DOE G 413.3-8, Environmental Management (EM) Cleanup Projects
Functional areas: Environmental Management, Program Management, Project Management
The guide supports DOE O 413.3A, Program and Project Management for the Acquisition of Capital Assets, and provides guidance on environmental management cleanup projects. Canceled by DOE N 251.105.
Superseded By:
DOE N 251.105, Cancellation of Directives on Jun 23, 2011
Version history and related documents
Superseded by
A newer version replaces this document.
- DOE N 251.105Cancellation of Directives (Jun 23, 2011)
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
AVAILABLE ONLINE AT: INITIATED BY:
www.directives.doe.gov Office of Environmental Management
DOE G 413.3-8
9-24-08
ENVIRONMENTAL MANAGEMENT (EM)
CLEANUP PROJECTS
[This Guide describes suggested nonmandatory approaches for meeting requirements.
Guides are not requirements documents and are not to be construed as requirements in
any audit or appraisal for compliance with the parent Policy, Order, Notice, or Manual.]
U.S. Department of Energy
Washington, D.C. 20585
NOT
MEASUREMENT
SENSITIVE
DOE G 413.3-8 i (and ii)
9-24-08
FOREWORD
This Department of Energy (DOE) Guide is for use by Environmental Management Program
Offices. This guide intends to provide approaches for implementing the project management
process in accordance with DOE O 413.3A, Program and Project Management for the
Acquisition of Capital Assets, dated 7-28-06. DOE Guides, which are part of the DOE Directives
System, provide supplemental information for fulfilling requirements contained in rules,
regulatory standards, and DOE directives. Guides describe a suggested non-mandatory approach
for meeting requirements. Guides are not requirements and are not to be construed as
requirements in any audit or appraisal for compliance with the parent Policy, Order, Notice, or
Manual. This guide does not establish or invoke new requirements nor is it a substitute for
requirements.
DOE G 413.3-8 iii
9-24-08
TABLE OF CONTENTS
1.0 PURPOSE ...........................................................................................................................1
2.0 SCOPE ....................................................................................................................2
2.1 ENVIRONMENTAL MANAGEMENT PROJECT BASELINE SUMMARIES ....................2
2.2 DEACTIVATION AND DECOMMISSIONING PROJECTS .............................................3
2.3 SOIL GROUNDWATER REMEDIATION PROJECTS ...................................................3
2.4 STABILIZATION AND DISPOSITION PROJECTS ........................................................4
3.0 EM PROJECT REQUIREMENT OVERVIEW ............................................................5
3.1 EM PROJECT MANAGEMENT PRINCIPLES .............................................................5
3.1.1 Critical Decisions .........................................................................................5
3.1.2 Baseline Development .................................................................................7
3.1.3 Performance Baseline ................................................................................11
3.1.4 Risk ............................................................................................................13
3.1.5 Contingency ...............................................................................................15
3.1.6 Reviews [External Independent Reviews (EIR) and Independent Project
Reviews (IPR)]...........................................................................................25
3.1.7 Quality Assurance (QA) ............................................................................27
3.1.8 Integrated Safety Management System (ISMS) ........................................29
3.2 DEACTIVATION AND DECOMMISSIONING PROJECTS ...........................................30
3.2.1 Critical Decisions .......................................................................................32
3.2.2 Deactiviation and Decommissioning Engineering Activities ....................34
3.2.3 Baseline Development ...............................................................................34
3.2.4 Performance Measurement ........................................................................35
3.2.5 Waste Management for Deactivation and Decommissioning ....................35
Section 2
3.3 SOIL AND GROUNDWATER REMEDIATION PROJECTS ..........................................38
3.3.1 Critical Decisions .......................................................................................38
3.3.2 Supplemental Information .........................................................................40
3.3.3 Baseline Development ...............................................................................47
3.3.4 Performance Measurement ........................................................................47
3.4 STABILIZATION AND DISPOSITION ........................................................................48
3.4.1 Critical Decisions .......................................................................................48
3.4.2 Baseline Development ...............................................................................49
3.4.3 Performance Measurement ........................................................................49
4.0 ATTACHMENTS ............................................................................................................51
5.0 TERMS AND DEFINITIONS ........................................................................................51
6.0 REFERENCES .................................................................................................................54
iv DOE G 413.3-8
9-24-08
LIST OF FIGURES
Figure 1. Environmental Management Cleanup Projects Framework .................................. 6
Figure 2. Relationship of NTB and OPER in Project Life-cycle ............................................. 8
Figure 3: Project Scope Detail Improves as the Project Matures .......................................... 18
Figure 4: Conceptual Cost and Schedule Risk Analysis Process ............................................ 19
Figure 5: S-curve Representation of MR, EM Project, and EM Unfunded Contingency ... 20
Figure 6: Near Term Baseline vs Contract and Future Contract Period .............................. 21
Figure 7: Project Lifecycle Components ................................................................................... 21
Figure 8: Project Completion Confidence Levels at Specified Project Costs ........................ 24
Figure 9: MR and EM contingency relationship to the project baseline ............................... 24
Figure 10: Allocation of Schedule Contingency to Selected Schedule Milestones ................ 25
Figure 11. Example of a WBS Structure for Deactivation and ............................................. 37
LIST OF TABLES
Table 1. Acronyms ........................................................................................................................ v
Table 2. Environmental Management Corporate Key Performance Parameters ............... 12
Table 3. Critical Decision Targeted EM Cleanup Projects Definition Rating Index Scores
for Each Projects Type ....................................................................................................... 27
Table 4. Waste Planning ............................................................................................................ 36
Table 5. Cleanup Project - Phases, Requirements and Equivalent Project Management
Documentation .................................................................................................................... 43
Table 6. Cleanup Project - Phases, Requirements and Equivalent Project Management
Section 3
Documentation .................................................................................................................... 45
Table 7. Team Membership .......................................................................................................55
LIST OF ATTACHMENTS
Attachment 1-EM Cleanup Projects by Major Category and by Type of Project ............... 57
Attachment 2-Decommissioning Project Overview (CERCLA Non-time Critical) ............. 59
Attachment 3-Decommissioning Project Overview ................................................................. 61
Attachment 4-Soil and Groundwater RCRA/CERCLA Flow Process .................................. 63
Attachment 5-Stabilization and Disposition Project Overview .............................................. 65
DOE G 413.3-8 v
9-24-08
TABLE 1. ACRONYMS
ACWP Actual Cost of Work
Performed
AE Acquisition Executive
ANSI American National Standards
Institute
ASTM American Society for Testing
and Materials
BCWP Budgeted Cost of Work
Performed
BCWS Budgeted Cost of Work
Scheduled
CD Critical Decision
CDR Conceptual Design Report
CERCLA Comprehensive
Environmental Response,
Compensation and Liability
Act
CFR Code of Federal Regulations
CMP Corrective Measures Plan
CMS Corrective Measures Study
CP Contract Price
CX Categorical Exclusion
D&D Deactivation and
Decommissioning
DOE US Department of Energy
DQO Data Quality Objective
DSA Documented Safety Analysis
ECAS Environmental Cost Analysis
System
ECES Environmental Cost Element
Structure
EIA Electronic Industries
Association
EIR External Independent Review
EIS Environmental Impact
Statement
EM Environmental Management
EM-1 Office of Environmental
Management
EM-30 EM Program, Planning and
Budget
EPA US Environmental Protection
Agency
ER Environmental Restoration
ESH Environmental Safety and
Health
EVMS Earned Value Management
System
FDE Facility Decontamination
Evaluation
FFA Federal Facility Agreement
FPD Federal Project Director
FS Feasibility Study
FY Fiscal Year
G DOE Guide
GFSI Government Furnished
Services and Items
HASP Health and Safety Plan
HQ Headquarters
HSS Office of Health, Safety and
Security
ICE Independent Cost Estimate
IGCE Independent Government Cost
Estimate
IPABS Integrated Planning,
Accountability and Budget
System
IPR Independent Project Review
IPT Integrated Project Team
ISM Integrated Safety
Management
ISMS Integrated Safety
Management System
LCC Life Cycle Cost
LCCE Life Cycle Cost Estimate
LLW Low Level Waste
LOE Level of Effort
LTRA Long Term Response Action
LTS Long Term Stewardship
LUCIP Land Use Control
Implementation Plan
MARSSIM Multi Agency Radiation
Survey and Site Investigation
Manual
MR Management Reserve
MTHM Metric Tons of Heavy Metal
KPP Key Performance Parameter
vi DOE G 413.3-8
9-24-08
NEPA National Environmental
Policy Act
NFA No Further Action
NPL National Priorities List
NRC US Nuclear Regulatory
Commission
NTB Near Term Baseline
O DOE Order
OECM Office of Engineering and
Construction Management
OMB Office of Management and
Budget
OPER Out-year Planning Estimate
Range
OSHA Occupational Safety and
Health Administration
PA Preliminary Assessment
PARS Project Accountability and
Reporting System
PBCE Performance Baseline Cost
Estimate
PBS Project Baseline Summary
PCR Post Construction Report
PDRI Project Definition Rating
Index
PDSA Preliminary Documented
Safety Analysis
PEP Project Execution Plan
PMB Performance Measurement
Section 4
Baseline
QA Quality Assurance
QC Quality Control
RACR Remedial Action Completion
Report
RAIP Remedial Action
Implementation Plan
RAO Remedial Action Objectives
RAOR Risk Analysis and
Opportunity Report
RCRA Resource Conservation and
Recovery Act
RD Remedial Design
RFA RCRA Facility Assessment
RFI RCRA Facility Investigation
RFI/RI Remedial Facility
Investigation/Remedial
Investigation
RI Remedial Investigation
RMP Risk Management Plan
ROD Record of Decision
RSA/ORR Readiness Self
Assessment-Operational
Readiness Review
S&D Stabilization and Disposition
S&GW Soil and Groundwater
S&M Surveillance and Maintenance
SE Site Evaluation
SI Site Investigation
SSC Structures, Systems and
Components
SWMU Solid Waste Management
Unit
T&PRA Technical and Programmatic
Risk Assessment
TPC Total Project Cost
TRU Transuranic Waste
TS Treatability Study
TSCA Toxic Substances Control Act
TSR Technical Safety
Requirements
TYSP Ten Year Site Plan
VE Value Engineering
WAEP Work
Authorization/Execution Plan
WBS Work Breakdown Structure
WIPP Waste Isolation Pilot Plant
DOE G 413.3-8 1
9-24-08
1.0 PURPOSE
The purpose of this guide is to define how DOE O 413.3A is applied to Environmental
Management (EM) cleanup projects. It also delineates how the regulatory processes for the
Comprehensive Environmental Response, Compensation and Liability Act (CERCLA), the
Resource Conservation and Recovery Act (RCRA), Atomic Energy Act (AEA), and US Nuclear
Regulatory Commission (NRC) Decommissioning Plans fall into the Critical Decision (CD)
process. This guide lays out the framework for executing a cleanup project within the
DOE O 413.3A requirements, and supplements DOE O 413.3A by providing consistent project
management guidance for EM cleanup projects.
1.1 OBJECTIVES
The major objective of this guide is to provide guidance to the federal project director (FPD),
integrated project teams (IPTs), and Headquarters (HQ) program managers on nine unique
project types, which are described in Section 2.0, and associated regulatory processes that should
be included in the overall EM project management process. Other objectives include the
following:
• Recommend the integration methods essential to EM cleanup projects and the regulatory
drivers that have an impact on implementation of DOE O 413.3A. Regulatory drivers,
which are not explained in this guide, include RCRA, CERCLA, the National
Environmental Policy Act (NEPA), and the site specific Federal Facility Agreement (FFA).
[See references 6.7, (NEPA) and 6.6, (CERCLA, RCRA) for additional information.]
• Define the types of projects and the differences with regard to the Critical Decision (CD)
process and provide perspective on the way in which specific project management
deliverables and the CD process may vary.
• Differentiate between the application of DOE O 413.3A to EM cleanup projects for a
portion of (subset or subproject) or an entire project baseline summary (PBS). A PBS or
subproject may include operations and facility support activities such as surveillance and
maintenance.
• Address attributes of EM projects that are unique compared with traditional capital
construction projects for developing a project performance baseline. A key example of
this is the management of waste generated by the project. This guidance is needed
because the nature of similar functional activities varies considerably from traditional
capital construction projects. The EM project management goals for CD baseline
development, performance measurement, risk, contingency, reviews, Quality Assurance
and Integrated Safety Management (ISM) are highlighted in section 3.0 of this guide.
Section 5
See references 6.13 and 6.14 for additional information and expectations regarding
contingency.
2 DOE G 413.3-8
9-24-08
2.0 SCOPE
A PBS is an EM designated program scope that contains a logical grouping of work activities,
which are “projectized” through establishing technical scope, cost and schedule baselines;
defining performance metrics; and providing financial history, budget request justification and
other information such as programmatic risk and compliance drivers.
In most cases, EM defines a cleanup project as the entire PBS; however, a project may be a
portion of a single or multiple PBSs. EM is responsible for clearly defining the composition of
each project. The nine types of EM cleanup projects can be grouped into three major categories
of Deactivation and Decommissioning (D&D) (section 2.2), Soil and Groundwater Remediation
(S&GW) (section 2.3), and Stabilization and Disposition (S&D) (section 2.4) as follows:
• D&D
nuclear deactivation and decommissioning
non-nuclear deactivation and decommissioning
• S&GW Remediation
• S&D
radioactive liquid waste tank stabilization and disposition
nuclear materials stabilization and disposition
spent nuclear fuel stabilization and disposition
solid waste stabilization and disposition
waste disposal facility operation
waste and material transportation
A graphic representation of the types of EM Cleanup projects is provided in Attachment 1,
“Environmental Management Cleanup Projects by Major Category and by Type of Project.”
There are two types of PBSs, which are not considered EM cleanup projects. They are
Safeguards and Security and the Community Involvement PBSs. The guidance provided in this
document may be useful in the management of these PBSs. Within a cleanup project PBS, there
can be one or more subprojects which are typically defined as a non-major acquisition comprised
of a series of tasks or activities within a PBS that are related and have a specific objective. These
subprojects can be contained within the nine types of projects identified above. Sections 3.2 to
section 3.4 apply to these nine types of projects at PBS and subproject level.
2.1 Environmental Management Project Baseline Summaries
During fiscal year 2001, EM “projectized” its portfolio organizing scope, schedule, and cost of
all EM activities into descrete projects. EM projects that have common attributes, such as a
common assumed end state, geographic location, or activity type, were typically grouped under
the rubric of a PBS, which is directly linked to the more detailed project baselines developed by
DOE G 413.3-8 3
9-24-08
each site. More recently, EM mandated that all EM projects produce and execute against
certified near-term baselines (NTB), as well as produce reasonable out-year estimates.
2.2 Deactivation and Decommissioning Projects1
D&D are the two major phases of a facility disposition project.
In general, deactivation includes stabilization, removing nuclear materials, shutting down
non-essential systems, and other activities to convert a facility from operations to a mode
characterized as low surveillance and maintenance. Regardless of this generality, the scope of
deactivation is flexible and project specific; in some cases, deactivation can include total
cleanout of a facility.
Section 6
Decommissioning is used to indicate achieving an end state (e.g., demolition, entombment) for a
facility or group of facilities. Decommissioning of nuclear facilities is performed under
CERCLA non-time critical removal action regulatory umbrella unless the circumstances at the
facility make it inappropriate or unnecessary. This approach effectively integrates Environmental
Protection Agency (EPA) oversight responsibility; DOE lead agency responsibility, and state
regulator and stakeholder participation.
D&D may be conducted as two discrete activities, separated in time by an interim period of
surveillance and maintenance, or they may be conducted integrally in which case deactivation
activities usually occur early in the project. Decisions regarding the scope of D&D, the project
end state, or whether or not to conduct D&D as a single project are dependent on factors such as
budget, safety, and site and national priorities.
This does not mean that deactivation is not a part of the S&D projects. For five of the six S&D
projects, deactivation is a customary phase at the end of an operations cycle prior to
post-deactivation surveillance and maintenance.
2.3 Soil Groundwater Remediation Projects2
The soil and groundwater at most sites across the DOE complex is contaminated with hazardous
chemicals, metals, or radionuclides that are harmful to human health and the environment.
Cleanup of contaminated soil, groundwater, surface water, and biota at DOE sites continues
under EM's S&GW program. S&GW projects are not like typical design-build construction
projects. For example S&GW projects may include:
• subsurface contaminant characterization necessary to define the scope of work, which
may involve extensive drilling, sampling, and analysis;
• excavation and disposal of contaminated media along with sampling, testing, and
monitoring;
1 DOE O 413.3A defines D&D as “decontamination and decommissioning.” For the purposes of this guide,
however, that definition will not be used for D&D.
2 DOE O 413.3A defines S&GW as environmental restoration (ER). For purposes of this guide, ER projects are
called S&GW projects.
4 DOE G 413.3-8
9-24-08
• treatment of contaminated soil and groundwater using one or more remediation
methods to extract contaminants;
• immobilization and containment of the contaminant plume by stabilization methods
and remediation methods;
• construction of underground barriers to restrict contaminant movement; and
• construction of engineered caps over contaminated waste areas to control contaminant
movement.
Certain waste materials are regulated under the RCRA, a comprehensive law requiring
responsible management of hazardous waste. Areas where hazardous constituents may remain
uncontrolled and potentially released to the environment are identified as a solid waste
management unit (SWMU) under RCRA section 3004(U). RCRA section 3004(U) mandates
investigations and corrective actions at these units.
Sites included on the National Priorities List (NPL) fall under the jurisdiction of CERCLA,
which imposes requirements for the remediation of releases of hazardous substances and inactive
hazardous waste disposal sites. The NPL inclusion created a need to integrate the established
RCRA facility investigation (RFI) program with the CERCLA requirements to provide for a
focused environmental program. At several sites, DOE negotiated a FFA with the EPA and state
environmental regulatory agencies to coordinate remedial activities into one comprehensive
strategy to fulfill these dual regulatory requirements. RCRA and CERCLA regulatory processes
are further discussed under section 3.
Section 7
2.4 Stabilization and Disposition Projects
S&D projects are not defined as traditional projects but per DOE O 413.3A, can be managed as
projects. The following are classified as S&D:
• radioactive liquid waste tank stabilization and disposition
• nuclear materials stabilization and disposition
• spent nuclear fuel stabilization and disposition
• solid waste stabilization and disposition
• waste disposal facility operation
• waste and material transportation
S&D Projects can include traditional projects. Activities such as deactivation, research,
maintenance, start-up, and operations may be common to all EM cleanup projects.
DOE G 413.3-8 5
9-24-08
3.0 EM PROJECT REQUIREMENT OVERVIEW
3.1 EM Project Management Principles
The following sections describe the basic project management principles applicable to EM
cleanup projects and sub-projects. Secitons 3.2, 3.3, and 3.4 discuss the uniqueness of EM
cleanup project types.
3.1.1 Critical Decisions
CD-0 through CD-4 are decision points to evaluate project status and to determine if the project
is ready to go to the next phase and commit resources. CDs for S&GW and some D&D projects
are driven by the regulatory requirements in the CERCLA, RCRA, and regulatory agreements
with EPA, state and/or tribal authorities. These projects go through the same phases of initiation,
definition and execution; however, the sequence and grouping of specific activities and the
timing of CDs and documentation requirements for decisions may differ somewhat from those of
other projects. Refer to Figure 1, “Environmental Management Cleanup Projects Framework,”
for an illustration of a typical CD process.
The terminology used within this guide in the discussion of CERCLA and RCRA documentation
may differ based on Federal, State, and local regions and should be verified with the particular
EPA regional office and/or state regulatory agency governing the facility location. Appropriate
documentation of agreed upon terminology should be completed.
DOE Order 413.3A specifies “Project Closeout” (CD-4) in general terms for environmental
management projects as the point at which a project may proceed to EM completion. More
specifically, it is recommended in this guidance that project closeout and turnover address the
following subjects:
• Identifying the receiving organization that will be responsible for managing the site after
completion of a D&D and/or Soils and Groundwater project; for example a DOE
Program Secretarial Office (PSO) such as Legacy Management, another Federal
Department or Agency, State or Local community, and Indian Tribe, or others.
• Agreed-upon criteria for transfer such as an overall End State Definition and End Point
Specifications; these can include, for example, physical conditions/configuration,
allowable residual contamination, and specified records.
• Identification of project activities, such as operation of treatment systems and monitoring,
to be terminated by EM or to be continued by the receiving party.
• The status of various agreements and commitments, for example based on regulatory
requirements, legal settlements, contractual commitments, and others.
The record for CD-4 may take any of a number of forms that depend on who is assuming
responsibility. A Memorandum of Understanding (MOU) would be typical instrument for
transfer to another PSO.
6 DOE G 413.3-8
9-24-08
SITE
DISCOVERY
and
PROBLEM
Remediation (Cleanup) Requirements
US DOE Project Management Requirements
Section 8
Typical Project Life Cycle (2)
CD-0
INITIATION PHASE DEFINITION PHASE EXECUTION PHASE
PERFORMANCE BASELINE
CLOSEOUT and
TRANSITION PHASE
LONG-TERM
RESPONSE
ACTION
and
LONG-TERM
STEWARDSHIP
EM Cleanup Project Requirements for Existing Project Baseline Summaries
POST-COMPLETION PHASE
DISPOSITION BASELINE (3)
1) The typical CERCLA cleanup process is shown. Other programs [e.g. RCRA, Toxic
Substances Control Act (TSCA), US Nuclear Regulatory Commission (NRC), etc.] have a
similar structure.
2) Department policy is to apply project management principles to cleanup.
3) Refer to DOE O 430.1B regarding requirements for preparing disposition baseline for real
property assets.
(1)
CLEANUP LIFE CYCLE
LONG TERM
RESPONSE ACTION
RESPONSE
ACTION
EVALUATION
RESPONSE
ACTION
PROPOSAL
RESPONSE
ACTION
SELECTION
RESPONSE
ACTION
IMPLEMENTATION
EM
COMPLETION
RESPONSE
ACTION
COMPLETION
CD-1 CD-3 CD-4 CD-2
CD-2
CD-3
CD-4
EXECUTION PHASE
PERFORMANCE BASELINE
Combined CD-2 and CD-3 for when
the next phase of Life Cycle Estimate
is advanced into a new Near-term
baseline
CD-0 and CD-1 for
ongoing programs
have been waived
because they are in
their execution
(operating) phase.
New projects will
follow the CD
process as outlined
in DOE O 413.3A.
Note: The above two CD processes show the typical example of capital projects compared to an existing
EM Project Baseline Summary which has CD-0/1 waived and CD-2/3 combined. The CD processes are
discussed further in Sections 3.2.1 and 3.3.1 of this guide.
For existing S&D projects, which were already in the execution phase, the EM protocol
(reference 6.1) provides guidance on CDs. The CD-0, Approve Mission Need and CD-1,
Approve Alternative Selection and Cost Range have been waived because S&D projects were
already in their execution phase when EM decided to projectize them. Future projects and
subprojects require implementation of the CD process as delineated in DOE O 413.3A with
appropriate tailoring. For new S&D Projects or subprojects, CD-0 and CD-1 will not be waived.
Figure 1. Environmental Management Cleanup Projects Framework
DOE G 413.3-8 7
9-24-08
3.1.2 Baseline Development
This section describes the general steps involved in developing a PBS baseline including how,
when and by whom the NTB and out year planning estimate range (OPER), should be
developed, and who should develop independent government cost estimate (IGCE) for future
acquisitions and the role that the IGCE plays in the acquisition process and baselines updates. In
March 1999, EM issued the Integrated Planning, Accountability, and Budgeting Systems
(IPABS) Handbook. EM, through IPABS, directed HQ and field offices to projectize the entire
EM Program work into PBSs. Refer to Figure 2 for the relationship between OPER, NTB and
risk discussed in subsequent sections. Upon AE certification of the baselines, the NTB and
OPER should be placed under configuration control as described in reference 6.15.
Further baseline requirements are listed throughout the EM protocol. EM cleanup PBS should be
coordinated with baselines at the site and EM complex levels. Integration of complex-wide and
site level baselines provides key information for the determination of:
• construction of new facilities,
• operation of existing facilities, or
• expansion/modification of existing facilities.
Section 9
Consolidation, disposition, storage, transportation, and solid waste functions should be
considered during integration. Because the previous lists are not all inclusive, other activities
should be considered. In addition, baseline integration supports the process of deactivation,
decontamination, and decommissioning providing information that may lead to waste
management or S&GW remediation activities.
The life cycle of an EM cleanup project is broken into three time frames (see Figure 2) as
follows:
• Completed Work. This includes all actual costs from 1997 to the year before the
Near-Term Baseline.
• NTB. This baseline will be a minimum of five years or for the period of performance
of the current contract if it exceeds five years.
• OPER. This baseline has been defined as the first fiscal year following the last fiscal
year of the current NTB through project completion.
8
D
O
E G
413.3-8
9-24-08
Figure 2. Relationship of NTB and OPER in Project Life-cycle
Prior Costs Near-Term Baseline Out-Year Planning Estimate Range
Federal Risk,
(May be technical or programmatic)
Unfunded Contingency for
up to 80% Confidence level
+ Government furnished items**
TIME
Contractor’s Profit/Fee + Management Reserve
(Risks Identified by the contractor)
** Government Furnished Items include all
government-furnished materials and equipment
* EM PBS is treated like project
PMB (BCWS+UB)
CBB + Profit/Fee
EM Cleanup Project Life-cycle Cost Estimate
At Least 5 years
D
O
LL
A
R
S
Federal Lifecycle Baseline
(Performance Baseline)
(includes prior costs, NTB, and OPER)
*Project Baseline Summary (PBS)
Prior Costs Near-Term Baseline Out-Year Planning Estimate Range
Federal Risk,
(May be technical or programmatic)
Unfunded Contingency for
up to 80% Confidence level
+ Government furnished items**
TIME
Contractor’s Profit/Fee + Management Reserve
(Risks Identified by the contractor)
** Government Furnished Items include all
government-furnished materials and equipment
* EM PBS is treated like project
PMB (BCWS+UB)
CBB + Profit/Fee
EM Cleanup Project Life-cycle Cost Estimate
At Least 5 years
D
O
LL
A
R
S
Federal Lifecycle Baseline
(Performance Baseline)
(includes prior costs, NTB, and OPER)
*Project Baseline Summary (PBS)
DOE G 413.3-8 9
9-24-08
3.1.2.1 Near-Term Performance Baseline (i.e., Near-Term Baseline)
The near-term performance baseline for EM cleanup projects will normally be a minimum of
five years or for the period of performance for the current contract if it exceeds five years. For
projects that are scheduled to be completed within a few years (up to 3 years) after the five-year
period, the project certification may include the entire remaining out years. In the case where
fewer than 5 years remain on the current contract, the NTB should include the current contract
plus the expected period of performance for the next contract. For projects with durations of five
years or less, the entire project may be included in the near-term baseline review. In all cases
except possibly the tail end of the project lifecycle, the near-term baseline will start at the
beginning of a fiscal year and be complete at the end of a fiscal year.
Section 10
When the proposed near-term period is not completely covered by a contract, EM will be
responsible for developing summary level planning packages for those years not covered by the
contract. The entire near-term period may be included in the external independent review (EIR)
or independent project review (IPR). Once the contract is awarded and a detailed near-term
performance baseline is developed, a follow-up EIR or IPR will be performed to evaluate the
completeness of the contactor’s cost and schedule. The near-term performance baseline includes
fee, management reserve (MR), and all costs associated with executing the project within the
applicable window (e.g., 5 years). The fee and MR are reported outside the contractor’s
performance measurement baseline (PMB) but included in the contract price of the near-term
performance baseline.
Because the number of years included in the near-term baseline can vary for each project, the
final decision on the scope of the EIR including the length of the near-term baseline may be
based on a negotiated agreement between the Office of Engineering and Construction
Management (OECM) and EM. Near-term baselines will be aligned with target funding levels
which are part of the current approved strategic funding plan (e.g., Five-Year Plan) issued by EM
Program Planning and Budget. An EIR should be conducted on the near-term baseline if its cost
is equal to or greater than $250M, otherwise an IPR should be conducted.
The AE will approve CD-2 and CD-3 for the near-term baseline within 6 months after OECM
issues a memorandum certifying the near-term performance baseline or the certification may be
considered void. The goal is to provide a draft EIR report within 30 days after the on-site visit is
completed. Corrective Action Plans and closure of the actions is the joint responsibility of EM
and OECM.
For EM cleanup projects an independent cost estimate (ICE) should be developed or an
independent cost review should be performed as part of the OECM near-term performance
baseline validation. An ICE should be performed where complexity, risk, cost, or other factors
create a significant cost exposure for the Department.
3.1.2.2 Out-year Planning Estimate Range (OPER)
The OPER is defined as the first fiscal year following the last fiscal year of the current near-term
baseline through project completion. The OPER is the baseline for uncompleted PBS scope not
included in the near-term baseline. If the completion date remains constant, the timeframe of the
10 DOE G 413.3-8
9-24-08
OPER will decrease each time a new near-term baseline is certified. Verifying the
reasonableness of the OPER is part of the EIR or IPR review process.
The Office of Environmental Management, EM-1, approves the reasonableness of the OPER,
and is responsible for managing, changing and controlling the cost and schedule ranges. The cost
and schedule ranges may be adjusted annually based upon changing project or program
conditions including directed changes.
EM may tailor the requirements of DOE O 413.3A to the OPER but at a minimum a summary
scope of work, cost and schedule range, funding profile provided by Program Planning and
Budget, EM-30, and a robust project and program risk management plan should be included. The
amount of detail required will be less than the near-term baseline, and may vary from project to
project based upon the complexity of the work, ability to define the remaining scope, regulatory
drivers, disposition paths, existing or new technology requirements, etc. The scope of the
OPER-EIR and required documents will be part of the OECM and EM negotiations. The OPER
is reported in IPABS and in the planning section of PARS.
Section 11
3.1.2.3 Work Breakdown Structure (WBS)
The WBS provides a product/activities-oriented structure that arranges, defines, and graphically
displays all work elements in an organized and structured framework. The higher-level activities
necessary to accomplish a defined scope of work should be identified during the planning phase
of a project.
When possible, the Environmental Cost Element Structure (ECES) as described below should be
used in development of the WBS and cost elements. The below structure may not be a good
match for specific projects and the Federal Project Director should have some flexibility in
choosing the the cost elements that make the most sense for managing and controllong the
project in the most cost-effcient and appropriate matter.
The WBS is identifier information for D&D, S&GW, and S&D cleanup projects including waste
management activities. It should incorporate or refer to standard EM cost categories per ASTM
International (ASTM) Standard E2150, Standard Classification for Life-Cycle Environmental
Work Elements Environmental Cost Structure. Use or reference to the Environmental Cost
Element Structure (ECES) standard cost categories allows for the project historical costs to be
captured in EM’s historical cost database in the Environmental Cost Analysis System (ECAS).
These historical costs can then be analyzed and used in the development of future baselines for
NTBs and OPERs.
At the close of the contract period or as defined in the contract, contractors should provide to
DOE completed project or project phase historical cost data for use in the ECAS at the level
specified in the contract documents or by the DOE contracting officer. This cost categorization
information is invaluable to the DOE for comparing the contract prices with the estimated cost in
the IGCE and NTBs . The contractor can use a suitable WBS below that level to accommodate
work activities in more detail for execution, performance measurement, and other purposes
beyond supporting the historical cost collection efforts by EM through ECAS. The level of the
WBS structure is determined contractually and through the reporting requirements.
DOE G 413.3-8 11
9-24-08
A WBS dictionary that summarizes the scope of work included in any WBS element should be
available so that the cost, schedule, and risk factors associated with that element can be analyzed.
3.1.2.4 Environmental Cost Element Structure (ECES)
The ECES is a lower level life-cycle work/cost breakdown structure that provides a framework
for managing cost, schedules, and performance objectives of an environmental project developed
by the Interagency Environmental Cost Engineering Committee to improve cost management of
Federal environmental projects. The ECES enhances cost management by providing a
comprehensive, consistent structure that allows cost collection and identification for all project
phases and phase activities (e.g., program management, project management, or sampling and
analysis, etc.). The ECES allows for the separation of project components into logical parts,
which allows for task separation and the detailed monitoring of those components. These major
tasks/activities can be followed by more detailed cost elements to facilitate bottoms-up cost
estimating, cost reporting, and collection. In addition to its primary project management
function, ECES can facilitate the solicitation process and compare project data between sites and
agencies.
Section 12
The ECES follows the major steps in the CERCLA and RCRA processes, including preliminary
assessment, site inspection, remedial design, and construction.
The ASTM classifies the ECES as a national standard. The ECES standard is ASTM Standard
E-2150-02, Standard Classification for Life Cycle Environmental Work Elements -
Environmental Cost Element Structure. More information is available online at
http://www.em.doe.gov/pages/Aceteam.aspx.
3.1.3 Performance Baseline
The contractor performance baseline (PB) is a subset of the NTB and is the baseline that the
FPD, under EM configuration control, manages, controls, and monitors the progress during
project execution. As such, a PBS is comprised of one or more PBs. It includes completed work
(may include a completed NTB) and the current NTB. OPER work will be classified as PB once
baselined as an NTB. The method of monitoring should be established during the development
of the baseline and should include an earned value management system that is compliant with the
American National Standards Institute/Electronic Industries Association ANSI/EIA 748-A-1998,
Earned Value Management Systems (EVMS) (reference 6.2). EVMS data, major milestones, and
key performance parameters (KPPs) including those listed in Table 2 are entered into PARS and
IPABS.
Performance measurement only applies to the near-term baseline periods. Some unique
performance metrics used for EM cleanup projects are described in sections 3.2.3, 3.3.3 and
3.4.3. EM Cleanup projects are unique in that they may have funded and unfunded contingency
(see section 3.1.5).
Monitoring of the PBS at the HQ level is completed primarily using the Integrated Planning,
Accounting and Budgets System (IPABS). Actual cost, schedule, and performance data are
collected for each PBS and compared to the established baseline. All elements of the lifecycle
12 DOE G 413.3-8
9-24-08
baseline are under EM configuration control. Performance data include project performance
measures and milestones. IPABS currently tracks performance through the corporate
performance measures shown in Table 2, “Environmental Management Corporate Performance
Measures.” The EM Corporate Performance metrics are a range of activities that account for
many of EM’s cleanup activities across the complex. This includes D&D of nuclear,
radiological, and industrial facilities (categorized in DOE-STD-1027-92) as well as S&GW
remediation. These metrics are counted as complete upon acceptance by the local regulatory
agency.
There are metrics associated with the stabilization and disposition of nuclear materials, nuclear
materials storage areas, radioactive and mixed wastes, and tanks for storage of high-level liquid
waste. The metrics listed in Table 2 are corporate performance metrics and with appropriate
approval may be adjusted to better accommodate regulatory direction as well as changes to
current practices. These performance measures are discussed fully at
http://www.em.doe.gov/Pages/perfmeasdef.aspx.
Table 2. Environmental Management Corporate Key Performance Parameters
Category Units
Plutonium, metal or oxide package for long term
storage
Number of Canisters
Enriched Uranium packaged for long term storage Number of Containers
Material Access Areas eliminated Number of Areas
Plutonium or Uranium residues packaged for
disposition
Kilograms of Bulk Materials
Transuranic Waste dispositioned Cubic Meters
Depleted and other Uranium packaged for
disposition
Metric tons
Section 13
Spent Nuclear Fuel packaged for final disposition Metric Tons of Heavy Metal (MTHM)
High-Level Waste packaged for final disposition Number of Containers
Liquid Waste in Inventory eliminated Kilo Gallons
Liquid Waste Tanks closed Number of Tanks
Low-Level and Mixed Low-Level Waste disposed Cubic Meters
Remediation completed Number of Remediation Completions
Nuclear Facility completed Number of Facilities
Radioactive Facility completed Number of Facilities
Industrial Facility completed Number of Facilities
DOE G 413.3-8 13
9-24-08
3.1.4 Risk
This section provides additional fundamental requirements and information for the application of
risk management to the EM programs and projects as required by DOE Order 413.3A, Program
and Project Management for the Acquisition of Capital Assets. This information and
fundamental requirements are not provided specifically in DOE G 413.3-7, Risk Management
Guide.
The DOE G 413.3-7 Risk Management Guide’s operable risk culture is captured in the EM risk
management policy. The policy states that safety-related risks are to be avoided. In other risk
areas, the handling strategy should first be analyzed for an avoidance strategy within the bounds
of a cost/benefit analysis. If, however, the analysis does not justify an avoidance strategy, a step-
wise risk handling strategy should be found that would eliminate or reduce the impact of
forecasted risks.
EM’s risk culture exists in a framework that is bounded by the extent to which an individual
project can effectively absorb risks to the project within their scope. Risks to the project that
cannot be effectively absorbed by the project should be clearly identified in the RMP. Other
constraints exist within this framework and should also be recognized within the Risk
Management Plans (RMPs) of both the federal and the contractor IPTs. These constraints,
among others, include:
• Funding
• Schedule
• Human resources
• Equipment, material and other field office resources
• Technical knowledge
RMPs are to be developed and documented for all PBSs per the EM Protocol on both the NTB
and OPER.
A fundamental component of the risk planning process is the federal RMP, which captures risks
as well as risk handling strategies. The RMP is the roadmap that tells the government or
contractor team how to proceed in risk management from where the project is conceptually to
where the project is predicted to be in the future based upon initial risk management project
planning documentation. During preparation for CD-1, the contractor will prepare a contractor
RMP reflecting the risk handling strategy for the contract period.
These RMPs are strategic documents that state the processes that will be used to accomplish the
overall risk process, the resources that will be applied, the schedule required for the initial
completion of the first cycle of the process, and the first re-issue of the RMP with the Risk
Register. The Risk Register is either included by reference or physically included in the RMP.
Depending upon the number of transferred threats or shared opportunities, a project may choose
to have separate risk registers for threats and opportunities. It is recommended for large projects
that a separate register be maintained for threats and opportunities.
14 DOE G 413.3-8
9-24-08
Risk can be identified at the sub-project level, depending upon the size and complexity of the
project. Individual subprojects, programs or projects within the PBS may require their own
RMP, which may be contained expressly in the PEP or included by reference.
Section 14
It is DOE policy that all contingency requests be supported by a quantitative risk analysis.
Identified risks must be sufficiently characterized to support a quantitative analysis that all
projects must undergo to support the contractor and EM cost and schedule contingencies. The
quantitative analysis should be prepared in support of the CD-2 project phase, and the
contingency management associated with the approved baseline should be fully implemented
after the contract is awarded.
Qualitative analysis is also mandatory for projects within the EM program portfolio or field
program office and is an integral part of the monthly project status reporting.
Unless otherwise specified in the PEP, the IPT for each project should prepare a formal risk
report to the FPD, who should file a reviewed report with the Office of Project Management
Oversight (EM-53) on a monthly basis. The report should be integrated with other metric
reporting for the near-term. Although the project life-cycle risks are always important, the focus
of the monthly status report should be near-term, often a 90-day rolling horizon, and changing
life cycle risks should be addressed in more detail during the periodic quantitative updates (often
performed on a quarterly basis).
The monthly risk report should contain the following:
• Status of the key project risks and explanations of any significant changes
• Review of risk handling strategies taken or postponed during the previous month and
their effectiveness
• Review of risk handling strategies due during the next 90 days, including the
responsible parties
• Review of any safety or security risk for which the avoidance strategy is viewed as
presenting secondary risks
Discussion of the status of the risk should include more than whether the risk is open or closed.
It could include items such as whether the trigger metric did not transpire and the risk time has
elapsed; the risk has significantly changed and is being entered as a new risk; the risk handling
strategy is being modified; or other information that might highlight such items as a lessons
learned or a new risk item. These discussions are a necessary element of risk communication
and feedback.
Any new risks which are identified during the risk reporting process should be entered into the
risk register. If the project has had scope changes or other impacts that have resulted in changes
to the project’s risk profile, the risk identification process should be re-initiated and the risk
register resubmitted either in hard copy or electronically during the reporting period when the
changes are noted
All risks, including those risks which have been judged by the IPT to be qualitatively overall low
in risk, should be reviewed. A report should be submitted by the contractor project manager to
DOE G 413.3-8 15
9-24-08
the FPD, and by the FPD to the appropriate designee in the Office of Project Management
Oversight (EM-53) stating any changes in risk classifications and in the handling strategies for
near-term risks.
On a quarterly basis, risks, including those risks which have been judged by the IPT to be
qualitatively overall low in risk, should be reviewed. This review does not negate the need to
maintain the review for trigger metrics for the risks.
Section 15
The risks of the most concern for the next quarter should also be reported in the quarterly project
review (QPR) or in a currently existing quarterly project report or review with the step-wise risk
handling strategy with the date metric as it appears in the risk register for risk reporting.
Other quarterly reporting may be accomplished through the QPR through detailed supporting
slides. In addition to the information contained in the monthly risk report, the quarterly report
should contain the following:
• An updated project key risk table that reflects the current project level risks
• An updated Risk register including handling actions for risks ranked greater than an
overall low classification with their associated due dates and responsible party for the
risk handling strategy
• Identification, one level below the project level, of risks which have the largest
potential to impact the project if their likelihood or their impacts were to increase
over current projections
If changes in risk handling strategies and/or risk levels are indicative of a forecasted shortfall, an
updated quantitative analysis assessing the adequacy of project cost and schedule contingencies
is recommended.
3.1.5 Contingency
Contingency is an integral part of EM baseline budgetary and planning processes that
acknowledges and makes provision for the possible impacts to project cost and schedule of latent
project risks. Appropriate estimates, management, and funding of contingency are essential
elements to project success.
Contingency is a tool used to help management respond to the uncertainty that is inherent in EM
projects. Coupled with a well administered Baseline Management processes, EM cleanup
projects set the stage for a project management culture that is Best-in-Class. EM contingency
provides the flexibility to successfully deal with planned and unplanned project risks that would
otherwise result in unanticipated work scope delays.
Cost and schedule contingency are project resources, which are expected to be used as risks and
uncertainties are realized.
EM contingency policy creates several categories of contingency, each of which is discussed in
this section. The various categories of contingency are used to provide EM and their contractors
the ability to control project risks in support of the project success.
16 DOE G 413.3-8
9-24-08
EM establishes the following categories of risk based contingencies:
• Contractor Management Reserve (MR) is for use by a contractor and is a portion
of the negotiated contract cost estimate/target that the contractor sets aside for the
management of risks within the contractor’s contractual obligations. MR is
maintained separate from the performance measurement baseline and is utilized by
means of the contractor change control process. MR is determined by the contractor
and it is not estimated at a specified DOE EM confidence levels.
It is also important to recognize that the contract price is established by cost analysis
and price analysis and once established is allocated to PMB, MR, and profit/fee;
PMB, MR, and profit/fee are a function of contract price–contract price is not a
function of PMB, MR, and profit/fee. As such, MR is determined as the resultant of
the contact price less profit/fee, less PMB.
(MR = CP – profit/fee – PMB)
• Contractor schedule reserve is for use by the contractor and is that portion of the
overall project schedule duration that is estimated to allow for the time related
impacts of risk.
Section 16
• EM project contingency is for use by the FPD and is the portion of the project
budget that is available for managing risk within the funded project baseline. EM
policy establishes project contingency at a level that provides at least a 50 percent
confidence level for completing the near-term baseline (NTB) for EM cleanup
projects.
• EM unfunded contingency is applicable only to EM cleanup projects and is
calculated as the additional funds that would be needed for managing project risk to
bring the overall confidence level in completing the project up to at least an 80
percent confidence level.
• EM schedule contingency is for use by the FPD and is the portion of the overall
project schedule duration that is estimated to allow for the time impacts of risk. EM
policy establishes contingency to provide a project confidence level range from 50 to
80 percent for EM cleanup projects.
Newly certified NTBs are to identify any contingency needed to represent at least 50%
confidence level regarding project risk (both contractor and DOE project risks). Any increment
above the sum of the PMB, profit/fee, and other DOE direct costs, required to ensure this level of
confidence will be identified as “DOE Contingnency (50% CL).” Requests for approval of new
NTBs must reflect funding consistent with this level of contingency. EM policy related to
“Unfunded Contingency” (i.e., the increment form 50% to 80% confidence level) remains the
same. This guidance should be incorporated during the next rebaselining effort. This guidance
by itself is not intended to trigger a rebaselining effort.
The intent of MR and contingency for both cost and schedule is to:
DOE G 413.3-8 17
9-24-08
• Allow EM and contractor management the time and funding resources to respond to
the changing risk circumstances of the project in a manner that will maximize the
projects ability to hold project cost and schedules.
• Provide a risk-adjusted forecast of Estimate-to-Complete and completion date.
• Support the FPD and contractor project manager in aggressively managing the
potential risks to the project.
The overarching goal of this section is to assist each EM cleanup project in the development of a
consistent approach to contingency determination and management through:
• Contingency concepts such as MR, schedule reserve, project contingency, unfunded
contingency, and EM schedule contingency.
• Development and management of cost contingency for EM related project risks.
• Development and management of schedule contingency for EM related project risks.
3.1.5.1 Cost and Schedule Contingency Development
Initial cost and schedule estimates are developed as rough-order-magnitude (ROM) estimate
alternatives during the CD-0 project stage with contingency included as part of the ROM
estimate uncertainty. As the project progresses toward the CD-1 planning stage a project
approach is selected and the project scope refinement begins. After CD-1 approval an
independent government cost estimate (IGCE) is developed providing a more definitive cost and
schedule estimate of the project. During the CD-1 planning stage, a formal Federal Risk
Management Plan should be developed identifying anticipated contractor and EM project risks as
well as the cost and schedule impacts expected from these risks. At this stage of the project
planning the project estimate is evaluated to provide at least at a 50 percent confidence level for
budget planning (project funding) and at least an 80 percent confidence level for life-cycle
planning. The project estimate to complete and project confidence levels will be periodically re-
evaluated throughout the project’s life-cycle.
Section 17
To provide for the planning and development of the project OMB, Circular No. A-11, Part 7,
Planning, Budgeting, Acquisition and Management of Capital Assets, states that life-cycle costs
means the overall estimated cost for a particular program alternative over the time period
corresponding to the life of the program, including direct and indirect initial costs plus any
periodic or continuing costs of operation and maintenance. The guidance also states new
projects must be justified based on the need to fill a gap in the agency’s ability to meet strategic
goals and objectives with the least life-cycle costs of all the various possible solutions and
provide risk adjusted cost, schedule goals, and measurable performance benefits.
The DOE G 413.3-7, Risk Management Guide recommends that risk management activities such
as risk identification and risk assessment be initiated early in the project life-cycle. As a project
matures, the detail and precision of the project baseline improves through the various critical
decision (CD) phases (i.e., CD-0 to CD-4), as shown in Figure 3. Early project estimates are
subject to large uncertainties and are based on conceptual scope definition. These early
estimates use cost estimating relationships, parametric relationships, and historical data to
18 DOE G 413.3-8
9-24-08
provide ROM estimates of project cost. While it is possible to perform a Monte Carlo analysis
on a ROM estimate, the results of the analysis do not add a great deal of value because the costs
and risks are aggregated at such a high level. In addition, the project baseline and program
uncertainty are quite high as a project progresses from CD-0 through to CD-2. Consequently,
there is an elevated likelihood that many project risks will remain unrecognized or unidentified
throughout the early project phases.
Figure 3: Project Scope Detail Improves as the Project Matures
The DOE G 413.3-7, Risk Management Guide states that the preferred methodology for
quantitative analysis is a Monte Carlo analysis. A Monte Carlo analysis requires a model that
includes identified risks and uncertainties and defines their interrelationships. Normally,
baseline cost estimates are the basis for cost risk models and critical path method (CPM)
schedules are the basis for schedule risk models. Inputs to the analysis are the risks identified in
the project risk register; the various risk likelihoods (probability of occurrence) and impacts
(consequence) as well as the associated project cost and schedule uncertainties.
To complete the contingency analysis, a project may use an integrated cost and schedule model
or individual cost and schedule risk models, as depicted in Figure 4. If separate cost and
schedule models are used they must be developed using the same baseline information and
assumptions. The interactions between the cost and schedule risk models must be integrated to
account for hotel and other level-of-effort costs associated with project delays and extensions.
DOE G 413.3-8 19
9-24-08
Because EM projects vary in complexity and scale, it is impossible to stipulate the exact design
of the Monte Carlo models.
Figure 4: Conceptual Cost and Schedule Risk Analysis Process
Risk: Threats Risk: Opportunities
Cost Risk Profile
(CDF)
Current Schedule
Risk Profile (CDF)
Estimate Uncertainty
Cost Schedule
Cost
Risk Model
Schedule
Risk Model
Risk: Threats Risk: Opportunities
Cost Risk Profile
(CDF)
Current Schedule
Risk Profile (CDF)
Section 18
Estimate Uncertainty
Cost Schedule
Cost
Risk Model
Schedule
Risk Model
The contractor’s MR risk model is based on the project work breakdown structure (WBS)
elements and their associated cost estimates. The risk model should only include the contractor
risks that would normally be managed within the performance measurement baseline. The
contractor’s estimation of the contractor schedule reserve is typically based on the contractor
CPM schedule using only the contractor risks that the contractor would normally be expected to
manage within their contractual obligations.
Similarly, the calculation of EM cost contingency is based on the WBS and represents the
incremental expected cost of the project related risks at a given confidence level. Due to the
effects of risk interrelationship, competing risks, and compounding impacts, both EM project and
contractor risks are included in the EM contingency calculation and contractor MR (representing
contractor risks only) is subtracted from the total estimated contingency amount. Similar
considerations apply to the calculation of the project’s schedule contingency. Figure 5, is
representative of the relationship between contractor MR, EM project contingency, EM
unfunded contingency, and the EM project NTB and OPER baseline. The cumulative
distribution function (CDF) curves (S-curves) shown in the Figure 5 represent the likelihood of
successful project completion (y-axis) for a given project cost (x-axis).
20 DOE G 413.3-8
9-24-08
Figure 5: S-curve Representation of MR, EM Project, and EM Unfunded Contingency
NTB & OPER
(Contractor, Project, &
Project Specific Programmatic Risks)
PB
+ OPER Work Scope
Probabilistic Projection of Cost using Monte Carlo Analysis
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Pr
ob
ab
ili
ty
o
f C
om
pl
et
io
n
at
a
gi
ve
n
Pr
oj
ec
t C
os
t
Contractor PB
(Contractor Risks Only)
NTB @ 50% CL
Includes all
Contactor & EM
Project Risks
80% CL
NTB
(Contractor & Project Risks)
50% CL
NTB & OPER @ 80% CL
Includes all Contractor, EM
Project, & EM Project Specific
Programmatic Risks
Project Cost
+ Profit/Fee
+ DOE ODCs
+ Un-contracted
Work Scope
PMB
Includes Only
Contactor
Risks
NTB & OPER
(Contractor, Project, &
Project Specific Programmatic Risks)
PB
+ OPER Work Scope
Probabilistic Projection of Cost using Monte Carlo Analysis
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Pr
ob
ab
ili
ty
o
f C
om
pl
et
io
n
at
a
gi
ve
n
Pr
oj
ec
t C
os
t
Contractor PB
(Contractor Risks Only)
NTB @ 50% CL
Includes all
Contactor & EM
Project Risks
80% CL
NTB
(Contractor & Project Risks)
50% CL
NTB & OPER @ 80% CL
Includes all Contractor, EM
Project, & EM Project Specific
Programmatic Risks
Project Cost
+ Profit/Fee
+ DOE ODCs
+ Un-contracted
Work Scope
PMB
Includes Only
Contactor
Risks
Each project may have a mix of current and future contract activities during the NTB period and
may include multiple DOE contracts within the same project. The length of the NTB will be
based on an agreement between the FPD and the AE. The NTB period for EM cleanup projects
will be for a minimum of five years. Figure 6 provides a graphical representation of the NTB
and OPER periods.
• For cleanup projects where less than five years remain on the current contract, the
NTB should include the current contract plus the expected period of performance for
the next contract.
Section 19
• For cleanup projects which are scheduled to be completed within a few years (up to
three years) after the five year period, the NTB includes the entire remaining out-
years.
• For cleanup projects with durations five years or less, the NTB includes the entire
project.
• For cleanup projects where the NTB equals the contract period which equals to the
entire cleanup project baseline.
DOE G 413.3-8 21
9-24-08
Figure 6: Near Term Baseline vs Contract and Future Contract Period
Remaining Contract plus
Remaining Baseline
Remaining Contract
less than 5 years
EM Cleanup Project
(Case 3) NTBNTB
OPEROPER
Existing Contract
Existing Contract
Future Contract(s)Next Contract Period
Completed Work Future Work
EM Cleanup Project
(Case 1)
EM Cleanup Project
(Case 2)
Remaining Baseline
less than 5 years
Existing Contract
For projects to be
completed within 3-years
after the 5-year period, the
NTB includes the entire
remaining out years.
5-year
Threshold
EM Cleanup Project
(Case 4) NTBNTB
Existing Contract
Contract Period Equals
the Entire Project Baseline
Remaining Baseline
NTBNTB
NTBNTB
Remaining Contract plus
Remaining Baseline
Remaining Contract
less than 5 years
EM Cleanup Project
(Case 3) NTBNTB
OPEROPER
Existing Contract
Existing Contract
Future Contract(s)Next Contract Period
Completed Work Future Work
EM Cleanup Project
(Case 1)
EM Cleanup Project
(Case 2)
Remaining Baseline
less than 5 years
Existing Contract
For projects to be
completed within 3-years
after the 5-year period, the
NTB includes the entire
remaining out years.
5-year
Threshold
EM Cleanup Project
(Case 4) NTBNTB
Existing Contract
Contract Period Equals
the Entire Project Baseline
Remaining BaselineRemaining Baseline
NTBNTBNTBNTB
NTBNTBNTBNTB
Figure 7 is applicable to EM cleanup projects and shows the components of both the current
contract and the future contract period. Although the components in Figure 7 are similar for both
current contract and the future contract periods, the methods used to estimate them may be very
different with different degrees of uncertainty. Development of EM funded contingency for
future contract scope within the NTB is required and it is recommended in the OPER to facilitate
budget development, federal life-cycle baseline analysis, and strategic planning.
Figure 7: Project Lifecycle Components
Current Contract
Near-Term Baseline
EM Project
Contingency
Contract
Price
Future Contract
Prior Costs
Project Life-cycle Baseline
EM Unfunded
Contingency *
EM Direct Costs
Profit/Fee
Management Reserve
Contractor
Performance
Measurement Baseline
(PMB)
Estimated
Management Reserve
Estimated Future
Contract Baseline
Estimated Profit/Fee
* For EM Cleanup projects only
At least 80% CL
Based on
Contractor,
EM Project, &
EM Project Specific
Program Risks
At least 50% CL
Based on
Contractor &
EM Project
Out-Year Planning
Estimate Range
Estimated Future
Contract Baseline
Estimated Profit/Fee
Estimated EM Direct Costs
Estimated EM Project
Contingency
Estimated EM Unfunded
Contingency *
Estimated
Management Reserve
Current Contract
Near-Term Baseline
EM Project
Contingency
Contract
Price
Future Contract
Prior Costs
Project Life-cycle Baseline
EM Unfunded
Contingency *
EM Direct Costs
Profit/Fee
Management Reserve
Contractor
Performance
Measurement Baseline
(PMB)
Estimated
Management Reserve
Estimated Future
Contract Baseline
Estimated Profit/Fee
* For EM Cleanup projects only
Section 20
At least 80% CL
Based on
Contractor,
EM Project, &
EM Project Specific
Program Risks
At least 80% CL
Based on
Contractor,
EM Project, &
EM Project Specific
Program Risks
At least 50% CL
Based on
Contractor &
EM Project
At least 50% CL
Based on
Contractor &
EM Project
Out-Year Planning
Estimate Range
Estimated Future
Contract Baseline
Estimated Profit/Fee
Estimated EM Direct Costs
Estimated EM Project
Contingency
Estimated EM Unfunded
Contingency *
Estimated
Management Reserve
22 DOE G 413.3-8
9-24-08
Figure 7 represents the fundamental building blocks used in the development of MR and
contingency. This depiction is from a combination of EM documents including the Protocol for
Environmental Management Cleanup Projects (reference 6.1), the Policies for EM Operating
Project Performance Baselines (reference 6.14), and the Configuration Control Process for
Project Baselines (reference 6.15). Policy reference 6.1 incorporates three project periods: the
prior costs, the NTB, and the OPER. Policy reference 6.14 identifies the following attributes
with respect to contractor MR and EM contingency, which are paraphrased below:
• Contractor MR and EM project contingency represent funds available for managing
known project risks.
• To estimate EM unfunded contingency, EM performs a project life-cycle risk
analysis of known project and project related programmatic risks. The estimated
cost of risk impacts and risk handling strategies for managing those risks are an
integral part of the contingency development.
• EM funding requests include PMB, contractor MR, Profit/Fee, EM other direct costs
(ODC)/GFS&I, and any available EM funded contingency allocated to the funding
year.
• Federal risk management plans identify both contractor and EM risks for the entire
life-cycle of the project and are used to establish EM contingency amounts.
• EM programmatic risks generally involve activities like those associated with federal
deliverables and can include: funding availability risks, technical complexities such
as disposal paths, regulatory uncertainties, funding shortfalls, and schedule changes.
In many cases, these federal deliverable risks can prevent or preclude a contractor
from successfully completing the assigned contract work.
Once contingency estimates are developed, the FPD uses the cost and schedule contingency to
manage and mitigate the potential consequences of project risks and uncertainties.
MR is held in a consolidated reserve account within the contract budget base to provide
flexibility for the contractor to manage risks associated with the contract requirements. MR
cannot be used to address risk issues arising beyond the scope of the contract requirements or
used to resolve negative variances resulting from poor contract performance.
EM project contingency is maintained in an EM held consolidated reserve account within the
project and can be used to recover from the impacts of realized project risks incurred either in
executing the project baseline or by other EM work scope. Project contingency can also be used
to fund opportunities, and newly identified risk handling strategies. EM project contingency
includes funds for:
• Uncertainties in the estimate of EM costs within the PBS.
• The occurrence of identified EM risks.
EM project contingency can be used to reduce the likelihood or the impacts of identified EM
risks. EM contingency, by design, may be used to fund contractor realized risks when available
MR has been expended.
Section 21
DOE G 413.3-8 23
9-24-08
EM unfunded contingency applies only to EM cleanup projects. EM recognizes that additional
project funds may be required above the 50 percent CL. The decision to request unfunded
contingency is made by the site FPD. Currently, EM unfunded contingency is funded by:
• Managing funds within a project to address critical path and realized risk events.
• Requesting additional funds from the Configuration Control Board.
• Requesting additional funds in the next budget cycle or through re-programming for
that project.
• Performing Value Engineering studies to determine alternative methods for meeting
the requirements but at reduced costs.
The EM project baseline schedule includes clearly identified EM schedule contingency that
provides a confidence level range of 50 to 80 percent for meeting the selected key milestones,
which includes the project completion date.
Since contractor reserves (cost and schedule) and EM contingency (cost and schedule) are finite
resources for managing project risk, their use must be monitored and evaluated as part of the
ongoing project control function. Evaluation of these resources involves the periodic assessment
of the overall adequacy of the remaining contractor MR and schedule reserve as well as EM cost
and schedule contingencies. The evaluation also identifies the areas of the project that are
contributing the most to cost and schedule variances. The utilization of cost and schedule
contingency should be planned, reported, and managed over the project duration to insure that
sufficient contingency is available to support successful project completion. Drawdown curves
are used to depict the planned and actual contingency utilized to assist the evaluation and
management of contingency. Changes in the previously identified risk likelihoods and impacts,
which may have significant impact on the analysis, should be identified and the risk should be
updated in the risk register.
3.1.5.2 Calculating MR and Contingency
A common way to evaluate Monte Carlo models is to use a CDF. The CDF represents the entire
range of values encountered in the Monte Carlo analysis of the cost estimate (depicted on the x-
axis) and the cumulative probability of occurrence of a particular value (depicted on the y-axis).
Figure 8 illustrates sample CDF curve for a hypothetical project. The CDF represented by the
curve is based on project risks (contractor and DOE project risks).
24 DOE G 413.3-8
9-24-08
Figure 8: Project Completion Confidence Levels at Specified Project Costs
Project cost
305
244
183
122
61
0
300 500
Fr
eq
ue
nc
y
of
O
cc
ur
re
nc
e
C
um
ul
at
iv
e
Pr
ob
ab
ili
ty
— 100 %
— 95 %
— 90 %
— 85 %
— 80 %
— 75 %
— 70 %
— 65 %
— 60 %
— 55 %
— 50 %
— 45 %
— 40 %
— 35 %
— 30 %
— 25 %
— 20 %
— 15 %
— 10 %
— 5 %
750
300
500
750
Project cost
305
244
183
122
61
0
300 500
Fr
eq
ue
nc
y
of
O
cc
ur
re
nc
e
C
um
ul
at
iv
e
Pr
ob
ab
ili
ty
— 100 %
— 95 %
— 90 %
— 85 %
— 80 %
— 75 %
— 70 %
— 65 %
— 60 %
— 55 %
— 50 %
— 45 %
— 40 %
— 35 %
— 30 %
— 25 %
— 20 %
— 15 %
— 10 %
— 5 %
750
300
500
750
305
244
183
122
61
0
300 500
Fr
eq
ue
nc
y
of
O
cc
ur
re
nc
e
C
um
ul
at
iv
e
Pr
ob
ab
ili
ty
— 100 %
— 95 %
— 90 %
— 85 %
— 80 %
— 75 %
— 70 %
— 65 %
— 60 %
— 55 %
— 50 %
— 45 %
— 40 %
— 35 %
— 30 %
— 25 %
— 20 %
— 15 %
— 10 %
— 5 %
750
300
500
750
Section 22
EM project contingency, is defined as the difference between the anticipated project cost,
estimated to provide at least a 50 percent confidence level, and the project’s contract award
price. EM unfunded contingency includes all contractor and project risks above the 50 percent
CL and all project related program risks to provide at least an 80 percent CL. Figure 9 illustrates
the relationship of MR and EM contingency to the EM project baseline, which includes the NTB
and OPER.
Figure 9: MR and EM contingency relationship to the project baseline
Contractor MR
Contractor Risks
Only
EM Funded Contingency
at least @ 50% CL
Includes All
Contactor & Project Risks
EM NTB Unfunded
Contingency
at least @ 80% CL
Includes All
Contractor &
Project Risks
EM Performance Baseline
(NTB & OPER)
at least 80% CL Includes All
Contractor,
Project &
Project Specific Programmatic Risks
Contractor MR
Contractor Risks
Only
EM Funded Contingency
at least @ 50% CL
Includes All
Contactor & Project Risks
EM NTB Unfunded
Contingency
at least @ 80% CL
Includes All
Contractor &
Project Risks
EM Performance Baseline
(NTB & OPER)
at least 80% CL Includes All
Contractor,
Project &
Project Specific Programmatic Risks
DOE G 413.3-8 25
9-24-08
EM schedule contingency is developed based on all project risks (contractor and EM) for the
certified project baseline. The schedule contingency is calculated using a Monte Carlo analysis
based on logic-driven schedule. Schedule activities that are affected by an identified risk or
estimated duration uncertainty are modeled in a Monte Carlo scheduling program with an
appropriate probability distribution. When the Monte Carlo analysis is conducted, the EM
schedule contingency is calculated to provide a 50 to 80 percent confidence level range that the
project will be completed by the scheduled date. Schedule contingency should be applied to the
project schedule to support the successful completion of the planned project end date and key
project milestones, as illustrated in Figure 10.
Figure 10: Allocation of Schedule Contingency to Selected Schedule Milestones
Regulatory
Milestone
P50 DOE Milestone Date, at least a 50%CL Contactor & EM Project Risks
P80 DOE Milestone Date, at least an 80%CL Contractor, EM Project, & EM Project Related Program Risks
Activity 1
Activity 2
Activity 3
Schedule Contingency
Project Level of Effort Activities (LOE)Project Level of Effort Activities (LOE)
P80, 80%CLP50, ≥ 50%CL
Deterministic
Finish,
No Risks
Estimated
Contractor
Completion Date
Regulatory
Milestone
P50 DOE Milestone Date, at least a 50%CL Contactor & EM Project Risks
P80 DOE Milestone Date, at least an 80%CL Contractor, EM Project, & EM Project Related Program Risks
Activity 1
Activity 2
Activity 3
Schedule Contingency
Project Level of Effort Activities (LOE)Project Level of Effort Activities (LOE)
P80, 80%CLP50, ≥ 50%CL
Deterministic
Finish,
No Risks
Estimated
Contractor
Completion Date
3.1.6 Reviews [External Independent Reviews (EIR) and Independent Project Reviews
(IPR)]
The process for review and validation of the NTB and verification of the reasonableness of the
OPER is specified in the EM Protocol (reference 6.1).
Section 23
An EIR is to be conducted on the NTB if its cost estimate is equal to or greater than $250M,
otherwise an IPR may be conducted. Once a contract is awarded which encompasses the NTB, a
detailed near-term performance baseline will be developed. If the previously certified federal
NTB exceeds cost by more than 15 percent, increases schedule by a year or more, or modifies
scope significantly, a follow-up limited EIR or IPR may be required. Each new NTB period will
have a new baseline to report performance against. Once the NTB is certified, adjustments will
not be allowed annually except the change control process.
The EIR scope for EM cleanup projects will focus on technical scope, schedule, cost, risk
management and project management. The required documentation for the review is defined in
the EM Protocol (reference 6.1).
26 DOE G 413.3-8
9-24-08
The following documentation identified in the Protocol typically does not apply to EM cleanup
projects:
• system functions and requirements document,
• preliminary design drawings and performance specifications,
• results of and responses to preliminary design reviews,
• final design drawings and specifications,
• results of and responses to site final design review, or
• construction planning document.
Table 3 provides information relative to project phase and the expected score derived from the
Project Definition Rating Index (PDRI), a project management tool that provides a numerical
assessment of how well a project is planned. The PDRI has five key areas that are utilized in the
up-front planning stages of each phase. These are:
• cost,
• schedule,
• scope/technical,
• management and planning, and
• external factors.
Each area listed has a rating element defined by the type of project and is applicable to the
particular project or project phase. The project team develops a maturity score for each element
and the resultant score provides a basis for determining that a particular project or project phase
is of sufficient maturity to proceed to the next step. The expected/actual score is not used as a
go/no-go requirement for CD approval, but the score is an important factor in supporting a
decision to proceed to the next phase. For each type of project area, various rating elements
provide a sound indication of project planning maturity at each phase of the project. PDRI
information is available at the following link http://www.em.doe.gov/pages/pdri.aspx.
DOE G 413.3-8 27
9-24-08
Table 3. Critical Decision Targeted EM Cleanup Projects
Definition Rating Index Scores for Each Projects Type
Soil and Groundwater Projects
Critical Decision Critical Decision Description Expected Score
CD-0/CD-1 Mission Need/Proposed Plan 500
CD-2/CD-3 Performance Baseline/Start Work
(Approved to Start ER Work) 1000
Deactivation and Decommissioning Projects
CD-0 Mission Need Justification 400
CD-1/CD-2 Conceptual/Preliminary Design
(Performance Baseline) 900
CD-3 Final Design
(Approved to start D&D) 1000
Stabilization and Disposition Projects
CD-0/CD-1 Mission Need/Alternative Selection N/A—Waived *
CD-2/CD-3 Performance Baseline/Start Execution Scoring TBD
* Note: Future projects and subprojects require implementation of the CD process as delineated
in DOE O 413.3A with appropriate tailoring.
3.1.7 Quality Assurance (QA)
Section 24
EM cleanup projects should follow the guidance in DOE G 413.3-2 “Quality Assurance” for
overall QA guidance and for application of the graded approach. For many cleanup projects the
QA requirements may be embodied in a combination of the implementing organization’s QA
program and other plans and procedures. It is the responsibility of the project team, in concert
with the FPD, to decide if a project-specific quality control (QC) plan is needed. It is suggested
that such a decision be reached by conducting a review of the project activities to determine if
the project’s QA/QC needs are already embodied in existing processes, procedures, and
instructions (e.g., procedures for design, laboratory sample analyses requests, and waste
management shipping and disposal requirements). If such a review indicates a need, then a
project-specific QC plan should be created that identifies the affected activities and specify the
procedures needed for those activities.
28 DOE G 413.3-8
9-24-08
A project-specific QA program and/or QC plan3 should be developed in the following
circumstances.
• There exists unusual conditions or a one-of-a-kind situation that poses a significant
project or safety risk; for example, demolishing a building connected to another
building that will remain.
• It is required by specific environmental regulations or DOE Orders; for example, for
work plans created to meet the requirements of the RCRA and CERCLA QA/QC
project program/plan as defined in the Remedial Feasibility Investigation/Remedial
Investigation (RFI/RI) Program Plan.
• It is considered necessary by organizations participating in the collection and
evaluation of environmental data.
Whether or not a project-specific QC plan is created, there are activities that may require
verification and/or inspection steps (for quality control). One such group of EM activities relates
to safety. A few examples are as follows:
• isolating mechanical and electrical system for worker protection and for facility
deactivation or demolition;
• structural analyses for demolition planning and specification;
• analyses to downgrade a facility’s nuclear or hazard category so as to reduce the
authorization basis and eliminate unneeded technical safety requirements; and
• remediation of waste units, physical removal of wastes, capping inactive waste units,
and inspecting closed waste units.
Additional activities that need verification and/or inspection regardless of a project-specific QC
plan include, but are not limited to the following:
• characterization to show conformance with regulatory drivers and or needed for
baseline planning;
• characterization activities of environmental processes to include the generation,
collection, analysis, evaluation, and reporting of environmental data;
• survey results to record project completion [e.g., Multi-Agency Radiation Survey and
Site Investigation Manual (MARSSIM) method;];
3 DOE O 413.3A states that the project’s application of Quality Assurance is documented in either the organizational
or project-specific Quality Assurance Program; therefore the use of project specific QA plan is not used here.”
DOE G 413.3-8 29
9-24-08
• design, construction and operation of engineered environmental systems such as
collection equipment, systems and facilities for pollution control, waste treatment,
and waste site remediation;
• cleaning, inspecting, testing, maintaining, repairing or modifying of systems or
components;
Section 25
• estimating waste quantities and types;
• procuring, handling, shipping, receiving and storing of material;
• waste characterization for processing and packaging to comply with transport and
disposal regulations;
• documentation of contents, waste form and concentration for compliance with
disposal site waste acceptance criteria;
• supporting decisions as to whether to decontaminate surfaces and/or mechanical
systems to support dose reduction; or for decisions related to decontaminating to
reduce hazardous materials concentrations below regulatory limits; amd
• removing special nuclear material.
3.1.8 Integrated Safety Management System (ISMS)
This section describes the implementation of Integrated Safety Management (ISM) principles
into EM cleanup projects. Requirements on ISMS are described in DOE P 450.4, Safety
Management System Policy, dated 10-15-96, and guidance for cleanup projects is described in
DOE-STD-1120-2005, Integration of Environment, Safety, and Health into Facility Disposition
Activities. DOE-STD-1120-2005 does not apply to new nuclear facility design activities or
major facility modifications as defined in 10 CFR 830, Subpart B. These activities should be
conducted in accordance with DOE O 420.1B, Facility Safety, dated 12-22-05, DOE-STD-1189,
and 10 CFR 851.
The ISMS process is applied to all CDs and the Office of Health, Safety and Security (HSS)
activities and documentation as defined in the following sections.
Prior to CD-0 (Mission Need):
• Develop inventory of available documents based on existing facilities/sites identified
in the scope of the project to facilitate hazard analysis and project planning.
• Identify the potential hazards and their safety and risk implications in the mission
need statement.
CD-0 to CD-1 (Alternative Selection and Cost Range):
• Develop a Safety Design Strategy (DOE-STD-1189, section 2.3) and integrate into
project planning documentation.
30 DOE G 413.3-8
9-24-08
• Develop/update initial hazard identification and nuclear facility hazard categorization.
Supporting activities may include site walk-downs, employee interviews,
characterization studies, etc. (DOE-STD-1120-2005, section 2.1).
• Determine the set of HSS directives applicable to the project (DOE-STD-1120-2005,
section 2.2, Appendix A).
• Assess existing HSS documents against the proposed scope of cleanup activities (e.g.,
planned end states) (DOE-STD-1120-2005, Appendix C).
• Initiate the preliminary hazards analysis and establish/update an initial list of safety
structures, systems, and components (SSCs) for public and worker protection.
• Determine whether facility scope involves any major modifications in accordance
with 10 CFR 830 and DOE-STD-1189. If so, follow DOE-STD-1189 process for
design and Preliminary Documented Safety Analysis (PDSA) development.
• Determine the qualified safety and health professionals on the Integrated Project
Team necessary to support the FPD.
CD-1 to CD-2 (Performance Baseline):
• Complete a process hazard analysis and update list of safety Structures, Systems, and
Components (SSCs) (see DOE-STD-1120-2005, sections 3 and 4).
• Draft documented safety analysis (DSA) or draft changes to existing DSA (see
DOE-STD-1120-2005, sections 3 and 4).
• Update to cleanup plan (DOE-STD-1120-2005, section 2.2).
CD-2 to CD-3 (Start of Construction):
• Prepare final DSA and technical safety requirements (TSRs) (see
DOE-STD-1120-2005, sections 3 and 4).
Section 26
• Prepare/update health and safety plans (HASPs) or applicable hazard analysis
documents (DOE O 413.3A, 10 CFR 851).
• Finalize cleanup plans (DOE-STD-1120-2005, section 2.2).
CD-3 to CD-4 (Start of Operations or Project Completion):
• Approve DSA/TSR.
• Conduct readiness review or operational readiness review (DOE O 425.1C).
• Commence with operations, where applicable.
3.2 Deactivation and Decommissioning Projects
D&D projects are defined as projects subject to DOE O 413.3A. New construction projects
generally benefit from a large number of “known” attributes relevant to planning, design,
engineering, physical construction (how big, how many floors, how many rooms, etc.), and the
type, size and capacity of systems (process, utility, support systems). Conversely, D&D projects
are frequently characterized by attributes that are unknown until a substantial part of the project
DOE G 413.3-8 31
9-24-08
is conducted. While the end-state (e.g., deactivation and long-term surveillance and maintenance,
demolition, in-situ decommissioning) of a D&D project is generally understood at the onset of
project planning, requisite knowledge of many other conditions, for which characterization
activities are required may not be sufficiently well understood. Examples include types and
extent of contamination, structural integrity and configurations of systems and modifications
within areas that are difficult to access because of radiation or contamination.
Activities essential to a design-build project such as creating drawings, specifications, and other
new construction design products to achieve conceptual, preliminary, and final design stages
associated respectively to CDs 1, 2, and 3 are rarely significant in D&D projects. It is important
that reviewers understand these differences. While there are often minor design-build aspects of
D&D projects, in general, the following are noted:
• There is relatively little traditional design work (of a construction nature) for D&D.
The amount of engineering leading to design drawings and specifications is usually
limited relative to the overall project scope. Such design efforts would be a minor
factor in the CD process.
• D&D involves a significant amount of engineering. The type of engineering
activities, however, is for the most part very different from design-build engineering.
Deactivation of equipment and systems, equipment removal, demolition, operational
safety analysis, and material stabilization are a few examples of D&D engineering. In
addition to the traditional structural, mechanical, chemical and electrical disciplines,
skills required include nuclear safety (including the prevention of inadvertent
criticality) and radiological engineering.
• Activities tend to be heavy in operations and services types of activities and light on
fabrication or new construction, resulting in a labor mix that is unique to these types
of activities. Also, with the exception of decommissioning equipment (e.g.,
excavators, cutting equipment), the need for new equipment is low. The need for
materials can be heavily weighted toward consumable items that may be disposed of
as they may become contaminated and/or processed as radioactive waste. These and
other differences are significant to the basis-of-estimate for project baselines.
• Pre-existing conditions may be extremely variable from facility to facility because of
differences in vintage of construction and the nature of operations that have been
conducted.
Section 27
Many of these differences are the subject of guides associated with DOE O 430.1B. This
guide (DOE G 413.3A-8) is to be used as a supplement to those listed below:
• DOE G 430.1-2, Implementation Guide for Surveillance and Maintenance during
Facility Transition and Disposition, dated 9-29-99.
• DOE G 430.1-3, Deactivation Implementation Guide, dated 9-29-99.
• DOE G 430.1-4, Decommissioning Implementation Guide, dated 9-2-99.
• DOE G 430.1-5, Transition Implementation Guide, dated 2-24-01.
32 DOE G 413.3-8
9-24-08
3.2.1 Critical Decisions
Decommissioning projects may be driven by the regulatory requirements in CERCLA, RCRA
and regulatory agreements with EPA and/or state authorities. Therefore, many of the specific
actions and deliverables called for in DOE O 413.3A have equivalents because of the
CERCLA/RCRA process. The CERCLA/RCRA approval and decision stages for a major D&D
project may differ considerably from the CD milestones for a typical design build project.
Example comparisons of the environmental regulatory decision milestones and deliverables
compared with those in DOE O 413.3A can be seen in the following diagrams, where
deliverables noted therein are tailored to each project:
• Attachment 2, Decommissioning Project Overview (CERCLA Non-Time Critical)
• Attachment 3, Decommissioning Project Overview (typical 413.3A deliverables)
In those cases where decommissioning is a remedial action in lieu of non-time critical, the
workflow process is similar to that shown in Attachment 4 for S&GW. This might be the case
where facility and surrounding soil are combined as one project. These examples do not
specifically apply to a deactivation project because deactivation, as a focused project, is not a
subject of a CERCLA action.
The project deliverables for S&GW projects are shown in Tables 5 and 6. Similar listings can be
applied to decommissioning projects but are not applicable to deactivation projects or the
deactivation phase of an integrated project.
As part of the project tailoring, CD milestones are sometimes combined. Many D&D projects
combine CD-1 and CD-2 or CD-2 and CD-3 when there is relatively little technical development
needed between the two decision points. In these cases, the level of detail described below for
CD-1 and CD-2 is applicable for a combined CD-1/2; and CD-2 and CD-3 is applicable to a
CD-2/3 combined approach. However, in all cases of large and/or complex projects these CDs
should be addressed separately. The DOE O 413.3A requirements from CD-1 to CD-3 are based
on the progression of design from conceptual, to preliminary, to final. As noted, D&D projects
have very little classical design, but have a large content of other than design-build engineering.
The following interpretations illustrate the characteristics of D&D projects:
• CD-0. Approval of Mission Need; a project is authorized either as an individual
stand-alone project, as an inclusive part of a larger PBS, or as a result of a Record-of
Decision, an Action Memorandum, or other agreement resulting from environmental
authorities or a Federal Facility Agreement.
• CD-1. Approval marks the completion of the project definition phase and
selection of an alternative and estimate of the cost range. For a D&D project, this
can be a preferred alternative end state and/or project scope resulting from
environmental decision-making and/or concept development within the DOE. The
design requirements at CD-1 require a Conceptual Design Report (CDR). Most
D&D projects do not involve much traditional design activities. To meet the
intent of CD-1 D&D projects subject to DOE O 413.3A should determine the
expectations and present the concepts of the project work to be conducted. For
Section 28
DOE G 413.3-8 33
9-24-08
some D&D projects, there may be a need to conduct some project activities to
obtain information needed to support detailed planning, engineering and design
before reaching the CD-1 milestone. Prime examples include characterization for
condition assessment and for input to technology development. In these examples,
adequate progress needs to be realized to support meeting the technical challenges
of the project.
• CD-2. Sufficient information has been developed to support formulation of the
Performance Baseline founded on a mature design, a well-defined and documented
scope, a resource-loaded detailed schedule, a definitive cost estimate, and defined key
performance parameters. D&D preliminary design should include decisions and
descriptions of “how” the concepts are to be implemented.
• CD-3. Approval authorizes the project to commit all the resources necessary, within
the funds provided, to execute the project. For D&D this will be authority to start
field activities. Final “design” encompasses having work packages, instructions,
and/or procedures ready for implementation.
• CD-4. Provides authorization for start of operations or project closeout. For D&D
projects, this will generally verify that the specified project end-points have been
established and the facility end state has been achieved.
At some sites, the critical decision process is exercised at the PBS level that encompasses several
facilities versus the individual D&D Projects at the facility level. However, for a major facility
project (per DOE O 413.3A total project cost criteria) within a PBS, planning, engineering and
baseline development should be conducted to meet the intent of DOE O 413.3A for the CD
process.
It is important to understand that many D&D projects vary with regard to conducting
engineering/design well after CD-3 and initiating fieldwork well before CD-3. Many
engineering and design deliverables for specific activities are provided well after project
implementation has started but sufficiently in advance of their actual need. This is
acceptable for activities that are well known and for which the ability to create a high
confidence project baseline does not rely on their detail. In addition, many facilities have
operational requirements (e.g., to maintain safety) that are to be conducted regardless of the
timing of the CD process. Similarly, some D&D projects are funded for activities to be
initiated in the field prior to completion of the CD process. These include activities that are
necessary to define the project (e.g., characterization), conducted under operations budgets
(e.g., removal of nuclear materials, flushing of systems containing hazardous chemicals,
etc.), and those for which the scope, schedule, and cost are well understood (e.g., stand-alone
equipment removal, permanent shutdown, road grading for heavy equipment access, isolation
of a piping system).
It is a key responsibility of project management to meet the intent of the CD process while
necessarily conducting design activities and fieldwork in the sequence not envisioned by
DOE O 413.3A. This responsibility is most important with regard to the CD-2 objectives of
creating a high confidence project baseline.
34 DOE G 413.3-8
9-24-08
3.2.2 Deactiviation and Decommissioning Engineering Activities
Section 29
EM has prepared guidance entitled “Tailoring and Decommissioning Engineering /Design
Activities to the Requirements of DOE Order 413.3A.” The guidance has been created to address
in detail how the objectives of Conceptual, Preliminary, and Final Design as required by the
Order can be met for D&D projects. The theme of this guidance, is to start early development of
D&D projects’ technical detail to create a comprehensive technical project concept at CD-1, to
increase the level of detail sufficiently to provide a reliable scope, schedule, and cost
performance baseline at CD-2, and to be ready for implementation at CD-2 or CD-2/3.
This tailoring document describes engineering/design output for 41 typical D&D activities. It
then addresses project management regarding decisions for thelevel of detail needed for
engneering at various phases of D&D projects, provides a process for identifying significant
project activities that would require detailed engineering and design development to support a
baseline, and includes sample ines-of-inquiry for reviewers of D&D projects.
3.2.3 Baseline Development
A complicating factor in developing the baseline for a D&D project is that because of difficulty
of access or interfering structures, knowledge of important physical conditions can only be
obtained when the project proceeds to the point necessary to collect requisite characterization
data. Then modifying the project baseline can redirect project activities, change schedules,
modify the sequence of work, necessitate resource allocation, etc. The potential for these
variations should be recognized in the project risk and contingency planning efforts.
In addition, the following specific differences should be noted for baseline development.
• To the degree possible, baseline development should be based on activity-based
schedules and estimates. However, some D&D project elements are estimated as
level-of-effort because the labor is for operations and/or provided by support
organizations that conduct a wide variety of tasks not associated with work
breakdown structure elements at an activity level. Examples include plant operations,
nuclear safety engineering, health and safety oversight, and project controls. Project
reviewers should recognize that some level-of-effort elements are unavoidable for
developing a D&D project baseline.
• The costs of packaging, shipping, and disposing of waste and scrap/salvage are very
significant for almost every D&D project. Because of the importance of waste in a
D&D project, further details of baseline development are included in section 3.2.4.
• Estimating D&D field activities is somewhat different from that for design-build
projects. The latter are characterized by decades of developing unit cost factors for
construction and installation of facilities and equipment. Estimated costs for D&D
are more often developed by conducting walk downs and projecting the skills
required, type of and number in a crew, and duration (e.g., number of days) to
conduct each activity. In addition, parametric estimates are used (e.g., unit cost per
building gross square feet) where site-specific experience has collected data for a
DOE G 413.3-8 35
9-24-08
class of buildings, typically based on facility nuclear safety category, type of
construction, and nature of its contamination.
3.2.4 Performance Measurement
Section 30
Performance metrics for D&D projects vary considerably from design-build projects. The
following three types of performance measurements have proven useful. These are not intended
to be exclusive of other methods that project management may choose.
• End-Points. The end-points method is a very important process for specifying the
conditions to be achieved for a D&D project. The method was derived for DOE
projects in the 1990’s as a systematic way to specify facility deactivation because
construction specifications for the most part do not apply. End-points can also be
specifications for demolition and in-situ decommissioning projects. End-points for
deactivation or in-situ decommissioning will generally be more elaborate than for
demolition.
• Work Sets. The work sets approach for building cleanout can also be used for
progress metrics. A work set is a definition of a bounded incremental scope of work;
for example, removal of a set of equipment in a given area of a building.
• Quantitative Metrics. Quantitative characteristic of D&D projects; that is, units of
measure relevant to specific activities, provide useful performance metrics. Examples
include volume (cubic yards) of soil removed, area (square feet) of
asbestos-containing siding removed; individual or numbers of equipment removed
such as glove boxes and hoods, etc.
3.2.5 Waste Management for Deactivation and Decommissioning
The effective products of D&D projects are industrial, hazardous, and radioactive waste, and
scrap/salvage materials. For all but the simplest projects, waste planning is essential. The costs
of packaging, shipping, and disposing of waste and scrap/salvage can be as much as 40 percent
of a D&D project. Planning should consider factors such as the variability in waste constituents,
limited choice of disposal sites, landfill regulations that apply to other than radioactive waste,
transport through local communities, the DOE metals moratorium, several of which are existing
conditions that cannot be known until well into the project. A cost-benefit analysis for
decontamination vs. direct product waste disposal will often influence technical approaches and
options.
This guidance focuses on the relation of waste management planning to CD stages and
considerations of waste during baseline development.
3.2.5.1 Waste Management Planning for Deactivation and Decommissioning Projects
For a D&D project, the approach to waste management relative to CD points should be as
follows:
36 DOE G 413.3-8
9-24-08
• At CD-0, the primary objective is to recognize the degree to which waste processing
and disposal will be significant project activities. To understand the overall project
cost, a gross estimate of the waste volume by type (addressed below) and a rough
order of magnitude cost estimate should be included in the overall cost profile.
• At CD-1/CD-2, project waste planning results should be available to address the
topics in Table 4. The results of waste planning provide the basis for activity-based
schedules and cost estimating for waste management (See section 3.2.4.2).
• At CD-3, revise the project baseline from new information or revised assumptions.
• At CD-4, the project summary report is generated, including project waste statistics.
Table 4. Waste Planning
Subject Purpose
Waste types and quantity estimates
Waste estimates by type and quantity are the key
assumptions for input to the project scope. These
assumptions/estimates are needed for all the following
subjects in this Table.
Section 31
Constraints
Address constraints and issues that affect cost and project
schedule. Examples include waste acceptance criteria,
available disposal sites, and the DOE Metals Recycle
Suspension
Processing required for removal Plans and assumptions are needed for input to the project
schedule and basis of estimates.
Processing and characterization for
packaging; packaging by waste type
Plans and assumptions are needed for input to the project
schedule and basis of estimates.
Transportation mode by waste type
Plans and assumptions are needed for input to the project
schedule and basis of estimates (e.g., rail, truck, or a
combination).
Disposal destinations Affects packaging and transportation plans. Provides input
to the project schedule and basis of estimates.
Organization The organization and individuals that will directly manage
the project’s waste are input to the PEP.
Waste related trade studies Results used for project decisions that affect the baseline.
Verifications required
Identify review requirements of waste characterization
result to ensure that transportation and disposal criteria are
met. In effect this is the QA part of waste management.
Uncertainties
Identify inability to obtain information that can potentially
affect project schedule and cost if the related assumptions
prove to be incorrect.
Project risks Identify any significant project risks associated with waste
management.
DOE G 413.3-8 37
9-24-08
3.2.5.2 Project Baseline Development Related to Waste
Waste Management Baseline for projects that will generate a large quantity of waste, it may be
necessary for a project to assign a dedicated staff to manage, coordinate, and schedule material
package characteristics, on-site staging management, and status of shipments. Such staffing
needs should be recognized in the baseline development.
The costs of waste retrieval, conditioning, packaging, shipping, and disposal are major elements
of most D&D projects. For example, significant expenses can be incurred with procuring
certified waste containers and characterization of the loaded waste to demonstrate compliance
with disposal facility waste acceptance criteria. For all D&D projects, as well as other types of
EM projects, a separate WBS element should be considered for these activities. Therefore, the
WBS structure for a project should have project waste as a Level 2 WBS element. Figure 4
illustrates a five-level WBS that represents a project with a comprehensive assortment of waste
types.
Figure 11. Example of a WBS Structure for Deactivation and
Decommissioning Project Waste
The bases for elements beneath Level 2 in this figure are described below:
• At Level 3, legacy refers to wastes that were generated prior to start of the project. In
general, such waste will have been quantified and characterized. Project-generated
waste refers to wastes that will be generated during the course of the project as a
result of processing, cleanup, material stabilization, dose reduction, equipment
removal, radiological control, and other similar activities. The reason for the two
separate WBS elements is that project-generated waste involves a larger number of
activities, is likely to have more schedule elements, and its basis of estimates will be
different than for legacy waste.
Waste
Project
Legacy Waste Project Generated
Waste
Level 1,
Project
Level 2,
Major Element
Level 3,
Waste Source
Level 4,
Waste Type
Level 5,
Activities
LLW Contact
Handled TRU
Section 32
Remote
Handled TRU Mixed.
Processing,
Characterizing, &
Packaging
Shipping Disposal
Hazardous Industrial.
38 DOE G 413.3-8
9-24-08
• Level 4 elements address each type of waste. Only the waste types that exist for the
project should be included. The reason for separate planning activities is wide
variations in costs for each waste type. Also, since overall project waste activities
represent a large fraction of the project, progress, cost, and earned value are all likely
to be reported at this level.
• Level 5 elements are the root-level activities conducted for each waste type. The
basis for scheduling and estimating each activity will be different for each waste type.
Characterization at this level is for packaging and handling the waste. Overall
characterization within a facility should be addressed elsewhere.
Projects in which a significant scope of work includes cleanout and/or equipment removal that
generates waste should manage these as separate WBS elements from the waste WBS. For
example, the removal of substantial equipment (e.g., glove boxes) or material (e.g., massive
shielding) can generate a substantial amount of waste. However, the removal activities are
distinct from the waste handling activities. Therefore, these two unique tasks should be
scheduled and estimated separately.
Processing of liquid or gaseous waste are operational activities and not similar in nature to those
for waste destined for disposal locations. Both of these types of activities can be major project
elements and should be addressed in establishing a baseline.
3.3 Soil and Groundwater Remediation Projects
DOE O 413.3A defines S&GW remediation projects as environmental restoration. The remedial
action activities require a different approach to establish the information relative to CD
development. Environmental restoration projects begin with site evaluation, historical data and
information reviews, interviews with employees and former employees and research of previous
activities at the location. Information is gathered during the CD-0/1 phase to enable the
development of subsequent CD-2/3 project phases. The exact location, extent of contamination,
contaminant behavior, accurate localized geological information, and many other attributes are
not sufficiently understood at the onset of the project planning. These attributes generally evolve
as the project planning matures and further develops as the remedial activities progress.
Consideration of several alternatives and the application of a diligent, systematic process to
identify, select and/or implement new technologies that could be deployed for the remediation of
S&GW, and negotiating cleanup requirements with the regulators are a continuing part of the
cleanup process.
3.3.1 Critical Decisions
The CD documents are formal determinations or decisions at specific points in a project that
allow the project to proceed to the next phase and commit resources. S&GW remediation
projects are driven by the regulatory requirements in the CERCLA and RCRA and in regulatory
agreements such as the FFA established with EPA and/or state or tribal authorities. These
projects require a decision process that supports regulatory requirements to meet mandated
performance periods. The CDs should be combined (tailored) to match the project’s
developmental process that considers the regulatory and legal requirements.
DOE G 413.3-8 39
9-24-08
Section 33
As an example, combining CD-0 and CD-1 steps should be considered for these projects and the
information submitted at the same time in support of the regulatory process. CD-2 and CD-3 steps
should be combined to facilitate the regulatory requirement of remedial action start within 15
months of the signed Record of Decision (ROD). A time line showing the correlation between the
CD points and regulatory documents is provided in Attachment 4.
For S&GW remediation projects, the CD process should proceed as follows:
CD-0, Approve Mission Need, and CD-1, Approve Alternative Selection and Cost
Range/Proposed Work Plan, are combined.
• CD-0/1 (Combined) Mission Need/Proposed Work Plan. Complete restoration
screening process (preliminary assessments/site investigation) and need assessments.
Mission need for S&GW remediation is established through legally enforceable
agreements such as the FFA and various regulatory permits, direction and remediation
processes based on RCRA and/or CERCLA law that are subject to HQ concurrence.
These documents are consistent with goals outlined in DOE strategic plans and thereby
establish mission need and constitute CD-0 or CD-0/1 when combined.
To integrate the requirements of the RCRA and CERCLA programs, the DOE, EPA
and the affected states/tribes entered into a legally enforceable agreement (FFA). The
FFA establishes the primary requirements for effecting remedial activities at
contaminated waste units, thus achieving comprehensive clean up and closure. DOE
submittal of the FFA Appendix E and/or DOE submittal of a RCRA Permit
Application, both requiring the DOE site manager’s certification, should constitute
CD-0 “Mission Need” approval.
CD-2, Approve Performance Baseline, and CD-3, Start fieldwork are combined.
• CD-2/3 (Combined) Perform Baseline Start/Remedial Action. Start fieldwork. This
activity generally equates to the construction phase of a conventional project. The
updated cost and schedule baselines form the basis for the review and approval of the
CD–2/3 packages. Refer to subsequent sections for key activities associated with CD
2/3 document development.
CD-4, Approve Project Completion. Approve Start of Operations/Project Closeout (Project
Transition/Closeout Phase).
• CD-4 marks the end of the execution (construction) phase for a project and transition
to operations and/or to post closure care. In the RCRA/CERCLA regulatory process,
upon completion of construction activities (including startup, as appropriate), a waste
unit walk down is performed with the regulators for approval of implemented actions.
Successful completion of the walk down and any other checklist actions are
documented in the Post-Construction Report (PCR) generated by DOE.
For environmental restoration projects that require continued operation of remedial systems or
require post-closure care, the CD-4 document is prepared after turnover and documents the
40 DOE G 413.3-8
9-24-08
turnover to operations of the remedial facility or to the organization for post-closure care or
long-term stewardship. Regulator-approval of the Operations and Maintenance Plan (O&M)once a
remedy has been put in place and/or the regulator's determination that the remedy is operating
properly and successfully (OPS) may be required. The PCR is submitted to the regulatory
agencies for approval. After operation of the remedial system is complete, the remedial action
completion report (RACR) is submitted to the regulatory agencies for approval. (Note:
Completion could be many years after the system is constructed and placed into operation.)
Section 34
For environmental restoration projects that do not require continued operation of remedial
systems, the CD-4 process marks the end of all activities at the waste unit. The PCR and RACR
are combined into a single document (PCR/RACR) and submitted to the regulatory agencies for
approval. For sites where a remedial action must continue to operate, post-EM Completion the
CD-4 can be submitted upon attainment of EM Completion (which may include an approved
O&M Plan and an OPS determination from the regulators).
Each approved PCR/RACR for individual waste units constitutes a CD and supports the
development and approval of the final CD-4 documentation. The documentation is submitted to
the regulatory agencies in accordance with the regulatory approved implementation schedule.
Through the incremental completion of waste units, and ultimately area completions, the desired
end state is accomplished.
The documents listed in Tables 5 and 6 are provided as a guide to assist the FPD in identifying the
regulatory documents under CERCLA and RCRA that may be utilized to meet the requirements of
DOE O 413.3A. This list is not all-inclusive but illustrates the relationships among the major
documents required in DOE O 413.3A. It should be noted that other regulatory document
requirements not related to project management are not shown or discussed in this guide.
3.3.2 Supplemental Information
The following is provided as additional information relative to the correlation of regulatory
required documentation and the requirements identified in DOE O 413.3A. This information is not
all-inclusive and there are opportunities to combine various regulatory documents to expedite the
regulatory approval process. The combining of documents can affect the normal review and
submittal of CD packages. The project director and the IPT should consider the combining
process when developing the CD documentation.
Regulatory documents required under RCRA/CERCLA contain the same or similar information as
required under DOE O 413.3A. These documents may be utilized to fulfill those requirements. In
certain instances only a portion of the DOE O 413.3A requirements are covered. In those cases,
the FPD should supplement the regulatory document with the information to fulfill the
DOE O 413.3A requirement.
Overview of Core Team Scoping Process
Project scoping is conducted at various points in the RCRA/CERCLA investigative
process to build consensus on the path forward for the project. A project core team
consists of representatives from the DOE, EPA and state environmental agency staff who
DOE G 413.3-8 41 (and 42)
9-24-08
are responsible for project scoping and response action decision-making. Scoping consists
of communicating existing information (documented in project scoping summaries)
throughout the project life-cycle to ensure that the project core team and supporting
technical team share a common understanding of site conditions and cleanup strategies.
The intention of frequent scoping is to establish a systematic process for project
communication and technical agreement by which the formal documentation is a result of
collaboration. Throughout the scoping process, the project core team employs the
Principles of Environmental Restoration as a guide for establishing a more effective
approach to remedial decision making.
Additional information on the Principles of Environmental Restoration can be found at the
following locations:
Section 35
http://www.hss.energy.gov/nuclearsafety/nsea/oepa/training/restoration/
http://www.epa.gov/correctiveaction/curriculum/download/env-rest.ppt#13
The emphasis on each scoping meeting is a thorough presentation of the most current
project information, a shared technical understanding of conditions and problems, and
robust questioning of the technical information to ensure confident real-time
decision-making. The outcome of scoping will be alignment of DOE, EPA, state agency,
and contractor staff with respect to the following decisions:
• presence/absence of a problem that warrants remedial action,
• remedial action objectives (RAO)
• scope of the problem, and
• response actions.
These decisions are addressed for each Operable Unit (OU).
Data Quality Objectives
The data quality objective (DQO) process is an important tool for project management and
planners to determine the type, quantity and quality of data needed for remediation project
decision making. DQOs are qualitative and quantitative statements derived from the
application of a systematic approach to data collection. The DQO process follows seven
steps; the output of each step provides input to the subsequent step. Over the course of the
effort, some steps may be iterative. A complete DQO process will provide added assurance
that the type, quantity and quality of environmental data used in decision-making is
appropriate for the intended application. Additional information on the DQO process is
available in the EPA document, EPA QA/G-4, “Guidance for the Data Quality Objectives
Process.”
D
O
E G
413.3-8
43 (and 44)
9-24-08
Table 5. Cleanup Project - Phases, Requirements and Equivalent Project Management Documentation
PLANNING PHASE
Baseline
Management
Project Management
(Critical Decisions may be combined as one
decision)
Environmental Management Cleanup
CERCLA RCRA Facility Disposition
Planning Phase
Initiation
Phase CD-0
Approve
Mission Need
• Identify Program
Performance gap
• Identify need in terms of the
mission, purpose, capability,
schedule and cost goals, and
operating constraints
• Preliminary Assessment/Site
Inspection (PA/SI)
• Federal Facility Agreement/
Interagency Agreement
• RCRA Facility Assessment
Report (RFA)
• Federal Facility Compliance
Agreement
• Facility Assessment (Site
Wide Infrastructure Long
Range Plan)
Establish Integrated Project
Team
Establish Project and Core Team Establish Project and Core Team
Definition
Phase
Critical
Decision-1
Approve
System
(Project)
requirements
and
alternatives,
Conceptual
Design
Report
Pre-conceptual Design and
Conceptual Design includes:
• Project Risk Management
Plan
• Alternative Analysis
• Environmental Compliance
• Waste Management
• Quality Assurance
• Value Engineering
• Safeguards and Security
Plans
Preliminary Baseline Range
includes:
Project Requirements
Alternatives Analysis Process
Technical Scope
High-Level/Summary Schedule
Cost Estimate Range
Remedial Investigation/Feasibility
Study (RI/FS) includes:
• Scoping the RI/FS
• RI Site Characterization
• RI: Baseline Risk Assessment
(supplement with a project risk
management plan)
• RI Report
• FS: Development and screening
of alternatives
• FS: Detailed Analysis of the
alternatives
• FS: Treatability Studies
• FS Report
Remedy Selection includes:
• Identifying the preferred
alternative
• Statement of Basis
• Corrective Action Plan
• VE, QA
RCRA Facility Investigation
(RFI) includes:
• Scoping the RFI
• RFI: Work Plan
• RFI: Site Characterization
• RFI Report (supplement with
Section 36
a project risk assessment
plan)
Corrective Measures Study
(CMS) includes:
• Scoping the CMS
• CMS: Work Plan
• CMS Report
Remedy Selection includes:
• Identifying the preferred
alternative
• Statement of Basis
• Corrective Action Plan
• VE, QA
Facilities Characterization
Phase includes:
Develop Mission
Alternatives
NEPA (CX, EA, EIS)
Sampling and Analysis Plan
Characterization Work Plan
Characterization Report
Develop Risk Assessments
and Impacts (supplement
with a project risk
assessment plan)
Develop Preferred
Alternative
Remedy Selection
includes:
Engineering
Evaluation/Cost Analysis
Draft Action Memorandum
VE, QA
Acquisition Strategy Acquisition Strategy Acquisition Strategy Acquisition Strategy
Preliminary Project Execution
Plan
Proposed Plan and Draft Record of
Decision
Public participation
Define Decommissioning
Work Plan
Identify Project Endpoint Define risk-based end state that is
consistent with intended future use
Define risk-based end state that is
consistent with intended future
use
Define risk-base end state
that is consistent with
intended future use
D
O
E G
413.3-8
45 (and 46)
9-24-08
Table 6. Cleanup Project - Phases, Requirements and Equivalent Project Management Documentation
PERFORMANCE PHASE
Baseline
Management
Project Management
(Critical Decisions may be combined as one decision)
Environmental Management Cleanup
CERCLA RCRA Facility Disposition
Performance
Phase
(Performance
Baseline)
Execution Phase CD-2
Approved
Acquisition
Performance
Baseline, Final
Design Report
Performance Baseline is the
original baseline for the
project that defines;
• Performance parameters
• Technical scope
• Schedule
• Cost
Final Design Includes:
External Independent Review
(EIR ) Independent Project
Review (IPR)
Final ROD
Remedial Design/Remedial
Action Implementation Plan
(RD/RAIP) includes:
• Cost and Schedule
• Waste Management
• Contractor/Subcontractor
strategies
• Independent Field Office and
HQ Assessments
• Land Use Control
Implementation Plan
Final RCRA Permit
Modification
Corrective Measure
Implementation Plan
includes:
• Cost and Schedule
• Environmental
Compliance
• Waste Management
• Public Participation
• Independent Field Office
and HQ Assessment
Final Decommissioning
Work Plan includes:
• Environmental
Compliance
• Cost and Schedule
• Waste Management
• Environment, Safety and
Health
• Safety Analysis Report
• Quality Assurance
• Safeguards and Security
• Public Participation
• Independent Field Office
and HQ Assessments Final Project Execution Plan Final RD/RAIP Final CMP
Execution Phase CD-3
Approve Start of
Construction
(Remediation)
Construction • Execute RD/RAIP
• Independent cleanup
verification per Work
Plan/ROD
• Execute CMIP
• Independent cleanup
verification per RCRA
Permit/CMIP
• Execute D&D Work Plan
• Independent cleanup
verification per Work Plan
Transition/Closeout
Phase CD-4
Approved Project
Transition, Project
Closeout
• Final/Financial Closeout
• Site/Facility/System/Transitio
n
• Transition/Acceptance
Criteria
• Begin beneficial occupancy
• Begin initial or full operating
capability
• Transition to LTRA
• Field Demobilization
• Final RA report
• Notice of Deletion from
NPL, if required
• Operation and Maintenance
plan
• ROD Reviews
• Field Demobilization
• Corrective Measures
report
• Operation and
Maintenance plan
• Post-Closure Inspection
and Maintenance plan
• Periodic Corrective Action
reports
• RCRA permit renewals
Section 37
• Demobilization
• D&D Final report
• Post Closure Monitoring if
necessary
Post Completion
Phase
(N0 CD)
Transition and Start
of Long Term
Stewardship
• CD-4 accomplishes transition
of completed short-term
cleanup to long-tern response
action, institutional controls
and other needed caretaker
actions.
• Site/project transferred from
EM to the Lead Program
Secretarial Office or other
receiving entity.
• Post Construction Report
• Site Completion Report
Execute the actions of the
disposition baseline (DOE
Operations 430-1B)
Project/Site Transfer Plan Site Completion Report Closure Report Field Decommissioning
Report
DOE G 413.3-8 47
9-24-08
3.3.3 Baseline Development
The S&GW remediation project baseline development process begins in the early stages of
planning, leading to project performance baseline. Documents to be prepared include cost
estimates, schedule, scope and historical baseline information. These documents should be
maintained throughout the project life cycle and controlled through the change control process.
The S&GW project baseline is managed through the utilization of proven project management
systems, including an EVMS. The system is the primary cost and schedule management tool
utilized for external and internal project management objectives.
The WBS or similar grouping organizes and defines the total scope of the project. The primary
objective of this structure is to define and arrange all authorized work at prescribed levels for
project management, data collection, and reporting.
3.3.4 Performance Measurement
An essential component of project management is the measurement of project progress. Soils
and groundwater remediation project performance is measured by the number of actual
completed waste units against the number of planned completions and the regulatory milestones,
as applicable. Soils and groundwater remediation provides reporting information and project
status as necessary to meet the requirements of the EVMS for cost and schedule information.
This system is the primary cost and schedule management tool used to meet external and internal
project management objectives.
Progress toward these measures, milestones and any proposed changes to them are reported as
follows:
• remediation of all waste units will be completed;
• waste unit and source unit “remediation complete” is defined as—
- completion of the remedial action as documented in the submittal of a
post-construction report or a final remediation report and
- agreement from the regulatory agencies that no further action (NFA) is the
appropriate remedial action for a waste unit (including site evaluation areas) as
documented through the issuance of a Record of Decision (ROD) or concurrence
from the regulatory agencies on NFA for site evaluation areas;
• remedial actions at all sources that contributed to the groundwater contamination
have been completed; and
• groundwater unit “remediation complete” is defined as—
- construction or remedial system is complete,
- remedial action is implemented, and
48 DOE G 413.3-8
9-24-08
- progress toward remedial goals can be demonstrated.
Milestones reflect waste unit completions by the end of the program cycle. The proposed
baseline spreads the milestones over the life of the program, integrates decommissioning
activities with S&GW activities to complete clean up in entire areas.
Section 38
Record of Decision milestones for S&GW units are established in accordance with the regulatory
schedule and the program end date. Milestones can change as the regulatory agreement or
regulatory driven document schedule modifications occur.
Project milestones are established to align with the near term completion strategy established for
each project and are included in the Project Execution module of IPABS.
3.4 Stabilization and Disposition
3.4.1 Critical Decisions
Most S&D projects are covered by and included in the CD for the EM PBS (life cycle) as
discussed in section 3.1. However, stand-alone programs/projects or sub-projects may require
their own CD process.
For example, when the path forward for the disposition of a material is significantly changed or
modified, a CD process should be used for programs/projects with a NTB of $100M or more.
This threshold of $100M or more should not be applied to surveillance and maintenance or
maintaining the facilities, plants, and systems. The threshold may be applicable to the costs
associated with modifying these facilities, plants, and systems to process the material (e.g.,
engineering [the flow sheet development, safety documentation, etc.], training and qualification
of personnel, additional storage and/or security costs, material processing costs, and any costs
associated with waste streams from these materials). If the disposition of the additional material
is the only purpose for extending the life of these facilities, plants, and systems, then the
surveillance and maintenance costs are to be considered in the $100M threshold for the CD
process. For S&D projects, the CD process should proceed as follows:
New projects being created:
• CD-0, Approve Mission Need
• CD-1, Approve Alternative Selection and Cost Range
• CD-2/3, Approve Performance Baseline and Start fieldwork are combined
• CD-4, Approve Project Completion
For existing projects, when a new NTB is established:
• CD-0/1, Approve Mission need; and Approve Alternative Selection and Cost range
have been waived, because these S&D projects were already in their execution phase
when EM decided to “projectize” them.
DOE G 413.3-8 49
9-24-08
• CD-2/3, Approve Performance Baseline and Start fieldwork are combined.
• CD-4, Approve Project Completion.
These new projects should be appropriately tailored as should all projects.
3.4.2 Baseline Development
S&D projects are driven by the requirements of the EM PBSs (life cycle) in section 3.1. S&D
projects need to take in consideration the same components as traditional projects. Some
additional considerations in developing a baseline for S&D projects are as follows.
• Staffing costs are often driven by minimum control room and watch station
requirements for emergency response teams.
• Surveillance and maintenance costs associated with maintaining the facility, plant
and systems.
• Campaign startup costs associated with the disposition of new materials.
• Material costs (chemicals, glass frit, consumables, etc) associated with running the
process.
• Utility costs associated with steam, water, and electrical requirements.
• Transportation costs associated with shipping material, including special shipping
containers, drums, casks, and special transportation vehicles.
• Costs associated with storage and security requirements for certain materials.
• Cost associated with critical spare parts and replacement vessels and tanks.
3.4.3 Performance Measurement
Section 39
Many S&D projects are process driven and project performance measurements can be developed
based on the metrics identified in Table 2, “Environmental Management Corporate Key
Performance Parameters” in section 3.1.3. In addition to these metrics, other performance
measurement elements are identified below for each type of S&D project.
3.4.3.1 Radioactive Liquid Waste Tank Stabilization and Disposition
• Number of canisters produced, where process costs for a particular waste material are
divided by the number of canisters scheduled. Performance is earned by canisters
produced.
• Planned outages are given a performance value as operations and facility support
personnel efforts will be focused on the outage versus producing canisters.
50 DOE G 413.3-8
9-24-08
• Surveillance and maintenance costs are normally level-of-effort activities. These are
costs associated with maintaining the facility, which are independent of running the
process. These are also known as hotel costs.
• Gallons of liquid waste dispositioned using metric similar to canisters above.
• Tanks cleaned based upon a predetermined value.
• Sludge batches prepared based a predetermined value.
• Safety documentation prepared for a particular waste stream.
• Projects and major modifications are a portion of these S&D projects, but are treated
as traditional projects with respect to performance measurement
3.4.3.2 Nuclear Materials Stabilization and Disposition
• Material campaign preparations are given a performance value.
- modifications,
- training,
- safety documentation,
- shipping requirements, etc.
• Processing these different material campaigns using metric similar to canisters above.
• Surveillance and maintenance costs are normally level-of-effort activities.
• Safety documentation prepared for a particular waste stream.
• Projects and major modifications are a portion of these S&D projects.
• Materials shipped based upon a predetermined value.
3.4.3.3 Spent Nuclear Fuel Stabilization and Disposition
• Cask loading and shipping and cask receiving and unloading.
• Surveillance and maintenance costs are normally level-of-effort activities.
• Safety documentation prepared for a particular waste stream.
• Projects and major modifications are a portion of these S&D projects.
DOE G 413.3-8 51
9-24-08
3.4.3.4 Solid Waste Stabilization and Disposition
• Drum remediation using a metric similar to canisters above.
• Drum shipping using a metric similar to canisters above.
• Safety documentation prepared for a particular waste stream.
3.4.3.5 Waste Disposal Facility Operation
On site waste disposal based upon either a metric or level-of-effort type of activities.
3.4.3.6 Waste and Material Transportation
Number of waste shipments using a metric similar to canisters above
In addition to the metrics above, a component breakdown by PBS type for S&D projects is
provided. Most of these components are taken into consideration to measure true project
performance as the metrics above only account for 20 percent to 50 percent of the costs of each
PBS project.
4.0 ATTACHMENTS
Attachment 1. Environmental Management Cleanup Projects by Major Category
and by Type of Project
Attachment 2. Decommissioning Project Overview (CERCLA Non-Time
Critical)
Attachment 3. Decommissioning Project Overview typical (DOE O 413.3A
products)
Attachment 4. Soil and Groundwater RCRA/CERLA Work Flow Process
Attachment 5. Stabilization and Disposition Project Overview
Section 40
5.0 TERMS AND DEFINITIONS
Capital Assets
Capital Assets are land, structures, equipment, intellectual property (e.g., software), and
information technology used by the Federal government and having a useful life of two or more
years. Capital assets include environmental restoration (decontamination and decommissioning)
of land to make useful leasehold improvements and land rights, and assets whose ownership is
shared by the Federal government with other entities. Capital assets may be acquired through
purchase, construction, or manufacture; a lease-purchase or other capital lease (regardless of
whether title has passed to the Federal Government); or exchange. This Guide does not apply to
land, structures, equipment, intellectual property (e.g., software), or information technology
52 DOE G 413.3-8
9-24-08
acquired by State and local governments or other entities through financial assistance (i.e., DOE
grants and cooperative agreements), or to assets acquired under general plant projects for
maintaining infrastructure at a site (DOE O 413.3A)
Cleanup Subproject
A subproject within a cleanup project PBS will be identified based upon an approved mission
need statement, and is defined as a non-major acquisition comprised of a series of tasks or
activities within a PBS that are related and have a specific objective. Creation of a subproject
is intended to provide enhanced visibility to project elements ( cost, scope and schedule) and
performance/execution analysis and reporting (e.g., EV data), and to provide for future
corporate “what if” planning analysis. Subprojects follow the DOE O 413.3 process, which
includes using a tailored approach for EM cleanup projects. The subprojects may have a
defined scope, cost, and schedule (including end-point); have certified FPDs; and upon
establishment of a performance baseline should be able to report earned value data separately
from other portions of the PBS. In general, the TPC for subprojects will be greater than $20
million and less than $1 billion. Subprojects will not be established for level-of-effort types of
activities; where a PBS has subprojects, the balance of the PBS scope e.g., other
level-of-effort, site infrastructure support, contract fee, management reserve, etc) could be
captured as a separate element, e.g., “balance of PBS.” Examples of subprojects include: the
deactivation and decommissioning of a single or related group of facilities; construction of
temporary facilities and structures to perform a specific cleanup; construction or modification
of fixed facilities with an operational life of less than five years (such as treatment or storage
facilities to support a specific cleanup action).
Contaminated Facilities
Contaminated facilities are those that have structural components and/or systems contaminated
with hazardous chemical and/or radioactive substances. This definition excludes facilities that
contain no residual hazardous substances other than those present in building materials and
components, such as asbestos,-containing material, lead-based paint, or equipment containing
PCBs. This definition excludes facilities in which bulk or containerized hazardous substances,
including radionuclides, have been used or managed if no contaminants remain in or on the
structural components and/or systems (DOE O 430.1B).
Deactivation
Section 41
Deactivation places a facility in a stable and known condition including the removal of
hazardous and radioactive materials to ensure adequate protection of workers, public health and
safety, and the environment, thereby limiting the long-term cost of surveillance and maintenance.
Actions include the removal of fuel, draining and/or de-energizing nonessential systems, removal
of stored radioactive and hazardous materials, and related actions. Deactivation does not include
all decontamination necessary for the dismantlement and demolition phase of decommissioning
(e.g., removal of contamination remaining in the fixed structures and equipment after
deactivation [DOE O 430.1B]). This term is commonly used to describe the activities associated
with removal of equipment for the purpose of hazard mitigation or salvage and reuse and other
DOE G 413.3-8 53
9-24-08
preparatory operations such as utility isolation. The desired end state is a facility that can be
categorized as “inactive” or “shutdown” pending final disposition.
Decommissioning
Decommissioning is the process of closing and securing a nuclear facility or nuclear materials
storage facility to provide adequate protection from radiation exposure and to isolate radioactive
contamination from the human environment. It takes place after deactivation and includes
surveillance, maintenance, decontamination, and/or dismantlement. These actions are taken at
the end to retire it from service with adequate regard for the health and safety of workers and the
public and protection of the environment. The ultimate goal of decommissioning is unrestricted
release or restricted use of the site (DOE O 430.1B)
Decontamination
The removal or reduction of residual chemical, biological, or radiological contaminant and
hazardous materials by mechanical, chemical or other techniques to achieve a stated objective or
end condition (DOE O 430.1B). This applies to all facilities that are being dispositioned.
Demolition
Demolition is described as the dismantling, razing, destroying, or wrecking of any building or
structure or any part thereof (ANSI A10.6). This is a term widely used and understood in the
public domain and applies to all facilities being dispositioned.
Disposition
Those activities that follow the completion of program missions, including but not limited to,
preparation for reuse, surveillance, maintenance, deactivation, decommissioning, and long-term
stewardship (DOE O 430.1B).
EM Completion
EM Completion occurs when: 1) all required short-term response activities at a specific site are
complete (e.g., soil excavation, cap construction, building decommissioning); 2) all required
long-term response measures (e.g., ground water treatment systems) are constructed and
determined to be operational and functional; 3) all necessary documentation is in place (e.g.,
engineering certifications/and verifications, post-closure or operating permits, final site
condition/configuration records); and 4) the site is administratively transferred from EM
responsibility to another DOE, Federal, State or private entity.
Environmental Management Cleanup Project:
EM defines a cleanup project as the entire PBS; however, in some cases the project may be a
portion of one PBS or portions of multiple PBSs. EM is responsible for clearly defining the
composition of each project. The major categories of EM cleanup projects are as follows: D&D
projects, S&GW Remediation, and S&D. These projects have TPCs greater than $20 million
Section 42
54 DOE G 413.3-8
9-24-08
and some in excess of $1 billion. A new cleanup project would be established following an
approved mission need statement requiring environmental cleanup.
Project Baseline Summary
The PBS is defined as the EM designated program scopes containing logical groupings of work
scope, which are projectized through establishing technical scope, cost and schedule baselines,
defining performance metrics, providing financial history, budget request justification and other
information such as programmatic risk and compliance drivers.
6.0 REFERENCES
6.1 “Protocol for Environmental Management Cleanup Projects,” dated April 24, 2007,
Memorandum from James A. Rispoli to Paul Bosco.
6.2 American National Standards Institute/Electronic Industries Association ANSI/EIA
748-A-1998, Earned Value Management Systems
6.3 DOE-STD-1120-2005, April 2005 Standard Integration of Environment, Safety, and
Health into Facility Disposition Activities, Volume 1 of 2,
6.4 “Risk Management Policy,” dated February 23, 2007, Memorandum from James A.
Rispoli to J.E. Surash
6.5 “Protocol for External Independent Review (EIR),” dated June 30, 2005, Memorandum
between EM and OECM
6.6 DOE O 413.3A, Program and Project Management for the Acquisition of Capital Assets,
dated 7-28-06.
6.7 Code of Federal Regulations, Title 7, Agriculture, Part 650 Compliance with NEPA.
6.8 Code of Federal Regulations, Title 40, Protection of Environment, CERCLA, RCRA.
6.9 DOE G 430.1-2, Implementation Guide for Surveillance and Maintenance during Facility
Transition and Disposition, dated September 29, 1999.
6.10 DOE G 430.1-3, Deactivation Implementation Guide, dated September 29, 1999.
6.11 DOE G 430.1-4, Transition Implementation Guide, dated September 29, 1999.
6.12 “Delegation of Acquisition Executive Authority for Office of Environmental
Management Cleanup Projects,” dated August 16, 2007, Memorandum from James A.
Rispoli for Clay Sell.
6.13 “Environmental Management Contingency Policy,” dated February 3, 2005,
Memorandum from Paul Golan.
DOE G 413.3-8 55
9-24-08
6.14 “Policies for EM Operating Project Performance Baselines Contingency and Federal Risk
Management Plans, and Configuration Control,” dated July 10, 2006, Memorandum from
C.E. Anderson.
6.15 “Environmental management Configuration Control Process for Project baselines,” dated
February 13, 2008, Memorandum from Mark Frei.
6.16 DOE-STD-1189-2008, Integration of Safety into the Design Process, dated March 2008.
Table 7. Team Membership
Name Organization
Autar Rampertaap
Team Lead
Office of Project Management Oversight
EM-53
Ken Kawasaki Project Time & Cost, Inc.
C.J. Plummer-Wooley Savannah River Nuclear Solutions
Andrew Szilagyi D&D and Facility Engineering EM-23
Bill Harker Idaho Operations Office
Steve Balone Richland Operations Office
Pramod Mallick Office of Project Management Oversight
EM-53
Tom Longo NA-56
Larry Romine Federal Project Director, Richland
Operations Office
Amiya Das Office of Groundwater and Soil Remediation
EM-22
Joe Knick
EFCOG Lead
SRS, WSRC, Washington
Group International
Chuck Negin PEC-EFCOG
Tony Eng Nuclear safety HS-20
Todd Lapointe Nuclear safety HS-20
Pete Zionkowski SRS, WSRC, Bechtel
Casey Knapp SRS, WSRC, Bechtel
Greg McCallum SRS, WSRC, Bechtel
D
O
E G
413.3-8
A
ttachm
ent 1
9-24-08
Page 57 (and Page 58)
Example-EM Cleanup Projects by
Major Category and by Type of Project
EM Lifecycle Scope (PBS)
Deactivation and
Decommissioning
Section 43
Soil and Water
Remediation
Stabilization
and Disposition
PBS-0011 Nuclear Materials S&D
PBS-0012 Spent Nuclear Fuel S&D
PBS-0013 Solid Waste S&D
PBS-0014c Radioactive Liquid Waste
Tank S&D
PBS-0080 Operate Waste Disposal
Facility
PBS-0090 Waste & Material
Transportation
PBS-0030 Soil and Water
Remediation
PBS-0040 Nuclear D&D
PBS-0050 Non-Nuclear D&D
S&WR PBSs S&D PBSsD&D PBSs
Attachment 1-EM Cleanup Projects by Major Category and by Type of Project
DOE G 413.3-8 Attachment 2
9-24-08 Page 59 (and Page 60)
Attachment 2-Decommissioning Project Overview (CERCLA Non-time Critical)
• Project Performance Baseline
DEFINITIONDEFINITION EXECUTIONEXECUTION ACCEPTANCEACCEPTANCE LTSLTS
Pre -decision Phase
(Operations – S&M)
PHASES PHASES
CRITICAL
DECISIONS (O 413.3A)
G 430.1-4
Regulatory
Actions
MAJOR
ACTIVITIES
MAJOR
DELIVERABLES
START
PROJECT
Alternative Selection
FINAL DESIGN CONSTRUCTION
Disposition Plan
END
PROJECT
APPROVE START OF
OPERATIONS OR
PROJECT CLOSEOUT
CD-4
Close Out Long Term
Surveillance
APPROVE
MISSION NEED
CD - 0
APPROVE START OF
CONSTRUCTION
CD-3
3/13/07 Rev. A
Note: Deliverables from each phase are
input to subsequent phases
APPROVE ALTERNATIVE &
PERFORMANCE
BASELINE
CD-1 & CD-2
UP UP --FRONT FRONT
PLANNINGPLANNING
Final Engineering &
Planning
Decommission
Inputs
• Ten Year Site Plan
(TYSP)
• Surveillance &
Maintenance Plan
• Federal Facilities
Agreement
Problem
Discovered
Facility Due for
D&D (TYSP)
Gather
Information
Assess Need for
Decommissioning
Decommission?
Continue S&M No
Prepare
Scoping Document &
CD -0 Package
• End Point Determination
• Scoping Document
• Engineering Evaluation
• Initial Technology Needs
• Initial Project Risk Identification
• Draft Notification Letter
Evaluate Existing Data
Inform/Involve Public &
Stakeholders
Develop Char.
Plan Conduct
Characterization
Conduct ESH Risk
Assessment
Conduct Safety
Assessment
Yes
Evaluate
Alternatives
Select Preferred
Alternative
Public
Input Response to
Comments
Finalize
Selection
Decommissioning
Plan
HASP
Project Documents
• Cost Estimate
• Schedule
• Acquisition Plan
• Proj. Risk Asses.
Prepare Package
CD-1 / CD-2
• Engineering Evaluation Cost Analysis Report
• Permit Plan
• Characterization Plan (EPA Approval)
• HASP for Characterization
• ESH Risk Assessment
• Safety Assessment
• Admin. Record for CERCLA
• Community Relations Plan
• Facility Baseline Report
• Form Integrated Project Team (IPT)
• Technology Development Plan
• Project Risk Assessment
• Draft Action Memorandum
• Preliminary Project Life Cycle Baseline
• Decommissioning Plan
• HASP
• End Point Determination
• Cost Estimate
• Schedule
• Acquisition Plan
• Project Risk Assessment
• Technology Development Plan
• Project Performance Baseline
Finalize
Engineering
Details
Develop Work
Plans
Finalize Project
Documents
Readiness
AssessmentNo
Prepare CD-3
Package
Place Contracts
Perform
Decommissioning
Phase Out S&M
Confirmatory
Survey
Decom.
Complete?
Close Out
Project
Yes
Yes
No
• Decommissioning
Final Report
• Post
Decommissioning
Action Plan
• Independent
Verification Report
• Work Plans
• Readiness Assessment
•
• Cost Estimate
• Schedule
• Project Risk Assessment
Long Term
Surveillance
Implement Post
Decom. Action
Plan
•
No
Prepare
Scoping Document &
CD -0 Package
• End Point Determination
• Scoping Document
• Engineering Evaluation
• Initial Technology Needs
• Initial Project Risk Identification
• Draft Notification Letter
Section 44
Evaluate Existing Data
Inform/Involve Public &
Stakeholders
Develop Char.
Plan Conduct
Characterization
Conduct ESH Risk
Assessment
Conduct Safety
Assessment
Yes
Evaluate
Alternatives
Select Preferred
Alternative
Public
Input Response to
Comments
Finalize
Selection
Decommissioning
Plan
HASP
Project Documents
• Cost Estimate
• Schedule
• Acquisition Plan
• Proj. Risk Asses.
Prepare Package
CD-1 / CD-2
• Engineering Evaluation Cost Analysis Report
• Permit Plan
• Characterization Plan (EPA Approval)
• HASP for Characterization
• ESH Risk Assessment
• Safety Assessment
• Admin. Record for CERCLA
• Community Relations Plan
• Facility Baseline Report
• Form Integrated Project Team (IPT)
• Technology Development Plan
• Project Risk Assessment
• Draft Action Memorandum
• Preliminary Project Life Cycle Baseline
• Decommissioning Plan
• HASP
• End Point Determination
• Cost Estimate
• Schedule
• Acquisition Plan
• Project Risk Assessment
• Technology Development Plan
•
Finalize
Engineering
Details
Develop Work
Plans
Acquisition
Plan
Finalize Project
Documents
Readiness
AssessmentNo
Prepare CD-3
Package
Place Contracts
Perform
Decommissioning
Phase Out S&M
Confirmatory
Survey
Decom.
Complete?
Close Out
Project
Yes
Yes
No
• Decommissioning
Final Report
• Post
Decommissioning
Action Plan
• Independent
Verification Report
• Work Plans
• Readiness Assessment
• Acquisition Plan
• Cost Estimate
• Schedule
•
Long Term
Surveillance
Implement Post
Decom. Action
Plan
• Decommissioning Final
Report – Draft
• Post Decommissioning
Action Plan - Draft
• Facility Decom. Evaluation (FDE) Concurrence
• NEPA Determination • Sampling Plan – Approval by EPA & State
• Regulator & Public comment on Engineering
Evaluation & Cost Analysis
• NEPA
• Regulator & Public
comment on Decom Plan
• NEPA
• Approval by EPA &
State of Final
Report
DOE G 413.3-8 Attachment 3
9-24-08 Page 61 (and Page 62)
Attachment 3-Decommissioning Project Overview
• Perform Project & Detail Design
Phase T&PRA
• Set Project Execution Strategy
• Review Alternatives
• Identify Project Codes, Standards
and Procedures
• Perform Safety & Operability Review
• Update Acquisition Strategy
• Develop Next Phase Budget &
Schedule
• Update TPC BDER & Schedule
Range
• Identify Current & 2 FYs Funding
Requirements
DEFINITIONDEFINITION EXECUTIONEXECUTION ACCEPTANCEACCEPTANCE LTSLTS
(Typical products)
PHASESPHASES
CRITICAL
DECISIONS (O 413.3A)
FUNDING
MAJOR INPUT
ITEMS
MAJOR
ACTIVITIES
MAJOR
DELIVERABLES
START
PROJECT
• Problem / Need Definition
• Document Proposed
Modification
• Conceptual Design Business
Decision Estimate & Budgets
• Statement of Mission Need
• Technology Dev Issues List
• TPC BDER & Schedule Range
• Acquisition Strategy
• Next Phase Budget & Schedule
• Risk & Opportunity Mgmt
Plan/Prelim. Risk Assessment
• Program Plan
• Systems Eng. Mgmt. Plan
• Project Definition Rating Index
• CD - 0 Package
• Project End State Vision
• Project Expectations Summary
• Statement of Work
• Preliminary NEPA Documentation
• Preliminary Project Execution Plan
• Preliminary Hazard Analysis Report
• Risk Anal. & Opport. Report (RAOR)
• Verification of Mission Need
• Updated TPC BDER & Schedule
Range
PRELIMINARY DESIGN FINAL DESIGN D&D
•Completed Systems
• Specified End State
and End-points
Verification
• Project Completion
Report
END
PROJECT
APPROVE PROJECT
CLOSEOUT
CD-4
• Approval of Preliminary Base-
line Range
Section 45
• Facility Scope Package
• TPC BDER & Schedule Range
• Special Requirements
• Define Special Procurement
• Finalize Permit Requirements
• Commit Critical Equipment
• Perform Hazards Review
• Finalize PEP
• Update ROAR
• Develop Baselines
• Develop CD1 / CD 2 Package
• Define Project End-points
• Update Annual/Outyear BA
• Project End-points
Specification
• Detailed Schedules
• Responsibility Assign. Matrix
• Finalize NEPA documentation
• Performance Metrics
• Staffing Plans
• Project/Tech. Risk Analysis
Report
• Technology Dev Output
• Documented Safety Analysis
• Final PEP
• Project Definition Rating
Index (PDRI)
• TPC Estimate
• CD-1 / CD- 2 Package
• Approved Baselines
• Source Documents
• Technology Development
output
• Finalize Field Support
Plan
• Engineering & Design
deliverables needed to
initiate fieldwork
• Develop CD- 3 Package
• Equipment and Material
Requisitions
• 100% Definitive Estimate
• Detail Schedules
• Updated PEP &
Performance Baseline
• Verif. of Mission Need
• Request for Project Auth.
(D&D)
• Approved Safety Docs
• Execution Readiness
Independent Review
• PDRI
• Updated ROAR
• CD-3 Package
• Material and Equipment
• Project Authorization
• Permits
• Conduct Site Work
• Final Waste and Material
Disposition
• Initiate Closeout Process
• Deactivation or
Decommissioning
Completion
• Turnover & Closeout
APPROVE START OF
Deactivation & Decommissioning
CD-3
3/13/07 Rev A
• Financial Closeout or
transfer to Long Term
Stewardship
• Permit Requirements
• Facilities Scope
• Preliminary Technology Dev Input
• RSA / ORR Applicability
Note: Deliverables from each phase are
input to subsequent phases
APPROVE ALTERNATIVE &
PERFORMANCE
BASELINE
CD-1 & CD-2
UP UP --FRONT FRONT
PLANNINGPLANNING
• Establish Project Team
• Establish Program/Project Planning Budget
• Develop Project Scope
• Initiate Planning & Technical Approach
• Assess Technology Needs
• Submit CD- 0 Package
• Identify Project Risks
• Environmental Strategy has been decided
• Identify Customer Expectations
• Identify Key Schedule Drivers
• Identify Funding Constraints
• Identify Project- Level Interfaces
• Establish Placeholder in Out Year Budget
• Identify Current & Next 2 FY Funding
Requirements
• Establish Next Phase Budget & Schedule
• Develop TPC BDER & Sched Range
Pre-decision Phase
(Operations – S&M)
Alternative Selection Disposition Plan Close Out Long Term
Surveillance
Final Engineering &
Planning
Deactivate or
Decommission
APPROVE
MISSION NEED
CD- 0
DOE G 413.3-8 Attachment 4
9-24-08 Page 63 (and Page 64)
Attachment 4-Soil and Groundwater RCRA/CERCLA Flow Process
NO FURTHER
ACTION
CRITICAL
DECISIONS
FUNDING
PROCESS
STEPS
M
A
J
O
R
A
C
T
I
V
I
T
I
E
S
CONSTRUCTION
COMPLETE; TRANSITION
TO OPERATONS
CD-4
APPROVE DESIGN / BASELINE
CONSTRUCTION START
CD-2/3
D
E
L
I
V
E
R
A
B
L
E
S
DEFINITION EXECUTION TRANSITION / CLOSEOUT
PROJECT
PHASE
INITIATION
APPROVE
MISSION NEED
CD-0
• Literature/History
Search
• Sampling Plan
• Soil Sampling
• Radiation Survey
• Groundwater Data
• Monitoring Data
• Geophysical
Analysis
• Soil/Water Sample
Analysis
• Environmental
Evaluation/Exchange
• Site Evaluation
Report
• Establish Project
Team
• Review Existing Data
• Initiate Conceptual
Site Model
Development
• Data Quality
Objectives
• Unit Specific
Contaminant Lists
• Data Evaluation
• Preliminary Data
Collection
Requirements
• Identify Key Schedule
Drivers
• Identify Project Risks
• Prepare Life Cycle
Section 46
Cost Estimate
• RFI/RI Work Plan
• Develop Unit
Description
• Develop Conceptual
Site Model
• Determine Exposure
Point Concentrations
• Contaminant Fate and
Transport Scenario
• Exposure, Toxicity, and
Human Health Risks
• Ecological Risks
• Identify Contaminants
of Concern
• Identify Remedial
Action Objectives
• Identify Remedial Goal
Options
• RFI/RI Baseline Risk
Assessment
• Document Public
Comments
• Document the
Preferred Alternative
• Record of Decision
• Identify/Screen
Alternative Measures
• Analyze/Rank
Alternatives
• Identify Technologies
• Evaluate Treatability
Study
• Technology Selection
• Identify the Preferred
Alternative
• Corrective Measure
Study/Feasibility Study
• Identify Options
• No Further Action
• Institutional
Controls
• Remedial Action
• Identify the Preferred
Remedial Alternative
• Update Life Cycle Cost
Estimates
• Initiate Project
Definition Rating Index
• Public Interface/Comment
• Statement of
Basis/Proposed Plan
• Project Execution Plan
• Analytical Request
• Drilling Request
• Define Process for
Characterization
• Define Methods to be
Employed
• Review/Oversight of
Output
• Technical Analysis
• Data Interpretation
• Readiness Review
• Sampling Plan
• Health and Safety Plan
• Waste Management
Plan
• Data Summary Report
STATEMEN
TOF BASIS
/PROPOSE
D
• Define Permit
Requirements
• Define Criteria
• Develop Specifications,
Drawing, Permits
• Design/ Maintenance/
Operability/ Construction
Review
• Develop Remedial Action
Implementation Plan
• Develop Operating
Parameters
• Screening Process Hazard
Review
• Auditable Safety Analysis
• Safeguards and Security
• Update Life Cycle Cost
Estimate
• Update Project Definition
Rating Index
• Develop Procurement
Package
• Develop Storm water
Management Plan
• Updated Waste
Management Plan
• Updated Health & Safety
Plan
• Pollution Prevention Plan
• Environmental Monitoring
Plan
• Develop Construction
Scope/Statement of
Work
• Update Life Cycle
Cost Estimate
• Subcontract
Development
• Subcontract Award
• Permits
• Readiness Review
• Work Authorization
• Field Work
• Non-conformance
report
• Final Acceptance
• Turnover Process
• Close - out Activities
• Procurement Plan
• Process / Work
Package
• Health & Safety Plan
• Final As - Built
4/13/20
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
••
STATEMENT
OF BASIS
/PROPOSED
PLAN
•
-
-
Drawings
• Post Construction
Report
• Process Hazard
Review
• Operating Procedure
Development
• Operator Training
• Acceptance Testing
• Startup Testing
• Maintenance
Activities
• Readiness Review
• Continuous
Operations
• Permit
Requirements
• Effectiveness
Monitoring Plan •
Remedial Action
Completion Report
NORMALLY COMBINED NORMALLY COMBINED
CMS/FS
DEVELOPMENT
RFI/RI
BASELINE
RISK
ASSESSMENT
FIELD
CHARACTER
-IZATION
RFI/RI
WORK
PLAN
SITE
EVALUATION
POST
CLOSUREOPERATIONS
CONSTRUCTION -
REMEDIATION
DESIGN
RECORD
OF
DECISION
(Operations Funded)
APPROVE PREFERRED
ALTERNATIVE
CD-1
Total Project Cost (TPC)
(Operations Funded) (Operations Funded)
•
•
DOE G 413.3-8 Attachment 5
9-24-08 Page 65 (and Page 66)
Attachment 5-Stabilization and Disposition Project Overview
EEXXEECCUUTTIIOONN
PPHHAASSEESS
CRITICAL
DECISIONS (O 413.3A)
FUNDING
MAJOR
INPUT
MAJOR
ACTIVITIE
MAJOR
DELIVERABLE
START
PROJECT
FACILITY OPERATIONS DEACTIVATION
END
PROJECT
1/12/08 Rev A
Section 47
PERFORMANCE BASELINE CD-2
&
APPROVE NEW
NEAR TERM BASELINE CD-3
(Operations – S&M)
Disposition Plan
APPROVE MISSION NEED CD-0 Waived (1)
APPROVE ALTERNATIVE CD-1
NNEEAARR TTEERRMM BBAASSEELLIINNEE OOUUTT YYEEAARR PPLLAANNNNIINNGG EESSTTIIMMAATTEE
PERFORMANCE BASELINE CD-2 (2)
&
APPROVE NEW
NEAR TERM BASELINE CD-3 (2)
FACILITY OPERATIONS
(Operations – S&M) (Operations – S&M)
CCOOMMPPLLEETTEEDD WWOORRKK
FACILITY OPERATIONS
DDEECCOOMMMMIISSSSIIOONNIINNGG
(Operations – S&M)
Note (1): CD-0 and CD-1 for ongoing programs have
been waived because they are already
in their Execution (Operating) phase.
Future projects require implementation
of the Critical Decision process as
outlined in DOE O 413.3A with
appropriate tailoring.
• Approved Baselines
• Approved Funding
• Material to be dispositioned identified
• Technology / Methodology identified
• Process Flow Sheet Development
• Safety Document Development & Implementation
• Transportation & Shipping Activities
• Procedure Development and Approval
• Training
• System & Equipment Upgrades
• Cold Runs
• Integrated Cold Runs
• Facility Operation Safety Committee Reviews
• Demo Run/ Hot Operations
• Contractor Review & Approval
• DOE Review & Approval
• Material Processing
• Facility/System Outages
For S&D Projects the materials being processed,
dispositioned, treated, stored, and/or being shipped
are continually changing. Each material campaign can
be treated as project within the overall Facility
Operations. Most material campaigns do not required a
formal CD process. The Federal Project Director
should use a systematic process to determine which
materials required a formal CD process. This process
needs to be identified in the PEP for the project.
Coincident with the PEP preparation the FPD should
update the Acquisition Strategy to identify any new or
special procurement requirements. An example of one
such process is the “Programmatic Project Execution
Plan for PBS SR-0014C, Liquid Waste Subprojects”.
Inputs, activities, and deliverable identified on this
attachment are typical of material campaigns, which
do not require a formal CD.
• Approved Process Flow Sheets
• Approved & Implemented Safety Document
• Approved Shipper Receiver Agreement & Protocol
• Approved Procedures
• Qualified Operators, Engineering & Maintenance
Staff
• Completed System & Equipment Upgrades
• Successful Cold Runs
• Successful Integrated Cold Runs
• Approved Facility Operation Safety Committee
Reviews
• Successful Demo Run/ Hot Operations
• Contractor Approval
• DOE Approval
• Material Processed per Production Plan
• Successful Facility/System Outages, which do not
impact Production Plan
In addition activities identified to the left
other activities performed during
processing include, but are not limited to
the following:
• Sample Analysis
• Surveillance and Maintenance Activities
• Radiological Control
• Waste Management
• Completed Sample Analysis
• Completed Surveillance and Maintenance
Activities
• Successful Radiological Control
• Successful Waste Management
• Deactivation Plan
• Proposed End State and End-points for
Deactivation
• Facility Characterization
• Identification of Legacy Wastes
• Vessel, Tank & Piping Flush Plan
• Utility & Equipment Isolation Plan
• Legacy Waste De-inventory
• Safety Document Revisions for End State
• Suspension of Preventive Maintenance
• Removal of Cold Chemicals No Longer
Needed for Processing
• Revised Surveillance Plan Based upon End
State
• Inventory of Usable Equipment to be Made
Available to Other Facilities