DOE G 413.3-9, U.S. Department of Energy Project Review Guide for Capital Asset Projects
Functional areas: Program Management, Project Management
This Guide addresses the various project reviews conducted during the life-cycle of a project based on the stage, complexity and duration of a project. This Guide describes typical reviews, the purpose of each, the timing during the project life-cycle, lines of inquiry, and required documentation. No cancellations.
Version history and related documents
Superseded by
A newer version replaces this document.
Related documents
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
AVAILABLE ONLINE AT: INITIATED BY:
www.directives.doe.gov Office of Management
DOE G 413.3-9
9-23-08
U.S. DEPARTMENT OF ENERGY
PROJECT REVIEW GUIDE
FOR
CAPITAL ASSET PROJECTS
[This Guide describes suggested non-mandatory approaches for meeting requirements. Guides are not
requirements documents and are not to be construed as requirements in any audit or appraisal for
compliance with the parent Policy, Order, Notice, or Manual.]
U.S. Department of Energy
Washington, D.C. 20585
NOT
MEASUREMENT
SENSITIVE
DOE G 413.3-9 i (and ii)
9-23-08
FOREWORD
This Department of Energy Guide is for use by all DOE elements. This Guide provides
acceptable approaches for implementing the project reviews requirements and criteria
required by DOE O 413.3A, Program and Project Management for the Acquisition of
Capital Assets, dated 7-28-07, and related to the development, methodology and
implementation of a Project Reviews and Evaluation Process for the project. This Guide
describes suggested non-mandatory approaches for meeting requirements. DOE Guides are
part of the DOE Directives System and are issued to provide supplemental information and
additional guidance regarding the Department’s expectations of its requirements as contained
in rules, Orders, Notices, and regulatory standards. Guides may also provide acceptable
methods for implementing these requirements. Guides are not substitutes for requirements,
nor do they replace technical standards that are used to describe established practices and
procedures for implementing requirements.
DOE G 413.3-9 iii (and iv)
9-23-08
TABLE OF CONTENTS
1.0 Purpose ...................................................................................................................................... 1
2.0 Scope ......................................................................................................................................... 2
3.0 Discussion of Project Reviews.................................................................................................. 3
4.0 Overview of the EIR/IPR Planning Process ........................................................................... 12
5.0 Required and Optional Project Reviews ................................................................................. 15
5.1 Mission Need Review ................................................................................................. 16
5.2 Alternative Selection and Cost Range (CD-1) Reviews ............................................. 17
5.3 Performance Baseline Review (CD-2) ........................................................................ 19
5.4 Approve Start of Construction Review (CD-3) .......................................................... 33
5.5 Technical Reviews ...................................................................................................... 45
6.0 Tailoring .................................................................................................................................. 47
APPENDICES
Appendix A: Glossary................................................................................................................. A-1
Appendix B: Acronyms .............................................................................................................. B-1
Appendix C: References ............................................................................................................. C-1
Appendix D: Sample of a Tailored External Independent Review Plan .................................... D-1
Appendix E: Shell Independent Project Review Plan .................................................................. E-1
Section 2
DOE G 413.3-9 1
9-23-08
1.0 Purpose
This guide is a tool for Federal Project Directors (FPD) and Federal Program Managers in
planning and preparing for appropriate reviews (as discussed herein below) as an integral part of
the project planning and implementation cycle. Reviews and evaluations are essential to
maintain confidence that project management processes and technical efforts are integrated and
effectively coordinated for the Department of Energy (DOE). Reviews provide peer review and
subject matter expert opinion and feedback on the project readiness to proceed to the next stage
in the project decision-making process (see the project Critical Decision Process in DOE O
413.3A).
Reviews and evaluations are performed by several levels of management at various points in the
lifecycle of a project, including the project’s Initiation, Definition, Execution and
Transition/Closeout phases. Reviews and evaluations should be planned and structured using a
tailored and graded approach which considers project-specific attributes including
review/decision objectives, scope, project size, cost, technical complexity; and findings from
previous reviews, and emerging or intervening issues which may not have been previously
present, defined or evaluated.
Reviews and evaluations conducted during the Initiation and Definition phases verify that
projects support the Department’s mission goals and strategic plans; and can be successfully
performed within the funding range given applicable conditions such as site and installation
conditions, safety and security requirements, and the content of NEPA Site-wide Environmental
Impact Statements (SWEIS). During these phases the review process will also be evaluating
technology alternatives and maturation levels prior to granting approval for the project to
proceed into design and execution. It is also the time to conduct reviews to verify that the
project scope is matured and well defined prior to proceeding to execute and baseline the project.
The purposes of reviews and evaluations during the Execution and Transition/Closeout phases
are to: (a) support validation of the project technical scope, cost and schedule baseline; (b) ensure
that the project is being successfully executed according to plans and within established cost
baselines; (c) ensure understanding of the project risks and management strategies; (d) provide
recommendations for improving the project’s technical scope, schedule, and cost performance;
(e) support the project process by developing recommendations and necessary supporting data to
arrive at decisions to either proceed or not proceed with subsequent project lifecycle phases; and
(f) ensure agreed upon project products and deliverables are being provided.
All aspects of the review and evaluation (assessment) process allow opportunities for continuous
improvement through a feedback process occurring at critical decision points. Information
feedback is typically provided on topics including adequacy of project controls, opportunities for
improving work definition and planning, adequacy of risk management evaluation and planning,
applicability of lessons learned across the department, plans for and probability of internal and
external independent oversight, impacts and likelihood of possible regulatory enforcement
actions, likelihood of proposed project funding profiles given planned and budgeting for
competing interests in each proposed funding year, etc.
2 DOE G 413.3-9
9-23-08
Section 3
2.0 Scope
This guide will address the various types of project reviews that are conducted during the life-
cycle of a project based on the stage, complexity and duration of a project. This guide will
describe typical reviews for DOE projects, the purpose of each review, the timing during the
project life-cycle stages, lines of inquiry, and the documentation. This guide also includes a
general discussion of the review process, review participants and qualification of reviewers. The
guide incorporates lessons learned from recent project reviews, and recommendations of recent
studies of DOE’s project management processes by the National Research Council, Government
Accountability Office (GAO) and the Inspector General.
One or more of the following types/categories of reviews are performed in support of DOE
projects:
• Regular/Periodic. Involve project status, trends, quality assurance, design and
construction progress for systems and interfaces. These reviews include monthly
reviews, quarterly reviews, peer reviews for development work and so forth. All are
integral part of ongoing project activities.
• Areas of Special Concern/Risk-Driven Reviews. Involve critical technology assessments,
hazards, special procurements, high risks, etc. Some of these reviews can be planned and
budgeted in advance; others will be on an as-needed basis.
• Event-Driven/Decision Point. Involves mission validation, safety analysis, conceptual
design review and assessment, baseline validation and critical decision readiness reviews.
These reviews are necessary to obtain approval to proceed to follow-on project phases.
These reviews are an integral part of a project and are planned in advance; most are
performed by independent entities.
• Unscheduled. Could involve the Government Accountability Office, Nuclear Regulatory
Commission (NRC), Defense Nuclear Facilities Safety Board (DNFSB), DOE
Headquarters, or the user. Generally performed on projects with high congressional
visibility or projects that experience schedule or cost difficulties. For large, visible
projects, these reviews may be anticipated and planned, and should include both schedule
and cost components.
• Status Reviews. Performed to determine the current condition of a project activity. For
example, progress towards completion, compliance status, or readiness to proceed.
Reviews could include items (project baselines, requirements, subsystems, project end
products), or activities (planning, design, or construction). These reviews can involve
management and/or the user. Products from these reviews include review plans, review
reports, action item lists, and action item resolution reports.
• Design Reviews. Design reviews determine if a product (drawings, analysis, or
specifications) is correct and will perform its intended functions and meet requirements.
Design reviews are an integral part of the project. Beginning at Critical Decision-1 (CD-
1), Alternative Selection and Cost Range, and continuing through the life of the project,
DOE G 413.3-9 3
9-23-08
as appropriate, design reviews are performed by individuals internal and external to the
project. Design reviews should be conducted for all projects and should involve a
formalized, structured approach to ensure the reviews are comprehensive, objective, and
documented.
This guide will provide an overview of various project reviews within the aforementioned type
of reviews that may occur during the project life-cycle. These reviews include:
Section 4
1. Performance Reviews
2. Independent Project Reviews (IPR)
3. External Independent Reviews (EIR)
4. Independent Cost Reviews
5. Technical Reviews
6. Operational Readiness Reviews and Readiness Assessments
3.0 Discussion of Project Reviews
Reviews are essential for the FPD to maintain confidence that project systems, processes, and
technical efforts are integrated, effectively coordinated and provide the required information.
Reviews also help ensure that the project is progressing at an effective and acceptable rate,
particularly regarding established baselines. Although reviews are required at key junctures by
the Critical Decision process, FPDs may also recommend project reviews at their discretion at
any time if they encounter conditions which warrant special review.
Each project has phases through which it evolves. A clear understanding of these phases permits
better control and use of resources in achieving goals. Regardless of size and complexity,
project phases consist of Initiation, Definition, Execution, and Transition/Closeout. The
following sections provide an overview of various reviews:
3.1 Regular/Periodic and Status Reviews—Performance Reviews
Project management performance reviews presented to senior leadership are performed at least
quarterly through the project phases or life-cycle, or more frequently (such as monthly) when the
project complexity, cost, or concerns warrant such review. These reviews provide a forum to
communicate status and ensure continued support from senior executives within the Department.
The reviews provide both information exchange and more detailed information than that
provided in status reports. After approval of CD-0, the Acquisition Executive or designee should
begin holding quarterly progress reviews through the approval of CD-4 for projects with a Total
Project Cost or Environmental Management Total Project Cost greater than or equal to $5M.
The Secretarial Acquisition Executive may delegate quarterly reviews for Major System Projects
to the Under Secretaries. For Environmental Management Clean-Up Projects, quarterly reviews
may be delegated to the Program Secretarial Officer.
4 DOE G 413.3-9
9-23-08
A performance review can take many forms; generally, the Federal Project Director presents the
current program/project status. Performance reviews allow improved communication of detailed
project information. These meetings provide opportunities to respond to questions, discuss future
activities, identify needed support, and discuss actions by external entities influencing the project
(e.g., the Office of Management and Budget, the U.S. Environmental Protection Agency,
Congress, Defense Nuclear Facilities Safety Board, and others). Finally, these meetings are a
forum for identifying, discussing, and resolving issues (or assigning actions) before issues
become a problem. Performance reviews should use a graded approach tailored to project
specific attributes, review/decision objectives, project status, size, and complexity.
3.2 Event Driven Reviews—Independent Project Reviews (IPRs) and External
Independent Reviews (EIRs)
3.2.1 Independent Project Reviews
Section 5
The overall purpose of Independent Project Reviews are to determine, by a non-proponent body,
whether the scope of programs, projects, or activities; the underlying assumptions regarding
technology and management; the technical, cost and schedule baselines; safety and security; and
the contingency provisions are valid and credible within the budgetary and administrative
constraints under which DOE functions. IPRs assist in the process of risk management by
assuring existing and potential problems are identified in a timely manner so that an adequate
resolution is possible with minimum adverse impact to the project baselines. IPR’s may also be
scheduled to meet a specific objective, such as a budget validation, nuclear safety and security, a
technology readiness assessment, or a Critical Decision request. Some IPRs are mandatory as
delineated in the DOE O 413.3A (see Section 5.0, Table 3). The scope of an IPR is dependent
on the type of review, cost/complexity of the project and the project current status.
Within the realm of IPR’s (another form) is the Technical Independent Project Review which are
reviews conducted to reduce technical risk and uncertainty. These are discussed in more detail in
Section 3.4, Areas of Special Concern and Design Reviews/Risk Driven Reviews – Technical
IPRs.
Non-proponents of the project outside of the specific program and the project being reviewed,
conduct an Independent Project Review. The Deputy Secretary as the SAE, or the Program
Secretarial Officer, the Operations/Field Office Manager, Program Managers, and Federal
Project Directors can authorize Independent Project Reviews. IPR’s can be conducted on all
projects under DOE O 413.3A, which means, projects with a TPC equal to or greater than $5M.
3.2.1.1 Project Definition Assessments/Project Definition Rating Index
(PDRI).
The Project Definition Rating Index (PDRI) is a project management tool that the National
Nuclear Security Administration (NNSA) and the Office of Environmental Management (EM)
use when conducting IPR’s prior to CD-2 for assessing how well the project scope is defined.
The tool is designed to assist the project planners in increasing the likelihood of project success
by improving project definition. OECM will use the same methodology to supplement the CD-2
DOE G 413.3-9 5
9-23-08
EIR process prior to validating the project baseline to assess whether a consistent and sufficient
level of front-end planning has occurred prior to establishing a project baseline.
The PDRI tool was originated by the Construction Industry Institute for the purpose of
improving the success ratio of their projects; that is, achieving project objectives within the
original baseline budget and schedule. Essentially the tool uses a numeric assessment which
rates (i.e. scores) a wide range of project elements to determine how well the project is defined.
For a better understanding of the implementation of the tool the following references are
provided: NNSA, Office of Project Management and System Support, NNSA Project Definition
Rating Index (PDRI) Manual, Revision 0, June 2008; DOE, Office of Environmental
Management, Project Definition Rating Index (EM-PDRI) Manual, Revision 1, February 2001.
Section 6
The principal purpose of the PDRI tool is to assist the IPTs by identifying key engineering and
design elements that are critical to a well defined scope at various phases of a project. For
example: it assists in identifying staffing requirements at each project phase; reporting progress
on project definition at Quarterly Progress Reviews; assessing readiness for Internal and External
Project Reviews; and supporting the Acquisition Executive in approving Critical Decisions. The
PDRI review tool focuses on key project scope elements (e.g. Design Criteria, Design Drawings,
Safeguards and Security, Hazard Analysis, Quality Assurance requirements, Heat and Material
Balances, Constructability, etc.) that the PDRI review team believes will significantly improve
project definition if adequately developed – particularly during the up-front planning performed
prior to CD-1.
3.2.2 External Independent Reviews
The purpose of an EIR, which is conducted prior to approval of CD-2 (Approve Performance
Baseline), is to validate that the project can be executed to the proposed performance baseline
(scope, cost and schedule). The Performance Baseline EIRs were first mandated by
Congressional Language in 1998 and numerous times thereafter to ensure the validity of DOE’s
performance baselines prior to construction budget requests. As directed by DOE O 413.3A, for
all projects with a Total Project Cost (TPC) or Environmental Management TPC greater or equal
to $100M, OECM is responsible for conducting the EIR. Recent OECM and the Office of
Environmental Management approved protocol (Reference: Memorandum for Protocol for
Environmental Management Cleanup Projects dated April 24, 2007) tailors this requirement for
EM cleanup as follows: “An EIR will be conducted on the near-term baseline (see Section 6.1
for the tailored concept near-term baseline) if its cost is equal or greater than $250M, otherwise
an IPR will be conducted.” Independent Project Reviews are conducted by the Project
Management Support Office to validate the Performance Baseline for projects with a TPC less
than $100M and greater than $5M (for EM cleanup projects the IPR is for projects with a TPC
less the $250M and greater than $5M). EIRs are more than just a review of cost and schedule
(the same would apply to an equivalent IPR). They support validation that:
• costs and schedules are firmly supported with sound underlying planning and technical
assumptions;
• designs are mature enough (which includes technology readiness, nuclear safety, security
and quality assurance);
6 DOE G 413.3-9
9-23-08
• the number, skill set and effectiveness of the Integrated Project Teams (IPTs) are
appropriate to successfully execute the project; and
• the Acquisition Strategy is appropriate and enhances project delivery.
A second common type of EIR is the Construction/Execution Readiness External Independent
Review that supports Critical Decision-3 for Major System Projects. DOE O 413.3A requires
that OECM perform an EIR for all Major System Projects prior to authorization for CD-3. The
purpose of the EIR is to assess the readiness for construction and/or execution and to re-confirm
the completeness and accuracy of the performance baseline. In addition to the review elements
of the performance baseline review, this EIR focuses on the final drawings, specifications and
construction/execution planning. A similar IPR must be performed by the appropriate Program
Secretarial Officer for Non-Major System Projects unless justification is provided and a waiver
is granted by the Acquisition Executive.
Section 7
3.3 Event Driven Reviews—Front End Planning Reviews, Operational
Readiness Reviews (ORR), and Readiness Assessments.
“Front-End Planning Reviews” may be requested by the Acquisition Executive (AE) and/or the
Program. The purpose of these reviews, normally conducted sometime between CD-0 and CD-2,
are to evaluate project assumptions, validate project requirements, evaluate project scope
definition, assess the project risk analysis, verify the IPT project knowledge/participation, and
foster quality assurance, to name a few areas. At times it would be appropriate to conduct these
type of reviews in advance of a Performance Baseline Review (particularly for a Major System
Acquisition) to provide a readiness assessment to conduct a CD-2 EIR.
An Operational Readiness Review is an in-depth independent evaluation of the readiness of
completed facilities, systems, equipment, procedures, personnel, and supporting and interfacing
systems and organizations to begin facility operation. In the case of a facility project, the review
focuses on the readiness details associated with turning the facility over to the user, including but
not limited to final startup, testing and balancing mechanical systems. Because of the importance
of this activity, Operational Readiness Review planning is initiated early in a project’s life cycle.
Readiness Assessments (RA) are conducted on nuclear projects that do not require an ORR. An
ORR or RA is conducted in accordance with DOE O 425.1C, Startup and Restart of Nuclear
Facilities, and DOE STD 3006-2000, Planning and Conduct of Operational Readiness Reviews.
3.4 Areas of Special Concern and Design Reviews/Risk-Driven Reviews—
Technical Independent Project Reviews
Technical Independent Project Reviews are one of the measures that can be taken to ensure the
timely resolution of engineering, system integration, technology readiness assessments, design,
quality assurance, operations, maintenance and nuclear safety issues. The purpose of a technical
review is to reduce technical risk and uncertainty. Technical risk reduction increases the
probability of successful implementation of technical scope. Design Reviews could be
conducted independently of IPRs but the qualified technical personnel involved can be internal
or external to the project. The results of the Design Reviews are reviewed by the IPRs and the
DOE G 413.3-9 7
9-23-08
Technical IPRs, if relevant to the scope of the specific review being conducted, such as in
support of the Critical Decision Process.
Technical reviews are necessary when uncertainty exists concerning the outcome of a key project
decision. DOE O 413.3A requires, as part of the Design Review requirements and the Graded
Approach for Quality for high-risk, high-hazard, and Hazard Category 1, 2, and 3 nuclear
facilities, that a Technical Independent Project Review be conducted prior to CD-1, the focus of
which is to determine that the safety documentation is sufficiently conservative and bounding to
be relied upon the next phase of the project. DOE-STD-1189 was developed to provide the
Department’s expectations for incorporating safety early into the design process for new or
major modifications to DOE Hazard Category 1, 2, and 3 nuclear facilities, the intended purpose
of which involves the handling of hazardous materials, both radiological and chemical, in a way
that provides adequate protection for the public, workers, and the environment. The approach of
the Technical Independent Project Review for these facilities must ensure that safety aspects of
the design will be thoroughly investigated (it should not be permissible to tailor the technical
review for these type of facilities to exclude safety related aspects of the design, otherwise, the
objectives of DOE-STD-1189 could not be met).
Section 8
Another example where a technical review can be useful is when a process technology or special
equipment (such as one-of-a-kind equipment in development from concept to engineering
design) is untried, or unproven, and no standards against which judgments regarding viability
can be made, then an in-depth review by appropriately trained and knowledgeable peers is in
order. Other types of Technical Independent Project Reviews can include:
• Alternative Systems
• Constructability
• Functions and Requirements
• Project Definition (Scope) Assessment
• Design (at all stages of design status)
• Technology Readiness Assessment (TRA)
• System Verification (as part of System Engineering)
• Physical Configuration
• Test Readiness
• Safety and Security
• Functional Configuration
• Operability and Reliability, Availability, and Maintainability
8 DOE G 413.3-9
9-23-08
3.4.1 Technology Readiness Assessments (TRAs) and Technology Maturation
Plans (TMPs)
Technical Independent Project Reviews can include TRAs to provide an assessment of the
maturity level of a new proposed technology prior to insertion into the project design and
execution phases to reduce technical risk and uncertainty. A TRA provides a snapshot in time of
the maturity of technologies and their readiness for insertion into the project design and
execution schedule. A TMP is a planning document that details the steps necessary for
developing technologies that are less mature than desired to the point where they are ready for
project insertion. TRAs and TMPs are effective management tools for reducing technical risk
and minimizing potential for technology driven cost increases and schedule delays.
A TRA evaluates technology maturity using the Technology Readiness Level (TRL) scale that
was pioneered by the National Aeronautics and Space Administration (NASA) in the 1980s. The
TRL scale ranges from 1 (basic principles observed) through 9 (total system used successfully in
project operations). See Figure 1 for a schematic of the meaning of the TRLs in the context of
DOE EM projects.
In 1999 the General Accounting Office (GAO) (GAO/NSIAD-99-162) recommended that the
DoD adopt NASA’s TRLs as a means of assessing technology maturity prior to transition. In
2001, the Deputy Undersecretary of Defense for Science and Technology issued a memorandum
that endorsed the use of TRLs in new major programs. Subsequently, the DoD developed
detailed guidance for performing TRAs using TRLs in the 2003 DoD Technology Readiness
Assessment Deskbook (updated in May 2005 [DOD 2005]). Recent legislation (2006) has
specified that the DoD must certify to Congress that the technology has been demonstrated in a
relevant environment (TRL 6) prior to transition of weapons system technologies to design or
justify any waivers. TRL 6 is also often used as the level required for technology insertion into
design by NASA.
In March of 2007 the GAO recommended that DOE adopt the NASA/DoD methodology for
evaluating technology maturity. In March 2008, the DOE Office of Environmental Management
issued a process guide to assist individuals and review teams that would be involved in
conducting TRAs and TMPs in environmental restoration projects where new technologies are
proposed for insertion into the project (Reference: DOE, Office of Environmental Management,
Technology Readiness Assessment (TRA)/Technology Maturation Plan (TMP)Process Guide,
March 2008).
3.4.1.1 The Relationship of TRAs and TMPs to the DOE Critical Decision
Process
Section 9
The TRA/ TMP process can be employed in a variety of situations requiring the determination of
the state of technology development. In the realm of project management, TRAs and TMPs can
be used as a project management tool to reduce the technical and cost risks associated with the
introduction of new technologies into the realm of a project. For example, this management tool
can be used to support the Critical Decision Process when assessing readiness and technology
maturity levels of a new technology for a project before proceeding to the next development
DOE G 413.3-9 9
9-23-08
phase of a project. While the TRA/TMP process is not currently required by DOE O 413.3A, in
the realm of program and project management, the TRA/TMP process can serve as one of the
tools employed in helping to make the Critical Decisions required by DOE O 413.3A effective.
The five Critical Decisions are major milestones approved by the Secretarial Acquisition
Executive or Acquisition Executive that establish the mission need, recommended alternative,
Acquisition Strategy, the Performance Baseline, and other essential elements required to ensure
that the project meets applicable mission, design, security, and safety requirements. Each Critical
Decision marks an increase in commitment of resources by the Department and requires
successful completion of the preceding phase or Critical Decision. Collectively, the Critical
Decisions affirm the following:
• There is a need that cannot be met through other than material means [CD-0];
• The selected alternative and approach is the optimum solution [CD-1];
• The proposed scope, schedule and cost baseline is achievable [CD-2];
• The project is ready for implementation [CD-3]; and
• The project is ready for turnover or transition to operations [CD-4].
The recommended guidance is to conduct TRAs during conceptual design and preliminary
design processes; and at least 90 days prior to CD milestones. The review process should follow
the system engineering approach to assess proper integration of systems with new technologies
into the project (system within systems rather than piecemeal review). Figure 2 shows how
TRAs and other key reviews support each of the CDs. (There are numerous additional
requirements for each CD. See Table 2 of DOE O 413.3A for a complete listing.)
10 DOE G 413.3-9
9-23-08
Figure 1 – Schematic of DOE/EM Technology Readiness Levels
Figure 2 – Suggested Technology Assessments and Other Review
Requirements for Critical Decisions
Note: The technology reviews, design reviews, and ORR are conducted in advance of the CD milestone to
support the milestone decision. The TRL values above (in parenthesis) at each Critical Decision point are
recommended values.
DOE G 413.3-9 11
9-23-08
CD-0, Approve Mission Need: Identification of a mission-related need and translation of this gap
into functional requirements for filling the need. The mission need is independent of a particular
solution and should not be defined by equipment, facility, technological solution, or physical end
item (413.3A). The focus for Technology Assessment, at this stage, is on clear statement of the
requirements of the input and the desired output of the process. For waste processing this would
include characterization of the waste as well as definition of requirements for the processing and
the waste form. A Technology Requirements Review would assess the adequacy of requirements
definition and characterization information and determine any additional work necessary, to
include an assessment of technology unknowns that need to be further evaluated. If additional
work is necessary to adequately define technical scope of the project, a plan should be developed
detailing its scope and schedule.
Section 10
CD-1, Alternative Selection and Cost Range: Identification of the preferred technological
alternative, preparation of a conceptual design, and development of initial cost estimates. A TRA
and a TMP should be performed during conceptual design, to support the CD-1 approval process.
The TRA and TMP should be linked to the project risk assessment process as a whole. Prior to
CD-1 approval, it is recommended that all Critical Technology Elements (CTEs) of the design
should have reached at least TRL 4 and a TMP should have been prepared that details the
strategies for bringing all CTEs to TRL 6, if possible.
CD-2, Performance Baseline: Completion of preliminary design, development of a performance
baseline that contains a detailed scope, schedule, and cost estimate. The process of technology
development, in accordance with the approved TMP should support all CTEs reaching TRL 6;
attainment of TRL 6 is preferable and indicates that the technology is ready for insertion into
detailed design.
CD-3, Start of Construction: Completion of essentially all design and engineering and beginning
of construction, implementation, procurement, or fabrication. A TRA is only required if there is
significant technology modification as detailed design work progresses. If substantial
modification of a technology occurs, the TRA should be performed and a focused TMP
developed or updated to ensure that the modified technology has attained TRL 6, if possible,
prior to its insertion into the detailed design and baseline.
CD-4, Start of Operations: Readiness to operate and/or maintain the system, facility, or
capability. Successful completion/operation corresponds to attainment of TRL 7/8.
3.5 Unscheduled/Stakeholder Driven Reviews—Independent Cost Reviews
(ICRs)
Independent Cost Reviews are used primarily to verify project cost and schedule estimates and
support the Critical Decision-2 process in establishing project performance baselines.
Independent Cost Reviews are part of the Performance Baseline External Independent Review.
However, an Independent Cost Review or even an Independent Cost Estimate may be requested
at other times for other reasons.
DOE O 413.3A requires the development of an Independent Cost Estimate (ICE) or an
Independent Cost Review for Major System Projects as part of the Performance Baseline
12 DOE G 413.3-9
9-23-08
Validation EIR performed by the Office of Engineering and Construction Management. An ICE
should be performed where complexity, risk, cost, or other factors create a significant cost
exposure for DOE. For Major System Projects, the ICR or ICE required by DOE O 413.3A
should be developed by OECM in coordination with the DOE Office of Cost Analysis, as part of
the performance cost baseline validation process.
Also under the category of Unscheduled/Stakeholder Driven Reviews, the Acquisition Executive
or PSO/Deputy Administrator can request any type/category of review for the project as deemed
appropriate. These reviews could also be driven by stakeholders such as the Government
Accountability Office, NRC, DNFSB, DOE Headquarters, or the user.
4.0 Overview of the EIR/IPR Planning Process
Section 11
The EIR/IPR review process is normally a collaborative process, although the overall
coordination of all review activities resides with OECM or the Project Management Support
Office (PMSO), as it applies to the type of review and purpose. During the planning phase,
project background information is assembled for the review committee or team. The IPR team is
always led by a DOE Federal employee. For an EIR, the team is led by an OECM representative
(Federal employee) but the review is usually conducted by an external group/contractor. Key
project team points of contact at DOE Headquarters and the field are identified. The proposed
scope of the review is planned in coordination with the DOE Proponent (program office),
program manager and the Federal Project Director. For EIRs, since they are meant to be
“external” and “independent”, after receiving scope input from appropriate project stakeholders,
ultimately the final scope of work is determined by OECM and their external stakeholders. After
determining the scope of the review, it is possible to identify the subject matter expertise that
should be represented to staff each review team. OECM or the PMSO identify and arrange for
appropriate personnel to staff each review team, in consultation with the requesting organization
(personnel are matched with the lines of expertise required). The review team develops a
Review Plan to help the review team coordinate activities as it executes the review (see
Appendix D for an example of a tailored EIR Review Plan and Appendix E for an example of an
IPR Review Plan Template). Table 1 shows the Review Plan main elements.
Table 1 – Review Plan Main Elements
Purpose Primary reason for the review and type of review.
Background
Relationship of the project to the sponsoring DOE program element
Project Description and Status.
Objectives Scope of Review and Lines of Inquiry. The scope of the review (tailored
by the type of review and stage of the project) should address technical,
cost, and schedule baselines, including management factors and
acquisition approach used to justify the project and develop its scope. It
should also address risk, safety and security management approaches.
Problem/Issues Key obstacles the project faces.
DOE G 413.3-9 13
9-23-08
Review
Logistics Review Process to include dates and site visit schedule.
Resources/Team
Members
Size and configuration of the review team.
Biographies of Team Members and assignments for the review.
Documentation Project documentation to be prepared and made available prior to or at
the review.
Budget Possible budget issues for funding the review (not included in EIR plan).
Detailed
Schedule
Primary activities in the review with completion dates for these activities.
The typical activities in a review schedule and associated timing are shown in Table 2. The
standard deliverables of a review, in addition to the Review Plan, include the Closeout Report
(exit briefing), Draft Review Report and the Final Report.
Team Members Selection
Each review team is configured to satisfy the unique purpose of the review. It is critical that the
individuals selected to perform the independent reviews be technically qualified/certified,
credible and possess indisputable integrity and independence (contractors can be employed). All
members of the review team should have excellent track records of performance under the
technical areas assigned to review and recognized professional credibility. The reviewers should
have no affiliation with the project being reviewed and are as independent as possible. In
addition, the reviewers are not drawn from the responsible program office within the Program
Secretarial Office, related contractors from the project office, or a related funding office.
Section 12
The EIR/IPR review chairperson is always a DOE Federal employee, usually from OECM or the
Project Management Support Office, as it applies. Team members can be selected from experts
from national laboratories, universities, and private industry (contractors) and Federal employees
from other sites or offices. EIR team members should be independent (i.e., have no interest
and/or equity) of the project to be reviewed. The range of disciplines involved may include
project relevant technical disciplines, project management, contract systems, cost engineering,
Environment, Safety, Quality and Health.
14 DOE G 413.3-9
9-23-08
Table 2 – Typical Timeline for a Performance Baseline External Independent Review
Week
0
Week
1
Week
2
Week
3
Week
4
Week
5
Weeks
6-8
Week
9
Week
10
Week
11
Weeks
12+
OECM Receives
documents
EIR team prepares Draft
Review plan and submits
for comments.
Kick-off meeting
conducted. Team reviews
project documents.
Program/ Project / Site
provide comments; team
continues document
review.
EIR team develops Final
Review Plan and provides
specific Review
Questions. Site reviews
questions and prepares
for EIR.
On-site review ending with
Out Brief to Project Team
EIR team prepares draft
report and submits to
OECM.
OECM transmits Draft EIR
Report for factual
accuracy review.
Resolution conference
held, if requested.
Program/ Projects submits
factual accuracy
comments
Project Develops
Corrective Action Plan
Response
EIR Team and OECM
reviews Corrective Action
Plan and resolves any
outstanding issues with
Program/Project
EIR Team develops Final
EIR Report and Validation
Recommendation
OECM transmits Final EIR
Report ,Corrective Action
Plan, and Validation
Recommendation
Project submits Updated
Corrective Action Plan for
EIR Team review, as
needed
EIR Team develops
Correction Action Plan
Review Report, as needed
OECM transmits EIR
Corrective Action Plan
Review Report, as needed
DOE G 413.3-9 15
9-23-08
5.0 Required and Optional Project Reviews
This section provides the scope and project documentation for reviews that may occur during a
DOE project’s life cycle. Table 3 provides a summary of the reviews in the order they normally
occur and the responsible organizations.
Table 3 – Types of Project Reviews in Support of
Critical Decision Milestones (DOE O 413.3A)
Review Type
Accomplished
Prior to Critical
Decision (CD):
Required or
Optional
Responsible
Organization Type of Review
Mission Need CD-0 Required for
Major System
(MS) Projects
Program Secretarial
Officer (PSO)/Deputy
Administrator.
Independent Project
Review (IPR). In
addition, the Office of
Program Analysis and
Evaluation, must
review the Mission
Need Statements and
provide a
recommendation to the
PSO/Deputy
Administrator for
projects with a TPC
greater than or equal to
$100M.
Technical
IPR/Design
Review
CD-1 As part of the
Design Review,
IPR required for
high risk, high-
hazard, Hazard
Category 1, 2 and
3 nuclear
facilities. Design
Review required
of the Conceptual
Design and
continuing
through the life of
the project, as
appropriate.
PSO/Deputy
Administrator.
IPR and Design
Reviews. Technical
IPRs and Design
Reviews for Hazard
Category 1, 2, and 3
facilities should identify
substantial safety issues
earlier in the design
process, determine a
satisfactory resolution
for these issues, and
ensure this task will be
performed/accomplished
prior to CD-1.
Acquisition
Strategy
CD-1 Required for MS
Projects
Section 13
OECM for MS Projects Review of Acquisition
Strategy Document by
OECM and provide
recommendation to the
PSO/Deputy
Administrator.
Alternative
Selection and
Cost Range
CD-1 Optional PSO/Deputy
Administrator
IPR
Design Beginning at CD-1 Required for PSO/Deputy Design Review by
16 DOE G 413.3-9
9-23-08
Review Type
Accomplished
Prior to Critical
Decision (CD):
Required or
Optional
Responsible
Organization Type of Review
Reviews and continuing
through the life of
the project as
appropriate.
projects with a
TPC equal or
greater than
$20M. Optional
for Projects
greater or equal to
$5M and < $20M
Administrator or as further
delegated.
technical qualified
individuals internal and
external to the project.
Performance
Baseline
CD-2 Required OECM for projects with
TPC greater or equal to
$100M. For projects with
a TPC <$100M the Project
Management Support
Office.
External Independent
Review (EIR) for TPC
equal or greater than
$100M. IPR for
projects with a TPC <
$100M (see Note 1).
Performance
Baseline
Validation
Review as a
result of a
Deviation
After CD-2 and
prior to approval
of the proposed
new baseline
through a Baseline
Change Proposal
(BCP).
Required OECM for projects with a
TPC greater or equal to
$100M or where the
Secretarial Acquisition
Executive (SAE) is the
approval authority for the
BCP. For projects with a
TPC <$100M, and the
BCP is below the SAE
approval authority, the
Project Management
Support Office.
External Independent
Review (EIR) for
projects with a TPC
equal or greater than
$100M or where S-2 is
the approval authority
for the BCP. IPR for
projects with a TPC <
$100M and the BCP is
below the SAE approval
authority (see Note 1).
Construction
or Execution
Readiness
Review
CD-3 Required for
Major System
Projects. Optional
for Non-MS
Projects when
justification is
provided and
waiver is granted
by the Acquisition
Executive
authority.
OECM for MS projects;
PSO/Deputy
Administrator for Non-MS
projects
EIR for MS projects;
IPR for Non-MS
projects
Note 1: The Acquisition Executive may request an EIR in lieu of and IPR through OECM, and must do so if the Acquisition
Executive has no Project Management Support Office to perform the review.
5.1 Mission Need Review
A Mission Need Review conducted at the direction of the PSO/Deputy Administrator assesses
the Mission Need Statement as the translation into functional requirements of the performance
gap between current capabilities and those capabilities required to achieve the goals in the
strategic plan. The Mission Need Statement should describe the general parameters of the
project, why it is critical to the overall accomplishment of the Department mission, including the
benefits to be realized. The mission need is independent of a particular solution, and should not
be defined by equipment, facility, technological solution, or physical end-item to allow
exploration of a variety of potential solutions. This review should be conducted for Major
System Projects.
DOE G 413.3-9 17
9-23-08
A. Scope of Review
Key review elements for a Mission Need Review include:
• Mission Need Statement. Assess adequacy of documentation confirming that the new
project provides a specific capability that the Department currently lacks to meet its
assigned mission.
• Program/Mission Requirements. Assess whether high-level requirements are sufficiently
defined to identify potential alternatives (to be analyzed in the next phase) that are both
applicable and capable of meeting project goals.
Section 14
• Total Project Cost and Schedule Ranges. Review basis of the rough order of magnitude
cost range and provide an assessment of whether this range reasonably bounds the cost
and schedule of alternatives to be analyzed in the next project phase. Review basis of
schedule range and assess whether the schedule is consistent with strategic requirements
for when this project is required. Also, for projects closely linked to other projects, assess
whether schedule results in appropriate integration.
B. Required Documentation
The required documentation is prescribed by the Review Team as tailored to the specific project.
A suggested list not all inclusive is as follows:
• Mission Need Statement
• Program Requirements Document
• Rough order of magnitude cost ranges and schedule
• Tailoring Strategy (if required)
• Pre-conceptual Integrated Safety Documentation as prescribed by DOE Standard 1189 –
Integration of Safety into the Design Process (if applicable).
5.2 Alternative Selection and Cost Range (CD-1) Reviews
Except for Technical IPRs for Nuclear Facilities, which are required, CD-1 Reviews are optional
IPRs that focus on the analysis supporting the selection of the preferred alternative, ensuring the
system functions and requirements are defined, and ensuring the preliminary cost and schedule
range is reasonable and justified. The Acquisition Strategy is also an integral part of the review.
Technical IPR’s for Nuclear Facilities at CD-1 should also focus on the safety documentation to
determine that it is sufficiently conservative and bounding to be relied upon for the next phase of
the project.
A Design Review should have been conducted of the conceptual design by a qualified technical
team composed of members internal and external to the project whose primary function are to
18 DOE G 413.3-9
9-23-08
determine if the product (drawings, analyses, or specifications) is correct and will perform its
intended functions and meet requirements.
A. Scope of Review
Key review elements for an Alternative Selection and Cost Range Review include:
• Alternative Analysis. Assess whether the alternative selection process evaluates a range
of appropriate attributes for each alternative including cost, maintainability, safety,
technology requirements, risks, and regulatory requirements. Assess whether the analysis
process for recommending a preferred alternative is reasonable and provides best value to
the government. Asses the results of the Design Review of the conceptual design as to
meeting its intended function and will support the Critical Decision 1 process.
• System Functions. Assess whether functions and requirements are provided in sufficient
detail that the preliminary design can be initiated with an unambiguous statement of
work.
• Acquisition Strategy. Assess whether the acquisition strategy has considered the full
range of acquisition alternatives to achieve project objectives within specified constraints.
Assess the Acquisition Strategy ability to meet the mission need in the most effective,
economical, and timely manner.
• Risk Management. Assess whether the key risks for the recommended alternative have
been identified with mitigation steps defined. Assess whether the preliminary cost and
schedule estimates reflect cost contingency and schedule contingency needed to address
risks.
Section 15
• Hazard Analysis. Assess whether the hazard analysis is comprehensive and identifies key
hazards and corresponding safety measures needed to be incorporated into the
preliminary design. Technical IPRs and Design Reviews for Hazard Category 1, 2, and 3
facilities should identify substantial safety issues earlier in the design process, determine
a satisfactory resolution for these issues, and ensure this task will be
performed/accomplished prior to CD-1.
• Preliminary Cost and Schedule Estimates. Review basis of preliminary cost and schedule
estimates for reasonableness and executability. Assess whether the preliminary cost and
schedule estimates include cost contingency and schedule contingency appropriate for the
project.
B. Required Documentation
The required documentation is prescribed by the Review Team as tailored to the specific project.
A suggested list not all inclusive is as follows:
DOE G 413.3-9 19
9-23-08
• Conceptual Design Report (including Alternative Analysis, Hazard Analysis, site
selection criteria, NEPA documentation, system functions and requirements, preliminary
cost and schedule estimates)
• Risk Management Assessment
• Acquisition strategy
• Integrated safety documentation (as required by DOE Standard 1189 – Integration of
Safety into the Design Process). It should not be permissible for Technical IPRs for
Hazard Category 1, 2, and 3 nuclear facilities to be tailored to exclude safety related
aspects of the design; otherwise, the objectives of DOE-STD-1189 could not be met.
• High Performance Sustainability Building considerations
• Preliminary Security Vulnerability Assessment Report
• Preliminary Hazard Analysis Report
• Environmental Documents
• Quality Assurance Plan
5.3 Performance Baseline Review (CD-2) and Baseline Change Proposals
This is an External Independent Review performed by OECM for projects with a TPC of $100M
or greater and by the PMSO for projects with a TPC less than $100M (unless otherwise
requested by the Acquisition Executive). The primary purpose of this review is to support the
validation of the Performance Baseline, and provide reasonable assurance that the project can be
successfully executed.
For projects with a TPC of $100M or greater OECM is responsible for developing and finalizing
the scope for External Independent Reviews. The draft scope of work (Review Plan) will be
provided to the FPD and the project team one week after receipt of the required documentation.
This will allow the project team time to identify specific activities to be covered in the review.
The project team at the site will then have one week to review, comment, and provide
recommendations on the scope of the review for OECM consideration.
Below is a discussion of the 21 core elements that will generally form the scope of the
Performance Baseline review, as well as the required documentation for this review. Additional
elements or lines of inquiry beyond those presented in this document may be included in the
scope of the Performance Baseline review based on unique aspects of the project being reviewed.
It is important to recognize that both the scope and required documentation may vary for specific
projects depending on the type of project and any tailoring that may be applied to the EIR (see
Section 6 for a further discussion of tailoring). On a project by project basis, one of more of the
21 core elements may also be deleted from the review. The focus areas will vary with each
project.
Section 16
20 DOE G 413.3-9
9-23-08
A. Scope of Review
The following are the normal elements and standard Lines of Inquiry (LOIs) that an EIR team
should address. Elements may be added or deleted during the EIR scoping process, and LOIs
will be further clarified and documented in the review plan.
(1) Basis of Scope (As defined in the Work Breakdown Structure(WBS), System
Functions and Requirements)
• Assess whether the Work Breakdown Structure (WBS) and WBS dictionary incorporate
all project work scope, and that the defined work scope and system requirements are
derived from and consistent with the approved Mission Need.
• Assess whether the Resource Loaded Schedule is consistent with the WBS for the project
work scope.
• Assess if the WBS represents a reasonable breakdown of the project work scope, and
whether it product oriented.
• Identify and assess the basis for and reasonableness of key programmatic, economic and
project scope assumptions as related to the quality and completeness of the WBS,
technical and design requirements, and risk management planning and contingency
requirements. Identify all underlying technical assumptions and assess whether they are
sound and/or appropriately addressed within the Risk Management Plan and adequately
supported with funded contingency, particularly for new technologies that have never
been developed and/or prototyped within the proposed environment.
• Assess whether it is reasonable to divide the work scope presented into more than one
discrete project. If applicable, identify the basis for managing such discrete projects in an
integrated program.
• Review the Program Requirements Document (PRD), or equivalent, and assess if project
planning reflects the PRD and is consistent with the Mission Need.
• Assess whether "design-to" functions are complete and have a sound technical basis (The
EIR Team should include in their assessment safety and external requirements such as
permits, licenses, and regulatory approvals).
• Assess whether the requirements have been defined well enough to establish a firm
performance baseline.
• Assess whether the CD-4 (project completion) activities and requirements, and project
key performance parameters (KPPs) are clearly defined in the Requirements Document.
Assess whether these activities and requirements are sufficiently defined, under change
control and not expected to change, quantified, measurable, and can reasonably be
determined as complete. Identify the CD-4 requirements/activities/KPPs in a separate
table in the EIR report, including summary analysis results.
DOE G 413.3-9 21
9-23-08
• Assess adequacy and completeness of standards and requirements to include DOE
Directives (e.g., Policies, Orders, Standards and Guides to include DOE O 413.3A, DOE-
STD-1189, etc.) identified as being applicable and appropriate to the project either due to
the nature of the project or contract requirements. Identify any areas of non compliance
with the identified standards and requirements.
(2) Basis of Cost (As defined in the Resource Loaded Schedule (RLS))
• For selected Work Breakdown Structure (WBS) elements (typically, those constituting
significant cost and/or risk), evaluate the detailed basis for the cost estimate.
• Assess the method of estimation and the strengths/weaknesses of the estimates for each
WBS element reviewed.
• Identify and assess the basis for and reasonableness of key programmatic, economic and
project cost assumptions as related to the quality of estimates for each WBS element, and
risk management planning and contingency requirements.
Section 17
• Develop an Independent Cost Estimate (ICE) or perform an Independent Cost Review
(ICR) for Major System Projects as part of the EIR baseline validation process as
required by DOE O 413.3A (the ICR or ICE should be developed by OECM in
coordination with the DOE Office of Cost Analysis.
• Assess the amount of and basis for economic escalation.
• Assess reasonableness of resource loading, including what resources are loaded.
• Develop summary baseline cost tables of the proposed costs (i.e., PED, TEC, OPC, TPC,
PMB, MR, Fee, DOE Direct Costs, and Contingency) for the EIR report. Verify whether
the estimated costs for the project are reasonable based on professional expertise,
parametric estimates, historical data, etc.
• Verify that the cost value of schedule contingency is included in the TPC.
(3) Basis of Schedule (As defined in the Resource Loaded Schedule)
• For the selected Work Breakdown Structure (WBS) elements, evaluate the detailed basis
of schedule estimate. Assess the total schedule for reasonableness and completeness.
• Assess the method of estimation and the strengths/weaknesses of estimates.
• Review and assess schedule assumptions and evaluate the reasonableness of these
assumptions as related to the quality estimates for each WBS.
• Develop summary baseline schedule tables of the proposed milestones (i.e., Critical
Decision dates and other significant or critical project dates) for the EIR report. Identify
22 DOE G 413.3-9
9-23-08
whether the estimated schedule for the project is reasonable based on professional
expertise, parametric estimates, historical data, etc.
• Determine if schedule contingency is derived quantitatively and if the calculated duration
is placed between the end of the last project critical path activity and the “Submit Request
for CD-4” milestone.
(4) Funding Profile and Budget
• Review and provide the basis for the Funding Profile (e.g. latest Project Data Sheet).
Compare the annual budget with the cost requirements, and assess whether the costs and
budget are reasonably linked. Evaluate any significant disconnects between the
Performance Baseline requirements and budget/out-year funding. Evaluate the
reasonableness of the Budget Authority versus Budget Obligation profiles.
(5) Critical Path
• Assess whether the Critical Path is reasonably defined. Assess whether the Critical Path
reflects an integrated schedule and schedule durations are reasonable.
• Review the duration between the Critical Path completion date and the Project
Completion date (CD-4). Assess whether the schedule contingency (float) is reasonable
for this type of project.
• Evaluate if there is a clearly defined critical path leading to submission of the CD-4
request.
• Assess the critical path schedule for level of effort activities.
• Verify that “near critical paths” are clearly identified.
(6) Risk and Contingency Management
• Review the approach used to identify project risks and assess adequacy of this approach.
• Assess adequacy and completeness of both DOE and contractor risk management planning
including the method(s) used to identify risks, and whether a reasonably complete list of
potential risks was developed for analysis.
o Review key risks (e.g., programmatic, economic, those resulting from assumptions,
technical including those associated with use of critical technologies, etc.) and the
risk rankings, and provide the EIR Team’s assessment of the risk evaluation process
and conclusions.
Section 18
• Assess whether the appropriate risk handling strategies/actions, including accepted risks
and residual risks, have been incorporated into the performance baseline.
• Review and assess cost and schedule contingency (both contractor and DOE).
DOE G 413.3-9 23
9-23-08
o Provide an assessment of whether the analysis for and basis of contingency is
reasonable for this type of project and its associated risks.
o Ensure contingency analysis and allowances are tied to risk assessments.
o Ensure contingency accounts for estimate uncertainty, which is directly tied to design
maturity and estimating methodologies used.
• Assess adequacy of the qualitative analysis and rating (high, medium, or low) of current
risks (including site specific factors such as availability of contractors) for probability of
occurrence and for consequence of occurrence.
• Evaluate the extent and adequacy of quantitative risk analysis.
• Evaluate whether the risk watch list and risk assessment sheets appear to be complete.
• Evaluate the adequacy of the management control process for risk status/updating.
(7) Hazards Analysis/ Safety
• Review the functional make-up of the hazards analysis/safety project team, and provide
an assessment of the overall staffing mix and expertise of the team.
• Assess whether the hazards identified and the accident scenarios represent a reasonably
comprehensive list. Determine if controls are capable of mitigating defined accidents and
if confinement/containment of radioactive material is addressed.
• Assess expectations for facility level systems, structures, and components (SSCs).
Determine whether SSCs for worker and public safety, and safety class/safety significant
(SC/SS) equipment and components, have been incorporated into the design and
Performance Baseline.
• Review the Integrated Safety Management System implementation and assess whether
safety has been appropriately addressed throughout the lifecycle of the project.
• Assess the relevant change control process relative to required documentation and
necessary SSCs.
• Assess the hazard analysis process, including the use of internal and external safety
reviews.
• As applicable, review any Defense Nuclear Facilities Safety Board (DNFSB) and/or
Nuclear Regulatory Commission (NRC) interface and discuss the status of their
involvement. Assess whether DNFSB/ NRC issues have been reasonably considered and
addressed. If not, review the outstanding issues, assess when they will be resolved, and
determine what risks they pose.
24 DOE G 413.3-9
9-23-08
• Assess status of and resolution of corrective actions by the contractor, including
incorporation of any additional identified safety requirements.
Note: The following Lines of Inquiry (LOIs) are applicable to Hazard Category 1, 2,
and 3 nuclear facilities.
• Review if the hazard analysis incorporates expectations from the Safety Design Strategy
(SDS).
• Review the Preliminary Safety Design Report (PSDR), SDS and Fire Hazards Analysis
(FHA). Assess whether these documents are complementary, reflect continuously refined
analyses based on evolving design and safety integration activities during preliminary
design, address all required elements in accord with DOE-STD-1189, and have been
evaluated by appropriate individuals and organizations.
• Assess whether the SDS addresses the following three main attributes of safety
integration as the project progresses through project planning and execution:
Section 19
o The guiding philosophies or assumptions to be used to develop the design;
o The safety-in-design and safety goal considerations for the project; and
o The approach to developing the overall safety basis for the project.
• Ensure a Preliminary Safety Validation Report (PSVR) has been completed; and
• Assess whether it adequately addresses the required review of the PSDR or Preliminary
Documented Safety Analysis (PDSA).
(8) System Functions and Requirements; Basis of Design
• Assess whether “design-to” functions are complete and have a sound technical basis (The
review team should include safety and external requirements such as permits, licenses,
and regulatory approvals).
• Review all underlying technical assumptions and assess whether they are sound and/or
appropriately addressed within the Risk Management Plan and adequately supported with
funded contingency, particularly for new technologies that have never been developed
and/or prototyped within the proposed environment.
• Assess whether the requirements have been defined well enough to establish a firm
performance baseline.
• Assess whether system requirements are derived from and consistent with the Mission
Need.
DOE G 413.3-9 25
9-23-08
• Assess whether the CD-4 (project completion) activities are clearly defined in the
Requirements Document, and whether these activities are quantified and measurable,
or can otherwise be reasonably determined as complete.
• Review the basis of design and assess the reasonableness of the design requirements
and output for each function/operation. Review the unit operation, the design
parameters, and the basis of the design parameters and whether the design basis is
reasonable.
• Review the technology readiness assessment and technology maturation plans and
assess the status of the technology to support baseline validation.
• Ensure safety requirements resulting from review of safety documents (e.g., PSDR and
PSVR) are incorporated into the design and baseline.
• Review the surrogate tests, as applicable, and whether the surrogate composition
reasonably represents the full range of feed streams and whether the design basis
incorporates results of the tests.
• Review process and material balance flow sheets to assess the reasonableness of the
input and output parameters for each unit operation, and adequacy to support
environmental permitting, licensing and other regulatory decisions.
• Ensure that the design addresses results of reliability, availability, maintainability, and
inspect ability (RAMI) analyses.
(9) Preliminary Design Review and Comment Disposition
• Assess whether the design has progressed far enough (is “mature” enough) to support
the proposed performance baseline.
• Confirm that a Design Review has been performed by a qualified team, to ensure the
adequacy of the preliminary design including adequacy of the drawings and
specifications, and assess whether they are consistent with system functions,
requirements, and key performance parameters.
o Review the disciplines and experience of the Project Design Review Team. Assess
whether the Design Review team had appropriate experience and technical
disciplines on the team.
• Review the Design Review comments and responses. Based on a reasonable sample,
assess whether these comments have been incorporated into the design, and whether
the costs and schedule associated with design changes have been incorporated into the
Performance Baseline.
26 DOE G 413.3-9
9-23-08
Section 20
(10) Start-Up Planning and Operations Readiness
• Assess whether the start-up test plan identifies how tests will be determined to be
successful, and evaluate whether the associated equipment and instrumentation has been
included in the preliminary design.
• Review the startup and operational readiness test requirements and plans and assess
whether they represent:
o The acceptance and operational system tests required to demonstrate that the system
meets design performance specifications, safety requirements, and key performance
parameters; and
o Sufficient scope definition to enable reasonable estimates of cost, schedule, and
resources.
• Assess traceability of functional, operational, and safety requirements into the start-up
test plan.
• Determine and evaluate any exceptions taken by a potential construction contractor or
project consultants in meeting startup test specifications.
• Assess whether cost, time and resources estimates are reasonable to accomplish the
required startup activities and have been included in the performance baseline.
• Assess whether the start-up plan has been fully integrated with existing functional
organizations including security.
• Assess whether results of tests (e.g., equipment tests, process tests, surrogate tests, etc.)
have been factored into startup and operational readiness planning.
• Assess whether risks of the test program are provided in the project risks and that there is
sufficient cost and schedule contingency assigned, if appropriate, for problems with test
and equipment failure during start-up testing.
(11) Project Controls/Earned Value Management System (EVMS)
Note: The EIR Team review of a contractor’s Earned Value Management System does not
constitute an EVMS Certification Review or Surveillance review, unless made part of the
EIR scope during the scoping meeting.
• Assess the status of the contractor’s project control system to include the Earned Value
Management System relative to the requirements of the contract and DOE O 413.3A.
• Assess whether project control systems and reports are being used to report project
performance, whether the data is being analyzed by the Federal IPT and contractor
DOE G 413.3-9 27
9-23-08
management, and that management action is taking place as an outcome of the analysis
function.
• Assess the project control process to determine as to how the project incorporate formal
changes, conduct internal re-planning, and adjust present and future information to
accommodate changes. Determine if changes, including acceptable retroactive changes
(correcting errors, routine accounting adjustments, or improving accuracy of the
performance measurement data), are documented, justified, and explained.
• If the project contractor has a certified Earned Value Management System, assess
whether a surveillance system is in place to maintain the system for continued
compliance with the American National Standards Institute EVMS Standard (ANSI/EIA-
748-A-1998).
o Review the contractor’s EVMS system/project control description.
o Assess the contractor’s surveillance program.
• If the project contractor does not have a certified EVMS, assess the likelihood of the
EVMS being certified prior to by CD-2 and no later than CD-3.
o Determine if there is an EVMS certification review scheduled to occur within
sufficient time to permit EVMS certification, and assess the status of efforts and
management focus on ensuring the EVMS is ready for certification review.
Section 21
o If a certification review is in process, assess the status of efforts and management
focus on resolving open issues to obtain certification within sufficient time preceding
the baseline Critical Decision dates.
(12) Quality Control/Assurance
• Assess the applicability, completeness, adequacy, and flow-down of the Project Quality
Assurance Program, including software quality assurance (SQA), based on DOE Order
414.1C and 10 CFR 830 Subpart A. The review team will review the record of QA
audits performed on the Project and the disposition of the audit findings.
• Assure that the QA/QC Plan and implementing procedures address personnel training and
qualifications, quality improvement programs, document and record management, work
processes, management and independent assessments, acceptance test planning and
implementation, and the process for disposition of field changes.
• Assess QA/QC requirements for construction planning.
• Assess whether QA requirements (NQA-1 if applicable) have been appropriately
incorporated into the “Design-to” functions, and costs, time and resources adequately
estimated and included in the baseline.
28 DOE G 413.3-9
9-23-08
(13) Value Management/Engineering.
• Assess the applicability of Value Management/Engineering, and whether a Value
Management/Engineering (VM/E) analysis has been performed with results being
incorporated into the baseline.
• Assess the Value Management/Engineering process for this project including whether the
VM/E team had a reasonable skill mix and experience background.
• Assess whether life cycle cost analysis was reasonably performed as part of the trade-off
studies and various alternatives reviewed.
(14) Project Execution Plan.
• Review the Project Execution Plan (PEP) and determine if it establishes a plan for
successful execution of the project, if the project is being managed and executed in
accordance with the PEP, and if it is consistent with other project documents. Determine
if it has been reviewed by appropriate site and Headquarters’ organizations and comment
resolution agreed to.
• Determine if there is a program for integrated regulatory oversight and assess if
applicable Federal, state, and local government permits, licenses, and regulatory
approvals, including strategies and requirements necessary to construct and operate a
facility or to initiate and perform project activities are identified and will be obtained
when needed to continue project execution on schedule or milestone dates established.
Identify if schedule for receipt of authorization from regulators is realistic and based on
experience, and that requirements and milestone dates are updated as necessary and kept
current.
• Assess key inter-site coordination issues and determine if they are identified, addressed
and resolved or appropriate plans in place to accomplish resolution.
• Assess key on-site coordination issues and determine if they are identified, addressed and
resolved or appropriate plans in place to accomplish resolution.
• Determine if all stakeholders are identified, and assess if their relationship to the project
is evaluated, project impacts on them and their interests identified, and required interfaces
with external organizations or authorities addressed.
• Determine if an appropriate Public Participation Plan is in place based on available
stakeholder information and size and scope of project, and if specific stakeholder group
issues are addressed relative to project goals and objectives, technical issues, project risk,
and environmental strategies.
Section 22
• Identify applicable GAO, IG, and other oversight body reports and determine if issues or
concerns have been resolved or otherwise adequately addressed. Similarly, identify and
assess relevant Congressional language in authorization and appropriation bills.
DOE G 413.3-9 29
9-23-08
(15) Acquisition Strategy
• Review the Acquisition Strategy (AS) to determine if it is consistent with the way the
project is being executed.
• Assess whether there are provisions in the AS for adequate contractor incentives (and
disincentives) to enhance project execution.
• Identify any changes from previously approved AS, and assess whether the changes have
been properly reviewed and authorized and if the current AS still represents the best
value to the Government.
(16) Integrated Project Team (IPT)
• Review Federal and contractor IPT Charters and determine if all appropriate disciplines
are included.
• Confirm that the FPD is certified to manage this project.
• Assess both Federal and contractor project management staffing in terms of number of
personnel, skill set, effectiveness, quality, organizational structure, division of
roles/responsibilities, and processes for assigning work and measuring performance.
(Differentiate between full and part-time IPT members.)
• Assess whether the federal and contractor project teams can successfully execute the
project.
• Ensure IPT membership includes appropriate safety experts. Identify if the Federal IPT
nuclear safety expert is validated as qualified by the Chief of Nuclear Safety/Chief of
Defense Nuclear Safety in accordance with DOE O 413.3A.
• Assess the span of control (in terms of not only supervisory responsibility but also
management of dollars and project issues) of key project management personnel,
including the FPD, to determine whether they can successfully perform their duties.
• Evaluated any deficiencies in the federal or contractor IPTs that could hinder successful
execution of the project.
(17) Sustainable Design
• Assess whether the project has identified sustainable design features, in accordance with
the Energy Policy Act of 2005, Executive Order 13423, and DOE O 450.1 chg 3, and that
these features have been properly accounted for within the performance baseline.
• Assess whether the project is eligible for Leadership in Energy and Environmental
Design (LEED) certification.
30 DOE G 413.3-9
9-23-08
(18) Safeguards and Security
• Assess whether a Preliminary Security Vulnerability Assessment Report as defined in
DOE M 470.4-1 has been updated as required by DOE O 413.3A.
• Assess the completeness and accuracy of the applicable safeguards and security
requirements, the methods selected to satisfy those requirements, and any potential risk
acceptance issues applied to the project and their incorporation into the project.
• Assess adequacy of incorporation of Design Basis Threat requirements into the baseline.
• Review the Performance Baseline to ensure that cost, schedule, and integration aspects of
safeguards and security are appropriately addressed.
• Assess whether all feasible risk mitigation has been identified and that the safeguards and
security concerns for which explicit line management risk acceptance will be required are
appropriately supported.
(19) New Technology and Technology Readiness
• Review all technology decisions that have been made to date and determine whether the
project is incorporating new technologies or existing technologies in new applications.
Section 23
• Assess the plans for and results of tests of new technologies or new applications of
existing technology. Determine if the scale of the test is adequate to mitigate risks and/or
safety concerns.
• Assess whether the identified technologies are at a sufficient level of maturity to be
incorporated into the design and baseline. To the extent possible, provide an analysis of
the Technology Readiness Level for the applicable technologies identified [Government
Accountability Office Report 07-336, Major Construction Projects Need a Consistent
Approach for Assessing Technology Readiness to Help Avoid Cost Increases and Delays,
March 2007].
• Assess whether the current baseline adequately provides for sufficient cost and schedule
to accomplish required research, development, testing, and implementation of these new
technologies or new applications of existing technologies.
• Determine if the Risk Management Plan accounts for risks associated with new
technologies or new applications of existing technologies, and that adequate contingency
has been included.
(20) Contract Management
• Assess the current contract including cost, schedule and work scope against the proposed
baseline and identify any potential contract and project integration issues.
DOE G 413.3-9 31
9-23-08
o Determine whether the terms of the current contract support the project as currently
planned and identify any gaps between the current contract and planned performance
baseline.
o Assess effectiveness of integrated change control and use of change control boards by
both federal and contractor organizations.
o Likewise, assess any planned contract modifications and requests for equitable
adjustments relative to the proposed performance baseline.
• Evaluate the status of contract management, and if applicable, plans and schedule to
bring the contract up to date.
• Assess project plans to self-perform construction and operations readiness versus
subcontracting that work.
• Assess draft documents to be provided to the services (e.g., construction) and product
(e.g., purchased materials and equipment) subcontractors including submittal of
documents by the subcontractors required before notice to proceed (e.g., design
requirements, EVMS, and systems testing and turnover requirements).
(21) Documentation and Incorporation of Lessons Learned
• Assess whether the project team is documenting and sharing lessons learned from their
project internally and externally.
• Assess whether the project team is reviewing and incorporating lessons learned from this
and other projects.
B. Required Documentation
In general, the following documents (or equivalents) are normally required for the Performance
Baseline (EIR). Other associated material may be requested by OECM and the Review Team to
ensure a complete and accurate review is performed. Documentation required can also be
tailored to the EIR plan.
• CD-0 Documents (e.g., Mission Need Statement, Approval of Mission Need)
• CD-1 Documents (e.g., Approval of Alternative Selection and Cost Range)
• Work Breakdown Structure (WBS) and WBS Dictionary
• Detailed Cost Estimate, including Basis of Estimate for selected elements
• Detailed Resource Loaded Schedule (in native format and pdf format)
• Project Data Sheet; identified/approved funding profile
32 DOE G 413.3-9
9-23-08
• Program Requirements Document (or equivalent)
• Critical Path and Near Critical Path Schedules
Section 24
• System Functions and Requirements Document (also referred to as the "Design-to"
requirements or Design Criteria)
• Results of and Responses to Project Design Reviews and Technical Independent Project
Reviews (copy of reports); Design Reviews and Technical Reviews personnel and brief
resumes.
• Design documents including drawings, specifications and design lists; process flow
diagrams, material balance(s)
• Design change logs
• Process test plan including plans for surrogate testing; proof-of-process tests
• Technology Readiness Assessment(s) and Technology Maturation Plan
• Conceptual Design Report
• Project Execution/Management Plans
• Preliminary Construction Execution/Management Plans
• Integrated Project Team Charter (assignment letters as appropriate)
• Documented IPT Processes
• FPD Certification status and Integrated Project Team qualifications (resumes as
appropriate)
• Start-up Test Plan and other operations readiness plans (as appropriate)
• Hazards Analysis/Hazard Analysis Report
• DNFSB and NRC Reports and correspondence identifying any project issues and
resolution
• Responses to DNFSB and NRC reports
• Preliminary Safety Design Report (Hazard Category 1, 2, or 3 nuclear facilities)
• Preliminary Security Vulnerability Assessment Report
• Preliminary Safety Validation Report (Hazard Category 1, 2, or 3 nuclear facilities)
DOE G 413.3-9 33
9-23-08
• Final National Environmental Policy Act documentation
• Risk Management Assessment(s)/Risk Management Plan(s) with identified
federal/contractor contingency
• Risk Watch List
• Contingency/Monte Carlo Analyses and Contingency Plan
• Acquisition Strategy
• Value Management/Engineering Report(s)
• Quality Control/Assurance Plan
• Interface Documentation (procedures, MOU/MOA with site M&O)
• Reports and Corrective Action Plans (CAPs) from previous internal and external project
reviews (if applicable)
• Sustainable design documentation including LEED certification eligibility
• EVMS or project controls reports and project monthly/quarterly reports (last three)
• Trend reports
• Project Control System description
• Change Control Process
• Monthly and Quarterly Progress reports for past year
• Contracts applicable to the project
• Contract Management Plan
• Pending contract modifications/Requests for Equitable Adjustment
• Project Funding Profile (Program budget/planning office should identify if this profile is
within the Program target budget profile)
5.4 Approve Start of Construction Review (CD-3)
The purpose of the Construction or Execution Readiness Review is to assess the readiness for
construction or execution and to confirm the completeness and accuracy of the Performance
Baseline. An External Independent Review is performed by the Office of Engineering and
Construction Management on Major System Projects to verify execution readiness. A similar
Independent Project Review should be performed by the appropriate Program Secretarial Office
34 DOE G 413.3-9
9-23-08
for Non-Major System Projects unless justification is provided and a waiver is granted by the
Acquisition Executive.
The Scope of review for an EIR in support of CD-3 has several elements specific to construction
readiness, but retains many of the elements contained in the Performance Baseline Review.
Below is a discussion of 19 core elements that will generally form the scope of the Construction
or Execution Readiness Review, as well as the required documentation for this review.
Additional elements or lines of inquiry beyond those presented in this document may be included
in the scope of the Construction or Execution Readiness Review based on unique aspects of the
project being reviewed.
Section 25
It is important to recognize that both the scope and required documentation may vary for specific
projects depending on the type of project and any tailoring that may be applied to the EIR. On a
project-by-project basis, one or more of the core elements may be deleted from the review while
others areas are added. The focus areas may also vary if partial CD-3 phases (e.g., CD-3A, CD-
3B) for long lead procurements or early site work are being reviewed and approved in advance of
the complete CD-3 EIR. In addition, if the project is requesting a CD-3A at the time of CD-2,
applicable elements and LOI from the following list should be included in the scope and Review
Plan for a combined CD-2/CD-3A EIR.
A. Scope of Review
The following are the normal elements and standard Lines of Inquiry (LOIs) that an EIR Team
should address. Elements may be added or deleted during the EIR scoping process, and LOIs
will be further clarified and documented in the review plan.
(1) Basis of Scope (As Defined in the Work Breakdown Structure, the Final Drawings
and Specifications, the Final Design Functions and Requirements, and the Site Final
Design Review)
• Identify and assess any changes to the project mission need, scope, or Work Breakdown
Structure (WBS) since CD-2.
• Identify and assess any changes to the basis for and reasonableness of key programmatic,
economic and project scope assumptions as related to the quality and completeness of the
WBS, technical and design requirements, and risk management planning and contingency
requirements since CD-2.
• Identify and assess any changes to the CD-4 (project completion) activities and
requirements and project KPPs since CD-2.
• Assess completeness and quality of drawings and design specifications. Review selected
construction elements or systems, including the key project elements posing the more
difficult construction challenges.
• Assess whether bid packages are sufficiently clear and well defined as to be ready for bid.
DOE G 413.3-9 35
9-23-08
• Assess whether all final design functions and requirements are reflected in the
Performance Baseline, including safety SSCs and external requirements such as permits,
licenses, and regulatory approvals.
• Assess whether all required changes from the Site Final Design Review are incorporated
into the Performance Baseline, and assess whether the technical scope elements of the
Performance Baseline remain consistent with that approved at CD-2.
• Assess whether any design activities that are planned to be performed during construction
as appropriate as to type and amount of designed to be performed. Assess the design
basis for this additional work, what organization will perform the design work, and the
basis to proceed with construction.
• Assess the technology readiness status level to proceed with design and determine if any
process testing is planned and the potential impact to design.
(2) Basis of Cost and Schedule (As defined in the RLS)
• Identify and assess substantive changes to the RLS since CD-2 relative to its consistency
with the approved Performance Baseline (TPC, CD-4 completion schedule).
• For selected WBS elements (typically, those constituting significant cost, schedule and/or
risk), evaluate the detailed basis for the cost or schedule estimate. Assess
strengths/weaknesses of the estimates reviewed.
• Identify and assess any changes since CD-2 to the basis for and reasonableness of key
programmatic, economic and project cost assumptions as related to the quality of
estimates, and risk management planning and contingency requirements.
Section 26
• Assess the amount of and basis for economic escalation. Identify changes since CD-2.
• Assess reasonableness of resource loading, including what resources are loaded.
Determine if resource requirements factor in project performance since CD-2 or
performance of other similar projects in execution.
• Assess whether approved changes are included in the project master cost and schedule
and evaluate if trends or planned changes are adequately identified to provide a firm basis
to proceed with construction.
(3) Construction/Execution Planning
• Assess adequacy of construction/project execution planning.
o Review the adequacy of constructability reviews to assess whether construction
documents have been reviewed for accuracy, completeness, and systems coordination
issues.
36 DOE G 413.3-9
9-23-08
o Assess status of logistics including interface with operating facilities and maintenance
organizations, infrastructure interfaces, adequacy of lay-down areas, temporary
construction facilities, security and badging readiness, and other logistical elements.
o Assess potential coordination issues, missed details, time delays, potential liability, or
inter-contractor coordination items.
• Assess adequacy of the Federal IPT, Site M&O/Prime Contractor and/or Construction
Management Organization (as applicable), and construction contractor staffing for
construction execution to ensure adequate oversight of the work, including safety,
performance, and quality.
o Assess oversight and management of the construction contractor by IPT and site
prime contractor.
• Assess the updated Startup Test Plan to ensure that sufficient information is provided for
contractor commissioning test and system/facility acceptance tests including cold and hot
testing and plans for ORR/RA, as appropriate.
(4) Funding Profile and Budget
• Review and assess the basis for the Funding Profile (e.g. latest Project Data Sheet).
• Compare the annual budget with the cost requirements, and provide an assessment of
whether the costs and budget are reasonably linked. Identify any significant disconnects
between the Performance Baseline requirements and budget/out-year funding. Assess the
reasonableness of the Budget Authority versus Budget Obligation profiles.
(5) Critical Path
• Assess whether the Critical Path is reasonably defined. Identify any changes since CD-2.
• Review the Resource Loaded Schedule relative to the Critical Path and assess whether
the Critical Path reflects an integrated schedule and schedule durations which are
reasonable.
• Assess the duration between the Critical Path completion date and the Project Completion
Date (CD-4). Assess whether the schedule contingency (float) is reasonable for this type
of project.
• Assess if there is a clearly defined critical path leading to submission of the CD-4
request.
• Assess the critical path schedule for level of effort activities.
• Verify that “near critical paths” are clearly identified.
DOE G 413.3-9 37
9-23-08
(6) Hazards Analysis/ Safety
• Identify changes to the hazards analysis and safety basis since CD-2. Assess whether
these changes are reflected in the performance baseline scope, cost and schedule.
• Review the functional make-up of the hazards analysis/safety project team, and provide
an assessment of the overall staffing mix and expertise of the team.
• Assess the Hazard Analysis (HA) process, including the use of internal and external
safety reviews.
Section 27
• As applicable, review any Defense Nuclear Facilities Safety Board (DNFSB) and/or
Nuclear Regulatory Commission (NRC) interface and discuss with the local
representatives the status of their involvement. Assess whether DNFSB/NRC issues have
been reasonably considered and addressed. If not, identify the outstanding issues, assess
when they will be resolved and determine what risks they pose.
• Review the Integrated Safety Management System and assess whether safety has been
appropriately addressed throughout the lifecycle of the project.
• Assess whether the hazards identified and the accident scenarios represent a reasonably
comprehensive list. Determine if controls are capable of mitigating defined accidents and
if confinement/containment of radioactive material is addressed.
• Assess expectations for facility level systems, structures, and components (SSCs).
Determine whether SSCs for worker and public safety, and safety class/safety significant
(SC/SS) equipment and components, have been incorporated into the design and
Performance Baseline.
• Assess the relevant change control process relative to required documentation and
necessary SSCs.
• Assess status of and resolution of corrective actions by the contractor, including
incorporation of any additional identified safety requirements.
Note: The following LOIs are applicable to Hazard Category 1, 2, and 3 nuclear
facilities.
• Identify if the HA incorporates expectations from the Safety Design Strategy (SDS).
• Review the Preliminary Documented Safety Analysis (PDSA) and SDS. Assess whether
these documents are complementary, reflect continuously refined analyses based on
evolving design and safety integration activities during preliminary design, address all
38 DOE G 413.3-9
9-23-08
required elements in accord with DOE-STD-1189, and have been evaluated by
appropriate individuals and organizations.
• Assess whether the SDS addresses the following three main attributes of safety
integration as the project progresses through project planning and execution:
o The guiding philosophies or assumptions to be used to develop the design;
o The safety-in-design and safety goal considerations for the project; and
o The approach to developing the overall safety basis for the project.
• Ensure a Safety Evaluation Report (SER) has been completed and assess whether it
adequately addresses the required review of the PDSA.
(7) Risk Management
• Identify and assess any substantive changes to the Federal and contractor risk and
contingency management plans or processes since CD-2.
• Assess whether the risk assessment and management plan have been updated, as
appropriate, to address any new risks identified in final design and evaluate the adequacy
of the management control process for risk status/updating.
• Evaluate whether the risk watch list appears to be complete.
• Assess whether all appropriate risk handling strategies/actions, including accepted risks,
and residual risks have been incorporated into the performance baseline including cost
and schedule contingency.
• Identify and assess cost and schedule contingency. Provide an assessment of whether the
basis of contingency is reasonable for this type of project and its associated risks, and
whether cost and schedule contingency, including value/cost associated with schedule
contingency, remains sufficient for project risks.
• Assess MR/contingency drawdown and utilization history for reasonableness, and
determine if sufficient contingency remains.
Section 28
(8) Value Management/Engineering
• Assess the application of Value Management/Engineering during Final Design, and if
results have been incorporated into the Performance Baseline.
(9) Acquisition Strategy
• Review the Acquisition strategy to determine if there have been any significant changes
and if the acquisition approach continues to represent the best value to the government.
DOE G 413.3-9 39
9-23-08
(10) Project Execution Plan
• Review the Project Execution Plan and assess if the project is being managed and
executed in accordance with it. It should be updated to reflect any changes as a result of
Final Design and be consistent with the other project documents.
• Identify and assess any changes to the integrated regulatory oversight program since CD-
2. Assess if applicable Federal, state, and local government permits, licenses, and
regulatory approvals, including strategies and requirements necessary to construct and
operate a facility or to initiate and perform project activities are being obtained when
needed to continue project execution on schedule or milestone dates established. Assess
if schedule for receipt of authorization from regulators is updated and kept current.
• Identify and assess any changes since CD-2 to key inter-site or on-site coordination
issues, or stakeholder relationships. Assess if they are identified, addressed and resolved
or appropriate plans in place to accomplish resolution.
• Identify and assess if any new GAO, IG, or other oversight body reports are available
since CD-2 and determine if issues or concerns are adequately addressed. Similarly,
identify and assess relevant Congressional language in authorization and appropriation
bills.
(11) Project Controls/Earned Value Management System
• Assess the status of the contractor’s project control system to include the Earned Value
Management System relative to the requirements of the contract and DOE O 413.3A.
• Assess whether project control systems and reports are being used to report project
performance, whether the data is being analyzed by the Federal IPT and contractor
management, and that management action is taking place as an outcome of the analysis
function.
• Evaluate the control process whereby projects incorporate formal changes, conduct
internal re-planning, and adjust present and future information to accommodate changes.
Determine if changes, including acceptable retroactive changes (correcting errors, routine
accounting adjustments, or improving accuracy of the performance measurement data),
are documented, justified, and explained.
• If the project has a certified Earned Value Management System, assess whether a
surveillance system is in place to maintain the system for continued compliance with the
American National Standards Institute EVMS Standard (ANSI/EIA-748).
o Review the project’s EVMS system/project control description.
o Assess the project’s surveillance program.
40 DOE G 413.3-9
9-23-08
• If the project does not have a certified EVMS, but a certification review is in process of
being completed, assess the status of efforts and management focus on resolving open
issues to obtain certification consistent with the baseline CD-3 date.
(12) Integrated Project Team
• Review Federal and contractor IPT Charters and determine if all appropriate disciplines
are included.
• Confirm that the FPD is certified to manage this project.
Section 29
• Assess both Federal and contractor project and construction management staffing in
terms of number of personnel, skill set, effectiveness, quality, organizational structure,
division of roles/responsibilities, and processes for assigning work and measuring
performance. (Differentiate between full and part-time IPT members.)
• Assess whether the federal and contractor project and construction management teams
can successfully execute the project.
• Ensure IPT membership includes appropriate safety experts. Identify if the Federal IPT
nuclear safety expert is validated as qualified by the Chief of Nuclear Safety/Chief of
Defense Nuclear Safety in accord with DOE O 413.3A.
• Assess the span of control (in terms of not only supervisory responsibility but also
management of dollars and project issues) of key project management personnel,
including the FPD, to determine whether they can successfully perform their duties.
• Assess any deficiencies in the federal or contractor IPTs that could hinder successful
construction or project execution.
(13) Safeguards and Security
• Assess whether a Preliminary Security Vulnerability Assessment Report as defined in
DOE M 470.4-1 has been updated as required by DOE O 413.3A.
• Assess the completeness and accuracy of the applicable safeguards and security
requirements to include Design Basis Threat requirements, the methods selected to satisfy
those requirements, and any potential risk acceptance issues applied to the project and
their incorporation into the project.
• Assess whether all feasible risk mitigation has been identified and that the safeguards and
security concerns for which explicit line management risk acceptance will be required are
appropriately supported.
• Assess any changes to safeguards and security requirements since CD-2 and whether
there is any impact to the project’s performance baseline.
DOE G 413.3-9 41
9-23-08
(14) Contract Management
• Assess the current contract including cost, schedule and work scope relative to the
baseline at CD-3 and identify any potential contract and project integration issues.
o Assess whether the terms of the current contract support the project as currently
planned and identify any gaps between the current contract and planned performance
baseline.
o Assess effectiveness of integrated change control and use of change control boards by
both federal and contractor organizations.
• Assess any planned contract modifications and requests for equitable adjustments relative
to the performance baseline at CD-3.
• Evaluate the status of contract management, and if applicable, plans and schedule to
bring the contract up to date.
• Assess project plans to self-perform construction and operations readiness versus
subcontracting that work.
• Assess draft documents to be provided to the services (e.g., construction) and product
(e.g., purchased materials and equipment) subcontractors including submittal of
documents by the subcontractors required before notice to proceed (e.g., design
requirements, EVMS, and systems testing and turnover requirements).
(15) Start-Up Planning and Operational Readiness
• Identify and assess any changes to the start-up and operations readiness plan since CD-2.
• Ensure the start-up test plan identifies how tests will be determined to be successful, and
that associated equipment and instrumentation has been included in the preliminary
design.
• Review the startup and operational readiness test requirements and plans and assess
whether they represent:
Section 30
o The acceptance and operational system tests required to demonstrate that the system
meets design performance specifications and safety requirements, and
o Sufficient scope definition to enable reasonable estimates of cost, schedule, and
resources.
• Ensure traceability of functional, operational, and safety requirements into the start-up
test plan.
42 DOE G 413.3-9
9-23-08
• Identify and assess any exceptions taken by potential construction contractor or project
consultants in meeting startup test specifications.
• Assess whether cost, time and resources estimates are defensible to accomplish the
required startup activities and have been included in the performance baseline.
• Assess whether there is sufficient cost and schedule contingency for test and equipment
failure during start-up testing.
• Assess whether the start-up plan has been fully integrated with existing functional
organizations including security.
• Assess whether results of tests (e.g., equipment tests, process tests, surrogate tests, etc.)
have been factored into startup and operational readiness planning.
(16) Quality Control/Assurance
• Identify and assess any changes to the Quality Control and Quality Assurance plan since
CD-2.
• Assess the applicability, completeness, adequacy, and flow-down of the Project Quality
Assurance Program, including software quality assurance (SQA), based on DOE Order
414.1C and 10 CFR 830 Subpart A. Review and assess the record of QA audits
performed on the Project and the disposition of the audit findings.
• Assure that the QA/QC Plan and implementing procedures address personnel training and
qualifications, quality improvement programs, document and record management, work
processes, management and independent assessments, acceptance test planning and
implementation, and the process for disposition of field changes.
• Assess QA/QC requirements for construction planning.
• Assess whether QA requirements (NQA-1 if applicable) have been appropriately
incorporated into the “Design-to” functions, and costs, time and resources adequately
estimated and included in the baseline.
(17) Sustainable Design
• Identify and assess any changes to sustainable design requirements and plans since CD-2.
• Assess whether the project team has identified sustainable design features, in accordance
with the Energy Policy Act of 2005, Executive Order 13423, and DOE O 450.1 chg 3,
and that these features have been properly accounted for within the proposed
performance baseline.
• Assess whether the project is eligible for LEED certification.
DOE G 413.3-9 43
9-23-08
(18) New Technology and Technology Readiness
• Identify and assess any changes to technology readiness since CD-2.
• Assess whether the identified technologies are at an in increased and sufficient level of
maturity to be included in construction. To the extent possible, provide an analysis of the
Technology Readiness Level for the applicable technologies identified [Government
Accountability Office Report 07-336, Major Construction Projects Need a Consistent
Approach for Assessing Technology Readiness to Help Avoid Cost Increases and Delays,
March 2007].
• Assess whether the performance baseline adequately provides for sufficient cost and
schedule to implement these new technologies or new applications of existing
technologies.
• Assess if the Risk Management Plan accounts for risks associated with new technologies
or new applications of existing technologies, and that adequate contingency has been
included.
Section 31
(19) Documentation and Incorporation of Lessons Learned
• Assess whether the project team is documenting and sharing lessons learned from their
project internally and externally.
• Assess whether the project team is reviewing and incorporating lessons learned from this
and other projects.
B. Required Documentation
In general, the following documents (or equivalents) are normally required for the Construction
or Execution Readiness Review. Other associated material may be requested by OECM and the
Review Team to ensure a complete and accurate review is performed.
• CD-0 Documents (e.g., Mission Need Statement, Approval of Mission Need)
• CD-1 Documents (e.g., Approval of Alternative Selection and Cost Range)
• CD-2 Documents (e.g., Approval of Performance Baseline)
• Work Breakdown Structure (WBS) and WBS Dictionary
• Program Requirements Document (or equivalent)
• All Baseline Change Proposal and disposition documentation
• Final Design Documents (including drawings, specifications, design lists); construction
bid packages
44 DOE G 413.3-9
9-23-08
• Design Review Team resumes
• Conceptual Design Report
• Results of and Responses to project Design Reviews and Technical Independent Project
Reviews
• Construction Execution/Management Plans
• Project Execution/Management Plans
• Detailed Resource Loaded Schedule
• Detailed bottoms-up Cost and Schedule Estimates based on the completed design
(includes bases of estimate and assumptions)
• Contingency Analysis/Contingency Plan
• Critical Path and Near Critical Path Schedules
• System Functions and Requirements Document (also referred to as the "Design-to"
requirements or Design Criteria)
• Integrated Project Team Charter (assignment letters as appropriate)
• Documented IPT Processes
• FPD Certification status and Integrated Project Team qualifications (resumes as
appropriate)
• Risk Management Plan/Process
• Risk Watch List
• Risk Assessment
• Contingency/Monte Carlo Analyses and Contingency Plan
• Safety Documentation including:
o Preliminary Documented Safety Analysis Report
o Safety Evaluation Report
o Hazards Analysis/Hazard Analysis Report
o Preliminary Safety Design Report (Hazard Category 1, 2, or 3 nuclear facilities)
DOE G 413.3-9 45
9-23-08
o Preliminary Safety Validation Report (Hazard Category 1, 2, or 3 nuclear
facilities)
o Construction Project Safety and Health Plan
• Preliminary Security Vulnerability Assessment Report
• DNFSB and NRC Reports and correspondence
• Responses to DNFSB and NRC reports
• Acquisition Strategy
• Value Management/Engineering Report
• Start-up Test Plan and other operations readiness plans (as appropriate)
• Final National Environmental Policy Act documentation
• Quality Control/Assurance Plan
• Interface Documentation (procedures, MOU/MOA with site M&O)
• Reports and CAPs from previous internal and external project reviews (if applicable)
• Project Control System description
• Change Control Process
• Change Log; trend logs or reports
• Monthly and Quarterly Progress reports for past year
• Contracts applicable to the project
• Contract Management Plan
• Pending contract modifications/Requests for Equitable Adjustment
• Project Data Sheets
• Project Funding Profile (Program budget/planning office should identify if this profile is
within the Program target budget profile)
5.5 Technical Reviews
Technical Reviews are required at CD-1 for high risk, high-hazard, Hazard Category 1, 2, and 3
nuclear facilities. Other types of technical reviews may be required by a stakeholder if a design
Section 32
46 DOE G 413.3-9
9-23-08
includes cutting edge technology and standards for the design do not exist, then a review by
appropriately trained and knowledgeable experts is in order.
A. Scope of Review
Specific types of reviews can include the following lines of inquiry (list is not all inclusive):
• CD-0, CD-1and CD-2 documentation (as applicable depending on project status)
• Functions and Requirements
• WBS and WBS Dictionary
• Alternative Systems
• Basis of Scope, Cost and Schedule
• IPT membership and qualifications; to include nuclear safety experts, as applicable
• Basis for Design
• Preliminary Design
• Detailed Design
• Hazard Analysis/Safety
• Project Definition Readiness Assessment
• Technology Readiness Assessment
• Risk Assessment/Management
• System Verification
• Physical Configuration
• Constructability
• Test Readiness
• Nuclear Safety Integration
• Functional Configuration
• Reliability, availability, and maintainability considerations for maintenance
DOE G 413.3-9 47
9-23-08
B. Documentation
The documentation required for Technical Reviews is tailored to the specific technical
review to be performed by the Review Team. Documentation required depends of the size
and complexity of the project and the particular stage of the project lifecycle, and any project
issues that need to be evaluated.
6.0 Tailoring
Tailoring is an essential component of EIRs and IPRs. Tailoring can apply to any project’s EIR
and IPR. Tailoring will also be used by OECM when validating Performance Baselines as part
of a Baseline Change Proposal following a deviation.
It should not be permissible to tailor the Technical IPR or EIR for High Hazard Category 1, 2,
and 3 nuclear facilities to exclude safety related aspects of the design, otherwise, the objectives
of DOE-STD-1189 could not be met.
A key consideration when tailoring the Performance Baseline EIR is to ensure that the EIR
supports OECM validation of the Performance Baseline. Tailoring strategies should be well
defined and supportable. Tailoring may include:
• Documented EIR/IPR Tailoring Strategy
• Use of summary level Resource Loaded Schedules
• Use of summary cost and schedule supporting documents
• Conducting limited interviews with selected members of the Integrated Project Team over
the telephone or in a videoconference
• Reviewing key documents with minimal site visit, if any
• Reducing the scope of review requirements
• Inclusion of additional review elements and/or lines of inquiry
6.1 Tailored EIR’s for the Office of Environmental Management’s (EM)
Cleanup Projects
The nature of environmental restoration and closure activities performed by the Office of
Environmental Management (EM) requires a tailored approach to EIRs. This tailored approach
has been formalized between OECM and EM into a protocol that will govern the review and
validation of the baseline for EM cleanup projects. These projects are referred to as EM
operations funded project baselines (PBSs- Performance Baseline Summaries) and they present
unique challenges not typically found in capital asset construction projects. The duration of many
of the operations funded project baselines are in excess of 10 years with many continuing to the
year 2035, and beyond. Cost estimates for cleanup activities and operations that far into the
48 DOE G 413.3-9
9-23-08
Section 33
future are highly dependent upon a set of assumptions for escalation rates, current and emerging
technologies, regulatory issues, and success of near-term activities. The cost and schedule basis
of near-term work typically has a higher confidence level than work far into the future. For EM
PBSs, the EIR team will review the performance baseline for the near-term of each PBS and for
the life-cycle closure period of the PBS. The near-term is generally defined as a minimum of five
years or for the contract performance period if the current contract exceeds five years. For
projects that are ending within a couple years or so after the five year period, the near term
should encompass the entire remaining lifecycle baseline. The EIR team will provide a separate
recommendation for the near term assessment and for the life-cycle closure assessment. A more
detailed discussion on the scope, lines of inquiry and required documentation for these reviews is
found in the DOE, OECM, External Independent Review, Standard Operating Procedure (SOP),
dated July 2008.
APPENDICES
DOE G 413.3-9 Appendix A
9-23-08 A-1 (and A-2)
Appendix A: Glossary
1. Acquisition Executive. The individual designated by the Secretary of Energy to integrate
and unify the management system for a program portfolio of projects, and implement
prescribed policies and practices. He/she is the approving authority for a project’s Critical
Decisions, per DOE O 423.3A.
2. External Independent Review. A project review conducted by individuals outside DOE.
The Office of Engineering and Construction Management selects the appropriate contractor
to perform these reviews. One of the most common types of External Independent Reviews
is the Performance Baseline External Independent Review that is utilized to support
validation of the Performance Baseline for Critical Decision-2. A second common type is
the Construction/Execution Readiness External Independent Review that supports Critical
Decision-3, approve start of construction, for Major System Projects.
3. Independent Cost Estimate. A documented independent cost estimate prepared by an entity
outside the proponent program and project being reviewed that has the express purpose of
serving as an analytical tool to validate, crosscheck, or analyze cost estimates developed by
the project proponents. The key attribute of independent cost estimates is that they are
prepared independently of the project proponent estimate.
4. Independent Cost Review. A project management tool used to analyze and validate an
estimate of project costs by individuals having no direct responsibility for project
performance.
5. Independent Project Review. A project management tool that serves to verify the project’s
mission, organization, development, processes, technical requirements, baselines, progress,
and/or readiness to proceed to the next successive phase in the DOE’s Acquisition
Management System.
6. Project Definition Rating Index (PDRI). This is a project management tool used for
assessing how well the project scope is defined. The tool uses a numeric assessment which
rates a wide range of project elements to determine how well the project is defined.
7. Technical Independent Project Review. An independent project review conducted prior to
obtaining Critical Decision-1, Alternative Selection and Cost Range, for high risk, high
hazard, and Hazard Category 1, 2, and 3 nuclear facilities. As a minimum, the focus of this
review is to determine the safety documentation is sufficiently conservative and bounding
to be relied upon for the next phase of the project.
Section 34
8. Technology Maturation Plan (TMP). A TMP detail the steps necessary for developing
technologies that are less mature than desired to the point where they are ready for project
insertion.
9. Technology Readiness Assessment (TRA) Review. A TRA is an assessment of how far
technology development has proceeded. It provides a snapshot in time of the maturity of
technologies and their readiness for insertion into the project design and execution
schedule.
DOE G 413.3-9 Appendix B
9-23-08 B-1
Appendix B: Acronyms
AE Acquisition Executive
ANSI American National Standards Institute
AS Acquisition Strategy
AP Acquisition Plan
CBB Contract Budget Baseline
CD Critical Decision
CDR Conceptual Design Report
CFR Code of Federal Regulations
CO Contracting Officer
CY Calendar Year
DEAR Department of Energy Acquisition Regulation
DoD U.S. Department of Defense
DOE U.S. Department of Energy
CTE Critical Technology Element
EIR External Independent Review
EIS Environmental Impact Statement
EM Environmental Management
EPA U.S. Environmental Protection Agency
ESAAB Energy Systems Acquisition Advisory Board
EVMS Earned Value Management System
FAR Federal Acquisition Regulations
FONSI Finding of No Significant Impact
FY Fiscal Year
GPRA Government Performance and Results Act
HA Hazard Assessment
ICE Independent Cost Estimate
ICR Independent Cost Review
IMS Integrated Master Schedule
IOC Initial Operating Capability
IPL Integrated Priority List
IPR Independent Project Review
IPS Integrated Project Schedule
Appendix B DOE G 413.3-9
B-2 9-23-08
IPT Integrated Project Team
ICE Independent Cost Estimate
IPR Independent Project Review
ISM Integration Safety Management
ISMS Integrated Safety Management System
ISO International Standards Organization
IT Information Technology
KPP Key Performance Parameter
LEED Leadership in Energy and Environmental Design
LOI Lines of Inquiry (EIR and IPR related)
MNS Mission Need Statement
MR Management Reserve
MS Major System Project
NEPA National Environmental Policy Act
NNSA National Nuclear Security Administration
NQA-1 Nuclear Quality Assurance Standard – 1 (ANSI/ASME standard)
NRC National Research Council
OBS Organizational Breakdown Structure
OECM Office of Engineering and Construction Management
OMB Office of Management and Budget
OMBE Office of Management, Budget and Evaluation (DOE)
OPC Other Project Costs
ORR Operational Readiness Review
OSHA Occupational Safety and Health Administration
PARS Project Assessment and Reporting System
PB Performance Baseline
PBC Performance-Based Contract
PBS Performance Baseline Summary
PDS Project Data Sheet
PED Project Engineering and Design
PEP Project Execution Plan
PMB Performance Measurement Baseline
PPBES Planning, Programming, Budgeting and Execution System
PSO Program Secretarial Office
DOE G 413.3-9 Appendix B
9-23-08 B-3 (and B-4)
PMSO Project Management Support Office
QA Quality Assurance
QAP Quality Assurance Plan
QAPP Quality Assurance Program Plan
QC Quality Control
RCRA Resource Conservation and Recovery Act
RD Requirements Document
RFP Request for Proposal
RLS Resource Loaded Schedule
ROM Rough Order of Magnitude
SAE Secretarial Acquisition Executive
SOW Scope of Work
TEC Total Estimated Cost (Capital)
TPC Total Project Cost
VM Value Management
WA Work Authorization
DOE G 413.3-9 Appendix C
9-23-08 C-1
Appendix C: References
10 CFR 830, Subpart A, Quality Assurance Requirements.
10 CFR 830, Subpart B, Safety Basis Requirements.
Section 35
10 CFR 830.206, Preliminary Documented Safety Analysis.
10 CFR 851, Worker Safety and Health Program.
29 CFR 1910.119, Process Safety Management of Highly Hazardous Substances.
40 CFR 68, Chemical Accident Prevention Provisions.
ANSI-EIA-649, National Consensus Standard for Configuration Management.
ANSI-EIA-748-B-2007, Earned Value Management Systems.
DEAR 48 CFR 970.5204-2, Integration of Environmental, Safety, and Health into Work
Planning and Execution.
DOE P 413.1, Program and Project Management Policy for the Planning, Programming,
Budgeting, and Acquisition of Capital Assets, dated 6-10-00.
DOE O 425.1C, Startup and Restart of Nuclear Facilities, dated 3-13-03.
DOE O 451.1B, Chg 1, National Environmental Policy Act Compliance Program, dated 9-28-
01.
DOE P 470.1, Integrated Safeguards and Security Management, dated 5-8-01.
DOE P 450.4, Safety Management System Policy, dated 10-15-96.
DOE P 226.1A, Department of Energy Oversight Policy, dated 5-25-07.
DOE O 205.1A, Department of Energy Cyber Security Management, dated 12-4-06.
DOE O 413.3A, Program and Project Management for the Acquisition of Capital Assets, dated
7-28-06.
DOE O 414.1C, Quality Assurance, dated 6-17-05.
DOE O 420.1B, Facility Safety, dated 12-22-05.
DOE O 450.1A, Environmental Protection Program, dated 6-4-08.
DOE M 470.4-1 Chg 1, Safeguards and Security Program Planning and Management, dated 3-
7-06.
Appendix C DOE G 413.3-9
C-2 9-23-08
DOE-STD-1189-2008, Integration of Safety into the Design Process, dated April 2008
DOE-STD-3006-2000, Planning and Conduct of Operational Readiness Reviews (ORR), dated
June 2000
DOE Office of Engineering and Construction Management (OECM), Project Management
Practices, Integrated Safety, Revision E, dated June 2003.
DOE Office of Engineering and Construction Management (OECM), External Independent
Review (EIR), Standard Operating Procedure (SOP), dated July 2008.
DOE Office of Environmental Management, Technology Readiness Assessment / Technology
Maturation Plan Process Guide, dated March 2008.
DOE Office of Environmental Management, Project Definition Rating Index (EM-PDRI)
Manual, Revision 1, dated February 2001.
DOE Office of Management, Budget and Evaluation, Reviews, Evaluations, and Lessons
Learned, Rev E, dated June 2003.
DOE Office of Science, Independent Review Handbook, dated May 2007.
House Report 109-86, Energy and Water Development Appropriations Bill, 2006.
National Research Council, Improving Project Management in the Department of Energy,
1999.
National Research Council, Progress in Improving Project Management in the Department of
Energy, 2001.
National Research Council, Progress in Improving Project Management in the Department of
Energy, 2003.
National Research Council, Assessment of the Results of External Independent Reviews for U.S.
Department of Energy Projects, 2007.
NNSA Policy Letter: BOP-50.003 (DOE O 413.3A), Establishment of NNSA Independent
Project Review Policy, dated June 2007.
NNSA, Office of Project Management and System Support, Project Definition Rating Index
(PDRI) Manual, Revision 0, dated June 2008.
DOE G 413.3-9 Appendix D
9-23-08 D-1 (and D-2)
Appendix D: Sample of a Tailored External Independent Review Plan
DOE G 413.3-9 Appendix D
9-23-08 D-3 (and D-4)
REVIEW PLAN
EXTERNAL INDEPENDENT REVIEW
OF
PROJECT TITLE:
PROJECT NUMBER:
APPROVE PERFORMANCE BASELINE
AT THE
LOS ALAMOS NATIONAL LABORATORY
LOS ALAMOS, NM
NOVEMBER 28 – DECEMBER 6, 2007
(SITE VISIT)
Section 36
DOE G 413.3-9 Appendix D
9-23-08 D-5 (and D-6)
TABLE OF CONTENTS
ACRONYMS ................................................................................................................................. 7
Section 1 - Review Overview ........................................................................................................ 9
Section 2 – Background .............................................................................................................. 19
Section 3 – Review Logistics ....................................................................................................... 21
Section 4 – Team Members and Assignments .......................................................................... 25
Appendix A – Information Requested ...................................................................................... 26
DOE G 413.3-9 Appendix D
9-23-08 D-7
ACRONYMS
A/E Architect/Engineer
AS Acquisition Strategy
BCP Baseline Change Proposal
BPD Basis of Preliminary Design
CD Critical Decision
CDR Conceptual Design Report
CM Construction Management
CMO Construction Management Organization
CP Critical Path
CPDS Construction Project Data Sheet
DOE Department of Energy
DR Design Review
EIR External Independent Review
EVMS Earned Value Management System
F Finding
F&OR Functional and Operational Requirements
FY Fiscal Year
G&A General and Administrative
GFE Government Furnished Equipment
HA Hazard Analysis
IPT Integrated Project Team
LANL Los Alamos National Laboratory
LANS Los Alamos National Security, LLC
LASO Los Alamos Site Office
LOI Line of Inquiry
M Million
MF Major Finding
NFPA National Fire Protection Association
NMSSUP II Nuclear Materials Safeguards and Security Upgrade Project Phase II
NNSA National Nuclear Security Administration
NRC Nuclear Regulatory Commission
O Observation
OECM Office of Engineering and Construction Management
OPC Other Project Costs
OR Operations Readiness
P3e Primavera Planning and Scheduling Program
Appendix D DOE G 413.3-9
D-8 9-23-08
PDS Project Data Sheet
PED Project Engineering and Design
PEP Project Execution Plan
PHA Preliminary Hazard Analysis
PIDADS Perimeter Intrusion Detection, Assessment, and Delay System
PIDAS Perimeter Intrusion Detection and Assessment System
PM Project Management
PMP Project Management Professional
PRD Program Requirements Document
QA Quality Assurance
QC Quality Control
R&D Research and Development
RLS Resource-Loaded Schedule
RM Risk Management
RMP Risk Management Plan
SER Safety Evaluation Report
SF Square Feet
SFR Systems Functions and Requirements
SME Subject Matter Expert
SNM Special Nuclear Material
SOP Standard Operating Procedure
SSC Structures, Systems, and Components
TA Technical Area
TEC Total Estimated Cost
TIAZ Technical Area Isolation Zone
TPRA Technical and Programmatic Risk Analysis
TPC Total Project Cost
VE Value Engineering
VM Value Management
VM/E Value Management/Engineering
WBS Work Breakdown Structure
DOE G 413.3-9 Appendix D
9-23-08 D-9
Section 1 - Review Overview
The following sections identify the type of review, define the scope and purpose of the review to
be performed, and establish the objectives of the review.
1.1 Type of Review
In accordance with DOE O 413.3A, an External Independent Review (EIR) must be conducted
for all capital asset projects greater than $100 million prior to Critical Decision (CD) – 2,
Approve Performance Baseline. An EIR will be conducted for the Nuclear Materials Safeguards
and Security Upgrade Project Phase II at the Los Alamos National Laboratory, Los Alamos, NM.
The site visit is scheduled for October 9-15, 2007.
Section 37
The EIR Team will review Project documentation prior to and during the site visit, interview
Project participants, and prepare the draft EIR Report (including the Corrective Action Plan
shell) for factual accuracy review by the Project. The EIR report format focuses on the review
elements described in Section 1.3 below. The EIR Team will identify major findings, findings,
and observations in the body of the EIR Report. The EIR Team will insert recommendations
corresponding to all major findings, findings, and observations in a Corrective Action Plan
(CAP) shell that will be an appendix to the report. Major findings and findings will be discussed
during the site visit. Key definitions are:
Major Finding - Any finding that has a significant scope, cost or schedule impact and, in the
professional judgment of the EIR Team, needs to be satisfactorily addressed prior to an EIR
team recommendation to validate the baseline. Major Findings also include findings that
significantly impact safety or the ability of the project team to successfully execute the
baseline.
Finding - Any deficiency that can impact the estimated project cost or schedule. In general,
findings include deficiencies in the hazards analysis, design, risk assessment, scope
definition, system requirements, and start-up. Findings also include safety concerns or the
ability of the project team to successfully execute the baseline.
Observation - A comment, not of sufficient gravity to question the validity of the project
baseline, but identifies an opportunity for project improvement, or an item of exceptionally
good practice for which the project should be commended.
1.2. Objectives of Review
The primary objective of this review is to support the Department of Energy (DOE), Office of
Engineering and Construction Management’s (OECM) validation of the performance baseline.
To accomplish this objective, the EIR Team will review available technical and project
management documents to confirm the completeness and accuracy of the performance (scope,
cost, and schedule) baselines for the NMSSUP II.
Appendix D DOE G 413.3-9
D-10 9-23-08
1.3. Scope of Review
The review will be conducted in accordance with the OECM Statement of Work and consistent
with requirements provided in DOE O 413.3A [Section 5.h.(3) Performance Baseline Validation
Review and Table 2 Critical Decision Requirements]; and subsequent OECM direction and
guidance. The review areas and associated lines of inquiry shown below will be addressed for
the NMSSUP II review using a tailored approach. Information requested is identified in
Appendix A.
1.3.1. Basis of Scope (As defined in the Work Breakdown Structure, System Functions
and Requirements)
The EIR Team will:
• Assess whether the WBS incorporates all Project work and whether the WBS represents a
reasonable breakdown of the Project work scope and is product oriented.
• Assess whether a WBS dictionary adequately describes the Project work scope.
• Review the Program Requirements Document (PRD) and assess if project planning is
consistent with the PRD and the Mission Need.
• Assess whether the overall integrated Project Resource-Loaded Schedule (RLS) is
consistent with the WBS for the Project work scope.
1.3.2. Basis of Cost (As defined in the Resource Loaded Schedule (RLS))
For all WBS elements the EIR Team will:
• For Work Breakdown Structure (WBS) elements constituting significant cost and/or risk,
assess the estimating method(s), quality and confidence level, and summarize the detailed
basis for the cost estimate including escalation and equipment procurements.
Section 38
• For escalation
- Determine the cost escalation rate for the out years;
- Determine whether the risk of higher cost escalation is addressed in risk management;
- Determine how much management reserve/contingency is provided to cover
increased cost escalation above what was planned.
• Identify and assess key cost assumptions and evaluate the reasonableness of these
assumptions as related to the quality of estimates for each WBS and determine whether
these assumptions are factored into the Risk Management Plan and resulting contingency
requirements.
DOE G 413.3-9 Appendix D
9-23-08 D-11
• Determine the cost to get to CD-3.
1.3.3. Basis of Schedule (As defined in the RLS)
The EIR Team will:
• For Work Breakdown Structure (WBS) elements constituting significant cost and/or risk,
assess the schedule development method(s), quality and confidence level; summarize the
detailed basis of schedule estimate.
• Identify and assess schedule assumptions and evaluate the reasonableness of these
assumptions as related to the quality estimates for each WBS and determine whether
these assumptions are factored into the Risk Management Plan and resulting contingency
requirements.
• Assess the reasonableness of the schedule relative to the critical path.
• Assess that work packages are organized based on dependencies, interdependencies,
constraints and other factors into a time-phased sequence that will fit within the
boundaries established by mission dates and available budget.
1.3.4. Funding Profile and Budget
The EIR Team will:
• Review/confirm the basis for the Funding Profile (e.g. latest Project Data Sheet).
• Compare the annual budget with the estimated costs and obligation requirements, and
provide an assessment of whether the projected costs and budget are reasonably linked.
• Identify any significant disconnects between the Performance Baseline requirements and
budget/out-year funding.
• Develop a comparison of the performance baseline (across the life of the project) to the
latest (budget) funding profile.
1.3.5. Critical Path
The EIR Team will:
• Assess the method(s) employed to develop the Critical Path and whether the Critical Path
is reasonably defined, reflects a fully integrated schedule and schedule durations are
reasonable.
• Assess whether the schedule contingency (float) is reasonable for this type of project.
Appendix D DOE G 413.3-9
D-12 9-23-08
1.3.6. Risk and Contingency Management
The EIR Team will:
• Assess adequacy of the risk management plan and of the method(s) used to identify risks,
including evaluation of assumptions, and whether a reasonably complete list of potential
risks was developed for analysis.
• Ensure that all programmatic, technical, cost, and schedule assumptions were properly
addressed in the risk assessment and assess the reasonableness of the assumptions.
• Assess adequacy of the qualitative analysis and rating (high, medium, or low) of current
risks (including site specific factors such as availability of contractors) for probability of
occurrence and for consequence of occurrence.
• Evaluate the extent and adequacy of quantitative risk analysis.
• Evaluate whether the risk watch list and risk assessment sheets appear to be complete.
• Evaluate the adequacy of the management control process for risk status/updating.
• Identify cost and schedule contingency/management reserve and provide an assessment
of whether the basis of the NNSA contingency and National Security Technologies
(NSTec) management reserve are reasonable for this type of project and its associated
risks.
Section 39
• Assess whether all appropriate risk handling actions, including accepted risks and
residual risks, and cost and schedule contingency/management reserve have been
incorporated into the performance baseline including.
1.3.7. Hazards Analysis/Safety
The EIR Team will:
• Identify the functional make-up of the Preliminary Hazards Analysis (PHA) team, and
provide an assessment of the overall staffing mix and expertise of the team.
• Assess the PHA analysis process and results, including the use of internal LASO and
external NNSA Service Center safety subject matter expert (SME).
• Assess whether the PHA and NNSA Safety Evaluation Report (SER) identified the
accident scenarios and represents a reasonably comprehensive list.
• Assess whether all systems, structures, and components (SSCs) needed for worker and
public safety have been incorporated into the Performance Baseline.
DOE G 413.3-9 Appendix D
9-23-08 D-13
• Review the SER and NNSA designation of the NMSSUP Phase II as a non-major
modification to TA-55, and assess whether safety has been (1) appropriately integrated
into the design efforts, (2) appropriately addressed throughout the lifecycle of the project,
and (3) reflects continuously refined analysis based on evolving design and safety
integration activities during the design process and planned construction.
• Review any Defense Nuclear Facilities Safety Board (DNFSB) interfaces. Discuss the
status of their involvement and determine whether DNFSB issues were reasonably
considered and addressed.
1.3.8. Systems Functions and Requirements
The EIR Team will:
• Assess whether system requirements are derived from and consistent with the Mission
Need, Program Requirements Document (PRD), CD-1 Acquisition Execution approval
and direction, and NNSA direction for the 3-Corner and Inner-Dog-Leg reconfiguration
design and construction planning.
• Assess whether systems functions and requirements have been defined well enough to
establish a firm performance baseline and properly documented, e.g., requirements
document, system design descriptions, facility design description, or equivalent
documentation.
• Assess whether "design-to" functions are complete and have a sound technical basis
including safety and external requirements such as permits, licenses, and regulatory
approvals.
• Identify all underlying technical assumptions and assess whether they are sound and/or
appropriately addressed within the Risk Management Plan and adequately supported with
funded contingency.
• Assess whether the CD-4 (project completion) requirements/key performance parameters
(KPPs) are clearly defined in the Project Execution Plan, and whether these requirements
are locked down (not subject to change), quantified and measurable, or can otherwise be
reasonably determined as satisfied.
1.3.9. Basis of Design
The EIR Team will
• Review the basis of design and assess the reasonableness of the design requirements and
output for each function/operation. Summarize the assessment by providing a description
of the unit operation, the design parameters, the basis of the design parameters and an
assessment of whether the design basis is reasonable.
Appendix D DOE G 413.3-9
D-14 9-23-08
1.3.10. Preliminary Design, Design Review and Comment Disposition
The EIR Team will:
• Review the adequacy of the preliminary design including adequacy of the drawings and
specifications, and assess whether they are consistent with system functions and
requirements.
Section 40
• Assess whether all designated safety structures, systems, and components (SSCs) are
incorporated into the preliminary design.
• Assess whether the design documents support the proposed performance baseline.
• Assess whether the NSTec Project Design Review team had appropriate experience and
technical disciplines.
• Assess whether the design review process is adequate.
• Assess, based on a reasonable sample, whether the 30%, 60% and 90% complete LANL
design review comments were incorporated into the design and whether the costs and
schedule changes associated with design changes were incorporated into the performance
baseline.
1.3.11. Value Management/Engineering
The EIR Team will:
• Assess the applicability of Value Management/Engineering, and whether a Value
Management Assessment and a Value Engineering Study were performed with results
being incorporated into the baseline.
• Assess the Value Management/Engineering process including whether the VM team has
a reasonable skill mix and experience background.
• Assess whether life cycle cost analysis was reasonably performed for the trade-off studies
and various alternatives reviewed.
1.3.12. Project Controls/Earned Value Management System
The EIR Team will:
• Determine status of obtaining EVMS certification and the extent to which the EVMS is
compliant with the ANSI/EIA-748-A-1998 standard.
• Assess whether the project is reporting and analyzing earned value management
information and that management action is taking place as an outcome of the analysis
function.
DOE G 413.3-9 Appendix D
9-23-08 D-15
• Assess the project EVMS deliverables to NNSA for usefulness, content and quality.
• Assess the system/methodology for analyzing and managing the critical path schedule.
• Assess the methodology for determining Estimate at Complete for the Project activities.
• Evaluate the Federal and contractor control processes whereby projects incorporate
formal changes, conduct internal replanning, and adjust information to accommodate
changes, including control and use of management reserve and contingency.
1.3.13. Acquisition Strategy
The EIR Team will:
• Determine whether the project is being executed consistent with the AS.
• Assess whether there are adequate contractor incentives (and disincentives) to enhance
project execution.
• Evaluate changes from the previously approved AS and whether the current AS
represents best value to the government.
1.3.14. Project Execution Plan (PEP)
The EIR Team will determine whether the PEP:
• Is complete and current and signed by at least the FPD.
• Reflects and supports the way the Project is being and will be managed, establishes a plan
for successful execution of the Project, and is consistent with the other Project
documents.
1.3.15. Integrated Project Team (IPT)
The EIR Team will:
• Assess the Federal IPT Charter, staffing (number and skill mix of full and part-time
members), organizational structure, division of roles/responsibilities, and processes for
assigning work and measuring performance, to determine whether the IPT is properly
constituted to successfully execute the project within the proposed performance baseline.
• Assess whether the contractor project management staffing level is appropriate,
determine if appropriate disciplines are included on the contractor project management
team, and identify any deficiencies that could hinder successful Project execution.
Section 41
• Assess the span of control (in terms of not only supervisory responsibility but also
management of dollars and project issues) of key project management personnel,
Appendix D DOE G 413.3-9
D-16 9-23-08
including the FPD, to determine whether they can successfully perform their duties.
• Identify any deficiencies in the IPT or overall program/project management structure
(federal and contractor) that could hinder successful execution of the project.
1.3.16. Start-Up Planning and Operations Readiness
The EIR Team will:
• Assess whether the startup test requirements represent acceptance and operational system
tests required to demonstrate that the system meets design performance specifications and
safety requirements, and
• Ensure that the startup test plan identifies how tests will be determined to be successful
and that associated equipment and instrumentation were included in the design and
construction documents.
• Review key tests to ensure that sufficient description is provided to estimate cost and
schedule durations associated with these tests, including sufficient cost management
reserve and schedule contingency for test and equipment failure during startup testing.
• Assess whether cost and schedule included in the performance baseline are defensible to
accomplish the required startup activities.
• Assess whether the start-up plan has been fully integrated with existing LANL functional
organizations.
1.3.17. Quality Control/Assurance
The EIR Team will:
• Assess if the Quality Assurance Plan includes all the processes required to ensure that the
project meets DOE QA Criteria and produces the following outcomes:
- Project development and execution has and or will occur in a controlled manner
- Components, systems, and processes have and or will be designed, developed,
constructed, tested, operated, and maintained according to engineering standards and
technical specifications.
- Resulting technical data are valid and retrievable.
• Assess the adequacy in the QA Plan of roles and responsibilities for quality Management.
1.3.18. Safeguards and Security
The EIR Team will:
DOE G 413.3-9 Appendix D
9-23-08 D-17 (and D-18)
• Assess whether a Preliminary Security Vulnerability Assessment Report as defined in
DOE M 470.4-1 has been updated as required by DOE O 413.3A.
• Assess the completeness and accuracy of the applicable safeguards and security
requirements, the methods selected to satisfy those requirements, and any potential risk
acceptance issues applied to the project and their incorporation into the project.
• Assess adequacy of incorporation of Design Basis Threat requirements into the baseline.
• Review the Performance Baseline to ensure that cost, schedule, and integration aspects of
safeguards and security are appropriately addressed.
• Assess whether all feasible risk mitigation has been identified and that the safeguards and
security concerns for which explicit line management risk acceptance will be required are
appropriately supported.
DOE G 413.3-9 Appendix D
9-23-08 D-19
Section 2 – Background
This section includes a description of the project, cost data, and status of the project. A detailed
description of the Project is located in the PEP.
2.1 Project description and status
The NMSSUP Phase II will provide a modern, state-of-the-art, exterior physical security
protection system designed to meet NNSA and DOE protection requirements of current and
future Category I (CAT-I) special nuclear material (SNM) facilities sited within LANL
Technical Area (TA) 55.
Section 42
The NMSSUP Phase II scope of work consists of an exterior Perimeter Intrusion Detection,
Assessment, and Delay System (PIDADS) replacing the existing Perimeter Intrusion Detection
and Assessment System (PIDAS) with a re-configured Perimeter Intrusion Detection,
Assessment and Delay System (3-Corner PIDADS) having an Inner Dog-Leg PIDADS to
support future Chemistry and Metallurgical Research Replacement Facility (CMRR)
construction, an Airborne Mitigation System, a Technical Area Isolation Zone (TAIZ), two
Entry Control Facilities (EFC) (East ECF for pedestrian and vehicle entry and West ECF for
vehicle traffic only), and the Limited Area fencing for three existing Nuclear Material
Technology Division support facilities located adjacent to the PIDADS, including the CMRR
Radiological Laboratory Utility Office Building. NMSSUP Phase II is presently under design
using multiple time and material subcontracts and will use multiple fixed-price construction
subcontracts for delivery of the project.
Table 2-1: Total Project Cost ($K)/Schedule Summary*
NMSSUP II Proposed
Baseline
Performance Measurement Baseline
Management Reserve
Fee
Other Project Costs
Contingency
Performance Baseline/TPC
CD-4 Schedule
Life Cycle Cost
Lifecycle Schedule
* Estimates from ___________.
Appendix D DOE G 413.3-9
D-20 9-23-08
Table 2-2: Major Milestones for LANL NMSSUP II
Milestones Description Planned Date Actual Date
CD-0 Approved mission need
CD-1 Approved preliminary baseline range
OECM CD-2 EIR visit External Independent Review site visit to support
establishment of performance measurement baseline
11/28-
12/6/2007
CD-2
Establish performance measurement baseline,
authorize some early site work and some long lead
procurements
CD-31 Authorize construction
CD-41 Approve project completion/start of operations
1 Dates are from________.
DOE G 413.3-9 Appendix D
9-23-08 D-21
Section 3 – Review Logistics
3.1 Dates of site visit
The EIR Team plans to visit the project organization in Los Alamos during the period November
5-9, 2007, to review Project documentation, interview Project participants and present results of
the review at an out-brief. The draft EIR Report, including a Corrective Action Plan shell, for
factual accuracy review will be prepared immediately after the visit.
3.2 Site visit Schedule
The schedule for the NMSSUP II EIR Team site visit is shown in Table 3-1.
Table 3-1: EIR Site Visit Schedule (Preliminary)
Day Date
(2007) Location Time Activity
1 Nov 28,
2007 TBD
8 am – 8:30 am Check-in and Badging
8:30 – 9:30 am
- Introductions
- OECM Inbrief
- EIR Team Inbrief
9:30 am – 12 noon
Agree on schedule for focus area interviews
(complete Table 3-3) and begin focus area
interviews
12 noon – 1 pm Lunch
1 pm – 5 pm Site Tour
Document Reviews/Focus Area Interviews
2-3 Nov 29-30 TBD 8 am – 5 pm Document Reviews/Focus Area Interviews
4-5 Dec 1-2 Offsite 8 am – 5 pm
6-8 Dec 3-5 TBD 8 am – 5 pm Document Reviews, Focus Area Interviews,
Report Preparation
9 Dec 6 TBD
8 am – 12 noon Report Preparation; Out-brief Preparation
1 pm – 3 pm Out-brief Preparation
3 pm – 4 pm Outbrief
The OECM Representative, EIR Team Lead, and FPD will meet at the end of each day to discuss potential high-
level issues regarding the Project and to identify what additional documents or interviews may be required for the
EIR Team to complete their task. Because the EIR will still be in progress and the EIR Team will not have had
enough time to synthesize all the information gathered, the discussion elements are understood to be preliminary
indicators but do not necessarily reflect the end conclusions of the EIR Team or the preliminary findings to be
presented at the closeout briefing.
Section 43
Appendix D DOE G 413.3-9
D-22 9-23-08
Table 3-2
Focus Area Interview Schedule
Item No. Review Area EIR Team Participants Project Participants Date Time Place
1 Work Breakdown Structure
(Basis of Scope) • • • • •
2 Resource Loaded Schedule
(Basis of Cost) • • • • •
3 Resource Loaded Schedule
(Basis of Schedule) • • • • •
4 Funding Profile and Budget • • • • •
5 Critical Path • • • • •
6 Risk Management • • • • •
7 Hazards Analysis/Safety • • • • •
8 Systems Functions and
Requirements • • • • •
9 Basis of Design • • • • •
10
Preliminary Design, Design
Review and Comment
Disposition
• • • • •
11 Value Management/
Engineering • • • • •
12 Project Controls/Earned
Value Mgmt System • • • • •
13 Acquisition Strategy • • • • •
14 Project Execution Plan • • • • •
15 Integrated Project Team • • • • •
16 Operations Readiness • • • • •
17 Quality Assurance/ Quality
Control
• • • • •
18 Safeguards and Security • • • • •
3.3 Review Process
The EIR Team will analyze Project documentation and interview information and compile a
draft EIR report that will document major findings, findings, observations, and associated
recommendations. The EIR Team will structure the EIR report around the review areas
contained in Section 1.3 of this document. The report will contain appendices as required,
including a listing of documents reviewed, summary resumes of the EIR Team, and a corrective
actions plan (CAP) shell that contains a complete listing of the recommendations associated with
major findings and findings.
DOE G 413.3-9 Appendix D
9-23-08 D-23 (and D-24)
Prior to the site visit, the EIR Team will determine whether the project baseline documentation is
sufficiently complete to conduct a meaningful EIR. The Team leader will provide his
determination in writing to the Contracting Officer’s Representative (COR) and the Office of
Engineering and Construction Management (OECM). The recommendation may be to proceed
as planned, conduct a partial review, or suspend the review.
If the determination is to proceed with the EIR, the EIR Team will conduct desktop reviews of
documents until the start of the site visit. At the end of the site visit a copy of the out brief will
be left with Project officials. After issuance of the draft EIR Report including CAP shell and
completion of the factual accuracy review by the Project Team, the EIR Team submit the final
draft report to OECM for acceptance. OECM, with the assistance of the EIR Team, will review
responses to the corrective action plan until the Major Findings and Findings have been
satisfactorily addressed to support validation of the performance baseline.
These milestones are summarized below.
• Draft EIR Review Plan October 19, 2007
• Receipt of Project Materials for Sufficiency Review November 9, 2007
• Final EIR Review Plan November 14, 2007
• EIR Team Desktop Review of Documents November 9-27, 2007
• On-Site Review November 28 – December 6,
2007
• Draft EIR Report including CAP shell December 6, 2007
• Factual Accuracy Review by Project Team December 7-10, 2007
• Final EIR Report (early finish) December 14, 2007
3.4 Report Distribution (after OECM approval)
OECM (12)
NETL, COR (2)
DOE G 413.3-9 Appendix D
9-23-08 D-25
Section 4 – Team Members and Assignments
4.1 Review Team Assignments
Section 44
The EIR Team members and their principal areas of focus for the reviews or the NMSSUP II are
shown in the table below. Team member biographies are also provided.
Table 4-1: Review Team Assignments
No. Review Area Name*† Name Name**† Name Name†
* Team Lead | ** Cost Lead | † “Q” cleared
1
Work Breakdown
Structure (Basis of
Scope)
2 Resource Loaded
Schedule (Basis of Cost)
3
Resource Loaded
Schedule (Basis of
Schedule)
4 Funding Profile and
Budget
5 Critical Path
6 Risk Management
7 Hazards Analysis/Safety
8 Systems Functions and
Requirements
9 Basis of Design
10
Preliminary Design,
Design Review and
Comment Disposition
11 Value Management/
Engineering
12 Project Controls/Earned
Value Mgmt System
13 Acquisition Strategy
14 Project Execution Plan
15 Integrated Project Team
16 Operations Readiness
17 Quality Assurance/
Quality Control
18 Safeguards and Security
L – Lead; S – Assist
Appendix D DOE G 413.3-9
D-26 9-23-08
4.2 Biographies of EIR Team
List names with biographies and specialty areas as applicable to the functional areas assigned in
the Review Plan.
Appendix A – Information Requested
Item
No. Review Area Information Requested
1 Work Breakdown Structure
• WBS to at least the Project control level
(consistent with numbering system shown in
the cost estimate and project schedule
documentation)
• WBS Dictionary (definitions and responsible
parties for all WBS numbers)
2 Resource Loaded Schedule (Basis of Cost)
• Project cost estimate and bases including
• Activity cost and man hours
• Staffing requirements showing discipline,
activity performed, wage rates, and man-hours
allotted for each task/activity
• Estimates/quotes for procured products and/or
services
• Analyses, calculations and basis/rational used
for developing escalation cost
• TPC, TEC and OPC totals
• Major cost totaling to the TEC cost and cost
totaling to the OPC cost
• Summary and backup for the major cost totals
• Summary and backup for the level 4 costs
• Independent Cost Estimate Report
• Resource loaded schedule (Primavera P3 or
equivalent) showing corresponding WBS
element numbers to level 4 minimum
• Management reserve and basis including
analyses and calculations
• Contingency and basis including analyses and
calculations
• Drawings and specifications, i.e., current
(preliminary or final) drawings and
specifications for Civil, Structural, Architectural,
Mechanical, Electrical, Special Systems and
Special and Standard Equipment including,
specifically, site plan with contours, floor plans,
elevations, buildings cross section, mechanical
equipment list & plan with ductwork, electrical
equipment list & location plan and special &
standard equipment list & location
3 Resource Loaded Schedule (Basis of
Schedule)
• Project schedule and associated assumptions
and bases, milestone list
• Project schedule native files
4 Funding Profile and Budget • Latest Construction Project Data Sheet
DOE G 413.3-9 Appendix D
9-23-08 D-27
Item
No. Review Area Information Requested
including funding profile and yearly
financial/obligation costs
• Project annual cost projections by funding
category
• Latest NNSA Integrated Construction Program
Plan (ICPP) excerpt for the Project
5 Critical Path
• Critical path schedule with float identified
• Duration or float between physical completion
and CD-4
6 Risk Management
• Contractor risk management process
• Project risk management plan
• Project risk assessment documentation
• Project risk watch list
• Correlation of risks to Project cost and
Section 45
schedule management reserve and
contingency
• Monte Carlo risk analysis at 50-95 confidence
levels
7 Hazards Analysis/Safety
• Contractor hazard analysis process
• Project hazard analysis documentation
• Project hazard analysis integrated project team
• Identification of safety structures, systems, and
components including safety class and safety
significant systems
8 Systems Functions and Requirements
• Mission Need Statement
• Systems functions and requirements document
• Table(s) of CD-4 requirements and key
performance parameters
• Facility design description
• System design descriptions
• Identification of permits, licenses and
regulatory approvals required and NEPA
checklist
9 Basis of Design • Design criteria
• Design parameters and there bases
10 Preliminary Design, Design Review and
Comment Disposition
• Preliminary design drawings and specifications
• Exceptions to design and specifications by
potential construction contractors, if contacted
• Project Design Review Team
• Design review comment disposition process
• Design review comments, responses, and
disposition records and impact of design
review comments on drawings
11 Value Management/ Engineering
• Project value management process and value
management team
• Value Management Assessment (DOE M
Appendix D DOE G 413.3-9
D-28 9-23-08
413.3-1, Section 2.2.1)
• Value management/engineering studies
• Life cycle cost analysis
12 Project Controls/Earned Value Mgmt
System
• Project control system description
• EVMS certification, if achieved, or planned
date for certification
• Interface control documents
• Change control process
13 Acquisition Strategy • Project approved Acquisition Strategy
document
14 Project Execution Plan (PEP) • Current PEP including current summary
Project cost and milestone tables
15 Integrated Project Team (IPT)
• Federal IPT Charter and membership list
• Federal IPT organizational diagram, roles and
responsibilities, and operating processes
• LANS project management organization and
plan
16 Operations Readiness
• Project Startup Test Requirements
• Project Startup Test Plan
• Readiness Assessment or Operational
Readiness Review Plan
17 Quality Assurance/ Quality Control
• Project Quality Assurance Plan
• Project implementing QA procedures
• QA/QC requirements for construction
18 Safeguards and Security • Preliminary Security Vulnerability Assessment
Report
DOE G 413.3-9 Appendix E
9-23-08 E-1 (and E-2)
Appendix E: Shell Independent Project Review Plan
DOE G 413.3-9 Appendix E
9-23-08 E-3 (and E-4)
REVIEW PLAN
INDEPENDENT PROJECT REVIEW
In Preparation for
Critical Decision-«CDX» (CD-«CDX»)
«ReviewType»
«Title» («TitleAcronym»)
Project No. «ProjectNum»
at
«Site» («SiteAcronym»)
«ReviewDate»
«DateofDocument»
Approved by:
Office of Project Management and Systems Support, NA-54
DOE G 413.3-9 Appendix E
9-23-08 E-5 (and E-6)
INDEPENDENT PROJECT REVIEW
In Preparation for
Critical Decision-«CDX» (CD-«CDX»)
«ReviewType»
«Title» («TitleAcronym»)
Project No. «ProjectNum»
at
«Site» («SiteAcronym»)
TABLE OF CONTENTS
(Note: Table of Contents left blank intentionally; this is a sample template document)
DOE G 413.3-9 Appendix E
9-23-08 E-7
INDEPENDENT PROJECT REVIEW
In Preparation For
Critical Decision-«CDX» (CD-«CDX»)
«ReviewType»
«Title» («TitleAcronym»)
Project No. «ProjectNum»
At
«Site» («SiteAcronym»)
1.0 BASIS FOR REVIEW
<<pick one>>
CD-0
Section 46
The «Office» «Office1» has requested that a Mission Validation «TailoredFull» Independent
Project Review (IPR) be performed in preparation for CD-0, «ReviewType», of «Title»,
«ProjectNum» at «SiteAcronym». Approval of CD-0 constitutes approval to proceed with
Conceptual Design and a request for Project Engineering and Design (PE&D) funds for the
Preliminary and Final designs.
CD-1
The «Office» «Office1» has requested a «TailoredFull» Independent Project Review (IPR) of
documents produced during the Conceptual Design prior to approving proceeding to Preliminary
Design and approving CD-1, «ReviewType». Approval of CD-1 allows for the expenditure of
Project Engineering and Design (PE&D) funds for design.
CD-2
The «Office» «Office1» has requested a «TailoredFull» Independent Project Review (IPR) of
documents produced during the Preliminary Design prior to approving proceeding to Final
Design and approving CD-21, «ReviewType». CD-2 establishes a Performance and Budget
Baseline for the Project. It allows the design to continue and is required for the request of
constructions funds.
CD-3
The«Office» «Office1» has requested an Execution Readiness Independent Project Review (IPR)
prior to CD-3, «TailoredFull» «ReviewType». This is a general review of the project prior to
CD-3 that verifies the readiness of the project to proceed into construction. The Project
Execution Plan (PEP) and performance baseline will be updated, if required, and the final design
and procurement packages are to be completed.
Appendix E DOE G 413.3-9
E-8 9-23-08
FIRP
In accordance with ongoing management initiatives of the Office of Infrastructure and Facilities
Management (NA-52), The Office of Engineering and Systems Support (NA-54) has been
requested to conduct a «TailoredFull» Independent Project Review (IPR) to determine if FIRP
projects at «SiteAcronym» are sufficiently baselined and that «SiteAcronym» has the capability
to execute them successfully.
To meet this request, the Office of Project Management and Systems Support, NA-54, will
conduct a «TailoredFull» IPR utilizing NNSA’s IPR procedures and infrastructure support.
The draft Independent Review Process for Construction Programs, National Nuclear Security
Administration (July 7, 2003, Draft) describes this review as:
<<pick one>>
Mission Validation IPR (Pre CD-0 Review)
A Mission Validation IPR is a review of the project prior to CD-0, Approve Mission Need. It
assures the project has clear objectives, strongly linked to mission; identifies major risks;
evaluates the acquisition and conceptual planning relative to those risks; and validates the
funding request.
Alternative Selection and/or Cost Range Review (Pre CD-1 Review)
The purpose of an Alternative Selection and/or Cost Range Review (previously a Readiness to
Proceed Into Preliminary (Title I) Design Review) is to examine in depth the readiness of the
Project to proceed with Title I Design and evaluates the planning for the design phase.
Performance Baseline Independent Project Review (IPR) prior to Critical Decision -2
IPRs are conducted for Capital Asset Projects under $20M prior to Critical Decision 2. This
requirement applies regardless of whether the project is capital or expense funded. An IPR
may be required to validate a new baseline resulting from a Baseline Change Proposal due to
a Performance Baseline Deviation. The purpose of the Performance Baseline IPR is to
support validation of the Performance Baseline and to provide reasonable assurance that the
project can be successfully executed. The Performance Baseline validation provides
confirmation to the Deputy Secretary, the Chief Financial Officer, OMB, and Congress that
the project scope and key performance parameters are well defined and the project can be
completed for the Total Project Cost and schedule associated with the Performance Baseline. I
Section 47
Execution Readiness IPR (Pre CD-3 Review)
An Execution Readiness IPR is a general review of the project that may range from an abridged
review of specific areas to a comprehensive review of the entire project. As a minimum, it must
verify the readiness of the project to proceed into construction or remedial action, and
evaluation of prospective procurement packages. NA-54 may elect to delegate IPR
DOE G 413.3-9 Appendix E
9-23-08 E-9
responsibility for projects in which the ESAAB authority for CD-3 resides in the field, if the
capability and processes exist for the proper execution of IPRs in the field.
Long Lead Procurement Review (Pre CD-3A Review)
A Long Lead Procurement (LLP) Review (CD-3A) may be conducted to determine whether
procurement of a long lead item is justified and whether the project is ready to proceed with the
requested procurement. The bases for implementing LLP Reviews are found in DOE Order
413.3A (7/26/06)
• DOE O 413.3A Chap. III.3.b: "Where long lead procurement is required, a tailored may be
used, subject to prior budget approval and funding availability."
• DOE O 413.3A Chap. III.3.c: "For long lead procurement, a separate budget request [BR]
for capital funds (non-PED) may be submitted prior to CD-2 for a partial CD-3
determination."
• DOE O 413.3A Attach. 6: "If long lead procurement (LLP) is required, a BR for LLP
funding should be approved as a partial CD-3 during the conceptual design phase and
submitted into the budget cycle to ensure timely receipt of LLP funds."
Procurement Package Review (A-E, Design-Build, or Construction)
A Procurement Package Review is conducted when the Project is ready to proceed with a major
procurement of engineering, construction, or design-build services.
Corrective Action Plan Closure Review
The purpose of a CAP Closure Review is to ensure that issues raised during prior reviews have
been adequately resolved, including: conditions which do not satisfy applicable Federal
regulations, DOE Orders, or agreements with regulatory agencies; actions that must be taken
before the Project can have a reasonable expectation of achieving its documented objectives.
This review generally addresses all previous reviews (EIR and IPR.)
When possible the CAP Closure Review should involve the Review Team Leader(s) of as many of
the past independent review(s) as possible.
Cost and/or Schedule Review
Cost and/or Schedule Reviews focus on the process used by the Project in preparing the cost
estimates and schedule. Cost and/or Schedule Reviews are generally conducted as a portion of
an overall Project Review; however, cost/schedule may also be the focus of a Review. The
Review Team will determine whether the Project has applied sound and accepted cost estimating
processes and whether they are likely to represent the actual cost/schedule. The Cost and/or
Schedule Review will also evaluate the schedule and scope to ensure consistency.
Appendix E DOE G 413.3-9
E-10 9-23-08
Cost Reviews should look at the Critical Decision being considered and the items that must be
addressed in that time frame, pursuant to DOE Cost Estimating Guide, DOE G 430.1, Chapter 6,
Table 6-1.
Ad Hoc (For Cause) Reviews
Ad Hoc (For Cause) Reviews may be requested by the Administrator, Deputy Administrator(s),
other NNSA AEs and Site Office Manager(s) or Program Managers, or the FPD with the
concurrence of the Program Office. The Review will be developed by the requesting Program
Office as well as the Review Team Lead to meet the specific needs of the requestor.
Section 48
Value Engineering Reviews
Value Engineering reviews and/or exercises are generally conducted as part of an overall
Project Review, however, value engineering may also be the focus of a Review. Value
Engineering Reviews evaluate the project to identify ways of improving performance, reliability,
quality, safety, and life cycle costs of products, systems, or procedures to achieve "best value". A
Value Engineering exercise may be conducted as part of an IPR or separately; however such an
exercise is not to be confused with a review of Value Engineering plans/implementations
conducted as part of a normal IPR. A full Value Engineering Review will include a Certified
Value Engineering Specialist (CVS).
System Reviews
The Administrator, Deputy Administrators, other NNSA Acquisition Executives, Program Office,
or the FPDs may request System Reviews. A System Review evaluates a project or projects to
determine the status of a system or systems at a site or within a particular organization.
Reviews Pursuant to a Charge Memorandum
The Administrator, Deputy Administrators, other NNSA Acquisition Executives, Program Office,
or the FPDs may request reviews with the pursuant to a Charge Memorandum. The Charge
Memorandum will identify the scope and focus of the Review and it will be tailored accordingly.
Capability Reviews
Capability reviews assess the systems, procedures, organizations, personal qualifications and
other institutional elements to determine the degree of organizational readiness to plan, manage
and execute projects.
Performance Reviews
Performance reviews of projects are conducted during the execution phase (i.e. post CD-3) to
analyze variances, forecasts, potential problems, etc…
DOE G 413.3-9 Appendix E
9-23-08 E-11
2.0 GENERAL REVIEW INFORMATION
2.1 Points of Contact and Logistical Information
This review will be conducted at «SiteAcronym» and «Walkdown_Willwont» require a
walkdown of the site or facility. The Review Team and FPD are requested to
review/follow/adhere to all Attachments for facilitation and coordination of this review.
NNSA Federal Program
POC
NNSA Site Office
FPD
NA-54 Review Interface and
Review Team Leader
NA-54 Review
Integrator
«FedProgamPOC» «FedProjectName» «IntegratorName»
«FedProgam_Tel» «Fed_Project_Tel» «IntegratorPhone»
«FedProgram_Email» «Fed_Project_Email» @nnsa.doe.gov «IntegratorEmail»
Review Team Members are requested to stay at the «Hotel» in «Hotel_City», «Hotel_State». The
Telephone number is «Hotel_phone». The Integrator has reserved a block of rooms for this
review. When you check in, please change
the reservation to your name. The confirmation number is _______. If you prefer to make your
own reservations, you can find a hotel that offers government rates at www.government-
traveler.com.
2.2 Documentation for Review
Documentation requested by the Review Team is listed in Attachment 2, Documentation
Required for Review. The FPD is required to return this form to NA-54 (Attachment 2), together
with requested documents, in accordance with the Review Plan Schedule. The FPD also is
required to comply with Attachment 5, Federal Project Director Responsibilities.
The Project is requested to directly email the Review information to the NA-54 Review
Interface and the Review Integrator. The Review Integrator will coordinate reviewer access to
the information.
Section 49
Advance documentation that cannot be emailed should be sent by the Project directly to each
Review Team Member identified in Section 4.0, pending classification issues. If documentation
cannot be sent to the Review Team Members for classification reasons, send a sufficient number
of copies for all Review Team Members to the Review Integrator. Send all documents by
overnight express.
2.3 Preliminary Review Schedule
Date Activity
Pre-Review
<<Insert Date>> Advance Historical Documentation distributed by NA-54
<<Insert Date>> Review Documentation distributed by Federal Project Director;
PDRI Self-Assessment provided to Integrator
<<Insert Date>> Review Team only Conference Call 10:00 am EST
Call in #: TBD
Appendix E DOE G 413.3-9
E-12 9-23-08
Day 1-On-Site «ReviewDate»
7:00 am local time - Meet in lobby of hotel for breakfast team
meeting
7:45 am – Meet at Badge Office for check in
8:15 am – Project Team Overview Presentation to Review
Team
PM Interviews and Discussions
Day 2-On-Site <<Insert Date>> 8:00 am – Review Team meeting in Conference Room
PM Proposed Exit Briefing by Review Team
Post-Review
«DateofDocument» Factual Accuracy Draft issued to FPD and Program
TBD Factual Accuracy Comments Received
Within one week of
comments
Final Report with Corrective Action Plan Cap Shell
Issued
On or Before
«DateofDocument» Review Team Leader de-briefs A/E
Date Activity
Pre-Review
<<Insert Date>> Review Documentation distributed by Federal Project Director;
PDRI Self-Assessment provided to Integrator
<<Insert Date>> Review Team only Conference Call 10:00 am EST
Call in #: TBD
Day 1-On-Site «ReviewDate»
7:00 am local time - Meet in lobby of hotel for breakfast team
meeting
7:45 am – Meet at Badge Office for check in
8:15 am – Project Team Overview Presentation to Review
Team
PM Interviews and Discussions
Day 2-On-Site <<Insert Date>> 8:00 am – Review Team Meeting in Conference Room
8:15 am - Interviews and Discussions with Project
Day 3-On-Site <<Insert Date>> 8:00 am – Review Team Meeting in Conference Room
PM Proposed Exit Brief by Review Team
Post-Review
«DateofDocument» Factual Accuracy Draft issued to FPD and Program
TBD Factual Accuracy Comments Received
Within one week of
comments Final Report with Corrective Action Plan Cap Shell Issued
On or Before
«DateofDocument» Review Team Leader de-briefs A/E
Date Activity
Pre-Review
<<Insert Date>> Review Documentation distributed by Federal Project Director;
PDRI Self-Assessment provided to Integrator
<<Insert Date>> Review Team only Conference Call 10:00 am EST
Call in #: TBD
Day 1-On-Site «ReviewDate»
7:00 am local time - Meet in lobby of hotel for breakfast team
meeting
7:45 am – Meet at Badge Office for check in
8:15 am – Project Team Overview Presentation to Review
Team
PM Interviews and Discussions
Day 2-On-Site <<Insert Date>> 8:00 am – Review Team Meeting in Conference Room
8:15 am - Interviews and Discussions with Project
DOE G 413.3-9 Appendix E
9-23-08 E-13
Day 3-On-Site <<Insert Date>>
8:00 am – Review Team Meeting in Conference Room
8:15 am - Interviews and Discussions with Project
PM – Review Team Meeting in Conference Room
Day 4-On-Site <<Insert Date>> 8:00 am – Review Team Meeting in Conference Room
PM Proposed Exit Briefing by Review Team
Post-Review
«DateofDocument» Factual Accuracy Draft issued to FPD and Program
TBD Factual Accuracy Comments Received
Within one week of
comments Final Report with Corrective Action Plan Cap Shell Issued
Section 50
On or Before
«DateofDocument» Review Team Leader de-briefs A/E
Date Activity
Pre-Review <<Insert Date>> Review Documentation distributed by Federal Project Director;
PDRI Self-Assessment provided to Integrator
Day 1-On-Site «ReviewDate»
7:00 am local time - Meet in lobby of hotel for breakfast team
meeting
7:45 am – Meet at Badge Office for check in
8:15 am – Project Team Overview Presentation to Review
Team
PM Interviews and Discussions
Day 2-On-Site <<Insert Date>> 8:00 am – Review Team Meeting in Conference Room
8:15 am - Interviews and Discussions with Project
Day 3-On-Site <<Insert Date>> 8:00 am – Review Team Meeting in Conference Room
8:15 am - Interviews and Discussions with Project
Day 4-On-Site <<Insert Date>>
8:00 am – Review Team Meeting in Conference Room
8:15 am - Interviews and Discussions with Project
PM – Review Team Meeting in Conference Room
Day 5-On-Site <<Insert Date>> 8:00 am – Review Team Meeting in Conference Room
PM Proposed Exit Brief by Review Team
Post-Review
«DateofDocument» Factual Accuracy Draft issued to FPD and Program
TBD Factual Accuracy Comments Received
Within one week of
comments Final Report with Corrective Action Plan Cap Shell Issued
On or Before
«DateofDocument» Review Team Leader de-briefs A/E
Not more than five days following receipt of factual accuracy comments, NA-54 will issue the
Final Report to the FPD and Program Officer with a Corrective Action Plan (CAP) shell.
3.0 REVIEW FOCUS AREAS AND LINES OF INQUIRY
The review will cover the following focus areas utilizing a graded approach tailored to the
Project. The Project is requested to address all these focus areas in its Kick-off Overview
Presentation and assign Project Team POCs. The numbers below are to be used by the Reviewers
in their write-ups (see Attachment 6, Exhibit 1).
Delete or add as many as required
3.1 Mission Need and Project Goals
Appendix E DOE G 413.3-9
E-14 9-23-08
3.2 Management Systems, Controls, and Planning
3.3 Acquisition Strategy
3.4 Safeguards and Security
3.5 Scope and Technical Considerations
3.6 Cost Estimates and Funding
3.7 Schedule
3.8 Risk and Contingency Management
3.9 Environment, Waste Management and Energy Conservation
3.10 Occupational Safety and Health
3.11 Nuclear Safety
3.12 Waste Minimization, Energy Conservation, and Pollution Prevention
3.13 Value Engineering
3.14 Quality Assurance/Quality Control
3.15 Evaluation of Corrective Actions from Previous Reviews
Review Focus Areas are listed above while the specific Lines of Inquiry for these focus areas are
listed in Attachment 1. The Reviewers shall, by reading documentation and/or discussions with
Project personnel, evaluate the Focus Areas using the Lines of Inquiry as a guide. The
evaluations shall be recorded in the IPR Report as findings: Significant Concerns, Other
Concerns and Observations in accordance with Section 5.1.
4.0 REVIEW TEAM
4.1 Team Members and Focus Areas
NAME AFFILIATION EMAIL PHONE LEADER FOR WHICH FOCUS
AREA
Review Team Leader
Team Leader
Other Review Team Members
DOE G 413.3-9 Appendix E
9-23-08 E-15
4.2 Review Team Responsibilities
The Review Team is requested to follow the guidelines for Review Team Responsibilities and
Review Team Leader Responsibilities in Attachments 3 and 4, respectively.
5.0 REVIEW REPORT
5.1 Definitions
Independence
During the formulation of Independent Project Review Teams, the Independence of the Review
Team members must be maintained. Two independence standards must be utilized, one for the
Review Team Leader and a slightly less rigorous standard for the remaining Team members.
Section 51
Team Leader -For qualifications as an NNSA Independent Review Team Leader or Chair of a
Technical Independent Project Review, an individual can have no present or prior participation
in the project to be reviewed. Participation means direct responsibility for or assignment to a
given project team, including NNSA, other Federal and state agencies, contractors and sub-tier
contractors. Team Leaders may not review projects from their current line program [Deputy and
Associate Administrators] or field site.
Review Team Members - To qualify as a member of a Review Team or Committee, an
individual can have no current involvement in the project to be reviewed. In addition to a
personal standard, the organization to which an individual is currently assigned cannot be a
participant in the project. Organization is defined to be a corporation, non-profit entity, state or
Federal agency, laboratory, or NNSA program/project office (at the Deputy and Associate
Administrators and level). Headquarters program personnel may participate as observers or in
limited non-critical roles.
Other exclusion criteria may apply:
• An individual or the organization to which he/she belongs, has a relationship to the
project being reviewed which would cause, or could be perceived to cause, them to be
biased in their assessment of the project.
• An individual is a member of a corporation which is an active competitor to the
corporation performing the project which is being reviewed.
Appendix E DOE G 413.3-9
E-16 9-23-08
In matters of judgment, the bias shall be towards erring on the side of conservatism in order to
ensure the integrity of the review process. That is, the bias shall be to exclude individuals and
entities which may have the potential to have a conflict of interest.
In cases of dispute, the decisions of the Review Team Leader, in consultation with the Director,
Office of Project Management and Systems Support shall make a determination. In extreme
cases where there is a disagreement, the decision may be appealed to the Associate
Administrator of Infrastructure and Environment, whose decision shall be final. In some cases, it
may be necessary to document the basis for inclusion/exclusion of members of the Review
Team.
Findings
The IPR results will be classified into four (4) categories: Significant Findings (also known as
Significant Concerns), Other Concerns, Opportunities for Improvement and Positive
Observations.
Significant Findings or Significant Concerns (SC): A Significant Concern (SC) represents a
finding that, in the opinion of the Review Team, needs to be addressed by the Acquisition
Executive prior to approval of the pertinent Critical Decision. In cases where NA-54 is
responsible for validation of the Performance Baseline (i.e. CD-2 for projects less than $100M),
the actions taken to address SCs will require concurrence by NA-54. The actions to be taken to
address SCs must be documented in the Corrective Action Plan.
In general, SCs have the potential to significantly impact the cost, schedule, or scope of the
project or potentially have a significant impact on safety or security. There should be a minimal
number of SCs (never more than 10, and normally 3-6). Resolution of the SCs requires the
direct involvement of the AE as part of the ESAAB/ ESAAB-equivalent approval process. In the
case where the Review Team has numerous such findings, the Project is likely not ready for
an IPR and there should be an overarching SC which so states and provides examples of why
additional preparation is needed. SCs can be rolled up to reflect a common finding of a similar
deficiency by the Review Team (e.g. an IPT may require additional expertise -- each skill area
would not be a separate SC).
Section 52
The following criteria are consistent with DOE O 413.3A and will be applied to determine
whether or not a finding is a Significant Concern. In the past, Lessons Learned from historic
projects show the SC has resulted from one of the following criteria:
• An increase in excess of the lesser of $25M or 25% (cumulative) of the original CD-
2 cost baseline,
• A delay of six-months or greater (cumulative) from the original project completion
date, or
• A change in scope that affects the ability to satisfy the mission need, an inability to
meet a Key Performance Parameter, or non-conformance with the current approved
Project Execution Plan.
DOE G 413.3-9 Appendix E
9-23-08 E-17
Other than DOE O 413.3 a Significant Concern could describe a condition that:
• Will potentially result in a significant release to the environment, human exposure to
a radiological or toxic substance, or a significant accident/injury
• Is a significant deviation from the DOE Order 413.3A or other DOE Order
requirements or is not in compliance with Federal, state or local regulations
• Could result in a breach of security that could put the asset at risk
The SCs shall be satisfactorily resolved prior to conducting an ESAAB/ESAAB Equivalent. For
projects with TPC of $20-100M a Performance Baseline Validation IPR and an ICE or an ICR
by NA-54 is required. According to DOE O 413.3A, Program and Project Management for the
Acquisition of Capital Assets, July 28, 2006, the Project Management Support Office (NA-54)
must issue a Performance Baseline Validation Letter to the Program Secretarial Officer that
describes the cost, schedule, and scope being validated thus, requiring concurrence of corrective
actions prior to the ESAAB. Significant findings from all IPRs/T-IPRs must be addressed at the
ESAAB/ESAB-Equivalent meeting. If there is a disagreement between the Project Team and the
Review Team on the resolution of a Significant Finding, the finding can be taken to the
Acquisition Executive for final disposition.
Other Concerns (OC): Any finding, in the opinion of the Review team, which if
unresolved, could pose a risk to the successful completion of the project within the
established baseline or reported cost and schedule range estimate. (i.e. CPDS, cost, scope, and
schedule). The resolution of the OCs is not necessarily required prior to the next Critical
Decision but should be addressed in the Corrective Action Plan.
Opportunities for Improvement (OFI): Recommendations by the Review Team in areas
where project enhancements could occur that could yield improvements in the overall project
performance and execution. OFI typically yield the most effective results if considered prior to
the next Critical Decision.
Positive Observations (PO): Positive Observations (PO): Observations of Project activities
that in the judgment of the Review Team demonstrate a best practice, proactive implementation
of requirements, or where the basic expectations and requirements have been exceeded. The POs
will be included in the NNSA NA-54 Bulletin and the NA-54 Lessons Learned Database for
distribution to all NNSA Site Offices and Program.
As soon as a Team Member identifies a deficiency that he or she perceives should be elevated to
a Significant Concern, he or she will identify that concern to the Focus Area Lead, who, in turn,
will provide the input to the Review Team Leader. The Team Member will prepare a brief
summary of the concern and be prepared to discuss the concern at the daily Review Team status
meetings.
Section 53
If Team agreement is reached on a Significant Concern, the Team Member will prepare a
complete discussion and Recommendation for the Significant Concern for inclusion in the final
Appendix E DOE G 413.3-9
E-18 9-23-08
report and in the Exit Briefing. The proposed Recommendation and written discussion also
requires review and consensus by the entire Team.
Team members will generate Observations reflecting their particular area of expertise within the
Focus Area to which they have been assigned. Team Members will document these Observations
and any Recommendations, as appropriate, as soon as they have developed them and will then
submit them to the Focus Area Lead. The Focus Area Lead will review these Observations and
share them with other reviewers for information and possible applicability to particular activities
that they may be reviewing.
The Exit Briefing, performed on the last day of the review, has a slightly different format than
the final report. Only those Observations that are deemed Notable Achievements will be included
in the Exit Briefing, but not the report. All other observations will be contained only in the
report. The Exit Briefing also will contain Significant Concerns and Other Concerns, but will not
contain Recommendations.
5.2 Reports and Corrective Action Plan (CAP)
In accordance with the schedule listed in Section 2.3, the Review Team will provide a Factual
Accuracy Report to the FPD and Program Officer. After receipt of factual accuracy comments
from the FPD, NA-54 will issue a final report which will include a draft CAP Shell. NA-54 will
coordinate the issuance of all reports. The CAP shell can be used by the Project to organize and
document their responses to the report Recommendations. It is the FPD’s responsibility to ensure
that all Recommendations in the CAP shell are addressed and that NA-54 receives a copy of the
completed CAP. It also is the FPD’s responsibility to update the PARS database once the Final
Report has been issued.
6.0 GENERAL LINES OF INQUIRY
There are many reasons that a project might fail to meet its objectives or fulfill its mission. Some
are beyond the Project’s control - market forces, funding cuts, extreme complexity, policy
changes, etc. Some reasons are common to a wide variety of projects, regardless of the stage of
design or completion they are in. These potential problems may be project-specific, site-specific
or systemic to NNSA.
There are certain indicators that can be used to assess the overall likelihood that a particular
project might become a victim of common shortcomings. In Attachment 1 are the Lines of
Inquiry that are pursued at each Critical Decision, organized by Focus Area. Figure 1, however,
is a Project Measures of Success Checklist that each Reviewer should complete, regardless of the
Critical Decision point at which the IPR is performed.
The checklist in Figure 1 can help to identify overall weakness in the Project or supporting
management and assist Project or Program managers in averting problems before they grow to
become threats to a Project’s success.
This checklist documents the general impressions of each Reviewer as to the overall health of a
project. Thus, Figure 1 is a checklist that must be completed by each Reviewer and a copy
DOE G 413.3-9 Appendix E
9-23-08 E-19
provided to the Review Team Leader prior to the Exist Briefing. Because the answers are based
on opinion, no supporting documentation is required.
7.0 PROJECT DEFINITION RATING INDEX (PDRI)
Section 54
The Project Team should perform a self-assessment using the PDRI scoring sheets and send the
completed form to the Integrator prior to the on-site review. Each Reviewer will evaluate the
Project before leaving the site on the PDRI scoring sheets that will be distributed to the Review
Team prior to the Exit Briefing. Instructions as to the proper way to complete the forms will be
provided by the Integrator at the time the forms are distributed. The completed forms will be
handed in to the Integrator before the Reviewer leaves the site. The Integrator will analyze the
data and include it in the final report. The Independent Reviewer score will be used to verify the
self-assessment and determine whether or not the Project score meets or exceeds the
recommended threshold for the appropriate level of maturity.
Note to Reviewers: Review Project documents as soon after you receive them as possible. Alert
the Team Leader or the Integrator to any critical information is missing or
incomplete as soon as you discover it.
Appendix E DOE G 413.3-9
E-20 9-23-08
1 = Strongly Agree
5 = Strongly Disagree
Don’t Know or
Insufficient
Information to
Judge
Project Measures of Success
These have been found to be the top reasons for project failures. Prior to the Exit Briefing, form a
general impression as to the condition of the Project and its ultimate likelihood of success (not just for
this CD). Then complete the following checklist by circling the answer that most closely represents your
impression.
1 2 3 4 5 1. There was adequate pre-project planning and definition of
project requirements and assumptions are clearly stated.
1 2 3 4 5 2. DOE has appropriately retained its “ownership” role relative to
the M&O contractor.
1 2 3 4 5 3. The alternative analysis is robust and the alternative selection is
clearly supported by objective criteria from the analysis.
1 2 3 4 5 4. The IPT is well-staffed and engaged.
1 2 3 4 5 5. The next project phase is sufficiently defined for decision-
making.
1 2 3 4 5 6. The risk assessment is rigorous, comprehensive, and is used to
allocate project resources.
1 2 3 4 5 7. The Mission Need is linked to the Strategic Goals.
1 2 3 4 5 8. The facility start-up process is sufficiently planned and
documented.
1 2 3 4 5 9. The design is matured to the appropriate phase of the project
and/or the project is starting construction with a complete design.
1 2 3 4 5 10.There is no need for more Headquarters oversight/advocacy in
order for this Project to succeed.
1 2 3 4 5 11. There are no TEC vs. OPC binning concerns.
1 2 3 4 5 12.There is no project history of major cost escalation or schedule
slippage.
1 2 3 4 5 13.The Project has applied lessons learned from similar projects at
other sites to avoid common pitfalls.
1 2 3 4 5 14. The budget is integrated and linked (timing of
funds/appropriations, Critical Decisions, PDS, etc.)
1 2 3 4 5
15. The cost and schedule estimates are not overly-optimistic and
there is an independent DOE/NNSA cost estimate that confirms
this based on actual costs and/or cost models.
1 2 3 4 5 16. The project has resolved any safety issues that could affect cost
or schedule.
1 2 3 4 5 17. Project staff has sufficient and appropriate experience to
perform all aspects of the project.
Section 55
1 2 3 4 5
18. The contracting strategy and execution provide sufficient risk
allocation, accountability, and incentives to both Federal and
Contractor entities.
1 2 3 4 5
19. Market forces, changing requirements and potential materials
cost escalation and availability are taken into account in the budget
and schedule.
Site: Reviewer: Date:
DOE G 413.3-9 Appendix E
9-23-08 E-21 (and E-22)
LIST OF SUPPLEMENTAL MATERIALS
Note: Attachments and Exhibit 1 are not included herein
ATTACHMENT 1 - SPECIFIC LINES OF INQUIRY
CRITICAL DECISION 0 - APPROVE MISSION NEED
CRITICAL DECISION 1 - APPROVE ALTERNATIVE SELECTION AND COST RANGE
CRITICAL DECISION 2 - APPROVE PERFORMANCE BASELINE
CRITICAL DECISION 3 - APPROVE START OF CONSTRUCTION
ATTACHMENT 2 - DOCUMENTATION REQUIRED FOR REVIEW
ATTACHMENT 3 - REVIEW TEAM RESPONSIBILITIES
ATTACHMENT 4 - REVIEW TEAM LEADER RESPONSIBILITIES
ATTACHMENT 5 - FEDERAL PROJECT DIRECTOR RESPONSIBILITIES
ATTACHMENT 6 - IPR STYLE GUIDE FOR REVIEWERS
EXHIBIT 1 – REVIEWER DELIVERABLE FORM