DOE G 413.3-6B, High Performance Sustainable Building
Functional areas: Project Management, Program Management
This Guide highlights the DOE O 413.3B drivers for incorporating high performance sustainable building (HPSB) principles into Critical Decisions 1 through 4 and provides guidance for implementing the Order's HPSB requirements. Cancels/supersedes DOE G 413.3-6A Chg 1 (AdminChg).
Supersedes:
Cancels:
Version history and related documents
Supersedes
Earlier documents this one replaced.
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
AVAILABLE ONLINE AT: INITIATED BY:
www.directives.doe.gov Office of Project Management
U.S. Department of Energy GUIDE
Washington, DC
DOE G 413.3-6B
Approved: 4-5-2020
SUBJECT: HIGH PERFORMANCE SUSTAINABLE BUILDINGS
[This Guide describes acceptable, but not mandatory means for complying with requirements.
Guides are not requirements documents and are not to be construed as requirements in any audit
or appraisal for compliance with associated rules or directives.]
NOT
MEASUREMENT
SENSITIVE
http://www.directives.doe.gov/
DOE G 413.3-6B i (and ii)
4-5-2020
FOREWORD
This Department of Energy (DOE) Guide, for use by all DOE elements, assists with
documenting compliance with high performance sustainable building requirements.
This DOE Guide provides acceptable, but not mandatory, means for complying with
requirements included in DOE Order 413.3B, Program and Project Management for the
Acquisition of Capital Assets, current version. This DOE Guide does not impose, but may cite,
requirements. Guides neither substitute for requirements nor replace technical standards that
implement requirements. Send citations of errors, omissions, ambiguities, and contradictions
found in this Guide to PMpolicy@hq.doe.gov.
DOE G 413.3-6B iii
4-5-2020
Contents
Foreword .......................................................................................................................................... i
1 Purpose ......................................................................................................................................... 1
1.1 Overview .......................................................................................................................... 1
1.2 Acquisition Approaches ................................................................................................... 1
1.3 Applicability ..................................................................................................................... 1
2 Basis ............................................................................................................................................. 3
2.1 DOE Directives ................................................................................................................ 3
2.2 Executive Order and Implementing Instructions ............................................................. 3
2.3 Guiding Principles for Sustainable Federal Buildings ..................................................... 4
2.4 Office of Management and Budget Circular A-11 Guidance .......................................... 4
2.5 Acquisition Regulations and Guidance ............................................................................ 4
3 Background .................................................................................................................................. 5
3.1 Other Resources ............................................................................................................... 5
3.2 Guiding Principles ............................................................................................................ 5
3.3 LEED Certification .......................................................................................................... 6
3.4 Equivalence and Training ................................................................................................. 6
Section 2
4 Roles and Responsibilities ........................................................................................................... 9
4.1 Chief Executive for Project Management ........................................................................ 9
4.2 Project Management Executive ........................................................................................ 9
4.3 Program Secretarial Officer ............................................................................................. 9
4.4 Federal Project Director ................................................................................................... 9
4.5 Director of the Office of asset management ................................................................... 10
4.6 Project Analyst in Office of Project Management ......................................................... 10
5 Schedule ..................................................................................................................................... 11
6 Deliverables ............................................................................................................................... 13
6.1 Initiation Phase ............................................................................................................... 13
6.2 Definition Phase ............................................................................................................. 13
6.2.1 Planning Documents ............................................................................................... 13
6.2.2 Integrated Project Team .......................................................................................... 14
6.2.3 LEED Registration .................................................................................................. 14
6.2.4 Identifying Energy Goals ........................................................................................ 14
6.2.5 Commissioning ....................................................................................................... 15
6.2.6 LEED and GP Site Credits ...................................................................................... 15
6.2.7 LEED and GP documentation ................................................................................. 15
6.2.8 LEED Minimum Requirements .............................................................................. 15
6.2.9 LEED Waiver .......................................................................................................... 15
6.2.10 Communication with the Designers ........................................................................ 16
iv DOE G 413.3-6B
4-5-2020
6.2.11 Conflicting Requirements ....................................................................................... 16
6.2.12 Scorecards and Checklists ....................................................................................... 16
6.3 Execution Phase, Prior to Critical Decision-2 ................................................................ 16
6.3.1 Assigning Responsibility ........................................................................................ 16
6.3.2 Routine Progress Meetings ..................................................................................... 17
6.3.3 Preliminary Design ................................................................................................. 17
6.3.4 Use of “Not Applicable” for GPs ............................................................................ 17
Section 3
6.3.5 LEED Credit and GP Element Documentation ...................................................... 17
6.3.6 LEED Waiver .......................................................................................................... 17
6.3.7 Project Reviews ...................................................................................................... 17
6.3.8 USGBC Split Review ............................................................................................. 17
6.4 Execution Phase, Prior to Critical Decision-3 ................................................................ 18
6.4.1 Final Design ............................................................................................................ 18
6.4.2 Scorecards and Checklists ....................................................................................... 18
6.4.3 Project Reviews ...................................................................................................... 18
6.4.4 LEED Credit and GP Element Documentation ...................................................... 18
6.4.5 Commissioning ....................................................................................................... 18
6.5 Execution Phase, Prior to Critical Decision-4 ................................................................ 18
6.5.1 LEED Credit and GP Element Documentation ...................................................... 19
6.5.2 Commissioning ....................................................................................................... 19
6.5.3 Benchmarking ......................................................................................................... 19
6.6 Project Closeout Phase ................................................................................................... 19
6.6.1 Third-party Entity ................................................................................................... 19
6.6.2 LEED Certification ................................................................................................. 19
6.6.3 GP Documentation .................................................................................................. 20
6.6.4 GPs for Existing Buildings ..................................................................................... 20
6.7 Tailoring and Exceptions ............................................................................................... 20
6.7.1 LEED Gold Waiver Procedures .............................................................................. 20
6.7.2 LEED Non-Applicability Documentation .............................................................. 21
6.7.3 Non-Applicable GP Element Documentation ......................................................... 21
6.8 Summary System Diagram ............................................................................................. 21
7 Acronyms and Abbreviations .................................................................................................... 23
8 Sources Cited ............................................................................................................................. 25
Attachment 1: Resources by Guiding Principle Element ............................................................ 1-1
Attachment 2: Example LEED Scorecards and GP Checklists ................................................... 2-1
DOE G 413.3-6B 1
4-5-2020
1 PURPOSE
1.1 OVERVIEW
Section 4
This Guide addresses implementing the high performance sustainable building (HPSB)
requirements in Department of Energy (DOE) Order 413.3B, Program and Project Management
for the Acquisition of Capital Assets1 (“the Order”), current version, incorporating the HPSB
principles in the design, construction, and commissioning of new, and renovation of existing,
DOE buildings, and verifying their incorporation at Critical Decisions (CDs) 0 through 4 and
project closeout.
Application of HPSB principles yields benefits including:
1. Reduced total (life-cycle) ownership cost of facilities;
2. Improved energy efficiency and water conservation;
3. Safe, healthy, and productively built environments; and
4. Protection of the natural environment.
1.2 ACQUISITION APPROACHES
The Order references two approaches for acquiring HPSBs.
1. Earning United States Green Building Council (USGBC) Leadership in Energy and
Environmental Design2 (LEED) Building Design and Construction (BD+C)
certification at the Gold rating level; and,
2. Achieving all of the 2016 Guiding Principles for Sustainable Federal Buildings3
(GPs) for new construction referenced by Executive Order (EO) 13834 implementing
instructions.4
1.3 APPLICABILITY
1. This Guide applies to buildings acquired in accordance with the Order that DOE will
either own or lease and that will have the characteristics in the following table:
Criteria LEED BD+C GPs
Total Project Cost ≥ $50M Any
Individual Building Size ≥ 1,000 GSF > 5,000 GSF
Real Property Trailers No Yes
Human Occupants Yes Yes or No
Individual Building Cost Any Any
Sources: DOE Order 413.3B, USGBC Minimum Program Requirements5, DOE Order 430.1C
1 DOE Order 413.3B, https://go.usa.gov/xVW8j
2 USGBC LEED Green Building Rating System, http://www.usgbc.org/ and http://www.gbci.org/certification
3 Guiding Principles for Sustainable Federal Buildings, https://go.usa.gov/xpMbp
4 EO 13834 Implementing Instructions, https://go.usa.gov/xVW8k
5 USGBC LEED MPR, https://www.usgbc.org/creditst
https://go.usa.gov/xVW8j
http://www.usgbc.org/
http://www.gbci.org/certification
https://go.usa.gov/xpMbp
https://go.usa.gov/xVW8k
https://tinyurl.com/t9ab42t
2 DOE G 413.3-6B
4-5-2020
2. Although structured by the CDs pertinent to capital asset projects with a total project
cost of $50 million or more, this Guide also provides useful information for
incorporating HPSB principles into minor construction6 projects acquiring or
renovating buildings at DOE sites.
6 DOE Order 413.3B refers to minor construction projects as “general plant projects (GPPs)”.
DOE G 413.3-6B 3
4-5-2020
2 BASIS
2.1 DOE DIRECTIVES
1. DOE Order 413.3B, Program and Project Management for the Acquisition of Capital
Assets7, along with its contractor requirements document (CRD), requires
incorporating the HPSB principles in the project management of capital asset
acquisitions involving the siting, design, construction, and commissioning of new
facilities and major renovations of existing facilities.
2. DOE Order 430.1C, Real Property Asset Management8, in Section 4(b)(1)(c),
requires that the construction or renovation of existing DOE-owned buildings larger
than 5,000 gross square feet must meet the White House Council on Environmental
Quality (CEQ) Guiding Principles for Sustainable Federal Buildings and Associated
Instructions, February 2016, or subsequent revision (GPs).
Section 5
3. DOE Order 436.1A, Departmental Sustainability9, implements sustainable practices
for enhancing Department environmental, energy, and transportation management
performance. Section 4(c) requires the preparation of site sustainability plans that
typically include a list of planned HPSBs while Sections 4(c)(3) and 5(e)(2) require
the utilization of environmental management systems that support HPSBs.
2.2 EXECUTIVE ORDER AND IMPLEMENTING INSTRUCTIONS
1. Executive Order (EO) 13834, Efficient Federal Operations10, directs the head of each
agency to ensure that new construction and major renovations conform to applicable
building energy efficiency requirements and sustainable design principles. For new
construction and modernization (NC), EO 13834 implementing instructions, in
Section III(A)(5), identifies as the basis for HPSBs either the GPs revised in 2016 or
one or more third-party building certifications or standards identified by the General
Services Administration (GSA). GSA has not published a list of third-party building
certifications or standards yet.
2. According to the implementing instructions, CEQ will evaluate agencies based on
progress made toward bringing or keeping 15 percent of their buildings 10,000 GSF
or larger into compliance with the GPs. CEQ will give bonus credit to agencies that
have buildings under 10,000 GSF that comply with the GPs by adding this compliant
building area to both the denominator and numerator of the performance metric ratio.
EO 13834 revokes and replaces EO 13693 which revoked and replaced EOs 13423
and 13514 referenced in DOE Order 413.3B and DOE Order 436.1A.
7 DOE Order 413.3B, https://go.usa.gov/xVW8j
8 DOE Order 430.1C, Section 4(b)(i)(c), https://go.usa.gov/xV5mN
9 DOE Order 436.1, https://go.usa.gov/xRwCR
10 EO 13834, Section 2(e), https://go.usa.gov/xVW8K
https://go.usa.gov/xVW8j
https://go.usa.gov/xV5mN
https://go.usa.gov/xRwCR
https://go.usa.gov/xVW8K
4 DOE G 413.3-6B
4-5-2020
2.3 GUIDING PRINCIPLES FOR SUSTAINABLE FEDERAL BUILDINGS
CEQ issued the GPs11 in two documents: “Determining Compliance with the Guiding Principles
for Sustainable Federal Buildings” (GP Compliance Document), which outlines evaluation
criteria for each of the GPs and the “Guiding Principles for Sustainable Federal Buildings and
Associated Instructions,” which provides instructions, guidance and recommended practices.
Where the latter contains generalities, the former offers specifics.
2.4 OFFICE OF MANAGEMENT AND BUDGET CIRCULAR A-11 GUIDANCE
OMB Circular A-1112 addresses, among other topics, the planning, budgeting, and acquisition of
capital assets. The Capital Programming Guide, a supplement to the Circular, in Section (I)(5(1),
requires integrated project teams (IPTs) to determine the extent to which asset acquisition or
renovation requirements have incorporated sustainable design principles.
2.5 ACQUISITION REGULATIONS AND GUIDANCE
1. The Federal Acquisition Regulation (FAR) in 48 CFR §7.103(p)(3)13 directs heads of
agencies to ensure their planners comply with the GPs in designing, constructing, or
renovating federal buildings.
2. The Department of Energy Acquisition Regulation14 (DEAR) supplement the FAR,
which codifies uniform policies for acquisition of supplies and services by executive
agencies, and contains clauses for inclusion in contracts. Several clauses support
HPSB principles in the acquisition of capital assets. For the sustainable acquisition
program, see DEAR 952.223-78 and DEAR 970.5223-7. For integration of
environment, safety, and health into work planning and execution, see DEAR
952.223-71 and DEAR 970.5223-1.
Section 6
3. The Department of Energy Acquisition Guide, Chapter 23.115, addresses
sustainability especially from the perspective of purchasing sustainable supplies,
materials, and equipment.
11 FEMP, Resources on the Guiding Principles for Sustainable Federal Buildings, https://go.usa.gov/xVW8R and
https://go.usa.gov/xVW85
12 OMB, Circular A-11, Supplement to Part 7—Capital Programming Guide, https://go.usa.gov/xVW8E
13 FAR, 48 CFR §7.103, https://go.usa.gov/xV5y3
14 DEAR, 48 CFR §952, https://go.usa.gov/xV5yB, and 48 CFR §970, https://go.usa.gov/xV5yk
15 DOE Acquisition Guide, Chapter 23.1, Sustainable Acquisition Policy, https://go.usa.gov/xVW82
https://go.usa.gov/xVW8R
https://go.usa.gov/xVW85
https://go.usa.gov/xVW8E
https://go.usa.gov/xV5y3
https://go.usa.gov/xV5yB
https://go.usa.gov/xV5yk
https://go.usa.gov/xVW82
DOE G 413.3-6B 5
4-5-2020
3 BACKGROUND
3.1 OTHER RESOURCES
1. This Guide does not fully address all of the other governing statutes, rules, and other
guidance related to sustainability at Federal sites, such as the Energy Policy Act of
200516 (EPAct) and the Energy Independence and Security Act of 200717 (EISA).
Note that the GPs do not incorporate EISA Section 523 which requires agencies to
install solar hot water heaters when lifecycle cost effective.18,19
2. Regulation requires newly constructed buildings to comply with the applicable
version of the American Society of Heating, Refrigerating and Air-Conditioning
Engineers (ASHRAE) 90.120, or if low-rise residential, the International Energy
Conservation Code (IECC),21 at a level 30 percent more energy efficient than the
applicable version of ASHRAE 90.1 or the IECC if life-cycle cost effective or, if not
life-cycle cost effective, at the maximum percentage more energy efficient than the
applicable version of ASHRAE 90.1 or the IECC to achieve life-cycle cost
effectiveness.22
3. The Office of Project Management (PM) has published a glossary of DOE project
management terms.23 A building meeting the GPs also conforms to the definition of a
high performance green building.24 However, a building that conforms to the
definition of a high performance green building has not necessarily conformed to
federal statutes related to sustainability, met the GPs, or earned LEED Gold
certification.
3.2 GUIDING PRINCIPLES
1. The GPs originate in the January 24, 2006 Memorandum of Understanding on
Federal Leadership in High Performance and Sustainable Buildings,25 in which
signatory agencies committed to follow a set of principles in the siting, design,
construction and commissioning of federal buildings.
16 EPAct, Pub. L. No. 109-58, https://go.usa.gov/xVW8Z
17 EISA, Pub. L. No. 110-140, https://go.usa.gov/xVW8D
18 Solar Hot Water Heaters, 42 USC §6834(a)(3)(a)(iii), https://go.usa.gov/xp7jV
19 FEMP, Solar Hot Water Heater Guidance, https://go.usa.gov/xVW8n and https://go.usa.gov/xVW8Q
20 See 10 CFR §433.100, https://go.usa.gov/xV5ZN, which specifies the applicable version of ASHRAE 90.1 based
on when design began. Determine energy consumption levels using the performance rating method found in
ASHRAE 90.1, Appendix G.
21 See 10 CFR §435.4, https://go.usa.gov/xpHvE, which specifies the applicable version of the International Energy
Conservation Code based on when design began.
22 See 10 CFR §436.19 et. seq. for the methodology for determining life-cycle cost effectiveness.
23 DOE Acquisition and Project Management Glossary of Terms Handbook, https://go.usa.gov/xRwxb
24 Per DOE and GSA interpretation of the HPGB Definition, 42 USC §17061(13), https://go.usa.gov/xVfjg
25 Memorandum of Understanding, http://www.wbdg.org/references/mou.php
Section 7
https://go.usa.gov/xVW8Z
https://go.usa.gov/xVW8D
https://go.usa.gov/xp7jV
https://go.usa.gov/xVW8n
https://go.usa.gov/xVW8Q
https://go.usa.gov/xV5ZN
https://go.usa.gov/xpHvE
https://go.usa.gov/xRwxb
https://go.usa.gov/xVfjg
http://www.wbdg.org/references/mou.php
6 DOE G 413.3-6B
4-5-2020
2. The GPs as revised in 2016 include:
a. Employ integrated design principles;
b. Optimize energy performance;
c. Protect and conserve water;
d. Enhance indoor environmental quality;
e. Reduce environmental impact of materials; and,
f. Assess and consider climate change risks.
3. Attachment 1 lists by GP element resources useful to projects.
3.3 LEED CERTIFICATION
1. The USGBC created the LEED rating system as an independent commercial green
building certification program. The system provides guidelines for, and third-party
verification of, features intended to improve environmental performance in functional
areas including site selection and access, site development, energy and water
consumption, materials selection, and indoor environmental quality. The Green
Business Certification Inc. (GBCI) administers LEED including LEED Online,
performs third-party technical reviews, and verifies LEED-registered projects.26
USGBC charges fees.27
2. The LEED rating system offers multiple certification tracks applicable to different
project or building types. The Order in its CRD specifies achievement of LEED
certification at the Gold rating level but does not prescribe a particular certification
track. Based on the number of points achieved, a project earns one of four LEED
rating levels: Certified, Silver, Gold or Platinum. Due to its ubiquity in the
commercial sector, construction contractors will likely have, or at least access to,
expertise in LEED.
3. Each LEED rating system has minimum program requirements (MPRs) and credit
category prerequisites. Buildings that cannot satisfy one or more MPRs and credit
category prerequisites for a LEED rating system may not earn certification under that
LEED rating system. Some credit category pre-requisites introduce scope beneficial
only when a building will have human occupants.
3.4 EQUIVALENCE AND TRAINING
1. CEQ has not identified any green building certifications as equivalent to the GPs.
Instead, DOE has determined that a LEED Gold rating level equates to compliance
with the GPs under the following circumstances:
26 USGBC LEED Green Building Rating System, http://www.usgbc.org/ and http://www.gbci.org/certification
27 USGBC LEED Fee Schedule, https://www.usgbc.org/cert-guide/fees
http://www.usgbc.org/
http://www.gbci.org/certification
https://www.usgbc.org/cert-guide/fees
DOE G 413.3-6B 7 (and 8)
4-5-2020
a. Any contracts supporting constructing a new, or renovating an existing, building
invoke 48 CFR § 970.5223-7, Alternate I for Construction Contracts and
Subcontracts; and,
b. The LEED credits earned satisfy the GPs per 10 CFR § 433.300(c).
2. GSA has determined28 that prerequisite and point criteria for LEED BD+C Version
4.0 do not incorporate the following component requirements of the GPs:
a. Radon detection; and,
b. Waste diversion for occupants.
3. GSA has further determined29 that buildings may earn LEED BD+C Version 4.0
certification without incorporating the following component requirements of the GPs:
a. Indoor air quality plans;
b. Moisture control;
c. Integrated pest management;
d. Actual energy use reduction;
e. ENERGY STAR products;
f. Energy efficiency benchmarking;
g. Procuring materials with recycled content; and,
h. Procuring materials with biobased content.
Section 8
4. The Federal Energy Management Program (FEMP) provides training on the GPs30
including using spreadsheets to track compliance.31 USGBC offers training on
LEED.32 Both offer reference materials. GSA and FEMP have also published other
HPSB resources.
28 Per 42 USC §17092(h), GSA reviews high-performance building certification systems quinquennially. GSA, HPB
Certification System Review, Table 3-1, https://go.usa.gov/xVWN3
29 GSA, HPB Certification System Review, Table 3-1, https://go.usa.gov/xVWN3
30 FEMP, Training on the 2016 Guiding Principles, https://go.usa.gov/xVW8P
31 FEMP GP compliance tracking spreadsheets, https://go.usa.gov/xp7RM
32 USGBC, LEED Training, https://new.usgbc.org/education
https://go.usa.gov/xVWN3
https://go.usa.gov/xVWN3
https://go.usa.gov/xVW8P
https://go.usa.gov/xp7RM
https://new.usgbc.org/education
DOE G 413.3-6B 9
4-5-2020
4 ROLES AND RESPONSIBILITIES
4.1 CHIEF EXECUTIVE FOR PROJECT MANAGEMENT
Reviews CD documents including plans to incorporate the GPs or design for LEED Gold
certification on projects with a total project cost equal to or greater than $750 million.
4.2 PROJECT MANAGEMENT EXECUTIVE
1. Adjudicates LEED Gold certification waiver requests.
2. Reviews CD documents including plans to incorporate the GPs or design for LEED
Gold certification on projects with a total project cost equal to or greater than $100
million.
4.3 PROGRAM SECRETARIAL OFFICER
1. Sets sustainability goals for capital asset projects and ensures their incorporation in
the mission need statement.
2. Devises a process for requesting LEED Gold certification waivers.
3. Reviews CD documents including plans to incorporate the GPs or design for LEED
Gold certification on projects with a total project cost equal to or greater than $50
million.
4. Provides first tier interpretations of the GPs.
4.4 FEDERAL PROJECT DIRECTOR
1. Gains a familiarity with the GPs and LEED certification requirements.
2. Staffs the IPT with design and construction management professionals proficient in
building commissioning, the GPs, and LEED certification requirements.
3. Arranges for the appointment of a commissioning agent.
4. Includes sustainability requirements in the scope to ensure compliance with DOE
Order 413.3B. Verifies incorporation of GPs in design and construction documents.
Furnishes documentation addressing sustainability to project review teams.
5. Arranges for the preparation and submission of LEED Gold certification waiver
requests when necessary.
6. Documents plans associated with HPSBs in the DOE Sustainability Dashboard.33
Documents GPs met in FEMP GP checklists, LEED credits earned in the GBCI
33 DOE Sustainability Dashboard, https://sustainabilitydashboard.doe.gov/.
https://sustainabilitydashboard.doe.gov/
10 DOE G 413.3-6B
4-5-2020
system “LEED Online,” and applies for LEED certification. Documents completed
HPSBs in the Facilities Information Management System (FIMS).34
4.5 DIRECTOR OF THE OFFICE OF ASSET MANAGEMENT
1. Issues guidance related to HPSBs, complying with GPs, updating site sustainability
plans, and documenting plans to construct or renovate a HPSB.
2. Provides second tier interpretations of the GPs.
3. Reports to OMB annually the inventory of buildings complying with the GPs either
outright or through equivalence.
4.6 PROJECT ANALYST IN OFFICE OF PROJECT MANAGEMENT
1. Includes lines of inquiry related to HPSB in reviews as appropriate.
Section 9
2. Compares scope baselined to scope delivered to confirm that the project delivered
HPSB-related requirements.
34 Facilities Information Management System (FIMS), https://fims.doe.gov/.
https://fims.doe.gov/
DOE G 413.3-6B 11 (and 12)
4-5-2020
5 SCHEDULE
The below schedule arranges deliverables or actions required by the Order and recommended by
this Guide according to the timing of their completion, either prior to or following a CD.
PRE CRITICAL
DECISION
POST
Action Basis Action Basis
• Address meeting the GPs in
Mission Need Statement and
Program Requirements
Document.
Guide 0
• Ensure IPT and support
contractors have adequate
expertise. Guide
• Address meeting the GPs and
earning LEED certification in
the conceptual design report,
acquisition strategy, analysis
of alternatives, and project
execution plan.
Order 1
• Ensure design contractors
have adequate expertise.
• Begin commissioning plan.
• Track work towards
complying with the GPs.
• Submit LEED waivers.
Guide
• Address meeting the GPs and
earning LEED certification in
the preliminary design and
design review. Order 2
• Document which parts of
specific GPs, if any, do not
apply to each building.
• Ensure the contractor will
provide adequate
documentation.
Guide
• Address meeting the GPs in
the final design and External
Independent Review (or
equivalent).
• Obtain an initial LEED credit
determination
• Confirm the GPs inclusion in
commissioning plans.
Order
Guide
Guide
3
• Document compliance with
the GPs and LEED credits.
• Profile the buildings
acquired or renovated in
ENERGY STAR Portfolio
Manager
Guide
• Verify compliance with the
GPs.
• Verify the completion of
commissioning. Guide 4
• Confirm completeness of GP
compliance records.
• Obtain a final LEED credit
determination
• Confirm records in FIMS
address compliance with the
GPs.
Guide
DOE G 413.3-6B 13
4-5-2020
6 DELIVERABLES
6.1 INITIATION PHASE
Mission Need Statement and Program Requirements Documents
Source: DOE Order 413.3B, Appendix A, Table 2.0 Applies to:
• Approve a Mission Need Statement Document with recommendation
from PM for projects with a TPC ≥ $100M.
• For NNSA only, prepare a Program Requirements Document that
defines the ultimate goals which the project must satisfy.
• Pre-CD-0
1. The Mission Need Statement documents the gap between current and needed
capabilities. Include in it a brief discussion on how the project intends to incorporate
HPSB principles in its plans for constructing new or renovating facilities.
2. Address in the Program Requirements Document, required for NNSA projects per the
Order, achieving a minimum of a LEED Gold rating and complying with the GPs.
3. Identify a representative of a site or field sustainability or energy management
program office familiar with the current version of LEED and the GPs during the
formation of the IPT. This representative will provide first tier interpretations of the
GPs.
6.2 DEFINITION PHASE
Conceptual Design Report, Acquisition Strategy, and Project Execution Plan
Source: DOE Order 413.3B, Appendix A, Table 2.1 Applies to:
• Document Guiding Principles for Federal Leadership in High
Performance and Sustainable Building provisions . . . and/or other
sustainability considerations planned in the Conceptual Design
Report, Acquisition Strategy, and/or [Project Execution Plan (PEP)],
as appropriate.
• Pre-CD-1
6.2.1 Planning Documents
Section 10
1. Apply integrated design principles as early as possible and throughout the life of the
project to both establish expectations up front and provide the framework for tracking
progress throughout the project.
2. Benchmark the theoretical energy and water demands of each building proposed for
construction or renovation under each alternative as part of determining the life-cycle
costs for each alternative.
3. Include in the conceptual design report LEED and GP related requirements in the
code of record. Post CD-1, identify the target LEED certification level.
14 DOE G 413.3-6B
4-5-2020
4. Include in the acquisition strategy requirements that contractors or execution agents
will need to meet, including LEED certification levels.
6.2.2 Integrated Project Team
1. Ensure the IPT has:
a. Federal or contractor members with HPSB experience, including a LEED
accredited professional35, who will document accomplishment of LEED credits
and GP compliance; and,
b. A representative from the commissioning agent that ideally will remain under
contract to support the project through occupancy.
2. Select design firms with experience in sustainable buildings.
3. Use scorecards and checklists to keep the IPT informed of planned and completed
actions supporting achieving LEED credits or GP compliance.
6.2.3 LEED Registration
Register projects with USGBC as soon as possible.36 Note registration incurs a fee. Although
either federal or contractor personnel may register a project, if DOE plans to own the building, a
federal employee signs the registration. Begin each registered building name with "US DOE,"
followed by the two letter program abbreviation of the project owner, the site abbreviation, and
then the planned property name appearing in the FIMS Anticipated Asset Information Module.37
Once registered with USGBC, the building may comply with the current or a future version of
LEED, whichever seems most advantageous to the project. After registration the project may:
1. Access reference materials that will aid in planning;
2. Access credit-specific templates;
3. Store project documents; and,
4. Assign roles to members of the integrated project team.
6.2.4 Identifying Energy Goals
1. Complying with the GPs for new construction requires an energy efficiency at least
30 percent better than the current ASHRAE 90.1 standard.38
2. The current version of the International Green Construction Code may present
options for energy efficiency ASHRAE 90.1 does not address.39
35 USGBC LEED Accredited Professionals, https://www.usgbc.org/people
36 USGBC LEED Project Registration Agreement and Form, https://www.usgbc.org/resources/leed-project-
registration-agreement and https://www.leedonline.com/ or https://arcskoru.com/
37 DOE Order 430.1C, Section 4(b)(1)(b), https://go.usa.gov/xV5mN
38 Guiding Principles for Sustainable Federal Buildings, https://go.usa.gov/xpMbp.
39 International Green Construction Code, https://www.iccsafe.org/products-and-services/i-codes/2018-i-codes/igcc/
https://www.usgbc.org/people
https://www.usgbc.org/people
https://www.usgbc.org/resources/leed-project-registration-agreement
https://www.usgbc.org/resources/leed-project-registration-agreement
https://www.leedonline.com/
https://arcskoru.com/
https://go.usa.gov/xpMbp
https://www.iccsafe.org/products-and-services/i-codes/2018-i-codes/igcc/
DOE G 413.3-6B 15
4-5-2020
3. The earlier energy efficiency planning begins, the more likely the project will
maximize its LEED “Optimize Energy Performance” credit points.
Section 11
4. Under the LEED credit “Optimize Energy Performance,” pursue option 1, “Energy
Performance Compliance.” Projects complying with regulation40 already model the
estimated energy consumption of their buildings except for low-rise residential
buildings.
6.2.5 Commissioning
Post CD-1, develop a commissioning plan with your commissioning agent. Address at a high
level in the Preliminary Project Execution Plan (PPEP) startup and commissioning processes.
Include in the Owner’s Project Requirements (OPR) and Basis of Design (BOD) documents
commissioning requirements. Have the commissioning agent review both the OPR and the BOD.
6.2.6 LEED and GP Site Credits
Some GP elements concern site-wide policies or activities. Similarly, LEED awards some credits
based on sustainable features or practices external to the building(s) seeking certification. Sites
may leverage related documentation for multiple buildings seeking compliance with the GPs or
LEED certification. Involve site sustainability contacts in planning discussions as they will
provide supporting documentation.
6.2.7 LEED and GP documentation
Despite the similarities between the GP and LEED credit categories, specific requirements and
documentation methods differ. Achieving a LEED Gold rating does not equate to meeting all of
the GPs nor does achieving 100 percent of the GPs guarantee receipt of a LEED Gold rating.
Track LEED credits and GP compliance separately; however, where requirements coincide, the
IPT may use LEED credit documentation to document compliance with the GPs.
6.2.8 LEED Minimum Requirements
Post CD-1, with an alternative selected, the project may determine which buildings it will
acquire or renovate will meet the USGBC-defined MPR and prerequisites for certification. The
project may select any LEED rating system to follow for each building in the scope.
6.2.9 LEED Waiver
Where the IPT suspects that a building while meeting the LEED MPR will not satisfy LEED
prerequisites or earn enough credits for a LEED Gold rating, the federal project director (FPD)
requests a waiver from the Project Management Executive (PME). Section 7.7.1 describes the
waiver process. Section 7.7.2 addresses instances where a building does not meet LEED MPR.
40 See 10 CFR §433.101, https://go.usa.gov/xV5ZN.
https://go.usa.gov/xV5ZN
16 DOE G 413.3-6B
4-5-2020
6.2.10 Communication with the Designers
Include in the OPR and BOD the requirements to (1) achieve LEED Gold certification absent a
waiver the terms of which may still require earning LEED certification at a target certification
level and (2) comply with the GPs.
6.2.11 Conflicting Requirements
If a federal regulation seems stricter than the GPs, LEED credit requirement, or industry
standard, follow the federal regulation. The contracting officer, in consultation with the FPD,
decides what constitutes stricter.
6.2.12 Scorecards and Checklists
1. Scorecards and checklists facilitate tracking the project’s sustainable features through
design, construction, and transition to operations.
2. Based on the recommended alternative, and if seeking LEED certification, use a
scorecard to identify LEED credits and points the project intends to earn.
3. If seeking compliance with the GPs outright to modernize an existing building,
identify the preferred energy efficiency strategy in a checklist.
4. As the project progresses, use LEED scorecards to document completed and
remaining credits for LEED certification and GP checklists to document actions
planned and taken to achieve compliance. Find example scorecards and checklists in
Attachment 2.
Section 12
6.3 EXECUTION PHASE, PRIOR TO CRITICAL DECISION-2
Preliminary Design and Design Review
Source: DOE Order 413.3B, Appendix A, Table 2.2 Applies to:
• Incorporate the Guiding Principles for Federal Leadership in High
Performance and Sustainable Buildings . . . and/or other
sustainability considerations into the preliminary design and design
review.
• Pre-CD-2
6.3.1 Assigning Responsibility
1. The FPD will address requirements associated with attaining a LEED Gold rating and
compliance with the GP in the PDR, OPR, and contract documents including the
BOD.
2. The FPD will identify one or more IPT members to bear the responsibility for each
LEED credit or GP element and empower them to work closely with the appropriate
members of the design team.
DOE G 413.3-6B 17
4-5-2020
6.3.2 Routine Progress Meetings
Hold regular HPSB team meetings in order to review progress made and identify potential
challenges to complying with a GP element or achieving LEED credits early. Continue meetings
through the start of operations.
6.3.3 Preliminary Design
1. Verify 60 percent design incorporates all sustainable features except for final energy
and water savings projections, which 90 percent design documents will include.
2. Identify achievable sustainable building features in the preliminary design report.
Update the energy projections and model. Analyze the lifecycle cost effectiveness of
installing solar hot water systems to meet at least 30 percent of the design hot water
demand, per EISA Section 523.41
6.3.4 Use of “Not Applicable” for GPs
Identify GP NC elements or sub-elements deemed “not applicable” to each applicable building
per Section 7.7.3. Justify each such determination in the GP checklist.
6.3.5 LEED Credit and GP Element Documentation
Update documentation so that it identifies the LEED level deemed achievable to include a LEED
scorecard and GP checklist identifying the sustainable features that will contribute to achieving
the certification. Much like USGBC provides a website for documenting compliance with credit
requirements, FEMP provides checklists for the GPs.42 Identify risks to planned sustainable
features and develop risk response strategies. Update scorecards and checklists to reflect the
validated sustainable features of the preliminary project design and justify decisions to deem a
GP element or sub-element not applicable.
6.3.6 LEED Waiver
Where the IPT suspects that a building while meeting the LEED MPR will not satisfy LEED
prerequisites or earn enough credits for a LEED Gold rating, the FPD requests a waiver from the
PME if it did not do so prior to CD-1. See Section 7.7.1 for a description of a waiver process.
6.3.7 Project Reviews
Include a line of inquiry related to the project’s sustainable features in project reviews.
6.3.8 USGBC Split Review
At the project’s request, GBCI completes a review of LEED credit documentation following
preliminary design and a second and final review prior to project closeout. Negative
determinations may result in the IPT revising documentation or pursuing additional credits
41 FEMP, Solar Hot Water Heater Guidance, https://go.usa.gov/xVW8n and https://go.usa.gov/xVW8Q
42 FEMP, Resources on the GPs, https://go.usa.gov/xVW85
https://go.usa.gov/xVW8n
https://go.usa.gov/xVW8Q
https://go.usa.gov/xVW85
18 DOE G 413.3-6B
4-5-2020
documentable during either final design or construction. Note that USGBC assesses fees for each
review conducted by GBCI.
6.4 EXECUTION PHASE, PRIOR TO CRITICAL DECISION-3
Section 13
Final Design and External Independent Review
Source: DOE Order 413.3B, Appendix A, Table 2.3 Applies to:
• Incorporate the Guiding Principles for Federal Leadership in High
Performance and Sustainable Buildings . . . and/or other
sustainability considerations into the Final Design and the EIR.
• Pre-CD-3
6.4.1 Final Design
Ensure that the final design and the solicitation for construction incorporate the sustainable
features deemed necessary to comply with the GPs and attain LEED Gold certification in the
absence of an approved waiver. Confirm specifications address acquiring environmentally
preferable products for construction and other materials, energy efficiency, and recycling of
construction and demolition waste. Select contractors with experience constructing sustainable
buildings.
6.4.2 Scorecards and Checklists
Update scorecards and checklists to reflect any changes made during the final design process that
might impact the project’s ability to comply with the GPs or achieve LEED certification. Reflect
the final energy and water savings projections in updated scorecards and checklists.
6.4.3 Project Reviews
Include a line of inquiry related to the project’s sustainable features in project reviews.
6.4.4 LEED Credit and GP Element Documentation
Maintain documentation of LEED credits sought and attained along with GP elements satisfied.
6.4.5 Commissioning
Begin coordinating commissioning agents, subcontractors, site contractors, federal personnel,
and federal support contractors to facilitate cooperation during testing, startup, commissioning,
and transition to operations.
6.5 EXECUTION PHASE, PRIOR TO CRITICAL DECISION-4
Construction and Commissioning
Source: DOE Order 413.3B, Attachment 1, 15 Applies to:
• The Guiding Principles for Federal Leadership in High Performance
and Sustainable Buildings . . . must be applied to the siting, design,
construction, and commissioning of new facilities and major
renovations of existing facilities.
• Pre-CD-4
DOE G 413.3-6B 19
4-5-2020
6.5.1 LEED Credit and GP Element Documentation
Earning certain LEED credits and satisfying certain GP elements depends on collecting each
month information on construction activity pollution prevention, indoor air quality management,
sustainable building materials, and construction and demolition waste recycling.
6.5.2 Commissioning
Confirm that the project’s commissioning plan incorporates the sustainable features of each
building. The commissioning agent will verify correct installation and proper operation of
equipment and systems followed by checking that personnel have received sufficient training in
their operations and maintenance and that management contracts include each commissioned
building.
6.5.3 Benchmarking
Add each acquired building to, or update existing building records in, the Environmental
Protection Agency (EPA) ENERGY STAR Portfolio Manager to facilitate tracking of energy
and water consumption in addition to greenhouse gas emissions.
6.6 PROJECT CLOSEOUT PHASE
Documentation of Compliance with GPs and LEED Certification
Source: DOE Order 413.3B, Appendix A, Table 2.5 Applies to:
• Complete and document achievement of Facility Sustainment goals
(e.g., LEED Gold, LEED Silver, etc.), as applicable, via an
independent third-party entity within one year of facility occupancy.
• Post CD-4
6.6.1 Third-Party Entity
1. GBCI serves as the third-party review entity for LEED certification.
Section 14
2. Programs may determine compliance with the GPs themselves, through the project
commissioning agent, or through an independent service provider external to the
project that charges fees such as GBCI43 or Green Building Initiative.44
6.6.2 LEED Certification
Obtain a final LEED credit determination from GBCI by requesting a construction review.
Convene a formal ceremony for, and issue a press release upon, mounting the LEED certification
plaque. Invite key stakeholders such as the PME to the ceremony. Provide to the site FIMS
coordinator the LEED rating earned on each building acquired or renovated.
43 GBCI GP compliance determination, https://guidingprinciples.gbci.org/
44 GBI GP compliance determination, https://thegbi.org/guiding-principles-compliance-certification/overview/
https://guidingprinciples.gbci.org/
https://thegbi.org/guiding-principles-compliance-certification/overview/
20 DOE G 413.3-6B
4-5-2020
6.6.3 GP Documentation
Document compliance with the GPs in a final version of the GP checklist or in the project
closeout report in accordance with the procedures set by the Program Secretarial Officer (PSO)
of the Project Owner. Provide to the site FIMS coordinator documentation, such as a completed
GP checklist, of the percentage of the GP NC achieved on each building acquired.
6.6.4 GPs for Existing Buildings
If a site wishes to document a building’s compliance with the GPs subsequent to a FIMS annual
snapshot recording the building as either “evaluated and does not meet the guidelines” or “not
yet evaluated”, the site would evaluate the building’s compliance with the GPs for Existing
Buildings.45
6.7 TAILORING AND EXCEPTIONS
LEED Gold Waiver
Source: DOE Order 413.3B, Attachment 1, 16 Applies to:
• At a minimum, all new construction and major building renovations
must meet U.S. Green Building Council’s Leadership in Energy and
Environmental Design (LEED) Gold certification absent an approved
waiver from the PME.
• Pre-CD-2
6.7.1 LEED Gold Waiver Procedures
1. Each PSO creates a waiver process for planned construction or renovation of
buildings that meet the LEED MPR but will not earn a LEED rating of Gold or
Platinum.
2. The PME adjudicates the waiver request. Waiver request adjudication may occur
prior to the approval of CD-1 but may not occur after CD-2.
3. The PME may approve a blanket waiver applicable to specific usages or other
objective attributes.
4. To support the waiver request, use a LEED scorecard to indicate the achievable
sustainability criteria and justify sustainability criteria deemed unachievable. Reasons
to request a waiver may include:
a. A building meets the LEED MPR46 but will not meet LEED prerequisites;
b. A building meets the LEED MPR, will meet LEED prerequisites, but cannot
achieve sufficient credits for a LEED Gold rating, and does not plan to obtain
LEED Certification.
45 FEMP, Resources on the GPs, https://go.usa.gov/xVW85
46 USGBC LEED MPR, https://www.usgbc.org/credits
https://go.usa.gov/xVW85
https://www.usgbc.org/credits
DOE G 413.3-6B 21 (and 22)
4-5-2020
c. A building meets the LEED MPR and prerequisites, cannot achieve sufficient
credits for a LEED Gold rating, but does plan to obtain a LEED Certification.
6.7.2 LEED Non-Applicability Documentation
1. Buildings that do not meet LEED MPR, or buildings meeting the LEED MPR but
will have no human occupants, may forgo submitting a waiver request by
documenting these findings in either a:
a. Preliminary Design Report or the PEP; or,
Section 15
b. Memorandum to file from the PSO responsible for sustainability prepared in
consultation with the IPT.
2. LEED non-applicable buildings have the potential to still comply with the GPs.
6.7.3 Non-Applicable GP Element Documentation
1. Document using a checklist any GP elements or sub-elements deemed “not
applicable” to the building. A project may not deem all elements of a single GP “not
applicable” but still claim compliance with the GPs.
2. The FPD may make a “not applicable” determination where the building’s inherent
function, mission, safety or designation prevents compliance with a specific GP
element, or sub-element.
3. The PSO responsible for sustainability or, when no such office exists, the Office of
Asset Management reviews the project’s “not applicable” determinations prior to CD-
2. Retain documentation of the determination with project and real property asset
records.
6.8 SUMMARY SYSTEM DIAGRAM
Figure 1 depicts the inputs that inform the planning, design, and acquisition of HPSBs, tools and
techniques used to track LEED points earned and GP elements met, and project management
deliverables, i.e., outputs, that provide evidence of accomplishing the above.
Inputs Tools & Techniques Outputs
1. Mission Need
Statement
2. Program
Requirements
Document
3. EO 13834 Instructions
4. GPs
5. LEED Rating System
6. Commissioning plan
1. GP Checklists
2. LEED Scorecards
3. Documentation
templates
4. LEED Online
5. ENERGY STAR
Portfolio Manager
1. Commissioning report
2. GP Compliance
Documentation
3. LEED Credits
4. LEED Certification
5. LEED Gold Waiver
6. Benchmarked energy
and water
consumption
Figure 1: Inputs, Tools & Techniques and Outputs for HPSBs
DOE G 413.3-6B 23 (and 24)
4-5-2020
7 ACRONYMS AND ABBREVIATIONS
ASHRAE American Society of Heating, Refrigerating and Air-Conditioning Engineers
BD+C Building Design and Construction
BOD Basis of Design (LEED term)
CD Critical Decision
CEQ White House Council on Environmental Quality
CFR Code of Federal Regulations
DEAR Department of Energy Acquisition Regulation
DOE Department of Energy
EIR External Independent Review
EISA Energy Independence and Security Act
EO Executive Order
EPA Environmental Protection Agency
EPAct Energy Policy Act
FAR Federal Acquisition Regulation
FEMP Federal Energy Management Program
FIMS Facility Information Management System
FPD federal project director
IECC International Energy Conservation Code
IPT integrated project team
GBCI Green Business Certification Incorporated
GPs 2016 Guiding Principles for Sustainable Federal Buildings
GSA General Services Administration
GSF gross square feet
HPSB High Performance Sustainable Building
LEED Leadership in Energy and Environmental Design®
M million
MPR Minimum Program Requirements
NC new construction and modernization
OMB Office of Management and Budget
OPR Owner’s Project Requirements (LEED term)
PM The Office of Project Management
PME Project Management Executive
PSO program secretarial officer
USACE United States Army Corps of Engineers
USGBC United States Green Building Council
WBDG Whole Building Design Guide
DOE G 413.3-6B 25
4-5-2020
8 SOURCES CITED
1. Code of Federal Regulations, 10 CFR §433, https://go.usa.gov/xV5ZN.
2. Code of Federal Regulations, 48 CFR §7.103, https://go.usa.gov/xV5y3.
3. DOE Acquisition Guide, Chapter 23.1, Sustainable Acquisition Policy, August 2017,
https://go.usa.gov/xVW82.
4. DOE Acquisition Regulation, 48 CFR §952, https://go.usa.gov/xV5yB, and 48 CFR §970,
https://go.usa.gov/xV5yk.
Section 16
5. DOE Acquisition and Project Management Glossary of Terms Handbook,
https://go.usa.gov/xRwxb.
6. DOE Interpretation of High Performance Sustainable Building Guiding Principles,
PowerPedia page, https://go.usa.gov/xVW8b.
7. DOE Order 413.3B, Chg. 5, Program and Project Management for the Acquisition of Capital
Assets, https://go.usa.gov/xVW8j.
8. DOE Order 430.1C, Real Property Asset Management, https://go.usa.gov/xV5mN
9. DOE Order 436.1, Departmental Sustainability, https://go.usa.gov/xRwCR.
10. Energy Independence and Security Act of 2007, Pub. L. No. 110-140,
https://go.usa.gov/xVW8D.
11. Energy Policy Act (EPAct) of 2005, Pub. L. No. 109-58, https://go.usa.gov/xVW8Z.
12. Executive Order 13834, Efficient Federal Operations, May 17, 2018,
https://go.usa.gov/xVW8K.
13. Executive Order 13834, Efficient Federal Operations, Implementing Instructions, April 2019,
https://go.usa.gov/xVW8k.
14. Executive Order 13834, Efficient Federal Operations, Implementing Resources,
https://go.usa.gov/xVW89.
15. Federal Energy Management Program, Guiding Principles for Sustainable Federal Buildings,
https://go.usa.gov/xVW8R.
16. Federal Energy Management Program, Resources on the Guiding Principles for Sustainable
Federal Buildings, https://go.usa.gov/xVW85.
17. Federal Energy Management Program, Solar Hot Water Heater Calculator and Guidance,
https://go.usa.gov/xVW8n and https://go.usa.gov/xVW8Q.
https://go.usa.gov/xV5ZN
https://go.usa.gov/xV5y3
https://go.usa.gov/xVW82
https://go.usa.gov/xV5yB
https://go.usa.gov/xV5yk
https://go.usa.gov/xRwxb
https://go.usa.gov/xVW8b
https://go.usa.gov/xVW8j
https://go.usa.gov/xV5mN
https://go.usa.gov/xRwCR
https://go.usa.gov/xVW8D
https://go.usa.gov/xVW8Z
https://go.usa.gov/xVW8K
https://go.usa.gov/xVW8k
https://go.usa.gov/xVW89
https://go.usa.gov/xVW8R
https://go.usa.gov/xVW85
https://go.usa.gov/xVW8n
https://go.usa.gov/xVW8Q
26 DOE G 413.3-6B
4-5-2020
18. Federal Energy Management Program, Training on the 2016 Guiding Principles,
https://go.usa.gov/xVW8P.
19. Federal Leadership in High Performance and Sustainable Buildings Memorandum of
Understanding, http://www.wbdg.org/references/mou.php.
20. General Services Administration, High-Performance Building Certification System Review
Findings Report, March 2019, https://go.usa.gov/xVWN3.
21. Green Business Certification Inc., Third-party Assessment of Compliance for Sustainable
Federal Buildings, https://guidingprinciples.gbci.org/.
22. Green Building Initiative, Guiding Principles Compliance, https://thegbi.org/guiding-
principles-compliance-certification/overview/
23. International Code Council, International Green Construction Code,
https://www.iccsafe.org/products-and-services/i-codes/2018-i-codes/igcc/.
24. Office of Management and Budget, Circular A-11, Supplement to Part 7—Capital
Programming Guide, https://go.usa.gov/xVW8E.
25. United States Code, Solar Hot Water Heaters, https://go.usa.gov/xp7jV.
26. US Green Building Council, LEED Accredited Professionals Listing,
https://www.usgbc.org/people.
27. US Green Building Council, LEED Certification Guide,
https://new.usgbc.org/print/pdf/node/38.
28. US Green Building Council, LEED Fee Schedule, https://www.usgbc.org/cert-guide/fees.
29. US Green Buildings Council, LEED Green Building Rating System, http://www.usgbc.org/
and http://www.gbci.org/certification.
30. US Green Building Council, LEED Minimum Program Requirements (MPR),
https://www.usgbc.org/credits.
Section 17
31. US Green Building Council, LEED Project Registration Agreement and Form,
https://www.usgbc.org/resources/leed-project-registration-agreement and
https://www.leedonline.com/ or https://arcskoru.com/.
32. US Green Building Council, LEED Training, https://new.usgbc.org/education.
https://go.usa.gov/xVW8P
http://www.wbdg.org/references/mou.php
https://go.usa.gov/xVWN3
https://guidingprinciples.gbci.org/
https://thegbi.org/guiding-principles-compliance-certification/overview/
https://thegbi.org/guiding-principles-compliance-certification/overview/
https://www.iccsafe.org/products-and-services/i-codes/2018-i-codes/igcc/
https://go.usa.gov/xVW8E
https://go.usa.gov/xp7jV
https://www.usgbc.org/people
https://new.usgbc.org/print/pdf/node/38
https://www.usgbc.org/cert-guide/fees
http://www.usgbc.org/
http://www.gbci.org/certification
https://www.usgbc.org/credits
https://www.usgbc.org/resources/leed-project-registration-agreement
https://www.leedonline.com/
https://arcskoru.com/
https://new.usgbc.org/education
DOE G 413.3-6B Attachment 1
4-5-2020 Page 1-1
ATTACHMENT 1: RESOURCES BY GUIDING PRINCIPLE ELEMENT
1. Employ integrated design principles
a. FEMP Training, https://go.usa.gov/xVWXj
b. FEMP Commissioning, https://go.usa.gov/xVWXB
c. GSA Commissioning Plan Template, https://go.usa.gov/xvqfA
d. Building Commissioning Association, http://www.bcxa.org/
2. Optimize energy performance
a. Building modeling software, http://www.buildingenergysoftwaretools.com/
b. Renewable energy, https://go.usa.gov/xpHH8
c. Life-cycle cost analysis, https://go.usa.gov/xpHH9
d. Metering, https://go.usa.gov/xVWX8
3. Protect and conserve water
a. Water Products, https://go.usa.gov/xVWXn
b. Conserve Water:
i. Water Planning, https://go.usa.gov/xVWX5
ii. Water Management, https://go.usa.gov/xVWXN
c. Single Pass Cooling, https://go.usa.gov/xVWXU
d. Cooling Tower Management, https://go.usa.gov/xVWXP
e. Stormwater, https://go.usa.gov/xVWXE
4. Enhance indoor environmental quality
a. ENERGY STAR, https://go.usa.gov/xVWXy
b. Daylighting, http://www.wbdg.org/resources/daylighting.php
c. Low Emitting Products, https://www.wbdg.org/references/mou_lem.php
d. Integrated Pest Management, https://go.usa.gov/xp7R4
e. Indoor Air Quality, https://www.smacna.org/store/indoor-environmental-air-quality
5. Reduce environmental impact of materials
a. Purchasing:
i. GSA Sustainability Tool, https://sftool.gov/
ii. USDA Biopreferred, http://www.biopreferred.gov
iii. Environmental Protection Agency, www.epa.gov/epp/
iv. WBDG, Green Specifications, www.wbdg.org/design/greenspec.php
b. Standards and Labels, http://scorecard.goodguide.com/chemical-groups/one-
list.tcl?short_list_name=ods and https://www.epa.gov/greenerproducts
https://go.usa.gov/xVWXj
https://go.usa.gov/xVWXB
https://go.usa.gov/xvqfA
http://www.bcxa.org/
http://www.buildingenergysoftwaretools.com/
https://go.usa.gov/xpHH8
https://go.usa.gov/xpHH9
https://go.usa.gov/xVWX8
https://go.usa.gov/xVWXn
https://go.usa.gov/xVWX5
https://go.usa.gov/xVWXN
https://go.usa.gov/xVWXU
https://go.usa.gov/xVWXP
https://go.usa.gov/xVWXE
https://go.usa.gov/xVWXy
http://www.wbdg.org/resources/daylighting.php
https://www.wbdg.org/references/mou_lem.php
https://go.usa.gov/xp7R4
https://www.smacna.org/store/indoor-environmental-air-quality
https://sftool.gov/
http://www.biopreferred.gov/
http://www.epa.gov/epp/
http://www.wbdg.org/design/greenspec.php
http://scorecard.goodguide.com/chemical-groups/one-list.tcl?short_list_name=ods
http://scorecard.goodguide.com/chemical-groups/one-list.tcl?short_list_name=ods
https://www.epa.gov/greenerproducts
Section 18
Attachment 1 DOE G 413.3-6B
Page 1-2 4-5-2020
6. Assess and consider climate change risk
a. Federal Emergency Management Agency, Floodplain Determination,
https://msc.fema.gov/portal/search
b. EPA, Ozone Depleting Substances, https://go.usa.gov/xVWXd
c. EPA, Alternatives, https://go.usa.gov/xVWXv
https://msc.fema.gov/portal/search
https://go.usa.gov/xVWXd
https://go.usa.gov/xVWXv
DOE G 413.3-6B Attachment 2
4-5-2020 Page 2-1
ATTACHMENT 2: EXAMPLE LEED SCORECARDS AND GP CHECKLISTS
1. LEED Scorecard example (http://bit.ly/2fQPKZG) – Link provides a legible version of the
image below.
LEED v4 for BD+C: New Construction and Major Renovation
Project Checklist
Y ? N
Credit 1
0 0 0 16 0 0 0 13
Credit 16 Y Prereq Required
Credit 1 Y Prereq Required
Credit 2 Credit 5
Credit 5 Credit 2
Credit 5 Credit 2
Credit 1 Credit Building Product Disclosure and Optimization - Material Ingredients 2
Credit 1 Credit 2
Credit Green Vehicles 1
0 0 0 Indoor Environmental Quality 16
0 0 0 10 Y Prereq Required
Y Prereq Required Y Prereq Required
Credit 1 Credit 2
Credit 2 Credit 3
Credit 1 Credit Construction Indoor Air Quality Management Plan 1
Credit 3 Credit 2
Credit 2 Credit 1
Credit 1 Credit 2
Credit 3
0 0 0 11 Credit 1
Y Prereq Required Credit 1
Y Prereq Required
Y Prereq Building-Level Water Metering Required 0 0 0 Innovation 6
Credit 2 Credit 5
Credit 6 Credit 1
Credit 2
Credit Water Metering 1 0 0 0 Regional Priority 4
Credit Regional Priority: Specif ic Credit 1
0 0 0 33 Credit Regional Priority: Specif ic Credit 1
Y Prereq Required Credit Regional Priority: Specif ic Credit 1
Y Prereq Required Credit Regional Priority: Specif ic Credit 1
Y Prereq Required
Y Prereq Required 0 0 0 TOTALS Possible Points: 110
Credit 6
Credit 18
Credit 1
Credit 2
Credit 3
Credit 1
Credit 2
Acoustic Performance
Quality View s
Enhanced Indoor Air Quality Strategies
Low -Emitting Materials
Indoor Air Quality Assessment
Thermal Comfort
Certified: 40 to 49 points, Silver: 50 to 59 points, Gold: 60 to 79 points, Platinum: 80 to 110
Access to Quality Transit
Reduced Parking Footprint
Open Space
Site Assessment
Interior Lighting
Daylight
LEED Accredited Professional
Innovation
Rainw ater Management
Light Pollution Reduction
Environmental Tobacco Smoke Control
Energy and Atmosphere
Minimum Energy Performance
Fundamental Refrigerant Management
Cooling Tow er Water Use
Green Pow er and Carbon Offsets
Heat Island Reduction
Outdoor Water Use Reduction
Indoor Water Use Reduction
Outdoor Water Use Reduction
Indoor Water Use Reduction
Enhanced Commissioning
Building-Level Energy Metering
Water Efficiency
Fundamental Commissioning and Verif ication
Demand Response
Renew able Energy Production
Enhanced Refrigerant Management
Optimize Energy Performance
Advanced Energy Metering
Construction Activity Pollution Prevention
High Priority Site
Surrounding Density and Diverse Uses
Sustainable Sites
Building Life-Cycle Impact Reduction
Site Development - Protect or Restore Habitat
Building Product Disclosure and Optimization - Sourcing of Raw Materials
Project Name:
Date:
Location and Transportation
Sensitive Land Protection
LEED for Neighborhood Development Location
Bicycle Facilities
Construction and Demolition Waste Management Planning
Materials and Resources
Storage and Collection of Recyclables
Construction and Demolition Waste Management
Minimum Indoor Air Quality Performance
Building Product Disclosure and Optimization - Environmental Product
Declarations
Section 19
Integrative Process
http://bit.ly/2fQPKZG
Attachment 2 DOE G 413.3-6B
Page 2-2 4-5-2020
2. GP Checklist (https://go.usa.gov/xRhk8) – Link provides a legible version of the image
below.
https://go.usa.gov/xRhk8
Foreword
1 Purpose
1.1 Overview
1.2 Acquisition Approaches
1.3 Applicability
2 Basis
2.1 DOE Directives
2.2 Executive Order and Implementing Instructions
2.3 Guiding Principles for Sustainable Federal Buildings
2.4 Office of Management and Budget Circular A-11 Guidance
2.5 Acquisition Regulations and Guidance
3 Background
3.1 Other Resources
3.2 Guiding Principles
3.3 LEED Certification
3.4 Equivalence and Training
4 Roles and Responsibilities
4.1 Chief Executive for Project Management
4.2 Project Management Executive
4.3 Program Secretarial Officer
4.4 Federal Project Director
4.5 Director of the Office of asset management
4.6 Project Analyst in Office of Project Management
5 Schedule
6 Deliverables
6.1 Initiation Phase
6.2 Definition Phase
6.2.1 Planning Documents
6.2.2 Integrated Project Team
6.2.3 LEED Registration
6.2.4 Identifying Energy Goals
6.2.5 Commissioning
6.2.6 LEED and GP Site Credits
6.2.7 LEED and GP documentation
6.2.8 LEED Minimum Requirements
6.2.9 LEED Waiver
6.2.10 Communication with the Designers
6.2.11 Conflicting Requirements
6.2.12 Scorecards and Checklists
6.3 Execution Phase, Prior to Critical Decision-2
6.3.1 Assigning Responsibility
6.3.2 Routine Progress Meetings
6.3.3 Preliminary Design
6.3.4 Use of “Not Applicable” for GPs
6.3.5 LEED Credit and GP Element Documentation
6.3.6 LEED Waiver
6.3.7 Project Reviews
6.3.8 USGBC Split Review
6.4 Execution Phase, Prior to Critical Decision-3
6.4.1 Final Design
6.4.2 Scorecards and Checklists
6.4.3 Project Reviews
6.4.4 LEED Credit and GP Element Documentation
6.4.5 Commissioning
6.5 Execution Phase, Prior to Critical Decision-4
6.5.1 LEED Credit and GP Element Documentation
6.5.2 Commissioning
6.5.3 Benchmarking
6.6 Project Closeout Phase
6.6.1 Third-Party Entity
6.6.2 LEED Certification
6.6.3 GP Documentation
6.6.4 GPs for Existing Buildings
6.7 Tailoring and Exceptions
6.7.1 LEED Gold Waiver Procedures
6.7.2 LEED Non-Applicability Documentation
6.7.3 Non-Applicable GP Element Documentation
6.8 Summary System Diagram
7 Acronyms and Abbreviations
8 Sources Cited
Attachment 1: Resources by Guiding Principle Element
Attachment 2: Example LEED Scorecards and GP Checklists