S3-DEL-GD1-2023, Redelegation to the Director, Grid Deployment Office
Rescinds:
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
DEPARTMENT OF ENERGY
REDELEGATION ORDER NO. S3-DEL-GD1-2023
TO THE DIRECTOR, GRID DEPLOYMENT OFFICE
1. REDELEGATION. Under the authority vested in me as Under Secretary (for
Infrastructure) and pursuant to section 642 of the Department of Energy Organization
Act (Public Law 95-91, 42 U.S.C. 7252), I delegate to the Director, Grid Deployment
Office authority to take the following actions:
1.1 Under section 643 of the Department of Energy Organization Act (42 U.S.C.
7253), establish, alter, consolidate, or discontinue such second tier or below
organizational units or components within the Director, Grid Deployment
Office’s assigned programs and organizational elements as the Director, Grid
Deployment Office may deem to be necessary or appropriate.
A. In exercising this authority, or as redelegated pursuant thereto, the
Director, Grid Deployment Office will be limited by approved budgets,
staffing level allocations, and Senior Executive Service and other
executive resource position allocations. Organizational changes shall not
be announced or implemented until appropriate union coordination and
other prerelease clearances have been obtained.
B. This authority does not include approval of additions, deletions, or
transfers of mission and functions of or between Departmental
Headquarters or Field Elements, which authority is reserved to the
Secretary.
C. The authority to alter or consolidate second tier or below organizational
elements may be redelegated, in whole or in part consistent with the
terms of the Department of Energy Organization Act, to an official or
officials one level below the Head of the Departmental Element.
D. The authority to establish or discontinue organizational elements at the
second tier or below may not be redelegated.
1.2 Formulate and establish enforcement policy; initiate and conduct investigations;
conduct conferences, administrative hearings, and public hearings; prepare
required reports; issue orders; and take such other action as may be necessary
or appropriate to perform any of the functions in this Redelegation.
1.3 Under section 646(a) of the DOE Organization Act (Public Law 95-91, 42 U.S.C.
7256(a)), enter and perform such contracts, leases, cooperative agreements, or
other similar transactions with public agencies and private organizations and
persons, and to make such payments as deemed necessary or appropriate to
carry out functions delegated to the Director, Grid Deployment Office.
2
1.4 Under the Inflation Reduction Act (IRA), Public Law 117-169:
A. Under Section 50151, administer the Transmission Facility Financing
Program.
B. Under section 50152, administer the Grants to Facilitate the Siting of
Interstate Electricity Transmission Lines Program.
C. Under Section 50153, administer the Interregional and Offshore Wind
Electricity Transmission Planning, Modeling, and Analysis Program.
1.5 Implement section 13 of the Federal Energy Administration Act of 1974 (15
U.S.C. 772), to collect, assemble, evaluate, and analyze energy information and
to exercise all information gathering authorities provided in this section.
1.6 Implement section 11 of the Energy Supply and Environmental Coordination Act
of 1974 (ESECA) (Public Law 93-319, 15 U.S.C. 796), to request, acquire and
collect such energy information as the Director, Grid Deployment Office
determines to be necessary to assist in the formulation of energy policy or to
carry out the purposes of ESECA, and to exercise all energy information reporting
authorities provided in this section.
Section 2
1.7 In reference to fuel use under the Powerplant and Industrial Fuel Use Act (FUA),
(Public Law 95-620, 42 U.S.C. 8301 et seq.) as amended:
A. Monitor compliance with the prohibition against the construction of new
powerplants without the capability to use coal or another alternate fuel
as a primary energy source, pursuant to section 201 of FUA; grant or
deny exemptions from such prohibition, pursuant to sections 211
through 214 of FUA; issue prohibitions against the use of oil or natural
gas to certifying existing electric powerplants under section 301 of FUA;
grant or deny exemptions to certifying existing electric powerplants
under sections 311 through 314 of FUA; and take such other actions as
may be necessary or appropriate to perform any of the above functions
pursuant to section 701 of FUA.
B. Issue notices of effectiveness, modification, or rescission to coal
conversion orders issued pursuant to section 2 of the Energy Supply and
Environmental Coordination Act of 1974 (Public Law 93-319, 15 U.S.C.
791 et seq.), as amended.
1.8 Participate in any proceeding before the Federal Energy Regulatory Commission,
pursuant to the provisions of section 405 of the Department of Energy
Organization Act (42 U.S.C. 7175), or in any proceeding before any Federal or
State agency or commission, whenever such participation is related to the
exercise of authority delegated to the Director, Grid Deployment Office. The
exercise of this authority is subject to the concurrence of the General Counsel.
3
1.9 In reference to electric power regulations under the Federal Power Act (FPA), (16
U.S.C. 791a-825r):
A. Regulate the export of electric energy to a foreign country, pursuant to
the provisions of sections 202(e) and 202(f) of the FPA, and authorize the
construction, operation, maintenance, or connection of facilities, at the
borders of the United States, for the transmission of electric energy
between the United States and a foreign country, pursuant to the
provisions of Executive Order 10485, as amended by Executive Order
12038.
B. Implement section 206(d) of the FPA to investigate and determine, upon
the Director, Grid Deployment Office’s or a delegate's own motion or the
request of any State commission, the cost of production or transmission
of electric energy by means of facilities that are subject to the jurisdiction
defined by section 201 of the FPA, as the Director, Grid Deployment
Office or a delegate determines is necessary or appropriate to perform
his or her functions.
C. Under Section 216(a) (16 U.S.C. 824p(a)), execute all activities necessary
to carry out a study of electric transmission capacity constraints and
congestion and designate national interest electric transmission
corridors.
D. Exercise the authority under section 216(h) of the FPA for the
coordination of Federal authorizations for transmission facilities.
E. Implement section 307 of the FPA to investigate any facts, conditions, or
practices which the Director, Grid Deployment Office or a delegate may
find necessary or proper in order to determine whether any person has
violated or is about to violate any provision of the FPA or any rule,
regulation, or order thereunder; or to aid in the enforcement of the
provisions of the FPA or in prescribing rules or regulations thereunder; or
in obtaining information to serve as a basis for recommending further
legislation concerning the matters to which the FPA relates.
Section 3
F. Implement section 311 of the FPA to conduct investigations regarding the
generation, transmission, distribution, and sale of electric energy,
however produced, throughout the United States and its possessions,
including the generation, transmission, distribution, and sale of electric
energy by any agency, authority, or instrumentality of the United States,
or by any State or municipality or other political subdivision of a State, as
the Director, Grid Deployment Office or a delegate determines is
necessary or appropriate to perform these functions.
4
1.10 Under the Infrastructure Investment and Jobs Act (IIJA) (Public Law 117-58):
A. Pursuant to section 40101 (42 U.S.C. 18711), execute all activities
necessary to carry out the Preventing Outages and Enhancing the
Resilience of the Electric Grid program.
B. Pursuant to section 40106 (42 U.S.C. 18713), execute all activities
necessary to carry out the Transmission Facilitation Program.
C. Pursuant to section 40125(d) (42 U.S.C. 18724(d)), execute all activities
necessary to carry out the Modeling and Assessing Energy Infrastructure
Risk Program.
D. Pursuant to section 40323 (42 U.S.C.A. 18753), execute all activities
necessary to carry out the Civilian Nuclear Credit Program.
1.11 Under the Energy Policy Act of 2005 (Public Law 109):
A. Pursuant to section 242 (42 U.S.C. 15881), as amended by section 40331
of the IIJA, execute all activities necessary to make incentive payments to
qualified owners or operators of hydroelectric facilities.
B. Pursuant to section 243 (42 U.S.C. 15882), as amended by section 40332
of the IIJA, execute all activities necessary to carry out the Hydroelectric
Efficiency Improvement Incentives program.
C. Pursuant to section 247 (42 U.S.C. 15883), as added by section 40333 of
the IIJA, execute all activities necessary to carry out the Maintaining and
Enhancing Hydroelectricity Incentives program.
D. Pursuant to section 936 (42 U.S.C. 16236), execute all activities necessary
to carry out a grid integration research, development, and demonstration
programs in coordination with the Office of Electricity.
1.12 Under the Energy Act of 2020 (Public Law 116-260, Div. Z):
A. Pursuant to section 8006 (42 U.S.C. 16215), consult with entities specified
in section 16215(b)(2) in carrying out the amendments made by Title VIII,
as appropriate under Federal law.
B. Pursuant to section 8011 (42 U.S.C. 17392), execute all activities
necessary to carry out a micro-grid and integrated micro-grid systems
program in coordination with the Office of Electricity.
1.13 Under the Energy Independence and Security Act of 2007 (Public Law 110-140):
A. Pursuant to section 137 (42 U.S.C. 17014), execute all activities necessary
to carry out research, development, and demonstration to advance
5
electric vehicle integration on the electric grid in coordination with the
Office of Electricity.
B. Pursuant to section 1304 (42 U.S.C. 17384), execute all activities
necessary to carry out under a smart grid technology research,
development, and demonstration program in coordination with the
Office of Electricity.
C. Pursuant to Section 1306 (42 U.S.C. 17386), as amended by section 40107
of the IIJA, execute all activities necessary to carry out the Smart Grid
Investment Matching Grant Program and the Deployment of
Technologies to Enhance Grid Flexibility program.
1.14 Under section 988 of the Energy Policy Act of 2005 (Public Law 109-58, codified
at 42 U.S.C. 16352):
Section 4
A. Approve requests for reduction or elimination of the cost sharing
requirement for a research and development activity of an applied nature
in accordance with section 988(b)(3);
B. Approve requests for reduction of the cost sharing requirement for the
non-federal share of demonstration and commercial application activities
in accordance with section 988(c)(2); and
C. Exclude research and development of a basic or fundamental nature from
the cost sharing requirements, as described in section 988(b)(2).
These authorities may not be redelegated and may be exercised only after
providing notification to the Office of the Secretary. Furthermore, the approval
authorities delegated in subparagraphs A and B can be exercised only in
coordination with the Secretarial Policy Statement entitled, “Application of Cost
Share Requirements under Section 988 of Energy Policy Act (EPACT) of 2005,
Pub. L. 109-58.” These authorities may be redelegated solely to Heads of
Departmental Elements reporting directly to the Under Secretary for
Infrastructure.
1.15 Exercise all authorities vested in the Secretary of Energy under the Stevenson-
Wydler Technology Innovation Act of 1980 (Public Law 96-480), as amended by
section 105(a) of the America Creating Opportunities to Meaningfully Promote
Excellence in Technology, Education, and Science Reauthorization Act of 2010
(Public Law 111-358) and section 401(b) of the American Innovation and
Competitiveness Act (Public Law 114-329), as set forth in 15 U.S.C. 3719.
1.16 Under section 644 of the Department of Energy Organization Act (Public Law 95-
91, 42 U.S.C. 7254), prescribe such procedural and administrative rules and
regulations as the Under Secretary for Infrastructure and the Director, Grid
Deployment Office deem necessary or appropriate.
6
2. RESCISSION. Redelegation Order No. S3-DEL-GD1-2022 is hereby rescinded.
3. LIMITATION.
3.1 In exercising the authority delegated in this Order, a delegate shall be governed
by the rules and regulations of the Department of Energy and the policies and
procedures prescribed by the Secretary or delegate(s).
3.2 Nothing in this Order precludes the Secretary or the Under Secretary (for
Infrastructure) from exercising any of the authority delegated by this Order.
3.3 Nothing in this Order shall be construed as to supersede or otherwise interfere
with the authorities provided to the Administrator for Nuclear Security by law or
by delegation. Furthermore, nothing herein constitutes authority to exercise
authority, direction, or control of an employee of the National Nuclear Security
Administration or its contractors.
3.4 Any amendments to this Order shall be made in consultation with the
Department of Energy General Counsel.
4. AUTHORITY TO REDELEGATE.
4.1 Except as expressly prohibited by law, regulation, or this Order, the Director,
Grid Deployment Office may delegate this authority further, in whole or in part.
4.2 Copies of redelegations and any subsequent redelegations shall be provided to
the Office of Management, which manages the Secretarial Delegations of
Authority system.
5. DURATION AND EFFECTIVE DATE.
5.1 All actions pursuant to any authority delegated prior to this Order or pursuant to
any authority delegated by this Order taken prior to and in effect on the date of
this Order are ratified and remain in force as if taken under this Order, unless or
until rescinded, amended or superseded.
5.2 This Redelegation Order is effective _______________.
____________________
Kathleen Hogan
Acting Under Secretary
(for Infrastructure)
April 10, 2023