DOE G 413.3-21A, Cost Estimating Guide
Functional areas: Budget, Financial Management
This Guide provides uniform guidance and best practices that describe the methods and procedures that could be used in all programs and projects at DOE for preparing cost estimates. Supersedes DOE G 413.3-21 Admin Chg 1.
Supersedes:
DOE G 413.3-21 Chg 1 (Admin Chg), Cost Estimating Guide on Jun 06, 2018
Version history and related documents
Supersedes
Earlier documents this one replaced.
- DOE G 413.3-21 Chg 1 (Admin Chg)Cost Estimating Guide (Jun 06, 2018)
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
NOT
MEASUREMENT
SENSITIVE
DOE G 413.3-21A
6-6-2018
Cost Estimating Guide
[This Guide describes suggested non-mandatory approaches for meeting requirements.
Guides are not requirements documents and are not to be construed as requirements in
any audit or appraisal for compliance with the parent Policy, Order, Notice, or Manual.]
U.S. Department of Energy
Washington, D.C. 20585
AVAILABLE ONLINE AT: INITIATED BY:
www.directives.doe.gov Office of Project Management
DOE G 413.3-21A i (and ii)
6-6-2018
FOREWORD
A strong cost estimating foundation is essential to achieving program and project success. Every
Federal cost estimating practitioner is challenged to strive for high quality cost estimates by
using the preferred best practices, methods and procedures contained in this Department of
Energy (DOE) Cost Estimating Guide. Content in this guide supersedes DOE Guide 413.3-21,
Chg1, Cost Estimating Guide, 10-22-2015.
The Guide is applicable to all phases of the Department’s acquisition of capital asset life-cycle
management activities and may be used by all DOE elements, programs and projects. When
considering unique attributes, technology, and complexity, DOE personnel are advised to
carefully compare alternate methods or tailored approaches against this uniform, comprehensive
cost estimating guidance. Programs may specify more specific processes and procedures that
augment or replace those in this guide (e.g. NNSA Life Extension Programs (LEPs) fall under
the process/timeline in the Phase 6.X process).
Guides provide non-mandatory supplemental information and additional guidance regarding
executing the Department’s Policies, Orders, Notices, and regulatory standards. Guides may also
provide acceptable methods for implementing these requirements. Guides are not substitutes for
requirements, nor do they replace technical standards that are used to describe established
practices and procedures for implementing requirements. Send citations of errors, omissions,
ambiguities, and contradictions found in this guide to PMpolicy@hq.doe.gov.
mailto:PMpolicy@hq.doe.gov
iii DOE G 413.3-21A
6-6-2018
TABLE OF CONTENTS
1.0 PURPOSE........................................................................................................................... 1
2.0 KEY GUIDANCE CHARACTERISTICS............................................................................. 1
2.1 High-Quality Cost Estimates .......................................................................................... 2
2.2 Cost Estimate Structure................................................................................................... 4
2.3 Purpose of the Cost Estimate .......................................................................................... 6
2.4 Overview of the Cost Estimating Process Model ........................................................... 6
3.0 COST ESTIMATING INPUTS ............................................................................................ 6
3.1 Project/Program Requirements ....................................................................................... 7
3.2 Application of this Guide to DOE Estimating ................................................................ 9
4.0 COST ESTIMATING CHARACTERISTICS and CLASSIFICATIONS............................. 13
4.1 Planning the Cost Estimates.......................................................................................... 13
4.2 Cost Estimate Classifications........................................................................................ 15
4.3 Cost Estimate Ranges ................................................................................................... 17
Section 2
5.0 COST ESTIMATING METHODS ..................................................................................... 18
5.1 Detailed Estimating Method ......................................................................................... 18
5.2 Parametric Estimating Techniques ............................................................................... 19
5.3 Other Estimating Methods ............................................................................................ 22
5.4 Methods of Estimating Other Life-Cycle Costs............................................................ 25
6.0 COST ESTIMATING DEVELOPMENT PROCESS.......................................................... 26
6.1 Overview of the Cost Estimating Process..................................................................... 26
6.2 Estimate Planning ......................................................................................................... 33
6.3 Cost Estimate Inputs ..................................................................................................... 34
6.4 Cost Estimate Production.............................................................................................. 37
6.5 Cost Estimate Review................................................................................................... 64
6.6 Estimate Reconciliation ................................................................................................ 65
6.7 Cost Estimate Documentation....................................................................................... 65
6.8 Estimate Maintenance................................................................................................... 69
7.0 COST ESTIMATING OUTPUTS ...................................................................................... 70
7.1 Cost Estimate Interfaces ............................................................................................... 70
7.2 Presenting the Estimate to Management....................................................................... 71
7.3 Baselines and Change Control ...................................................................................... 72
7.4 Analysis......................................................................................................................... 73
8.0 COST ESTIMATING EXPECTATIONS............................................................................ 73
8.1 Summary of Expectations ............................................................................................. 73
8.2 Lessons Learned............................................................................................................ 74
8.3 Independent Cost Estimates and Cost Reviews ............................................................ 74
Appendix A: Acronyms and Definitions...................................................................................A-1
Appendix B: Summary of Federal Requirements.....................................................................B-1
Appendix C: Summary of DOE Requirements ........................................................................ C-1
iv DOE G 413.3-21A
6-6-2018
Section 3
Appendix D: Generic Review Criteria.................................................................................... D-1
Appendix E: Example of the Calculation and Use of Economic Escalation ...........................E-1
Appendix F: Example of Life-Cycle Cost Analysis ..................................................................F-1
Appendix G: Cost Estimate Classifications (AACE International) ........................................ G-1
Appendix H: References.......................................................................................................... H-1
Appendix I: DOE Recommendations for Quality Cost Estimates.............................................I-1
1 DOE G 413.3-21A
6-6-2018
1.0 PURPOSE
The primary purpose of the DOE Cost Estimating Guide is to supply DOE cost estimating
practitioners with uniform guidance, methodologies, and best practices to ensure development
of high quality cost estimates. Although applicable to all cost estimating, this guidance is
tailored to be largely applicable to the cost estimation of construction projects and/or programs.
These cost estimates usually result in project independent cost estimates (ICEs) to validate a
project performance baseline. They are similar but different from an independent government
cost estimate (IGCE) normally used to support a contract action. The guidance considers all
phases of the Department's work in creating credible project cost estimates that can be used to
predict, analyze, and evaluate a project and program's cost and schedule, and serve as a critical
program control planning tool. Once credible cost estimates have been presented to and
approved by management, they can be used as a basis for measuring performance against an
approved baseline using an Earned Value Management (EVM) System.
While this guide is largely applicable to the cost estimation of construction projects and/or
programs, the recommended practices and methodologies are also valid when applied to
IGCEs. The IGCE can be used to support contract cost and price analysis, cost realism
analysis for a negotiated contract action, or a contract source selection matter must be
coordinated with the contracting officer and their supporting cost and price analyst to ensure
that they are consistent with the prescribed methodologies, cost treatment, and guidance set
forth in the Federal Acquisition Regulations, DOE Acquisition Regulations, and other agency
policies and guidance. This guide references the GAO Twelve Steps of a High-Quality Cost
Estimating Process (GAO-09-3SP) for techniques that have been proven to improve cost
estimates. Formally documenting the cost estimate using the GAO 12-step process provides an
additional measure of quality. GAO best practices alone are not sufficient to ensure a high
quality cost estimate in all cases; thus this Guide outlines additional techniques and best
practices that, when used in conjunction with the GAO 12-step process, should improve cost
estimates.
The Guide conveys information that conforms to the accepted industry estimating standards
and is intended to facilitate the development of local or site-specific cost estimating
requirements.
2.0 KEY GUIDANCE CHARACTERISTICS
High quality cost estimates support the execution of projects and programs and help to ensure
that management is given the information it needs to make informed decisions. The cost
estimating principles and processes provided herein may be used to meet or adhere to Federal
and DOE requirements while utilizing industry standards and best practices.
Section 4
2 DOE G 413.3-21A
6-6-2018
2.1 High-Quality Cost Estimates
The GAO Cost Estimating Guide, through documentation of industry best practices, cites four
characteristics of high quality cost estimates. They should be credible, well-documented,
accurate and comprehensive.1
1. Credible – Estimates are considered credible if they clearly identify limitations because
of uncertainty or bias surrounding the data or assumptions. Major assumptions should
be varied and other outcomes recomputed to determine how sensitive outcomes are to
changes in the assumptions. A risk and uncertainty analysis should be performed to
determine the level of cost estimate uncertainty or risk. A full scale Monte Carlo
analysis may not be necessary based on type of estimate. Results of the estimate should
be cross-checked and an Independent Cost Estimate (ICE) performed when deemed
necessary based on the CD requirement and/or the risk of the work to determine
whether alternative estimate views produce similar results. Estimates should also be
evaluated against historical ACWP values for similar work that may have been done at
DOE sites. Cost estimating involves collecting and analyzing available historical data
and applying quantitative models techniques, tools and databases to predict a program’s
future cost.
a. Sensitivity analysis is used to identify key elements that drive cost by
manipulating each potential driver in the cost estimate individually and analyzing
the associated impact, to determine which activities have the potential for the
greatest impact to the program amounting to a what-if analysis.
b. Along with a sensitivity analysis, a risk and uncertainty analysis adds to the
credibility of the cost estimate, because it identifies the level of confidence
associated with achieving the cost estimate. Risk and uncertainty analysis
produces more realistic results, because it assesses the variability in the cost
estimate from such effects as schedules slipping, missions changing, and proposed
solutions not meeting users’ needs. An uncertainty analysis gives decision makers
perspective on the potential variability of the estimate should facts, circumstances,
and assumptions change. By examining the effects of varying the estimate’s
elements, a degree of uncertainty about the estimate can be expressed with a range
of potential costs that is qualified by a factor of confidence.
c. Another way to reinforce the credibility of the cost estimate is to see whether
applying a different method produces similar results. In addition, industry rules of
thumb can constitute a sanity check. The main purpose of cross-checking is to
determine whether alternative methods produce similar results. If so, then
confidence in the estimate increases, leading to greater credibility. If not, then the
cost estimator should examine and explain the reason for the difference and
determine whether it is acceptable.
1 GAO Cost Estimating and Assessment Guide, GAO-09-3SP (Washington, D.C., March 2009), p.179.
3 DOE G 413.3-21A
6-6-2018
2. Well-documented – Cost estimates need to be well documented, traceable to original
sources, and easily repeatable or updated. Rigorous documentation also increases an
estimate’s credibility and helps support an organization’s decision making.
Section 5
a. The documentation should explicitly identify the primary methods, calculations,
results, rationales or assumptions, and sources of the data used to generate each
cost element. Cost estimate documentation should be detailed enough to provide
an accurate assessment of the cost estimate’s quality. For example, it should
identify the data sources, justify all assumptions, and describe each estimating
method (including any cost estimating relationships) for every Work Breakdown
Structure (WBS) cost element. Further, schedule milestones and deliverables
should be traceable and consistent with the cost estimate documentation.
b. Estimating methods used to develop each WBS cost element should be
thoroughly documented so that their derivation can be traced to all sources,
allowing for the estimate to be easily replicated and updated.
3. Accurate – Estimates should be based on an assessment of most likely costs, adjusted
properly for inflation, and contain few, if any, minor mistakes. In addition, revise cost
estimates to reflect schedule revisions initiated by contract modifications.
a. Validating that a cost estimate is accurate requires thoroughly understanding and
investigating how the cost estimate was constructed. For example, all WBS cost
estimate elements should be checked to verify that calculations are accurate and
account for all costs, including indirect costs. Moreover, proper escalation factors
should be used to inflate costs so that they are expressed consistently and
accurately. Rechecking spreadsheet formulas and data input is imperative to
validate cost model accuracy.
b. Besides these basic checks for accuracy, the estimating technique used for each
cost element should be reviewed, to make sure it is appropriate for the degree of
design or requirements definition that is complete.
c. Depending on the analytical method chosen, several questions should be
answered to ensure cost estimate accuracy. The GAO Cost Estimating and
Assessment Guide outlines typical questions that should be answered to assess
accuracy associated with various estimating techniques.
4. Comprehensive – Cost Estimators or Analysts should make sure that the cost estimate is
complete and accounts for all costs that are likely to occur. They should confirm its
completeness, its consistency, and the realism of its information to ensure that all
pertinent costs are included.
a. Comprehensive cost estimates completely define the program, reflect the project
schedule, and are technically reasonable. The Cost Estimator should also identify
the technical approach to complete the scope identified, considering that each
approach may yield a different estimate covering the same scope. Estimates
4 DOE G 413.3-21A
6-6-2018
should be structured in sufficient detail to ensure that cost elements are neither
omitted nor redundant. For example, if it is assumed that software will be reused,
the estimate should account for all associated costs, such as interface design,
modification, integration, testing, and documentation.
b. To determine whether an estimate is comprehensive, an objective review must be
performed to certify that the estimate’s criteria and requirements have been met.
This step also infuses quality assurance practices into the cost estimate. In this
effort, the reviewer checks that the estimate captures the complete technical scope
of the work to be performed, using a logical WBS that accounts for all
performance criteria and requirements. In addition, the reviewer must determine
that all assumptions and exclusions the estimate is based on are clearly identified,
explained, and reasonable.
Section 6
From GAO-09-3SP, there are 12 key steps that are recommended to DOE practitioners to
produce high quality cost estimates:2
1. Define the estimate’s purpose
2. Develop an estimating plan
3. Define the Project (or Program) characteristics
4. Determine the estimating structure [e.g., WBS]
5. Identify ground rules and assumptions
6. Obtain data
7. Develop a point estimate and compare to an independent cost estimate
8. Conduct sensitivity analysis
9. Conduct risk and uncertainty analysis
10. Document the estimate
11. Present the estimate for management approval
12. Update the estimate to reflect actual costs and changes
2.2 Cost Estimate Structure
One of the GAO characteristics and best practice steps – determining the estimating structure –
includes the need to develop a “product-oriented” WBS that reflects the requirements and basis
for identifying resources and tasks necessary to accomplish the project’s objectives.
DOE O 413.3B promotes the development of a well-defined and managed project performance
baseline (defined by scope, schedule, cost, and key performance parameters).
This guidance highlights the importance of four closely interrelated processes to help define the
project baseline: development of a WBS for scope definition, cost estimating, schedule
development, and risk management.
• The Work Breakdown Structure process provides:
2 GAO-09-3SP
5 DOE G 413.3-21A
6-6-2018
o A complete decomposition of the project into the discrete products and
activities needed to accomplish the desired project scope (the WBS dictionary
should contain in a narrative format what each activity includes);
o Compatibility with how the work will be done and how costs and schedules
will be managed;
o The visibility to all important project elements, especially those areas of
higher risk, or which warrant additional attention during execution;
o The mapping of requirements, plans, testing, and deliverables;
o A clear ownership by managers and task leaders;
o Organization of data for performance measurement and historical databases; and,
o A living document that is the basic building block for the planning of all
authorized work.
• The Cost Estimate process provides:
o Documented assumptions and basis of estimate that provide further project
definition;
o The activity quantities that make up the scope of work;
o The cost element data (labor and non-labor) needed to complete the
products/deliverables;
o The estimated resource hours and non-labor values that make up the work;
o The component elements (labor, materials, equipment, etc.) required to
complete activities and work packages; and,
o Additional WBS elements mined during the detailed take-off.
o Description of any applicable indirect costs (e.g. operation and maintenance,
security, legacy pension requirements).
• The Schedule process provides:
o The activity durations based on the “crew” production rates per quantity and
other work influences, i.e. hold points, space restrictions, cure time;
o Logical relationships of all schedule activities;
o Critical path that represents the longest duration for the project and the
sequence of work with the least margin for deviation or flexibility;
o The time phasing of activities that identify new activities or costs, i.e. winter
work, escalation needs;
o The milestones and activity relationships that define possible impacts, i.e.
overtime needed to complete activities.
o The durations of Level of Effort (LOE) activities needed for the cost estimate
to accurately develop costs.
Section 7
o The sequence of the procurement of long lead items needed for the cost
estimate to accurately develop costs and expose any possible impacts to the
overall project planning due to the procurements; and
o Additional WBS elements exposed during the development of the planning
sequence and logic.
6 DOE G 413.3-21A
6-6-2018
• The Risk Management process provides3:
o Identification of technical, schedule, and cost risks.
o Selection of appropriate risk handling strategies to either reduce impact of
threats (negative risks) and enhance impact of opportunities (positive risks)
o Analysis of both threats and opportunities to determine fair and reasonable
allowances for risk and estimate uncertainty to support the project/ program
(Contingency & Management Reserve)
2.3 Purpose of the Cost Estimate
The purpose of a cost estimate is determined by its intended use (e.g., studies, budgeting,
baseline proposals, etc.), and its intended use determines its scope and detail. Cost estimates
should have general purposes such as:
• Establish cost and schedule ranges throughout the project development phases;
• Support the budget process by providing estimates of the annual funding and phased
budget requirements required to efficiently execute work for a project or program;
• Support long-term portfolio cost projections;
• Provide data for value engineering/value analysis studies, independent reviews, and
baseline changes.
For projects governed by DOE 413.3B, the purposes of cost estimates include:
• Provide a rough order of magnitude cost range at Critical Decision (CD)-0 (see
Figures 3-1 and 3-2 for a pictorial description of the DOE Critical Decision Process);
• Help the DOE and its managers evaluate and select alternative solutions at CD-1;
• Create a Project Performance Baseline to obtain CD-2 approval and to measure
progress following the CD-2 approval; or,
2.4 Overview of the Cost Estimating Process Model
Traditionally, cost estimates are produced by gathering input, developing the cost estimate and
its documentation, and generating necessary output in an iterative fashion. The scope of work,
schedule, risk management plan, and peer review interact to influence the cost estimating process
and techniques used to develop the output.
3.0 COST ESTIMATING INPUTS
Cost estimate development is initiated by inputs to the process. These inputs are process
elements that can be either one-time or iterative in nature as illustrated in the above process
model. One-time inputs may include project/program requirements, the mission need statement,
and the acquisition strategy or acquisition plan. Iterative inputs may include the technical/scope
development, the schedule development, and the risk management plan with associated risk
identification and mitigation strategies. The peer review results in the process may also identify
the need to revisit various process elements to improve the quality of the cost estimate. Cost
3 See DOE G 413.3-7A, Risk Management for more information.
7 DOE G 413.3-21A
6-6-2018
estimates that are developed early in a project’s life may not be derived from detailed
engineering designs and specifications (may not be a point estimate but a high/low range project
estimate), but they should be sufficiently developed to support budget requests for the remainder
of the project definition phase.
Section 8
Over the life of the project or program, the scope will become more definitive. As this level of
definition increases cost estimates become more definitive with narrower cost ranges, and will
eventually reflect the scope and schedule of work packages and planning packages defined for
the project. Normally, this should reduce uncertainty, assumptions, and number of risks and/or
their impact if realized.
3.1 Project/Program Requirements
Appendixes B and C provide summaries of the Federal and DOE requirements for cost estimates,
respectively. Each DOE program or project may have more specific, detailed requirements.
Examples include the Comprehensive Environmental Response, Compensation, and Liability
Act (CERCLA), National Environmental Policy Act (NEPA); safety and health; site security
requirements; and local requirements that may be specified in contracts, labor agreements, etc.
Many of these requirements are implemented through the DOE annual budget formulation and
execution process, and may add cost to projects. The primary requirement for developing cost
estimates for capital asset projects is DOE O 413.3B. During the life cycle of a project (see
Figures 3-1 and 3-2), various cost estimates and related documents are required to support the
Critical Decision process, the project reviews process, and the annual budget formulation and
execution process.
8 DOE G 413.3-21A
6-6-2018
Figure 3-1. Typical DOE Acquisition Management System for Line Item Capital Asset
Projects4
CD = Critical Decision
EIR = External Independent Review
PARS = Project Assessment and Reporting System
PB = Performance Baseline
PED = Project Engineering and Design
TPC = Total Project Cost
4 DOE Order 413.3B, Program and Project Management for the Acquisition of Capital Assets (October 2017).
9 DOE G 413.3-21A
6-6-2018
Figure 3-2. Typical DOE Acquisition Management System for Other Capital Asset Projects
(i.e., Major Items of Equipment and Operating Expense Projects)5
3.2 Application of this Guide to DOE Estimating
Common cost estimating outputs are shown in Figure 3-3. As this figure depicts, cost estimates
must be developed, updated, and managed over the total life-cycle of any asset and are an
important element for total life-cycle asset management within the DOE. Furthermore, project
cost estimates are an integral element and key input into the management of programs over their
life-cycle. Thus the concepts for cost estimate development described in this Guide can be
applied to all instances when cost estimates are required to support both project and program
management objectives.
As described by the DOE O 413.3B, and other DOE directives, cost estimates and LCC analyses
may be produced for a variety of purposes. As discussed below, these may include:
• The critical decision process within programs/projects (DOE O 430.1C and DOE O
413.3B);
• The DOE annual budget guidance document; and
• Other project/program management purposes (various Federal regulations, DOE Orders,
and industry practices).
5 DOE Order 413.3B
10 DOE G 413.3-21A
6-6-2018
Best practices for Life-Cycle Cost (LCC) include all anticipated costs associated with a project
or program alternative throughout its life; i.e., from authorization through operations to the end
of the facility/system life cycle. (Figure 3-3).6
Facility/System Life Cycle
Figure 3-3. Facility/System Estimate Outputs as Compared to Life-Cycle Major Milestones
3.2.1 DOE Critical Decisions for Project Management and the Supporting Cost
Estimates
Section 9
Critical Decision (CD)-0, Approve Mission Need — Generally, a Rough Order of Magnitude
(ROM) cost estimate range is prepared to support CD-0. Assumptions developed by the project
team generally will drive the project scope and bound both the project scope and costs. There
will likely be very little detail to support these cost estimates, so it is important that scope
assumptions be well-documented. A project cost magnitude range should be established based on
potential project alternatives and major areas of risk, with appropriate consideration of the
accuracy range of any supporting estimates or analyses. The proposed range should be
sufficiently broad such that it fully bounds all possible project cost outcomes, understanding the
very limited design basis that exists at the time and the more imprecise methodologies used at
this stage of the project. This estimate assists in establishing the Acquisition Authority Level for
6 DOE Life Cycle Cost Handbook, Guidance for Lifecycle Cost Estimation and Analysis (September 2014), pages 30-40; see also Appendix F -
Example of Life-Cycle Cost Analysis.
11 DOE G 413.3-21A
6-6-2018
CD-0. In addition, an estimate of the costs to be incurred prior to CD-1, such as preparing an
Analysis of Alternatives and Conceptual Design for the project, could also be required to support
resource planning and near-term schedules.
CD-1, Approve Alternative Selection and Cost Range — Prior to the approval of CD-1, the
project team should develop a definitive estimate of the near-term preliminary design cost, which
is needed for the project engineering and design (PED) funding request (if needed for project
execution). An estimate may also be used to support PED funding for use in preliminary design,
final design and baseline development. The quality of the cost estimate at this stage, as well as
other stages, depends on the uncertainties and risk.
As part of the CD-1 requirement, the project team should perform analyses of the most likely
project alternatives. Thus, the second cost estimate needed at CD-1 is the LCC7 of the likely
alternatives that are being considered. A risk adjusted LCC estimate should be prepared for each
alternative under consideration to ensure the alternative with the best cost/benefit ratio (and
generally the lowest life-cycle cost) to the government is considered. Full LCCs, including all
direct and indirect costs for planning, procurement, operations and maintenance (operational
analysis should be used to evaluate condition and any negative trends on cost projections for
assets in use), and disposal costs must be considered for each alternative being evaluated (OMB
A-11).
After selecting the alternative that best meets the mission, the project team develops the third
estimate, the total project cost (TPC) range, a schedule range with key milestones and events,
and annual funding profiles. The TPC range should consider identified project risks and estimate
uncertainty and encompass the full range of potentially required resources necessary to
successfully execute the planned work associated with the preferred/recommended alternative.
The TPC range also assists in establishing the Critical Decision Authority Thresholds.
Section 10
CD-2, Approve Performance Baseline—Cost estimates supporting CD-2 should utilize more
definitive cost estimating techniques (see Section 5.0). For CD-2, since available information
will be more developed, the range should be collapsed to a point estimate. A single cost estimate
will represent the entire project, utilizing the current scope and associated design parameters.
The estimate will include appropriate allowances for risk and estimate uncertainty, i.e.,
Management Reserve and Contingency (see Section 6.4.5). This estimate is the basis for the cost
estimate of the project’s Performance Baseline and the Performance Measurement Baseline used
for earned value reporting as required for projects with a TPC greater than $50 million.8
CD-3, Approve Start of Construction—Cost estimates based on the Final Design may
incorporate some actual bids received from contractors used to establish the project’s
requirements for construction or execution. Cost estimates for Other Project Costs and
Operational phases of the asset being acquired are finalized. These updated estimates support
authorization to commit resources necessary, within funds provided, to execute the project.
7 DOE Life Cycle Cost Handbook.
8 DOE Order 413.3B
12 DOE G 413.3-21A
6-6-2018
CD-4, Approve Start of Operations or Project Completion—establishes when the project is
ready for turnover or transition to operations, if applicable. Determines the final Estimate at
Completion (EAC) and provides final project cost and performance reports developed in
accordance with the project’s approved WBS. Cost and performance reports are necessary to
document the TPC for the asset acquired, as well as assisting in the capture of historical cost
information.
3.2.2 Annual Budget Process
Project or program budgets are sometimes adjusted to accommodate appropriations and
allocations that are more or less than expected. Some situations may require development of
alternative budget scenarios that can mitigate the risk of project funding uncertainty. When
actual funding differs from planned budgets, baselines and estimates for current-period work
(work packages) should be adjusted accordingly. Timing changes of actual funding versus
planned budgets may not change the technical scope for which an estimate has been developed.
However, those timing changes (extending work into the future from planned schedules) can
cause changes to programmatic scope, project duration, and efficiencies, which affect overall
project costs (such changes are subject to change control – scope, schedule and cost).
3.2.3 Contract Actions
During the normal course of project execution, contract actions occur. The Contracting Officer
may request an Independent Government Cost Estimate (IGCE) to support the action. The
guidance, methodologies, and best practices reflected in this guide are largely applicable to the
cost estimation of projects (i.e., ICEs). However, the development of an IGCE and other analyses
that will be used to support contract cost and price analysis, cost realism analysis for a negotiated
contract action, or a contract source selection matter must be coordinated with the contracting
officer and their supporting cost and price analyst to ensure that they are consistent with the
prescribed methodologies, cost treatment, and guidance set forth in the Federal Acquisition
Regulation, DOE Acquisition Regulations, and other agency policies and guidance. As a best
practice and to derive efficiencies, it is possible and advisable to use the same cost estimating
team to estimate the direct costs (labor, material, and subcontracts) and additional project cost
elements (contingency and government other direct costs (ODCs)) required to complete an ICE
in support of a project performance baseline but advisable to firewall information on other costs
such as contract cost elements (e.g., indirect, fee, etc.) and incentives that directly impact
contract negotiating strategies.
Section 11
The type of contract that will be used to execute the work impacts the basis of an estimate. Types
of contracts range from firm-fixed price, where the contractor assumes the full cost and
performance risk, to cost reimbursement, where the Government assumes the cost and
performance risk and the available strategies for incentivizing successful performance include
the potential for an award fee or a performance-based incentive fee. The contract type and
incentive structure influences the balance of assumed government and contractor risks.
13 DOE G 413.3-21A
6-6-2018
3.2.4 Other Project/Program Management Actions
Various other project or program management actions, such as development of LCC analyses,
cost-benefit analyses, value engineering (VE) studies, earned value analyses, and change
requests may require development of cost estimates.
LCC estimates may be required for many purposes. As a part of alternative selection, LCC
analysis may point to the alternative with the lowest LCC but other analyses and considerations
may need to be considered in the decision process. In cases where benefits can be quantified,
LCC analyses can support more formal cost-benefit analysis for alternative evaluation and
selection. Any time a change in the project is contemplated, or an alternative must be evaluated,
LCC analysis should be considered. (Appendix F presents a simplified example of a LCC
analysis).
Cost estimates are also required to support day-to-day project management decisions. In many
cases, alternatives (e.g., changes in the work flow) are considered that do not affect the entire
project, but do affect the day-to-day details of managing a project. A design detail change that
does not exceed a cost or schedule threshold for management approval is an example.
Comparisons of estimates from diverse sources may require reconciliation. Generally, the
differences are due to the estimates not being based on consistent or current information. Some
examples of sources for differences include assumptions concerning weather, productivity, and
commodity markets. The reconciliation should clearly state the differences and the rationale for
the differences. The Government may have access to more detail on cost estimates for cost
reimbursement projects.
4.0 COST ESTIMATING CHARACTERISTICS and CLASSIFICATIONS
4.1 Planning the Cost Estimates
Table 4-1 describes the elements of planning required to produce credible cost estimates. GAO
conducted an industry-wide survey to address the characteristics of a good estimate; participants
represented a wide variety of industries– including aerospace, automotive, energy, consulting
firms, the Navy, and the Marine Corps. The survey verified that the characteristics listed in the
table are valid and support estimate credibility. GAO also found that despite the fact that these
characteristics have been published and known for decades, many Federal agencies still lack the
ability to develop cost estimates that can satisfy these basic characteristics.
14 DOE G 413.3-21A
6-6-2018
Table 4-1. Basic Characteristics of Credible Cost Estimates9
Planning Step Description
Clear Identification
of Task
• Estimator must be provided with the scope description, ground rules
and assumptions, and technical and performance characteristics.
• The estimate’s constraints and conditions must be clearly identified
to ensure the preparation of a well-documented estimate.
Section 12
Broad Participation • The Integrated Project Team and the Integrated Acquisition Team
in Preparing should be involved in determining requirements based on the
Estimates mission need, in development of the Project Execution Plan, and in
defining parameters and other scope characteristics at each Critical
Decision milestone.
• Data should be independently verified for accuracy, completeness,
and reliability.
Availability of • Use numerous sources of suitable, relevant, and available data.
Valid Data • Use relevant, historical data from similar work to project costs of
the new work. The historical data should be directly related to the
scope’s performance characteristics.
Standardized • Use of a standard WBS that is as detailed as possible, continually
Structure for the refining it as the maturity of the scope develops and the work
Estimate becomes more defined.
• The WBS elements should ultimately drill down to the lowest level,
the work package.
• The WBS ensures that no portions of the estimate (and schedule)
are omitted or duplicated. This makes it easier to make comparisons
to similar work.
Provision for
Uncertainties and
Risk
• Identify the confidence level (e.g., 80 percent) needed to establish a
successful planning process. Identify uncertainties and develop an
allowance to mitigate cost effects of the uncertainties.
• Include known costs and allow for historically likely but
specifically unknown costs. (Reference: DOE G 413.3-7A, Risk
Management Guide).
Recognition of • Ensure that economic escalation is properly and realistically
Escalation reflected in the cost estimate. Escalation is schedule driven, and
scheduling assumptions need to be clearly noted. NOTE: Project
teams may use specific rates relative to the site when available. In
any case, the source of escalation information used should be
9 GAO 09-3SP, p.6.
15 DOE G 413.3-21A
6-6-2018
Planning Step Description
identified and the applicability of the rates should be
explained/justified.
Recognition of
Excluded Costs
• Include all costs associated with the scope of work; if any cost has
been excluded, disclose and include a rationale.
Independent
Review of
Estimates
• Conducting an independent review of an estimate is crucial to
establishing confidence in the estimate. The independent reviewer
should verify, modify, and correct an estimate to ensure realism,
completeness, and consistency.
Revision of
Estimates for
Significant Changes
• Update estimates to reflect changes in the design requirements.
Large changes that affect costs can significantly influence
decisions.
DOE project review and assessment teams examine how well project cost estimates align with
the GAO 12 Step Best Practices. Most DOE contractors have already incorporated a best
management practice depicting how their project planning and cost estimating structure
development relates to the GAO 12 Steps. Appendix I presents more detail for applying GAO
guidelines to develop quality DOE cost estimates.
4.2 Cost Estimate Classifications
Most cost estimates have common characteristics, regardless of whether the technical scope is
traditional (capital funded, construction, equipment purchases, etc.) or nontraditional (expense
funded, research and development, operations, etc.). The most common characteristics are levels
of definition, requirements (end usage/purpose), and techniques used. These characteristic levels
are generally grouped into cost estimate classifications. Cost estimate classifications may be used
with any type of traditional or nontraditional project or work and may include consideration of
(1) where a project stands in its life cycle, (2) level of definition (amount of information
available), (3) techniques to be used in estimation (e.g., parametric vs. definitive), and/or (4) time
constraints and other estimating variables.
Section 13
Typically, as a project evolves, it becomes more definitive. Cost estimates depicting evolving
projects or work also become more definitive over time. Determination of cost estimate
classifications helps ensure that the cost estimate quality is appropriately considered.
Classifications may also help determine the appropriate application of contingency, escalation,
use of direct/indirect costs (as determined by cost estimate techniques), etc.
Widely accepted cost estimate classifications are found in AACE International Recommended
Practice (RP) 17R-97 and RP 18R-97; see Appendix G). Appendix G includes a complete
description of AACE International’s classifications. Table 4-2 provides example primary and
secondary characteristics and expected estimate uncertainty ranges, as a function of the estimate
class. These characteristics and ranges provide expected estimate accuracy ranges based on
scope definition data from historical projects, however they should not be used to calculate
16 DOE G 413.3-21A
6-6-2018
contingency. Further information on risk analysis can be found in DOE G 413.3-7A, Risk
Management Guide. DOE’s cost estimate classifications generally follow these recommended
practices, although historically the more common cost estimate classifications are order of
magnitude, preliminary, and definitive, which approximately equate to the AACE International’s
Classes 5, 3 and 2, respectively. Table 4-3 provides an example of the typical suggested types of
cost estimates for each DOE Critical Decision as compared with the AACE International
classification.
A project cost estimate may comprise separate estimates of differing classifications. Certain
portions of the design or work scope may be well defined, and therefore warrant more detailed
cost estimating techniques and approaches, while other areas are relatively immature and
therefore appropriately estimated using parametric or other less definitive techniques.
Table 4-2. Cost Estimate Classification for Process Industries10
10 AACE International Recommended Practice 18R-97, Cost Estimate Classification System – As Applied in Engineering, Procurement, and
Construction for the Process Industries (March 2016).
17 DOE G 413.3-21A
6-6-2018
Table 4-3. Generic Anticipated Types of Estimates for DOE Critical Decisions
Critical
Decision Suggested Estimate
Recommended
Minimum AACE
International
Estimate
Classification
CD-0 Cost estimate range Class 5
Estimate of costs to be incurred prior to CD-1 Class 3
CD-1 TPC Range Class 4
Estimate of near term preliminary design cost Class 3
CD-2 Single point estimate representing entire project:
− Low risk projects Class 3
− High risk projects Class 2
CD-3 Cost estimate based on Final Design [or
sufficiently mature to start construction]:
− Low risk projects Class 2
− High risk projects Class 2
CD-4 N/A
As a general rule, particularly for projects that are in the early stages of development, a
combination of estimate classifications must be used to develop the entire estimate. In these
situations, estimators should use a combination of detailed unit cost estimating, unit costs, and
detailed take-off (Class 1) techniques for work that will be executed in the near future and is well
defined; semi-detailed unit costs with assembly level items (Class 3) techniques for for
preliminary or budget authorization and control estimating work that is currently in the planning
stages but less defined; and capacity factored parametric models, judgment, or analogy (Class 5)
techniques for order of magnitude estimating of future work that has not been well defined. As a
project progresses through the Acquisition Management System (initiation, definition, execution,
and transition/closeout phases) and the project development and planning matures, the life-cycle
cost estimate becomes more definitive. This may be referred to as “rolling-wave” planning,
where detailed planning of future work is done in increments, or waves as the project progresses
through phases.
Section 14
4.3 Cost Estimate Ranges
The Department’s Acquisition Management System includes Critical Decisions (CDs) that
define exit points from one phase of project development and entry into the succeeding project
phase. Prior to CD-2 approval, DOE O 413.3B requires the use of ranges to express project cost
estimates. These ranges should depict TPCs in the early stage, even at CD-0. Ranges may be
determined or based upon various project alternatives, project identified risks, and confidence
levels.
LCC estimates that are developed early in a project’s life may not be derived from detailed
engineering, but must be sufficiently developed to support budget requests for the remainder of
18 DOE G 413.3-21A
6-6-2018
the project definition phase. In addition, ranges should include all anticipated resources, using
appropriate estimating techniques that are necessary to acquire or meet the identified capability.
During the project definition phase, at the conclusion of the concept exploration process, the
alternative selected as the best solution to a mission need is presented for approval. The solution
presented includes the TPC range, a schedule range with key milestones and events, and annual
funding profiles that are risk-adjusted and define all required resources necessary to successfully
execute the planned work.
The estimate range (lower and upper bounds) as defined in DOE G 413.3-13, Acquisition
Strategy Guide, is determined by independently assessing the lower and upper cost estimate
range for each of the major WBS elements. In some situations, the range may be in part a
function of scope variability, e.g., if a decision to add five or 10 glove-boxes is pending. The
range can also be established by the project team considering the cost and schedule estimate
uncertainties as part of the risk analysis. A risk analysis is analytical in nature and, although
simulation tools aid the analyst in assessing impact and consequences, no simulation tool can
substitute for a thorough logical deterministic process. The risks are identified by the likelihood
of occurrence and the probable impact.
The lower bound of the cost range may represent a scenario where the project team has
determined a low likelihood of occurrence and low impact of the identified risks, and a higher
likelihood for the realization of opportunities. The risks may be accepted; therefore it is not
necessary to include resources to mitigate them.
The upper bound of the cost range may represent a scenario where the project team has
determined a low likelihood of occurrence, but the impact of the identified risks would be
significant. The risks will be managed and appropriate resources identified to mitigate each
risk.11
5.0 COST ESTIMATING METHODS
Many cost estimating methods/techniques are available to facilitate the cost estimating process.
Depending on project scope, estimate purpose, project maturity, and availability of cost
estimating resources, the estimator may use one, or a combination, of these techniques. As
shown in Table 4-3, as the level of project definition increases, the estimating methodology tends
to progress from conceptual (stochastic/parametric) techniques to deterministic/definitive
techniques. The following sub-sections include techniques that may be employed in developing
cost estimates.
5.1 Detailed Estimating Method
Activity-based, detailed or unit cost estimates are typically the most definitive of the estimating
techniques and use information down to the lowest level of detail available. They are also the
most commonly understood and utilized estimating techniques.
Section 15
11 A more thorough discussion on the risk management process can be found in DOE G 413.3-7A, Risk Management Guide (January 2011).
19 DOE G 413.3-21A
6-6-2018
The accuracy of activity-based detailed or unit cost techniques depends on the accuracy of
available information, resources spent to develop the cost estimate and the validity of the bases
of the estimate. A work statement and set of drawings or specifications may be used to identify
activities that make up the project. Nontraditional estimates may use the WBS, team input and
the work statement to identify the activities that make up the work.
Each activity is further decomposed into detailed items so that labor hours, material costs,
equipment costs, and subcontract costs are itemized and quantified. Good estimating practice is
to use a verb as the first word in an activity description. Use of verbs provides a definitive
description and clear communication of the work that is to be accomplished. Subtotaled, the
detailed items comprise the direct costs. Indirect costs, overhead costs, contingencies and
escalation are then added as necessary. The estimate may be revised as known details are refined.
The activity-based detailed or unit cost estimating techniques are used mostly for Class 1 and
Class 2 estimates, and they should always be used for proposal or execution estimates.
Activity-based detailed cost estimates imply that activities, tasks, work packages, or planning
packages are well-defined, quantifiable, and are to be monitored, so that performance can be
reported accurately. Quantities should be objective, discrete, and measurable. These quantities
provide the basis for an earned value measurement of the work within the activities and the
WBS.
Advantages in using activity-based detailed or unit cost estimating methods include:
• A greater level of confidence;
• More detail that can be used for better monitoring, change control, etc.;
• Enhanced scope and individual activity definition;
• Detailed quantities to establish more accurate metrics; and,
• Better resource basis for the schedule.
Disadvantages include:
• More time needed to develop the estimate; More costly to develop than relationship
estimating; and,
• Some elements can be omitted by accident.
5.2 Parametric Estimating Techniques
A parametric model is a useful tool for preparing early conceptual estimates when there is little
technical data or engineering deliverables to provide a basis for using more detailed estimating
methods.12 A parametric estimate comprises cost estimating relationships and other cost
estimating functions that provide logical and repeatable relationships between independent
variables, such as design parameters or physical characteristics and cost, the dependent variable.
Capacity factor and equipment factor are simple examples of parametric estimates; however,
sophisticated parametric models typically involve several independent variables or cost drivers.
12 It is recommended that when using these cost estimating models that they should be verified and validated by recognized standard industry
practices such as the Tri Services Parametric Cost Model Standard.
20 DOE G 413.3-21A
6-6-2018
Parametric estimating is reliant on the collection and analysis of previous or historical project
cost data in order to develop the cost estimating relationships.
5.2.1 Cost Estimating Relationships
Section 16
Cost estimating relationships (CERs), also known as cost models, composites, or assemblies/
subassemblies, are developed from historical data for similar systems or subsystems. A CER is
used to estimate a particular cost or price by using an established relationship with an
independent variable.13 For example, a CER of design hours per drawing may be applied to the
estimated number of drawings to determine total design hours. Identifying an independent
variable (driver) that demonstrates a measurable relationship with contract cost or price develops
a CER. That CER may be mathematically simple in nature (e.g., a simple ratio), or it may
involve a complex equation.
Parametric estimates are commonly used in conceptual and check estimates. A limitation to the
use of CERs is that to be most effective, one must understand completely how the CER was
developed and where and how indirect costs, overhead costs, contingency, and escalation are
applicable. The parametric estimating technique is most appropriate for Class 5, 4, and 3 cost
estimates. The parametric technique is best used when the design basis has evolved little, but the
overall parameters have been established.
There are several advantages to parametric cost estimating. Among them are:
• Versatility—If the data are available, parametric relationships can be derived at any level
(system, subsystem component, etc.). As the design changes, CERs can be quickly
modified and used to answer “what-if” questions about design alternatives.
• Sensitivity—Simply varying input parameters and recording the resulting changes in cost
will produce a sensitivity analysis.
• Statistical output—Parametric relationships derived through statistical analysis will
generally have both objective measures of validity (statistical significance of each
estimated coefficient and of the model as a whole) and a calculated standard error that can
be used in risk analysis. This information can be used to provide a confidence level for
the estimate based on the CERs predictive capability.
There are also disadvantages to parametric estimating techniques, including:
• Database requirements—The underlying data must be consistent and reliable. In
addition, it may be time-consuming to normalize the data or to ensure that the data were
normalized correctly. Without understanding how data were normalized, the estimator is
accepting the database on faith, thereby increasing the estimate’s risk.
• Currency—CERs must represent the “state-of-the-art;” that is, they must be periodically
updated to capture the most current cost, technical, and programmatic data.
• Relevancy—Using data outside the CER range may cause errors because the CER loses
its predictive capability for data outside the development range.
13 FAI Glossary, FAR 15.404-1(c)(2)(i)(C); PM Glossary of Terms Handbook; and, AACE International Cost Engineering Terminology
21 DOE G 413.3-21A
6-6-2018
• Complexity—Complicated CERs (e.g., non-linear CERs) may be difficult for others to
readily understand the relationship between cost and its independent variables.
5.2.2 End Products Unit Method
The End Products Unit Method is used when enough historical data are available from similar
work based on the capacity of that work. The method does not take into account any economies
of scale, or location or timing of the work.
Section 17
Consider an example of estimating the construction cost of a parking lot. From a previous project
the total cost was found to be $150,000 for 100 parking stalls, or $1,500/stall. For a new parking
lot of 225 parking stalls, the estimated cost would be $1,500/parking stall x 225 parking stalls =
$337,500.
5.2.3 Physical Dimension Method
The Physical Dimension Method is used when enough historical data is available from similar
work based on the area or volume of that work. This method uses the physical dimension
relationship of existing work data to that of the physical dimensions of similar new work. The
method does not take into account any economies of scale, or location or timing of the work
To consider the example in section 5.3, the total cost of the previous project was $150,000 for a
3,000 square feet parking lot. The new parking lot is to be 7,000 square feet; therefore,
($150,000/3,000 square feet = $50/ square feet for the previous project so the estimated cost of
the new project is $50/ square feet x 7,000 square feet = $350,000.
5.2.4 Capacity Factor Method
The Capacity Factor Method is used when enough historical data are available from similar work
based on the capacity of that work. The method uses the capacity relationship of existing work
data to that of the capacity of similar new work. It accounts for economies of scale, but not
location or timing of the work.
For example, consider a known power plant that produces 250 MW(t)/hour and costs
$150,000,000 to construct. A new plant will produce 300 MW(t)/hour. From historical data, 0.75
is the appropriate capacity factor.
Using the equation Cost (new) = Cost (known) (Capacity (new)/ Capacity (known)e
Where: e = capacity factor derived from historical data
Cost (new) = $150,000,000 (300/250).75
Cost (new) = $172,000,000 (rounded)
5.2.5 Ratio or Factor Method
The Ratio or Factor Method is used when historical building and component data are available
from similar work. Scaling relationships of existing component costs are used to predict the cost
http:300/250).75
22 DOE G 413.3-21A
6-6-2018
of similar new work. This method is also known as “equipment factor” estimating. The method
does not account for any economies of scale, or location or timing of the work.
To illustrate, if a plant that cost $1,000,000 to construct has major equipment that costs
$300,000, then a factor of 3.33 represents the plant cost to equipment cost “factor.” If a proposed
new plant will have $600,000 of major equipment, then the factor method would predict that the
new plant is estimated to cost $600,000 x 3.33 = $2,000,000.
5.3 Other Estimating Methods
5.3.1 Level of Effort Method
A form of parametric estimating is based on level of effort (LOE). Historically, LOE is used to
determine future repetitive costs based on past cost data, as in, “we spent ~$10M on operations
last year, so we need ~$10M next year.” Often LOE estimates have few parameters or
performance objectives from which to measure or estimate, but are carried for several time
periods at a similar rate (e.g., the costs of operations, such as X number of operators for Y
amount of time). LOE estimates are normally based on hours, full-time equivalents (FTEs), or
“lot.” Since they are perceived to have little objective basis, LOE estimates are often subject to
scrutiny. The keys to LOE estimates are that they should generally be based on known scope
(although quantities may be assumed) and have a basis, even if it is simply the opinion of an
expert or a project team.
Section 18
Variations on LOE techniques are numerous and should be considered carefully before deciding
to employ a specific technique. For instance, using LOE for installing a piece of equipment may
raise questions about why it does not include the circumstances surrounding the installation
(contamination and security issues and related productivity adjustments). Also questionable in
LOE estimates are indirect costs, overhead costs, profit/fee, and other assumptions.
5.3.2 Specific Analogy Method
Specific analogies use the known cost or schedule of an item as an estimate for a similar item in
a new system. Adjustments are made to known costs to account for differences in relative
complexities of performance, design, and operational characteristics.
A variation of this technique is the “review and update technique,” where an estimate is
constructed by examining previous estimates of the same or similar projects for logic, scope
completion, assumptions, and other estimating techniques, and then updated to reflect any
pertinent differences. The specific analogy technique is most appropriate in the early stages of a
project; that is, for Class 5 and 3 cost estimates.
There are several advantages to using the analogy method, including:
• It can be used before detailed program requirements are known;
• If the analogy is strong, the estimate will be defensible;
• An analogy can be developed quickly and at minimal cost; and,
• The tie to historical data is simple enough to be readily understood.
23 DOE G 413.3-21A
6-6-2018
There are, however, also some disadvantages in using analogies, such as:
• An analogy relies on a single data point;
• It is often difficult to find the detailed cost, technical, and programmatic data required for
analogies; and,
• There is a tendency to be too subjective about the technical parameter adjustment factors.
The last disadvantage can be better explained through an example. If a cost estimator assumes
that a new component will be 20 percent more complex, but cannot explain why, this adjustment
factor is unacceptable. The complexity must be related to the system’s parameters, such as the
new system will have 20 percent more data processing capacity or will weigh 20 percent more.
5.3.3 Expert Opinion Method
As stated in the GAO Cost Estimating and Assessment Guide, “expert opinion, also known as
engineering judgment, is commonly applied to fill gaps in a relatively detailed WBS when one or
more experts are the only qualified source of information, particularly in matters of specific
scientific technology.” Expert opinion is an estimating technique whereby specialists are
consulted until a consensus can be established regarding the cost of a program, project,
sub-project, task, or activity. The expert opinion technique is most appropriate in the early stages
of a project, or for Class 5, 4, and 3, cost estimates. These cost estimates document a list of the
experts consulted, their relevant experience, and the basis for their opinions.
A formalized procedure, the Oracle Method, has been used to forecast cost based on expert
opinion. Six or more experts are given a specific, usually quantifiable, question. Each expert sees
the estimates produced by the others and modifies his or her previous estimate until a consensus
is reached. If after four rounds there is no consensus, the original question may be broken into
smaller parts for further rounds of discussion or a moderator may attempt to produce a final
estimate.
Section 19
This technique may be used for either portions of or entire estimates and activities for which
there is no other sound basis. A limitation arises when a cost estimator’s or project manager’s
status as an expert is questioned.
The advantages of using an expert opinion are:
• It can be used in the case where there are no historical data available;
• The approach takes minimal time and is easy to implement once the experts are
assembled;
• An expert may provide a different perspective or identify facets not previously
considered leading to a better understanding of the program; and,
• It can be useful as a cross-check for CERs that require data significantly beyond the data
range.
The disadvantages associated with an expert opinion include:
24 DOE G 413.3-21A
6-6-2018
• It should be used as a last resort due to its lack of objectivity;
• There is always a risk that one expert will try to dominate the discussion and sway the
group toward his/her opinion; and,
• This approach is not considered very accurate or valid as a primary estimating method.
Due to its subjectivity and lack of supporting documentation, expert opinion should be used
primarily for confirming that the estimate does not contain elementary mistakes or invalid
assumptions.
5.3.4 Trend Analysis Method
Trend analysis method is an estimating technique for current, in-progress work, and is also used
to explain quantitatively how a project is progressing. It is especially useful when large
quantities of commodities are a significant part of a project (e.g., mass excavations, mass
concrete placement, structural steel fabrication/installation, etc.) A trend is established using an
efficiency index derived by comparing originally planned costs (or schedules) against actual
costs (or schedules) for work performed to date. For example, a project’s actual costs to date,
divided by the number of units produced provides a measure of current costs per unit. Variations
in this measure from previous periodic trending information can be used to adjust the estimate
for the remaining work, as well as to help project managers with decisions regarding resources
(people, equipment, etc.) and make near term planning adjustments.
The trend analysis technique can be used at almost any stage of project development and can
even be used to update cost estimates developed using other techniques. It should be
remembered, however, that during a long project activity, productivity rates may vary, with less
than optimal productivity occurring as project activity begins, improved productivity developing
until an optimum sustained level can be achieved, and then less than optimal productivity
encountered near the end of the project as problems are resolved and final activities are
completed. Thus trend analysis estimates should consider the current stage and remaining stage
of a project activity carefully before extrapolating current productivity or cost values.
5.3.5 Learning Curve Method
The learning curve is a way to understand the efficiency of producing or delivering large
quantities. Studies have found that people engaged in repetitive tasks will improve their
performance over time, i.e., for large quantities of time and units, labor costs will decrease, per
unit.
Section 20
The aircraft industry first recognized and named the learning curve and successfully used it in
estimating. It can be used most effectively when new procedures are being fielded and where
labor costs are a significant percentage of total unit cost. But it should always be understood that
the learning curve applies only to direct labor input. Materials and overhead will not necessarily
be affected by the learning curve. Figure 5-1 illustrates a hypothetical learning curve.
25 DOE G 413.3-21A
6-6-2018
U
ni
ts
o
f P
ro
du
ct
io
n
Average Unit Cost
Figure 5-1. The Learning Curve Method
Typical learning curves start with high labor costs (hours) that decrease rapidly on early
production units, and then flatten as production continues. This exponential relationship between
labor productivity and cumulative production is expressed in terms of labor reduction resulting
from production increases. For example, a 90-percent learning curve function requires only 90
percent of the labor hours per unit each time production doubles. When a total of 200 units are
produced, labor costs for the second 100 units will be only nine tenths the costs of the first 100.
Increased productivity allows for lower labor costs later in a project, and should result in a lower
overall project cost. Subsequent similar projects should have fewer labor hours for each unit of
production also, which could result in both more contractor profit and lower government contract
costs.
No standard reduction rate applies to all programs, and learning curve benefits will vary. When
labor hour reductions of the first units are known, an accurate percentage reduction can be
calculated and extended to subsequent units. If no data exists, it may be risky to assume that
learning curve savings will be experienced.
The learning curve estimating technique can be considered for all traditional and nontraditional
projects. The learning curve is most effective when applied to repetitive activities, and can also
be used to update labor hours calculated in earlier estimates.
5.4 Methods of Estimating Other Life-Cycle Costs
Different methods may be used to estimate other project/program support costs, including
design, engineering, inspections, environmental, safety and health (ES&H), etc. Some common
methods are counting drawings and specifications, FTE, and percentage.
26 DOE G 413.3-21A
6-6-2018
5.4.1 Count Drawings and Specifications Method
The estimator calculates the number of drawings and specifications representing a specific
project. The more complex a project is, the more drawings and specifications it will require
meaning that associated design costs will be higher.
5.4.2 Full-Time Equivalent Method
The number of individuals anticipated to perform specific functions of a project forms the basis.
The man-hour quantity is calculated and multiplied by the cost per labor hour and the duration of
the project function to arrive at the cost.
5.4.3 Percentage Method
The estimator calculates a certain percentage of the direct costs and assigns this amount to the
other project functions (such as design, project management, etc.). Some possible benchmarks
for DOE projects include:
• Total design percentages are usually 15 to 25 percent of estimated construction costs for
DOE projects. Non-traditional, first of a kind projects may be higher, while simple
construction such as buildings will be lower than this range (approximately 6 percent);
the more safety and regulatory intervention is involved, the higher the percentage.
Section 21
• Project management costs range from 5 to 15 percent of the other estimated project costs
for most DOE projects, depending on the nature of the project and the scope of what is
covered under project management. The work scope associated with this range should be
defined very specifically and clearly.
6.0 COST ESTIMATING DEVELOPMENT PROCESS
6.1 Overview of the Cost Estimating Process
The overall Cost Estimating Process Model described here appeared earlier in Section 2.4,
Figure 2-1. The cost estimating development process discussed in this section follows the 12
steps model recommended by GAO14 and is part of the cycle of iterative activities for developing
the cost estimate depicted in Figure 2-1. Figure 6-1 depicts the 12 step GAO model. Table 6-1
further identifies the implementing tasks related to the GAO-12 step cost estimating development
process. Systematically conducting these tasks enhances the reliability and validity of cost
estimates. The process is iterative.
14 GAO-09-3SP
D
O
E G
413.3-21A
27 (and 28)
6-6-2018
Figure 6-1. The GAO 12 Steps Cost Estimating Development Process Model
SOURCE: GAO-09-3SP
DOE G 413.3-21A 29
6-6-2018
Table 6-1. DOE Crosswalk Depicting DOE G 413.3-21 and GAO Twelve Steps of a High-
Quality Cost Estimating Process by Project Phase, Best Practices
GAO Best Practice GAO Cost Estimating Activities
Where Conformance to
GAO Practice is
Demonstrated in
DOE G 413.3-21
Step 1: Define the
Estimate's Purpose
1. Determine estimate’s purpose, required level of detail, and
overall scope.
2. Determine who will receive the estimate.
Guidance related to the
purpose of the estimate is
found in Sections 2.3, 3.2,
6.2, & 6.7.1.
Step 2: Develop an
Estimating Plan
1. Determine the cost estimating team and develop its master
schedule.
2. Determine who will do the independent cost estimate
3. Outline the cost estimating approach
4. Develop the estimating timeline.
Guidance related to
planning the estimate
development can be found
in Section 4.1, Table 4-1, &
Section 6.2.
Step 3: Define the
Program
Characteristics
1. In a technical baseline description document, identify the
program’s purpose and its system and performance
characteristics and all system configurations.
2. Describe technology implications.
3. Describe acquisition schedule and strategy.
4. Describe relationship to other existing systems, including
predecessor or similar legacy systems.
5. Define support (manpower, training, etc.) and security needs
Guidance related to DOE
Program characteristics
and requirements for cost
estimates are discussed in
Section 3 & also in Section
and risk items.
6. Develop system quantities for development, test, and
production.
7. Define deployment and maintenance plans.
6.3.2.
Step 4: Determine
the Estimating
Structure
1. Define a WBS and describe each element in a WBS
dictionary (a major automated information system may have
only a cost element structure).
2. Choose the best estimating method for each WBS element.
3. Identify potential cross-checks for likely cost and schedule
drivers.
4. Develop a cost estimating checklist.
Guidance relative to
estimate structure is found
in Table 4-1, & discussed
extensively in Section 5
30 DOE G 413.3-21A
6-6-2018
GAO Best Practice GAO Cost Estimating Activities
Where Conformance to
GAO Practice is
Demonstrated in
DOE G 413.3-21
Step 5: Identify
Ground Rules and
Assumptions
1. Clearly define what the estimate includes and excludes.
2. Identify global and program-specific assumptions, such as the
Section 22
estimate’s base year, including time-phasing and life cycle.
3. Identify program schedule information by phase and program
acquisition strategy.
4. Identify any schedule or budget constraints, inflation
assumptions, and travel costs.
5. Specify equipment the government is to furnish as well as the
use of existing facilities or new modification or development.
The concepts related to
ground rules and
assumptions are discussed
in Table 4-1, and again in
Section 6, with specific
6. Identify prime contractor and major subcontractors.
7. Determine technology refresh cycles, technology
assumptions, and new technology to be developed.
8. Define commonality with legacy systems and assumed
heritage savings.
9. Describe effects of new ways of doing business.
guidance in Section 6.7.1.
Step 6: Obtain Data
1. Create a data collection plan with emphasis on collecting
current and relevant technical, programmatic, cost, and risk
data.
2. Investigate possible data sources.
3. Collect data and normalize them for cost accounting,
inflation, learning and quantity adjustments.
4. Analyze the data for cost drivers, trends, and outliers and
compare results against rules of thumb and standard factors
derived from historical data.
5. Interview data sources and document all pertinent
information, including an assessment of data reliability and
accuracy.
6. Store data for future estimates
Estimate data sources and
associated guidance can
be found in Section 2.2,
Section 3,and is the focus
of Section 6.3
Step 7: Develop a
Point Estimate and
Compare it to an
Independent Cost
Estimate
1. Develop the cost model, estimating each WBS element,
using the best methodology from the data collected, and
including all estimating assumptions.
2. Express costs in constant year dollars.
3. Time-phase the results by spreading costs in the years they
are expected to occur, based on the program schedule.
4. Sum the WBS elements to develop the overall point
estimate. Validate the estimate by looking for errors like
double counting and omitted costs.
5. Compare estimate against the independent cost estimate
The techniques available
for estimate development
are described in Section 5
and the estimate
development process itself
is discussed extensively in
Section 6.4. Other tasks
identified here are
discussed in Sections 6.5
and 6.6.
and examine where and why there are differences.
6. Perform cross-checks on cost drivers to see if results are
similar.
7. Update the model as more data become available or as
changes occur and compare results against previous
estimates.
Independent Cost
Estimates are discussed in
Section 8.3 with guidance
provided in Appendix I.
DOE G 413.3-21A 31
6-6-2018
GAO Best Practice GAO Cost Estimating Activities
Where Conformance to
GAO Practice is
Demonstrated in
DOE G 413.3-21
Step 8: Conduct The concept of Sensitivity
Sensitivity
Analysis (method
and rigor of the
analysis will vary
1. Test the sensitivity of cost elements to changes in estimating
input values and key assumptions.
2. Identify effects on the overall estimate of changing the
Analysis discussed in
Section 6.4.5 is a subset of
contingency analysis.
Requirements for analyses
depending on the program schedule or quantities. can also be found in
estimate level) 3. Determine which assumptions are key cost drivers and
which cost elements are affected most by changes.
Guidance document
Section 6.1, Table 6-1 and
Section 6.7.1.
Step 9: Conduct
Risk and
Uncertainty
Section 23
1. Determine and discuss with technical experts the level of
cost, schedule, and technical risk associated with each WBS
A full explanation of DOE’s
guidance relative to risk
and uncertainty analysis
Analysis (method element. and contingency
and rigor of the 2. Analyze each risk for its severity and probability. allowances can be found in
analysis will vary 3. Develop minimum, most likely, and maximum ranges for Section 6.4.5 and more in-
depending on the
estimate level)
each risk element.
4. Determine type of risk distributions and reason for their use.
5. Ensure that risks are correlated.
depth treatment can be
found in DOE G 413.3-7A,
Risk Management Guide.
6. Use an acceptable statistical analysis method (e.g., Monte
Carlo simulation) to develop a confidence interval around
the point estimate.
7. Identify the confidence level of the point estimate.
8. Identify the amount of contingency funding and add this to
the point estimate to determine the risk-adjusted cost
estimate.
9. Recommend that the project or program office develop a risk
management plan to track and mitigate risks.
32 DOE G 413.3-21A
6-6-2018
GAO Best Practice GAO Cost Estimating Activities
Where Conformance to
GAO Practice is
Demonstrated in
DOE G 413.3-21
Step 10: Document Estimate documentation is
the Estimate 1. Document all steps used to develop the estimate so that a discussed in Section 3.2,
(method and rigor of cost analyst unfamiliar with the program can recreate it and extensively in Section
the analysis will vary quickly and produce the same result. 6.7.
depending on the 2. Document the purpose of the estimate, the team that
estimate level) prepared it, and who approved the estimate and on what
date.
3. Describe the program, its schedule, and the technical
baseline used to create the estimate.
4. Present the program’s time-phased life-cycle cost.
5. Discuss all ground rules and assumptions.
6. Include auditable and traceable data sources for each cost
element and document for all data sources how the data
were normalized.
7. Describe in detail the estimating methodology and rationale
used to derive each WBS element’s cost (prefer more detail
over less).
8. Describe the results of the risk, uncertainty, and sensitivity
analyses and whether any contingency funds were
identified.
9. Document how the estimate compares to the funding profile.
10. Track how this estimate compares to any previous
estimates.
Step 11: Present
Estimate to
Management for
1. Develop a briefing that presents the documented life-cycle
cost estimate.
Guidance related to the
presentation of estimate
results can be found in
Approval 2. Include an explanation of the technical and programmatic
baseline and any uncertainties.
3. Compare the estimate to an independent cost estimate (ICE)
and explain any differences.
4. Compare the estimate (life-cycle cost estimate (LCCE)) or
independent cost estimate to the budget with enough detail to
easily defend it by showing how it is accurate, complete, and
high in quality.
5. Focus in a logical manner on the largest cost elements and
cost drivers.
6. Make the content clear and complete so that those who are
unfamiliar with it can easily comprehend the competence that
underlies the estimate results.
7. Make backup slides available for more probing questions.
8. Act on and document feedback from management.
9. Request acceptance of the estimate.
Section 3.2.4, Section
6.7.1, and specifically in
Section 7.2.
DOE G 413.3-21A 33
6-6-2018
Section 24
GAO Best Practice GAO Cost Estimating Activities
Where Conformance to
GAO Practice is
Demonstrated in
DOE G 413.3-21
Step 12: Update
the Estimate to
Reflect Actual
Costs and
Changes (Projects
should update
estimates once
incurring actual
costs.)
1. Update the estimate to reflect changes in technical or
program assumptions or keep it current as the program
passes through new phases or milestones.
2. Replace estimates with EVM EAC and Independent estimate
at completion (EAC) from the integrated EVM system.
3. Report progress on meeting cost and schedule estimates.
4. Perform a post mortem and document lessons learned for
elements whose actual costs or schedules differ from the
estimate.
5. Document all changes to the program and how they affect the
cost estimate.
Estimate maintenance is
discussed in Sections 6.8
and 7.3, and more
extensively in DOE O
413.3B (requirements) and
other associated guidance
documents.
Sources: GAO-09-3SP, DOD, DOE, NASA, Society of Cost Estimating and Analysis (SCEA), Industry, DHS
6.2 Estimate Planning
Estimate planning (Input in Figure 2.1, Process Model) should include:
• Establishing when the estimate is required;
• Determining who will prepare the estimate;
• Producing a plan/schedule for estimate completion;
• Selecting and notifying individuals whose input is required;
• Collecting scoping documents;
• Selecting estimating technique;
• Conducting an estimate kickoff meeting; and,
• Visiting the work site.
Develop Estimate Purpose Statement—The purpose of the estimate should be stated in
precise, unambiguous terms. The purpose statement should indicate why the estimate is being
prepared and how the estimate is to be used. This should include a description of any relevant
regulatory or DOE drivers.
Prepare Technical Scope Summary—The technical scope summary should provide a detailed
description of the work included in the estimate. Additionally, the technical scope should
identify the activities included in the cost estimate as well as relevant activities excluded from
the cost estimate and the rationale for their exclusion.
Determine Approaches to be used to develop the Estimate—Develop the estimate using
techniques and methodologies such as the ones described in Section 5. For example, when
developing a detailed estimate, the following approach could be followed (among others):
• Activity-Based Estimates—Section 5.1 describes detailed estimating methodologies
used for preparing activity-based cost estimates. To be activity based, an estimate activity
should have discrete quantifiable units of work associated with it. Examples of work
34 DOE G 413.3-21A
6-6-2018
items that are activity-based include:
o Place 16 CY of concrete
o Produce 12 monthly reports
o Perform 100 surveillances
o Prepare a lesson plan for a course in safe lifting
• Level-of-Effort (LOE)—Certain activities cannot be associated with quantifiable units
of work. Instead, these activities should be expressed as a defined level of expenditure
over time. Estimates that include LOE activities should be closely scrutinized, and the
use of LOE estimates minimized. Examples of LOE activities include:
o Secretarial support
o Site safety program
o Clerical support
6.3 Cost Estimate Inputs
6.3.1 Sources of Data Input
Section 25
Since all cost estimating methods are data-driven, it is critical that the estimator know the best
data sources (Input in Figure 2.1, Process Model). Whenever possible, estimators should use
primary data sources. Primary data are obtained from the original source, are considered the best
in quality, and are ultimately the most useful. They are usually traceable to an audited document.
Secondary data are derived, rather than obtained directly from a primary data source. Since they
were derived (and thus changed) from the original data, they may be of lower overall quality and
usefulness. In many cases, data may have been “sanitized” for a variety of reasons that may
further complicate its use as full details and explanations may not be available. Cost estimators
must understand if and how data were changed before determining if they will be useful or how
that data can be adjusted for use. Furthermore, it is always better to use actual costs, rather than
estimates as data sources since actual costs represent the most accurate data available.
While secondary data are not the first choice, they may be all that are available. Therefore, the
cost estimator must seek to understand how the data were normalized, what the data represent,
how old the data are, and whether the data are incomplete. If these questions can be answered,
the secondary data should be useful for estimating and would certainly be helpful for cross-
checking the estimate for reasonableness.
Some specific sources of data are the following:
Estimating Manuals—The construction industry produces numerous costing manuals to assist
in the pricing of work. RSMeans and Richardson are two readily available manuals.
Data Bases—Commercial and in-house data bases provide the estimator with the ability to
retrieve data to be used for estimating. Commercial data bases are readily available. In-house
data bases more accurately reflect the parameters that influence local costs.
Vendor Quotes—Vendor quotes provide for a greater confidence of real time accuracy. Use
caution when using vendor quotes. Often the vendors provide quotes with either incomplete or
35 DOE G 413.3-21A
6-6-2018
preliminary information. Other times only one vendor is polled, possibly skewing the
information. In other situations, market conditions may drastically change from the time vendor
quotes were obtained.
Level of Effort Data—As discussed in Section 5.3.1, LOE activities are of a general or
supportive nature usually without a deliverable end product. Such activities do not readily lend
themselves to measurement of discrete accomplishment. LOE is generally characterized by a
uniform rate of activity over a specific period of time. Value is earned at the rate that the effort is
being expended. LOE activities should be kept at a minimum for Class 1 and 2 estimates.
Expert Opinions (Subject Matter Experts)—As described in Section 5.3.3, expert opinions
can provide valuable cost information in the early stages of a project, for Class 5, 4, and 3 cost
estimates. The data base should include a list of the experts consulted, their relevant experience,
and the basis for their opinions. If a formalized procedure was used, such as the Oracle Method,
it should be properly documented.
Section 26
Benchmarking—Benchmarking is a way to establish heuristics, or rules-of-thumb. Benchmarks
may be useful when other means of establishing reasonable estimates are unavailable. An
example of a benchmark is the statistic indicating that design should be 6 percent of construction
cost for non-complex facilities. If construction costs can be calculated (even approximately)
using a parametric technique, design should be approximately 6 percent. Typical benchmarks
include such rules as:
• Large equipment installation costs should be X percent of the cost of the equipment
• Process piping costs should be Y percent of the process equipment costs
• DOE facility work should cost approximately Z percent of current, local, commercial
work
Team/Individual Judgment Data—Team/Individual judgment data are used when the maturity
of the scope has not been fully developed and/or the ability to compare the work to historical or
published data is difficult. This involves the reliance of information on individuals or team
members who have experience in the work that is to be estimated. This process may involve
interviewing the person(s) and applying their judgment to assist in the development of the cost
estimate. Because of its subjectivity and usually the lack of supporting documentation,
team/individual judgment should be used sparingly.
Trend Analysis Data—As described in Section 5.3.4, trend analysis can provide data for
comparing the original planned baseline costs (or schedules) and the per unit value against actual
costs (or schedules) and the per unit value for work performed to date. Trend analysis data can be
used at almost any stage of work and can even be used as a basis for cost estimates developed
using other techniques.
The Learning Curve Data—As described in Section 5.3.5, learning curve data are useful for
understanding the efficiency of producing or delivering large quantities. Numerous sources are
available from trade associations and governmental organizations.
36 DOE G 413.3-21A
6-6-2018
6.3.2 Considerations for Cost Estimate Development
When given the task of developing an estimate, an estimator must first gather general project
information, including:
• Project background;
• Where the project stands in its life cycle;
• General description of the technical scope;
• Pertinent contract or sub-contract information;
• Estimate purpose, classification, how the estimate will be used, and techniques
anticipated; and,
• Approximate time frame for the work to be performed.
Some specific inputs to the cost estimating process include:
• Mission Need Statement;
• Critical Decision approval documents;
• Acquisition Strategy;
• Project Execution Plan;
• WBS;
• Code of Accounts (COA - also known as account code);
• Key Milestone Activities and Proposed Dates;
• Functional Design Criteria;
• Functional Performance Requirements;
• Conceptual Design Report;
• Preliminary Design;
• Definitive Design;
• Risk Analysis and Register;
• Historical Information and Other Sources of Information, including previous cost
estimates;
• Results of Alternative and Requirements Analyses;
• Applicable Resources and Labor Rates;
• Applicable Indirect Rates;
• Assumptions
o Estimate ground rules and constraints; e.g., 4 day work-weeks, 10 days of weather
shutdowns per year, site access limitations, acquisition strategies and associated
contractor markups, and all other assumed conditions under which the estimator
believes project work will be performed;
Section 27
o Assumptions made by the estimator to fill gaps and inconsistencies in the
technical scope, sources of materials;
• Estimate Allowances (see 6.4.2.3);
• Exclusions (a clearly stated list of excluded items such as furnishings, equipment,
finishes, landscaping, etc.);
37 DOE G 413.3-21A
6-6-2018
• Government Supplied Equipment; and,
• Construction and Operations Input.
From this information, whether provided by others or developed by the estimator as an
assumption, appropriate estimating techniques may be determined.
6.4 Cost Estimate Production
The principle step in the estimating process is producing the cost estimate and its corresponding
schedule and basis of estimate. It is important that scope development, documentation, and
control be coordinated with the cost estimate production as key iterative processes. Cost estimate
production includes several steps that should be based on requirements, purpose, use,
classification, and technique, including:
• Identify the scope of work;
• Identify the project, subprojects, milestones, activities, and tasks;
• Document all bases of the estimate, assumptions, allowances, risks, etc. during the
estimating process;
• Perform quantity takeoffs and field walk-downs;
• Develop the detail items or models that make up the activities;
• Assign measurable quantities to the detail items or models;
• Obtain budgetary or vendor information, conduct market research, or establish other
pertinent sources of information;
• Establish productivity rates or perform task analyses;
• Calculate all applicable costs, including direct costs, indirect costs, contingency, and
escalation (utilizing the schedule to calculate years for escalation);
• Produce all applicable detail and summary reports;
• Establish a funding profile utilizing the WBS and time phasing from the schedule;
• Determine what risks (and to what extent) should be mitigated with activities (or
assumptions) in the cost estimate; and,
Consider other inputs, including schedule information, risk management plan, and peer
reviews, as appropriate.
6.4.1 Schedule Development
A project plan and schedule should be developed as the main basis for any cost estimate. By
going through the process of schedule development, the activities needed to execute a project are
clearly identified and appropriately sequenced. This, then, forms a basis for estimating the
resources and costs needed to accomplish the project plan. That process in turn provides a basis
for estimating activity durations used to construct the schedule. As this process indicates, the
development of schedule and cost estimates is a highly iterative and inter-related process.
However, it is difficult to generate a credible and realistic cost estimate without at least a basic
understanding of the project plan and the activities that comprise the project schedule.
38 DOE G 413.3-21A
6-6-2018
After both the schedule and cost estimates have been developed, the project schedule is also used
to determine a cost estimate over time in order to calculate escalation, identify available
resources, and establish budget requirements. This process can result in further iteration, both to
refine the schedule (to accommodate resource and budget constraints) and to finalize the estimate
(to adjust escalation allowances and other time-based costs, e.g., management staffing).
A project’s schedule should not only reflect activities in a cost estimate, but it should also
indicate project milestones, deliverables, and relationships between activities.
Section 28
6.4.2 Direct Cost Development
Direct Costs include any costs that can be attributed solely to a particular project or activity,
including labor, materials, subcontracts, equipment, salaries, and travel. Emphasis is placed on
the term activity, which typically in standard practice equates to a lowest WBS element, account
code, work package, or planning package.
Commonly recognized direct costs include:
• Design, planning, and development;
• Project management;
• Construction management;
• Construction activities to include mobilization and de-mobilization, site work, concrete
work, masonry work;
• Operations labor, materials, equipment, subcontract costs, premium pay, and similar
productivity adjustments, such as those for contamination or security restrictions;
• Maintenance labor, materials, equipment, subcontract costs, premium pay, and similar
productivity adjustments, such as those for contamination or security restrictions;
• Routine and preventive maintenance activities include minor facility repairs or upgrades,
minor paving or landscaping;
• De-contamination, de-commissioning, dismantling, and demolition;
• Security escorts and restrictions;
• Special (capital) and standard (capital or non-capital) equipment;
• Freight, packaging, and transportation;
• Health physics support, radiological controls support, protective clothing/PPE, and
industrial safety/health; and,
• Sales and use taxes.
6.4.2.1 Resources and Crews and Quantities
Cost estimators should be familiar with any site or project-specific labor agreements, and if
applicable, reflect these labor agreements in the cost estimate.
Resources include the labor, material, equipment, services, and any other cost items required to
perform a scope of work. One or more resource can be assigned to an activity. A list of the
39 DOE G 413.3-21A
6-6-2018
resources and their associated unit prices needs to be defined before applying resources to
activities:
• Rates for labor should include wages, taxes, insurance, fringe benefits, overtime, and
shift differential as applicable;
• Unit prices for material should include the material price, sales tax, and shipping costs as
applicable; and,
• The hourly rate in cases involving equipment purchased by the Government should
include only operation and maintenance costs but not the capital cost of ownership since
the site may have some pre-arranged pool and the equipment rate should correspond with
current pool service rates.
Crews are groupings of the various labor classifications along with the tools and equipment (not
installed equipment) required to accomplish activities. A production rate/output for each crew is
identified. A crew used to place concrete slabs might include a foreman, laborers, cement
finisher, concrete vibrators, forms, and air compressor. In addition, the crew’s production
rate/output should be established (e.g., 110 cubic yards per day).
• Estimators should examine the production rate/output for each crew and make
adjustments for local conditions if necessary. Working with crews, rather than the
individual cost elements, allows the estimator to estimate work activities more quickly.
Quantities are the units of measure and number of units associated with each activity. Each
activity needs to have an identifiable unit of measure and a quantity associated with that activity
(e.g., 200 tons, 75 linear feet, etc.) For LOE activities, the quantity may be “one” and the unit of
measure “lot.”
Section 29
6.4.2.2 Assigning Resources to Activities
Detailed Work Scope. Once activities have been defined, units of measure identified, and
quantities determined, resources are assigned to each activity. Unit rates are used to assign
resources to estimate activities. The resources assigned should correspond with the resources that
will be used to complete the work. Such distinctions are especially important when detailed
schedules are required, but less important for ROM or conceptual estimates. Unit rates can be
expressed as dollars per unit, labor hours per unit, or a percentage of an associated cost.
Direct Labor. Unit rates expressed as labor hours per unit require that the type of labor
(carpenter, engineer, secretary, etc.) be identified by associating a labor type or a crew with each
unit rate. A crew is defined by the various labor types that make up the crew. Each labor type has
a corresponding wage rate to allow calculation of cost in dollars. If there is a contract already in
place, rates should be provided by the cognizant auditor. The wage rates for each labor type
includes the base rate, taxes and insurance, fringe benefits, travel or subsistence, and adjustment
for overtime, if required.
Percentages. Some activities may use percentages to assign resources. The appropriateness of
using percentages for such items as project management and construction management will
40 DOE G 413.3-21A
6-6-2018
depend on the level of maturity in the work scope definition. Examples of cost items where
percentages are often used include:
• Plan of the day (POD) meetings;
• Small tools;
• Consumable materials;
• Labor insurance;
• Project management; or,
• Construction management.
Regardless of the method used to assign resources to an activity, the following is true for each
activity; all costs are identified, labor hours, when applicable, are identified, and labor type for
all labor hours is identified.
Summary Work Scope. When details of the work scope are not known, the work scope may be
estimated by using the analogy technique or the parametric technique. These techniques may use
unit rates expressed as dollars per unit, labor hours per unit, or percentages.
Costs Included in Unit Rate. All costs should be “fully burdened.” A description of what is
included in the burdened rate should be included because the definition of “fully burdened”
frequently varies.
Unit Rate Adjustments. The development and/or use of estimating factors to adjust unit rates
require the skills of an experienced cost estimator. Such adjustments allow use of a database with
known productivity or costs, which are then adjusted to reflect the project specific activities and
the conditions under which the work is to be performed. Situations that might affect productivity
include type of work, weather conditions, level of confinement, security posture.
Examples of estimating factors (or unit rate adjustments):
• Add 25 percent to labor for work in radiation zones
• Reduce labor for shop work by 20 percent
• Add 20 percent to labor for work requiring use of a respirator
Estimating factors are available from published sources or estimators can develop them. For
example, the U.S. Army Corps of Engineers, “Productivity Study for Hazardous, Toxic and
Radioactive Waste (HTRW) Remedial Action Projects,” dated October 1994, provides suggested
labor productivity adjustment factors considering levels of worker protection and temperature.
6.4.2.3 Allowances
Section 30
In planning projects, it is normal to include allowances for activities for which there is little or no
design basis, especially in the earliest stages. These are not considered contingency costs.
Allowances should be included at the discretion of the Federal Project Director, project manager,
and IPT to cover anticipated costs associated with a known technical requirement or activity.
Any allowances included in cost estimates should include a basis for these costs within the
supporting Basis of Estimate (BOE) document.
41 DOE G 413.3-21A
6-6-2018
For instance, in a Class 5 cost estimate (order of magnitude), it would be appropriate to see a line
item (cost account or activity) such as “utility relocation, 1 lot, $1M material and $1M labor,”
indicating that some utilities needed to be relocated as part of this project. Documentation
supporting these costs should include approximate quantities, basis for those quantities, and
source of the projected costs (e.g., consensus of the project team) proportional to the significance
of the activity. Allowances also may be included in a project to cover costs associated with
productivity adjustments, anticipated subcontract changes, anticipated design changes, and
similar elements of known scope and costs.
6.4.2.3.1 Allowances for Special Conditions
Consideration must be given to all factors that affect a project or program. Some of these factors
are:
• Availability of skilled and experienced manpower and its productivity;
• The need for overtime work;
• The anticipated weather conditions during the period of performance;
• Work in congested areas;
• Working under the authorization basis;
• Work in radiation areas;
• Security requirements imposed on the work area;
• Use of respirators and special clothing;
• Training; and,
• Site access.
Special conditions may be estimated by applying a factor. For example, 10 percent applied to
labor hours for loss of productivity due to work in a congested area. Other items may be
calculated by performing a detailed takeoff. An example would be an activity that could only be
performed over a two-day period. Overtime would be required to complete the activity and the
number of hours and rates could be calculated.
An estimator should be vigilant that there is no duplication of costs—for example, if the control
account manager who provided the cost data to the estimator already included unit rate
adjustments such as productivity factors, additional allowances for productivity should not be
included or the cost estimate may be inflated. All allowances applied or used to develop the cost
estimate should be documented in the BOE.
6.4.2.4 Design Costs
To estimate design costs, the estimator should understand what activities are included. Typical
design-related activities include:
• Surveys (surveying), topographic services, core borings, soil analyses, etc., to support
design
• Preliminary and final design calculations and analyses
42 DOE G 413.3-21A
6-6-2018
• Design studies required to support safety analysis if not included in the Conceptual
Design Report
Section 31
• Building Energy Modeling
• Preparation of as-built drawings
• Travel to support design
• Acceptance procedures
• Outline specifications
• Reproduction during design
• Design Reviews (not third party)
• Construction cost estimates
• Design kickoff meeting
• Certified engineering reports
• Computer-Aided Drafting and computer services
• Constructability reviews
• Bid package preparation
• A/E internal design coordination
• Safety reviews by A/E
• Bid evaluation/opening/ award
• Design cost and schedule analyses and control
• Value engineering
• Inspection planning
• Design progress reporting
• Identification of long lead procurements
• Inspection services
• Regulatory/code overview by A/E
• Design change control
• Review shop drawings
• Procurement and construction specifications
• Modification of existing safety analysis report
• Preliminary and final plans and drawings
Design costs are normally directly related to the magnitude and complexity of a project. The
following factors should be considered when assessing design costs for the design-related
activities due to the magnitude and complexity of a particular project.
• Comprehensive functional requirements
• Off-site architecture/engineering
• Quality level
• Overtime
• Design planning
• Adequacy of plans and specifications
• Design layout
• Off-site fabrications
• Drafting and CADD methodologies
43 DOE G 413.3-21A
6-6-2018
• Travel and per diem
• Project reviews
• Guidelines
• Design reviews
• Performance specification
• Safety analysis requirements
• Cost estimating Activities
• Reporting requirements
• Inspection Requirements
• Government furnished equipment
• Schedule Analysis
• Complexity
• Labor density
For EM projects, the regulatory process requires rigorous examination of design alternatives
before the start of cleanup design, especially for remedial investigation/feasibility studies under
CERCLA to support a record of decision (ROD) or for corrective measure studies under RCRA
to support issuance of a permit. Cleanup design executes a design based on the method identified
in the ROD or permit, which often narrows the scope of preliminary design and reduces the cost
and schedule requirements.
On EM projects, the estimator should assess the extent to which design development is required
or allowed in cleanup design. In some cases, the ROD or permit will be specific, such as for a
disposal facility where all features such as liner systems and configuration, are fixed. When
treatment options such as incineration are recommended, considerable design effort may be
required.
Requirements for construction engineering, including observation, design of temporary facilities,
quality control, testing, and documentation, will often be higher than for conventional
construction because of requirements to comply with rigid regulations governing health and
safety, quality assurance and other project requirements.
6.4.2.5 Construction Management Costs
A construction management (CM) firm, whether in the form or a subcontractor or as a function
of an M&O contractor, is responsible for construction activities, including coordination between
prime contractors and subcontractors. This responsibility includes subcontracting, purchasing,
scheduling, and often a limited amount of actual construction. The cost estimate for this function
must include all CM costs for site management and force account labor wages, payroll taxes,
overheads, and procurements for which the CM is responsible.
Section 32
6.4.2.6 Project Management Costs
The estimates for project and program management must consider project duration from start of
preliminary design through completion of the construction for the project. Other factors to
44 DOE G 413.3-21A
6-6-2018
consider are the complexity of the project, the specific design group, the organization for which
the project is to be performed, and the extent of procured items. The encompassed functions
include:
• Management and integration;
• Program/project management;
• Administrative services;
• Peer review;
• Records management;
• Training;
• Information resources management;
• Project controls;
• Quality assurance;
• Licensing;
• Communications; and,
• Travel by management staff.
Management functions associated with environmental restoration projects parallel construction
project management.
6.4.2.7 Construction Coordination Costs
Construction coordination comprises field engineering services, sometimes called “Title III
Engineering” services or “Engineering Support during Construction”. Field engineers should be
involved in the review of the design documents, as well as in the coordination of field
construction and resolution of design conflicts encountered during the construction phase. Other
responsibilities may include furnishing and maintaining governing lines and benchmarks to
provide horizontal and vertical controls to which construction may be referred; checking and
approving or requiring revision to all vendor shop drawings to assure conformity with the
approved design, working drawings and specifications; inspecting the execution of construction
to assure conformance with approved drawings and specifications, and with established
requirements for workmanship, materials and equipment; and providing field or laboratory tests
of construction workmanship, materials and equipment as may be required.
6.4.2.8 Research and Development (R&D) Costs
Traditionally, cost estimating involves the use of historical cost data to correlate and validate
existing estimating methodologies. Historical cost data lend some accuracy and credibility to a
cost estimate. When a cost estimate is required for new, innovative, state-of-the-art, first, or one-
of-a-kind projects, historical data are not always available.
For these projects, knowledge of the processes involved should help the cost estimator to prepare
an accurate and credible cost estimate. In the absence of accurate cost information, process
knowledge can focus the estimator toward parts of the project that are significant contributors to
overall project cost.
45 DOE G 413.3-21A
6-6-2018
Personnel Costs—Personnel costs are usually the largest R&D expense. R&D personnel are
often well-educated and may have a correspondingly higher pay scale than personnel for
conventional projects. Personnel resources include those needed to construct R&D facilities;
purchase supplies, materials, and equipment; operate equipment, prototypes, pilot plants or
laboratories; develop software; information technology operations; and other labor functions
needed to complete R&D efforts.
Equipment Costs—Equipment costs for R&D projects can be divided into hardware (for
prototypes and pilot plants as well as other activities) and software costs (including computer
models discussed below). Hardware includes machinery, computers, and other technical
equipment. Equipment costs increase with increasing project complexity and a lengthy testing
and verification phase may be required. Vendor quotes can sometimes be obtained to support
early-stage cost estimates, but expert opinion is often the only recourse to obtain Class 5 cost
estimates for equipment with no precedent.
Section 33
Prototypes and Pilot Plants—In some instances, it will be cost effective to develop a prototype
or a pilot plant for an R&D project. A cost estimate for a prototype or a pilot plant will have to
account for the following major items:
• Procurement and/or construction of the equipment or plant
• Operation of the equipment, including necessary utilities
• Development of test criteria for plant studies
• Analysis of test results
• Computer simulation of plant processes
• Supplies and materials used for testing
The cost estimate may also need to include costs for project management and other personnel
during the pilot plant study or prototype testing.
Scaled and Computer Models—Scaled or computer-generated 3D models may need to be
created for some projects. For example, if the project goal is to construct a new incinerator for
mixed waste, site-specific air-dispersion modeling may be required to demonstrate that emissions
from the incinerator will not have an adverse impact on public health or the environment.
Groundwater modeling may be required for some remediation sites (e.g., groundwater
contamination has been found at a site, and several technologies are being proposed). Modeling
can be used to select the best technology or determine the optimum locations for equipment.
DOE regulations on energy efficiency performance standards require the use of whole building
energy simulation models in accordance with 10 CFR 433.15 Some models can be quite complex
and require specialized technical expertise.
15 Energy Efficiency Standards for New Federal Commercial and Multi-Family High-Rise Residential Buildings.
https://www.gpo.gov/fdsys/granule/CFR-2013-title10-vol3/CFR-2013-title10-vol3-part433/content-detail.html
https://www.gpo.gov/fdsys/granule/CFR-2013-title10-vol3/CFR-2013-title10-vol3-part433/content-detail.html
46 DOE G 413.3-21A
6-6-2018
R&D Disposition – Finally, it is important to consider the cost of disposing of all equipment,
chemicals, products, materials, facilities, etc., used during the R&D phase. The assumption that
another project will pay for the “cleanup” of an experiment, bench-scale demonstration or even a
pilot scale facility has often resulted in low initial government life-cycle estimates. The initial
government life-cycle estimate should consider the R&D disposition estimate attributable to the
project or share of the R&D disposition estimate when attributable to multiple projects.
6.4.2.9 Regulatory Costs
ES&H regulatory compliance is required for all projects thus, an estimate should contain
sufficient provisions for ES&H compliance costs. Regulatory costs should include the cost of
coordination and negotiation with regulators, documentation costs, site characterization analysis,
stakeholder meetings and other related activities.
For Government projects, the facility must satisfy all Federal, state, and local requirements (i.e.,
building permits, energy conservation and the Leadership in Energy and Environmental Design
(LEED) requirements16, waste disposal, wastewater effluent disposal, and air emission
limitations) imposed by the other agencies. Regulations are even more stringent for facilities that
process or store radioactive materials. Construction sites must follow Occupational Safety and
Health Administration (OSHA) rules.
Familiarity with applicable regulations is required so that a plan may be developed for the
project to comply with those regulations.
Environmental Compliance Costs
Section 34
The number and requirements of environmental regulations have increased dramatically in the
past 30 years. When preparing cost estimates for environmental compliance activities, the
following should be considered:
• Type of project;
• Project location;
• Waste generation;
• Effluent characteristics;
• Air emissions;
• Noise requirements; and,
• Project start-up or completion date.
Location significantly influences project costs when a wetlands area will be disturbed, or the
project is located in an area with extensive environmental regulations. Increased environmental
compliance costs should be factored into projects in such locations.
16 Energy conservation and LEED requirements in particular will require calculation of future building energy costs for new construction.
47 DOE G 413.3-21A
6-6-2018
Knowledgeable design staff and personnel familiar with environmental regulations that will
affect the project should be consulted when composing an estimate. Knowledge of wastes or air
emissions generated during the project will facilitate the identification of environmental
compliance design requirements and subsequent costs. For example, wastewater treatment may
be required prior to effluent discharge into a stream or publicly owned treatment works. Air
pollution control devices may be required for process equipment. Permitting costs could include:
• Labor for data gathering;
• Equipment for testing;
• Analytical tests;
• Data analysis and writing or completing documents;
• Time for interface with project personnel and outside consultants;
• Time for interaction and negotiation with regulator and stakeholders;
• Application and/or permit fees;
• Annual permitting costs;
• Upgrades to existing equipment; and,
• New pollution control equipment
Once a plan for regulatory compliance has been established, the regulatory costs can be
estimated. This will establish a baseline for the regulatory costs such that changes that affect the
baseline can be tracked and estimated throughout the project’s life.
For some projects, a permit is required before work can commence. For example, construction
projects that will disturb more than five acres are required to obtain a storm water permit before
commencing construction. Project scheduling can be affected if operating permits are not
received in a timely manner. Facilities may be shut down for violations of operating permits or
failure to comply with existing regulations. The time required for regulatory review of the permit
application also must be factored into the cost estimate.
Health and Safety Compliance Costs
Employee health and safety regulations have also increased. As allowable limits for worker
exposure decrease, design cost estimates must account for specific engineering controls to
minimize employee exposures to toxic or hazardous substances in the workplace, especially
for facilities with radioactive materials. Planning for environmental controls is essential
because retrofit costs can exceed original installment costs. State-of-the-art, high-
technology facilities may require initial employee exposure monitoring if unknown factors
are encountered. Protective equipment must also be supplied and maintained for the
employee.
Past experience with increased regulatory rigor within DOE has shown that the costs associated
with employee workspace controls, including industrial hygiene monitoring, is the most
significant cost factor in a rigorous health and safety program. The trend will probably continue.
Health and safety compliance issues may involve strict health and safety requirements, including
routine medical surveillance, preparation of health and safety plans, and employee training.
Section 35
48 DOE G 413.3-21A
6-6-2018
Employees may not be able to work 8 hours per day if daily personnel and equipment
decontamination is mandatory.
Other Regulatory Costs
In addition to the costs described above, there are quality assurance (QA) costs, security costs,
other ES&H requirements, project controls compliance costs, building energy modeling costs to
meet energy performance standards, and other standards or legal requirements that drives costs
the project must consider.
6.4.3 Indirect Costs
Indirect costs support common or joint objectives that do not link to a particular activity or
project. Indirect costs are “any costs not directly identified with a single final cost objective but
identified with two or more final cost objectives.” Consequently, IPTs should identify
opportunities to allocate indirect costs to an activity or asset based on direct cost elements, such
as labor hours, material cost, or both (see Section 6.4.3.1). No definitive criteria for determining
the appropriate cost type, direct or indirect, exists.
Some examples of indirect costs include:
• Facilities, operating equipment, small tools, and general maintenance;
• Temporary facilities (e.g., water, compressed air, and power);
• Motor pool, camp, and aircraft operations;
• Warehousing, transfer, and relocation;
• Safety, medical, fire protection, and first aid;
• Security;
• Administration, accounting, procurement, and legal;
• Personnel expenses, office supplies, and time reporting;
• Site-wide permits and licenses;
• Contributions to welfare plans and signup/termination pay; or,
• Contract fee/profit, bond costs (performance and material payment).
NOTE: Do not double count costs. For example, if acquisitions personnel are costed with
the pilot plant activity ensure that this person is not also included as part of Indirect Costs.
6.4.3.1 Indirect Rates
The development of indirect rates is usually the responsibility of both the financial accounting
organization and the cost estimator. Indirect rates should be developed in accordance with Cost
Accounting Standards. The financial accounting organization determines rates for organizational
overheads and general and administrative (G&A) cost, while the cost estimator usually estimates
rates for project management, construction management, and subcontract costs. If there is a
contract in place, the indirect rates are provided by the Contracting Officer (CO), obtained from
49 DOE G 413.3-21A
6-6-2018
the cognizant audit entity). The estimator, however, should clearly understand how to allocate all
indirect rates in the estimate to avoid duplication or omission, as well as document what each
indirect rate includes.
Indirect rates estimated for subcontract work such as design services, construction, and
remedial actions should be estimated and documented at a level of detail appropriate to the type
of cost estimate being prepared. There is no uniform standard for establishing indirect rates; a
typical method for applying indirect rates calculates indirect costs as a percentage of a category
of work. For example, quality control inspection could be estimated as 6 per cent of direct craft
labor, consumable materials at 6 percent of direct craft labor, and administrative support for
engineering at 38 percent of direct engineering, etc.
Section 36
The basis for applying individual indirect rates will vary greatly depending on the specific
costs included in the rate. Allowances for small tools or consumable materials would
typically use the direct labor cost of the appropriate construction craft, operations or
maintenance activities as its base. General and administrative cost is usually estimated using
the sum of all direct and indirect costs for the specific items of work as its base. Indirect rates
should be documented in detail so that what is included (and excluded) in each rate is clear.
A separate line item in the estimate should exist for each rate used.
6.4.4 Escalation
Escalation costs change continuously following changes in: such as technology, availability of
resources, and value of money (e.g., inflation).
Historical cost indices and forecast escalation indices have been developed to document and
forecast changing costs. The use of an established escalation index is required to consistently
forecast future project costs. To ensure proper use of an index, Estimators must understand its
basis and method of development.
Escalation is the provision in a cost estimate for increases in the cost of equipment, material,
labor affected by continuing price changes over time. Escalation may be: forecasted, to estimate
the future cost of a project based on current year costs; or historical, to convert a known
historical cost to the present.
Although the forecasted and historical escalation rates may be used in succession, most cost
estimating is done in current dollars and then escalated to the time when the project will be
executed. This section discusses the use and calculation of escalation and historical cost indices.
An example of the calculation and use of escalation can be found in Appendix E.
6.4.4.1 Forecasted Escalation Rates
Forecasted escalation rates may be obtained from commercial forecasting services, such as
Global Insight, which supplies its most current predictions using an econometric model of the
United States economy. The forecast escalation index is the ratio of the future value to the
current value expressed as a decimal.
50 DOE G 413.3-21A
6-6-2018
Forecasted escalation rates are simply the percentage change from one year to the next, typically
prepared for various groups, utilizing different sources of data. Because larger projects extend
over several years, it is necessary to have a method for predicting budgets that must be made
available in the future. This is where forecasted escalation rates are used. The current year cost
estimate is divided into components and then multiplied by the appropriate escalation rate to
produce an estimate of the future cost of the component. The future costs of these components
are then summed to give the total cost of the project.
To properly apply escalation, the following data are required:
1. Reference date the estimate was prepared and base date of costs;
2. Escalation index, or cumulative rates, to be used (including issue date and index); and,
3. Schedule, with start and completion dates of scheduled activities.
Escalation could be applied for the period from the date the estimate was prepared to the
midpoint of the performance schedule or the activity being escalated. There are many other more
detailed methods of calculating escalation, but care should be taken not to make this calculation
too complex. Remember, someone external to the project may need to review this calculation.
Regardless of the method used, the process should be well-documented.
Section 37
“Which comes first, contingency or escalation?” If a project includes a contingency that is
based on risks, and those risks have associated costs, this may imply use of the same base-year
dollars. And generally, performance periods can be associated with those risks within
components, so, escalation may be applied to contingency. However, if contingency is not easily
discernable by WBS element (or cost elements) or cannot be associated with a time period, it
may not be appropriate to escalate contingency. Also, the accuracy of an escalation forecast can
also be considered a risk, with appropriate cost impacts that are then included in contingency
allowances. The cost estimate should ultimately represent total escalated costs, or “then-year
dollars.”
6.4.4.2 Historical Escalation
Generally, historical escalation is generally easily evaluated. For example, the cost of concrete
increased between 1981 and 2002. The ratio of the two costs expressed as a percentage is the
historical escalation rate, or expressed as a decimal number is the historical cost index. Several
commercial historical cost indices are available.
To properly apply a historical cost index to make price more current, the following data are
required:
• An applicable historical cost index; and,
• The prior cost or price, with a reference date, such as an actual price for a known project
or a component. This cost or price may include direct material and/or labor cost, and it
should be known to what extent indirect costs (sales taxes, freight, labor burden, etc.),
overheads, and profit were included.
51 DOE G 413.3-21A
6-6-2018
6.4.4.3 Escalation Calculations
Most costs are estimated in “current dollars” and then escalated to the time when the work is
expected to be performed. The escalation rates are used for developing project performance
baselines. Rates should be evaluated for global, regional, and local conditions; should have a
maximum period of 1 year; and should be clearly documented including the basis.
The following are some suggested sources of major indices and escalation (recognized by
industry best practices):
• U.S. Department of Labor, Bureau of Labor Statistics, Inflation & Prices,
http://www.bls.gov/bls/inflation.htm;
• U.S. Department of Labor, Bureau of Labor Statistics, Contract Escalation,
http://www.bls.gov/bls/escalation.htm;
• Engineering News Record, Economics, http://enr.construction.com/economics/;
• RSMeans, Cost Books, https://rsmeans.com/CostBooks.aspx;
• The Richardson Construction Estimating Standards, http://www.costdataonline.com/;
• IHS Global Insight, http://www.ihsglobalinsight.com; and
• Office of Management and Budget Circular A-94, Guidelines and Discount Rates for
Benefit-Cost Analysis of Federal Programs,
https://www.whitehouse.gov/sites/whitehouse.gov/files/omb/circulars/A94/a094.pdf
6.4.5 Contingency
This section is compatible with the guidance provided in DOE G 413.3-7A, Risk Management
Guide, for the consistent use and development of Contingency and Management Reserve (MR)
in capital asset projects cost estimates. Contingency and MR are project cost elements directly
related to project risks and are an integral part of project cost estimates.
Section 38
The specific confidence level (CL) used to develop a project performance baseline estimate is
determined by the project’s FPD/IPT and approved by the Project Management Executive. The
project confidence level should be based on but not limited to the project risk assumptions,
project complexity, project size, and project criticality. At a minimum, it is recommended that
project performance baselines should be estimated, budgeted, and funded to provide a CL range
of 70 - 90 percent for DOE capital asset projects. FPDs should confirm with their program
sponsor whether additional guidance is to be provided. The CL for Major Items of Equipment
may be significantly different from the construction of conventional facilities that will house the
equipment. If a project has an approved performance baseline change, the FPD should consider
reanalyzing the risks at 95% CL or at a confidence level deemed appropriate for the project’s
size and complexity for budgetary requests and funding profiles to ensure project completion.
The DOE G 413.3-7A defines four categories of contingency, each of which is briefly described
below:
• DOE contingency budget is identified as funded contingency for use by the FPD.
Contingency is the risk based, quantitatively derived portion of the project budget that is
available for managing risks within the DOE performance baseline. At a minimum, it is
http://www.bls.gov/bls/inflation.htm
http://www.bls.gov/bls/escalation.htm
http://enr.construction.com/economics/
https://rsmeans.com/CostBooks.aspx
http://www.costdataonline.com/
http://www.ihsglobalinsight.com/
https://www.whitehouse.gov/sites/whitehouse.gov/files/omb/circulars/A94/a094.pdf
52 DOE G 413.3-21A
6-6-2018
recommended that DOE capital asset project costs should be estimated to provide a CL
range of 70-90%; the normal default is 80% at CD-2, to as high as 95% with a BCP.
• DOE schedule contingency is the risk-based, quantitatively derived portion of the overall
project schedule duration that is estimated to allow for the time-related risk impacts and
other time-related project uncertainties. It is recommended that project schedule
contingency should be estimated to provide a CL range of 70-90 percent.
• Contractor MR Budget is the risk-based quantitatively derived portion of the contract
budget base (CBB) that is set aside for management purposes to handle risks that are
within the contractor’s contractual obligations. Once the CBB has been established, it is
allocated to MR and the Performance Measurement Baseline (PMB). The MR is not
intended to justify a post contract increase to the CBB. MR is maintained separately from
the PMB and is utilized through the contractor’s change control process. MR is not used
to resolve past variances (positive or negative) resulting from poor contractor
performance or to address issues that are beyond the scope of the contract requirements.
Use of MR should follow EVMS rules as per EIA-748 (current).
• Contractor schedule margin is the risk-based quantitatively derived portion of the overall
contract schedule duration estimated to allow the contractor time to manage the time-
related impacts of contractor execution risks and other contractor duration uncertainties
within the contract period. Contractor schedule margin does not add time or schedule
duration to the contracted end date.
Section 39
The quantitative method used to analyze project contingency and MR should consist of objective
analysis of cost and schedule estimate uncertainties and discrete project risks. The analysis
should aggregate the probability and consequences of individual risks, and cost and schedule
uncertainties to provide an estimate of the potential project costs.
The quantitative risk analysis determines a risk-based project budget and completion date using
statistical modeling techniques such as Monte Carlo, Quasi-Monte Carlo, sensitivity simulations,
and other stochastic methodologies depending upon the project data.
While the Monte Carlo simulation is one standard used by DOE, alternate forms of quantitative
analysis may be used. Other recognized forms of quantitative analysis include: decision trees,
influence diagrams, system dynamics models, and neural networks. Figures 6-2 and 6-3 show the
typical components of the DOE project performance baseline.
53 DOE G 413.3-21A
6-6-2018
Figure 6-2. Total Project Cost Composition. Note: CL = Recommended Confidence Level
Figure 6-3. DOE and Contractor Budget Baseline
6.4.5.1 Quantitative Contingency Analysis
DOE O 413.3B requires that DOE project estimates be developed based on qualitative and
quantitative analysis of project risks and other uncertainties. The DOE qualitative and
quantitative analysis process begins in the project’s planning stage with the identification of
54 DOE G 413.3-21A
6-6-2018
project risks during the initial project planning phase prior to CD-0, Approve Mission Need.
After CD-0, project development and planning documentation are prepared that includes the
initial Risk Management Plan (RMP). During this phase of the project, development of the
project risk register is initiated with the identification of potential project risks and enabling
assumptions.
At CD-1, the baseline scope is refined enough to develop a preliminary baseline cost range and
schedule. The RMP continues to evolve as the project scope is refined, new risks are added to the
risk register and existing risks are re-examined and the project knowledge base increases.
In preparation for the CD-2, the performance baseline estimate is refined to include costs to be
incurred in executing the risk handling strategies. The baseline estimate is also evaluated, and
adequate contingency allowance incorporated, to determine the project budget needed to provide
an appropriate CL so that the project execution will be successful as defined in DOE O 413.3B.
This document assumes Monte Carlo methodologies will be used to develop the cost and
schedule baselines. The diverse and unique nature of DOE projects characterized by an
assortment of distinct technologies, physical locations, project duration, and project size has a
significant impact on the risk profile that makes it impossible to establish a prescriptive
procedure or single quantitative risk model for determining a project’s contingency needs.
Consequently, only a basic framework is used to outline considerations essential in the
development of DOE contingencies.
6.4.5.2 Cost and Schedule Risk Models
Contingency risk models are used to evaluate the probability and effects of risk impacts, and
estimate uncertainties on project cost and schedule performance baselines. The results of the risk
analysis are used to establish the cost and schedule contingency needed to provide a suitable
confidence level for DOE project success. The analyses may use one or more risk models to
evaluate the cost impacts and the associated schedule impacts.
Section 40
For each risk, a percent or percentage distribution is assigned to the probability (the likelihood of
the risk occurring), a dollar value or dollar value distribution is assigned to the cost impact, and a
schedule duration impact or schedule duration distribution is assigned to the affected activity in
the schedule.
In general the concept is implemented as:
EV = ∑PRi x CIRi (or SIRi)
Where: EV = Expected Value of cost impact (or duration impact) of all risks
PRi = Probability distribution function of a risk occurring
CIRi = Cost Impact distribution function of a risk occurrence
SIRi = Schedule Impact distribution function of a risk occurrence.
[Note: ∑ is not the summation of individual expected values for each risk, but represents a
stochastic process (e.g., Monte Carlo simulation) using the collective probabilities and
cost/schedule impacts for all identified risk events.]
DOE G 413.3-21A 55
6-6-2018
Figure 6-4 is a sample from a DOE construction project risk register showing the residual risk
data elements used for modeling the probability of occurrence (probability percentage) and the
triangular distribution representing a three-point estimate of the anticipated range of cost and
schedule impacts (the assumption in this example is of a triangular distribution of cost and
schedule impacts; other distributions can be used, such as step, rectangular, etc.).
Risk # Owner Risk Description
Residual Risk
Likelihood Consequence Risk
Score/Rank
Probability
(%)
Cost Impacts ($) Schedule Impacts (Days)
Best Case Most Likely Worst Case Best Case Most Likely Worst Case
T47 Federal
Nonperformance of contract to
provide shielded overpack
containers leads to project delays
and cost.
Unlikely Significant Moderate 40 850,000 3,000,000 6,000,000 0 0 0
T52 Federal
Overnight organizations interpret
requirements different than
implementation, leading to cost and
schedule impacts.
Likely Significant Moderate 60 -- 3,000,000 6,000,000 0 30 90
T12 Contractor
Failure of crane results in delayed
removal of canisters, impacting
schedule.
Unlikely Marginal Low 40 100,000 200,000 1,400,000 1 2 14
T61 Contractor Calibration services are unavilable causing shut down of operations. Very Unlikely Marginal Low 10 100,000 410,000 715,000 1 4 7
T266 Contractor
Hot cell cannot be designed to meet
active ventilation strategy increasing
design and construction costs.
Very Unlikely Critical Moderate 10 3,200,000 7,000,000 20,000,000 30 60 150
Figure 6-4. Sample Risk Register
The results of Monte Carlo analyses are generally summarized by a probability distribution
function (PDF) and a cumulative distribution function (CDF), as shown in Figure 6-5. The PDF
represents the distribution of the analytical model outcomes. As an example, the Monte Carlo
analysis may be designed to estimate the cost or duration of a project. The PDF represents the
number of times a certain cost or duration is achieved. The CDF is a statistical function based on
the accumulation of the probabilistic likelihoods of the analytical analysis. In the case of the
DOE risk analysis, it represents the likelihood that at a given probability the project cost or
duration will be at or below a given value. As an example, the x-axis might represent the range
of potential project cost values evaluated by the Monte Carlo simulation, and the y-axis
represents the project’s probability of success.
56 DOE G 413.3-21A
6-6-2018
PDF Curve
C
um
ul
at
iv
e
Pr
ob
ab
ili
ty
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
Section 41
CDF Curve
300 400 500 600 700 800 900 1000 1100 1200
Contractor Budget Base
100 %
95 %
90 %
85 %
80 % 800
75 %
70 %
65 %
60 %
55 %
50 % 600
45 %
40 %
35 %
30 %
25 %
20 % 500
15 %
10 %
5 %
305
Fr
eq
ue
nc
y
of
O
cc
ur
re
nc
e 244
183
122
61
0
Figure 6-5. Sample PDF and CDF Curves
An advantage of an integrated cost and schedule risk model is the ability to capture schedule-
related costs impacts, such as LOE support activities that increase project costs as schedule-
related risk impacts delay or extend work efforts. Ideally, the integrated risk model is based on a
life-cycle resource-loaded critical path schedule to which cost and schedule risks and cost and
schedule uncertainties are applied. Integrated risk models increase the flexibility of the risk
analysis and reduce the amount of manual coordination needed to model cost and schedule risk
impacts.
Project risks and the associated cost and schedule impacts are the primary inputs to the risk
model and are maintained within the project’s risk register. Figure 6-6 depicts a conceptual risk
model showing typical inputs and outputs.
Figure 6-6. Conceptual Risk Analysis Process
57 DOE G 413.3-21A
6-6-2018
An important consideration when identifying project risks is the careful analysis of the
assumptions upon which the cost estimate and schedule are predicated. Each assumption made
by the estimator, scheduler, or the project team should be analyzed by the IPT to determine if
there is a risk (threat or opportunity) that the assumption may not be valid or representative of
the actual conditions realized during project execution. In such cases, the probability of
alternative situations should be assessed and the impacts of those situations occurring should be
quantified and analyzed. These impacts can be an important element in both the cost and
schedule risk models and the determination of cost and schedule contingency allowances
appropriate for the project.
It should also be noted that Monte Carlo simulations are based on estimates of probability of
occurrence and estimated impacts when risk events do occur. As such, the quality of the output is
dependent on the quality and accuracy of these inputs. Inaccurate estimates of either probability
or impact will lead to erroneous project probability outputs and misstatement of needed
contingency allowances and/or CL.
Another issue that can lead to poor Monte Carlo analysis results is a failure to identify significant
project risks. Only if all significant risks are identified and properly evaluated can the Monte
Carlo model be expected to provide realistic forecasts of project outcomes and the contingency
allowances needed to achieve the desired CL.
6.4.5.3 Cost Risk Model
DOE capital asset projects should be estimated to provide a CL which is adequate to support
project success and reflects evaluation of all project risks, with reasonable estimates of cost and
schedule impacts. Risk models should include all risks (DOE, contractor and subcontractor
assumed risks). The risk cost model should provide an estimate of the performance baseline with
a CL range of 70 - 90 percent for success (recommended), which includes the contractor’s CBB,
profit/fee, and government contingency and other direct costs. The contractor MR is determined
by the contractor and represents the amount of the CBB that will be used for project management
purposes for accomplishing the work scope within the contractor’s PMB.
Section 42
When developing risk models, care should be exercised to assure the risk models are developed
using appropriate performance baseline information and project risk assumptions.
The recommended cost risk model should:
• Include all risks, especially significant risks;
• Use reasonable estimates of cost impacts;
• Include estimate uncertainties (cost and schedule) that are within the project baseline;
• Contain enough detail to allow identification of risk owners;
• Contain enough detail to allow project risks to be associated with the WBS they affect;
• Include a provision for uncertainty ranges in cost escalation rates for the project;
• Allow correlated risks that affect multiple cost elements, e.g., escalation rates, to be
modeled at a high level to preserve the dependent relationship among correlated risks;
• Include sufficient information to estimate costs associated with uncertainties in task
58 DOE G 413.3-21A
6-6-2018
durations consistent with the schedule risk model;
• Allow for inclusion of threats and opportunities; and,
• Allow risk impacts to be placed in the appropriate fiscal year to support the identification
of annual contingency budgeting and reporting requirements.
6.4.5.4 Schedule Risk Model
Schedule risk models should be based on the project performance baseline schedule. If practical,
the schedule risk model should be developed to include the schedule impacts of all risks that
impact the project, as well as any schedule duration uncertainties.
The recommended schedule risk model should:
• Include all significant risks;
• Use reasonable estimates of schedule impacts;
• Contain enough detail to allow identification of risk owners;
• Contain enough detail to distinguish among schedule activities that have different degrees
of schedule uncertainty and should include estimate uncertainties;
• Contain enough detail to allow specific risk events to be associated with the schedule
activity that they affect;
• Estimate the schedule impact on LOE activities so cost increases associated with
schedule slippages can be calculated and incorporated into the contingency estimates;
and,
• Allow for alterations in activity duration that result from implementation of risk handling
strategies or opportunities.
6.4.5.5 Sensitivity Analysis
The GAO-09-3SP, GAO Cost Estimating and Assessment Guide, states that, “As a best practice,
sensitivity analysis should be included in all cost estimates because it examines the effects of
changing assumptions and ground rules.” DOE endorses this best practice and believes it to be a
vital element and consideration when developing a cost estimate. Since uncertainty cannot be
avoided, it is necessary to identify what cost elements present the most risk and if, possible, cost
estimators should quantify the risk. Only when decision makers fully understand the results of
sensitivity analyses, combined with the results of the uncertainty and risk analyses, can they
ensure they made the best choices at either a programmatic or project level.
A sensitivity analysis “considers all activities associated with one cost estimate. If a cost estimate
can be sorted by total activity cost, unit cost, or quantity, sensitivity analyses can determine
which activities are cost drivers to answer the question: ‘If something varies, what most affects
the total cost of the project?’”17 A tailored analysis may be needed to avoid overly burdensome
or repetitive site wide impacts arising in lower level estimates down to the work package level.
Section 43
17 Project Management Glossary of Terms, Office of Project Management Oversight and Assessments, September 2014.
59 DOE G 413.3-21A
6-6-2018
Uncertainty about the values of technical parameters is common initially in design and
development and can result in inaccurate assumptions. Some examples of cost drivers that GAO
has identified18 include:
• A shorter or longer economic life • Testing requirements
• Volume, mix or pattern of workload • Changes in performance characteristics
• Potential requirements changes • Acquisition strategy
• Configuration changes • Labor rates.
• Higher or lower learning curves • Testing requirements
• Alternative assumptions • Down-scoping a project
To determine what the key cost drivers are, a cost estimator needs to determine the percentage of
total cost that each cost element represents. The major contributing variables within the highest
percentage cost elements are the key cost drivers that should be varied in the sensitivity analysis.
The cost practitioner should always include the assumptions that are most likely to change, such
as an assumption that was made for lack of knowledge or one that is outside the control of the
program or project office. The sensitivity analysis addresses some of the estimating uncertainty
by testing discrete cases of assumptions and other factors that could change. By examining each
assumption or factor independently, while holding all others constant, the cost estimator can then
evaluate the results to discover which assumptions or factors most influence the estimate.
It is important to understand and be able to communicate the potential impact from variations in
key assumptions and estimate cost drivers.
GAO recommends incorporating a five-step process that will result in a credible sensitivity
analysis:
Step 1. Identify key cost drivers, ground rules, and assumptions for sensitivity testing
Step 2. Re-estimate the total by choosing one of the identified cost drivers or assumptions
and varying it between two set amounts. The amounts chosen may represent
maximum and minimum, various performance thresholds, or alternative
assumptions; ranges should be documented during data collection and cost
estimating
Step 3. Document the results
Step 4. Repeat Steps 2 and 3 until all factors identified in Step 1 have been independently
tested
Step 5. Evaluate results to determine which drivers affect the cost estimate the most
To identify the key cost drivers and critical assumptions, there are several recommended
approaches:
• Research and appropriately reference historical data, industry benchmarks, and other
relevant data sources to determine the ranges of values a sensitivity analysis should
18 GAO Cost Estimating and Assessment Guide, CAO-09-3SP, Chapter 13 pages 147-150.
60 DOE G 413.3-21A
6-6-2018
consider. It is not a best practice to merely use arbitrary plus or minus values or other
approaches that do not have a sound basis. However, in the absence of relevant data, use
the expert opinion of suitably qualified subject matter experts.
• Examine the sub-elements or assumed values that contribute to the cost estimate value.
• Review all assumptions made and documented in the basis of estimate to isolate those
assumptions that seem most uncertain or most critical to the viability of the resultant
estimate.
Section 44
• Evaluate the results of the sensitivity output from the Monte Carlo simulation model that
assessed cost estimate uncertainty and risks when time permits. Visual output depicted
from “tornado charts” show the relative contribution of each simulation-model variable to
the final cumulative probability profile. It should be noted, however, that the elements
highlighted in such tornado charts may or may not be the most critical elements for a true
sensitivity analysis and usually do not represent an all-inclusive listing of such elements.
In summary, GAO best practices for sensitivity analysis necessitates satisfying the following
tests:
• The cost estimate was accompanied by a sensitivity analysis that identified the effect of
changing key cost driver assumption and factors:
o Well-documented sources that support the assumptions or factor ranges used in analyses;
o The sensitivity analysis was part of a quantitative risk assessment and was not based on
arbitrary plus or minus percentages;
o Cost-sensitive assumptions and factors were further examined to see whether design
changes should be implemented to mitigate risk;
o Sensitivity analysis was used to create a range of best- and worst-case costs;
o Assumptions and performance characteristics listed in the technical baseline description,
as well as ground rules and assumptions, were tested for sensitivity, especially those
assumptions and characteristics least understood or at risk of changing; and,
o Results were well documented and presented to management for decisions.
• The following activities were taken during the sensitivity analysis:
o Key cost drivers were identified;
o Cost elements representing the highest percentage of cost were determined and their
parameters and assumptions were examined;
o The total cost was re-estimated by varying each parameter between its minimum and
maximum range;
o Results were documented and the re-estimate was repeated for each parameter that was a
key cost driver; and,
o Outcomes were evaluated for parameters most sensitive to change.
• The sensitivity analysis provided a range of possible costs, a point estimate, and a method for
performing what-if analysis.
61 DOE G 413.3-21A
6-6-2018
6.4.5.6 Estimate Uncertainty
Estimate uncertainty is part of the risk analysis process for the development of contingency
estimates as was illustrated in Figure 6-6. Estimate uncertainties are fundamental contributors to
cost growth and are expected to decrease over time as the project definition improves and the
project matures. Estimate uncertainty is a function of, but not limited to, the quality of the project
scope definition, the current project life-cycle status, and the degree to which the project team
uses new or unique technologies. Estimate uncertainties occur throughout the DOE baseline. One
approach to account for estimate uncertainty is to use uncertainty ranges established by the
professional societies such as AACE International, Table 6-4, or other estimating guidance.
Estimate uncertainty contributes to both cost and schedule contingency.
Table 6-4 could be used for both cost and schedule estimate uncertainty and should be done
separately for evaluating quantitative impacts on project contingency.
Table 6-4. Estimate Uncertainty Range as a Function of Estimate Class
Class of Cost Estimate
Estimate
Uncertainty
(Low Range)
Estimate Uncertainty
(High Range)
Class 5 – Concept Screening -20% to -50% +30% to +100%
Class 4 – Study or Feasibility -15% to -30% +20% to +50%
Section 45
Class 3 – Budget Authorization -10% to -20% +10% to +30%
Class 2 – Control or Bid -5% to -15% +5% to +20%
Class 1 – Check Estimate -3% to -10% +3% to +15%
6.4.5.7 Determining Cost Contingency Amounts
A common method to evaluate risk model results is the use of CDF curves, also referred to as S-
curves. For a cost risk model, the S-curve represents the probability of completing the project at
or below a given project cost baseline. In this example the x-axis represents the range of
potential project cost values estimated by the Monte Carlo simulation and the y-axis represents
the probability of project success. Figure 6-7 illustrates two S-curves for a hypothetical project.
The S-curve on the left is based on the CBB and the S-curve on the right is for the DOE capital
asset project performance baseline and includes both the contractor and DOE risks.
Pr
ob
ab
ili
ty
o
f C
om
pl
et
io
n
at
a
gi
ve
n
Pr
oj
ec
t C
os
t
Based on
Contactor
Budget Base
80% CL Includes all
Contactor Execution Risks &
DOE Project Risks
62 DOE G 413.3-21A
6-6-2018
PPrrobaobabbiilliissttiicc PPrroojjeeccttiionon ofof CosCostt ususiinngg MMononttee CaCarlrloo AAnnaallyysseess
CBBCBB PBPB
Pr
ob
ab
ili
ty
o
f C
om
pl
et
io
n
at
a
gi
ve
n
Pr
oj
ec
t C
os
t
100%100%
90%90%
80%80%
70%70%
60%60%
50%50%
40%40%
30%30%
20%20%
10%10%
0%0%
Capital Asset Project CostCapital Asset Project Cost
Based on
Contactor
Budget Base
80% CL Includes all
Contactor Execution Risks &
DOE Project Risks
Figure 6-7. S-Curves of Contractor CBB and DOE Performance Baseline
6.4.5.8 Determining Schedule Contingency
The DOE schedule contingency is based on the same risks used in the development of the DOE
cost contingency. The DOE schedule contingency requirements should be analyzed using a
resource-loaded and logically tied schedule, so that impacts to overall schedule duration along
the critical path can be fully assessed. As risks and uncertainties are realized, the critical path for
the project may possibly change; the model needs to accommodate such situations.
Schedule activities that are affected by an identified risk or duration uncertainty are modeled in
the schedule risk analysis with an appropriate probability distribution. The calculation of
schedule contingency is an iterative process requiring an initial analysis of the schedule to
determine the base schedule contingency values followed by a revision of the schedule to adjust
work scope to meet the existing selected key milestones and deliverable dates.
DOE schedule contingency needs to be added to the overall critical path of the project. This can
be completed by applying the DOE schedule contingency incrementally before key milestones or
in total before the project completion date. In this way, forecasted completion dates (individual
milestones and/or overall project) can be established based on a probabilistic determination of
the expected completion date should project risks be realized. This differs from contractor
schedule margin, which cannot add time or schedule duration to the contracted end date.
63 DOE G 413.3-21A
6-6-2018
6.4.5.9 Risk Model Outputs
To support the required budgeting, management, and reporting requirements of the project, the
contingency analysis should provide the following:
• The contingency analysis models should be able to produce a PDF and a CDF for the
project
• The contingency analysis models should be able to produce a PDF and a CDF for each
selected milestone
Section 46
• The models should be capable of performing a sensitivity analysis for project cost and
schedule elements. Risk analysis sensitivity results are typically presented as tornado
diagrams that provide an analytical and visual representation of risk event impacts
• Ideally, the model should place resulting contingencies in a time frame to allow for fiscal
year budgeting of DOE contingency. Figure 6-8 illustrates how contingency budget
projections can be depicted
Figure 6-8. Contingency Budget Projection
6.4.5.10 Unknown-Unknowns
Because there may not be viable means to quantify certain “unknown-unknowns”, IPTs may not
be expected to set aside contingency for them. Unknown-unknowns could be major schedule
changes or unknown design factors, unanticipated regulatory standards or changes, additions to
project scope definition (changes outside a project’s intended scope), force majeure situations, or
http:6.4.5.10
64 DOE G 413.3-21A
6-6-2018
program budget reductions. These may be considered programmatic risks, which could be
applicable to all projects within a respective specific Program.
However, there should be clear communication between the project team and their sponsoring
Program to communicate and agree to the bounding assumptions for the project. Furthermore,
Programs are advised to include appropriate allowances for programmatic contingencies (for
risks and events that occur outside project space but that may in fact impact on project execution)
in their overall portfolio budgets.
6.4.5.11 Contingency Adequacy Evaluation
Numerous tools exist to analyze the adequacy of the contingency valuation that has resulted from
the qualitative and/or quantitative analysis of the risks. Various costs estimating guidance
documents have been compiled by industry and are available in texts and journals (e.g., AACE
International), and are updated on a regular basis. These references provide percent ranges of the
base that a contingency should represent in order to be considered adequate. Further, the
contingency value should be commensurate with the maturity and type of the project, project
size, and risks, including technical and technology uncertainties. It should be cautioned that the
recommended contingency levels in these documents do not provide a basis for the
recommended confidence levels (70 – 90 percent) in this Guide for the derivation of contingency
and management reserve by quantitative risk analysis.
If a quantitative risk analysis will not be conducted, estimates for cost and schedule contingency
should be provided. As a general rule, the IPT should use various inputs to determine those
values. Those inputs may be, but should not be limited to:
• Historical records (considering actual costs and time impacts for certain events);
• Subject matter experts;
• Delphi techniques;
• Interviews of staff, crafts, retirees, and others familiar with similar work activities at the
site or similar sites; and,
• Technical records such as safety analysis documents including the risk and opportunity
assessment, quality assessments, and environmental assessments.
As the information is gathered and finalized, the data should be analyzed for bias and perception
errors. While the data will not be systematically used for a quantitative analysis, it should still be
analyzed and perceptions scrutinized.
6.5 Cost Estimate Review
Section 47
Cost estimates should be reviewed for quality and reasonableness before release. Reviews can be
either objective, subjective, or a combination of both. As a minimum, all estimates should
address the review criteria listed in Appendix D.
DOE cost estimates, and the BOEs that support them, should include an assessment of the
realism and reasonableness of the primary cost elements comprising the cost estimate. Such
http:6.4.5.11
65 DOE G 413.3-21A
6-6-2018
an assessment evaluates the relative percentages of the total proposed cost baseline and the
underlying BOE for each of the significant cost elements. Additionally, primary cost drivers
within the estimate consistent with a product oriented WBS, should be identified and
compared to established benchmarks for similar items or activities.
Such efforts will facilitate independent reviews of cost estimate reasonableness by competent
qualified personnel who have not been involved in preparing the estimate. This review should
provide an unbiased check of the assumptions, productivity factors, and cost data used to
develop the estimate. An independent cost review is a vital step in providing consistent,
professionally prepared cost estimates (Step 7, GAO 12 Key Steps Development Process,
GAO-09-SP). The review should be documented to indicate:
• The name of the reviewer(s) – Office/Agency/Contractor it belongs
• The date of the review
• Review comments and comment disposition
6.6 Estimate Reconciliation
Reconciliation may be necessary to account for changes made between CDs or other life-cycle
project milestones. Reconciliations should be organized by WBS and cover all aspects of project
documentation (cost estimate, basis of estimate, schedule, and risks). In general, reconciliation
should recognize or focus on specific changes in scope, basis of estimate, schedule, and risks.
There should be an understanding that, as time progresses, more and better information is
expected to be available and used as project or cost estimate documentation. Reconciliations are
necessary to mitigate budget shortfalls and may be used to correct deficiencies identified during
internal or external reviews.
6.7 Cost Estimate Documentation
A well-documented estimate is one of GAO’s best practices for high-quality cost estimates for
the following reasons:19
1. Complete and detailed documentation is essential for validating and defending a cost
estimate.
2. Documenting the estimate in detail, step by step, provides enough documentation so that
someone unfamiliar with the program/project could easily recreate or update it.
3. Good documentation helps with analyzing changes in program costs and contributes to
the collection of cost and technical data that can be used to support future cost estimates.
4. A well-documented cost estimate is essential if an effective independent review is to
ensure that it is valid and credible. It also supports reconciling differences with an
independent cost estimate, improving understanding of the cost elements and their
differences so that decision makers can be better informed.
19 GAO-09-3SP
66 DOE G 413.3-21A
6-6-2018
Documentation should be organized into an indexed repository, either physical or digital, with a
document control plan and, preferably, a documentation engineer/administrator. To the extent
practical, the documentation index should be consistent with the WBS for the project for ease of
reference.
6.7.1 Cost Estimate Package
Section 48
A cost estimate package or report should be prepared for all cost estimates. Each estimate
package should contain the same categories of information and the same types of
documentation; only the level of detail in the estimate package varies. The contractor in
coordination with the IPT determines the format used to present this information. A cost
estimate package or report supporting baselines, management decisions, and budgetary
documents should include the following information. A graded approach to cost estimate
packaging and reporting should be used when documenting cost estimates for other purposes.
• Estimate Purpose Statement—the reason the estimate was prepared including
- Determine the estimate’s purpose
- The level of detail required
- Determine who will receive the estimate
- Identify the overall scope of the estimate.
• Technical Scope Summary—summary of the technical scope of the project
including what is included in the project as well as what is not included.
• Qualifications and Assumptions—the key project qualifications and cost
assumptions that provide a “bounding” of the estimate and scope. Specifically, the
assumed condition under which the estimator believes the project work scope will be
performed should be defined. The qualifications and assumptions may describe the
types of work expected, the amount of work expected, the source of various materials,
conditions in which the work is to be performed (winter, contaminated building, etc.),
and any other information that significantly influences the estimate but is not clearly
identified in the technical scope description. Major assumptions and exclusions that
affect the project or the accuracy of the estimate are also described. Concrete
examples of scope assumptions include, but are not limited to changes in the seismic
criteria, safety criteria, materials, method of construction, siting, orientation,
construction methods assumed, and open air versus enclosed D&D.
In completing this activity, the estimator should identify areas where work scope
descriptions have deficiencies, or where key information is missing and has to be
assumed. Vital information concerning the project is also identified for those
reviewing or using the estimate.
Qualifications and assumptions should be described and documented at the most
detailed level practical, and they should be clearly described so an individual not
intimately involved with the project can understand the estimate’s basis.
67 DOE G 413.3-21A
6-6-2018
• Overall Basis of Estimate—the dollar amount indicated in a cost estimate is
meaningless without understanding the quality of information that led to developing
the estimate. With all estimates, the basis is communicated at a higher level in a
summary document and at a more specific level within the estimate.
Include in the estimate package a high level summary explaining the genesis for the
source information for the estimated resources and a breakdown of cost estimate
basis. For example, a breakdown may indicate that 30% is vendor quote, 20%
engineering judgment, 30% historical data, and 20% cost database/cost books.
The basis should also describe the design basis, the planning basis (significant
features and components, proposed methods of accomplishment, and proposed
project schedule), the risk basis, supporting research and development requirements
(important when new technologies are contemplated for certain components,
equipment or processes), special construction or operating procedures, site conditions,
the cost basis, and any other pertinent factors or assumptions that may affect costs.
Section 49
If the estimate is prepared in support of another formal document that addresses these
issues (i.e., a Conceptual Design Report or definitive design document), separate
documentation is not required but reference to the original documentation must be
made. If the estimate is a standalone document, or deviates substantially from a
previous estimate scope, the above issues should be addressed and included in the
estimate basis.
• Estimate Summary and Detail Reports—a presentation of the estimate details in a
variety of ways (e.g., sorted by labor type, by WBS etc.)
• Technical Scope Detail—a statement of the details of the technical scope necessary
for a thorough understanding of the work. This may be by reference to specific
technical documents.
• Estimate Specific WBS and WBS Dictionary—a decomposition of the organization
and related cost estimates.
The initial basis for any cost estimate should be documented at the time the estimate
is prepared. The basis should describe or reference the purpose of the project
element, the design basis, the planning basis (significant features and components,
proposed methods of accomplishment, and proposed project schedule), the risk
basis, supporting research and development requirements (important when new
technologies are contemplated for certain components, equipment or processes),
special construction or operating procedures, site conditions, the cost basis, and any
other pertinent factors, assumptions, or inclusions that may affect costs.
If the estimate is prepared in support of another formal document that addresses these
issues (i.e., a Conceptual Design Report or definitive design document), separate
documentation is not required. If the estimate is a standalone document, or deviates
68 DOE G 413.3-21A
6-6-2018
substantially from a previous estimate scope, the above issues should be addressed
and included in the estimate basis.
At the WBS level, include quantities, applicable rates and costs. Also, include sources
of information, such as historical costs, industry standards, published price lists; cost
databases, informal budgetary information, cost estimating relationships, etc. for the
WBS.
At the WBS level, include the resource and Crew Listing—a listing of the type of
resources used in the estimate.
• Method and Justification for Use of Indirect Rates—an explanation of how
indirect rates were selected and applied.
• Method and Justification for use of Allowances—an explanation of how
allowances were determined and applied.
• Method and Justification for use of Escalation—an explanation of the escalation
rates used, how they were obtained, why they were selected and how they were
applied.
• Schedule—a time-frame for the work to assist in understanding how escalation was
applied. The schedule should reflect the same technical scope and cost as the
estimate.
• Risk Register—discusses sources of risk and uncertainty, including critical
assumptions, associated with the estimate. Identifies major risks within the scope of
work and how those risks are mitigated. The basis for contingency reserves and how
they were calculated is fully documented.
• Sensitivity Analysis—describes the effect of changing key cost drivers and
assumptions independently. Identifies the major cost drivers that should be closely
monitored.
• List of Participants—lists contacts for questions about the estimate. Estimate
preparers and reviewers should be identified in the cost estimate documentation.
Section 50
• Documentation of Review and Approval—demonstrates that the estimate was
reviewed and approved.
• Location of Estimate Files and Reference Information—identifies the locations
copies of the estimate, review the original, and review information that was not
included in the estimate package. The cost estimate package should include
documentation providing the location of the estimate, historical data, technical scope,
worksheets and any other pertinent information used to prepare the estimate.
69 DOE G 413.3-21A
6-6-2018
• Documentation of Changes to the Estimate—clarifies how and where the estimate
was changed, eliminating the need to review the entire estimate. Cost estimates
should be updated or modified as necessary. Updates should be promptly documented
when significant changes occur.
6.7.2 Cost Classification
A specific definition of items to be included as direct costs and indirect costs should be
included at the discretion of the DOE program offices and field offices and/or determined by
their contractor’s financial system. This would also apply to activities under either Other
Project Costs (OPC) or Total Estimated Cost (TEC) (refer to DOE O 413.3B for definitions
and requirements for these terms as they apply to projects).
It is important to assure that there is no double counting of costs estimated as direct, indirect,
or overhead. Generally, all cost estimates should include:
• Direct costs
• Indirect costs
• Contingency
• Escalation
6.8 Estimate Maintenance
It is important to maintain estimates over the life cycle of the project or program. For projects,
the cost estimate is a key element in establishing the Performance Baseline, as depicted in
Figures 6-2 and 6-3. The project cost performance baseline consists of a project’s TPC, which
includes various contract prices, non-contract costs, profit/fee, and contingency.
Project baselines in turn are key elements of overall program planning and budgeting,
including portfolio management. As projects are identified and defined, and the cost estimates
and baselines evolve, they become key inputs into the management of the program’s life cycle.
This may involve multiple projects and/or operational activities (e.g., construction of facilities
to treat waste, decommissioning of treatment facilities, waste management, surveillance and
maintenance). As such, active maintenance of all estimates is essential – they need to reflect
the latest and most realistic projections of cost and resource requirements to facilitate effective
program planning.
The need to make changes to a cost estimate generally results from determining that the
estimate no longer accurately portrays the expected cost for the work. The means to formally
control changes to a cost estimate are dependent on the purpose of the estimate. Estimates
supporting project baselines must be changed and approved through a formal baseline change
process (refer to DOE O 41.3.3B, Appendix A, Section 6, Baseline Management).
Changes require documentation, and as each estimate is updated, modified, or revised, an audit
trail must be maintained to show the relationship between the new estimate and the previous
estimate. The reason(s) for each change should be identified and may include such things as
70 DOE G 413.3-21A
6-6-2018
modification of scope, unexpected increases in labor rates, schedule extensions, variance in
escalation rates, project reprioritization, etc. All such changes should be identified in a manner
that will permit verification of the specific quantitative change(s) in the cost estimate.
Section 51
Changes may be documented by the use of addenda, officially approved change request
documents, or by completion of a new estimate. The method used depends upon the magnitude
of the estimated change and the underlying causes. All estimate changes should include the
appropriate level of indirect costs, escalation, and allowances, as dictated by the phase of the
project when the change was identified.
The process of officially revising and updating cost estimates supporting project baselines
frequently involves the use of change requests. Change requests are the official means by
which all changes to the cost baseline should be documented. Change requests are prepared
using standard contractor procedures and forms, which describe proposed changes to approved
technical, cost and/or schedule baselines.
As work is authorized to proceed, cost estimates inform budget development. There is a
distinction between cost estimates and budget allocations. The cost estimate provides the
expected cost while the budget forms the basis for measuring work execution over time. If the
cost changes due to scope changes, funding profile changes, or other drivers, the cost estimate
may need to be updated to support development of a new budget.
7.0 COST ESTIMATING OUTPUTS
This Guide defines traditional output from the Cost Estimating Process. Outputs include, the
traditional change control process, economic and cost-benefit analysis, value engineering,
earned-value, and final project cost reports.
7.1 Cost Estimate Interfaces
Cost estimate development is initiated into a process through one-time or iterative inputs.
Potential one-time inputs may include (but are not limited to) the project charter, project
execution plan, acquisition strategy, and acquisition plan. All of these are inputs to the cost
estimating process.
Other inputs may evolve through the cost estimating process and use the outputs from the cost
estimating process, such as the risk assessment (primarily risk identification and impact
assessment), schedule, and scope development. Input from cost estimating peers may improve
the quality of a cost estimate, and peer reviews should be required before external reviews are
conducted.
The cost estimate output provides a key interface to other project processes, including the
planning/scheduling, project control, risk management, and project approval processes.
71 DOE G 413.3-21A
6-6-2018
7.2 Presenting the Estimate to Management
Cost estimates are a primary input into the DOE decision-making and project approval CD
process. A cost estimate is not considered valid until DOE management has approved it. Since
many cost estimates are developed to support a DOE budget request or make a decision between
competing alternatives, it is vital that a high quality cost estimate be intentionally planned to
anticipate management concerns and inspire confidence in the desired outcome.
The preferred presentation format is designed to allow management to gain confidence in the
practitioner’s cost estimating process and the estimate itself:
1. Cost practitioner should initially convey how the estimate was developed, including risks
associated with the underlying data and methods. The presentation should contain enough
detail for easy defense as to why the estimate is credible, well-documented, accurate and
comprehensive.
Section 52
2. The presentation should be clear and complete, making it easy for those unfamiliar with
the estimate to comprehend its level of competence. The presenter should focus on the
key cost drivers and the final cost estimate’s outcome. Slides with visuals should be
available to answer more probing questions. A GAO best practice is to provide the
presentation in a consistent format to facilitate management’s understanding the
completeness of the cost estimate, as well as its high quality. A decision maker who is
familiar with the presentation format is better able to concentrate on the presentation’s
content, and on the cost estimate, rather than focusing on the format itself.
3. Results should be communicated succinctly to fortify management confidence in the
ground rules, methods, and results and in the process that was followed to develop the
estimate. The presentation must include program and technical information specific to the
program, along with displays of budget implications, contractor staffing levels, and
related industrial base considerations. The following elements are recommended for
inclusion in the presentation:
• Title page, presentation date and the name of the person(s) receiving the
presentation;
• Estimate purpose – why it was developed and what approval is needed;
• A brief program overview – its physical and performance characteristics and
acquisition strategy, sufficient to understand its technical foundation and
objectives;
• Estimating ground rules and assumptions;
• Copies of the cost estimate both at the detail level and rolled up WBS level;
• LCCE time phased in constant-year dollars and tracked to any previous estimate;
• For each WBS cost element, show the estimating method for cost drivers and high
value items;
• Show a breakout of cost elements and their percentage of the total cost estimate to
identify key cost drivers;
72 DOE G 413.3-21A
6-6-2018
• Sensitivity analysis, interpreting results carefully if there is a high degree of
sensitivity;
• Discussion of risk and uncertainty analysis, including:
(1) cost drivers, the magnitude of outside influences, contingencies, and
the confidence interval surrounding the point estimate and the
corresponding S curve showing the range within which the actual estimate
should fall;
(2) other historic data for reality checks; and,
(3) how uncertainty, bounds, and distributions were defined;
• Comparison to an independent cost estimate, explaining differences and results;
• Comparison of the budget needs or LCCE, expressed in current-year dollars, to
the funding profile, including contingency reserve based on the risk analysis and
any budget shortfall and its effect;
• Concerns or challenges the audience should be aware of;
• Conclusions, recommendations, and associated level of confidence in the
estimate; and,
• When presenting LCCEs to management, the presenter should include separate
sections for each program phase—research and development, procurement,
operations and support, disposal—and should provide the same type of
information as the cost estimate documentation contains. In addition, the
presentation should provide the summary information, main conclusions, and
recommendations first, followed by detailed explanations of the estimating
process.
4. Cost practitioner should conclude the presentation by asking management to formally
accept the cost estimate. Acceptance, along with any feedback from management, should
be acted on immediately and documented in the cost estimate documentation package.
Section 53
7.3 Baselines and Change Control
Cost estimates are normally organized by a WBS, account code, and/or some other standardized
definition. Standard definitions of direct and indirect costs provide consistency in estimating
costs and project reporting. This also benefits program/project management, independent
estimates (Government estimates), reviews, and contract/project validations and cost/price
analysis. The cost portion of the performance baseline consists of a project’s TPC, including
various contract prices, non-contract costs, and contingency.
As projects evolve, baselines are established and changes are managed against those baselines.
Cost estimates supporting proposed or directed changes should contain the same level of quality
as the primary baseline cost estimate.
Baselines are expected to remain intact throughout the project execution from approval at CD-2
to completion at CD-4. Changes are expected to remain within the performance baseline as per
the definition of a successful project at CD-4 in DOE O 413.3B. Cost estimates for the baseline
project are modified (updated) when changes are approved.
73 DOE G 413.3-21A
6-6-2018
7.4 Analysis
Analysis includes decomposition and examination. In many cases, analysis will provide insight
to a decision maker. Such is the case of cost benefit analysis. Cost-benefit analysis is a required
element in capital planning within the Federal government. Note that cost analysis and price
analysis have different meanings. This Guide focuses on cost analysis.
Analysis could be performed in the life of a project, including cost benefit analysis, cost-
effective analysis, economic analysis, LCC analysis, sensitivity analysis and uncertainty analysis.
Analyses supporting CDs should be structured and formal; i.e., well documented. Other analyses
may be loosely structured and informal.
Normally, analyses require using similar cost estimate structures (i.e., separate cost estimates for
each alternative considered); having all costs for all alternatives depicted; and comparing
alternatives using net present value or annuities. Normally a written summary of the findings is
also prepared to explain the analysis.
More information on cost estimating and analysis can be found through the Society for Cost
Estimating and Analysis (SCEA) at http://www.sceaonline.org/.
More information on cost engineering can be found through AACE International, at
http://web.aacei.org/
8.0 COST ESTIMATING EXPECTATIONS
8.1 Summary of Expectations
A DOE cost estimate, regardless of purpose, classification, or technique employed, should
demonstrate sufficient quality to infer that it is appropriate for its intended use, is complete, and
has been subjected to internal checks and reviews. It should also be clear, concise, reliable, fair,
reasonable, and accurate, within some probability or confidence levels. In addition, it should
follow accepted standards such as the GAO 12 steps of a high quality cost estimating process
(GAO-09-3SP) in accordance with other guiding DOE policy. There could be more expectations,
depending on the program, project, contract type, specific budget requirements, or other
situations.
Section 54
Organization of some cost elements may be specified (e.g. resources, material, other direct costs,
and sub-contract costs). These coded costs facilitate development of management information
and earned value assessments, and can provide extremely useful information as projects are
completed. Industry standard codes are exemplified by the Construction Specifications Institute’s
Uniformat II and Masterformat, for construction projects. The environmental cost element
structure (ECES), an ASTM standard for environmental projects, is another common coding
structure. Project data sheets (PDSs) for budget formulation and other coding formats should be
produced, according to program office requirements.
More information on the Uniformat II can be found at http://www.uniformat.com/
http://www.sceaonline.org/
http://web.aacei.org/
http://www.uniformat.com/
74 DOE G 413.3-21A
6-6-2018
More information on the Masterformat can be found at http://www.masterformat.com/
More information on the ECES can be found at
https://www.emcbc.doe.gov/Office/ProjectManagement
More information on OMB’s Exhibit 300 forms can be found in OMB A-11, Part 7 at
https://www.whitehouse.gov/omb/circulars_a11_current_year_a11_toc
8.2 Lessons Learned
Lessons learned from experience are essential to structuring increasingly more accurate cost
estimates. A reasonable expectation of a cost estimating process is that it systematically collects
historical project information in real time, rather than being done at the last minute or by trying
to recollect long after the fact.
Historical cost information can be collected as lump sum (representing some specific scope of
work), unit cost, or productivity (hours per unit, or units per hour) information. Historical costs
should be collected for analysis, normalization, and use in future project cost estimates. Lessons
learned that can help cost estimators with future cost estimates may be generic in nature or
specific to a site, location, contract type, etc. They may apply to a particular scope of work or a
cost estimating technique. There are many ways to communicate lessons learned. The point is to
document what has been learned from the experience and share it with others, as appropriate.
8.3 Independent Cost Estimates and Cost Reviews
The following requirements are described in DOE O 413.3B:
Prior to CD-0, for Major System Projects, or for projects as designated by the CE, PM will
conduct an Independent Cost Review (ICR).
Prior to CD-1, for projects with a TPC ≥ $100M, PM will develop an Independent Cost Estimate
(ICE) and/or conduct an ICR, as they deem appropriate.
Prior to CD-2, for projects with a TPC ≥ $100M, PM will develop an ICE. The ICE will support
validation of the Performance Baseline (PB).
Prior to CD-3, for projects with a TPC ≥ $100M, PM will develop an ICE.
In addition to the specific requirements placed on PM in DOE O 413.3B, a project may be well-
served by having its own cost estimate completed at various points in the development and
execution of the project, no matter the size of the project (for projects less than $100M).
Comparison to an ICE is a key element in Step 7 of the GAO Best Practices.
All ICRs and ICEs should be developed by individuals or organizations that are truly
independent of the project. This may be accomplished by issuance of contracts or task orders by
http://www.masterformat.com/
https://www.emcbc.doe.gov/Office/ProjectManagement
https://www.whitehouse.gov/omb/circulars_a11_current_year_a11_toc
Section 55
75 DOE G 413.3-21A
6-6-2018
PM, through another DOE direct contract vehicle, or directly by other DOE organizations.
However, it may not be generally appropriate for the project proponents (i.e., a DOE site office,
a DOE program office, or a DOE contractor) to conduct, or to contract for, and direct an ICE or
ICR development.
In general, the types of reviews that DOE normally recognizes (the types of reviews may be
modified/combined by the size, technology and complexity of the project) are the following:
Documentation Review—this type of review is not normally accomplished as an ICR/ICE, nor
does it fulfill the requirements as specified in DOE O 413.3B, since it only consists of an
assessment of the documentation available to support the estimate. It is merely an inventory of
existing documents to determine that the required support documentation exists and to identify
any missing data. This type of review can be beneficial for a project team facing an upcoming
EIR or ICE, to ensure readiness to proceed with those activities.
Reasonableness Review—this equates to the ICR as required in DOE O 413.3B.
For this review, the ICR team reviews all available project documentation, receives briefings
from the project team, holds discussions with the project team, completes sufficient analysis to
assess the reasonableness of the project assumptions supporting the cost and schedule estimates,
ascertains the validity of those assumptions, assesses the rationale for the methodology used, and
checks the completeness of the estimate, including appropriate allowances for risks and
uncertainties. The result is a report that details the findings and recommendations.
Parametric Estimating Approach—this approach, in addition to incorporating all of the
activities needed for a Reasonableness Review, uses parametric techniques, factors, etc., to
analyze project costs and schedules, and is usually accomplished at a summary WBS level. The
parametric techniques (including CERs and factors) should be based on accepted historical
cost/schedule analyses. At a minimum, these tools should be based on historic estimates from
which models have been derived, and, where possible, from actual completed projects. An
estimate with a minimum of 75 percent of the TPC based on parametric techniques is classified
as a parametric estimate.
Sampling Approach—this review also begins with the activities needed for a Reasonableness
Review, but it also requires the ICE team to identify the key cost drivers. A “cost driver” is a
major estimate element whose sensitivity significantly impacts TPC. Detailed, independent
estimates should be developed for these cost drivers. Such estimates should include vendor
quotes for major equipment, and detailed estimates of other materials, labor, and subcontracts.
For the balance of the project costs, the project team’s estimate may be used (if deemed
reasonable), or, if appropriate, parametric techniques may be used for certain portions of the
project costs. An estimate which provides a detailed cost for all cost drivers is classified as a
Sampling Estimate.
Bottom-up Estimating Approach—this is the most detailed and extensive ICE effort. It begins
with the activities needed for a Reasonableness Review. In addition, this approach requires a
detailed bottom-up independent estimate for both cost and schedule. This will require quantity
take-offs/development, vendor quotations, productivity analysis, use of historical information,
Section 56
76 DOE G 413.3-21A
6-6-2018
and any other means available to do a thorough and complete estimate of at least 75 percent of
the project’s cost. It may not be possible to do a completely independent estimate on some
portions of the project estimate, and for those portions – which should not exceed 25 percent of
the total estimate – the project estimate may be used if it has passed the test of reasonableness. In
all cases, the total cost (TEC and TPC) should be developed.
ICEs will often involve a combination of the approaches and techniques described above, due to
the varying levels and quality of information available. The accuracy of the ICE will be
subjectively determined based on the weighted evaluation of the information available.
A key element of any ICE is a comprehensive reconciliation between the ICE and the
project team estimate. Such reconciliation identifies areas of significant difference between the
estimates and attempts to explain those differences. This information provides a useful basis for
subsequent estimate (cost range or baseline) approval or identification of necessary estimate
revision and refinement.
DOE G 413.3-21A Appendix A
6-6-2018 A-1 (and A-2)
(
Appendix A: Acronyms and Definitions
A/E Architect/Engineer
AACE AACE International
ANSI American National Standards Institute
AS Acquisition Strategy
ASTM American Society for Testing Materials
BOE Basis of Estimate
CD Critical Decision
CER Cost Estimating Relationship
CFO Chief Financial Officer
CFR Code of Federal Regulations
CM Construction Management
CO Contracting Officer
DoD Department of Defense
DOE Department of Energy
EIR External Independent Review
ES&H Office of Environment, Safety, and Health
EVMS Earned Value Management System
FPD Federal Project Director
FTE Full-Time Equivalents
GFE Government-Furnished Equipment
ICE Independent Cost Estimate
ICR Independent Cost Review
IGCE Independent Government Cost Estimate
IPT Integrated Project Team
LEED Leadership in Energy and Environmental Design
LCC Life-Cycle Cost
LOE Level of Effort
NPV Net Present Value
NNSA National Nuclear Security Administration
OMB Office of Management and Budget
PM Office of Project Management
PME Project Management Executive
PMB Performance Measurement Baseline
R&D Research and Development
TEC Total Estimated Cost
TPC Total Project Cost
VE Value Engineering
WBS Work Breakdown Structure
Refer to DOE Project Management Terms and Acronyms, for additional information.
https://community.max.gov/x/TYFUQw
http://www.energy.gov/sites/prod/files/2014/10/f18/DOE%20APM%20Glossary%20of%20Terms%20Handbook_FINAL_Sep_30_2014.pdf
https://community.max.gov/x/TYFUQw
DOE G 413.3-21A Appendix B
6-6-2018 B-1
Appendix B: Summary of Federal Requirements
Summary of Requirements
Generally, Federal requirements are promulgated by:
• Office of Management and Budget (OMB), which provides specifics for budgeting,
discount rates, and management of projects (acquisitions) in their circulars;
• The Federal Acquisition Regulation (FAR), which provides Federal contract
requirements for government estimates, cost and price analyses, and contract changes;
• The Code of Federal Regulations (CFR), which provides requirements for alternative
considerations and life-cycle cost analyses; and,
• Various other Federal laws, such as the Government Performance and Results Act
(GPRA), the Government Management Reform Act, the Federal Acquisition Reform Act,
the Federal Acquisition Streamlining Act, the Information Technology Management
Reform Act, the Chief Financial Officers Act (CFO Act), and others.
Section 57
These Federal laws and policies drive the way DOE conducts business. DOE’s Directives
Management System is the means by which departmental policies, requirements, and
responsibilities are developed and communicated. Directives are used to inform, direct, and
guide employees in the performance of their jobs and enable employees to work effectively
within the Department and with Agencies, contractors, and the public.
The most significant, relevant DOE Orders include:
• DOE O 130.1, Budget Formulation, dated 9-29-95.
• DOE O 413.3B, Chg4, Program and Project Management for the Acquisition of Capital
Assets, dated 10-13-2017.
• DOE O 430.1C, Real Property Asset Management, dated 8-19-16.
• DOE O 520.1A, Chg 1, Chief Financial Officer Responsibilities, dated 11-21-06.
• DOE O 534.1B, Accounting, dated 1-6-03.
This section includes a summary of Federal requirements stemming from Office of Management
and Budget (OMB), the Code of Federal Regulations (CFR), Federal Acquisition Regulation
(FAR), and Public Laws (P.L.) that drive DOE requirements for cost estimating relative to
capital asset acquisitions and real property.
OMB Circular No. A-11, Preparation, Submission, and Execution of the Budget, Appendix J,
Principles of Budgeting for Capital Asset Acquisitions and the Capital Programming Guide,
provides the framework to guide Federal agencies through the process of formulating a
cost-benefit analysis and ultimately the budget submission for Federal agency projects and
programs. Major capital investments proposed for funding must:
• Support Agency missions;
Appendix B DOE G 413.3-21A
B-2 6-6-2018
• Support work redesign to cut costs and improve efficiency and use of off-the-shelf
technology;
• Be supported by a cost-benefit analysis based on both qualitative and quantitative
measures;
• Integrate work processes/information flows with technology to achieve strategic goals;
• Incorporate clear measures to determine not only a project’s success, but also its
compliance with a security plan;
• Be acquired through a strategy that allocates the risk between the Government and the
contractor and provides for the effective use of contracting; and,
• Ensure that the capital plan is operational and supports the Information Resource
Management (IRM) strategic plan.
OMB Circular No. A-94, Guidelines and Discount Rates for Benefit-Cost Analysis of Federal
Programs (October 29, 1992), provides an analytical framework for capital planning and
investment control for information technology investments. The circular provides the
information necessary to complete a thorough review of an IT investment’s financial
performance. Requirements include:
• Evidence of a projected return on investment in the form of reduced cost; increased
quality, speed, or flexibility; and improved customer and employee satisfaction; and,
• A cost-benefit analysis for each information system throughout the life cycle that
describes:
o Level of investment;
o Performance measures; and,
o A consistent methodology with regard to discount rates for cost benefit analyses
of Federal programs.
10 CFR 436, Subpart A, Methodology and Procedures for Life-Cycle Cost Analyses, establishes
methodology and procedures for estimating and comparing the life-cycle costs of Federal
buildings, determining the life-cycle cost effectiveness of energy and water conservation
measures, and rank-ordering life-cycle cost effectiveness measures in order to design a new
Federal building or to retrofit an existing Federal building. It also establishes the method by
which efficiency shall be considered when entering into or renewing leases of Federal building
space.
Section 58
In accordance with GAO-09-3SP, Chapter 5, “A life-cycle cost estimate is a best practice
because it provides an exhaustive and structured accounting of all resources and associated cost
elements required to develop, produce, deploy, and sustain a program. As such, a life-cycle cost
estimate should encompass all past (or sunk), present, and future costs for every aspect of the
program, regardless of funding source. Life-cycle costing enhances decision making, especially
in early planning and concept formulation of acquisition. Design trade-off studies conducted
during this period can be evaluated on a total cost basis, as well as on a performance and
technical basis. A life-cycle cost estimate can support budgetary decision, key decision points,
milestone reviews, and investment decisions. Because they encompass all possible costs, life-
cycle cost estimates provide a wealth of information about how much programs are expected to
cost over time.”
DOE G 413.3-21A Appendix B
6-6-2018 B-3
Chief Financial Officers (CFO) Act of 1990 (P.L. 101-576)
Section 902(a) lists the CFO’s regular duties, including:
• Develop and maintain an integrated Agency-accounting and financial management
system, including financial reporting and internal controls, which:
o Comply with applicable accounting principles, standards, and requirements and
internal control standards;
o Comply with such policies and requirements as may be prescribed by the Director
of OMB;
o Comply with any other requirements applicable to such systems;
o Ensure information is complete, reliable, consistent, and timely, which is prepared
on a uniform basis and which is responsive to the financial information needs of
Agency management;
o Development and reporting of cost information;
o Integration of accounting and budgeting information; and,
o Systematic measurement of performance.
• Direct, manage, and provide policy guidance and oversight of Agency financial
management personnel, activities, and operations, including:
o Preparation and annual revision of an Agency plan to (i) implement the 5-year
financial management plan prepared by the Director of OMB under section
3512(a)(3) of this title and (ii) comply with the requirements established under
sections 3515 and subsections (e) and (f) of section 3521 of this title;
o Development of Agency financial management budgets;
o Recruitment, selection, and training of personnel to carry out Agency financial
management functions;
o Approval and management of Agency financial management systems design or
enhancement projects; and,
o Implementation of Agency asset management systems, including systems for cash
management, credit management, debt collection, and property and inventory
management and control.
The CFO Act also set requirements for submission of annual financial statements and annual
external audits.
Government Performance and Results Act (GPRA) of 1993, P.L. 103-62, establishes the
foundation for budget decision making to achieve strategic goals in order to meet Agency
mission objectives. GPRA provides for the establishment of strategic planning and performance
measurement in the Federal government.
GPRA changes the way the Federal government does business, changes the accountability of
Federal managers, shifts organizational focus to service quality and customer satisfaction, and
improves how information is made available to the public. GPRA states that an organization’s
mission should drive its activities. Furthermore, GPRA states that the final measure of Federal
program effectiveness and efficiency is results, and it requires organizations to measure their
results through stated goals. It requires the development of annual performance plans and
Section 59
Appendix B DOE G 413.3-21A
B-4 6-6-2018
Agency strategic plans. It requires a return on investment that equals or exceeds those of
alternatives.
Federal Managers’ Financial Integrity Act (FMFIA) of 1982 (P.L. 97-255), as codified in 31
U.S.C. 3512, requires accountability of financial and program managers for financial results of
actions taken, control over the Federal government’s financial resources, and protection of
Federal assets.
Paperwork Reduction Act of 1995 (P.L. 104-13) requires that Agencies perform their
information resource management activities in an efficient, effective, and economical manner.
Federal Acquisition Streamlining Act of 1994 (P.L. 103-355) requires Agencies to establish
cost, schedule, and measurable performance goals for all major acquisition programs and
achieve, on average, 90% of those goals. OMB policy for performance-based management is
also provided in this section.
Clinger-Cohen Act of 1996 (P.L. 104-106) requires Agencies to use a disciplined capital
planning and investment control process to acquire, use, maintain, and dispose of IT. The spirit
and intent of Information Technology Management Reform Act (ITMRA)20 directs Agencies to
ensure that IT investments are improving mission performance by:
• Establishing goals to improve the efficiency and effectiveness of Agency operations and,
as appropriate, the delivery of services to the public through the effective use of
information technology;
• Ensuring that performance measurements assess how effectively the information
technology supports programs of the executive agency;
• Quantitatively benchmarking processes in terms of cost, speed, productivity, and quality
of outputs and outcomes where comparable processes and organizations in the public or
private sectors exist;
• Analyzing the missions of each executive agency and, based on the analysis, revising the
executive agency’s processes as appropriate before making significant investments in
information technology; and,
• Ensuring that the information security policies, procedures, and practices of the executive
agency are adequate.
20 The DAU Glossary provides more information on the Clinger-Cohen Act and ITMRA. https://dap.dau.mil/glossary/pages/2041.aspx
https://dap.dau.mil/glossary/pages/2041.aspx
DOE G 413.3-21A Appendix B
6-6-2018 B-5 (and B-6)
Table B-1. Relevant Cost Estimating and Earned Value Legislation and Regulation
Applicable Agency Name of Legislation or Regulation
All Federal agencies Government Performance and Results Act (GPRA) of 1993 (Among other things,
GPRA requires agencies to prepare multiyear strategic plans that describe mission
goals and methods for reaching them. The act also requires agencies to prepare
annual program performance reports to review progress toward annual performance
goals.)
All Federal agencies Clinger-Cohen Act of 1996 (Among other provisions, this law requires agencies to
base decisions about Information Technology (IT) investments on quantitative and
qualitative factors associated with the costs, benefits, and risks of those investments
and to use performance data to demonstrate how well the IT expenditures support
improvements to agency programs.)
All Federal agencies Federal Acquisition Regulation (FAR) Major System Acquisition, 48 CFR part 34,
subpart 34.2, Earned Value Management System (EVMS)
Source: GAO and DOD
Table B-2. Relevant Cost Estimating and Earned Value Policy
Section 60
Applicable Agency Name of Policy
All Federal agencies Office of Management and Budget (OMB) Circular No. A-11, Preparation,
Submission, and Execution of the Budget, July 2017
All Federal agencies Office of Management and Budget (OMB) Circular No. A-94, Guidelines and
Discount Rates for Benefit-Cost Analysis of Federal Programs, 10-29-92
All Federal agencies Office of Management and Budget (OMB) Circular No. A-109, Major Systems
Acquisitions, April 5, 1976
All Federal agencies Office of Management and Budget (OMB) Memorandum for Chief Information
Officers, No. M-05-23, Improving Information Technology (IT) Project Planning and
Execution, August 4, 2005
All Federal agencies Office of Management and Budget (OMB) Capital Programming Guide, Supplement
to Circular A-11, Part 7, Preparation, Submission and Execution of the Budget, 2011
Source: GAO, OMB, and DOD
DOE G 413.3-21A Appendix C
6-6-2018 C-1 (and C-2)
Appendix C: Summary of DOE Requirements
There are several DOE Orders that reference cost estimating. Among them, the primary DOE
Orders are:
• DOE O 130.1, Budget Formulation, dated 9-29-95, establishes the processes for
developing, reviewing, and exchanging budget data. DOE O 130.1 requires that budget
formulation be performance based, supportive of the DOE strategic plans, measurable,
verifiable, and based on cost estimates deemed reasonable by the program and field
offices.
• DOE O 413.3B, Program and Project Management for the Acquisition of Capital Assets,
updated 10-13-2017, originally approved 11-29-10, promotes the systematic acquisition
of projects and emphasizes the necessity for managing successful projects. DOE O
413.3B defines the Critical Decision process, which establishes protocol, authorities, and
consistency between the DOE programs.
• DOE O 430.1C, Real Property Asset Management (RPAM), dated 8-19-16, establishes a
corporate, holistic, and performance-based approach to real property life-cycle asset
management that links real property asset planning, programming, budgeting, and
evaluation to program mission projections and performance outcomes. The
implementation of RPAM maintains requirements for cost estimates and Life Cycle Cost
Analysis (LCCA). RPAM also includes DOE’s requirements of the Facilities Information
Management System (FIMS) and the Condition Assessment and Information System
(CAIS). These systems require cost estimate information concerning replacement plant
values (RPVs) and facility maintenance costs.
• DOE O 520.1A, Chief Financial Officer Responsibilities, dated 11-21-06, promotes the
achievement of the objectives of the CFO Act (sound financial management policies and
practices, effective internal controls, accurate and timely financial information, and
well-qualified financial managers) by setting forth the functions, organizational roles, and
specific financial management responsibilities of the CFO, the field CFOs, and other
appropriate DOE officials.
• DOE O 534.1B, Accounting, dated 1-6-03, designates the requirements and
responsibilities for the accounting and financial management of the DOE. Requirements
include, but are not limited to establishing a single, integrated financial management
system that serves program management, budgetary, and accounting needs so that DOE
and integrated contract records contain sufficient details in accounting for all DOE funds,
assets, liabilities, and costs.
DOE G 413.3-21A Appendix D
6-6-2018 D-1
Appendix D: Generic Review Criteria
Section 61
When reviewing DOE cost estimates, this generic criterion is suggested as a minimum. All
criteria should be addressed to be complete, and if all criteria are reasonably addressed, then the
estimates represented may be considered of quality, reasonable and as accurate as possible. The
estimates should also have been prepared by following the GAO 12 steps for a High Quality
Estimating Process (GAO-09-3SP) as recommended in this Guide.21
Work Breakdown Structure (WBS) - A WBS should be consistent between the technical
definition, cost estimate, and schedule. The use of a common WBS should be considered for
consistency between projects within a program WBS. Use of a standardized code of accounts is
also recommended.
Scope of Work - A scope of work should be commensurate with the planning, phase, size and
complexity of the project and should be activity based to the most practical extent.
Direct and Indirect Costs - All direct costs should be included appropriately, and rates applied
as percentages—including contract indirect and overhead rates or site indirect rates. They should
be documented and referenced in the basis of estimate. Indirect rates should be defined for
consistent application and appropriate for a given project.
Escalation - Escalation should be included appropriately. The rates applied should have
documented basis. Escalation is the provision in a cost estimate for increases in the cost of
equipment, material, labor, etc., due to continuing price changes over time. Escalation is used to
estimate the future cost of a project or to bring historical costs to the present.
Contingency - Contingency should be included appropriately, based on apparent project risks or
project risk analysis to the most possible extent. In any event, contingency should have a
documented basis. Contingency may be calculated using a deterministic or probabilistic
approach, but the method employed should be appropriate and documented.
Contingency is an amount included in an estimate to cover costs that may result from incomplete
design, unforeseen and unpredictable conditions, or uncertainties. Contingency should also be
commensurate with risk—a factor, element, constraint, or course of action in a project that
introduces the uncertainty of outcomes and the possibilities of technical deficiencies, inadequate
performances, schedule delays, or cost overruns that could impact a Departmental mission. In the
evaluation of project risk, the potential impact and the probability of occurrence should be
considered.
Contingency is most significant and appropriate for long-term projects and most order of
magnitude and preliminary estimate classes with significant size and complexity. Contingency
may be less significant for nearer term projects with less significant size and complexity.
21 GAO-09-3SP, Chapter 15, Validating the Estimate
Appendix D DOE G 413.3-21A
D-2 6-6-2018
Techniques - Cost estimating techniques employed should be appropriately based on estimate
class and purpose, available technical information, time constraints, and compliance with
planning, project size and complexity. The chosen techniques should facilitate systematic cost
estimate duplication or verification.
Basis of Estimate Documentation - Documentation that should describe how an estimate,
schedule, or other plan component was developed, and defines the information used in support of
development. It should explain the origins and logic of all WBS elements. A basis document
should commonly include a description of the scope, methodologies, references and defining
deliverables, assumptions and exclusions, clarifications, adjustments, and level of uncertainty.
Section 62
Cost Estimate Documentation - Cost estimate documentation should be easily discernable,
traceable, and consistent. As a matter of great relative importance, cost estimate documentation
should be very thorough (provided to the most possible extent). In most cases, documentation
should be specific for a given project (or sub-project) and should be centrally maintained to
assure technical/cost/schedule consistency, management focus, and ease of reference.
Cost Estimate Updates - Cost estimate updates should be considered and included, as
appropriate, to reflect new information, given a project planning phase and/or execution.
Previous versions of cost estimates should be appropriately considered, whether considering
information contained in a previous estimate supporting a critical decision, a potential change to
a project/contract/budget, or a value engineering study.
Life-Cycle Costs - Life-cycle costs should be appropriately included in estimates. Life-cycle
cost estimates are most pertinent during the decision-making phases of a project’s life, or when
LCC analyses (comparison of life-cycle cost estimates or VE Studies) are performed, but should
also be considered throughout a project’s life. Life-cycle costs should include: start-up costs,
operating costs, manufacturing costs, machining costs, research and development costs,
engineering costs, design costs, equipment costs, construction costs, inspection costs, and
decommissioning costs, as well as direct costs, indirect costs, overhead costs, fees, contingency,
and escalation costs.
Qualified Cost and Schedule Estimators - Cost and schedule estimators, cost engineers, and
risk managers should join the integrated project team and begin engaging with the project early.
Cost estimates should be performed and documented by those qualified to do so. Professional
cost and schedule estimators, and cost engineers are trained in the use of cost estimating tools,
techniques, and all aspects of estimating, project control, and project management.
DOE G 413.3-21A Appendix E
6-6-2018 E-1
Appendix E: Example of the Calculation and Use of Economic Escalation
Economic cost escalation should be included in all estimates where TPC may be affected by
inflation or increases in unit costs. Following are the steps in calculating escalation amounts.
Step 1 – Finalize the estimate cost in “current dollars” and develop a corresponding schedule
estimate. Ensure that the cost and schedule estimates are organized by a common WBS.
Step 2 – Determine the midpoint of primary scheduled activity groups (e.g., design, construction,
construction management, start-up, etc.)
Step 3 – Select appropriate escalation rates by using the estimate preparation date (“today”) as
the index date for determining the rates. The rates are ideally based on documented information
for the worksite location, but alternative rates provided by DOE/HQ may be used in the absence
of appropriate local information.
Step 4 – Calculate the estimate of escalation for each scheduled activity grouping by applying
the rates selected in Step 3 to the midpoint dates determined in Step 2. A straight-line spending
curve application may be assumed, although other spending curves may be used, as appropriate.
To illustrate the application of escalation calculations, the following is an example of a five-year
project. The Tables E-1 through E-4 present the stages necessary for calculating cost escalation.
Note that major activity groupings defined as “scheduled activity.”
Section 63
Table E-1. Escalation Example - Step 1, Sample Project Cost Estimate Summary
Represents the Estimate Summary Prior to Adding Cost Escalation
WBS Scheduled Activity
Total
Base
Cost
(000$)
Start Duration
(Months) Complete Midpoint
A1A Preliminary Design (Title I Design) 100 10/1/12 6 3/30/13 1/1/13
A1B Definitive Design (Title II Design) 200 4/1/13 6 9/30/13 7/1/13
A1C Design During Construction (Title III
Design) 100 10/1/13 36 9/30/16 7/1/15
B2A Equipment Procurement (General Services) 200 10/1/14 24 9/30/16 10/1/15
B2B Equipment Procurement (Long-Lead, GFE) 2,500 3/30/13 18 9/30/14 1/1/14
B2C Facility Construction 6,000 10/1/14 37 9/30/16 10/1/15
C1A Project Management 500 10/1/12 48 9/30/16 10/1/14
C1B Construction Management 250 10/1/12 48 9/30/16 10/1/14
C1C Project Support 250 10/1/12 48 9/30/16 10/1/14
Total 10,100
Appendix E DOE G 413.3-21A
E-2 6-6-2018
Table E-2 provides illustrative escalation rates. Site specific rates based on documented
information for the worksite location are best, but alternative rates provided by DOE/HQ (when
available) are used in the absence of appropriate local information. Regardless of the source, the
rates used, and the reason for using them should be clearly explained in the cost estimate
documentation. In the table, “index” represents the compounded escalation rate as a factor for
multiplying costs in a given year. The “%” term is the expected percentage of cost increase in
each stated year, Thus, the 1.076 construction index in 2015 is determined from the 2013, 2014
and 2015 escalation percentages as follows: 1.021 (2013 percentage) x 1.025 (2014 percentage)
x 1.029 (2015 percentage) = 1.076. Thus, 1.076 would be the factor to multiply costs estimated
in 2012 and expected to occur in 2015.
Table E-2. DOE Escalation Rates (notional for illustrative purposes)
Project Categories *
FY Construction EM IT O&M R&D
2012 Index % Index % Index % Index % Index %
2013 1.021 2.1 1.02 2 1.008 0.8 1.018 1.8 1.023 2.3
2014 1.046 2.5 1.047 2.7 1.017 0.9 1.045 2.6 1.051 2.8
2015 1.076 2.9 1.075 2.7 1.022 0.5 1.073 2.7 1.08 2.7
2016 1.106 2.8 1.103 2.6 1.032 1 1.101 2.6 1.108 2.6
2017 1.135 2.6 1.13 2.4 1.041 0.8 1.127 2.4 1.136 2.5
Table E-3 provides a table of notional monthly escalation rates through the corresponding fiscal
years. This example assumes a straight-line escalation for each FY, although other applications
may be appropriate (e.g., weighted at the beginning or end of a FY). Use of the escalation
“curve” (i.e., straight-line or other) and the reason it was selected should be well-documented.
From the table, the escalation rate to apply to costs estimated in December 2011 and expected to
occur in July 2015 would be 9.17%.
DOE G 413.3-21A Appendix E
6-6-2018 E-3
Table E-3. Illustrative Monthly Escalation Rates
Months of
Escalation 0 1 2 3 4 5 6 7 8 9 10 11 12
Month of the
Year (Mid-
Point) 10 11 12 1 2 3 4 5 6 7 8 9 10
FY Rate
2012 2.10% 0.00% 0.17% 0.35% 0.52% 0.70% 0.87% 1.05% 1.22% 1.40% 1.57% 1.75% 1.92% 2.10%
2013 2.10% 2.10% 2.28% 2.46% 2.64% 2.81% 2.99% 3.17% 3.35% 3.53% 3.71% 3.89% 4.07% 4.24%
2014 2.50% 4.24% 4.46% 4.68% 4.90% 5.11% 5.33% 5.55% 5.76% 5.98% 6.20% 6.42% 6.63% 6.85%
2015 2.90% 6.85% 7.11% 7.37% 7.62% 7.88% 8.14% 8.40% 8.66% 8.92% 9.17% 9.43% 9.69% 9.95%
2016 2.80% 9.95% 10.21% 10.46% 10.72% 10.98% 11.23% 11.49% 11.74% 12.00% 12.26% 12.51% 12.77% 13.03%
2017 2.60% 13.03% 13.27% 13.52% 13.76% 14.01% 14.25% 14.50% 14.74% 14.99% 15.23% 15.48% 15.72% 15.97%
Section 64
2018 2.60% 15.97% 16.22% 16.47% 16.72% 16.97% 17.22% 17.47% 17.72% 17.98% 18.23% 18.48% 18.73% 18.98%
Table E-4 provides a notional example of the project cost estimate summary with columns added
to illustrate compound escalation rates and escalation amounts by summary WBS element.
In calculating applicable escalation percentages, repetitive calculations are normal, so use of a
computerized escalation forecast algorithm is recommended. The specific conditions that prevail
must also be taken into account. For example, a construction subcontract awarded to span
multiple fiscal years at a firm fixed-price would not need to have escalation applied to the cost of
that contract.
Appendix E DOE G 413.3-21A
E-4 6-6-2018
Table E-4. Sample Project Cost Estimate Summary (Including Escalation)
WBS Scheduled Activity
Total
Base
Cost
(000$)
Start Duration
(Months) Complete Midpoint
Compounded
Escalation
Rate
Total
Escalation
Cost
(000$)
A1A
Preliminary Design
(Title I Design) 100 10/1/12 6 3/30/13 1/1/13 2.64% 103
A1B
Definitive Design
(Title II Design) 200 4/1/13 6 9/30/13 7/1/13 3.71% 207
A1C
Design during
Construction
(Title III Design) 100 10/1/13 36 9/30/16 7/1/15 9.17% 109
B2A
Equipment
Procurement (General
Services) 200 10/1/14 24 9/30/16 10/1/15 9.95% 220
B2B
Equipment
Procurement (Long-
Lead, GFE) 2,500 3/30/13 18 9/30/14 1/1/14 4.90% 2,623
B2C Facility Construction 6,000 10/1/14 37 9/30/16 10/1/15 9.95% 6,597
C1A Project Management 500 10/1/12 48 9/30/16 10/1/14 6.85% 534
C1B
Construction
Management 250 10/1/12 48 9/30/16 10/1/14 6.85% 267
C1C Project Support 250 10/1/12 48 9/30/16 10/1/14 6.85% 267
Totals 10,100 10,927
NOTE: Cost vs. Obligations - Funding Profile
A funding profile is a normal part of budget submissions. There is a difference between the
timing of project costs and obligations and funding requirements. As a project evolves, it should
be very clear that funds are required prior to spending them. This lead time should be carefully
evaluated and established by the project team. Care should be taken to establish the most
appropriate funding profile to provide for efficient use of funds and to minimize carry-over
(where funds are not obligated within the FY for which they are authorized).
DOE G 413.3-21A
6-6-2018
Appendix E
E-5 (and E-6)
Resources for Cost Escalation
Bureau of Labor Statistics
http://www.bls.gov/bls/escalation.htm
Producer Price Index (PPI) Guide to
Contract Escalation
http://www.bls.gov/cpi/cpi1998d.htm
Employment Cost Index for Escalation
www.bls.gov/ncs/ect/escalator.htm
www.bls.gov/ppi/ppiescalation.htm
Consumer Price Index for Escalation
Employment Cost Trends Home Page
http://www.bls.gov/ect/
Construction Economics – Engineering News Record
http://www.enr.com/economics
Note: The Non-IT Capital Asset Budget Guidance22 has been updated to include
past ENR construction indices. The cost estimate escalation assumption includes
the following statement: “Some of the annual and monthly indices including
(ENR construction Cost index) have been documented by the USDA NRCS.23
The USDA NRCS link provides a spreadsheet with past ENR construction cost
index (CCI), one of several indices published by ENR. Rule of thumb; generally
CCI escalation represents more than 3-4%.
Cost Index | Turner Construction Company
http://www.turnerconstruction.com/cost-index
Industrial producer price index overview
http://ec.europa.eu/eurostat/
Power Capital Costs Index - IHS.com
https://www.ihs.com/info/cera/ihsindexes/
Section 65
DOE Escalation Rates for Energy
http://energy.gov/eere/femp/energy-escalation-rate-calculator-download
22 https://powerpedia.energy.gov/wiki/Non-IT_Capital_Asset_Budget_Guidance
23 http://www.nrcs.usda.gov/wps/portal/nrcs/main/national/technical/econ/prices/
http://www.bls.gov/bls/escalation.htm
http://www.bls.gov/ppi/ppiescalation.htm
http://www.bls.gov/cpi/cpi1998d.htm
http://www.bls.gov/ncs/ect/escalator.htm
http://www.bls.gov/ncs/ect/escalator.htm
http://www.bls.gov/ect/
http://www.enr.com/economics
http://www.enr.com/economics
https://powerpedia.energy.gov/wiki/Non-IT_Capital_Asset_Budget_Guidance
http://www.nrcs.usda.gov/wps/portal/nrcs/main/national/technical/econ/prices/
http://www.turnerconstruction.com/cost-index
http://www.turnerconstruction.com/cost-index
http://ec.europa.eu/eurostat/statistics-explained/index.php/Industrial_producer_price_index_overview
http://ec.europa.eu/eurostat/
https://www.ihs.com/info/cera/ihsindexes/
https://www.ihs.com/info/cera/ihsindexes/
http://energy.gov/eere/femp/energy-escalation-rate-calculator-download
https://powerpedia.energy.gov/wiki/Non-IT_Capital_Asset_Budget_Guidance
http://www.nrcs.usda.gov/wps/portal/nrcs/main/national/technical/econ/prices/
DOE G 413.3-21A Appendix F
6-6-2018 F-1
Appendix F: Example of Life-Cycle Cost Analysis
This Appendix presents the Life Cycle Cost Analysis (LCCA) as excerpted from the DOE PM
document, Life Cycle Cost Handbook, Guidance for Life cycle Cost Estimation and Analysis
(September 2014). The Handbook provides the reader with procedures, information, examples,
and tools to develop consistent and defensible life-cycle cost estimates (LCCE) and perform
appropriate life-cycle cost analyses (LCCA) for capital projects.
The Department of Energy has affirmed that the LCCA in conjunction with the Alternatives of
Analysis process may be used to determine the most cost effective option among alternatives,
and to fully document the selection process. In cases where all alternatives have the same
annual effects or benefits, a cost effectiveness analysis can be performed where only the
discounted monetized cost is analyzed. For example, analyses of alternatives of defense
systems or programs eliminating a problem (e.g. toxic waste, unsafe conditions) often fall
into this category.,
The process used to conduct LCCA comprises those tasks that enable a comparative
investigation of competing project or program alternatives. The process begins with developing
a life-cycle cost estimate for each alternative, generally including all costs for all project
phases.
An LCCA seeks to find the best value solution by linking each alternative to how it satisfies a
strategic objective. The analysis presents facts and supporting details in addition to
assessments of cost. The process is sometimes defined as a business case analysis or cost-
benefit analysis, but in this appendix it will consistently be termed LCCA. An LCCA considers
not only all the life-cycle costs that an LCCE identifies but also quantifiable and non-
quantifiable benefits when they differ among alternatives and can be assessed. The LCCA
should be unbiased by considering all practical alternatives and should not be developed solely
for supporting a particular solution. Moreover, it should be rigorous enough that independent
auditors can review it and clearly understand why a particular alternative was chosen.
For each alternative, the LCCA should be documented with the following information:
Section 66
• Relative life-cycle costs and benefits;
• Methods and rationale for quantifying the life-cycle costs and benefits, including
definition of assumptions, analyzing alternatives, applying escalation, and discounting
for net present value (NPV);
• Effect and value of cost, schedule, and performance tradeoffs;
• Sensitivity to changes in assumptions and discount rates; and,
• Risk factors.
In addition to supporting an investment decision made in support of a Critical Decision, the
LCCA should be considered a living document and updated often to reflect changes in scope,
schedule, or budget. In this way, the LCCA is a valuable tool for validating decisions to
sustain or enhance the enterprise through ongoing value engineering assessments.
Appendix F DOE G 413.3-21A
F-2 6-6-2018
If the project sponsor expects alternatives to have differing performance levels (e.g., differing
production rates, research and development throughput or quality), the project should
monetize the performance levels to include them in the analysis of alternatives.
Project Analysis
The principal technique for evaluating project alternatives is to calculate the NPV for each
project alternative considered (e.g., site selection, materials of construction, development
timespan) in developing a project. The project analysis compares the costs and benefits (when
there is a perceived benefit difference among the alternatives) of each alternative. For example,
for a given environmental remediation project the least expensive alternative may be to leave
waste in place and cap it, versus treatment and shipment for disposal. The long-term costs of
Surveillance and Maintenance (S&M) would need to be included in this example. In another
example, a method for tritium production might consider particle accelerator production,
versus irradiation of lithium rods. These alternatives would entail very different concepts, types
of cost, and timespans.
To avoid perceived bias, care must be taken in assigning monetary values to future benefits.
This is particularly true when evaluating an alternative that produces a seemingly better result.
For example, in high-technology science projects, an alternative may provide “better science”
than competing alternatives’ technologies. Assigning monetary values to “better” conditions
can be controversial and a major determinant in the alternative selection. Thus, the
measurement of relative value must be carefully done and fully documented. In every case, all
the costs for the competing solutions and benefits to be derived are determined and brought to
an NPV figure.
The cornerstone of NPV calculations is the selection and application of an appropriate discount
rate. The discount rate is a percentage applied to expenditures expected to be made in the future
(or payments received in the future) that converts the future amount to its equivalent today.
Estimation of the present value of future benefits/costs is highly sensitive to the choice of a
discount rate. OMB Guidelines and Discount Rates for Benefit-Cost Analysis of Federal
Programs (Circular No. A-94) gives specific guidance on discount rates for evaluating federal
programs whose benefits and costs are distributed over time. As described in the circular, a
“real” discount rate of 7 percent should currently be used, as this rate approximates the marginal
pretax rate of return on an average investment in the private sector in recent years. Changes in
this rate will be reflected in future updates of the circular, and the current circular should always
be used for DOE LCCAs.
Section 67
Before defining the “real” discount rate, an understanding of the “nominal” interest rate is
needed. The nominal interest rate is simply the stated interest rate guaranteed by an issuer. It is
the actual monetary price that borrowers pay to use a lender’s money. The “real” interest rate
is so named because it states the “real” rate that the lender or investor receives after inflation is
taken into account; that is, the interest rate that exceeds the inflation rate. If a bond that
compounds annually has a 6 percent nominal yield and the inflation rate is 4 percent, then the
real rate of interest is only 2 percent.
DOE G 413.3-21A Appendix F
6-6-2018 F-3
In essence,
Nominal interest rate – Inflation = Real interest rate
Tip: When using constant year dollars, without escalation added, a real discount rate
should be used to calculate NPV. When escalated, or as-spent, dollars are being used
for the analysis, a nominal (or higher) discount rate should be used.
A commanding knowledge of the project’s cost-driving parameters is required to analyze the
alternatives. It is important to understand what is driving the costs and the time phasing of
those costs for each alternative. Developing an LCCA may greatly assist in understanding the
cost drivers and thus directly influence a project’s design and implementation planning.
Funding constraints are a major consideration in most DOE and National Nuclear Security
Administration (NNSA) programs, and they must be assessed within the context of LCCA
development. Such constraints can force schedule considerations that may make a less
attractive alternative the favorable selection in terms of NPV, such as when funding
constraints slow a program component schedule to the extent that out-year expenditures
appear more favorable when brought to a present day basis.
NPV is computed by assigning monetary values to benefits and costs, discounting future
benefits and costs using an appropriate discount rate, and subtracting the total of discounted
costs from the total of discounted benefits. (As mentioned, solutions with equal benefits need
consider only costs) The process transforms gains and losses occurring at different times to a
common unit of measurement. A discussion of the mathematical process used to calculate NPV
for two competing alternatives is provided in the Example 3-1.
Example 3-1. Comparative Life Cycle Costs
In this example, both Project A and Project B are assumed to be production
facilities that provide an equally acceptable product over a 20-year useful
life. Project B requires a shorter and less expensive construction span, but
runs at a higher operating cost, is expected to be more expensive to
disposition (i.e., develops a higher environmental liability), and has no
salvage value. Project B yields an excess capacity than can generate $5
million per year revenue stream.
Appendix F DOE G 413.3-21A
F-4 6-6-2018
Capital Project A
Element Estimated Cost
Capital Project Cost Year 1 Year 2 Year 3 Year 4
Project Management 6,000,000 7,000,000 8,000,000 5,000,000
Design 25,000,000 15,000,000 - -
Procurement 5,000,000 20,000,000 5,000,000
Construction - 15,000,000 40,000,000 85,000,000
Title III - 3,000,000 3,000,000
Transition to Ops - 5,000,000
Year 5
2,850,000
-
30,000,000
2,500,000
35,000,000
Year 6
-
-
-
-
-
-
Total
28,850,000
40,000,000
30,000,000
170,000,000
8,500,000
40,000,000
36,000,000 57,000,000 56,000,000 98,000,000
Section 68
Operations and Maintenance Cost
Annual O&M (Assume 20 years @ $50,000,000/year)
Periodic Capital Replacements (Assume $20,000,000 each in year 10, 15, and 20)
Final Disposition Cost
Deactivation/Decommissioning in year 26
Salvage Value
Total-Life Cycle Cost (net of all costs less salvage value)
70,350,000 -
50,000,000
-
317,350,000
1,000,000,000
60,000,000
50,000,000
(5,000,000)
1,422,350,000
Capital Project B
Element Estimated Cost
Capital Project Cost Year 1 Year 2 Year 3 Year 4
Project Management 3,500,000 7,000,000 5,500,000 -
Design 17,000,000 13,000,000 - -
Procurement 4,000,000 15,000,000 - -
Construction - 60,000,000 70,000,000 -
Title III - 4,000,000 3,000,000 -
Transition to Ops - 30,000,000
Year 5 Total
16,000,000
30,000,000
19,000,000
130,000,000
7,000,000
30,000,000
24,500,000 99,000,000
Operations and Maintenance Cost
Annual O&M (Assume 20 years @ $58,000,000/year)
Periodic Capital Replacements (Assume $20,000,000
each in operating year 7 and 14)
Revenue
Annual income from excess production
Assume $5M/year for operating life of plant
Final Disposition Cost
Deactivation/Decommissioning
Salvage Value
Total-Life Cycle Cost (net of all costs less revenue)
78,500,000 30,000,000
-
58,000,000
(5,000,000)
232,000,000
1,160,000,000
40,000,000
(100,000,000)
95,000,000
-
1,427,000,000
DOE G 413.3-21A Appendix F
6-6-2018 F-5
A simple comparison of life-cycle cost indicates the alternatives are nearly equivalent,
although Project A appears to be the more desirable from a cost standpoint,
$1,422,350,000 for Project A versus $1,427,000,000 for Project B.
Conducting an LCCA for the two alternatives is then done in order to take into account
the time value of money. Development of NPV figures for alternatives is based on the
formula PV = 1/(1+r)t where r is the discount rate, and t is the number of years in
advance when an expenditure is made, or a payment received. To illustrate the use of a
PV factor, at a discount rate of 10 percent per year, the PV factor is 0.621 for year 5,
meaning the present value of $1 spent or received at year 5 is $0.621.
Tip: Although present value tables are commonly available and useful,
Appendix G provides a formatted spreadsheet that computes, from discount
rate and time inputs chosen by the user, PV costs of future expenditures
developed from the 1/(1+r)t relationship.
Comparing capital project A and B on an NPV basis begins with calculating the
present worth of each expenditure or payment (salvage value of alternative A, revenue
stream of alternative B) and summing them, as done in the Example 3-2.
Appendix F DOE G 413.3-21A
F-6 6-6-2018
Another example of a LCCA is presented in Example 3-3. This example uses the LCCE for the
hypothetical radiological laboratory that was used to illustrate LCCE principles earlier in this
guide. Note that the estimate values used for this analysis do not include any allowances for
estimate uncertainty or risk.
Example 3-3. LCCA Comparison of Alternatives
This example compares the costs to construct a new, more efficient radiological laboratory at an
existing DOE site to replace an aging, less efficient laboratory.
Other elements and assumptions used for this analysis include the following items:
• The annual O&M costs for the existing facility are 25% higher than those of the new facility,
because more work shifts will be needed in the existing facility to match the needed capacity
(for which the new facility will be designed to achieve).
Section 69
• It will be possible to continue to operate the existing facility for the remaining period needed,
after some near-term modifications (which will not disrupt operations), and periodic
upgrades over the remaining life that will be somewhat higher than the new facility will
require.
• For the new facility option, the old facility final disposition (after a short S&M period) will
need to be completed.
• It is assumed the S&M and final disposition costs will be the same for both facilities.
The results of the NPV calculations are presented in Appendix E.1. In summary, the analysis shows
that, on a present value basis, it is slightly more economical to keep operating the existing facility
($358M) than it would be to design and construct a new more efficient facility ($367M)
Occasionally, it will become apparent that certain costs related to a given alternate are likely to
change. In such cases, it may be possible to conduct a revised comparative analysis that
addresses only the components that have changed. However, it is always preferable to conduct a
full comparative analysis of alternatives to ensure that all variables have been considered, and
full documentation remains intact to support the program decision selection.
Program Analysis
This section discusses the composition and use of a life-cycle baseline as an instrument to
manage a program comprising multiple projects and other elements, for example, laboratory
support and research and development contracts. A program-level life-cycle cost baseline can be
used to document a program’s critical cost, schedule, and performance parameters, and express
them in measurable, quantitative terms that must be met in order to accomplish the program’s
goals. By tracking and measuring actual program performance against this baseline, the
program’s management is alerted to potential problems, such as cost growth or requirements
creep and can take early corrective action. As a point of reference, to develop budget estimates
for operating programs, NNSA has implemented a planning, programming, budgeting, and
evaluation (PPBE) process that provides a framework for the agency to plan, prioritize, fund, and
evaluate program activities.
DOE G 413.3-21A Appendix F
6-6-2018 F-7
A program life-cycle baseline must be comprehensive. A formalized program WBS structure is
required to provide a clear picture of what needs to be accomplished, where and when cross-
cutting milestones must be achieved, and how the work will be done and to provide a basis for
identifying resources and tasks for developing a cost estimate. Without a program-level work
WBS, there is no assurance that a life-cycle cost estimate will capture all relevant costs, which
can lead to cost overruns and schedule delays.
The program life-cycle baseline must be well-documented. Documentation is best when prepared
as a single document to describe data sources and steps taken in developing the estimate—such
as applying escalation rates, the basis for labor costs, sources of procurements, application of
overhead, and other indirect costs—so that the estimate could be replicated by someone other
than the preparers. Benefits and the methodology for assessing associated dollar values of
benefits, attributed to each alternative, should also be documented, along with an explanation of
how benefits support the mission need. Changes in baseline ground rules and assumptions should
be evaluated promptly, and the affected cost estimates adjusted accordingly.
Section 70
The program life-cycle baseline must be accurate. A formal system for tracking and reporting
cost and schedule performance (earned value system) to update the estimate is essential to
provide early identification of when, how much, and why the program cost more or less than
planned.
The program life-cycle baseline must be credible. This is best accomplished by:
• Conducting an independent cost estimate to provide an unbiased test of whether the
estimate is reasonable
• Providing a formal sensitivity analysis to examine the effects of changing assumptions
and ground rules
• Developing a risk and uncertainty analysis to assess variability in point estimates due to
factors such as errors and estimator bias
The basic concepts of LCCA are identical for use in evaluating both the elements of programs
and projects. That is, LCCA always compares the NPV of competing alternatives.
Appendix F DOE G 413.3-21A
F-8 6-6-2018
Alternative Selection Considerations
Simply stated, the best solution among alternatives is the one with the lowest NPV. When the
alternatives offer varying levels of benefits, or when placing a specific dollar value on benefits is
difficult to assess, selection of the best alternative is more challenging. In general, the process for
identifying benefits should include the following actions:
• Use a standard process to quantify the benefits and effectiveness of each alternative and
document this process
• Quantify the benefits and effectiveness resulting from each alternative over that
alternative's full life cycle, if possible
• Explain how each measure of benefit and effectiveness supports the mission need
These actions should be included in the baseline documentation.
DOE G 413.3-21A Appendix F
6-6-2018 F-9
Tip: Providing a thorough explanation of the methodology used in assessing benefits to a
program alternative not only clarifies the selection team’s criteria, but also helps to allay
concerns that the selection process was biased.
Appendix F DOE G 413.3-21A
F-10 6-6-2018
Example 3-6. Cost Avoidance Benefits
In another example, alternatives are assessed for competing projects considered for improving site
security at a national laboratory. The projects are assumed to offer differing levels of benefits. The
assessment therefore must find a means to measure a value for the unequal benefits to be achieved.
First, assume that the relative level of improved site security can be equated to the relative reductions in
frequency and severity of undesirable events, such as unauthorized IT system access (external or
internal), unauthorized physical access, and disasters affecting the site infrastructure (fire, flood, etc.)
Each undesirable event can have specific costs associated with it, such as productivity losses resulting
from virus attacks or from intruder caused stoppages, legal liability from unauthorized system access,
etc. Relative benefits would comprise the sum of such costs avoided by each alternative solution.
Assume two competing site security improvement schemes, Project P and Project Q, are contemplated,
with equivalent as-spent capital construction costs. Further, assume that both schemes can be brought
into operation after a 3-year installation schedule; that is, through completion of all project phases,
including procurement and construction.
The only difference in Projects P and Q lies in their ability to avoid “upset” costs. Their differing
approaches (Project P is more heavily concerned with physical security and Project Q more with IT
improvements) lead to differing types and amounts of cost avoidance benefits.
Section 71
Assume that the benefits can be distilled to two types of cost avoidance; namely, avoidance of plant
stand-downs caused by unauthorized intrusions, estimated to cost $2 million each, and IT compromises
leading to total system outages and loss of data, estimated to cost $4 million each. Further, assume the
plant currently experiences on average an unauthorized intrusion stand-down every 2 years and an IT
compromise every 2 years.
Project P, with its focus on physical security is expected to yield one intrusion stand-down in the 5th
year of its 10-year operating life. It is also expected to yield one IT compromise every 3 years, occurring
in the 3rd, 6th, and 9th years of operating life.
Project Q, structured more heavily towards IT security, is expected to experience five intrusion stand-
downs occurring in the 2nd, 4th, 6th, 8th, and 10th years of operating life, and one IT compromise in the
5th year of operations.
In the LCC Handbook Appendix E.4, PVs are calculated for the historical upsets costs over the operating
life of the plant security improvements, compared to PVs of the expected upset costs under Project P and
Q. As can be seen, the historical cost PV is expected to be $15.57 million if no improvements are made
to plant security. Project P would result in $8.63 million in upset costs, and Project Q in $9.15 million.
The savings produced by Project P would therefore be $15.57 million − $ 8.63 million = $ 6.94 million.
Project Q would produce $15.57 million − $9.15 million = $6.42 million in avoided cost. Because
Project P produces greater benefits (cost savings), it would be the best solution, if all other costs are
equivalent, as assumed.
DOE G 413.3-21A Appendix F
6-6-2018 F-11 (and F-12)
DOE Order 413.3B and its associated guides and handbooks addressing Analysis of Alternatives,
Systems Engineering, Acquisition Strategy, and Cost Estimating provide best practices for the
analysis and comparison of alternatives.
LCCA Cost Tools
To assist the user in preparing NPV calculations of alternatives and to provide consistency in
their formatting, LCC Handbook Appendix G provides an Excel spreadsheet template that can be
used to enter the variables of an LCCA. The template will yield a finished product that will be
complete and consistent with other LCCAs.
As provided, it includes yearly life-cycle costs by project phase for two alternative programs.
The yearly values represent the escalated, as-spent amount estimated by the user. There is also a
single cell where the user enters the discount rate upon which to base the analysis. The
spreadsheet then automatically calculates NPV for each alternative.
The LCC Handbook Appendix G is both an example of how the spreadsheet is used and the
actual analytical tool for use in developing an LCCA. As the example, the spreadsheet depicts
two program alternatives, A and B. Shaded areas of the spreadsheet contain entries made by a
user. In this case, the user has selected 7 percent as the appropriate discount rate, and has entered
annual as-spent cost estimates that amount to life-cycle costs of $639 million and $643 million
for A and B, respectively. The spreadsheet then calculates NPV for each alternative, amounting
to $431.5 million and $436 million for A and B, respectively. Users of the spreadsheet need
simply delete the example figures and insert their own cost estimates in place of the sample
figures.
Section 72
The National Institute of Standards & Technology’s Building Life Cycle Cost (BLCC) software
provides an additional resource for life cycle costing (LCC). This software tool incorporates
material from several documents discussed in this Guide. For further information, including
BLCC program downloads and discussion, see https://energy.gov/eere/femp/building-life-cycle-
cost-programs.
https://energy.gov/eere/femp/building-life-cycle-cost-programs
https://energy.gov/eere/femp/building-life-cycle-cost-programs
DOE G 413.3-21A Appendix G
6-6-2018 G-1
Appendix G: Cost Estimate Classifications (AACE International)
AACE International Recommended Practice 17R-97, Cost Estimate Classification System
AACE International Recommended Practice 18-R-97, Cost Estimate Classification System – As
Applied in Engineering, Procurement, and Construction for the Process Industries
Appendix G DOE G 413.3-21A
G-2 6-6-2018
DOE G 413.3-21A Appendix G
6-6-2018 G-3
Appendix G DOE G 413.3-21A
G-4 6-6-2018
DOE G 413.3-21A Appendix G
6-6-2018 G-5
Appendix G DOE G 413.3-21A
G-6 6-6-2018
DOE G 413.3-21A Appendix G
6-6-2018 G-7
Appendix G DOE G 413.3-21A
G-8 6-6-2018
DOE G 413.3-21A Appendix G
6-6-2018 G-9
Appendix G DOE G 413.3-21A
G-10 6-6-2018
DOE G 413.3-21A Appendix G
6-6-2018 G-11
Appendix G DOE G 413.3-21A
G-12 6-6-2018
DOE G 413.3-21A Appendix G
6-6-2018 G-13
Appendix G DOE G 413.3-21A
G-14 6-6-2018
DOE G 413.3-21A Appendix G
6-6-2018 G-15
Appendix G DOE G 413.3-21A
G-16 6-6-2018
DOE G 413.3-21A Appendix G
6-6-2018 G-17
Appendix G DOE G 413.3-21A
G-18 6-6-2018
DOE G 413.3-21A Appendix G
6-6-2018 G-19
Appendix G DOE G 413.3-21A
G-20 6-6-2018
DOE G 413.3-21A Appendix G
6-6-2018 G-21
Appendix G DOE G 413.3-21A
G-22 6-6-2018
DOE G 413.3-21A Appendix G
6-6-2018 G-23
Appendix G DOE G 413.3-21A
G-24 6-6-2018
DOE G 413.3-21A Appendix G
6-6-2018 G-25
Appendix G DOE G 413.3-21A
G-26 6-6-2018
DOE G 413.3-21A Appendix G
6-6-2018 G-27 (and G-28)
DOE G 413.3-21A Appendix H
6-6-2018 H-1 (and H-2)
Appendix H: References
AACE International. Recommended Practice 17R-97 “Cost Estimate Classification System.”
AACE-International, Morgantown WV, November 2011.
AACE International. Recommended Practice 18R-97 “Cost Estimate Classification System as
Applied in Engineering, Procurement, and Construction for the Process Industries.” AACE
International, Morgantown WV, March, 2016.
U.S. Department of Energy. Acquisition and Project Management Glossary of Terms Handbook.
Office of Project Management, Washington D.C., September 2014.
https://community.max.gov/x/bZloRQ.
U.S. Department of Energy. “Life Cycle Cost Handbook: Guidance for Life Cycle Cost Estimating
and Analysis.” Office of Project Management, Washington D.C., September 2014.
https://community.max.gov/x/bZloRQ.
U.S. Department of Energy. DOE Order 413.3B “Program and Project Management for the
Acquisition of Capital Assets.” Office of Project Management, Washington D.C., October
2017. https://www.directives.doe.gov/directives-documents/400-series/0413.3-BOrder-b-chg4-
minchg
U.S. Department of Energy. DOE Guide 413-3-7A “Risk Management Guide.” Office of Project
Management, Washington D.C., October 2015. https://www.directives.doe.gov/directives-
documents/400-series/0413.3-EGuide-07a-admchg1
U.S. Department of Energy. DOE Guide 413.3-13, Acquisition Strategy Guide for Capital Asset
Projects. Office of Project Management, Washington D.C., October 2015.
https://www.directives.doe.gov/directives-documents/400-series/0413.3-EGuide-13-admchg1
Section 73
Office, U.S. Government Accountability. “GAO Cost Estimating and Assessment Guide: Best
Practices for Developing and Managing Capital Program Costs (Supersedes GAO-07-
1134SP).” U.S. Government Accountability Office (U.S. GAO), Washington D.C., March
2009. www.gao.gov/products/GAO-09-3SP.
https://community.max.gov/x/bZloRQ
https://community.max.gov/x/bZloRQ
https://www.directives.doe.gov/directives-documents/400-series/0413.3-EGuide-07a-admchg1
https://www.directives.doe.gov/directives-documents/400-series/0413.3-EGuide-07a-admchg1
www.gao.gov/products/GAO-09-3SP
https://www.directives.doe.gov/directives-documents/400-series/0413.3-EGuide-13-admchg1
https://www.directives.doe.gov/directives-documents/400-series/0413.3-BOrder-b-chg4
DOE G 413.3-21A Appendix I
6-6-2018 I-1
Appendix I: DOE Recommendations for Quality Cost Estimates
It is important that cost estimators and the program office validate that all cost elements are
credible and can be justified by acceptable estimating methods, adequate data, and detailed
documentation. This crucial step ensures that a high-quality cost estimate is developed,
presented, and defended to management. This process verifies that the cost estimate adequately
reflects the program baseline and provides a reasonable estimate of how much it will cost to
accomplish all tasks. It also confirms that the program cost estimate is traceable and accurate and
reflects realistic assumptions.
Verifying the quality of the point estimate is considered a best practice. One reason for this is
that independent cost estimators typically rely on historical data and therefore tend to estimate
more realistic program schedules and costs for state-of-the-art technologies. Moreover,
independent cost estimators are less likely to automatically accept unproven assumptions
associated with anticipated savings. That is, they bring more objectivity to their analyses,
resulting in estimates that are less optimistic and higher in cost. An independent view provides a
reality check of the point estimate and helps reduce the odds that management will invest in an
unrealistic program that is bound to fail.
Cost Estimating Best Practices
There are four characteristics of a high-quality, reliable cost estimate. It is well-documented,
comprehensive, accurate, and credible.
An estimate must be thoroughly documented, including source data and significance, clearly
detailed calculations and results, and explanations of why particular methods and references
were chosen. Data must be traced to their source documents.
An estimate must have enough detail to ensure that cost elements are neither omitted nor double
counted. All cost-influencing ground rules and assumptions are detailed in the estimate’s
documentation.
An estimate must be unbiased, not overly conservative or overly optimistic, and is based on an
assessment of most likely costs. Few, if any, mathematical mistakes are present; those that are,
are minor.
Any limitations of the analysis because of uncertainty or bias surrounding data or assumptions
are discussed. Major assumptions are varied, and other outcomes are recomputed to determine
how sensitive they are to changes in the assumptions. Risk and uncertainty analysis is performed
to determine the level of risk associated with the estimate. The estimate’s results are
crosschecked, and an independent cost estimate (ICE) conducted by a group outside the
acquiring organization is developed to determine whether other estimating methods produce
similar results.
Section 74
Appendix I DOE G 413.3-21A
I-2 6-6-2018
Table I-1 shows how the 12 steps of a high-quality cost estimating process can be mapped to
these four characteristics of a high-quality, reliable cost estimate.
Table I-1. The Twelve Steps of High-Quality Cost Estimating (GAO)
Mapped to the Characteristics of a High-Quality Cost Estimate
Cost estimate characteristic: Cost estimating step:
Well documented. The estimate is thoroughly
documented, including source data and significance,
clearly detailed calculations and results, and
explanations for choosing a particular method or
reference:
• Data are traced back to the source documentation;
• Includes a technical baseline description;
• Documents all steps in developing the estimate so
that a cost analyst unfamiliar with the program can
recreate it quickly with the same result;
• Documents all data sources for how the data were
normalized;
• Describes in detail the estimating methodology
and rationale used to derive each WBS element’s
cost.
1. Define the estimate’s purpose;
3. Define the program;
5. Identify ground rules and
assumptions;
6. Obtain the data;
10. Document the estimate;
11. Present the estimate to
management.
Comprehensive. The estimate’s level of detail ensures
that cost elements are neither omitted nor double
counted:
• Details all cost-influencing ground rules and
assumptions;
• Defines the WBS and describes each element in a
WBS dictionary;
• A major automated information system program
may have only a cost element structure.
2. Develop the estimating plan;
4. Determine the estimating
approach.
Accurate. The estimate is unbiased, not overly
conservative or overly optimistic, and based on an
assessment of most likely costs:
• It has few, if any, mathematical mistakes; its
mistakes are minor;
• It has been validated for errors like double counting
and omitted costs;
• Cost drivers have been cross-checked to see if
results are similar;
• It is timely;
7. Develop the point estimate and
compare it to an independent cost
estimate;
12. Update the estimate to reflect
actual costs and changes.
DOE G 413.3-21A Appendix I
6-6-2018 I-3
Cost estimate characteristic: Cost estimating step:
• It is updated to reflect changes in technical or
program assumptions and new phases or milestones;
• Estimates are replaced with EVM EAC and the
independent EAC from the integrated EVM system.
Credible. Discusses any limitations of the analysis
from uncertainty or biases surrounding data or
assumptions:
• Major assumptions are realistic, varied and other
outcomes recomputed to determine their sensitivity
to changes in assumptions;
• Risk and uncertainty analysis is performed to
determine the level of risk associated with the
estimate;
• An independent cost estimate is developed to
determine if other estimating methods produce
similar results
7. Develop the point estimate and
compare it to an independent cost
estimate;
8. Conduct sensitivity analysis;
9. Conduct risk and uncertainty
analysis.
Validating Cost Estimates
Too often program assumptions are optimistic and thus cost estimates are unrealistic and as a
result, cost more than originally estimated. One way to avoid this predicament is to ensure that
program and project cost estimates are both internally and externally validated—that is, that they
are comprehensive, well documented, accurate, and credible. This increases the confidence that
an estimate is reasonable and as accurate as possible.
Section 75
The following steps should be taken to validate a program or project cost estimate:
1. Determine That the Estimate Is Well Documented:
Cost estimates are considered valid if they are well documented to the point at which they
can be easily repeated or updated and can be traced to original sources through auditing.
Rigorous documentation also increases an estimate’s credibility and helps support an
organization’s decision making. The documentation should explicitly identify the primary
methods, calculations, results, rationales or assumptions, and sources of the data used to
generate each cost element.
Cost estimate documentation should be detailed enough to provide an accurate
assessment of the cost estimate’s quality. For example, it should identify the data sources,
justify all assumptions, and describe each estimating method (including any cost
estimating relationships) for every WBS cost element. Further, schedule milestones and
deliverables should be traceable and consistent with the cost estimate documentation.
Finally, estimating methods used to develop each WBS cost element should be
Appendix I DOE G 413.3-21A
I-4 6-6-2018
thoroughly documented so that their derivation can be traced to all sources, allowing for
the estimate to be easily replicated and updated.
2. Determine That the Estimate Is Comprehensive:
Cost Estimators or Analysts should make sure that the cost estimate is complete and
accounts for all costs that are likely to occur. They should confirm its completeness, its
consistency, and the realism of its information to ensure that all pertinent costs are
included. Comprehensive cost estimates completely define the program, reflect the
current schedule, and are technically reasonable. In addition, cost estimates should be
structured in sufficient detail to ensure that cost elements are neither omitted nor double-
counted. For example, if it is assumed that software will be reused, the estimate should
account for all associated costs, such as interface design, modification, integration,
testing, and documentation.
To determine whether an estimate is comprehensive, an objective review must be
performed to certify that the estimate’s criteria and requirements have been met. This step
also infuses quality assurance practices into the cost estimate. In this effort, the reviewer
checks that the estimate captures the complete technical scope of the work to be
performed, using a logical WBS that accounts for all performance criteria and
requirements. In addition, the reviewer must determine that all assumptions and
exclusions the estimate is based on are clearly identified, explained, and reasonable.
3. Determine That the Estimate Is Accurate:
Estimates are accurate when they are not overly conservative or too optimistic, based on
an assessment of most likely costs, adjusted properly for inflation, and contain few, if
any, minor mistakes. In addition, when schedules or other assumptions change, cost
estimates should be revised to reflect their current status.
Validating that a cost estimate is accurate requires thoroughly understanding and
investigating how the cost estimate was constructed. For example, all WBS cost estimate
elements should be checked to verify that calculations are accurate and account for all
costs, including indirect costs. Moreover, proper escalation factors should be used to
inflate costs so that they are expressed consistently and accurately. Finally, rechecking
spreadsheet formulas and data input is imperative to validate cost model accuracy.
Section 76
Besides these basic checks for accuracy, the estimating technique used for each cost
element should be reviewed, to make sure it is appropriate for the degree of design or
requirements definition that is complete.
Depending on the analytical method chosen, several questions should be answered to
ensure cost estimate accuracy. Table I-2 outlines typical questions that should be
answered to assess accuracy associated with various estimating techniques.
DOE G 413.3-21A Appendix I
6-6-2018 I-5
Table I-2. Questions for Checking the Accuracy of Cost Estimating Techniques
Technique Question
Analogy • What heritage programs and scaling factors were used to create the
analogy?
• Are the analogous data from reliable sources?
• Did technical experts validate the scaling factor?
• Can any unusual requirements invalidate the analogy?
• Are the parameters used to develop an analogous factor similar to
the program being estimated?
• How were adjustments made to account for differences between
existing and new systems? Were they logical, credible, and
acceptable?
Data collection • How old are the data? Are they still relevant to the new program?
• Is there enough knowledge about the data source to determine if it
can be used to estimate accurate costs for the new program?
• Has a data scatter plot been developed to determine whether any
outliers, relationships, and trends exist?
• Were descriptive statistics generated to describe the data, including
the historical average, mean, standard deviation, and coefficient of
variation?
• If data outliers were removed, did the data fall outside three
standard deviations?
• Were comparisons made to historical data to show they were an
anomaly?
• Were the data properly normalized so that comparisons and
projections are valid?
• Were the cost data adjusted for inflation so that they could be
described in like terms?
Engineering build-
up
• Was each WBS cost element defined in enough detail to use this
method correctly?
• Are data adequate to accurately estimate the cost of each WBS
element?
• Did experienced experts help determine a reasonable cost estimate?
• Was the estimate based on specific quantities that would be ordered
at one time, allowing for quantity discounts?
• Did the estimate account for contractor material handling overhead?
• Is there a definitive understanding of each WBS cost element’s
composition?
• Were labor rates based on auditable sources? Did they include all
applicable overhead, general and administrative costs, and fees?
Were they consistent with industry standards?
• Is a detailed and accurate materials and parts list available?
Appendix I DOE G 413.3-21A
I-6 6-6-2018
Technique Question
Expert opinion • Do quantitative historical data back up the expert opinion?
• How did the estimate account for the possibility that bias influenced
the results?
Extrapolate from • Were cost reports used for extrapolation validated as accurate?
actuals (averages, • Was the cost element at least 25% complete before using its data as
learning curves, an extrapolation?
estimates at • Were functional experts consulted to validate the reported
completion) percentage as complete?
• Were contractors interviewed to ensure the cost data’s validity?
• Were recurring and nonrecurring costs separated to avoid double
counting?
• How were first unit costs of the learning curve determined? What
historical data were used to determine the learning curve slope?
Section 77
• Were recurring and nonrecurring costs separated when the learning
curve was developed?
• How were partial units treated in the learning curve equation?
• Were production rate effects considered? How were production
break effects determined?
Parametric • Was a valid statistical relationship, or CER, between historical costs
and program, physical, and performance characteristics established?
• How logical is the relationship between key cost drivers and cost?
• Was the CER used to develop the estimate validated and accepted?
• How old are the data in the CER database? Are they still relevant
for the program being estimated?
• Do the independent variables for the program fall within the CER
data range?
• What is the level of variation in the CER? How well does the CER
explain the variation (R2) and how much of the variation does the
model not explain?
• Do any outliers affect the overall fit?
• How significant is the relationship between cost and its independent
variables?
• How well does the CER predict costs?
Software estimating • Was the software estimate broken into unique categories: new
development, reuse, commercial off-the-shelf, modified code, glue
code, integration?
• What input parameters—programmer skills, applications
experience, development language, environment, process—were
used for commercial software cost models, and how were they
justified?
• How was the software effort sized? Was the sizing method
reasonable?
DOE G 413.3-21A Appendix I
6-6-2018 I-7
Technique Question
• How were productivity factors determined?
• How was labor hours converted to cost? How many productive
hours were assumed in each day?
• How were savings from auto-generated code and commercial off-
the-shelf software estimated? Are the savings reasonable?
• What were the assumptions behind the amount of code reuse? Were
they supported?
• How were the integration between the software, commercial
software, system, and hardware estimated, and what historical data
supported the results?
• Were software license costs based on actual or historical data?
• Were software maintenance costs adequately identified and
reasonable?
Validating Parametric Cost Estimates and Cost Models
Cost Estimating Relationships (CERs) and cost models also need to be validated to
demonstrate that they can predict costs within an acceptable range of accuracy. To do
this, data from historical programs similar to the new program should be collected to
determine whether the CER selected is a reliable predictor of costs. In this review,
technical parameters for the historical programs should be examined to determine
whether they are similar to the program being estimated. For the CER to be accurate, the
new and historical programs should have similar functions, objectives, and program
factors, like acquisition strategy, or results could be misleading. Equally important, CERs
should be developed with established and enforced policies and procedures that require
staff to have proper experience and training to ensure the model’s continued integrity.
Before a parametric model is used to develop an estimate, the model should be calibrated
and validated to ensure that it is based on current, accurate, and complete data and is
therefore a good predictor of cost. Like a CER, a parametric model is validated by
determining that its users have enough experience and training and that formal estimating
system policies and procedures have been established. The procedures focus on the
model’s background and history, identifying key cost drivers and recommending steps for
calibrating and developing the estimate. To stay current, parametric models should be
continually updated and calibrated.
Section 78
Validation with calibration gives confidence that the model is a reliable estimating
technique. To evaluate a model’s ability to predict costs, a variety of assessment tests can
be performed. One is to compare calibrated values with independent data that were not
included in the model’s calibration. Comparing the model’s results to the independent
test data’s “known value” provides a useful benchmark for how accurately the model can
predict costs. An alternative is to use the model to prepare an estimate and then compare
Appendix I DOE G 413.3-21A
I-8 6-6-2018
its result with an independent estimate cost or check estimate based on another estimating
technique.
4. Determine That the Estimate Is Credible:
Credible cost estimates clearly identify limitations because of uncertainty or bias
surrounding the data or assumptions. Major assumptions should be varied and other
outcomes recomputed to determine how sensitive outcomes are to changes in the
assumptions. In addition, a risk and uncertainty analysis should be performed to
determine the level of risk (cost estimate uncertainty) associated with the estimate.
Finally, for projects that require an ICE, the results of the estimate should be cross-
checked and an ICE performed to determine whether alternative estimate views produce
similar results.
To determine an estimate’s credibility, key cost elements should be tested for sensitivity,
and other cost estimating techniques should be used to cross-check the reasonableness of
Ground Rules & Assumptions (GR&As). It is also important to determine how sensitive
the final results are to changes in key assumptions and parameters. A sensitivity analysis
identifies key elements that drive cost and permits what-if analysis, often used to develop
cost ranges and risk reserves. This enables management to know the potential for cost
growth and the reasons behind it.
Along with a sensitivity analysis, a risk and uncertainty analysis adds to the credibility of
the cost estimate, because it identifies the level of confidence associated with achieving
the cost estimate. Risk and uncertainty analysis produces more realistic results, because it
assesses the variability in the cost estimate from such effects as schedules slipping,
missions changing, and proposed solutions not meeting users’ needs. An uncertainty
analysis gives decision makers perspective on the potential variability of the estimate
should facts, circumstances, and assumptions change. By examining the effects of
varying the estimate’s elements, a degree of uncertainty about the estimate can be
expressed with a range of potential costs that is qualified by a factor of confidence.
Another way to reinforce the credibility of the cost estimate is to see whether applying a
different method produces similar results. In addition, industry rules of thumb can
constitute a sanity check. The main purpose of cross-checking is to determine whether
alternative methods produce similar results. If so, then confidence in the estimate
increases, leading to greater credibility. If not, then the cost estimator should examine and
explain the reason for the difference and determine whether it is acceptable.
An ICE is considered one of the best and most reliable validation methods. An ICE is
conducted independently of the Project or Program by an outside organization external to
the project’s decision making process. Preparing an ICE is an inherently government
function.
DOE G 413.3-21A Appendix I
6-6-2018 I-9
Section 79
GAO states that ICEs should be conducted by an organization outside the acquisition
chain, using the same detailed technical information as the program estimate, it is a
comparison with the program estimate to determine whether it is accurate and realistic.
ICEs can provide decision makers with additional insight into a program’s potential
costs—in part, because they frequently use different methods and are less burdened with
organizational bias. Moreover, ICEs tend to incorporate adequate risk and, therefore, tend
to be more conservative by forecasting higher costs than the program office.
The ICE is usually developed from the same technical baseline description the program
office used so that the estimates are comparable. An ICE’s major benefit is that it
provides an objective and unbiased assessment of whether the program estimate can be
achieved, reducing the risk that the program will proceed underfunded. It also can be
used as a benchmark to assess the reasonableness of a contractor’s proposed costs,
improving management’s ability to make sound investment decisions, and accurately
assess the contractor’s performance.
In most cases, the ICE team does not have insight into daily program events, so it is
usually forced to estimate at a higher level or use analogous estimating techniques. It is,
in fact, expected that the ICE team will use different estimating techniques and, where
possible, data sources from those used to develop the baseline estimate. It is important for
the ICE team and the program’s cost estimate team to reconcile the two estimates.
Two issues with ICEs are the degree of independence and the depth of the analysis.
Degree of independence depends on how far removed the estimator is from the program
office. The greater the independence, the more detached and disinterested the cost
estimator is in the program’s success. The basic test for independence, therefore, is
whether the cost estimator can be influenced by the program office.
Thus, independence is determined by the position of the cost estimator in relation to the
program office and whether there is a common superior between the two. For example, if
an independent cost estimator is hired by the program office, the estimator may be
susceptible to success-oriented bias. When this happens, the ICE can end up too
optimistic.
History has shown a clear pattern of higher cost estimates the further away from the
program office that the ICE is created. This is because the ICE team is more objective
and less prone to accept optimistic assumptions. To be of value, however, an ICE must
not only be performed by entities far removed from the acquiring program office but
must also be accepted by management as a valuable risk reduction resource that can be
used to minimize unrealistic expectations. The second issue with an ICE is the depth of
the review.
Table I-3 (taken from Table 27 in the GAO Cost Estimating and Assessments Guide,
GAO-09-3SP) lists eight types of independent cost estimate reviews and describes what
they entail.
Appendix I DOE G 413.3-21A
I-10 6-6-2018
Table I-3. Eight Types of Independent Cost Estimate Reviews:
Review Description
Document review It is an inventory of existing documentation to
determine whether information is missing and an
assessment of the available documentation to support
the estimate.
Independent cost assessment An outside evaluation of a program’s cost estimate that
examines its quality and accuracy, with emphasis on
specific cost and technical risks, it involves the same
procedures as those of the program estimate but using
different methods and techniques.
Section 80
Independent cost estimate Conducted by an organization outside the acquisition
chain, using the same detailed technical information as
the program estimate, and is a comparison with the
program estimate to determine whether it is accurate and
realistic.
Independent Government
Cost Estimate
Analyzing contractors’ prices or cost proposals, it
estimates the cost of activities outlined in the statement
of work; does not include all costs associated with a
program and can only reflect costs from a contractor’s
viewpoint. Assumes that all technical challenges can be
met as outlined in the proposal, meaning that it cannot
account for potential risks associated with design
problems.
Non-advocate review Performed by experienced but independent internal non-
advocate staff, it ascertains the adequacy and accuracy
of a program’s estimated budget; assesses the validity of
program scope, requirements, capabilities, acquisition
strategy, and estimated life-cycle costs.
Parametric estimating
technique
Usually performed at the summary WBS level, it
includes all activities associated with a reasonableness
review and incorporates cross-checks using parametric
techniques and factors based on historical data to
analyze the estimate’s validity.
DOE G 413.3-21A Appendix I
6-6-2018 I-11 (and I-12)
Reasonableness, or It is a review of all documentation by an independent
sufficiency, review cost team, meeting with staff responsible for developing
the program estimate, to analyze whether the estimate is
sufficient with regard to the validity of cost and
schedule assumptions and cost estimate methodology
rationale and whether it is complete.
Sampling technique It is an independent estimate of key cost drivers of
major WBS elements whose sensitivity affects the
overall estimate; detailed independent estimates
developed for these key drivers include vendor quotes
and material, labor, and subcontractor costs. Other
program costs are estimated using the program estimate,
as long as a reasonableness review has been conducted
to ensure their validity.
As the table shows, the most rigorous independent review is an ICE. Other independent
cost reviews address only a program’s high-value, high-risk, and high-interest elements
and simply pass through program estimate values for the other costs. While they are
useful to management, not all provide the objectivity necessary to ensure that the estimate
going forward for a decision is valid.
After an ICE or independent review is completed, it should be reconciled to the project or
baseline estimate to ensure that both estimates are based on the same GR&As. A synopsis
or reconciliation of the cost estimates and their differences is then presented to
management. Using this information, decision makers use the ICE or independent cost
estimate review to validate whether the program estimate is reasonable.
1.0 PURPOSE
2.0 KEY GUIDANCE CHARACTERISTICS
2.1 High-Quality Cost Estimates
a. Validating that a cost estimate is accurate requires thoroughly understanding and investigating how the cost estimate was constructed. For example, all WBS cost estimate elements should be checked to verify that calculations are accurate and accoun...
2.2 Cost Estimate Structure
2.3 Purpose of the Cost Estimate
2.4 Overview of the Cost Estimating Process Model
3.0 COST ESTIMATING INPUTS
3.1 Project/Program Requirements
3.2 Application of this Guide to DOE Estimating
3.2.1 DOE Critical Decisions for Project Management and the Supporting Cost Estimates
3.2.2 Annual Budget Process
3.2.3 Contract Actions
3.2.4 Other Project/Program Management Actions
Section 81
4.0 COST ESTIMATING CHARACTERISTICS and CLASSIFICATIONS
4.1 Planning the Cost Estimates
4.2 Cost Estimate Classifications
4.3 Cost Estimate Ranges
5.0 COST ESTIMATING METHODS
5.1 Detailed Estimating Method
5.2 Parametric Estimating Techniques
5.2.1 Cost Estimating Relationships
5.2.2 End Products Unit Method
5.2.3 Physical Dimension Method
5.2.4 Capacity Factor Method
5.2.5 Ratio or Factor Method
5.3 Other Estimating Methods
5.3.1 Level of Effort Method
5.3.2 Specific Analogy Method
5.3.3 Expert Opinion Method
5.3.4 Trend Analysis Method
5.3.5 Learning Curve Method
5.4 Methods of Estimating Other Life-Cycle Costs
5.4.1 Count Drawings and Specifications Method
5.4.2 Full-Time Equivalent Method
5.4.3 Percentage Method
6.0 COST ESTIMATING DEVELOPMENT PROCESS
6.1 Overview of the Cost Estimating Process
6.2 Estimate Planning
6.3 Cost Estimate Inputs
6.3.1 Sources of Data Input
6.3.2 Considerations for Cost Estimate Development
6.4 Cost Estimate Production
6.4.1 Schedule Development
6.4.2 Direct Cost Development
6.4.2.3 Allowances
6.4.2.3.1 Allowances for Special Conditions
6.4.3 Indirect Costs
6.4.4 Escalation
6.4.5 Contingency
6.5 Cost Estimate Review
6.6 Estimate Reconciliation
6.7 Cost Estimate Documentation
6.7.1 Cost Estimate Package
6.7.2 Cost Classification
6.8 Estimate Maintenance
7.0 COST ESTIMATING OUTPUTS
7.1 Cost Estimate Interfaces
7.2 Presenting the Estimate to Management
7.3 Baselines and Change Control
7.4 Analysis
8.0 COST ESTIMATING EXPECTATIONS
8.1 Summary of Expectations
8.2 Lessons Learned
8.3 Independent Cost Estimates and Cost Reviews
Appendix A: Acronyms and Definitions
Appendix B: Summary of Federal Requirements
Appendix C: Summary of DOE Requirements
Appendix D: Generic Review Criteria
Appendix E: Example of the Calculation and Use of Economic Escalation
Appendix F: Example of Life-Cycle Cost Analysis
In addition to supporting an investment decision made in support of a Critical Decision, the LCCA should be considered a living document and updated often to reflect changes in scope, schedule, or budget. In this way, the LCCA is a valuable tool for v...
If the project sponsor expects alternatives to have differing performance levels (e.g., differing production rates, research and development throughput or quality), the project should monetize the performance levels to include them in the analysis of ...
Project Analysis
Example 3-1. Comparative Life Cycle Costs
Appendix G: Cost Estimate Classifications (AACE International)
Appendix H: References
Appendix I: DOE Recommendations for Quality Cost Estimates