DOE G 413.3-11, Project Management Lessons Learned
Functional areas: Program Management, Project Management
The guide supports DOE O 413.3A, Program and Project Management for the Acquisition of Capital Assets, and aids the federal project
directors and integrated project teams in the execution of projects.
Superseded By:
DOE N 251.109, Cancellation of DOE G 413.3-11 on Nov 09, 2011
Version history and related documents
Superseded by
A newer version replaces this document.
- DOE N 251.109Cancellation of DOE G 413.3-11 (Nov 09, 2011)
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
AVAILABLE ONLINE AT: INITIATED BY:
www.directives.doe.gov Office of Engineering and Construction Management
DOE G 413.3-11
8-5-08
PROJECT MANAGEMENT
LESSONS LEARNED
(This Guide describes suggested non-mandatory approaches for meeting requirements.
Guides are not requirements documents and are not to be construed as requirements in
any audit or appraisal for compliance with the parent Policy, Order, Notice or Manual)
U.S. DEPARTMENT OF ENERGY
Washington, D.C. 20585
NOT
MEASUREMENT
SENSITIVE
DOE G 413.3-11 i (and ii)
8-5-08
FOREWORD
This Department of Energy (DOE) Guide is for use by all DOE elements. Specifically, this
Guide is written to aid the federal project directors and their integrated project team members
during the execution of projects.
Beneficial comments (recommendations, additions, and deletions) and any pertinent data that
may improve this document should be sent by letter or by sending the self-addressed
Standardization Document Improvement Proposal (DOE F 1300.3) to—
Director, Office of Policy
U.S. Department of Energy
Washington, DC 20585
This Guide is intended to provide approaches for implementing the project management lessons
learned requirements of DOE O 413.3A, Program and Project Management for the Acquisition
of Capital Assets, dated 7-28-06. DOE Guides, which are part of the DOE Directives Program,
provide supplemental information for fulfilling requirements contained in rules, regulatory
standards, and DOE directives. Guides do not establish or invoke new requirements nor are they
substitutes for requirements.
DOE G 413.3-11 iii (and iv)
8-5-08
CONTENTS
SECTION I. INTRODUCTION .................................................................................................. I-1
1. GOAL ............................................................................................................................... I-1
2. SCOPE .............................................................................................................................. I-1
3. OBJECTIVES ................................................................................................................... I-1
4. APPLICABILITY ............................................................................................................. I-2
5. PROFESSIONAL DEVELOPMENT UNITS .................................................................. I-2
6. DEFINITIONS .................................................................................................................. I-2
SECTION II. ROLES AND RESPONSIBILITIES .................................................................. II-1
1. DOE SENIOR MANAGER ............................................................................................ II-1
2. CORPORATE CHAMPION .......................................................................................... II-1
3. GATEKEEPER ............................................................................................................... II-1
4. ORGANIZATION COORDINATORS .......................................................................... II-2
5. PROGRAM OFFICE ...................................................................................................... II-2
6. PROJECT/SITE CONTROLLERS ................................................................................ II-2
7. PROJECT MANAGEMENT EXPERT (PME) .............................................................. II-2
8. INTEGRATED PROJECT TEAM ................................................................................. II-2
9. DOE ENTERPRISE........................................................................................................ II-2
Section 2
SECTION III. ELEMENTS AND INTERFACES .................................................................. III-1
SECTION IV. CONTENT ....................................................................................................... IV-1
SECTION V. PROCESS ........................................................................................................... V-1
1. CAPTURE ...................................................................................................................... V-1
2. CHECK ........................................................................................................................... V-1
3. LEARN ........................................................................................................................... V-1
4. CLOSE ............................................................................................................................ V-1
ATTACHMENT 1. PROJECT MANAGEMENT LESSONS LEARNED PROCESS
BY STAGE ..................................................................................................................................... 1
ATTACHMENT 2. PROJECT MANAGEMENT LESSONS LEARNED PROCESS
BY RESPONSIBILITY .................................................................................................................. 1
ATTACHMENT 3. REFERENCES ............................................................................................... 1
DOE G 413.3-11 I-1
8-5-08
SECTION I. INTRODUCTION
1. GOAL. The goal of this Guide is to encourage compiling and disseminating project
management lessons learned as part of effective project management practices
encompassing the project lifecycle, Critical Decision 0 to Critical Decision 4, as a viable
method of identifying issues and opportunities that influence successful project
execution. This information should be collected, reviewed and promptly distributed to all
affected programs throughout the Department/DOE Enterprise to aid in achieving the
Department goal of improving overall project management performance. However,
identification alone is insufficient to promulgate change in Department operations. Each
negative lesson learned should be evaluated for appropriate corporate/program actions to
prevent the recurrence of the situation. The Department also gains credibility for effective
project management when, as a learning organization, positive project performance is
realized. The contractor project management organizations and their subcontractors have
the opportunity to enhance their performance as well.
2. SCOPE. This Guide can enable federal project directors and contractor project managers
to capture, check, learn, and close lessons learned during the execution of Department
projects. It suggests a logical process for an implementation program from Critical
Decision-0 to Critical Decision-4. DOE G 413.3A-11 is not intended to duplicate or
conflict with DOE O 210.2, DOE Corporate Operating Experience Program, dated
6-12-06. This Guide is specifically for Project Management Lessons Learned associated
with the non-operational phase of a facility during construction. Lessons Learned that fall
within the applicable category of DOE O 210.2 should follow requirements.
3. OBJECTIVES. The objective of this Guide is to suggest a results-based system by
capturing Department-wide knowledge, validating its applicability and its correctness,
creating a learning platform and recalling relevant lessons for cross-pollination. This
includes:
Section 3
a. helping to curtail repeated mistakes during project execution and providing a
conduit for transmitting information to all active organizations;
b. defining a methodology for capturing applicable data;
c. providing a positive closure process for implementation;
d. providing a means to publish lessons learned for DOE Enterprise-wide
dissemination;
e. providing the ability to retrieve information that will enable federal project
directors and contractor project managers to accomplish and support the DOE
mission, specifically related to projects, in a cost effective and timely manner;
f. defining the program's critical elements.
I-2 DOE G 413.3-11
8-5-08
4. APPLICABILITY. This Guide may apply to all DOE elements, including the National
Nuclear Security Administration (NNSA), which fund, direct and manage acquisition
projects as defined by DOE O 413.3A.
This Guide may be applicable to all projects managed by or for DOE in accordance with
DOE O 413.3A and should include Facility and Infrastructure Recapitalization Program
(FIRP) projects, general plant projects (GPPs), capital equipment projects (CEPS), line
item projects, environmental management cleanup projects, operations expense funded
projects (OP-EX), and work-for-others (WFO) projects. In order to improve performance
and credibility across the DOE, every project (from conception to completion) can
benefit from the application of this Guide. Therefore, the program utilized for the
Department should capture both the positive and negative lessons during project
execution. It is equally important to publicize both positive and negative lessons.
The provisions in the Guide are DOE’s views on acceptable methods of program
implementation and are not mandatory. Alternative methods that are demonstrated to
provide an equivalent or better level of performance are acceptable. DOE encourages
contractors to go beyond minimum requirements and to pursue excellence in their
programs.
The words “should “and “may” are used to denote optional program recommendations
and allowable alternatives, respectively.
5. PROFESSIONAL DEVELOPMENT UNITS. Continuous improvement in project
management cannot occur without sharing these lessons. Internal and external to DOE,
project management certification and maintaining continuing education is important for
the Project Management Career Development Program and the Project Management
Professional Credentials administered through the Project Management Institute,
respectively. Continued education units can be obtained several ways, including the
generation of valuable lessons learned. For each lesson learned entered into the DOE
Enterprise database and endorsed, one continued education unit can be earned (up to a
maximum of 15). Once the lessons learned is endorsed, an individual can file for credit
through the accrediting agent.
6. DEFINITIONS.
a. Project Management Lessons Learned. A work practice or innovative approach to
project management that is captured and shared to promote repeat application or
an adverse work practice or experience that is captured and shared to prevent
recurrence.
b. Improvement Actions. Specific activities in response to a project management
lesson learned. Actions should have a responsible individual assigned for
completion and a proposed due date. Resolution does not constitute direction to
the DOE contractors. Contracting officers or the appropriate technical
representative should be consulted before any direction is given to a contractor
about implementation of an improvement action.
Section 4
DOE G 413.3-11 II-1
8-5-08
SECTION II. RECOMMENDED ROLES AND RESPONSIBILITIES
An effective system should be supported by a DOE Senior Manager who can serve as the senior
member of the project and will appoint the corporate champion. The corporate champion should
ensure that the program has the necessary support within all organizations that are executing
projects so that lessons learned are being identified and improvement actions are being resolved.
As previously identified in roles and responsibilities, the corporate champion resides in the
Office of Engineering and Construction Management (OECM).
The primary responsibility for the successful execution of the program SHOULD rest with
Gatekeeper, The responsibility of utilizing the lessons learned to the full extend possible
SHOULD rest with federal project director and contractor project manager, although the entire
integrated project team should be knowledgeable of and utilize lessons learned to provide input
and application from their respective areas of expertise.
1. DOE SENIOR MANAGER.
a. SHOULD serve as the senior champion who supports initiatives related to the
execution and visibility of the program to the DOE Enterprise.
b. Can be responsible for appointing a corporate champion.
2. CORPORATE CHAMPION. The role should reside in the Office of Engineering and
Construction Management (OECM) and should be appointed by the DOE Senior
Manager. Responsibilities should include—
a. Administering the program,
b. Monitoring activities of each program office,
c. Coordinating distribution of lessons learned to the DOE Enterprise, and
d. Appointing a gatekeeper.
3. GATEKEEPER.
a. Should determine DOE Enterprise applicability.
b. Should review all incoming project management lessons learned for
completeness.
c. Should notify appropriate organizations for improvement actions.
d. Should disseminate DOE Enterprise improvement actions.
e. Should observe trends across DOE that may point to the need for revisions to
project management policy and direction
II-2 DOE G 413.3-11
8-5-08
f. Should sun-set DOE Enterprise project management lessons learned.
4. ORGANIZATION COORDINATORS. Should coordinate development and
implementation of project management lessons learned resolutions.
5. PROGRAM OFFICE. Should appoint the appropriate organization coordinator and
should ensure application of project management lessons learned within the program.
6. PROJECT/SITE CONTROLLERS.
a. Site Federal and/or contract representatives who should address each lesson
learned submitted by the project/site integrated project team (IPT) and the
organizational coordinator,
b. Should input data into the Project Management Lessons Learned System,
c. Should validate the information on each entry and coordinate the response
(including generation of improvement actions) with the appropriate project
management expert,
d. Should disseminate the specific lessons learned at their respective locations.
7. PROJECT MANAGEMENT EXPERT (PME).
a. Designated site or Headquarters employee within each DOE program office who
should have knowledge of the program and project management and organization.
b. Responsibilities should include offering recommendations for implementation and
resolution of improvement actions assigned by the controller or coordinator.
c. Should have the organizational knowledge to obtain input from subject matter
experts for those areas outside their capabilities.
8. INTEGRATED PROJECT TEAM.
Section 5
a. May consist of professionals representing diverse disciplines with the specific
knowledge, skills, and abilities to support efforts of the federal project director.
b. Member may enter data into the system.
9. DOE ENTERPRISE. Membership includes all stakeholders of the DOE complex.
DOE G 413.3-11 III-1 (and III-2)
8-5-08
SECTION III. ELEMENTS AND INTERFACES
DOE O 413.3A requires the collection of project management lessons learned during Critical
Decision-4. Limiting the preparation of a lessons learned report to the Critical Decision-4 stage
of a project can be beneficial as a close-out activity, but it does not allow for full utilization of
the program or provide an opportunity for immediate process improvement.
During the Critical Decision-4 stage, many of the IPT members have been reassigned to other
tasks or projects. Therefore, unless documentation continues throughout the project execution,
many of the lessons learned may be lost. It is incumbent on all members of the IPT (as a
minimum) to try to provide “real time” lessons learned information. It is recommended that the
program is queried prior to each Critical Decision authorization request to ensure that applicable
lessons learned have been considered for the project. In addition, as resolution/incorporation of a
specific lesson learned is undertaken, the resources of the IPT should be made available to
implement the change. The report at Critical Decision-4 should be a collection of identified and
applicable PMLLs gathered throughout the project life cycle starting before Critical Decision-0,
as well as those generated through any lessons learned activities conducted during the closeout
process. The report should contain at a minimum the information listed within the “PMLL
Content” section of this guide.
Each IPT member is encouraged to remain current on external influences that can affect his/her
particular area of expertise. Other federal and corporate lessons learned programs (e.g., NASA
ASK Magazine, Construction Industry Institute) provide sources of lessons learned information
that can be utilized by the Department to enhance overall project execution performance. Each
IPT member’s parent organization can contribute to a project’s lessons learned program. For
example, a change in the national methodology of calculating seismic response may impact
several projects simultaneously. This information should be transmitted to all active projects for
evaluation.
DOE G 413.3-11 IV-1 (and IV-2)
8-5-08
SECTION IV. CONTENT
Each lesson learned should contain the following basic attributes when submitted:
1. A clear statement of the project management lessons learned and the Critical Decision
stage when it was identified..
2. A background summary of how the project management lessons learned was realized.
3. Contact information for additional detail related to project management lessons learned.
4. Key data fields for future search capabilities.
5. Assumptions and reasoning associated with improvement action (if improvement actions
are being realized) including any applicable analysis, such as causal, performed.
6. Specific information relating to the improvement action (if improvement actions are
being realized).
DOE G 413.3-11 V-1
8-5-08
SECTION V. PROCESS
Section 6
The OECM should establish a system that is accessible to all individuals within DOE, especially
federal project directors and contractor project managers. This system should provide a
mechanism for documenting lessons learned from any source (field, Headquarters, etc.), tracking
the closure or implementation of improvement actions, and retrieval of historical data for use by
the Department. When necessary, the OECM should become the change agent in support of
modifications to Department procedures and DOE directives to resolve a project management
lesson learned and should be responsible for collecting all project management lessons learned
and tracking coordination and completion of improvement actions. Periodically, OECM should
conduct surveys to determine the effectiveness of the overall program (i.e., is information being
distributed, are lessons learned being captured from field submittals, etc.) and should provide
briefing to the DOE managers on the effectiveness of the program.
The process exists in four stages: Capture, Check, Learn, and Close.
1. CAPTURE. This stage includes all actions that translates information from
projects and captures it into the Project Management Lessons Learned
System.
A lesson learned can be identified by any federal or contractor individual and transmitted
to the controller. Each project federal project director and contractor project manager
should encourage IPT members to submit lessons learned as they are identified without
any fear of reprisal or blame.
2. CHECK This stage includes all actions that take place to validate and disseminate the
lessons learned to the appropriate audience including the DOE Enterprise.
To begin executing the process, each program office should select a controller for
program site/projects, who will be responsible for screening each lesson learned to ensure
that the item is clearly stated and then disseminated to the OECM gatekeeper for
evaluation. If the gatekeeper deems the lesson learned applicable to the DOE Enterprise,
he/she may notify appropriate organization coordinators.
3. LEARN. This stage includes all actions that can translate the lessons learned into
actionable tools and create and implement improvement actions.
The controller can interface with designated project management experts for resolution of
improvement actions and can disseminate improvement actions to the site/project. The
organization coordinator can ensure the resolution of the improvement actions and
disseminate the information to the gatekeeper for dissemination.
4. CLOSE. This stage can include all actions that historically archive the project
management lessons learned and those actions that include sun-setting of historical
records contained in the system.
The controller can designate a lesson learned closed when notified by the project
V-2 DOE G 413.3-11
8-5-08
management experts that improvement action resolution has been implemented. If the
lesson learned is DOE Enterprise applicable, the organization coordinator can notify the
gatekeeper and disseminate the information to the DOE Enterprise. The gatekeeper
should be responsible for the sun-setting of lessons learned that are no longer applicable
and conducting quality audits on the historical archives to ensure applicability for the
DOE Enterprise.
DOE G 413.3-11 Attachment 1
8-5-08 Page 1 (and Page 2)
PROJECT MANAGEMENT LESSONS LEARNED PROCESS BY STAGE
DOE G 413.3-11 Attachment 2
8-5-08 Page 1 (and Page 2)
PROJECT MANAGEMENT LESSONS LEARNED PROCESS BY RESPONSIBILITY
DOE G 413.3-11 Attachment 3
8-5-08 Page 1 (and Page 2)
REFERENCES
1. DOE O 413.3A, Program and Project Management for the Acquisition of Capital Assets,
dated 7-28-06.