DOE G 413.3-18, Integrated Project Teams Guide for Use with DOE O 413. 3A
Functional areas: Program Management, Project Management
This Guide provides those responsible for program and project management with the information and perspective needed to successfully implement the requirements of DOE O 413.3A relating to the use of integrated project teams to achieve improved project outcomes and efficiency.
Superseded By:
Version history and related documents
Superseded by
A newer version replaces this document.
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
AVAILABLE ONLINE AT: INITIATED BY:
www.directives.doe.gov National Nuclear Security Administration
DOE G 413.3-18
9-24-08
INTEGRATED PROJECT TEAMS GUIDE
FOR USE WITH
DOE O 413.3A
[This Guide describes suggested nonmandatory approaches for meeting requirements.
Guides are not requirements documents and are not to be construed as requirements in
any audit or appraisal for compliance with the parent Policy, Order, Notice, or Manual.]
U.S. Department of Energy
Washington, D.C. 20585
NOT
MEASUREMENT
SENSITIVE
DOE G 413.3-18 i (and ii)
9-24-08
CONTENTS
1.0 INTRODUCTION .............................................................................................................. 1
1.1 Applicability ........................................................................................................... 1
1.2 Sources of Information ........................................................................................... 1
1.3 Structure .................................................................................................................. 1
2.0 GUIDELINES ..................................................................................................................... 1
2.1 What Are IPTs ........................................................................................................ 1
2.2 The Underlying Rationale for IPTs ......................................................................... 2
2.3 Key Variables.......................................................................................................... 2
2.4 IPT Roles and Responsibilities ............................................................................... 4
2.5 Formation of the IPT ............................................................................................... 9
2.6 Membership and Structure ...................................................................................... 9
3.0 IPT PERFORMANCE ...................................................................................................... 16
3.1 Factors Influencing IPT Performance ................................................................... 16
3.2 Measuring the IPT’s Performance ........................................................................ 17
3.3 The Importance of IPTs to Project Success .......................................................... 19
ATTACHMENT 1. SAMPLE IPT CHARTER .............................................................................. 1
ATTACHMENT 2. AREAS HISTORICALLY REQUIRING CROSS ORGANIZATION
ALIGNMENT AT THE FUNCTIONAL DISCIPLINE LEVEL ....................................... 1
ATTACHMENT 3. REFERENCES ............................................................................................... 1
DOE G 413.3-18 1
9-24-08
1.0 INTRODUCTION
This Guide provides those responsible for program and project management with the
information and perspective needed to successfully implement DOE O 413.3A
requirements relating to the use of integrated project teams (IPTs) to achieve improved
project outcomes and efficiency.
1.1 Applicability
The Guide should be useful to Department of Energy (DOE) and the National Nuclear
Security Administration (NNSA) employees who are either assigned to or interface with
capital asset acquisition projects having a total project cost of $20 million or greater. It
should also be of value to external organizations under contract to the Department and
internal organizations that manage smaller projects.
Section 2
The Guide includes both requirement statements taken directly from DOE O 413.3A and
recommended procedures for implementing these requirements. Those instructions taken
from DOE O 413.3A are stated as “must” while recommended implementing procedures
are stated as “should”s. Should statements are not mandatory and are not to be construed
as requirements by those conducting compliance appraisals or reviews.
1.2 Sources of Information
The Guide draws upon: other DOE directives, best practices from different professional
fields, Office of Management and Budget (OMB) Circulars, Governmental
Accountability Office reports, research by the nation’s leading universities, Defense
Nuclear Facilities Safety Board publications and presentations, National Research
Council findings and recommendations pertaining to DOE, other government agencies
policies and practices, and lessons that have been learned from past project successes and
failures.
OMB recommendations should be given particular attention since their views are derived
from government wide studies of project management problems and have been
extensively field tested. All of the source material utilized has been cross checked to
ensure its validity and its applicability to DOE projects and programs.
1.3 Structure
Recent changes in the use of IPTs will be discussed and the classic “Who? What? When?
Where? Why? and How?” questions will be answered. Lessons learned are included
when applicable.
2.0 GUIDELINES
2.1 What Are IPTs
DOE O 413.3A requires that all projects establish IPTs led by a federal project director
(FPD). The order defines IPTs as “cross-functional groups of individuals organized for
2 DOE G 413.3-18
9-24-08
the specific purpose of delivering a project to an external or internal customer.”1 IPTs are
the crossroads where the technical, management, budgetary, safety, and security interest
meet.
2.2 The Underlying Rationale for IPTs
The IPT is the primary tool for breaking down the walls that can exist between different
organizations, different professions, and different levels within the different organizations
command structures. A successful IPT brings these diverse elements together to form a
unit that willingly shares information, balances conflicting priorities and ideologies, and
jointly plans and executes the project mission.
2.3 Key Variables
2.3.1 Variables That Impact the IPT
The membership and depth of an IPT is dependent on the following project variables:
size, cost, and complexity;
number of organizations involved and their geographical separation;
presence or absence of a management and operating contractor;
number of organization approvals needed;
degree of organizational independence;
type of the contractual relationships between organizations;
whether the different organizations and functional disciplines share a similar
objective;
level of technical challenge;
novelty of the design and construction;
FPD range and depth of knowledge;
FPD and IPT levels of the authority;
political and market conditions;
existence of a systems engineering office and/or a lead systems integrator;
1 DOE O 413.3A, Attachment 3, paragraph 19.
DOE G 413.3-18 3
9-24-08
budgetary and schedule constraints;
stakeholder involvement;
number and variety of operations performed in the facility;
types and quantities of material processed in the facility;
security classification;
whether the project is a “green field” undertaking or a modification;
Section 3
phase of development;
degree of consensus on methodology and what is an acceptable end product;
awareness and commitment of organization top management; and
risk to the public, workers and the environment [See Title 10 Code of Federal
Regulations (CFR) 830 for nuclear projects].
The relationship between these variables and the IPT’s membership ranges from obvious
to complex. It is fairly apparent that a greater number of functional disciplines will be
needed on large or technically challenging projects, as compared to smaller, less
technically challenging projects. Nuclear projects with accompanying security concerns
require more IPT members with higher skill and knowledge levels than would be needed
for conventional projects.
It is similarly apparent that larger projects almost always involve more customers/users
and more subcontractors and vendors that should be represented on the IPT.
The relationship between the variables such as the vertical command structure for the
project and the various organizations involved is more complex and can be difficult to
grasp. Complex, first-of-a-kind projects that involve unknowns, tradeoffs and input from
the different participants as the design process evolves need some form of partnering
arrangement among the organizations, command levels, and functional disciplines within
each organization. The IPT, when properly structured and used with the appropriate types
of contracts, is the means for fostering this partnership.
2.3.2 IPT Evolution over the Course of the Project
The composition of an IPT should, of necessity, evolve in parallel with the project, which
is a severe challenge at the concept definition stage. Each of the variables needs to be tied
down during this phase in order to determine the composition of the IPT, but it is the IPT
that would normally generate the information that is needed to tie down each of the
variables. This catch 22 dilemma can be resolved by forming an interim or initiating team
4 DOE G 413.3-18
9-24-08
that can explore each of the variables and simultaneously define the size and composition
of the IPT that is required to be established and chartered prior to Critical Decision 12.
The interim or initiating team should be made up of senior employees with prior
experience on similar project types and missions.
2.4 IPT Roles and Responsibilities
DOE O 413.3A, OMB’s Capital Programming Guide, and the O 413.3 series Guides
assign nearly a hundred roles and responsibilities to the IPTs. The more significant of
these are discussed below with accompanying insight regarding the extent to which each
focuses on an integration related objective and when each must be performed.
2.4.1 Supporting the Federal Project Director
The initial requirement imposed upon the IPT by DOE O 413.3A is to support the FPD3
by providing individual expertise to fill the voids in his or her knowledge base in the
areas of planning and implementing the project using a systems engineering approach4;
“meeting cost, schedule and performance targets,”5 and, “demonstrating initiative in
incorporating and managing an appropriate level of risk to ensure best value for the
government”6. Each of these tasks can be fully achieved only when undertaken from a
holistic frame of reference which considers and unites the views of all of the IPT
members.
2.4.2 Managing Environment, Health and Safety and Safeguards and Security
Section 4
The extent of the IPT’s roles and responsibilities for environmental, health, and safety
depends upon the project's Hazard Category and overall safety risks. The IPT must
identify, define and manage environmental, safety, health, security, and QA on all
projects7. It must also “ensure that safety is fully integrated into design and construction
for high-risk, high-hazard, and Hazard Category 1, 2, and 3 nuclear facilities.” 8Specific
products and activities for Hazard Category 1, 2, and 3 facilities and timetables for
delivery are defined in DOE Technical Standard (DOE-STD) 1189.
While these roles extend over the length of the project, the identification and definition of
requirements should include heavy IPT involvement in the period between CD-0 and
CD-1. Failure to define the requirements at this point in the project can result in costly
downstream rework and schedule delays.
2 DOE O 413.3A, Table 2.
3 DOE O 413.3A, paragraph 6m(1).
4 DOE O 413.3A, paragraph 6g(2).
5 DOE O 413.3A, paragraph 6g.
6 DOE O 413.3A, paragraph 6g.
7 DOE O 413.3A, paragraph 6m(4).
8 DOE O 413.3A, paragraph 6m(13).
DOE G 413.3-18 5
9-24-08
A highly integrated team effort should be employed to execute environmental, health, and
safety responsibilities. Many of these matters should be addressed simultaneously to
avoid having a solution in one area conflict with another. An example might be finding
satisfactory solutions to inherent conflicts between security and safety objectives.
Quality assurance decisions can also involve tradeoffs that can become contentious if not
considered from all frames of reference. OMB recommends that “if a commercial or
non-developmental item is procured, the IPT should consider using commercial quality
standards or the contractor’s quality system to ensure acceptability,” 9a recommendation
that is not tenable for nuclear facility projects governed by 10 CFR 830 Subpart A.
2.4.3 Acquisition Planning
Input from all members of the IPT is important for development of an integrated project
plan. DOE O 413.3A states that the IPT “develops a project contracting strategy”10 that
“conveys the IPT’s approach for the successful acquisition of the project, its intended
outcomes, and (the) rationale for the approach.”11 Development of the acquisition
strategy is ultimately a Federal responsibility that is supported by the IPT.
The OMB suggests market studies as part of developing the acquisition strategy as
follows.
With the decision to evaluate the feasibility of acquiring a capital asset,
management should provide the IPT with an estimate of the range of budget
resources that may be available for an asset. The IPT should conduct market
research to determine the feasibility of various capital asset alternatives that are
available in the market to satisfy the requirements. Emphasis should be placed on
generating innovation and competition from private industry and on the use of
commercial items and non-developmental items to meet the mission needs. The
IPT should determine: 1) availability; 2) affordability; 3) cost and benefits; 4)
sustainable design principles; and, 5) risk.12
“Once a clear agency need has been identified, the IPT should begin with a plan
to conduct both market surveillance and market research to ensure that as many
alternative solutions as possible are identified for consideration.”13
In market research, the IPT seeks information through research of published
information, talking to other agencies that have conducted similar market
research, and/or going directly to the market for information.14
Section 5
9 OMB Capital Programming Guide, paragraph II.10 pages 51 and 52.
10 DOE O 413.3A, paragraph 6m(2).
11 DOE O 413.3A, paragraph 5k(1).
12 OMB Capital Programming Guide, paragraph I.5, page 14
13 OMB Capital Programming Guide, paragraph I.5.1.2, page 16.
14 OMB Capital Programming Guide, paragraph I.5.1.1, page 15.
6 DOE G 413.3-18
9-24-08
“The IPT should engage potential suppliers in an advisory process in which the
government provides a general description of the scope or purpose of the
acquisition … and invites potential offerers to submit information…”15
OMB goes on to say:
Market surveillance is an on-going process. The IPT technical staff should keep
abreast of the latest capabilities and performance through trade journals,
advertisements, sales brochures, etc.16
At the beginning of the Acquisition Phase (which they define as the availability of
project funding) the IPT should re-assess the market capabilities to verify earlier
decisions as to whether a commercially available asset can be acquired or limited
(or full-scale) development work is needed.17
The IPT should also re-examine how it can make the most effective use of
competition and financial incentives.18
Post failure analyses of DOE projects have shown the importance of all OMB
recommended actions.
2.4.4 Other Project Planning Tasks
DOE O 413.3A does not specify the IPT’s roles and responsibilities for developing the
project execution and risk management plans. It is recommended that the IPT be heavily
involved in both in support of the FPD. To be of real value, both documents should
integrate varied knowledge bases and frames-of-reference and should be developed in
unison with the acquisition strategy, for which the IPT is responsible.
2.4.5 Defining Technical, Schedule, and Cost Parameters
According to DOE O 413.3A, the IPT must “identify and define appropriate and adequate
project technical scope, schedule, and cost parameters”19 as one of its roles and
responsibilities. This requirement dovetails with the following OMB recommendations:
“If current assets cannot bridge the gap between planned and actual performance
the IPT should define the gap in terms of performance requirements to be
achieved. Depending on the depth of the analysis of program requirements during
the first round of strategic planning, the IPT may wish to define more detailed
15 OMB Capital Programming Guide, paragraph I.5.1.2, page 16.
16 OMB Capital Programming Guide, paragraph I.5.1.1, page 15.
17 OMB Capital Programming Guide, paragraph II.1, page 32.
18 OMB Capital Programming Guide, paragraph II.1, page 32.
19 DOE O 413.3A, paragraph 6m(5).
DOE G 413.3-18 7
9-24-08
requirements against which they can evaluate options for reducing the
performance gap.”20
“It is incumbent upon the agency IPT to clearly define the performance
requirements and estimated costs for major acquisitions before RFPs are
issued.”21
“The IPT must also develop sound cost estimates. . . .”22
“The IPT must ensure that the proposals and in-house estimates clearly recognize
the amount and impact of risk on cost, schedule and technical effort.”23
Thus, the IPT is responsible for identifying the functional and operational requirements,
alternative approaches, the level of resources needed to undertake them, and the optimal
path forward.
2.4.6 Managing Interfaces
Section 6
DOE O 413.3A assigns the IPT the responsibility to “ensure project interfaces are
identified, defined, and managed to completion.”24 DOE G 413.3-1, Managing Design
and Construction Using Systems Engineering, provides detailed information relating to
this responsibility.
2.4.7 Overseeing Project Performance
DOE O 413.3A requires that the IPT:
“Perform periodic reviews and assessments of project performance and status
against established performance parameters, baselines, milestones, and
deliverables.”25
“Plan and participating in project reviews, audits, and appraisals as necessary.”26
“Participate, as required, in operational readiness reviews or readiness
assessments.”27
“Review change requests (as appropriate) and support change control boards as
requested."28
20 OMB Capital Programming Guide, paragraph I.3, page 10.
21 OMB Capital Programming Guide, paragraph II.4, page 44.
22 OMB Capital Programming Guide, paragraph I.2.1 page 9.
23 OMB Capital Programming Guide, paragraph II, page 31.
24 DOE O 413.3A, paragraph 6m(3).
25 DOE O 413.3A, paragraph 6m(6).
26 DOE O 413.3A, paragraph 6m(7).
27 DOE O 413.3A, paragraph 6m(11).
8 DOE G 413.3-18
9-24-08
The IPT, therefore, should have a lead role in change control.
OMB expands upon the DOE O 413.3A requirement that the IPT review change requests,
adding that the IPT prepares an analysis of the estimated changes in cost, schedule, and
performance goals if the existing goals will not be achieved and determines the reasons
for cost, schedule or performance deviations and evaluates whether the corrective actions
are likely to be effective.29
When all four of the IPT’s performance oversight responsibilities are viewed in total, it
becomes obvious that the IPT serves as DOE’s primary tool for tracking and controlling
project progress and that the members of the IPT should be skilled in recognizing the
early warning signs of an emerging performance problem. The need for the IPT to have
this, and other, project management skills is addressed in section 2.6.2.
2.4.8 Reviewing and Approving Project Deliverables
The IPT has responsibility for reviewing, and in some instances, approving key
deliverables. They are to:
“Review all Critical Decision packages and recommend approval/disapproval.” 30
“Review and comment on project deliverables (e.g., drawings, specifications,
procurement, and construction packages).”31
“Support preparation, review, and approval of project completion and closeout
documentation.”32
It is important not to underestimate the time and personnel needed to perform each
review. The best approach from a manpower leveling, rework avoidance, and a schedule
standpoint is for the IPT to utilize a “rolling wave” concept wherein prior to allowing
design to begin, they ensure that:
all system and component level functional and operating requirements have been
identified, checked and approved;
the full design criteria for the structures, systems, and components (including all
applicable codes and standards) have similarly been identified, checked and
approved; and
the methods that will be used to demonstrate at each review point that
deliverables will achieve the above are specified and agreed upon by all parties.
28 DOE O 413.3A, paragraph 6m(10).
29 OMB Capital Programming Guide, paragraph II.9.1, page 50.
30 DOE O 413.3A, paragraph 6m(8).
31 DOE O 413.3A, paragraph 6m(9).
32 DOE O 413.3A, paragraph 6m(12).
DOE G 413.3-18 9
9-24-08
Section 7
Reviews and compliance demonstrations can also be approached from a “rolling wave”
concept wherein non-interdependent components or elements are reviewed in advance of
the systems. These “rolling wave” approaches can cut significant time off of the review
process and shorten the total cost and duration of the project by reducing rework.
The FPD should ensure that IPT members do not review their own work. It is acceptable
for an IPT member to review products that others in their company have produced as
long as the IPT member is not in the same chain of command as the group that developed
the product being reviewed.
2.5 Formation of the IPT
DOE O 413.3A requires that the IPT t be established and chartered no later than CD-1.33
Many of the IPT’s roles and responsibilities should, however, either be performed
concurrently with or precede CD-1 approval. For example, conceptual designs should not
precede development of the Acquisition Strategy, Project Execution Plan, or Risk
Management Plan. Similarly; the IPT should be fully functional in advance of CD-1 to
fulfill its obligations for managing environmental, health, and safety; defining technical,
schedule, and cost parameters; managing interfaces; and overseeing and reviewing
project activities prior to CD-1.
Paragraph 5k(5) of DOE O 413.3A seems to support the importance of having the IPT in
place prior to CD-1 as an essential element in DOE’s acquisition process and is used
during all phases of a project’s life cycle and then goes on to state that “the Federal
Project Director and the team will prepare and maintain a Team Charter…”
The OMB also endorses the establishment of the IPT at the initiation of major
acquisitions and indicates that the IPT should define the performance requirements to be
achieved and the Work Breakdown Structure during the earliest stage of the planning
phase.34
2.6 Membership and Structure
2.6.1 Composition of the IPT
OMB recommends that an IPT include:35
a qualified program manager and contracting officer;
personnel with expertise in architecture, budget, capital planning, contract
oversight, cost estimating, financial, earned-value management, project
management, procurement, risk management, sustainability, scheduling, security,
technical, information resource, and value management skills; and
33 DOE O 413.3A, Table 2, page 12.
34 OMB Capital Programming Guide, paragraph I.2.1, page 10 and paragraph I.3, page 10.
35 OMB Capital Programming Guide, paragraph I.2.1, page 9.
10 DOE G 413.3-18
9-24-08
those that will use the project after it is completed.
The list of those that should be considered for membership on complex or nuclear
projects goes beyond OMB's. It includes:
design disciplines (civil, structural, electrical, instrumentation, etc.)
health physics and radiological protection
safety, accident, or risk analysts
criticality safety
process and equipment research and development specialist
process chemistry
industrial safety
fire protection
emergency preparedness
environmental protection and waste management
human factors
interfacing system representatives
seismic/geotechnical
Other lists add the following functional disciples that may need to be included:
safeguards and security
high performance sustainable building experience
configuration management
human resources
document control
legal
communications
permitting
DOE G 413.3-18 11
9-24-08
transportation safety
Section 8
emergency protection
startup testing
system design descriptions
conduct of operations
maintenance
operational readiness
equipment lay-up
commissioning
quality assurance
Counterintelligence and Intelligence
NQA-1 auditors and inspectors
Functional disciplines represented on the IPT should be determined based on the project
and should include the manufacturing, construction, and support expertise needed.
2.6.2 IPT Member Qualifications
Studies have shown the importance of ensuring that IPT members have the education,
experience, and training necessary to meet the specific project demands, which
DOE O 413.3A refers to as “competence commensurate with responsibility.”
The following DOE 450-series directives on Integrated Safety Management are good
resources for understanding the concept:
DOE P 450.4, Safety Management System Policy, dated 10-15-96.
DOE M 450.4-1, Integrated Safety Management System Manual, dated 11-1-06.
DOE G 450.4-1B Volume 1, Integrated Safety Management System Guide
(Volume 1) for use with Safety Management System Policies (DOE P 450.4,
DOE P 450.5, and DOE P 450.6); The Functions, Responsibilities, and
Authorities Manual; and the DOE Acquisition Regulation, dated 3-1-01.
These directives collectively add that both federal and contractor personnel should
“possess the experience, knowledge, skills, and abilities that are necessary to discharge
their responsibilities.”
12 DOE G 413.3-18
9-24-08
The specific experience, knowledge, skills, and abilities that both the DOE and contractor
members should have are broader than typically realized. Both functional area and
project skills are essential for project success.
2.6.2.1 Functional Discipline Qualifications
IPT members should be well-versed in the functional disciplines they represent.
DOE has institutionalized a formal certification process to help ensure that the correct
match of functional discipline abilities is achieved, on the Federal side of the ledger, for
at least one category of projects. This process is titled the Federal Technical Capability
Program. It applies to all defense nuclear facility projects and is explained in DOE P
426.1 and DOE M 426.1-1A. The specific functional area competency requirements
associated with the Federal Technical Capability Program are contained in the following
Standards:
Radiation Protection (DOE-STD-1107)
Electrical Systems (DOE-STD-1170)
Instrumentation and Control (DOE-STD-1162)
Fire Protection (DOE-STD-1137)
Industrial Hygiene (DOE-STD-1138)
Quality Assurance (DOE-STD-1150)
Environmental Compliance (DOE-STD-1156)
Facility Representative (DOE-STD-1151)
Waste Management (DOE-STD-1159)
Occupational Safety (DOE-STD-1160)
Mechanical Systems (DOE-STD-1161)
Deactivation and Decommissioning (DOE-STD-1166)
Safeguards and Security (DOE-STD-1171)
Safety Software Quality Assurance (DOE-STD-1172)
Criticality Safety ( DOE-STD-1173)
Chemical Processing (DOE-STD-1176)
DOE G 413.3-18 13
9-24-08
Technical Program Manager (DOE-STD-1178)
Construction Management (DOE-STD-1180)
Facility Maintenance Management (DOE-STD-1181)
Civil Structural Engineering (DOE-STD-1182)
Nuclear Safety (DOE-STD-1183)
Field element managers, Principal Secretarial Officers, and the Administrator of the
National Nuclear Security Administration designate positions and/or individuals in their
organizations that will participate in the program and certify the competency of these
individuals following verification of their competency.
Section 9
Principles of the Federal Technical Capability Program designated for Defense Nuclear
Facilities are effective and can be employed in other projects. The program acknowledges
that individuals within any of the covered competency areas may possess anywhere from
“familiarity level” to “expert level” knowledge of particular subtopics within their
domains, and that fact is germane when selecting IPT members.
DOE O 413.1A requires that the Chiefs of Defense Nuclear Safety and Nuclear Safety
“validate that Federal personnel assigned to the IPT as nuclear safety experts are
appropriately qualified.”36 This validation is limited to Hazard Category 1, 2, and 3
nuclear facilities and is normally performed as part of the technical independent project
review required for Critical Decision 1, but it can be performed when the IPT is
established.
DOE quality assurance directives and 10 CFR 830 Subpart A can also come into play in
regards to the functional area qualifications of the IPT members. DOE O 414.1C
specifies that each DOE and contractor organization must develop and implement a
quality assurance program that addresses actions taken to “train and qualify personnel to
be capable of performing assigned work.”
DOE G 414.1-2A goes on to state that “personnel should be qualified based on—
previous experience, education, and training;
performance demonstrations or tests to verify previously acquired skills;
completion of training or qualification programs; and/or
on-the-job training.”
36 DOE O 413.3A, paragraph 6o(5).
14 DOE G 413.3-18
9-24-08
2.6.2.2 Project Area Qualifications
DOE G 414.4.1-2 also suggests the project area knowledge, skills, and abilities that the
IPT members should possess. It states:
“Project/task-specific training should impart the knowledge required for personnel to
perform their assigned duties safely and successfully. This training may include
project-task goals and schedules, implementing procedures, safety and hazard controls,
methods, requirements, process metrics, and skills. Project/task-specific training
requirements should be defined by project managers.”
The goal of project/task specific training is to ensure that each IPT member has at least:
a working level knowledge of the project’s mission and how this mission relates
to the sponsoring program;
a working level knowledge of the procedures IPTs normally utilize in fulfilling
each of their assigned roles and responsibilities;
a working level knowledge of the Department’s project management directives;
a familiarity level knowledge of non-project management directives that could
impact the project;
a working level ability to communicate findings and recommendations.
2.6.3 Stakeholder Involvement
Both private and public sector IPTs seek input from customers (i.e., the owners and user
community); constructors; key suppliers; regulators; supporting functions; and,
non-governmental interest groups that may be impacted by or have impact on the
eventual outcome of the project. Although this input is necessary for the planning
process, it should be recognized that, other than the owner, stakeholders are seldom
responsible for cost or schedule and may have little incentive to compromise or look
beyond their own self interests. The challenge is to find a method of involving these
groups without losing sight of the key concept that IPTs seldom find a means of
satisfying all of the stakeholders desires and can only be effective when the members
focus on what is best for the project from a combined frame-of-reference.
Section 10
2.6.4 Organization and Structure
The need to integrate many different functional disciplines, organizations, and
stakeholders views and knowledge creates a significant organizational problem for the
IPT. Having more people on the team means a broader and deeper pool of knowledge,
but it also means more opinions to reconcile, increased time spent distributing
information, and an increased likelihood that not all of the members will be heard. IPTs
normally become ineffective if they are made up of more than 25 members, which is far
DOE G 413.3-18 15
9-24-08
fewer than the number of functional disciplines and organizational representative
involved in even a medium sized DOE project.
This problem can be eased slightly by finding members with multi-discipline functional
knowledge and skill. However, this does not provide a complete solution.
The appropriate approach, for most projects, is to create a core IPT at the federal level
with supporting sublevel IPTs within each of the major contractor organizations and
satellite IPTs or subcommittees for special focus areas that are challenging enough to
warrant the participation of both DOE and contractor subject matter experts. Each
sublevel or satellite IPT should retain a cross-functional/cross organizational composition
and should be led by a member of the core IPT. DOE-STD-1189 describes how a
sublevel IPT (the safety design integration team) should be utilized on a Hazard Category
1, 2, or 3 project.
The need for sublevel and satellite IPTs should be determined by the core IPT as it
develops project planning documents. Sublevel and satellite IPTs typically have shorter
periods of existence than the core IPT and differ in membership and seniority (with the
exception of the leads). This makes them easier to staff, since they do not involve the
same level of commitment as the IPT.
2.6.5 The IPT Charter
DOE O 413.3A indicates that with the IPT support, the FPD is responsible for preparing
and maintaining the IPT’s charter and operating guidance.37 The charter defines the level
of decision-making authority to be delegated to the IPT. An example of an IPT charter is
provided in Attachment 1.
The appropriate level of decision-making authority to be devolved to the IPT should
depend on both the project’s phase and IPT performance factors that will be described in
Section 3; therefore, it is recommended that the charter be updated and reissued at each
Critical Decision. This approach allows the charter to identify both the specific
challenges/issues that the IPT should focus on during the upcoming phase and their level
of decisional authority relating to that challenge/issue. It also provides the acquisition
executive and the FPD valuable insight into the quality and quantity of IPT members that
will be required for the upcoming phase prior to Critical Decision approval.
The FPD will need the core IPT’s input to accurately identify the challenges/issues and
their accompanying staffing requirements. This input may involve contractual questions
and must, therefore, be coordinated with the Contracting Officer.
2.6.6 Contractor Participation
The management and operating contractor’s project manager and the
architect/engineering firm’s project manager should both be members of the core IPT.
37 DOE O 413.3A, paragraph 6g(11).
16 DOE G 413.3-18
9-24-08
Section 11
While they must be excluded from some duties that can only be performed by the Federal
members, direct federal and contractor collaboration is desirable on the bulk of the IPTs
roles and responsibilities. The term IPT was, in fact, originally coined by the Department
of Defense to differentiate joint federal/contractor teams from their previous, federal
only, “project teams.”
The leads for any other contractor IPTs, or satellite IPTs should also be members of the
core IPT to ensure direct communications between the IPTs. The lack of such direct
communications negates the rationale for IPTs. Direct communications between the
organizations is particularly important when dealing with topics such as nuclear safety
that have historically been prone to misalignment. A partial list of the nuclear safety areas
that have proven to be the most troublesome in this regard is provided as Attachment 3. It
is recommended that the functional discipline members responsible for each of these
areas within each organization form either separate working groups or satellite IPTs to
assist the alignment process.
In keeping with this line of thought, both the private sector and the Department of
Defense have now expanded the concept of multi-organizational IPTs even further and
are including key subcontractors and suppliers on their IPT. The government receives the
greatest advantage from this approach when these participants can be engaged early in
the design process, but this is only appropriate in selected cases, and can only be done
within the bounds of the procurement regulations so as not to provide the representatives
with an unfair competitive advantage.
From experience with multi-organizational IPTs the Department of Defense has found
that the ratio between federal and contractor personnel needs to be kept in reasonable
balance. It is important that DOE profit from this experience and not turn the reins of the
IPT over to contractors that may not share the same objectives as the federal government.
3.0 IPT PERFORMANCE
3.1 Factors Influencing IPT Performance
The degree of IPT success depends upon numerous factors, the most critical of which are
addressed below.
3.1.1 Staffing
GAO and internal reviews consistently reveal a significant shortage of vital functional
discipline members and skill levels. These functional discipline shortages are not
confined to DOE, but are government wide. Projects should be vigilant of such capability
gaps and augment federal staff with contractor support where appropriate.
3.1.2 Personnel Utilization
Finding an adequate number of functional discipline members to fill the IPT organization
chart does not guarantee an end to the staffing challenge. Independent reviews of failing
DOE G 413.3-18 17
9-24-08
projects often show that some matrix support members are “phantoms” who generally
attend a few meetings and then drift away because of time issues, competing work
demands, a lack of clearly defined work assignments, or a perceived lack of authority.
It is the FPD’s responsibility to ensure these situations do not occur. Research has
repeatedly indicated that IPTs are successful only when they are given clear roles to
perform and authority commensurate with these roles.
Projects of longer duration can relieve the problem of name-only participation by either
having the core IPT members reassigned to the project or by entering into formal
agreements with IPT members’ parent organizations to guarantee a specific level of
commitment.
Section 12
3.1.3 Team Distribution
Physically collocated IPTs bond into a seamless unit more quickly and successfully, than
physically distributed teams. OMB states, “Agencies should strongly consider co-locating
the IPT …”38 While electronic communications can partially offset the problems of
physical separation, face-to-face communication is a strong basis for developing
esprit-de-corps. It is particularly important that funding be available to allow virtual
teams to come together physically for at least a period of time at the start of the project to
melt barriers that may exist and arrive at a shared vision.
3.1.4 Federal Project Director Leadership
The act of assigning people to a cross-functional/cross-organizational group does not
automatically create an IPT. Each IPT member comes with his or her own values, biases,
and priorities. The FPD should not wait passively for collaboration to occur but should be
diligent in making the members aware of their inter-dependencies and collective
interests; showing how each member contributes to the projects mission; communicating
the importance of that mission; and, by rotating lead responsibility within the IPT based
upon which member has the most knowledge and capability of the subject being
addressed.
3.2 Measuring the IPT’s Performance
There are three ascending levels of IPT success. Starting at the lowest level, they occur
when the IPT arrives at a common vision or goal, when individual members or
organizations are able to align their efforts so that no one is working at cross purposes,
and when the team can draw upon each person’s or organization’s unique perspective to
see challenges and solutions that were not apparent from any singular frame-of-reference.
This third level of performance is difficult to reach but essential when undertaking a
large, complex project.
38 OMB Capital Programming Guide, paragraph I.2.1, page 9.
18 DOE G 413.3-18
9-24-08
An experienced observer can tell almost immediately what level of performance
an IPT has reached by simply watching how the members approach an issue or
task. A few of the more obvious indicators of level one or two performance are:
meeting attendance and participation;
the amount of positive energy members display;
whether members appear to like what they are doing and the other members of the
team with whom they are working;
absence of personality conflicts;
open communication between team members;
whether communication is directed toward creating a common understanding or
advocates a member’s personal views and priorities;
degree of alignment on early trade-offs relating to project requirements, priorities,
strategies, etc;
the extent to which members reflect ownership of assigned and unassigned tasks;
and
whether the team has correctly identified the barriers to project and team success
and focused their efforts towards the elimination of these barriers.
It is necessary to look beyond the surface indicators of consensus when assessing an
IPT’s performance level. What appears to be consensus may, if fact, be no more than
passive submission of some members or “group-think.” Both are indicators that the
project is headed in a negative direction.
Section 13
While there are relatively few ways to foresee an IPT’s potential for reaching the third
level of performance at the early stages of a project, there is a simple and highly reliable,
indicator that can be utilized within the first week to determine the IPT’s potential for
moving beyond the second level. That indicator is the individual member’s willingness to
seek out and utilize lesson learned from other projects. Team members that are not
willing to learn from similar projects are unlikely to willingly listen to, and learn from,
their fellow team members and will, by definition, never reach the third level of
performance.
The FPD is confronted with a difficult decision if an individual that has just been brought
on board as one of the core IPT members clearly rejects the concept of utilizing lessons
learned. Either the team member must be replaced or the FPD must accept the very real
risk that that team member will prevent the entire IPT from rising above the second level
of performance. The correct decision on most complex projects is to find a replacement,
DOE G 413.3-18 19 (and 20)
9-24-08
even if that replacement has less talent or experience within their particular functional
discipline.
3.3 The Importance of IPTs to Project Success
It is the IPT that actually implements the bulk of the procedures laid out in
DOE O 413.3A. Studies consistently show a strong positive correlation between the
strength of the IPT and project success and failure. This correlation increases with each
of the key variables identified in Section 2.3. The simple truth is, large, complex,
technically challenging projects involving multiple stakeholders and tight budgetary,
schedule, and safety constraints have a minimal chance of succeeding without an equally
competent and committed IPT. The various organizational and functional elements of the
project will not come together unless the IPT works together.
SAMPLE IPT CHARTER
(Appendix A of the Sample Charter is not included in this Guide)
DOE G 413.3-18 Attachment 1
9-24-08 Page 1
Attachment 1 DOE G 413.3-18
Page 2 9-24-08
DOE G 413.3-18 Attachment 1
9-24-08 Page 3
Attachment 1 DOE G 413.3-18
Page 4 9-24-08
DOE G 413.3-18 Attachment 1
9-24-08 Page 5
Attachment 1 DOE G 413.3-18
Page 6 9-24-08
DOE G 413.3-18 Attachment 1
9-24-08 Page 7
Attachment 1 DOE G 413.3-18
Page 8 9-24-08
DOE G 413.3-18 Attachment 1
9-24-08 Page 9
Attachment 1 DOE G 413.3-18
Page 10 9-24-08
DOE G 413.3-18 Attachment 2
9-24-08 Page 1
AREAS HISTORICALLY REQUIRING CROSS ORGANIZATION
ALIGNMENT AT THE FUNCTIONAL DISCIPLINE LEVEL
Safety-class and safety-significant fire protection systems.
Adequacy of water supplies
Fireproofing of structural steel
Degradation of HEPA filters
Combustible loadings
Fire detection and suppression system activation mechanisms
Hydrogen and flammable gas generation accumulation in systems and
components.
Seismic
Ground motion
Adequacy of geotechnical investigations
Soil settlement
Structural engineering
Soil-structure interaction analyses
Load paths for seismic and settlement induced forces.
Finite element analysis
Structural computer codes
Confinement strategy
Analysis of the adequacy of the confinement barriers
Magnitude of the radiological source term
Models
Criticality standards
Chemical process safety
Attachment 2 DOE G 413.3-14
Page 2 9-24-08
Definition, selection, and implementation of quality assurance requirements
Section 14
Potential for solids settlement in pipes and ducts
Application of lessons learned
Assumptions bases
Degree of conservatism
Timely verification/confirmation
The technical defensibility of calculations and designs.
Nuclear safety basis documentation
DOE G 413.3-18 Attachment 3
9-24-08 Page 1
REFERENCES
Browning, Tyson R., Multi-Team Integration: Interdependence and Integrative
Mechanisms, Proceedings of the Sixth Annual International Symposium of INCOSE,
7/96.
Caruso, Rogers, & Bazerman, “Leading and Creating Collaboration in Decentralized
Organizations,” Harvard Business School Working Knowledge, 5/07.
Cooke, Salas, & Kiekel, Advances in Measuring Team Cognition, Undated.
Cooke, Salas, & Stout, “Measuring Team Knowledge,” Human Factors #42, 2000.
Construction Industry Institute, IR 113-3, Alignment During Pre-Project Planning: A
Key to Project Success, 8/05.
Construction Industry Institute, TAL 113-31, Development and Alignment of Project
Objectives, 11/04.
Construction Industry Institute, RR105-11, Team Building: An Assessment Tool for
Improving Team Communications, 1/97.
Construction Industry Institute, RS105-1, Compass: An Assessment Tool for
Improving Team Communications, 12/96.
DOD Guide, Integrated Product and Process Development, 2/96.
DOD Guide, Rules of the Road - A Guide for Leading Successful Integrated Product
Teams, 10/09.
GAO, Report 01-510, Best Practices - DOD Teaming Practices Not Achieving
Potential Results, 4/01.
GAO, Report 08-745, Coast Guard - Change in Course Improves Deepwater
Management and Oversight, but Outcome Still Uncertain, 6/08.
GAO, Report 04-380, Contract Management: Coast Guard's Deepwater Program
Needs Increase Attention to Management and Contractor Oversight, 3/04.
GAO, Report 07-380, Defense Acquisitions - Role of Lead Systems Integrator on
Future Combat Systems Program Poses Oversight Challenge, 6/07.
Hackman, J.R., Leading Teams: Setting the Stage for Great Performances, 2002.
Huckman, Staats, & Upton, Team Familiarity, Role Experience, and Performance,
Harvard Business School Working Knowledge, 10/07.
Attachment 2 DOE G 413.3-14
Page 2 9-24-08
Katzenbach & Smith, The Wisdom of Teams, 1993.
MIT (Bernstein), Multidisciplinary Design Problem Solving on Product Development
Teams, 2/01.
MIT (Browning), RP97-01-19, Systematic IPT Integration in Lean Development
Programs, 2/97.
MIT (Bresman), Learning Strategies and Performance in Organizational Teams, 2/05.
MIT (Dare), Stakeholder Collaboration in Air Force Acquisition: Adaptive Design
Using System Representations, 6/03.
MIT (Flores), Organizational Team Characteristics That Enable Successful Projects at
NASA - A Framework for the Future, 6/01.
MIT (Mostashari), Stakeholder-Assisted Modeling and Policy Design Process for
Engineering Systems, 6/05.
MIT (Oehmen), Approaches to Crisis Prevention in Lean Product Development By
High Performance Teams and Through Risk Management, 9/05.
MIT (Stanke), Creating High Performance Enterprises, 9/06.
MIT (Tondreault), Improving the Management of System Development to Produce
More Affordable Military Avionics Systems, 2/03.
MIT (Utter), Performing Collaborative, Distributed Systems Engineering: Lessons
Learned, 2/07.
National Defense University, Acquisition for the 21st Century, 1999.
Parker, Glenn, Cross-Functional Teams - Working with Allies, Enemies, and Other
Strangers, 1994.
Project Management Institute (Bourgault), How's Your Distributed Team Doing? 10
Suggestions from the Field, Undated.
Project Management Institute (Hecker), Setting Up and Managing Integrated Project
Teams, 2000.
Project Management Institute (Verma), Managing the Project Team: The Human
Aspects of Project Management, Volume Three, 1997.
Shonk, James, Team-Based Organizations - Developing a Successful Team
Environment, 1992.