DOE G 413.3-3A, Safeguards and Security for Program and Project Management
Functional areas: Program Management, Property Management, Safety and Security
The Guide provides a methodology for implementing the safeguards and security requirements of DOE O 413.3B. Supersedes DOE G 413.3-3.
Version history and related documents
Superseded by
A newer version replaces this document.
Supersedes
Earlier documents this one replaced.
Related documents
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
AVAILABLE ONLINE AT: INITIATED BY:
www.directives.doe.gov Office of Management
DOE G 413.3-3A
Approved: 08-15-2013
SAFEGUARDS AND SECURITY FOR
PROGRAM AND PROJECT
MANAGEMENT
[This Guide describes suggested non-mandatory approaches for meeting requirements.
Guides are not requirements documents and are not to be construed as requirements in
any audit or appraisal for compliance with the parent Policy, Order, Notice, or Manual.]
U.S. Department of Energy
Washington, D.C. 20585
NOT
MEASUREMENT
SENSITIVE
DOE G 413.3-3A i (and ii)
08-15-2013
FOREWORD
This Department of Energy (DOE) Guide is for use by all DOE elements.
This Guide is intended to provide a methodology for implementing the safeguards and security
requirements of DOE O 413.3B, Program and Project Management for the Acquisition of
Capital Assets, dated 11-29-2010. DOE Guides are not requirement documents and should not
be construed as requirements. Guides are part of the DOE Directives Program and provide
suggested ways of implementing Orders, Manuals, and other regulatory documents.
Beneficial comments (recommendations, additions, and deletions) and any pertinent data that
may improve this document should be sent to: The Department of Energy, Office of Acquisition
and Project Management, Attention: MA-63, 1000 Independence Avenue, SW, Washington, DC
20585.
DOE G 413.3-3A iii (and iv)
08-15-2013
CONTENTS
SECTION I. INTRODUCTION ................................................................................................ I-I-1
1. GOAL ................................................................................................................ I-I-1
2. SCOPE ............................................................................................................... I-I-1
3. OBJECTIVES .................................................................................................... I-I-1
SECTION II. ROLES AND RESPONSIBILITIES ................................................................ II-II-1
1. UNDER SECRETARIES .................................................................................. II-1
2. FEDERAL PROGRAM/SITE OFFICE MANAGER .................................... II-II-1
3. FEDERAL PROJECT DIRECTOR ................................................................ II-II-1
4. FEDERAL SITE SECURITY PROGRAM REPRESENTATIVES .............. II-II-2
5. OTHER INTEGRATED PROJECT TEAM MEMBERS .............................. II-II-2
6. SITE CONTRACTOR PROJECT MANAGER ............................................. II-II-3
7. SITE CONTRACTOR SECURITY REPRESENTATIVE ............................ II-II-3
8. SITE CONTRACTOR EMERGENCY MNGT. REPRESENTATIVE ......... II-II-3
9. HQ SECURITY PROGRAM OFFICES ........................................................ II-II-3
SECTION III. SAFEGUARDS AND SECURITY PROGRAM BACKGROUND ................. III-1
SECTION IV. DESIGN CONSIDERATIONS AND INTERFACES ................................ IV-IV-1
1. BASIS FOR DESIGN STANDARDS ......................................................... IV-IV-1
2. FACILITY AND PHYSICAL PROTECTION STANDARDS .................. IV-IV-1
3. SECURITY SYSTEM DESIGN.................................................................. IV-IV-2
4. SECURITY SYSTEM ALTERNATIVES EVALUATION ....................... IV-IV-3
SECTION V. SAFEGUARDS & SECURITY AND
THE CRITICAL DECISION PROCESS ................................................................... V-V-1
1. INITIATION PHASE (PRE-CONCEPTUAL PLANNING—
Section 2
PRE-CRITICAL DECISION-0) ..................................................................... V-V-1
2. DEFINITION PHASE (CONCEPTUAL DESIGN—
POST CRITICAL DECISION-0) ....................................................................... V-3
3. EXECUTION PHASE I (PRELIMINARY DESIGN PHASE) ..................... V-V-4
4. EXECUTION PHASE II (FINAL DESIGN PHASE
AND CONSTRUCTION) ............................................................................... V-V-5
5. TRANSITION/CLOSEOUT PHASE/OPERATION PHASE ....................... V-V-6
ATTACHMENT 1. SAFEGUARDS AND SECURITY PROJECT CHECKLIST
ATTACHMENT 2. REFERENCES
DOE G 413.3-3A I-1
08-15-2013
SECTION I. INTRODUCTION
1. GOAL. To ensure that safeguards and security requirements are identified and integrated
into a capital asset project early in its development timeline and that their implementation
and effectiveness are assessed throughout the project life cycle. Protection strategies
should consider potential threats to assist early on during the asset design process.
Establishing and integrating safeguards and security requirements early in the project is
necessary for efficient project planning and cost estimating to avoid scope creep later in
the project which leads to cost and schedule overruns. Good front end planning is a
fundamental principle of good project management that enhances the probability of
completing projects within the initially approved project baseline. The initial
identification of safeguards and security requirements and the requirements of other
critical disciplines (e.g., safety), and the integration with other project functional and
physical requirements is critical to the development of the best overall cost effective
acquisition strategy solution for the project.
2. SCOPE. This Guide addresses the implementation steps for achieving safeguards and
security systems that support the Department’s protection objectives. It provides a logical
process for the implementation of accepted safeguards and security principles, which are
translated into system requirements and configuration with an auditable cost and
schedule; from project/program initiation through the transition/closeout phases.
3. OBJECTIVES.
a. Provide safeguards and security guidance to Federal Project Directors and Federal
Program/Site Office Managers (and to contractors and subcontractors as
applicable) in identifying and implementing key safeguards and security
components of their projects; and integrating safeguards and security
consideration into each acquisition management phase (initiation, definition,
execution and transition/closeout).
b. Define the project’s safeguard and security related features and functions, as
developed or required by the security program and security policies, early enough
to minimize impact on operations;
c. Identify the function of the federal site security program representative who
serves as the security design point of contact for security features and is a member
of the integrated project team during the entire project cycle.
d. Facilitate communication and interaction between the site security professionals;
classification and Unclassified Controlled Nuclear Information (UCNI) officials;
the integrated project team; and the members of the project design team.
e. This guide applies to the DOE elements specified in DOE O 413.3B, including
the National Nuclear Security Administration (NNSA), which fund, direct, and
manage acquisition projects as defined by such Order.
Section 3
I-2 DOE G 413.3-3A
08-15-2013
As used in this guide, “security” refers to both safeguards and security as it is applicable
to the project or facility regardless of the type of building, structure, or facility; and
whether it is new or a modification to an existing facility.
This Guide provides suggested approaches for implementing security provisions within
the security functional areas as specified in DOE O 413.3B, Program and Project
Management for the Acquisition of Capital Assets.
The DOE G 413.3-X series provides companion supplemental project management
guidance. Specific regulatory citations are provided in the body of the Guide series. This
Guide provides explanations and examples for implementing requirements of
DOE O 413.3B and specific to compliance with safeguard and security requirements
provisions, including requirements to identify classification and controlled unclassified
information.
Except for requirements established by a regulation, contract, or DOE policy means, the
provisions in this Guide are DOE’s views on acceptable methods of program
implementation and are not mandatory. Conformance with this Guide should not,
however, create an inference of compliance with the related requirements. Alternative
methods of program implementation that are demonstrated to provide an equivalent or
better level of protection are acceptable. DOE encourages its contractors to go beyond the
minimum requirements and to pursue excellence in their programs.
The words “should” and “may” are used to denote recommended or optional
implementation guidance that could be used to meet the requirements of the DOE O
413.3B. This Guide is applicable to all DOE activities that are subject to the requirements
of DOE O 413.3B.
DOE G 413.3-3A II-1
08-15-2013
SECTION II. ROLES AND RESPONSIBILITIES1
1. UNDER SECRETARIES.
a. Receive Acquisition Executive (AE) authority from the Secretarial Acquisition
Executive (SAE), as appropriate (see DOE O 413.3B for more details on
delegation of authority to Acquisition Executives).
b. Under DOE O 470.4B, the Associate Administrator for Defense Nuclear Security,
the Under Secretary of Science, and the Under Secretary for Energy are
designated as the DOE cognizant security officer for the organizations under the
purview of their Offices, and may delegate this authority officially in writing as
appropriate to carry out the associated responsibilities.
c. Hold accountability for project-related site environment, safety and health, and
safeguards and security.
2. FEDERAL PROGRAM/SITE OFFICE MANAGER.
a. Ensures that the Federal Project Director has adequate support on the federal
integrated project team and access to other project specific support as needed
throughout the project life cycle for safeguards and security.
b. Oversees the project line management organization, including the integrated
project team membership, and ensures that the identified individuals have
adequate time to devote to the task.
c. Approves change control actions at the levels agreed upon in the project execution
plan, including security scope changes.
d. Approves the project security management documents as stipulated in the Project
Execution plan.
3. FEDERAL PROJECT DIRECTOR.
a. As head of the integrated project team, relies on the project team members to help
identify requirements, and safety and security issues.
b. Works with integrated project team members to assure cost effective integration
of security with safety and other project areas.
Section 4
1 Safeguard and security provisions from DOE O 413.3B, Program and Project Management for the Acquisition of
Capital Assets, Appendix B, dated 11-29-2010; and DOE O 470.4B, Admin Chg. 1, Safeguard and Security
Program, dated 2-15-2013.
II-2 DOE G 413.3-3A
08-15-2013
c. Works with the contractor project manager and integrated project team
representatives and the design team to resolve security issues in an effective and
efficient manner.
d. Assures safeguards and security requirements are integrated into the project
documents.
e. Approves changes within control ranges set in the safeguards and security aspects
of the project execution plan.
4. FEDERAL SITE SECURITY PROGRAM REPRESENTATIVES.
a. Represent the security interests of the site and are the points of contact for
resolving security issues on the integrated project team (IPT).
b. Responsible for ensuring that safeguards and security concerns and criteria are
identified, to include oversight of reviews for the safeguard and security of
classified and controlled unclassified information (see DOE O 470.4B, Appendix
A; DOE O 475.2A, Identifying Classified Information; DOE O 471.1B,
Identification and Protection of Unclassified Controlled Nuclear Information, for
requirements).
c. Work with the Federal Project Director, contractor project manager, and the
contractor site security representatives to monitor incorporation of security
requirements into the design and construction of a project.
d. Participate/lead in facility security vulnerability assessments and/or security risk
analysis in coordination with specialized security vulnerability analysts from
contractor staff and consultants, as required.
e. Review design documents (i.e., safety and security), operational procedures, and
readiness assessments.
f. Concur in security operations procedures for the facilities being built.
g. Monitor any changes to site operational requirements which may affect the
security project approved baseline.
h. Validate/approve the System Requirements Documents for Safeguards and
Security to ensure that all requirements are identified and addressed.
5. OTHER INTEGRATED PROJECT TEAM MEMBERS
a. IPT members represent their disciplines and work to ensure that design and
construction incorporate the security area concerns and requirements.
DOE G 413.3-3A II-3 (and II-4)
08-15-2013
b. Ensure that reviews for classified and controlled unclassified information are
conducted by appropriate authorities in accordance with Departmental regulations
and directives.
6. SITE CONTRACTOR PROJECT MANAGER.
a. Implements the design and construction activities for security.
b. Works with the Federal Project Director and integrated project team to ensure that
security project requirements are being met.
c. Approves changes within control ranges set in the project execution plan.
d. Throughout the life cycle of the project ensure that plans developed in previous
phase(s) are periodically updated based on increased planning maturity.
7. SITE CONTRACTOR SECURITY REPRESENTATIVE
a. Works with the site project manager to ensure that security requirements and
issues are being properly represented and resolved.
8. SITE CONTRACTOR EMERGENCY MANAGEMENT REPRESENTATIVE.
a. Works with the site project manager to ensure that security requirements and
issues, and potential interfaces with emergency management assets are being
properly represented and resolved.
9. HQ SECURITY PROGRAM OFFICES.
Section 5
a. Provide assistance in the areas of guidance and expert opinion in the resolution of
security requirements, issues, deviations and technologies.
b. Exercises project oversight responsibilities and monitors the program
requirements as outlined in the program requirements document and the project
execution plan.
c. Review and concur on the safeguard and security aspects of the Project Execution
Plan.
DOE G 413.3-3A III-1
08-15-2013
SECTION III. SAFEGUARDS AND SECURITY PROGRAM BACKGROUND
All DOE facilities should be evaluated for potential risks to employees, the public, and the
environment. DOE O 470.4B, Admin Chg. 1, Safeguard and Security Program, dated 2-15-2013;
DOE O 470.3B, Graded Security Protection (GSP) Policy, dated 8-12-2008; and successor
Orders/Policies, contain requirements for determining the level of protection, based on facility
functions and potential security risks and graded security protection policy requirements. This
also includes Cyber Security under the provisions of DOE O 205.2B, Department of Energy
Cyber Security Program, dated 3-11-2013, and DOE O 150.1, Continuity Program, dated
5-08-2008.
A preliminary safeguards and security review should be initiated during the project conceptual
design phase and further developed during the preliminary and final design phases. In most
situations, these reviews are included in the project planning and design documentation (e.g., in
conceptual design reports, or critical decisions). Facility design and construction features,
identified as a result of security reviews, should be factored early into the conceptual design
before establishing the project cost range at Critical Decision-1, requesting funding authorization
for design, and establishing the project performance baseline at Critical Decision-2. The last is
especially important when the project will involve construction of a protected area, material
access area, and/or special designated security areas due to the substantial scope and cost
associated with these types of facilities.
An appropriate security plan should be completed and approved prior to the start of construction
(including site preparation), consistent with DOE O 470.4B, Safeguards and Security Program,
Admin Chg.1. The plan should be updated as appropriate to reflect changes affecting security
that are made to the facility during its lifetime.
DOE assets are defined and protection standards outlined in DOE O 470.3B, Graded Security
Protection (GSP) Policy. Depending on the asset being protected, protection strategies range
from a combination of compliance with DOE security policies to specific performance standards
that should be met. This constitutes a graded and risk-based approach ensuring the highest levels
of protection for those assets where loss, theft, compromise, and/or unauthorized use would
seriously affect national security, the environment, Departmental programs, and/or
public/employee health and safety.
For those assets requiring high physical protection the Federal Project Director should make
reference to the GSP Policy because additional performance-based security measures may
necessitate a security vulnerability assessment/security assessment to be performed by the site to
determine what additional security measures are necessary to achieve an integrated protection
system consisting of detection, assessment, communication, response, interruption, and
neutralization.
Section 6
The DOE O 470.3B establishes minimum design principles based on vulnerability assessments.
Adherence to this directive should provide reasonable assurance that safeguards and security
designs embody the DOE tenets of providing graded security and establishing defense in-depth.
For example, a security area denotes a physically defined space containing departmental security
III-2 DOE G 413.3-3A
08-15-2013
assets and subject to physical protection and access controls. Security areas are established by
the requirements of DOE O 473.3, Protection Program Operations, dated 6-27-2011.
The type of security area established depends on the nature of the security interests to be
protected. The following list of security areas is based on the restrictive nature for the security
interests protected:
general access area
property protection area,
limited area,
protected area,
material access area, and
special designated security areas.
The general access area (to an office building or administrative area) is the least restrictive area,
and the most restrictive is a material access area which is located within a protected area.
Physical protection strategies for the physical protection of DOE facilities must be developed,
documented, and implemented consistent with both the Graded Security Protection Policy,
formerly the Design Basis Threat Policy; and the overall National policy to protect against
radiological, chemical, or biological sabotage (specifically to DOE described in DOE O 470.3B,
Graded Security Protection (GSP) Policy, dated 8-12-2008).
The following DOE Directives describe DOE policy and procedures to implement various
aspects of safeguards and security which should apply to the protection of capital asset projects:
DOE O 470.3B, Graded Security Program (GSP) Policy, dated 8-12-2008;
DOE O 470.4B, Admin Chg. 1, Safeguards and Security Program, dated
2-15-2013;
DOE O 474.2, Admin Chg. 2, Nuclear Material Control and Accountability,
dated 11-19-2012;
DOE O 473.3, Protection Program Operations, dated 6-29-2011; and
DOE O 471.6, Chg. 1, Information Security, dated 11-23-2012.
Requirements for identifying and protecting classified and controlled unclassified information
are specified in the following references:
10 CFR Part 1045, Nuclear Classification and Declassification. It establishes the
Government-wide policies and procedures for implementing sections 141 and 142
DOE G 413.3-3A III-3 (and III-4)
08-15-2013
of the Atomic Energy Act of 1954 for classifying and declassifying Restricted
Data (RD) and Formerly Restricted Data (FRD) and implements the requirements
of Executive Order 13526 concerning National Security Information (NSI) that
affects the public.
Executive Order 13526, Classified National Security Information. It prescribes
the Government-wide system for classifying, safeguarding, and declassifying
NSI.
32 CFR Part 2001, Classified National Security Information. Implements the
requirements prescribed in Executive Order 13526 for classifying, safeguarding,
and declassifying NSI.
DOE O 475.2A, Identifying Classified Information, dated 2-01-2011. It
establishes requirements for managing the DOE program including details for
classifying and declassifying information, documents, and material classified
under the Atomic Energy Act (RD, FRD, and Trans Classified Foreign Nuclear
Information) or Executive Order 13526 (National Security Information), so that it
can be protected against unauthorized dissemination.
Section 7
10 CFR Part 1017, Identification and Protection of Unclassified Controlled
Nuclear Information. It establishes Government-wide policies and procedures for
implementing the requirements of Section 148 of the Atomic Energy Act of 1954
concerning the identification and protection of certain unclassified but sensitive
Government information concerning atomic energy defense programs.
DOE O 471.1B, Identification and Protection of Unclassified Controlled Nuclear
Information, dated 3-01-2010. It establishes the requirements for managing the
DOE program for indentifying and protecting UCNI.
DOE Order 471.3, Admin. Chg. 1, Identifying and Protecting Official Use Only
Information, dated 1-13-2011, and DOE M 471.3, Admin. Chg. 1, Manual for
Identifying and Protecting Official Use Only Information, dated 1-13-2011. They
establish the requirements for the DOE program to identify certain unclassified
information as Official Use Only and to identify, mark, and protect documents
containing such information.
Also for unusual or special conditions the following directive provides the construction
requirements for the protection of classified information requiring extraordinary security
protection:
Intelligence Community Standard (ICS) 705-1, Physical and Technical Security
Standards for Sensitive Compartmented Information Facilities, dated 9-17-2010
Additionally, program office specific guidance (if any) should be referenced in the design and
construction of security related projects.
DOE G 413.3-3A IV-1
08-15-2013
SECTION IV. DESIGN CONSIDERATIONS AND INTERFACES
1. BASIS FOR DESIGN STANDARDS.
a. DOE security assets are to be protected from theft or diversion, sabotage,
espionage, loss or theft, and other hostile acts which could cause unacceptable
adverse impacts on national security, program continuity, or the health and safety
of employees, the public, or the environment.2
b. Levels of protection appropriate to particular safeguards and security interests are
to be provided in a graded fashion in accordance with potential risks to national
security and the health and safety of employees and the public.
c. Protection programs are tailored to address site-specific characteristics on the
basis of DOE directives and other requirements.
d. Site-specific protection programs describing the implementation of these
requirements are documented in protection program plans and/or site security
plans.
2. FACILITY AND PHYSICAL PROTECTION STANDARDS.
a. Planning, design, and installation of security systems should be determined in
consultation with the officially designated DOE cognizant security office and
should be consistent with security policies.
b. A key role of the security professional assigned to the integrated project team
should be to ensure that the best approach to meeting policy objectives is
identified.
c. The approach should provide a security solution that maintains compliance with
safeguard and security requirements, or includes approved deviation from; and
provides effective security, while minimizing security’s impact on project cost,
potential safety concerns, and operational impacts. The approach should also
consider interim and/or temporary safeguards and security measures that should
be implemented during the execution phase of the project.
d. Technologies should be used in lieu of staff to perform routine security functions
whenever possible and feasible. The design features should accomplish the
majority of the tasks.
Section 8
e. The application of these approaches should include cost to benefit analyses, and
documented returns on investment and break even points where possible.
2 Interagency Security Committee (ISC) Standard, Physical Security Criteria for Federal Facilities; ISC Standard,
Facility Security Level Determinations for Federal Facilities.
IV-2 DOE G 413.3-3A
08-15-2013
3. SAFEGUARDS AND SECURITY SYSTEM DESIGN. The basis for each discipline
standard should be addressed.
a. Successful design accounts for all requirements within the area’s applicability and
expected environmental conditions for the system to operate. For example, DOE
nuclear safety directives do not address malevolent acts, sabotage, or terrorist
activities, while security requirements are focused primarily on such actions.
Another example, while security may address the guns/gates/guards needed to
meet physical protection standards, the requirements for identifying classified and
controlled unclassified information and documents is found in other regulations
and DOE directives and are listed in Section III. For cyber security requirements
the applicable DOE directive is DOE O 205.1B, Department of Energy Cyber
Security Program.
b. Design should necessitate accommodating potential interactions and overlaps
among applicable requirements, such as those that might be encountered between
postulated security technologies and normal operation or accident conditions,
such as those required to be evaluated for life safety.
c. Controls should be established to prevent unauthorized access to security areas,
unauthorized activities within security areas, and unauthorized removal of
security interests. Where there are conflicts between the security requirements and
those of other disciplines, these need to be defined as early in the project as
practicable, so as to provide the time to reach the best overall solution to all
requirements. For example:
(1) Although building access points are often minimized for security reasons,
personnel egress from security areas should meet the requirements of
National Fire Protection Association 101 and the applicable portions of the
project building code (e.g., International Building Codes or National Fire
Protection Association 5000).
(2) Entrances to and exits from security areas should be designed for efficient,
yet controlled, movement of personnel or vehicles through designated
portals.
(3) Due to the security limitations on exiting certain buildings, alternative life
safety approaches, such as a safe haven, based on performance based
compliance with the National Fire Protection Association requirements,
may be necessary to meet the requirements of both disciplines.
(4) External and internal areas within security boundaries should be provided
with infrastructure support (e.g., electrical power, alarm communications
and control systems).
DOE G 413.3-3A IV-3 (and IV-5)
08-15-2013
4. SECURITY SYSTEM ALTERNATIVES EVALUATION.
a. During the conceptual and preliminary design phase, alternatives analysis of the
security system is performed along with the other major activities of the project,
including the evaluation of operational implications and estimated life-cycle costs
of security considerations of proposed alternatives and sites.
Section 9
b. To ensure consideration of all alternatives appropriate to the significance of the
threat, the project team should consult departmental programs supporting the
development or deployment of security technologies. Currently these include the
DOE Office of Health, Safety and Security and the NNSA Chief, Defense Nuclear
Security. These organizations should be able to provide technical and contact
information for security technologies being developed, tested, or deployed by the
Department or other agencies of the United States. Care should be taken to avoid
new untested systems (see DOE G 413.3-4, Technology Readiness Assessment
Guide, for managing technology risk in projects). They should not be installed at
DOE facilities unless there is a conscious decision that the site should be a field
test facility for those systems.
c. Project teams may need to request technical assistance from their officially
designated DOE cognizant security office. Communication is essential to ensure
that the facility is able to receive the technology and that its deployment is
appropriate for the facility.
DOE G 413.3-3A V-1
08-15-2013
SECTION V. SAFEGUARDS & SECURITY
AND THE CRITICAL DECISION PROCESS
Figure V-1 depicts the overall timeline of a project. The key security tasks associated with each
project phase are presented in Table V-1, Overarching Areas of Consideration. Note that these
tasks need to be finished to complete the phase and support the Critical Decision. However, it is
important to start these efforts early in the phase, providing time for project interaction in support
of these tasks and to address project changes they drive.
Figure V-1 Typical DOE Project Timeline
1. INITIATION PHASE (PRE-CONCEPTUAL PLANNING—PRE-CRITICAL
DECISION-0).
For all projects, an early evaluation of probable security concerns and vulnerabilities
should be made by the federal program/site office manager. The site security office and
contractor’s security office should develop functional design requirements to meet
safeguard and security, and cyber security requirements using the Graded Security
Protection Policy (DOE O 470.3B or successor documents) and applicable DOE
safeguards and security, and cyber security requirements. When indicated by this
evaluation, a security professional for the project should be identified to serve as
technical advisor and integrated project team member on security matters for the life of
the project.
If this preliminary security evaluation indicates that the project is classified, the DOE site
office manager and Federal Project Director should determine, with assistance from the
security staff, the actions necessary for identifying the level of security and the associated
requirements cited in Appendix B, Section 1, Chapter VII of DOE O 470.4B, Safeguards
and Security Program. This action should identify the scope of the access authorizations
required for project personnel and the need for identifying procedures for submitting the
necessary changes to the Facility Data and Approval Record.
V
-2
D
O
E
G
413.3-3A
07-15-2013
Table V-1. Overarching Areas of Consideration.*
Initiation
Phase (Pre-Conceptual Planning)
Definition
Phase (Conceptual Design)
(Prior to CD-1)
Execution
Phase I (Preliminary
Design Phase)
(Prior To CD-2)
Execution
Phase II (Final Design
Phase and Construction)
(Prior to CD-3)
Transition/Closeout
Phase/Operational
Phase
Section 10
Safeguards and security program planning
and management integrate physical
protection, protective force, information
security, technical security programs,
personnel security, and nuclear material
control & accountability.
Develop functional design requirements to
meet safeguard and security and cyber
security requirements using the Graded
Security Protection Policy.
Identify safeguards and security
Representative for project.
Identify general safeguards and
security requirements:
- threat assessment;
- materials control and
accountability;
- physical security;
- information security;
- personnel security;
- cyber security;
- barriers, access controls,
explosives, communications.
Conduct preliminary
security vulnerability
assessment/ security
assessments.
Construct/order necessary
safeguards and security
components supporting the
project as per Acquisition
Plan.
Submit final Security
Vulnerability Assessment /
Security Assessment Report.
Have approved
security plans: e.g.
facility data and
approval record,
materials control and
accountability, site
security & emergency
mngt. plan, or site
safeguards and security
and emergency mngt.
plan.
Identify major safeguards and security
assets associated with the project.
Information and Matter:
- classified;
- unclassified controlled;
Accountable Material:
- nuclear;
- radiological;
- classified parts;
Type of Safeguards and Security
Function:
- classified & controlled unclassified
information;
- classified & controlled unclassified parts;
- nuclear material processing;
- nuclear radiological material storage.
Look at safeguards and security
programs/projects impacting the
new projects or identify the
impacts this project may have on
existing programs or operations.
Formulate data for conduct of
preliminary security vulnerability
assessment/security assessment
for the selected project
alternative after CD-1 in
conformance with
DOE O 470.4B and DOE O
413.3B.
Prepare system
configuration.
Identify specific
safeguards and security
requirements such as:
materials control and
accountability;
physical security;
information security;
personnel security;
cyber security.
Obtain approval for any
deviations from
Departmental security
requirements.
Prepare training documents
(operations & maintenance)
based on final installed
system.
Begin training as necessary
for the various topical areas
as identified.
Complete safeguards
and security and
emergency
management
professional training.
Assess application of Graded Security
Protection (GSP) Policy.
Identify types of safeguards and
security range of costs associated
with each Phase and Critical
Decision.
Identify resources
needed.
Finalize organizational
structure.
Conduct and complete
an operations readiness
review for security.
Formulate order of magnitude range of
costs.
Identify safeguards and security
risks to the project alternatives.
Refine cost and
schedule estimates to
support CD-2.
Prepare safeguards and
security plans/procedures.
Submit Lessons
Learned Report
*Consistent with DOE O 413.3B, DOE O 470.4B, DOE O 473.3, DOE O 474.2, DOE O 471.6, & DOE O 205.1B CD = Critical Decision
DOE G 413.3-3A V-3
08-15-2013
Note to Figure V-1 – Information, documents, or material generated at any phase of the
project should be reviewed by appropriate officials (e.g., Derivative Classifiers, UCNI
Reviewing Officials) in accordance with applicable departmental directives and
regulations when it has the potential to contain classified or controlled unclassified
information as part of information security.
Section 11
2. DEFINITION PHASE (CONCEPTUAL DESIGN—POST CRITICAL DECISION-0).
a. Once mission need is approved (Critical Decision-0), the site security program
representative should begin to plan for the role of security within the project. This
represents a critical point for determining and defining the security involvement
in the project.
(1) Prior to beginning conceptual design, the site security program
representative should develop a functional design document based on
DOE safeguard and security and cyber security orders. This document
should provide the baseline for conceptual design alternatives.
(2) During conceptual design, the site security program representative should
evaluate the security risk of the proposed facility and document the
security requirements (e.g. physical security devices and systems, nuclear
materials safeguards, information security and any specialized security
equipment) that result from this evaluation.
(3) The site security program representative should summarize requirements
associated with safeguard and security assets being protected/affected by
the project. The site security program representative and the Federal
Project Director working with the Contractor Project Manager should
review and concur with the alternative protection and control strategies,
along with estimate ranges for capital and operating costs of alternatives
which meet security policy requirements.
(4) This should occur with all topical security areas to ensure that alternatives
for protection and control of security risks are evaluated for effectiveness
and for long-term costs.
(5) This information should be incorporated into the conceptual design and
cost estimates, to be used to evaluate the project alternatives for Critical
Decision-1 (CD-1).
b. For facilities that will handle, store, or process categories I or II quantities of
Special Nuclear Materials, or where roll up quantities to a Category I quantity is
credible, or as defined by their program office as “mission critical” an
identification of general safeguard and security requirements for the
recommended alternative should be performed prior to CD-1 (this should be
followed by a preliminary security vulnerability assessment/security assessment
prior to CD-2).
V-4 DOE G 413.3-3A
08-15-2013
c. The identification of general safeguard and security requirements should be based
upon the conceptual design of the facility and uses staffing and operational
assumptions. It may make recommendations regarding changes to the physical
security, protective force, material control and accountability, or other
administrative/engineered controls for the proposed facility in order to mitigate
potential risks to Departmentally approved ranges of risks. These
recommendations should be considered and incorporated, where applicable into
the conceptual design for the facility at CD-1. The identification of the safeguards
and security requirements for the selected alternative at CD-1 should have
assessed the potential risks to Departmental assets, if the facility were built to this
design. This process should be conducted with the assistance of trained security
analysts familiar with DOE requirements.
d. At the conclusion of conceptual design (CD-1), the Federal Project Director
should know the impact of incorporating adequate safeguards and security
elements into the project (e.g., security’s impact on the project will be significant,
minimal, or serve in an advisory role ensuring safeguards and security
departmental requirements are identified).
Section 12
3. EXECUTION PHASE I (PRELIMINARY DESIGN PHASE). Once CD-1 has been
obtained, and design funds authorized, the preliminary design phase commences.
a. The integrated project team should closely monitor the preliminary design efforts
to ensure that all project requirements are being incorporated.
b. The site security program representative should stay involved by assisting in
refining security strategies, defining and validating the security system
performance requirements; evaluating the responses to the safeguard and security
requirements; determining the physical security, alarm station, material control
and accountability, administrative/engineered controls, and other infrastructure
requirements for the proposed facility; and preparing more mature cost estimates.
(1) Prior to Critical Decision-2 (CD-2), conduct a preliminary security
vulnerability assessment/security assessment; if necessary (see DOE O
413.3B and DOE STD 1192-2010, Vulnerability Assessment Standard,
dated February 2010).
(2) If at all possible, the same team of security analysts should perform a
preliminary security vulnerability assessment/security assessment on the
preliminary design documents. Due to the complex nature of these
assessments, it is suggested that the resulting preliminary security
vulnerability assessment be peer reviewed by an independent team of
experienced analyst prior to CD-2.
(3) This should offer an opportunity to easily compare results from the
identification of the safeguard and security requirements with the
preliminary security vulnerability assessment prior to CD-2 and reconcile
DOE G 413.3-3A V-5
08-15-2013
differences. As indicated before, the results of this assessment are to be
incorporated, based on the identified security risks, into the facility design.
b. Depending on the scope of and risk of assets associated with the project, the
resources necessary to conduct security vulnerability assessments and security
technology option analyses might be significant.
c. Risks may be identified in the course of the preliminary security vulnerability
assessment or the security technology option analysis and captured in the risk
register, which is part of the risk management plan. Additionally, security designs
and associated electrical; communications; heating; ventilation; and air
conditioning; and other appropriate support infrastructures for the security
features of the project should be integrated into the overall project design and
engineering package. These vulnerability assessments should add separate
assessments from the counterintelligence, telecommunications, or cyber security
programs which normally are not included in the security vulnerability
assessments, or security vulnerability technology option analysis, which could
add additional equipment and infrastructure support requirements.
d. Where possible, industry standards should be used to plan for future growth or
technological changes in the security systems.
e. When developing the project schedule, the need for and timing of construction
personnel with security clearances should be ascertained. The Federal Project
Director should ensure that sufficient time exists for the acquisition of services
requiring security clearances.
f. Risks identified during the security vulnerability assessments should be included
in the project risk management plan and accounted for in the project cost
estimates to include cost and schedule contingency allowances for safeguard and
security elements of the project.
Section 13
g. At CD-2, the project should include all safeguard and security elements that
would impact the project scope, cost and schedule performance baseline.
4. EXECUTION PHASE II (FINAL DESIGN PHASE AND CONSTRUCTION). After
CD-2 has been obtained, the final design phase continues toward conclusion.
a. The site security program representative should stay engaged in monitoring and
providing assistance to the design team during final design. Engagement should
include: reviewing design documents against the functional requirements
document and the security vulnerability assessment; ensuring the infrastructure is
in place to support safeguard and security requirements; being involved in
cost/benefit tradeoffs discussions/decisions, and in conduct of limited scope
security vulnerability assessments of proposed design changes.
V-6 DOE G 413.3-3A
08-15-2013
b. Prior to CD-3 finalize the security vulnerability assessment/security assessment
report. At the conclusion of final design, all project requirements should be
satisfied by the facility design and/or proposed operational features. The site
security program representative of the integrated project team should ensure
approval of the selected security system design by both contractor and field office
managers.
c. Testing requirements and acceptance criteria are prepared for security systems
and for system components, and acceptance tests, based upon required
performance levels, should be specified for all security-relevant systems in the
proposed contract documents for construction.
d. Upon approval of Critical Decision-3 (CD-3) and the start of construction,
security should provide support to construction activities of necessary security
initiatives, begin safeguards and security-identified training objectives, finalize
organizational structure, and prepare appropriate security plans and procedures
necessary to support the project.
e. The scheduling of system operations and maintenance training should take place
along with acceptance plan preparation and approval by the Federal Project
Director.
f. The acceptance plan includes the supporting operations and maintenance manuals
and procedures. Project activities that are in progress in parallel with construction
include final preparation of plans and procedures for facility operations. This
includes acceptance testing of systems as construction is completed and the
facility is transferred from the project to operations.
g. The site security program representative should continue to monitor and evaluate
the impact of design or concept of operation changes that occur during
construction, or be satisfied by an approved deviation. The impact of these
changes should be reported to the Federal Project Director and reported in the
appropriate document of record.
5. TRANSITION/CLOSEOUT PHASE/OPERATION PHASE.
a. During the Transition/Close-out phase, all security system documentation is
reviewed and an acceptance determination made by the Federal Project Director.
System component and complete system acceptance testing is evaluated against
the test and acceptance plan. For security, efforts leading to Critical Decision-4
(CD-4) should represent an approved security plan, procedures, trained security
professionals on-hand, and a successful Operational Readiness Review.
b. Prior to CD-4, the final update of the Security Vulnerability Assessment/Security
Assessment should be prepared, with a resulting Final Security Vulnerability
Assessment/Security Assessment Report. This report should document the
installed security systems and features, as well as demonstrate how the facility
Section 14
DOE G 413.3-3A V-7 (and V-8)
08-15-2013
design, construction, and operations satisfy security requirements, or can be
accomplished by an approved deviation from Departmental security requirements.
c. CD-4 is the achievement of the project completion criteria defined in the Project
Execution Plan at which the operations organizations assume responsibility for
starting operations and maintenance. The facility/site Management and
Operations Group takes over the responsibility for the management, operation,
and associated support including security.
DOE G 413.3-3A Attachment 1
08-15-2013 Page 1
SAFEGUARDS AND SECURITY PROJECT CHECKLIST
While Table V-1 gives the basics of Safeguards and Security, the following checklist gives the
Federal Project Director more detail of how to integrate the safeguards and security disciplines
into the critical decision phases of a project.
As used in this attachment, “security” refers to both safeguards and security as it is applicable to
the project or facility regardless of the type of building, structure, or facility and whether new or
a modification. Security assessments should include reviews for the protection of classified
information and unclassified controlled nuclear information as required in the Directives cited in
Section III of this Guide. These lists are not meant to be all-inclusive. It is suggested that they be
used in conjunction with other tools and techniques such as, but not limited to, lessons learned,
brain-storming, scenario planning, similar projects, and subject matter experts.
1. INITIATION PHASE (PRE-CONCEPTUAL PLANNING – PRE CD-0):
a. Safeguards and security point of contact is designated by the Federal program/site
office manager as a member of the integrated project team as appropriate and
informed on the parameters of the potential project and mission need.
(1) Classification as new facility or retrofit.
(2) Classification of the type of facility (e.g., research, production,
administrative/computing facility, nuclear and/or radiological material
storage, processing with or without classified parts).
(3) Estimate of population for the facility (e.g., numbers and origin).
(4) Potential locations for the facility.
(5) Existing facility or infrastructure upgrade project (e.g., fire safety upgrade,
security systems upgrade, adding classified capabilities to a formally
unclassified facility).
b. Begin identification of potential security-related assets associated with the project.
(1) Special nuclear materials, other nuclear material, radiological material,
biological assets (virus samples, etc.), chemical inventories, classified
and/or controlled unclassified information or parts, sensitive
compartmented information, critical assets, high cost or unique items, high
availability items [fire station, emergency operations center, etc.].
(2) Potential physical size and location of the project.
(3) Potential for hazardous materials.
(4) Potential impacts to protective force size and posture.
Attachment 1 DOE G 413.3-3A
Page 2 08-15-2013
(5) Potential interfaces with emergency management/response and fire
department response assets due to nature of the facility.
(6) Impacts on existing security infrastructure/operations.
(7) Assess the graded security protection (GSP) policy and other
Departmental security directives for application to the project.
c. Establish relationships with other team members or disciplines involved to ensure
programmatic integration.
Section 15
(1) Operations.
(2) Safety (i.e. life safety; environment, safety and health; and nuclear safety).
(3) Engineering.
(4) Information/cyber security technologies/Technical Security Program.
(5) Classified design. Plan to minimize/segregate the classified portion of the
design and train the project team in the plan. The goal is to minimize the
cost of the design effort.
(6) Emergency Management.
(7) Budget [i.e. review (of) security costs].
Note: See Appendix F, DOE G 413.3-18A, Integrated Project Team Guide for
Formation and Implementation, for special considerations for nuclear projects.
The need for classified and controlled unclassified information reviews should be
considered.
d. Preliminary schedule for major security related milestones and associated
resources.
(1) Development of a safeguard and security functional requirements
document to assist in concept development.
(2) Conduct of security vulnerability assessments/security assessments.
(3) Security system design initiated and completed.
(4) Security documentation prepared, updated to include any deviations from
Departmental security requirements, and completed (e.g., security
vulnerability assessment/security assessment; security plan; materials
control and accountability plan; security clearances; Technical Security
Program documentation, if applicable).
DOE G 413.3-3A Attachment 1
08-15-2013 Page 3
(5) Security tests (all safeguards and security functions).
(6) Security operational readiness review.
2. DEFINITION PHASE (CONCEPTUAL DESIGN – PRE CD-1):
a. Confirm the parameters of the project and mission need.
(1) New facility or retrofit.
(2) Type of facility (e.g. research, production, sensitive compartmented
information, administrative/computing facility).
(3) Population of the facility.
(4) Potential locations for the facility.
(5) Existing facility or infrastructure upgrade project (e.g. fire safety upgrade,
security systems upgrade, adding classified capabilities to a formerly
unclassified facility, electrical power distribution and communications).
(6) Perform alternative analysis and ensure security risks for the
recommended alternative are identified in the Risk Management Plan for
the project.
(7) Validate the application of the GSP policy and other Departmental
security directives to the facility and its operation.
(8) Develop an understanding of the facility’s concept of operations.
(9) Identify general safeguards and security requirements for the
recommended alternative prior to CD-1 based on the proposed facility
configuration.
b. Confirm security related assets identified in initiation phase and identify any new
security-related assets.
(1) Special nuclear materials, other nuclear material, radiological material,
biological assets (virus samples, etc.), classified and/or controlled
unclassified information or parts, sensitive compartmented information,
critical assets, high cost or unique items, high availability items (fire
station, emergency operations center, etc.).
(2) Potential physical size and location of the project.
(3) Potential for hazardous materials.
Attachment 1 DOE G 413.3-3A
Page 4 08-15-2013
(4) Complete plan to minimize/segregate the classified portion of the design
and training of the project team on the plan. Goal is to reduce design costs.
(5) Perform a red/black analysis of the major process equipment (gloveboxes,
etc.) to assist design with equipment spacing requirements (classified
process additional spacing requirements are often not factored in).
Section 16
(6) Potential impacts to safeguards and security staffing.
(a) Protective force size and posture.
(b) Materials control and accountability staffing.
(c) Information security staffing.
(d) Testing and maintenance or Performance Assurance Program
resources if the project is for a facility that requires a facility
clearance.
(e) Additions to infrastructure and maintenance.
(7) Potential interfaces with emergency management/response and fire
department response assets due to nature of the facility.
c. Integration with existing security infrastructure/operations.
(1) Finalize security-related functional and operational requirements for
inclusion in overall project functional and operational requirements
document.
(a) Identify general safeguards and security requirements, to include
barriers, explosives, security communications, protective force
support, entry/access controls, intrusion detection/surveillance
systems, and materials control and accountability systems.
(b) Identify operational and infrastructure support needed for
safeguards and security features.
Note: Cyber security is not a security organization function. This function
is primarily handled by the Chief Information Officer organization. This
should be coordinated with an information technology representative
rather than a security representative.
(2) Identify safeguards and security-related disciplines necessary to consult on
the project (e.g., physical security, information security, materials control
and accountability, operations security, protective force, personnel
security, etc.).
DOE G 413.3-3A Attachment 1
08-15-2013 Page 5
(3) Continue sharing information with other team members or disciplines
involved especially in regard to the overlap of design requirements that are
known or evolving.
(a) Operations.
(b) Safety (i.e. life safety; environment, safety and health; and
nuclear safety).
(c) Engineering.
(d) Information/cyber security technologies/technical security
programs.
(e) Project management with other members integrated project
team.
(f) Emergency management.
(4) Begin to finalize timeline for major security-related milestones and
associated resources.
(a) Conduct of preliminary computer-based security vulnerability
assessments/security assessment of the system and its
components, if necessary.
(b) Security system design initiated and completed.
(c) Security documentation updated and completed.
(d) Finalize the Security Vulnerability Assessment/Security
Assessment Report.
(e) Security performance/acceptance tests.
(f) Security operational readiness review.
(g) System operations and training documentation.
(h) System source code documentation.
(5) Begin to develop/review security-related costs and resources.
(a) Direct project related.
(b) Security operations.
(c) Project support related.
Attachment 1 DOE G 413.3-3A
Page 6 08-15-2013
3. EXECUTION PHASE I (PRELIMINARY DESIGN PHASE – PRE CD-2):
a. Conduct security-related assessments based on the confirmed parameters of the
project and mission need.
(1) New facility or retrofit.
(2) Type of facility (e.g. research, production, administrative/computing
facility).
(3) Population of the facility.
(4) Potential locations for the facility.
(5) Concept of facility operations.
(6) Existing facility or infrastructure upgrade project (e.g., fire safety upgrade,
security systems upgrade, and adding classified or controlled unclassified
capabilities to a formerly unclassified facility).
Section 17
b. Conduct security-related assessments based on the GSP policy, other
Departmental security directives, and the confirmed security-related assets.
(1) Special nuclear materials, other nuclear material, radiological material,
biological assets (virus samples, etc.), classified and/or controlled
unclassified information or parts, sensitive compartmented information,
critical assets, high cost or unique items, high availability items (fire
station, emergency operations center, etc.).
(2) Potential physical size and location of the project.
(3) Potential for hazardous materials.
(4) Potential impacts to protective force size and posture.
(5) Potential interfaces with emergency management/response and fire
department response assets due to nature of the facility.
(6) Impacts on existing security infrastructure/operations.
(7) Associated security risks.
c. Conduct reviews of overall project documentation for:
(1) General and specific security requirements inclusion in engineering and
design packages (e.g., physical security, barriers, explosives, security
communications, protective force support, entry/access controls, intrusion
detection/surveillance systems, materials control and accountability
DOE G 413.3-3A Attachment 1
08-15-2013 Page 7
systems, classified, sensitive compartmented information, controlled
unclassified information, Controlled Unclassified Nuclear Information
systems, cyber systems).
(2) Operational and infrastructure support needed for security features.
(3) Interfaces and impacts to and from other sections of the engineering and
design package (e.g. safety systems, general and specific layouts,
operational descriptions, etc.).
(4) Perform a Red/Black analysis of the minor security process equipment
(instruments, etc.) to assist design with cable tray and conduit space
requirements. Note: Projects historically have not factored additional
spacing needed when a project has Red and Black cable trays and conduit.
d. Provide tasking, as required, to security-related disciplines to consult on the
project (e.g., physical security, information security, materials control and
accountability, operations security, protective force, personnel security, etc.).
(1) Begin development of security-related training strategies.
(2) Begin development of security-related operational strategies.
(3) Interface with safety and operational training development.
e. Continue sharing information with other team members or disciplines involved
especially in regard to the overlap of design requirements that are known or
evolving.
(1) Operations.
(2) Safety (i.e. life safety; environment, safety and health; and nuclear safety).
(3) Engineering.
(4) Training.
(5) Information/cyber security technologies/technical security programs.
(6) Emergency Management.
(7) Budget [i.e. review (of) security costs].
f. Execute and review/complete major security-related milestones.
(1) Conduct of security vulnerability assessments/security assessments.
(2) Security system design, including key technologies.
Attachment 1 DOE G 413.3-3A
Page 8 08-15-2013
(3) Security documentation.
(4) Security performance/functional tests.
(5) Security operational readiness review.
g. Review/Finalize security-related costs and resources.
(1) Direct project related.
(2) Security operations and staffing.
(3) Project support related.
4. EXECUTION PHASE II (FINAL DESIGN PHASE AND CONSTRUCTION – POST
CD-2):
a. Monitor construction and change control.
(1) Document reviews.
Section 18
(2) Project meeting attendance.
(3) Construction site walkthroughs.
(4) Participation/observation in security related acceptance testing.
(5) Conduct impact on design changes. Analyses should include cost,
risk/protection effectiveness, and operability factors.
b. Continue security related assessments based on the GSP policy, other security
directives, and the confirmed security-related assets.
(1) Special nuclear materials, other nuclear material, radiological material,
biological assets (virus samples, etc.), classified and/or controlled
unclassified information or parts, sensitive compartmented information,
critical assets, high cost or unique items, high availability items (fire
station, emergency operations center, etc.).
(2) Potential physical size and location of the project.
(3) Potential for hazardous materials.
(4) Potential impacts to protective force size and posture.
(5) Potential interfaces with emergency management/response and fire
department response assets due to nature of the facility.
(6) Impacts on existing security infrastructure/operations.
DOE G 413.3-3A Attachment 1
08-15-2013 Page 9
(7) Associated security risks.
c. Continue reviews of overall project documentation and construction for:
(1) General and specific security requirements inclusion in engineering and
design packages (e.g. barriers, explosives, security communications,
protective force support, entry/access controls, and intrusion
detection/surveillance systems).
(2) Operational and infrastructure support needed for security features.
(3) Interfaces and impacts to and from other sections of the engineering and
design package (e.g., safety systems, general and specific layouts,
operational descriptions, etc.).
(4) Verify the Red/Black analysis of security process equipment as significant
design modifications are approved (check for additional space
requirements). Note: Projects historically have not factored the additional
spacing requirements needed when a project has Red and Black cable
trays and conduit.
d. Provide tasking, as required, to security-related disciplines to consult on the,
project (e.g., physical security, information security, material controls and
accountability, operations security, protective force, personnel security, etc.).
(1) Begin development of security-related training strategies.
(2) Begin development of security-related operational strategies.
(3) Interface with safety and operational training development.
(4) Develop a plan and conduct training to ensure efficient and complete
startup and turnover of the integrated safeguard and security (S&S)
systems. The plan should include interaction with the various DOE S&S
personnel since they will be involved with the acceptance/approval of the
S&S systems.
(5) Prior to the installation of classified equipment, train the appropriate
construction personnel on the classification sensitivities.
e. Continue sharing information with other team members or disciplines involved
especially in regard to the overlap of design requirements that are known or
evolving.
(1) Operations.
(2) Safety (i.e. life safety; environment, safety and health; and nuclear safety).
Attachment 1 DOE G 413.3-3A
Page 10 08-15-2013
(3) Engineering.
(4) Training.
(5) Information/cyber security technologies/technical security programs.
(6) Emergency Management.
(7) Budget (i.e. review of security costs).
f. Update and/or complete documentation and analysis necessary to support major
security-related milestones and associated As-built documentation.
Section 19
(1) Finalize security vulnerability assessment/security assessment report, if
required.
(2) Staffing plans.
(3) Security System installation, including security technology.
(4) Security documentation updated and completed.
(a) Security plans; including site security plan; performance
assurance program plan; materials control and accountability.
(b) Security procedures.
(c) Operations/maintenance plans.
(d) Proposed operation/maintenance budgets.
(5) Security function and performance tests (all safeguards and security
functions).
(6) Security operational readiness review.
(7) Documentation in support of the Safeguards and Security Information
Management System data registration.
g. Review/finalize security related costs and resources.
(1) Direct project related.
(2) Security operations.
(3) Project support related.
5. TRANSITION/CLOSEOUT PHASE/OPERATIONAL PHASE - PRE CD-4:
DOE G 413.3-3A Attachment 1
08-15-2013 Page 11
a. Monitor construction closeout and change control.
b. Transition security to an operational status.
c. Continue security-related assessments based on the GSP policy, other security
directives, and the confirmed security-related assets.
(1) Special nuclear materials, other nuclear material, radiological material,
biological assets (virus samples, etc.), classified and/or controlled
unclassified information or parts, sensitive compartmented information,
critical assets, high cost or unique items, high availability items (fire
station, emergency operations center, etc.).
(2) Physical size and location of the project.
(3) Hazardous materials.
(4) Impacts to protective force size and posture.
(5) Interfaces with emergency management/response and fire department
response assets due to nature of the facility.
(6) Impacts on existing security infrastructure/operations.
(7) Associated security risks.
d. Review final project documentation and construction (As-built) and assist in the
development of punch lists for:
(1) General and specific security requirements inclusion in engineering and
design packages (e.g., barriers, explosives, security communications,
protective force support, entry/access controls, intrusion
detection/surveillance systems).
(2) Operational and infrastructure support needed for security features.
(3) Interfaces and impacts to and from other sections of the engineering and
design package (e.g., safety systems, general and specific layouts,
operational descriptions, etc.).
e. Provide tasking, as required, to security related disciplines to consult on the
project (e.g., physical security, information security, materials control and
accountability, operations security, protective force, cyber security, etc.).
(1) Finalize/conduct security-related training.
(2) Finalize/conduct security-related operational procedures.
Attachment 1 DOE G 413.3-3A
Page 12 08-15-2013
(3) Interface with safety and operational training development.
(4) Interface with safety and operational procedures.
(5) Continue sharing information with other team members or disciplines
involved especially in regard to the overlap of design requirements that are
known or evolving.
(6) Operations.
(7) Safety (i.e. life safety; environment, safety and health; and nuclear safety).
(8) Engineering.
(9) Training.
(10) Information/cyber security technologies/technical surveillance
countermeasures.
(11) Emergency Management.
(12) Budget [i.e. review (of) security costs].
Section 20
f. Update documentation and analysis necessary to support major security-related
milestones.
(1) Updates to security vulnerability assessment/security assessment report.
(2) Staffing plans.
(3) Security system installation.
(4) Security documentation updated and completed.
(a) Security plans.
(b) Security procedures.
(c) Maintenance and test plans/procedures.
(d) Proposed operational budgets.
(5) Security functional, performance/acceptance tests.
(6) Security operational readiness review.
DOE G 413.3-3A Attachment 1
08-15-2013 Page 13 (and Page 14)
g. Conduct/oversee security-related operational acceptance tests and
performance-related tests.
h. Finalize security-related costs, resources and reports.
(1) Direct project related.
(2) Security operations.
(3) Project support related.
(4) Facility registration activities, e.g., Facility Data and Approval Record
changes.
DOE G 413.3-3A Attachment 2
08-15-2013 Page 1
REFERENCES
1. LEGISLATION
a. 42 U.S.C. § 2011, et seq., Atomic Energy Act of 1954, as amended.
b. 42 U.S.C. §§ 7101 to 7352, Department of Energy Organization Act, as amended.
c. 42 U.S.C. § 7144a, Establishment of Security, Counterintelligence, and
Intelligence Policies.
2. REGULATIONS.
a. 10 CFR Part 1045, Nuclear Classification and Declassification.
b. 10 CFR Part 1017, Identification and Protection of Unclassified Controlled
Nuclear Information.
c. 32 CFR Part 2001, Classified National Security Information.
d. 41 CFR 102-74, Facility Management.
e. 48 CFR 952.204-2, Security Requirements.
3. EXECUTIVE ORDERS.
a. Executive Order 13526, Classified National Security Information.
4. DEPARTMENT DIRECTIVES.
a. DOE P 205.1, Departmental Cyber Security Management Policy, dated
5-08-2001.
b. DOE P 470.1A, Safeguards and Security Program, dated 12-29-2010.
c. DOE O 150.1, Continuity Program, dated 5-08-2011.
d. DOE O 205.2B, Department of Energy Cyber Security Program,
dated 3-11-2013.
NOTE: Although separate from the safeguards and security information security
program, the Department’s cyber security program operates under the same basic
protection principles. The cyber security program (including both classified and
unclassified cyber security) is administered by the Department’s Chief
Information Officer.
e. DOE O 251.1C, Departmental Directives Program, 01-15-2009.
Attachment 2 DOE G 413.3-3A
Page 2 08-15-2013
f. DOE O 413.3B, Program and Project Management for the Acquisition of Capital
Assets, dated 11-29-2010.
g. DOE O 470.4B, Admin. Chg. 1, Safeguards and Security Program, dated
2-15-2013.
h. DOE O 470.3B, Graded Security Protection (GSP) Policy, dated 8-12-2008.
i. DOE O 471.1B, Identification and Protection of Unclassified Controlled Nuclear
Information, dated 3-01-2010.
j. DOE O 471.3, Admin. Chg. 1, Identifying and Protecting Official Use Only
Information, dated 1-13-2011.
k. DOE O 471.6, Chg.1, Information Security, dated 11-23-2012.
l. DOE O 472.2, Personnel Security, dated 6-27-2011.
m. DOE O 473.3, Protection Program Operations, dated 6-29-2011.
n. DOE O 474.2, Admin. Chg. 2, Nuclear Material Control and Accountability,
dated 11-19-2012.
o. DOE O 475.2A, Identifying Classified Information, dated 2-01-2011.
p. DOE STD 1192-2010, Vulnerability Assessment Standard, dated February 2010.
q. DOE M 205.1-3, Chg. 1, Telecommunications Security Manual, dated
12-20-2012.
r. DOE M 471.3, Admin. Chg. 1, Manual for Identifying and Protecting Official
Use Only Information, dated 1-13-2011.
Section 21
5. OTHER FEDERAL DIRECTIVES.
a. 4-010-01, Unified Facilities Criteria, Department of Defense Minimum
Antiterrorism Standards for Buildings.
b. U.S. Army Corps of Engineers, Technical Manual 5-853-4, Electronic Security
Systems.
c. U.S. Army Corps of Engineers, CEGS 13720, Electronic Security System, dated
11-01-1998.
d. General Services Administration Office of Government Policy, Federal Real
Property Council Security Resource Guide.
DOE G 413.3-3A Attachment 2
08-15-2013 Page 3
e. Director for Central Intelligence Directive 6/9, Physical Security Standards for
Sensitive Compartmented Information Facilities.
f. Department of Justice, Vulnerability Assessment of Federal Buildings.
DOE G 413.3-3A Attachment 2
08-15-2013 Page 5 (and Page 4)
g. Intelligence Community Standard (ICS) 705-1, Physical and Technical Security
Standards for Sensitive Compartmented Information Facilities, dated 9-17-2010.
h. Interagency Security Committee (ISC) Standard, Physical Security Criteria for
Federal Facilities.
i. ISC Standard, Facility Security Level Determinations for Federal Facilities.
j. ISC Report, The Design Basis Threat (DBT).