DOE G 231.1-2, Occurrence Reporting Causal Analysis Guide
Functional areas: Emergency Preparedness, Occurrence Reporting, Safety
Canceled by DOE O 232.2.
Superseded By:
Version history and related documents
Superseded by
A newer version replaces this document.
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
DOE G 231.1-2
Approved: 08-20-03
OCCURRENCE REPORTING
CAUSAL ANALYSIS GUIDE
[This Guide describes suggested nonmandatory approaches for meeting requirements. Guides are not
requirements documents and are not to be construed as requirements in any audit or appraisal for
compliance with the parent Policy, Order, Notice, or Manual.]
U.S. DEPARTMENT OF ENERGY
Office of Environment, Safety and Health
DISTRIBUTION: INITIATED BY:
All Departmental Elements Office of Environment, Safety and Health
DOE G 231.1-2 Page i
08-20-03
CONTENTS
1. PURPOSE............................................................................................................................1
2. REFERENCES ....................................................................................................................1
3. INTRODUCTION ...............................................................................................................1
4. CAUSAL ANALYSIS TREE DESCRIPTION...................................................................2
5. CAUSAL ANALYSIS PROCESS GUIDANCE.................................................................2
A. Operational Emergency (SC OE) ..................................................................................2
B. Significance Category 1 (SC 1) . ...................................................................................2
C. Significance Category R (SC R) ...................................................................................2
D. Significance Category 2 (SC 2) and Significance Category 3 (SC 3) ..........................2
E. Significance Category 4 (SC 4) ....................................................................................3
F. Evaluation of Significance Categories ..........................................................................3
G. Guidance Tables ............................................................................................................3
6. CAUSAL ANALYSIS PROCESS………………………………………………………...5
Page ii DOE G 231.1-2
08-20-03
ATTACHMENTS
ATTACHMENT 1. ISM FUNCTIONS AND THE B-LEVEL CAUSAL ANALYSIS TREE
BRANCHES
ATTACHMENT 2. CAUSAL ANALYSIS TREE
ATTACHMENT 3. CAUSAL ANALYSIS KEY TERMS AND DEFINITIONS
ATTACHMENT 4. CAUSAL FACTOR IDENTIFICATION METHODOLOGIES
ATTACHMENT 5. INPO ERROR PRECURSORS (SHORT LIST) VERSUS CAUSAL
ANALYSIS TREE C NODES
ATTACHMENT 6. CAT BRANCH A3 MATRIX
ATTACHMENT 7. CAUSAL ANALYSIS NODE DESCRIPTIONS
ATTACHMENT 8. REFERENCES
DOE G 231.1-2 Page 1
08-20-03
1. PURPOSE
This Guide is intended to assist personnel in determining the Apparent Cause(s) of specific reportable
occurrences and to explain the structure and nodes of the Causal Analysis Tree for use in occurrence reporting
and causal analysis. It does not introduce or impose any new requirements and is to be used in conjunction with
the References listed below.
2. REFERENCES
DOE O 231.1A, Environment, Safety and Health Reporting, dated 08-19-03
DOE M 231.1-2, Occurrence Reporting and Processing of Operations Information, dated 08-19-03
DOE G 231.1-1, Occurrence Reporting and Performance Analysis Guide, dated 08-20-03
3. INTRODUCTION
The Department of Energy has established the requirements for identification of occurrences/events,
categorization of the significance of the identified events, determination of the cause or causes of the events,
and development of corrective actions designed to eliminate the events and to prevent their recurrence using a
graded approach based on the significance of the event. Figure 1 illustrates the relationship between the
Significance Category (SC) and the causal analysis step from the Occurrence Reporting Model in Section 11 of
DOE M 231.1-2, Occurrence Reporting and Processing of Operations Information.
Section 2
FIGURE 1
OE Root Cause
Determined
Root Cause
Determined 1
Apparent Cause
Determined
3
Apparent Cause
Determined
2
Recurring Event
Root Cause
Determined
R
Causal Analysis
per Contractor
Corrective Action
Program
4
SC
Identified
Event
Identification /
Documentation
Page 2 DOE G 231.1-2
08-20-03
Typically, more investigation and analysis is necessary as the level of significance of the identified event
increases (i.e., the SC number decreases). The scope of the corrective actions being developed also becomes
more extensive as the significance level of the event increases. This Guide does not address specific Root
Cause methodologies that can be used to determine the Root Cause(s) of an event. Rather, it addresses the
Apparent Cause analysis and use of the Causal Analysis Tree (CAT) to determine the causes for all events.
4. CAUSAL ANALYSIS TREE DESCRIPTION
The Causal Analysis Tree (CAT) has been developed to assist in the assignment of Apparent Cause(s) to
identified events and for use in coding causes for all occurrences. The CAT is shown in Attachment 1 (“B”-
Level) and Attachment 2 (“C”-Level) of the Guide. The CAT is a result of a benchmarking study of industry
causal analysis systems. The lowest level of the CAT is typically referred to as the “C” Level of the CAT.
Attachment 7 provides a detailed description of each “C”-Level node in the CAT with examples and potential
corrective actions identified.
In accordance with DOE M 231.1-2, guidance found in Table I of this Guide, used in conjunction with the
CAT, allows for a tailored approach to developing corrective actions based on the significance category. Table
I also prompts for the identification of applicable ISM Core Functions. For instance, as shown in Table I, for a
SC 1 event or a recurring event (R) identified during performance analysis, root causes should be determined,
and corrective actions should be identified to remedy the problem, prevent recurrence of the specific problem,
and also preclude occurrence of similar problems. However, for a SC 3 event, Apparent Cause(s) are identified
and the corrective actions are targeted to remedy the problem.
5. CAUSAL ANALYSIS PROCESS GUIDANCE
Table I, Causal Analysis Process Guidance, and the CAT should be used to implement the causal analysis
process such that appropriate corrective actions can be determined according to the significance of the event.
The causal analysis guidance discussed below meets the minimum requirements; however, there may be
additional causal analysis requirements imposed by individual organizations.
A. Operational Emergency (SC OE)
A team using any formal causal analysis method (e.g., interviews, event and causal factors charting,
barrier analysis, or change analysis) should perform an analysis of SC OE events to determine Root
Cause(s). Any site-specific Root Cause methodology can be used to determine Root Cause(s). In
addition, all of the cause codes for entry in the occurrence reports should be selected from the CAT.
At least one investigation team member should be a trained investigator per DOE M 231.1-2,
Occurrence Reporting and Processing of Operations Information, should understand the CAT, and
should have experience in previous investigations. Corrective actions for SC OE events are to be
developed to remedy the problem, prevent its recurrence, and also preclude the occurrence of similar
problems.
B. Significance Category 1 (SC 1)
Section 3
A team with a trained investigator, as defined in DOE M 231.1-2, should use the methods described in
(A) above to analyze SC 1 events. Additionally, corrective action methods as described in (A) also
apply to SC 1 events.
C. Significance Category R (SC R)
A trained investigator, as defined in DOE M 231.1-2, should use the methods described in (A) above to
analyze SC R events. Additionally, corrective action methods as described in (A) also apply to SC R
events.
D. Significance Category 2 (SC 2) and Significance Category 3 (SC 3)
DOE G 231.1-2 Page 3
08-20-03
For SC 2 and SC 3 events, a trained investigator should use the best available information (such as
critiques, log entries, or engineering judgment) to determine Apparent Causes using the CAT.
Corrective actions for SC 2 events are required to remedy the problem and prevent its recurrence.
Corrective actions for SC 3 events are required only to remedy the problem.
E. Significance Category 4 (SC 4)
Analysis of SC 4 events is accomplished per the contractor’s specific corrective action program.
F. Evaluation of Significance Categories
Upon completion of the analysis of the event, the significance category should be reviewed for
appropriateness based on any new information that may have been identified during the investigation.
If it is determined that the significance category of the event should be higher or lower (i.e., the
reporting criterion has changed), then the correct reporting criterion should be assigned, which will
result in an automatic change to the significance category. The causal analysis should then be
reworked to the requirements of the higher or lower significance category. In such cases, the reporting
organization needs to submit an Update Report or, if the occurrence does not meet any of the reporting
criteria, the existing report can be cancelled.
G. Guidance Tables
The guidance listed in Sections A – E is summarized in Table I.
Page 4 DOE G 231.1-2
08-20-03
TABLE I
CAUSAL ANALYSIS PROCESS GUIDANCE
Significance
Category Causal Analysis Level Analysis Requirements Corrective Action Development
Requirements
OE
All causes of the event
are determined and
documented using the
organization’s approved
Root Cause Analysis
Process.
• Identify deficient ISM
core functions
• Perform Root Cause
Analysis
• Select all appropriate
Cause Codes (Levels
A, B, and C of the
CAT)
Corrective Actions are designed to remedy
the problem, prevent recurrence of the
specific problem, and preclude occurrence
of similar problems.
1
All causes of the event
are determined and
documented using the
organization’s approved
Root Cause Analysis
Process.
• Identify deficient ISM
core functions
• Perform Root Cause
Analysis
• Select all appropriate
Cause Codes (Levels
A, B, and C of the
CAT)
Corrective Actions are designed to remedy
the problem, prevent recurrence of the
specific problem, and preclude occurrence
of similar problems.
R Same as SC 1 above Same as SC 1 above Same as SC 1 above
2
Apparent Cause(s) of the
event is identified and
documented.
• Identify deficient ISM core
functions
• Apparent Cause Analysis
(Levels A, B, and C of the
CAT)
Corrective Actions are designed to remedy
the problem and prevent its recurrence.
3
Apparent Cause(s) of the
event is identified and
documented.
• Identify deficient ISM core
functions
• Apparent Cause Analysis
(Levels A, B, and C of the
CAT)
Corrective Actions are designed to remedy
the problem.
Section 4
4 Analysis and Actions per the contractor specific Corrective Action Program.
DOE G 231.1-2 Page 5
08-20-03
6. CAUSAL ANALYSIS PROCESS
The causal analysis process is an integral part of the Occurrence Reporting and Processing System (ORPS)
model and supports the required Performance Analysis process described in the Occurrence Reporting and
Performance Analysis Guide, DOE G 231.1-1. When implementing the causal analysis process, Apparent
Cause(s) are identified as the most probable cause(s) of an event or condition that management has the control
to fix and for which effective recommendations for corrective actions can be generated. A model for the causal
analysis process is provided below. Causal Analysis Key Terms and Definitions are provided in Attachment 3.
There are three basic steps in the process: 1) identifying causal factors, 2) selecting ISM Core Functions, 3)
using the CAT to identify Apparent Causes/Cause Codes.
1. Identify Causal Factors. Use one of the contractor’s supported/recommended methodologies or those
methodologies recommended in Attachment 4 to determine causal factors.
2. Select Applicable ISM Core Function(s). Select all of the ISM core function(s) necessary to identify any
observed weakness(es) in the facility's implementation of the ISM program (Attachment 1). Deficient ISM
Core Functions are considered to be Causal Factors and processed in the same manner as the Causal
Factors determined above.
3. Use the CAT to Identify Apparent Causes/Cause Codes. Use the CAT (Attachment 2) to determine the
appropriate cause(s) for each causal factor identified. Causal Analysis Node Descriptions are shown in
Attachment 7 and can be used, as needed, to determine the appropriate cause(s). Additionally, the logic
provided below for using the CAT will ensure that all possible cause(s) are considered during the analysis.
A. Use the Design/Engineering (A1) Branch and the Equipment/Material (A2) Branch to codify any
design/equipment related deficiencies.
B. Use the Human Performance (A3) Branch to codify errors by personnel. If any Human Performance
Codes are determined to be applicable, use Attachment 6 to determine applicable C level apparent
cause codes in the other branches that may have caused the resultant human error. These codes
coupled together describe the cause of the human error.
C. Use the Management Problem (A4), Communications LTA (A5), Training Deficiency (A6), and Other
Problem (A7) branches to determine other Cause Codes.
D. Repeat this process with remaining causal factors until all causal factors have been addressed.
DOE G 231.1-2 Attachment 1
08-20-03 Page 1
Attachment 1
INTEGRATED SAFETY MANAGEMENT FUNCTIONS AND
THE B-LEVEL CAUSAL ANALYSIS TREE BRANCHES
The objective of ISM is to integrate safety considerations into management and work practices at all levels to accomplish
missions while protecting the public, the worker, and the environment. Identification of a breakdown or gap in an ISM
core function is considered essential; the information provides additional insight into the probable cause of the
occurrence. Deficient ISM Core Functions are considered to be Causal Factors and processed in the same manner as the
Causal Factors determined above.
B1 CALIBRATION FOR
INSTRUMENTS LTA
B2 PERIODIC/
CORRECTIVE
MAINTENANCE LTA
B3 INSPECTION/
TESTING LTA
B4 MATERIAL
CONTROL LTA
B5 PROCUREMENT
CONTROL LTA
B6 DEFECTIVE,
FAILED OR
CONTAMINATED
A2
Equipment/Material
Problem
Section 5
Scope of Work
LTA
B1 SKILL BASED
ERROR
B2 RULE BASED
ERROR
B3 KNOWLEDGE
BASED ERROR
B4 WORK
PRACTICES LTA
A3
Human Performance
LTA
Level A nodes are underlined.
Level B nodes are in ALL CAPS.
Level C nodes are in “Sentence case.”
LTA = Less than Adequate
A1
Design/
Engineering
Problem
B1 DESIGN INPUT
LTA
B2 DESIGN
OUTPUT LTA
B3 DESIGN/
DOCUMENTATION
LTA
B4 DESIGN/
INSTALLATION
VERIFICATION LTA
B5 OPERABILITY
OF DESIGN/
ENVIRONMENT
LTA
Developed /
Implemented
Controls LTA
Performed work
within Controls
LTA
Feedback /
Improvement
LTA
Determination of
Deficient ISM
Function
Integrated Safety Management
B1 WRITTEN
COMMUNICATIONS
METHOD OF
PRESENTATION
B2 WRITTEN
COMMUNICATION
CONTENT LTA
B3 WRITTEN
COMMUNICATION
NOT USED
B4 VERBAL
COMMUNICATION LTA
A5
Communications
LTA
A6
Training
Deficiency
B1 NO
TRAINING
PROVIDED
B2 TRAINING
METHODS LTA
B3 TRAINING
MATERIAL
LTA
B1 MANAGEMENT
METHODS LTA
B2 RESOURCE
MANAGEMENT
LTA
A4
Management Problem
B3 WORK
ORGANIZATION &
PLANNING LTA
B4 SUPERVISORY
METHODS LTA
B5 CHANGE
MANAGEMENT LTA
A7 Other Problem
B1 EXTERNAL
PHENOMENA
B2 RADIOLOGICAL/
HAZARDOUS
MATERIAL PROBLEM
Causal Analysis Tree
START
HERE
Analyzed
Hazards LTA
DOE G 231.1-2 Attachment 2
08-20-03 Page 1
Attachment 2
B1 SKILL BASED ERROR
C01 Check of work was LTA
C02 Step was omitted due to
distraction
C03 Incorrect performance due to
mental lapse
C04 Infrequently performed steps
were performed incorrectly
C05 Delay in time cause d LTA
actions
C06 Wrong action selected based
on similarity with other actions
C07 Omission / repeating of steps
due to assumptions for
completion
B2 RULE BASED ERROR
C01 Strong rule incorrectly
chosen over other rules
C02 Signs to stop were ignored
and step performed incorrectly
C03 Too much activity was
occurring and error made in
problem solving
C04 Previous success in use of
rule reinforced continued use of
rule
C05 Situation incorrectly
identified or represented result ing
in wrong rule used
B3 KNOWLEDGE BASED
ERROR
C01 Attention was given to wrong
issues
C02 LTA Conclusion based on
sequencing of facts
C03 Individual justifie d action by
focusing on biased evidence
C04 LTA review based on
assumption that process will not
change
C05 Incorrect assumption that a
correlation existed between two or
more facts
C06 Individual underestimated the
problem by using past events as
basis
B4 WORK PRACTICES LTA
C01 Individual ’s capability to
perform work LTA [Examples
include: Sensory / perceptual
capabilities LTA, Motor / physical
capabilities LTA, and Attitude /
psychological profile LTA.]
C02 Deliberate violation
A3 Human PerformanceLTA
B1 MANAGEMENT METHODS
LTA
C01 Management policy guidance/
expectations not well-defined,
understood or enforced
C02 Job performance standards not
adequately defined
C03 Management direction created
insufficient awareness of impact of
actions on safety / reliability
C04 Management follow-up or
monitoring of activities did not
identify problems
C05 Management assessment did not
determine causes of previous event or
known problem
C06 Previous industry or in-house
experience was not effectively used
to prevent recurrence
C07 Responsibility of personnel not
well-defined or personnel not held
accountable
C08 Corrective action responses to a
known or repetitive problem was
untimely
Section 6
C09 Corrective action for previously
identified problem or event was not
adequate to prevent recurrence
B2 RESOURCE MANAGEMENT
LTA
C01 Too many administrative duties
assigned to immediate supervisor
C02 Insufficient supervisory resources
to provide necessary supervision
C03 Insufficient manpower to support
identified goal / objective
C04 Resources not provided to assure
adequate training was provided /
maintained
C05 Needed resource changes not
approved / funded
C06 Means not provided to assure
procedures / documents / records were
of adequate quality and up -to-date
C07 Means not provided for assuring
adequate availability of appropriate
materials / tools
C08 Means not provided for assuring
adequate equipment quality,
reliability, or operability
C09 Personnel selection did not assure
match of worker motivations / job
descriptions
C10 Means / method not provided for
assuring adequate quality of contract
services
A4 Management Problem
Level A nodes are
underlined.
Level B nodes are in
ALLCAPS.
Level C nodes are in
“sentence case.”
LTA = Less than adequate
A1 Design / Engineering
Problem
B1 DESIGN INPUT LTA
C01 Design input cannot
be met
C02 Design input obsolete
C03 Design input not
correct
C04 Necessary design
input not available
B2 DESIGN OUTPUT LTA
C01 Design output scope
LTA
C02 Design output not
clear
C03 Design output not
correct
C04 Inconsistent design
output
C05 Design input not
addressed in design output
C06 Drawing,
specification, or data error
C07 Error in equipment or
material selection
C08 Errors not detectable
C09 Errors not recoverable
B3 DESIGN /
DOCUMENTATION LTA
C01 Design / documentation
not complete
C02 Design / documentation
not up-to-date
C03 Design / documentation
not controlled
B4 DESIGN /
INSTALLATION
VERIFICATION LTA
C01 Independent review of
design / documentation
LTA
C02 Testing of design /
installation LTA
C03 Independent
inspection of design /
installation LTA
C04 Acceptance of
design / installation LTA
B5 OPERABILITY
OF DESIGN /
ENVIRONMENT LTA
C01 Ergonomics LTA
C02 Physical environment
LTA
C03 Natural environment
LTA
B1 CALIBRATION FOR
INSTRUMENTS LTA
C01 Calibration LTA
C02 Equipment found
outside acceptance criteria
B2 PERIODIC /
CORRECTIVE
MAINTENANCE LTA
C01 Preventive
maintenance for equipment
LTA
C02 Predictive maintenance
LTA
C03 Corrective
maintenance LTA
C04 Equipment history
LTA
B3 INSPECTION / TESTING
LTA
C01 Start-up testing LTA
C02 Inspection / testing LTA
C03 Post-maintenance / Post-
modification testing LTA
B4 MATERIAL CONTROL
LTA
C01 Material handling LTA
C02 Material storage LTA
C03 Material packaging
LTA
C04 Material shipping LTA
C05 Shelf life exceeded
C06 Unauthorized material
substitution
C07 Marking / labeling LTA
B5 PROCUREMENT
CONTROL LTA
C01 Control of changes to
procurement specifications /
purchase order LTA
C02 Fabricated item did
not meet requirements
C03 Incorrect item received
C04 Product acceptance
requirements LTA
B6 DEFECTIVE, FAILED
OR CONTAMINATED
C01 Defective or failed part
C02 Defective or failed
material
C03 Defective weld, braze
or soldering joint
C04 End of life failure
C05 Electrical or instrument
noise
C06 Contaminant
A2 Equipment / Material
Problem
Section 7
B1 WRITTEN
COMMUNICATIONS
METHOD OF
PRESENTATION LTA
C01 Format deficiencies
C02 Improper referencing or
branching
C03 Checklist LTA
C04 Deficiencies in user aids
(charts, etc.)
C05 Recent changes not made
apparent to user
C06 Instruction step /
information in wrong
sequence
C07 Unclear / complex wording
or grammar
B2 WRITTEN
COMMUNICATION
CONTENT LTA
C01 Limit inaccuracies
C02 Difficult to implement
C03 Data / computations
wrong / incomplete
C04 Equipment identification
LTA
C05 Ambiguous instructions /
requirements
C06 Typographical error
C07 Facts wrong / requirements
not correct
C08 Incomplete / situation not
covered
C09 Wrong revision used
B3 WRITTEN
COMMUNICATION
NOT USED
C01 Lack of written
communication
C02 Not available or
inconvenient for use
B4 VERBAL
COMMUNICATION LTA
C01 Communication between
work groups LTA
C02 Shift communications
LTA
C03 Correct terminology not
used
C04 Verification / repeat back
not used
C05 Information sent but not
understood
C06 Suspected problems not
communicated to supervision
C07 No communication
method available
A5 Communications LTA A6 Training Deficiency
B1 NO TRAINING
PROVIDED
C01 Decision not to train
C02 Training requirements not
identified
C03 Work incorrectly
considered “skill of the craft”
B2 TRAINING METHODS
LTA
C01 Practice or hands -on
experience LTA
C02 Testing LTA
C03 Refresher training LTA
C04 Inadequate presentation
B3 TRAINING
MATERIAL LTA
C01 Training objectives LTA
C02 Inadequate content
C03 Training on new work
methods LTA
C04 Performance standards
LTA
Causal Analysis Tree Rev. 0
B3 WORK ORGANIZATION & PLANNING LTA
C01 Insufficient time for worker to prepare task
C02 Insufficient time allotted for task
C03 Duties not well-distributed among personnel
C04 Too few workers assigned to task
C05 Insufficient number of trained or experienced workers
assigned to task
C06 Planning not coordinated with inputs from
Walk downs/ task analysis
C07 Job scoping did not identify potential task interruptions
and / or environmental stress
C08 Job scoping did not identify special circumstances
and / or conditions
C09 Work planning not coordinated with all departments
involved in task
C10 Problem performing repetitive tasks and / or subtasks
C11 Inadequate work package preparation
B4 SUPERVISORY METHODS LTA
C01 Tasks and individual accountability not made clear to
worker
C02 Progress / status of task not adequately tracked
C03 Appropriate level of in-task supervision not determined
prior to task
C04 Direct supervisory involvement in task interfered with
overview role
C05 Emphasis on schedule exceeded emphasis on
methods / doing a good job
C06 Job performance and self-checking standards not
properly communicated
C07 Too many concurrent tasks assigned to worker
C08 Frequent job or task “shuffling”
C09 Assignment did not consider worker’s need to use
higher-order skills
C10 Assignment did not consider worker’s previous task
C11 Assignment did not consider worker’s ingrained work
patterns
C12 Contact with personnel too infrequent to detect work
habit/attitude changes
C13 Provided feedback on negative performance but not on
positive performance
B5 CHANGE MANAGEMENT LTA
C01 Problem identification did not identify need for change
C02 Change not implemented in timely manner
C03 Inadequate vendor support of change
Section 8
C04 Risks / consequences associated with change not
adequately reviewed / assessed
C05 System interactions not considered
C06 Personnel / department interactions not considered
C07 Effects of change on schedules not adequately addressed
C08 Change-related training / retraining not performed or not
adequate
C09 Change-related documents not developed or revised
C10 Change-related equipment not provided or not revised
C11 Changes not adequately communicated
C12 Change not identifiable during task
C13 Accuracy / effectiveness of change not verified or not
validated
START
HERE
A7 Other Problem
B1 EXTERNAL PHENOMENA
C01 Weather or ambient conditions LTA
C02 Power failure or transient
C03 External fire or explosion
C04 Other natural phenomena LTA
B2 RADIOLOGICAL / HAZARDOUS
MATERIAL PROBLEM
C01 Legacy contamination
C02 Source unknown
DOE G 231.1-2 Attachment 3
08-20-03 Page 1
Attachment 3
CAUSAL ANALYSIS KEY TERMS AND DEFINITIONS
Apparent Cause– the most probable cause(s) that explains why the event happened, that can reasonably be identified,
that local or facility management has the control to fix, and for which effective recommendations for corrective action(s)
to remedy the problem can be generated, if necessary.
Causal Factor - an event or condition that either caused the occurrence under investigation or contributed to the
unwanted result. If it were not for this event or condition, the unwanted result would not have occurred or would have
been less severe.
LTA – Less Than Adequate
Root Cause-- the most basic cause(s) that explains why the event happened, that can reasonably be identified, that senior
management has the control to fix, and for which effective recommendations for corrective action(s) to remedy the
problem, prevent specific recurrence of the problem, and preclude occurrence of similar problems can be generated, if
necessary. This is typically one level further in analysis beyond the Apparent Causes(s) (i.e., one level beyond the Level
C node of the CAT).
DOE G 231.1-2 Attachment 4
08-20-03 Page 1
Attachment 4
CAUSAL FACTOR IDENTIFICATION METHODOLOGIES
Data Collection - It is important to begin data collection immediately following the occurrence to ensure all relevant
information associated with the event is identified. The information that should be collected consists of conditions
before, during, and after the occurrence; personnel involvement; environmental factors and other information having
relevance to the occurrence. This information is key to determining causal factors associated with the occurrence.
Methodologies - Identify causal factors immediately proceeding and surrounding the occurrence using one of the
recommended methodologies (or equivalent) listed below.
• Events and Causal Factor Analysis - Events and Causal Factor Analysis identifies the time sequence of a series
of tasks and/or actions and the surrounding conditions leading to an event. The results are displayed in an
Events and Causal Factor chart that gives a picture of the relationships of the event and causal factors.
• Change Analysis - Change Analysis is used when the event is obscure. It is a systematic process that is
generally used for a single occurrence and focuses on elements that have changed to identify causal factors.
• Barrier Analysis - Barrier Analysis is a systematic process that can be used to identify causal factors related to
physical, administrative, and procedural barriers or controls that should have prevented the event.
Section 9
• Management Oversight and Risk Tree (MORT) Analysis - MORT is used to identify causal factors related to
inadequacies in barriers/controls, specific barrier and support functions, and management functions.
• Kepner-Tregoe Problem Solving and Decision Making - Kepner-Tregoe provides a systematic framework for
gathering, organizing, and evaluating information to determine causal factors during the investigation process.
DOE G 231.1-2 Attachment 5
08-20-03 Page 1
Attachment 5
INPO ERROR PRECURSORS (SHORT LIST) VERSUS
CAUSAL ANALYSIS TREE LEVEL C NODES
The Institute of Nuclear Power Operations has developed a list of Error Precursors that are useful in preventing events
from occurring. For example, if the operator recognizes that a number of Error Precursors are present in a given
situation, awareness can be increased to reduce the likelihood of Human Performance errors. Similarly, knowing that a
particular precursor was evident during an event can aid the analyst in determining proper corrective action. The matrix
below is provided in that vein. It also shows that the error precursors are imbedded within the Causal Analysis Tree. In
some cases, the B node is listed. This is to be interpreted as all of the relevant C nodes applying to that precursor.
AREA ELEMENT CAT
High workload
[memory
requirements]
A4B4C07, Too many concurrent tasks assigned to worker,
A5B2C05, Ambiguous instructions / requirements,
A5B2C08, Incomplete / situation not covered
Time pressure
[in a hurry]
A4B3C02, Insufficient time allotted for task,
A4B3C07, Job scoping did not identify potential task interruptions and/or
environmental stress
Simultaneous,
multiple tasks
A4B3C07, Job scoping did not identify potential task interruptions and/or
environmental stress,
A4B4C07, Too many concurrent tasks assigned to worker
Repetitive
action/monotony
A4B3C07, Job scoping did not identify potential task interruptions and/or
environmental stress,
A4B3C10, Problem performing repetitive tasks and/or subtasks
Irrecoverable
actions
A1B2C09, Errors not recoverable
Interpretation
requirements
A1B5C01, Ergonomics LTA,
A1B5C02, Physical environment LTA,
A3B3, Knowledge based error,
A4B1C01, Management policy guidance / expectation not well-defined,
understood or enforced,
A4B4C01, Tasks and individual accountability not made clear to worker,
A5B2C05, Ambiguous instructions / requirements,
A5B2C08, Incomplete / situation not covered,
A5B4C03, Correct terminology not used,
A5B4C04, Verification / repeat back not used,
A5B4C05, Information sent but not understood
Unclear goals,
roles or
responsibilities
A4B1C07, Responsibility of personnel not well-defined or personnel not
held accountable,
A4B4C01, Tasks and individual accountability not made clear to worker,
A5B2C02, Difficult to implement,
A5B2C05, Ambiguous instructions / requirements,
A5B2C07, Facts wrong / requirements not correct,
A5B2C08, Incomplete / situation not covered,
A5B3C02, Not available or inconvenient for use,
A6B3C01, Training objectives LTA
Task Demands
Lack of or
unclear
standards
A4B1C01, Management policy guidance / expectation not well-defined,
understood or enforced,
A5B2C08, Incomplete / situation not covered
Attachment 5 DOE G 231.1-2
Page 2 08-20-03
AREA ELEMENT CAT
Distractions /
interruptions
A1B5C02, Physical environment LTA,
A4B3C07, Job scoping did not identify potential task interruptions and/or
environmental stress,
A4B4C07, Too many concurrent tasks assigned to worker
Section 10
Changes /
departures from
routine
A4B3C07, Job scoping did not identify potential task interruptions and/or
environmental stress,
A4B4C01, Tasks and individual accountability not made clear to worker,
A6B3C02, Inadequate content
Confusing
procedure /
vague guidance
A4B4C01, Tasks and individual accountability not made clear to worker,
A5B1C01, Format deficiencies,
A5B1C07, Unclear / complex wording or grammar,
A5B2C05, Ambiguous instructions / requirements,
A5B2C08, Incomplete / situation not covered
Confusing
displays /
controls
A1B5C01, Ergonomics LTA,
A2B4C07, Marking / labeling LTA
Work-arounds;
Out of Service
instrumentation
A1B5C01, Ergonomics LTA,
A2B1C01, Calibration LTA,
A2B2C01, Preventive maintenance for equipment LTA,
A4B4C01, Tasks and individual accountability not made clear to worker,
A5B2C08, Incomplete / situation not covered,
A6B3C02, Inadequate content
Hidden system
response
A1B2C08, Errors not detectable,
Unexpected
equipment
conditions
A1B5C01, Ergonomics LTA,
A2B1C01, Calibration LTA,
A2B2C01, Preventive maintenance for equipment LTA,
A2B2C04, Equipment history LTA,
A2B3C02, Inspection / testing LTA,
A2B4C04, Material shipping LTA,
A4B3C07, Job scoping did not identify potential task interruptions and/or
environmental stress,
A4B3C08, Job scoping did not identify special circumstances and/or
conditions,
A4B3C11, Inadequate work package preparation
Work
Environment
Lack of
alternative
indication
A1B2C01, Design output scope LTA,
DOE G 231.1-2 Attachment 5
08-20-03 Page 3
AREA ELEMENT CAT
Unfamiliar with
task/first time
A4B2C01, Too many administrative duties assigned to immediate
supervisor,
A4B2C02, Insufficient supervisory resources to provide necessary
supervision,
A4B4, Supervisory methods LTA,
A6B1C01, Decision not to train,
A6B1C02, Training requirements not identified,
A6B1C03, Work incorrectly considered skill of the craft,
A6B2C01, Practice or hands-on experience LTA
Lack of
knowledge
[mental model]
A3B3, Knowledge based error,
A6B1C01, Decision not to train,
A6B1C02, Training requirements not identified,
A6B3C02, Inadequate content
Imprecise
communication
habits
A5B4C03, Correct terminology not used,
A5B4C04, Verification / repeat back not used,
A5B4C05, Information sent but not understood
Lack of
proficiency /
inexperience
A6B2C01, Practice or hands-on experience LTA
New technique
not used before
A4B2C01, Too many administrative duties assigned to immediate
supervisor,
A4B2C02, Insufficient supervisory resources to provide necessary
supervision,
A4B4, Supervisory methods LTA,
A6B1C01, Decision not to train,
A6B1C02, Training requirements not identified,
A6B3C03, Training on new work methods LTA
Unsystematic
problem-solving
skills
A3B4C01, Individual’s capability to perform work LTA,
‘Can do’ attitude
for crucial task
A3B3C01, Attention was given to wrong issues,
A4B4C01, Tasks and individual accountability not made clear to worker
Individual
capabilities
Illness or fatigue A3B4C01, Individual’s capability to perform work LTA,
A4B1C01, Management policy guidance / expectation not well-defined,
understood or enforced,
A4B2C03, Insufficient manpower to support identified goal / objective,
A4B3C07, Job scoping did not identify potential task interruptions and/or
environmental stress
Attachment 5 DOE G 231.1-2
Page 4 08-20-03
AREA ELEMENT CAT
Stress A3B4C01, Individual capabilities to perform work LTA,
Section 11
A4B3C07, Job scoping did not identify potential task interruptions and/or
environmental stress,
A4B4C11, Assignment did not consider worker’s ingrained work patterns
Habit patterns A4B4C11, Assignment did not consider worker’s ingrained work patterns,
A5B1C03, Checklist LTA,
A5B3C01, Lack of written communication
Assumptions A3B3, Knowledge based error
Complacency /
overconfidence
A3B1, Skill based error,
Mind set
[intention]
A4B3C01, Insufficient time for worker to prepare task,
A3B4C02, Deliberate violation,
A4B4C01, Tasks and individual accountability not made clear to worker,
A6B1C01, Decision not to train,
A6B1C02, Training requirements not identified
Inaccurate risk
perception
A4B1C03, Management direction created insufficient awareness of impact
of actions on safety / reliability,
A4B3C07, Job scoping did not identify potential task interruptions and/or
environmental stress,
A4B5C04, Risks / consequences associated with change not adequately
reviewed / assessed,
A6B1C01, Decision not to train,
A6B1C02, Training requirements not identified
Mental shortcuts
[biases]
A3B3C03, Individual justified action by focusing on biased evidence,
A3B3C04, LTA review based on assumption that process will not change,
A3B3C05, Incorrect assumption that a correlation existed between two or
more facts,
A3B3C06, Individual underestimated the problem by using past events as
basis
Human nature
Limited short
term memory
A3B4C01, Individual’s capability to perform work LTA,
A4B4C07, Too many concurrent tasks assigned to worker
DOE G 231.1-2 Attachment 6
08-20-03 Page 1
Attachment 6: CAT BRANCH A3 MATRIX
Potential Associated Level C Nodes from Different CAT Branches*** Human Performance
A3 Level C Nodes Level C nodes applicable to the
particular A3 Level C Node
Additional Level C Nodes applicable to
the associated A3 Level B Node
A3B1C01
Check of work was LTA
A1B5C02, Physical environment LTA,
A5B1C03, Checklist LTA
A3B1C02
Step was omitted due to
distraction
A4B4C08, Frequent job or task
“shuffling”
A3B1C03
Incorrect performance due
to mental lapse
A4B4C07, Too many concurrent tasks
assigned to worker,
A4B4C08, Frequent job or task
“shuffling”
A3B1C04
Infrequently performed
steps were performed
incorrectly
A3B1C05
Delay in time caused LTA
actions
A4B4C07, Too many concurrent tasks
assigned to worker,
A4B4C08, Frequent job or task
“shuffling”
A3B1C06
Wrong action selected
based on similarity with
other actions
A5B1C07, Unclear / complex wording
or grammar,
A5B2C05, Ambiguous instructions /
requirements
A3B1C07
Omission/repeating of
steps due to assumptions
for completion
A5B1C03, Checklist LTA
A1B1C03, Design input not correct,
A1B5C01, Ergonomics LTA,
A4B1C03, Management direction
created insufficient awareness of impact
of actions on safety / reliability,
A4B2C04, Resources not provided to
assure adequate training was provided /
maintained,
A4B3C02, Insufficient time allotted for
task,
A4B3C05, Insufficient number of
trained or experienced workers assigned
to task,
A4B3C07, Job scoping did not identify
potential task interruptions and/or
environmental stress,
A4B4C03, Appropriate level of in-task
supervision not determined prior to task,
A4B4C06, Job performance and self-
checking standards not properly
communicated,
A4B4C10, Assignment did not consider
worker’s previous task,
A5B1C01, Format deficiencies,
A6B1C03, Work incorrectly considered
skill of the craft
A3B2C01
Strong rule incorrectly
chosen over other rules
Section 12
A3B2C02
Signs to stop were ignored
and step performed
incorrectly
A4B4C06, Job performance and self-
checking standards not properly
communicated
A3B2C03
Too much activity was
occurring and error made
in problem solving
A1B5C02, Physical environment LTA,
A4B3C04, Too few workers assigned
to task,
A4B3C07, Job scoping did not identify
potential task interruptions and/or
environmental stress,
A4B4C07, Too many concurrent tasks
assigned to worker,
A4B4C08, Frequent job or task
“shuffling”
A3B2C04
Previous success in use of
rule reinforced continued
use of rule
A4B3C10, Problem performing
repetitive tasks and/or subtasks
A3B2C05
Situation incorrectly
identified or represented
resulting in wrong rule
used
A5B1C07, Unclear / complex wording
or grammar
A1B2C06, Drawing, specification, or
data error,
A1B5C01, Ergonomics LTA,
A4B1C03, Management direction
created insufficient awareness of impact
of actions on safety / reliability,
A4B1C09, Corrective action for
previously identified problem or event
was not adequate to prevent recurrence,
A4B2C06, Means not provided to assure
procedures / documents / records were
of adequate quality and up-to-date,
A5B1C01, Format deficiencies,
A5B2C05, Ambiguous instructions /
requirements,
A6B1C03, Work incorrectly considered
“skill of the craft”,
A6B2C01, Practice or hands-on
experience LTA
Attachment 6 DOE G 231.1-2
Page 2 08-20-03
Attachment 6: CAT BRANCH A3 MATRIX
Potential Associated Level C Nodes from Different CAT Branches*** Human Performance
Level C Nodes Level C nodes applicable to the
particular A3 Level C Node
Additional Level C Nodes applicable to
the associated A3 Level B Node
A3B3C01
Attention was given to
wrong issues
A3B3C02
LTA conclusion based on
sequencing of facts
A5B1C06, Instruction step /
information in wrong sequence
A3B3C03
Individual justified action
by focusing on biased
evidence
A3B3C04
LTA review based on
assumption that process
will not change
A4B3C10, Problem performing
repetitive tasks and/or subtasks,
A4B5C12, Change not identifiable
during task,
A5B1C05, Recent changes not made
apparent to user
A3B3C05
Incorrect assumption that
a correlation existed
between two or more facts
A3B3C06
Individual underestimated
the problem by using past
events as basis
A4B3C10, Problem performing
repetitive tasks and/or subtasks
A1B5C01, Ergonomics LTA,
A4B1C09, Corrective action for
previously identified problem or event
was not adequate to prevent recurrence,
A4B2C04, Resources not provided to
assure adequate training was provided /
maintained,
A4B3C08, Job scoping did not identify
special circumstances and / or
conditions,
A4B4C06, Job performance and self-
checking standards not properly
communicated,
A5B4C03, Correct terminology not
used,
A5B4C04, Verification / repeat back not
used,
A5B4C05, Information sent but not
understood,
A6B1C02, Training requirements not
identified,
A6B2C01, Practice or hands-on
experience LTA,
A6B3C02, Inadequate content
A3B4C01
Individual’s capability to
perform work LTA
A1B5C01, Ergonomics LTA,
A1B5C02, Physical environment LTA,
A4B3C07, Job scoping did not identify
potential task interruptions and/or
environmental stress,
A4B4C09, Assignment did not
consider worker’s need to use higher-
order skills,
A4B4C10, Assignment did not
consider worker’s previous task,
A4B4C11, Assignment did not
consider worker’s ingrained work
patterns
A3B4C02
Deliberate violation
Section 13
A4B2C02, Insufficient supervisory
resources to provide necessary
supervision,
A4B4C03, Appropriate level of in-task
supervision not determined prior to
task,
A4B4C05, Emphasis on schedule
exceeded emphasis on methods / doing
a good job,
A4B4C12, Contact with personnel too
infrequent to detect work habit /
attitude change
A4B1C04, Management follow-up or
monitoring of activities did not identify
problems,
A4B1C09, Corrective action
for previously identified
problem or event was not
adequate to prevent recurrence,
A4B2C09, Personnel selection did not
assure match of worker motivations / job
descriptions,
A4B4C04, Direct supervisory
involvement in task interfered with
overview role
*** The left column contains each A3 Level C node. The center column contains nodes from the other branches that can be coupled with the
associated A3 Level C nodes. The right column contains Level C nodes that can be coupled with the any of the A3 Level C nodes that are
associated with the B level node. This list shows recommendations only and is not all-inclusive.
DOE G 231.1-2 Attachment 7
08-20-03 Page 1
Attachment 7
CAUSAL ANALYSIS NODE DESCRIPTION
A1 Design / Engineering Problem –
An event or condition that can be traced to a defect in design or other factors related to configuration, engineering,
layout, tolerances, calculations, etc. Note: even though Engineering is explicitly only in the branch title, its use
throughout this branch is implicit. Also, it is Engineering as a function or process, not as a job title.
• B1 Design Input Less Than Adequate (LTA) – Input to a design that was lacking adequate information that was
necessary for the design.
• B2 Design Output LTA – Inadequate design output that did not meet the customer’s expectations or design
requirements.
• B3 Design / Documentation LTA – Design or documentation that did not include all of the required information and
did not comply with document control and record requirements.
• B4 Design Verification / Installation Verification LTA – Design reviews, testing, independent inspections, and
acceptance were not in compliance with customer expectations and/or site requirements.
• B5 Operability of Design / Environment LTA – Personnel or environmental factors were not considered as part of
the design.
A1B1C01 - Design input cannot be met
Definition: The criteria and other requirements were so stringent that they could not be met. There were
conflicting criteria. Not all of the necessary references were included.
Examples: A flow controller could not adequately control flow during an infrequent operation. The flow
requirements for normal, emergency and infrequent operation covered too wide a range for a controller
to operate properly under all conditions.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Determine which mode of operations is causing the range to be too wide. Install a separate controller for that mode.
A1B1C02 - Design input obsolete
Definition: The criteria were out-of-date. An old version of a requirement or specification was used. Process
requirements/conditions changed and the changes were omitted from the input.
Examples: A valve failed because it was designed to operate under the original operating requirements of the plant
rather than to the revised operating requirements.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Replace valve with one designed for current operating requirements.
Section 14
A1B1C03 - Design input not correct
Definition: The wrong standards or requirements were used. The requirements were transcribed in error.
Examples: A valve failed because the design input had incorrect information concerning the chemical
concentrations in the system in which the valve would be used.
An o-ring failed because the design input defined incorrect temperatures for the system in which the o-
ring was to be used. The actual temperature extremes were much greater than those stated in the
Design Input.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Replace with equipment/material designed for operating environment.
Attachment 7 DOE G 231.1-2
Page 2 08-20-03
A1B1C04 - Necessary design input not available
Definition: The necessary requirements, codes, standards, etc. were not available to the designer.
Examples: A valve failed because the design input [performance requirements of the system] had been changed,
but the revised requirements had not been given to the designer.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Replace with valve designed for current requirements.
A1B2C01 - Design output scope LTA
Definition: The design did not consider all the possible scenarios. All the operating conditions, [normal and
emergency] were not included in the design.
Examples: A line ruptured because a flange failed. The flange was constructed of the wrong material because the
design did not consider all the possible chemicals that would be in the line during different operating
conditions. One that was not considered caused the flange to fail.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Replace with flange designed for current environment.
A1B2C02 - Design output not clear
Definition: The drawings were difficult to read. The specifications were difficult to understand. The specification
could be interpreted in more than one way.
Examples: A pump did not provide the necessary cooling water during an emergency. The pump was sized wrong
because the drawings were difficult to read and the wrong pump was ordered and installed.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Provide clearer copy of drawing and replace pump.
A1B2C03 - Design output not correct
Definition: The drawings and other specifications were incorrect. The final design output did not include all
changes.
Examples: A pump did not provide the necessary cooling water during an emergency. The pump was sized wrong
because the final design did not include changes identified in the safety analysis.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Install pump designed to new criteria.
A1B2C04 - Inconsistent design output
Definition: There were differences between different output documents. The drawings and other design
documents did not agree.
Examples: A pump did not provide the necessary cooling water during an emergency. The procurement
specifications were not updated to reflect final changes to the drawings.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Replace with pump designed to new criteria.
DOE G 231.1-2 Attachment 7
08-20-03 Page 3
A1B2C05 - Design input not addressed in design output
Definition: The specifications did not include all the requirements. Some criteria were left out of the design
Section 15
output.
Examples: A line ruptured due to a failed flange. The flange failed because it was constructed of the wrong
materials. Some potential process upsets were not identified in the input and were not addressed in the
output.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Replace with flange designed to all applicable criteria.
A1B2C06 – Drawing, specification or data error
Definition: The latest drawing revision was not referenced. The latest vendor information was not included in the
design documentation. The correct data was not noted on the design documentation request.
Examples: A recent print revision reflected that a modification was made to a steam supplied transfer pit. The
print reflected that a common header, instead of a dedicated header to each system supplied steam.
The as-found field condition reflected that each system still had a dedicated supply header.
Investigation found out that funds had run out when approximately 50% of the work had been
completed. The system had to be modified for continued operation. The prints were never revised to
reflect the modifications that were made.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Revise the design documentation and perform better checks of process system configuration.
A1B2C07 - Error in equipment or material selection
Definition: The correct vendor identification number was not used for procurement of equipment. The correct
grade of stainless steel was not specified for the material.
Examples: The wrong grade of piping was specified and installed in a caustic piping system. Grade 304L
Stainless Steel piping was mistakenly specified and installed in a system that contained a highly
caustic solution. The use of this incorrect piping code resulted in premature failure of the newly
installed system.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Replace piping with the proper piping per applicable codes.
A1B2C08 - Errors not detectable
Definition: Personnel were unable to detect errors [by way of alarms or instrument readings] during or after the
occurrence. A serious error went unnoticed because there was no way to monitor system status.
Note: It is unreasonable to expect all systems and equipment to have alarms; however, important safety-
related equipment should have reliable error detection systems.
Examples: A tank fill was in progress. Initial tank level had been determined using the dipstick. There was no
level alarm on the tank to indicate that overflow was imminent. The standard practice was to mentally
time the closure of the inlet valve knowing the flowrate of the centrifugal pump. The inlet valve was
on the opposite side of the tank from the dipstick. Thus, the tank overflowed.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Consider installation of tank level alarm.
Attachment 7 DOE G 231.1-2
Page 4 08-20-03
A1B2C09 – Errors not recoverable
Definition: The system was designed such that personnel were unable to recover from error discovered before a
failure occurred.
Note: Important safety-related equipment should be designed so that detected errors can be alleviated before
system failure occurs.
Examples: A computer operator started an automatic operating sequence, controlled by a distributed control
Section 16
system, before the valving lineups in the process area had been completed. Even though operators in
the field called in to tell the operator to stop the operation, the computer was not programmed to allow
interruption of the sequence. As a result, process flow was routed to waste.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Reprogram operating sequence to allow abort.
A1B3C01 – Design / documentation not complete
Definition: The designs and other documentation for equipment were incomplete. Items were missing from the
documentation. A complete baseline did not exist.
Examples: A waste tank overheated because incompatible materials were mixed. The baseline documentation
was not complete. It failed to show a line that emptied into the tank. The line apparently was installed
during original construction, but the drawings did not show it.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Update drawing.
A1B3C02 – Design / documentation not up-to-date
Definition: Drawings and documents were not updated when changes were made. Documents/drawings did not
reflect the current status.
Note: Problems with this node will often be multiple coded. The system for controlling documents may not
be adequate. Another problem could be that changes are being made without proper authorization and
are, therefore, not being entered into the system.
Examples: An acid spill occurred during a line break. Lockouts had been performed based on current drawings.
The drawings were not up-to-date and did not show an acid stream that had been tied into the line.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Update drawings.
A1B3C03 – Design / documentation not controlled
Definition: The design documentation was not controlled per site requirements for document control and records.
Examples: During a recent assessment, an individual preparing some design documentation was noted using
“Uncontrolled” and “Information Only” design documentation to complete a Design Change Form.
When questioned he responded that he did not have to contact document control because he was the
only person responsible for the system and no other changes had been made to the system since the last
modifications he had completed.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Contact site document control and verify the latest revision status of necessary design documentation.
DOE G 231.1-2 Attachment 7
08-20-03 Page 5
A1B4C01 - Independent review of design / documentation LTA
Definition: A required review was not performed on the design. The review was not performed by an independent
reviewer. The design had problems passing the functional testing.
Examples: A tank failed because it was not constructed of materials suitable for the environment in which it was
installed. The designer was not familiar with the area where the tank was to be used and did not know
that it was a corrosive environment. An independent review by a knowledgeable reviewer was not
conducted.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Change affected procedure[s] to insert independent verification step. Note this would imply that another Apparent
Cause was under Written Communication Content LTA [A5B2].
• Assign additional independent reviewer[s] to design function. Note this would imply that another Apparent Cause
Section 17
was under Work Organization & Planning LTA [A4B3].
A1B4C02 - Testing of design / installation LTA
Definition: Testing was not included as part of the design acceptance process. The testing did not verify the
operability of the design. Design parameters did not successfully pass all testing criteria.
Examples: A Flow Indicator failed testing because the test plan was not reviewed and approved by the Design
Agency. The test engineer requested a pressure rating that when applied to the system over
pressurized the flow indicator, which caused the test to fail.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Have the Design Agency review and approve the test plan. Examine the flow indicator, replace if necessary, and
perform the test using the correct pressure rating.
A1B4C03 - Independent inspection of design / installation LTA
Definition: Independent Inspection attributes were not included in the design installation. Required Hold/Witness
points were not verified by Quality Assurance (QA). Hold/Witness points did not pass the acceptance
criteria. Commercial Grade Material was not adequately dedicated and documented.
Examples: A Safety Class designed system required QA Independent Inspections.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Disassemble the system and have the Owner Examiner perform the required examinations.
A1B4C04 - Acceptance of design / installation LTA
Definition: The customer had problems with acceptance of the design, testing, and/or verification.
Example: During the Operations Acceptance it was noted that the required design change documentation was not
included in the completed document package.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Obtain the required design change documentation and include it as part of the completed work package.
A1B5C01 - Ergonomics LTA
Note: Ergonomics is defined as the science that seeks to adapt work or working conditions to suit the worker.
The design should include provisions for eliminating problems encountered by personnel performing
tasks. This may also include problems resulting from Physical or Environmental factors.
Attachment 7 DOE G 231.1-2
Page 6 08-20-03
Definition: Inadequate ergonomic design contributed to the occurrence. The operator was physically incapable of
performing the required task. The operator had to go too far to respond to the alarm. Personnel
mobility or vision was restricted. An individual had difficulty reaching the equipment or assumed an
awkward position to complete a task. The event was caused because illumination levels were not
sufficient for task performance.
Examples: A Balance of Plant (BOP) Operator was making rounds when a response alarm activated. The control
room operator requested the BOP Operator to go to the alarm location. When arriving at the newly
installed panel the Operator could not gain access from the direction or see the panel from where they
were standing. The Operator had to go around the building to gain access to the area to be in a position
to provide the information requested by the Control Room Operator. This resulted in loss of valuable
time necessary to take the necessary compensatory actions.
A control room operator made a mistake in reading a meter that was placed at ceiling level. The
position of the meter did not allow the operators to take readings from floor level. It was necessary to
use a stepladder to take the reading.
Section 18
A serious incident occurred when glare caused by improper overhead lighting prevented an operator
from detecting that an important annunciator tile was illuminated.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Assure design includes ease of access to area and takes into consideration time and distance that a worker has to
travel to perform tasks due to response requirements.
• Reduce lighting in area.
• Replace with glare resistant glass.
A1B5C02 - Physical environment LTA
Definition: Inadequate equipment controls or control systems [e.g., push-buttons, rotary controls, J-handles, key-
operated controls, thumb-wheels, multiple switches, joysticks] contributed to the occurrence. The
control failed to provide an adequate range of control for the function it performs. The control was
inadequately protected from accidental activation. Similar controls were indistinguishable from one
another. Controls were in too close proximity of each other. Operating conditions [e.g. room
temperature, work location, physical location, restricted vision, personal protective equipment,
excessive noise, arrangement or placement of equipment] affected performance of the task. Lighting
was inadequate. Noise was a factor.
Examples: An operator made an error in reading a meter because of the unusual scale progression. Instead of a
scale with major markings divided by units of five [i.e., 5, 10, 15, 20], the scale was divided into units
of six [i.e., 6, 12, 18, 24].
Two computer systems, located side-by-side in the facility, were programmed using different color
schemes. On the first system, the color red indicated flow to the process. On the second system, red
indicated the lack of flow. Because of the inconsistency in color coding between the two systems, an
operator who normally worked on the second system allowed a tank to overflow when he was
temporarily assigned to the first system. His mindset was that red indicated lack of flow.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Replace with a meter with standard scale progression.
• Install a warning as to nonstandard scale progression.
• Select one of the two color schemes as standard. Reprogram the other unit. Retrain affected system operators.
A1B5C03 - Natural environment LTA
Definition: Exposure to heat, cold, wind, and rain was not included in the design. Earthquake tested devices were
not included in the design. System was not designed to withstand flooding, freezing, or high wind
conditions. Lightning suppressing devices were not included in the design. The event was caused by
excessive exposure of personnel to a hot or cold environment.
DOE G 231.1-2 Attachment 7
08-20-03 Page 7
Examples: During an extreme cold spell, a mechanic damaged an expensive piece of equipment by dropping a
tool into its moving parts. Even though the mechanic was wearing gloves, his hands were so cold that
he was unable to get a firm grip on the tool.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Provide portable space heaters. Note: this will not be acceptable in certain environments.
A2 Equipment / Material Problem
Is defined as an event or condition resulting from the failure, malfunction, or deterioration of equipment or parts,
including instruments or material.
• B1 Calibration for Instruments Less Than Adequate (LTA) - Calibrations did not include all the essential elements.
Section 19
Equipment as-found condition was less than adequate.
• B2 Periodic / Corrective Maintenance LTA - Periodic maintenance was not established for the equipment,
instrument or component. The periodic maintenance was inadequate. Corrective maintenance was inadequate to
correct the problem. Equipment history did not exist for the instrument or component. The equipment history was
incomplete.
• B3 Inspection / Testing LTA - Scheduled inspection/testing did not exist for the instrument or equipment. The
inspection/testing was inadequate or not performed as required. The inspection/testing did not include all the
essential elements. Note: A1B4 should be used for Design Testing.
• B4 Material Control LTA - The problem was due to the inadequate handling, storage, packaging or shipping of
materials or equipment. The shelf life for material was exceeded. An unauthorized material or equipment
substitution was made. Spare parts were inadequately stored. There was an error made in the labeling or marking.
• B5 Procurement Control LTA - The error was due to inadequate control of changes to procurement specifications or
purchase orders. A fabricated item failed to meet requirements or an incorrect item was received. Product
acceptance requirements failed to match design requirements or were otherwise unacceptable. Note: This is only for
equipment and materials, procured services are addressed in A4B2C10.
• B6 Defective, Failed or Contaminated - An event was caused by a failed or defective part. The material used was
defective or flawed. The weld, braze or soldered joint was defective. The component reached the end of its
expected service life. There was electrical or instrument noise interference or interaction. Foreign material or
contaminant caused the equipment or component to fail.
A2B1C01 - Calibration LTA
Definition: The equipment involved in the incident was not included in a routine calibration program. Calibrations
were performed too infrequently. The calibration did not include all the essential elements.
Examples: A tank overflowed because the level indicator was out of calibration. The instrumentation was not
included in a calibration program.
A tank overflowed because of faulty liquid level instrumentation. The instrument calibration was not
performed in accordance with the manufacturer’s recommended frequency for calibrations.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Calibrate instrument.
• Incorporate manufacturer’s recommended frequency into the calibration program.
A2B1C02 - Equipment found outside acceptance criteria
Definition: An event occurred as a result of equipment that was found outside of the specified acceptance criteria.
The instrument calibration drift was outside of the acceptable range. Process instrumentation was
outside of acceptable range criteria due to a standard that was out of calibration.
Attachment 7 DOE G 231.1-2
Page 8 08-20-03
Examples: A pressure switch is required to activate when vessel coil pressure is at a high pressure of 5.83 to 5.95
pounds per square inch (psi). During a functional check, the pressure switch activated at 5.98 psi. The
pressure switch had drifted outside of the acceptable calibration criteria.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Adjust the pressure switch back into calibration and re-perform the functional test.
• Replace pressure switch if warranted by adverse trend or decreased performance.
• Increase pressure switch calibration frequency to improve instrument reliability.
Section 20
A2B2C01 - Preventive maintenance for equipment LTA
Definition: An equipment malfunction was caused by a failure to carry out scheduled preventive maintenance.
Preventive maintenance was not established for the equipment or component that failed. Preventive
maintenance was scheduled too infrequently. The preventive maintenance was incomplete. Preventive
maintenance was performed on some of the components but not on others.
Examples: A motor failed due to a lack of lubrication. Routine maintenance had not been performed on the
equipment.
A motor failed due to a lack of lubrication. Preventive maintenance had been performed on the
equipment but on a longer frequency than that recommended by the manufacturer.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Repair/replace motor.
• Establish routine maintenance frequencies for failed equipment.
• Adjust preventive maintenance frequencies to correspond to manufacturer’s recommendations.
A2B2C02 - Predictive maintenance LTA
Definition: Predictive maintenance was not established for the equipment. The established frequency was
inadequate to prevent or detect equipment degradation. The established method used to prevent or
detect equipment degradation was inadequate.
Examples: A bent fan shaft went undetected and generated high vibrations that caused the catastrophic failure of a
building supply fan. Predictive maintenance was not used to manage and assess equipment
performance / condition.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Repair/replace fan components as necessary.
• Establish predictive maintenance for the failed equipment to help detect the onset of equipment problems.
• Identify the appropriate predictive maintenance strategy to better evaluate machinery condition.
A2B2C03 - Corrective maintenance LTA
Definition: Corrective maintenance was performed but failed to correct the originating problem. The equipment
or component was reassembled improperly during corrective maintenance. Other problems were noted
during maintenance activities that were not corrected. The actual job of performing a maintenance
activity was complete, but was not performed correctly.
Examples: Corrective maintenance was performed to replace a malfunctioning time delay relay to address
problems associated with the building exhaust fans. After replacement of the relay, it was discovered
that the problem still existed with the building exhaust fans.
Corrective maintenance was performed to replace a malfunctioning time delay relay to address
problems associated with the building exhaust fans. After installation of the relay, it was discovered
that the relay contacts were positioned incorrectly.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
DOE G 231.1-2 Attachment 7
08-20-03 Page 9
• Replace the time delay relay per approved work instructions.
• Assure work instructions specify correct setting/position for relay contacts prior to installation.
A2B2C04 – Equipment history LTA
Definition: Equipment history / records did not exist for the equipment that malfunctioned. The history for the
equipment that malfunctioned was incomplete / inadequate. The history did not contain all the
information necessary to assure equipment reliability. Knowledge of equipment history would have
prevented the incident or lessened its severity.
Section 21
Examples: A tank overflowed because of faulty liquid level instrumentation. Previous problems had occurred
with the instrumentation. This was not known by Maintenance personnel because there was no
equipment history available.
A tank overflowed because of faulty liquid level instrumentation. The problem had occurred on
similar equipment in other facilities. This was unknown to facility personnel since the equipment
history did not contain information on similar equipment.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Expand the maintenance inspection / activity to include equipment history files to collect and use historical data for
Structures, Systems, and Components (SSCs).
• Establish provisions for similar equipment within equipment history program. Note: this may also indicate a
weakness in the implementation of lessons learned [A4B1C06].
A2B3C01 – Start-up testing LTA
Definition: Functional testing did not exist for the equipment or system prior to placing them in service. Start-up
testing was inadequate for the equipment or system being placed into service.
Examples: A fire alarm system failed to activate during a fire in a process room. The system had not been
functionally tested prior to being placed in service.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Functionally test fire alarm system for process room.
• Assure systems are functionally tested prior to being placed in service. Note: this may also imply an inadequate
written communication [A5] or work organization / planning deficiency [A4B3] as an Apparent Cause.
A2B3C02 – Inspection / testing LTA
Definition: Required testing / inspection was not established or performed for the equipment involved in the
incident. The required testing / inspection was performed at an incorrect frequency. The acceptance
criteria for the required testing / inspection were inadequately defined. All essential components were
not included in the required testing / inspection.
Examples: An emergency generator failed to start during a power outage. The generator had not been included in
the routine functional testing program.
An environmental release occurred because of a slow leak from a chemical tank. Thorough quarterly
inspections were specified for the tank, but more frequent inspections were not required to identify
leaks.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Establish routine functional testing for the generator.
• Review routine functional testing program to assure applicable equipment is included. Note: this corrective action
strongly implies that there is at least one programmatic weakness
• Revise the required inspection program for the tank to include more frequent leak inspections. Note: this may also
imply inadequate written communication [A5] as an Apparent Cause.
Attachment 7 DOE G 231.1-2
Page 10 08-20-03
A2B3C03 – Post-maintenance / post-modification testing LTA
Definition: The post-maintenance or post-modification testing specified was not performed or was performed
incorrectly. The post-maintenance or post-modification testing was completed, but the testing
requirements were less than adequate. The post-maintenance or post-modification testing was not
performed in accordance with the schedule for testing.
Examples: A high-pressure steam flow interlock failed to actuate when the high coil pressure limit was reached
Section 22
inside a process vessel. Post-maintenance testing was not completed for the system prior to its being
placed in service.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Establish and perform post-maintenance testing for the interlock.
A2B4C01 – Material handling LTA
Definition: Material / equipment was damaged during handling. Material / equipment was “mixed up” during
handling.
Note: This code is for handling occurring onsite. Problems with handling occurring offsite would be coded
under Procurement control LTA [A2B5], Management Methods LTA [A4B1], Means not provided for
assuring adequate equipment quality, reliability, or operability [A4B2C08], or Written communication
content LTA [A5B2].
Examples: The wrong pump was installed in a line. The mechanics were installing several pumps and had them
all on a cart. They were “mixed up” and installed in the wrong locations.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Install pumps in correct line. Provide separation between distinct work packages and materials. Note: this may also
imply a work organization / planning deficiency [A4B3] as an Apparent Cause.
A2B4C02 – Material storage LTA
Definition: The material, equipment or part was stored improperly. The material, equipment, or part was damaged
in storage. The material, equipment, or part had weather damage. The material, equipment, or part
was stored in an environment [heat, cold, acid fumes, etc.] that damaged it. Inadequate preventive
maintenance [cleaning, lubrication, etc.] was performed on spare parts.
Examples: An absorption column installed to remove contaminants from solvent did not operate as designed.
Investigation revealed that the absorbent material used to pack the column had been stored outside and
uncovered. The damaged material reduced the efficiency of the column.
A pump failed shortly after installation, much earlier than anticipated given the life expectancy of the
pump. Investigation revealed that the pump had been stored in spare parts for a long time. During the
storage, no preventive maintenance, such as cleaning and lubrication, had been performed as specified
in the manufacturer’s instructions for storage.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Refill absorption column after verifying that absorbent packing material is acceptable.
• Verify remaining stock of absorbent material is stored under cover.
• Review spare parts inventories to identify and address preventive maintenance concerns, which will be included in a
preventive maintenance program. Note: this may also imply that preventive maintenance was LTA [A2B2C01] as an
Apparent Cause.
DOE G 231.1-2 Attachment 7
08-20-03 Page 11
A2B4C03 – Material packaging LTA
Definition: Material or equipment was packaged improperly. The material or equipment was damaged because of
improper packaging. Material or equipment was exposed to adverse conditions because the packaging
had been damaged.
Note: This code is for packing occurring onsite. Problems with packing occurring offsite would be coded
under Procurement control LTA [A2B5], Management Methods LTA [A4B1], Means not provided for
assuring adequate equipment quality, reliability, or operability [A4B2C08], or Written communication
content LTA [A5B2].
Examples: An electronic system received water damage because it was not packaged in waterproof packaging as
Section 23
specified in the packaging requirements.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Repair/replace the damaged material or equipment.
• If reusable, restore material packaging to design specifications.
A2B4C04 – Material shipping LTA
Definition: The material / equipment was transported improperly. The material / equipment was damaged during
shipping.
Note: This code is for shipping originating within the local organization. Problems with shipping originating
at another organization would be coded under Procurement control LTA [A2B5], Management
Methods LTA [A4B1], Means not provided for assuring adequate equipment quality, reliability, or
operability [A4B2C08], or Written communication content LTA [A5B2].
Examples: A technical limit was exceeded because several containers of nuclear material were not shipped in
approved shipping containers.
Sensitive electronic equipment transported by rail was damaged.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Revise shipping procedure to include caution for using approved containers. Note: this may also imply inadequate
written communication [A5] or a work organization / planning deficiency [A4B3] as an Apparent Cause.
• Repair/replace damaged equipment. Assure replacement equipment is shipped under more favorable conditions.
A2B4C05 – Shelf life exceeded
Definition: Material, equipment, or parts that had exceeded the shelf life were installed. Materials continued in
use after the shelf life was exceeded.
Note: Shelf life can be highly dependent on storage environment, i.e., this could be a storage issue
[A2B4C02] instead or as well.
Examples: A technical limit was violated because resin that had exceeded its shelf life was used for a separation
process. When old resin is used, separation efficiency of different elements is greatly reduced.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Replace affected resin with material within its shelf life.
• Assure remaining resin stock is within its shelf life.
A2B4C06 – Unauthorized material substitution
Definition: Incorrect materials or parts were substituted. Material or parts were substituted without authorization.
The requirements specified no substitution.
Attachment 7 DOE G 231.1-2
Page 12 08-20-03
Note: This code is for material substitution occurring onsite. Problem with material substitution occurring
offsite would be coded under Procurement control LTA [A2B5], Management Methods LTA [A4B1],
Means not provided for assuring adequate equipment quality, reliability, or operability [A4B2C08], or
Written communication content LTA [A5B2].
Examples: A valve failed, causing a spill to the environment. The valve was not the one specified in the
requirements. Since the specified one was not available, a substitute valve had been installed without
the proper review and authorization.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Install correct valve or get proper approval for the substitute.
• Determine why unapproved substitution was made and correct that cause.
A2B4C07 – Marking / labeling LTA
Definition: There was an error made in the labeling or marking. Equipment identification, labeling, or marking
was less than adequate.
Examples: Procurement specification required that parts be stamped 304 SS for use in a critical safety significant
Section 24
system. A facility was shutdown because the parts did not meet marking specification.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Replace parts with proper marking specification to bring system into compliance.
• Evaluate procurement specification to provide additional controls for assurance and validation of parts and material
used in safety related systems.
• Determine the necessary controls to assure proper procurement and selection of materials/parts.
A2B5C01 – Control of changes to procurement specification / purchase order LTA
Definition: Changes were made to purchase orders or procurement specifications without the proper review and
approvals. The changes resulted in purchase of the wrong material, equipment, or parts.
Examples: A process upset occurred because the acid used was out of specifications. Investigation revealed that
the purchase order had been changed without the proper review and approval.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Replace affected acid.
• Determine if affected acid could be used somewhere else [excess chemicals program]. If not, dispose of acid in
accordance with applicable regulations.
A2B5C02 – Fabricated item did not meet requirements
Definition: The item of concern was not fabricated according to the requirements specified in the procurement
specifications/purchase requisition.
Examples: A pump failed because it was not fabricated with materials specified in the procurement specifications.
As a result, it did not withstand the corrosive environment where it was installed.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Contact manufacturer for replacement pump made of correct materials.
A2B5C03 – Incorrect item received
Definition: An item received was not the one ordered. The inconsistency was not recognized. The item was
accepted rather than returned.
DOE G 231.1-2 Attachment 7
08-20-03 Page 13
Examples: A process upset occurred because the acid used was out of specifications. When the acid was received,
personnel in material receiving did not recognize that it was not what was ordered. It was accepted
and sent to the operating facility for use.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Replace affected acid.
• Provide additional instructions to receiving inspectors on recognizing chemicals.
• Determine if affected acid could be used somewhere else [excess chemicals program]. If not, dispose of acid in
accordance with applicable regulations.
A2B5C04 – Product acceptance requirements LTA
Definition: The product acceptance requirements were incomplete. The product acceptance requirements did not
address all the safety concerns for the item. The requirements did not address all the concerns for
efficiency. The product acceptance requirements did not address all the safety concerns for the items.
Examples: A pump failed shortly after installation because it was constructed of material incompatible with the
environment in which it was used. The acceptance requirements correctly addressed the size of the
pump but did not address specifications for the corrosive environment in which the pump would be
installed.
A pump of the wrong size was installed in the process. Investigation revealed that the acceptance
requirements used when the pump was received were not the same as the design requirements.
Section 25
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Repair/replace the failed pump.
• Assure procedure for acceptance requirement development has sufficient cautions on incorporation of all applicable
criteria. Note: this may also imply inadequate written communication [A5] as an Apparent Cause.
A2B6C01 – Defective or failed part
Definition: A part/instrument that lacked something essential to perform its intended function. The degraded
performance of a part or a component contributed to the failure of the component, equipment, or
system. Note: this does not to explain why the object failed or was defective. Therefore, this node
should be multiple coded.
Examples: A motor on a pump that had only been in operation for six months failed due to defective windings.
A large turbine/generator bearing failed during normal equipment operation. Follow-up investigation
determined that an internal oil pump contributed to the premature failure of the turbine bearing.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Replace the failed components (i.e., windings, oil pump, bearings, etc.) and return the system to normal operation.
A2B6C02 – Defective or failed material
Definition: A component failed because the material used was not adequate for the application. The material used
was found to be defective, flawed, or damaged. Note: this does not explain why the object failed or
was defective. Therefore, this node should be multiple coded.
Examples: A steel plate on a waste storage tank leaked due to failed material. The steel from which the plate was
fabricated exhibited laminations that formed during the extrusion process when the steel was rolled at
the manufacturer’s plant.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Replace the steel plate with a replacement suitable for the harsh chemical environment.
Attachment 7 DOE G 231.1-2
Page 14 08-20-03
A2B6C03 – Defective weld, braze or soldering joint
Definition: A specific weld/joint defect or failure. Note: this does not explain why the object failed or was
defective. Therefore, this node should be multiple coded.
Examples: A leak occurred due to cracks in weld at the bottom of a tank. The weld cracked due to inadequate
length of time allowed for pre-heating of surface prior to making the weld.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Repair the weld using correct surface pre-heat procedures.
• Assure pre-heat and interpass temperatures for weldments are conducted and controlled in accordance with
procedures.
A2B6C04 – End of life failure
Definition: The failure resulted from equipment or material having reached the end of its expected / normal service
life. The failure was a result of the normal aging process for this component.
Examples: A facility had determined that it was more cost effective to run a certain pump to failure rather than
provide preventive maintenance that only yielded minimal life extension. Note: if the facility has not
made this determination, then it is under A2B2.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Replace the failed pump.
A2B6C05 – Electrical or instrument noise
Definition: An unwanted signal or disturbance that interfered with the operation of equipment.
Examples: Actuation of a radio in close proximity to instrumentation caused indication fluctuations.
Section 26
The Distributed Control System (DCS) installed in the facility received erroneous alarms due to excess
instrumentation noise on the system. The noise was a result of not having an adequate building
grounding system installed.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Consider posting location to eliminate radio use.
• Evaluate the use of shielding for affected components.
A2B6C06 – Contaminant
Definition: Failure or degradation of a system or component due to foreign material (i.e., dirt, crud, impurities,
trash in river intake, etc.) or radiation damage due to excessive radiation exposure. Note: can be
related to any material in an unwanted location.
Examples: During post-maintenance testing, flowrate from a centrifugal pump was less than specification. Upon
subsequent disassembly, it was determined that a rag had been left in the pump, partially blocking the
intake.
A valve actuator coupling was leaking. The coupling o-ring had become embrittled due to radiation
exposure.
During facility surveillance of diversion valve timers for the Segregated Cooling Water System, a
diversion valve failed to operate completely. Dirt and crud inside the valve mechanism caused the
valve to bind.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
DOE G 231.1-2 Attachment 7
08-20-03 Page 15
• Remove the rag and reassemble the pump. Note: this also implies administrative controls [A4B1 or A5] for foreign
material exclusion are less than adequate.
• Replace the o-ring. Note: this may also imply that preventive maintenance was LTA [A2B2C01], since radiation
embrittlement can be predicted, therefore, the o-ring could have been replaced prior to failure.
• Establish a means to filter the water prior to entering the diversion valve. Note: this could imply that preventive
maintenance was LTA [A2B2C01], since more frequent refurbishment of the valve could have reduced the binding.
The life cycle costs of the preventive maintenance could be less expensive than the modification cost to install the
filter.
A3 Human Performance Less Than Adequate (LTA) –
An event or condition resulting from the failure, malfunction, or deterioration of the human performance associated with
the process. Note: Strictly speaking, A3B1, A3B2, & A3B3 nodes are only applicable when “problem-solving,” although
this does not have to be conscious. These are not the intended coding when not engaged in solving a problem, e.g.,
falling asleep because of prescription medication [which might be A3B4C01 or A5B4C06]. Further, these codes are for
individual actions or lack thereof. If an event has multiple occurrences of the same A3 C node[s], it is time to look for
other rationale behind the behavior. Yes, there are single examples of group performance that is LTA. However, when
it is multiple examples, there is usually another explanation. For example, the control room operators at Three Mile
Island mutually incorrectly diagnosed several of the accident indications and also mutually avoided application of
several potential recovery paths. These errors were eventually traced to how their training had treated these
potentialities.
• B1 Skill Based Errors – Inattention or over-attention to performance of work affected the event.
• B2 Rule Based Error – A misapplication of a good rule for behavior or application of a bad rule applied for behavior
Section 27
during the work process impacted the event. Note: application of this node is not limited to misapplication of
procedures. Rules are often mental rather than written.
• B3 Knowledge Based Error – The problem was solved without using stored rules for behavior. The involved
personnel were in a problem solving/troubleshooting mode. Note: Some people find it easier to think of this node as
“Lack of Knowledge Based Error” since the essential gap is experiential.
• B4 Work Practices LTA – The capacity to perform work was impaired. The act to incorrectly perform work was
deliberate.
People create all non-natural systems. There is no such thing as a perfect [error-free] system. All people who come into
contact with any given system both affect the system and are affected by it. This applies to the designers, builders,
operators and management. Although the degree/amount of affect may vary, there is an affect. Further, the vast
majority of people [>95%] do not intend to commit an error. When a human performance error occurs, it is the
individual that acted incorrectly, however, the real question is what in the system[s] failed to allow that action? In this
context, a “system” can be hardware, administrative, or mental*. We essentially never deal with a single system in
isolation. Similarly, the permutation or combination of impacted systems is constantly changing. This means that before
the fact analysis of all potential system interactions is basically impossible.
Thus, the intent is for A3 cause codes to be “coupled” (Refer to Attachment 6 of the Guide) with cause codes somewhere
else on the CAT for each applicable causal factor. The A3 node needs to be captured to allow future root cause analysis
on the human performance clusters. The other nodes are to fix the system(s) and annotate clusters other than human
performance. You cannot permanently fix the individual [thereby preventing recurrence]. There are a few cases where it
may be acceptable not to determine couplets:
• Deliberate violations [<3%]. These are limited to those cases where the individual, with conscious forethought,
violates the accepted norms.
• Where the individual is at >2 standard deviations (σ)**, i.e., is an outlier in human performance. There is no
intentional error or violation in this case. For example, the individual has been repeatedly trained [for a rule or
knowledge based error] and the error still recurs with that person. By definition, this is an isolated case. These are
not limited to training issues.
Even here, there are ancillary issues that need to be addressed. Why didn’t the supervisor know about [take action on]
this individual previously? What in the system broke down to allow this individual to get into this position [both in
terms of where there were untoward challenges to his/her physical capabilities or uncompensated degradation of
psychological environment that challenged mental capabilities]? If the total of these exceptions starts running at more
Attachment 7 DOE G 231.1-2
Page 16 08-20-03
than 5% of the facility’s total evaluations, it is time to investigate why, i.e., the facility’s application of causal analysis is
faulty.
Section 28
In summary, A3, typically, is coupled with other coding from other branches. It is recognized that the number of links
and number of impacted systems will vary with the event significance category. However, this is not to be used as a
rationale for single-coding a particular event. The Attachment 6 matrix provides suggested links between the A3 nodes
and the rest of the CAT. It is reiterated that while there is reason to believe that the nodes listed are more likely than
others, there is no constraint that these are the only potential links. Similarly, while it is possible that there is no link for
a particular situation, overuse of this extreme exception is indicative of other issues.
* Mental systems are tricky because there is no requirement for them to be conscious. For example, most people are
not aware of the influence of “culture” on their actions. The converse is also true, i.e., people are typically not aware of
their influence on various systems.
** All intentionally designed systems are statistical in concept [nothing works perfectly every time]. They are designed
for normative behavior/capabilities on the part of the “operator.” If the “operator” falls outside of these norms [>2σ],
he/she cannot be expected to perform error free [be solely culpable for the event].
A3B1C01 - Check of work was LTA
Note: All corrective actions defined for this C node can be used in any combination to mitigate or prevent the
any “Skill” error from recurring. Suggested corrective actions are:
A. Install blocking devices between similar controls.
B. Identify critical steps of a task to increase attention.
C. Increase supervision or include additional personnel to peer check critical steps of a task.
D. Avoid multi-mode switches or controls.
E. Implement practice of rereading previous two/three steps of a procedure before proceeding with
task, if distracted or interrupted.
F. Improve planning to reduce distractions or interruptions.
G. Eliminate unnecessary time pressure through scheduling.
H. Rotate individuals through various jobs.
I. Practice using skill to maintain proficiency.
J. Simplify and standardize manual checks (skill of the craft).
K. Automate some tasks less suited for human beings.
Definition: An individual made an error that would have been detectable and correctable if a check of the
completed, or partially completed, work was performed.
Examples: A transcription error was made when entering process data into a procedure.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Identify critical steps of the task. Include peer checking for critical steps.
A3B1C02 - Step was omitted due to distraction
Definition: Attention was diverted to another issue during performance of the task and the individual committed
an error in performance due to the distraction.
Examples: Procedure steps were not properly completed because the performer was distracted and skipped a step
in the procedure.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Implement practice of rereading previous two or three steps in the procedure before proceeding with task for
affected individual.
• See note for A3B1C01.
A3B1C03 - Incorrect performance due to mental lapse
DOE G 231.1-2 Attachment 7
08-20-03 Page 17
Definition: The individual knew appropriate action(s) to take, but failed to initiate the correct action(s) based on
inattention/over-attention.
Section 29
Examples: A routine task was incorrectly performed when an individual forgot the correct action to take.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Improve planning to reduce distractions or interruptions.
• Review the work flow to see if checks can be put into place that would catch similar mental lapses.
• See note for A3B1C01.
A3B1C04 - Infrequently performed steps were performed incorrectly
Definition: An individual was not completely familiar with the tasks required based on not frequently performing
the tasks and not operating at a fluency level.
Examples: A particular method for reaching valving was used to install a lockout. Based on the Lockout Installer
infrequently installing a lockout on the particular system, an incorrect method was chosen for reaching
the valving and the installer was injured in the process.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Increase supervision or include additional personnel to peer check critical steps of the task.
• See note for A3B1C01.
A3B1C05 – Delay in time caused LTA actions
Definition: An individual performed the wrong actions based on an extended length of time expiring between the
time the task was defined and the time the task was completed.
Examples: A motor failed due to a lack of lubrication. Routine maintenance had not been performed on the
equipment. After an extended period of time, repair was made to the motor, but the Preventive
Maintenance was not reviewed for adequacy to assure lubrication performance. This was based on the
individual not recalling the cause for motor failure.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Improve planning to reduce distractions or interruptions.
• Assure inclusion of failure cause in equipment history. Note: this would be multiple coded as Equipment history
LTA [A2B2C04].
• See note for A3B1C01.
A3B1C06 - Wrong action selected based on similarity with other actions
Definition: An individual selected a wrong action out of a series of actions that appeared to be the same, but are
not.
Examples: Multiple procedure steps were similarly written that required addition of the same chemical, but each
step varied in timing and quantity of chemical.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Install blocking devices between similar controls.
• Place an explanatory note in the procedure just before, or in, the steps to notify the user that differences exist.
• See note for A3B1C01.
A3B1C07 – Omission / repeating of steps based on assumptions for completion
Definition: Individual, based on assumptions, concluded that activity steps were not completed or completed.
Based on the perceptions, an error occurred because the incorrect decision or assumption was made.
Attachment 7 DOE G 231.1-2
Page 18 08-20-03
Examples: Multiple steps that were similar and sequential in a procedure required completion. A shift change
occurred and no turnover was performed. Individual did not have enough knowledge of where the
previous shift left off, and assumed specific steps had been completed, but were not documented. The
individual proceeded with the procedure, but did not complete required steps in the procedure.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Implement practice of rereading previous two or three steps in the procedure before proceeding with task for
Section 30
affected individual.
• Implement policy to initial, date and time wherever a procedure is stopped prior to shift change.
• See note for A3B1C01.
A3B2C01 - Strong rule incorrectly chosen over other rules
Note: All corrective actions defined for this C node can be used in any combination to mitigate or prevent the
any “Rule” error from recurring. Suggested corrective actions are:
A. Clearly delineate key decision points in a procedure.
B. Eliminate procedure inconsistencies.
C. Simplify procedures.
D. Train individuals to Skill-Based mode (fluency).
E. Add “Forcing Functions” (fail safe mechanisms that allow performance only one way, the right
way).
F. Eliminate drawing and technical manual errors.
G. Improve knowledge of procedure bases.
H. Practice using multiple, alternative indications.
I. Promote practice of verbalizing intentions.
J. Practice on transition between procedures.
K. Eliminate unwise use of “Rule of Thumb”.
L. Specialize on specific, safety critical tasks (resident expert).
M. Improve human factors identification and layout of displays.
Definition: Individual chose behavior rules based on the number of times the rule(s) had been used successfully in
the past. The more times the rule(s) have been used successfully, the stronger the desire to apply the
rule(s) become.
Examples: An individual who did not use seat belts when driving vehicles was consistently applying a strong rule
to not use them, but was incorrectly choosing to use that rule over another rule that, if applied would
have guided the individual(s) to use seat belts.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Train individual(s) to a Skill Based performance mode (fluency).
A3B2C02 - Signs to stop were ignored and step performed incorrectly
Definition: Most activities generate indication of status [both positive and negative]. The human tendency is to
focus on the indications of success rather than all the indicators. The negative indicators are the “signs
to stop.” “Signs” are not necessarily physical.
Note: “Signs to stop” are not limited to any standardized list of error precursors. Yes, those can, and do,
have an effect. The Institute of Nuclear Power Operations short list of error precursors is built into the
Causal Analysis Tree [see Attachment 5 of this guide].
Examples: Time pressure (in a hurry) is a common sign to stop for an event. When an individual(s) is in a hurry
to complete tasks and move on to additional tasks, errors can occur during the effort in completing the
tasks.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Add “Forcing Functions” (fail safe mechanisms that allow performance only one way)
• See note for A3B2C01.
DOE G 231.1-2 Attachment 7
08-20-03 Page 19
A3B2C03 - Too much activity was occurring and error made in problem solving
Definition: This error was initiated when the individuals committing the error experience information overload.
The right set of decisions was not made based on too many details to process mentally.
Examples: Multiple activities were taking place in the control room. The control room was required to take
readings, set up transfer paths, and fill out log sheets documenting activities. In addition, a number of
people were in the control room creating distraction. When taking a reading and recording the result,
the operator skipped a required step in the procedure by not focusing on the procedure completion due
to other activities and distractions in the control room.
Section 31
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Train individual(s) to a Skill Based performance mode (fluency).
• Establish a policy to allow only essential personnel into the control room during select evolutions.
• See note for A3B2C01.
A3B2C04 - Previous successes in use of rule reinforced continued use of rule
Definition: If a rule for behavior has been used successfully in the past, there is an overwhelming tendency to
apply the rule again, even though circumstances no longer warrant the use of the rule.
Examples: In the past, chains had been used to prevent ball valves from manipulation. The recent facility practice
had been to use alternative valve locking devices for the valves that had been proven to be more
effective in preventing the valve from being manipulated. However, the facility did not prevent the use
of chains. Lockout Installers were comfortable using chains and continued to use the chains instead of
the alternative locking devices.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Add “Forcing Functions” (fail safe mechanisms that allow performance only one way)
• Develop a list of ball valves and state their best lockout device. Provide list to Installers.
• See note for A3B2C01
A3B2C05 - Situation incorrectly identified or represented resulting in wrong rule used
Definition: Individual interpreted facts based on training and experience that helped form stored mental
knowledge from which the individual interpreted the facts. When the individual used the stored
knowledge, the right set of training and experience was sometimes not selected based on the existing
facts. A broader search of the stored knowledge would have been necessary to explain the existing
facts.
Examples: A transfer of solutions was being made and the receipt vessel liquid levels were increasing. The
situation appeared normal when an alarm was received that indicated the vessel was overflowing. A
review of the situation revealed that the liquid level indicator installed in the vessel had been elevated
[a different, higher position] in the vessel in the past. Although the individual taking the liquid level
readings had known about the elevation change to the liquid level indicator, the information was not
recalled when the transfer was being performed.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Practice using multiple alternative indications.
• See note for A3B2C01.
A3B3C01 – Attention was given to wrong issues
Note: All corrective actions defined for this C node can be used in any combination to mitigate or prevent the
any “Knowledge” error from recurring. Suggested corrective actions are:
Attachment 7 DOE G 231.1-2
Page 20 08-20-03
A. Practice, practice, practice using methodical problem solving techniques with novel unfamiliar
situations.
B. Design displays to enhance use without keyboarding.
C. Practice using team and communication skills.
D. Assign the role of devil’s advocate.
E. Develop and practice lateral thinking skills.
F. Use system component knowledge and fundamental principles of physical sciences associated
with plant systems and components in unfamiliar problem situations.
G. Train on and verify accuracy of system and social mental models.
Definition: Selective mental processing of information was targeted at the wrong issues and was not focused on
Section 32
the right issues. Often the individual focus was centered around what was psychologically important
instead of targeted on what was logically important.
Examples: Maintenance was being performed on a pump. A flex nylobraid line was to be disconnected and
replaced. This line was connected to the pump and was connected by a slip-on fit onto a barbed fitting
and secured with an aviation clamp. In order to remove the line, the individual placed his foot on the
pump to apply backward leverage for the purpose of pulling the line off the barbed fitting. In doing
this action, the individual was focused on getting the job done instead of hazards associated with
falling down if the line suddenly released from the fitting under extreme force.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Develop and practice lateral thinking skills. For this specific example, develop and practice of the thinking skills
could be applied through the use of ‘Field non-punitive observation/mentoring program’ intervention concepts and
practices.
• Develop a standard method for removing the line and place it in the maintenance procedure.
A3B3C02 - LTA conclusion based on sequencing of facts
Definition: An individual, when establishing a timeline or recalling step-by-step compilation of facts as they
occurred in an event, sometimes reordered the sequence which affected the conclusion based on the
facts.
Examples: Chemicals added to a process vessel that had to be added in a specific sequence to prevent a reaction of
the chemicals. After a reaction had occurred, the individual(s) investigating the event inadvertently
failed to recall the actual sequence of chemical additions, believed the sequence to be correct when it
was not correct, and overlooked the cause for a chemical reaction in the vessel.
An individual was in a problem solving performance mode, he/she incorrectly recalled the sequence of
steps that were performed to disassemble a piece of equipment. During the re-assembly, the sequence
that was recalled for disassembly was applied and the equipment could not properly be reassembled.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Train on and verify accuracy of system mental models.
• See note for A3B3C01.
A3B3C03 - Individual justified action by focusing on biased evidence
Definition: An individual was overconfident in evaluating the correctness of his/her knowledge. The chosen
course of action was selected based on evidence that favored it and contradictory evidence was
overlooked.
Examples: Often, the statement is used: “this is the way we did it where I used to work”. The problem with this
mindset is that existing conditions, parameters, controls, etc. may be different enough to the
individual(s) past experiences to require a different set of actions than what was required in the past.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Practice, Practice, Practice using methodical problem solving techniques with novel unfamiliar situations.
DOE G 231.1-2 Attachment 7
08-20-03 Page 21
• Practice using team and communication skills.
• See note for A3B3C01.
A3B3C04 - LTA review based on assumption that process will not change
Definition: Individual believed that no variability existed in the process and overlooked the fact that a change has
occurred leading to differing results than normally realized.
Section 33
Examples: Vessel concentrations of material were calculated based on a heel of material (solution left in bottom
of vessel after flushing) believed to be present in the vessel. The normal flushing method provided for
a specific amount of solution to be flushed through the vessel. However, during a flushing of the
vessel, the amount of solution was less than specified for required flushing. The result was a larger
heel containing more concentration of material than had been calculated.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Develop and practice lateral thinking skills.
• See note for A3B3C01.
A3B3C05 - Incorrect assumption that a correlation existed between two or more facts
Definition: Wrong assumptions were made based on the belief that two or more facts are related to each other and
incorrect actions were taken based on the assumption.
Note: This also covers the case where there is an incorrect assumption that two or more facts do not correlate
when they do.
Examples: During a transfer of solutions from one vessel to the next, it was recognized that liquid levels on the
chart recorder were increasing and the transfer had been initiated. However, further investigation
revealed that a valve was incorrectly positioned allowing solution from another source to flow into the
receipt vessel and the sending vessel was set-up for the wrong transfer path.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Use system component knowledge and fundamental principles of physical sciences associated with plant systems
and components in unfamiliar problem situations.
• See note for A3B3C01.
A3B3C06 - Individual underestimated the problem by using past events as basis
Definition: Individuals tend to oversimplify events. Based on stored knowledge of past events, the individual
underestimated problems with the existing event and plans for fewer contingencies than will actually
be needed.
Examples: Contamination incidents had been a regular occurrence in the past for the facility. The source of these
contamination incidents had usually not been determined. The current contamination occurrence had
an identifiable source, but extensive surveys were required to locate it. The individual performing the
surveys believed the current event was like the past events and did not perform an extended set of
surveys in the facility to locate the source.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Practice skills using methodical problem solving techniques with novel unfamiliar situations.
• See note for A3B3C01.
A3B4C01 – Individual’s capability to perform work LTA
Definition:
Attachment 7 DOE G 231.1-2
Page 22 08-20-03
• Sensory/Perceptual Capabilities LTA - The problem was due to less than adequate vision [e.g., poor visual acuity,
color blindness, tunnel vision]. The problem was caused by some defect in hearing [e.g., hearing loss, tone
deafness]. There was a problem due to some sensory defect [e.g., poor sense of touch or smell].
• Motor/Physical Capabilities LTA - The causal factor was attributable to trouble with inadequate coordination or
inadequate strength. The problem was due to inadequate size or stature of the individual involved. Other physical
limitations [e.g., shaking, poor reaction time] contributed to the problem.
Section 34
• Attitude/Psychological Profile LTA - The problem was due to a poor attitude on the part of an individual. The
individual involved showed signs of emotional illness. Note: Symptoms like the following are often warning signs of
poor attitude or mental illness:
1. Horseplay
2. Absence from work location
3. Failure to perform expected work
4. Maliciousness
5. Poor performance under stress
6. Poor psychological health
7. Use of drugs or alcohol
8. Insubordination
9. Failure to work well or communicate with others
10. Disregard for safety rules
Note: These capabilities refer to physical and mental attributes [over which the employee has no control]
and/or disease related symptoms [which may or may not be under the control of the individual]. It
may take professional diagnosis to determine if this code is applicable. Related codes are Ergonomics
LTA [A1B5C01] and Job scoping did not identify potential task interruptions and/or environmental
stress [A4B3C07]. Intentional non-compliance is A3B4C02. Also, this code relates only to a single
individual, group behavior is entirely different.
Examples:
• Sensory/Perceptual Capabilities LTA - An operator read the wrong temperature on a chart that recorded
temperature for several tanks. The chart was color coded. The operator was partially color blind and confused the
readings. He recorded a temperature as being in range when the actual temperature was out of range.
• Motor/Physical Capabilities LTA - A tank overflowed because the operator could not close the valve. The valve
was large and difficult to close. The operator did not have the strength to close the valve. By the time he obtained
help in closing it, the tank had overflowed.
• Attitude/Psychological Profile LTA - An operator failed to close a valve after filling a tank, resulting in a process
upset. The operator showed symptoms of alcohol abuse and absence from his work location.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Sensory/Perceptual Capabilities LTA - Confirm diagnosis and reassign to duties that do not utilize affected
capabilities.
• Motor/Physical Capabilities LTA - Determine if the valve can be made easier to close [i.e., repair, replace or
increased preventive maintenance]. If not, consider [non-punitive] reassignment of operator.
• Attitude/Psychological Profile LTA - Process through Employee Assistance Program.
A3B4C02 - Deliberate violation
Definition: The action on the part of the individual was a deliberate action to commit human error.
Note: Be very careful in the application of this code. It may take professional diagnosis to determine if the
action was intentional or the result of something beyond the control of the individual [A3B3C01].
There is usually some form of personal gain associated with this code. Also, this code relates only to a
single individual; group behavior is entirely different. If this code is cited in more than ~5% of the
incidents for a given facility, there is most likely some other underlying cause.
Examples: An individual cut the lock on a defined lockout point for a Lockout/Tagout on a system to bypass the
lockout.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
DOE G 231.1-2 Attachment 7
08-20-03 Page 23
• Apply the Constructive Discipline program.
A4 Management Problem –
Section 35
An event or condition that could be directly traced to managerial actions, or methodology (or lack thereof). A
“management” problem attributed to management methods (directions, monitoring, assessment, accountability, and
corrective action), inadequate resource allocation, work organization and planning, supervisory methods and/or change
management practices.
Note: Apparent Cause Corrective Actions for this branch in particular easily slip into correcting the program as
opposed to the implementation. Fixing the program is the realm of Root Cause[s]. The analyst is cautioned to
gauge Corrective Actions appropriately.
• B1 Management Methods Less Than Adequate (LTA) - The processes used to control or direct work-related plant
activities, including how manpower and material was allocated for a particular objective. Note: This cause section
addresses management-controlled practices and policies and requires that the investigator gain familiarity with the
standards or expectations that exist for performing work. [See note for A4B4.]
• B2 Resource Management LTA - Evaluation of the processes whereby manpower and material were allocated to
successfully perform assigned tasks. Note: B2 serves as an expansion to B1, Management Methods, since both B1
and B2 are important inter-related factors. B2 provides more in-depth causal nodes for evaluating manpower and
material issues impacting performance of work-related activities.
• B3 Work Organization & Planning LTA – Problems in how the work to be performed was organized. This would
include work scope, planning, assignment and scheduling of a task to be performed. Note: While B3 addresses the
organization and planning of work, failures in this node usually imply related failures in Supervisory Methods
addressed in B4.
• B4 Supervisory Methods LTA - Causes that can be traced back to the immediate supervision and evaluated
techniques that were used to monitor, direct and control work assignments. Note: this is supervision as a function
not as a title. A manager can be the supervisor of another manager or a non-supervisor [by title] can be
functioning as a supervisor. Problems with other than immediate supervision are coded under B1, B2 or B5 [which
does not say that immediate supervision problems cannot be multiple coded under those B nodes].
• B5 Change Management LTA – Problems caused by the process by which changes were controlled and
implemented by management as organizational needs change to accommodate new business needs.
A4B1C01 - Management policy guidance / expectations not well-defined, understood or enforced
Definition: Personnel exhibited a lack of understanding of existing policy and/or expectations, or
policy/expectations were not well-defined or policy/expectation is not enforced.
Example: A key piece of equipment in a process safety system failed. The policy stated that the required
maintenance and inspections were to be performed annually. Because of the difficulty of the work and
the amount of work involved, maintenance was performed the last two weeks of odd numbered years
and the first two weeks of even numbered years. This allowed nearly two years between the required
maintenance and inspections. The policy was confusing and not well defined, leaving room to
interpret a 24 month gap between maintenance and inspections when it was intended to have not more
than a 12 month gap between maintenance and inspections.
Section 36
During a routine inspection, containers of controlled material were found to be in violation of a safety
policy regarding required information on container labels. In order to comply with the security policy
concerning controlled material access, the safety policy was violated. The two policies were
contradictory regarding labeling of controlled material.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Modify administrative control to stipulate maximum period of 12 months.
• Modify safety and security policies to balance concerns and still meet operational mission.
Attachment 7 DOE G 231.1-2
Page 24 08-20-03
A4B1C02 - Job performance standards not adequately defined
Definition: Measurement of effectiveness could not be performed for a specific job function due to lack of defined
standards.
Example: During an extended facility outage, routine surveillance of process alarm panels was not performed.
As a result, a chemical leak went undetected for two days. Facility management had not clearly
defined normal surveillance standards during the extended outage.
An operator made a mistake operating a process that was color-coded on the distributed control
system. The operator was color-blind. There were no job performance standards or requirements
concerning color blindness for this job even though being able to discriminate among colors was
necessary to operate the process. Note: this [or similar] example should be multiple coded under
A3B4C01.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Assure job performance standards for surveillance requirements during extended outages are adequately defined.
• Reassign affected individual to position that does not require color discrimination.
• Assure medical review of job performance standards where the ability to discern colors is essential to adequate
performance of this assigned task and modify task requirements accordingly.
A4B1C03 – Management direction created insufficient awareness of the impact of actions on safety / reliability
Definition: Management failed to provide direction regarding safeguards against non-conservative actions by
personnel concerning quality, safety or reliability.
Example: An event occurred in a waste tank because incompatible materials were mixed. The Process Hazards
Review (PHR) had been performed, but it failed to consider the possible sources of material that could
be added to the tank.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Reexamine the baseline for the PHR to assure the specific incompatible materials have been documented and
appropriate safeguards are integrated into management expectations, organizational programs and system designs
such that employees are trained and skilled in knowing operational limitations and safety parameters.
A4B1C04 - Management follow-up or monitoring of activities did not identify problems
Definition: Management's methods for monitoring the success of initiatives were ineffective in identifying
shortcomings in the implementation.
Example: Job-specific bioassay sampling program for tritium requires personnel to leave a sample at the end of
Section 37
the workshift as required in the Radiation Work Permit. If the sample is not left prior to leaving work,
the employee is in noncompliance with regulatory requirements and places the company at risk for
Price Anderson Amendments Act enforcement liability. The first formal opportunity to detect
noncompliance was during weekly employee logsheet sign-ins and sampling label checks by the
Radiological Controls Organization supervisor. Multiple noncompliance events had occurred over
time with related corrective actions tracked and closed; however, corrective actions were ineffective in
preventing the problem from recurring.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Develop bioassay sampling interventions that detect noncompliance at the point of failure.
A4B1C05 - Management assessment did not determine causes of previous event or known problem
Definition: Analysis methods failed to uncover the causal factors of consequential or non-consequential events.
Example: Over a period of time, several related ORPS events involving noncompliance with operational
requirements had been reported to DOE. With each similar event being reported, the significant
DOE G 231.1-2 Attachment 7
08-20-03 Page 25
category progressed from low-level performance monitoring and trending to Significant Category 1.
Price Anderson Amendments Act fines for violations were assessed against the company. The
respective program office conducted two formal root causes. Corrective actions were tracked to
closure with corrective action effectiveness reviews performed to prevent recurrence. Recommended
solutions from the first reported event to the most recent event have basically been the same; however,
noncompliance is still problematic for the company where risk is high for a potential repeat violation.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Determine why causal analysis was not implemented in former cases. Implement appropriate corrective actions.
A4B1C06 - Previous industry or in-house experience was not effectively used to prevent recurrence
Definition: Industry or in-house experience relating to a current problem that existed prior to the event, but was
not assimilated by the organization.
Note: This code is not necessarily limited to the site’s formal lessons learned program. It can apply to any
event of which the facility had been made aware.
Example: The DOE customer shared problematic issues from another DOE site concerning radiation protection
issues. The site had obtained the information and discussed several corrective actions but did not take
any action [or only implemented a single action]. A similar problem occurred several months later. It
was evident that the department organization had not fully assimilated the significance of the prior
issue.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Re-review the information provided particularly actions taken at other site, determine if actions taken were effective
and implement appropriate corrective actions.
• Assure work is prioritized that allows appropriate level analysis to be performed on lower level trending information
as an investment in prevention.
• Assure analysis of performance trending data is comprehensive enough based on the severity of the event to
employees and the business and potential consequences if the event is not corrected in a manner to prevent
recurrence.
Section 38
A4B1C07 - Responsibility of personnel not well defined or personnel not held accountable
Definition: Responsibility for process elements (procedures, engineering, training, etc.) was not placed with
individuals or accountability for failures of those process elements was not placed with individuals.
Example: A technical limit for the length of time allowed between airflow checks on a stack exhaust system was
violated. The Operations Department considered the checks to be maintenance items. The
Maintenance Department considered them to be an operations item. Responsibility for the checks was
not defined.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Develop memorandum of understanding to establish responsibility.
A4B1C08 - Corrective action responses to a known or repetitive problem was untimely
Definition: Corrective action for known or recurring problem was not performed at or within the proper time.
Example: A tank overflowed because the liquid level instrumentation was out of calibration. Corrective
measures had been identified during a previous overflow of the tank but had not been implemented
when the second overflow occurred.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Calibrate liquid level instrumentation. Note: this should be multiple coded under Calibration for instruments LTA
[A2B1].
Attachment 7 DOE G 231.1-2
Page 26 08-20-03
• Either promptly implement corrective actions from previous event or implement compensatory measures or justify
delay.
A4B1C09 - Corrective action for previously identified problem or event was not adequate to prevent recurrence
Definition: Management failed to take meaningful corrective action for consequential or non-consequential events.
Example: Over a period of time, several related ORPS events involving noncompliance with operational
requirements for had been reported to DOE. With each similar event being reported, the significance
category progressed from low-level performance monitoring and trending to Significance Category 2.
Recommended solutions from the first reported event to the most recent event were basically the same
with procedural changes and employee training.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Review implementation of causal analysis technology and frequency of analyses.
• Develop new corrective actions that do not rely on procedural changes or employee training.
A4B2C01 - Too many administrative duties assigned to immediate supervisors
Definition: The administrative load on immediate supervisors adversely affected their ability to supervise ongoing
activities.
Note: This is a problem with the management of the supervisor not his/her supervisory methods [A4B4].
This is non-task activities [not actively supervising employees]. Task overload is A4B2C02.
Example: A first line supervisor and his experienced crew were assigned a work package to repair a leaking tank
containing a hazardous chemical. The supervisor was also involved with other important activities
supporting the First Line Managers’ (FLM) Council, safety program initiatives within his department,
and the division golfing event for the United Way Campaign. During the maintenance repair, the crew
failed to execute a critical step in the repair process that resulted in further damage to the tank. At the
time of the event, the supervisor was making a formal presentation to the FLM Council on issues
impacting the work environment.
Section 39
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Reduce non-task items assigned to affected supervisor.
• Examine work planning, scheduling and work prioritization processes and the adequacy of communications
channels (oral and written) among the supervisor, the maintenance crew and the management team to accommodate
duties beyond direct supervisory responsibilities.
A4B2C02 - Insufficient supervisory resources to provide necessary supervision
Definition: Supervision resource is less than that required by task analysis considering the balance of procedures,
supervision and training.
Note: This is a problem with the management of the supervisor not the supervisory methods [A4B4]. This is
too many jobs to be actively supervised at once. Non-task [not actively supervising employees]
overload is A4B2C01.
Example: The Operations Department recently restructured to new performance management contract initiatives
and other company conditions. Several experienced employees retired and/or left the organization and
replacements were part of a new multi-skilled job ladder. Job responsibilities and duties were being
redistributed to accommodate the reduced staffing and organizational consolidation. Although many
job titles had remained the same during the last several years, most of the job functions had revised
duties and tasks. Formal position descriptions and related job task analyses had not been reviewed for
several years. Regulatory requirements had gradually become more stringent over the years, reducing
the amount of time supervisors had available. Previous jobs that took an hour for the supervisor to
complete now took 4 hours to accomplish. Therefore, even less time was spent on important job tasks
DOE G 231.1-2 Attachment 7
08-20-03 Page 27
where supervision was needed. Considering tasks involving procedures, training and supervisory
responsibilities, supervisory resources were not adequate to meet the need.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Update position descriptions and job task analyses based on company initiatives and regulatory changes. Modify
assignments based on updated documentation.
• Review department’s ability to adequately plan, prioritize and staff for human resources based on changes in scope
driven by changing business conditions.
A4B2C03 - Insufficient manpower to support identified goal / objective
Definition: Personnel were not available as required by task analysis of goal/objective.
Example: Changes in the site’s waste generation program required increased characterization of waste streams to
accommodate storage in metal storage vaults versus direct ground burial. With multiple waste streams
in laboratory operations and the unpredictability of those streams, Generator Certification Official
(GCO) manpower was added to staff the certification function. Other job skills impacted by the
program change included radiological control technicians (increased survey calculations and shipment
preparation) and technical lab personnel (increased GCO training, slow downs in performing lab-
specific functions resulting from characterizing, bagging and preparing waste products for shipment).
Waste storage locations for staging characterized waste impacted facility housekeeping programs and
generated additional ALARA concerns. Appropriate task analysis had not been conducted on the
manpower needed to adequately support the overall waste management program for lab operations.
Section 40
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Review adequacy of job/task assignment, modify task analysis or manpower loading as necessary to meet program
changes.
• Reduce workload in related area to provide necessary personnel in the critical area.
A4B2C04 - Resources not provided to assure adequate training was provided / maintained
Definition: Training resources were not available as required by task analysis.
Example: Recent site restructuring efforts reduced some program manpower resources based on the percentage
of budget the organization contributed to the overall program. Additionally as part of restructuring,
early retirement and voluntary separation incentives were offered to qualified personnel to meet
corporate budget targets by the end of the Fiscal Year. A new Multi-skilled Technician job ladder was
introduced to accommodate certain organizational shifts in manpower and to fill some essential job
functions. All the changes created movement within the workforce that required additional training to
meet various mission essential tasking. New task analysis of job functions revealed that there were not
enough resources to provide adequate training for the newly restructured organization.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Provide additional training resources, rotate existing training personnel from less important tasks, or implement
compensatory actions and justify delay in resource allocation.
A4B2C05 - Needed resource changes not approved / funded
Definition: Corrective actions for existing deficiencies that were previously identified were not approved or
funded.
Example: A small project experienced problems in costs and schedule. Issues and performance deficiencies with
related corrective actions were being tracked by project management, but due to emphasis on schedule
delays and cost overruns, some of the corrective actions were not approved or funded. It was
determined through independent management evaluation that had some of the corrective actions been
Attachment 7 DOE G 231.1-2
Page 28 08-20-03
funded and approved, the project would have been able to detect its downward trend earlier and
prevented further project performance degradation and reduction of scope.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Review implementation of performance monitoring and trending program to assure project scope stays within
acceptable parameters of performance (quality, production, schedule costs) using leading, real-time and lagging
indicators.
• Assure acceptance criteria for deviations between performance and expectations are known prior to restarting the
project.
• Re-examine original baseline planning documents to assure plan is sensitive to unexpected business changes.
A4B2C06 - Means not provided to assure procedures / documents / records were of adequate quality and up-to-
date
Definition: A process for changing procedures or other work documents to assure quality and timeliness was
nonexistent or inadequate.
Example: A Lockout/Tagout (L/T) to perform Diesel Generator (D/G) maintenance was ready for review and
Section 41
approval. The First Line Manager (FLM) for Maintenance was unable to locate electrical prints for the
L/T. The FLM walked down the lockout plan and checked adjacent electrical panels for other feeds
that may have been associated with the D/G. No other electrical feeds were identified other than those
already listed on the L/T. In addition to the Subject Matter Expert, Utilities, Engineering and
Operations had approved the L/T. The FLM signed the approval block on the L/T. The next day the
mechanic was performing determination and voltage checks on the D/G and discovered 120 volts. The
process for assuring appropriate documentation was available to verify and validate the L/T was
inadequate.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Provide electrical prints [or equivalent compensatory measure] for D/G L/T.
A4B2C07 - Means not provided for assuring adequate availability of appropriate materials / tools
Definition: A process for supplying personnel with appropriate materials or tools did not exist.
Example: A employee was cutting plastic with a table saw when several teeth broke off the blade, causing
material to kick back and rip off the employee’s fingernail. The manufacturer produced the blade as
part of their “woodworking line.” The carbide-tipped, 12-inch blade with 60 teeth had become the
“blade of choice” by the site for general-purpose cutting. The manufacturer recommended not using
the woodcutting blade for cutting plastics, but recommended another blade product designed
specifically for plastics. The process to assure employees were provided with the proper tool was not
adequate.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Review adequacy of man-machine interface and adequacy of assumptions used in tool selection among employees
and supervisors.
A4B2C08 - Means not provided for assuring adequate equipment quality, reliability, or operability
Definition: A process for assuring personnel’s equipment was satisfactory did not exist.
Example: During a confined space entry into a valve box to leak test inter-connecting pipeline to a low level
waste system, the Radiation Work Permit (RWP) required Personal Protective Equipment (PPE),
including two sets of Tyvek [water-resistant, disposable coveralls], booties and a respirator. Blotter
paper was placed into the floor area of the pit to help control transfer of contamination while the
employee was standing on the floor. The employee began leak-testing piping using a leak test soap
solution. Once the leak was fixed, the employee exited the pit and removed shoe covers, harness, first
layer of Tyvek and outer gloves with assistance from the Radiological Controls Technician. Upon
proceeding to the buffer area and removing the second layer of Tyvek, respirator and inner gloves,
DOE G 231.1-2 Attachment 7
08-20-03 Page 29
contamination of 20,000 dpm beta-gamma was discovered on the right shoe and 24,000 dpm beta-
gamma was on the left pant leg. The RWP called for two sets of Tyvek and non-skid shoe covers. The
work package, which included the use of liquid soap solution in a dry work environment, did not
include the need for waterproof PPE. The process for assuring reliable and operable equipment was
available to adequately protect the employee was unsatisfactory.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Include guideline for waterproof PPE when working with water-based solutions. Note: this should be multiple
Section 42
coded under Written communications content LTA [A5B2].
• Review implementation of organization interfaces with focus on hazards analysis completeness.
A4B2C09 - Personnel selection did not assure match of worker motivations / job descriptions
Definition: Personnel selection processes failed to determine a mismatch between motivation and job description
prior to task.
Note: Mismatch with motivations is under this code. Mismatch with skills is under A4B4C09.
Example: An employee was assigned, along with a small group, to routine production of work packages. Under
the system in use at the time, each package had to be individually created in several separate databases
for the different forms involved. The employee took it upon himself to integrate the various files into a
single platform for work package creation for use by the entire group. This development effort
detracted from the employee's work output, however, and his manager voiced disapproval with the
distraction. The manager failed to realize that the investment involved with upgrading the work
process would eventually lead to vastly improved efficiency for the entire work group. The employee's
motivation - increasing long-term productivity - was in conflict with management's desire for short-
term increased work output.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Consider methods to increase manager’s ‘big picture.’
• Review implementation of management processes in assigning personnel to tasks based on proper knowledge and
training required in meeting performance standards/expectations and motivation of employee in accomplishing
assignment.
A4B2C10 – Means / method not provided for assuring adequate quality of contract services
Definition: A process for assuring quality contract services was being provided was nonexistent or inadequate.
Example: A subcontract had been awarded to a vendor for supplying low level radioactive waste containers that
met appropriate waste acceptance criteria and Department of Transportation packaging requirements.
The vendor utilized welding procedures as administrative controls to assure that welding processes and
qualifications met American Society of Mechanical Engineers standards. During a contract renewal
assessment visit, the vendor’s inspection/test records and their respective results were found to have no
irregularities. However, information entered on welding procedures and their corresponding
qualification records revealed discrepancies that did not meet welding code. The technical direction
provided to the welders responsible for fabrication and assembly of the waste containers had
compromised the quality of the services required by the subcontract. The process for assuring quality
contract deliverables was inadequate.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Review implementation of specific vendor’s internal assessment methods focusing on methods for detecting and
correcting discrepancies in quality.
A4B3C01 - Insufficient time for worker to prepare task
Attachment 7 DOE G 231.1-2
Page 30 08-20-03
Definition: Scheduling of the task did not adequately address the time frame required for accepted worker
preparation practices to occur.
Example: An electrical job was placed on the facility schedule, as normal, eight weeks in advance of the planned
Section 43
work start. Despite foreknowledge of the need for a lockout/tagout (L/T) plan to perform the work, no
L/T was requested from the lockout writer until the day before the job was scheduled to begin. The
lockout writer, given the time constraint, re-used an old L/T plan that had been written for a similar job
some months before. However, the work boundary was different on the new job, resulting in an
inappropriate isolation (i.e., the lockout plan did not adequately isolate the planned work boundary).
The lockout writer did not take the time to verify the work boundary against the lockout due to the
‘rush’ nature of the job. The time frame for scheduling the task did not adequately address the time
frame required for accepted worker preparation practices to occur.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Require Work Control Supervisor to review the facility schedule on a periodic basis. Any work on the schedule
would be assessed for L/T requirements.
• Review implementation of the organizational function or structure to plan and assign work consistent with work
priorities, examining work planning and communication barriers impacting teaming efforts.
A4B3C02 - Insufficient time allotted for task
Definition: Scheduled duration of the task did not adequately address known conditions or account for reasonable
emergent issues.
Example: A job was planned to perform decontamination activities in an Airborne Radioactivity Area (ARA),
competing with another job also requiring the use of the building’s breathing air system. Only one job
could be accommodated at a time. The facility manager decided to reduce the allotted duration of the
decontamination task from 3 days to 2 days to accommodate the other remaining breathing air work
deemed critical to the facility’s mission. During the course of the decontamination job, one of the
workers fell over waste bags that were left in the area, resulting in a sprained wrist. The workers were
under a time constraint to complete both tasks within the allotted 3-day period. The removal of the
waste bags prior to starting the decontamination task was not part of the initial work scope. The work
plan was to make a separate entry to remove the waste bags at a later time rather than add an additional
person for the decontamination entry.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Review implementation of work practices, focusing on shortcuts used to accelerate job completion when there is
perceived pressure to complete work.
A4B3C03 - Duties not well-distributed among personnel
Definition: The work loading of individuals within a group or team did not adequately address training,
experience, task frequency and duration, or other situational factors such that responsibility was
inappropriately distributed.
Example: As part of an organizational shuffle, a new engineer had been assigned as the Design Authority for the
breathing air system in the facility. The engineer held a degree in electrical, not mechanical
engineering, and as such was unfamiliar with the calculations performed on breathing air relief
devices. As a result, a pressure relief calculation error was not discovered, resulting in a premature
activation of the relief device which caused a job stoppage and additional protective clothing (i.e.,
plastic suit) expense. The work loading process did not adequately address situational factors to assure
responsibility was appropriately distributed among individuals within the group.
Section 44
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Provide the new engineer with training concerning the breathing air system.
• Review implementation of management processes in assigning personnel to tasks based on proper knowledge and
training required in performing the job assignment.
DOE G 231.1-2 Attachment 7
08-20-03 Page 31
A4B3C04 - Too few workers assigned to task
Definition: Job planning did not allot a realistic number of man-hours or the number of people necessary to
complete the task based on the scope of work described.
Example: A job was planned to perform a test of an electronic control system. This test typically took two hours
and involved three workers, one to manipulate controls, one to observe the time-dependent system
changes, and one to record results. The supervisor only allotted two workers, informing the second
that he would have to note the system changes and record them. During the middle of the test, the
observer/recorder had to abort the test as one of the test readings was missed while he was recording
previous observations.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Reschedule and perform test when three workers are available.
• Put a note in the test procedure prerequisites that this test requires three people to accomplish. Note: this should be
multiple coded under A5B2.
A4B3C05 - Insufficient number of trained or experienced workers assigned to task
Definition: Though the overall number of personnel assigned matched the planned man-hour allotment,
organization methods failed to identify that the personnel assigned did not have adequate experience or
training to perform the work.
Example: Four jobs underway were utilizing the facility breathing air system, since work was being performed in
Airborne Radioactivity Areas. There was a shortage of trained and qualified operators to perform
manifold attendant duties, so facility management assigned untrained operators at two of the job sites,
while providing for a third “trained and qualified” operator to move between the two sites to ‘check
up’ on the untrained coworkers. During the time the “trained and qualified” operator was unavailable
to one of the untrained operators, a fluctuation in breathing air pressure was observed. This fluctuation
did not trigger a breathing air alarm; however, the inexperienced operator immediately ordered the
exiting of the airborne area, resulting in a costly, unnecessary work stoppage. The organization failed
to assign personnel with adequate experience and training to perform the work.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Designate additional operators to become qualified as a Breathing Air System manifold attendant.
• Review implementation of work practices, focusing on shortcuts used to accelerate job completion when there is
perceived pressure to complete work.
A4B3C06 - Planning not coordinated with inputs from walkdowns / task analysis
Definition: The job plan did not incorporate information gathered during field visits or task analysis concerning
the steps and conditions required for successful completion of the task.
Example: An electrical job was planned to replace a malfunctioning light fixture. This fixture was not shown on
Section 45
the facility drawings, so the lockout writer included all lighting circuits in the general area on the
lockout, as well as a warning that the power source could not be confirmed. It was later discovered
that Electrical & Instrumentation had previously determined the correct feed for the light fixture in
question on a “Fix-It-Now” task, but this information was not communicated to the lockout writer or
work planner. As a result, one section of the facility was without lighting for half a day, when all that
was really necessary was to de-energize a single circuit. Additionally, operator time was wasted from
hanging a documented lockout/tagout, when a single-point lockout/tagout installed by the work group
would have sufficed.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
Attachment 7 DOE G 231.1-2
Page 32 08-20-03
• Review implementation of interface requirements required by one program but belonging to another program,
focusing on program design and work planning processes for standardization between the groups (Electrical &
Instrumentation, lockout writers and the work planners).
A4B3C07 - Job scoping did not identify potential task interruptions and/or environmental stress
Definition: The work scoping process was not effective in detecting reasonable obstructions to work flow (e.g.,
shift changes) or the impact of environmental conditions.
Note: This code applies to disruptions of circadian rhythms [biological functions based on 24-hour schedule]
caused by scheduling of work.
Example: Work was conducted in the underground liquid waste transfer cells. The cells were located in an
outdoor area between the facility’s buildings. Workers require plastic suits and breathing air systems
in this area to perform work. Previous entry to this area had been made when ambient temperatures
were in the mid-to-low 70s. A job required entry into this area later when ambient temperatures
typically reached 90 degrees or more during the hottest part of the day. The work package, which was
scheduled for a mid-morning start, required the use of ice barrels to chill breathing air being used by
the six workers. During the 8-hour job, 2 of the 6 workers became ill and asked to be cut out of their
suits and relieved from work. This resulted in premature termination of the job. Medical diagnosed
both workers as first aid cases due to heat stress. The work scoping process did not examine other
provisions or options for minimizing the impact of environmental conditions on the workers.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Review implementation of work practices that could potentially lead inadequately planning for contingencies.
A4B3C08 - Job scoping did not identify special circumstances and/or conditions
Definition: The work scoping process was not effective in detecting work process elements having a dependency
upon other circumstances or conditions.
Example: The facility was planning work for an upcoming outage period. Several of the jobs involved outages to
Section 46
building systems and equipment. One such case involved an electrical outage of Motor Control Center
(MCC) 1 to perform planned maintenance on a pump that served as a primary pump for the cooling
water to the instrument air compressor for that section of the facility. The primary pump was fed
directly from MCC 1. The secondary pump for the instrument air compressor was fed from a
secondary sub-feeder coming from MCC 2. MCC 2 was also scheduled for planned maintenance,
unrelated to work on MCC 1. Lockouts were applied for both MCC 1 and MCC2 simultaneously,
resulting in both the primary and secondary pumps rendered inoperative for the cooling water system
to the instrument air compressor. Neither the shift manager nor the operators recognized the impact to
the cooling water system and the instrument air compressor when the lockouts were applied. The work
scoping process did not detect the dependency the components had on other systems and
circumstances.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Review implementation of work planning processes, examining program-to-program interface (configuration
management, work planning, operations, engineering, maintenance) requirements.
A4B3C09 - Work planning not coordinated with all departments involved in task
Definition: Interdepartmental communication and teamwork did not support the work flow being planned.
Note: The key word is “coordinated.” By not getting input from affected departments, the work plan is likely
not to succeed.
Example: During a planned outage, the planned work flow called for conducting lockout/tagout procedures in a
specified order to support safe facility shutdown. The order of the lockouts dictated that verification of
isolation was performed by Electrical & Instrumentation (E&I) personnel at the same time in three
DOE G 231.1-2 Attachment 7
08-20-03 Page 33
different locations to support the work as scheduled. When tasked to support the plan, E&I could not
support lockout/tagout due to limited resources availability. As a result, the outage work schedule was
revised and extended four hours beyond the original timeline, since one of the lockouts had to be
removed and re-installed at a later time in order to accommodate the availability of E&I.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Review implementation of interface requirements required by one program but belonging to another program,
focusing on work planning processes between the groups (E&I, lockout writers and the work planners).
A4B3C10 – Problem performing repetitive tasks and/or subtasks
Definition: The work flow plan repeated tasks or subtasks to the detriment of successful completion of the
evolution.
Example: A lockout plan was written to install Ground Fault Circuit Interrupter (GFCI) receptacles in a room.
Since these devices are polarized, it was necessary to provide a temporary lift for the lockout in order
to test the polarity and verify correct installation. The lockout used involved multiple points, as all
receptacles in the room were being changed. Because of this, seven separate lockout plans were
written to allow for lifts to take place on each of the lockouts. It would have been more efficient to
install seven single-point lockouts and treat each receptacle as a separate task on the work order. Then,
any number of lifts could be performed on a given receptacle without the need to install a time-
consuming multiple-point lockout. The work flow plan process did not recognize the repetitive nature
of the job and the subsequent impact on effective utilization of resources.
Section 47
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Review implementation of lockout design, prioritization of work and staffing resources, focusing on excessive
implementation requirements.
A4B3C11 - Inadequate work package preparation
Definition: Though scoping and planning were adequately performed, the work package did not reflect the
information gathered from these activities. The work package did not accurately reflect the work that
was to be completed.
Example: A job was planned to replace a defective motor on a fan. Previously, Electrical & Instrumentation
personnel had verified that the control voltage for the motor was fed from the control transformer in
the Motor Control Center cubicle. As a result, de-energizing the single point would completely de-
energize the work boundary. However, the information was not included in the work package or the
lockout order. When the work crew arrived to perform the maintenance, they refused to sign onto the
lockout until the work boundary could be independently verified. Significant time was lost in
confirming that the lockout did indeed properly cover the scope of the job. Although scoping and
planning were adequately performed, the work package did not reflect the information gathered from
these activities.
A first line supervisor prepared a detailed job plan for changing out a pump. The new pump was
installed perfectly. The plan, however, did not provide instructions for handling the pump that was
removed from service. As a result, the crew disassembled the pump and sent the scrap metal to the
salvage yard. A significant amount of money was lost, since the original pump was expensive and was
to be rebuilt.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Review implementation of methods to assure necessary information used in decision-making by all involved parties.
• Review implementation of work practices, examining supervisory actions or decisions made without assessing the
entire situation and lacking the big picture.
A4B4C01 - Tasks and individual accountability not made clear to worker
Attachment 7 DOE G 231.1-2
Page 34 08-20-03
Definition: Tasks (and the individual accountability for the task) that were outside written guidance or training
were not made clear to the worker.
Example: The facility heating, ventilation and air conditioning (HVAC) control system reported a variation in
humidity control in one area of the building. The system engineer was contacted. The engineer
indicated that the humidistat for that area appeared to be out of adjustment, and suggested that one of
the operators adjust it to the correct set point. No procedure existed for adjustments to the controls.
The Shift Manager dispatched an operator to perform the adjustment. The operator was new and not
yet qualified on the system. When the operator arrived at the HVAC unit, he observed a hand-
inscribed hash mark on the adjustment knob for the instrument. He did not know that this mark was
the factory setting, not the correct setting for the building. When he adjusted the instrument to the
factory setting, the humidity situation worsened rather than improving, resulting in condensation
forming on the floor and creating a potential slip and fall hazard. The task and accountability, which
was outside written guidance and training, was not made clear to the worker.
Section 48
A step in the waste acceptance procedure required the waste receipt operator to compare the manifest
that arrived with the waste to the manifest that was sent to the site for review and approval prior to the
waste being shipped. This was done because changes were sometimes made in the waste before it was
sent. The procedure did not specify what was to be compared on the two manifests. The waste receipt
operator typically compared only the box numbers and weights. In one case, the box numbers and
weight had not changed but the box contents were significantly different. This box of waste was put in
the wrong location based on its actual contents.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
Review implementation of task assignments, focusing on assigning the right people to the right jobs. Note: this
should be double coded under A5B3.
•
• State in the waste acceptance procedure what items are to be compared between the original manifest and the
manifest that arrives with the shipment. Note: this should be double coded under A5B2.
A4B4C02 – Progress / status of task not adequately tracked
Definition: Supervision did not take the appropriate actions to monitor the task progress or status.
Example: An employee was tasked to design and develop a new program and related information management
system that would provide an assessment of team performance for the unit. The unit did not have any
defined integrated process and application tool available to the supervisors and workers that could
provide an assessment of the unit’s overall team performance. The supervisor did not have any
experience with development of administrative systems, so he left the project to the employee.
Working through the details and benchmarking with other groups, the employee presented the new
program to the supervisory team, only to be criticized for its perceived complexity and exposure of
performance information to the management team. Supervision did not take the appropriate actions to
monitor the task progress or status of the overall task.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Review implementation of the supervisory and technical task assignment, examining whether the task complexities
exceeded the capability of the supervisor to perform supervisory duties.
A4B4C03 - Appropriate level of in-task supervision not determined prior to task
Definition: Supervision did not adequately assess the task for points of supervisory interaction prior to assignment
to workers.
Example: The work package for an evolution included full details on the work to be done, but did not expressly
identify hold points for supervisory intervention. During his review, the supervisor scanned the work
instructions, looking for safety problems and his ability to execute the task. He made a few notations
to the planner about proper protective equipment, entering them on the Work Clearance Permit.
However, the supervisor failed to note that, at one point in the evolution, the mechanics were being
asked to make adjustments to an instrument. The supervisor failed to notify the planner to include a
DOE G 231.1-2 Attachment 7
08-20-03 Page 35
hold point in the work package so that he could be contacted. The planner scheduled this job on a day
when the supervisor who initiated the work package was on vacation. The stand-in supervisor
performed a pre-job brief, but did not realize that the instrument adjustment needed a hold point. The
work was completed without the needed supervisor’s check.
Section 49
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Review implementation of supervisory methods/work practices, focusing on supervisory actions or decisions that
are made without assessing the entire situation.
A4B4C04 - Direct supervisory involvement in task interfered with overview role
Definition: Supervision became so involved with the actual task steps that overall command and control were
adversely affected.
Example: During the installation of a new computer system, the immediate supervisor of the responsible crew
became so interested in the technical installation of the central control unit that he started performing
more of the technician duties. As a result, he was not as attentive to other members of his crew who
were installing the auxiliary unit. Some important checks were missed on the auxiliary unit. Upon
powering both units, the auxiliary unit failed to start, prolonging the completion of the task.
Supervision became so involved with the details of the new system that they failed to maintain
perspective on their overview role of the larger team performance picture.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Review adequacy of supervisory methods, focusing on the supervisor’s necessary perspective.
A4B4C05 - Emphasis on schedule exceeded emphasis on methods / doing a good job
Definition: Accepted standards for methods were not met due to supervision's focus on completing the activity
within a certain time frame.
Example: A project called for renovation of two rooms in a facility. As part of the renovation, a new electrical
panel was installed. The project was experiencing budget and scheduling pressures, and there was an
urgency to turn over the project to the operations organization before the project funding was
exhausted. As a result, a new electrical panel was never energized prior to turnover, and the normal
startup testing was not conducted. When the electrical panel was energized for the first time, the
breaker feeding it tripped immediately. It was discovered that the panel had been wired incorrectly by
the contractor, but the fault was never found due to a lack of startup testing. Accepted standards for
methods were not met due to supervision’s focus on completing the activity within a certain time
frame. Emphasis on schedule exceeded emphasis on doing a good job.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Rewire affected panel.
• Review implementation of supervisory methods and communications, focusing on supervisor’s not paying attention
and/or taking shortcuts to secondary tasks or indications during a task of perceived tight schedule.
A4B4C06 - Job performance and self-checking standards not properly communicated
Definition: Supervision failed to adequately communicate how standards for job performance and self-checking
could be applied to the actual job at hand.
Example: A plant crew was scheduled to cut up a large piece of equipment using a plasma arc cutter for the first
time. The first day’s activities proceeded with no problems, however, during an informal post-job
review among some workers, the workers modified the assignment and sequence of setup steps to
streamline the process. The only first day duty for the fire watch was to assure that the cutter was not
in danger while cutting. During the second day, the fire watch set up the work area for cutting,
including attaching the ground clamp to the piece to be cut and energizing the cutter. A rigger
positioning the material to be cut removed the grounding clamp from the material and placed it on a
Section 50
Attachment 7 DOE G 231.1-2
Page 36 08-20-03
metal cabinet where the energized cutter gun was resting. When the rigger looked up to locate the
crane hook, he took a step back and contacted the box and the cutter gun. He apparently trapped the
gun between the box and his thigh and depressed the trigger causing a pre-spark. The pre-spark
slightly shocked the rigger and burned a hole through his Personal Protective Equipment and burned
his leg. Supervision failed to adequately communicate how standards for job performance and self-
checking could be applied to the actual job.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Review implementation of supervisory methods in communicating adherence to job performance standards and
reinforcing application of self-checking methods to the task at hand by the workers, particularly for workers not
familiar with the task or associated job standards.
A4B4C07 - Too many concurrent tasks assigned to worker
Definition: Supervision failed to detect that concurrent job assignments for an individual exceeded the individual's
abilities.
Example: An engineering employee was responsible for multiple tasks, including the written preparation of
lockouts. Other tasks included: design, development, maintenance and upgrade of a computer database
system (used for multiple tasks in the facility); vice-chair of the facility Work Scope Review Team;
scheduling of project tasks; chair of scheduling process improvement task team; point of contact for
computer user support; and various ad hoc tasks assigned by management. As a result of this varied
and heavy workload, the employee had developed and utilized a database containing historical
lockouts for multiple items of equipment in the facility. During a lockout incident, the engineer re-
used a similar, but not identical, lockout job, and, as a result, the work boundary was inadequate.
Some of the equipment to be maintained was still energized when the mechanic tested it. Supervision
failed to detect that concurrent job assignments for an individual exceeded the individual’s abilities.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Review implementation of supervisory methods and work planning prioritization practices for appropriately
assessing task assignment work load of employees.
A4B4C08 - Frequent job or task “shuffling”
Definition: Supervision transferred a worker from one task to another without adequate time to shift attention
away from previous task.
Example: Two Electrical & Instrumentation mechanics, one experienced and the other with less than two years
experience, were completing a job to rewire a motor. The experienced mechanic was called away by
the supervisor to perform some emergent work. He left verbal instruction with the new mechanic to
‘bump the motor’ for rotation to assure that they had connected it correctly for purposes of phase
rotation. The new mechanic did as he was told, releasing the lockout and asking the operator to
energize the motor. However, the mechanic did not realize that his partner had forgotten to tape the
motor leads located inside the junction box in his haste of leaving for the emergent work. As a result,
the leads were resting against the inside of the junction box causing a ground fault explosion when the
operator energized the motor. Supervision transferred a worker from one task to another without
adequate time to shift attention from the previous task.
Section 51
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Repair junction box/motor, as necessary.
• Review implementation of supervisory methods and work practices, examining environmental conditions and/or
work planning processes that contribute to work overload and handling multiple tasks simultaneously where
committed actions are not successfully carried out.
A4B4C09 - Assignment did not consider worker's need to use higher-order skills
Definition: Supervision did not consider the worker's talents or innovative strengths that could be used to perform
more challenging work.
DOE G 231.1-2 Attachment 7
08-20-03 Page 37
Note: For mismatch with motivations, see A4B2C09.
Example: In an internal reorganization, three degreed engineers were changed in their job function from
‘engineers’ to ‘specialists’. One of the engineers, successful as a start-up engineer, was tasked to
perform coordinator duties for Installed Process Instrumentation (IPI) and Radiation Monitoring
Equipment (RME) as a specialist. Although the employee performed these functions extremely well,
his talents were dramatically underutilized. Another of the engineers eventually left the organization
and found more challenging work in another department. The third engineer remained in place and
created more challenging work by designing essential information systems for monitoring, tracking
and measuring business performance. While the engineers filled ‘specialist’ work positions on the
organization’s staffing chart, supervision did not consider their talents or innovative strengths that
could be used to perform more challenging work.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Return remaining Engineers to engineering positions.
• Review implementation of normal supervisory-human resource support processes and lack of teamwork culture that
contribute to the under utilization of human resources.
• Review adequacy of supervision to cultivate people, focusing on successor planning processes where task
assignments have been made where the wrong people are assigned to the wrong jobs.
A4B4C10 - Assignment did not consider effects of worker's previous task
Definition: Supervision did not adequately assess the previous task's impact upon the worker's ability to
implement the current task.
Example: An operator had completed a decontamination job in a hot environment. After a short break in a cool
area, the supervisor asked the operator to perform a procedure checking emergency battery-operated
exit lights. The procedure required the operator to climb ladders in several cases to reach the lights.
Although the supervisor had given the worker a rest period, and the emergency lights were all in air-
conditioned areas, the effects of several hours’ work, coupled with inadequate water intake, led to heat
cramps in the worker’s leg muscles. The cramps caused the worker to fall from a ladder during the
emergency light checks, resulting in an injury. Supervision did not adequately assess the previous
task’s impact upon the worker’s ability to implement the current task.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Review supervisory work practices, focusing on supervisory actions or decisions that are made without assessing the
mental and physical task demands and work environment factors with the capabilities and limitations of workers to
identify potential mismatches.
Section 52
• Review supervisory work practices where task complexity, scope or depth is underestimated and contingency
planning is inadequate.
A4B4C11 - Assignment did not consider worker's ingrained work patterns
Definition: Supervision failed to assess the incompatibility between worker's ingrained work patterns and
necessary work patterns for successful completion of the current task.
Example: A materials storage project called for converting a crane maintenance area in a former production
reactor to a warehouse type facility to accommodate storage of other nuclear material. Painters were
assigned the task of preparing the Crane Wash Area (CWA) floor for future painting activities.
Preparation activities included the use of a scabbler machine to remove a thin layer of paint from the
floor. The painters attended one of three pre-job briefings to address scabbling activities and noted
that Radiological Control Operations (RCO) personnel were originally assigned to the job but were
absent during the pre-job brief. The painters requested respiratory protection but the supervisor
explained that none was necessary due to the recent hazard analysis. The CWA had been posted as a
Contamination Area based upon a complete hazard review of known radiological conditions. Because
of the hazard review, RCO, Construction and Operations supervision decided that RCO coverage was
Attachment 7 DOE G 231.1-2
Page 38 08-20-03
not needed during the work activity. After each day’s activities, the painters successfully exited
through personnel contamination monitors. Upon completion of the work, RCO conducted surveys of
the CWA in efforts to rollback the work area and discovered fixed contamination on the floor. No
transferable contamination was discovered, although a survey of the bagged paint chips revealed some
low-level contamination. The fixed contamination resulted in RCO re-posting the area as a High
Contamination Area. Supervision failed to assess the incompatibility of the RCO work patterns in
working with known radiological conditions versus RCO analysis of unknown radiological conditions
resulting from the painters’ task. Supervision also failed to assess the incompatibility of the RCO
response with the safety concerns expressed by the painters prior to the work activity.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Review supervisory interface among organizations, focusing on formality of pre-job briefings, interface documents
and communications and promptly resolving conflicts between individuals and work groups before, during and after
the task starts.
A4B4C12 - Contact with personnel too infrequent to detect work habit / attitude changes
Definition: Supervision not aware of deviation from desired work habits/attitudes due to lack of interaction with
personnel.
Example: An operator, working on the back shift, was experiencing marital difficulties. While always a reliable,
conscientious employee previously, this new distraction created a somewhat indifferent attitude
towards work. Since the employee was working on the back shift, he was without supervision a
significant portion of the time. As a result, the employee began completing round sheets without
actually looking at the equipment. It went unnoticed for several weeks, until a particular instrument
was tagged out of service, and the shift manager noticed that the employee had continued to report
normal readings on the instrument. Supervision was not aware of the worker’s deviation from desired
work habits due to lack of interaction.
Section 53
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Provide employee with information on Employee Assistance Program and refer employee.
• Review adequacy of formal supervisory interface with team and workers, focusing on pre/post job briefings and
other team and individual settings.
• Review ability of supervisor to monitor and coach workers through firsthand observations, active listening and
questioning techniques that reinforce expected behaviors and resolve emerging human performance problems.
A4B4C13 - Provided feedback on negative performance but not on positive performance
Definition: Worker's performance adversely affected by supervision's focus on negative performance feedback.
Example: A mechanic frequently performed tasks ahead of schedule, with no safety incursions. His jobs were
always of a high quality. However, his supervisor never reinforced this positive behavior. Because the
mechanic worked 10-hour days, and the supervisor only worked 8 hours, they did not see each other at
the end of the shift. They met in the morning for the pre-job toolbox meeting, and then the mechanic
was essentially ‘on his own’ to complete the day’s tasks. As a result, there was little opportunity for
reinforcement of good behavior at the end of the workday, and in the morning, the focus was always
on the present day’s work, not a recap of the previous day. On one occasion, the mechanic made a
mistake, resulting in a potential safety situation. A critique was held, in which it was determined that
the employee was at fault for the oversight. The employee was given constructive discipline (time off
without pay) for the mistake. After the incident, the employee’s attitude became one of avoiding
punishment, not of earning rewards. As a result of the supervisor’s focus on negative feedback, the
worker’s subsequent job performance was significantly affected.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Review adequacy of supervisory behaviors that cultivate and facilitate excellence in human performance, facilitating
open communications; promoting teamwork to eliminate error-likely situations and strengthen defenses; searching
for eliminating organizational weaknesses that create conditions for error; reinforcing desired jobsite behaviors; and
valuing the prevention of errors.
DOE G 231.1-2 Attachment 7
08-20-03 Page 39
• Review the adequacy of management’s commitment to cultivating people, focusing on supervisory training designed
to provide appropriate interpersonal skills and tools for supervisors.
A4B5C01 -– Problem identification methods did not identify need for change
Definition: Existing problem identification methods did not recognize the difference between actual practices and
expectations.
Example: A site maintained over 2500 active pressure vessels and over 5000 active pressure relief devices. The
Section 54
pressure safety program, administered by the Pressure Equipment Protection Committee (PEPC), was
responsible for the initial and continued adequacy of the site’s pressure equipment. Verification
records were standard site documents used for systematic evaluation to determine the adequacy of
pressure equipment for the intended service application. At the beginning of the year, approximately
25% of the total population of active pressure equipment did not have verification records, with some
equipment having been in service for several years, some dating to the 1950’s. An extensive 1-year
effort was undertaken to complete verification records for all pressure vessels and pressure relief
devices. Major pressure protection inadequacies were discovered during the verification assessment.
The PEPC had been in place for many years; however the original focus was on the structure and
administration of pressure protection activities and not the technical aspects of pressure protection.
Existing problem identification methodologies had not recognized the significant difference between
actual unsatisfactory practices and equipment and corporate safety expectations.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Develop schedule to fix major pressure protection inadequacies.
• Review organization-to-program evaluation process implementation, examining skills and knowledge of analysts
performing evaluations, use of technology-based causal analysis, strength and weaknesses of observation/event
solving teams to identify critical problem areas.
A4B5C02 - Change not implemented in a timely manner
Definition: A change in expectations was not realized in practices within an acceptable time period.
Example: A site maintained over 2500 active pressure vessels and over 5000 active pressure relief devices. At
the beginning of the year, approximately 25% of the total population of active pressure equipment did
not have verification records, with some equipment having been in service for several years, some
dating to the 1950’s.
The corrective action plan involving major physical modifications that included: selection of new and
relocation of existing pressure relief valves, regulators and valves; and resizing and rerouting of piping
configurations. Execution of the modifications was based on the risk associated with the pressure
protection design. Problems were broadly classified as either safety or non-safety concerns with safety
concerns referring to personnel and equipment safety, not nuclear safety. Less than 5% of
overpressure protection problems were categorized as safety concerns. These issues required
immediate action to either resolve the issue or shut down the system. Non-safety problems did not
pose an immediate safety concern and implementation of the corrective actions was handled through a
4-year program. In order to maintain a consistent approach to pressure protection designs, the
development of a detailed and comprehensive pressure protection design guide was prepared. The
guide finally put pressure protection expectations into practice, although the corporate safety
expectations had been reinforced significantly during the past 12 years.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Review management’s implementation of pressure protection regulatory implications.
A4B5C03 - Inadequate vendor support of change
Section 55
Definition: Management failed to adequately assess the ability of vendors to supply products or services in support
of changing expectations for a particular objective.
Attachment 7 DOE G 231.1-2
Page 40 08-20-03
Example: An operator performing routine rounds discovered a leak at a weld on the discharge line of a chemical
process cell vaporizer of a Safety Grade Nitrogen System (SGNS). Subsequent radiographic
examinations indicated that the welds at the inlet and outlet flanges of all 5 SGNS vaporizers (10
welds) did not meet ASME code requirements. The SGNS were procured as Level 2 “non-safety
class” equipment and were upgraded to Level 1 “Safety Class” by the Commercial Grade Dedication
(CGD) process. The “Safety Class” system was leased from the system supplier. The system supplier
obtained the vaporizers (including inlet and outlet flanges and welds) from a vaporizer supplier who
provided documentation that the welds were fabricated to ASME code as required. However, prior to
delivery to the job site, the system supplier had the inlet flanges of the 5 vaporizers and associated
welds replaced to allow proper connection to facility piping. There was no documentation to
substantiate the system supplier modifications was in compliance with ASME code. Management
failed to adequately assess the ability of the system supplier to sustain modified products in support of
the changing expectations when the leased equipment was modified to meet critical criteria of the
CGD package and the procurement specifications, both while in-process and after delivery to the job
site.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Review vendor program and self-verification process, examining inspection and testing activities, sampling plans,
technology-based review and verification processes, and oversight methodologies.
A4B5C04 - Risks / consequences associated with change not adequately reviewed / assessed
Definition: Elements of the process change were not recognized as having adverse impact or increased risk of
adverse impact prior to implementing the change.
Example: New waste regulations promulgated by the program office affected the packaging of all waste products
generated by the facilities. The new requirements involved the characterization of ‘waste streams’,
including isotopic distributions, to assure that the waste storage vaults in areas of the site would not
exceed their permit limits. These requirements created some level of difficulty for process facilities,
which was understood at the time. Program personnel were available to assist the larger operating
facilities. However, due to the complex, variant nature of radioisotopes handled in laboratory
environments and related facilities, the new regulations were virtually impossible for laboratories to
meet. This situation resulted in over two years of waste buildup in the laboratories, while they
struggled to determine waste streams for various laboratory modules and methods. The waste
accumulations resulted in significant housekeeping and safety issues, along with violations of ALARA
principles due to increased material holdup in the working spaces. Some waste streams are at risk of
regulatory violations with state and federal agencies. Elements of the process change were not
recognized as having an adverse impact or increased risk of adverse impact prior to implementing the
change.
Section 56
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Request 12-month exemption to the regulations so waste streams at risk of exceeding the regulations can be
dispositioned.
• Review radioisotope handling procedures in affected laboratory environments and related facilities. Develop
program changes that allow waste stream segregation to comply with new regulations.
• Review implementation of regulatory implications processing, examining the adequacy of the organizational
structure in preparing for new regulations and responding to new regulatory challenges.
A4B5C05 - System interactions not considered
Definition: Changes to processes or physical systems caused interactions with other processes or physical systems
that had were not identified prior to implementation.
Example: A non-safety class piping system was inadvertently routed over safety class electrical equipment. The
designers did not take into account potential system interactions [failure of electrical components]
from rupture of the piping system during a design basis earthquake.
DOE G 231.1-2 Attachment 7
08-20-03 Page 41
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Reroute the affected piping. Include cautions in the appropriate manuals warning of potential interactions.
A4B5C06 – Personnel / department interactions not considered
Definition: Changes to processes created new requirements for interaction between personnel or departments that
were not considered in the implementation phase of the change.
Example: New waste requirements were added to the facility’s workload due to reconfiguration of solid waste
regulations. These new requirements involved verification of proper waste packaging by Generator
Certification Officials (GCOs). While procedures were revised to promulgate the requirement, these
interactions were not woven into the work planning process. As a result, significant job delays were
due to the scheduling organization being unaware of the need to schedule GCO time for any job
requiring waste removal. Changes created new requirements for interaction between personnel and
departments that were not considered in the implementation phase of the change.
Potential Corrective Actions: [these are only examples, it is not an exhaustive list]
• Provide briefing to work planners concerning the new GCO requirements.
• Add GCO to process loop for waste removal activities. Review management’s implementation of regulatory
changes for this case, examining the adequacy of the organizational structure in preparing for new regulations and
responding to new regulatory challenges.
A4B5C07 - Effect of change on schedules not adequately addressed
Definition: Changes to processes that resulted in scheduled changes had effects on personnel or equipment that
were not addressed in the change implementation.
Example: New waste requirements were added to the facility’s workload due to reconfiguration of solid waste
regulations. These new requirements consumed significant man-hours in the identification of waste
streams, training personnel, dealing with rejected waste cuts, and other issues. However, facility
schedules continued to show work duration as though the requirements did not exist. Work
management did not follow-up with waste personnel in determining what effect the change would have
on jobs previously scheduled. As a result, several schedule failures occurred that could have been
avoided by adjusting schedule requirements earlier. Changes to the schedule resulting from the new
waste requirements were not addressed in the change implementation.
Potential Corrective Actions: