DOE G 413.3-23, Nuclear Facilities Commissioning
This guide addresses best practices for planning and executing the commissioning of equipment, components, structures, and systems comprising nuclear facilities. The best practices in this guide come from recent lessons learned from nuclear construction projects. The Department of Energy (DOE) has restarted or started up nearly 200 nuclear facilities since 1992. Projects that follow this non-mandatory guidance will have a thorough, carefully planned process for confirming that nuclear facilities conform to design requirements thus increasing the likelihood that they will perform as intended following the introduction of radioactive materials.
Version history and related documents
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
AVAILABLE ONLINE AT: INITIATED BY:
www.directives.doe.gov Office of Project Management
DOE G 413.3-23
8-30-2019
Nuclear Facilities Commissioning
[This Guide describes acceptable, but not mandatory means for complying with requirements.
Guides are not requirements documents and are not to be construed as requirements in any audit
or appraisal for compliance with associated rules or directives.]
U.S. Department of Energy
Washington, DC
NOT
MEASUREMENT
SENSITIVE
http://www.directives.doe.gov/
i (and ii) DOE G 413.3-23
8-30-2019
FOREWORD
This Department of Energy (DOE) Guide, for use by all DOE elements, assists with developing a
checkout, testing, and commissioning plan in preparation for acceptance and turnover of the
structures, systems, and components produced by the project in advance of startup.
This DOE Guide provides acceptable, but not mandatory, means for complying with
requirements included in DOE Order 413.3B, Program and Project Management for the
Acquisition of Capital Assets. This DOE Guide does not impose, but may cite, requirements.
Guides neither substitute for requirements nor replace technical standards that implement
requirements. Send citations of errors, omissions, ambiguities, and contradictions found in this
guide to PMpolicy@hq.doe.gov.
iii DOE G 413.3-23
8-30-2019
CONTENTS
FOREWORD .................................................................................................................................. 1
1. Purpose of the Guide ............................................................................................................... 1
2. Commissioning Related Requirements in DOE Order 413.3B .............................................. 1
3. Project Management Considerations for Commissioning and Startup ................................... 4
3.1. Pre-CD-0: Initiation Phase ............................................................................................... 4
3.2. Pre-CD-1: Definition Phase ............................................................................................. 4
3.2.1. Pre-CD-1 Commissioning Considerations ................................................................ 4
3.2.2. Pre-CD-1 Design Considerations .............................................................................. 5
3.2.3. Pre-CD-1 Construction Considerations .................................................................... 6
3.2.4. Pre-CD-1 Operations Considerations ....................................................................... 8
3.3. Pre-CD-2: Execution Phase .............................................................................................. 8
3.3.1. Pre-CD-2 Commissioning Considerations ................................................................ 9
3.3.2. Pre-CD-2 Design Considerations ............................................................................ 10
3.3.3. Pre-CD-2 Construction Considerations .................................................................. 10
3.3.4. Pre-CD-2 Operation Considerations ....................................................................... 12
3.4. Pre-CD-3: Execution Phase ............................................................................................ 12
3.4.1. Pre-CD-3 Commissioning Considerations .............................................................. 12
3.4.2. Pre-CD-3 Design Considerations ............................................................................ 13
Section 2
3.4.3. Pre CD-3 Construction Considerations ................................................................... 13
3.4.4. Pre-CD-3 Operation Considerations ....................................................................... 13
3.5. Pre-CD-4: Execution Phase ............................................................................................ 13
3.5.1. Pre-CD-4 Commissioning Considerations .............................................................. 15
3.5.2. Pre-CD-4 Design Considerations ............................................................................ 21
3.5.3. Pre-CD-4 Construction Considerations .................................................................. 21
3.5.4. Pre-CD-4 Operation Considerations ....................................................................... 22
3.6. Post CD-4: Closeout Phase ............................................................................................ 26
3.6.1. Post CD-4 Commissioning Considerations ............................................................ 26
3.6.2. Post CD-4 Construction Considerations ................................................................. 26
3.6.3. Post CD-4 Operations Considerations .................................................................... 26
Appendix A: Acronyms .............................................................................................................. A-1
Appendix B: Sources Consulted ................................................................................................. B-1
Appendix C: Definitions ............................................................................................................. C-1
Appendix D: Sample Commissioning Plan Outline ................................................................... D-1
iv DOE G 413.3-23
8-30-2019
TABLE OF FIGURES
Figure 1: Commissioning Activities Overview .............................................................................. 3
Figure 2: CD-0 to CD-2 Project Commissioning Activities by Organization ................................ 7
Figure 3: CD-2 to CD-3 Project Commissioning Activities by Organization ............................ 111
Figure 4: CD-3 to CD-4 Project Commissioning Activities by Organization ............................ 144
Figure 5: Post CD-4 Activities by Functional Area .................................................................... 255
TABLE OF TABLES
Table 1: DOE Order Requirements Related to Commissioning ..................................................... 1
Table 2: DOE Directive and Guidance Documents .................................................................... B-1
Table 3: Non-DOE Standards and Informative Documents ....................................................... B-1
DOE G 413.3-23 1
8-30-2019
1. PURPOSE OF THE GUIDE
This guide addresses best practices for planning and executing the commissioning of equipment,
components, structures, and systems comprising nuclear facilities. The best practices in this guide
come from recent lessons learned from nuclear construction projects. The Department of Energy
(DOE) has restarted or started up nearly 200 nuclear facilities since 1992. Projects that follow this
non-mandatory guidance will have a thorough, carefully planned process for confirming that
nuclear facilities conform to design requirements thus increasing the likelihood that they will
perform as intended following the introduction of radioactive materials.
Section 3
Commissioning occurs between construction and full operations although, preparations begin
during conceptual design. Commissioning and startup bring a facility from the construction phase
to stable operations in a manner that confirms attainment of functional requirements and design
objectives, demonstrates system operability and reliability, and establishes a base for long term
operation in accordance with contract requirements. This process ensures all facility equipment,
structures, components, and systems perform interactively in accordance with the design
documentation and intent, and in accordance with operational needs including training and
preparation of operations personnel.
This guide primarily applies to new construction of Hazard Category 1, 2, and 3 nuclear facilities
and below Hazard Category 3 nuclear facilities regardless of the source of the radioactivity.
For nuclear facilities, a readiness review (RR), either an operational readiness review (ORR) or a
readiness assessment (RA), precedes authorization to operate and occurs concurrently with Critical
Decision (CD)-4, Approve Start of Operations or Project Completion. Current project experience
suggests that commissioning and startup planning should begin early in the design, continue
through project completion, and involve research and development and operations personnel.
Interfacing with these organizations early in the design will reduce startup and testing schedules
because these organizations will have a better understanding of the facility, reducing rework, and
improving process knowledge.
2. COMMISSIONING RELATED REQUIREMENTS IN DOE ORDER 413.3B
DOE Order 413.3B, Program and Project Management for the Acquisition of Capital Assets,
includes requirements related to commissioning, not all of which this guide addresses.
Table 1: DOE Order 413.3B Requirements Related to Commissioning
Item
Number Requirement Source Deadline
Location in this
Guide
1 “For nuclear facilities, develop a
Checkout, Testing and
Commissioning Plan in preparation
for acceptance and turnover of the
structures, systems and components
at CD-4. (Refer to DOE-STD-1189-
2016.)”
Appendix A,
Table 2.1
Post-CD-
1
Appendix D
2 DOE G 413.3-23
8-30-2019
Item
Number Requirement Source Deadline
Location in this
Guide
2 “The Program Office must determine
if hot commissioning (i.e.,
introduction of radioactive material)
is a condition of CD-4. Ultimately,
the capital asset must have the
capability to meet the end-state
capacity requirements approved in the
CD-2 decision by the respective
[Project Management Executive], but
not as a condition of CD-4.”
Appendix A,
Section 5(d)
Pre-CD-2 The guide does
not address hot
commissioning
3 “The Guiding Principles for Federal
Leadership in High Performance and
Sustainable Buildings . . . must be
applied to the . . . commissioning of
new facilities and major renovations
of existing facilities.”
Attachment 1,
Section 15
Pre-CD-4 The guide does
not address
commissioning of
conventional
equipment and
systems.
4 “[Other project costs] will include . .
. commissioning costs.”
Attachment 2,
Definition 77
N/A The guide does
not address costs.
The Office of the Chief of Nuclear Safety, Office of Environmental Management (EM), published
Design and Commissioning Report, Revision 1, in July 2017 to further identify commissioning
plan needs. This report resolved an Office of the Inspector General finding related to EM projects
and issues pertaining to commissioning and startup. The report, although written for the
consideration of EM projects, may apply to other programs’ capital acquisition projects. Using
this report and the documents listed in Appendix B, a working group of the Energy Facilities
Contractors Group prepared the first draft of this guide.
Section 4
DOE G 413.3-23 3
8-30-2019
Figure 1: Commissioning Activities Overview
4 DOE G 413.3-23
8-30-2019
3. PROJECT MANAGEMENT CONSIDERATIONS FOR COMMISSIONING AND
STARTUP
This section focuses on the activities in each project phase necessary to prepare a nuclear project
for commissioning prior to the RR. Figure 1 depicts commissioning-related activities within the
framework of critical decisions. Critical decisions structure this section.
3.1. Pre-CD-0: Initiation Phase
No commissioning-related activities occur prior to establishing a mission need.
3.2. Pre-CD-1: Definition Phase
While updates to the commissioning plan continue until prior to CD-4, the commissioning process
begins early in the project in order for the transition to operations to occur efficiently. Prepare an
initial commissioning plan in advance of the requirement to complete a commissioning plan
following CD-1. Engage early with commissioning authorities to coordinate schedules and
resource needs in advance of setting a performance baseline.
Following CD-0 during conceptual design, commissioning planning includes identifying federal
personnel who will provide, track, and ensure fulfillment of commissioning related requirements
along with developing an initial testing approach and set of testability requirements to inform the
design process. This informs the approach to achieving the key performance parameters.
Best Practice: Early in the definition phase, development of the checkout, testing,
and commissioning plan begins with the initial evaluation of systems and
identification of preliminary testing requirements.
Identify early in the project initial considerations for developing an organizational structure that
includes adequate design interfaces, testing, and operations. The testing program engages in the
procurement process to ensure testability, maintainability, and operability of acquired components
and general plant layout. The program can also engage in setting factory acceptance testing
requirements to ensure a smooth transition to plant testing following equipment installation in the
plant. Engineering defines the functional acceptance criteria for testing.
Best Practice: Include in the project scope a simulator or pilot plant if the process
or operating system has a low technical readiness level, has a high complexity, or
large size. The simulator or pilot plant offers an opportunity to hone
commissioning techniques planned.
3.2.1. PH
Best Practice: Use DOE’s “Readiness Certification Assurance Process Tracking System
(RCAPTS)” to retain documents and records in an easily retrievable way through hypertext
links that establish a relationship between related test, performance, acceptance, procedural,
and lessons learned information. Obtain from https://go.usa.gov/xyQj2.
DOE G 413.3-23 5
8-30-2019
3.2.2. Pre-CD-1 Design Considerations
Perform an alternatives analysis for permanent plant design features or temporary modifications
supportive of testing. Address the following factors that influence commissioning and startup
processes in the alternatives analysis:
1. Technology Readiness Level for Systems – The level of experience with the specific processes,
the degree of complexity, and the design maturity level of the components provide information
relating to the need to incorporate a pilot facility in the project’s scope.
2. Processing fluids – As the concentration of suspended and dissolved solids anticipated in the
process lines increase, the complexity of commissioning and operations will likely increase.
Section 5
3. Radiological conditions - Source term, radiation levels, material radiation tolerance and other
special considerations addressed in the nuclear safety design strategy may require
commissioning approaches which differ from consensus standards and industrial norms.
4. Obsolescence – Due to the length of nuclear facility projects, materials and equipment available
during design may become obsolete prior to testing. Select easily replaced or upgraded
instruments and control systems preferably situated outside of radiological zones.
5. Interface with existing facilities and systems – Hazards and regulatory requirements stemming
from nearby existing facilities may impact new projects and their systems. Interfaces include:
a. Systems such as waste transfer pipes to isolate the new facility from the existing facilities;
b. Capacities of, and interface with, fire protection systems; and,
c. Pressures in new systems connected to existing systems.
6. Configuration management – Maintaining configuration management will facilitate efficient
commissioning. Have the cognizant system engineer define boundaries, operations system, and
how they relate to functional areas and construction zones early. Establish a configuration
control process to support tracking of design inputs, outputs, and validation via testing,
inspection, calculation, or other means. Delineate a design change notification process. Retain
assumptions used to develop the design or proof of process in a configuration management
system that provides traceability later for system design description development and provides a
basis for operation. DOE Guide 413.3-1, Managing Design and Construction Using Systems
Engineering, addresses configuration management.
7. Test requirements – Test requirements for commissioning, regardless of their origin, need
documentation in the configuration management system, controls, and need to trace back to the
design. Testing validates components against commercial grade dedication criteria. Having the
Best Practice: Establish the code of record prior to CD-1 but consider proposals to update it
if a project assumption does not bear out.
6 DOE G 413.3-23
8-30-2019
ability to isolate systems through valves or other testable boundary allows testing and turnover
to occur at logical points and often allows for less complex individual testing prior to integrated
tests.
Best Practice: Have the design agency track design authority requirements on a system basis
along with component and system test criteria during design. A joint board including
engineering, configuration management, and startup or commissioning personnel ensures the
efficacy of the test requirements prior to approving the criteria.
3.2.3. Pre-CD-1 Construction Considerations
1. Acquisition and Tailoring Strategy – Projects planning to acquire multiple facilities, whether
nuclear or non-nuclear, but do not anticipate placing all facilities into service
contemporaneously, may benefit from phasing CD-4. This will simplify scheduling the startup
authorization authority (SAA) approvals to start hot operations so that they occur shortly
before CD-4 approval.
2. Accessibility – Accommodate testing and commissioning activities when considering plant and
equipment layouts. Avoid minimizing the physical size of the facility at the expense of the
ability of construction or testing staff to perform work. Verify related requirements with
operations personnel. Select places for valves needed to isolate areas for testing.
Section 6
DOE G 413.3-23 7
8-30-2019
Figure 2: CD-0 to CD-2 Project Commissioning Activities by Organization
8 DOE G 413.3-23
8-30-2019
3. Constructability – Find opportunities to stagger system turnover to reduce peak labor burdens
on the testing crews.
4. Construction testing scope and needs – At this stage, the development of the construction
approach with consideration for testing begins. Identify in conjunction with commissioning
personnel the tests and inspection points. Include equipment to support testing various aspects
of the structure. Include inspections and materials tests in the project schedule.
3.2.4. Pre-CD-1 Operations Considerations
Having experienced operations personnel involved early in the conceptual design phase will lead
to a smoother transition to operations.
3.3. Pre-CD-2: Execution Phase
Consider the resources required to complete commissioning prior to setting the performance
baseline at CD-2. In this phase, start considering system boundaries or at least define the systems
and key components. This section elaborates on the commissioning best practices between CD-1
and CD-2 depicted in Figure 2.
Complete an initial commissioning plan to document the commissioning and testing strategies
under development following the structure and guidance found in Appendix D. Trace test
requirements back to the engineering design. Control the test requirements flow down, whether
from the design authority or another source. In addition, where engineering assumptions need
validation or component commercial grade dedication needs system testing to validate criteria, the
configuration management program records these validation needs and manages them
appropriately.
Consider the following while planning commissioning pre-CD-2:
1. Division of required testing between pre-construction (vendor, factory, or other testing not
performed in the permanent plant) and in-plant commissioning testing. This division may
drive procurement specification requirements for vendor design/build systems, establishment
of additional test platforms, or design features to support in-plant testing. Typically, in-plant
testing most effectively demonstrates functional performance but costs the most by far and
carries the highest risk. The testing approach balances these considerations based on mission
value.
2. Provisions for testing and management. Designs may require special design provisions for
testing of utility and process feeds or effluent disposal paths. Address in design provisions
commissioning sequence, radiological conditions of interfacing processes, and required hazard
controls. Provisions may impact physical layout of facilities and systems, piping system
designs, commissioning sequence planning, and other design phase considerations. For
example, valve placement to facilitate testing can make significant improvements in testing by
zone versus system and increase overall schedule and manpower efficiency. Select interfaces
that isolate adjacent systems to facilitate commissioning of completed systems when adjacent
systems remain under construction.
DOE G 413.3-23 9
8-30-2019
3. Environmental permits. Plan to commission equipment and systems required by permits.
Permits may require sampling and testing from emissions, effluents, and waste streams, stack
certification, and destruction removal efficiency demonstrations. Since permits may not allow
waste streams classified as radioactive and hazardous waste (mixed waste) to include non-
hazardous or non-radioactive substances, ensure that all waste streams have disposal paths.
Section 7
Best Practice: Defining system boundaries on the piping and instrument diagrams prior to
CD-2 enables a more efficient turnover from construction to operations/testing.
3.3.1. Pre-CD-2 Commissioning Considerations
Identify the commissioning authority and its responsibilities. Develop the readiness review
strategy. Devise a schedule for commissioning and estimate its budget. Define testable system
boundaries so that relationships between the different boundaries become clear. Establish a
process to ensure testing of each turned over system occurs.
1. Component and System Testing – Plan system tests that adhere to the assumptions in the
conduct of operations section of the safety management plan (SMP).
2. Quality Assurance (QA) – Activities during testing and commissioning support QA. Identify
commissioning elements in the QA requirements. Develop QA processes for testing and
acceptance to ensure the final product meets the design and safety basis criteria regardless of
who completed the work.
3. Procedure Development and Verification – Commissioning will need procedures for testing,
operations, and maintenance during normal, off-normal and emergency operations. Start
procedure development early, beginning with operational task analysis and establishment of
operational jurisdictions as a basis for determining operational staffing levels.
4. Training and Qualification – Commissioning personnel need training on systems and
operations of the plant. Leverage training intended for later delivery in support of transition to
and initial operations.
5. Commissioning Phase Hazard Controls – Plan for the management of hazards as the facility
incrementally introduces them during commissioning. DOE STD 3009 describes preparing a
documented safety analysis useful for analyzing and controlling chemical as well as
radiological hazards. Commissioning frequently introduces electrical, hydronic, pneumatic,
and chemical hazards prior to introducing radiological hazards.
6. Simulants – Simulants represent radioactive materials for testing and demonstration purposes.
Consider manufacturability, stability, hazardous characteristics, and impact to installed systems
when selecting simulants. Obtain simulant approvals from DOE and regulatory entities as
early as possible. Plan for the disposition of wastes generated through the use of simulants.
7. Simulators – Plan and budget for one or more process simulators to validate design
assumptions, testing and process procedures, and support training development and execution
including off-normal operator response in a safe environment.
10 DOE G 413.3-23
8-30-2019
3.3.2. Pre-CD-2 Design Considerations
Include in a requirements traceability matrix the methodology planned to demonstrate compliance.
In some instances, the design validation cannot occur until after admitting radioactive material to
the facility. Ensure designs include features supporting test requirements. Typical features include
flushing spools, instrument test ports or taps, sample ports, tees and spools for chemical simulant
introduction or secondary waste collection, and isolations for sub-system level testing. Layout the
plant and space equipment to support testing needs. Inaccessible areas of the facility will need
special testing planning to meet commissioning requirements.
Section 8
Best Practice: The use of a requirements traceability matrix as a means of linking design
requirements through the review and validation process enables a successful commissioning
program. The requirements traceability matrix also helps in the development of system design
documents and validation files to support the RR process.
Where radiation levels, chemical exposure, or other factors prevent safe direct access, the design
may include a means to either remove the hazard prior to entry or maintain or repair systems using
remotely controlled equipment (i.e., remotability). The effectiveness of the latter depends on the
skill and proficiency of the operator. Address system controls in design documents. Include
diagnostics where feasible.
Best Practice: Follow the change control process when changing the code of record prior to
CD-2.
3.3.3. Pre-CD-2 Construction Considerations
Have an independent entity conduct constructability reviews at meaningful design milestones with
the final constructability review occurring following completion of 90 percent design. Plan for the
time and costs to complete commercial grade dedication.
The construction function at this stage will work with the commissioning function to determine
test sequences, installations to support testing and other test requirements. Assign all equipment
and systems an identifier recorded in a database. Complete the delineation of system boundaries
and testable systems. Sequence system turnover in the commissioning plan.
Address commissioning and startup in contract documents. Have the contract specify delivery of
operation and maintenance manuals within 30 to 60 calendar days of submittal approvals. This
would give the commissioning manager early access to needed documentation to complete pre-
functional and functional tests in a timely fashion.
DOE G 413.3-23 11
8-30-2019
Figure 3: CD-2 to CD-3 Project Commissioning Activities by Organization
12 DOE G 413.3-23
8-30-2019
3.3.4. Pre-CD-2 Operation Considerations
Identify the SAA. For further details see DOE Order 425.1D, Verification of Readiness to Start up
or Restart Nuclear Facilities, Section 4(b).
3.4. Pre-CD-3: Execution Phase
This section elaborates on the commissioning best practices between CD-2 and CD-3 depicted in
Figure 3.
3.4.1. Pre-CD-3 Commissioning Considerations
1. Establish a Commissioning and Readiness Team - Staff the commissioning and readiness team
with qualified personnel to manage all activities described in the commissioning plan.
2. Establish a Joint Test Group – Ensure through oversight of the commissioning test program
receipt of valid results and prompt and effective resolution of related issues. A joint test group
(JTG) comprised of key stakeholder organizations including operations, engineering, the
design authority, and DOE validates procedures and provides oversight. Involve nuclear
safety, environmental, or QA organizations when agenda items affect those functional areas.
The JTG may draw conclusions about the whole from samples. Including DOE in the JTG
exposes DOE to test results as the commissioning agent returns them and may result in less
rework. The JTG makes decisions with a quorum present.
3. Site Integration – Identify in the commissioning plan the project’s site interfaces and the
testing required to confirm effective connections.
4. Update Commissioning Plan – Update the commissioning plan to reflect the project’s final
design and commissioning commitments.
Section 9
5. Establish Commissioning Sequence and Schedule – Sequence the various commissioning
phases in the plan to include simulant usage, facility configurations, and ramping system
modes up to full capacity.
6. Temporary Modifications - Identify early temporary modifications and equipment specifically
needed for testing for inclusion in procurement and installation schedules. Approval of
modifications and system overrides occur prior to installation.
7. Review Design for Testability – Address in the commissioning plan how the commissioning
team will test the systems. Include areas outside the main process area even if early design
documents omitted their functions or when they may contain no safety class or safety
significant components.
8. Finalize Test Requirements – Finalize test requirements that acknowledge access limitations in
the design and limit conflicts with operations. Ensure testing demonstrates that the plant can
operate within its design parameters pertinent to not just routine operations but also to
transients and upsets.
DOE G 413.3-23 13
8-30-2019
3.4.2. Pre-CD-3 Design Considerations
Develop a field change notice process integrated with configuration management, documenting
changes during construction ultimately recorded in as-built drawings and asset inventories.
3.4.3. Pre CD-3 Construction Considerations
Constructability - Have an independent entity supplemented with commissioning representatives
conduct a constructability review. Include in the review the planned sequence of activities and
construction methods.
Procurement - The nuclear supply chain has atrophied. Delayed delivery of materials and
equipment require rescheduling work, changing craft assignments, and expediting new or revised
work and instructions. Apply the best practices associated with CD-2 and CD-3 to any long lead
procurement acquiring equipment even if the project has not received CD-2 or CD-3.
Best Practice: Establish a process that enables acquisitions utilizing best value for vendor
selection. This mitigates risk to the project associated with the limited number nuclear-related
component suppliers.
Best Practice: Apply best practices and procedures outlined in this guide for CD-2 and CD-3
to any long lead equipment procurement.
3.4.4. Pre-CD-3 Operation Considerations
Engage operations personnel in design reviews to ensure that the design adequately addresses
operations requirements including those related to equipment access, adequacy of travel paths,
maintainability of systems, redundancies allowing for downtime, and radiological controls.
Provide training recommendations discerned during this engagement to operations management.
Ensure compatibility between the records management system(s) relied on by operations personnel
and the records the project intends to turn over to operations. Take corrective actions where the
review identifies incompatibilities.
3.5. Pre-CD-4: Execution Phase
Commissioning, testing, and verification activities typically proceed from lower to higher levels in
terms of both systems and complexity. Construction and commissioning activities may overlap.
Describe the interface points in the commissioning plan. The common order of testing follows:
1. Installation tests
2. Component tests (e.g., motors, actuators, sensors)
14 DOE G 413.3-23
8-30-2019
Figure 4: CD-3 to CD-4 Project Commissioning Activities by Organization
DOE G 413.3-23 15
8-30-2019
3. Calibration and alignment
4. Grooming and balancing
Section 10
5. System functional performance tests
6. Cold commissioning tests
7. Simulant test
8. Testing with radioactive materials post CD-4 (outside the scope of this manual)
Figure 4 shows project commissioning activities between CD-3 and CD-4. The readiness process
follows cold commissioning.
3.5.1. Pre-CD-4 Commissioning Considerations
1. Issue Final Commissioning Plan – Issue the final commissioning plan in a timely manner so
that commissioning can proceed smoothly.
2. Turnover from Construction to Operations for Testing – Establish consistent standards
regarding the completeness and quality of the systems deemed ready for turnover. Optimally,
turnover occurs after construction completion. Include in the turnover:
a. A report detailing which organizations visually inspected completed systems and when
they completed their walk-down;
b. Clear boundaries for each completed system deemed ready for turnover through
verification and testing;
c. Documentation suitable for inventorying, managing, and operating the completed systems;
d. Documentation of incomplete1 installations tracked through punchlists divided into:
i. “A items” resolution of which must occur prior to turnover and
ii. “B items” resolution of which may occur after turnover.2
e. A budget estimate for resolving punchlist items;
1 Incomplete encompasses work that fails to meet specifications including quality standards.
2 The number of punchlist items at the time of turnover indicates progress towards construction completion. A lengthy
punchlist log may indicate an unpreparedness for turning over scope.
16 DOE G 413.3-23
8-30-2019
f. A division of responsibilities made within the context of configuration management and
documented in accordance with DOE Order 420.1C; and,
g. A statement estimating the readiness of the receiving organization for the management and
maintenance of systems after turnover.
3. Lessons learned related to system turnover include:
a. Complete and have approved documentation associated with the applicable system before
stakeholder and oversight inspections. When not practicable, identify paperwork that may
remain incomplete while the inspections occur.
b. Engage the owner, stakeholders, and oversight personnel in developing the turnover
process. Familiarize them with the systems and processes.
c. Include oversight team members in the decision to close punchlist “A” items.
d. Trace punchlist “B” items back to the original turnover scope. Once resolved, annotate
installation records with pertinent information.
e. Manage all project documents electronically.
f. Practice system turnover procedures with interested personnel to ensure actual turnovers
proceed as efficiently as possible.
g. Turnover each system to the entity identified in planning documents with the responsibility
for testing that system. If the designated receiving entity cannot fulfill its assigned
responsibility, either follow project change control procedures to reassign the responsibility
or wait until it can.
Best Practice: Use a configuration-controlled database to permit electronic review of
turnover packages to make the receiving organization most efficient.
4. Substantial Completion
a. Consider “construction complete” as a synonym for “substantial completion.”
Section 11
b. Define substantial completion in the contract as the point in time when the owner accepts
the contractor’s claim that a specific list of systems have attained a particular status
indicated by evidence that specific inspection, testing, calibration, alignment, and grooming
procedures have occurred and that the contractor has resolved any punchlist “A” items.
See the American Institute of Architects (AIA) Document A201-2017, General Conditions
of the Contract for Construction, §9.8, Substantial Completion, for adaptable language.
c. Include in the list of systems conventional structural, interior, mechanical, and electrical
systems such as building shell, partition, heating, ventilation, and air conditioning,
DOE G 413.3-23 17
8-30-2019
plumbing, fire protection, electrical, lighting, communications, controls, and vertical
transportation systems. The contracting officer in conjunction with the FPD may expand
the list.
d. Direct the contractor to submit in writing its declaration of substantial completion. Base
this declaration on AIA Document G704-2017, Certificate of Substantial Completion.
Include in the declaration turnover acceptance forms, manuals, evidence of inspections,
testing, calibration, grooming, and alignment, open punchlist items, schedule for resolving
punchlist items, procedures for commissioning, schedule and cost information, and other
documents specified in the contract as comprising the turnover package. Abide by time
limits set in the contract for accepting or challenging the declaration. The federal project
director and contracting officer issue the response to the contractor’s declaration.
e. Provide additional guidance for rework through construction if testing reveals defects.
Address different courses of action dependent on causes stemming from the design,
component manufacturer, or the installation. Use a nonconformance process deemed
acceptable under the project quality assurance program.
Best Practice: Contractors should correct errors and omissions in work packages as soon as
possible. Some projects hire clerical staff to review packages each night to catch and correct
obvious problems.
5. Commissioning Phase Modifications
a. Confirm procurement and installation schedules address all needed temporary
modifications and equipment specifically needed for testing.
b. Approve modifications and system overrides prior to installation. Reloading baseline
control software regularly ensures no software overrides or erroneous modifications remain
in the system for prolonged periods during the testing phase.
c. Install and remove modifications to the physical plant as directed in a conduct of operations
SMP. The conduct of operations SMP and the hazardous material protection SMP protects
against spills, mis-transfers, and unplanned worker exposure to chemicals or industrial
hazards during the commissioning phase.
6. Test Requirements Management – Ensure tests and results trace to testing requirements. NRC
RG-1.68 Initial Test Programs for Water-Cooled Nuclear Power Plants provides examples of
acceptable test requirements for possible benchmarking. Document the design authority’s
acceptance of test results as evidence of the project meeting its scope baseline requirements.
The JTG actively contributes to the management of test requirements.
Section 12
7. Commissioning Testing – Commissioning phase activities include integrated testing and
demonstrating that systems, structures, and components meet functional requirements and
performance criteria. Test in increments starting with installation testing, progressing through
component testing, system testing, and then integrated facility testing. This approach reduces
18 DOE G 413.3-23
8-30-2019
risks by verifying the function of components and subcomponents before verifying the function
of systems or facilities. Component testing may occur on multiple components in parallel
leading to less work impacted by delays to address test failures or other issues. Projects need
to balance using simulation, overlap tests, and similar methods to demonstrate function with
less than fully integrated conditions with the need to provide adequate demonstration.
Appropriate test conditions established during the design phase and traceable to test
requirements, support finding this balance. Commission only following implementation of all
system control software. The following sections discuss typical phases of, and considerations
during, testing.
a. Installation Testing – Confirm proper construction and installation through appropriate
tests such as hydrostatic testing, welding radiography, or cable continuity tests. Include in
turnover packages records of these test results. Verify acceptable results prior to accepting
a construction completion declaration.
b. Component Testing, Calibration, Alignment, and Grooming – Component testing confirms
fitness for use, proper installation, and preparation for subsequent integrated testing
through configuration and calibration. Component tests typically include electrical circuit
scheme checks, insulation resistance testing, and mechanical run-in tests. Test components
as early as practical, even during construction, to maximize the time available for resolving
issues. Select initial calibrations that align with the operating phase calibration program.
Grooming includes adjusting or aligning components to optimize their performance.
Grooming includes setting limit switches, stroke and cycle timers, and dead-bands and also
tuning component response parameters. In some cases, grooming may occur only after
systems or sub-systems can provide complete control loops. Complete grooming as early
as practical in the sequence to maximize the time available for resolving issues. Involve
operations staff in grooming activities to improve its proficiency and the continuity of
records.
c. System Testing – System testing follows component testing to demonstrate that systems
meet system level and integrated system requirements. Like with component testing, test
systems as early as practical to maximize the time available for resolving issues before
integrated facility testing. System testing confirms achievement of design and operations
requirements. Tune control loops to stabilize process controls through dynamic response to
transients and upsets. Test mechanical handling systems to confirm remote operation,
maintenance, and recovery features meet design requirements.
d. Technical Safety Requirement Surveillances – Verify under the test program that safety
system maintenance and surveillance requirements, such as technical safety requirements
(TSRs), demonstrate compliance and effectiveness.
Section 13
Best Practice: Perform TSR surveillances before documented safety analysis (DSA)
implementation to reveal problems such as uninstalled or inaccessible test points or other
interfering interlocks or functions. Ensure the surveillance tests the function or protective
action on which the safety basis depends. Omit from surveillances invalid acceptance criteria
that do not demonstrate the required functions.
DOE G 413.3-23 19
8-30-2019
e. Hazardous Materials - Test systems with non-hazardous materials where practical. Where
testing of control loops or functions must occur with hazardous materials, hazard controls
protecting workers along with additional readiness verification and oversight will minimize
the consequences of a test failure.
f. Hazard Review - A hazard review evaluates any hazards associated with pressurizing or
energizing the equipment for testing. The review includes:
i. Determining the readiness of interfacing systems for testing;
ii. Confirming placement of area controls to exclude personnel not involved with the
testing from the area;
iii. Approving testing procedures and test acceptance criteria;
iv. Confirming personnel responsible for executing the tests have received sufficient
training; and,
v. Confirming the identification of post-testing actions needed to configure the facility
and systems has occurred.
g. Equipment readiness evaluations (EREs) ensure that the safety structures, systems,
and components (SSC) will operate in accordance with design and functional
requirements and performance criteria. Turning over of equipment for testing
follows completion and approval of the results of EREs.
i. EREs begin with identifying and validating the design and equipment performance
requirements in need of verification.
ii. Approval for including the equipment in the cold commissioning process, including
integrated system testing, follows successful equipment testing.
h. Ventilation System Testing – Incorporate in the integrated commissioning schedule
ventilation testing such as volumetric flow adjustments and coarse and fine balancing since
it will limit access to the facility. Ventilation testing may follow completion of the
building shell including doors and access ports. Address confinement for normal and
anticipated upset conditions in the testing. This may require final system balance
verification during integrated facility demonstrations in cold commissioning.
i. Vendor Support for Testing – Plan and schedule vendor support for testing as early as
practical. Vendors may provide technical support for specialized equipment, staff holding
required certifications, or direct testing of installed systems and components.
Best Practices:
• Obtain from vendors and their subcontracted suppliers early utility startup support.
• Understand the scope of vendor support for equipment startup to avoid delays.
20 DOE G 413.3-23
8-30-2019
• Confirm vendors complete updates to equipment they supply prior to transition.
• Include engineers in vendor training on procedures and process changes from
construction to testing.
• Define testing and troubleshooting boundaries to avoid conflicts with interfacing or
collocated systems not within the vendor’s scope.
j. Operations Personnel – To the extent practical, involve operations personnel in the testing
program to teach them about the as-built configuration of the plant, system response, and
component locations. However, operations personnel need to know how testing procedures
differ from the conduct of operations SMP.
Section 14
8. Cold Commissioning Testing
a. Background – Cold commissioning verifies achievability of the design capacity, process
objectives, and environmental performance. Test procedures govern the test activities and
ensure collection of all required data. Follow approved plant operating procedures during
these tests. This testing may entail use of measuring and test equipment and temporary
modifications or use of temporary test systems, structures, or analytical facilities. List in
procurement documents commissioning testing requirements. Ensure the approved DSA or
commissioning plan evaluates all SSCs. Address in the DSA any permanent operational
changes resulting from the commissioning activities.
b. Timing and Schedule – Cold commissioning under the purview of the commissioning and
operations groups begins after successful completion of individual component testing.
Cold commissioning may occur in phases.
c. Overview – Cold commissioning entails integrated facility testing demonstrating integrated
facility function and performance completed prior to introducing radioactive materials.
These tests employ air, water, and simulants to confirm attainment of regulatory,
maintainability, capacity, and key performance parameter (KPP) requirements.
d. Main objectives of cold commissioning –
i. Operate plant systems at design operating conditions (e.g., design flow rates,
temperatures, and pressures) with the chosen simulant and non-nuclear process
chemicals in accordance with approved procedures to verify that the process meets
specifications;
ii. Identify deficiencies in the equipment, processes, or procedures and make
corrective modifications before the facility goes hot (radioactive); and,
iii. Provide on the job training and assessments for operation, maintenance,
administrative support, and training staff.
e. Simulants – Cold commissioning typically involves introducing hazardous simulants or
process reagents or both. This may involve the introduction of greater than standard
DOE G 413.3-23 21
8-30-2019
industrial hazards and implementation of the authorization basis for environmental
considerations and chemical hazard controls.
f. Documented Safety Analysis – Validation of many of the SMPs required for nuclear
operations occurs in conjunction with cold commissioning. Practice implementing the
DSA for cold commissioning hazard controls before actually implementing the DSA from
a regulatory and reporting standpoint. Since the DSA governs industrial hazard control
analysis and control requirements, leverage the DSA controls to control hazards, develop
proficiency, and validate the procedures without requiring reporting issues under 10 CFR
830. While implementing cold commissioning hazard controls, maintain the scope baseline
in alignment with the DSA.
g. Remotability – Demonstrate during cold commissioning not only that installed equipment
functions as required, but that features supporting remotability, like cameras, operator aids,
and human machine interfaces, adequately allow a trained operator to perform required
tasks. Complete remotability tests early to take advantage of testable features evident
during construction.
Section 15
h. Resources - Plan for sufficient resources including time, personnel, and funds for cold
commissioning to allow the project to fully demonstrate system capabilities, develop
operator proficiency, and resolve emergent technical issues. Involve operations and
maintenance staff and program personnel to the maximum practical extent in cold
commissioning to develop their competencies and proficiencies in preparation for the RR.
Initiate scheduled inspection and maintenance activities during lengthy cold commissioning
of the systems and equipment in the facility. Ensure that equipment remains ready for
startup following commissioning. Dispose of wastes generated through the use of
simulants.
3.5.2. Pre-CD-4 Design Considerations
Confirm by examination of objective evidence that the project has fulfilled specified requirements.
Add to the requirements traceability matrix verification and validation process results documenting
satisfaction of the requirements. Testing and acceptance for requirements that will remain
unverified until after the admission of radioactive material to the facility would occur post CD-4.
Address these activities in the startup plan.
3.5.3. Pre-CD-4 Construction Considerations
1. Factory Acceptance Testing (FAT) - Ensure that FAT demonstrates attainment of quality
requirements. Project, commissioning, operations, and maintenance staff may wish to observe
this testing. FAT, conducted through approved final software, entails extended performance
tests to demonstrate robustness, maintainability, acceptable system availability, and attainment
of system performance parameters. Exercising equipment during FAT to the maximum extent
possible can significantly reduce testing problems and rework during the commissioning phase.
Resolving issues at the vendor’s facility rather than during the commissioning phase
compresses the project schedule and minimizes costs.
22 DOE G 413.3-23
8-30-2019
2. Construction Testing – Structural testing may examine compaction, concrete density and
moisture, concrete, rebar inspections and locations, slab smoothness and flatness, masonry,
asphalt, anchors, fire retardants and other. Schedule the tests to avoid rework and minimize
schedule impacts. Hydrostatic testing of plumbing systems and electrical testing through wire
conductivity and continuity also occurs at this point.
3. Documentation – Collect and manage construction acceptance testing documentation to
associate records with specific components, systems, and facilities. Verify through non-
destructive examinations (NDE) that the quality of installed commodities meet quality
requirements. Pre-qualify suppliers against program requirements.
3.5.4. Pre-CD-4 Operation Considerations
As construction progresses, operations personnel added to the project will begin developing
operating procedures and training while supporting commissioning. Hire sufficient operations
personnel, as described in the commissioning plan, to develop a timely familiarity with the plan,
operations training, and commissioning.
1. Verify Operability and Maintainability – During construction, operations personnel verify
unfettered access to equipment, valves, gauges, sumps, valve pits, and other isolated locations.
Design the plant to allow for the relocation of equipment where required for operations or
maintenance.
Section 16
2. Startup Plan – Develop a startup plan for review prior to the RR. The startup plan describes
how the facility will introduce radioactive material, and the additional surveillance, oversight,
hold points, and other key controls necessary to ensure safe performance of this major
transition. The startup plan then guides subsequent activities conducted in preparation for
demonstrating a readiness for routine operations with radioactive materials. Include in the
startup plan criteria for release to normal operations within the constraints of the DSA. Include
a procedure for confirming operator proficiency and the shift staff’s capacity to accommodate
the pace of the desired production rate.
3. Operations Preparations – To the extent practical, involve operations personnel in the testing
program to teach them about the as-built configuration of the plant, system response, and
component locations. However, operations personnel need to know how testing procedures
differ from the conduct of operations SMP. As systems achieve readiness for operations, the
facility will implement the SMPs as a part of plant operations. The facility will also need to
determine whether it creates its own stand-alone safety management programs or incorporates
any of the site’s programs. Consider tasking maintenance personnel with early commissioning
related activities like calibration to improve proficiency earlier.
4. Operations Procedures - Procedures direct operating systems and equipment during normal and
postulated abnormal and emergency conditions to ensure that the facility operates within its
design and safety bases. Review project or site quality assurance program documents as they
may control aspects of the development, review, approval, issuance, implementation, and
revision of operating procedures.
DOE G 413.3-23 23
8-30-2019
a. Procedure Development and Review
i. Write procedures in the sequence that steps and actions would occur. Qualified
procedure writers aided by a team of qualified subject matter experts and those who
will implement the procedures write operating procedures for the facility.
ii. Solicit, track, and incorporate feedback from the organization’s functions
responsible for safety, health and environmental requirements, design requirements
and engineering documentation, and safety basis requirements. For example, the
facility safety review committee or its equivalent reviews procedures that affect
safety SSC or implement emergency responses.
iii. Commenters validate the technical content while confirming the procedures give
adequate consideration to human factors. Proceed only after all required reviewers
or functions have commented.
iv. Until DOE approves the DSA and operations procedures, follow a process similar
to an unreviewed safety question (USQ) review.
b. Procedure Verification and Validation
i. Formally review, verify, and validate procedures. Include related activities
supported by qualified resources in the integrated schedule.
ii. Match drawing and label-plate identifiers to components, use units consistent with
those marked on applicable instrumentation, and include easily read and interpreted
charts and graphs.
iii. Conduct a walk-through in the facility or through a simulator with qualified
personnel to verify and validate the procedure and its sequence.
iv. Confirm plant configuration and labelling, procedure sequence, implementation of
the safety basis and design basis requirements, and that procedures conform to the
latest controlled version.
Section 17
Best Practice: Formal procedure verification and validation in the field by qualified
personnel precedes readiness.
c. Procedure Approval - Receive approval of new and revised procedures prior to
implementation from the appropriate functional group managers. Develop and maintain a
list of authorized approvers.
Best Practice: Incorporate mature operating procedures in the testing procedures to allow
operators to gain familiarity with the equipment and find issues with the procedures.
5. Readiness - Simulated operations follow approved procedures to increase the proficiency of
facility personnel. Readiness experts will confirm the state of procedure readiness through
24 DOE G 413.3-23
8-30-2019
drills that simulate both operations and upset conditions. Cold commissioning verifies
performance reflects design, safety, and environmental requirements when conducted in
accordance with approved procedures by qualified personnel under normal and abnormal
conditions.
6. Introduction of Radioactive Materials – After satisfying the requirements of DOE Order
425.1D, Verification of Readiness to Start Up or Restart Nuclear Facilities, the SAA approves
the introduction of radioactive materials into the facility.
Best Practice: Perform each procedure at least twice without intent changes, equipment
failures, or operator errors. This provides a higher level of confidence that the operators will
perform well during the readiness reviews.
DOE G 413.3-23 25
8-30-2019
Figure 5: Post CD-4 Activities by Functional Area
26 DOE G 413.3-23
8-30-2019
3.6. Post CD-4: Closeout Phase
Achieving, validating, and verifying readiness to operate newly built projects consumes significant
time and costs accounted for in the performance baseline. Figure 5 delineates activities for
achieving and verifying readiness to operate.
3.6.1. Post CD-4 Commissioning Considerations
1. Demonstrations - Post CD-4 activities for commissioning may entail demonstrations with
production materials, shielding and confinement appurtenances, and site interfaces. Startup
plans required by DOE Order 425.1D addresses each of these.
2. Hot Commissioning, typically begun following CD-4, often includes verification of shielding,
radioactive confinement and decontamination processes, and validation of process flowsheet
modeling with actual material. Consider these activities as an extension of testing completed
only in full compliance with the authorization basis under the operational configuration
management and quality controls. This guide does not address the details of hot
commissioning.
3.6.2. Post CD-4 Construction Considerations
Transfer as-built drawings, asset inventories, and testing documentation to operations personnel.
3.6.3. Post CD-4 Operations Considerations
1. Overview - Procedures direct operating systems and equipment during normal and postulated
abnormal and emergency conditions to ensure that the facility operates within its design and
safety bases. Review project or site quality assurance program documents as they may control
aspects of revising operating procedures, training, or verifying operator proficiency.
2. Operator Proficiency - Maintain operator proficiency and the shift staff’s capacity to
accommodate the pace of the desired production rate.
3. Procedure Revisions - Changes to requirements, identification of efficiencies, discovery of
errors or omissions, and acceptance of best practices lead to procedure changes.
Section 18
a. Perform an USQ review on all procedure revisions following approval of the DSA.
Document the reason for revisions to procedures. Track procedure revisions over time.
b. Implement procedure revisions concurrently with modifications. Handle procedure
updates required by temporary modifications as a procedure revision implemented
concurrently with the temporary modification.
c. Communicate procedure revisions to appropriate facility personnel through formal means,
such as in a class, or informal means, such as in a pre-shift briefing, in consultation with
the training organization.
DOE G 413.3-23 27 (and 28)
8-30-2019
4. Procedure Configuration Management - Maintain configuration control for procedures to
ensure personnel have access to current approved procedures.
a. Classify procedures according to the methods they employ. Prior to performing work,
verify the procedure reflects the current revision.
b. Submit records of completed procedures to the facility records management organization.
c. Give operators responsible for responding to alarms easy access to controlled alarm
response procedure (ARP) information. Provide ARPs at local control panels, or, where not
possible, at alternate locations convenient to the equipment operator.
5. Training and Proficiency - Training on new and revised procedures satisfy personnel
qualification requirements for readiness to transfer to operations.
a. Plan and schedule proficiency activities prior to and during commissioning.
b. Include scenarios representative of normal, abnormal, and emergency conditions.
c. Verify that operator proficiency has increased during cold commissioning, scheduled
policy revisions, simulations, drills, and on-the-job training.
DOE G 413.3-23 Appendix A
8-30-2019 A-1 (and A-2)
APPENDIX A: ACRONYMS
ARP Alarm response procedures
ASME American Society of Mechanical Engineers
CD Critical decision
CFR Code of Federal Regulations
CGD Commercial grade dedication
CM Configuration management
COR Code of record
CP Commissioning plan
CSE Cognizant system engineer
DOE Department of Energy
DSA Documented safety analysis
EM DOE Office of Environmental Management
ERE Equipment readiness evaluations
FAT Factory acceptance testing
FPD Federal Project Director
HVAC Heating, ventilation, and air conditioning
JTG Joint test group
KPP Key performance parameter
NDE Non-destructive examination
NRC Nuclear Regulatory Commission
ORR Operational readiness review
QA Quality assurance
RA Readiness Assessment
RCAPTS Readiness Certification Assurance Process Tracking System
RR Readiness Review
SAA Startup authorization authority
SDD System design description
SER Safety evaluation report
SMP Safety management program
SOM Shift operations manager
SSC Structures, systems, and components
TRL Technology readiness level
TSR Technical safety requirement
USQ Unreviewed safety question
DOE G 413.3-23 Appendix B
8-30-2019 B-1
APPENDIX B: SOURCES CONSULTED
Table 2: DOE Directive and Guidance Documents
# Organization Document Number Title Version
1 Department of
Energy
DOE O 413.3B Program and Project Management for the
Acquisition of Capital Assets
04/12/2018
(Chg 5)
2 Department of
Energy
DOE G 413.3 – 1 Managing Design and Construction
Using Systems Engineering for Use with
DOE O 413.3A
10/22/2015
(Chg 1)
3 Department of
Energy
DOE G 413.3 – 16A Project Completion and Closeout 10/22/2015
(Chg 1)
4 Department of
Energy
DOE O 425.1D Verification of Readiness to Start Up or
Restart Nuclear Facilities
Section 19
04/02/2013
(Chg 1)
5 Department of
Energy
DOE O 426.2 Personnel Selection, Training,
Qualification, and Certification
Requirements for DOE Nuclear
Facilities
07/29/2013
(Chg 1)
6 Department of
Energy
DOE STD 1189 Integration of Safety into the Design
Process
12/22/2016
7 Department of
Energy
DOE STD 3006-2014 Planning and Conducting Readiness
Reviews
11/12/2014
8 Department of
Energy
DOE HDBK 3012-
2015
Guide to Good Practices for Operational
Readiness Reviews, Team Leader’s
Guide
11/24/2015
9 Department of
Energy
DOE-CNS-
Commissioning-2017
Design and Commissioning Report
https://go.usa.gov/xmvw2
July 2017
(Rev 1)
Table 3: Non-DOE Standards and Informative Documents
# Organization Document Number Title Version
1 American Institute
of Architects
A201 General Conditions of the Contract for
Construction
2017
2 American Institute
of Architects
G704 Certificate of Substantial Completion 2017
3 American Society
of Heating,
Refrigeration, Air
ASHRAE Guideline
1.1
HVAC&R Technical Requirements for
The Commissioning Process
2007
Appendix B DOE G 413.3-23
B-2 8-30-2019
# Organization Document Number Title Version
Conditioning
Engineers
4 American Society
of Heating,
Refrigeration, Air
Conditioning
Engineers
ASHRAE Standard
202
Commissioning Process for Buildings
and Systems
2013
5 Construction
Industry Institute
CII 121 – 1 Planning for Startup: Overview of
Research
6 Construction
Industry Institute
CII 121 – 2 Planning for Startup April 1998
7 Construction
Industry Institute
CII 312 – 2 Vol I Achieving Success in the
Commissioning and Startup of Capital
Projects: Implementing Critical Success
Factors
September
2015
8 Construction
Industry Institute
CII 312 – 2 Vol II Achieving Success in the
Commissioning and Startup of Capital
Projects: Mini – Case Studies
September
2015
9 Department of
Defense Unified
Facilities Guide
Specifications
UFGS – 01 91 00.15 Total Building Commissioning May 2016
10 Institute for
Nuclear Power
Operations
INPO 86 – 023
Vol 5
Guidelines for Nuclear Power Station
Construction Projects, Volume 5,
Startup Testing
October
1986
11 International
Atomic Energy
Agency
IAEA NS – G – 2.9 Commissioning for Nuclear Power
Plants
2003
12 International
Atomic Energy
Agency
IAEA SSR – 2/2 Safety of Nuclear Power Plants:
Commissioning and Operation
2007
13 National Electrical
Contractors
Association
NECA 90 – 2004 Commissioning Building Electrical
Systems
2004
14 National Fire
Protection
Association
NFPA 3HB15 Commissioning and Integrated System
Testing Handbook
2014
15 Nuclear
Regulatory
Commission
NRC RG 1.206, Part
II.1
Inspections, Tests, Analyses, and
Acceptance Criteria
June 2016
16 Nuclear
Regulatory
Commission
NRC RG 1.68 Initial Test Programs for Water-Cooled
Nuclear Power Plants
June 2013
DOE G 413.3-23 Appendix C
8-30-2019 C-1
APPENDIX C: DEFINITIONS
Rely on definitions found in the APM Glossary of Terms (2014). Terms listed below do not appear
in the glossary.
Acceptance criteria – The conditions for declaring that some aspect of the project meets defined
requirements, thus permitting subsequent activities to proceed.
Authorization basis – Those aspects of the facility design basis and operational requirements
important for safe facility operations and relied on by DOE to authorize operation. The facility
safety analysis report and other safety analyses, hazard classification documents, the technical
safety requirements, DOE issued safety evaluation reports, and facility-specific commitments
made to comply with DOE Orders or policies contain the authorization basis.
Section 20
Cold commissioning – Testing activities completed with non-radioactive chemical simulant
materials to confirm attainment of certain requirements prior to introducing radioactive materials
or hazards.
Commissioning authority – The entity responsible for developing and maintaining the
commissioning plan and for advocating for commissioning.
Commissioning plan – A document developed by the commissioning authority establishing
commissioning strategies, sequence, schedule, system design capabilities, and resources needed to
complete the commissioning phase of a project. Updates to the commissioning plan may occur
throughout the project as more project details become known.
Commissioning report – The final commissioning document which presents the commissioning
requirements, process, documentation, findings, process results, compliance with the acceptance
criteria, and actions taken to rectify any deficiencies.
Component testing (grooming) – Testing performed at the component level to confirm proper
installation, serviceable condition, and ability to support system level testing.
Constructability – The effective and timely integration of construction knowledge into the
conceptual planning, design, construction, and field operations of a project to achieve the overall
project objectives in the best possible time and accuracy at the most cost-effective levels. (Source:
CII)
Construction authority - The entity responsible for ensuring the constructability of the project.
Construction complete – See “Substantial completion.”
Construction testing – Testing performed by the construction organization prior to system
turnover for commissioning that typically includes hydrostatic testing, flushing, wiring continuity
checks, nondestructive weld examination through radiography, dye penetration, and ultrasonic
methods, and similar tests.
Appendix C DOE G 413.3-23
C-2 8-30-2019
Design agency – The organization responsible for developing design outputs implementing
requirements established by the design authority.
Design verification – The process of tracing design requirements to placed scope through
analysis, inspection, testing, or other specified approach.
Facility testing – Testing done on groups of systems to demonstrate achievement of facility level
requirements related to product quality, environmental impact, and production capacity or
throughput.
Factory acceptance tests (FATs) – Inspection and static or dynamic testing of systems or major
system components to support the qualification of an equipment system conducted and
documented at the supplier site or facility.
Grooming – See component testing.
Inspection – Verification of construction and installations to confirm their fidelity to the detailed
design and specifications including quality requirements.
Integrated system testing – Tests to verify proper functional interface between systems that
typically include reviewing building system responses to the loss of a utility, transfers to
emergency power, transfers from emergency power to regular power and interfaces between
HVAC, vertical transportation, and security controls and the emergency notification systems for
equipment or system shutdown or lockdown.
Joint test group – Appointed representatives serving as the test authority who review and approve
test documents prepared by the engineering, procurement, and construction testing organization.
Punchlist – A list of incomplete or unacceptable work and malfunctioning equipment or systems
tracked through resolution.
Section 21
Qualified person – A person with specific knowledge, skills, abilities, or credentials designated to
fulfill specific duties and responsibilities.
Readiness verification – the process of establishing through either compliance or performance-
based means that an activity, operation, or facility has achieved an adequate state of preparedness
to advance.
Resolution – The implementation of corrective actions that correct a tested or observed deficiency
in accordance with the contract or, when silent on the matter, to the mutual satisfaction of the
owner and contractor.
Substantial completion – The point in time when the owner accepts the contractor’s claim that a
list of systems have attained a particular status evidenced by desired outcomes of specific
inspection, testing, calibration, grooming and alignment procedures all of which the contract
enumerates and that the contractor has resolved punch list items preventing turnover.
DOE G 413.3-23 Appendix C
8-30-2019 C-3 (and C-4)
System – Linked components that provide a required function or capability identified during the
design process and isolatable from other systems to allow for independent inspection or
confirmation of process function.
System Testing – System or subsystem level testing with integrated sets of components performed
by entities identified in the contract to demonstrate attainment of requirements including, for
example, balance of cooling loop flow or pressure, interlock and control logic verification, transfer
pump performance, and safety function response time.
System Turnover – The transfer of jurisdictional control of a system from one organization to
another, typically part of the phased transition of a project from construction through
commissioning and into operations.
Testing – The determination of the capability of an item to meet specified requirements under a set
of physical, chemical, environmental, or operational conditions.
DOE G 413.3-23 Appendix D
8-30-2019 D-1
APPENDIX D: SAMPLE COMMISSIONING PLAN OUTLINE
1. Introduction
1.1. Plan Purpose – Identify objectives of the commissioning plan based on the applicable
contract(s) and project execution plan.
1.2. Project Description – Describe the project to provide context for the commissioning
plan.
1.3. Scope – List what the commissioning will and will not entail based on project
documents including applicable contract(s).
2. Organization Roles
2.1. Current Phase Organization Roles – Identify current project phase (e.g. pre-CD-2)
organization roles, responsibilities, authorities, and accountabilities. Include the
commissioning or operations organizations supporting design or construction
activities.
2.2. Commissioning Phase Organization Roles – List the roles, responsibilities,
authorities, and accountabilities in the commissioning organization, especially with
respect to commissioning deliverables. Address interfaces with client and regulatory
entities. Describe the organization that will operate the facility during the integrated
testing and readiness assessment activities associated with commissioning.
3. Commissioning Requirements Management
3.1 Programmatic Requirements – List requirements made by reference to contract
clauses, statute, regulation, directive, standard or code related to commissioning and
describe how the project will manage these requirements. Address configuration
management.
Section 22
3.2. Technical Requirements – List technical requirements related to commissioning and
describe how the project will manage these requirements and the testing. Address
utilities needed and remotability.
4. Commissioning Phase Execution
4.1. Turnover – Describe the turnover of constructed systems, facilities, and associated
documentation to include manuals to testing organizations and ultimately to the
operating organization.
4.2. Testing – Describe the test requirements management, test planning, types of tests,
test execution, and test results collection, storage, and reporting. Include how the
project will relate test results to test requirements.
Appendix D DOE G 413.3-23
D-2 8-30-2019
4.3. Safety Management – Describe safety requirements and assumptions in addition to
emergency preparedness needed for commissioning.
4.4. Staff Training and Qualification – Describe qualifications required of
commissioning personnel and site or project specific training required to supplement
those qualifications.
4.5. Operating Scenarios – Describe the full range of routine and non-routine operating
scenarios.
4.6. Operating Procedures – Describe the development, validation, and approval of
routine and non-routine operating procedures during commissioning.
4.7. Readiness Reviews – Identify the standards or handbooks such as DOE-STD-3006 or
DOE-HDBK-3012 that will provide the procedures for the readiness reviews that will
follow commissioning.
5. Commissioning Execution
5.1. Commissioning Sequence – Sequence commissioning activities from turnover
through completion of commissioning. Include with each activity a description or
reference to the applicable requirements. Include major integrated testing activities,
operator proficiency demonstration periods, readiness verification activities, and major
completion milestones.
5.2. Commissioning Deliverables – Describe commissioning deliverables including their
requirements such as format and contents and the entities responsible for generating,
reviewing, approving, and receiving the deliverables.
6. References
6.1. Project Documents
6.2. Codes and Standards
6.3. Master equipment list with links to specifications and submittals
6.4. Other Documents
Appendices
Appendix A: Commissioning Summary Schedule
FOREWORD
1. Purpose of the Guide
2. Commissioning Related Requirements in DOE Order 413.3B
3. Project Management Considerations for Commissioning and Startup
3.1. Pre-CD-0: Initiation Phase
3.2. Pre-CD-1: Definition Phase
3.2.1. PH
3.2.2. Pre-CD-1 Design Considerations
3.2.3. Pre-CD-1 Construction Considerations
3.2.4. Pre-CD-1 Operations Considerations
3.3. Pre-CD-2: Execution Phase
3.3.1. Pre-CD-2 Commissioning Considerations
3.3.2. Pre-CD-2 Design Considerations
3.3.3. Pre-CD-2 Construction Considerations
3.3.4. Pre-CD-2 Operation Considerations
3.4. Pre-CD-3: Execution Phase
3.4.1. Pre-CD-3 Commissioning Considerations
3.4.2. Pre-CD-3 Design Considerations
3.4.3. Pre CD-3 Construction Considerations
3.4.4. Pre-CD-3 Operation Considerations
3.5. Pre-CD-4: Execution Phase
3.5.1. Pre-CD-4 Commissioning Considerations
3.5.2. Pre-CD-4 Design Considerations
3.5.3. Pre-CD-4 Construction Considerations
3.5.4. Pre-CD-4 Operation Considerations
3.6. Post CD-4: Closeout Phase
3.6.1. Post CD-4 Commissioning Considerations
3.6.2. Post CD-4 Construction Considerations
3.6.3. Post CD-4 Operations Considerations
Appendix A: Acronyms
Appendix B: Sources Consulted
Appendix C: Definitions
Appendix D: Sample Commissioning Plan Outline