G, GAO Schedule Assessment Guide: Best Practices for Project Schedules,
https://www.gao.gov/products/GAO-16-89G
DOE EM SOP Technology Readiness Assessments/Technology /Maturation Plan
https://community.max.gov/download/attachments/1321765038/SOPP%2027.pdf?version=1&m
odificationDate=1504806757912&api=v2
NNSA Policy Letter NAP-29, Technology Readiness Assessments
https://nnsaportal.energy.gov/intranet/na-mb/Active%20Policies/Forms/DispForm.aspx?ID=311
https://www.directives.doe.gov/directives-documents/400-series/0413.3-EGuide-04-admchg1
https://www.gao.gov/products/GAO-16-410G
https://www.gao.gov/products/GAO-16-89G
https://community.max.gov/download/attachments/1321765038/SOPP%2027.pdf?version=1&modificationDate=1504806757912&api=v2
https://community.max.gov/download/attachments/1321765038/SOPP%2027.pdf?version=1&modificationDate=1504806757912&api=v2
https://nnsaportal.energy.gov/intranet/na-mb/Active%20Policies/Forms/DispForm.aspx?ID=311
DOE G 413.3-9A Appendix A
9-14-2018 A-1 (and A-2)
Appendix A: Project Reviews and when they are typically performed
Reviews DOE O 413.3B
Thresholds
Pre-
CD-0
Pre-
CD-1
Pre-
CD-2
and
BCP
Pre-
CD-3
Pre-
CD-4
Design Reviews $50M or greater x x x
Earned Value Management System
(EVMS) Review
$100M or greater
or at request of
PMSO
x
Energy Systems Acquisition Advisory
Board (ESAAB) Review
$100M or greater
or as directed by
chair
x x x x
External Independent Review (EIR) $100M or greater x
Independent Cost Review (ICR) or
Independent Cost Estimate (ICE) $100M or greater x x x x
Independent Project Review (IPR)
less than $100M
or as directed by
PSO
x x x
Mission Validation Independent Review
(MVIR) $750M or greater x
National Environmental Policy Act
(NEPA) Review $50M or greater* x
Operational Readiness Review (ORR) or
Readiness Assessment (RA)
initial startup or
restart of
HAZCAT
x
Project Definition Rating Index Analysis
(PDRI) Assessment $100M or greater x
Project Management Risk Committee
(PMRC) Review
$100M or greater
or as requested
x x x x
Project Peer Review (PPR) $100M or greater x x x x
Quarterly Project Review (QPR) $50M or greater x x x x
Technical Independent Project Review
(TIPR)
all high risk, high
hazard, or
HAZCAT
x
Technology Readiness Assessment
(TRA)
$750M or greater
or first of a kind x x x
* NEPA does not have cost thresholds. DOE O 413.3 applies to projects with a total project cost
of $50M or more.
DOE G 413.3-9A Appendix B
9-14-2018 B-1
Appendix B: Acronyms
AoA Analysis of Alternatives
BCP Baseline Change Proposal
CAP Corrective Action Plan
CAR Corrective Action Request
CD Critical Decision
CDR Conceptual Design Report
CE Chief Executive for Project Management
CII Construction Industry Institute
CIO Continuous Improvement Opportunities
CTE Critical Technology Element
CRD Contractor Requirements Document
CX Categorical Exclusion
DOE U.S. Department of Energy
DR Discrepancy Report
EA Environmental Assessment
EIA Electronic Industries Alliance
EIR External Independent Review
EIS Environmental Impact Statement
EM Environmental Management
ESAAB Energy Systems Acquisition Advisory Board
ES&H Environment, Safety, and Health
EVMS Earned Value Management System
FAR Federal Acquisition Regulation
FPD Federal Project Director
GAO U.S. Government Accountability Office
ICE Independent Cost Estimate
ICR Independent Cost Review
IPR Independent Project Review
IPT Integrated Project Team
KPP Key Performance Parameter
MSP Major System Project
MVIR Mission Validation Independent Review
NASA National Aeronautics and Space Administration
NEPA National Environmental Policy Act
NCO NEPA Compliance Officer
NNSA National Nuclear Security Administration
NQA-1 Nuclear Quality Assurance Standard – 1 (ANSI/ASME standard)
ORR Operational Readiness Review
PARS Project Assessment and Reporting System
PB Performance Baseline
PDRI Project Definition Readiness Index
PM Office of Project Management
Section 20
Appendix B DOE G 413.3-9A
B-2 9-14-2018
PME Project Management Executive
PMSO Project Management Support Office
PMRC Project Management Risk Committee
PPR Project Peer Review
PSO Program Secretarial Office
QPR Quarterly Project Review
RA Readiness Assessment
ROD Record of Decision
ROM Rough Order of Magnitude
SME Subject Matter Expert
SOP Standard Operating Procedure
TIPR Technical Independent Project Review
TPC Total Project Cost
TRA Technology Readiness Assessment
TRL Technology Readiness Level
DOE G 413.3-9A Appendix C
9-14-2018 C-1
Appendix C: References
10 CFR Part 1017, Identification and Protection of Unclassified Controlled Nuclear Information.
Construction Industry Institute (CII) Front-end Planning;
https://www.construction-institute.org/resources/knowledgebase/best-practices/front-end-planning.
DOE O 413.3B Chg 5, Program and Project Management for the Acquisition of Capital Assets,
dated 4-12-18.
DOE G 413.3-3A Chg 1, Safeguards and Security for Program and Project Management, dated
10-22-15.
DOE G 413.3-4A Chg 1, Technology Readiness Assessment Guide, dated 10-22-15.
DOE G 413.3-10A Chg 1, Earned Value Management System (EVMS), dated 10-22-15.
DOE G 413.3-12 Chg 1, Project Definition Rating Index Guide for Traditional Nuclear and
Non-Nuclear Construction Projects, dated 10-22-15.
DOE G 413.3-17 Chg 1, Mission Need Statement Guide, dated 10-22-15.
DOE O 425.1D, Chg 1, Verification of Readiness to Startup and Restart of Nuclear Facilities,
dated 4-12-13.
DOE P 451.1, National Environmental Policy Act Compliance Program, dated 12-21-17.
DOE P 470.1B Safeguards and Security Program, dated 2-10-16.
DOE PM Earned Value Management System Webpage.
https://community.max.gov/display/DOEExternal/PM+EVM+Home.
DOE PM ESAAB Webpage.
https://community.max.gov/display/DOEExternal/PM+ESAAB+Home.
DOE PM PMRC Webpage.
https://community.max.gov/display/DOEExternal/PM+PMRC+Home.
PM’s Project Management Risk Committee (PMRC) Standard Operating Procedures (SOP) for
Planning and Conducting PMRC Meetings.
https://community.max.gov/display/DOEExternal/PM+413.3+SOPs.
DOE PM SOP Energy System Acquisition Advisory Board (ESAAB) Standard Operating
Procedures (SOP). https://community.max.gov/display/DOEExternal/PM+413.3+SOPs.
DOE O 471.1B, Identification and Protection of Unclassified Controlled Nuclear Information,
dated 3-1-10.
https://www.construction-institute.org/resources/knowledgebase/best-practices/front-end-planning
https://community.max.gov/display/DOEExternal/PM+EVM+Home
https://community.max.gov/display/DOEExternal/PM+ESAAB+Home
https://community.max.gov/display/DOEExternal/PM+PMRC+Home
https://community.max.gov/display/DOEExternal/PM+413.3+SOPs
https://community.max.gov/display/DOEExternal/PM+413.3+SOPs
Appendix C DOE G 413.3-9A
C-2 9-14-2018
DOE Order 471.3, Chg 1, Identifying and Protecting Official Use Only Information, dated
1-13-11.
DOE M 471.3, Chg 1, Manual for Identifying and Protecting Official Use Only Information,
dated 1-13-11.
DOE O 475.2B, Identifying Classified Information, dated 10-2-14.
DOE-STD-1189-2016, Integration of Safety into the Design Process, dated 12-22-16.
DOE-STD-3006-2010, Planning and Conduct of Operational Readiness Reviews (ORR), dated
5-6-10.
DOE Office of Environmental Management, Technology Readiness Assessment / Technology
Maturation Plan Process Guide, dated March 2008.
DOE Office of Management, Budget and Evaluation, Reviews, Evaluations, and Lessons
Learned, Rev E, dated June 2003.
Section 21
DOE Office of Science, Independent Review Handbook.
https://science.energy.gov/~/media/opa/pdf/processes-and-procedures/1201_Review_Process.pdf.
GAO-09-3SP, GAO Cost Estimating and Assessment Guide: Best Practices for Developing and
Managing Capital Program Costs, March 2, 2009.
GAO-16-410G: GAO Technology Readiness Assessment Guide: Best Practices for Evaluating
the Readiness of Technology for Use in Acquisition Programs and Projects – Exposure Draft,
dated August 11, 2016.
National Research Council, Progress in Improving Project Management in the Department of
Energy, 2001.
NNSA Business Operating Procedure (BOP)-06.04, Project Reviews.
https://nnsaportal.energy.gov/intranet/na-mb/Active%20Policies/BOP-06.04.pdf .
NNSA Business Operating Procedure (BOP)-50.003, Establishment of NNSA Independent
Project Review Policy, dated June 2007.
https://nnsaportal.energy.gov/intranet/na-mb/Active%20Policies/Forms/DispForm.aspx?ID=69.
NNSA Policy Letter NAP-29, Technology Readiness Assessments.
https://nnsaportal.energy.gov/intranet/na-mb/Active%20Policies/Forms/DispForm.aspx?ID=311.
NNSA Policy 451.1, National Environmental Policy Act Compliance Program.
https://nnsaportal.energy.gov/collab/na-apm/na-apm-20/Lists/Announcements/DispForm.aspx?I
D=44.
https://science.energy.gov/%7E/media/opa/pdf/processes-and-procedures/1201_Review_Process.pdf
https://nnsaportal.energy.gov/intranet/na-mb/Active%20Policies/BOP-06.04.pdf
https://nnsaportal.energy.gov/intranet/na-mb/Active%20Policies/Forms/DispForm.aspx?ID=69
https://nnsaportal.energy.gov/intranet/na-mb/Active%20Policies/Forms/DispForm.aspx?ID=311
https://nnsaportal.energy.gov/collab/na-apm/na-apm-20/Lists/Announcements/DispForm.aspx?ID=44
https://nnsaportal.energy.gov/collab/na-apm/na-apm-20/Lists/Announcements/DispForm.aspx?ID=44
FOREWORD
TABLE OF CONTENTS
1.0 PURPOSE AND SCOPE OF THIS GUIDE
2.0 NEED FOR PROJECT REVIEWS
3.0 REVIEW TYPES
3.1 Design Reviews
3.2 Earned Value Management System (EVMS) Review
3.3 Energy Systems Acquisition Advisory Board (ESAAB) Review
3.4 External Independent Review (EIR)
3.5 Independent Cost Review (ICR) and Independent Cost Estimate (ICE)
3.6 Independent Project Review (IPR)
3.7 Mission Validation Independent Review (MVIR)
3.8 National Environmental Policy Act (NEPA) Review
3.9 Operational Readiness Review (ORR)/Readiness Assessment (RA)
3.10 Project Definition Rating Index (PDRI) Assessment
3.11 Project Management Risk Committee (PMRC) Review
3.12 Project Peer Review (PPR)
3.13 Quarterly Project Review (QPR)
3.14 Technical Independent Project Review (TIPR)
3.15 Technology Readiness Assessment (TRA)
Appendix A: Project Reviews and when they are typically performed
Appendix B: Acronyms
Appendix C: References